Draft Development Plan 2017-2026

July 2017

Table of Contents

ABBREVIATIONS ...... 4 CHAPTER 1: INTRODUCTION ...... 5 CHAPTER 1.1. COMPLIANCE OF NNGS DEVELOPMENT PLAN WITH ENTSOG’S TEN-YEAR DEVELOPMENT PLAN (TYNDP) AND GAS REGIONAL INVESTMENT PLAN (GRIP) ...... 7 CHAPTER 2: DEVELOPMENT PLAN 2017-2026 ...... 7 CHAPTER 2.1. PROJECTS INCLUDED FOR THE FIRST TIME IN DEVELOPMENT PLAN 2017-2026 ...... 7 CHAPTER 2.1.1. PROJECTS FOR USERS CONNECTION ...... 7 2.1.1.1. M STATION AT SALFA ANTHOUSA ...... 7 2.1.1.2. M STATION AT SALFA A. LIOSSIA ...... 8 CHAPTER 2.1.2. PROJECTS FOR NNGS DEVELOPMENT ...... 9 2.1.2.1. NEW JETTY FOR SMALL SCALE LNG ...... 9 2.1.2.2. PIPELINE NEA MESSIMVRIA – EIDOMENE/ AND M/R STATION ...... 10 2.1.2.3. COMPRESSOR STATION IN AMPELIA ...... 11 2.1.2.4. UPGRADING PROJECTS OF NNGS -3RD GROUP ...... 12 2.1.2.5. UPGRADE OF PHYSICAL PROTECTION OF DESFA FACILITIES - PHYSICAL SAFETY CONTROL CENTER ...... 14 2.1.2.6 IMPROVEMENT OF METERING ACCURACY IN NNGTS STATIONS ...... 15 2.1.2.7. REPLACEMENT OF METERING AND CONTROL SYSTEMS ON M/R STATIONS OF NNGTS ...... 16 2.1.2.8 NEW BUILDING FOR DESFA’S HEADQUARTERS ...... 17 CHAPTER 2.2. PLANNED PROJECTS ...... 18 CHAPTER 2.2.1. PROJECTS INCLUDED IN THE APPROVED DEVELOPMENT PLAN AND THEIR IMPLEMENTATION IS ONGOING IN THE REFERENCE PERIOD OF THE CURRENT DEVELOPMENT PLAN ...... 18 2.2.1.1. CONSTRUCTION OF HIGH PRESSURE PIPELINE FROM MANDRA ATTIKIS TO THE FACILITY OF ELPE IN ELEFSINA FOR THE CONNECTION WITH NNGS AND RELEVANT METERING STATION ...... 18 2.2.1.2. CONSTRUCTION OF HIGH PRESSURE PIPELINE MAVROMATI (VAGIA)- LARYMNA AND NECESSARY METERING STATION FOR THE CONNECTION OF LARCO GMM SA WITH NNGS...... 19 2.2.1.3. COMPRESSION STATION IN KIPI ...... 20 2.1.1.4. M/R STATION IN ...... 21 2.2.1.5. M/R STATION IN N. MESSIMVRIA FOR THE CONNECTION OF NNGTS TO TAP ...... 21 2.2.1.6. KOMOTINI-THESPROTIA HIGH PRESSURE PIPELINE (PART OF NNGS) ... 22 2.2.1.7. 2ND UPGRADE OF LNG TERMINAL ON THE ISLAND REVITHOUSA ...... 23 2.2.1.8. 2 ND UPGRADE OF BOARDING METERING STATION (BMS) OF SIDIROKASTRO ...... 25 2.2.1.9. UPGRADING OF ELECTRICAL AND ELECTRONIC EQUIPMENT, BILLING SYSTEM AND EQUIPMENT SCADA FIELD IN STATIONS M/R OF 1ST GENERATION (1995-2000) ...... 27

NNGS Development Plan 2017-2026 Pg 2 of 45

2.2.1.10. EXTENSIONS AND UPGRADES OF METERING STATIONS OF NORTH AND EAST ...... 27 2.2.1.11. UPGRADE THE SYSTEM OF FIXED COMMUNICATION OF NNGS ...... 28 2.2.1.12. IT & TELECOMMUNICATIONS PROJECTS ...... 29 2.2.1.13. UPGRADING PROJECTS OF NNGS -1ST GROUP ...... 32 2.2.1.14. UPGRADING PROJECTS OF NNGS -2ND GROUP ...... 33 2.2.1. 15. INSTALLATION OF M/R ΚAVALA ...... 35 2.1.2.16. UPGRADE OF LNG LOADING ARMS AT REVITHOUSSA LNG TERMINAL . 35 2.2.1.17. TRUCK LOADING PILOT STATION ...... 36 2.2.1. 18. LNG TERMINAL BOIL-OFF GAS COMPRESSOR STATION ...... 37 CHAPTER 2.2.2. PROJECTS THAT HAVE ALREADY BEEN INCLUDED IN THE LIST OF SMALL PROJECTS AND THEIR IMPLEMENTATION IS ONGOING IN THE REFERENCE PERIOD OF THE SUBMITTED DEVELOPMENT PLAN...... 37 CHAPTER 2.3. PROJECTS OF THE THREE YEAR DEVELOPMENT PERIOD ...... 37 CHAPTER 3. PLANNED PROJECTS THAT WERE NOT INCLUDED IN THE DRAFT DEVELOPMENT PLAN 2017-2026 ...... 38 ANNEX I ...... 39

NNGS Development Plan 2017-2026 Pg 3 of 45

IMPORTANT NOTE: The English translation is not binding. In the event of discrepancies between the Greek and English version, the Greek text prevails.

ABBREVIATIONS

INGS: Integrated Natural Gas System L/V: Linevalve DESFA: TSO of the Greek Natural Gas System TSO: Transmission System Operator NNGS: National Natural Gas System NNGTS: National Natural Gas Transmission System NSRF 2007-2013: National Strategic Reference Framework 2007-2013 PA 214-2020: Partnership Agreement for the Development Framework 2014-2020 EIB: European Investment Bank CHP: Combined Heat and Power unit P/P: Power Producer O&M Centers: Centers of Operation and Maintenance BMS: Boarding Metering Station IISNG: Integrated IT System for Natural Gas RAE: Regulatory Authority of Energy RAB: Regulated Asset Base LNG: Liquefied Natural Gas HP: High Pressure Bcma: Βillion cubic meter per annum BCC: Back up Control Center CCTV: Closed Circuit Television CNG: Compressed Natural Gas DCS: Distributed Control System GCC: Gas Control Center IGB: Interconnector Bulgaria IGI: Interconnector Greece Italy M/R: Metering/Regulating station Νm3: Normal Cubic meter PLC: Programmable Logic Controller REM: Remote RTU: Remote Terminal Unit SCADA: Supervisory Control and Data Acquisition TAP: Trans Adriatic Pipeline TDM/PDH: Time Division Multiplexing/ Plesiochronous Digital Hierarchy ΤΜ : Tele-metering

NNGS Development Plan 2017-2026 Pg 4 of 45

CHAPTER 1: INTRODUCTION

In accordance with paragraph 2g of Article 69 of Law 4001/2011 as valid, the Hellenic Gas Transmission System Operator (DESFA) conducts the Development Plan and the Regulatory Authority for Energy (RAE) approves and overviews the implementation of it, which establishes the projects for the development, enhancement and interconnections of the National Natural Gas System (NNGS) for the next ten (10) years.

The above mentioned clauses are specified within art. 92 of the NNGS Administration Code (Network Code).

For the preparation of the Development Plan, the Development Study is taken into consideration as well as: a) data of the current and the estimated supply and demand of natural gas b) the fulfillment of public service obligations and the assurance of natural gas supply in a credible and cost-effective way c) the improvement of the NNGS efficiency and the ensuring of its smooth operation aiming at the prevention of congestions, emergencies and refusal of access for new Users d) the supply of new areas with natural gas and the ensuring of new Users’ potential access e) the protection of the environment f) the European development plan and the regional investment programs in accordance with the provisions of part (b) of paragraph 3 of Article 8 and of paragraph 1 of Article 12 of Regulation 715/2009 g) the sustainability of projects that are included in the Plan and their potential financing outside the framework of the Development Plan.”

The Development Plan includes projects that their construction is scheduled to begin within the timeframe of the Plan (i.e. for the period 2017-2026) as well as the Planned Projects that their construction has not been completed yet. The TSO substantiates the feasibility of the inclusion of the newly proposed projects in the Development Plan and includes information about the construction method, the estimated budget, the time schedule of the implementation, the way of financing the relevant investments as well as the cost recovery method. In the following paragraphs the projects of the Development Plan of 2017-2026 are presented, including for each project all the necessary elements arising from the Network Code for the regulation of NNGS (Article 92).

The Development Plan is structured as follows:

I. Projects that are included for the first time in the draft (Chapter 2.1) i. Projects for the Connection of Users ii. Projects for the Development of NNGS

NNGS Development Plan 2017-2026 Pg 5 of 45

II. Planned Projects (Chapter 2.2) i. Projects included in the approved Development Plan and their implementation is ongoing during the reference period of the current Development Plan ii. Projects included in the List of Small Projects and their implementation is ongoing during the reference period of the current Development Plan

III. Projects included in the Three-Year Development Period (Chapter 2.3)

According to par. 3 of article 92, the TSO is obliged to justify in the Development Plan any reasons for not including any planned project.

For each project a summary table of the following information is given, as presented below: type of project (Planned Project/New Project, the type of the investment (Pipeline, metering station, LNG/CNG, UGS, compressor, equipment for the transmission system and/or LNG facility), expected benefit (according to the criteria of art. 92 par. 2 of NNGS Administration Code as valid), the current status (under feasibility study, under technical study/authorization, under the process of award for the construction/ implementation, under construction), whether the Final Investment Decision has been taken or not, the current budget of the project and the part of which is considered maintenance capex, the estimated date that the project will be ready for operation 1.

Maintenance capex is considered to be any addition or replacement to NNGS assets in order the latter to be maintained in their initial operational capability as long as possible.

When new projects are included in the Draft Development Plan, their impact on the average usage tariff of the NNGS is calculated.

Furthermore, the financing plan and the recovery method of the investment are presented for each project.

Project Summary Type of project Type of investment Current Budget Of which Maintenance Capex Expected benefit Start date End date Connection Agreement with User (Projects for the connection of Users only) Resolution to Construct/FID Current Status of Project

1 The above mentioned definitions are described in the NNGS Network Code (Gov. Gazette 1549 B’ /5-5-17) NNGS Development Plan 2017-2026 Pg 6 of 45

Financing plan Recovery method Impact on the average tariff for the usage of NNGS (for new projects only 2)

Following the project summary of each project, a short description of the scope of it and any other necessary relevant information is given.

CHAPTER 1.1. COMPLIANCE OF NNGS DEVELOPMENT PLAN WITH ENTSOG’s TEN-YEAR DEVELOPMENT PLAN (TYNDP) AND GAS REGIONAL INVESTMENT PLAN (GRIP)

In compliance with Regulation 715/2009/EC Transmission System Operators are obliged to establish a regional cooperation in the framework of European Network of Transmission System Operators for Gas (ENTSO-G). Specifically, the TSO publishes every two years a non-binding ten years system development plan, as well as the gas regional investment plan (GRIP).

The purpose of these documents is to provide information to stakeholders about the new projects that will create opportunities for transporting natural gas in each country.

DESFA has taken into consideration the currently approved TYNDP 2017 as well as the latest GRIP for the NNGS Development Plan for 2017-2026 is compatible with the latest approved TYNDP as well as the approved regional investment plan.

CHAPTER 2: DEVELOPMENT PLAN 2017-2026

CHAPTER 2.1. PROJECTS INCLUDED FOR THE FIRST TIME IN DEVELOPMENT PLAN 2017-2026

CHAPTER 2.1.1. PROJECTS FOR USERS CONNECTION (art. 92 par. 4 Α(i) of the Network Code of the NNGS as applicable)

2.1.1.1. M station at SALFA Anthousa Project Summary Type of Project New Project Type of investment Metering station Current budget 0.45 million €

2 Projects that are part of the Development Plan for the first time NNGS Development Plan 2017-2026 Pg 7 of 45

Expected benefit Enabling access to new Users Start date Jun-17 End date May-18 Connection Agreement with User Yes (Projects for the connection of Users only) Resolution to Construct/FID Yes Current Status Under study Financing plan DESFA’s own equity Recovery method Connection Fee Impact on the average usage tariff of the 0% NNGS

The project is necessary according to the provisions of art. 5 par. 7 of Tariff Regulation (RAE decision 339/2016) as well as the relevant agreement of Public Gas Corporation “DEPA SA”. The project refers to the construction of a metering station which will be owned by DESFA in Anthousa. The estimated cost of the project is 450.000 €, and it will be ready for operation in May 2018.

2.1.1.2. M station at SALFA A. Liossia Project Summary Type of Project New Project Type of investment Metering station Current budget 0.68 million € Expected benefit Enabling access to new Users Start date Jun-17 End date Sep-18 Connection Agreement with User Yes (Projects for the connection of Users only) Resolution to Construct/FID Yes Current Status Under study Financing plan DESFA’s own equity Recovery method Connection Fee Impact on the average usage tariff of the 0% NNGS

The project is necessary according to the provisions of art. 5 par. 7 of Tariff Regulation (RAE decision 339/2016) as well as the relevant agreement of Public Gas Corporation “DEPA SA”.

NNGS Development Plan 2017-2026 Pg 8 of 45

The project refers to the construction of a metering station which will be owned by DESFA in A. Liossia. The estimated cost of the project is 680.000 €, and it will be ready for operation in September 2018.

CHAPTER 2.1.2. PROJECTS FOR NNGS DEVELOPMENT (art. 92 par. 4A(ii) of the Network Code of the NNGS as applicable)

2.1.2.1. New jetty for small Scale LNG in Revithoussa Project Summary Type of Project New Project Type of investment Equipment for LNG facility Current budget 30 million € Expected benefit Provisions of Directive 94/2014 for LNG fuel in shipping, development of NNGS Start date Jun-17 End date 2020 Resolution to Construct/FID No 3 Current Status Under study Financing plan DESFA’s own equity, CEF and NSRF 4 grants, EIB loan 5 Recovery method Inclusion in RAB(excluding possible grants) Impact on the average usage tariff of the 0% NNGS

The project will be an implementation of the ongoing studies under POSEIDON MED II.

POSEIDON MED II, under the auspices of the INEA(Innovation and Network Executive Agency), is part of the necessary steps towards adopting liquefied natural gas as a marine fuel in the Eastern Mediterranean, making Greece the focal point for supplying and distributing liquefied natural gas In Southeast Europe, implementing Directive 94/2014 / EU and Law 4439/2016 incorporating the above Directive into Greek law. In this action 26 partners from shipping and gas industry from three EU Member States are involved (Cyprus, Greece, Italy). The new jetty is planned to be constructed in the northern eastern part of Revithousa and will serve the operation of the loading to small ships (1.000 m 3 and up to 20.000 m 3). The smallest of them will supply boats, either coastal or seagoing shipping, to the port of . The larger ones will supply satellite LNG storage and distribution stations to other ports in Greece or abroad. The new jetty will provide for the mooring and simultaneous refueling of two ships.

3 To be taken after the approval of Development Plan and the decision for the financing of the project 4 Grants will be pursued 5 Loan will be pursued NNGS Development Plan 2017-2026 Pg 9 of 45

In the same project the addition of a small LNG loading arm and of relevant mooring equipment is included in order to allow the loading and unloading of small LNG ships from the existing jetty. The possibility of using the existing facility initially for the loading of small vessels will increase the relevant capacity of Revithoussa, with relatively low cost and will increase the operational flexibility of the installation. The basic design of the project is programmed to begin by the end of 2017 and the construction within 2019. The project is estimated to be in operation by the end of 2020. The cost of the project that will be included in the RAB is estimated at 30 mil. € and is not expected to increase the average usage tariff taking into consideration the preliminary demand estimations for the loading of vessels for the supply with gas of ships to the port of Piraeus or the supply of distribution networks in coastal areas as well as the expected grant. The grant amount is estimated at 40% (the exact amount will stem from the relevant study according to the procedures of PA).

2.1.2.2. Pipeline Nea Messimvria – Eidomene/Gevgelija and M/R station Project Summary Type of Project New Project Type of investment Pipeline Metering station Current budget 48.7 million € Expected benefit Development SEE market, increase of usage of NNGS Start date Jun-17 End date 2020 Resolution to Construct/FID No 6 Current Status Under study Financing plan DESFA’s own equity , Grants 7, EIB loan 8 Recovery method Inclusion in RAB(excluding grants) Impact on the average usage tariff of the 0% NNGS

The project aims at the interconnection of natural gas transmission systems of Greece and FYRoM which will enhance the diversification of supply sources for FYRoM. The latter one is currently solely dependent for the supply of gas from Trans Balkan Pipeline. DESFA and MER have signed a Memorandum of Understanding for the project in October 2016. Access to NNGS, and especially to the LNG terminal of Revithoussa can benefit market competition thus leading to lower prices for the supply of natural gas. Meanwhile the

6 To be taken after a) appropriate booking for transmission capacity by users b) the approval of Development Plan and c) the decision for the financing of the project 7 Grants will be pursued 8 Loan will be pursued NNGS Development Plan 2017-2026 Pg 10 of 45

project enhances the role of Greece as a hub and enables the participation of more natural gas users in the region. The required project within Greece is constituted from -A 55 km pipeline of 28 in with 70 barg design pressure and 66.4 barg maximum operating pressure starting from Nea Messimvria (downstream of the current compressor station) an ending to the Greek/FYRoM borders near Customs station of Evzoni. -A Metering/Regulating border Station, 2 Launcher Scraper Stations and 1 Receiver Scraper Station

Picture 1: Routing of the pipeline form Nea Messimvria to the boarder with FYRoM

The project is estimated to be in operation in 2020. The cost of the project that will be included in RAB is 48.7 M€, while the above inclusion does not increase the Average Tariff for the usage of NNGS with the assumption of appropriate grant for the project and booking of sufficient capacity from users.

2.1.2.3. Compressor Station in Ampelia Project Summary Type of Project New Project Type of investment Compressor Station Current budget 49 million € Expected benefit Efficiency of NNGS, effective operation in respect to prevent congestion Start date Jun-17 End date 2020 Resolution to Construct/FID No 9 Current Status Under study Financing plan DESFA’s own equity, Grants 10 , EIB loan 11 Recovery method Inclusion in RAB (excluding grants) Impact on the average usage tariff of the 1.630% NNGS 12

9 To be taken after the approval of Development Plan and the decision for the financing of the project 10 Grants will be pursued 11 Loan will be pursued 12 With grant assumption of 50% NNGS Development Plan 2017-2026 Pg 11 of 45

The project is necessary on the basis of the hydraulic simulation studies carried out by DESFA and given the expected increase in the transported quantities of natural gas from north to south with the start of the TAP pipeline and its interconnection with NNGTS in New Messimvria. The existing technical capacities at North Entry Points (Sidirokastro + Kipi) are considered to remain as of today. In order to ensure the stability and efficiency of the system, it is necessary to progressively increase its technical capacity with the installation of a compressor station at the southern part of Greece, which concentrates the larger part of the demand. The characteristics of the compressor station were preliminary identified to 10 MW (1+1) with the appropriate stab outs for a 3 rd unit to be installed in the future if the natural gas demand justifies it. The detailed characteristics of the unit will be defined during the basic design. The compressor will be designed to provide reverse flow as well. The cost of the project is preliminary identified at 49 M€. The cost will be included in RAB, and the above inclusion will increase the average tariff for the usage of the system by 1.630% assuming 50% financing from grant (the exact amount will stem from the relevant study according to the PA procedures).

2.1.2.4. Upgrading Projects of NNGS -3rd group Project Summary Type of Project New Project Type of investment Equipment on NNGS Current budget 2,12 million € Expected benefit Efficiency of NNGS, effective operation in order to prevent emergency situations Start date Jun-17 End date Mar-19 (projects 1,2 Table 1) Dec-19 (projects 3,6 Table 1) Dec-17 (projects 4,5 Table 1) Resolution to Construct/FID No Current Status (see Table 1) Financing plan DESFA’s own equity, NSRF grant 13 (for project no.1) Recovery method Inclusion in RAB Impact on the average usage tariff of the 0.132% NNGS

Table 1: Projects for the upgrade of NNGS operation

No. Investments Estimated Completion date Current status cost(€) 1 Implementation of 600.000 Mar-19 Under study training centre

13 Will be pursued NNGS Development Plan 2017-2026 Pg 12 of 45

2 Procurement and 300.000 Mar-19 Under study installation of Pipeline Integrity Management System 3 Upgrade of electrical 1.000.000 Dec-19 Under study switches for medium voltage and internal lighting in the control room of LNG facility 4 Procurement of special 40.000 Dec-17 Under award for equipment for detecting procurement corrosion and irregularities in natural gas pipeline 5 Upgrade of DCS in CHP 80.000 Dec-17 Under award for unit procurement 6 Upgrade of 100.000 Dec-19 Under Geographical implementation Information System (GIS) system

TOTAL 2.120.000 €

Τhe following paragraphs analyze the feasibility and the technical characteristics of the projects presented in table 1 above.

1. Implementation of training centre

In order to accommodate the training needs of his staff, DESFA plans to set up a Training Center for theoretical and practical practice of natural gas techniques. The development of such an infrastructure is the first in the Balkan region and can be used for the training of staff of other Operators with whom there will be cooperation. The cost of the project is estimated at € 600,000 with projected completion in March 2019.

2. Procurement and installation of Pipeline Integrity Management System

In order to prevent the potential risks of the facilities (Risk Management), the company will proceed with the development of a system for the integrity of the NNGTS transport network by supplying a Pipeline Integrity Management System (PIMS) based on the need and the requirements of DESFA and the possibility of updates and extensions. From 1 September 2017 and over a period of 6-7 months, the completion of the first phase of the project is expected, which includes the installing of software, the integration of data on a single basis for an initial number of NNGTS sections, and the pilot implementation of a risk model. For the next year, from March 1, 2018 to March 1, 2019, the installed PIMS will be extended to the entire transport network. The total amount required for the PIMS (Pipeline Integrity Management System) procurement and installation project is € 300,000.

NNGS Development Plan 2017-2026 Pg 13 of 45

3. Upgrade of electrical switches for medium voltage and internal lighting in the control room of LNG facility

It concerns the supply and replacement of medium voltage (6 kV) electrical switches at the LNG facility (60 pcs.) aiming at the smooth operation of the automation in the distribution of electricity and supply of medium voltage loads (motors and pumps). The upgrade study is in progress. The cost of the project is estimated at 1,000,000 with anticipated completion in December 2019.

4. Procurement of special equipment for detecting corrosion and irregularities in natural gas pipeline

It concerns the procurement of special Portable Non - Destructive Testing (NDT) equipment for field - specific detection and assessment of corrosion and discontinuities such as cracks, stresscorrosioncracking (SSC), lamination, inclusions, etc. in the pipelines and containers of the NNGTS, which will contribute to the upgrading of the NNGTS integrity inspection and evaluation services. The cost of the project is estimated at € 40,000 and will be completed by December 2017.

5. Upgrade of DCS in CHP unit

It concerns the upgrading of the DCS of CHP in Revithoussa in hardware and software, the installation, programming and commissioning. The addition of the third tank substation and the new equipment of the 2nd LNG upgrade will make the upgrading necessary until the end of 2017. The cost of the project is estimated at € 80,000.

6. Upgrade of Geographical Information System (GIS) system

The project will further develop DESFA’s geographic database in order to fully integrate assets and their efficient performance through gis-web applications to the end users.

The cost of the above projects that will be included in RAB is 2.12 mil. € and the above inclusion will increase the average tariff for the usage of the system by 0.132%.

2.1.2.5. Upgrade of physical protection of DESFA facilities - Physical Safety Control Center Project Summary Type of Project New Project Type of investment Equipment of NNGS Current budget 1.2 million € Expected benefit Efficiency of NNGS, effective operation Start date Jun-17 End date Dec-19 Resolution to Construct/FID No Current Status Under study

NNGS Development Plan 2017-2026 Pg 14 of 45

Financing plan DESFA’s own equity Recovery method Inclusion in RAB Impact on the average usage tariff of the 0.080% NNGS

NNGS facilities are considered as European critical infrastructure. Possible shutdown or destruction would have a significant impact on the country and Europe-wide. The aim of the project is to upgrade the physical security of all DESFA infrastructure due to the rapid development of the technological applications in the sector and the establishment of a Physical Security Control Center covering the requirements of the Directive 2008/114/EC concerning critical infrastructure security, which was incorporated into the Greek law with Presidential Decree 39/2011. The aim is to prevent, mitigate and eliminate risk threats (examples include theft, sabotage, terrorism, accidents, and natural phenomena). The project includes: -Implementing a vulnerability study of all DESFA installations and developing an Infrastructure Safety Management Plan - Compilation of Technical Specifications of Safety Systems and Physical Security Control Center - Installation of security systems in DESFA infrastructure including pipelines (eg CCTV systems, tamper detectors, alarms, headlamps, access control, DAS, drones, etc.) - Development and operation of a Physical Security Control Center for the management and coordination of the security systems of the Infrastructure. The cost of the above projects that will be included in RAB is 1.2 mil.€ and the above inclusion will increase the average tariff for the usage of the system by 0.080%.

2.1.2.6 Improvement of metering accuracy in NNGTS stations Project Summary Type of Project New Project Type of investment Equipment of NNGS Current budget 0,2 million € Of which Maintenance Capex 0,2 million € Expected benefit Efficiency of NNGS, effective operation Start date Jun-17 End date Nov-18 Resolution to Construct/FID No Current Status Under study Financing plan DESFA’s own equity Recovery method Inclusion in RAB Impact on the average usage tariff of the 0.014 % NNGS

NNGS Development Plan 2017-2026 Pg 15 of 45

In the context of the public consultation of the Development Plan 2016-2025 it was pointed out that in some distribution networks due to reduced consumption there are differences between the amount of gas resulting from the sum of the metering systems of the distribution networks and the quantity of gas measured in the Metering/ Regulating stations that make up the corresponding Distributed Network Exit Point (SIDD) of the NNGTS. DESFA, as stated with no. 100240 / 13.12.2016 letter to RAE, pledged to examine the matter and come back with a project proposal to a next Development Plan or List of Small Projects. DESFA examined the issue and it results in 17 Metering/Regulating stations the turbine meters operate for a substantial amount of time outside of their approved metering rates. This occurs due to the low consumption rates in the distribution networks that are connected to the relevant SIDDs’of NNGTS. In order to resolve the problem it is proposed to replace said turbine meters in 17 stations with new ones that combine improved operational features such as lower Qmin requirement and improved minimum / maximum flow ratio-from 1:20 to 1:50. The project will be in operation in November 2018. The cost of the project that will be included in RAB is 0.2 million € and said inclusion will increase the average tariff for the usage of NNGS by 0.014 %

2.1.2.7. Replacement of Metering and control systems on M/R stations of NNGTS Project Summary Type of Project New Project Type of investment Equipment of NNGS Current budget 4,5 million € Of which Maintenance Capex 4,5 million € Expected benefit Efficiency of NNGS, effective operation Start date Jun-17 End date Dec-19 Resolution to Construct/FID No 14 Current Status Under fstudy Financing plan DESFA’s own equity, Recovery method Inclusion in RAB Impact on the average usage tariff of the 0.252% NNGS

The proposed project concerns the replacement of the Measurement Management and Supervision / Control Systems in thirty (30) existing Metering (M) and Metering / Regulating (M / R) Stations, in order to achieve:

- the compatibility with each other as well as with the under upgrade stations as presented in the planned projects 2.2.1.10 and 2.2.1.11 herein, through similar equipment and software as well as similar architecture, achieving on the one hand direct economies of scale on the one hand by maintaining a smaller number of required spare parts and

14 To be taken after approval of Development Plan NNGS Development Plan 2017-2026 Pg 16 of 45

consumables and on the other hand by the support services of these systems during their operational phase,

- the separation to the maximum extent of the Measurement Management System from the Supervision /Control System at NNGTS Stations, achieving (a) the stations’ measurement data to be collected in the SCADA of the Control and Load Distribution Centers (KEKF ) of DESFA directly - without intermediate processing - by the certified Multi-Stream Flow Computers which will be installed in the framework of this project at the NNGTS stations and (b) by extension the optimization of the services provided by DESFA under the requirements of european and national regulatory framework (publication of data, quantities distributions Natural Gas Users, pricing), and

- to ensure the operation of the Measurement Management and Supervision / Control Systems of the Stations for the next decade as the equipment and software at these Stations operate on average for a decade and is expected not to be supported by the manufacturers in the coming period.

The replacement of the Measurement Management and Supervision / Control Systems in the Stations of DESFA refers to the following elements: • SCADA • programmable Logic Controller – PLC • flow computer • gas chromatograph, and • equipment of local stations network

The project is expected to be completed in December 2010. The cost of the project which will be included in the RAB is equal to 4.5 mil. € and said inclusion will increase the average tariff for the usage of NNGS by 0.252 %.

2.1.2.8 New building for DESFA’s headquarters

Project Summary Type of Project New Project Type of investment Equipment of NNGS and LNG Current budget 11 million € Expected benefit Efficiency of NNGS Start date Jun-17 End date Dec-19 Resolution to Construct/FID No 15 Current Status Under study Financing plan DESFA’s own equity Recovery method Inclusion in RAB Impact on the average usage tariff of the 0 % NNGS

15 To be taken after approval of Development Plan and when an appropriate building is found. NNGS Development Plan 2017-2026 Pg 17 of 45

DESFA headquarters are now housed in a rented building. It is considered that today, due to the conditions prevailing in the Greek real estate market, that it becomes economically desirable for DESFA to acquire a privately-owned headquarters building, which will constitute a company's fixed asset, contribute to the saving of operating expenses and ensure improved health and safety of work. The office area is planned to be approximately 6,500 square meters in line with the existing DESFA headquarters. The goal is to avoid burdening the NNGS users due to the savings that will be achieved, mainly by the rental cost. It is also estimated that there will be energy savings due to higher energy specifications of the new building. From the quantification of the above in a timeline of 20 years, according to the Billing Regulation, it is considered possible to purchase a building with a total cost of up to 11.000.000 € including possible modifications, and not lead to an increase in the Average NNGS usage fee. The purchase will be completed within 2019, including possible modification works.

Effect on the Average Tariff for the Usage of NNGS

The inclusion in the RAB of the above mentioned projects (2.1.2.1- 2.1.2.3) increases the Average Tariff for the usage of NNGS by 3.53%. The benefit achieved from the above mentioned projects compensates for the increase.

CHAPTER 2.2. PLANNED PROJECTS

CHAPTER 2.2.1. PROJECTS INCLUDED IN THE APPROVED DEVELOPMENT PLAN 16 AND THEIR IMPLEMENTATION IS ONGOING IN THE REFERENCE PERIOD OF THE CURRENT DEVELOPMENT PLAN

2.2.1.1. Construction of High Pressure Pipeline from Mandra Attikis to the Facility of ELPE in Elefsina for the Connection with NNGS and Relevant Metering Station Project Summary Type of Project Planned Project Type of investment Pipeline Metering Station Current budget 5.9 million € Expected benefit Enabling access to new Users Start date Nov-12 End date Sep-18 (for M/R) Connection Agreement with User Yes Resolution to Construct/FID Yes Current Status Under construction (for M/R) Completed (for the pipeline)

16 Decision No 64/2017/27-1-2016 by RAE concerning the “Approval of NNGS Development Plan 2016- 2025”. NNGS Development Plan 2017-2026 Pg 18 of 45

Financing plan DESFA’s own equity Recovery method -Connection Fee by User -Inclusion of the remaining amount to RAB

The project consists of the construction of a: • Pipeline of 6.5 km and 10 inch diameter which will start from line valve “Mandra” of the main pipeline and will end in the facility of Elefsina Refinery of ELPE SA • Metering station that is currently installed in an area provided by ELPE within the Elefsina Refinery.

2.2.1.2. Construction of High Pressure Pipeline Mavromati (Vagia)-Larymna and necessary Metering Station for the Connection of LARCO GMM SA with NNGS. Project Summary Type of Project Planned Project Type of investment Pipeline Metering Station Current budget 17,5 million € Expected benefit Enabling access to new Users Start date Jun-13 End date Dec-20 17 Connection Agreement with User Pending Resolution to Construct/FID No 18 Current Status Under technical study/permitting Financing plan DESFA’s own equity, possible EIB loan, possible grant Recovery method -Connection Fee by User -Inclusion in RAB (excluding grants)

The project consists of: • Pipeline of 36 km and10 inch diameter which will start from the main natural gas pipeline line valve station “Mavromati (Vagia)” and ends up in the facility of LARCO in Larymna. • Metering station that will be installed in land provided by LARCO

Technical studies as well as licenses procedures for the project are expected to be finalized in January 2019 in order for the project to be in operation by the end of 2020. These studies are carried out under DESFA’s contract with LARCO for the “Elaboration of studies for the connection of the installations of LARCO SA with NNGS”.

17 Connection Agreement has not been signed yet 18 Pending necessary contractual commitments by the applicant User .Until then the project is not included in RAB NNGS Development Plan 2017-2026 Pg 19 of 45

2.2.1.3. Compression Station in Kipi Project Summary Type of Project Planned Project Type of investment Compressor Current budget 70 million € Expected benefit Technical adequacy of NNGS, increase of flexibility of NNGS Start date 19-Jul-07 19 End date -20 Resolution to Construct/FID No 21 Current Status Under technical study 22 Financing plan Not defined yet Recovery method Not defined yet

The project aims at increasing the Transmission Capacity of NNGS and to enable supply of larger natural gas quantities to the greek market as well as to transit gas to european markets via NNGS to the region of Komotini and/or via new gas projects which are foreseen to be developed in the region (IGI, IGB).

The project is included in the PCI list that was elaborated by the EC of November 2015 (Delegated Regulation 89/2016).

Considering that the market needs are not defined yet the size of the compressor station is indicative. However in the case of maximum flow for transit projects 3 compression units with centrifugal compressor and a turbine (2+1) of 9,7 MW each will be installed.

As DESFA has stated in previous Development Plans, the compressor could operate with smaller capacity. This could be required to serve only the Greek market west of Komotini and for requests for import of gas from Turkey for quantities above the current technical capacity of the 4.3 mNm3/ day, and / or to ensure reverse flow to the Sidirokastro in cases of increased flow or increased delivery pressure, according to the relevant simulation studies.

The preliminary budget for the project is 70 million € including the upgrade of the current existing metering station in “Kipi”, as well as a regulating station at Komotini for the regulation of pressure. This station is necessary to be installed along with the compressor in order to protect NNGTS from the change of maximum operating pressure at Komotini. The time schedule of the project depends on the request of the market for imports of gas through Entry Point Kipi or the request for reverse flow quantities.

19 Approval time of basic design 20 Construction decision t has not been taken 21 Final construction decision will be taken when there will be strong data supporting the necessity of the project, and especially commitments from the Users of the infrastructure. The cost of the project is not included in the RAB 22 The technical study has been completed / preliminary authorization for the case of maximum flow NNGS Development Plan 2017-2026 Pg 20 of 45

It is obvious that the implementation and the time of the project’s completion are dependent from the import of gas through the Entry Point Kipi or the possibilities for reverse flow in NNGS. At the moment there are no indications for the necessity of the project.

2.1.1.4. M/R Station in Komotini Project Summary Type of Project Planned Project Type of investment Metering Station Current budget 7.5 million € Expected benefit Security of supply Start date 19-Jul-07 23 End date -24 Resolution to Construct/FID No 25 Current Status Under technical study Financing plan Not defined yet Recovery method Not defined yet The project consists of Metering/Regulating station in Komotini for the foreseen connection of NNGTS with transit projects (IGB, IGI etc.) in case these are implemented.

The preliminary budget of the project is 7.5 million €. The time schedule for the completion of the project is dependent to the request of the Users and the booking of Transmission Capacity according to the provisions of the NNGS Network Code.

2.2.1.5. M/R Station in N. Messimvria for the Connection of NNGTS to TAP Project Summary Type of Project Planned Project Type of investment Pipeline, Metering Station Current budget 10 million € Expected benefit Security of supply Start date 19-Jul-07 26 End date 2019 Resolution to Construct/FID No 27 Current Status Under award for the basic design study Financing plan EIB loan, own equity, possible grants Recovery method Inclusion in RAB (excluding possible grants)

23 Approval time for the basic design 24 Resolution to construct has not been taken yet 25 Same as before. The project’s cost has not been added to RAB 26 Approval time for the basic design 27 To be taken after the decision for the co-financing of the project NNGS Development Plan 2017-2026 Pg 21 of 45

According to the provisions of the Host Government Agreement (HGA) in section 7.2a and those in paragraph 4.7.4 of Joint Decision of Greek, Albanian and Italian Regulators for the exemption of TAP from articles 9, 32, 41(6), (8) and (10) of Directive 2009/73/EC (Decision of RAE 269/2013 Gov. Gaz. 1833/29.07.2013) at least one (1) Tie In Point between NNGS and TAP pipeline should be realized, with a technical capacity of 10 mil. Nm 3/ day and bi-directional flow capability. The cost of construction of the above mentioned investment, based on the exception decision, will be covered by DESFA and will be recovered through the tariffs of the Users of the National Natural Gas System.

In this contexts, a study was conducted by DESFA to find the optimal interconnection point from a technical and economic point of view, which resulted to be Nea Messimvria. The study was submitted to RAE. According to the regulatory framework the tie in point must be bidirectional. Flow from TAP to NNGTS due to the difference in the operating pressure (93 barg and 66,4 barg accordingly) requires only the installation of a Metering/Station. However, flow from NNGTS to TAP requires also the installation of a compressor station. The preliminary budget of the project is 10 million € and includes a) engineering-procurement-construction of the Metering/Regulating station b) engineering-procurement-construction of a small connecting pipeline between the two systems c) purchase of land for the M/R and compressor station in the long-term. With the proposed investment the uni-directional flow from TAP to NNGTS is secured (1 st phase of the project) and it is foreseen the land acquisition where the compressor station will be installed in the future (2 nd phase of the project) enabling full bi-directional flow in the interconnection. The project is included in the PCI list of November 2015. The FEED study is co-financed from Connecting Europe Facility (CEF). The detailed time schedule and cost will be available during the execution of the FEED study, which is ongoing. EPC of the project will be awarded after the approval of the co-financing of the project from Partnership Agreement 2014-2020.

2.2.1.6. Komotini-Thesprotia High Pressure Pipeline (part of NNGS) Project Summary Type of Project Planned Project Type of investment Pipeline Current budget 1100 million €28 Expected benefit Diversification of supply sources, security of supply Start date 19-Jul-07 29 End date -30 Resolution to Construct/FID No 31 Current Status Under technical study 32

28 Preliminary estimation for the case of maximum flow 29 Approval date of basic design 30 Resolution to construct has not been taken yet 31 Same as before. The project’s cost has not been added to RAB NNGS Development Plan 2017-2026 Pg 22 of 45

Financing plan Not defined yet Recovery method Not defined yet

Komotini-Thesprotia pipeline project consists of high pressure pipeline (80 barg), 613 km length and 42 inch diameter. The proposed routing of the pipeline starts from the industrial area of Komotini in Rodopi Prefecture and ends near the coast of Thesprotia Prefecture. The project consists also of above-ground facilities that are necessary for the safe operation such as Operation & Maintenance center, two compressor stations (one in Komotini and one in N. Mesimvria), metering and regulating stations, line valves stations, scrapper trap stations and telecommunication equipment. The pipeline is designed in a way to enable a potential future supply of customers in the adjacent urban areas along the routing.

2.2.1.7. 2nd Upgrade of LNG Terminal on the Island Revithousa Project Summary Project Type Planned Project Type of investment LNG facility Current budget 147 million € Of which Maintenance Capex 1 million € Expected benefit Increase of NNGS flexibility, security of supply, enhancement of competition Start date 09-Apr-10 End date Sep-18 Resolution to Construct/FID Yes Current Status -Under engineering-procurement- construction (3rd tank) Under engineering-procurement- construction (send out rate, M/R Ag. Triada) - Under a tender procedure for the supply and installation of buffers and a competitive tender for the construction of the bases and other infrastructures for the installation of two (2) binders (QRMHs) of ships (marine facilities) Financing plan -Grants NSRF 2007-2013 (35%) -EIB loan (80 M€)- Own equity (remaining cost) Recovery method Inclusion in RAB (excluding grants)

The scope of the project includes:

32 The technical study has been completed/ preliminary authorization for the case of maximum flow. Environmental terms are not approved yet. An update of the studies is required. NNGS Development Plan 2017-2026 Pg 23 of 45

a. Increase of storage space of the station with the installment of a new tank of 95.000 m3capacity With the addition of the 3rd tank the total storage space will be increased, from 130.000 m3 to 225.000 m 3 and the available storage space for Users will be increased from 110.000 m3 to about 200.000 m 3 (i.e. 82%) The installation of the 3rd tank will enhance the safety in the case of a cut-off for the northern entry points. The technical solution that is chosen to be constructed is the one with the highest safety standards and the minimum visual disturbance. b. Upgrade of marine to accommodate larger ships The marine works will enable the mooring of larger ships with a capacity of up to 260.000 m3 (Q-max) in comparison to the up to date capacity equal to 140.000 m 3 . As a result it will be feasible the mooring of all types of ships. The project is expected to enhance competition due to the realization of increased LNG transportations. Further to that Users will be benefitted from the fact that greater range of LNG carriers will be able to be accommodated while the transportation cost per unit of LNG will be decreased as the cargo volume is increased. Consequently, the project is expected to lead to lower gas prices for consumers. c. Upgrade of gasification rate The project will include the installation of cryogenic equipment that will increase the rate of gasification in normal conditions (Sustained Maximum Send-out Rate) (i.e. without the use of backup equipment), from 1.000 Nm 3/h LNG 33 that is today, to 1.400 Nm 3/h LNG (i.e. an increase of 40%). The auxiliary equipment of 250 Nm 3/h LNG will remain in use. The proposed upgrade of the gasification rate will increase the rate of gasification in normal operating conditions (Sustained Maximum Send-out Rate) from 12,47 million Nm 3/d to 19,15 million Nm 3/d, while in a case of emergency (i.e. use of backup equipment), this rate can be up to 22,57 million Nm 3/d. The technical solution that is chosen for the increase of the gasification send-out rate is the addition of an Open Rack Vaporizer, which is the most environmentally friendly solution. Also three sea water pumps will be replaced, and other works will be performed on piping facilities.

The project includes the necessary mechanical modifications in the existing unloading arms in order to be able to reload LNG to large ships (at least 20.000 m 3). The above reloading rate is 2.400 m 3 LNG/hr.

33 1 m 3 of LNG= 570 Nm 3 of Natural Gas NNGS Development Plan 2017-2026 Pg 24 of 45

Picture 2: Aerial view of terminal station with the installation of the 3rd tank

d. Upgrade of Ag. Triada Metering Station This project is considered to be a necessary complement to the upgrade of the gasification rate as stated above and refers to the upgrade of the metering station in Ag. Triada

Progress of the project Construction works of the third tank started on 1st of June 2014 while the EPC contract has been awarded. Also, the upgrade of the gasification rate and the metering station in Ag. Triada has been started. The upgrade of the marine facility is under tender procedure for engineering-procurement-construction. The completion of the entire project is expected in September 2018 according to the current time schedule. The expected budget is 147 million €.

DESFA has requested financing of the project from NSRF in order to minimize the impact on tariffs of the investment. The approved grant rate (public expenditure) is 35% of the eligible costs via Public Investment Program (PIP) under NSRF. The amount of the total budget that will not be co-financed by NSRF (65%) will be covered by own equity and loan. DESFA has received a loan from EIB. The cost of the investment that will not be subsidized will be added to the RAB.

2.2.1.8. 2nd Upgrade of Boarding Metering Station (BMS) of Sidirokastro Project Summary

NNGS Development Plan 2017-2026 Pg 25 of 45

Project Type Planned Project Type of investment Equipment of transmission system Current budget 3.3 million € Of which Maintenance Capex 2.3 million € Expected benefit Security of Supply, Efficiency of NNGS, effective operation, enhance of competition Start date 15-May-12 End date Sep-17 (for item i) Resolution to Construct/FID Yes Current Status Under construction (i) Completed -In operation ii, iii iv) Financing plan DESFA’s own equity Recovery method Inclusion in RAB

The project includes: i) the remote control of Border Metering Station (BMS) in Sidirokastro through Supervisory Control and Data Acquisition (SCADA) system from the Gas Control Center in Patima and the Back up Control Center in Nea Messimvria. The remote control is possible by upgrading and automating sub-systems of the Station, that are considered to be technologically out of time and by upgrading the local monitoring & control system (Distributed Control System). ii) the replacement of the existing orifice meters with ultrasonic meters in order to be compatible with the requirements of measurement standards. The metering system has been constructed based on the standard ISO 5167:1991 iii) the upgrade of the supporting station utilities in accordance with the requirements of remote controlling, taking into consideration the life cycle of the installed equipment iv) the possibility of permanent reverse flow through BMS Sidirokastro, so that exporting of volumes from NNGS to Bulgaria will be possible in respect to either the European legal framework, concerning security of supply 994/2010/EC, or the 3rd energy package for the liberalization of the energy markets. The current budget of the project is 3.3 million €. Item (i) of the project as described above is expected to be finalized in September 2017. Items (ii) and (iii) were completed in 2016. The scope of work (iv) is competed and is ready to operate from late May 2014.

RAE based on this decision 452/2013 has approved the joint proposal of DESFA and Bulgartransgaz for the reverse flow in Sidirokastro interconnection point, according to ar. 7 of Reg. 994/2010/EC. According to that proposal the cost of the investment for the reverse flow (abovementioned item iv) regarding the Greek system is 1 million € and relevant cost for the Bulgarian system is 0.5 million € (this will be performed by Bulgartransgaz).

Τhe investment cost relating to the NNGS (for the whole project including scope of work (iv)) will be covered by DESFA’s own equity while the recovery of the investment will be made through the transmission tariffs.

NNGS Development Plan 2017-2026 Pg 26 of 45

2.2.1.9. Upgrading of Electrical and Electronic Equipment, Billing System and Equipment SCADA Field in Stations M/R of 1st generation (1995-2000) Project Summary Project Type Planned Project Type of investment Equipment of transmission system Current cost 3.5 million € Of which Maintenance Capex 3.5 million € Expected benefit Efficiency of NNGS, effective operation Start date 16-May-12 End date Dec-17 Resolution to Construct/FID Yes Current Status Under engineering-procuement- construction Financing plan DESFA’s own equity Recovery method Inclusion in RAB

The project refers to 15 stations of NNGS (M VFL, M/R PPC Komotini, M/R EKO, M/R Platy, M/R North, M/R Larissa South, M/R , M/R North, R Ano Liossia, M/R Athens East, M PPC Lavrio, M/R Thriassio, M/R Athens West, M Agia Triada, M/R Inofita) of which the existing equipment for metering and managing invoicing and signaling has overpassed a 10 year operation period thereby creating maintenance problems due to both unavailability of spare parts from manufacturers and equipment compatibility issues. The SCADA Field equipment in these Stations is non-merchantable (available) by the manufacturing company, which has no longer stock of spare parts, making the maintenance of equipment costly or impossible in some cases. This results to the increase of operating costs and the low efficiency of the equipment. The investment will combine the use of common equipment to serve at the same time the operational needs of both the station and the system SCADA and will ensure the smooth operation of the equipment at the lowest possible operating cost, thus satisfying the main objective of the company for safe and reliable transport of natural gas. The current budget of the project is 3.5 million € and the project is expected to be ready for operation in December 2017. The investment cost will be covered by DESFA’s own equity while the recovery of the investment will be made through the transmission tariffs.

2.2.1.10. Extensions and Upgrades of Metering Stations of North and East Thessaloniki Project Summary Project Type Planned Project Type of investment Equipment of transmission system Current cost 2 million € Of which Maintenance Capex 0.6 million €

NNGS Development Plan 2017-2026 Pg 27 of 45

Expected benefit Efficiency of NNGS, effective operation Start date 16-May 12 End date Aug-17 Resolution to Construct/FID Yes Current Status Under engineering-procurement- construction Financing plan DESFA’s own equity Recovery method Inclusion in RAB

The metering - regulatory stations North and East of Thessaloniki are designed to be installed in two phases. The first phase (which has been implemented), included the installation of two lines for regulating and metering (one in operation and one in a standby mode), while the second phase provides installation and setup of a third-line of regulating and metering (two in operation and one in standby mode). The maximum capacity that was created on the first phase has been used several times in peak loads and therefore the upgrade of the two stations is considered to be necessary, in order the back-up intended degree of the equipment to be ensured, assuring the security of supply of natural gas consumption. The project includes the design, supply and installation of the third metering control line on the existing stab outs as well as all the electrical and electronic component equipment. It also includes the SCADA upgrade of North and East Thessaloniki metering stations, whose equipment is old resulting in the creation of maintenance problems. The current budget of the project is 2 million € and the project is expected to be ready for operation in August 2017.

2.2.1.11. Upgrade the System of Fixed Communication of NNGS Project Summary Project Type Planned Project Type of investment Equipment of transmission system Current budget 4.5 million € Of which Maintenance Capex 4.5 million € Expected benefit Efficiency of NNGS, effective operation Star date 30-Sep-11 End date Dec-17 Resolution to Construct/FID Yes Current Status Under engineering-procurement- construction Financing plan DESFA’s own equity Recovery method Inclusion in RAB

The system of fixed communication of NNGS currently consists of fiber optic cable alongside the NNGS, eighty-four (84) knots multiplexing optical fiber gas stations to serve

NNGS Development Plan 2017-2026 Pg 28 of 45

local needs, communications (telephony, remote control & operation, computer field networks and offices), networking equipment in twenty-four (24) gas stations as well as seven (7) call centers located in the Centers of Operation and Maintenance (O&M) and the LNG terminal Revithousa. Also, the management centers for multiplexing hubs, of telephone exchanges and network equipment are located in Patima’s Ο&Μ Center.

Communications via fiber-optic are based on technology multiplex-type TDM / PDH and have a total capacity of 34 Mbps, that even though it was adequate when installed (1996), it marginally covers the current needs of DESFA and will not be able to meet the future ones. Indicatively, for the purposes of the internal computer network and closed circuit television channels of natural gas stations, the connection with agencies O&Ms 100 - 1000 Mbps is required.

Additionally, the call centers that serve today the NNGS are no longer commercially available and their support by the manufacturing company expires in the forthcoming years.

The new branches use IP (IP over Ethernet, VoIP, Modbus TCP / IP) systems (FTS, telephone network, SCADA). The choice of technology offers significantly cheaper solutions, with more development options and expansion capabilities, and better utilization of proprietary fiber optic network. IP technology is the one currently used in new telecommunications networks and will be used for the next 15 years. To meet these needs, it is advisable to install new fiber optic multiplexing technology with a capacity of 1-10 Gbps. The capacity requirements are not the same in all parts of the NNGS. The estimated total budget for the project is 4.5 million € and is expected to be ready for operation in December 2017.

2.2.1.12. IT & Telecommunications Projects Project Summary Project Type Planned Project Type of investment Equipment of transmission system Current budget 1.6 million € Expected benefit Efficiency of NNGS, effective operation Start date 31-May-10 End date Dec-17(Project No. 1) Dec-18 (Project No. 2) Resolution to Construct/FID Yes Current Status Under award Financing plan DESFA’s own equity Recovery method Inclusion in RAB (excluding grants)

These projects are related to investments for the development of applications that will facilitate the operation of the company and will upgrade the level of services provided by DESFA. Those projects are presented in Table 2.

NNGS Development Plan 2017-2026 Pg 29 of 45

Table 2: IT Development applications

No. INVESTMENTS COST(€) COMPLETION CURRENT FINAL DATE STATUS INVESTMENT DECISION 1 Balancing platform 100.000 Dec-17 Under Yes award procedure 2 Integrated IT 1.500.000 Dec-18 Under Yes System for Natural award Gas - IISNG procedure TOTAL 1.600.000

In the following paragraphs the feasibility and technical characteristics of the applications that are presented in Table 1 are analyzed.

1. Balancing platform

In April 2014 the Regulation 312/14/EC concerning the balancing of natural gas in the transmission networks (Balancing Code), bookings of transmission users, balancing fees as well as information from/to the TSO. This includes, among other things, rules and measures relating to the operational balancing of the Transmission System, daily transmission Users' declarations, daily disruptive charges and the provision of information to and from DESFA.

The regulation at the stage of full implementation sets out the basic principles for the creation and development of a balancing scheme of the Transmission System, based on gas market rules. Transmission Users actively participate in the daily balancing of their portfolios by buying and selling standard products at marginal values defined in the Virtual Trading Point (VTP). For the achievement of the above it is necessary to create an electronic balancing environment (balancing platform), and a Virtual Trading Point (VTP) in accordance with the provisions of Art. 47 of the Balancing Regulation.

Through this electronic environment, it will be possible to carry out transactions of natural gas between pure traders and between Transmission Users and Operators for balancing purposes, without being necessary the booking of transmission Capacity to the NNGS.

By enhancing liquidity on the market, the Balancing Platform will gradually evolve into a Trading Platform, as defined by the Balancing Code. The above actions aim at creating a "GasHub" with the transition to a new model of European specifications market. The estimated budget is 100.000 € and it will be ready for operation in December 2017.

2. Integrated Information System for Natural Gas - IISNG The purpose of the project is the development, installation and commissioning of the Integrated Natural Gas Information System (INGS), which is to be the main communication / transaction platform between DESFA and NNGS Users as well as between NNGS Users / Selected Customers based on the provisions of the Network Code.

NNGS Development Plan 2017-2026 Pg 30 of 45

The IISNG is a regulatory obligation for DESFA under National and European Regulatory Framework for the Gas Market.

The IISNG consists of: a) The Electronic Information through which the management of the primary market for NNGS capacity is implemented (eg booking of transmission capacity and gasification capacity, daily reporting, calculation and notification of quantity allocations, LNG facility storage management, tariffs for the usage of NNGTS and LNG etc.) b) the Electronic trading system, through which the secondary market is managed (eg. the transferring of Booked Transmission Capacity, submission of proposals, accepting the transfer of Booked Transmission Capacity or the transfer of Booked Gasification Capacity). Through IISNG, actions that must be daily conducted both by DESFA and Users are automated, resulting to the drastical reduction of the time of completion and of error occurrence.

Furthermore, through IISNG Users can be informed about the quantity transmitted through NNGS in order to balance their portfolio.

The budget of the project as described above is estimated at 1.5 million € and the completion date is December 2018.

2.2.1.13. Upgrading Projects of NNGS -1st group

NNGS Development Plan 2017-2026 Pg 31 of 45

Project Summary Project Type Planned Project Type of investment Equipment on NNGS Current budget 2.097 million € Of which Maintenance Capex 2.097 million € Expected benefit Efficiency of NNGS, effective operation Start date 31-May-10 End date Mar-19 (project 1 Table 3) Sep-18 (project 2 Table 3)

Resolution to Construct/FID Yes for the 2 nd subproject No for the 1 st subproject 34 Current Status Award of engineering-procurement- construction process (projects no. 1, 2 Table 3) Financing plan DESFA’s own equity, PA 2014-2020 grants for the 1 st subproject Recovery method Inclusion of cost in RAB

These projects upgrade the operation of the NNGS. Table 3 presents these projects in a more analytical way.

Table 3. Projects for the upgrade of the operation of NNGS

No. INVESTMENTS COST (€) READY FOR CURRENT STATUS OPERATION DATE 1 Upgrade of 1.900.000 Mar-19 Under award of engineering- SCADA in procurement-construction dispatching process centers 2 Design, supply, 197.000 Sep-18 Under award of engineering- installation, procurement-construction system design of process daily gas flow TOTAL 2.097.000 €

34 Except for project “Upgrade of graphical environment of SCADA in control centers”. FID will be taken after the decision for the cofinancing of the project. NNGS Development Plan 2017-2026 Pg 32 of 45

Each one of the proposed investments in Table 2 is described in the next paragraphs.

Project Summary

1. Upgrade of SCADA in dispatching centers The project includes the procurement , installation and operation of a new SCADA system in the main dispatching center in Elefsina as well as in the back up dispatching center in Nea Messimvria. The new SCADA system in the Control Centers will replace the current system, which began trading in 2006, and will provide DESFA with new tools for managing graphic images, database, system alarms, historical data, and so on. It is noted that the equipment of the existing SCADA Control Center system is not supported by the manufacturing company, which no longer holds a security reserve for it. The investment will enhance the utilization of the system's capabilities (user friendliness, better display of parameters, ease of designing new graphic images, etc.), improve the management of NNGTS within the European and Greek regulatory framework and ensure the Telepresence and remote control of NNGTS and its extensions for the next decade.

2. Design, supply and installation of a daily gas flow system design The establishment of a system for forecasting-planning-control of daily gas flow will provide DESFA the ability to:  estimate the volume of gas that will be transmitted,  increase the level of accuracy in the prediction of the volume  embody a regular review of the progress of the daily planning of gas and  adjust the levels of unexpected consumption or shortages in supply. The investment will:  unburden DESFA from operating costs (overtime of field staff, unnecessary start- up/shut-down of LNG terminal, Compressor N. Messimvria, etc.)  optimize the management of Users' reports and  provide daily justified gas flow plans.

2.2.1.14. Upgrading Projects of NNGS -2nd Group

Table 4. Projects for the upgrade of the operation of NNGGS -2nd group

NNGS Development Plan 2017-2026 Pg 33 of 45

Project Type Planned Project Type of investment Equipment of transmission and LNG system Current budget 0.345 million € of which Maintenance Capex 0.345 million € Expected benefit Efficiency of NNGS, effective operation Start date 28-Jun-12 End date Jul-19 (project 1, Table 4) Oct-17 (project 2, Table 4) Resolution to Construct/FID Yes Current Status Under construction (i) Under Technical Study (ii) Financing plan DESFA’s own equity Recovery method Inclusion of cost in RAB

No. INVESTMENTS COST (€) READY FOR CURRENT STATUS OPERATION DATE 1 Upgrade of the 280.000 Jul-19 Under technical study system for the corrosion protection of the NNGS 2 Restoration of the 65.000 Oct-17 Under award of construction visual monitoring /implementation process field system CCTV TOTAL 345.000 €

i. Upgrade of the system for the corrosion protection of the NNGS The project refers to the installation of defusing induced voltages, metering sensors of the corrosion speed and extension of the existing telemetry system for recording relevant measurements. The estimated budget is 280.000 € and the project is expected to be ready for operation in July 2019.

ii. Restoration of the visual monitoring field system CCTV The project refers to the installation of monitors, recording cameras in the Control Room of LNG terminal and their connection with the possibility of central management and recording. The estimated budget is 65.000 € and the expected completion date is October 2017.

NNGS Development Plan 2017-2026 Pg 34 of 45

2.2.1.15. Installation of M/R Κavala Project Summary Project Type Planned Project Type of investment Metering Station Current budget 3.9 million € Expected benefit Supply on new areas Start date 17-Oct-12 End date - Resolution to Construct/FID No 35 Current Status Under feasibility study Financing plan DESFA’s own equity 36 , possible grants Recovery method Inclusion of cost in RAB (excluding possible grants)

The project refers to the installation of an M/R 70/19 station in the area of Kavala line valve. The aim of the project is to supply the city of Kavala and the nearby cities of Palaio and Eleftheroupoli.

2.2.1.16. Upgrade of LNG Loading Arms at Revithoussa LNG Terminal Project Summary Type of Project New Project Type of investment LNG facility Current budget 1.2 million € Of which Maintenance Capex 1.2 million € Expected benefit Efficiency of NNGS, effective operation Start date Jul-17 End date Nov-18 Resolution to Construct/FID Yes Current Status Under feasibility study Financing plan DESFA’s own equity Recovery method Inclusion in RAB

The project scope is replacement of electrical and mechanical equipment of the LNG loading arms at Revithoussa LNG Terminal in order the LNG loading to be effected with equipment of modern technology. Latest technology electro pneumatic equipment shall be

35 The project has not received Resolution to construct. Time schedule will be in coordination with downstream connected systems. 36 DESFA will seek financing from EIB and PP for 2014-2020 NNGS Development Plan 2017-2026 Pg 35 of 45

installed as well. Additionally, maintenance of the existing cryogenic equipment shall be executed after 15 year operation. The project is deemed necessary for the safer and easier connection of the loading arms on the vessel (ship to shore connection) which is the most crucial and hazardous operation during LNG unloading. The project will be completed and operational in November 2018 with total budget equal to 1.2 mil. €.

2.2.1.17. Truck Loading Pilot Station Project Summary Type of Project New Project Type of investment LNG facility Current budget 6 million € Expected benefit Efficiency of NNGS, effective operation Start date Apr-16 End date Jul-19 Resolution to Construct/FID No Current Status Under engineering-procurement- construction Financing plan DESFA’s own equity, possible grant from PA 2014-2020 Recovery method Inclusion in RAB (ecluding grants)

The construction of a truck loading station will give the possibility to use natural gas in areas where the transmission system has not been developed yet (ex. West Greece). The result will be an increased gas consumption and more efficient use of the NNGS.

The market has soundly expressed interest for the said application during the public consultation of NNGS Development Plan for period 2013-2022. The station will be one point for trucks loading with a capacity of 50 m 3 and loading flow of 100 m 3/h. The project also includes: - Measurement of LNG loaded via weighbridge - Control of the truck loading station from the LNG Terminal Control Room and DESFA SAP system for the issuance of invoices and other required documentation - Traffic arrangements within DESFA property as well as on the access road to Revithoussa.

DESFA has performed a separate techno- economic assessment study, by an external consultant, in order to identify the optimum route for long trucks (approx. 16 m) from the LNG truck loading station in Revithoussa to a suitable point in the mainland.

Demand study for this new service is in the published NNGS Development Study for 2015- 2024. The estimated cost of the project derives from the Basic Design study.

NNGS Development Plan 2017-2026 Pg 36 of 45

The station is programmed to be completed in the end of 2018. The latter depends on the approval of the Development Plan and timely approval for the co-financing of the project from PA 2014-2020.

2.2.1.18. LNG Terminal Boil-off Gas Compressor Station Project Summary Type of Project New Project Type of investment LNG facility Current budget 5 million € Expected benefit Efficiency of NNGS, effective operation Start date Apr-16 End date Jul -19 Resolution to Construct/FID No Current Status Under study Financing plan DESFA’s own equity, possible grant Recovery method Inclusion in RAB(excluding possible grant)

The compressor will be installed at Revithousa LNG Terminal in order to receive boil off gas from LNG process in the tanks and piping instrumentation, convey via Ag.Triada Metering Station and inject them into the NNGTS.

The current necessary combustion of boil off gas in the flare when the LNG Terminal is not in operation will be terminated with this environmental friendly project.

The gas that is conveyed to the flare for combustion is approx. 3.500 kg LNG / h. The proposed project, apart from saving of LNG significantly for the users of the station is an important environmental benefit by eliminating the carbon dioxide emissions during the period of non- operation of the Terminal.

The budget of the project is 5 million € for the installation of a 400 kW reciprocating compressor, which will receive boil off gas from the two existing LNG tanks and the third tank which is being constructed. The project is estimated the project to be operational in December 2018, depending also on the approval for co-funding of the project.

CHAPTER 2.2.2. PROJECTS THAT HAVE ALREADY BEEN INCLUDED IN THE LIST OF SMALL PROJECTS AND THEIR IMPLEMENTATION IS ONGOING IN THE REFERENCE PERIOD OF THE SUBMITTED DEVELOPMENT PLAN

There are no projects in this category.

CHAPTER 2.3. PROJECTS OF THE THREE YEAR DEVELOPMENT PERIOD

NNGS Development Plan 2017-2026 Pg 37 of 45

According to the provisions of ar. 92 of the revision of Network Code (DESFA’s proposal Nov. 2015), Three Year Development period applies to projects for which the final Investment Decision (i) has been taken, (ii) is considered possible to be taken within three (3) years from the publication of the draft Development Plan in DESFA’s website. These projects are mentioned in Annex I.

CHAPTER 3. PLANNED PROJECTS THAT WERE NOT INCLUDED IN THE DRAFT DEVELOPMENT PLAN 2017-2026

DESFA, taking into account:

• developments in the field of enterprise recovery of corporate information systems after physical or malicious disaster, • the operational advantages and disadvantages of using cloud technology against the creation of a mirror site of the central Data Center in Patima in order to recover data and to have a business continuity of the company in the event of a disaster. • the cost of running, maintaining, and committing resources that will be created by mirror site creation, • the operational deprecation of the hardware that the company will acquire for the implementation of the mirror site of the central Data Center over time has decided to explore the possibility of using cloud services offered through an existing software licensing agreement to create a mirror site and not to include the project "Development of a disaster recovery plan and a mirror site" in the Draft Development Plan for 2017 -2026.

NNGS Development Plan 2017-2026 Pg 38 of 45

Annex I Summary Table of the Projects of the NNGS Development Plan 2017-2026, with distinct reference to the Three-Year Development Period (Article 92, par. 4D of the Network Code of NNGS)

NNGS Development Plan 2017-2026 Pg 39 of 45

No INVESTMENT COST (€) INCLUDED IN START DATE 37 READY FOR NOTES . THE 3-YR OPERATION DEVELOPMENT DATE PERIOD I. PROJECTS INCLUDED FOR THE FIRST TIME IN THE DEVELOPMENT PLAN Α. Projects for the connection of Users (art. 92 par.4Ai. of NNGS Administration Code as applicable) 1 M station at SALFA 450.000 Yes Jun-17 May-18 Anthousa 2 M station at SALFA 680.000 Yes Jun-17 Sep-18 A. Liossia Β. Projects for the Development of NNGS (art. 92 par.4Aii. of NNGS Administration Code as applicable) 1 New jetty for small 30.000.000 Yes Jun-17 2020 Scale LNG in the LNG terminal at Revithoussa 2 Pipeline Nea 48.7000.000 Yes Jun-17 2020 Messimvria – Eidomene/Gevgelija and M/R station 3 Compressor Station 49.000.000 Yes Jun-17 Dec- 20 in Ampelia

Implementation of 4 600.000 Yes Jun-17 Mar-19 training centre

5 Procurement and 300.000 Yes Jun-17 Mar-19 installation of Pipeline Integrity

37 The date a project is included in a Development Plan or List of Small projects

NNGS Development Plan 2017-2026 Pg 40 of 45

Management System 6 Upgrade of electrical 1.000.000 Yes Jun-17 Dec-19 switches for medium voltage and internal lighting in the control room of LNG facility 7 Procurement of 40.000 Yes Jun-17 Dec-17 special equipment for detecting corrosion and irregularities in natural gas pipeline 8 Upgrade of DCS in 80.000 Yes Jun-17 Dec-17 CHP unit 9 Upgrade of 100.000 Yes Jun-17 Dec-19 Geographical Information System (GIS) 10 Upgrade of physical 1.200.000 Yes Jun-17 Dec-19 protection of DESFA facilities - Physical Safety Control Center

11 Improvement of 200.000 Yes Jun-17 Dec-18 metering accuracy in NNGTS stations

12 Replacement of 4.500.00 Yes Jun-17 Dec-19 Metering and control systems on M/R stations of NNGTS

NNGS Development Plan 2017-2026 Pg 41 of 45

13 New building for 11.000.000 Yes Jun-17 Dec-19 DESFA’s headquarters

II. PLANNED PROJECTS Α. Projects included in the approved Development Plan and their implementation is ongoing in the reference period of the current Development Plan 1 Construction of a high 5.900.000 Yes Nov-12 Sep-18 pressure pipeline from Mandra Attikis to the facility of ELPE in Elefsina for the connection with NNGS and of the relevant metering station 2 Construction of high 17.500.000 No Jun-13 Dec-20 pressure pipeline Mavromati (Vagia) - Larymna and the necessary Metering Station for the connection of LARCO GMM SA with NNGS. 3 Compression Station 70.000.000 No 19-Jul-07 - Implementation dependent in Kipi on the interest of Users 4 M/R Station in 7.500.000 No 19-Jul-07 - Implementation dependent Komotini on the interest of Users

NNGS Development Plan 2017-2026 Pg 42 of 45

5 M/R Station in 10.000.000 No 19-Jul-07 2019 FID has not been taken yet N.Messimvria for the connection of TAP to the NNGS 6 Komotini Thepsrotia 1.100.000.000 No 19-Jul-07 - Implementation dependent H.P. pipeline (part of on the interest of Users NNFS) 7 2nd Upgrade of the 147.000.000 Yes 09-Apr-10 Sep-18 LNG Terminal on the island of Revithoussa

8 Upgrade of Boarding 3.300.000 Yes 15-May-12 Sep-17 Metering Station (BMS) of Sidirokastro 9 Upgrade of electrical 3.500.000 Yes 16-May-12 Dec-17 and electronic equipment, billing system and SCADA field equipment in M/R stations of 1st generation (1995- 2000) 10 Extensions and 2.000.000 Yes 16-May-12 Aug-17 upgrades of metering stations in Thessaloniki

11 Upgrade of the system 4.500.000 Yes 30-Sep-11 Dec-17 of fixed communication of the NNGS

NNGS Development Plan 2017-2026 Pg 43 of 45

12 Balancing platform 100.000 Yes Jul- 16 Dec-17 13 Integrated IT System 1.500.000 Yes 31-May-10 Dec -18 for Natural Gas 14 Upgrade of SCADA 1.900.000 Yes 31-May-10 Mar-19 graphical environment in control centers 15 Design, supply and 197.000 Yes 31-May-10 Sep-18 installation of a programming system for the daily gas flow 16 Upgrade of the system 280.000 Yes 28-Jun-12 Jul-19 for the corrosion protection of the NNGS 17 Restoration of the 65.000 Yes 28-Jun-12 Oct-17 visual monitoring field system CCTV 18 Installation of Μ/R in 3.900.000 No 17-Οct-12 - Time schedule is dependent Kavala on the time schedule of the downstream Connected System 19 Upgrade of LNG 1.200.000 Yes Mar-16 Nov-18 Loading Arms at Revithoussa LNG Terminal 20 Truck Loading Pilot 6.000.000 Yes Mar-16 Dec-18 Station 21 LNG Terminal Boil- 5.000.000 Yes Mar-16 Dec-18 off Gas Compressor Station

NNGS Development Plan 2017-2026 Pg 44 of 45

B. Projects that have already been included in the list of small projects and their implementation is ongoing in the reference period of the submitted Development Plan - Total 1.539.192.000 €

NNGS Development Plan 2017-2026 Pg 45 of 45