BY SPEED Steel Authority of Limited POST Steel Plant Rourkela – 769011 Fax : 0661-2510183

Ref. No.: 691/EE/59/228 Date :19/05/2020

Dear Sir,

Sub : Implementation Status of Env. Clearance Conditions issued to RSP.

Ref. : EC vide ref. no. F No. J-11011/757/2007-IA II(I), dated 29/01/2008, extension order dated 05/07/2013 & amendment order dated 26/03/2014.

# # #

This has reference to the aforesaid Environment Clearance (EC) accorded to Rourkela Steel Plant (RSP) for its Expansion project, its extension order and amendment w.r.t. water consumption. The implementation status of the various Special and General Conditions mentioned in EC order for the period of October 2019 to March, 2020 is enclosed.

Thanking you sir, With warm regards,

Yours faithfully, For Rourkela Steel Plant,

(S N Xess) General Manager I/c Environmental Engg. Department

Note : Soft copy mailed to [email protected]

To : The Dy. Director General of Forests (C), Eastern Zone Regional Office, Ministry of Environment & Forests, A/3, Chandrasekharpur, Bhubaneswar. – 751023.

Environmental Engg. Department, 1 st Floor of OHSC Building, Rourkela Steel Plant, Rourkela Phone : 0661-2510395 Fax : 0661-2510183 Regd. Office : Ispat Bhawan, Lodi Road, New Delhi – 110 003

Anexure -2

Steel Authority of India Limited Rourkela Steel Plant’s Expansion Project (Environment Clearance vide ref.no. F No. J-11011/757/2007-IA II(I), dated 29/01/2008 & EC extension up to 29/01/2018 vide order , dated 05/07/2013 & Amendment order dated 26/03/2014) Half Yearly Report (October, 2019 – March, 2020) Contact Persons : Sri S N Xess, GM I/c (Env. Engg.) Phone : 0661-2447258 Sri V V R Murty, GM(Env. Engg.) Phone : 0661-2448254

Special Conditions

SN. CONDITION STATUS/ ACTION PLAN

RSP has 6 no. of Coke Oven Batteries. • COB#1, COB#3, COB#4 & COB#5 have been rebuilt. • COB#2 has been put down, awaiting for re-building. • COB#6 is a new battery constructed under recent expansion. All the existing batteries shall be rebuilt by

2012 meeting all the pollution control Battery wise details are, i) norms as per CPCB guidelines and a • COB#1 -- Rebuilt & commissioned in May, 2007 commitment in this regard shall be • COB#2 – Put down since March, 2016 for rebuilding. submitted to the Ministry • COB#3 – Rebuilt and commissioned in December, 2016. • COB#4 – Last rebuilt & commissioned in May 2010 • COB#5 – Last rebuilt & commissioned in July, 2000 • COB#6 -- Newly Constructed & commissioned in March, 2014

The industry shall follow coke oven RSP is following the Coke Oven Standards and also following E(P) Rules. VOCs standards as per E(P) Rules. VOCs from the ii) are being monitored by a NABL accredited external agency. The monitoring coke oven shall be monitored and results along with interpretation are given at Annexure- 1. controlled as per CPCB guidelines.

All out efforts are being made to further reduce waste generation, reduce all Efforts shall be made to further reduce the stack emissions, thereby to improve ambient air quality. A report is being existing ambient air and stack emissions submitted to CPCB and SPCB once in a month regularly giving the status of stack iii) and waste generation and a report emissions, ambient air quality & solid waste utilization. A report showing the submitted to the Ministry, its Regional stack emissions, ambient air quality and solid waste utilization for the period of Office at Bhubaneswar, CPCB and OPCB. October, 2019 – March, 2020 along with interpretation are given at Annexure-2, 3 & 4 respectively.

Efforts shall be made to reduce RSPM a) All out efforts are being put for reducing RSPM levels. levels in the ambient air and a time bound b) On-line stack monitoring facilities are provided in all stacks under Expansion action plan shall be submitted. On-line Project stack monitoring facilities for all the stacks c) All air pollution control systems viz., ESPs, Bag Filters etc., are designed to and sufficient air pollution control control stack emissions < 100 mg/Nm3. iv) methods shall be provided to control d) The stack emissions are monitored regularly and data submitted to all emissions below 100 mg/Nm 3 viz. ESP and statutory authorities once in a month. bag filters etc. and data submitted to the Ministry’s Regional Office at The ambient air quality & stack emissions during October, 2019 – March, 2020 Bhubaneswar, CPCB and OSPCB along with interpretation are given at Annexure -2 & 3.

2

SN. CONDITION STATUS/ ACTION PLAN

a) 3 no. of ESPs were provided in Sinter Plant No. 3 & another 3 no. of ESPs were provided in Blast Furnace No. 5, under recently concluded Expansion Project. Electrostatic precipitator (ESP) shall be b) One new ESP was provided for MP Boiler#3 and 2 no. of ESPs were provided to Sinter plant, Power Plant and Blast augmented for HP Boiler#5 & #6 of Captive Power Plant#1 for bringing Furnace (BF) to control gaseous emissions from down stack emissions below 100 mg/Nm3. all the vents/stacks within 100 mg/Nm 3. Coal c) CDI is provided in all Blast Furnaces viz., BFc#1, BFc#4 & BFc#5. dust injection (CDI) shall be provided to Blast d) 9 no. of Bag houses were provided in Calcining Plant. furnace plants. Bag filter shall be provided to e) Dedicated ESPs are provided for Cast House de-fuming and Stock House v) lime Calcining Plant, new vertical shaft kiln and of BFc#5. Dolomite plant. Emissions shall be controlled f) Dedicated ESPs were provided for Cast House De-fuming of BFc#1 & from the Cast house and Stock house within BFc#4. permissible limits. High Pressure Liquor g) HPALA system was provided in new COB#6. Aspiration (HPLA) system shall be provided to new Coke Oven Battery The stack emissions i.e., at the outlet of pollution control systems are regularly monitored and cross checked with norms. Preventive and corrective actions are being taken for maximizing the efficiency of ESPs based on the monitoring results. BaP, PAHs and VOCs are monitored in Ambient air and Stack emissions regularly and the reports are submitted to all statutory authorities. Regular monitoring of the Benzo(a)Pyrene, Poly

Aromatic Hydrocarbons (PAHs) and Volatile vi) The PAH levels along with interpretations are given at Annexure-5. Organic Compounds (VOCs) in the ambient air

and stack emissions shall be carried out. VOCs in stacks and ambient air are monitored and the results along with interpretation are given at Annexure- 1 & 2. Secondary fugitive emissions from all the Dust extraction systems viz., ESPs, Bag Houses & Cold Fog Dust suppression sources including blast furnace and sinter plant systems are provided in COB#6, Sinter Plant#3 & Blast Furnace #5 to control shall be controlled within the latest permissible the fugitive emissions and to meet statutory guidelines. vii) limits issued by the Ministry and regularly monitored. Guidelines / Code of Practice issued RSP is following all the CPCB guidelines / code of practices in controlling by the CPCB shall be followed. secondary fugitive emissions. Total make up water requirement of the Plant a) The water requirement is being confined to 2,27,352 m 3/day as per the from Brahamani River shall not exceed Corrigendum issued by MoEF dated 26/03/2014. (Total water drawl *2,27,352 m3/day and prior permission shall be in March., 2020 was 1,99,664 m3/day). obtained from the concerned department. No

ground water shall be used for the plant. The b) Dedicated WWTPs are provided in all Units & treated water is recycled effluent shall be treated in the effluent back. treatment plant. Maximum treated

wastewater shall be recycled and reused in the viii) c) Only little quantity of blow down water is discharged after confirming process for cooling, gas cleaning plant (GCP), to norms. steel making, slag granulation plant (SGP), dust

suppression, green belt development etc. The d) No ground water is used in RSP. excess wastewater shall be discharged only

after conforming all the parameters to the The quality of finally treated effluent discharged to river during prescribed standards within the permissible October, 2019 – March, 2020, monitored by a NABL accredited external limits of OPCB. agency along with interpretation is given at Annexure-6. *MoEF’s Corrigendum dated 26 th March, 2014. a) The Solid Waste Utilization for October, 2019 – March, 2020 is 79.65% As proposed, 90% of the solid waste shall be b) The un-utilized Solid Wastes are kept inside RSP’s Plant boundary for recycled and reused and remaining shall be future utilization. disposed off in secured landfill designed as per c) A Secured Landfill Facility has been constructed as per CPCB guidelines, the specifications of the CPCB. BF slag shall be first time in SAIL and is in operation. granulated and used in environment-friendly The utilization of total solid wastes have already been enhanced by manner. Slag from SMS-I & II shall be used for maximizing the utilization of BFc slag for cement making. SMS slag ix) making road embankments. Iron ore fines, utilization is being increased by enhancing its utilization in base mix Fluxes cinder, Mill scales and Scrap etc. shall be preparation (Sinter making) in blast furnaces, as rail ballast, road making recycled and reused in Sintering Plant. SMS and its use for development of land areas inside the plant premises. All the scrap shall be recycled in Steel Melting Shop. metallic scrap is being recycled back to SMS. All the waste oil is being sold All the waste oil shall be sold to recyclers/re- to the outside parties who are having valid registration with statutory processors. agencies. The solid waste utilization during October, 2019 – March, 2020 is given at Annexure-4.

3

SN. CONDITION STATUS/ ACTION PLAN Ground Water Samples are regularly collected from waste disposal areas & Secured Land Fills i.e., from Sitalpara dump area and Old BFc Slag Dump area (Deogaon) once in a month and are analyzed through a NABL accredited external agency. The data is submitted to all statutory authorities through monthly basis. Ground water monitoring around the solid waste

disposal site / secured landfill (SLF) shall be carried out x) The ground water quality during October, 2019 – March, 2020 regularly and report submitted to the Ministry’s along with interpretation is given at Annexure-7. Regional Office at Bhubaneswar / CPCB and OPCB.

Monitoring of the Ground Water Table levels has been started at 8 locations covering all directions along the plant boundary using Water Level meter. Location wise Water table level is given at Annexure-7a. An action plan for the disposal of fly ash, granulated All the Blast Furnace Slag is being granulated through in-house slag and SMS slag shall be submitted to the Ministry within 3 granulation units and used for making slag cement. months. All the BF slag generated shall be granulated

and provided to cement manufacturers for further State of the art technologies are being adopted in steel making so utilization and should not be disposed off anywhere xi) that the SMS slag generation rate will be minimized. The SMS slag else. SMS slag shall also be properly utilized. All the is being utilized for Sinter Making through base mix, charged into char from DRI plant shall be utilized in AFBC boiler of Blast Furnaces to replace lime stone and also used for pavement power plant and no char shall be disposed off anywhere making and as rail ballast. The balance slag is used for else. All the fly ash shall be utilized as per the Fly Ash development of land inside the plant premises. Notification, 1999 and subsequently amended in 2003.

There is no additional fly ash generation after implementation of this modernization cum expansion project, as the additional power is being obtained from Top Recovery Turbine (14 MW) & Power Blowing Station of Blast Furnace No. 5 (36 MW), Back Pressure An action plan for the disposal of fly ash, granulated Turbo Generator (6.4 MW) of COB#7 and remaining 110 MW and SMS slag shall be submitted to the Ministry within 3 power is being obtained from State Grid. months. All the BF slag generated shall be granulated

and provided to cement manufacturers for further As per the present agreement with NTPC, the joint venture power utilization and should not be disposed off anywhere xi) company NSPCL is managing the fly ash, generated from captive else. SMS slag shall also be properly utilized. All the power plant of RSP. The fly ash is being utilized for dyke height char from DRI plant shall be utilized in AFBC boiler of raising of Ash Ponds, being given free of cost to the fly ash users. power plant and no char shall be disposed off anywhere

else. All the fly ash shall be utilized as per the Fly Ash Dry fly ash is being given to local entrepreneurs for brick making Notification, 1999 and subsequently amended in 2003. free of cost. All the fly ash is being utilized as per the Fly Ash Notification, 1999, amended from time to time.

There is no char generation in Rourkela Steel Plant

RSP is developing green belt in and around steel plant. 1,46,397 Green belt shall be developed in 33 % area within and no. of saplings have been planted during 2019-20. So far more xii) around the plant premises as per the CPCB guidelines in than 49 lakh trees have already been planted, covering more than consultation with DFO. 33% of the area.

Recommendations of the State Forest Department shall be obtained regarding impact of the proposed The findings of EIA/EMP were submitted to State Forest xiii) expansion of the plant on the Sona Parbat RF, North Department. DFO, Rourkela has authenticated the report and the Chirobeda RF and South Chirobeda RF and copy of the letter from DFO is enclosed at Annexure-8. implemented. RSP is strictly following all the CREP action points and will continue All the recommendations mentioned in the CREP to follow the same. The status of implementation is being xiv) guidelines for the steel plants shall be implemented submitted to SPCB, CPCB & MoEFCC on monthly basis. CREP status report for the month of March, 2020 is enclosed as Annexure-20.

4

GENERAL CONDITIONS

SN. CONDITION STATUS/ ACTION PLAN

The project authorities must strictly adhere to the RSP strictly adheres to the stipulations made by State i) stipulations made by the Orissa Pollution Control Board Pollution Control Board, Odisha and State Government. (OPCB) and the State Government No further expansion or modifications in the plant should be The Expansion Project is being implemented as per the ii) carried out without prior approval of the Ministry of approval obtained from MoEFCC. Environment and Forests. RSP is following all the standards notified by the MoEF and The gaseous emissions from various process units shall State Pollution Control Board from time to time. conform to the load/mass based standards notified by this

Ministry on 19th May, 1993 and standards prescribed from a) All gaseous emissions (SO2, NOx & CO) are being time to time. The state Board may specify more stringent monitored regularly and meeting the norms. standards for the relevant parameters keeping in view the

nature of the industry and its size and location. At no time, iii) b) 20 no. of On- line stack monitoring systems for SPM are the emission level shall go beyond the prescribed standards. installed in RSP and the systems have been uplinked On-line continuous monitoring system shall be installed in with the servers of SPCB & CPCB. stacks to monitor SPM and interlocking facilities shall be

provided so that process can be automatically stopped in case c) State of the art Burners are provided in COB#6 for under emission level exceeds the limit. NOx burners shall be firing for controlling NOx levels. installed to control NOx levels

a) RSP has installed 6 no. of Ambient Air Quality Monitoring At least four ambient air quality-monitoring stations shall be Stations in consultation with SPCB covering all established in the downward direction as well as where directions. maximum ground level concentration of SPM, SO2 and NOX iv) are anticipated in consultation with the OPCB. Data on b) The monitored data viz., Stack Emissions and Ambient ambient air quality and stack emission shall be regularly Air Quality is being submitted to all statutory authorities submitted to this Ministry including its Regional Office at on monthly basis regularly through email. The ambient Bhubaneswar / OPCB / CPCB once in six months air quality for the period Oct. – March, 2020 along with data interpretation is given at Annexure – 2. a) RSP has a dedicated Env. Engg. Department with an Environment Laboratory which is certified with ISO- 14001. In-plant control measures for checking fugitive emissions b) Env. Engg. Dept.’s monitoring group carry out monitoring from all the vulnerable sources like Coke oven area, Sinter of fugitive emissions regularly throughout the plant and plant, Blast Furnace area etc. shall be adopted. Further, data is submitted to statutory authorities regularly on specific measures like water sprinkling shall be carried out at monthly basis. In addition, RSP engaged a NABL the stock piles of raw material, stacker, reclaimer, transfer accredited external agency for monitoring fugitive points etc. Dust extraction system and bag filters shall be emissions and the data is submitted to statutory provided to the sinter plant, stock house, blast furnace and steel melting shop etc. Fume extraction system in steel authorities. v) refining units shall also be provided. Centralized dedusting c) Dust suppression systems are provided in stock yard. system i.e. collection of fugitive emissions through suction d) Dust extraction systems viz., ESP & Bag Houses are hood and subsequent treatment through bag filter or any provided in all Expansion Units. other device and finally emitted through a stack of e) Fume extraction units with Bag House and ESP are appropriately designed and height conforming to the provided for LHF#2A, #2B & #3 of SMS#2. standards for induction furnaces in the industry shall be f) Dog house systems are being provided for control of provided. Fugitive emissions shall be controlled, regularly monitored and records maintained. secondary fugitive emissions from converters of SMS#2

The fugitive emissions monitored during October, 2019 – March, 2020 along with data interpretation is given at Annexure-9. a) Dedicated Waste Water Treatment Plants are provided Industrial wastewater shall be properly collected, treated so in all units of Expansion Units. as to conform to the standards prescribed under GSR 422 (E) b) The treated water is recycled back to the process. vi) dated 19th May, 1993 and 31st December, 1993 or as c) Only little quantity of blow down water is discharged amended form time to time. The treated wastewater shall be through a net work of drains to Lagoon for final utilized for plantation purpose. treatment.

5

SN. CONDITION STATUS/ ACTION PLAN

a) Noise control devices viz., Acoustic Hoods, Silencers and The overall noise levels in and around the plant area Enclosures are provided to control noise at source. shall be kept well within the standards (85 dBA) by b) RSP has developed a buffer zone along with RSP plant boundary by providing noise control measures including acoustic planting Trees for control of Noise. hoods, silencers, enclosures etc. on all sources of vii) c) Noise levels are regularly monitored by Env. Engg. Dept. and data noise generation. The ambient noise levels should is submitted to Statutory authorities on monthly basis. conform to the standards prescribed under EPA The monitored noise levels at various ambient air quality monitoring Rules, 1989 viz. 75 dBA (daytime) and 70 dBA stations during October, 2019 – March, 2020 along with data (nighttime). interpretation are given at Annexure-2.

The company shall develop surface water harvesting structures to harvest the rain water for utilization in 16 no. of Rain Water Harvesting systems have been constructed and viii) the lean season besides recharging the ground put into operation during 2018-20. water table.

RSP established Occupational Health Service Center (OHSC) inside the Occupational Health Surveillance of the workers plant itself with dedicated team of doctors, and other skilled medical ix) shall be done on a regular basis and records staff. Health checkup of all the workers is carried out by OHSC once in maintained as per the Factories Act. a year and the records are being kept. RSP is implementing all the action points mentioned under CREP for Recommendations made in the CREP guidelines Steel Industry. The status is being submitted on monthly basis to all x) issued for the steel plants shall be implemented. statutory authorities, CREP status report for the month of March, 2020 is given as Annexure-20. a) All the pollution control measures recommended in EIA/EMP report have been implemented. b) RSP has a dedicated CSR department for the socio-economic development activities in surrounding villages. The main focus areas of CSR department are; The project proponent shall also comply with all the a) Infrastructure development environmental protection measures and safeguards b) Water & Sanitation recommended in the EIA / EMP report. Further, the c) Education company shall undertake socio economic xi) d) Health development activities in the surrounding villages e) Sustainable livelihood and Income generation like community development programmes, educational programmes, drinking water supply and programmes health care etc. f) Alternate Renewable Energy g) Community welfare & Industrial Township development

The highlights of CSR activities during 2019-20 are given at Annexure-14. Funds allocated for the Pollution control were not diverted. The list of Pollution Control schemes implemented in different new units and The project authorities shall utilize Rs. 614.00 Crs. their value are given below; and Rs. 36.00 Crs. earmarked total capital cost and a) COB#6 Complex : Rs. 440 Crs. recurring cost/annum for environment pollution b) Blast Furnace No. 5 : Rs. 80 Crs. control measures respectively judiciously to c) Sinter Plant#3 : Rs. 47 Crs. implement the conditions stipulated by the Ministry d) Steel Melting Shop#2 : Rs. 120 Crs. xii) of Environment and Forests as well as the State e) New Plate Mill : Rs. 10 Crs. Government. An implementation schedule for f) New Calcining Plant#2 : Rs. 10 Crs. implementing all the conditions stipulated herein g) New OBBP : Rs. 5 Crs. shall be submitted to the Ministry’s Regional Office Total : Rs. 616 Crs. at Bhubaneswar. The funds so provided shall not be RSP has not diverted the funds allocated for pollution control measures diverted for any other purpose. and implemented all the conditions. The implementation schedule of various conditions stipulated in EC is enclosed at Annexure-10.

6

SN. CONDITION STATUS/ ACTION PLAN

The Regional Office of this Ministry at Bhubaneswar/CPCB/OPCB will monitor the stipulated The compliance report is being submitted & uploaded to xiii) conditions. A six monthly compliance report and the MoEFCC’s web site, once in six months, regularly. monitored data along with statistical interpretation shall be submitted to them regularly.

RSP released an advertisement In the following news papers. The Project Proponent shall inform the public that the project

has been accorded environmental clearance by the Ministry 1) The Times of India, Bhubaneswar edition dated and copies of the clearance letter are available with the 07/02/2008. (English) OPCB/Committee and may also be seen at Website of the 2) Samaj, Rourkela dated 07/02/2008 (Oriya) Ministry of Environment and Forests at http:/envfor.nic.in. xiv) This shall be advertised within seven days from the date of Copies of the paper advertisement were submitted to MoEF issue of the clearance letter, at least in two local newspapers regional office vide letter no. 691/EE/59/354-355, dated that are widely circulated in the region of which one shall be 08/02/2008. in the vernacular language of the locality concerned and a

copy of the same shall be forwarded to the Regional office. Copy of the news paper cutting is enclosed at Annexure-11. Project authorities shall inform the Regional Office as well as the Ministry, the date of financial closure and final approval The project was sanctioned by SAIL on 23/06/2007. Copy of xv) of the project by the concerned authorities and the date of the sanction order is enclosed at Annexure-12. The land commencing the land development work started in November,2008. development work.

Additional Conditions

(Reference : Letter of Dr. V P Upadhyay, Director(S) addressed to Managing Director, RSP 106-9/EPE, dtd. 08/06/2011)

SN. CONDITION STATUS/ ACTION PLAN Ambient air quality is monitored continuously using 4 no. of AAQMS- automatic ambient air quality monitoring stations installed at Sector-2, Sector-22 of Steel Township and along the plants boundary - one at ERWPP and another at SSSY Continuous monitoring of stack emissions as well as ambient area. All these four stations have been uplinked with SPCB & air quality (as per notified standards) shall be carried out and CPCB servers. In addition to this, ambient air quality is continuous records maintained. Based on the monitored regularly monitored at six number of ambient air stations (i) data, necessary corrective measures as may be required from located along plant’s boundary. Stack emissions are also time to time shall be taken to ensure that the levels are monitored regularly. Continuous records are maintained for within permissible limits. The results of monitoring shall also ambient air quality and stack emissions and necessary be put on the website of the company in the public domain corrective actions are taken to contain pollution.

The monitoring results are uploaded to SAIL’s official Web Site at www.sail.co.in (Web page  Environment Management under Rourkela Steel Plant)

The six monthly monitoring reports as well as the monitored The monitored data as per Env. Clearance conditions are data on various parameters as stipulated in the environment submitted to State Pollution Control Board, Odisha on clearance conditions shall be put on the website of the (ii) monthly basis, regularly. This half yearly compliance report company and also regularly updated. The monitored data for the period October, 2019 – March, 2020 will be shall also be submitted to respective State Pollution Control uploaded to SAIL’s website by 01/06/2020. Board/ UTPCC and the Regional Office of MoEF.

The ambient air quality data and stack emission data is displayed in the form of two number of Flex Board of 8’ x 5’ The ambient air quality data as well as the stack emission size, in front of Main Gate of RSP. The data is updated on data will also be displayed in public domain at some quarterly basis. (iii) prominent place near the main gate of the company and updated in real time. The environment data is being continuously displayed through LED based electronic display board which was installed at Main gate of RSP.

7

Annexure-1

Data interpretation of Monitoring results of VOC in Stack & Work zone of Coke Ovens (October, 2019 – March, 2020) April., Oct., Change Stack 2019 – Oct., Nov., Dec., Jan., Feb., March., 2019 – w.r.t. SN. Department connected to Sep., 2019 2019 2019 2020 2020 2020 March., Oct., 2018- 2019 2020 March., 2019 1. Battery#1 BDL BDL BDL BDL BDL BDL BDL BDL No change 2. Battery#2 S/D S/D S/D S/D S/D S/D S/D S/D No change 3. Battery#3 BDL BDL BDL BDL BDL BDL BDL BDL No change Coke Ovens 4. Battery#4 BDL BDL BDL BDL BDL BDL BDL BDL No change 5. Battery#5 BDL BDL BDL BDL BDL BDL BDL BDL No change 6. Batery#6 BDL BDL BDL BDL BDL BDL BDL BDL No change 7. Process ESP BDL S/D BDL BDL BDL BDL BDL BDL No change Sinter 8. Plant#1 Addl. ESP BDL S/D BDL BDL BDL BDL BDL BDL No change 9. Old ESP BDL S/D BDL BDL BDL BDL BDL BDL No change 10. Process ESP BDL BDL BDL BDL BDL BDL BDL BDL No change Sinter Space De 11. Plant#2 BDL BDL BDL BDL BDL BDL BDL BDL No change dusting ESP 12. Process ESP-1 BDL BDL BDL BDL BDL BDL BDL BDL No change 13. Sinter Process ESP-2 BDL BDL BDL BDL BDL BDL BDL BDL No change Plant#3 Plant de- 14. BDL BDL BDL BDL BDL BDL BDL BDL No change dusting ESP 15. TA Line BDL BDL BDL BDL BDL BDL BDL BDL No change 16. Decarb Line BDL BDL BDL BDL BDL BDL BDL BDL No change Silicon Steel 17 Pickling line BDL BDL BDL BDL BDL BDL BDL BDL No change Mill Ammonia 18. BDL BDL BDL BDL BDL BDL BDL BDL No change cracking unit 19. MP Boiler#1 BDL BDL S/D BDL BDL BDL BDL BDL No change 20. MP Boiler#2 BDL BDL BDL BDL BDL BDL BDL BDL No change 21 Captive MP Boiler#3 BDL BDL BDL BDL BDL BDL BDL BDL No change 22. Power HP Boiler#1 BDL S/D S/D S/D BDL S/D S/D BDL No change 23. Plant#1 HP Boiler#2 BDL BDL BDL BDL S/D BDL BDL BDL No change 24. HP Boiler#5 BDL BDL BDL BDL BDL BDL BDL BDL No change 25. HP Boiler#6 BDL BDL BDL BDL BDL BDL BDL BDL No change

Work zone Monitoring :

Oct., April., - Change w.r.t. Depart- Oct., Nov., Dec., Jan., Feb., March. 2019 – SN. Work zone location Sep., April., - Sep., ment 2019 2019 2019 2020 2020 , 2020 March., 2019 2019 2020 Ram side – at Central 1. <1 <1 <1 <1 <1 <1 <1 <1 No change control room Coke side – at Central +1.56 % (Lower) 2. 6.4 – 8.1 6.9 7.5 8.2 7.6 6.5 7.8 6.5 – 8.2 control room +1.23 % (Upper) Coke Near Wharf – at +3.22% (Lower) 3. 6.2 – 8.3 6.4 7.5 7.8 7.8 8.1 6.9 6.4 – 8.1 Ovens Central Control room -2.40% (Upper) -8.69% (Lower) 4. Near Quenching Tower 6.9 – 7.9 6.3 7.5 7.9 7.4 8.2 7.6 6.3 – 8.2 +3.79% (Upper) +1.56 % (Lower) 5. Coke Oven top 6.4 – 7.4 6.5 7.3 7.4 7.9 8.1 7.6 6.5 – 8.1 +9.45 % (Upper) (Units : all are in micrograms/m3) %Change is calculated for Lower limit and Upper limit of the range. BDL : Below detectable limit <1 & S/D : Shutdown

8

Annexure - 2 Data interpretation of Monitoring results of Ambient Air Quality in Rourkela Steel Plant (October, 2019 – March, 2020)

LOCA- Arse- Ben- PAH Min. / Max PM 2.5 PM 10 SO 2 NOx CO Pb NH Nickel Noise VOC TION 3 nic zene BaP

Oct., 2019 – 28.8 – 59.8 – 11.8 – 20.3 – 392 - 10.2 – 8.22 – 67.4 – <0.01 <0.01 ND ND BDL EED Mar., 2020 44.2 80.4 14.8 27.3 420 13.3 9.21 74.1 Building Apr., – Sep., 31 - 73.1- 11- 21.8- 100- 10.8- <2- 66.8- <0.01 <0.01 ND ND BDL 2019 45.4 87 14.7 29 432 29 10.45 71.7

% Lower limit -7.09% -18.19 % +7.27% -6.88% +292% -5.55% +311% +0.89% 0% 0% - - - Change Upper Limit - 2.64% -7.58% +0.68% -5.86% -2.77% -54.13% -11.86% +3.34%

Oct., 2019 – 24.2- 57.2- 10.1- 18.7- 312- 9.4- 8.34- 69.2- <0.01 <0.01 ND ND BDL Mar., 2020 38.8 69.7 12.4 23.4 337 12.4 9.41 74.2 RDCIS Building Apr., – Sep., 29.8- 64.2- 10- 17.3- 100- 10.9- <2 – 70.4- <0.01 <0.01 ND ND BDL 2019 34 86 12.6 30 312 31 10.9 72.8

Lower limit -18.7% -10.9% +1% +8.09% +212% -13.7% +317% -1.7% % Change 0% 0% - - - Upper Limit +14.4% -18.9% -1.58% -22% +8.01% -60% -13.6% +1.9% Oct., 2019 – 27.9- 58.1- 14.2- 18.9- 348- 9.7- 67.2- <0.01 <0.01 9.0-9.8 ND ND BDL Mar., 2020 34.8 81.2 14.7 25.1 378 10.3 73.6 PMPH 67.8- Building Apr., – Sep., 23.6- 13- 19.8- <100- <2 – 65.2- 84 <0.01 9.6-21 <0.01 ND ND BDL 2019 32 16.2 29 355 10.22 71.7

Lower limit +18.2% -14.3% +9.23% -4.54% +248% +1.04% +350% +3.06% % Change 0% 0% - - - Upper Limit +8.75% -3.33% -9.25% -13.4% +6.47% -50.9% -4.10% +2.64% Oct., 2019 – 28.1- 57.4- 10.8- 18.8- 388- 10.3- 8.3- 66.4- <0.01 <0.01 ND ND BDL BOD Mar., 2020 48.1 81.5 13.8 25.1 437 12.6 10.2 73.3 Building Apr., – Sep., 36- 75.6- 11- 19.4- <100- 11.9- <2 – 64.2- <0.01 <0.01 ND ND BDL 2019 51.3 89.1 14.6 28 429 30 13.11 71.7 Lower limit -21.9% -24.0% -1.81% -3.09% +288% -13.4% +315% +3.42% % Change 0% 0% - - - Upper Limit -6.23% -8.5% -5.47% -10.3% +1.86% -58% -22.1% +2.23% Oct., 2019 – 27.2- 58.4- 10.9- 20.4- 372- 10.3- 6.56- 66.0- TOP#2 <0.01 <0.01 ND ND BDL Mar., 2020 38.2 78.6 19.6 23.7 406 12.4 8.7 73.7 Admn. Apr., – Sep., 33- 66.7- 12- 19.4- <100- 11.4- <2 - 64.2- Building <0.01 <0.01 ND ND BDL 2019 36.4 83 16.8 30 410 22 7.85 71.7

Lower limit -17.5% -12.4% -9.16% +5.15% +272% -9.64% +228% +2.80% % Change 0% 0% - - - Upper Limit +5.49% -5.3% +16.6% -21% -0.97% -43.6% +10.8% +2.78%

Oct., 2019 – 27.2- 59.4- 10.5- 18.7- 342- 10.5- 8.7- 68.4- OBBP <0.01 <0.01 ND ND BDL Mar., 2020 40.2 77.5 11.8 23.1 385 13.1 10.26 73.6 Admn. Apr., – Sep., 28- 73.1- 18.3- <100- 12.8- <2- 65.8- Building 8-13.2 <0.01 <0.01 ND ND BDL 2019 47.6 86.5 25 386 23 11.23 71.5 Lower limit -2.85% -18.7% +31.2% +2.18% +242% -17.9% +335% +3.95% % Change 0% 0% - - - Upper Limit -15.5% -10.4% -10.6% -7.6% -0.25% -43.0% -8.63% +2.93%

60 100 80 80 4000 1.0 400 6 1.0 20 ng/m3 75 dB(A) 5 µµµg/m3 - Norm µµµg/m3 µµµg/m3 µµµg/m3 µµµg/m3 µµµg/m3 µµµg/m3 µµµg/m3 ng/m3 ng/m3

Units : All are in micro grams/m 3 except BaP which is in ng/m 3 Note: %Change is calculated for Lower limit and Upper limit of the range. PAH (Bap) is done once in a year. ND : Not detectable; BDL : Below detectable limit <1 & S/D : Shutdown

9 Monitoring Results of AAQM Stations in RSP & Townships

(October, 2019 – March, 2020)

Oct., 2019 – Change w.r.t. April., - Oct., Nov., Dec., Jan., Feb., March AAQMS Location March., April., - Sep., Sep., 2019 2019 2019 2019 2020 2020 ., 2020 2020 2019

3 Parameter : PM 2.5 (Norm : 60 µg/m )

Sector#2, Rourkela 18.38 – -14.14% (Lower) 21.31 25.8 43.7 15.78 25.9 16.4 15.78 – 43.7 Steel Town (North) 21.42 +104.01% (Upper) Rourkela Fertilizer -35% (Lower) 9 – 24.49 26.29 55.39 15.38 13.40 5.85 8.37 5.85 – 55.39 Township (South) +126.17% (Upper) +3.99% (Lower) ERWPP Area (West) 10.77 - 14 11.2 12.39 27.56 16.18 23.26 19.96 11.2 – 27.56 +96.85% (Upper) -17.8% (Lower) SSSY Area (East) 15 NA NA NA 21.48 23.15 12.33 12.33 -23.15 +54.33% (Upper)

3 Parameter : PM 10 (Norm : 100 µg/m )

Sector#2, Rourkela - - NA NA NA NA NA NA - Steel Town (North) Rourkela Fertilizer +184.08% (Lower) 12 – 59.54 34.09 37.85 NA 60.1 57.46 40.8 34.09 - 60.1 Township (South) +0.94% (Upper) ERWPP Area (West) 17 – 24.21 NA NA NA NA NA NA - - - SSSY Area (East) - NA NA 35.82 63.37 77.98 44.57 35.8 – 77.98

3 Parameter : SO 2 (Norm : 80 µg/m )

Sector#2, Rourkela 19.97 – -40.46% (Lower) 19.98 19.99 14.99 58.64 11.89 19.0 11.89-58.64 Steel Town (North) 19.99 +193.3% (Upper) Rourkela Fertilizer -68.41% (Lower) 18.46 - 30 20.37 22.46 19.48 5.83 10.94 14.97 5.83-22.46 Township (South) -25.13% (Upper) -54.95% (Lower) ERWPP Area (West) 27.06 - 40 24.93 16.17 18.18 12.19 15.13 23.47 12.19-24.93 -37.67% (Upper) +5.9% (Lower) SSSY Area (East) 10 – 15.88 12.17 14.37 10.59 33.62 38.76 37.22 10.59-38.76 +144.08% (Upper)

Parameter : NOx (Norm : 80 µg/m 3)

Sector#2, Rourkela 24.19 – -39.31% (Lower) 42.22 79.2 15.5 34.28 NA 14.68 14.68-79.2 Steel Town (North) 79.24 -0.05% (Upper) Rourkela Fertilizer -1.45% (Lower) 15.1 - 39 14.88 14.95 14.98 17.04 NA 15.99 14.88-17.04 Township (South) -56.03% (Upper) +4.56% (Lower) ERWPP Area (West) 9.64 - 14 10.08 10.95 12.12 10.93 10.77 17.55 10.08-17.55 +25.35% (Upper) +4.43% (Lower) SSSY Area (East) 6.31 - 8 6.59 6.83 6.64 15.99 12.67 12.24 6.59-12.67 +58.37% (Upper)

Parameter : Carbon Monoxide (Norm : 4000 µg/m 3)

Sector#2, Rourkela 793 NA NA NA NA NA NA - - Steel Town (North) Rourkela Fertilizer +16.14% (Lower) 570 - 982 1025 902 716 662 805 1011 662-1025 Township (South) +4.37% (Upper) -16.56% (Lower) ERWPP Area (West) 483 - 762 451 408 403 1146 751 878 403-1146 +50.39% (Upper) -30.93% (Lower) SSSY Area (East) 682 - 693 691 674 670 671 471 474 471-691 -0.28% (Upper)

10

Annexure - 3

Monitoring of Stack Emissions (SPM in mg/NM3) (October, 2019 – March, 2020)

Oct., April., - Change w.r.t. Depart- Stack Oct., Nov., Dec., Jan., Feb., March. 2019 – SN. NORM Sep., April., - Sep., ment connected to 2019 2019 2019 2020 2020 , 2020 March., 2019 2019 2020 -66.6% (Lower) 1. Battery#1 15 – 45 24 15 5 13 40 42 5-42 -6.66%(Upper) 2. Battery#2 S/D S/D S/D S/D S/D S/D S/D S/D - +27.2% (Lower) 3. Battery#3 11 – 37 25 25 27 23 23 14 14-27 Coke -27.0% (Upper) 50 -36.3% (Lower) 4. Ovens Battery#4 11 - 28 21 19 9 16 7 42 7-42 +50% (Upper) -40.9% (Lower) 5. Battery#5 22 – 46 32 13 36 29 14 23 13-36 -21.7% (Upper) -14.2% (Lower) 6. Battery#6 7 – 17 17 18 15 19 6 14 6-19 +11.7% (Upper) 10 – +40% (Lower) 7. Process ESP 25 14 22 42 22 25 14-42 Sintering 126 -66.6% (Upper) 150 Plant#2 Space De +300% (Lower) 8. 11 – 85 61 46 54 61 44 48 44-61 dusting ESP -28.2% (Upper) -37.5% (Lower) 9. Process ESP -1 8 – 35 34 25 7 5 44 12 5-44 +25.7% (Upper) Sintering -30% (Lower) 10. Process ESP -2 150 10 – 28 36 29 9 7 47 22 7-47 Plant#3 +67.8% (Upper) Plant De -28% (Lower) 11. 25 – 94 47 18 27 25 24 50 18-47 dusting ESP -50% (Upper) -30.7% (Lower) 12. MP Boiler #1 & 2 13 – 91 9 38 31 49 34 28 9-49 -46.1% (Upper) 100 +85.7% (Lower) 13. MP Boiler # 3 7 –78 13 32 49 16 26 - 13-49 Captive -37.1% (Upper) Power -57.8% (Lower) 14. Plant#1 HP Boiler # 1 & 2 38 – 95 74 16 52 86 31 33 16-74 -22.1% (Upper) 100 +183.% (Lower) 15. HP Boiler # 5 &6 18 – 87 73 51 86 62 98 62 51-98 +12.3 % (Upper) Note: %Change is calculated for Lower limit and Upper limit of the range.

11

Annexure - 4

Solid Waste Utilization in Rourkela Steel Plant (October, 2019 – March, 2020) ( Unit : % ) Change April., - Oct., 2019 Name of the Oct., Nov., Dec., Jan., Feb., March., w.r.t. SN. Sep., – March., Solid Waste 2019 2019 2019 2020 2020 2020 April., - 2019 2020 Sep., 2019 Blast furnace 1. 100 100 100 100 100 100 100 100 No change slag +73.20% 9.18 – 15.90 – (Lower) 2. SMS slag 16.90 15.90 23.70 28.40 30.91 36.56 33.30 36.56 +9.78% (Upper)

3. Lime dust 100 100 100 100 100 100 100 100 No change

+149.37 Blast Furnace 40.10 – 100 – (Lower) 4. 111.46 100 100 100 100 100 flue dust 149.17 111.46 -25.27% (Upper) Blast furnace 5. 100 100 100 100 100 100 100 100 No change sludge -57.87% 22.34 – 9.41 – (Lower) 6. SMS Sludge 27.58 82.82 81.29 9.41 63.86 97.25 165 97.25 -41.06% (Upper) Broken 7. Refractory/Fire 100 100 100 100 100 100 100 100 No change clay bricks

8. Mill scale 100 100 100 100 100 100 100 100 No change

-0.17% Total Solid 74.30 – 74.17 – (Lower) 74.17 74.41 80.70 80.36 80.17 83.56 Waste 82.93 83.56 +0.75% (Upper)

Note: %Change is calculated for Lower limit and Upper limit of the range.

12

Annexure - 5

PAH & BaP monitoring

Analysis was done at Environment Laboratory, RDCIS, SAIL, Ranchi (Sampling & Analysis : 01/03/2020 – 31/03/2020)

COKE OVEN WORKZONE AMBIENT AIR QUALITY STACK EMISSIONS

SN. EED SP#3 SP#3 Steel CDCP CDCP OBBP PARAMETER RDCIS PMPH CPP#1 CPP#1 TOP#2 HPB#6 SMS#2 LHF 2B Batt.#6 Process BATT#6 BATT#6 BATT#6 BATT#6 Building Building Building Building Gr.Floor Roof top Sector#2 Roof Top Ram Side Oven Top Township Coke Side BOD Plant Coke Oven

1. PHN 34 19 11 14 3 3 5 4 3 5 2 175 162 218 149

2. ANT 54 15 14 59 6 8 4 8 6 8 7 84 93 153 87

3. FLT 131 42 58 62 12 10 8 7 5 6 4 364 376 210 351

4. PYR 319 237 125 69 26 14 4 6 7 6 4 389 392 1087 361

5. BAA 479 327 141 56 35 19 4 10 8 11 9 974 969 2314 987

6. CHR 511 357 135 87 14 24 NT NT NT NT NT 724 691 3199 685

7. BBF 756 418 149 82 24 18 NT 9 10 8 6 1041 1093 1882 1067

8. BKF 782 437 149 127 22 11 1 NT NT NT NT 2123 2174 2176 2180

9. 821 412 168 127 1 1 1 1 1 1 1 1823 1842 1726 1864 BaP (ng/m3)

10. DBA 90 55 51 17 2 1 1 NT NT NT NT 284 251 1105 204

11. BGP 20 10 10 8 NT NT NT NT NT NT NT 72 89 2749 85

12. IPY 7 4 3 3 NT NT 2 2 3 1 3 26 35 2078 25

5000 2000 2000 2000 1 1 1 1 1 1 1 - - - - Norms (ng/m3)

(Units : All are in nano grams /m3 except SPM which is in micro grams/m3) BDL : Below detectable limit.

Note : For uniformity all the figs. are given in nano grams/m3

13

Annexure – 6

Quality of final treated effluent going to river Brahmani from RSP (October, 2019 – March, 2020)

Oct., April., - Change w.r.t. Oct., Nov., Dec., Jan., Feb., March. 2019 – SN. PARAMETER NORM Sep., April., - Sep., 2019 2019 2019 2020 2020 , 2020 March., 2019 2019 2020 5.5 – 7.0 – 7.55 7.47 7.48 7.18 7.50 7.22 7.18 – +2.57% (Lower) 1. pH 9.0 7.77 7.55 -2.83% (Upper) Shall not 2. Temperature exceed 25 25 25 25 25 25 25 25 - 5oCof input Total Suspended 18 15 16 25 15 26 -25% (Lower) 3. 100 20 - 24 15 – 26 Solids (TSS) +8.33% (Upper) 0.72 – 1.10 1.05 1.05 0.69 1.20 0.88 0.69 – -4.16% (Lower) 4. Oil & Grease 10.0 1.08 1.20 +11.11% (Upper) 1.28 – 2.40 2.36 2.36 2.03 3.15 1.88 1.88 – +46.87% (Lower) 5. Ammonia as NH -N 50 4 2.60 3.15 +21.15% (Upper) Total Kjeldahl 3.24 – 4.15 5.15 5.16 3.67 7.44 3.81 3.81 – +17.59% (Lower) 6. 100 Nitrogen 5.30 7.44 +40.37% (Upper) 0.06 – 0.03 0.20 0.05 0.13 0.06 0.18 0.03 – -50% (Lower) 7. Free Ammonia 5.0 0.13 0.20 +53.84% (Upper) Biochemical Oxygen 8.79 – 8.50 7.66 9.62 11.52 17.33 12.17 7.66 – -12.85% (Lower) 8. 30 Demand (BOD 3) 14.76 17.33 +17.41% (Upper) Chemical Oxygen 27.72 - 22.16 20.12 24.28 37.46 52.63 39.42 20.12 – -27.41% (Lower) 9. 250 Demand (COD) 48.49 52.63 +8.53% (Upper) 0.002 – 0.002 0.006 0.003 0.004 0.002 0.003 0.002 – 0% (Lower) 10. Phenol 1.0 0.01 0.006 -40% (Upper) 0.008 – 0.002 0.004 0.003 0.03 0.06 0.04 0.002 – -75% (Lower) 11. Cyanide 0.2 0.04 0.06 +50% (Upper) 1.15 – 0.98 0.96 1.13 1.22 0.93 0.96 0.93 – -19.13% (Lower) 12. Fluoride (as F) 2.0 1.27 1.22 -3.93% (Upper) 0.30 0.15 0.94 0.28 0.21 0.31 0.15 – 0.009 – +1566 % (Lower) 13. Dissolved Phosphates 5.0 0.94 0.48 +95.83% (Upper)

0.003 – 0.003 0.004 0.004 0.007 0.004 0.006 0.003 – 0 % (Lower) 14. Sulphide (as H2S) 2.0 0.009 0.007 -22.2% (Upper) 0.02 – 0.13 0.13 <0.05 0.17 0.39 0.15 0.05 – +150% (Lower) 15. Manganese 2.0 0.36 0.39 +8.33% (Upper) Nitrate Nitrogen 1.48 – 1.80 1.83 0.96 1.31 2.16 1.38 0.96 – -35.13% (Lower) 16. 10 (NO3-N) 2.23 2.16 -3.13% (Upper) 1.02 – 1.04 1.57 1.98 1.01 2.38 1.32 1.01 – -0.98% (Lower) 17. Iron (a Fe) 3.0 2.24 2.38 +6.25% (Upper) % Change is calculated based on Lower & Upper limits of range -- All units are in mg/lit except pH

14 Annexure – 7

Ground Water Quality at Waste Disposal Sites (October, 2019 – March, 2020)

1) Location of Sampling : Sitalpara Dump yard

Oct., April., - Change w.r.t. PARA- Oct., Nov., Dec., Jan., Feb., March 2019 – SN. NORM Sep., April., - Sep., METER 2019 2019 2019 2020 2020 ., 2020 March., 2019 2019 2020 6.54 – 6.80 – +3.97% (Lower) 1. pH 6 – 8.5 6.80 7.62 6.83 7.34 7.30 7.18 7.98 7.62 -4.511% (Upper) Turbidity 0.50 – +20% (Lower) 2. 5 0.9 0.7 0.9 0.7 0.8 0.6 0.6 – 0.9 (NTU) 4.8 -81.25% (Upper) Total 128 – 120.39 – -5.94% (Lower) 3. Hardness 300 124.7 196.7 120.39 231.61 196.7 189.81 228.9 231.61 +1.18% (Upper) as CaCO 3 0.16 – 0.33 – +106.25% (Lower) 4. Iron 0.3 0.38 0.87 0.91 0.33 0.33 0.45 0.29 0.91 +213.79% (Upper) 24.74 – 24.84 – -10.45% (Lower) 5. Chlorides 250 26.72 34.62 24.84 34.80 36.15 31.44 70.93 36.15 -49.03% (Upper) 0.11 – 0.48 – +336.36% (Lower) 6. Fluoride 1.0 0.54 0.70 0.49 0.52 0.48 0.50 0.50 0.70 +40% (Upper) (All units are in mg/lit except pH & Turbidity) 2) Location of Sampling : Blast Furnace Dump yard

Oct., April., - PARAME Oct., Nov., Dec., Jan., Feb., March 2019 – Change w.r.t. SN. NORM Sep., 2019 2019 2019 2020 2020 ., 2020 March., April., - Sep., 2019 TER 2019 2020 6.4 – 6.67 – +4.21% (Min) 1. pH 6 – 8.5 6.72 7.07 6.67 7.15 7.11 7.21 7.97 7.21 -9.53% (Max) Turbidity 0.70 – 0.50 – -28.57% (Min) 2. 5 0.80 0.60 0.90 0.60 0.50 0.50 (NTU) 4.1 0.90 -78.04% (Max) Total 159 – 188.4 – +18.49% (Min) 3. Hardness 300 190.08 198.2 188.4 215.61 194.20 210.39 242.4 215.61 -11.05% (Max) as CaCO 3 0.22 – 0.50 – +127.27% (Min) 4. Iron 0.3 0.98 0.50 0.94 0.98 0.98 0.84 0.29 0.98 +237.93% (Max) 23.99 – 20.83 – -13.17% (Min) 5. Chlorides 250 33.65 26.12 30.42 20.83 22.86 22.43 40.11 33.65 -16.10% (Max) 0.10 – 0.15 – +50% (Min) 6. Fluoride 1.0 0.15 0.80 0.17 0.94 0.78 0.91 0.91 0.94 +3.29% (Max) (All units are in mg/lit except pH & Turbidity) % Change is calculated based on Lower & Upper limits of range

15

Annexure-7a

Ground Water Table Levels

Depth of Water Table from Ground Level Location of bore (mtr.) SN. Direction Latitude Longitude hole Oct.19-March,2020 Apr.-Sept.2019

Near FMM Old Time 1. North 22°21’9 N 84°85’67 E 3.35 2.60 Office

2. Near Samskar Gate North East 22°13’13 N 84°52’1 E 4.21 3.62

3. SSSY East 22°13’6 N 84°54’15 E 4.39 1.38

4. SLF South East 22°13’6 N 84°54’11 E 6.46 5.92

5. WT-14 South 22°12’27 N 84°54’13 E 4.34 3.31

6. FP Gate South West 22°11’16 N 84°51’56 E 1.56 1.01

7. Near New Plate Mill West 22°12’14 N 84°50’15 E 3.51 1.50

8. SGP Gate North West 22°11’49 N 84°50’33 E 4.12 1.25

16

Annexure-8

17

Annexure - 9

Fugitive emission (SPM) levels monitored inside RSP (Shop Floor) (October, 2019 – March, 2020)

Oct., Change April., - Location of Oct., Nov., Dec., Jan., Feb., March., 2019 – w.r.t. SN. Department Sep., monitoring 2019 2019 2019 2020 2020 2020 March., April., - 2019 2020 Sep., 2019 +224.6% Blast Furnaces 199 – 646 – (Lower) 1. Cast House 1144 646 - - 1998 1762 (PM10) 2818 1998 -29.09% (Upper) +627.84% Steel Melting In front of 352 – 2562 - (Lower) 2. 2796 - - 2642 2562 - Shop#1(PM10) BOF 2158 2796 +29.56% (Upper) -35.31% Steel Melting In front of 1382 – 894 - (Lower) 3. Shop#2 - 894 2695 3058 2311 1600 BOF 2348 3058 -96.83 (PM10) (Upper) Unit : Norm 4000 4000 4000 4000 4000 4000 4000 4000 µg/m3 (Units : µg/m3)

% Change is calculated based on Lower & Upper limits of range

18

Annexure-10

Rourkela Steel Plant Status of the Implementation Schedule

SN. CONDITION IMPLEMENTATION SCHEDULE RSP has 6 no. of coke oven batteries. Battery No. 1, 3, 4 & 5 have been rebuilt & commissioned in the years 2007, 2016, 2010 & 2000 respectively. Battery No. 6 is a new Green field Battery which was commissioned on 01/04/2014, under this Expansion 1. Rebuilding of Coke Oven Batteries Project.

Coke Oven Battery No. 2 was put down since March, 2016 as it has outlived its life and due for rebuilding. PAH and BaP in the Coke Oven area are being monitored once in a year. VOCs in Monitoring of VOCs, PAH and BaP in 2. Coke Oven Stacks, ambient & work zone were monitored and analysis results stacks and ambient air. along with data interpretation are given at Annexure- 1 & 5. Monthly report covering Stack Reports are being sent to SPCB & CPCB since April, 2008 onwards every month, 3. Emissions, Ambient air quality and regularly. Six monthly reports are being sent to MoEFCC regularly. Waste utilization Monitoring of Ground water quality Ground water quality at waste disposal sites is being monitored and the six 4. at waste disposal sites – once in six monthly report of ground water quality along with data interpretation is given at months Annexure-7. Blast Furnace Slag : In-house Slag granulation facilities have already been installed in all Blast Furnaces viz., BFc No. 1, 4 & 5. The granulated slag is being sent to cement plants for production of slag cement. The present BFc Slag utilization is more than 100% .

SMS Slag : State of the art technologies have been adopted in steel making so that the SMS slag generation rate is minimized. The SMS slag is being utilized for Sinter Making through base mix route, charged into Blast Furnaces directly to replace lime stone and also used for pavement making and rail ballast and also used for reclaiming low lying areas inside plant premises. Enhancement of waste utilization to 5. 90%. Fly Ash : There is no additional fly ash generation after commissioning of this Expansion project as the additional power is being obtained from Top Recovery Turbo Generator of BFc#5, Power Blowing Station of Blast Furnace No. 5 (36 MW), Back Pressure Turbo Generator of Coke Oven Battery No.7 - CDCP and remaining 110 MW power will be purchased from State Grid.

As per the present agreement with NTPC, the joint venture power company NSPCL is managing the fly ash generated from captive power plant of RSP. The fly ash will be utilized for dyke height raising of existing Ash Ponds. The fly ash is also being given to local entrepreneurs free of cost. RSP is also bearing the transportation costs as per the latest Fly Ash Gazette notification. RSP has already developed Greenbelt in 2168.28 Ha. out of total land of Development of Green Belt to cover 6527.48 Ha. which is coming to 33.22 % of the total area. RSP has planted more 6. 33% of the total area in and around than 49 lakh trees so far including 1,46,397 no. of saplings planted during the plant. 2019-20.

Development of Rain water 16 no. of Rain Water harvesting systems units have been constructed and put into 7. harvesting systems. operation during 2018-20.

19 Annexure-11

20 Annexure-12

21 Annexure – 13 Quality of RSP’s finally treated Sewage (October, 2019 – March, 2020) Oct., April., - Change w.r.t. Oct., Nov., Dec., Jan., Feb., March. 2019 – SN. PARAMETER NORM Sep., April., - Sep., 2019 2019 2019 2020 2020 , 2020 March., 2019 2019 2020 5.5 – 7.0 – 7.55 7.47 7.48 7.18 7.50 7.22 7.18 – +2.57% (Lower) 1. pH 9.0 7.77 7.55 -2.83% (Upper) Shall not 2. Temperature exceed 25 25 25 25 25 25 25 25 - 5oCof input Total Suspended 18 15 16 25 15 26 -25% (Lower) 3. 100 20 - 24 15 – 26 Solids (TSS) +8.33% (Upper) 0.72 – 1.10 1.05 1.05 0.69 1.20 0.88 0.69 – -4.16% (Lower) 4. Oil & Grease 10.0 1.08 1.20 +11.11% (Upper) 1.28 – 2.40 2.36 2.36 2.03 3.15 1.88 1.88 – +46.87% (Lower) 5. Ammonia as NH -N 50 4 2.60 3.15 +21.15% (Upper) Total Kjeldahl 3.24 – 4.15 5.15 5.16 3.67 7.44 3.81 3.81 – +17.59% (Lower) 6. 100 Nitrogen 5.30 7.44 +40.37% (Upper) 0.06 – 0.03 0.20 0.05 0.13 0.06 0.18 0.03 – -50% (Lower) 7. Free Ammonia 5.0 0.13 0.20 +53.84% (Upper) Biochemical Oxygen 8.79 – 8.50 7.66 9.62 11.52 17.33 12.17 7.66 – -12.85% (Lower) 8. 30 Demand (BOD 3) 14.76 17.33 +17.41% (Upper) Chemical Oxygen 27.72 - 22.16 20.12 24.28 37.46 52.63 39.42 20.12 – -27.41% (Lower) 9. 250 Demand (COD) 48.49 52.63 +8.53% (Upper) 0.002 – 0.002 0.006 0.003 0.004 0.002 0.003 0.002 – 0% (Lower) 10. Phenol 1.0 0.01 0.006 -40% (Upper) 0.008 – 0.002 0.004 0.003 0.03 0.06 0.04 0.002 – -75% (Lower) 11. Cyanide 0.2 0.04 0.06 +50% (Upper) 1.15 – 0.98 0.96 1.13 1.22 0.93 0.96 0.93 – -19.13% (Lower) 12. Fluoride (as F) 2.0 1.27 1.22 -3.93% (Upper) 0.30 0.15 0.94 0.28 0.21 0.31 0.15 – 0.009 – +1566 % (Lower) 13. Dissolved Phosphates 5.0 0.94 0.48 +95.83% (Upper)

0.003 – 0.003 0.004 0.004 0.007 0.004 0.006 0.003 – 0 % (Lower) 14. Sulphide (as H2S) 2.0 0.009 0.007 -22.2% (Upper) 0.02 – 0.13 0.13 <0.05 0.17 0.39 0.15 0.05 – +150% (Lower) 15. Manganese 2.0 0.36 0.39 +8.33% (Upper) Nitrate Nitrogen 1.48 – 1.80 1.83 0.96 1.31 2.16 1.38 0.96 – -35.13% (Lower) 16. 10 (NO3-N) 2.23 2.16 -3.13% (Upper) 1.02 – 1.04 1.57 1.98 1.01 2.38 1.32 1.01 – -0.98% (Lower) 17. Iron (a Fe) 3.0 2.24 2.38 +6.25% (Upper)

% Change is calculated based on Lower & Upper limits of range -- All units are in mg/lit except pH

22

Annexure-14

Rourkela Steel Plant RSP’s CSR Initiatives during 2019-20

Bringing cheers to the most marginalized local stake holders in and around Steel Plant is the main objective of RSP which is being fulfilled through CSR activities. RSP established a separate department called “CSR” for carrying out various activities under Corporate Social Responsibility. The main focus of CSR activities are on, A) Educatio n B) Infrastructure C) Health D) Support for disabled/under privileged E) Income generation & livelihood F) Water supply and sanitation G) Sports and culture H) Women empowerment

The different developmental activities taken up under different heads are,

1. EDUCATION:

• The Akshaya Patra Project, Rourkela, a CSR endeavor of RSP regarding hygienic and nutritious mid -day meals for 40536 students, continued to supply good quality mid -day meals to schools in Rourkela Municipality, Bisra Block & Lathikata Block. • 11 no. of tribal students from peripheral areas of RSP have been sponsored for free education at Kalinga Institute of Social Sciences (KISS), Bhubaneswar. • “Deepika Ispat Sikshya Sadan”, a special school functioning for underprivileged children of Rourkela and neighboring area (Class -1 to 10) with free education, uniform, educational kits, books & mid -day refreshments. Total students enrolled in AY 2019 -20 was 675. • Financial assistance provided to 14 no of class X passed out students of “Deepika Ispat Siks hya Sadan pursuing ITI course at KIIT, ITI. • Annual installment cheques under scheme of Financial Assistance for professional studies were handed over to 38 students from peripheral villages for FY 2015 -16 & 2016-17. • 1018 no of students have been selected for Merit based cash award for the year on 25 th & 26th October2019 for the year 2016 -17. • Scholarship cheques for 200 underpreviledged students distributed on 11/07/2019 at Civic Centre for the year 2016-17.

23

2. INFRASTRUCTURE

• Beautification of Vedvyas Temple. • Construction of resettlement tank at Akshaya Patra, Sector -7, Rourkela. • Bituminous road work of 6600mtr in Ushra colony, Laing colony & Dandiapalli completed. • Concrete road work of 2510mtr in Silikata, Samra basti, Laing Colony completed.

3. HEALTH

• Free bi-weekly medical aid centres operated in 34 peripheral locations (i.e. 68 camps a week). Total number of patients treated during the year 58087 • Free health centres operated at Ispat Sanjeevani, Sector -6; Chikatmati Village & Jalda RS colony six days a week. Total number of patients treated during the year 25308. • 3 Nos. Multi-disciplinary medical camps were conducted at Dhangrinacha in kuarmunda block,Singher (Lathikata Block), Urmei (Nuagaon Block) and Jar aikela (Bisra Block) in which 1354 patients benefitted. Medical specialties coverage was given in disciplines such as Medicine, Surgery, Pediatrics, Ophthalmology, Dermatology & ENT etc. • The following specialized projects, for providing free treatment/surg ical procedures for targeted persons, are continuing at IGH. • Project Sunayana for treatment of vision impaired. Patients operated 28. • Project Sushruti for treatment of hearing impaired. Patients operated 3. • Project Akshay for tuberculosis. Patients trea ted 30. • Project Surabhi for women with gynecological disorders. Patients treated 7. • Project Swabalamban for persons with cleft lip, clubbed feet, hair lip, congenital cataract disorders. • Project Charaka for general surgical services. Patients operated 6 5. • Health promotional activities are continuing in slum areas of township periodically through Deepika Mahila Sanghati. • Reproductive & Child Health (RCH) and Family Welfare (FW) activities at IGH are being conducted. Total patients benefitted 101.

24

4. SUPPORT FOR THE DISABLED/ UNDERPRIVILGED:

• Mid Day Meals provided through Akshay Patra Foundation (fully sponsored by RSP) continued to Radhakrishna Drustihin Vidyalaya, Lathikata; Home & Hope, Asha, Rourkela, in addition to the Deepika Ispat Sikhya Sadan. Total 857 no of students are benefitted.

5. INCOME GENERATION & LIVELIHOOD: Under employability skills enhancement programs in health sector, the training programs conducted at IGH included the followings:

• Medical Attendant Training • Advanced Specialised Nursing Training • Advanced Specialised Physiotherapy Training • Anaesthesia/OT assistant Training • Data entry operator/Medical transcription training • Hospital administra tion training • 12 nos. Mushroom Cultivation Training programs were conducted for peripheral villagers to augment their Income Generation Skills. Total 171 participants were participated in the programme

6. WATER SUPPLY & SANITATION :

• Mission Project on Water & Sanitation in Kuarmunda Block at 9 villages i.e. Sarandamal, Chandiposh, Sarandaposh,Raiberna, Bhaludumer, Bhagattola, Madatola, Belpada, Mandira in Kuarmunda block completed.

25

7. SPORTS & CULTURE:

SAMVARDHAN (Rural Sports): • Zonal level Samvardhan Rural Football Tournament were organized at Chengjharan (Bisra Block), Zadakudar (Lathikata Block) and Baniguni (Kuarmunda Block) for the year 2018 -19. Samvardhan Rural football tournament final meet for the year 2018 -19 was held at Ispat Stadium, Sector -6 on 20/11/2019. • Zonal level Men’s Samvardhan Rural Football Tournament was organised at Bagdega in Nuagaon Block on 13/12/2019 and at Dalposh in Bisra block on 16/12/2019 for the year 2019 -20. 32 teams from each block (ie. a total o f 64 teams from two blocks) participated in the tournament. 8 teams (2 from each block) will be selected to play the final round of matches at Ispat stadium.

SYNERGY : The Lok Samskrutik Mahotsav: Zonal level Synergy: The Lok Samskrutik Mahotsav were organized at Dumerjore (Kuarmunda Block), Dalposh (Bisra Block) Khuntagaon (Nuagaon Block) for the year 2018-19. The final round of Synergy: The Lok Samskrutik Mohotsav was conducted at Bhanja Cultural Trust on 27/04/2019 for the year 2018 -19. Zonal level synergy were organized at Jagdishpur (Kuarmunda Block), Zadakudar(Lathikata Block) and Lindra (Nuagaon Block) on 20/11/2019, 27/11/2019, 6/12/2019 respectively for the year 2019-20. 30 teams from each block (ie. a total of 90 teams from threer blocks) participated in the zonal round. 12 teams (i.e 3 top winners from each block) will be selected for final round to participate at Bhanja Bhawan,Rourkela.

8. WOMEN EMPOWERMENT :

• Handloom Centre: Handloom training is continuing at the Handloom Centre, Sector -2. The girls from peripheral areas are being trained in identifying yarn, separation of hank, finding & joining loose ends, usage of Chatta & Asari, Bobbin & Cha rkha, Bobbin machine, Warping Machine, starching, reed joining, sizing, dyeing, weft lining, reed fitting in looms, weaving, badhi preparation, tie & dye, weaving. The trainees are now able to weave handkerchieves, bedsheets, and different types of fabric s including sarees. So far 113 women have been trained here.

• The products of Handloom Centre were put up for exhibition -cum-sale in Pallishree Mela -2019-20, at Rourkela.

• A White Phenyl Production Center has been established at Deepika Mahila Jagruti Sa nsthan, Sec-2 and is in operation. • A low cost Sanitary Napkins Production Center has been established at Deepika Mahila Jagruti Sansthan, Sec-2 and is in operation.

26

9. MISCELLANEOUS : Skill Development:

• Livelihood Incubation Centre Project at Rourkela – MoU signed on 30/8/2018 and Foundation laying ceremony was held by Hon’ble Minister, Shri Jual Oram, Ministry of Tribal Affairs, Govt. of India on 25/2/2019.More than 50% of Civil jobs have been completed & electrical hobs sta rted. • Sadbhavana Divas celebrated on 20th August,2019. • Swachhata pakhwada at Dareikela Govt. UP School with 84 students on 27/08/2019 was organized. • International Day for differently abled celebrated on 3/12/2019675675 at Home & Hope. • Digital training camp s were conducted at Tulsikani, Bhalulata, Kulenbahal, Jodabandha, Mahipani, Bijadih, Bangurkela, Dhadhari in Bisra Block.

27

Annexure-15

Special Noise Monitoring at Ambient Air Stations at Ground Level (October, 2019 – March, 2020)

Noise Noise LOCA-TION Min. / Max Day time Night time

Oct., 2019 – March, 2020 67.4 – 74.1 56.4 – 64.4 EED Building

April. – Sept.,2019 66.8 – 71.7 55.4 – 65.1

Lower limit +0.89% +1.80% % Change Upper Limit +3.34% -1.07%

Oct., 2019 – March, 2020 69.2 – 74.2 57.2 – 65.8 RDCIS Building April. – Sept.,2019 70.4 – 72.8 57.5 – 65.0

Lower limit -1.70% -0.52% % Change Upper Limit +1.92% +1.23%

Oct., 2019 – March, 2020 67.2 – 73.6 58.2 – 64.9 PMPH Building April. – Sept.,2019 65.2 – 71.7 58.4 – 66.2

Lower limit +3.06% -0.34% % Change Upper Limit +2.64% -1.96%

Oct., 2019 – March, 2020 66.4 – 73.3 54.2 – 64.9 BOD Building April. – Sept.,2019 64.2 – 71.7 52.6 – 65.5

Lower limit +3.42% +3.04% % Change Upper Limit +2.23% -0.91%

TOP#2 Admn. Oct., 2019 – March, 2020 66.0 – 73.7 54.7 – 64.6 Building April. – Sept.,2019 64.2 – 71.7 52.9 – 65.0

Lower limit +2.80% +3.40% % Change Upper Limit +2.78% -0.61%

OBBP Admn. Oct., 2019 – March, 2020 68.4 – 73.6 53.2 – 64.6 Building April. – Sept.,2019 65.8 – 71.5 51.3 – 65.0

Lower limit +3.95% +3.70% % Change Upper Limit +2.93% -0.61%

Norm 75 dB(A) 70 dB(A)

28

Annexure-16

Work zone dust special monitoring

(October, 2019 – March, 2020)

PM10 Dust Date of Noise SN. Department Location of monitoring concentration Monitoring dB(A) in mg/m3 1. Conveyor A1.001 Discharge end 09/01/2020 2.515 85.1

2. Conveyor E2.001 Discharge end 09/01/2020 2.674 88.5

3. Sintering Conveyor E7.007 Discharge end 09/01/2020 2.580 81.4 Plant#3 4. Conveyor E9.003 Tail end 10/01/2020 3.045 81.9

5. Conveyor FS-10 Tail end 10/01/2020 3.758 83.2

6. Raw material handling building 23/01/2020 3.460 89.5 Calcining 7. Kiln feed building 23/01/2020 3.350 88.1 Plant#2 8. Flux storage building 23/01/2020 3.860 84.2

9. HR coil receiving yard of pickling line 27/01/2020 2.100 89.4

10. Uncoiler area of pickling line -1 27/01/2020 1.600 91.5

11. Uncoiler area of pickling line-2 27/01/2020 1.700 92.5 Cold Rolling 12. Regeneration Plant 27/01/2020 1.500 90.0 Mills 13. 2nd floor of regeneration plant 27/01/2020 1.900 89.1 Furnace area of HAL near running 14. 27/01/2020 2.180 89.8 fire 15. Zinc pot area of Galvanizing line 27/01/2020 1.980 90.5 Cylinder loading area of Oxygen 16. 12/02/2020 1.300 85.1 Plant Unit#1 Oxygen Plant Cylinder filling area of Oxygen Plant 17. 12/02/2020 1.260 86.6 Unit#1 18. LDBP In front of press 4 & 5 20/02/2020 1.200 84.8

29

Annexure-17

Expenditure on various Pollution Control Systems installed in different plant units

Expenditure in Rs. SN. Department Pollution Control Equipment installed Lakhs

Land Based Pushing Emission Control 1. System 2. Multi Cyclone and Bag Houses for CDCP

3. Dust suppression system in Wagon Tippler Wet fog dust suppression system in coke 4. handling system 34400 Coke Oven Battery#6 5. Zero leak doors 6. HPALA system and on main charging

7. Door and Door frame cleaning machines

8. H2S recovery system Heat recovery in CDCP for power generation 9. through Back Pressure Turbine. 10. Process ESPs – 2 units

11. Plant De-dusting ESP Sintering Plant#3 4700 12. Bag houses for lime unit

13. Bag house for granulator Cast House De-fuming systems - 2 no. of 14. Electro Static Precipitators 15. Stock House de dusting system – ESP

16. Wet fog dust suppression system

17. Blast Furnace#5 Dust catcher 8000

18. Wet scrubber

19. Clarifiers – 2 nos.

20. Belt press systems – 2nos.

21. Dog House with 2 no. of ESPs

22. 2 no. of Bag Houses for LHF#2A & #2B

23. BOF#3 & Caster#3 in ESP for LHF#3 Steel Melting 12000 24. Shop#2 Bowl classifier

25. Clarifiers

26. Belt press systems

30 Expenditure in Rs. SN. Department Pollution Control Equipment installed Lakhs

27. Scale pit with Oil skimmers Sedimentation tank with Oil skimmer – 2 28. sets 29. New Plate Mill Pressure Filters 10

30. Clarifloculator

31. Sludge drying bed – 2 compartments Calcining Plant#2 32. Bag Houses – 6 nos. 10 Expansion 33. OBBP Expansion Dry fog dust suppression systems 500

Total 61600

31 Annexure-18

List of ESPs installed in different departments and PG Test Status

SN. ESP located at PG Test carried out Efficiency

1) Sintering Plant#3 – Process ESP Yes 99.9% 2) Sintering Plant#3 - Plant Dedusting ESP Yes 99.8% Blast Furnace No.5 – Cast House 3) Yes 99.8% Defuming system – 2 nos. 4) Blast Furnace No.5 – Stock House Yes 99.6% Captive Power Plant#1 – ESP provided to 5) Yes 99.6% MP Boiler#3 Captive Power Plant#1 – ESP provided to 6) Yes 99.5% HP Boiler#5 Captive Power Plant#1 – ESP provided to 7) Yes 99.5% HP Boiler#6

32

Annexure-19

Microfine dust generation from ESPs of Expansion Project

1) SP#3 Process ESPs -- 30 TPD 2) SP#3 Plant de-dusting ESP – 15 TPD 3) BFc Stock House ESP -- 15 TPD 4) BFc Cast House ESPs -- 15 TPD 5) SMS#2 LHF#3 ESP – 5 TPD 6) SMS#2 Dog House ESP – 20 TPD Total dust generation -- 100 TPD

33

Annexure-20

1. Status of CREP Action Points (31/03/2020) -- Steel Plant

SN CREP POINT STATUS

Complied. PLD, PLL & PLO levels for this month are; To meet the parameters PLD (% leaking doors), PLL (% leaking lids), PLO (% leaking offtake) of the notified BATTERY NO. PLD PLL PLO standards under EPA within three years (By December 2005). Units % % % Battery # 1 8.21 NIL NIL Battery # 3 7.32 NIL NIL 1. Battery # 4 4.06 0.73 NIL

Battery # 5 7.53 0.11 NIL

Battery# 6 4.66* 0.12 NIL

NORM 10/5* 1 4

To rebuild atleast 40% of the coke oven batteries in Complied. 5 out of 6 Coke Oven Batteries viz., Batt#1, #3, #4 & #5 next 10 years (Dec.,2012) have already been rebuilt and COB#6 is a newly built battery. Steel Melting Shop : Fugitive emissions – To reduce Being Complied. 30% within March, 2004 and 100% compliance with The fugitive emission levels for this month are; norms by March, 2008 (Including installation of 2. secondary de-dusting facilities) SMS#2 Norm

1285 (Avg.) 4000µg/m3

Blast Furnaces : Direct injection of reducing agents 3. CDI installed in all Blast Furnaces. (CDI) by June, 2013. Solid Waste Management : • Utilization of BFc/SMS slag – 70% by 2004, BF’cs slag Utilization for the month of Mar., 2020 = 100 % 80% by 2006 & 100% by 2008. SMS Slag utilization for the month of Mar., 2020 = 36.56%

Hazardous Waste Management : • Charge of Tar Sludge/ETP sludge to Coke Complied. 4. Ovens by June, 2003.

• Inventorisation of H/Waste as per the Complied. H/Waste (M&H) Rules, 1989 as amended from time to time and implementation of Rules by Dec., 2003. Water Conservation / Water Pollution : • To reduce Sp. Water consumption to 4.8 Complied. m3/TCS for flat product plants. Sp. Water Consumption for Mar., 2020 = 3.65 m3/TCS 5. • To operate CO&BP plant efficiently to achieve 89 the notified effluent discharge standards by July, 2004. Working effectively.

34

SN CREP POINT STATUS

Installation of Online Stack monitoring systems by June, Complied. 2005. 6. Installation of Online Ambient Air Quality Monitoring Complied. Stations by June, 2005. To operate the existing pollution control equipment efficiently and to have proper record keeping of Complied. Quarterly reports are regularly submitted. Qrt#4 pollution control equipment’s run hours, failure time 7. report submitted. The next report will be submitted by and efficiency compliance with immediate effect. 10/07/2020. Compliance report to be submitted to CPCB/SPCB every three months.

Implementation of Life Cycle Assessment 18 out of 30 recommendations have already been implemented. 8. recommendations. Remaining is under active consideration. To take necessary steps for adopting the following clean technology measures to improve the performance;

• Energy recovery of top Blast Furnace Gas.  Installed.

• Use of tar free runners linings.  Installed.

• Dedusting of cast house at tap holes, runners,  Installed. skimmers, ladle and charging points.

• Suppression of fugitive emissions by nitrogen gas or  Dust suppression systems installed. other inert gas.

 Studied. Not feasible for Rourkela Steel Plant. • To study the possibility of slag and fly ash transportation back to the abandoned mines to fill up the cavities through empty railway wagons when they return and its implementation.

9.

• Processing of waste containing flux and ferrous  Being followed meticulously. waste through waste recycling plant.

• Implementation of rain water harvesting.  Implemented in different areas.

• Reduction of Green House Gases by,  Regularly been practiced. By product gases are used in CPP#1 &

 Reduction in power consumption. Power Blowing Station for power generation.

 Use of by product gases for power generation.  Energy audits are carried out regularly by qualified Energy Auditors

 Promotion of energy optimization of EMD. technology including energy audit.  Environmental Engg. Laboratory has been provided with latest

• Up-gradation of Monitoring and Analysis facilities instruments for monitoring & analysis. Training is being provided to for Air & Water pollutants and also to impart personnel on regular basis. training to manpower so that realistic data can be obtained.

• To improve Housekeeping.  A massive housekeeping drive is going on.

35

2. Status of CREP Action Points (31/03/2020) -- Captive Power Plant#1 :

SN CREP POINT STATUS

Implementation of environmental standards (emission and effluent) in Pollution control equipment has already been 1. non compliant power plants. Installation and commissioning of installed and the environmental standards are pollution control equipment by 31 st December, 2005 being met.

For existing thermal power plants, a feasibility study shall be carried out by Central Electricity Authority (CEA) to examine possibility to reduce 2. the particulate matter emissions to 100 mg/NM3. The studies shall also Not applicable. suggest the road map to meet 100 mg/NM3 wherever found feasible. CEA shall submit the report by March, 2004.

New/expansion power projects to be accorded environmental clearance 3. on or after 01/04/2003 shall meet the limit of 100 mg/NM3 for Not applicable. particulate matter.

Development of SO 2 and NOx emission standards for coal based plants by December, 2003; • New /expansion power projects shall meet the limit of SO 2 and 4. Complied. NOx by w.e.f. 01/01/2005. • Existing power plants shall meet the limit of SO 2 and NOx w.e.f. 01/01/2006.

Continuous stack monitoring system with Install/active opacity meters/continuous monitoring systems in all the calibration arrangement was installed and 5. units by December 31 st , 2004 with proper calibration system. commissioned in the stacks of HP Boilers & MP Boilers.

Development of guidelines/standards for mercury and other toxic heavy 6. Not applicable. metals emissions by December, 2003.

Review of stack height requirement and guidelines for power plants All the stacks are erected based on statutory 7. based on micro meteorological data by June, 2003 clearance. Implementation of use of beneficiated coal as per GOI notification. Power Plants will sign fuel supply agreement (FSA) to meet the requirement as per the matrix prepared by CEA for compliance of the notification as short term measure.

Options/mechanisms for setting up of coal washaries as a long term measure; The matter was taken up with 8. Limited who is our supplier. • Coal India will set up its own washery. • State Electricity Board to set up its own washery. • Coal India to ask private entrepreneurs to set up washeries for CIL and taking washing charges.

SEBs to select a private entrepreneur to set up a washery near pit head installation of coal beneficiation plant.

36

SN CREP POINT STATUS

Power Plants will indicate their requirement of abandoned coal mines Not feasible as the mines are too far from 9. for ash disposal and Coal India/MOC shall provide the list of abandoned Rourkela. mines by June,2003 to CEA Dry fly ash loading systems are provided at Boilers. Fly ash is being given to the fly ash brick Power plants will provide dry ash to the users outside the premises or 10. manufactures free of cost. Actions are being uninterrupted access to the users within six months. taken to encourage outsiders to take the fly ash.

11. Power Plants should provide dry fly ash free of cost to the users. Dry fly ash is being given free of cost.

State PWDs/construction and development agencies shall also adhere to 12. the specifications/schedules of CPWD for ash/ash based products Not applicable. utilization. MoEF will takeup the matter with State Government. i) New Plants to be accorded environmental clearance on or after 01/04/2003 shall adopt dry fly ash extraction or dry disposal system or medium (35 – 40 %) ash concentration slurry disposal system or The treated water from ash ponds is being re- 13. lean phase with hundred percent ash water recirculation system circulated. depending upon site specific environmental situation. ii) Existing plants shall adopt any of the systems mentioned in 13(i) by December, 2004. Not applicable, however CPP#1 of RSP is Fly ash mission shall prepare guidelines/manuals for fly ash utilization by utilizing fly ash for construction of dykes of ash 14. March, 2004 pond and giving to the outside parties free of cost. New plants shall promote adoption of clean coal and clean power 15. Not applicable. generation technologies.

37