SESSION OF 1970. Act No. 256 773

No. 256

A SUPPLEMENT SB 1304

To the act of November 25, 1969 (P.L.310), entitled ‘An act providing for the capital budget for the fiscal year 1969-1970,” itemizing public improvement projects to be acquired or constructed by the General State Authority, together with their estimated financial costs.

The General Assembly of the Commonwealth of hereby enacts as follows:

Section 1. Short Title—This act shall be known and may be cited as the “Capital Budget Act for Fiscal Year 1969-1970, Public Improvement Project Itemization Supplement—General State Authority.” Section 2. Itemization and Authorization of Projects—Additional capital projects in the category of public improvement projects to be acquired or constructed by the General State Authority, its successors or assigns, and to be financed by the incurring of debt, are hereby itemized, together with their respective estimated financial costs and the total additional amount authorized for public improvement projects, as follows: A. Total Project Authorization $442,047,860 I. Department of Agriculture 883,000 (1) Regional Office: District No. 6 401,000 (Base Construction Cost $321,000) (2) Regional Office: District No. 3 482,000 (Land Acquisition $450,000) II. Department of Commerce 17,661,573 (1) Cover for Delaware Avenue: Penn’s Landing, Philadel- phia 4,036,573 (Base Construction Cost $3,000,000) (2) Additional Funds for GSA 650-1, Philadelphia Civic Center 1,875,000 (Base Construction Cost $1,500,000) (3) Additional Funds for GSA 1201-1, Convention-Exposi- tion Center, City of 11,750,000 (Base Construction Cost $9,378,000) III. Department of Forests and Waters 32,279,050 (1) Flood Protection Project: Blakely Borough 978,000 (Base Construction Cost $782,000) (2) Flood Protection Project: Glenside Area 773,000 (Base Construction Cost $618,000) (3) Flood Protection Project: Philipsburg Area 795,000 (Base Construction Cost $636,000) (4) Inflatable Dam: Pine Creek 278,000 (Base Construction Cost $222,000) 774 Act No. 256 LAWS OF PENNSYLVANIA,

(5) Beach Erosion Control: 625,000 (Base Construction Cost $500,000) (6) Launching Ramps: Pymatiming State Park 225,000 (Base Construction Cost $180,000) (7) FM Radio System: State Forest District No. 5 135,000 (Base Construction Cost $108,000) (8) District Office: State Forest District No. 10 110,000 (Base Construction Cost $83,000) (Land Acquisition $6,000) (9) Administration and Service Buildings and Marina, Beach and Picnic Facilities, Blanchard State Park 1,581,250 (Base Construction Cost $1,265,000) (10) Improve Water Systems: State Park 225,000 (Base Construction Cost $180,000) (11) Improvements to Camping Area: 187,500 (Base Construction Cost $150,000) (12) Swimming Facilities: Frances Slocum State Park 335,000 (Base Construction Cost $268,000) (13) Improvements to Camping Area: State Park 188,000 (Base Construction Cost $150,000) (14) Improvements to Dam: 188,000 (Base Construction Cost $150,000) (15) Water and Sanitary System: 723,500 (Base Construction Cost $578,800) (16) Expand Camping Area and Extend Camping Area Road: Keystone State Park 366,500 (Base Construction Cost $293,200) (17) Improve Day Use Area, Phase I, Keystone State Park.. 216,800 (Base Construction Cost $173,400) (18) Improvements to Camping Area: Link Pine State Park 248,000 (Base Construction Cost $198,000) (19) Marina Building: 475,000 (Base Construction Cost $380,000)

(20) Water and Sanitary System: .... 1,010,000 (Base Construction Cost $808,000) (21) Water and Sanitary System: 1,075,000 (Base Construction Cost $860,000) (22) Electrical Distribution Line: 120,000 (Base Construction Cost $96,000) SESSION OF 1970. Act No. 256 775

(23) Sanitary Sewer System: Raccoon Creek State Park 2,558,000 (Base Construction Cost $2,046,000) (24) Water and Sanitary Facilities: Rickets Glen State Park 381,000 (Base Construction Cost $305,000) (25) Administration and Service Buildings and Swimming and Day Use Facilities: 1,148,000 (Base Construction Cost $918,250) (26) Sanitary Facilities for Picnic Areas: Presque Isle State Park 136,000 (Base Construction Cost $109,000) (27) Reconstruct Outerline Drive: Valley Forge State Park 120,000 (Base Construction Cost $96,000) (28) Additional Funds for GSA 191-9, Access Facilities 62,500 (Base Construction Cost $50,000) (29) Chapman Dam State Park Camping Facilities 560,000 (Base Construction Cost $500,000) (30) Continuation of Construction of Park Improvements,

Curwensville State Park, GSA Project No. 191-13 .... 156,250 (Base Construction Cost $125,000) (Construction costs in addition to project estimate (including Base Construction Cost of $320,000) in act of January 21, 1966 (P.L.1452), section 2, IV, (7)) (31) Flood Control Project, Germania, Kettle Creek 250,000 (Base Construction Cost $200,000) (32) Additional Funds for GSA 195-1, Earth Dam, Brandy- wine, Chester County 2,096,250 (Base Construction Cost $1,677,000) (33) Danville Flood Control Project, Sechler Run, North- umberland County 2,000,000 (Base Construction Cost $1,600,000) (34) Marina, Delaware River, South of Municipal Wharf at Mill Street, Bristol Borough, Bucks County 375,000 (Base Construction Cost $300,000) (35) Widen, Deepen and Straighten Adam Hollow Creek, Bristol Borough, Bucks County 437,500 (Base Construction Cost $350,000) (36) Improve Southern Portion of Delaware Canal from Mill Creek Road in Falls Township to Adam Hollow Creek in Bristol Borough, Tullytown Borough and Falls Township, Bucks County 312,500 (Base Construction Cost $250,000) (37) Lake Erie Waterfront Development Plan: Construction of East Side Boat Launching Ramp and Parking Area 778 Act No. 256 LAWS OF PENNSYLVANIA,

Below East Avenue in Erie, Pennsylvania 950,000 (Base Construction Cost $712,500) (38) Construction of Bathing Facilities, Fireman’s Beach, Conneaut Lake, Crawford County 250,000 (Base Construction Cost $200,000) (39) Flood Control Project, Upland Borough, Delaware County 715,000 (Base Construction Cost $572,000) (40) Land Acquisition and Improvements, , Luzerne County 2,500,000 (Base Construction Cost $2,000,000) (41) Land Acquisition and Improvements, Swatara Gap, Lebanon County 3,437,500 (Base Construction Cost $2,750,000) (42) Swoyersville-Forty-Fort Flood Protection 2,000,000 (Base Construction Cost $1,600,000) (43) Wyoming-West Wyoming, Flood Protection 975,000 (Base Construction Cost $780,000) IV. Department of Health 982,000 (1) Construction of Two-Story Surgical Wing: State Hospital for Crippled Children, Elizabethtown 847,000 (Base Construction Cost $678,000) (2) Renovation, Infant Care Ward: State Hospita] for Crippled Children, Elizabethtown 135,000 (Base Construction Cost $108,000) V. Historical and Museum Commission 8,686,000 (1) Fixed Exhibit Units, Phase II: William Penn Memorial Museum 150,000 (Base Construction Cost $120,000) (2) Fixed Exhibit Units, Phase III: William Penn Memorial Museum 525,000 (Base Construction Cost $420,000) (3) Orientation Building: Port of History Museum 4,449,000 (Base Construction Cost $3,559,000) (4) Eckley Unit, Visitor Center and Restoration of Facilities, Anthracite Museum 688,000 (Base Construction Cost $550,000) (5) Lackawanna Unit, Museum and Related Facilities, An- thracite Museum 1,862,000 (Base Construction Cost $1,489,600) (6) Schuylkill Unit, Museum and Visitor Center: Anthracite Museum 561,000 (Base Construction Cost $449,000)

(7) Restoration: Old Custom House and Cashier’s House .... 188,000 (Base Construction Cost $150,000) SESSION OF 1970. Act No. 256 777

(8) Permanent Exhibit Facilities: Fort LeBoeuf 113,000 (Base Construction Cost $90,000) (9) Lumber Museum, Sheffield, Warren County 150,000 (Base Construction Cost $120,000) VI. Department of Justice 17,299,400 (1) Electric Generation for Power Plant Building: State Correctional Institution, Dallas 300,000 (Base Construction Cost $250,000) (2) Replace Water Tank: State Correctional Institution, Graterford 286,500 (Base Construction Cost $229,200) (3) Electrical Improvement: State Correctional Institution, Huntingdon 834,600 (Base Construction Cost $667,700) (4) New Correctional Institution: Region II, Lackawanna County 6,250,000 (Base Construction Cost $5,000,000) (5) Three Cell Buildings and Corridor Extension: State Regional Institution at Creensburg 1,633,000 (Base Construction Cost $1,306,748) (6) New Maximum Security Cell Block, State Correctional Institution, Craterford 785,000 (Base Construction Cost $644,000) (7) New Correctional Institution: Region VI 6,151,000 (Base Construction Cost $4,920,740) (8) New Correctional Institution: Region I 481,500 (Land Acquisition Only $450,000) (9) New Correctional Institution: Region III 321,000 (Land Acquisition Only $300,000) (10) New Correctional Institution: Region IV 256,800 (Land Acquisition Only $240,000) VII. Department of Military Affairs 2,054,000 (1) Rehabilitation and Addition: Berwick Armory 193,000 (Base Construction Cost $154,000) (2) Rehabilitation and Addition: Bethlehem Armory 245,000 (Base Construction Cost $196,000) (3) Construct New Armory: Greensburg 171,000 (Base Construction Cost $137,000) (4) Addition: Hamburg Armory 178,000 (Base Construction Cost $142,000)

(5) Addition to Administrative Wing: Harrisburg Armory .... 158,000 (Base Construction Cost $126,000) (6) Addition: Indiantown Gap Armory 225,000 (Base Construction Cost $180,000) 778 Act No. 256 LAWS OF PENNSYLVANIA,

(7) Addition: Johnstown Armory. 321,000 (Base Construction Cost $257,000) (8) Addition: Ligonier Armory 188,000 (Base Construction Cost $150,000) (9) Renovation and Addition: Nanticoke Armory 375,000 (Base Construction Cost $300,000) VIII. Department of Property and Supplies 1,656,000 (1) Rehabilitation and Replacement of Exterior Lighting, Capitol Area 900,000 (Base Construction Cost $720,000) (2) Expansion of Commonwealth Garage: Capitol Area 756,000 (Base Construction Cost $605,000) IX. Department of Education 290,137,692 (1) Classroom Building: Bloomsburg State College 2,625,000 (Base Construction Cost $2,100,000) (2) Air-Condition Sutliff Hall: Bloomsburg State College 150,000 (Base Construction Cost $120,000) (3) Women’s Dormitory, Lower Campus: Bloomsburg State College 2,256,000 (Base Construction Cost $1,805,000) (4) One New Boiler and Convert Three Existing Boilers: Bloomsburg State College 312,500 (Base Construction Cost $250,000) (5) Expansion of Utilities: California State College 954,000 (Base Construction Cost $763,000) (6) Health Services Building: California State College 673,000 (Base Construction Cost $538,200) (7) Parking Area: California State College 312,500 (Base Construction Cost $250,000) (8) Industrial Arts Addition, Phase H: California State College 406,000 (Base Construction Cost $325,000) (9) Fine Arts and Humanities Building: California State College 2,250,000 (Base Construction Cost $1,800,000) (10) Renovate Existing Boiler Plant to Include Installation of Two Gas-Oil Fired Boilers: California State College.. 343,750 (Base Construction Cost $275,000) (11) Additional Funds for GSA 402-30, Land Acquisition and Demolition: California State College 852,537 (Acquisition $740,000; Demolition $60,000) (12) Improvement and Extension of Utilities, and Site Development, Cheyney State College 2,000,000 (Base Construction Cost $1,600,000) SESSION OF 1970. Act No. 256 779

(13) Garage and Maintenance Building: Cheyney State College 938,000 (Base Construction Cost $750,000) (14) Land Acquisition: Cheyney State College 107,000 (Land Acquisition Cost $100,000) (15) Additional Funds for GSA 403-26, Industrial Arts Building; Cheyney State College 875,000 (Base Construction Cost $700,000) (16) Expansion of Sewage Treatment Plant: Cheyney State College 700,000 (Base Construction Cost $560,000) (17) Liberal Arts Building: Clarion State College 5,599,000 (Base Construction Cost $4,479,000) (18) Utilities Expansion No. 3: Clarion State College 345,000 (Base Construction Cost $276,000) (19) Library Classroom Building, Venango Campus, Clarion State College 787,275 (Base Construction Cost $629,820) (20) Instructional Complex and Campus Master Plan Venan- go Campus, Clarion State College 960,000 (Base Construction Cost $768,000) (21) Fine Arts Building: East Stroudsburg State College 4,573,000 (Base Construction Cost $3,658,000) (22) Science Building and Land Acquisition: East Strouds- burg State College 2,404,000 (Base Construction Cost $1,776,000) (Land Acquisition $172,000) (23) Data Processing and Computer Center: East Strouds- burg State College 188,000 (Base Construction Cost $150,000) (24) Extension of Utilities and boiler Conversion: East Stroudsburg State College 600,000 (Base Construction Cost $480,000) (25) Auditorium: Edinboro State College 4,000,000 (Base Construction Cost $3,200,000) (26) Conversion of Ross Dining Hall to Electric Heat: Edinboro State College 125,000 (Base Construction Cost $100,000) (27) Administration Building: Edinboro State College 1,250,000 (Base Construction Cost $1,000,000) (28) Additional Funds for GSA 406-36, Dormitory Complex, Edinboro State College 952,500 (Base Construction Cost $762,000) 780 Act No. 256 LAWS OF PENNSYLVANIA,

(29) Student Center Addition: Edinboro State College 1,211,000 (Base Construction Cost $969,000) (30) Additional Funds for GSA 406-32, Library: Edinboro State College 2,500,000 (Base Construction Cost $2,000,000) (31) Dining Hall and Parking Area: Indiana University of Pennsylvania 3,474,000 (Base Construction Cost $2,779,000) (32) Women’s Health and Physical Education Building and

Land Acquisition - Indiana University of Pennsylvania 4,804,000 (Base Construction Cost $3,555,000) (Land Acquisition $336,000) (33) Utility’ Expansion: Indiana University of Pennsylvania.. 600,000 (Base Construction Cost $480,000) (34) Education Center: Indiana University of Pennsylvania 3,766,000 (Base Construction Cost $2,769,000) (Land Acquisition Cost $285,000) (35) Graduate Hall and Computer Center: Indiana University of Pennsylvania 3,167,000 (Base Construction Cost $2,431,000) (Land Acquisition $120,000) (36) Classroom Building: Kutztown State College 2,066,250 (Base Construction Cost $1,653,000) (37) Dormitory: Kutztown State College 2,820,750 (Base Construction Cost $2,256,600) (38) Dining Hall Addition: Kutztown State College 1,678,500 (Base Construction Cost $1,350,000) (39) Utility Extension: Kutztown State College 750,000 (Base Construction Cost $600,000) (40) Conversion of Power Plant and Additional Boiler: Kutztown State College 187,500 (Base Construction Cost $150,000) (41) Raub Hall Air-Conditioning: Lock Haven State College 180,000 (Base Construction Cost $144,000) (42) Research-Learning Center: Lock Haven State College 4,617,500 (Base Construction Cost $3,694,000) (43) Utilities and Facilities Extensions: Lock Haven State College 288,000 (Base Construction Cost $230,000) (44) Women’s Dormitory: Mansfield State College 5,625,000 (Base Construction Cost $4,500,000) SESSION OF 1970. Act No. 256 781

(45) Utilities Expansion: Mansfield State College 450,000 (Base Construction Cost $360,000) (46) Additional Funds for GSA 410-20, Renovation of Arts Building: Mansfield State College 344,000 (Base Construction Cost $275,216) (47) Osborn Hall Renovation: Millersville State College 300,000 (Base Construction Cost $240,000) (48) Land Acquisition: Millersville State College 500,000 (Land Acquisition $467,000) (49) Dining Hall (West): Millersville State College 3,519,300 (Base Construction Cost $2,760,000) (Land Acquisition $39,000) (50) Dormitory: Shippensburg State College 3,620,750 (Base Construction Cost $2,896,600) (51) Athletic Field-Additional Funds-(GSA 412-21): Shippens- burg State College 875,000 (Base Construction Cost $700,000) (52) Construction and Extension of Utilities: Shippensburg State College 775,000 (Base Construction Cost $620,000) (53) Additional Steam Generating Capacity and Boiler Con- version: Shippensburg State College 375,000 (Base Construction Cost $300,000) (54) Site Development and Extension of Utilities, Roads and Parking Areas: Slippery Rock State College 2,560,000 (Base Construction Cost $2,048,000) (55) Maintenance Building and Garage: Slippery Rock State College 750,000 (Base Construction Cost $600,000) (56) Women’s Dormitory: Slippery Rock State College 5,000,000 (Base Construction Cost $4,000,000) (57) Land Acquisition: Slippery Rock State College 272,500 (Land Acquisition $250,000) (58) Dining Hall (GSA 2413-7): Slippery Rock State College 3,318,000 (Base Construction Cost $2,654,000) (59) Conversion of Boiler Plant: Slippery Rock State College 375,000 (Base Construction Cost $300,000) (60) Student Health and Life Center: West Chester State College 3,392,500 (Base Construction Cost $2,714,000) (61) Land Acquisition: West Chester State College 108,000 (Land Acquisition $101,000) 782 Act No. 256 LAWS OF PENNSYLVANIA,

(62) South Campus Site Development, Phase II: West Chester State College 737,500 (Base Construction Cost $590,000) (63) Utility Extensions: West Chester State College 1,193,000 (Base Construction Cost $954,000) (64) Conversion of Boiler Plant: West Chester State College 250,000 (Base Construction Cost $200,000) (65) School Building Addition: Scotland School for Veterans’ Children 805,000 (Base Construction Cost $644,000) (66) Sanitary Sewer System: Scotland School for Veterans’ Children 335,000 (Base Construction Cost $268,000) (67) Alterations to Boiler Plant and Electrical System: Scotland School for Veterans’ Children 437,500 (Base Construction Cost $350,000) (68) Additional Funds for GSA 416-2, New Primary Building: Pennsylvania State Oral School for the Deaf 674,000 (Base Construction Cost $539,136) (69) Student Center and Dining Hall: Thaddeus Stevens Trade School 811,000 (Base Construction Cost $649,000) (70) Two Dormitories-125 Each: Thaddeus Stevens Trade School 1,991,000 (Base Construction Cost $1,593,000) (71) Utilities and Service Areas: Thaddeus Stevens Trade School 339,500 (Base Construction Cost $271,600) (72) Administration Building, State Fire Training School, Lewistown 280,000 (Base Construction Cost $224,000) (73) Addition to Physical Science Building Unit I: The Pennsylvania State University-University Park Campus 1,S75,000 (Base Construction Cost $1,500,000) (74) Student Recreation and Intramural Physical Education Building: The Pennsylvania State University Park Campus 5,247,500 (Base Construction Cost $4,198,000) (75) Environmental Science Building: The Pennsylvania State University-University Park Campus 6,806,000 (Base Construction Cost $5,445,000) SESSION OF 1970. Act No. 256 788

(76) Expansion of Utilities: The Pennsylvania State Univer- sity-University Park Campus 5,730,000 (Base Construction Cost $4,584,000) (77) Three Maintenance Service Buildings: The Pennsylvania State University 433,000 (Base Construction Cost $346,000) (78) Conversion of Osmond Laboratory Building: The Pennsylvania State University 500,000 (Base Construction Cost $400,000) (79) Conversion of Mineral Industries, Willard and Mineral Sciences Buildings: The Pennsylvania State University 1,430,000 (Base Construction Cost $1,144,000) (80) Road System Expansion: The Pennsylvania State Uni- versity, University Park Campus 628,750 (Base Construction Cost $503,000) (81) Central Air Conditioning Plant and Accessories, The Pennsylvania State University 8,400,000 •(Base Construction Cost $6,720,000) (82) Additional Funds for GSA 800-7 1, Construction of Auditorium and Lecture Hall, The Pennsylvania State University 2,875,000 (Base Construction Cost $2,300,000) (83) Multipurpose Building: Pennsylvania State University, Altoona Campus 1,684,000 (Base Construction Cost $1,347,000) (84) Physical Education Building, Pennsylvania State Uni- versity, Altoona Campus 625,000 (Base Construction Cost $500,000) (85) Development and Expansion of Utilities: Pennsylvania State University, Behrend Campus 310,000 (Base Construction Cost $248,000) (86) Library: The Pennsylvania State University, Berks Campus 1,198,000 (Base Construction Cost $958,000) (87) Physical Education Building, The Pennsylvania State University, Capitol Campus 3,100,700 (Base Construction Cost $2,480,500) (88) Student Study and Learning Center: The Pennsylvania State University, DuBois Campus 1,360,000 (Base Construction Cost $1,088,000) (89) Development and Expansion of Utilities: The Pennsyl- vania State University, Hazleton Campus 206,000 (Base Construction Cost $165,000) 784 Act No. 256 LAWS OF PENNSYLVANIA,

(90) Physical Education Building: The Pennsylvania State University, Hazieton Campus 2,850,000 (Base Construction Cost $2,281,600) (91) Extension of Utilities: The Pennsylvania State University, McKeesport Campus 925,000 (Base Construction Cost $740,000) (92) Science Building: The Pennsylvania State University, Mont Alto Campus 2,295,000 (Base Construction Cost $1,836,000) (93) Development and Expansion of Utilities: The

Pennsylvania State University, Mont Alto Campus .... 528,750 (Base Construction Cost $423,000) (94) Development and Expansion of Utilities: The Pennsyl- vania State University, Ogontz Campus 275,000 (Base Construction Cost $220,000) (95) Multipurpose Building: The Pennsylvania State Univer- sity, Schuylkill Campus 1,598,750 (Base Construction Cost $1,279,000) (96) Student Study and Learning Center: The Pennsylvania State University, Scranton Campus 1,270,000 (Base Construction Cost $1,016,000) (97) Development and Expansion of Utilities: The Pennsyl- vania State University, Shenango Campus 275,000 (Base Construction Cost $220,000) (98) Development and Expansion of Utilities: The Pennsyl- vania State University, Wilkes-Barre Campus 525,000 (Base Construction Cost $420,000) (99) Classroom Building: The Pennsylvania State University, York Campus 1,655,000 (Base Construction Cost $1,324,000) (100) Additional Funds for Project GSA 1103-13, Profes-

sional Quadrangle: The University of Pittsburgh .... 18,642,250 (Base Construction Cost $14,913,000) (101) Chilled Water Distribution System: The University of Pittsburgh 1,671,000 (Base Construction Cost $1,337,000) (102) School of Nursing and Allied Health Professions Building: The University of Pittsburgh 9,742,500 (Base Construction Cost $7,780,000) (Acquisition $250,000) (103) Additional Funds for GSA 1103-10, Natural Science Facility Underground, Phase II, Chemistry Building: The University of Pittsburgh 4,750,000 (Base Construction Cost $3,800,000) SESSION OF 1970. Act No. 256 785

(104) Land Acquisition and Demolition, Forbes Area: The University of Pittsburgh 2,919,000 (Base Construction Cost $200,000) (Land Acquisition $2,164,000) (105) Psychology Building: The University of Pittsburgh 4,298,000 (Base Construction Cost $1,440,000) (Land Acquisition $2,335,000) (106) Relocation of Utilities: The University of Pittsburgh, Forbes Complex 1,875,000 (Base Construction Cost $1,500,000) (107) Academic Building: The University of Pittsburgh, Bradford Campus 1,992,500 (Base Construction Cost $1,594,000) (108) Laboratory Building: The University of Pittsburgh, Bradford Campus 2,561,250 (Base Construction Cost $2,049,000) (109) Science Building: The University of Pittsburgh, Greensburg Campus 2,731,250 (Base Construction Cost $2,185,000) (110) Engineering and Science Building: The University of Pittsburgh, Johnstown Campus 3,720,000 (Base Construction Cost $2,750,000) (111) Library Building: The University of Pittsburgh, Titusville Campus 1,650,000 (Base Construction Cost $1,320,000) (112) Addition to Underground Electrical-Signal Systems, Health Services Center: Temple University 728,750 (Base Construction Cost $583,000) (113) Addition to Underground Electrical-Signal Systems, Broad and Montgomery Campus: Temple University 375,000 (Base Construction Cost $300,000) (114) Urban Center: Temple University 15,818,000 (Base Construction Cost $12,519,000) (Land Acquisition $135,000) (115) Computer Center: Temple University 8,695,000 (Base Construction Cost $6,956,000) (116) Additional Funds for GSA 1104-15, Clinical Teaching Building and Expansion of Outpatient Facility: Temple University 25,841,250 (Base Construction Cost $20,673,000) (117) Ambler Campus: Temple University Amphitheater Roof 375,000 (Base Construction Cost $300,000) 786 Act No- 256 LAWS OF PENNSYLVANIA,

(118) Women’s Medical College . 1,783,332 Additional authorization required as the college share for the clinical teaching and service building (GSA 1107-1). When this project is leased by the authority to the Department of Education, the department shall sublease this portion of the project to the medical college for the same aggregate rentals as this portion of the authority’s lease to the department, upon terms and conditions as shall be agreed to. This provision shall not be applicable to that portion of the project previously designated as the authority share. (119) Additional Funds for GSA 1505-5, Physical Education Center and Land Acquisition: Drexel University 2,500,000 (Base Construction Cost $2,000,000) (120) Additional Funds for University of Pennsylvania’s share of new facility for Children’s Hospital of Philadelphia to be used for service to the University as its Pediatric Division 13,199,048 (Base Construction Cost $12,191,185) X. Department of Public Welfare 56,354,945 (1) Utility Distribution System: Dixmont State Hospital 3,100,000 (Base Construction Cost $2,480,000) (2) Water Distribution System: 256,250 (Base Construction Cost $205,000) (3) Electric System in South-2 Annex Building: Mayview State Hospital 210,000 (Base Construction Cost $168,000) (4) Increase Capacity, Main Sub-Station: Philadelphia State Hospital 500,000 (Base Construction Cost $400,000) (5) Renovate Steam Supply and Return System: Philadelphia State Hospital 750,000 (Base Construction Cost $600,000) (6) Additional Funds for GSA 514-17, Specialized Thera- peutic Activity Facility: 125,000 (Base Construction Cost $100,000) (7) New Water Distribution System: Woodville State Hospital 675,000 (Base Construction Cost $540,000) (8) Renovation of Electrical Distribution System: Woodville State Hospital 2,813,000 (Base Construction Cost $2,250,000) (9) Renovation of Electrical Distribution System-Phase II: Cresson State School and Hospital 1,116,250 (Base Construction Cost $893,000) SESSION OF 1970. Act No. 256 787

(10) Renovation of Electrical Distribution System-Phase III: Laurelton State School and Hospital 1,583,000 (Base Construction Cost $1,266,000) (11) Renovation of Utilities: Pennhurst State School and Hospital 2,678,000 (Base Construction Cost $2,142,000) (12) Renovation of Patient Building-Female 1: Pennhurst State School and Hospital 2,300,000 (Base Construction Cost $1,840,000) (13) Renovation of Patient Building-Female 2: Pennhurst State School and Hospital 2,300,000 (Base Construction Cost $1,840,000) (14) Additional Funds for GSA 551-14, Patient Building for Hyperactive Children, Air Conditioning: Pennhurst State School and Hospital 387,500 (Base Construction Cost $310,000) (15) New Boiler Plant: Polk State School and Hospital 3,868,000 (Base Construction Cost $3,094,000) (16) Additional Funds for GSA 518.1, Altoona Geriatric Center 2,620,345 (Base Construction Cost $2,097,000) (17) Additional Funds for GSA 534-5, Main Hospital Building and Renovate Maternity Wing: Hazleton State General Hospital 1,468,800 (Base Construction Cost $1,175,000) (18) Renovations to Boiler Plant: Scranton State General Hospital 250,000 (Base Construction Cost $200,000) (19) Philadelphia Diagnostic and Rehabilitation Center 2,649,800 (Base Construction Cost $2,000,000) (Land Acquisition $140,000) (20) Construction of Annex to Philadelphia State Hosp~ta1for Resident Treatment Addiction Center for Rehabili- tation of Alcoholics and Narcotics Patients: St. Lukes and Children’s Medical Center, Philadelphia 5,625,000 (Base Construction Cost $4,500,000) (21) For planning, design and construction of mental retardation service units; and, acquisition of property, total population survey and social system analysis as required to provide definitive treatment and normalizing accommodations for mentally retarded residents of Bucks, Chester, Delaware, Montgomery and Philadelphia Counties and to be located in the same counties. The units are to provide accommodations for approximately 900 788 Act No. 256 LAWS OF PENNSYLVANIA,

patients to reduce the population at Pennhurst State School and Hospital to a maximum of 1,000. This capital investment to provide logical dispersal and reorientation into the community for Pennhurst residents and alternatives to institutionalization for the Pennhurst waiting list population and other mentally retarded citizens of the area who require such treatment and accommodations. This program is to be completed as expeditiously as possible so that the first units may be occupied not later than two years from the effective date of this act 21,079,000 (Base Construction Cost, Acquisition, Survey and Analysis $16,863,000) XI. Department of Revenue 562,500 (1) Driver Examination Point: Cumberland County 285,000 (Base Construction Cost $210,000) (Land Acquisition $21,000) (2) Driver Examination Point: Columbia County 277,500 (Base Construction Cost $210,000) (Land Acquisition $14,000) XII. Pennsylvania State Police 12,591,700 (1) Substation and Driver Examination Point: Bucks County 752,000 (Base Construction Cost $581,000) (Land Acquisition $24,000) (2) Troop Headquarters: Dauphin County 2,125,000 (Base Construction Cost $1,700,000) (3) Substation: Delaware County 433,200 (Base Construction Cost $326,000) (Land Acquisition $24,000) (4) Substation: Montgomery County 446,000 (Base Construction Cost $336,000) (Land Acquisition $24,000) (5) Substation: Venango County 168,750 (Base Construction Cost $135,000) (6) State Police Crime Laboratory, Wyoming Barracks: Luzerne County 243,750 (Base Construction Cost $195,000) (7) Regimental Headquarters: Dauphin County 8,423,000 (Base Construction Cost $6,711,000) (Land Acquisition $32,000) XIII. Department of Transportation 900,000 (1) Emergency Equipment and Maintenance Building, Olmsted State Airport 900,000 (Base Construction Cost $720,000) SESSION OF 1970. Act No. 256 789

Section 3. Allocation of Funds—Whenever as determined by the General State Authority, the full estimated financial cost of any of the public improvement projects itemized in section 2 hereof is not necessary for the proper design, acquisition or construction of such project, the excess funds no longer required may be allocated by the General State Authority to increase the estimated cost of any one or more of the public improvement projects specifically itemized in a capital budget. Section 4. Effective Date—This act shall take effect immediately. APPRovED—The 27th day of November, A. D. 1970. RAYMOND P. SHAFER The foregoing is a true and correct copy of Act of the General Assembly No. 256.