DRAFT February 22, 2021 Reasonable Progress Assessment for Domtar Paper Company, LLC – Plymouth, NC

Disclaimer As a part of the Regional Haze State Implementation Plan (SIP) process, the Division of Air Quality (NCDAQ) has requested Domtar Paper Company (Domtar) to complete a Reasonable Progress Assessment/Four-Factor Analysis for further controlling sulfur dioxide (SO2) emissions for improving visibility in the Swanquarter Wilderness Area. The NCDAQ has received external requests for the Reasonable Progress Assessment/Four-Factor Analysis for this facility. It is important to note that the NCDAQ staff is still reviewing this analysis that Domtar submitted to the NCDAQ. Furthermore, the NCDAQ will request that the U.S. Environmental Protection Agency (USEPA) and Federal Land Managers (FLMs) review this analysis before the Regional Haze SIP is released for public comment later this Spring. The following analysis from Domtar is draft and will be revised to address any comments from NCDAQ staff as well as comments received from the USEPA and FLMs prior to the public comment period.

Correspondence Record Date From To Description Request to review 2028 SO2 emissions and PSAT May 4, 2020 NC DAQ Domtar modeling, evaluate sources for four-factor analysis NC May 12, 2020 Domtar Revised emissions estimates DAQ Request four-factor analysis on three units using May 22, 2020 NC DAQ Domtar updated emissions and revised PSAT modeling results NC Four-factor analysis of requested units for SO2 July 17, 2020 Domtar DAQ control

May 4, 2020

Everick Spence Mill Manager Domtar Paper Company, LLC PO Box 747 NC Highway 149 North Plymouth, NC 27962

Subject: Regional Haze Reasonable Progress Assessment for Second Planning Period

Dear Mr. Spence:

The North Carolina Division of Air Quality (DAQ) is preparing the North Carolina Regional Haze State Implementation Plan (SIP) for the second planning period (2018 – 2028). The DAQ has worked with the Visibility Improvement State and Tribal Association of the Southeast (VISTAS), of which North Carolina is a member, to identify emission source sectors and facilities that significantly impact visibility impairment in Class I Federal areas within and outside of North Carolina consistent with the regional haze statutory and regulatory requirements and Environmental Protection Agency (EPA) guidance. Based on analyses conducted by North Carolina and VISTAS, sulfur dioxide (SO2) emissions from Domtar Paper Company (Domtar) in Plymouth, North Carolina have been shown to contribute ≥1% to visibility impairment at the Swanquarter .

I am requesting that Domtar review the projected 2028 SO2 emissions upon which the DAQ’s contribution assessment is based, and either confirm or revise the 2028 emissions for the DAQ to review and determine if it will be necessary for Domtar to complete a four-factor analysis of its major SO2 sources. We request that you complete this review and report your conclusions with documentation of any revised emissions to the DAQ by May 15, 2020. The DAQ will review your submittal and notify you by May 22, 2020, if it is necessary for Domtar to complete a four-factor analysis of its major SO2 sources.

Part I of this letter provides background on the regional haze program requirements. Part II explains the process that VISTAS followed to identify facilities such as Domtar for additional analyses. Part II also includes a summary of SO2 emissions for your facility for your review. Part III explains how to proceed with a four-factor analysis of the major SO2 sources at Domtar, if needed.

Please submit all items requested in this letter to the DAQ Planning Section Chief, Randy Strait ([email protected]), within the dates specified. Should you have any questions regarding this request, please feel free to contact me at (919) 707-8447 or Randy Strait at (919) 707-8721.

Mr. Spence May 4, 2020 Page 3 of 8

Part I. Overview of the Regional Haze Program

In Section 169A of the 1977 Amendments to the Clean Air Act (CAA), Congress set forth a program for protecting visibility in Federal Class I areas which calls for the "prevention of any future, and the remedying of any existing, impairment of visibility in mandatory Class I Federal areas which impairment results from manmade air pollution." In the 1990 Amendments to the CAA, Congress added section 169B and called on the United States Environmental Protection Agency (EPA) to issue regional haze rules. The Regional Haze Rule (RHR) that EPA promulgated on July 1, 1999 (64 FR 35713) revised the existing visibility rule to integrate provisions addressing regional haze impairment and establish a comprehensive visibility protection program for each Class I Federal area that provides for reasonable progress towards achieving natural visibility conditions by 2064.

The regional haze rules are codified at 40 Code of Federal Regulations (CFR) 51.300. Paragraph 40 CFR 51.308(f) (Regional Haze Program Requirements) requires each state to “address regional haze in each mandatory Class I Federal area located within the State and in each mandatory Class I Federal area located outside the State that may be affected by emissions from within the State.” The State of North Carolina submitted its regional haze plan for the first planning period (2008 – 2018) to EPA on December 1 17, 2007.0F The North Carolina Division of Air Quality (DAQ) is now preparing the States regional haze plan for the second planning period (2018 – 2028).

The EPA finalized revisions to the RHR in January 2017 (82 FR 3078) to strengthen, streamline, and clarify certain aspects of the agency’s regional haze program. Paragraph 40 CFR 51.308(f) of the RHR requires that states must submit a regional haze plan for the second planning period by July 31, 2021. As part of the plan revision, the State of North Carolina must establish a reasonable progress goal (expressed in deciviews) that provides for reasonable progress towards achieving natural visibility conditions by 2064 in the Swanquarter National Wildlife Refuge. The goal “must provide for an improvement in visibility for the most impaired days over the period of the implementation plan and ensure no degradation in visibility for the clearest days over the same period.”

The State of North Carolina must also submit a long-term strategy that addresses regional haze visibility impairment for Swanquarter National Wildlife Refuge. The long-term strategy must include enforceable emissions limitations, compliance schedules, and other measures as necessary to achieve the reasonable progress goal established for the Swanquarter National Wildlife Refuge.

In establishing reasonable progress goals, the State must consider the four factors specified in section 169A of the CAA and in paragraph 51.308(f)(2)(i) of the RHR: (1) the cost of compliance, (2) the time necessary for compliance, (3) the energy and non-air quality environmental impacts of compliance, and (4) the remaining useful life of any potentially affected sources.

On August 20, 2019, EPA issued “Guidance on Regional Haze State Implementation Plans for the Second 2 Implementation Period.”1F Among other things, this document provides guidance to states on the selection of sources for analysis, characterization of factors for emission control measures, and decisions on what control measures are necessary to make reasonable progress.

1 North Carolina’s Round 1 SIP submittals and EPA approval of those submittals is provided on the DAQ’s website at: https://deq.nc.gov/about/divisions/air-quality/air-quality-planning/state-implementation-plans/regional-haze- state-sip. 2 The guidance document is available on EPA’s website at: https://www.epa.gov/sites/production/files/2019- 08/documents/8-20-2019_-_regional_haze_guidance_final_guidance.pdf.

Mr. Spence May 4, 2020 Page 4 of 8

Part II. Reasonable Progress Assessment

The DAQ has recently completed the reasonable progress assessment for its second Regional Haze SIP. The following explains the DAQ’s process for conducting its reasonable progress assessment for the current planning period from 2018 through 2028.

Step l: Determine pollutants of concern.

Using 2013 through 2017 Interagency Monitoring of Protected Visual Environments (IMPROVE) monitoring data for Class I Federal areas in the VISTAS states, VISTAS evaluated the species contribution on the 20% most impaired visibility days and concluded that sulfate accounted for greater than 70% of the visibility impairing pollution associated with anthropogenic emission sources. The VISTAS states concluded that controlling sulfur dioxide (SO2) emissions was the appropriate step in addressing the reasonable progress assessment for 2028.

Step 2: Determine which source sectors should be evaluated for reasonable progress.

For the 10 VISTAS states, point source SO2 emissions in 2028 are projected to represent over 80% of the total SO2 emissions inventory for all sectors. Therefore, the VISTAS states concluded that the focus should be on electricity generating unit (EGU) and non-EGU point sources of SO2 emissions.

Step 3: Determine which facilities would be evaluated based on impact.

VISTAS initially utilized an Area of Influence (AoI) analysis to help identify the areas and sources most likely contributing to poor visibility in Class I Federal areas. This AoI analysis involved running a backward trajectory model to determine the origin of the air parcels affecting visibility in each Class I Federal area. This information was then spatially combined with emissions data to determine the pollutants, sectors, and individual sources that were most likely contributing to the visibility impairment at each Class I Federal area. North Carolina first used this information to determine that the pollutant and sector with the largest impact on visibility impairment was SO2 from point sources.

North Carolina then used the results of the AoI analysis for each Class I Federal area to identify sources to select for Particulate Matter Source Apportionment Technology (PSAT) modeling. Point source facilities with an AoI contribution of ≥3% for sulfate and nitrate combined were selected for PSAT modeling (Domtar’s contribution to Swanquarter was 3.3%). PSAT modeling uses “reactive tracers” to apportion particulate matter among different sources, source categories, and regions. PSAT was implemented with the Comprehensive Air Quality Model with extensions (CAMx) photochemical-grid model to determine visibility impairment due to individual facilities. Use of PSAT modeling is a superior approach to the AoI analyses for determining individual facility contributions to visibility impairment in Class I Federal areas. North Carolina identified facilities with an impact on one or more Class I Federal areas with ≥1% of the total visibility impairment associated with SO2 on the 20% most impaired days for each Class I Federal area. These sources are being considered for additional reasonable progress analyses.

Based on analyses conducted by North Carolina and VISTAS, SO2 emissions from Domtar Paper Company in Plymouth, North Carolina have been shown to contribute 1% to visibility impairment at the Swanquarter National Wildlife Refuge.

Mr. Spence May 4, 2020 Page 5 of 8

Step 4: Evaluate 2028 emissions.

For the 2028 modeling analysis, the DAQ projected 2028 non-EGU point source emissions from EPA’s 2016 modeling platform that includes emissions that North Carolina facilities submitted to the DAQ. The DAQ projected 2028 SO2 emissions to be about 687 tons for Domtar by applying growth and control factors to 2016-year emissions. For each SO2 emission unit at Domtar, Table 1 shows historical emissions for 2016-2018, projected 2028 emissions, and the growth and control factors applied to 2016 emissions to estimate 2028 emissions. Table 2 provides a cross-reference between Group and Permit IDs for the SO2 emission units in Table 1. Please review the 2028 projected emissions and notify the DAQ if these estimates are reasonable or not. If you provide revised 2028 estimates, please explain the methodology and assumptions for the revised estimates. Please respond to this request by May 15, 2020.

If you can document controls or process modifications that have been implemented since 2016 (or will be implemented before 2028) that significantly lower the DAQ’s 2028 emission estimates for your facility, the DAQ will use the PSAT modeling results for your facility to determine if the revised emissions will significantly lower the contribution to visibility impairment at Swanquarter. Otherwise, the DAQ is requesting that you complete a four-factor analysis as outlined in Part III of this letter.

Part III. Evaluate the Four Factors

To meet the requirements of Section 51.308(d)(1)(i)(A) of the RHR, the DAQ must consider each of the four statutory factors for emission sources at your facility that are estimated to significantly contribute to visibility impairment in a Class I Federal area. The four factors include: 1) cost of compliance, 2) time necessary for compliance, 3) the energy and non-air quality environmental impacts of compliance, and 4) the remaining useful life of the emissions unit. If after completing Part II it is determined that a four factor analysis is necessary, the DAQ requests that you conduct a four-factor analysis on each of the hog fuel boilers (Nos. 1 and 2) at Domtar’s Plymouth facility. You should submit the requested four-factor analyses by no later than July 31, 2020.

EPA’s August 20, 2019, regional haze guidance explains how the four statutory factors can be characterized. To identify control measures with the highest level of control effectiveness that are both technically feasible and cost effective using the minimal amount of effort, the DAQ requests that the analyses be conducted using a “top-down” approach for each emission unit as follows:

Step 1: Identify all control technologies; Step 2: Eliminate technically infeasible options; Step 3: Rank remaining control technologies by control effectiveness; Step 4: Application of the four statutory factors (cost of compliance, time necessary for compliance, energy and non-air quality environmental impacts, remaining useful life of existing source) to control technologies identified in Step 3 and document the results; and Step 5: Select control technology and control effectiveness

Implementation of the methodology specified in EPA’s August 20, 2019, guidance using a top-down approach is provided in the following summary.

Mr. Spence May 4, 2020 Page 6 of 8

Table 1. Domtar – Plymouth (Facility ID 3711700069) Actual Sulfur Dioxide Emissions for 2016 – 2018 and Projected Emissions for 2028

Annual SO2 Emissions (Tons) Control Factor Growth Unit ID Unit Description 2016 2017 2018 2028 (%)1 Factor2 G-148 No. 2 Hog Fuel Boiler 526.28 555.74 635.15 505.23 4.0 1.00 G-143 No. 1 Hog Fuel Boiler 174.83 200.10 223.12 167.84 4.0 1.00 South smelt tank and salt G-225 6.05 5.77 4.93 6.52 1.078 cake mix tank G-158 No. 5 Recovery Boiler 6.51 0.89 6.72 6.51 1.00 Lime Kiln No. 5 and G-431 0.78 0.77 0.66 0.84 1.078 crusher Backup diesel and G-258 0.68 0.56 1.20 0.37 0.541 natural gas engines Spill collection tank and G-408 0.09 0.09 0.07 0.10 1.078 white liquor surge tank Material reuse handling of various by-product GR44 0.04 0.04 0.12 0.04 1.078 streams at the No. 3 landfill location Total 715.26 763.96 871.97 687.45 1 Control Factor: 4% reduction was applied to 2016 emissions to account for boiler tune-up required under Section 112 DDDDD Boiler Maximum Achievable Control Technology (MACT) rule effective for North Carolina sources on May 20, 2020. 2 Growth Factors (GF) were applied to 2016 emissions to estimate 2028 emissions: GF = 1.078: Average of the growth rates computed from projections of Paper industry employment and revenue for the southeast region (region that includes North Carolina); based on employment projections (available at 3-digit NAICS code level (322)) and revenue Projections (available at 4-digit NAICS code level (3221)). GF = 0.541: Projected change in distillate fuel oil consumption in the Paper industry (NAICS 322) for the southeast region. GF = 1.00: No growth assumption based on an analysis of 2010-2016 trend in wood/wood waste consumption (in million British thermal units) by Domtar (EIA plant ID 50189) as reported to EIA via Form-923.

Mr. Spence May 4, 2020 Page 7 of 8

Table 2. Domtar – Plymouth (Facility ID 3711700069) Cross-reference between Group and Permit IDs for SO2 Emission Units in Table 1

Unit ID Permit ID G-148 ES-65-25-0310 G-143 ES-64-25-0290 G-225 ES-10-08-0010, ES-14-05-0050, ES-14-05-0300 G-158 ES-10-25-0110 G-431 ES-14-60-3000, ES-14-60-3015 ES-14-60-3000a,ES-53-40-0130, ES-53-40-0140, ES-53-40-0145, ES-71-95-0500, ES-73- 05-4570, ES-73-05-4580, ES-14-60-3000a, ES-53-40-0130, ES-53-40-0140, ES-53-40- G-258 0145, ES-71-95-0500, ES-73-05-4570, ES-73-05-4580, ES-14-60-3000a, ES-53-40-0130, ES-53-40-0140, ES-53-40-0145, ES-71-95-0500, ES-73-05-4570, ES-73-05-4580 G-408 ES-08-65-1060, ES 08-70-0900 GR44 IES-KLime

Mr. Spence May 4, 2020 Page 8 of 8

Summary of 4-Factor Analysis Methodology Specified in EPA’s August 20, 2019, Guidance Using a Top-Down Approach

Determining which emission control measures to consider – You should first identify all technically feasible sulfur dioxide control measures for each source selected for four-factor analysis. You should then rank them in order of highest to lowest control effectiveness. The projected 2028 actual sulfur dioxide emissions from the source should be used as the baseline emission level for estimating control effectiveness of each control measure.

Characterizing the cost of compliance (statutory factor 1) – You should estimate the cost of compliance starting with the control measure with the highest level of control effectiveness. The cost of compliance should be in terms of cost/ton of sulfur dioxide reduced. The cost used as the numerator in the cost/ton metric should be the annualized cost of implementing the control measure and should be determined using methods consistent with United States Environmental Protection Agency’s (EPA) Air Pollution 3 Cost Control Manual.2F Should you use a method that deviates from the Cost Control Manual, you should include that methodology, including all calculations and assumptions, and you should justify why the method used is more appropriate than methods specified in the Cost Control Manual. The emission reduction used as the denominator for the cost/ton metric should be the annual tons of reduction from implementation of the control measure. If your analysis indicates that the control measure should be included as part of North Carolina’s long-term strategy for the second implementation period, further analysis is not necessary. If your analysis indicates that the control measure is not cost effective, you should estimate the cost of compliance for the control measure with the next highest level of control effectiveness. This process should be repeated until you have identified a control measure that should be included in North Carolina’s long-term strategy or until all control measures have been analyzed.

Characterizing the time necessary for compliance (statutory factor 2) – You should provide an estimate of the time needed to comply with the control measure(s) identified using statutory factor 1. You should specify the source-specific factors used to estimate the time to install the control measure and provide a justification as to why the estimated time is reasonable.

Characterizing energy and non-air environmental impacts (statutory factor 3) – The cost of the direct energy consumption of the control measure should be specified and included in the cost of compliance analysis. If there are any non-air environmental impacts associated with a control measure, such as impacts on nearby water bodies, those impacts should be specified.

Characterizing remaining useful life of the source (statutory factor 4) – The length of the remaining useful life of a source is the number of years prior to the shutdown date during which the new emission control would be operating. If the remaining useful life of the source is less than the useful life of the control system being analyzed, then you should use the remaining useful life of the source in determining the annualized cost in the cost of compliance analysis. Otherwise, you should use the useful life of the control measure in the cost of compliance analysis. If the remaining useful life of a source is relied upon in in a four-factor analysis of a control measure instead of the useful life of the control system, and that control system becomes part of the state’s long-term strategy, the shutdown date for the source will need to be included in the Regional Haze SIP and be made federally enforceable.

3 https://www.epa.gov/economic-and-cost-analysis-air-pollution-regulations/cost-reports-and-guidance-air- pollution#cost manual.

(y Domtar Paper ~ Company. LLC Plymouth Mill Domtar P.O. Box 747 Highway 149 North Plymouth, NC 27962 Tel: (2S2) 793-8111

May 12, 2020

Mr. Randy Strait Certified .Mai/ Planning Section Chief Re.turnReceipt Requested NC Department of Environmental Quality Division of Air Quality 1641 Mail Service Center Raleigh, NC 27699- I64 I

Re: Review of Projected 2028 Emissions for Regional Haze Analysis Domtar Paper Company, LLC Mill in Plymouth, NC Permit No. 04291T47/Facility ID 07/59/00069

Dear Mr. Strait:

On May 4, 2020, Domtar Paper Company, LLC - Plymouth Mill (Domtar or Mill) received a letter from the North Carolina Division of Air Quality (DAQ) requesting that Domtar review the projected 2028 Sulfur Dioxide (SOi) emissions upon which the DAQ's contribution assessment was based for the Regional Haze Second Planning Period. Domtar reviewed the projected 2028 SOi emissions presented in Table I of DAQ's request and is providing an update as described below and in Attachment I.

On August 15. 2018, DAQ issued Pennit No. 04291T45 authorizing the Mill Optimization Project that is intended to improve efficiency and streamline operations. The project includes installation of a Thennal Oxidizer (TOx) as a backup control device for High Volwne, Low Concentration (HVLC) pulp mill gases as use of No. I Hog Fuel Boiler (HFB!) is phased out. The TOx started up in July of 2019 and the HFBI will be pennanently shut down prior to 2028. Table 1 has been updated to include SO2 emissions from combusting HVLC gases in the TOx and to remove future emissions from the HFB I. SO2 emissions as a result of firing HVLC gases in the TOx are calculated based on sampling of the HVLC header conducted in 2014, assuming 100% conversion of sulfur compounds to SO2. and actual pulp production data during use of the TOx.

The bulk of the SO2 emissions from No. 2 Hog Fuel Boiler (HFB2) are from combustion of pulp mill non-condensable gas (NCG) because the main fuel fired in HFB2 is biomass. In December 2019, Domtar conducted emissions testing for multiple pulp mill NCG firing scenarios in HFB2 to obtain updated emissions factors representing the current configuration of the Mill. Domtar performed follow-up testing in March 2020 and May 2020 to gather additional data. For reporting year 2019, Domtar is updating the S02 emissions calculation methodology when firing NCG's in HFB2 to more accurately calculate emissions.

Domtar is providing an update to the 2028 SO2 emissions projection using 20 I 9 as a more representative base year (in place of 2016) to reflect the Optimization Project and the recent HFB2 SO2 test data. The attachment includes an update to Table I provided by DAQ. Table 2 of the attachment includes the basis of the 2028 emissions estimates for the hog fuel boilers and thermal oxidizer. The growth factors provided by DAQ were applied to 2019 emissions in order to project 2028 emissions, excluding use of the 4% control factor for boiler tune-ups because the tune-up has already been performed.

Should the DAQ have any questions concerning Domtar's update to the 2028 SOi emissions projection, please contact Don Wynne by phone at (252} 793-8984 or by email at [email protected] or Claire Corta by phone at (919) 578-4195 or by email at [email protected].

Sincerely, ~R.:JI~~ Diane R. Hardison EH&S Manager

Everick W. ence Mill Manager cc: Don Wynne • Domtar Claire Corta - ALL4 Betsy Huddleston - NC DAQ· WaRO

Attachment 1 - Update to 2028 Emissions Projection

Page2 Attachment 1 Update to 2028 Emissions Projedion Table l. Domtar· Plymoutb (Facility ID 3711700069) Actual Sulfur Dioxide Emissioos for1016·2019 and Frojtcttd E.missioas for2028

Annual so, Emi11iem (Tons) c.... 1ro1 Grewtll F1t10r Unit ID Ullit Descrlntlon 2Glfi 2817 2018 2019' 2828 1%11 Faetor' G,.148 No. 2 Ho• Fuel Boiler 526.28 55S.74 63S.lS 877.87 1009.57 0.0 1.0' G,.143 No. I Ho• Fuel Boiler 174.83 200.10 223.12 58.22 0.00 0.0 o.o, mx Thermal Oxidizer NIA NIA NIA SS.81 85.96 1.0' Smelt Oi300lving Tanks and G-225 salt cake mix tank 6.05 S.11 4.93 5.08 5.47 1.078 G,.ISS No. S RecoveryBoiler 6.51 6.89' 6.72 S.91 5.91 1.00 G,.431 Lime Kiln No.Sand Crusher 0.78 0.77 0.66 o.ss 0.63 1.078 Backup diesel and G-258 natural gas engines 0.68 0.56 1.20 1.22 0.66 0.541 Spill collection tank and "'-408 white liquor surge tank 0.09 0.09 0.07 0.07 0.08 1.078 Material reuse handling of various by-product streams at the No. 3 landfill location "'R44 0.04 0.04 0.12 0.12 0.13 1.078 Total Emi11ions: 715.26 763.117 871,!)7 1834,11'7 1108,41 l) Control Fa,:tor: Removoo4% e-0n1rolfa«or sintill8'e fuel oil 0011surnpsions from the No. 5 Recovery Boile, G,oupG-158 from 0.89 to 6.89. 4) Draft 2019 Emis$iOn$to b, sobmittcdto NC DAQwith !ht reponin$ year 2019 oiremissions invontocydue lune 30, 2020. Ttbk: 2. J)QNU.t' • Pl)'«no111• (Facilry m 3111100069) Z(r.2::8: Sulrur Dlo'lidt Eraistslioas from N'o. 1 aod l Hag Fud Boiffl ind HVL<: ntemal ()Jjdh:cr'

Emluion1 FllclD'r m8'°2!milllua, T•nu11h.... I/Bibo .. ~ Val& II) Unit • -...:; ... Seed•rio t' Th,...""•a1Unllo &nl11ID111 Fadelr ,...., -14S No. 2 H- Fllel Boiler I LVHCJSOG + Fud S8.384 ODTUB!>M 7.48 ll>'OmUBJ> 218.36 -148 Wo. 2 H....,, Fuel Boik::f -2 LVHC/SOO + FUH 4WLS Offiint) 6,1)1 OD'l"UBJ>~•• &91 ll>'ODTIJBJ> 30.01 -)48 N'o. 2 ff,.. fuel 0oiltt 3 HVLC-tFuel ◄ IS.166 oorusp/... c 3.66 lbiODTUBP 760.SS •148 No. 2 H= Fllel Boiler • H- Fud aod NflW"l.l Gas ,....,o NCG'I 431.519 MMB1u/•r l.63E.03 lb/MMBto O.lS ·10 N'o. I HM' Fuel Boiic.- 7 Shut Down 0 OD'I\IBl'l•r 3.66 lb.'◊DTUBJ> 0.00 Ox Thmna.l O:cidilX:J' s Nt1..wl 0~ n..io NOO'I IS MMSCF,.,,. 0.6 lb/MMSCF 4.SSs.>3 Ox ThcmuJ O;,cidi.z.er 6 HVl..C end N&lunl C<> 34,723 ODTUBP/vr 4.95 lb,'OOTUBP SS.96 I) ~iOM &ti« foi:n }.~b 2020 stae\ tiut .,,i.nw.,gq fut:l c.11Nn.l s;u.. acd l.VHCISOO. 2) E:ris.siom. &c!Of 6'ocn May '2.020 IIUd: ~t ""'~ firillf, ~ fG.cL ~ z-. aol LVHCISOO .,.jd\ .,,~10 li4.a tctu'eibct y 6rt4 01 O'lec No. 2 Hog Fuel 0oik:r&Od ink Thermal C));:i,d.o,.CT-. \.td:op. &:igi,-nr.g WI 201~. HYLC ge.sosw, t» l~bd ban:itd ilt N

(This page intentionally left blank) ROY COOPER Governor MICHAEL S. REGAN Secretary MICHAEL ABRACZINSKAS Director NORTH CAROLINA Environmental Quality

May22,2020

Everick Spence Mill Manager Domtar Paper Company, LLC PO Box 747 NC Highway 149 North Plymouth, NC 27962

Subject: Regional Haze Reasonable Progress Assessment for Second Planning Period

Dear Mr. Spence:

Thank you for your letter dated May 12, 2020, responding to my May 4, 2020 letter. I appreciate you

reviewing the North Carolina Division of Air Quality's (DAQ) projected 2028 sulfur dioxide (SO2) emissions for the Domtar Paper Company (Domtar) in Plymouth, North Carolina and providing revised 2028 emissions for the nine SO 2 emission units at the facility. As noted in your letter, Domtar developed SO2 emissions for 2019 based on the Mill's Optimization Project that is intended to improve efficiency and streamline operations as authorized under Permit No. 04291 T45 issued by the DAQ on August 15 , 2018. Domtar then projected 2019 emissions to 2028 using the growth factors applied by DAQ in

developing the initial 2028 SO2 emission estimates that you reviewed. Relative to the DAQ's original 2028 emissions projections, the revised emissions provided in your letter increased SO2 emissions by 61.2% (420.96 tons) with the majority of the emissions associated with the No. 2 Hog Fuel Boiler and Thermal Oxidizer.

The DAQ used the revised 2028 SO2 emissions you provided and recalculated Domtar's contribution to visibility impairment for the 20% most impaired days at Swan quarter National Wildlife Refuge using the PSAT modeling approach referenced in my May 4, 2020 letter. The revised PSAT results indicate that Domtar' s contribution would increase from 1. 00% to 1.61 % in 2028.

In establishing reasonable progress goals, the North Carolina must consider the four factors specified in section 169A of the Clean Air Act and in paragraph 51.308(f)(2)(i) of the regional haze rule: (1) the cost of compliance, (2) the time necessary for compliance, (3) the energy and non-air quality environmental impacts of compliance, and (4) the remaining useful life of any potentially affected sources. To fulfill this requirement, North Carolina is requesting that facilities that have 2': 1.00% sulfate contribution to visibility impairment at a Class I Federal area to complete a four-factor analysis. For this reason, I am

requesting that you conduct a four-factor analysis on the SO2 emission sources at Domtar's Plymouth facility as outlined in Part III of my May 4, 2020 letter.

Please submit the requested four-factor analyses to the DAQ Planning Section Chief, Randy Strait ([email protected]) by no later than July 31, 2020. Should you have any questions regarding this request, please feel free to contact me at (919) 707-8447 or Randy Strait at (919) 707-8721.

North Carolina Department of Environmental Quality I Division of Air Quality 217 West Jones Street I 1641 Mail Service Center I Raleigh, North Carolina 27699-1641 ~~~~~ 919.707.8400 Mr. Spence May 22, 2020 Page 2 of 2

Sincerely,

Michael A. Abraczinskas, Director Division of Air Quality, NCDEQ

MAA/rps

cc: Robert Bright, NCDAQ Betsy Huddleston, NCDAQ Tammy Manning, NCDAQ Randy Strait, NCDAQ Central Files Domtar Paper 'Y Company, LLC ~ Domtar Plymouth Mill P.O. Box 747 Highway 149 North Plymouth, NC 27962 Tel: (252) 793-8111

July 17, 2020

Mr. Randy Strait Planning Section Chief NC Department of Environmental Quality Division of Air Quality 1641 Mail Service Center Raleigh, NC 27699-1641

Re: Regional Haze Rule Four-Factor Analysis Domtar Paper Company, LLC Mill in Plymouth, NC Permit No. 04291T47/Facility ID 07/59/00069

Dear Mr. Strait:

On May 4, 2020, Domtar Paper Company, LLC - Plymouth Mill (Domtar or Mill) received a letter from the North Carolina Division of Air Quality (DAQ) requesting that Domtar review the projected 2028 Sulfur Dioxide (SO2) emissions upon which the DAQ's contribution assessment was based for the Regional Haze Second Planning Period. Domtar reviewed the projected 2028 SO2 emissions and provided DAQ with an updated 2028 emissions projection on May 12, 2020 using 2019 as a more representative base year (in place of 2016) to reflect the Optimization Project and the recent No. 2 Hog Fuel Boiler SO2 test data.

On May 22, 2020, Domtar received a letter from the DAQ requesting that the Mill conduct a four-factor analysis for the SO2 emission sources outlined in Part III of the May 4, 2020 letter (Nos. I and 2 Hog Fuel Boilers). Please find enclosed the requested Regional Haze Rule Four-Factor Analysis. Based on the enclosed analysis, no additional SO2 emissions controls were determined to be cost effective for the Mill's hog fuel boilers. Page2

Should the DAQ have any questions on Domtar•s Four-Factor Analysis. please contact Don Wynne by phone at (252) 793-8984 or by email at [email protected] or Claire Corta by phone at (919) 578-4195 or by email at [email protected].

Sincerely,

Diane R. Hardison EH&S Manager [Xi~)t-- Everick W. Spence Mill Manager

cc: Don Wynne - Domtar Claire Carta - ALL4 Betsy Huddleston - NC DAQ- WaRO

Enclosure REGIONAL HAZE RULE FOUR-FACTOR ANALYSIS FOR THE DOMTAR PAPER COMPANY PLYMOUTH IVIILL

JULY 2020

Submitted by: Submitted to: 0 ~ Domtar

Domtar Paper Company - Plymouth Mill NC Department of Environmental Quality P.O. Box 747 Division of Air Quality Highway 149 North 1641 Mail Service Center Plymouth, NC 27962 Raleigh, North Carolina 27699-1641 TABLE OF CONTENTS Section Name Page Number

1. INTRODUCTION...... 1-1 1.1 FOUR-FACTOR ANALYSIS ...... 1-3 1.2 SUMMARY OF SOURCES EVALUATED ...... 1-4 1.3 SUMMARY OF RECENT EMISSIONS REDUCTIONS ...... 1-5 1.4 DOCUMENT ORGANIZATION ...... 1-5 2. FOUR-FACTOR ANALYSIS FOR BOILERS ...... 2-1 2.1 AVAILABLE CONTROL TECHNOLOGIES ...... 2-1 2.1.1 Available S02 Control Technologies ...... 2-2 2.2 ELIMINATION OF TECHNICALLY INFEASIBLE OPTIONS ...... 2-4 2.3 COST OF TECHNICALLY FEASIBLE CONTROL TECHNOLOGIES ...... 2-4 2.3.1 Site-Specific Factors Limiting Implementation ...... 2-6 2.3 .2 S02 Economic Impacts - Wet Scrubber ...... 2-6 2.3 .3 S02 Economic Impacts - OSI...... 2-7 2.3.4 Energy and Non-Air Related Impacts ...... 2-8 2.4 TIME NECESSARY FOR COMPLIANCE ...... 2-8 2.5 REMAINING USEFUL LIFE OF EXISTING SOURCES ...... 2-9 2.6 CONCLUSION ...... 2-9 3. SUMMARY OF FINDINGS ...... 3-1 LIST OF TABLES

Table 1-1 Summary of Emissions Sources Evaluated ...... 1-4 Table 2-1 Control Technology Summary ...... 2-2 Table 2-2 Wet Scrubber Cost Summary ...... 2-7 Table 2-3 Trona Injection System Cost Summary ...... 2-8

ii LIST OF APPENDICES

Appendix A - Control Cost Estimates Appendix B - Supporting lnfonnation

iii Domtar Pupcr Company Four-Factor Anal) sis

1. INTRODUCTION

The North Carolina Department of Environmental Quality (DEQ) Division of Air Quality (DAQ) is in the process of developing a State Implementation Plan (SIP) revision for the second planning period under the 1999 Regional Haze Rule (RHR) at 40 CFR Part 51, Subpart P. The RHR focuses on improving visibility in federal Class I areas by reducing emissions of visibility impairing pollutants. DAQ is required to update the SIP by July 2021 to address further controls that could be applied to reduce emissions of visibility impairing pollutants, such as sulfur dioxide (SO2), for the 2021-2028 period. DAQ has requested that several facilities within the State submit a Four­ Factor Analysis (FF A) to examine the feasibility of additional SO2 emissions controls. This report provides the Domtar Paper Company's (Domtar's) FFA for SO2 emissions from the following units at the Plymouth, NC Mill, as requested in Part Ill of DAQ's May 4, 2020 letter:

• No. I Hog Fuel Boiler

• No. 2 Hog Fuel Boiler

The U.S. EPA developed the RHR to meet the Clean Air Act (CAA) requirements for the protection of visibility in 156 scenic areas across the United States. The first stage of the RHR required that certain types of existing stationary sources of air pollutants evaluate Best Available Retrofit Technology (BART). Specifically, the BART provisions required states to conduct an evaluation of existing, older stationary sources that pre-dated the 1977 CAA Amendments and, therefore, were not originally subject to the New Source Performance Standards (NSPS) at 40 CFR Part 60. The purpose of the program was to identify older emission units that contributed to haze at Class I areas that could be retrofitted with emissions control technology to reduce emissions and improve visibility in these areas. The BART requirement applied to emission units that fit all three of the following criteria:

l. The units came into existence between August 7, 1962 and August 7, 1977; 2. The units are located at facilities in one of26 NSPS categories; and

1-1 Domtar Pnpcr Compnn:v r-our- Factor Anal) sis

3. The units have a total potential-to-emit (PTE) of at least 250 tpy ofNOx, S02, and PM1 0 from all BART-era emission units at the same facility.

MACT standards that limit visibility-impairing pollutants were determined to meet the requirements for BART unless there were new cost-effective control technologies available. Per Section IV of 40 CFR Part 51, Appendix Y, Guidelines for BART Determinations under the Regional Haze Rules: " Unless there are new technologies subsequent to the MACT standards which would lead to cost-effective increases in the level of control, [state agencies] may rely on the MACT standards for purposes of BART." Sources demonstrating compliance with MACT and BART are already well controlled. If sources are already well-control led and not significantly contributing to visibility impacts at nearby Class I areas, further control should not be required to reduce emissions for the second planning period of the RHR.

In accordance with the August 2019 Guidance on Regional Haze State Implementation Plans for the Section Implementation Period, "there is no specified outcome or amount of emission reduction or visibility improvement that is directed as the reasonable amount of progress for any Class I area." 1 The guidance states that it may be reasonable for a state not to select an effectively controlled source for further measures and provides several examples on pages 23-25, such as sources subject to recently reviewed or promulgated federal standards, sources that combust only natural gas, and sources that are already well-controlled. This report focuses on two of the most significant sources of S02 emissions at the Domtar Plymouth pulp and paper mill, as per DAQ's request, and does not evaluate other well-controlled sources. Appendix A presents the control cost calculations and Appendix B presents supporting information.

1 EPA-457/8-19-003, August 2019, "Guidance on Regional Haze State Implementation Plans for the Second Implementation Period."

1-2 Domtar Pupcr Company r-our-Factor Analysis

1.1 FOUR-FACTOR ANALYSIS

Pursuant to 40 CFR 5 I .308(f)(2)(i), DAQ has requested that the mill address the following four factors to determine if additional S02 emissions control measures are necessary to make reasonable progress toward natural visibility conditions at Class I areas:

• The cost of compliance

• Energy and non-air quality impacts of compliance • The time necessary for compliance

• Remaining useful life of existing affected sources

Domtar has addressed these factors for additional control options that could be applied to the hog fuel boilers at the mill using available site-specific data, capital costs of controls from U.S. EPA publications or previous analyses (either company-specific or for similar sources), and operating cost estimates using methodologies in the U.S. EPA Office of Air Quality Planning and Standards (OAQPS) Control Cost Manual and U.S. EPA fact sheets. The mill has not performed site-specific engineering analyses for this study but has used readily available information to determine if additional emissions controls may be feasible and cost effective. The emissions reduction expected for each control technology evaluated was based on a typical expected control efficiency and projected 2028 actual emissions. Evaluating cost effectiveness based on actual emissions provides a better representation of the true cost of each technology to the mill than an evaluation based on allowable emissions. ln addition, actual emissions are more representative of the 2021- 2028 planning period than potential emissions.

An interest rate of 4.75% and the typical values for equipment life shown in the OAQPS Cost Manual examples were used to calculate the capital recovery factor. A 4.75% interest rate represents the prime rate just prior to the COVID-19 pandemic and is representative because the prime rate has varied over the past two years from the current low of 3.25% to a high of 5.5% in December 2018. Labor, chemical, and utility costs are based on mill-specific values for 2020. Domtar P.ipcr Company Four-Factor Anal>::. is

1.2 SUMMARY OF SOURCES EVALUATED

Table 1-1 provides basic information regarding the sources that were evaluated in detail. The boilers evaluated in this report are already subject to regulation under several programs aimed at reducing emissions of conventional and hazardous air pollutants (HAPs) and are already well controlled. Industrial boilers are subject to National Emission Standards for Hazardous Air Pollutants (NESHAP), which require the use of Maximum Achievable Control Technology (MACT). While the MACT standards are intended to minimize HAP emissions, they also directly reduce acid gas emissions and promote good combustion practices. NSPS Subpart D contains emission limits for SO2. The fuels fired by the hog fuel boilers are low-sulfur fuels (natural gas, No. 2 fuel oil, and biomass). The majority of the historical SO2 emissions from these boilers result from combustion of pulp mill gases that contain sulfur compounds. These gases a.re combusted to meet the HAP emissions control requirements of 40 CFR 63, Subpart S. The alkaline nature of the bark fly ash provides some SO2 capture.

Table 1-1 Summary of Emissions Sources Evaluated

2019 Projected Emissions Major 2028 Unit Size, Year Pennltted Control Actual SOz MMBtulhr Installed Fuels Technology Regulatory Actual S02 Description Programs Emissions (tons) Emissions (tons) 1,021 (any combination Lignin, natural PM: of fuels) gas, biomass, No. I Hog Electroscrubbers NSPS Subpart D 835 (hog 1977 No. 2 fuel oil, Fuel Boiler' S02: Low-sulfur MACT 58.22 0 fuel with used oil, fuels and inherent Subpart DDDDD any other sludge bark scrubbing fuels) Lignin, natural PM: Electrostatic gas, biomass, No. 2 Hog precipitator (ESP) NSPS Subpart D 889 1982 Fuel Boiler2 No. 2 fuel oil, S02: Low-sulfur MACT 877.87 1,009.57 used oil, fuels and inherent Subpart DDDDD slud2e bark scrubbin2 1 The No. I Hog Fuel boiler is permitted to combust high-volume, low-concentration (HVLC) pulp mill gases but is no longer able to combust HVLC. This boiler will be pennanently shutdown during the 2021 -2028 planning period. 1 The No. 2 Hog Fuel boiler can also com bust HVLC and low-volume, high-concentration (L VHC) pulp mil I gases and stripper off-gases (SOG).

14 Domtur Pnpcr Company rour-ractor Anal) sis

1.3 SUMMARY OF RECENT EMISSIONS REDUCTIONS

Since 20 I 0, the mill has made emissions reductions for a variety of reasons. The mill is subject to the provisions of 40 CFR Part 63, Subpart DDDDD, NESHAP for Industrial Commercial, and Institutional Boilers and Process Heaters (NESHAP DDDDD or Boiler MACT). Boilers subject to NESHAP DDDDD were required to undergo a one-time energy assessment and are required to conduct tune-ups at a frequency specified by the rule. Compliance with these standards required changes to operating practices, including the use of clean fuels for startup. In addition, the Plymouth Mill improved the PM control device on No. 2 Hog Fuel Boiler and is reducing utilization of No. 1 Hog Fuel Boiler and its associated emissions by transitioning to firing primarily natural gas, with No. 2 fuel oil as backup, and discontinuing combustion of HVLC in this boiler.

1.4 DOCUMENT ORGANIZATION

The document is organized as follows: • Section I -Introduction: provides the purpose of the document and what emission units are included in the FFA.

• Section 2-Four-Factor Analysis for Boilers: provides the FF A for the boilers evaluated.

• Section 3 - Summary of Findings: presents a summary of the FF A.

• Appendix A - Control Cost Analyses

• Appendix B - Supporting Information

1-5 Domtar Paper Company Four-Factor Anni) sis

2. FOUR-FACTOR ANALYSIS FOR BOILERS

This section of the report presents the results of the FF A for S02 emissions from the two industrial boilers at the mill. To evaluate the cost of compliance portion of the FFA, Domtar performed the following steps:

• identify available control technologies, • eliminate technically infeasible options, and • evaluate cost effectiveness of remaining controls.

The time necessary for compliance, energy and non-air environmental impacts, and remaining useful life were also evaluated.

2.1 AVAILABLE CONTROL TECHNOLOGIES

Available control options are those air pollution control technologies or techniques (including lower-emitting processes and practices) that have the potential for practical application to the emissions unit and pollutant under evaluation, with a focus on technologies that have been demonstrated to achieve the highest levels of control for the pollutant in question, regardless of the source type on which the demonstration has occurred. The scope of potentially applicable control options for industrial boilers was determined based on a review of the RBLC database2 and knowledge of typical controls used on boilers in the pulp and paper industry. RBLC entries that are not representative of the type of emissions unit, or fuel being fired, were excluded from further consideration. Table 2-1 summarizes the potentially feasible control technologies for industrial boilers.

2 RACTIBACT/LAER Clearinghouse (RBLC) hllps /fwww epa.gov/catc/ractbactlaer-cleannghouse-rblc-basic-informauon

2-1 Domtar Paper Company Four- Factor Anal~ sis

Table 2-1 Control Technology Summary

Pollutant Controls on Industrial Boilers

Low-sulfur fuels S02 Wet scrubber Dry sorbent injection (DSI)

Technically feasible control technologies for industrial boilers were evaluated, taking into account current air pollution controls, fuels fired, and RBLC Database information. Fuel switching from biomass to I 00% natural gas was not evaluated because the purpose ofthis analysis is not to change the operation or design of the source or to evaluate alternative energy projects. The August 20, 2019 regional haze implementation guidance indicates that states may determine it is unreasonable to consider fuel use changes because they would be too fundamental to the operation and design of a source. EPA BACT guidance states that it is not reasonable to change the design of a source, such as by requiring conversion of a coal boiler to a gas turbine. 3 It is not reasonable as part of this analysis to convert an existing biomass boiler at a forest products mill to a natural gas-fired boiler because biomass boilers at forest products mills fire the biomass residuals from the mill processes as a readily available and relatively inexpensive source of fuel. In addition, the alkaline nature of bark fly ash serves to provide some S02 emissions capture.

2.1.1 Available S02 Control Technologies

Natural gas, No. 2 fuel oil, and biomass are considered low-sulfur fuels and are fired by the boilers included in this report. Natural gas and biomass combustion result in negligible S02 emissions. However, as mentioned above, the majority of the historical emissions from the hog fuel boilers (and the future actual S02 emissions from No. 2 Hog Fuel Boiler) are from combustion of HVLC, LVHC, and SOG that contain sulfur compounds that oxidize to S02. LVHC gases are treated by a white liquor scrubber for reduction of sulfur compounds prior to combustion in the No. 2 Hog

3 https://.,nrn.epa.gov/sites/production/files/2015-07/docum,mts/igccbact.pdf

2-2 Domtar Paper Company Four-Fnc1or Anal) sis

Fuel boiler, resulting in lower S02 emissions. The potentially feasible add-on control technologies for reducing emissions of S02 from industrial boilers are discussed in detail in this section.

Wet Scrubbers

In a wet scrubber, a liquid is used to remove pollutants from an exhaust stream. The removal of pollutants in the gaseous stream is done by absorption. Wet scrubbing involves a mass transfer operation in which one or more soluble components of an acid gas are dissolved in a liquid that has low volatility under process conditions. For S02 control, the absorption process is chemical­ based and uses an alkali solution (i.e., sodium hydroxide, sodium carbonate, sodium bicarbonate, calcium hydroxide, etc.) as a sorbent or reagent in combination with water. Removal efficiencies are affected by the chemistry ofthe absorbing solution as it reacts with the pollutant and the amount of gas to liquid contact and residence time. Wet scrubbers may take the form of a variety of different configurations, including packed columns, plate or tray columns, spray chambers, and venturi scrubbers.

Dry Sorbent Injection (DSI)

OSI accomplishes removal of acid gases by injecting a dry reagent (i.e., lime or trona) into the flue gas stream and prior to PM air pollution control equipment. A flue gas reaction takes place between the reagent and the acid gases, producing neutral salts that must be removed by the PM air pollution control equipment located downstream. The process is totally "dry," meaning it produces a dry disposal product and introduces the reagent as a dry powder. The benefits of this type of system include the elimination of liquid handling equipment requiring routine maintenance such as pumps, agitators, and atomizers. The drawbacks to using this type of system are the costs associated with the installation of a dry PM control device to collect the dry by-product, as well as ongoing operating costs to procure the sorbent material and dispose of additional dry waste. Dry sorbents can also prove challenging to maintain a very low moisture content and keep flowing. OSI systems are typically used to control S02, hydrochloric acid and other acid gases on coal-fired boilers. Domtar Pupcr Company Four-f'.1ctor Anal~sis

2.2 EL/MINA TION OF TECHNICALLY INFEASIBLE OPTIONS

An available control technique may be eliminated from further consideration if it is not technically feasible for the specific source under review. A demonstration of technical infeasibility must be documented and show, based on physical, chemical, or engineering principles, that technical reasons would preclude the successful use of the control option on the emissions unit under review. U.S. EPA generally considers a technology to be technically feasible if it has been demonstrated and operated successfully on the same or similar type of emissions unit under review or is available and applicable to the emissions unit type under review. If a technology has been operated on the same or similar type of emissions unit, it is presumed to be technically feasible. However, an available technology cannot be eliminated as infeasible simply because it has not been used on the same type of unit that is under review. If the technology has not been operated successfully on the type of unit under review, its lack of "availability" and ''applicability" to the particular unit type under review must be documented in order for the technology to be eliminated as technically infeasible.

The No. I Hog Fuel Boiler currently burns only natural gas and hog fuel, with low-sulfur No. 2 fuel oil as backup and is reducing hog fuel use. HVLC gases are no longer combusted and S02 emissions from No. I Hog Fuel Boiler are now very low. Additionally, the Mill plans to shut down No. I Hog Fuel Boiler during the 2021-2028 planning period. Therefore, there are no additional S02 controls beyond the current practice of combustion of low-sulfur fuels that are necessary to evaluate for this boiler.

Installing a wet scrubber following the No. 2 Hog Fuel Boiler ESP is considered technically feasible and was evaluated. Installing OSI in the form of trona injection prior to the No. 2 Hog Fuel Boiler ESP is also considered technically feasible and was evaluated.

2.3 COST OF TECHNICALLY FEASIBLE CONTROL TECHNOLOGIES

Cost analyses were developed where add-on controls were considered technically feasible. Budgetary estimates of capital and operating costs were determined and used to estimate the

2-4 Domtur Pupcr Company Four-l"actor Anal~ ~is annualized costs for each control technology considering existing equipment design and exhaust characteristics. A capital cost for each control measure evaluated was based on company-specific data, source-specific vendor cost estimates, or EPA cost spreadsheets. The cost effectiveness for each technically feasible control technology was calculated using the annualized capital and operating costs and the amount of pollutant expected to be removed based on the procedures presented in the latest version of the U.S. EPA OAQPS Control Cost Manual. Projected actual emissions and a typical expected control efficiency were used as the basis for emissions reductions.

Capital, operating, and total annual cost estimates for each feasible pollution control technique are presented in Appendix A. These are screening level cost estimates and are not based on detailed site-specific engineering studies.

Although DAQ has not indicated what additional controls they would consider cost effective, similar analyses performed by U.S. EPA and others were reviewed to get a general idea of the level above which additional controls on industrial boilers are not cost effective. For example, as part of the 20 I 6 CS APR update rule\ U.S. EPA performed an analysis to characterize whether there were non-electric generating unit (EGU) source groups with a substantial amount of available cost-effective NOx reductions achievable by the 2017 ozone season. They evaluated control costs for non-EGU point sources with NOx emissions greater than 25 tpy in 2017.5 U.S. EPA did not further examine control options above $3,400 per ton. This is consistent with the range U.S. EPA analyzed for EGUs in the proposed and final CSAPR rules and is also consistent with what the U.S. EPA has identified in previous transport rules as cost-effective, including the NOx SIP call. Notably, $3,400 per ton represents the $2,000 per ton value (in 1990 dollars) used in the NOx SIP call, adjusted to the 2011 dollars used throughout the CSAPR update proposal. Adjustments of costs were made using the Chemical Engineering Plant Cost Index (CEPCI) annual values for

~ 81 Fed. Reg. 74504 l Technical Support Document for the Cross-State Air Pollution Rule for the 2008 Ozone NAAQS, Docket ID EPA­ HQ-OAR-2015-0500, Assessment of Non-EGU NOx Emission Controls, Cost of Controls, and Time for Compliance, U.S. EPA, November 20 I 5. Domtar P.1pcr Com pan~ l·our•I a~1or :\nal~ :;is

1990 and 2011.) Note that industrial boilers were among the source categories that the very conservative U.S. EPA cost analysis determined were above $3,400/ton. In addition, the Western Regional Air Partnership (WRAP) Annex to the Grand Canyon Visibility Transport Report (June 1999) indicated that control costs greater than $3,000/ton were high. 6 The costs presented in this report were developed using conservative assumptions and are above these thresholds.

2.3.1 Site-Specific Factors Limiting Implementation

Currently known, site-specific factors that would limit the feasibility and increase the cost of installing additional controls include space constraints. A detailed engineering study for each of the controls evaluated in this report would be necessary before any additional controls were determined to be feasible or cost effective.

2.3.2 S02 Economic Impacts - Wet Scrubber

The wet scrubber capital cost is based on a cost estimate provided by LDX Solutions on June 15, 2020 and the fan upgrade cost is from H. Clay Moore & Associates Inc. The cost estimate was based on design conditions obtained from 2020 air emissions testing on No. 2 Hog Fuel Boiler and discussions with the Mill. Operating costs were estimated using the factors in the OAQPS Cost Manual, Section 5, Chapter I, operating data provided by LDX Solutions, and site-specific labor, chemical. and utility costs.

U.S . EPA indicates that a retrofit factor is appropriate when estimating the cost to install a control system on an existing facility, in order to address the unexpected magnitude of anticipated cost elements; the costs of unexpected delays; the cost of re-engineering and re-fabrication; and the cost of correcting design errors. A retrofit factor can be used to reflect additional difficulty associated with installing auxiliary equipment, special care in placing equipment, additional insulation and painting of piping and ductwork, additional site preparation, extra engineering or

6 https:/tw,\ w. wrapai r .org//forums/mtf/doc u ments/group reports/Tee hSupplS02Tech. htm

2-6 Domtar Pnpcr Company Four-f'actor Anal~ si s supervision during installation, and unanticipated delays that cause lost production costs. The manual states that at the study cost level, a retrofit factor of as much as 50 % is justified, and even at the detailed cost level, a retrofit factor is often added. A retrofit factor of 1.3 was applied to the total capital cost as the vendor cost estimate was conducted remotely, an engineering study has not been performed, and production will be lost due to an extended Mill outage that is required for scrubber installation.

Table 2-2 Wet Scrubber Cost Summary

Cost Emissions Unit Description Capital Cost ($) Annual Cost {$/yr) Effectiveness of Controls ($/Ton S02) No. 2 Hog Fuel Boiler $13,341,296 $4,106,120 $4,281

Installing a wet scrubber is not considered cost effective because the estimated capital cost is more than $13 million and the cost effectiveness value is over $4,000/ton of SO2 removed.

2.3.3 S02 Economic Impacts - DSI

The capital cost for a system to inject milled trona prior to the ESP on the No. 2 Hog Fuel Boiler was estimated using an April 2017 Sargent and Lundy report prepared under a U.S. EPA contract. 7 Site-specific labor, chemical, and utility costs were used to estimate the annual cost of operating the system. The Sargent and Lundy report indicates that 50% SO2 control can be achieved when injecting trona prior to an ESP without increasing PM emissions. Table 2-3 summarizes the estimated capital cost, annual cost, and cost effectiveness of implementing this control technology for the No. 2 Hog Fuel Boiler, based on operating data and the projected 2028 actual S02 emissions.

7 Sargent & Lundy LLC. 2017. Dry Sorbent Injection for SOilHCI Control Cost Development il,/ethodology, Project 13527-00 I, Eastern Research Group, Inc. Chicago, IL.

2-7 Domhir Paper Company Four-Factor Anal) sis

Table 2-3 Trona Injection System Cost Summary

Cost Effectiveness of Emissions Unit Description Capital Cost ($) Annual Cost ($/yr) Controls {$/Ton S02) No. 2 Hog Fuel Boiler $13,813,979 $11,647,397 $23,074

Installing trona injection is not considered cost effective because the estimated capital cost is more than $13 million and the cost effectiveness value is over $20,000/ton of SO2 removed.

2.3.4 Energy and Non-Air Related Impacts

This section describes the energy and non-air environmental impacts associated with each add-on control option evaluated.

Additional electricity and water would be needed to run a wet scrubber and additional fan power would be required overcome the additional pressure drop through the wet scrubber. Other environmental and energy impacts associated with operating a wet scrubber include generation and disposal of wastewater. Additional electricity would be needed to operate a DSl system and it would create additional solid waste.

2.4 TIME NECESSARY FOR COMPLIANCE

U.S. EPA allows three years plus an optional extra year for compliance with MACT standards that require facilities to install controls after the effective date of the final standard. Although our f FA shows there are no additional controls that would be feasible, if controls are ultimately required to meet RHR requirements, the Mill would need at least three years to implement them after final EPA approval of the RHR SIP. The Mill would need time to obtain corporate approvals for capital funding and would have to undergo substantial re-engineering (e.g., due to space constraints) to accommodate new controls. Design, procurement, installation, and shakedown of these projects would easily consume three years. The Mill would need to engage engineering consultants,

2-8 Domhtr Paper Complm~ Four-f"actor i\nal: !>iS equipment vendors, construction contractors, financial institutions, and other critical suppliers. The Mill would also need to execute air permit modifications, which are often time-consuming and have an indeterminate timeline and endpoint. Lead time would be needed to procure pollution control equipment even after it is designed and a contract is finalized, and installation of controls must be aligned with mill outage schedules that are difficult to move due to the interrelationships within corporate mill systems, the availability of contractors, and the like. The Mill would need to continue to operate as much as possible while retrofitting to meet any new requirements.

Extensive outages for retrofitting must be carefully planned. Only when all the critical prerequisites for the retrofit have been lined up (e.g., the engineering is complete and the control equipment is staged for immediate installation), can an owner afford to shut down a facility's equipment to install new controls. This takes planning and coordination both within the company, with the contractors, and with customers. The process to undertake a retrofitting project is complex.

2.5 REMAINING USEFUL LIFE OF EXISTING SOURCES

The No. I Hog Fuel boiler will be permanently retired during the 2021-2028 planning period. The No. 2 Hog Fuel Boiler has a remaining useful life of twenty years or more.

2. 6 CONCLUSION

Based on the FFA presented above, no additional S02 emissions controls were determined to be cost effective for the Mill's hog fuel boilers. Domtar Paper Company Four-Factor Anal) sis

3. SUMMARY OF FINDINGS

The emission sources at the Domtar Plymouth Mill evaluated in this report are already subject to various stringent emission limits. However, in response to a request from DAQ, Domtar evaluated whether additional emissions controls for S02 are feasible for the hog fuel boilers.

As part of the Ff A, the following information was reviewed: site-specific emissions and control information, industry- and site-specific cost data, publicly-available cost data, previous similar control evaluations, the U.S. EPA RBLC database, and U.S. EPA's OAQPS Control Cost Manual. The best information available in the time allotted to perform the analyses was used.

Our review of the best available information indicates that additional emissions controls for S02 are not feasible. Any determination that additional controls are feasible would need to be justified based on a more detailed evaluation that fully considers site-specific factors. rn addition, it is important to note the following points:

• The boilers included in the FF A are subject to Boiler MACT emission limits and work practices that became effective in 2020. The required tune ups serve to ensure good combustion practices (indirectly limiting emissions of all pollutants) and the boilers only start up on clean fuel. • U.S. EPA will continue the required process to evaluate acid gas control technology improvements for the industrial boiler source category with its upcoming periodic technology review for NESHAP Subpart DDDDD sources. • U.S . EPA determined in its CSAPR rulemaking that additional controls on non-EGU combustion units are not cost effective.

3-1 APPENDIX A­ CONTROL COST ESTIMATES T•bleA-1 Domtar Plymouth • No. 2 Hog Fuel Boller Caplt■I and Annual Coats Assoc:l ■ted with Wet Scnibbing

CAPITAL COSTS1" ANNUALIZED COSTS

COSTITEM COST FACTOR COST($) COST ITEM COST FACTOR RATE COSTl$1

Direct Costs Direct Annual Cosls Purch.sed Efl.Ularnenl !;;osts Oe!!,lliTl!I. ubor (a) A Equipmenl Cos1s • we1 scrubbe< $3,187,000 (b) Opera1or" 0.5 hours/shift $65.00 per h0t.r•1 $35,588 (a) lnstrumenlaijon $0 (b) Supervisor 15% of opera1or labor S5,338 (b) Sales Tax 0.03 A $95,610 Ma/nt.nance (b) Freight 0.05 A $159,350 (b) Mainlenance labor" 0.5 hOurslshift $65.00 per hour•• $35,588 B Total Purchased Equipment Cost $3,441,960 (b) Maintenance materials 100% of mainlenance labor $35,588 Ulilltiesf $19.238 (b) Piping 0.30 B $1,032,588 Total Direcl Annual Costs $2,241,505 (b) Insulation for ductwo(k 0.01 B $34,420 (b) Painting 0.01 B $34,420 Dlrecl lnstallalion Cost S2,925,U6 Indirect Annual Costs (a) Installed Cost for New Fan S:1,000,000 (b) Ovemead 60~ Labor and Material Costs $67.260 Total Direct Costs $9,367,626 (b) General and administrative 2~ olTCI $266,826 (b) Property tues 1'11, olTCi S133.413 Indirect Costs (bl Insurance , ,., ofTCI $133.413 (a) Engineefing so (bJ Capital recovery 0.095 xTCI $1,263.703 (b) Cons1tUCIJOl'I Managemenl o 10 B $344,196 LHe or the conlrol: 15 1111ars at 4,75,., in1erest (b) Cof11nlctor fees 0.10 B $344, 196 (b) Start-._., 0.01 B $34.420 Tot•/ Ind/reel Annual Costs $1,864,615 (b) Performance tesl 0.01 B S34.420 Re-cerlification of monitors In new (b) 0.01 B $34,420 locations (b) C~ngencies 0.03 B $103.259 Total Annual Costs U,106,120 Tot1tl Ind/reel Costs S,94,910

(h) Rel/Oflt Factor 0.3 $3,078,761 Cost Elr9cd-. {Jlton) SO, Com-ol Efficiency": 9511, Tolal Capital lnveslment (TCI) $13,341,296 SO, EmlsslonsCII: 1.009.6 tpy Total Anrull COS1slConlrolec SO, Emissions: Controlled so. Eminioos: 959.1 tons of ~ remowc1 anruallv u.n1 wi Wei a.crwbbt, equtpm.nt quote f,on, LOX Solutlion, (inclUOH scn.1bDer. s.lack instrumtntalion. and eng1nNlingJ. ln5taHed ran cost lrOm H. Clay Moore & A.5$0Q1ln (eslimatltd between $2,5 and$$ mlllon ror "ew l~n. installed). 2020.

._..Casi inlormalion KlinMiltd tined on the U.S. EPA OAQPS Conllol C05t Manual, Section S, Chapter 1, Oecembttr 1995. Added ■ lina item Jo, ~t of re-citrtifying the re-localed HOx CEMS and COMS. equar 10 ltle pedormanc. IHt line. 1c1 Based on 9,760 ope,Ht'IQ hou~ flU MiU •PKifie rain. ••1 Ulility cos1 rep,uents Iha etec1ricaJ consuq,tion (ICfubbet at ◄ 72 kW ,,om LOX Solutions ■nd the ineren• flN the H Clay Moor ■ & As,oaa1es Ian or 500 hpor 373 kW). chemical use, water co.,surnption. •nd wastewater disposal l)f a LOX Solulions wet scrubber 1ystffl'I. " 195 percent 1edudion wn quoted t,y LOX -.i Projected 2028 emillioons.

,,., U.S. EPA iN;llic:ates lhllt a ,-1rofit lactCN'i■ •ppropnate when eslimating Iha cosl lolm.lall• conllol s~tem on an •••s~ing lacility 1n ordtf to ~l'HS U'le u11t11~ttec:I magnitude of antiapaled cost elements. A ttlrcr11 factor or 1.lwas appied to 1he tolel capital cosl as the vendor cost eslim111 was conducted remolely. an enginNring sludy has not been performtcl... and production 'MIi bt lost due to an ertended ~U outage thal •s required for serubber iMlallation. Table A-2 Domtar Plymouth • No. 2 Hog Fuel Boller Capital and Annual Costs Associated with Milled Trona DSI System Prior to the ESP

Variable Desil!llation Units Value Cakulation 889 MM Btu/hr, assumes 30¾ efficiency to convert to equivalent UmtS1zc A MW 78 MW output Retrofit Factor B . I Gross Heat Rate C BtulkWh 37,944 Assumes 30% efficiency Fuel and pulp mill gases. projected 2028 emissions d1v1ded by SO! Rate (uncontrolled I D lblMMBtu O,S2 Iproiected 2028 fuel use rrvpe of Coal E . NA Particulate Camure F . ESP Sorbent G . MtlledTrona Per the Sargent and Lundy document, 50% reduction can be achieved Removal Target H .,. 50 w11hou1 an increase in PM emissions. Heat lnout J Btu/hr 8.89E+08 889 MMBtu/hr

NSR K 1.43 Milled Trona w l ESP • tf(H<40, 0 0270•H. 0,353e~(O 0280•HIJ

Sorbenl Feed Rate M tonlhr 2 66 Trona ~ (1 20t t•I0·' -06)•K•A•C•D Es111na1ed HCI Removal V o/. 9289 Milled or Unm1lled Trena wr ESP = 60 86•WO 108 1 Sorbenl Waste Rate N tM .'hr 2 14 Trona ~ (0 7387+0.0018S•H;KJ•M Ash in Bark - 0.05. Boiler Ash Removal • 0.2; HHV - 4600 Fly Ash Waste Rate p ton'hr 12 88

S01 Control Effidency: 50"/

2028 S01 Emissions: 1009.< Controlled SO, Emissions: 504.l

Capital Costs Dir«t Costs

BM (Base Module) $ s 10,963,475 M1lkd Trona 1flM>25, 8200oo•s•M, 8300000•B•(M··o 284H

Indirect Cosls Engineering & Constructton Management Al s s 1,096,348 10"·• BM Labor adjustment A2 s s 5-18,17-4 5°a BM Contractor profit and fees A3 s s 548.17-1 5~o8M Capital. engineering and construction ost subtotal CECC s s 13,156. 170 BM~Al - A2 •A3 Owner costs including all "home office" costs Bl s s 657,809 5°oCECC Total project cost w'out AFUOC TPC s s 13,813.979 Bl+CECC AFUDC (0 for

Additional adminisua1ive labor costs FOMA s s 9,428 O.OJ*(FOMO+O4°FOMM ) !Total fiud O&M Costs FOM s s 389,462 FOMO+FOMM+FOMA

Variable O&M Cosl Cost for Sorbent VOMR s s 3,618.598,9 M•R

Cost for wasle disposal thal includes bo1h sorbent & ny ash was1e not removed prior 10 sorbent injecuon VOMW $ s 6,001 ,503.5 (N .-P)•S Additional aux1hary power required VOMP s s 179 10 Q*T* IO"ton SO: [Total Variable O&M Cost \'OM s s 9,620,281.5 VOMR • VOMW+VOMP

lndirecl Annual Costs General and Administrative 2°~0 ofTCI s 276,280 Propeny Tax ,. . ofTCI s 138,140 Insurance 1% ofTCI s 138,140 Capnal Recovery 7.86°'o x TCI s 1.085,094 !Total Indirect Annual Costs s 1,637,654

Life of the Con1rol 20 years 4 75°·0 mleres1

Total Annual Costs s 11 ,647,397 Tolal Annual Costs/SO2 Emissions s 13,074

'"Cost informalion based on the Apnl 2017 "Dr, Sorbent lnJecllon for SO:-'HCI Control Cost Development Methodology" stud) b\' Sargent & Lundy for a milled Trana syslem APPENDIX B - SUPPORTING INFORMATION LOX Solutions Cost Estimate for the S02 Scrubber Lundberg'' Dustex'~ Geoenergy~ www.LDXsolutions.com L!>>tSOLUTIONS

June 15, 2020 Domtar Reference : P·W3063, Rev. 00 1375 NC·l49 Attention: Mr. Ken Hardison Plymouth, NC 27962 Subject: SOi Scrubber for Bo~~ Emission Control

Dear Mr. Hardison: LDX Solutions is pleased to provide the following budgetary proposal for one (1) wet scrubber system for the SOi emissions from the upstre,lm No. 2 hog fuel boiler at Oomtar's Plymouth, North Carolina facility. The design cooditions have been provided via January, March, and May 2020 emission test reports. Please review the 'Design Base' section of our proposal and confirm the assumed values. As noted, we have not received confirmation of HCI loading concentrations and have assumed a reference value from similar applications. Accurate HCI loading information will affect the blowdown and scrubber consumption rates. The scrubber system has been designed to achieve a 95% collection efficiency of SOi emissions or down to 20 ppmv11, whichever iS less stringent, using us EPA Method 6/6C. The reduction in emissions will drastically reduce the blue haze that is currently emitted from the existmg dry ESP exhaust stack. The scope includes a short sectiOI\ of quench duct into the main scrubber vessel body and a top-­ mounted exhaust stack. We have indudl'd all major components of the scrubber recycle system that will be required: tanks, PtJITl)S, and instrumentation. We have exduded structural steel, external piping, manual valves, and interconnecting ductwork from upstream equipment to the inlet of the quench duct. Additionally, the scrubber system is assumed use the available static in the upstream dry ESP ID fan. Pressure drop requirements are listed in our proposal but will need to be confirmed with the existing fan curves/fan supplier. Installation (mechaoical/demolitioo/electrical/civil aoo safety services) and freight have been excluded from our current supply. Plec1se let us know if you have any questions or comments. LDX Solutions appreciates the opportunity to present this proposal and look fOJWard to your favorable consideration. Sincerely,

Pete Rose LOX Solutions East Coast Regional sales Manager

Atlanta. CIIOfgla Bilbao, Spain sealtle, Washrng1on BUDGETARY PRICING ( + / • 150/o)

LDX Solutions offers the following budgetary pricing per the detailed scope of work as described within:

Description Price ( $ USO) Supply of scrubber equipment and ancillary recycle/flush systems ( excludes freight). Includes system engineering. $3,187,000 Construction supervision, on-site services, and training $125,000 Estimated equipment freight $128,000 Total $3,440,000 DESIGN BASE

The following information comprises the design conditions that were used to develop this proposal.

DRY ESP EXHAUST STREAM CONDITIONS

Row Rate 444,829 Aa=M

285,000 SCFM (wet)

Temperature 375 Of

Moisture 18.5 % volume

SC>i Loading ~ 225 ppmv"

515 lb/hr

PM Loading ~ 11.3 lb/hr

0.0057 9r/dscf

HCI Loading 35.5 lb/hr*

28 ppmVd*

EXPECTED SPRAY TOWER OUTLET CONDITIONS

Flow Rate 358,789 ACfM

311,599 SCFM (wet)

Temperature 150 Of

Moisture 25.5 % volume (saturated)

11.2 ppmvd

SOi Loading s 25.75 lb/hr (95% removal efficiency)

*Hd loading provided via June 12th email from Don Wynne, using worst case Ha loading (Jan-19 tl.0411 lb/MMBTU) and a boiler MCR of 889 MMBTU/hr. DESIGN BASE • CONTINUED

SPRAY TOWER REQUIREMENTS

Evaporation Rate 150.0 gpm

Blowdown Rate 66.5 gpm (At 3% solids by weight, maximum expected)

Make·up Rate (Evap. + Blowdown) 216.S gpm

Water Recirculation Rate 10,880 9pm (Includes blowdown)

Estimated Electrical Consumption 472 kW

Compressed Air 80 psig

Estimated NaOH Consumption 1.61 gal/min of 50% solution**

Make-Up Water Guidellnes

. Total Hardness < 10 mg/L . pH 7.0 • Chlorides < 10 ppm-tH TSS& TOS < 200 mg/L

• 'NaOH must be membrane grade with <75 ppm NaCl. Warning, diaphragm grade caustic cannot be used d ue to high concentration of NaCl.

1 ' 'Warning, chloride concentrations in the make-up water exceeding 10 mg/L can cause severe corrosion. Sargent & Lundy OSI Cost Methodolog'L 1PM Model - Updates to Cost and Perfonnance for APC Technologies

Dry Sorbent Injection for S02/HCl Control Cost Development Methodology

Final

April 2017

Project 13527-001 Eastern Research Group, Inc.

Prepared by

Sarge

55 East Monroe Street• Chicago. IL 60603 USA• 312-269-2000

Page I LEGAL NOTICE

This analysis ("Deliverable") was prepared by Sargent & L11ndy, LL C'. ("S&l"), expressly for the sole 11se ofEastern Research Group. Inc. ("Client") in accordance with the agreement between S&L and Client. This Delfrerabfe was prepared using the degree of skill and care ordinarily exercised by engineers practicing under similar circumstances. Client acknowledges: (/) S&L prepared this Deliverable subject to the particular scope limitations. budgetmJ' and time constraints, and business objectives of the Client: (2) it?formation and data provided by others may not have been independently verified by S&I.; ,md (1) the information and data contained in this Deliverable are time sensitive and changes in the data. applicable codes, standards. and acceptable engineering practices may invalidate the findings ofthis Deliverable. Any use or reliance upon this Deliverable hy third parties shall be at their sole risk

This work was funded by the US Environmental Protection Agency (EPA) through Eastern Research Group. Inc. (ERG) as a contractor cmd reviewed by ERG and EPA personnel.

Page 2 Sargent:& Lundy"'

1PM Model - Updates to Cost and Performance for Project No. 13527-001 APC Technologies April 2017 OSI Cost Methodology

Purpose of Cost Algorithms for the 1PM Model The primary purpose of the cost algorithms is to provide generic order-of-magnitude costs for various air quality control technologies that can be applied to the electric power generating industry on a system-wide basis, not on an individual unit basis. Cost algorithms developed for the 1PM model are based primarily on a statistical evaluation of cost data available from various industry publications as well as Sargent & Lundy's proprietary database and do not take into consideration site-specific cost issues. By necessity. the cost algorithms were designed to require minimal site-specific information and were based only on a limited number of inputs such as unit size, gross heat rate, baseline emissions, removal efficiency, fuel type, and a subjective retrofit factor.

The outputs from these equations represent the "average" costs associated with the ·'average" project scope for the subset of data utilized in preparing the equations. The 1PM cost equations do not account for site-specific factors that can significantly affect costs, such as flue gas volume and temperature, and do not address regional labor productivity, local workforce characteristics, local unemployment and labor availability, project complexity, local climate, and working conditions. In addition, the indirect capital costs included in the 1PM cost equations do not account for all project-related indirect costs, such as project contingency, that a facility would incur to install a retrofit control.

Technology Description Dry sorbent injection (DSI) is a viable technology for moderate SO2/HCl reduction on coal-fired boilers. Demonstrations and utility testing have shown SO2/HCI removals greater than 80% for systems using sodium-based sorbents. The most commonly used sodium-based sorbent is Trona. However, if the goal is only HCI removal, the amount of sorbent injection will be significantly lower. In this case, Trona may still be the most commonly used reagent, but hydrated lime also has been employed in some situations. Because ofTrona's high reactivity with SO2, when this sorbent is used, significant SO2 removal must occur before high levels of HCI removal can be achieved. Studies show, however, that hydrated lime is quite effective for HCI removal because the need for simultaneous SO2 removal is much reduced. In either case, actual testing must be carried out before the permanent DSI system for SO2 or HCI removal is designed.

The level of removal for Trona can vary from 0 to 90% depending on the Normalized Stoichiometric Ratio (NSR) and particulate capture device. NSR is defined as follows:

(moles ofNa injected)¼ (moles ofS02 in flue gas) (theoretical moles of Na required)

Page I Sargent; & Lundy•••

1PM Model - Updates to Cost and Performance for Project No. 13527-00 I APC Technologies April 2017 DSI Cost Methodology

The required injection rate for alkali sorbents can vary depending on the required removal efficiency, NSR, and particulate capture device. The costs for an S02 mitigation system are primarily dependent on sorbent feed rate. This rate is a function of NSR and the required S02 removal (the latter is set by the utility and is not a function of unit size). Therefore, the required S02 removal is determined by the user-specified S02 emission limit, and the cost estimation is based on sorbent feed rate and not unit size. Because HCI concentrations are low compared with S02 concentrations, any unused reagent for S02 removal is assumed to be used for HCI removal, resulting in a very small change in the NSR used for S02 removal when HCI removal is the main goal.

The sorbent solids can be collected in either an ESP or a baghouse. Baghouses generally achieve greater S02 removal efficiencies than ESPs because the presence of filter cake on the bags allows for a longer reaction time between the sorbent solids and the flue gas. Thus, for a given Trona removal efficiency, the NSR is reduced when a baghouse is used for particulate capture.

The dry-sorbent capture ability is also a function of particle surface area. To increase the particle surface area, the sorbent must be injected into a relatively hot flue gas. Heating the solids produces micropores on the particle surface, which greatly improve the sulfur capture ability. For Trona, the sorbent should be injected into flue gas at temperatures above 275°F to maximize the micropore structure. However, if the flue gas is too hot (greater than 800°F), the solids may sinter, reducing their surface area and thus lowering the S02 removal efficiency of the sorbent.

Another way to increase surface area is to mechanically reduce the particle size by grinding the sorbent. Typically, Trona is delivered unmilled. The ore is ground such that the unmilled product has an average particle size of approximately 30 µm. Commercial testing has shown that the reactivity of the Trona can be increased when the sorbent is ground to produce particles smaller than 30 µm. In the cost estimation methodology, the Trona is assumed to be delivered in the unmilled state only. To mill the Trona, in-line mills are continuously used during the Trona injection process. Therefore, the delivered cost of Trona will not change; only the reactivity of the sorbent and amount used change when Trona is milled.

Ultimately, the NSR required for a given removal is a function ofTrona particle size and particulate capture equipment. In the cost program, the user can choose either as­ delivered Trona (approximately 30 µm average size) or in-line milled Trona (approximately 15 µm average size) for injection. The average Trona particle size and the type of particulate removal equipment both contribute to the predicted Trona feed rate.

Page 2 Sargent: & Lundy"'

1PM Model - Updates to Cost and Performance for Project No. 13527-001 APC Technologies April 2017 DSI Cost Methodology

Establishment of the Cost Basis For wet or dry FOO systems, sulfur removal is generally specified at the maximum achievable level. With those systems, costs are primarily a function of plant size and target sulfur removal rate. However, OSI systems are quite different. The major cost for the OSI system is the sorbent itself. The sorbent feed rate is a function of sulfur generation rate, particulate collection device, and removal efficiency. To account for all of the variables, the capital cost was established based on a sorbent feed rate, which is calculated from user input variables. Cost data for several OSI systems were reviewed and a relationship was developed for the capital costs of the system on a sorbent feed-rate basis.

Methodology Inputs Several input variables are required in order to predict future retrofit costs. The sulfur feed rate and NSR are the major variables for the cost estimate. The NSR is a function of the following:

• Removal efficiency, • Sorbent particle size, and • Particulate capture device.

A retrofit factor that equates to difficulty in construction of the system must be defined. The gross unit size and gross heat rate will factor into the amount of sulfur generated.

Based on commercial testing, removal efficiencies with OSI are limited by the particulate capture device employed. Trona, when captured in an ESP, typically removes 40 to 50% of SO.2 without an increase in particulate emissions, whereas hydrated lime may remove an even lower percentage of SO2. A baghouse used with sodium-based sorbents generally achieves a higher SO2 removal efficiency (70 to 90%) than that of an ESP. OSI technology, however, should not be applied to fuels with sulfur content greater than 2 lb SO2/MMBtu.

Units with a baghouse and limited NOx control that target a high SO2 removal efficiency with sodium sorbents may experience a brown plume resulting from the conversion of NO to NO2. The formation of NO2 would then have to be addressed by adding an adsorbent, such as activated carbon, into the flue gas. However, many coal-fired units control NOx to a sufficiently low level that a brown plume should not be an issue with sodium-based OSI. Therefore, this algorithm does not incorporate any additional costs to control NO2.

Page 3 Sergenc & Lundy•••

1PM Model - Updates to Cost and Performance for Project No. 13527-001 APC Technologies April 2017 DSI Cost Methodology

The equations provided in the cost methodology spreadsheet allow the user to input the required removal efficiency, within the limits of the technology. To simplify the correlation between efficiency and technology, SO2 removal should be set at 50% with an ESP and 70% with a baghouse. The simplified sorbent NSR would then be calculated as follows:

For an ESP at the target 50% removal - Unmilled Trona NSR = 2.00 Milled Trona NSR = I .40

For a baghouse at the target 70% removal - Unmilled Trona NSR = 1.90 Milled Trona NSR = 1.50

The algorithm identifies the maximum expected HCI removal based on SO2 removal. The HCl removal should be limited to achieve 0.002 lb HCI/MBtu to meet the Mercury Air Toxics (MATS) regulation. The hydrated lime algorithm should be used only for the HCI removal requirement. For hydrated lime injection systems, the SO2 removal should be limited to 20% to achieve maximum HCI removal.

The correlation could be further simplified by assuming that only milled Trona is used. The current trend in the industry is to use in-line milling of the Trona to improve its utilization. For a minor increase in capital, milling can greatly reduce the variable operating expenses, thus it is recommended that only milled Trona be considered in the simplified algorithm.

Outputs Total Project Costs (TPC) First, the base installed cost for the complete OSI system is calculated (BM). The base installed cost includes the following:

• All equipment. • Installation. • Buildings, • Foundations, • Electrical, and • Average retrofit difficulty.

The base module cost is adjusted by the selection of in-line milling equipment. The base installed cost is then increased by the following:

Page4 Sargent & Lundy" •

1PM Model - Updates to Cost and Performance for Project No. 13527-00 I APC Technologies April 2017 DSI Cost Methodology

• Engineering and construction management costs at I 0% of the BM cost; • Labor adjustment for 6 x IO-hour shift premium, per diem, etc., at 5% of the BM cost; and • Contractor profit and fees at 5% of the BM cost.

A capital, engineering, and construction cost subtotal (CECC) is established as the sum of the BM and the additional engineering and construction fees.

Additional costs and financing expenditures for the project are computed based on the CECC. Financing and additional project costs include the following:

• Owner's home office costs (owner's engineering, management, and procurement) are added at 5% of the CECC. • Allowance for Funds Used During Construction (AFUDC) is added at 0% of the CECC and owner's costs because these projects are expected to be completed in less than a year.

The total project cost is based on a multiple lump-sum contract approach. Should a turnkey engineering procurement construction (EPC) contract be executed, the total project cost could be IO to 15% higher than what is currently estimated.

Escalation is not included in the estimate. The total project cost (TPC) is the sum of the CECC and the additional costs and financing expenditures.

Fixed O&M (FOM) The fixed operating and maintenance (O&M) cost is a function of the additional operations staff (FOMO), maintenance labor and materials (FOMM), and administrative labor (FOMA) associated with the DSI installation. The FOM is the sum of the FOMO, FOMM, and FOMA.

The following factors and assumptions underlie calculations of the FOM:

• All of the FOM costs are tabulated on a per-kilowatt-year (kW-yr) basis. • In general, 2 additional operators are required for a DSI system. The FOMO is based on the number of additional operations staff required. • The fixed maintenance materials and labor is a direct function of the process capital cost (BM). • The administrative labor is a function of the FOMO and FOMM.

Page 5 Sarger-n: & Lundy•><

1PM Model - Updates to Cost and Performance for Project No. 13527-001 APC Technologies April 2017 DSI Cost Methodology

Variable O&M (VOM) Variable O&M is a function of the following:

• Reagent use and unit costs, • Waste production and unit disposal costs, and • Additional power required and unit power cost.

The following factors and assumptions underlie calculations of the VOM:

• All of the VOM costs are tabulated on a per megawatt-hour (MWh) basis. • The additional power required includes increased fan power to account for the added DSI system and, as applicable, air blowers and transport-air drying equipment for the SO2 mitigation system. • The additional power is reported as a percentage of the total unit gross production. In addition, a cost associated with the additional power requirements can be included in the total variable costs. • The reagent usage is a function of NSR and the required SO2 removal. The estimated NSR is a function of the removal efficiency required. The basis for total reagent rate purity is 95% for hydrated lime and 98% for Trona. • The waste-generation rate, which is based on the reaction of Trona or hydrated lime with SO2, is a function of the sorbent feed rate. The waste­ generation rate is also adjusted for excess sorbent fed. The reaction products in the waste for hydrated lime and Trona mainly contain CaSO-1 and Na1SO-1 and unreacted dry sorbent such as Ca(OH)2 and Na2CO3, respectively. • The user can remove fly ash disposal volume from the waste disposal cost to reflect the situation where the unit has separate particulate capture devices for fly ash and dry sorbent. • If Trona is the selected sorbent, the fly ash captured with this sodium sorbent in the same particulate control device must be landfilled. Typical ash content for each fuel is used to calculate a total fly ash production rate. The fly ash production is added to the sorbent waste to account for a total waste stream in the O&M analysis.

Page6 Sargent~ Lundy•·• •

1PM Model - Updates to Cost and Performance for Project No. 13527-00 I APC Technologies April 2017 DSI Cost Methodology

Input options are provided for the user to adjust the variable O&M costs per unit. Average default values are included in the base estimate. The variable O&M costs per unit options are as follows:

• Reagent cost in $/ton. • Waste disposal costs in $/ton that should vary with the type of waste being disposed. • Auxiliary power cost in $/kWh; no noticeable escalation has been observed for auxiliary power cost since 2012. • Operating labor rate (including all benefits) in $/hr.

The variables that contribute to the overall VOM are:

VOMR = Variable O&M costs for reagent VOMW .., Variable O&M costs for waste disposal VOMP = Variable O&M costs for additional auxiliary power

The total VOM is the sum ofVOMR, VOMW, and VOMP. The additional auxiliary power requirement is also reported as a percentage of the total gross power of the unit. Table I contains an example of the complete capital and O&M cost estimate worksheet for a DSI installation with milled Trona injection ahead of an ESP. Table 2 contains an example of the complete capital and O&M cost estimate worksheet for a OSI installation with milled Trana injection ahead of a baghouse. Table 3 contains an example of the complete capital and O&M cost estimate worksheet for a OSI installation with unmilled Trona injection ahead of an ESP. Table 4 contains an example of the complete capital and O&M cost estimate worksheet for a DSI installation with unmilled Trona ahead of a baghouse. Table 5 contains an example of the complete capital and O&M cost estimate worksheet for a DSI installation with hydrated lime injection ahead of an ESP. Table 6 contains an example of the complete capital and O&M cost estimate worksheet for a DSI installation with hydrated Iime ahead of a baghouse.

Page 7 Sarge~ & Lundy«<

I PM Model - Updates to Cost and Performance for Project No. 13527•00 I APC Technologies April 2017 DSI Cost Methodology

Table I. Example of a Complete Cost Estimate for a Milled Trona DSI System with an ESP

..,.. Sb°'°''~ ....~ -"- < ~ ..... - -F.::• II -I <-Us,., tAn•~.,__... ,nvftr.h.lt •'Klot • 1 ~ -'""'"' Hutfb.llt 1 ... < . v,.. l 0 ~-~~ ~ 1 < ..:.-,. rr-.,~ E ~ <-lh•lnpui. IP.....,_C.,..,. , -...._,_ ., -c ... U.«.,.,,, - G • <-Us•~ U,,•ffVTl~alT.-o,tb - llnmlll-dTrcn.awai~ESP•&~ ~ Tron,, .ct, an &:SP •SO. .._. .., .. .. ,.., :

trana ■ 4 12011, 10,,,,.0,,•w A'C"O ~ f"...-qllit:1'4' 10).3 "' ~aid Un-.• (8 ~ • ll>"-OT)'K'A'C"t) -· "8itdor Urvr.a.d TrtW\&W'ChM ESP• eo 1e~tt"O 10&1, or00l2&1,lfku E1-om.t«t I-Cl Fl--«# .., :, 1 113 ~°' U'Wh:a.d ln:1"16-.t:halKit-t-&4 !1"8'H"O 034eo,,OOQ2 b'M91u H,at-.ct UtN __, an£SI- • !M ln'H"'O 1'17 or e co2 bM9ta., Hydnll:Ml.ifNW\aSGM•(l~"H+00120r0.002t1,'1,11Elu

Jrun,, ■ ~ 131.J • 0 00l8''Hlkr M Sorbent W~t• Fbllt N 13-11 Lm. • 11 oo • ooorn•~"M '""""' WM-1•ptt0,;Ct...,.ttd..,...• 1N"""""' ,ntf'lCIDl"';111f1d!iltlo IDtT,or,.,, .,..,N fol'Hys.ztffl,,.,. (A."C)"Ash1n_(I·- Ash __,..,.2')'12"t-lHV~ Fly Atoh W,HM R,I• p 1...... , II)>, ForB«uffWICIIACoaS ~~C4.ii•012.:S.0,..-AshR...-.::rv.al•O:?. HHV• 11COO l~lf\VOMT rr. f011'118CN,l.Ash11'1Co.w•IUNl, Bole'"Ash~~•02". l+ril • t400 ...... , Fort...• COM. A\h in eo.l' 0.08. 81::iitiH- Astl Rftnw.al ,... Q l'"'I •If Mihdi lrcN lt'Mi.A etw M II/A ~inVOM'l (;' ·- " ~ , ...... < u... • J u u ...... • a l Pu-, < UIH~l0ispoulC!Dltwdl8J,nh • IW W.1fWN.ty.nt,,1M~w.nleXIM Nn.. t:a. .._.c.-1 .._, s "° •'S100l --, ,... w...... • .... <- -· ...... u "' < ·0- Iba"~. .albenefl:s, Costs are all based on 2016 dollars C,ipit.ailCl'5 ~ (74$.000'B'UI fflc 7 5CO.ootn!"1M"O 284~ It~...... ,. a.aw rnodu"e b ~ ~ ~-~IO"N't'Ct'OmWI~ Ml.led TmtLa • (M>251hM(t10.000WS'Ll•---8 .lOO IXD"B"tU"O 2'84) 18.J,&8.000 '° ~ f'C:Ndl"IQ def'vnlicaon 'fyUMt 9Nl($.1\W)• 37 B.tMMOO.d111"WM.,....,w lot.I P'ro;ftl Cost ,i,••1D'll.c111111,,ii 1tJMOII E,,ginMmgandCu•.s.l~~l tMl.s A2.•~dBM 0 J7J)OO u.bof~fotO:stO_..,iftftllk"fft'Wm.~ditm NC Al• ,_,dBM Dl7.Dl0 CCMrx:uat ~ .,,di Ml CEC.C (S) • EadudH Ownan Cbib • 8'11•.1'1 •A2•A3 11.011000 ~•~Yld~cost~ ace: C".W> • bduclH 0wni1n COits • .. ~ ~ __..,~oolt IUllloul fMf' kW

81•~at~a; 1, 101.QJO Or-Ntsc:cn:ts.lt'ldudlng,a~oll"l:»'""'"'4~~­ ~ar.d~t~) f'PC" ($) - lndi.GH Ownotr"s C641t • eeec • at n.u,,ooo T~~CCKtMhcuAFUOC tPC" (111:W) - Snchms Owntr"s Costs• Tot.,1~001,tfHttkW'MhoutAFUOC 82•0'5dtC-eCC•Bt) " ~UDC(Zafab r.t,.s.,.,_, l y,t,1r~MldCCIMCl'\dan~~ tPC (SJ• CIECC • 81 t 81 11, 11 ■- l'PC(SMW)•

fl•dO&IICM.t " f=OMO (l,'IW ~j • 12 ~ ope,r.Jlot)7090'U,'(A' 1000) " •lll'dOUol~opH-.LamcK-~ Fca.lM CS.,llVf yr)• ea.c·OOl"9'A'IDIXJJ ~i,.e,dO&l,I .additian.11 ~ ~ ~\Jba, CIOtu (Sf\W yr)• FC..lA. 0.03•(FOMO♦O. ♦•FOfA1) ~ tdO&P.I ~~r.atMJ.abof"costs FOIi fhW yrl • FOIIO + FOMflll • fOMA T~ Faed OW COits YMWlilr9 OUI Cost VOMR(~>•44'RIA V.IIWJII.OUteot11b-~ V.-wibltOGIJC0:111 For___,ddoo-wilhlinc.t.de..bolhtM~1 ..,.,h ly,Mh W.a&eftCl~ ....Jq,hsorbeftt..-,.aan VOUP tSIM'Ml)aOTIO V~O&Ma:nu.fo,~~J.-,s:oMf~ ~R .... WIIAu. Po,wr ~ Abov-.~ Ye. (ltlillWhJ • VOMR • VOMW ♦ VOMP 933

Page 8 Sargent;; & Lundy•••

1PM Model - Updates to Cost and Performance for Project No. 13527-00 I APC Technologies April 2017 OSI Cost Methodology

Table 2. Example of a Complete Cost Estimate for a Milled Trona OSI System with a Baghouse

on um• .. ...,, !500 < IJs«~~I ,Eftd1FK1Dr 9 I <-Uti•-&M""¥-•~tl\al ••.actcw' • 1 Or ...... ·'\'~, uoo < • us« In-, , ..... 0 {ll•• ltJ81,,,) 2 c.-~lnput ~..... Co.II e • I ~ \k« ltlpul P~C..""" • -_,_ ..., "-\Jt,.O:M5't4)1 Mlhtd TIUNI ..hM\ i'.SP • If (1-i"40.0 0210'H.0. 353e"{00280'H)) Ul'lfflihdfn)NWCf'laBGtl,...f(H<-40.0.021$'H.D~.~7'1,f)j 1$· OC, • MJ.td Tirvn.~.aBGH •d (H"'40,0.D190'H.0.~00:Sl'H~t ,._.~Um.Wollhat1ESP • D~'H"'OM-s tf)dt'atwd Urne ~ • BGH • 0 0017'1'++0 ~ ~ ,9"11,...,...... , lll>N • tt..2011 it. IO'\,OO)'~'A"C'O . Hydnt.cl LffW • (e.OOM a: 1()'\47)'1\'A'C•O - Mili.der~T,on,1-.ilf"lan ESP •IOM•wo.1091 or0002~ Es.-naeCOTn"H."kl"M -~ fYi' nt11 P'ffl,Ct -,.rad fer•~ lf'lllf1 oonwc d ~"' b' Tl'O'\il and N !Qr ~.,c, t,.,_ (A~)"A,P,. ""vual'(1-lklllittAloh lf.,.•ov.aFy.2'HHV~ FlyAs,,W_.,.,._ For~Ci»I ~,,,Ca.1•012 8--AshA~.ai•0~. t·0·N•l fCOO ~~VDU., f'" r ( ...... ;r).t3 Fo, .PR8 Co.I; 4,h ft Co.,1 • D.oe, Bo...- 41'1 Rit,tno,,JI • 0 2. J,,O,tV • U00 Fo,tl.anla.~ Alh Ill Cul• D.08~~A$1'1 fwrrov~ ...... _ 0 l"l .,, •IIUltdT,vn,,.M'lO:AfilMM"1e,A 1a.1.tlld.ifl'tilOM:P CZ: M 110 <-U- ...... • ,,~.i;; ~- 1G <-lhll"lnput\~005t.. ·t'tf..sh•s.e,Q 'WrtholJt..,a\h,.lheMNbenlWMt41 .... s will be_....,....,od"&~ •StOO «--Oma •oc .. •U'I• ..,, ..... ~' ... , .. ~ "'· -- Costs are all based on 2016 dollars CapmiCOi!,(~,,_. E....,..._--...... ___,, ______..,. c-

Unffihd Trana• ~t,,.,. t1M>~ IIIW' {745.0Jl"B'M) ..1.,00 oocr&·t~Z841 1,,112,000 e.... mrdM lot I.INftl«I ,O"tlrMt l'ldudn .. ~ fn)m I.A"lioadi"CII MMitd T~ • (M>25 hft (820.0lXl"'&'M).,_ t.300.0CO•&'tU"O 2941 tD~ndudiftQ~'l~lffl BM(SJk'WI • hMl'nOdulllGMlp,!!ol"~ total rr.,.c:e COit Al • 1(N,4!1f 81A 1,-!,IJ l!ICD E:r'lglil'IMl"l"IO-~ Cem!NCtic,i MM,g~ OMts ~•KcfBM 791.COO LNOl'~fl:r"61: 10tao.,,1hiftpN,.,._..,., pe,r-diMt W A3•54cl8M 7i1 000 ~--Jldor~lolndlffos CECC ($) - IE.ccludn ~Coats• Bll•.-hA2•Al 11,,15,0DO c.,,...,.. ~ ,11,dcon&truc;c,on cotl wbtoai1 CECC (S,'\W) • &dl,,dtt ~ CO'ib • • ~erainNrino.w,dcon'lwceionOOS1~~kW 81 • 541>cfCECC CMQ.000 0Mltrscotb.i~.,-,ic,m.a1t,u•oo'll,Cow,en~. ~ll\dpr0Q.lrwnM'tl~) Ownar",s Cou:s fPC' (Sf -Ir.dudes a CE.CC • Bt tt,tlt_DOO Tobi~ oolt wi1ttour: AFU0C TPC' ct,lltW) - lndudn o-.r'~ Cosb • .. T~Plq,ldo:,tto.,lkW ..... AFUOc 8? • ft ol(CECC • 81) JPClfJ•Ci.CC+Bt•B2 n,n,.oao TPC(1M¥)• .. FiaHOUC..l FQUO (1'11Wyr) •{2 addrbonalapanD'.'2Dl(I~· 1000) Fa.M o&M ~ ~ lllbor costs FOMM (S.'11W'Wf) •8U'O.Ol1t8•A'tto>~ F'uedou.l ~~ ~ MdWxrc:cus FOMA (S/kW ~ • D.03"'FOll()t0 -4'~j F'n.dO&M ~~ bOo,«,,St'I FOM (1/llW yrJ • 1"0110 • FOIIM • fOIIA Tot.IS F~ O&M msts v~oa..c-1 VOMR(~)• M·R:.- V.anablitO&Monbiot~t , V~<>almutb....-dapoWlthM.ind..ldftbathlhttorbtnl .. W h ly,1~----~l'IC"OIION'klrtMnt-,.ctJofl

VONP tS.-M'Nhl -O"T"10 023 V__... 0aMCOHI laradcl~ .11,,1.1.~ powat" ~W (FtefwlDAf,DIPQlllll9t1'~> UI

Page 9 Sargent & Lundy" '

1PM Model - Updates to Cost and Performance for Project No. 13527-00 I APC Technologies April 2017 DSI Cost Methodology

Table 3. Example of a Complete Cost Estimate for an Un milled Trona OSI System with an ESP on _,,, ii;(,-, e ~ - 1:-.;: ·M'"av•.&1· liNllal~;J,f,Xltlf.& 10) '.=..!!!!I!. _I,' _llbfJM9tul ~ _,. •-U..-·~ E . U...1.-c,A ...... ,.c.,pu. r ,.,. II - • l"<-"" U$erlrc,ut ~ G • uw,""' -·- ~--·---31~~ -- i'Jnnlod !""'3 "'111 ;in ESP , °"" ~ Trm:11 -..111 .n E!\P : eo,(i ~ ;i,T- H ~ II 511 lm'de01ra,o...,an8 Qo➔ , _ !;.A.led T,u,a Win an 8GH I ~ H'PJ:ed._.,.~il'IEsP ■ JOw. H-, ",

Tron;a; 11 2011 1. 10"-06J'l< ~A'tC10 _ r...,Ft!I• .. ,...,..,, 22!>4 Jt;ln'"" Lmo = 160056 • 1(1',-0l)'>

Mile00r lffl'llled TR:11:1 V!Chan£SP = 6036'H"O 1081, oro m2 ~ ~1bmiltedf-CJ~:al 9} "'llldor ~ r~ Id, 3 8GH ~ ~H"'O 0346 CIO(XQ ~ ' H)a>IOd l.lme - an ESP: 54 92-H"O 197 orO COl- ""' ...-,'• N i~ 1111 L,ne : j100•0 00777'Hn JIii) For~Co.ll Mh W'I C«al :012'.;8oilit'tA.VIRtfflc:Na .a.02, t-+i\ 1 11CO) :l'Qlele n va,, a! Fa PR8 C.oal Ash II Co.'.f 'I. 0 OS, Bollft Ash Rtlra,val ;:; 0 2 ..,., 2 8400 F~~ C,,.,, '"" ,..1:o:,1 •008~ lloolo< AsnRe,n1,.11 ,..,._, 0 N o.t, ~ Trcn,M"1QIAilfsa M·1ii IAtltdt ft'WIMJ' ..m _.._ ?= d IM-25"'"" 111211000-S-"'} - 8,JOO,OCXMl'(M"01&11 " .168.000

BM(~I• J6 befflOOM eoslc,e., k.'N t Otll Prc)f9Ct Cost Al • ~<'O>,I I JU.a» E-,noandCmsdtldes 0Wllcf'1 Costs• .. r-"C)i1a1,...,._.....,.....,_eos1...... _...,,w 81: Sllol CcCC 1.0'l0.000 °"""'005tS~all'tonacfflai"_<_...... ,.,..MO _.,...:nl,..,...... _Oots• '6 Tobi o,ojed COS1""' ~N~ ARJ0C 82•0..d(CcCC•BI} AR.OC(Z...bmslllan l--..-.a-.-"""'1 TPC 1$) • CECC • 81 • 8l 22.891.000 T 050 Flllo:IO&M--lobol• FOMO • FOMII • rOMA 0.18 F"-O&M----T~ foed O&M msls V.wi~O&IIIC011t V0MR IWM!l, M'PJA 1014 v..-O&Mcoot>b­ "°""' ,_,..' (NoPJ'SI~ -O&ldmslsJQt--lllal-OO

Page 10 Sargenc & Lundy«<

1PM Model - Updates to Cost and Performance for Project No. 13527-00 I APC Technologies April 2017 OSI Cost Methodology

Table 4. Example of a Complete Cost Estimate for an Unmilled Trona OSI System with a Baghouse v...... v.... ••'• A u-N, Jl:ft'Of.tf.xD"""" . ~-< User~w·~' - •,. h,H,1r.lC'll)l"•ll;I) C'.ros1H1.1tR.H• C --- ' < ...., 50~~ 0 Ch1t.ll!JaJ"" ) ~~ <-U... ' T)"P4' olCoill E ·- ... <-Ute,tnp.i: :,~---~~fa_, F • <- ~tnprt - • <- IJHf Input G -,- - ''.a..J"nUm Rtmov-T,geu.: Ul'VNhd T,on,a WVI .aft ESP• 65'4 l.'.. litdT~wid'la,iESJ)aa&I, IRl,Ol;ll, .. r~,.. K ,.. , ,. ~ T~ ~ •1t 80H • ~ l~ fn,ruMh~BGH •~ ~ UM .:ti' ,n ESP• 3t"I. 1-t..a.aedUnw..,af)GH ... ~ •-u. ..L "' .l'!!M.4C0 14.•c•1...- Ul1fl'ded Tf'ONI..,, an ESP .... v•t<-40.8'_Ql~O·M.o °l6:.-"1GOJ,4~· .. .u -,WIN Troin. wilh a.-. E~ • 4 (M~ 0.0270'M 0 3$3r10.0::to'Hll UMWIM Tn:>Nwdl .a eGH • If tl-t<-40.0.02·,·H.o~o.02tr1·1-J)• i'-t..O.~ ~,t __ Tt'Of'I.II • tt 201111 10"•-0CWl-.'A'C' O .. 1219 -~ ~l.-.• 10CJ05.S110l'"47)'"1K'A'C-0 "6td0tu.niSNJl0ft.lwCh.a\ESP•DOll!.~H'O 1011 •OC:02~ MAl-d orUMded T,uu,~ 1 9GH aC-4 -!~'H"'0.0:MO o,0002 b'MIBtu, l=,.iMnlll.-d HO AMOr.111 V ,,. 07 H,d,&N UM ....,, an ESP • 5,4 ;zo»"O gT r,1 00C2bM8tu .... ~Lffle...,_.a 8GH •0008S"H+W 12,.tJCJJ2b'\18ri.t T~ • ~0131T • D001e51Hlll.)"M ~1W.i;MR.J.II ti ,110n1v) 10_50 l.nte • j1(l]•000177·~~ WM&4'pn,dl..ct-.,wdl'o'.1111.1..amwn ,Nf', ~d,-.b'T,v,,aardNfa'H-,o.1'1ed l inw {A,'C~'A$1'1 _._ 1• -Soiii_r A-sh RMnOv.ail,'i2'1tHV) l#"~A,V.Wn•Rp, Fo,~C.0.-• Afjr,, nC&/ •O I?: BONf'AVIR..-r.cw.1111 •02. ~l-4'V • l ll)GI) lncl.adeinvo,.4" _:;: ~ ('n'hr> "',, Fo,~8C:o.it' "5'-n COAi • 008; Sad4,,A1,h ""'"°"~ •01.11,fV • f400 Fo,l...,,...Co.lAlhin~•DOl:8-,AVIR,e,ro,.,.il ~ ..,., Pow.-, 0 .... •f~T1UNM'~A..,.ll'Ul11\ u-ua. in VOii"? ,. R 1S.1an < • • l ;rn ...... • • 1~1 < Us..-.,..,.(~,i1 cos1-.ihftrnh•SW W~,-,.nt\.OM~_,.-..-,. N-,. ih.o:.r.....___.. Coj,I .'° s _.bt~4-fo.11tto.._.._•_I_IOQI: .... ~ T 0..~\v,n-n .... < ·'-"--- l..lOOtR.M• u .. < -- '"' Costs are all based on 2016 dollars C•pdal Cosl C.ue.eion c-. w::ti.riK e~ ""5~.11u~_foundaan5 ~.--,,...c,tt~ \hnhd Jrona.p ...... ,tt14Ul'oa • ~~2:S....,_ n◄5.000'8"1,1')fflll' t.e,c;»JJ0VB'l-...02&41 1$.4$9..000 B.a,w ~ 1br ~ Mlr'benl. rdl.,dM M -.,'P'l'.-1 ~ ur,IOD""O l.Yed f~ '(1'>25'nlri Jl.."'l(J,DOIJ'8\'III ..8,300.0IXl'B"IW,01' ◄) IO~ f'dyf..,O~ ~ya.Im 9M(1/l'lofgMwni~I A.l•WdSM ·~•.ooii rn.ooo Labor"~UWMnl:rota, tOholJ,~~~ pe,ditffl • II[ .U•S..clBM T7l.OOO Cu.l'M10t ~I and ,..,.

CECC ($. bcluditt o-n.h Cosb • 8M+At•A2-tAJ tl,$Cl,000 eapc,.!. ~~COM~I CECC ($,'11.Wl • Ea:dudH OWN,-, Cot.k • )7 c.pull. ~ .lf'ld ~ CXKt~~ P'!-1' ..w

Bl •5'Jl.olCECC 029.Jm o.n.n cos ... ~ ,.,'honM office" cos.ts ,lJIMW'f t"O~ ~ aftd ~nt,ld N!tiH TPC" l$), lnc:kMfiH ~~ Cu.b • CECC + 81 tt,'6.DOO local prqt,ct COil WChout AFUOC TPC" (1/liW)•1advdn o-w.f'i.C~"' • .. JOUI ~ C:in1 per lriW lllihout Ml.CC Bl•KolfCECC +61) TPC(S)•CIECC+B1 +EU 19,m.ooo TPC41ikW)• .. FindO&MC0t.l FOMOt~"kW Y') • (Z ~ oprw.KOtf2080'U't,t•H)00) .... FirNOSM'"6._,.,..apwW!g'.JborOOM'I FOMM (l,'lW ~I• 841'00l,'(B'A' IOCX>) D ll Fiwd 04M MeitioNI lft.U'IMnanc::ia nut1tl\M .MG~ co'lb FOMA (1,\W ~,. 0A)3•~.,•~ot.W.~ 0-'>l F"~ O&M ~ achw!KU..... \i,bo,' °"'' yr] • FOIi l$111W FOIIO + FOIA#: + fOIIA 0.IJ TOQI ~ O&M wt-ti V~blt OUI C051 V0ai!Rts-,.rwl'l)•M'R'A \l~O&ll.4onhb~

1.12 \I~ O&M COlb bw:11U.OISP)NI ltlat irlc:ludH bOlt'I G'le ~t Md1'1• fly ,1shw-. I'd temowd'pno,-toftt ~irfe<;tion

028 V~OUICOIIS.forNdiaionala,:d,aoypqtllllltf~ ~DA.ulPOMl'1'~J VOM C'1rrlMI) ■ VOIIR ♦ YOMW • VOUP I.II

Page 11 Sargent & Lundy• • •

1PM Model - Updates to Cost and Performance for ProjectNo.13527-001 APC Technologies April 2017 DSI Cost Methodology

Table 5. Example of a Complete Cost Estimate for a Hydrated Lime DSI System with an ESP ..._ ... .. ••N 500 ..__VI., inpc1· 8 I < o,., , i"'l1 ~..,.,,_.,.~tllas •fxtot• 1 .11.'t 9-'l.;;ltWhl . o,., Ii~ D (hfi.1Wb1l ¥- < 0,., T)'DtotC()M ~ ,,. .. ' thtflnp,,!. ?~•~· • • . ,~-UfM ltlp,! -Hlrt'C.,:,,t,. _.,, c;:-U,e,~ G P-f~•ff¥11 ~JIii T.a,g.ts: ·- tl.Jnnwle4T~..,,, _,,.ESP• e,w. l•llH TraN Mh an ESP,. 80'i, IA..,..illl,..,.i;.t ~ ]O U~Tn,l'\Jow:lf'l~nBGM •80"' ~· "wi.d TION ..h an 8GH • 00-. H-;drad Lime.....,..., ESP • 30'11. ~ ~u.-n.,....,,,.B,OH•~ M-·- 6 H A'C•IIEl;I 0 U'"6d TtolU...,. .M'I e:,;.p • 11 fl4<40.o lll!D H.o 35~ 0 03o4:5•NJ1 "-IN Tta\awith ~ESP• ,t tHc.t0,O0'210"t-i.0.l$3..-'(OO280'H)1 k I iO L>tvnliffTtOfl.l ll'Ctl aBGH • ,,,~.o 011,'M.O2toe-"{O.0207'J,4_tt ~ I.UH TtDn.J _.,.., 8GM • rt (H-t40.0.010D"M,O Dr(!>0?81"H)~ ~ Utrw ....,,_ an ESP• 0 '°''M"O l004 ~ ~ Mth .1 UGH• 0 0017'... 0 6'<1¼ Fil-.... ,...,...... -f •o~ fl'ON • {1 2011 • 104-Qe)'K'A'C'O ttyo,-.c.1 Lim.. t0.()06$-. 10,0,..01 •.-_•..,-c·o

~ o,lhniled Trer,.a aCtl.., ESP• l!O.IO' H'"(I 1011. « 8-0DilblMStu IE,"""1edH0-al V ..... lrMIM o, UIWIIH lrau 'IIIIO'I • BGH -&4.$Q&'H"O.O'J,10 1W :1.002 ~ .. ~u,r,..-,,_.,£SP•5'492'tt"GtW«0 Cll2•\,19tu ....,.-.d!LilN Mtt'l.aBGH•D~•t,,f+OQ 12or0002~au ___ , _ flUU • 107)87 • 0.00!6$"1-L'k}'A.t ~tW~~ 'f l~J tl ,. ~-t i oo • o 00m•~1-u WJl:lte~~lic, • PNloWl'Vn....,,c:onl&oHd,'Jl,.,_.T~..-1d~b H-,0'•-..dLffw (4~)"Ath1W1Co1,1°(,,Bo,i,ttA11\RMIO'#~.i,,2'Jil-N') fl',AlhW,41.-A..11- ,. ,.,,..,,, l01~ For~Co,11 A.th 1t.11i COfll•O.l~!';Boief'A!hR..,._.,....a,.g2;t-tHV• 1tCCO ForPR9~l;A"1,n t.4f,f• ooe; eot.tA'IPI ~~•Ot; Hf.{V■ 8AOO """"•~"°"' ~ Fo,U..e eo,. Ash ,n Coat• 0 08. 8odtr A.51'1 R.-no,,Jj 0 I") -.t--TMNM-,... .1..tw.\4'18/A i.w~_,.VOII'? ITi ." -·- R ,~ .. _ u, ... -art,a•:111.n:. ~ ~- ~ c- U,erinsiu(4~~wchffr

e, •ftof'C€(1; Ownt~ cow.-'dudrv.111'ome alfc,e• co,11(~ ~ ­ se

82 • O'!llo d(C€CC • B'l1 " MVOC IZ.-0 101' '-H th.VI I ,...,,. ~Mftl'IO arid conMNC'Kl'I c-)"dtl

TPCf$J •CECC ♦ 81 • BJ II.I00,000 T~~CCC1 tP<:~• 31 ToblpR)fedeettpMkV,, FladO&MCosl FOMO l'lrlW yr) • (2 .add!DOQI ~r.-wrxaru·"'°•?COOi iJ.'KI F~O&Madchc:l'\ll~labotCOl-lt, FOUM '"W )l'I} • 8M'OOl.-,B'A"1000) 0.30 ;~O&M~~m,taNIM,dbbG<:09-b FOMA. (1/tW 'Jfl •0.01'tFOU0+0.-4'FOMl,tJ 0 ,02 F1ndO&Madotnnll~._,.iao,-e,o,nt,

FOM (~yr)• F0M0 • FOIIM • F0MA Q 11 Tor.,, ~cqd O&M COlll V.ariMlitOUICost ~ l~l • M"AJA V.an,atte O&M i001b fortofiMnt ..,. V__..O&M001tsbW1... 6tipONICh.al.ird.idftbath.,_sorbffl1 •rtdlhelly.ilhw~l'IClt~ptior-10thrt~l-,.ct.on VOMP ($.'MWh) •O"T'IO Vlf\MM04Mcalbfct~~~ ....'nd (R.,_ 10 Ac.Ix~ • .toff) VOM (S/MYt'h) • VOIIR • YOflN • Y0IIP .. ,.

Page 12 Sargent & Lundy"•

1PM Model - Updates to Cost and Performance for Project No. I 3527-00 I APC Technologies April 2017 DSI Cost Methodology

Table 6. Example of a Complete Cost Estimate for a Hydrated Lime DSI System with a Baghouse ...... v- A •vi, -- - ■ -1 ~-~... --.... ,• ..,., ... ,,..,...,. ,01 .~ <-U.---c; D tb'~tM8tt, l .,.., ...... ' ~T~C>'Co.al ' -" • ~-vsr~pu! P~C.apv• 'F _... _ • o,;,_Vs•lnp.,t - ... <-Us«tnp.,: ...... G - >l~,1.ffll,lrn Remov,1 T.atQ•ts UNn&d T"->N Mh .a11 E;SP • f54' ._'tiOftdTl'Ct'IJl.«h~ESP ■~ R~,.ill"tM H ,.. , !,(I lJMIMtd r~~~BOM•~ ~TtcA11WM..attBGH•00'6 H~-.ci U'ht ~ •n ESP• JO-. atJ Uffit.th.aeGt-1-ro-.. -· ~ ...... ◄.75E.OC. A"(:'tCIXJ UnmiCltd Tron.. di Ml ESP ■ tf (H<40.0.03~•K 0 36::!,r'(0.03'45'M,) W~ Trcn.aWCh Ml &SP• d IM"-40.0 cr.?10'H.O.l!>3¥tO.OltO'H)J i' • ~ TtclNl,.t, ~ 9GH ■ ,t (Mc4(l.0.01$0"H.0 :?Olr'{00211"HI' 1-f)dt.,t.-d'U'Na«hMI ESP• D.~~H"OlQO!) ~a.id l.JtN wOI • 9GH •OOJl7"H+O~

fr01"Y • 0 201 I • U)''~l' K'A'C' D ~ •,woRn (~ .,. .. H'yd,.-dunrt• ($.0056 1 !0--07)'k'A"C•O

WiedOf~T~-..ai ... ESP• eaeo'M-'010,t er 0.Q»lh'IAJ:tu WIHotU-WTto'\l-#1'1 111 6GH-&45Cllll•H"OQ340orDQ01b'M8o,i i unvt.d HO Raff'OIV.ll V ,,. "' M)O-.act Lme 1111Cf\.at1 ESP• ~ «!~H"O 101 tr a.an bMBtu .....,,.-.dU.,,.,.a. a&Gl-l•O~·M+QQ 1lo,0002 b WBtu

Tni>N - tD mr .. o.oo,~•wt,;i•a.t N ••• ~•(I 00 ♦ DfXJTT7'~-,.I - II,•-- ~· Wasttpn:,duct~fot.11t1.&an\lffl-.ia,ntend5•tctTl"QNl~:-.kwH)O.a1ie<1l....,. (4"wl'A$h in Co.aL'(1-&iwA~ A..,.._,,,~·{2"Ht,f'I) F~AUIW~A,I. 'I-Of"Bn Incl.Ide 91 Y0M7 Z Fm PRB Co.It~., CN1 .. 0.0&. 8oklf Asl'I Rfflw:N.11 • D? HHV • 1MOO ,or1 .:.-•.-.eo,ar.A,t1.,Coal•O.Of~BoolttA'1'1~.II ~PGl"lftt Q I") t22 .,M.a.d Tnwu u·ro·A 'IIM U' I StA - - -.e:iuc.ift"6'\M'J• 7 .. 1.'ton < a ,.; l !ll:::ii - :,,.,....__..,,...____I ~ c - Us• lftP,111~.,i "°''~It/al\• seo W1ttaA: fty.nh, the~~..., acb'l4 C -·· • •be rno,.a ...... , --...... • 1100~ ll.l.1f'Ofl1191"Col,t T l'·i.Wh·-·l .... <-VII.,~ .. u "' <-lk,w - .. Costs are au based on 2016 dollars

c.aptut coa C.~ion Eumplo (: ~ '"4::tudu "Equipr,wnl~~foud.lician,.~.lftl,..,,,.~

~ ::ir ~ .111 ~ .__, (1◄ $.000'8'M).a. ll"C:IN #(IP?5then 7.500.00ti"6't-.v'O .;:MJ 9,n,e~ID,~~~--...~h,nt.r,~ MiladTl'Ofta ,,u;.z, .,....(8l0.000·a·t.11 ittM 1.100.ooo·e~(M-"O 214) 10~1'1dl.1:la'IQ~Sy$1'"1 IWtS.-kWI • 8.lM~CIO'PpertW Total ProitctCOII: A• • j,Ofi;..-1!1111 ~.~-la! E~.andCcin~~GMt1, A2a~vf~ 0.'"9.000 L.abot'~~ for ,e • 10hcuf lhft~ P

CECC rt~ · lf■ cll.-dH ~ ~ • 8MtA1•A2•A3 15,tOS,DOO ~ ~fig~o:,,n\tNeton cost tu~ CE.CC ISI\W) • EadudH 0-,.C-s Cosb • 30 C~~.w,d,constf\,lctGneoitwblQf.alOH"-W

81 • 5'11, otCEO:. ~eom ~ ,i111 "hoi'N ~· cm4i iOW"Mn •rv.,...... ao. 7!55.i;c(l ~.a,nd~~· J'PC"f11 •I,.,...,_~ com• CECC • 81 15.HD,000 TINI p,qe,ctCIMI 'flll'il'lcutAF'UOC IPC'ttlkWJ · llldudH 0--,-~ Co1-b • 32 rau1 ~-eott"'" ~w #Oo.C Muoc

82 •OCW. oliCECC' • 81) MUOC(Z.,,,k)rtnt,INft I fffM ti1Ji)~Mldoo-iWUC1iol'lcyei.l

WC(t) •CECC •St• 82 15,8'0,DOO Tct.t,l ,>tqiKtIAI) 0.02 F<$.«IIOUt~~~labatOQ11,tt, FOIi tt,I.W yr)• FO.O + roMM • FOIIA on TCUIIF',.:tdO..,..costs Y~t.&.O&IIICM.1 VOMR IS.I.~• t.l"AIA VM'Bbte O&L• ocnts b ~I

VOAfN (1,Vll\i,) • (N+Pt:JIA 2 .il V.wtilt O&Moosts to, WIKI ■ dll,pot.el th,tnc:lt,,,d" boltl ht~ ~ti...llyuhwateftOl:~JlriairtDhlG't:telt~IIOl'I

VOUP ~1.:M'Nh) -0~ 10 0. 1] Va,n,t,fieQ&l,'lo:,1t1,fof,~klft.1l&Oll!.arypc,Mtr■qw,td (R■if• IOAua.Pow..-1' ,a,bov,■ ) Yotll (Sfll'Mil) • Ya.t • VOMW • V011P 4.91

Page 13

(This page intentionally left blank)