Railway Project

1.0 Month of Review : December’2012

2.0 Salient Feature :

2.1 Name of the project : Gauge Conversion of Lunding- - Jiribam, Badarpur to Baraigram & Baraigram to Kumarghat (377.56 Km) & MM for GC of Baraigram-Dullabhchera (29.4 Km), -Maishasan (10.3 Km) and Karimganj by pass line (3 Km) (National project)

2.2 Implementing Agency : N. F. Railway, Construction

2.3 Length of the Railway line : 420.26 Km

2.4 Estimated Cost : `4255.37 Crs. (Value revised as per material modification) 2.5 Date of Commencement : 1996-97

2.6 Schedule date of completion : Dec’2014

2.7 Brief description of project : Gauge Conversion of Lunding-Silchar - Jiribam, Badarpur to Baraigram & Baraigram to Kumarghat & MM for GC of Baraigram-Dullabhchera, Karimganj-Maishasan and Karimganj by pass line. This involves earthwork 722.32 lac cum, major bridges (substructure 102 Nos., superstructure 138 Nos.) and minor bridges 729 Nos. Tunneling 10745 RM & Cut & Cover 2022 m.

2 Measurable Milestone for Gauge Conversion of LundingLunding----SilcharSilchar --- Jiribam, Badarpur to Baraigram & Baraigram to KumarKumarghatghat (377.56 Km) & MM for GC of BaraigramBaraigram----DullabhcheraDullabhchera (29.4 Km), KarimganjKarimganj----MaishasanMaishasan (10.3 Km) and Karimganj by pass line (3 Km)Km) (National project) Sl. Activities/Sub section Duration Schedule Schedule % progress Reasons Revised Bottleneck/Remarks No (Days) Date of Date of Target Achieve - for delay date of (if any) . start finish up to ment up to completion Dec’2012 Dec’2012 1 Date of sanction of project 1996 -97 Dec’201 4 2 Detailed project report (FLS) Completed Section wise 3 Regulatory clearance (if any) 3.6 hect. of forest land in of , 3.72 hect. of land in Karimganj district of Assam state and 0.2969 Acres of land in Dharmanagar district of is yet to be received. 4 Land acquisition (if involved) Out of 606.825 hect. 571.634 hect. land acquired. Section wise However, there is problem in doing work at acquired locations as per Annexure-I. 5 Construction i. Earthwork 30.11.13 699.54 681.385 Law & progress (Lac cum) (96.85%) (94.33%) Order (section wise) ii . Major Bridges: Sub - 31.10.13 95 87 problem & str.( No.) (93.14%) (92.55%) working Major Bridges: Super 30.11.13 120 100 condition of Less due to rain, welding system for steel girders Structure: (No.) (87.14%) (72.46%) Road & & very bad road & bridge condition affecting Bridge on transportation of fabricated component. iii. Track linking (KM) 25.12.13 308.02 214.397 NH-54-E Less due to d ifficulty in movement of Rail panels . (73.29%) (51.02%) from Dual gauge sleepers and ballast due to shortage Lanka- of MG BFRs, hoppers and Power. iv. Tunnelin g (M) 30.11.13 9447.48 7965.20 Lumding- Due to late finalization of Risk & Cost tender for (87.927%) (74.13%) Silchar. Tunnel No10 & worsening condition of Roads & Bridge in N. C. hills (now Dimahasao, Distt. of Assam), problems in transportation of materials due to rain. Frequent bandhs and uncertain security scenario have a detrimental effect on the progress of work. v. Commissioning 31.12.13 - - 3.0 Financial Monitoring 3.1 Sanctioned Cost of the project : `4255.37 Crs. (Revised) `1689.12 Crs. (original) 3.2 Cash-flow projections up to the month : `3291.16 Crs. (up to Dec’12) 3.3 Actual Expenditure up to the month : `3291.16 Crs. (up to Dec’12) 3.4 Variations (if any) : NIL 3.5 Reasons for 3.4 above : No variation. 3.6 Revised cost projects. : Revised estimate amount `4255.37 Crs. 3 Annexure-I

Reasons for delay in execution of work: -

(A) Technical reasons:

(i) The main reason for the delay in the project is the slow pace of tunneling specially in tunnel nos 7 & tunnel 10. The tunneling operation is slow due to geological surprises such as squeezing nature of soil strata, loose strata resulting in cavities & chimney formation as well as presence of methane in the tunnels making welding & gas cutting work hazardous. (ii) Road conditions are generally poor in the NC Hills due to which transportation of construction materials is time consuming and costly.

(B) Land acquisition problems :

1. 3.6 hectare of forest land has to be deserved in the NC Hills District. Matter is under correspondence since 2008 with the Forest authorities but final approval is yet to be achieved. Superstructure of bridge no.127 and ROB no129 are still to be constructed.

2. (a) Land acquisition of 2.53 hectares at Bhanga, and 0.29 hectares between Dharmanagar & Nadiapur under Dharmanagar district of Tripura state are required to be expedited for handing over to Railway.

(b) For Karimganj-Moishasan under Karimganj Dist. of Assam 8.3 hector land is required to be handed over. For Baraigram-Dullabhchera – under Karimganj Dist. of Assam, Joint verification for land acquisition to be expedited.

(C) (i) Law and order situation in N. C. Hills is poor with kidnapping of contractors engineers & workers occurring at frequent intervals and non availability of labour and supervisors in N.C. hills areas.

(ii) Frequent bandhs and resultant work stoppages in Dima Hasao district of Assam affect progress of work. About 7 working days were lost in September 2012 due to Bandhs and curfew in Haflong area. (D) Allotment of funds to this project was initially very less due to which long lead items like tunnels could not be taken up. Fund allotment picked up only after 2004 when this project was declared as a National Project. In 2006-09 the project was hit by severe insurgency in the NC Hills in which a number of railway personnel were also killed.

4

Railway Project

1.0 Month of Review : December’2012

2.0 Salient Features :

2.1 Name of Project : Bogibeel bridge with linking lines between & North bank (73 Km) (National Project ).

2.2 Implementing Agency : N. F. Railway (Construction Organisation)

2.3 Length of the Railway line : 73 Km.

2.4 Estimated Cost : `3378.82 Crs. - `3087.44 Crs (Work to be executed by Railway)

- `291.385 Crs. (Work to be executed by PWD/NH, Assam)

`4864.0 Crs. (Estimate under Revision)

2.5 Date of Commencement : 21 st April 2002

2.6 Schedule Date of Completion : Decmeber’2015

2.7 Brief description of Project : Rail-cum-Road bridge across river Brahmaputra at Bogibeel near Dibrugarh along with linking lines between Dibrugarh and North Bank line.

2.8 Scope of work : i. Bogibeel rail-cum-road main bridge – Length 4.940 Km (2x32.75m+39 x125m) ii. Raising & strengthening of north & south dykes for 9 Km on upstream & 7 km on down stream. iii. Rail link on south & north banks – 74 Km iv. NH road link 29.455 Km on north & south banks including 4.941 Km on Main Bridge. 5

Measurable mil estones for Bogibeel Bridge with linking lines between Dibrugarh & North Bank line Sl. Activities/Sub section Duration Schedule Schedule Progress Reasons Revised Bottleneck/ No. (Days) Date of Date Targeted Achieve - for delay date of Remarks start of finish up to ment up to comple- Dec’2012 Dec’2012 tion 1 Date of sanction of project 1997 -98 Dec’15 2 Detailed project report Completed Completed (FLS) Section-wise 3 Regulatory clearance CCEA Co mpleted (If any) clearance received Sept’97 4 Land acquisition (If involved) 505.94 505.94 Completed Section-wise (Hect ) (100%) (100%) 5 Construction progress (Section-wise) A. Earth Work (Lakh Cum) i) Embankment Feb’03 June’11 179.42 179.42 June’11 Completed. (100%) (100%) ii) Dykes Mar’04 June’10 58.37 57.50 Dec ’11 Strengthening of north & south dykes completed except 3 Km raising in South Dyke. (100%) (98.51%) iii) Guide Bunds Nov’08 June’11 50.73 50.73 June’11 Comp leted . (100%) (100%) B. Formation (Km) Feb’03 June’11 70.60 70.60 Mar’12 Completed . (100%) (100%) D. Bridges a) Minor Bridges (No.) Feb’03 Mar’11 104 104 Mar’11 Completed. (100%) (100%) b) Major Bridges(No) - Sub-Structure Nov’03 Dec’10 17 17 Mar’11 Completed. (100%) (100%) - Super Structure Nov’03 Dec ’10 17 17 Mar’11 Completed. (100%) (100%) E. Track Linking (Km) Jan’06 Dec ’1 3 75.20 45.40 Chalkhowa - Moranhat (44 Km) section of Bogibeel project commissioned on - South Bank (87.58%) (49.88%) Dec’13 8.12.2009 and the section has been handed over to open line on 29.01.2010. - North Bank Apr’12 Dec ’13 0.0 0.0 Dec’13 Track linking will be done to match completion of main bridge F. Boulder Supply Apr’02 Mar’11 22. 35 21. 381 Dec’13 Work in Progress at North Bank., South Bank completed. (1000 Cum) (100%) (95.66%) G. Main bridge a) Sub -structure (Nos.) i. Well Foundation(no) Oct’08 Sept’11 40 32 Mar’13 32 nos. of well fou ndations completed and balance are under progress. (95.24%) (76.19%) ii. Pier/Abutment(no) Oct’09 June’12 22.50 20 June ’13 Work in progress. (53.57%) (47.62%) b) Super structure (no. of span) July’10 Dec’13 0.0 0.0 Dec’1 5 Tender for Superstructure accepted in favour of M/s. HCC on 23.11.2011. Fabrication of girders will be started in Nov’2012. 6

3. Financial monitoring :

3.1 Sanctioned Cost of the Project : Pt. I detailed estimate - `371.14 Crs. (Sanctioned) Pt. II detailed estimate - `578.08 Crs. (Sanctioned) Pt. III detailed estimate - `516.35 Crs. (Sanctioned) Pt. IV detailed estimate - `581.80 Crs. (Sanctioned) Pt-V detailed estimate - `182.64 Crs . (Sanctioned) Total = `3378.82 Crs.

3.2 Cash – flow projections up to the month : `2590.05 Crs. (up to Dec’2012)

3.3 Actual Expenditure up to the Month : a) Expenditure up to Mar’2012 `2380.64 Crs. b) Expenditure up to Dec’2012 ` 209.41 Crs . Total = `2590.05 Crs.

3.4 Variations (if any ) : NIL

3.5 Reasons for 3.4 above : No variation.

3.6 Revised Cost Projects : Revised estimate for the project is under preparation and will be approximately `4500.00 Crores. 7

Railway Project

1.0 Month of Review : December’2012

2.0 Salient Feature :

2.1 Name of the project : New BG Railway Line from Harmuti to Naharlagun (21.76 Km).

2.2 Implementing Agency : N. F. Railway, Construction Organisation.

2.3 Length of the Railway line : 21.76 Km 2.4 Estimated Cost : `156.00 Crs. as on February’97. 2.5 Date of Commencement : Feb’1997 2.6 Schedule date of completion : Harmuti-Naharlagun : March’2013

Govt. of has decided to terminate the Railway line of Harmuti to Itanagar at Naharlagun station communicated vide letter No.TPT/RL/16/2009/ 514 dt.17.3.10.

2.7 Brief description of project : New BG Railway Line Project is taking off from Harmuti station of Rangiya – Murkongselek section under going Gauge Conversion from MG to BG and connecting capital of Arunachal Pradesh i.e. Itanagar. The Project was sanctioned during year 1996-97. Part Detailed estimate from Harmuti to Naharlagun was sanctioned by Rly. Board on 31.01.2008 at a cost of `160.48 Crs. Detailed estimate for balance section i.e. Naharlagun to Itanagar at a cost of `371.33 Crs. has been sent to Railway Board on 7.7.2009 for sanction. Revised estimate of `406.40 Crs. for Harmuti-Naharlagun has been sanctioned by Rly. Board on 04.09.2012. Progress of work adversely affected due to paucity of fund.

Measurable Milestone (Specific activities with respect to the project in question can be inserted if required). 8 Measurable Milestone for New BG Railway Line from Harmutiarmuti----NaharlagunNaharlagun (33.00 Km) Sl. Activities/Sub section Duration Schedule Schedule % progress Reasons for delay Revised Bottleneck/Remarks No (Days) Date of start Date of Target upto Achievement date of (if any) . finish Dec’2012 upto completion Dec’ 2012 1 Date of sanction of project Feb’97 2 Detailed project report (FLS) Completed. Section wise 3 Regulatory clearance (if any) 4 Land acquisition (if involve ) Section wise (i) Harmuti -Naharlagun Section Oct’2008 Oct’2009 138.70 Hect. 138. 70 Hect. Delay in land Mar’12 (100%) (100.00%) acquisition process by state Govt. of Assam. (ii) Naharlagun -Itanagar Detailed Estimate Section submitted t o Rly. Board. 5 Construction Progress (i) Harmuti -Naharlagun Section i. Earthwork (lakh Oct’2008 March’12 40 (100 %) 39. 95 Land in Assam Land in Assam covering cum) (99. 88 %) covering 5.25 Km 5.25 Km handed over in ii. Major Bridges (nos.) Oct’2008 March’12 length handed over May-June’11. Sub -structure 8 5 in May-June’11. (100 %) (62.50 %) Land in Arunachal Super structure 8(100%) 5(62.50 %) Pradesh handed over for execution iii. Minor Bridges(no s.) Oct’2008 March’12 46 (100 %) 46 of work. (100 %) iv Track linking March’12 21.76 20 (91.91 %) (100%) v. Commissioning March’13 - - Dec’13 Can be com plet ed along with GC of Rangapara North-Harmuti section in June ’13 . (ii) Naharlagun -Itanagar Sect ion

i. Earthwork Detailed Estimate ii. Bridges (nos.) submitted to Rly. Board. iii. Track linking iv. Commissioning 9

3.0 Financial Monitoring 3.1 Sanctioned Cost of the project : ` 160.48 Crs. (Harmuti-Naharlagun section) : ` 406.40 Crs. sanctioned in Revised Estimate. :`371.33 Crs. (Naharlagun-Itanagar section, detailed estimate sent to Rly. Bd. on 7.7.09 for sanction)

3.2 Cash-flow projections up to the month : ` 332.34 Crs. (up to Dec’2012) 3.3 Actual Expenditure up to the month : ` 280.75 Crs. (up to Dec’2012) 3.4 Variations (if any) : ` 51.59 Crs. 3.5 Reasons for 3.4 above : Because of non-allotment additional fund against budget allotment.

3.6 Revised cost projects. : Harmuti-Naharlagun section – ` 406.40 Crs. Naharlagun-Itanagar section – ` 371.33 Crs.

10

Railway Project

1.0 Month of Review : December’2012

2.0 Salient Feature

2.1 Name of the project : New BG Railway Line from Jiribam to Imphal (Tupul) (84 Km).

2.2 Implementing Agency : N. F. Railway, Construction Organisation.

2.3 Length of the Railway line : 98.0 Km (now reduced to 84 Kms.)

2.4 Estimated Cost : `3056.85 Crs. anticipated cost.

`4444.00 Crs. (for Jiribam-Tupul-Imphal as per Pink Book)

2.5 Date of Commencement : April’2003.

2.6 Schedule date of completion : (i) Jiribam-Tupul = March’2015 : (ii) Tupul-Imphal = March’2017

2.7 Brief description of project : For over all development of the remote area in Northeast and to provide reliable through Rail transportation facility to the capital of state.

Measurable Milestone (Specific activities with respect to the project in question can be inserted if required).

11 Measurable Milestone for Jiribam ––– Tupul ((84848484 Km)

Sl. Activities/Sub section Duration Schedule Schedule % progress Reasons for Revised date Bottl eneck/ No (Days) Date of Date of Target up to Achieve - delay of completion Remarks . start finish Dec’2012 ment up to (if any) Dec’2012 1 Date of sanction of project 4077 April’03 Mar ’14 26.7 Insurgency March’17 Long Tunnels, Insurgency. 2 Detailed project report (FLS) 1795 May’05 Marc h’10 100 Km 100 Km Completed. Section wise (Km) (100%) (100%) 3 Regulatory clearance (if any) 4 Land acquisition (if involve) 1460 April’06 March’10 1202.00 1089.022 Delay by State Sep’13 Delay by State Govt. Section wise(Hect.) (93.71%) (84.90%) Govt. Pt.IV Detailed Estimate submitted to Board on 10.12.09, sanctioned on 13.12.10. 5 Construction i. Earthwork 1733 April’07 March’11 358.35 344.195 Unsafe sites Mar’1 4 ●Insurgency. Progress (lac cum) (69.66%) (66.91%) due to ●Frequent Bandhs. (section wise) insurgency ●Prolonged economic blockades. ●No movement of heavy machinery and material through both highways (i.e. NH-53 & NH-39) between April – Nov’10 and Aug- Nov’11 due to their bad condition and economic blockage. ●About 13 months lost due to series of Economic Blockades/counter blockades/ Transporters’ strike etc. ●Pt. IV detailed estimate submitted on 10.12.09, sanctioned by Rly. Bd. on 13.12.10. ●UNC ban on Railway works for 2 months w.e.f. 16.12.2011 to 15.2.2012 with the result contractors’ workers refused to go to site. ●Pt.V detailed estimate for Tupul-Imphal (26.925 Km) for an amount of `1420.83 Crs. has been submitted to Rly. Board for sanction on 23.9.2011. ii . Major Bridges(nos) 912 Oct’09 March’12 - - -do - Jan’15 -do - ii i. Minor Bridges(nos.) 1735 April’07 March’11 46.31 30 -do - Sep’14 -do - (43.28%) (28.00%) iv Track linking 1095 Jan’11 Dec’13 - - - Feb’1 5 v. Commissioning March’14 - - - Mar’1 5 3.0 Financial Monitoring 3.1 Sanctioned Cost of the project : `4444.00 Crs. (Revised for Jiribam-Tupul-Imphal, 111 Kms); `727.53 Crs. (Original) for Jiribam-Tupul (84.00 Km) 3.2 Cash-flow projections up to the month : `1079.17 Crs. (up to Dec’2012) 3.3 Actual Expenditure up to the month : `1079.17 Crs. (up to Dec’2012) 3.4 Variations (if any) : NIL 3.5 Reasons for 3.4 above : No variation. 3.6 Revised cost projects. : `4444.00 Crs. 12

Railway Project

1.0 Month of Review : December’2012

2.0 Salient Feature

2.1 Name of the project : Sivok-Rangpo New Line (44.39 Km).

2.2 Implementing Agency : N. F. Railway, Construction Organisation.

2.3 Length of the Railway line : 44.39 Km (As per FLS)

2.4 Estimated Cost : `1339.48 Crs. anticipated cost (Supplementary Budget 08-09)

2.5 Date of Commencement : April, 2009

2.6 Schedule date of completion : March’2017

2.7 Brief description of project :

Measurable Milestone (Specific activities with respect to the project in question can be inserted if required). 13

Measurable Milestone for Sivok ––– Rangpo (44.39 Km)

Sl. Activities/Sub section Duration Schedule Schedule % progress Reasons Revised Bottleneck/Remarks No (Days) Date of start Date of Target Achievement for delay date of (if any) finish upto upto completion Dec’2012 Dec’2012 1 Date of sanction of project Feb, 2009 N.A. 2 Detailed project rep ort (FLS) After FLS Project is being executed by the M/s IRCON as per Rly Bd’s L/No.2006/ W1/ Section wise (Km) detail NF/36()/Pt. dated 15.9.09. CA signed with IRCON on 07.05.2010. estimate submitted to Board. 3 Regulatory clearance (if any) Requested for first 5 Km, 5-22 Km Forest clearance. 4 Land acquisition (if involve) 0.00 0.00 Section wise(Hect.) 5 Construction i. Earthwork (lac cum) 0.00 0.00 Detailed estimate for `3380.58 Crs. has been subm itted to Railway Board for Progress ii. Major Bridges nos.) 0.00 0.00 sanction on 30.12.2009. Board’s latest observation complied on 03.08.2012. (section wise) iii. Minor Bridges(nos.) 0.00 0.00 Project has been entrusted to M/s. IRCON for execution and MOU has been iv. Tunnels signed with IRCON on 7.5.10. Forest clearance from Km 0.00 to Km 5.50 falling in Mahananda Wild Life sanctuary have been cleared by State Govt. and submitted to MOEF/New on 30.3.2012. Approval for survey and investigation from Km 5 to Km 41.50 has been obtained from Forest Deptt. Topographical, Geophysical and photogrammetric survey work has been completed. Land acquisition proposal for 0.957 Acres and 67.285 Acres has been submitted to DM/Darjeeling and DC/East Sikkim, Gangtok respectively. Land acquisition, revised consolidated proposal from Km 5.78 to Km 41.548 has been submitted to forest Deptt .of West and from Km 41.548 to Km 44.9 to forest deptt of Sikkim. IRCON has submitted the final alignment report for alignment design prepared by M/S Geo-data for approval. IRCON were suggested to explore the possibility of alternate alignment from Sivok to Km 9 which is passing through East bank of River Teesta avoiding Mahananda Wild Life Sanctuary. IRCON in consultation with M/s Geo-data examined alternate alignment proposal and submitted the comments. Alternate alignment on East side of Teesta river via Kalimpong is being considered as better option Bore whole drilling, soil exploration and soil testing for both portal of Tunnel No.1 has been completed. Seismic refraction survey and 2-D Resistivity survey has been completed. v. Track linking vi. Commissioning 14

3.0 Financial Monitoring

3.1 Sanctioned Cost of the project : Not yet sanctioned. (Detailed estimate submitted to Rly. Board on 30.12.09)

3.2 Cash-flow projections up to the month : `57.12 Crs. (up to Dec’2012) 3.3 Actual Expenditure up to the month : `57.12 Crs. (up to Dec’2012) 3.4 Variations (if any) : NIL 3.5 Reasons for 3.4 above : NIL 3.6 Revised cost projects. : N.A.

15

Railway Project

1.0 Month of Review : December’2012

2.0 Salient Feature : Group ‘E’ Route.

2.1 Name of the project : Kumarghat – New Line (109 Km)

2.2 Implementing Agency : N. F. Railway, Construction Organisation. 2.3 Length of the Railway line : 109 Km

2.4 Estimated Cost : `984.97 Crs. (sanctioned); ` 1150.00 Crs. (anticipated)

2.5 Date of Commencement : July’1996

2.6 Schedule date of completion : December’2014 (Revised)

2.7 Brief description of project : To connect state capital of Tripura with rail network and to develop backward region of remote state of Tripura in Northeast. Project completed and MG services commissioned w.e.f. 05.10.2008. Commissioning for BG train services will be done on completion of Lumding-Silchar Gauge Conversion project.

Measurable Milestone (Specific activities with respect to the project in question can be inserted if required).

► 5 ROBs in lieu of L-xing to be completed. ► Revised estimate is under process. ► Total ` 150.00 Crs. fund to be made available for balance works related to BG conversion.

16 Measurable Milestone for KumarghatKumarghat----AgartalaAgartala (109 Km)

Sl. Activities/Sub section Duration Schedule Schedule % progress Reasons Revised date of Bottleneck/Rem -arks No (Days) Date of Date of Target up Achieve - for delay completion (if any) . start finish to ment up to Dec’2012 Dec’2012 1 Date of sanction of project Completed. 2 Detailed project report (FLS) Completed. Section wise (Km) 3 Regulatory clearance (if any) Completed. 4 Land acquisition (if involve) Completed. Section wise(Hect.) 5 Construction i. Earthwork Completed. Progress (lac cum) (section ii. Major Bridges Completed. wise) (nos.) iii. Minor Completed. Bridges(nos.) iv Track linking Completed. v. Commissioning Completed. Commissioning for BG train services will be done on completion of Lumding-Silchar Gauge Conversion project. 3.0 Financial Monitoring 3.1 Sanctioned Cost of the project : `984.98 Crs. Anticipated : ` 1150.00 Crs.

3.2 Cash-flow projections up to the month : `940.95 Crs. (up to Dec’2012)

3.3 Actual Expenditure up to the month : `940.95 Crs. (up to Dec’2012) 3.4 Variations (if any) : NIL 3.5 Reasons for 3.4 above : No variation. 3.6 Revised cost projections. : `1150.00 Crs. 17

Railway Project

1.0 Month of Review : December’2012

2.0 Salient Feature : Group ‘E’ Route.

2.1 Name of the project : Agartala-Sabroom New Railway Line (111.81 Km).

2.2 Implementing Agency : N. F. Railway, Construction Organisation.

2.3 Length of the Railway line : 111.81 Km

2.4 Estimated Cost : `1141.75 Crs. Anticipated ` 1600.00 Crs.

2.5 Date of Commencement : Oct’2008

2.6 Schedule date of completion : Dec’2015

2.7 Brief description of project : Project will provide rail network up to the southernmost town of Sabroom which is at the border with and situated 70 Km north of Chittagong Port. The proposed rail line is of strategic importance as well as for development of backward area of the state of Tripura.

Measurable Milestone (Specific activities with respect to the project in question can be inserted if required).

18 Measurable Milestone for Agartala ––– Sabroom (11(111.1.1.1.81818181 Km) Sl. Activities/Sub section Duration Schedule Schedule % progress Reasons for delay Revised date Bottleneck/Remarks No (Days) Date of Date of Target up Achieve - of completion (if any) . start finish to ment up to Dec’2012 Dec’2012 1 Date of sanction of project April’08 March’14 2 Detailed project report (FLS) Sept’08 March’10 110 110 Completed Section wise (Km) (100 %) (100%) 3 Regulatory clearance (if a ny) Not required. 4 Land acquisition (if involve d) March’09 March’11 617.61 494.26 Obstruction by Dec ’1 3 ●Frequent interruptions by villagers Section wise(Hect.) (78.13%) (62.52%) villagers & time regarding alignment near Bishalgarh bound taken by (Km10-16) & Bisramganj (Km 23-28). ● State Forest deptt Delay in land acquisition by State Govt. & MOEF. between Km 10-16 near Bishalgarh. ●Delay in getting Forest Clearance from MOEF. 5 Construction i. Earthwork (lac cum) July’09 - March’13 96.52 49.24 Delay by State Apr’15 ●Delay in land acquisition & Paucity of Progress (55.31%) (28.22%) Govt. in handing fund. (section wise) over land ii. Major Bridges (nos.) 13 7 - Sub -str. Jan’10 March’13 (48.15 %) (25.93%) - do - Apr’15 - do - - Super -str. 9 5 (33.33%) (18.52%) iii. Minor Bridges(nos.) July’09 March’13 118 50 (48.49 %) (20.58 %) Apr’15 -do - iv Track linking Jan’12 Dec’13 - - Oct’15 v. Commissioning March’14 - - Dec’15 The section from Km 0 -44.11 i.e. Agartala to Udaipur was planned for completion by 31.3.2012. But land between Km 10-16 has not been handed over to Railway physically by March’2012.

3.0 Financial Monitoring

3.1 Sanctioned Cost of the project : `1141.75 Crs. Anticipated : `1600.00 Crs 3.2 Cash-flow projections up to the month : `449.26 Crs. (up to Dec’2012) 3.3 Actual Expenditure up to the month : `449.26 Crs. (up to Dec’2012) 3.4 Variations (if any) : NIL 3.5 Reasons for 3.4 above : No variation. 3.6 Revised cost projections. : ` 1600.00 Crs