Resettlement Planning Document

Document Stage: Final Project Number: 40683 August 2010

PRC: Risk Mitigation and Strengthening of Endangered Reservoirs in Province Project

Final Resettlement Plan for Muyu Reservoir Subproject in Laiyang City (English)

Prepared by the Shandong Provincial Government.

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Laiyang City Muyu Reservoir Risk Mitigation Project

Under

Risk Mitigation of Endangered Reservoir Project in Shandong Province

Of

The People’s Republic of

Resettlement Plan

Water Resources Design and Research Institute of Shandong Province December 2009

Letter of Endorsement

Laiyang City Water Resources Department (LCWRD) received the approval of constructing the Risk Mitigation of Muyu Reservoir Project in Laiyang City from the related departments. This Project is proposed to be started in December 2009, and completed by November 2010. Laiyang City Government, through Ministry of Finance, has requested a loan from the Asian Development Bank (ADB) to finance part of the Project. Accordingly, the Project will be implemented in compliance with ADB social safeguard policies. This Resettlement Plan (RP) represents a key requirement of ADB and will constitute the basis for land acquisition and resettlement. The RP fully complies with requirements of the relevant laws, regulations and policies of the People’s Republic of China (PRC), Shandong Province and Laiyang City Government as well as complies with ADB’s policy on involuntary resettlement. Laiyang City Government and LCWRD hereby affirm the contents of this Resettlement Plan prepared dated in October 2009 and ensures that the resettlement will be made available as stipulated in the budget. LCWRD has discussed the draft resettlement Plan with relevant local officials and has obtained their concurrence. Laiyang City Muyu Reservoir Project Management Bureau under Laiyang City Government was authorized as the responsible agency to manage the implementation of the Project and related resettlement activities.

Governor, Laiyang City Government

______(signature)

______(date)

Abbreviation ADB Asian Development Bank AHs Affected Households APs Affected Persons EA Executing Agency EIA Environmental Impact Assessment FSR Feasibility Study Report IA Implementing Agency IMA Independent Monitoring Agency LLAB Laiyang Land Administration Bureau LAR Land Acquisition and Resettlement LCG Laiyang City Government LCWRD Laiyang City Water Resources Department M&E Monitoring and Evaluation MRPMB Muyu Reservoir Project Management Bureau PMO Project Management Office PPTA Project Preparatory Technical Assistance PRC People’s Republic of China RP Resettlement Plan SPMO Shandong Project Management Office SES Socioeconomic Survey TA Technical assistance TOR Terms of reference

Table of Contents

EXECUTIVE SUMMARY ...... 1 1. INTRODUCTION ...... 2 1.1 PROJECT BACKGROUND ...... 2 1.2 PROJECT DESCRIPTION ...... 3 2. IMPACTS OF LAND ACQUISITION AND RESETTLEMENT ...... 6 2.1 MEASURES TAKEN TO AVOID OR MINIMIZE LAR IMPACTS ...... 6 2.2 PHYSICAL INDICES SURVEY ...... 6 2.3 SCOPE OF LAND ACQUISITION AND RESETTLEMENT ...... 6 3. SOCIO-ECONOMIC PROFILE IN AFFECTED AREAS ...... 8 3.1 SOCIO-ECONOMIC PROFILE OF LAIYANG CITY ...... 8 3.2 SOCIO-ECONOMIC PROFILE OF AFFECTED TOWNSHIP ...... 8 3.3 SOCIO-ECONOMIC PROFILE OF AFFECTED VILLAGE ...... 8 3.4 SOCIO-ECONOMIC SITUATION OF AFFECTED HOUSEHOLDS ...... 9 3.4.1 Population Distribution by Age ...... 9 3.4.2 Population Distribution by Education ...... 9 3.4.3 Productive Resources ...... 10 3.4.4 Household Annual Income and Expenditure ...... 10 4. POLICY FRAMEWORK, ENTITLEMENT AND COMPENSATION ...... 12 4.1 APPLICABLE LAWS, REGULATIONS & POLICIES FOR RESETTLEMENT ...... 12 4.2 OBJECTIVES AND PRINCIPLES OF RESETTLEMENT ...... 12 4.3 ELIGIBILITY OF COMPENSATION...... 12 4.4 COMPENSATION STANDARDS ...... 13 4.4.1 Compensation Standards for Permanent Land Acquisition ...... 13 4.4.2 Compensation Standards for Attachments ...... 13 4.5 ENTITLEMENT ...... 13 5. REHABILITATION MEASURES ...... 15 5.1 OBJECTIVES OF RESETTLEMENT ...... 15 5.2 REHABILITATION PLAN FOR PERMANENT LAND ACQUISITION ...... 15 5.2.1 Rehabilitation Plan for Affected Households ...... 15 5.2.2 Rehabilitation Measures of the Affected Village ...... 15 5.3 TRAINING FOR THE AFFECTED PERSONS ...... 16 5.4 JOB OPPORTUNITIES FROM THE PROJECT ...... 16 5.5 INCOME RESTORATION PLAN OF WOMEN ...... 16 6. COST ESTIMATE AND IMPLEMENTATION SCHEDULE ...... 17 6.1 RESETTLEMENT COST ...... 17 6.2 MANAGEMENT AND DISBURSEMENT OF RESETTLEMENT FUNDS ...... 17 7. POST-RESETTLEMENT PROGRAM FOR RESETTLERS IN RESERVOIR AREA ...... 19 7.1 BACKGROUND AND REMAINING ISSUES...... 19 7.2 POST-RESETTLEMENT SUPPORT APPROACHES ...... 19 7.3 POST-RESETTLEMENT SUPPORT IN RESERVOIR AREA ...... 20 8. IMPLEMENTATION SCHEDULE ...... 21 9. PUBLIC PARTICIPATION AND GRIEVANCE REDRESS ...... 22 9.1 PUBLIC PARTICIPATION ...... 22 9.2 GRIEVANCE PROCEDURE ...... 22 10. INSTITUTIONAL ARRANGEMENT ...... 24

10.1 RESPONSIBLE INSTITUTIONS FOR RESETTLEMENT IMPLEMENTATION ...... 24 10.2 TRAINING PLAN FOR RESETTLEMENT MANAGEMENT STAFF ...... 24 11. MONITORING AND EVALUATION ...... 26 APPENDIX 1 APPLICABLE LAWS AND REGULATIONS ...... 27 APPENDIX 2 TERMS OF REFERENCE FOR EXTERNAL MONITORING ...... 32

Executive Summary

Muyu Reservoir was constructed in May1958. In July1960, the main engineering works were finished and started to store water and produced benefit. Since Muyu Reservoir was built during the period of Great Leap Forward, there are many serious safety problems of the dam, spillway, and diversion tunnel. Therefore, it is urgent to carry on the risk mitigation and strengthening and reinforcement of Muyu Dam and Reservoir, eliminate all kinds of dangers in the project in order to make it operate normally, and perform its proper economic benefits and social benefits of flood prevention, irrigation, the urban water supply and so on.

Based on the field survey for Construction Map Design (CMD), no inundation impacts are caused by the Project. However, the land requisition of the flood control road with the length of 470m will acquire 15.2 mu land permanently, including 2.6 mu orchard and slope wasteland 12.6 mu. The slope wasteland is the collective owned land of Muyu Village. The permanent land acquisition of 2.6 mu of orchard will affect 11 households with 41 persons. The other engineering construction organization activities are all within the scope of reservoir management and only affects the ground attachment of some lotus trees owned by the Reservoir Administration Bureau. The total cost for land acquisition and resettlement is CNY 222,189.

According to the “Notice on the Adjustment of Land occupying Annual Production And Compensation Standard, which is forwarded by General Office of Shandong Provincial People’s Government, and issued by Shandong Province People's government Office” Luzhengbanfa [2004] No.51, project influenced area, Laiyang, belongs to the third-class areas. The Annual Average Output Value (AAOV) of the third-class area is 1,400 Yuan per mu. Land compensation for farmland is 10 times of AAOV, and resettlement subsidy for farmland is 6 times of AAOV. So the total farmland compensation standard is 22,400 Yuan/Mu. Land compensation for wasteland is 4,200 Yuan/Mu, i.e. 3 times of AAOV.

According to the field interview, all affected households prefer cash payment and most of them plan to use the compensation in 3 ways as follows: i) Purchasing irrigation facilities including pumping and water transferring tubes, to increase the output of crops and orchards through improvement the irrigation conditions; ii) Improving the fruit species and growing Chinese chestnut on ditch side to increase the income; and iii) Improving living environment by concreting the house yard or decorate house. The construction of flood control road will acquire 12.6 mu slope waste land owned by Muyu Village collective. Through the discussion with the village committee and villager representatives, the village plan to improve the village road. The road is 300 m long and 3.5 m wide. The investment of improvement of the road, including road concreting will be 48,300 yuan.

The APs have participated in the planning process and their concerns have been integrated into the RP. The draft RP was distributed to the affected village in December 2009. In accordance with ADB’s public communications policy, the draft RP will be posted on the ADB website prior to loan appraisal. An effective and transparent channel for lodging complaints and grievances has been established, and relevant institutions shall accept the complaints and grievances lodged by the APs free of charge. The reasonable costs incurred shall be covered by the contingency of the project.

In order to implement RP successfully and achieve the goals of resettlement, the implementation of RP will be subject to internal and external monitoring according to ADB resettlement policies. The external monitoring and evaluation will be done by an independent monitoring agency (IMA). The external monitoring and evaluation institution shall undertake regular monitoring and evaluation of the resettlement implementation activities and provide necessary consultative proposals.

1

1. INTRODUCTION

1.1 Project Background

1. Muyu Reservoir is located on the midstream and downstream of Xian River, a branch of Wulong River, 9 km northeast of Laiyang City, Shandong Province. It covers 455km2 of control catchment area, with a total capacity of 189.4 million m3 and engineering grade-II. Graded Large (2), the reservoir is a multipurpose reservoir that mainly serves for the purpose of flood prevention and is also involved in irrigation, water supply for city, power generation and aquaculture. The geographical position is important and the social and economic profits are remarkable. Downstream flood prevention protects a population of 400,000 villages, towns and the urban area of Laiyang along the river, more than 500 industrial enterprises, 60,000 mu cultivated lands as well as Lanyan Railroad, Yanqing Road and other important infrastructure facilities.

2. Muyu Reservoir was constructed in May1958. In July1960, the main engineering works were finished and started to store water and produced benefit. The construction of the reservoir inundated 44 villages and farmland of 42,070 mu. Totally 2,225 households or 10,748 persons were involved in resettlement, of which 2,172 households or 10,482 persons were relocated within Laiyang City and 53 households or 266 persons were moved to Liaoning Province. Based on the “Shandong Rural Resettlers Registration and Ratification Method of Large and Medium-sized Reservoirs”, in 2006 the total resettlers are 14,927 persons from 5,069 households1 in 7 townships. The details of resettlement information is presented in Table 1-1.

Table 1-1 Resettlement Status Caused by Original Construction of Muyu Reservoir Resettlement Status in 2006 Resettlement Destination Townships Households APs Muyudian 1,818 5,869 Longwangzhuang 3 9 Bolinzhuang 11 11 Laiyang City Chengxiang 1 1 Heluo 835 2,308 Xuanfang 193 534 Tangezhuang 2,208 6,195 Total 7 5,069 14,927

3. Since Muyu Reservoir was built during the period of Great Leap Forward, the project was under the abnormal state that planning, designing, and constructing were conducted simultaneously, so the standard of engineering construction is somewhat low and the quality of construction is bad. There are many serious safety problems of the dam, spillway, and diversion tunnel. A series of unexpected safety problems occurred in service, which mainly includes: after the completion of dam, there are longitudinal cracks on the top of dam; transition part of west (right) drainage tunnel is scoured; concretes of the dam body cracked; shaft inclines and wall cracks; there are rock breaking and serious weathering on the base and both banks of the auxiliary spillway entrance; oil pressure hoist machine does not work on the east (left) drainage tunnel and the gate leaks. In December 2004, according to the Ministry of Water Conservancy Reservoir Dam Safety Evaluation Method, the Department of Water Conservancy of Shandong, safety evaluation on Muyu Reservoir was performed. The reservoir is judged as grade-Ⅲ dilapidated reservoir, and in December 2005, this result was

1 The Ministry of Water Resources maintains a record of all families affected by reservoir inundation. Today, the numbers have grown due to population increase and division of households.

2

checked by Dam Safety Management Center under Ministry of Water Conservancy. Figure 1-1 is the sketch map of Muyu Reservoir.

4. The downstream of Muyu Reservoir protects not only some important infrastructure facilities, such as Lanyan Railroad, Yanqing Road and so on, but also lives and properties of 400,000 persons in villages and towns along the river and Laiyang City as well as more than 60,000 mu cultivated lands resources. At the same time, the reservoir also has the tasks of supplying water to Laiyang City and irrigation fields, for which it plays the important role in the development of Laiyang's industry and agriculture. There are some safety dangers in the project and it cannot operate normally, and thus it cannot perform its proper social benefits and economic benefits. Therefore, it is urgent to carry on the risk mitigation and strengthening and reinforcement of Muyu Dam and Reservoir, eliminate all kinds of dangers in the project in order to make it operate normally, and perform its proper economic benefits and social benefits of flood prevention, irrigation, the urban water supply and so on. At the same time, it can maximally safeguard life and property of people on downstream. After the risk mitigation and strengthening of the reservoir, it will promote the sustainable development of local economy, improve the local water condition and investment environment, and safeguard society's stability and unity.

1.2 Project Description

5. Aiming at the safety problems of Muyu dam and reservoir, the risk mitigation and strengthening project mainly includes: anti-seepage treatment to the dam foundation and dam body, filling the sag and ploughing-compression of the upstream shell, overhauling the upstream revetment, transforming and consolidating dam crest; reconstructing the original unconventional spillways and building sluices, blocking off the original primary spillway, consolidating and eliminating risks of the east and west outlets and lying pipes under the dam, and improving project observation facility as well as other project management facilities.

6. The overall risk mitigation works was divided into 2 phases. The first phase started in December 2008, including anti-seepage treatment to dam foundation and dam body, transforming and consolidating dam crest; reconstructing the original unconventional spillways and building sluices, blocking off the original primary spillway. The total investment is CNY29.57 million and CNY21.08 million has been completed. The above-mentioned engineering works and corresponding construction activities were implemented on unused land within the existing reservoir management scope, so no land acquisition or temporary land use impacts were involved. Figures 1-2 and 1-3 show theconstruction material area of the ongoing works and the spillway excavation. The other parts of the engineering works were followed into the 2nd phase, referred as the Project.

7. The Project is planned to start in March 2010 and be completed in March 2011; project construction period is 12 months. The Project construction will necessitate permanent land acquisition. To mitigate the impacts, the short resettlement plan (RP) has been prepared by Shandong Water Resources Surveying and Design Institute on behalf of Muyu Reservoir Management Bureau in line with the Asian Development Bank’s (ADB) Involuntary Resettlement Policy (1995) and the relevant laws, regulations and guidelines issued by the governments of People’s Republic of China (PRC) and Shandong Province.

3

Figure 1-2 Construction Material Area within engineering Figure1-3 Spillway Excavation management scope

4

Muyu Village

Figure1-1 Sketch Map of Muyu Reservoir

5

2. IMPACTS OF LAND ACQUISITION AND RESETTLEMENT

2.1 Measures Taken to Avoid or Minimize LAR Impacts

8. In order to avoid or reduce LAR impacts to the minimum, engineering alternatives have been carefully reviewed and the optimal option has been adopted during the Project design phase. All engineering works except the flood control road will be implemented within the reservoir management property and has no negative impacts on people’s lives. At the same time, various compensation measures are prepared for affected persons who are unavoidably affected by land acquisition for the road. During the construction phase, a reasonable construction plan has been formed before the start of construction, and the construction sites should be strictly controlled within the scope of red line and awareness of responsibilities for construction workers should be raised to minimize the land acquisition and resettlement.

2.2 Physical Indices Survey

9. The physical indices survey was conducted based on Specifications on Land Requisition and Resettlement Design for Construction of Water Resources and Hydropower Engineering (SL290-2003) in December 2008. As per the engineering CDM and the scope of land acquisition and occupation, the detailed investigation of each physical index in engineering construction land acquisition scope was measured and recorded on August 12-22, 2009. The participants in survey include staff of Muyu Reservoir Management Bureau, the Design Institute, Heluo town government and involved Muyu Village.

2.3 Scope of Land Acquisition and Resettlement

10. The project will acquire 15.2 mu land including 2.6 mu of orchard land and 12.6 mu of slope wasteland. The 12.6 mu slope wasteland is owned by Muyu village of Heluo Township of Laiyang City. 2.6 mu of orchard is contracted by 11 households with 41 persons of Muyu Village. Table 2-1 and Table 2-2 provide the details of impact of permanent land acquisition. The land loss of all affected households is less than 10% and the average land loss is 7% among the 11 affected households. The accurate land and income loss of each household caused by land acquisition will be decided after the designation of the construction red line. The average income loss associated with the land loss is CNY462, accounting for 6.6% of the total income. No vulnerable people will be affected. Figure 2-1 and Figure 2-2 show the orchard and wasteland to be affected in Muyu Village.

Figure 2-1 Orchard to be affected by Figure 2-2 Slope Wasteland to be affected by Flood Control Road Flood Control Road

6

Table 2-1 Summary of Permanent Land Acquisition of Flood Control Road

Affected Affected Ownership of Land to Land Acquisition (mu) AHs APs Town Village Be Acquired Total Orchard Wasteland Contracted Farmland 2.6 2.6 11 41 Heluo Town Muyu Collective-owned 12.6 12.6 Total 1 15.2 2.6 12.6 11 41

Table 2-2 Impact Analysis of Permanent Land Acquisition Muyu Village Range of Land Loss Ratio AHs (No.) Percentage (%) 1% - 10% 11 100% 11% - 25% 26% - 50% 51% - 75% 76% - 100% TOTAL 11 100%

11. 280 apple trees and 35 ornamental trees such as lotus trees will be affected. The apple trees are the villagers-owned trees and the lotus trees within the reservoir management scope belong to reservoir administration bureau. The lotus trees will be affected by temporary land use. Table 2-3 are the impacts of affected ground attachments.

Table 2-4 Affected Ground Attachments Affected Unit Fruit Trees Lotus Trees Muyu village 280 Reservoir Management Bureau 35 Total 280 35

12. Muyu Reservoir is located in mountainous area surrounded by waste hills with deep slopes (greater than 25 gradient), which is not suitable for farming. Moreover, Muyu Reservoir is the only water source for domestic water supply in Laiyang City. Based on the “Muyu Reservoir Management and Protection Method” issued by Laiyang City Government (Laizhengfa [1996] No.26), it is prohibited to farm land and graze within reservoir management scope in order to protect water quality. The reservoir management scope includes: i) reservoir area below utilization benefit level; ii) dam protection area including 200m beyond the foot of dam slope; iii) embankment protection area including 10m beyond foot of Xian River embankment; iv) channel protection area including 4m beyond the foot of the main canal slope; and v) water conservancy structures protection area including 50m beyond the side line of the main structures. There are no crops being grown within the drawdown zone, so there will be no impact when the reservoir is filled to its originally designed full storage level.

13. According to the field investigation, all the affected persons are Han (i.e., no ethnic minority people) and there are no vulnerable persons affected by this project.

7

3. SOCIO-ECONOMIC PROFILE IN AFFECTED AREAS

14. From August 12-22, 2009, Muyu Reservoir Project Management Bureau and the Design Institute organized an investigating group to investigate the impacts of land acquisition by the Project. At the same time, socio-economic information of the APs was also collected. This survey on socio-economic conditions of the affected households is carried out by one by one interview.

3.1 Socio-economic Profile of Laiyang City

15. Laiyang City governs 14 towns, 4 sub-district offices, and 784 village committees. Its economy grew rapidly in 2008, and its GDP has reached 28.03 billion, 12.3% more than that in 2007. Among which, the primary industry increased 3.01billion,4.3% more than that in 2007; the secondary industry increased 16.56 billion, 9.8% more than that in 2007; the tertiary industry increased 8.47 billion, 20.3% more than that in 2007.

3.2 Socio-economic Profile of Affected Township

16. One township (Heluo) is affected by land acquisition, details are as follows: Heluo Township is situated in the north of Laiyang, and it has a population of 25,100 people in 6,720 households. There is 25,000 mu of farmland, which is 0.99 mu of farmland of per capita. The annual per capita net income of farmers is 5,650 Yuan, which is relatively high.

3.3 Socio-economic Profile of Affected Village

17. One village (Laiyang Village) is affected by land acquisition. The basic socio-economic condition of the Muyu Village is shown in Table 3-1. The socio-economic survey indicates that Muyu Village is situated 9km north of Laiyang City. The total farmland of the village is 872 mu in 2008, including 370 mu of crops, accounting for 42% of the total farmland, and 502 mu of orchard, accounting for 58% of the total farmland.

Table 3-1 Socio-economic Survey of Muyu Village Township Heluo Village Affected Muyu Total Households 272 Total Population 911 Male 501 Population Female 410 Agriculture Population 911 Nonagricultural Population 0 Total Labor Force 460 Male 254 Female 206 Labor Force 1st Industry 460 2ndIndustry 3rd Industry Farmland Total Area (mu) 872 Output Value GDP(million Yuan) 6.56

8

1st Industry(million Yuan) 6.56 2nd Industry(million Yuan) 3rd Industry(million Yuan) Net Income Per Capita(Yuan) 4,200 The 1st Industry (%) 100 Net Income of Farmers The 2nd Industry (%) The 3rd Industry (%)

3.4 Socio-economic Situation of Affected Households

18. In August 12-22 2009, Muyu Reservoir Management Bureau carried out a questionnaire investigation in Muyu village on the 11 affected households. The characteristics of the surveyed population can be seen in Table 3-2.The survey indicates that most of the affected laborers are now engaged in farming and orchard management. The villagers seldom go out for migrate work because the village is far from the urban area and most of the households have orchard, including apple , pear and chestnut. Their agricultural income accounts for all of their total income. The per capita farmland is 0.96 mu. The average per capita loss of land is 0.06 mu (7% of their farmland).

Table 3-2 Statistical Characteristic of People Affected by Land Acquisition Man Women Total Item Quantity % Quantity % Quantity % Age ≤6 years old 2 8.3% 1 5.9% 3 7.3% 6-16 years old 4 16.7% 2 11.7% 6 14.6% 16-60 years old 15 62.5% 12 70.6% 27 65.9% ≥60 years old 3 12.5% 2 11.8% 5 12.2% Subtotal 24 100.0% 17 100.0% 41 100.0%

Education illiterate and almost illiterate 1 4.2% 2 11.8% 3 7.3% primary schooling 4 16.7% 2 11.7% 6 14.6% middle school schooling 15 62.5% 12 70.6% 27 65.9% high school schooling 4 16.6% 1 5.9% 5 12.2% college schooling and above Subtotal 24 100.0% 17 100.0% 41 100.0% Labor Force 13 54.2% 12 70.5% 25 60.9%

3.4.1 Population Distribution by Age

19. Among 41 surveyed persons in 11 households, 3 persons are under 6 years old, accounting for 7.3% of total population; 6 persons are ranging from 6 to 16 years old, accounting for 14.6% of total population; 27 persons are ranging from 16 to 60 years old, accounting for 65.9% of total population; 5 persons are above 60 years old, accounting for12.2% of total population.

3.4.2 Population Distribution by Education

9

20. Among 41 surveyed persons in 11 households, 3 persons are illiterate and almost illiterate, accounting for 7.3% of total population; 6 persons are primary schooling, accounting for14.6%; 27 persons are ranging middle school schooling, accounting for 65.9% of total population; 5 persons are high school schooling, accounting for 12.2% of total population.

3.4.3 Productive Resources

21. Among 41 surveyed persons in 11 households, the total farmland is 39.36 mu, with 0.96 mu per capita. Corn and wheat are the prime crops of 17 mu and orchard is 22.36 mu.

3.4.4 Household Annual Income and Expenditure

22. According to the statistical analysis of 41 surveyed persons in 11 households, per capita annual income is 7,200 Yuan. As for expenditure, household annual expenditure is 3,000 Yuan, among which expenditure for household business is 878.7 Yuan, accounting for 29.29%; purchase of productive fixed assets is 205.2 Yuan, accounting for 6.84%; and consumption expenditure is 1916.1 Yuan, accounting for 63.87%. Income and Expenditure structure is shown in Table 3-3.

Table 3-3 Annual Income and Expenditure Structure of Affected Households Per Capita Percentage Item (Yuan/Person) (%) Wage Income Income From Household Business 7200 100% Among Which: 7200 100% Primary Industry Household annual Secondary Industry Gross Income Tertiary Industry Property Income Transfer Income Total Income 7,200 100.00% Expenditure for Household Business 878.7 29.29% Expenditure for Productive Fixed Assets 205.2 6.84% Tax Expenditure Household annual Consumption Expenditure 1916.1 63.87% Expenditure Expenditure for Property Expenditure for Transfer Total Expenditures 3000 100.00% Net Income 6,116 Savings 4,200

Public Opinion Survey 23. A public opinion survey of 11 households was conducted. The results indicate that all of them support the Project, and think the Project can bring benefits to the county, collectives and individuals, because the villagers can use the flood control road for travelling. All or 100% of them think that the compensation for permanent land acquisition should be paid to the APs and village collectives in cash, 96% of them are satisfied with the compensation standards, 4% are not very satisfied, 93% of them have some knowledge about the land administration law, 7 of them are not familiar with the law, and 92% know the policy about land acquisition and resettlement, and 8% of them don’t know the policy. Please see Table 3-4 for the detailed information of public opinion survey. As the survey was carried out before series of public participation and consultation activities, a small proportion of the APs are not very satisfied

10

with the compensation standards, are not familiar with the land administration law, and don’t know the policy about land acquisition and resettlement. Based on the facts, meetings with the APs have been organized to inform them on their rights and options and to increase their awareness of the LAR policy, laws, regulations and standards. As a result, the awareness of the APs has been increased than before and they are in favour of the suggested approaches.

Table 3-4 Public Opinion Survey Results (%) No. Questions Optional answers (1) (2) (3) (4) total Do you support this 1 (1) yes, (2) no, (3) it doesn’t matter 100 100 project? Who do you think can get (1) nation 100 100 2 benefit from the Project (2) collectives 100 100 (multiple choices)? (3) individuals 100 100 What benefits can the (1) improve income, (2) increase job 100 100 3 Project bring to your life? opportunity, (3) no benefit 100 100 (1) compensation to the whole group, then land adjustment; (2) compensation to the group collective to develop After land acquisition, how economy, then land adjustment; (3) cash 4 to solve the problem of compensation to APs, no land 100 100 land loss? adjustment; (4) partial cash compensation to APs, partial cash compensation to the group, then no land adjustment Are you satisfied with the (1) yes, (2) not very satisfied, (3) 5 96 4 100 land compensation rate? dissatisfied Do you know Land 6 Administration Law of (1) yes, (2) not too much, (3) no 93 7 100 PRC? Do you know the policy 7 about land acquisition and (1) yes, (2) not too much, (3) no 92 8 100 resettlement? If your legal rights are offended during land 8 acquisition and (1) yes, (2) no 100 100 resettlement, do you know to appeal? Do you need other help, 9 e.g. training, and job (1) yes, (2) no 90 10 100 opportunities?

11

4. POLICY FRAMEWORK, ENTITLEMENT AND COMPENSATION

4.1 Applicable Laws, Regulations & Policies for Resettlement

24. The resettlement policy for this project is established mainly in accordance with the relevant laws of China and the relevant policies of ADB, including:

ADB Policies  Safeguard Policy Statement, July 2009 (effective from 20 January 2010)  Handbook on resettlement A Guide to Good Practice (effective from 1998)  Gender and Resettlement Analysis, February 2003.

Laws and Regulations of the PRC  Land Administration Law of the People’s Republic of China (effective from January 1, 1999, latest version on August 28, 2004)  The State Council's Decision on Deepening Reform and Managing Land Strictly (Guo Fa [2004] No.28) (effective from October 21, 2004)  Guidelines on Improving the System of Land Acquisition Compensation and Resettlement (Guo Tu Zi Fa [2004] No.238) (effective from November 3, 2004)  Regulations on Land Requisition Compensation and Resettlement for Construction of Large and Medium-sized Water Conservancy and Hydropower Projects (effective in 2006)  Specifications on land requisition and resettlement design for construction of water resources and hydropower project (SL 290—2003).

Relevant Policies of Shandong Province  The Implementation Regulations of Shandong Province for the PRC Land Administration Law  Circular of Shandong Provincial Government Concerning the Adjustment of the Annual Output Value and Compensation Standard of Acquired Land (Lu Zheng Ban Fa [2004] No. 51)  Circular of Shandong Provincial Government Concerning the Approval of the Associated Attachments Compensation Standard of Acquired Land (Lu Jia Fei Fa [1999] No.314).

The applicable provisions of relevant laws and regulations are in Appendix 1.

4.2 Objectives and Principles of Resettlement

25. The primary objective of the LAR program is to ensure that the APs will improve their standards of living, or at least will not be made worse off because of the Project. The principles of the compensation and entitlements established for the Project are as follows: (i) Compensation and entitlements provided must be adequate to allow APs to at least maintain their pre project standard of living, with the prospect of improvement; (ii) Compensation and entitlements provided are based on market value or replacement value and must be adequate; (iii) Compensation should not be paid to those people who occupy land or construct structures and auxiliaries in the project area after cut-off date determined by the local government; (iv) Adequate compensation should be provided to the APs timely; (vi) All the APs will be adequately informed about eligibility, compensation rates and standards, livelihood and income restoration plans and project timing; and (vii) Close monitoring and timely actions will be carried out to identify and resolve any problems.

4.3 Eligibility of Compensation

26. The Project APs who are entitled to receive compensation from the Project refer to the persons affected by the involuntary taking of land resulting in: (i) permanent loss of land or

12

access to land; (ii) loss of income sources or means of livelihood, whether or not the affected persons must move to another location; and (iii) loss of ground attachments and standing crops.

27. All landowners and users in the Project areas affected by land acquisition and resettlement as a consequence of the Project will be eligible for fair compensation and rehabilitation according to the type of loss and quantities as well as the cut-off date determined by the government within the completion date of the construction map and investigation. The newly cultivated land and newly built houses shall not be compensated after the cut-off date on August 12, 2009

4.4 Compensation Standards

4.4.1 Compensation Standards for Permanent Land Acquisition

28. According to the Land Administration Law of the People’s Republic of China, the Implementation Regulations of Shandong Province for the PRC Land Administration Law, the compensation standard for land acquisition is determined in coordination with villages whose land is to be acquired. According to the “Notice on the Adjustment of Land occupying Annual Production and Compensation Standard, which is forwarded by General Office of Shandong Provincial People’s Government, and issued by Shandong Province People's government Office” Luzhengbanfa [2004] No.51, project influenced area, Laiyang, belongs to the third-class areas. The Annual Average Output Value (AAOV) of the third-class area is 1,400 Yuan per mu.

29. Land compensation for farmland is 10 times of AAOV, and resettlement subsidy for farmland is 6 times of AAOV. So the total farmland compensation standard is 22,400 Yuan/Mu. Land compensation for wasteland is 3 times of AAOV. The waste land compensation standard is 4,200 Yuan/mu. For details see Table 4-1.

Table 4-1 Compensation Rate of Permanent Land Acquisition Resettlement Subsidy Land Compensation (Yuan/mu) (Yuan/mu) Total Type of Land Cost Cost (Yuan/mu) AAOV Multiple AAOV Multiple (Yuan/mu) (Yuan/mu) Orchard 1,400 10 14,000 1,400 6 8,400 22,400 Wasteland 1,400 3 4,200 4,200

4.4.2 Compensation Standards for Attachments

30. Affected ground attachments and infrastructure will be compensated for based on replacement cost. For details see Table 4-2.

Table 4-2 Compensation Standards for Attachments Item Unit Compensation Rate (CNY) Fruit Trees No. 200 Lotus Trees (transplant) No. 100

4.5 Entitlement

31. For the losses associated with land acquisition of the Project, the entitlement matrix has been prepared as a guide to compensation payments, which is presented in Table 4-3. The compensation fees for land acquisition will be directly paid to the land owners or users at all levels before implementation of land acquisition. According to the “Land Administration Law of

13

PRC”, the farmland is owned by village collective. The land lease contract was signed in 1989 between the village collective and villagers and will be effective for 30 years. After the expiration of the contract in 2019, all contracted farmland will be readjusted among villagers. After consultation with the APs and village representatives, it has been agreed that 100% of orchard land compensation will be paid to the affected households. Slope wasteland compensation will be paid to the village collective. All compensation fees for fruit trees will be paid to affected persons. The compensation for affected lotus trees will be paid directly to reservoir administration bureau. The APs have accepted these rates and the entitlements.

32. With the compensation payment, slope wasteland compensation fees will be used by the village collective to improve village infrastructures (roads, irrigation system or power services facilities). APs will use the payment to buy irrigation facilities, improve tree species to increase their income and concreting yard to beautify living environment. with remaining money left.

Table 4-3 Entitlement Matrix Affected Responsible Policy of Land Acquisition Compensation Affected Items type Agency and Resettlement Standard 1. Orchard Land Orchard Land : 2.6 mu orchard with 11 Muyu Reservoir compensation is 10 times of CNY 22,400/mu households or 41 persons Permanent Project Construction AAOV, and resettlement Wasteland: CNY to be affected in Muyu Land Bureau, Muyu City subsidy is 6 times of AAOV 4200/mu Village and is paid to APs. Acquisition Land Resources 12.6 mu slope wasteland 2. Wasteland compensation Bureau owned by Muyu Village is 3 times of AAOV and is paid to the village collective. 280 Fruit trees of Muyu Fruit trees: 200 In the project compensation fee Villagers Muyu Reservoir yuan each or replanting cost for the Trees 35 lotus trees owned by Project Construction Ornamental trees scattered trees shall be paid to reservoir management Bureau (lotus trees): 100 the owners. bureau yuan each

14

5. REHABILITATION MEASURES

5.1 Objectives of Resettlement

33. The objective of resettlement is to compile a resettlement and rehabilitation action plan for APs to ensure their living standard can be improved or at least recovered to the former level after project construction.

5.2 Rehabilitation Plan for Permanent Land Acquisition

5.2.1 Rehabilitation Plan for Affected Households

34. In Muyu Village, 11 households will be affected by land acquisition of 2.6 mu orchard due to the construction of flood control road. Based on the compensation policy and standards, the land compensation of orchard will be 58,240 yuan and fruit trees will be 56,000 yuan in total. The total compensation will be 114,240 yuan for the affected households. According to the field interview, all affected households prefer cash payment and most of them plan to use the compensation in 3 ways as follows: i) Purchasing irrigation facilities including pumping and water transferring tubes, to increase the output of crops and orchards through improvement the irrigation conditions; 5 households will purchase pumps with the total investment of 13,500 yuan. 9 households will invest 21,600 yuan to buy irrigation tubes and fittings. ii) Improving the fruit species and growing Chinese chestnut on ditch side to increase the income; it is estimated the total budget will be 51,800 yuan. iii) Improving living environment by concreting the house yard or decorate house. It is estimated the cost will be 19,320 yuan.

35. The detailed arrangement of the compensation for rehabilitation measures is presented in Table 5-1. Since the compensation to each household will vary according to the actual land acquisition area which will be decided after the designation of the construction red line, the detailed plan will be carried out based on the actual situation.

Table 5-1 Rehabilitation Measures and Budget Programs Unit Price Quantity/household AHs (No.) Investments (CNY) Purchasing 2,700 yuan each 1 5 13,500 Pumps Irrigation 6 yuan/m 400m 9 21,600 Tube Fruit species 8 41,000 improvement Chestnut 12 yuan each 100 9 10,800 Trees Yard 230 yuan/m2 12 m3 7 19,320 Hardening Total 106,220

5.2.2 Rehabilitation Measures of the Affected Village

36. The construction of flood control road will acquire 12.6 mu slope waste land owned by Muyu Village collective. The total compensation will be 52,920 yuan. Through the discussion with the village committee and villager representatives, the village plan to improve the village road. The earth road runs through the village in south-north direction and it is the necessary path to farmland and the other villages. The road condition is very poor, especially in rainy days when covered by sludge. The road is 300 m long and 3.5 m wide. The investment of improvement of the road, including road concreting will be 48,300 yuan. Muyu Reservoir

15

Management Bureau will provide assistance for the construction of the road during construction Table 5-2 provides the detail budget of road hardening.

Table 5-2 Investment of Rehabilitation Measures of Muyu Village Item Unit Price (CNY/m2) Road Length (m) Road Width (m) Investment (CNY) Road Hardening 46 300 3.5 48,300

5.3 Training for the Affected Persons

37. To ensure the income of the APs will be restored in a sustainable way, Laiyang Social Security Bureau and Heluo Township Government will provide free skill training programs regularly. The skill training programs to APs will focus on fruit farming and insect control. The training plan is shown in Table 5-3.

Table 5-3 Schedule of Training for APs No. Time Place Manner Recipients Contents Workshop, Lecture, and 1 Feb. 2010 Town APs Fruit farming and insect control Practical demonstration 2 Other irregular technical trainings APs Not determined yet

5.4 Job Opportunities from the Project

38. About 100 temporary job opportunities (55% are unskilled) will be created during the project construction stage. In the project construction stage, the main unskilled job opportunities include manual laborers for excavation, material handling, greening, etc.

39. According to the survey, since the affected villages are located far from urban area and 25 affected laborers from 11 AHs work in their own orchard normally, they hope to join the project construction while working time has no conflict with their fruit planting activities. LCG and MRPMB will arrange the jobs and training for them as a priority.

5.5 Income Restoration Plan of Women

40. In the stage of RP preparation, the affected women were organized to actively participate in the survey of project impacts so as to understand their ideas on income restoration. As a result, women hold a positive attitude toward project construction by thinking that the project will help improve the environment and improve the flood control road; and land acquisition has little impacts on their lives.

41. Women will fully participate in the compensation and resettlement activities through the information disclosure and village meetings; they have equal entitlement with men in receiving compensation, employment and training. In addition, the following measures will be taken to improve women’s income: (1) During the project construction, MRPMB has ensured that the affected women will be given priority in unskilled jobs, including food and cleaning service. As per labor laws, women will get equal pay to men for the same work. (2) Technical training program including fruit farming and insect control, etc. will be provided for the affected female laborers (at least 50% will be women) to ensure their income would not be reduced.

16

6. COST ESTIMATE AND IMPLEMENTATION SCHEDULE

6.1 Resettlement Cost

42. The estimated cost of land acquisition is CNY222,189 in 2009 prices, including contingency. In terms of the categories of resettlement impacts, compensation of LAR is CNY170,669, accounting for 76.8%. According to Shandong Province Implementation methods of Law of Land Administration of PRC, the land reclamation fee is 7,840 Yuan per mu according to” Notification on Relevant Issues of Building-purposed Land-use for Water Conservancy and Hydropower Engineering” promulgated by National Land Resources Department [2001] No.355.Table 6-1 provides the cost estimation of LAR.

Table 6-1 Budget of Land Acquisition and Resettlement Unit price No. Items Unit Quantity Cost(104) (Yuan) 1 Land 170,660 acquisition 1.1 Permanent 111,160 land acquisition Orchard mu 22,400 2.6 58,240 Waste land mu 4,200 12.6 52,920 1.2 Ground 59,500 attachments Fruit trees Tree 200 280 56,000 Lotus Trees No. 100 35 3,500 (transplanted) Subtotal 1 170,660 2 Other 12,799 expenses 2.1 Survey design 3.0% 5,120 scientific research expense 2.2 Implementation 3.0% 5,120 management fee 2.3 Technical 0.5% 853 training fee 2.4 M & E Cost 1.0% 1,707 Subtotal(1+2) 183,459 3 Basic 10% 18,346 Contingencies 4 Land mu 7,840 2.6 20,384 Reclamation Fee Total 222,189

6.2 Management and Disbursement of Resettlement Funds

43. Laiyang City Water Resources Bureau will provide the entire fund for resettlement activities and ensure that land acquisition and resettlement budgets are delivered on time for timely implementation of the RP. All LAR cost will be paid in December 2009, before the construction of the Project. Land compensation and resettlement subsidy will be disbursed in full to the APs. Compensation for attachments will be paid to the affected unit or individuals directly.

17

44. In order to ensure the funds for land acquisition is paid to the APs in full and in a timely manner in line with the compensation policies and standards of the resettlement plan, a strict fund appropriation plan has been established, the principles of which are as follows:  All the costs related to resettlement are covered in the general budget of this project.  The land compensation and resettlement subsidy must be paid up before the land acquisition.  To ensure the land compensation is implemented successfully, financial and supervisory agencies will be set up to make all funds appropriate in a timely manner.  The budget is based on the resettlement cost estimate. The resettlement costs may increase due to changes in the actual resettlement impacts and other factors such as inflation. Meanwhile, the resettlement budget includes a contingency cost and will be modified based on the actual needs.

18

7. POST-RESETTLEMENT PROGRAM FOR RESETTLERS IN RESERVOIR AREA

7.1 Background and Remaining Issues

45. Since the founding of new China, a number of large and medium-sized reservoirs have been constructed and brought into huge benefits in flood control, power generation, irrigation and water supply and ecological aspects. A large number of resettlers of large and medium-sized reservoirs made major contributions to effectively promote the national economy and social development. In order to help them to improve production and living conditions, the country has established the post reservoir resettlement support fund of the large and medium-sized reservoirs and try to solve the remaining resettlement issues in reservoir area. But due to the low support level and insufficient direct benefit to resettlers, at present their production and living conditions are still generally poorer. To help the resettlers in reservoir shaking off the poverty and promote the economic and social development in the new period, the central government of PRC issued the “Suggestions on Perfecting Post-resettlement Support Policies for Large and Medium-sized Reservoirs Resettlers” in 2006 (Guofa [2006]No.17).

46. Since 2006, the central government has distributed special fund of CNY 2.09 million to persons affected by the original the construction of the Reservoir to help improve the living condition of resettlers in Muyu Reservoir Area. Due to the out-dated infrastructure and limited income sources some villages still have some troubles in aspect of drinking water, transportation, medical service and education. In addition, the employment difficulties stayed with resettlement villagers. The remaining issues include:

Economic income. Since most of the resettlement villages have not any industrial and sideline production programs, they relied on agricultural activities for living. Income of resettlement villagers lagged greatly behind other people outside the reservoir area. Land Resources. The reservoir area is located in mountainous area where poor land quality and limited farmland resources lead to the limited output value. Although the resettlers were allocated some farmland in host area, the farmland available is very poor and output is low as well. The per capita farmland is much less than they have before relocation. Infrastructure Situation. The poor infrastructure condition includes the poor road, limited and poor quality of domestic water supply, no access to electricity, health care service and education facilities. 51% of the households have the cable TV and 37% of households have telephone. 95% of children at compulsory education age entered school. 53% of resettlers join the rural medical insurance programs. The above-mentioned percentages are much lower than the average level in Laiyang City.

7.2 Post-resettlement Support Approaches

47. Based on the “Suggestions of State Council on Perfecting the Post-resettlement Support Policies of Large and Medium-sized Reservoir Resettlement” and the corresponding Implementation Method issued by Shandong provincial government, Laiyang City government led the preparation of the post-resettlement program for Muyu Reservoir. The goals of the programs include :i) the per capita farmland will be at least 1 mu; ii) the drinking water quality will be secured; iii) road access between administrative villages; iv) power supply is available in each resettlement village; v) each administrative village has clinic; vi) 100% children at education age join the compulsory education program; vii) at least 2 laborers from each household, including one female, can join the technical skill training program; viii) cable and telephone are accessible in each village.

48. Based on the “ Management Method of Post-resettlement Support Fund of Large and Medium-sized Reservoirs in Shandong Province”, the support fund can be paid directly to resettlers or be used in actual development programs. In Laiyang City, after full consultation

19

with affected people, all support fund has been paid to resettlers directly at the annual rate of CNY 600/person. The total resettlers are 14,927 persons in 7 townships of Laiyang City that were identified as the support target of Muyu Reservoir. The support will last for 4 and a half year in the duration of 2006-2010. The total cash payment will be CNY 40.3 million for resettlers of Muyu reservoir area. The cash subsidy was paid quarterly. In addition to the cash payment, some other development programs has been planned and implemented since 2006. The details of such programs and implementation status of Muyu Reservoir Area is presented in Table 7-1. It is planned that 4 development programs have been or will be implemented in reservoir area villages from 2006 to 2010, including water resources facilities and farmland improvement, domestic water supply, transportation works and marsh gas facilities. The implementation of the programs will be monitored during the Project period. It is expected through the improvement of infrastructures the living condition of people in Muyu Reservoir Area will be better-off.

Table 7-1 Post-resettlement Support Program of Muyu Reservoir Beneficiaries of Investment Programs Contents Resettlers (No.) (CNY 104) Well drilling, pipeline installation, irrigation Water Resources Facilities equipment, water storage pond, terrace 8,487 691 and Farmland Improvement plowing, etc. Domestic Water Supply Tap water facilities 10,068 648 Transportation Village-village road 7,979 790.62 Marsh Gas Construction of marsh gas tank 945 65 Total 2,194.62

7.3 Post-resettlement Support in Reservoir Area

49. In Laiyang City, after full consultation with affected people, all support fund has been paid to resettlers quarterly at the annual rate of CNY 600/person. The support will last for 4 and a half year in the duration of 2006-2010. The total cash payment will be CNY 40.3 million for resettlers of Muyu reservoir area. In addition to the cash payment, some other development programs has been planned and implemented since 2006. The total budget of the programs is CNY 1.34 million and the overall progress is 6% in term of the expenditure of the investment. The progress varies in different programs. All support funds will be allocated by central government. Table 7-2 presents the details of the budget of the programs. All the funds will be disbursed by 2010 and the activities will be completed by 2011. The implementation of the programs will be monitored during the Project period.

Table 7-2 Investment and Implementation of Post-resettlement Support Budget Beneficiaries of Implementation in Progress Programs Township (CNY104) Resettlers (No.) Cost(CNY 104) (%) Xuanfang 48 327 0 0 Water Resources Facilities Heluo 145 2,707 0 0 and Farmland Improvement Muyudian 498 5,453 0 0 Xuanfang 137 534 34 25 Heluo 169 2,967 30 18 Domestic Water Supply Muyudian 76 2,564 33 43 Tangezhuang 266 4,003 37 14 Xuanfang 122 207 0 0 Heluo 169 1,635 0 0 Transportation (Road) Muyudian 352 3,394 0 0 Tangezhuang 148 2,743 0 0 Marsh Gas Tangezhuang 65 945 0 0 Total 2,195 134 6

20

8. IMPLEMENTATION SCHEDULE

50. The resettlement is scheduled to begin in December 2009 and complete in November 2010, with reflecting the linkage and consistency between the time schedule of LAR and civil works construction tasks. Civil works will not begin before compensation for the APs are paid in full, which is in accordance with the recently promulgated State Council Decree #31. All compensation for residential structures and ground attachments will be paid before construction. Table 8-1 provides the resettlement activities and supervision milestone. Based on these surveys, the short RP will be updated and submitted to ADB for concurrence.

Table 7-1 Resettlement Activities Milestone Responsibilities Progress No. Compensation Task Targets Deadline Agencies Status 1. Information Disclosure 1.1 -Resettlement Plan disclosure 11 households MRPMB 2009.12 Completed with 41 persons in Jianguo Village 1.2 -Publish Resettlement Plan on ADB 2010.01 Planned ADB website 2. Approval of RP & Budget LCG 2009.12 Completed 3 Compensation Agreement 3.1 -Compensation rates Muyu village LCG, MRPMB,LLAB, VC 2010.03 Planned 3.2 -Household agreements 11 AHs LCG, MRPMB,LLAB, VC 2010.03 Planned 3.3 -Approval of land use certificate MRPMB,LLAB 2010.03 Planned 4. Monitoring and Evaluation 4.1 -Baseline Survey (additional) one village MRPMB 2010.01 Planned 4.2 -Establish Internal M&E As per RP LWRMD, MRPMB 2009.09 Completed mechanism 4.3 -Sign contract with External M&E LCG, MRPMB 2010.01 Planned agency 4.4 - Internal M&E Report Quarterly LWRMD, MRPMB 2010.06 Planned Report 4.5 - External M&E Report Semi-annually MRPMB,,IMA 2010.07, Planned Report 2010.12 4.6 - Evaluation report 2 Report MRPMB,,IMA Dec. 2011, Planned Dec. 2012 4.7 -Resettlement Completion Report 1 Report MRPMB,,IMA As work is Planned completed 5 Consultation documentation MRPMB/VC Ongoing 6 Grievance and appeal files MRPMB /VC Ongoing 8 Capital/compensation payment 8.1 - Paid to affected village 2010.03 Planned 8.2 - Paid to affected Households 2010.03 Planned 9 Commencement of civil works Flood control MRPMB 2010.03 Planned road

21

9. PUBLIC PARTICIPATION AND GRIEVANCE REDRESS

9.1 Public Participation

51. The RP was prepared with full public participation and full information sharing with APs. The Muyu Reservoir Project Management Bureau (MRPMB) has informed the resettlement policies to all the APs via socio-economic survey, social impact survey and other communication and consultation channels. MRPMB also has consulted with various affected persons through consultation meetings. Through wide consultation, coordination and communication, related local government, affected villages and APs can fully understand the resettlement impacts, resettlement policies and formulate feasible income restoration measures.

52. MRPMB contacted the affected village committee in August 2009, and discussed the Project and compensation costs, compensation policies, entitlement, and impacts of the Project on the village and APs. MRPMB will disclose the draft RP to affected people and then sign the land agreement with APs and the affected village in November 2009. The RP approved by LCG will be redistributed to village committee in November 2009 to any one wishing to consult the document at the affected village. Copies of the short RP will be kept in the Project office and the affected VC. At the same time this short RP will be posted on the ADB’s website in November 2009. The public consultation activities and schedule is presented in Table 8-1.

Table 9-1 Public Consultation Activities and Schedule Organizations Objectives Task Date Participant Involved 1. Inform and discuss Release of location and February LCWRD, MRPMB Representatives of issues related with LA; area of LA, compensation 2009 and VC each organization Obtain suggestion or standards, and advices resettlement, etc. 2. Survey on affected Field survey of affected, August MRPMB, Laiyang Representatives of physical index, and physical index, and 2009 LAB, and VC each organization preparation of RP socioeconomic status of affected households 3. Land acquisition Agreement of March 2010 MRPMB, Laiyang Representatives of agreement signed with complementation LAB, and VC each organization Muyu Village standards, and grievance appeal procedures 4. RP disclosure on ADB Release of draft RP Jan. 2010 ADB website 6. Implementation of Final Verification and March 2010 MRPMB, Laiyang Representatives of RP implementation of Final RP LAB, and VC each organization 7. Monitoring & Evaluation Survey on the rehabilitation Jan. 2010 MRPMB, Laiyang Socioeconomic sample of RP of APs after resettlement LAB, VC, and IMA survey implementation

9.2 Grievance Procedure

53. During the preparation and implementation of the RP, public participation is encouraged, and thus there should not be any major issues or grievances. However, some unforeseen issues may occur during such process. In order to settle such issues effectively and make the construction and land acquisition implement successfully, an effective and transparent channel for lodging complaints and grievances has been established. The basic stages for grievance redress are:

Stage 1: The APs submit an oral or written petition/complaint to the village committee. For an

22

oral complaint, the village committee must make written records properly and give a clear reply within 2 weeks.

Stage 2: If the complainant is not satisfied with the reply in Stage 1, he can appeal to the township government/sub-district office after receiving the reply in Stage 1 and the township government/sub-district office will deal with the complaint within 2 weeks.

Stage 3: If the affected person is still not satisfied with the reply of township government/sub-district office, he can appeal to Laiyang Land Resources Bureau and Laiyang Land Resources Bureau must give a reply within 30 days.

Stage 4: If the affected person is still not satisfied with the reply of Laiyang Land Resources Bureau, he can appeal to SPMO after receiving the reply of Stage 3. They also have the right to appeal to the civil court within 3 months of receiving the reply.

54. Besides the established channel above, the external monitor can also receive grievances from APs and the APs can even submit directly to ADB2. The appeal process, institutions, sites, leaders, and telephone numbers for redress of grievances will be publicized to APs via meetings, notices and the information handbook. In this way, the APs will fully realize their rights of appeal. Meanwhile, the system of information dissemination will be strengthened through use of the media, and all APs feedback will be compiled and distributed to all involved organizations.

55. Relevant institutions shall accept the complaints and grievances lodged by the APs free of charge. The reasonable costs incurred shall be covered by the contingency of the project. During the whole process of project construction, these grievance procedures remain valid so that the APs may deal with relevant issues.

2 ADB has an Accountability Mechanism to ensure policy compliance. APs are required to seek grievance resolution using the above procedures, but if they still believe that their concerns have not been resolved in accordance with this RP or ADB's Involuntary Resettlement Policy (1995), they may submit a complaint to ADB. The procedures are provided on ADB's website: http://www.adb.org/Accountability-Mechanism/default.asp

23

10. INSTITUTIONAL ARRANGEMENT

10.1 Responsible Institutions for Resettlement Implementation

56. The departments responsible for planning, implementation, management, and monitoring of the resettlement activities of the Laiyang Muyu Reservoir ADB Loan project are:  Laiyang Water Resources Department  Muyu Reservoir Project Management Bureau  Laiyang Land Resources Bureau  Heluo Township Government  Muyu Villagers committee  Design Institute. 57. Laiyang Water Resources Department is in charge of resettlement investigation, development of the RP and implementation of land acquisition.

58. Muyu Reservoir Project Management Bureau is the specific implementing agency, which is responsible for the socio-economic investigation, coordinating with Laiyang Land Resources Bureau, governments and the affected village committees, and implementing the work of land acquisition and resettlement.

59. Laiyang Land and Resources Bureau is responsible for collective land acquisition, directing the implementation of resettlement, organizing and coordinating.

60. Heluo Township government is responsible for the project impact investigation, and assisting the Laiyang Land and Resources Bureau to sign land acquisition agreements with land departments and the APs in order to implement land occupation and resettlement successfully.

61. Muyu village committee is responsible for providing the land contract, assisting or participating in the various surveys and the work of land acquisition, community mobilization activities for publicity, and undertaking the verification of the measurement, valuation and finalization of demolition agreements after APs negotiations together with the relevant technical personnel.

62. Design institute is responsible for the design of the project and defining the scope of affected land and assets.

The staffing of institutional arrangement for LAR is presented in Table 10-1

Table 10-1 Staffing of Institutional Arrangement for LAR Staff (No.) Name of Institution Personnel Composition Male Female Laiyang Water Resources Department 1 Official Laiyang City Muyu Reservoir Project 2 1 Officials Management Bureau Laiyang City LAB 1 Official Heluo Township Gov't 1 Official Affected village committee (1) 3 1 Cadres and representatives of APs

TOTAL 8 2

10.2 Training Plan for Resettlement Management Staff

63. A system for staff training and human resource development will be established at all levels of resettlement management institutions. The training plan is organized by LWRD, and the form of training will include specialist lectures, technical training seminars, inspection of

24

other similar projects and site training, etc. The training plan is shown in Table 10-2, while the training contents will include: resettlement principles and policies, planning and management of projects with resettlement, resettlement planning and design, resettlement progress management, resettlement financial management, resettlement quality control and resettlement monitoring assessment.

Table 10-2 Schedule for Resettlement Implementation Training Training Time Location Recipients Training content methods Centralized Resettlement Feb. 2010 City Resettlement business training course work staff Learn from Key personnel of The implementation site visit of the Jun. 2010 Domestic demonstration the office ADB project Resettlement Discuss the resettlement experience Oct. 2010 Jinan City Seminars work staff and the problems

25

11. MONITORING AND EVALUATION

64. In order to ensure the successful implementation of the RP and accomplish the objectives to achieve appropriate resettlement, monitoring and evaluation should be carried out for the implementation of resettlement in accordance with the requirement of the ADB resettlement policies. The monitoring include both internal and external. The reporting schedules were shown in Table 8-1.

65. The external monitoring and evaluation is done by an independent monitoring agency (IMA). The IMA will carry out semi-annual monitoring and evaluation of the resettlement activities.

66. The IMA, approved by ADB and LCG, will undertake the independent monitoring of the Project in respects of: (i) extent of consultation undertaken with APs; (ii) compensation disbursement to the APs and affected village or group; (iii) production and livelihood rehabilitation measures for the APs; (iv) schedule of above LAR activities; (v) compliance with the policies and regulations of the resettlement plan; (vi) participation and consultation during the project implementation; (vii) grievances, problem resolution and follow-up; (viii) staffing, training, schedule and work efficiency of the resettlement officers. The IMA, being independent of the project, will inspect the whole implementation from an overall and long-term point of view. The IMA will put forward recommendations to SPMO, LCG and MRPMB in time so that the problems taking place in the implementation of the resettlement can be solved as soon as possible. The terms of reference for external monitoring and evaluation is presented in Appendix 2.

67. The major external monitoring and evaluation indicators are as follows:

(1) M&E on Progress of Land Acquisition Implementation: i) progress of land acquisition; ii) progress of temporary land occupation; and iii) progress of project impacts;

(2) M&E on Fund Disbursement and Usage: i) Fund disbursement; and ii) Fund usage (planning and actual fund usage).

(3) M&E on Rehabilitation of APs’ Production and Livelihood: i) Production and living conditions of the APs before land acquisition; ii) Production and living conditions of the APs after land acquisition; iii) Analysis and evaluation of employment and living condition before and after the resettlement; and iv) Grievance mechanism and problem resolution.

(4) M&E on capabilities of resettlement institution, public participation, grievance and appeal procedures.

26

Appendix 1 Applicable Laws and Regulations

The Applicable Provisions in Land Administration Law of the People’s Republic of China

Article 43 All entities and individuals that need land for construction purposes shall, in accordance with law, apply for the use of state-owned land, with the exception of the collective economic organizations and farmers of such entities that have lawfully obtained approval of using the land owned by farmer collectives of these organizations to build township or town enterprises or to build houses for villagers and the entities and individuals that have lawfully obtained approval of using the land owned by farmer collectives to build infrastructure or public welfare undertakings of a township (town) or village. “State-owned land” referred to in the preceding paragraph includes land owned by the state and land originally owned by farmer collectives but expropriated by the state.

Article 44 Where farmland is to be used for construction purposes, the formalities of examination and approval shall be gone through for the conversion of use. Where farmland is to be converted to land for the construction of road, pipeline or large infrastructure projects, for which approval has been obtained from people’s governments of provinces, autonomous regions and municipalities directly under the Central Government, or for the construction of projects for which approval has been obtained from the State Council, the conversion shall be subject to approval by the State Council. Where farmland is to be converted to land for construction of projects in order to carry out the overall plan for land utilization within the limits of the area of land fixed in the plan for construction projects of cities, villages or towns, the conversion of use of land shall, in accordance with the annual plan for land utilization, be subject to approval in batches by the organ that originally approved the overall plan for land utilization. Land for construction of specific projects within the limits of the area of farmland, conversion of the use of which has been approved, may be subject to approval by people’s governments of cities or counties. Where farmland is to be converted to land for construction projects other than what is provided for in the second and third paragraphs of this Article the conversion shall be subject to approval by people’s governments of provinces, autonomous regions and municipalities directly under the Central Government.

Article 46 Where land is to be expropriated by the State, the expropriation shall, after approval is obtained through legal procedure, be announced by people’s governments at or above the county level, which shall help execute the acquisition. Entities and individuals that own or have the right to the use of the land under expropriation shall, within the time limit fixed in the announcement, register for compensation with the land administration department of the local people’s government by presenting their certificates of land ownership or land-use right.

Article 47 Land expropriated shall be compensated for on the basis of its original purpose of use. Compensation for expropriated farmland shall include compensation for land, resettlement subsidy and compensation for attachments and young crops on the acquisitioned land. Compensation for expropriated of farmland shall be six to ten times the average annual output value of the expropriated land, calculated on the basis of three years preceding such acquisition. Resettlement subsidy for expropriated farmland shall be calculated according to the agricultural population needing to be resettled. The agricultural population needing to be resettled shall be calculated by dividing the area of expropriated farmland by the average area of the original farmland per person of the entity the land of which is expropriated. The standard resettlement subsidy to be divided among members of the agricultural population needing resettlement shall be four to six times the average annual output value of the

27

expropriate farmland calculated on the basis of three years preceding such expropriation. However, the maximum resettlement subsidy for each hectare of the expropriated farmland shall not exceed fifteen times its average annual output value calculated on the basis of three years preceding such expropriation. Rates of land compensation and resettlement subsidy for expropriation of other types of land shall be prescribed by provinces, autonomous regions and municipalities directly under the Central Government with reference to the rates of compensation and resettlement subsidy for expropriation of farmland. Rates of land compensation and resettlement subsidy for expropriation of other types of land shall be prescribed by provinces, autonomous regions and municipalities directly under the Central Government with reference to the rates of compensation and resettlement subsidy for expropriation of farmland. For expropriation of vegetable plots in city suburbs, the land users shall pay towards a development and construction fund for new vegetable plots in accordance with the relevant regulations of the State. If land compensation and resettlement subsidy paid in accordance with the provisions of the second paragraph in this Article are still insufficient to enable the farmers needing resettlement to maintain their original living standards, the resettlement subsidy may be increased upon approval by people’s governments of provinces, autonomous regions and municipalities directly under the Central Government. However, the total land compensation and resettlement subsidy shall not exceed 30 times the average annual output value of the expropriated land calculated on the basis of three years preceding such expropriation. The State Council may, in light of the level of socio-economic development and under special circumstances, raise the rates of land compensation and resettlement subsidy for expropriation of farmland.

Article 48 Once a plan for compensation and resettlement subsidy for acquisitioned land is decided on, the local people’s government concerned shall make it known to the general public and solicit comments and suggestions from the collective economic organizations, the land of which is acquisitioned, and the farmers.

Article 49 The rural collective economic organization, the land of which is expropriated, shall accept supervision by making known to its members the income and expenses of the compensation received for land expropriation. The compensation and other charges paid to the entity for its land expropriated is forbidden to be embezzled or misappropriated.

Article 50 Local people’s governments at all levels shall support the rural collective economic organizations, the land of which is acquisitioned, and the farmers in their efforts to engage in development or business operation or to start enterprises.

Article 51 The rate of compensation for expropriation of land to build large or medium-sized water conservancy or hydroelectric projects and the measures for resettling the migrants shall be prescribed separately by the State Council.

Article 52 During the feasibility study of a construction project, land administration department may, in accordance with the overall plan for land utilization, the annual plan for land utilization and the standard area of land for the use of construction, examine the matters related to land for construction and offer its comments and suggestions.

Article 53 Where a construction entity needs to use state-owned land for construction of an approved project, it shall apply to the land administration department of the people’s government at or above the county level that has the approval authority by presenting the relevant documents as required by laws and regulations. The said department shall examine the application before submitting it to the said people’s government for approval.

28

Article 54 A construction entity that wishes to use state-owned land shall get it by such means of compensation as assignment. However, land for the following purposes may be allocated with the lawful approval of a people’s government at or above the county level: (1) for state organs or military purposes; (2) for urban infrastructure projects or public welfare undertakings; (3) for major energy, communications, water conservancy and other infrastructure projects supported by the state; and (4) other purposes as provided for by laws or administrative regulations.

Article 55 A construction entity that obtains right to the use of state-owned land by such means of compensation as assignment shall, in accordance with the rates and measures prescribed by the State Council, pay, among other charges, compensation for use of land such as charges for the assignment of land-use right, before it can use the land. Beginning from the date of implementation of this Law, 30 percent of the compensation paid for the use of additional land for construction shall go to the Central Government and 70 percent to the local people’s governments concerned, both of which shall exclusively be used for developing farmland.

Article 56 A construction entity that uses state-owned land shall do so in agreement with the stipulations of the contract governing compensation for the use of land such as the assignment of the land-use right or with the provisions in the documents of approval for allocation of the land-use right. Where it is definitely necessary to change the purposes of construction on this land, the matter shall be subject to agreement by the land administration department of the people’s government that originally approved the use of land. Where the land the purposes of use of which need to be changed is located in the area under city planning, the matter shall be subject to agreement by the city planning administration department concerned before it is submitted for approval.

Article 57 Where land owned by the State or by farmer collectives needs to be used temporarily for construction of projects or for geologic prospecting, the matter shall be subject to approval by the land administration department of a people’s government at or above the county level. However, if the land to be temporarily used is located in the area covered by city planning, the matter shall be subject to agreement by the city planning administration department concerned before it is submitted for approval. The land user shall, depending on who owns the land and who has the land-use right, enter into a contract for the temporary use of the land with the land administration department concerned, or the rural collective economic organization, or the villagers committee, and pay compensation for it in accordance with the provisions of the contract. The temporary land user shall use the land for purposes stipulated in the contract for temporary use of the land and may not build permanent structures on it. Generally, the period for temporary use of land shall not exceed two years.

The Implementation Regulations of Shandong Province for the PRC Land Administration Law

Article 24 Within the scope of construction land defined in the overall land use plan, the use of state-owned construction land and state-owned unused land in detail construction project should transact the following procedure: (1) Land occupation below 2 hectares should be approved by city/county Peoples’ Government and reported step by step to province Peoples’ Government for record; (2) Land occupation between 2 hectares and 8 hectares should be approved by city (govern districts) Peoples’ Government or regional government, and then reported to province Peoples’ Government for record; (3) Land occupation exceeding 8 hectares should be approved by province Peoples’

29

Government for record. As for state important project construction, military establishment construction, multi-provincial project construction and other construction regulated by State Council, the use of state-owned unused land defined in the overall land use plan should be approved by State Council. It should be approved by State Council or Peoples’ Government of province if the land used is out of the range of construction land in city, village and town, which is defined in the overall land use plan.

Article 25 Land acquisition compensation rate should be as follows: (1)If farmland (including garden plot, pond and lotus root pool, the same below) within urban planning district is acquired, land compensation should be 8 to 10 times the AAOV of the three years preceding such acquisition; (2)If farmland out of urban planning district is acquired, land compensation should be 6 to 8 times the AAOV of the three years preceding such acquisition; (3)If farmland such as woodland, grassland, reed pool and water surface is acquired, land compensation should be 5 to 6 times the AAOV of preceding three years in nearest common farmland; (4)If collective-owned land occupied by public establishment, commonweal industry, township business or rural residential house is acquired, land compensation should be 5 to 7 times the AAOV of preceding three years in nearest common farmland; (5)If unused land is acquired, land compensation should be 3 times the AAOV of preceding three years in nearest common farmland.

Article 26 Compensation rate of movement subsidy should be as follows: (1) Movement subsidy for farmland acquisition shall be calculated according to the agricultural population needing to be resettled. The agricultural population needing to be resettled shall be calculated by dividing the amount of acquisitioned farmland by the average amount of the original farmland per person of the entity the land of which is acquisitioned. The standard resettlement subsidy to be divided among members of the agricultural population needing resettlement shall be 4 to 6 times the average annual output value (AAOV) of the acquisitioned farmland for three years preceding such acquisition. However, the highest resettlement subsidy for each hectare of the acquisitioned farmland shall not exceed 15 times its average annual output value (AAOV) for the three years preceding such acquisition. (2) If woodland, grassland, reed pool, water surface and village collective-owned construction land are acquired, the standard resettlement subsidy of agricultural population needing resettlement shall be 4 times the average annual output value (AAOV) of preceding three years in nearest common farmland. However, the highest resettlement subsidy for each hectare of acquired land shall not exceed 10 times the average annual output value (AAOV) of preceding three years in nearest common farmland.

Article 27 Ground attachments and young crop compensation rate for acquired land should be as follows: (1) Young crop compensation is calculated at output value of one crop rotation; (2) As for the tree on acquired land, transplant should be organized if possible; the labor cost for the transplanter and loss of sapling should be compensated for. If trees are impossible to transplant, compensation should be pay after evaluation. (3) The attachments on acquired land shall be compensated for by converting into money according relevant regulation, or by reconstructing the same quality and same quantity as the former. Trees and green seeding planted during land acquisition period will not be compensated for, so are the constructions building during land acquisition period. Constructions and other establishments built on illegal-occupied land will not be compensated for.

Article 38 If project implementation and geology perambulation need to occupy state-owned land or collective-owned land temporarily, the examination and approval on temporary land

30

occupation should be conducted according to the Article 57 of Land Administration Law of the PRC. And compensation for temporary land occupation should be paid. The time for temporary land occupation should be no more than two years. If exceeding two years, the examination and approval on temporary land occupation should be conducted again.

Article 39 Compensation rate for temporary land occupation should be as follows: (1) When construction land within urban planning district is occupied temporarily, compensation should be calculated at the price of land use right in corresponding period. When construction land out of urban planning district is occupied temporarily, compensation should be calculated according to local temporary occupation compensation rate for common farmland. Ground attachments destroyed should be compensated for appropriately according to the actual condition. (2) Temporary farmland occupation should be compensated for according to AAOV for the three years preceding such acquisition; ground attachments destroyed should be compensated for appropriately according to the actual condition. (3) Temporary unused land occupation should be compensated for at 30% of the compensation rate for common farmland. The temporarily occupied farmland should revert by the construction entity within one year after expiry of temporary occupation.

Circular of Shandong Provincial Government Concerning the Adjustment of the Annual Output Value and Compensation Standard of Acquired Land (Lu Zheng Ban Fa [2004] No. 51) 1. Define the lowest standard of AAOV. According to the socio-economic condition of different places, the AAOV is divided into 4 types in Shandong Province in reference to the compensation for newly added construction land use. The detail standards are as follows: the first district is 1,800 Yuan/mu, the second district is 1,600 Yuan/mu, the third district is 1,400 Yuan/mu, and the fourth district is 1,200 Yuan/mu. The lowest AAOV is 1,000 Yuan/mu out of the urban planning area in the whole province. According to the socio-economic condition and difference of corps, municipal government can be compile specific, implementing standards on the basic of the lowest AAOV. And the modified standards should be submitted to Price-Fixing Bureau, Financial Bureau, and Land Recourses Bureau of Shandong Province. 2. Define the standard of land compensation. Land compensation includes land compensation, resettlement subsidy and young crop compensation. In reference to “The Implementation Regulations of Shandong Province for the PRC Land Administration Law”, the standard of land compensation and resettlement subsidy is defined on the basic of the AAOV. The multiple is not below the middle limit of the statutory multiple. The young crop compensation is defined by the municipal government, and is implemented after the approval of the Price-Fixing Bureau, Financial Bureau and Land Recourses Bureau of Shandong Province. When land acquisition is happened in the urban planning area, compensation standard should be defined reasonably in different places. 3. Set up hearing system of land acquisition. When the compensation standard is defined, hearing should be set up to hear the party’s statement. After defining the compensation standard, the results should be noted to accept supervision.

31

Appendix 2 Terms of Reference for External Monitoring

A Objectives of resettlement monitoring and evaluation In accordance with the requirements of ADB’s resettlement policies, it is to undertake external monitoring and evaluation for resettlement of Risk Mitigation of Endangered Reservoir Project in Shandong Province. Through monitoring the progress, funds mobilization and management of land acquisition, demolition and resettlement, it is to analyze and compare the changes and restoration of the production and livelihoods of the affected people, and thus to provide with follow-up evaluation in this connection. In addition to the regular reports (twice a year in resettlement implementation period) respectively submitted to ADB, JPMO and relevant competent authorities. This process shall also provide information and suggestions to all departments for implementation. Through external monitoring and evaluation, ADB and the project administrative agencies can have full understanding of the conditions and existing problems of land acquisition, demolition and resettlement, such as timely implementation of the resettlement plan, full achievement of the expected targets as well as the suggestions for improvement, etc.

B Major contents of resettlement monitoring and evaluation (1) Baseline Survey should include: (i) family information; (ii) household annual income and expenditure; (iii) affected land production and income loss; and (iv) affected informal land production and income loss. (2) Monitoring and evaluation of the progress of land acquisition include: (i) progress of land acquisition; (ii) progress of temporary land occupation; and (iii) progress of house demolition and reconstruction. (3) Monitoring and evaluation of funds mobilization and utilization include: (i) situation of in-place funds; and (ii) utilization of funds (planned and actual). (4) Monitoring the implementation of agreed rehabilitation measures, training programns, and post-reservoir development investment. (5) Monitoring and evaluation of living standards of relocated of people include: (i) production and living conditions before displacement; (ii) production and living conditions after displacement; and (iii) comparative analysis and evaluation of the employment and living conditions before and after displacement. (6) Evaluation of the capacity of resettlement institutions and the situation of public participation and complaints handling.

C External Monitoring Agency The external monitoring agency in this project will be undertaken by an external institution entrusted by SPMO and acceptable to ADB.

D Organization and work division for resettlement monitoring and evaluation  SPMO entrusts external institutions take charge of the investigation, date collection, computing and analysis about the monitoring and evaluation work, and review the research results;  The external monitoring institutes compose the Monitoring and Evaluation Group of the Risk Mitigation of Endangered Reservoir Project, the tasks of which conclude monitoring and evaluating the resettlement according to the Involuntary Resettlement Policy of ADB; designing an outline of the monitoring and evaluation work; setting the monitoring spot; monitoring field investigation and internal analysis; and preparing monitoring and evaluation reports in Chinese and English;  SPMO provides support in terms of staffing, contacting relevant officials, project documents and transport for the Independent Resettlement Monitoring and Evaluation Institution during on-the-spot monitoring and investigation.

E. Methods of resettlement monitoring and evaluation.

32

 Monitoring and evaluation shall adopt the combined methods of site survey, computational analysis and expert review;  The method of point-area method shall be adopted in the survey. The progress, funds, organizations and management of resettlement implementation shall be fully explored; the progress, funds, organizations and management of the resettlement implementation shall be fully explored. Sample survey shall be conducted for the APs;  The random sampling method shall be adopted in the sampling survey, while the typical samples shall be followed up for survey. (Samples are taken and categorized among all the affected households involved in the socio-economic surveys at the project preparatory stages. It is primarily decided that all households affected by land acquisition are sampled. All of the vulnerable groups if any are surveyed as sample families). The methods of tabular format survey, interview discussion, archives consultation etc. shall be adopted in the full-coverage survey;  In addition to the written materials, other materials such as photos, recordings, videos and articles in-kind shall be also collected.

F M&E Report for resettlement external monitoring According to the requirements of ADB and the project schedule, the external monitoring and evaluation agency would submit to ADB and SPMO the monitoring report twice a year during resettlement implementation, followed by two annual evaluation reports. The last report will be prepared as a resettlement completion report (i.e., summarizing the entire process and results).

33