City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/1/20 B2020-1125 ISSUED 157-461-04 21 PIMENTEL NOVO TENANT 340,000 12,164.00 Installation of a new instrument Air CT CONSTRUCTI IMPROVE system, including a new three ON, INC MENT sided enclosure with Roof. Includes - electrical, mechanical, plumbing structural and fire protection upgrades to the existing facility as part of this project.

9/1/20 B2020-1592 ISSUED 153-281-01 1 FOX CT MOORE MINOR 4,500 289.10 Add on 4 Ton AC (16 Seer) in the back HOME MECHANI Yard and add a gable mounted attic - SERVICES CAL WUI

9/1/20 B2020-1847 FINALED 153-055-02 910 RAILROAD NORTHERN SOLAR 29,340 240.68 5.61 kW Residential Roof Mounted PV AVE PACIFIC Installation (17 Modules) POWER SYSTEMS

9/1/20 B2020-1851 ISSUED 160-760-48 290 IGNACIO SOLAR CITY SOLAR 27,950 608.34 Install ( 27 ) roof mount solar panels at VALLEY CIR dba TESLA 9.18 kw and 2 energy storage systems to back up existing electrical and 1 inverter WUI

9/1/20 B2020-1888 FINALED 140-191-40 730 DEL MAR SAFE & CONSTR 4,825 168.86 Installation of a gas burning AVE WARM UCTION insert. Install of electrical for blower from CHIMNEY nearby plug. SERVICES

9/1/20 B2020-1912 FINALED 124-202-03 47 ANDREAS PETER LEVI WATER 3,000 39.90 40 Gallon Water Heater Change Out CIR PLUMBING HEATER INC

9/1/20 B2020-1915 ISSUED 143-441-03 94 PETER LEVI MINOR 23,154 94.44 96% 100K BTU change out, 5 ton ROBINHOOD PLUMBING MECHANI 18 seer AC change out - WUI DR INC CAL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/1/20 B2020-1926 ISSUED 125-271-02 25 SAN OWNER- MINOR 2,500 111.38 Replacement - Install NEW 200 AMP JOAQUIN PL BUILDER ELECTRI Service Overhead - WUI CAL

9/1/20 B2020-1946 FINALED 143-421-42 21 KNOLLTOP GENE BURCH FURNAC 18,772 93.23 replace furnace/ac with new one in same CT PLUMBING & E AC location WUI HEATING HVAC OL

9/1/20 B2020-1947 FINALED 150-472-06 45 TERRY CIR SUTTER REROOF 24,000 467.12 Tear off, reroof, install new plywood, install ROOFING & Class A Comp Shingles, 31 Squares WUI SHEET METAL INC

9/1/20 B2020-1948 FINALED 124-211-36 276 SAN M&Z Electrical MINOR 1,600 94.44 Emergency Changing a broken Zinsco FELIPE WAY Contractor ELECTRI main panel - House without power CAL

9/1/20 B2020-1950 FINALED 153-262-15 491 WILLOW JOHN MINOR 1,000 94.44 Dig Up and Install New Water Line from CT GLEASON PLUMBIN home to street - WUI PLUMBING & G SEWER SERVICE

9/1/20 B2020-1951 ISSUED 140-470-08 30 TWIN BELLOWS MINOR 8,000 196.08 Replace existing FAU/AC like for like Seer CREEKS CT PLUMBING, MECHANI 16 AFUE 96% HEATING & CAL AIR City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/1/20 B2020-1952 FINALED 140-201-42 760 PLAZA PETER LEVI MINOR 26,973 93.23 2 Ton MiniSplit Change out Like for Like AMAPOLA PLUMBING MECHANI INC CAL

9/1/20 B2020-1953 ISSUED 160-730-13 174 HADDON MINOR 10,387 94.44 AC And Furnace Replacement - 14 Seer SANDPIPER HEATING AND MECHANI and 96% AFUE - WUI CT COOLING CAL

9/1/20 B2020-1959 FINALED 153-047-19 800 GRANT LIC.CONTRAC MINOR 840 94.44 Repair Electric Box - Per CBO Subject to AVE T.HIRED BY ELECTRI Field Inspection OWNER CAL

9/1/20 B2020-1964 FINALED 160-621-09 15 VERDE FURNAC 14,075 93.23 Replace furnace, coil and condenser for PENSACOLA METALS INC. E AC system #1 WUI CT HVAC OL

9/1/20 B2020-1965 FINALED 160-621-09 15 VERDE FURNAC 14,075 93.23 Replace furnace, coil and condenser for PENSACOLA METALS INC. E AC system #2 WUI CT HVAC OL

9/1/20 RP2020-0069 FINALED 132-223-63 739 KENDON OWNER- MINOR 5,000 514.66 Work w/o Permit: As-Built Rear Fence 105 LN BUILDER CONSTR Feet Length UCTION City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/2/20 B2019-0910 FINALED 143-292-05 155 CERRO MARINKITCHE CONSTR 58,188 3,381.59 Add (2) new bedrooms on second floor. CREST DR NCO INC UCTION Relocate bathroom with new shower. Replace 4 windows; Add new HVAC to new location; Replace (2) electrical sub-panels; Repair and replace exterior siding with new hardie panels; Replace exterior lighting. No structural modifications. WUI; (1/8/20 KM)- Revision-Add new additional bedroom - see plans (1/30/20 DWS) Revision: Bedroom #1 is existing, but construction being done and is labeled as "additional bedroom". Construction is being done on Bedroom #1

9/2/20 B2020-1372 ISSUED 160-621-07 3 PENSACOLA OWNER- MINOR 15,000 363.41 Replacing rotting deck with new material. CT BUILDER CONSTR Keeping what is salvagable. WUI UCTION

9/2/20 B2020-1541 FINALED 153-380-18 229 CLUB DR SUN FIRST SOLAR 27,658 249.43 Install ( 24 ) Roof Mounted Solar PV SOLAR Modules and Enphase Inverters - WUI

9/2/20 B2020-1546 ISSUED 160-531-50 53 FLICKER MOORE MINOR 7,250 253.98 Add on 3 Ton AC in the back way and DR HOME MECHANI change out 7000 BTU Furnace - WUI SERVICES CAL

9/2/20 B2020-1701 ISSUED 152-033-11 1466 PASTEL BENGA ELECTRI 9,800 376.30 Installation of a permanently mounted 16 w LN CONSTRUCT., CAL Generac Standby, whole house back up J BENGA generator connectedto gas meter and GROUP INC. electric meter disconnect panel. **COA: zombie box noise enclosure shall be installed over generator, as shown on the plan set. KZitelli** City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/2/20 B2020-1704 ISSUED 160-352-04 482 FAIRWAY JAJ ROOFING ELECTRI 15,304 405.15 New Battery ( add to existing solar ) 1 DR dba CITADEL CAL Tesla Powerwall, 1 subpanel 225a, 1 back ROOFING up gateway - WUI AND SOLA

9/2/20 B2020-1763 ISSUED 132-142-08 862 RAE LN OWNER- MINOR 5,000 210.56 Replace heating unit with New Air BUILDER MECHANI Conditioning/heating unit. CAL

9/2/20 B2020-1786 FINALED 143-233-28 2445 TOPAZ UNITED ELECTRI 6,000 239.65 Install emergency back up generator - WUI DR CONSTRUCTI CAL ON, UNITED GENERATOR

9/2/20 B2020-1853 ISSUED 151-081-03 1522 OWNER- ELECTRI 1,000 115.84 Remove and replace 11 recessed existing BUCHANAN ST BUILDER CAL light trims in Kitchen and Living Room - Per Plans

9/2/20 B2020-1933 ISSUED 151-102-21 1536 SOS MINOR 3,500 128.32 Upgrade 100 A main panel to 200 A in the BUCHANAN ST ELECTRICAL ELECTRI same location CAL

9/2/20 B2020-1940 FINALED 157-910-02 20 ASHLAND VIVINT SOLAR SOLAR 8,580 278.92 Install 12 panel PV Roof Mount System - DR DEVELOPERS 3.90 kW LLC

9/2/20 B2020-1957 ISSUED 125-460-06 3 WINDMILL PL HOFFMAN MINOR 2,500 111.38 Emergency Main Panel Replacement 100 - ELECTRIC ELECTRI 100 amp Underground Feed - WUI CAL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/2/20 B2020-1961 ISSUED 153-121-07 817 REICHERT ALEXEY MINOR 4,500 184.88 Upgrade existing 100 amp zinsco panel to AVE BYCHKOV ELECTRI 200 amp meter main panel, located on DBA ALL CAL exterior of garage Upgrade existing MARIN 100amp zinco sub panel to 200 amp Eaton ELECTRIC sub panel. Located in the garage. See attached site plan

9/2/20 B2020-1963 FINALED 124-222-02 159 SAN LUX Lighting MINOR 1,499 94.44 Upgrade Electrical Sub Panel - 100 Amp ) - CARLOS WAY Design & ELECTRI Located inside Garage left hand side Flush Electrical CAL Mounted

9/2/20 B2020-1966 ISSUED 140-031-70 95 GROVE LN OWNER- WINDOW 7,000 183.27 Repair termite damage on front of house - BUILDER Remove old Siding / Replace window and front door

9/2/20 B2020-1970 FINALED 150-461-17 60 JOHN OWENS FURNAC 5,033 93.23 Install Mini-Split AC unit in Residence WUI DRAKEWOOD SERVICES E AC LN INC HVAC OL

9/2/20 B2020-1971 FINALED 141-021-23 31 NOVA LN WEDGE REROOF 14,675 358.18 House Only - Excludes Detached Garage. ROOFING, Prepare existing surface to recieve new INC. roof. Apply 1" SPF with Silicone Coating - REVISION REQUEST RECIEVED - Add Garage - Prepare existing surface to recieve new roof. Apply 1: SPF with Silicone Coating

9/2/20 B2020-1975 FINALED 124-294-37 16 ROMERO Reggie's WATER 2,500 39.90 replace water heater, 50 gal, natural gas CT Reliable HEATER Plumbing Ser OL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/2/20 B2020-1976 FINALED 160-810-21 146 PELICAN GENE BURCH FURNAC 9,785 93.23 replace furnace/ac with new one in same LN PLUMBING & E AC location WUI HEATING HVAC OL

9/2/20 B2020-1977 ISSUED 160-700-50 37 HECTOR LN OWNER- MINOR 3,800 312.73 Work without Permits: As Built Water BUILDER CONSTR Heater - WUI UCTION

9/2/20 B2020-1978 ISSUED 132-231-19 22 LAURIE CT ADAMS MINOR 5,500 147.88 install ductless AC unit in living room - 16 REFRIGERATI MECHANI Seer Unit ON SERVICE CAL

9/2/20 RP2020-0068 FINALED 132-223-63 739 KENDON OWNER- MINOR 5,000 542.00 Work w/o permits - Pergola - Ref# RI2020- LN BUILDER CONSTR 0407 UCTION

9/3/20 B2020-1752 ISSUED 140-021-19 8 ST PAUL CIR NORTHERN ELECTRI 35,493 674.33 Residential Energy Storage System PACIFIC CAL (11/2/20 KDON) Revision: Relocated POWER equipment from inside garage to exterior. SYSTEMS No change in equipment

9/3/20 B2020-1774 ISSUED 141-261-29 1320 GRANT BAY CONSTR 2,000 344.44 Work w/o permits: Recess lights, washer & AVE BUILDERS UCTION dryer installed. Ref CE-18-0089 INC. City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/3/20 B2020-1857 ISSUED 141-340-15 4 MITCH CT SUNRUN SOLAR 31,751 563.21 Install ( 33 ) roof mounted PV Solar panels INSTALLATIO at 10.395kW. ESS & (1) 200 a control N SERVICES panel. Main breaker derate: Replace INC existing 200 a main breaker with new 150a 22k AC rtd main breaker. Main Panel Replacement. Replace Existing 200 a mn panel 2/ 200 mn breaker with new 200 a mn panel with 150 a mn breaker. - WUI

9/3/20 B2020-1868 ISSUED 140-360-66 809 DIABLO AMERICAN CONSTR 32,530 2,131.06 LED Lighting for exterior common area AVE POWER UCTION (9/22/20 GBA) Revised: Master permit for SOLUTIONS B2020-2162, B2020-2163, AND B2020- INC 2164--per Acting CBO Starnes and SCEO Beretta

9/3/20 B2020-1932 FINALED 132-183-02 10 SIERRA OWNER- REROOF 10,000 229.96 ReRoof VISTA BUILDER

9/3/20 B2020-1944 ISSUED 124-211-42 290 SAN KAPRANOS MINOR 42,800 904.57 Remodel / upgrade (2) adjacent existing FELIPE WAY CONSTRUCTI CONSTR residential bathrooms W/ (N) plumbing & ON UCTION electrical fixtures, cabinets, counters, tile. Add (1) 4'x 1'6" fiberglass window in shower (WUI tempered)

9/3/20 B2020-1949 ISSUED 140-191-40 730 DEL MAR C M MINOR 1,225 95.84 Run a dedicated gas line from the meter, AVE PLUMBING PLUMBIN into the fireplace for a fireplace insert. SERVICES G Starting off with a 3/4", enter attic and continue with approx 45' of 1/2" pipe. City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/3/20 B2020-1954 ISSUED 157-412-12 1 DIGITAL DR D C TAYLOR REROOF 469,991 3,738.21 T/O Existing Modified Bituminous Roof. CO. Install Class A Sikaplan FR 60 mil PVC Fleeced Back roof membrane 51,200 sq. ft

9/3/20 B2020-1956 ISSUED 124-212-13 84 SAN GLOBAL SOLAR 23,000 512.40 RES Photovoltaic: Roof mount (23) panels CARLOS WAY ENERGY @ 7.36 kWUpgrade MSP to 200 Amp (9/28/20 KDON) Revision: Changed the layout of solar panels on plans

9/3/20 B2020-1982 ISSUED 125-500-42 6 BRIDLE Renewal by WINDOW 12,279 93.73 REPLACING 4 RETROFIT WINDOWS PATH LN Andersen of SF S 1 TO 8 WUI (JEMICO) OL

9/3/20 B2020-1990 FINALED 146-411-14 2042 EL BENJAMIN WATER 3,200 39.90 REPLACING 40 GALLON GAS WATER DORADO CT FRANKLIN HEATER HEATER WUI PLUMBING OL

9/3/20 B2020-1996 ISSUED 143-401-01 724 AMERICAN WINDOW 1,650 93.73 Manufacture and install 1 Simonton Bay ALBATROSS WINDOW S 1 TO 8 Window WUI DR SYSTEMS OL

9/3/20 B2020-1997 FINALED 146-081-24 9 GOLDFINCH UNITED FURNAC 7,150 93.23 replace furnace and ac WUI CT HEATING AND E AC COOLING HVAC OL

9/4/20 B2020-1998 FINALED 146-031-02 617 BENJAMIN WATER 2,100 39.90 REPLACING 40 GALLON GAS WATER TRUMBULL FRANKLIN HEATER HEATER WUI AVE PLUMBING OL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/8/20 B2019-2394 ISSUED 160-421-08 920 IGNACIO OWNER- CONSTR 65,000 4,836.56 Bedroom addition; 440 sq feet to be added. BLVD BUILDER UCTION Roof over entry- per plans

9/8/20 B2020-1637 ISSUED 152-071-07 27 SEQUOIA OWNER CONSTR 18,000 565.22 Remove and replace existing deck, replace GLEN LN UCTION (2) windows & dry rot repair

9/8/20 B2020-1918 ISSUED 160-441-10 81 BECKER MINOR 18,000 217.27 Remodel bathroom as like existing.New BROADMOOR BUILDER CONSTR toilet, vanity, shower stall, tile floor and CT UCTION upgrade lighting to LED w/fan.

9/8/20 B2020-1983 ISSUED 153-055-02 910 RAILROAD HOFFMAN MINOR 2,500 111.38 Upgrade main panel from 100 - 200 amp AVE ELECTRIC ELECTRI overhead feed - No Location Change CAL

9/8/20 B2020-1988 ISSUED 160-970-36 4 W PETER LEVI MINOR 7,335 93.23 80% Furnace Change Out - WUI BARBERRY PL PLUMBING MECHANI INC CAL

9/8/20 B2020-1994 ISSUED 143-251-50 2701 TIKI RD OWNER- MINOR 2,000 94.44 Main Panel Upgrade - Replacement - WUI BUILDER ELECTRI CAL

9/8/20 B2020-1995 ISSUED 146-441-08 180 CABRO CT BELLOWS MINOR 3,500 93.23 Replace existing 80% furnace in garage PLUMBING, MECHANI with new 96% furnace - WUI HEATING & CAL AIR City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/8/20 B2020-2001 FINALED 152-340-19 54 Renewal by WINDOW 13,119 93.73 REPLACING 1 WINDOW AND 1 DOOR SCOTTSDALE Andersen of SF S 1 TO 8 BOTH RETROFIT WUI WAY (JEMICO) OL

9/8/20 B2020-2004 ISSUED 160-831-01 1 PACIFIC DR MOORE MINOR 4,200 94.44 Change out 900000 BTu furnace in the HOME MECHANI garage - WUI SERVICES CAL

9/8/20 B2020-2005 ISSUED 141-221-21 1117 CLAYTON NEW CAP REROOF 11,800 263.84 Tear off existing roof and replace with CT ROOFING class A shingles - No structural change - WUI

9/8/20 B2020-2011 ISSUED 157-810-02 73 PRESIDIO CALIFORNIA FURNAC 15,523 93.23 A/C , FURNACE AND COIL 17 SEER 5 DR HEATING & E AC TON 80% 90K COOLING HVAC OL

9/8/20 B2020-2016 FINALED 152-381-33 17 STARVING WATER 1,880 39.90 Replace a 40 gallon water heater WUI BRIARWOOD PLUMBERS HEATER CT OL

9/8/20 B2020-2017 ISSUED 141-242-26 1100 THIRD ST BECKER WATER 1,500 39.90 EMERGENCY: Replacement of hot water BUILDER HEATER heater (on-demand) City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/8/20 B2020-2020 ISSUED 160-201-29 55 IGNACIO LN OWNER- MINOR - 94.94 Permit for Final - Ref# RP2019-0084 Work BUILDER CONSTR w/o permit: Dual pane windows (7), Kitchen UCTION remodel (no plans), Water heater, Added 220v outlet (off electrical panel), Reference RI2019-0160

9/8/20 B2020-2021 FINALED 157-461-03 20 PIMENTEL WEDGE REROOF 79,300 1,046.69 Prepare existing surface to receive new CT #B ROOFING, roof - Apply 1" SPF with Silicone Coating INC.

9/9/20 B2020-1211 FINALED 140-201-47 1541 CENTER SEMPER ELECTRI 36,380 907.26 Solar Install - One Battery 6.4 ku 20 silfeb RD SOLARIS CAL sil-320 NL Solar Panels ; 1- SEG .. NS Inverter ;1 Tesla Power wall Battery back up: REVISION RECEIVED - Resubmittal due to Plan Check Comments - New Install: 20 ( N ) solar panels 1 ( N) inverter, 1 Tesla backup powerwall 2 ( N ) battery back up ( N ) 200 A. Tesla backup gateway ( N ) 125 a generation Load center ( N ) Tesla Powerwall 2 ( N ) SE6000H-us inverter (N) Nema 3R J-Box (N) 3R J-Box - NO CHANGE IN VALUATION 9/9/20 B2020-1721 FINALED 160-480-30 215 ALAMEDA OWNER- MINOR 1,000 226.03 Minor repairs to existing wood retaining DEL PRADO BUILDER CONSTR wall (8/24/20 KHA) Updated description per UCTION revised permit worksheet: Repair of 2' wood retaining wall in 3 sections totaling approx 24 linear ft. Work includes the replacement of prressure treated 2" X 12" horizontal boards and the replacement of 2 to 3 posts. WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/9/20 B2020-1722 ISSUED 150-610-17 104 GARNER SEMPER SOLAR 27,900 608.34 Installation, (N) 200A. Tesla Backup DR SOLARIS Gateway 2 (N) 100A AC Disconnect 240V AC, (N) 200A selectedLoad Center. 240 V AC, 30A/2P, 30A/ 2P 30A/2P, (N) Tesla Powerwall 2 Tesla P/N 1092170-xx-x 5KW 13.51 KWH (N) Tesla Powerwall 2 Tesla P/N 1092170-xx-x 5KW 13.5 KWH

9/9/20 B2020-1767 ISSUED 140-241-53 9 HARRIS HILL SEMPER SOLAR 32,155 606.40 New Install Solar only ( 4 ) solar panels, 4 ( DR SOLARIS N) 60 A enpahse solar only load center nema - 3r 10A (8/27/20 EW) 20/2P, battery, 4-SPR x 22 360 E-AC- (N) inverter - WUI

9/9/20 B2020-1778 ISSUED 153-380-15 242 CLUB DR ELEMENT POOL 70,000 1,571.62 New in-ground swimming pool & spa OUTDOOR POOL CONSTRUCTI ON 9/9/20 B2020-1780 ISSUED 141-022-01 93 LAMBERT OWNER- CONSTR 20,000 698.36 Resurfacing pool, renovating patio deck & WAY BUILDER UCTION equipment shed renovation per plans

9/9/20 B2020-1881 FINALED 152-291-09 103 SCOTIA LN ROMAN'S MINOR 8,990 178.60 Run New 3/4 copper water service from PLUMBING PLUMBIN meter, in trench, to side of carport, Run line G up carport wall (9/2/20 EW) to existing "I" beam and continue to back side of Unit #103 - Continue line into backyard along fence line. Run up and over water heater door. Tie into existing 3/4 supply with new shutoff valve, hose bib, and vacuum breaker. Insulate Water line - REVISION - CHANGING DESCRIPTION - Not a Water Heater City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/9/20 B2020-1936 FINALED 160-601-01 949 SUSAN BELLOWS MINOR 9,000 314.62 Install four Wall Mount Port Mini Splits.Two WAY PLUMBING, MECHANI will be installed in two upstairs bedrooms, HEATING & CAL one to be installed in living room. One in the AIR master bedroom. Condenser placed behind home. WUI

9/9/20 B2020-2010 FINALED 124-071-29 49 SAN LUIS OWNER- CONSTR 2,500 39.90 Replacement of Water Heater - New water CT BUILDER UCTION heater in existing location

9/9/20 B2020-2026 ISSUED 146-165-26 16 NANCY DR AFFORDABLE WATER 2,221 39.90 REPLACE WATER HEATER, SAME WATER HEATER LOCATION WUI HEATERS OL AND PLUMBING IN

9/9/20 B2020-2028 ISSUED 150-442-04 215 SHEVELIN CAPSTONE REROOF 23,250 467.12 T/O existing. Taper all dead flat areas to RD ROOFING meet requirements of 1/4" per foot of positive drainage.(9/9/20 EW) Install a Mule Hide 60 ml bright white TPO. Install 2 layrers of shingle underlayment on sloped sections, new lifetime class a comp shingles - WUI

9/9/20 B2020-2031 ISSUED 160-750-13 145 QUAIL CT ONGARO & FURNAC 9,000 93.23 replace failed furnace with new furnace SONS E AC and add ac new WUI HVAC OL

9/9/20 B2020-2033 ISSUED 150-631-10 1 SAVANNA GENE BURCH FURNAC 7,448 93.23 replace ac with new one WUI CIR PLUMBING & E AC HEATING HVAC OL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/9/20 B2020-2037 FINALED 124-172-02 4 SANTA GENE BURCH FURNAC 7,400 93.23 replace ac with new one WUI GABRIELLA CT PLUMBING & E AC HEATING HVAC OL

9/9/20 B2020-2039 ISSUED 160-452-04 37 BONNIE SAVE MINOR 26,000 127.61 Replace 10 Windows & 2 patio doors in BRAE DR ENERGY CONSTR kind with white vinyl and WUI Glass - in- COMPANY UCTION kind - WUI (MAAP DBA)

9/9/20 B2020-2044 FINALED 160-760-35 238 IGNACIO KELLY FURNAC 8,000 93.23 REPLACE FURNACE & AC WUI VALLEY CIR PLUMBING & E AC HEATING HVAC OL

9/10/20 B2020-0307 ISSUED 132-231-69 35 HICKOX RD OWNER- CONSTR 40,000 2,596.74 359 sq. ft. addition-room with bathroom, BUILDER UCTION covered porch 221 sq.ft. proposed shed, 169 sq. ft. pergola and new concrete patio with firepit.

9/10/20 B2020-1487 ISSUED 153-340-36 300 VINTAGE RMC CONSTR 100,000 539.92 Reconstruct ADA parking stalls to meet WAY CONSTRUCT UCTION current standards. ORS

9/10/20 B2020-1717 ISSUED 124-295-07 54 ESTRELLA LIC.CONTRAC MINOR 10,500 304.80 Addition of and new WAY T.HIRED BY CONSTR ductwork. OWNER UCTION

9/10/20 B2020-1733 ISSUED 153-031-04 673 ORANGE BEI ELECTRI 14,374 402.53 Install 16 kw back up generator behind AVE CAL garage - WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/10/20 B2020-1822 ISSUED 141-090-43 1199 SIMMONS LIC.CONTRAC MINOR 4,000 475.62 Work w/out permit - Ref # CE-P20-0143 as LN T.HIRED BY CONSTR built fence OWNER UCTION

9/10/20 B2020-1909 ISSUED 132-222-18 5 CONCORD JAJ ROOFING SOLAR 22,000 472.11 New PV & MPU: 6.4 kw sys. 20 panels x CT dba CITADEL 20 Microinverters MPU 125 solar ready PV ROOFING AND SOLA

9/10/20 B2020-1945 FINALED 124-294-20 57 ESTRELLA GHS MINOR 12,610 304.38 Swimming Pool Partial demolition/ 24" WAY LANDSCAPIN CONSTR down from top of copping/drill bottom of G INC UCTION pool all and compact with engeneem fill to top of grade

9/10/20 B2020-1962 ISSUED 153-380-18 229 CLUB DR SUN FIRST ELECTRI 26,000 585.87 Install (2) wall mounted batteries SOLAR CAL

9/10/20 B2020-1979 ISSUED 158-081-04 7 AVOCET CT JAJ ROOFING SOLAR 31,000 613.90 RES Photovoltaic: Roof mount (16) panels dba CITADEL @ 5.12kw(1) powerwall, (1) gateway, (N) ROOFING Subpanel AND SOLA

9/10/20 B2020-1980 FINALED 150-301-01 1145 SIMPLY SOLAR 37,166 573.77 RES Photovoltaic: Flush roof mount (18) CAMBRIDGE SOLAR dba panels @ 5.94kW - (1) battey b/u ST ROCKIN ROOFERS City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/10/20 B2020-1984 FINALED 150-254-04 1220 DENLYN BRIGHT SOLAR 12,240 469.80 RES Photovoltaic: Install (15) roof mount ST PLANET panels @ 6kW (9/17/20 EW) REVISION SOLAR INC RECEIVED - Revision to permit B2020- 1984 Module Type changed from sunpower 400 to Sunpower 360 - kw went rfrom 6 kw to 6.12 kw and Module count went from 15 to 17

9/10/20 B2020-1992 FINALED 124-450-08 24 DOROTHY Eclipse Energy SOLAR 11,000 423.81 Install 4.51 kw solar panels. SPR 410 W WAY & Construction panels with a new 100 amp minimum sub / Solar panel - WUI

9/10/20 B2020-2006 ISSUED 160-461-01 481 ALAMEDA HOME DEPOT WINDOW 12,522 93.73 Replace 1 window & 3 patio doors with DE LA LOMA USA INC., retrofiut vinyl window & patio doors - WUI DBA, THE current standards on right hand side of HOME DEPOT house - WUI

9/10/20 B2020-2023 FINALED 157-331-21 122 HAMILTON Colindres REROOF 60,000 876.29 Tear off existing roof layers install new DR Roofing, Co. modified bitmen membrane as per manufacturers requirement

9/10/20 B2020-2032 FINALED 132-222-16 40 LAURIE DR OWNER- MINOR 1,500 94.44 Replace existing 100 amp main electrical BUILDER ELECTRI w/ new 200 amp panel located on exterior CAL west facing wall @ back of garage City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/10/20 B2020-2040 ISSUED 153-272-17 1144 LEA DR MODERN REROOF 15,600 331.60 ReRoof - House & Garage - T/O existing METHOD and install new underlayment & GAF cool ROOFING CO roof shingles in Charcoal 3200 sq. ft - WUI

9/10/20 B2020-2046 FINALED 140-251-22 5 GOTHIC DR OWNER- CONSTR 50,000 77.90 Final inspection for B-CN2006-1016: 247 BUILDER UCTION sq. ft. addition & interior remodel (see permit record for

9/10/20 B2020-2053 FINALED 132-245-36 2365 DOMINIC BELLOWS MINOR 16,000 184.58 Replace existng FAU & AC in Garage DR PLUMBING, MECHANI Replace existing FAU upstairs in Attic - HEATING & CAL existing condenseris being replaced on side AIR of home (replacement only ) per plans - WUI

9/10/20 B2020-2055 ISSUED 125-343-29 52 WOODLEAF HULBERT MINOR 6,700 158.16 Add AC to the existing furnace CT HEATING AND MECHANI AC CAL

9/10/20 B2020-2056 ISSUED 160-780-21 266 PELICAN HADDON MINOR 10,400 93.23 Replacement - AC and Furnace LN HEATING AND MECHANI Replacement 15 Seer and 80% AFUE - COOLING CAL WUI

9/10/20 B2020-2060 FINALED 151-133-03 21 TRUMAN CAPSTONE REROOF 19,750 399.36 T/O existing roof and install new Lifetime DR ROOFING Class A Compostion shingles, Shakewood color 3400 sq ft - WUI

9/10/20 B2020-2064 ISSUED 125-411-08 42 SPINOSA BELLOWS WATER 1,500 39.90 Replace existing 50G AWH with new50G WAY PLUMBING, HEATER AWH Like for like WUI HEATING & OL AIR City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/11/20 B2020-1678 ISSUED 141-130-21 101 BRYAN DR OWNER- MINOR 2,600 152.74 Remove Wood Burning fireplace. Remove BUILDER CONSTR and replace wood burning stove with gas UCTION freestanding stove

9/11/20 B2020-1814 ISSUED 141-161-51 1135 SEVENTH US DEMO CONSTR 4,500 1,109.14 Work without Permits - Retaining wall ST AND HAULING UCTION replacement at driveway: Replace old wood INC 3' H retaining wall at N side of driveway with 3' H block pavers. Pavers will start at 3' H and end at 6" H. No plumbing, electrical, or mechanical required. No Grading - Per Plans - WUI (reference CE-P20-0170) (9/28/20 JW) REVISION: To increase the number fo steps from 6 to 10

9/11/20 B2020-1934 FINALED 132-231-77 6 GREGOR LN LIC.CONTRAC MINOR 7,000 430.61 Work without permit: Per Energy Form T.HIRED BY CONSTR work description: 16 Windows replaced in OWNER UCTION 2000.

9/11/20 B2020-1973 ISSUED 160-790-29 178 RED CL MINOR 14,000 390.82 Replace Kitchen Cabinets, counter tops HAWK RD CONSTRUCTI CONSTR using existing layout. Add 7 4" lights LED - ON UCTION Replace GFCI Outlet

9/11/20 B2020-2070 FINALED 140-162-17 85 STANFORD Reggie's WATER 2,600 39.90 50 Gal WH, nat gas, standard, .68 CT Reliable HEATER energy,8 WUI Plumbing Ser OL 9/11/20 RP2020-0071 ISSUED 141-101-50 15 PIONEER OWNER- MINOR 2,356 556.87 Work Without Permits: RI2020-0390 - CT BUILDER CONSTR Replace 40 Gallon Water Heater with UCTION Energy Efficiency 50 Gallon Water Heater AOSmith; Replace single pain windows with Dual Pane Windows (4 windows) Extend hot water tank's pressure release valve to the outside of the house to meet regulation - WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/14/20 B2020-1680 ISSUED 141-272-03 1407 GRANT RAKE ELECTRI 3,000 205.81 Electrical connection for portable generator AVE ELECTRIC CAL COMPANY

9/14/20 B2020-1725 FINALED 157-820-27 137 CHAPEL NEXUS SOLAR 18,000 289.48 Installing Roof Mount SOlar PV 5.85 kW HILL RD ENERGY 18 mods SYSTEMS 9/14/20 B2020-1777 FINALED 124-071-48 6 ISABELLA CT JOHN PERRY CONSTR 7,000 242.97 Construct 8 x 15" deck 20" above Grade - CONSTRUCTI UCTION WUI ON

9/14/20 B2020-1791 FINALED 160-392-28 130 COUNTRY ISLAND ELECTRI 2,000 94.44 Upgrade main service panel to 200 amps - CLUB DR ELECTRIC CAL WUI

9/14/20 B2020-1793 ISSUED 143-492-07 50 SAMROSE J & J ELECTRI 13,700 377.72 Provide and install 22 kw air-cooled DR ELECTRIC CAL Generac Generator Series Automatic standby back up powergenerator with 100/200 A Auto Transfer Switch ( ATS ). Installation includes gas and electric hook up ( Max 15' ) all piping, conduit, wiring and final testing andcommissiong. WUI

9/14/20 B2020-1830 FINALED 146-031-02 617 OWNER- MINOR 15,000 94.94 Permit to Final expired Permit B2015-0107: TRUMBULL BUILDER CONSTR As Built 40 gallon water heater,tub/shower AVE UCTION enclosure, kitchen remodel installation of exterior door to master bedroom. New: recessed lighting at living room. Per CE- HI13-0295. SEE ATTACHED COMMENTS City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/14/20 B2020-1849 FINALED 125-600-24 36 PINHEIRO REGAL SOLAR 2,000 683.60 Solar Roof Mount 6.935 kw 19 modules 1 CIR SOLAR Inverter, Battery Bank, New Back Up Sub ELECTRIC INC Panel

9/14/20 B2020-1850 FINALED 125-610-16 213 RANCH CT REGAL SOLAR 9,000 271.93 Solar Roof Mount 3.65kw 10 Modules and SOLAR 1 inverter ELECTRIC INC

9/14/20 B2020-1906 ISSUED 151-142-13 42 BROWN DR BELLOWS MINOR 11,000 320.10 Add New AC to right side of home with a PLUMBING, MECHANI Sound Blanket - Replace existing FaU with HEATING & CAL New High efficiency FAU - WUI AIR

9/14/20 B2020-1986 FINALED 125-311-06 121 MICHELE OWNER- CONSTR 8,600 744.62 Replacing part of the house siding due to CIR BUILDER UCTION Termites before painting - Per Site Plan CE- P20-0175 - WUI (9/11/20 RMO) Also small are of roofing material above front of garage

9/14/20 B2020-1989 ISSUED 160-123-03 29 OLYMPIA ONE STOP MINOR 5,000 534.66 Work w/out permit: New stucco around WAY PLASTERING CONSTR windows and at side of garage Ref# B2020- INC UCTION 1659: Building inspector inspection comments

9/14/20 B2020-2029 ISSUED 143-242-54 2817 TOPAZ Powur Home SOLAR 16,000 399.36 Solar Roof Mount 5.86kW 17 modules, DR Construction New Main Service Panel 225 amps

9/14/20 B2020-2036 ISSUED 132-151-09 97 WESTERN FREEDOM SOLAR 21,922 279.43 Roof Mount Residential Photovoltaic DR FOREVER LLC System 4.640 kW City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/14/20 B2020-2052 FINALED 160-561-33 87 PACHECO RAVEN MINOR 4,800 184.26 Add 5-ton air conditioning system to CREEK DR HEATING AND MECHANI existing AIR CAL CONDITIONIN G

9/14/20 B2020-2063 FINALED 140-211-15 5 PLAZA LOMA MOORE MINOR 7,500 196.08 Replace 8 supply ducts and 1 return HOME MECHANI SERVICES CAL

9/14/20 B2020-2079 ISSUED 141-241-32 1 BURDELL PL HADDON MINOR 7,864 93.23 AC Condenser & Coil Replacement - 16 HEATING AND MECHANI Seer COOLING CAL

9/14/20 B2020-2080 ISSUED 160-591-13 1009 HADDON MINOR 0 93.23 AC Condenser & Coil Replacement - 16 MARGARET CT HEATING AND MECHANI Seer - WUI COOLING CAL

9/14/20 B2020-2081 ISSUED 143-041-23 35 SUMMERS HADDON MINOR 4,849 93.23 Furnace Replacement 80% AFUE AVE HEATING AND MECHANI COOLING CAL

9/14/20 B2020-2082 ISSUED 146-051-02 5 TENAYA LN ONE HOUR MINOR 12,681 93.23 AC Condenser & Coil Replacement - *( AC HEATING & MECHANI Slim Line ) - WUI A/C CAL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/14/20 B2020-2092 ISSUED 151-031-19 17 HAYES ST VALLEY MINOR 7,402 93.23 AC Condenser & Coil Replacement 16 COMFORT MECHANI Seer - WUI HEATING & CAL AIR

9/14/20 RP2020-0073 FINALED 160-551-05 8 ELEGANT OWNER- MINOR 4,800 114.44 Work without Permits: As Built - Furnace TERN RD BUILDER MECHANI Replacement Final B2017-0918 CAL

9/15/20 B2019-2928 ISSUED 153-182-50 1 ROSALIA CT LIC.CONTRAC NEW SFD 1,500,000 38,974.47 NSFD - New split level 4,498 sq. ft.Ref. T.HIRED BY P2019-031 OWNER

9/15/20 B2020-1633 ISSUED 151-137-03 77 Marin Home CONSTR 40,000 1,496.10 Kitchen remodel, upgrade electrical WASHINGTON Remodeling UCTION subpanel,removal of 2 walls and replace ST sliding glass door. (9/10/20 EW) REVISION REQUEST: OMITTING DECK FROM PLANS. THEY ARE NOT WORKING ON THE DECK. (9/14/20 EW) RECEIVED REVISED PERMIT WORKSHEET - Exterior Deck needs to be removed from permit. Customer decideded not to build a new deck.

9/15/20 B2020-1739 FINALED 140-162-17 85 STANFORD OWNER- CONSTR 4,000 219.68 Installation of 12 x 12 prefabricated shed - CT BUILDER UCTION WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/15/20 B2020-1765 ISSUED 146-061-36 3 SUNPOWER SOLAR 15,000 571.25 Install 6.15 kW ( 15 panels ) roof mount PV SADDLEBROO CORPORATIO System + 13 kWh Equinox Storage System K CT N (9/8/20 KDON) Revision: Plans reflecting change to PV Breakers and Storage System Breakers.

9/15/20 B2020-1795 ISSUED 157-502-12 51 DIGITAL DR DEVCON TENANT 75,583 2,667.20 Tenant Improvement to construct two [2] CONSTRUCTI IMPROVE ADA compliant restrooms and remodel ON INC. MENT adjacentspace. Work includes new walls, finishes, doors, plumbing HVAC and electrical. ***(8/20/2020 ML) Work in right- of-way requires Encroachment Permit.***

9/15/20 B2020-1804 FINALED 140-021-28 8 SANTIAGO OWNER- ELECTRI 6,000 277.30 Adding a gas generator to connect to CT BUILDER CAL electrical panel to operate household applicances and lightsduring PG&E power outages.

9/15/20 B2020-1843 FINALED 146-392-08 55 LA COSTA FITZPATRICK' MINOR 11,800 144.24 Install AC and Replace Furnace - WUI CT S HEATING, MECHANI INC CAL

9/15/20 B2020-1852 ISSUED 124-392-14 400 SAN BEI ELECTRI 18,000 465.13 Installation of Back Up Generator on South ANDREAS DR CAL East Side of House - WUI

9/15/20 B2020-1869 ISSUED 132-244-15 10 LIC.CONTRAC MINOR 8,700 455.18 Installing a Cummins Quiet Connect 17kW CHRISTOPHER T.HIRED BY MECHANI generatror. Adding a Lennox 4 Ton AC unit CT OWNER CAL to the currentLennox Furnace and HVAC System - WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/15/20 B2020-2041 ISSUED 157-732-65 14 JAJ ROOFING SOLAR 16,000 341.32 PV - 5.325 kw, 15 panels x 15 RICHARDSON dba CITADEL microinverters. New Cominer Box - no MPU RD ROOFING AND SOLA

9/15/20 B2020-2084 FINALED 141-120-23 1142 SIMMONS RidgeValley REROOF 13,000 280.78 ReRoof Tile - Off to comp on Install Tile LN Roofing Inc 24 CA Cool Roof Shingles - WUI

9/15/20 B2020-2090 ISSUED 124-341-15 125 SAN SIMPLY REROOF 22,265 450.18 ReRoof - 19 squares. Comp shingles GAF MATEO WAY SOLAR dba Timberline HDZ RS Tear off layers - 2 ROCKIN Sloped - WUI ROOFERS

9/15/20 B2020-2095 FINALED 160-840-12 1 BLUE OAK Richard Osorio FURNAC 14,455 93.23 Replace furnace & AC in existing location. CT Heating and Air E AC WUI HVAC OL

9/15/20 B2020-2099 ISSUED 160-452-04 37 BONNIE SAVE MINOR 7,895 196.58 Replace 2 Entry Doors: 1 2 panel with side BRAE DR ENERGY CONSTR Lights & 1 Fire Rated Door in the Garage - COMPANY UCTION WUI (MAAP DBA)

9/15/20 B2020-2102 FINALED 151-142-13 42 BROWN DR BELLOWS WATER 1,500 39.90 Replace existing 50G AWH with new50G PLUMBING, HEATER AWH Like for like WUI HEATING & OL AIR City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/15/20 B2020-2105 ISSUED 150-295-03 567 MIDWAY MCLERAN, REROOF 19,400 399.36 Tear off upper & lower roof sections to BLVD INC. solid sheathing. ReRoof sloped area wikth Class A Shingles -Re-Roof flat area with class A torch down - WUI

9/15/20 B2020-2106 ISSUED 160-840-17 62 AARON DR MCLERAN, REROOF 26,800 509.50 Tear off main roof to solid sheathing. INC. ReRoof with class A Presidential Shingles Color Shadow Grey -WUI

9/16/20 B2020-1401 ISSUED 153-101-17 808 REICHERT LIC.CONTRAC CONSTR 8,400 309.61 Demolition and rebuilding of backyard ( AVE T.HIRED BY UCTION non-attached ) storage shed.WUI OWNER

9/16/20 B2020-1783 ISSUED 150-271-41 1294 OWNER- CONSTR 23,000 1,216.77 Replace retaining wall on North East of CAMBRIDGE BUILDER UCTION property. Old retaining wall was deemed ST unsafe by engineer This is new work

9/16/20 B2020-1903 ISSUED 153-062-01 881 GRANT NOVO TENANT 20,000 1,994.64 Work without building permit: Demolition AVE CONSTRUCTI IMPROVE of 750 sf of interior space on 2nd floor. ON, INC MENT Demolition of 750 sf of interior space on 2nd floor. Partition walls, doors and carpet. In-fill (E) Door openings, scar patch and furr wall @ Confernce room. Electrical relocation only. Plumbing, lighting and HVAC are to remain "as is". New flooring and paint throughout. City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/16/20 B2020-1981 ISSUED 160-020-38 199 POSADA FAIRWAY CONSTR 375,000 3,164.79 Replace Mansard composition shingle DEL SOL DESIGN & UCTION roofing, replace 64 dormer windows, Repair A,B,C,D CONSTRUCTI or replace dormersiding and trim - Bldgs A, ON INC B, C, D Only - WUI

9/16/20 B2020-2012 ISSUED 151-051-32 8 BELLOWS MINOR 4,500 207.86 Add AC to existing FAU in interior closet - WASHINGTON PLUMBING, MECHANI WUI ST HEATING & CAL AIR

9/16/20 B2020-2054 ISSUED 124-211-38 280 SAN OWNER- MINOR 20,000 451.55 Kitchen Remodel - No new windows, FELIPE WAY BUILDER CONSTR plumbing & gas not being moved. No living UCTION space above work area

9/16/20 B2020-2058 FINALED 150-264-16 575 SUNSET NORTHERN SOLAR 17,045 273.18 3.96 kW Residential Roof Mounted PV PKWY PACIFIC Installation ( 12 Modules ) WUI POWER SYSTEMS

9/16/20 B2020-2066 FINALED 160-960-06 172 SOLAR CITY SOLAR 39,115 721.76 Install (36) roof mount solar panels at LAURELWOOD dba TESLA 12.24 kW and 3 energy storage systems to DR back up existingelectrical and 1 inverter. (10/12/20 EW) REVISION: - Panel layout and three line slightly changed. Scope of work still ( 36 ) panels at 12.24 kw and 3 energy storage systems. - No change in valuation

9/16/20 B2020-2094 FINALED 141-287-04 1127 ELM DR OWNER- REROOF 3,000 111.38 ReRoof lower elevation roof BUILDER City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/16/20 B2020-2103 FINALED 143-033-44 630 OLIVE AVE MEIER AND REROOF 18,000 365.48 Tear off existing metal tile and install new SONS plywood, felt, and composition shingles - ROOFING 2,900 sq. ft

9/16/20 B2020-2109 FINALED 157-840-21 18 HAYFORD PERFORMAN REROOF 18,000 365.48 ReRoof - Tear Off Main Residence - Class CT CE ROOFING A Composition Shingle

9/16/20 B2020-2110 FINALED 124-043-15 14 RAMONA KEN COOPER REROOF 16,985 348.54 Remove Shingles and install new Class A WAY ROOFING Fire Rated Material

9/16/20 B2020-2112 ISSUED 157-332-17 111 HAMILTON NORTHGATE REROOF 22,200 450.18 Remove roof and replace DR ROOFING (Patrick Newman

9/16/20 B2020-2113 ISSUED 132-311-47 701 ABEL C MINOR 5,000 94.44 Main Electrical Panel Upgrade - Same for EUCALYPTUS MALDONADO ELECTRI Same location and output - Upgrading to AVE CONSTRUCTI CAL service Panel WUI ON

9/16/20 B2020-2114 FINALED 132-341-38 1 OLIVA DR B SAVE WINDOW 4,431 93.73 Replace 4 windows in-kind with white vinyl ENERGY S 1 TO 8 & WUI glass COMPANY OL (MAAP DBA)

9/16/20 B2020-2116 ISSUED 140-211-28 3 PLAZA HADDON MINOR 10,032 93.23 AC Condenser & Coil Replacement - 16 DEMIRA HEATING AND MECHANI Seer COOLING CAL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/16/20 B2020-2117 FINALED 153-274-05 493 LEA CT ABLE REROOF 17,280 365.48 Remove and replace class A comp shngle ROOFING CO roof - WUI

9/16/20 B2020-2118 FINALED 153-272-20 1150 LEA DR ABLE REROOF 19,335 399.36 Remove and Replace class A comp ROOFING CO Shingle Roof - WUI

9/16/20 B2020-2120 ISSUED 132-321-36 710 SUTRO HADDON MINOR 17,521 93.23 AC Condenser & Coil and Furnace AVE HEATING AND MECHANI Replacement - 14 Seer 96% AFUE - WUI COOLING CAL

9/16/20 B2020-2121 ISSUED 143-432-04 50 Tech Air MINOR 7,000 93.23 Replace existing furnace in garage and AC ROBINHOOD MECHANI in Backyard - No work - WUI DR CAL

9/16/20 B2020-2122 ISSUED 124-071-16 24 SAN LUIS ONE HOUR MINOR 16,000 93.23 , Replacement - CT HEATING & MECHANI A/C CAL

9/16/20 B2020-2124 ISSUED 160-820-14 6 MADRID CT BEST WINDOW 10,982 93.73 Replace Like for Like 5 Windows and 2 EXTERIORS Doors - WUI CONSTRUCTI ON

9/17/20 B2020-0454 ISSUED 155-541-07 6 MUROC TERRASUR CONSTR 50,000 1,230.12 Elevated walkway, framing repair, Bldg. # LAKE DR CORPORATIO UCTION 6. Units - 610, 612, 614, 616, 620, 622, N 624, 626

9/17/20 B2020-1513 ISSUED 124-384-02 446 ESTADO Green Day ELECTRI 6,000 323.20 Generator Installation 22 kw - WUI WAY Power CAL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/17/20 B2020-1810 ISSUED 157-830-27 38 SWAN POOLS POOL 39,500 1,490.82 In ground gunite pool & spa ( 11' x 29' ) MILDENHALL [Venco w/ ST Management Inc.]

9/17/20 B2020-1812 ISSUED 125-450-40 178 SWAN POOLS POOL 44,000 1,563.87 In ground gunite pool & spa (18' x 40') BUTTERFIELD [Venco w/auto cover & gas heater DR Management Inc.]

9/17/20 B2020-1905 ISSUED 152-111-04 1304 A E CONSTR 45,555 1,211.44 Remove & rebuild exterior stairs - no LEAFWOOD CONTRACTO UCTION electrical, plumbing or mechanical work DR R proposed.(10/28/20 EW); REVISION REQUEST RECEIVED: Revision is to the Contractor: Change of Contractor.

9/17/20 B2020-2002 FINALED 124-301-28 425 SAN OWNER- MINOR 5,500 182.80 nstall new tankless water heater in garage - MARIN DR BUILDER MECHANI Moving Locations Per Plans - WUI CAL

9/17/20 B2020-2018 FINALED 150-444-02 765 SUNSET LIC.CONTRAC MINOR 900 115.34 Install dedicated electric line & receptacle PKWY T.HIRED BY ELECTRI from electric panel, along exterior of home, OWNER CAL to new receptacle. Will use 1/2 EMT pipe, using raintight fitting from main service panel, along exterior base of house, to merge at exterior 20 amp bubble cover receptacle, then tie into new 20 amp breaker in the service entrance panel. City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/17/20 B2020-2057 ISSUED 143-511-09 25 WENDY CT OWNER- MINOR 8,260 334.36 Repair/Replace leaking sink and water BUILDER CONSTR damaged countertops - WUI UCTION

9/17/20 B2020-2059 FINALED 143-433-11 61 SUNRUN SOLAR 20,766 429.76 Install (23) roof mounted, PV solar panels ROBINHOOD INSTALLATIO at 7.245kW, (1) ESS, (1) 200A control DR N SERVICES panel, MPD -Replace existing 200A main INC breaker with new 175A 22kW AIC rtd main breaker.

9/17/20 B2020-2111 ISSUED 151-051-17 21 TYLER ST Huffman Solar MINOR 4,000 94.44 Upgrade a 100 A main service panel with a ELECTRI new 125 A Service panel on the fornt of the CAL house - This work is to facilitate the installation on an existing solar permit B2020-1574 - WUI

9/17/20 B2020-2128 ISSUED 157-732-05 15 PRESIDIO INDOOR AIR FURNAC 7,950 93.23 Furnace and AC changeout DR TECHNOLOGI E AC ES HVAC OL

9/17/20 B2020-2134 ISSUED 152-381-11 1119 HOME DEPOT WINDOW 1,630 93.73 Replace 1 window with one retrofit vinyl REDWOOD USA INC., window BLVD DBA, THE HOME DEPOT

9/17/20 B2020-2135 ISSUED 132-183-05 40 SIERRA SIMPLY REROOF 22,725 450.18 ReRoof 31 Squares, Comp Shingle GAF VISTA SOLAR dba Timberline HDZ Tear Off Layers - 1 Roof ROCKIN Pitch 3:13 ROOFERS City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/17/20 B2020-2137 ISSUED 124-271-24 168 SAN Renewal by WINDOW 12,106 93.73 Replacing 1 retrofit window and 1 full frame FELIPE WAY Andersen of SF S 1 TO 8 SD (JEMICO) OL

9/17/20 B2020-2138 ISSUED 143-041-16 605 PLUM ST BENJAMIN WATER 2,300 39.90 REPLACING 40 GALLON GAS WATER FRANKLIN HEATER HEATER. PLUMBING OL

9/17/20 B2020-2141 FINALED 146-164-24 1 IRENE DR Renewal by WINDOW 3,268 93.73 1 RETROFIT LIKE FOR LIKE window sill Andersen of SF S 1 TO 8 height more than 48" WUI (JEMICO) OL

9/17/20 RP2020-0045 ISSUED 124-083-14 29 LAS OWNER- CONSTR 2,499 483.68 Work done w/out permits - Ref # RI2019- TARDES CT BUILDER UCTION 0452:Added electrical branches in garage and exterior (lighting, outlets); Gas fireplace insert; Gas line to dryer; Patio cover with deck approx. 13’ x 22’ x 9’h Demo/alter sideyard overhang (violates setback requirements). WUI

9/18/20 B2020-2146 ISSUED 124-332-01 205 SAN HULBERT MINOR 9,200 257.16 Replace a package unit on the roof - MARIN DR HEATING AND MECHANI Weight of New System 455 Lbs - WUI Old AC CAL weight of unit is 489 lbs.

9/21/20 B2020-1187 ISSUED 141-201-50 1761 GRANT ANELLO CONSTR 40,000 3,504.04 T.I. New Delicatessen at the downtown AVE PAINTING & UCTION Novato CenterA.K.A 1765 Grant Ave CONST. City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/21/20 B2020-1533 ISSUED 141-051-02 504 SAN INFINITY SOLAR 30,000 691.38 RES Photovoltaic: Roof mount (22) panels MARIN DR ENERGY INC @ 7.040kW(1) Tesla battery & derate the main from 200A to 150A

9/21/20 B2020-2088 ISSUED 143-402-21 721 BOLERO OWNER- MINOR 46,800 753.42 Replace 16 windows & 1 Sliding Glass CT BUILDER CONSTR Door. Remove dry rot trim & siding as UCTION needed. Install newexterior siding & Trim with Hardie Style concrete siding. Paint new siding & trim - House 2787 Sq. Ft. WUI (9/21/20 EW) REVISION RECEIVED: Replace 17 Windows/ Siding Square Footage is 2600 Sq. Ft - Replace 17 windows & 1 sliding glass door. Remove dry rot trim & siding. Repair as needed. Install new exterior siding & tri with Hardie Style concrete Siding. Paint New siding and Trim

9/21/20 B2020-2107 ISSUED 153-141-23 710 ALICE ST Sterling REROOF 15,000 314.66 Remove existing composition shingles and Construction, replace with new composition. Reflective Inc series GAFShingles over 30 lb felt - WUI

9/21/20 B2020-2148 ISSUED 132-031-11 870 SUTRO OWNER- MINOR 5,000 145.26 Electrical panel upgrade including PGE AVE BUILDER ELECTRI restringing the main electrical wire for CAL home.

9/21/20 B2020-2149 ISSUED 124-121-54 9 SOS MINOR 3,500 128.32 Replace 100 amp Zinsco main panel in the COTTONWOO ELECTRICAL ELECTRI same location D PL CAL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/21/20 B2020-2150 FINALED 160-511-07 14 EAGLE GAP PETER LEVI WATER 3,118 93.23 Replace 50 gallon water heater in the RD PLUMBING HEATER garage - WUI INC

9/21/20 B2020-2151 ISSUED 160-902-19 526 ENTRADA PETER LEVI MINOR 8,417 94.44 Change out XP14 Lennox Heat Pump, Like DR U 201 PLUMBING MECHANI for Like - WUI INC CAL

9/21/20 B2020-2156 ISSUED 160-531-50 53 FLICKER MOORE MINOR 1,900 94.44 Replace 7 supply ducts - WUI DR HOME MECHANI SERVICES CAL

9/21/20 B2020-2159 ISSUED 146-072-38 35 ONGARO & FURNAC 13,000 93.23 C/O failed furnace and heat pump with new CHARDONNAY SONS E HVAC LN OL

9/21/20 B2020-2161 FINALED 140-141-27 7 GARDEN CT Colindres REROOF 10,000 229.96 ReRoof - Tear off existing roof and install Roofing, Co. new composition shingles as per manufacturers Requirement

9/21/20 RP2020-0070 FINALED 157-800-07 11 OWNER- MINOR 200 115.44 As-Built 4 Ceiling Fans Installed 3 in WOODBRIDGE BUILDER CONSTR upstairs bedrooms and one in upstairs loft WAY UCTION area City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/22/20 B2020-1871 ISSUED 125-510-17 37 NUNES DR SEMPER ELECTRI 39,900 1,133.01 Installation of 3 Telsa Powerwalls, 1 200 A SOLARIS CAL Generation Load Center, 1 200 A Detached Load Center, 1Tesla Back up Gateway and 1 new 200 Main Service Panel - WUI

9/22/20 B2020-1873 ISSUED 143-261-37 690 LIC.CONTRAC MINOR 20,000 469.88 Remodel Masterbath & hall bath. Replace ALBATROSS T.HIRED BY CONSTR (3) window, fixtures, cabinets, flooring DR OWNER UCTION

9/22/20 B2020-1883 ISSUED 140-171-14 15 ORMOND BECKER CONSTR 45,000 1,135.28 Remove wall between bath & den to create CT BUILDER UCTION a larger master bathroom & laundry area Extend small wall area into garage. Move waste lines

9/22/20 B2020-1968 ISSUED 140-251-16 8 GOTHIC DR OWNER- CONSTR 7,500 799.11 Work without permit: Replacing concrete BUILDER UCTION steps. Per Plan. Ref. Case: CE-P20-0026.

9/22/20 B2020-2014 ISSUED 132-301-04 2046 MOORE MINOR 7,250 250.38 Add on 3 Ton A/C to the Left side yard (16 VINEYARD RD HOME MECHANI SEER) and Change Out 96% Furnace SERVICES CAL

9/22/20 B2020-2061 ISSUED 140-171-07 70 ORMOND CAPSTONE REROOF 10,525 246.90 T/O existing roof and install new Lifetime CT ROOFING Class A Composition Shingles HD stone Gray 2300 sq. ft

9/22/20 B2020-2077 ISSUED 132-311-40 2284 Renewal by MINOR 14,907 93.73 Replacing 1 retrofit patio door VINEYARD RD Andersen of SF CONSTR (JEMICO) UCTION City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/22/20 B2020-2085 ISSUED 160-872-45 3 ELMVIEW SOLAR CITY MINOR 14,000 392.76 Install 2 energy storage systems to back WAY dba TESLA ELECTRI up existing electrical WUI CAL

9/22/20 B2020-2086 ISSUED 151-078-09 1435 Eclipse Energy SOLAR 8,000 433.25 Install 3.2 kw roof mount solar with 8 SPR BUCHANAN ST & Construction 400 w Solar Panels -electrical service / Solar upgrade

9/22/20 B2020-2093 ISSUED 160-105-13 165 COUNTRY SIMPLY SOLAR 54,298 610.15 Residential PV Solar, flush roof mount - CLUB DR SOLAR dba Grid tied Battery Back Up 24 panels 8.88 ROCKIN kw - WUI ROOFERS

9/22/20 B2020-2104 FINALED 143-422-20 2 ROBINHOOD NORTHERN SOLAR 26,418 253.18 7.14 kW Residential Roof Mounted PV DR PACIFIC Installation ( 21 Modules ) - WUI POWER SYSTEMS

9/22/20 B2020-2153 ISSUED 141-101-47 1 PIONEER CT OWNER- REROOF 10,000 229.96 Replace roof with Class A shingles - WUI BUILDER

9/22/20 B2020-2157 FINALED 141-032-18 9 JEFFREY CT Reggie's MINOR 1,700 94.44 New Water Service From Meter to House Reliable PLUMBIN Plumbing Ser G

9/22/20 B2020-2166 ISSUED 152-241-69 28 PLUMAS RAVEN FURNAC 4,300 93.23 Replace air conditioning condensing unit, CIR HEATING AND E AC coil AIR HVAC OL CONDITIONIN G City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/22/20 B2020-2167 ISSUED 143-434-02 1 KNOLLTOP VALLEY MINOR 15,960 94.44 Replacements: AC Condenser & Coil & CT COMFORT MECHANI Furnace Replacements 16 seer and 80% HEATING & CAL AFUE - WUI AIR

9/22/20 B2020-2168 FINALED 125-343-17 12 WOODLEAF ONGARO & MINOR 1,700 94.65 Replace 3 duct runs- 50% of ducting- NO CT SONS MECHANI furnace replacement CAL

9/22/20 B2020-2169 FINALED 140-360-24 10 KRISTY CT MS SERVICES MINOR 6,700 94.44 Replace AC and Furnace aka SAME MECHANI DAY AIR CAL CONDITIONIN

9/22/20 B2020-2170 ISSUED 141-252-08 1029 FIFTH ST OWNER- MINOR 13,690 94.44 Replacement - floor heater with forces air BUILDER MECHANI heater & AC unit Same Location CAL

9/23/20 B2020-1515 ISSUED 143-272-07 8 MISTY RD RYDER NEW SFD 557,600 27,752.44 NSFD - Lot 2 Plan 1X B, 3,485 sq. ft - LOT 2 HOMES OF APN is: 143-272-13, 8 Misty Rd.(8/31/20 CALIFORNIA KHA) Deferred Submittal: Truss Calculation INC. submittal for Lot 2 - Plan 1X-B. (9/17/20 KHA) Revised permit worksheet submitted to reflect project valuation of $557,600.00 City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/23/20 B2020-1516 ISSUED 143-272-07 12 MISTY RD RYDER NEW SFD 557,600 27,752.74 NSFD - Lot 3 Plan 1X A, Sq. Ft. 3,485. LOT 3 HOMES OF APN is: 143-272-14; (8/31/20 KHA) CALIFORNIA Deferred Submittal: Truss Calculation INC. submittal for Lot 3 - Plan 1X A. (9/17/20 KHA) Revised permit worksheet submitted to reflect project valuation of $557,600.00

9/23/20 B2020-1517 ISSUED 143-272-07 16 MISTY RD RYDER NEW SFD 438,400 26,449.79 NSFD - Lot 4 Plan 1 B-R, Sq. Ft. 2,740. LOT 4 HOMES OF APN is: 143-272-15 (8/31/20 KHA) CALIFORNIA Deferred Submittal: Truss Calculation INC. submittal for Lot 4 - Plan 1B-R. Refer to B2020-0334 for Truss Calcs. (9/17/20 KHA) Revised permit worksheet submitted to reflect project valuation of $438,400

9/23/20 B2020-1892 FINALED 125-180-80 8141 OWNER- CONSTR 500 143.94 Repair beam rot at the landing near Room REDWOOD BUILDER UCTION 222. BLVD

9/23/20 B2020-1913 ISSUED 153-062-17 922 MACHIN W. BRADLEY CONSTR 175,000 0.00 Install Emergency Generator. No Fee AVE ELECTRIC, UCTION Permit. City of Novato Administrative INC. Offices Project.

9/23/20 B2020-1928 ISSUED 146-130-16 100 SOLAR MINOR 21,000 504.89 Install ( 2 ) Tesla Powerwalls, ( 1 ) Gateway CHAMBERLAIN OPTIMUM INC ELECTRI Unit, ( 1 ) 200 A sub panel,k ( 1 ) 125 A sub AVE CAL panel,( 1 ) 125 A sub panel, and ( 1 ) main breaker derate to 150 A (Existing solar not a part of scope of work) - WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/23/20 B2020-1974 ISSUED 124-251-15 30 SAN COONEY CONSTR 50,000 1,223.27 New support header in Living roomFrame RAMON WAY CONSTRUCTI UCTION for a new electric fireplace. Provide new ON INC counter tops, provide new engineeried flooring.

9/23/20 B2020-2007 ISSUED 150-473-09 509 STONE DR LIC.CONTRAC CONSTR 21,500 602.14 Remove bathrom: vanity/sink, vent fan, T.HIRED BY UCTION toilet, light, tub piping, and tile. Replace with OWNER new itemsand modify tub water piping to meet code. No changes to electrical wiring - per plans - WUI

9/23/20 B2020-2030 FINALED 143-321-18 820 J & J ELECTRI 32,200 667.67 Install (1) 20kWh battery, (1) Empower ALBATROSS ELECTRIC CAL smart switch(1) remote monitoring system DR

9/23/20 B2020-2047 ISSUED 157-810-50 63 MAYBECK DIVINE MINOR 8,000 217.48 Install new manual transfer switch and a ST ELECTRIC CONSTR new sub-panel control by the new transfer UCTION switch This is set up for portable generator only. seperate approval and permit for any mounted generator.

9/23/20 B2020-2087 ISSUED 143-242-42 2711 TOPAZ OWNER- MINOR 25,000 1,131.40 Work without permit: New Siding and Paint DR BUILDER CONSTR - 852 Sq. Ft to be replaced - Reference: UCTION CE-P20-0180WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/23/20 B2020-2098 ISSUED 152-402-16 77 OWNER- MINOR 5,000 217.27 Bath Remodel - Replacing failed fiberglass BIRCHWOOD BUILDER CONSTR tub/shower surround with new acrylic pan DR UCTION existing drain,new low flow toilet to replace old 6 gal toilet; new faucets on existing lavatory and thermostatic / pressure valve on shower to code. Add fan and LED lighting, switches to do that. Existing 20A GFCI outlets to stay and add 1 for future bidet seat.

9/23/20 B2020-2129 ISSUED 160-581-13 25 CLAY CT OWNER- MINOR 2,000 129.94 Replace Wood Siding Outside of Stairs. BUILDER CONSTR New hot water heater UCTION

9/23/20 B2020-2154 ISSUED 141-252-08 1029 FIFTH ST OWNER- REROOF 10,370 246.90 Replace damaged roof on house ( 850 Sq BUILDER ft ) and garage ( 344 sq ft )

9/23/20 B2020-2176 ISSUED 141-211-17 1025 EIGHTH MODERN REROOF 10,550 246.90 T.O Existing Roof. Install new solo versa ST METHOD shield and FR Sheet and a cool roof 60 mil ROOFING CO pvc - WUI

9/23/20 B2020-2178 ISSUED 140-221-10 28 LAUREN HADDON MINOR 11,593 94.44 AC Condenser & Coil and Furnace AVE HEATING AND MECHANI Replacemenrt 16 Seer and 80% AFUE COOLING CAL

9/23/20 B2020-2179 FINALED 146-164-34 25 NANCY DR ZARAGOZA MINOR 2,500 111.38 Replace existing domestic water line from PLUMBING PLUMBIN meter to the house approx 30' - 1' apart - G WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/23/20 B2020-2181 ISSUED 140-460-53 848 DIABLO HADDON MINOR 11,597 93.23 Replacement - AC Condenser & Coil and AVE 3 HEATING AND MECHANI Furnace Replacement - 16 seer & 96% COOLING CAL AFU

9/23/20 B2020-2182 ISSUED 146-020-57 11 CASUAL CT AAERO HTG. FURNAC 7,438 93.23 Replacement - Air Conditioner WUI & SHEET E AC METAL INC. HVAC OL

9/23/20 B2020-2183 ISSUED 160-092-08 85 FAIRWAY ONGARO & FURNAC 11,000 93.23 Replace furnace and AC, like for like WUI DR SONS E AC HVAC OL

9/23/20 B2020-2184 FINALED 146-452-04 2 BROOKE DR ONGARO & WATER 1,900 39.90 Replace 50 gallon water heater, like for like SONS HEATER WUI OL

9/23/20 B2020-2186 ISSUED 160-131-05 60 CAPILANO ONGARO & FURNAC 6,500 93.23 Replace AC, like for like WUI DR SONS E AC HVAC OL

9/23/20 B2020-2189 ISSUED 125-313-27 240 MICHELE BENJAMIN MINOR 4,500 145.26 Repiping Drain Lines in home - Replacing CIR FRANKLIN PLUMBIN existing - WUI PLUMBING G

9/23/20 B2020-2200 ISSUED 125-312-20 217 MICHELE ALL FURNAC 8,900 93.23 Install new ac WUI CIR WEATHER E AC HTG & HVAC OL COOLING City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/24/20 B2020-1356 ISSUED 140-171-48 15 VICTOR CT DEMELLO REROOF 18,620 382.42 Tear off existing built up roofing. Install ROOFING, new class comp shingle Charcoal color - INC. WUI

9/24/20 B2020-2067 ISSUED 146-211-25 50 HALF LIC.CONTRAC MINOR 7,500 220.18 Add sink & laundry (220V service) hook MOON RD T.HIRED BY CONSTR ups to room. Sink & Laundry to attach to OWNER UCTION existing sewer ejector pump. (ref#: B2020- 1833). WUI

9/24/20 B2020-2073 FINALED 160-511-20 1 EAGLE GAP LIC.CONTRAC MINOR 5,000 1,905.18 Work w/o Permits: 2 Bath remodels, RD T.HIRED BY CONSTR Tankless Water Heater, added electrical in OWNER UCTION garage,lighting in bedrooms, and sub panel. WUI. refer RI2020-0428

9/24/20 B2020-2075 ISSUED 124-383-06 484 ESTADO JETSON ENT MINOR 30,000 422.54 Master & Hall Bath Remodels. No Layout WAY DBA MHR CONSTR change. CONST UCTION

9/24/20 B2020-2108 FINALED 132-182-03 24 GRANDE THOMPSON MINOR 2,000 94.44 Complete replace of electric service with VISTA ELECTRIC ELECTRI new 200 AMP Service. New panel to be CAL installed inexisting locaton on back side of the house. Install new larger service lateral conduit through existing roof penetration. Existing overhead PG&E feed wire to remain - WUI. **COA: Must provide working clearance. LVazquez** City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/24/20 B2020-2136 ISSUED 132-183-05 40 SIERRA SIMPLY SOLAR 30,544 287.93 Residential PV solar, flush roof mount, grid VISTA SOLAR dba tied, battery back up 13 Panels 4.29 kw ROCKIN ROOFERS

9/24/20 B2020-2140 ISSUED 160-872-70 24 PALMER DR NORTHERN SOLAR 19,320 253.18 RES Roof Mounted PV Installation ( 14 PACIFIC modules ) @ 4.83kW ROOFING INC

9/24/20 B2020-2143 FINALED 153-045-21 1016 MACHIN MODERN REROOF 8,900 94.44 Expired Permit - B2019-2143 - ReRoof AVE METHOD with new underlayment and GAF Cool Roof ROOFING CO Shingles -

9/24/20 B2020-2203 ISSUED 152-381-37 31 BENJAMIN WATER 2,100 39.90 REPLACING 40 GALLON GAS WATER BRIARWOOD FRANKLIN HEATER HEATER WUI CT PLUMBING OL

9/24/20 B2020-2206 FINALED 143-331-12 2521 LAGUNA ADAMS FURNAC 14,000 93.23 REPLACE FURNACE AND AC SYSTEM VISTA DR REFRIGERATI E AC WUI ON SERVICE HVAC OL

9/24/20 RP2020-0072 FINALED 150-502-02 553 STONE DR OWNER- MINOR 1,500 316.44 Work Without Permits: Re: RI2020-0414 - BUILDER ELECTRI Sub Panel Replacement in Garage & CAL added electrical branch at right exterior sideyard for lighting - WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/24/20 RP2020-0075 FINALED 160-314-06 4 WINGED OWNER- MINOR 8,400 891.32 Work w/out permits: Hot water heater (in FOOT DR BUILDER CONSTR garage) Back yard pond electrical; hall UCTION bathroom. Ref# RI2020-0411

9/24/20 RP2020-0079 FINALED 153-232-01 17 LAWRENCE LIC.CONTRAC MINOR 5,000 493.76 Work without Permits: RI2020-0380 - DR T.HIRED BY CONSTR Subpanel replaced in closet, added OWNER UCTION lights/ceiling fans ( 5) invarious locations in home, added elecrtrical branches at exterior garage for outlets and lighting / hot tub - WUI

9/25/20 B2020-1676 ISSUED 151-092-05 1408 NEXUS SOLAR 17,500 519.76 RES Photovoltiac: Roof mount (11) CAMBRIDGE ENERGY moduels @ 3.57kW Installing (1) Tesla ST SYSTEMS Powerwall 5kW; 13.5kwH; Derating main breaker from 200amp to 175 amp

9/25/20 B2020-1805 ISSUED 153-272-07 1141 BENGA ELECTRI 9,911 460.01 Installation of a permanently mounted MCCLELLAND CONSTRUCT., CAL 16kW Generac standby, whole house, back DR J BENGA upgenerator connected to gas meter and GROUP INC. electric meter disconnected panel. (9/16/20 EW) REVISED PLANS DUE TO PLAN CHECK LETTER - Plans should show the addition and sound dampening. ***COA: Installation of ZombieBox noise enclosure as shown on plans is required. KZitelli****

9/25/20 B2020-1927 ISSUED 146-071-41 66 SHIELDS LN OWNER- MINOR - 94.94 Permit to Final expired permit B2018-1145: BUILDER CONSTR 581 sq. ft. addition for Great room& storage UCTION 9/11/18 Revision-Foundation brackets, trusses to rafters (roof) (12/12/20 JP) Revision- Main Service Panel upgrade 200 AMP. City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/25/20 B2020-2043 FINALED 160-451-08 35 BAYWOOD RAVEN MINOR 10,900 305.90 Add 4-Ton Air Conditioning System to CIR HEATING AND MECHANI existing heating system, Install 1-ton AIR CAL ductless mini-split heat***COA: Heat pump CONDITIONIN and condenser to meet 20' ft. setback as G per site plan. LVazquez.***

9/25/20 B2020-2071 ISSUED 132-103-09 68 BACA VISTA UNTITLED MINOR 20,000 232.27 Bathroom Remodel LABS INC CONSTR UCTION 9/25/20 B2020-2144 FINALED 160-091-02 160 FAIRWAY Eclipse Energy SOLAR 22,000 308.02 Install 9.02 kw roof mount solar with 22 DR & Construction SPR 410 Watt modules and a new 100 / Solar AMP minimum loadingCenter - WUI

9/25/20 B2020-2147 ISSUED 124-161-11 248 SAN SOLAR CITY SOLAR 26,075 627.69 RES Photovoltaic: Install (24) roof mount RAMON WAY dba TESLA sloar panels @ 8.16kW & 1 inverter(2) energy storage systemes to back up existing electrical. (11/4/20 KDON) Revision: Slight site plan and three line drawing change. Install 24 panels at 8.16kW and 2 Energy Storage System

9/25/20 B2020-2210 ISSUED 132-245-08 2351 DOMINIC GENE BURCH FURNAC 12,040 93.23 replace furnace/ac with new one in same DR PLUMBING & E AC location WUI HEATING HVAC OL

9/25/20 B2020-2214 ISSUED 146-032-37 11 SINALOA AMERICAN WINDOW 1,511 93.73 Manufacture and Install 1 Window CT WINDOW S 1 TO 8 SYSTEMS OL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/28/20 B2020-1922 ISSUED 160-970-28 7 W HERB'S POOL CONSTR 113,095 2,050.40 Install a new in-ground pool that is 16' x 27' BARBERRY PL SERVICE UCTION with a section of raised bond bema and an automaticsafety cover - WUI (11/2/2 KDON) Revision: (2) 12 x 12 x 30 columns to be added to raised bond beam. (2) grand effects Fire/Water Elements Corinthian Bowls will be installed on top of columns

9/28/20 B2020-1941 ISSUED 157-910-01 16 ASHLAND VIVINT SOLAR SOLAR 15,730 509.87 Install 22 Panel PV Roof Mount System DR DEVELOPERS 7.150kw PV Battery Storage LLC

9/28/20 B2020-1958 ISSUED 151-077-12 455 ARTHUR Alvarado MINOR 50,000 3,816.47 Work without permits: CE-P20-0126 - ST Construction CONSTR Kitchen and two bathroom remodel - like for UCTION like - LED Lightingin living room and kitchen. Replace sub panel to make space for kitchen circuit breaker. Water Heater, windows, retaining wall removed. **COA: Applicant to apply for separate building permit for 'as built' addition behind the garage prior to final inspection of this building permit.**

9/28/20 B2020-2025 ISSUED 160-872-20 24 TAN OAK LIC.CONTRAC MINOR 7,500 367.12 Installation of new direct vent zero WAY T.HIRED BY CONSTR clearance gas fireplace. Installation of EV OWNER UCTION charging outletin garage

9/28/20 B2020-2027 ISSUED 143-402-23 713 BOLERO J & J MINOR 33,900 663.80 Install ( 9 ) LG Neon LG335N1C-V5 CT ELECTRIC ELECTRI inverter. ( 9 ) Enphase IQ7Plus 72 ACM- CAL us,k Branch details, 1 x 9enphase branch storage system (1) enphase encharge 3 battery encahrge 3 1p na - Per Plans - WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/28/20 B2020-2042 ISSUED 124-251-24 44 SAN PETER LEVI MINOR 11,080 93.73 3 ton 17 seer AC Change Out ( RAMON WAY PLUMBING MECHANI Replacement ) in Left Side Yard INC CAL

9/28/20 B2020-2048 FINALED 141-081-62 2010 FELIZ RD J. H. OLSEN MINOR 1,000 253.16 Replace 2 x 6 deck boards with trex CONSTRUCTI CONSTR decking. ON UCTION

9/28/20 B2020-2089 ISSUED 152-210-05 301 NORTH BAY WINDOW 5,000 93.73 Replace 2 windows like for like CAPETOWN HANDYMAN CT

9/28/20 B2020-2139 ISSUED 153-031-14 674 ORANGE Eclipse Energy SOLAR 24,000 405.06 Install 8.0kW roof mount solar with 22 SPR - AVE & Construction G-A400-G-AC panels and upgrade main / Solar service panel to AMP with a 100 Amp OCPD

9/28/20 B2020-2158 FINALED 141-287-04 1127 ELM DR Eclipse Energy SOLAR 18,000 268.18 Install 7.38kW Roof Mount Solar with 18 & Construction SPR 410 Watt Modules / Solar

9/28/20 B2020-2165 FINALED 140-241-53 9 HARRIS HILL SEMPER REROOF 34,409 607.27 Remove & dispose of existing roofing DR SOLARIS material. Re-Flash pipes, install gutters and downspouts, vent to code - WUI

9/28/20 B2020-2196 ISSUED 160-551-17 32 CURLEW OWNER- MINOR 47,000 753.42 Replacement of 17 Windows; WAY BUILDER CONSTR Replacement of 2 Patio Sliding Doors; 1500 UCTION sq ft siding replacement including Tyvek, insulation, battons, and trim boards - WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/28/20 B2020-2211 FINALED 140-181-42 18 VILLA R P C REROOF 16,000 331.60 Remove old Roofing materials and install MARIA CT ROOFING new composition shingles

9/28/20 B2020-2223 FINALED 157-732-24 182 EMERSON RAVEN FURNAC 10,900 93.23 Replace furnace, A/C condensing unit & AVE HEATING AND E AC coil AIR HVAC OL CONDITIONIN G

9/28/20 B2020-2224 ISSUED 151-136-05 15 BROWN DR BENJAMIN WATER 2,200 39.90 REPLACING 40 GALLON GAS WATER FRANKLIN HEATER HEATER WUI PLUMBING OL

9/28/20 B2020-2226 ISSUED 160-332-17 6 NORTHWEST WINDOW 9,854 93.73 Replace 1 patio door and 6 windows all CARNOUSTIE EXTERIORS, retrofit, like for like WUI DR INC.

9/28/20 B2020-2233 FINALED 160-531-32 20 AAERO HTG. FURNAC 6,833 93.23 Replaced Air Conditioner WUI HUMMINGBIRD & SHEET E AC WAY METAL INC. HVAC OL

9/28/20 B2020-2234 ISSUED 132-302-07 1 ENA CT OWNER- REROOF 12,000 263.84 ReRoof BUILDER City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/28/20 B2020-2236 ISSUED 132-223-63 739 KENDON ONGARO & WATER 1,800 39.90 Replace failed 50 gal WH with new 50 gal LN SONS HEATER WH OL

9/29/20 B2020-0599 ISSUED 124-323-11 495 SAN Evenich CONSTR 90,000 2,212.16 Repair & alterations to kitchen area,plus MARIN DR Construction UCTION accessible upgrade Inc

9/29/20 B2020-1621 FINALED 153-061-13 7300 ABLE CONSTR 85,000 1,737.12 Replace (4) Wayne Ovation 2 gasoline REDWOOD MAINTENANC UCTION dispensers BLVD E INC

9/29/20 B2020-1902 ISSUED 146-460-09 11 BROOKE Kristine ELECTRI 15,000 430.88 Install 2 Tesla 13.5 Powerball 2 Batteries - DR Durham - CAL WUI INFINITY ENERGY INC

9/29/20 B2020-1991 FINALED 141-120-23 1142 SIMMONS Eclipse Energy SOLAR 24,000 303.18 Install 9.8 kw roof mount solar 24 SPR 410 LN & Construction W modules with a new minimum 100 amp / Solar sub panel - WUI

9/29/20 B2020-2000 ISSUED 140-331-94 1677 HILL RD ADAMS MINOR 7,800 239.58 Install AC to existing heating system. REFRIGERATI MECHANI Install 16 seer system - WUI ON SERVICE CAL

9/29/20 B2020-2019 ISSUED 153-272-08 1139 BENGA MINOR 11,062 382.84 Installation of a permanently mounted 20 MCCLELLAND CONSTRUCT., ELECTRI 20 kw generac standby, wholehouse, back DR J BENGA CAL up generator connected to gas meter and GROUP INC. electric meter disconnect panel - WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/29/20 B2020-2024 ISSUED 160-561-42 9 BUCKEYE CT BELLOWS MINOR 5,500 224.60 Add AC to existing furnace in the garage - PLUMBING, MECHANI Seer 16 - WUI (11/3/20 EW) RECEIVED HEATING & CAL REVISION REQUEST. Replace existing AIR FAU in garage with new AFU 96% - No Change in Cost

9/29/20 B2020-2050 FINALED 146-460-16 12 BROOKE ONGARO & MINOR 7,000 248.19 Add New AC in Side Yard - WUI DR SONS MECHANI CAL

9/29/20 B2020-2145 FINALED 160-840-20 67 AARON DR OWNER- CONSTR 200 155.14 Repairs to retaining wall as per engineers BUILDER UCTION report. Ref# CE-C19-0325

9/29/20 B2020-2198 ISSUED 150-591-05 102 INDIAN THOMPSON MINOR 2,000 94.44 Complete replacement of electric service HILLS DR ELECTRIC ELECTRI with new 125 Amp Service. New panel to CAL be installed in existing locatoin on right side of garage. Existing PG&E underground feed to remain - WUI

9/29/20 B2020-2216 ISSUED 160-461-10 75 PEBBLE KLJ ELECTRIC MINOR 3,000 111.38 Replace existing 125amp underground BEACH DR ELECTRI electric service with new. CAL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/29/20 B2020-2232 ISSUED 160-644-14 1256 MOORE WATER 1,800 39.90 50 Gallon Water Heater tanked, gas HIGHLAND DR HOME HEATER SERVICES

9/29/20 B2020-2245 ISSUED 151-073-09 515 ARTHUR FAST WATER WATER 2,611 39.90 Remove/replace gas water heater. ST HEATER COM- HEATER FWH AQUIC. OL CO. LLC

9/29/20 B2020-2246 ISSUED 141-061-19 901 SIMMONS FAST WATER WATER 1,808 39.90 Remove/replace gas water heater. WUI LN HEATER COM- HEATER FWH AQUIC. OL CO. LLC

9/29/20 B2020-2248 ISSUED 125-390-02 30 ALYSSUM FAST WATER WATER 1,694 39.90 Remove/replace gas water heater. WUI CT HEATER COM- HEATER FWH AQUIC. OL CO. LLC

9/29/20 B2020-2249 ISSUED 146-392-05 25 LA COSTA HOME DEPOT WINDOW 4,323 93.73 Replace 7 windows with retrofit vinyl CT USA INC., windows - WUI DBA, THE HOME DEPOT

9/29/20 B2020-2250 ISSUED 124-272-03 179 SAN HOME DEPOT WINDOW 3,324 93.73 Replace 1 Patio Door with Retrofit Vinyl FELIPE WAY USA INC., Patio Door DBA, THE HOME DEPOT City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/29/20 B2020-2251 ISSUED 125-313-01 140 MICHELE BENJAMIN MINOR 7,800 196.08 Drain Line Re-Pipe Replacing Existing - CIR FRANKLIN PLUMBIN WUI PLUMBING G

9/29/20 B2020-2257 ISSUED 143-402-21 721 BOLERO LIC.CONTRAC REROOF 16,200 348.54 Re-Roof front half of roof & garage. CT T.HIRED BY Remove existing roofing/install new. OWNER Removegutters/install new gutters, downspouts & mesh gutter screens - WUI

9/29/20 B2020-2258 FINALED 125-450-36 183 Grier Argall WATER 8,145 39.90 Replace 50 gallon hot water heater WUI BUTTERFIELD HEATER DR OL

9/29/20 RP2020-0077 FINALED 143-322-04 40 CIRCE CT OWNER- CONSTR 8,000 691.78 Work without Permits: Remodel master BUILDER UCTION bathroom - Replaced claw foot tub and shower with tile in shower. Replaced sinks/counter tops on existing vanities. Replaced window in shower area with new window. Replaced Lighting over sinks - Reference RI2020-0077 - WUI

9/30/20 B2020-1493 ISSUED 150-542-23 735 TOM MINKA CONSTR 45,000 900.98 Kitchen remodel. Demo to bare studs, ARLINGTON UCTION structural framing to add, relocate and CIR remove windows anddoors. New sheetrock, cabinets, appliances, countertops, and flooring installs. WUI City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/30/20 B2020-1716 ISSUED 141-130-60 3 BEYER CT Anderholm ELECTRI 27,493 845.17 Add 22 kw Generac Whole House Electric CAL generator with 200 amp transfer switch. 10 kw generac whole house generator with 100 amp transfer switch -WUI

9/30/20 B2020-2035 FINALED 124-301-28 425 SAN LIC.CONTRAC MINOR 3,500 229.57 Install New AC "SuitCase" unit on garage MARIN DR T.HIRED BY MECHANI exterior wall in front courtyard. Old AC has OWNER CAL been removed.New furnace and ducting already installed. Just need to run power and connect to furnace - Per plans - WUI (10/6/20 EW) REVISION REQUEST RECEIVED. Revision to B2020-2035 - Alternative location proposed - All other specs and previously approved items on permit remain the same - No change in cost

9/30/20 B2020-2142 FINALED 132-351-09 120 OLIVA CT PACIFIC MINOR 10,000 241.02 Replacing bathtub with new tub. Replacing D RESTORATIO CONSTR shower faucets. Replace ventaliation fan. N INC dba UCTION Replace 2 vanities with sink & lighting, P Trap, Supply Line - Per Plans - WUI

9/30/20 B2020-2191 ISSUED 124-420-25 61 SANDY SUNRUN SOLAR 16,680 471.01 Install ( 17) roof mounted, PV Solar panels CREEK WAY INSTALLATIO at 5.35 kw, (1) ESS , and (1) 200 a control N SERVICES panel - WUI INC

9/30/20 B2020-2192 ISSUED 140-091-74 17 ROSE SUNRUN SOLAR 23,000 580.15 Install ( 16 ) roof mounted, PV Solar panels STONE WAY INSTALLATIO at 5.04 kw, ( 2 ) ESS, and ( 2 ) 200a Control N SERVICES Panels INC City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/30/20 B2020-2194 ISSUED 141-130-70 3 ANNA CT SUNRUN SOLAR 21,580 471.01 Install ( 23 ) roof monted , PV Solar panels INSTALLATIO at 7.935 kw, ( 1 ) ESS, (1) 200 a central N SERVICES panel, and MBD - Replace existing 200 a INC with new 175 a 22k AC RTD Main Breaker - Per Plans - WUI

9/30/20 B2020-2221 ISSUED 150-284-08 1150 PETER LEVI MINOR 6,500 179.14 Replace water piping to 2 Tub/Showers CAMBRIDGE PLUMBING PLUMBIN and 2 Toilets ST INC G

9/30/20 B2020-2239 ISSUED 160-392-23 23 BRASSIE PETER LEVI MINOR 9,650 93.23 2 Ton AC Change Out Left side of yard - CT PLUMBING MECHANI Like for Like - WUI INC CAL

9/30/20 B2020-2244 ISSUED 152-071-19 75 SEQUOIA Decarli MINOR 25,805 318.79 Replace 3 windows that have blown seals. GLEN LN Construction CONSTR Replace dry rott siding with New. Incuding UCTION plywood sheer ply OSB and TYVEX. South and east elevation Repair Only - WUI

9/30/20 B2020-2254 ISSUED 140-292-01 1524 HILL RD NEW CAP REROOF 20,000 399.36 Tear Off existing roof and replace with Bldg. 1514 U 41 ROOFING Class A shingles. No Structural Changes - 50 Bldg. 1514 - Units 41 - 50

9/30/20 B2020-2259 FINALED 141-212-06 1032 EIGHTH NOVATO WINDOW 1,900 93.73 Replacement Windows WUI ST GLASS, INC. S 1 TO 8 OL City of Novato Issued Building Permit Report: September 1 - September 30, 2020 Issue Valua- Permit No. Status Parcel # Site Address Contractor Type Total Fees Description Date tion 9/30/20 B2020-2266 ISSUED 125-380-03 114 ARONIA Baier Heating FURNAC 5,700 93.23 We are replacing existing furnace. LN and Air E HVAC Conditioning, OL Inc