PROJECT NOTE by the Project Authority
Total Page:16
File Type:pdf, Size:1020Kb
PROJECT NOTE By the Project Authority Name of the Project: Improvement of Daund - Karmala - Paranda - Barshi - Osmanabad Road, SH 68 (Km 137/260 to Km 189/120) Part Barshi to Osmanabad Dist.- Solapur. 1.0 GENERAL 1.1 The Government of Maharashtra has taken up a massive programme of up- gradation and development of existing two-lane State Highways taking in account the rapid economic and financial growth of the state under Maharashtra Road Improvement Programme (MRIP). The Government of Maharashtra also taking financial aid from Asian Development Bank (ADB) for the execution of the same. 1.2 One of the Major stretches included under this is Daund-Karmala-Paranda Barshi - Osmanabad Road, SH-68. The Major portion of this stretch passes through Solapur district. The Solapur district is foremost players in tourism and aided industry along with agricultural. It is a need of an hour for better transportation facilities to cope up with the future demands. The state highway connects to other major National Highways, State highways and cities of the state using secondary roads like Major District Roads. Considering all the major factors, the Government has taken a policy decision of developing this state highway for better and safe transportation. 2.0 DESIGN STANDARDS 2.1 Road markings perform the important function of guiding and controlling traffic on a highway. The markings serve as psychological barriers and signify the delineation of traffic paths and their lateral clearance from traffic hazards for safe movement of traffic. Road markings are therefore essential to ensure smooth and orderly flow of traffic and to promote road safety. The Code of Practice for Road Markings, IRC: 35-2015 will be used in the study as the design basis. The location and type of marking lines, material and colour is followed using IRC: 35-2015 “Code of Practice for Road Markings”. The road markings are carefully planned on carriageways, intersections, parking and bridge locations. 2.2. Roads Improvement of Daund - Karmala - Paranda - Barshi - Osmanabad Road, SH 68 (Km 137/260 to Km 189/120) Part Barshi to Osmanabad Dist.- Solapur are provided in Table 2.1 Table 2.1 Improvement Proposals Sr. No. Design Elements Proposed Features 1 Design speed 20 Km/h to 80 Km/h 2 Right of way in Open area(m) As per ROW – 12mtr. 3 Right of way in Built up area(m) As per ROW – 14mtr. 4 Carriageway width 3.5m. lane 7.00m 5 Paved Shoulder (m) 1.50 on either side 6 Earthen Shoulder (m) 1.0m on either side 7 Edge Strip (m) - 8 Median (m) - 9 Lane width 3.5 m. 10 Longitudinal Gradient (%) - Ruling - Absolute - Minimum - 10 Cambers - 11 Bus Bays 09 Nos. 12 Truck lay byes Nil B. Bridge and Culverts The numbers of Bridges/Flyovers/CD structures widening, proposed for the project is presented in the table -2.2 Table 2.2 Widening, Proposed Bridges, Flyovers & CD structures Sr. No. Structures Nos. 1 No. of Major bridges 02 Nos. 2 No. of Minor bridges 11 Nos. 3 Flyover/ROB Nil 4 Vehicular underpass Nil 5 Pedestrian underpass Nil 6 Cattle/underpass Nil 7 Tunnels Nil 8 Foot Over Bridges Nil 9 Slab Drain 05 Nos. 10 Culverts 47 Nos. 2.3 Road Alignment The development of the road under consideration starts at Ch: 137/260 Km on Korti District border and ends at Awati District border at Ch: 189/120 Km (excluding karamala Municipal length- 1.32km) Dist. Solapur measuring of 50.54 Km in Maharashtra state. 2.4 Proposed ROW In general, right of way (ROW) of 12 mtr in open area and 14 mtr in built up area are required for the 2 lanes road. 2.5 Lane Configuration Based on the traffic survey, analysis and forest the 2-lane configuration is sufficient to cater to the traffic up to year 2035. 2.6 Financial Details The capital cost of the project 136.51 Crores Construction period 24 Months Date: 30/08/2019 Place: Solapur. (V. H. More) Executive Engineer, Public Work Division No.2, Solapur. .