API C2 / SC 17 SUBCOMMITTEE ON SUBSEA PRODUCTION SYSTEMS

API 17E SPECIFICATION for SUBSEA UMBILICALS REVISION TASK GROUP STATUS

JANUARY 19, 2012 API 17E - SUBSEA UMBILICALS WINTER MEETING STATUS REPORT API 17E - SUBSEA UMBILICALS WINTER MEETING STATUS REPORT

1. INTRODUCTION

The Subsea Umbilical Specification was adopted back as the Fourth Edition of API 17E on October 2010 with an effective date of April 1, 2011. The API TG, from the start, intended to begin the revision process soon after publication. On April 19, 2011 an SRRR form was submitted to API with a planned completion date of May 16, 2012.

2. STATUS

Reviewed API clarification matrix from the DIS/FDIS where we confirmed it would be looked at in the next Revision has been made. Final resolution of agreed upon comments are in process.

The Umbilical Manufacturers Federation (UMF) has submitted comments for TG review and action. The steel tube suppliers, the fiber optic cable suppliers and the electric cable suppliers have commented to the existing specification and any clarifications are being reviewed. Note, most have confirmed no or very little clarification.

We started out like a ball of fire and then things went to hell in a hand basket. We are, however, back in the game.

3. MEMBERSHIP

Task Group

The working task group is made up of the following personnel:

TABLE 1-1: API 17E TASK GROUP MEMBERS

Name Company e-mail John McManus Aker Solutions [email protected] Katrina Clausing Shell International Exploration & Production [email protected] Chris Kassner Chevron [email protected] Teguh Inarsoyo BP [email protected] Dave Madden DUCO Inc. [email protected] Andre Chartier Oceaneering Umbilical Solutions [email protected]

-1- January 19, 2012 API 17E - SUBSEA UMBILICALS WINTER MEETING STATUS REPORT

Reader/Comment Group

The reader/comment group is made up of the following personnel:

1. Danny Weber Chevron 2. Mark Kurtz Chevron 3. Dustin Collier Chevron 4. Leo Caffrey Chevron 5. Lionel Fontenette ExxonMobil 6. Paul Donavan ExxonMobil 7. David Micheletti ExxonMobil 8. Jose Baca Andrade ExxonMobil 9. John Respess Marathon Oil 10. Godfried Dekeyser Deepsea QCI 11. Paul Shaw Alpha Petroleum 12. Jeremy Woulds Helix Energy 13. Jim Macklin Helix Energy 14. Stian Karlsen Nexans Norway 15. Lars Mehus Aker Solutions 16. Jeff Lami Aker Solutions 17. David Hickman Aker Solutions 18. Alva Davis Oceaneering Umbilical Solutions 19. Chris Jameson Oceaneering Umbilical Solutions 20. Joao Melo Oceaneering Umbilical Solutions 21. Derek Shackleton Oceaneering Umbilical Solutions 22. Fraser Thomson Oceaneering Umbilical Solutions 23. Joe Wong Oceaneering Umbilical Solutions 24. Ryan Hocevar Parker Cabett Subsea 25. Joe Dunbar Parker Cabett Subsea 26. John Brown DUCO Ltd. 27. Alan Dobson DUCO Ltd. 28. Martin Kokes Sandvik Materials Technology 29. Leandro Finzetto Sandvik Materials Technology 30. Dave O’Donnell RathGibson 31. John Sinks RathGibson 32. Ken Bertram Webco Industries 33. David Boyer Webco Industries 34. John Willhoite Tenaris 35. Bruce Reichert Tenaris 36. Robert Karlin Tenaris 37. Rod Brown INTECSEA 38. Amedo Marlotulli Pegasus International 39. Marsha Carlstrom Pegasus International 40. Ryan Romero Deep Trend Inc. 41. Steve Mansfield J P Kenny 42. Dave Robson Technip 43. Geoff Moody Technip 44. Vincent Ledoux Technip 45. Jean François Saint Marcoux Paragon Engineering 46. Darrel Evans Stolt Offshore

-2- January 19, 2012 API 17E - SUBSEA UMBILICALS WINTER MEETING STATUS REPORT

47. Norb Gorman Oceaneering International 48. Sandy Fraser Subsea 7 49. Knut Ivar Ekeberg ultradeep

4. UPDATED TARGET DATES FOR DELIVERABLES

Table 4-1 shows the new proposed milestone targets:

TABLE 4-1: MILESTONE TARGET DATES Milestone Targets Proposed Completion Date

SRRR Form Submitted April 19, 2011 – Completed

TG Kick-off Meeting June 10, 2011 – Completed

Publication of API/ISO Revised Standard May 2013

5. MAJOR ISSUES

None at this time

6. ANTICAPTED NEW WORK ITEMS

None at this time

7. PLANS FOR FUTURE MEETINGS

Three TG meetings have been held. Monthly meetings, or sooner as required, will be held until completion.

8. RESOURCE NEEDS

None at this time

-3- January 19, 2012