J-K Capital Projects and Planning South Kensington campus London, SW7 2AZ TAKE OVER CERTIFICATE

Project Number Project Title Project Manager Location Employer Contractor Contract

Take Over Certificate TOC No.

This Certificate applies to the whole of the works/part(s) of the works (stated below) (delete as necessary)

Part(s) of the works (to be stated)

Events Day Month Year Planned Completion was

The take over date is

Completion was achieved on

The Completion Date is

The Defects Date is

The defects on the attached schedule (ref. No. ???) are to be corrected within the defect correction period which ends on

As detailed below:

Note: This is not a notification of a compensation event

Signed (Contractor) Date:

Issued to Contractor Project Manager Supervisor File Other

Reference: Date – 14/09/2010 F.39 – TAKE OVER CERTIFICATE X:\Building Projects\Administration\Administration\Documents - Masters\Process & Procedures\f39takeovercert.doc