The World Bank Implementation Status & Results Report CH-Second Cultural and Natural Heritage Protection and Development Project (P149528)

CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

EAST ASIA AND PACIFIC | | Urban, Resilience and Land Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 8 | ARCHIVED on 15-Jan-2021 | ISR44886 | Public Disclosure Authorized

Implementing Agencies: People's Republic of China, Gansu Culture Tourism Group, Co. Ltd (CTG)

Key Dates

Key Project Dates

Bank Approval Date: 24-Feb-2017 Effectiveness Date: 27-Oct-2017 Planned Mid Term Review Date: 05-Aug-2019 Actual Mid-Term Review Date: 09-Aug-2019 Original Closing Date: 31-Dec-2022 Revised Closing Date: 31-Dec-2023 pdoTable

Project Development Objectives Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) To conserve cultural and natural heritage, enhance tourism services and improve community services in selected project sites in Gansu Province.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No

Components Table

Name Heritage Conservation and Tourism Services Improvement:(Cost $80.94 M) Community Basic Services Delivery:(Cost $41.73 M) Capacity Building, Institutional Strengthening, and Project Management Support:(Cost $8.00 M) Public Disclosure Authorized Overall Ratings

Name Previous Rating Current Rating

Progress towards achievement of PDO Moderately Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Moderate

Implementation Status and Key Decisions

The project remains relevant to the Gansu Huaxia Cultural Heritage Initiative of 2013 and the World Bank Group-China Country Partnership Strategy. It is making progress and is on track to conserve cultural and natural heritage, enhance tourism services, and improve community services in selected project sites in Gansu Province. The Gansu Provincial Government and participating project Counties and Districts have consistently shown strong commitment to the project throughout implementation and have given high priority to activities in support of reaching the Project’s Development Objective. After project restructuring in June 2020, project progress has been further accelerated and major barriers have been Public Disclosure Authorized removed. With the launching of additional activities, the project’s impact is expected to be enhanced. On the ground achievements to-date include 5 management plans adopted and fully funded by county budgets, 97 tourism-related small businesses supported by new community organizations, an increase in the spending by tourists in project sites of 2074 RMB/tourist, 3,820,000 visitors to project-supported tourist sites, and 29,366 people in project areas with improved access to community services – all exceeding the planned results for 2020.

1/15/2021 Page 1 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

Risks

Systematic Operations Risk-rating Tool

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance Low Low Low Macroeconomic Moderate Moderate Low Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Moderate Institutional Capacity for Implementation and Substantial Substantial Moderate Sustainability Fiduciary Substantial Substantial Moderate Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other -- Moderate Low Overall Substantial Substantial Moderate

Results

PDO Indicators by Objectives / Outcomes

To conserve cultural and natural heritage, enhance tourism services and improve community services

IN00934516 ►KPI 1 Direct project beneficiaries-Core Sector Indicator (CSI) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 25,351.00 106,016.00 120,000.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020 although the female breakdown result is slightly below its 2020 target. 2020 target 2020 Actual

Subtotal Female Subtotal Female

Comments: Hezheng 43,996

Tanchang 22,389

Kangxian 13,656

1/15/2021 Page 2 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

Jingchuan 25,975

Jingtai -

Total 106,016 53,360 106,016 52,061

Source: PIUs

IN00934521 of which female (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 12,009.00 52,061.00 66,700.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023

To conserve cultural and natural heritage

IN00934517 ►KPI 2 Site management plans adopted and fully funded by county budgets (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 5.00 5.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020 and achieved the final target. Five plans are: 1. Hezheng: Master Plan for Ancient Fossil Scenic Zone of Songmingyan of . 2. Tanchang: Master Plan for Greater Guan'ergou Scenic Zone 3. Kangxiang: Plan for Yangba Scenic Zone 4. Jingchuan: Ten Major Events of Jingchuan County Comments: 5. Jingtai: Notice Jointly Issued by Government and County Committee of the Communist Party of China on Distributing the Implementation Plan of Establishing Jingtai County for National Demonstration Zone of all-for-one Tourism Source: PIUs

To enhance tourism services

IN00934518 ►KPI 3 Tourism related small businesses supported by new community organizations (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 80.00 97.00 120.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020 with breakdowns below. KPI#3- By Dec 2020

Comments: Target Actual

Hezheng 9

1/15/2021 Page 3 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

Tanchang 45

Kangxian 22

Jingchuan 19

Jingtai 2

Total 96 97

Business setups mainly in aspects of food and beverage provision, small ornaments, local specialities, homestays and, farm produces.

Source: PIUs

IN00934520 ►KPI 4 Increase in spending by tourists in project sites (RMB/visitor) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 85.00 118.00 207.00 230.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020. By Dec 2020

Target Actual

Hezheng 200

Tanchang 200

Kangxian 230 Comments: Jingchuan 175

Jingtai 200

Average 150 207

Source: PIUs

IN00934522 ►KPI 5 Visitors to the tourist sites (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 2,900,000.00 3,429,400.00 3,820,000.00 4,225,000.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 Comments: This indicators exceeded its annual target for 2020 with breakdowns below: By Dec 2020

1/15/2021 Page 4 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

Target Actual

Hezheng 195

Tanchang 72

Kangxian 84

Jingchuan 1

Jingtai 30

Total 363 382

Source: PIUs from Tourism Management Authorities.

To improve community services

IN00934519 ►KPI 6 People in project areas with improved access to community services (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 24,819.00 29,366.00 30,600.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020 with breakdowns below: Source: PIUs

KPI#6 People in project areas with improved access to community services

By Dec 2020

Target Actual

Hezheng 14,196 Comments: Tanchang 7,001

Kangxian 460

Jingchuan 7,709

Jingtai -

Total 24,480 29,366

Intermediate Results Indicators by Components

1/15/2021 Page 5 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

Component 1 Heritage Conservation and Tourism Services Improvement

IN00934523 ►IOI 1.1 Cultural heritage sites conserved (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 2.00 13.00 23.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceeded its annual target for 2020. By Dec 2020

Target Actual Notes

Hezheng

Tanchang 2 Tanchang:鹿仁村、新坪村2处; Kangxan:民俗舞 台、村史馆、观光茶园、梅园沟景区大门、梅园沟海 Comments: Kangxian 5 棠谷共5处; Jingchuan:韩王墓;罗汉洞石窟;凤凰 Jingchuan 6 沟;千佛嘴;丈八寺、南城崖共6处

Jingtai

Total 9 13

Source: PIUs

IN00934526 ►IOI 1.2 Sites with soil erosion and landslide risks addressed (number) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 5.00 7.00 14.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result is partially achieved for the annual target for 2020, which should be 11 sites. By Dec 2020

Target Actual

Hezheng

Tanchang 5

Comments: Kangxian 2

Jingchuan

Jingtai

Total 11 7

Source: PIUs

1/15/2021 Page 6 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

IN00934528 ►IOI 1.3 Visitor centers established (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 1.00 5.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result is partially achieved for the annual target for 2020, which should be 3 places. Comments: Kangxian Meiyuangou Tourist Center has been set up.

IN00934530 ►IOI 1.4 Length of pathways improved in scenic areas (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 27.20 45.00 92.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result is partially achieved for the annual target for 2020, which should be 50km. By Dec 2020

Target Actual

Hezheng 18

Tanchang 27

Comments: Kangxian

Jingchuan

Jingtai

Total 50 45

Source: PIUs

IN00934532 ►IOI 1.5 Museums established (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 1.00 2.00 8.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 Comments: This result is partially achieved for the annual target for 2020, which should be 3 places. By Dec 2020

Target Actual Notes

Hezheng

Tanchang

1/15/2021 Page 7 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

Kangxian 1 Folk Custom Exhibition Hall for Qiang Ethnic Minority

Folk Custom Exhibition Hall for Wanyan Ethnic Jingchuan 1 Minority

Jingtai

Total 2 3

Source: PIUs

IN00934534 ►IOI 1.6 New tourism destinations established at communities (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 1.00 2.00

Date 31-Dec-2019 24-Jun-2020 31-Dec-2020 31-Dec-2023 This is a new indicator introduced in the June 2020 restructuring. Its result is as planned for 2021. The result achieved slightly ahead of schedule. By Dec 2020

Target Actual

Hezheng

Tanchang

Comments: Kangxian

Jingchuan

Jingtai 1

Total - 1

Source:

Component 2 Community Basic Services Delivery

IN00934524 ►IOI 2.1 Sewage pipelines improved (km) -CSI (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 68.00 82.00 124.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result is partially achieved for the annual target for 2020, which should be 100km. By Dec 2020 Comments: Target Actual

1/15/2021 Page 8 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

Hezheng 13.5

Tanchang 67

Kangxian 1

Jingchuan

Jingtai

Total 100 82

Source: PIUs

IN00934527 ►IOI 2.2 Rural roads rehabilitated (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 26.00 28.00 27.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceeded the annual (26km) and final target (27km). By Dec 2020

Target Actual

Hezheng 26

Tanchang

Comments: Kangxian

2

Jingtai

Total 26 28

Source: PIUs

IN00934529 ►IOI 2.3 Consultations held with local communities -CSI (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 82.00 187.00 224.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 Comments: This result exceeded the annual target (150). Consultations on subjects of routing the community roads, transplating trees, land acquistion, construction plans, environmental protection and public participation training by the consultant. By Dec 2020

Target Actual

1/15/2021 Page 9 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

He zhe 38 ng

Tan cha 53 ng

Ka ngx 45 ian

Jin gch 34 uan

Jin 17 gtai

Tot 150 187 al

Source: PIUs

IN00934531 ►IOI 2.4 Percentage of registered grievances appropriately responded within two weeks (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 40.00 95.00 100.00 100.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceeded its target for 2020 (95%). Comments: All GRMs have been properly replied by contractors, PIUs and/or villages committees.

IN00934533 ►IOI 2.5 Percentage of beneficiaries who feel Project investments reflected their needs (GRM indicator) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 60.00 95.00 97.00 95.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceed its target for 2020 and the end target (95%) Source: PIUs. Data were estimated by village committees and reported to PIUs Comments: No survey was conducted because of Covid-19 but village-level surveys have been scheduled on July 2021 for all project villages.

Community 3 Capacity Building, Institutional Strengthening, and Project Management Support

IN00934525 ►IOI 3.1 People receiving skills training (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

1/15/2021 Page 10 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

Value 0.00 2,376.00 5,509.00 7,400.00

Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceeded the annual target for 2020 (3,500). By Dec 2020

Target Actual

Hezheng 927

Tanchang 1,120 Including training on torism, livestock breeding, farming, vegetable planting, Comments: Kangxian 2,200 greenhouse managing, household, cooking and project management training delivered by PMC and other consultant. Jingchuan 530

Jingtai 732

Total

Source: PIUs

Overall Comments IR

7 intermediate output indicators out of 12 total reached or exceeded the annual target. 5 indicators partially reached the annual target due to the impacts of the Covid-19 pandemic.

Performance-Based Conditions

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed

P149528 IBRD-86760 Effective USD 100.00 100.00 0.00 36.41 63.59 36%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P149528 IBRD-86760 Effective 24-Feb-2017 07-Jul-2017 27-Oct-2017 31-Dec-2022 31-Dec-2023

Cumulative Disbursements

1/15/2021 Page 11 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)

PBC Disbursement

Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC

Restructuring History

Level 2 Approved on 23-Jun-2020

Related Project(s)

There are no related projects.

1/15/2021 Page 12 of 12