Environmental Monitoring Report

Semestral Report #2 January 2019

TAJ: Strengthening Technical and Vocational Education and Training Project

(July – December 2018)

Prepared by the Project Administration Group, Ministry of Labor, Migration and Employment for the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Semi-annual Environmental Monitoring Report ______

Project Number: 46535-001 G0452/53/3309 Reporting period: July-December 2018

Republic of : Strengthening Technical and Vocational Education and Training (Financed by the Asian Development Bank)

Prepared by: STVET PAG, Tajikistan

For: Ministry of Labor, Migration and Employment of the Republic of Tajikistan, Project Administration Group

Endorsed By: Manager of PAG STVET Doston Turaev

January 2019

Strengthening Technical and Vocational Education and Training ______

TABLE OF CONTENT 1. INTRODUCTION ...... 4 1.1. Preamble ...... 4 2. PROJECT DESCRIPTION AND CURRENT ACTIVITIES ...... 5 2.1. PROJECT DESCRIPTION ...... 5 2.2. Project contracts and management...... 8 2.3. Construction activities and project progress in reporting period ...... 9 2.3.1. Rehabilitation of the Regional Resource center in Bokhtar ...... 9 2.3.2. Construction activities conducted on Regional resource centers of Kulyab ...... 12 2.3.3. Construction activities conducted on Regional Resource Center of Khujand ...... 15 2.3.4. Construction activities conducted on Constructional Lyceum of Dushanbe ...... 18 2.3.5. Construction activities conducted on Polytechnic Lyceum of Khujand, financed by Clean energy fund ...... 21 2.3.6. Construction activities conducted on Construction Lyceum of Dushanbe ...... 25 2.3.7. Construction activities conducted on Sewing Lyceum of Dushanbe ...... 27 2.3.8. Construction activities conducted on Polytechnic Lyceum of Dushanbe ...... 31 2.3.9. Construction activities conducted on Auto Transport Lyceum of Dushanbe ...... 33 2.3.10. Construction activities conducted on Tourism and Service Lyceum of Dushanbe ...... 36 2.3.11. Construction activities conducted on Technical Vocational Lyceum of ...... 40 2.3.12. Construction activities conducted on Construction Lyceum in Kulob ...... 42 2.3.13. Construction activities conducted on Agricultural Lyceum of Kulob (Dahana) ...... 44 2.3.14. Construction activities conducted on Technical Vocational Lyceum of Vose ...... 45 2.3.15. Construction activities conducted on Technical Vocational Lyceum in Tojikobod ...... 47 2.3.16. Construction activities conducted on Technical Vocational Lyceum of Shugnon ...... 49 2.3.17. Construction activities conducted on Adult Learning Center of Farkhor ...... 50 III. ENVIRONMENTAL MANAGEMENT ...... 52 3.1. General Description of Environmental Safeguard Activities...... 52 3.2. Site audits ...... 52 3.3 Non-conformance notices ...... 64 IV. ENVIRONMENTAL MONITORING ...... 65 4.1. Water quality monitoring ...... 65

______Semi-annual Environmental Monitoring report, July – December 2018 1 Strengthening Technical and Vocational Education and Training ______

4.2. Air quality monitoring ...... 65 4.3. Noise and vibrations monitoring ...... 65 4.4. Flora and fauna monitoring ...... 65 4.5. Waste management ...... 65 4.6. ACM management plan ...... 66 4.7. Health and safety Plan ...... 66 5. FUNCTIONING OF THE SSEMP...... 67 6. SUMMARY AND RECOMENDATIONS ...... 74 Annex 1: Post-Construction Monitoring Check-lists ...... 75

TABLES Table 1: List of sub-projects ...... 6 Table 2: Construction activities conducted on RRC of Bokhtar – July-December 2018 ...... 10 Table 3: Construction activities in RRC in Kulyab – July-December 2018 ...... 12 Table 4: Construction activities in RRC in Khujand ...... 15 Table 5: Construction activities in Construction Lyceum in Dushanbe, financed by Clean energy fund ...... 18 Table 6: Construction activities in Polytechnic Lyceum in Khujand, financed by Clean energy fund ...... 22 Table 7: Construction activities in Construction Lyceum in Dushanbe ...... 25 Table 8: Construction activities in Sewing Lyceum in Dushanbe ...... 28 Table 9:Construction activities in Polytechnic Lyceum in Dushanbe ...... 31 Table 10: Construction activities in Auto transport Lyceum in Dushanbe ...... 33 Table 11: Construction activities in Tourism and service lyceum in Dushanbe ...... 37 Table 12: Construction activities in Technical Vocational Lyceum in Shahrinav ...... 40 Table 13: Construction activities in Constructional Lyceum in Kulob ...... 43 Table 14: Construction activities in Agricultural Lyceum in Kulob (Dahana) ...... 44 Table 15: Construction activities in Technical Vocational Lyceum in Vose ...... 46 Table 16: Construction activities in Technical Vocational Lyceum in Tojikobod ...... 47 Table 17: Construction activities in Technical Vocational Lyceum in Shugnon ...... 49 Table 18: Construction activities in Adult Learning center of Farkhor ...... 50 Table 19: Site visits and audits in the reporting period ...... 53 Table 20: Status of SSEMPs for reporting period from July to December 2019 ...... 67 Table 21: Implementation of SSEMPs‘ mitigation measures ...... 69

______Semi-annual Environmental Monitoring report, July – December 2018 2 Strengthening Technical and Vocational Education and Training ______

ABBREVIATIONS ADB Asian Development Bank SEMR Semi-Annual Environmental Management Report CSJC Closed stock joint company DRS Districts of Republican Subordination EMP Environmental Management Plan GBAO Gorno-Badakhshan Autonomous Oblast IEE Initial Environmental Examination LLC Limited Liability Company MOLME Ministry of Labor, Migration and Employment OSJC Open stock joint company PAG Project administration group PIC Project Implementation Consultants PPE Personal Protective Equipment RRC Regional Resource center RETA Regional Technical Assistance SSEMP Site Specific Environmental Management Plan TJRM Tajikistan Resident Mission TVET Strengthening Technical and Vocational Education and Training Project

Units

°C degree Celsius cm centimeter km kilometer km2 square kilometer m meter m2 square meter

______Semi-annual Environmental Monitoring report, July – December 2018 3 Strengthening Technical and Vocational Education and Training ______

1. INTRODUCTION 1.1. Preamble

1. The Strengthening Technical and Vocational Education and Training Project supports the expansion of quality training of unskilled youth and adults to prepare them for skilled employment in Tajikistan and abroad through upgrading of the public TVET system. The upgraded system will train and empower individuals to move from unemployment and underemployment into higher-paying jobs, alleviating poverty by strengthening the livelihood opportunities of trainees and their families and increasing their ability to participate in national economic development.

2. The Project addresses a range of challenges faced by the public TVET system that provides most of Tajikistan’s TVET training: outdated curriculum and learning materials; obsolete and inadequate equipment; dilapidated instructional buildings; unmaintained and damaged dormitories; low-paid teachers and masters without updated training; very limited staff development and succession planning; little or no linkage with industry; outdated approaches to school management; weak interagency coordination; and continuing underinvestment generally. A large number of graduates are produced each year, but the training does not impart modern skills and qualifications in demand in the labor market.

3. The outcome of the Project will be a national workforce with an increased proportion of skilled workers employed in Tajikistan. The outcome will be a demand-driven, quality- assured, and flexible TVET system responsive to labor market needs.

4. The Project has four outputs as follows: (i) TVET system methodology modernized; (ii) physical learning facilities in selected TVET institutions upgraded; (iii) access to quality TVET programs improved; and (iv) governance and management of TVET system strengthened.

5. This fourth semi-annual report on environmental monitoring covers the period from July to December 2018 and presents the results of the monitoring of environmental safeguards implementation at construction sites . During this period rehabilitation works have been started on 17 subrojects, 3 of them completed.

______Semi-annual Environmental Monitoring report, July – December 2018 4 Strengthening Technical and Vocational Education and Training ______

2. PROJECT DESCRIPTION AND CURRENT ACTIVITIES 2.1. PROJECT DESCRIPTION

6. The Republic of Tajikistan has received Grant 0452/53/Loan 3309 from the Asian Development Bank (ADB) for implementing Strengthening Technical and Vocational Education and Training (TVET) Project (the Project). The Project supports the expansion of quality training of unskilled youth and adults to prepare them for skilled employment in Tajikistan and abroad through upgrading of the public TVET system. The upgraded system will train and empower individuals to move from unemployment and underemployment into higher-paying jobs, alleviating poverty by strengthening the livelihood opportunities of trainees and their families and increasing their ability to participate in national economic development.

7. The “Strengthening Technical and Vocational Education and Training (TVET), Tajikistan Project funding consists of an ADB US$15 million loan, US$ 15 million grant, co-financing of $2 million from the Clean Energy Fund under the Clean Energy Financing Partnership Facility, and Government of Tajikistan $2 million counterpart funds. The implementing agency is the Ministry of Labor, Migration and Employment (MOLME).

8. The Project has four outputs as follows: (i) TVET system methodology modernized; (ii) physical learning facilities in selected TVET institutions upgraded; (iii) access to quality TVET programs improved; and (iv) governance and management of TVET system strengthened.

9. The Project is classified as ADB Environmental Category B with the potential environmental impacts confined to activities within Output 2, Upgrade Physical Learning Facilities. This component consists of:

• civil works to rehabilitate existing buildings; and • provision of new equipment to rehabilitated workshops, laboratories and other facilities. 10. The Project will rehabilitate physical facilities at 36 TVET institutions located throughout the country. The importance of the Project will be through its impact on the skills and employability of graduates of the rehabilitated TVET schools. The map showing location of the educational facilities covered by the Project is presented below.

11. This is the third Bi-annual Environmental Report for the TVET Project, covering the period from January to June 2018. The scope of the report is to describe the monitoring of environmental, social and safety issues associated with the implementation of the project.

12. The Figure 1 below shows the location of all TVET sub-projects in the scale of country.

______Semi-annual Environmental Monitoring report, July – December 2018 5 Strengthening Technical and Vocational Education and Training ______

Figure 1: Location of the selected TVET institutions

13. Table 1 presents list of STVET sub-projects and their status.

Table 1: List of sub-projects № CW Facility name Status Package 1 Rehabilitation of Construction Lyceum in Dushanbe Ongoing CW01-01 2 Rehabilitation of Polytechnic Lyceum in Dushanbe Ongoing

3 Rehabilitation of Sewing Lyceum in Dushanbe Ongoing 4 Rehabilitation of Auto Transport Lyceum in Dushanbe Ongoing CW01-02 5 Rehabilitation of Tourism Lyceum in Dushanbe Ongoing

6 Rehabilitation of Lyceum in Shahrinav Ongoing 7 CW02 Rehabilitation of Polytechnic Lyceum in Khujand Not started 8 Rehabilitation of Lyceum in Isfara Not started 9 CW02 Rehabilitation of Lyceum Mastchoch Not started 10 Rehabilitation of ALC Branch in Kanibadam Not started

______Semi-annual Environmental Monitoring report, July – December 2018 6 Strengthening Technical and Vocational Education and Training ______

№ CW Facility name Status Package 11 Rehabilitation of ALC Branch in Ghafurov Not started 12 Rehabilitation of Construction Lyceum in Khujand Not started 13 Minor Renovation of Lyceum Panjikent Not started 14 CW04 Minor Renovation of Lyceum Istaravshan Not started 15 Minor Renovation of Lyceum Shariston Not started 16 Minor Renovation of ALC Branch in Farhor. Ongoing 17 Minor Renovation of Lyceum in Vose. Ongoing CW05 18 Minor Renovation of Agricultural Lyceum in Kulyab Ongoing 19 Renovation of Construction Lyceum in Kulyab Ongoing 20 Minor Rehabilitation of Lyceum in Bokhtar (Kurgan-Tube) Not started 21 Minor Rehabilitation of Lyceum in Vakhsh Not started 22 Minor Rehabilitation of ALC Branch in Yavan Not started CW06 23 Minor Rehabilitation of Branch of Vocational and Not started Entrepreneurial Centre in Nurek 24 Rehabilitation of Lyceum in Shaartuz Not started 25 CW07-01 Minor Rehabilitation of Lyceum in Tojikobod Minor Ongoing 26 CW07-02 Rehabilitation of Lyceum in Shugnon Ongoing 27 CW08 Minor repair in Adult Learning Center branch in Vanj district Completed (GBAO) 28 CW09 minor repair in Adult Learning Center branch: Center of Completed Vocational training and Entrepreneurship in (DRS) 29 CW10 Rehabilitation of Bokhtar Energy Institute. Completed 30 CW11 State Institution “Center for Training Methodologв and Completed Monitoring Education Qualitв” and “Engineering Pedagogical college in Dushanbe” 31 CW12-1 Rehabilitation of Polytechnic Lyceum in Khujand* Ongoing 32 CW12-2 Rehabilitation of Construction Lyceum in Dushanbe* Ongoing 33 CW13 Rehabilitation of Training Center Completed 34 Rehabilitation of Regional Resource Centre in Bokhtar Completed CW14 35 Rehabilitation of Regional Resource Centre in Khujand Completed 36 CW14 Rehabilitation of Regional Resource Centre in Kulyab Completed

14. In December 2018, 14 projects have the “on-going” status.

______Semi-annual Environmental Monitoring report, July – December 2018 7 Strengthening Technical and Vocational Education and Training ______

2.2. Project contracts and management

15. The Executing Agency for the project is MOLME. The Project Administrative Group (PAG) has been set up within MOLME for the management of the implementation contracts. The environmental and social safeguards expert in PAG is Mrs. Larisa Kamilova and environmental safeguards consultant in PAG Mr. Dilshod Dadobaev. They are responsible for the coordination for environmental and social safeguards issues

16. The Project Implementation Consultants (PIC), a joint venture led by GOPA with CAICO, supports the PAG. Project Implementation Consultant company has not currently any International nor National Environmental Consultant in the team. The previous PIC’s International consultant Rangina Nazrieva left the project in December 2017. It was agreed with ADB (PTL) that all functions on ensuring the environmental and social safeguards would be devolved to PAG. In order to ensure environmental performance of the project two new experts, namely Environmental and social safeguards specialist – Larisa Kamilova in February 2018 and Environmental and social safeguards consultant – Dilshod Dadobaev in March 2018, have been recruited by the PAG .

17. The project organization chart for reporting period is presented in Figure 2.

______Semi-annual Environmental Monitoring report, July – December 2018 8 Strengthening Technical and Vocational Education and Training ______

MOLME PAG

Contractors

Environmental and social safeguards expert Contractors’

(Larisa Kamilova) Environmental Officer Health and Safety Environmental and Officer social safeguards consultant (Dilshod Dadobaev)

Figure 2: Environmental management of TVET project

2.3. Construction activities and project progress in reporting period

18. The construction activities within the reporting period covered 17 sub-projects out of the remaining 31, five sub-projects was completed in previous periods. The 3 sub-projects completed in reporting period and 14 are is in progress.

19. During the reporting period, construction work on the Rehabilitation of the Regional Resource centers in Bokhtar, Khujand and Kulyab has been completed. The post-construction environmental audit of the completed sub-projects have been carried out in September 2018, with the check-lists filled as required (Annex 1). Defect liability period has started in November 2018 and will last till November 2019.

2.3.1. Rehabilitation of the Regional Resource center in Bokhtar 20. During the reporting period, in September 2018 construction work on the Resource Center of Bokhtar has been completed. The Table 2 below presents information on implemented construction activities.

______Semi-annual Environmental Monitoring report, July – December 2018 9 Strengthening Technical and Vocational Education and Training ______

Table 2: Construction activities conducted on RRC of Bokhtar – July-December 2018 CW14-A Rehabilitation of Regional Resource Centre in Bokhtar

Month Construction activities July ➢ Dismantling works ➢ Construction of partition walls ➢ Filling of surface of walls ➢ Construction of suspended ceilings type "Armstrong" on a framework from a galvanized profile ➢ Installation of metal plastic windows ➢ Solid alignment of the wall surfaces, door and window slopes of dry gypsum mixes Rotband ➢ Electrical works August ➢ Electrical work ➢ Installation of wooden door blocks September ➢ Laying laminated flooring on the finished base by way of glue-free locking with sound insulation pads ➢ Installation of window bars Total progress of construction work by end of September 2018 – 100%

21. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the RRC in Bokhtar

Photo 1: The territory of Photo 2: First aid kit and fire extinguisher are in place, 08.08.2018 construction works is fenced, 08.08.2018

______Semi-annual Environmental Monitoring report, July – December 2018 10 Strengthening Technical and Vocational Education and Training ______

Photo 3Environmental documentation is in place, 08.08.2018

Photo 4: Rehabilitation works of facade, floors and ceilings completed, 06.09.2018

______Semi-annual Environmental Monitoring report, July – December 2018 11 Strengthening Technical and Vocational Education and Training ______

Photo 5: Rehabilitation of main Photo 6: Meeting hall equipped with Photo 7: Sanitary appliances entrance completed, 28.09.2018 furniture, 28.09.2018 are installed, 28.09.2018

2.3.2. Construction activities conducted on Regional resource centers of Kulyab 22. During the reporting period, in September 2018 the construction works on the Regional Resource Center of Kulyab were completed. The Table 3 below presents information on implemented construction activities.

Table 3: Construction activities in RRC in Kulyab – July-December 2018 CW14-C Rehabilitation of Regional Resource Centre in Kulyab

Month Construction Activities July ➢ Dismantling works ➢ Construction of a partition walls ➢ Filling openings with bricks ➢ Installation of metal plastic windows ➢ Installation of metal plastic doors ➢ Flooring ➢ Construction of concrete ramps ➢ Electrical works

August ➢ Electrical works ➢ Improved plastering of interior walls ➢ Solid alignment of the wall surfaces, door and window slopes of dry gypsum mixes Rotband ➢ Installation of Armstrong-type suspended ceilings on a galvanized profile frame ➢ Installation of ceramic tiles in sanitary facilities ➢ Installation of metal frames for ceilings in sanitary units ➢ Sheeting by plastic the ceilings in sanitary units

______Semi-annual Environmental Monitoring report, July – December 2018 12 Strengthening Technical and Vocational Education and Training ______

September ➢ Reconstruction of the front face of the building • Paint plinth decorative facade paints • Painting of facades and slopes with facade paints

Total progress of construction work by end of September 2018 – 100%

23. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the RRC in Kulyab

CW14-C Rehabilitation of Regional Resource Centre in Kulyab

Photo 10: Ffire protection means Photo 8: Environmental Photo 9: The territory of the site are in place, and well equipped, documents are in place, fenced, 08.08.2018 08.08.2018 08.08.2018

Photo 11: Progress of rehabilitation works, 08.08.2018

______Semi-annual Environmental Monitoring report, July – December 2018 13 Strengthening Technical and Vocational Education and Training ______

Photo 12: Progress of rehabilitation works, 08.08.2018

Photo 13: Rehabilitations works on facade almost completed, Photo 14: Rehabilitation works 28.09.2018 in corridor completed, 28.09.2018

______Semi-annual Environmental Monitoring report, July – December 2018 14 Strengthening Technical and Vocational Education and Training ______

Photo 15: The territory of the RRC cleaned and restored after completion of works, 17.10.2018

2.3.3. Construction activities conducted on Regional Resource Center of Khujand 24. In August 2018, construction works on the Regional Resource Center of Khujand have been completed. The Table 4 below presents information on implemented construction activities

Table 4: Construction activities in RRC in Khujand CW14-В Rehabilitation of Regional Resource Centre in Khujand

Month Construction Activities July ➢ Dismantling works ➢ Installation of metal plastic windows ➢ Installation of metal plastic doors ➢ Improved plastering of interior walls ➢ Solid alignment of the wall surfaces, door and window slopes of dry gypsum mixes Rotband ➢ Electrical works

August ➢ Painting with polyvinyl acetate water-emulsion compositions of walls, partitions and slopes ➢ Laying laminated flooring on the finished base by way of glue-free locking with sound insulation pads ➢ Installation of window bars ➢ Electrical works

Total progress of construction work by end of August 2018 – 100%

______Semi-annual Environmental Monitoring report, July – December 2018 15 Strengthening Technical and Vocational Education and Training ______

25. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the RRC in Khujand

Photo 16: The territory is Photo 17: Fire protection means are Photo 18: Environmental fenced, 15.08.2018 in place, 15.08.2018 documentation are in place

Photo 19: Workers are Photo 20: Fire extinguisher are in Photo 21: Rehabilitation works equipped with PPE, 15.08.2018 place, 15.08.2018 in progress, 15.08.2018

______Semi-annual Environmental Monitoring report, July – December 2018 16 Strengthening Technical and Vocational Education and Training ______

Photo 22: Temporary waste Photo 23: Floring works in Photo 24: Finishing works in storing, 04.09.2018 progress, 04.09.2018 Metting hall, 04.09.2018

Photo 25: Construction site is Photo 26: Meeting hall after rehabilitation, 25.09.2018 cleaned, all waste removed, 25.09.2018

______Semi-annual Environmental Monitoring report, July – December 2018 17 Strengthening Technical and Vocational Education and Training ______

2.3.4. Construction activities conducted on Constructional Lyceum of Dushanbe 26. During the reporting period, construction works on the Construction Lyceum in Dushanbe, which is financed by Clean Energy Fund, are 95% completed in December 2018. Table 5 below presents information on implemented construction activities.

Table 5: Construction activities in Construction Lyceum in Dushanbe, financed by Clean energy fund CW12-2 Rehabilitation of Construction Lyceum in Dushanbe Month Construction Activities August ➢ Dismantling works ➢ Construction of a partition walls ➢ Plastering of walls surfaces with cement-lime mortar ➢ Installation of metal plastic windows ➢ Electrical works ➢ Roofing o Installation of wooden rafters o Installation of wooden roof frames made of uneven bars

September ➢ Electrical works ➢ Interior finishing works ➢ Thermal insulation of floors using expanded clay gravel (expanded clay) ➢ Roofing o Galvanized steel roofing o Installation of a solar inverter o Installation of a solar collector Aqua SP

October ➢ Installation of sanitary appliances ➢ Painting walls, partitions and slopes by improved water-color paint ➢ Painting ceilings by improved water-color paint ➢ Roofing o Thermal insulation of ceilings using expanded clay gravel o Fencing the edge of the roof by railings ➢ Construction of overhangs

November ➢ Installation of of double-leaf self-closing doors in corridors ➢ Electrical works ➢ Interior finishing works ➢ Installation of suspended ceilings type "Armstrong" ➢ Installation of a 5000W Solar Monocrystalline Panel ➢ Installation and connection of gel batteries

December ➢ Painting with improved water-emulsion paint walls, partitions and slopes ➢ Installation of cast iron radiators ➢ Laying of heating pipelines by polyethylene pipes Ø32 mm ➢ Reconstruction of the front face of the building • Paint plinth decorative facade paints • Painting of facades and slopes with facade paints

Total progress of construction work by end of December 2018 – 95%

27. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in

______Semi-annual Environmental Monitoring report, July – December 2018 18 Strengthening Technical and Vocational Education and Training ______the Construction Lyceum in Dushanbe

Photo 27: Informational and warning signs installed, 28.08.2018 Photo 28: Environmental documentation in place, 28.08.2018

Photo 29: Workers equipped with PPE Photo 30: Fire protection means in place

______Semi-annual Environmental Monitoring report, July – December 2018 19 Strengthening Technical and Vocational Education and Training ______

Photo 31: Works on improving the facade, during removal of plaster, the construction waste is temporarily stored and cleared daily, 20.09.2018

Photo 32: Ceiling works, 08.10.2018 Photo 33: Solar panels installed, 19.11.2018

______Semi-annual Environmental Monitoring report, July – December 2018 20 Strengthening Technical and Vocational Education and Training ______

Photo 34: Improving facade completed, 19.11.2018

Photo 35: Works on rehabilitation of foyer completed, 21.12.2018

2.3.5. Construction activities conducted on Polytechnic Lyceum of Khujand, financed by Clean energy fund

28. During the reporting period, construction works on the Polytechnic Lyceum in Khujand, which is financing by Clean energy fund have been implemented at 83%. The below presents information on implemented construction activities

______Semi-annual Environmental Monitoring report, July – December 2018 21 Strengthening Technical and Vocational Education and Training ______

Table 6: Construction activities in Polytechnic Lyceum in Khujand, financed by Clean energy fund CW12-1 Rehabilitation of Polytechnic Lyceum in Khujand Month Construction activities August- ➢ Dismantling works September ➢ Installation of Euro type window units, double glazing ➢ Interior finishing works ➢ Roofing o Installation of wooden roof frames made of uneven bars ➢ Installation of a solar split type collector for 5000 l ➢ Electrical works

October ➢ Electrical works ➢ Interior finishing works ➢ Installation of sanitary appliances ➢ Thermal insulation of floors using expanded clay gravel (expanded clay) ➢ Laying laminated coatings on the finished base ➢ Installation of suspended ceilings type "Armstrong" ➢ Fencing the edge of the roof by railings ➢ Installing plastic drainpipes ➢ Installation of drain funnels

November ➢ Installation of solar inverter, rated output power 2400W ➢ External work ➢ Construction of overhangs ➢ Installation work on heating system

December Due to weather conditions, work was not carried out in December 2018.

Total progress of construction work by end of December 2018 – 83%

29. Photos below shows progress of rehabilitation works and implementation of SSEMP in the Polytechnic Lyceum in Khujand

______Semi-annual Environmental Monitoring report, July – December 2018 22 Strengthening Technical and Vocational Education and Training ______

Photo 36: Territory fenced, information and warning signs installed

Photo 37: Fire protection Photo 38Environmental Photo 39: Workers equipped means are in place, 15.08.2018 documentation are in place, with PPE, 15.08.2018 15.08.2018

______Semi-annual Environmental Monitoring report, July – December 2018 23 Strengthening Technical and Vocational Education and Training ______

Photo 40: Internal works, 25.09.2018 Photo 41: Roofing works, 25.09.2018 25.09.2018

Photo 43: Ceiling works , 22.10.2018 Photo 42: Facade works, 22.10.2018

______Semi-annual Environmental Monitoring report, July – December 2018 24 Strengthening Technical and Vocational Education and Training ______

2.3.6. Construction activities conducted on Construction Lyceum of Dushanbe 30. During the reporting period, construction work on the Construction Lyceum in Dushanbe has been completed at 60%. The Table 7 below presents information on implemented construction activities

Table 7: Construction activities in Construction Lyceum in Dushanbe

CW01-01-A Rehabilitation of Construction Lyceum in Dushanbe

Month Construction Activities Workshops November ➢ Dismantling works ➢ Works on improving ventilation system o Installation of radial dust removal fans for wood dust and sawdust o Installation of galvanized air ducts o Installation of exhaust ventilation channels ➢ Installation of metal plastic windows ➢ Flooring works of showers ➢ Interior finishing works o Continuous alignment of ceiling surfaces o Plastering of walls surfaces with cement-lime mortar ➢ Reconstruction of the front face of the building o Plastering of walls Dormitory Block B ➢ Dismantling works ➢ Installation of metal plastic windows ➢ Masonry of separate sections of brick walls and sealing of holes in brick walls ➢ Painting with improved water-emulsion paint of ceilings ➢ Reconstruction of the front face of the building o Plastering of walls ➢ Electrical works

December ➢ Installation of metal doors ➢ Flooring works of showers and laboratories o Installing ceramic tiles on cement mortar ➢ Painting with improved water-emulsion paint walls, partitions and slopes ➢ Facing of walls of bathrooms by ceramic tiles ➢ Reconstruction of the front face of the building o Painting the façades by improved façade paint

Total progress of construction work by end of December 2018 – 60%

31. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the Construction Lyceum in Dushanbe

______Semi-annual Environmental Monitoring report, July – December 2018 25 Strengthening Technical and Vocational Education and Training ______

Photo 44: Information sign Photo 45: Territory is fenced, Photo 46: Workers are equipped installed, 30.10.2018 30.10.2018 with PPE, 30.10.2018

Photo 47: Demolishing works on Photo 48: Environmental documentation in place, 30.10.2018 Dormitory building, 30.10.2018

______Semi-annual Environmental Monitoring report, July – December 2018 26 Strengthening Technical and Vocational Education and Training ______

Photo 49: Rehabilitation of facade and roofing works in dormitory building, territory fenced, workers equipped with PPE, 05.11.2018

Photo 50: Rehabilitation of The Photo 51: Rehabilitation of The Photo 52: Fire extinguishers dormitory building, territory is workshop building, territory is and first aid kits, 21.12.2018 fenced, 21.12.2018 fenced, warning signs installed, 21.12.2018

2.3.7. Construction activities conducted on Sewing Lyceum of Dushanbe 32. During the reporting period, construction work on the Sewing Lyceum in Dushanbe has been 58% completed. The Table 8 below presents information on implemented construction activities

______Semi-annual Environmental Monitoring report, July – December 2018 27 Strengthening Technical and Vocational Education and Training ______

Table 8: Construction activities in Sewing Lyceum in Dushanbe

CW01-01-C Rehabilitation of Sewing Lyceum in Dushanbe

Month Construction activities

November Dormitory ➢ Dismantling works ➢ Disassembly of roofing made from asbestos-cement slate ➢ Installation of metal plastic windows ➢ Flooring works o Works on leveling by a cement-sandy mortar ➢ Interior finishing works o Continuous alignment of ceiling surfaces o Plastering of walls surfaces with cement-lime mortar ➢ Reconstruction of the front face of the building o Plastering of walls ➢ Roofing works o Installation of wooden rafters o Fire protection of wooden structures o Roofing by Galvanized Steel o Fencing the edge of the roof by railings ➢ Works on rehabilitation water supply and sewerage ➢ Electrical works Educational Building ➢ Dismantling works ➢ Installation of metal plastic windows ➢ Flooring works o Works on leveling by a cement-sandy mortar ➢ Interior finishing works o Continuous alignment of ceiling surfaces o Plastering of walls surfaces with cement-lime mortar ➢ Installation of suspended ceilings type "Armstrong" ➢ Reconstruction of the front face of the building o Plastering of walls ➢ Interior finishing works ➢ Construction of Concrete ramps ➢ Roofing works ➢ Electrical works

December Dormitory ➢ Installation of metal plastic doors ➢ Flooring works o Installing ceramic tiles on cement mortar in the showers and corridors ➢ Reconstruction of the front face of the building o Painting the façades by improved façade paint ➢ Rehabilitation of water supply and sewerage system ➢ Electrical works

Educational Building

______Semi-annual Environmental Monitoring report, July – December 2018 28 Strengthening Technical and Vocational Education and Training ______

➢ Masonry of separate sections of brick walls ➢ Installation of metal plastic windows ➢ Installation of metal plastic doors ➢ Flooring works o Installing ceramic tiles on cement mortar ➢ Interior finishing works o Plastering of walls surfaces with cement-lime mortar Total progress of construction work by end of December 2018 – 58%

33. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the Sewing Lyceum in Dushanbe

34.

Photo 53: Territory is fenced, information and warning signs installed, Environmental documentations in place

______Semi-annual Environmental Monitoring report, July – December 2018 29 Strengthening Technical and Vocational Education and Training ______

Photo 54: Temporary storing of the ACM, 05.11.2018

Photo 55: Demolishing works in progress, 14.11.2018

______Semi-annual Environmental Monitoring report, July – December 2018 30 Strengthening Technical and Vocational Education and Training ______

2.3.8. Construction activities conducted on Polytechnic Lyceum of Dushanbe 35. During the reporting period, construction work on the Polytechnic lyceum in Dushanbe has been 60% completed. The Table 9 below presents information on implemented construction activities

Table 9:Construction activities in Polytechnic Lyceum in Dushanbe

CW01-01-B Rehabilitation of Polytechnic Lyceum in Dushanbe

Month Construction activities ➢ Dismantling works November ➢ Masonry of separate sections of brick walls ➢ Installation of metal plastic windows ➢ Roofing works o Installation of wooden rafters o Fire protection of wooden structures o Roofing by Galvanized Steel o Fencing the edge of the roof by railings ➢ Interior finishing works o Plastering of walls surfaces with cement-lime mortar ➢ Improving of the front face of the building o Plastering of walls ➢ Electrical works Workshop no 2 ➢ Dismantling works ➢ Installation of metal plastic windows ➢ Flooring works ➢ Interior finishing works o Plastering of walls surfaces with cement-lime mortar ➢ Reconstruction of the front face of the building o Plastering of walls ➢ Works on improving ventilation system ➢ Interior finishing works December ➢ Improvement of the front face of the building o Plastering of walls ➢ Flooring works Total progress of construction work by end of December 2018 – 60%

36. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the Polytechnic Lyceum in Dushanbe

______Semi-annual Environmental Monitoring report, July – December 2018 31 Strengthening Technical and Vocational Education and Training ______

Photo 56: Information and Photo 57: Fire protection means in place warning signs installed

Photo 58: Environmental Photo 59: Temporary storage of ACM documentation is in place

______Semi-annual Environmental Monitoring report, July – December 2018 32 Strengthening Technical and Vocational Education and Training ______

Photo 60: Demolishing works in progress

2.3.9. Construction activities conducted on Auto Transport Lyceum of Dushanbe 37. During the reporting period, construction work on the Auto transport lyceum of Dushanbe has been completed at 51%. The Table 10 below presents information on implemented construction activities

Table 10: Construction activities in Auto transport Lyceum in Dushanbe

CW01-02-A Rehabilitation of Auto Transport Lyceum in Dushanbe

Month Construction activities ➢ Dismantling works October ➢ Manual cleaning of ceiling surfaces from water-emulsion paints ➢ Improvement of the front face of the building o Plastering of walls ______Semi-annual Environmental Monitoring report, July – December 2018 33 Strengthening Technical and Vocational Education and Training ______

➢ Dismantling of internal water supply and sewerage system in the workshop

November ➢ Sanitary units o Preliminarв smoothing of the аalls’ surface o Preliminarв smoothing of the ceilings’ surface ➢ Façade o Wall plastering using concrete-lime mortar ➢ Roofing o Change of the existing roll roofs on the coating of the deposited materials in 2 layers ➢ Electrical works ➢ Flooring works December o Installing ceramic tiles on cement mortar in the sanitary units and corridors ➢ Construction of Concrete ramps ➢ Facade o Facing the plinth with porcelain tiles ➢ Works on rehabilitation of internal water supply and sewerage system ➢ Electrical works

➢ Earth works on workshop building ➢ Construction of strip reinforced foundation for workshop building

Total progress of construction work by end of December 2018 – 51%

38. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the Auto transport Lyceum in Dushanbe

______Semi-annual Environmental Monitoring report, July – December 2018 34 Strengthening Technical and Vocational Education and Training ______

Photo 61: Information and warning signs installed, environmental documentation is in place

Photo 62: Fire protection means Photo 63: Container for liquid waste Photo 64: Territory is fenced

______Semi-annual Environmental Monitoring report, July – December 2018 35 Strengthening Technical and Vocational Education and Training ______

Photo 65: Internal finishing works in progress

Photo 66: Rehabilitation of facade Photo 67: Construction works of the workshop, workers equipped with PPE

2.3.10. Construction activities conducted on Tourism and Service Lyceum of Dushanbe 39. During the reporting period, construction work on the Tourism and Service lyceum in Dushanbe has been 29% completed. The Table 11 below presents information on implemented construction activities

______Semi-annual Environmental Monitoring report, July – December 2018 36 Strengthening Technical and Vocational Education and Training ______

Table 11: Construction activities in Tourism and service lyceum in Dushanbe

CW01-02-B Rehabilitation of Tourism and Service Lyceum in Dushanbe

Month, 2018 Construction Activities

October Educational Building ➢ Construction of Concrete ramps ➢ Preliminarв smoothing of the аalls’ surface ➢ Improving of the front face of the building o Installation of rain gutters o Installation of drainage pipes ➢ Electrical works Canteen ➢ Earth works ➢ Construction of strip reinforced foundation

November Educational Building ➢ Masonry of separate sections of brick walls ➢ Installation of metal plastic windows ➢ Improving of the front face of the building o Plastering Canteen ➢ Construction of strip reinforced foundation

December Educational Building ➢ Preliminary smoothing of the аalls’ surface ➢ Preliminarв smoothing of the ceilings’ surface ➢ Painting the façades by improved façade paint ➢ Electrical works Canteen ➢ Masonry of brick walls

Total progress of construction work by end of December 2018 – 29%

40. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the Tourism and Service Lyceum in Dushanbe

______Semi-annual Environmental Monitoring report, July – December 2018 37 Strengthening Technical and Vocational Education and Training ______

Photo 68: Territory fenced, information and warning signs installed, Environmental documents are in place

Photo 69: First aid kit in place Photo 70: Containers for liquid waste is arranged

______Semi-annual Environmental Monitoring report, July – December 2018 38 Strengthening Technical and Vocational Education and Training ______

Photo 71: Internal finishing works Photo 72: Construction works of The canteen workers equipped with PPE

Photo 73: Internal finishing works in progress

______Semi-annual Environmental Monitoring report, July – December 2018 39 Strengthening Technical and Vocational Education and Training ______

Photo 74: Works on facade rehabilitation

2.3.11. Construction activities conducted on Technical Vocational Lyceum of Shahrinav 41. During the reporting period, construction work on the Technical Vocational Lyceum in Shahrinav has been 46% completed. The Table 12 below presents information on implemented construction activities

Table 12: Construction activities in Technical Vocational Lyceum in Shahrinav

CW01-02-С Rehabilitation of Lyceum in Shahrinav

Month, 2018 Construction Activities ➢ Dismantling works October ➢ Masonry of separate sections of brick walls ➢ Installation of metal plastic windows ➢ Roofing works o Installation of wooden rafters o Fire protection of wooden structures o Roofing by Galvanized Steel o Fencing the edge of the roof by railings ➢ Façade o Wall plastering using concrete-lime mortar

November ➢ Reinforcement foundations with monolithic reinforced concrete clips made my concrete M200 ➢ Installation of metal plastic windows in canteen ➢ Flooring o Preliminary smoothing of the flors ➢ Internal finishing works ➢ Façade o Wall plastering using concrete-lime mortar

______Semi-annual Environmental Monitoring report, July – December 2018 40 Strengthening Technical and Vocational Education and Training ______

➢ Electrical works ➢ Rehabilitation of internal water supply and sewerage system

December ➢ Internal finishing works o Installing ceramic tiles on cement mortar in the lobby and corridors ➢ Roofing works ➢ Façade o Wall plastering using concrete-lime mortar ➢ Electrical works

Total progress of construction work by end of December 2018 – 46%

42. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the Technical Vocational Lyceum in Shahrinav

Photo 75: Works on rehabilitation of the facade, workers equipped with Photo 76: Fire protection means PPE

______Semi-annual Environmental Monitoring report, July – December 2018 41 Strengthening Technical and Vocational Education and Training ______

Photo 77: Rehabilitation works in canteen

Photo 78: Warning signs installed Photo 79: Environmental Photo 80: Territory is fenced, documents are in place information sign installed 27.11.2018

2.3.12. Construction activities conducted on Construction Lyceum in Kulob 43. During the reporting period, construction work on the Construction Lyceum in Kulob has been 37% completed. The Table 13 below presents information on implemented construction activities

______Semi-annual Environmental Monitoring report, July – December 2018 42 Strengthening Technical and Vocational Education and Training ______

Table 13: Construction activities in Constructional Lyceum in Kulob

CW05-D Renovation of Construction Lyceum in Kulyab

Month, 2018 Construction Activities ➢ Dismantling works November ➢ Masonry of separate sections of brick walls ➢ Installation of metal plastic windows ➢ Installation of metal plastic windows ➢ Flooring works o Preliminarв smoothing of the floors’ surface ➢ Construction of Concrete ramps ➢ Dismantling works of internal water supply and sewerage system ➢ Electrical works

December ➢ Electrical works ➢ Internal finishing works o Plastering of walls surfaces with cement-lime mortar ➢ Roofing works ➢ Façade o Plastering of walls surfaces with cement-lime mortar

Total progress of construction work by end of December 2018 – 37%

44. Photos bellow shows progress of rehabilitation works and implementation of SSEMP in the Construction Lyceum in Kulob

Photo 83: Environmental Photo 81: Territory is fenced, Photo 82: workers equipped with documents are in place warning signs installed PPE

______Semi-annual Environmental Monitoring report, July – December 2018 43 Strengthening Technical and Vocational Education and Training ______

Photo 84: Territory is fenced, Photo 85: Demolishing works on Photo 86: Demolishing works on warning signs are installed Canteen workshop

2.3.13. Construction activities conducted on Agricultural Lyceum of Kulob (Dahana) 45. During the reporting period, construction work on the Agricultural Lyceum in Kulob (Dahana) has been 25% completed. The Table 14 below presents information on implemented construction activities

Table 14: Construction activities in Agricultural Lyceum in Kulob (Dahana)

CW05-D Renovation of Agricultural Lyceum in Kulob (Dahana)

Month, 2018 Construction Activities

November ➢ Earth works for workshop building ➢ Construction of strip reinforced foundation for workshop building ➢ Dismantling works in dormitory ➢ Electrical works ➢ Masonry of walls for workshop December ➢ Installation metal plastic windows in the dormitory building Total progress of construction work by end of December 2018 – 25%

46. Photos below shows progress of rehabilitation works and implementation of SSEMP in the Agricultural Lyceum in Kulob

______Semi-annual Environmental Monitoring report, July – December 2018 44 Strengthening Technical and Vocational Education and Training ______

Photo 87: Territory is fenced, informational and warning signs are installed, environmental documents are in place

Photo 88: External works on dormitory Photo 89: Construction works of the workshop November 2018

2.3.14. Construction activities conducted on Technical Vocational Lyceum of Vose 47. During the reporting period, construction work on the Technical Vocational Lyceum of Vose has been 30% completed. The Table 15 below presents information on implemented construction activities

______Semi-annual Environmental Monitoring report, July – December 2018 45 Strengthening Technical and Vocational Education and Training ______

Table 15: Construction activities in Technical Vocational Lyceum in Vose

CW05-D Renovation of Technical Vocational Lyceum of Vose

Month, 2018 Construction Activities ➢ Dismantling works November ➢ Installation of metal plastic windows ➢ Plastering of walls surfaces with cement mortar M150 ➢ Roofing works • Leveling screed of cement-sand solution m 150 thickness. 30 mm PL-1, PL-2, PL-3

December ➢ Internal finishing works o Plastering of walls surfaces with cement-lime mortar ➢ Roofing works ➢ Façade o Plastering of walls surfaces with cement-lime mortar ➢ Electrical works

Total progress of construction work by end of December 2018 – 30%

48. Photos below shows progress of rehabilitation works and implementation of SSEMP in the Technical Vocational Lyceum in Vose

Photo 90: Territory is fenced, informational and warning signs installed

______Semi-annual Environmental Monitoring report, July – December 2018 46 Strengthening Technical and Vocational Education and Training ______

Photo 92: Fire protection means are in place Photo 91: Environmental documents are in place

2.3.15. Construction activities conducted on Technical Vocational Lyceum in Tojikobod 49. During the reporting period, construction work on the Technical Vocational Lyceum in Tojikobod has been 41% completed. The Table 16 below presents information on implemented construction activities.

Table 16: Construction activities in Technical Vocational Lyceum in Tojikobod

CW05-D Renovation of Technical Vocational Lyceum of Tojikobod

Month, 2018 Construction Activities ➢ Dismantling works November ➢ Installation of metal plastic windows ➢ Installation of metal plastic doors ➢ Plastering of walls surfaces with cement-lime mortar ➢ Electrical works ➢ Well Drilling o Rotary drilling of wells with direct washing o Fastening of a well at rotary drilling by pipes with welded connection o Cementing of the grinding space with a set of drilling equipment and cement installation ➢ Internal finishing works December ➢ Plastering of walls surfaces with cement-lime mortar ➢ Earth works for constructing a cesspool

______Semi-annual Environmental Monitoring report, July – December 2018 47 Strengthening Technical and Vocational Education and Training ______

➢ Construction of water tower Total progress of construction work by end of December 2018 – 41%

50. Photos below shows progress of rehabilitation works and implementation of SSEMP in the Technical Vocational Lyceum in Tojikobod

Photo 93: Facade works completed

Photo 94: Internal finishing works are in progress

______Semi-annual Environmental Monitoring report, July – December 2018 48 Strengthening Technical and Vocational Education and Training ______

21.12.2018

2.3.16. Construction activities conducted on Technical Vocational Lyceum of Shugnon 51. During the reporting period, construction work on the Technical Vocational Lyceum of Shugnon has been 31% completed. The Table 17 below presents information on implemented construction activities

Table 17: Construction activities in Technical Vocational Lyceum in Shugnon

CW05-D Renovation of Technical Vocational Lyceum of Shugnon

Month, 2018 Construction Activities ➢ Dismantling works December ➢ Installation of metal plastic windows ➢ Masonry of separate sections of brick walls ➢ Roofing works Total progress of construction work by end of December 2018 – 31%

52. Photos below show progress of rehabilitation works and implementation of SSEMP in the Technical Vocational Lyceum in Shugnon

______Semi-annual Environmental Monitoring report, July – December 2018 49 Strengthening Technical and Vocational Education and Training ______

Photo 95: Roofing works in progress, December 2018

2.3.17. Construction activities conducted on Adult Learning Center of Farkhor 53. During the reporting period, construction work on the The Adult Learning Center of Farkhor has just started and has been 10% completed. The Table 18 below presents information on implemented construction activities.

Table 18: Construction activities in Adult Learning center of Farkhor

CW05-D Renovation of The Adult Learning Center of Farkhor

Month Construction Activities ➢ Dismantling works December

Total progress of construction work by end of December 2018 – 10%

54. Photos below shows progress of rehabilitation works and implementation of SSEMP in the Adult learning center in Farkhor

______Semi-annual Environmental Monitoring report, July – December 2018 50 Strengthening Technical and Vocational Education and Training ______

Photo 96: Territory is fenced, informational and warning signs installed Photo 97: The reinforcement works of the existing walls November 2018

______Semi-annual Environmental Monitoring report, July – December 2018 51 Strengthening Technical and Vocational Education and Training ______

III. ENVIRONMENTAL MANAGEMENT 3.1. General Description of Environmental Safeguard Activities

55. The Project administration group (PAG) is responsible to carry out day-to-day management of project execution. The PAG includes an Environmental and Social Safety specialist and Environmental and Social Safety Consultant whose responsibilities include the management of all environmental and social aspects of the project. Environmental Safeguards team of the PAG is responsible for supervising the construction works in relation to environmental impact and, in particular, for supervising and reporting on the Contractor’s performance in the implementation of the EMP.

3.2. Site audits

56. The overall objective of the audits is to ensure good environmental practice in project operations, and enable PAG to establish good governance and efficient environmental management of day to day activities. Site inspections and audits in the reporting period are shown in Table 19 below. In three facilities - the Resource Centers of Bokhtar, Kulyab and Khujand, the rehabilitation works have been completed; a post-construction audit has been done and the results are provided in Appendix 1.

______Semi-annual Environmental Monitoring report, July – December 2018 52 Strengthening Technical and Vocational Education and Training ______

Table 19: Site visits and audits in the reporting period

№ Date Object Auditors Purpose of Audit Summary of any Findings

1 08.08.2018 CW14-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Regional Resource Centre in STVET PAG fulfillment of the and environmental safeguards can be Bokhtar requirements of the considered as satisfactory Kamilova L. SSEMP during Technical Vocational lyceum in STVET PAG construction works Bokhtar

6.09.2018 CW14-A Rehabilitation of Dadobaev D. Completion Audit The contractor completed Regional Resource Centre in STVET PAG reinstatement of the site after Bokhtar completion of construction activities. Kamilova L. STVET PAG Karimov D. GOPA, CAICO

28.09.2018 CW14-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Regional Resource Centre in STVET PAG fulfillment of the and environmental safeguards can be Bokhtar requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works Karimov D. GOPA, CAICO

2 15.08.018 CW14-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Regional Resource Centre in STVET PAG fulfillment of the and environmental safeguards can be Khujand requirements of the considered as satisfactory Kamilova L. SSEMP during Professional vocational service STVET PAG construction works Lyceum in Khujand

04.09.2018 CW14-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Regional Resource Centre in STVET PAG fulfillment of the and environmental safeguards can be Khujand requirements of the considered as satisfactory Kamilova L. STVET PAG

______Semi-annual Environmental Monitoring report, July – December 2018 53 Strengthening Technical and Vocational Education and Training ______

SSEMP during construction works

25.09.2018 CW14-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Regional Resource Centre in STVET PAG fulfillment of the and environmental safeguards can be Khujand requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works Karimov D. GOPA, CAICO

3 08.08.2018 CW14-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Regional Resource Centre in STVET PAG fulfillment of the and environmental safeguards can be Kulyab requirements of the considered as satisfactory Kamilova L. SSEMP during Professional vocational STVET PAG construction works construction Lyceum in Kulyab Karimov D. GOPA, CAICO

06.09.2018 CW14-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Regional Resource Centre in STVET PAG fulfillment of the and environmental safeguards can be Kulyab requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

28.09.2018 CW14-C Rehabilitation of Dadobaev D. Completion Audit The contractor completed Regional Resource Centre in STVET PAG reinstatement of the site after Kulyab completion of construction activities. Kamilova L. STVET PAG Karimov D. GOPA, CAICO

17.10.2018 CW14-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Regional Resource Centre in STVET PAG fulfillment of the and environmental safeguards can be Kulyab requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 54 Strengthening Technical and Vocational Education and Training ______

Karimov D. GOPA, CAICO

4 15.05.2018 CW12-1 -A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Polytechnic Lyceum in Khujand* STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Clean Energy Kamilova L. SSEMP during STVET PAG construction works

04.09.2018 CW12-1 -A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Polytechnic Lyceum in Khujand STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

25.09.2018 CW12-1 -A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Polytechnic Lyceum in Khujand STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

22.10.2018 CW12-1 -A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Polytechnic Lyceum in Khujand STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

5 28.08.2018 CW12-2-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe* Clean Energy requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

31.08.2018 CW12-2-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe* requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 55 Strengthening Technical and Vocational Education and Training ______

20.09.2018 CW12-2-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

08.10.2018 CW12-2-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

30.10.2018 CW12-2-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

05.11.2018 CW12-2-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

19.11.2018 CW12-2-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

30.11.2018 CW12-2-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 56 Strengthening Technical and Vocational Education and Training ______

6 14.09.2018 CW01-02-A Rehabilitation of Dadobaev D. Audit of mobilization of Mobilization of construction works is Auto Transport Lyceum in STVET PAG construction works ongoing. The Contractor has been Dushanbe instructed to Environmental and social Kamilova L. requirements STVET PAG

04.10.2018 CW01-02-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Auto Transport Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG - construction works Workers equipped аith PPE but don’t wear it, Contractor has been orally warned to control this issue

16.10.2018 CW01-02-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Auto Transport Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

05.11.2018 CW01-02-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Auto Transport Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

19.11.2018 CW01-02-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Auto Transport Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

30.11.2018 CW01-02-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Auto Transport Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 57 Strengthening Technical and Vocational Education and Training ______

20.12.2018 CW01-02-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Auto Transport Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

7 04.10.2018 CW01-02-B Rehabilitation of Dadobaev D. Audit of mobilization of Mobilization of construction works is Tourism and Service Lyceum in STVET PAG construction works, ongoing. The Contractor has been Dushanbe instructed to Environmental and social Kamilova L. requirements STVET PAG

05.11.2018 CW01-02-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Tourism and Service Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

19.11.2018 CW01-02-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Tourism and Service Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

30.11.2018 CW01-02-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Tourism and Service Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

20.12.2018 CW01-02-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Tourism and Service Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 58 Strengthening Technical and Vocational Education and Training ______

8 04.10.2018 CW01-02-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Lyceum in Shahrinav STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

16.10.2018 CW01-02-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Lyceum in Shahrinav STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

15.11.2018 CW01-02-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Lyceum in Shahrinav STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

27.11.2018 CW01-02-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Lyceum in Shahrinav STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

9 30.10.2018 CW01-01-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

05.11.2018 CW01-01-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 59 Strengthening Technical and Vocational Education and Training ______

14.11.2018 CW01-01-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

19.11.2018 CW01-01-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

30.11.2018 CW01-01-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

21.12.2018 CW01-01-A Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in STVET PAG fulfillment of the and environmental safeguards can be Dushanbe requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

10 05.11.2018 CW01-01-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Polytechnic Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

14.11.2018 CW01-01-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Polytechnic Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 60 Strengthening Technical and Vocational Education and Training ______

30.11.2018 CW01-01-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Polytechnic Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

20.12.2018 CW01-01-B Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Polytechnic Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

11 30.10.2018 CW01-01-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Sewing Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

05.11.2018 CW01-01-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Sewing Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

14.11.2018 CW01-01-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Sewing Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

14.11.2018 CW01-01-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Sewing Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be (Dormitory) requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 61 Strengthening Technical and Vocational Education and Training ______

30.11.2018 CW01-01-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Sewing Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. Гл SSEMP during STVET PAG construction works

30.11.2018 CW01-01-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Sewing Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. Ощт SSEMP during STVET PAG construction works

20.12.2018 CW01-01-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Sewing Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Ощт Kamilova L. SSEMP during STVET PAG construction works

21.12.2018 CW01-01-C Rehabilitation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Sewing Lyceum in Dushanbe STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Гл Kamilova L. SSEMP during STVET PAG construction works

12 14.12.2018 CW05-A Minor Renovation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs ALC Branch in Farhor STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works Karimov D. GOPA, CAICO

13 14.12.2018 CW05-B Minor Renovation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Lyceum in Vose STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works

______Semi-annual Environmental Monitoring report, July – December 2018 62 Strengthening Technical and Vocational Education and Training ______

Karimov D. GOPA, CAICO

14 14.12.2018 CW05-C Minor Renovation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Agricultural Lyceum in Kulyab STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works Karimov D. GOPA, CAICO.

15 14.12.2018 CW05-D Renovation of Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs Construction Lyceum in Kulyab STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works Karimov D. GOPA, CAICO

16 21.12.2018 CW07-01-А Minor rehabilitation Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs of lyceum in Tojikobod STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works Karimov D. GOPA, CAICO

17 25.12.2018 CW07-02-A Minor rehabilitation Dadobaev D. Monitoring of the The implementation of EMP/SSEMPs of lyceum in Shugnon STVET PAG fulfillment of the and environmental safeguards can be requirements of the considered as satisfactory Kamilova L. SSEMP during STVET PAG construction works Karimov D. GOPA, CAICO

______Semi-annual Environmental Monitoring report, July – December 2018 63 Strengthening Technical and Vocational Education and Training ______

3.3 Non-conformance notices

57. There was no non-compliance observed and/or issued during the reporting period.

58. No complaints were received and recorded for reporting period from local people or other stakeholders.

59. No corrective action plan has been proposed for July-December 2018, for the previous subprojects finished by the end of May 2018 and new sub-projects started in July 2018.

______Semi-annual Environmental Monitoring report, July – December 2018 64 Strengthening Technical and Vocational Education and Training ______

IV. ENVIRONMENTAL MONITORING 60. According to IEE/EMP/SSEMP, no parameters of water, air and noise are planned to be instrumentally measured. During the routine works, no harmful impacts are expected.

4.1. Water quality monitoring

61. No instrumental measurements of water quality are foreseen for this Project according to IEE/EMP. The Project does not impact water bodies as all works will be implemented at the relevant distance from water sources and inside the fenced area of rehabilitated institutions buildings, which are existing infrastructures. During field visits to the sub-project sites were not observed any spills or discharge of contaminants in water objects

4.2. Air quality monitoring

62. No instrumental measurements of air quality are foreseen for this Project according to IEE/EMP.

63. No any significant dust emissions during the works within the reporting period were observed in the sub-project sites.

64. The vehicles of Contractors transported construction materials were covered by tarpaulin.

65. No dust was observed at construction sites.

4.3. Noise and vibrations monitoring

66. A regular instrumental monitoring of noise and vibrations is not foreseen for this Project according to IEE/EMP. However, the construction contractor is obliged to take care that workers shall wear ear protectors when loud drilling works.

67. The field visits to the sub-project sites revealed that Contractor’s аorkers аere аearing PPE in compliance with the requirements.

4.4. Flora and fauna monitoring

68. A monitoring of flora and/or fauna is not foreseen for this Project according to IEE/EMP. All works take place within the fenced area of sub-project institutions and learning centers. All rehabilitation measures are being implemented within the facilities and building constructions of the institutions.

4.5. Waste management

69. Construction works generate different type wastes starting from garbage, recycle waste, house hold waste and construction and demolition debris, including, ACM waste in the sites where the asbestos-cement slate have been used as roofing material before rehabilitation. Waste Management Plan was developed by Contractors and approved by STVET PAG.

______Semi-annual Environmental Monitoring report, July – December 2018 65 Strengthening Technical and Vocational Education and Training ______

70. Construction waste is accumulated on construction site in special isolated areas divided by hazardous, domestic and construction waste. There were installed containers for liquid waste . Proper signs are installed. Construction Company has signed contract with the companies for waste removal (SUE Khojagii Manziliyu Kommunali (KhMK)). The waste is being removed from construction site by authorized personal only in accordance of safety regulations.

71. During the reporting period, contractors collected information only on the amount of toxic waste such as AСM. The volume of toxic waste in the form of AСM amounted to a total of - 4041 m3.

72. Concrete debris generated during demolition works, as far as possible have been reused. Monitoring of waste management issues is being carried out by contractor environmental specialist and by environmental specialists of PAG.

73. During site visits bв PAG environmental specialists аeren’t observed anв nonconformance associated with waste management.

4.6. ACM management plan

74. An Asbestos Containing Materials Handling, Management and Disposal Plan was developed by Contractors and approved by STVET PAG.

75. The ACM have been removed by specially trained workers of Contractor. All necessary ASM handling safeguards have been undertaken. Removed ACM has been arranged with two layers of Polyethylene, area is fenced and appropriate warning signs installed.

76. The Construction Company collects ACM at the temporary storage sites and handed over it to Lyceums for a further write-off and disposal procedure.

4.7. Health and safety Plan

77. The Contractors took all precautions at all construction points for health and safety of the workers and the people of the surroundings in accordance to the Health and Safety Plan submitted by the Contractor and approved by the PAG. Health and Safety measures were continuously taken care and checked in all construction points by the health and safety manager of the Contractor and checked by the Environmental and social guarantee staff of the PAG. No accident or incident have been recorded during the period.

______Semi-annual Environmental Monitoring report, July – December 2018 66 Strengthening Technical and Vocational Education and Training ______

5. FUNCTIONING OF THE SSEMP 78. All rehabilitation objects are included in the project scope after project’s approval bв ADB. ADB has approved additional scope of work for every sub-project, for which the Due Diligence Reports has been prepared by the MOLME/PAG as well as approved by ADB.

79. Contractors prepared the SSEMPs which were approved by PAG. Status of SSEMPs for each sub-project construction site is provided in Table 20 below. Each contractor appointed Chief engineer as ES - responsible person for implementation of environmental safeguards requirements.

Table 20: Status of SSEMPs for reporting period from July to December 2018

Management Plan Status Note Contractor LLC Gayrat M Environmental Management Plan/Site-Specific EMP SSEMPs Scan letter from (SSEMP) with Annexes - Waste management plan for revised and approved PIG with approval construction phase, Emergency response plan, by PAG in 16 July 2018 of SSEMP is in Health and Safety protection plan, Plan for place consideration of Complaints, Dust control plan, Noise management plan, Monitoring, ACM Management plan, traffic and road safety management plan, for: - Regional resource centre in Kulob, - Regional resource centre in Khujand - Regional resource centre in Bokhtar

Contractor OJSC Imoratsoz Environmental Management Plan/Site-Specific EMP SSEMPs Scan letter from (SSEMP) with Annexes - Waste management plan for revised and approved PIG with approval construction phase, Emergency response plan, by PAG in 30 July 2018 of SSEMP is in Health and Safety protection plan, Plan for place consideration of Complaints, Dust control plan, Noise management plan, Monitoring, traffic and road safety management plan, for: - Polytechnic Lyceum in Khujand, Clean energy

Contractor LLC Ijrokor Environmental Management Plan/Site-Specific EMP SSEMPs Scan letter from (SSEMP) with Annexes - Waste management plan for revised and approved PIG with approval construction phase, Emergency response plan, by PAG in 13 August of SSEMP is in Health and Safety protection plan, Plan for 2018 place consideration of Complaints, Dust control plan, Noise management plan, Monitoring, ACM Management plan, traffic and road safety management plan, for:

- Construction Lyceum in Dushanbe, Clean energy

Contractor OJSC Soleh I Kompaniya

______Semi-annual Environmental Monitoring report, July – December 2018 67 Strengthening Technical and Vocational Education and Training ______

Environmental Management Plan/Site-Specific EMP SSEMPs Scan letter from (SSEMP) with Annexes - Waste management plan for revised and approved PIG with approval construction phase, Emergency response plan, by PAG in 11 of SSEMP is in Health and Safety protection plan, Plan for September 2018 place consideration of Complaints, Dust control plan, Noise management plan, Monitoring, ACM Management plan, traffic and road safety management plan, for: - Autotransport Lyceum in Dushanbe - Tourism and service lyceum in Dushanbe - Technical Vocational Lyceum in Shahrinav

Contractor OJSC Navbunyod Environmental Management Plan/Site-Specific EMP SSEMPs Scan letter from (SSEMP) with Annexes - Waste management plan for revised and approved PIG with approval construction phase, Emergency response plan, by PAG in 15 October of SSEMP is in Health and Safety protection plan, Plan for 2018 place consideration of Complaints, Dust control plan, Noise management plan, Monitoring, ACM Management plan, traffic and road safety management plan, for: - Polytechnic Lyceum in Dushanbe - Construction lyceum in Dushanbe - Sewing Lyceum in Dushanbe Contractor CJSC Sugdi SH Environmental Management Plan/Site-Specific EMP SSEMPs Scan letter from (SSEMP) with Annexes - Waste management plan for revised and approved PIG with approval construction phase, Emergency response plan, by PAG in 31 October of SSEMP is in Health and Safety protection plan, Plan for 2018 place consideration of Complaints, Dust control plan, Noise management plan, Monitoring, ACM Management plan, traffic and road safety management plan, for: - Technical Vocational Lyceum in Tojikobod Contractor LLC Somon International Environmental Management Plan/Site-Specific EMP SSEMPs Scan letter from (SSEMP) with Annexes - Waste management plan for revised and approved PIG with approval construction phase, Emergency response plan, by PAG in 31 October of SSEMP is in Health and Safety protection plan, Plan for 2018 place consideration of Complaints, Dust control plan, Noise management plan, Monitoring, ACM Management plan, traffic and road safety management plan, for: ─ Technical Vocational Lyceum in Shugnon ─ Contractor LLC Somon International Environmental Management Plan/Site-Specific EMP SSEMPs Scan letter from (SSEMP) with Annexes - Waste management plan for revised and approved PIG with approval construction phase, Emergency response plan, by PAG in 15 of SSEMP is in Health and Safety protection plan, Plan for November 2018 place consideration of Complaints, Dust control plan, Noise management plan, Monitoring, ACM Management plan, traffic and road safety management plan, for:

______Semi-annual Environmental Monitoring report, July – December 2018 68 Strengthening Technical and Vocational Education and Training ______

─ Technical Vocational Lyceum in Vose ─ Construction Lyceum in Kulob ─ Agricultural Lyceum in Kulob (Dahana) ─ ALC in Farkhor

80. Summary of application of mitigation measures for all construction sites during construction works is presented in Table 21

Table 21: Implementation of SSEMPs‘ mitigation measures

Potential Proposed mitigation measures Status of implementation the impacts mitigation measures

Temporary Ensure that the maximum and equivalent Project activities are limited to increase of noise levels comply with sanitary rehabilitation (i.e. minor background noise regulations. construction) of facilities, and noise and vibration due exposure is expected to be minimal. construction works Mitigation measures are taken to ensure minimum noise and dust emissions, and workers are provided with appropriate PPE to ensure safety.

Monitor and address complaints about the Not any complaints about noise noise level. level have been received

Construction works will be limited to Construction works was limited to restricted times agreed to in the permit restricted times from 9 am to 6 pm

Creation of dust Ensure that the quality of air at construction Project activities are limited to emissions and sites is in line with sanitary norms and rehabilitation (i.e. minor volatile organic regulations. construction) of facilities, and air compounds at exposure is expected to be minimal. construction site Mitigation measures are taken to while dismantling ensure minimum noise and dust work, emissions, and workers are transportation of provided with appropriate PPE to construction ensure safety. materials and waste Monitor dust emissions to ensure Mitigation measures (water emissions are minimized. spraying, dust screen) to reduce dust emission were implemented.

Monitor and address complaints about dust Not any complaints have been / volatile organic compounds and other received pollutants

Construction works will be limited to Construction works was limited to restricted times restricted times from 9 am to 6 pm

______Semi-annual Environmental Monitoring report, July – December 2018 69 Strengthening Technical and Vocational Education and Training ______

Providing the construction workers with PPE for workers have been suitable personal protective equipment provided (respirators)

There will be no open burning of Not any burning of waste or idling of construction / waste material at the site construction vehicles at the site observed There will be no excessive idling of construction vehicles at sites

Keep surrounding environment (side- implemented walks, roads) free of debris to minimize dust

Suppress dust during pneumatic implemented drilling/wall destruction by ongoing water spraying and/or installing dust screen enclosures at site

Construction Waste disposal facilities are available. implemented waste

Boxes for construction debris will be Waste boxes have been installed in the site. installed

The construction waste will be disposed according to general EMP requirements

Construction waste will be collected and Have been contracted disposed properly by licensed collectors with communal service to waste removal Timely sorting of rehabilitated and removing construction waste in an organized way, and disposal them on an authorized land field

Mineral construction and demolition wastes implemented will be separated from general refuse, organic, liquid and chemical wastes by on- site sorting and stored in appropriate containers

Dispose off waste appropriately to prevent Waste have been pollution of soil and groundwater disposed appropriately, not any spill of liquid have been observed

The approach to handling sanitary wastes implemented and wastewater from building sites (installation or reconstruction) must be approved by the local authorities

______Semi-annual Environmental Monitoring report, July – December 2018 70 Strengthening Technical and Vocational Education and Training ______

Recycle valuable materials within the Recyclable materials project or sold. have been used or handed over to lyceums

Aim to minimize waste through reducing and re-using (packaging) material

Prevent littering by construction staff at Waste bins have been work sites by providing bins or waste bags installed in sufficient in sufficient locations. quantity and location. Not any littering have been

observed in the site The records of waste disposal will be maintained as proof for proper management as designed

Toxic / hazardous Temporarily storage on site of all Not any toxic waste have been waste hazardous or toxic substances will be in observed in the site management safe containers labeled with details of composition, properties and handling information The containers of hazardous substances should be placed in an leak-proof container to prevent spillage and leaching The wastes will be transported by specially licensed carriers and disposed in a licensed facility Paints with toxic ingredients or solvents or lead-based paints will not be used

Soil contamination Construction materials that can impact the Construction materials that can due to accidental soil should be kept in a special premise or spill or can impact the soil have spillage in concrete ground. been kept in concrete ground • Contractor's personnel works in such a way as to avoid erosion and soil Not any soil erosion or spillage of contamination and avoid subsidence, as materials to soil have been well as contamination of the water flumes observed and irrigation canals;

• All measures on protection of soil erosion and contamination will be carried The territory have been improved out in accordance with the contract and and all vegetation layer on the the Engineer's instructions; territory restored. • The vegetation layer on the territory of the structure will be immediately restored if it is damaged.

Asbestos Ensure that the standard practice of Roofing material - asbestos containing handling existing asbestos containing cement slate, have been removed materials (ACM) materials is used to remove and and disposed accordance the ACM management plan.

______Semi-annual Environmental Monitoring report, July – December 2018 71 Strengthening Technical and Vocational Education and Training ______

decommission asbestos containing roofing materials.

Not any new ACM used in the site ACM will not be used as a roofing/new material in construction works of building.

Any existing ACM to be handled and disposed according to the ACM management plan

Health and labor • The local construction and Have been contracted with medical safety environment inspectorates have been centers. (occupational notified of upcoming activities

hazards) – during • All legally required permits have construction and been acquired for construction and/or All required permits have been operation rehabilitation received • All work will be carried out in a safe and disciplined manner designed to minimize impacts on neighboring residents All appropriate signs have been and environment. installed • Workers will comply with international good practice - providing the construction workers with suitable personal Not any accident have been protective equipment (always hardhats, as registered needed masks and safety glasses, harnesses and safety boots) • Appropriate signposting of the sites will inform workers of key rules and regulations to follow. Following plans to be developed for construction and operation phases of the project: Emergency Response Plan and Health and Safety Plan

Direct or indirect Contractor will observe the necessary All vehicles of contractor have hazards to public precautions (speed limit, working hours been tested by CEP for exhaust traffic and from 7 am to 5 pm), will monitor the gas contamination pedestrians by exhaust gas content of its own vehicle

construction fleet. activities In compliance with national regulations the contractor will insure that the construction site is properly secured and construction related traffic regulated. This includes but is not limited to: Appropriate signs have been Signposting, warning signs, installed barriers and traffic diversions: site will be clearly visible and the public warned of all potential hazards Traffic management system developed and implemented

______Semi-annual Environmental Monitoring report, July – December 2018 72 Strengthening Technical and Vocational Education and Training ______

Traffic management system and staff training, especially for site access and near-site heavy traffic. Adjustment of working hours to local traffic patterns, e.g. avoiding major transport activities during rush hours

______Semi-annual Environmental Monitoring report, July – December 2018 73 Strengthening Technical and Vocational Education and Training ______

6. SUMMARY AND RECOMENDATIONS

81. To ensure proper control on environment in rehabilitation objects, monitoring activities were held by environmental consultant and specialist. Site visits were executed with approximatelly frequency 1 times per week. Impact mitigation measures and environmental protection actions were successfully implemented. To ensure health and safety measures the Contractor provided to its staffs all necessary sanitary conditions, drinking water, PPE, fire- protection means and relevant application of safety rules.

82. Warning signs and information boards were installed at site to avoid potential accident. The contractor of RRC in Kulob, Bokhtar and Khujand completed reinstatement of the site after completion of construction activities.

83. During period no any complaints were registered.

84. The implementation of EMP/SSEMPs and environmental safeguards issues from July to December 2018 can be considered as satisfactory, no Corrective Action Plan is necessary for the next reporting period.

85. Environmental specialists of PAG will continue monitoring of safeguards compliance.

______Semi-annual Environmental Monitoring report, July – December 2018 74 Strengthening Technical and Vocational Education and Training ______

Annex 1: Post-Construction Monitoring Check-lists Regional Resource Center in Bokhtar

______Semi-annual Environmental Monitoring report, July – December 2018 75 Strengthening Technical and Vocational Education and Training ______

______Semi-annual Environmental Monitoring report, July – December 2018 76 Strengthening Technical and Vocational Education and Training ______

Sub-project Regional Resource Center in Bokhtar

Photo 98: Main entrance before rehabilitation Photo 99: Main entrance after rehabilitation

Photo 100: The foyer before rehabilitation Photo 101: The foyer after rehabilitation

______Semi-annual Environmental Monitoring report, July – December 2018 77 Strengthening Technical and Vocational Education and Training ______

Photo 102: Teachers room before rehabilitation Photo 103: Teachers rooms after rehabilitation as meeting hall

Photo 104: Photo 5: Teachers room before rehabilitation

______Semi-annual Environmental Monitoring report, July – December 2018 78 Strengthening Technical and Vocational Education and Training ______

Photo 105: Teachers rooms after rehabilitation as meeting hall

Photo 106: Foyer before rehabilitation

Photo 107: Part of the foyer merged with Teachers room and converted to meeting hall

Photo 108: Classroom before rehabilitation

______Semi-annual Environmental Monitoring report, July – December 2018 79 Strengthening Technical and Vocational Education and Training ______

Photo 109: Classroom after rahbilitation

______Semi-annual Environmental Monitoring report, July – December 2018 80 Strengthening Technical and Vocational Education and Training ______

Regional Resource Center in Khujand

______Semi-annual Environmental Monitoring report, July – December 2018 81 Strengthening Technical and Vocational Education and Training ______

______Semi-annual Environmental Monitoring report, July – December 2018 82 Strengthening Technical and Vocational Education and Training ______

Sub-project Regional Resource Center in Khujand

Photo 110: Installation metal plastic windows in progress Photo 111: After installatin of metal plastic windows

Photo 112: Dismantling works on meeting hall in progress Photo 113: After rehabilitation of meeting hall

______Semi-annual Environmental Monitoring report, July – December 2018 83 Strengthening Technical and Vocational Education and Training ______

Photo 114: Rehabilitation of meeting hall in Photo 115: Meeting hall after rehabilitation progress

______Semi-annual Environmental Monitoring report, July – December 2018 84 Strengthening Technical and Vocational Education and Training ______

Photo 116: Administrative room before rehabilitation Photo 117: Administrative room after rehabilitation

______Semi-annual Environmental Monitoring report, July – December 2018 85 Strengthening Technical and Vocational Education and Training ______

Regional Resource Center in Kulyab

______Semi-annual Environmental Monitoring report, July – December 2018 86 Strengthening Technical and Vocational Education and Training ______

______Semi-annual Environmental Monitoring report, July – December 2018 87 Strengthening Technical and Vocational Education and Training ______

Sub-project Regional Resource Center in Kulyab

Photo 118: Façade of the RRC before rehabilitation Photo 119: Façade of the RRC after rehabilitation

Photo 121: Façade of the RRC after rehabilitation Photo 120: Façade of the RRC before rehabilitation

______Semi-annual Environmental Monitoring report, July – December 2018 88 Strengthening Technical and Vocational Education and Training ______

Photo 122: Façade of the RRC before rehabilitation Photo 123: Façade of the RRC after rehabilitation

Photo 124: Dismantling works in progress Photo 125: After installation of metal plastic windows

______Semi-annual Environmental Monitoring report, July – December 2018 89 Strengthening Technical and Vocational Education and Training ______

Photo 126: Corridors before rehabilitation

Photo 127: Corridors after rehabilitation

Photo 128: Classroon before rehabilitation Photo 129: Classroom after rehabilitation works as Meeting hall

______Semi-annual Environmental Monitoring report, July – December 2018 90 Strengthening Technical and Vocational Education and Training ______

Photo 130: Administrative room during rehabilitation works in Photo 131: Administrative room after rehabilitation progress

Photo 132: Meeting hall during rehabilitation in progress Photo 133: Meeting hall after rehabilitation