APPENDIX I (See paragraph – 6) FORM 1

(I) Basic Information

S. Item Details No. “SAI ENCLAVE” 1. Name of the project/s (Residential Building Project) Developer : M/s Sri Anuanand Construction Pvt. Ltd 8 (a) 2. S. No. in the Schedule [Building & Construction Project] Total Plot Area 24633.43 Sq. M. Built-up area Tower (A, B, C, 4406.91*4 = D) (B+ G+7) 17627.64 Sq. M. E (B+ G+9) 5503.41 Sq. M. Proposed capacity/area/length/tonnage to F (B+ G+9) 5503.41 Sq. M. 3. be handled/command area/lease G (B+ G+9) 5503.41 Sq. M. area/number of wells to be drilled H, I, J, K, L (B+ G+9) 5503.41*5=27517.05 Sq. M. M (B+ G+9) 5503.41 Sq. M. N (B+ G+9) 5503.41 Sq. M. TOTAL BUIL UP AREA 72661.74 Sq. M. In existing Project 4 nos. building blocks have been constructed, 8 building blocks are under construction 4. New/Expansion/Modernization and remaining 2 building blocks are proposed. Construction activities have been stopped from Oct.’2018. 5. Existing Capacity / Area etc. Building Blocks Existing Construction A 4406.91 Sq. M. (B+G+7) B 4406.91 Sq. M. (B+G+7) C 4406.91 Sq. M. (B+G+7) D 4406.91 Sq. M. (B+G+7) E 4955.16 Sq. M. (B+G+8) F 4406.91 Sq. M. (B+G+7)

G 3310.41 Sq. M. (B+G+5) H 3310.41 Sq. M. (B+G+5) I 2213.91 Sq. M. (B+G+3) J 2213.91 Sq. M. (B+G+3) K 1117.41 Sq. M. (B+G+1) L 1665.66 Sq. M. (B+G+2) TOTAL 40821.41 Sq. M.

Page 1 of 12

6. Category of Project i.e. ‘A’ or ‘B’ ‘B2’ Does it attract the general condition? If 7. No yes, please specify Does it attract the specific condition? If 8. No yes, please specify 9. Location Corners Latitude Longitude N 25°36'3.26"N 85° 2'21.61"E S 25°35'57.57"N 85° 2'24.08"E

W 25°36'1.79"N 85° 2'19.50"E E 25°35'58.98"N 85° 2'27.17"E Mauza Mustafapur, Thana Phulwari,Thana No.-36, Tauzi Nos.-5276 Phulwari, Plot No. 159,160,161, 162, Plot/Survey/Khesra No. 163, 166, 168, 169, 170, 171, 172, 173, 174, 176, 177, 179, 180, 181, 182, 184, 185 & 186 Khata no. 165, 167, 168, 169, 170, 171, 190, 193, 198, 239, 240 & 242. Village Mauza Mustafapur Tehsil District State Danapur Railway Station : 1.75 Km. Nearest railway station / airport along Patliputra Railway Station : 3.45 Km. 10 Railway Station : 3.45 Km. with distance in kms. Patna Junction : 9.45 Km. Patna Airport : 4 km. Nearest town, city, District Headquarters 11 Patna along with distance in kms. Village Panchayats, Zilla Parishad, Nagar Parishad, Kahagaul Municipal Corporation, Local Body 12 Nagar Vikash Awas Vibhag (complete postal addresses with telephone Mauza Mustafapur, Thana Phulwari, Dist. Patna nos. to be given) 13. Name of the Applicant Sri Bimal Kumar M/s Sri Anu Anand Construction Pvt. Ltd 14. Registered Address 102 , 1st Floor , Kumar Tower, Patna 800001 M/s Sri Anu Anand Construction Pvt. Ltd 15. Address for Correspondence 102 , 1st Floor , Kumar Tower, Boring Road Patna 800001 Name Sri Bimal Kumar Designation (Owner/Partner/CEO) Owner/Managing Director M/s Sri Anu Anand Construction Pvt. Ltd Address 102 , 1st Floor , Kumar Tower, Boring Road Patna Pin Code 800001 [email protected] / E-mail anuanandconstruction.com Telephone No. 09934674008 / 9771481333 / 0612 2538544 Fax No.

Page 2 of 12

Details of Alternative Sites examined, if No Alternate Site has been examined as the project 16. any. Location of these sites should be proponent is having development agreement with land shown on a toposheet owner for proposed building project 17. Interlined Projects No Interlined Projects Whether Separate application of interlined 18. Not Applicable project has been submitted 19. If yes, date of submission Not Applicable 20. If no, reason Whether the proposal involves approval/clearance under : 21. (a) The Forest (Conservation) Act, 1980 No (b) The Wildlife (Protection) Act, 1972 (c) The C.R.Z. Notification, 1991 The project area is classified as Residential Area (R1) Whether there is any Government in Draft Master Plan 2031, issued by Urban 22 Development & Housing Department, Govt. of Bihar, Order/Policy relevant/relating to the site vide Memo No. 11/N.Vi.Ma.Plan(Samiti)- 17/2014/832/UD&HD/Patna Dt: 28.10.2016 23. Forest land involved (Hectares) No forest land is involved Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up (a) Name of the Court 24. 82 (C2)of 2015; 06/04/2015 by SEIAA, Bihar (b) Case No. (c) Orders/directions of the Court, if any and its relevance with the proposed project

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Details thereof (with approximate Sl. Information/Checklist confirmation Yes/No quantities/rates, wherever possible) with source No. of information data Permanent or temporary change in land There will be permanent change in land use & use, land cover or topography including land cover of the area due to proposed building project with increase in intensity of 1.1 increase in intensity of land use (with Yes respect to local land use plan) land use as per Draft Master Plan 2031, issued by Urban Development & Housing Department, Govt. of Bihar. Clearance of existing land, vegetation No clearance work is required for the proposed project as land is flat with small 1.2 and buildings? Yes bushes & shrubs. There is no vegetation & buildings. Land will be used for establishment of 1.3 Creation of new land uses? Yes residential flats. 1.4 Pre-construction investigations e.g. bore Yes Soil Testing have been done. Geotechnical

Page 3 of 12

houses, soil testing? Investigation Report enclosed. Total Built Up Area (BUA) of project will be 1.5 Construction works? Yes 72661.74 Sq. M. for Residential. Demolition works? No demolition work is required, as currently 1.6 No there are no buildings or structures at project site. Temporary sites used for construction As all the construction workers will be from local nearby areas, thus, no temporary sites 1.7 works or housing of construction No workers? will be used for housing of construction workers Above ground buildings, structures or Total No. of flats will be 792 (3-BHK 264 + 2 1.8 earthworks including linear structures, Yes BHK 528) in 14 Nos. new residential building cut and fill or excavations blocks. Underground works including mining No underground works like tunneling or 1.9 No or tunneling? mining is involved. 1.10 Reclamation works? No No reclamation is required. 1.11 Dredging? No No dredging works involved 1.12 Offshore structures? No Not Applicable Production and manufacturing No production or manufacturing is involved. 1.13 No processes? Facilities for storage of goods or Construction Goods or materials will be 1.14 materials? No stored within the project area in temporary sheds. Solid waste will be disposed off through Facilities for treatment or disposal of /Danapur Nagar Parishad waste 1.15 Yes collection system.

solid waste or liquid effluents? STP of 500 KLD is proposed for residential building project. Facilities for long term housing of Most of the workers will be from local areas so 1.16 operational workers? No no long term housing facilities will be provided for workers. The project site is well connected with New road, rail or sea traffic during Danapur-Khagaul road, therefore there is no 1.17 No construction or operation? requirement of any new approach road construction. New road, rail, air waterborne or other The project site is well connected with transport infrastructure including new Danapur-Khagaul road, therefore no need to 1.18 No construct new road, rail, air waterborne or or altered routes and stations, ports, other transport infrastructure, altered routes airports etc? and stations, ports, airports etc Closure or diversion of existing There will not be any Closure or diversion of 1.19 transport routes or infrastructure leading No existing transport routes or infrastructure to changes in traffic movements? leading to changes in traffic movements. New or diverted transmission lines or There is no transmission or pipe lines passing 1.20 No pipelines? through the project site. Impoundment, damming, culverting, Due to the proposed project there will not be 1.21 realignment or other changes to the No any changes in the hydrology of watercourses hydrology of watercourses or aquifers? or aquifers. 1.22 Stream crossings? No There is no stream crossing Abstraction or transfers of water form Water will be used during construction and 1.23 Yes operational phase after obtaining permission

ground or surface waters? from CGWA/SGWA

Page 4 of 12

There is no water bodies within or near the Changes in water bodies or the land project site. However, there will be some effect 1.24 Yes on natural drainage or run off pattern which

surface affecting drainage or run-off? will be address through storm water management. Transport of personnel or materials for Transport of personnel and construction 1.25 construction, operation or Yes materials will be through existing road decommissioning? networks. Long-term dismantling or There is no Long-term dismantling or 1.26 No decommissioning or restoration works? decommissioning or restoration works. Ongoing activity during There will a minimal impact on the environment as this is a building construction 1.27 decommissioning which could have an Yes project. No additional activity will be carried impact on the environment? out during decommissioning. This is a residential building project. Total No. Influx of people to an area in either of flats will be 792 in 14 Nos. of Blocks so 1.28 Yes therefore influx of people temporarily during

temporarily or permanently? construction phase and permanently during operational phase both. No alien species will be introduced due to 1.29 Introduction of alien species? No proposed residential project Loss of native species or genetic There is very less probability in loss of native 1.30 No species or genetic diversity due to proposed diversity? building project 1.31 Any other actions? No

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Details thereof (with approximate Information/checklist confirmation Yes/No quantities/rates, wherever possible) with source of Sl. No. information data The land is classified as residential in nature by Urban Development Deptt., Govt. of Bihar. Land especially undeveloped or The proposed residential project will be 2.1 Yes agricultural land (ha) established on Land available under Development Agreement in an area of 24633.43 Sq. M. Water (expected source & competing 620 KLD (Fresh Water: 360 KLD; Recycle 2.2 Yes Water from STP: 260 KLD) Fresh water will users) unit: KLD be sourced through Borewells No minerals will be used for the proposed 2.3 Minerals (MT) No project operations. Construction materials such as Cement, Steel, Construction material – stone, Bricks, Stone aggregates, and Sand would be 2.4 aggregates, sand / soil (expected Yes required for the project. These will be source – MT) procured from reputed licensed local vendors. 2.5 Forests and timber (source – MT) Yes No forest & timer source are required Energy including electricity and fuels 2.6 Yes 4000 KW through BSEB Grid & for power (source, competing users) Unit: fuel back-up 7 Nos. of DG Sets (125 KVA each) in

Page 5 of 12

(MT), energy (MW) each Blocks will be installed. Approx. 12 Ltr./Hr. HSD with low sulphur content will be used for operation for each DG Sets. Any other natural resources (use No other natural resources will be utilized 2.7 No appropriate standard units) for proposed project.

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Information/Checklist Details thereof (with approximate quantities/rates, Sl. No. Yes/No confirmation wherever possible) with source of information data This is a Building Construction project. No storage Use of substances or of hazardous chemicals (as per MSIHC rules) materials, which are would be done, apart from Waste Lube Oil (0.5 hazardous (as per MSIHC KL/Annum) which would be generated from the 3.1 No rules) to human health or the DG Sets. environment (flora, fauna, The Spent Oil would be carefully stored in HDPE and water supplies) drums in isolated covered facility and disposed off through CPCB/BSPCB authorized vendors. Changes in occurrence of This is an infrastructure project which involves disease or affect disease retail complex and residential flats therefore 3.2 No vectors (e.g. insect or water no changes in occurrence of disease is borne diseases) anticipated. Proposed residential project will change living Affect the welfare of people condition of people as the project will provide opportunity to earn their livelihood by various 3.3 e.g. by changing living Yes activities such as Retail staffs & Managers, Drivers, conditions? Cleaners, Security guards, Horticulturist, Servants etc. Vulnerable groups of people No vulnerable groups of people will be adversely who could be affected by the affected by the project rather there may be positive 3.4 Yes project e.g. hospital patients, effects due to the proposed residential area in the children, the elderly etc., complex. 3.5 Any other causes No

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Details thereof (with approximate Sl. Information/Checklist Yes/No quantities/rates, wherever possible) with source No. confirmation of information data Spoil, overburden or mine This is an infrastructure project, no Spoil, 4.1 No wastes overburden or mine wastes will be generated. 1432 Kg/Day of Solid wastes will be generated from Municipal waste (domestic and the proposed Residential Building Project which 4.2 Yes or commercial wastes) will be disposed off, either, through, Danapur Nagar Parishad Waste lube oil generated from DG Sets will be Hazardous wastes (as per 4.3 Yes disposed off through CPCB/BSPCB authorized Hazardous Waste Management Rules) vendors. 4.4 Other industrial process wastes No No industrial process wastes will be generated.

Page 6 of 12

4.5 Surplus product No No Surplus product will be generated. Sewage sludge or other sludge Dried STP Sludge can be used as manure for 4.6 Yes from effluent treatment gardening. Construction or demolition Excavation waste may be recycled for raft, columns 4.7 Yes wastes etc. & reuse for land filling. Redundant machinery or 4.8 No equipment Contaminated soils or other 4.9 No No contaminated soils will be generated materials 4.10 Agricultural wastes No No agricultural wastes will be generated 4.11 Other solid wastes No

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sl. Information/Checklist Details thereof (with approximate quantities/rates, Yes/No No. confirmation wherever possible) with source of information data

Air emissions comprising of PM10, PM2.5, NO2 & SO2 are anticipated from the operation of DG sets which will be used for power back-up during emergency only Emissions from combustion of Besides DG sets, air emissions will also be from the 5.1 fossil fuels from stationary or Yes vehicles approaching and leaving the proposed mobile sources Residential premises.

Green belt will be developed all around the premises & water sprinkling will be done to minimize air pollution due to above sources. Emissions from production 5.2 No There is no production process processes Fugitive emissions are envisaged during handling, transport and unloading of construction materials which would be controlled through water Emissions from materials sprinkling and other such techniques. Vehicles carrying construction materials will be covered 5.3 handling including storage or Yes with Tarpaulin to prevent fugitive emission. All transport loose construction materials which can lead to fugitive dust emission will be properly covered and entire construction site will be fenced by raising 20 feet GI sheet fence. Emissions from construction There will be some amount of dust generation 5.4 activities including plant and Yes during construction. Proper care will be taken for equipment suppression of dust by water sprinkling. Dust or odours from handling of Dust emissions due to construction activity. Proper 5.5 materials including construction Yes control measures will be taken to minimize the materials, sewage and waste generated volume of dust and dirt Emissions from incineration of 5.6 No There will no incineration of waste at project site. waste Emissions from burning of 5.7 waste in open air (e.g. slash No There will no burning of waste at project site. materials, construction debris)

Page 7 of 12

Emissions from any other 5.8 No There will be no other source of emissions sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Information/Checklist Details thereof (with approximate quantities/rates, Sl. No. Yes/No confirmation wherever possible) with source of information data The DG set room, compressors and pump room From operation of equipment will be isolated from the outside environment and proper acoustic arrangements will be made to 6.1 e.g. engines, ventilation plant, Yes control the noise generated. The proposed DG set crushers will meet the criteria of CPCB specification.

From industrial or similar No industrial or similar processes are ongoing at 6.2 No processes proposed site From construction or Noise [upto 55 - 65 dB(A) ] will be generated during 6.3 Yes demolition construction activity Piling will be carried out with latest modern technology which will have very little level of noise 6.4 From blasting or piling Yes and vibration only during initial stage of construction. Due to operation of vehicles carrying construction From construction or materials 60-65 dB(A) & due to movement of 6.5 Yes operational traffic vehicles during operation 50-55 dB(A) within the proposed residential premises. From lighting or cooling 6.6 No systems 6.7 From any other sources No There will be no other source for Noise & Vibration

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Information/Checklist Details thereof (with approximate quantities/rates, Sl. No. Yes/No confirmation wherever possible) with source of information data From handling, storage, use Waste oil from DG sets will be stored in leak proof sealed barrels to prevent any risk of contamination 7.1 or spillage of hazardous No of land or water and will be disposed through materials authorized dealers / re-processors. From discharge of sewage or 500 KLD STP proposed, Treated water will be other effluents to water or suitable for re-circulation & car washing, green 7.2 No belt irrigation and fire water tanks. Balance treated the land (expected mode and water from above will be discharged to Main Sewer place of discharge) Line of Patna Municipal Corporation. There will be no other source of emission except By deposition of pollutants DG Sets & vehicular movement. DG Sets will be 7.3 emitted to air into the land Yes equipped with proper air pollution control device or into water & adequate stack height for wider dispersion of pollutants. Only domestic waste water will be generated which 7.4 From any other sources No will be treated in proposed STP inside the premises. Is there a risk of long term No there is no a risk of long term build up of 7.5 No pollutants in the environment from the proposed build up of pollutants in the project.

Page 8 of 12

environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

Information/Checklist Details thereof (with approximate quantities/rates, Sl. No. confirmation Yes/No wherever possible) with source of information data

No explosive, flammable material will be handled, stored or used beyond the Threshold Limit of From explosions, spillages, MSIHC Rules at proposed Residential Project. fires etc from storage, Fire fighting & Evacuation plan in compliance to 8.1 No Fire Clearance is proposed for the proposed handling, use or production of residential complex to tackle any emergency hazardous substances situations. The fire fighting installations incorporated in the building will conform to the NBC Guidelines. Fires due to mishandling of gas cylinders & electrical short circuiting or other such related problems. The basic system for fire fighting shall be designed 8.2 From any other causes Yes as per the provisions of the NBC, 2005 (part IV). The fire classification of the complex would be as Residential Building ‘Group A’ & Mercantile ‘Group F’. Patna Fire Station is at a distance of 10 Kms. Could the project be affected As Bihar is situated in Seismic Zone IV, thus, by natural disasters causing there are possibilities of earthquakes. In the year 1988 there was massive earthquake take place. 8.3 environmental damage (e.g. Yes Proposed Buildings are designed as per floods, earthquakes, earthquake resistant norms as prescribed in IS landslides, cloudburst etc)? 1893, IS 4326 & IS 13920.\

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Details thereof (with approximate quantities/rates,

wherever possible) with source of information data Yes/No Information/Checklist Sl. No. confirmation 9.1 Lead to development of supporting. facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: • Supporting infrastructure Yes Due to proposed residential project there may be (roads, power supply, waste or some upliftment in the Supporting infrastructure waste water treatment, etc.) (roads, power supply, waste or waste water treatment, etc. • housing development

Page 9 of 12

• extractive industries Yes More residential projects may come • supply industries No This is not an industrial project. • other No No Lead to after-use of the site, After use of site will not make any impact on the 9.2 which could have an impact No environment on the environment Set a precedent for later The proposed project may set precedent for later 9.3 Yes developments developments Have cumulative effects due There will be cumulative effects, in the form of increased traffic generation which will increase 9.4 to proximity to other existing Yes or planned projects with similar the air pollution load, due to proposed residential effects building Project. (III) Environmental Sensitivity

Name/ Aerial distance (within 15 S. No. Areas km.) Proposed project Identity location boundary Kumhrar Archeological 14.5 Km. Site Areas protected under international conventions, Sanjay Gandhi 1 national or local legislation for their ecological, 6 km. landscape, cultural or other related value Zoological Park 10.5 Km.

Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or 2 River Ganga 5 Km. other water bodies, coastal zone, biospheres, mountains, forests Danapur Cantonment where the rare species of migratory birds 4.0 km. Areas used by protected, important or sensitive known as 'Asian 3 species of flora or fauna for breeding, nesting, Open Bill foraging, resting, over wintering, migration Storks' come on an annual basis.

Flood Plains of 4.0 Km. River Ganga

4 Inland, coastal, marine or underground waters Not Exists 5 State, National boundaries Not Exists Routes or facilities used by the public for access 6 Bailey Road 2.5 km. to recreation or other tourist, pilgrim areas Danapur 7 Defence installations 4.0 km. Cantonment

Page 10 of 12

Rampur 700 m. Ramnagar 3.75 Km. 8 Densely populated or built-up area Colony Daroga Rai 1.5 Km. Colony Mainpura 900 m. Paras HMRI Areas occupied by sensitive man-made land uses Hospital 3.75 Km. 9 (hospitals, schools, places of worship, community IGIMS 4.75 Km. facilities DAV School 500 m. DPS School 1.5 Km Hanuman 3.15 Km. Temple Radha Krishna Mandir and Sai 6.50 Km. Temple Areas containing important, high quality or 10 scarce resources (ground water resources, surface River Ganga 5 Km. resources, forestry, agriculture, fisheries, tourism, minerals) Areas already subjected to pollution or River Ganga 5 Km. 11 environmental damage. (those where existing legal environmental standards are exceeded) Patna Urban Area 3 Km. Earthquakes As Bihar is situated in Seismic Zone IV, thus, there are possibilities of earthquakes.

Flooding Due to proximity to River Ganga, there may be chances of Flood. Last major flood was recorded in the year 1975 Subsidence/Land No Landslide will be slide occurred due to the Areas susceptible to natural hazard which could proposed project. No 12 cause the project to present environmental ground subsidence due problems (earthquakes, subsidence, landslides, erosion, to the active toe erosion flooding or extreme or adverse climatic conditions) by rivers and streams Erosion No such erosion will be occurred due to the proposed project. However Landscaping, indigenous plant or green belt will be developed within the premises. Extreme or No extreme or adverse Adverse climate conditions are observed in the study area

Page 11 of 12

(IV).Proposed Terms of Reference for EIA studies

The proposed activity will not covered under Terms of Reference

“I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.

Date : 24.10.2018 Place : Patna Signature of the applicant With name and Full Address (Project Proponent / Authorised Signatory) NOTE :

1. The projects involving clearance under Coastal Regulation Zone Notification, 1991 shall submit with the application a C.R.Z. map duly demarcated by one of the authorized agencies, showing the project activities, w.r.t. C.R.Z. and the recommendations of the State Coastal Zone Management Authority. Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the C.R.Z. Notification, 1991 for the activities to be located in the CRZ.

2. The projects to be located within 10 km. of the National Parks, Sanctuaries, Biosphere Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and the recommendations or comments of the Chief Wildlife Warden thereon.

3. All correspondences with the Ministry of Environment & Forests including submission of application for TOR/Environmental Clearance, subsequent clarifications, as may be required from time to time, participation in the EAC Meeting on behalf of the project proponent shall be made by the authorized signatory only. The authorized signatory should also submit a document in support of his claim of being an authorized signatory for the specific project.

Page 12 of 12

FORM-1 A

CHECK LIST OF ENVIRONMENTAL IMPACTS

(Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme)

1. LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity)

1.1 Will the existing landuse get significantly altered from the project that is not consistent with the surroundings? (Proposed landuse must conform to the approved Master Plan / Development Plan of the area. Change of landuse if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. SAI ENCLAVE project area falls under Residential Area (R1) in approved Draft Master Plan 2031 (attached as Fig. 1) of Urban Development & Housing Department, Govt. of Bihar, issued vide Memo No. 11/N.Vi.Ma.Plan(Samiti)-17/2014/832/UD&HD/Patna Dt: 28.10.2016. Site location (SOI toposheet), 500m. radius surrounding Google map and site photographs are attached herewith as Fig. 2, Fig. 3 & Fig. 4 respectively.

SAI ENCLAVE is a new Project in which 4 nos. building blocks have been constructed, 8 building blocks are under construction and remaining 2 building blocks are proposed. Construction activities have been stopped from Oct.’2018.

Existing land use has not get significantly altered due to Proposed Residential Project of “SAI ENCLAVE”. The project is consistent with the surroundings of the project area. Surrounding area comprises of residential flats, schools, offices and health care facilities. Proposed Project is coming up on land under Development Agreement between land owners and Developer at Mauza Mustafapur, Thana Phulwari, Thana No.-36, Tauzi Nos.-5276 Phulwari, Plot No. 159,160,161, 162, 163, 166, 168, 169, 170, 171, 172, 173, 174, 176, 177, 179, 180, 181, 182, 184, 185 & 186 Khata no. 165, 167, 168, 169, 170, 171, 190, 193, 198, 239, 240 & 242.

Approved Master Plan of proposed buildings is enclosed herewith as Annexure – I, approved by certified architect of Khagaul Nagar Parishad.

Development Agreement copy is enclosed herewith as Annexure – II.

Total cost of the project is approx. Rs. 108.5 Crores.

Building Plan has been Approved vide Plan Case No. NPK/Mustafapur/(R), Ref. No. RK/38/12 Dt: 10.12.2012 by Nagar Parishad Khagaul Certified Architect, Fire Clearance from State Fire Office vide Letter No. 644 dt: 12.03.2012 & 1882 Dt: 13.06.2013 has been

1 obtained. (Copy enclosed as Annexure – III) Height Clearance from Airport Authority of has been obtained vide Letter No. 09/2012 has been obtained. (Copy enclosed as Annexure – IV)

The project site is located at Danapur - Khagaul Road at Mauza Mustafapur, Thana Phulwari,Thana No.-36, Tauzi Nos.-5276 Phulwari, Plot No. 159,160,161, 162, 163, 166, 168, 169, 170, 171, 172, 173, 174, 176, 177, 179, 180, 181, 182, 184, 185 & 186 Khata no. 165, 167, 168, 169, 170, 171, 190, 193, 198, 239, 240 & 242., Dist. Patna, Bihar. The Geo Co-ordinates of the project site are as under ;

Corners Latitude Longitude N 25°36'3.26"N 85° 2'21.61"E S 25°35'57.57"N 85° 2'24.08"E W 25°36'1.79"N 85° 2'19.50"E E 25°35'58.98"N 85° 2'27.17"E

The various features in the vicinity of the project area are as follows ;

Jalalpur (2.10 km.), Dhanaut (2.75 km.), Rukunpura Khagaul Road (1.5 Km.), Devi West Temple (1.5 Km), Danapur Khagaul Road (100 m.) East Jamsaut (50 m.), Residential Area, Danapur Road (3 Km) North Danapur (2.25 Km.), Mainpura (1000 m.), Saguna More (2.75 Km), South Danapur Railway Station (1.75 Km.), Rampur (600 m.), Khagaul (2 Km.)

Topographical Map and Site & Surroundings location map of 500 m. radius area is shown hereunder ;

2

Fig. 1 - Patna Master Plan 2031, issued by Urban Development & Housing Department, Govt. of Bihar vide Memo No. 11/N.Vi.Ma.Plan(Samiti)-17/2014/832/UD&HD/Patna Dt: 28.10.2016

PROJECT SITE of “SAI ENCLAVE” Residential Building Project M/s Sri Anu Anand Construction Pvt. Ltd

3

Fig. – 2 PROPOSED PROJECT SITE ON TOPOSHEET MAP

Project Site of SAI Enclave

4

Source : Survey of India Toposheet No. 72 G/2 Scale 1:50,000

FIG. – 3 SURROUNDINGS LOCATION MAP OF 500 M. RADIUS AREA

5

FIG. – 4 -- SITE PHOTOGRAPHS

6

1.2 List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc.

Land & Area Details of Residential Project “SAI ENCLAVE” are as under ;

Particulars Details 1. Total Plot Area 24633.43 Sq. M. 2. Total Built-up Area 72661.74 Sq. M. Block A: 4406.91 m2 Block B: 4406.91 m2 Block C: 4406.91m2 Block D: 4406.91 m2 Block E: 5503.41 m2 Block F: 5503.41 m2 3. Residential Block wise built-up area A,B,C &D (B+G+7) & Block G: 5503.41 m2 Block H: 5503.41 m2 Block E,F,G,H, I,J,K,L,M &N Block I: 5503.41 m2 Block J: 5503.41 m2 Block K: 5503.41 m2 Block L: 5503.41 m2 Block M: 5503.41 m2 Block N: 5503.41 m2 4. Total Built-up Area 72661.74 Sq. M. 5. Ground Coverage Achieved 34.00% 6. Ground Coverage permissible 50.00% 7. FAR Achieved 2.99 8. FAR Permissible 3.00 9. Total Parking Area Available 15882 Sq. M. 10. Covered Parking Area 7840 m2 11. Open Parking Area 8042 m2 12. Green Belt & Landscape Area 4926.68 Sq. M. (20%) 13. Maxm. Height of Buildings 33 m. 14. Total Nos. of Residential Flats 792 Nos. 15. Proposed Occupancy of residential Building (@ 5 persons for = 792 3960 persons Flats 16. Visitors @ 15% 594 persons 17. Energy / Power including 4000 KW through BSEB Grid & for power electricity and fuels (source, back-up 7 Nos. of DG Sets (125 KVA each) in competing users) Unit: fuel (MT), each Blocks will be installed. energy (MW)

7

- Water Consumption : 620 KLD (360 KLD Fresh Water through Borewells & 260 KLD STP treated water)

- Power requirement : 4000 KW through BSEB Grid

- Connectivity: The project site is located on Danapur Khagaul Road connecting Danapur Railway Station in the South to Saguna More in the North. The nearest railway station is Danapur Railway Station about 1.75 km. E, Patliputra Railway Station in NE, Phulwari Sharif Railway Station in SE is about 3.45 Km each & Patna Junction 9.75 Km. E from the project site. The nearest airport is Lok Nayak Jayprakash Narayan International Airport, at 4 km (SE) from the project site.

- Community facilities: All community facilities like schools, market, educational institutions, banks, hospital etc. are located within 0.5 – 2 km. radius of Project area.

- Parking Needs:. As per MoEFCC guidelines, 1 ECS for every 2 tenements having built- up area 101 to 200 m2 (Refer : Manual on norms and standards for environment clearance of large construction projects, by MoEF, Govt. of India, Annex 3.1) parking is required.

However in the SAI Enclave building project 7840 Sq. M area has been provided as covered parking and 8042 Sq. M. is open parking space with multilevel parking facility. Total parking area of 23924 Sq. M. area is allocated. Parking provisions have been made for 792 ECS for residents and 119 ECS for visitors.

1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities, details of the existing landuse, disturbance to the local ecology). Increased traffic volume & Water use are major impacts envisaged due to proposed Residential “SAI ENCLAVE” Building Project. Project site is located nearby Danapur Khagaul Road (width 40 ft.) connecting Danapur Railway Station in the South to Saguna More in the North is well developing residential area which is connected with all important places of Patna Town through Bailey Road. At present existing land use of the surrounding areas is residential.

There will be no disturbance to local ecology of the area, as waste water generated from the Sai Enclave building project will be treated in STP inside the premises & treated water will be reused within the premises for car washing, irrigation of green areas, fire water tanks and balance treated water will be discharge to govt. Drains.

1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given).

The Soil of the study area has been developed under the dominant influence of river, vegetation and climatic factors. The site is clear and surface level is flat. Also, for execution of the proposed buildings piling activities will take place. Therefore, while executing the project,

8

the existing ground level will be modified. But, adequate measure will be taken to minimize the land disturbance of the project site and surrounding areas.

The area under study falls in Zone-IV according to the Indian Standard Seismic Zoning Map. Suitable seismic coefficients in horizontal and vertical directions respectively, will be adopted while designing the structures. 1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site)

No intersection or alteration in natural drainage system envisaged due to SAI Enclave Residential building project. Well planned storm water drainage has been designed to take care of internal storm water drainage. There is also plan of govt. drains in the surrounding areas, therefore, problem of water logging will not arise due to building project.

1.6 What are the quantities of earthwork involved in the construction activity-cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc.)

For the construction of proposed residential building project cutting works are involved for basement floor. Approx. 28000 m3 of soil will be excavated for basement. All the excavated soil will be used for filling of the site and for land leveling purposes and future green belt development activity.

1.7 Give details regarding water supply, waste handling etc during the construction period. Water requirement during construction phase is expected to be about 30 m3/day, which will be met by temporary borewells.

There is no demolition works, however, whatever waste will be generated during construction period will be used for filling purposes.

1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity)

Not Applicable. As there is no low lying & wetlands areas at the proposed Residential Building Project area.

1.9 Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)

There is no such construction activity which can cause health hazard. However, generated waste will be sold to authorized vendors.

9

2. WATER ENVIRONMENT

2.1 Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement.

The total water requirement for the proposed residential building project of “SAI ENCLAVE” Project will be approx. 620 KL/day. Fresh water requirement will be 360 KL/Day. Toilet flushing, Car Washing, Green belt & landscape irrigation and Fire fighting water requirement will be met by Treated Water from STP. The fresh water will be sourced through Borewells. Water Budget & Water Balance for the Building Project are shown here as under ;

WATER BUDGET :-

Components Occupancy Requirements as per MoEF / NBC Actual / Area Guidelines Requirement Domestic Flushing Total in KLD (Fresh Water) (Treated Requirement Requirement Water) Requirement Residential Flat 3960 Nos. 90 45 135 535.0 Occupancy Ltr./day/head Ltr./day/head Ltr./day/head (Domestic 356 & Flushing (178) Visitors @15% 594 Nos. 5 10 15 9.0 (Residential Ltr./day/head Ltr./day/head Ltr./day/head (Domestic 3 & Area) Flushing (6) Security & 15 Nos. 5 10 15 0.23 Maintenance Ltr./day/head Ltr./day/head Ltr./day/head (Domestic 0.08 Staff & Flushing (0.15) Total Fresh Ground Water Requirement for Domestic Use 360 Toilet Flushing Water Requirement (STP Treated Water) 184 Horticulture, Landscaping & Miscellaneous (STP Treated Water) 6 Car Washing (STP Treated Water) 20 Fire Fighting Tanks (STP Treated Water) 50 TOTAL WATER REQUIREMENT 620 KLD maxm.

10

WATER BALANCE FOR “SAI ENCLAVE” (RESIDENTIAL) PROJECT

Water Requirement 260 KL/day STP Treated Water 620 KL/day Recycle & Reuse

Toilet Flushing Green Belt Car Washing Fire Water Requirement Domestic Water Water 20 KL/day Tanks 184 KL/day Requirement (Fresh Requirement 50 KL Ground Water) 6 KL/day 360 KL/day

Waste Water @ 80% Treated Water

STP STP 288 KL/day 184 KL/day

472 KL/day

STP based on MBBR Process 500 KL/day Overflow Treated Water @ 90% 190 KL/day discharge to say 450 KL/day Govt. Sewer Line 11

2.2 What is the capacity (dependable flow or yield) of the proposed source of water? Fresh water will be sourced through Bore wells with an Yield of 100 KL /hr working to meet the overall water requirement of the proposed building project.

2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality)

Fresh water will be sourced through Bore wells within premises. Borewell will act as standby source. Ground Water Characteristics of the project area is enclosed herewith.

Analysis Report Enclosed as Annexure – VI 2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage) Approximately 260 KLD treated sewage will be reused for toilet flushing, car washing, irrigation of landscape & green belt within premises & Fire water tanks. Balance treated water will be discharged to govt. drains.

12

2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption) No, there will not be any diversion of water from other users because water will be extracted through borewells within premises. 2.6 What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity) Approx. 472 KLD waste water will be generated from the proposed Residential Building project. All waste water generated will be treated in STP and reused for toilet flushing, car washing, landscape irrigation & Fire water storage tanks. Characteristics of effluent from proposed building project will be as under ;

Expected Concn. of Generated Parameters Effluent from proposed Project 1. pH 6.5 - 7.5

2. Suspended Solids mg/l., 100 – 200 mg/l.

3. BOD ( 3 days at 270C), mg/l. 100 – 200 mg/l.

4. COD, mg/l. 300 – 400 mg/l.

5. Oil & Grease, mg/l. 2 – 5 mg/l.

At present there is no sewage line, so we will discharge our treated effluent to soak pit within premises. 2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created. No water requirement will be met from rain water harvesting in the proposed building Project. Rather, rain water from the roof of the proposed buildings will be collected and discharged into ground water aquifer through recharge pits.

RAIN WATER HARVESTING POTENTIAL OF PROPOSED BUILDING PROJECT :- Rain Water Harvesting Plan Enclosed as Annexure – VII.

Run-Off Annual Avg. RWH Type of Area Area is M2 Coefficient Rainfall in m. Potential (m3) Roof Area 8375 0.90 0.85 6407 Roads & Paved 3200 0.85 0.85 2312 Areas Open Area 8131 0.30 0.85 2073 Green Belt Area 4926 0.20 0.85 837 TOTAL 11630 M3 Annual Rainwater Harvesting Potential

13

As per Guidelines of MoEFCC, 14 Nos. of Recharge Pits will be provided within this building project to recharge ground water aquifer.

2.8 What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long term basis? Would it aggravate the problems of flooding or water logging in any way? The proposed project will not cause any adverse impact on runoff characteristics. All the drains within the proposed Residential Building Project will be connected with main govt. drain outside the premises. Further, Rainwater harvesting scheme is proposed to collect the rainwater falling within the project premises which will be used for groundwater recharge. Proposed building Project will not aggravate the problems of flooding or water logging in any way as there will be proper drainage network within the premises for storm water management which will be finally connected to govt. drain.

2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any)

- Ground water will be abstracted through borewells. - Ground Water depth of the area is approx. 5-10 m. bgl during pre monsoon & 2-5 m. bgl during Post monsoon. (Source : CGWB Data) - Annual Rain Water Harvesting Potential : 11630 M3

2.10 What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts) The following control measures will be adopted in order to minimize the construction impacts on water quality : o Appropriate sanitation facilities will be provided for the labours to reduce impact on water quality. o No construction wastewater will be discharged directly on land or into the river as there is no river within 500 m. where drainage slope of the project is leading. A couple of Sediment traps with retention period of half an hour will be constructed during the construction stage, where all construction wastewater will be collected. After the sedimentation of the construction wastewater, the comparatively cleaner water may be reused for wetting of building materials & structures. 2.11 How is the storm water from within the site managed?(State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels)

Storm water from the proposed Residential Building project will be discharge to govt. drains. There will be properly designed drain network within the proposed project. Premises which will be finally connected to govt. drain.

2.12 Will the deployment of construction labourers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation)

14

No, as most of the construction labours are from local areas. However, following measures will be adopted to avoid unsanitary conditions around the project site ;

- Proper on-site sanitation facilities will be provided for the construction labourers so as to avoid defecation in and around project site.

- Temporary Toilets comprising lavatory, bath, hand-wash facilities will be constructed inside the project site.

- Moreover, adequate water supply for drinking and other domestic uses will also be provided during the construction stage of the project.

2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal) Approx. 436 KLD domestic effluent will be generated from the proposed Residential cum “SAI ENCLAVE”. All these effluent will be sent to 450 KLD capacity STP inside premises for treatment. The process of treatment is as under ;

A 450 KLD Sewage Treatment Plant (STP) based on MBBR (Moving Bed Bio Reactor) Technology will be installed. Operation details of proposed MBBR technology STP are as under ;

Preliminary Treatment: The treatment will include the following unit / equipment; o Screen Chamber o Oil & Grease Trap o Raw Sewage Collection Tank o Raw Sewage Transfer pumps

Biological Treatment (Secondary Treatment): This will include the following; o MBBR Bioreactor o Secondary Clarifier o Sludge Dewatering System-(Filter press)

Tertiary Treatment: The treatment will include the following unit / equipment; o Filter feed pumps o Pressure Sand Filter (PSF) o Activated Carbon Filter (ACF) o UV system

The clear supernatant from the Secondary clarifier will be collected in a Filter feed tank this tank will be provided with level switch for unmanned operations. The treated sewage will be pumped to MGF followed by ACF. After ACF treated sewage will be passed through UV filtration for disinfection. After UV filtration treated sewage will be collected in Treated Water Tank.

The treated effluent will be of suitable quality for use as flushing, car washing landscape irrigation & fire water tanks. Treated water Characteristics will be as under ;

15

General Standards as per Schedule VI Expected Concn. Parameters of E(P) Rules for (mg/l.) Irrigation of Land 1. pH 5.5 – 9.0 6.5 – 7.5 2. Suspended Solids mg/l., 200.0 mg/l. < 20.0 3. BOD ( 3 days at 270C), mg/l. 100.0 mg/l. < 10.0 4. COD, mg/l. Not Specified < 30.0 5. Oil & Grease, mg/l. 10.0 mg/l. < 2.0

STP SCHEMATIC FLOW DIAGRAM

2.14 Give details of dual plumbing system if treated waste used is used for flushing of toilets or any other use. 184 KLD of treated water from STP will be recycle and reused for toilet flushing by dual plumbing system.

3. VEGETATION

3.1 Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem with it’s unique features, if any) There will not be any kind of threat due to the proposed project on the biodiversity of the area, as the area is identified as residential area as per Master Plan of Govt. of Bihar. The area is predominantly residential in nature (Refer Fig. 1). No sanctuary / forest is situated within 10 km. radius. Neither any rare or endangered species have been recorded in the project influence area (500 m. radius). So considering the type and nature of project and commonly found flora and fauna within the project

16

influenced area, no adverse effects are envisaged on the ecology of the region. List of Flora in the project influence area is enclosed as Annexure – VIII.

3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project) No, the establishment of Proposed Residential Project will not involve clearing or modification of vegetation as there is no vegetation present at the project site and the land use around the project site is residential in nature.

3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale)

In the proposed Residential Building Project trees will be grown to the maximum extent possible in the strip of open land surrounding the buildings. Green belt & landscape will be developed and maintained in 4926.68 Sq. M. area within the project premises. Mostly native species will be planted. Decorative trees and hedges will be provided along pedestrian pathways. Green Belt Plan enclosed as Annexure IX.

4. FAUNA

4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details. No, Proposed project is coming up in an area which is already populated and identified as residential area is Master Plan of Govt. Therefore, there is a very less probability for the displacement or any other effect on the local fauna. List of Fauna in the project influence area is enclosed as Annexure - X

4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

In the proposed Residential Building Project, Green belt & landscaping will be developed and various species are planted to create a clean, healthy and aesthetic environment within the premises. Common native variety of trees and ornamental flowering species will be planted in the green belt. Landscaping can have direct positive impact on the local avifauna, as this will provide shelter to local birds. List of common Avifauna found in the project influence area is enclosed as Annexure – X

4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna

Not Applicable for this Project

17

5. AIR ENVIRONMENT

5.1 Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions)

In the “proposed Residential project of “SAI ENCLAVE”, DG Sets & vehicular traffic movement are the major sources of air pollution. DG sets will be equipped with exhaust muffler with adequate stack height of 3.5 m. above the roof of buildings where DG Set will be installed as per CPCB norms.

Project surroundings are similar in nature and there are no major industries located with 5 Km. radius of the proposed Residential Building Project.

Background Ambient Air Quality of the project site area was monitored at three locations within 500 m. radius of project area on 9th Oct.’ 2018. The average values are as under ; (Test Report enclosed as Annexure - XI ) ;

24 Hrs. Average Limit as per NAAQS Parameters Concn. in µg / m3 Nov.’2009 3 1. Particulate Matter (PM10) 58.3 100 µg / m 3 2. Particulate Matter (PM2.5) 34.8 60 µg / m 3 3. Sulphur Dioxide as SO2 8.9 80 µg / m 3 4. Nitrogen Dioxide as NO2 22.4 80 µg / m

AAQ Monitoring Location at project site is as under ;

18

Current traffic survey data (on 09.10.2018) near project site (at Danapur Khagaul Road) is as under ;

Location of Traffic Study near Project Site

Time (Hrs.) TYPE OF VEHICLE 4 Wheleers 2 Wheelers 3 Wheelers HCV’s & LCV’s 06-07 142 11 46 24 07-08 223 15 84 21 08-09 250 20 76 19 09-10 286 10 102 15 10-11 319 6 140 13 11-12 370 8 131 12 12-13 370 14 108 10 13-14 401 6 119 14 14-15 433 11 136 12 15-16 381 15 116 17 16-17 399 19 133 10 17-18 358 11 136 9 18-19 282 10 125 12 19-20 237 6 116 9 20-21 189 8 104 8 21-22 152 4 88 13 22-23 67 3 45 23 23-24 53 6 20 33 00-01 20 6 4 44

19

Time (Hrs.) TYPE OF VEHICLE 4 Wheleers 2 Wheelers 3 Wheelers HCV’s & LCV’s 01-02 12 1 0 36 02-03 17 1 9 32 03-04 25 5 19 28 04-05 49 6 47 35 05-06 78 10 59 22 TOTAL 5114 213 1964 471

Due to proposed Residential Building Project there will be increment in traffic density in the project area. Incremental Traffic Scenario will be as under ;

Present Increment in Traffic Load due to Type of Vehicle Scenario Proposed Residential Building Project HTV (Trucks, Tractors etc.) 471 5 MTV (Car & Jeeps) 1964 792 LTV (Two & Three Wheelers) 5327 792

Existing Pollution Load (based on CPCB Document CUPS/10/1982-83) due to traffic density of project area is as under;

Total No. of Pollution Load (Kg./Day) Type of vehicle vehicles / Day CO HC NO2 SO2 SPM HTV (Trucks, Tractors etc.) 471 6.0 0.99 9.9 0.71 0.35 MTV (Diesel based 4 Wheelers) 589 0.648 0.165 0.583 0.230 0.265 MTV (Petrol based 4 Wheelers) 1375 55.0 8.25 4.40 0.1100 0.454 LTV (2 & 3 Wheelers) 5327 90.6 53.3 0.373 0.1065 1.065 TOTAL 152.2 62.7 15.2 1.15 2.14

Incremental Pollution Load (based on CPCB Document CUPS/10/1982-83) due to movement of vehicles during Operation Stage of proposed Residential Building Project will be as under;

Total No. of Pollution Load (Kg./Day) Type of vehicle vehicles / Day CO HC NO2 SO2 SPM HTV (Trucks, Tractors etc.) 476 6.0 1.00 10.0 0.71 0.36 MTV (Diesel based 4 Wheelers) 827 0.910 0.232 0.819 0.323 0.372 MTV (Petrol based 4 Wheelers) 1929 77.2 11.57 6.17 0.1543 0.637 LTV (2 & 3 Wheelers) 6119 104.0 61.2 0.428 0.1224 1.224 TOTAL 188.1 74.0 17.4 1.31 2.59

5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters.

20

During construction period major sources of dust & smoke are Vehicular movement & construction activities. To mitigate these effects regular water sprinkling will be done all around the construction area and building materials will be stored in covered area by way of covering them with tarpaulin or keeping them in temporary makeshift sheds.

During Operation stage of proposed Residential Buildings, Dust & smoke will be emitted due to operation of DG Sets & vehicular traffic movement which will be minimized and controlled through in-built exhaust muffler & acoustic enclosures in DG Sets & regular water spraying all around the premises.

4926.68 Sq. M. Green Belt will be developed & maintained within the proposed Residential Project Premises. Regular Water Spraying will be done all around the project premises to minimize dust emissions.

Meteorological Condition (Source IMD Data) of Project area is as under ;

The temperature variations in the study area are as under :

Period Minm. Temperature Maxm. Temperature Mar. – June 15 0C – 22 0C 32 0C – 44 0C Jul. – Oct. 16 0C – 18 0C 30 0C – 38 0C Nov.- Feb. 5 0C – 11 0C 15 0C – 24 0C

Rainfall in Study Area :

Year Rainfall in mm. 2013 916.8 2014 1070.4 2015 590.6 2016 994.8 2017 722.8 Average Rainfall 858.96 mm. Source : imd.gov.in

Wind Direction and Velocity :

Season Direction Maximum Velocity Mar. – June SE to SW 5 – 30 km/hr Jul. – Oct. NE to SW 2 – 25 km/hr Nov.- Feb. NW to SE 1 22 km/hr –

21

Wind rose is as under;

Incremental Air Pollution (PM) Load Due to proposed Residential Building Project ;

22

Incremental Air Pollution (SO2) Load Due to proposed Residential Building Project ;

Incremental Air Pollution (NO2) Load Due to proposed Residential Building Project ;

23

5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

As per MoEFCC guidelines, 1 ECS for every 2 tenements having built-up area 101 to 200 m2 (Refer : Manual on norms and standards for environment clearance of large construction projects, by MoEF, Govt. of India, Annex 3.1) parking is required.

However in the SAI Enclave building project 7840 Sq. M area has been provided as covered parking and 8042 Sq. M. is open parking space with multilevel parking facility. Total parking area of 23924 Sq. M. area is allocated. Parking provisions have been made for 792 ECS for residents and 119 ECS for visitors.

Present level of transport infrastructure around the Danapur Khagaul Road at East front of Project Site. Parking Plan & Traffic Movement plan enclosed as Annexure – XII. 5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category. Keeping a long-term perspective and movement of traffic (cars and two-wheelers predominantly), internal roads has been planned in the proposed residential building project. Arrangement for Streetlights will be provided all along the roads and junctions.

5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above. There will be marginal increase in traffic noise & vibrations due to proposed residential building project as the project site is located in well developed area with heavy traffic density. Present Background Ambient Noise Level Data is enclosed as Annexure XIII.

Noise level will be minimized through development of green belt all around the project premises. 5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details. Noise will be generated by DG sets when they are operating, operation of compressors and water pumps.

It shall be ensured that the DG sets to be installed shall comply Notification No. G.S.R. 371(E), dt: 17th May’2002 for emission limits for new diesel engines (> 1000 KVA) for genset applications, issued by Ministry of Environment & Forests, Govt. of India. As per this notification, the acoustic enclosure for new DG Sets with rated capacity more than 1000 KVA, manufactured on or after the 01st Jul.’2003 shall have an insertion loss of 25 dB(A).

The DG Set will have an acoustic enclosure and an exhaust muffler, which will ensure a minimum of 25 dB(A) insertion loss. The design is in such a manner that within the proposed Residential premises the noise level will be limited to 50-55 dB(A). This criterion is also essential from occupants & visitors comfort point of view.

Plantation and landscaping will be designed to ensure that there will be green belt all around

24

the project premises so that further noise attenuation is achieved.

Overall design of facilities, equipment, layout and landscaping is done with a view to maintain noise level within Ambient Noise Level standards for Residential Areas.

6. AESTHETICS

6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents? No, The maximum height of the residential buildings are 33 m. only from G.L. Adequate open spaces according to the municipal building rules are being provided. 6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?

There will be not any adverse impact of this project on existing structures as all other existing structures are similar in nature. 6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out. There is no local urban design criteria which require to be considered. 6.4 Are there any anthropological or archaeological sites or artefacts nearby? State if any other significant features in the vicinity of the proposed site have been considered. No there are no such structures within 5 km. radius of the project area. 7. SOCIO-ECONOMIC ASPECTS

7.1 Will the proposal result in any changes to the demographic structure of local population? Provide the details. Yes, the proposed Residential Building Project will definitely change the demographic structure of the area as 3960 nos. of people will reside in 792 nos. flats. Number of people will reside in the area due to establishment of Corporate Tower and many offices.

Demographic Pattern of Area is enclosed as Annexure – XIV.

7.2 Give details of the existing social infrastructure around the proposed project. The proposed project is located in a developing residential area. The area is well connected with roads to all the important places of city. However, all the basic needs & amenities are available within the 1 – 5 Km. radius of the project site.

Jalalpur (2.10 km.), Dhanaut (2.75 km.), Rukunpura Khagaul Road (1.5 Km.), Devi West Temple (1.5 Km), Danapur Khagaul Road (100 m.) East Jamsaut (50 m.), Residential Area, Danapur Naubatpur Road (3 Km) North Danapur (2.25 Km.), Mainpura (1000 m.), Saguna More (2.75 Km), South Danapur Railway Station (1.75 Km.), Rampur (600 m.), Khagaul (2 Km.)

25

All social infrastructure facilities i.e. Hospitals, Clinics, Banks, Post Offices, Commercial shops etc. exists within 500 – 1000 m. of proposed project area.

7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed? No, the proposed residential project will not cause any adverse effects on local communities, disturbance to sacred sites or other cultural values. Rather, it will provide shelter to 3960 nos. of dwellers. “SAI ENCLAVE” project will also generate indirect employment opportunities in the form of retail shops, security guards, servants, helpers, cleaners, washermans, electrician etc.

8. BUILDING MATERIALS

8.1 May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency)

All building materials to be used in the construction of proposed Residential Building project are of high embodied energy content. (Aluminium 200-250 Gj/tonne, Steel 30-60 Gj/Tonne, Glass 12-25 Gj/Tonne, Cement 5-8 Gj/Tonne, Lime 3-5 Gj/Tonne).

As energy conservation measures sun dried pavers will be used for making paved path, instead of baked pavers as they are manufactured from energy efficient processes. Non toxic Paints and Fly ash products may be used as per availability in the region.

8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts? Noise during the construction phase is expected due to operation of construction equipment, material and vehicular movement. The expected noise levels will be in the range of about 60 – 70 dB(A), though close to the construction site. Construction equipment and vehicles will be provided with mufflers and silencers thereby reducing the noise levels. Also, no major noise generating activity will be carried out during night to maintain the ambient noise standards.

All building materials carrying vehicles will be covered with tarpaulin or polythene sheets to avoid spreading of dust and dirt. Separate raw material handling yard will be made. Cement will be separately stored under cover bales. Sand will be stacked neatly under tarpaulin cover. All material transportation will be done during the off peak hours only. Raw material handling yard will be located within the project site and separated by enclosures.

In order to minimize impact on traffic congestion due to construction activities of the projects, all construction vehicles will be instructed to ply during off-peak hours. It shall also be ensured that vehicles being allowed within the construction site and for the construction activity shall meet the vehicular pollution regulation (PUC).

8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?

26

Recycled materials from outside may be used in roads and land development activities. These materials will be used as fillers in base and sub-base of the carriageway, footpaths pavements or pedestrian way.

Depending upon the situation 5 to 10% savings may be achieved by using recycled materials.

8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project. The collection, transportation and disposal of the solid waste generated during the operation phase of the proposed Residential Building project will be done as per the Municipal Solid Wastes (Management & Handling) Rules, 2016 (MSW Rules).

During operational phase approx. 1432 Kg/day solid waste will be generated from proposed residential building project in the form of Kitchen waste & other domestic waste. (@ 0.15 to 0.36 Kg per capita).

These generated solid wastes will be first segregated as plastic, glass, paper and other waste separately and disposed off as per MSW Rule, 2016. The plastic, glass and paper waste may be collected by private vendors for recycling. Sludge generated from STP (after drying) will be filled in HDPE bags and used as manure for gardening purpose.

All biodegradable and non-biodegradable waste will be handled as per Municipal Solid Waste (Management and Handling) Rule, 2016. Waste from biodegradable bins will be reutilized in bio-composting to prepare organic manure. Non bio-degradable waste will be disposed off through

Three-bin system will be adopted. Storage facilities will be created and established by taking into account quantities of waste generation in a given area and the population densities. Different coloured bins for different categories of wastes will be provided.

Three colour of wheeled bins in each building: - Dark grey for non-recyclable waste, Green for kitchen food/ compostable garden waste and Blue for paper.

In addition, boxes will be provided for the collection of other recyclable materials; a green box is used for paper and a black box is used for cans and plastic collections.

Following measures will be adopted for safe disposal and management of solid wastes from the proposed project ;

a. Waste from biodegradable bins will be reutilized in bio-composting to prepare organic manure. b. The dried STP Sludge will be used as manure for gardening c. Waste oil generated from DG Set / Other machinery overhauling and waste transformer oil will be sold off to CPCB / BSPCB authorized vendors for waste oil. d. Old newspapers & other paper waste and used empty bottles will be sold off to authorized scrap dealers. e. All the non bio-degradable waste disposal will be done through Khagaul Nagar Parishad waste collection system or other authorized vendors.

The used Spent Oil from DG sets would be carefully stored in HDPE drums in isolated covered facility and disposed off through CPCB/BSPCB authorized recyclers as per guidelines of Hazardous and Other Wastes (Management and Transboundary Movement) Rules ‘2016.

27

9. ENERGY CONSERVATION

9.1 Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption? Power requirement : 4000 KW through BSEB Grid Source of Supply : BSEB Back-up Source : 7 Nos. 125 KVA DG Set Energy Consumption per Sq. Ft. Built-up Area: 5.11 Watt/Sq. Ft.

Measures for minimizing energy consumption ;

. Outer walls will be properly insulated to reduce heat load . Provisions for using Solar power for landscape, corridors & pathways lighting. . Capacitors system to improve the load power factor . LED lamp fitting will be used. . Roof Top Thermal Insulation will be provided . Buildings will be designed to more daylight integration. . The electrical installations are designed to comply with the regulations and practices and under stipulation of Pollution Control Authorities. They are based on the recommendation of the Indian National electrical code & Electrical Installation Standards.

9.2 What type of, and capacity of, power back-up to you plan to provide? There will be 7 Nos. DG Sets of 125 KVA set to meet emergency power load. Solar panels will also be provided to meet the emergency lighting purposes.

9.3 What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation? In the proposed Building project clear & tinted glass will be used having U-Value of 2.9 W/m2K

9.4 What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project. Passive solar design refers to use of the sun’s energy for the heating and cooling purposes. Pergolas, projections, façade elements, metal louvers will be provided for sun shading to reduce the heat influx into the building and thus reduce the air conditioning loads.

Moreover, Solar energy will be used for meeting the requirement of hot water & landscape and street lighting purposes within the proposed building premises.

9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.

28

Proposed Buildings are designed in a way so that direct radiations can be received during day hours which are specific to the orientation. Solar energy will be utilized to meet various energy requirements.

Street lights, Green Belt & Landscape lights will be solar powered. The on/off control of external lighting will be through automatic time based timers.

Provisions have been made for Solar street lights, Solar blinkers, Solar power packs/inverters, Roof top SPV (Solar Photo voltaic) systems.

9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

Shadings provided to reduce cooling loads. Green area and open areas will be spaced in a way to achieve reduction in temperature. 9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications.

The space heating load will be minimized by using passive solar structures and suitable building envelope material. LED will be used in all common areas. The façade lighting and external lighting shall be controlled by timer clock. There will be on/off control of external lighting through automated timer based systems.

. The glass area to be covered with curtain / Venetian blinds / sun film . The roof has been considered as insulated with 50 mm thick insulation, also under deck insulation of the roof is suggested. . The main entrances shall have air Curtains.

The system design for all material equipments shall in general comply with the standards, codes and statutory regulations issued by the relevant authorities.

Integrated building management system (IBMS) will enable automation and effective operation of building and facilities. The IBMS can integrate energy management system, Electrical distribution system, lifts, CCTV system, fire alarm system and others.

The system design for all material equipments shall in general comply with the standards, codes and statutory regulations issued by the relevant authorities.

9.8 What are the likely effects of the building activity in altering the micro-climates? Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?

29

The proposed project is Building project due to which there will be insignificant emission of air pollutants by vehicular movements and occasional use of DG sets, therefore no heat island effect is envisaged, as the area is similar to proposed structures. Increased traffic generation and occasional use of DG sets used due to project is not going to cause significant increase in atmospheric concentration of gases and will not result in heat island formation and inversion effects. Grass pavers may be provided to avoid heat island effects.

9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R values of the individual components. The structural design of proposed Residential Building Project will reduce heating loads as major part is of brick wall with plaster and paint finish. The U-factors & R values of the individual components are as under ; - Roof Assembly – R Value : 2.1 sqm. 0C/W; U-factor : 0.409 W/sqm. 0C - Opaque Walls Assembly – R Value : 2.35 sqm. 0C/W ; U-factor : 0.352 W/sqm. 0C - Vertical Fenestration : U-factor : 3.177 W/sqm. 0C ; SHGC : 0.25 9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans. In the proposed Residential Building Project following considerations have been taken for Fire Fighting arrangements ; i. Hydrant & Sprinkler system will be common ii. Sprinkler system will fed from the Hydrant riser and being the residential complex, sprinkler system will be restricted only in the basement and parking areas. iii. Single Jockey pump will be used to maintain the pressure on hydrant system. iv. Electrically operated hydrant pump to be used under the DG Supply only and not under the grid supply. v. Electrical load for jockey pump only to be considered under the grid supply. vi. Another diesel operated pump of same capacity to be kept as stand by.

Recommendation by the State Fire Office will be followed during the operational phase of the project. The following provisions will be made for combating fire hazards;

a. Underground Fire Water Tank & Pump Room b. Hydrant System & Wet Riser Piping c. Automatic Smoke Detectors d. Automatic Sprinkler System e. Fire Alarm System f. Portable CO2 Fire Extinguishers.

Moreover, Emergency Evacuation Plan will be displayed at all strategic locations within the propo Residential Building Premises.

Emergency Evacuation Plan is enclosed as Annexure – XV.

9.11 If you are using glass as wall material provides details and specifications including emissivity and thermal characteristics.

30

The proposed project is a Residential Building Complex and no glass will be used as wall materials within the proposed residential premises.

9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration. In the proposed Residential Project premises prime importance is given to the natural wind circulation and illumination aspect. Keeping that in mind open terraces, cutouts, larger open able windows and the inter-block spaces have been proposed so that air infiltration through all the spaces is maximum. However, due to close proximity to River Ganga favorable wind will be received all around the year.

9.13 To what extent the non-conventional energy technologies are utilized in the overall energy consumption? Provide details of the renewable energy technologies used. In order to conserve electrical energy, it is proposed to utilize solar energy for staircase lightings. The landing and mid-landing of all the staircases shall be provided with 12 hours back-up solar power lighting. All light fittings shall be provided with electronic ballast. Solar Power will be utilized for ;

 Street lights  Solar power packs/inverters  Green Belt & landscape lighting

31