Details of Project

Asansol Development Authority (Govt. of West ) allotted the land to SUGAM PARK (AOP) to develop the project as a private partner of the Government through competitive bidding. The project comprised of residential and commercial development. Land Area as per document is 30.094 acres (121785.152 sqm) and Land Area as per physical measurement is 117965.00 sqm. The project is being constructed at Mouza – Shitla, J.L. No. – 21, R.S. Plot No. - 635(P), 639 – 642, 1329 – 1335, 1336(P), 1341(P), 1342(P), 1343, 1344, 1346(P), 1348(P), 1342 / 1561, 1348 / 1563, 638 / 1496 (P), 640 / 1497 and Mouza - Dakshin Dhadka, J.L. No. – 27, R.S. Plot No. - 265(P), 266(P), 267, 268(P), 310, 318(P), 319, 320(P), 323(P), 324(P), 325(P), 326 – 331, 332(P), 333 - 354, 355(P), 356 – 366, 368, 373(P), 374, 375(P), 382, 383, 384(P), 327 / 1082, 335 / 1083, 382 / 1087, 268 / 1080(P), 355 / 1308. Police Station – Asansol (North). Under - Asansol Municipal Corporation, Dist. – Paschim Burdwan,

The project site is a flat land. Land Area (as per deed) = 117965.00 sqm. There is construction of Residential Building with 111558.46 sqm built up area.

Proposed Project Area 117965.00 sqm Total Built Up Area 111558.46 sqm Ground Coverage 15906.85 sqm (13.48%) Exclusive Tree Plantation Area 23657.03 sqm (20.05%) Total Green Area 28475.56 sqm (24.14%) Total Paved Area 21902.06 sqm (18.57%) Total Residential Blocks – 36 nos. Building LIG-1 to LIG-10 – G+3 storied (10 nos.), Building MIG – B1, C1, C2, C6, C7 and C8 – G+7 storied (6 nos.) No. of Blocks &Stories Building MIG – C3, C5, C9, C10, C11 – G+8 storied (5 nos.) Building HIG – A1 to A15 – G+7 storied (14 nos.) Building HIG – A2– G+8 storied (1 no.) Club – 1 no. – G+1 Developed Plots – 136 nos. No. of Dwelling units Flats – 1190 nos., Plotted developments – 136 nos. Source of Water AMC supply Total Quantum of Water required 1290 KLD Quantity of Wastewater Generation 861 KLD Quantity of treated wastewater recycled 253 KLD (Landscaping : 214 KLD & Car Washing : 39 KLD) Quantity of treated wastewater 608 KLD Discharge Quantum of Fresh Water required 1037 KLD Quantity of Solid Waste Generation 4295 kg/day Constructional Phase Water Demand 82 KLD (Construction work – 12 KLD, Workers – 70 KLD) Total Population During Construction 905 persons

Total Population During Operation 7750 persons (permanent – 6630 and temporary – 1120) Electricity Load 5375 KVA (4300 KW) Electricity Supplied By WBSEDCL D. G. Sets 6 nos. 180 KVA each (for residential part) Fuel (diesel) Required for D. G. Sets 173 litre/hr. Stack Height for D. G. Sets For each 180 KVA is 2.7 meter above DG roof level. 970 nos. (covered – 600 and open – 370) car parking; 314 Parking provided nos. of motorbike parking No. of trees Planted More than 1750 Nos. Project Latitude and Longitude 23° 42' 8" N, 86° 58' 39" E

Water Supply, Wastewater Generation, Recycling and Discharge

Total water demand is 1290 KLD. Out of that fresh water demand is 1037 KLD and rest (255 KLD) will met from treated wastewater recycling (Landscaping: 214 KLD & Car Washing: 39 KLD)

The excess treated wastewater that is discharged to the covered drain/conduit inside project site – 608 KLD.

Flat/ Plot Occu. Rate Total popu. Lpcd Total litre/day kLD Nos. Residential 1190 5 5950 150 892500 893

Plotted Development 136 5 680 150 102000 102

Club 200 45 9000 9 Service persons 320 45 14400 14

Floating Population 600 15 9000 9 Sub Total 1 1027 Landscaping 214 Car washing 39 Losses 10 Sub Total 2 263 TOTAL WATER REQUIREMENT 1290 Total Wastewater Generation 861 Total Wastewater discharge 608 Total Recycling 253 Landscaping 214 Car washing 39 Fresh Water Requirement 1037 OCCUPANCY RATE AS PER NBC 2005, PART 9, PAGE 20, PARA 4.3.1.1

Waste required for the project is being supplied by Asansol Municipal Corporation (AMC)

The wastewater is collected through a well designed sewer network leading to STP. A 500 KLD capacity STP based on Anaerobic Baffled Reactor (ABR) Technology followed by tertiary system has already been constructed and another STP will be constructed for the rest.

WATER BALANCE DIAGRAM

FRESH INPUT 1037 KLD

Residential 893 Plotted Club Service Floating Losses KLD Development 9 KLD Persons Population 10 KLD 102 KLD 14 KLD 9 KLD

WASTEWATER

GENERATED

861 KLD

TREATED CAR WASTEWATER LANDSCAPING WASHING GENERATED 214 KLD 39 KLD 861 KLD

TREATED WASTEWATER DISCHARGE 608 KLD

Solid Waste Generation and Its Management

MSW/Garbage will be generated during operational phase of 4295 kg/day. All MSW generated from the project will be disposed of by Asansol Municipal Corporation (AMC) as per MSW (M&H) Rules, 2000.

Rate Total Person kg/day kg/day Residential 5950 0.60 3570.00 Plotted Development 680 0.60 408.00 Club 200 0.15 30.00 Service persons 320 0.10 32.00 Floating Population 600 0.10 60.00 Street Sweeping 7750 0.025 193.75 GRAND TOTAL 4293.8 Say 4295

Storm Water Management

The surrounding area is predominantly residential and commercial area. The project area is 117965.00 sqm. By applying rational formula the peak rate of storm runoff considering 12 mm/hr rainfall is given below.

The project area = 117965.00 sqm = 11.7 ha. By applying rational method, the peak rate of run- off = 10 x 0.60 x 12 x 11.7 cum/hr. = 842.4 cum/hr. = 0.234 cum/sec. Velocity through pipe is 1.0 m/sec (non-scouring and non-silting). The required diameter of pipe is 550mm.

The storm drains of the complex are/will be collecting and conveying the rainwater into the adjacent Corporation drain. The internal drainage system will be designed considering the invert level of the Corporation drain (outfall) in-front of the project site to avoid any flooding or water logging in the site.

Rain Water Harvesting

The total roof area is about 15906.85. The SEAC guideline regarding rain water harvesting is as follows -

Sl. Category of Building Minimum percentage of rain water which No. should harvested by Surface Storage Sub-surface Recharge

1 10 to 15 storied Building & Above 40% 60% 2 6 to 10 storied Building 35% 45% 3 3 to 5 storied Building 25% 15% (recharge or additional storage) 4 Less than three storied Building 10% 10%

Note While suggesting the guidelines, RWH potential in 1000 sqm Roof Area was considered to be 7, 68,000 liters annually based on the rainfall characteristics. Uniform utilization of harvested rainwater throughout the year from created storage tank was also considered. Based on the above consideration, the storage facility to be created from 1000 sqm roof area for Sl. No. 1,2, 3 were thought to be 3 lakh litre, 2.5 lakh litre and 1.5 lakh liters respectively.

As per SEAC proposed guidelines the rain water harvesting potential is calculated in the following Table:

MINIMUM PERCENTAGE RAIN WATER OF RAIN WATER WHICH HARVESTING TOTAL SHOULD HARVESTED POTENTIAL AS PER ROOF RAIN NO. OF BY SEAC GUIDELINES DETAILS AREA, WATER STORY SUB- SUB- SQM POTENTIAL, SURFACE SURFACE SURFACE SURFACE lakh litre STORAGE STORAGE, RECHARGE RECHARGE, (%) lakh litre (%) lakh litre G+8, Residential 11592.2 89.03 35 45 31.16 40.06 G+7

Residential G+3 2968.59 22.80 25 15 5.70 3.42

Club G+1 1346.06 10.34 10 10 1.03 1.03

Total 15906.85 122.16 37.89 44.51 TOTAL 82.40

As per SEAC proposed guidelines of storage facilities and sub-surface recharging facilities required will be 37.89 lakh liters and 44.51 lakh liters respectively. Total volume of rooftop rainwater to be harvested as per SEAC guideline is 82.40 lakh litres i.e. 8240 cum.

There are two water bodies present within the site, which act as natural rain water storage. Apart from that we are proposing 5 nos. storage tanks (3 nos. storage tanks already constructed and another 2 nos. will be constructed) each of 40 cum capacity i.e. 200 cum (total) for rooftop rainwater storage. Rest 80.40 lakh litre i.e. 8040 cum) will be recharged through 2 nos. recharge tubewell of each 150 mm diameter. Considering 81 days rainfall in a year, per day average rain water available is 99.27 cum/day. Per day average rainfall available for recharge for each recharge structure = 99.27/2 = 49.64 cum/day.

RAINWATER HARVESTING FLOW SHEET

OVER OVER INTERNAL STORM ROOF TOP RAIN STORAGE RECHARGE

WATER STRUCTURE WATER DRAIN TANKS FLOW FLOW

FINALLY TO MUNICIPAL DRAIN

RECHARGE STRUCTURE

Electricity, DG sets, Stack height

Electricity is being supplied by WBSEDCL. The electrical load is about 5375 KVA (4300 KW). DG sets - 6 nos. 180 KVA each (for residential part) has been proposed. The emission from DG sets would be discharged through stack of height 2.7 meter above DG room for each 180 KVA DG set. Fuel required for DG sets was about 173 litre/hr. Energy consumption = 38.54 W/sqm. Solar energy used will be more than 1% (43 KW) of the demand load.

TREE PLANTATION DETAILS

Sl. No. Botanical Name Common Name Quantity

1 Delonix Regia Gulmohar 6 2 Plumeria Rubra Red Frangipani 2 3 Spathodea Campanulate Spathodea 16 4 Erythrina Crista Galli Indian Coral Tree 20 5 Licuala Grandis Ruffled Fan Palm 7 6 Tecoma Gaudichaudi Yellow Bells 63 7 Lantana Depressa Yellow Lantana 1746 8 Michelia Champaca Champa 4 9 Lagerstroemia Indica Jarul 11 10 Tabebuia Rosea Pink Trumpet Tree 10 11 Cassia Fistula Amaltas 9 12 Peltophorum Ferrugineum Radha Chura/Krishnachura 16 13 Bauhinia Purpurea Purple Kachnar 12 14 Plumeria Alba White Frangipani 9 15 Mangifera indica var. 'MULLICA' Mango 5 16 Aegle marmelos Beal 1 17 Chatim 2 18 Terminalia Arjuna Arjuna 2 19 Juniper 15 20 Bottle Palm 2 Total 1958

Shrubs and Climbers 11472

Fire Fighting

There will be all provisions as per NBC-2005 and other norms of fire fighting for the given height of the building. Clearance from WBFES will be obtained.

Others

There will be adequate car parking for the owners and provision for visitor’s car park.