1

Social Impact Assessment Study

FINAL REPORT

Holiday Home for Central Government Employees

District :

Taluk :

Village :

Submission District Collector, Thrissur

Central Division Executive Engineer, CPWD, Thrissur

Special Tahsildar, (L.A.) General, Thrissur

SIA Unit

Youth Social Service Organisation Social Service Centre

College P.O, -686666 Phone: 0485 2971222, 9446510628 Website: ysso.net, Email: [email protected]

2

DECLARATION

Asper Gazatte notification No.DCTSR/2513/2018-E2 dated 13/08/2020. From District Administration Thrissur, Youth Social Service Organization is assigned as the SIA Unit to study the Social impact Assessment of Land Acquisition for Holiday Home Project for Central Government Employees. The land details are given to the SIA team by Special Tahasildar Office (L.A) General, Thrissur. The SIA team has collected data from the project affected families and the stake holders at Holiday Home Project for Central Government Employees to be constructed under Central Division Executive Engineer CPWD, Thrissur, the proposed project area. The supportive documents have to be verified by the concerned authorities.

Chairman,

SIA Unit

Thrissur, Youth Social Service Organisation

11-09-2020.

3

FORM NO.6 [See Rule 15(5)]

Holiday Home Project for Central Government Employees

Chapter Contents

1.Executive Summary 1.1 Project And Popular Goals

1.2 The Site

1.3 Size of The Acquired Land

1.4 Alternative Routes

1.5 Social Impacts And Mitigation Steps

2. Detailed Project 2.1 Background of the project and rationale for the Description project

2.2 Project Size, Location, Products, targets and costs

2.3 Authorised Basis of Project

2.4 Examination of alternatives

2.5 Work force requirement

2.6 Stages of construction

2.7 Importance of public requirement of this project

2.8 Environment Impact Assessment

2.9 Previous Studies

2.10 Applicable rules and statutes

3. Team composition, Study 3.1 Back Ground Approach And Methodology

3.2 Information about the study group

3.3 SIA and SIMP preparation process

3.4 Desk Research

3.5 Secondary data:

4

3.6 The affected area visit and project awareness campaigns

3.7 Evaluation of circumstances

3.8 The overall impact due to effect of the project

3.9 Summary of public hearing

4. Valuation of land 4.1 Background

4.2 Total impact due to influence of the project:

4.3 Land required for the project

4.4 Acquisition of affected land

4.5 Requirement of public land

4.6 Land purchased for the project

4.7 Geography, current purpose, and landforms

4.8 Nature of ownership

4.9 Duration of ownership of land

4.10 Previous transactions in the area

5. Assessment And 5.1 Preface Calculations

5.2 People affected directly by the project

5.3People affected indirectly by the project

5.4 Families of scheduled tribe and forest dwellers who lose right on forest

5.5 Are the affected families depending on public land after acquirement?

5.6 Families which have been assigned land by the state government or the central government under any of its schemes and such land is under acquisition

5.7 Were the affected families, inhabitants of for 3 years or more ?

5.8 Did the families depend on this land for livelihood in past 3 years ?

5.9 Details of fruitful properties

5

6. Socio- Economic Design 6.1 Preface

7. Planning Of Counter – 7.1 Approach to reduce impact Impact Implementation

7.2 Measures to eradicate impact or loss

7.3 Measures to fulfill the project suggestions

7.4 Measures to reduce impact

8. Social impact action plan 8.1 Directorate and responsible officials directorate

9. Social Impact Management 9.1 Costs of all resettlement and rehabilitation Budget and Financing of required Mitigation plan

9.2 Annual budget and plan of action

9.3 Finding sources with break up

10. Social Impact 10.1 Key monitoring and evaluative indicators Management Plan Monitoring and Evaluation

10.2 Reporting mechanisms and monitoring roles

10.3 Plan of Independent evaluation

11. Analysis of Costs And 11.1 Final conclusion and assessing the aims Benefits Recommendation on Acquisition

11.2 Character of social impacts

Summary

Acknowledgment

6

LIST OF TABLES

Table No. 3.1 Schedule of Consultations with key Stake Holders

Table No 4.1 Acquisition of Land Affected area

Table No.4.2 Nature of ownership

Table No.4.3 Duration of ownership

7

LIST OF ANNEXURES

Annexure 1 (a) Gazette notification

Annexure 1 (b) Notification (English)

Annexure 1 (c) Draft notice copy

Annexure 2 Socio economic survey questionnaire

Annexure 3 Public hearing notification news (Janmabhoomi, Metro vartha)

Annexure 4 Notice to the affected families

Annexure 5 List of participants-officials and affected families

Annexure 6 Copy of the reply letter from the authorities

8

Name of the Project Holiday Home Project for Central Government Employees

State Kerala

District Thrissur

Taluk Chavakkad

Revenue Village Guruvayoor

Muncipality Guruvayoor

Division Division 14

Land to be acquired 0.2104 Hectare

Arthana Official Central Division Executive Engineer CPWD,Thrissur

Acquiring Officer Special Tahsildar (LA), General, Thrissur

Location of Project The project locates at Guruvayur village, Chavakkad taluk, . It belongs to Division 14 of Guruvayur Municipality

9

CHAPTER 1

SUMMARY OF THE STUDY

1.1 INTRODUCTION: PROJECT AND ITS OBJECTIVES

This report deals with the social impact on those who are to surrender their properties for the construction of the Holiday Homes in Thrissur District for the Central Government Employees.

Thrissur district is situated in the central part of Kerala State. It was formed on 1 July, 1949 comprising 7 taluks, 7 municipalities 17 Block Panchayats and 87 Grama Panchayats. The district administration is located at Ayyanthol in Thrissur city. Thrissur is hailed as the cultural capital of Kerala. ‘Thrissur Puram’ is a most fascinating festival within as well as outside Kerala. Tens of thousands of people including foreign tourists reach Thrissur every year to view the spectacle and celebration of ‘Puram’. Guruvayoor Sreekrishna Temple, the holy Hindu shrine is also situated in Thrissur. The city has ever remained a place of attraction for many a tourist by virtue of its leaning towards culture spirituality and religion all through its long history. The Kerala Kala Mandalam, the well-known college of Performing Arts that imparts training in their original style to cultural perfection, is housed at Cheruthuruthy in Thrissur district.

The CheramanJuma Masjid, the first in , stands at Kodungalloor, 40 km from Thrissur. And the most ancient Christian church is India, the St. Thomas Syro- Malabar Catholic church of Palayoor is also situated in Thrissur district.

28Km north-west of Thrissur town, lies Guruvayoor, the suburban town, renowned for pilgrimage. Land acquisition for the Holiday Home Project for the Central Govt. Employees, is to be undertaken at division14 of Guruvayoor municipality. The project is yet another jewel to the famously bejeweled crown of Thrissur district. The project is envisaged to be designed in a most modern fashion. Indeed the project is expected to add to the popularity of the town.

The project’s sole goal is to build living facilities for the Central Govt. Employees to spend their holidays comfortably.

10

Members of the staff of all Central govt departments could make use of the accommodation at fair cost. Above all, the project paves the way for the overall development of the State.

1.2 THE AFFECTED REGION

The total land area required to be acquired for the project is 0.2104 Hectare belonging to Guruvayoor village, Chavakkad taluk, and Thrissur district. The projected is located in division 14 of Guruvayoor municipality. The project impacted area is owned by Bossino International Pvt. Ltd.

1.3 AREA AND BENFITS OF LAND ACQUISITION

The total land area required to be acquired for the project is 0.2104 Hectare belonging to Guruvayoor village, Chavakkad taluk, and Thrissur district. The project impacted area is owned by Bossino International Pvt. Ltd. The projected is located in division 14 of Guruvayoor municipality.

1.4 ALTERNATE METHODS SUGGESTED

A better alternate route or location suitable for this project is not identified or suggested.

1.5 SOCIAL IMPACTS AND STEPS TO REDUCE THEM

When we analyze the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Re-settlement Act, 2013, it is concluded that social impacts can be managed through legal compensatory measures.

Sl. Expected loss Approach Possible reduction measures No.

1. Sound, atmosphere Control Include in the blueprint of impact pollution, dust etc. reduction measures

2. Delay in land acquisition Effective Distribution of compensation before and compensation monitoring land acquisition distribution and control

3. Loss of Water sources Control Implementation Agency to ensure underground water source with the help of local self-govt. establishment

11

4. Loss of Trees Compensati Adequate compensation and on and arrangement to plant equal number of Restriction trees in Private or Govt. Lands.

5. Include the affected Control Ensure participation of the affected in through land acquisition proceedings measures

6. Grievance redressal Control Functioning of efficient grievance redressal committees at district and panchayat level

12

CHAPTER 2

DETAILS OF THE STUDY

2.1 BACKGROUND AND LOGIC OF THE PROJECT

This chapter includes information related to the project of Holiday Home for Central Government Employees in Thrissur District. Public objectives and expense will be mentioned here.

2.2 DETAILS OF LOCATION, SIZE, OBJECTIVES AND EXPENDITURE OF THE PROJECT

The total land area required to be acquired for the project is 0.2104 Hectare belonging to Guruvayoor village, Chavakkad taluk, and Thrissur district. The project impacted area is owned by Bossino International Pvt. Ltd. Land acquisition authority has been the Directorate of CPWD, and the Special Tahsildar General (L.A) is the Land Acquisition Officer.

The project’s sole goal is to build living facilities for the central Govt. employees to spend their holidays comfortably. Constructing, maintaining and managing guest houses, holiday homes, officer’s hostel across India, come within the activities of the CPWD.

Members of the staff of all centralgovt departments could make use of the accommodation at fair cost. Above all, the project paves the way for the overall development of the State.

2.3 AUTHORISED BASIS OF PROJECT

 State Govt. entrusted the Revenue Dept. with the acquisition of land as per the rules and regulation of the new Act of 2013 and handing over to the CPWD.

 As per Notification No. 1823 of Volume 9 of Special Gazette dated August 13, 2020 of Kerala Govt. Youth Social Service Organisation was authorized to conduct a social impact study as per the laws and statutes of 2013, Act and submit a social impact study Report and counter impact implementation Plan.

13

 For the Holiday Home Project for Central Government Employees, Social impact study was conducted in 0.2104 hectares of land.  Dispensation of compensation prior to land acquisition as per 2013, Act is the demand of the impacted stakeholders.  The Central Division Executive Engineer, CPWD, Thrissur, shall be the Finance Authority and the Special Tahsildar (L.A) General Thrissur, shall be the Land Acquisition Officer.

2.4 CONSIDERATION OF ALTERNATIVE ROUTES

Only Holiday Home Project for Central Government Employees are included in the proposed project. The question of considering alternative route is quite irrelevant.

2.5 WORK FORCE REQUIREMENTS

In order that the project be completed successfully on the estimated time, it is imperative to ensure availability of the required diverse skilled manpower in the initial execution phase and work should eventually be finished as per schedule. For this purpose, most modern equipment and expert engineers are necessarily essential. Therefore, once work has begun, it should go on uninterrupted until the project is completed. It is expected that the locals as well as outsiders will get work opportunities during the project execution phase.

2.6 STAGES OF CONSTRUCTION

The construction has not started yet in the project area.

2.7 IMPORTANCE OF PUBLIC REQUIREMENT OF THIS PROJECT

Holiday Home Project for Central Government Employees,for which land is acquired and social impact is assessed is required for providing basic facilities for Kerala’s economic growth.

2.8 ENVIRONMENT IMPACT ASSESSMENT

 Should ensure eco-friendly construction  Should protect natural resources  A committee should formed to prevent any harm to the environment during after construction

14

2.9 PREVIOUS STUDIES

No previous studies have been conducted on Holiday Home Project for Central Government Employees; and the present study organized by the Youth Social Service Organisation can well be deemed as the first of its kind in this regard.

2.10 ACTS AND RULES AFFECTING THE PROJECT

Acts & rules listed below affect Land acquisition, Transparency, Rehabilitation and Re-settlement related to Holiday Home Project for Central Government Employees.

Sl. No. Acts and Rules Affected area

1. The Right to Fair Compensation and Transparency in Impact reduction land Acquisition, Rehabilitation and Re-settlement Act and Rules

2. Land Acquisition Acts & Rules Land acquisition Rehabilitation & Re-settlement act of the government Rehabilitation and Right to Information act 2005 Resettlement Rights of Persons with Disabilities Act 2016

RIGHT TO INFORMATION ACT 2005

For the effective functioning of democratic processes in a nation, informed citizens are a prerequisite. The Right to information Act 2005 is aimed to strengthen the democratic process by public participation through citizens’ empowerment, ensuring transparency and responsibility in governance and prevent corruption. This is an act giving information regarding activities of government to the citizens.

RIGHTS OF PERSONS WITH DISABILITIES ACT 2016

Rights of Persons with Disabilities Act 2016 came into being for socially and economically empowering persons with disabilities. On one hand it promotes equality and participation and the other hand it eradicates all discriminations.

15

CHAPTER 3

UNIT, APPROACH AND RATIONALE OF THE STUDY

3.1 BACKGROUND

As per G.O(P)No.DCTSR/2513/2018-E2 dated 13/08/2020, Youth Social Service Organization, Social Service Centre, College P.O, Kothamangalam is assigned to conduct Social Impact Assessment study on Holiday Home for Central Government EmployeesProject. This study unit is responsible to assess social impacts of the project.

This study is being conducted to submit report of social impact of Holiday Home for Central Government Employees Project on land to be acquired, public and private properties etc to District Collector. This study is conducted by collecting primary and secondary data from related individuals and institutions systematically. The affected people, families and institutions were approached directly and data were collected through a questionnaire.

3.2 DETAILS OF THE STUDY UNIT

The data collection for the social impact assessment study and their integration was done under Team Director of Youth Social Service Organization by a group of 6 experienced members. Services of experts from development and legal sector have been availed for the study and report preparation. And, revenue official helped to identify the affected areas.

Sl. Name Designation, Eligibility and Experience No.

1. Jose Paruthuvayalil Director, MSW, 22 years experience in development sector

2. Kuriakose George Project Coordinator, LLB, 15 years experience in development sector

3. Baiju P.T. Research Associate, MSW, 10 years experience in development sector

4. Savitha Sajeesh Research Associate, BA, 2 years experience in development sector

16

5. Jinu Joseph Research Associate, B.Com, ICW, 2 years experience in development sector

6. Mini Jibish Research Associate, BA, 2 years experience in development sector

3.3 SOCIAL IMPACT ASSESSMENT STUDY AND PREPARATION OF IMPLEMENTING PLAN

Acquisition of land and properties affects social and economic sustainability, social impact study and properly planned rehabilitation programs should be done. Rehabilitation plans should establish livelihood programs of the affected people same as before the land acquisition. The study unit has conducted the preparations for the social impact assessment with these obligations as priority.

Figure 3.1 shows the approach and rationale of the study in a flowchart. And stages of the study are listed below.

Figure 3.1: Social Impact Assessment study design and method Stage 1: Activities before study

Social Analysis and pilot meeting Pilot survey and beginning of external works

 Pilot study  Detailed project analysis  Preparation and checking of survey tools  Preparation of the project  Identifying the groups for data collection blueprint  Finalizing the pilot report  RFCT in LARR Act 2013  State laws on land acquisition

Stage 2: Data collection methods and implementation

The affected families/people/society Facilities required for the project

 Analysis of legal rules and regulations  Training for the field staff  Analysis of rehabilitation programs with  Data collection from the affected local officials family members  Data analysis  Discussions with officials of  Draft of collected data, their analysis and concerned departments impact assessment

17

Stage 3: Activities after survey and blueprint of the analysis

Tabulation of the collected data and Concerns on the Social Impact Assessment blueprint of analysis Study

 Integration, categorization of data  Organize public hearing  Finalization of the report  Meeting and discussions on study  Analysis of the collected data findings with affected people  Preparation and submission of the  Analysis and opinions of concerned draft report of the social impact officials assessment study  Integration of the opinions and submission of final report

3.4 DESK RESEARCH

Study Team examined the relevant documents, Reports, Project Plans etc. in details.

3.5 SECONDARY DATA

Secondary data was prepared from the studies conducted earlier and concerned departments. The study unit could realize the social economic and cultural circumstances of the affected people through the social impact assessment study.

3.6 THE AFFECTED AREA VISIT AND PROJECT AWARENESS CAMPAIGNS

Field visit and pilot study of socio economic survey was conducted before the detailed study of social impact assessment. Responses of the affected people were documented while conversing with them. The unit made adequate additions and corrections in the interview schedule.

As the area of the study and affected people were identified, primary data was collected from the concerned in August 2020, and the report was prepared by integrated analysis of the collected data.

18

AFFECTED AREA

3.7 EVALUATION OF CIRCUMSTANCES

The data collected where analyzed and studied, and where modified as per new information was generated. The study unit has taken required measures before data collection to prevent errors.

19

3.8 SCHEDULE OF CONSULTATIONS WITH KEY STAKE HOLDERS

Table 3.1 contains the socio-economic impact on the parties who are to be compensated for giving up land for the Project.

Sl. Name and address Survey Problems/requirements put forward No. No.

1. Bossino International 116/10 Impacted land belongs to Bossino International Pvt. Ltd. The land has water Private Ltd. well, compound wall and tree. Demanded fastest takeover of land and payment of fair compensation Issues raised at the public hearing: CPWD has intimated that decision was taken in 2017 to purchase land owned by Bossino International Pvt. at Rs 15.5 lakh per cent and instructed to take over the land at the price agreed by.

3.9 SUMMARY OFPUBLIC HEARING

A public hearing of the landowners affected by acquisition of plots belonging to Guruvayur Village, at Chavakkad Taluk, Thrissur District, was held before the authorities at 11 am on September 2020 at the Devaganam Residency Hall, Guruvayur.

Participated Officials

1. Sri. Sunil Kumar J. Junior Superintend (L.A. General Thrissur) 2. Smt. Rathi Teacher, Chairperson, (Guruvayur Muncipality) 3. Smt. Savitha Sajeesh, Ysso 4. Smt. Mini Jibish, Ysso 5. Sri. Yedhu Krishnan, Ysso

MAJOR ISSUES RAISED BEFORE AUTHORITIES Major subjects submitted before the authorities

1. Concerning appraisal of the land.

2. Concerning the period of time required to acquire the land following notification ll (1)

20

3. CPWD has intimated that decision was taken in 2017 to purchase land owned by Bossino International Pvt. at Rs 15.5 lakh per cent and instructed to take over the land at the price agreed by.

REPLY OF AUTHORITIES

Ex. Engineer, CPWD, Thrissur

With reference to above subject it is informed that this office has invited as per quotations through public notice in newspaper and identified the suitable land of Bossino International Pvt. Ltd. Company for 52 cents bearing survey No. 116/10 at Guruvayur Village, Chavakkad Taluk, Thrissur district, received three quotations by the Expert Committee formed by the Competent Authority. The quotationer has quoted at rate of Rs. 15, 50,000/- per cent. However as per the Land Acquisition, Rehabilitation and Resettlement Act, the identified land to be acquired through District Collector, Thrissur. Accordingly Special Thasildar, Thrissur vide letter No. 1578/2018 dated 12/12/2018 intimated the preliminary estimate as per the direction of District Collector, Thrissur and Competent Authority has accorded Administrative Sanction vide OM No.24/16/2019/W-1 DG/499 dated 27/11/2019.

Special Tahsildar (L.A.) General

 Appraisal :- As per RFCT LARR Act, 2013 as and when land need be undertaken for public purpose, land appraisal and compensation are calculated in accordance with sections 26,27,28,29 and 30 of the said Act.  In terms of time space, land shall be taken into possession within 12 months latest from Notification ll (1) and the Collector shall issue the amount within 12 months from the date of 19(1) publication. The above cited terms are stipulated in section 19 (2), 25 respectively of LARR Act, 2013.

Guruvayur Municipality Chairperson declared fullest support and co- operation necessary for the success of the project. The meeting was concluded with a vote of thanks.

21

PHOTOS OF PUBLIC HEARING

22

CHAPTER 4

EVALUATION OF THE LAND

4.1 INTRODUCTION

For acquiring land for Holiday Home Project for Central Government Employees, details of people losing land, the affected people, their socio economic information were collected through interview schedule prepared for it in August 2020. Details regarding the affected properties, their type, ownership, impacts on private properties, income and livelihood of people, and depth of impact due to project were collected. The effects of land acquisition for Holiday Home Project for Central Government Employees depicted below with the help of survey.

4.2 TOTAL IMPACT DUE TO INFLUENCE OF THE PROJECT:

Table 4.1 includes socio economic impact of people who donates their land and need compensation

Sl. Name and address Survey Problems/requirements put forward No. No.

1. Bossino International 116/10 Impacted land belongs to Bossino International Pvt. Ltd. The land has water Private Ltd. well,compound wall and coconut tree. Demanded fastest takeover of land and payment of fair compensation Issues raised at the public hearing: CPWD has intimated that decision was taken in 2017 to purchase land owned by Bossino International Pvt. at Rs 15.5 lakh per cent and instructed to take over the land at the price agreed by.

4.3 LAND REQUIRED FOR THE PROJECT

The total land area required to be acquired for the project is 0.2104 Hectare belonging to Guruvayoor village, Chavakkad Taluk, and Thrissur district. The project impacted area is owned by Bossino International Pvt. Ltd. The impacted land has a water well, compound wall and coconut tree.

23

4.4 ACQUISITION OF AFFECTED LAND

The total land area required to be acquired for the project is 0.2104 Hectare belonging to Guruvayoor village, Chavakkad Taluk, and Thrissur district. The project impacted area is owned by Bossino International Pvt. Ltd. The impacted land has a water well, compound wall and coconut tree.

4.5 REQUIREMENT OF PUBLIC LAND

No public land is required for the construction of Holiday Home Project for Central Government Employees.

4.6 LAND PURCHASED FOR THE PROJECT

No land is purchased for the project yet. Formalities for purchasing land will begin only after social impact assessment study.

4.7 GEOGRAPHY, CURRENT PURPOSE, AND LANDFORMS

Holiday Home project for Central Government Employees impacted area is owned by Bossino International Pvt. Ltd. The impacted land has a water well, compound wall and coconut tree.

4.8 NATURE OF OWNERSHIP

Table No.4.2 Nature of ownership

Type No. Percentage

Inherited 0 0

Purchased 1 100

No reply 0 0

Total 1 100

24

4.9 DURATION OF OWNERSHIP OF LAND

Table No.4.3 Duration of ownership

Year No. Percentage

2014 1 100

Total 1 100

4.10 EARLIER BUSINESSES IN THE AFFECTED AREA

Informants told that there were no land transactions in previous 3 years.

(The above information was provided by informants during data collection. Documents related need to checked and verified.)

25

CHAPTER 5

NO. OF FAMILIES AFFECTED AND DETAILS OF LOSS OF LAND

5.1 INTRODUCTION

The depth of impact on people and their properties affected directly and indirectly is depicted in this chapter.

5.2 PEOPLE AFFECTED DIRECTLY BY THE PROJECT

The total land area required to be acquired for the project is 0.2104 Hectare. The project impacted area is owned by Bossino International Pvt. Ltd. The impacted land has a water well, compound wall and coconut tree.

5.3 PEOPLE AFFECTED INDIRECTLY BY THE PROJECT

Those who have been living or working in the impacted area, but are not directly impacted by the project, are considered indirectly affected persons. The project impacts no such category of people.

5.4 FAMILIES OF SCHEDULED TRIBE AND FOREST DWELLERS WHO LOSE RIGHT ON FOREST

The acquisition of land for mentioned project does not affect any families of scheduled tribe and forest dwellers that lose right on forest, as it is owned by Bossino International Private Ltd Company.

5.5 DID THE FAMILIES DEPEND ON THIS LAND FOR LIVELIHOOD IN PAST 3 YEARS?

The land is owned not by individuals but by Bossino International Private Ltd Company. So, no families depend on this land for livelihood.

26

5.6 WAS THE LAND AVAILED THROUGH ANY WELFARE PROGRAMS OF STATE-CENTRE GOVERNMENTS?

No, the land in question is not owned by a family as part of any govt. welfare scheme.

5.7 WERE THE AFFECTED FAMILIES, INHABITANTS OF CITY FOR 3 YEARS OR MORE?

The land is owned not by individuals but by Bossino International Private Ltd Company. So, no families inhabiting city are involved.

5.8 ARE THE AFFECTED FAMILIES DEPENDING ON PUBLIC LAND AFTER ACQUIREMENT?

The land is owned not by individuals but by Bossino International Private Ltd Company. The affected does not have any families depending on public land after acquirement.

5.9 DETAILS OF FRUITFUL PROPERTIES

The area to be acquired for the Holiday Home for Central Govt. employees contains a number of coconut trees.

27

CHAPTER 6

SOCIO ECONOMIC BLUEPRINT

6.1 PREFACE

The total land area required to be acquired for the project is 0.2104 Hectare belonging to Guruvayoor village, Chavakkad taluk, Thrissur district. The project impacted area is owned by Bossino International Pvt. Ltd.

As the land to be undertaken for the Holiday Home Project is a private property, but that owned by a private limited Company, details regarding population, livelihood of families etc do not come in the scope of this project report.

28

CHAPTER 7

REDUCTION OF SOCIAL IMPACT

7.1 APPROACH TO REDUCE IMPACT

The affected individuals are demanding compensation amount and job for family members in order to reduce the impact of land acquisition. Hence, in order to reduce the impact, compensation of land acquisition needs to be decided through discussions with the affected families and distribute them before land acquisition.

Giving proper awareness to the affected regarding benefits of the project will help to reduce impact.

7.2 MEASURES TO ERADICATE IMPACT OR LOSS

The compensation should be decided and distributed as per ‘The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement act, 2013 (RFCTLARR Act 2013) in a timely manner.

7.3 MEASURES TO FULFILL THE PROJECT SUGGESTIONS

A special budget needs to be identified for distribution of compensation.

7.4 MEASURES TO REDUCE IMPACT

Sl. Expected loss Approach Possible reduction measures No.

1. Sound, atmosphere pollution, Control Include in the blueprint of dust etc. impact reduction measures

2. Delay in land acquisition and Effective Distribution of compensation compensation distribution monitoring and before land acquisition control

3. Loss of Water sources Control Implementation Agency to ensure underground water source with the help of local self-govt. establishment

4. Loss of Trees Compensation Adequate compensation and and Restriction arrangement to plant equal

29

number of trees in Private or Govt. Lands.

5. Include the affected through land acquisition measures Control Ensure participation of the affected in proceedings

6. Grievance redressal Control Functioning of efficient grievance redressal committees at district and panchayat level

30

CHAPTER 8

SOCIAL IMPACT MANAGEMENT

8.1 INSTITUTIONAL SYSTEMS AND RESPONSIBLE PERSONS

Administrator appointed by government as per RFCTLARR Act 2013 will be responsible for developing Re-settlement scheme for affected families. Under the supervision and guidance of government and Commissioner of Rehabilitation and Re- settlement, Administrator of Rehabilitation and Re-settlement t will be responsible for the formulation, implementation and monitoring of scheme for Rehabilitation and Re- settlement.

Provision of adequate compensation to the affected, as per RFCTLARR Act 2013, will not reduce impact.

As per the laws of state government, the district level committee on adequate compensation, Rehabilitation and Re-settlement should include following persons.

 District Collector  Administrator of Rehabilitation and Re-settlement  Land acquisition officer  Finance officials  Representatives of Arthana officials for taking financial decisions  Representatives of Local Self Government

31

CHAPTER 9

SOCIAL IMPACT ERADICATION BUDGET

9.1 EXPENDITURE FOR REHABILITATION AND RE-SETTLEMENT

The expenditure for Rehabilitation and Re-settlement is not calculated.

9.2 ANNUAL BUDGET AND PLANNING

Not applicable

9.3 CATEGORIZATION OF FINANCIAL SOURCE

Financial source of the affected area is not categorized.

32

CHAPTER 10

SOCIAL IMPACT ERADICATION PROGRAM-MONITORING & EVALUATION

10.1 MONITORING & EVALUATION – IMPORTANT INDICATORS

 Participation of land owners in District Level Purchasing Committee  Land was purchased directly from how many land owners  Indicators used to calculate compensation  Re-settlement of blocked entrances  Formation of grievance redressal committee  Time required for Rehabilitation and Re-settlement

10.2 METHOD OF REPORTING, MONITORING AND RESPONSIBILITIES

Not applicable

10.3 INDEPENDENT EVALUATION- MODEL

Not applicable

33

CHAPTER 11

ANALYSIS OF ADVANTAGES AND DISADVANTAGES: SUGGESTIONS ON LAND ACQUISITION

11.1 FINAL CONCLUSION: ANALYSIS OF POPULAR OBJECTIVES

0.2104 Hectare land of Guruvayur village of Chavakkad Taluk in Thrissur District is required for project of Holiday Home for Central Government Employees. This land is owned by Bossino International Private Ltd Company.

The land to be acquired is in private ownership and can be acquired by providing compensation as per 2013 act. The affected are ready to provide land for the project.

11.2 NATURE & EXTREME OF IMPACTS

Holiday Home Project for Central Government Employees requires land is under ownership of Bossino International Private Ltd. Company. The land has water well, compound wall and coconut tree.

The project area to be taken over for the Holiday Home Project contains no residential area, building or any related activities. Hence the project warrants no package for Rehabilitation or Re-Settlement.

But as it is a public development program, individuals need to provide their private land. Many people get affected adversely when land is acquired for public purposes. For protecting such person’s rights, the right to fair compensation and transparency in land acquisition, Rehabilitation and Re-settlement act, 2013 was enacted. 4th section of this act rules that if land is acquired for the nation’s development, public interest and social impact needs to be assessed.

SUGGESTIONS

Compensation should be given to owners by considering the benefits to public above project expenditure

34

SUMMARY

Holiday Home Project for Central Government Employees is a milestone in Thrissur city’s developmental race. This requires 0.2104 Hectare of land. This study will help to provide adequate compensation for the affected as per RFCTLARR Act, 2013.

Private properties need be surrendered for the sake of public projects. In connection with land acquisition for the project, the Bossino International Pvt.Ltd. Company suffers a loss of their land, water-well, a compound wall, coconut trees etc. The local landowners deserve fair compensation as per Act 2013.

While analyzing the beneficial side of the project, land acquirement for the project is highly essential. RFCTLARR Act 2013, has enough provisions to acquire land and provide compensations.

35

ACKNOWLEDGEMENT

This SIA Study project would not have completed without the help of different people and organisations. First of all we are grateful to the revenue department for entrusting this project to Youth Social Service Organisation. We also remember and acknowledge our gratitude to Thrissur District collector and all the staff members for their timely guidance to complete this project successfully.

We also acknowledge our gratitude to Special Thahasildar, and all the staff members for helping us to collect all the details of land acquisition. We remember CPWD Thrissur and all the staff members for their service to complete this project.

We extend our sincere thanks to the Chairperson of Guruvayur muncipality, Village officials of Guruvayur, and the people of the project area for then great help and co-operation.

We also gratefully remember the Executive Director of youth social service organisation for being the back bone of this project and guiding us in every step. If we could not have received any support from all these persons, we would not have completed this project successfully.

36

37

Annexure 1 (a) Gazatte notification

38

39

40

Annexure 1 (b) Notification (English)

41

42

Annexure 1 (c) Draft notice copy

43

44

45

46

47

48

49

Annexure 2 Socio economic survey questionnaire

Socio Economic Survey for Social Impact Assessment Study Land Acquisition for Holiday Home Project for Central Government Employees

SIA Ref No Interviewer’s Name Survey Date Supervisor Name Data Entry Staff Name Date Entered Date Data verified by, and Date

Respondent’s Name Name of the affected person (if different from above) Address including PINCODE (Location in the Affected Area) Contact (Landline No.) Contact (Mobile No) Identity Card Details (any one id proof) Aadhaar No. Ration Card No. Passport No. Voters Id

Q.1 Identification Place/Location Ward No. Name of Panchayath

Q. 2 Respondent Owner Representative of Owner

Q. 3 Name & Address Owner Representative of the Respondent of Owner

ASSET DETAILS

Q. 4 Type of Property

Open Land Nilam NilamNikathuPurayidam

50

Q. 5 Type of use

Open Land Wet Land Others (specify) (Agricultural Land)

Q. 6 Name of title holder of the property (Specify the names of all the members specified as per the title deed) a) Communication Address (with PINCODE) b) Contact No c) Relationship with family head d) Acquisition by Hereditary Purchase Encroached/squatter Others (specify) e) Date of acquiring of the property (approx period) f) Details of transactions made on the property within the last three years

Q. 7 Property Details a) Survey No (Mandatory b) Total Area (in hectares) c) Area Affected (in hectares)

In case of more than one property please use additional pages IMPACT

Q.8 Extent of acquisition Fully Partially Q. 9 Whether property viable after Yes No implementation of project

Q. VULNERABILITY

Q. 10 Do you have Ration Card? Yes No If Yes, Mention Number Q. 11 Type of Ration Care BPL APL AAY

GENERAL INFORMATION

Q. 12 Size of Male Female Family/household (specify no of family members)

51

Family Joint Nuclear Individual Pattern

Q. 13 Hindu Muslim Christian Jain Others Religious Q. 14 SC ST OBC General Others Social Group

FAMILY MEMBERS – DETAILS

SL. Name Relationship Age Sex Marital Education Job Monthly Major No. with the Status Income diseases Head of the Completed Continuing family

Q. 15 Livelihood (Major Source of Income) of Family Yes No affected

Q. 16 Family Income & Source a) Family monthly income (in Rs.) b) Family monthly expenditure (in Rs.) c) Major Source of Income c) No of adult earning members d) No of dependents

Project Related Information

Q. 17. Are you aware of the proposed Socio Economic Yes No Survey for Social Impact Assessment Study Land Acquisition for Holiday Home Project for Central Government Employees

Q. 18 If yes, source of information

Newspaper Internet/Social media TV/Media Community members All of the above Other (Specify)

52

Q19. What is the positive or other impacts envisaged from this project development

Positive impacts perceived Other perceived impacts Increase in employment opportunities Loss of productive land for agriculture due to better access facilities Increase in movement in terms of Pressure on existing infrastructure facility and frequency Increase in economic and business Conflict with outsiders activities Increase land prices Increase in the density around the project area Improvement in the real estate sector Increased spread of communicable diseases and other vulnerabilities Better reach/access to larger towns Increase in rentals for tenants for both (health/education) residential and commercial properties Higher income from rental due to this Others (specify) ...... infrastructure development Others (specify) ......

Q. 20 REHABILITATION OPTIONS a) Owner

Equivalent/better productive land What is preferred rehabilitation measure Case compensation at replacement value Training for income restoration Other (Specify) ......

Additional information

Sign

53

Annexure 3 Public hearing notification news (Janmabhoomi, Metro vartha)

54

Annexure 4 Notice to the affected families

55

Annexure 5 List of participants-officials and affected families

56

Annexure 6 Copy of the reply letter from the authorities

57

58