SUMMARY 20 years of experience in Nuclear Planning and Scheduling, 6 years of experience in Fossil Plants Planning and Scheduling, and varied experience in Mechanical and Welding Supervision. Currently employed with ESG International contracted to Dominion Virginia Power at Surry Nuclear Power Plant in Surry, VA as a Controls Specialist. I am considered an expert in the Primavera Suretrack scheduling system. Additional Planning software experience includes: SAP, IBM CICS Mainframe CPU with Automated Management Maintenance System, IBM CICS Passport Mainframe; Network and Personal CPU's, and WPTS - Work Process Tracking System, and P3e scheduling system.

EDUCATION University of California, Los Angeles, California Completed 60 Hours

Los Angeles Technical Trade College, Los Angeles, California A.A.S. Certification (Welding, Drafting and Metallurgy)

WORK HISTORY

07/09/07 to Present Projects Planner DZ/Atlantic Group – Progress Energy CR3 , Crystal River , Fl. Responsible for total Planning effort for Engineering Change Modification Projects. Develop detailed instructions for work processes, specify and order replacement parts, identify required procedures, specifications, drawings, support group requirements, and post maintenance testing, and review completed work orders to verify completeness and accuracy prior to closure. Provide information for schedule updates as needed. Utilize IBM CICS/Passport mainframe, P3e, network, and personal computers.

07/10/06 to 05/31/07 Controls Specialist Energy Services Group - Dominion Power, Surry Power Station, Surry Va. Responsible for total Planning/Scheduling effort for NRC-GSI-191 (Containment Sump Mod.) project and other DCP Modifications. Develop detailed instructions for work processes, specify and order replacement parts, identify required procedures, specifications, drawings, support group requirements, and post maintenance testing, and review completed work orders to verify completeness and accuracy prior to closure. Create schedules and update as needed, generate cost control summaries and update as required. Utilize IBM CICS/Passport mainframe, P3e, network, and personal computers. Alton E. Pressley Page 2 of 4

01/06 to 04/15/06 Reactor Pump Replacement Planner Adecco Technical – First Energy, Davis-Besse Nuclear Plant Oak Harbor, OH Responsible for total planning effort for Reactor Coolant Pump Replacement. Develop detailed instructions for work processes, specify and order replacement parts, identify required procedures, specifications, drawings, support group requirements, and post maintenance testing, and review completed work orders to verify completeness and accuracy prior to closure. Utilize IBM CICS/Passport mainframe, network, and personal computers.

02/05 to 10/20/05 Reactor Head Replacement Planner Energy Services Group – Progress Energy, Robinson Nuclear Plant Hartsville, SC. Responsible for total planning effort for Reactor Vessel Closure Head Replacement. Develop detailed instructions for work processes, specify and order replacement parts, identify required procedures, specifications, drawings, support group requirements, and post maintenance testing, and review completed work orders to verify completeness and accuracy prior to closure. Utilize IBM CICS/Passport mainframe, network, and personal computers.

10/04 to 02/05 Security Modification Planner Energy Services Group – Progress Energy, Robinson Nuclear Plant Hartsville, SC. Responsible for walkdown and preparation of mechanical and electrical work packages for Engineering Changes for Security Modifications as required by the Nuclear Regulatory Commission for the latest Security Updates. Develop detailed instructions for work processes, specify and order replacement parts, identify required procedures, specifications, drawings, support group requirements, and post maintenance testing, and review completed work orders to verify completeness and accuracy prior to closure. Utilize IBM CICS/Passport mainframe, network, and personal computers.

03/99 – 05/04 Outage Maintenance Scheduler/Planner Energy Services Group – Dominion Virginia Power, Chesterfield Power Station, Bremo Power Station, & Yorktown Power Station Responsible for total maintenance and refit outage scheduling efforts at all three stations simultaneously. Maintain tracking and updating of all schedules utilizing Primavera P-3 Systems. Train Dominion outage personnel in use of Primavera Suretrack scheduling system at all stations. Plan outage work orders; procure and expedite required materials. Assemble work packages, generate weld and code weld packages and weld maps. Generate and update outage cost business plans for each station. Perform Scheduling Consultant role to Clover Power Station and Mount Storm Power Station (both Dominion Virginia Power stations) during this time.

01/98 – 03/99 Outage Mechanical/Structural/Electrical Maintenance Planner Energy Services Group - Virginia Power, Surry Nuclear Power Station, Surry, VA Responsible for assembling corrective maintenance work orders, including plant walkdowns, ordering spare parts, and identifying required procedures, drawings, specifications and post maintenance testing. Utilize IBM CICS mainframe computer with Automated Maintenance Management System. Alton E. Pressley Page 3 of 4

09/97 - 11/97 Project Assistant The Atlantic Group - Virginia Power, Surry Nuclear Power Station, Surry, Virginia Responsibilities include assisting first line Supervisors in coordinating and executing their work, tracking work schedules to remove any barriers prior to task performance including but not limited to safety issues, Procedure Action Requests, System windows, SQC equipment, task housekeeping, interfacing with other departments, and identifying and resolving issues before they impact the outage schedule.

05/96 - 09/97 Project Superintendent Press Construction, Talladega, Alabama Responsible for all phases of general construction and remodeling including removal, installation, disassembly and reassembly of above ground irrigation systems.

04/96 - 05/96 Heavy Lift Coordinator The Atlantic Group - Virginia Power, Surry Nuclear Power Station, Surry, Virginia Coordinate and observe all heavy lifts for the unit two refueling outage. Review and revise lifting/rigging procedures.

12/94 - 12/95 Heavy Lift Coordinator The Atlantic Group - Virginia Power, Surry Nuclear Power Station, Surry Virginia Coordinate and observe all heavy lifts for the station. Review and revise lifting/rigging procedures. Identify all rigging/lifting requirements in the Work Order Backlog. Review INPO and NUCNET reports for lifting/rigging problems at other facilities. Perform daily surveillance for rigging/lifting concerns. Identified all components that required weight permanently indicated by Engineering for craft personnel. Identify all lifting points and I-beams that require maximum weight capacity identification. Perform safety self-assessments for the Safety Department.

03/94 - 12/94 Outage Mechanical/Structural Maintenance Planner Energy Services Group - CP&L, Brunswick Nuclear Station, Southport, North Carolina One month break in service in July 1994. Returned in August 1994 for Work Order Backlog reduction effort. Assemble corrective maintenance work orders, perform plant walkdowns, order spare parts, identify required procedures, drawings, specifications and post maintenance testing. Utilize IBM CICS mainframe computer with Automated Maintenance Management System.

04/93 - 03/94 Electrical/Mechanical Planner The Atlantic Group - Virginia Power, Surry Nuclear Power Station, Surry, Virginia Responsible for walkdown and preparation of mechanical and electrical Design Change Packages and Engineering Work Requests as required by Nuclear Site Services. Develop detailed instructions for work processes, specify and order replacement parts, identify required procedures, specifications, drawings, support group requirements, and post maintenance testing, and reviewed completed work orders to verify completeness and accuracy prior to closure. Utilize IBM CICS/Passport mainframe, network, and personal computers. Alton E. Pressley Page 4 of 4

09/92 - 02/93 Mechanical/Structural/Maintenance Planner General Physics Corporation - CP&L, Brunswick Nuclear, Southport, North Carolina Responsible for assembling corrective maintenance work orders, including plant walkdown, order spare parts, identify required procedures, drawings, specifications and post maintenance testing. Utilize IBM CICS mainframe computer with Automated Maintenance Management System.

09/86 - 05/92 Mechanical and Electrical Maintenance Planner The Atlantic Group - Virginia Power, Surry Nuclear Power Station, Surry, Virginia Responsible for walkdown and preparation of mechanical and electrical corrective and preventive maintenance work orders, develop detailed instructions for work processes, specify and order replacement parts, identify required procedures, specifications, drawings, support group requirements, and post maintenance testing, create and revise model work orders and review completed work orders to verify completeness and accuracy prior to closure. For two years of this time period was the sole planner on night shift handling all maintenance problems for all disciplines including welding and instrumentation. Utilize IBM Mainframe, Network, personal computers and Data General Mainframe computers. From 1988 - 1992, job duties included planning and implementing corrective/preventative maintenance and inspections on all cranes at Surry.

09/84 - 09/86 Senior Mechanical Construction Specialist/Construction Coordinator Daniel Corporation - Virginia Power, Surry Nuclear Power Station, Surry, Virginia Responsible for the mechanical disciplines from an engineering level, including but not limited to demolition, renovation, new construction coordination, materials and material problems, all mechanical discipline field problems, review of drawings, procedures, design change packages and specifications. While coordinating the Laundry Facility, job duties included coordinating all lifting and rigging. As Construction Engineer was responsible for the replacement of feedwater heaters for Unit 2. Co-designed lifting A-frame for Turbine building crane and coordinated rigging.

07/84 - 09/84 Mechanical General Foreman Daniel Corporation - Dayton Power & Light Fossil Fuel Plant, Manchester, Ohio Supervise fabrication and installation of vacuum piping system and boiler rework.

05/83 - 03/84 Construction Engineer III Group Lead Daniel Corporation - KC&E/KCP&L, Wolf Creek Nuclear Project, New Strawn, Kansas

05/81 - 05/83 Mechanical Superintendent Daniel Corporation - KC&E/KCP&L, Wolf Creek Nuclear Project, New Strawn, Kansas

09/78 - 05/81 Maintenance Mechanical General Foreman/Pipe Superintendent Steam Generator Replacement Daniel Corporation - Virginia Power, Surry Nuclear Power Station, Surry, Virginia Supervise pipefitters and welders engaged in the removal and reinstallation of piping systems associated with the removal and replacement of the steam generators.