<<

ADDITIONAL INFORMATION TO EAC INDUSTRY-2 (MoEFCC) Installation of Polypropylene unit at , Taluka, , and interconnecting pipelines from M/s BPCL Refinery to Rasayani

Query 1: Details of protected area/ESA/ESZ within 10 km of the project area/pipeline route. Details of NBWL clearance and its updated status. Reply: The pipeline route is falling within the deemed ESZ area of Creek Flamingo Sanctuary and it is located at a distance of 5.5km from Protected Area of Thane Creek Flamingo Sanctuary. The pipeline route is falling outside of ESZ of Karnala Bird Sanctuary and the nearest distance is 1 km from ESZ boundary.

Draft Notification for Thane Creek Flamingo Sanctuary ESZ areas has been published by MoEFCC on 06/11/2019. Online application was submitted on Parivesh Portal for Wildlife Clearance for the pipelines passing through Thane Creek Flamingo Sanctuary on 09/08/2019 (Annexure I). Wildlife Clearance is not required for Karnala Bird Sanctuary as the pipelines falls outside of the ESZ areas. The Wildlife proposal has been forwarded by DFO, Wildlife () on 06/12/2019 to APCCF (Mangrove Cell), Mumbai for onward processing. Copy of the same is attached for reference (Annexure II).

Query 2: Details of pipeline route passing through mangrove area, details of area to be diverted and conservation plan.

Reply: The proposed pipeline is passing through mangroves of 7.8012 Ha (5.3200 Ha Mangrove Forest (not Notified) & 2.14812 Ha – u/s 4 of IFA 1927) in Mahul region. The pipeline is also passing through 14.4658 Ha mangrove areas in Alibaug region. Divisional Forest Officer, Mumbai Mangrove Conservation Unit has recommended the proposal for further approval. Letter from Additional Principal Chief Conservator of Forests, Mangrove Cell, Mumbai is attached for reference (Annexure III).

The pipeline is passing through CRZ-IA (Mangroves) for a length of 2644.93 m as per CRZ Report prepared by M/s Institute of Remote Sensing, Anna University, Chennai. A detailed mangrove conservation plan is attached in Annexure IV.

Query 3: Details of raw material/product taken through pipeline with quantity.

Reply: The proposed Rasayani Polypropylene complex project also envisages feed material pipelines from BPCL-Mumbai Refinery to Rasayani plant. To feed the petrochemical plant BPCL envisages laying following pipelines to Rasayani (District Raigad) Maharashtra. The details of pipelines are as below:

1

Pipelines From BPCL-MR to Rasayani Plant Diameter Capacity Propylene Pipeline 8” 0.45 MMTPA Multi product Pipeline (MS/ HSD/ SKO/ATF/Naphtha) 18” 6.4 MMTPA Lube Oil Pipeline 10” 0.45 MMTPA Unconverted Oil (UCO)/ Light Gas Oil (LGO) Pipeline 10” 1 MMTPA

Query 4: Action plan vis-à-vis CRZ recommendations/conditions from the SCZMA needs to be submitted.

Reply: The proposed pipelines, which are feed to proposed PP Plant at Rasayani are passing through coastal area and marine spread and hence as per TOR we had conducted CRZ Study through Anna University and Marine EIA Study from NIO. Subsequently after conducting EIA & RRA for entire project, BPCL applied to MCZMA, Mumbai on 18.07.2019 for CRZ clearance. MCZMA discussed our proposal vide their 138th Meeting held on 10.10.2019 had approved the project under CRZ Notifcation’2011. MCZMA recommended the proposal vide letter no. CRZ 2019/CR 153/TC 4 dated 19/11/2019. The action plan to the recommendations from the MCZMA is provided below.

BPCL undertake the responsibility for fulfilment of all 10 conditions mentioned in MOM and they are mentioned below in seriatim.

1. BPCL undertakes the responsibility that it shall be carrying out pipeline laying works strictly as per the provisions of CRZ Notification ’2011 (as amended from time to time) and guidelines/clarifications given by MoEF from time to time.

2. BPCL undertakes the responsibility that it shall be obtaining prior Hon. High Court of Bombay permission before commencement of pipeline laying activities, as the project involves removal of mangroves. We wish to inform that we had already applied to Forest Clearance (involving mangroves) on 31.03.2019 vide our application ref. FP/MH/Pipeline/39455/2019 and after obtaining approval from MoEFCC, we shall be applying to Hon. High Court for permission to disturb mangroves as per the laid down procedure by Hon High Court of Bombay.

3. BPCL undertakes the responsibility to obtain NOC from Mangrove Cell and shall be doing compensatory mangrove afforestation as advised by MoEFCC or / and Mangrove Cell, Mumbai. We wish to inform that while processing Forest Clearance for the project Mangrove Cell has already recommended BPCL proposal and forwarded proposal to DCF, for onward processing. Copy of same is enclosed herewith.

4. BPCL undertakes the responsibility to obtain Forest Clearance, under Forest Conservation Act, 1980. An application in this regard is already filed to Forest Department vide application ref. FP/MH/Pipeline/39455/2019 on 31.03.2019.

2

5. BPCL undertakes the responsibility to carry out site preparation, installation of pipeline and site restoration without damaging the coastal–geomorphological features, mangrove vegetation present in CRZ area.

6. BPCL confirms that the two end points of pipelines across coastal water body are in Non CRZ area.

7. BPCL undertakes the responsibility that the pipelines shall be laid at a depth of 2.5 m (approx. 10 feets), wherever mangroves are present / in intertidal area.

8. BPCL undertakes the responsibility that natural course of coastal water bodies should not be hampered due to proposed activities and BPCL shall undertake proper measures to avoid contamination of creek water.

9. BPCL undertakes the responsibility to implement all safety measures during construction and operation phase of project.

10. BPCL undertakes the responsibility to obtain all other required permissions from various statutory authorities, as applicable prior to commencement of work.

MCZMA recommended letter dated 19/11/2019 with Specific and General Condition is attached in Annexure V.

Query 5: The Committee noted that the project involves forest land. However PP is unable to explain to provide the details of status of forest clearance and accordingly PP needs to be submitted the details of FC proposal and its status.

The pipeline is passing through 26.0494 Ha forest areas of Mumbai Sub-urban district (7.8012 Ha) and Raigad (18.2482 Ha) district of Maharashtra. Out of which, 7.8012 Ha mangrove area falls in mahul division and 14.4658 Ha in Alibag division. A total of 3.7824 Ha of other forest areas also falls in Alibag division.

Online application was submitted on 31/03/2019 (Parivesh Portal) for Forest Clearance the pipelines passing through forest areas. The submitted Form A for Forest Clearance is attached in Annexure VI. The Forest proposal for Mahul areas mangroves (7.8012 Ha) has been recommended by APPCF (Mangroves), Mumbai on 08/11/2019. Joint Field Survey by Divisional Forest Office, Alibag is under progress for Alibag forest area.

Query 6: Details of rivers in the vicinity of the project site and details of mitigation measures to avoid pollution of rivers.

Reply: Patalganga river is 800 m from the proposed project site at Rasayani. The pipeline is crossing the and Kirki rivers on the way to Rasayani.

3

This will be a Zero-Liquid Discharge (ZLD) plant. The treated water will be reused as cooling tower make up. So, it can be noted that there is no impact on account of the waste water generation on the nearby Patalganga river.

The pipeline is crossing the rivers through Continuous Concrete Weight Coating (CCWC) method. There is no process emission from pipelines. Hence, there will be no impact on the rivers on which the pipelines are crossing.

Query 7: Details of map as per requirements under CRZ Notification needs to be submitted.

Reply: The CRZ mapping is carried out by M/s Institute of Remote Sensing, Anna University, Chennai. The CRZ report and maps are attached Annexure VII.

Query 8: Onsite emergency plan as per MSIHC Rules.

Reply: BPCL has developed a comprehensive Emergency Response and Disaster Management Plan (ERDMP) for their Mumbai Refinery. The document is prepared in line with the Petroleum and Natural Gas Regulatory Board (PNGRB) guidelines which defines and specifies roles and responsibilities, classification of emergencies, coordination within and outside agencies etc. The document is strictly in compliance with the PNGRB guidelines and no deviation from the guidelines. ERDMP for proposed Rasayani project shall also be developed in line with the existing ERDMP for BPCL Mumbai Refinery and as per MSIHC Rules. For proposed Rasayani Polypropylene project the emergency response plan guidelines are discussed below.

The project manager shall ensure that suitable instructions are issued to both BPCL and contractors personnel, identifying the action to be taken by each one in an emergency. This shall be achieved by display of organization chart/posters not only for firefighting but also other emergencies of large magnitude. A detailed Emergency/Disaster response plan (or DMP) will be drawn out in co-ordination with police authorities, fire brigade, hospitals, and neighboring industries. The plan considers organization set up, communication cell for information exchange, availability and mobilization procedure of resources for emergency situation and provision of mutual aid.

The best way to manage any emergency is to prevent it. The guidelines to be ensured for emergency prevention shall be as follows:

Sound engineering practice in the design fabrication, installation and maintenance of facilities: • Careful selection and correct use of equipment • Observance of safety and security requirement • Proper and constant training and guidance to all personnel working in the plant, with particular reference to product knowledge and maintenance practices

4

• Good house keeping • Constant supervision

BPCL will develop integration of existing on-site Emergency Response Plans (ERPs) with the proposed facilities to enable it to respond effectively to an emergency. These plans will address the following issues: • Emergency Response Organization • Alarm and Communication Rules • Contingency Plans for dealing with the emergency • Co-ordination between the various emergency response teams, both within the complex as well as emergency response teams from outside the Complex • Incident notification procedures • Community notification and Evacuation

Existing Emergency Control Centre (ECC) shall be the focal point to co-ordinate emergency response activities. An alternative control centre will also be selected if it is anticipated that the ECC is likely to be affected by heat wave radiation of other hazards from the proposed facilities. Adequate personal protective/safety equipments will be provided at the ECC. Emergency procedures shall be displayed along with the telephone numbers at appropriate locations in the proposed facilities.

On-site Emergency Response Plan

The on-site Emergency Response Plan (ERP) shall be prepared for the proposed facilities at Rasayani Complex. This shall deal with steps the complex staff will take to control an emergency within the proposed facilities. It has been developed in accordance with BPCL principles and local regulations, and shall include information on the following:

• The emergency response training and drill programs required to maintain emergency response preparedness • The company's emergency response organization, including a description of the make up, function and purpose of the emergency response teams. Alternates will be identified to assume responsibilities in case disaster occurs in the absence of principal coordinators. • Checklists will be developed for each member on the emergency response teams, which include a written description of the duties, responsibilities and authorities for each designated employee • Role of local authority when responding to emergencies • Alarm and communication system, including procedures for ongoing emergency communications • Detailed contingency plans for dealing with the most likely types of emergencies that can occur. These will include emergency procedures for safely shutting down operations • Procedure for reporting incidents to the appropriate authorities • Plan appraisal and updating

5

Query 9: Plan for Corporate Environmental Responsibility with activities and timelines.

Reply: BPCL is committed to undertake Corporate Environment Responsibility (CER) initiatives at Rasayani under the following thrust areas adopted by BPCL management:

 Quality Education  Water conservation  Skill Development  Health & Hygiene including Swatcha Bharat Initiatives  Community development

Corporate Environment Responsibility (CER) is planned for next 5 years and around 40 crores will be spent for the development of surrounding areas & betterment of people.

Presently, BPCL has carried out Refurbishment of nearby ITI at for benefit of the students at an expenditure of Rs. 68 Lakhs. Also, BPCL will be carrying out plantation of trees in nearby 17 acres plot of forest land. Around 5000 trees will be planted at an expenditure of about Rs. 1 Cr.

In order to assess and identify the needs of the local community village wise at Rasayani, we have commissioned Tata Institute of Social Sciences (TISS) to carry out a survey and submit a need assessment report. The study was conducted with mixed method design. Socio-economic profile, aspects of quality of life and livelihood are assessed through quantitative methods, while qualitative methods have been applied to go in-depth about the needs of the community.

Broad areas for intervention have been identified are listed below. Short term measures are within 1-2 years and long term measures are 3-5 years.

1. Living Environment and Housing Condition

Short-Term Measures –  BPCL will mark and provide a proper place for waste disposal. They may do the provision of garbage bin in the area.  BPCL will help the Gram Panchayat to regularize the circulation of Ghanta-Gadi. It may help the Panchayat to clean all the filths in and around the villages.  BPCL will upgrade the community toilets in the area.  BPCL will get the help of community volunteers to run the cleanliness campaign in their area and make the people aware about it.

Long-Term Measures –  BPCL will do the beautification and install adequate street lights.  BPCL will do the beautification of the community spaces.  BPCL will create some public utilities in the villages.

6

 With the help of panchayats, they may do the enlisting of public utilities in the area and its condition.

2. Drinking Water

Short Term Measures –  Channels of water supply should be maintained properly by MIDC, the CSR wing of BPCL will mediate the process between the community and MIDC.  Every village shall get connected to the supply line of water.  Cleanliness around public tap should be maintained in villages and wadis where poor and SC/ST/OBC and migrant population are concentrated.  The small water reservoirs and well shall be cleaned.

Long-Term Measures-  BPCL will find the scope of rain water harvesting in the area. The villages which have enough agricultural land shall get preference for it.  BPCL will try to upgrade the existing reservoir with the collaboration of stakeholders.  BPCL will try to develop the watershed and eco-system of the area with the collaboration of stakeholders.

3. Human resources, employment and skill development

Short-Term Measures-

BPCL will collaborate with an existing skill development center (Vocational Training Provider) in local area -

It will provide soft skills, important industrial skills, basic IT skills, English coaching and career counselling to the local youths. It will get accreditation from NSDC. Skilled youth of the local area who do not have any formal certification of their skills will be connected to it to get a formal certification. The center will also register the educated but unemployed youth with them. The selection of courses in skill development center shall be based on demand driven, which can be identified through industrial survey. This skill development center will also work as library and computer center for the local youths. They can culture and discipline themselves at there and learn professional mannerism. Youths will also get a basic business skill to try their future in self-employment.

BPCL will also facilitate some scholarship program in the local area. It will also facilitate the local talents who have done excellent in their profession.

Long-Term Measures-  BPCL will try to organize youths by creating facilities like gym, facilities of indoor games, cricket or football clubs and forming organizations for youths and try to win their participations through it.  Youth shall be made aware and competent enough to grab the opportunities outside the area, they shall be encouraged to migrate for it.

7

 BPCL will play the role of mentor for all round development of youths in the area.

4. Morbidity and Health services

Short-Term Measures-  BPCL will provide PHC in the area and health activities shall be done in a coordinated manner.  BPCL will take initiative through mobile medical van to provide some basic health check-ups like blood test, sugar and BP test etc. Record of each of the patients shall be kept with their background information.  It will help the community to get the medicine prescribed by the doctor.  A small team of community volunteers consisted by educated local youths shall be built to give the people basic awareness about health, preventive measures and provide counselling to the individuals and access to doctors. They will work as goodwill ambassador within the community.  The maternity care especially in areas dominated by poor and SC/ST/VJNT and OBC population shall be strengthened. Medicine kits and nutrition supplements shall be made available to them.  BPCL community volunteers will help the people to avail the insurance services and other health related schemes in the area.

Long-Term Measures-  An ambulance will be provided for referral services and emergency hospital admission.  BPCL will facilitate health services through the specialist doctors.

5. Agriculture and common property resources

Short-term Measures-  Water bodies and common property resources in the area will be improved.

Long-Term Measures-  Farmers shall be encouraged for horticulture, in which less land is required but its yields more and it is more commercial in nature.  Watershed of this area will be developed and bio-diversity will be enriched.

6. Social asset and entrepreneurship

Short-Term Measures-  The youth of this area shall be provided basic training of entrepreneurship aptitude and accounting.  Youths should be encouraged to start venture in group.  Existing SHG shall be facilitated further.  Demands in local market will be identified to give training and suggestions for youths and SHG women.  Women empowerment initiatives for developing sense of commitment among women for doing business.

8

As per suggested methodology by the EAC committee during 14th EAC meeting dated 22nd Nov 2019, the revised CER budget is as follows:

S. NO Capital Cost Amount Percentage for Amount (Crores) Applicable Green Field (Crores) Project 1 Less than 100 100 2.0 2.0 2 100-500 400 1.5 6.0 3 500-1000 500 1.0 5.0 4 1000-10000 5432 0.5 27.16 Total Amount 40.16

Total budget for CER activities will be around Rs 40 Crores and the amount will be spent in 5 years. Budget with CER activities is provided below.

S No Activity Amount (Crore) 1 Living Environment and Housing Condition 4 (Short & long term measures) 2 Drinking Water (Short & long term measures) 12 3 Human resources, employment and skill 6 development (Short & long term measures) 4 Morbidity and Health services 10 (Short & long term measures) 5 Agriculture and common property resources 5 (Short & long term measures) 6 Social asset and entrepreneurship 3 (Short term measures)

Query 10: The Committee noted that there are Schedule I species in the study area. PP needs to prepare the species specific conservation plan along with budgetary allocation and PP to take approval for the Wildlife conservation and management plan from CWLW State Government.

Reply: Two schedule I species i.e. Indian Python and Monitor Lizard are fund in the 10 km surrounding of the Rasayani site. They are not found in the project site. BPCL shall consult with the Forest and Wildlife Department of Government of Maharashtra and formulate a plan for conservation of the species. An amount of Rs. 50 lakhs will be spent to conserve the species. The broad procedure for conservation of species is as follows.  A thorough site survey will be carried out by fauna specialist to enumerate the number of species.  Special cage will be prepared to conserve the Indian Python snake with help from local Forest Department.  Habitat will be developed for the schedule I species.

9

Query 11: Issues raised during public hearing, response by the project proponent, action plan with budgetary allocation needs to be submitted. All Annexures of Public hearing proceedings needs to be submitted.

Reply: In all, 505 written queries & questions were received during the Public hearing at Rasrang Hall on 24th Sept 2019 about BPCL’s Polypropylene and cross country Pipeline project. However, on close scrutiny of the letters it is noticed that most of the letters are having same content and are identical copies with different signatories. Hence these letters were clubbed and consolidated replies are given as below:

Pattern Signatories of No. of General Content of BPCL Reply letters from Letters letters Villages A Turade, Savle, 267 The project will Based on EIA report, all Dapivali, lead to pollution environmental parameters Chambharli, and it will affect will remain well within Devloli, Navin the people’s prescribed limits during Posari, health. This will construction & operation Khane Ambivali cause diseases like phases of the project. cancer, deficiency Propylene is the major raw in reproductive material and it is non-toxic, system and general non-carcinogenic, non- health problem. mutagenic & non- teratogenic, so the apprehensions are incorrect.

Further, state of the art facilities with integrated environmental and safety controls conforming to relevant Indian & International standards will be built for safe handling of raw materials and products. B Dapivali 81 The project is very Environmental Impact close to our village. assessment is carried out The project is at and does not show any 500 mtr. Distance adverse impacts on Karnala from Karnala Bird BS. Sanctuary. The project is Based on EIA report, all dangerous to environmental parameters human life and will will remain well within cause diseases like prescribed limits during cancer, construction & operation

10

reproduction phases of the project. problem etc. deficiency in Propylene is the major raw reproductive material and it is non-toxic, system etc. non-carcinogenic, non- mutagenic & non- teratogenic, so the apprehensions are incorrect.

Further, state of the art facilities with integrated environmental and safety controls conforming to relevant Indian & International standards will be built for safe handling of raw materials and products C Dapivali 83 This project is BPCL has a Refinery in shifted from Mahul area and LPG and as it is plant at Uran. The subject is creating health a new plant and not being problems in that shifted from Chembur or area. There is a Uran. population of 40,000 to 50, 000 Based on EIA report, all within a distance of environmental parameters 3 to 4 km from the will remain well within project location. prescribed limits during construction & operation phases of the project. Propylene is the major raw material and it is non-toxic, non-carcinogenic, non- mutagenic & non- teratogenic, so the apprehensions are incorrect.

Further, state of the art facilities with integrated environmental and safety controls conforming to relevant Indian & International standards will be built for safe handling of raw materials and products.

11

D Mohopada, 74 This project is Based on EIA report, all Wasambe, dangerous to environmental parameters Chambarli, human being and will remain well within Khane Ambivali, animals. There is a prescribed limits during possibility of gas construction & operation leak incident like phases of the project and Bhopal. This does not show any adverse project will cause impact on surrounding disease like cancer, areas. Propylene is the skin diseases and major raw material and it is asthma. This will non-toxic, non-carcinogenic, cause environment non-mutagenic & non- pollution. teratogenic, so the apprehensions are incorrect.

Further, state of the art facilities with integrated environmental and safety controls conforming to relevant Indian & International standards will be built for safe handling of raw materials and products. E Grampanchayat 2 There is no buffer The Pipeline Right of User Devloli (Sarpanch) zone between will be acquired as per Villages, Houses provisions of Petroleum and and project. The Minerals Pipelines details of pipeline (Acquisition of Right of User passing through inland) Act, 1962. The route the land and maps and other details have Gavthan. We are been frozen by BPCL and not clear how the submitted to SDO, Panvel project will affect who is Designated as the land and Competent Authority under property belonging the Act. After scrutiny by to people. Hence Revenue Department, the permission to be final route details will be granted only after published in all leading submission of Land Newspapers. All necessary Survey Numbers NOCs will be obtained by and NOC from BPCL before MMRDA and commencement of pipeline MSRDC. laying works. F Group 1 This project is The subject is a new plant Grampanchayat, being shifted from and not being shifted from

12

Wasambe- Chembur Mumbai. Chembur or Uran. State of Mohapada There was an the art facilities conforming (Sarpanch) explosion in to relevant Indian & Chembur plant on International standards with Dated: 8-8-2018. fail-safe systems will be People are afraid built for safe handling of because of this raw materials and products. incident. There is danger to human Rapid Risk Assessment life because of this study has been carried out project. for proposed facility and its recommendations will be suitably implemented. G Group 1 It is understood Based on EIA report, all Grampanchayat that BPCL Company environmental parameters Waveghar project will will remain well within (Gramsevak) generate prescribed limits during poisonous gas and construction & operation liquid. People are phases of the project and afraid that this will does not show any adverse cause danger to impact on surrounding human life in this areas. area. Propylene is the major raw material and it is non-toxic, non-carcinogenic, non- mutagenic & non- teratogenic, so the apprehensions are incorrect.

Further, state of the art facilities with integrated environmental and safety controls conforming to relevant Indian & International standards will be built for safe handling of raw materials and products. H Mohan Balkrushna 1 This letter gives Deshmukh references of (Devloli) various documents related to incidents such as explosion in Mumbai refinery on 8-8-2018. The incident of gas leak

13 in ISRO plant on 13-12-2018 and paper articles. Suggestions / Objections mentioned are 1. Land 1. There is no land acquisition act acquisition. Land parcel 1963 to be is been procured from applied HOCL as part of 2. This project is restructuring plan at 300 m from approved by NITI Ayog ECO sensitive 2. Yes- project is outside zone from the Eco sensitive zone of Karnala Bird Karnala Wild Life Sanctuary sanctuary 3. Resettlement of 3. There is no resettlement people should of people – the proposed be done as per PP project will be 2013 act. entirely within HOCL 4. Buffer zone factory plot should be 4. For Pipelines all statutory applied. buffer zones shall apply 5. 33% area 5. Green belt will be should be developed as per MOEF develop as & CC Norms green belt. 6. Yes- will be maintained 6. Minimum 68 m distance to be left between pipeline and houses. 7. Yes- process is currently 7. Pipeline land ON survey numbers to be verified for any legal matters. 8. Yes- will be done 8. Environmental regularly during entire parameter to project life cycle be checked and limits to be followed 9. Yes- CER funds will be 9. implementation used for Health, Social of CSR activities welfare and education as about committed during Public education and Hearing health should

14

be mention 10. K.E.M. Hospital 10. Mahul is a complex area has observed having very large amount that people in of traffic and industrial Mahul are sources – there is no affected by direct linkage to BPCL breathing attributed in the KEM problems, Skin report for Mahul. problems, Eyes problems and Hair problems. This should be noted while giving permission to the project. 11. Project affected 11. All recruitments will be people should carried out as per be made Government norms. shareholders and should be given priority in job all location. I Khane Ambivali 1 BPCL project is Based on EIA report, all dangerous project. environmental parameters It is close to human will remain well within population of 1 prescribed limits during lakh. It should be construction & operation made clear that phases of the project and who will give does not show any adverse Compensation if impact on surrounding there is any areas. Further, state of the explosion or Death art facilities with integrated of people due to environmental and safety project. Also there controls conforming to is water shortage in relevant Indian & this area. International standards will be built for safe handling of raw materials and products. Water will be sourced from MIDC.

Hard copy of the written applications received from public will be submitted to MoEFCC by Hand (Annexure VIII). The amount Rs. 40 crores will be spent for the issues raised during public hearing.

15

Query 12: The Committee also noted that the project involves CRZ issues and accordingly the comments from CRZ sector also needs to be obtained by the Sector before placing the project in the EAC. Reply: Noted. BPCL officials visited the MoEFCC office on 25/11/2019 and discussed with concerned officials who are handling the CRZ issues and submitted the requisite CRZ documents for the proposed project.

16

8/11/2019 Wild Life Report

Wild Life Report

Form for seeking recommendation of Standing Committee of NBWL/SBWL.

PART - I & II (To be filled up by User Agency)

A. General Details

A-1. Project Details

(i). Forest Clearance Required?: Yes

(a).Forests Clearance Type : Fresh

(ii). Proposal No. : FP/MH/Pipeline/39455/2019

(iii). Name of Project: Proposal for Installation of Polypropylene (PP) unit at Rasayani and Interconnecting Pipelines from BPCL Mumbai Refinery (MR) to Rasayani

(iv). Short narrative of the Project : Diversion of Forest land for construction of under ground petroleum pipe lines from Mahul (Mumbai suburban) to Rasayani (Raigad) in Maharashtra

(v). State : Maharashtra

(vi). Category of the Project : Pipeline

(vii). Shape of project land : Linear

(viii). Distance of the project from the boundary of the Protected Area (in km.): 5.5

(ix). Estimated cost of the Project(Rupees in lacs) : 260500

(x). Total period for which clearance is required (in year): 99

(xi). Total Project Area(in ha.): 129.9612

(xii). Area of Forest Land required for this Project(in ha.): 26.0494

(xiii). Non-Forest Land required for this Project (in ha.): 103.9118

(xiv). Forest Land within Protected Area(in ha.): 0

forestsclearance.nic.in/Admin/UserAgency_Report_W.aspx?pid=FP/MH/Pipeline/39455/2019 1/6 8/11/2019 Wild Life Report

(xv). Non-forest Land within Protected Area (in ha.): 0

(xvi). Project Area under Protected Area(in ha.): 0

(xvii). Project Area under Non-Protected Area (in ha.): 129.961

(xviii). Project Area inside Wildlife Sanctuaries(in ha.): 0

(xiv). Project Area outside Wildlife Sanctuaries(in ha.): 71.093

(xv). Project Area inside Conservation Reserve(in ha.): 0

(xvi). Project Area outside Conservation Reserve(in ha.): 0

(xvii). Project Area inside National Park(in ha.): 0

(xviii). Project Area outside National Park(in ha.): 0

(xix). Project Area inside Ecologically Sensitive Zone(in ha.): 0

(xx). Project Area outside Ecologically Sensitive Zone(in ha.): 0

A-2. Details of User Agency

(i). Name : BHARAT PETROLEUM CORPORATION LIMITED MAHUL RASAYANI PIPELINE

(ii). Address1 : BHARAT PETROLEUM CORPORATION LIMITED

(iii). Address2 : A INSTALLATION SEWREE ROAD SEWREE EAST MUMBAI 400015

(iv). State : Maharashtra

(v). District : Mumbai City

(vi). Pin : 400015

(vii). Landmark : SEWREE FORT ROAD

(viii). Email address : [email protected]

(ix). Landline Telephone No. : 24176222

(x). Fax No. : NIL forestsclearance.nic.in/Admin/UserAgency_Report_W.aspx?pid=FP/MH/Pipeline/39455/2019 2/6 8/11/2019 Wild Life Report

(xi). Mobile No. : 9769378989

(xii). Website (if any) : NIL

(xiii). Legal status of User Agency : Central PSU

A-3. Details of Person Making Application

(i). First Name: KRISHNA

(ii). Middle Name: KUMAR

(iii). Last Name: DAMDE

(iv). Gender: Male

(v). Designation: PROJECTLEADER

(vi). Address 1: BHARAT PETROLEUM CORPORATION LIMITED A INSTALLATION

(vii). Address 2: SEWREE FORT ROAD SEWREE EAST MUMBAI

(viii). State: Maharashtra

(ix). District: Mumbai City

(x). Pin: 400015

(xi). Landmark: SEWREE FORT ROAD

(xii). Email Address: [email protected]

(xiii). Landline Telephone No.: 24176222

(xiv). Fax No.: NIL

(xv). Mobile No.: 9769378989

(xvi). Upload a copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure copy of documents in support of the competence B. Details of Land required for the Project forestsclearance.nic.in/Admin/UserAgency_Report_W.aspx?pid=FP/MH/Pipeline/39455/2019 3/6 8/11/2019 Wild Life Report

B-1. Details of Protected Area

B-1.1 No. of Divisions involved in Protected Area

Division wise details of land

Project Area Protected Area S.no Division Name under Protected Name Area 1. Mangrove THANE CREEK 0 FLAMINGO SANCTUARY

B-1.2 Details of Districts involved

District wise breakup Project Area Project Area under Non- S.no District Name under Protected Protected Area(ha.) Area(ha.) 1. Mumbai (Suburban) 0 37.5403 1. Thane 0 29.3527 3. Raigad 0 0

B-1.3 Component wise breakup

Component wise breakup Project Area Project Area under Non- S.no Component under Protected Protected Area(ha.) Area(ha.) 1 Laying of pipeline 0 67.424 2 Laying of pipeline 10m wide 0 0.266 3 Laying of pipeline 40 m wide 0 0.8

4 Laying of pipeline 5 m wide 0 2.599

C. Maps of protected area

Division 1. : Mangrove

(i). Project Area under Protected Area (in ha.) : NIL

(ii). Nature of the Project : Linear

(iii). No. of Segments : One

Patch/Segment wise details Protected Area of KML file of protected Segments segment(in ha.) area of segment forestsclearance.nic.in/Admin/UserAgency_Report_W.aspx?pid=FP/MH/Pipeline/39455/2019 4/6 8/11/2019 Wild Life Report

1. 0 View File (iv). copy of Survey of Toposheet indicating boundary of protected area: Annexure Survey of India Toposheet

(v). scanned copy of the Geo-referenced map of the protected area prepared by using DGPS or Total Station: Annexure scanned copy of the Geo-referenced map

D. Justification for locating the Project in protected area and details of alternates examined :

(i). copy of note containing justification for locating the Project in protected area: Annexure Justification

(ii). Whether a copy of map indicating location of alternative examined is required to be provided: Yes

(a). copy of map indicating location of alternative examined: Annexure alternative examined

E. Employment likely to be generated

(i). Whether project is likely to generate employment ?: Yes

(a). Permanent/Regular Employment(Number of persons): 10

(b). Temporary Employment(Number of person-days): 247500

F. Displacement of People due to the project, if any

(i). Whether project involve displacement?: No

G. Status of Environmental clearance

(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes

(a). Status of the Environmental Clearance to the Project : EC under process

(ii).Environmental Clearance File No.: IA-J-11011/168/2018-IA-II(I)

H. Whether proposal is for investigation/survey

(H- Details of the Bio diversity Impact Assessment report in case the proposal involves use of more than 2). 50 ha. NP/WLS.

(a).Copy of the Bio diversity Impact Assessment report: Annexure Copy of Bio diversity Impact Assessment report (H- forestsclearance.nic.in/Admin/UserAgency_Report_W.aspx?pid=FP/MH/Pipeline/39455/2019 5/6 8/11/2019 Wild Life Report 3). Information on the projects undertaken by the proponent agency in the past in Protected Areas

(a).Upload file: Annexure Information on the projects undertaken by the proponent agency in the past in Protected Areas

(H- Details regarding compliance of the conditions on each proposal 4).

(a).Upload file: Annexure Details regarding compliance of the conditions on each proposal (H-5).Whether any matter related to the project is sub judice in any court of law?: No

Documents

S.No Uploaded Additional Info. Files Remarks 1 Additional Info. Employment generation report 2 Additional Info. Document verification certificate 3 Additional Info. undertaking for EC &CRZ 4 Additional Info. FCA proposal acknowledgement

Print page

forestsclearance.nic.in/Admin/UserAgency_Report_W.aspx?pid=FP/MH/Pipeline/39455/2019 6/6

Office of the Divisional Forest Officer Mumbai Kandal Forest Conservation First Floor, near Tilaknagar Railway Station, Kula 400 024.

Letter

Outward no. /Survey/1764/2019-20 Kurla Mumbai - 400 024 Dated-06.12.2019 To, Additional Principal Chief Conservator of Forests, Kandal Forest Unit, Mumbai

Reference: Central Government Guidelines Sr. no. F.No. 6-10/2011 WL- 19/12/2012

As per the writ petition (sic) no-460/2004 date 04.12.2006 of the Honorable Supreme Court, according to the court order the project which requires environmental approval under the Environment (Protection) Rule and which is within the 10 km distance from the Sanctuary / National Park or within its eco-sensitive zone, such projects requires the approval of the Standing Committee of the National Wildlife Board. .

Government of India, Ministry of Environment and Forests has issued the guidelines for working in the sanctuary FNo. 6-10/2011 WL- 19/12/2012 released on 19/12/2012.

This office has received a proposal from General Manager, Bharat Petroleum Corporation Limited regarding the OFC in TCFS and its ESZ with the BPCL project of Laying 18 "dia petroleum product pipeline. The proposed area of this project appears to be passing through the human environment sensitive area of the Thane Bay Flamingo Sanctuary. According to the relevant guidelines, the proposal is submitted in 3 copies along with information from Annexure -I and Part – I, II for approval of the State Wildlife Board and the National Wildlife Board, as the sanctuary's human environmentally sensitive area is being disrupted.

This proposal has been proposed by the project system online. As the project is going through the environmentally sensitive area of the Thane creek Flamingo Sanctuary, 2% of the amount spent on the project in this area is recommended to be deposited to the Kandal Forest and Marine Biodiversity Establishment for remedies for conservation in this area.

Divisional Forest Officer, Mumbai Kandal Forest Conservation Unit

CC : Project Leader, BPCL, Rasayani Scanned by CamScanner Scanned by CamScanner Annexure IV

Mangrove management & Conservation Plan

The entire pipeline laying activity at off shore area shall be done by subsea method. While open cut method shall use for pipeline laying activity at on shore area and it shall be done by on developed area i.e. by side of road or in private land to be acquired by PMP Act. There will be temporary disturbance to Mangroves as the mangrove will be re-grown after laying the pipeline.

Approximately 4.171 km pipeline section shall passes through mangrove and mudflat area located on both ends of sub-sea portion.

During the construction of pipeline by using sub-sea method following points shall considered.

The entry & exit point sub-sea operation shall be on sparse mangrove area. Additionally, as a precautionary measures the entry and exit pits shall be provided with earthen bunds to prevent sudden ingress and egress of surface water. Due to usage of heavy construction equipment’s, DG sets, movement of labors at site etc. there are changes of disturbance to mangroves.

Thus project proponent will conserve the mangrove resource for maximum benefit to humans (involving preservation in some instances, sustainable product harvesting in others and restoration in still other instances); and to minimize those non-sustainable or conversion activities that lead to destruction of the mangrove resource.

The measures have been ensured for various stages involved in the construction of a pipeline viz. clearing and grading, trenching, stringing, bending, welding, joint coating, lowering in, backfilling, fabrication and tie-ins, hydrostatic testing and restoration.

The barges, cranes or vessels involved in the pipeline laying work should be in a proper condition with no leakages of oil, petrol, diesel, grease which can lead to leakage of pollutants to the sea. Turbidity monitoring can be performed periodically to ensure compliance with water quality standards. If at any time the turbidity levels are estimated to be approaching the turbidity exceeds criterion the work can be suspended temporarily. If required silt curtains, as well as careful selection of the dredging method, could be implemented in minimizing dispersal of re-suspended sediments. No waste should be directly released into the creek.

The intertidal and near shore sub tidal areas should be restored to their original contours once the pipeline laying activities are completed. General clean-up along the corridor areas should be undertaken and discarded materials including excavated soil from the site and the aesthetic quality of surroundings should be restored on completion.

Page 1 of 2

Annexure IV

Mangroves are well adapted to natural phenomena such as (erosion and accretion, storms and floods) and quickly recover from this disturbance without the need for planting. Regular assessment should be carried out to detect the mangrove health condition. Planting is the most favorable method, it can be done using seeds, propagules or seedling; the latter can be from nurseries or transplanted from other sites.

As a first important step towards the maintenance of health of the marine ecology of the study area, critical locations are to be carefully selected around the project as monitoring sites for periodic health checks with respect to water quality, sediment quality and flora and fauna.

Following are some points to be considered for mangrove management & conservation plan:

 The project proponent should not undertake uprooting of mangroves apart from the desired corridor of 56 m during construction of the project. The disturbed mangrove area in the construction corridor of 56 m shall be replanted immediately after the completion of pipeline laying works.

 Restoration and Rehabilitation of degraded mangroves on suitable location by planting of suitable species immediately after commissioning of the pipeline and in consultation with forest department & Mangrove management cell.

 Enforcement of environmental protection laws at construction site.

 Full protection of the mangrove flora and fauna by banning the extraction of mangrove wood. The sand dunes and mangroves should not be disturbed in any way.

 Regular monitoring for any changes in mangrove area, floristic and fauna composition and physiographic.

 BPCL shall additionally carry out mangrove afforestation for 5 times of mangroves disturbed for pipelines laying activities.

Page 2 of 2

damde krishna (दमडे कृ ण कु मार)

From: damde krishna (दमडे कृ ण कु मार) Sent: Monday, April 8, 2019 3:56 PM To: biju Gopinath (बीजू गोपीनाथ) Cc: jain lr (जैन एल आर); saikumar ps (साईकु मार पी एस); dash hr (दाश एच आर) Subject: FW: [EXT] Email Alert From System Administrator of Online Submission and Monitoring of Forests Clearances Proposal(OSMFCP) portal

Dear Sir

We are happy to inform that our proposal for Diversion of forest land for Construction of under Ground Petroleum Products Pipelines and associated facilities from Mahul (Mumbai Suburban District) to Rasayani (Raigad District) in Maharashtra has been accepted today by Nodal Office ,Nagpur.

Now the physical copies are to be submitted to DCF, Alibag office for further processing. The same shall be submitted to their office on 11.04.2019 for their acceptance and scrutiny.

Regards

K.K.Damde +91 976 937 8989

From: [email protected] [mailto:[email protected]] Sent: Monday, April 8, 2019 3:25 PM To: damde krishna (दमड े कृ ण कु मार) Cc: [email protected]; [email protected] Subject: [EXT] Email Alert From System Administrator of Online Submission and Monitoring of Forests Clearances Proposal(OSMFCP) portal

A proposal seeking prior approval of Central Government under the Forest (Conservation) Act 1980, as per the details given below, has been examined by the Nodal Officer, Forest (conservation) Act, 1980, Government of Maharashtra and has been found to be complete in all respect. 1. Proposal No. : FP/MH/Pipeline/39455/2019 Proposal for Installation of Polypropylene (PP) unit at Rasayani and 2. Proposal Name : Interconnecting Pipelines from BPCL Mumbai Refinery (MR) to Rasayani 3. Category of the : Pipeline Proposal 4. Date of : 31/03/2019 Submission 5. Name of the Applicant with Contact Details

Name : KRISHNA Mobile No. : 9769378989 State : Maharashtra District : Mumbai City Pincode : 400015

1 6. Area Applied : 26.0494 (ha.)

Please provide duly signed hard copy of the above proposal along with all necessary enclosures to the office of the each concerned Divisional Forest Officer and the District Collector and upload a copy of the acknowledgement slip(s) (single pdf file) as per the format given below, obtained from each of the above authorities, on portal of this Ministry for further processing of the above proposal.

(System Administrator)

Acknowledgement Slip

This is to certify that hard copy of the proposal seeking prior approval of Central Government under the Forest (Conservation) Act 1980, as per details given below, along with all necessary enclosures has been received in the Office of the Maharashtra on 31/03/2019. 1. Proposal No. : FP/MH/Pipeline/39455/2019 Proposal for Installation of Polypropylene (PP) unit at Rasayani and 2. Proposal : Interconnecting Pipelines from BPCL Mumbai Refinery (MR) to Name Rasayani 3. Category of : Pipeline the Proposal 4. Date of : 31/03/2019 Submission 5. Name of the User Agency with Contact Details

Name : KRISHNA Mobile No. : 9769378989 State : Maharashtra District : Mumbai City Pincode : 400015

6. Area Applied : 26.0494 (ha.)

(System Administrator)

*** This is a system generated email, please do not reply. ***

2 Report Part 1 Page 1 of 8

FORM - A

Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area

PART - I (To be filled up by User Agency)

A. General Details

A-1. Project Details

(i). Proposal No. : FP/MH/Pipeline/39455/2019

(ii). Name of Project for which Forest Land is required : Proposal for Installation of Polypropylene (PP) unit at Rasayani and Interconnecting Pipelines from BPCL Mumbai Refinery (MR) to Rasayani

(iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of Forest land for construction of under ground petroleum pipe lines from Mahul (Mumbai suburban) to Rasayani (Raigad) in Maharashtra

(iv). State : Maharashtra

(v). Category of the Project : Pipeline

(vi). Shape of forest land proposed to be diverted : Linear

(vii). Estimated cost of the Project(Rupees in lacs) : 260500

(viii). Total Area of Forest Land proposed for diversion(in ha.): 26.0494

(ix). Non-Forest Land required for this project(in ha.): 103.9118

(x). Total period for which the forest land is proposed to be diverted(in years): 3

A-2. Details of User Agency

(i). Name : BHARAT PETROLEUM CORPORATION LIMITED MAHUL RASAYANI PIPELINE

(ii). Address1 : BHARAT PETROLEUM CORPORATION LIMITED

(iii). Address2 : A INSTALLATION SEWREE FORT ROAD SEWREE EAST MUMBAI 400015

(iv). State : Maharashtra

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fMH%2fPipelin... 3/31/2019 Report Part 1 Page 2 of 8

(v). District : Mumbai City

(vi). Pin : 400015

(vii). Landmark : SEWREE FORT ROAD

(viii). Email address : [email protected]

(ix). Landline Telephone No. : 22-24176222

(x). Fax No. : 22-

(xi). Mobile No. : 9769378989

(xii). Website (if any) : NIL

(xiii). Legal status of User Agency : Central PSU

A-3. Details of Person Making Application

(i). First Name: KRISHNA

(ii). Middle Name: KUMAR

(iii). Last Name: DAMDE

(iv). Gender: Male

(v). Designation: PROJECTLEADER

(vi). Address 1: BHARAT PETROLEUM CORPORATION LIMITED A INSTALLATION

(vii). Address 2: SEWREE FORT ROAD SEWREE EAST MUMBAI

(viii). State: Maharashtra

(ix). District: Mumbai City

(x). Tehsil: Mumbai

(xi). Pin: 400015

(xii). Landmark: SEWREE FORT ROAD

(xiii). Email Address: [email protected]

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fMH%2fPipelin... 3/31/2019 Report Part 1 Page 3 of 8

(xiv). Landline Telephone No.: 22-24176222

(xv). Fax No.: NIL

(xvi). Mobile No.: 9769378989

(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:

B. Details of land required for the Project

Details of proposal seeking prior approval of Central Government under the Act B-1. for diversion of forest land for the Project already submitted in the past

List of proposal submitted in Past

Area Date of Moef Proposed Area Date of Proposal Proposal In- S.no File for Diverted Final Status. No. Principle No. Diversion (Ha.) Approval Approval (Ha.) NIL

B-2. Details of forest land proposed to be diverted

B-2.1 Details of Divisions involved

Details of Divisions involved

Forest Land Non-Forest S.no Division Name (ha.) Land(ha.)

1. Mangrove 7.8012 63.2918 2. Alibag 18.2482 40.62

B-2.2 Details of Districts involved

District wise breakup

Forest Land Non-Forest S.no District Name (ha.) Land(ha.)

1. Mumbai (Suburban) 7.8012 63.2918 1. Raigad 18.2482 40.62

B-2.3 Village wise breakup

Villages wise breakup

Forest Land Non-Forest S.no Village (ha.) Land(ha.)

1 Mahul-Refinery 0 2.011 2 Mahul-MBPT 0 0.588 3 Mahul-TataNala area 0.2661 0

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fMH%2fPipelin... 3/31/2019 Report Part 1 Page 4 of 8

4 Mahul-Ramp Area 0.8035 0 5 Mahul-Ramp Area-638 part 1.4116 0 6 Mahul-638 part- shore 1 5.32 0 7 Mahul- shore 1- to shore 2 0 58.5984 8 LFP-2 Shore 2 to Mangrove Start 0 2.094 9 Creek 5.74 0 10 1.5008 0 11 Motikhadi 1.036 0 12 Ulwe 3.6018 1.5696 13 Sonkhar 1.9512 0.8208 14 Owle 0.4608 2.9736 15 Bambavi 0.9264 0.1032 16 Pargaon Dungi 0.3696 1.4064 17 Pargaon Inam 0 2.9448 18 Kopar 0 0.9456 19 Vadghar 0 3.9336 20 Karanjade 0 6.3192 21 Nandgaon 0 1.1136 22 Vadvali 0 2.7072 23 Turmale 0 2.6496 24 Sirdhon 0.9768 5.6952 25 Girvale 0 0.5592 26 Dahivali 0.3552 0 27 Somtane 0.0408 1.2144 28 Narpoli 0.7728 1.4376 29 Devloli Budruk 0.516 4.2264

B-2.4 Component wise breakup

Component wise breakup

Forest Land Non-Forest S.no Component (ha.) Land(ha.)

1 Mahul Refinery 0 2.011 2 Mahul MBPT 0 0.588 3 Mahul - Tatanala area 0.2661 0 4 Mahul Ramp Area 0.8035 0 5 Mahul Ramp Area - 638 part 1.4116 0 6 Mahul - 638 part to shore 1 5.32 0 7 Mahul Shore 1 to shore 2 0 58.5984 8 LFP -2 shore 2 to Mangrove start 0 2.0944 9 Creek 5.74 0 10 Wahal 1.5008 0 11 Moti Khadi 1.036 0 12 Ulwe - 1 2.877 0 13 Ulwe-2 0.7248 1.5696 14 Sonkhar-1 1.344 0 15 Sonkhar-2 0.6072 0.8208

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fMH%2fPipelin... 3/31/2019 Report Part 1 Page 5 of 8

16 Owle 0.4608 2.9736 17 Bambavi 0.9264 0.1032 18 Pargaon Dungi 0.3696 1.4064 19 Pargaon Inam 0 2.9448 20 Kopar 0 0.9456 21 Vadghar 0 3.9336 22 Karanjade 0 6.3192 23 Nandgaon 0 1.1136 24 Vadavali 0 2.7072 25 Turmale 0 2.6496 26 Sirdhon 0.9768 5.6952 27 Girvale 0 0.5592 28 Dahivali 0.3552 0 29 Somtane 0.0408 1.2144 30 Narpoli 0.7728 1.4376 31 Devloli Budruk 0.516 4.2264

C. Maps of forest land proposed to be diverted

Division 1. : Mangrove

(i). Area of forest land proposed to be diverted(in ha.) : 7.8012

(ii). : Linear

(b). No. of Segments : Four

Segment wise details

Segments Segment Area(in ha.) Kml File of Segments

1. 0.2661 View File 2. 0.8035 View File 3. 1.4116 View File 4. 5.32 View File (iii). Copy of Survey of India Toposheet indicating boundary of forest

land proposed to be diverted:

(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:

Division 2. : Alibag

(i). Area of forest land proposed to be diverted(in ha.) : 18.2482

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fMH%2fPipelin... 3/31/2019 Report Part 1 Page 6 of 8

(ii). : Linear

(b). No. of Segments : Twelve

Segment wise details

Segments Segment Area(in ha.) Kml File of Segments

1. 12.4978 View File 2. 0.6072 View File 3. 0.5304 View File 4. 0.1944 View File 5. 0.9264 View File 6. 0.3696 View File 7. 0.144 View File 8. 0.0408 View File 9. 0.1104 View File 10. 0.4608 View File 11. 1.188 View File 12. 1.1784 View File (iii). Copy of Survey of India Toposheet indicating boundary of forest

land proposed to be diverted:

(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:

Justification for locating the Project in forest land and details of D. alternatives examined:

(i). Copy of note containing justification for locating the Project in forest land:

(ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes

(a). Copy of map indicating location of alternative examined:

E. Employment likely to be generated

(i). Whether the Project is likely to generate employment ?: Yes

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fMH%2fPipelin... 3/31/2019 Report Part 1 Page 7 of 8

(ii). Permanent/Regular Employment(Number of persons): 10

(iii). Temporary Employment(Number of person-days): 247500

F. Displacement of People due to the Project, if any

(i). Whether Project involves displacement?: No

G. Details of Cost-Benefit analysis for the Project

(i). Whether the Project requires Cost-Benefit analysis?: No

H. Status of Environmental Clearance

(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes

(a). Status of the Environmental Clearance to the Project: EC under process

(ii). Environmental Clearance File No.: IA-J-11011/168/2018-IA-II(I)

I. Status of Wildelife Clearance

(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : Yes

(a). Whether Project or a part thereof is located within a Protected Area ? : No

(ii). Status of approval of the Standing Committee of National Board for the Wildlife (NBWL) to the Project : Application yet to be submitted

J. Applicability of special provisions governing Scheduled Areas

(i).Whether the Project or a part thereof is located in a Scheduled Area? : No

Status of settlement of rights under the Forest Rights Act,2006 on the K. forest land proposed to be diverted

(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No

L. Details of land identified for Compensatory Afforestation

(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fMH%2fPipelin... 3/31/2019 Report Part 1 Page 8 of 8

(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable

(iii) . Reason for not providing Non-Forest Land: Not Applicable

Additional information Details

Documents

S.No Documents Remarks

1 FORM -A

2 CERTIFICATE FOR COMPENSATORY AFFORESTATION 3 CERTIFICATE FOR MINIMUM DEMAND OF FOREST AREA 4 UNDERTAKING FOR PAYMENT OF NPV 5 UNDERTAKING FOR ST & OTFD NOC

Print page

http://forestsclearance.nic.in/Admin/Useragencyreport.aspx?pid=FP%2fMH%2fPipelin... 3/31/2019