E1700

Guo Huan Ping Zheng A No. 1039 v 2

Public Disclosure Authorized Baosteel Co., Ltd. Product Matrix and Process Equipment Upgrading and Technical Transformation Project of Meishan Iron and Steel Company

Public Disclosure Authorized Environmental Impact Report (Simplified Version for World Bank)

Public Disclosure Authorized

Central Research Institute of Building and Construction, MCC Group

Public Disclosure Authorized Nanjing Municipal Environmental Protection Scientific Research Institute October 2005

Entrusted by: Shanghai Meishan Iron and Steel Co., Ltd., Baosteel Group

Assessed by: Central Research Institute of Building and Construction, MCC Group Assessment Certificate No.: Guo Huan Ping Zheng A No. 1039

Responsible person of Undertaker: Dong Wenjun (Director and prof. level senior engineer) Responsible person of assessment department: Yang Liqin (Senior engineer) Project responsible person: Yi Haitao (Prof. level senior engineer, A10390001)

Members of project team: Certificate Name Title Responsible for Signature No. 1. General

Prof. level 2. Briefs of project and pollution Yi Haitao senior factor analysis A10390001 engineer 8. Assessment conclusions Overall proofreading 3. Feasibility analysis of Senior environmental protection measures Yang Liqin A10390008 engineer and its technological and economic justification Senior 5. Environmental risk analysis Zhang Yuanqi A10390005 engineer Senior 6. Environmental management and Yuan Yuming A10390003 engineer monitoring program Doctor 4. Pollutant emission to standards and Wei Youquan A103900015 overall amount control and analysis Senior 7. Public participation Gao Xiaojie JA1907003 engineer Technical review by: Dai Jingxian (Prof. level senior engineer, A10390007)

Cooperated by: Nanjing Municipal Environmental Protection Scientific Research Institute

Assessment Certificate No.: Guo Huan Ping Zheng A No. 1907

Director: Feng Xiaoyi (EA) Post Certificate No. A19070002

Project responsible person: Dai Fengsheng (EA) Senior Post Certificate No. JA1907002 Jiang Leping (EA) Post Certificate No. A19070013

Main drafters: Gao Xiaojie (EA) Post Certificate No. JA1907003 Liu Chunyang (EA) Post Certificate No. A19070012 Ji Zhengyu (EA) Post Certificate No. A19070019 Xie Zhiwei (EA) Post Certificate No. A19070033

Cooperated by: Jiangsu Provincial Environmental Protection Scientific Research Institute Assessment Certificate No.: Guo Huan Ping Zheng A No. 1902 (Qualification dedicated for jetty)

Table of Contents

1. General ...... 5 1.1 Overall presentation of project...... 5 1.2 Analysis on the compatibility of the project with industrial policies and local development planning...... 8 1.2.1 The proposed project conforms to the industrial development policies of the state...... 8 1.2.2 The proposed project conforms to the requirements for industrial development policies of the state for metallurgical industry ...... 10 1.2.3 The proposed project conforms to the overall planning of Baosteel Co., Ltd. . 12 1.2.4 Analysis of compatibility of the proposed project with overall urban planning12 1.2.5 Analysis of compatibility of the proposed project with environmental planning ...... 13 1.3 Working procedure for assessment...... 14 1.4 Basis of preparation...... 14 1.4.1 Laws and regulations of the state ...... 14 1.4.2 Local laws and regulations...... 16 1.4.3 Relevant documents and data...... 16 1.5 Purposes and requirements of assessment...... 16 1.6 Main contents and points of assessment ...... 17 1.6.1 Main contents of assessment...... 17 1.6.2 Main points in assessment work...... 18 2. General conditions the proposed project and pollution factor analysis...... 19 2.1 Necessity of project construction ...... 19 2.2 Environmental protection control and rectification plan to bring up the old with the new21 2.3 Pollution factor analysis for the proposed coking project...... 22 2.4 Pollutant prevention, treatment and control measures for coking project...... 28 2.4.1 Discharge of waste gas pollutants and control and rectification measures ...... 28 2.4.2 Waste water pollutant discharge and control and rectification measures...... 38 3. Feasibility analysis and technical and economic demonstration of environmental protection measures ...... 29

1

3.1 Overview of environmental protection measures for existing projects...... 29 3.1.1 Existing waste gas pollution control measures ...... 29

3.1.2 Existing wastewater pollution control measures...... 32 3.1.3 Solid waste pollution control measures for existing projects...... 33 3.1.4 Noise control measures in existing projects...... 35 3.1.5 Existing environmental problems...... 37 3.2 Analysis of pollution prevention and control measures for intended project and countermeasures...... 38 3.2.1 Prevention and control measures of key waste gas pollution sources and feasibility analysis...... 38 3.2.2 Prevention and control measures for main wastewater pollution sources and feasibility analysis...... 55 3.2.3 Analysis of noise control...... 66 3.2.4 Solid waste treatment and comprehensive utilization...... 66 3.2.5 Control measures for general stock house...... 69 4. Analysis for Pollutant Meeting-standard Emission and Total Amount Control ...... 70 4.1 Determination of enterprise pollutant emission and total amount control quotas...... 70 4.2 Pollutant meeting-standard emission and total amount control analysis for planned project...... 70 4.2.1 Waste gas and its pollutant meeting-standard emission and total amount control...... 70 4.2.2 Waste water and its pollutant meeting-standard discharge and total amount control quotas ...... 71 4.2.3 Solid waste emission amount control quotas ...... 73 4.3 Analysis for total amount control...... 73 5. Environmental Risk and Accident Discharge Analysis...... 74 5.1 Risk factors Identification ...... 74 5.1.1 Risk factors identification of raw materials, assistant materials, and products. 74 5.1.2 Risk factors identification for production process ...... 76 5.1.3 Risk factors identification during materials storage...... 76 5.2 Precautions against risk accidents...... 76 5.2.1 Precautions against risk accidents occurring in production process ...... 76 5.2.2 Precaution against risk accident during materials storage ...... 77

2

5.3 Disaster plan and emergency measures against sudden accident...... 78 5.3.1 Disaster emergency plan against sudden accident ...... 78

5.3.2 Emergency measure against sudden accident ...... 78 5.4 Accident discharge and measures...... 79 5.4.1 Failures of sewage disposal facilities and measures ...... 79 5.4.2 Waste gas accident discharge and measures...... 79 5.5 Comprehensive measures against environment risk ...... 80 6. Environmental Management and Monitoring Plan...... 81 6.1 Environmental management and organizational structure ...... 81 6.1.1 Environmental management structure...... 81 6.1.2 Environmental management responsibilities ...... 83 6.2 Environmental monitoring organization and supervising plans...... 84 6.2.1 Environmental monitoring organization ...... 84 6.2.2 Tasks of the monitoring stations...... 85 6.2.3 Environmental supervising plans ...... 85 6.2.4 Automatic environmental monitoring ...... 86 6.3 Wastes outlets signs and management...... 88 6.4 Management of technical documents...... 90 6.5 Acceptance contents of environmental protection “three concurrence” of the planned and “new bringing along the old” projects...... 91 7. Public Involvement...... 96 7.1 Purpose and action of public involvement ...... 96 7.1.1 Purpose of public involvement...... 96 7.1.2 Action of public involvement...... 96 7.2 Methods, investigation and people to be visited of the public involvement...... 96 7.2.1 Methods of public involvement...... 96 7.2.2 Investigation items of the public poll...... 97 7.2.3 Composition of the public poll...... 97 7.3 Result of Public Poll...... 120 7.3.1 Statistics of the Poll...... 120 7.3.2 Public Suggestions and Demands ...... 120 7.3.3 Analysis of Objections ...... 122

3

8. Assessment conclusions...... 123 8.1 Overview of the current status of Meishan Iron and Steel Company ...... 123

8.1.1 Basic situation ...... 123 8.1.2 Discharge of main pollutants from existing facilities ...... 123 8.2 Overview of the intended project...... 125 8.2.1 Main construction content and compliance to industrial policy ...... 125 8.2.2 Compatibility between urban planning and environmental planning ...... 128 8.2.3 Main pollution control measures and environmental protection investment of intended project...... 128 8.2.4 Total discharge of pollutants in the intended project...... 129 8.3 Main conclusions on topic-specific assessment...... 130 8.3.1 Assessment on the feasibility of environmental protection measures...... 130 8.3.2 Assessment conclusions on clean production...... 131 8.3.3 Assessment on up-to-standard pollutant discharge and total amount control . 132 8.3.4 Conclusions on the feasibility of site selection ...... 133 8.3.5 Assessment conclusions on current status of ambient air quality and impact. 133 8.3.6 Assessment conclusions on the current status of water environmental quality and impact analysis ...... 135 8.3.7 Assessment conclusions on the current status of sound environmental quality and impact ...... 135 8.3.8 Conclusions on analysis of solid waste discharge and impact ...... 136 8.3.9 Analysis of environmental impact in construction period...... 136 8.3.10 Analysis of environmental risks ...... 136 8.3.11 Analysis conclusions on economic benefit of environmental impact ...... 136 8.3.12 Public participation and conclusions...... 137 8.4 General conclusion...... 137 8.5 Suggestions...... 139

4

1. General

1.1 Overall presentation of project Shanghai Meishan Iron and Steel Co., Ltd. (hereinafter referred to as Meishan Iron and Steel Company), formerly affiliated to Shanghai Economic Commission, is an enterprise with sole state investment. Meishan Iron and Steel Company became a subsidiary of Baosteel Co., Ltd. when it was formed by the state in 1998, and in May 2005, it became a holding subsidiary of Baosteel Co., Ltd., as one of the 512 large scale state-owned enterprises receiving prior support by the State Council. During the 1990s, with the approval by the State Planning Commission, Meishan Iron and Steel Company used national loans with discounted interest rates in the technical transformation for over a decade in succession, and the production and technical equipment and the automatic control level of the Company reached the advanced level in China, some reaching the advanced international level, especially in the construction of steel melting, continuous casting, hot rolling and blast furnace system projects and the associated works, thus greatly upgrading its actual production capacity, and the technical content and added value of products. Meishan Iron and Steel Company has become a large scale iron and steel complex with the complete production flow of coking, sintering, iron melting, steel melting, continuous casting and steel rolling. In 2004, Meishan Iron and Steel Company had total assets of 13,225 billion yuan, and its steel output reached 3 million tons. At present, although Meishan Iron and Steel Company has the overall production capacity of 2,980,000t/a iron, 3000,000t/a steel and 2,890,000t/a hot rolling plates and coils, with the equipment reaching the advanced level in the country, it can only produce hot rolling products because its product matrix is not quite rational, therefore its profitability ability is not strong, and it is vulnerable to market risks. In the meantime, as Meishan Iron and Steel Company was one of the iron making bases of Shanghai before it became a subsidiary of Baosteel in 1998, its systems for making iron already had a long operation life and the key production facilities have become aged, with equipment level at comparatively backward level, and they have the problems of high overall energy consumption, low comprehensive utilization rate of resources and poor environmental quality. According to the new industrial policies of the state, the requirements for sustainable development of national economy and the strategies of Baosteel Co., Ltd. for its new round of growth, Meishan Iron and Steel Company will take the opportunity of Baosteel Co., Ltd. to speed up the construction of high quality steel products manufacture system and to further advance the construction of high grade steel plate production base, make the upgrading and transformation of system equipment upgrading as the start point on the platform of rational, professional and large scale division of work in Baosteel, introduce new processes, new technologies and new equipment to a rational extent with the world first-rate iron and steel production technological and research and development ability of Baosteel, to further reduce the overall energy consumption, improve the environmental quality and increase the overall

5

competing power of Meishan Iron and Steel Company. For this purpose, Baosteel has decided to implement the project “Product matrix and process equipment upgrading and technical transformation project of Meishan Iron and Steel Company of Baosteel Co., Ltd.” with Meishan Iron and Steel Company as the leading investor and mainly on the existing factory areas of Meishan Iron and Steel Company, with small amount of land requisition in the surrounding areas. After the completion of this project, the production scale of Meishan Iron and Steel Company will be pig iron at 5,370,000t/a, converter steel (billets for continuous casting) at 5,300,000t/a, and steel materials at 5,030,000t/a, with sales amount reaching 7832.488bwy and profit 2132.89 million yuan; it will realize sufficient utilization of resources and the main economic indicators will be at the advanced level both at home and internationally. Therefore, it is necessary to perform the following upgrading and rectification and correction with an investment of 19.80539 billion yuan on the existing foundation of steel output of 3,000,000t/a: Add one 380m2 sintering strant, for annual output of sintered ores of 3,912,000t, increasing the total output of sintered ore of the whole Company to 8,752,000t/a; Add one 3200m3 blast furnace, for annual output of molten iron of 2,464,000t, increasing the total output of molten iron of the whole Company to 5,374,600t/a; Construct 2 sets of 2×55-duct coke ovens and 2×140t/h dry coke quenching ovens, for annual coke output of 2,133,000t, with one set of coke oven constructed for Shanghai No. 1 Steel Works, and upon their completion, the total coke output will be 3,200,000t/a, with 1,000,000t supplied to Shanghai No. 1 Steel Works; Add one 150t converter and one 150t dephosphurizing converter, for annual molten steel output of 2,359,000t/a, increasing the total output of molten steel of the whole Company to 5,452,000t/a; For the continuous casting system, add one 2-unit 2-strand thin slab continuous casting machine for annual output of 2,300,000t on-spec slabs, bringing the total output to 5,300,000t/a on-spec slabs plus the existing Nos. 1 and 2 continuous casting machines Add a 1700mm class hot rolling strip mill; Add a 1550mm cold rolling system and hot rolling, pickling and hot galvanizing system, with a production scale of 1800,000t/a; Add a 2×220t/h gas – steam combined cycle power generating unit with excessive gas; Transform and expand other associated production facilities, including the lime kiln, raw materials yard and jetty. Meishan Iron and Steel Company attaches great importance to environmental protection for the proposed project. According to the relevant provisions in the “Environmental Impact Assessment Law of the People's Republic of China” and “Environmental protection management decree for construction projects”, environmental impact assessment shall be performed for the project in its feasibility study phase. Therefore, Meishan Iron and Steel

6

Company entrusted Central Research Institute of Building and Construction, MCC Group and Nanjing Municipal Environmental Protection Scientific Research Institute in Dec. 2004 to undertake the work to prepare the environmental impact report for this project. After accepting the entrustment, the assessing institutes performed field surveys, investigations and studies, collected and verified relevant information and data, and prepared the environmental impact assessment program according to the relevant information of the project, the natural environmental conditions and social and economic status of the location for the proposed project. The program was approved by the environmental engineering evaluation center of the National Environmental Protection Bureau on 2005-4-1. In July 2005, after an evaluation of the “feasibility study report” of the former project, the Company suggested, based on the belief that the project has good conditions both internally and externally, that the production capacity be expanded as appropriate on the existing basis (for details of adjustment, see Table 1-1). In response to this suggestion, the owner entity made minor adjustment to the construction scheme, and promptly submitted a report to the State Commission of Development and Reform and the National Environmental Protection Bureau, which granted approval. The assessing institutes prepared the Report on the basis of the program, the approval comments for the program and the construction scheme after adjustment. On Sept. 9, 2005, the the environmental engineering evaluation center of the National Environmental Protection Bureau organized experts to conduct a technical review on the Report, and proposed modification comments in the review. The present Report is a version revised according to the review comments. The adjustments to the scheme after approval of the program are as detailed in Table 1-1. Table 1-1 Adjustments to the construction scheme after approval of the program Former scheme Scheme after adjustment “Expansion for 2Mt/a “Product matrix and process Description of works sheet and associated equipment upgrading and technical project for Shanghai transformation project of Meishan Meishan Iron and Steel Iron and Steel Company of Baosteel Co., Ltd.” Co., Ltd.” sintering strant 312m2 380 m2 Blast furnace 2500m3 3200m3 1×150t converter + 1×150t Converter 1×150t dephosphorizing converter Content Power generation Cancel the CCPP and change it to CCPP with gas 2×220t/h gas boilers Tar processing 300,000t/a Cancelled Steel output of the 2,000,000t/a 2,300,000t/a proposed project

7

1.2 Analysis on the compatibility of the project with industrial policies and local development planning

1.2.1 The proposed project conforms to the industrial development policies of the state On July 8, 2005, the state issued the “Development policies for iron and steel industry”. Comparing with the provisions in these policies, the construction policies and scale of the project meet the requirements in these policies. (1) Requirements in the technical policies for the industry The sintering strant shall have a usable area of 180m2 and over; the coke oven coking chamber shall have a height of 6m and over; the blast furnace shall have an effective volume of 1000 m3 and over; the converter shall have a nominal volume of 120t and over; and the electric furnace shall have a nominal volume of 70t and over. For a new project, the blast furnace must be provided with the associated blast furnace residual pressure power generating unit and coal powder sprouting and blowing device; the coke oven must be provided with the associated the associated dry coke quenching unit, dust collecting unit and coke oven gas desulfurization unit; the coke oven, blast furnace and converter must be provided with the associated gas recovering unit, and the electric furnace must be provided with the associated smoke and dust recovering unit. An iron and steel complex shall reach the following technological and economic indicators: overall energy consumption per ton of steel: less than 0.7t std. coal for blast furnace flow, less than 0.4t std. coal for electric furnace flow, less than 6t of fresh water per ton of steel for blast furnace flow, less than 3t of fresh water per ton of steel for electric furnace flow, with water recycling rate over 95%. For other iron and steel enterprises, the energy consumption level shall reach the average level of major large and medium iron and steel enterprises. An enterprise shall build comprehensive treatment systems for waste water and slag according to the requirements for the development of recycling economy, adopt energy and resources recovering and recycling technologies for flue gas, dust and slag such as dry coke quenching, recovery and utilization of gas from coke ovens, blast furnace and converter, gas – steam combined cycle power generation, power generation with residual pressure of blast furnace and vaporizing cooling, to increase the energy utilization efficiency and resources recycling rate and to improve the environment. There shall be ready external conditions such as ore, coke, water supply and communications and transport. (2) Policy objective requirements In Article 3 of the “Development policies for iron and steel industry”, it is pointed out that: “We should, through the readjustment of organizational structure of the iron and steel industry, implement merging and restructuring, to expand the scale of backbone enterprise groups with comparative superiority and increase the concentration of the industry. By the year 2010, the number of iron and steel melting and making enterprises shall be substantially reduced, and the proportion of steel output from the top ten iron and steel enterprise groups in the country

8

shall be over 50% of the national total, and this proportion shall be over 70% by the year 2020.”

It is pointed out in Article 5 that: “Iron and steel enterprises must develop power generation with residual heat and energy. An iron and steel complex sized at 5 million t/a shall endeavor to become self sufficient in power supply and also to supply power to the outside.” (3) Industrial layout adjustment requirements In Article 11 of the “Development policies for iron and steel industry”, it is pointed out that: “The steel market in East China has great potentials, but there layout of iron and steel enterprises in this region is in excessive density. Large backbone enterprises with comparative superiority in this region can endeavor to increase the production concentration and international competing power in conjunction with organizational and product matrix readjustment.” It is pointed out in Article 20 that: “We support and encourage all large enterprise groups with ready conditions to implement alliance and regrouping, and by the year 2010, there shall be some extra large enterprise groups with international competing power, with two at 30 million t/a and a number of them at 10 million t/a levels. It is pointed out in Article 21 that: “The state supports large iron and steel complexes after alliance and regrouping with reach conditions to expand the production scale as appropriate through readjustment and industrial upgrading, to increase the extent of concentrated production, and policy-based supports will be offered in the separation of primary and supporting systems, diverting of personnel and social guarantees.” (4) Access conditions for coking industry The State Commission of Development and Reform has published the access conditions for the calcium carbide, iron alloy and coking industries (Bulletin (2004) No. 76 of the State Commission of Development and Reform), and also specified the market access conditions for coking production as follows: The site of a new and transformed or expanded coking enterprise shall be close to the user and coking raw coal base, and must conform to the development planning for the coking industry of the provinces (autonomous regions and municipalities). No coking enterprise shall be built within 2km from the boundary of a city planned area (except for supplying gas to urban residents), within 1km from the banks of main rivers, on both sides of trunk highways, concentrated residential areas and food and drug producing enterprises for which pollution should be strictly prevented, and in ecological protection zones, natural reserves, scenic tourist zones, cultural relics reserves and potable water source protection zones as specified by the State Council and relevant state authorities and by the people’s governments of various provinces (autonomous regions and municipalities). The product matrix and process equipment upgrading and technical transformation project of Meishan Iron and Steel Company will consist of the following new items: one 380m2 sintering strant, one 3200m3 blast furnace (with associated TRT and coal powder spray and blowing), 2

9

sets of 2 ×55-duct coke ovens (with coking chamber height at 6m, and provided with 2×140t/h dry coke quenching units. The project is 1.2km to the east bank of Yangtze River Banqiao Section), one 150t converter and one 150t dephosphorizing furnace, one 2-unit and 2-strand thin slab continuous casting machine for 2,300,000t/a on-spec slabs, the 1700mm class hot rolling strip mill, 1550mm cold rolling system and hot rolling pickling hot galvanizing system and other associated production facilities. In the proposed project, the overall energy consumption ton of steel will be 0.683t std. coal, and fresh water consumption ton of steel 4.7t; it will adopt the dry coke quenching process, the gas from the coke oven, blast furnace, converter will be recovered and reused, and the residual gas will be used for gas and steam combined cycle power generation. The energy and resources recovering and recycling technologies for flue gas, dust and slag such as power generation with residual pressure of blast furnace and vaporizing cooling will be adopted. It will fully meet the technical requirements in the industrial policies. Also, as Meishan Iron and Steel Company is affiliated to Baosteel Co., Ltd., which is an extra-large iron and steel enterprise group of China, the industrial policies encourage it to expand as appropriate, and require that the affiliated enterprises to conduct adjustment and upgrading of product matrix, to further increase its international competing power. Therefore, this project conforms to the objectives and industrial layout adjustment requirements in the industrial policies. 1.2.2 The proposed project conforms to the requirements for industrial development policies of the state for metallurgical industry The product matrix and process equipment upgrading and technical transformation project of Meishan Iron and Steel Company is aimed at making products with high added-value and to substitute import, and brand products of sheets for light industry and household electrical appliances, steel for high, medium and low buildings and structural steel, medium and low grade silicon steel, container plates, hot rolling pickled plates and other cold and hot rolling plates and coils through technical transformation and rational completion of process lines and raising the overall process and technical equipment levels, and market these products, establish reputation and bring better economic efficiency for the enterprise. (1) The proposed project conforms to the "Eleventh Five-year Plan" for the metallurgical industry According to the current industrial development policies and technical policies of the state, during the "Eleventh Five-year Plan" period, the development of the metallurgical industry will be centered on structure adjustment, including the adjustment of process technology and equipment structure, product matrix and organizations. Through adjustment of process technology and equipment structure, it will be possible to develop steel products in urgent need in the country, and to raise the overall technical and equipment level of the industry as a whole and in various enterprises. During the "Eleventh Five-year Plan" period, the iron and steel industry will focus on developing 13 steel products, including: ① Hot rolling sheet: The emphasis is to encourage the transformation and construction of continuous hot rolling mills for hot rolling sheet less than 2mm and units for hot rolling

10

pickled sheet and plates. (The present demand for thin hot rolling wide strip steel with thickness below 2mm is over 5,000,000t, which mainly depends on import as the domestic production capacity is not sufficient.) ② Cold rolling sheet: The existing production lines will be transformed using new technologies such as plate profile control, precision thickness control, coating thickness and homogeneity control and surface finishing, and the production capacity will be increased as appropriate (the present domestic consumption is 11,000,000t, which can only be met by 50%). This shows that the construction of the product matrix and process equipment upgrading and technical transformation project of Meishan Iron and Steel Company and its products will conform to the development policy requirements of the state for the metallurgical industry during the "Eleventh Five-year Plan" period, and this will enhance the in-depth processing ability of Meishan Iron and Steel Company, increase the added values of its products, and makes its product matrix more rational. While the enterprise increases its competing power on domestic and international markets, it will also lessen the supply shortage on the domestic market, and save foreign exchange required to import such products for the state. (2) The proposed project conforms to the “Industrial structure adjustment planning outline for the ‘Eleventh Five-year Plan’” of the state It is emphasized in this outline to: increase the key steel varieties of cold rolling sheet, stainless steel sheets, galvanized sheets and plates, cold rolling silicon steel sheets, high quality alloy steel,……; popularize such technologies as dry coke quenching, pre-treatment of molten iron and refining outside the furnace. The construction of the proposed project conforms to the requirements in the “Outline”. (3) The proposed project matches the main points of fixed assets investment in present industrial and commercial fields The “Main points of fixed assets investment in present industrial and commercial fields” encourage the development of the following key steel varieties: -- Hot rolling sheets for automobiles, cold rolling sheets, galvanized sheets, refining with vacuum degassing, and improved galvanizing thickness, to make high quality products in conjunction with technological development; for cold rolling stainless steel sheets, transform the cold smelting and refining outside furnace, add continuous casting, transform hot continuous rolling mill and import spit shine annealing line, to improve the quality of stainless steel sheets; for bearing steel, gear steel, die steel and drill steel, the product quality will be improved through the “four-in-one” system transformation of extra high power electric furnace, refining outside furnace, continuous casting and high precision continuous rolling mills. The proposed project matches the “Main points of investment”. (4) In the “Catalogue of major industries, products and technologies currently encouraged by the State (2000 Rev.)”, a detailed list is given for 440 products and technologies and some

11

infrastructures and services encouraged by the state for development in 29 fields. In Item 14 for iron and steel, the encouraged products include the following:

Production of cold rolling silicon sheets, thin slab and thin strip slabs and other near terminal continuous casting and tandem rolling, zinc, aluminum and tin plated, color coated and composite coated sheets and plates. The product orientation of the proposed project conforms to this requirement. 1.2.3 The proposed project conforms to the overall planning of Baosteel Co., Ltd. According to the development program of all subsidiaries of Baosteel Co., Ltd. during the "Eleventh Five-year Plan" period, Baosteel Co., Ltd. will have five hot rolling systems completed or to be constructed, all of conventional tandem rolling type. In overall consideration for the planning of Baosteel Co., Ltd. as a whole, the product varieties and sizes of these systems should be well arranged for complementary supply, and the products should have their own characteristics. For the 1700 class thin slab continuous casting tandem rolling to be built in Meishan Iron and Steel Company, to bring into full play the process characteristics of thin slab continuous casting tandem rolling, the products to be made will be medium and low grade non-oriented silicon steel, steel for building purpose and special-purpose steel. The thin slab continuous casting tandem rolling mill is good at making extra-thin extra low carbon steel coils with ferrite production process, to really realizing substituting some cold rolling products with hot rolling products. It is also possible to further develop and produce extra low carbon and extreme low carbon steel and Phase Transformation Induced Plasticity (TRIP) steel and dual phase (DP) steel coils for automobiles. 1.2.4 Analysis of compatibility of the proposed project with overall urban planning According to the “Overall urban plan for Nanjing Municipality” (1991~2010), the function of Banqiao New Town (location of the proposed project) is set as a comprehensive industrial town in the metropolitan development zone, and its industrial function is set as: the metallurgical, machine building and processing industries and commercial and trading will be encouraged, and construction of projects with serious pollution to water body is prohibited. In the “Main points of overall planning for Banqiao New Town”, it is pointed out that, for the near term, with the Banqiao Subdistrict and Shanghai Meishan Iron and Steel Co., Ltd. of Baosteel as the backup, the emphasis of development will be placed on the area to the west of Nanjing – Wuhu highway and to the north of Meishan Iron and Steel Company, and for the far term, it will expand gradually from the north to the south and from the west to the east. With the traffic corridor from Nanjing to Wuhu, the dedicated railway line for Meishan Iron and Steel Company and natural topography, Banqiao New Town is divided into three major functional blocks: Yuhua Economic and Technological Development Zone block (northwest block, land for industrial use), Meishan block (southwest block, land for industrial use) and east town block (land for residential purpose). The northwest block is a processing industrial park mainly for industries, warehousing and urban engineering facilities, the southwest block will mainly for Meishan Iron and Steel Company and its extended processing industries, and the east town block is mainly for residential and living purpose. 12

In the “Overall plan in development of areas along the Yangtze River of Nanjing Municipality”, the industrial development goals are set as: to achieve substantial results in internationalization, modernization and scale growth of industries, markedly upgrade the industrial competing power, and basically form the overall framework as an advanced manufacturing base of world level. The industries will be further concentrated, the industrial competing superiority in the province and in Yangtze River Delta will be set up, and the sales income of five main industrial sectors of petrochemical, electronics and IT, automobiles, iron and steel and power generation in 2010 will be redoubled than that of 2002, being 500 billion yuan, with the total investment during 2003 ~ 2010 being about 300 billion yuan. The five main industrial sectors of petrochemical, electronics and IT, automobiles, iron and steel and power generation will be made bigger and stronger by adhering to the strategy of taking industry as the primary for new type of industrialization, and advancing the construction of industrial clusters along the Yangtze River. For the iron and steel industry, the superiority of the golden waterway and the existing industrial foundation should be brought into play, to speed up the pace of internationalization, modernization and scale growth of the industry, and foster it as an important pillar industry in Nanjing. The product matrix shall be adjusted and products upgraded, to form product series, with emphasis on the development of wide medium and thick plates, hot (cold) rolling stainless steel sheets (coils), corrosion resisting coated plates and other refined and high quality products. It can be seen from the above analysis that the proposed project conforms to the overall development planning for Nanjing. 1.2.5 Analysis of compatibility of the proposed project with environmental planning In the “Environmental protection plan in development of areas along the Yangtze River of Nanjing Municipality”, it is pointed out that industrial enterprises with serious pollution to water should be arranged downstream the city and water source, and industrial enterprises with serious air pollution should be arranged in the leeward direction of the city. According to the cyclic economy mode, industries with no or little pollution and high added values will be encouraged, to realize zero increase and even decrease in total pollution while maintaining rapid economic growth. Environmental impact assessment and the “three simultaneousness” system will be strictly implemented, to strengthen the control of total amount of pollutant and the efforts on pollution rectification. High and new technologies will be adopted to transform traditional chemical and metallurgical industries, clean production technologies be promoted, and the certification of ISO14000 environmental management series standards will be pushed ahead. The proposed project is for metal melting and rolling industry, which produces serious air pollution. Banqiao where the proposed project is located is in the leeward direction of Nanjing urban area, therefore the site location conforms to the principle in “Environmental protection plan in development of areas along the Yangtze River of Nanjing Municipality” that industry with serious air pollution should be arranged in the leeward direction of the city whenever possible.

13

1.3 Working procedure for assessment The working procedure for the proposed project is as shown in Fig. 1-1.

1.4 Basis of preparation 1.4.1 Laws and regulations of the state (1) “Environmental Protection Law of the People's Republic of China”; (2) “Environmental Impact Assessment Law of the People's Republic of China”; (3) “Water Pollution Prevention Law of the People's Republic of China”; (4) “Atmospheric Pollution Prevention Law of the People's Republic of China”; (5) “Solid Waste Pollution Environment Prevention Law of the People's Republic of China”; (6) “Environmental Noise Pollution Prevention Law of the People's Republic of China”; (7) “Clean Production Promotion Law of the People's Republic of China”; (8) “Environmental protection management decree for construction projects” (State Council Decree No. 98-253); (9) “Circular of opinions on strengthening the industrial water saving work” (Document Guo Jing Mao Ziyuan [2000] No. 1015 from six commissions, ministries and bureaus of the state including State Commission of Economic Relations and Foreign Trade); (10) “Program for industrial water saving during the ‘Tenth Five-year Plan’” (Document Guo Jing Mao Ziyuan [2000] No. 1017) (11) “Some opinions on implementing clean production” (Document of National Environmental Protection Bureau, Huan Kong [1997] No. 0232); (12) “Guideline of key fields for industrialization of high technologies for prior development at present” (State Commission of Development and Planning, Ministry of Sciences and Technologies, 2004); (13) “List of construction projects for classified management in environmental protection”, Decree of National Environmental Protection Bureau 2002- No. 14; (14) “Reply approval by the State Council on relevant issues about acid rain control areas and sulfur dioxide pollution control areas” State Council Guo Han [1998] No. 5, Jan. 20, 1998; (15) “Circular on some opinions to stop blind investment in iron and steel, electrolytic aluminum and cement industries”; Document [2003] No. 103 of the General Administration Department of the State Council; (16) “Urgent circular on some opinions about sorting out and normalizing the coke industry”; State Commission of Development and Reform and other authorities, Teji Fagan Chanye [2004] No. 941; (17) “Circular on relevant issues to further strengthen coordination and cooperation in industrial policies and credit policies to control credit risks”; State Commission of Development and Reform, Fagan Chanye [2004] No. 746; 14

Project approval document Overall plan of Catalog for Engineering documents of the city environmental the proposed project protection classified Other approval documents management 管 Determine assessment class

Assessing unit accepts the Industrial policies of the state Entrusted by owner entrustment entity

Determine the assessment Prepare the environmental impact standard assessment program

Environmental protection laws and regulations Expert consultation meeting organized by environmental protection authority Consultation comments Clean production standard Comparison survey and Confirm and approval by data retrieval Site survey and data collection EP authority Implementation of special topic plans Environmental quality status quo survey and monitoring Unfold work according to Public program participation Engineering documents of existing projects Model calculation Engineering documents for comparison Total amount Prepare environmental impact indicators report Cooperate by EP dept. of enterprise EP authority organizes expert review meeting for review

If modification or supplement is required

Review and approval by EP authority of government If modification or supplement is required

Submit environmental impact report for project

End of mission

Fig. 1-1 Block diagram of environmental impact assessment work procedure

(18) “Access conditions for the calcium carbide, iron alloy and coking industries” Bulletin (2004) No. 76 of the State Commission of Development and Reform (19) “Circular on some opinions to clean up projects in iron and steel, electrolytic aluminum 15

and cement industries”; State Commission of Development and Reform, Fagai Gongye [2004] No. 1791;

(20) “Development policies for iron and steel industry”, Decree No. 35 of State Commission of Development and Reform, July 8, 2005; (21) “Technical guideline for environmental impact assessment” HJ/T2.1~2.3-93 and HJ/T2.4-95; 1.4.2 Local laws and regulations (22) “Some provisions on strengthening environmental protection management for construction projects” (Document of Environment Commission of Jiangsu Province [98] No. 1); (23) “Tentative regulation on control of total amount of pollutant emission in Jiangsu Province” (Jiangsu Provincial Government Decree [1993] No. 38) (24) “Circular on printing and distributing the ‘Management measures on pollutant emission port setup and normalized control and rectification in Jiangsu Province” (Su Huan Kong [97] No. 122); (25) “Reply approval on classification of functional types of surface water environment in Jiangsu Province” (Document Su Zhengfu (95) No. 93); (26) “Circular on relevant matters for implementing the national standards for atmospheric environment” (Document Su Huan Ke [96] No. 27). 1.4.3 Relevant documents and data (27) “Overall urban plan for Nanjing Municipality” (Nanjing Municipal Planning Bureau, Aug. 2001); (28) “Overall plan for development of areas along the Yangtze River of Nanjing Municipality”; (29) “Environmental protection plan in development of areas along the Yangtze River of Nanjing Municipality”; (20) “Overall plan for Banqiao New Town” (Nanjing Municipal Planning and Design Research Institute, July, 2001); (31) “Project application report for the product matrix and process equipment upgrading and technical transformation project of Meishan Iron and Steel Company of Baosteel Co., Ltd.” (Zhongye Saidi Engineering and Technology Co., Ltd., July, 2005); (32) Letter of entrustment for environmental impact assessment work (Meishan Iron and Steel Co., Ltd.). 1.5 Purposes and requirements of assessment (1) In conjunction with the industrial policies of the state and the status quo characteristics of Meishan Iron and Steel Company, assess the role and feasibility of the project construction to mitigate pollution and realize sustainable development for Meishan Iron and Steel Company 16

through the analysis of the content of the proposed project. (2) Through the analysis of pollution factors of the project, know and assess the quantitative and qualitative role of the project after completion in the environmental quality impact to Banqiao area where the project is located, and verify again the pollution source emission conditions of Meishan Iron and Steel Company. (3) Through status quo environmental survey and monitoring, know the status quo of environmental quality of the project area, and predict and assess the extent and scope of possible impact of the proposed project to the surrounding environment in conjunction with the pollution analysis results of the project. (4) According to the engineering analysis and impact prediction assessment results, perform justification and evaluation on the process plans and the environmental protection measures to be adopted for the project, and propose further countermeasures and suggestions to control pollution and to mitigate and eliminate adverse impact. (5) Provide definite conclusion on the feasibility of the construction of the project based on the above assessment results and from the environmental protection point of view. (6) In the assessment work, contact with the construction and design entities and relevant local organizations must be strengthened, to achieve mutual support and cooperation. In the assessment, existing data shall be made full use, to save time and shorten the assessment work period and meet the construction schedule requirements. (7) In conjunction with the local development and environment plans, the basic principles of “clean production”, “recycling economy”, “emission after meeting standard”, “pollution prevention”, “bringing the existing ones to meet the standard by new ones”, “total amount control” and “increasing the production without increasing pollution” will be carried out in the assessment work. (8) The assessment work shall, from the beginning to the end, follow the principles of solving specific problems, adhering policies, and being scientific and fair”, so that the assessment will really play a role to “prevent possible perils and protect the environment”. 1.6 Main contents and points of assessment 1.6.1 Main contents of assessment The main contents of the assessment are: briefs of the project, engineering analysis and analysis of main environmental issues and pollution of the project, assessment on the status quo and impact of the environmental air quality, assessment on status quo of surface water environmental quality, description of ground water environmental quality, assessment on the status quo and impact of acoustic environment, survey on the status quo of solid wastes and impact analysis, evaluation and description of clean production, economic gain and loss analysis for environmental impact, public participation, pollutant emission after meeting standards and total amount control analysis, environmental management and monitoring plans, feasibility justification of environmental protection measures, and countermeasures and suggestions for pollution prevention and control.

17

1.6.2 Main points in assessment work The main points in this assessment work are the following:

(1) Site feasibility analysis and sanitary protection distance analysis; (2) Analysis of main pollutant emission from the project and the environmental protection measures; (3) Assessment on the status quo and impact of atmospheric environment; (4) Water environment impact assessment; (5) Public participation; (6) Clean production level of the project and analysis of its advanced nature of processes; (7) Emission after meeting standards and total amount control analysis.

18

2. General conditions the proposed project and pollution factor

analysis

2.1 Necessity of project construction (1) Briefs of existing project Meishan Iron and Steel Company now has 3×65-duct coke ovens, 2×130m2 + 1×180m2 sintering strants, and 2×1250m3 + 1×1280m3 blast furnaces, with an annual production capacity of molten iron of 3,000,000t; the steel melting system consists of 2×150t converters, one RH furnace, one LF furnace; the continuous casting system consists of 2 slab continuous casting machines, for annual output of slabs of 3,000,000t; the rolling plant is equipped with a 1422mm hot rolling mill, with a production capacity of 3,000,000t. The Company has completed the transformation for the finish rolling and coiling systems for hot rolling, and the technical level of its main production equipment has reached the advanced level in China. For the proposed project one thin slab continuous casting line will added to the existing facilities of Meishan Iron and Steel Company, to increase the cold rolling and hot rolling steel products by 2,300,000t/a, and corresponding systems and facilities for iron processing will also be built, so that the total steel output of Meishan Iron and Steel Company will reach 5,300,000t/a. (2) Necessity of project construction China is now in a rapid economic development period, with a large market for sheets for building purpose. These products mainly include zinc plated sheets, aluminum and zinc plated sheets, color coated sheets, hot rolling and cold rolling sheets. Especially, zinc plated sheets and cold rolling sheets of thin sizes are the steel products with the largest supply shortage, largest import and most outstanding supply to demand contradiction in China. Therefore, expanding the production of steel sheets is in line with the national interest. The product matrix adjustment and process equipment upgrading in Meishan Iron and Steel Company is the need of the strategic positioning of Baosteel Co., Ltd., and an important link for Baosteel to become one of the most competing iron and steel enterprises in the world. Baosteel is now among the world top 500, and it is striving to be one of the top three in the world in terms of comprehensive competing power among iron and steel producers by 2010. To realize this strategic goal and in conjunction with the strategic deployment of Baosteel Co., Ltd. to construct six major bases for fine and high quality products, Meishan Iron and Steel Company will be an important high quality sheets production base of Baosteel Co., Ltd. As the iron processing equipment in Meishan Iron and Steel Company is still at backward level and it can only making hot rolling products despite of its overall steel production scale of 3 million t/a, its product matrix is not quite rational, the profiting ability is not high, and the enterprise is still weak in market competing power and in resisting risks. Therefore, considering the market demand and the development of various units of Baosteel, the product development for Meishan Iron and Steel Company is focused on medium and high grade steel

19

for building purpose and silicon steel (for electrical purpose), especially, emphasis will be placed on the production of sheet materials in the professional and large scale production within Baosteel Co., Ltd., and the superiority of the thin slab continuous casting tandem rolling technology will be used to produce silicon steel, so that it can be complementary with other steel producing units of Baosteel, and also upgrade the comprehensive competing power of Meishan Iron and Steel Company. The output of existing cold rolling and galvanized sheets of Baosteel Co., Ltd. is limited, and after meeting the demand from automobiles and household electrical appliances and the base sheets for existing color coating units, the remaining products cannot meet the market demand for sheets for building purpose. The building industry is just the largest user for sheet materials. As the largest steel supplier in China, Baosteel Co., Ltd. has the conditions to bring into full play the superiority of the group, to organize the production to meet the market demand, while Meishan Iron and Steel Company has the ready conditions to undertake this mission. Adding a cold rolling mill in Meishan Iron and Steel Company aiming at steel for building purpose can further improve the professional division of work in the group and raise the comprehensive competing power of the group. The sustainable development of national economy needs cold rolling silicon steel, and presently in China, it is necessary to replace nearly 900,000t/a of hot rolling silicon steel with low cost cold rolling silicon steel. Sheet continuous casting technology will provide conditions to further lower the cost of raw materials for silicon steel. For the production of cold rolling silicon steel in Meishan Iron and Steel Company, the expanded sheet continuous casting machines can supply the raw materials, to reduce the production cost for silicon steel. The product matrix adjustment and process equipment upgrading in Meishan Iron and Steel Company is the need from industrial policies and the development of recycling economy. By bringing up the old with the new and the rational use of new technologies, new processes and new equipment, the overall energy consumption and production cost of Meishan Iron and Steel Company can be reduced, the production environment can be effectively controlled and improved, and the overall utilization rate of resources can reach a new level, so that the environmental quality and resident living quality in the surrounding area can be significantly improved, to achieve a harmonious win-win result for both the enterprise and the natural environment, realize concurrent improvement in social efficiency, economic efficiency and environmental efficiency, and to attain the goal of developing the recycling economy. (3) Favorable conditions for project construction There are complete front process conditions in Meishan Iron and Steel Company. The rough mill transformation is under way for the 1422mm hot rolling section, for supplying raw materials to the cold rolling plate plant of Baosteel Co., Ltd. The raw materials for wide sheets required in building market and silicon steel can be supplied by the sheet continuous casting tandem rolling mill under expansion. Therefore, the new cold rolling mill of Meishan Iron and Steel Company will have a steady and sufficient source of hot rolling raw material. Baosteel Co., Ltd. now has five high level cold rolling mills, and it has trained a large number of professional personnel for cold rolling mill construction, operation, management

20

and equipment maintenance, product development and marketing, which can ensure the smooth construction and operation of the cold rolling mill of Meishan Iron and Steel Company. Less land is required for the expansion of a cold rolling project by the existing 1422mm hot rolling mill of Meishan Iron and Steel Company. Meishan Iron and Steel Company has good capital supply conditions, hence sufficient capital guarantee can be provided for the construction of the cold rolling mill. Meishan Iron and Steel Company is located in East China and is affiliated to Baosteel Co., Ltd. Its equipment upgrading and product matrix adjustment is in line with the requirements in the latest “Development policies for iron and steel industry” of the state. 2.2 Environmental protection control and rectification plan to bring up the old with the new In Meishan Iron and Steel Company in 2004, the overall energy consumption per ton of steel was 0.82t std. coal, fresh water consumption 12.1m3/t steel, smoke and dust emission 3.56kg/t steel, and SO2 emission 6.2 kg/t steel. This shows that the environmental protection and energy consumption indicators are at a fairly backward level. Therefore, concurrent with the construction of the proposed project, it is necessary to implement technical transformation for the backward facilities of the whole plant in a way to bring up the old with the new, to substantially lower the energy consumption, water consumption and pollutant emission amount. The main measures are the following: (1) To realize the goal of fresh water consumption per ton of steel at 5m3 and to substantially cut the water pollutant emission, technical transformation will be implemented for the water systems of level II plants, to stop direct flow water systems as far as possible and replace them with recycling water systems; the recycling water systems with low recycling rate will also be transformed, to realize tandem discharge and raise the recycling rate. It is planned to build a new recycling water treatment facilities. It will be sized at 10×104m3/d. All waste water from production units and processing systems, and backwash water from the filtering tank in the water works will be recycled after treatment. The recycled water will mainly be used in the iron processing systems, as makeup water to circulating water systems and for cooling furnace slag and for spraying in raw materials yard. After the transformation, the fresh water consumption per ton of steel will be 4.7t/a, and the total fresh water consumption for both production and living purpose will be 4868m3/h, or 42,643,680 m3/a (including that for the co-gen power plant and Meishan Chemical Company). (2) It is planned to completely demolish the existing 3×65-duct coke ovens, which will be replaced by the new 2×55-duct large volume coke ovens, with coke output remaining unchanged. In the meantime, corresponding chemical product recovery unit and gas refined desulfurization facilities will be added, to basically eliminate the non-organized discharge from the coke oven, so that the hydrogen sulfide content in the coke oven gas will be less than 0.2g/m3, and the phenol and cyanogen containing waste water will be recycled after treatment without discharge. (3) At present, the co-gen plant of the Company has four 220t/h boilers, with one fired all by blast furnace gas, and the other three by mixed coal and blast furnace gas at 30%. Although 21

the raw coal only has a sulfur content of 0.4%, there is a SO2 discharge of 3190t per year. After the construction of the proposed sintering project, the total SO2 discharge of the Company will exceed the total amount control indicator (19000t/a) as specified by the environmental protection bureau. To effectively reduce the SO2 discharge of the Company, it has been planned to provide desulfurization devices for the three coal-fired boilers of the power plant. (4) The phenol and cyanogen waste water treatment station of Meishan Chemical will be transformed, and the A/O2 treatment process will be adopted, to treat all phenol and cyanogen containing waste water from the new and existing works, for a capacity of 300m3/h. The outflow water, as meeting the standard, will be recycled for slag sluicing for blast furnaces. (5) Overall control and rectification will be conducted for the blast furnace discharge yard, coking and sintering materials yard, raw materials yard, lime yard, slag yard, jetty and coal shed, by providing complete dust suppressing and removal facilities, adding fences, shed and hard pavement road, and providing water sprinkling facilities, so that the non-organized dust rising can be basically put under control. 2.3 Pollution factor analysis for the proposed coking project (1) Briefs of project Meishan Iron and Steel Company now has 3×65-duct coke ovens, producing 1,205,000t of coke in 2004. To meet the demand from increased steel output of 2,300,000t/a, it has been determined that the overall scale of the associated coking project will be 2,133,000t/a of dry complete coke, with 1 million t/a to be supplied to Shanghai No. 1 Steel Works. The coke ovens will be of 4×55-duct Model JN60-6 combination, and they will also be completed with the associated coal preparation, coke sieving, 2×140t/h dry coke quenching, gas refining and chemical products recovery units, as well as the corresponding auxiliary units and utility units. They will recover tar at 101,000t/a, sulfur at 4266t/a, ammonium sulfur at 24263t/a, crude benzene at 28440t/a, and gas at 910,1511 million m3/a. Investment in this Project is 1050.04 million yuan and the project will have a staff of 643 persons. Construction site is located at north part of the existing coking plant of Meishan Steel. (2) Process flow The process flow for coking production is as shown in Fig. 2-1. Coal preparation The coal preparation workshop is designed to store the incoming coal and process it into that meeting the requirements of coke oven production. The washed coal, after going through the coal receiving unit, is conveyed to the batching room for batching, and to the pulverizing room, and finally it is conveyed to the coal storage tower via a belt conveyor through the corridor and transit station, ready to be loaded into the coke ovens. ② Coking process The coal in the storage tower is loaded into the coking chambers by the dust removal and loading cart after metering, and the coal is distilled into coke in the coking chambers at high temperature, and raw gas is produced and collected at the top of the chambers. The raw gas enters the collecting pipe via the riser and bridging pipe, where it is cooled by ammonia water spray, and flows to the gas purifying workshop for further treatment. The gas for heating the coke oven and blast furnace gas is introduced by external pipes. 22

Coke焦 breeze尘 Coke焦 breeze尘、噪噪 and noise Dust焦除 removal库尘 at coke silo

Coke breeze焦尘 、噪噪and noise Coking炼焦煤 coal Coal煤 尘dust Coke干炉焦 silo in front库 of oven Sieving筛焦焦 plant Finished焦焦 coke Coal dust and 成成 煤尘noise、噪噪 Coal煤 场yard Exhaust排排排 mast Dry干干焦干 quenching oven Dust除除 collecto尘 r Coal dust and 煤尘noise、噪噪 Coal煤粉 dust Coal receiving受受煤受 and batching tank Ground除 尘dust 除除除collecting station Coke运焦 conveying车 cart Coke焦尘 breeze Coal dust and 煤尘noise、噪噪 Pulverizer粉粉焦粉 room Dust集集集 collecting尘 pipe Coke拦焦焦 guide 集集集Dust尘 collecting pipe Coke焦粉 breeze Coal 贮storage煤煤 tower Coal除除煤 尘车loading cart with Coke焦干 oven Ground除除除除尘 dust collecting station dust collecting device Smoke烟尘、 andSO dust,、 SONO2、、 焦Coke尘 breeze NO NH CO2 H S2 上上集Riser Exhaust排排排 mast 2、 、 3、 、、 2 、、 Coal煤 尘dust NHBaP3 andCO noiseH 2S BaP、噪噪 Gas collecting集排集 pipe Waste water含洗、 containing 酚、 benzene,氰、 烟烟Stack phenol, cyanide,中、 ammoniaSS的中废 and SS Suction吸排集 pipe Raw荒煤排 gas 高高HP and压 中中LP Smoke,烟尘 dust、 SO and ammonia water SO 2 Noise噪噪 Primary初初除 cooler 2

Intermediate Elect电捕焦捕除ric tar trap Ammonia中中氨氨氨氨受 separating and 中间 中中受 clarifying tank ammonia water tank Noise噪噪、 andH H2S 2 鼓焦Blowe风 r 焦捕焦Tar slag 焦捕Tar Tar焦捕焦、 slag and 噪噪noise Absorbed吸吸脱 liquid 蒸中煤Ammonia distilling column Pre-cooling tower 预初煤 Desulfurization脱硫脱再 硫硫硫Sulfur foam缓 liquid再煤 regenerating surging冲受 tank 或排 column Centr氨离氨氨除ifugal separator Filtrate滤脱 Naphthalene洗除洗萘 stripping unit Absorbing吸吸煤 tower

煤排Gas Sulfur硫浆 slurry Concentrato浓浓除 r

Acid制硫 making Tail或排 gas Sulfuric硫硫 acid Saturato饱和除r Acid除硫除 remover Smoke,烟尘 dust,、 SO and noise SO2 、噪噪Benzene stripping Clean净煤排 gas 2 洗洗煤 Fluidizing沸干沸除腾 dryer Smoke, dust column 烟and尘、 SOSO2 Ammonium 2 Tubular集管干 oven Ammonium sulfur sulfur硫铵 硫氨离铵铵 centrifugal pump Waste water treatment Benzene脱洗煤 removal column 污污中水除 station Production再生生产 process Regenerative再再再 slag flow 三排三废 焦、and hydrocarbon烃烃 Slurry,污 noise,泥、噪噪、 waste gas废 and 排 waste、含 water Waste discharge Crude粗洗 benzene containing、 SS, COD,、酚、 phenol氰废 的and cyanide 中 Coke焦干煤排 oven gas or SS COD tail gas 或或排 Fig. 2-1 Schematic of process flow for coking production and pollutant discharge points

23

The waste gas produced during heating of coke ovens is discharged into the atmosphere via the stack.

Dry coke quenching process The ready-made coke in the coking chambers is pushed out by the pushing machine into the coke cart as guided by the coke guide. The coke cart loaded with red coke is towed by the electric locomotive to the bottom of the hoisting shaft of the dry coke quenching unit, and the hoist lifts the coke tanks to the top of the dry quenching oven, where the coke is loaded into the oven. In the dry quenching oven, direct heat exchange is conducted between the coke and inert gas. After cooling, the coke is discharged onto the belt conveyor, which conveys it to the sieving system. The inert gas is recycled after filtering and heat exchange. The dry coke quenching boiler produces steam through heat exchange, and the steam is used for power generation. The process flow of dry coke quenching is as shown in Fig. 2-2.

Red coke

(900℃) Coke cart Primary dust S collector

Power generation Electric dry coke locomotive and steam quenching boiler

Hoist Secondary dust collector S

Coke loading system Feed

water unit water unit Storage chamber Circulating fan Inclined pass G (middle) Cooling chamber S Dry (Lower) (150℃) quenching Gas supply system Heat exchanger Demineralized water Inert gas heat exchange system G Coke discharge unit S

Note: Coke “wates”, including Coke Inert gas G——waste gas (to sieving system) Boiler feedwater W——waste water Steam S——coke breeze

Fig. 2-2 Schematic of dry coke quenching process flow and pollution

24

④ Gas purifying process The gas purifying section consists of the condensing and air blowing, desulfurization, ammonium sulfur, crude benzene, oil depot and associated auxiliary production facilities. The whole purifying process is performed by Meishan Chemical Company. a. Condensing and air blowing and electric trapping The raw gas from the coke ovens flows through the gas and liquid separator, transversal primary cooler, electric tar trapper, and is delivered to the desulfurization section after pressurizing by the blower. The condensate from the gas and liquid separator and transversal primary cooler is sent to the mechanical ammonia separating tank to separate the tar from ammonia, the tar is a finished product and ammonia will be recycled in use. Part of the ammonia water will be sent to the ammonia distilling column of the desulfurization section to extract concentrated ammonia, which will be used as desulfurizing agent. The deposited tar slag is removed by scrapers, and is delivered to the coal preparation system periodically to be mixed into the coal for coking. b. Desulfurization section This system consists of four parts: desulfurization and decyanizing, regeneration of desulfurization liquid, sulfur recovery and ammonia distilling with residual ammonia. The ammonia contained in the coke oven gas is used as the alkali source. Desulfurization is done with FRC process, to reduce the hydrogen sulfide content in gas to below 200mg /Nm3 and sulfuric acid is recovered. The gas from the intermediate naphthalene stripping unit enters the absorbing column, where the H2S and HCN is removed when it is sprayed with absorbing liquid, then it flows to the ammonium sulfur unit. The absorbing liquid from the bottom of the column is sent to the pre-mixing nozzle at the bottom of regenerating column, and then enters the regenerating column after mixing with air. The regenerated liquid flows via the foam separator in the middle of the column to remove the sulfur foam, and is pumped to the heat exchanger for cooling, before being sent back to the top of the absorbing column for recycling. The separated sulfur foam rises to the upper part of the regenerating column, and is discharged into the surging tank via the overflow port. The regenerated tail gas can be directly mixed into the gas pipe downstream the absorbing column. The suspended liquid in the surge tank is delivered to the super centrifugal machine for separation. The separated sulfur paste and filtrate flows respectively into the slurry tank and filtrate tank. The filtrate is pumped to the concentrating unit for concentration and then flows to the slurry tank to mix with the slurry, and the mixture is sent to the acid unit. The ammonia containing tail gas from the concentrating column is delivered to the gas absorbing pipe. Main features of FRC process: High efficiency to remove sulfur and cyanogens. High efficiency pre-mixing nozzles are used in the regenerating column, to reduce the amount of compressed air, the regenerated tail gas can be mixed directly into gas, eliminating

25

secondary pollution. The ammonia in the gas is used as the alkali source without additional alkali, to save operation cost. To avoid accumulated deposit from desulfurization liquid affecting the desulfurization effect, the discharged small amount of waste liquid is sent to the coal preparation section. c. Ammonium sulfur section The gas from the desulfurization section flows into the saturator via the gas preheater. In the upper part of the saturator, gas enters the ring chamber in two streams for spraying by the recycling master liquid, and the ammonia is absorbed by the sulfuric acid in the master liquid. Then the gas is combined into one stream to enter the rear chamber, where it goes through the last spray by master liquid, and enters the cyclone acid remover in the saturator, to separate off the acid mist carried by the gas. Finally it is sent to the light oil trapping device. The master liquid in the upper part of the lower section of saturator is pumped out continuously by the master liquid circulating pump to the ring chamber for spray. The recycling master liquid having absorbed ammonia flows via the central downcomer to the bottom of the lower section of saturator, where the crystal nucleus start to move upwards through the saturated medium, so that crystals grow and grains are sorted. The slurry liquid at the bottom is pumped to the crystallizing tank periodically. The master liquid overflowing from the saturator overflow port flows to the master tank via the liquid seal tank, and is then delivered by the minor master liquid pump to the rear chamber of the saturator for spray. In addition, the master liquid tank can also store master liquid when the saturator is serviced. The slurry liquid in the crystallizing tank is drained to the centrifugal machine, and the separated ammonium sulfur is conveyed to the vibrating fluidizing bed dryer, where it is dried by the heated air, and is then cooled by cold air, before flowing into the ammonium sulfur storage bucket. It is then weighed, packaged and delivered into the finished product store. The filtered master liquid and that overflowing from the crystallizing tank flow by gravity to the lower section of the saturator. The tail gas after drying the ammonium sulfur flows through the cyclone separator before being vented to the atmosphere by an induced draft fan. The ammonium sulfur is weighed and packaged semi-automatically, and is bagged and stacked manually. Main features: the spray type saturator is made of stainless steel, featuring a long service life, and integrating the pickling, acid removal and crystallization, the resistance across the gas system is low, the ammonium sulfur grains are big, with simple flow, advanced process and reliable technology. d. Crude benzene recovery section This system includes the process flows of end cooling, benzene stripping, nathphalene stripping and distillation of benzene containing rich oil to remove benzene. The gas, at 55~65 from the ammonium sulfur saturator, enters first the transversal gas end cooler and is cooled to 26~27 , and then it enters the benzene stripping column to contact in

26

counter flow with the lean oil at 29~30 sprayed from the top, so that the nathphalene and benzene in the gas are absorbed. The clean gas after benzene stripping will be partly supplied to the coke ovens and crude benzene tubular oven for heating in the plant, and the remaining will be conveyed to the gas storage and distribution station, where it is pressurized for supply to the outside. The rich oil having absorbed nathphalene and benzene flows into the rich oil tank at the bottom of the benzene stripping column, and is pumped to the crude benzene oil and gas condensing cooler and lean and rich oil heat exchanger, before being delivered into the tubular oven for heating. When heated to 180~190 , the rich oil enters the benzene removing column for distillation with superheated steam. The oil-gas escaping from the benzene removing column top enters the crude benzene oil and gas heat exchanger and condensing cooler, for heat exchange with rich oil and cold cooling water. The crude benzene obtained enters the oil and water separator, and the separated crude benzene flows into the reflux tank. This crude benzene will be partly delivered by the reflux pump to the top of the benzene removing column to control the quality of crude benzene product, and the remaining will flow from the top of the column to the crude benzene metering tank, pumped to the crude benzene tank by the product pump and periodically to the depot. e. Oil depot The oil depot stores the products of tar and crude benzene, and the raw materials tar stripping oil and concentrated sulfuric acid. The tar and crude benzene respectively from the condensing and blowing section and crude benzene section of the gas cleaning shop will be stored in the respective tanks, and then be pumped to the crude tar processing workshop of Meishan Chemical Company for further processing. (5) Emission of pollutants

The main pollutants from coking process are: smoke (powder) and dust, H2S, SO2, BaP and phenol and cyanogen containing waste water. The smoke (powder) and dust mainly come from the coal preparation system, coal loading during coking, leakage from oven doors, and from coke pushing and sieving; SO2 mainly comes from the combustion chambers of coke ovens; and coke breeze and water vapor from coke quenching; the waste water is the phenol and cyanogen containing waste water from the chemical systems; furthermore, the five major equipment and fans of the coke ovens will produce noise. The gas with coke breeze from the dry quenching oven loading port, discharge port, gas dispersed from the storage chamber and circulating gas fans will all be delivered to the ground dust collection station for dry coke quenching, and be discharged after removing the dust. The coke breeze separated from the primary and secondary dust collectors will be collected in the coke breeze tanks with special conveying equipment, for shipping out later on. The smoke and dust produced when coal is loaded into the coke oven is sucked into the dust collecting vehicle for coal loading, conveyed to the ground dust collection station via dust collecting duct, and is discharged to the atmosphere after dust removal. 27

The smoke and dust produced during coke oven discharge is sucked by the coke guide with dust hooks, conveyed to the ground dust collection station via dust collecting duct, and is discharged to the atmosphere after dust removal. During service of the dry coke quenching system, coke will be quenched with the standby wet method. The coke quenching tower is 45m high, with coke quenching water spray pipes at the bottom and baffled wooden strapping device at the top, so that it can trap the coke breeze and water drops produced during coke quenching, with a dust removal efficiency of over 70%. The phenol and cyanogen containing waste water produced during the desulfurization and refining of gas is treated by the coking waste water treatment station, and is all recycled for blast furnace slag sluicing and other purposes. 2.4 Pollutant prevention, treatment and control measures for coking project 2.4.1 Discharge of waste gas pollutants and control and rectification measures The fuel for heating and combusting in coke ovens is coke oven coke quenching (29773m3/h) and blast furnace gas (135220m3/h), and in addition, coke oven gas is also used in the tubular heating furnace for gas refining in Meishan Chemical Company. The main pollutants in the flue gas are SO2, NOX and small amount of smoke and dust. At present, coking plants in China usually use high stacks for discharge. In this project, high stacks will also be used, at a height of 125m. The pollutant discharge sources and control and rectification measures of the planned coking project are as shown in Table 2-1, and the discharge amount of pollutants are as shown in Tables 2-2 and 2-3. The main control and rectification measures for pollution sources are the following: (1) Coal dust from coal preparation system and control measures The coal preparation system includes the transport, batching, mixing, storage, pulverizing and belt conveying of coal. At all these points, in addition to water sprinkling to suppress dust and enclosed mechanical ventilation, enclosed air extraction is adopted at all dust producing points, and a mechanical dust collection system is provided. At all dust rising points at coal pulverizing room, such hooks are provided to prevent coal dust from escaping. High efficiency and low resistance Model DZW93 pulse bag filters have been selected to achieve a dust removal efficiency of 99.4%. The initial coal dust concentration will be 2000-5000mg/m3, and the dust concentration of the flue gas discharged after filtering will be about 30mg/m3. (2) Flue gas from coke oven loading and discharge and the control measures a) For coal loading, high pressure ammonia water will be ejected for the single gas duct, to form a negative pressure in the riser, to suck some smoke and dust into the gas duct. The remaining smoke and dust will be conveyed to the ground station via the flue gas suction and diverting mechanism of the coal loading and dust collecting vehicle, and the trunk dust collecting duct, so that the final discharge concentration of dust is less than 30mg/m3. To further improve the coal dust trapping effect, a small door sealing device is provided at the 28

coke pusher. b) Dust collection at coke discharge: it is realized by the ground station dust collecting system.

Dust collecting hoods are provided on the coke guide, to suck the flue gas produced at coke discharge via the hoods and trunk dust collecting duct to the ground station for cleaning and then discharge. c) Automatic venting and ignition device: This device is provided at the vent pipe, to burn up the lean gas dispersed from the collecting duct. The ground dust collection station system for coal loading and coke discharge is as shown in Fig. 2-3. (3) Smoke and dust control measures for coking a) Spherical sealing is adopted for the coal loading port cover, to increase the seal-tightness of this cover with its base through spherical contact. b) Elastic edge is adopted for the oven door, loaded with springs, so that the edge is subjected to homogeneous force for good sealing effect. c) Water seal structure is adopted for the riser cover and bridge pipe and valve socket on the top of the oven, to prevent smoke escaping from the riser cover and bridge pipe socket. d) The riser root is provided with a cast iron base, sealed with woven asbestos filled with slurry, to avoid smoke and flame escaping after damage of the riser root. (4) Flue gas from dry coke quenching and its dust collecting system After the high temperature flue gas from the coke tank top and circulating fan port is first trapped by the suction hoods, it is first cooled by a cooler and then mixed with the cool air with dust from the coke discharge port and the belt conveyor and the fresh coke transit station. The temperature of the mixed gas will be below 110 . It then enters the 24000m2 pulse bag dust collector for cleaning, with system air flow at 130000m3/h, dust removal efficiency at 99.7%, and discharge concentration 30mg/m3. The cleaned gas is discharged into the atmosphere via fans and silencers. The filtering element of dust collector is made of anti-electrostatic materials. The dust collected by the collector is put together with that from the primary and secondary process collectors, and is sent to the dust silo by the bucket lift. Then, it is moistened by the humidifier for periodical shipping out by dedicated vehicles. The process flow is as shown in Fig. 2-4. The wet coke quenching tower serves as a backup quenching facility. During quenching, steam containing dust and volatile pollutants will produce from the top of the tower. As a control measure, a demisting device and grid (or shutter) type baffle dampers are provided at the top of the tower as dust removal devices, with a cleaning efficiency better than 70%.

29

Coke oven coal loading cart Coke discharge Connection suction hood suction hood pipes

Connection pipes Cooling and separating flame arrestor for gusts of high temperature smoke and dust Pulse bag dust collector at ground station

Ventilation fan Ash handling Pre-spray unit system

Silencer Transport to ash bin

Humidified ash Stack unloader

Coal yard Transport out by vehicle Fig. 2-3 Ground dust collection station system for coal loading and coke discharge

Dry quenching tank top and vent of circulating Cooler fan

Coke discharge port and belt conveyor from the port, the Pulse bag dust collector fresh coke conveying station

Main exhaust fan Ash handling system Circulating gas from primary and secondary dust collection of dry coke quenching Silencer Transport out by vehicle Coal yard Stack Discharge to standard

Fig. 2-4 Dust collection flow for dry coke quenching

(5) Dust collection for coke sieving and coke store in front of oven Dust in this system is produced mainly from belt conveyor stations, coke tanks, vibrating feeders, coke store in front of oven, and vehicle transit points. As the equipment does not operate all at the same time, motor-driven valves are provided on the duct over each suction

30

hood, to reduce energy consumption. The dust-bearing gas collected by the hoods enters the 50000m2 pulse bag dust collector, before being discharged outdoor via fans and silencers. The system has a air flow of 210000m3/h and the discharge concentration 30mg/m2. The collected dust is put together by the scraper and sent to the dust silo by the bucket lift. Then, it is moistened by the humidifier for periodical shipping out by dedicated vehicles. The process flow is as shown in Fig. 2-5. (6) Waste gas sources from gas cleaning and chemical product recovery, and the control measures Waste gas from gas cleaning and chemical product recovery systems mainly consists of volatile pollutants produced from: condensing and blowing section, desulfurization section, ammonium sulfur section, crude benzene section and the main associated facilities such as clarification tank, storage tank and cool water frame. The main control measures are: a) Waste gas control measures for condensing and blowing section ·The tar slag separated from the mechanical ammonia water clarification tank is received by a dedicated slag box and sent periodically to the coal preparation system, for mixing into the coking coal, to prevent secondary pollution. ·Low noise conveying equipment will be selected, and measures to reduce noise level will be adopted for relevant buildings. ·An accident ammonia water tank will be provided, so that waste water from the circulating ammonia water system will not be directly discharged during a short production accident. Table 2-1 Waste gas pollutant discharge sources in coking production and their control and rectification measures

Section Pollutant Discharge source Control and rectification measures Large coal silo, and no 1 Coal yard TSP Basically no non-organized dust rising coal will fall onto ground 3 Coal receiving unit, coal Pulse bag filter: air flow: 50000m /h, transit station, pulverizing Initial concentration: 5g/m3 Stack height Coal room, belt conveyor 2 Coal dust 25m preparation corridor, etc. dust will escape from coal during Dust removal efficiency 99.4%, conveying and pulverizing Discharge concentration 30mg/m3 Coke oven body, oven door, coke oven coal 3 Coking New type coke oven, with sealed doors loading, coal port, riser and pushing

Smoke and dust, Ground dust station: waste gas flow 3 BaP, SO2, CO, 220000m /h Coal loading CmHm, H2S Initial dust concentration: 10g/m3 Coal loading, coke 4 and coke discharge and guiding Dust removal efficiency: 99.7%, discharge Discharge concentration 30mg/m3 Discharge height 25m

31

Section Pollutant Discharge source Control and rectification measures

3 Bag filter waste gas flow 130000m /h Initial dust concentration: 10g/m3 Dry coke Transition station and coke 5 Coke breeze: Dust removal efficiency: 99.7%, quenching silo in front of oven Discharge concentration 30mg/m3 Discharge height 40m Pulse bag filter Air flow: 210000m3/h, Coke platform, sieving 3 plant, transition station, Initial concentration: 10g/m 6 Coke sieving Coke breeze coke handling process and Stack height 30m vehicle loading points Dust removal efficiency 997.%, Discharge concentration 30mg/m3

Stack and Smoke dust and Coke oven stack and 3 7 Using clean H2S gas: 200mg/m tubular oven SO2 tubular oven Gas from gas cooling units 8 and vent pipes The ammonia and hydrogen sulfide NH , H S and of various tank 3 2 concentration at the plant boundary of C H , etc. equipment m n the project will meet the odor emission Gas from crude Waste gas flow: requirement specified in the standard 3 benzene 800m /h GB14554-93 after control measures are distilling units 3 adopted for various workshops and 9 NH3:5g/m and vent pipes Connected by sections and sections of oil tank collected and guided into separators the gas pipe before desulfurization Tail gas from desulfurization 10 NH , etc. regenerating 3 tower The ammonia and hydrogen sulfide Dust containing concentration at the plant boundary of tail gas from Waste gas flow the project will meet the odor emission 11 ammonium of ammonia and requirement specified in the standard sulfur system phenol: 300 GB14554-93 after control measures are m3/h adopted for various workshops and Dust containing sections tail gas from Inlet 12 ammonia concentration Inlet spray saturator distilling unit 1-2g/m3 drying system The pollution from gas desulfurization and refining workshop will be controlled and rectified from root mainly by using advance process flow and equipment. All equipment and pipes will be designed with seal-tightness, to prevent vent and non-organized leakage. 32

Table 2-2 Discharge of smoke, dust and SO2 pollutants from the proposed coking project

Flue gas Production of pollutant Discharge of pollutant Discharge standard Exhaust Pollution Dust removal Meet the S/N Pollutant flow mast height source measure Concentration Amount Concentration Amount Concentration Amount standard? m3⁄h (m) mg⁄m3 kg⁄h mg⁄m3 kg⁄h t⁄a mg⁄m3 kg⁄h The coal conveying station, pulverizer room and conveying corridors are enclosed, the refined coal yard is fully enclosed and water spray 1 Coal preparing facilities are designed at main dust rising locations to suppress dust. The coke conveying system is provided with an enclosed corridor. At main dust rising places, ground flushing and water spray facilities are provided to reduce dust. Coal batching 2 Dust 2×50000 Pulse bag filter 5000 500 30 3.0 26.3 120 14.5 √ 25 & pulverizing Coal sampling 3 Dust 15000 Pulse bag filter 5000 75 30 0.45 3.9 120 14.5 √ 25 room Coal loading Ground station 4 and coke Dust 2×220000 10000 4400 30 13.2 115.6 120 14.5 √ 25 and bags discharge Coke oven 5 SO 2×187074.5 Mixed gases 31.32 12.0 31.32 12.0 105 550 170 √ 120 heating 2 Dry coke quenching dust 2400m2 pulse 6 Dust 2×130000 8000 260 30 7.8 68.3 120 39 √ 40 removal bag filter system Coke silo in 5000 m2 pulse 7 front of oven Dust 210000 10000 210 30 6.3 55.2 120 23 √ 30 bag filter Sieving

8 Other non-organized smoke and dust discharge 40 SO2 66.6

9 Total Smoke and dust 309.3t/a, SO2: 171.6t/a Annual emission amount of other pollutants: (t/a) H S: 41.4 NH : 14.84 BSO: 1.2 HCN: 0.24 phenol: 2.22 BaP: 0.1067 2 3 (taken as 50mg/t coke)

33

Table 2-3 Discharge amount of other waste gases and pollutants in coking process Main pollutants

Discharge coefficient Ammonium S/N Item (g/t coke) H2S NH3 BSO HCN Phenol sulfur waste BaP gas Coefficient 0.5 0.001 1 Coking Discharge amount (t/a) 1.0 0.001 Coal Coefficient 2 preparation system Discharge amount (t/a) Coal Coefficient 5.5 6.4 0.1 0.12 0.11 0.03 3 loading and coking Discharge amount (t/a) 11 12.8 0.2 0.24 0.22 0.064 Coefficient 15.2 1.02 1.0 0.020 4 Pushing system Discharge amount (t/a) 30.4 2.04 2 0.043 Total Discharge amount (t/a) 41.4 14.84 1.2 0.24 2.22 35 0.1067

Coke sieving plant Coke cutting room and Coke silo in front of conveying station oven

Pulse bag dust collector

Humidifying Main exhaust Ash handling system fan

Silencer Transported out by Coal yard vehicle

Stack Discharge to standard Fig. 2-5 Flow diagram for dust collection in front of oven b) Waste gas control measures for ammonium sulfur section · The tail gas discharged from the fluidizing dryer is sucked into the cyclone separator, to collect the ammonium sulfur dust carried by the gas. The micro ammonium sulfur dust particles remaining in the gas will be stripped in the tail gas stripping column, before the gas is discharged into atmosphere via the exhaust fan. c) Waste gas control measures for crude benzene section · The benzene containing gas from the production system is collected to the benzene trap, where it is stripped with lean oil to remove benzene before the gas is discharged into atmosphere. 34

· The crude benzene product will be stored in an inner floating roof tank, to reduce volatility of crude benzene and improve the production environment. d) Waste gas control measures for oil depot section · The crude benzene tank will be of inner floating roof structure, to reduce volatility of crude benzene and improve the production environment. · The top of the concentrated sulfuric acid tank will be provided with a moisture removing device, to prevent dilution of concentrated sulfuric acid by absorbing water, to corrode equipment and prevent the gas from polluting the environment. · A breathing valve will be provided at the top of the tar storage tank, to reduce the emission of harmful gas. · The design will be based on the geographic location of the site and actual conditions, to ensure storage capacity for raw materials and products, and vehicle loading and unloading facilities will be designed accordingly. The storage period for tar, crude benzene, tar stripping oil and concentrated sulfuric acid will all be 15-20 days. (7) Non-organized discharge sources in the coking plant and control measures The pollutant discharge and control level of mechanical coke ovens in China In drafting the “Discharge standard of atmospheric pollutants from coke ovens”, the Environmental Science Academy of China conducted massive survey and investigation on the particles, BSO and BaP produced during coking for different levels of coke ovens in key coking and chemical enterprises of China. The classified statistic results of the monitored data are as given in Table 2-4. It can be seen from this table that the pollutant discharge level from coke ovens differs greatly among different types of coke ovens and for different management levels. Table 2-4 Overall and classified pollution control level for mechanical coke ovens in China

Particles BSO BaP No. of No. of coke Class Pollution control level mg/m3 mg/m3 μg/m3 monitored data ovens 1 1.23 0.23 1.233 30 2 World advanced level 2 2.76 0.61 2.757 135 9 Leading domestically 3 4.41 1.46 10.418 75 5 Domestic advanced level 4 5.48 3.23 23.010 45 3 Improvement required 5 26.54 20.35 130.250 15 1 Loss of control Overall 4.62 2.16 13.93 300 20 average Note: The data given in this table are the waste gas as monitored escaping from the oven top.

35

Non-organized discharge and control measures for the project a) The facilities in the coal yard will be reformed with the rebuilding of the existing

3×65-duct coke ovens, and all 6×55-duct coke ovens will share a common coal preparation system, so that the non-organized dust rising from the coal yard will be put under control fundamentally. The coal conveying station, pulverizer room and conveying corridors will all be enclosed structures to prevent pollution by the escaping coal dust, the refined coal yard is fully enclosed and water spray facilities are designed at main dust rising locations to suppress dust to prevent secondary dust rising. The coke conveying system is provided with an enclosed corridor to prevent escaping of coke breeze. At main dust rising places, ground flushing and water spray facilities are provided to reduce dust and prevent secondary dust rising. b) The raw gas escaping during coal loading into the coke ovens and the non-organized raw gas escaping from the oven doors and top during coking contains dust, SO2, BaP, CO and NOn. In this project, coal will be loaded with high pressure ammonia water spray, and ground dust collecting stations will be provided to control the smoke and dust during coal loading and coke discharge, therefore basically no smoke will produce during coal loading operation. c) The waste gas discharged from the coke oven body during coking contains dust, SO2, BaP, CO and NOn. With the negative pressure operation of the gas collecting pipes at -3bar or -300Pa, raw gas escaping during coal loading into the coke ovens and the non-organized raw gas escaping from the oven doors and top can be effectively controlled; the pressure of each coking chamber is adjusted separately, to ensure no smoke will escape from the oven door and coal loading port, so no smoke will produce in coke production. d) The flue gas discharged during coke discharge contains dust, H2S, BaP, SO2, NH3, CO and NOn. The horizontal coke discharge process is designed to reduce smoke and dust emission, and a ground station shared with the coal loading is used to collect dust. After dust removal, the dust concentration in the discharged flue gas will be about 30mg/m3. Investigation and analysis for comparison a) Monitoring result of BaP in the ambient air of the coking plant of Jiuquan Iron and Steel Company and its surrounding area At Jiuquan Iron and Steel Company three monitoring measurements were conducted during the 1980s for the BaP in the ambient air of the coke ovens and the surrounding area, and the monitoring results are as shown in Table 2-5. It can be seen from the table that the BaP in the ambient air during the monitoring period exceeded the standard. The BaP of the waste gas discharged from coke ovens 1# and 2# all exceeded the standard. During Nov. 28 to 30, 2000, we performed site measurement again for the particles, BSO and BaP in the non-organized waste gas discharged from the existing 1#, 2#, 3# coke ovens of Jiuquan Iron and Steel Company during their production, as shown in Table 2-6. There have been fundamental changes as compared with the monitoring results of the 1980s, and the non-organized discharge basically meet the standard. This indicates that technological progress and control with environmental protection actions have achieved good effect in

36

reducing pollutant discharge during coking process. Table 2-5 BaP testing results for coke oven and ambient air in Jiuquan Iron and Steel

Company Unit: μg/m3

S/N Monitoring point July 1983 Oct. 1984 Feb. 1989

1 Raw materials 0.46 0.0353 0.1554 2 Living area 0.0011 0.0107 0.0816 3 Coking plant 0.102 0.2046* 0.6948 4 **1# coke oven of coking plant 14.52 14.19 5 **2 # coke oven of coking plant 20.90 20.67 6 Ore dressing plant / 0.0107 7 Electrical repair shop / 0.0063 Notes: * This is the average of the monitoring results of the coking shop. **At top of coke oven Grade II value of ambient quality standard GB3095-1996: 0.01μg/m3 Grade III value for existing coke ovens in “Atmospheric pollutant emission standard for coke ovens” (GB16171-1996): 5.5μg/m3 Table 2-6 Non-organized pollutant discharge testing results for coke ovens in Jiuquan Iron and Steel Company Unit: μg/m3 Concentration Average Exceeding the Coke oven range mg/m3 concentration mg/m3 standard by (%) Smoke and dust Smoke and dust: 1# coke oven 0.446~14.116 2.506 11.11% Grade II standard value: 3.5 2# coke oven 0.205~20.618 3.547 11.11 3# coke oven 0.205~5.452 1.271 5.56 BSO 1# coke oven 0.10~0.31 0.187 BSO: 2# coke oven 0.10~0.27 0.138 Grade II standard value: 0.8 3# coke oven 0.11~0.23 0.177 BaP 1# coke oven 0.22 ~2.5 1.23 BaP: 2# coke oven 1.23~3.55 2.22 Grade II standard

37

3# coke oven 0.38~2.77 1.15 value: 4.0 b) BaP source intensity monitoring results and analysis of Iron and Steel Company In 1998, 1997 and 2001, the Environmental Monitoring Central Station of Province, the Environmental Monitoring Station of Taiyuan City and the Environmental Monitoring Station of Taiyuan Iron and Steel Company performed monitoring on the BaP from the 4#, 5# and 6# coke ovens of Taiyuan Iron and Steel Company, and the results are given in Table 2-7, It shows in the table that the non-organized discharge from the 4#, 5# and 6# coke ovens of Taiyuan Iron and Steel Company meets the discharge standard. Table 2-7 BaP monitoring results for coke oven top in Taiyuan Iron and Steel Company Unit: µg/m3 Grade II Item 4# 5# 6# standard value Concentration range 0.1-7.2 0.29-13.63 0.39-1.77 (µg/m3) 4 No. of samples 14 8 8 Average value 2.06 2.63 1.01 c) Pollutant discharge analysis for coke ovens of this project For this project, Model JN60-6 combination coke oven will be selected, which is advanced in process level and mature in technology. It is an advanced model in China, featuring short coal charging time, concentrated flue gas for easy collection, and good seal-tightness of oven door, therefore the amount of non-organized discharge will be small. By comparing with the monitoring results in Tables 2-6 and 2-7, it can be concluded that the non-organized discharge of waste gas from the coke ovens of this project can meet the grade II standard requirements in Table 2 of the “Atmospheric pollutant emission standard for coke ovens” (GB16171-1996), i.e. particles at 2.5mg/m3, BSO at 0.60mg/m3 and BaP at 0.0025mg/m3. The design institute shall take these into full consideration, so that the pollutants in the waste gas of non-organized from the coke ovens meet the “Atmospheric pollutant emission standard for coke ovens”. In the meantime, the amount of BaP will be controlled below 1.0 g/t coke (in the clean production standard for coking industry (HJ/T126-2003), the BaP limit values are ≤1.0g/t coke for grade I and ≤1.5g/t coke for grade II for coal loading). According to the source intensity monitoring on large and new type coke ovens by the Environmental Science Academy of Shanxi Province and others, the discharge source intensity of BaP from coke ovens is 36mg/t coke. For this project, it is taken as 50mg/ mg/t, so the annual BaP discharge amount from coke ovens will be 106.71kg. 2.4.2 Waste water pollutant discharge and control and rectification measures (1) All refining of coke oven gas in Meishan Iron and Steel Company will be performed by Meishan Chemical Company. For the production and discharge of relevant pollutant, refer to the section for gas refining.

38

(2) Water supply and drainage for coking and pollutant discharge The total water consumption for the planned coking project (4×55 ducts) will be 1027 m3/h, including 100m3/h (for steam production in the dry coke quenching boiler) as demineralized water, reflux water of 166.7 m3/h, and circulating water flow at 10000 m3/h, with water circulating rate of 97.4%. The production waste water discharged will be 106.7 m3/h, mainly as equipment cooling water. The water supply and drainage balance is as shown in Fig. 2-6.

Coal preparation -7

North discharge port

Ground station dust removal and humidifying -21.2

Dust removal and humidifying -12

Ground flushing water -0.5

Cooling water for other equipment Cooling tower Cooling water for dry -7.3 quenching equipment Refluxed water: 83.3

Cooling water tank

Demineralized water: 50 Dry quenching boiler-5 Steam users-27

Water consumption for 6×55-duct coke Waste water and water consumption for gas refining is ovens after completion of project: counted in Baosteel Chemical Co. Fresh water (m3/h): Refluxed water: 250 Demineralized water: 150 Circulating water: 15000 Total water consumption: 15400 Circulating rate: 97.4% Waste water discharged: 160

Fig. 2-6 Water consumption balance diagram of one coke oven (2×55 ducts) in 39

production 2.4.3 Solid wastes and control and rectification measures

See Table 2-8. Table 2-8 Production of solid wastes during coking in the proposed project and the disposal measures Description of solid Source Amount (t/a) Disposal measure waste Removing dust and Transported to the coal yard by vehicle 1 7320 powder after humidifying 2 Tar slag 2538 Coal batching 3 Slag of crude benzene 1223 In tar tank 4 Asphalt slag 60 Coal batching Gas refining is performed in 6 Dried slurry 420 Coal batching Meishan Chemical Dust removal for dry To sintering and Company 7 86250 coke quenching batching

40

3. Feasibility analysis and technical and economic demonstration

of environmental protection measures

The feasibility of environmental protection measures is a matter concerning not only the resource utilization of an enterprise and the environmental impact of its pollution discharge but also its economic benefit. The adoption of practical “three wastes” control measures is a prerequisite for an enterprise’s implementation of sustainable development. Principally in line with relevant requirements on pollutant discharge standards, control of total amount and the principle of up-to-standard discharge of pollutants, this chapter analyzes the technical and economic feasibility of the environmental protection measures of this construction project and provides corrective actions to address possible problems. During production of this project, the main “three wastes” discharged are waste gas and wastewater. Therefore, this chapter mainly analyzes and appraises the environmental protection measures for waste gas and wastewater and only gives general analysis on slag and noise. 3.1 Overview of environmental protection measures for existing projects 3.1.1 Existing waste gas pollution control measures The existing waste gas pollution control measures in Meishan Iron and Steel Company (including Meishan Chemical Branch) are shown in Table 3-1. From Table 3-1, we can see that both Meishan Iron and Steel Company and Meishan Chemical Branch have adopted effective measures to control waste gas pollutants, waste gas pollutants are emitted after reaching standard and all waste gas control facilities have passed the “three simultaneouses” completion acceptance.

29

Table 3-1 Existing waste gas pollution control measures in Meishan Iron and Steel Company and Meishan Chemical Branch

Control Pollutant Company Plant No. Pollution source Effect measures Removal efficiency Electric dust removal for head of 1# Heads of 1# and sintering (Smoke) dust Discharged after 2# sintering 1 machine collection reaching machines (share a /multicyclone efficiency≥92% standard chimney) for head of 2# sintering machine Electric dust removal for tail Discharged after Tails of 1# and 2# Dust collection 2 of 1#/2# reaching sintering machines efficiency≥99% sintering standard machine Discharged after Crushing of Electric dust Dust collection 3 reaching limestone flux removal efficiency≥99% standard 335m2 Discharged after Head of 3# Dust collection 4 electro-precipita reaching Sinter plant Sinter plant sintering machine efficiency≥98% tor standard 190m2 Discharged after Tail of 3# sintering Dust collection 5 electro-precipita reaching machine efficiency≥99.5% tor standard 140m2 Discharged after Sieving of 3# cold Dust collection 6 electro-precipita reaching Meishan Iron and Steel Company Company Steel and Iron Meishan sinter product efficiency≥99.5% tor standard Discharged after Crushing of 3# Electric dust Dust collection 7 reaching sinter flux removal efficiency≥99% standard Discharged after Crushing of 3# Foam dust Dust collection 8 reaching sinter fuel separator efficiency≥98% standard 3# sinter Discharged after Bag type dust Dust collection 9 dispersion and reaching collector efficiency≥99.5% transfer tower standard Discharged after 1# coal injection Bag type dust Dust collection 1 reaching dust removal removal efficiency≥95% standard Discharged after 2# coal injection Bag type dust Dust collection 2 reaching

Ironmaking plant plant Ironmaking dust removal removal efficiency≥95% standard

30

Control Pollutant Company Plant No. Pollution source Effect measures Removal efficiency Discharged after 3# coal injection Bag type dust Dust collection 3 reaching dust removal removal efficiency≥95% standard Discharged after 4# coal injection Bag type dust Dust collection 4 reaching dust removal removal efficiency≥95% standard 1# BF transfer Discharged after Electric dust Dust collection 5 tower and cast reaching removal efficiency≥99% house standard Discharged after Electric dust Dust collection 6 1# BF stock bin reaching removal efficiency≥99% standard Discharged after Electric dust Dust collection 7 3# BF stock bin reaching removal efficiency≥99% standard Discharged after Electric dust Dust collection 8 3# BF cast house reaching removal efficiency≥99% standard Discharged after 2# BF pulverized Bin top air bag smoke gas removal 9 reaching coal injection filter efficiency≥95% standard Discharged after 2# BF transfer Electric dust Dust collection 10 reaching tower removal efficiency≥99% standard Discharged after Electric dust Dust collection 11 2# BF stock bin reaching removal efficiency≥99% standard Discharged after Bag type dust Dust collection 12 2# BF cast house reaching removal efficiency≥99% standard Discharged after Bag type dust Dust collection 1 Mixer reaching removal efficiency≥95% standard Limekiln flue gas Discharged after Bag type dust Smoke gas removal 2 and lime product reaching removal efficiency≥95% dust standard 2# limekiln flue Discharged after Bag type dust Dust collection 3 gas and lime reaching removal efficiency≥99.5% Steelmaking plant Steelmaking product dust standard Dust from 2# Discharged after Electric dust Dust collection 4 limekiln raw reaching removal efficiency≥99.5% material workshop standard

31

Control Pollutant Company Plant No. Pollution source Effect measures Removal efficiency Dust from Discharged after Electric dust Dust collection 5 crushing of lime reaching removal efficiency≥99% product standard Discharged after Underground bin Bag dust Dust collection 6 reaching of charging system removal efficiency≥95% standard Discharged after Elevated bin of Bag type dust Dust collection 7 reaching charging system removal efficiency≥95% standard Dust collection of Discharged after Wet type dust Smoke gas removal 8 1# and 2# reaching removal efficiency≥95% converters standard Discharged after Ladle transferring Bag type dust Dust collection 9 reaching station removal efficiency≥95% standard Discharged after Bag type dust Dust collection 10 Refining furnace reaching removal efficiency≥95% standard Discharged after Bag type dust Dust collection 1 Transfer tower reaching removal efficiency≥99.5% standard Discharged after Bag type dust Dust collection 2 Inspection station reaching removal efficiency≥99.5% Raw material plant plant Raw material standard Smoke gas removal Discharged after Terminal section 1 Water film dust efficiency≥95%, 1 reaching boiler removal SO2 removal Terminal standard efficiency≥10%

Discharged after Electric dust Smoke gas removal 1 2#~4# boilers reaching removal efficiency≥99% standard Power plant Asphaltic smoke Discharged after Wash by V.S. 1 Asphalt shaper removal reaching wash oil efficiency≥86% standard

Branch Branch Wash and Discharged after 2-level acid and Phenol removal 2 decomposition reaching alkali wash efficiency≥86% Meishan Chemical Chemical Meishan device standard 3.1.2 Existing wastewater pollution control measures The existing wastewater control measures in Meishan Iron and Steel Company and Meishan Chemical Branch are shown in Table 3-2.

32

Table 3-2 Wastewater control measures in Meishan Iron and Steel Company and Meishan Chemical Branch

Standard Plant Wastewater Control measure attainment Sinter plant Sinter wastewater Plate settler Up to standard Wastewater from cleaning of Radiation Ironmaking plant Up to standard BF gas sedimentation basin Wastewater from oxygen Energy Oil separation and generation and machine Up to standard Department sedimentation basin maintenance Wastewater from Rotational flow and steelmaking and continuous advection Up to standard casting sedimentation basin Steelmaking plant Wastewater from cleaning of Plate settler Up to standard converter gas Cooling water from limekiln Direct discharge Up to standard equipment Advection Rolling mill Wastewater from hot rolling Up to standard sedimentation basin Blower station and Oil separation and thermal power Oil-containing wastewater Up to standard sedimentation basin plant Septic tank, sedimentation and — Domestic sewage Up to standard biochemical treatment Phenol removal, ammonia distillation, COD and Meishan Chemical Phenol-cyanogen wastewater oil separation and NH -N not up Branch 3 biochemical to standard treatment 3.1.3 Solid waste pollution control measures for existing projects The generation amount and disposal measures of solid waste in existing projects are shown in Table 3-3.

33

Table 3-3 Generation amount and disposal method of solid waste in existing projects of Meishan Iron and Steel Company

Amount Utilization Company Solid waste Code Source Disposal method (t/a) rate % BF granulating Sold as building 73 BF 1052014 100 slag material BF iron slag 81 2787 Reused by BF 100 Steel slag 74 Converter 327540 Sold 100 Sinter precipitated 56 Sinter 2733 Reused by sinter 100 sludge Used by Converter sludge 56 Converter 30070 100 converter Gas slime 56 BF gas wash 15084 Reused by sinter 100 Sintering, coking, Industrial dust 84 ironmaking and 93451 Reused by sinter 100 steelmaking Gas ash 81 Ironmaking 26552 Reused by sinter 100

Meishan Calcic waste 51 Limekiln 24194 Reused by sinter 100 Iron and Produce magnetic Mill scale 55 Hot rolling 32502 100 Steel material Company Ferrous Pulverized coal impurities in 81 110 Reused by BF 100 injection coal Preparation and Coaly dust 84 injection of 1000 Recovered 100 pulverized coal Sent to Jiantong Thermal power Fly ash 71 145834 Group to make 100 plant building material Disposed Waste refractory 99 Furnace lining 53000 together with 100 steel slag Recovered and Waste oil 11 Steel rolling 450 100 sold Recovered by the Waste steel etc. 85 Roll etc. 120000 100 plant Asphalt residue 11 52 100 Meishan Gas refining and Crude benzol Blended into coal Chemical 11 chemical product 1060 100 residue in coke plant Branch workshops Tar residue 11 2200 100 Total - - 1930633 - 100

34

3.1.4 Noise control measures in existing projects The noise control measures in existing projects are shown in Table 3-4.

Table 3-4 Existing main noise equipment and noise level in Meishan Iron and Steel Company Noise (Set) Treatment Company No. Noise equipment level Effect Qty measure dB(A) Meishan Coke pusher of coke Up to Iron and 1 oven (at 3m, pushing 85.4 3 — standard at Steel is in operation) boundary Company Sound Vertical crusher fan in 2 81.0 1 insulation by sinter plant (at 3m) buildings Sintering machine (at 3 76.8 2 — 5m on outside floor) Main exhaust fan for 4 97 3 sintering machine Fan for ignition 5 furnace of sintering 98 3 machine Recirculating cooling Use low-noise 6 fan for sintering 100 3 product and machine install muffler Fan for dust collection 7 system of sintering 97 5 machine Dust removing fan for 8 pulverized coal 80-100 1 preparation Vibrating screen for Install sealing 9 pulverized coal 80-85 1 hood to preparation insulate sound Sound Air compressor in air 10 90-95 8 insulation and compressor room muffler

35

Noise (Set) Treatment Company No. Noise equipment level Effect Qty measure dB(A) Sound muffling, 11 BF hot stove fan 100 3 insulation and absorption BF hot stove blower Sound 12 (3m outdoor, in 85.0 3 insulation by operation) buildings General noise of BF Sound 13 cast house platform 76.3 3 insulation by (when no casting) buildings Muffler and Fan for BF dust 14 98 4 sound collection system absorption 15 BF fan blow-off valve 120 3 Muffler Furnace top pressure 16 115 3 Muffler relief valve Sound Residual pressure 17 100 3 insulation and generator set absorption All kinds of Sound 18 circulating water 90 12 insulation and pumps absorption Active limekiln gas 19 80-100 2 Sound compressor muffling, Active limekiln insulation and 20 80-90 4 blower absorption Active limekiln dust 21 80-100 2 Muffler, and removing fan sound Active limekiln insulation and 22 80-90 2 ventilator absorption Install sealing Active limekiln 23 80-85 2 hood to vibrating screen insulate sound

36

Noise (Set) Treatment Company No. Noise equipment level Effect Qty measure dB(A) Dust removing fan for Sound 24 raw material transport 100 2 insulation and storage facilities Sound General noise in 25 76.4 — insulation by steelmaking workshop buildings Converter in Sound 26 steelmaking workshop 99.85 2 insulation by (at 12m, indoor) buildings General noise in Sound 27 continuous casting 78.8 — insulation by workshop buildings Sound 28 CCM (at 5m, indoor) 89.5 1 insulation by buildings Sound Hot rolling heating 29 93.0 2 insulation by furnace fan (at 2m) buildings Sound Continuous hot rolling 30 100.1 7 insulation by mill (at 5m) buildings 31 Train 105 18 — Sound insulation and 32 Turbo-generator set 101 2 vibration reduction 33 Steam bleeder valve 115 2 Muffler 1 Tube furnace 87.4 2 — Meishan Up to Sound Chemical Tube furnace pump standard at 2 76.9 2 insulation by Branch room boundary buildings 3.1.5 Existing environmental problems (1) The main wastewater generated from the existing projects in Meishan Chemical Branch includes remnant ammonia, condensed water from final gas cooling, process wastewater, floor

37

washing wastewater and tar raw material separating water. The above industrial wastewater enters the phenol-cyanogen sewage treatment station of Meishan Chemical Branch where it is treated and discharged into North Discharge Outlet. COD and NH3-N are not up to standard. (2) In existing projects, only 63% of coke oven gas is desulfurized. The desulfurization ratio is low. The amount of SO2 emitted from gas combustion is 2534t/a. (3) In Meishan Iron and Steel Company, the water consumption per ton of steel is high ((12.1t/t of steel) and water reutilization rate is low (92.6%). (4) Meishan Chemical Branch consumes a large amount of equipment cooling water, which is directly supplied with fresh water, causing much waste. (5) The existing three coke ovens were built in early 1970s and mid 1990s and are rundown with serious pollution of fugitively emitted smoke gas and other harmful gas. (6) The fugitive emission of dust at places like BF cast house, coke oven, stock house and slag yard is serious. The total emission reaches 6965t/a, accounting for 65% of the total emission of Meishan Iron and Steel Company. 3.2 Analysis of pollution prevention and control measures for intended project and countermeasures 3.2.1 Prevention and control measures of key waste gas pollution sources and feasibility analysis The waste gas emission sources in this project mainly include: smoke gas from coal charging during coking, flue gas from heads and tails of sintering machines, flue gas from BF cast house, flue gas from converter, flue gas from converter auxiliary system, flue gas from LF, dust from stock house, bulk material system, belt conveyance and other nodes, and a small amount of organic waste gas generated during chemical product processing. The main control measures adopted are described in Table 3-5. From Table 3-5, it can be seen that this project adopts nationally common practical and effective measures to control main waste gas pollution sources and ensure pollutants are discharged only after reaching emission standard. The measures are feasible. In an iron & steel company, coke plant, sintering plant, ironmaking plant, steelmaking plant and cold rolling mill are main contributors to pollution. Below is further feasibility demonstration on the environmental protection measures controlling the following key pollution sources: coal charging and coke discharging of coke ovens, dust removal at heads and tails of sintering machines, purification of BF gas, converter gas, and control of acid mist from cold rolling. (1) Analysis of dust removing measures for coking facility a. Coal preparation workshop In this project, a pulse bag filter is installed in coal pulverizer room. The dust collection efficiency exceeds 99.4%. The dust concentration and emission rate at the outlet of the exhaust tube are both up to Grade 2 standard for new projects as defined in the Integrated Emission Standard of Air Pollutants and the Emission Standard of Air Pollutants for Industrial Kiln and Furnace. About 1550t/a of emitted coal dust can be mitigated, showing 38

obvious environmental benefit. In the new coking projects or technical innovation projects in China, the coal pulverizer rooms of coal preparation workshops all adopt this dust collection method. This method is characterized by low investment, good effect, stable and reliable operation and high operability. In addition, this project adopts closed coal transfer tower, vestibule of coal belt conveyor and other dust suppression measures. b. Dust collection during coal charging and coke discharging and emission control of waste gas from coke oven proper Coke oven proper is one of the key pollution sources in the intended project. The air pollutants emitted from it cause big harm. This project adopts JN60 6m coke oven, which is the largest in China and adopts advanced process equipment and environmental protection facilities to minimize the emission of air pollutants from coke oven from the approach of process. Meanwhile, the project adopts advanced process equipment and environmental protection equipment: a series of general control measures are adopted, such as: adopting new-type sealing structure for coal charge lid of coke oven, water seal device for coke oven uptake lid and bridge pipeline spigot joint, plugging woven asbestos rope to uptake root, and injecting high pressure ammonia during coal charging. They are economical, practical, feasible and reliable technologies. These pollution control measures are widely adopted by coke ovens at home and abroad. It is proved that theses measures can effectively prevent leakage of coke oven proper and reduce smoke gas emission of coke oven proper by 90%-95%. In addition, this project also installs nationally, even internationally advanced dust collecting ground station system for coal charging and coke discharging in coke oven, realizing more than 95% of smoke gas collection rate and 99.7% of dust collection efficiency and effectively controlling air pollution of coke oven. It is one of the best methods at present to solve air pollution generated from coke oven during coal charging and coke discharging. In order to more easily analyze through comparison the advancement, reliability and feasibility of smoke gas control technology for coke oven during coal charging and coke pushing in this project, we list the general condition of the coke oven coal charging smoke gas control technologies adopted in China and foreign countries in Table 3-6 and that of the coke oven coke discharging smoke gas control technologies in Table 3-7.

39

Table 3-5 Main waste gas control measures and standard attainment status of intended project

Emission Height Emission amount Emission amount Amountof concentration Position Pollution Dust of NOX.(t No. waste gas 3 of (smoke) dust of SO2 source collector exhaust (mg/m ) /a) (m3/h) (Y /X) tube (m) Dust SO2 kg/h t/a kg/h t/a

Coal blending Pulse bag and 100000 25 30 3.0 26.3 529/290 filter pulverization

Coal charging Ground and coke 440000 station 25 30 13.2 115.6 648/343 discharging bag

Coke oven 374149 125 — 31.3 — — 12 105 655 647/481

Coal sampling 1500 25 30 0.45 3.9 544/173 room Coking

CDQ dust 260000 40 30 7.8 68.3 604/385 collection Pulse bag filter Oven-front coke warehouse 210000 40 30 6.3 55.2 592/830 Coke sieving

Other fugitive H2S: 41.4 NH3: 14.84 BSO: 1.2 SO2: 66.6 40 emission HCN: 0.24 Phenol: 2.22 BaP: 0.1067

250m2 Machine head 1140000 electrostatic 120 40 726 45.6 361.2 827.6 6554.5 1444 0/0 dust collection precipitator

195m2 Machine tail 570000 electrostatic 50 40 22.8 180.6 26/214 dust collection precipitator

63m2 Blending 207500 electrostatic 35 40 8.3 69.7 -89/127 Sintering Sintering precipitator

36m2 Crushing and 112000 electrostatic 30 40 4.48 37.6 -111/181 sieving precipitator

Other fugitive 30 emission

Furnace-top 57600 20 30 1.73 14.5 -1316/-688 charging

Stock bin 268800 30 30 8.064 67.7 -971/-786

Cast house 860000 Bag type dust 40 30 25.8 216.7 -1327/-693 collector Raw material 701360 35 30 21 176.4 -1084/-653 BF system

Coal injection 298286 55 30 2.688 22.6 -1129/-585 system

Hot stove 89600 Mixed gas 80 15 - - 4.49 37.7 150 -1287/-743

Other fugitive 80 emission

40

Table 3-5 Main waste gas control measures and standard attainment status of intended project (continued)

Emission Height Emission amount Emission amount Amountof concentration Position Pollution Dust of NOX.(t No. waste gas 3 of (smoke) dust of SO2 source collector exhaust (mg/m ) /a) (m3/h) (Y /X) tube (m) Dust SO2 kg/h t/a kg/h t/a

Converter flue 2-level wet 29500 80 2.36 16.2 -1557/-753 gas type

Secondary flue 500000 Bag type 70 30 15 103.1 -1538/-691 gas

72 (one set for Molten iron 600000 Bag type 40 30 18 2 -1620/-612 desulfurization convert

One converter One converter ers)

Refining furnace and 83000 Bag type 30 30 3.9 26.8 F:8.5 -1726/-595 charging

Other fugitive 34 5.59 emission

Adsorption and condensati Crystallizer 200000 30 10 2.0 14.6 -1740/-624 on by using double cooling

Baking in continuous 29240 - - - - 0.39 2.84 casting process Mixed gas Heating and annealing 143669 60 - - - - 2.58 18.82 209 -1899/-624

Sheet continuous casting and rolling and casting continuous Sheet furnaces

Sinter-plate Flue gas from 360000 dust 60 20 - 7.2 52.6 0.50 4.3 -2102/-620 finish rolling collector

Fugitive emission of stock 90 house

41

Table 3-5 Main waste gas control measures and standard attainment status of intended project (continued)

Height Emission Emission Emission Amountof of concentratio amount of Pollution Dust amount of SO Position No. waste gas exhaust n (mg/m3) smoke gas 2 NOx source 3 collector (Y /X) (m /h) tube (t/a) (m) Dust SO2 kg/h t/a kg/h t/a

Bag type Kiln-tail flue 46200 dust 40 30 — 1.4 11.3 — — 75 -1549/-1260 gas collection Finished Bag type product 100000 dust 30 30 - 3.0 24.5 -1601/-1276 hopper and Limekiln Limekiln collection crusher Stock house Bag type transfer 72000 dust 25 30 — 2.16 17.6 -1440/-1210 tower collection n Crude benzol 23331 25 - 74 — 0.83 6.0 34 917/963 tube furnace Fugitive

as purificatio NH 1.13 HS: 9.0 Ammonium sulfate waste gas: 35 emission 3 2 G Annealing Coke oven 63336 40 - 71 - - 5.13 37.46 92 -2000/-305 furnace gas Tension leveler and 72000 Bag 25 30 2.16 15.6 -1985/-350 welding machine Shot blasting 25000 Bag 25 30 0.75 5.4 -2004/-355 machine Skin pass 110000 Bag 40 30 3.3 24.1 -2594/-647 mill Acid regeneration 14000 Bag 30 30 0.42 3.1 -2086/-353 station HCl mist Cold rolling Cold rolling Acid from acid 24000 20 10 0.24 1.8 -2125/-410 mist wash Acid mist Chromic washer acid mist Acid 900 50 0.07 63mg 0.45kg -2310/-540 from mist annealing Oil mist Oil mist Oil from rolling 300000 20 20 6.0 43.2 -2110/-389 filter mist mill Alkali mist Alkali mist Alkal from 53000 45 10 0.53 3.8 -2200/-410 washer i mist washing

Gas-fired 726903 50 3.5 22 22.6 142.6 366 -1163/39 boiler

Total t/a 7784174.16×10000m3 2279.3 6987 3025

42

Table 3-6 Control technologies of smoke gas from coke oven during coal charging adopted at home and abroad 1 2 3 4 5 Wash, Dry-type Dry-type purification Lead the smoke gas purification andpurification and and dust collection fugitively emitted during Process Dust catching dust collection dust collection system of smoke gas coal charging into coal car system of system of ground ground station neighboring carbonization ground station station without combustion chamber Smoke gas from Smoke gas Smoke gas from coal The coal car is coal car is burnt from coal car is car is neither burnt installed with an The coal car is installed but not washed. Technical burnt, washed nor washed. The air-cooling with coal charging seal The ground feature and purified by ground station pre-coated bag sleeve, bypass pipe and station purifies two-level purifies air with bag type dust computer control system air with bag type venturi tube type dust collector collecting device dust collector Dust Smoke gas control rate collection <50mg/m3 40mg/m3 <50mg/m3 <120mg/m3 exceeds 95% effect 1) The coal car is 1) The coal car 1) Comparing small and ground 1) The coal car is is big and with wet type dust collecting big but doesn’t 1) The coal car has complex and coal car, it is device has not occupies floor complex structure but has high energy Technical smaller and explosion protection, space doesn’t occupies floor consumption and lighter and so both energy 2) Investment space 2) Sewage is economic consumes less consumption and and energy 2) Investment and energy generated performance energy investment are consumption are consumption are both 3) Need large 2) No sewage reduced. both lower than lower than those of other floor space 3) Need large 2) No sewage those of other control methods 4) High floor space 3) Less floor space control methods investment than the first two Coke plant of Jinan Iron & Steel Baosteel Phase Corporation Application This project Baosteel Phase 3 Germany 2 Coke plant of Kunming Iron & Steel Corporation

43

Table 3-7 Control technologies of smoke gas from coke oven during coke discharging adopted in China

1 2 3 4 Coal charging Ground smoke Ground smoke and coke Process gas purification gas purification discharging share Thermal buoyant hood device with flap device with belt a set of smoke docking valve sealed cart gas purification device The flue gas The captured captured from The captured flue flue gas is sent coal charging and gas is sent via a Thermal buoyant hood by smoke gas coke discharging flap docking captures flue gas by Technical transfer cart to is sent to a same valve to ground relying on thermal feature ground station dust collector on where bag type buoyancy and wash it by where bag type the ground, which dust collector is spraying dust collector is is usually bag used used type dust collector 3 3 3 <50mg/m 30mg/m Dust <50mg/m Dust collection Dust collection Dust collection collection Dust collection efficiency> efficiency> efficiency≈90% effect efficiency>99% 99% 99.9% 1) Energy 1) Coal charging 1) Energy consuming; and coke consuming; discharging share 1) Dust collection effect is 2) Low 2) High a set of dust inferior to that of ground investment; Technical investment; collection device, station dust collection and 3) Occupy floor system. It occupies less 3) Occupy floor thus saving economic space; floor space and its space; investment; performance operation and 4) No sewage; 4) No sewage; 2) Energy management are easy; 5) Good dust consuming; 5) Good dust 2) Sewage is generated collection collection effect 3) Require strict effect maintenance Capital Iron & Steel Corporation, Anyang Iron & Baosteel Phase 3 Panzhihua Iron & Steel Steel Application This project Corporation and Wuhan Shanghai Pudong Corporation, Iron & Steel Corporation Gas Plant Beijing Coke Plant, Shanxi Coke Plant, and Germany

44

In this project, non-combustion dry-type dust collecting ground station is used to purify and treat the smoke gas generated from coke oven during coal charging. The smoke gas collection rate exceeds 95%. This technology has been widely used in large coke ovens in China since Baosteel Phase-3 Project. Certain operation experience has been accumulated. It has obvious pollution control effect. The practice has proved the technology is mature and features stable and reliable operation and good effect. In this project, dust collecting ground station with flap docking valve is used to control smoke gas generated from coke pushing. After trapped by movable dust hood and the combined dust hood on coke guiding car, smoke gas is sent to dust collecting ground station to remove dust. The dust collecting ground station system for coke pushing of coke oven is an advanced technology controlling smoke gas generated from coke oven during coke pushing in the world. It is used in most coke plants in China at present and is one of the optimal methods solving pollution generated from coke oven during coke pushing. By adopting a series of pollution control measures for coke oven, the total amount of pollutants emitted from coke oven is cut by about 90% on average. c. Coke quenching system The intended project adopts CDQ (coke dry quenching). CWQ (coke wet quenching) is reserved. CDQ process can not only greatly reduce the emission of coke dust but also recover sensible heat of coke and generate steam. It is the development direction of coke quenching process in coking industry. In order to reduce dust emission during CDQ, dust traps are installed at coke charging point at the top of CDQ boiler, at coke discharging point in bin bottom, over the belt at coke outlet, at the bleeding outlet of circulating fan and other places to collect and send the dust to CDQ dust collecting ground station. In the station, large pulse bag filter is used to collect dust. This technology has been used in Baosteel, Jinan Iron & Steel Corporation and Shanghai Pudong Gas Plant for some years. Certain operation experience has been accumulated. Practice has proved this process and its equipment feature stable and reliable operation and obvious dust collection effect. The CWQ tower as standby is installed with baffle-style wood-grid dust trap at tower top. It can trap the coke dust generated during CWQ. The coke dust collection rate is 60%. The dust emission concentration and rate at tower top outlet are both up to Grade 2 standard as defined in the Integrated Emission Standard of Air Pollutants. This technology has been widely used as standby equipment for CDQ. d. Coke sieving and storage system The coke sieving and storage system is provided with a bag type dust collector with dust collection efficiency of above 99%. Bag type dust collector has desirable dust collection effect and stable and reliable operation. Mature operation experience has been achieved in China. The coke dust concentration and emission rate at the outlet of the dust collector both can steadily reach respective emission standard. In addition, the main dust generating points in coke sieving and storage system and coke

45

transfer vestibule are designed in a confined way to prevent fugitive emission of coke dust. e. Synchronous upgrading of existing coke ovens

The current coke oven facilities of Meishan Iron and Steel Company are backward. The fugitive emission of smoke gas reaches 4425t/a, SO2 412t/a and other harmful gas serious. Synchronously with the construction of this project, the current 3×65-duct coke ovens will be upgraded. They will adopt the process facilities and environmental protection measures same as those adopted by the intended coke ovens, thus basically bringing the fugitive emission from coke ovens under control and greatly improving the environment of the plant area. (2) Control measures for flue gas generated from heads and tails of sintering machines At present, the development of sinter dust collection technologies in China can be summed up into the following aspects: ◇ Universally adopt high-performance dust collectors, mainly including electro-precipitator and bag type dust collector; ◇ Combine large centralized dust collection system with decentralized dust collection; In recent years, Chinese and foreign sintering plants tend to use large centralized dust collection system. A dust collector usually contains tens or hundreds of dust collection points. Furthermore, such dust collection method is often combined with decentralized dust collection and separate dust collectors are installed for dust sources which are too far to be included into the large dust collection system. ◇ Priority is given to dry type dust collection in order to avoid sewage and sludge problems brought by wet type dust collection; ◇ Realize computerized control to raise equipment’s control capacity and ensure dust collection equipment runs in an optimized state. a. Flue gas control at the heads of sintering machines The amount of dust generated at the heads of sintering machine has a relation with such factors as sintering process, the characteristics of agglomerated charge, and sinter operating state. The intended 380m2 sintering machine adopts clean production process, such as: micropellet sintering and deep-bed operation. Such approaches will significantly reduce dust content of sinter waste gas and the concentration of smoke gas won’t exceed 2.5g/m3 in general. At machine head, 250m2 electrostatic precipitator is used. Its dust collection efficiency is above 99.5% and dust emission concentration is lower than 40 mg/m3, so it is rest assured that the pollutants emitted can steadily reach emission standard. b. Dust control at machine tail The initial dust concentration at machine tail is 5g/m3-15g/m3 in general. Electro precipitator with dust collection efficiency of above 99.5% is used. The dust emission concentration is lower than 40 mg/m3, steadily reaching emission standard. However, it is noteworthy that this is a large centralized dust collection system, so how to raise dust collection rate is an issue to which the design must give sufficient attention:

46

a) During design, importance shall be attached to the balance of resistance in each branch pipe and the adjustment of air volume, thus guaranteeing the dust collection efficiency of each dust source. b) Curve bends and tee pipes shall avoid orthogonal connection. The curvature of pipe bends should be as big as possible to reduce resistance loss and pipeline wear. c) Attention shall be paid to the design of dust hood. Although the structure of dust hood is simple, it has a direct bearing on the confinement of dust source and the effective use of air volume. A reasonably designed dust hood can generate double effect, as it not only confines dust source but also saves a great amount of energy. c. Dust control of the sieving and size stabilizing system for finished products The initial dust concentration in this system is usually lower than 5g/m3. According to design, an electro precipitator with dust collection efficiency of above 99.5% will be installed. The dust emission concentration is lower than 40mg/m3, lower than the emission limit 120mg/m3, steadily reaching emission standard. In conclusion, the intended sintering facility adopts high-performance dust collection facility to control smoke gas and uses large-scale centralized dust collection method. The dust collection design is advanced and reliable. Meanwhile, the assessment also points out the issues to which attention needs to be paid during design and management. Design and construction units are requested to attach importance to them. d. Pollution control of flue gas SO2 generated in machine heads and analysis of steady standard attainment

At present, there are three measures to control SO2 generated from sintering in China by and large: firstly, control sulfur content of raw and fuel material; secondly, adopt a high chimney to disperse and dilute it; thirdly, desulfurize sinter flue gas. The desulfurization installation needs a considerable amount of investment, accounting for above 30% of total investment of a project. What is more, its operation cost is high and the recovered byproducts usually don’t have a good way to use. The industrially advanced countries in Europe and America currently mostly adopt the method of dispersion by high chimney. In China, there still isn’t any practice about desulfurization of sinter flue gas. This intended 380 m2 sintering machine is not provided with flue gas desulfurization measure, but a space for flue gas desulfurization is reserved. It is believed this approach is feasible in light of China’s current situation, because: a) Sinter flue gas features large amount and low SO2 concentration. No economical and practical desulfurization method is available for the time being. b) The ore owned by Meishan Iron and Steel Company has high sulfur content, but the intended project will mostly use imported ore. In order to further reduce SO2 emission, it is planned to use 1.40 million tons of ore owned by Meishan Iron and Steel Company to reduce the average sulfur content in ore to 0.09459%. The sulfur content is in an average level compared to Chinese large sinter plants. The emission concentration of SO2 in flue gas is

47

726mg/m3, steadily reaching emission standard. Meanwhile, in order to control total amount of emission, the flue gas from power plant is desulfurized to partially reduce the increase of

SO2 from increased sinter. When the condition is ripe, desulfurization of sinter flue gas will be adopted. At present, Taiyuan Iron & Steel Corporation is carrying out initial preparatory work for sinter flue gas desulfurization project. (3) Analysis of dust collection measures for 3200m3 BF a. Dust collection of cast house Most of the large and medium blast furnaces built in recent decades have cast house dust collection facility. Except Wuhan Iron & Steel Corporation, other iron and steel companies all have adopted bag type dust collectors. In addition, with respect to the concentration of smoke gas at dust collector outlet, they all realize up-to-standard emission. This indicates China has no technical problem in the design and manufacture of cast house dust collection facility. The intended 3200m3 BF cast house has a set of long bag low pressure pulse bag filters. They work together with BF secondary flue gas dust collection system to collect dust. The dust collection efficiency: >99.0%. The filter material is membrane needle punched felt (24 chambers). According to Baosteel experience, the mode of induced draft from tap hole confined chamber is adopted, a hood is installed below tuyere platform, part of the platform is made into a movable platform and the hood and the movable platform are joined together. During normal tapping, the movable platform is slanted. During overhaul of tuyere, the movable platform is put down. In order to raise trap effect and prevent leakage of a small amount of flue gas, apron is installed around the hood. The area of the apron is about twice as much as that of the hood. In conclusion, this project borrows the experience of Baosteel. In addition, the filter material is membrane needle punched felt (24 chambers) characterized by damp resistance, easy dust removal and high efficiency. Provided the equipment is properly maintained and managed, emission standard can be steadily reached. b. Dust collection of raw and fuel material system The large and medium BF built or extended in recent years all adopt confined dust collection facilities for dust sources of raw and fuel material system and universally adopt bag type dust collectors. The dust collection design of raw and fuel material system in this project has two features: Firstly, the dust collectors of the raw and fuel material system are arranged by location and a mode combining large-scale centralized dust collection and decentralized dust collection is adopted. For example, the feeding system and transfer tower system have five sets of dust collection equipment in total and adopt decentralized layout. BF ore and coke bin, and railway stock bin have a large-scale dust collector and adopt large-scale centralized dust collection mode. In this way, the advantage of large-scale dust collection is fully played and meanwhile insufficient draft at far area and pipeline blockage due to too large coverage of dust collection

48

pipeline is avoided. Secondly, ore and coke bins are the biggest dust sources of this system. There are 15 bins in total. Discharging cars need to move between bins. The design adopts fixed-point discharging for the discharging cars and the dust collection method of bin top induced draft under the support of sealing rubber belt. The dust suction tube in the upper part of each bin has an electric shutoff valve. The opening and closure of the valve is interlocked with the discharge action of the discharging cars. When the car is discharging material at a bin, this electric valve corresponding to this bin will be switched on to suck wind, while other electric valves are closed to enhance the air suction effect of the bin where material is being discharged to reduce overall wind consumption of the system. This method has been universally applied in China and achieved good effect. It can not only effectively control dust dispersion but also obviously reduce wind consumption of dust collection, and energy consumption. Therefore, it is feasible that this project universally adopts bag type dust collectors in raw material dust collection system. Years’ experience has been accumulated in China and can be used as reference. It is a mature and reliable technology and can steadily reach emission standard. c. BF gas purification BF gas purification technologies can be classified into wet type purification technology and dry type purification technology. The dry type usually adopts bag type dust collector. It avoids the trouble of treating gas cleaning water, has small investment and low operation cost. It has been used in small blast furnaces since 1970s. At present, large blast furnaces still widely adopt wet type purification method. At present, there are three types of BF gas wet type purification process in the world: a) BF gas→gravity dust collector→washer→venturi→clean BF gas→Users b) BF gas→gravity dust collector→venturi→venturi→clean BF gas→Users c) BF gas→gravity dust collector→Bischoff scrubber→clean BF gas→Users Type a) is a comparatively backward process and universally adopted by normal-pressure BF. The large blast furnaces built in China in early period all adopt this process. The largest blast furnaces newly built in China and foreign countries no longer use it. The dust content in the gas purified by this system is lower than 10mg/m3 and can fully meet production requirement. However, it occupies large floor space, needs large investment in engineering construction and consumes much water (5~5.5kg/m3) and power. Type b) process has the following advantages: occupy a small floor space, save more than 60% of investment, and have small water consumption (2.1~2.2kg/m3). It is suitable for BF operated under high pressure. The large blast furnaces built in recent years in China almost all adopt this process, for example: 10# and 11#BF of Anshan Iron & Steel Corporation, and 1#, 2# and 3# BF of Baosteel. Its shortcomings: the first venturi is seriously worn and its throat and passage wall have to be replaced or mended about two years later. The life span is short. The key equipment of Type c) process is Bischoff scrubber which is a patented product of

49

German Bischoff Company. This system was firstly applied in West Europe and introduced into China in recent years. Kunming Iron & Steel Corporation is the first user. New 1# and 2# BFs of Anshan Iron & Steel Corporation also adopt this system. It is proved by production practice that Bischoff annular gap scrubber has an even flow field, can ensure gas dust collection quality even with a small pressure difference, and has a large adjustable range of pressure difference, small erosion wear and long use life. Moreover, the water consumption of gas cleaning is about 2.0kg/m3, equivalent to that of double venturi system. To summarize, the BF gas purification method adopted by this project: gravity dust collector+Bischoff scrubber is an advanced treatment method at present. (4) Dust collection measures for 150t converter and its refining furnace a. Control measures for primary converter flue gas This project adopts generation-4 OG system, i.e.: “annular gap (RSW) adjustable venturi new technology to purify primary converter flue gas. This technology has the following features: the flow cross-sectional area at throat has a large adjustment range, the adjustment is linear, and the flow cross-sectional area at venturi throat can be adjusted through a hydraulic servo device no matter how the flow of flue gas fluctuates or changes. As a result, little smoke comes out of converter throat opening, no much air is sucked into it, thus ensuring and strengthening the treatment effect of double venturi and raising gas recovery rate and dust collection efficiency. Comparing with original R-D throat in China, RSW has wider adjustment range. Under same resistance, the throat and water orifice are not easily blocked by lime, increasing the operation stability of the second venturi and obtaining higher dust collection efficiency than RD’s. This system is characterized by concise process, less equipment, easy maintenance, water and electricity saving, and good purification and recovery effect. The dust content in the recovered gas is ≤10mg/m3. 90m3/t steel of gas is recovered. The scale of the equipment is set at 100t converter. b. Control measures for secondary converter flue gas The secondary converter flue gas includes the flue gas generated from converter hot metal charging and blowing and the cutting of steel bound to throat, the smoke gas generated from inside the furnace during repair, the smoke gas generated during cutting with oxygen lance and the flue gas generated during conveyance and feeding of ferrous alloy. Secondary flue gas adopts large positive pressure reverse blow deashing large bag filter. Pulse deashing bag filter features high filtration speed, light equipment, small investment, small floor space, high deashing capacity, high dust collection efficiency, stable and reliable operation, and high assurance to steady attainment of emission standard. c. Control of flue gas generated from molten iron pretreatment Flue gas generated from molten iron pretreatment includes mixer flue gas, flue gas from external molten iron refining and so on. See Fig. 3-1. The flue gas from molten iron pretreatment adopts positive pressure reverse blow deashing large bag filter. Multiple dust suction points are arranged. The total air output is 600000m3/h. Dust collection efficiency exceeds 99.4%. The dust concentration in emitted flue gas is 30mg/m3. The flue gas is emitted

50

via a 40m chimney, meeting Grade-2 standard as defined in the Emission Standard of Air Pollutants for Industrial Kiln and Furnace (GB9078-1996) and basically guaranteeing no fugitive emission of smoke gas from converter workshop. (5) Dust collection measures for new thin-slab continuous casting and rolling machine a. When receiving protective slag, CCM crystallizer will generate a small amount of dust-containing flue gas. The flue gas is led by fan into continuous casting secondary cooling chamber where it is purified by vast water fog and then emitted via a 30m exhaust tube, meeting Grade-2 standard as defined in the Integrated Emission Standard of Air Pollutants. b. The instantaneous dust generated from unpacking and tipping of tundish is controlled by method of dust suppression through locally spraying water. c. Roller hearth-type heating furnace consists of heating section, common section and transverse movement section. The flue gas from combustion in heating section and common section is emitted via three 60m chimneys. The flue gas generated from transverse movement section is emitted via furnace top chimney. As desulfurized mixed gas is used, the emission concentration of SO2 is low. d. Finishing mill generates a small amount of flue gas that contains ferric oxide during rolling. Sinter-plate dust collector is installed. Its action principle is similar to bag type dust collector’s, but it has better deashing effect than the bag type dust collector. The dust concentration can be controlled below 20mg/m3. The stainless steel CCM of Taiyuan Iron & Steel Corporation adopts sinter-plate dust collector. Its dust emission concentration is below 10mg/m3 and the equipment is wear and corrosion resistant. Therefore, sinter-plate dust collection system has a lower possibility of accidental emission comparing with bag type dust collector.

Above-furnace auxiliary Exhaust hood for Exhaust hood of ladle Exhaust hood of raw material exhaust discharge of molten transferring station auxiliary raw material hood steel slag underground bin

Exhaust hood for molten Exhaust hood for Exhaust hood for iron vacuum treatment discharge of molten ferrous alloy Emit steel slag conveyance

Large bag filter Large exhaust Overflow exhaust hood of Exhaust hood in fan torpedo car desulfurization chamber of torpedo car Fig. 3-1 Coke gas dust collection system for molten iron pretreatment e. Baking and heating for continuous casting, and annealing furnace use clean gas as fuel, so

SO2 concentration in fugitive flue gas is not high. The emission of air pollutants from continuous casting facility is characterized by more sources of fugitive emission. This construction project is not an exception. The design adopts control measures to address the

51

characteristics of each pollution source. The steady attainment of emission standard can be realized by and large. f. The maintenance of tundish is an important step for continuous casting production. It is discontinuous and can be classified into light repair, medium repair, general overhaul and all repair. In this project, water spray is adopted to remove dust during tundish dismantlement and maintenance. No dust collection device is used. In view of pollution control in continuous casting process of Baosteel and the steelmaking plant of Benxi Iron & Steel Corporation, they all install dust collection facility for tundish maintenance to improve work environment. The popular dust collection facility in China is shrinking bellow-type sealing hood installed in the upper part of the slope platform and suction tube installed in the lower part of the lining removing platform. The dusty gas is emitted to the atmosphere after passing through bag type dust collector. Simply adopting spray method to settling dust may affect the progress and quality of repair, so it is suggested to reserve a space for dust collection facility. (6) Smoke gas control measures for cold rolling facility a. The ferric oxide-containing dust generated by welding unit and tension leveler adopts pulse bag filters. The air volume of the system is 72000m3/h and the dust emission concentration is lower than 30mg/m3. b. The acid washing and continuous rolling unit generates HCl mist and H2SO4 mist. Silicon coating unit generates chromic acid mist. 3 The initial emission concentration of acid mist is about 600mg/m ; meanwhile, NOx gas is generated, too. A cover is designed to seal each acid tank. An air suction system is installed to ensure the tank is under negative pressure. The acid mist sucked out is sent to purifying tower for treatment. HCl and chromic acids enter different washers for washing. Mixed acid mist is washed and neutralized by alkaline water and then the gas will be led to SCR treatment unit in which atomized KMnO4 and sodium thiosulfate are sprayed to convert NOx into “ammonia and water vapor”. The treatment efficiency is higher than 90%. The purified gas is emitted to the atmosphere via a chimney. The concentration of each kind of the main pollutants in the 3 3 3 purified gas is: HCl mist≤10mg/m , chromic acid mist≤0.07mg/m , NOx≤50mg/m , H2SO4 mist≤10 mg/m3, meeting Grade 2 standard as defined in the Integrated Emission Standard of Air Pollutants GB16297-1996. c. Rolling machine and finishing line generate oil mist. In order to avoid fugitive emission of oil mist in the workshop, it is designed that the oil mist is trapped by gas trap and smoke exhaust hood, purified by filter (purification rate is 90%), and finally emitted to outside of the workshop. The concentration of oil mist emitted to the outside is lower than 20mg/m3. The waste oil obtained from the filter is recycled by finishing unit. d. The degreasing of silicon steel generates alkali mist which is neutralized in spray washer. The emission concentration of alkali mist is lower than 10mg/m3. (7) Control measures for waste gas generated from gas refining

52

In this project, gas purification process adopts FRC desulfurization and decyanation, ammonia washing and distillation, removal of thick ammonia and so on. At present, this gas purification process is an advanced and mature gas purification technology and widely applied in China. 3 This process can reduce the content of H2S in gas to below 200mg/m . In this project, bleeding gas and production tail gas generated by each process section of gas purification system are connected section by section and led into gas pipeline in a centralized way. The integrated measures are all practical and effective control means which not only have desirable effect, small investment and easy operation but also can recover useful products and increase energy, showing good environmental benefit and certain economic benefit. Therefore, these control measures are environmentally, technically and economically feasible. As shown from the above analysis, the intended project adopts advanced measures to control smoke gas, acid mist and oil mist. They are mature measures universally adopted in current smelting and rolling processes in iron and steel firms. Among them, dust collection technology has made marked headway in recent years, for example: sinter-plate dust collector, the mesh of its filter plate can be as small as 4μm, showing high dust collection efficiency, easy operation and adaptation to humid environment. In addition, new-type membrane filter material is characterized by high filtration efficiency and good gas permeability. The data (“Metallurgical Environmental Protection”, 2001 Issue 1 P.49) indicate: an iron & steel company uses homemade 729 membrane filter material to replace conventional 729 filter material in its raw material dust collection system. As a result, the dust concentration at outlet is reduced from 79.4 mg/m3 to 4.8mg/m3 and the dust collection efficiency is significantly increased. After the implementation of the above measures, the emission concentration of smoke gas is far lower than Grade 2 standard as defined in the Integrated Emission Standard of Air Pollutants GB16297-1996, and the emission of other pollutants all meets Grade 2 standard as defined in the Integrated Emission Standard of Air Pollutants GB16297-1996. Therefore, the environmental control measures of waste gas generated in the intended project are feasible and can ensure that the total emission concentration of smoke gas from the intended project is lower than 2300t/a. (8) Measures to ensure fugitive emission concentration at boundary reaches standard In order to reduce the generation and emission of fugitive dust from stock house, material transfer process and smelting process, the project installs air suction and dust removing systems in material transfer, blending and sieving locations, BF bins, cast houses, mixers and so on. The air suction points are strictly confined. Dust trap points working in different time are switched over with hydraulic valves and interlocked with process equipment to reduce air volume handled by the system, cut power consumption, ensure dust removing effect, control the fugitive dust of stock house within 100t/a and fugitive emission in production steps within

400t/a and ensure the concentration of smoke gas, SO2, BaP, H2S, NH3 and other pollutants at boundary reach emission standard. In order to avoid secondary dust, all dust discharged from dust collectors is humidified and

53

taken away by truck in a confined manner. The concrete control measures are as follows: a. Raw material preparation and transport system and intermediate slag yard The handling and transfer of raw material are key sources of dust in stock house. The design adopts preventive and control measures for all dust sources. The dust in stock house is controlled by spraying water. Material transfer tower mainly adopts mechanical dust removal method. a) In the design, totally confined stock houses are adopted for sintering, coking, BF, converter and limekiln, and water spray dust suppression facilities are arranged in a certain space to increase water content of the raw material in surface layer to a degree that ordinary wind speed won’t lift the material up. The speed of the vehicles entering the site is limited in order to prevent secondary dust. The powdery material stored in stock houses is reasonably dispatched to control the amount of the material in stock houses. If a large amount of powdery raw material needs storing a long time, crustizing agent will be sprayed on the surface layer of the powdery raw material to reduce the generation of dust. b) All transfer towers, pulverizer rooms, transport vestibules and other storage construction are confined to avoid pollution of fugitive dust emission. Floor washing and other water spray dust suppression facilities are installed in main dust generating points to prevent secondary dust generation. c) Dust hood is installed in each dust generating point, such as: head of pulverizer, head of belt conveyor, material receiving point, material charging point and material discharging point. The dust trapped by them is led to main pipeline of dust collector in the respective workshop where the dust is collected. b. Coke plant a) High-pressure ammonia injection smokeless coal charging technology is adopted. Large-scale dust collecting ground station is adopted for coal charging and coke discharging. The three groups of coke ovens install ground station separately and can basically realize smokeless coal charging and coke discharging. b) CDQ method avoids the dust and other pollutants (such as: H2S and NH3) generated during CWQ and can also recover the heat of red coke. c) Strictly control the emission of malodor-containing gas during gas refining and chemical product production. c. BF system a) Dust collection of BF cast house In order to effectively control the large amount of smoke gas generated during tapping, cast house dust collection system is installed and air suction hoods are arranged at tapholes, upper part of ladle and so on. b) Dust collection of BF stock bins and transfer towers

54

The dust collection system consists of dust collection points under BF stock bins, above BF stock bins and at transfer towers. d. Converter steelmaking system a) Converter secondary flue gas dust collection system Converter secondary flue gas dust collection system is used to remove the smoke gas fugitively emitted from converter during molten iron charging and steel discharging, the smoke gas that OG hood can’t collect during converter blowing, the dust generated during transfer of converter ferric alloy raw material, the dust generated during cutting of the steel slag bound on converter oxygen lance, the dust generated during transfer of converter auxiliary raw material and the smoke gas fugitively emitted during argon bubbling at argon bubbling station. Large pulse bag filter is adopted. b) Bulk material dust collection system Steelmaking raw material (active lime, mill scale, coke and other bulk material) is delivered by belt conveyor to elevated bin where a large amount of dust is generated during discharging. Dust collecting points are set at each bin top and discharge outlet of each discharge cart. The underbin discharge outlets are controlled by pneumatic valves. Some dust is generated when weighing hopper and vibration feeder work, so dust trap points are set respectively. Dust is generated in transfer towers during transfer of raw material due to elevation drop of belt conveyor, so dust trap point is set at the place where material falls from belt conveyor. A dust collection system is installed for the above dust trap points, which is a large pulse bag filter. e. Control of dust from road transport After the intended project is completed, the total output of steel will increase from 3.00mt in 2004 to 5.30mt. Meanwhile, material transport amount will increase in the plant accordingly, so will the dust generated from material transfer and vehicle transport inside the plant. As transport dust features complex aspects, long line and wide area, main effort shall be made in strengthening management and avoiding fall of raw material to the road surface. Meanwhile, dedicated persons and vehicles shall be assigned to clean and water the roads; all areas that can be greened in the plant shall be greened, and an around-plant green isolation belt of 5-10m wide shall be built. Through the above measures, the transport dust inside the plant can be basically controlled. 3.2.2 Prevention and control measures for main wastewater pollution sources and feasibility analysis In this project, wastewater mainly includes phenol-cyanogen wastewater, floor wash water generated in general stock houses and sinter process, and wastewater generated from ironmaking, steelmaking, steel rolling and other workshops. In order to prevent pollution of water body, most process technologies and facilities have no pollution or mild pollution, and pertinent measures are adopted to control the wastewater inevitably generated during the process. The treated industrial wastewater is reused in production to maximize reutilization rate and minimize consumption of fresh water. The main measures controlling industrial

55

wastewater include: (1) Treatment of phenol-cyanogen wastewater generated from gas refining

◆ Phenol-cyanogen wastewater is generated during gas cooling and recovery of byproducts and mostly includes the wastewater from ammonia distillation, final gas cooling water, condensed water of gas pipeline, and phenol-containing wastewater generated during the recovery of tar and other byproducts. The existing facilities of Meishan Chemical Branch generate 85.7m3/h of phenol-cyanogen wastewater. The intended project will generate 98.9m3/h. 110.4m3/h of diluting water (equipment indirect cooling water) is added. The total wastewater is 295m3/h. A/O2 phenol and nitrogen removing – biochemical process is adopted. ◆ Phenol-cyanogen wastewater treatment station consists of pretreatment, biochemical treatment, post-coagulation treatment and sludge treatment. The pretreatment part consists of flotation tank and equalization tank. Biochemical treatment adopts A/O2 biological nitrogen removing process and consists of anoxic tank and aerobic tank (O1; O2), reflux settling tank, secondary settling tank and blower. The biochemical treatment capacity is 300m3/h. Post-coagulation treatment mainly adopts physiochemical method to treat the water discharged from secondary settling tank. The treated phenol-cyanogen wastewater amounts to about 295m3/h and is sent to BF for slag flushing. The remaining sludge and the sludge of flocculation sedimentation tank are concentrated and dewatered by dewaterer. The sludge cakes generated are used for coal blending. The phenol-cyanogen wastewater from coking plant is deoiled by oil separation tank, and then pumped to gas floating device to further remove residual oil. The discharged water enters heat exchanger where it exchanges heat with the stripped wastewater from stripper. When the temperature is increased to 95~100℃, it enters the stripper from top and is sprayed down via stuffing layer and meets upward vapor. The stripper is separated into two parts from the middle. The upper part is for stripping and the lower part for regeneration. The two parts are separated by a bubble-cap tray plate. The wastewater is blocked by the plate from which it flows out of the tower. Most of the phenol in the wastewater is transferred to vapor phase. The mixed gas is blown to stripper bottom. In the stripper, it upwardly meets the NaOH solution sprayed down from the upper and middle sections of stripper’s lower part. The phenol in the steam is absorbed by lye. The steam after phenol removal treatment enters the upper part of the stripper again via bubble cap where it meets again the downward wastewater. The lower part of the stripper is heated with fresh steam and the temperature is maintained at around 105℃. Lye is circulated. When reaching specific concentration, it will be taken out and crystallized to get sodium phenol and the solution will return to the circulation system. The phenol-removed wastewater passes through heat exchanger to recover part of sensible heat. After that, it will enter neutralization tank where its PH value is adjusted to below 8 with H2SO4. Then, the water enters cooling tower where it is cooled down to below 45℃ and then enters four aeration tanks which are connected in serial. In the tanks, it is subjected to anaerobic and aerobic biochemical treatment. The outflow water enters sedimentation tank. The clarified liquid is pressurized by pump and enters sand filter for filtration. The water 56

flowing out of the filter can meet discharge standard. Part or all of the active sludge settled in the sedimentation tank flows back to the aeration tank. When the sludge concentration in the aeration tank is too high, part of the sludge will be taken out and dewatered by press filter. The dewatered sludge is to be used as raw material for coal blending. ◆ After removal of phenol and biochemical treatment, the concentration and removal rate of pollutants in the phenol-cyanogen wastewater at discharge outlet are shown in Table 3-8. ◆ Phenol-cyanogen wastewater treatment station is designed with a capacity of treating 3.20mt/a of phenol-cyanogen wastewater from coking facility and 0.30mt/a of phenol-cyanogen wastewater generated from coke processing (existing facility of Meishan Chemical Branch). The total water volume is 295m3/h. ◆ Treating coking phenol-cyanogen wastewater by A/O2 method is used by many metallurgical enterprises in China, for example: the coke plants of Jiuquan Iron & Steel Corporation and Taiyuan Iron & Steel Corporation. All the treated wastewater can be reused for BF slag flushing, sinter mixing, gas cleaning and ash flushing of power plant. It is proved by practice this process is economical, practical and feasible. ◆ In order to ensure phenol-cyanogen wastewater won’t enter into other water consumption systems and soil during reuse, dedicated transmission pipelines will be built to deliver treated wastewater to BF for slag flushing. During flushing, the water is evaporated. Necessary measures are taken to prevent seepage and leakage of the slag pond. ◆ Considering the possible equipment faults, a large equalization tank is built at phenol-cyanogen wastewater treatment station, the water level of the collecting well in wastewater treatment system is strictly controlled, the water feeding time is defined for each process section and the water impoundment of the collecting well is controllable. In the event the wastewater treatment system stops production due to persistent power failure or emergent condition of sump pump, the wastewater will enter equalization tank for temporary storage and immediate measures are taken to solve the failure and resume operation. Table 3-8 Concentration and removal rate of pollutants in treated phenol-cyanogen wastewater Unit: mg/L

Pollutant pH SS COD NH3-N Ar-OH CN Petroleum Inflow water 6-9 ≤150 ≤2000 ≤200 ≤700 ≤12 ≤50 concentration Outflow water 6~9 ≤70 ≤100 ≤14 ≤0.5 ≤0.5 ≤7 concentration

Removal rate (%) 53.3 95 93 99.9 95.8 86

(2) Wastewater from sinter production The wastewater from sinter production is mainly floor wash water and equipment cooling

57

water from main factory building, vestibules and transfer towers. a. The equipment cooling water in sinter plant is not polluted except the temperature is raised.

This water will be reused after being cooled down by cooling tower and is not discharged to outside world. b. The intended 380m2 sintering machine will not discharge any industrial wastewater. However, the existing 2×130m2 sintering machines consume and discharge much water. It is suggested to eliminate or reform them. (3) Ironmaking wastewater Ironmaking step is a large water consumer, but the state-of-the-art ironmaking plant realizes zero discharge of industrial wastewater. The control technologies adopted mainly include water supply by quality, serial water supply, management of concentration rate, measured addition of chemicals, water filtration and automatic water makeup technology. As proved by production practice, these water conservation measures are effective. The large blast furnaces built in recent years in China all adopt these technologies. Therefore, the intended 3200 m3 BF system won’t discharge any industrial wastewater. a. Soft water closed circulating and cooling system adopts self-cleaning filter. Industrial clean water circulating and cooling system is provided with a bypass filter. Gas cleaning water circulating system adopts such measures as plate settlement, chemical addition, concentration, and filtration. As proved by the practice of ironmaking production, these measures play an effective role in maintaining the stability of water quality and the normal operation of the system. b. The net amount of circulating water totals 6740m3/h, the amount of circulating water is 6500m3/h and the amount of makeup water is 240m3/h. In order to stabilize water quality, 85m3/h of water is discharged to supplement slag flushing water circulation system and 15m3/h of cooling water is supplied to dust collectors to humidify collected ash. This system also adopts such measures as cooling, filtration and measured addition of chemicals. Water temperature and SS control measures are sound. Therefore, this system has no problem to maintain the stability of water quality. c. BF gas cleaning water circulation system In this system, the amount of circulating water is 1500m3/h, the amount of makeup water is 75m3/h, and water is discharged mainly by means of evaporation and sludge. The concentration rate is high, mainly because Bischoff gas scrubber can realize serial use of the wash water. As this system strengthens such measures as cooling, plate settlement, chemical addition, concentration and filtration, water temperature and SS concentration control measures are sound and the sludge formed is discharged together with gas slime. The actual operation results of 5# BF of Benxi Iron & Steel Corporation, 1# new BF of Anshan Iron & Steel Corporation and 6# BF of Kunming Iron & Steel Corporation indicate this system can operate stably without any doubt. d. BF slag flushing water circulation system

58

In this system, the amount of circulating water is 1500m3/h and the amount of makeup water is 247m3/h of which 60m3/h is phenol-cyanogen wastewater and 85m3/h is the blowdown from industrial water circulating and cooling system. As a large amount of water is evaporated or carried away by granulating slag, this system is under serious water deficiency, but due to the output of a large amount of granulating slag, scale (if any) will be carried away by granulating slag, too. It is proved by years’ production practice, this system has no such problems as scaling and blockage, but SS concentration in circulating water shall be controlled to prevent wear of water pump and pipeline. Therefore, new BF system can realize zero discharge. e. As Meishan Iron and Steel Company still has 2×1250 m3 BFs and a 1280 m3 BF which has undergone general overhaul, its water supply and drainage system is backward. Particularly, the 2×1250m3 BFs were built in 1970, their water supply and drainage system is backward and a large amount of water is consumed and discharged, so they should be eliminated or upgraded. (4) Waste water from steelmaking continuous casting The wastewater pollution sources in steelmaking process mainly include: equipment cooling water (water used by converter oxygen lance, LF, crystallizer and other equipment), converter gas cleaning wastewater, CCM casting mill scale wastewater, and continuous casting cooling wastewater which contains mill scale and a small amount of oil. a. Equipment cooling water: this water changes nothing except the temperature is raised. It is sent back to absorbing well after being cooled in cooling tower. From the well, it will be supplied to water consumers as per their need. In order to ensure the normal and stable operation of water supply, the system is installed with bypass filtration facility and water quality stabilizing unit and discharges a small amount of wastewater. b. Converter gas cleaning wastewater: Currently, the control of steelmaking wastewater is developing towards the direction of “circulated water supply, elimination of pollution, and comprehensive utilization”. In enterprises adopting wet method to clean converter flue gas, vertical sedimentation basin or radial sedimentation basin is universally used to eliminate horizontal sedimentation tanks, coagulation settlement replaces natural settlement and dispersant is used to solve scaling of circulating water. The intended converter adopts the technologies of “supplementing dirty water with clean water” and stabilizing water quality through bypass filtration and chemicals in water circulation system. As a result, water reutilization rate is raised to 97% and the generation of wastewater is reduced by process method. Two coarse particle separators and 8 plate settlers are used to treat the wastewater generated from dust removal of converter. Firstly, coarse particle separators are used to remove large dust particles (>60μm) accounting for 15% of the total SS in the water. After that, plate settlers are used to reduce SS concentration to below 100mg/L. The slurry in the settlers is filtrated with plate and frame press filter, and then is cooled and reused.

59

In the aspect of water quality stabilization, as lime is added during steelmaking as slag making material, a large amount of Ca2+ enters the wastewater generated from dust removal. The increase of Ca2+ results in the generation of scale during water circulation. If it is not handled properly, the circulation will become impossible and sewage has to be discharged. For this reason, mature and reliable chemicals are added into the water to settle down SS particles and prevent scaling. This treatment method is the most popular one in Chinese iron and steel companies. Three 300t converters in steelmaking plant of Baosteel adopt the above coarse particle separation – coagulation settlement – water quality stabilization method to purify water. Consequently, the overflow water of the settlers maintains below 50mg/L. The practice proves that the water quality can fully meet the requirement on the inflow water of sewage treatment plant. Moreover, the fine SS particles are usually settled down in radial sedimentation basin, whereas this project adopts more advanced plate settlers. The slurry settled from plate is filtrated with plate and frame press filter. The cakes are sent to sinter plant. The wastewater returns to the system for retreatment. In this way, a desirable settlement effect is achieved, the requirement on water quality is met, settlement area is increased and floor space is saved. This system is assessed feasible. For the intended converter, the total amount of industrial wastewater is 80m3/h with SS concentration of lower than 100mg/L, and other water discharge indexes all meet the requirement on the quality indexes of inflow water of sewage treatment plant. Its flow chart is shown in Fig. 3-2.

Overhead runner Coarse particle Plate settler Cooling tower Wastewater separation Sludge Plate and frame User press filter

Return to sinter process for material blending Filtration residue

Fig. 3-2 Schematic flow chart of converter gas cleaning wastewater

But, according to the study on multiple solutions to the filtration and utilization of the slurry generated from converter gas purification in domestic iron and steel enterprises, for example: baking cakes dry and then sending them to sinter process; adding lime into cakes and carbonizing them into coolant for steelmaking; sintering the cakes directly; not using plate and frame press filter but directly pumping the settled slurry to sinter process where it is fed into the first mixing machine for utilization, years’ practice proves that the approach of directly sintering slurry and sending it to the first mixing machine for use is feasible and reasonable. Chinese iron and steel companies like Baosteel, Shaoshan Iron & Steel Corporation and Jinan Iron & Steel Corporation all use this method. For this reason, we suggest abandoning plate and frame press filtration system and adopting the solution of directly sending slurry to sinter process for use.

60

c. Treatment of wastewater from continuous casting The treatment method for wastewater generated from continuous casting: wastewater→whirl well→advection sedimentation basin (with deoiling device)→filtration→reuse, without external discharge. This system mainly supplies CCM secondary cooling water, torch cutter granulation water, and mill scale flushing water. It adopts direct cooling. The backwater is not only hot but also contaminated (containing solid impurities like fine mill scale particles and oil). The sewage converges in scale ditch and flows into primary scale sump where large mill scale particles are settled down (the settled particles are taken out with grab bucket and filtered out water, then directly transported to sinter plant for comprehensive utilization). After that, part of the water is pressurized by pump and used to wash mill scale; another part of the water is pumped to chemical deoiling precipitator where the water is added with chemicals and undergoes secondary settlement treatment. The supernatant of the precipitator flows by gravity to hot water basin where it is pumped to sewage cooling tower. The cooled water is pressurized by pump and filtered with pipeline filter to control the diameter of impurities. After that, the water is reused. The mill scale sludge discharged from the bottom of the chemical deoiler is pressurized by pump and sent to plate and frame press filter for dewatering treatment. The cake sludge is loaded onto trucks by forklift and transported to sinter plant for comprehensive utilization. The filtrate of the press filter is sent to converter dirty circulating water system for reuse. This project adopts three-stage process, i.e.: whirl sedimentation basin → secondary advection sedimentation basin → filter → cooling, to treat the wastewater generated from continuous casting and rolling process. It is also a common method in China. The treatment of the wastewater generated from 1700 medium/thin-slab continuous casting and rolling of Anshan Iron & Steel Corporation, and the wastewater generated from the hot rolling plant of Panzhihua Iron & Steel Corporation all adopts this method. The intended thin-slab continuous casting and rolling facility will discharge 215m3/h of wastewater. The whole plant will discharge 500m3/h of wastewater from continuous casting and rolling process. The wastewater is discharged into the drainage pipeline in the plant and enters the intended reuse water treatment plant for unified treatment. The treated water will be reused as reclaimed water. (5) Wastewater generated from cold rolling The cold rolling wastewater of the new facilities mainly includes the equipment cooling water from cold mills, roller bearings and rollers, mill scale flushing wastewater generated during rolling, and the acid, alkali and oil-containing wastewater generated from plating and coating units. a. Equipment cooling water: this water is not polluted except that the temperature is increased. Therefore, this wastewater is reused after being cooled by cooling tower. The blowdown water of the cooling tower enters mill scale flushing wastewater treatment system and is not discharged to outside environment. b. Mill scale flushing wastewater: wastewater enters scale ditch→scale sump→(whirl

61

well)→deoiling unit→press filter→cooling tower→reuse. The concrete flow chart is shown in Fig. 3-3. The wastewater treatment device selected by this process is a mature method universally used in China.

Wastewater Sump Whirl well Oil separation Recovery of tank waste oil

Reuse of wastewater Cooling tower Press filter Filter cake

Return to sinter process for material blending

Fig. 3-3 Schematic flow chart of mill scale wastewater treatment c. Acidic/alkaline wastewater treatment system A circulating water treatment system is arranged for the acidic and alkaline wastewater discharged from cold rolling units. After being treated in equalization tank, primary neutralization tank, secondary neutralization tank, flocculation tank, reaction clarification tank, final neutralization tank and filtration, the wastewater is reused. d. Chromic wastewater treatment system This project has a chrome-containing wastewater treatment system with two-level deoxidation tank. Reducer is added into the deoxidation tank to reduce Cr6+ into Cr3+ and ensure the Cr6+ concentration in outflow water is below 0.5mg/L. the water is sent to reuse water treatment facility for further treatment. e. Waste emulsion and oily wastewater treatment system This project has a waste emulsion and oily wastewater treatment system in which paper filter is used to remove coarse particles in the wastewater, ultra filter unit is used to separate oil from water and the water is further treated with membrane bio-reactor to guarantee the discharged water meets discharge requirement. f. Waste acid regeneration unit A waste acid regeneration unit is installed to treat the waste acid generated from cold rolling mill in order to reduce the consumption of waste acid and convert waste into resources. Every water treatment system is provided with a sludge treatment system. g. When acidic/alkaline and chrome-containing wastewater is treated to reach Grade 1 discharge standard, it is further treated by hot slag splashing method or treated in general sewage treatment station and then is reused. In Taiyuan Iron & Steel Corporation and Benxi Iron & Steel Corporation, the wastewater is sent to general sewage treatment station for further treatment. In order to ensure acidic/alkaline wastewater won’t enter into other water consumption 62

systems and soil during reuse, dedicated transmission pipelines will be built to deliver treated wastewater to temporary steel slag yard. The slag yard is seepage and leakage resistant.

Considering the possible equipment faults, a large equalization tank is built at wastewater treatment station, the water level of the collecting well in wastewater treatment system is strictly controlled, the water feeding time is defined for each process section and the water impoundment of the collecting well is controllable. In the event the wastewater treatment system stops production due to persistent power failure or emergent condition of sump pump, the wastewater will enter equalization tank for temporary storage and immediate measures will be taken to solve the failure and resume operation. (6) Other wastewater Except the wastewater generated from main production steps in this project during production, the supporting production departments, such as: machine repair, oxygen generation, laboratory, transport and energy departments generate 345m3/h of wastewater in total. The main pollutant in the wastewater is SS. The wastewater is discharged into the drainage pipeline in the plant and enters the intended reuse water treatment plant for unified treatment. The treated water will be reused as reclaimed water. All domestic sewage generated by production and supporting departments can be treated in septic tanks and then discharged into the drainage pipeline in the plant and enters West Discharge Outlet. (7) Initial rainwater treatment On the premises of Meishan Iron and Steel Company, rainwater and sewage are separated. Initial rainwater is filtrated with the grids of rainwater well and then all enters the general sewage treatment plant for treatment. (8) General wastewater treatment station (general reuse water treatment station) Meishan Iron and Steel Company has made great effort and outstanding achievement in saving water in recent years. In 2003, the amount of makeup fresh water per ton of steel in the company (not including chemical and domestic water) was reduced to 16.34m3. Circulating water treatment facility has been universally used in every process step. The measures stabilizing water quality are advanced. Nevertheless, there are still a small number of users directly discharging wastewater. Due to topographic restriction, they directly discharge sewage into West Discharge Outlet. Moreover, the amount of discharged sewage from each circulating water system at each step is large, so the sewage needs to be treated in a centralized manner. In terms of water consumption indexes, the enterprise still has some gap from Chinese or foreign leading enterprises. In 2004, the consumption of fresh water per ton of steel was 12.1m3. Therefore, to continue to explore the potential of water conservation and reduce the unit consumption of fresh water is very essential for economically sustainable development of Meishan Iron and Steel Company. Meanwhile it is a matter of significance to reducing the pollution of water resources in the Changjiang River, improving water environment of Meishan Iron and Steel Company, protecting drinking water resources of the company, lifting the company’s social and public image and increasing the total amount of available water. It has remarkable social and environmental benefit.

63

Under the condition of adjusting product mix and increasing 2.30mt of steel production capacity, Meishan Iron and Steel Company sets its water consumption target as: 5m3 of fresh water consumption per ton of steel and 97.5% of reutilization rate of industrial water. For this reason, it is decided all industrial wastewater generated by the company will be intercepted at West Discharge Outlet, the general discharge outlet of Meishan Iron and Steel Company where the water is treated to reach the standard for industrial reuse water and then sent back to production steps for reuse. The intended general sewage treatment plant needs RMB110 million of investment, has a design treatment capacity of 100,000m3/d and will receive all industrial wastewater from Meishan Iron and Steel Company and partial domestic sewage from Meishan area. The plant is under design at present. The Environmental Protection Branch of the Central Research Institute of Building and Construction, MCC Group undertakes this design task. The inflow water is typical industrial wastewater of an iron and steel enterprise. Although it also includes some domestic sewage and contains organics, its biochemical treatment ability is poor and biochemical decomposition method is not suitable for it. The best method to remove such organic and inorganic pollutants is physiochemical method. In order to ensure the treated outflow water can be used as industrial makeup water, water softening step is added to remove temporary hardness during deep treatment of reuse water. Due to restriction of land area, high performance, energy saving and multifunctional equipment shall be reflected in every treatment unit. As the content of pollutants in the water coming from the plant area fluctuates considerably, direct treatment is difficult. Therefore, it is very necessary to retain the West Open Channel to regulate water quality. The process flow has the following features: As iron and steel wastewater contains oil, this solution is designed with deoiling equalization tanks to prevent the follow-up treatment effect from being affected; High-performance flocculation and sedimentation tank adopts the sludge backflow process of primary coagulation and secondary flocculation. While removing a majority of SS and organics in the sewage, it can also remove oil, iron, manganese and other trace pollutants. Plate settlement and sludge concentration clarify the outflow water. The post coagulation and chemical addition can raise the efficiency of Type D filter; Type D filter with 863 self adaptive filter material - comet fiber filter material as technical core is characterized by small floor space, stable quality of outflow water and easy operation and management. As the core process of this solution is high-performance flocculation and sedimentation tank and Type D filter, in order to ensure stable treatment effect, chemical adding equipment and control system supporting this process are all imported. The quality of inflow water required by the system and the realizable quality of outflow water are described in Table 3-9. Based on the quality of treated water, the wastewater will be reused as spray water of general stock houses, makeup water of the net circulating water at pre-ironmaking system and post-

64

ironmaking system, makeup water of dirty circulating water, and floor wash water of the plants. It can save 31.00m3/a of fresh water and reduce the consumption of fresh water per ton of steel in Meishan Iron and Steel Company to 5m3 from 12.1m3 in 2004. By now, the reuse water plant of Benxi Iron & Steel Corporation has been built up. Reuse water and fresh water are mixed in the distribution tank and then supplied to each process step through one pipeline. The effect is good. In contrast, the supply of reuse water currently being designed by Meishan Iron and Steel Company is separated from the supply of fresh water. It needs two pipelines to supply water to each plant and has no advantage in management and construction cost, so we suggest Meishan Iron and Steel Company carefully study the approach of Benxi Iron & Steel Corporation, learn from strong points to offset its weakness and adopt more reasonable and economical water supply method.

Sewage at West Thick grid Thin grid Deoiling Distribution well Discharge Outlet equalization tank Initial rainwater in the plant area Clear water Clear water tank Type D tank High-performance flocculation tank

Sludge treatment Sludge yard Chemical addition and preparation system Transport out to rubbish landfill

Fig. 3-4 Schematic flow chart of centralized sewage treatment plant for industrial wastewater generated by Meishan Iron and Steel Company

Table 3-9 Indexes of inflow and outflow water of the general sewage treatment plant (mg/L) Outflow Water Inflow No. Item Unit water consumption water index index requirement 1 pH 8~9 7.5~9 7.0-8.0 2 SS mg/l 80~150 ≤5 ≤20 3 CODcr mg/l 250 50 ≤100 4 Oil mg/l 2~3 ≤2 ≤3.0

5 Total hardness mg/l 195.1 ≤100 Based on CaCO3

6 Total alkalinity mg/l 145.1 Based on CaCO3 7 Salt content mg/l 400 400 8 Cl- mg/l 50~80

65

3.2.3 Analysis of noise control The main noise sources in this project: all kinds of production equipment, mixing machines, sieving machines, dust collection fans, air compressors, blowers, gas compressors and pumps should select low-noise equipment during design so far it is possible; for mixing machines, sieving machines and water pumps, mufflers are installed at each inlet of equipment and fan and outlet of air compressor; Dust collection fans, gas compressors, air compressors and water pumps are placed inside buildings separately; separate operation rooms, control rooms and rest rooms are arranged in workshops. Therefore, through sound insulation, screening of factory building walls, and air absorption and attenuation by distance, equipment noise at boundary can meet the requirement as specified in the Standard of Noise at Boundary of Industrial Enterprises. 3.2.4 Solid waste treatment and comprehensive utilization Iron and steel smelting generates a large amount of solid wastes, such as: BF slag, converter slag, ferric dust sludge, waste steel, tar residues, asphalt residues and industrial rubbish. These wastes are all useful resources in general. Through treatment, they can be reused. The treatment and comprehensive utilization of the solid waste generated by the intended project are shown in Fig. 3-6. All solid waste generated during production and operation of the project can all be recycled and reused or properly disposed. 3.2.4.1 Existing solid waste treatment and utilization facilities of Meishan Iron and Steel Company Meishan Iron and Steel Company pays great attention to comprehensive utilization of resources. It has set up Resource Comprehensive Utilization Committee to comprehensively coordinate the resource comprehensive utilization work of Meishan Iron and Steel Company. The comprehensive utilization of resources is managed by two departments. Manufacture Management Department is responsible for the utilization of “waste” resources and Safety & Environmental Protection Department is responsible for waste disposal. A resource comprehensive utilization company undertakes the comprehensive utilization of all wastes generated by the company. At present, all iron and CaO-containing dust sludge generated during production in Meishan Iron and Steel Company (such as: steelmaking dust ash, ironmaking dust ash, hot rolling sludge, sinter dust ash, coking coal dust and coke breeze) is blended into sinter raw material system and used as sinter raw material. Steelmaking sludge is pelletized and smelted in converter as steelmaking raw material. Steel slag is disposed by a joint venture steel slag company. Hot rolling mill scale is used to produce magnetic material. (1) Currently there are two 30 kt/a red ferric oxide magnetic material production line (built in 2001 and 2004 respectively). Steel rolling mill scale is used to produce magnetic material. This approach raises added value of mill scale, ensures mill scale is comprehensively utilized and generates better social and economic benefit. (2) In 2000, a 20 kt/a converter sludge pellet production line was built, which mixes converter sludge with limekiln leftovers, adds a certain amount adhesive and pelletizes the mixture and bakes it into finished pellets. The pellets are used as steelmaking raw material to substitute part of the iron ore and are reused in steelmaking converter.

66

(3) The dust collected by all dust collectors of Meishan Iron and Steel Company are all reused in production system. (4) In 2004, slag micropowder installation phase-1 project was completed. Some of the BF granulating slag in Meishan Iron and Steel Company is ground up in the slag micropowder production line. The powder is used as new-type building material. Part of it is sold out as raw building material. (5) Converter steel slag is delivered to the temporary storage yard north of the pump room to the west of the road at No. 25, Meishan at first. Then it will be treated by Nanjing Meishan Steel Slag Treatment Co., Ltd. After magnetic separation and sieving, waste steel is recovered and reutilized by Meishan Iron and Steel Company. The screenings is sent to wall material factories for comprehensive utilization. (6) Fly ash and slag are sold out for comprehensive utilization as raw building material. (7) Waste oil is transferred to other organizations for comprehensive utilization after going through required procedure strictly according to national regulations. 3.2.4.2 Solid waste disposal and utilization measures of the intended project (1) Sinter It is designed to reutilize the whole blending system. Sinter, ironmaking and steelmaking dust sludge and steel rolling mill scale are generally called ferric dust sludge. These solid wastes all contain ferric raw material, so they can be 100% utilized. (2) Ironmaking Solid waste generated in ironmaking step mainly includes BF slag, gas ash mud and dust ash. BF slag is pelletized into BF granulating slag. The BF granulating slag is used in cement building material industry and is a very popular base material. It is a widely adopted way of comprehensive utilization of BF slag. The utilization rate is 100%. BF gas ash and dust ash contain high iron. They are excellent sinter raw material and all utilized as sinter raw material. The gas slime recovered by BF gas cleaning system is very fine and sticky, creating difficulty for blending operation and affecting the quality of sinter ore. The gas slime in this project contains about 25~30% water. It is mixed with the return fines of sinter plant into pellets, which contain less than 10% water and can be utilized. This method can raise the air permeability of mixture and improve sinter process. (3) Solid waste generated from coking and chemical product processing The coal dust recovered from coal preparation system in coking plant is returned to coking coal process system for reuse; The coke dust recovered from coke discharging dust collection system of coke oven, the coke dust recovered from coking sieving dust collection system and the coke dust recovered from CDQ dust collection system are all humidified and then transported out of the plant by tanker; The tar residues discharged from mechanized ammonia separation tank, the asphalt residues discharged from ammonia distiller and waste solution from desulfurization process are all delivered to coal preparation workshop in a centralized way and blended into coking coal and 67

used for coking; The residues from the regenerator in crude benzol distillation section are added into tar tank.

The residues generated during tar separation and processing are blended into coking coal. The above control measures are common control means in domestic coking industry. They are economical, practical and effective and all comply with the regulations relevant with slag treatment. Therefore, the measures that the coking and chemical product processing project adopts to control solid waste is feasible. (4) Steelmaking There are many ways to utilize steel slag. The technology is going to become mature. With shallow tray hot splashing technology, steel slag has been successfully used as flux of iron and steel smelting, sinter burden and cement admixture. Dust ash and the converter dust sludge obtained after filtration by plate and frame filter and dewatering both contain high iron and low SiO2 and other impurities. They are sent to sinter plant where they are used as raw material for sinter production. This is also a popular method to treat converter dust sludge in China. From the perspective of production practice, the disposal technology is mature and reliable. The dust ash and converter dust sludge generate in this project are all delivered to sinter plant for comprehensive utilization. (5) Continuous casting and rolling The solid waste generated in this project includes mill scale, casting slag, precipitated sludge, waste oil and waste refractory. Except that waste oil is hazardous solid waste, others are all ordinary solid wastes. Among them, the waste oil recovered from deoiling facility in secondary advection sedimentation basin is drummed and sold out. At present, Anshan Iron & Steel Corporation adopts this method to dispose the waste oil generated from the sewage treatment system of 1700mm and 1780mm rolling mills. This measure is reliable. Mill scale and precipitated sludge are ferric dust sludge. They are disposed by a reliable method, i.e.: sent to sinter plant for comprehensive utilization; 65% of waste steel is recovered from casting slag. A small amount of residues are used to pave road. (6) Cold rolling Cold rolling facility generates waste steel, waste acid, water treatment sludge and zinc residues. a. Treatment of waste steel leftovers and ferric dust The steel sheet leftovers of slitting unit, skin pass mill and rolling mill in this project are all recycled and utilized. The ferric dust sludge is sent to sinter plant for reuse. b. Treatment of waste acid Waste acid comes from acid wash section. After treated in APU (acid purification unit) on the line, the waste acid is circulated and reused and won’t be discharged to outside. c. Sludge treatment The sludge generated from the radial flow sedimentation tank at neutralization station enters

68

sludge concentration tank and is treated with plate and frame press filter. The treated sludge cakes are sent to new landfill for disposal. Chromic sludge is sent to sinter plant and blended with material. d. Treatment of waste oil Meishan Iron and Steel Company has entrusted Wuxi Sandeli Chemical Co., Ltd. (hazardous waste operation license No.: JS.0282OOD040) to recover and utilize waste oil all the time. The main equipment of this company includes a set of waste oil regeneration equipment and two sets of grease production equipment. The main production process is as follows: Regeneration of waste oil: firstly heat waste oil to dewater it physically, and then add bleaching earth for physical slag settlement, filter it and add additives to complete the regeneration of waste oil. Grease processing: add waste oil, animal oil and lime in a certain ratio, then heat the mixture with steam to needed temperature, maintain this temperature for a specific time. In the end, grease will be generated. The regenerated oil and produced lubricant are sold by the company. Relevant agreement is described in annex. e. Zinc residues The galvanization of cold rolling generates about 550t/a of zinc residues. After recovery, it is sent to Yixing Jiangfeng Smeltery for treatment (hazardous waste operation license No.: JS0282OOD060). Relevant agreement is described in annex. f. Ferric oxide powder generated from steel rolling and acid wash processes, and mill scale are used to produce magnetic material by using the company’s existing facilities. 3.2.5 Control measures for general stock house (1) The general stock house of Meishan Iron and Steel Company mainly stores iron ore concentrate and anthracite. The general stock house is surrounded with isolation wall to prevent environmental pollution of dust. On days with strong wind, effort shall be made to minimize the transport of raw material to the general stock house. Water sprinkling devices are installed in the stock house. The sprinkling plan and amount are decided according to climatic characteristics to minimize dust generation from raw material layer. In addition, it is suggested to build protection forest and plant trees with luxuriant leaves and branches and leaf surface less sensitive to air permeation to minimize negative environmental impact of the dust generated from the general stock house. (2) Control measures of coal yard leaching water When there is plentiful rainfall, leaching water will be generated in coal yard. The leaching water contains pulverized coal and other water extracts. If the leaching water is directly discharged without any treatment, it will affect environment. It is designed to build closed ditch, collecting basin, grit removal chamber and other water treatment structures around the coal yard to reduce material loss, fallout and overflow and maximally avoid the uncontrolled overflow of the leaching water at coal yard. The water accumulated in collecting basin is used to sprinkle the coal yard. The pulverized coal inside grit removal chamber is transported back for production use on a regular basis to eliminate water impact of the leaching water generated by the coal yard. The control measure is feasible.

69

4. Analysis for Pollutant Meeting-standard Emission and Total

Amount Control

4.1 Determination of enterprise pollutant emission and total amount control quotas The total amount control for pollutants is one of the specific measures to improve environmental quality at present. The Nation requires definitely to implement the overall pollution emission amount control for the following pollution factors: SO2 industrial powder dust and smoke dust in waste gas, CODcr and ammonia nitrogen in waste water as well as solid waste. There are usually two methods to determine the total amount control of the project: one is that the local environmental protection department gives the overall pollutant emission amount to development organization according to local “total amount control” quotas (amount control quotas for pollutant emission in certain area); the other is to calculate the overall pollutant emission amount of the project according to environment assessment report, and then control the pollutant emission to meet the requirement of overall pollutant emission amount calculated from environment assessment report after the implement of the project according to the principle of “meeting-standard pollutant emission”. Meishan Iron and Steel Company is an old enterprise. Nanjing Municipal Environmental Protection Bureau gives it total amount quota every year, ant the quota reduces year by year. As for this project, the principle of total amount control is to increase the output without increasing pollution, bring up the old by the new, and reduce the overall emission amount of main pollutants by perfecting and improving environmental protection units. However, sinter ore increases a lot for the project, and it is without example for the actual use of sintering flue gas desulphurization. So the amount of the own ore is reduced so as to reduce the emission of

SO2. In this way, the total emission of smoke and powder dust and SO2 from Meishan Iron and Steel Company is reduced after the completion of the project. This chapter will analyze whether the overall pollutant emission amount meet the total amount quotas of powder and smoke dust, SO2 and CODcr in waste water given by Nanjing Municipal Environmental Protection Bureau. 4.2 Pollutant meeting-standard emission and total amount control analysis for planned project 4.2.1 Waste gas and its pollutant meeting-standard emission and total amount control (1) Waste gas meeting-standard emission analysis for planned project The main pollutant emission in waste gas after the waste gas pollutant source of planned project is treated is listed in table 3-5. From the table we can see that the main pollutant emission can meet the standard. (2) Total amount control quotas for waste gas and its pollutant in the whole company The overall amount of waste gas pollutant emission given to Meishan Iron and Steel

70

Company (including Meishan Chemical Subcompany) by Nanjing Municipal Environmental Protection Bureau in 2004 is in table 4-1. In order to assist the construction of the project, the

Bureau increases the overall SO2 emission by 2000t through the deployment inside the city. The overall emission of smoke and powder dust stays the same. The waste gas pollutant emission of the whole Meishan Iron and Steel Company is also in table 4-1. From the table we can see that the total amount control quotas for waste gas and its pollutants meet Nanjing total amount quotas requirement. Table 4-1 Waste gas as well as its main pollutant emission and total amount control quotas Pollutant (t/a) No. Project Smoke and powder dust SO2 Emission amount of the whole Meishan 1 Iron and Steel Company plant after the 6057 17243 completion of the project Total amount control quotas given by 2 Nanjing Municipal Environmental 10600 19000 Protection Bureau in 2004 3 Total amount control quotas added in 2005 2000 Whether meet the total amount control 4 Yes Yes quotas Note: Emission amount of pollutants reckoned in inorganizational discharge source. 4.2.2 Waste water and its pollutant meeting-standard discharge and total amount control quotas After the project is completed and put into production, waste water of the whole plant will be treated by planned sewage-treatment plant uniformly and then used as heavy water. The discharge amount is 2.52m3/t.steel (1.35 when thermoelectricity, Meishan Chemical Subcompany and sanitary waste water are excluded). The waste water discharged from west discharge port and treated to meet first-level discharge standard through the year is 1145 m3/h. The discharge quality is in Table 4-2. The annual waste water discharged from west discharge port to Yangtze River is 10,030,200 m3. The clean recycling condensate and steam condensate of Coking Subcompany and Meishan Chemical Subcompany discharged from north discharge port are 379m3/h and 332.004m3/a. After the completion of the project, the total waste water discharge amount will be substantially reduced, and phenol and cyanide waste water, acid and alkali waste water as well as chromic waste water will not be discharged to outside. So the water pollutant discharge amount to Yangtze River from west and north discharge ports will be substantially reduced. And COD will be reduced by 1630.5t/a, the reducing rate being 66%. In this way the influence on the water environment of Yangtze River will be evidently reduced. See Table 4-2. 71

Table 4-2 Changes in waste water discharge amount from Meishan Iron and Steel Company

Existing waste water discharge After the completion of the Total amount given project Meishan Iron and Steel Meishan Chemical Total Reduced by Nanjing Municipal Company(west discharge Subcompany discharge ( west discharge port and amount Environmental Protection Bureau Project name port) ( north discharge port) amount north discharge port)

Average DISCHARGE Average Average Discharge Discharge concentration AMOUNT concentration (t/a) concentration (t/a) (t/a) amount(t/a) amount(t/a) (mg/l) (T/A) (mg/l) (mg/l)

Waste water — 19080000 — 9688560 28768560 — 13350240 15418320 amount

PH 6-9 — 7.6 — — — 6-9

CODCr 56.5 1078 125.9 1220 2298 50 667.5 1630.5 5200

SS 55.0 1049 43.2 418.5 1467.5 ≤5 66.75 1400.8 9500

Ammonia 3.4 66.8 11.5 111.4 178.2 ≤5 66.75 111.5 — nitrogen

Petroleum 2.5 47.7 1.3 12.6 60.3 ≤2 26.7 33.6 320

Volatile 0.02** 0.023 0.44 0.04 0.388 0.828 0.27 0.558 4.0 phenol

Cyanide 0.044 0.83 0.04 0.388 1.218 0.02** 0.27 0.948 6.0

**——NO REQUIREMENT IN DESIGN. THERE IS NO PHENOL AND CYANIDE WASTE WATER SEWAGE-TREATMENT PLANT, SO THE CONCENTRATION

SHOULD BE VERY LOW. HERE THE VALUE IS HALF OF EXISTING VALUE.

72

4.2.3 Solid waste emission amount control quotas

The solid waste produced by planned project will be 1622079t/a. After the project is completed and put into production, the solid waste produced by all projects of the company will be 3494197t/a. The sludge (16850t/a) from sewage-treatment plant will be sent to the municipal solid waste landfill, and the rest will be recycled and reused. No industrial solid waste will be discharged to outside. 4.3 Analysis for total amount control With Product Matrix and Process Equipment Upgrading and Technical Transformation Project being completed and put into production, some old establishments will be reformed or rebuilt. Specific environmental protection measures against igorganizational discharge will be adopted. So the total emission amount of smoke and powder dust after the completion of planned project will be reduced by 4631 t (43.3%). SO2 will be reduced by 1325 t (7.7%) and achieve the goal of “increasing output without increasing waste” by desulfurizing the three boilers in power plant and reducing the amount of the own ore. Compared with current situation, the influence of TSP to atmosphere environment quality substantially reduced after reducing the emission amount, and the influence of SO2 and P M10 changes a little.

73

5. Environmental Risk and Accident Discharge Analysis

Environmental risk, caused by nature and human behaviors and spread by environmental medium, describes the happening probability and result of adverse accidents that exert ruinous, damaging, and destructive impact on human society and natural environment. ERA (Environmental risk assessment) is a process for estimating the likelihood of sudden disastrous accidents related with the project and environmental influence resulting from accidents, and making appropriate measures. The major materials for project, benzene and coal gas in products are flammable or explosive substance; ammonia water, NaOH, hydrochloric acid, chromic acid, etc. are strongly corrosive materials. It is essential to take efficient and stringent risk-control measures in terms of technology and management for preventing potential environmental risk existing in materials transportation and storage, as well as usage. The abnormal operation and damage of environmental treatment facilities during production will lead to off spec pollutant discharge resulting in affecting environmental quality. 5.1 Risk factors Identification The environmental risk identification for the project: on the one hand, start with raw materials, assistant materials, and products involved in the project, understand the potential risk of these chemical materials, including flash point, melting point, boiling point, self ignition point, explosive limit, risks and toxicity classification, etc.; on the other hand, proceed with production process and design scheme, understand device composition of project and its corresponding supporting and auxiliary facilities, important production equipment, process parameters, materials quantity and potential risk of all devices, analyze key positions and weak points of all devices; finally, analyze potential factors of accident discharge. 5.1.1 Risk factors identification of raw materials, assistant materials, and products The major raw materials, interim products and final products involved in the project contain benzene, coal gas, ammonia, tar, NaOH, sulfuric acid, etc., characterized in fire, explosive risk and poisonous damage to some extent. Fire risks grades of major materials are listed in the following table 5-1. Table 5-1 Characters and fire risks grades of major materials No. Materials name Explosive limit% Flash point Fire risk grade 1 Ammonia 15.0~30.2 132 II 2 Benzene <28 IB The harmful effect and occupational harm degree classification of major poisonous materials are listed in table 5-2 respectively.

74

Table 5-2 The major poisonous materials harm, first aid, and occupational harm degree classification

Maximum allowable Occupational Materials concentration Major harm and first aid harm degree name in workshop classification atmosphere (mg/m3) Harm: have a major corrosive and stimulation effect on upper respiratory tract. Ammonia 30 First aid: rinse with much cold water if into eyes, remove person in poison to open air. Harm: burn skin if contacting with it. First aid: for skin injury, rinse with much NaOH cold water, or neutralize with boric acid or 0.5 dilute acetic acid, apply ointment if necessary. Harm: absorbed through respiratory tract and skin. Acute poisoning affects mainly on central nervous system, while chronic poisoning affects mainly on hematopoietic system and nervous system. Benzene 40 First aid: if complexion is found abnormal, remove the one to open air, take off his clothes, remain the temperature, help him to breathe with oxygen containing 5% CO2, and hospitalize. Harm: exert an intensive stimulating effect on skin and respiratory mucosa if inbreathed. HCL 7.5 First aid: remove to windward position immediately, carry out oxygen therapy, artificial respiration and hospitalize. Harm: have an acute respiratory stimulation if inbreathed, eaten or absorbed by skin. CrO3 First aid: remove to windward position 0.01 immediately, carry out oxygen therapy, artificial respiration and hospitalize. Harm: high concentration naphthalin leads to hemolytic anemia, liver and kidney Naphthalin First aid: remove to windward position immediately, carry out oxygen therapy, artificial respiration and hospitalize.

75

5.1.2 Risk factors identification for production process As above-mentioned, since some production materials and products involved in the project are flammable or explosive substance, or strongly corrosive materials, some accidents occurring as follows during production process will cause serious pollution to surrounding environment or personnel injury: (1)Equipment failure during process Due to failure of instruments of production system, poor tightness and accidental damage of equipment, pipes, valves, such accidents as materials leakage may occur, resulting in serious influence on environment or personal injury. (2)During production, it is easy to cause fire and explosive accidents by static, fire, thunder and lightning, and various flammable or explosive factors. (3)Accidental faults during process operation Accidental faults during operation, leading to distillation, condensation, abnormal running of system, and accidents, not only contaminate environment, but cause personal injury. (4)Equipment shall open for repair and rinsing during overhauling equipment; any material remaining in equipment without proper treatment will put an adverse impact on environment. 5.1.3 Risk factors identification during materials storage During material storage, if tanks suffer any bump, damage, or solarization, material leakage or related harmful substance leakage may happen; such fire hazard explosion factors as thunder and lightning, static will lead to accidents, serious environmental pollution and personal injury. 5.2 Precautions against risk accidents For risks during production process and materials storage, it is essential to set up the concept of “giving first place to safety and laying stress on prevention” first, set down specific precautions, reduce probability of risks, so as to reduce loss severity to a certain extent. It is crucial to emphasize the importance of management on precaution, and plant design, process design and process control & monitor shall be incorporated into precaution work. Improve automation to ensure all machines are operated in optimized and safe condition. In order to avoid accidents on the basis of analysis and evaluation, many specific measures are come up with in terms of substantial safe design, fire and explosion prevention, poison resistance, corrosion prevention, and strict management. 5.2.1 Precautions against risk accidents occurring in production process (1)During design, take permissible velocity for flammable liquid transportation into full consideration, all process equipment within static focus devices shall be static grounding, and all pipeline flanges shall be static crossover. Anti-static grounding shall comply with design standard of the original chemical industry department (HGJ28-90). All electrical equipment within production devices shall be explosion-proof type, and designed according to GB50058-92 specification. During production process, any flammable, explosive and

76

combustible material shall be placed in sealing equipment and pipes under operation condition, and reliable sealing measures shall be taken for all joints. Limit alarm and interlock protection system shall be set in process control system to ensure hazardous materials are always under safe control in case of maloperation and abnormal condition. (2)For such accidents as leakage caused by poor tightness and accidental damage of equipment, pipes, valves of production system, check and maintain equipment, pipes, valves on a regular basis, and replace any defective part in time. (3)For an accidental fault, take precaution of human-oriented, establish corresponding work system; operators shall go through training before going to work; only technicians licensed shall work on key posts; operate strictly as per regulations, prevent maloperation, and prepare personal protective equipment. (4)Devices shall be designed to be airtight system, so during production, all toxic materials shall be used in hermetic condition, avoiding contacting with operators, to ensure employee healthy. Flammable gas detectors are set where oil and gas are easy to leak, once leakage occurs, detectors will alarm in time to help operators to take corresponding actions in time. All operators shall undergo strict safety education. In order to avoid static, they mustn’t smoke within plant or warehouse, do not bring such articles as match into factory, do not wear shoes with nails, do not dress or take off within warehouse or work site. In order to avoid spark, do not strike or bump equipment with any ironware. Working personnel shall comply with round-check system, in order to find accident potential in time. 5.2.2 Precaution against risk accident during materials storage (1)Comprehensive measures shall be taken in terms of technique, process, and management to avoid leakage accidents of toxic materials. During general layout design, for risk accidents during materials storage, consider risk segmentation measures, separate and space different risk units, for the sake of limiting risks to the range as small as possible , to preventing interlocking and intervolving during any risk occurring. In order to strengthen design work of fire and explosion prevention, operation within workshop shall strictly conform to related regulations concerning fire forbidden area; for reasonable layout of plant area, it’s optimal to put storage tank in the leeward, and keep sufficient distance away from other facilities, apart from site office buildings as far as possible. (2)Pay attention to solar protection, gentle handling, anti-shake and isolation during loading and unloading, as well as transportation. Transport route shall keep away from residential area and densely populated area, and shall not stop. Plant design and construction shall comply with relevant regulations with regard to flammable, explosive and toxic materials specified by the nation. Qualified level gauge and high level alarm shall be mounted to storage tank; the international advanced lightningproof and static protection system shall be adopted, and regular maintenance shall be strengthen for the system; seepage prevention treatment shall be taken for floor.

(3)Fire hydrant shall be provided surrounding devices and storage tanks; CO2 fire extinguisher and dry powder fire extinguisher shall be supplied within production device area; within tank area, besides mounted fire hydrant, sprinkler cooling water pipes shall be set on 77

the top of tank to sprinkle and cool if necessary. 5.3 Disaster plan and emergency measures against sudden accident

5.3.1 Disaster emergency plan against sudden accident Disaster emergency plan, prepared in advance, is the work procedure and specific measures with definite purposes, in order to provide clear action guide to personnel on site, making them take their time, properly deal with the problems in time, instead of pushing the panic button or discussing and studying on measures temporarily after various serious and malignant emergencies occur, so as to reduce personal injury, property and economic loss. Before planned project being put into production, enterprise shall, according to specific production process flow, set down disaster plan action scheme to effectively deal with sudden accidents. The scheme shall be approved by related department, and fully coordinated with actions of plant, local government and all service departments (e.g. fire fighting and medical). Disaster plan is made against serious risk accidents, which shall meet requirements as follows: a. panic alarm method on site; b. evacuating personnel on site in a safe manner; c. rescuing and treating injured personnel; d. controlling the further development of accidents, minimize the property loss and environmental damage; e. ensuring affected area shall be recovered to normal as soon as possible. Implement the disaster plan when an serious risk accident occurs or is about occur. 5.3.2 Emergency measure against sudden accident Although precaution is the essential measure against accidents, some emergency measures, if proper, shall be taken to reduce accident spread range and loss after accidents, and vice versa. Emergency measure is the plan after basically determining risk loss, aiming at overall recovering the interrupted production process due to serious risk accidents as soon as possible, reducing further loss and minimizing the affected degree. Emergency plan shall include not only the related measures to be adopted, but also corresponding duties of different working posts. In case any environmental accident occurs due to various faults and accidents, relevant emergency measures shall be taken immediately depending on characteristics and generating reasons, to control affecting range and degree. The core of accident treatment is to alarm in time, decide correctly, remedy rapidly. Treatment measures shall be sufficient to take efficient actions. With regard to the above-mentioned environmental risks, the emergency measures shall be as follows: a. If material splash and leakage occurs due to equipment failure or operation fault, shutoff valves and stop supplying materials at once. The overflowing materials shall be cleaned 78

immediately to store in the container for proper disposal; do not discharge with garbage or sewage, so as not to harm environment. b. For any material leakage accident due to such causes as machine damage during storage and transportation, stop leak at once, clear environment, try to collect overflow and leakage materials into sealing containers, absorb residual solution with sands or inert absorbent, and displace it to safe positions, do not discharge it at will. c. Attach great importance to some flammable, explosive or corrosive materials and products used in the project, as they are easy to cause fire during sudden accidents. Once fire happens, put out fire source at once with dry powder, CO2 fire extinguisher. In case of conflagration, call fire telephone, and connect with fire hydrant at once. Sprinkle to disperse steam of combustible materials, and put out the fire with CO2 fire extinguisher or sand. d. Corresponding emergency measures shall be adopted for other accidents. 5.4 Accident discharge and measures 5.4.1 Failures of sewage disposal facilities and measures (1)Failures of sewage treatment facilities During operation of sewage disposal station, any failure due to operation accident or other causes may result in degraded disposal effect or complete failure, putting an adverse impact on equipment, and discharge will lead to pollution to environment. (2)Major precautions against failure of sewage disposal equipment . Strengthen on-the-job-training for personnel of sewage disposal plant, improve professional quality, be strict with operation regulations; . Enforce regular management and maintenance for sewage disposal equipment; . In order to prevent off spec outlet water quality discharge caused by operation faults occurring in sewage treatment station, it is suggested that measures of reducing and even stopping production shall be taken once sudden accident happens. Equalization basin shall be provided for phenol-cyanogen wastewater disposal station and acid and alkaline wastewater disposal station. Stop the overall procedure producing wastewater if facilities failure longer than 4 hours. 5.4.2 Waste gas accident discharge and measures Waste gas treatment facilities failure means during operation of dust collectors, due to operation fault, cloth damage, power off or other reasons, the dust collection efficiency of electric dust collector, cloth dust collector drops or is completely out of work, causing pollutant concentration in waste gas to considerably rises, and resulting in contaminating environment. All dust collector devices for planned project are provided with on-line monitor; once off spec discharge happens due to equipment damage, corresponding measures shall be taken at once to stop production and overhaul, and long-period off spec discharge is not allowed. (2)Major precautions against waste gas treatment facilities failure 79

Strengthen on-the-job-training for personnel involved in waste gas disposal facilities, improve professional quality, and be strict with operation regulations.

. Enforce regular management and maintenance for such equipment as electric dust collector, cloth dust collector, and maintain and replace with new parts on a regular basis. . Cloth dust collector shall be made of new durable fiber material to improve usable lifespan. In order to prevent off spec waste gas pollutant discharge due to operation failure of dust collection facilities, remedy sudden accidents in time; if this isn’t feasible, reduce production and even stop production. 5.5 Comprehensive measures against environment risk To sum up, in order to avoid serious accidents, it is essential to enforce the risk awareness and environmental awareness education to every cadre and employee to strengthen safety and environmental protection awareness. Thus it is suggested to (1)Strengthen work post responsibility, be strict with all operation rules and rewards and punishment system. Besides special environmental protection organizations, specially-assigned personnel shall be provided for each production department with responsibility for safety and environmental protection of its department, often checking sectors easy to cause faults so as to eliminate hidden danger; reporting any problems found out to related department; (2)Arrange all personnel to go through emergency treatment drill on a regular basis for accidents, being capable of averting perils with precautions, and keeping busy but orderly even in case of accidents;

(3)Further to improve security and fire-fighting equipment outfit, strengthen construction of fire-fighting and security teams, so as to consistently promote the abilities of emergency response;

(4)Strengthen equipment maintenance and management, create strict operation system and emergency scheme; reinforce management of hazardous materials, set down all-around regulations for storage, transportation and usage; lay down strict check and register system for key departments and posts. To sum up, if effective precautions are taken, risk accidents can be limited to production site, and controlled rapidly and effectively, instead of causing great loss to production, personnel, and property, and affecting the areas outside factory and its surrounding neighborhoods.

80

6. Environmental Management and Monitoring Plan

Environmental management is one of the important links in enterprise management. In the enterprise, it is of vital significance to set up complete environmental protection organization, strengthen environmental management, carry out plant internal environmental monitoring and supervision, and integrate the environmental protection work into the production management in reducing discharges and emissions of the enterprise’s pollutants, in promoting reasonable use and recycling of resources, and in enhancing economic effects and environmental benefit. 6.1 Environmental management and organizational structure 6.1.1 Environmental management structure The environmental protection organization of Meishan Steelworks was established as early as in 1982; the company’s one deputy general manager has been in charge of the company’s environmental protection work; the company’s safety and environmental protection department is a functional department specialized in management for the whole company's environmental protection; it is manned with 6 people, responsible for the entire company’s daily environmental management, exercising all process supervision and management of environmental protection of the company’s development planning and all new, expanded and reconstructed projects and technological innovations, environmental protection statistics and environmental protection infrastructure. The company’s various plants have set up their own corresponding environmental management organizations, responsible for the environmental protection of their own units. The testing center of the company’s manufacture and management department has under it the environmental monitoring station, with 13 environmental monitoring personnel working in the sampling group, analysis group and quality control group; they have the monitoring abilities of atmospheric quality, flue gas, wastewater as well as noise, responsible for the routine monitoring, measurement and analysis of various sources of pollution in production areas and living quarters of the whole company according to the standard requirements; they provide the data support for understanding the company’s environmental quality and tendency of change, preventing and controlling pollution, protection and the improvement of the environment. In 2004, the entire company had altogether 121 people working in environmental protection work, of which 5 persons work as safety and environment protection managers, and 13 people as environmental monitors. After this project putting into operation, the newly built secondary plants will be arranged with corresponding environmental protection administrative personnel, and the areas, number of staff, and monitoring equipment of the existing testing station shall be correspondingly increased. For many years, the Meishan Steelworks environmental protection department has been doing a remarkable job in the enterprise’s environmental harnessing, management, and promotion of sustainable clean production of the enterprise, and environment monitoring in coordination with the governmental authoritative department; their environmental protection work has been systemized, standardized and scientific; they have worked out a complete set of environmental protection and management systems, which are unceasingly being modified and improved in practice; their management systems are mainly as follows: 81

a. Environmental protection and management methods of Meishan Steelworks; b. Implementation methods of environmental protection responsibility system of Meishan

Steelworks; c. Management stipulations of environmental protection facilities of Meishan Steelworks; e. Environmental monitoring and management system of Meishan Steelworks; f. Rules and regulations of construction project environmental protection and management of Meishan Steelworks; g. Management methods of Meishan Steelworks’ industrial solid wastes; h. Management methods of automatic monitoring system of industrial pollution sources of Meishan Steelworks. This planned construction project will completely rely on the existing plant area of Meishan Steelworks, therefore, it is not planned to establish new environmental organization, however, the environmental monitoring station of Meishan Steelworks will be strengthened. For the environmental protection organizational system of Meishan Steelworks, see Figure 6-1. To determine the Company’s environmental policies, provide the support required by the environmental management

Environmental management To strengthen the leading work of representative, organize the environmental management, implementation of environmental coordinate the relations between the management system production construction and the environmental protection

General manager To work out environmental management document, To support and environment development cooperate with the safety planning and organize its and environmental implementation, make Environmental protection department to inspection and examination Deputy general protection committee implement of the environmental manager environmental performance of each management production plant and promote sustainable development of the Company’s environmental protection

Safety and Environment Other environmental monitoring station departments protection department

To implement the environmental management requirement, and improve continuously the To execute the environment environmental performance monitoring task and provide data support for the environmental Each secondary production unit management

Fig. 6-1 Meishan Steelworks environmental protection management organization chart

82

6.1.2 Environmental management responsibilities (1)Environmental management responsibilities during construction period

To be responsible for routine environmental management during construction period; To coordinate and supervise the construction of environmental protection facilities that are for completion of the production plants conforming to the “three concurrence” requirement; To participate in the completion acceptance of the project environmental protection facilities (to make sure not to let the environmental protection facilities that do not conform to the performance requirements pass the acceptance inspection). To organize promotion activities of environmental protection for raising the constructors’ awareness of environmental protection; during the construction operation, to reduce as far as possible flying dust and noises. To exercise environmental supervision responsibility during the construction of environmental protection facilities. (2) Environmental management responsibilities during production To be responsible for the enterprise’s implementing the relevant laws, rules and regulations, environmental protection standards, stipulations and methods made by the state and local governments and the environmental protection authorities. To work out the enterprise’s internal environmental protection schemes, and see to it that each content of the schemes is implemented; to organize and work out the entire enterprise’s environmental protection management rules and regulations and to supervise their implementation; to establish the enterprise’s internal environmental protection management system; to work out and promote the environmental protection assessment system and methods, and carry on the enterprise’s internal audit of clean production. The environmental protection work of the construction projects is to be put under the centralized management. To get to know the pollution condition of the enterprise’s each production workshop and establish a pollution file; to carry out a dynamic management of the environmental protection statistical work according to the pollutant discharge index, the operation index of the environmental protection facilities and so on; and to make sure the emission and discharge of the enterprise’s “water, gas, noise, and slag” up to the national and local standards; To supervise and inspect the operation situation of the environmental protection facilities, to solve the problems found promptly; to guarantee the enterprise does not have occurrences of serious environmental pollution and leaking accidents; and to be responsible for dealing with problems arising from various kinds of environmental accidents. To carry on activities of environmental protection promotion, environmental protection training, environmental protection knowledge contest and summary and exchange of experience so as to raise all the employees’ environmental protection awareness; to organize and strengthen environmental protection special services, scientific research, exchange of study experience; and to organize the environmental protection personnel to participate in 83

technical training so as to raise their service quality. To establish gradually the ISO14001 environmental management system for the environmental management: To work out the company’s environmental policy, define the objectives and indexes, work out the annual environmental management plan, supervise their implementation, and realize continual improvement. To promote clean production; to carry on the enterprise internal audit of clean production of various working procedures according to the newly-issued “Clean production standard--the steel and iron industry” requirements, so as to make continual improvement. To promote use of new technology, new process, and new material for environmental protection. To do a good job of afforestation in the plant area. 6.2 Environmental monitoring organization and supervising plans 6.2.1 Environmental monitoring organization After this project put into production, it should strengthen the Meishan Steelworks’ existing environmental protection management structure, strengthen the disposition of monitoring stations, and purchase more necessary instruments and equipment, particularly, the instruments for analyzing pollutants from chemical product processing. See Table 6-1. Table 6-1 Summary of main instruments and equipment of environment monitoring station Instrument name Model, specification Number Liquid phase chromatograph WATEAS515 1 Atomic absorption spectroscopy photometer 3510 1 Ultraviolet spectrophotometer UV-755B 1 Visible complementary filter 721, 7230G 5 Infrared spectroscopy oil tester JK951, F2000 2 On-line COD analyzer - 2 COD quick determinator WMS-1 1 Velocity meter LS1206B 1 Atmospheric continuous automatic sampler TH3000A 4 Fume sampler PTP-1, TH880 , TH880 4 Dust sampler FC-2, FC-A- 2 Portable atmospheric sampler TH-110B 4 Intelligent flue gas analyzer TH-990 2 Ringelmen determinator CYG 1

84

Instrument name Model, specification Number

Large capacity TSP sampler TH1000C, TH1000CII 8 Medium capacity TSP sampler TH150C 4

PM10 cutter PM10 4 CO detector S-450 1 Flow meter TH-2MB 2 Acidometer PHS-1, PHSJ-4 2 Sound level meter AWA6218 1 Conductivity meter DDS-11A, DDS-307 2 Balance TG328A, TG332A, BS210S 5 6.2.2 Tasks of the monitoring stations Through throughout monitoring and controlling of the entire procedure of the construction projects, to get to know accurately the degree and scope of the construction projects’ pollution impact on the environment during the construction period and operation time, and to know well if the environmental impact from the sources of waste gas, waste water, and noise pollution conforms to the requirements of the national or local standards. Meanwhile, to supervise and inspect the prevention and controlling facilities of waste gas, waste water, and noise so as to guarantee normal operation. (1)To establish a file on the sources of pollution for the enterprise, to carry out the routine monitoring and measurement of the emitted and discharged pollution sources and pollutants (waste gas, waste water, noise) and the environmental conditions of the plant area; if there is excessiveness, a written notice shall be sent to the related unit requiring them to find out the cause and make corrections so as to guarantee the enterprise is able to emit and discharge pollutants up to the national and local laws, regulations and standards. (2)To participate in the acceptance inspection of the enterprise’s environmental protection facilities, and be responsible for monitoring and reporting the pollution accidents.

(3) To draw up the enterprise’s own monitoring plan and work plan based on the environmental quality standard and the “three wastes” discharge standard issued by the national and local governments. (4)To submit regularly to the department concerned the environmental monitoring plan and monitored data. 6.2.3 Environmental supervising plans Environmental monitoring is the basic work of environmental protection, and is the important method for implementing the environmental protection laws and regulations, determining the current situation of environmental quality, assessing the effect of environmental protection

85

facilities and environmental protection management. According to the industrial traits, the related laws, rules and regulations of the superior environmental protection department, in combination of the actual situation of this project, the following monitoring plan has been worked out for this plant; if the monitoring station does not have the analysis condition, some monitoring items may be entrusted to the Nanjing Environmental Monitoring Station for monitoring and analysis. (1)When the company’s environmental monitoring station is carrying on the environmental monitoring, the routine monitoring includes: atmospheric environment, flue gas, external discharge of wastewater, main industrial wastewater, metallurgical slag, noises and so on. Monitoring of atmospheric environment Monitoring of atmospheric environment is the foundation of atmospheric environmental management of iron and steel enterprises; its task is to carry on long-term and systematic monitoring of the atmospheric environmental quality in the plant areas and living quarters of various enterprises and the influence degree on the external environment. The routine monitoring of atmospheric environment is divided into two methods: the continuous sampling laboratory analysis and the automatic continuous monitoring system; the monitoring items are: dust fall, total suspended particles, PM10, sulfur dioxide, nitrogen oxide, and B[a]P. When the condition permits, analyses shall be made for grain distribution of the total suspended particles, the elemental composition and dust fall composition. Monitoring frequency: 1/a. Monitoring of process waste gas For monitoring of main process waste gas, see Table 6-2. Monitoring of wastewater The monitoring task of industrial wastewater is to implement the overall index of environmental protection examination and grasp the situation of up to standard operation (recycled use of the treated wastewater) of the main industrial wastewater after being treated. For monitoring of wastewater, see Table 18-3. Monitoring of solid wastes All the hazardous and poisonous solid wastes that is discarded and stored up must be monitored. If they can be utilized completely, they may not be monitored. At the phenol and cyanogen wastewater treatment station, the phenol and cyanide in the sludge of the biochemical pond must be monitored. Noise control Noise monitoring: noise at plant boundary, noise in plant area and noise sources; and noise sensitive points outside the plant. Monitor frequency: 1 /a. 6.2.4 Automatic environmental monitoring To prevent the environmental pollution and to control environmental quality cannot only depend on the intermittent manual sampling and laboratory chemical analyses, which cannot

86

grasp immediately the space and time change of emissions and discharges of the pollution sources and the environmental pollution situation and promptly provide various needed scientific data. Therefore, it is extremely essential to establish the automatic environmental monitoring system so as to carry on effective management and control of the environment and sources of pollution. (1)Purposes of establishing automatic environmental monitoring system To monitor the environmental and atmospheric pollution situations in the plant area; To monitor various processes pollution sources; To control and monitor the key pollution sources so as to prevent occurrence of pollution accidents; To monitor the water quality at the key wastewater discharge outlets; To lay a foundation for studying pattern and calculation; To build up conditions for realizing production process pollution control (i.e., control of total discharge amount), and for realizing automatic control of the system gradually. The environmental monitoring system constructed and improved in this way can carry out supervision and assessment of the environmental pollution condition, control emissions and discharges of pollutants, reduce effectively runoff of the pollutants, utilize reasonably the resources and energy, guarantee improvement of the environment quality, and, simultaneously, obtain better economic benefit and environmental benefit. (2)Scale and composition of the system Generally, the scale of automatic environmental monitor system should include: monitoring of atmospheric environment of the plant area, monitoring of industrial pollution sources, monitoring of wastewater external discharge outlets, monitoring of noises at plant boundary, meteorological observation of the pollution, mobile monitoring vehicle for pollution sources, digital transmission system with wire and wireless communication modes, and a network system that is composed of multi- monitoring sub-stations and a central control station. (3)Design of the system and arrangement of the instruments and equipment A special study subject shall be arranged for design of the automatic environmental monitoring system, and configuration of the instruments and equipment. Generally speaking, the system design shall be made according to the purposes of establishing the system and the technical specifications. Generally, the configuration of the system instruments and equipment shall meet the following requirements: To be reliable for long-term unattended automatic operation; To be accurate and reliable of the measured data, the accuracy and precision of the instruments meeting the requirements of the national stipulations; To be able to carry on zero and span automatic calibration at the preset time or by the

87

remote control instruction; Its measurement scope and technical performance index shall all conform to the national, ministerial and provincial standards; The instruments must be convenient for maintenance, so as to keep the maintenance frequency to minimum; The equipment for completion must conform to the national or international standards; The operation of the instruments and equipment must conform to the national safety stipulations. (4)Online monitoring system Before the automatic environmental monitoring station is constructed, in accordance with the requirements of the environmental protection department, “online monitoring instruments” shall be set up for carrying out online monitoring of the pollution sources. Mainly, the following items shall be set up: To set up “COD water quality online monitoring instruments” for the general wastewater discharge outlets of the plant area (west discharge outlet, north discharge outlet, recycle used water outlet) to monitor discharge of the wastewater. It is suggested to use SHZ-4COD gross amount online monitoring instrument to monitor discharge of the wastewater. This instrument has the following performances: a. Display function: CODcr gross amount, concentration and flowrate; b. Measurement range: 0-3000mg/L (accuracy: ±10%) c. Minimum time-interval of measurement: 1h d. Remote control: able to set measurement cycles, verify the clock and playback the stored data; e. Remote fault alarm: it has the remote control mode for reagent and pump pipe replacement, heating temperature, storage fault alarm.

To set up “SO2 online monitoring instrument” for the sintering plant charge end flue gas to monitor and control emissions of waste gas from the charge end.

To set up “SO2 online monitoring instrument” for the power plant waste gas to perform real-time monitoring of emissions of the power plant waste gas. 6.3 Wastes outlets signs and management (1)Graphic signs for sewage discharge outlets, waste gas emission outlets and noise emission sources The graphic signs for sewage discharge outlets, waste gas emission outlets and noise emission sources are divided into two kinds: the prompt graphic signs and the warning graphic signs; the setting of the graphic signs shall follow the requirements in GB15562.1-1995. (2) Graphic signs for solid wastes storage (disposition) yards

88

Graphic signs for solid wastes storage (disposition) yards are divided into two kinds: the prompt graphic signs and the warning graphic signs; the setting of the graphic signs shall follow the requirements in GB15562.2-1995. For the above said signs, see Figure 6-2. (3)Setting up signs at the wastes discharge outlets The environmental protection graphic sign boards at the pollutant discharge outlets must be set up close to the sampling point, at the eye-catching position; the height of the sign boards is approximately 2m from the top edge of the board to the ground. For the pollutant discharge outlets of the key wastes discharge units, vertical sign boards are primarily used; for the pollutant discharge outlets of the general wastes discharge units, either vertical sign boards or plane stationary type signs boards may be used according to the actual situation. (4)Management of wastes discharge outlets Management principle

Prompt graphic Warning graphic signs signs Background color: Background color: Name Function No. green yellow Graph color: white Graph color: black

Sewage 1 discharge Indicating sewage outlet drained to water body

Waste gas 2 emission Indicating waste gas outlet emitted to atmosphere

Normal solid Indicating solid wastes wastes storage storage disposal place 3

Danger Solid wastes Indicating solid wastes storage storage disposal place

Indicating noise 4 Noise source discharged to external environment

89

Fig. 6-2 Graphic signs for wastes discharge outlets The wastes outlets are the channels for the enterprises’ pollutants to enter the environment and pollute the environment; to strengthen management of the wastes outlets is one of the basic work tasks for controlling the gross amount of pollutants, and is also an important means for gradually realizing scientific and quantitative pollutant discharges and emissions of the regional environmental management. The specific management principles are as follows: a. The outlets that discharge and emit pollutants into the environment must be standardized. b. The pollutant discharge and emission sources (mainly SO2, flue gas, dust) that have been listed in the gross amount control are the key points of management. c. To report truthfully to the environmental protection and management department the number of wastes discharge and emission outlets, their locations and types of the main discharged and emitted pollutants, amount, concentration, discharge and emission destination. d. The waste gas exhaust device must be equipped with sampling holes and sampling platforms that are convenient for sampling and monitoring; their arrangement shall conform to the requirements in “Technical specification for pollution source monitoring”. e. When solid wastes of the project are stored up, special storage yards shall be provided for them and shall be provided measures to prevent flying up and scattering out,and anti-leakage measures shall be taken for poisonous and hazardous solid wastes. Keeping the discharge and emission sources on a file a. This project shall use the “Standardized sewage discharge outlet signs registration certificate of the People's Republic of China” prepared and printed by the State Environmental Protection Administration, and fill in relevant contents according to the requirements; b. According to the requirements for management contents of sewage discharge outlets, after the project being completed and put into production, the types, amount, concentration, and discharge and emission destination of the main pollutants, and the sign setup and operation situation of the facilities must be recorded and put in the file. 6.4 Management of technical documents During environmental monitoring and management, the following document files must be kept: (1)Technical documents of pollution source monitoring records; (2) Design and operation management documents of pollution control and environmental protection and control facilities;

(3)All the analysis reports and monitoring data for the causes of pollution accidents.

90

6.5 Acceptance contents of environmental protection “three concurrence” of the planned and “new bringing along the old” projects

For the acceptance contents of environmental protection “three concurrence” of the planned and “new bringing along the old” projects, see Table 6-2, Table 6-3, and Table 6-4.

Table 6-2 Acceptance table of waste gas environmental monitoring contents and “three concurrence” Acceptance Exhaust criteria Working Name of dust mast Monitoring factors Monitoring (mg/m3/kg/h) Pollution sources procedure collector height frequency Up to standard (m) discharge

Dust SO2 Others Dust SO2 Coal blending, Pulse bag type dust 25 √ 1/month crushing collector 120/14.5 Coal charging, coke Ground station 25 √ 1/ month extracting Bag 400 Coke oven 125 √ √ 1/a 250 mg/m3 Coking Coal sample 25 √ 1/ month 120/14.5 preparation room Dry coke quenching Pulse bag type dust 40 √ 1/ month 120/39 dust collecting collector Furnace front coke warehouse 40 √ 1/ month 120/39 Coke screening Machine head dust 250 ㎡ electrostatic 120 √ √ 1/ month 100 2000 collecting precipitator (ESP) Machine tail dust Sintering 195 ㎡ ESP 50 √ 1/ month 100 collecting Batching 63 ㎡ ESP 35 √ 1/ month 120/31 Crushing sifting 36 ㎡ ESP 30 √ 1/ month 120/23 Furnace top 20 √ 1/ month 120/5.9 charging Bin 30 √ 1/ month 120/23 Bag type dust Blast Casthouse 40 √ 1/ month 100 collector furnace Stock system 35 √ 1/ month 120/31 Coal injection 55 √ 1/ month 120/72 system Hot blast stove Mixed gas 80 √ √ 1/a 100 2000 Two-stage wet Converter flue gas √ 1/ month 100 method Secondary flue gas Bag type 70 √ 1/ month 100 Converter Molten iron Bag type 40 √ √ 1/ month 100 2000 desulfurization Refining furnace Bag type 30 √ Fluoride 1/a 100 and charging Utilizing secondary cooling vapor Sheet metal Mould 30 √ 1/a 120/23 adsorbing, continuous condensing casting and Heating, annealer Mixed gas 60 √ √ 1/a 200 550/55 rolling Plastic board dust Finish rolling smoke 60 √ 1/a 120/85 collector

91

Coke oven shell, quenching Dust: plant Flue gas dust tower, each workshop, plant boundary 1.0 SO boundaries, stock yards 2 mg/m3 Inorganized discharge Coke oven shell, related 1/a Others: workshops of Meishan GB16171-96 BaP, SBO, NH H S Chemical Branch, plant 3, 2 Newly established boundaries grade II standard Table 6-2 (continue) Acceptance table of waste gas environmental monitoring contents and “three concurrence” Monitoring factors Acceptance criteria Exhaus mg/m3/kg/h Working Pollution Name of dust t mast Monitoring ( ) procedure sources collector height frequency Dust SO2 Others Up to standard discharge (m) Dust SO2 Kiln charge Bag type dust 40 √ 1/month 250 flue gas collector Product batch Bag type dust √ bin and 30 1/month 250 Limekiln collector crusher Stock yard Bag type dust transport 25 √ 1/month 250 collector station Clumsy Chemical tubular 25 - √ 1/a 120/14.5 550/10 products furnace Cold Coke oven Annealer 40 √ √ - 1/a 200 550/25 rolling gas Drawing and straightening machine, Bag 25 √ 1/a welding 120/14.5 machine Shot blasting Bag 25 √ 1/a machine Leveling -bag 40 √ 1/a 120/39 machine set Acid regeneration Bag 30 √ 1 /a 120/23 station Acid cleaning Acid hydrochloric 20 1/3 months 100/0.43 mist acid mist Acid mist Annealing scrubber Acid chromic acid 50 1/3months 0.07/0.013 mist mist Oil Mill oil mist Oil mist filter 20 1/3months 120/10 mist

92

Cleaning Alkali mist Alkali 45 1/3months alkali mist scrubber mist 1. This table is also a “three concurrence” acceptance table of the project; the “three concurrence” acceptance monitoring will be carried out within 3 months after the project is completed and put into operation. 2. Environmental management monitoring shall be carried out by monitoring station of Meishan Steelworks, and Nanjing Municipal Monitoring Station will make an inspection monitoring once a year. 3. All pollution sources shall be monitored for their waste gas amount. Table 6-3 Acceptance table of wastewater, noise and solid wastes environmental monitoring items and “three concurrence”

Pollution sources Control method Disposal and handling method Acceptance criterion

Phenol cyanogens Water is used for slag flushing A/O2 method wastewater after treated up to standard

Acid alkali Chemical method Water is used for sag treatment Not discharged Wastewater wastewater treatment after treated up to standard

Wastewater 26% is discharged after 74% will be reused after treatment of whole Physicochemical method treated up to grade 1 treatment plant standard

Fan noise To install muffler, Fan muffler, sound insulation Oxygen generator To build sound insulation board noise room

Using acoustic board for Mixed noise in the Noise Plant building sound walls of pump house, Sound insulating wall board workshop is less than 85dB. insulation production building

Blast furnace blow To install special muffler Blast furnace muffler down valve

To be sent to building All are utilized, no wastes Solid wastes Blast furnace slag material plant for recycle Sluice, crane are discharged to outside use

Slag basin, crane, crusher, To be sent to outside the magnetic separator All are utilized, no wastes Converter slag plant for recycle used are discharged to outside after metal is recovered (To be handled by specialized company)

To be recovered completely and sent to All are utilized within the Dust of dust Collection tank car, enclosed sintering plant to be used Company, not discharged to collector storehouse as raw material, not outside discharged to outside

Coke tar slag, crude All are utilized within the Chemical products benzene residue, asphalt To go to coking coal blending Company, not discharged to solid wastes slag, desulfurization outside waste liquid, sludge, etc.

93

To be recovered completely and sent to All are utilized within the Water treatment dust Sludge separation, dewatering sintering plant to be used Company, not discharged to sludge, iron scale equipment, transport vehicle as raw material, not outside discharged to outside

To be recovered All are utilized, no wastes Refractory materials To sell completely are discharged to outside

To be recovered All are utilized, no wastes Waste oil To sell completely are discharged to outside

Plant area greening, isolated Greening rate greater than Others Greening area of plant boundary 35% Table 6-4 Acceptance table of “new bringing along the old” pollution control measures “three concurrence” “New bringing Completion No. along the old” Description Acceptance criterion time modification project a. Phenol cyanogens wastewater not discharged To treat all the production b. Acid, alkali, chromium Wastewater wastewater of the whole contained wastewater not End of 1 treatment plant of plant, 74% will be reused discharged 2007 the whole plant and 26% will be discharged c. All the production after treatment wastewater are treated d. Discharge is up to grade 1 standard 1. The existing coke oven To dismantle gas not desulfurized 3×65-ductold coke completely, emission of SO2 To be accepted according ovens after combustion is: 2534t/a; to the environmental 2 To be renewed to 2. The existing coke ovens protection facility standard 2008 2×55-duct coke are aging seriously, of the planned coking ovens inorganized discharge is project serious, smoke and dust is 4425t/a, SO2 is 412t/a After completion of the a. To monitor the ore sulfur project, the existing sintering content SO of the existing 2 machine will use more End of 3 sintering machine b. To monitor consumption imported ore, the average 2007 reduced of China-produced, sulfur content will be self-produced ore and reduced imported ore

94

At present, the 3 boilers of 220t/h of the power plant are firing coal and gas, with coal a. To monitor the Power plant boiler accounting for 70%, after desulfurization efficiency End of 4 flue gas completion of the project, all 2006 desulfurized the 3 boilers will fire coal b. To monitor raw coal only, and flue gas sulfur content desulfurization shall be implemented. At present, the arresting efficiency of the dust a. To monitor arresting Secondary dust collectors of 1#, 3# blast efficiency 5 collecting of blast furnace casthouse is low, 2008 furnace casthouse escape of flue gas is serious b. To monitor flue gas when opening and blocking emission concentration the tap hole To cancel mixer 6 Arresting efficiency low To cancel 2008 furnace Other inorganized To monitor the surrounding 7 stock yards, dust Dust suppression measures 2005-2008 dust concentration control

95

7. Public Involvement

7.1 Purpose and action of public involvement 7.1.1 Purpose of public involvement It is aimed to let the public fully know and understand the project so as to bring the environmental and social benefit into full play. 7.1.2 Action of public involvement (1)Public involvement is an important means to coordinate project construction and social influence. It is through this method of public involvement can fully understand what the public thinking about the environmental and social problems which maybe exist in this project so as to ensure that important environmental problems, which are caused or may be caused, be analyzed and proofed in the environmental impact assessment. (2)Based on the public views and comments on the project, try to ensure rationality and feasibility of the environmental measures by fully considering the public demands in the engineering plan of environmental measures. (3)Coordinate relations between the enterprise and masses through digestion of the public suggestions and demands towards the construction project, to improve social stability and unity. 7.2 Methods, investigation and people to be visited of the public involvement 7.2.1 Methods of public involvement For the public involvement this time, “A Brief Introduction to the Construction Project” is prepared based on its scale, features, main environmental issues, intended measures and the final effects, so as to enable the public to have a complete idea about this project and its impact to the environment. And those people visited will be asked to fill in the “A Form of Public Poll on EIA of Construction Projects in Jiangsu Province”. See the “Brief Introduction” and “Form of Public Poll” attached hereinafter. The evaluator issued and recovered the copies of “Form of Public Poll” on April 29-30 and May 9-18, 2005. The public poll covered as much as possible the wide areas concerned, including the residential areas of Meishan Iron & Steel Company, and nearly 10 natural villages affiliated to the 3 administrative villages Sanshan, Sunjia and Xinjian under Banqiao Town, Yuhua District, as well as the those departments, schools, enterprises, and so on, around the Company. The public poll copies recovered shall be representative as much as possible in such a way that those residents to be relocated, school teachers, workers, etc., are included in the people visited. The public poll shall be carried out in the following way: (1) The relevant working personnel from the Owner and Evaluator shall give presentations to those citizens visited about the environmental information after the Meishan Iron & Steel project is started;

96

(2) Discussions and answers will be had on those environmental issues of the citizens’ concern;

(3) Citizens shall, after fully advised of the construction project, be asked to fill in “A Form of Public Poll on EIA of Construction Projects in Jiangsu Province” for the public opinions from all walks of life. 404 copies of “A Form of Public Poll on EIA of Construction Projects in Jiangsu Province” were issued for public poll and recovered 100%. 7.2.2 Investigation items of the public poll (1) Is the public satisfied with the present environment quality (including atmospheric environment, water environment and sound environment etc.) of the construction project site? (2) The public’s awareness of, and response to, the construction project. (3) The public views and comments on the relations among the new construction project here and the environment and economic development. (4) The public views on the impact of pollutants, which the project may discharge, to the environment after they are aware of the construction project. (5) The public suggestions and demands on the Project-related anti-pollution measures and the review and approval by the competent authorities. See the attached form in this chapter for details of the Form. 7.2.3 Composition of the public poll 404 people were visited during the public poll, of whom 230 were males, 174 females; in terms of their education, 104 persons had college education or above, 113 persons finished high school education (including secondary specialized schooling), 104 persons finished junior middle schooling, 76 persons primary schooling, 7 persons illiterates; as for professions, 129 persons were workers and employees of enterprises, 153 persons were farmers, 66 persons cadres, 40 persons teachers, 3 persons students, 13 persons jobless guys; as for the age, 108 persons were 18-34 years old, 224 persons were 35-55 years old, and 72 persons were above 55. Refer to Table 7-1 for details about the people visited during the public poll. Table 7-1 A List of People Visited during Public Poll on EIA of Construction Projects Educa- No. Name Sex Age Profession Family address Tel tion Special Meishan residential area 86703185 1 Zhang Yan Female 35 Worker school 348-J-601 Miao Junior middle Meishan residential area 86704091 2 Female 20 Waitress Xiao-cui school 47-2-302 Special Meishan residential area 86704091 3 Huang Wei Female 45 Employee school 47-2-302 Wang Junior middle Yancun Group, Xinjian 86712123 4 Female 42 Cleaner San-ying school Village, Banqiao Town

97

Educa- No. Name Sex Age Profession Family address Tel tion

Wei Primary No.162, Sanshanying, 86713583 5 Female 58 Farmer Ming-xiang school Banqiao Town No.162, Sanshanying, 86715510 6 Chen Jie Female 29 Senior school Farmer Banqiao Town Sanshan Housing Estate, 13851734975 Yan Junior middle 7 Female 35 Farmer Sanshan Village, Banqiao Cui-xiang school Town Sanshan Housing Estate, 13851734975 Junior middle 8 Ai Hua Female 36 Farmer Sanshan Village, Banqiao school Town Sanshan Housing Estate, 86722356 Wu Junior middle 9 Male 37 Farmer Sanshan Village, Banqiao Shou-liang school Town Sanshan Housing Estate, 86722289 Junior middle 10 Zhu An-rong Male 43 Jobless Sanshan Village, Banqiao school Town Sanshan Housing Estate, 86722281 Wang Junior middle 11 Male 32 Jobless Sanshan Village, Banqiao Xiao-chun school Town Sanshan Housing Estate, 86713518 Yan 12 Female 38 Senior school Teacher Sanshan Village, Banqiao Yong-mei Town Sanshan Housing Estate, 86701950 Yan 13 Female 43 Senior school Jobless Sanshan Village, Banqiao Yong-qin Town Sanshan Housing Estate, 86713244 Junior middle 14 Wang De-xiu Female 42 Jobless Sanshan Village, Banqiao school Town Sanshan Housing Estate, 86712906 Wang Junior middle 15 Male 39 Farmer Sanshan Village, Banqiao Mao-zhong school Town Sanshan Housing Estate, 13047518544 16 Li Ben-fang Female 43 Senior school Worker Sanshan Village, Banqiao Town Sanshan Housing Estate, 86720380 Zhang Junior middle 17 Female 36 Farmer Sanshan Village, Banqiao Nian-cun school Town Sanshan Housing Estate, 86722075 Primary 18 Yan Liu-di Female 68 Farmer Sanshan Village, Banqiao school Town

98

Educa- No. Name Sex Age Profession Family address Tel tion

Sanshan Housing Estate, 8672292 Junior middle 19 Li Si-yun Female 43 Farmer Sanshan Village, Banqiao school Town Sanshan Housing Estate, 8671270 Zhang Junior middle 20 Female 43 Farmer Sanshan Village, Banqiao Gen-xiang school Town Sanshan Housing Estate, 86722306 Junior middle 21 Yan Li-jun Male 35 Farmer Sanshan Village, Banqiao school Town Sanshan Housing Estate, 86701003 22 Geng Jun Male 43 Senior school Worker Sanshan Village, Banqiao Town Sanshan Housing Estate, 86722241 Zhang Primary 23 Male 52 Farmer Sanshan Village, Banqiao Gui-xiang school Town Sanshan Housing Estate, Primary 24 Wu Shou-qin Female 40 Farmer Sanshan Village, Banqiao 86703353 school Town Sanshan Housing Estate, 86722987 Primary 25 Song Ai-yun Female 43 Farmer Sanshan Village, Banqiao school Town Sanshan Housing Estate, 8725513 Yan Junior middle 26 Female 39 Farmer Sanshan Village, Banqiao Hong-xiang school Town Huangnitang without Primary 27 Yan Min-liu Male 61 Farmer Group,Sanshan Village, school Banqiao Town Huangnitang 85763018 Wang Primary 28 Female 59 Farmer Group,Sanshan Village, Lai-xiang school Banqiao Town Huangnitang without 29 Cao Hong Female 58 Semi illiterate Farmer Group,Sanshan Village, Banqiao Town Huangnitang without Zhang Primary 30 Female 62 Farmer Group,Sanshan Village, Zhong-fang school Banqiao Town Xingguang Primary 86704468 31 Zhang Yi-zhi Female 28 College Teacher School, Sunjia Village, Banqiao Town Xingguang Primary 86704468 Kang Special 32 Male 59 Teacher School, Sunjia Village, Gui-wu school Banqiao Town

99

Educa- No. Name Sex Age Profession Family address Tel tion

Xingguang Primary 86712327 Special 33 Sun Cai-qin Female 33 Teacher School, Sunjia Village, school Banqiao Town Xingguang Primary 86704468 34 Wang Li-xia Female 27 College Teacher School, Sunjia Village, Banqiao Town Xingguang Primary 86704468 Lu 35 Female 28 College Teacher School, Sunjia Village, Zhong-xiang Banqiao Town Xingguang Primary 86707231 Special 36 Mei Zhi-gao Male 54 Teacher School, Sunjia Village, school Banqiao Town Xingguang Primary 86721424 37 Zhao Fu-xi Male 30 Senior school Teacher School, Sunjia Village, Banqiao Town Xingguang Primary 86717897 Special 38 Nie Yu-qiang Male 59 Teacher School, Sunjia Village, school Banqiao Town Xingguang Primary 86704468 39 Zhang Yi-de Male 28 College Teacher School, Sunjia Village, Banqiao Town Xingguang Primary 86716931 Zhang Special 40 Male 45 Teacher School, Sunjia Village, Wen-gen school Banqiao Town Primary Sunjia Group, Sunjia - 41 Sun Da-ping Male 49 Farmer school Village, Banqiao Town Ye Junior middle Niejiabian, Sunjia Village, 86705807 42 Male 55 Worker Chang-xiang school Banqiao Town Yang Primary Niejia Team 2, Sunjia 86720200 43 Female 52 Worker Ji-xiang school Village, Banqiao Town Wang Primary Niejia Team 2, Sunjia 86722309 44 Female 50 Farmer Cui-hua school Village, Banqiao Town Lin Junior middle Niejia Team 2, Sunjia 86712043 45 Female 48 Worker Wang-lan school Village, Banqiao Town Yan Junior middle Niejia Team 2, Sunjia without 46 Female 28 Farmer Ming-feng school Village, Banqiao Town Primary Niejia Team 2, Sunjia without 47 Fu Xiu-ying Female 71 Farmer school Village, Banqiao Town Primary Niejia Team 2, Sunjia without 48 Shi Qiao-yun Female 50 Worker school Village, Banqiao Town

100

Educa- No. Name Sex Age Profession Family address Tel tion

Junior middle Niejia Team 2, Sunjia 86713132 49 Liu Ba-yun Female 49 Worker school Village, Banqiao Town Special Wait for Niejia Team 2, Sunjia 86712043 50 Ye Min Female 24 school employment Village, Banqiao Town Primary Niejia Team 2, Sunjia 86726260 51 Nie Yu-nan Male 69 Farmer school Village, Banqiao Town Nie Niejia Team 2, Sunjia 82766863 52 Male 43 Senior school Worker Bao-chun Village, Banqiao Town Ye Primary Niejia Team 2, Sunjia without 53 Female 61 Farmer Chang-liang school Village, Banqiao Town Ye Primary Niejia Team 2, Sunjia 86720810 54 Male 55 Farmer Ming-shan school Village, Banqiao Town Junior middle Niejia Team 2, Sunjia 86720810 55 Ye Hong Female 30 Worker school Village, Banqiao Town Primary Niejia Team 2, Sunjia 86704185 56 Nie Gen-nan Male 61 Farmer school Village, Banqiao Town Junior middle Sunjia Group, Sunjia 86725519 57 Fu Hou-zhen Female 38 Farmer school Village, Banqiao Town Ye Primary Niejia Team 1, Sunjia - 58 Male 65 Farmer Ming-wang school Village, Banqiao Town Junior middle Niejia Team 2,Sunjia 86717879 59 Ye Ming-you Male 47 Worker school Village, Banqiao Town Ye Junior middle Sunjia Group,Sunjia without 60 Male 70 Farmer Chang-qin school Village, Banqiao Town Zhong Primary Team 3,Sunjia Village, without 61 Female 62 Farmer Ru-ying school Banqiao Town Chen Junior middle Niejia Team 2,Sanshan 86714338 62 Male 53 Worker Liu-qing school Village, Banqiao Town Ye Junior middle Niejia Team 2,Sanshan without 63 Male 49 Worker Ming-liang school Village, Banqiao Town Ye Primary Niejia Team 2,Sanshan without 64 Male 60 Farmer Chang-tao school Village, Banqiao Town Primary Niejia Team 2,Sanshan 86713863 65 Ye Chang-he Male 55 Farmer school Village, Banqiao Town Huangnitang Group ,86720174 66 Yan Ming-fu Male 42 Senior school Farmer Sanshan Village, Banqiao Town Huangnitang Group, 86710343 Yan 67 Male 40 Senior school Jobless Sanshan Village, Banqiao Chang-nian Town

101

Educa- No. Name Sex Age Profession Family address Tel tion

Huangnitang Group, without Yang Primary 68 Male 84 Farmer Sanshan Village, Banqiao Chang-you school Town Huangnitang Group, 86721449 69 Yan Luo-fa Male 29 Senior school Worker Sanshan Village, Banqiao Town Huangnitang Group, 86713068 Yan Primary 70 Male 58 Farmer Sanshan Village, Banqiao Heng-xing school Town Huangnitang Group, 86702291 Junior middle 71 Hu Ping Female 42 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86731018 Junior middle 72 Zhang Hua Female 43 Worker Sanshan Village, Banqiao school Town Huangnitang Group, 86710343 73 Xu Sai-lin Male 63 Senior school Worker Sanshan Village, Banqiao Town Huangnitang Group, 86706872 Primary 74 Jiang Qi-yun Female 57 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86706872 Wang 75 Male 34 Senior school Worker Sanshan Village, Banqiao Chun-hua Town Huangnitang Group, 86721449 Wang Primary 76 Female 52 Farmer Sanshan Village, Banqiao Qi-ying school Town Huangnitang Group, 86721449 Yan Primary 77 Male 58 Farmer Sanshan Village, Banqiao Heng-bao school Town Huangnitang Group,86724522 Junior middle 78 Jin Gui-liang Male 38 Worker Sanshan Village, Banqiao school Town

Jiang Junior middle No.45, Hejiachang, 86714529 79 Male 36 Farmer Xiao-chun school Banqiao Town Huangnitang Group, - Zhang Junior middle 80 Female 62 Farmer Sanshan Village, Banqiao Zhong-fang school Town Huangnitang Group, 86712626 Junior middle 81 Ma De-qun Female 40 Farmer Sanshan Village, Banqiao school Town

102

Educa- No. Name Sex Age Profession Family address Tel tion

Huangnitang Group, - Yan Junior middle 82 Male 65 Farmer Sanshan Village, Banqiao Heng-shou school Town Huangnitang Group, 86710343 Junior middle 83 Yan Mei Female 37 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86724522 Jing Junior middle 84 Female 30 Jobless 业 Sanshan Village, Banqiao Dong-dong school Town Huangnitang Group, 86712626 Yan Junior middle 85 Male 66 Farmer Sanshan Village, Banqiao Heng-lun school Town Huangnitang Group, 86106346 Yan Junior middle 86 Female 39 Farmer Sanshan Village, Banqiao Yu-xiang school Town Huangnitang Group, 86721328 Yan Junior middle 87 Male 38 Farmer Sanshan Village, Banqiao Chang-zhong school Town Huangnitang Group, 86724911 Yan Junior middle 88 Male 35 Farmer Sanshan Village, Banqiao Chang-ming school Town Huangnitang Group, - Primary 89 Yan Xiu-qin Female 42 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86710034 Zhang Junior middle 90 Male 72 Worker Sanshan Village, Banqiao Shu-jia school Town Huangnitang Group, 86714683 Junior middle 91 Yan Ai-rong Female 31 Worker Sanshan Village, Banqiao school Town Huangnitang Group, 86724991 Junior middle 92 Yan Ai-qin Female 35 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86714683 Primary 93 Li Jia-fang Female 61 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, - 94 Tao La-mei Female 59 Illiterate Farmer Sanshan Village, Banqiao Town Huangnitang Group, - Yan 95 Male 32 Senior school Farmer Sanshan Village, Banqiao Chang-hong Town

103

Educa- No. Name Sex Age Profession Family address Tel tion

Huangnitang Group, - Yan Qidong High 96 Male 31 Farmer Sanshan Village, Banqiao Chang-qi school Town Huangnitang Group, 86724522 Jin Junior middle 97 Male 68 Worker Sanshan Village, Banqiao Xing-quan school Town Huangnitang Group, 86724522 Junior middle 98 Xu xiu-ru Female 68 Worker Sanshan Village, Banqiao school Town Huangnitang Group, 86724522 Junior middle 99 Jin Gui-ping Male 36 Jobless Sanshan Village, Banqiao school Town Huangnitang Group, 86717299 Junior middle 100 Yan Zai-fu Male 42 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86714683 101 Yan Ai-min Male 37 Senior school Farmer Sanshan Village, Banqiao Town Huangnitang Group, 86713018 Yan Junior middle 102 Female 33 Farmer Sanshan Village, Banqiao Chang-lan school Town Huangnitang Group, 86704622 Jiang Junior middle 103 Female 50 Farmer Sanshan Village, Banqiao Gen-cui school Town Huangnitang Group, 86725826 Junior middle 104 Xu Xiao-jun Female 31 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86720714 Yan Primary 105 Male 56 Farmer Sanshan Village, Banqiao Heng-min school Town Huangnitang Group, Primary 106 Yan Ai-yun Female 61 Farmer Sanshan Village, Banqiao 86711379 school Town Huangnitang Group, - Junior middle 107 Fang Jia-bao Male 44 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86712049 Yang Primary 108 Male 48 Farmer Sanshan Village, Banqiao Zai-nian school Town Huangnitang Group, 86706872 Ding Primary 109 Male 68 Worker Sanshan Village, Banqiao Ruen-lin school Town

104

Educa- No. Name Sex Age Profession Family address Tel tion

Huangnitang Group, 86721429 110 Lu Yue-jin Male 26 Senior school Jobless Sanshan Village, Banqiao Town Huangnitang Group, 86714937 Yan Primary 111 Male 51 Farmer Sanshan Village, Banqiao Chang-liang school Town Huangnitang Group, 86710034 Zhang 112 Male 41 Senior school Cadre Sanshan Village, Banqiao Dao-yu Town Huangnitang Group, 86710034 113 Lu Xi-qin Female 40 Senior school Farmer Sanshan Village, Banqiao Town Huangnitang Group, - Huang Junior middle 114 Male 60 Farmer Sanshan Village, Banqiao Chang-zhi school Town Huangnitang Group, 86714167 Yan Primary 115 Male 68 Farmer Sanshan Village, Banqiao Min-dong school Town Kang Sanshan Village, Banqiao86710146 116 Male 20 College Student Gui-ping Town Zhong Sanshan Village, Banqiao 86710146 117 Female 54 Senior school Worker Guo-xiang Town Huangnitang Group, 86714167 Yan 118 Female 44 College Teacher Sanshan Village, Banqiao Yong-qing Town Huangnitang Group, - Junior middle 119 Fei Ji-bao Male 33 Farmer Sanshan Village, Banqiao school Town Huangnitang Group, 86722864 Gong Junior middle 120 Male 45 Jobless Sanshan Village, Banqiao Yu-yong school Town Huangnitang Group, - Yan Primary 121 Female 54 Farmer Sanshan Village, Banqiao Dong-mei school Town Huangnitang Group, - Yu 122 Female 72 Illiterate Farmer Sanshan Village, Banqiao Feng-ying Town Huangnitang Group, 86705753 Primary 123 Li Yu-qin Female 38 Farmer Sanshan Village, Banqiao school Town Sun Sunjia Village, Banqiao 86336669 124 Male 33 Senior school Farmer Guang-hua Town

105

Educa- No. Name Sex Age Profession Family address Tel tion

Zhu Bldg 82, Meishan 86366816 125 Female 38 Senior school Worker Xiao-dong residential area Room 201, Yuanyang 86700422 Zhou Special 126 Female 29 Employee Bldg, Energy Dept, Hua-yan school Meishan No.355-A-202, Meishan 86364700 127 Lu Zu-yong Male 51 College Engineer residential area Xuan No.329-B-202Meishan 86364576 128 Male 51 College Cadre Zhong-chang residential area Dong No.320-B-501, Meishan 86366629 129 Female 42 College Employee Qing-ling residential area No.202, Bldg 380, 86078378 130 Ren Lu Male 32 Senior school Cadre Meishan Century Garden Wang Special Assistant No.346-B-202, Meishan 86364729 131 Male 57 Guo-yan school engineer residential area No.301, Bldg 438D, 86363329 132 Xu Ji-jian Male 40 College Cadre Meishan residential area No.101, Bldg 442A, 86364996 133 Wu Jian-fen Female 49 College Engineer Meishan residential area No.601, Bldg 380C, 13951691756 134 Bao Yuan-ya Male 32 University Engineer Meishan residential area Special 86078440 135 Long Bin Male 30 Worker Meishan residential area school Bai Fenghua Garden, Meishan 86365958 136 Female 27 University Cadre Yong-ling residential area No.501, Bldg 105 A, 13813847333 137 Tao Er Male 49 Senior school Worker Meishan residential area Special No.102, Bldg 107 B, 86702035 138 Lu Qun Male 37 Worker school Meishan residential area No.301, Bldg 468 B, 86366054 139 Li Jia-quan Male 41 College Worker Meiqing Garden, Meishan Junior middle No.401, Bldg 459 B, 86706180 140 Chen Xin-lai Male 42 Worker school Meishan residential area No.401, Bldg 323 B, 86365865 141 Fan Yue-tai Male 61 College Cadre Meishan residential area Special No.302, Bldg 224 A, 86701735 142 Xu Wen Female 44 Cadre school Meishan residential area Special No.301, Bldg 412 B, 86362911 143 Wang Ling Female 42 Cadre school Meishan residential area

106

Educa- No. Name Sex Age Profession Family address Tel tion

No.301, Bldg 443 A, 86365706 Special 144 Sun Fen Female 38 Worker Shangyi Village 2, school Meishan No.602, Bldg 125 A, 145 Wu Di-hong Male 55 College Cadre 86702517 Meishan residential area Dai No.212, Bldg 1 , Yinghua 86715884 146 Male 25 University Cadre Zheng-gui Garden, Meishan No.410, Bldg7 , Yinghua 86078341 Chen 147 Male 44 Senior school Worker Garden, Meishan Zhi-ming residential area Zhang Junior middle No.403, Bldg 14 B, 86705872 148 Female 39 Worker Zheng-lan school Meishan residential area Special No.202, Bldg 112 A, 86703809 149 Jin Xiong Male 46 Worker school Meishan residential area Shi Special No.202, Bldg 416 B, - 150 Female 37 Worker Juan-juan school Meishan residential area Special No.502, Bldg 362 A, 86710383 151 Zhou Yan Female 29 Worker school Meishan residential area No.102, Bldg 372 A, 2276 152 Zhang Ji-yue Male 51 College Cadre Meishan residential area No.205, Bldg 408A, 86365040 153 Liu Jun Male 34 College Worker Meishan residential area Junior middle No.401, Bldg 349 A, 86365334 154 Li Jin-long Male 48 Worker school Meishan residential area No.102, Bldg 463 A, 86365458 155 Sun Jian-min Male 30 University Cadre Meishan residential area Zhong Junior middle No.502, Bldg 310 B, 86365370 156 Male 48 Worker Guo-jian school Meishan residential area Junior middle No.301, Bldg 424 A, 86365370 157 Chen Hua-fu Male 53 Worker school Meishan residential area No.102, Bldg 333 C, 86365640 158 Li Hong-yan Female 31 College Cadre Meishan residential area Junior middle No.502, Bldg 469 C, 86365648 159 Hu Ye-hua Male 52 Worker school Meishan residential area Wang No.302, Bldg 361 A, 86365149 160 Male 34 College Cadre Hai-zhong Meishan residential area No.102, Bldg 457 A, 86713487 161 Shi Jia-jin Male 40 Senior school Worker Meishan residential area Zhou Junior middle No.302, Bldg 331 A, 86721706 162 Male 36 Worker Feng-dong school Meishan residential area

107

Educa- No. Name Sex Age Profession Family address Tel tion

Zhang No.101, Bldg 351 A, 2276 163 Female 32 College Cadre Zhi-lin Meishan residential area 164 Cheng Min Female 37 College Cadre Meishan residential area - Zhang - 165 Female 33 University Cadre Meishan residential area Xiao-lin No.601, Bldg 117 A, 86362088 166 Zhang Rong Male 41 College Cadre Meishan residential area Cai Senior - 167 Male 51 University Meishan residential area Shan-yong engineer No.442, Shangyi Village 2, 86362536 168 Dong Gui-li Female 29 College Cadre Meishan Special No.301, Bldg 87, Meishan 86703217 169 Sun Shu-mei Female 46 Cadre school residential area Xia Special No.101, Bldg 358 B, 86363278 170 Female 38 Cadre Qing-qiong school Meishan residential area Zhang Special 86363278 171 Male 44 Worker - Jian-hua school No.401, Bldg 452 B, 86362536 172 Li Ming Male 38 College Cadre Meiqing Garden, Meishan Dong No.302, Bldg 421 C, 86701360 173 Male 50 College Cadre Chang-gui Meishan residential area No.602, Bldg 406 A, 86362536 Special 174 Hu Yu-hua Female 44 Cadre Shangyi Village 2, school Meishan No.302, Bldg 471 A, 86362276 175 Lu Wen-yi Female 29 College Worker Meishan residential area No.202, Bldg 312 B, 86362656 176 Liu Jia-he Male 55 University Cadre Shangyi New Village, Meishan No.101, Bldg 116 A, 86362276 177 Xie Yong Male 44 College Cadre Meishan East Junior middle No.501, Bldg 126 C, 0599 178 Li Yong-jin Male 54 Cadre school Meishan residential area No.302, Bldg 73, Meishan 86707910 179 Shi Mei-xia Female 41 Senior school Worker residential area No.401, Bldg 78 B, 2104 180 Li Ming Male 39 Senior school Worker Meishan residential area No.202, Bldg 26 A, 86362161 181 Li Li Female 42 Senior school Worker Meishan residential area

108

Educa- No. Name Sex Age Profession Family address Tel tion

Liu No.302, Bldg 109 B, 86363053 182 Female 42 College Cadre Pei-xiang Meishan residential area Zhang No.402, Bldg 402 B, 86711202 183 Female 41 Senior school Worker Li-hui Meishan residential area Xu No.202, Bldg447 C, 184 Female 45 Senior school Worker 86705376 Zheng-lan Meishan residential area 185 Lu Liang Male 27 University Cadre Meishan residential area 52919060 Wang New Village of Meishan 86717211 186 Male 31 Senior school Worker Shun-jin Middle School 187 -jun Male 27 Senior school Worker Meishan residential area 86710803 188 Ling Qiang Male 23 University Cadre 13645192376 Chen - 189 Male 32 Senior school Worker Meishan residential area Chun-bao Room 213, Bldg 6, 86725332 190 Tian Gang Male 25 University Cadre Meishan Dormitory Yuan Special - 191 Male 35 Worker Meishan residential area Yi-qiang school Yan No.201, Bldg 425 C, 86364926 192 Male 49 College Worker Chang-hu Meishan residential area No.301, Bldg 369B, 86364359 Jiang Special 193 Male 41 Worker Shangyi New Village, Ben-bao school Meishan Room 306, Yuanyang 13057519368 194 Bao Dui-ge Male 36 College Worker Building, Transportation Dept. Meishan Zhang Junior middle No.201, Bldg 404D, 86711441 195 Male 51 Worker Yu-min school Meishan residential area Zhong Special Shangyi Village 1, 86364425 196 Male 53 Cadre Xiu-ren school Meishan residential area Zhang 4899 197 Male 40 College Cadre Meishan residential area Zheng-ling Zhang Junior middle Zhaofen Group, Sanshan 86720369 198 Female 53 Farmer Ru-lan school Village, Banqiao Town Yang Junior middle Zhaofen Group, Sanshan 86717934 199 Male 55 Farmer Xin-chang school Village, Banqiao Town Zhang Junior middle Zhaofen Group, Sanshan 86712658 200 Male 55 Farmer You-zhi school Village, Banqiao Town Zhao Junior middle Zhaofen Group, Sanshan 86715340 201 Female 54 Farmer Liu-xiang school Village, Banqiao Town

109

Educa- No. Name Sex Age Profession Family address Tel tion

Chen Primary Zhaofen Group, Sanshan 86712937 202 Female 45 Farmer Qi-xiang school Village, Banqiao Town Gao Junior middle Zhaofen Group, Sanshan 86704419 203 Male 62 Farmer Wan-bao school Village, Banqiao Town Sheng Primary Zhaofen Group, Sanshan 86712658 204 Female 54 Farmer Wu-xiang school Village, Banqiao Town Gao Junior middle Zhaofen Group, Sanshan - 205 Male 37 Farmer Wan-yong school Village, Banqiao Town Zhao Junior middle Zhaofen Group, Sanshan - 206 Female 62 Farmer Rong-ying school Village, Banqiao Town Chen Junior middle Zhaofen Group, Sanshan 86712554 207 Female 48 Farmer Mei-xian school Village, Banqiao Town Wang Zhaofen Group, Sanshan - 208 Male 30 Senior school Farmer Hua-guo Village, Banqiao Town Wang Zhaofen Group, Sanshan - 209 Male 32 Senior school Farmer Shi-qin Village, Banqiao Town Primary Zhaofen Group, Sanshan 86711530 210 Zhu Xiu-qin Female 53 Farmer school Village, Banqiao Town Ye Special 86700329 211 Male 52 Cadre Jiantong Material Corp. Chuan-hua school 212 Shi Song-bai Male 36 University Cadre Jiantong Material Corp. 86726179 Fu 86732101 213 Male 41 Senior school Worker Jiantong Material Corp. Hou-zhong Wu Special 86713396 214 Male 55 Accountant Jiantong Material Corp. Chang-ming school Zhang 86721819 215 Male 40 College Cadre Jiantong Material Corp. Xiao-hua 216 Hu Yong Male 48 Senior school Worker Jiantong Material Corp. - 217 Chen Qi Female 47 Senior school Worker Jiantong Material Corp. 86732138 218 Xie Ren-min Female 38 Senior school Worker Jiantong Material Corp. 86732123 Junior middle - 219 Wu Liu-shun Male 54 Worker Jiantong Material Corp. school Special 86732108 220 Li Yang Female 43 Worker Jiantong Material Corp. school Shen Primary - 221 Female 49 Worker Jiantong Material Corp. Lan-ying school Special 86732112 222 Ping Jun Male 53 Cadre Jiantong Material Corp. school

110

Educa- No. Name Sex Age Profession Family address Tel tion

Zhang Junior middle Jiantong Residential Area, 51513267 223 Male 68 Retired Mao-song school Banqiao Town Jiantong Residential Area, 86732138 224 Zhen Min Female 45 Senior school Cadre Banqiao Town Jiantong Residential Area, 86732112 225 Wang Jian Female 42 Senior school Worker Banqiao Town Yi Junior middle Jiantong Residential Area, 86732138 226 Male 47 Worker Yong-biao school Banqiao Town Liu Retired due to Jiantong Residential Area, 86722458 227 Male 49 Senior school Dao-sheng illness Banqiao Town Jiantong Residential Area, 86700670 228 Liu Li Female 40 Senior school Worker Banqiao Town Jiantong Residential Area, 86700670 229 Lu An Male 42 Senior school Worker Banqiao Town Jiantong Residential Area, 86700670 230 Xu Lai-fa Male 51 Senior school Worker Banqiao Town Zhang Junior middle Jiantong Residential Area, 86721645 231 Female 38 - Chun-mei school Banqiao Town Zhang Junior middle Jiantong Residential Area, 86715623 232 Male 35 Worker Yong-jin school Banqiao Town Hu Sunjia Middle School, 86712532-8015 233 Female 24 University Teacher Hong-yan Banqiao Town Sunjia Middle School, 86712509 234 Chen Ming Male 37 University Teacher Banqiao Town Li Sunjia Middle School, 86707463 235 Male 57 College Teacher Zheng-rong Banqiao Town Ye Special Sunjia Middle School, - 236 Female 37 Teacher Ming-feng school Banqiao Town Special Sunjia Middle School, 86712532-8009 237 Hu Wan-qin Female 33 Teacher school Banqiao Town Zou Sunjia Middle School, 86712532-8009 238 Female 25 College Teacher Yue-ping Banqiao Town Cao Sunjia Middle School, 86712532-8004 239 Male 29 College Teacher Guang-ping Banqiao Town Sunjia Middle School, 86712532-8009 240 Han Wen Female 21 College Teacher Banqiao Town Liu Sunjia Middle School, 86712532-8009 241 Male 30 College Teacher Xing-bao Banqiao Town Sunjia Middle School, 86131449 242 Wang Da-jin Male 58 College Teacher Banqiao Town

111

Educa- No. Name Sex Age Profession Family address Tel tion

Kan Sunjia Middle School, 86714870 243 Male 30 College Teacher Hong-chao Banqiao Town Sunjia Middle School, 86712532 244 Li Li Female 38 University Teacher Banqiao Town Sunjia Middle School, 86712532 245 Peng Bang Male 38 College Teacher Banqiao Town Chang Sunjia Middle School, 86712532 246 Male 38 College Teacher Ke-tian Banqiao Town Han Sunjia Middle School, 86712532-8014 247 Male 23 University Teacher Liang-bing Banqiao Town Tang Sunjia Middle School, 86712532-8014 248 Male 31 University Teacher Zheng-tong Banqiao Town Wang Sunjia Middle School, 86132191 249 Female 29 Senior school Printer Yi-ning Banqiao Town Sunjia Middle School, 86712532 250 Gu Rong-hai Male 32 College Teacher Banqiao Town Sunjia Middle School, 86712532 251 Jin Jie-yun Female 40 College Teacher Banqiao Town Sunjia Middle School, 86712532-8015 252 Lu Wen-yun Female 29 University Teacher Banqiao Town Sunjia Middle School, 86712531-8014 253 Zhu Li Female 24 College Teacher Banqiao Town Sunjia Middle School, 86712532-8014 254 Ma Yun-qiu Female 32 University Teacher Banqiao Town Hou Sunjia Middle School, 86714870 255 Male 50 College Teacher Yu-cheng Banqiao Town Xuan Sunjia Middle School, 86710332 256 Female 43 College Teacher An-ting Banqiao Town Sunjia Middle School, 86712532-8000 257 Yin Yi-lin Male 46 College Teacher Banqiao Town Sunjia Middle School, 86712532-8011 258 Jiang Xia Female 25 University Teacher Banqiao Town Chu Sunjia Middle School, 86712532-8011 259 Female 34 University Teacher Jiang-hong Banqiao Town Sunjia Middle School, 86712532-8011 260 Yu Lei Male 33 College Teacher Banqiao Town Sunjia Middle School, 86712532-8002 261 Zhu Jun Male 39 College Teacher Banqiao Town Hang Sunjia Middle School, 86711775 262 Female 35 University Teacher Jun-hong Banqiao Town

112

Educa- No. Name Sex Age Profession Family address Tel tion

Primary Caofu, Sunjia Village, 86715549 263 Qin Yu-ge Female 40 Farmer school Banqiao Town Zhang Primary Caofu, Sunjia Village, 86702445 264 Male 52 Worker Ren-cai school Banqiao Town Zhang Caofu, Sunjia Village, 86702445 265 Male 30 Senior school Worker Bi-ping Banqiao Town Xu Primary Caofu, Sunjia Village, - 266 Male 70 Retired Kai-sheng school Banqiao Town Zhang Caofu, Sunjia Village, 86723149 267 Male 44 Senior school Farmer Ren-fa Banqiao Town Ye Caofu, Sunjia Village, - 268 Female 38 Senior school Farmer Ming-feng Banqiao Town Caofu, Sunjia Village, - 269 Xu Kai-ming Male 69 Illiterate Farmer Banqiao Town Gu Caofu, Sunjia Village, 86702445 270 Male 40 Senior school Worker Ming-long Banqiao Town Junior middle Caofu, Sunjia Village, 86721034 271 Xu Guo-ping Male 37 Worker school Banqiao Town Jiang Junior middle Caofu, Sunjia Village, 13601464390 272 Female 35 Worker Yuan-fang school Banqiao Town Caofu, Sunjia Village, 86700123 273 Zhang Jie-xi Male 39 Senior school Worker Banqiao Town Liu Junior middle Gujiabian,Sunjia Village, 86704067 274 Male 69 Farmer You-zhen school Banqiao Town Junior middle Gujiabian, Sunjia Village, 13770953099 275 Lu Yu-bao Male 32 - school Banqiao Town Junior middle Gujiabian, Sunjia Village, 13951648879 276 Liu You-fa Male 61 Retired school Banqiao Town Junior middle Gujiabian, Sunjia Village, 13914796474 277 Xie Yun Male 43 Farmer school Banqiao Town Junior middle Gujiabian, Sunjia Village, 86723959 278 Liu Ji-pu Male 35 Farmer school Banqiao Town Gujiabian, Sunjia Village, 86106569 279 Liu Ji-kui Male 34 Senior school Farmer Banqiao Town Liu Junior middle Gujiabian, Sunjia Village, 13182802532 280 Female 30 Farmer Ling-ling school Banqiao Town Gujiabian, Sunjia Village, 86706941 281 Liu Hai-yan Female 30 Senior school Farmer Banqiao Town Primary Gujiabian, Sunjia Village, - 282 Liu Kai-sen Male 75 Farmer school Banqiao Town

113

Educa- No. Name Sex Age Profession Family address Tel tion

Primary Gujiabian, Sunjia Village, 86715679 283 Liu Ji-sheng Male 53 Farmer school Banqiao Town Primary Gujiabian, Sunjia Village, 86706913 284 Liu Kai-long Male 56 Farmer school Banqiao Town Gujiabian, Sunjia Village, 876226421 285 Liu You-gen Male 46 Senior school Farmer Banqiao Town Gujiabian, Sunjia Village, 86707282 286 Liu You-he Male 63 Senior school Retired Banqiao Town Primary Gujiabian, Sunjia Village, - 287 Gu Yu-yun Female 64 Farmer school Banqiao Town Primary Gujiabian, Sunjia Village, 86721459 288 Gu Jin-gui Male 68 Farmer school Banqiao Town Wang Primary Gujiabian, Sunjia Village, 86712901 289 Male 57 Farmer Gui-dong school Banqiao Town Zhong Junior middle Hekou Group, Sunjia 86706524 290 Female 29 Farmer Xin-xia school Village, Banqiao Town Tang Junior middle Hekou Group, Sunjia 86706524 291 Male 58 Farmer Zheng-bang school Village, Banqiao Town Hekou Group, Sunjia 86714361 292 Xu De-hua Female 47 Senior school Farmer Village, Banqiao Town Special Hekou Group, Sunjia 13414124487 293 Sun Ming Female 24 Student school Village, Banqiao Town Wang Junior middle Hekou Group, Sunjia - 294 Female 44 Farmer Jing-mei school Village, Banqiao Town Junior middle Hekou Group, Sunjia 86701034 295 Tang Su-hua Male 29 Farmer school Village, Banqiao Town Zhang Primary Hekou Group, Sunjia - 296 Male 50 Farmer Shou-de school Village, Banqiao Town Primary Hekou Group, Sunjia - 297 Ji Ou-xiang Female 39 Farmer school Village, Banqiao Town Zheng Junior middle Hekou Group, Sunjia - 298 Male 45 Farmer Zhi-nian school Village, Banqiao Town Zhang Hekou Group, Sunjia 86702195 299 Female 29 Senior school Farmer Bi-qin Village, Banqiao Town Junior middle Lijia Group, Sunjia - 300 Zhao Shao Female 59 Farmer school Village, Banqiao Town Shi Primary Lijia Group, Sunjia - 301 Male 66 Farmer Yong-nian school Village, Banqiao Town Junior middle Lijia Group, Sunjia 86716994 302 Li Ben-jiu Male 47 Farmer school Village, Banqiao Town

114

Educa- No. Name Sex Age Profession Family address Tel tion

Junior middle Lijia Group, Sunjia - 303 Xu Ming-lan Female 36 Farmer school Village, Banqiao Town Junior middle Lijia Group, Sunjia 86721534 304 Li Ben-shan Male 54 Village head school Village, Banqiao Town Lijia Group, Sunjia 86721834 305 Li Qiu-xiao Male 23 University Student Village, Banqiao Town Lijia Group, Sunjia 86721834 306 Li Xue-lian Female 26 College Security guard Village, Banqiao Town Chen Junior middle Lijia Group, Sunjia 86712180 307 Male 56 Farmer Guo-qiang school Village, Banqiao Town Primary Lijia Group, Sunjia - 308 Li Wei-chun Male 76 Farmer school Village, Banqiao Town Junior middle Lijia Group, Sunjia - 309 Zhang De-di Female 56 Farmer school Village, Banqiao Town Wang Junior middle Lijia Group, Sunjia - 310 Male 39 Farmer Li-bing school Village, Banqiao Town Shao Primary Lijia Group, Sunjia - 311 Female 35 Farmer Hai-yan school Village, Banqiao Town Li Primary Lijia Group, Sunjia 86712131 312 Female 60 Farmer Sheng-mei school Village, Banqiao Town Primary Lijia Group, Sunjia - 313 Zhang Ya-di Female 57 Farmer school Village, Banqiao Town Lijia Group, Sunjia 86713087 314 Li Wei-rong Female 32 Senior school Farmer Village, Banqiao Town Shan Junior middle Lijia Group, Sunjia 86722580 315 Male 64 Farmer Xiu-ming school Village, Banqiao Town Jiang Primary Lijia Group, Sunjia 86721534 316 Female 50 Farmer Ben-lan school Village, Banqiao Town Primary Lijia Group, Sunjia - 317 Li Zong-yun Female 65 Farmer school Village, Banqiao Town Sun Lijia Group, Sunjia 13023407254 318 Male 41 Senior school Worker Guo-qing Village, Banqiao Town Li Junior middle Lijia Group, Sunjia - 319 Female 35 Farmer Zheng-xiang school Village, Banqiao Town Zhang Special Lijia Group, Sunjia 86714726 320 Male 43 Teacher Wen-ping school Village, Banqiao Town Zhang Junior middle Lijia Group, Sunjia 86714726 321 Male 38 Farmer Wen-huai school Village, Banqiao Town Zhang Lijia Group, Sunjia 86714726 322 Male 35 Senior school Farmer Wen-qing Village, Banqiao Town

115

Educa- No. Name Sex Age Profession Family address Tel tion

Lijia Group, Sunjia - 323 Li Wei-he Male 63 Illiterate Farmer Village, Banqiao Town Junior middle Lijia Group, Sunjia 86716931 324 Gu Ji-lan Female 43 Farmer school Village, Banqiao Town Junior middle Lijia Group, Sunjia - 325 Li Ge-xiang Female 29 Farmer school Village, Banqiao Town Jiang Junior middle Lijia Group, Sunjia 86722482 326 Female 49 Farmer Cong-lan school Village, Banqiao Town Junior middle Lijia Group, Sunjia 86716994 327 Li Ben-qin Male 36 Farmer school Village, Banqiao Town Gu Primary Lijia Group, Sunjia 86723445 328 Male 43 Farmer Rong-zhen school Village, Banqiao Town Junior middle Lijia Group, Sunjia 86716931 329 Ye Cui-nian Female 81 Farmer school Village, Banqiao Town Lijia Group, Sunjia 86703486 330 Sun Yu-cui Female 44 Senior school Farmer Village, Banqiao Town Zhang Junior middle Lijia Group, Sunjia 86722024 331 Male 43 Farmer Wen-guang school Village, Banqiao Town Primary Lijia Group, Sunjia 86723621 332 Yu He-hua Female 36 Farmer school Village, Banqiao Town Junior middle Bldg 385, Meishan 86711468 333 Xu Zhi-fang Female 37 Worker school residential area Pan 86365703 334 Male 53 College Cadre Meishan residential area Duo-long 335 Sun Jin-quan Male 47 University Section head Meishan residential area 86365472 Wang 86364690 336 Male 46 Senior school Worker Meishan residential area Jian-she Wei Special No.512, Construction 86366472 337 Male 29 Cadre Zhen-sheng school Dept. Dormitory, Meishan Xiong 86366472 338 Male 29 College Cadre Meishan residential area Xie-ning No.301, Bldg 466 C, 86366643 339 Li Xue-gen Female 28 University Cadre Meishan residential area Gu No.501, Bldg 103 C, 86701704 340 Male 50 College Cadre Song-yuan Meishan residential area No.310, Bldg 4, Fenghua 86712725 341 Guo Yan Male 26 University Cadre Garden, Meishan No. 303, Bldg 44 B, 13626102262 342 Bai Jun Male 37 University Cadre Meishan residential area

116

Educa- No. Name Sex Age Profession Family address Tel tion

Cao No.302, Bldg 338 B, 86366803 343 Male 31 University Cadre Zhi-qiang Meishan residential area No.501, Bldg 110 B, New 51631005 Zheng 344 Male 29 College Cadre Village of Meishan Middle Hong-yi School Wang No.602, Bldg 455 A, 86704697 345 Male 50 Senior school employee Jin-bao Meishan residential area Cai Junior middle 86704814 346 Male 36 Employee Meishan residential area Yao-zhong school Song Special No.601, Bldg 344, Shangyi 86704814 347 Male 27 Employee Shi-xiao school New Village, Meishan No.601, Bldg 462-J, 13851992687 348 Liu Hai-min Male 27 College Employee Meiqing Garden, Meishan Zhang Special No.202, Bldg 455 A, 86365297 349 Male 37 Cadre Yuan-bing school Meiqing Garden, Meishan Bian Special New Village of Meishan 86706637 350 Male 31 Employee Ru-gang school Middle School Sunjiachen Garden, 86706637 351 Zhou Hai-bo Male 36 Senior school Employee Meishan residential area Special Meisheng Garden, 86712648 352 Wang Wei Female 42 Employee school Meishan residential area Zhu Special Meiqing Garden, Meishan 86712648 353 Female 38 Employee Zhong-hua school residential area No.601, Bldg 76 A, 86365140 354 Mi Hua Male 47 Senior school Employee Meishan residential area Wang Employee No.601, Bldg 384 C, 86365543 355 Male 33 College Yin-ning Meishan residential area Le Employee 356 Male 40 College Meishan residential area Jiang-ping 357 Liu Qiang Male 34 College Employee Meishan residential area 358 Ni Jian-guo Male 50 College Cadre Meishan residential area 359 Guo Hong-li Female 33 College Cadre Meishan residential area Nie 86366096 360 Male 38 University Cadre Meishan residential area Deng-hong Sun 86362378 361 Male 30 College Employee Meishan residential area Ben-gang No.302, Bldg 336 A, Zeng 362 Male 26 University Employee Shangyi New Village, Hai-hong Meishan

117

Educa- No. Name Sex Age Profession Family address Tel tion

363 Li wei-wei Female 26 College Employee Meishan residential area

Employee No.602, Bldg 306 B, Ji 364 Male 31 College Shangyi New Village, Shang-long Meishan

Special Employee 365 Cehn Liang Male 25 Meishan residential area school

Wang Employee Yinghua Garden, Meishan 86724967 366 Male 25 College Jun-feng residential area

Zuo Employee 367 Male 45 College Meishan residential area Sheng-sheng

Employee No.101, Bldg 304 C, 86705142 368 Huang Jian Male 25 College Meishan residential area

No.401, Bldg 319 B, 86366285 369 Qian Qun Female 43 University Employee Meishan residential area

No.301, Bldg 3, Meishan 86717010 370 Bao Jun-wu Male 23 University Employee Yinghua Garden

Special Bldg 336, Meishan 51970404 371 Wu He-jun Male 31 Employee school residential area

372 Li Ru-yi Male 23 University Employee Meishan residential area 86361406

Wang No.302, Bldg 5, Meishan 373 Male 25 University Employee Ya-bing Yinghua Garden

Wang 374 Male 34 University Employee Meishan residential area Wan-yuan

375 Gu Ye Male 26 University Employee Meishan residential area 86720860

Wang 376 Male 41 Senior school Employee Meishan residential area Yu-biao

Shanyi New Village, 13337800537 377 Ye Ning Male 35 Senior school Employee Meishan residential area

No.312, Bldg 5, Meishan 86701184 378 Guo Yu-jie Male 24 College Employee Yinghua Garden

Zhu 4899 8102 379 Male 31 University Employee Meishan residential area Shi-quan

Junior middle Zhushan Group, Sanshan 86725796 380 Liu De-hong Female 38 Farmer school Village, Banqiao Town

118

Educa- No. Name Sex Age Profession Family address Tel tion

Primary Zhushan Group, Sanshan 86706692 381 Zhu Xi-hua Male 58 Farmer school Village, Banqiao Town

Junior middle Zhushan Group, Sanshan 86710871 382 Liu Jia-hua Female 31 Farmer school Village, Banqiao Town

Yan Junior middle Zhushan Group, Sanshan 86714432 383 Female 55 Farmer Ming-lin school Village, Banqiao Town

Du Primary Zhushan Group, Sanshan 86717639 384 Female 49 Farmer Peng-xiang school Village, Banqiao Town

Zhushan Group, Sanshan 86717892 385 Wang Jiu-lan Female 32 Senior school Farmer Village, Banqiao Town

Primary Zhushan Group, Sanshan 386 Zhao La-mei Female 66 Farmer school Village, Banqiao Town

Liu Junior middle Zhushan Group, Sanshan 86701955 387 Female 42 Farmer Heng-xiang school Village, Banqiao Town

Junior middle Zhushan Group, Sanshan 86711227 388 Zhu Yu-hua Male 40 Farmer school Village, Banqiao Town

Primary Zhushan Group, Sanshan 86720418 389 Zhu Cai-qin Female 39 Farmer school Village, Banqiao Town

Zhushan Group, Sanshan 86724816 390 Yan Xiao-lan Female 45 Senior school Farmer Village, Banqiao Town

Zhushan Group, Sanshan 391 Ai Shi-yun Female 60 Illiterate Farmer Village, Banqiao Town

Primary Zhushan Group, Sanshan 86713873 392 Li Shu-qin Female 50 Farmer school Village, Banqiao Town

Zhushan Group, Sanshan 86714432 393 Liu Gui-lan Female 58 Illiterate Farmer Village, Banqiao Town

Special Zhushan Group, Sanshan 86707294 394 Zhu Yu-hong Female 43 Teacher school Village, Banqiao Town

Zheng Special Zhushan Group, Sanshan 86717562 395 Male 62 Retired Cadre Ding-zhong school Village, Banqiao Town

Zhu Primary Zhushan Group, Sanshan 86725004 396 Male 33 Farmer Guo-ping school Village, Banqiao Town

Yan Gujia Group, Xinjian 86732290 397 Female 24 College Village cadre Xiu-zhen Village, Banqiao Town

Xujiachang, Xinjian 86732290 398 Chen Lan Female 41 College Village cadre Village, Banqiao Town

119

Educa- No. Name Sex Age Profession Family address Tel tion

Wangjiazhuang, Xinjian 86732296 399 Yu Fang-lan Female 40 Senior school Village cadre Village, Banqiao Town

Zhu Junior middle Meicun Group, Xinjian 86732291 400 Female 42 Village cadre Kuan-lan school Village, Banqiao Town

Xinjiang Housing Estate, 86732291 401 Wei Su-qin Female 38 Senior school Village cadre Xinjian Village, Banqiao Town

Wang Junior middle Qiaojiazhuang, Xinjian 86732290 402 Female 48 Village cadre Gui-lan school Village, Banqiao Town

Xujiachang, Xinjian 86705268 403 Xu Yi-li Male 50 Senior school Village cadre Village, Banqiao Town

Xinjian Flat, Street 86707775 404 Xu Ming-gui Male 42 College Village cadre Committee, Banqiao Town

7.3 Result of Public Poll 7.3.1 Statistics of the Poll (1) With the status quo of environmental quality at the project location area, 35 persons are very satisfied, 166 persons are relatively satisfied, 141 persons are not satisfied, and 62 persons are very dissatisfied; (2) About the planned project, 44 persons know nothing, 333 persons know something, and 27 persons know clearly; (3) About the harm or affect by the project, when completed, on the local environmental quality, 61 persons think it will be serious, 96 persons think it will be a little serious, 193 persons think it will be just so so, 37 persons think it will be not so serious, and 17 persons have no ideas; (4) In terms of the attitude towards this project, 8 persons are strongly for it, 300 persons are for it with conditions, 14 persons do not care about it, and 8 persons are against it. 7.3.2 Public Suggestions and Demands Most of the people visited during the public poll put forward their views and demands in the column of Public Suggestion & Requirement, of the 404 people, 314 people filled in this column, the participation rate is up to 78%, very seldom in the public polls carried out before. This shows that the local people have a very strong sense of involvement, very concerned with environmental protection, their own interests, as well as the social development and progress. The views and comments of people visited are given in the summarized form of Table 7-2, based on the proportion of people with different opinions.

120

Table 7-2 Public Comments and Demands

Comments & Demands No. of persons Proportion Sequence

Support the project 8 2% 6 Improve environmental control and emission to the 88 21.8% 3 standards Protect the environment 139 34.4% 1 Ask for relocation 62 15.3% 4 Improve construction management 10 2.5% 5 Suggest for landscaping 8 2% 8 Ask for economic compensation 4 1% 7 Demand for better environmental supervision 4 1% 8 Protect people’s interests and economic compensations 7 1.7% 7 Number of persons that didn’t fill in this column 90 22.3% 2 From the table, the following points of views are derived: Most of the people believe that construction projects are important to facilitate the local social and economic development and promote entrepreneurial boom, but full attention should be paid to environmental protection in the course of project construction, that is why those suggestions concerning environmental protection rank top in the percentage. Many people wrote a lot in this column, expressing that the construction project is a good thing for local development, but also worrying that possible environmental pollutions may endanger their own homes. The people visited during the public poll this time have a strong environmental awareness, they put forward a lot of suggestions and comments on strengthening management of emissions to standards, covering the aspects from project design, construction, three wastes control, cleaner production, environmental management and supervision, and some of their views and opinions are very wise, and keep to the point. For example, an old gentleman named Fan Yue-tai made 6 recommendations covering processes like coking, sintering, steel-making, iron-making, rolling, environmental supervision and monitoring program. One of his suggestions is that coking process must be provided with equipment for coal feeding and coke pushing and dust removal, with application of CDQ technology. And full negative pressure process shall be used in gas refining, and hydrogeneration process be used in benzene fine processing, with the gas concentration after desulfurization below 200mg/m3, etc. Such suggestions are very good indeed, very high in reference value. It also shows that public involvement during environmental impact assessment (EIA) really means much in reality. During the public poll this time, the people in Huangnitang, Zhushang, Zhushan and some other villages asked for relocations to places further away from the plant area. These people asking for relocation are those residents on the whole who are to be relocated for the current project, and their main reason for relocation is serious air pollution, heavy dust near the plant area, a smell of sulfur dioxide and other smells. Some people complain about noises and poor water quality. The relocation plan to be carried out for the current project is in line with the requirements of these people, as detailed in the scope of relocation shown in the plant layout plan.

121

Some other advices and comments are of good reference value, too, such as those on strengthening management during the construction phase, protection of people’s interests, a good job in environmental supervision, a good planning of the areas for relocated people, and so on. 7.3.3 Analysis of Objections Of the public poll, there are 8 persons who have objections to the project, covering 2% of the poll sheets, the project owner is supposed to pay due attention to them in spite of the small percentage they have. Of the 8 persons against the project, 4 persons filled in their reasons for their objections while the other 4 did not. However, of the 4 persons who didn’t mention their reasons for objection, 3 persons did wrote down their requirements and suggestions in the column of Intended Suggestion, in which they also mentioned atmospheric pollution, water pollution and noise pollution. We think it is normal protection of individual rights for good environment. Of the 8 opposers, 7 persons made suggestions in the column of Intended Suggestion that the project owner should strengthen pollution control and make it to do emissions up to standards. This shows these persons are not resolute opposers, on the other hand it means they do not have specific reasons for their objections. See Table 7-3 for the analysis of the specific objections. Table 7-3 Analysis of Objections

Name Objection Comment Measures

Yan Ming-fu

Yin Yi-lin Asking for solution to During the intended construction, Further environmental Meishan Iron & Steel Company should do Hu Hong-yan identification of pollutions, one person more in presentation to the local residents, pollutions is to Zhu Jun clearly means it is environmental protection, and protection be made Hang Jun-hong atmospheric pollution of the legal rights of the people.

Zhang Yu-xi

The construction owner should inquire This is a just with this person about noise impact. If Liu You-gen Loud noises opinion. production noises have impact to his life, it should be settled down.

Not clear—what Xie Yun To solve problems problem? The objections in the public poll are mainly on the worry over environmental pollutions, so the project owner should, during the construction, do its best in the environmental protection and pollution control to the satisfaction of the people, and carry out immediate solutions to pollution problems that upset people. On the other hand, the project owner should do more as much as possible to explain to the people and masses about those issues of their concern, so as to dissipate their doubts and have their support for this construction project.

122

8. Assessment conclusions

8.1 Overview of the current status of Meishan Iron and Steel Company 8.1.1 Basic situation Shanghai Meishan Iron & Steel Co., Ltd. is a wholly-owned subsidiary of Baosteel Co., Ltd. and a large iron & steel conglomerate engaged in coking, sintering, ironmaking, steelmaking, continuous casting and steel rolling. The company is located outside Zhonghua Gate of Nanjing City, connected to Ningwu Railway and Ningwu Highway to the east and adjacent to the Changjiang River to the north and has internal rail lines and wharf with 10,000-tonnage berths, enjoying very convenient transport. After years’ constant, timely and well-planned technology innovation, particularly the completion of the systematic project for the overhaul of steelmaking, continuous casting and steel rolling facilities and No. 2 BF as well as the supporting projects, its production equipment, technical equipment and auto-control level all have reached national advanced level, some of them have reached international advanced level and a great headway has been made in its actual production capacity, and the technology content and added value of its products. Covering an area of 4.2 km2, the company registered 5357 employees including 1772 technical personnel, RMB13.225 billion of total assets and RMB11.409 billion of original value of fixed assets by the end of 2004. In that year, it produced 2.980 million tons of pig iron, 3.000 million tons of continuously cast blooms and 2.9388 million tons of hot rolled coils and realized RMB6.177 billion of product sales revenue, RMB1.1019 billion of profit and tax (including RMB547.8 million of profit) and 560t steel/person*year of labor productivity. The company comprises sintering plant, ironmaking plant (including coking), steelmaking plant (including continuous casting), rolling mill, power department, transport department and so on. By the end of 2004, it owned the following main production facilities: 2×130m2+1×180m2 sinter machines, 3×65-duct coke ovens, 2×1250m3+1×1280m3 BFs, 2×150t converters, 1×1300t hot metal mixer, a set of molten iron desulphurization unit, 1×150t LF (ladle refining furnace), 1×150t RH vacuum treatment unit, a 1320mm 2-unit 2-strand CCM, a 1320mm high-performance 1-unit 1-strand CCM, and a set of 1422mm continuous hot rolling mill. Output in 2004: 4.75 million tons of sinter, 1.205 million tons of  coke, 2.980 million tons of pig iron, 3.00 million tons of continuously cast blooms, and 2.92 million tons of hot rolled coils. 8.1.2 Discharge of main pollutants from existing facilities (1) Wastewater In 2004, Meishan Iron and Steel Company used 49757.88×104m3 of water in total, including 3679.2×104m3/a of supplemented fresh water, 58.0×104m3/a of fresh water for domestic use

123

(including Meishan Chemical Branch) and 3621.2×104m3/a of fresh water for production use. 12.1m3 of fresh water per ton of steel was consumed. The reused water amounted to 46078.68×104m3/a. The reutilization rate was 92.6%. In 2004, Meishan Chemical Branch used 4731.1×104m3 of water in total, including 1080.1×104 m3/a of supplemented fresh water. The reused water amounted to 3650.0×104m3/a. The reutilization rate was 77.1%. The status of wastewater discharge in Meishan Iron and Steel Company in 2004 is listed in Table 8-1. Table 8-1 Status of wastewater discharge in Meishan Iron and Steel Company in 2004

Wastewater from Total amount Wastewater from Meishan Wastewater from index set by West Discharge Chemical Branch Total Meishan Iron & Steel Nanjing Item Outlet (North Discharge discharge Environmental Outlet (t/a) Protection Ave. C Dis. amt. Ave. C Dis. amt. Ave. C Dis. amt. Bureau(t/ a) mg/l t/a mg/l t/a mg/l t/a

Wastewater — 19080000 — 48910800 — 9688560 58599360 —

PH 6-9 — 7.5 — 7.6 — — —

CODCr 56.5 1078 57.1 2792.81 125.9 1220 4012.81 4680

SS 55.0 1049 76.0 3717.22 43.2 418.5 4135.72 8550

NH3-N 3.4 66.8 8 391.29 11.5 111.4 502.69 —

Petroleum 2.5 47.7 2.09 102.22 1.3 12.6 114.82 288

Ar-OH 0.023 0.44 0.009 0.44 0.04 0.388 0.828 3.6

CN 0.044 0.83 0.017 0.83 0.04 0.388 1.218 5.4 (2) Waste gas In Meishan Iron & Steel, the current air pollution sources mainly include coke oven, coke quenching tower, sinter machine, ironmaking BF, limekiln, steelmaking converter, heating furnace for hot rolling and thermal power plant. The fuels used include coke, coke oven gas, BF gas, converter gas, hard coal and so on. In 2004, Meishan Iron & Steel and Baosteel Chemical emitted 7206225×104m3/a of non-fugitive waste gas, 999t/a of smoke gas, 2724.6t/a of dust, 18156t/a of SO2 and 7637.38 t/a of NOx. The pollutants contained in the fugitively emitted gas are dust and SO2 with an emission amount of 6965t/a and 412t/a, respectively.

10688t/a of smoke (dust) and 18568t/a of SO2 are emitted in total. (3) Major environmental issues The fresh water consumption per ton of steel is 12.1m3 and there are a considerable number of once through systems. It is needed to upgrade the existing circulating water

124

systems with low circulation rate to realize serial sewage discharge and raise circulation rate; The amount of fugitive dust is large, existing coke ovens and BF cast houses in particular;

Coke oven gas is not all desulfurized. The emission of SO2 in gas is large; The sulfur content of self-owned ore reaches 0.42%. In the future, the percentage of import ore must be increased so as to reduce the overall sulfur content of ore and when the condition is ripe, desulfurization of sinter flue gas shall be undertaken; The water supply and discharge in Meishan Chemical Branch is large. More than 90% of it is directly discharged water, causing considerable waste; Phenol-cyanogen wastewater is discharged without reaching discharge standard. 8.2 Overview of the intended project Main facilities of the intended project are listed in Table 8-2. 8.2.1 Main construction content and compliance to industrial policy From Table 8-2, it can be seen that the new project under the Product Matrix and Process Equipment Upgrading and Technical Transformation Project of Meishan Iron and Steel Company meets the requirement of industrial policy in terms of technical scale. Meanwhile, the coke oven of this project is provided with CDQ, BF TRT and pulverized coal injection. All waste heat and energy of sinter, converter and steel rolling are recovered and utilized, all gas is recovered, and the remaining gas is used to generate power and produce steam. The overall energy consumption per ton of steel in this project is 0.683t of standard coal and the consumption of fresh water per ton of steel is 4.7m3. Therefore, this project meets the Development Policy for Iron and Steel Industry. Moreover, Meishan Iron and Steel Company is subordinate to Baosteel Co., Ltd. Baosteel Co., Ltd. is a super large iron and steel business conglomerate in China. The industrial policy encourages it to appropriately expand scale and its subordinates to adjust and upgrade their product matrix to further enhance international competitiveness. Therefore, this project tallies with the goal of the industrial policy and its requirement on adjustment of industrial layout. Meanwhile, all external conditions of this project are possessed: (1) The intended project mainly uses imported ore and relies on the import of Baosteel Co., Ltd.; (2) By building a general sewage treatment plant, the intended project won’t increase the amount of fresh water of the company as a whole; (3) Take the reform measure of “pushing ahead old by new” to realize the goal of output increase and pollution reduction; (4) Coal, ore and lime use the transport conditions of the current supply channels. Only new raw material and finished product terminals need to be built.

125

Table 8-2 List of main facilities in existing and intended projects “pushing ahead old by Facility scale after completion of Production No. Existing main facility Intended facility new” project the project capacity (10kt) Dismantle 3×65-duct 4×55-duct 6m coke ovens 6×55-duct 6m coke ovens Coking 3×65-duct coke ovens Coke: 320 Upgraded with new (CDQ) (CDQ) 2×55-duct coke ovens 2×130m2+1×180m2 sintering Sintering Adjust ore ratio 1×380m2 2×130m2+1×180m2+1×380 ㎡ Sinter: 875.2 machines

# # 1×3200m3 BF Improve 1 and 3 BF 2×1250m3+1×1280m3+ 3 3 Molten iron: Ironmaking 2×1250m +1×1280m BF secondary dust (TRT+pulverized coal 1×3200m3 537.46 collection measures injection) 2×150t converter

1×1300t mixer 2×150t converter 4×150t converter A set of molten iron 1×150 RH 2×150 RH Molten steel: Steelmaking desulfurization unit Cancel mixer 2×158 LF 162t LF+158 LF 545.2 1×162t LF 2×ladle desulfurization units 3×ladle desulfurization units 1×150t RH vacuum treatment installation 1×1320mm 2-unit 2-strand slab 1×1320mm 2-unit 2-strand CCM Continuously Continuous slab CCM 2×thin slab CCM 1×1320mm 1-unit 1-strand cast bloom: casting 1×1320mm 1-unit 1-strand high-performance slab CCM 516.4 high-performance slab CCM 2×thin slab CCM

126

“pushing ahead old by Facility scale after completion of Production No. Existing main facility Intended facility new” project the project capacity (10kt)

1×1422mm continuous hot 1×1700mm hot rolling mill rolling mill 1×1422mm continuous hot Steel product: Steel rolling rolling mill 1550 cold rolling steel strip 1×1700mm hot rolling mill 502.69 mill 1550 cold rolling steel strip mill

Limekiln 2 ×500t/d shaft kiln 1×500t/d shaft kiln 3×500t/d shaft kiln Lime: 51

2×5000m3/h oxygen generator Oxygen 2×5000m3/h PSA oxygen 1×35000m3/h oxygen sets generation generator generator set 1×35000m3/h oxygen generator set

Raw material terminal Raw material terminal: 2×2000t+5000t berth 2×2000t+2×10000+5000t berths Throughput: Terminal 2×10000+3×5000t berths Finished product terminal Finished product terminal: 2914 2×5000t berth 2×5000t+3×5000t berths

3× 220t/h boiler (all 1×220t/a gas-fired boilers 3×220t/a gas-fired boilers Power: 1.06 coal) Thermal billion KWH 3×220t/a coal/gas-fired 2×220t/a gas-fired boilers 3×220t/a coal-fired boilers with power plant Desulfurization of flue boiler desulfurization facility Steam: 498 gas

Sewage treatment Sewage treatment plant 100kt/d 100 kt/d plant

127

8.2.2 Compatibility between urban planning and environmental planning

(1) The construction project complies with the master development plan of Baosteel Co., Ltd. According to the “11th Five-Year Plan” of each subsidiary of Baosteel Co., Ltd., it is planned to build 1700-level thin slab continuous casting and rolling facility in Meishan Iron and Steel Company. Meanwhile, considering to give full scope to the process features of thin slab continuous casting and rolling, the product orientation is set to produce medium/low grade non-oriented silicon steel, building steel and special-purpose steel and further develop and produce ultra low and extremely low carbon steel, as well as various kinds of steel coils, such as: transformation induced plastic steel (TRIP) for automobile, and double phase steel (DP). (2) The construction of the project complies with the urban development plan of Nanjing City Meishan Iron and Steel Company is located in Banqiao new town on the outskirts of Nanjing. According to Nanjing Urban Master Plan (1991-2010), the functional orientation of Banqiao new town (the location of the intended project) is that Banqiao is a comprehensive industrial town in urban development zone, its industrial orientation is to encourage the development of metallurgical and mechanical processing industry and trade circulation and forbid the construction of projects causing serious pollution on water body. Therefore, the intended project complies with the master plan. (3) The construction of the project complies with Nanjing environmental development plan It is indicated in the Nanjing Environmental Protection Plan for Riverfront Development: industries with serious water pollution shall be arranged in the downstream of a city and water source, and industry with serious air pollution shall be arranged at leeward so far it is possible. Banqiao area where the project is located is at down wind of Nanjing and conforms to the principle of Nanjing Environmental Protection Plan for Riverfront Development, i.e. to arrange industry with serious air pollution down wind the city as far as possible. 8.2.3 Main pollution control measures and environmental protection investment of intended project The intended project is designed as per the concepts of clean production, cyclic economy and sustainable development, and all process equipment and environmental protection facilities are internationally and nationally mature and reliable advanced technologies. 3 a.CDQ and coke oven gas is desulfurized to ensure the content of H2S is below 200mg/m ; b.The waste heat of sinter flue gas is recovered and macropellet sintering technique adopted; c.BF oxygen enriched pulverized coal injection and TRT power generation; d.Converter gas recovery, Generation-4 “OG” technology and converter lining protection technology by slag splashing; e.Sequential casting and continuously cast bloom hot charging; f. Adopt high-performance electro-precipitators and new material bag type dust collectors in 128

3 an all-round way to basically control smoke gas emission concentration below 30mg/m ; g. Attach importance to generation control, trap and collection of fugitive dust from BF cast house and raw material system, and secondary flue gas; h. Build a general sewage treatment plant, reuse 74.4% of sewage discharged from the process, and reduce fresh water consumption from 5433t/h to 4868t/h and discharge of wastewater from 3284t/h to 1524t/h on the precondition that the output increases by 76%. i. After treated to reach Grade 1 discharge standard, phenol-cyanogen wastewater is reused to flush BF slag (other reuse options include ash flushing in thermal power plant, BF gas cleaning, sinter pelletization and so on). Acidic/alkaline wastewater (chromic wastewater) is reused internally and won’t be discharged. j. The total investment in environmental protection accounts for 9.4% of the total investment. 8.2.4 Total discharge of pollutants in the intended project The total amount of pollutants emitted to the atmosphere in the intended project is listed in Table 8-3. The total emission amount of smoke gas is 2279t/a, and SO2 6987t/a. The intended project consumes 13.977 million m3/a of fresh water and 7.47228 million m3/a of reuse water and discharges 5.94366 million m3/a of wastewater, of which 5.51442 million m3/a is discharged into the sewage treatment plant. 429,240 m3/a of condensed water and equipment indirect cooling water is discharged into North Discharge Outlet (from Meishan Chemical Branch). After deduction of the water used by a set of (2×55-duct) coke ovens, the consumption of fresh water per ton of steel is 5.66m3, about 48% of which is used by cold rolling process; the amount of wastewater discharged per ton of steel is 2.38m3, about 41.6% of which is discharged from cold rolling process. Table 8-3 Emission amount of air pollutants in the intended project (t/a)

No. Production step Emission amount Source of SO2

Smoke gas SO2 t/a 1 Coking 309.3 171.6 Flue gas from head of sintering machine: 6554.5 2 Sintering 679 6554.5 BF gas combustion: 23.3 3 BF 578 37.7 Coke oven gas combustion: 4 *Steelmaking (2×150t.) 432.2 11.18 342.6 5 Thin slab 67.2 25.96 Fugitive emission during coking: 6 Limekiln 53.4 66.6 7 Gas purification 6.0 8 Cold rolling 48.2 37.5 Fugitive emission in 9 90 stock house

129

No. Production step Emission amount Source of SO2

10 New gas-fired boiler 22 142.6 11 Total 2279.3 6987 6987 *——emission amount of one converter ×2; for smoke gas and dust, 72t/a of flue gas emitted from molten iron desulfurization process is deducted

Coking NH3: 15.93 H2S: 50.4 characteristics Ammonium sulfur waste gas: 35 BSO: 1.2 HCN: 0.24 Pollutants BaP: 0.1067 The intended project will generate 1,622,079t/a of solid waste, which can all be recovered and utilized except 16850t/a of sludge generated by sewage treatment plant. 8.3 Main conclusions on topic-specific assessment 8.3.1 Assessment on the feasibility of environmental protection measures (1) Analysis conclusion on the feasibility of environmental protection measures for waste gas The waste gas in this project mainly includes: flue gas from coke oven production, and heads and tails of sintering machines, BF primary flue gas and secondary flue gas, BF cast house flue gas, mixer flue gas, converter flue gas, flue gas from converter auxiliary system, LF flue gas, dust from stock house, bulk material system and belt conveyance, and acidic waste gas generated from cold rolling process. After treatment, the emission of pollutants complies with Grade 2 standard as defined in the Integrated Emission Standard of Air Pollutants GB16297-1996, the Emission Standard of Air Pollutants for Industrial Kiln and Furnace BG9078-1996 and the Emission Standard of Air Pollutants for Coke Oven GB16171-1996. Therefore, the environmental protection measures for waste gas pollution sources of the intended project are feasible. (2) Analysis conclusion on the feasibility of environmental protection measures for wastewater The water use of the intended project adopts a series of techniques to conserve water resources, such as: separation of dirty and clean water, circulated use, multiple use, “blowdown” in reasonable serial connection, and water quality stabilization. The main pollutants in clean circulating water system and dirty circulating water system are SS, ppetroleum and temperature rise. The water is circulated and reused after cooling and precipitation treatment. The water discharged in a small amount is led to the company’s sewage treatment plant where it is treated and sent back to production for reused. The reuse rate is 74.4%. Phenol-cyanogen wastewater is treated separately to reach standard, and then is used to flush BF slag. Acidic/alkaline wastewater (chromic wastewater) is treated separately to reach standard, and then is used to treat steel slag. As a whole, the project once completed will significantly reduce the amount of wastewater discharged into the Changjiang River. The wastewater still needing to be discharged in a small amount will be discharged after it is

130

treated to exceed Grade 1 standard. Therefore, it is believed the control measures for wastewater pollution sources of this project are feasible.

(3) Analysis conclusion on the feasibility of environmental protection measures for noise Sound insulation, sound silencing, sound absorption and vibration reduction measures are adopted for noise sources according to the nature of the sound source to reduce environmental impact of noise. They are environmental protection measures universally adopted by iron and steel companies and feasible. (4) Comprehensive utilization and treatment of solid waste The intended project will generate 1,622,079t/a of solid waste, mainly including steel slag and recovered ash and sludge which can completely recovered and utilized. The solid waste generated in coking gas refining process is directly sent back to prepare coal. Only the sludge generated by the general sewage treatment plant is treated by municipal administrative institution and amounts to 16,850t/a. Therefore, the solid waste generated by the intended project won’t affect ambient environment. 8.3.2 Assessment conclusions on clean production (1) The comparison between the current clean production level of Meishan Iron and Steel Company and indexes indicates that 10 items are in Grade 3 level, 12 in Grade 2 and 14 in Grade 1, a sound environmental management system is yet to be established and the level of clean production is in around Grade 2. The comparison with the intended project reveals that the principal gap lies in the facts that coking process doesn’t adopt CDQ, sintering machines don’t all lay hearth layer, and water consumption and discharge are large. They are the very goal for current and future technology renovation of Meishan Iron and Steel Company. (2) The production process and equipment adopted by the new coke oven reach Grade-1 level; resource utilization and product and waste recovery all reach Grade-1 level; the indexes for the production of waste gas pollutants all reach Grade-1 level, and the amount of particular waste gas pollutants reaches Grade -2 level (including the tar processing facility of Meishan Chemical Branch, so the wastewater generated during ammonia distillation is more than that generated from a simple coking facility). Therefore, it can be determined the clean production indexes for new coke oven is in Grade-1 level as a whole. (3) In consultation of the “cleaner production standard” for iron and steel industry (draft for comment), the intended project has two indexes in Grade 2 level, 4 in or above Grade 3 level (mainly resulting from the high sulfur content of sinter), and 23 in Grade 1 level. In addition, the intended project will establish and implement ISO 14001 environmental management system as per the requirement of Grade 1 standard. Therefore, it is assessed that the clean production level of the intended project can reach Grade 1 level. (4) The total energy consumption of the intended project is 1.5709 million tons of standard coal and its comprehensive energy consumption per ton of steel is 683kgec, meeting the access condition (700 kgec/t of steel) specified in industrial policy. Compared to major large iron and steel enterprises in China, the energy consumption indexes in each process step are advanced and the energy consumption indexes in main process steps are better than the current average level of Baosteel.

131

(5) After the intended project is completed, Meishan Iron and Steel Company plans to upgrade existing backward equipment in succession. To coordinate the construction of environmental protection facilities under the “pushing ahead old by new” project, Meishan Iron and Steel Company will ensure all production facilities reach the level of this intended project, all clean production indexes of the company reach current Grade 1 level and the consumption of fresh water per ton of steel below 5m3 and comprehensive energy consumption per ton of steel less than 700kgec by the end of the “11th Five-year Plan” period. 8.3.3 Assessment on up-to-standard pollutant discharge and total amount control (1) Up-to-standard discharge of current pollutants All non-fugitive waste gas emission sources in the existing facilities of Meishan Iron and Steel Company reach emission standard;

The sewage in the company is discharged after reaching standard, except that CODcr and

NH3 contained in phenol-cyanogen wastewater discharged from North Discharge Outlet exceeds specified limits; (2) Up-to-standard discharge of pollutants generated in the intended project The intended project strictly observes applicable pollutant discharge standards. Except converter primary flue gas, the emission concentration in every smoke gas emission source is controlled below 40mg/m3 (electro-precipitator) and 30mg/m3 (bag type dust collector), and all heating furnaces use clean gas. The emission concentration in thermal power plant and heads of sintering machines is much lower than respective emission limit; All industrial sewage generated in the intended project (except phenol-cyanogen wastewater and chromic wastewater) enters the general sewage treatment plant for treatment. After treatment, 74% of it is reused and 26% of it is discharged as per Grade 1 standard; Except that the sludge generated by the general sewage treatment plant is sent to municipal rubbish landfill, all other solid waste generated by the intended project is recovered and utilized and no hazardous and harmful solid waste is discharged. (3) Total amount control measures The total emission amount of air pollutants generated by existing facilities and intended facilities of Meishan Iron and Steel Company and the whole company after the project is completed is shown in Table 8-4. Table 8-4 Table for control of total emission amount of waste gas pollutants (unit: t/a) Emission Total amount Current Emission Total emission reduction Increase/ control index Pollutant emission increase from of the company through decrease and set by factor of the intended after the project “pushing percentage (%) environmental pollutants project is completed ahead old by protection Smoke gas 10688 6910 2279 -4631/-43.3 6057 10600 (dust)

SO2 18568 8312 6987 -1325/-7.1 17243 19000+2000

132

a. The amount of smoke gas emitted by existing facilities is slightly higher than the set total amount index, but fugitive emission accounts for a large percentage, causing obvious impact on the quality of surrounding air environment. The total emission amount of SO2 is close to the total amount index; b. The intended project will emit 2,279t/a of smoke gas and 6987t/a of SO2; c. After the project is completed, Meishan Iron and Steel Company will totally emit

6,057t/a of smoke gas and 17,243t/a of SO2. The emission amount of smoke gas is reduced by

4,631t/a and SO2 by 1,325t/a than the present level. The construction of the project meets the requirement on total amount control; d. As a general sewage treatment plant is built, after the project is completed, the amount of discharged wastewater will decrease by 1,541.832t/a than the present, and the discharge of CODcr will be reduced by 1,630.5/a with a value much lower than the total amount index. 8.3.4 Conclusions on the feasibility of site selection (1) The work with regard to land acquisition for the intended project near the current plant area is under the way. The land has been included into urban master plan. Procedures for land use are proceeding. Demolition and relocation plan is being implemented by government department. Obviously, this project complies with Nanjing urban master plan. (2) The intended project is located in Banqiao new town, Nanjing City, which belongs to Category 2 functional zone of ambient air quality. Although the intended project will emit a small amount of pollutants, through controlling (eliminating) the current pollution sources by measure of “pushing ahead old by new”, the total emission of main pollutants in waste gas generated by Meishan Iron and Steel Company will be reduced by about 43.3% and the emission of SO2 will be reduced by 7.1% after the project is completed. The forecast analysis indicates the impact of Meishan Iron and Steel Company on ambient air quality is lightened to some extent. (3) At the villages within the sanitation protection distance of this project, 1160 households including 2230 people are affected. A plan has been worked out to relocate all of them. (4) The intended project has no obvious impact on surrounding ecological environment. (5) The intended project closely relies on the existing infrastructure facilities of the company, minimizes the occupation of land and reduces impact on ecology and environment. After fully considering the impact of positive and negative factors, the assessment believes the site selected is feasible, but the construction unit shall give full consideration to the suggestions described in 7.4.3. 8.3.5 Assessment conclusions on current status of ambient air quality and impact (1) Assessment conclusions on current status of ambient air quality Around Meishan Iron and Steel Company, 12 monitoring points are arranged (monitoring time: April 2005). The monitoring results are assessed as follows: Through statistics and analysis of monitoring results, the pollution of atmospheric

133

environment by various kinds of pollutants in the assessed area can be known and is described separately as follows: 3 The range of hourly SO2 concentration is 0.003-0.171mg/m and that of daily concentration is 0.003-0.077mg/m3. Neither hourly concentration nor daily concentration in each monitoring point exceeds the specified limit. 3 The range of hourly NO2 concentration is 0.006-0.098mg/m and that of daily concentration is 0.009-0.063mg/m3. Neither hourly concentration nor daily concentration in each monitoring point exceeds the specified limit. 3 The range of daily PM10 concentration is 0.086-0.439mg/m . In the whole assessed area, the daily average concentration in every monitoring point exceeds the specified limit. The range of daily TSP concentration is 0.171-3.094mg/m3. In the whole assessed area, the daily average concentration in every monitoring point exceeds the specified limit. The range of hourly F concentration is 0.13-5.00μg/m3 and that of daily average concentration is 0.48-4.14μg/m3. Neither hourly concentration nor daily concentration in each monitoring point exceeds the specified limit. The range of daily B[a]P concentration is 0.0011-0.0365ug/m3. Except 9# monitoring point (aside the original coke oven), in the whole assessed area, the daily average concentration in each monitoring point doesn’t exceed specified limit. 3 The range of NH3 primary concentration is 0.01-0.01mg/m . In the whole assessed area, the primary concentration in each monitoring point doesn’t exceed specified limit. 3 The range of H2S primary concentration is 0.001-0.003mg/m . In the whole assessed area, the primary concentration in each monitoring point doesn’t exceed specified limit. The range of hourly HCl mist concentration is 0.007-0.032mg/m3 and that of daily average concentration is 0.008-0.014mg/m3. Neither hourly concentration nor daily concentration in each monitoring point exceeds the specified limit. The range of chromic acid mist primary concentration is 0.001-0.009mg/m3. In the whole assessed area, the primary concentration in each monitoring point doesn’t exceed specified limit. From the above analysis result, it can be seen that: the current status of ambient air quality in the assessed area exceeds Grade 2 standard as defined in the Ambient Air Quality Standard. (2) Conclusions on ambient air quality impact assessment The forecast on the concentration of air pollutants indicates: after the intended project is completed, Meishan Iron and Steel Company will have a small contribution to the hourly, daily and annual concentration of SO2 and PM10 in the whole assessed area and each assessment point. After the intended project is put into production, the impact that the dust generated by Meishan Iron and Steel Company exerts on the quality of atmospheric environment will be significantly reduced. The impact of SO2 and PM10 on the quality of atmospheric environment is basically same as the current projects does. The change range is

134

below 2% of standard value. The impact of NO2 is net increase, because the contribution concentration is small and the background concentration is low, and the superposition of these two still meets the requirement of Grade 2 environmental quality. The daily average emission concentration of characteristic pollutants in this project has no much impact on the ambient environmental quality at boundary. 8.3.6 Assessment conclusions on the current status of water environmental quality and impact analysis (1) At present, the water quality at each monitoring section in Nanjing’s Banqiao Section of the Changjiang River is good and better than two years ago. It can reach the requirement of Class II standard as defined in the Environmental Quality Standards for Surface Water (GB3838-2002). (2) After the intended project is completed, Meishan Iron and Steel Company (including Meishan Chemical Branch) will significantly reduce the amount of discharged wastewater, totally reduce the amount of discharged CODcr by 1630.5t/a, and lower CODcr concentration at the section 1400m (water intake) down West Discharge Outlet of Meishan Iron and Steel Company by about 0.01 mg/L, for although the amount of discharged pollutants is reduced significantly, the flow of the Changjiang River is very big, the effect of concentration reduction is limited and the water quality in this section of the river will still maintain current level. 8.3.7 Assessment conclusions on the current status of sound environmental quality and impact (1) Assessment conclusions on the current status of sound environmental quality The noise level at boundary of Meishan Iron & Steel Company is 46.8-69.5dB (A) in the daytime and 42.5-63.9 dB(A) at night. The noise at boundary exceeds specified limit in a number of monitoring points, but only at four night monitoring points, the excess of specified limit is caused by production noise, which are 6#, 11#, 12# and 19# monitoring points. After the intended project is completed, there is no residential area affected, and it won't cause much impact on environment. The intended project will, based on the principle of pushing ahead old by new, take appropriate noise control measures to ensure day and night noise at boundary reaches standard. The environmental noise at 21#, 22#, 23# and 24# sensitive points is lower than the standard value for Class 2 area during both day and night. The surrounding noise environment is good. (2) Conclusions on impact analysis of acoustic environmental quality After the intended project is put into production, the equipment noise may have certain impact on each monitoring point. The superposed value will increase slightly. But the forecast day and night noise values at boundary all meet the requirement of assessment standard. Moreover, after the sanitation protection distance is determined, the noise won’t affect the residential areas and villages near the boundary.

135

8.3.8 Conclusions on analysis of solid waste discharge and impact The dust recovered by the dust collection system of the intended project is coal or ferric particles. It is nontoxic and all reused in production. BF granulating slag, converter slag and continuous casting mill scale are all subject to comprehensive utilization. The slag and residue solution discharged during gas purification are all directly reused in production and not discharged to outside, so they won’t pollute the environment. 8.3.9 Analysis of environmental impact in construction period During construction of the project, the construction activities will inevitably create environmental impact, mainly including the environmental impact from waste gas, dust, noise, solid waste and wastewater. According to the analysis of the construction characteristics of the project, the environmental impact in construction period is short-term, recoverable and local environmental impact. 8.3.10 Analysis of environmental risks Among the main production raw material and products of this project, benzene and gas are inflammable and explosive; ammonia, and NaOH and HCl are highly corrosive. The storage, transport and use of raw material have potential environmental risk. Effective and strict risk control measures must be taken from the perspectives of technology and management to nip it in the bud. During production, abnormal operation or damage of environmental protection facilities will result in excessive discharge of pollutants and affect environmental quality. This assessment puts forth disaster plan and emergency measures for sudden accidents and provides countermeasures for failure of environmental protection facilities. In a word, even if risk accident occurs, by taking the above preventive measures, it can still be limited to production site and effectively controlled and won’t spread out of the factory and to neighboring enterprises. 8.3.11 Analysis conclusions on economic benefit of environmental impact (1) Investment in environmental protection The total investment of this project is RMB19,805.39 million, including RMB17,309.64 million of fixed asset investment, and RMB292.20 million of working capital. Among the investment in engineering construction, the investment in environmental protection amounts to RMB1.864 billion, accounting for 9.4% of the investment in engineering construction. (2) Economic benefit of the investment in environmental protection The environmental protection facilities of the intended project can recover all kinds of usable solid waste and recover and utilize water resources, thus reducing the consumption of raw material and the emission of pollutants. They have obvious economic benefit. If the industrial wastewater generated in the whole company is treated and reused, 27.156 mt/a of fresh water can be saved. (3) Environmental benefit of the investment in environmental protection The environmental benefit generated by environmental protection facilities is mainly reflected

136

by reduced discharge of pollutants. It will play a positive role in improving the atmospheric quality and ecological environment inside and near Meishan Iron and Steel Company and reducing the impact on the water quality in the Changjiang River. (4) Social benefit of the investment in environmental protection The social benefit of the investment in environmental protection can hardly be assessed with money, but it is remarkable and mainly reflected in the following aspects: reducing pollutant discharge, helping improve people’s life quality and health, and help the development of local economy and the comprehensive utilization of water resources as well as the sustainable development of the enterprise. To summarize, in view of economic benefit of environmental impact, the intended project’s investment in environmental protection has good economic benefit as well as sound environmental and social benefit. 8.3.12 Public participation and conclusions (1) During this public participation, 404 copies of “Form of Solicitation for Public Opinions on Environmental Protection of Construction Projects in Jiangu” were distributed and all were returned. (2) In the suggestion and requirement column, most respondents gave their own suggestion and requirement. 314 of the 404 people filled out this column, with a participation rate of 78% which is rare in the past survey of public participation, indicating people in the area have a very strong sense of participation and they care about environmental protection, their own interest and social development and progress. (3) Among the respondents, 82 firmly support this project, 300 conditionally support it, 14 don’t care it and 8 oppose it. (4) Among the eight opposers, 4 wrote reasons and 4 not. The requirement and suggestion written by 3 persons in the suggestion column indicate that this project has air, water and noise pollution. We believe this is a proper act for protecting their environmental rights and interests. Although the opposers are a minority, construction unit shall give sufficient attention to their voices. 8.4 General conclusion (1) The intended project complies with the Development Policy for Iron and Steel Industry. a. Building area of sintering machine>180m2; height of coke oven carbonization chamber≥6m; effective area of BF≥1000m3; nominal volume of converter≥120t; nominal capacity of electric furnace≥70t. b. Pulverized coal injection unit, oven-front dust trap and residual pressure generator unit are built to support BF; CDQ, dust collection unit for coal charging and coke pushing is built to support coke oven; converter gas recovery unit is built synchronously to support converter. c. In the intended project, the overall energy consumption per ton of steel is 0.683t of standard coal, the consumption of fresh water per ton of steel is 4.7 tons, meeting the

137

requirement of clean production, and pollutant discharge indexes meet the requirement of environmental protection standard. d. The remaining gas is used for heat and power generation, meeting the requirement for saving energy and increasing the production of self-provided power. e. Meishan Iron and Steel Company is subordinate to Baosteel Co., Ltd. and is within the scope that industrial policy encourages it to increase scale to a proper extent and adjust industrial mix. f. The project realizes the goal of increasing output and reducing sewage. g. External conditions such as: ore, coke, water supply, and transport are possessed and can fully meet the production demand of this project. (2) The intended project complies with Nanjing urban master plan. The construction of the Product Matrix and Process Equipment Upgrading and Technical Transformation Project of Baosteel Meishan Iron and Steel Company is implemented on the acquired land at the neighborhood of the current premises. The land has been included into urban master plan. Procedures for land use are proceeding. Demolition and relocation plan is being implemented by government department. This project complies with Nanjing urban master plan. (3) The intended project complies with Nanjing environmental protection planning It is indicated in the Nanjing Environmental Protection Plan for Riverfront Development: industries with serious water pollution shall be arranged in the downstream of a city and water source, and industry with serious air pollution shall be arranged at leeward so far it is possible. The construction site of this project meets this requirement. (4) The construction of the intended project meets the requirement of up-to-standard discharge and total amount control Definite control measures are provided for every waste gas emission source in this intended project and the waste gas is emitted only after it reaches emission standard; a small amount of wastewater is led into the general sewage treatment plant via pipeline network. After treated, it enters the company’s reuse water system. The amount of wastewater discharged by the company is reduced significantly and all discharged wastewater reaches Grade 1 standard. After the intended project is put into production, the emission amount of main pollutants in waste gas: SO2 17243t/a, and smoke gas 6057t/a, meeting the requirement set by Nanjing Environmental Protection Bureau on the total amount control index of Meishan Iron and Steel

Company (smoke gas: 10600 t/a, SO2: 19000+2000t/a). So it can be seen: after this project is completed, the discharge of pollutants will meet the requirement of up-to-standard discharge and total amount control. (5) The site of the intended project is basically feasible. (6) The construction of the intended project meets the requirement of clean production 138

In consultation of the “cleaner production standard” for iron and steel industry (draft for comment), after this project is completed, the clean production level of Meishan Iron and Steel Company can basically reach Grade 1 level. (7) After the Product Matrix and Process Equipment Upgrading and Technical Transformation Project of Meishan Iron and Steel Company is completed and put into production, Meishan Iron and Steel Company will adopt a series of environmental protection measures. After the project is completed, the company will meet the requirement of total amount control as ratified by Nanjing Environmental Protection Bureau. (8) After the intended project is completed, the emission amount of smoke gas will be reduced significantly, compared to the existing projects. The reduction amount is 4631t/a, the reduction amount of SO2 is 1325t/a and the reduction amount of industrial wastewater is 15.41832 mt/a. All these lighten Meishan Iron and Steel Company’s impact on local environmental quality. The noise impact on surrounding environment is in an acceptable range. In a word, after the intended project is completed, the impact of Meishan Iron and Steel Company on surrounding environmental quality will be alleviated. (9) General conclusion on the assessment of the construction of the intended project The construction of the intended project complies with national industrial development policy, Nanjing urban master plan, Nanjing environmental protection plan and the requirement of environmental quality. The assessment index for pollutant discharge meets the requirement of up-to-standard discharge and total amount control. The site selected is basically feasible. Therefore, as long as the Product Matrix and Process Equipment Upgrading and Technical Transformation Project of Meishan Iron and Steel Company earnestly implements all kinds of pollution control measures set forth in report, and establishes and implements ISO14001 environmental management system, the construction of this project is feasible in terms of environmental protection. 8.5 Suggestions (1) In order to meet total amount control index, while the intended project is completed and put into production, the “pushing ahead old by new” environmental protection project shall be carried out. Meishan Iron and Steel Company shall work out practical and feasible control solutions and make active effort to implement them to ensure “three simultaineouses” acceptance inspection is carried out as per the time specified in the report. (2) By now, the reuse water plant of Benxi Iron & Steel Corporation has been built up. Reuse water and fresh water are mixed in the service reservoir and then supplied to each process step through one pipeline. The effect is good. In contrast, the supply of reuse water currently being designed by Meishan Iron and Steel Company is separated from the supply of fresh water. It needs two pipelines to supply water to each plant and has no advantage in management and construction cost, so we suggest Meishan Iron and Steel Company carefully study the approach of Benxi Iron & Steel Corporation, learn from strong points to offset its weakness and adopt more reasonable and economical water supply method. In addition, after treated in sewage treatment station, 74% of industrial water is reused. This

139

ratio can be further increased, thus further reducing the consumption of fresh water. (3) Ensure all phenol-cyanogen wastewater is treated to reach standard and then is reused without discharge. The reuse ways include BF slag flushing, sinter pelletization, ash flushing in power plant, and BF gas cleaning. Meanwhile, a buffer reservoir shall be built to cope with emergent equipment failure. When it is used to flush slag and ash, the sump and ash flushing tank should be seepage and leakage resistant to avoid soil and underground water pollution. (4) Among the existing facilities, 2×130m2 sintering machines and 2×1250m3 BFs have been in service for more than 30 years. They are aged and near to the end of their life, have such problems as low production efficiency, high energy consumption and backward environmental protection facilities and can’t adapt to the requirement of cyclic economy and sustainable development. For this reason, it is suggested to reasonably eliminate them in the “11th Five-Year Plan” period and develop the production facilities for pre-ironmaking system of Meishan Iron and Steel Company towards the directions of scale, intensiveness and efficiency to make the configuration of pre-ironmaking system more reasonable. (5) In the area within the sanitation protection distance of this project and beyond the boundary of Meishan Iron and Steel Company, effort shall be made to prevent the unapproved construction of residential points, or purchase the residence by Meishan Iron and Steel Company and use the area for greening and landscaping or as reserve land. (7) It is suggested that Nanjing Environmental Protection Bureau exercises strict environmental supervision and examination on Meishan Iron and Steel Company and ensure the control measures determined in the report are implemented on schedule.

140