FOR EARTH/SAVUDU/GRAVEL QUARRY LEASE IN, MUTHUSERVAMADAM (THONDAMAN ERI) (Prepared under 12 - 2A Tamilnadu Minor Mineral Concession Rules, 1959 And amended Minor Mineral Conservation and Development Rules, 2010)

PERIOD: (THREE) 3 MONTHS ONLY

LOCATION OF THE APPLIED AREA

EXTENT : 2.50.0Ha

S.F.No : 125(P)

VILLAGE : MUTHUSERVAMADAM

TALUK : UDAYARPALAYAM

DISTRICT :

STATE : TAMILNADU

APPLICANT Tvl.PATEL INFRASTRUCTURE LIMITED, PATEL HOUSE, BESIDE PRAKRUTI RESORT, 3, BP ESTATE, CHHANI ROAD, CHHANI, NH 8 VADODARA, GUJARAT STATE– 391740

PREPARED BY R.RAJASEKAR.M.Sc., RQP/CNN/264/2015/A

No.4A, Chozha Nagar, Post, Taluk, Cuddalore- 606105 Cell: 9486905579 / 8870110245 Email: raja.parvathi @ gmail.com

CONTENTS

Sl. No. Description Page No. 1.0 Introduction 7 2.0 Executive Summary 9 3.0 General Information 10 4.0 Location 11 5.0 Geology and Mineral Reserves 13 6.0 Mining 16 7.0 Blasting 18 8.0 Mine Drainage 18 9.0 Other Permanent Structures 18 10.0 Employment Potentials & Welfare Measures 20 11.0 Environment Management Plan 22 12.0 Mine Closure Plan 26 13.0 Any Other Details Intend to furnish by the Applicant 27

1

ANNEXURES

Sl. No. Description Annexure No.

1 Precise Area Communication Letter from the I District Collector 2 FMB Sketch II

3 ID Proof III

4 Copy of RQP Certificate IV

LIST OF PLATES

Sl. No. Description Plate No Scale

1 Location Plan I Not to scale

2 Key Plan II Not to scale

3 Topo Sketch of Quarry Lease area for 10Km III 1:100000 Radius. 4 Environmental Plan IV 1:10000

5 Quarry Lease and Surface Plan V Plan-1:1000

6 Topography, Geological Plan & Section VI & Plan- 1:1000 Year wise Development, Production Plan & Sec Hor-1:1000; Sections VI-A Ver-1:100

7 Conceptual Plan and Section VII & Plan-1:1000 Sec Hor-1:1000; VII-A Ver-1:100

2

CONSENT LETTER FROM THE APPLICANT

The Mining Plan in Respect of Earth/Savudu/Gravel quarry over an extent of

2.50.0hectares of Thondaman Eri in S.F.No. 125(P) of Muthuservamadam Village,

Udayarpalayam Taluk, , Tamilnadu State has been prepared by

R.Rajasekar,M.Sc., Reg.No. RQP/CNN/264/2015/A

I request the Assistant Director, Department of Geology and Mining, Ariyalur

District to make further correspondence regarding modifications of the Mining Plan with the said Recognised Qualified Person on this following address.

R.RAJASEKAR.M.Sc., Reg.No.RQP/CNN/264/2015/A No.4A, Chozha Nagar, Pennadam Post, Tittakudi Taluk, Cuddalore- 606105 Cell – 9486905579 /8870110245 Email: raja.parvathi @gmail.com

I hereby undertake that all modifications so made in the Mining Plan by the

Recognised Qualified Person may be deemed to have been made with my knowledge and consent and shall be acceptable to me and building on me in all respects.

Signature of the Applicant

For Tvl.Patel Infrastructure limited

Place : Ariyalur

Date :

3

Tvl.PATEL INFRASTRUCTURE LIMITED,

Patel House,

Beside Prakruti Resort,

3, BP Estate, Chhani Road,

Chhani, NH 8 Vadodara,

Gujarat State– 391740

DECLARATION

The Mining Plan in respect of Earth/Savudu/Gravel quarry over an extent of

2.50.0hectares of Thondaman Eri in S.F.No. 125(P) of Muthuservamadam Village,

Udayarpalayam Taluk, Ariyalur District, and State have been prepared with my consultation and I have understood the contents and agree to implement the same in accordance with the Mining Laws.

Signature of the Applicant

For Tvl.Patel Infrastructure limited

Place: Ariyalur

Date:

4

R.RAJASEKAR.M.Sc., RQP/CNN/264/2015/A No.4A, Chozha Nagar, Pennadam Post, Tittakudi Taluk, Cuddalore- 606 105

CERTIFICATE

This is to certify that, the provisions of Minor Minerals Conservation and

Development Rules, 2010 (MMCDR) have been observed in the Mining Plan for the grant of Earth/Savudu/Gravel quarry lease over an extent of 2.50.0hectares of Thondaman

Eri in S.F.No. 125(P) of Muthuservamadam Village, Udayarpalayam Taluk, Ariyalur

District, Tamil Nadu State applied by Tvl.Patel Infrastructure limited.

Wherever specific permission / exemptions / relaxations or approvals are required, the applicant will approach the concerned authorities of State and Central

Government for granting such permissions etc.

Certified

Signature of Recognised Qualified Person

Place: Cuddalore

Date:

5

R.RAJASEKAR.M.Sc., RQP/CNN/264/2015/A No.4A, Chozha Nagar, Pennadam Post, Tittakudi Taluk, Cuddalore- 606 105

CERTIFICATE

Certified that, in preparation of Mining Plan for Earth/Savudu/Gravel quarry over an extent of 2.50.0hectares of Thondaman Eri in S.F.No. 125(P) of

Muthuservamadam Village, Udayarpalayam Taluk, Ariyalur District, Tamil Nadu State for

Tvl.Patel Infrastructure limited covers all the provisions of Mines Act, Rules, and Regulations etc made there under and whenever specific permission are required, the Applicant will approach the Director General of Mines Safety, Chennai. The standards prescribed by DGMS in respect of Mines Health will be strictly implemented.

Certified

Signature of Recognised Qualified Person

Place: Cuddalore Date:

6

MINING PLAN FOR MINOR MINERALS

EARTH/SAVUDU/GRAVEL QUARRY

Over an Extent 2.50.0hectares of Thondaman Eri in S.F.No. 125(P) of Muthuservamadam Village, Udayarpalayam Taluk, Ariyalur District and Tamilnadu (Prepared under 12 – 2A Tamilnadu Minor Mineral Concession Rules, 1959 And amended Minor Mineral Conservation and Development Rules, 2010)

1.0 INRODUCTION

2. The present Mining Plan and Environmental Management Plan are prepared

for Tvl.Patel Infrastructure Limited, Patel House, Beside Prakruti Resort, 3BP

Estate, Chhani Road, Chhani, NH 8, Vadodara, Gujarat State-391740.

3. The applicant proposed to quarry Earth/Savudu/Gravel in Thondaman Eri, over

an extent of 2.50.0hectares at S.F.No. 125(P) in Muthuservamadam Village of

Udayarpalayam Taluk, Ariyalur District for a period of (Three) 3 Months only. The

excavated Earth/Savudu/Gravel is used for filling and leveling of low lying areas

for road projects and other infrastructure development work in and around the

district.

4. The application was meritoriously processed by the District Collector Ariyalur

and passed an order vide R.c.No.319/G&M/2018, dated 10.12.2018 to get

Approved Mining Plan and obtain Environmental Clearance from the District

Level Environment Impact Assessment Authority, (DEIAA) Ariyalur, Tamil Nadu

vide MOEF and Climate Change Notification. S.O.141 (E) dated 15.01.2016.

5. Geological Reserves is estimated at 1,25,000m3 and Mineable Reserves is

estimated at 25,000m3 of Earth/Savudu/Gravel the area of Quarrying should be

Maintain without any damage to tank bund water inlet and outlet channels at the

time of quarrying as indicated in precise area communication letter and relevant

mining laws in force.

7

6. Production Schedule is proposed an average production of 25,000m3 (4167

Lorry Loads) of Earth/Savudu/Gravel upto a depth of 1.0m below ground level

for the period of (Three) 3 Months only.

7. Environmental parameters,

i) Forest Conservation Act, 1980: The area does not attract the Forest around 10Kms radius. ii) Interstate Boundary: The area does not attract the Interstate Boundary around 10Kms radius. iii) Wildlife (Protection) Act, 1972: The area does not attract the wild life sanctuary around 10Kms radius.

iv) The area does not attract the Coastal zone around 10kms radius from the lease applied area.

v) Infrastructure around 500m radius

Distance from boundary of S.No Description Direction Quarry site (m)

1 Approach Road 330m N

2 Open Wells ------

3 Water Bodies (Odai) ------

4 Habitation 420m N

5 LT/HT Line ------

Therefore the project seeks clearance only from District Level Environmental Impact Assessment Authority (DEIAA), under B2 Category.

8

2.0 EXECUTIVE SUMMARY:

The area applied for lease is a Thondaman Eri in Survey No. 125(P) of

Muthuservamadam Village, Udayarpalayam Taluk, Ariyalur District.

a. Village Panchayat - Muthuservamadam

b. Panchayat Union - Udayarpalayam

c. The proposed total Mineable Reserves = 25,000m3 of Earth/Savudu/Gravel.

d. The proposed quantity of Reserves (level of Production) to be mined

= 25,000m3 (i.e.; 25,000 m3/6 m3 (2 Unit) = 4,167 Loads/90 days (3 Months)

= 46 Lorry Loads Per day) of Earth/Savudu/Gravel for a Period of (Three) 3 Months

Only

e. Total extent of the area = 2.50.0Ha

f. Proposed Period of mining = (Three) 3 Months only.

g. Proposed Depth of mining = 1.0m below ground level.

h. Method of mining (level of mechanization)

Opencast Semi mechanized method is proposed without drilling and blasting.

i. Type of machineries used in the quarry

Machineries like Excavators and Tippers 10Tons capacity are proposed for

quarrying operation.

j. No trees are uprooted due to mining operations.

k. Around 18 employees are proposed to be deployed for the quarrying

Operation.

9

MUTHUSERVAMADAM VILLAGE (TOPOSHEET No. 58 – M / 08)

The lease applied area is bounded by all corners and the coordinates are clearly marked in Plate no - VI

Co- ordinates Distance between the Corners Latitude Longitude corners 1 11°12’56.56"N 79°27’52.05"E 1-2 = 250.0m 2 11°13’04.48"N 79°27’53.61"E 2-3 = 100.0m 3 11°13’03.86"N 79°27’56.87"E 3-4 = 250.0m 4 11°12’55.97"N 79°27’55.08"E 4-1 = 100.0m

3.0 GENERAL INFORMATION 3.1 a. Name of the Applicant : Tvl.Patel Infrastructure Limited

b. Address of the Applicant with : Patel House,

phone No and e-mail id if any Beside Prakruti Resort,

3BP Estate,

Chhani Road, Chhani,

NH 8, Vadodara,

Gujarat State-391740

Cell No :

Email :

c. Status of the Applicant : Individual

3.2 a. Mineral Which the applicant : Earth/Savudu/Gravel only intends to mine b. Precise area communication : Precise area communication letter letter No. received from District Collector, Ariyalur letter vide R.c.No. 319/G&M/2018 dated 10.12.2018

c. Period of permission / lease : The District Collector consider for grant granted of lease period of (Three) 3 Months only.

10

d. Name and Address of the RQP : R.RAJASEKAR.M.Sc., preparing Mining Plan Recognised Qualified Person No.4A, Chozha Nagar, Pennadam Post, TittakudiTaluk, Cuddalore- 606105. Cell : 9486905579/ 8870110245 Email : raja.parvathi @ gmail.com e. RQP Registration. No. : RQP/CNN/264/2015/A

Valid Til. 27.04.2025.

4.0 LOCATION a) Details of the area (with : The quarry lease applied area falls in the location map) Muthuservamadam Village. The applied area for quarrying lease bounded by following villages,

∑ Pappakudi - 0.6Km - (NE)

∑ Kundaveli West-0.7km - (NW)

∑ Gangai Konda Cholapuram - 1.4 km - (SW)

∑ Meensurutty - 0.8km - (SE)

i) District, Taluk and : Ariyalur District, Udayarpalayam Taluk and Village Muthuservamadam Village. ii) Survey Number : 125(P)

iii) Extent(in hectares) : 2.50.0Ha

b) Classification of the area : It is a Government Poramboke Land (Thondaman (Ryotwari/ Poramboke / Eri ) others) c) Ownership / Occupancy : It’s a Muthuservamadam Thondaman Eri, there is of the applied area no surface rights to lease applied area Please (surface right) refer the Annexure No – I.

d) Toposheet No. with : Topo sheet No : 58-M/08 latitude and longitude Latitude :11°12'55.97"N to 11°13'04.48"N

Longitude:79°26'03.07"E to 79°27'56.87"E79°28'38.69"Eto79°28'47.78"E

11

Details of Existence Infrastructures nearby approximate distance

S.No Description Place Distance Direction (Km) 1 Bus stand Jayamkondan 8.5 W

2 Post Office MS Madam 0.8 NW

3 Police Station Kundaveli West 2.5 NE

4 Fire service Jayamkondan 8.5 W

5 Railway Station Kuttalam 19.0 SE

6 Primary Health Centre Utkottai 4.5 SW

7 Government School Kattumannarkovil 10.0 NE

8 Airport 94 SW

9 Seaport Thoothukudi 309 S

12

PART – A

5.0 GEOLOGY AND MINERAL RESERVES 5.1 Brief description of : The lease applied area is exhibits almost Plain Terrain the Topography and topography covered with Earth/Savudu/Gravel which general Geology of does not sustain any type of vegetation due to the the area (with plans) topography of the land. The altitude of the area is 24m (Maximum) from MSL, the slope of the area is gentle towards Southeastern side. Please refer the Topography, Geological plan and sections (Plate No – VII).

S.No Age Rock Formation Recent to Sub 1 Alluvium, Topsoil recent 2 Archaean Charnokite Peninsular Gneiss, and Calc 3 Archaean Gneiss

5.2 Details of exploration : No exploration was carried out. The already carried out if Earth/Savudu/Gravel formation clearly visible right from any the surface. 5.3 Estimation of : The Geological plans demarcating the reserves commercially viable Earth/Savudu/Gravel have been prepared in 1:1000 scales (Plate No. VI).

Totally Two sections have been drawn, One section drawn Length wise as (X-Y) another One section drawn width wise as (A-B) to choose the maximum area cover under the lease in the Horizontal 1:1000 and Vertical 1:100 (please refer Plate No- VI).

The cross sectional area for the proved depth persistence of 1.0m has been worked out for the section. The cross sectional area multiplied by its length of influence on the longer axis gives the volume (insitu) in the cross sectional area. The sum total of the insitu reserves available within the individual cross sectional area gives the geological reserves of the lease applied area.

13

As the Mineable of Earth/Savudu/Gravel in the terms of cubic meter. The Geological Reserve, Mineable Reserves are given only in terms of Cubic meter. The Details of estimation of Geological Reserves and Mineable Reserves with reference to Topography, Geological Plan and Section shown in (Plate No. VI ).

<

a) Geological reserves The Geological Reserves are estimated as given below are calculated Cross Sectional method GEOLOGICAL RESERVES Lengt Geological Width Depth Section h in Reserves in in (m) in (m) (m) Cbm XY - AB 250 100 5 1,25,000

1,25,000 Total

The availability Geological Reserves

of Earth/Savudu/Gravel upto a depth of 5m = 1,25,000m3

b) Recoverable The Mineable Reserves are calculated as given below reserves (Please refer Plate No-VII & VII-A)

MINEABLE RESERVES Recoverable Length Width Depth in Section Reserves in in (m) in (m) (m) m3 XY-AB 250 100 1 25,000

25,000 Total

Total Mineable Reserves upto Depth 1.0m= 25,000m3

The applicant proposed to excavate 25,000m3 of

Earth/Savudu/Gravel up to a depth of 1.0m for a period

of (Three) 3 Months Only.

14

Fig.1 – Photograph shows general view of the lease applied area

Fig.2 – Close view of medium to fine grained Earth/Savudu/Gravel deposit

15

6.0 MINING

6.1 Method of mining (opencast / : Opencast method of shallow mining is underground) proposed, Machineries like excavators are proposed for quarrying Earth/Savudu/Gravel 1.0m depth below the ground level,

It is being loose in nature No drilling or blasting is proposed for this type of Earth/Savudu/Gravel quarrying, it is an ecofriendly quarrying operation.

The Earth/Savudu/Gravel will be loaded directly to the 10T/Tippers for transportation to the needy customer’s site for filling and leveling of low lying areas for road project and other infrastructure development work in and around the District.

6.2 Mode of working (mechanized, : It’s an opencast quarrying operation without semi mechanized, manual) drilling and blasting.

6.3 Proposed bench height & width : The applied area is soft soil / float deposit with 45° slope from the horizontal and benches depth 1.0m and width not less than 1.0m formed as per 106 (2) of MMR 1961.

6.4 Indicate the overburden / : There is no overburden, the mineral production expected pit Earth/Savudu/Gravel is to exploit only to a wise as detailed below depth of 1.0m below ground level. The (composite plan and section applicant proposed to excavate upto a depth showing pit layout, dumps, of 1.0m for a period of (Three) 3 Months disposal of waste if any etc.) only.

16

6.5 Machineries used

a) For mining : Excavator of 0.90m3 capacity, Diesel Drive.

b) Loading equipment : Excavator of 0.90m3 capacity, Diesel Drive.

c) Transportation (includes : Hired Tippers 10Tons capacity. Diesel Drive. within the mine and mine (Only from quarry to needy customer’s site). to destination 6.6 Disposal of overburden / : There is no wastage is anticipated during the waste quarrying operation the entire Earth/Savudu/Gravel will be used for filling and leveling of low lying areas road project and other infrastructure development work in and around the District.

6.7 Brief note on conceptual : Conceptual mining plan is prepared based mining plan for the entire upon Topography, Geological plan and section lease period base on the with an object of (Three) 3 Months of systematic geological, mining and development of lay outs, selection of ultimate environmental pit limit etc., The ultimate pit dimensions of the considerations quarry are given below.

CONCEPTUAL TABLE

Length in Width in Depth in (m) Max (M) Max (m)

250 100 1.0

It is an Eco friendly Quarrying operation without drilling and Blasting.

17

EXCAVATOR OF 0.90m3 CAPACITY, DIESEL DRIVE

HIRED TIPPERS 10/20TONS CAPACITY. DIESEL DRIVE

18

7.0 BLASTING 7.1 Blasting pattern 7.2 Type of explosives to be used It is being loose soil in nature No drilling or 7.3 Measures proposed to blasting is proposed for this type of : minimize ground vibration Earth/Savudu/Gravel quarrying, it is an due to blasting ecofriendly quarrying operation. 7.4 Storage and safety measures to be taken while blasting

8.0 MINE DRAINAGE 8.1 Depth of water table (based : The water table is noticed as 17m to 18m on nearby wells and water below ground level observation from nearby bodies) Bore hole during the seasonal condition water level like Post monsoon is 17m and Pre monsoon 18m below ground level of this quarry area. 8.2 Arrangements and places : There is no such type of activities anticipated where the mine water is in this quarrying operation. finally proposed to be discharged

9.0 OTHER PERMANENT STRUCTURES (also shown in the map) 9.1 Habitations/Village, Natham : There is Habitation located at the distance of 430m on Northern side of the lease applied area

9.2 Power lines (HT/ LT) : There is no HT/LT within 500m radius from the area

9.3 Water bodies (river, Pond, : The Lease area is located at Thondaman Eri lake, odai, channel etc.)

9.4 Archaeological / historical : There is no Archaeological / historical monuments monuments within 500m radius from the area.

9.5 Existence of public road / : ∑ There is an existing road from the area (SH,NH others),Railway line if leads Pappakudi road at the distance any 0.33Km on Northern side of the area. ∑ (SH-150) Ukkarai to Pandanallur road is located which is about 10.5Km on the Southeastern side of the area.

∑ (NH-45C) Kombakonam to road is located which is about 0.5Km on the Eastern side of the area. ∑ The Nearest Railway line is Kuttalam station line which is about 19.0km on the Southeastern of the area. 9.6 Places of worship : There is no Temples is found around the 500m

19

radius of the proposed site

9.7 Reserved forest / forest / : There is no Reserved forest / Social forest social forest within 10km radius.

9.8 National Park, Wild life There are no National Park, Wild life Sanctuary, Interstate Sanctuary, Interstate Boundary, C.R.Z, Notified Boundary, C.R.Z, Notified eco eco sensitive zones etc. within a radius of sensitive zones etc., 10km. 9.9 Any other structure Nil

10.0 EMPLOYMENT POTENTIAL & WELFARE MEASURES ,

10.1 Employment : The following man power is proposed for the potential (skilled, Earth/Savudu/Gravel quarrying to carry out the day-to- day quarrying activities, aimed at the proposed semi skilled, production target and also to comply with the statutory unskilled) provisions of the Government norms.

Management/Supervisory staff : 1

Skilled :

∑ Mines Mate : 1 ∑ Mechanic : 2

Semi-skilled:

∑ Excavators Operators : 2

∑ Co-operator : 1

Un -Skilled:

∑ Labours : 5

∑ Watchman : 1

∑ Unskilled – helpers : 5

Total : 18

The above manpower is adequate to meet out the production schedule and the machinery strength envisaged in the mining plan and to comply with the statutory provisions of the Mines Safety Regulations. It is ensured that the labor will not deployed under 18 Years. No child labor will engage or entertained for

20

any kind of quarrying operation, all the labors engaged for quarrying operation will be insured till the end of life of quarry.

10.2 Welfare measures

a) Drinking water : Drinking water is available from the nearby water vendors or agriculture land in the Pappakudi which is about 0.6Km on the Northeastern side of the area.

b) Sanitary facilities : Hygienic Sanitary facilities will be constructed with in the quarrying area as semi permanent structure.

c) First Aid facility : First aid kits are kept in nearby village if any accident happens first aid will be given at site and the injured person will be taken to the hospital immediately, Hospital is available at Jayamkondan which is about 11.0km on the Western side of the area. The competent statutory Mines Mate will be in charge of first aid.

d) Labors Health : In the Eco friendly opencast quarrying operation No drilling or blasting is involved only Excavator are used, hence labors health may not affect in any manner however periodically medical checkup will be conducted to all the workers for any mine health related problems, proper First Aid training and induction will be given to quarrying qualified personnel to create awareness to the workers.

e) Precautionary : All the quarry workers will be provided with Safety safety measures to Helmets, Mine Goggles, Ear plugs, Ear muffs, Dust the labourers mask, Reflector Jackets and Safety Shoes as personal protective device as per the specification of Director of Mine Safety.

21

PART – B

11.0 ENVIRONMENT MANAGEMENT PLAN 11.1 Existing land use : It’s a dry barren land covered with Earth/Savudu/Gravel pattern formation, does not sustain any type of vegetation due to this Earth/Savudu/Gravel formation.

11.2 Water Regime : Ground water level is noticed as 17m to 18m below ground level observation from the nearby Open well and bore hole. The quarrying is restricted up to 1.0m below ground level, hence the quarry operation will not be affected by the ground water.

11.3 Flora and fauna : The main trees are Julia Flora, Neem, etc, There is no notified reserve forest or social forest near the area applied for quarrying lease. No flora of botanical interest or fauna of zoological interest noticed.

11.4 Climatic : Both the North East and South West monsoon occurs here conditions and the summer are hot and winters are cool. During April and May the temperature may shoot upto 34.0°C and during winter the temperature does not fall below 23.8°C. The annual rainfall is around 1170mm.

11.5 Human settlement : There are few villages located in 5.0Km radius from the

lease applied area the details of the areas are given below.

Approximate distance & Approximate S.No Name of the Village Direction from population lease applied area

1. Pappakudi 0.6Km (NE) 210

2. Kundaveli West 0.7km(NW) 260

3. Gangai konda 1.5 km (SW) 310 Cholapuram

4. Meensurutty 0.8km (SE) 290

22

11.6 Plan for air, dust : In this Eco friendly quarrying operation only Excavator suppression are proposed without drilling and blasting, hence the air quality will not affect due to the quarrying operation, water will be sprinkled in the haul roads periodically to suppress dust Ambient Air Quality monitoring will be carried out to check the Quality of Air in and around the Quarry. Water for dust suppression will be extract from the existing borehole by the applicant from the nearby villages. During transportation the Earth/Savudu/Gravel will be fully covered by Tarpaulin to prevent dust and spillage.

11.7 Plan for noise : This Eco Friendly quarrying operation does not involve level control any blasting and drilling methods, hence noise will be minimal and this is only due to the movement of Excavators and Trucks. Periodically Noise level monitoring will be carried out to check the Noise level in and around the Quarry.

11.8 Environmental : The life span of the quarry is proposed for the impact period of (Three) 3 Months only, the Proposed quarrying assessment for a small production of Earth/Savudu/Gravel does not statement involve deep whole drilling and blasting. Such limited describing impact mining activity is not likely to cause any impact adversely of mining on the on environment as far as pollution of air, water and noise is next five Months concerned. 11.9 Proposal for : There are no wastages anticipated during the quarrying waste operation. The entire Earth/Savudu/Gravel will be management transported to the needy customer’s site. 11.10 Proposal for : The quarry operation is restricted up to a depth of reclamation of 1.0m, after removing the Earth/Savudu/Gravel there is no land affected proposal for backfilling or reclamation. The quarried out during mining activities and at land will be used for water storage purpose the end of mining (refilling / fencing etc.)

23

11.11 Program of : After the completion of the quarrying operation, the afforestation land will used for water storage purpose. The applicant (indicate extend, ensured to plant native species like pungam, neem, and number, name of teak wood nearby villages, village road and govt school species to be after consultation with the competent panchayat afforested) authorities. It is proposed to plant around 150 trees for the period of (Three) 3 Months.

11.12 Proposed : The proposed financial estimate budget for EMP is financial estimate around Rs.99,500/-for the lease period of (Three) 3 /budget for (EMP) Months only. environment management:

Project cost / investment

i) Land cost : It is Muthuservamadam Thondaman Eri - NIL

ii) Machinery : The Excavators of 0.90m3 bucket capacity and Tippers of to be 10Tons capacity will be used for the quarrying operation. used iii) Refilling/ : Nil Fencin g iv) Laborers : Nil shed v) Sanitary : Sanitary facility will be constructed as semi-permanent facility structure, the cost will be around Rs.50,000/-

vi) Others items : Nil

24

Project Cost / Investment :-

i) Land cost = Rs. Nil

ii) Machinery to be used = Rs. 7,00,000/-

iii) Refilling/Fencing cost = Rs. Nil

iv) Rest shelter = Rs. Nil

v) Sanitary Facility = Rs. 50,000/-

vi) Other Items = Rs. Nil

vii) Total = Rs. 7,50,000/

(a) Expenditure i) Drinking water : 18 Labours at the rate of Rs.3000/- month for a period of facility and (Three) 3 Months, the cost will be around Rs.9,000/- other utilities for the laborers ii) Sanitary : Sanitary maintenance at the cost of Rs.2500/- month the arrangement cost will be around Rs.7,500/- for a period of (Three) 3 Months.

iii) Safety kits, : Rs.50,000 will be spent for the safety kits such as Helmet, Mine Goggles, Ear plugs, Ear muff, Dust Mask, Reflector jackets and safety Shoes.

25

iv) Water : Rs 6000/ month will be spent for sprinkling the water on sprinkling haul roads for Dust suppression; the cost will be around (if necessary) Rs. 18,000/- for a period of (Three) 3 Months.

v) Afforestation : Afforestation is proposed to plantation will be carried out etc. on the nearby villages, village roads and govt school after consultation with the panchayat authorities. The cost estimate is around Rs.15,000/-

EMP Cost i. Drinking water = Rs. 9,000/- ii. Sanitary Arrangements = Rs. 7,500/- iii. Safety kits = Rs 50,000/- iv. Water Sprinkling = Rs. 18,000/- v. Afforestation cost = Rs. 15,000/- Total = Rs. 99,500/-

Total Project Cost = Rs. 7,50,000/-

EMP Cost = Rs. 99,500/-

12.0 MINE CLOSURE PLAN

12.1 Steps proposed for phased : It’s a New quarrying project no quarried out restoration, reclamation of areas within the lease applied area. already mined out areas

12.2 Measures to be under taken : This Eco – Friendly quarrying for a depth of on mine closure as per Act & 1.0m below ground level does not require Rules any backfilling, Reclamation and Rehabilitation, the quarried out land will be used for more water storage purpose.

12.3 Mitigation measure to be : This is a fresh Earth/Savudu/Gravel quarry. undertaken for safety and restoration / reclamation of the already mined out area

26

13.0 ANY OTHER DETAILS INTEND TO FURNISH BY THE APPLICANT

i) Permission will be obtained from the District Mines Office to extract the Earth/Savudu/Gravel from the Boundary barriers and for slopes. ii) Care and precautionary measures will be taken for the safety of workers as per Rules and Acts. iii) The applicant will endeavor every attempt to quarry the Earth/Savudu/Gravel economically without any wastage and to improve the environment and ecology. iv) The Mining Plan is prepared by incorporating the conditions stipulated in the precise area communication issued and also prepared by incorporating the details mentioned in the letter SEIAA/TN/Minor and Minerals/2012 dated 17.04.2013. v) Any violation pointed out by the inspecting authorities shall be rectified as per the guidelines of the Department vi) The proposed quantity of Earth/Savudu/Gravel is 25,000m3 up to a depth of 1.0m below ground level for a lease period of (Three) 3 Months only.

Prepared by

Signature of Recognised Qualified Person

Place : Cuddalore Date :