Project handbook

Version 0.1 Project manager: Vorname Nachname Date:

Version: 2.9 10.5.2011 pma certification body 1/28 Content

1 Project plans...... 5 1.1 Project Assignment...... 5 1.2 Project Objectives (objectives, non-objectives)...... 6 1.3 Description of Pre- and Post Project Phase...... 7 1.4 Project Environment Analysis...... 8 1.5 Relationship to Other Projects and the Organisations´s Strategy...... 9 1.6 Project Organisation Chart...... 10 1.7 Plan of Objects of Consideration of the Project...... 11 1.8 Work Breakdown Structure (WBS)...... 12 1.9 Project Work-Package Specification...... 13 1.10 Project Responsibility Matrix...... 14 1.11 Milestoneplan...... 15 1.12 Project Bar Chart...... 16 1.13 Resource Plan...... 17 1.14 Project Cost Plan...... 18 1.15 Project Communication...... 19 1.16 Project „Rules“...... 20 1.17 Project Risk Analysis...... 21 1.18 Project Documentation...... 22

2 Project Start...... 23 2.1 Minutes– Project Start...... 23

3 Project Co-ordination...... 24 3.1 Approval of Work-packages...... 24 3.2 Minutes – Project Co-ordination...... 24

4 Project Controlling...... 25 4.1 Project Status Report...... 25 4.2 Additional Project Status Reports...... 26 4.3 Minutes – Project controlling...... 26

5 Project Close Down...... 27 5.1 Project Close Down Report...... 27 5.2 Minutes – Project Close Down...... 28

Version: 2.9 10.5.2011 pma certification body 2/28 Document versions

Versionno. Date Change Author

Version: 2.9 10.5.2011 pma certification body 3/28 Distribution list

Name Organisational Role in project Telephone E-mail Unit

Version: 2.9 10.5.2011 pma certification body 4/28 1 Project plans

1.1 Project Assignment

PROJECT- ASSIGNMENT

Project start event: Project start date:   project close down event in terms of Project close down dates: content:    Formal project close down event: 

Project objectives: Non-objectives:      

Main tasks (Project phases): Project resources and costs*:  resource/type of cost unit Costs (€)   

Project owner: Project manager:  

Project team members:    

, (Project owner) (Project manager)

* Possible categories of total Project budget: Category A: up to 0,3 million Euro Category B: up to 1 million Euro Category C: up to 10 million Euro Category D: mor than 10 million Euro

Version: 2.9 10.5.2011 pma certification body 5/28 1.2 Project Objectives (objectives, non-objectives)

PROJECT OBJECTIVES

Type of objective Project objectives Adjusted prroject objectives as of...

objectives:  Main   objectives 

  Additional objectives 

Non-objectives  

Version: 2.9 10.5.2011 pma certification body 6/28 1.3 Description of Pre- and Post Project Phase

DESCRIPTION OF PRE- AND POST- PROJECT PHASE

1) Pre-project phase

What triggered the project?    

Relevant douments for the project („Minutes“, … ONLY documents and no content necessary)    

Experience from similar projects    

2) Post-project phase

What will happen after the projet has ended? (follow-up activities, further projects, …)?    

Version: 2.9 10.5.2011 pma certification body 7/28 1.4 Project Environment Analysis

PROJECT ENVIRONMENT GRAPHIC

PROJECT ENVIRONMENT TABLE

Environment Relationship Measures Who / when (potential/conflict) PSP Code

Version: 2.9 10.5.2011 pma certification body 8/28 1.5 Relationship to Other Projects and the Organisations´s Strategy

RELATIONSHIP TO OTHER PROJECTS

Programs/ Relationship Sanctions Who / when Projects/ (potential/conflict) PSP Code

CONNECTION TO THE ORGANISATION´S STRATEGY

Strategy Description of connection/relationship

Version: 2.9 10.5.2011 pma certification body 9/28 1.6 Project Organisation Chart

PROJECT- ORGANISATION

Role in Project Field of duties/Skills Name Project owner

Project manager

Project team members

Project members

Version: 2.9 10.5.2011 pma certification body 10/28 1.7 Plan of Objects of Consideration of the Project

PLAN OF OBJECTS OF CONSIDERATION

Version: 2.9 10.5.2011 pma certification body 11/28 1.8 Work Breakdown Structure (WBS)

Version: 2.9 10.5.2011 pma certification body 12/28 1.9 Project Work-Package Specification

PROJECT WORK-PACKAGE SPECIFICATION

WBS-Code, WP Content (What shall be done?) WP Title     

Non-WP Content (What shall not be done? optional)     

WP Result (What is achieved after WP was finished?)     

Progress Measurement (How is progress measured?)     

Version: 2.9 10.5.2011 pma certification body 13/28 1.10 Project Responsibility Matrix

PROJECT- RESPONSIBILITY- MATRIX t r r r 1 2 3 4 5 1 2 3 h

e e e n Roles & Environment c r r r r r r r r e n n g a e e e e e e e t e a o w w s b b b b b b b b i n c o o

s a m m m m m m m m t s t t e e e e e e e c e c c a m

e

e e j t m m m m m m m m t j j

c c o t t t o o r e e r r c c c m m m m m j j P p P e e e a a a a a o o

j j j l r r e e e e e o o o t t t t t a P P r r r

t t t t t n P P P r c c c c c e e e e e e t j j j j j x o o o o o r r r r r E WBS-Code WP-Title P P P P P

1.1 Project management 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.1.7 1.2 Phase 2 1.2.1 1.2.2 1.2.3 1.2.4 1.2.5 1.2.6 1.2.7 1.3 Phase 3 1.3.1 1.3.2 1.3.3 1.3.4 1.3.5 1.3.6 1.3.7

Functions R …….Responsible C …….Contribution I ……..has to be informed

Version: 2.9 10.5.2011 pma certification body 14/28 1.11 Milestoneplan

MILESTONEPLAN

WBS- Milestone Plan date Revised date Actual date Code

*In order of plan dates.

Version: 2.9 10.5.2011 pma certification body 15/28 1.12 Project Bar Chart

Version: 2.9 10.5.2011 pma certification body 16/28 1.13 Resource Plan

Resource Plan

WBS- Phase/Work- Type of resource Planned Revised Actual Deviation Code package quantity quantity quantity (days) (days) (days) (days)

Version: 2.9 10.5.2011 pma certification body 17/28 1.14 Project Cost Plan

PROJECT COST PLAN

WBS-Code, Type of Cost Planned Revised Actual cost Deviation WP-Title cost cost  Personnel

 Material

 External services

 Other

Total

 Personnel

 Material

 Externalservices

 Other

Total

 Personnel

 Material

 External services

 Other

Total

Project cost

Version: 2.9 10.5.2011 pma certification body 18/28 1.15 Project Communication

PROJECT- COMMUNICATION

Title Objectives, Content Participants Schedule Location

Project owner meeting  project status Project owner,  decisions Project manager  acceptance of progress report

Project controlling  project status Project manager, meeting  controlling of tasks, Project team, schedule, resources, costs Project coach  controlling of project environments  social controlling  prepare proposal for decision

Subteam meeting  Coordination of subteams Subteam  Discussion of problems

Version: 2.9 10.5.2011 pma certification body 19/28 1.16 Project „Rules“

Version: 2.9 10.5.2011 pma certification body 20/28 1.17 Project Risk Analysis

PROJECT RISK ANALYSIS Cost for WBS- WBS- Risk- Benefit Risk- minimizing Code descripton description Priority /Cost Probability value Delay Avoidong action risk (Code) (Text) (Text) (Range) (iuro) (Percentage) (iuro) (iWeeks) (Text) (Euro)

Project total

Version: 2.9 10.5.2011 pma certification body 21/28 1.18 Project Documentation

Area Description File

Access Authorisation

Naming convention

Rules

Version: 2.9 10.5.2011 pma certification body 22/28 2 Project Start

2.1 Minutes– Project Start

2.1.1 Project Start Workshop

2.1.2 Follow-up Workshop

2.1.3 Project Owner Meeting

Version: 2.9 10.5.2011 pma certification body 23/28 3 Project Co-ordination

3.1 Approval of Work-packages APPROVAL OF WORK-PACKAGES

WBS- Work-package WP-Owner Date Approval by Signature Code

3.2 Minutes – Project Co-ordination

Version: 2.9 10.5.2011 pma certification body 24/28 4 Project Controlling

4.1 Project Status Report PROJECT STATUS REPORT as of ......

Project crisis 1) Overall Status:

Project in difficulties 

Project according to plan

2) Status Project objectives Activities:    

3) Status Project progress Activities:    

4) Status Schedule Activities:    

5) Status Resources/costs Activities:    

6) Status Context Activities:    

7) Status Organisation/culture Activities:    

Version: 2.9 10.5.2011 pma certification body 25/28 4.2 Additional Project Status Reports

4.3 Minutes – Project controlling

4.3.1 Project Controlling Meetings

4.3.2 Project Owner Meetings

Version: 2.9 10.5.2011 pma certification body 26/28 5 Project Close Down

5.1 Project Close Down Report

PROJECT CLOSE DOWN REPORT

1) Overall impression 2) Reflection: Fulfilment of objectives

3) Reflection: Deliverables / Schedule

4) Reflection: Resources / Costs

5) Reflection: Internal Organisation / Environmental Relationships

6) Performance appraisal (Project owner, Project 7) Lessons learned (Summary of Experiences and manager, Project member) suggestions for improvement)

8) Post-Project Phase Planning, Additional Tasks To-Do Owner Schedule

9) Project Close Down

(Project owner) (Project manager)

Version: 2.9 10.5.2011 pma certification body 27/28 5.2 Minutes – Project Close Down

5.2.1 Project Close Down Workshop

Version: 2.9 10.5.2011 pma certification body 28/28