The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
EAST ASIA AND PACIFIC | China | Urban, Resilience and Land Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 8 | ARCHIVED on 15-Jan-2021 | ISR44886 | Public Disclosure Authorized
Implementing Agencies: People's Republic of China, Gansu Culture Tourism Group, Co. Ltd (CTG)
Key Dates
Key Project Dates
Bank Approval Date: 24-Feb-2017 Effectiveness Date: 27-Oct-2017 Planned Mid Term Review Date: 05-Aug-2019 Actual Mid-Term Review Date: 09-Aug-2019 Original Closing Date: 31-Dec-2022 Revised Closing Date: 31-Dec-2023 pdoTable
Project Development Objectives Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) To conserve cultural and natural heritage, enhance tourism services and improve community services in selected project sites in Gansu Province.
Has the Project Development Objective been changed since Board Approval of the Project Objective? No
Components Table
Name Heritage Conservation and Tourism Services Improvement:(Cost $80.94 M) Community Basic Services Delivery:(Cost $41.73 M) Capacity Building, Institutional Strengthening, and Project Management Support:(Cost $8.00 M) Public Disclosure Authorized Overall Ratings
Name Previous Rating Current Rating
Progress towards achievement of PDO Moderately Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Moderate
Implementation Status and Key Decisions
The project remains relevant to the Gansu Huaxia Cultural Heritage Initiative of 2013 and the World Bank Group-China Country Partnership Strategy. It is making progress and is on track to conserve cultural and natural heritage, enhance tourism services, and improve community services in selected project sites in Gansu Province. The Gansu Provincial Government and participating project Counties and Districts have consistently shown strong commitment to the project throughout implementation and have given high priority to activities in support of reaching the Project’s Development Objective. After project restructuring in June 2020, project progress has been further accelerated and major barriers have been Public Disclosure Authorized removed. With the launching of additional activities, the project’s impact is expected to be enhanced. On the ground achievements to-date include 5 management plans adopted and fully funded by county budgets, 97 tourism-related small businesses supported by new community organizations, an increase in the spending by tourists in project sites of 2074 RMB/tourist, 3,820,000 visitors to project-supported tourist sites, and 29,366 people in project areas with improved access to community services – all exceeding the planned results for 2020.
1/15/2021 Page 1 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
Risks
Systematic Operations Risk-rating Tool
Risk Category Rating at Approval Previous Rating Current Rating
Political and Governance Low Low Low Macroeconomic Moderate Moderate Low Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Moderate Institutional Capacity for Implementation and Substantial Substantial Moderate Sustainability Fiduciary Substantial Substantial Moderate Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other -- Moderate Low Overall Substantial Substantial Moderate
Results
PDO Indicators by Objectives / Outcomes
To conserve cultural and natural heritage, enhance tourism services and improve community services
IN00934516 ►KPI 1 Direct project beneficiaries-Core Sector Indicator (CSI) (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 25,351.00 106,016.00 120,000.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020 although the female breakdown result is slightly below its 2020 target. 2020 target 2020 Actual
Subtotal Female Subtotal Female
Comments: Hezheng 43,996
Tanchang 22,389
Kangxian 13,656
1/15/2021 Page 2 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
Jingchuan 25,975
Jingtai -
Total 106,016 53,360 106,016 52,061
Source: PIUs
IN00934521 of which female (Number, Custom Breakdown)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 12,009.00 52,061.00 66,700.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023
To conserve cultural and natural heritage
IN00934517 ►KPI 2 Site management plans adopted and fully funded by county budgets (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 5.00 5.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020 and achieved the final target. Five plans are: 1. Hezheng: Master Plan for Ancient Fossil Scenic Zone of Songmingyan of Hezheng County. 2. Tanchang: Master Plan for Greater Guan'ergou Scenic Zone 3. Kangxiang: Plan for Yangba Scenic Zone 4. Jingchuan: Ten Major Events of Jingchuan County Comments: 5. Jingtai: Notice Jointly Issued by Jingtai County Government and County Committee of the Communist Party of China on Distributing the Implementation Plan of Establishing Jingtai County for National Demonstration Zone of all-for-one Tourism Source: PIUs
To enhance tourism services
IN00934518 ►KPI 3 Tourism related small businesses supported by new community organizations (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 80.00 97.00 120.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020 with breakdowns below. KPI#3- By Dec 2020
Comments: Target Actual
Hezheng 9
1/15/2021 Page 3 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
Tanchang 45
Kangxian 22
Jingchuan 19
Jingtai 2
Total 96 97
Business setups mainly in aspects of food and beverage provision, small ornaments, local specialities, homestays and, farm produces.
Source: PIUs
IN00934520 ►KPI 4 Increase in spending by tourists in project sites (RMB/visitor) (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 85.00 118.00 207.00 230.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020. By Dec 2020
Target Actual
Hezheng 200
Tanchang 200
Kangxian 230 Comments: Jingchuan 175
Jingtai 200
Average 150 207
Source: PIUs
IN00934522 ►KPI 5 Visitors to the tourist sites (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 2,900,000.00 3,429,400.00 3,820,000.00 4,225,000.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 Comments: This indicators exceeded its annual target for 2020 with breakdowns below: By Dec 2020
1/15/2021 Page 4 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
Target Actual
Hezheng 195
Tanchang 72
Kangxian 84
Jingchuan 1
Jingtai 30
Total 363 382
Source: PIUs from Tourism Management Authorities.
To improve community services
IN00934519 ►KPI 6 People in project areas with improved access to community services (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 24,819.00 29,366.00 30,600.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This outcome exceeded its annual target for 2020 with breakdowns below: Source: PIUs
KPI#6 People in project areas with improved access to community services
By Dec 2020
Target Actual
Hezheng 14,196 Comments: Tanchang 7,001
Kangxian 460
Jingchuan 7,709
Jingtai -
Total 24,480 29,366
Intermediate Results Indicators by Components
1/15/2021 Page 5 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
Component 1 Heritage Conservation and Tourism Services Improvement
IN00934523 ►IOI 1.1 Cultural heritage sites conserved (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 2.00 13.00 23.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceeded its annual target for 2020. By Dec 2020
Target Actual Notes
Hezheng
Tanchang 2 Tanchang:鹿仁村、新坪村2处; Kangxan:民俗舞 台、村史馆、观光茶园、梅园沟景区大门、梅园沟海 Comments: Kangxian 5 棠谷共5处; Jingchuan:韩王墓;罗汉洞石窟;凤凰 Jingchuan 6 沟;千佛嘴;丈八寺、南城崖共6处
Jingtai
Total 9 13
Source: PIUs
IN00934526 ►IOI 1.2 Sites with soil erosion and landslide risks addressed (number) (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 5.00 7.00 14.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result is partially achieved for the annual target for 2020, which should be 11 sites. By Dec 2020
Target Actual
Hezheng
Tanchang 5
Comments: Kangxian 2
Jingchuan
Jingtai
Total 11 7
Source: PIUs
1/15/2021 Page 6 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
IN00934528 ►IOI 1.3 Visitor centers established (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 1.00 5.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result is partially achieved for the annual target for 2020, which should be 3 places. Comments: Kangxian Meiyuangou Tourist Center has been set up.
IN00934530 ►IOI 1.4 Length of pathways improved in scenic areas (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 27.20 45.00 92.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result is partially achieved for the annual target for 2020, which should be 50km. By Dec 2020
Target Actual
Hezheng 18
Tanchang 27
Comments: Kangxian
Jingchuan
Jingtai
Total 50 45
Source: PIUs
IN00934532 ►IOI 1.5 Museums established (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 1.00 2.00 8.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 Comments: This result is partially achieved for the annual target for 2020, which should be 3 places. By Dec 2020
Target Actual Notes
Hezheng
Tanchang
1/15/2021 Page 7 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
Kangxian 1 Folk Custom Exhibition Hall for Qiang Ethnic Minority
Folk Custom Exhibition Hall for Wanyan Ethnic Jingchuan 1 Minority
Jingtai
Total 2 3
Source: PIUs
IN00934534 ►IOI 1.6 New tourism destinations established at communities (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 1.00 2.00
Date 31-Dec-2019 24-Jun-2020 31-Dec-2020 31-Dec-2023 This is a new indicator introduced in the June 2020 restructuring. Its result is as planned for 2021. The result achieved slightly ahead of schedule. By Dec 2020
Target Actual
Hezheng
Tanchang
Comments: Kangxian
Jingchuan
Jingtai 1
Total - 1
Source:
Component 2 Community Basic Services Delivery
IN00934524 ►IOI 2.1 Sewage pipelines improved (km) -CSI (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 68.00 82.00 124.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result is partially achieved for the annual target for 2020, which should be 100km. By Dec 2020 Comments: Target Actual
1/15/2021 Page 8 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
Hezheng 13.5
Tanchang 67
Kangxian 1
Jingchuan
Jingtai
Total 100 82
Source: PIUs
IN00934527 ►IOI 2.2 Rural roads rehabilitated (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 26.00 28.00 27.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceeded the annual (26km) and final target (27km). By Dec 2020
Target Actual
Hezheng 26
Tanchang
Comments: Kangxian
2
Jingtai
Total 26 28
Source: PIUs
IN00934529 ►IOI 2.3 Consultations held with local communities -CSI (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 82.00 187.00 224.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 Comments: This result exceeded the annual target (150). Consultations on subjects of routing the community roads, transplating trees, land acquistion, construction plans, environmental protection and public participation training by the consultant. By Dec 2020
Target Actual
1/15/2021 Page 9 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
He zhe 38 ng
Tan cha 53 ng
Ka ngx 45 ian
Jin gch 34 uan
Jin 17 gtai
Tot 150 187 al
Source: PIUs
IN00934531 ►IOI 2.4 Percentage of registered grievances appropriately responded within two weeks (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 40.00 95.00 100.00 100.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceeded its target for 2020 (95%). Comments: All GRMs have been properly replied by contractors, PIUs and/or villages committees.
IN00934533 ►IOI 2.5 Percentage of beneficiaries who feel Project investments reflected their needs (GRM indicator) (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 60.00 95.00 97.00 95.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceed its target for 2020 and the end target (95%) Source: PIUs. Data were estimated by village committees and reported to PIUs Comments: No survey was conducted because of Covid-19 but village-level surveys have been scheduled on July 2021 for all project villages.
Community 3 Capacity Building, Institutional Strengthening, and Project Management Support
IN00934525 ►IOI 3.1 People receiving skills training (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
1/15/2021 Page 10 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
Value 0.00 2,376.00 5,509.00 7,400.00
Date 07-Mar-2016 24-Jun-2020 31-Dec-2020 31-Dec-2023 This result exceeded the annual target for 2020 (3,500). By Dec 2020
Target Actual
Hezheng 927
Tanchang 1,120 Including training on torism, livestock breeding, farming, vegetable planting, Comments: Kangxian 2,200 greenhouse managing, household, cooking and project management training delivered by PMC and other consultant. Jingchuan 530
Jingtai 732
Total
Source: PIUs
Overall Comments IR
7 intermediate output indicators out of 12 total reached or exceeded the annual target. 5 indicators partially reached the annual target due to the impacts of the Covid-19 pandemic.
Performance-Based Conditions
Data on Financial Performance
Disbursements (by loan)
Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed
P149528 IBRD-86760 Effective USD 100.00 100.00 0.00 36.41 63.59 36%
Key Dates (by loan)
Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date
P149528 IBRD-86760 Effective 24-Feb-2017 07-Jul-2017 27-Oct-2017 31-Dec-2022 31-Dec-2023
Cumulative Disbursements
1/15/2021 Page 11 of 12 The World Bank Implementation Status & Results Report CH-Second Gansu Cultural and Natural Heritage Protection and Development Project (P149528)
PBC Disbursement
Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC
Restructuring History
Level 2 Approved on 23-Jun-2020
Related Project(s)
There are no related projects.
1/15/2021 Page 12 of 12