To: & Malling Joint Transportation Board

By: KCC Highways and Transportation

Date: 10th June 2013

Subject : Highway Works Programme 2013/14

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction in 2013/14

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2013/14

Footway and Carriageway Improvement Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Traffic Systems – see Appendix D

Bridge Works – see Appendix E

Conclusion

1. This report is for Members information.

Contact Officers:

The following contact officers can be contacted on 0845 8247 800

Carol Valentine Highway Manager (West) Mark Simmons District Manager Sue Kinsella Street Lighting Manager Neil Tree Carriageway Surface Treatment Russell Boorman Carriageway Machine Surfacing Wendy Bousted Footway Improvement Team Leader Katie Lewis Drainage Manager Toby Butler Intelligent Transport Systems Manager Tony Ambrose Structures Manager

Appendix A – Footway and Carriageway Improvement Schemes

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.

Surface Treatments - Contact Officer Mr Neil Tree

Micro Asphalt Schemes Road Name Parish Extent of Works Current Status

Clare Lane East Malling From its junction with Mill Works Completed Street to its junction with Lucks Hill Mill Street East Malling Whole length Works Completed

Dryland Road Whole length Works Completed

Plaxdale Green Road Stansted From its junction with Works Completed Parsons Lane to its junction with A20 The Freehold Whole length Works Completed

Rochester Road From its junction with Works Completed Knowle Road to its junction with Scarborough Terrace Western Road Whole length Works Completed

Deakins Lea Tonbridge Whole length Works Completed

Shipbourne Road Tonbridge From its junction with Works Completed Higham lane to its junction with Willow Lea Sandy Lane Addington Ford Lane to St Vincents To be Programmed Lane

A227 Road Tonbridge Welland Road to The Works Completed Ridgeway

Plaxtol Lane A227 Tonbridge Rd to The Works Completed Street

Beltring Road East Peckham Road to Programmed to start Halt 15 th May 2013 for one day Church Road Offham A20 London Rd to Church Works Completed Farm Pilgrims Way Wouldham Knowle Rd to Boundary Works Completed

Surface Dressing Schemes – Contact Officer Mr Neil Tree

Road Name Parish Extent of Works Current Status

A227 Rd Shipbourne Plaxtol Lane to Springhill Programmed to start Cottages 18 th May 2013 for one day Quarry Hill Rd Borough Green Conyerd Rd to Basted Lane Programmed to start 18th May 2013 for one day Fartherwell Road Teston Rd to Sandy Lane Programmed to start 21st May 2013 for one day Sandy Lane A20 London Rd to Programmed to start Fartherwell Rd 19th May 2013 for one day Hatham Green Lane Stansted Ash Lane to Plaxdale Programmed to start Green Rd 19th May 2013 for one day Old Church Road Court Rd to Water Programmed to start Treatment 19th May 2013 for one day Tumblefield Stansted Plaxdale Green Rd to Programmed to start Hill Rd 19th May 2013 for one day Kemsing Road Wrotham Borough Green Rd to New Programmed to start House Farm 18th May 2013 for two days B245 London Rd Morley’s Cafe to Nizels Programmed to start Lane 16th May 2013 for one day A26 Tonbridge Rd A228 Rdbt to Bull Farm Programmed to start Cottages 16th May 2013 for one day Ladds Lane Snodland Manley Boulevard to Old Programmed to start Quarry 22nd May 2013 for one day Leigh Rd Hildenborough Stock Green Rd to Programmed to start Meopham Bank Farm 16th May 2013 for one day A20 London Road Ryarsh Rd to Roughetts Programmed to start Rd 20th May 2013 for two days Carpenters Lane Water Slippe to Common Programmed to start Rd 18th May 2013 for one day A20 London Road Addington Seven Mile Lane to Aldon Programmed to start Lane 19th May 2013 for two days A20 London Road Trottiscliffe Hernewell Farm to Programmed to start Trottiscliffe Rd 20th May 2013 for one day Seven Mile Lane East Peckham A26 Maidstone Rd to Programmed to start B2015 Maidstone Rd 16th May 2013 for two days Pratling St Rochester Road to No 256 Programmed to start 22nd May 2013 for one day Way Leybourne Park Rd Rdbt to Ashton Programmed to start Way 21st May 2013 for one day Castle Way Leybourne M20 j/w to Pump Close Programmed to start 21st May 2013 for two days

Machine Resurfacing – Contact Officer Mr Russell Boorman

Road Name Parish Extent of Works Current Status

Seven Mile Lane (3 Offham From outside Viking Oak Completed Sections) Kennels to its junction Orchard Place Business Centre East Street (North) Addington Whole length Completed

A228 - 2 roundabouts at East Peckham At its junction with Part complete due to the end of Boyle Way Branbridges Road and Health & Safety Seven Mile Lane Issues. To be re-programmed.

Bradbourne Lane Ditton From its junction with Completed London Road to its junction with St. Peter's Road B245 Tonbridge Rd Hildenborough From its junction with Completed Orchard Lea to the BP garage Quarry Hill Road Tonbridge A21 Flyover Completed

To be programmed Hall Road Aylesford At its junction with Station for Summer/Autumn Road 2013

High Street Tonbridge Approach to Vale Road To be programmed Roundabout for Summer/Autumn 2013

High Street Tonbridge At its junction with Medway To be programmed Wharf Road for Summer/Autumn 2013 To be programmed Shipbourne Road Hadlow Outside Dene Court for Summer/Autumn 2013 To be programmed A26 Tonbridge Road Hadlow At its junction with Bourne for Summer/Autumn Grange Lane 2013 To be programmed A26 Tonbridge Road Hadlow At its junction with for Summer/Autumn Blackmans Lane 2013 From its junction with To be programmed Dry Hill Park Road Tonbridge London Road to its junction for Summer/Autumn with Shipbourne Road 2013 To be programmed Snodland Bypass Snodland Ham Hill Roundabout for Summer/Autumn Roundabout 2013

Footway Improvement - Contact Officer Mrs Wendy Boustead

Road Name Parish Extent and Description of Cu rrent Status Works High Street Tonbridge The rear of bus stops in Programmed to start front of the castle – week commencing Replacing existing stone 7th May and due to flag paving with a new clay complete by 31 st paver to match existing May 2013 Appendix B – Drainage Repairs & Improvements

Drainage Repairs & Improvements - Contact Officer Katie Lewis

Road Name Parish Description of Works Current Status Riding Lane Tonbridge Culvert replacement Scheme identified and being designed

Hall Road Aylesford Soakaway replacement Scheme identified and being designed

London Road Aylesford Soakaway replacement Scheme identified and being designed

Appendix C – Street Lighting

These columns in Tonbridge High Street will be replaced early in the next financial year:

Street Lighting Column Replacement – Contact Officer Sue Kinsella

Column Road Name Location Status Ref High Street JHBR001 O/S 4 Programmed for June 2013

High Street JHBR002 O/S 1a Programmed for June 2013

High Street JHBR003 O/S 12a/14 Programmed for June 2013

High Street JHBR004 O/S 9 Programmed for June 2013

High Street JHBR005 O/S 26/28 Programmed for June 2013

High Street JHBR006 O/S 34/34a Programmed for June 2013

High Street JHBR007 O/S 21/23 Programmed for June 2013

High Street JHBR008 O/S ANGEL WALK Programmed for June 2013

High Street JHBR009 O/S 54/58 Programmed for June 2013

High Street JHBR010 O/S 39 Programmed for June 2013 High Street JHBR013 O/S 62/64 Programmed for June 2013

High Street JHBR014 O/S 47 Programmed for June 2013

High Street JHBR015 O/S 66/68 Programmed for June 2013

High Street JHBR016 O/S 59 Programmed for June 2013

High Street JHBR017 O/S 82/82a Programmed for June 2013

High Street JHBR018 O/S 69/71 Programmed for June 2013

High Street JHBR019 O/S 73 Programmed for June 2013

High Street JHBR020 O/S 92a Programmed for June 2013

High Street JHBR021 O/S 85/87 Programmed for June 2013

High Street JHBR022 O/S 96/98 Programmed for June 2013

High Street JHBR023 O/S THE CASTLE PH Programmed for June 2013

Railway Approach JRCT001 J/W BARDEN ROAD Programmed for June 2013

Railway Approach JRCT002 OPPS 4 Programmed for June 2013

Railway Approach JRCT003 ADJ 8 LHS Programmed for June 2013

Railway Approach JRCT004 OPPS STATION RHS Programmed for June 2013

Railway Approach JRCT005 OPPS STATION LHS Programmed for June 2013

Quarry Hill Road JQAK001 J/W WATERLOO Programmed for June 2013 ROAD LHS Quarry Hill Road JQAK002 OPPS J/W PRIORY Programmed for June 2013 ROAD Quarry Hill Road JQAK003 O/S 13 Programmed for June 2013

Quarry Hill Road JQAK004 O/S 6/7 QUARRY Programmed for June 2013 HILL PARADE Quarry Hill Road JQAK005 J/W PEMBURY ROAD Programmed for June 2013 ROUNDABOUT Quarry Hill Road JQAK006 O/S 11 QUARRY HILL Programmed for June 2013 PARADE

These columns are being replaced as part of ongoing maintenance and improvement programme:

Street Lighting Column Replacement – Contact Officer Sue Kinsella

Column Road Name Location Status Ref Elm Lane JEAX001 ON ELM COTTAGE Replacement by end of June 2013 Road JFAW002 O/S 91/93 Replacement by end of May LANE 2013 Hallsfield road JHAK502 J/W Replacement by end of May WOODS 2013 London Road JLCL006 OPP OAKDENE CAFÉ Replacement by end of June 2013 London Road JLCH001 ADJ 85A Replacement by end of May 2013 Lucas Road JLDW006 OPP 45 Replacement by end of June 2013 Lunsford Lane JLDD539 J/W LEYBOURNE Replacement by end of May WAY 2013 Malling Road JMAQ036 O/S 66 SHOP Replacement by end of May 2013 Oak Drive JOAB001 O/S 2/4 Replacement by end of June 2013 Pembury Road JPAT002 OPP J/W ST MARYS Replacement by end of May ROAD 2013 Quincewood Gardens JQAI004 OPP 11 Replacement by end of May 2013 Raeburn Close JRAA002 O/S 14 Replacement by end of May 2013 Railway Approach JRCT001 J/W BARDEN ROAD Replacement by end of June 2013 The Ridgeway JTBW010 O/S 36/38 Replacement by end of May 2013 The Stream JTCA001 O/S 2 Replacement by end of June 2013 The Stream JTCA002 O/S 4/6 Replacement by end of June 2013 Tudeley Lane JTDW001 ADJ 19/25 Scheme Works – Due to be completed by end of June 2013. Tudeley Lane JTDW002 ADJ 35/41 Scheme Works – Due to be completed by end of June 2013. Tudeley Lane JTDW004 ADJ 67/73 Scheme Works – Due to be completed by end of June 2013. Whistler Road JWBD010 O/S 51 Replacement by end of May 2013

Appendix D – Traffic Systems

There is a programme of scheduled maintenance to refurbish life expired traffic signal equipment across the county based upon age and fault history. The delivery of these schemes is dependent upon school terms and holiday periods; local residents, businesses and schools will be informed verbally and by a letter drop of the exact dates when known.

Traffic Systems - Contact Officer: Toby Butler

Location Description of Works Current Status A227 Shipbourne Road near White Cottage Refurbishment of traffic To be programmed Road, Tonbridge signal controlled crossing. 2013/14 - will require two weeks to complete.

Appendix E – Bridge Works

Bridge Works – Contact Officer Tony Ambrose

Road Name Parish Description of Works Current Status High Street in Tonbridge Repainting of Great Bridge Works to commence Tonbridge in June 2013 for 8 weeks. Pierce Mill East Peckham Bridge - Works to commence Lane Replacement of a weak bridge in late May 2013 for deck. 12 weeks.

1.1 Legal Implications

1.1.1 Not applicable.

1.2 Financial and Value for Money Considerations

1.2.1 Not applicable.

1.3 Risk Assessment

1.3.1 Not applicable.

Contact: Carol Valentine / Mark Simmons 08458 247 800