(PRS of River Amlakhadi)

National Mission for Clean Ganga Monthly Progress Report of State for April -20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in-situ least in-situ remediation remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPs 31.03.2020 Ankleshwar STP (14 MLD):- may be and connecting all the drains and other completed by March-2021 sources of generation of sewage to the STPs must be ensured PRH & RDD was informed to submit the action plan for the sewage generated from the villages (2.75 MLD) 2 Timeline for completing all steps of 31.03.2021 14 MLD STP (Ankleshwar Nagar Palika):- action plans including completion of March -2021 setting up of STPs and their PRH & RDD was informed to submit the commissioning action plan for the sewage generated from the villages 3 Chief Secretaries may set up 22.01.2020 Quarterly RRC meeting held at GPCB, appropriate monitoring mechanism at Gandhinagar to review the progress & State level minutes of the same (having progress • Specifying accountability of status) is regularly submitted to CPCB nodal authorities not below the Secretary Level Reviews of all NGT matters are taken • Chief Secretaries may have an 22.01.2020 frequently under chairmanship of Hon’ble accountable person attached in CS (Last meeting was conducted on their office for this purpose. 24/12/2019) in matter of O.A. No.:- • Monitoring at State level must 606/2018 take place Fortnightly commenci ng 21.12.2019 4 Progress report may be furnished by Monthly Noted & Complied the States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th • Member Secretary, CPCB of every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources including sources including drains drains contributing to river pollution is contributing to river already completed and submitted in the PRS pollution and action as per action plan which is already approved by NGT order on in-situ CPCB w.r.t Priority I and II. treatment In-situ treatment:- Pl. refer point no:-1 (PRS of River Amlakhadi)

(ii) Status of STPs, I&D and Existing infrastructure: 22.5 MLD (only 7.5 sewerage networks MLD capacity is utilized for the sewage Details of existing generated from Notified area) infrastructure, gap analysis, Gap: 10.75 MLD (due to sewage generated proposed along with from Nagarpalika and nearby villages) completion timeline Proposed : 14 MLD Completion Timeline : March-2021 Proposed plan with present status:- • Ankleshwar STP (14 MLD):- may be completed by March-2021

• PRH & RDD was informed to submit the action plan for the sewage generated from the villages (2.75 MLD) (iii) Status of CETPs There is no any direct waste water discharge Details of existing CETP and from any CETP in to Amlakhadi ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure –II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 321 # of HCUs (Health Care management including bio- Units) located in the Ankleshwar taluka, medical wastes, plastic treatment wastes and decentralizing & disposal of Bio Medical Waste of which is waste processing, including being taken care of by a common facility waste generated from M/s, Globe Bio Care located in GIDC hotels, ashrams etc. Ankleshwar Industrial Waste:- In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (PRS of River Amlakhadi)

(vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly. (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III. management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by Forest the river Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

(PRS of River Amlakhadi)

Annexure- I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:

Types of Generat Collection/Sto Disposal/Trea Total Gap Proposed Time Remarks Present Status Waste/ ed rage facility tment facility with action plan limit Characte Quantit with capacity with capacity generation /facility to ristic of y (MT/Day) along with & existing cover gap waste (MT/Da location treatment y) facilities if any Anklesh 23 10 MT/Day dry 13 MT/day 10 MT/day Installing Dec Earlier it was decided by Ankleshwar Notified war waste and 13 kitchen waste MSW 2019 Board of Management of area: For MSW plot no Notified MT/Day disposed to processing Notified Area, GIDC. 9207 admeasuring 14000 Area Kitchen Waste Bio gas plant plant Ankleshwar to give O & SQMT is allotted by MSW of BEIL Of 10 MTD WASTE Capacity M for MSW plot for five GIDC. Kitchen waste of years and for the same housing area is dumped estimate was prepared to BEIL, Ankleshwar. and DPR is almost ready Estimate work for for inviting tender. But development of MSW there is problem with site as per MSW Rules the disposal of existing 2016 is under process dumped solid waste. And and same may approved broadly discussed about and tender of the same this problem and Now will be done in 5 to 6 Board has decided to months. Door to door prepare estimate MSW collected from considering disposal of GIDC area is dumped to existing dumped waste plot no 9207. GIDC, in the plot allotted for Ankleshwar. MSW purpose. So, (PRS of River Amlakhadi)

Earlier the time for tendering work was given up to Dec-2019 but now the same is to be revised and it will be published up to May- 2020. Anklesh 23.54 23.54 14.64 TPD 0 - - Ankleshwar Nagar - war (Wet Waste Palika- MSW collected Nagar being from household of Palika processed at Ankleshwar town is MSW Compost WASTE plant-25 TPD segregated for Amboli road, converting 15 MT of Ankleshwar) inorganic fertilizer and 08.50 TPD plastic waste is used for (Dry Waste making molds. being segregated & sold out to recyclers) 00.40 TPD (Mix Waste to be disposed at dump site) Total 46.54 36.54 -- 10 MT ------(PRS of River Amlakhadi)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality monitoring for the Month April -20:

Sr.no. Location ID Name of Parameter Location DO (mg/l) pH BOD COD Total coliform Fecal coliform (mg/l) (mg/l) (MPN/ 100ml) (MPN/100 ml) 1434 33440 Low Level bridge BDL 7.82 13 79 1400 260

1980 32618 Pungam 1.53 7.76 7 41 280 130

Progress /Status Report for Ground water quality monitoring pertaining to PRS River (April -20):

Location Name of Location Parameter ID pH BOD COD Cu mg/l T.Cr. H.Cr. Fe Pb Mn Ni Zn (mg/l) (mg/l) mg/l mg/l mg/l mg/l mg/l mg/l mg/l 50634 Gujarat Gas Office, 7.83 0.28 5 0.014 BDL BDL 0.301 BDL -- 0.067 0.05 Umervada 50635 Vill. Juna Pungam 7.94 0.40 5 0.013 BDL BDL 0.048 BDL -- 0.050 0.01

Vill. Bhadkodra ------

Vill. Kosmadi ------

Piraman Gram Panchayat ------

Vill. Sakarporbhatha ------(PRS of River Amlakhadi)

Drains details with Flow:

Sr. Location Name of Inletting River/Drain Discharge MLD No. Max Min 1 GIDC Ankleshwar Valia Chokdi Ankleshwar 7.5 3 GIDC STP w/w stream/Ankleshwar GIDC drain* 2 Ankleshwar Station side Ankleshwar Station side drain nr Low level 0.5 0.2 drain bridge 3 Piraman village Domestic w/w stream of Piraman village 0.25 0.1 4 Ankleshwar Nagar Palika Ankleshwar Town drain 6.45 2.01 Oxidation pond overflow 5 Ankleshwar Nagar Palika Juna Diva Drain 0.5 0 Juna Diva 6 Ankleshwar Nagar Palika Surti Bhagor drain 0.05 0 Surti Bhagor drain

(PRS of River Amlakhadi)

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Amlakhadi 1) Environmental flow – NA 2) Details of good irrigation practice- NA 3) Details of flood plain management zone - details mentioned below

(PRS of River Amlakhadi)

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing Proposed plan to Time Remarks plantation/vegetation cover remaining gap limit cover details along river /river stretch Amlakhadi Total plantation / trees -- along Amlakhadi: 8000 The details received from Social Forestry wing, Aranya Bhavan, Gandhinagar are as under Amla kahdi About 11000 trees Target submitted by APCCF for all the Rivers of (Limed to Dadhal) Gujarat is as per attached details in Annexure-A 43.00 Km

(PRS of River Amlakhadi)

Annexure-A

(PRS of River Amlakhadi)

(PRS of River Bhadar)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-2020 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl. Activity to be monitored Timeline Submission of Progress by States/UT- N Compliance Status o. 1 Ensure 100% treatment of sewage at least 31.03.2020 Presently there is no any proposal for in- in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS and 31.03.2020 STP Jetpur - Navagadh Nagarpalika (23.5 connecting all the drains and other sources MLD):- Trial run to be expected by April- of generation of sewage to the STPs must 2020 be ensured 2 Timeline for completing all steps of action 31.03.2021 STP Jetpur - Navagadh Nagarpalika (23.5 plans including completion of setting up of MLD): - Trial run to be expected by April- STPs and their commissioning 2020 CETP: - CETP JDPA (Upgradation) - may be completed Apr- 2020 CETP Dhareshwar (Modification): - work completed. New CETP JDPA: - Dec- 2020 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of nodal minutes of the same (having progress authorities not below the Secretary status) is regularly submitted to CPCB Level • Chief Secretaries may have an 22.01.2020 Reviews of all NGT matters are taken accountable person attached in frequently under chairmanship of Hon’ble their office for this purpose. Fortnightly CS (Last meeting was conducted on • Monitoring at State level must take commencing 24/12/2019) in matter of O.A. No.:- place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: Identification of polluting sources (i) Identification of polluting including drains contributing to river sources including drains pollution is already completed and contributing to river pollution submitted in the PRS action plan which is and action as per NGT order on already approved by CPCB w.r.t Priority I in-situ treatment and II In-situ treatment:- Pl. refer point no:-1 (PRS of River Bhadar)

(ii) Status of STPs, I&D and Existing infrastructure: 6 MLD sewerage networks Gap analysis: 8 MLD Details of existing Proposed: 23.5 MLD infrastructure, gap analysis, Completion Timeline: April-2020 proposed along with Proposed plan with present status:- completion timeline STP:- STP Jetpur - Navagadh Nagarpalika (23.5 MLD):- Trial run to be expected by April- 2020 (iii) Status of CETPs No. of industries and complying status: - Details of existing CETP and ETP Industries: - 1430 Industrial Units are infrastructure, gap analysis, there in Jetpur Ind area & Dhareshwar proposed along with GIDC and 2 CETPs i.e. CETP JDPA (Having completion timeline, no. of domestic & Industrial mixed effluent) & industries and complying status CETP Dhareshwar are there which are disposing final treated effluent for irrigation & plantation. However due to consequences like overflows/broken/choke up /seepage in “C” etc., effluent leads to River Bhadar. CETP Dhareshwar GIDC has upgraded their treatment plant before timeline. To overcome this situation following action are proposed i) CETP JDPA Modification by means of construction of the collection sump: - CETP JDPA has constructed new collection sump for mercerizer units at CETP of JDPA for the conveyance of wastewater through road tankers and progress is going on for other collection sump for printing units. ii) Setting up of New CETP (JDPA-20 MLD) at Derdi, Monpar:- Design and engineering work in progress. Construction work started (Timeline- Dec-2020) iii) Shifting of washing ghats:- Still shifting of washing ghat not done due to treated waste water disposal problems. However, illegal washing Ghats are regularly demolished by joint drive of GPCB, Police dept., Revenue dept. etc. as per High court order iv) CETP Dhareshwar Modification: - work completed v) Deep Sea Disposal Pipeline: - As Permanent Solution to this & to eliminate Industrial Footprint from River Sabarmati and Bhadar, Deep sea disposal pipeline projects for the State (PRS of River Bhadar)

of Gujarat worth Rs. 2147 Cr. have been given approval by State Government.(Detail is attached as Annexure:- V ) (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Jetpur-navagadh Nagarpalika allocated Processing Facilities SWM land fill site, DPR prepared and Details of existing tendering is not done. infrastructure, gap analysis, MRF is installed and operational. proposed along with (timeline as per RAP:- 31/12/2020) completion timeline (v) Latest water quality of polluted 5 (v) Status is attached as Annexure – II river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of waste Bio-Medical Waste:- and scientific waste Total 101 Nos. of Health Care Unit’s are management including bio- operating in Jetpur and generated Bio medical wastes, plastic wastes Medical Waste is disposing their waste in to and decentralizing waste the CBWTF of M/s. Distromed Bio Clean processing, including waste Pvt. Ltd. generated from hotels, Industrial Waste:- ashrams etc. In the State, all Hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and management of attached as Annexure – III Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of the Details w.r.t point no. 5 (xii) given by river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (PRS of River Bhadar)

(xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

(PRS of River Bhadar)

Annexure- I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:

Type of Generated Collection Disposal/ Total gap with Proposed Time Present Waste / Quantity MTPD /Storage Treatment facility generation and action plan/ limit Status Characterist facility with with capacity along existing facility to ic of Waste capacity with location treatment facility cover gap if any MSW @39 Only At present @ 15 @24 MSW and 31/ Jetpur- collection and MTPD MSW recycling MTPD other waste 12/ navagadh Nagarpalika segregation facility throughout dumping site 2020 allocated facility. sourcing agency will be SWM land setup. developed at fill site, DPR Scientifically landfill S.No. 972/3 prepared and site is not developed derdi Road, tendering is Jetpur. not done. MRF is installed and operational. Total @ 39 -- 15 MTPD 24 MTPD ------(PRS of River Bhadar)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality monitoring for the Month April-2020:

Location ID Name of Parameter Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Total coliform (MPN/ Fecal coliform 100ml) (MPN/100 ml) 31211 Dublipat 0 7.80 88 411 ** TC & FC parameters not analyzed due to Renovation work of Rajkot Laboratory

Progress /Status Report for Ground water quality monitoring pertaining to PRS River: Location Sampling BOD COD TDS pH date Bore well of P.K.Patel 02/04/2020 1.7 06 492 7.15

Drains Details with Flow:

Sr. Location Discharge (MLD) No. (Latitude and longitude) Max Min 1 Opp. Bhadar Stone Crusher 1.8 0.2 2 Sarang Nallah 1.1 0.1 3 Behind Gondra area 3 1 4 Behind Kabrastan 4 1.5 5 Near railway bridge 0.4 0.05 6 Maghedi Vokda 3 1 (PRS of River Bhadar)

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Bhadar Data/details will be furnished soon

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/ Existing plantation / vegetation cover Proposed plan to Time Remarks River details cover remaining limit gap along river/river stretch Vegetation Cover is scattered and scanty Target submitted by APCCF for all the covered by Thorny trees with Dry Rivers of Gujarat is as per attached details deciduous vegetation in Annexure-A Bhadar Prosopios juliflora, Azadirachta aindica About 91% is covered with such scartly vegetation.

(PRS of River Bhadar)

Annexure-A

(PRS of River Bhadar)

(PRS of River Bhadar)

Annexure-V

Deep Sea Disposal Pipeline for PRS Gujarat

• An unprecedented initiative, deep sea disposal pipeline projects to eliminate Industrial Footprint from River Sabarmati and Bhadar worth Rs. 2147 Crore as stated below have been given approval by State Government vide GR dated 26/11/2019.: 1. Ahmedabad (Priority I) (300 MLD) (Rs. 1478 Cr.) 2. Jetpur (Priority I) (80 MLD) (Rs. 669 Cr.) • For Ahmedabad, 70% contribution of Capex will be from State Government and 30% from industries. For Jetpur, 80% contribution of Capex will be from State Government and 20% from industries. Opex will be entirely borne by the industries. • State Government has allotted budget of Rs. 500 Cr. for the financial year 2019-2020 for the entire pipeline project. • Industrial Associations have also deposited their first installment of 10 % of project cost towards capital cost contribution. • State Government has allotted pipeline projects to Industries & Mines Department and execution of the project will be done by Gujarat Water Infrastructure Ltd (GWIL) as depository work. • Gujarat Water Infrastructure Ltd (GWIL) has already invited tender for appointing Project management Consultant for execution of the projects. • DPRs are prepared and are under vetting by Gujarat Water Infrastructure Ltd (GWIL).

(PRS of River Bhogavo)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in-situ least in-situ remediation remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 Surendranagar (32.3 MLD STP) - Work and connecting all the drains and other completed (100%) sources of generation of sewage to the Vadhwan 12.1 MLD STP :- Might be STPs must be ensured completed by March-2021 2 Timeline for completing all steps of 31.03.2021 Surendranagar (32.3 MLD STP) - Work action plans including completion of completed (100%) setting up of STPs and their Vadhwan 12.1 MLD STP - Might be commissioning completed by March-2021 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress

nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an 22.01.2020 Reviews of all NGT matters are taken accountable person attached in frequently under chairmanship of Hon’ble their office for this purpose. Fortnightly CS (Last meeting was conducted on • Monitoring at State level must commencing 24/12/2019) in matter of O.A. No.:- take place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources including sources including drains drains contributing to river pollution is contributing to river already completed and submitted in the PRS pollution and action as per action plan which is already approved by NGT order on in-situ CPCB w.r.t Priority I and II treatment In-situ treatment:- Pl. refer point no:-1

(PRS of River Bhogavo)

(ii) Status of STPs, I&D and Existing infrastructure: --- sewerage networks Gap analysis: 15 MLD Details of existing Proposed : 44.4 MLD infrastructure, gap analysis, Completion Timeline : March-2021 proposed along with Proposed plan with present status:- completion timeline Surendranagar (32.3 MLD STP) - Work completed (100%) Wadhwan 12.1 MLD STP - Work could not start due to land problem. It will be sorted out shortly as per the information given by UDD and might be completed by March- 2021 (iii) Status of CETPs Not applicable as there is no any CETP in the Details of existing CETP and region of Surendranagar and there is no ETP infrastructure, gap industrial effluent discharge in the Bhogavo analysis, proposed along river with completion timeline, no. of industries and complying status (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste In Surendranagar region @ 381 HCU are management including bio- registered and all are member of two medical wastes, plastic CBMWTF i.e E coli Waste management Pvt. wastes and decentralizing Ltd, Sanand, Dist. Ahmedabad & Distromed waste processing, including Bio Clean Pvt. Ltd. Kuvadava GIDC, Dist. waste generated from Rajkot and regularly sending their waste hotels, ashrams etc. Industrial Waste:- In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently

(PRS of River Bhogavo)

framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by Forest the river Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

(PRS of River Bhogavo)

Annexure- I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:

Types of Waste/ Generated Collection/ Disposal/ Total Gap with Proposed Time limit Remarks Present Status Characteristic of waste Quantity/ Storage facility with Treatment facility generation & action plan / day capacity with capacity along existing treatment facility to with location facilities if any cover gap Domestic waste from @ 50 MT/ Not provided as per the Solid Waste 50 MT/Day -- NA Vermi compost There is no any Surendranagar Day Management Rules solid waste Municipality (Mixed type) management & Processing Domestic Solid waste @ 10 MT/ Not provided as per the Solid Waste 10 MT/Day -- NA Vermi compost facilities from Vadhwan Day Management Rules provided by the Municipality (Mixed Nagarpalika. Type) Scientific landfill site is not developed by the Nagarpalika

(PRS of River Bhogavo)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality monitoring:

Date Location DO pH BOD (mg/l) COD (mg/l) Fecal Total (mg/l) Coliform coliform (MPN/100 (MPN/100 ml) ml) April D/S of 2.8 7.40 7.63 45 N.A. N.A - Surendranagar 2020 City, Near Wadhvan Bridge

Progress /Status Report for Ground water quality monitoring pertaining to PRS River:

Location of sample collected WATER PROJECT EMP PROGRAM BORE WELL WATER SAMPLE OF M/s BHAVANI PLASTIC GIDC WADHWAN - MONTHLY Sample ID 279015 Date of sample collection 01/04/2020 Parameter Unit Result Arsenic mg/l BDL BOD mg/l 1.7 COD mg/l 6.0 Copper mg/l BDL pH pH units 7.80 TDS mg/l 2380 Iron mg/l 0.128 Lead mg/l BDL Mercury Ppb N.A. Nickel mg/l BDL Zinc mg/l BDL

(PRS of River Bhogavo)

Drain details with flow:-

Total no. of drains = 05

Sr. Location Discharge No. (MLD) Max. Min. 1 Kumbharpara 0.80 0.10 2 Naklangpara 1.00 0.15 3 Near Shradhdha 0.50 0.10 Hotel 4 Nr. Bari Darwaja 0.90 0.15 5 Vadhwan Bridge 0.40 0.05

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Bhogavo Data/details will be furnished soon

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/ Existing plantation / vegetation cover Proposed plan to Time Remarks River details cover remaining limit gap along river/river stretch Vegetation Cover is scattered and scanty Target submitted by APCCF for all the covered by Thorny trees with Dry Rivers of Gujarat is as per attached deciduous vegetation details in Annexure-A Bhogavo Prosopiosjuliflora, Azadirachtaaindica About 91% is covered with such scartly vegetation.

(PRS of River Bhogavo)

Annexure-A

(PRS of River Bhogavo)

(PRS of River Khari)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at least 31.03.2020 Presently there is no any proposal for in-situ remediation in-situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc will be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS and 31.03.2020 Vinzol (35 mld) AMC - Commissioned connecting all the drains and other sources Vinzol (100 mld) AMC- Expected to be of generation of sewage to the STPs must completed by Sep-2020 be ensured 2 Timeline for completing all steps of action 31.03.2021 plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of nodal minutes of the same (having progress authorities not below the Secretary status) is regularly submitted to CPCB Level • Chief Secretaries may have an 22.01.2020 Reviews of all NGT matters are taken accountable person attached in frequently under chairmanship of their office for this purpose. Fortnightly Hon’ble CS (Last meeting was • Monitoring at State level must take commencing conducted on 24/12/2019) in matter of place 21.12.2019 O.A. No.:- 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting sources including drains contributing to Identification of polluting sources river pollution and action as including drains contributing to river per NGT order on in-situ pollution is already completed and treatment submitted in the PRS action plan which is already approved by CPCB w.r.t Priority I and II In-situ treatment:- Pl. refer point no:-1 (PRS of River Khari)

(ii) Status of STPs, I&D and sewerage Existing infrastructure:70 MLD networks Gap analysis: 115 MLD Details of existing Proposed : 135 MLD infrastructure, gap analysis, Completion Timeline:Sep-2020 as proposed along with below completion timeline Proposed plan with present status:- 1) 35 MLD STP – Commissioned and 2) 100 MLD STP – Expected to be completed by Sep-2020 as per the information given by representative during the meeting held with PRS Assessment Team on 04/02/2020 (iii) Status of CETPs Industrial waste water generation Details of existing CETP and ETP from the GIDCs of Naroda, Odhav, infrastructure, gap analysis, Vatva and GVMM are discharging proposed along with their treated waste water from completion timeline, no. of CETPs in to the MEGA Pipeline industries and complying status which is specifically dedicated for conveying of Effluent generated from the estates which ultimately discharging in River Sabarmati. Hence there is no industrial waste water discharge in to River Khari from these industrial estates. (iv) Status of Solid Waste Management 5 (iv) Status is attached as Annexure – I & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of polluted 5 (v) Status is attached as Annexure – II river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of waste and Bio-Medical Waste:- scientific waste management Total 333 Nos. of Health Care Unit’s including bio-medical wastes, are operating in Ahmedabad (East) plastic wastes and decentralizing waste and generated Bio Medical Waste is processing, including waste disposed in to the CBWTF of generated from hotels, − Care Bio Medical Waste ashrams etc. Incinerator, Gandhinagar − E.Coil Waste (PRS of River Khari)

Management System, Ahmedabad − Pollucare Biomedical Management Pvt. Ltd., Ahmedabad − Medicare Environmental Management Pvt. Ltd., Ahmedabad Industrial Waste:- In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), practices (xi) given by Irrigation Dept. as on date (ix) Protection and management of is attached as Annexure – III Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of the Details w.r.t point no. 5 (xii) given by river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii)Setting up biodiversity parks on GBB informed during the meeting held flood plains by removing on 04/02/2020 at GPCB with PRS encroachment Assessment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested (PRS of River Khari) tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

(PRS of River Khari)

Annexure- I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:

Types of Generated Collection/ Disposal/ Treatment Total Gap with Proposed action Time Present Status Waste/ Quantity/ Storage facility facility with capacity generation & existing plan /facility to limit Characteristic Day with capacity along with location treatment facilities if any cover gap of waste (MT/day) (MT/day) Domestic 0.5 10 Sludge hygienisation Generated quantity is Sludge is -- Capacity to hygienise sewage plant at Pirana (100 sent to the Sludge hygeinised at 100 tons of dry sludge TPD) and AMC hygienisation plant at Sludge sewage sludge is gardens Pirana, hence there is hygienisation operationalized and no gap generation at plant and commercial present. marketed to production has farmers/ nurseries commenced. The plant was inaugurated on March 2019. Total 0.5 10 100 TPD ------(PRS of River Khari)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Table: 1 Progress/Status Report of the River/PRS water quality monitoring for April-20

River/PRS Name of Parameter Location DO pH BOD COD Total Fecal coliform (mg/l) (mg/l) (mg/l) coliform (MPN/100 ml) (MPN/ 100ml) Khari Lali village BDL 7.52 106 336 9400 700

Table:-2 Progress /Status Report for Ground water quality monitoring pertaining to PRS River for April-2020

Location Name of Parameter ID Location pH BOD COD Cu Fe Pb Cd Ni Zn T. Cr. (mg/l) (mg/l) mg/l mg/l mg/l mg/l mg/l mg/l 10836 Borewell 7.76 0.61 5 BDL 0.04 BDL BDL BDL BDL BDL of Lali Gram Panchayat

Drain details with flow details:

Total no. of drains = 02

Sr.No. Location Name of Inletting River/Drain Discharge (MLD) Max. Min. 1 Vinzol STP STP discharge of AMC at 185 165 Vinzol in to river Khari through Pipeline 2 Kharicut Canal at Railway Bridge near Vinzol 0.5 0.2 Railway Bridge (PRS of River Khari)

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Khari Data/details will be furnished soon

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/ Existing plantation / vegetation cover Proposed plan to Time Remarks River details cover remaining limit gap along river/river stretch 25,000 Plants were planted along the Target submitted by APCCF for all the Sabarmati and Meshwo river in the areas Rivers of Gujarat is as per attached details Sabarma available under the Vanmahotsav and other in Annexure-A ti, Khari Schemes of the forest Department with the co-operation of local People.

(PRS of River Khari)

Annexure-A

(PRS of River Khari)

(PRS of River Sabarmati)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in-situ least in-situ remediation remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 (i)155 MLD STP:- May-2020 and connecting all the drains and other (ii) STP of Shankar Bhuvan 25 MLD:- March- sources of generation of sewage to the 2020 STPs must be ensured (iii) STP at Dafnala 25 MLD:- Mar-2021 (iv) STP at Kotarpur 60 MLD:- Mar-2021 (v) STP at Koteshwar 60 MLD by AUDA- Timeline not given. RRC instructed AUDA to submit the same with details action plan without any further delay. AUDA has dropped this project due to land issue. 2 Timeline for completing all steps of 31.03.2021 STPs:- action plans including completion of (i)155 MLD STP:- May-2020 setting up of STPs and their (ii) STP of Shankar Bhuvan 25 MLD:- March- commissioning 2020 (iii) STP at Dafnala 25 MLD:- Mar-2021 (iv) STP at Kotarpur 60 MLD:- Mar-2021 STP at Koteshwar 60 MLD by AUDA- Timeline not given. RRC instructed AUDA to submit the same with details action plan without any further delay. AUDA has dropped this project due to land issue. CETPs:- Green Environment Co-Operative So. Ltd., (GECSL)- Expn :16 to 35 MLD (Dec-2020) Naroda Enviro Projects Ltd. (NEPL)- Expn:-:- 3 to 14 MLD (Feb-2020) Odhav Enviro Projects Ltd. (OEPL)- Modification: - Proposed Spray Dryer (Mar-2020). Narol Dyestuff Enviro Society (NDES)- Expn: - up to 0.45 MLD (Mar-2020) Narol Textile Integrated Enviro Management (NTIEM)- Expn :- 100 to 130 MLD (Mar-2020) (PRS of River Sabarmati)

Ahmedabad Hand Screen Printing Association (AHSPA)- New CETP: - (Dec- 2021) 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. CS (Last meeting was conducted on • Monitoring at State level must Fortnightly 24/12/2019) in matter of O.A. No.:- take place commencing 606/2018 21.12.2019 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of Identification of polluting sources including details along with completion timelines drains contributing to river pollution is on: already completed and submitted in the PRS (i) Identification of polluting action plan which is already approved by sources including drains CPCB w.r.to Priority I and II contributing to river In-situ treatment:- Pl. refer point no:-1 pollution and action as per NGT order on in-situ treatment (ii) Status of STPs, I&D and Existing infrastructure: 855 MLD sewerage networks Gap analysis: 25 MLD Details of existing Proposed : 265 MLD as below infrastructure, gap analysis, (i)155 MLD STP, 72% construction proposed along with completed, May-2020. completion timeline (ii) STP of Shankar Bhuvan 25 MLD- Commissioned (iii) STP at Dafnala 25 MLD, Tender stage, Mar-2021 (iv) STP at Kotarpur 60 MLD, Tender stage, Mar-2021 (v) STP of 60 MLD at Koteshwar (AUDA) :- For the treatment of domestic sewage discharges of Bhat, Koteshwar & nearby other area. Timeline not given. RRC instructed AUDA to submit the same with details action plan without any further delay-- AUDA has dropped this project due to land issue (Feb submission). (PRS of River Sabarmati)

(iii) Status of CETPs No. of industries:- 1351. 1066 (CETP Details of existing CETP and ETP member units). Rest 285 (Danilimda- infrastructure, gap analysis, Behrampura) having individual ETPs. 1 proposed along with completion New CETP is also proposed at danilimda timeline, no. of industries and as below. complying status Existing CETPs:- 07 Nos. having Treatment capacity:- 120.88 MLD. Gap in terms of quality of treated effluents is there hence, Up gradation /expansion of CETPs & Deep Sea disposal Pipeline are proposed as below.:- Deep Sea disposal Pipeline:- As permanent Solution to eliminate Industrial Footprint from River Sabarmati and Bhadar, Deep sea disposal pipeline projects for the State of Gujarat worth Rs. 2147 Cr. have been given approval by State Government.(Detail is attached as Annexure:- V)

Proposed New/Expansion/upgradation/Modification of CETP:- CETPs:- 1) New CETP proposed in Danilimda (AHSPA -30 MLD) - Work order issued (Dec-2021) 2) GECSL Expn: 16 to 35 MLD -:- Tendering for civil work completed. (Dec-2020) 3) NEPL Expn:-:- 3 to 14 MLD:- Modification/up gradation work is completed (Feb-2020) 4) OEPL Modification: - Proposed Spray Dryer completed by Mar- 2020. 5) NDES Expn: - up to 0.45 MLD :- Up- gradation of CETP units is in progress.(Mar-2020) 6) NTIEM- Expn :- 100 to 130 MLD - Preliminary survey of present process is completed .(Mar-2020) (PRS of River Sabarmati)

(iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste Total 5083 Nos. of Health Care Unit’s are management including bio- operating in Ahmedabad City and generated medical wastes, plastic Bio Medical Waste is disposed in to the wastes and decentralizing CBWTF of waste processing, including M/s. Care Bio Medical Waste Incinerator, waste generated from Gandhinagar hotels, ashrams etc. M/s. E.Coil Waste Management System, Ahmedabad M/s. Pollucare Biomedical Management Pvt. Ltd., Ahmedabad and M/s. Medicare Environmental Management Pvt. Ltd., Ahmedabad. Industrial Waste:- In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.to point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III management of Flood Plain Zones (FPZ) (PRS of River Sabarmati)

(x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.to point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

(PRS of River Sabarmati)

Annexure- I 5 (iv) Status of Solid Waste Management & Details of Processing Facilities: Types of Generate Collection Disposal/Treatment Total Gap Proposed Action Time limit & Budgetary Present Status Waste/ d /Storage facility with capacity with Plan/Facility to cover provisions Characteristi Quantity/ facility along with location generation & gap c of waste day with existing capacity treatment facilities if any Solid Waste 3500 TPD 3500 TPD 2500 TPD 1000 TPD Work of 2 Nos. Waste Power purchase As per information given from • 1000 TPD Composting to Energy Plants of agreement and Land lease by representative during Residential, • 1000 TPD C & D Waste 1000 TPD each has agreement done by both meeting held on commercial • 100 TPD Plastic waste been started the agencies. 04/02/2020 at GPCB, units of • 400 TPD MRF Plants are expected to Gandhinagar with PRS Ahmedabad commence functioning assessment team before end of 2020. nominated by Ministry of Budgetary provisions:-* Jalshakti , it will be completed by Dec 2020 Domestic 25 m3/day 100 Sludge hygienisation 0 Sludge shall be March 2019 Capacity to hygienise sewage m3/day plant at Pirana (100 hygeinised at Sludge 100 tons of dry sewage sludge TPD) and AMC hygienisation plant sludge plant is gardens and shall be marketed operationalized and to farmers/nurseries commercial production has commenced. The plant was inaugurated on March 2019. * Budgetary Provision: - These plants are on PPP mode and all involved infrastructure shall be developed by agencies. AMC will give the differential amount as per below mentioned rate to GUVNL as approved by Standing Committee resolution. For Mass - Incineration based plant For RDF based plant Rate as per GERC - Rs.7.03 kWh Rate as per GERC - Rs.7.07 kWh Tarrif given by GUVNL - Rs.6.31 kWh Tarrif given by GUVNL - Rs.6.31 kWh AMC will give - Rs. 0.72 kWh AMC will give - Rs. 0.76 kWh

(PRS of River Sabarmati)

Annexure-II 5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river Progress/Status Report of the River/PRS water quality monitoring for April-2020:

Sr River Sabarmati at PH COD BOD DO (mg/I) TC (MPN) FC (MPN) No (mg/I) (mg/I) 1. Kheroj Sample is not collected as no flow observed 2. Mahudi Sample is not collected as no flow observed 3. Chiloda 4. Hansol Bridge 8.12 11 1.2 8.0 120 6.1 5. Railway Bridge 8.27 14 1.9 8.2 150 6.8 6. V N Bridge 7.02 198 57 BDL 330 45 7. Miroli 7.10 96 20 4,26 1700 170 8. Vautha 7.98 63 12 4.37 700 110

Progress /Status Report for Ground water quality monitoring pertaining to PRS River (April-2020):

Sr Bore wells TDS(mg/I) pH BOD(mg/I) COD(mg/I) No 1. Gandhi Ashram, Ahmedabad 8.31 0.66 05 420 2. Jain Temple, Ahmedabad (Half yearly) 8.4 0.87 05 748 3. P T College, Ahmedabad 7.78 0.81 05 964 Pirana Pumping Station, Ahmedabad (Half 4. 7.08 0.82 07 1766 Yearly) 5. Gyaspur Nr.MSW Site, Ahmedabad 7.47 0.51 06 2158 6. Ajmeri Farm, Ahmedabad 7.25 0.52 06 2560 7. Excel Industries, Ahmedabad 7.61 0,69 07 1696 8. UPL Djl, Ahmedabad 7.68 0.75 08 1082 9. Miroli Pumping Station, Ahmedabad 8.04 0.6 06 1056 10. Naklang Mahadev, Ahmedabad 7.97 0.52 04 1206 11. Paldi -Kankaj, Ahmedabad 7.60 0.65 05 1518 12. GIDC Naroda, Ahmedabad 7.82 0.7 05 938 13. GIDC -Vatva, Ahmedabad 7.55 0.49 05 1300 14. GIDC -GVMM, Ahmedabad 7.94 0.58 06 942 15. GIDC -Odhav, Ahmedabad 7.45 0.68 05 1086 (PRS of River Sabarmati)

Narol, Ahmedabad (*closed) 16. - - - -

Drains with flow details: Total No of drains:- 11 Major Drains: • Outfall of old city area, danilimda (D/S of Vasna Barrage) • AMC storm water drain (Danilimda)-30 MLD • Pumping Station 76 MLD (Old Vasna area) • Pumping Station 182 MLD (Old Pirana area) • Outfall of new city area, Vasna ((D/S of Vasna Barrage) • Domestic waste water discharged at Wagha Kotar, Sukhadeshwar Pumping station, Pethapur Nagarpalika, flow-55.3 MLD • Domestic waste water discharged through natural drain nala, Village – Koteshwar, flow- 0.73 MLD • Domestic waste water discharged through through underground pipeline at Bank of River Sabarmati near Indira Bridge, Vill – Bhat, flow- 0.06 MLD • Domestic waste water discharged through underground pipeline at Bank of River Sabarmati near Indira Bridge, Village – Bhat, flow-2.16 MLD • Domestic waste water discharged from outfall of AUDA line, Village Nana Chiloda, flow-0.43 MLD • Domestic waste water discharged from outfall of Village Nana Chiloda, Flow-6.48 MLD (PRS of River Sabarmati)

Annexure-III

Details w.r.to point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Sabarmati Data/details will be furnished soon

Annexure-IV

Details w.r.to point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/ Existing plantation / vegetation cover details Proposed plan to Time Remarks River cover remaining gap limit along river/river stretch 25,000 Plants were planted along the Sabarmati Target submitted by APCCF for all the Rivers of Sabarmati and Meshwo river in the areas available under the Gujarat is as per attached details in Annexure-A , Khari Vanmahotsav and other Schemes of the forest Department with the co-operation of local People.

(PRS of River Sabarmati)

Annexure-A

(PRS of River Sabarmati)

(PRS of River Sabarmati)

Annexure-V

Deep Sea Disposal Pipeline for PRS Gujarat

• An unprecedented initiative, deep sea disposal pipeline projects to eliminate Industrial Footprint from River Sabarmati and Bhadar worth Rs. 2147 Crore as stated below have been given approval by State Government vide GR dated 26/11/2019.: 1. Ahmedabad (Priority I) (300 MLD) (Rs. 1478 Cr.) 2. Jetpur (Priority I) (80 MLD) (Rs. 669 Cr.) • For Ahmedabad, 70% contribution of Capex will be from State Government and 30% from industries. For Jetpur, 80% contribution of Capex will be from State Government and 20% from industries. Opex will be entirely borne by the industries. • State Government has allotted budget of Rs. 500 Cr. for the financial year 2019-2020 for the entire pipeline project. • Industrial Associations have also deposited their first installment of 10 % of project cost towards capital cost contribution. • State Government has allotted pipeline projects to Industries & Mines Department and execution of the project will be done by Gujarat Water Infrastructure Ltd (GWIL) as depository work. • Gujarat Water Infrastructure Ltd (GWIL) has already invited tender for appointing Project management Consultant for execution of the projects. • DPRs are prepared and are under vetting by Gujarat Water Infrastructure Ltd (GWIL).

(PRS of River Vishwamitri)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2021 1. Kapurai (new) (STP + Network):- Dec- and connecting all the drains and other 2020 sources of generation of sewage to the 2.Sayaji garden:- Mar-2021 STPs must be ensured 3. Channi (new-50 MLD) (STP + Network)- 2 Timeline for completing all steps of 31.03.2021 Dec-21 action plans including completion of setting up of STPs and their 4. Atladara (new 24 MLD)- Dec-21 commissioning 5. Tarsali / GIDC (new 20 MLD) (STP + Network):- Dec-21 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress

nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. CS (Last meeting was conducted on • Monitoring at State level must Fortnightly 24/12/2019) in matter of O.A. No.:- take place commencing 606/2018 21.12.2019 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan which is NGT order on in-situ already approved by CPCB w.r.t Priority I treatment and II In-situ treatment:- Pl. refer point no:-1 (PRS of River Vishwamitri)

(ii) Status of STPs, I&D and Existing infrastructure: 354.5 MLD sewerage networks Gap analysis: 114 MLD Details of existing Proposed : 161.5 MLD infrastructure, gap analysis, Completion Timeline: Dec-21 as proposed along with mentioned below: completion timeline STP Present TimeLine Status Kapurai 90% work of Dec- (new 60 STP is 2020 MLD) (STP + completed. Network) Sayaji 4%. Mar- garden (7.5 Engineering 2021 MLD) work is completed Channi (new 5% Dec- 50 MLD) 2021 (STP + Network) Atladara DPR is under Dec- (new 24 progress and 2021 MLD) tender Tarsali / DPR under Dec- GIDC (new preparation. 2021 20 MLD) (STP + Network)

(iii) Status of CETPs There is no direct discharge of Details of existing CETP and industrial effluent into river ETP infrastructure, gap Vishwamitri. analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (PRS of River Vishwamitri)

(vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 2318 # of HCUs (Health management including bio- Care Units) located in the Vadodara. medical wastes, plastic & disposal of Bio Medical Waste of which wastes and decentralizing is being taken care of by a common facility waste processing, including Quantum Environment Engineers having waste generated from capacity of 8 MT/Day. hotels, ashrams etc. Industrial Waste:- In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks Attached as Annexure – V. on flood plains by removing GBB informed during the meeting held on encroachment 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

(PRS of River Vishwamitri)

(PRS of River Vishwamitri)

Annexure- I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:

Types of Waste/ Generated Collection/ Disposal/Treatment facility Total Gap with Proposed action plan Time Characteristic of Quantity Storage facility with with capacity along with generation & existing /facility to cover gap limit waste MT/day capacity location treatment facilities if any MSW Total 1050 100 % Door to Door As mentioned below 0 NA NA Collection • 1050 TPD Waste to Energy Preprocessing plant at R.S.No.346, Makarpura, • Secured Scientific landfill Phase – 1, Capacity 4 lac MT operational since June 2010 at R. S. 346, Makarpura. • 15 TPD Biomethanation Plant Voragmadi, • 5 TPD Biomethanation plant Gajarwadi, • 100 KG OWC at Ratri Bajar & Sayajibag, (OWC : Organic Waste Converter) • 500 KG OWC at Khanderav Market, Akota atithigruh, indrapuri atithi gruh, Nizammpura Atithigruh & 22 Nos. of 100 ltr. Capacity mulching drum at Bulk waste generator & RWA (Residential Welfare Association) • MRF Facility : Atladara : 50 TPD, Near VUDA Office : 20 TPD, Gadheda Market : 10 TPD (MRF : Material Recovery Facility) (Source : VMC)

(PRS of River Vishwamitri)

(PRS of River Vishwamitri)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring:

Sample ID and Sampling Point pH COD BOD DOX FCO TCO Date 279009- RIVER VISHWAMITRI AT ASOD 7.64 4 0.57 6.4 4 47 03/04/2020 279023- RIVER VISHWAMITRI AT KHALIPUR 7.32 50 12 BDL >1600 >1600 03/04/2020

Progress /Status Report for Ground water quality monitoring pertaining to PRS River:

Sample ID and Sampling Point pH COD BOD TDS Date 279496- WATER PROJECT RAP BOREWELL AT 8.08 4 0.46 1328 09/04/2020 HANUMAN TEMPLE ATLADRA 279027- WATER PROJECT RAP BOREWELL AT 7.61 4 0.46 896 03/04/2020 KAMATIBAUG

Drain details with flow:

Sr. No. Location Name of Inletting Drain Flow in MLD 1 Nr. New Sama Bridge Cygnus School – Krishna Party Plot Drain 0.972 2 Parth School Bharwadwas 1.440 3 Behind VUDA Bldg. - 1.500 4 Behind Sayaji Soc. Sayaji Soc.Drain 1.944 (PRS of River Vishwamitri)

5 Bahucharaji Kirti Tower Various Tributaries at different Locations 11.127 6 Bhimnath Bridge Parshuram Bhatta 1.35 7 B/H Jail Court Jail & Court Compund Drain 0.305 8 Nr. Akota Dandia Barzar - 0.00 Bridge 9 Nr. Urmi School Overflow of Sama Lake 2.333 10 Bharwadwas Sama GIPCL Circle Drain 3.840 11 Nr. Narhari Bridge - 2.092 12 Planatorium Various Tributaries at different Locations in Bhukhi 14.959 Kaans 13 Nr.Darshanam (Parshuram Parshuram Bhatta 2.218 nagar Soc.) 14 Nr. Akota Dandia Barzar - 1.037 Bridge 15 B/h. Akota Village Akota Village 0.47 16 Nr. Ratri Bazar VIP road drain 2.312 17 Urmi Bridge Sama Lake Char Rasta 2.197 18 Bharwadwas Kamatipura Area 2.00 19 Opp. Agora Mall Navrachana School – GIPCL Circle 1.128 20 Opp. Ratri Bazar EME Campus 0.00 21 Munjmahuda Bridge Western part of Munjmahuda 8.156 22 Kalali B/H BSUP Kalali Village 1.620 23 B/H Dental Colledge - 1.00 TOTAL 64

(PRS of River Vishwamitri)

Annexure – III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Vishwamitri Data/details will be furnished soon

Annexure – IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing Proposed plan to cover Time limit Remarks plantation/ remaining gap along river vegetation /river stretch cover details Vadodara city limit 80% 20% Year 2022 Target submitted Vishwamitri river by APCCF for all the Rivers of Gujarat is as per attached details in Annexure-A Remarks : Sayajibaug, M.S.U. Campus and Rajmahal (Palace) has a dense green cover along the bank of river vishwamitri. Largely the entire stretch of vishwamitri River is covered with natural vegetation. There is a rich biodivertsity along the river which includes wide variety of flora and fauna.

Stretch/river Existing Proposed plan Time limit Remarks plantation/vegetation to cover cover details remaining gap along river /river stretch Existing sparse vegetation covered by Propopis juliflora Target submitted by APCCF for all the Rivers of Vishwamitri & Caparis aphylla and other Gujarat is as per attached details in Annexure-A shrubs. Source:- Social Forestry wing., Aranya Bhavan, Gandhinagar

(PRS of River Vishwamitri)

Annexure-A

(PRS of River Vishwamitri)

(PRS of River Vishwamitri)

Annexure – V

Biodiversity Park

District/Area Existing Biodiversity Total area of Proposed Time Limit Remarks Name park Name Biodiversity Biodiversity park park Vadodara city Sayajibaug 100 Acre Near Govindnagar 3 Years Vadodara city Vadsar 7.4 Acre ------Source : Parks & Garden Department – VMC Nil Source:- Social Forestry wing., Aranya Bhavan, Gandhinagar

(PRS of River Dhadhar)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April- 20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl. Activity to be monitored Timeline Submission of Progress by States/UT-Compliance No. Status 1 Ensure 100% treatment of sewage at least 31.03.2020 Presently there is no any proposal for in-situ in-situ remediation remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS and 31.03.2021 River Vishwamitri ultimately meets with River connecting all the drains and other Dhadhar in upstream of Village: Kothwada. sources of generation of sewage to the Action plan of River Vishwamitri is already STPs must be ensured approved & is under implementation and details 2 Timeline for completing all steps of action 31.03.2021 are mentioned hereunder in Point-1 to 5: plans including completion of setting up of 1. Kapurai (new) (STP + Network):- Dec-2020 STPs and their commissioning 2.Sayaji garden:- Mar-2021 3. Channi (new-50 MLD) (STP + Network)- Dec-21 4. Atladara (new 24 MLD)- Dec-21 5. Tarsali / GIDC (new 20 MLD) (STP + Network):- Dec-21 6. STP of 5.2 MLD (Karjan)– March 2021 7. PRH & RDD was informed to submit the action plan for the sewage generated from the village Por for 0.36 MLD discharge) 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & minutes of • Specifying accountability of nodal the same (having progress status) is regularly

authorities not below the submitted to CPCB Secretary Level 22.01.2020 • Chief Secretaries may have an Fortnightly Reviews of all NGT matters are taken frequently commencing accountable person attached in under chairmanship of Hon’ble CS (Last meeting their office for this purpose. 21.12.2019 was conducted on 24/12/2019) in matter of O.A. • Monitoring at State level must No.:- 606/2018 take place 4 Progress report may be furnished by the Monthly Noted & to be Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th • Member Secretary, CPCB of every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources including drains sources including drains contributing to river pollution is already contributing to river pollution completed and submitted in the PRS action plan. and action as per NGT order In-situ treatment:- Pl. refer point no:-1 on in-situ treatment

Page 1 of 7

(PRS of River Dhadhar)

(ii) Status of STPs, I&D and Existing infrastructure: 354.5 MLD sewerage networks Gap analysis: 115.66 MLD Details of existing Proposed : 166.7 MLD infrastructure, gap analysis, Completion Timeline: Dec-21 as mentioned proposed along with below completion timeline Proposed Plan with Present Status:- STP Present TimeLine Status Kapurai 90% work of Dec- (new 60 STP is 2020 MLD) (STP + completed. Network) Sayaji 4%. Mar- garden (7.5 Engineering 2021 MLD) work is completed Channi (new 5% Dec- 50 MLD) 2021 (STP + Network) Atladara DPR is under Dec- (new 24 progress and 2021 MLD) tender Tarsali / DPR under Dec- GIDC (new preparation. 2021 20 MLD) (STP + Network) Karjan Tendering Mar- nagarpalika done 2021 (5.2 MLD) pending for approval at GUDC Total 166.7 -- -- MLD

(iii) Status of CETPs There is no direct discharge of industrial Details of existing CETP and effluent in to PRS Dhadhar ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste Not Applicable as the stretch is not meandering Management & Details of through any City / Towns Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline

Page 2 of 7

(PRS of River Dhadhar)

(v) Latest water quality of 5 (v) Status is attached as Annexure – I polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of waste Bio-Medical Waste:- and scientific waste There are total 57 # of HCUs (Health Care Units) management including bio- located in the Karjan and Por & disposal of Bio medical wastes, plastic wastes Medical Waste of which is being taken care of by and decentralizing waste a common facility Samvedna Biomedical waste processing, including waste Incineration. generated from hotels, Industrial Waste:- ashrams etc. In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule- 9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by practices Irrigation Dept. as on date is attached as (ix) Protection and management Annexure – II of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of the Details w.r.t point no. 5 (xii) given by Forest Dept. river /PCCF/ACCF/Concerned as on date is attached as Annexure – III (xiii) Setting up biodiversity parks on GBB informed during the meeting held on flood plains by removing 04/02/2020 at GPCB with PRS Assessment Team encroachment nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 7

(PRS of River Dhadhar)

Annexure-I

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring:

Sample ID and Sampling Point pH COD BOD DOX FC TC Date mg/l mg/l mg/l 279145- WATER PROJECT SAMPLE RIVER DHADHAR AT 7.63 38 6.7 3.8 920 1600 07/04/2020 KOTHWADA

WATER PROJECT RAP RIVER DHADHAR AT 279175- 7.87 8 0.72 6.5 20 94 07/04/2020 VILLAGE PINGALWADA

Progress /Status Report for Ground water quality monitoring pertaining to PRS River:

Sample ID and Sampling Point pH COD BOD TDS Date mg/l mg/l mg/l WATER PROJECT RAP 279341- BOREWELL AT POR GIDC 8.5 4 0.53 1238 08/04/2020 OFFICE

Drain details with flow:

Sr. No. Location Name of Flow in MLD Inletting Drain 1 Downstream of Vishwamitri 409 Pingalwada 2 Upstream of Rangai @ 1.3 Pingalwada 3 Upstream of Natural Kaans @ 0.36 Pingalwada

Annexure – II

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Dhadhar Data/details will be furnished soon

Page 4 of 7

(PRS of River Dhadhar)

Annexure – III

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/APCCF/Concerned as on date

Stretch/river Existing Proposed plan to Time Remarks plantation/vegetation cover cover remaining gap limit details along river /river stretch Existing vegetation covered by Propopis juliflora & Target submitted by APCCF for all the Rivers of Dhadhar Caparis aphylla and other Gujarat is as per attached details in Annexure-A shrubs.

Page 5 of 7

(PRS of River Dhadhar)

Annexure-A

Page 6 of 7

(PRS of River Dhadhar)

Page 7 of 7

(PRS of River Triveni)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 There is no domestic wastewater and connecting all the drains and other discharge in to this stretch sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of 31.03.2021 action plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken 22.01.2020 accountable person attached in frequently under chairmanship of Hon’ble their office for this purpose. CS (Last meeting was conducted on • Monitoring at State level must Fortnightly take place commencing 24/12/2019) in matter of O.A. No.:- 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan. NGT order on insitu In-situ treatment:- Pl. refer point no:-1 treatment

Page 1 of 6

(PRS of River Triveni)

(ii) Status of STPs, I&D and There is no discharge of domestic sewerage networks wastewater into this River stretch Details of existing infrastructure, gap analysis, proposed along with completion timeline (iii) Status of CETPs There is no Industrial effluent Details of existing CETP and discharge in to Triveni Sangam. ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste There is no solid waste disposal in Management & Details of Triveni stretch area. Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – I polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste In Veraval city area, there are 74 nos. management including bio- of Health Care Units are running. medical wastes, plastic Generated BMW is collected and wastes and decentralizing handled by common biomedical waste waste processing, including treatment facility at Girnar Biomedical waste generated from Waste Management Facility, GIDC- II, hotels, ashrams etc. Junagadh.

Industrial Waste:- In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 Page 2 of 6

(PRS of River Triveni)

at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly. (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – II. management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 6

(PRS of River Triveni)

Annexure-I

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring (April -2020): Name of Parameter Location DO pH BOD COD (mg/l) Total coliform Fecal coliform (mg/l) (mg/l) (MPN/ 100ml) (MPN/100 ml) Triveni 6.4 8.44 2.1 10 NA NA Sangam Annexure-II Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Triveni Details to be furnished soon

Annexure-III Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/APCCF/Concerned as on date Stretch/river Existing Proposed plan to Time Remarks plantation/vegetation cover remaining limit cover details gap along river /river stretch The details received from Social Forestry wing, Aranya Bhavan, Gandhinagar are as under Triveni About 11000 trees Target submitted by APCCF for all the Rivers of Gujarat is as per attached details in Annexure-A

Page 4 of 6

(PRS of River Triveni)

Annexure-A

Page 5 of 6

(PRS of River Triveni)

Page 6 of 6

(PRS of River Kolak)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April - 2020 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sr. Activity to be monitored Timeline Submission of Progress by States/UT- No. Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter. Commencement of setting up of STPS 31.03.2020 Gunjan STP proposed by Vapi Notified and connecting all the drains and other Area Authority (10 MLD):- - 2020. sources of generation of sewage to the PRH & RDD was informed to submit the STPs must be ensured action plan for the sewage generated from 2 Timeline for completing all steps of 31.03.2021 the village Chhiri, Chharwada, Salvav & action plans including completion of Balitha (18 MLD) setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. CS (Last meeting was conducted on • Monitoring at State level must 24/12/2019) in matter of O.A. No.:- take place 606/2018 Fortnightly commencing 21.12.2019 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan NGT order on insitu In-situ treatment:- Pl. refer point no:-1 treatment

Page 1 of 10

(PRS of River Kolak)

(ii) Status of STPs, I&D and Existing infrastructure: --- sewerage networks Gap analysis: 26 MLD Details of existing Proposed : 10 MLD infrastructure, gap analysis, Completion Timeline: 2020 proposed along with Proposed Plan and Present Status:- completion timeline I. Gunjan (10 MLD) proposed by Vapi notified area authority to treat the 8 MLD sewage generated from Gunjan, Notified Area. Time line-2020 (Land Issue:- Insufficient land). II. PRH & RDD was informed to submit the action plan for the sewage generated from the village Chhiri, Chharwada, Salvav & Balitha (18 MLD) (iii) Status of CETPs No any industrial effluent is being Details of existing CETP and discharge into the stretch of River Kolak ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 717 # of HCUs (Health Care management including bio- Units), treatment & disposal of Bio medical wastes, plastic Medical Waste of which is being taken wastes and decentralizing care of by a common facility M/s En-Cler waste processing, including Biomedical Waste Treatment Pvt. Ltd waste generated from located in hotels, ashrams etc. Industrial Waste:- In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per Page 2 of 10

(PRS of River Kolak)

consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 Crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 10

(PRS of River Kolak)

Annexure-I

5 (iv ) Status of Solid Waste Management & Details of Processing Facilities

(From Notified Area Authority) Types of Waste/ Generated Collection/ Disposal/Treatment Total Gap with Proposed action plan /facility to Time limit Remarks/Present Characteristic of Quantity/da Storage facility facility with capacity generation & existing cover gap Status waste y with capacity along with location treatment facilities if any Domestic 8.50 MT @3 Lakh MT Composting Method At present @5.50 The Tender for Collection, June - Expected to - 5.50 MT/Day MT/day waste is Sorting and Recovery of waste 2019 complete by Total Area – At Survey/Plot No. converted through and set up material recovery June-2020 3.8 Hectare 4804 to 4807, GIDC composting process. facility under DBFOOM model Vapi (Near TSDF For the Gap of 3.00 as per Rules, Norms and Site, GIDC Vapi) MT/Day the regulation of SWM Rules – 2016 Capacity: 15 MT/Day Total 8.50 MT 5.5 TPD 3.0 TPD 15 TPD -- --

Page 4 of 10

(PRS of River Kolak)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring (April- 2020):

Date Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) 09/04/ River Kolak at N H No. 8, 6.40 8.06 1.00 5.00 21.00 70.00 2020 Morai River Kolak at Pataliya 5.50 7.51 2.00 16.00 1600 >1600 Bridge

Progress/Status Report of the River/PRS ground water quality Monitoring (April - 2020):

Date Location DO (mg/l) pH BOD COD Fecal Coliform Total coliform SS Iron Lead Nickel (mg/l) (mg/l) (MPN/100 ml) (MPN/100 ml) 09/04/2020 Borewell at Koteshwar 4.00 0.149 BDL BDL 4.30 7.12 2.30 7.00 <2 <2 Mahadev Temple, Vatar

Zinc Manganese Nitrite Nitrate Hexavalent Total Percent Ammonical Total Kejeldahl TDS Conductivity Chromium Chromium Sodium Nitrogen Nirtogen

0.123 BDL 0.032 0.245 BDL BDL 12.50 0.29 1.61 214.00 336.70

Page 5 of 10

(PRS of River Kolak)

Drain details with flow:

Sr. Location/Name Name of Discharge No. of Drain Inletting (MLD) River/Drain Max. Min. 1 Bill Khadi 26 10 Morai, Vapi MLD MLD

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr. No River name Details/Status

1 Kolak Details as per below

Page 6 of 10

(PRS of River Kolak)

Page 7 of 10

(PRS of River Kolak)

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing Proposed plan to Time Remarks plantation/vegetation cover remaining limit cover details gap along river /river stretch Kolak(kikarla to Target submitted by APCCF for all the Rivers of Nil salvav) Gujarat is as per attached details in Annexure-A

Page 8 of 10

(PRS of River Kolak)

Annexure-A

Page 9 of 10

(PRS of River Kolak)

Page 10 of 10

(PRS of River Mahi)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl. Activity to be monitored Timeline Submission of Progress by States/UT- No. Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in-situ least in-situ remediation remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 There is no any domestic discharge/outlet in to and connecting all the drains and other this stretch sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of 31.03.2021 action plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & minutes • Specifying accountability of of the same (having progress status) is regularly nodal authorities not below the submitted to CPCB Secretary Level • Chief Secretaries may have an 22.01.2020 Reviews of all NGT matters are taken frequently accountable person attached in Fortnightly under chairmanship of Hon’ble CS (Last meeting commencing their office for this purpose. was conducted on 24/12/2019) in matter of O.A. 21.12.2019 • Monitoring at State level must No.:- 606/2018 take place 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th • Member Secretary, CPCB of every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources including sources including drains drains contributing to river pollution is already contributing to river completed and submitted in the PRS action plan. pollution and action as per In-situ treatment:- Pl. refer point no:-1 NGT order on insitu treatment

Page 1 of 7

(PRS of River Mahi)

(ii) Status of STPs, I&D and Existing infrastructure: --- sewerage networks Gap analysis:--- Details of existing Proposed : --- infrastructure, gap analysis, Completion Timeline : --- proposed along with There is no any domestic discharge/outlet in to completion timeline this stretch (iii) Status of CETPs There is no any industrial or domestic Details of existing CETP and discharge/outlet in River Mahi in this stretch. ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste There is no Nagarpalika area in this stretch of Management & Details of River. Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – I polluted river, its tributaries, As per the CPCB report (Sep-18) based on results drains with flow details and of 2016 & 2017, also Mahi not been fall in any ground water quality in the priority with <3 mg/L BOD and information for catchment of polluted river the same is already submitted to CPCB.

(vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 105 # of HCUs (Health Care management including bio- Units) located in the Thasra Taluka medical wastes, plastic All are members of either M/s. Samvedana wastes and decentralizing BMW Incinerator or M/s. Pollucare Biomedical waste processing, including Management Pvt. Ltd. waste generated from Industrial Waste:- hotels, ashrams etc. In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule- 9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly

Page 2 of 7

(PRS of River Mahi)

(viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) given practices by Irrigation Dept. as on date is attached as (ix) Protection and Annexure – II management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by Forest the river Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment Team encroachment nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 7

(PRS of River Mahi)

Annexure- I

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

• Latest water quality of polluted river

Month Location DO pH BOD COD Fecal Total (mg/l) (mg/l) (mg/l) Coliform coliform (MPN/100 (MPN/100 ml) ml) April 2020 River Mahi at 7.9 7.84 0.38 4 4 46 Sevalia Annexure-II

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Mahi 1. Environmental flow: 300 cusecs 2.Detail of Good lrrigation Practices and Flood Plain Management Zone: Detail given below

Page 4 of 7

(PRS of River Mahi)

Annexure-III

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing plantation/vegetation Proposed plan to Time Remarks cover details cover remaining limit gap along river /river stretch 8,32,000 Plants were planted Target submitted by APCCF for all the Rivers of along the Mahi, Shedhi and Other Gujarat is as per attached details in Annexure-A river in the areas available under Mahi, Shedhi the Vanmahotsav and other Schemes of the forest Department with the co- operation of local People.

Page 5 of 7

(PRS of River Mahi)

Annexure-A

Page 6 of 7

(PRS of River Mahi)

Page 7 of 7

(PRS of River Amravati)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 PRH & RDD was informed to submit the and connecting all the drains and other action plan for the sewage generated from sources of generation of sewage to the the villages Limbet, Hirapor, Sangpur, STPs must be ensured Pardi, Piprod, and Dadhal for 1.36 MLD 2 Timeline for completing all steps of 31.03.2021 discharge action plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. Fortnightly CS (Last meeting was conducted on • Monitoring at State level must commencing 24/12/2019) in matter of O.A. No.:- take place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan. NGT order on insitu In-situ treatment:- Pl. refer point no:-1 treatment (ii) Status of STPs, I&D and Existing infrastructure: -- sewerage networks Gap analysis: 1.36 MLD (from the Villages) Details of existing Proposed : -- infrastructure, gap analysis, Completion Timeline : -- proposed along with PRH & RDD was informed to submit the completion timeline action plan for the sewage generated from Page 1 of 8

(PRS of River Amravati)

the villages Limbet, Hirapor, Sangpur, Pardi, Piprod, and Dadhal for 1.36 MLD discharge

(iii) Status of CETPs There is no Industries in the vicinity of Details of existing CETP and River Amravati and there is no discharge ETP infrastructure, gap of industrial effluent in to Amravati river analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste Data not available Letter issued to concern Management & Details of authorities Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – I polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 321 # of HCUs (Health Care management including bio- Units) located in the Ankleshwar taluka, medical wastes, plastic treatment & disposal of Bio Medical wastes and decentralizing Waste of which is being taken care of by a waste processing, including common facility M/s, Globe Bio Care waste generated from located in GIDC Ankleshwar. hotels, ashrams etc. Industrial Waste:- In the State, all hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be Page 2 of 8

(PRS of River Amravati)

submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – II management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 8

(PRS of River Amravati)

Annexure –I (Amravati)

Progress/Status Report of the River/PRS water quality Monitoring (April-2020):-

Sr.no. Location ID Name of Location Parameter DO (mg/l) pH BOD (mg/l) COD Total coliform Fecal coliform (mg/l) (MPN/ 100ml) (MPN/100 ml) 1 43527 At village Dadhal 6.47 7.58 0.88 6 130 49

Progress /Status Report for Ground water quality monitoring pertaining to PRS River (April-2020):-

Location Name of Location Parameter ID pH BOD COD Cu T.Cr. H.Cr. Fe mg/l Pb Mn Ni Zn (mg/l) (mg/l) mg/l mg/l mg/l mg/l mg/l mg/l mg/l 50637 Jitali Water works 7.65 0.35 5 0.020 BDL BDL 0.041 BDL --- 0.147 0.030

Page 4 of 8

(PRS of River Amravati)

Drain details with flow:

Sr. Location Name of Inletting River/Drain Discharge *(Cusec) No Max Min 1 Limbet Gram Domestic w/w drain pipe line 0.1878 0.1 Panchayat- Ta. outlet in to River Amravati Jhagadia

2 HiraporGram Domestic w/w drain pipe line 0.2120 0.1 Panchayat- Ta. outlet in to River Amravati Valia

3 Sangpur Gram Domestic w/w drain pipe line 0.2884 0.2 Panchayat- Ta. outlet in to River Amravati Ankleshwar

4 Pardi Domestic w/w drain pipe line 0.0633 0.03 (Pardi-Piplod outlet of Pardi in to River Group Gram Amravati Panchayat)- Ta. Ankleshwar 5 Piprod Domestic w/w drain pipe line 0.0656 0.03 (Pardi-Piplod outlet of Piprod in to River Group Gram Amravati Panchayat)- Ta. Ankleshwar 6 Avadar Gram Domestic w/w drain pipe line 0.1440 0.1 Panchayat- Ta. outlet in to River Amravati Ankleshwar 7. Dadhal Gram Domestic w/w drain pipe line 0.3991 0.4 Panchayat- Ta. outlet in to River Amravati Ankleshwar

Page 5 of 8

(PRS of River Amravati)

Annexure-II

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Amravati Data/details will be furnished soon

Annexure-III

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing Proposed plan to Time limit Remarks plantation/vegetation cover remaining cover details gap along river /river stretch Amravati (Dadhal Target submitted by APCCF for all the Rivers of to Ankleshwar) 1200 trees Gujarat is as per attached details in Annexure-A 8.00 Km Source:- Social Forestry Wing, Aranya Bhavan, Gandhinagar

Page 6 of 8

(PRS of River Amravati)

Annexure-A

Page 7 of 8

(PRS of River Amravati)

Page 8 of 8

(PRS of River Damanganga)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April - 20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sr. Activity to be monitored Timeline Submission of Progress by States/UT- No. Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in-situ least in-situ remediation remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 Vapi Namdha (14 MLD) – Dec –2020 and connecting all the drains and other Vapi Chandor (29.53 MLD) - May-2021 sources of generation of sewage to the Vapi Notified Area Authority (5 MLD) – Sep - STPs must be ensured 2021 2 Timeline for completing all steps of 31.03.2021 STPs:- action plans including completion of Vapi Namdha (14 MLD) – Dec –2020 setting up of STPs and their Vapi Chandor (29.53 MLD) - May-2021 commissioning Vapi Notified Area Authority (5 MLD) – Sep - 2021 CETPs:- CETP Vapi (VGEL) - Expansion 55 to 70 MLD. Dec-2019 (Timeline already due, EC awaited however, CETP is meeting with the norms) 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & minutes • Specifying accountability of of the same (having progress status) is regularly

nodal authorities not below the submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble CS their office for this purpose. Fortnightly (Last meeting was conducted on 24/12/2019) in • Monitoring at State level must commenci matter of O.A. No.:- 606/2018 take place ng 21.12.2019 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th • Member Secretary, CPCB of every month)

Page 1 of 11

(PRS of River Damanganga)

5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources including sources including drains drains contributing to river pollution is already contributing to river completed and submitted in the PRS action pollution and action as per plan. NGT order on insitu In-situ treatment:- Pl. refer point no:-1 treatment (ii) Status of STPs, I&D and Existing infrastructure: --- sewerage networks Gap analysis: 20.5 MLD Details of existing Proposed : 48.53 MLD infrastructure, gap analysis, Completion Timeline: December 2021 proposed along with Proposed Plan with Present Status:- completion timeline Vapi Namdha (14 MLD) - Work in Progress. 25 % completed. Expected to complete by Sep – 2020 Vapi Chandor (29.53 MLD) - Land proposal at revenue level. Tender invited. Expected to complete by May-2021 Vapi Notified Area Authority (5 MLD) - Design to be finalized. Expected to complete by Sep - 2021 (iii) Status of CETPs GIDC Vapi Estate located at Bank of River Details of existing CETP and Damanganga. 519 Nos. of units having ETP infrastructure, gap discharge into CETP Vapi (55 MLD). At present analysis, proposed along CETP meeting with the norms. with completion timeline, Existing CETP/ETP:- no. of industries and • CETP VGEL-55 MLD complying status • M/s. GHCL, Sarigam-2.5 MLD. Meeting with the Norms Proposed Expansion with Status:-VGEL - Proposed Expansion 55 to 70 MLD. EC awaited. VGEL proposed to complete their up gradation up to March – 2020. Time line is already due but CETP at present meeting with norms. (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline

Page 2 of 11

(PRS of River Damanganga)

(v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 717 # of HCUs (Health Care management including bio- Units), treatment & disposal of Bio Medical medical wastes, plastic Waste of which is being taken care of by a wastes and decentralizing common facility M/s En-Cler Biomedical waste processing, including Waste Treatment Pvt. Ltd located in Surat waste generated from Industrial Waste:- hotels, ashrams etc. In the State, all Hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) given practices by Irrigation Dept. as on date is attached as (ix) Protection and Annexure – III management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by Forest the river Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP. Page 3 of 11

(PRS of River Damanganga)

Annexure-I

5 (iv ) Status of Solid Waste Management & Details of Processing Facilities (From Notified Area Authority) Types of Generated Collection/ Disposal/ Total Gap with Proposed action plan Time Remarks/ Waste/ Quantity/day Storage facility Treatment facility generation & existing /facility to cover gap limit Present Characteri with capacity with capacity along treatment facilities if Status stic of with location any waste Domestic 8.50 MT @3 Lakh MT Composting Method Gap of 3.00 MT/Day The Tender for June - Expected to - 5.50 MT/Day Collection, Sorting and 2019 complete by Total Area – At Survey/Plot No. Recovery of waste and June-2020 3.8 Hectare 4804 to 4807, GIDC set up material Vapi (Near TSDF recovery facility under Site, GIDC Vapi) DBFOOM model as per Rules, Norms and regulation of SWM Rules – 2016 Capacity:- 15 MT/Day Total 8.50 TPD 5.5 TPD 3 TPD ------

(From Nagarpalika Vapi)

Types of Waste/ Generated Collection/ Disposal/ Total Gap with Proposed action Time Present Status Characteristic of Quantity/ Storage facility Treatment facility generation & existing plan /facility to limit waste day with capacity with capacity along treatment facilities if cover gap with location any

Page 4 of 11

(PRS of River Damanganga)

Domestic 50 MT/D Vermi Compost – 3 Total Gap is 34.9 Tendering for Dec- At present Capacity: 4 – 5 MT/Day, TPD. solid waste 2019 Vapi has Lakh MT. Organic Fertilizers - management for Vermi Compost – 3 100 Kg/Day, 100 TPD with O MT/Day, Total Area: Material Recovery and M for 9 years Organic 31472 Sq. Facility – 12 MT/Day has been done Fertilizer – Meter. At Village Namdha and same has 100 Kg/Day, Survey No. 113 to been floated in Material 116. new paper on Recovery 18/1/2019 Facility – 12 MT/Day hence

Now for 34.9 MT/Day Gap Nagarpalika has work tender is on agreement stage. Vapi Nagarpalika has proposed to work completion upto July – 2021. Total 50 TPD 15.1 TPD 34.9 TPD ------

Page 5 of 11

(PRS of River Damanganga)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring: April - 2020

Date Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) 09/04/ GIDC Vapi Weir 7.00 7.13 1.50 5.00 17 46 2020 09/04/ Zari Causeway Kachigam 4.90 7.57 2.70 28.00 280 920 2020 09/04/ Village Namdha 5.20 7.04 2.40 18.00 170 540 2020

Progress/Status Report of the River/PRS ground water quality Monitoring: April - 2020

Date Location DO pH BOD COD Fecal Coliform Total coliform SS Iron Lead Nickel (mg/l) (mg/l) (mg/l) (MPN/100 ml) (MPN/100 ml) 09/04/2020 Borewell at Jilla Panchayat School, Kanta 6.00 0.165 BDL BDL 4.30 6.68 2.40 7.00 <2 <2 Faliya, Village Namdha

Zinc Manganese Nitrite Nitrate Hexavalent Total Percent NH3 Total Kejeldahl TDS Conductivity Chromium Chromium Sodium Nirtogen

0.162 BDL 0.016 0.184 BDL BDL 10.80 0.29 1.61 354.00 565.00

Page 6 of 11

(PRS of River Damanganga)

Drain details with flow:

Sr.No. Location/Name of Name of Inletting River/Drain Discharge (MLD) Drain Max. Min. 1 Zari Causeway Kalkada Khadi (Domestic 20 MLD 18 MLD Kachigaon Bridge, outfall from Vapi Nagarpalika Daman (UT) Area) 2 Domestic outfall from Village 0.5 0.3 Near GIDC Weir, Vapi Chanod Area MLD MLD

Page 7 of 11

(PRS of River Damanganga)

Annexure-III Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date Sr.No River name Details/Status

1 Damanganga Details mentioned as below

Page 8 of 11

(PRS of River Damanganga)

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing Proposed plan to Time Remarks plantation/vegetation cover cover remaining limit details gap along river /river stretch Damanganga Target submitted by APCCF for all the Rivers of Gujarat 8 ha. Plantation (kachigaon to Vapi) is as per attached details in Annexure-A

Page 9 of 11

(PRS of River Damanganga)

Annexure-A

Page 10 of 11

(PRS of River Damanganga)

Page 11 of 11

(PRS of River Shedhi)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl. Activity to be monitored Timeline Submission of Progress by States/UT- No. Compliance Status 1 Ensure 100% treatment of sewage at least 31.03.2020 Presently there is no any proposal for in-situ in-situ remediation remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS and 31.03.2020 Kheda STP (5.2 MLD) - Feb-2021 connecting all the drains and other Underground drainage Project for Nadiad sources of generation of sewage to the Nagarpalika - Feb-2021 STPs must be ensured 2 Timeline for completing all steps of action 31.03.2021 • Kheda STP (5.2 MLD) GWSSB- Expected plans including completion of setting up of to be commissioned by Feb-2021 STPs and their commissioning • Underground drainage Project for Nadiad Nagarpalika - Feb-2021

• ETP:- Mafatlal Industries Limited Upgradation – RRC asked to submit the proposal of modification to achieve River discharge norms / ZLD. Unit has submitted letter dated 20/01/2020 regarding permission of Nadiad Nagarpalika to continue discharge of treated wastewater to inlet of STP via drainage line. • CETP Nadiad (0.5 MLD) - Dec-2020 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of nodal minutes of the same (having progress

authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. Fortnightly CS (Last meeting was conducted on • Monitoring at State level must commencing 24/12/2019) in matter of O.A. No.:- take place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied. States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th • Member Secretary, CPCB of every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources including sources including drains drains contributing to river pollution is contributing to river pollution already completed and submitted in the PRS and action as per NGT order action plan. on insitu treatment In-situ treatment:- Pl. refer point no:-1

Page 1 of 9

(PRS of River Shedhi)

(ii) Status of STPs, I&D and Existing infrastructure: 52 MLD (Spare sewerage networks capacity):- Details of existing Gap analysis: 8.2 MLD infrastructure, gap analysis, Proposed : 5.2 MLD proposed along with Completion Timeline : Feb-2021 completion timeline Proposed Plan and Present Status:- I. Kheda STP (5.2 mld):- Feb-2021 Primary line out work in progress. Work order issued. DILR demarcation to be done. II. Underground drainage Project - Feb-2021 Nadiad Nagarpalika has STP of adequate capacity. Underground drainage Project Phase I is completed. Work order is issued dated 17/01/2020 by GUDC for Underground drainage Project Phase II under AMRUT. (iii) Status of CETPs No of Industries:- GIDC Nadiad has 21 no. Details of existing CETP and of industries ( 13 discharging units having ETP infrastructure, gap captive ETP while rest 8 are zero discharge) analysis, proposed along with M/s. Mafatlal Industries Limited (5 MLD):- completion timeline, no. of ETP Upgradation – RRC asked to submit the industries and complying proposal of modification to achieve River status discharge norms / ZLD Unit has submitted letter dated 20/01/2020 regarding permission of Nadiad Nagarpalika to continue discharge of treated wastewater to inlet of STP via drainage line. Proposed CETP & Status:- CETP Nadiad 0.5 MLD .Timeline:- Dec-2020 (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of waste Bio-Medical Waste:- and scientific waste There are total 232 # of HCUs (Health Care management including bio- Units) located in the Nadiad and Kheda medical wastes, plastic wastes taluka, treatment & disposal of Bio Medical and decentralizing waste processing, including waste Waste of which is being taken care of by a generated from hotels, common facility M/s. Samvedana BMW ashrams etc. Incinerator or M/s. Pollucare Biomedical Management Pvt. Ltd.

Page 2 of 9

(PRS of River Shedhi)

Industrial Waste:- In the State, all Hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and management attached as Annexure – III of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of the Details w.r.t point no. 5 (xii) given by Forest river Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 9

(PRS of River Shedhi)

Annexure- I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:

Types of Generated Collection/ Disposal/ Total Gap Proposed Time Respons Present Status Waste/ Quantity/ day Storage facility Treatment facility with action plan limit ible Characteristic with capacity with capacity along generation & /facility to agency of waste with location existing cover gap treatment facilities if any Domestic 85 TPD 70 TPD 45 Ton 25 TPD 25 Tone 1 Nadiad SLF site - MRF Wastage will be Year Nagar Proposed to be 15 Ton Pit treat by on site palika carried out in cluster level by composting waste concerned composting authority. machines Present status of Domestic (Dry 6 TPD 6 TPD Iyavapura dumping 6 TPD Action Plan 31- Kheda SLF - Nil Waste + Site At-Kheda Under Planning 4- Nagar Identification of Wet Waste) Not scientifically 2019 palika land – 6 months developed Design and construction – 6 months Commissioning of SLF – 1 year (31/03/2022) Total 91 TPD 76 TPD 31 TPD ------

Page 4 of 9

(PRS of River Shedhi)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

• Latest water quality of polluted river

Month Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) Apr 2020 River Shedhi at 6.1 8.18 1.7 21 140 350 Kheda Matar Bridge At Nadiad - 6.7 7.72 1.2 12 110 430 Mahemdabad Bridge • Latest ground water quality in the catchment of polluted River Shedhi

Month Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) April 2020 (Half Borewell Nadiad Not Applicable 7.73 0.61 8 <2 <2 yearly) GIDC Water Works

• Drain details with flow:

Sr.No. Location Name of Inletting Discharge (MLD) River/Drain Max. Min. 1 Nadiad Natural Drain 34 28 2 Kheda Natural drain 0.020 0.010

Page 5 of 9

(PRS of River Shedhi)

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Shedhi Environmental Flow:- River is not a perennial river Detail of good irrigation practices:- Detail attached below Details on flood plain management zone:- Detail attached below

Page 6 of 9

(PRS of River Shedhi)

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing Proposed plan to cover Time Remarks plantation/vegetation cover remaining gap along limit details river /river stretch 8,32,000 Plants were planted Target submitted by APCCF for all the Rivers of along the Mahi, Shedhi and Gujarat is as per attached details in Annexure-A Other river in the areas available under the Mahi, Shedhi Vanmahotsav and other Schemes of the forest Department with the co- operation of local People.

Page 7 of 9

(PRS of River Shedhi)

Annexure-A

Page 8 of 9

(PRS of River Shedhi)

Page 9 of 9

(PRS of River Tapi)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 Signapore (155 MLD) – Expansion. Dec- and connecting all the drains and other 2020 sources of generation of sewage to the Gavier (53 MLD) – Expansion. March-2021 STPs must be ensured Bhatar (162 MLD) – Expansion. March- 2 Timeline for completing all steps of 31.03.2021 2021 action plans including completion of Bhesan (100 MLD) – Expansion. June- 2020 setting up of STPs and their STPs under Tapi Suddhikaran Yojana (Total commissioning 37 STPs by SUDA and GWSSB) –Feb-22 to Dec-22 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. CS (Last meeting was conducted on • Monitoring at State level must 24/12/2019) in matter of O.A. No.:- take place 606/2018 Fortnightly commencing 21.12.2019 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan.. NGT order on insitu In-situ treatment:- Pl. refer point no:-1

Page 1 of 16

(PRS of River Tapi)

treatment (ii) Status of STPs, I&D and Existing infrastructure: 470 MLD sewerage networks Gap analysis: 370.15 MLD Details of existing Proposed : 564.99 MLD infrastructure, gap analysis, Completion Timeline: December 2022 proposed along with Proposed STPs and present status:- completion timeline • Signapore (155 MLD) – Upgradation & expansion.50% completed. Work in Progress. Expected to complete by Dec- 2020 • Gavier (53 MLD) - Network is under process. Expected to complete by March-2021 • Bhatar (162 MLD) – Expansion. 50% completed.Work in Progress. Expected to complete by March- 2021 • Bhesan (100 MLD) - Expansion. 80% completed. Work in Progress. Expected to complete by June- 2020 • STPs under Tapi Suddhikaran Yojana (Total 37 STPs by SUDA and GWSSB) – Proposed. Tender to be invited subject to land possession issues. Expected to complete by Feb-22 to Dec-22 (Please refer Annexure V for details). • In last video conference meeting, CS has intimated to concerned dept. to resolve the issues (iii) Status of CETPs No Industrial wastewater discharge Details of existing CETP and into this river stretch ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline

Page 2 of 16

(PRS of River Tapi)

(v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 3683 # of HCUs (Health management including bio- Care Units), treatment & disposal of Bio medical wastes, plastic Medical Waste of which is being taken wastes and decentralizing care of by a common facility M/s, Globe waste processing, including Bio Care and En-Cler Biomedical Waste waste generated from Treatment Pvt. Ltd located in Surat hotels, ashrams etc. Industrial Waste:- In the State, all Hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the Page 3 of 16

(PRS of River Tapi) development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 4 of 16

(PRS of River Tapi)

Annexure-I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities

Types of Waste/ Generated Collection/Storage Disposal/Treatment Total Gap with Proposed action plan Time limit Remarks/Present Status Characteristic of Quantity/day facility with capacity facility with capacity generation & /facility to cover gap waste along with location existing treatment facilities if any Wet waste 800 TPD 100% collection and • 50 TPD bio methanation 40 TPD SMC has formulated 12 month Surat Municipal transportation facility is at APMC market policy of Decentralized Corporation has in place • 700 TPD composting at waste processing facility municipal waste Khajod Disposal site i.e. OWC, 50 to 100% disposal site at subsidy is being provided • 10 TPD decentralized Khajod which is in plants for onsite for such kind of Facility. operation treatment 7 nos of 10 TPD decentralized processing plants have been planned. Dry Waste 500 TPD 100% collection and • 500 TPD RDF unit at 80 TPD 12 -18 transportation facility is Khajod disposal site months in place • 20 TPD Plastic Plastic waste 100 TPD treatment unit at SMC has planned to Bhatar expand the processing • 300 TPD C&D treatment capacity in next 12-18 C&D waste 300 TPD unit at months • 100 TPD Textile - cloth Plant is under tendering cutting waste 100 TPD stage at SMC level. (Chindi waste) Total 1800 TPD 1680 TPD 120 TPD ------

Page 5 of 16

(PRS of River Tapi)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring:

Date Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) 07-04-20 Kathor, N.H. 8 7.12 7.10 0.82 08 9 41 07-04-20 Varachha Bridge 7.05 7.11 0.92 09 6 39 05-04-20 ONGC Bridge 6.92 7.51 1.21 22 6 53 07-04-20 7.07 7.13 0.96 12 6 41 05-04-20 Swamivivekanand 6.79 7.25 1.85 22 6 41 Bridge 05-04-20 Sardar Bridge 6.82 7.16 1.27 20 9 41 05-04-20 Umara Temple 6.54 7.44 1.49 - 9 41

Progress/Status Report of the River/PRS ground water quality Monitoring:

Name of Location Date BOD DOX FCO FLU MAG NH3 pH SS SUP T.H TCO TDS TKN TMP

BORE WELL OF April- , 0.77 7.03 9 0.14 24.32 0.56 7.27 8 42 220 41 670 1.12 25 2020 TA.MANDVI BORE WELL OF SHREE SAI ASHA April- 0.91 7.01 11 0.35 51.07 0.56 7.32 8 90 380 64 1910 1.12 29 PETROL 2020 PUMP(IOC),

Page 6 of 16

(PRS of River Tapi)

Drain details with flow:

Sr.No. Location/Name of Drain Discharge (MLD) Average Outside SUDA - L 1 Koliwad 0.12 2 Rataniya 0.09 3 Tarsada 0.47 4 Village near Tarsada 2.44 5 Mori 0.07 6 Bhamaiya 0.08 7 Vaghechha 0.16 8 Timba 0.40 9 Machhi 0.10 10 Dhatva 0.20 11 Dungra 0.45 12 Kholeshwar 0.21 SUDA-L 13 6.58 14 Kholwad 4.58 15 Vav 14.37 16 Laskana 4.75 17 Koli Bharthana 3.84 18 Valak Creek 43.24 19 Varachha Creek 51.72 20 Jat Bharthana 5.19 21 Pasodara 4.09 22 Sevni 4.98 SMC-L 23 Kotar-7 75 24 Kotar-9 5 25 Makkai Bridge 9 26 Sardar Bridge 11 27 Umra Drain 7 28 Dimple Row House 5 29 Rundh Jakatnaka 2 Outside SUDA – R 30 Mandvi 22.28

Page 7 of 16

(PRS of River Tapi)

31 Gamtalav Bujrang 0.23 32 Ushkhed khurd 0.07 33 Puna gam 0.26 34 Unn -kosadi 0.21 35 Nandpore 1.23 36 Kharoli 1.07 37 Kevadiya - Vadod 0.20 38 0.88 39 Nogama 1.30 40 Karjan 0.46 41 Virpore 0.20 42 Limodara 0.67 43 Dhoran Pardi 12.31 44 Khanjroli 0.14 45 Ghala 0.66 SUDA – R 46 Kathor 13.56 47 Bharthana 17.29 SMC – R 48 Swaminarayan Temple 7.5 49 Pal Jakatnaka 12.5 50 Pal-Halpativas 15

Page 8 of 16

(PRS of River Tapi)

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Tapi Details mentioned as below

Page 9 of 16

(PRS of River Tapi)

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

The details received from Social Forestry wing, Aranya Bhavan, Gandhinagar are as under Stretch/river Existing Proposed plan to cover Time limit Remarks plantation/vegetation remaining gap along cover details river/river stretch Tapi 5,10,035 sq.mt 1,50,000 sq.mt 24 months at Katargam Water Works Tapi River 2350 trees (Source:- Social Target submitted by APCCF for all the Rivers of Gujarat is as (khadod to surat) Forestry wing, Aranya per attached details in Annexure-A Bhavan)

Page 10 of 16

(PRS of River Tapi)

Annexure-A

Page 11 of 16

(PRS of River Tapi)

Page 12 of 16

(PRS of River Tapi)

Annexure-V

Break up of STPs proposed in Tapi Suddhikaran Yojana

River Proposed (P) STPs, Present Status Timeline Expected Remarks capacity (%) given in time line RAP Tapi Bharthana SPS 1 at Tender to be February February- Land is finalised, Detail engineering is started TPS-83 (22.7 mld) invited subject -2022 2022 but possession is yet to be received. SUDA give SUDA to land consent letter to collectorate to submit 10 % possession (0%) cost of land for advance possession vide letter dtd 23/12/2019 Kamrej- Dungra Tender to be February February- Other parcel of land to be neemed in lieu of (0.67 mld) SUDA invited subject -2022 2022* GAUCHAR land by GoG. Proposal is sent by to land Collectorate to revenue department, GoG on possession 14/10/2019 Kamrej- Kholeshwar Tender to be February February- Land is finalised, Detail engineering is started (0.33 mld) SUDA invited subject -2022 2022* but possession is yet to be received. Hon. to land Collector shri Instructed mamlatdar to check possession land is whether GAUCHAR or GOVERNMENT on 25/11/2019. Kamrej- Kamrej 1 Detail February February- Land Possession received , (18.5 mld) SUDA Engineering -2022 2022* stated. Kamrej- Valak creek Work in Decemb Decembe Land Possession received (43.24 mld) SUDA Progress er-2021 r-2021*

Kamrej- Vav- 1 Tender to be February February- Land is already NEEM for “Smashangruh” Hon. (16.09 mld) SUDA invited subject -2022 2022* Collector shri will visit site to land possession Kamrej- Laskana Tender to be February February- Other parcel of land to be neemed in lieu of (5.17 mld) SUDA invited subject -2022 2022* GAUCHAR land by GoG. Proposal is sent by to land Collectorate to revenue department, GoG on possession 14/10/2019 Kamrej – Tender to be February February- Other parcel of land to be neemed in lieu of Kolibharthana (4.3 invited subject -2022 2022* GAUCHAR land by GoG. Proposal is sent by mld) SUDA to land Collectorate to revenue department, GoG on possession 14/10/2019 Kamrej- Varachha Work in Decemb Decembe Land Possession received Creek (51.72 mld) Progress er-2021 r-2021* SUDA

Page 13 of 16

(PRS of River Tapi)

Kamrej- Pasodara Tender to be February February- Other parcel of land to be neemed in lieu of (4.15 mld) SUDA invited subject -2022 2022* GAUCHAR land by GoG. Proposal is sent by to land Collectorate to revenue department, GoG on possession 14/10/2019 Kamrej- Karjan (1 Tender to be February February- Other parcel of land to be neemed in lieu of mld) SUDA invited subject -2022 2022* GAUCHAR land by GoG. Proposal is sent by to land Collectorate to revenue department, GoGon possession 25/10/2019 Kamrej- Dhoran Tender to be February February- SUDA put up proposal to Irrigation Department Creek (1.18 mld) invited subject -2022 2022* SUDA to land possession Kamrej- Dhoran Tender to be February February- Other parcel of land to be neemed in lieu of Pardi-2 (12.5 mld) invited subject -2022 2022* GAUCHAR land by GoG. Proposal is sent by SUDA to land Collectorate to revenue department, GoG on possession 14/10/2019 Kamrej- Kathor (16 Tender to be February February- Land is finalised, Detail engineering is started mld) SUDA invited subject -2022 2022* but possession is yet to be received from DDO to land shri. possession Kamrej- DPR under February February- Land acquisition proposal is with Revenue JatBharthana (5.22 approval -2022 2022 Department dtd.14/10/2019. Compliance asked mld) GWSSB from Collector Surat dated.24/12/20219

Kamrej- Ghala (1.4 mld) GWSSB

Kamrej- Datva (0.34 February February- Land acquisition proposal is with Revenue mld) GWSSB -2022 2022 Department dtd.25/10/2019. Compliance asked from Collector Surat dated.24/12/20219 Kamrej- Sevni (5.18 Decemb Decembe Land acquisition proposal is with Revenue mld) GWSSB er-2022 r-2022 Department dtd. 14/10/2019. Compliance asked from Collector Surat dated. 24/12/20219 Mandvi- Koliwad DPR under Decemb Decembe Land acquisition proposal is with Collector, Rataniya (0.41 mld) preparation er-2022 r-2022 Surat GWSSB Mandvi- Khanjroli DPR under Decemb Decembe Land acquisition proposal is with Collector,Surat (0.21 mld) GWSSB approval er-2022 r-2022

Bardoli- Mori (0.15 Decemb Decembe Land acquisition proposal is with Collector, mld) GWSSB er-2022 r-2022 Surat Land is not Available as per requirement. So Land acquisition proposal is sent to Mamlatdar for scrutiny as on dt.25/11/2019

Page 14 of 16

(PRS of River Tapi)

Mandvi- Unn DPR under Decemb Decembe Land acquisition proposal is with Collector, Kosadi (0.29 mld) preparation er-2022 r-2022 Surat GWSSB

Mandvi- Patna DPR under Decemb Decembe Land acquisition proposal is with Collector, Creek(0.35 mld) preparation er-2022 r-2022 Surat GWSSB

Mandvi- Tarsada DPR under Decemb Decembe Land acquisition proposal is with Collector, (0.82 mld) GWSSB approval er-2022 r-2022 Surat

Bardoli – Kadod DPR under Decemb Decembe Land acquisition proposal is with Collector, Creek (3.5 mld) preparation er-2022 r-2022 Surat GWSSB

Bardoli- Bhamaiya DPR under Decemb Decembe Land acquisition proposal is with Collector, (0.17 mld) GWSSB approval er-2022 r-2022 Surat

Bardoli- Vaghecha Decemb Decembe Land acquisition proposal is with Collector, (0.28 mld) GWSSB er-2022 r-2022 Surat

Kamrej- Timba Decemb Decembe Land acquisition proposal is with Collector, (0.75 mld) GWSSB er-2022 r-2022 Surat

Kamrej- Maachi Decemb Decembe Land acquisition proposal is with Collector, (0.16 mld) GWSSB er-2022 r-2022 Surat

Mandvi- Mandvi DPR under Decemb Decembe Land available (25 mld) GWSSB preparation er-2022 r-2022

Mandvi- Puna Gam Decemb Decembe Land acquisition proposal is with Collector, (0.36 mld) GWSSB er-2022 r-2022 Surat Scrutiny is necessary for Site situation for land allocation in favour of Panchayat Mandvi- Kamlapore Decemb Decembe Land acquisition proposal is with Collector, Creek (1.9 mld) er-2022 r-2022 Surat GWSSB

Page 15 of 16

(PRS of River Tapi)

Mandvi- Vareli Decemb Decembe Land acquisition proposal is with Collector, Kudashi (2 mld) er-2022 r-2022 Surat GWSSB Mandvi- Bodhan Decemb Decembe Land acquisition proposal is with Collector, Creek (2.2 mld) er-2022 r-2022 Surat GWSSB Mandvi- Uskhed Decemb Decembe Common land for both STPs. Land acquisition Khurd (0.11 mld) er-2022 r-2022 proposal is with Collector, Surat GWSSB Mandvi- Gamtalav Decemb Decembe Bujrang (0.34 mld) er-2022 r-2022 GWSSB Mandvi- Bodhan Decemb Decembe Proposal under preparation Village (1.3 mld) er-2022 r-2022 GWSSB * Timeline given as per DPR sanctioned by NRCP.

Note:- • A meeting was held under the chairmanship of The Chief Secretary, Gujarat for policy level decisions of Pollution Abatement And Conservation Of River Tapi At 85 Km Stretch From Kakarapar Barrage To ONGC Bridge, Surat Project at Chief Secretary’s office dated 24/01/2020 in which following matters were brought forward: • Operation and Maintenance shall be done by GWSSB for a specific duration of 7 years and funds arrangement for the same shall be done by Panchayat Department • After completion of Project as Deposit works, project has to be handed over to Gram Panchayat. • Non Core items like River Front Garden Development, Vermi-Compost, River Quality Monitoring System etc. shall not be implemented by GWSSB in Rural Areas of Surat.SMC/SUDA shall decide implementation of the same. • Mandvi STP tender is included in SJMMSVY and Administrative Approval is accorded for the same. The same is also included in above project.

• Secretary (Water Supply) and Chairman, GWSSB informed the estimated project cost varies with respect to the original sanctioned cost by NRCD. • For 17 villages, DPR cost was RS 115 crore (without O&M). Now revised cost : Capital cost-99.65 Cr & 7 yr O&M cost -71.79 Cr . Total cost - Rs 171 crore (with 7 year O&M) • Presently only sewage interception and treatment are considered for villages near creek. It won’t be technically feasible to collect sewage from open drains as storm water and other solid waste may also enter in creek. • Each creek receives sewage from more than 5 villages so 26 more villages will have to be planned with complete UGD system and STP with 7 years O&M. • Thus tentative project cost for additional villages may be around Rs.146 crore .Total revised tentative project cost may be around Rs.320 crore

Page 16 of 16

(PRS of River Anas)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 I. 13.70 MLD of STP of Dahod and connecting all the drains and other Nagarpalika – Oct 2020 sources of generation of sewage to the II. 4.60 MLD of STP of Zalod STPs must be ensured Nagarpalika – Oct-2020 2 Timeline for completing all steps of 31.03.2021 action plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. Fortnightly CS (Last meeting was conducted on • Monitoring at State level must commencing 24/12/2019) in matter of O.A. No.:- take place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan. NGT order on insitu In-situ treatment:- Pl. refer point no:-1 treatment

Page 1 of 8

(PRS of River Anas)

(ii) Status of STPs, I&D and Existing infrastructure: --- sewerage networks Gap analysis: 12 MLD Details of existing Proposed : 18.3 MLD infrastructure, gap analysis, Completion Timeline : Oct, 2020 proposed along with Proposed STPs and present status:- completion timeline Given by RO

I. 13.70 MLD of STP (Dahod Nagarpalika):- work in progress. May be completed by October - 2020 II. 4.60 MLD of STP (Zalod Nagarpalika):- work in progress. Time line for completion:- Oct - 2020 (iii) Status of CETPs No Industrial effluent discharge in the Details of existing CETP and identified stretch of River Anas ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 364 # of HCUs (Health Care management including bio- Units) located in the Dahod and Zalod medical wastes, plastic Taluka:- Bio-medical waste of HCUs in wastes and decentralizing Dahod and Zalod Taluka is disposed at waste processing, including Common Bio-medical waste management waste generated from facility namely Samvedana Biomedical hotels, ashrams etc. waste Incinerator facility, Plot No. 217/1, Chandrapura Industrial Estate, Halol Dist. Panchmahals. Industrial Waste:- In the State, all hazardous waste

Page 2 of 8

(PRS of River Anas)

generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 8

(PRS of River Anas)

Annexure- I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:

Types of Waste/ Generated Collection/ Disposal/ Total Gap with Proposed action plan / Time Remarks Characteristic of Quantity/ Storage facility Treatment generation & facility to cover gap limit waste Day with capacity facility with existing treatment (MT/Day) capacity along facilities if any with location Municipal Solid 50 Collection -- At present there is MSW Processing Facility Feb 2020 Proposed project of Waste (Dahod) System and no solid waste of 60 MT/day capacity is (as submitted Solid Waste Dumping site treatment facility. proposed at S.No. by processing is at provided 50 MT/Day 315/P, Vill. Pushari Municipality) Tender Process Project Cost of Rs. 52.76 Stage. Crore with Capex and MRF & Processing Opex for five years. facility made operational at Dahod Nagarpalika Municipal Solid 10 Collection system -- At present there is MSW Processing Facility August 2020 Proposed project of Waste (Zhalod) and Dumping Site no solid waste of 1000 kg/hr (about 20 (as submitted Solid Waste provided. treatment facility. MT/day) is proposed by processing is at DPR 10 MT/Day with Project cost of Rs. Municipality) Stage. 1.91 Crores at S.No. MRF facility made 784/1. At operational at Jhalod Vill.Kakradungra, Nagarpalika

Total 60 -- -- 80 MT/day -- --

Page 4 of 8

(PRS of River Anas)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring (April– 2020):

Sampling Point Type BOD COD DO FCO pH TCO TDS

RIVER ANAS AT LIMADI (ZALOD) ROU 0.43 4 7.8 14 8.3 79 240 - KUSHALGADH ROAD, VILL. CHAKALIYA, DIST. DAHOD.

Progress /Status Report for Ground water quality monitoring pertaining to PRS River (April– 2020):

Sampling Point Type BOD COD DO FCO pH TCO TDS

HAND PUMP OPP. M/S STAR ROU 0.44 4 2.9 <2 6.8 <2 796 REDIATOR, CHAKALIYA ROAD, GIDC, DAHOD, DIST. DAHOD WELL AT HINDU ROU 0.40 4 2.5 <2 7.7 <2 426 DHARAMASHALA, STATION ROAD, DAHOD

Drain details with flow:

Sr.No. Location Name of Discharge (MLD) Inletting Max. Min. River/Drain 1 Mandavav Bridge, River Khan -- -- Mandavav - Dhamarada Road, Dahod. 2 Kharasana Bridge, River -- -- Zalod – Machhananala Thunthikankachiya Road, Dist. Dahod. (Zalod)

Page 5 of 8

(PRS of River Anas)

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Anas Data/details will be furnished soon

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing plantation/vegetation Proposed plan to cover Time Remarks cover details remaining gap along river limit /river stretch Existing vegetation covered by Target submitted by APCCF for all the Rivers of Anas Propopis juliflora & caparis Gujarat is as per attached details in Annexure-A aphylla, other shrubs.

Page 6 of 8

(PRS of River Anas)

Annexure-A

Page 7 of 8

(PRS of River Anas)

Page 8 of 8

(PRS of River Baleshwar Khadi)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in-situ least in-situ remediation remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 PRH & RDD was informed to submit the action and connecting all the drains and other plan for the sewage generated from the villages sources of generation of sewage to the (Baleshwar, Samrod & nearby) STPs must be ensured 2 Timeline for completing all steps of 31.03.2021 • PRH & RDD was informed to submit the action plans including completion of action plan for the sewage generated setting up of STPs and their from the villages (Baleshwar, Samrod & commissioning nearby) • Up gradation of GETPL-2021 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & minutes • Specifying accountability of of the same (having progress status) is regularly

nodal authorities not below the submitted to CPCB Secretary Level • Chief Secretaries may have an 22.01.2020 Reviews of all NGT matters are taken frequently accountable person attached in Fortnightly under chairmanship of Hon’ble CS (Last meeting their office for this purpose. commencin was conducted on 24/12/2019) in matter of O.A. • Monitoring at State level must g No.:- 606/2018 take place 21.12.2019 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th • Member Secretary, CPCB of every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources including sources including drains drains contributing to river pollution is already contributing to river completed and submitted in the PRS action plan. pollution and action as per In-situ treatment:- Pl. refer point no:-1 NGT order on insitu treatment

Page 1 of 8

(PRS of River Baleshwar Khadi)

(ii) Status of STPs, I&D and Existing infrastructure: --- sewerage networks Gap analysis: 9 MLD Details of existing Proposed : --- infrastructure, gap analysis, Completion Timeline : --- proposed along with PRH & RDD was informed to submit the action completion timeline plan for the sewage generated from the villages (Baleshwar, Samrod & nearby-9 MLD) (iii) Status of CETPs No. of industries: - Industrial Estate Gujarat Eco Details of existing CETP and Textile Park and Industries located near ETP infrastructure, gap Palsana village with total 80 Nos. of analysis, proposed along industries. with completion timeline, All the industries are CETP members having no. of industries and primary ETP facility. complying status Existing CETPs:- There are two CETPs namely- Gujarat Eco Textile Park Ltd (GETPL), Palsana and New Palsana Industrial Co-op Society Ltd, Palsana having GPCB permission for final discharge of treated effluent Surat 105 MLD

Proposed CETP Modification/Upgradation:- Gujarat Eco Textile Park Ltd,-GETPL, Palsana (60 MLD) - has obtained CTE Amendment for zero liquid discharge as the treated water shall be recycled to member units. They will propose new installation of Sedimentation tank, casket cooling system, Disk flotation, ultrafiltration and RO plant for upgradation and recycle of treated waste water to member units. Present Status- Land levelling & Compound wall / Gabion wall under Progress. Expected to be completed by 2021 (iv) Status of Solid Waste Letter has been issued to Panchayat, Rural Management & Details of Housing & Rural Development Department by Processing Facilities GPCB, Head office-Gandhinagar to submit the Details of existing action plan of solid waste management infrastructure, gap analysis, proposed along with completion timeline

Page 2 of 8

(PRS of River Baleshwar Khadi)

(v) Latest water quality of 5 (v) Status is attached as Annexure – I polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 45 # of HCUs (Health Care Units), management including bio- treatment & disposal of Bio Medical Waste of medical wastes, plastic which is being taken care of by a common wastes and decentralizing facility M/s, Globe Bio Care located in Surat waste processing, including Industrial Waste:- waste generated from In the State, all Hazardous waste generating hotels, ashrams etc. units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule- 9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) given practices by Irrigation Dept. as on date is attached as (ix) Protection and Annexure – II management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by Forest the river Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment Team encroachment nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 8

(PRS of River Baleshwar Khadi)

Annexure-I

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river Progress/Status Report of the River/PRS water quality Monitoring (April -2020):

Date Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) 06-04-20 Baleshwar Khadi 7.01 7.45 1.05 12 6 53 Progress/Status Report of the River/PRS ground water quality Monitoring:

Location:- BOREWELL AT LUCKY FILLING STATION PALASANA

Date ALK BOD BOR CHL CND COD COL DOX FCO MAG NH3 NIT NTR pH PHO POT SOD SS SUP T.H TCO TDS TKN TMP

06/04/2020 320 0.91 0.04 210 1458 10 10 5.922 11 43.77 0.84 0.040 0.072 7.35 0.045 2.9 120.4 6 102 410 39 910 1.12 29 Location:- BOREWELL AT PRIMARY HEALTH CENTER(PHC)

Date ALK BOD BOR CHL CND COD COL DOX FCO FLU MAG NH3 NIT NTR pH PHO POT SOD SS SUP T.H TCO TDS TKN 06/04/2020 170 0.99 0.035 380 2280 09 10 5.92 6 0.24 38.91 0.28 0.026 0.063 7.22 0.042 3.9 207.1 100 90 340 41 1300 1.12

Drain details with flow:

Sr.No. Name of Drain/Location Discharged

Max Min

1 Bagumara-Gangadhara 0.3 MLD 0.1 MLD

2 Baleshwar-Samrod 114 MLD 50 MLD

Page 4 of 8

(PRS of River Baleshwar Khadi)

Annexure-II

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Baleshwar Khadi Details mentioned as below

Page 5 of 8

(PRS of River Baleshwar Khadi)

Annexure-III

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

The details received from Social Forestry wing, Aranya Bhavan, Gandhinagar are as under Stretch/river Existing Proposed plan to Time limit Remarks plantation/vegetation cover cover remaining details gap along river /river stretch Baleshwar Kahdi Target submitted by APCCF for all the Rivers of Gujarat (Pandesara to 1430 trees is as per attached details in Annexure-A )

Page 6 of 8

(PRS of River Baleshwar Khadi)

Annexure-A

Page 7 of 8

(PRS of River Baleshwar Khadi)

Page 8 of 8

(PRS of River Kim)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 PRH & RDD was informed to submit the and connecting all the drains and other action plan for the sewage generated from sources of generation of sewage to the the villages Sahol & Kim having discharge STPs must be ensured 10 MLD 2 Timeline for completing all steps of 31.03.2021 action plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. Fortnightly CS (Last meeting was conducted on • Monitoring at State level must commencing 24/12/2019) in matter of O.A. No.:- take place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan. NGT order on insitu In-situ treatment:- Pl. refer point no:-1 treatment

Page 1 of 9

(PRS of River Kim)

(ii) Status of STPs, I&D and Existing infrastructure: -- sewerage networks Gap analysis: 10 MLD Details of existing Proposed : -- infrastructure, gap analysis, Completion Timeline : -- proposed along with PRH & RDD was informed to submit the completion timeline action plan for the sewage generated from the villages (Sahol & Kim-10 MLD) (iii) Status of CETPs No Industrial wastewater discharge Details of existing CETP and into this river stretch ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste • Letter is issued from ACS, F & ED, GoG to Management & Details of PRH & RDD, GoG for proper discharge & Processing Facilities disposal of sewage /solid waste & its Details of existing management. infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – I polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 30 # of HCUs (Health Care management including bio- Units), treatment & disposal of Bio medical wastes, plastic Medical Waste of which is being taken wastes and decentralizing care of by a common facility M/s, Globe waste processing, including Bio Care located in Surat waste generated from Industrial Waste:- hotels, ashrams etc. In the State, all Hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020

Page 2 of 9

(PRS of River Kim)

at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – II management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 9

(PRS of River Kim)

Annexure-I

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring (April-2020):

Date Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) 07/04/20 Sahol Bridge 7.05 7.26 0.98 10 9 39

Progress/Status Report of the River/PRS ground water quality Monitoring:

Location:- BOREWELL AT GARG TEX-O FEB PVT.LTD

Date %NA ALK BOD CAL COD CND DOX FLU MAG NH3 NIT NTR pH PHO POT SOD SS SUP T.H TCO TDS TKN TMP TUR

07/04/2020 47 320 0.82 661.32 10 15720 7.09 0.35 364.8 0.56 0.047 0.072 7.59 0.048 34.5 1306 8 888 3150 39 9130 1.12 29 2.0

Location:- BOREWELL AT PIRAMAL GLASS

Date ALK BOD BOR CHL CND COD COL DOX FCO FLU MAG NH3 NIT NTR pH PHO POT SOD SS SUP T.H TCO TDS TKN TMP TUR 390 07/04/2020 0.89 0.04 690 3595 09 10 5.93 6 0.55 58.37 0.84 0.048 0.077 7.55 0.043 3.4 413 8 210 450 41 2610 1.12 26 3.0

Location:- BOREWELL AT NEELAM FIBER KIM IND AREA PLOT-202

Date ALK BOD BOR CHL CND COD CAL DOX FCO FLU MAG NH3 NIT NTR pH PHO POT SOD SS SUP T.H TCO TDS TKN TMP TUR 84.17 07/04/2020 390 0.81 0.04 512 3595 10 7.09 9 0.55 58.37 0.56 0.048 0.077 7.48 0.043 3.4 323.7 8 190 450 53 2080 1.12 26 3.0

Page 4 of 9

(PRS of River Kim)

Drain details with flow:

Sr.No. Location/ Name of Inletting Discharge Name of Drain River/Drain Max Min

1 Kim to Sahol Village Kim drain 10 MLD 2 MLD

Page 5 of 9

(PRS of River Kim)

Annexure-II

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Kim Details mentioned as below

Page 6 of 9

(PRS of River Kim)

Annexure-III

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

The details received from Social Forestry wing, Aranya Bhavan, Gandhinagar are as under Stretch/river Existing Proposed plan to Time limit Remarks plantation/vegetation cover cover remaining gap details along river/river stretch Kim (Sahol Bridge to Target submitted by APCCF for all the Rivers of Gujarat is as 370 trees Hansol) per attached details in Annexure-A

Page 7 of 9

(PRS of River Kim)

Annexure-A

Page 8 of 9

(PRS of River Kim)

Page 9 of 9

(PRS of River Meshwo)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 There is no sewage discharge in Meshvo least in-situ remediation river in the stretch of Meshvo at Shamalaji Commencement of setting up of STPS 31.03.2020 No STP is required as there is no sewage and connecting all the drains and other discharge in the stretch of Meshvo at sources of generation of sewage to the Shamalaji. STPs must be ensured 2 Timeline for completing all steps of 31.03.2021 action plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress

nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. Fortnightly CS (Last meeting was conducted on • Monitoring at State level must commencing 24/12/2019) in matter of O.A. No.:- take place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting There are no polluting sources in the sources including drains stretch of Meshvo at Shamalaji. The contributing to river polluted stretch is required to be deleted pollution and action as per from the list of polluted river stretches in NGT order on insitu the state treatment (ii) Status of STPs, I&D and No sewage is discharged in to polluted sewerage networks river stretch Details of existing infrastructure, gap analysis, proposed along with completion timeline

Page 1 of 7

(PRS of River Meshwo)

(iii) Status of CETPs There is no Industrial wastewater Details of existing CETP and discharge into this river stretch ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste NA Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – I polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 970 # of HCUs (Health Care management including bio- Units) located in the Himmatnagar, medical wastes, plastic treatment & disposal of Bio Medical wastes and decentralizing Waste of which is being taken care of by a waste processing, including waste generated from common facility Ecoli waste management hotels, ashrams etc. pvt. Ltd (unit-2) located at Plot no- 98,99,100 Sabar industrial park, opp. Asopalav Hotel, Himmatnagar- Shamlaji road, Asal, Ta. Bhiloda, Dist. Aravalli. Industrial Waste:- In the State, all Hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which Page 2 of 7

(PRS of River Meshwo)

is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – II management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – III (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 7

(PRS of River Meshwo)

Annexure- I

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring:

Date Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) April- River Meshwo River is dry hence sample is not collected 20 D/s at Shamlaji

Progress/Status Report of the ground water quality Monitoring:

Date Location pH BOD (mg/l) COD (mg/l) TDS (mg/l)

April- Borewell from Shamlaji 7.23 0.63 4 564 20 Dharamshala

Annexure-II

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Meshwo Data/details will be furnished soon

Page 4 of 7

(PRS of River Meshwo)

Annexure-III

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing Proposed plan Time limit Remarks plantation/vegetation to cover cover details remaining gap along river /river stretch Meshwo Sparse Natural Vegetation of Target submitted by APCCF for all the Rivers of River bank of Propopis juliflora & other Gujarat is as per attached details in Annexure-A River Shamlaji shrubs and climbers

Page 5 of 7

(PRS of River Meshwo)

Annexure-A

Page 6 of 7

(PRS of River Meshwo)

Page 7 of 7

(PRS of River Mindhola)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 STP of 4 MLD (2+2 MLD) proposed by and connecting all the drains and other Sachin Notified Area Authority –2020 sources of generation of sewage to the STPs must be ensured 2 Timeline for completing all steps of 31.03.2021 action plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an Reviews of all NGT matters are taken accountable person attached in 22.01.2020 frequently under chairmanship of Hon’ble their office for this purpose. Fortnightly CS (Last meeting was conducted on • Monitoring at State level must commencing 24/12/2019) in matter of O.A. No.:- take place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan. NGT order on insitu In-situ treatment:- Pl. refer point no:-1 treatment

Page 1 of 9

(PRS of River Mindhola)

(ii) Status of STPs, I&D and Existing infrastructure: -- sewerage networks Gap analysis: 1.6 MLD Details of existing Proposed : 04 MLD infrastructure, gap analysis, Completion Timeline : 2020 proposed along with Proposed STP:- completion timeline STP of 4 MLD capacity is proposed by Sachin Notified Area Authority. DTR is ready. Allotment of land is under approval in GIDC. (iii) Status of CETPs No Industrial wastewater discharge Details of existing CETP and into this river stretch ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 30 # of HCUs (Health Care management including bio- Units), treatment & disposal of Bio medical wastes, plastic Medical Waste of which is being taken wastes and decentralizing care of by a common facility M/s, Globe waste processing, including Bio Care located in Surat waste generated from Industrial Waste:- hotels, ashrams etc. In the State, all Hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and

Page 2 of 9

(PRS of River Mindhola)

Management of Ground Water in Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS Assessment encroachment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 9

(PRS of River Mindhola)

Annexure-I

5 (iv ) Status of Solid Waste Management & Details of Processing Facilities

Type of waste/ Generated Collection/ Disposal/Treatment Total Gap Proposed Time Present Status Characteristic quantity/ facility with capacity with action limit of waste Storage facility with along with location generation plan/facility day capacity &existing to cover gap treatment facilities if any

Solid waste 10 Authorized 10 DPR is under Year Sachin Notified Agencies/end processes 2020 Area Authority users/recyclers has requested for land allotment required for municipal solid waste disposal site development in their Head Office. After receiving necessary approval they will proceed for further development. Total 10 10

Page 4 of 9

(PRS of River Mindhola)

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring:

Date Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) 06/04/2020 River Mindhola 7.02 7.22 0.91 12 6 53

Progress/Status Report of the River/PRS ground water quality Monitoring:

Location: - BOREWELL AT SACHIN GIDC (SIEL)

Date %NA ALK BOD CAL CHL CND COD COL DOX FDS FLU MAG NAA NH3 NTR pH PHO POT SOD SS SUP T.H TCO TDS TKN TMP TUR

05/04/2020 38 440 0.9 609.22 1812 10630 10 10 7.02 -- 0.28 221.31 6.04 0.84 0.084 7.28 0.038 6.7 681.2 8 587 2430 41 6270 1.4 29 3.0 Location: - BOREWELL AT NR COMMON HAZ WASTE DSPO.SITE(GEPIL)

Date %NA ALK BOD CAL CHL CND COD COL DOX FDS FLU MAG NH3 NTR pH PHO POT SOD SS SUP T.H TCO TDS TKN TMP TUR

05/04/2020 53 280 1.09 288.58 710 4446 12 15 4.93 -- 0.28 97.28 1.12 0.057 7.40 0.045 4.2 577.8 8 282 1120 53 2490 1.68 29 3.0 Location: - OPEN WELL AT GABHENI OPP: PANCHYAT OFFICE

Date %NA ALK BOD CAL CHL CND COD COL DOX FDS FLU MAG NH3 NTR pH PHO POT SOD SS SUP T.H TCO TDS TKN TMP TUR

05/04/2020 18 380 0.87 136.27 432 2741 08 10 7.05 -- 0.16 97.28 0.56 0.061 7.12 0.031 2.15 72.12 10 117 740 39 1510 1.12 30 2.0

Page 5 of 9

(PRS of River Mindhola)

Drain details with flow:

Sr.No. Location Name of Inletting River/Drain Discharged Max Min 1 Sachin Notified area Kapletha village drain meeting 1.6 MLD 0.5 MLD River Mindhola Note:- Entire Baleshwar Khadi is meeting to River Mindhola at village Samrod as major drain. Polluted River action plan of Baleshwar Khadi is prepared and submitted separately.

Annexure-III Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Mindhola Details mentioned as below

Page 6 of 9

(PRS of River Mindhola)

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

The details received from Social Forestry wing, Aranya Bhavan, Gandhinagar are as under Stretch/river Existing Proposed plan to cover Time limit Remarks plantation/vegetation remaining gap along cover details river/river stretch

Mindhola Target submitted by APCCF for all the Rivers of Gujarat is as (Along 1250 trees per attached details in Annexure-A sachin)

Page 7 of 9

(PRS of River Mindhola)

Annexure-A

Page 8 of 9

(PRS of River Mindhola)

Page 9 of 9

(PRS of River Narmada)

National Mission for Clean Ganga Monthly Progress Report of Gujarat State for April-20 (Hon’ble NGT in the matter of OA No.673/2018 dated 06/12/2019) Sl.No. Activity to be monitored Timeline Submission of Progress by States/UT- Compliance Status 1 Ensure 100% treatment of sewage at 31.03.2020 Presently there is no any proposal for in- least in-situ remediation situ remediation. However, as per the suggestion given by Assessment team during meeting held on 04/02/2020, NEERI, UP Govt., Punjab Gov. etc may be approached by UDD/GUDM/Concerned for technical support in the matter Commencement of setting up of STPS 31.03.2020 There is no discharge of domestic and connecting all the drains and other wastewater from any Municipal sources of generation of sewage to the Corporation (city) or Municipality STPs must be ensured (town) in this river stretch. 2 Timeline for completing all steps of 31.03.2021 action plans including completion of setting up of STPs and their commissioning 3 Chief Secretaries may set up appropriate 22.01.2020 Quarterly RRC meeting held at GPCB, monitoring mechanism at State level Gandhinagar to review the progress & • Specifying accountability of minutes of the same (having progress nodal authorities not below the status) is regularly submitted to CPCB Secretary Level • Chief Secretaries may have an 22.01.2020 Reviews of all NGT matters are taken accountable person attached in frequently under chairmanship of their office for this purpose. Fortnightly Hon’ble CS (Last meeting was conducted • Monitoring at State level must commencing on 24/12/2019) in matter of O.A. No.:- take place 21.12.2019 606/2018 4 Progress report may be furnished by the Monthly Noted & Complied States/UTs to (preferably • Secretary, Ministry of Jal Shakti before 20th of • Member Secretary, CPCB every month) 5 Progress Report may be comprised of details along with completion timelines on: (i) Identification of polluting Identification of polluting sources sources including drains including drains contributing to river contributing to river pollution is already completed and pollution and action as per submitted in the PRS action plan. NGT order on insitu In-situ treatment:- Pl. refer point no:-1 treatment

Page 1 of 7

(PRS of River Narmada)

(ii) Status of STPs, I&D and There is no discharge of domestic sewerage networks wastewater from any Municipal Details of existing Corporation (city) or Municipality (town) infrastructure, gap analysis, in this river stretch. proposed along with completion timeline (iii) Status of CETPs No Industrial wastewater discharge into Details of existing CETP and this river stretch ETP infrastructure, gap analysis, proposed along with completion timeline, no. of industries and complying status (iv) Status of Solid Waste 5 (iv) Status is attached as Annexure – I Management & Details of Processing Facilities Details of existing infrastructure, gap analysis, proposed along with completion timeline (v) Latest water quality of 5 (v) Status is attached as Annexure – II polluted river, its tributaries, As per the CPCB report (Sep-18) based on drains with flow details and results of 2016 & 2017, Narmada not ground water quality in the been fall in any priority with <3 mg/L BOD catchment of polluted river and information for the same is already submitted to CPCB. (vi) Preventing dumping of Bio-Medical Waste:- waste and scientific waste There are total 61 # of HCUs (Health Care management including bio- Units) located in the Ankleshwar taluka, medical wastes, plastic treatment & disposal of Bio Medical wastes and decentralizing Waste of which is being taken care of by waste processing, including a common facility M/s, Globe Bio Care waste generated from located in GIDC Ankleshwar hotels, ashrams etc. Industrial Waste:- In the State, all Hazardous waste generating units are consented with the authorization under Haz. Waste Management Rules, amended time to time & they are disposing their waste to TSDF/CHWIF/registered recycler under Rule-9/Co-processing and as per consented conditions (vii) Ground water regulation GWRDC has given details about the recently framed draft bill titled “Conservation, Protection, Regulation and Management of Ground Water in

Page 2 of 7

(PRS of River Narmada)

Gujarat State” in the meeting held on 04/02/2020 at GPCB with PRS Assessment Team nominated by Ministry of Jal Shakti which is in process and within 3 months to be submitted to the Assembly (viii) Adopting good irrigation Details w.r.t point no. 5 (viii), (ix), (x), (xi) practices given by Irrigation Dept. as on date is (ix) Protection and attached as Annexure – III management of Flood Plain Zones (FPZ) (x) Rain water harvesting (xi) Maintaining minimum environmental flow of river (xii) Plantation on both sides of Details w.r.t point no. 5 (xii) given by the river Forest Dept. /PCCF/ACCF/Concerned as on date is attached as Annexure – IV (xiii) Setting up biodiversity parks GBB informed during the meeting held on on flood plains by removing 04/02/2020 at GPCB with PRS encroachment Assessment Team nominated by Ministry of Jal Shakti about proposal sent by them to CAMPA for funding of around Rs. 5 crore for the development of Biodiversity Park. Team suggested tying up with AMC as they already have some plan to develop Biodiversity park at Khari under NRCP.

Page 3 of 7

(PRS of River Narmada)

Annexure- I

5 (iv) Status of Solid Waste Management & Details of Processing Facilities:

Types of Generated Collection/ Disposal/ Treatment Total Gap with Proposed action plan Present Status Waste/ Quantity/day Storage facility facility with capacity generation & /facility to cover gap Characteristic with capacity along with location existing treatment of waste facilities if any MSW waste 95 MT/d No proper Disposed off at village 95 MT/d The Nagarpalika has Physical progress is collection & Mandva-bhuzarg site on proposed facility for waste so far not started storage open land without fencing to energy. This project is or any other measures. proposed at plot no. DP 97 & DP 98/1, Saykha GIDC, Vill: Saykha, Tal: Vagra, Dist: Bharuch

Annexure-II

5 (v) Latest water quality of polluted river, its tributaries, drains with flow details and ground water quality in the catchment of polluted river

Progress/Status Report of the River/PRS water quality Monitoring:

Date Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal Coliform Total coliform (MPN/100 ml) (MPN/100 ml) April- NTPC Zanor 7.52 7.51 0.78 6 49 79 20 Zadeshwar 7.42 7.53 0.80 7 94 220 Garudeshwar 7.56 7.78 0.65 6 23 49

Page 4 of 7

(PRS of River Narmada)

Annexure-III

Details w.r.t point no. 5 (viii), (ix), (x), (xi) given by Irrigation Dept. as on date

Sr.No River name Details/Status

1 Narmada Data/details will be furnished soon

Annexure-IV

Details w.r.t point no. 5 (xii) given by Forest Dept. /PCCF/ACCF/Concerned as on date

Stretch/river Existing Proposed plan to Time Remarks plantation/vegetation cover remaining gap limit cover details along river /river stretch Narmada River South side Target submitted by APCCF for all the Rivers of (Asha to mulad village) 12500 trees Gujarat is as per attached details in Annexure-A 56.44 Km

Page 5 of 7

(PRS of River Narmada)

Annexure-A

Page 6 of 7

(PRS of River Narmada)

Page 7 of 7