Resettlement Plan
Project Number: 44019-013 August 2017
PRC: Hubei Huangshi Urban Pollution Control and Environmental Management Project
Prepared by Huangshi Municipal Government for the Asian Development Bank.
2
This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
ADB-financed Hubei Huangshi Urban Pollution Control and Environmental Management Project (Mid-term Adjustment)
Resettlement Plan
Huangshi Municipal Government (HMG)
Huangshi PMO
MAY 2017
Contents
1. Overview of the Project ...... 7
1.1 Background of the Project ...... 7
1.2 Components and Resettlement Impacts ...... 7
1.3 Measures to Reduce Resettlement ...... 10
1.4 Estimated Resettlement Budget and Implementation Plan ...... 10
2. Impacts of the Project ...... 11
2.1 Scope of Impact Survey of LA and HD ...... 11
2.2 LA and HD Impacts ...... 12
2.2.1 Permanent LA ...... 12
2.2.2 Temporary Land Occupation ...... 13
2.2.3 Demolition of Residential Houses ...... 14
2.2.4 Demolition of Non-residential Properties ...... 17
2.2.5 Ground Attachments ...... 19
2.3 Other Impacts of the Project ...... 20
2.3.1 Affected Population ...... 20
2.3.2 Vulnerable Groups ...... 21
3. Socioeconomic Profile...... 23
3.1 Socioeconomic Profile of the Project Area ...... 23
3.1.1 Huangshi City ...... 23
3.1.2 Affected Villages / Communities ...... 23
3.2 Socioeconomic Profile of the Affected Population ...... 24
3.2.1 Permanent LA ...... 24
3.2.2 Affected Population ...... 25
3.2.3 Willingness Survey ...... 28
4. Legal Framework and Policies ...... 31
4.1 Laws, Regulations and Policies Applicable to Resettlement ...... 31
II 4.2 Objective and Principles of Resettlement ...... 31
4.2.1 Objective ...... 31
4.2.2 Principles ...... 31
4.3 Compensation Rates ...... 32
4.3.1 Permanent LA ...... 32
4.3.2 Demolition of Houses and Attachments ...... 32
4.3.3 Permanent Occupation of State-owned Land ...... 35
4.3.4 Temporary Occupation of State-owned Land ...... 35
4.4 Attachments and Scattered Trees ...... 35
4.5 Fund Disbursement and Schedule ...... 37
4.6 matrix of right ...... 37
5. Resettlement and Income Restoration ...... 41
5.1 Resettlement Program for Permanent LA ...... 41
5.1.1 Cash Compensation ...... 41
5.1.2 Endowment Insurance for LEFs ...... 42
5.1.3 Nonagricultural Employment Promotion ...... 43
5.1.4 Skills Training ...... 44
5.2 Compensation for Fishpond Contractors ...... 45
5.2.1 Basic Information ...... 45
5.2.2 Compensation and Resettlement ...... 45
5.3 Resettlement Program for Demolished Residential Houses ...... 46
5.3.1 Cash Compensation ...... 46
5.4 Resettlement Program for Demolished Non-residential Properties ...... 49
5.5 Women’s Development ...... 51
5.6 Assistance Measures for Vulnerable Groups ...... 51
5.7 Restoration Program for Infrastructure and Ground Attachments ...... 52
6. Organizational Structure ...... 53
6.1 Resettlement Implementation and Management Agencies ...... 53
6.1.1 Organizational Setup ...... 53
III 6.1.2 Organizational Responsibilities ...... 53
6.1.3 Organizational Chart ...... 55
6.2 Staffing and Equipment ...... 56
6.2.1 Staffing ...... 56
6.2.2 Equipment ...... 57
6.2.3 Organizational Training Program ...... 57
7. Public Participation and Grievance Redress...... 60
7.1 Public Participation ...... 60
7.1.1 Public Participation at the Preparation Stage ...... 60
7.1.2 Public Participation at the Implementation Stage ...... 61
7.2 Grievance Redress ...... 62
8. Resettlement Budget ...... 67
8.1 Resettlement Budget ...... 67
8.2 Resettlement Investment Schedule and Funding Sources ...... 67
8.3 Disbursement and Management of Resettlement Funds ...... 73
8.3.1 Disbursement of Resettlement Funds ...... 73
8.3.2 Management of Resettlement Funds ...... 73
9. Resettlement Implementation Plan ...... 75
9.1 Principles for Resettlement Implementation ...... 75
9.2 Resettlement Implementation Schedule ...... 75
10. Monitoring and Evaluation ...... 79
10.1 Internal Monitoring ...... 79
10.2 External Monitoring ...... 80
10.2.1 Scope and Methods ...... 80
10.2.2 Reporting ...... 81
10.3 Post-resettlement Evaluation ...... 82
Appendix 1: RIB ...... 83
Appendix 2: TORs for External M&E ...... 99
Appendix 3: Minutes of Public Participation Meetings ...... 105
IV Appendix 4: Identification of Vulnerable Households ...... 106
Appendix 5: Small-amount Loan Incentive Mechanism of Huangshi City (Abstract) ...... 109
Appendix 6: Fieldwork Photos ...... 110
Appendix 7: Note on Resettlement for Lake Ecology Rehabilitation (Phase 2) ...... 111
Appendix 8: Reply of the Huangshi Municipal Land and Resources Bureau on Preliminary Land Examination for Downstream Wetland Construction ...... 112
Appendix 9: Laws, Regulations and Policies Applicable to Resettlement ...... 114
Appendix 10: Interview Minutes ...... 121
Appendix 11: Summary of HD Compensation Fees in Xisaishan District ...... 127
Appendix 12: Summary of HD Compensation Fees in Xialu District ...... 135
List of tables
table 1-1 Summary of Adjustments to Components ...... 8
table 1-2 Summary of Adjusted Components ...... 9
table 2-1 Range of Resettlement Impacts ...... 11
table 2-2 Permanently Occupied State-owned Land...... 12
table 2-3 State-owned Land to be Permanently Occupied ...... 13
table 2-4 Land to be Temporarily Occupied...... 13
table 2-5 Impacts of Demolition of Residential Houses ...... 14
table 2-6 Impacts of Demolition of Non-residential Properties ...... 18
table 2-7 Affected Ground Attachments ...... 19
table 2-8 Summary of Affected Population ...... 21
table 2-9 Summary of Affected Vulnerable Groups ...... 22
table 3-1 Socioeconomic Profile of Huangshi City (2015) ...... 23
table 3-2 Socioeconomic Profile of the Affected Communities...... 24
table 3-3 Summary of Acquired Collective Land (by group) ...... 25
table 3-4 Summary of Acquired Collective Land (by component) ...... 25
table 3-5 Basic Sample Information ...... 25
table 3-6 Income and Expenditure of AHs in Xialu District ...... 27
V table 3-7 Income and Expenditure of AHs in Xisaishan District ...... 27 table 3-8 Demographics of Sample Population ...... 28 table 3-9 Statistics of Willingness Survey on Households affected by HD ...... 29 table 3-10 Statistics of Willingness Survey on Households affected by LA ...... 29 table 4-1 LA Compensation Rates ...... 32 table 4-2 HD Compensation Rates ...... 33 table 4-3 Benchmark Compensation Rates for Main Houses ...... 34 table 4-4 Benchmark Compensation Rates for House Attachments ...... 34 table 4-5 Compensation Rates for Exterior Decoration of Main Houses ...... 34 table 4-6 Reward for Main Houses ...... 35 table 4-7 Compensation Rates for Attachments ...... 35 table 4-8 Compensation Rates for Trees ...... 37 table 4-9 Matrix of right ...... 39 table 5-1 LA Compensation Rates ...... 42 table 5-2 Summary of Expected Employment under the Project ...... 44 table 5-3 Resettlement Program for Demolished Non-residential Properties ...... 49 table 5-4 Support for Vulnerable Groups ...... 52 table 6-1 Resettlement Agencies and Staffing ...... 56 table 6-2 Staffing and Working Schedule of Resettlement Agencies ...... 57 table 6-3 Equipment of Resettlement Agencies ...... 57 table 6-4 Resettlement Training Schedule ...... 58 table 7-1 Public Participation at the Preparation Stage...... 60 table 7-2 Public Participation Plan ...... 61 table 7-3 Registration Form of Grievances and Appeals...... 63 table 7-4 Contact Information for Grievances and Appeals ...... 64 table 8-1 Resettlement Investment Plan ...... 68 table 8-2 Resettlement Budget ...... 69 table 9-1 Resettlement Implementation Schedule ...... 75 table 10-1 Resettlement M&E Schedule ...... 82
VI
List of figure
Figure 2-1 Current Situation of Collective Land to be Acquired ...... 12
Figure 2-2 Current Situation of Residential Houses to be Demolished ...... 17
Figure 2-3 Current Situation of Non-residential Properties to be Demolished ...... 19
Figure 5-1 Current Situation of Land to be Acquired ...... 42
Figure 5-2 List of Subjects of Endowment Insurance in Baitayan Village ...... 43
Figure 5-3 Employment Information Release in a Community ...... 44
Figure 5-4 Location of Huangjinshan Development Zone ...... 46
Figure 5-5 Final Effects of the Jinguangsha Resettlement Community ...... 48
Figure 5-6 Location of the Jinguangsha Resettlement Community ...... 48
Figure 5-7 Items around the sale of real estate distribution map ...... 49
Figure 6-1 Organizational Chart ...... 56
Figure 7-1 LA Announcement and HD Appraisal Result Disclosure ...... 62
Figure 7-2 Community-based Grievance Redress Mechanism ...... 65
Figure 8-1 Resettlement Disbursement Flowchart ...... 73
VII Abbreviations
ADB - Asian Development Bank
AH - Affected Household
AP - Affected Person
DMS - Detailed Measurement Survey
FGD - Focus Group Discussion
HD - House Demolition
HMG - Huangshi Municipal Government
Huangshi Urban Construction Investment HUCIC - Company
LA - Land Acquisition
LEF - Land-expropriated Farmer
M&E - Monitoring and Evaluation
MLS - Minimum Living Security
PMO - Project Management Office
PRC - People’s Republic of China
RIB - Resettlement Information Booklet
RP - Resettlement Plan
Units
Currency unit = Yuan (CNY)
1.00 yuan = $0.15
1 hectare = 15 mu
VIII
Executive Summary
1. Introduction
In 2012, HMG applied for a loan of $100 million with ADB for the implementation of the Project. By the end of February 2017, 9 out of the 35 contracts had been completed, 14 were being implemented, 3 were under or after bidding, and the 5 contracts of River-lake Connection had been cancelled. After the adjustment, the Project consists of 1) Downstream Wetland Construction; 2) Sewer Network Construction; 3) Lake Ecology Rehabilitation (Phase 2); 4) Waste Transfer Station Equipment Upgrading and Vehicle Purchase; and 5) Emergency Drainage Equipment. HMG is the executing agency of the Project, and Huangshi Urban Construction Investment Company (HUCIC) is the implementing agency (IA). The Project has a construction period of 26 months, from October 2017 to December 2019.
The resettlement budget of the Project is 233.8053 million yuan, accounting for 22.44% of the gross investment in the Project of 1.0421194 billion yuan. Resettlement will begin in July 2017 and be completed in December 2020.
2. Range and impacts of resettlement
The Project will affect Xialu, Xisaishan and Huangshigang Districts. 1,590.29 mu of collective land will be acquired for the Project, including 868.58 mu of lake surface (76.3%), 363.66 mu of urban and industrial land (22.87%), and 355.60 mu of water facility land (0.19%), affecting 302 households with 1,291 persons. 25.45 mu of state-owned land will be occupied permanently, and state-owned roads of 347.26 mu will be occupied temporarily.
Residential houses of 7,751.46 m2 will be demolished for the Project, including 3,652.54 m2 in masonry concrete structure, 4,036.62 m2 in masonry timber structure, and 62.3 m2 in other structure; non-residential properties in residential areas of 11,823.55 m2 will be affected, including 644.09 m2 in masonry concrete structure, 10,909.03 m2 in masonry timber structure and 270.43 m2 in other structure, affecting 81 households with 363 persons; 12 entities will be affected by HD, with a total demolition area of 12,525.83 m2, including 1,065.92 m2 in masonry concrete structure (8.51%), 10,534.64 m2 (84.10%) in masonry timber structure and 925.27 m2 in steel structure (7.39%), affecting 42 persons. The Project will also affect some ground attachments.
3. Policy framework and entitlements
This RP is based on the Land Administration Law of the PRC (2004), the Decision of the State Council on Deepening the Reform and Rigidly Enforcing Land Administration (SC [2004] No.28), the Regulations on House Acquisition on State-owned Land and Compensation (Decree No.590 of the State Council), the Uniform AAOV Rates and Location-based Composite Land Prices for Land Acquisition of Hubei Province (HPG [2014] No.12), and ADB’s Safeguard Policy Statement (2009).
1
According to the above policies, and in consultation with local governments and affected persons (APs), the resettlement principles of the Project are: 1) The APs are granted compensation and rights that can at least maintain or even improve their livelihoods in the absence of the Project; 2) The APs are given compensation and assistance in resettlement whether legal title is available or not; 3) If the land available to everyone is insufficient to maintain his/her livelihood, replacement in cash or in kind and other income-generating activities shall be provided for the lost land; 4) The APs fully understand their entitlements, the method and standard of compensation, the livelihood and income restoration program, and the project schedule, and participate in the implementation of the RP; 5) No land should be acquired before the APs receive resettlement land or sufficient compensation; 6) The executing agency and an independent agency / third party shall monitor the compensation, relocation and resettlement operations; 7) The vulnerable groups shall be provided special assistance or treatment so that they lead a better life, and all APs shall have an opportunity to benefit from the project; 8) The RP is consistent with the master plans of the affected city (district, county); and 9) The resettlement costs are sufficient to cover all affected aspects.
4. Resettlement strategy
Compensation for permanent LA includes land compensation fees, resettlement subsidies and young crop compensation fees. For LA in Xisaishan and Xialu Districts, location-based composite land price is 49,000 yuan/mu, and young crop compensation rate is 1,750 yuan/mu for cultivated land or 2,100 yuan/mu for vegetable land.
For the affected fishpond contractors, the PMO will compensate for affected fishery facilities, fry losses, etc. reasonably, where the compensation rate for fishery facilities is 1,000 yuan/mu and that for fries 1,573 yuan/mu. In addition, the PMO will take other livelihood restoration measures for them. Demolished residential houses will be subject to cash compensation and property swap. In case of cash compensation, compensation will be fixed through market appraisal, but not less than the benchmark rates of the Project: 4,380 yuan/m2 for reinforced concrete structure, 4,180 yuan/m2 for masonry concrete structure and 4,080 yuan/m2 for masonry timber structure. In case of property swap, each AH will settle the price difference between the demolished house and the resettlement house. The resettlement community is Jinguangsha Community, within 2.5km from the demolished houses.
Demolished non-residential properties will be compensated for at a time based on market appraisal at rates not less than the benchmark rates: 900 yuan/m2 for masonry concrete structure, 700 yuan/m2 for masonry timber structure, 500 yuan/ m2 for simple properties and 150 yuan/ m2 for simple sheds. The PMO will assist the affected fishpond contractors and enterprises operating normally in leasing land out of the project area, and offer equipment relocation subsidies and compensation for losses from production suspension.
2
5. Vulnerable groups and women
The Project will affect 4 vulnerable households with 6 persons, including old people living alone, MLS households and households affected by disability. Except that these vulnerable households will be resettled as planned, the PMO will also offer extra subsidies, employment support, MLS, medical assistance and other assistance measures to help them restore production and living conditions as soon as possible.
During project implementation, at least 30% of women will obtain unskilled jobs. In addition, women will receive equal pay for equal work like men do. However, employment of child labor is prohibited. Priority will be given to female labor in terms of skills training so as to ensure that their economic status and income. The compensation agreement must be signed by the couple. A special FGD for women will be held to introduce resettlement policies and improve their awareness.
6. Public participation and information disclosure
All APs (with 50% being women) have been informed of the key points of this RP by various means and involved in the Project, such as meeting, interview, FGD, public participation meeting and community consultation, and their opinions have been well incorporated into this RP. The RP will be published on ADB’s website after approval by ADB, and the Resettlement Information Booklet (RIB) will be distributed to the APs or groups along.
7. Grievances and appeals
An appeal procedure has been established to settle disputes over compensation and resettlement. The aim is to respond to appeals of the APs timely and transparently. Grievances about the Project may be from collective LA and HD. Correspondingly, the Huangshi Project Leading Group, Huangshi PMO, Resettlement Department, and the affected sub-district offices and community committees will coordinate and handle grievances and appeals arising from resettlement. The APs may file appeals about any aspect of resettlement, including compensation rates. All agencies will accept grievances and appeals from the APs for free, and costs so reasonably incurred will be disbursed from the contingencies.
8. Organizational structure
HMG is the executing agency of the Project, and HUCIC is the IA. The Huangshi PMO is responsible for the implementation of this RP together with the affected sub-district offices and community committees.
9. Monitoring and evaluation
In order to ensure the successful implementation of this RP, resettlement implementation will be subject to internal and external monitoring. Internal monitoring will be conducted by the
3
Resettlement Department of the Huangshi PMO and other agencies concerned (e.g., land and resources bureau, and labor and social security bureau), and an internal monitoring report will be submitted to ADB quarterly. The Huangshi PMO will appoint an independent agency to conduct external monitoring and evaluation (M&E) semiannually, and M&E costs will be included in the resettlement budget. A comprehensive survey will be completed before resettlement. The baseline report (No.1 M&E report) will be submitted in August 2017, and an external M&E report will be submitted to ADB semiannually until project completion.
10. Resettlement budget
The resettlement budget of the Project is 233.8053 million yuan, accounting for 22.44% of the gross investment in the Project of 1.0421194 billion yuan, including LA costs of 78.8826 million yuan, accounting for 33.74%; HD costs of 104.938 million yuan, accounting for 44.88%; compensation fees for ground attachments of 10.8136 million yuan, accounting for 4.63%; and other costs (including resettlement planning and design costs, M&E costs, implementation management costs, training costs, LA taxes, contingencies, etc.) of 39.1712 million yuan, accounting for 16.75%.
4
Glossary
Affected People (households) affected by project-related changes in use of person (or land, water or other natural resources household)
Money or payment in kind to which the people affected are entitled in Compensation order to replace the lost asset, resource or income
Range of measures comprising compensation, income restoration, transfer assistance, income substitution, and relocation which are Entitlement due to affected people, depending on the nature of their losses, to restore their economic and social base
Income Reestablishing income sources and livelihoods of people affected restoration
Rebuilding housing, assets, including productive land, and public Resettlement infrastructure in another location
Loss of physical and non-physical assets, including homes, Resettlement communities, productive land, income-earning assets and sources, impact subsistence, resources, cultural sites, social structures, networks and ties, cultural identity, and mutual help mechanisms
A time-bound action plan with budget setting out resettlement Resettlement strategy, objectives, entitlement, actions, responsibilities, monitoring plan and evaluation
Vulnerable Distinct groups of people who might suffer disproportionately from
5
group resettlement effects
6
1. Overview of the Project
1.1 Background of the Project
In order to promote Huangshi City’s environmental improvement and urban development, HMG has applied for a loan with ADB for integrated water pollution control. The Project formerly consisted of Wastewater Collection and Treatment, Inland Lake Ecological Rehabilitation and River-lake Connection, Sludge Treatment and Disposal, Solid Waste Management, and Capacity Building and Institutional Strengthening.
Due to policy changes, etc., River-lake Connection cannot be implemented, and the Project has been adjusted. The gross investment in the Project is 1.0421194 billion yuan, including an ADB loan of $54.3826 million (equivalent to 375.24 million yuan), accounting for 36.01%, domestic bank loans of 340 million yuan, accounting for 32.63%, and government investments of 326.8794 million yuan, accounting for 31.36%.
HMG is the executing agency of the Project, and HUCIC is the IA.
1.2 Components and Resettlement Impacts
Huangshi City’s urban development is faced with many challenges, including the deterioration of the ecological environment around Cihu, Qingshan and Qinggang Lakes due to industrial wastewater discharge, water pollution of the Yangtze River, and disorderly land use. The Project will help improve the living and ecological environment, and promote economic development. According to the Master Urban Development Plan of Huangshi City, 10 wastewater control measures will be taken for the Yangtze River watershed, and the above 3 lakes in the next 3 years to meet the national Class III water quality standard, and realize flow regulating, climate regulating, sightseeing, tourism and other functions; wetlands and a sound urban sewer network will be established, and the efficiency of solid waste disposal improved in the next 5 years.
The Project is both an urban infrastructure construction project and an environmental one. It will generate significant environmental, social and economic benefits, including: 1) improving the tourism environment and urban image; 2) promoting economic and social development; and 3) improving the living environment.
After the adjustment, the Project consists of: 1) Downstream Wetland Construction; 2) Sewer Network Construction; 3) Lake Ecology Rehabilitation (Phase 2); 4) Waste Transfer Station Equipment Upgrading and Vehicle Purchase; and 5) Emergency Drainage Equipment, in which Components 1, 2 and 3 involve LA and/or HD. See Table 1-2.
According to the latest Feasibility Study Report (FSR), the Project has been adjusted as
7
follows:
1. Wastewater Collection and Treatment
1) Reduction of sewer lines by 25% or 23km (12km in the Cihu lake area, 3km in the Qingshan and Qinggang Lake areas, and 8km in the Hexi area) as compared to the former FSR due to changes in administrative division and design;
2) Addition of sewer lines by 49.07km (24.31km in Tieshan District, 10.26km in Laoxialu District and 14.5km in Tuanchengshan District);Addition of sewer lines is to Sewage treatment plant in the northwest of Dayecheng, and the project is in charge of Tieshan District and Xialu District.
3) Emergency Drainage Equipment: purchase of specialized drainage equipment to improve productivity and avoid secondary pollution
2. Inland Lake Ecological Rehabilitation and River-lake Connection
1) Cancellation of River-lake Connection: In November 2016, HMG agreed to cancel River-lake Connection, which was approved by a special ADB mission in January 2017.
2) Expansion of the artificial wetland
The treatment capacity of the Tuanchengshan WWTP for the artificial wetland has been expanded from 40,000 t/d in the former FSR to 80,000 t/d for 2020.
3. Lake Ecology Rehabilitation (Phase 2)
According to the ADB Memorandum in January 2017, the Qinggang Lake part of Lake Ecology Rehabilitation (Phase 2) would be fully cancelled.
table 1-1 Summary of Adjustments to Components
Variation from the Component Former FSR Adjustment former FSR
Pollution source census, GIS, Reduction of sewer 1) Addition of sewer lines drainage monitoring system, lines by 25% or 23km by 49.07km (24.31km in sewer line construction, Hexi (12km in the Cihu lake Tieshan District, 10.26km WWTP construction, etc. area, 3km in the in Laoxialu District and Wastewater Qingshan and 14.5km in Tuanchengshan Collection Budget: 201.1127 million yuan Qinggang Lake areas, District); and and 8km in the Hexi Treatment area) 2) Purchase of specialized drainage equipment 3) Adjusted budget: 109.2782 million yuan
Inland Lake Dredging and sludge disposal 1) Cancellation of 1) Expansion of the Cihu Ecological of Qingshan, Qinggang and River-lake Lake artificial wetland to Rehabilitatio Cihu Lakes, ecological Connection; 80,000 t/d, with a floor area n and rehabilitation, Cihu Lake of 98.2ha River-lake artificial wetland and river-lake 2) Cancellation of Connection connection ecological 2) Ecological rehabilitation rehabilitation of of Qinggang Lake (Phase
8
Budget: 663.1207 million yuan Qinggang Lake 2) 3) Adjusted budget: 439.8485 million yuan
Construction of a sludge Implemented as No adjustment disposal plant for Cihu Lake, planned Sludge Tuanchengshan District, Treatment Huangjinshan and Hexi and Disposal WWTP Budget: 28.4838 million yuan
Construction of waste transfer Implemented as 1) Upgrading of waste stations and environmental planned transfer station facilities sanitation facilities, purchase of vehicles 2) Purchase of upgraded Solid Waste vehicles Managemen Budget: 100.9647 million yuan t 3) Purchase of leachate treatment equipment 4) Adjusted budget: 36.77 million yuan
Capacity Capacity building, topical Implemented as No adjustment Building and studies, etc. planned Institutional Strengthenin g
table 1-2 Summary of Adjusted Components
Resettlement No. Component Composition Document impacts
1. Downstream Wetland Construction: 1) Phase 2: surface and sub-surface flow wetlands, tail water reflux and lifting, water outlet pump, flood control; 2) Phase 3: sub-surface flow Downstream wetland, tail water reflux, water outlet pump, well 1 Wetland LA and HD RP
Construction 2. Buildings 3. Landscape: roads, square, wood platform, temporary and permanent car parks, bridges, landscaping, gallery, arts, toilets, urban furniture, indication system 1. Sewer system of Tieshan District: 1) Zone A: covering Tieshan main urban area, Xiushan Road area and Tieshan east area, totaling 851.05ha; 2) Zone B: South Logistics Park and Mulan Industrial Park, totaling 528.78ha; 3) Zone C: Sancha Road Community, totaling 376.54ha; 4) Zone D: Temporary land Dongfang Mountain Scenic Zone and Huangshi National Mine occupation, and Sewer Network permanent 2 Park, totaling 1059.89ha RP Construction occupation of 2. Sewer system of Laoxialu District: covering Fenglieshan, state-owned Jiangyang, Wangshou, Datang, Tuanjie, Kangning, Shengli, land Shenniu and Laoxialu Communities, totaling 11,261m 3. Sewer system of Tuanchengshan District: covering Qinglongshan, Chenbaizhen, Hangzhou East Road, Huangguling, Jianlouxia, Ke’ershan, Ma’anshan, Shiliuyuan,
9
Xiaojiapu and Yuanjiafan Communities, totaling 14,541m
Daquan Road entrance of Qinggang Lake Experience and leisure area Permanent Lake Ecology Lakefront viewing area occupation of 3 Rehabilitation RP state-owned (Phase 2) ecological area land Suoqian Port reconstruction work Qingshan Lake Bridge 1. Purchase of equipment for waste transfer stations, including old equipment replacement, vehicle upgrading and Waste Transfer purchase of leachate treatment equipment Station Equipment 4 2. Purchase of cleaning vehicles None Upgrading and Vehicle 3. Purchase of gardening vehicles Purchase 4. Purchase of water surface waste collection equipment for Cihu Lake
Emergency Purchase of specialized drainage equipment 5 Drainage None Equipment
1.3 Measures to Reduce Resettlement
HUCIC and the project proposal preparation agency have chosen the project site carefully based on the requirements of ADB’s policy on involuntary resettlement to minimize LA and HD. In addition, compensatory measures will be taken for those inevitably affected to minimize negative impacts. Sewer lines will be constructed along existing roads, and construction scheduled rationally taken to reduce traffic impacts.
1.4 Estimated Resettlement Budget and Implementation Plan
Based on prices in May 2017, the resettlement budget of the Project is 233.8053 million yuan, including land compensation, resettlement subsidy, HD compensation, ground attachment compensation, compensation for losses from production suspension, etc.
The planned construction period of the Project is 26 months (from October 2017 to December 2019), in which Downstream Wetland Construction, Sewer Network Construction and Lake Ecology Rehabilitation (Phase 2) will be constructed from October 2017 to December 2019, and Waste Transfer Station Equipment Upgrading and Vehicle Purchase, and Emergency Drainage Equipment from October 2017 to December 2018. Correspondingly, resettlement will begin in July 2017 and be completed in December 2020.
10
2. Impacts of the Project
2.1 Scope of Impact Survey of LA and HD
In March 2017, HUCIC and the Huangshi PMO appointed Wuhan Engineering Design & Research Institute Co., Ltd. to prepare and submit the first draft of the FSR.
In March 2017, the task force was appointed by the Huangshi PMO to conduct a preliminary socioeconomic survey in the project area using such methods as literature review, key informant interview, FGD and sampling survey, covering household population, land resources, housing conditions, household economic status, and expected resettlement modes.
According to the FSR and the survey, the Downstream Wetland Construction component will affect Baitayan Village, Chengyue Sub-district, Xisaishan District, and Chenbaizhen, Jianlouxia and Ke’ershan Communities, Tuanchengshan Sub-district, Xialu District; the Sewer Network Construction component will affect urban roads in Tieshan and Xialu Districts; the Lake Ecology Rehabilitation (Phase 2) component will affect Huangshigang District. See Table 2-1.
table 2-1 Range of Resettlement Impacts
No. Component District Sub-district (area) Village / community Group Remarks Chengyue Xisaishan Baitayan Village —— Sub-district
1
Chen Baizhen Community 3 Downstream Permanent 1 Wetland 9 LA Construction Tuanchengshan Xialu - 5 Sub district Jianlouxia Community 6
5 Ke’ershan Community 7
Tieshan old area
Xiushan Road area Tieshan —— Tieshan east area
Tieshan west area Temporary Sewer land 2 Network Fenglieshan, Jiangyang, Wangshou, —— occupation & Construction Datang, Tuanjie, Kangning, Shengli, Laoxialu area permanent LA Shenniu and Laoxialu Communities
Xialu Qinglongshan, Chenbaizhen, Hangzhou Tuanchengshan East Road, Huangguling, Jianlouxia, area Ke’ershan, Ma’anshan, Shiliuyuan, Xiaojiafu and Yuanjiafan Communities
11
Lake Ecology Huangshi Huahu Permanent 3 Rehabilitation —— —— -gang Development Zone LA (Phase 2)
2.2 LA and HD Impacts
2.2.1 Permanent LA
1) Collective land
Only the Downstream Wetland Construction component involves the permanent acquisition of collective land. 1,590.29 mu of collective land will be acquired, including 2.45 mu of woodland (0.15%), 868.58 mu of lake surface (76.3%), 363.66 mu of urban and industrial land (22.87%), and 355.60 mu of water facility land (0.19%). See Error! Reference source not found..
table 2-2 Permanently Occupied State-owned Land
Lake Urban and Water Woodland Village / surface industrial facility land Total (mu) Remarks District (mu) community (mu) land (mu) (mu)
Baitayan Xisaishan 868.58 57.92 168.40 1094.91 Village
Ke’ershan 30.90 7.84 38.74 5, 7 Community
Jianlouxia Xialu 100.57 2.95 103.52 5, 6 Community
Chenbaizhen 2.45 174.27 176.41 353.12 1, 3, 9 Community
Total 2.45 868.58 363.66 355.60 1590.29
Lake surface Water area
Figure 2-1 Current Situation of Collective Land to be Acquired
12
2) State-owned land
The Sewer Network Construction and Lake Ecology Rehabilitation (Phase 2) components involve the permanent occupation of state-owned land, including 0.22 mu for a lifting pump station in Sewer Network Construction, and 25.23 mu for Lake Ecology Rehabilitation (Phase 2), including 4.46 mu for the Daquan Road entrance of Qinggang Lake, 13.05 mu for the experience and leisure area, 1.05 mu for the lakeside viewing area, 6.42 mu for the ecological area and 0.25 mu for the Qingshan Lake Bridge. See Table 2-3.
table 2-3 State-owned Land to be Permanently Occupied
Component Land area (mu) Land type
1. Sewer Network Urban construction Lifting pump station 0.22 Construction land
Daquan Road entrance of Qinggang 4.46 Lake
Experience and leisure area 13.05 2. Lake Ecology
Rehabilitation Lakeside viewing area 1.05 Water facility land
(Phase 2) Ecological area 6.42 Suoqian Port reconstruction work 0.00
Qingshan Lake Bridge 0.25
Total 25.45
2.2.2 Temporary Land Occupation
Sewer Network Construction will involve the temporary occupation of state-owned roads of 347.26 mu for 15-30 days. Since construction will be conducted in stages, nearby stores and residents will be affected slightly during occupation. See Table 2-4.
table 2-4 Land to be Temporarily Occupied
Pipe diameter Pipe length Excavation Temporarily occupied Subcomponent Land type (mm) (m) width (m) area (mu)
800 1059 3 4.77 State-owned road
600 937 3 4.22 State-owned road Sewer lines in 500 1231 2.5 4.62 State-owned road Tieshan old area 400 5577 2.5 20.91 State-owned road
400 16000 2.5 60.00 State-owned road
13
Subtotal 24804 94.51 State-owned road
600 1171 3 5.27 State-owned road
500 3054 2.5 11.45 State-owned road Sewer lines in 400 12317 2.5 46.19 State-owned road Tieshan west area 300 850 2 2.55 State-owned road
Subtotal 17392 65.46 State-owned road
400 15026 2 45.08 State-owned road
500 2125 2.5 7.97 State-owned road Sewer lines in 600 3214 2.5 12.05 State-owned road Laoxialu District 800 1023 3 4.60 State-owned road
Subtotal 21388 69.70 State-owned road
400 15020 2.5 15.00 State-owned road Sewer lines in Tuanchengshan 600 9020 3 27.00 State-owned road District Subtotal 24040 117.59 State-owned road
Total 87624 347.26
2.2.3 Demolition of Residential Houses
81 residential houses will be demolished for the Project, all for the Downstream Wetland Construction component, affecting 81 households with 363 persons, including 16 households with 86 persons in Baitayan Village, 33 households with 144 persons in Ke’ershan Community, 15 households with 65 persons in Jianlouxia Community and 17 households with 68 persons in Chenbaizhen Community, with a total demolition area of 19,575.01 m2, including 3,652.54 m2 in masonry concrete structure, 4,036.54 m2 masonry timber structure, 62.3 m2 in other structures, and non-residential properties of 644.09 m2 in masonry concrete structure, 10,909.03 m2 in masonry timber structure and 270.43 m2 in other structures, See Error! Reference source not found..
table 2-5 Impacts of Demolition of Residential Houses
Residential size (m2) Non-residential size (m2) Village / No. Head of household Masonry Masonry Masonry Masonry Total community concrete timber Other concrete timber Other structure structure structure structure
1 Wang Huali 108.82
2 Li Shengliu 620.13 557.97 21.09 1199.19 Baitayan Village 3 Li Shengkai 233.87 1110.51 1344.38
4 Li Shengbin 219.11 132.17 351.28
14
5 Zhang Jiaxiang 193.45 62.3 255.75
6 Huang Rui 109.69 109.69 219.38
7 Li Shengqi 227.26 227.26
8 Li Shengwang 9.94 322.67 332.61
9 Li Shengqii 18.54 18.54
10 Zhou Xiuying 118.77 118.77
11 Li Shengqiang 222.72 222.72
12 Li Yong’er 492.68 492.68
13 Li Guoqiang 51.12 62.19 113.31
14 Zhang Haiyuan 241.54 241.54
15 Zhang Jiakun 87.03 87.03
16 Li Hengshan 271.9 271.9
Subtotal 813.58 1432.95 62.3 61.06 3125.58 109.69 5605.16
1 Chen Ruyi 49.62 49.62
2 Li Jinlu 68.23 68.23 136.46
3 Yin Tiangui 119.63 28.64 148.27
4 Liu Zhenqiang 185.1 185.1
Cao Dazhen 101.38 101.38
5 Peng Yiyan 50.67 50.67
6 Li Jingzhong 44.27 34.21 78.48
7 Li JIamen 76.69 76.69
8 Chen Bo 34.88 34.88
9 Wang Fuhua 194.62 194.62 Ke’ershan Community 10 Yin Chuanliu 69.33 69.33 400.91 539.57
11 Peng Xixiu 132.43 77.45 209.88
12 Li Ming 58.05 58.05
13 Peng Tianyu 36.33 36.33 173.84 246.5
14 Peng Fangneng 131.89 59.57 525.02 7.57 724.05
15 Zhang Yinghua 1314.82 1314.82
16 Zhang Qiuping 168.05 168.05
17 Li Jiakun 11.52 11.09 22.61
18 Pump house 28.6 28.6
Peng Yibing, Peng 19 0 Yiguang
15
20 Peng Qingqing 38.7 38.7
21 Peng Biao 8.42 8.42
22 Bai Shou 21.13 21.13
23 Peng Hongying 97.71 97.71
24 Zhang Guojun 146.83 146.83
25 Zhang Shengyou 66.76 66.76
26 Huang Jing 204.11 141.6 345.71
Zhang Shengcai, Zhang 27 122.71 122.71 Jiaxiong
28 Dan Junyi 74.06 74.06
29 Zhang Sizhi 166.24 166.24 46 46 424.48
30 Zhang Siqing 127.43 127.43
31 Zhang Shuiqing 275.48 37.27 312.75
32 Zhang Shuiqing 82.91 71.34 154.25
33 Feng Xixiu 104.37 42.31 6.76 133.12 286.56
Subtotal 1201.63 1529.03 0 163 3694.57 7.57 6595.8
1 Jiang Zufa 41.53 41.53
2 Jiang Youzhuan 105.1 32.69 137.79
3 Shao Zhongyong 150.66 64.95 40.63 256.24
4 Peng Yixia 211.52 211.52
5 Peng Huanhuan 41.98 41.98 51.55 135.51
6 Peng Biao 64.2 52.7 116.9
7 Peng Peng 231 231
8 Wang Wei 394.26 247.45 93.72 735.43 Chenbaizhe 9 Peng Zhineng 246.13 241.36 56.69 33.08 577.26 n Community 10 Wang Sheng 436.06 56.73 150.93 643.72
11 Yu Guoxing 96.18 32.06 128.24
12 Li Baozhen 163.3 133.09 222.01 518.4
Zhan Xiaofeng, Zhan 13 108.76 108.76 282.93 500.45 Xiaoli
14 Yu Chengpeng 112.51 112.51
15 Community 6.7 6.7
16 Wang Yiqun 36.2 73.98 110.18
17 Community 126.31 44.18 170.49
16
Subtotal 1637.33 930.59 0 360.87 1664.45 40.63 4633.87
1 Wang Wei 124.55 124.55
2 Hu Hongqiao 157.11 157.11
3 Wang Yueying 99.63 99.63
4 Wang Fang 140.8 140.8
5 Xiang Weiguo 124.36 124.36
6 Zhang Guoxiang 69.55 69.55
7 Wang Wei 112.65 112.65
8 Zhang Fu’an 46.06 84.62 130.68 Jianlouxia Community 9 Hu Hongjiao 69.71 112.54 182.25
10 Li Huan 19.73 19.73
11 Li Yuanlai, Lu Lanzhi 567.04 567.04
12 Community 17.44 12.1 29.54
Li Yuanliang, Li 13 13.1 824.06 837.16 Yuandong, Li Dongzhi
14 Zhan Shixue 18.52 18.52
15 Wang Daigang 126.61 126.61
Subtotal 0 144.05 0 59.16 2424.43 112.54 2740.18
Total 3652.54 4036.62 62.3 644.09 10909.03 270.43 19575.01
Figure 2-2 Current Situation of Residential Houses to be Demolished
2.2.4 Demolition of Non-residential Properties
The demolition of non-residential properties for the Project will affect 4 enterprises and 8 pig farms, with a total demolition area of 12,525.83 m2, including 1,065.92 m2 in composite structure (8.51%), 10,534.64 m2 in masonry timber structure (84.10%), and 925.27 m2 in steel structure
17
(7.39%), affecting 42 workers. See Error! Reference source not found..
table 2-6 Impacts of Demolition of Non-residential Properties
Demolition area (m2)
Masonry Masonry Work No. Enterprise Steel Proprietor Business status concrete timber Total force structure structure structure
Baita Trading 1 Pig farm 310.33 1405.6 1715.93 0 Closed in 2013 Company
Tianlong Door & Li Shengliu, Qi Founded in 2005, 2 198.36 1774.58 925.27 2898.21 25 Window Co., Ltd. Chunmei operating normally
Chengxin Driving Founded in 1998, 3 82.13 82.13 3 Li Shengliu School operating normally
4 Pig farm 360.05 360.05 0 Li Shengliu Closed
Lijiafang Storage & 5 1260.26 1260.26 4 Li Chunjin Logistics Company Sharing one place after closing 6 Pig farm 1606.94 1606.94 4 Li Chunjin Zhang 7 Root Carving Factory 501.84 1982.65 2484.49 6 Operating normally Jiachuan
8 Pig farm 493.08 493.08 0 Li Bingtuan Closed 9 Pig farm 138.57 138.57 0 Li Jun Closed
10 Pig farm 648.68 648.68 0 Huang Rui Closed
Jianlouxia 11 Tuanjieban Farm 55.39 282.1 337.49 0 Closed Community
12 Huahu Pig Farm 500 500 0 Huahu Farm Closed
Total 1065.92 10534.64 925.27 12525.83 42
Chengxin Driving School Lijiafang Storage & Logistics Company and Li Chunjin Livestock Farm (shared)
18
Tianlong Door & Window Co., Ltd. Root Carving Factory
Exterior of Huahu Pig Farm Interior of Huahu Pig Farm
Figure 2-3 Current Situation of Non-residential Properties to be Demolished
2.2.5 Ground Attachments
The Project will affect some ground attachments, including trees, vegetable cellars and telegraph poles, mostly in the Downstream Wetland Construction component. See Table 2-7.
table 2-7 Affected Ground Attachments
Downstream Sewer Lake Ecology Item Unit Wetland Network Rehabilitation Total Construction Construction (Phase 2)
Big / 896 896
Medium / 701 701 1. Timber trees Small / 9014 9014
Young / 12098 12098 Trees Ultra-big / 1029 1029
Big / 7933 7933 2. Commercial trees Medium / 30222 30222
Small / 17137 17137
19
Young / 63882 63882
Ultra-big / 60 60
Big / 37 37
3. Special trees Medium / 66 66
Small / 113 113
Young / 26 26
4. Total / 143214 143214
Young vegetables / 45.59 45.59
Masonry m³ 14.34 0 Dung cellars Jar m³ 75.36 0
Masonry m³ 8.87 0
Retaining walls Dry stone m³ 19.08 0
Brick m³ 18 0
Cement telegraph poles / 12 12
Wood telegraph poles / 1 1
6mm wires / 5100 5100
Cement sluices m³ 30 0
2.3 Other Impacts of the Project
2.3.1 Affected Population
In sum, 352 households with 1,500 persons will be affected by LA and HD for the Project.
By impact type:
1) LA: 302 households with 1,291 persons will be affected by LA, including 107 households with 451 persons in Baitayan Village and 195 households with 840 persons in Chenbaizhen Community;
2) Demolition of residential houses: 81 households with 363 persons will be affected by HD, including 33 households with 144 persons in Ke’ershan Community and 15 households with 65 persons in Jianlouxia Community; 33 households with 154 persons (16 households with 86 persons in Baitayan Village and 17 households with 68 persons in Chenbaizhen Community) by both LA and HD;
3) Demolition of non-residential properties: 12 households with 42 persons will be affected by the demolition of non-residential properties, in which 10 households with 42 persons (Baitayan Village) will be affected by both LA and HD.
20
By component:
1) In Downstream Wetland Construction, 302 households with 1,291 persons will be affected by LA, 81 households with 363 persons by the demolition of residential houses, in which 33 households with 154 persons will be affected by both LA and HD; and 12 households with 42 persons by the demolition of non-residential properties, in which 10 households with 42 persons will be affected by both LA and HD;
2) Sewer Network Construction will have negligible impacts on nearby residents due to stage-by-stage construction and a short period of land occupation.
3) In Lake Ecology Rehabilitation (Phase 2), state-owned water facility land will be occupied permanently, affecting no one, and a pig farm in Huahu Farm demolished, affecting no one. A non-residential property will be demolished for Lake Ecology Rehabilitation (Phase 2), affecting no one.
The Project affects no minority population. See Error! Reference source not found..
table 2-8 Summary of Affected Population
Both LA and Non-residential Village / LA HD District Group HD properties Component community AHs APs AHs APs AHs APs AHs APs
Baitayan Xisaishan 107 451 16 86 16 78 10 42 Village
Ke’ershan 5, 7 33 144 Downstream Community Wetland Jianlouxia Construction Xialu 5, 6 15 65 1 0 Community
Chenbaizhen 1, 3, 9 195 840 17 68 11 49 Community
Subtotal 302 1291 81 363 27 127 11 42
Sewer Network Construction
Lake Ecology Rehabilitation 1 0 (Phase 2)
Total 302 1291 81 363 27 127 12 42
2.3.2 Vulnerable Groups
The Project will affect 4 vulnerable households with 6 persons, all being 4 MLS households. Local governments offer sound security measures to local vulnerable groups, such as each MLS household member in Chenbaizhen Community receives a MLS subsidy of 580 yuan, and is entitled
21
to a two-year interest free small-amount loan. In addition, local governments offer special policies for the resettlement of vulnerable groups (see Section 5.6). Therefore, the Project will affect vulnerable groups slightly. See Table 2-9.
table 2-9 Summary of Affected Vulnerable Groups
Where Family size Impact type
Old people people livingalone Old households MLS by disability affected Households Subtotal Male Female Village / Vulnerable Vulnerable community households population LA HD
Baitayan Village
Ke’ershan 2 2 3 3 1 2 2 Community
Jianlouxia Community
Chenbaizhen 2 2 3 3 1 2 2 Community
Total 4 4 6 6 2 4 4
22
3. Socioeconomic Profile
3.1 Socioeconomic Profile of the Project Area
3.1.1 Huangshi City
Huangshi City is located in southeastern Hubei Province, south of the middle Yangtze River, bordered by Ezhou City on the north, Wuhan City on the west, Xianning City on the southwest, and Jiujiang City on the southeast.
Huangshi is a major city and an important raw material industrial base in central China, and a riverfront open city approved by the State Council.
Huangshi has a land area of 4,583 km2, and governs 4 districts, a county and a state-level development zone, with a resident population of 2.6014 million. In 2015, the city’s GDP was 92.596 billion yuan. See Error! Reference source not found..
table 3-1 Socioeconomic Profile of Huangshi City (2015)
Land Fiscal Farmers’ Urban residents’ per Population GDP per capita capita disposable area revenue Division net income income km2 0,000 00m yuan 00m yuan yuan yuan
Huangshi City 4582.9 260.14 925.96 92.17 6487 17003
Huangshigan 42 22 108.5 6.55 8510 18872 g
Xisaishan 111.96 24 145.53 5.34 6678 16302
Xialu 38 12 146.8 5.31 7560 17274 Tieshan 29.4 6.15 21.68 3.04 6850 17876
Development 28.2 13.87 60.6 10.92 5643 16058 zone
Source: Statistical Yearbook 2016 of Huangshi City
3.1.2 Affected Villages / Communities
1. Downstream Wetland Construction will affect Baitayan Village, Chenbaizhen Community, Ke’ershan Community and Jianlouxia Community.
1) Baitayan Village, also known as Baita Trading Company, and formerly called Lijiafang Village, has 7 groups.
2) Chenbaizhen Community was converted from a village in 2001 due to LA with the progress of urbanization. The community has 11 groups, 353.12 mu farmland and about 3,000 residents,
23
including about 1,800 laborers. Agricultural income accounts for less than 5% of gross income.
3) Ke’ershan Community was converted from a village in 2002, and has a land area of 3 km2, 19 groups, 4,500 households with 10,535 persons, and 1,400 mu of land.
4) Jianlouxia Community was converted from a village in 2002, and has a land area of 5 km2. 17 groups and 1,316 households with 3,218 persons. Most residents work at plants, and agricultural income is low.
See Error! Reference source not found..
table 3-2 Socioeconomic Profile of the Affected Communities
Per Cultivate Averag capita Farmers’ per District Village / community HHs Population d area e family capita net cultivated (mu) size income (yuan) area (mu)
Xisaishan Baitayan Village 107 451 1094.91 4.21 2.43 6853
Laoxialu Village 298 1040 100 3.49 0.10 9016 250 10535 200 4.214 0.02 8588 Ke’ershan Community 0
Xialu 131 Jianlouxia Community 3218 300 4.33 0.09 8307 6
129 Chenbaizhen Community 3000 353.12 4.14 0.12 9117 9
3.2 Socioeconomic Profile of the Affected Population
3.2.1 Permanent LA
1,590.29 mu of collective land will be acquired for the Project, including 2.45 mu of woodland (0.15%), 868.58 mu of lake surface (76.3%), 363.66 mu of urban and industrial land (22.87%), and 355.60 mu of water facility land (0.19%), affecting 302 households with 1,291 persons in Xisaishan and Xialu Districts.
Baitayan Village, and Groups 1, 3 and 9 of Chenbaizhen Community will be affected seriously by LA, with land loss rates of 100%.
1,094.91 mu of land in Baitayan Village will be acquired, affecting 107 households with 451 persons. 353.12 mu of land in Groups 1, 3 and 9 of Chenbaizhen Community will be acquired, affecting 195 households with 840 persons.
24
table 3-3 Summary of Acquired Collective Land (by group)
Lake Urban and Water Woodland Total area District Community surface industrial facility land Remarks (mu) (mu) (mu) land (mu) (mu)
Xisaishan 868.58 57.92 168.4 1094.91
Ke’ershan 30.9 7.84 38.74 5, 7
Xialu Jianlouxia 100.57 2.95 103.52 5, 6
Chenbaizhen 2.45 174.27 176.41 353.12 1, 3, 9
Total 2.45 868.58 363.66 355.6 1590.29
table 3-4 Summary of Acquired Collective Land (by component)
No. Component Affected area Land use Resettlement
West to Tanshan Acquiring 532 mu of land (incl. Permanent LA Viaduct, east to fishponds) and demolishing Downstream Lijiafang Viaduct, houses of 7,840.52 2 in Xialu 1 Wetland m south to Yanhu Road District; acquiring 981 mu of Construction and north to planned land and demolishing houses of 47# Road 16,743 m2 in Xisaishan District Tieshan old and west Occupying 159.97 mu of land Temporary land areas temporarily occupation, and Sewer Network permanent 2 Construction Tuanchengshan and Occupying 187.29 mu of land occupation of Laoxialu Districts temporarily state-owned land
Huahu Development Lake Ecology Zone, west of 3 Rehabilitation Dazhongshan Park, (Phase 2) Huangshigang District
3.2.2 Affected Population
In order learn the basic information of the AHs, the task force conducted a sampling survey on 62 households with 231 persons (sampling rate 17.61%) during March 5-10, 2017, including 17 households with 64 persons in Xisaishan District (sampling rate 15.89%), and 45 households with 171 persons in Xialu District (sampling rate 18.44%).
table 3-5 Basic Sample Information
Sample information District Village / community All HHs Sample HHs Percent (%) Xisaishan Baitayan Village 107 17 15.89%
Xialu Ke’ershan Community 33 8 24.24%
25
Jianlouxia Community 16 3 18.75% Chenbaizhen Community 195 34 17.44%
Total 352 62 17.61%
1) Gender
The 45 sample households in Xialu District have an average size of 3.8, and 84 women, accounting for 49.12%. The 17 sample households in Xisaishan District have an average size of 3.76, and 30 women, accounting for 46.88%. Women deal with cultivation, stockbreeding and housework mainly. No ethnic minority or vulnerable group is involved.
2) Age
Among the 45 sample households in Xialu District, 33 are aged below 16 years, accounting for 19.30%; 67 aged 16~39 years, accounting for 39.18%; 61 aged 40~59 years, accounting for 35.67%; and 10 aged 60 years or above, accounting for 5.85%. Among the 17 sample households in Xisaishan District, 12 are aged below 16 years, accounting for 18.33%; 22 aged 16~39 years, accounting for 35.00%; 21 aged 40~59 years, accounting for 33.33%; and 9 aged 60 years or above, accounting for 13.33%.
3) Education
Among the 45 sample households in Xialu District, 33 have received primary school or below education, accounting for 19.30%; 67 junior high school education, accounting for 39.81%; 60 senior high school / secondary technical school education, accounting for 35.09%; and 11 junior college or above education, accounting for 6.43%. Among the 17 sample households in Xisaishan District, 12 have received primary school or below education, accounting for 18.33%; 22 junior high school education, accounting for 35.00%; 21 senior high school / secondary technical school education, accounting for 33.33%; and 9 junior college or above education, accounting for 13.33%. See Table 3-4.
4) Housing
The 45 sample households in Xialu District have a total house size of 8,190.9 m2 and a per capita house size of 47.90 m2. The 17 sample households in Xisaishan District have a total house size of 3,653.12 m2 and a per capita house size of 57.08 m2.
5) Land
Almost all cultivated land in the project area has been acquired, and the remaining land is mostly fishpond and water area. However, some residents grow seasonal crops on flood land in the low-flow period.
26
6) Household properties
Among the 45 sample households in Xialu District, an average household has 1.6 TV sets, 0.8 refrigerator / air-conditioner, 0.45 hi-fi, 3.8 fixed telephones / mobile phones, 1.48 bicycles / motorcycles and 0.1 tractor / water pump, indicating an above-average living standard. Among the 28 sample households in Xisaishan District, an average household has 1.7 TV sets, 0.9 refrigerator / air-conditioner, 0.41 hi-fi, 3.9 fixed telephones / mobile phones, 1.9 bicycles / motorcycles and 0.1 tractor / water pump, indicating an average living standard.
7) Household Income and Expenditure
Among the 45 sample households in Xialu District, per capita annual income is 22,782 yuan, per capita annual expenditure 14,264 yuan, and per capita net income 8,518 yuan. Among the 17 sample households in Xisaishan District, per capita annual income is 18,329 yuan, per capita annual expenditure 11,476 yuan, and per capita net income 6,853 yuan. The average income of the sample population is much higher than the national rural poverty line (2,300 yuan in 2011). See Tables 3-6, 3-7 and 3-8.
table 3-6 Income and Expenditure of AHs in Xialu District
Average per Per capita Percent Item household (yuan) (yuan) (%)
Cultivation income 968.24 284.78 1.25% Forestry income 890.78 261.99 1.15%
Individual business income 20906.13 6148.86 26.99% Annual household Stockbreeding income 1022.46 300.72 1.32% income Labor service income 48605.40 14295.71 62.75%
Property income 5065.81 1489.94 6.54%
Subtotal 77458.80 22782.00 100%
Productive expenses 13608.43 4002.48 28.06%
Annual Nonproductive expenses 30325.55 8919.28 62.53% household expenditure Other 4563.62 1342.24 9.41% Subtotal 48497.60 14264.00 100%
Per capita net income 8518
table 3-7 Income and Expenditure of AHs in Xisaishan District
Average per Per capita Percent Item household (yuan) (yuan) (%) Cultivation income 716.66 210.78 1.15% Annual household Forestry income 1339.85 394.07 2.15%
27
income Individual business income 17648.63 5190.77 28.32% Stockbreeding income 697.97 205.28 1.12%
Labor service income 39210.86 11532.61 62.92%
Property income 2704.63 795.48 4.34% Subtotal 62318.60 18329.00 100%
Productive expenses 10168.20 2990.65 26.06% Annual Nonproductive expenses 24382.60 7171.35 62.49% household expenditure Other 4467.61 1314.00 11.45% Subtotal 39018.40 11476.00 100% Per capita net income 6853
table 3-8 Demographics of Sample Population
Xialu District Xisaishan District
Male Female Total Male Female Total Item Percent Percent Percent Percent Percent Percent N N N N N N (%) (%) (%) (%) (%) (%)
Age Age ≤16 years 17 19.54% 16 19.05% 33 19.30% 7 20.00% 5 16.67% 12 18.33% 16-39 years 34 39.08% 33 39.29% 67 39.18% 11 33.33% 11 36.67% 22 35.00% 40-59 years 31 35.63% 30 35.71% 61 35.67% 11 33.33% 10 33.33% 21 33.33%
≥60 years 5 5.75% 5 5.95% 10 5.85% 5 13.33% 4 13.33% 9 13.33% Subtotal 87 100.00% 84 100.00% 171 100.00% 34 100.00% 30 100.00% 64 100.00%
Education Education Primary school or 17 19.54% 16 19.05% 33 19.30% 7 20.00% 5 16.67% 12 18.33% below
Junior high school 34 39.08% 33 39.29% 67 39.18% 11 33.33% 11 36.67% 22 35.00%
Senior high school / secondary technical 30 34.48% 30 35.71% 60 35.09% 11 33.33% 10 33.33% 21 33.33% school
Junior college or 6 6.90% 5 5.95% 11 6.43% 5 13.33% 4 13.33% 9 13.33% above
Subtotal 87 100.00% 84 100.00% 171 100.00% 34 100.00% 30 100.00% 64 100.00%
3.2.3 Willingness Survey
1. Households affected by HD
1) Willingness survey
In March 2017, the task force conducted a willingness survey on 47 households affected by HD, accounting for 58.02% of all households affected by HD. See 3-9.
28
table 3-9 Statistics of Willingness Survey on Households affected by HD
Sample information District Village / community All HHs Sample HHs Percent (%)
Xisaishan Baitayan Village 16 8 50.00%
Ke’ershan Community 33 19 57.58%
Xialu Jianlouxia Community 15 9 60.00% Chenbaizhen Community 17 11 64.71%
Total 81 47 58.02%
2) Survey results