Recharge : Building Pakistan’s Resilience to Climate Application Title Change through Ecosystem-Based Adaptation for Integrated Flood Risk Management

Country/ Region Pakistan

Accredited Entity World Wildlife Fund

Approval Date 09/29/2020

GREEN CLIMATE FUND | PAGE 0 OF 2

Request for Support from the Project Preparation Facility (PPF)

Recharge Pakistan: Building Pakistan’s Resilience to Application Title Climate Change through Ecosystem-Based Adaptation for Integrated Flood Risk Management Country(ies) Pakistan

Accredited Entity World Wildlife Fund (WWF)

Date of first submission/ [2020-04-16] [V.1] Version number

Date of current submission/ [2020-07-31] [V.3] version number

Please submit the completed form to [email protected], using the following naming convention in the subject line and the file name: “PPF-[Accredited Entity]- [Country]-yyyymmdd” 2017

Project Preparation Facility GREEN CLIMATE FUND | PAGE 1 OF 18 Version 2.0

Notes • The PPF supports the development of projects and programmes and enhance their quality at entry into the Fund’s pipeline. With a view to enhancing the balance and diversity of the project pipeline, the PPF is designed to especially support Direct Access Entities for projects in the micro-to-small size category. International Accredited Entities seeking project preparation support from the PPF are encouraged to do so especially for LDCs, SIDS and African countries where no Direct Access Entity is accredited. All Accredited Entities are encouraged to articulate counterpart support for project preparation within their requests for support from the PPF. • A PPF submission should include below documents: 1. PPF request (this form) 2. PPF No-Objection letter1 3. Concept Note • Please copy the National Designated Authority (ies) when submitting this PPF request. • Requests for support from the PPF should be submitted at the same time or following submission of a GCF Concept Note for a project or programme. • Further information on GCF PPF can be found on GCF website Project Preparation Facility Guidelines.

1Please note that the PPF No-Objection Letter is different from the Funding Proposal No-Objection Letter. PPF No-Objection Letter template can be downloaded from here.

Project Preparation Facility GREEN CLIMATE FUND | PAGE 2 OF 18 Version 2.0

A. Executive Summary Name: David McCauley Position: WWF Senior Vice President and Global Lead, Public Sector Partnerships Accredited Entity Email: [email protected] cc: [email protected] (AE) Tel: (202) 495-4159 Full Office address: World Wildlife Fund, 1250 24th Street, N.W., Washington, DC 20037 Yes ☒ No ☐ If yes, please indicate Project/Programme title: Yes ☒ No ☐ Has a Concept Note2 Has a No-Objection Recharge Pakistan: 3 been submitted in Building Pakistan’s Letter been submitted for association with this this request for support Resilience to Climate request for support from the PPF? from the PPF? Change through Ecosystem-Based Adaptation for Integrated Flood Risk Management Total cost of Project Preparation activities: USD$ 765,265 Total Cost Amount requested from the PPF: USD$ 694,646 Counterpart funding from the AE: USD$ 70,618 Government of Pakistan Support – field staff and logistics: USD$ 100,000 Anticipated Duration Number of months to implement the Project Preparation activities: 12 months The project’s goal to implement ecosystem-based adaptation (EbA) at scale to effectively reduce flood risks and secure groundwater recharge presents a paradigm shift for the country - transitioning to consistent integration of EbA interventions using nature based solutions to increase the efficiency of hard infrastructure in reducing climate change threats. This requires extensive feasibility studies and assessments to be effective. The project’s EbA focus depends on evidence-based identification of sites where these interventions would be most effective. Potential sites have been identified with stakeholders in each province, but detailed engineering designs and cost-benefit analyses to identify the Summary of the best adaptation solutions are needed. In parallel, detailed ecological, socio-economic, request for Project environmental and social safeguards, and gender assessments are required to establish Preparation support baselines and develop management plans to maximize positive impacts. The project’s work to enhance vulnerable communities’ resilience and create necessary policy enabling environments also requires: vulnerability assessments; detailed identification of appropriate adaptation interventions; further policy reviews and gap analysis to align the project with relevant government plans and policies; updated institutional capacity needs assessments and climate resilience planning; detailed integrated flood risk and groundwater management planning involving extensive consultations with stakeholders, potential partners and co-financers to ensure project ownership and support.

B. Description of Project Preparation Activities Month Outputs and Activities 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 Activity and deliverable 1: Pre-feasibility Study Activities: Prefeasibility study for shortlisting project sites using defined criteria and GIS land-use and X floodplain zoning maps, hydrological and climate assessments, stakeholder consultations at national and provincial levels, desk reviews of policies and

2 See here to download the Concept Note template. 3Template for PPF No-Objection Letter can be downloaded here.

Project Preparation Facility GREEN CLIMATE FUND | PAGE 3 OF 18 Version 2.0

plans, review of case studies, and review of existing feasibilities/plans for proposed sites. Deliverables: Prefeasibility study including criteria for shortlisted sites and identification of infrastructure/interventions for flood/hill torrents management. Use of deliverables: This output is necessary to initiate the detailed feasibilities in identified project sites through the pre-feasibility assessment, and environmental, social and gender studies in the finalized target areas of the project. Activity and deliverable 2: Gender Studies Activities: Assessments of local gender dynamics and issues, education, livelihood opportunities, participation in development, decision-making representation, differential aspects of assets ownership and disaster vulnerabilities, analysis of enabling national gender-related policies, etc. x Deliverables: Gender Assessment and Gender Action Plan. Use of deliverables: The Gender Assessment and Gender Action Plan will contribute toward the final project design, including the M&E plan with gender- disaggregation where appropriate and gender- specific indicators, and the associated ESMP included with the funding proposal. Activity and deliverable 3: Environmental and Social Studies Activities: Environmental Studies - Baseline setting, impact assessments, and identification of locally applicable adaptation practices. Social Studies - Demographic profiles, population mapping, poverty assessments, disaggregated socio- economic indicators (e.g. natural resource X dependence, social inclusion, etc.). Deliverables: Environmental and Social Assessments, and Environmental and Social Management Plan (ESMP). Use of deliverables: Environmental, social and gender assessments will contribute towards the final project design, and the associated management plans will be included with the funding proposal. Activity and deliverable 4: Detailed Feasibility Study Activities: After proposed project sites have been shortlisted, analyses will be conducted, including: hydro-geological assessments (water availability, stream flow, rainfall data, flood dynamics, etc), multi- hazard risk and vulnerability assessments, detailed X site specific engineering designs, modelling, cost benefit analyses of EbA options for each site, appropriate disaster risk management interventions, local water use/distribution rights study etc. Deliverables: Detailed feasibility study including the designs, drawings and cost estimates of the

Project Preparation Facility GREEN CLIMATE FUND | PAGE 4 OF 18 Version 2.0

proposed interventions at the selected project implementation sites Use of deliverables: The study may suggest changes in the initial project design and will be incorporated in the final proposal. Activity and deliverable 5: Identification of Project Indicators Activities: Project indicators will be defined during the preparatory phase to gather appropriate data during socio-ecological baselines and studies, develop a detailed Logical Framework, and Monitoring & Evaluation Framework. Gender disaggregated data of beneficiaries at the shortlisted X sites will be collated for effective monitoring of the implementation status and impact of interventions. Deliverables: Detailed Logical Framework and Monitoring & Evaluation Framework Use of deliverables: Data to be used in developing the project Logical Framework and Monitoring Framework for project proposal. Activity and deliverable 6: Project Design and Consultations Activities: Stakeholder consultations (gender- responsive), negotiations (e.g. on finances and roles) with co-financers and implementing partners, project risk analysis and mitigation measures, design of training and monitoring programs, identification of institutional and policy gaps to be addressed. Full GCF funding proposal, Deliverables: X incorporating findings and recommendations from the feasibility studies and analyses conducted, will be a collaborative effort between the lead executing entities and the accredited entity. Use of this deliverable: The GCF full funding proposal will provide the details of execution of the Recharge Pakistan project including specific interventions, management arrangements among all partners, budgeting, etc. Estimated time for submission of corresponding full Funding Proposal to the GCF. X

C. Justification of the Project Preparation Request Pakistan is a lower-middle income country , and WWF is an international not-for-profit NGO with limited available resources to fully finance project preparation for the Recharge Pakistan project. WWF is therefore submitting this PPF request to support the design of this important project with broad support across the government of Pakistan. WWF is firmly committed to the careful design of this project and will be contributing approximately USD$70,000 to completion of the Funding Proposal.

Project Preparation Facility GREEN CLIMATE FUND | PAGE 5 OF 18 Version 2.0

D. Implementation Arrangement The project preparation phase will be coordinated overall by WWF-Pakistan, a separate legal entity from WWF US, in close collaboration with Pakistan’s Ministry of Climate Change (Pakistan’s GCF NDA), the Ministry of Water Resources, particularly its Federal Flood Commission (FFC), and the Provincial Irrigation Department. The pre-feasibility and feasibility studies, as well as the environmental, social and gender studies will be competitively procured to identify qualified international and local-level consultants (draft TORs are included as annexes). WWF-US will be responsible to the GCF for the implementation, financial management and oversight of PPF activities as approved and in line with WWF US’s policies, including with respect to procurement, as well as for the submission of the funding proposal. At the national level, the project preparation and implementation will be guided by a well-represented Project Steering Committee (PSC), which will meet regularly to provide guidance for all aspects of project design and execution. The PSC will include representatives from the Ministry of Climate Change (NDA), Ministry of Water Resources including the Federal Flood Commission, Ministry of Planning, Development and Reforms (including representative from the SDGs Unit), National Disaster Management Authority (including representative from the Gender and Child Cell), Pakistan Council of Research in Water Resources, Provincial Planning and Development Departments, WWF-Pakistan, and others. During the preparation phase, the Project Steering Committee will direct the discussions and decision-making for shortlisting sites and agreement on final project interventions, as these are the key Government stakeholders in Pakistan under whose jurisdiction these areas of work lie. Inter-provincial coordination shall be ensured through provincial government departments working in coordination with the PSC. WWF-Pakistan’s offices in Lahore (Head Office in Punjab Provincial Capital), Islamabad (Federal Capital – for liaison with Federal Ministries), Peshawar (Khyber Pakhtunkhwa Provincial Capital), Quetta (Balochistan Provincial Capital), ( Provincial Capital), and at various other field sites will provide logistics and coordination with the respective Provincial Governments and stakeholders in each geographic area during project preparation. In addition, the Federal Flood Commission (Ministry of Water Resources) and Provincial Irrigation and Environment Protection Departments will also provide logistical and technical oversight support during the feasibility studies and for project preparation activities requiring government collaboration. A Project Lead, within WWF-Pakistan, will coordinate the project preparation activities along with a team of research associates, experts from the Government, consultants, and other M&E and program development specialists. The WWF Accredited Entity Office will be supporting the project implementing agencies (WWF-Pakistan, and relevant Government of Pakistan agencies) in developing the full GCF funding proposal, and will act as a supervisory entity to guide the entire process. WWF shall implement the Project Preparation Activities with the goal of submitting a funding proposal for approval by the Board within 2 years of the approval of the Project Preparation Funding Application. WWF shall notify the Fund as soon as it has reasons to believe that a submission within this timeframe may not be possible.

Project Preparation Facility GREEN CLIMATE FUND | PAGE 6 OF 18 Version 2.0

E. Budget4 Details and Disbursement Schedule Disbursement and Reporting Schedule 5 For reporting purpose, WWF will submit all deliverables of proposed project preparation activities and a draft Funding Proposal of the underlying project together with the completion report for this PPF application.

Reporting plan • 6-month progress report will be submitted to the GCF within thirty (30) days following the end of the 1st reporting period, 6 months after effectiveness of signed Grant Agreement. • A final report will be submitted to the GCF within sixty (60) days following the end of the implementation period and will include an audited financial report.

Disbursement schedule

1st Tranche: 90% of total grant, which equates to USD $625,181 only will be disbursed upon or after effectiveness of the Grant Agreement and also upon fulfilment of the disbursement conditions specified in the Grant Agreement and Standard Conditions.

Final Tranche: 10% of total grant, which equates to USD $69,465 only, will be transferred upon submission of a project completion report and final Audit Report. Submission of a completion and audit report will be furnished no later than three (3) months after the completion of the PPF Support.

4“Sub-total cost” must be provided for each activity, and broken down by the “cost categories” (e.g. Consultants, Travel, Equipment, Training & workshops, Others). Please provide sufficient breakdown of costs to enable effective review. - 5 For PPF requests of 12 months or less, 70% of the overall budget can be disbursed upon effectiveness of the signed funding agreement, with a 30% final payment upon approval of the final substantial and audited financial report. For PPFs of 12 months or more, 40% can be for first disbursement upon effectiveness of the signed funding agreement; 30% upon delivery of first approval of first progress report, and 30% upon approval of the final substantive and audited financial report. A progress report is required every 6 months during the PPF implementation period and this report should include all deliverables scheduled to be completed within this time frame.

Project Preparation Facility GREEN CLIMATE FUND | PAGE 7 OF 18 Version 2.0

Recharge Pakistan PPF Application Annexes Contents Annex 1: Terms of Reference Feasibility Studies ...... 7 Annex 2: Terms of Reference: Environmental and Social Management Framework ...... 11 Annex 3: Terms of Reference: Gender Assessment ...... 14 Annex 4: Preliminary Environmental and Social Safeguards Categorization Memorandum ...... 16

Annex 1: Terms of Reference Feasibility Studies 1. Project Information Project Focus: Ecosystem-based Adaptation (wetlands restoration, hill torrents and catchment area management) Project Beneficiaries: 10 Million Direct Beneficiaries; 58 Million Indirect Beneficiaries, >100 Tehsils of 49 districts along Policy Alignment: National Climate Change Policy & Implementation Framework, National Water Policy, NDCs, the National Flood Protection Plan-IV, SDGs, Sendai Framework, Ramsar Convention, and others Time for Assignment: 12 Months 2. Background and Summary The Indus River is the lifeline of water-stressed Pakistan, but it also delivers catastrophic floods exacerbated by climate change. Pakistan currently relies on costly infrastructural flood management measures, having limited efficacy. This project brings a paradigm shift towards managing floods through large-scale ecosystem-based adaptation (EbA). It unifies 20 Government ministries and departments in a hitherto unprecedented collaboration to build Pakistan’s climate resilience and water security. The proposed three-pronged approach includes: ecosystem-based flood management through wetland restoration, hill-torrent management, and green infrastructures; community-based natural resource management, climate-adapted livelihoods and risk reduction; and a paradigm shift to scale up the EbA approach. The integrated flood risk management project proposes to undertake Ecosystem-based Adaptation (EbA) interventions at several priority sites nationwide, build resilience of communities, and enable the Government and relevant stakeholders to implement and replicate EbA work, providing a cumulative, no-regrets approach to building climate change resilience. The proposed interventions will enable better management of high peak flood flows in the Indus by employing EbA solutions to: 1) restore wetlands by diverting and storing floodwater from the Indus River, and: 2) manage hill torrents to slow down and divert flash floods that add to flood peaks in the Indus River. The proposed project will have multiple, long-term, wide-ranging benefits for Pakistan, including: a) EbA that improves resilience to flooding and drought; b) increased capacity of water-stressed areas to efficiently store and use floodwater; c) enhanced recharge of groundwater through wetland restoration interventions, and hill torrent management interventions, e.g. watershed restoration, check dams, and terracing; and d) other environmental and socio-economic benefits, e.g. biodiversity and habitat conservation, carbon sequestration, wetlands based livelihoods. The project’s proposed activities will be implemented under three distinct components: Component 1: Ecosystem-Based Adaptation for Integrated Flood Risk Management

Project Preparation Facility GREEN CLIMATE FUND | PAGE 8 OF 18 Version 2.0

Component 2: Enhancing resilience of vulnerable communities to climate change Component 3: Enabling a paradigm shift towards Ecosystem Based Adaptation (EbA) The project’s proposed sites are scattered along a 1500 km stretch of the Indus, from Tarbela Dam (in Khyber Pakhtunkhwa Province) to Kotri Barrage (in Sindh Province). Proposed project sites are: Manchar Lake, Darya Khan Ramak, Bhakkar Lala Creek Layyah, D.I. Khan Hill Torrents, Nara Canal-Deh Akro-Chotiari Wetlands Complex, Esa Khel Watershed, Haleji & Hadero Lake, Kaha Hill Torrent, Chakar Lehri sub-basin. 3. Objective The objective of the feasibility study is to have detailed analysis and assessments of the proposed sites with specific reference to: a) EbA that improves resilience to flooding and drought; b) increased capacity of water-stressed areas to efficiently store and utilise floodwater; c) enhanced recharge of groundwater through wetland restoration interventions and hill torrent management as well as other social, economic and environmental co-benefits. 4. Methodology The process will include a review of previous feasibility studies, relevant reports, published literature, master plans and other related documents and maps for the potential sites and a comprehensive gap analysis. Collect and/or procure available data from authentic sources on topography and land use, soil type and quality, meteorological and hydrological information, historic climate trends, hydraulic and sedimentation, groundwater quality, drainage, environment and other related aspects of the project with reference to selected project sites. Based on field data collection, the following tasks will be completed: a) Institutional mapping and arrangements, multi-scale vulnerability and hazard risk mapping; b) Gender assessment and action plans, environmental and social management plans, integrated flood risk management plans, cost benefit analysis and financial management plan; c) Identification of relevant and specific EBA /NBS interventions for Hill Torrent Management and Floodplain Management with detailed engineering designs and costing. 5. Detailed Terms of Reference Pre-Feasibility Studies (02 months) a. Conduct a comprehensive literature review/detailed desk review of studies on the Indus Basin; including, but not limited to: o Indus Basin overall assessments; studies focused on proposed project sites; gap analyses o Past or in pipeline floodplain management plans, hill torrent management plans, structural and non- structural interventions; associated plans, research publications, feasibility studies; documented successes and failures; o Review hydro-meteorological network in the Indus basin o Land use condition, soil analysis, and watershed /hill torrent management o Flood hazard, risk, and climate change assessment o Flood damage impacts to the downstream communities o Maps of Flood zoning o Reviewing the performance of existing flood protection Infrastructures o Provision of recommendations on identification and prioritizations of potential interventions b. Analysis of geomorphological features relevant to dynamic flow in the river (river flow patterns, base flow, drainages, water utilization, floodplain characteristic along the river); c. Analysis of hydrological condition and future trends in rainfall patterns within catchment/hill torrents and assess how these might influence future flow condition in the main river and its floodplains; d. Within the possible limitations of available data (hydro-meteorology, contour maps of the land & floodplain, water utilization, etc.) understand the frequency of flooding events and its management, create an inundation map for the respective issues, also consider predicted implication of climate change; e. Develop criteria to shortlist sites from the identified potential areas, for undertaking detailed feasibility studies; f. Identification of potential infrastructure/interventions on the proposed sites for the flood/hill torrents management and assessment of their storage capacity. Detailed Feasibility Studies (10 months) a. Review all the provincial and federal acts, ordinances, accords, and treaties that discuss the floodplain and hill torrent management in the country;

Project Preparation Facility GREEN CLIMATE FUND | PAGE 9 OF 18 Version 2.0

b. Review the existing institutional set up for flood hazard and crisis/risk management; c. Study the historic climate patterns and see the future climate scenarios as well as physiographic features to understand the hydrology of floods; d. Collect hydrological data through a real time VHF telemetry system from different river and rain gauges; Review of possible investment opportunities and financial services (non-grant financing) to sustain EbA for flood risk management and community-based disaster management Hydrological Assessment: a. Undertake the review/updating of hydrologic parameters considered in previous studies; b. Collect/update and validate hydro-meteorological data within the basin/ hydrological region with the last year of available records preferably not older than one (1) year; c. Estimate the stream flow at the identified/proposed sites and perform flow duration curves. In the use of stochastic or deterministic method of runoff estimation, calibrate the derived runoff with the base runoff of the base station. Present and discuss the conceptual models used; d. Gather water samples from several floodways, proposed project sites, and groundwater wells for water quality testing and mapping of polluted areas; e. Carry-out sediment transport analysis for several floodways and each project site (both hill Torrent and floodplain) for the determination of sediment-discharge relationship; f. Conduct flood studies for different return period. In estimating the unit hydrograph, preference is given to the use of actual peak discharge data from different flood events in the water source or nearby rivers; g. Compute the hydrographs for the following return periods in years: 2, 5, 10, 15, 20, 25, 50, 100; h. Carry out hydrological studies for assessing frequency of occurrence of droughts and floods in the Project areas to assist in project planning; i. Carry out hydrological studies for assessing the potential of floodwater diversions from the Indus River to selected sites in the project area in the light of the “Water Apportionment Accord”; j. Provide alternate options for areas already waterlogged and define measures to divert water for other uses k. Analyse and optimize the inter-linkage of structural and non-structural measures and their combined efficiency for effective flood management. Hill Torrents Data Collection a. Review the available data on hill torrents in the selected project areas and suggest systematic investigation to augment available data for covering the entire project area; b. Review or analyse existing sediment related issues in Hill Torrents; c. Identification of possible sites for installation of early warning systems upstream for protecting communities living in downstream areas; d. Assessment of the water quality of the floodwater in order to utilize it in other areas e.g. Agriculture, irrigation etc; e. Review and assess water storage capacities keeping in view the soil analysis and topography (slope) of the hill torrents; f. Design of diversion and storage interventions of hill torrents using EBA interventions; g. Identify possible locations for installation of earthen check dams and other EBA infrastructures with detailed designs and drawings; h. Prepare cost estimates for various physical interventions (EBA infrastructures) on selected feasible sites. Floodplains Data Collection a. Plan and design effective route plans for channels using Ecosystem Based Adaptation mechanisms to divert flood water-to-water bodies; b. Review of existing designs and capacities of channels and structures linked to existing lakes or water bodies especially the flood bypasses; c. Assess the potential of existing lakes or water bodies to retain water as well as recharge the groundwater d. Carry out soil analysis, and seepage, evaporation and transpiration assessment studies; e. Assessment of sediment studies to assess the reduction of lake capacity in flood season; f. Identify suitable depression sites in the project area for storage of floodwater diverted from River Indus; g. Carry out studies for conveyance of floodwater towards project area in suitable depressions; h. Plan and design embankment for forming new ponds for storage of floodwater; i. Prepare utilization plan of stored water; j. Identify for possible sites for early warning systems; k. Identify possible locations for Ecosystem Based Adaptation Interventions with detailed designs and drawings;

Project Preparation Facility GREEN CLIMATE FUND | PAGE 10 OF 18 Version 2.0

l. Prepare cost estimates for various physical interventions on selected feasible sites. 6. Deliverables The studies will produce the following deliverables: a. A detailed Prefeasibility Study (Activity 1) including detailed criteria and shortlisting of sites and identification of potential infrastructure/interventions on those sites for the floodplains/hill torrents management; b. List of recommendations emanating from pre-feasibility assessments and multi-stakeholder consultation sessions to shortlist final sites for detailed assessments; c. Detailed Feasibility Study (Activity 4) including the detailed designs, drawings and BOQs (Bill Of Quantities) of the proposed interventions at the selected project implementation sites; the feasibility study will include an assessment and recommendations for non-grant financing options and financial services to support nature based solutions and EbA, including public-private partnerships, blended financing, incentive schemes, micro- insurance, and community-based enterprises. d. A detailed hydrological assessment and soil analysis of the project sites in the Indus basin (flood plain and hill torrents); e. An estimation of potential benefits of the interventions in terms of flood handling, water utilization in agriculture, communities and groundwater recharging; f. Multi-stakeholder sessions to discuss recommendations from detailed feasibilities to finalize EbA/NbS solutions to be adopted in Hill Torrents and Floodplains. 7. Qualifications Education A firm/individuals having professionals of at least master’s degrees in Civil Engineering/Water Resource Management/Engineering, Environmental Sciences, Natural Resource Management, Social Sciences or other closely related fields Professional experience The team leader (international expert) should demonstrate: • At least fifteen (15) year of relevant experience in environmental assessments, flood risk management, water resources engineering/management; • Working experience in designing mitigation measures for projects in the field of Ecosystem-based Adaptation (wetlands restoration, hill torrents and catchment area management); • Experience conducting similar studies with other GCF, ADB and World Bank projects; • Experience in designing, managing or monitoring conservation and/or natural resource management projects; • The necessary expertise to organize and supervise topographic surveys and any other investigations required to provide necessary input data for preparation of feasibility studies, design of the interventions, and undertaking climate and hydrological modelling; • Experience in management and supervision of designs of non-structural engineering systems preferably EBA structures; • Experience working in the South Asian region would be an advantage; • Fluent in English, Urdu (preferred), and any local languages in the region (preferred). Other team members (national experts) should demonstrate: • At least five (5-10) years of experience in environmental assessments, civil engineering/water resource engineering/management, working with indigenous peoples; • Education background complementary to the field of the international expert; • Proven track record in facilitating participatory processes and engaging local communities; • Working experience contributing to the preparation of an ESMF report; • Fluent in English, Urdu , and any local languages in the region (preferred).

Project Preparation Facility GREEN CLIMATE FUND | PAGE 11 OF 18 Version 2.0

Annex 2: Terms of Reference: Environmental and Social Management Framework 1. Background and Introduction The Indus River is the lifeline of water-stressed Pakistan, but it also delivers catastrophic floods exacerbated by climate change. Pakistan currently relies on costly infrastructural flood management measures, having limited efficacy. This project brings a paradigm shift towards managing floods through large-scale ecosystem-based adaptation (EbA). It unifies 20 Government ministries and departments in a hitherto unprecedented collaboration to build Pakistan’s climate resilience and water security. The proposed three-pronged approach includes: ecosystem-based flood management through wetland restoration, hill-torrent management, and green infrastructures; community-based natural resource management, climate-adapted livelihoods and risk reduction; and a paradigm shift to scale up the EbA approach. This project proposes to undertake Ecosystem-based Adaptation (EbA) interventions at several priority sites nationwide, build resilience of communities, and enable the Government and relevant stakeholders to implement and replicate EbA work, providing a cumulative, no-regrets approach to building climate change resilience. The proposed interventions will enable better management of high peak flood flows in the Indus by employing EbA solutions to: 1) restore wetlands by diverting and storing floodwater from the Indus River, and: 2) manage hill torrents to slow down and divert flash floods that add to flood peaks in the Indus River.

The proposed project will have multiple, long-term, wide-ranging benefits for Pakistan, including: a) EbA that improves resilience to flooding and drought; b) increased capacity of water-stressed areas to efficiently store and use floodwater; c) enhanced recharge of groundwater through wetland restoration interventions, and hill torrent management interventions, e.g. watershed restoration, check dams, and terracing; and d) other environmental and socio-economic benefits, e.g. biodiversity and habitat conservation, carbon sequestration, wetlands based livelihoods. The project’s proposed activities will be implemented under three components and these are Component 1: Ecosystem-Based Adaptation for Integrated Flood Risk Management Component 2: Enhancing resilience of vulnerable communities to climate change Component 3: Enabling a paradigm shift towards Ecosystem Based Adaptation (EbA)

This proposed project proposal will require carrying out several technical feasibility studies, the development of the full GCF project document and monitoring/evaluation system, the definition of institutional arrangements, and the costing of proposed activities under the project.

WWF GCF Agency requires that all GCF projects comply with WWF’s WWF’s Environmental and Social Safeguards Framework, as detailed in the Environment and Social Integrated Policies and Procedures (SIPP). WWF’s Environment and Social Safeguards Integrated Policies and Procedures include the following policies: • Policy on Environment and Social Risk Management • Policy on Protection of Natural Habitats • Policy on Involuntary Resettlement • Policy on Indigenous Peoples • Policy on Accountability and Grievance Mechanism • Standard on Pest Management • Standard on Cultural Resources • Standard on Stakeholder Engagement • Standard on Public Consultation and Disclosure • Standard on Community Health, Safety and Security • Guidance Note on Dams and Dam Safety • Guidance Note on Labour and Working Conditions • Guidance Note on Gender-Based Violence and Sexual Exploitation, Abuse and Harassment The necessary safeguards assessments and/or mitigation plans will be commissioned subsequent to the GCF Agency due diligence site visits and screening. The Screening will be done at an early stage of PPF phase once the local socio-cultural, economic and political baseline is available, the theory of change has been confirmed and activities have been agreed upon. The screening will result in defining the detailed scope of the necessary safeguards documents by providing a preliminary description of potential environmental and social impacts to be analysed and

Project Preparation Facility GREEN CLIMATE FUND | PAGE 12 OF 18 Version 2.0

specific instruments required by the policies/standards triggered. The GCF Agency’s safeguards due diligence mission will be contingent on travel restrictions related to COVID-19 and the process will be adapted accordingly to remain in compliance with WWF’s safeguards policies and procedures.

The project’s proposed sites are scattered along a 1500 km stretch of the Indus, from Tarbela Dam (in Khyber Pakhtunkhwa Province) to Kotri Barrage (in Sindh Province). Specific project sites identified are: Manchar Lake, Darya Khan Ramak, Bhakkar Lala Creek Layyah, D.I. Khan Hill Torrents, Nara Canal-Deh Akro-Chotiari Complex, Esa Khel Watershed, Haleji & Hadero Lake, Kaha Hill Torrent, Chakar Lehri sub-basin. 2. Objective The objective of the ESMF is to propose mitigation measures identified during the screening and due diligence visits to mitigate any potential negative social and environmental impacts triggered by the Project. The ESMF will comprise ESMPs for each separate site, tailored to each local situation. The ESMF would encompass other mitigation plans such as the Indigenous Peoples Planning Framework, Process Framework, Environment Management Plan or any other specific type of mitigation plan. 3. Methodology The analysis should make use of existing literature and available statistics and analysis and will involve comprehensive exchange with all relevant stakeholders. The ESMF will be prepared after visits to the sites and through consultations with local communities, Indigenous people groups and other key stakeholders that may be potentially be affected by project activities. The ESMF will include guidance for developing site specific management plans once the project design activities have been identified during project implementation. 4. Tasks The Consultant is expected to undertake the following tasks: a) Policy, legal and administrative framework Analyse the policy, legal and administrative framework within which the project takes place and identify any laws and regulations that pertain to environmental and social matters relevant to the project. This includes: • regulations about assessment and management of environmental and social risks; • policies and regulations related to issues covered by WWF Environment and Social Safeguards Integrated Policies and Procedures; • requirements for public consultation and disclosure; • environmental authorization procedures relevant to the project; and • policies and regulations implementing the host country’s obligations under international law (e.g. on indigenous peoples, human rights.).

If gaps are identified, it will need to be described how this will be addressed by the project. b) Environmental and social baseline Describe and analyse the environmental and social context in which the project operates. The main purpose of this step is to provide an understanding of current environmental and social conditions that form the baseline against which project impacts can be predicted and measured during project implementation. While some broad contextual information is necessary, the analysis should focus on the immediate context of the project site and aspects that relate to the identified impacts in order to be relevant to decisions about project design, operation, or mitigation measures. The analysis will cover a range of physical, biological, socio-economic and cultural conditions relevant and/or potentially impacted by the project. c) Identification of affected groups Based on the stakeholder analysis prepared by the project design team, stakeholders need to be identified that might be affected by project activities (positively or negatively). The analysis should cover all relevant social groups present in the sites, in particular vulnerable groups, indigenous, tribal or traditional peoples. It should consider formally organized stakeholder groups such as government organizations, civil society organizations, academia and private sector as well as individuals present in the intervention sites without any formal organization. The identification of affected groups is instrumental for identifying the stakeholders to be consulted during the development of the ESMF.

Project Preparation Facility GREEN CLIMATE FUND | PAGE 13 OF 18 Version 2.0

This activity will require coordination with the stakeholder engagement consultant and gender consultant to ensure proper identification of stakeholders and project affected people. d) Assessment, prediction and significance of environmental and social impacts This Project is considered a moderate-risk project and hence does not require a scoping study. Therefore, the first step is to review and substantiate the results of the Screening by confirming potential impacts and/or identifying other potential impacts in consultation with relevant stakeholders and key informants. Once the list of impacts has been consolidated, predictions need to be made in terms of the impact’s probability and their magnitude. In accordance with the WWF’s Policy on Environment and Social Risk Management, the assessment should pay particular attention to impacts related to the WWF Environment and Social SIPP such as adverse impacts on indigenous peoples, cultural heritage, biodiversity or on people’s livelihood through access restrictions or resettlement. However, thematic coverage of the WWF’s Policy on Environment and Social Risk Management also involves other potential social impacts including impacts on women or vulnerable groups, health and safety risks, environmental risk issues not covered by the Standard on Protection of Natural Habitats or risks triggered by the project failing to take climate change effects into consideration.

When analysing the risks both direct and indirect impacts should be taken into consideration, such as inadvertent knock-on effects or cumulative effects that materialize through interaction with other developments, impacts occurring at the project site or within the project’s wider area of influence and impacts triggered over time. Once the impact issues have been confirmed, they need to be rated on their significance, which is important for prioritizing the mitigation measures. For social impact issues this task should be undertaken in consultations with the respective affected groups. Significance rating should consider the expected likelihood of the potential impact and the impact’s anticipated magnitude. The magnitude is influenced by factors such as sensitivity of receptor, severity of impact, manageability of impact, its duration and reversibility. The methods and analytical tools for analysing impacts should be commensurate with the type and significance of the impacts. It should allow rigorous assessment of the significant impacts using qualitative and to the extent possible, quantitative methods. Participatory research and assessment tools should be employed wherever sensible to enable participation of affected groups in the assessment of significance of impacts and the development of mitigation measures. e) Environmental and social management framework (ESMF) and plans (ESMPs) The main output of the ESMF process is a strategy for managing risks and mitigating impacts at the project sites; each site will have an ESMP prepared for its local situation. The aim of the project is to arrive at a suite of interventions for achieving intended restoration and ecosystem management outcomes in which adverse environmental and social impacts are avoided; if complete avoidance is not feasible it will need to be ensured that impacts are minimized and/or compensated for in a fair, equitable and agreed way. 5. Stakeholder consultation An appropriate level of stakeholder engagement in the ESMF process will ensure that impact scoping is comprehensives, that significance is thoroughly assessed, and that proposed mitigation actions are feasible, culturally appropriate and gender inclusive. Following WWF’s Standard on Stakeholder Engagement the scale and depth or intensity of engagement in the ESMF process is dependent on the concerns expressed, as well as the magnitude of expected impacts.

Consultation events held with affected people and other stakeholder groups need to be documented by providing dates of consultations, a list of participants together with a summary of issues raised and how they are or could be addressed in project design. A final stakeholder meeting should be organized towards the end of the fieldwork for gathering views on the draft ESMF and ESMPs. 6. Deliverables The ESMF (Activity 3) will produce the following deliverables: • An analysis of the legal national framework for addressing social and environment impacts; • An environmental and social baseline to monitor the effectiveness of mitigation measures; social baseline to be disaggregated between relevant social groups (e.g. vulnerable groups, indigenous people, etc.); studies to include demographic profiles, population mapping, poverty assessments, disaggregated socio- economic indicators (e.g. natural resource dependence, social inclusion, etc.)

Project Preparation Facility GREEN CLIMATE FUND | PAGE 14 OF 18 Version 2.0

• An assessment of environmental and social risks including risk matrix specifying likelihood and magnitude of each impact issue; • Identified mitigation measures presented with budget, implementation schedule and organisational responsibilities; • Development of other safeguard tools as required by the due diligence and screening of the project and the respective safeguards policies triggered; • In particular, if the Policy on Indigenous People is triggered: An Indigenous People Plan (IPP) or Indigenous People Planning Framework will be including evidence of free, prior and informed consent of indigenous people present in the site and/or affected by project activities; • Development of a project-level grievance mechanism; • Development of Environmental and Social Baselines based on assessments of selected sites, and development of overarching ESMF with site level ESMPs; • A list of key environmental and social indicators are identified and mainstreamed into the results framework and included in the project M&E plan.

7. Qualifications

Education At least a master’s degree in the area of forestry, water resource management, environmental sciences, natural resource management, social science or other closely related field. Professional experiences

The team leader (international expert) should demonstrate: • At least ten (10) years of relevant experience in environmental assessments, flood risk management, evaluating risks for indigenous peoples. socio-economic analysis, environment and social safeguards and environmental and social impact assessments (ESIA) and management frameworks (ESMFs); • Working experience creating ESMFs and designing mitigation measures for projects in the field of Ecosystem-based Adaptation (wetlands restoration, hill torrents and catchment area management); • Experience with other GCF projects; • Experience in designing, managing or monitoring conservation and/or natural resource management projects; • Experience working in the South Asian region would be an advantage; • Fluent in English, Urdu (required), and any local languages in the region (preferred).

Other team member (national expert) should demonstrate:

• At least five (5) years of experience in environmental assessments, working with indigenous peoples; socio-economic analysis; environment and social management plans; • Education background complementary to the field of the international expert; • Proven track record in facilitating participatory processes and engaging local communities; • Working experience in contributing to the preparation of an ESMF report concerning national resources management; • Fluent in English, Urdu (required), and any local languages in the region (preferred).

Annex 3: Terms of Reference: Gender Assessment 1. Background and Introduction The WWF GCF Agency, on behalf of and in collaboration with the Government of Pakistan, requests funding from the Project Preparation Facility (PPF), in order to prepare the project Integrated Flood Risk Management: Building Pakistan’s Resilience to Climate Change through Ecosystem-Based Adaptation.

Project Preparation Facility GREEN CLIMATE FUND | PAGE 15 OF 18 Version 2.0

The Indus River is the lifeline of water-stressed Pakistan, but it also delivers catastrophic floods exacerbated by climate change. Pakistan currently relies on costly infrastructural flood management measures, having limited efficacy. This project brings a paradigm shift towards managing floods through large-scale ecosystem-based adaptation (EbA). It unifies 20 Government ministries and departments in a hitherto unprecedented collaboration to build Pakistan’s climate resilience and water security. The proposed three-pronged approach includes: ecosystem-based flood management through wetland restoration, hill-torrent management, and green infrastructures; community-based natural resource management, climate-adapted livelihoods and risk reduction; and a paradigm shift to scale up the EbA approach. This project proposes to undertake Ecosystem-based Adaptation (EbA) interventions at several priority sites nationwide, build resilience of communities, and enable the Government and relevant stakeholders to implement and replicate EbA work, providing a cumulative, no-regrets approach to building climate change resilience. The proposed interventions will enable better management of high peak flood flows in the Indus by employing EbA solutions to: 1) restore wetlands by diverting and storing floodwater from the Indus River, and: 2) manage hill torrents to slow down and divert flash floods that add to flood peaks in the Indus River. The proposed project will have multiple, long-term, wide-ranging benefits for Pakistan, including: a) EbA that improves resilience to flooding and drought; b) increased capacity of water-stressed areas to efficiently store and use floodwater; c) enhanced recharge of groundwater through wetland restoration interventions, and hill torrent management interventions, e.g. watershed restoration, check dams, and terracing; and d) other environmental and socio-economic benefits, e.g. biodiversity and habitat conservation, carbon sequestration, wetlands based livelihoods. The project’s proposed activities will be implemented under three components and these are Component 1: Ecosystem-Based Adaptation for Integrated Flood Risk Management Component 2: Enhancing resilience of vulnerable communities to climate change Component 3: Enabling a paradigm shift towards Ecosystem Based Adaptation (EbA) The project’s proposed sites are scattered along a 1500 km stretch of the Indus, from Tarbela Dam (in Khyber Pakhtunkhwa Province) till Kotri Barrage (in Sindh Province). Specific project sites identified are: Manchar Lake, Darya Khan Ramak, Bhakkar Lala Creek Layyah, D.I. Khan Hill Torrents, Nara Canal-Deh Akro-Chotiari Complex, Esa Khel Watershed, Haleji & Hadero Lake, Kaha Hill Torrent, Chakar Lehri sub-basin. 2. Objective The main objective of a gender assessment is to collect gender-specific data that will lead to gaining knowledge on roles of women and men in the Recharge Pakistan project area (once identified), the decision-making processes among women and men at the community level, control over the management of natural resources and the types of resources, access to land by women and men in the project area, etc. The aim is to identify gaps, opportunities and solutions to improve active and equal participation of both women and men in climate change adaptation and promote more equitable management of, and benefits from, the use and protection of natural resources, including water resources. Specific Objectives a) Provide clear background information on the context and the situation relating to gender issues in the project area (local, national, regional levels as appropriate) and more generally; b) Collect sex- and age-disaggregated data in at least five domains of the gender assessment – access to, use of and control over resources (revenues, employment, land, etc.); roles, responsibilities and utilization of time; norms, beliefs and perceptions; laws, policies, institutional practices; and decision-making processes; c) Identify constraints and opportunities for the full and equal participation of women and men into the project activities; d) Identify sustainable economic activities of interest to women and men to improve their livelihoods and wellbeing; e) Formulate recommendations to orient the implementation of a gender-responsive project through a Gender Mainstreaming Action Plan; f) Reinforce all project staff knowledge and capacity in the implementation of a project sensitive and responsive to gender issues and mainstreaming, including support to the project development team in conducting gender-responsive stakeholder consultations through the project design phase and the project life cycle.. 3. Scope of Work a) Elaboration and preparation for the data collection: 1) Literature review and desk study of existing gender-related data and information;

Project Preparation Facility GREEN CLIMATE FUND | PAGE 16 OF 18 Version 2.0

2) Preparation of the data collection tools; 3) Plan partner identification meetings; 4) Conduct gender responsive stakeholder consultations throughout the project development phase (and the whole project cycle) to provide details on gender-related issues, dynamics, and roles specific to the project area(s) necessary to consider in achieving the project objectives. b) Data collection in the project site (for each survey site, the general steps mentioned below should be followed): 1) Organize information sharing meetings with project stakeholders (local authorities, community leaders, etc.) to inform them of the survey objectives, the methodologies used and the timeline for data collection and the potential timeframe for sharing survey results; 2) Organize a separate meeting with community-based organizations and local associations identified in the project area; 3) Hold individual interviews or conduct focus group discussions with various age-groups to gather further qualitative data about the local gender dynamics and the context of this particular area; 4) Proceed to conduct household interviews in the various pre-selected sites for the survey as appropriate; 5) Set up a meeting with local authorities and other relevant stakeholders to provide feedback/report on the data collection process and schedule follow up community meetings to communicate survey results and recommendations. 4. Expected Outputs/Deliverables a) A Gender Assessment (Activity 2) detailing baseline data on the gender dynamics and the status of women in the context of the project, including an analysis of the national policies that promote gender equality that could provide an enabling environment supportive of a gender-responsive approach in the project. The report will also relate gender issues to climate change which will constitute the project’s base for a monitoring and evaluation plan for gender integration; b) A set of recommendations that can be incorporated into project design in order to ensure improvement of women’s conditions in general and more specifically as it relates to climate change adaptation work and equitable access to, and benefit from, resources in each targeted area of the project; c) A Gender Mainstreaming Action Plan (Activity 2) is developed according to the survey results, recommendations, and relevant results obtained in the stakeholder consultations for implementation of gender-responsive activities throughout the life of the project; d) A list of key gender-related indicators are identified and mainstreamed into the results framework and included in the project M&E plan, which include sex-disaggregated data wherever possible. 5. Qualifications Professional experiences: The team leader (international expert) should have: • Proven experience in conducting surveys (socio-economic, gender, etc.) and evaluation with strong expertise in gender-related work; at least (10) years of experience is preferred; • Ability to work in teams and monitor/supervise the work of local consultants as part of the gender assessment team • Previous experience and good comprehension of the local context where the survey will be conducted; • Fluent in English, Urdu (required), and any local languages in the region (preferred).

Annex 4: Preliminary Environmental and Social Safeguards Categorization Memorandum

Project Title: Recharge Pakistan: Building Pakistan’s Resilience to Climate Change Date: through Ecosystem-Based Adaptation for Integrated Flood Risk Management 4/13/2020 Project Location and salient physical characteristics relevant to the safeguard analysis: The project’s proposed sites are scattered along a 1500 km stretch of the Indus, from Tarbela Dam (in Khyber Pakhtunkhwa Province) to Kotri Barrage (in Sindh Province). Proposed project sites are: Manchar Lake, Darya Khan Ramak, Bhakkar Lala Creek Layyah, D.I. Khan Hill Torrents, Nara Canal-Deh Akro-Chotiari Wetlands Complex, Esa Khel Watershed, Haleji & Hadero Lake, Kaha Hill Torrent, Chakar Lehri sub-basin.

Project Preparation Facility GREEN CLIMATE FUND | PAGE 17 OF 18 Version 2.0

Project Description: This project’s goal is to implement ecosystem-based adaptation (EbA) at scale to effectively reduce flood risks and secure groundwater recharge presents a paradigm shift for the country - transitioning to the consistent integration of EbA interventions using nature based solutions to increase the efficiency of hard infrastructure development to help address challenges presented by increased precipitation variability and intensity caused by climate change. This requires extensive feasibility studies and assessments to be effective.

The project’s focus on EbA depends on the evidence-based identification of sites where these interventions would be most effective. Potential sites have been identified with stakeholders in each province, but detailed engineering designs and cost-benefit analyses to identify the best adaptation solutions are needed. In parallel, detailed ecological, socio-economic, and gender assessments will be required to establish baselines and develop management plans to minimize negative and maximize positive impacts.

The project’s work to enhance vulnerable communities’ resilience and create necessary policy enabling environments also requires: improved vulnerability assessments; detailed identification of appropriate adaptation interventions; further policy reviews and gap analysis to align the project with relevant government plans and policies; updated institutional capacity needs assessments and climate resilience planning; detailed integrated flood risk and groundwater management planning involving extensive consultations with stakeholders, potential partners and co-financers to ensure project ownership and support.

The project’s proposed activities will be implemented under three distinct components: Component 1: Ecosystem-Based Adaptation for Integrated Flood Risk Management Component 2: Enhancing resilience of vulnerable communities to climate change Component 3: Enabling a paradigm shift towards Ecosystem Based Adaptation (EbA

Feasibility studies will be conducted under the Project Preparation Facility Grant will include detailed analysis and assessments of the proposed sites with specific reference to: a) EbA that improves resilience to flooding and drought; b) increased capacity of water-stressed areas to efficiently store and utilize floodwater; c) enhanced recharge of groundwater through wetland restoration interventions and hill torrent management as well as other social, economic and environmental co-benefits.

The preliminary assessment of policies triggered are below and will be later validated and finalized once activities have been better defined and site visits have been conducted. The project is preliminarily categorized as Category B based on available information. This Categorization will be validated or may be revised once feasibility assessments are completed to identify the proposed activities and potential sites. Safeguard Policies Triggered Yes No

Natural Habitats X

Pest Management X

Indigenous Peoples X

Involuntary Resettlement X

Cultural Resources X

Community Health and Safety X

In addition to the above, given the nature of the activities to be financed the proposed project will prepare a full Stakeholder Engagement Plan (SEP) during project preparation. Given that WWF does not have a standalone policy on Dam Safety for the purposes of this project, FAO’s Guidelines on Small Dams will be used for purposes of dam safety.

Summary of Key Safeguards Issues:

Project Preparation Facility GREEN CLIMATE FUND | PAGE 18 OF 18 Version 2.0

Natural Habitats: The overall environmental and social impacts of the proposed project are expected to be overwhelmingly positive and the project expected impacts on Natural Habitats are also expected to be significantly positive, through efforts to improve Pakistan’s climate resilience and water security through ecosystem-based adaptation. Nonetheless, potential small-scale impacts on Natural Habitats may occur due to the construction of green infrastructure and the promotion of livelihood activities. Provision would be made in the ESMF to adequately address such possibilities. Any relevant sub grant financed activity under the project will be screened for its potential to cause negative impacts to natural habitats under the ESMF procedures. If any such activity is likely to cause irreversible or significant damage to habitats it will be excluded from project grant funding.

Pest Management: As part of livelihoods development, the project will include climate smart agriculture. Therefore, the Standard on Pest Management has been triggered. Upon further definition of activities, if the project activities involve the acquisition, use, or storage of pesticides, a Pest Management Plan would be developed to minimize associated risks.

Indigenous People: The specific project sites are not yet defined; however, there is a possibility that the project may be operational in areas where indigenous people live. Therefore, if there is a potential that the selected sites would be near or affect indigenous people, an Indigenous People’s Planning Framework (IPPF) will be prepared which contains basic principles, social concerns unique to IP groups, guidance on the identification of IPs and consultation strategies that will guide the preparation of Indigenous Peoples Plans (IPPs) where and when required. The IPPF, if deemed necessary, will be approved and disclosed before project design finalization.

Involuntary Resettlement: The project is not expected to involve land acquisition leading to involuntary resettlement of project affected persons (PAPs). All project activities will be executed on government or community-owned lands. Project activities are also expected to positively affect local communities’ access to livelihoods. However, some of the planned activities may have some minor effects on the livelihoods of local communities, such as temporarily restricting access to natural resources. To mitigate any adverse impacts, all activities that may affect local communities’ access livelihoods should be closely coordinated with community representatives and only carried out after consultations with all relevant stakeholders. If disturbance of access to livelihoods cannot be avoided, full and timely compensation shall be provided to all livelihood users, irrespective of their formal land ownership status or title. Full details regarding these measures will be provided in the ESMFs.

Cultural Resources: There is a possibility that there will be physical or intangible cultural resources in the project sites. Should cultural resources be identified and potential risks be present, this standard would be triggered in order to develop mitigation actions to protect the cultural resources.

Community Health and Security: This standard is triggered primarily due to the construction of green infrastructure. While the green infrastructure will bring benefits for both the environment and communities, there could be potential short term environmental or health impacts that need to be managed properly.

Recharge Pakistan: Building Pakistan’s Resilience to Climate Project/Programme Title: Change through Ecosystem-Based Adaptation for Integrated Flood Risk Management

Country(ies): Pakistan

National Designated Ministry of Climate Change, Government of Pakistan Authority(ies) (NDA):

Accredited Entity(ies) (AE): World Wildlife Fund (WWF)

Date of first submission/ 2019-08-17 V.01 version number:

Date of current submission/ 2020-05-28 V.04 version number

Please submit the completed form to [email protected], using the following name convention in the subject line and file name: “CN-[Accredited Entity or Country]-YYYYMMDD”

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2

Notes • The maximum number of pages should not exceed 12 pages, excluding annexes. Proposals exceeding the prescribed length will not be assessed within the indicative service standard time of 30 days. • As per the Information Disclosure Policy, the concept note, and additional documents provided to the Secretariat can be disclosed unless marked by the Accredited Entity(ies) (or NDAs) as confidential. • The relevant National Designated Authority(ies) will be informed by the Secretariat of the concept note upon receipt. • NDA can also submit the concept note directly with or without an identified accredited entity at this stage. In this case, they can leave blank the section related to the accredited entity. The Secretariat will inform the accredited entity(ies) nominated by the NDA, if any. • Accredited Entities and/or NDAs are encouraged to submit a Concept Note before making a request for project preparation support from the Project Preparation Facility (PPF). • Further information on GCF concept note preparation can be found on GCF website Funding Projects Fine Print.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 1 OF 13

A. Project/Programme Summary (max. 1 page) ☒ Project A.2. Public or ☒ Public sector A.1. Project or programme Programme Private sector ☐ private sector ☐ Yes ☐ No ☒ Confidential A.3. Is the CN submitted in If yes, specify the RFP: ☐ A.4. Confidentiality ☒ Not confidential response to an RFP? ______

Mitigation: Reduced emissions from:

☐ Energy access and power generation

☐ Low emission transport

☐ Buildings, cities and industries and appliances

A.5. Indicate the result ☐ Forestry and land use areas for the Adaptation: Increased resilience of: project/programme ☒ Most vulnerable people and communities

☒ Health and well-being, and food and water security

☒ Infrastructure and built environment

☒ Ecosystem and ecosystem services Direct beneficiaries: 10 A.7. Estimated million people (~5% of A.6. Estimated mitigation adaptation impact ~207 million) impact (tCO2eq over Not Applicable (number of direct Indirect beneficiaries: lifespan) beneficiaries and % of Approximately 20 population) million (~10% of ~207 million) Amount: USD 50 A.8. Indicative total project Amount: USD 150 million A.9. Indicative GCF cost (GCF + co-finance) funding requested million A.10. Mark the type of financial instrument ☒ Grant ☐ Reimbursable grant ☐ Guarantees ☐ Equity requested for the GCF ☐ Subordinated loan ☐ Senior Loan ☐ Other: specify______funding A.12. Estimated 10 years (2020-2030; A.11. Estimated duration 10 years project/ Programme this is Phase 1 of a 30 of project/ programme: lifespan year Program Vision) Yes ☒ No ☐ Other support received ☒ If so, by A.13. Is funding from the ☐ A or I-1 who: Cash, data, and in-kind Project Preparation A.14. ESS category ☒ B or I-2 support from WWF (USD 70,000) Facility requested? ☐ C or I-3 and Government of Pakistan (USD 100,000) A.15. Is the CN aligned A.16. Has the CN been with your accreditation Yes ☒ No ☐ Yes ☒ No ☐ shared with the NDA? standard?

A.18. Is the CN A.17. AMA signed (if Yes ☒ No ☐ included in the Entity Yes ☒ No ☐ submitted by AE) Work Programme?

The Indus River is Pakistan’s lifeline, and is now experiencing catastrophic floods and droughts exacerbated by climate change. Pakistan relies on costly hard-infrastructure flood and water management measures with limited efficacy. This project will build A.19. Project/Programme Pakistan’s climate resilience and water security through cost-effective ecosystem-based rationale, objectives and adaptation. Recharge Pakistan will: increase water storage and recharge through approach of wetlands, floodplains, and hill-torrents management; promote climate-adapted programme/project (max community-based natural resource management and livelihoods; and forge a paradigm 100 words) shift to scale up this approach. This project unifies several Government entities in an unprecedented collaboration with WWF-Pakistan to effect nature-based solutions for crucial climate change adaptation in Pakistan.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 2 OF 13

B. Project/Programme Information (max. 8 pages) B.1. Context and baseline (max. 2 pages) Pakistan’s Climate Vulnerabilities Pakistan is a lower-middle income country, with USD 1,443.6 per capita GDP (World Bank, 2016), and a population of 207.8 million (Government of Pakistan, 2017d). It is ranked the 8th most affected country in the world on Germanwatch’s Long-Term Climate Risk Index (1998-2017), with losses from recent disasters amounting to USD 3.8 billion in Purchasing Power Parity terms (Eckstein et al., 2018). In addition, Pakistan is one of the most water-stressed countries of the world, with average per capita water availability of 964 m3 per annum (Government of Pakistan, 2014). It has one of the world's highest water use and water intensity rates (water used per unit GDP). Water is crucial for the country’s predominantly agriculture-based economy, which accounts for 19.5% of GDP, 42.3% of jobs (Government of Pakistan, 2017c), and 91.6% of the annual freshwater usage (UNDP, 2016b). Climate change is anticipated to alter annual precipitation patterns and exacerbate floods and droughts across Pakistan (Annex 1B). Water availability is expected to be less predictable, and floods and droughts more common. Moreover, studies indicate that Pakistan will reach ‘absolute scarcity’ water levels by 2025 (Government of Pakistan, 2018) due to depleting ground-water resources, thereby adding to climate change induced vulnerabilities of millions of poor people affected by lack of water, food and energy security. During the catastrophic 2010 Indus flood, which affected more than 20 million people, approximately 2,000 lives were lost, 3,000 people were injured, 1.6 million houses and millions of acres of crops were damaged, and financial damages were estimated at USD 40 billion. Since then, Pakistan has experienced large floods for 6 consecutive years, which is unprecedented (Government of Pakistan, 2017e). Indus River Basin: Water Resources and Infrastructure, and Historical Trends and Projections for Climate Pakistan is highly dependent on the Indus River that flows 3,200 km down the length of the entire country and is fed by five tributaries. The target sites for this proposed ‘Recharge Pakistan’ project are scattered along a 1300km stretch of the Indus River from Tarbela Dam to Kotri Barrage across four provinces, and include a mix of upstream (watersheds and hill torrents) and downstream (wetlands and floodplains) locations (Annex 1A). Renewable water resources in the Indus Basin amount to approximately 175 billion cubic meters (bcm), fed by glacier and snow melt from the Hindukush- Karakoram-Himalayan ranges and monsoon rains. Almost 82% of the water inflows are during summer (April-September) and about 18% in winter (October-March). The Indus Basin hosts one of the world’s largest irrigation systems and supports 95% of the nation’s irrigated agriculture; the existing infrastructure includes 4 reservoirs, 16 barrages, 12 inter- river link canals, irrigation canals, and flood embankments (Annex 1C). However, the present water storage capacity of Pakistan corresponds to just 15% of the average river flow, i.e. far lower than the world average, and this capacity is decreasing annually by 0.2 MAF due to heavy sediment load (Qureshi, 2011; ADB, 2017). The Indus River also brings increasingly frequent and severe riverine floods, which build up slowly from heavy rains and glacial melt, and flash floods from hill torrents that are due to sudden, heavy cloudbursts. Over the last century, Pakistan’s average annual temperature has increased by 0.57°C and the average annual precipitation has increased by 25%. Heat waves per year increased by 31 days in the period of 1980 to 2007, while cold waves decreased in north-eastern and southern parts, and increased in western and north-western parts of the country. Annual precipitation has increased by 61 mm in Pakistan from 1901 to 2007; monsoon rains increased by 22.6 mm, and winter precipitation increased by 20.8 mm. During 1960–2007, there has been: an increase of 0.6°C to 1.0°C in the mean temperature over the hyper arid plains, arid coastal areas, and mountain regions of Pakistan; a decrease of 10%–15% in winter and summer rainfall in the arid plains and coastal areas; and a rise of 18%–32% in the summer rainfall over the core monsoon region of Pakistan. The number of heavy rainfall events has increased since 1960, and the nine heaviest rains recorded in 24 hours were recorded in 2010. The figures below illustrate: 1) the time series data for area-weighted mean annual temperatures; 2) long-term annual average precipitation; and 3) the occurrences of floods, landslides (mainly due to hill torrents and flash floods) and droughts in Pakistan. (ADB 2017)

Figure 1: Time Series of Area-Weighted Mean Daily Temperatures Averaged Yearly, 1960–2013 (ADB, 2017)

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 3 OF 13

Figure 2: Time Series Annual Average Precipitation in Millimetres, 1901–2007 (ADB 2017)

Figure 3: Occurrence of Flood, Landslide, and Drought Events 1985-2018 (World Bank Group, 2020)

National level climate change projections for the Indus Basin conducted by the Pakistan Meteorological Department (PMD) in 2015 provide empirical evidence of increasing variability in mean annual temperatures (oC) and precipitation levels (mm) for the Upper Indus Basin and Lower Indus Basin. The trends projecting variations in temperature and rainfall patterns under the Representative Concentration Pathways (RCP) 4.5 emission scenario and RCP 8.5 emission scenarios (see Figure 4 below), reveal an estimated 3 – 5oC rise in the entire Indus Basin by 2060; Pakistan’s projected temperature increase is expected to be higher than the global average. Whereas, high peaks of precipitation levels are forecasted between 2011 – 2100, indicating frequently occurring heavy rainfalls in some instances and conditions of extreme drought in others. (ADB, 2017) To elaborate, projections show an annual increase in temperature of 3°C – 4°C under RCP 4.5 in the northern areas of Pakistan, as well as 2°C – 3°C under RCP 4.5 in the southern part of the country, this demonstrates an accelerated rate of warming at high elevations that will impact snow and glacial melt. The annual precipitation also shows an overall increase of 2 – 3 mm/day under RCP 4.5. Heavy rainfall event analysis shows intense rainfall events over Pakistan being confined to the key monsoon region and coastal area of Sindh with return periods of 1 to 2 years. A significant increase in the number of dry days is expected, i.e. 130/year under RCP4.5 scenario. As a consequence of longer dry periods with intense heavy precipitation days, there is a higher risk of flooding because the decrease in regular light and moderate rainfall will make the ground drier, harder and unable to absorb excess water in short spans of time. (Ikram, et al. 2016)

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 4 OF 13

Figure 4: Pakistan’s Mean Annual Temperature and Precipitation Deviation Projections during 21st Century Using Two Different Emission Scenarios (ADB, 2017)

Hence, extreme rainfall events in the future, including the projected increase in the South-Asian monsoons (Pachauri & Meyer, 2014), combined with drier and more compacted soil due to higher temperatures and reduced wet days, will increase flood peaks and associated damage through higher frequency and intensity of flash floods in hill-torrent prone areas (Babar et al., 2016). Natural wetlands and floodplains that regulate floods have been disconnected and constrained by irrigation infrastructure, and catchment areas have been degraded, reducing the ecosystems’ groundwater recharge and storage capacity. This has hampered the Indus Basin’s natural ability to absorb runoff, passing extra flows downstream, and exacerbating flood peaks. Integrated ecosystem-based adaptation across the Indus Basin is, therefore, critical for Pakistan to adapt and build resilience to climate change, and to effectively utilize floodwater in dry spells to overcome water insecurity and associated socio-economic and environmental challenges. Climate Change Impacts on Vulnerable Communities and Ecosystems According to the Multidimensional Poverty Index, 38.8% of Pakistan’s population is poor. Most of the poor reside in rural areas (54.6% rural poverty), including this proposed project’s target sites (Annex 1E provides the population and poverty profile of proposed sites), and are disproportionately more vulnerable to climate change impacts (UNDP, 2016a). Factors that contribute to and compound this vulnerability include high dependence on agriculture, livestock, and fishing livelihoods, and inadequate safe drinking water, food, and basic services. Climate change is already causing and will worsen: unpredictable floods and droughts; decreased agriculture productivity, especially for wheat and rice; reduced water availability per capita; degradation of surface water quality; increased irrigation demand due to higher evaporation rates at higher temperatures; reduction in water storage capacities due to higher sedimentation from floods; and other issues, exacerbating communities’ vulnerability (ADB, 2017). Pakistan’s projected temperature rise and increased uncertainty and variability in precipitation, glacial melt, and river flows (ADB, 2017), will impact the Indus Basin’s wetlands, floodplains, and watersheds ecosystems and their services. Vulnerable communities depend on the water supply and recharge, food and products, flood protection, sediment control, carbon sequestration, climate regulation, and other benefits provided by these ecosystems for their survival. For example, ecosystem services from Keenjhar Lake, in the lower Indus Basin, have an estimated Total Economic Value of over USD 11,500/hectare1 (Dehlavi & Nawaz, 2012). Degradation of wetlands, forests, and pastures due to climate change is causing habitat and land productivity loss and decreasing grazing areas and fodder (ADB, 2017). These are compounded by the constraints on the Indus Basin by irrigation infrastructure and other stresses, e.g. pollution of ecosystems, adding to the vulnerability of communities and their livelihoods. Water Resources and Flood Management Sector in Pakistan In Pakistan there are numerous Government stakeholders at the federal, provincial, and local levels that govern the environment, water resources, flood management, and other sectors relevant for the proposed concept. At the Federal level: Ministry of Water Resources, and its attached departments and agencies (e.g. the Federal Flood Commission) oversee water resources management, hydropower development, flood management, and National Water Policy implementation; Ministry of Climate Change (NDA for GCF) holds the mandate for environment and climate change policies and interventions; the National Disaster Management Authority coordinates and implements disaster risk

1 Total Economic Value (TEV) figure was inflation adjusted in 2012, from a TEV derived in 2008 under a WWF-Pakistan study; this TEV assumes a limitless time horizon.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 5 OF 13 reduction and management strategies; and others. The Provincial Irrigation, Drainage, Environment, Disaster Management, and other Departments manage water use, irrigation, and floods and implement plans on the ground. Annex 2 describes Government stakeholders and Annex 3 outlines stakeholder engagement for this concept. Country Ownership and Alignment - Building Resilience to Indus Floods is a National Priority Improving resilience to climate change hazards, particularly floods and droughts, is among the top priorities for the Government of Pakistan (GoP). Following a Ramsar Advisory Mission (RAM) recommended exposure visit to China’s Yangtze Basin project (which integrates ecological solutions with ‘hard’ infrastructure to optimize water resource management), the GoP increasingly recognizes that “a mono-disciplinary approach based on engineering solutions alone - as in the case of the Indus Basin - cannot fully handle hydrological cycles, ecosystems, and the security of people prone to flood risks” (Ali, 2013). A ‘Diversified Portfolio Approach’ is needed, combining: infrastructure; non-structural interventions, e.g. floodplain zoning; and green infrastructure, e.g. wetlands restoration and reconnection, for ecosystem- based adaptation (Opperman et al., 2017). WWF’s desk research and stakeholder consultations illustrate that nearly all of Pakistan’s ongoing and in-pipeline initiatives for water resource management focus on hard infrastructure (Annex 10). This project’s interventions, by contributing towards regulation of flow and recharge of water bodies, will help sustain those projects (in proximity or further downstream) that aim to improve water supplies for communities. This proposed project will also contribute towards achieving commitments under relevant policies, including the National Climate Change Policy and Pakistan’s Nationally Determined Contributions (NDCs). It contributes to the short, medium (2030), and long-term visions of the NDCs by “enhancing integrated water resource management” and “harvesting rainwater and floodwater”, sub-national adaptation planning, capacity building, and climate resilient infrastructure. Under NDC Priorities, it contributes to “additional water reservoir capacity on the river system to regulate water discharges during high floods” and “promote(s) local rainwater harvesting and development of small storages on run of the rivers during peak flows” (Government of Pakistan, 2016). Alignment with other commitments and policies, e.g. Pakistan’s Strategic Framework for Engagement with GCF, National Flood Protection Plan IV, National Water Policy, and Sustainable Development Goals, are discussed in Section B.3. In addition, the proposed project is aligned with, and complements, other initiatives, e.g. World Bank’s and Asian Development Bank’s Balochistan Integrated Water Resources Management work, the GCF funded ‘Scaling Up of Glacial Lake Outburst Flood (GLOF-II) Risk Reduction in Northern Pakistan’ project being implemented by UNDP, and FAO’s ‘Climate Resilient Agriculture and Water Management’ proposal in the pipeline for GCF funding. This proposed concept brings together more than 20 Government of Pakistan Ministries and Departments in a concerted and collaborative action in the face of increasing climate change impacts. The concept has generated momentum and ownership for a “Recharge Pakistan” vision among the highest levels of the Government of Pakistan. It is 1 of 5 national initiatives that the Ministry of Climate Change is prioritizing and is being discussed internationally at platforms such as UNFCCC’s COPs. Barriers to be Addressed There are various policy, financial, and capacity constraints that inhibit the GoP from responding effectively to climate change. 1) Lack of holistic, basin level policy and planning: There is still neither an Indus Basin management plan, nor a holistic flood management plan; the National Water Policy was approved (2018) after a decade. There has historically been an ad-hoc, reactive approach to flood management. Provincial Irrigation Departments have Annual Flood Fighting Plans that focus on maintenance of flood embankments and irrigation infrastructure, without addressing vulnerable ecosystems and communities. 2) Inadequate finances and coordination across government entities: There are several GoP ministries, departments, and agencies at the federal, provincial, and district levels, with different plans, policies, and mandates for flood and disaster management. These lack coordination, coherence, and adequate budgets; only 5-7% of their budget is designated for climate change adaptation (see sections B.3. and C.2.). GoP plans predominantly focus on hard infrastructure for flood protection that incurs significant annual rebuilding and maintenance costs. 3) Limited capacities for effective inclusion of climate change adaptation in planning instruments: Information on future scenarios and long-term impacts of climate change is not incorporated within GoP policies and development plans. There is no precedence for ecosystem-based solutions, e.g. storage for flood peak attenuation, being included in plans. Bridging this gap in knowledge is critical, as it limits GoP decision makers to traditional, reactive options for flood risk and disaster management plans and investments. These inadequacies result in large-scale loss of infrastructure, livestock, crops, and other assets during floods. 4) Limited knowledge about ecosystem services and livelihood options for vulnerable communities: There is lack of expertise to harness flood mitigation and other ecosystem services provided by floodplains, watersheds, and wetlands, limiting inclusion in GoP planning for climate change adaptation and communities’ resilience. Limited economic options restrict communities to livelihoods (e.g. agriculture) that are not only negatively impacted by climate change (e.g. unpredictable harvests) but increase their vulnerability to climate change impacts and economic shocks (e.g. inability to climate-proof assets due to worsening poverty-environment cycle). Women and marginalized groups are at higher risk of negative impacts due to lack of access to knowledge and livelihoods options, and exclusion from the decision-making on climate adaption solutions that meet their needs. B.2. Project/Programme description (max. 3 pages) Rationale Flooding is increasing in intensity and frequency in the Indus Basin, with large numbers of vulnerable people adversely affected, and the capacity of existing grey infrastructure to manage the flood volumes is limited, resulting in serious humanitarian and economic impacts. Integrated flood risk management is now a key national priority for the Government of Pakistan (GoP). The project proposes to undertake ecosystem-based adaptation (EbA) interventions that will store flood water in wetlands, floodplains and depressions (green infrastructure) at several priority sites, build resilience of

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 6 OF 13 communities at these sites, and enable the GoP and relevant stakeholders to implement and replicate EbA work, providing a cumulative, no-regrets approach to building climate change resilience. To ensure that the EbA interventions are sustained and continue to function effectively, the project will ensure that climate-adapted, community-based natural resource management is implemented locally. Thus, this project will contribute towards improving water and food security at a national level, and climate-adapted livelihoods locally, increasing resilience through the protection and restoration of ecosystems, and building the climate resilience of vulnerable communities in the Indus Basin. Theory of Change IF: a diversified portfolio approach is taken for integrated flood risk management in the Indus Basin, which includes green infrastructure for ecosystem-based adaptation, going beyond traditional hard infrastructure investments only; local communities at target sites are involved in ecosystem restoration and management that benefits their livelihoods and empowers them to build their own resilience for climate adaptation; and there is Government leadership to drive a paradigm shift towards mainstreaming EbA into sectoral plans across Government entities through a multidisciplinary, coordinated approach. THEN: the proposed project will create multi-sectoral, long-term benefits for Pakistan, including: a) improved resilience of vulnerable communities to river and hill-torrent flooding; b) increased capacity of this water- stressed country to efficiently store and use floodwater; c) enhanced recharge of groundwater; d) improved biodiversity, habitat conservation, and other ecosystem services e.g. carbon sequestration; e) climate-adapted alternative livelihoods for local communities; and f) a new standard for integrated flood risk management that combines scalable green and grey infrastructure approaches in Pakistan. The Theory of Change is given below and in Annex 4.

Project Locations Ten possible sites, including upstream watersheds and hill torrents and downstream wetlands and floodplains that are linked to the Indus River, have been identified based on flood risks, climate projections, water storage and recharge potential, and local communities’ needs. These are scattered along a 1300km stretch of the Indus River, across the provinces of Khyber Pakhtunkhwa, Punjab, Balochistan and Sindh. Please see the map provided below. From these potential sites, at least 6 will be shortlisted for this project after detailed feasibilities are carried out for funding proposal development. Annex 1 provides details on site selection criteria, maps, climate projections, and a concept illustration (also provided further below) for one proposed site as an example.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 7 OF 13

Project Preparation Phase The project will be applying for Project Preparation Facility (PPF) support to supplement GoP and WWF funds to finance the necessary assessments for the development of a full funding proposal for the GCF. These assessments will include but will not be limited to: gender-responsive and inclusive local communities’ consultations and assessments on water rights and natural resource use and management; stakeholder consultations and feasibility studies for drafting site- specific Integrated Flood Risk Management (IFRM) plans with detailed designs and costing of EbA and green infrastructure interventions; assessments of surface water and groundwater water balance and storage potential at sites, e.g. using the Basin Assessment Scenario Intervention Tool; local socio-economic analyses and gender assessments; development of Environmental and Social Management Framework (ESMF) and Environmental Management, Social Management, and Gender Action Plans; Community-Based Natural Resource Management Plans; and a Monitoring & Evaluation Plan.

Project Outline: Annex 5 provides a detailed project outline and proposed EbA interventions. Vision: By 2050, ecosystem-based adaptation contributes towards better climate resilience, water and food security, and sustainable livelihoods in Pakistan. Impact: By 2030, flood risk reduced and water recharge enhanced at 6 sites in the Indus Basin, building resilience of 10 million people and vulnerable ecosystems. Component 1: Ecosystem-Based Adaptation for Integrated Flood Risk Management Outcome 1: Floodwater and hill torrent management improved, through ecosystem-based adaptation at selected sites across the Indus Basin Output 1.1: Ecosystem-based adaptation supports functional and resilient floodplain and watershed ecosystems 1.1.1: Multi-stakeholder consultations for: final adjustments of Integrated Flood Risk Management (IFRM) plans; alignment with GCF and other donor-funded initiatives in the Indus Basin (e.g. GLOF-II); and partner mobilization for implementation. 1.1.2: Implement site-specific EbA interventions as per IFRM plans (Annex 5B gives details of recommended EbA interventions): 1.1.2.1 – Integrated floodplain management to manage flood flow in the Indus River: multi-purpose flood bypasses; diversion of flood water to wetland restoration sites; restoring degraded wetlands; introducing suitable sub-surface water storage solutions; riverine afforestation; and erosion control. 1.1.2.2 – Hill- torrent management in catchments, to alleviate flood peak pressures on the Indus River: watershed management, e.g. check dams, delay-action/recharge dams, terracing, and afforestation; flash flood dispersion for spate irrigation; diversion and storage for dry season. 1.1.3: Implement Environmental Management Plans. Output 1.2: Sustainability of EbA interventions ensured and case for replication established

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 8 OF 13

1.2.1: Collate data against baselines and indicators (including metrics for a ‘Ground Water Atlas’ under National Water Policy), conduct economic valuation of ecosystems and their services and benefits (using tools such as InVEST), and prepare case studies. 1.2.2: Measure progress and impact of EbA and green infrastructure, including risk reduction impacts, ecosystem benefits such as groundwater recharge, improved soil and water quality, and number of beneficiaries. 1.2.3: Develop protocols and guidelines with relevant provincial government line departments to ensure maintenance and sustainability of the project’s EbA interventions. 1.2.4: Disseminate lessons learnt for improving and building the case for replication of EbA in other flood prone sites. Component 2: Enhancing Resilience of Vulnerable Communities to Climate Change Outcome 2: Adaptive capacity of communities vulnerable to flood risks is strengthened Output 2.1: Improved socio-economic resilience among target communities through livelihoods enhancement 2.1.1: Strengthen community-based organizations (CBOs), e.g. women organizations and youth development organizations, and enhance their management skills. 2.1.2: Implement Climate Resilient Livelihood Diversification Plans for women and men, which include: 2.1.2.1 - Site-level green income generation initiatives, e.g. fishing, ecotourism, fish drying and storing facilities to reduce post-harvest losses, nursery raising for plantations, beekeeping, nature-based tourism, etc. 2.1.2.2 - Skill development, market access and linkages, and exploring financing through public-private partnerships for sustainability. 2.1.3: Implement Social Management Plans, which include social safeguards, gender, and marginalized groups’ inclusion considerations. Output 2.2: Community-based natural resource management ensures sustainability of EbA interventions 2.2.1: Initiate an awareness campaign and build technical knowledge and skills of CBOs, employing a gender balanced and inclusive approach, to participate in implementation of IFRM interventions. 2.2.2: Implement Community-Based Natural Resource Management Plans, for ensuring sustainability of interventions and ecosystems, e.g. maintenance of restored wetlands, floodplains, flood bypasses and washlands, watersheds and plantations on reforested sites. Output 2.3: Enhanced capacity for flood risk reduction, preparedness and response among key stakeholders 2.3.1: Conduct a communications and public awareness campaign to enable better responses to climate-induced extreme events. 2.3.2: Implement disaster preparedness and response interventions, e.g. early warning systems and hydrological gauging stations, Disaster Recovery and Resource Centres, and Disaster Rapid Response Force, aligned with Disaster Management Plans. 2.3.3: Implement risk reduction and resilience-building interventions, e.g. no-build zones, flood resilient structures (e.g. raised platforms, and flood vents), community-based disaster risk management and insurance solutions, and support roll-out of funds (e.g. National Disaster Risk Management Fund). Component 3: Enabling a Paradigm Shift towards Ecosystem-Based Adaptation in Pakistan Outcome 3: Ecosystem-based Adaptation is mainstreamed as a key approach towards integrated flood risk and water resource management in Pakistan Output 3.1: Regulatory framework is in place for integrated flood risk and water resource management 3.1.1: Develop integrated Indus River Basin management guidelines to mainstream EbA in national plans (in line with National Water Policy and National Flood Protection Plan IV). 3.1.2: Facilitate development of an integrated National Flood Risk Management Framework that includes EbA approaches. 3.1.3: Integrate EbA approaches within Provincial Adaptation Plans, aligned with the National Adaptation Plan (Ministry of Climate Change), and the National Wetlands Management Plan (under National Water Policy). 3.1.4: Mobilize suitable financing options, e.g. public-private partnerships, blended financing, incentive schemes, micro-insurance, community-based enterprises, and other private sector based solutions, identified during project preparation and inception phases, to scale up and sustain EbA for flood risk management and community-based disaster management. Output 3.2: Institutional capacity is strengthened for employing EbA approaches in the Indus Basin 3.2.1: Implement Capacity Building Plans, based on institutional needs and gaps assessments, for improving capacity and coordination, and ensuring a social safeguards and gender responsive approach, across district, provincial, and national institutions for EbA approaches. 3.2.2: Establish a research and information centre for advanced research, knowledge management, and capacity building on integrated flood risk management. 3.2.3: Develop a national pool of experts for scaling up EbA through investment in curriculum development, academic programmes, training of trainers, and exposure visits.

Concept Illustration – Manchhar Lake Site: The diagram below illustrates the different types of EbA interventions proposed in the watershed and floodplain areas around the Manchhar Lake, which is one of the potential wetland sites for the project.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 9 OF 13

Diversified Portfolio Potential Benefits: Approach: 1. Environmental benefits (e.g. net volume of water in lake increased and quality improved, improved Integrating Ecosystem- hydrological flows around Manchar Lake, ecosystem services improved) Based Adaptation with 2. Social benefits (e.g. reduced flood risk to lives and assets, local and provincial institutions Government Irrigation strengthened, local knowledge and capacity built keeping in view gender sensitivity) Departments’ Grey 3. Economic benefits (e.g. reduced flood damages and costs avoided, green/grey infrastructure made Infrastructure Solutions more resilient to flooding, livelihoods sustained through improved aquaculture and agriculture development in and near Manchar Lake site) Potential Interventions: Site A: Hill-torrent and Hill-Torrent/Watershed Management watershed management Floodplain Management interventions in Kirthar Complement Government’s Mountains: infrastructure Alleviate flash flood risks on solutions through improved vegetation communities, while cover (for soil maintaining flows to Manchar erosion control), Lake; watershed management, restoration of natural B water pathways etc. e.g. check dams, terracing, and afforestation; flash flood dispersion for spate irrigation; diversion, soil bio-engineering.

Site B: Floodplain management to manage flood flow from Indus River on eastern end of Manchar Lake: Identify naturally inundated and undeveloped areas to be Indus River maintained as floodways/ washlands/ bypass channels, restore floodways and bypass channels through removal of blockages, re-linking with main river channels, and flood tolerant plantations etc; riverine afforestation; and erosion control.

Capacity of Accredited Entity WWF: World Wildlife Fund (WWF) US, the AE for this project proposal, is part of the global WWF Network that is present in over 100 countries. More than 6,000 WWF staff collaborate with an extensive network of partners at the local, national, and global levels to deliver science-based solutions for conserving biodiversity, halting environmental degradation, and tackling climate change. WWF has well-established relationships with country governments, private sector entities, indigenous peoples’ groups, and civil society partners. Recently, WWF and the Royal Bhutan Government launched a GCF funded project, “Bhutan for Life”, which leverages nearly USD 100 million, with a GCF contribution of USD 26.6 million. The WWF Network supports implementation of the Paris Agreement; it works with communities, governments, industries, and the development sector, and leveraged USD 555 million in 2017, to address climate change, water, and other conservation issues. WWF is a global leader in EbA approaches, including climate-adapted water management. Examples of publications include: Natural & Nature-based Flood Management: A Green Guide developed with the USAID (WWF, 2017); Flood Risk Management: A Strategic Approach developed with China’s Ministry of Water Resources, ADB and UNESCO (Sayers et al., 2013). WWF Network experts have also developed various tools for EbA implementation, e.g. Water Risk Filter, Green Recovery and Reconstruction Toolkit with the Red Cross, Flowing Forward with the World Bank, and Shifting Course: Climate Adaptation for Water Management Institutions. WWF’s relevant on-ground experience around the world, mentioned in Annex 6, will allow effective planning and implementation for the EbA interventions proposed under this project. Capacity of Executing Entities and Implementation Strategy The Government of Pakistan has requested WWF-Pakistan to serve as the lead Executing Entity (EE) for the project. Project funds will flow from the Accredited Entity to WWF-Pakistan, which will then disburse funds to the Executing Partners for their respective roles under the project. As the Executing Entity, WWF-Pakistan will lead coordination between all Government (through the Federal Flood Commission), non-Government, and community’ stakeholders. It will lead implementation of interventions with target communities for community-based EbA, natural resource management, and livelihood development, as well as coordinate effective project delivery in collaboration with key government and non- government stakeholders. It has experience in climate change adaptation, managing and restoring wetlands, rivers, and watersheds (ecosystem-based approaches), disaster risk reduction and management (e.g. flood recovery), and sustainable agriculture. WWF-Pakistan’s EbA experience includes Watershed Management in Ayubia National Park's buffer zone (recently closed after a decade) and Khanpur Dam's catchment areas (ongoing since 2017), with interventions

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 10 OF 13 such as afforestation and natural regeneration support in degraded forest patches, slopes and landslip stabilization through bioengineering, terracing, check damming for streams, soil erosion control, that are being proposed for the hill torrents management interventions for Recharge Pakistan. Other major interventions in the past that have employed EbA measures for conservation and climate change adaptation include the Indus for All Programme, Flood Early Recovery Programme, Climate Change Adaptation Project, and Pakistan Wetlands Programme. WWF-Pakistan’s ongoing projects that have EbA elements and contribute towards climate change adaptation include: 1) Sustainable Management of Mangroves Ecosystem and Enhancing Resilience of Communities in Indus Delta, Sindh, Pakistan, funded by BMZ via WWF-Germany; 2) Integrated Watershed Management and Livelihood Improvement Project in Selected Sub-catchments of Khanpur Dam – Phase II, funded by The Coca-Cola Foundation; 3) Agriculture, Water, Energy, and Hazard Management in the Upper Indus Basin for Improved Livelihoods - Phase II, funded by the International Centre for Integrated Mountain Development (ICIMOD); 4) Improvement of Central Karakoram National Park Management System as a Model for Mountain Ecosystems in Northern Pakistan: Assessing Climate Change Impacts and Introducing Adaptation Measures and Sustainable Livelihood Options – Phases I & II, funded by the United Nations Development Programme (UNDP), Pakistan; and 5) Harmonizing Conservation with Sustainable Development in Hindukush Karakorum Pamir Landscape in Pakistan, funded by the International Centre for Integrated Mountain Development (ICIMOD). WWF has worked with the Government of Pakistan for replication of its successful interventions, e.g. watershed management interventions under the ‘Billion Tree Afforestation Programme’ (see Annex 6). WWF-Pakistan has also been working on effective decision making and action on water issues, e.g. coordinating the River Ravi Commission. WWF and its partners are also developing a Basin Assessment Scenario Intervention Tool (BASIT) that utilizes an integrated approach to assess both surface water and groundwater data of a river basin to identify the water balance. These approaches and BASIT will support effective planning, flood zone mapping, green infrastructure investment, and alignment of stakeholders across sectors for Indus. The Federal Flood Commission (FFC), under the Ministry of Water Resources (MoWR), will be the second executing entity for this project and will lead coordination on behalf of the Government of Pakistan, steering the project directly through the Federal Government’s MoWR that has authority over flood and water resources management. The FFC, as a part of MoWR, has the mandate and authority to manage water allocations and diversions through the Indus River Basin irrigation system, including: preparation of National Flood Protection Plans; approval of flood control schemes prepared by Provincial Governments and concerned Federal Agencies; review of flood damages to flood protection infrastructure and review of plans for restoration and reconstruction works; and undertaking measures for improvements in Flood Forecasting and Warning Systems. The FFC will be coordinating on-ground implementation of green infrastructure and EbA interventions at the target sites through the respective Provincial Irrigation Departments, zonal irrigation teams, and focal experts. In addition, the FFC is the key partner for any water resources-related policy development, planning, and institutional capacity building proposed under this project. The third executing entity is the Ministry of Climate Change (MoCC), the GCF NDA for Pakistan, which holds the national mandate for climate change, environment, and Multilateral Environmental Agreements, including UNFCCC and NDC commitments. The EE and main Executing Partner (FFC) will coordinate with the MoCC for on-ground implementation of interventions through the Provincial Forest and Environment Protection Departments. The Executing Partners are also mobilizing Government co-financing for the project. The AE will monitor use of funds and compliance with GCF regulations, while the EE will ensure on-ground alignment with national and international priorities, and relevant standards and policies. A Project (Indus Basin) Steering Committee (PSC) will be established to guide the project with representatives from the following: MoWR (Chair), MoCC (Co-chair, & GCF NDA), FFC, National Disaster Management Authority, Ministry of Planning Development and Reform, Pakistan Council of Research in Water Resources, WWF-Pakistan, Provincial Advisory Committees Chairpersons (see below), and other members. Project teams of other GCF funded projects in the Indus Basin, e.g. UNDP’s GLOF-II and FAO’s proposed ‘climate resilient agriculture and water management’ project, will also be consulted for project design and implementation complementarities. The PSC will also ensure that EbA interventions are streamlined in the main development agenda of the Government of Pakistan. Provincial Advisory Committees (PACs) will be established under the leadership of respective Chairs of Provincial Planning and Development Departments with members (ensuring inclusive representation of all groups and genders) from Provincial Departments of Irrigation, Forest, Wildlife, Fisheries, Environment, Agriculture, Women Development, and Disaster Management, academia, and CSOs. Provincial Focal Points will be notified to provide technical support to the field teams and for mainstreaming successful interventions into the provincial governments’ development agenda. The national Project Management Unit will be based in an independent office in the Federal Capital, headed by a National Project Director, with oversight by the PSC. There will be 4 Provincial Implementation Units in the Provincial Capital to coordinate project implementation through the provincial government departments, guided by the PACs. The on-ground site teams will be based at field offices. The proposed implementation structure is as follows; please see Annex 6 for further details:

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 11 OF 13

Risks and Mitigation Risks identified include: a) Technical and Operational (e.g. delays, implementation complications, and low capacity); b) Social and Governance (e.g. lack of commitment from stakeholders); c) Financial (e.g. changes in rates/inflation, delays in disbursement); d) Environmental (e.g. extreme events during project implementation). These risks will be assessed in detail during project preparation and appropriate mitigation measures will be incorporated in the project design, e.g. sensitization of policy makers and ensuring government and communities’ participation in the project planning and implementation process, dedicated efforts from WWF and GoP for streamlining coordination mechanisms, and collaboration with Disaster Management Authorities. See Annex 7 for a preliminary Risk Analysis Matrix. B.3. Expected project results aligned with the GCF investment criteria (max. 3 pages) Impact Potential • Ecosystem-based Adaptation and Green Infrastructure (estimates to be revised during feasibilities): ○ 14,000 square kilometres of multi-purpose flood bypasses, washlands, and wetland restoration and reconnection sites; about 3-4 Million Acre Feet of water retention capacity expected to be added with these interventions. ○ 40,000 square kilometre area under watershed and hill torrent management. It is expected that an additional 25% of rainwater will be retained through watershed protection interventions for hill torrent management. ○ Groundwater recharge potential will increase as a result of wetlands, floodplains, watershed, and hill-torrent management interventions. This will improve water security for local communities by improving the water table around the project sites and help build drought resilience and climate change adaptation capacity for dry seasons. ○ Overall enhanced services from restored ecosystems, e.g. rivers and lakes provide services valued (2007 PPP) at 1,779-13,487 Int.$/ha/year 2 and floodplains/marshes 981-44,597 Int.$/ha/year (Russi et al., 2013). Under the current global crisis, damaged ecosystems are being linked with the rising incidence of infectious diseases; there is, hence, growing recognition that restoration of ecosystems holds much higher value than can be fully quantified. • Direct benefits to approximately 10 million individuals (around 5% of Pakistan’s population, 52% of whom are women) among vulnerable communities in and in close proximity to target sites, through reduced flood risks, increased water security, improved agriculture productivity and food security, community-based disaster risk management (CBDRM), and climate-resilient livelihood options. Project interventions will also increase overall health, income, and food security,

2 The international dollar (Int.$) is a hypothetical currency to standardise values across countries by correcting to the same purchasing power that the U.S. dollar had in the United States at a given point in time. Figures in international dollars cannot be converted using market exchange rates; they must be converted using the country’s purchasing power parity exchange rate. 1Int.$=1USD for 2007.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 12 OF 13

while improving ecosystem benefits for target beneficiaries. The proposed project will, thus, support Pakistan’s recovery from the COVID-19 pandemic-induced economic crisis and enhance resilience to future shocks. • Indirect benefits to an additional 20 million people in 50 vulnerable districts along the Indus River from reduced flood risk, through early warning systems, DRM trainings to authorities, improved governance, and enhanced ecosystem services. Multiplier benefits are also expected through replication of climate resilient livelihood options introduced. Paradigm Shift Pakistan’s approach to water and flood management is currently focused on grey infrastructure, i.e. hard engineering. Though this has helped manage water resources and diffuse some risks from moderate floods, albeit with very low efficiency, the high expansion costs and inflexible infrastructure are unable to manage larger floods that are likely to occur with greater frequency and intensity in the future. This project proposes a paradigm shift by introducing EbA, with a three- pronged approach that would: a) retain and store water using green infrastructure, e.g. flood bypasses, wetlands restoration, and hill torrent management, for flood risk management; b) work with rural communities at project sites to empower them for local climate adaptation, flood risk reduction and natural resources management; and c) forge a paradigm shift so the approach can be replicated and scaled-up to keep up with changes as climate change advances and climate variability increases. The project will also contribute towards exploring viable public-private partnerships, blended financing, incentive schemes, micro-insurance, community-based enterprises, and other private sector based solutions to scale up EbA for flood risk management and community-based disaster management. • Innovation: The project brings innovation across its implementation areas. This will be the first project in Pakistan to implement basin-wide EbA interventions to manage flood water and advocate for more flexible and integrated decision making and responses (e.g. BASIT). Secondly, the project addresses hill torrents as part of integrated flood risk management. The implementation of EbA interventions upstream for reducing flash flood flows during extreme weather events, and harnessing their potential, especially in arid and drought prone areas such as Sindh and Balochistan, will help reduce the significant contribution of hill torrents to the flood peaks in the Indus River. There is only limited experience with the use of EbA for these purposes, and the project will document and share its lessons for application to address climate adaptation challenges in similar settings around the world. • Impacts beyond project life - opportunities to replicate and scale up: The project’s executing consortium, particularly the government representatives, will safeguard long-term engagement and replication of its activities, as well as stakeholder coordination, by ensuring that the Project Steering Committee (PSC) and the Provincial Advisory Committees (PACs) meet regularly during and after the project. As the Federal Flood Commission will lead the project, there will be federal level involvement in ensuring that the EbA interventions continue to benefit communities and ecosystems beyond the project span. In addition, as EbA measures are inherently long lasting, they will continue to provide benefits to vulnerable communities that are also enabled to sustain and replicate interventions through community-based natural resource management and flood risk management efforts. In Sindh and Punjab, the project will facilitate pre-existing bodies, e.g. Indus Ecoregion Steering Committee, to support the project’s EbA interventions. Similar bodies will be formed for Khyber Pakhtunkhwa and Balochistan. • Creating an enabling environment – regulatory framework and capacity: The project’s component 3 ensures that there is an enabling environment for integrated floodplain management and ecosystem-based adaptation. A detailed set of activities, focusing on: enhancing collaboration across various government and private sector entities (both local and suppliers of international brands are being engaged for water stewardship by WWF-Pakistan); mainstreaming EbA recommendations under various policies and plans; developing basin level action plans; and building institutional capacity, strengthening regulatory frameworks for climate responsive planning, and enhancing technical capacities, will be undertaken by the project. The PSC includes the Planning & Development Departments, ensuring that EbA will be mainstreamed and budgeted for in longer term government strategies, plans and practices. The proposed trainings will also help local organizations build awareness and capacity to address climate change induced threats and risk. Sustainable Development - Social, Economic and Environmental Co-benefits and Gender Responsiveness: The project is being designed through a participatory approach, with multi-stakeholder consultations, particularly with local communities at target sites. Consultation sessions will be held with rural communities for free prior and informed consent and ensuring there is no resettlement or loss of agricultural land. Communities will be empowered so that local resources are better managed, livelihoods improved, and climate vulnerability reduced. The proposed project will make a significant contribution to sustainable development in the Indus Basin, and contribute towards a green recovery for Pakistan, by reducing escalating flood risks through EbA and strengthening resilience to climate change, the COVID19 pandemic, and future disasters and shocks through sustainable and inclusive growth. The expected impacts will be more accurately quantified during the detailed site level feasibility studies in the forthcoming project preparation phase. Benefits will be measured through gender disaggregated indicators during project implementation. • Job creation and increase in disposable income: The project will directly benefit at least 200,000 vulnerable people through skills-based trainings and diversified livelihood interventions, which will take into account the differential needs and interests of women, men and youth. Pakistan’s Government has announced a “Green Stimulus” in response to the COVID-19 crisis, with two objectives – job creation and restoration of ecosystems. This will focus on provision of green jobs, e.g. nursery raising, plantation, and protection of forests under the 10 Billion Tree Afforestation Programme, for those that are now unemployed due to the pandemic-induced economic crisis, especially women and youth, and are returning to rural areas from urban centres. The proposed project is, hence, directly aligned with the Government of Pakistan’s ‘Green Stimulus’ and the GCF’s COVID-19 response, particularly through Component 2, wherein Output 2.1

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 13 OF 13

focuses on climate resilient livelihoods diversification through skills development and creation of green jobs, and Output 2.2 focuses on community-based management of natural resources that entails community custodians maintaining restored ecosystems. • Government’s budget deficits reduced and savings: The project will help the GoP to reduce the financial impacts of flooding through more cost effective and sustainable solutions (Section C.2.). EbA and green infrastructure interventions will improve the resilience of the riverine ecosystem and vulnerable communities, thus reducing pressure on the GoP’s budget. There will also be reduced deficit for the GoP due to savings from EbA solutions as opposed to hard infrastructure costs, as well as reduced rescue and relief expenses. • Improved ecosystem services for water management, food security and biodiversity conservation: Through flood bypasses and wetland restoration, the project will help distribute silt in the adjoining agricultural lands and increase soil fertility. The enhanced water storage and groundwater recharge will improve agricultural productivity and food security. Improved water availability will also support healthy habitats (e.g. riverine forests and wetlands), and associated ecosystem services (e.g. fish stocks, clean water, and fodder sources), as well as key species (e.g. the endangered Indus river dolphin, a species endemic to the Indus). • Carbon sequestration: Although this is an adaptation-focused project, it will also contribute towards carbon sequestration. This will occur through the restoration and increased water retention capacity of targeted wetland sites, expanding and rehabilitating riverine forest areas, and improving watershed management. • Gender responsive development: Rural women in Pakistan are considered more vulnerable to climate change as they have more limited access than men to resources for building resilience, including income, land, loans and access to off-farm employment. Women also have fewer opportunities than men to obtain trainings and knowledge such as those for disaster emergency response. They are often excluded from local decision-making processes, in conservative areas. Yet they are responsible for ensuring their households’ energy, water and subsistence farming needs are met. Many of the proposed interventions to build resilience and provide alternate energy solutions will be specifically designed to benefit and improve the adaptive capacity of vulnerable women. The provision of alternate and efficient sources of energy for poor rural households, and improved WASH facilities, will help with COVID-19 and other infectious diseases response and resilience, reduce workloads and free-up time (e.g. spent on fuel collection), which can be used for studies or income generation. In addition, skills-based training for green jobs, e.g. kitchen gardening, poultry farming, and planting household level fruit orchards, and establishing community level vocational centres will directly benefit the women as well. • Education, culture, health, and standard of living: The project will promote cultural conservation by including culturally and historically significant sites in livelihood development plans and awareness campaigns, for preservation of these sites and promotion of tourism for local, sustainable livelihoods. The proposed project sites have potential for revenue generation. By introducing these interventions and by mobilising communities and local organisations, public funds can also be leveraged for providing education and health facilities, which can further improve the living standards of the local communities. Needs of Recipients • Vulnerability to Climate Change: Pakistan is ranked the 8th most affected country in the world on Germanwatch’s Long-Term Climate Risk Index (1998-2017), with losses from recent disasters amounting to USD 3.8 billion in Purchasing Power Parity terms (Eckstein et al., 2018). Its contribution to global greenhouse gas emissions is only 0.8% however. Climate change poses serious threats to water, energy and food security, and, as discussed, the country has already suffered significant losses from floods. The Government’s Global Change Impact Study Centre has modelled climate change projections, including changes in precipitation and flooding, for potential sites for this proposed project to help prioritize those that are at increased flood risk under medium-range stabilizing scenario Representative Concentration Pathways (RCP) 4.5 and high-end scenario RCP 8.5 (Annex 1B). • Economic and social development level of the country and affected population: Pakistan is classified as a lower middle-income country, with per capita GDP of USD 1,443.6 in 2016. In the project’s target rural areas, the communities are some of the poorest and most vulnerable in Asia. With 54.6% rural poverty, the majority of the rural communities living along the Indus River floodplains live below the poverty line, with poor or no access to basic facilities, such as clean drinking water, sanitation, health, education and other public infrastructure (UNDP, 2016a). Furthermore, low development in the area perpetuates a variety of socio-economic problems, e.g. limited income earning opportunities, income disparity, and unsustainable dependence on agriculture, fishing and other natural resource-based income sources. Annex 1E provides the population and poverty profile of the potential target areas along the Indus River. • Absence of Alternative Sources of Financing/Financing Needs for Adaptation: Refer to Section C.2. Country Ownership The Ramsar Advisory Mission (RAM) recommendations and the subsequent exchanges with flood management experts in the Yangtze Basin successfully convinced the Government of Pakistan (GoP) of the advantages of EbA for the management of Indus Basin floods. This project has been developed at the request of the GoP, specifically to take actions on these recommendations, and in close consultations with all of Pakistan’s main water resources, flood management, and climate change adaptation stakeholders (Annex 3 details multi-stakeholder consultations). Twenty letters of support from federal Ministries and provincial departments and the NOC from the GCF NDA, indicating the country’s ownership and commitment to this project, have also been received and are attached in Annex 8 and 9.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 14 OF 13

This project has been presented and approved at the highest levels of GoP, including the Standing Committees of Senate and National Assembly in 2017 and to the Advisor to the Prime Minister on Climate Change at the Ministry of Climate Change in 2018. Both presentations led to strong agreements by officials that EbA integration was necessary to store surplus floodwater for social, economic and environmental needs of the country. The Ministry of Climate Change further presented this project to the Prime Minister of Pakistan in September 2018; during this meeting this proposed concept was approved and prioritized for immediate funding under the “Recharge Pakistan” initiative. The Office of the Advisor to the Prime Minister on Climate Change has directed relevant GoP authorities to provide necessary support for development, co-financing, and implementation of the proposed project. The Advisor to the Prime Minister on Climate Change, while leading the Pakistani delegation at various national and international environment and climate change platforms, including the UNFCCC’s COPs, has been discussing this concept as a priority for the GoP – Recharge Pakistan is one of the five initiatives on Pakistan’s five-point Green Agenda – and has also included it in discussions on a bilateral MoU between the Governments of China and Pakistan (see Annex 3 and B.4.). Coherence and Alignment Discussions on various aspects of climate change adaptation and flood risk management have been on-going with all relevant GoP entities, and WWF-Pakistan has been engaged with drafting relevant policies, such as the National Climate Change, Water, Wetlands and Forest Policies. The project is aligned with objectives pertaining to management of water resources and flood control under the: National Climate Change Policy (2012) and its implementation framework (2014- 30); National Forest Policy 2015; National Water Policy 2018; draft National Wetlands Policy; National Disaster Risk Management Framework (2007); and National Disaster Risk Reduction Policy (2013). The proposed project will contribute adaptation targets outlined by the GoP in its NDCs. In the near term (2020-2025) it will: contribute to sub-national adaptation planning by building the capacity of relevant line departments and the development of adaptation strategies, such as the ‘National Floodplain Management Policy, and Hill Torrent Management Policy’ as described in the NFPP IV, and the ‘Indus River Basin Management Plan’; and ensure an enabling environment for floodplain management at the national level. The importance of creating an enabling environment for ecological solutions to be undertaken, i.e. having relevant policies and legislation in place, a coordinated basin level approach by establishing a single coordinating body (e.g. Wetlands Management Authority under National Forest Policy, Water Council under the National Water Policy), and enhancing institutional capacity (prioritised under the NFPP IV), was also stressed in the country’s NDCs and is incorporated in this proposed project. The project will also contribute towards SDGs 6, 11, 13 and 15 and all 4 priorities under the Sendai Framework (2015- 2030). Alignment has been confirmed with GoP and development sector organizations’ projects. The implementation strategy also ensures coordination with the executing entities of relevant GCF funded projects in Pakistan, i.e. UNDP’s ‘GLOF-II’ project, FAO’s ‘Climate Resilient Agriculture and Water Management’ project, and the National Rural Support Programme’s (NRSP) ‘Climate Smart Villages’ project in the pipeline, to leverage complementarity and avoid any duplication of efforts. Efficiency and Effectiveness The project proposes EbA solutions under a diversified portfolio approach to reduce disaster risks and manage floodwaters. These are based on recommendations emanating from best practices detailed in Annex 5. According to UNDP’s National Economic, Environment and Development Study (NEEDS), Pakistan’s current adaptation need is on average more than USD 10 billion/annum, reflected in the country’s NDCs as well, and there is a significant gap between the amount of funding needed and the amount available (Khan et al., 2011; UNDP, 2015). Not only does grey infrastructure need heavy investments, it also has high environmental costs associated with it; for example, the Indus Delta has been degrading due to the reduced flow of water as a result of the vast irrigation and hydropower infrastructure upstream. The National Flood Protection Plan (NFPP) IV budget, which predominantly focuses on rebuilding flood embankments and other hard engineering measures for flood protection, is estimated at USD 375 million. Diamer-Bhasha Dam alone is costing Pakistan more than USD 10 billion, and over 35,000 people will be displaced while historically significant sites are submerged. Tarbela Dam has been silting up for decades, due to the Indus having a very high sediment load, reducing capacity to 33% and resulting in high rehabilitation and maintenance costs. This proposed project is estimated at around USD 150 million and has multiple benefits and none of the social, economic, and environmental costs associated with water storage through grey infrastructure. Please see sections B1 and C2 for further details on economic and financial soundness and efficiency. Cost-Benefit Analyses will also be conducted to determine the economic efficiency of the proposed solutions to be piloted, in comparison to the flood control and management measures budgeted in the NFPP IV. B.4. Engagement among the NDA, AE, and/or other relevant stakeholders in the country (max ½ page) The project concept development is being carried out through the financial and in-kind support of the Government of Pakistan (GoP), WWF Network (including WWF-Pakistan and WWF-US), and other development sector stakeholders. In line with suggestions from Pakistan’s GCF NDA and the GCF Board of Pakistan (at its meeting on 4th February, 2017), WWF-Pakistan held numerous consultations with provincial and national stakeholders. The AE, WWF-US, has been involved since the beginning of project development and has been guiding and supporting WWF-Pakistan. At the international level, a meeting of the representatives of Pakistan’s GCF NDA and WWF’s AE was held during the GCF Asia Dialogue (Bali, Indonesia, April 2017). The Government’s Ministries of Water Resources (e.g. Federal Flood Commission, and Provincial Irrigation Departments), Climate Change, and Planning Development and Reforms have been integral in defining proposed interventions, potential sites, implementation strategy, and co-financing options.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 15 OF 13

National Consultative Sessions were conducted with representation from all relevant GoP entities. Discussions were held to identify potential sites, criteria, and alignment with Government projects. Recommendations shared by Government counterparts revealed the need for the project in the national context. The need for hill torrents management was also highlighted and led to the inclusion of additional vulnerable sites to the list. Additionally, other multi-stakeholder sessions and meetings have been held, including with the Ministry of Water Resources, Federal Flood Commission, Pakistan Council of Research in Water Resources, Ministry of Climate Change (GCF NDA), and Provincial Irrigation, Forest, Wildlife, Fisheries, Environment and Disaster Management Authorities (Annex 3). The purpose of these meetings was: a) to discuss the project design; b) to define roles and responsibilities in the proposed project; and c) to obtain formal commitments of support. Endorsements in the form of Letters of Support were obtained from all of the national and provincial government agencies as described above (Annex 8). The GCF Board of Pakistan met again on 29th January 2018, where the NDA and key stakeholders (including executing partners) discussed the project design, and final endorsement was received. The NDA’s No Objection Certificate (NOC) for the project was subsequently received in March 2018 (Annex 9). Thereafter, as mentioned in section B.3, the concept was presented to, and approved by, the Prime Minister and his Cabinet as a national initiative termed “Recharge Pakistan”. At subsequent National Consultative Sessions, the latest one in April 2019, updates to the site selection criteria, governance structure, and implementation strategy, along with Government procedures for project concept and budget development for co-financing were discussed further with Provincial and Federal Government stakeholders. The updated concept is being discussed with development partners, including ADB, for funding and implementation roles. As the concept is developed into a funding proposal, WWF will continue engaging with stakeholders, particularly local communities at shortlisted sites during feasibility assessments, for a participatory and need-based project design. The ‘Project Steering Committee’ and provincial and inter-provincial coordination and advisory committees will also be mobilized soon to guide the project design and inception. C. Indicative Financing/Cost Information (max. 3 pages) C.1. Financing by components (max ½ page) Government of Pakistan’s Ministries, Departments, and Authorities, WWF Network, and other partners will be contributing in cash and in-kind towards this project. Please note that at this concept stage, the funding numbers below are indicative only and co-funding and roles have been discussed with partners at a high level. Detailed discussions and costing will follow during the feasibility assessments and project proposal development for each potential site, with relevant provincial and national/federal level Government, communities, and other stakeholders. Component Indicative GCF financing Co-financing cost Amount Financial Amount Financial Name of Institutions (USD) (USD) Instrument (USD) Instrument Component 1: USD 95 32 Grant 63 Grant, In-kind Federal Flood Commission, Ecosystem-based million MoWR; MoCC; National Adaptation for Disaster Risk Management Floodplain and Hill Fund (NDRMF); NDMA; Torrent PDMAs; Provincial Irrigation Management & Forest Departments; WWF Component 2: USD 33 11 Grant 22 Grant, In-kind NDRMF; NDMA; PDMAs; Community million WWF Resilience Component 3: USD 12 4 Grant 8 Grant, In-kind Federal Flood Commission; Coordination, million Provincial Departments Legislation and Capacity Building Transversal USD 10 3 Grant 7 Grant, In-kind WWF; MoWR; MoCC Component: million Coordination, Management, M&E and Audit Indicative total USD 150 USD 50 million USD 100 million cost (USD) million

C.2. Justification of GCF funding request (max. 1 page) This project presents a clear example of why funding is needed from the GCF as an international fund that supports innovative approaches to climate adaptation and fosters paradigm shifts, especially in developing countries that lack the means to undertake such urgent interventions. Funding Constraints

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 16 OF 13

Pakistan already suffers immense losses from climate change impacts and evidence suggests that climate change will have a significant and increasing effect on national GDP if no action is taken. Between 1995 and 2014, climate change cost Pakistan USD 3.9 billion (PPP) in average economic losses annually. Please see ‘Needs of Recipient’ section in B.3. Combating these effects requires action on both mitigation (reduction of GHG emissions) and adaptation (building resilience in natural and human systems). A comparison of the global cost estimates with the current level of adaptation funding indicates that projected global adaptation needs are to be significantly greater than current investment levels, particularly in vulnerable developing countries like Pakistan. The average costs for annual adaptation and mitigation to climate change for Pakistan were estimated to range annually from more than USD 10 billion to up to USD 32 billion by 2050 (UNDP, 2015; Government of Pakistan, 2017b). Pakistan remains a resource-constrained economy, dependent on foreign financing in the shape of loans, foreign investment, and grant aid. Pakistan relies predominantly on loans from multilateral banks for infrastructure projects and has often relied on foreign aid to assist in post disaster situations. There is significant investment required to meet the requested budgets for National Flood Protection Plans (NFPPs) - USD 375 million estimated for NFPP IV – and due to insufficient GoP funds, foreign financing is relied on significantly for tackling the impacts of floods and/or investing in flood management initiatives. To highlight the inadequate funding issue, the Federal Flood Commission’s Annual Flood Report from 2017 provides data on the significant gap annually between the amount of funding needed and the amount available for the Provinces and Federal Line Agencies for flood protection work. The budget need from the Government’s Normal/Emergent Flood Programme by the Provinces and Federal Line Agencies, for 2016-17, for example, was PKR 5.5 billion, while only PKR 267.5 million were released for use (Government of Pakistan, 2017a). In spite of the country’s financial constraints, estimated federal climate-related expenditure was between 5.8 and 7.6 per cent of the total expenditures in the federal budget (UNDP, 2015). This expenditure is expected to increase further, primarily due to the increase in frequency and intensity of climate induced disasters. The budget, however, will still fall short for funding this proposed EbA disaster risk reduction project that inherently has high up-front costs. The Government of Pakistan, particularly the Ministry of Climate Change (the GCF NDA) has explored various funding options for initiating this concept since the RAM recommendations, but has not been able to secure commitments from any entities with the requisite level of funding. WWF-Pakistan was subsequently asked to lead concept development, in collaboration with the Government, for GCF funding. Co-Financing Options WWF has been discussing co-financing options, project design and implementation strategy with the Government and key development sector stakeholders, e.g. Asian Development Bank (ADB), Development Agency of France (AFD), European Union Delegation in Pakistan, and other bilateral and multilateral agencies. The Government has announced that it will prioritize interventions under this proposed project as a national ‘Recharge Pakistan’ programme with around USD 50 million in funding from various Government budgets that align with this concept. Around USD 39.9 million has recently been committed as co-financing through the National Flood Protection Plan IV (NFPP IV) budget, by the Federal Flood Commission of the Ministry of Water Resources (letter attached in Annex 8). WWF and Government of Pakistan representatives are also discussing and working on project concept development in-line with Government procedures for further funding (see section C.3 and Annex 3 for details). In addition, a National Disaster Risk Management Fund (NDRMF) has been established (under Pakistan’s Companies Ordinance) with an initial investment of USD 250 million from the ADB. The Government, ADB, and NDRMF CEO have highlighted this as an avenue for co-financing interventions that align with NDRMF’s objectives and the Government’s aims for achieving greater impact in the long term through this project. The project also aligns with the NDRMF and Government’s COVID-19 response. Private commercial resources, either local or international, are all but absent from climate adaptation investments in rural areas of Pakistan, as is the case in most low-income developing countries. Rural communities in the project areas are too poor to be able to make significant financial contributions to the project. Though flood damages add up to billions of dollars, addressing this through ex-ante investment schemes (e.g. insurance) has thus far proved elusive. Still, this may be an approach to consider for the long-term sustainability of the proposed project and similar projects as well. In addition, public-private partnerships and other blended finance options (e.g. European Union Delegation in Pakistan) are also being explored during the project preparation phase.

C.3. Sustainability and replicability of the project (exit strategy) (max. 1 page) Sustainability This proposed project, Recharge Pakistan, is being designed and will be implemented in collaboration with all key Government stakeholders to ensure that country ownership for sustaining and scaling up interventions is guaranteed. It is expected that approximately USD 50 million (as co-financing) will be allocated to address this issue as high priority. In this regard, the Ministries of Climate Change, Water Resources, and Planning Development & Reform have been well integrated during planning discussions, will be involved on-ground during the feasibility assessments, and will support the project proposal development, which will ensure sustainability of the project in the long-term. In addition to this, the Government project development process has been initiated simultaneously through the Ministry of Water Resources. WWF supported the Ministry of Water Resources with development of the ‘Recharge Pakistan’ project concept clearance proforma, which has been approved by Ministry of Planning Development and Reforms. The Project Concept (PC1) will now be developed through the Provincial Governments of the 4 provinces with target sites, and then collated at the federal level by the Ministry of Water Resources for allocation of Government budget and resources.

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 17 OF 13

The project will address institutional needs that have been voiced by the Government of Pakistan at various fora, and identified under their policies and plans (e.g. the NFPP IV). It will include stakeholders’ capacity building, handing over responsibility to the Government of Pakistan for continued function of the Project Steering Committee (PSC), Provincial Advisory Committees, PSC working group, and Provincial Focal Points, and identifying financing schemes to ensure that project interventions are sustained. One of the outcomes of the project is putting the requisite policy and regulatory framework in place to successfully achieve the envisioned impact and ensure long term support and ability to scale up. Further, adopting an inclusive approach, with regular consultation of stakeholders and local communities, means that community ownership is integrated into the project, which will help with sustainability at the local level. The green infrastructure solutions proposed require lower maintenance costs as compared to traditional hard-engineering flood protection and water storage measures, e.g. flood bunds, dams and barrages, which require costly rehabilitation measures due to issues like silt build-up reducing storage capacity. This will ensure that long term financing for sustaining EbA interventions will hence be more feasible for the Government. In addition, community-based natural resource management interventions built into the project will ensure maintenance of most of the EbA and green infrastructure interventions of the project, e.g. de-siltation of community-managed wetlands and diversion channels. At the national level, other than the ‘Recharge Pakistan’ project approved by the federal Government, the project’s afforestation and watershed management interventions will also align with the Government’s ‘Plant for Pakistan’, ‘Green Pakistan’ and ‘10 Billion Tree Tsunami Afforestation’ Programmes, which focus on rehabilitating the forests of Pakistan. In addition to this, long-term programmes such as the Sustainable Forest Management and Sustainable Land-use Management Programme can absorb some of the field-based interventions. In Sindh the project will become part of the Indus Ecoregion Steering Committee mandate under the Government of Sindh’s aim to address the poverty-environment nexus and contribute to the SDGs. WWF-Pakistan will include EbA introduced under this project in its core business to ensure that the achievements made during this project are not lost. It may also consider aligning other activities in the selected areas to this project. This will ensure knowledge exchange for the benefit of this and other projects. Replicability Successfully completed, this approach has great replication potential in other areas of the Indus basin which will help to keep pace with the adverse impacts of climate change in the future. Given the limitations of traditional flood management interventions in other countries, and the high investment requirements for further hard infrastructure, the proposed EbA approach is gaining favour across the world. Successful project interventions will be showcased to stakeholders in other parts of Pakistan where the approach can be replicated, as well as to decision-makers in other countries to encourage EbA approaches to flood management elsewhere. The major Asian rivers rising from the Himalayas, including Yangtze, Mekong, Ganges, and Indus, support more than one quarter of the world’s population and some of the most dynamic economies. Millions of people, however, suffer from flooding and water insecurity in Asia, largely in the river basins around the Himalayas. There are many opportunities to take this approach to other Asian floodplains that also face high flood risks. This proposed project has a duration of under 10 years for achieving impact at the chosen sites by 2030, but a 30 year vision that extends till 2050 for expanding the EbA solutions to a multitude of suitable sites that have been suggested by Provincial and Federal Government representatives, bilateral and multilateral agencies, and other integrated water resource management and climate change adaptation experts. Out of the many sites suggested during consultations, there are 10 potential sites being studied with the objective of choosing the 6 most suitable sites. Thus, this project is being seen as the first 10 year phase of a potential 30 year programme with at least 2 more 10 year phases that will target a multitude of other suitable sites. The Government of Pakistan and key development stakeholders in the country and region will benefit from preparation of case studies of the most effective, impactful EbA interventions under this project to be replicated. This project will provide critical reinforcement of nature-based solutions as the sustainable, ecosystem-friendly approach to take for climate change adaptation. To facilitate the replication of the proposed initiatives across other Asian river basins, the project will emphasise documentation and sharing of results and lessons throughout the project life within Pakistan and across the world. WWF, the AE, is in a unique position to transfer lessons from this project as it is active in over 100 countries around the world, and often engaged in fostering ecosystem-based adaptation for management of floods and other climate hazards. WWF can work with government institutions, river basin organizations, multinationals, regional and international development agencies like Asian Development Bank and Mekong River Commission, and others to achieve water security and climate adaptation in these basins. The initiative could make a significant contribution to fostering sustainable water management in large Asian basins and beyond where WWF already has a country presence. Component 3 includes interventions for knowledge exchange and policy recommendations to facilitate replication nationally and internationally. D. Supporting documents submitted (OPTIONAL) ☒ Map indicating the location of the project/programme ☒ Diagram of the theory of change ☐ Economic and financial model with key assumptions and potential stressed scenarios ☐ Pre-feasibility study ☐ Evaluation report of previous project ☐ Results of environmental and social risk screening

PROJECT / PROGRAMME CONCEPT NOTE Template V.2.2 GREEN CLIMATE FUND | PAGE 18 OF 13

Self-awareness check boxes Are you aware that the full Funding Proposal and Annexes will require these documents? Yes ☒ No ☐

• Feasibility Study • Environmental and social impact assessment or environmental and social management framework • Stakeholder consultations at national and project level implementation including with indigenous people if relevant • Gender assessment and action plan • Operations and maintenance plan if relevant • Loan or grant operation manual as appropriate • Co-financing commitment letters Are you aware that a funding proposal from an accredited entity without a signed AMA will be reviewed but not sent to the Board for consideration? Yes ☒ (Not Applicable; AMA has been signed.) No ☐

Tel: 051-9245626 Fax: 051-9245627 (F.No.CFU/GCF/004/2015) Government of Pakistan Ministry of Climate Change LG& RD Complex, Sector G-5/2, Islamabad ***** SECRETARY

Islamabad, the 21st March,2018

To: Green Climate Fund (GCF) Secretariat Song Do, South Korea

Subject: Proposal for the GCF Project Preparation Facility by WWF regarding "Integrated Flood Risk Management: Building Pakistan's Resilience to Climate Change through Ecosystem- Based Adaptation"

We refer to the Project Preparation Facility proposal for preparation of funding proposal "Integrated Flood Risk Management: Building Pakistan's Resilience to Climate Change through Ecosystem- Based Adaptation" in Pakistan as included in the PPF proposal submitted by WWF to us on 16th March, 2018.

2. The undersigned is the duly authorized representative of the Ministry of Climate Change, National Designated Authority/Focal Point of Pakistan. Pursuant to GCF decisions B.08/10 and B.13/21, the content of which we acknowledge to have reviewed, we hereby communicate our no-objection to the Project Preparation Facility activities as included in the PPF Proposal.

3. By communicating our no-objection, it is implied that:

(a) The National Designated Authority (NDA) of GCF Pakistan has no-objection to the Project Preparation Facility request as included in the PPF Proposal; (b) The PPF Proposal is in conformity with Pakistan's national priorities, strategies and plans; and (c) In accordance with the GCF's environmental and social safeguards, the PPF activities as included in the PPF Proposal are in conformity with relevant national laws and regulations.

4. We also confirm that our national process for ascertaining no-objection to the PPF Proposal has been duly followed.

5. We acknowledge that this letter will be made publicly available on the GCFwebsite.

Yours sincerely, ~·~M~ ' (Khiza~ayat Khan) Copy to: 1. WWF Country Office-Pakistan, Lahore.