Roadworks & events report

Effective from 11th September 2020

For further information please contact the following:

Edinburgh and contact CLARENCE on 0800 23 23 23 Key Work suspended or postponed, some restrictions remain in place Traffic Scotland - information on motorways and City Bypass New information in this version Spaces for People measures SE Scotland trunk roads maintained by BEAR Underlined entries contain links to maps or further information Transport for - Lothian Buses and

Follow Edintravel on Twitter for regular updates See details of Ward boundaries

Entries are arranged by Ward and then by start date.

Planned roadworks and events affecting major routes have been approved by the Citywide Traffic Management Group (a partnership between City of Edinburgh Council Transport Officers, Locality teams, Lothian Buses and Police Scotland.) = temporary traffic lights in use = diversion in operation

Ward Street Location Description Traffic Control Start date Finish date CALA / Barratt Homes development - construction Various lane closures / contraflow arrangements. of site entrance, installation of new pedestrian Almond ROAD Between and Barnton Speed limit reduced to 30mph along whole length between Barnton and 08/01/20 TBC crossing points and redetermination of west Maybury junctions footway. Between Parkway and City of Edinburgh Council - to provide space for Until further Almond SILVERKNOWES ROAD Road closed to all vehicles except cycles 30/04/20 Marine Drive safe walking and cycling notice City of Edinburgh Council - to provide space for Until further Almond WALK Road closed except for residents' access, pedestrians and cycles 08/05/20 safe walking and cycling notice Between Craigs Road and roundabout at City of Edinburgh Council - to provide space for Until further Almond MAYBURY ROAD New temporary pedestrian crossing in operation 30/06/20 Maybury Drive safe walking and cycling notice Until further Almond HAWES PIER Police Scotland initiative Car park closed 10pm - 5am each night 10/07/20 notice Telecoms company - installation of new phone Almond AVENUE At Pennywell Road Road closed 31/08/20 04/09/20 mast (TBC as at 04/08/20) *postponed* City of Edinburgh Council - carriageway surface Almond BO'NESS ROAD In its entirety Stop / Go boards, parking restrictions as signed 09/09/20 11/09/20 treatment programme City of Edinburgh Council - carriageway surface Almond MUIRHOUSE PARKWAY Lane closures and parking restrictions as signed 12/09/20 14/09/20 treatment programme

Almond At Groathill Road North BT / Morrison Utility Services - remedial repairs 3-way temporary traffic lights 13/09/20 13/09/20

Almond STATION ROAD At RBS goods entrance BT / KN - cabling *postponed* Temporary traffic lights 14/09/20 14/09/20

City of Edinburgh Council - installation of Spaces Almond PENNYWELL ROAD In its entirety Lane and parking restrictions as signed 14/09/20 02/10/20 for People measures

Almond GLASGOW ROAD Between RBS bridge and Gogar off-slip Telecoms company - trial holes Off-peak citybound lane closure 16/09/20 16/09/20

Network Rail - bridge inspection Almond CLIFTONHALL ROAD At rail bridge closest to M8 overbridge Road closed 10pm - 6am 16/09/20 17/09/20 (TBC as at 11/09/20)

Varying lane closures and contraflow arrangements. St James' Place, STREET / PICARDY City Centre St James redevelopment works. Cathedral Lane and St James' car parks closed. Alterations to lane layout 04/01/16 Autumn 2020 AREA on all approaches to Picardy roundabout as work progresses

Between Waverley station access and Unsafe rock face, restrictions in place to provide City Centre CALTON ROAD Temporary traffic lights. Ongoing New Street safety zone Various lane and road closures as signed on-street. Between Hanover Street and Frederick City of Edinburgh Council - public space City Centre ROSE STREET Rose Street and Rose Street North / South Lanes closed as required 06/05/19 October 2020 Street improvements including laying of new setts from 03/08/20 Traffic reduced to one lane in each direction. Footway closures and temporary walkways as signed. Bus stops relocated as required. City Centre NORTH BRIDGE City of Edinburgh Council - bridge refurbishment 15/02/20 Summer 2021 Regular changes to traffic management as work switches between east and west sides and progresses southwards To provide adequate pedestrian space passed the Until further City Centre LEVEN STREET At Valleyfield Street Lane closures / contraflow to accommodate pedestrian walkway 04/06/20 development site at Pacific Building notice Between South St David Street and East City of Edinburgh Council - to provide space for Until further City Centre PRINCES STREET Buses, taxis and cycles only 7.30am - 6.30pm each day 18/06/20 End junction safe walking and cycling notice City of Edinburgh Council - to provide space for Road closed at Princes Street (except for cycles). Taxi and loading Until further City Centre WAVERLEY BRIDGE 18/06/20 safe walking and cycling access via Market Street notice City of Edinburgh Council - to provide space for Until further City Centre FORREST ROAD Installation of segregated cycle lanes 22/06/20 safe walking and cycling notice City of Edinburgh Council - to provide space for Road closed except for cycles and blue badge holders. Until further City Centre COCKBURN STREET 10/07/20 safe walking and cycling Loading permitted 6.30am - 10.30am each day. notice Start dates indicate earliest anticipated start. Finish dates represent formal notice periods - From 11 September 2020 www.edinburgh.gov.uk/edintravel works may finish earlier or be extended. City of Edinburgh Council - to provide space for Road closed except for cycles and blue badge holders. Until further City Centre VICTORIA STREET 10/07/20 safe walking and cycling Loading permitted 6.30am - 10.30am each day. notice BAM Construction - water main connection at City Centre MORRISON STREET Eastbound approach to Semple Street 2 lanes (of 3) closed (alterations to lane layout expected 09/09/20) 27/07/20 w/c 14/09/20 Capital Square development At Leven Street, Home Street. City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further City Centre TOLLCROSS 31/07/20 Brougham Street and Earl Grey Street safe walking and cycling wheelchairs, prams or bicycles to physically distance notice City of Edinburgh Council - trial holes for CCWEL City Centre MELVILLE STREET At Walker Street Minor lane and parking restrictions 03/08/20 21/09/20 project

Laing O'Rourke - footway, cycleway and drainage Road closed to westbound traffic from Conan Doyle pub to Elder Street. works; City of Edinburgh Council - site surveys for Closure extended to North St Andrew Street 8pm - 6am each weeknight 6am City Centre YORK PLACE 17/08/20 CCWEL cycleway (nightshift works); for the first 5 weeks. 12/10/20 Edinburgh Trams - routine track maintenance (nightshift works) Eastbound lane closure 13/09/20 for 3 nights (11pm - 5am) Temporary traffic lights. No access to Dundee Street from East SEMPLE STREET / City of Edinburgh Council - footway and , diversion via Semple Street - Morrison Street - Gardner's City Centre FOUNTAINBRIDGE 19/08/20 End of October carriageway resurfacing, traffic signals upgrade Crescent. JUNCTION Footway on west side of Ponton Street closed Road closed to westbound traffic. Diversion via Pleasance - West Richmond Street - West Nicolson Street - 6am City Centre COWGATE At Candlemaker Row Redevelopment of India Buildings 18 months Potterrow - Teviot Place - Place - Lady Lawson Street - West 24/08/20 Port 06/09/20 06/09/20 City Centre GEORGE STREET St Andrew Square to Hanover Street Crane operations Road closed to westbound traffic and and 13/09/20 13/09/20 City of Edinburgh Council - footway slabbing, City Centre LAURISTON PLACE At Lauriston Gardens Temporary traffic lights, no exit from Lauriston Gardens 09/09/20 11/09/20 replacement of traffic signals cabinet Crane operations for high-level window City Centre EARL GREY STREET Outside Bank of Scotland Southbound lanes 1 and 2 closed 13/09/20 13/09/20 replacement Road closed 8pm - 10pm Sunday 20/09/20 to remove site cabins. Between Old Tolbooth Wynd and City Centre CALTON ROAD Clark Contracts development site Temporary traffic lights from 21/09/20 for power connection. 20/09/20 12/10/20 Lochend Close Road closed 8pm - 10pm Sunday 11/10/20 to reinstall site cabins. City of Edinburgh Council - installation / repair of City Centre SOUTH BRIDGE At Chambers Street 4-way temporary traffic lights, 7pm - 7am 24/09/20 25/09/20 traffic detection loops

Colinton /

Scottish Power - cabling / Between St John's Road and Belgrave 11/09/20 ROAD *Update 11/09/20 - works extended until further Road closed 31/08/20 Road TBC notice, jointing still in progress* Corstorphine / At Broomhall Avenue / 10 days ROAD NORTH Scottish Water - mains upgrade Temporary traffic lights 07/09/20 Murrayfield Parkway TBC 26/02/20 SGN - gas main renewal Corstorphine / Between Clermiston Road and Lane closures / contraflow, temporary pedestrian crossing lights, ST JOHN'S ROAD *work suspended and restrictions lifted 30/03/20* Late October Murrayfield Road Belgrave Road closed Resumes 14/09/20

Lane closures and Road South (Smokey Brae) closed. City of Edinburgh Council - carriageway / Between Jock's Lodge and Northfield From 03/09/20 - 3-way temporary traffic lights at Jock's Lodge junction, PORTOBELLO ROAD resurfacing. 18/02/20 Late October Broadway no right turn from London Road into Willowbrae Road (divert via Work resumes 07/08/20 Terrace), expected for around 6 weeks Craigentinny/ City of Edinburgh Council - repairs / upgrade to Path closed, diversion signed via Holyrood Park Road - Duddingston Low INNOCENT TUNNEL 07/09/20 16/10/20 Duddingston tunnel lighting Road with temporary crossing facility on Holyrood Park Road 3-way temporary traffic lights. Craigentinny/ MOUNTCASTLE DRIVE At Mountcastle Gardens Openreach - network upgrade Lane and parking restrictions also on Mountcastle Place and Mountcastle 07/09/20 18/09/20 Duddingston NORTH Green

Start dates indicate earliest anticipated start. Finish dates represent formal notice periods - From 11 September 2020 www.edinburgh.gov.uk/edintravel works may finish earlier or be extended. Craigentinny/ LONDON ROAD At Meadowbank Terrace BT / KN - manhole repairs (x2) *postponed* 3-way temporary traffic lights 13/09/20 13/09/20 Duddingston Craigentinny/ PORTOBELLO ROAD Scottish Water - ironwork repairs (1 days' work At Telferton 3-way temporary traffic lights 12/09/20 15/09/20 Duddingston (INCHVIEW TERRACE) within date range shown, exact date TBC) Road closed to through traffic between Farrer Grove and Portobello Craigentinny/ FISHWIVES' CAUSEWAY Openreach - network upgrade Road. 14/09/20 25/09/20 Duddingston Temporary traffic lights various locations along Farrer Terrace

Lane closures / contraflow, bus stop closures as signed. North Gyle Terrace closed at Maybury Road. Scottish Power - installation of new cables and Mid Drum Brae / Gyle MAYBURY ROAD At North Gyle Terrace Worksite extended northwards towards Maybury drive from 20/07/20 - 08/06/20 supporting apparatus September contraflow with 2-way traffic on southbound carriageway and Craigs Road closed west of Maybury Road *this section clear as at 31/08/20*

City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Drum Brae / Gyle ST JOHN'S ROAD In its entirety 22/07/20 safe walking and cycling wheelchairs, prams or bicycles to physically distance notice Scottish Power - installation of new cables and Drum Brae / Gyle ROAD At Temporary traffic lights 10/08/20 8-10 weeks supporting apparatus Cityfibre - cable / ducting installation Drum Brae / Gyle DRUM BRAE SOUTH At Duart Crescent 3-way temporary traffic lights 14/09/20 28/09/20 (TBC as at 11/09/20)

Lane closures / contraflow. Drum Brae / Gyle GLASGOW ROAD At North Gyle Road Scottish Water - trial holes 17/09/20 21/09/20 North Gyle Road closed between Glasgow Road and North Gyle Avenue,

Between Crewe Toll Roundabout and City of Edinburgh Council - to provide space for FERRY ROAD Installation of segregated cycle lanes 03/08/20 17/08/20 Row safe walking and cycling Lane and parking restrictions, temporary traffic lights. Forth EAST TRINITY ROAD SGN - gas main renewal 17/08/20 4 weeks York Road closed at East Trinity Road Between Afton Terrace and Boswall Carriageway subsidence due to collapsed sewer Road closed. Estimate Forth GRANTON ROAD 22/08/20 Green (Scottish Water defect) Update 27/08/20 - Boswall Green closed at Granton Road 15/09/20 City of Edinburgh Council - to provide space for Forth WEST GRANTON ROAD At Waterfront Broadway safe walking and cycling 4-way temporary traffic lights 26/08/20 18/09/20 Note revised end date Phase 1 - 2-way temporary traffic lights, Bangholm Place and Clark SGN - gas main renewal Avenue closed; 14/09/20 Forth FERRY ROAD At Clark Road (start date dependant on progress at Granton 26/10/20 Phase 2 - 3-way temporary traffic lights, Bangholm Place closed and 21/09/20 Road) Bangholm Avenue closed at Clark Road

Fountainbridge/ November GILMORE PARK At Dundee Street Building development works - utility connections Road closed, access maintained for pedestrians 16/01/20 2020 Fountainbridge/ At Road / Terrace Lochwynd - safety camera repairs and refresh of ANGLE PARK TERRACE 4-way temporary traffic lights 7pm - 7am 20/09/20 21/09/20 Craiglockhart junction carriageway line markings Fountainbridge/ Road closed. Diversion via Gilmore Place - Polwarth Crescent / Yeaman VIEWFORTH At the canal bridge Mackenzie Construction - bridge repairs 12/10/20 25/10/20 Craiglockhart Place

WATER OF LEITH PATH AT Inverleith Landslip Path closed beneath Dean cemetery April 2013 Ongoing Temporary traffic lights between Portgower Place and Raeburn Street. *work duration extended 30/07/20* Inverleith RAEBURN PLACE SGN - gas main renewal 06/01/20 End of October No vehicle access to Veitch's Court from St Bernard's Row from 18/08/20 for 4-5 weeks. Between St Mark's Park and entrance to City of Edinburgh Council - to provide space for Road closed to through traffic except for cycles. Crematorium and Until further Inverleith ROAD 29/05/20 Warriston allotments safe walking and cycling allotment access via Ferry Road notice City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Inverleith CREWE ROAD SOUTH In its entirety 05/06/20 safe walking and cycling wheelchairs, prams or bicycles to physically distance notice

Start dates indicate earliest anticipated start. Finish dates represent formal notice periods - From 11 September 2020 www.edinburgh.gov.uk/edintravel works may finish earlier or be extended. Path closed, diversion signed via South Groathill Avenue - Telford Road (exit path at Craigleith retail park, rejoin on north side of Telford Road Inverleith NEPN TELFORD PATH At Telford Road bridge City of Edinburgh Council - bridge repairs and vice versa). 06/07/20 18/09/20 Parking suspended on both sides of Groathill Avenue / South Groathill Avenue between Telford Road and Groathill Road South. SGN - essential gas main assessment and 4-way temporary traffic lights Between roundabout and subsequent repair / renewal Road closed, diversion via Carrington Road - East Fettes Avenue - Inverleith CREWE ROAD SOUTH 27/07/20 11/09/20 Carrington Road Comely Bank Road. *All restrictions lifted 11/09/20* Learmonth Avenue closed at Comely Bank Road RAEBURN PLACE / Between Portgower Place and St Stephen City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Inverleith DEANHAUGH STREET / 30/07/20 Street safe walking and cycling wheelchairs, prams or bicycles to physically distance notice KERR STREET Between Deanhaugh Street and City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Inverleith HAMILTON PLACE 30/07/20 Patriothall safe walking and cycling wheelchairs, prams or bicycles to physically distance notice City of Edinburgh Council - upgrade to pedestrian Inverleith COMELY BANK ROAD At Fettes Avenue refuge island Temporary traffic lights 13/08/20 16/08/20 Work postponed, awaiting revised dates Lane closures / contraflow on Queensferry Road, no right turn into Orchard Drive; Inverleith QUEENSFERRY ROAD At Craigleith Drive SGN - gas main renewal Craigleith Drive closed at Queensferry Road; 07/09/20 02/11/20 Blinkbonny Gardens closed at Craigleith Drive; Residents' access only to / from Blinkbonny Avenue 2-way temporary traffic lights. Footways closed (one side at a time) with Inverleith QUEENSFERRY ROAD Dean Bridge City of Edinburgh Council - bridge inspection 07/09/20 11/09/20 temporary crossing points at either end of the bridge 10 days Inverleith INVERLEITH ROW At Royal Botanic Gardens entrance Scottish Water - pipe renewal Temporary traffic lights 11/09/20 TBC LEARMONTH TERRACE SGN - gas main renewal (start date TBC as at Learmonth Terrace closed at Dean Park Crescent; Inverleith 21/09/20 4 weeks AREA 02/09/20) Dean Park Crescent closed to northbound traffic at Queensferry Road SGN - gas main renewal (start date TBC as at Inverleith ARBORETUM ROAD Between Ferry Road and Kinnear Road Road closed 28/09/20 6 weeks 02/09/20)

Road closed between Foot of the Walk and Coatfield Lane.Access maintained from Laurie Street to Kirkgate House car park. East footway Leith CONSTITUTION STREET Trams to Newhaven. closed adjacent to South Leith Parish Church. 16/11/19 30/04/21 Road closed between Queen Charlotte Street and Tower Street and Bernard Street reduced to one lane in each direction.

Leith TOWER STREET West side of Constitution Street Trams to Newhaven - utility diversions Road closed, access via Shore 28/02/20 TBC

Road closed to eastbound traffic, diversion via Melrose Drive. Between North Leith Sands and Trams to Newhaven construction - click cell to visit Leith LINDSAY ROAD Hawthornvale closed at Lindsay Road. No right turn from Annfield, no left 06/03/20 31/07/21 Newhaven Place website turn from Melrose Drive, no exit from Newhaven Place

Leith OCEAN DRIVE Between roundabouts at Ocean Terminal Trams to Newhaven Northbound side closed, 2-way traffic on southbound side. 13/03/20 Autumn 2020

Between Gladstone Place and Links City of Edinburgh Council - to provide space for Until further Leith LINKS GARDENS Road closed to all vehicles except cycles 03/05/20 Gardens Lane safe walking and cycling notice Between Connaught Place and West City of Edinburgh Council - bridge repairs at Leith WATER OF LEITH PATH Path closed 22/06/20 19/09/20 Bowling Green Street Newhaven Road

BALTIC STREET / BERNARD Until further Leith Trams to Newhaven - utility diversions Temporary traffic lights 26/06/20 STREET JUNCTION notice

City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Leith GREAT JUNCTION STREET Between Bangor Road and Leith Walk 28/07/20 safe walking and cycling wheelchairs, prams or bicycles to physically distance. notice QUEEN CHARLOTTE Scottish Power works within Trams to Newhaven Leith At Constitution Street Temporary traffic lights 14/09/20 1 week STREET project Morrison Utility works within Trams to Newhaven Leith OCEAN DRIVE At Tower Place roundabout 4-way temporary traffic lights 14/09/20 16/09/20 project

Start dates indicate earliest anticipated start. Finish dates represent formal notice periods - From 11 September 2020 www.edinburgh.gov.uk/edintravel works may finish earlier or be extended. Leith Walk LEITH WALK Between London Road and Crown Place Trams to Newhaven Road closed to northbound traffic, southbound reduced to 1 lane 20/06/20 Autumn 2021

Leith Walk ANNANDALE STREET At Leith Walk Trams to Newhaven No exit from Annandale Street to Leith Walk 20/06/20 14 weeks

Signal timings and lane markings altered. LONDON ROAD / EASTER Trams to Newhaven - alterations to accommodate Leith Walk No right turn from Easter Road into eastbound London Road (East 20/06/20 Autumn 2021 ROAD JUNCTION Leith Walk diverted traffic Norton Place) Until further Leith Walk MCDONALD ROAD At Leith Walk Trams to Newhaven Road closed 11/07/20 notice Bellevue Road and West Annandale Street closed. City of Edinburgh Council - footway resurfacing, Leith Walk BELLEVUE ROAD AREA Footway closures and parking restrictions as signed on Bellevue Road, 13/07/20 8 weeks drainage and street lighting upgrades West Annandale Street and East Claremont Street

Leith Walk BRUNSWICK STREET At Leith Walk Trams to Newhaven - utility works Road closed 27/08/20 11/09/20

Leith Walk MONTGOMERY STREET Between Leith Walk and Brunswick Street SGN - gas main renewal Lane and parking restrictions 31/08/20 6 weeks

Leith Walk MANDERSTON STREET At Leith Walk SGN - site investigations Road closed 15/09/20 1 week

Narrow lanes for daytime footway works. City of Edinburgh Council - carriageway and Liberton / Between Morrison's supermaket and Walter Scott Avenue closed from 04/09/20 for 2 weeks. ROAD footway resurfacing, traffic signals and street 03/08/20 4 months Gilmerton Walter Scott Avenue Nightshift works from Monday 07/09/20 for 5 nights - 2-way temporary lighting renewal traffic lights between The Pillars and Morrisons junction. Temporary traffic lights at Park Crescent / Mortonhall Park Liberton / MORTONHALL AREA SGN - gas main renewal View; 24/08/20 05/10/20 Gilmerton Mortonhall Park Gardens closed at Frogston Road East Liberton / Scottish Water - multiple ironwork repairs LASSWADE ROAD At Captain's Road 4-way temporary traffic lights 30/08/20 30/08/20 Gilmerton Not carried out, to be rescheduled Liberton / City of Edinburgh Council - kerbing and footway MOREDUNVALE ROAD At Gilmerton Road Road closed 07/09/20 11/09/20 Gilmerton works as part of Gilmerton Road upgrade project Liberton / DRUM STREET At Ravenscroft Street Scottish Water - repairs to burst main Temporary traffic lights *work complete 11/09/20* 08/09/20 TBC Gilmerton Liberton / HYVOT PARK At Gilmerton Dykes Street Scottish Water - repairs to burst main Road closed, diversion via Dykes Road 10/09/20 TBC Gilmerton Liberton / Between Carnbee Avenue and Lockerby Cityfibre - cable / ducting installation LASSWADE ROAD Temporary traffic lights 14/09/20 28/09/20 Gilmerton Cottages (TBC as at 11/09/20) Liberton / GILMERTON DYKES Between junctions with Gilmerton Dykes City of Edinburgh Council - pedestrian refuge Contraflow 16/09/20 24/09/20 Gilmerton STREET Crescent island upgrade Liberton / DRUM STREET At East Farm of Gilmerton BT / KN - installation of cable ducting 3-way temporary traffic lights 19/09/20 20/09/20 Gilmerton

Between Old Dalkeith Road and Scottish Power - making good temporary road Midlothian THE WISP Temporary traffic lights 07/09/20 18/09/20 Edmonstone Road reinstatement

Midlothian RULLION ROAD, PENICUIK Midlothian Council - carriageway resurfacing Road closed in sections 14/09/20 4 weeks

Midlothian SEAFIELD ROAD, BISLTON Scottish Power - cable installation Road closed in sections 21/09/20 7 weeks

Various locations between Cluny Drive City of Edinburgh Council - footway repairs, new Lane closures, temporary traffic lights as required. Morningside BRAID ROAD and Buckstone Drive (working north to pedestrian refuge islands, improvements to street 13/01/20 TBC Riselaw Crescent closed at Braid Road 07/09/20 - 11/09/20 south) lighting, street signage and road markings Between Woodburn Terrace and Morningside CANAAN LANE To facilitate safe egress for construction traffic One-way order suspended 24/02/20 23/08/21 Morningside Road Phased road closures - Albert Terrace, Abbotsford Park and Morningside SGN - gas main renewal Morningside ABBOTSFORD AREA Place and Road between Napier Road and Avenue 09/03/20 11/04/20 *work suspended* (anticipated 02/04/20 for 4 days) Start dates indicate earliest anticipated start. Finish dates represent formal notice periods - From 11 September 2020 www.edinburgh.gov.uk/edintravel works may finish earlier or be extended. Between Braid Farm Road and Hermitage City of Edinburgh Council - to provide space for Until further Morningside BRAID ROAD Road closed except for cycles and essential works vehicles 03/05/20 Drive safe walking and cycling notice With the exception of cycles - From its junction with Road to City of Edinburgh Council - to provide space for Until further Morningside BRAIDBURN TERRACE Road open to eastbound traffic only; 08/05/20 its junction with Braid Road safe walking and cycling notice No right turn from Greenbank Place into Braidburn Terrace. City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Morningside MORNINGSIDE ROAD In its entirety 27/07/20 safe walking and cycling wheelchairs, prams or bicycles to physically distance. notice City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Morningside PLACE In its entirety 27/07/20 safe walking and cycling wheelchairs, prams or bicycles to physically distance. notice City of Edinburgh Council - to provide space for Until further Morningside CANAAN LANE Road closed between Morningside Road and Woodburn Terrace safe walking and cycling notice Between Greenbank and Fairmilehead City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Morningside COMISTON ROAD 20/08/20 crossroads safe walking and cycling wheelchairs, prams or bicycles to physically distance. notice Phased road closures of Midmar Gardens, Cluny Drive, Avenue and SGN - gas main renewal 02/03/20 End of Morningside HERMITAGE AREA Gardens, Braid Avenue, Corrennie Gardens, Hermitage Gardens and *work suspended, resumed 24/08/20* 24/08/20 September Terrace, Nile Grove Brunstfield Avenue closed at Bruntsfield Place; BRUNSTFIELD AVENUE, City of Edinburgh Council - to provide space for Until further Morningside Montpelier closed at Montpelier Park. MONTPELIER safe walking and cycling notice Except for cycles and residents' access City of edinburgh Council - installation of Spaces Morningside MORNINGSIDE ROAD At Church Hill Place for People measures 3-way temporary traffic lights 16/09/20 18/09/20 (TBC as at 11/09/20) SGN - gas main renewal, then Between Hermitage Terrace and Braid Morningside CLUNY GARDENS City of Edinburgh Council - carriageway Road closed 21/09/20 2 weeks Road resurfacing

Morningside MORNINGSIDE ROAD At Jordan Lane Scottish Water - manhole repairs 4-way temporary traffic lights 27/09/20 27/09/20

City of Edinburgh Council - carriageway and Pentland Hills PENTLAND AVENUE footway resurfacing. Road closed 23/03/20 17/04/20 *work postponed*

Pentland Hills PARK ROAD Between Baird Road and West Croft SGN - gas main renewal 2/3-way temporary traffic lights 03/08/20 02/10/20

Scottish Water - water main upgrade (continuation LANARK ROAD WEST and Working between Main Street Rolling programme with 2/3/4-way temporary traffic lights. Pentland Hills of work carried out in 2019). 24/08/20 mid November BRIDGE ROAD and Somerville Road Beginning at Main Street / Johnsburn Road roundabout Rescheduled from April 2020 City of Edinburgh Council - carriageway surface Pentland Hills KIRKGATE / HARLAW ROAD Roads closed 15/09/20 17/09/20 treatment programme City of Edinburgh Council - carriageway surface Pentland Hills RICCARTON AVENUE Road closed 23/09/20 23/09/20 treatment programme

Portobello/ Between Sir Harry Lauder Road and Advance Construction - sewer replacement and BAILEYFIELD CRESCENT Road closed 10/09/18 TBC Fishwives' Causeway road realignment Portobello/ Road and footway realignment as part of Taylor ROAD At Pringle Drive 3-way temporary traffic lights TBC Craigmillar Wimpey housing developments Portobello/ STANLEY STREET / HOPE Between Christian Grove and access to City of Edinburgh Council - to provide space for Until further Road closed to through traffic except cycles 29/05/20 Craigmillar PARK Network Rail yard safe walking and cycling notice Portobello/ PORTOBELLO HIGH Between Fishwives' Causeway and City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further 24/07/20 Craigmillar STREET Marlborough Street safe walking and cycling wheelchairs, prams or bicycles to physically distance. notice Portobello/ At and extending into Niddrie Marischal Cityfibre - installation of fibreoptic cables and GREENDYKES ROAD Lane and footway restrictions, temporary traffic lights as required 10/08/20 18/09/20 Craigmillar Drive ducting Portobello/ THE JEWEL At the bus gate Mulholland - construction of new sewage system Road closed 17/08/20 12/10/20 Craigmillar Lane closures and temporary traffic lights as required. Portobello/ MILLIGAN DRIVE Whole length, various locations Scottish Water - mains investigations Bowes Place closed 10 - 13/09/20 24/08/20 21/09/20 Craigmillar East leg of Hammond Place closed 16 - 20/09/20

Start dates indicate earliest anticipated start. Finish dates represent formal notice periods - From 11 September 2020 www.edinburgh.gov.uk/edintravel works may finish earlier or be extended. Portobello/ DUDDINGSTON ROAD At Peffer Bank / Peffer Place Cityfibre - ducting / fibreoptics installation 4-way temporary traffic lights 31/08/20 11/09/20 Craigmillar WEST Portobello/ PORTOBELLO ROAD Between Christiemiller Avenue and Lane and parking restrictions as signed. Syndey Terrace closed Openreach - network upgrade 01/09/20 14/09/20 Craigmillar (MOIRA TERRACE) Vandeleur Avenue southbound from Sydney Park to Moira Terrace

1 - Lane restrictions on Milton Road West, Durham Road closed. Portobello/ 1 - At Durham Road MILTON ROAD WEST Openreach - network upgrade 2 - From 10/09/20 no right turn permitted Duddingston Park into Milton 07/09/20 23/09/20 Craigmillar 2 - At Duddingston Park Road West and Milton Road West into Duddingston Park South

Portobello/ Contraflow with no right turn into or out of Park Avenue; DUDDINGSTON PARK Various locations Openreach - network upgrade 10/09/20 14/09/20 Craigmillar 4-way temporary traffic lights at Duddingston Road / Baileyfield Road. Portobello/ COILLESDENE AVENUE At Coillesdene Gardens Scottish Power - equipment repairs 3-way temporary traffic lights 14/09/20 23/09/20 Craigmillar Portobello/ NIDDRIE MAINS ROAD At Hay Avenue / Niddrie Marischal Road Cityfibre - cable / ducting installation 4-way temporary traffic lights 14/09/20 18/09/20 Craigmillar Portobello/ ROAD At the rail bridge Network Rail - bridge survey Temporary traffic lights 10pm - 6am 17/09/20 18/09/20 Craigmillar

Scottish Water - mains replacement Westbound lane closure from 11/03/20 Saughton Road to Broomhouse Sighthill/ BROOMHOUSE DRIVE 20/01/20 10/05/20 *work suspended, traffic management removed* Medway. Between Saughton Road and Stenhouse SGN - essential gas main assessment and repairs Sighthill/Gorgie STENHOUSE DRIVE Lane closures / contraflow 07/07/20 Ongoing Avenue West as required Between McLeod Street and Ardmillan City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Sighthill/Gorgie GORGIE ROAD 23/07/20 Terrace safe walking and cycling wheelchairs, prams or bicycles to physically distance Notice Between Distillery Lane and Ardmillan City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further Sighthill/Gorgie DALRY ROAD 23/07/20 Terrace safe walking and cycling wheelchairs, prams or bicycles to physically distance Notice City of Edinburgh Council - to provide space for Until further Sighthill/Gorgie SIGHTHILL LOAN Road closed between Sighthill Avenue and Sighthill Gardens safe walking and cycling Notice

Sighthill/Gorgie GORGIE ROAD Avenue to outside LIFT gym Scottish Water - pipe repairs Westbound lane closure 05/09/20 14/09/20

09/10/19 2-way temporary traffic lights between the rail bridge and Sainsbury's car Scottish Power - to Westfield cable park then 4-way temporary traffic lights at Westfield Avenue junction, Sighthill/Gorgie WESTFIELD ROAD Rail bridge to Westfield Avenue Propose to End of October installation Westfield Road closed between Gorgie Road and Westfield Avenue resume during final phase. 14/09/20 At Ardmillan Terrace / Angle Park Terrace 7am Sighthill/Gorgie SLATEFORD ROAD Scottish Water - new service installation 4-way temporary traffic lights 13/09/20 / Harrison Road 14/09/20 ROAD Scottish Power - cable jointing Sighthill/Gorgie At Longstone Place Temporary traffic lights 15/09/20 28/09/20 NORTH (TBC as at 11/09/20) Scottish Water - new service installation Sighthill/Gorgie INGLIS GREEN ROAD At Redhall Drive / Sainsbury's 4-way temporary traffic lights proposed 19/09/20 20/09/20 (TBC as at 11/09/20) Between Calder Road Gardens and Sighthill/Gorgie CALDER ROAD Scottish Power - cable jointing Westbound lane closure 30/09/20 1 week Longstone roundabout

Cameron House Avenue, Clearburn Southside / Road, King's Meadow, Priestfield Avenue Cityfibre - installation of fibreoptic cabling Lane and parking restrictions, temporary traffic lights when required. One- PRESTONFIELD AREA 09/03/20 17/04/20 Newington / Gardens / Crescent / Road, Peffermill *work suspended* way order on Cameron House Avenue suspended Road and Prestonfield Avenue

Southside / Between and City of Edinburgh Council - to provide space for Re-designating key parts of the road to help pedestrians, people using Until further OLD DALKEITH ROAD 05/06/20 Newington Road safe walking and cycling wheelchairs, prams or bicycles to physically distance notice Southside / West Relugas Road to West Savile BLACKFORD AVENUE Scottish Power - works at substation Southbound lane closure 07/09/20 18/09/20 Newington Terrace

Start dates indicate earliest anticipated start. Finish dates represent formal notice periods - From 11 September 2020 www.edinburgh.gov.uk/edintravel works may finish earlier or be extended. Anti-clockwise one-way system between Crichton Street and Meadow Lane. Crichton Street one-way (westbound only) expect for cycles; Southside / City of Edinburgh Council - to provide space for Until further GEORGE SQUARE AREA George Square east side closed; 09/09/20 Newington safe walking and cycling notice George Square north and west sides one-way (westbound / southbound only) except for cycles; Meadow Lane one-way (eastbound only) except cycles Southside / DALKEITH ROAD At Prestonfield Avenue Scottish Water - manhole repairs 3-way temporary traffic lights 11/09/20 11/09/20 Newington Southside / City of Edinburgh Council - installation / repair of DALKEITH ROAD At Priestfield Road 4-way temporary traffic lights, 7pm - 7am for 2 nights 22/09/20 24/09/20 Newington traffic detection loops

West Lothian B7030 BONNINGTON ROAD At A71 Scottish Water - pipe replacement Road closed. Diversion via A71 - A899 - A89 - Cliftonhall Road (B7030) 28/09/20 02/10/20

Trunk roads (information from Traffic Scotland / BEAR websites)

Carriageway damage - click cell for more details on Road closed. A68 Between Pathhead and Fala 11/08/20 11/09/20 Traffic Scotland website Reopened with temporary traffic lights 07/09/20, fully open as of 11/09/20 13/09/20 18/09/20 Between Oaktree and Abbotsview A1 BEAR - carriageway resurfacing Road closed to eastbound traffic 8pm - 6am and and junctions 22/09/20 23/09/20 23/09/20 25/09/20 Between Bankton and Gladsmuir A1 BEAR - carriageway resurfacing Road closed to eastbound traffic 8pm - 6am and and junctions 29/09/20 03/10/20

Start dates indicate earliest anticipated start. Finish dates represent formal notice periods - From 11 September 2020 www.edinburgh.gov.uk/edintravel works may finish earlier or be extended.