MINISTRY OF REGIONAL DEVELOPMENT AND INFRASTRUCTURE OF

01.12.2018 Roads Department of Georgia

Preparation of design Bidding period of Implementation of documentation construction works construction works N Name Status Note Start Completion Start Completion Start Completion

Ongoing construction

1 Zestaponi-Kutaisi new bypass (including Argveta July, 2013 January, 2018 Construction interchange) 2 Samtredia-Grigoleti (Lot I) Construction 3 Samtredia-Grigoleti (Lot II) March, 2016 December, 2019 Construction

4 Samtredia-Grigoleti (Lot IV) May, 2015 December, 2018 Construction

5 Kobuleti bypass (Lot II) May, 2013 June, 2018 Construction 6 Construction of bypass road (15 km) of Akhmeta- December, June, 2019 Construction Telavi-Bakurtsikhe road (Bakurtsikhe-Gurjaani) 2016

7 Devdoraki tunnel March, 2017 June, 2018 Detailed design Contract is signed 8 Stepantsminda Sameba Church April, 2017 November, 2018 Detailed design Contract is signed 9 Zestaponi-Kutaisi lighting June, 2017 February, 2018 Construction bidding Ongoing and planned construction biddings

1 Batumi bypass road October, 2016 July, 2017 October, 2017 May, 2020 Construction Contract is bidding signed 2 Samtredia-Grigoleti (Lot III) October, 2016 June, 2017 September, November, 2019 Construction Contract is 2017 bidding signed 3 Zemo Osiauri-Chumateleti (Lot I) February, July, 2017 August, 2017 August, 2019 Construction Contract is 2016 bidding signed 4 Zemo Osiauri-Chumateleti (Lot II) February, July, 2017 August, 2017 August, 2020 Construction Contract is 2016 bidding signed 5 Grigoleti- April, 2016 July, 2017 August, 2017 February, 2018 May, 2018 May, 2020 Detailed design Contract is signed 6 Dzirula-Moliti (Lot I) February, 2017 July, 2017 August, 2017 February, 2018 May, 2018 May, 2020 Detailed design Contract is signed 7 Moliti-Chumateleti (Lot 2) February, 2017 January, 2018 February, July, 2018 August, 2018 February, 2021 Detailed design 2018 Khulo-Goderdzi (Lot I) February, August, 2017 March, 2018 March, 2019 Detailed design Bidding 8 2017 procedures are ongoing 9 Goderdzi-Zarzma (Lot II) August,2017 March, 2018 March, 2019 Detailed design Bidding procedures are 10 Construction of a bridge on Debeda River Contractongoing is signed 11 Sno-Juta-Roshka-Shatili-Omalo-Khadori gorge- December, 2016 October, 2018 Detailed design Contract is Akhmeta-Batsara signed 12 Bagdati-Abastumani January, 2017 July, 2018 Detailed design Contract is signed 13 Zemo Imereti-Racha January, 2017 July, 2018 Detailed design Contract is signed Preparation of design Bidding period of Implementation of documentation construction works construction works N Name Status Note Start Completion Start Completion Start Completion

14 Kobuleti bypass (Lot I) lighting June, 2017 November, December, May, 2018 Bidding 2017 2017 procedures are Ongoing design of construction ongoing

1 Chumateleti-Khevi (F1) February, 2017 March, 2018 May, 2018 October, 2018 November, November, 2021 Detailed design 2018

2 Khevi-Ubisa (F2) April, 2017 April, 2018 June, 2018 November, December, December, 2021 Detailed design 2018 2018 3 Ubisa-Shorapani (F3) April, 2017 March, 2018 May, 2018 October, 2018 December, December, 2021 Detailed design 2018 4 Shoropani-Argveta (F4) April, 2017 January, 2018 May, 2018 November, January, 2019 January, 2022 Detailed design 2018 5 Kvesheti-Kobi May, 2017 May, 2018 July, 2018 December, January, 2019 January, 2022 Design 2018 6 Natakhtari-Zhinvali June, 2017 September, 2018 December, May, 2019 June, 2019 December, 2021 Preparation of 2018 feasibility study and detailed design 7 Batumi(Chorokhi)-Sarpi November, 2017 September, 2018 November, April, 2019 May, 2019 November, 2021 Preparation of 2018 feasibility study and detailed design 8 Rustavi-Red Bridge February, 2017 March, 2018 May, 2018 October, 2018 November, May, 2021 Detailed design 2018 9 -Sadakhlo February, 2017 May, 2018 July, 2018 December, January, 2019 July, 2021 Detailed design 2018 10 Tbilisi-Sagarejo June, 2017 May, 2018 July, 2018 December, January, 2019 July, 2021 Preparation of 2018 feasibility study and detailed design 11 Sagarejo-Bakurtsikhe June, 2017 June, 2018 August, 2018 February, 2019 March, 2019 March, 2021 Preparation of feasibility study and detailed design 12 Zugdidi-Anaklia (PFS and FS) February, 2017 February, 2018 December, May, 2019 June, 2019 December, 2020 Preparation of 2018 feasibility study and detailed design 01.12.2018 Roads Department of Georgia Preparation of design Bidding period of Implementation of documentation construction works construction works N Name Status Note Start Completion Start Completion Start Completion

Ongoing construction

1 Zestaponi-Kutaisi new bypass (including Argveta July, 2013 January, 2018 Construction interchange) 2 Samtredia-Grigoleti (Lot I) Construction 3 Samtredia-Grigoleti (Lot II) March, 2016 December, 2019 Construction

4 Samtredia-Grigoleti (Lot IV) May, 2015 December, 2018 Construction

5 Kobuleti bypass (Lot II) May, 2013 June, 2018 Construction 6 Construction of bypass road (15 km) of Akhmeta- December, June, 2019 Construction Telavi-Bakurtsikhe road (Bakurtsikhe-Gurjaani) 2016

7 Devdoraki tunnel March, 2017 June, 2018 Detailed design Contract is signed 8 Stepantsminda Sameba Church April, 2017 November, 2018 Detailed design Contract is signed 9 Zestaponi-Kutaisi lighting June, 2017 February, 2018 Construction bidding Ongoing and planned construction biddings

1 Batumi bypass road October, 2016 July, 2017 October, 2017 May, 2020 Construction Contract is bidding signed 2 Samtredia-Grigoleti (Lot III) October, 2016 June, 2017 September, November, 2019 Construction Contract is MINISTRY OF REGIONAL DEVELOPMENT2017 ANDbidding signed 3 Zemo Osiauri-Chumateleti (Lot I) February, July, 2017 August, 2017 August, 2019 Construction Contract is INFRASTRUCTURE OF GEORGIA2016 bidding signed 4 Zemo Osiauri-Chumateleti (Lot II) February, July, 2017 August, 2017 August, 2020 Construction Contract is 2016 bidding signed 5 Grigoleti-Choloki April, 2016 July, 2017 August, 2017 February, 2018 May, 2018 May, 2020 Detailed design Contract is signed 6 Dzirula-Moliti (Lot I) February, 2017 July, 2017 August, 2017 February, 2018 May, 2018 May, 2020 Detailed design Contract is signed 7 Moliti-Chumateleti (Lot 2) February, 2017 January, 2018 February, July, 2018 August, 2018 February, 2021 Detailed design 2018 Khulo-Goderdzi (Lot I) February, August, 2017 March, 2018 March, 2019 Detailed design Bidding 8 2017 procedures are ongoing 9 Goderdzi-Zarzma (Lot II) August,2017 March, 2018 March, 2019 Detailed design Bidding procedures are 10 Construction of a bridge on Debeda River Contractongoing is signed 11 Sno-Juta-Roshka-Shatili-Omalo-Khadori gorge- December, 2016 October, 2018 Detailed design Contract is Akhmeta-Batsara signed 12 Bagdati-Abastumani January, 2017 July, 2018 Detailed design Contract is signed 13 Zemo Imereti-Racha January, 2017 July, 2018 Detailed design Contract is signed Preparation of design Bidding period of Implementation of documentation construction works construction works N Name Status Note Start Completion Start Completion Start Completion

14 Kobuleti bypass (Lot I) lighting June, 2017 November, December, May, 2018 Bidding 2017 2017 procedures are Ongoing design of construction ongoing

1 Chumateleti-Khevi (F1) February, 2017 March, 2018 May, 2018 October, 2018 November, November, 2021 Detailed design 2018

2 Khevi-Ubisa (F2) April, 2017 April, 2018 June, 2018 November, December, December, 2021 Detailed design 2018 2018 3 Ubisa-Shorapani (F3) April, 2017 March, 2018 May, 2018 October, 2018 December, December, 2021 Detailed design 2018 4 Shoropani-Argveta (F4) April, 2017 January, 2018 May, 2018 November, January, 2019 January, 2022 Detailed design 2018 5 Kvesheti-Kobi May, 2017 May, 2018 July, 2018 December, January, 2019 January, 2022 Design 2018 6 Natakhtari-Zhinvali June, 2017 September, 2018 December, May, 2019 June, 2019 December, 2021 Preparation of 2018 feasibility study and detailed design 7 Batumi(Chorokhi)-Sarpi November, 2017 September, 2018 November, April, 2019 May, 2019 November, 2021 Preparation of 2018 feasibility study and detailed design 8 Rustavi-Red Bridge February, 2017 March, 2018 May, 2018 October, 2018 November, May, 2021 Detailed design 2018 9 Algeti-Sadakhlo February, 2017 May, 2018 July, 2018 December, January, 2019 July, 2021 Detailed design 2018 10 Tbilisi-Sagarejo June, 2017 May, 2018 July, 2018 December, January, 2019 July, 2021 Preparation of 2018 feasibility study and detailed design 11 Sagarejo-Bakurtsikhe June, 2017 June, 2018 August, 2018 February, 2019 March, 2019 March, 2021 Preparation of feasibility study and detailed design 12 Zugdidi-Anaklia (PFS and FS) February, 2017 February, 2018 December, May, 2019 June, 2019 December, 2020 Preparation of 2018 feasibility study and detailed design 01.12.2018 Roads Department of Georgia Preparation of design Bidding period of Implementation of documentation construction works construction works N Name Status Note Start Completion Start Completion Start Completion

Ongoing construction

1 Zestaponi-Kutaisi new bypass (including Argveta July, 2013 January, 2018 Construction interchange) 2 Samtredia-Grigoleti (Lot I) Construction 3 Samtredia-Grigoleti (Lot II) March, 2016 December, 2019 Construction

4 Samtredia-Grigoleti (Lot IV) May, 2015 December, 2018 Construction

5 Kobuleti bypass (Lot II) May, 2013 June, 2018 Construction 6 Construction of bypass road (15 km) of Akhmeta- December, June, 2019 Construction Telavi-Bakurtsikhe road (Bakurtsikhe-Gurjaani) 2016

7 Devdoraki tunnel March, 2017 June, 2018 Detailed design Contract is signed 8 Stepantsminda Sameba Church April, 2017 November, 2018 Detailed design Contract is signed 9 Zestaponi-Kutaisi lighting June, 2017 February, 2018 Construction bidding Ongoing and planned construction biddings

1 Batumi bypass road October, 2016 July, 2017 October, 2017 May, 2020 Construction Contract is bidding signed 2 Samtredia-Grigoleti (Lot III) October, 2016 June, 2017 September, November, 2019 Construction Contract is 2017 bidding signed 3 Zemo Osiauri-Chumateleti (Lot I) February, July, 2017 August, 2017 August, 2019 Construction Contract is 2016 bidding signed 4 Zemo Osiauri-Chumateleti (Lot II) February, July, 2017 August, 2017 August, 2020 Construction Contract is 2016 bidding signed 5 Grigoleti-Choloki April, 2016 July, 2017 August, 2017 February, 2018 May, 2018 May, 2020 Detailed design Contract is signed 6 Dzirula-Moliti (Lot I) February, 2017 July, 2017 August, 2017 February, 2018 May, 2018 May, 2020 Detailed design Contract is signed 7 Moliti-Chumateleti (Lot 2) February, 2017 January, 2018 February, July, 2018 August, 2018 February, 2021 Detailed design 2018 Khulo-Goderdzi (Lot I) February, August, 2017 March, 2018 March, 2019 Detailed design Bidding 8 2017 procedures are ongoing 9 Goderdzi-Zarzma (Lot II) August,2017 March, 2018 March, 2019 Detailed design Bidding procedures are 10 Construction of a bridge on Debeda River Contractongoing is signed 11 Sno-Juta-Roshka-Shatili-Omalo-Khadori gorge- December, 2016 October, 2018 Detailed design Contract is Akhmeta-Batsara signed 12 Bagdati-Abastumani January, 2017 July, 2018 Detailed design Contract is signed 13 Zemo Imereti-Racha January, 2017 July, 2018 Detailed design Contract is signed Preparation of design Bidding period of Implementation of documentation construction works construction works N Name Status Note Start Completion Start Completion Start Completion

14 Kobuleti bypass (Lot I) lighting June, 2017 November, December, May, 2018 Bidding 2017 2017 procedures are Ongoing design of construction ongoing

1 Chumateleti-Khevi (F1) February, 2017 March, 2018 May, 2018 October, 2018 November, November, 2021 Detailed design 2018

2 Khevi-Ubisa (F2) April, 2017 April, 2018 June, 2018 November, December, December, 2021 Detailed design 2018 2018 3 Ubisa-Shorapani (F3) April, 2017 March, 2018 May, 2018 October, 2018 December, December, 2021 Detailed design 2018 4 Shoropani-Argveta (F4) April, 2017 January, 2018 May, 2018 November, January, 2019 January, 2022 Detailed design MINISTRY OF REGIONAL DEVELOPMENT2018 AND 5 Kvesheti-Kobi May, 2017 May, 2018 July, 2018 December, January, 2019 January, 2022 Design INFRASTRUCTURE OF GEORGIA2018 6 Natakhtari-Zhinvali June, 2017 September, 2018 December, May, 2019 June, 2019 December, 2021 Preparation of 2018 feasibility study and detailed design 7 Batumi(Chorokhi)-Sarpi November, 2017 September, 2018 November, April, 2019 May, 2019 November, 2021 Preparation of 2018 feasibility study and detailed design 8 Rustavi-Red Bridge February, 2017 March, 2018 May, 2018 October, 2018 November, May, 2021 Detailed design 2018 9 Algeti-Sadakhlo February, 2017 May, 2018 July, 2018 December, January, 2019 July, 2021 Detailed design 2018 10 Tbilisi-Sagarejo June, 2017 May, 2018 July, 2018 December, January, 2019 July, 2021 Preparation of 2018 feasibility study and detailed design 11 Sagarejo-Bakurtsikhe June, 2017 June, 2018 August, 2018 February, 2019 March, 2019 March, 2021 Preparation of feasibility study and detailed design 12 Zugdidi-Anaklia (PFS and FS) February, 2017 February, 2018 December, May, 2019 June, 2019 December, 2020 Preparation of 2018 feasibility study and detailed design 13 Gurjaani(Chumlaki)-Telavi bypass March, 2017 April, 2018 14 Bakurtsikhe-Tsnori March, 2017 February, 2018 April, 2018 September, October, 2018 April, 2021 Detailed design 2018 15 Bridge on River near Poti April, 2016 November, 2017 January, 2018 June, 2018 July, 2018 July, 2020 Detailed design

16 Lentekhi-Mestia December, 2016 July, 2018

Sum Total