1St Quarter 2020 Page 1 of 52 DPWH CONSTRUCTORS' PERFORMANCE SUMMARY REPORT (ON-GOING / COMPLETED PROJECTS) 1St Quarter CY 2020
Total Page:16
File Type:pdf, Size:1020Kb
DPWH CONSTRUCTORS' PERFORMANCE SUMMARY REPORT (ON-GOING / COMPLETED PROJECTS) 1st Quarter CY 2020 No. of CATEGORY PROJECT CONTRACT DATE FINAL RATING/ No. of NAME OF LICENSE DATE OF NO. OF *IMPL. FUNDING SLIPPAG CPES VISIT Contract L/F STATUS WMS MTL TIME FAC ESH RDR QUALITATIVE REMARKS Project CONSTRUCTOR NO. EVALUATION VISIT AGENCY SOURCE AMOUNT DUR E (%) RATING or PCAB ARC TYPE NAME LOCATION STARTED COMP DESCRIPTION (Php, M) (C.D) Asset Preservation - Preventive 115 CONSTRUCTION & Maintenance - Tertiary Roads - Jct. Galimuyod, Ilocos Sur 2nd 88.5% 1 1 38309 L D SB GE 03/10/2020 Final LF 8.697 134 07/08/2019 11/18/2019 2.24% C 0.453 0.132 0.300 - - - 88.50% AHD DEVELOPMENT Candon - Salcedo - Del Pilar Road, Ilocos Sur DEO Satisfactory K0349+580 - K0350+454 Road Widening on Secondary Roads 2-R CONSTRUCTION AND along Villasis - Malasiqui - San Carlos Malasiqui, Pangasinan 4th 91.38% 2 2 15304 L B MA GE 03/05/2020 Final LF 19.748 150 07/05/2019 12/01/2019 0.00% C 0.483 0.132 0.300 - - - 91.50% ONS SUPPLY Rd., K0190+660 to K0192+018, Pangasinan DEO Very Satisfactory K0192+700 to K0192+729 Improvement of Multi-Purpose Building Quezon City 88.51% 3 3 3FJ CONSTRUCTION 37156 L B SB GB Quezon City 03/10/2020 Final LF 2.965 93 08/27/2019 11/27/2019 0.00% C 0.464 0.133 0.300 - - - 89.70% ONS at Pinyahan Elementary School 2nd DEO Satisfactory San Fernando, Construction of Drainage Structure along 3RB CONSTRUCTION & San Jacinto & Masbate 1st 89.52% 4 4 19541 L B MA GE Road - on Specific Locations along San 03/07/2020 Final LF 29.519 210 07/11/2019 02/05/2020 0.00% C 0.487 0.143 0.300 - - - 93.00% ONS SUPPLY Monreal, DEO Very Satisfactory Fernando North Road (S00009TC) Masbate Misamis 3R'S BUILDERS AND Misamis 89.14% 5 5 35922 L D SB GE Concreting Of Road, Sinacaban Cluster 03/08/2020 Final Occidental 2nd LF 23.401 100 08/22/2019 11/29/2019 1.00% C 0.438 0.133 0.300 - - - 87.10% AHD RESOURCES Occidental Very Satisfactory DEO 5G GALVEZ Road Widening of Catarman- Calbayog Catarman, Northern 93.06% 6 6 CONSTRUCTION AND 34736 L B MA GE Road K0755+585- K0755+775, 03/05/2018 Final LF 29.479 294 11/05/2018 08/25/2019 34.70% C 0.475 0.200 0.300 - - - 97.50% AHD Northern Samar Samar 1st DEO Very Satisfactory SUPPLY K0759+883-K0759+1472 Rehabilitation/Reconstruction/ Upgrading of Damaged Paved Roads along Calapan North Road K0008+600 - Calapan City - 811 TRADING & K009+000, K0011+403 - K0011+493, Puerto Galera, Mindoro 7 7 21215 L A MB GE 03/10/2020 1st LF 53.753 270 07/25/2019 04/19/2020 1.05% OG 0.391 0.240 0.150 0.024 0.061 0.050 91.60% - AHD CONSTRUCTION K0013+935 - K0014+224, K0015+058 - Oriental Oriental DEO K0015+351, K0026+1065 - K0027+311, Mindoro K0050+014 - K0050+644, K0050+985 - K0051+106 85 AQUARIUS BUILDERS Construction of Multi-Purpose Building Davao City 2nd 90.57% 8 8 41653 L D SB GB Davao City 03/12/2020 Final LF 4.705 170 06/29/2019 12/15/2019 16.09% C 0.485 0.134 0.300 - - - 91.90% AHD CORPORATION at Barangay Mintal, Tugbok District DEO Very Satisfactory Rehabilitation/Major Repair of Along Borongan- Eastern Samar 91.8% 9 9 888 ACY ENTERPRISES 32898 L B MA GE Permanent Bridge at Vigan Bridge 03/03/2020 1st LF 29.399 113 06/11/2019 10/01/2019 0.88% C 0.486 0.132 0.300 - - - 91.80% AHD Guiuan Road DEO Very Satisfactory (B00490SM) Construction/Improvement of Access Sulat, Eastern Eastern Samar 10 - 888 ACY ENTERPRISES 32898 L B MA GE Road Leading to Paninihian Island and 03/03/2020 1st LF 41.941 270 07/16/2019 04/10/2020 -2.53% OG 0.373 0.300 0.125 0.030 0.051 0.033 91.20% - DEL Samar DEO Barangitaw Beach Construction of Elementary and 969 CONSTRUCTION & Diadi, Nueva Nueva Vizcaya 93.3% 11 10 35818 L C SB GB Secondary School Buildings at Diadi 03/08/2020 Final LF 5.32 120 09/22/2019 01/19/2020 0.00% C 0.500 0.133 0.300 - - - 93.30% ONS SUPPLIES Vizcaya 1st DEO Very Satisfactory Central School,1STY2CL Convergence and Special Support Program- Construction/Improvement of A. DE GUIA Access Roads Leading to Trades, CONSTRUCTION AND Industries and Economic Zones- Brgy. Isabela 2nd 87.8% 12 11 18228 L AA MB GE Gamu, Isabela 03/04/2020 Final LF 19.584 161 06/17/2019 11/24/2019 0.04% C 0.472 0.133 0.300 - - - 90.50% AHD DEVELOPMENT Upi Road Connecting Rice and Corn DEO Satisfactory CORPORATION Production to National Road Leading to Rice Milling Companies in Support to Agri-Business Industry A. DE GUIA Network Development- Construction of CONSTRUCTION AND By-Pass and Diversion Road- Alicia Isabela 3rd 86.28% 13 - 18228 L AA MB GE Alicia, Isabela 03/06/2019 Final LF 75.36 208 06/27/2019 01/20/2020 67.75% C 0.485 0.133 0.300 - - - 91.80% AHD DEVELOPMENT Bypass Road Incl. ROW and Slope DEO Satisfactory CORPORATION Protection Convergence and Special Support Program - Construction/Improvement of Access Road Leading to Declared Sanches Mira, Cagayan 2nd 90.1% 14 12 A. NIDUAZA BUILDERS 45856 L C SB GE 03/03/2020 Final LF 9.8 145 08/27/2019 01/18/2020 0.00% C 0.401 0.200 0.300 - - - 90.10% ONS Tourism Destinations - Access Road Cagayan DEO Very Satisfactory along Minanga - Namuac Road Leading to Estuary Sand Dunes and Beaches Hernaez Street leading to Murcia Proper and Mambukal Resort, Brgy. A.C. RIVERO Brgy. Mansilingan, Bacolod City, Negros Bacolod City 15 13 DEVELOPMENT 5122 L A MB GE Mansilangan, 03/04/2019 1st LF 86.85 270 08/05/2019 04/30/2020 -0.93% OG 0.367 0.238 0.141 0.030 0.056 0.033 86.50% - DEL Occidental (Construction/Improvement DEO CORPORATION Bacolod City of Access Roads leading to Declared Tourism Destination) Rehabilitation/ Reconstruction of Roads A.C. RIVERO with Slips, Slope Collapse and Landslide 88.9% 16 - DEVELOPMENT 5122 L A MB GE Along Toledo-Tabuelan-San Remegio Cebu 03/08/2020 Final Cebu 3rd DEO LF 14.254 198 07/07/2019 01/20/2020 24.75% C 0.486 0.133 0.300 - - - 91.90% AHD Satisfactory CORPORATION Road, K0071+130-K0071+180, K0071+296-K0071+348 A.C. RIVERO 19IF0058-Construction of Road, Brgy. 92.3% 17 - DEVELOPMENT 5122 L A MB GE Domonar - Brgy. Mabini Road, Palompon, Leyte 03/05/2020 Final Leyte 4th DEO LF 9.384 70 07/04/2019 09/11/2019 21.43% C 0.490 0.133 0.300 - - - 92.30% AHD Very Satisfactory CORPORATION Palompon, Leyte Consolidated in CY 2020 CPES Reports in 1st Quarter 2020 Page 1 of 52 DPWH CONSTRUCTORS' PERFORMANCE SUMMARY REPORT (ON-GOING / COMPLETED PROJECTS) 1st Quarter CY 2020 No. of CATEGORY PROJECT CONTRACT DATE FINAL RATING/ No. of NAME OF LICENSE DATE OF NO. OF *IMPL. FUNDING SLIPPAG CPES VISIT Contract L/F STATUS WMS MTL TIME FAC ESH RDR QUALITATIVE REMARKS Project CONSTRUCTOR NO. EVALUATION VISIT AGENCY SOURCE AMOUNT DUR E (%) RATING or PCAB ARC TYPE NAME LOCATION STARTED COMP DESCRIPTION (Php, M) (C.D) 19IL0066-Buildings and Other Structures - Brgy. San A.C. RIVERO Multipurpose/Facilities - Local Program, Antonio, San Southern Leyte 92.6% 18 - DEVELOPMENT 5122 L A MB GB 03/03/2020 Final LF 3.465 90 06/13/2019 09/10/2019 0.00% C 0.493 0.133 0.300 - - - 92.60% ONS Construction of Multi-Purpose Building, Ricardo, DEO Very Satisfactory CORPORATION Brgy. San Antonio Southern Leyte A.C. RIVERO 19IF0027-Construction of Road, Brgy. Lat- Brgy. Lat-osan, 92.2% 19 - DEVELOPMENT 5122 L A MB GE 03/05/2020 Final Leyte 4th DEO LF 4.7 50 07/04/2019 08/22/2019 2.00% C 0.489 0.133 0.300 - - - 92.20% AHD osan, Palompon, Leyte Palompon, Leyte Very Satisfactory CORPORATION Rehabilitation / Reconstruction / Upgrading Of Damaged Paved Roads Primary Roads, Butuan City Cagayan De A.C. RIVERO Oro City Iligan City Road, Naawan To Naawan to Misamis 95.28% 20 - DEVELOPMENT 5122 L A MB GE Manticao, Misamis Oriental, K1495+346 - Manticao, 03/02/2020 Final Oriental 2nd LF 40.617 208 07/29/2019 02/21/2020 36.76% C 0.451 0.200 0.300 - - - 95.10% AHD Very Satisfactory CORPORATION K1496+100, K1496+399 - K1497+302, Misamis Oriental DEO K1499+695 - K1500+000, K1500+000 - K1500+346, K1500+346-K1500+678, K1500+678-K1500+903 Construction/Maintenance of Flood A.C. RIVERO Brgy. Batobalani, Mitigation Structures and Drainage Camarines 92.28% 21 - DEVELOPMENT 5122 L B MA GE Paracale, 03/06/2020 Final LF 49.000 194 07/08/2019 01/17/2020 5.00% C 0.451 0.200 0.300 - - - 95.10% AHD Systems-Construction of Flood Control Norte DEO Very Satisfactory CORPORATION Camarines Norte Project Construction of Concrete Road including Drainage and Construction of Road Slope A.C. RIVERO Protection Structure - Malubi - Masbate 2nd 91.52% 22 - DEVELOPMENT 5122 L A MB GE Cabangcalan - Dayhagan - Tinigban - Aroroy, Masbate 03/06/2020 Final LF 79.659 216 08/04/2019 03/06/2020 5.00% C 0.470 0.180 0.300 - - - 95.00% AHD DEO Very Satisfactory CORPORATION Mataba Road, Masbate including ROW Acquisition, Net Length = 1.930 lane km.