Received April 6, 2021 at 9:30 am

April 05, 2021

Via E-mail Delivery: [email protected]

Breeyn Handberg Rapid Response Program Manager Office of Workforce Development 4020 East 5th Avenue P.O. Box 1618 Columbus, OH 43216-1618

Re: WARN Notice

Dear Ms. Handberg:

This is to notify you that Bechtel Infrastructure and Power Corporation will permanently destaff and cease operations at the South Field Energy Facility Project, 43250 Hibbetts Mill Road (Township 1006), Wellsville, OH 43968, commencing on June 15, 2021. We currently expect to complete all our work and cease operations at the site by November 30, 2021.

A total of 63 employees will be impacted through November 30, 2021. The anticipated schedule of separations is as follows: June 15, 2021 (1); June 25, 2021 (3); June 30, 2021 (8); July 16, 2021 (1); July 30, 2021 (16); August 13, 2021 (1); August 31, 2021 (22); September 30, 2021 (5); October 29, 2021 (5); and November 30, 2021 (1). Attachment A sets forth the job titles/job family of positions to be affected and the number of employees in each job title/job family. The employees are not represented by a union. No bumping rights exist, and the separations are expected to be permanent.

Should you have any questions or would like additional information concerning this matter, please contact Cheryl McTamany, Human Resources Representative, 12011 Sunset Hills Rd, Suite 110, Reston, 20190, (571) 262-0755.

Sincerely,

Mark Voorhis Project Manager, South Field Project

Attachment A enclosed

Bechtel Infrastructure and Power Corporation 12011 Sunset Hills Rd Suite 110 Reston, VA 20190

Attachment A

JOB Title/Family NUMBER Project Controls 6 Field Engineers/Superintendents 26 Project Accounting 1 IS&T 1 Startup Engineers 15 Contract Administrators/ 6 1 Administration/Document Management 4 Safety 3

Total 63

Bechtel Infrastructure and Power Corporation 12011 Sunset Hills Rd Suite 110 Reston, VA 20190