Total Project Snapshot Report 2013 Legislature TPS Report 59487v2 Agency: Commerce, Community and Economic Development Grants to Named Recipients (AS 37.05.316) Grant Recipient: Association Federal Tax ID: 92-0029566 Project Title: Project Type: Maintenance and Repairs Tanana Valley State Fair Association - Sewer and Water Line Replacement

State Funding Requested: $46,800 House District: Fairbanks Areawide (1-5) One-Time Need

Brief Project Description: Replacement of all existing sewer lines on the Fairgrounds.

Funding Plan: Total Project Cost: $46,800 Funding Already Secured: ($0) FY2014 State Funding Request: ($46,800) Project Deficit: $0 Funding Details: No funding history for this project. TVSFA has been paying for repairs as needed when there is a sewer failure.

Detailed Project Description and Justification: Approximately 1000 feet of 40 year old wooden stave sewer is in need of replacment and upgrade to PVC sewer lines. Current sewer system cannot handle demand, and is shutting down in some areas. Project includes digging up the old staves and removing them, then replacing with new material which will be insulated.

Project Timeline: Project to begin in the Fall of 2014, with completion in Summer 2015.

Entity Responsible for the Ongoing Operation and Maintenance of this Project: Tanana Valley State Fair Association

Grant Recipient Contact Information: Name: Randi Carnahan Title: General Manager Address: 1800 College Road Fairbanks, 99709 Phone Number: (907)451-5560 Email: [email protected]

Has this project been through a public review process at the local level and is it a community priority? X Yes No

For use by Co-chair Staff Only: Page 1 Contact Name: Pete Fellman $46,800 Contact Number: 465-3613 Approved 2:02 PM 5/9/2013