Das grüne Kabel

Kieler Branchenfokus Windindustrie Kiel 07.07.2015 Gunnar Spengel TenneT Project Director NordLink Offshore Projekte I Projekte Lehrte

\ 1 NordLink NordLink German-Norwegian Co-Operation

 Realized by the Norwegian TSO , TenneT TSO GmbH and KFW

 Final Investment Decision and start construction project execution in the first quarter 2015

 Start commercial operation in 2020 (commissioning and trial operation in Q4/2019)

 Investment 1,5 – 2 billion Euro

\ 2 NordLink NordLink Overview

 TenneT – The Company  NordLink Partners  Facts and Figures  Key Argument & Benefits  German Production and Consumption  HVDC Technology  Conclusion

\ 3

NordLink TenneT - The Company

• We supply 41 million end users with

• Operation, maintenance and further development of extra high-voltage power grids in parts of and the

TenneT

• Approx. 21.000 km total grid length • 445 substations • Approx. 2.800 employees • € 2,3 billion turn over in grid business

\ 4 NordLink TenneT Offshore Grid Connections

Capacity Project Commissioning (MW)

Operational alpha ventus 62 2009 BorWin1 400 2010 BorWin2 800 2015 HelWin1 576 2015 HelWin2 690 2015 Riffgat 113 2014 SylWin1 864 2015 Ʃ 3.505 Under construction / awarded BorWin3 900 2019 DolWin1 800 2015 DolWin2 916 2016 DolWin3 900 2017 Nordergründe 111 2016 Ʃ 3.627 NordLink

NordLink Partners

Norwegian TSO Owner and operator of the Norwegian grid, including interconnectors  50% project ownership

Dutch and German TSO

Owner and operator of the grid at the connection

points in Germany

 25% project ownership

German government owned financial institution Active in financing Energiewende projects  25% project ownership

DC Nordseekabel GmbH & Co. KG

\ 6 NordLink

Facts and Figures  Connection  Europe‘s longest HVDC Link  623 km grid connection  Onshore DE: 54 km land cable  Technical details  Offshore: 516 km subsea cable 1400 MW, 500 kV, bi-pole HVDC  Onshore NO: 53 km overhead line

\ 7 NordLink Impressions & Germany

\ 8 NordLink Germany-Norway Norway can export its energy surplus . Germany can export energy  Facilitate European Market to Norway when the wind is intergration blowing on the continent during dry season

 The NordLink interconnector will stabilize electricity prices and facilitate a more predictable energy market

 Add welfare to the society

\ 9 NordLink Energy Production and Consumption

2012  2022 Offshore- Windparks NordLink ++

2012- 2022

Leistungsbilanz 2012 [MW] Leistungsbilanz 2022 [MW] -500 9000 -500 9000 Lichtenfels, 11. Oktober 2012 www.netzentwicklungsplan.de

\ 10 NordLink

HVDC Technology

HVDC  High Voltage Direct Current (HGÜ)  Voltage Source Converter – VSC  Transmission from AC to DC and vice versa AC ~ DC -

DC - AC ~

Why HVDC?

. AC cable transmission links have a maximum distance of ~ 100 km . HVDC avoids the heavy currents required to charge and discharge the cable . For longer distances HVDC cable transmission is the only possible solution . Active and reactive power independently and rapidly controlled . Black start possible

\ 11 NordLink Schematic Converter Station

Area ~ 200m x 200m

12 NordLink

Mass Impregnated Cables

 Why mass impregnated cables? only proven technology for voltage level ≥ 500 kV used for HVDC power cable since 1954 environmental friendly - no liquids or gases are released

 NordLink Facts

rated voltage U0= 525 kV overall cable diameter up to 128 mm  weight in air up to 70 kg/m total cable weight ~ 70.000 t

Source TenneT: NorNed Cable

\ 13 NordLink Offshore Cable Installation

Post Lay Burial Norwegian and Danish sector

Simultaneous Lay German sector

Bundled cables German sector

\ 14 NordLink Installation Nearshore Vertical Injector (Stehendes Spülschwert)

\ 15 NordLink Underground Cable Laying

Underground Cable (Cu) ~ 2.280 mm² ~ 46 kg/m ~ 100 mm Ø ~ 1200 m batch lenghts

\ 16 NordLink

TenneT Interconnectors

. BritNed cable to the United Kingdom . NorNed cable to Norway . NordLink cable linking Germany to Norway (planned) . COBRA cable linking the Netherlands to (in development) . Interconnector linking Doetinchem in the Netherlands to Wesel in Germany . Increasing capacity planned of the interconnector Meeden (NL) – Diele (GER)

TenneT contributes to the development of an integrated NWE by supporting interconnection countries.

\ 17 NordLink

NordLink Conclusion

The exchange of power enabled by NordLink will…  increase security of supply for the German and Norwegian grid  stabilize electricity prices and facilitate a more predictable energy market  facilitate European market integration  transmit hydroelectric power to the Bavarian industry from Norway or wind energy from north Germany.  allow exchange of 1400 MW renewable energies

\ 18 NordLink

Thanks for your Attention!

Gunnar Spengel TenneT Project Director NordLink Offshore Projekte I Projekte Lehrte