Projects Update For Ward 7
Monday, November 17, 2014 Public Outreach for Ward 7 Projects Update Mee ng • Public no ce posted to DDOT website, AWI website, and on DDOT’s Twi er and Facebook pages • DDOT Communica ons Office distributed the Public No ce to the DDOT email distribu on list three mes • DDOT no fied the Mayor’s Office of Neighborhood Engagement to inform residents • DDOT no fied Councilmember Yve e Alexander’s Office • DDOT no fied Ward 7 ANC Commissioners to inform residents • DDOT posted flyers in the public libraries in Ward 7 o Anacos a Neighborhood Library (NL), Francis A. Gregory NL, Capitol View NL, Dorothy Height NL, Deanwood NL
2 Public Outreach for Ward 7 Projects Update Mee ng (con’t) • DDOT no fied relevant (and s ll ac ve) Ward 7 Community Groups listed on the Mayor’s Office of Neighborhood Engagement website
ü Randle Highland Civics Associa on ü Penn-Branch Ci zens/Civic Associa on ü Fairlawn Ci zens Associa on ü Central Northeast Civic Associa on ü Deanwood Ci zens Associa on ü Dupont Park Civic Associa on ü Fort Dupont Civic Associa on ü River Terrace Community Organiza on ü Hillcrest Community Civic Associa on ü Fairfax Village I-VII Community Assoc. ü Eastland Gardens Civic Associa on ü Burrville Civic Associa on ü Capitol View Civic Associa on ü Fort Davis Civic Associa on ü Far Northeast/Southeast Council ü Hillbrook Civic Associa on ü Benning Ridge Civic Associa on ü Park Naylor Community Associa on ü 6th District Ci zens Advisory Council ü Neighbors of Burns Street Organiza on ü Northeast Boundary Civic Associa on ü Parkside Civic Associa on ü Kingsman Park Civic Associa on ü Lincoln Heights/Richardson Dwelling New Communi es Mee ng 3 Agenda 6:30 p.m. Call to Order and Welcome – Delmar Lytle, Facilitator 6:35 p.m. Opening Remarks – Ma hew Brown, Director 6:40 p.m. Engineering Remarks – Muhammed Khalid, Interim Chief Engineer 6:45 p.m. Administra ve Remarks – Delmar Lytle 7:25 p.m. Group 3: 6:50 p.m. Group 1: • Minnesota Avenue NE Phase I • Project Development Process Overview • Six Bridges Over Wa s Branch • moveDC • 49th Street NE Traffic Calming Project • Benning Rd Transporta on Improvements • Sheriff Road NE Safety Improvements • DC Power Line Undergrounding (PLUG) 7:40 p.m. Group 4: 7:05 p.m. Group 2: • Traffic Improvements • 11th Street Bridge • Traffic Light Synchroniza on • South Capitol Street Corridor • Asset Management • Parkside Pedestrian Bridge • Green Infrastructure/Low Impact Dev • Kenilworth Aqua c Gardens Segment • Urban Forestry Anacos a Riverwalk Trail • Street Light Upgrades • Other Projects 8:00 p.m. Ques ons and Comments 8:25 p.m. Next Steps 8:30 p.m. Adjourn 4 Projects Update For Ward 7
Group 1 Transporta on Project Development Process
Planning
Na onal Environmental Policy Act (NEPA)
Final Design
Right-of-Way
Construc on
6 moveDC is… Statewide Vision Plan – Mandated by FHWA, similar to what MDOT, VDOT, and other state DOTs produce Local Transporta on Plan – like what major ci es produce, New York, San Francisco, London, Vancouver Blueprint to support future growth – District’s last long-range plan was in 1997 even as travel has changed radically
7 moveDC Engagement from Day 1! Goals: • Sustainability and Health ü Achieve 75% of District trips by non-auto modes • Citywide Accessibility and Mobility • Neighborhood Accessibility and Connec vity • Safety and Security ü Achieve zero fatali es and serious injuries on transporta on network • Public Space ü Reinforce Washington DC’s historic landscapes and quality of public space • Preserva on ü Achieve a state of good repair for all District infrastructure • Funding and Financing ü Invest to achieve outcomes within planning horizon 8
moveDC Status: • Final document was released October 21 • Two Year Ac on Plan released ü 36 recommenda ons ü Improvements to all modes ü Metrics to assess performance • Quarterly and Annual repor ng
9 Benning Road Transporta on Improvements
The purpose of this project is the reconstruc on of Benning Road and bridge(s) to provide safety and mul -modal improvements Goals: • Improve condi on of roadway and bridge(s) • Provide addi onal transit op ons • Enhance mul -modal safety • Improve mul -modal transporta on access • Support land use Schedule:
NEPA – Na onal Environmental Policy Act FHWA lead federal agency, with DDOT as joint lead FTA, NPS, NCPC invited as coopera ng agencies
10 Benning Road Transporta on Improvements PROJECT AREA
• 2 mile corridor including roadway , bridges, and 2 Metrorail sta ons • Adjacent to H Street/Benning streetcar line • Benning Road is primarily 3-lanes in each direc on from 15th Street NE to Minnesota Avenue • Benning Road is primarily 2-lanes in each direc on from Minnesota Avenue to the Benning Road Metro Sta on 11 Benning Road Transporta on Improvements STREETCAR ALIGNMENTS Today Oklahoma to Minnesota Avenue Metrorail
Oklahoma to Benning Road Metrorail Oklahoma to Minnesota Avenue and Benning Road Metrorail
12 Benning Road Transporta on Improvements
Public Involvement: • Public Mee ng 1, Scoping Mee ng April 22, 2014, 6:30-8:00 PM Department of Employment Services Building(DOES) 4058 Minnesota Ave NE Washington, DC 20019
• Public Mee ng 2, Alterna ves Development Mee ng May 28, 2014, 6:00-7:30 PM Department of Employment Services Building(DOES) 4058 Minnesota Ave NE Washington, DC 20019
• Public Mee ng 3, Public Hearing Will be scheduled
13 DC Power Line Undergrounding (DC PLUG) – Goals: • Ward 7Underground poorly performing primary electrical feeders • Improve District’s power system’s reliability and resilience Status: • Approved to begin in November 2014 • Design on Feeder 14261 (Ward 7) and Feeder 00308 (Ward 3) set to begin November 2014 Schedule: Project Milestones Date/Time of Year Plan Approval November 2014 Start Design November 2014 End Design Feb/Mar 2015 Begin Construc on Spring 2015 End Construc on Winter 2015 Projects Update For Ward 7
Group 2 11th Street Bridges Replacement Project Goals: • Improve mobility by providing separate freeway and local traffic connec ons to both direc ons 295, the SE/SW Freeway and local streets • Provide a shared use path for pedestrians and bicyclists • Replace the exis ng func onally deficient and structurally obsolete bridges • Provide an addi onal alternate evacua on Schedule: route from our Na on’s Capital Project Milestones • Include new trail connec ons, improved Date/Time of Year drainage and other environmental All Freeway and Ramp Lanes August 2014 investments Opened Status: Final Configura on of 11th Street October 2014 • Phase II (Project Comple on) is on-going, Southeast Blvd to Barney Circle Winter 2014/2015 scheduled for comple on in mid-2015 Phase II Comple on Fall 2015 Parkside Pedestrian Bridge
Goals: • Further connect neighborhoods on each side of DC 295 • Provide new access to Minnesota Avenue Metro Sta on • Make bridge safe, well-lit and
disabili es-accessible
Status: • Adver sing for construc on
Schedule: Project Milestones Date/Time of Year Adver se for Construc on Winter 2014/2015
Receive Bids from Contractors Spring 2015 Issue No ce to Proceed Spring 2015
17 South Capitol Street Corridor Project Goals: • Replace Frederick Douglass Memorial Bridge • Transform the corridor into a grand urban boulevard • Increase safety and community accessibility • Improve mul -modal transporta on op ons • Support economic development Status: • Procurement stage for Phase 1 construc on Schedule: Project Milestones Date/Time of Year No fy Short-Listed Contactor Teams January 31, 2014 Issue Request for Proposals Winter 2014/2015 Receive Technical Proposals Spring 2015 Select Design-Build Team Fall 2015 Issue No ce to Proceed Fall 2015 Final Comple on End of 2019 Kenilworth Aqua c Gardens Segment Anacos a Riverwalk Trail Goals: • Be er connect 16 communi es, the river and recrea onal sites • Increase transit sta on accessibility • Make bicycle commu ng more a rac ve • Provide missing link between Benning Road and Bladensburg Waterfront Park in larger 60-mile regional trail network
Status: Schedule: • Construc on ongoing Project Milestones Date/Time of Year Begin Construc on Spring 2014
Complete Construc on and Open Spring 2016
19 Projects Update For Ward 7
Group 3 Revitaliza on of Minnesota Avenue NE – Phase I (A Street to Benning Road) Goals: • Increase mul -modal safety in the corridor for residents and businesses • Enhancements to Minnesota Avenue include: ü Streetscape work with new roadway and sidewalks ü Traffic signal upgrades Status: ü New streetlights • Solicita on Phase ü New storm drain inlets • The project is projected to take 18 ü New landscaping with LID features months to complete a er and a tree canopy construc on start ü U lity upgrades Schedule: ü ADA upgrades and pavement Project Milestones Date/Time of Year markings Design Complete July 2014 • Traffic signals will be added to intersec on Contract Award April 2015 of Minnesota Avenue and Blaine Street 21 Six Bridges over Wa s Branch (48th Place) Goals: • New bridge deck overlay • Substructure concrete repair • Repair stone work and sidewalk • New railing
Status: • Construc on ongoing (95% complete)
Schedule: Project Milestones Date/Time of Year Construc on Started May 2014
Construc on Ends January 2015
22 Six Bridges over Wa s Branch (55th Street) Goals: • New bridge deck overlay • Substructure concrete repair • Repair stone work and sidewalk • New railing installa on
Status: • Construc on ongoing (95% complete) • Railing installa on remains to be completed
Schedule: Project Milestones Date/Time of Year Construc on Started May 2014
Construc on Ends January 2015
23 Six Bridges over Wa s Branch (Gault Place) Goals: • Superstructure replacement • Bridge railing replacement • Concrete repair
Status: • Construc on ongoing (90% complete)
Schedule: Project Milestones Date/Time of Year Construc on Started May 2014
Construc on Ends January 2015
24 Six Bridges over Wa s Branch (58th Street) Goals: • Superstructure replacement • Sidewalk improvements (widening per ADA requirements) • Rail improvements
Status: • Construc on ongoing (70% complete)
Schedule: Project Milestones Date/Time of Year Construc on Started May 2014
Construc on Ends January 2015
25 Six Bridges over Wa s Branch (Division Avenue) Goals: • Superstructure replacement • Concrete and stone work repair • Installa on of new railing
Status: • Construc on ongoing (25% complete)
Schedule: Project Milestones Date/Time of Year Construc on Started May 2014
Construc on Ends January 2015
26 Six Bridges over Wa s Branch (44th Street) Goals: • Superstructure replacement (bridge deck and girders) • Concrete and stone work repair
Status: • Construc on ongoing (25% complete)
Schedule: Project Milestones Date/Time of Year Construc on Started May 2014
Construc on Ends January 2015
27 49th Street, NE Traffic Calming Project Goals: • Implementa on of the NE Livability Study • Calm traffic along 49th Street • Low impact traffic measures • ADA compliant ramps Schedule: Status: Project Milestones Date/Time of Year • Construc on ongoing Construc on Started October 2014 (20% complete) Construc on Ends February 2015
28 Sheriff Road, NE Safety Improvements (43rd Place to 52nd Street) Goals: • Safety improvements • Improve mul -modal transporta on • Ensure safe passage for all users of the street network • Traffic calming • Resurfacing
Status: • Construc on ongoing (30% complete)
Schedule: Project Milestones Date/Time of Year Construc on Started October 2014
Construc on Ends January 2015
29 Projects Update For Ward 7
Group 4 Traffic Improvements
• Signal Op miza on • Road Safety Audits • Highway Safety Improvement Program (HSIP) • Traffic Calming Applica on
31 Pennsylvania Avenue & 27th Street Redesign Network-wide Traffic Light Synchroniza on Wards 6, 7, and 8 Goals: Op mize 203 traffic signals to… • Reduce traffic conges on/vehicular emissions • Improve bus running mes • Op mize pedestrian crossing mes Status: • Completed April 2014 - Results show benefit of $77 for every dollar spent • Vehicles ü 13% network-wide travel me savings over all peaks ü 34% reduc on in delays at traffic signals ü 23% reduc on in stops at traffic signals • Transit Opera ons ü Percentage of late buses reduced from 17% to 10% ü On- me arrivals improved from 74% to 78% ü Increase in ‘ahead-of-schedule’ arrivals • Pedestrians ü Pedestrian clearances meet Manual on Uniform Traffic Control Device STDs Asset Management Projects FY-14 Completed Loca ons Sidewalk Repairs : • 30th Street SE (Eric to Gainesville Street) • East Capitol Street SE (40th Street to • Highview Terrace SE (Denver to 34th Stoddert Place/ADA) Street) • Barnes Street NE (Hayes Street to Grant • Jay Street NE (55th Street to Nannie Place) Helen Burroughs Avenue) • Quarles Street NE (49th Street to • Kenilworth Terrace NE (Cassell Place to Eastern Avenue) Hayes Street) • 49th Street NE (Quarles to Nash Street) • Kenilworth Terrace NE (Jay Street to • Barnes Street NE (Cassell to Grant Deane Avenue) Place) • 25th Street SE (at Southern Avenue/ADA) • Dix Street NE (60th Street to Eastern • Hayes Street NE (Parkside Place to Barnes Avenue) Street/ADA) • 37th Street SE (Alabama Avenue to • Parkside Place (Burnham to Cassell Place/ Suitland Road) ADA) • Benning Road NE (at 34th Street) • Parkside Place (Cassell Place to Hayes Street/ADA) 34
Asset Management Projects FY-14 Completed Loca ons Street Paving (Local) (8.72 Lane Miles): • 38th Street SE (Carpenter Street to • Emerson Street NW (Iowa Avenue to Pennsylvania Avenue) 16th Street) • Adrian Street SE (Texas Avenue to • Greenvale Street NW (Western Avenue Hildreth Street) to Chestnut Street) • G Street SE (Ridge Road to Alabama • 33rd Street SE (Ely Place to F Street) Avenue) • Bu ernut Street NW (4th Street to Blair • Hildreth Street SE (Adrian to Burns Road) Street) • S Street SE (Texas Avenue to 38th Street) • Texas Avenue SE (Pennsylvania Avenue to S Street) • Carpenter Street SE (Texas Avenue to 38th Street) • Kenilworth Avenue NE (Deane Avenue to Hayes Street)
35 Asset Management Projects FY-14 Completed Loca ons Street Paving (Federal) (10.52 Lane Miles): Alley Repair: • H Street NW (North Capitol to First • 2200 32nd Place SE Street) • 1209 47th Place NE • 13th Street NW (Logan Circle to K Street) • 4445 Benning Road NE • Eastern Avenue NE (Bunker Hill Road to • 4916 Blaine Street NE Monroe Street) • 732 Ridge Road SE • 15th Street SE (A Street to Potomac Avenue) • M Street SE (South Capitol to 1st Street) Slurry Seal (4.51 Lane Miles): • 55th Street NE (East Capitol to Dix Street) • D Street NE (19th Street to Oklahoma Avenue) • Jay Street NE (49th Street to Division Avenue) • 55th Street SE (East Capitol Street to Central Avenue) 36 Asset Management Projects NOT A COMPLETE LIST! FY-15 Proposed Loca ons S ll Finalizing the FY-15 Work Plan Street Paving (Local and Federal) : Sidewalk Repair: • Dix Street NE (Minnesota Avenue from • 35th Street NE (Ames to Blaine Street) 40th Street, Clay Place) • Blaine Street NE (49th Street to • Southern Avenue SE (Pennsylvania Sycamore Road) Avenue to Belt Road, Fort DuPont • Edson Place NE (42nd to 44th Street) Street) • Jay Street NE (43rd Pl to 44th Street) Alley Repair: • Jay Street NE (45th Pl to 46th Street) • 1004 Chaplin Street SE • Just Street NE (Jay to 52nd Street) • 1035 49th Street NE • Meade Street NE (50th to 51st Street) • 1501 Olive Street NE • Ord Street NE (44th Street to 45th Pl) • 1542 25th Street SE • S Street SE (18th to 19th Street) • 2050 Fort Davis Street SE Slurry Seal: • 3000 V Place SE • 53rd Street NE (East Capitol to Dix • 4717 Foote Street NE Street) • 5900 Foote Street NE • 55th Street NE (Dix Street to Eastern • 640 Croissant Place SE Avenue)
37 Green Infrastructure (GI) & Low Impact Development (LID)
Watersheds • Reduce Stormwater Runoff from streets, Potomac River Rock Creek Anacostia River sidewalks, and alleys using green infrastructure • District Stormwater Regula ons (2013) require reten on of 1.2 inches of runoff • Retrofit projects – Green Alleys & sites Separated Sewer Area Combined Sewer Area citywide (primarily Separated Sewer Area) • DDOT Green Infrastructure Standards • ddot.dc.gov/GreenInfrastructure
38 Green Infrastructure (GI) Prac ces Permeable Bioreten on Pavement
Before: P SE St open
Reducing Impervious Tree A er: P St SE closed Surface Space Design
P St NE & North Capitol
Before A er 39 Green Infrastructure (GI) & Low Impact Development (LID) Ward 7 Projects
Project Site Design Construc on Status Start Fitch Place NE (Ward 7) Complete Spring 2015 Fort Dupont St & Q St SE 90% Summer 2015 (Ward 7) complete Fitch Place @ Alger Park Upland LID Start Spring 2016 Division Ave NE 2015
Fort Dupont Street & Q St SE Alger Park Upland LID: 31st Street & W St SE Landscaped Medians/Green Spaces/Tree Services Ward Based Goals: • Support and enhance storm water capture rates from the Districts streets as mandated by EPA in the MS 4 permit • Tree Boxes shall be maintained by the abu ng owner as per the DCMR 24 • Street Trees are maintained by the UFA ISA cer fied arborist and services should be requested through the Mayor Call Center at 311 • Landscape/green spaces enhance the neighborhood and provide traffic calming Schedule: Status: Trash Weekly except winter months • Ongoing and seasonally based Weeding Monthly from April to October Mulching As needed Pruning As needed Plan ng As needed 41 Ward 7 Tree Plan ng Goals: • Support and enhance community livability • Sa sfy federally-mandated stormwater management consent decree (MS4 Permit) • Deliver environmental services ü Cleaner air - Cleaner water • To calm traffic • To beau fy neighborhoods! Status: • This fall and spring UFA will install over 350 trees in Ward 7 • DDOT’s plan ng season will start in October and will con nue through April The link to all our plan ng sites can be found on the DDOT web site under - urban forestry - DDOT Tree Services Schedule - first map in the middle of the screen Web Site is h p://ddot.dc.gov/node/500202 42 Branch Avenue, SE Streetlight Upgrade
Goals: • Upgrade exis ng streetlight system between Randle Circle to Pennsylvania Avenue. • Provide be er uniformity of light mee ng engineering standards • Enhance safety and security • Install more efficient LED fixtures (reduces power cost).
Status: Construc on was completed in July 2014 Recent Streetlight Upgrade in Ward 7 Goals: • Upgrade exis ng streetlight system • Provide be er uniformity of light mee ng engineering standards • Enhance safety and security • Install more efficient LED fixtures (reduces power cost)
Loca on No. of Lights Exis ng Light New Light Comple on Upgraded Date Alley Behind 3 none 75W LED 10/01/2014 5221 Clay St 1000 Block of 5 250W HPS 110W LED 10/06/2014 49th Place NE 3300 Block of 5 250W HPS 110W LED 10/02/2014 Croffut Place SE 3700 Block of 9 100W HPS 60W LED 10/07/2014 Carpenter Street SE East Capitol Streetlight Design from 40th Street to 53rd Street
Goals: • Upgrade exis ng streetlight system • Provide be er uniformity of light mee ng West East engineering standards Limit Limit • Enhance safety and security • Install more efficient LED fixtures (reduces power cost).
Status: Design Underway.
Schedule:
Design comple on January 2015 Expected construc on start May 2015 Expected construc on end December 2015 Other Projects with Ward 7 Impacts
• Pennsylvania Avenue-Potomac Avenue Pedestrian Safety Study • Barney Circle and Southeast Boulevard
46 Upcoming Projects Update Mee ngs
• Ward 2 (December 8, 2014) – New York Avenue Presbyterian Church, 1313 New York Avenue, NW • Ward 6 (January 26, 2015) – Tyler Elementary School, 1001 G Street, SE • Ward 3 (February 17, 2015) • Ward 5 (March 9, 2015) • Ward 4 (March 30, 2015)
Visit the upcoming events sec on on the homepage of ddot.dc.gov to find out the latest informa on on mee ng dates and loca ons
47 Agenda 6:30 p.m. Call to Order and Welcome – Delmar Lytle, Facilitator 6:35 p.m. Opening Remarks – Ma hew Brown, Director 6:40 p.m. Engineering Remarks – Muhammed Khalid, Interim Chief Engineer 6:45 p.m. Administra ve Remarks – Delmar Lytle 7:25 p.m. Group 3: 6:50 p.m. Group 1: • Minnesota Avenue NE Phase I • Project Development Process Overview • Six Bridges Over Wa s Branch • moveDC • 49th Street NE Traffic Calming Project • Benning Rd Transporta on Improvements • Sheriff Road NE Safety Improvements • DC Power Line Undergrounding (PLUG) 7:40 p.m. Group 4: 7:05 p.m. Group 2: • Traffic Improvements • 11th Street Bridge • Traffic Light Synchroniza on • South Capitol Street Corridor • Asset Management • Parkside Pedestrian Bridge • Green Infrastructure/Low Impact Dev • Kenilworth Aqua c Gardens Segment • Urban Forestry Anacos a Riverwalk Trail • Street Light Upgrades • Other Projects 8:00 p.m. Ques ons and Comments 8:25 p.m. Next Steps 8:30 p.m. Adjourn 48 Thank you! Ques ons and Comments?