York River Treatment Plant

Gloucester County Historic Courthouse, home of the Daffodil Festival, combines history and beauty.

Hampton Located on the mouth of the , Hampton is graced with miles of shoreline and breathtaking water views. Residents and businesses alike choose to call this beautiful city home.

Mathews County Historic New Point Comfort Lighthouse, the lonely sentinel at the southern tip of Mathews County, traces its history from the earliest days of the . First lighted in 1805, it has survived war, hurricanes, abandonment and the eroding grasp of the sea. It stands as a reminder of the nation's first efforts to establish commerce during the presidency of Thomas Jefferson.

Poquoson It was the water that brought the first settlers to Poquoson. The name of the city is a Native American word which roughly translates to “great marsh.”

York County Yorktown is most remembered as the site where British General Lord Cornwallis surrendered to American and French forces prosperous 18th century seaport, having been established by the under the command of General , bringing an end 1691 Act of Ports. Yorktown also witnessed major Civil War activity. to the last major battle of the American Revolutionary War. But even Its fortifications held off a Union army attack during the Peninsula before the struggle for independence, the town was a bustling and Campaign of 1862. York River

Q3±

YR011900

YR010300 YR010530 YR010520 YR013400

Feet Legend 0 5,50011,000 22,000 33,000 44,000

York River

Q3± Treatment Plant Service Area CIP Projects Ü CIP Location ^_ CIP Interceptor Point _ CIP PumpStation Point

± ± CIP Interceptor Line Treatment Plant Projects CIP Abandonment YR012220 Treatment Plant Service Area YR013110 HRSD Interceptor Force Main YR013140 HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station Service Area 3PS HRSD Pump Station HOWE RD

PACERS PT

ADMIRAL CT

CREEKVIEW LN BEACH RD SUGARBERRY RUN

PINE LN HARRIS CREEK RD CLIPPER DR

WADE RD

WINDJAMMER DR NEFF DR ZILBER CT

HOLIDAY DR

YR010300

HALL RD DUVAL CT

NG-088 HIDALGO DR

PELHAM DR

YR010300 ALLENDALE DR ALLENDALE

NG-086 DURHAM ST NOTTINGHAM DR

FORT WORTH ST

ESSEX PARK DR

CABOT DR GREENVILLECT

NG-087

HARRIS CREEK RD

HOUSTONAVE STOCKTON ST

REVEREDR

QUEENSVIEW CT

FAIRFIELDBLVD

NATHANST PAGE DR

ROSSER DR

NF-089

WINNARD RD NF-066 NF-120

NF-090

BH015100

MARIGOLD LN

EAGLES LNDG

SESCO DR

GLASCOW WAY

AMBLER CT NF-091

RHODA CT

BONNEY LN

WOODLAND RD

YR010300 Feet ± 0 400 800 1,600 2,400 3,200 ± Project Interceptor Line ^!] Project Interceptor Point ]^! Project Pump Station Point / Project Area CIP Location Legend YR010300 ^_ CIP Interceptor Point

_ CIP Pump Station Point ± Foxridge Sanitary Sewer System ± CIP Interceptor Line Sections 1, 4 & 5 Gravity and CIP Abandonment Woodland Road Fox Hill Road CIP Project Area Gravity Sewer Rehabilitation HRSD Interceptor Force Main HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station Hampton

3PS HRSD Pump Station Foxridge, Woodland Road and Fox Hill Road Gravity PR_YR010300 Sewer Rehabilitation

System: York River Driver Category: I&I Abatement-Rehabilitation Plan Type: Pipelines Project Status: Proposed Regulatory: Rehab Plan Phase Two

PROGRAM CASH FLOW PROJECTION ($,000)

Exp to Prog Cost Previous Year FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27

$2,940 $0 $0 $0 $0 $0 $214 $1,414 $1,312 $0 $0 $0 PROJECT DESCRIPTION

This project involves the rehabilitation and/or replacement of (length dimensions approximate): NG-086 - 2,920 LF of 15-inch and 410 LF of 14-inch, from the terminus manhole at the intersection of Little Back River and Harris Creek to the intersection of Ft. Worth Street and Waco Court. NG-087 - 1,523 LF of 18-inch pipe NG-088 – 2,060 LF of 10-inch pipe from Beach Road and Catalina Drive to Bloxoms Corner Pump Station NG-092 - 509 LF of 21-inch and 228 LF of 24-inch pipe

Line rehabilitation will also include the rehabilitation/ replacement of at least 54 manholes. This project has been updated to reflect work removed from the CIP and added to the find and fix requirements of the Federal EPA Consent Decree.

PROJECT JUSTIFICATION

The Foxridge, Bloxoms Corner and Woodland/Fox Hill Road gravity systems are primarily collection systems that require rehabilitation/replacement. Upon completion of the rehabilitation/replacement, these systems should be transferred to the City of Hampton. Approx. 1935 LF of existing 10-inch Vetrified Clay pipe was replaced along Beach Road with new 10-inch PVC pipe as part of the Prompt Repair program. This portion of new gravity pipe will also be transferred over to the City of Hampton for operation and maintenance.

FUNDING TYPE CONTACTS

Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-Interceptors Contacts-Dept Contacts: Ryan Brewster Contacts-Managing Dept: Engineering

PROPOSED SCHEDULE START DATE COST ESTIMATE

PrePlanning 02/01/2021 PrePlanning $0 PER 07/01/2021 PER $47,122 Design Delay 02/01/2022 Design $267,028 Design 02/01/2022 PreConstruction $6,591 Bid Delay 10/01/2022 Construction $2,614,260 PreConstruction 10/01/2022 Closeout $5,000 Construction 12/01/2022 Est. Program Cost $2,940,001 Closeout 02/01/2024 Contingency Budget $522,852 Est. Project Costs $3,462,853 ROLAND DR WESTOVER ST

SHORELINE DR GILBERT ST W

MARVIN DR

LASALLE AVE

NG-063

ROANE DR

WHEATLAND DR

LASALLE AVE COURTNEY DR

NKING ST

PARKWAYDR

N SELDENDALE DR

SALEM ST

NF-065 YR010520 NF-058

W MERCURY BLVD NG-067 W MERCURY BLVD N KING ST

PLAZA DR LANGLEY AVE

EASTERLY AVE

LASALLE AVE

MERCERAVE

BETHEL AVE

NG-078

FOLEY ST

RIP RAP RD WEST AVE

LASALLE AVE

N ARMISTEAD AVE NG-082 QUASH ST THOMAS ST NF-075

LANGLEY AVE

YR010520 Feet ± 0 310 620 1,240 1,860 2,480 ± Project Interceptor Line ^!] Project Interceptor Point ]^! Project Pump Station Point / Project Area CIP Location Legend YR010520 ^_ CIP Interceptor Point

_ CIP Pump Station Point ± Magruder Mercury Interceptor ± CIP Interceptor Line Force Main Replacement - Section B CIP Abandonment CIP Project Area HRSD Interceptor Force Main HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station Hampton

3PS HRSD Pump Station Magruder Mercury Interceptor Force Main Replacement- PR_YR010520 Section B

System: York River Driver Category: Aging Infrastructure/Rehabilitation Type: Pipelines Project Status: Proposed Regulatory: None

PROGRAM CASH FLOW PROJECTION ($,000)

Exp to Prog Cost Previous Year FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27

$4,007 $0 $0 $0 $64 $312 $1,316 $2,311 $3 $0 $0 $0 PROJECT DESCRIPTION

This project will consist of design and construction for the replacement of 6,200 LF of 30-inch prestressed concrete cylinder pipe (PCCP) and ductile iron (DI) force main (NF-058) from the Langley Circle Pump Station to just east of the Newmarket Creek Crossing. This project will require bypass pumping and temporary piping to facilitate maintenance of existing flows during construction.

PROJECT JUSTIFICATION

There a number of infrastructure issues providing the justification for this project and each issue should be considered during the design of the replacement. A force main break and emergency repair occurred on this line in the vicinity of Langley Circle Pump Station due to crown corrosion. During the by-pass operation required during the VDOT relocation in the late 1980's, significant debris and sedimentation was observed. The as-built profile and the construction methods used during the original installation of this line provide indication that numerous locations of this force main are at elevated risk for internal crown corrosion.

FUNDING TYPE CONTACTS

Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-Interceptors Contacts-Dept Contacts: Ryan Brewster Contacts-Managing Dept: Engineering

PROPOSED SCHEDULE START DATE COST ESTIMATE

PrePlanning 07/01/2019 PrePlanning $0 PER 12/01/2019 PER $64,291 Design Delay 07/01/2020 Design $364,316 Design 07/01/2020 PreConstruction $5,000 Bid Delay 09/01/2021 Construction $3,567,967 PreConstruction 09/01/2021 Closeout $5,000 Construction 01/02/2022 Est. Program Cost $4,006,574 Closeout 06/01/2023 Contingency Budget $713,593 Est. Project Costs $4,720,168 PEABODY DR DOWNEY FARM RD

N ARMISTEAD AVE

MEDICAL DR

HARDY CASH DR

TIDE MILL LN

TERRELL LN

WILLIAMSBURGDR

WYNDHAM DR COLISEUM DR RAYMOND DR

NF-058 N ARMISTEAD AVE MARCELLA RD WHEATLAND DR

HARTFORD RD EXECUTIVE DR

COLISEUM XING

CUNNINGHAM DR

ENFIELD DR NF-068

YR010530 INGLEWOOD DR

MERCHANT LN

I-64 VON SCHILLING DR W MERCURY BLVD NF-071

W MERCURY BLVD REESE DR SAVILLE ROW

NPS-222

I-64

NF-074

COMMERCE DR

263B

PINE CHAPEL RD FINDLEY ST

YR010530 Feet ± 0 385 770 1,540 2,310 3,080 ± Project Interceptor Line ^!] Project Interceptor Point ]^! Project Pump Station Point / Project Area CIP Location Legend YR010530 ^_ CIP Interceptor Point

_ CIP Pump Station Point ± Magruder Mercury Interceptor ± CIP Interceptor Line Force Main Replacement - Section C CIP Abandonment CIP Project Area HRSD Interceptor Force Main HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station Hampton

3PS HRSD Pump Station Magruder Mercury Interceptor Force Main Replacement- PR_YR010530 Section C

System: York River Driver Category: Aging Infrastructure/Rehabilitation Type: Pipelines Project Status: Proposed Regulatory: None

PROGRAM CASH FLOW PROJECTION ($,000)

Exp to Prog Cost Previous Year FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27

$5,266 $0 $0 $0 $0 $0 $30 $54 $480 $1,508 $2,255 $939 PROJECT DESCRIPTION

This project will consist of design and construction for the replacement of 8,300 LF of 30-inch prestressed concrete cylinder pipe (PCCP) force main (NF-058) from the intersection of Mercury Boulevard and Windsor Drive to just east of the intersection of Executive Drive and Marcella Road. This project will require bypass pumping and temporary piping to facilitate maintenance of existing flows during construction.

PROJECT JUSTIFICATION

There a number of infrastructure issues providing the justification for this project and each issue should be considered during the design of the replacement. During the by-pass operation required during the VDOT relocation in the late 1980's, significant debris and sedimentation was observed. The as-built profile and the construction methods used during the original installation of this line provide indication that numerous locations of this force main are at elevated risk for internal crown corrosion. Lastly, there are numerous locations where building structures and/or lack of vehicular and equipment access present significant operational response difficulties.

FUNDING TYPE CONTACTS

Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-Interceptors Contacts-Dept Contacts: Ryan Brewster Contacts-Managing Dept: Engineering

PROPOSED SCHEDULE START DATE COST ESTIMATE

PrePlanning 09/01/2021 PrePlanning $0 PER 02/01/2022 PER $84,639 Design Delay 04/01/2023 Design $479,623 Design 07/01/2023 PreConstruction $4,702 Bid Delay 07/01/2024 Construction $4,697,122 PreConstruction 07/01/2024 Closeout $0 Construction 11/01/2024 Est. Program Cost $5,266,086 Closeout 12/01/2026 Contingency Budget $939,425 Est. Project Costs $6,205,511 CARYS CHAPEL RD

COLLINS LN

VA-172

NF-026

YR011900

WYTHE CREEK RD

WYTHE LANDING LOOP

YR011900 Feet ± 0 125 250 500 750 1,000 ± Project Interceptor Line ^!] Project Interceptor Point ]^! Project Pump Station Point / Project Area CIP Location Legend YR011900 ^_ CIP Interceptor Point

_ CIP Pump Station Point ± Bethel-Poquoson Force Main Part III ± CIP Interceptor Line Replacement CIP Abandonment CIP Project Area HRSD Interceptor Force Main HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station Hampton, York County, Poquoson

3PS HRSD Pump Station Bethel-Poquoson Force Main Part III Replacement PR_YR011900

System: York River Driver Category: Relocation Type: Pipelines Project Status: Design Regulatory: None

PROGRAM CASH FLOW PROJECTION ($,000)

Exp to Prog Cost Previous Year FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27

$1,137 $139 $0 $666 $333 $0 $0 $0 $0 $0 $0 $0 PROJECT DESCRIPTION

This work will be constructed as part of a Department of Transpiration (VDOT) roadway improvements project. Portions of the existing pipeline will be relocated at VDOT project expense and some portions will be relocated at HRSD expense. This project will replace and/or rehabilitate approximately 5,000 linear feet of existing 20-inch prestressed concrete cylinder pipe (PCCP) along the eastern edge of Wythe Creek Road. VDOT will replace approximately 3,250 feet of pipe at project cost and HRSD will be responsible for replacement of 1,750 feet of pipe at HRSD's cost.

PROJECT JUSTIFICATION

The relocation of this pipeline is due to a VDOT roadway project to widen Wythe Creek Road.

FUNDING TYPE CONTACTS

Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-Interceptors Contacts-Dept Contacts: Jeremiah Burford Contacts-Managing Dept: Engineering

PROPOSED SCHEDULE START DATE COST ESTIMATE

PrePlanning 01/01/2015 PrePlanning $0 PER 07/01/2016 PER $0 Design Delay 10/01/2016 Design $138,683 Design 11/01/2016 PreConstruction $465 Bid Delay 08/01/2016 Construction $998,094 PreConstruction 01/01/2019 Closeout $0 Construction 04/01/2019 Est. Program Cost $1,137,242 Closeout 06/01/2020 Contingency Budget $199,619 Est. Project Costs $1,336,861 YR013140

YR012220

NF-961 BACK CREEK RD

YR012220 Feet ± 0 70 140 280 420 560 ± Project Interceptor Line ^!] Project Interceptor Point ]^! Project Pump Station Point / Project Area CIP Location Legend YR012220 ^_ CIP Interceptor Point

_ CIP Pump Station Point ± York River Treatment Plant Digester ± CIP Interceptor Line Cover Replacement Phase II CIP Abandonment CIP Project Area HRSD Interceptor Force Main HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station York County

3PS HRSD Pump Station York River Treatment Plant Digester Cover Replacement PR_YR012220 Phase II

System: York River Driver Category: Aging Infrastructure/Rehabilitation Type: Biosolids Project Status: Bid Delay Regulatory: None

PROGRAM CASH FLOW PROJECTION ($,000)

Exp to Prog Cost Previous Year FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27

$1,175 $48 $882 $245 $0 $0 $0 $0 $0 $0 $0 $0 PROJECT DESCRIPTION

This project is comprised of the design and installation of a fixed steel cover with liquid seal arrangement to replace the damaged WesTech DuoSphere currently in place on the secondary anaerobic digester.

PROJECT JUSTIFICATION

The cover currently installed on the secondary anaerobic digester is damaged and no longer functional. The fixed steel cover installed with a liquid seal arrangement will replace the damaged cover and allow the secondary digester to be put back into service. The proposed replacement cover will meet the needs of the York River Treatment Plant and was recommended to meet a fast-track design schedule.

FUNDING TYPE CONTACTS

Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-Treatment Contacts-Dept Contacts: Eddie Abisaab Contacts-Managing Dept: Engineering

PROPOSED SCHEDULE START DATE COST ESTIMATE

PrePlanning PrePlanning $0 PER PER $0 Design Delay Design $44,370 Design 03/01/2016 PreConstruction $5,360 Bid Delay 07/01/2016 Construction $1,120,000 PreConstruction 05/01/2017 Closeout $5,000 Construction 08/01/2017 Est. Program Cost $1,174,730 Closeout 10/01/2018 Contingency Budget $225,000 Est. Project Costs $1,399,730 YR013140

YR013110

NF-961

WATERVIEW RD

N BEACH RD

YR013110 Feet ± 0 255 510 1,020 1,530 2,040 ± Project Interceptor Line ^!] Project Interceptor Point ]^! Project Pump Station Point / Project Area CIP Location Legend YR013110 ^_ CIP Interceptor Point

_ CIP Pump Station Point ± York River Treatment Plant Outfall ± CIP Interceptor Line and Diffuser Modifications CIP Abandonment CIP Project Area HRSD Interceptor Force Main HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station York County

3PS HRSD Pump Station York River Treatment Plant Outfall and Diffuser PR_YR013110 Modifications

System: York River Driver Category: Relocation Type: Wastewater Treatment Project Status: Construction Regulatory: None

PROGRAM CASH FLOW PROJECTION ($,000)

Exp to Prog Cost Previous Year FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27

$18,642 $17,817 $825 $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECT DESCRIPTION

This project evaluated options for the relocation of the plant outfall and possible addition of a diffuser to provide required dilution of York River Treatment Plant (YRTP) effluent. Three options were evaluated: a) discharge into the existing Dominion Power canal b) use existing Dominion Power diffuser, and c) construct a new outfall pipe and new diffuser. In addition, the effluent pumps at YRTP will be evaluated.

Options a) temporarily discharging into the existing Dominion Power canal and c) relocating and extending the outfall were selected. The design-build team's design and construction schedule indicates that the construction will be complete in February 2016, which is prior to the April 2016 date that DVP provided for their shutdown of coal-fired generation units 1 & 2 and change in operation of oil- fired generation unit 3. Therefore, no interim pumping plan is needed.

Upgrades will be necessary to the YRTP Effluent Pump Station for the effluent to be able to be pumped to the discharge point in the York River. These upgrades will be a separate CIP: YR013120 YRTP Effluent Pump Station Improvements.

PROJECT JUSTIFICATION

This project is necessary due to Dominion Power's plan to shut down two existing coal-powered units. Dominion will continue to operate one existing oil powered unit periodically. Cooling water from this one unit may not provide the required dilution of the YRTP effluent.

FUNDING TYPE CONTACTS

Funding Type: Revenue Bond Contacts-Requesting Dept: Engineering Contacts-Dept Contacts: Ann Copeland Contacts-Managing Dept: Engineering

PROPOSED SCHEDULE START DATE COST ESTIMATE

PrePlanning 01/02/2013 PrePlanning $101,372 PER 09/01/2013 PER $0 Design Delay 03/01/2014 Design $950,160 Design 03/01/2014 PreConstruction $1,649,464 Bid Delay 03/01/2014 Construction $15,933,123 PreConstruction 12/01/2014 Closeout $7,500 Construction 07/01/2016 Est. Program Cost $18,641,619 Closeout 08/01/2017 Contingency Budget $215,444 Est. Project Costs $18,857,063 YR013140

YR013110

NF-961

WATERVIEW RD

WATERVIEW RD

GOODWIN NECK RD

YR013140

NF-012 YR012220

YR013140 Feet ± 0 435 870 1,740 2,610 3,480 ± Project Interceptor Line ^!] Project Interceptor Point ]^! Project Pump Station Point / Project Area CIP Location Legend YR013140 ^_ CIP Interceptor Point

_ CIP Pump Station Point ± York River Treatment Plant ± CIP Interceptor Line Environmental Studies and Habitat CIP Abandonment Enhancement CIP Project Area HRSD Interceptor Force Main HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station York County

3PS HRSD Pump Station York River Treatment Plant Environmental Studies and PR_YR013140 Habitat Enhancement

System: York River Driver Category: Risk Mitigation Type: Wastewater Treatment Project Status: Pre Planning Regulatory: None

PROGRAM CASH FLOW PROJECTION ($,000)

Exp to Prog Cost Previous Year FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27

$1,000 $223 $478 $299 $0 $0 $0 $0 $0 $0 $0 $0 PROJECT DESCRIPTION

The York River Outfall Mitigation Project has two primary goals: (a) create a one acre oyster brood stock sanctuary reef in the lower York River, and (b) examine alternative and/or additive methodologies which improve the Commonwealth's ability to accurately determine shellfish condemnation zones necessary to preserve public health in waters adjacent to wastewater treatment facilities. The project will be conducted in collaboration with HRSD, Virginia Marine Resources Commission (VMRC), Virginia Department of Health Division of Shellfish Sanitation (VDH DSS), Virginia Institute of Marine Science (VIMS), and the University of North Carolina - Chapel Hill – Institute of Marine Science (UNC).

PROJECT JUSTIFICATION

This project is a result of an agreement with VMRC to mitigate the condemnation of shellfish growing areas, which was required as part of the approval of HRSD York River Outfall and Diffuser Modifications.

FUNDING TYPE CONTACTS

Funding Type: Cash Contacts-Requesting Dept: Water Quality Contacts-Dept Contacts: Jim Pletl Contacts-Managing Dept: Water Quality

PROPOSED SCHEDULE START DATE COST ESTIMATE

PrePlanning 02/01/2016 PrePlanning $900,000 PER 12/01/2018 PER $0 Design Delay 12/01/2018 Design $0 Design 12/01/2018 PreConstruction $0 Bid Delay 12/01/2018 Construction $100,000 PreConstruction 12/01/2018 Closeout $0 Construction 12/01/2018 Est. Program Cost $1,000,000 Closeout 01/01/2019 Contingency Budget $0 Est. Project Costs $1,000,000 HODGES DR RIVERDALE DR

BROOKFIELD DR

CHARLTON DR

W MERCURY BLVD

W MERCURY BLVD

NF-058

NF-074

BROADSTREET RD

GILDNER RD

REESE DR

NF-072

YR013500

CANTERBURY RD

MARSH LOOP

N ARMISTEAD AVE

FORSYTH WAY

EMORY WAY

NPS-222 DELBROOK WAY NF-073

MERCER AVE

MURRAY AVE BRYSON CIR

FINDLEY ST

YR013500 Feet ± 0 115 230 460 690 920 ± Project Interceptor Line ^!] Project Interceptor Point ]^! Project Pump Station Point / Project Area CIP Location Legend YR013500 ^_ CIP Interceptor Point

_ CIP Pump Station Point ± Westminster Drive Force Main ± CIP Interceptor Line Replacement CIP Abandonment CIP Project Area HRSD Interceptor Force Main HRSD Interceptor Gravity Main

Q3 HRSD Treatment Plant

3SRP HRSD Pressure Reducing Station

3PS HRSD Pump Station Westminister Drive Force Main Replacement PR_YR013500

System: York River Driver Category: Aging Infrastructure/Rehabilitation Type: Pipelines Project Status: Proposed Regulatory: None

PROGRAM CASH FLOW PROJECTION ($,000)

Exp to Prog Cost Previous Year FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27

$668 $0 $0 $0 $96 $567 $5 $0 $0 $0 $0 $0 PROJECT DESCRIPTION

This project will replace approximately 1,450 LF of 10-inch Cast Iron (CI) pipe along Westminister Drive from Mercury Blvd to just south of Canterbury Rd, to include the valving and connection to NF-058 (YR4027) at Mercury Blvd.

PROJECT JUSTIFICATION

This force main has experienced three recent failures (April 2014, March 2016 and November 2016). The failures have all been longitudinal cracks along the bottom of the pipe. Forensic analysis performed on the first two failures identified external corrosion and loading as the primary causes. No forensic analysis is to be performed on the third failure due to similarity to previous failures.

FUNDING TYPE CONTACTS

Funding Type: Revenue Bond Contacts-Requesting Dept: Operations-Interceptors Contacts-Dept Contacts: Ryan Brewster Contacts-Managing Dept: Engineering

PROPOSED SCHEDULE START DATE COST ESTIMATE

PrePlanning 07/01/2019 PrePlanning $0 PER 09/01/2019 PER $28,100 Design Delay 01/01/2020 Design $67,440 Design 01/01/2020 PreConstruction $5,000 Bid Delay 07/01/2020 Construction $562,000 PreConstruction 07/01/2020 Closeout $5,000 Construction 10/01/2020 Est. Program Cost $667,540 Closeout 07/01/2021 Contingency Budget $106,000 Est. Project Costs $773,540