Power Supply Procurement Plan

Total Page:16

File Type:pdf, Size:1020Kb

Power Supply Procurement Plan POWER SUPPLY PROCUREMENT PLAN BUKIDNON SECOND ELECTRIC COOPERATIVE, INC. POWER SUPPLY PROCUREMENT PLAN In compliance with the Department of Energy’s (DOE) Department Circular No. DC 2018-02-0003, “Adopting and Prescribing the Policy for the Competitive Selection Process in the Procurement by the Distribution Utilities of Power Supply Agreement for the Captive Market” or the Competitive Selection process (CSP) Policy, the Power Supply Procurement Plan (PSPP) Report is hereby created, pursuant to the Section 4 of the said Circular. The PSPP refers to the DUs’ plan for the acquisition of a variety of demand-side and supply-side resources to cost-effectively meet the electricity needs of its customers. The PSPP is an integral part of the Distribution Utilities’ Distribution Development Plan (DDP) and must be submitted to the Department of Energy with supported Board Resolution and/or notarized Secretary’s Certificate. The Third-Party Bids and Awards Committee (TPBAC), Joint TPBAC or Third Party Auctioneer (TPA) shall submit to the DOE and in the case of Electric Cooperatives (ECs), through the National Electrification Administration (NEA) the following: a. Power Supply Procurement Plan; b. Distribution Impact Study/ Load Flow Analysis conducted that served as the basis of the Terms of Reference; and c. Due diligence report of the existing generation plant All Distribution Utilities’ shall follow and submit the attached report to the Department of Energy for posting on the DOE CSP Portal. For ECs such reports shall be submitted to DOE and NEA. The NEA shall review the submitted report within ten (10) working days upon receipt prior to its submission to DOE for posting at the DOE CSP Portal. The content of the PSSP shall be consistent with the DDP. The tables and graph format to be use on the PSPP report is provided on the following sheets. Further, the PSPP shall contain the following sections: I. Table of Contents II. Introduction III. Energy and Demand Forecast (10 year historical and forecast) IV. Energy Sales and Purchase V. Daily Load Profile and Load Duration Curve VI. Existing Contracts & Existing GenCos due diligence report VII. Currently approved SAGR for Off-Grid ECs to be passed-on to consumers; VIII. DU’s Current Supply and Demand IX. Distribution Impact Study X. Schedule of Power Supply Procurement XI. Timeline of the CSP For inquiries, you may send it at [email protected] or you may contact us through telephone numbers (02) 840-2173 and (02) 479-2900 local 202. POWER SUPPLY PROCUREMENT PLAN I. TABLE OF CONTENTS I. Table of Contents II. Introduction 1 III. Energy Sales and Purchase 2 IV. EC's Current Demand and Supply 3 V. Daily Load Profile and Load Duration Curve 4 VI. Existing Contracts & Existing GenCos due diligence report 6 VII. Distribution Impact Study 7 VIII. Schedule of Power Supply Procurement 8 IX. Energy and Demand Forecast 13 POWER SUPPLY PROCUREMENT PLAN II. INTRODUCTION DISTRIBUTION UTILITIES PROFILE The Bukidnon Second Electric Cooperative, Inc. (BUSECO) has been formed in accordance with the provisions of PD 269 under the NEA, and was registered on July 28, 1977. BUSECO’s franchise was granted permanent on June 10, 1981. However, construction immediately followed after the registration. Operations started on February 2, 1970 when BUSECO took over Manolo Fortich Municipal Electrical System, even if the first energization was on June 29, 1979 yet. BUSECO is a non-stock, non-profit Electric Distribution Utility (EDU) registered with the National Electrification Administration (NEA) under PD 269 as amended on September 27, 1979. Its main office is located in Barangay Tankulan, Manolo Fortich, Bukidnon and has an area office in Casisang, Malaybalay City, Bukidnon. BUSECO serves the City of Malaybalay, Municipality of Manolo Fortich, Sumilao, Impasug-ong, Sumilao, Lantapan, Cabanglasan, Libona, Baungon, Malitbog and a portion of the Municipality of Talakag and the City of Valencia. Number of ACTUAL FORECAST Customer 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Residential 89,745 94,462 99,363 104,437 109,664 115,026 120,508 126,098 131,785 137,560 143,416 Commercial 4,802 5,054 5,317 5,588 5,868 6,155 6,448 6,747 7,051 7,360 7,674 Industrial 572 602 633 666 699 733 768 804 840 877 914 Others 2,596 2,732 2,874 3,021 3,172 3,327 3,486 3,648 3,812 3,979 4,149 Contestable Customers - served by RES - - - - - - - - - - Total (Captive Customers) 97,715 102,851 108,187 113,712 119,403 125,241 131,210 137,296 143,488 149,776 156,152 The increase of demand was mainly attributable to 2018 No. of Customers the entry of big loads. Residential Commercial Industrial Others POWER SUPPLY PROCUREMENT PLAN III. ENERGY SALES AND PURCHASE ENERGY SALES AND HISTORICAL PURCHASE 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Energy Sales (MWh) 88,712 92,616 104,575 109,772 118,505 124,365 135,034 144,306 161,617 174,332 Energy Purchase (MWh) 101,225 106,524 118,563 124,198 133,098 139,323 148,815 161,012 181,308 191,052 System Loss (MWh) 12,513 13,908 13,988 14,426 14,593 14,958 13,781 16,706 19,691 16,720 ENERGY SALES AND FORECAST PURCHASE 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Energy Sales (MWh) 229,806 274,855 295,918 316,287 335,956 356,209 375,804 396,037 416,256 436,874 Energy Purchase (MWh) 247,154 293,594 316,466 339,034 361,265 384,413 407,211 430,930 454,898 479,508 System Loss (MWh) 17,348 18,739 20,548 22,748 25,309 28,204 31,407 34,893 38,642 42,634 Energy Purchase vs Energy Sales Energy, MWHEnergy, 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 FORECAST YEARS Energy Sales (MWh) Energy Purchase (MWh) System Loss (MWh) Based on the 10 year forecasted data, it can be inferred that there will be an average increase of 10% in energy sales and energy purchase. Meanwhile, the system loss from 2009 of 12% and is projected to decrease to 8.34% in 2019. POWER SUPPLY PROCUREMENT PLAN IV. EC’s CURRENT SUPPLY AND DEMAND HISTORICAL Demand 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Coincident Peak 19.47 21.45 24.61 24.10 25.86 27.83 28.47 29.70 33.09 33.62 Demand (MW) Off Peak Demand 11.82 13.10 15.06 15.98 17.91 19.28 18.87 19.55 19.38 23.29 (MW) FORECAST Demand 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Coincident Peak 40.76 49.35 53.92 58.27 62.45 66.82 71.19 75.76 80.40 85.15 Demand (MW) Off Peak Demand 28.23 34.19 37.35 40.36 43.26 46.29 49.31 52.48 55.69 58.98 (MW) Coincident Peak Demand vs Off-peak Demand 85.15 80.40 75.76 71.19 66.82 62.45 58.98 58.27 55.69 53.92 52.48 49.35 49.31 46.29 MW 43.26 40.76 40.36 37.35 34.19 28.23 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 HISTORICAL Years Coincident Peak Demand (MW) Off Peak Demand (MW) BUSECO's growth rate in terms of demand for the past 10 years is at 6.15%. It is then forecasted that for the next 10 (ten) years, BUSECO's demand will have an increase of 4.61%. The forecasting methodology used is Minitab: Winter's Method, additive: time series. 15 MW is its baseloaddemand at while 25 MW. As reflected inthe2017 Load Profile Load Durationand is Curve,peak estimated BUSECO's demand at 10000 15000 20000 25000 30000 35000 10000 15000 20000 25000 30000 35000 5000 5000 Axis Title 0 0 1 1 238 304 ANDDURATIONCURVE LOAD PROFILE LOAD V. DAILY 475 607 712 910 949 1213 1186 1423 1516 1660 1819 1897 2122 2134 (MW) Curve Load BUSECO 2018 2425 POWER SUPPLY PROCUREMENT PLAN 2371 2728 Curve(MW) Duration Load 2608 3031 2845 3334 3082 3637 3319 3940 3556 4243 3793 4030 4546 4267 4849 4504 5152 4741 5455 4978 5758 5215 6061 5452 6364 5689 6667 5926 6970 6163 7273 6400 6637 7576 6874 7879 7111 8182 7348 8485 7585 7822 8059 (MW) Demand Coincident 8296 8533 POWER SUPPLY PROCUREMENT PLAN VI. EXISTING CONTRACTS & EXISTING GENCOS DUE DILIGENCE REPORT MIX SUPPLY VS DEMAND AND THE OPTIMAL SUPPLY ACTUAL FORECAST Supply Demand 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Demand, MW 32.32 34.09 36.96 40.07 43.41 46.94 50.64 54.50 58.49 62.62 66.86 Spot Load, MW 6.67 12.39 13.85 14.86 15.51 16.18 16.69 17.27 17.78 18.29 Total Demand, MW 32.32 40.76 49.35 53.92 58.27 62.45 66.82 71.19 75.76 80.40 85.15 Supply Contracted, MW 39.38 39.59 29.36 33.18 33.18 33.18 33.18 33.18 33.18 33.18 33.18 NPC/PSALM 14.16 4.37 4.36 Gerphil Renewable Energy, Inc. 0.22 0.22 Therma South Inc. 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 FDC MISAMIS (Phividec Coal) 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 Therma Marine Inc.
Recommended publications
  • Download 3.54 MB
    Initial Environmental Examination March 2020 PHI: Integrated Natural Resources and Environment Management Project Rehabilitation of Barangay Buyot Access Road in Don Carlos, Region X Prepared by the Municipality of Don Carlos, Province of Bukidnon for the Asian Development Bank. CURRENCY EQUIVALENTS (As of 3 February 2020) The date of the currency equivalents must be within 2 months from the date on the cover. Currency unit – peso (PhP) PhP 1.00 = $ 0.01965 $1.00 = PhP 50.8855 ABBREVIATIONS ADB Asian Development Bank BDC Barangay Development Council BDF Barangay Development Fund BMS Biodiversity Monitoring System BOD Biochemical Oxygen Demand BUFAI Buyot Farmers Association, Inc. CBD Central Business District CBFMA Community-Based Forest Management Agreement CBMS Community-Based Monitoring System CENRO Community Environmental and Natural Resources Office CLUP Comprehensive Land Use Plan CNC Certificate of Non-Coverage COE Council of Elders CRMF Community Resource Management Framework CSC Certificate of Stewardship Contract CSO Civil Society Organization CVO Civilian Voluntary Officer DCPC Don Carlos Polytechnic College DED Detailed Engineering Design DENR Department of Environment and Natural Resources DO Dissolved Oxygen DOST Department of Science and Technology ECA Environmentally Critical Area ECC Environmental Compliance Certificate ECP Environmentally Critical Project EIAMMP Environmental Impact Assessment Management and Monitoring Plan EMB Environmental Management Bureau EMP Environmental Management Plan ESS Environmental Safeguards
    [Show full text]
  • Conflict, Cooperation, and Collective Action: Land Use, Water Rights, and Water Scarcity in Manupali Watershed, Southern Philippines
    CAPRi Working Paper No. 104 February 2012 CONFLICT, COOPERATION, AND COLLECTIVE ACTION Land Use, Water Rights, and Water Scarcity in Manupali Watershed, Southern Philippines Caroline Piñon, World Agroforestry Centre (ICRAF-Philippines) Delia Catacutan, World Agroforestry Centre (ICRAF-Nairobi) Beria Leimona, World Agroforestry Centre (ICRAF-Indonesia) Emma Abasolo, World Agroforestry Centre (ICRAF-Philippines) Meine van-Noordwijk, World Agroforestry Centre (ICRAF-Indonesia) Lydia Tiongco, Department of Environment and Natural Resources (DENR-X) Presented at the International Workshop on Collective Action, Property Rights, and Conflict in Natural Resources Management, June 28th to July 1st 2010, Siem Reap, Cambodia CGIAR Systemwide Program on Collective Action and Property Rights (CAPRi) C/- International Food Policy Research Institute, 2033 K Street NW, Washington, DC 20006-1002 USA T +1 202.862.5600 • F +1 202.467.4439 • www.capri.cgiar.org The CGIAR Systemwide Program on Collective Action and Property Rights (CAPRi) is an initiative of the 15 centers of the Consultative Group on International Agricultural Research (CGIAR). The initiative promotes comparative research on the role of property rights and collective action institutions in shaping the efficiency, sustainability, and equity of natural resource systems. CAPRi’s Secretariat is hosted within the Environment and Production Technology Division (EPTD) of the International Food Policy Research Institute (IFPRI). CAPRi receives support from the Governments of Norway, Italy and the World Bank. CAPRi Working Papers contain preliminary material and research results. They are circulated prior to a full peer review to stimulate discussion and critical comment. It is expected that most working papers will eventually be published in some other form and that their content may also be revised.
    [Show full text]
  • NO. TENEMENT ID TENEMENT HOLDER DATE DATE AREA (Has
    Annex "B" MINING TENEMENT STATISTICS REPORT AS OF MARCH 2019 MGB REGIONAL OFFICE NO. X MINERAL PRODUCTION SHARING AGREEMENT (MPSA) I. Approved and Registered NO. TENEMENT ID TENEMENT HOLDER DATE DATE LOCATION AREA (has.) COMMODITY PREVIOUS STATUS/REMARKS FILED APPROVED Barangay Mun./'City Province HOLDER 1 MPSA - 039-96-X Holcim Resources and Development 8/3/1993 4/1/1996 Poblacion Lugait Misamis Oriental 129.6974 Shale Alsons Cement * On final rehabilitation. Corporation Corporation * Assigned to HRDC effective January 18, 2016. * Order of Approval registered on June 07, 2016. 2 MPSA - 031-95-XII Mindanao Portland Cement Corp. 4/29/1991 12/26/1995 Kiwalan Iligan City Lanao del Norte 323.0953 Limestone/Shale None * Corporate name changed to Republic Cement Iligan, Inc. (changed management to Lafarge Kalubihan * Officially recognized by MGB-X in its letter of March 9, 2016. Mindanao, Inc. and to Republic Cement Taguibo Mindanao, Inc.) 3 MPSA - 047-96-XII Holcim Resources and Development 8/21/1995 7/18/1996 Talacogon Iligan City Lanao del Norte 397.68 Limestone/Shale Alsons Cement * Assigned to HRDC effective January 18, 2016. Corporation Dalipuga Corporation * Order of Approval registered on June 07, 2016. - Lugait Misamis Oriental 4 MPSA-104-98-XII Iligan Cement Corporation 9/10/1991 2/23/1998 Sta Felomina Iligan City Lanao del Norte 519.09 Limestone/Shale None * Corporate name changed to Republic Cement Iligan, Inc. (changed management to Lafarge Bunawan * Officially recognized by MGB-X in its letter of March 9, 2016. Iligan, Inc. and to Republic Cement Kiwalan Iligan, Inc.) 5 MPSA - 105-98-XII MCCI Corporation 6/18/1991 2/23/1998 Kiwalan Iligan City Lanao del Norte and 26.7867 Limestone Maria Cristina * Existing but operation is suspended.
    [Show full text]
  • Integrated Natural Resources and Environmental Management Project Rehabilitation and Improvement of Liguron Access Road in Talakag, Bukidnon
    Initial Environmental Examination January 2018 PHI: Integrated Natural Resources and Environmental Management Project Rehabilitation and Improvement of Liguron Access Road in Talakag, Bukidnon Prepared by Municipality of Talakag, Province of Bukidnon for the Asian Development Bank. i CURRENCY EQUIVALENTS (as of 30 November 2017 Year) The date of the currency equivalents must be within 2 months from the date on the cover. Currency unit – peso (PhP) PhP 1.00 = $ 0.01986 $1.00 = PhP 50.34 ABBREVIATIONS ADB Asian Development Bank BDC Barangay Development Council BUB Bottom-Up Budgeting CDORB Cagayan De Oro River Basin CNC Certificate of Non-Coverage CSC Construction Supervision Consultant CSO Civil Society Organization DED Detail Engineering Design DENR Department of Environment And Natural Resources DILG Department of Interior and Local Government DSWD Department of Social Welfare and Development ECA Environmentally Critical Area ECC Environmental Compliance Certificate ECP Environmentally Critical Project EHSM Environmental Health and Safety Manager EIA Environmental Impact Assessment EIS Environmental Impact Statement EMB Environmental Management Bureau ESS Environmental Safeguards Specialist GAD Gender and Development IEE Initial Environmental Examination INREMP Integrated Natural Resources and Environment Management Project IP Indigenous People IROW Infrastructure Right of Way LIDASAFA Liguron-Dagundalahon-Sagaran Farmers Association LGU Local Government Unit LPRAT Local Poverty Reduction Action Team MKaRNP Mt. Kalatungan Range Natural
    [Show full text]
  • The Indigenous Peoples of Mt. Kitanglad Range Natural Park
    Case study The Indigenous Peoples of Mt. Kitanglad Range Natural Park Ma. Easterluna Luz S. Canoy and Vellorimo J. Suminguit Ancestral home The Mt. Kitanglad Range Natural Park (MKRNP) in north- central Mindanao is home to three non-Christian and non- Muslim indigenous groups who refer to themselves as Talaandigs, Higaonons and Bukidnons. These indigenous inhabitants are known collectively as Bukidnon, a Bisayan word for “people from the mountain,” and they share a common culture and a common language, the Binukid. According to Talaandig tradition, most of Bukidnon was the land of the Talaandig, the people of the slopes (andig). When the coastal dwellers moved to the uplands, the Talaandig referred to them as “Higaonon” because the latter came from down the shore (higa). The Higaonon claim that their ancestors were coastal dwellers and were the original inhabitants of Misamis Oriental. However, the arrival of the dumagat (people from over the sea) during the Spanish times encouraged the natives to move up to the plateaus or uplands, which now belong mostly to Bukidnon province. The Higaonon today occupy communities north of Malaybalay down to the province of Misamis Oriental, while Talaandigs live in communities south of Malaybalay, around Lantapan and Talakag (Suminguit et al. 2001). According to tradition, as recounted in an epic tale called the olaging (a story chanted or narrated for hours), a common ancestor and powerful datu (chieftain) named Agbibilin sired four sons who became the ancestors of the present-day Manobo, Talaandig, Maranao, and Maguindanao. Tribal legend has it that Agbibilin named the mountain Kitanglad, from tanglad (lemon grass), a medicinal plant that was associated with the visible portion of the peak left when the mountain was almost submerged during the Great Deluge.
    [Show full text]
  • (CSHP) DOLE-Regional Office No. 10 July 2018
    REGIONAL REPORT ON THE APPROVED/CONCURRED CONSTRUCTION SAFETY & HEALTH PROGRAM (CSHP) DOLE-Regional Office No. 10 July 2018 Date No. Company Name and Address Project Name Project Owner Approved L-BETHS CONSTRUCTION CONSTRUCTION OF BENCH FLUMES AND CANAL National Irrigation 1 July 01, Upper Bontong, Camaman-an, STRUCTURES OF BULOD COMMUNAL IRRIGATION SYSTEM Administration Region-x, 2018 Cagayan de Oro City CHB ADDITIONAL Lamisa Imo ERIANE CONSTRUCTION & 2 SUPPLY CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE V, LGU-VALENCIA CITY, July 02, 2nd Floor, P & E Building, BARANGAY SAN ISIDRO BUKIDNON 2018 Valencia City WDC BUILDERS & SUPPLIES 3 CONSTRUCTION OF DRAINAGE ALONG PACLAR STREET, Patag, Cagayan De Oro July 02, Z-5, B-18, L-20 Cilrai, Puntod, PATAG; SN: 53-2018 City 2018 Cagayan De Oro City ZI 9 BUILDERS & SUPPLIES REHABILITATION OF MUNICIPAL STREETS (DECOLORES 4 Poblacion Pangantucan, July 02, L-32, B-8, BHP3, Casisang, VILLAGE ALONG LUBI ST., FRM JCT. DURIAN ST., TO JCT Bukidnon 2018 Malaybalay City PAPAYA ST.) ZI 9 BUILDERS & SUPPLIES REHABILITATION OF MUNICIPAL STREETS (BAGONG BUHAY 5 July 02, L-32, B-8, BHP3, Casisang, VILLAGE ALONG ONTEJO ST., FRM JCT. M. ONTEJO ST., TO Pangantucan, Bukidnon 2018 Malaybalay City PROPOSED NATIONAL HIGHWAY ZI 9 BUILDERS & SUPPLIES INSTALLATION OF COUNTER, CABINETS & COMPLETION OF Capitol Compound, 6 July 02, L-32, B-8, BHP3, Casisang, TILE WORKS AT PTO & REPLACEMENT OF ROTTEN CEILING Malaybalay City, 2018 Malaybalay City AT PSWDO Bukidnon ZI 9 BUILDERS & SUPPLIES Capitol Compound, 7 July 02, L-32,
    [Show full text]
  • Order, ERC Case No. 2016-099 RC
    ~Q>\itATORf? c} O~~ 'I~~~~l:'ejvcr(\ Republic of the Philippines •., . ~()~Ci;l'ii ENERGY REGULATORYCOMMISSIO ,,,' c" ":J c .:. \'fI',"Mrc,~\W,!Jh San Migllel Avenue, Pasig City ,', <:J...:--- , IN THE MATTER OF THE JOINT APPLICATION FOR THE APPROVAL. OF THE ELECTRICITY SUPPLY. AGREEMENT ENTERED INTO BY AND BEllNEEN BUKIDNON SECOND ELECTRIC COOPERATIVE, INC. (BUSECO) AND SUNASIA ENERGY INC., WITH PRAYER FOR THE ISSUANCE OF PROVISIONAL AUTHORITY ERC CASE NO. 2016-099 RC BUKIDNQN SECQND ELECTRIC COOPERATIVE, INC. (BUSECO) AND SUNASIA DOCKE'rED Date';" iJU~IL:h.•••••••••••••••••1 2016_~ ENERGY INC., 8.1":,;..... • ...........•._, Applicants. "- - - - - - - - - - - - - - - - - - - - - - - - " ORDER On 29 April 2016, the Bukidnon Second Electric Cooperative, Inc. (BUSECO) and SunAsia Energy Inc. (SunAsia) filed a Joint Application for approval of the electricity supply agreement, with prayer for the issuance of provisional authority. In the. said Application, BUSECO and SunAsia alleged the following: 1. This Joint Application is respectfully submitted to the Honorable Commission for due consideration and approval of the Electricity Supply Agreement (ESA) executed by and between BUSECO and SunAsia pursuant to Rule 20(B) of the Energy Regulatory. Commission's Rules of Practice and Procedure approved by this Honorable Commission on 22 June 2006 in Resolution No. 38 Series of 2005 (ERC Rules) and other relevant rul~~~a~gulations. A copy of the ESA is ,tt"h,d" Annex"A/{ , ERC Case No. 2016-099 RC Order/12 July 2016 Page 2 of 17 THE APPLICANTS 2. BUSECO is a non-stock, non-profit membership electric cooperative duly organized and existing under and by virtue of the laws of the Republic of the Philippines with principal office address at the Municipality of Manolo Fortich, Province of Bukidnon.
    [Show full text]
  • Province of Bukidnon
    Department of Environment and Natural Resources MINES & GEOSCIENCES BUREAU Regional Office No. X Macabalan, Cagayan de Oro City DIRECTORY OF PRODUCING MINES AND QUARRIES IN REGION 10 CALENDAR YEAR 2017 PROVINCE OF BUKIDNON Head Office Mine Site Mine Site Municipality/ Head Office Mailing Head Office Fax Head Office E- Head Office Mine Site Mailing Mine Site Type of Date Date of Area Municipality, Year Region Mineral Province Commodity Contractor Operator Managing Official Position Telephone Telephone Email Permit Number Barangay Status TIN City Address No. mail Address Website Address Fax Permit Approved Expirtion (has.) Province No. No. Address Commercial Sand and Gravel San Isidro, Valencia San Isidro, Valencia CSAG-2001-17- Valencia City, Non-Metallic Bukidnon Valencia City Sand and Gravel Abejuela, Jude Abejuela, Jude Permit Holder City 0926-809-1228 City 24 Bukidnon Operational 2017 10 CSAG 12-Jul-17 12-Jul-18 1 ha. San Isidro Manolo Manolo JVAC & Damilag, Manolo fedemata@ya Sabangan, Dalirig, CSAG-2015-17- Fortich, 931-311- 2017 10 Non-Metallic Bukidnon Fortich Sand and Gravel VENRAY Abella, Fe D. Abella, Fe D. Permit Holder Fortich, Bukidnon 0905-172-8446 hoo.com Manolo Fortich CSAG 40 02-Aug-17 02-Aug-18 1 ha. Dalirig Bukidnon Operational 431 Nabag-o, Valencia agbayanioscar Nabag-o, Valencia Valencia City, 495-913- 2017 10 Non-Metallic Bukidnon Valencia City Sand and Gravel Agbayani, Oscar B. Agbayani, Oscar B. Permit Holder City 0926-177-3832 [email protected] City CSAG CSAG-2017-09 08-Aug-17 08-Aug-18 2 has. Nabag-o Bukidnon Operational 536 Old Nongnongan, Don Old Nongnongan, Don CSAG-2006- Don Carlos, 2017 10 Non-Metallic Bukidnon Don Carlos Sand and Gravel UBI Davao City Alagao, Consolacion Alagao, Consolacion Permit Holder Calrlos Carlos CSAG 1750 11-Oct-17 11-Oct-18 1 ha.
    [Show full text]
  • DA-Normin's P6.2-M Agri-Interventions to Boost Farm
    DA-NorMin’s P6.2-M agri-interventions to boost farm productivity DALWANGAN, MALAYBALAY CITY, BUKIDNON, May 21- The Department of Agriculture in Northern Mindanao (DA- 10) turned over P6.2 million agricultural interventions to farmer organizations and a local government unit in Bukidnon. Under the DA-Special Area for Agricultural Development (DA-SAAD) machineries and equipment worth P5.9 million aims to help improve productivity and reduce poverty among the marginalized sectors in agriculture. The local government of Talakag, Bukidnon received three units 35 horsepower mini four-wheel drive farm tractors with implements and two units corn mechanical sheller amounting P3.2 million. The Upper Patag Growers and Farmers Associations, Inc. of Lantapan, Bukidnon received one unit rice combine harvester, one unit 35 horsepower four-wheel drive farm tractors with implements which include rotavator and trailer amounting P2.6 million. “The need to increase the level of farm mechanization, to produce more food efficiency and quality will be beneficial both for farmers and consumers,” said Carlene C. Collado, OIC-Regional Executive Director of DA-10. RED Collado explained, farm machinery will boost farming activities and ensure high production and reduce postharvest losses. DA-Philippine Center for Postharvest Development and Mechanization (DA-PhilMech) reported that postharvest losses for corn accounts to 7.18 percent and 16.47 percent for rice, from harvesting, piling, hauling, shelling, drying and storage. He has been emphasizing the need for farmers to adopt the different agri-machinery and equipment innovations to increase the country’s mechanization rate from 2.31 horsepower per hectare to 4 hp per hectare.
    [Show full text]
  • 2016 X Lanao Del Norte Lake Lanao WPDP Lanao Del Sur Tugaya Talao II 50 Lumbac Farmers Association Falcata Timber Reforestation Proetcted Area
    ***Data is based on submitted maps per region as of April 2018. NAME OF SITECODE YEAR REGION PENRO CENRO PROVINCE MUNICIPALITY BARANGAY DISTRICT AREA IN HECTARES SPECIES COMMODITY COMPONENT TENURE ORGANIZATION 16-100000-0002-0050 2016 X Lanao del Norte Lake Lanao WPDP Lanao del Sur Tugaya Talao II 50 Lumbac Farmers Association Falcata Timber Reforestation Proetcted Area 16-103508-0004-0060 2016 X Lanao del Norte Kolambugan Lanao del Norte Munai Ramain II 60 BLGU of Balintad Falcata Timber Reforestation Untenured LGU of Barangay Lower 16-103508-0012-0070 2016 X Lanao del Norte Kolambugan Lanao del Norte Magsaysay Lower Caningag I 70 Falcata Timber Reforestation Untenured Caningag Lanao del Norte Cassava 16-103508-0010-0070 2016 X Lanao del Norte Kolambugan Lanao del Norte Magsaysay Lower Caningag I 70 Falcata Timber Reforestation Untenured Farmers Association Panansalan Dagumbaan 16-101304-0025-0050 2016 X Bukidnon Don Carlos Bukidnon Maramag Dagumbaan III 50 Talaandig Tribal Asso. Falcata Timber Reforestation (PADATTA), Inc. Nagkahiusa Gagmay Mag uuma 16-104300-0001-0085 2016 X Misamis Oriental Mt. Balatukan PAO Misamis Oriental Talisayan Macopa I 85 Falcata TIMBER REFO Protected area Association Incorporated San Isidro Medina Upland 16-104300-0002-0096 2016 X Misamis Oriental Mt. Balatukan PAO Misamis Oriental Gingoog Sitio Dagalas, Pigsalohan I 96 Planters Association Falcata TIMBER REFO Protected area (SIMUPA) Nagkasabwa Higaonon Lumad 16-104300-0003-0096 2016 X Misamis Oriental Mt. Balatukan PAO Misamis Oriental Medina San Roque I 96 Falcata TIMBER REFO Protected area Dini ta Misamis Oiental Blooming Forest Workers 16-104300-0005-0096 2016 X Misamis Oriental Mt.
    [Show full text]
  • BRIEF ASSESSMENT of CAGAYAN DE ORO RIVER BASIN Presentation Outline
    BRIEF ASSESSMENT OF CAGAYAN DE ORO RIVER BASIN Presentation Outline • Basic Information of Cagayan de Oro River Basin Thematic maps Rainfall Information • Major Flooding 2009 (Action taken) 2011 (Action taken) • Recommendations/Action Plan Bubunawan river Tumalaong river CAGAYAN DE ORO RIVER BASIN 137,933.77 HAS. Cagayan de Oro River Basin Political Map & Drainage System The existing rivers and creeks which are tributaries of Cagayan de Oro River that flows and discharges into Macajalar Bay is named as CAGAYAN DE ORO RIVER Cagayan de Oro BASIN with a total land area 10,365.73 of 137,933.77 hectares Libona Location Map 8,130.33 Baungon 23,971.56 Iligan City 15,678.39 Talakag 79,484.28 Bubong 244.91 Pangantucan 58.82 Rivers, Creeks, Road & Barangay Map The entire Basin has 8 major rivers, within the 7 municipalities : Talakag, Baungon, Libona, and Pangantucan of Bukidnon; Iligan City of Lanao del Norte; Municipality of Bubong of Lanao del Sur,ARMM; and Cagayan de Oro City, which are composed with 122 barangays 8 SUBWATERSHEDS OF CDO RIVER BASIN Bubunawan, Cagayan de Oro Rivers (26,875.89 has.) Tumalaong, Samalawan Rivers (13,352.12 has.) Tagiti River (9,255.24 has.) Kalawaig, Tutoban, Minontay Rivers (19,382.66 has. ) Batang, Banongcol, Baylanan, Sangaya, Sagayan Rivers (31,598.07 has.) Tikalaan, Picalin Rivers (7,527.20 has.) Pigcotin, Bulaong Rivers (24,438.30 has.) Munigui River (5,504.29 has.) Sub -Watershed Areas of Cagayan de Oro River Basin Timberland Area Sub -Watershed Length of Rivers & Sub-Watersheds Location within Sub- Area Tributaries (Km) watershed 1.
    [Show full text]
  • General Description of the Manupali Watershed, Bukidnon
    Mainstreaming Climate Change Adaptation in Watershed Management and Upland Farming in the Philippines Draft Final Report Florencia B. Pulhin 1, Rodel D. Lasco2, Ma. Victoria O. Espaldon3 and Dixon T. Gevana4 1 Forestry Development Center, College of Forestry and Natural Resources, University of the Philippines Los Banos 2 World Agroforestry Centre, 2nd Floor Khush Hall, IRRI 3School of Environmental Science and Management, University of the Philippines Los Banos 4 Environmental Forestry Programme, College of Forestry and Natural Resources, University of the Philippines Los Banos I. Introduction Being an archipelagic developing country composed of more than 7000 small islands, the Philippines is highly vulnerable to the impacts of climate related events such as tropical cyclones and ENSO. The Philippines is always battered by typhoons because it is geographically located in a typhoon belt area. Based on the 59 year period (1948- 2006), annual average number of typhoons occurring within the Philippine Area of Responsibility (PAR) is around 19 to 20 (PAGASA, 2007). During the last two decades, an increasing trend on the number of strong typhoons (> 185 kph wind speed) hitting the Philippines has been observed. From 1990-1998, a total of seven strong typhoons have crossed the country (NDCC, 2000 and Typhoon 2000.com). Damages from these typhoons are staggering. They not only caused damage to properties but also claimed the lives of people. For instance, typhoon “Uring” (Thelma) which made a landfall in November 1991 caused the death of around 5101-8000 people and damaged properties amounting to PhP 1.045 billion. Typhoons ‘Ruping” (Mike) and “Rosing” (Angela) caused damage to properties of almost PhP 11B each.
    [Show full text]