Water Utility Journal 3: 33-42, 2013. © 2013 E.W. Publications

Flood mitigation at the downstream areas of a transboundary river

C. Papathanasiou1, D. Serbis2 and N. Mamassis3 1 Civil Engineer, PhD candidate, Research associate, Department of Civil Engineering, National Technical University of Athens University of Athens, , e-mail: [email protected] 2 Civil Engineer, PhD candidate, Department of Civil Engineering, National Technical University of Athens University of Athens, Greece, e-mail: [email protected] 3 Assistant Professor, Department of Civil Engineering, National Technical University of Athens University of Athens, Greece, e-mail: [email protected]

Abstract: Floods in the basin of the Ardas river, a transboundary river that has its springs in and its outlet in Greece, have often created havoc and caused millions of damage, especially in downstream Greek areas, which repeatedly receive unregulated flow from upstream dams. More specifically, the Ardas river, a tributary of the river, flows for 241 km in Bulgaria and for only 49 km in Greece and its catchment stretches for 5.200 km2 (94% of the total area) in Bulgaria and for 350 km2 (6% of the total area) in Greece. Three large dams along the river have been constructed in Bulgaria (Kardzhaly, Studen Kladenets and ), the last one, Ivaylovgrad dam, being in short distance (approx. 15 km) from the transnational borders. During heavy rain, excessive flow from Ivaylovgrad dam is often released downstream, in order to relieve the reservoir that is kept at maximum level for energy production reasons. As a result, the downstream areas, also affected by the same heavy rain events, need to regulate large flows, often with inadequate response time and relevant means. The present study describes an approach to estimate flood water levels in the Greek territory, caused by both intense rain events and increased releases from the upstream dam. For this purpose the study area was divided into three sub-basins and the corresponding flood volumes were calculated using several methodologies. Given the fact that downstream areas are proved to be in high risk in terms of flooding, a series of structural and non-structural measures for the downstream area is examined and the paper concludes with an approach towards the confrontation and mitigation of flood effects in transboundary river basins..

Key words: Transboundary river, hydrological analysis, hydraulic analysis, flood extent, flood mitigation, structural and non- structural measures.

1. INTRODUCTION

The Ardas river, a tributary of the river Evros, is a transboundary river that has its sources in Bulgaria and its outlet in Greece. The river springs are located in the north slopes of the Bulgarian . The river flows for 290 km in total before reaching its outlet, out of which 241 km in Bulgarian and 49 km in Greek terrain. The Ardas outlet falls in the Evros river, which is the natural Greek – Turkish border. The basin of the river Ardas stretches for appr. 5.550 km2, out of which 5.200 km2 (or 94%) in Bulgaria and 350 km2 (or 6%) in Greece. During the decade 1950 – 1960 three large dams were constructed in Bulgaria: Kardzhaly (upstream dam), Studen Kladenets and Ivaylovgrad (downstream dam), with a total storage capacity exceeding 1 billion m3. These dams, also referred as hydro power cascade, were mainly constructed for hydropower production purposes and have a total installed capacity equal to 270 MW (106 MW, 60 MW and 104 MW respectively) and a mean annual electricity generation equal to 609 GWh (160 GWh, 244 GWh and 195 GWh respectively) (NEK, 2007). In Greek territory, dam, a hydropower dam with an installed power capacity equal to 2.6 MW serving also irrigation purposes, was constructed in 1969. Flood protection structures in the downstream areas include a natural bank formed just before Komares bridge and several levees constructed along the Ardas river. The structures are adequate only for low intensity flood events, and as a result the area is vulnerable to floods, which are quite frequent. The exact location and the extent of the Ardas river basin are presented in Figure 1.

34 C. Papathanasiou et al.

Figure 1: The river basin of the transboundary Ardas river in Bulgaria and Greece.

To maximize potential hydropower, reservoirs in Bulgarian dams are kept at high levels. As a result, massive water volumes are released from upstream dams to the downstream areas during periods of heavy rainfall. These volumes need to be controlled downstream, often with inadequate response time and relevant means. Therefore, several downstream areas are flooded causing havoc and millions in damaged property and livestock. A methodology was applied for the estimation of flood water levels in Greek areas caused by both intense rainfall events and increased releases from the upstream dam. The results of this estimation are presented in this paper and highlight the need for adoption of appropriate measures for flood mitigation at the downstream areas of the Ardas river. A list of both structural and non- structural measures that could be adopted in the area is compiled, the positive and negative aspects of each measure are commented and an integrated approach to flood mitigation is suggested.

2. METHODOLOGY

The study area includes the area downstream Ivaylovgrad dam extended until the outlet of the basin to the Evros river. Based on topographic features, this area was divided into 3 sub-basins (A, B and C) which are presented in Figure 2, the main characteristics of which are listed in Table 1. Particularly for the hydrographic network, the Shreve classification method (Shreve, 1966) was adopted.

Figure 2: Hydrographic network (a) and altitude map (b) of the study area.

Water Utility Journal 5 (2013) 35

Table 1. Main topographic and hydrographic network characteristics of the 3 sub-basins Total Basin Sub-basins Ivaylovgrad Lochias Ivaylovgrad Dam – Lochias Basin characteristics stream – Dam Lochias stream Evros River – Evros River stream (A) (B) (C) Area (km2) 495.85 154.03 241.95 99.87 Circunference (km) 131.23 68.86 77.49 72.36 Lenght of main watercourse (km) 44.99 18.69 26.30 38.48 Maximum altitude H (m) +537 +534 +265 +567 Altitude of basin inlet (m) +100 +100 +55 +537 Altitude of basin outlet (m) +35 +55 +35 +55 Stream order (by Shreve) 37 22 15 41 Length (km) 44.99 18.69 26.30 38.48

In order to produce design storms for different return periods for the study area Intensity – Duration – Frequency (IDF) curves had to be constructed. Numerous methods exist in order to carry out this analysis (Chow et al., 1988). The Gumbel (Extreme Value Type I) Distribution seems to fit best to extreme events (both floods and droughts) and was considered more appropriate for this analysis. To this end, rainfall datasets were collected from Alexandroupolis station, a meteorological station owned by the Hellenic National Meteorological Service (HNMS) that is closer to the study area. The datasets were properly processed and the resulting properties of the Gumbel distribution are presented in Table 2.

Table 2. Statistical characteristic of rainfall timeseries available for the study area.

Property Value 5 min 10 min 15 min 30 min 1 hr 2 hrs 6 hrs 12 hrs 24 hrs n 15 15 15 15 15 15 15 15 15 Average x 84.72 64.32 52.59 36.76 22.77 14.55 6.89 4.10 2.22 Standard Deviation sx 27.10 26.02 21.10 16.65 8.46 4.33 2.32 1.45 0.88 λ 0.05 0.05 0.06 0.08 0.15 0.30 0.55 0.88 1.46 c 72.53 52.61 43.09 29.27 18.96 12.60 5.85 3.44 1.82

Based on this analysis, IDF curves were produced for different return periods and are presented in Table 3.

Table 3. IDF curves developed for different, specific return periods T IDF curves 2 i = 19.43 * t -0.647 5 i = 26.21 * t-0.649 10 i = 30.69 * t-0.650 20 i = 34.98 * t-0.651 50 i = 40.53 * t-0.651 100 i = 44.69 * t-0.652 200 i = 48.84 * t-0.652 500 i = 54.30 * t-0.652 1000 i = 58.43 * t-0.652

A regression analysis performed for these curves resulted in the development of a general expression for the IDF curves for any return period in the study area (Equation 1).

i = 19.79 * T 0.167 * t–0.651 (1)

36 C. Papathanasiou et al. Two methods were applied for the development of synthetic Unit Hydrographs (UH) for each sub-basin, i.e. the Snyder and the British Hydrological Institution methods. The 1 hour UHs that were produced for both cases are presented in Figure 3.

Figure 3: Snyder (top line) and British Institute (bottom line) unit hydrographs for each sub-basin of the study area.

The Snyder UHs seem to describe more accurately the response of the basin and were finally selected for the construction of the design storm. It is assumed that the design storm follows the second distribution pattern as defined by Huff (Huff, 1970). All necessary information for the hydrological study of the area (including inter alia topographic and other characteristic of the sub-basins, values of parameters for Snyder UHs, the design storms etc.) was collected, properly processed and imported in a widely used hydrological model, HEC- HMS, version 3.5 (USACE, 2010a). The hydrological simulation with HEC-HMS resulted in the generation of discharge timeseries for different design storms at the outlets of all 3 sub-basins. The discharge datasets that were made available during this study were limited to a single timeseries of discharge releases (excessive floods) from Ivaylovgrad dam. These datasets were provided by local authorities and were considered representative of adverse conditions and thus appropriate for the current simulation. In order to estimate flood levels in the area, the outputs of the hydrological model had to be imported in a hydraulic model. Another HEC model was selected as more appropriate for the hydraulic simulation. More specific, hydraulic modelling was performed using the version 4.1 of HEC-RAS model (USACE, 2010b). The exact geometry of the river sections has been measured at 50 m intervals along the river. All necessary datasets were properly processed and imported in HEC-RAS model for the hydraulic simulation that was successfully performed and enabled the drawing of flood lines for rainfall events of a return period equal to T=50 years. Indicative results of the study are presented in the following section. Given the extent to which downstream areas are vulnerable to floods, even for low return periods of floods, a list of structural and non-structural measures for flood mitigation, customized to the particularities and the needs of the study area is proposed.

3. RESULTS

A schematic representation of the study area, including the sub-basins with their reaches, their junctions and the outlet, as developed in HEC-HMS environment, is presented in Figure 4.

Water Utility Journal 5 (2013) 37

Figure 4. A schematic representation of the elements of the study area, as developed in HEC-HMS environment

The hydrological study was performed for two cases. In the first one, the discharge timeseries from the upstream dam were ignored, while in the second one, these datasets were considered in the analysis. Therefore, two sets of results were produced for each sub-basin. The simulated hydrographs for each case at the outlet of the basin and for different return periods are presented in Figures 5 and 6, respectively.

Figure 5. The simulated hydrograph at the outlet of the basin, when releases from Ivaylovgrad dam are ignored.

38 C. Papathanasiou et al.

Figure 6. The simulated hydrograph at the outlet of the basin, when releases from Ivaylovgrad dam are taken into consideration.

In the second case, the flood hydropraph has two peaks, the second, lagged one, being attributed to the peak release from Ivaylovgrad dam. In general, as expected, when releases from the upstream dam are taken into account the flood hydropraph represents a more critical situation. Specifically for the 2-year return period, the contribution of the releases from Ivaylovgrad dam results in an increase in peak flow by appr. 167% and appr. 440% for the first and the second peak, respectively, when compared with the peak flow estimated in case these releases are ignored. Additionally, in the second case, the values of the peak discharges are particularly high, especially for high return periods. It also needs to be highlighted that when return periods exceed 250 years the first peak of the hydrograph is more significant than the second one. Even for medium return periods (close to 50 years) both peaks are particularly high and the combined impact of the two successive peaks, the time distance of which is approximately 6 days, is expected to be significant for the unprotected downstream areas. The peak discharges for every case are summarized in Table 4.

Table 4. Peak discharges for selected return periods, when releases from Ivaylovgrad dam are considered (ALL) and when they are ignored (WITHOUT)

ALL WITHOUT T [years] Qpeak I Qpeak II [m3/s] [m3/s] [m3/s] 2 366,4 743 137,5 50 619,4 743 408,4 100 678,4 743 467,9 250 757,6 743 547,3 500 818 743 607,5

The hydraulic analysis was performed only for the second case considered in the hydrological analysis, i.e. only when discharge timeseries from Ivaylovgrad dam are included (worst case scenario) and only for a return period equal to 50 years, which is the design period for most

Water Utility Journal 5 (2013) 39 technical works. HEC-RAS model that was used for the simulation resulted in specific water levels on the banks of the river. HEC-RAS outputs were transformed to AutoCAD coordinates using a customized routine that was exclusively developed for this purpose. The flood plain was finally projected on a 1:5.000 scale map produced by the Hellenic Military Geographical Service (HMGS). For reasons of clarity, only selected parts of the total flood plain are presented in Figure 7, and more specifically the parts that concern areas that are close to settlements and cultivated land.

Figure 7. The flood plain close to Fylakion, Keramos and Elaia settlements (left) and close to settlement (right), as projected on a map of the area (scale in meters).

As it can be concluded from the analysis, releases from the upstream dam during a flood of T=50 years return period affect significantly both populated and cultivated areas. Of course, the situation becomes even worse in case of greater discharge releases from upstream. As mentioned above, due to the absence of additional datasets, the single discharge timeseries that was available for Ivaylovgrad dam was considered typical and adequate for the current hydrological analysis and the conclusions are based on this assumption.

4. DISCUSSION

The need to manage transboundary rivers is neither new, nor rare, since the majority of neighboring countries, at a global scale, share at least one river (Brochmann and Gleditsch, 2012). It is widely accepted however that in order to reduce flood risk, the management of transboundary rivers should be organized centrally, i.e. at a river basin basis rather than a national basis. This is a fact recognized and particularly highlighted in EU Floods Directive 2007/60/EC. Of course, one should not ignore the difficulties towards such an approach, which include inter alia economic, national security, hydropower, geomorphologic, societal and cultural issues, many of which have been extensively analyzed in the past (Bakker, 2009; El-Swaify and Hurni, 1996). Particularly for this case study, it can be concluded from the analysis that the international river basin cooperation and management between Greece and Bulgaria in what concerns the Ardas discharges and more specifically the releases from Ivaylovgrad dam, should be an issue of priority. It becomes obvious from the analysis that in order to design a strategy of best management practices and measures for flood protection and flood mitigation in the Ardas basin downstream Ivaylovgrad dam, it is critical to take into consideration the discharges released from the upstream dam. For the time being and as concluded from the analysis, the fortification of downstream areas in the Greek territory that are prone to floods, especially the ones that are close to settlements and cultivations, emerges as a necessity. Aiming to mitigate the effects of floods at a planning basis, an approach to

40 C. Papathanasiou et al. flood management that incorporates the adoption of both structural and non-structural measures needs to be developed. A series of relevant structural and non-structural measures that may be undertaken to confront and mitigate flood effects in the study area is presented in Tables 5 and 6, respectively. The measures were appropriately selected, based on literature review (TUHH, 2013; Faisal et al., 1999; Tucci and Villanueva, 1999) and considering the particularities of the study area in terms of geomorphology, hydrometeorology, as well as current land uses in the area. More specifically, five structural and five non-structural measures are examined for the study area. The structural measures include river regulation, sand extraction and the construction of small berms-dams, retention ponds or embankments. The suggested non-structural measures include the development of a program for discharge regulation mutually agreed between neighboring countries, regulations for land uses, flood proofing approaches, development of Early Warning and Flood Forecasting Systems and campaigns for public awareness raising. A more detailed presentation of the main positive and negative aspects of each one of the examined measures is included in Table 5 (for structural measures) and Table 6 (for non-structural measures). In general, it can be concluded from Table 5 that most structural measures are long- lasting solutions, the construction of which may serve additional purposes, other than flood protection exclusively, if designed properly. However, structural measures are usually related to increased construction or maintenance costs and are associated with significant environmental footprint. As far as non-structural measures are concerned and as it can be concluded from Table 6, most of them are environment-friendly and from a certain perspective more robust solutions. On the other hand, non-structural measures are usually inadequate when used alone and a fair amount of time is often required before the accomplishment of desired results. The measures are listed following a decreasing priority order, as this turns out from the evaluation of the land uses and the particular geomorphological and hydrometeorological features of the study area.

Table 5. Positive and negative aspects of examined structural measures Structural measures Measures Positive aspects Negative aspects . Long-lasting solution . Increased construction cost Construction of successive small . The stored water can be recycled and . Significant environmental footprint berms – dams for retention of used also for other purposes (e.g. peak discharge during floods hydropower production, recreational purposes etc.) Construction of retention ponds to . The stored water can be recycled and . Increased construction cost temporarily store flood water in used also for other purposes (e.g. used . Maintenance is necessary reservoirs and release it latter, for recreational purposes etc.) with a time lag . Eco-friendly solution Regulation of the parts of the . Long-lasting solution . Increased construction cost river where the river section is . Low uncertainty in flood protection . Significant environmental footprint inadequate to carry over flood discharges. . Concrete embankments prevent bank . Possible downstream sedimentation Construction of embankments erosion . Impact on biodiversity and natural along the stream to confine . Earth embankments provide habitat for resources stream flow flora and fauna . Enhances the overall hydraulic . Non negligible environmental impact operation of the river . Increased maintenance cost (needs to . The extracted sand could be used as a be performed regularly) Sand extraction at areas of construction material . Environmental Impact Assessment interest studies need to be performed regularly (in accordance to the frequency of applied program for sand extraction)

Water Utility Journal 5 (2013) 41

Table 6. Positive and negative aspects of examined non-structural measures Non-structural measures Measures Positive aspects Negative aspects Development of a program to . Enhances overall mutual understanding . Inadequate when used alone – needs regulate discharge releases from and cooperation between the two to be combined with other measures Ivaylovgrad dam, mutually neighbouring countries . Requires time to be accomplished agreed between Bulgarian and . Measure in agreement to what is Greek relevant authorities foreseen in EU Directive 2007/60/EC . Assist environmental preservation (e.g. . Inadequate when used alone – needs Land use regulations conservation of ecosystems) to be combined with other measures . Requires time to be accomplished Flood proofing (e.g. cleaning of . Prevention of negative impacts on . Inadequate when used alone – needs primary and secondary drainage environment (e.g. spread of pollutants) to be combined with other measures channels prior to the beginning of . Low cost . Short term solution, since the flooding season, removal of maintenance is necessary harmful industrial and agricultural chemicals from flood prone areas) . Can become accessible to stakeholders . Active collaboration between and also the local society (filtered stakeholders and scientists is needed Development of Early Warning information) (SPI) and Flood Forecasting Systems . Permanent facility that allows for real- . Reliable datasets are necessary for an time monitoring through efficient calibration of the system telecommunication and wireless links . Contributes to an overall . Inadequate when used alone – needs environmental awareness to be combined with other measures Campaigns to raise public . Makes the environmental problem a . Requires time to be accomplished awareness on flood risk issues “personal” problem and its solution . Awareness campaigns need to be becomes more urgent frequent

To sum up, in order to confront and efficiently mitigate flood effects in flood prone areas case- specific measures need to be adopted. Different structural and non-structural measures that take into consideration the particularities of the area need to be examined for each case study. Each one of these measures could be applied as an independent measure for flood mitigation. Nevertheless, given that some of these (especially the non-structural ones) are often inadequate when used exclusively, a combination of some of these measures, considering economical, technical, environmental and other criteria, and often involving both structural and nonstructural measures will definitely be more effective. Papathanasiou et al. (2013) suggest a combined application of flood risk management measures both structural and non-structural, each one with case-specific attributed weight, to support an Early Flood Warning System in Attica. Finally, it needs to be stressed that this latter approach, which engages the examination and adoption of a combination of structural and non-structural measures, may not be restricted to flood management of transboundary river basins; it can be expanded to any case where flood managements is required, even within national borders. For transboundary rivers, it should be emphasized that flood management needs to be organized centrally. Therefore, the seamless cooperation between authorities from neighboring countries, should also involve the setting up of an integrated list of appropriate for the area measures (both structural and non-structural) that will be identified by all involved authorities and the co-evaluation of the identified measures, using economical, technical, environmental and other criteria that cross the narrow geographical boundaries. Especially for the Ardas river, the efficient protection of downstream flood prone areas necessitates the fruitful cooperation between the relevant Greek and Bulgarian authorities and the justified adoption of a properly selected combination of structural and non-structural measures, similar to the ones listed in Tables 5 and 6.

42 C. Papathanasiou et al. REFERENCES

Bakker, M. H. N., 2009. Transboundary river floods and institutional capacity. Journal of the American Water Resources Association; 45 (3): 553-566. Brochmann, M. and Gleditsch, N. P., 2012. Shared rivers and conflicts: A consideration. Political Geography; 31 (8): 519-527. Chow, V. T., Maidment, D. R. and Mays, L. W., 1988. Applied Hydrology. USA: Mc-Graw-Hill, Inc. El-Swaify, S. and Hurni, H., 1996. Transboundary effects of soil erosion ad conservation in the Nile Basin. Land Husbandry; 1: 6-21. Faisal, I. M., Kabir, M. R. and Nishat, A., 1999. Non-structural flood mitigation measures for Dhaka City. Urban Water; 1: 145-153. Huff, F. A., 1970. Time distribution characteristics of rainfall rates. Water Resources Research; 6 (2): 447-454. NEK (Natsionalna Elektricheska Kompania EAD), 2007. Hydro Power Cascades and Dams, Republic of Bulgaria. Report produced by NEK EAD; 68 p. (available at www.nek.bg). Papathanasiou, C., Makropoulos, C. and Mimikou, M., 2013. An innovative approach to Floods and Fire Risk Assessment and Management: the FLIRE Project. Proc. 8th International Conference of EWRA "Water Resources Management in an Interdisciplinary and Changing Context", 26th-29th June 2013, Porto, Portugal. Shreve, R. L., 1966. Statistical law of stream numbers. Journal of Geology; 74: 17–37. Technische Universität Hamburg-Harburg (TUHH), 2013. Flood Manager E-Learning, Tutorial on Flood Risk Management, Flood Management Measures (available at: http://daad.wb.tu-harburg.de). Tucci, C. E. M. and Villanueva, A. O. N., 1999. Flood control measures in União da Vitoria and Porto União: structural vs. non- structural measures. Urban Water; 1: 177-182. U.S. Army Corps of Engineers (USACE), 2010a. Hydrologic Modeling System HEC-HMS. User’s Manual; Version 3.5. U.S. Army Corps of Engineers (USACE), 2010b. River Analysis System HEC-RAS. User’s Manual; Version 4.1.