Wisdot DTSD, NE Region March 2008 Solictation Number NE 01
Total Page:16
File Type:pdf, Size:1020Kb
Ashwaubenon (920) 492-2905 ext. SCHOOL DISTRICT Fax: (920) 492-2911 1055 GRIFFITHS LANE @ashwaubenon.k12.wi.us ASHWAUBENON WI 54304-5599 www.ashwaubenon.k12.wi.us
Scope of Services Narrative
Transportation Region/Bureau Solicitation Number Project ID Northeast Region Ashwaubenon School 01 9266-10-00
Solicitation Type (Roster or Open) SOLICITATION DATE NOI DUE DATE Roster April 26, 2011 May 31, 2011, 3 p.m.
Location/Description Ashwaubenon School District 1055 Griffiths Lane Ashwaubenon, WI 54304 Brown County
Local selection? No Anticipated Construction Cost: $120,000 Anticipated Project Start Date: June, 2013 Anticipated Completion Date: August, 2013
Project purpose and need The purpose of this project is to improve pedestrian and bicycle safety in the Village of Ashwaubenon including training and special enforcement activities.
Project description The proposed improvements will be to construct a multi use path and student drop off area along Marvelle Lane to the north of the school, reconfigure the front driveway of the school along True Lane, widen a path from Orrie Lane west of the school and install new bicycle pads and racks for bicycle parking.
Deliverables Consultant is expected to complete environmental analysis and documentation, design reports, utility coordination, all agency coordination, preliminary and final plat, preliminary and final design, final plan and PS&E documents all in accordance with the Sponsors Guide to Non-Traditional transportation Project Implementation. The consultant will be expected to complete construction/engineering services under a separate construction project number
Schedule for deliverables Environmental Document submitted September 2011 Right of way plat due November 1, 2011 PS&E package submitted to NE Region for review: April 1, 2012 PS&E date: August 1, 2012 Letting date: November 25th, 2012 Construction Engineering Services to begin June, 2013
Page 1 of 3 Ashwaubenon (920) 492-2905 ext. SCHOOL DISTRICT Fax: (920) 492-2911 1055 GRIFFITHS LANE @ashwaubenon.k12.wi.us ASHWAUBENON WI 54304-5599 www.ashwaubenon.k12.wi.us
Department provides List of known utilities Horizontal and vertical control for surveys Existing right-of-way plats
Consultant requirements (listed in approximate rank order of importance) Familiarity with design criteria- WisDOT’s Facilities Development Manual, SRTS Manual, and the AASHTO Roadside Design Guide Knowledge of the PS&E Process Experience with SRTS design Experience with agency coordination Experience with project management Experience with the public involvement process Familiarity with WisDOT’s community sensitive design principals and the ability to work with the local communities
Special skills and expectations (listed in approximate rank order of importance) N/A
Interview dates No interview will be conducted.
Submit questions about this project to Tom Schmitt. Email to [email protected] by 3:00 pm of the Monday following the publication.
Page 2 of 3 Ashwaubenon (920) 492-2905 ext. SCHOOL DISTRICT Fax: (920) 492-2911 1055 GRIFFITHS LANE @ashwaubenon.k12.wi.us ASHWAUBENON WI 54304-5599 www.ashwaubenon.k12.wi.us
Instructions for consultants:
1. Complete the NOI portion, to a maximum of 8 pages, adhering to these guidelines: a. All submittals shall be in hard copy form, no electronic files will be submitted b. Submit only one (1) NOI per firm. Firms with multiple locations and/or parent companies may not submit more than one NOI. c. Additional comments may be added in narrative form after the tables in each question. d. General formatting: i. Do not add colors in the tables or to fonts. ii. This is a quality based selection, do not include any dollar values. iii. Limit font bolding to highlight only the most important words. Do not bold questions. iv. Use the Arial font, sized between 9-12 only. Only table labels should be font size 8. v. Using bullets within tables is allowed. vi. Limited table column size changing is allowed, but expanding tables is not. vii. Deleting unneeded tables from the default form is allowed. Do not delete any questions. viii. Leave at least two blank lines between information and the next question. e. Special instructions for NOI questions: i. Question 2—be sure to identify time period for availability. ii. Question 3—if reference is WisDOT employee, it is not necessary to list full street address.. f. Minimize the number and size of pictures inserted. g. Do not copy resumes or other external documents into the NOI form to supply firm qualifications. h. Automatic disqualification will occur if: i. Questions are deleted or changed. ii. The NOI response is longer than 8 pages. iii. Dollar values are included in the submittal
Page 3 of 3 Ashwaubenon (920) 492-2905 ext. SCHOOL DISTRICT Fax: (920) 492-2911 1055 GRIFFITHS LANE @ashwaubenon.k12.wi.us ASHWAUBENON WI 54304-5599 www.ashwaubenon.k12.wi.us
NOTICE OF INTEREST QUESTIONNAIRE
Transportation Region/Bureau Solicitation Number Project ID(s) Northeast Region Ashwaubenon School 9266-10-00 01 Solicitation Type (Roster or Open) SOLICITATION DATE NOI DUE DATE Roster April 11, 2011 May 31, 2011, 3 p.m.
Firm Name
Street Address Area Code - Telephone Number Area Code - FAX Number
City, State, ZIP Code Contact Person, E-Mail Address
Use only the format furnished; changes or deletion of questions or format may disqualify you from consideration. Limit your response to 8 pages.
1. List credentials, qualifications and years experience for the project manager and other key staff you would assign to this project in the following table. If showing more than two individuals, add tables using the format provided. Key subconsultants may be listed. Be sure to clearly identify the subconsulting firm.
POSITION/ YEARS REGISTRATION KEY STAFF EDUCATION PROJECT ROLE EXPERIENCE (PE, RLS, etc.)
Narrative
POSITION/ YEARS REGISTRATION KEY STAFF EDUCATION PROJECT ROLE EXPERIENCE (PE, RLS, etc.)
Narrative
2. Workload Capacity - Describe your staff's capacity, availability and their ability to perform the work in a timely manner relative to present workload. Address the availability of the named key staff members, including competing commitments and the percent of time available for this project. If showing more than four individuals, add rows to the table below. Key subconsultants may be listed.
CURRENT ESTIMATED KEY STAFF CURRENT COMMITMENTS AVAILABILITY BY TIME PERIOD Name Firm Location
Name Firm Location
3. List recently completed or substantially completed projects for each key staff/project manager and provide contact name for each project. Only show the deliverables for which key staff/project manager were responsible on the
Page 1 of 2 Ashwaubenon (920) 492-2905 ext. SCHOOL DISTRICT Fax: (920) 492-2911 1055 GRIFFITHS LANE @ashwaubenon.k12.wi.us ASHWAUBENON WI 54304-5599 www.ashwaubenon.k12.wi.us
project. If showing more than two projects, add tables using the format provided. Key subconsultants may be listed. Be sure to clearly identify the subconsulting firm.
Project Name Begin/End Service Dates Firm's Fees on Project Reference--Name, Address, Phone, E-mail
DELIVERABLES KEY STAFF Narrative
Project Name Begin/End Service Dates Firm's Fees on Project Reference--Name, Address, Phone, E-mail
DELIVERABLES KEY STAFF Narrative
4. If the projects listed in question 3 are not WIDOT projects, demonstrate your familiarity with WIDOT processes and procedures.
Narrative
5. For projects with a DBE subcontracting requirement, list the DBE firm/s you intend to use and describe their role(s). If more than two DBE firms are involved, add rows to the table below. Repeat DBE subconsultants listed in question #2.
ESTIMATED % FIRM NAME PROJECT ROLE(S) OF CONTRACT
6. In 100 words or less, note any other pertinent information about your firm's qualifications for the project.
Narrative
Page 2 of 2