Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, District

CONTENTS

CHAPTER – 1 EXECUTIVE SUMMARY – ENGLISH & TAMIL CHAPTER – 2 DETAILED PROJECT DESCRIPTION 2.1. Introduction 2-1 2.2. Background of the Project 2-1 2.3. Profile of Coimbatore Corporation 2-3 2.4. Governance 2-4 2.5. Objective of the project 2-4 2.6. Rationale of the study 2-4 2.7. Proposed Project Scheme Details 2-5 2.8. Examination of Alternative Routes 2-12 2.9. Work Force Requirements 2-12 2.10. Applicable Legal and Policy Framework 2-13 2.11. Social Safeguards Framework 2-15 CHAPTER – 3 APPROACH AND METHODOLOGY 3.1. Objective of Social Impact Assessment Study 3-1 3.2. Approach and Methodology 3-1 3.3. SIA team 3-2 3.4. Socio economic profile of the project area 3-4 3.5. Stakeholder Analysis 3-5 3.6. Transect walk made along the proposed water supply scheme 3-7 alignment 3.7. Focus Group Discussion (FGD) 3-9 3.8. Socio Economic Survey 3-13 3.9. Social Screening and Categorization 3-22 3.10. Social categorization of projects 3-23 3.11. Impact identification & mitigation measures 3-23 3.12. Public consultation and Disclosure 3-30 3.13. Compensation and settlement for PAPs 3-30 3.14. Institutional Arrangements 3-32 3.15. Gender Issues 3-34 3.16. Grievance Redress Mechanism (GRM) 3-35 ANNEXURE I – Alignment Map ANNEXURE II - Proforma for Socio Economic Survey ANNEXURE III – Focus Group Discussion report ANNEXURE IV – Details of Village wise project affected people

WAPCOS Limited i

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project,

LIST OF TABLES 2.1. Salient Features of Coimbatore Corporation 2-4 2.2. Quantity of water supplied from the proposed Scheme 2-9 2.3. Private / Poromboke Land Requirement for Pillur Water 2-11 Supply project 2.4. Work Force Requirement 2-12 2.5. List of acts and policies applicable 2-13 3.1 Study Team for SIA 3-2 3.2 The list of stakeholders and how they are associated drinking 3-6 water pipe line project 3.3 Methods used in the study 3-6 3.4 Summary schedule of Transit Walk 3-8 3.5 Village wise % of survey samples 3-13 3.6 Details of household heads 3-14 3.7 Educational Qualification of PAPS 3-16 3.8 Details of Number of Family Members 3-17 3.9 House Type of PAPS 3-18 3.10 Annual Income of PAPS 3-20 3.11 Perception about impact due to the lose off the land 3-21 3.12 Perception about how the project impact the community 3-21 3.13 Social Categorization of Projects 3-23 3.14 Activities and potential impacts and suggested mitigation 3-24 measures 3.15 Table Details of land loss and number of PAPs 3-27 3.16 Table Details of tree crops and other tree species loss and PAPs 3-29 3.17 Implementation Arrangement – Roles and Responsibilities 3-34

LIST OF FIGURES 2.1. Coimbatore Corporation Map showing added areas 2-2 3.1 Village wise total number of Households and Population 3-3 3.2 Constitutional Status of PAPs 3-15 3.3 Age structure of PAPs 3-15 3.4 Primary Occupation of Land Owners 3-17 3.5 Land holding of PAPs 3-19 3.6 Organization Chart of TWAD 3-33

WAPCOS Limited ii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

CHAPTER- 1 Executive summary Detailed Project description

In the G.O Ms.No.33, Municipal Administration & Water Supply (Corp.2(2) Department dated 20.02.2019, the Government have accorded administrative sanction for acquiring lands measuring an extent of 174.42 acres (or) 657098.42 Sq.mts. covering 7 villages, namely, Naickenpalayam, Kudalur North, Kudalur South, Narasimanacikenpalayam, Gurudamplalayam, Pannimadai and Nanjudapuram in Coimbatore North Taluk and two villages namely, Thekkampatti and Marudur in of Coimbatore District under the provisions of the RFCTLARR ACT 2013 for the proposed Pillur Water Supply Project by Corporation of Coimbatore. The objective of this assignment is to implement the proposed Water Supply Scheme to achieve effective drawal, treatment and conveyance of water to the upgraded Storage and Distribution System in the Corporation and provide a percapita supply of 135 LPCD potable water supply as required for corporation Status. The cost of the proposal for Water supply Improvement Scheme to Expanded Coimbatore Corporation including newly merged areas with River Bhavani as source works is Rs. 740.15 Crore (TWAD Board schedule of rates for the year 2017-2018 has been adopted) to install and Rs. 20.17 Crore (For first year i.e. 2020) to maintain as finalized by AMRUT/ TNUIFSL/ADB as per DS Finance Norms. The scheme has been administratively sanctioned vide G.O Ms. No:50 / MA & WS(MA2) DEPT Dated 21.05.18. for Rs.740.15 Crore with the following funding pattern 1. GOI Share under AMRUT - Rs. 214.27 Crore. 2. GOTN Share under AMRUT - Rs. 129.86 Crore. 3. ULB Share under OWN fund - Rs. 74.02 Crore. under ADB - Rs. 322.00 Crore. Total - Rs. 740.15 Crore

WAPCOS Limited 1 - 1

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

The Municipality of Coimbatore was established in 1866, the city has registered the decadal growth rate of 49.20 % during the period 1971- 1981. This is attributed to the up gradation of Municipality to the status of Corporation in 1981, and it was the third in . Now the total extent of Coimbatore Corporation is 257.04 Sq.km. The population of the Corporation as per 2011 Census is 1617711.

Since, land is the basic capital for the establishment of the project, the criteria and basic considerations to select the route for the project and to undertake land acquisition was decided based on the field Inspection done for checking Feasibility of alternative alignment of Pillur III Scheme from Intake at Samayapuram to Pannimadai MST and the present alignment has been finalized.

Study and Methods The main objective of the Social Impact Assessment (SIA) study is to understand the adverse impact of the project to the population affected by the project implementation and to address the impacts. Also it helps to explore various options and to consider the best and acceptable option which has minimum or no impact. In the SIA process, consultation with major stakeholders and the local farming communities was undertaken.

The project area covers nine revenue villages, seven from Coimbatore north taluk and two from Mattupalayam taluk.

Stakeholder consultations were conducted at two levels, at the first level with the communities and local leaders during the field visits and at the second level meetings with the officials of the Coimbatore corporation, revenue department and TWAD Board to discuss about the project objectives, implementation plan, activities each department will carry out, time line and the outputs.

The project team made several field visits, during the first visit had meetings with the different stakeholders discussed and collected the details about the project, in the first visit conducted the transect walk along the alignment and in the subsequent visits the team members conducted nine FGDs and house hold survey (17% of the total PAPs) and

WAPCOS Limited 1 - 2

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District also finalized the Project affected persons list in each revenue village in consultation with the officials of revenue and survey departments.

Results of Focus Group Discussions  The main loss to the project affected people is mostly the agricultural land both irrigated and dry. The other properties people may lose are compound walls, bore wells, tree crops such as coconut areca nut, teak trees and a few other species. The other loss is the housing sites located in the lay outs (both approved and non- approved) in some villages.  Many of the project affected people expressed their concern that the alignment is going straight in the middle of the their lands and in the house sites and divides the land into two and are left with narrow strips on both sides, and this will make the lands unsuitable for agriculture and construct of new houses. Therefore requesting the department to acquire the entire land/plot and add in the compensation amount.  The Project Affected People say the compensation is going to be a one time payment for the permanent asset they are going to lose, a source for their livelihood, hence expecting a fair compensation an agreeable amount.  The project affected people expressed their concern about the possible delay in the payment of compensation; they want the payment to be made immediately after the land acquisition.  The amount of land they may lose in some of the small holders is more than 50% of the land they own. Hence, worried about the loss of income they get from the fields. These small holders are demanding the job opportunities created in the project so that the family is not affected by the land acquisition and benefitted by the Job.  There are a few women headed households going to lose their lands they mentioned that none of the family member are educated their only source for income is through agriculture, if the govt decides to take away the land the compensation should be fair and should help to improve their livelihoods.

WAPCOS Limited 1 - 3

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 Wildlife intrusion particularly elephants and destruction of crops is a big issue in the villages which are located close to the forest boundaries, the farmers are worried that sometimes the new road going to be laid may create an easy access to their fields.

 The local farmers expressed their worries with respect to taking water from the dam for drinking water this will result in decreasing of water storage level; thus may affect the ground water table of the surrounding areas.  They want the road built over the pipelines to be made open for public use.  Some of the project affected farmers said they are experiencing meetings fatigue; many meetings were organized in the past without sharing the right information and arriving any concrete conclusions.

Socio Economic Survey  The survey results show majority of the household heads are males (89.8%) only one tenth (10.2%) are the female household heads.  Constitutional status of the communities surveyed show that more than half (58.5%) of the PAPs are from Backward communities and nearly one fourth (22.0%) belonging to communities from Most backward category, 8.5% are from the two following Scheduled caste and the remaining 11.0% are from other communities.  Educational status of the PAPs as per the survey results, 12.7% of the PAPs are illiterates, the highest number is who studied up to secondary education (27.1%, this is followed by primary education 22.0%, some of the land owners are graduates (11.0%), professional degree holders (9.3%) post graduates (5.15%), and Diploma holders (4.2%) etc.  Primary occupation of the land owners, the survey results reveal that more than half of the lane owners (PAPs) are farmers (61.9%), 11.0% of the land owners are doing business, another 11% are working for private sectors, a small portion of the owners (6.8%) are earning their livelihood through working as daily wage labourers. 5.9% of the owners who are going to loss land is retired people from

WAPCOS Limited 1 - 4

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

the Government and private service. The remaining few categories are in negligible percentage.  Majority (66.9%) are living in pucca houses, most of the old houses are tiled, 17.8% and the remaining 15.3% are living in partially pucca and the remaining area tiled or asbestos roofed houses.  Majority (72.9%) have their own tap, 11.8% are depending on common tap and 11.0% have responded they get from their own tube wells, a small per cent (3.4%) get from the open wells. 89% have responded that they have their own vehicles (it includes different kind of vehicles) and 11.0% depends on public or private transport system.  About landholding details of the PAPs maximum percentage of farmers lose land are marginal holders (42.4%), next is semi medium category (20.3%). More or less the same percentage of farmers from small holders (16.1%) and medium size holder (12.7%) lose their lands, and a small number of PAPs are big farmers (2.9%). Remaining 5.9% are the owners of house sites and they involved in different kinds of occupations.  As per the survey results only less than half of the respondents (43.2%) own livestock (which include, cattle, sheep, goat and poultry) and remaining households own no livestock.  Regarding the annual income of the households of the PAPs, the results reveal that the highest percentage PAPs (19.5%) earns from 3 lakh to 5 lakh, the next in the order families earn is 50 thousand to 75 thousand, 11.0% of the PAPs come under this category, a little lesser percentage of 10.2% is reported by three groups (75 thousands to 1 lakh, 1.5 lakh to 2.0 lakh and above 10 lakh). All remaining groups with different amount of annual income are reported as less than 10%.  Regarding willingness to provide the land for the project the survey results reveal except one PAP all other remaining (99.2%) have responded positive, considering the objective of the project they cannot say no to the government for implementing the project.

WAPCOS Limited 1 - 5

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 PAPs perception about the impact they face due to the land loss varies, the highest percentage of 36.3% feel their income will come down and will affect the livelihood. Next category 19.5% of PAPs understanding is that simply they will lose their traditional asset. 14.4% worried that the remaining land will be meagre, a narrow strip and become unfit to do farming. Some of the PAPs (10.2%) are unable to form any opinion about the impact due to land loss.  PAPs from the villages located close the source from where the water will be pumped expressed their concern that taking water will reduce the storage and subsequently results in the depletion of the ground water in the surrounding areas.

Based on the outcome of SIA, it is found out that the project involves acquisition of agricultural lands of local farmers and in some areas the house sites. Implementation of this project makes around 477 farmers partially lose their farming lands and total area estimated is 46.02.71 Ha. In the case of house sites it is enumerated 211 owners will lose the land and the area is 3.48.51Ha land. The total amount of land people lose is less than 20 % of the total amount of land and tree crops (productive asset) they owned; hence this project is categorized as S2.

Impacts and mitigation measures

The general impacts have been assessed from field visit observations, FGDs, and the socio economic survey conducted. The possible impacts at various stages of the project such as prior initiation, during implementation and post project period have also been assessed and mitigation measures are suggested.

Land acquisition (a portion of the agricultural field) will be the main activity; a fair compensation will be made for the loss, hence will not create any permanent impact. In the cases of land fragmentation and the owners feel it will be difficult to useful of agriculture, it is expected the government can acquire these narrow pieces and add the compensation. Similarly in the case of house site acquired from the PAPs.

Due to land loss the livelihood of the most vulnerable sections like women headed households, or small holders from vulnerable categories may impacted in a considerable

WAPCOS Limited 1 - 6

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District way, members of these most vulnerable families can be considered if any job created in the project.

Construction of road over the pipeline may create easy access to the agricultural fields for the wildlife; this can be mitigated with digging trenches with the support of the forest department.

Public consultation is planned in two places one in each taluk during the second week of April 2020, during the consultation the results of the SIA will be presented to the public and the feedback can be used as constructive inputs to minimize the damage and loss.

The land owners are entitled to legal compensation for land that they will lose as per the “Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013’. The final compensation amount for the land acquisition and structures will be determined by the Competent Authority.

Institutional arrangements and Grievance Redress Mechanism (GRM)

The main objective of the institutional arrangement is to ensure quality assurance and safety structures to apply social safeguards. The present institutional arrangements in TWAD for implementation of the Social Safeguards measures in the 9 villages under Pillur Water Supply project has been reviewed and it is felt that the existing arrangements need to be strengthened to meet the requirements of general public and project affected families which includes a social expert. The institutional arrangements for implementation of different project components would be made such that participation of different stakeholder’s particularly primary stakeholders and women are ensured. The project shall be implemented by TWAD and coordinated by Revenue Department, Public Works Department and City Municipal Corporation. All the departments shall report to District Collector, Coimbatore to review the progress of the project at regular intervals and shall provide strategic directions, guidance on policy matters and resolve conflicts, if any.

WAPCOS Limited 1 - 7

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

It has been observed in general during implementation of project vulnerable category like women farmers suffer most. Therefore project implementation unit should ensure that proper and adequate care has taken to minimize adverse impacts on women farmers.

GRM is an essential component of any project administration, particularly if the project involves project affected families and the local communities with diverse socio economic backgrounds and have as the major stakeholder. The GRM will be in place for addressing project related grievances. The GRC will receive and redress grievances and complaints that are formally brought to the GRC in writing by the persons and/or group of persons who have a grievance because of the Program’s adverse impact on him/her and them. The grieved/complainant will have the right to seek legal redress through the judicial system if he/she or they are not satisfied with the decisions of the GRC.

WAPCOS Limited 1 - 8

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

-1

-

’ RFCTLARR

-

WAPCOS Limited 1 - 9

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

-

- -

-

1. - -

2. - -

3. -

- -

-

WAPCOS Limited 1 - 10

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

-

- -

-

-

WAPCOS Limited 1 - 11

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

WAPCOS Limited 1 - 12

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

-

WAPCOS Limited 1 - 13

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

.

WAPCOS Limited 1 - 14

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

WAPCOS Limited 1 - 15

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

WAPCOS Limited 1 - 16

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

-

WAPCOS Limited 1 - 17

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

WAPCOS Limited 1 - 18

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 -

WAPCOS Limited 1 - 19

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

-

WAPCOS Limited 1 - 20

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 SIA)-

WAPCOS Limited 1 - 21

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

,

,

.

-

WAPCOS Limited 1 - 22

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

WAPCOS Limited 1 - 23

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

(Institutional Arrangement and Grievance Redress Mechanism)

WAPCOS Limited 1 - 24

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

GRM)

WAPCOS Limited 1 - 25

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

WAPCOS Limited 1 - 26

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

CHAPTER -2 DETAILED PROJECT DESCRIPTION

2.1 Introduction

Coimbatore City Municipal Corporation is one of the major Corporations in Tamil Nadu. Coimbatore is the District Headquarters of Coimbatore District with a total population of 16.18 Lakhs (2011 census) and spread over an area of 257.04 sq.km. As per the Government Notification issued with regard to Delimitation Act, vide G.O. Ms. No.49/Election Dept./dated 22-2-2011 and G.O Ms. No.72/Election Dept./Dt.12-05- 2011, the erstwhile Kurichi, Kuniamuthur and Kavundampalayam Municipalities, 7 Town Panchayats viz. Chinnavedampatty, Kalapatti, Saravanampatti, Vellakinaru, Thudiyalur, Vadavalli and Veerakeralam and Vilankurichi Village Panchayat were added to Coimbatore Corporation with an extent of 151.44 Sq.Km adding to the already existing area of 105.60 Sq.Km making the total Corporation area to 257.04 Sq.Km. Fig-2.1 shows the Coimbatore corporation with added areas. Among the 100 Wards in the Expanded Coimbatore Corporation, 40 Wards are located in the newly merged areas. Since these added areas were originally Municipalities / Town Panchayats / Village Panchayat the existing per capita supply is less than 135 LPCD as required for corporation Status, subsequently which requires additional quantity of water.

2.2 Background of the Project

This project is to provide the additional requirement of water from River Bhavani by pumping the water from the river through head works and acquiring / alienating land of 15m wide along the proposed alignment for the pumping main, Booster stations, Water treatment plant, Service reservoir and access roads.

In the G.O Ms.No.33, Municipal Administration & Water Supply (Corp.2(2) Department dated 20.02.2019, the Government have accorded administrative sanction for acquiring lands measuring an extent of 174.42 acres (or) 657098.42 Sq.mts. covering 7 villages, namely, Naickenpalayam, Kudalur North, Kudalur South, Narasimanacikenpalayam, Gurudamplalayam, Pannimadai and Nanjudapuram in Coimbatore North Taluk and two

WAPCOS Limited 2 - 1

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District villages namely, Thekkampatti and Marudur in Mettupalayam Taluk of Coimbatore District under the provisions of the RFCTLARR ACT 2013 for the proposed Pillur Water Supply Project by Corporation of Coimbatore.

Saravanampatti

Kalapatti Chinna

Thudiyalur vedampatti

Vilankurichi

Goundampalayam

Vadavalli Old Corporation

Veerakeralam

Kurichi Kuniyamuthur

Fig 2.1: Coimbatore Corporation Map showing added areas

Pursuant to this, the District Collector, Coimbatore has requested to appoint SIA Agency so as to study and prepare Socio, Economic and Cultural profile of the affected area under the Right to Fair Compensation and Transparency in Land acquisition, Rehabilitation and Resettlement Act, 2013 (Central Act 30/2013) to Principal Secretary, Commissioner of Revenue Administration & Commissioner of Land Administration, GoTN.

In continuation the Principal Secretary, Commissioner of Revenue Administration & Commissioner of Land Administration, GoTN entrusted WAPCOS LIMITED as SIA agency to conduct the Social Impact Assessment Study.

WAPCOS Limited 2 - 2

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

2.3 Profile of Coimbatore Corporation

Coimbatore City is located in Western Tamil Nadu. The Municipality of Coimbatore was established in 1866 according to the Town Improvements Act of 1865 with Sir Robert Stanes, a renowned industrialist as its first Chairman. The city has registered the decadal growth rate of 49.20 % during the period 1971- 1981. This is attributed to the up gradation of Municipality to the status of Corporation in 1981, and it was the third in Tamil Nadu., whereby additional areas were included in its jurisdiction. Coimbatore also known as Kovai, is the second largest city and urban agglomeration in the Indian state of Tamil Nadu, after Chennai and the sixteenth largest urban agglomeration of . Coimbatore is the fourth largest metropolis in South India. It is one of the fastest growing tier-II cities in India and a major textile, industrial, commercial, educational, information technology, healthcare and manufacturing hub of Tamil Nadu well connected with major cities and towns of India by Highways, Railways and Airways and also abroad. Other important industries include software services. It is the capital city in the region and is often referred to as the Manchester of South India. The city is located on the banks of the surrounded by the Western Ghats and is administered by the Coimbatore City Municipal Corporation. In 2012, the Corporation won the Best Corporation Award in Tamil Nadu. Coimbatore City Corporation has been adjudged the best among 100 corporations selected from across the country by Skoch, a Gurgaon- based independent group dealing with social economic issues. Coimbatore City is now emerging as a major industrial, textile and Information Technology hub of Tamil Nadu. Major National and International Computer companies are planning to start their software parks at Coimbatore in the near future. Thereby job opportunities and population are expected to increase manifold. In 1866, Coimbatore was constituted as a Municipal town with an area of 10.88Sq.Km. Coimbatore Corporation was upgraded from special grade Municipality to Corporation in the year of 1981 spreading over an area of 105.60 Sq.Km. Now the Corporation area has been extended as per the Tamilnadu Government order with the inclusion of local bodies adjacent to Coimbatore. The extended Corporation area is effective from 2011. Now the total extent of Coimbatore Corporation is 257.04 Sq.km. The population of the Corporation as per 2011 Census is 1617711.

WAPCOS Limited 2 - 3

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

2.4 Governance

Coimbatore Corporation consists of 100 wards and is headed by a Mayor who presides over a Deputy Mayor and 99 other councilors who represent the wards. The Mayor is elected directly through a first past the post voting system and the deputy mayor is elected by the councilors from among their numbers. For administrative purpose the Coimbatore Corporation is divided into five zones namely North, South, East, West, Central headed by a chairman. The Salient Features of Coimbatore Corporation are detailed in Table 2.1. Table 2.1: Salient Features of Coimbatore Corporation. No. Aspect Description. 1. Location: Latitute Latitude: 10o 58’00” N Longitutde & Longitude: 76o 58’ 00”E 2. Neighbouring District. North The Nilgris West Kerala State East Erode South Dindigul 3. Total area of Coimbatore 257.04 Sq.Km Corporation 4. Total Wards 100

2.5 Objective of the project

The objective of this assignment is to implement the proposed Water Supply Scheme to achieve effective drawal, treatment and conveyance of water to the upgraded Storage and Distribution System in the Corporation and provide a percapita supply of 135 LPCD potable water supply as required for corporation Status.

2.6 Rationale of the study

It has been alleged that development projects emphasize only on the productive issues and ignore or neglect justice issues. Any policy towards displacement and resettlement should, therefore, take into consideration as well the “social cost” and “human costs”

WAPCOS Limited 2 - 4

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District rather than confining to mere payment of compensation. That the principles of justice and equality should be equally made applicable more so in the case of scheduled castes and scheduled tribes particularly, is already established by law and the constitution. Taking the points into consideration, RFCTLARR Act 2013 mandates to conduct Social Impact Assessment study prior to acquisition of land for any public purpose. The present SIA is undertaken for the purpose of land acquisition required for Pillur Water Supply project wherein the alignment passes through 9 villages under two Tehsil of Coimbatore district to meet the requirements of the said Act.

2.7 Proposed Project Scheme Details 2.7.1 Source The source is River Bhavani. The location of the Head works is at the upstream of EB Barrage I at Samayapuram located 5 KM upstream of Mettupalayam Town. The Senior Hydrologist, TWAD, Head Office Chennai vide Lr No 113/AHG3/WSIS Coimbatore Corporation / HG/2016/dt 29.6.2017 has recommended the location of Head Works at Murugayyan Parisalthurai with Co-ordinates 11o18’16.84”N, 76o53’47.115”E.The FRL at Barrage I is 308.50 m which will hold water for 9 m depth near the Barrage. As per the discussion with the TANGEDCO officials during the joined inspection of the Barrage I, it was ensured that maintaining a Storage depth of 7 m i.e. at level 306.50 m at Barrage I will assure the required quantity of water for the proposed Scheme. Necessary agreement between Coimbatore Corporation and TANGEDCO has to be made assuring to maintain the required level at Barrage I for drawal of 318.17 MLD for the proposed Scheme, before taking up the implementation of the Scheme.

2.7.2 Head Works

Intake Chamber (10m x8m) in river bed with Sluice Gate & Screen ,Leading pipe of 1626 mm -2 nos-2m length, Forebay 15 x 10 m along the River Bhavani at Bhavani Barrage I and pump house of Rectangular in shape (36 m x 9 m) at bank of river are proposed near Muruggayan Parisalthurai. River Bed Level : 301.45 m Ground Level : 308.20 m

WAPCOS Limited 2 - 5

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

MFL : 309.20 m Base Slab level : 297.542 m FVL of P sets : 298.042 m Floor Level of Pump Room : 313.00 m

Structures in headwork’s Internal Roads & Drains at Pump house, Compound wall of length 180 m, Dewatering Arrangement, Transformer Yard, Coffer Dam for 120 m of length, canal wall, Control room, Security Building and Retaining wall of length 60 m. Headwork Components are provided above the MFL by filling the excavated surplus earth from sump cum pump house area.

Raw Water Pumpset It is proposed to install of 6 Nos. of Vertical Turbine Pumpset for 23 hours pumping ( 4 nos to run in parallel and 2 Nos as standby) each having duty 32300 lpm (Intermediate Stage) against the head of 121 m to pump water from the Intake Well to Water Treatment Plant near Maruthur village at Thandiperumal Palayam, proposed at a distance of 16500 m from Headworks.

Staff Quarters It is proposed to construct 1 No of B-Type and 1 No of C-Type quarters (Twin) having ground floor and first floor.

Control Room It is proposed to construct a Control room consisting of LT Panel room of size 12.0 m x 7.0m and HT Panel room of size 9.12 m x 6.0m.

Control room and Staff quarters and are proposed in site measuring 50 m x 30 m in SF No 900 for which land (0.40 acres) has to be acquired.

2.7.3 Raw Water Pumping Main Raw water pumping main will be of 1829 mm dia MS pipes, 16 mm thickness for a length of 1500 m & 1829 mm dia MS pipes, 14.2 mm thickness for a length of 15000

WAPCOS Limited 2 - 6

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District m upto Water Treatment Plant. Total Raw Water Pumping Main length is 16500 m. The proposed Raw water main alignment will be adjacent and parallel to the HT Power Transmission Line from LS 7500, near Nellimalai at Dasanur upto Water Treatment Plant near Kattan Hills from LS 0 to LS 16500 m. The Raw water main from Head works to the Water Treatment Plant proposed at Maruthur in the outskirts of Coimbatore Corporation will be of 1829 mm, 16 mm/14.2 mm thickness MS pipes of 16.50 Km. Considering the operation and maintenance, construction of valve pits and thrust blocks of large sizes it is not feasible to lay pipes of 1829 mm size in the existing public roads. Hence it is proposed to acquire/alienate land of 15 m wide for the entire 16.50 KM length to lay the clear water pipelines and for service road along the proposed alignment.

2.7.4 Treatment Plant The proposed treatment plant of capacity 178.30 MLD capacity for Intermediate Stage is proposed to be constructed in Maruthur Village near Kattan Hills in SF Nos 455,454,543 & 544 in private and SF No 496 in Vari Porambokku (nearly 20 acres) land measuring 400 x 350 m of total extent of 35 acres which includes the land earmarked for construction of water treatment plant for the ultimate stage. The land has to be acquired for construction of Water Treatment Plant. The Construction of Treatment Plant will be based on DBOOT system for 178.30 MLD.

Staff Quarters It is proposed to construct 2 Nos of A-Type, 2 Nos of B-Type and 2 Nos of C-Type quarters (Twin) having ground floor and first floor.

2.7.5 Clear Water Pumpsets It is proposed to install of 6 Nos. of Vertical Turbine Pumpset of 23 hours pumping (4 nos to run in parallel and 2 Nos as standby) each having duty 31360 lpm (Intermediate Stage) against the head of 129 m to pump water from the clear water sump to the Master Storage Tank at Pannimadai, proposed at a distance of 16960 m from Water Treatment Plant.

WAPCOS Limited 2 - 7

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

2.7.6 Clear Water Main The Clear water main from the Water Treatment Plant upto Master Storage Tank proposed at Pannimadai in the outskirts of Coimbatore Corporation will be of 1829 mm, 17.5 mm thickness MS pipes of 480m, and 1829 mm, 14.2 mm thickness MS pipes of 16480 m. Total Length of Clear water main is 16.960 Km. Considering the operation and maintenance, construction of valve pits and thrust blocks of large sizes it is not feasible to lay pipes of 1829 mm size in the existing public roads. Hence it is proposed to acquire/alienate land of 15 m wide for the entire 16.90 Km length to lay the clear water pipelines and for service road along the proposed alignment. The proposed Clear Water main from Water Treatment Plant to Master Storage Tank, i.e. LS 0 m to LS 16960 m, the pipeline will be laid through the proposed tunnel (900 m length) to cross the Kattan Hills at distance of 1160m from WTP. From the Kattan Hills the alignment is proposed parallel to the HT Power Transmission line upto Kathirnaickenpalayam Village. From Kathirnaickenpalayam it proposed to lay the pipeline along Lakshmi Nagar upto the proposed Master Storage Tank at LS 16960 m in Pannimadai.

2.7.7 Tunnel for Clear Water Pipeline The Clear water Main has to cross the Kattan Hills. It is proposed to lay the pipe line through a tunnel to be constructed 30 m from the existing Clear water gravity Tunnel of Pillur I Scheme. The tunnel will be of 0.9 Km length. The width of the tunnel has been arrived as 8 m to lay the proposed Clear water Main of 1829 mm MS pipes and the existing Clear water Main of 1500 mm MS pipes of the Dedicated WSS to Coimbatore Corporation which will be delinked from the existing tunnel. Necessary space in the tunnel for laying additional pipes in future has been proposed and the size and levels have been finalized during the meeting held at Coimbatore Corporation with the Corporation Officials and the Consultants for the tunnel work. The entry and exit levels of the proposed tunnel will be kept the same as that of the existing tunnel to ensure the original hydraulic gradient in existing pipe line of the Dedicated WSS beyond the tunnel. Construction of Tunnel will be based on DBOOT system and the cost of the same is included in DPR.

WAPCOS Limited 2 - 8

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

2.7.8 Master Storage Tank (MST) The Expanded Coimbatore Corporation has been divided into seven major distribution zones under the proposed 24x7 Water Supply Project prepared by TWIC. The Service Reservoirs in each of these Zones will be commanded by Master Balancing Reservoirs (MBR), one in each Zone. The contour of the Expanded Coimbatore Corporation varies from 485.00 m to 368.00 m. Since the location of these MBRs are located at various levels, in order to avoid more drawal in MBRs located in low contours it is proposed to construct a Master Storage Tank at the highest elevation at Pannimadai at the outskirts of Coimbatore Corporation from where the MBRs will be fed by gravity through Feeder Mains. The Master Storage tank of 2 hours detention time capacity will act as a Balancing Reservoir for all the six MBRs. The Master Storage tank will be of rectangular underground reservoir, Two Numbers 73.00 Lakh litres capacity each with two compartments of 25m x 45m and storage depth 3.30 m & total depth including scour depth & free board of 3.75 m is now proposed for the Ultimate quantity. An extent of 5 acres of land in S.F. No. 674 has to be acquired for the construction of MST. The construction of Master Balancing reservoirs in the added areas has been included in the DPR for Improvements to Distribution System in added areas.

2.7.9 Feeder Mains from Master Storage Tank to Balancing Reservoirs The quantity of water to be supplied from the proposed Scheme for the Intermediate and Ultimate Stages after deducting the supply from other sources as furnished in Table 2.2 is as follows. Table 2.2: Quantity of water supplied from the proposed Scheme Quantity in litres Zone MBR Location Wards Intermediate Ultimate Stage Stage 10-15, 20-25, Bharathi Park 44, 45, 49-53, 1 82189106 127181098 Existing MSR 55, 70-73, 76- 81, 83-85 37-41, 46-48, Ramakrishnapuram 2 54, 56-69, 74, 32988954 76887907 Existing Old MSR 75, 82, 86 Pillayarpuram 3 94-100 7526043 18094470 Proposed MBR

WAPCOS Limited 2 - 9

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Quantity in litres Zone MBR Location Wards Intermediate Ultimate Stage Stage Press Enclave 4 87-93 5145024 13200876 Proposed MBR Kavunampalayam 5 5-9,16-19 11667971 25371414 Existing Sump Valarmathy Nagar 1-4, 26-33, 6a 31050354 41190210 Proposed MBR 42,43 Ramakrishnapuram 6b Existing New 31-36 2537033 6972508 MSR 173104485 308898483 Total Clear water 173.10 MLD 308.90 MLD

It is proposed to provide two separate Feeder mains with separate outlets from the MST. Feeder Main I will convey the quantities of the MBRs located at Pillayarpuram and Press Colony. The length of Feeder main I is 33.25 KM, comprising 813 mm , 7.1 mm/ 711 mm, 6.3 mm MS pipes and 600 mm/350 mm DI K9 pipes. Feeder Main II will feed the proposed MBRs located in Valarmathy Nagar, Bharathi Park, Ramakrishnapuram (Old and New MSRs proposed under 8 added areas). The quantity for Kavundampalayam MBR from the proposed Scheme will be made available in Ramakrishnapuram New MSR (proposed under 8 added areas). The Feeder main from Ramakrishnapuram MSR to Kavundampalayam Sump has already been included in the DPR for improvements to Distribution System in 3 added areas. The length of the proposed Feeder Main II is 24.52 Km comprising 1219 mm, 10 mm thickness, 1016 mm, 8.8 mm thickness, 914 mm, 8 mm thickness, MS pipes and 600 mm DI K9 pipes.

2.7.10 Requirement of Land

For the proposed Pillur Water Supply project 174.42 acres of Private / Poromboke land will be required. This land will be affected in 9 revenue villages under two Tehsils of Coimbatore District. Land requirement for the whole project is summarized in the Table 2.3.

WAPCOS Limited 2 - 10

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Table 2.3: Private / Poromboke Land Requirement for Pillur Water Supply project Sl.No Component Extent Type of Land 1. Head works- For Control Room, 0.40 acres Private Quarters 2. Raw Water Main 15 m wide – 16.50 Private / KM 59.26 acres Poromboke

3. Water Treatment Plant 35 acres Private / Poromboke 4. Clear water Main 15 m wide -16.96 KM Private / – 61.05 acres Poromboke 5. Booster stations 1 and 2 2 x 5 acres each Private 6. Master Storage Tank 5 acres Private

7. Approach Road for Master 15 m wide – 1.1 KM Private Storage Tank from Varapalayam 3.71 acres Road Total 174.42 acres

2.7.11 Cost The cost of the proposal for Water supply Improvement Scheme to Expanded Coimbatore Corporation including newly merged areas with River Bhavani as source works is Rs. 740.15 Crore (TWAD Board schedule of rates for the year 2017-2018 has been adopted) to install and Rs. 20.17 Crore (For first year i.e. 2020) to maintain as finalized by AMRUT/ TNUIFSL/ADB as per DS Finance Norms.

2.7.12 Funding Pattern The scheme has been administratively sanctioned vide G.O Ms. No:50 / MA & WS(MA2) DEPT Dated 21.05.18. for Rs.740.15 Crore with the following funding pattern 4. GOI Share under AMRUT - Rs. 214.27 Crore. 5. GOTN Share under AMRUT - Rs. 129.86 Crore. 6. ULB Share under OWN fund - Rs. 74.02 Crore. under ADB - Rs. 322.00 Crore. Total - Rs. 740.15 Crore

Also an amount of Rs. 20.17 crore has been administratively sanctioned towards annual maintenance for the first year and it has been mentioned that it will be borne by the Local

WAPCOS Limited 2 - 11

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District body. After completion of the scheme and the Contractor’s maintenance for five years, the scheme will be handed over to Coimbatore Corporation for further maintenance.

2.8 Examination of Alternative Routes The proposed project is a Drinking water supply scheme. Since, land is the basic capital for the establishment of the project, the criteria and basic considerations to select the route for the project and to undertake land acquisition was decided based on the field Inspection done for checking Feasibility of alternative alignment of Pillur III Scheme from Intake at Samayapuram to Pannimadai MST and the present alignment has been finalized based on the following reasons.

1. Alternate alignment for laying Pipes was tried along Mettupalayam city road, the Village panchayat has very narrow lanes along Residential packets. If suggested will lead to evacuvation of many houses 2. Already both side of NH road from Mettupalayam to Narasimanaickenpalayam has Drinking water Feeder main - KV Scheme and Pillur I (TWAD). 3. Provision and Maintenance of Air valve and Scour valves along NH road will be very difficult. 4. Any further development scheme pipes can also be accommodated in proposed alignment in Future without much Hinderance

2.9 Work Force Requirements

The present water supply scheme requires man power for maintenance of Head works, Raw Water main, Water Treatment Plant, Clear Water Main, Feeder Mains and Master Storage Tank. A total of 26 technical / non-technical staff are required for the project maintenance apart from the work force required during execution period. The details of work force requirement are given in Table 2.4. 2.4: Work Force Requirement Sl.No Description Quantity Head Works 1. Electrical Superintendent 1 No

WAPCOS Limited 2 - 12

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

2. Electrician Grade II 3 Nos 3. Maintenance Assistant 1 No Raw Water Main 1. Fitter 1 No Water Treatment Plant 1. Electrical Superintendent 1 No 2. Electrician Grade II 3 Nos 3. Maintenance Assistant 1 No 4. Fitter Bed Operator 3 Nos 5. Chemist 1 No 6. Laboratory Assistant 1 No 7. Gardener 1 No Clear Water Main 1. Fitter 1 No Feeder Mains 1. Fitter 2 Nos 2. Tum Cook 1 No 3. Maintenance Assistant 1 No Master Storage Tank 1. Maintenance Assistant 3 Nos 2. Gardener 1 No

2.10 Applicable Legal and Policy Framework Applicable acts, notifications and policies relevant in the context of the project are discussed below. The project authority will ensure the project activities implemented are consistent with the national, state, local regulatory /legal framework. The list of Acts and Policies applicable are given in Table2.5. 2.5: List of acts and policies applicable S.N Acts and Policies Relevance to this project Applicability 1. National The national policy provides a reference to Applicable Rehabilitation and the social part of the assessment. In order to Resettlement provide a framework for the R&R process in policy (NRRP), projects. This assessment provides a list of 2007 entitlements for project affected persons and families. 2. Right to Fair The act has been framed for the upliftment Applicable Compensation of the project affected families, which

WAPCOS Limited 2 - 13

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

S.N Acts and Policies Relevance to this project Applicability and Transparency provides a reference for the social in Land Management Framework. It also majorly Acquisition, deals with the social assessment of the Rehabilitation and people affected by the Government projects. Resettlement Act, Three broad categories of economic and 2013 social impact that would be mitigated are: Loss of assets, homestead and land and other fixed assets, loss of income or means of livelihood, and indirect group oriented impacts due to loss of common property resources 3. Tamil Nadu Ensure that all PAPs will be resettled and Applicable (Resettlement rehabilitated with the aim of improving and their livelihoods and standards of living or Rehabilitation) at least restored to earlier levels and in Policy for such a manner that PAPs have a share in Involuntary project benefits. When PAPs lose Resettlement land/structures and will be displaced and/or under the Tamil economically affected adversely, detailed Nadu Urban planning will be made along with Development implementation arrangements in an Project operational Resettlement Plan. 4. Ancient This act will be applicable, only if any of Not Monuments and the projects is in proximity to any Ancient Applicable Archaeological Monument, declared protected under the act. sites and Remains 1958 5. The Right to An Act to provide for setting out the Applicable Information Act practical regime of right to information for

WAPCOS Limited 2 - 14

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

S.N Acts and Policies Relevance to this project Applicability 2005 citizens to secure access to information under the control of public authorities, in order to promote transparency and accountability in the working of every public authority, the constitution of a Central Information Commission and State Information Commissions. Subject to the provisions of this Act, all citizens shall have the right to information. And every public authority have to maintain all its records duly catalogued and indexed in a manner and the form which facilitates the right to information under this Act 6. National Policy The policy advocates for equal access to Applicable for Empowerment participation and decision making of women of Women, 2001 in social, political and economic life of the nation and mainstreaming a gender perspective in the development process. The project shall provide equal access and opportunity to women in employment, remuneration, occupational health and safety, social security etc.

2.11 Social Safeguards Framework It aims to promote environmentally sound, socially acceptable and economically viable urban infrastructure projects. It is believed that each project will improve the living standards of the people and the quality of environment in and around projects location. Environment: Environmental soundness by conserving natural resources, preserving biodiversity and ecological equilibrium; minimizing release of polluting wastes and

WAPCOS Limited 2 - 15

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District integrating mechanisms within projects to maintain and enhance environmental quality of project locations.

Social: Addressing legitimate concerns of relevant stakeholders, especially project affected persons; Avoiding or minimizing resettlement and rehabilitation due to land acquisition and transfer of government land under different tenure system through appropriate technical and management measures; Ensuring appropriate resettlement and rehabilitation of project affected persons irrespective of legal status with a view to provide sustainable livelihood options that at least restore, if not improve, their standard of living; Protecting marginalized and vulnerable groups, including the economically and socially disadvantaged; and Minimizing health and safety hazards (TNUIFSL, 2006: ix). The basic objective of the social safeguards policy is to mitigate the social adverse impact to the population affected by the project implementation. This policy also emphasizes that the involuntary resettlement will be avoided and minimized by exploring different options. The broad categories of economic and social impacts that would be mitigated are: a) Loss of land and assets b) Loss of shelter or homestead lands, c) Loss of income or means of livelihood d) Loss of access to productive resources, shelter/residences e) Loss of collective impacts on groups such as loss of community assets, common property resources and others.

WAPCOS Limited 2 - 16

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

CHAPTER 3 APPROACH AND METHODOLOGY

3.1 Objective of Social Impact Assessment Study The main objective of the Social Impact Assessment study is to understand the adverse impact of the project to the population affected by the project implementation and to address the impacts. Also it helps to explore various options and to consider the best and acceptable option which has minimum or no impact. Following are the objectives of the study:  To conduct socio economic, cultural and institutional analysis of the communities in the project area and also the major social problems related to the project.  Avoiding or minimizing the loss due to the interventions for creating the pipe lines for drinking water supply to Coimbatore City Municipal Corporation.  Ensuring appropriate compensation for the Project Affected Persons (PAP)/Project Affected Families (PAF) irrespective of legal status with a view to provide suitable options that enable the affected people to improve or at least restore their standard of living in the post impact period.  Protecting marginalized and vulnerable groups, including the economically and socially disadvantaged (vulnerable PAF) through additional support.

The assessment helps to find out how the proposed pipe line project would affect the lives of the communities, residential structures, livelihoods, common properties, religious structures, infra-structure facilities etc. It would also help to look for alternative options and take the right decisions in terms of social sustainability; hence it is a valuable tool in the decision-making process.

3.2 Approach and Methodology

In the SIA process, consultation with major stakeholders and the local farming communities was undertaken. Consultations with the local communities, all affected persons, and representatives of other stakeholder groups provide opportunities to express

WAPCOS Limited 3 - 1

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District their opinions and concerns related to likely adverse impacts of the project plan and mitigate them. The process of consultation and participation included discussions with groups of men, women and other vulnerable sections of society. All the key issues and concerns expressed was documented, taken as inputs for the plan and to decide the necessary interventions. Secondary sources were referred to collect on the following aspects, demographic profile of the project area, social profile, economic profile and land use pattern.

3.3 SIA team

The SIA team consists of a senior expert with social science background who leads the team and a junior expert with social science back ground to coordinate the team in the field to conduct Focus Group Discussions (FGD), household survey and carry out interviews with the key informants in the field and department officials. The other members in the team are one Senior Environmental expert, one water engineer and a civil engineer to deal the technical matters related to alignment, water management etc. The team also has a gender specialist with sociology background to mainstreams gender concerns in the assessment and follow up implementation. Table 3.1 shows the study team of the project. Table 3.1: Study Team for SIA Sl.No Name Designation Qualification Experience 1. Dr.P.Thamizoli Social Expert Ph.D More the 26 Years’ / Team (Anthropology) experience in project Leader design, research, study and assessment of social impacts and preparation of management plans. 2. Sh.A.Stephen Leo Environment M.Sc More the 28 Years’ Expert / (Environmental experience in project Project Science) design, research, study Manager and assessment of Environmental impacts and preparation of management plans. 3. Dr.G.Pandiaraj Social Expert Ph.D More than 6 years’ (Anthropology) experience in qualitative data collection and

WAPCOS Limited 3 - 2

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Sl.No Name Designation Qualification Experience conducting FGDs & PRAs 4. Sh.Thumma Venu Project B.Tech, Civil More the 5 Years’ Madhav Engineer Engineering experience in project designs, analysis and preparation of project reports 5. Smt. M.Padma Gender MSW More than 5 years’ Malini Expert experience in qualitative data collection from women and organizing / conducting FGDs & PRAs 6. Sh.K.Periyasamy Coordinator Diploma in Civil More than 7 years’ Engineering experience in collecting secondary data, qualitative data collection, organizing FGDs & PRAs and liasoning for the project activities with various stakeholders. 7. Sh.Vishnu Programme MSW More than 3 years’ assistant/ experience in data entry Computer and analysis. Operator

A team of around 8 post graduate students from the Department of Anthropology, University of Madras supported SIA team to conduct the household survey and data entry. An experienced data analyst has carried out data entry, analysis and created tables using Special Package for Social Sciences (SPSS).

3.4 Socio economic profile of the project area

The project area covers nine revenue villages, seven from Coimbatore north taluk and two from Mattupalayam taluk. In the total nine villages seven are village panchayats and the following two are categorized as town panchayats, 1.Gudalore and 2.Narashimmanaikan palayam. The total number of households residing in the nine villages is 35439, and the total population is 126425 (Male: 64286, female: 62139).

WAPCOS Limited 3 - 3

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Villagewise total number of households and population

38859

17858 18749 13785 12414 9355 10897 9491 5914 3802 5023 4985 1710 2666 3619 2737

Fig 3.1: Village wise total number of Households and Population

Among the nine villages, Gudalur village has maximum number of households and more population compared with the other villages. On the other hand Naickenpalaym has the least number of households and population.

The total population scheduled caste population is 16278 (male: 8248, female: 8030) and scheduled tribe population is 1527 (male: 766, female: 761). Gudalur, Pannimadai and Thekkampatti are the three villages have more number of SC population and regarding ST communities the maximum number people among the nine village are living in Naickenpalayam and in two villages it is reported no tribal population.

Literate population is 94022 (74.36%). Literacy rate among the male population is 44503 (78%) and among the female Total worker population is 60485 (67.3%). Number of individuals involved in cultivation is 3133 (male: 2044, female: 1089) and the number of people work as agriculture labour is 7246 (male: 3939, female: 3307). About household industry workers population the total number is 1428, in which 788 are males and 694 are females.

WAPCOS Limited 3 - 4

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

The region is dominated by communities from backward and most backward classes. Majority of the farmers are small and marginal holders. Farmer use open well and bore wells for irrigation, cultivate for two seasons minimum and multi crops, cash crops like coconut, areca nut, banana and many vegetable and floriculture crops. The income from the dry land farming is not much; mainly they cultivate sorghum and use it as cattle feed. Agriculture in the region is mainly depending on monsoon rainfall. Livestock management particularly dairy provides additional income to the rural families. Although newly married couple forming nuclear families is increasing at present still joint family system is also in practice, particularly families in rural areas depending on farming for their livelihood.

Coimbatore is one of the most industrialized cities with small, medium and large scale industries, due to fast urbanization people from the villages are daily community to the city to work in the private sector. This gradually reduces the number f people depending on agriculture. The other factor due to rapid urbanization and the development of sub urban areas is the conversion of agricultural land in to house sites.

3.5 Stakeholder Analysis Stakeholder Analysis is generally used to identify the key actors and to assess their knowledge, experiences, interests, partnerships and contributions for the project etc. This allows policymakers and managers to interact more effectively with the identified key stakeholders and to increase the support for specific intervention, also to find out and act to prevent potential misunderstandings and conflicts. Information on stakeholders’ interests, and their capacity to oppose, assessment about their advantages, would help to decide how best to accommodate them. Stakeholder analysis would reveal the capacities of different stakeholders to participate in (and benefit from) the proposed development activity, and the complexity of organizational relationships.

WAPCOS Limited 3 - 5

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Table 3.2: The list of stakeholders and how they are associated drinking water pipe line project Coimbatore City Municipal Governance and responsible for services like water supply, Corporation drainage, health, education, solid waste management etc. Tamil Nadu Water Supply Providing links, laying pipelines, treatment, water supply and Drainage (TWAD) Board schemes etc. Revenue Department Responsible for Government lands and ensuring proper maintenance of land records for the State, resolve revenue disputes and also in charge for other aspects like address proof, community identity etc. Forest Community Protection of forest areas and wild life and to avoid human wild life conflict Local communities – men End users, and local people who provide land and support and women for the implementation of the drinking water project Local bodies – PRI Grass root governing systems responsible for local planning and implementation of development programmes

Stakeholder Consultations and participation Stakeholder consultations were conducted at two levels, at the first level with the communities and local leaders during the field visits and at the second level meetings with the officials of the Coimbatore corporation, revenue department and TWAD Board to discuss about the project objectives, implementation plan, activities each department will carry out, time line and the outputs. The following methods were used to carry out the consultations in the study.

Table 3.3: Methods used in the study Level Method/tools Output adopted Community Transect walk (in To witness the landscape, terrain, present level selected field sites – conditions of the area in the proposed alignment, along the capture the opinions and perceptions of the local alignment) people etc.

WAPCOS Limited 3 - 6

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Level Method/tools Output adopted Focus group To collect the opinions and perspectives of the discussion (FGD) local men and women, about the project objectives loss and compensation, needs and

priorities of the community members, and to understand the issues related to project implementation. Semi structured To get information about the local situation, interviews with the farmers’ status and possible solutions if there are local leaders and conflicts, and smooth implementation of the key informants project activities and mitigation measures. Department Office visits and To get understanding about the scheme and its level meetings /semi objectives, alignment, implementation process, structured problems and issues fore see etc. and the interviews with the interdepartmental coordination. officials

The project team made several field visits, during the month of February and March during the first visit had meetings with the different stakeholders discussed and collected the details about the project, in the first visit conducted the transect walk along the alignment and in the subsequent visits the team members conducted FGDs and house hold survey and also finalized the Project affected persons list in each revenue village in consultation with the officials of revenue and survey departments.

3.6 Transect walk made along the proposed water supply scheme alignment

The SIA team conducted transects on 6th and 7th February and covered the entire stretch of the proposed alignment area with the support of the officials from the District Revenue Department and Survey department. The team visited 18 selected sites covering all nine revenue villages and walked along the proposed alignment where boundaries are marked. During the transect the team members observed the land types, structures, standing crops

WAPCOS Limited 3 - 7

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

in the irrigated lands and dry land, tree crops, the facilities available for irrigation etc. Also visited the fields located closed to the forest boundaries and the points from where the wild life intrudes in the agricultural fields. The team members met some of the men and women farmers who were working in the fields and also met some of the farmers in their residence which are located close to area where the transect walks were conducted discussed with them and collected their views, opinions and suggestions about the project and land acquisition plan for the project.

Table 3.4: Summary schedule of Transit Walk S.No Taluk Revenue Village Date Participants

1 Mettupalayam Marudur 22.02.2020 16 2 Mettupalayam Thekampatti 22-02-2020 16 3 Coimbatore (North) Narasimhanaicken - 23-02-2020 8 palayam 4 Coimbatore (North) Kurudampalayam 29-02-2020 11

WAPCOS Limited 3 - 8

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

S.No Taluk Revenue Village Date Participants

5 Coimbatore (North) Pannimadai 29-02-2020 6 6 Coimbatore (North) Naickenpalayam 01-03-2020 12 7 Coimbatore (North) Nanjundapuram 01-03-2020 6 8 Coimbatore (North) Gudalur (North) 02-03-2020 7 9 Coimbatore (North) Gudalur (South) 02-03-2020 15

3.7 Focus Group Discussion (FGD) Focus Group Discussions (FGD) with the local communities helped to build a common understanding about the topics discussed and to adopt a coordinated approach subsequently to implement the project related development activities. In the context of the present assessment for the current project, it allows the project team to interact more effectively with the local leaders and representatives of the local communities to increase their understanding and elicit the view points of the local communities for better understanding of the situation and issues - and to find solutions. During the FGD, the project team sought the views of the local communities, generated information, mobilized opinions, gathered feedback, resolved conflicts, arrived at a consensus and recommendations, etc. To conduct FGD in the field, project team received the support of District Revenue Department field staff working in all revenue villages in the project area the support was mainly to identify the PAPs, mobilize them, fix the convenient venue and actively participate in the discussion.

Totally nine FGDs were conducted one in each revenue village. Men and women PAPS, were the participants of the FGDs. At the beginning of the FGD the project team members briefed the participants about the project objectives, approach and the purpose of the FGD, expected outputs of the FGD to help them to know about the background of the meeting and actively participate in the discussion (Annexure III gives the details of FGDs).

WAPCOS Limited 3 - 9

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Results of FGDs

 Considering the objective of the project, viz. supply of drinking water to the residents of Coimbatore city, the project affected people are not negative to give the lands for the project to lay pipe line and construct the required structures.

 The land owners who are going to lose their lands in the villages are mixed categories of farmers, small and marginal, medium and a few big farmers belonging to different communities.  The project affected people and some of the village leaders informed the SIA team that apart from the few meetings organized by the departments there has been no official NEWS and official communications regarding the proposed project and land acquisition. They opined that they should be properly informed about the objectives and other details of the project.

 The losses to the project affected people are mostly the agricultural land both irrigated and dry; some of them lose bore wells meant for irrigation. The crops grown in the irrigated fields are many vegetable and floricultural crops and fruit crops like banana. In the dry land they grow mostly sorghum and use it as feed for the livestock.  The other property people may lose are the house constructed (one or two), cattle shed, compound walls, tree crops such as coconut areca nut, teak trees and a few other species. Also the housing sites located in the lay outs (both approved and non approved) located in some villages.  Many of the project affected people expressed their concern that the alignment is going straight in the middle of the their land and divides the land into two and are left with narrow strips on both sides, this will make plowing, irrigating the crops difficult, hence requested to change the alignment to one side of the field and leave the rest of the land for agriculture. In few other cases where the alignment goes through the land and leaves a very narrow strip as remaining land, which cannot be used to do any farming, the owners of the land are requested to look in

WAPCOS Limited 3 - 10

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

to the possibility of acquiring this narrow strip of land and add the compensation amount.  Similar to fragmentation of agricultural land, the alignment divides some of the house sites in the layouts and leave small area of land on both sides of the alignment– in such cases the owners feel these sites cannot be used for construction of the house and therefore requesting the department to acquire the entire plot and provide a fair compensation as per the market value or provide an alternative site for construction of a new house.  Most of them expressed their serious concern about a fair compensation to the land, trees, standing crops and other structures they are going to lose. The project affected people say the compensation is going to be a onetime payment for the permanent asset they are going to lose, a source for their livelihood, hence expecting a fair compensation an agreeable amount.  The project affected people expressed their views regarding the transparency in compensation by the department viz. the method used for fixing the rate, how the rate is calculated and fixed for different properties like farm land, crops, trees and sheds and other structures.  The project affected people expressed their concern about the possible delay in the payment of compensation; they also mentioned about some of the earlier cases in Coimbatore district and other places the prolonged delay in making payments for farmers. They want the payment to be made immediately after the land acquisition. It was suggested to develop a method for the payment on a mutually agreeable terms and conditions.  Small and marginal holders expressed their concern that losing nearly one third of the land going to make them extremely vulnerable to manage their livelihood, hence expecting a better deal, which could help them to manage by investing the amount in some other income generation activities.  The amount of land they may lose in some of the small holders is more than 50% of the land they own. Hence, worried about the loss of income they get from the fields. These small holders are demanding whether the govt can provide any job

WAPCOS Limited 3 - 11

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

opportunities created in the project so that the family is not affected by the land acquisition and benefitted by the Job. The other option suggested is the vacant government land located adjacent to the village can be given to the farmers as compensation or on long term lease basis minimum for 20 years lease.  A few of the project affected farmers who are small and marginal holders feel taking land for the project would affect their livelihood, certain area of their land have been already affected due to the erection of high tension towers by TNEB. Hence requested to explore and find an alternative lay out.  The land going to be acquired are fertile lands and some of them are with perennial standing crops like herbs and medicinal plants, they may face a big lose in their annual income, hence expecting to provide compensation for such crops.  There are a few women headed households going to lose their lands they mentioned that none of the family member are educated their only source for income is through agriculture, if the govt decides to take away the land the compensation should be fair and should help to improve their livelihoods.

 The local farmers expressed their worries with respect to taking water from the dam for drinking water this will result in decreasing of water storage level; thus may affect the ground water table of the surrounding areas.  Wildlife intrusion particularly elephants and destruction of crops is a big issue in the villages which are located close to the forest boundaries, the farmers are worried that sometimes the new road going to be laid may create an easy access to the agricultural fields for the wild life and increase the problem.  The project affected farmers demand the compensation for fencing on both side of the new road going to be laid to protect the crops. They want the expenditure of the same can be added in the compensation package.  They want the road built over the pipelines to be made open for public use.  Some of the project affected farmers said there is experiencing meetings fatigue, many meetings were organized in the past without sharing the right information and arriving any concrete conclusions.

WAPCOS Limited 3 - 12

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

3.8 Socio Economic Survey The survey was conducted to understand the socio economic conditions of the Project Affected Persons / families in the project area. A household schedule was used to conduct the survey with questions related to multiple topics such as socio-economic status of the families, livelihoods, nature of loss, their perception about the project, perceptions about the loss, opinions and problems they may encounter etc. The draft schedule prepared for the survey was field tested and finalized (Annexure II).

The total number of PAPs going to be affected are enumerated as 688, out the total 118, which forms 17% of the households were selected for conducting the survey. The survey was conducted in all nine revenue villages the respondents covered are from 27 settlements, the maximum number of samples are collected from Thekkampatti (30.5%), the village where the number of land owners who are going to lose the number is maximum, the other villages which crossed more than 10% of the total samples are Gudalur (south) 12.7%, Marudur 10.2% and Nayakanpalayam 15.3%.

Table 3.5: Village wise % of survey samples

S.No Village Frequency Percent 1 Gudalur-North 9 7.6 2 Gudalur-South 15 12.7 3 Kurudampalayam 7 5.9 4 Marudhur 12 10.2 5 Nanjundapuram 8 6.8 6 Narasimma Nayakan Palayam 7 5.9 7 Nayakanpalayam 18 15.3 8 Pannimadai 6 5.1 9 Thekkampatti 36 30.5 Total 118 100.0

A group of 10 members’ team pursuing / completed post graduate degree in Social Anthropology from the University of Madras have conducted the survey. As a first step an orientation meeting was conducted to the field work team to provide a brief

WAPCOS Limited 3 - 13

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District description about the project and to discuss the house hold scheduled already prepared and translated in to Tamil, each question in the schedule was explained well to the team members to avoid any confusion later when they were doing the survey. The team carried out the survey during the last week of February and first week of March 2020.

Results of the socio economic survey

The following are the major results derived from the socio economic survey conducted:

The survey results show majority of the household heads are males (89.8%) only one tenth (10.2%) are the female household heads.

Table 3.6: Details of household heads

S.No Sex Frequency Percentage 1 Male 106 89.8 2 Female 12 10.2 118 100

Regarding the details of the constitutional status of the communities surveyed the survey results show that more than half (58.5%) of the PAPs are from Backward communities and nearly one fourth (22.0%) belonging to communities from Most backward category, 8.5% are from the two following Scheduled caste communities Aruthathiar and Parayar and the remaining 11.0% are from other communities.

WAPCOS Limited 3 - 14

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Contitutional status of PAPs

60 50 40 30 20 10 0 Backward Most Class Schduled Backward Others Class Caste

Fig 3.2: Constitutional Status of PAPs

Regarding the age structure of the land owners it starts from 21 years onwards and some of them are above 80 years old. The maximum percentage is from the age group 51 to 60 years (34.7%), the next highest percentage 25.4 is the age group 61 to 70 years old. The age group of 31 to 40 is 8.5% similarly the age group of 21 to 30 is only 6.8. Above 80 years (5.1%) and 21 to 30 age group (1.7%) are small in numbers.

Fig 3.3: Age structure of PAPs

WAPCOS Limited 3 - 15

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Education is an important variable to understand social change and development of a community. Regarding the educational status of the PAPs as per the survey results, 12.7% of the PAPs are illiterates, the highest number is who studied up to secondary education (27.1%0, this is followed by primary education 22.0%, some of the land owners are graduates (11.0%), professional degree holders (9.3%) post graduates (5.15%), and Diploma holders (4.2%) etc.

Table 3.7: Educational Qualification of PAPS Educational S.No Qualification Frequency Percent 1 primary 26 22.0 2 secondary 32 27.1 3 Higher secondary 7 5.9 4 ITI 2 1.7 5 Diploma 5 4.2 6 Doctorate 1 .8 7 Graduate 13 11.0 8 post graduate 6 5.1 9 professional 11 9.3 10 illiterate 15 12.7 Total 118 100.0

Regarding the primary occupation of the land owners, the survey results reveal that more than half of the lane owners (PAPs) are farmers (61.9%), 11.0% of the land owners are doing business, another 11% are working for private sectors, a small portion of the owners (6.8%) of dry land or unable to get enough income from the land are earning their livelihood through working as daily wage labourers. A small section (5.9%) of the owners who are going to loss land is retired people from the govt and private service. The remaining few categories are in negligible percentage.

WAPCOS Limited 3 - 16

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Primary occupation of the land owners Govt.service Driver 2% Daily wage 1% Retired 8% 7%

Business 12%

Agriculture 70%

Fig 3.4: Primary Occupation of Land Owners

About the family types nuclear, joint and single member household, majority of the informants (58.5 %) are from nuclear families, next is joint family 39.1%, according to the respondents staying together as family of two or three generation as a joint family is good to carry out different agricultural activities, and a small number of PAPs (3.4%) are single member households.

Table 3.8: Details of Number of Family Members S.No Number of Family Frequency Percent Members 1 1 4 3.4 2 2 26 22.0 3 3 20 16.9 4 4 34 28.8 5 5 17 14.4 6 6 10 8.5 7 7 4 3.4 8 8 3 2.5 Total 118 100

WAPCOS Limited 3 - 17

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

The above table provides the details of the size of the family of the PAPs, maximum number of families (28.8%) are with average four members, next is (22%) families with just two members, families with three members are 16.9%. Four families (3.4%) are reported with seven members and three families (2.5%) are with eight members’ highest number reported. The vulnerable cases are four (3.4%) are single individual households.

Table 3.9: House Type of PAPS S.No House type Frequency Percent 1 Pucca (house with concrete walls and terrace) 79 66.9 2 Semi pucca (one portion is terrace and the 18 15.3 remaining are tiled or asbestos roof) 3 Tiled 21 17.8 Total 118 100.0

According to the responses received, majority (66.9%) are living in pucca houses, most of the new houses constructed in the recent past are pucca houses. Mostly old houses are tiled, 17.8% have told they are living in tiled houses, and the remaining 15.3% are living in partially pucca and the remaining area tiled or asbestos roofed houses.

More than 90% houses are old houses, some of them are built ten or twenty years back. All houses are electrified and have ration cards. Among the PAPs 11.0% have reported that at present they are living in rented houses and the remaining 89% are residing in their own houses.

Regarding the drinking water facility majority (72.9%) have their own tap, 11.8% are depending on common tap and 11.0% have responded they get from their own tube wells, a small per cent (3.4%) get from the open wells. For the mobility 89% have responded that they have their own vehicles (it includes different kind of vehicles) and 11.0% depends on public or private transport system. About the modern ICT facilities like, TV, mobile phone etc., 97.5% responded positive own these facilities use it to watch news or entertainment programmes.

WAPCOS Limited 3 - 1 8

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

About landholding details of the PAPs maximum percentage of farmers lose land are marginal holders (42.4%), next is semi medium category (20.3%). More or less the same percentage of farmers from small holders (16.1%) and medium size holder (12.7%) lose their lands, and a small number of PAPs are big farmers (2.9%). Remaining 5.9% are the owners of house sites and they involved in different kinds of occupations.

Fig 3.5: Land holding of PAPs

The survey results show that more than half of the respondents (61.9) own irrigated lands and cultivate different vegetable crops, floriculture crops, and many other cash crops. 32.2% owned only dry land which they use to cultivate for a single season and corps like sorghum, horse gram, and many of them left the land as fallow because doing farming in dry land is not profitable now days. The remaining 5.9% of the owners are as indicated already owners of house sites.

As per the survey results only less than half of the respondents (43.2%) own livestock (which include, cattle, sheep, goat and poultry) and remaining households own no livestock.

WAPCOS Limited 3 - 19

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

In the survey an effort is made to collect the annual income of the households of the PAPs, the results reveal that the highest percentage PAPs (19.5%) earns from 3 lakh to 5 lakh, the next in the order families earn is 50 thousand to 75 thousand, 11.0% of the PAPs come under this category, a little lesser percentage of 10.2% is reported by three groups (75 thousands to 1 lakh, 1.5 lakh to 2.0 lakh and above 10 lakh). All remaining groups with different amount of annual income are reported as less than 10%. Table 3.10: Annual Income of PAPS S.No Annual income Frequency Percent 1 below 27K 3 2.5 2 27K - 50K 9 7.6 3 50K - 75K 13 11.0 4 75K - 1 lakh 12 10.2 5 1 lakh - 1.5 lakh 11 9.3 6 1.5 lakh - 2 lakh 12 10.2 7 2 lakh - 2.5 lakh 9 7.6 8 2.5 lakh - 3 lakh 4 3.4 9 3 lakh - 5 lakh 23 19.5 10 5 lakh - 10 lakh 10 8.5 11 10 lakh and above 12 10.2 Total 118 100.0

Regarding willingness to provide the land for the project the survey results reveal except one PAP all other remaining (99.2%) have responded positive, considering the objective of the project they cannot say no to the government for implementing the project. Some of them told that they feel bad to give their ancestral land and also due to other issues like fragmentation, wild life intrusion etc., but still could not refuse to give the land considering the public benefit of the project. The reason given by the person who is unwilling to give the land is that it is his ancestral property, he likes to transfer the proper to the next generation, he feels it is his duty to support the next generation to inherit the age old property as he inherited from the previous generation.

WAPCOS Limited 3 - 20

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Table 3.11: Perception about impact due to the lose off the land S.No Impact Frequency Percent 1 Fragmentation of land and unfit to do 17 14.4 farming 2 Fragmented land needs extra 1 .8 maintenance 3 Loss of traditional asset 23 19.5 4 Loss of asset, Fragmented land needs 3 2.5 extra maintenance 5 Loss of income which affect the 43 36.4 livelihood 6 Loss of income, Fragmented land 2 1.7 needs extra maintenance 7 Loss of land value in future 8 6.8 8 Loss of income, Fragmented land 8 6.8 needs extra maintenance 9 Loss of perennial crops have in the 1 .8 land 10 No opinion 12 10.2 Total 118 100.0

According to the survey results, PAPs perception about the impact they face due to the land loss varies, Some of them provide single impact and others expect more than one, combination of two impacts. The highest percentage of PAPs (36.3%) feel their income will come down and will affect the livelihood. Next category 19.5% of PAPs understanding is that simply they will lose their traditional asset. 14.4% worried that the remaining land will be meagre, a narrow strip and become unfit to do farming. Some of the PAPs (10.2%) are unable to form any opinion about the impact due to land loss.

Table 3.12: Perception about how the project impact the community S.No Impact Frequency Percent 1 Groundwater depletion 6 5.1 2 Increases wildlife intrusion 16 13.6

WAPCOS Limited 3 - 21

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

3 Increases wildlife intrusion, Groundwater 1 0.8 depletion 4 No opinion 95 80.5 Total 118 100.0

Regarding the impact at community level, the results of the survey show that majority of the PAPs (80.5%) have no opinion about how the project will impact the local communities. 13.6% fear about the increase of wild life intrusion and destruction of crops, farmers living in the villages located close to the borders of the forest area expressed this fear. PAPs from the villages located close the source from where the water will be pumped expressed their concern that taking water will reduce the storage and subsequently results in the depletion of the ground water in the surrounding areas.

3.9. Social Screening and Categorization Socio sustainability is basic to ensure the achievement of any development result and subsequent impact. In the process of implementation it needs to be ensured about the positive results of the project and also the adverse and irreversible social risks, and impacts are avoided, minimized and mitigated.

Activities with high risks may result in significant adverse impact on the existing socio economic systems; they may raise serious concerns among the target communities particularly the project affected people.

The screening process involves the following steps:  Identify the potential risks and their significance  Decide the project risk category like low, moderate and high  Determine the level of social assessment and management required to address the potential risks

In order to facilitate proper identification of potential social risks and mitigate and manage potential impacts, sub-projects to be financed under the project will be placed into one of the three categories given below. The categories defined on the extent, scale and magnitude and duration of expected potential negative results and adverse impacts.

WAPCOS Limited 3 - 22

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

As per categorization of sub-projects, the various safeguard instruments/tools – Environment and Social Management Framework (ESMF) will be applied.

3.10 Social categorization of projects Based on the magnitude of impact to the Project Affected Persons (PAPs), projects have been categorized as either S-1, S-2 or S-3 as follows: Table 3.8 given below shows the Social Categorization of Projects Category Description Type of project Level of issues Management measures Table 3.13: Social Categorization of Projects Category Description Type of the project Level of issues Management measures S1 Serious social SIA and RAP 1. If it involves acquisition of private issues expected land with major impacts (people lose more than 20 % of the productive assets) 2. If it involves physical displacement. S-2 Moderate social SIA and If impacts are limited to less than 200 issues expected Abbreviated Persons or about 50 families of minor RAP nature (people lose less than 20 % of the productive assets). S-3 No social issues Social No private land acquisition or no expected hence Screening impacts to PAPs socially benign Report Source: Tamil Nadu Sustainable Urban Development Project (TNSUDP) Environmental and Social Management Framework (ESMF) http://www.tnuifsl.com/index.asp

3.11 Impact identification & mitigation measures

The general impacts have been assessed from field visit observations, FGDs, and the socio economic survey conducted. The possible impacts at various stages of the project such as prior initiation, during implementation and post project period have also been assessed

WAPCOS Limited 3 - 23

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

and mitigation measures are suggested.

Table 3.14: Activities and potential impacts and suggested mitigation measures Activity Potential Impact Suggested mitigation measures Land acquisition – A portion of the agricultural land is A fair compensation will Agricultural land acquired from each PAP be made for the loss, hence will not create any permanent impact Due to land fragmentation in some cases Govt can acquire these the farmers are left with small narrow narrow pieces and add the strips of lands, these lands will not be compensation useful for cultivation practices Land acquisition House site is acquired from the PAP A fair compensation will be made for the loss, hence will not create any permanent impact Due to fragmentation of house site – the Govt can acquire the remaining area may not be enough to remaining land of the construct a house house site and provide a fair compensation or an alternative house site Livelihood issues A portion of the agricultural land is each PAP and a fair acquired compensation will be made for the loss, hence will create any permanent impact The livelihood of the most vulnerable Members of these most sections like women headed households, vulnerable families can or small holders from vulnerable be considered if any job

WAPCOS Limited 3 - 24

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Activity Potential Impact Suggested mitigation measures categories may impacted in a created in the project considerable way Felling the trees like coconut and areca Explore the possibility to nut may impact the family annual change the alignment to income save more tress and reduce number of felling Loss of bore wells Compensation will be paid to dig another bore well, hence will not create any permanent impact Construction of No negative impact, indeed the local - road over the pipe people will get the new road facility line Increase of wild life intrusion Digging trenches along particularly elephants the borders of fringe villages as natural barrier to prevent intrusion – For this the PIU need to work with the State Forest Department The trenches need to be maintained by removing the silt regularly The other option – explore the possibility to change in the alignment in the problematic areas

WAPCOS Limited 3 - 25

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Activity Potential Impact Suggested mitigation measures Public health Minimal impact Provision of onsite healthcare Communication No negative impact - and electric system Religious No negative impact - structures

Based on the outcome of SIA, it is found out that the project involves acquisition of agricultural lands of local farmers and in some areas the house sites. Implementation of this project makes around 477 farmers partially lose their farming lands and total area estimated is 46.02.71 Ha. In the case of house sites it is enumerated 211 owners will lose the land and the area is 3.48.51Ha land.

The total amount of land people lose is less than 20 % of the total amount of land and tree crops (productive asset) they owned, hence this project is categorized as S2. The details of the impacts are provided in Table 3.15 and Table 3.16 for better understanding.

WAPCOS Limited 3 - 26

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Table 3.15: Table Details of land loss and number of PAPs Agriculture land Agri House Total Total SI.No Taluk Name Village Name Wet Dry land PAPs PAFs site Area Area PAFs Land Land Area Mettupalayam Thekkampatti - Dry 13.39.94 207 1.88.67 148 15.28.61 355 1. land Mettupalayam Marudur - Dry 13.46.62 91 0.24.49 22 13.71.11 113 2. land Coimbatore Gudalur North - Dry 3.68.17 50 0.15.79 10 3.83.96 60 3. North land Coimbatore Gudalur South - Dry 6.02.59 41 0.12.12 8 6.14.71 49 4. North land Coimbatore Kurudampalayam - Dry 3.03.97 25 - - 3.03.97 25 5. North land Coimbatore Naickenpalayam - Dry 2.30.53 38 0.45.19 5 2.75.72 43 6. North land Coimbatore Nanjundapuram - Dry 0.78.76 07 0.13.49 5 0.92.25 12 7. North land Coimbatore Narashimanaickenpalayam - Dry 0.96.33 07 - - 0.96.33 07 8. North land Coimbatore Pannimadai - Dry 3.35.80 11 0.48.76 13 3.84.56 24 9. North land Total 46.02.71 477 3.48.51 211 50.51.22 688

WAPCOS Limited 3 - 27

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

The enumeration is done jointly by the revenue and survey department covering the entire length of alignment, areas of head work and treatment plant. As per the revenue records the entire land area going to be acquired is under dry land category. But in some portion of the area is used for irrigated agriculture using the water from bore wells and open wells. The total number of PAPs enumerated is 688. Thekkampatti and Marudur the two revenue villages come under Mettupalayam taluk from where more area of land will be acquired. Nanjundapuram and Narashimanajckenpalayam are the other two villages where least number of farmers are affected.

The loss of land may not create much negative impact over the income and livelihood of the medium and big holders; they are in a position to manage their income and livelihoods with the remaining land they own. Their concerns are primarily that their lands will be fragmented and sometimes will have practical difficulty to do farming in some of the land area. But small and marginal holders who loss considerable amount land which they use for cultivating cash crops or fodder crops for their cattle are concerned about the loss of land which may affect their annual income and livelihood. They are expecting a fair compensation which will help them to invest in some other suitable income generation activities and compensate the income loss.

Regarding the loss of house sites land, those owners who are residing somewhere else and invested here are not having much issue except a fair compensation for the land loss, but some of the owners told that they bought the land to build a new house and settle here later and they are expecting to get the compensation amount which can help them to buy another house site in the same area or the govt can provide another house site as compensation instead of giving money.

WAPCOS Limited 3 - 28

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Table 3.16: Table Details of tree crops and other tree species loss and PAPs S. Tree Crops Total Total Coconut palmyra Areca Tamari Neem Teak Mango Lakshmi Bamboo Pongam N Village Name Trees PAF’s o palm Nut nd Taru oiltree 1. Thekkampatti 353 - 167 - 50 283 - - - - 853 36

2. Marudur 118 4 - - 10 - 1 - - - 133 16 3. Gudalur North ------4. Gudalur South 253 - - - 100 - - - - - 353 18 5. Kurudampalayam 3 - - 1 38 - - - 1000 - 1042 8

6. Naickenpalayam 191 - - - - 9 - - - - 200 9 7. Nanjundapuram 2 - - - 2 - - - - - 4 3 8. Narashimanaickenpalaya 16 - - - 3 - - - - - 19 2 m 9. Pannimadai - - - - 15 - - 8 - 45 68 2 Total 936 4 167 1 218 292 1 8 1000 45 2672 94

WAPCOS Limited 3 - 29

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Regarding the loss of tree crops, 94 families will lose the tree crops and other trees located in the land, and the total number tree enumerated is 2672, the loss coconut trees will be maximum 936 followed by teak 292, Neem 218, Areca nut 167 the other species are in negligible numbers. Farmers of Thekkampatty and Gudalur south will lose more number of trees; Marudur and Naikenpalam are the other two villages where the farmers will lose considerable number of trees.

Coconut and Areca nut are the two important tree crops which fetch them good income to the families, and felling of the trees will affect the income they get from these trees, about the other trees, farmers told that these trees are like a reserve whenever they need urgent money they sell the trees and manage the situation, now due to the project they lose that option.

It is reported in some of the fields with standing perennial crops located within the boundaries of the alignment, destruction of the crops is a loss to the farmers, and hence they expect compensation to the loss.

3.12 Public consultation and Disclosure Stakeholder involvement in the form of public consultation and disclosure is defined as the two-way communication between the project team and the targeted and affected groups. The main objective of such stakeholders’ participation is primarily to promote public understanding and acceptance of the proposed developmental activity or a project by minimizing potential perceived environmental impacts through education and open discussion. In return, public feedback can be used as constructive input and minimize the damage, loss and to promote alternatives in the project design.

3.13 Compensation and settlement for PAPs The need for compensation arises when the land which is acquired is involuntary and/or loss of livelihood, sources of income and access to common properties/resources on which people depend for economic, social and cultural needs irrespective of their legal

WAPCOS Limited 3 - 30

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District status. If the lands are privately owned, the land owners are entitled to legal compensation for land that they will lose as per the “Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013’.

The clauses in the act provide compensation, rehabilitation and resettlement to the affected persons. The law makes sure that:  The Project Affected Persons get fair compensation when their land is taken away for the project  Transparency is ensured in the land acquisition process and arriving the consensus  Local self-government including the gram sabhas are consulted in the process of land acquisition  Ensures adequate provisions for the improving the livelihoods and rehabilitation of the Projected Affected Persons.

The following are the clauses which deal about the determining the market value of the land, calculation of compensation and determination of the award for the land owners.

 Clause 26 of act provides the criteria need to be considered in assessing and determining the market value of land  Clause 27 provides the details about how to calculate the total amount of compensation to be paid to the land owner  Clause 28 provides the details about the parameters to be considered in determination of the award

As per the alignment plan and enumeration made the total area of private land need to be acquired for the project implementation is 50.51.22 Ha from 688 families of various socio economic backgrounds. Around 2692 trees will be removed from the lands of 94 land owners.

The compensation will be made based on the consent award (acquisition through mutual negotiation) would be preferred for land acquisition.

WAPCOS Limited 3 - 31

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

The benefit to the land losers would be provided as lump sum assistance. The amount will be used to improve the livelihood.

Apart from providing compensation to the land acquired with the alignment, as indicated in the mitigation measures the following aspects need to be considered:  Provide compensation for the land which cannot be used for doing agriculture due fragmentation of land.  Similarly to the house site due to fragmentation which cannot be used to construct a new house due to lack of enough area.  The other aspects need to be addressed is to avoid wild life particularly elephants intrusion digging trenches as natural barriers in the areas due to the new road laid close to forest boundaries with the support of the State Forest Department.  Any other unforeseen impact due to the project implementation would be addressed and mitigated as per the Act 2013.  The final compensation amount for the land acquisition and structures will be determined by the Competent Authority.

3.14 Institutional Arrangements The main objective of the institutional arrangement is to ensure quality assurance and safety structures to apply social safeguards.

The present institutional arrangements in TWAD for implementation of the Social Safeguards measures in the 9 villages under Pillur Water Supply project has been reviewed and it is felt that the existing arrangements need to be strengthened to meet the requirements of general public and project affected families which includes a social expert. If the issues and concerns land acquisition and compensation are not identified and addressed, it may affect the implementation of the planned activities under the project components.

The institutional arrangements for implementation of different project components would be made such that participation of different stakeholder’s particularly primary stakeholders and women are ensured. The organization charts for TWAD as follows:

WAPCOS Limited 3 - 32

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Fig 3.6: Organization Chart of TWAD

The project shall be implemented by TWAD and coordinated by Revenue Department, Public Works Department and City Municipal Corporation. All the departments shall report to District Collector, Coimbatore to review the progress of the project at regular intervals and shall provide strategic directions, guidance on policy matters and resolve conflicts, if any.

The concerned Executive Engineer (EE) of TWAD and concerned line department shall act as Project Implementing Units (PIU’s) for all the project activities falling within their domain/responsibility.

It is suggested that TWAD / District Collector, Coimbatore will hire a qualified social expert. In addition, orientation on safeguards will be provided to JE, AE, AEE and EE and

WAPCOS Limited 3 - 33

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District their equivalents in charge of implementing project activities. One nodal environmental and social safeguards person will be identified in each line department who will be responsible for monitoring and reporting on the implementation of the safeguards arrangements and mitigation actions. The roles and responsibilities of social expert hired by TWAD / District Collector, Coimbatore are given below. Table 3.17: Implementation Arrangement – Roles and Responsibilities Experts Responsibility Senior Social Scientist  Shall provide necessary inputs on social aspects related to the project  Shall provide input in implementation the implementation of the mitigation measures identified and support to resolve if there are any conflicts during implementation.  Shall undertake site inspections with the other nodal person from the departments  Giving orientation on social safeguards to the project implementation unit  Shall ensure women’s participation and empowerment

3.15 Gender Issues

It has been observed that during implementation of project women farmers are most vulnerable and suffer most. Therefore project implementation unit should ensure that proper and adequate care has taken to minimize adverse impacts on women farmers.

The following issues should be addressed to minimize discrepancies amongst men and women and some of the special support for women during the implementation of the project activities.

Special care and extra support should be provided for those households headed by women.

Equal wage must be provided in the project implementation works to the women in the villages. This should be ensured by the employer who should also undertake regular inspection/checks for proper implementation of the process.

WAPCOS Limited 3 - 34

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

As special case relaxation of work hours should be there for working women having small children.

Efforts should be made to coordinate with the relevant line departments to help dove tailing with their development programmes for the social economic development of women particularly the women PAPs.

In case of any grievances specific to women the local women may approach the project implementation unit and the Grievance Redressal cell.

3.16 Grievance Redress Mechanism (GRM) Grievance Redress Mechanism (GRM) is one of the important tools for project management where major stakeholders are public community having diverse socio-economic status. Pillur water supply project deals with the acquisition of land from farmers and public and hence likely to have grievances in terms of receipt of compensation for the acquired land, alignment of the pipeline, construction practices, timelines, water management and other issues. The institutional arrangement proposed in the project needs to ensure the concerns of all the project affected families and stakeholders are addressed and accommodated in a comprehensive manner.

GRM at Project Implementation Unit GRM is an essential component of any project administration, particularly if the project involves project affected families and the local communities with diverse socio economic backgrounds and have as the major stakeholder. The grievance redress process will be a continuous, transparent and participatory process that would be an integral part of the project’s accountability and governance agenda.

A project level GRM will be in place for addressing social, environmental and project related grievances. The GRM will have multi-level structures and processes. At the district level the committee is made up of DRO, Coimbatore, City Engineer, Corporation EE, TWAD, and EE, WRD, this committee meets on fortnight basis. This committee will look after the grievances related to payment of compensation for the land, implementation of the mitigation measures, construction practices and water management. At the next level the Collector heads the

WAPCOS Limited 3 - 35

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District committee and convenes the meetings monthly ones. The next level is the HODs at the state level they contact remotely monthly once and organize meetings at every quarterly. Secretary occupies the next level in the structure and in charge of overall appeals and supervision of grievance redress; he calls for a meeting once in six months and annually. For every six months report is prepared at all levels and sent to the Secretary. Quarterly report will be submitted to Vigilance Commission and Disciplinary Proceedings.

Grievance Redress and Feedback Review and feed back

DRO / EE / CE Fortnightly

Six monthly District Collector Monthly Report

Monthly – remotely HODs – State level Quarterly in Person

Secretary Six monthly and Annual Appeals and Supervision

Effort will be made to create awareness about GRC mechanism to the beneficiaries through use of flyers and pamphlets at the village and Block level.

Scope of GRC The GRC will receive and redress grievances and complaints that are formally brought to the GRC in writing by the persons and/or group of persons who have a grievance because of the Program’s adverse impact on him/her and them. The grievance would, among others, relate to payment of compensation to all project affected persons in accordance with the compensation matrix.

WAPCOS Limited 3 - 36

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Process of GRC  The GRC will receive all grievances/complaints and enter them in the Grievance Register;  The GRC will work out a timeframe to redress grievances/complaints if such grievances / complaints are not redressed during the first meeting;  The GRC will acknowledge receipt of all grievances/complaints, by registered post, within 7 days of receipt;  The GRC will consider and redress grievances/complaints through public and transparent process in which all those who have lodged their grievances and complaints in order to facilitate transparency and accountability;  The GRC will communicate its decisions/redress in writing to the complainants within 4 weeks depending on the nature of complaints and  The GRC decisions are not the final and the grieved and complainants have the right to seek judicial redress if they are not happy with the decisions of GRC. But it should not the paraphrase the constitution fundamental rights.

Name, Office Address, Contact number and email id of authorised officer shall be communicated to all the project affected families. The beneficiaries can register complaints in following ways: 1. Open House at the Tehsil and District levels. 2. By ordinary/registered/speed post addressed to concerned authorised officer of their area.

Complaints/Grievances Register will contain (a) Serial Number; (b) Case Number; (c) Name of the Grieved/Complainant; (d) Name of Father/Husband; (e) Gender (f) Age; (g) Full Address; (h) Brief details of grievance/complaint; (i) List of documents, if any, attached; (j) Details of previous grievance/complaint, if any; (k) Date of receipt of grievance/complaint and (l) Date of acknowledgement of grievance/complaint

WAPCOS Limited 3 - 37

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

When closing the complaint, agreement should be made with the complainant on remedy, and both parties sign to their approval of the case being closed and outcome accepted. Copies are kept in both hard copy and electronic by both parties.

Right to seek Legal Redress The grieved/complainant will have the right to seek legal redress through the judicial system if he/she or they are not satisfied with the decisions of the GRC. The option of seeking redress through the GRC or through the judicial system will be explained to project affected persons during the process of public consultation and participation. But it should not paraphrase the constitutional fundamental rights.

WAPCOS Limited 3 - 38

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Annexure I - Alignment Map

WAPCOS Limited i

WATER SUPPLY IMPROVEMENT SCHEME TO EXPANDED COIMBATORE CORPORATION INCLUDING NEWLY MERGED AREAS WITH RIVER BHAVANI AS SOURCE NELLITHURAI NANJUNDAPURAM HEADWORKS

NAICKENPALAYAM

248

1A

1B

1C 264

124

118 255

255 154 1A 153

157

1E 1B 156

255

1D

1G

2

116

1I 1F

120 1K 1C

159

1J 117

1

1H 117

MST LOCATION

1L

1M 256

1N 1

1A

2A

2 257

1B 114

258

2C

1C 256 113

2B

1H 1E 256

116 257

1D

1I

258 1G

210

113 210 3 264

210

2A 160

1 2A

1F

2B

1A

113 1J 1 1

2A 2B 113 2

161 261

162

2C 1 6 1B

398

4 2 5

5 2C

7 3 4

155 1 2B 3

1 2A 4 5

356 8 124

3 2D

351

4 5 357 398 2 4 261

8 2

6A

2A

3A 1A 210 2B

1 3 2E 902

210 258 6B

3B 4 2 326

1B 11A

124 1G 2B

342 397 3 7

391 3A

3

THEKKAMPATTY V.NO:9 308 9 10 262 NELLITURAI

9 3C 1C 11B

3 2A 397 2C

346 1A

141

1A 174 1D 2 142

1B2 1E 142

174

355 391 1F 396

3B 353 2 1B 395 395 6

3D 1H THEKKAMPATTY 7

1 1 8

9 5 392 605 901 397 NELLITUDAI

2 3F THEKKAMPATTY 3

352 355 V.NO:3 2B 1C 3B 900 3A

3H 392 899 899 1B1 1I 900

3G 2 899

345 3I 3C 603

1B3 394

899

1 4A 289 960 1 2 2

3A 900 4B 898 263

3B 206 393 3A

900

178 897 403 263 2 901 896 897

344 4 901

10 123

3B 604 896 2C 1A 909 895

602 1

320 393 1B 1C 2

3 354

343

602 3A 897 898 3 897

NO7 MARUDHUR 2 1A 586

NO7 MARUDHUR

319 602

4 896 896 575 WELL 1B V.NO:THEKKAMPATTY 896

5 NO7 MARUDHUR

573 895 895

1 544 894

NO7 MARUDHUR

NO7 MARUDHUR 587 603 587 207

615 1C

603 602 3B

601

587 2 587

565 SURVEY NO : 599 1 896

886

576

V.NO.3 THEKKAMPATTY 585 : NO SURVEY 2 887 576 895

894 2A 572 1 887 V.NO.3.THEEAMPATTY 2 893 894 3 6004 1

SURVEY NO : 588 599 888 599 606 893 895

2B 576 892 888

588 BUILDING R 819 WELL 919

V.NO.3.THEKKAMPATTY V.NO:3 585 889

THEKKAMPATTY 888 601 957 893 572 5 4B 585 4A 1 889 601

198 577 3 2 4C

SURVEY NO : 560 899

200 565 6 BUILDING C

588 7 3A 3B 3A 577 3D 3C 8 SURVEY NO : 600

9 600 1 572 672 577 3 3B 1A1 1

201 589

598 WELL

1A2 SURVEY NO : 564

584 588 WELL 589

920 201 606 : NO SURVEY

564 634 SURVEY NO : 634 577 193 584 888

1A 10 2 202 890 889 9A 598

1A

633 BUILDING R 1A3 9B SURVEY NO : 571 589 563 2 11A 889

563 5 634 571 263 634

2A1 1 8 1 2 891 890 192 PANNIMADAI

225 1B 613 564 589 890

2 2A BUILDING R 11B 5

1A4 3 920

560 R BUILDING BUILDING R 1A2 948

891 7 560 193

4 2 2A2 2 597

578 1B1 3 192 578 1A5

2D 597 1B 1 WELL BOOR 2

SURVEY NO : 556 SURVEY NO : 584

192 566 597

1 WELL 2A4 6 1B2 191 3 566 2A3 2B 566

2C 3

188/B 891

5 590 THEKKAMPATTY 920 204 2E

3 940

204

224 883 263 4 238 238 1B 882 188/A

203 2A5 880 881

2A6 562 882

239 880 881

188/A 881

579 921 880

1D3 562 567 947

5 570 579 607

239 921 189 223 4

190 612

2B2 188/A : NO SURVEY 567

238 2B1 1C1 223 203

204 205

561

1C2 591 V.NO:22

V.NO:22 561

NANJUNDAPURAM 224

224 209 191

2 1 880 651

2C 921

191

644

205 BUNK HP 947 553 650 2 208 4A 581 3

250 221 611 209 608

208 1G 2B 222 205 1A 2E 2C

2D

THADAGAM 1B V.NO:24 1 244 4B

490 264 2A

222 208 1A 249 43

206 1A 49 44 49 207 459

221 222 209 208 206 209 49

208 205 880 222

343 921

210 947 491

361 221 220 652

210 250

220 207 1B 362

210

207 207 879

491 210 210 49 593 2 930 922 399

399 210 210 206

250 250 2A 362 220 220 1B 649

2A2 249

251 1C

1A 343 248 220

248 1

249 1A 361 1 400 251 583 207 2B

498 252

2C 2A1A 449 407 220 1D 361 1C1

542 2A1B 50

NANJUNDAPURAM 493 V.NO:22 498

EXISTING PIPELINE 245 291 251 1B 251

400 252 2B 457 211 357 291 449

2A3 1A 251 879

2 936

361 1F

NANJUNDAPURAM 457 1D 219 V.NO:22 245

252 219 922 SURVEY NO : 401 : NO SURVEY

291 1E

457 252 1 450 : NO SURVEY 289

407 51 538 211 SURVEY NO : 492 1C2

273 400 247

545 653 1B 407

247

2A4 494 290

1B1 287 219 363 1G

2D

494 494 2

501 51

358 492 494 253 1C

SURVEY NO : 456 879

2B 1B2 936

497 494 258 2 539 450 2A 2D 1A

492 217 456 2 870 2C 290 363

3A1 358 540 SURVEY NO : 495 2B 935

495 2C 497 923

406 1B3 2 495

358 539

3B1 3A2 3B2

456 3A3 653 541 3C2

1

363 495

365 2C 2B 3C1 357 500 3B3 496

540 1C 2A 289 496 648

SURVEY NO : 406 2 923

935

357 455 451 1A 451

287 870

455 1D

543 357 455 359 543 1B 541 361 543 451 451 1

365

1A 500 543

2C 647 1E 656

3 497 1F

455 879

352 SURVEY NO : 496 : NO SURVEY

514

2 289

1B 356 356 403 402

354 363

1B 923

354 356

354

360 2 359 1C

656

512 NANJUNDAPURAM 1 497 654 924

360 V.NO:22 365 3 924

V.NO:21 364 935 1D 354

360

3A 581 512 360 356 556 659

1 355 1C 1A 580 1

351 355 4 2 326 2 360

3B 1B 1 365 1 869 581

510 V.NO:21,PANNIMADI 596 364

THADAGAM RESERVED FOREST RESERVED THADAGAM

V.NO:21,PANNIMADI 1 326 2 3 1C 359 655

591

3C1 511 1D 655 596 496 597 544

591 351 1D

591 355

355

THADAGAM RESERVED FOREST RESERVED THADAGAM 597 1 364 366 PROPOSED PIPELINE

594 927

V.NO:21,PANNIMADI

2 454

596 544 3A 1A 2 594 2B 3C2 320 596 2 2

3

582 592 1 593 326 EXISTING TUNNEL

511 594 657

3B

582 511 590 320 590 593 326 320

2C

6A 582 389 320

658

1A 592 3A

1B 1B 595 4 2A 593 592 594

2 2D 595 2 4 366 3B 349 323

595

351 595 597

586 1 1 HILL

588 589 366

589

349 5

588 V.NO:21,PANNIMADI V.NO:21,PANNIMADI 324 2E 2A

2B

319 V.NO:18 KURUDAM PALAYAM KURUDAM V.NO:18

327 325

V.NO:21,PANNIMADI 664 845 V.NO:14.THADAGAM RESERVE FOREST 2

V.NO:21.PANNIMADAI

925

368 367 NELLITHURAI 523 PROPOSED TUNNEL 663

367 845

522

667

665

1 1 1 1

1 2

2 2 524 844 844

4 845

842 814 521 2

FOREST RESERVED

FOREST RESERVED 2 668 NO1 NELLITURAI 1C 1462

789

1 RESERVED FOREST 788

788

3A RESERVED HOLE MAN 842

846 843 FOREST RESERVED 3C

3B 844 NELLITHURAI 1B 3B FOREST HOLE MAN 3A 789

524 1A1 525 RESERVED 843 825 824

FOREST 843 2 3C 845 3A 3

788

1A 967 3B 843 1 842 825 843

2 1A2 982

801

3C 517 1462 3C 828 828

1 CANNAL 967 1

828 824 1B 982 1463 3 515 1 1A

521 RESERVED 1465 1A

526 RESERVED 848 3 521 FOREST MOTORROOM 1 669

3 849

2 FOREST 982

525 967 981 981 1461 848

969 1461 521

966

967 2 963

966 1 981 MARUTHUR

1461

2 2

847

963 847

966 970 980

963 1 771

1461 962 981 823

1C 962 1461 1463 HILLS

969 1A1 1433 1463

975 842

4B 4B 911 970 1432 4B 825

979 980

517 842 787

847 6 CANNAL 1432 2 909 970 1B

2 1431 1B

911 682

4A 4A 4A 1430 4A

1A 975 976 787 786

976 980 1431 1432

3

1D 3A3 1B 979

975

978 1432 1433

1 898 2 1433 1C 1A2 979 1432 1C 1

965 2A 828 828 9 1D 968 1433

2 1

526 CANNAL

112 968 1B BORE 3 828

874 1 2 978 1431

965

3 3 3 2B 976

964 2

1A

4 978 1430 1431 1460

961

1B 4C

520 912 964 965 GUDALUR VILLAGE 4C 4C 1E 3 971 1430 964

908 961 956 1464

1460

2 2

1432

3A2

863 1460 1464

912 961 971 1465

1 2 974 CANNAL

899

533 971

1433

3A1 974

2A2 867 864 1431

899 841 841 841 CANNAL

875 1D 977

526 899 899 908 964 851 2

865 well 956 2

863 908 912 961

1C 1427

875 874 957 1

1434

912

912 956 1429 1429

875 864 958

2 864 864 863

520 908

864 514 957 1427

874 1434 1434

1429 958 1423 3 2C

2B1 959 974

960 958 1428 1 977 841 900 1423 959 959 1429 1427

913 1422

3 27 1427

520 960

1428

1434 7A 1D 28 1

913 1419 KURUDAMPALAYAM 857 907

110 1418 680

1

1428

518 HOUSE RCC 826 826 2B2 1467

2A1 1459 WTP 829

1466

4 2 1459 900 2 829

1467 823

877 823

871 527

518 119

3B

527 871 858 907 913

870 862 CANNAL 67 873 960 959

1

118 900

913

879 2 907 913 2 872 858

1

32 878 900

872

870 7B 960

5 527 3C2

1435 47 856

532 477 47 4 1426

3C1 873

31

870

865 118 856 858 871 857 514 117

29

47 871 862 907 683 2 48 865 3 32

1 2 857 520 48 49

8C 518

528 870 872

528 49

873

8B 29 861 69 877 2B 8A 2A 1B

866 756

528 901

856 736 901

901 1A 906

69 865

867 952

109 2 GUDALUR V.NO:2

115 1 951 1A 867 866

31

873 2 3 906

30

70 914 914 914

116 70 69 906 867 2 859 951 1C

45 30

519

869

109 1 857 862 1B 111 115 31 737 513

46

46 869 867

530 116 68 44 33 30 736

33 2

734

115 494 735 temple

1D 493 108 737

45 30 737 2 866

SURVEY NO : 511 : NO SURVEY 866 866 31 well 2B 71

492 68 31 861

492 1A 33 1 734 865

well 1C 735

498 111 46 NAICKENPALAYAM

519 513 45 1 1A

5 492 116 44

107

108 116 71 2B 870 71 2A 44 34 35 866 35 1B 68 859 33

6A 107 34 855

107 70 V.NO:1

108 NAICKENPALAYAM 733

519 7A 513 1 SURVEY NO : 35

529 104 45 854 6B 3 4 2

477 107 853

738

853 859

106 733 870

853 well house 733 106

2

well house

519 477 111 104 SURVEY NO : 43 house GUDALUR

7C 104 106 35

529 111 42 1 34 SURVEY NO : 34

7B house 43 869

519 house 70 738 738 755 399 513 521 1 44 44

42 34

533 477 2 43 43 684

104 106 42 42 2

732 868 522 1 house 868

522 852 738 SURVEY NO : 533

101 738 513 521 101 73 852

SURVEY NO :534 72 732

512 99 732

5 851

house house 1 868

548 2A 522 72 well

513 521 855 2A2 521 42 851

2A1 513 534 99 534 41

2C 533 house 492 513 34

484 534 1A1 2B

41 104

492 739

511 104 41

485 2A2 522 522 house

521 72 742 742 868

2B3 2C 739

1B2A 533 36

1B1 4 514 535 731 2B2 857 2 36

535 3

520 860

1B house

1 520 house

2B1 523 512 514 535 678 492 105

523 741 684 NAYAKENPALAYAM 100 680

523

520 3A 532 house 484 house

484 3B 2C2 514 4

2

860 520

2C1 1 532 740

492 437

house 536 684

house house 2

2C3 SURVEY NO :523 house 2

511 453 548 485 453 1 SURVEY NO : 99

523 3A2 514

520

3

729 842 729 V.NO.1.Nellithurai 509 3A1 485

485 499 537

1 4A 2D

677 856

453 1A 520 514 841 438 448 1B 531 857

3B2 1A V.NO.1.Nellithurai

485 493 450 512 679 2

685

839

1B house 754

well 4B 515 515 519

2 510

451 519 1 1

3B1 525 524 679

438 1A 515

729 3 524

1C 450

486 486 685 5A1 2

450 518

4C1

493 453

1 5A 483 515 518 525

1B1 493 1 6 2B1 2A1 487

house 98 5A2A

4 454 538 1D

house

436 438

499 436 451 519 1B2

492 1 1D

GUDALUR 491

742 1 3A

4C2 487 1A1 R.F THADAGAM 3B

753 494 499 3

1C 685 3C

486 2 450 4 487

1B2 494 452 2D 5B 2 496 1A 1D

686 492 491 358

496 454

494 495 5A2B

436 449 516 2A2

494 3 435 435 3D 491

2 2A 363 686 2A 357 448 2C 1B

541 5C

439 448 451 452 452

3 1A 439 498 451

1B 398 448 3 498 2B2 742

495 2 449 449 748

489 494 435

2B

491 439

1 452 451

495 742

488 495 714 2A TUNNEL

4 491 495 449 2B 439

495 4B 4 3

236 2 489

489 490 2A

1C

4

2B1 491 1 434 447 399 354 R.F THADAGAM 447 745 399

2B2 2

399 9 434 3

490 2A

490 448 448 448 491 440 447

345

4.THADAGAM RESERVED FOREST RESERVED 4.THADAGAM

1 746 5B1

3A 2B 354 434 447 447 447 447 6J

440 6A 745

RESERVED FOREST RESERVED V.NO.4.THADAGAM

1 447 447 746

345

454 746

468 5B3

7 440 752 490 714

490 4 2 1A 3B 489

430 345 747 3 445 2C 3

240 364 2A

430 1 469 5B2 2C 4 377 5 6B

430 454

399 2 2B 2A 6A4 6A2 434 1 2C 468

2 469 469 1 6A1 440 2D 8A

446 446 1 6I 6

440 2 372 445 469 468

445 446 353 6A3 5B4 445 5 6C2

398 446

431 1 3 6C 3A

2C

5A1 714 344 1B 5A2 352

440 8B

430 6C3 399 440 6H

399 3 4 445

2B

440 6F

445 10A

5B1 378 362 433 6 5B2 433 6C1

431 365 6D 751 1

1A 397 2A 7

2B 429 362 470 429 400 433 1C 3C 467 467 1

379 2 6B

397 379 433 10B 433 429 370 1D 1B 3B 1A 474

352 365 474 741 745

444

2A 441 470 433 444 1 743 6C4

431 156 344 444 474 741

400 366 2C 441

1

400 2 241 441 5 1 369 474

379 170 2A 10C

481 352

444

397 366 2 441 397 1 744

2 2B 397 3 380

2B

1 366 444

366 248 432

369 432 433

380 366 368

368

396 1 248 343 3 442 474 380

428 1 1

346

1 713 2B 442

442

443 3D 10D

323 323 431 743

729 350 442

396 2B

713 396 369 713 346 351

252 346

252 396 2 432

334 351 431 7 400 2 351 1 2C 396 2 2

713 327 350

442 3 350 432 443

400 431 442

169

343 2 729 327 367 475 11

1 351 2A

395 368 430

395 1B 346

401 324 334

369

327 1A 1A 328 350

2A 476 728

395 168 477 SOUTH 401

729

477 4 728 350 GUDALUR

395 380 365 2B 347

431 251 368 5 V.NO:17 347 324 347 NORTH & 367

2 NARASIMANAIKENPALAYAM 328 347 326 430 368

315 322

328 334 2A 324 249 343

1C 328 347 347 1 326

2B 322 1 1B 249

253 253 326

2 349

329 334

343

2

348 1 349 2A 328 1D 1 2

395 325

2C 348 348

380 167 322 349 402

715

1 1 3 366 253 322 3 2

380 325 2 329

454

1 367 366 454 325 2 326 478 715 326 715 2 330

367 2 451 325

716 1 2B

716 450 427

3 315 427

479

717 364

325 3 3 342

446 367 321 330 334

381 342

321 341 339

326 451 329 329 2B

163 4 395

717 330 251

249 3 3 3B 342

381

320 3A

453 330 381 364 446

357

452 162 363 320 2A

1 339

434 368

254

381 162 315 3C 452

318

453 358 342

2 V.NO:17.NARASIMMANAICKENPALAYAM 250 385

198

452

251 445 318 251 321 480

250 250 4A 318

445

198 251 331 318 1

250

364 445

433

443 321

321 2B1 320

434

434

362 254

363 363 459

433 453 4B 370 428

453 320

459 2

2 358

GUDALUR

358 1

431 452 443 2 315

363 430 257 318 256 254 338 362

1

4A 1

435

257

359 437

437 356 4B

359 438 438 161 435 444

254

3A 444 3

257 257

359 356 1 2 3B

354 256

353 430

198 319 424

362 331

432 257

3C 426 359 438 435

438 360 198 256

336

361 V.NO:18,KURUDAMPALAYAM 3 2 437 316

435

425

362 2 161 316

429 2 4 256 437

432 1 1

4

432

KOVIL 442 KARUPPARAYAN

355 2 335 258 5 255 316

259 258

428 332 255 436 2

436 352

428 259 255 360 160

1

361

429 428 382

376

160

260

260 314 333

1A

1B 427

261

159

426 391 157

262 425

149

156 NAICKENPALAYAM NARASIMMA LEGENDS: NELLITHURAI KEY PLAN NANJUNDAPURAM GOVERNMENT LAND PATTA LAND ALIGNMENT HEADWORKS MST LOCATION NAICKENPALAYAM THEKKAMPATTY PANNIMADAI MARUTHUR KURUDAMPALAYAM WTP TUNNEL SOUTH GUDALUR NORTH & NAICKENPALAYAM NARASIMMA Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Annexure II - Proforma for Socio Economic Survey

பில்쯂ர் அணை நீர் லறங்கல் திட்டம், ககோ஬ம்ꯁத்鏂ர் ச믂க பபோ쏁ரோதோ஭ கைக்பக翁ப்ꯁ ஋ண்:

1. ஊர்பப஬ர் :

2. ல쏁லோய் கி஭ோ஫ம் : 3. தோ쯁கோ : 4. 埁翁ம்பத் தணயல쎿ன் :

பப஬ர்,போயினம்

5. தகலல் பகோ翁ப்பல쎿ன் :

பப஬ர்

6. இல쏁க்埁ம் தகலல் : பகோ翁ப்பல쏁க்埁ம் உள்ர பதோடர்ꯁ 7. 믁கல쎿 :

8. ல஬鏁 : 9. கல்லி :

10. 믁தன்ண஫ பதோறில் : 1.லிலசோ஬ம் ( ) 2.埂யிகலணய ( ) 3.அ஭毁ப் பைி ( ) 4.தனி஬ோர் பைி ( ) 5.லி஬ோபோ஭ம் ( ) 6. பிம

11. ச믂க : 1.பறங்埁羿 ( ) 2.தோழ்த்தப்பட்கடோர் ( ) 3.஫ிகퟁம்பிற்ப翁த்தப்பட்கடோர் ( ) 4.பிற்ப翁த்தப்பட்கடோர் ( ) 5. பிம

12. 埁翁ம்பத்தின் லணக : 1.ஒற்ணம நபர்ல ீ翁 ( ) 2.தனிக்埁翁ம்பம் ( ) 3.埂ட்翁க் 埁翁ம்பம் ( )

13. ல ீ翁லணக : 1. 埁羿ணச ( ) 2.கோண்கி쏀ட் ( ) 3.இ஭ண்翁ம்கசர்ந்鏁 ( )

14. ல ீட்羿ல் ஋வ்லரퟁ : 1. ஒ쏁ல쏁டத்திக்埁ம்கீழ் ( ) 2.கடந்த 2 ல쏁டங்கள்( ) கோய஫ோக 3. கடந்த 5 ல쏁டங்கள் ( ) 4. 5 ல쏁டத்திக்埁ம்க஫ல் ( ) இ쏁க்கிமீர்கள் 15. ஋ப்பபோ폁鏁 : 1.ஒ쏁 ல쏁டத்திற்埁ள் ( ) 2.கடந்த இ஭ண்翁 ஆண்翁கரில் ( ) 3.கடந்த ஐந்鏁 ஆண்翁கரில் ( ) கட்羿஬鏁 4.ஐந்鏁 ஆண்翁க쯃க்埁 க஫ல் ( ) 5.பத쎿஬ோ鏁 16. ல ீட்羿ற்கோன உ쎿ண஫ : 1. பசோந்தம் ( ) 2. லோடணக ( )

WAPCOS Limited ii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

17. உத்கதச஫ோக ப஭ப்ꯁ :

18. ஫ின்சோ஭ லசதி : 1.உண்翁 ( ) 2. இல்ணய ( )

19. க஭சன்கோர்翁 : 1. உண்翁 ( ) 2. இல்ணய ( )

20. 埁羿நீர் லசதி : 1.தனிப்பட்ட埁றோய் ( ) 2. பபோ鏁க்埁றோய் ( ) 3. தனி஬ோர் ணக பம்ப் ( ) 4. பபோ鏁 ணக பம்ப் ( ) 5.ஒ쏁 பபோ鏁லோன இடத்தில் அண஫ந்鏁ள்ர ஒ쏁 பதோட்羿஬ில் இ쏁ந்鏁 லறங்கல் ( ) 6. ஆழ்鏁ணரகின쟁 ( ) 7. கின쟁 ( ) 21. பசோந்த஫ோன : 1.ணசக்கிள் ( ) 2.க஫ோட்டோர் ணபக் ( ) 3.ஆட்கடோ ( ) 4.கோர் ( ) லோகைங்கள்

22. : 1. பதோணயக்கோட்சி ( ) 2.லோபனோயி ( ) 3. பசய்தித்தோள் ( ) 4. ணககபசி ( )

5.இணை஬தரம் ( ) 23. நியம் ணலத்தி쏁க்埁ம் : 1. ஆம் ( ) 2. இல்ணய ( ) ஆப஫னில் லில஭ங்கள் 1.போசன நியம் ( ) ப஭ப்பரퟁ 2.஫ோ லோ쎿 நியம் ( ) ப஭ப்பரퟁ 24. கோல்நணட லில஭ம் : 1. ஆம் ( ) 2. இல்ணய ( )

ஆப஫னில், ஋த்தணன இ쏁க்埁 கோல்நணட ( ) பலள்ரோ翁 ( ) ஫ற்쟁ம் ககோறி ( )

25. 埁翁ம்பலில஭ம்

ல பப஬ர் 埁翁ம்ப ல஬鏁 போல் தி쏁஫ைலிப஭ம் 믁தன்ண஫பதோறில் ஆண்翁

஋ண் தணயல쏁டன் ல쏁஫ோனம்

உள்ர உமퟁ

26. ப஫ோத்தல쏁஫ோனம் :

27. நீங்கள் இறக்கப் : 1. நியம் கபோ埁ம் பசோத்鏁 போசனம் ( ) ப஭ப்பரퟁ

WAPCOS Limited iii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

஫ோ லோ쎿 நியம் ( ) ப஭ப்பரퟁ

2. ல ீ翁

埁羿ணச ( )கோண்கி쏀ட் ( ) இ஭ண்翁ம்கசர்ந்鏁 ( )

ல஬யில் உள்ர ப஬ிர்கள் ஫ற்쟁ம் ப஭ப்பரퟁ:

1.

2.

3.

4.

5.

1.

2.

3.

4.

5.

28. நி஬ோ஬஫ோன இறப்பீ翁 : 1.ஆம் ( ) 2. இல்ணய ( ) லறங்கப்பட்டோல் இல்ணயப஬ன்மோல் கோ஭ைம் உங்க쯃க்埁 பகோ翁க்க லி쏁ப்ப஫ோ 1.

2.

WAPCOS Limited iv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

29. நீங்கள் பசோத்ணத : இறந்தோல், நீங்கள் சந்திக்க கலண்羿ல쏁ம் இ쏁 லிணரퟁகள்

30. இந்த திட்டத்தினோல் : ச믂கம் ஋திர்பகோள்쯃ம் லிணரퟁகள் தோல鏁 இ쏁ப்பின் 埂쟁க

கண埍கக翁鏍தவரின் கெயர் ம쟍쟁ம் கககயொப்ெம் கததி:

WAPCOS Limited v

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Annexure III - Focus Group Discussion report Focus Group Discussion 1 Village name : Marudur Revenue village : Marudur village Taluk :Mettupalayam Venue : Village Panchayat office Date : 22.02.2020 Participants : Around 20 Project affected persons and their family members and the ex and current panchayat leaders Major concerns and points discussed and conclusions arrived during the FGD:  It is a mixed group of farmers of irrigated land and dry land and owners of house sites meant for building houses in the future. Some of them are not the local residents; they are absentee farmers and house plot owners from outside. A few women farmers also participated in the meeting.  The project affected people and some of the other village leaders assembled informed that there has been no official NEWS and official communications regarding the proposed project and land acquisition. They opined that they should be properly informed about the objectives and other details of the project.  The people expressed that already a few other water supply scheme are in operation and few more schemes have been formulated from which will reduce the local storage of water hence will result in the depletion of Ground Water Table in the surrounding area. The excess take-off of water from the river will also slowly lead water scarcity in the downstream areas.  The project affected people feel that no information is provided about the alignment design and reliability of the project. They informed that the planting of boundary stones in the field was carried out without the permission from the land owners.  The project affected people have not been served with notices regarding the land acquisition with survey numbers and have no data with respect to the amount of

WAPCOS Limited vi

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

land (in figures) that is proposed to be acquired under the project. Therefore demanded to circulate the GO’s to PAPs.  One of the owners of Maruthi Nagar, approved layout expressed his concern that the pipeline is passing through his plot purchased for construction of house. As the proposed pipeline is passing the plot the remaining land upon acquiring the required land cannot be used for construction of the house and therefore it was requested to acquire the entire plot and provide a fair compensation as per the market value or provide an alternative site for construction of the house.  Few of the projects affected small and marginal holders informed that the only source of income is through agriculture. If the land is acquired by the government is will affect daily livelihood. Hence, expecting a fair compensation.  Some of the participants expressed their concern that the Bhavani water in non- rainy season is just sufficient to meet Metupalayam domestic and agriculture needs then sometimes this next project to carry water to Coimbatore will deprive their water need.  The project affected people and other people expressed their fear that due to take- off of the river water the ground water table may get depleted and as most of the agriculture depends on water the yield will be affected.  One of the women project affected person envisaged that down the line by 10 years their shall be no water for the agriculture as more and more schemes are formulated from Bhavani River and hence, it will be necessary to migrate to city for making a living.  The project affected people remarked that the project benefits many people of Coimbatore Corporation. But compensation need to be paid is only a small number compared to the number of project beneficiaries, therefore the govt can be liberal in fixing the compensation to the land going to be acquired.  The project affected people expressed their fear that in few projects where land has been acquired no compensation is paid till now, hence project affected people have demanded that the amount finalized for compensation is to be paid before the registration.

WAPCOS Limited vii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 Few of the project affected person requested that one of the family member should be considered by the government to provide a Job in the present scheme so that the family is not affected by the land acquisition and benefitted by the Job.  At last the project affected people said there are experiencing meetings fatigue, that too many meetings are held without any concrete conclusions.

Participants list S.No Name 1 V.Velusamy 2 Kandasamy 3 D.Ravi 4 M. Sundaraman 5 V.Ramasamy 6 N.Sundarajan 7 S.Jayaraman 8 Gopalsamy 9 N.Manokaran 10 Nagasubramanian 11 V.Srinivasan 12 P.Ranganathan 13 R.Manikandarajan 14 R.Amirthalingam 15 Chinnaraj 16 S.Nanjamma 17 Saraswathi

Focus Group Discussion

WAPCOS Limited viii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Focus Group Discussion 2 Village name : Thottathasanur (North) Revenue village: Thekkampatty Taluk : Mettupalayam Venue : Farmer’s house Date : 22.02.20 Major points discussed and concerns of the participants:  Farmers told that the discussion about the project since 2013 hence now they doubt the credibility of the project.  Some of them told that they were not informed when the boundaries were marked.  Farmers told they are emotionally attached to their lands if they lose the land with such value they need to be compensated with a fair amount which will meet their satisfaction.  Some of the farmers who are small and marginal holders in the group feel taking land for laying of pipeline would affect their livelihood, certain portion of their land have been already affected due to TNEB towers. Hence requested to find an alternative lay out. These farmers may lose nearly half of the land they owned.  Another reason why the people don’t want this project it my increase the chances of wildlife intrusion from the reserve forests of Vellimalai and Kannuvai malai – the roan laid will be an easy route for the wild life to reach their farmers. Govt should take the responsibility and provide compensation if the standing crop is lost.  Depletion of ground water will happen if water in the Pillur dam is taken regularly during the summer months when there is not enough water in the dam. This point was clarified by the team that water will not be taken if the level is below certain point as indicated in the proposal.  People fear that the Pillur pipeline project will lead to fragmentation of land, some cases this may create a narrow piece of land on side or either sides of the pipe line, and the will not be suitable to do farming. They are doubtful whether they will be allowed to take water from the bore well from one side to the other side of the lay out.

WAPCOS Limited ix

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 Mr.Sundarlingam, one of the farmers told that he bought 1 acre of land for Rs. 40 lakhs but the government may not pay that much amount, hence he feels he cannot buy the land for an equal amount of land with the compensation amount received.  The participants of the group requested to consider their demand for local supply of water from the scheme when water scarcity in the area.  One of the villagers Kalavathy, says it is her ancestral property hence has emotional attachment hence the govt should pay fair compensation.

Participants list S.No Name Age 1 Varatharajan 51 2 Murugan 51 3 Rangaraj 60 4 Pathirammal 59 5 Kalavathy 45 6 Sarojini 50 7 Rajamani 55 8 Shanmugam 63 9 Sivarama lingam 58 10 Murugesan, 42 11 Nagenthran, 55 12 Velumani, 47 13 Raja Gopal 59 14 Palaniappan 70 15 Shanmuga sundar 58 16 Thiruvengadam 54

Focus Group Discussion Household Survey

WAPCOS Limited x

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Focus Group Discussion 3 Village name : Narasimhanayakan palayam Revenue village: Narasimhanayakan palayam Taluk : Coimbatore -north Venue : VAO office Date : 23.02.20 Participants : Project affected persons and their family members Major points discussed and concerns of the participants:  Most of them are small farmers and marginal farmers. There are two big farmers with 8 to 10 acres of land.  Mostly dry land owners and they grow cow pea, horse gram, sorghum and kudurai masal – fodder crop. A few of them also grow coconut and teak.  According to them most of them would lose for the water supply quarter to half of the area of the land they own.  The farmers want to know more about the project and the govt departments involved in the project, they are not very clear about who is responsible for taking decisions and implementing the project etc.  The farmers want to know about the methodology, how much they get as compensation for the land, tree crops and other assets they will lose to meet the project needs.  Thennai, thekku vembu are the trees growing in this area. They have a high market value hence expecting a high rate for these tree crops.  Some families expressed that they wanted their ancestral land to pass on to next generation as they received from the previous generation. Now this may not happen as they wish.  They felt that they may lose more area of their agricultural land, the other worry is apart from this scheme, they may need to provide their land to the proposed ring road project.

WAPCOS Limited xi

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 The people are skeptical due to the bad experiences of some other farmers affected in other projects. They also fear that all proposals and promises made by the government are just empty promises.  Certain amount of land area going to be acquired from the villagers are dry lands and unfit for doing irrigated agriculture.  They have been working as farmers in the same land for the last four generations and hence they feel bad to lose of their ancestral property.  Farmers feel that the implementation of this project will lead to fragmentation of land into smaller pieces rendering them useless for cultivation.  As the people here mostly depend on agriculture for their livelihood, they want compensation for their loss in accordance with market value, but there is no consensus about the market value.

Participants list S.No. Name Age 1. Devaraj 65 2. Ramesh 48 3. Shanmugam 54 4. Duraisami 58 5. Kanagaraj 56 6. Rajalakshmi 80 7. Naveen kumar 26 8. Venkatesan 71

WAPCOS Limited xii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Focus Group Discussion: 4 Village name : Thottathasanur (North) Revenue village : Karudampalayam Taluk : Mettupalayam Venue : VAO - office Date : 29.02.20 Participants : Project Affected persons and their family members Major points discussed and concerns of the participants:  The primary occupation of residents of the village is agriculture. The land owners are heterogeneous groups, include small and marginal, medium size and large holders. Some of them own livestock.  While agriculture is definitely is the main source of income, some of them are working in the private companies and a few are involved in petty business to earn their livelihood.  The main concern of the project affected people is that they are properly informed about the water supply project, they know very little about the project, not very clear about the objectives of the project. They like to get more information and details about the project to get a holistic understanding about the project.  They want the road built over the pipelines to be made open for public use.  Impact will fragmentation of agriculture land, need to make fencing to protect the crops from wild life intrusion, and which will involve cost.  The people demand the market value for their lands from the government. They wish to have a meeting with the higher officials like district collector to press their demands.  Apart from private land, the land acquisition includes the temple land belonging to two temples one for Lord Vettaikaran (64 cents) and other one for Lord Veerabathraswamy (27 cents), the local committee managing the land is willing to provide the land to the scheme.  It was reported that one large holder his name is Mr. Elango owns more than 10 acres of land and going to lose nearly 7.5 acres of land. He is willing to give the

WAPCOS Limited xiii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

land provided the government pays a fair compensation either cash or equal area of land.

Participants list S.No. Name Age 1. Elango 63 2. Raja Gopalan 78 3. Prasanth 30 4. Santhamani 56 5. Rangasamy 69 6. Elangovan 23 7. Thiyagarajan 63 8. Lakshmi 56 9. Ravi 50 10. Sivakumar 54 11. Marisami 60

Focus Group Discussion Household Survey

WAPCOS Limited xiv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Focus Group Discussion: 5 Village name : Pannimadai Revenue village: Pannimadai Taluk : Coimbatore (north) Venue : VAO - office Date : 29.02.20 Participants : Project Affected persons and their family members Major points discussed and concerns of the participants:  The dominant community residing in the village are called as Kurumba goundars also called as Kurumbars (most backward classes)  Most of the participants are illiterate farmers, among the participants one is physically challenged name Mr. Ramasamy age 39.  The primary occupation of the people of this village is agriculture and they also own livestock. 75% of the farmers among them come under small farmers’ category. These small farmers are largely dependent on their livestock; through this they get additional income like selling milk in the open market.  Small holders losing nearly one third of the land is going to make them extremely vulnerable.  Mrs.Malarkodi, a women farmer in the group mentioned that since the family member are not educated their only source for income is from the land and they can only rely on land and agriculture, if the govt decides to take away the land it need to support to meet our livelihood needs.  Some of the farmers mentioned that they have attended a few meetings before conducted by the departments, but the need more information about the project and the final decisions about the compensation they will get, and to avoid have meetings and waste the time they like to hear final decisions from the departments.  Wildlife intrusion and destruction of crops is a big issue faced by the people of this village, they are not sure how the new plan and road laid over the pipe line is

WAPCOS Limited xv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

going to impact, they are worried that sometimes the new road facility may create an easy access to the agricultural fields for the wild life.  Fragmentation of the land due to the project may cause a problem for the farmers, if the lands are divided in to two pieces on both sides of the road, they may face difficulty to irrigate the lands. Moreover they need to fence the lands on both sides which will increase the cost of the land’s maintenance.  In the previous meetings the farmers are not happy with the rate proposed, told the department officials to increase, and the officials promised that they would consult the higher authorities and get back but haven’ t heard anything about the rate after that. Now they like to know the final rate of compensation.

Participants list S.No. Name Age 1. Karupasamy 45 2. Malarkodi 46 3. Arusami 39 4. Natraj 62 5. Rajendran 60 6. Rangasamy 60

Focus Group Discussion Household Survey

WAPCOS Limited xvi

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Focus Group Discussion: 6 Village name : Nayakanpalayam Revenue village : Nayakanpalayam Taluk : Coimbatore (north) Venue : VAO - office Date : 01.03.20 Participants : Project Affected persons and their family members Major points discussed and concerns of the participants:  The dominant groups in the village are Vellala koundars, Okiliya koundars and Naidus.  Most of the household heads have completed their school education and a few have also gone to college and completed their bachelor and master degree. The main occupation is agriculture or labourers in the farms, some of them work in private companies, and do business.  Farmers do irrigated and dry land farming, coconut groves and banana cultivation are major crops in the irrigated fields, sorghum is cultivated in the dry lands. Bore wells are the source for irrigation and drip irrigation method is used to save water. The farmers are worried that the drip system laid will be disturbed due to this project.  The govt can fix the land value keeping in mind the increase of land value.  They insist that the land should be used to lay the pipe line only after the compensation is paid for the land.  TNEB has already acquired some portion of their lands to erect the high tension towers which have already fragmented their lands. They do not want their get further fragmented and the remaining land become unfit to do any farming.  A few want to know whether the alignment can be changed, the current alignment is dividing the lands into irregular pieces, it will be difficult to irrigate the lands or late if they want sell, no one be willing to buy the land.

WAPCOS Limited xvii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 The farmers proposed that they want the unused government lands adjacent to the acquired lands can be leased for about 20 years for a nominal amount for doing agriculture and generate some income and meet the loss.  They also demand the compensation for fencing and maintenance of the newly fragmented lands. They want the expenditure of the same can be added in the compensation package.  They also want the payment to be made immediately after the land acquisition. According to some of the farmers what they heard about the experiences of farmers who provided the land for the govt scheme and also read in the newspapers were not good due to payment delay and farmers need to go after the department for the settlement.

Participants list S.No. Name Age 1. Alwar 61 2. Balaji 40 3. Duraisami 64 4. Chinnaraj 38 5. Damodaran 68 6. Vijay Lakshmi 60 7 . Radhakrishnan 22 8. Immanuel 50 9. Mani Maran 52 10. Kanagaraj 60 11. Guna sekaran 56 12. Niraimathi 36

Focus Group Discussion Household Survey

WAPCOS Limited xviii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Focus Group Discussion: 7 Village name : Nanjundapuram Revenue village : Nanjundapuram Taluk : Coimbatore (north) Venue : VAO - office Date : 01.03.20 Participants : Project Affected persons and their family members Major points discussed and concerns of the participants:  It is a heterogeneous village, families of different communities are residing in the village, they are Kurumbas, Yadavas, Chettiars, Naidus, and Vellala goundars.  Primary occupations of the majority of the families are agriculture and work for daily wages.  Majority of them are small and marginal holders and mostly have dry lands. Bore well is source for irrigation. The few who have irrigation facility own coconut grooves. The other two main crops cultivated using irrigation is banana and sugarcane. In the dry land they cultivate sorghum, green gram and redgram.  Although the land owned by the families are small in area, they could manage to get regular income.  The amount of land they may lose in some of the small holders is more than 50% of the land they own. Hence, worried about the loss of income they get from the fields. These small holders are demanding whether the govt can provide any job opportunities created in the project to make their livelihoods. The other option suggested is the vacant govt land located adjacent to the village can be give to the farmers as compensation or on long term lease basis minimum for 20 years lease.  The people like to know or the department should clearly communicate how the department will calculate and finalize the compensation amount.  The farmers expect fragmentation due to project will result in additional expenses to make fencing, rearrange the irrigation system particularly the drip irrigation system.

WAPCOS Limited xix

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 They want the road over the pipeline to be made open for public usage and they demand a written pledge from the government assuring the same.

Participants list S.No. Name Age 1. Viji 35 2. Arumuguan 78 3. Nataraj 62 4. Kanagaraj 44 5. Rangasamy 51 6. Ravi Kumar 34

Focus Group Discussion Household Survey

WAPCOS Limited xx

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Focus Group Discussion: 8 Village name : Gudalur (North) Revenue village: Gudalur (North) Taluk : Coimbatore (North) Venue : VAO - office Date : 01.03.20 Participants : Project Affected persons and their family members Major points discussed and concerns of the participants:  Majority of the people of this village belong to the Backward Community and a few belong to the Most Backward Community and Scheduled Caste.  Primary occupation of the families is agriculture, some families depending on wage labour in the neighbouring farms or other opportunities available to work as wage labourer.  In general here people are well educated, the most of the younger generation have completed till college education.  The lands are usually dry lands grow Sorghum as a fodder crop.  Some of the farmers may lose 50% of the total amount of the land they own, they mentioned that they don’t want to say no to the project, but expecting fair compensation for the land they will provide for the project.  Some of them have already lost some portion of the land for TNEB to erect the towers. Since in some plots in the same land the new project also planned, they may find the land will be fragmented and become difficult to do agriculture.  Some of them are not happy about the uniform rate going to be fixed for the land, they insisted that the department need to consider the market value and fix the rate accordingly. Otherwise the uniform rate may result in providing lesser amount of compensation for some of the lands which have very high market value.  People think laying road over pipe line may increase the wildlife intrusion in to the agriculture fields and destroy the crops.

WAPCOS Limited xxi

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 The fragmentation due to the project may affect the land area and become unfit for cultivation, in such cases, if it is very narrow piece, the govt can take the narrow piece also or pay compensation to the area.  No final decisions are arrived in all previous meetings, the department officials were also not very clear about the impacts and the compensation can be made. Hence, the suggestion from the farmers is that when they are called for the next meeting the officials should come with concrete proposals which can be negotiated and finalized with the affected farmers.  The people want the road that would be laid over the pile lines should be open for villagers use.  The land that would be fragmented into two parts, this will create problem particularly for taking water from one side to the other side.  Farmers suspect that they may not get the compensation amount immediately after the land is acquired, hence skeptic about the disbursement of the amount to the farmers by the department immediately, therefore insisting that the department should promise and pay the amount without any delay and a methodology need to be worked out for the payment on mutually agreeable terms and conditions. Participants list S.No. Name Age 1. Rajenderan 52 2. Gurusamy 70 3. Jaishankar 39 4. Subramanium 58 5. Vasudevan 56 6. Krishnamoorthy 60 7. Arunkarthikeyan 40

Focus Group Discussion Household Survey

WAPCOS Limited xxii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Focus Group Discussion: 9 Village name : Gudalur (south) Revenue village: Gudalur (south) Taluk : Coimbatore (north) Venue : VAO - office Date : 01.03.20 Participants : Project Affected persons and their family members Major points discussed and concerns of the participants:  The communities that live in this village are Backward Community, Most Backward Community and some of them are from Scheduled Caste called Arunthathiyar.  Regarding the primary occupation it is mixed, predominantly agriculture, govt staff, business and one section is wager labour. Among the land owners a considerable number of farmers are medium and big size holders.  Most of the farmers have irrigated lands and only a few have dry lands. On the irrigated lands they grow sorghum, vegetable and floriculture crops like tomatoes, cucumber, oleander, chrysanthemum, sambangi, banana and tree crops like coconut and areca nut.  Out of the 16 project affected families, two are female headed households.  Farmers reported they didn’t get any concrete information about how the compensation is going to be calculated, they are confused with the rates whether based on guidelines, market or an arrangement to consider both values etc. Hence the suggest if the meeting is organized the department should come out with the method and how much amount the farmers will get for the land they are going to lose.  The land going to be acquired are fertile lands and some of them are with prenial standing crops like herbs and medicinal plants, they may face a big lose in their annual income due to uprooting of the plants, hence expecting to provide compensation for such crops.

WAPCOS Limited xxiii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

 The intrusion of wild animals into the farmlands is an issue faced by the people. Every year they destroy near 100 to 200 acres of crops, now they expect the problem may increase due to the new road is going to be laid.  Some of them have already lost a portion of their lands, acquired by TNEB for constructing towers, if the alignment is in the same land they will lose another portion of the land and will get divided and fragmented, they expect they may face practical problems for ploughing and irrigation etc.  The participants proposed an alternative route passing through forests and mountain areas, but it was clarified that forest land cannot be used for any developmental purpose as per the forest act, hence it cannot be considered.  The farmers said that they will sign the official document only if they are convinced the rate fixed for the land and tree crops.  The people want the government to consider the same pipe line can supply water to their area and if extra to fill the nearby water bodies. It was told this they can discuss with the officials in the next meeting.  The farmers also make a demand they compensation can be if any job opportunities are created in the project, or allocate the unused govt land to do cultivation on long term lease basis for doing agriculture and get some additional income.

Participants list S.No. Name Age 1. Uma 41 2. Rathhanasamy 66 3. Devaraj 69 4. Krishnaveni 46 5. Nanjammal 70 6. Palaniswamy 59 7. Ravichandran 47 8. Duraiswamy 70

WAPCOS Limited xxiv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

9. Mohan 50 10. Durairaj 53 11. Jagadeesh 32 12. Babu 42 13. Muruganatham 49 14. Iyappan 55 15. V.Duraisamy 62

Focus Group Discussion Household Survey

WAPCOS Limited xxv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Annexure IV - Details of Village wise project affected people Thekkampatty Village Land Classification Details of Sl.No Survey No/Sub Acquisition Name of the Owner Family Division No (in Hectares) 1. 899/3B 0.05.50 Dry Land Amirtham W/o Suburayan 1 899/3A 0.05.20 Dry Land 897/3A 0.01.50 Dry Land 897/3D 0.01.00 Dry Land 897/1A 0.01.15 Dry Land 680/1A/A 0.26.74 Dry Land 682 0.19.60 Dry Land 669 0.09.10 Dry Land 668 0.14.30 Dry Land 667 0.15.24 Dry Land 2. 896-3 0.19.70 Dry Land 1.Balasubramaniyam 2 2.Velumani 3. 896-1 0.06.62 Dry Land RamKrishnan S/o 1 4. 895-3B 0.07.58 Dry Land Sivamani S/o Saravanan 1 889-3 5. 895-1 0.05.47 Dry Land 1.chellammal W/o Kalimuthu 2 889-1 0.00.29 2.Kalpana S/o Kalimuthu 6. 891/3B 0.00.64 Dry Land Nasappan S/o 1 900-2 0.09.40 VenkataramaGounder 7. 900-1 0.06.80 Dry Land Amirthalal Jain S/o 1 AmirthalalRuph Chand 8. 789/101 0.17.29 Dry Land Balan S/o Subbaiyyan and 51 25 others 9. 789/10 0.03.06 Dry Land Veeraragavan S/o Ramasamy and 3 2 others 10. 788-1 0.56.75 Dry Land Rukhmani 6 11. 824/1 0.09.20 Dry Land 1.Rameshkumar 2

WAPCOS Limited xxvi

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Land Classification Details of Sl.No Survey No/Sub Acquisition Name of the Owner Family Division No (in Hectares) 824/2 0.03.10 Dry Land 2.Senthilkumar 824/3 0.21.50 Dry Land 12 828-3 0.14.78 Dry Land Selvappan 1 13 844 0.00.77 Dry Land Thangavel S/o Rangasamy 1 Mudalaiyar 14 842/3A 0.11.57 Dry Land Subbaiyyan 3 845/2D 0.07.88 15 842/3B 0.06.15 Dry Land Sarojini 1 16 842/3c 0.06.24 Dry Land Vimala 1 17 847/1 0.05.68 Dry Land Rajan 1 18 849 0.24.14 Dry Land Thalammal and 50 others 30 19 851 0.30.33 Dry Land G.Vijayaprakash and 1 person 2 20 756 0.22.00 Dry Land Mahalingam and 41 others 25 21 855 0.19.04 Dry Land Kumar and 8 others 5 856/1B 0.06.19 22 856/1C 0.06.90 Dry Land Saruk 3

23 857/1 0.04.98 Dry Land Jesudos Thomas S/o Girigoori 1 857/2 0.05.02 24 857/3A 0.03.30 Dry Land Benjamin Vincent babu and 3 4 others 25. 857/3B 0.03.30 Dry Land Visalakchi W/o Ponnusamy and 2 3 others 26. 857/3C 0.03.50 Dry Land Chinnasamy and 2 others 3 857/3D 0.03.50 857/3E 0.02.80 27. 857/3F 0.06.40 Dry Land Amudha W/o Sengon and also 6 7 others 28. 857/3G 0.09.72 Dry Land Govindharaj and 7 others 8

WAPCOS Limited xxvii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Land Classification Details of Sl.No Survey No/Sub Acquisition Name of the Owner Family Division No (in Hectares) 29. 747/5A 0.00.95 Dry Land Rangammal and 11 others 12 30. 747/6 0.01.30 Dry Land Nishamanth Nisha W/o Karim 10 746/1 0.07.38 and 17 others 31. 746/5A 2A 0.08.62 Dry Land Rangasamy and 24 others 15 32. 746/5A 2B 0.08.54 Dry Land 1.Suresh Hitech 2 2.Maithili W/o Gunasekaran 33 745/3A 0.02.80 Dry Land Pommappan 1 34. 745/3B 0.03.06 Dry Land Subalakshmi and 5 others 6 35. 745/3C 0.02.52 Dry Land Pathirammal and 2 others 3 745/3B 0.01.10 745/4A 0.01.70 36. 745/4B 0.11.82 Dry Land Balasubramanian S/o Ramasamy 1 37. 742/1A 0.01.92 Dry Land Jayanthi S/o Raju 1 742/1D 0.45.60 742/3 0.08.14 38. 684/1B 0.11.90 Dry Land Veerapathiran 1 984/2 0.01.84 39. 665/1 0.08.59 Dry Land Sivapughazh 1 40. 664 0.11.70 Dry Land Velliyangiri 1 41. 657 0.19.08 Dry Land Govinda Gounder and 21 others 15 42. 654 0.25.82 Dry Land Latha S/o Soundarrajan and 3 4 others 43. 653 2.37.60 Dry Land Thangavelu and 2 others 3 44. 652 0.21.20 Dry Land Natarajan 1 45. 651-2 0.07.06 Dry Land Karruppan and 5 others 6 46. 260 0.53.15 Dry Land Nirajanbabu S/o Sitaraman 8 9 others 47. 261 0.46.30 Dry Land Sivaramalingam and one person 5 264 0.28.85 Punithavathi and 2 others

WAPCOS Limited xxviii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Land Classification Details of Sl.No Survey No/Sub Acquisition Name of the Owner Family Division No (in Hectares) 48. 263 0.30.05 Dry Land Shanmugam and 15 others 16 49. 258/1B 0.05.90 Dry Land Amudhaveni W/o Velumani 1 50. 258/1C 0.01.10 Dry Land Eswari W/o Subaiyyan 1 51. 258/2 0.21.20 Dry Land Rukhmani and 3 others 4 52. 257/1 0.23.70 Dry Land Saranvel S/o Palanisamy and 8 9 others 53. 256/1 0.22.60 Dry Land Muthusamy and 8 others 9 54. 255/1 0.10.35 Dry Land Shanmugam and one person 2 55. 255/2 0.02.40 Dry Land Palaniyappan S/o 1 Soundhapandaram 56. 255/3 0.01.05 Dry Land Murgesh S/o Ramasamy and 3 4 others 57. 117/1C 0.19.10 Dry Land Varadharajan and 2 others 3 117/1M 0.11.70 Varadharajan and 5 others 6 117/1L 0.00.25

58. 117/1N1 0.07.00 Dry Land Pathirammal 1

59. 117/1I2 0.00.70 Dry Land Pathirappan s/o 1 MarudhappaGounder 60. 2/1A 0.05.10 Dry Land Rangasamy Gounder 1 2/1C 0.04.50 61. 2-1 B 0.04.65 Dry Land MaranaGounder S/o 1 2-1D 0.04.60 MarudhappaGounder 62. 2-1E 0.00.80 Dry Land Rangasamy S/o 1 MarudhappaGounder 63. 2-1G 0.00.40 Dry Land MaranaGounder and 7 others 8 64. 2-1J 0.19.55 Dry Land Ramasamy and 5 others 6 65. 3-1 0.09.30 Dry Land Thiruvenkadaraj s/o subbaiyyan 1

WAPCOS Limited xxix

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Land Classification Details of Sl.No Survey No/Sub Acquisition Name of the Owner Family Division No (in Hectares) 66. 3-3 0.04.30 Dry Land Ponnusamy S/o Subbaiya 1 Gounder 67. 3-5 0.06.55 Dry Land Murugan S/o Ramasamy 1 Gounder 68. 4/1B 0.18.30 Dry Land Pathiran S/o Periyaranganathan 1 5/2 0.08.25 69. 4/2a 0.07.00 Dry Land Ganapathy S/o Periyaranganathan 1 5/1 0.09.25 70. 210-1 0.05.00 Dry Land V.J.lakshmi Textiles limited 1 210-2 0.05.15 210-3 0.03.60 71. 210/4 0.00.15 Dry Land Muthan S/o Vedan 1 72. 210/9 0.10.80 Dry Land V.J.lakshmi and 2 others 3 73. 397/1B 0.01.95 Dry Land Marammal and 5 others 6 74. 397/2B 0.04.20 Dry Land Super sales Agencies 1 1F, 0.06.15 1G, 0.07.40 3A, 0.13.50 392/2 0.14.50 1A 0.05.40 1B2 0.05.50 75. 355/1C- 0.16.10 Dry Land R.Boopathi Kannappan 2 3I 0.02.30 76. 355/1D 0.00.35 Dry Land BoojijayaGounder and 2 others 3 77. 355/3E 0.00.45 Dry Land ChinnaSamy and 10 others 1 78. 355/3G 0.06.15 Dry Land Vijaya (or) Dhanalakshmi 1 79. 355/3H 0.06.15 Dry Land Sundarammal 1 80. 352/2 0.17.20 Dry Land Samraj 1 354/3B1 0.01.60

WAPCOS Limited xxx

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Land Classification Details of Sl.No Survey No/Sub Acquisition Name of the Owner Family Division No (in Hectares) 81. 353/2 0.23.20 Dry Land Malaika W/o Natarajan and one 2 person 82. 354/382 0.06.10 Dry Land Malarvizhi 1 209/1A 0.02.10 83. 209-1B 0.02.90 Dry Land Santhamani s/o Chinnasamy 1 84. 345 0.11.70 Dry Land Varadharajan and 1 other 2 85. 344-3 0.15.05 Dry Land Pathirappa Gounder 1 86. 343-5 0.01.50 Dry Land Pathirammal 1 87. 343-4 0.09.90 Dry Land Rangasamy 1 88. 343-2 0.06.65 Dry Land Paramasivam and 1 other 2 89. 319 0.06.80 Dry Land Rangasamy and 1 other 2 Total 355

WAPCOS Limited xxxi

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Marudhur Village Survey Name of the Owner Land Acquisition Details of Sl.No No/Sub Classification (in Square Meter) Family Division No

614/5 Dry Land 0.05.90 S.C.Rangasamy 1 1. Dry Land 1.Murugaiyyan S/o Bhoojingounder 2. 614/8 2.Kandasamy S/o Bhoojingounder 0.05.21 3 3. 614/8 3.DuraisamyS/oBhoojingounder

Dry Land 1.Savitiri W/o Selvaraj Rahul S/o Selvaraj Janani D/o Selvaraj 2.Ganesan S/o Kuppusamy Gounder 3.Somasundaram S/o Kuppusamy Gounder 4. 601 0.07.94 6 4.Nagaraj S/o Kuppusamy Gounder 5.Vijayalakshmi W/o Elango 6.Aruchamy S/o Kuppusamy Gounder

602/4 Dry Land 0.05.82 Janakiyammal W/o Subaiyyagounder 5. 2 603/1B2 0.02.36 Ramasamy S/o ThottannaGounder Dry Land ThottannaGounder Subaiyyan S/o ThottannaGounder 6. 603/1B2 0.02.36 1 Ranjithkumar S/o Palanisamy

7. 600/4 Dry Land 0.01.44 Ramasamy S/o Rangasamy Dry Land Ramasamy S/o NachappaGounder 599 0.16.96 2 Velliyangiri S/o Rangasamy 8. 9. 588/1 Dry Land 0.05.72 Kalamani W/o Nagarajan 1

WAPCOS Limited xxxii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land Acquisition Details of Sl.No No/Sub Classification (in Square Meter) Family Division No Dry Land 10. 588/2 0.04.26 Palanisamy S/o Rangasamy 1

11. 588/3 Dry Land 0.03.02 Rangaraj S/o GovindaGounder 1 12. Dry Land 0.07.20 Rangasamy S/o KalappaGouder 1 588/4B 0.05.76 634/5

576 Dry Land 0.03.11 13. Padmavathy W/o Rangasamy 1 577/1 0.07.81 14. 577/3 Dry Land 0.07.73 Rangammal W/o Rangasamy Gounder 1 15. 577/4 Dry Land 0.05.37 Revathi W/o Rajendran 1 577/5 Dry Land 0.04.81 ThavudurappaGounder S/o Ramayya 16. 1 572/2 0.27.20 Gounder 565/3A Dry Land 0.06.07 634/1 0.00.67 17. Ramasamy S/o Venkadusamy Naidu 1 563/1 0.12.27 563/2 0.00.28 Dry Land Viswanathan S/o Palaniyappan 565/3B 0.00.51 Saroja W/o Viswanathan 634/2 0.06.48 Srinivasan S/o Viswanatahn 18. 563/2 0.00.28 1

560/2 0.03.11 Viswanathan S/o Palaniyappadevar 634/5 0.05.76

564/1A Dry Land 0.11.96 19. Kandasamy S/o Pandithan 1 564/1B 0.07.90 Dry Land Indirani W/o Narayanasamy 563/1 0.12.27 20. Karthikeyan S/o Narayanasamy 1 563/2 0.00.28

WAPCOS Limited xxxiii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land Acquisition Details of Sl.No No/Sub Classification (in Square Meter) Family Division No Kanakamani W/o Senthilkumar

Dry Land Rajeswari W/o Yadukulamthilagam 1 21. 560/1 0.01.70 Banumathi W/o Velusamy 1 Dry Land Murugesan S/o Kuzhandaisamy Mudaliyar Vijayagopal S/o Krishnasamy Naidu 560/2 0.03.11 Selvaraj S/o Krishnasamy Naidu 22. 1 560/3 0.11.25 Manogaran S/o Krishnasamy Naidu Banumathy W/o Krishnasamy Naidu Rukhmani W/o Krishnasamy Naidu Dry Land Rajagopal S/o Ponnusamy 23. 560/3 0.11.25 1 Govindaraj S/o Ponnusamy 24. 188 A/1 Dry Land 0.00.42 Kumarasamy Gounder and 12 others 6 25. 188 B/1A Dry Land 0.12.45 Rajamani and 17 others 4 26. 191/1D2 Dry Land 0.00.52 Ramasamy and 13 others 7 27. 19/1D3 Dry Land 0.11.10 Palanisamy and 7 others 5 Dry Land Manikkavasagam S/o Chinnayya 28. 191/1E 0.00.70 1 Mudaliyar 29. 191/1C2 Dry Land 0.00.21 Murugasamy S/o Kandasamy 1 30. 206/1B Dry Land 0.08.72 Masilamani S/o Subaiyamudaliyar Jayaraman S/o Dry Land 3 31. 206/1A 0.05.99 Subaiyamudaliyar Vijaybabu S/o Masilamani Dry Land Sanmugham S/o Ramasamy 207/1A 0.05.87 32. Natarajan S/o Ramasamy 3 205/4B 0.19.14 Santhamani D/o Ramasamy 33. 205/4A Dry Land 0.00.27 Rangasamy S/o Ramegounder 1

WAPCOS Limited xxxiv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land Acquisition Details of Sl.No No/Sub Classification (in Square Meter) Family Division No 208/1 0.24.95 208/2 0.00.16 251/1B 0.08.52 222 0.00.08 Dry Land Natarajan S/o ChinnatambiGounder Karthikeyan S/o Subramaniam 220/1 0.15.71 Nagarajan S/o Subramaniam 34. 1 251/1A 0.00.64 Nagarathinam W/o Subramaniam Mohanalakshmi D/o Kandasamy Sarojamani W/o Kandasamy Dry Land RangasamyGounder S/o Rangasamy 35. 221 0.04.51 1 Gounder 251/1C1 Dry Land 0.09.94 36. Natarajan S/o Muthappagounder 1 252 0.18.31 Dry Land Rangasamy Gounder Sundaramurthy S/o 37. 250 0.00.93 1 Rangasamy Gounder 249/2 Dry Land 0.01.45 38. 248/2 0.00.79 Nanchammal W/o Subaiyyan 1 291/ 0.29.25 248/2 Dry Land 0.00.79 39. Kesammal (or) Santhamani W/o Natarajan 1 291/ 0.29.25 40. 290/1A Dry Land 0.03.19 Shanmugan S/o Murugasamy 1 290/1b Dry Land 0.07.30 Ravi S/o Devarjan 41. 2 287/1A 0.00.93 Ragupathy S/o Ranganathan Dry Land Kandasamy S/o Ramasamy Marudan S/o Raman 42. 287/3 0.01.70 Palani S/o Raman 5 Arumugam S/o Raman Subramani S/o Rangasamy 43. 289/1A Dry Land 0.14.28 Marimuthu S/o Pandithan 2

WAPCOS Limited xxxv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land Acquisition Details of Sl.No No/Sub Classification (in Square Meter) Family Division No 245/2C 0.00.86 Angamuthu S/o Pandithan Gurusamy S/o Ramasamy Yasoda W/o asikumar Shankar S/o Shanmugam 289/1B Dry Land 0.00.15 Sundararajan S/o Narayanasamy 44. 245/2D1 0.01.34 1 Suganthi W/o Sundararajan 245/2D2 0.17.84 45. 245/2B Dry Land 0.00.87 Kaman S/o Jothi 1 46. 401/1A Dry Land 0.11.47 Rajkumar S/o Duraisamy 1 Ramasamy Gounder S/o Sivanappa Gounder Rangagounder S/o Sivanappa Gounder Kandasamy Gounder S/o Sivanappa 401/2 Dry Land 0.00.27 Gounder 2 Ramathal W/o Velumayildevar Deivanaiyammal Palanisamy S/o Chinnasamy Sakthivel S/o Palanisamy Dry Land KareGounder S/o S/o Sivanappa Gounder Subbulakshmi W/o Kandasamy Gounder Ramasamy S/o Sivanappa Gounder 406/3 0.24.61 Karunanidhi S/o Kandasamy Gounder 47. 8 450/3 3B3 0.05.23 Rajasekar /o Kandasamy Gounder Rukhmani W/o Umapathi Palanisamy S/o Kandasamy Gounder Sumathi w/o Palanisamy 48. 450/3C Dry Land 0.00.73 Arasiyammal W/o Venkittal 1 Dry Land Pathiran S/o Palanipoyan 49. 451 0.12.60 2 Rangasamy S/o Palanipoyan 50. 455 Dry Land 2.22.50 Rangasamy S/o RamayyaGounder 1

WAPCOS Limited xxxvi

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land Acquisition Details of Sl.No No/Sub Classification (in Square Meter) Family Division No Dry Land Rakhannadevar S/o AngannaDevar 51. 454/1 2.44.50 1 Palaniyammal W/o Velumayildevar Dry Land Jagan (Or) Mohan S/o Ramalinga Chettiyar 543 1.10.00 Kathirvelu S/o Ramalinga Chettiyar 52. 5 544 2.00.00 Amirthalingam S/o Ramalinga Chettiyar Manigandan S/o Ramalinga Chettiyar Vasanthakokilam W/o Rajendran 53. 497/2A Dry Land 0.14.15 Nanchappan S/o Palaiyandi (Late) 1 54. 497/2B Dry Land 0.10.35 Velusamy S/o Venkatesan 1 Dry Land AttiyannaGounder S/o Nanchaiyya Gounder Rangasamy S/o Nanchaiyya Gounder Nanjundan S/o Nanchaiyya Gounder Kannappan S/o Nanchaiyya Gounder 55. 500 0.20.13 8 Marakkal W/o Nanchaiyya Gounder Muthammal W/o Rangasamy Appichiyannan S/o Krishnappa Gounder Rangasamy S/o Erappagounder Sugumaran S/o Chinnasamy 56. 541/1 Dry Land 0.08.81 Ramasamy Gounder S/o Chinnaiyagounder 1 Dry Land Ramasamy Gounder S/o Thimmaiyagounder 57. 541/2 0.01.36 1 Venkitaiya Gounder S/o Thimmaiyagounder Total 113

WAPCOS Limited xxxvii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Gudalur North Village Survey Name of the Owner Land No/Sub Details of Sl.No Classification Acquisition (in Division Family Hectares) No

856/1 Dry Land 0.10.67 Swarnambal W/o Gurusamy 1 1. Dry Land 856/2 0.12.62 Kalavani W/o Balasubramaniam 1 2. Dry Land 1.Govindasamy S/o Palanisamy 3. 858 0.20.34 2 2.Saraswathi Chellam W/o Kaalisamy Dry Land 1. Kaalisamy S/o Ganapathy Gounder 4. 862/2 0.16.58 2 2.Govindasamy S/o Palanisamy Dry Land 1.Krishnan 2.Sorppan S/o Yonna 5. 865/2 0.12.37 4 3.Cyon Assembles O/o 4.Samlies 6. 867 Dry Land 0.16.00 Amsaveni W/o Purushothaman 1 Dry Land 869 0.17.84 Veerabatiran S/o Thasappa Gounder 1 7. Dry Land 1. Kaalisamy S/o Ganapathy Gounder 8. 900 0.17.32 2 2.Govindasamy S/o Palanisamy Dry Land 1. Chinnanachappa Gounder S/o Rangappa 9. 907/2 0.17.43 1 Gounder

10. 907/4 Dry Land 0.14.30 Sanmugam S/o Devanagounder 1

Dry Land 11. 0.00.07 Agilarasu S/o Govindasamy 1 908

WAPCOS Limited xxxviii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land No/Sub Details of Sl.No Classification Acquisition (in Division Family Hectares) No Dry Land 12. 1.Alagarsamy S/o Sangarappan 912 0.09.87 2 2.Rangasamy S/o Karrupanan

Dry Land 913 0.11.23 Nandakumar S/o Ramadoss 1 13. Dry Land 1.Ramadoss

2.Prakash S/o KrishnaGounder 960 0.00.24 3 3.Ravichandran S/o KrishnaGounder 14.

Dry Land 964 0.20.82 Arunkumar S/o Balasubramaniam 1 15. Dry Land 1.Viyakthi Viyas Kendira Ravindraprasad S/o Balappa 16. 965/1 0.07.63 4 2.M.P.Joe 3.A.K.Joy Dry Land 1.Viyakthi Viyas Kendira Ravindraprasad S/o Balappa 17. 965/3 0.09.79 4 2.M.P.Joe 3.A.K.Joy Dry Land 1.Viyakthi Viyas Kendira Ravindraprasad S/o Balappa 18. 968/2 0.15.87 4 2.M.P.Joe 3.A.K.Joy Dry Land 1.Rajendran S/o Chinnasamy 19. 970/2 0.21.09 2 2.Jayasankar S/o Rathiran 20. 976/1A Dry Land 0.08.19 Arunkarthickeyan A/o Venkatakrishnan 1

WAPCOS Limited xxxix

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land No/Sub Details of Sl.No Classification Acquisition (in Division Family Hectares) No 976/1B 0.07.72 976/1C 0.09.55 978/2 0.09.26 978/3 0.09.91 978/4 0.07.90 Dry Land Subramaniam S/o Senthil 21. 978/1 0.08.64 Sabarinathan S/o Subramaniam 3 Subramaniam Minirajan 979 Dry Land 0.11.46 22. V.Sugunan S/o K.S.Vasudevan 1 980 Dry Land 0.08.82 Dry Land 1. Manoharan S/o Vasudevan 23. 1430/1 0.05.40 3 V.S. Krishnan S/o Narayanasamy Chettiyar 24. 1430/2 Dry Land 0.05.59 Marappa Gounder S/o Kamatchi Gounder 1 1431 Dry Land 0.15.31 1.R.K.Mani S/o Karuppasamy Dry Land 2.R.K.Amavasaikutty S/o Karuppasamy 25. 3.R.K.Thirumoorthy S/oKaruppasamy 4 1432 0.17.89 4.R.K.Ramasamy S/o Karuppasamy 5.R.K.Subramanian S/o Karuppasamy Dry Land 1.N.R.Dhandapani 2.N.R.Shanmugam 26. 1460/2A 0.03.40 3.M.S.Maideen 6 4.M.Mahendran 5.M.Kalpana Dry Land 1.Devaraj 2.Vasudevan (or) Kuppusamy S/o Thiruvenkatam 27. 1464/1 0.02.84 3 3.Vadivelu S/o Thiruvenkatam

Total 60

WAPCOS Limited xl

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Naickenpalayam Village

Survey Name of the Owner Land Sl.No No/Sub Details of Classification Acquisition (in Division Family Sq.m) No 1. Manimaran S/o Muthu 2.Joseph S/o John 1. 33/1 Dry Land 0.16.93 3.Rajeswari 5 4.Sabitha 5.Chitra Dry Land 1.Immanuvel S/o Jayaseelan 2.Rajeswari 2. 34 0.11.55 4 3.Sabitha 4.Chitra 3. 35 Dry Land 0.13.60 1.Saravanakumar 2 2.Manoharan Dry Land 1.Kanakaraj S/o Govindasamy 4. 44 0.14.11 2 2.Duraisamy S/o Govindasamy 5. 45/2A Dry Land 0.08.51 1.Sreenivasan S/o Venkatesan 1 6. 45/2B Dry Land 0.08.40 Babu Narasimman S/o Venkatesan 1 7. 46 Dry Land 0.10.31 Dhamodaran S/o Venkedasamy 1 8. 70/2 Dry Land 0.13.72 Niraimathi W/o Sekar 1 9. 71/2 Dry Land 0.08.43 Dry Land 10. 71/1 0.08.43 4 Fathima 11. 106 Dry Land 0.04.36 Rengaraj S/o Ramasamy 12. 107/1B Dry Land 0.02.78 1 13. 116/2B Dry Land 0.08.58 13. Dry Land Vijayachand Jabec 108 0.16.95 1

WAPCOS Limited xli

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land Sl.No No/Sub Details of Classification Acquisition (in Division Family Sq.m) No Dry Land Viajayalakshmi W/o Duraisamy 116/1 0.10.31 1 14. 15. 510/1A Dry Land 0.08.49 Uma Lakshmi 1 Dry Land 510/1B 0.07.76 Uma Lakshmi 5 16. 17. 514/1 Dry Land 0.00.79 Balaji S/o Selvarajan 1 18. Dry Land 1. Alwar 514/3 0.20.28 2. Saravanakumar S/o Kangaraj 2

19. 520/1 Dry Land 0.01.93 Chinnaraj S/o Selvarajan 1 20. 523/2 Dry Land 0.14.87 21. Dry Land 1. Dhanalakshmi W/o Selvarajan 520/2 0.31.98 2 2. Selvarajan 22. 523/1 Dry Land 0.04.31 23. 532/3 Dry Land 0.02.00 Kandasamy Gounder 1 24. 533/3 Dry Land 0.06.45 25. 533/1C1 Dry Land 0.09.72 Rajagopal S/o Rengasamy 1 26. 533/1D Dry Land 0.06.44 Dhamodaran S/o Rengasamy 1 27. 533/2A Dry Land 0.00.62 1.Duraisamy 3 2.Dhamodaran 3.Saravanan 28. 533/2B1 Dry Land 0.05.09 Duraisamy S/o Nanchappa Gounder 1 Total 43

WAPCOS Limited xlii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Gudalur South Village Survey Name of the Owner Sl.No Land Acquisition Details of No/Sub Classification (in Hectares) Family Division No 1. . 161/1 Dry Land 0.00.39 1.Raju S/o Venkedusamy and 4 others Dry Land 2. 161/2 0.35.64 Jagadeesh S/o Narasimman 1

3.. 254/2B1 Dry Land 0.11.88 Muthusamy S/o Rengasamy 1 Dry Land 1.Rajamani S/o Palaniyappan 2.Rajagopal S/o Ponnusamy 3.Singaravelu S/o Sivaraman 4. 256/1 0.06.26 6 4.Murugaraj S/o Singaravelu 5.Latha W/o Sounderrajan 6.Thangamani W/o Ponnusamy 257/1 Dry Land 0.46.44 5. M/s Martin Housing (p) Ltd 1 257/3 0.66.00 257/2 Dry Land 0.57.00 6. Krishnamoorthy S/o Thamburaj 1 257/4 0.56.50 7. 320 Dry Land 0.15.19 Rathinasamy S/o Chinnaiya Gounder 1 321 Dry Land 0.17.48 1.Senthilkumar S/o Krishnasamy 8. 325/3 Dry Land 0.02.54 2.Karthick S/o Krishnasamy 3

326/4 Dry Land 0.07.27 3.Anandhi W/o Iyyappan 326/1 Dry Land 0.12.02 326/2 Dry Land 0.01.28 1.Sundari Ramadoss W/o Ramadoss 1 9. 326/3 Dry Land 0.01.78 329/1 Dry Land 0.04.03 343/4 Dry Land 0.07.07 Dry Land Dr.Uma W/o Senthilkumar 1 343/5 0.12.85 10. 11. 346/2 Dry Land 0.02.22 1.Manimuthu S/oPalsamy Nadar 2

WAPCOS Limited xliii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Sl.No Land Acquisition Details of No/Sub Classification (in Hectares) Family Division No 347/1 Dry Land 0.04.02 2.Ashokvarathan S/o Loganthan Dry Land 347/2 0.09.72 350/1 Dry Land 0.00.59 350/2A Dry Land 0.18.01 351 Dry Land 0.11.56 12. 366/2 Dry Land 0.04.92 Lakshmanan (or) Duraisamy S/o Pathiran 1 Dry Land 1.Dr.Priya S/o Ramamoorthy 13. 368/1 0.22.13 2 2.Jaganathan S/o Venugopal 432 Dry Land 0.00.68 14. 1.Thangammal W/o Arumugham 1 433/3 Dry Land 0.04.42 Dry Land 1.Devaraj S/o Chinnasamy 15. 433/1 0.15.95 2.Sundarraj S/o Chinnasamy 3 3.Ravichandran S/o Chinnasamy 16. 433/2 Dry Land 0.07.30 1.Nanjammal W/o Sadaiyappan 1 434/2A Dry Land 0.09.66 17. 434/2B Dry Land 0.00.73 1.Babu s/o Krishnan 1 440/5 Dry Land 0.04.47 18. 439 Dry Land 0.14.80 1. Gunasekaran S/o Palanisamy 1 Dry Land 1.Badruteen S/o Muhammad Gani 19. 440/2 0.00.35 1 Rawther 20. 440/4 Dry Land 0.08.68 1.Sivakumar S/o Palanisamy 1 21. 448/2 Dry Land 0.11.87 1.Vetrivelan S/o Palanisamy 1 Dry Land 1. Selvaraj S/o Velingiri 22. 449/1 0.09.67 2 2.Duraisamy S/o Velingiri Dry Land 1.Ponnusamy S/o Chinna naganna 23. 449/3 0.11.89 1 Gounder 24. 451/1 Dry Land 0.15.64 1.Jagadeesh S/oBalakrishnan 5

WAPCOS Limited xliv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Sl.No Land Acquisition Details of No/Sub Classification (in Hectares) Family Division No 2.KAnnappan S/o Balamalai Gounder 3.Vijayakuar S/o Velugan 4. Palanisamy S/o Balamalai Gounder 5.Rajammal W /o Arukutty 25. 733 Dry Land 0.12.12 1.Premalatha and also 55 Others 8 737 Dry Land 0.30.12 26. 1.ELA.Kumar S/o Lakshmanan 1 738/5 Dry Land 0.10.72 25. 451/2 Dry Land 0.10.85 1.Selvaraj S/o Perumal 1 Total 49

WAPCOS Limited xlv

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Narasimmanaickenpalayam Village

Survey Name of the Owner Land Acquisition Sl.No No/Sub Classification Details of Family (in Hectares) Division No Dry Land Naveenkumar S/o Mani 1. 432 0.26.36 1

Dry Land 1 2. 435 0.09.45

Devarajan S/o Lakshmana Gounder 437/2 Dry Land 0.03.36 3.

4. 443/1 Dry Land 0.13.10 Santhi W/o Sivanandham 1 5. 445/1 Dry Land 0.27.68 Vasantha W/o Renganathan 1 Dry Land 3 6. 452 0.09.80 1.Sanmugham S/o Rengasamy Gounder 2.Kangaraj S/o Rengasamy Gounder 3.Duraisamy S/o Rengasamy Gounder 7. 453 Dry Land 0.06.58 Total 7

WAPCOS Limited xlvi

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Kurudampalayam Village

Survey Name of the Owner Land No/Sub Details of Sl.No Classification Acquisition Division Family (in Hectares) No 1.Santhamani 3. 353/11 Dry Land 0.03.34 2.Marisamy 3 3.Devaraj 353/10 Dry Land 0.09.71 4. Veerabathra Devasthanam 1 353/4 Dry Land 0.16.97 Dry Land 5. 356/2 0.08.39 Sarasu W/o Duraisamy 1

6. 363/2 Dry Land 0.10.76 S.P.Kangarajan 1 Dry Land 1.Srinivasan 7. 363/1 0.06.96 2.Sivakumar 4 Dry Land 1.Natarajan 367/2 0.04.73 2.Kamalam 8. 367/1 Dry Land 0.12.47 Rajagopal 1 Dry Land 1.Lakshmi 9. 380/3 0.04.88 2 2.Rajagopal 396/1 Dry Land 0.01.34 396/2 Dry Land 0.07.14 713/1 Dry Land 0.06.05 1.Lakshmi 10. 713/2 Dry Land 0.00.46 2.Balasoundaryalakshmi 3 397/2 Dry Land 0.04.05 3.BalaradhaShyamala 397/3 Dry Land 0.03.94 430/2C Dry Land 0.05.35 430/2A Dry Land 0.01.42 491/1C Dry Land 0.04.69 11. Sree Durgadevi Property Management (P) Ltd 1 491/1B Dry Land 0.06.64 491/1A1 Dry Land 0.02.02

WAPCOS Limited xlvii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Name of the Owner Land No/Sub Details of Sl.No Classification Acquisition Division Family (in Hectares) No 491/2B2 Dry Land 491/2A Dry Land 0.01.40 485/2 Dry Land 0.00.02 485/4 Dry Land 0.10.82 430/3A Dry Land 0.00.39 12. 492/4C2 Dry Land 0.05.28 Shoba Developers 1 520/2 Dry Land 0.22.35 13. Keerthiman Groups 1 519/7C Dry Land 0.09.43 14. 526/6 Dry Land 0.05.36 Chitra Elango 1 492/4C1 Dry Land 0.02.20 492/4B Dry Land 0.05.54 492/4A Dry Land 0.12.12 15. Sree Parvathy Land Developers 1 492/3B Dry Land 0.06.28 519/2 Dry Land 0.03.25 519/3 Dry Land 0.11.46 520/3B Dry Land 0.00.01 520/1D Dry Land 0.04.35 520/3C1 Dry Land 0.00.27 16. Virundha 1 520/3A1 Dry Land 0.15.72 520/3A2 Dry Land 0.02.68 520/3A3 Dry Land 0.01.88 526/1E Dry Land 0.04.58 526/1D Dry Land 0.06.31 17. Chitra Elango 1 526/1C Dry Land 0.08.02 526/1B Dry Land 0.07.05 18. 524/2 Dry Land 0.25.09 CJT Charles Dhilip Roy 1 19. 356/1 Dry Land 0.10.80 Vettaikarasamy Thirukoil 1 Total 25

WAPCOS Limited xlviii

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Pannimadai Village

Survey Land Sl.No No/Sub Classification Acquisition (in Name of the Owner Details of Family Division Hectares) No 1. 320/1 Dry Land 0.02.31 Kalaivannan S/o Late Ramdoss 1 Dry Land Mithun Charavathy S/o Pasanthkumar 1 2. 354/1D 0.03.76 Chakaravathy 355/1A Dry Land 1 3. 0.04.90 Rangasamy S/o Chinnarangappan

Dry Land 1.Rajamani S/o Nanchappan 3 4. 355/1B 0.04.86 2.Manoharan S/o Kuppusamy 3.Aruchamy S/o Kuppusamy Dry Land Lakshmana Gounder S/o Chinnarangappa 1 5. 355/1C 0.04.86 Gounder 6. 355/1D Dry Land 0.04.28 Arumuga Gounder S/o Chinnarangappa Gounder 1 7. 355/2 Dry Land 0.01.10 R.Ayyasamy S/o Rangappan 1 8. 356/2 Dry Land 0.01.35 Shyam Hari S/o Parthiban 1 9. 356/3 Dry Land 0.17.80 Masiyakkal W/o Nachappa Gounder 1 10. 356/4 Dry Land 0.00.98 Arumugam S/o Marudaiyan 1 11. 359/1A Dry Land 0.12.22 1. Chitra W/o Krishnamoorthy 5 Dry Land 2. Ramanathan S/o Krishnamoorthy 3.Jayanthi W/o Ramesh 12. 359/1B 0.08.98 4.Tilak K. Nath S/o (late) K.V Nath, Sudha Tilak W/o Tilak K . Nath 5.Ravi S/o Ragunathan Dry Land 1. Sivakumar S/o Narayanan Kutty 6 2.Ramya W/o Saravanakumar, Priya W/o 13. 361/1D 0.23.90 Sivakumar 3.Karthick S/o Sivanandham

WAPCOS Limited xlix

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Survey Land Sl.No No/Sub Classification Acquisition (in Name of the Owner Details of Family Division Hectares) No 4.Nagasubramaniam S/o Sri Veykadasubaiyar 5.Thirusengodu Perumal Sridharan , vanisree Sridharan 6.Noorudeen Shajahan, Muhammed Appas 14. 361/1F Dry Land 0.03.59 Nil Nil 1.M/s Gautham Houses P Lt Managing Director 1 15. 360/3 1.17.00 Dry Land 2.A.S.Elango S/o Sambasivam Dry Land 1.M/s Gautham Houses P Lt Managing Director 16. 361/2C 0.04.89 2.A.S.Elango S/o Sambasivam Dry Land 1.M/s Gautham Houses P Lt Managing Director 17. 363/3 0.52.94 2.A.S.Elango S/o Sambasivam Dry Land 1.M/s Gautham Houses P Lt, Managing Director 18. 364/1 0.56.0 A.S.Elango S/o Sambasivam 19. 366/1 Dry Land 0.29.41 1.M/s Gautham Houses P Lt, Elango 20. 366/2 Dry Land 0.04.63 A.S.Elango Dry Land 1. A.S.Elango 21. 367/1 0.16.0 2.A.M. Sambasivam 1. A.S.Elango 22. 367/2 Dry Land 0.08.80 2.A.M. Sambasivam Total 24

WAPCOS Limited l

Draft SIA/ Audit Report Social Impact Assessment study for Pillur Water Supply Project, Coimbatore District

Nanjundapuram Village

Land Name of the Owner Sl.No Survey No/Sub Details of Classification Acquisition Division No Family (Sq.m) 1. 581/1 Dry Land 0.16.13 Arumugam S/o neelikonaan 1 2. 591/1 Dry Land 0.13.08 Manjula Sathish W/o Sathishkumar 1 3. 592/1 Dry Land 0.01.89 1.Chinnasamy S/oMuthappa Gounder 5 592/2 0.05.22 2.Murugesan S/o Palanisamy 593 0.06.38 3.Veerasamy S/o KaruppanaGounder 4.Ramasamy S/o Kumarasamy 5.Dharmalingam S/o ArunachalaGounder 6.Manigandan S/o Ramasamy Gounder 4. 594/1 Dry Land 0.14.73 Purushothaman 1 5. 596/1 Dry Land 0.08.35 Selvaraj 1 6. 597/3 Dry Land 0.01.94 Rengasamy 1 7. 596/2 Dry Land 0.08.33 Kandasamy 1 8. 597/2 Dry Land 0.16.20 Natarajan 1 Total 12

WAPCOS Limited li