Public Disclosure Authorized

* ENVIRONMENTAL ACTION PLAN (EAP) Ofthe - XIAOSHANGYUAN- LANTIAN CLASS 11 MOTOR VEHICLE HIGHWAY 1I HIGHWAY PROJECT SHAANXI PROVINCE, PEOPLE'S REPUBLIC OF Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Shaanxi Provincial Transportation Department

May 1995 CONTENTS

1. INTRODUCTION I

1.1 General Description 1

1.2 Significant Environmental Inpacts 1

1.3 Consideration or Project Alternatives 1

2. ENVIRONMENTAL IMPACTS AND PROPOSED MITIGATION MEASURES 4

2.1 Signiricant EnvirounmentalImpacts 4 2.1.1 Location Issues 4 2.1.2 ConstructionPhase 4 2.1.3 Operation Phase 5

2.2 Proposed Mitigation Concepts and Measures 5 2.2.1 Design Phase 6 2.2.2 ConstructionPhase 9 2.2.3 Operation Phase 13

3. ENVIRONMENTAL MONITORING PLAN 14

3.1 Introduction 14

3.2 Monitoring Plan: Schedule, Parameters and Locations 14 3.3.1 Construction Phase 15 3.3.2 Operation Phase 16

3.3 Monitoring Organizations and Personnel 16

4. INSTITUTIONAL ARRANGEMENTS 18

4.1 Project Environmental Management and Supervision 18

4.2 Envirom-nental Training 19

4.3 Environmental Equipment 24 5. IMPLEMENTATION SCHEDULE AND COSTS 26

5.1 Inplementation Schedule 26

5.2 Summary or Costs 26

APPENDIX Key Elements or the EAP/EMP for the Proposed Xiaoshangyuan-LantianClass II Auto-only Highway

MAP I Locations or Sensitive Sites, Excavation Sites and Monitoring Sites

This document was prepared in English by ERM-Environomics,, under supervision of the Shaanxi Provincial Highway Survey and Design Institute, Xi'an, Shaanxi Province. ENVIRONMENTALACTION PLAN (EAP) XIAOSHANGYUAN-LANTIAN CLASS IIMOTOR VEHICLE HIGHWAY

1. INTRODUCTION

1.1 Geneml Description

1. The proposed Xiaoshangyuan- Lantian Highway project (XLH) is an integral component of National Highway No. 312 from Shanghaito Yining. It is also a key section of the Shaanxi province highway network. The highway links Shangzhoucity in Shangluo to Luolicun in (see Fgure 1.la).

2. The objective of the proposed XLH project is to provide a connecting link between the existing Shangzhou-Xiaoshangyuanand Lantian-Xi'an Class II roads, increase transport capacity and promote the economic development of Shangluo district. It is anticipated that the project will strengthen economic ties in the region, by facilitating transport of commodities and the transfer of technology.

3. The physicalcomponents of the project include constructionof a 48.28km long Class II motor vehicle highway, including: six tunnels with a total length of 2470m, the longest of which will be 1,670m; 7 large bridges, 22 mediumbridges and 12 small bridges. The project will entail acquiring 1575 mu (105 ha) of land, 880.3 mu (58.7 ha) of which is agricultural, and demolishing8923.3 me of buildingarea.

1.2 Significant Envis onmental impacts

4. Significant environmental impacts during project construction include temporary agricultural land disruption, soil erosion, and impacts on water and air qua;kty. Major anticipated operational impactsincludeairquality degradation, increase n background noise-levels and lead pollution to crops along the proposed alignment.

1.3 Considerationof Project Alternatives

5. The proposed alignment was selected from four alternatives (See Figure 1.3a) on the basis of minimizingboth soejo-econoinicand environmentalimpacts. The proposed alignment minimizes land acquisition, population displacement and elogical disturbance through, where possible, avoiding large land cuts.

1 N

'nS, X > *ii >iws4 a~. t / ' :' 7 04' laan TWiWn

xigp~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~i

l~~~~~~~~~~~~~~~~~~ - ( Yongji

J~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

- i - X .,-- Z i-rt Ato)zhshui ~~~~~~~~~~~~-Gild uah

, l;\ ttA X of f; eS ytiaA- /o

. , _ .~~7- LEGEND 9t etg.,,..

.- ;: d,- _ i t >$ ~ O Villa_eoTown f._ 0XIAOSILAMUIAN-LANIYTANISE3GHWiAY PROJECT

; l _ Proposed Expressxvay ...... _ ) _~_-> ...... _-i ENVIRONOM9fIlCS |Figure 1.1a L r $S>4 Railway ERMu li-4-mian Puhu/

0 ~~~~~~~~sqiaXiTngdianzi < ?;AL rt/ 7E Wangchuan o X

L D LTALrERATIVE11IVe uzi

OV TownMtihuguan

-PhuedRiapineuH

A< ~~~~~~~~~~~~~~~~Xiaosha.gyun

LEGEND ALTERNAJeVE IV

O Villne orT... _Mcihe~ = ~~~Pr~opsedRoeue _ ~~~~AlterrtattveRoute --- Tunnel(L67 hin) XIAOSHFANGYIJAN-LANTIAN HIGHWAY PROJECT

'

2. ENVIRONMENTAL IMPACTS AND PROPOSED MITIGATION MEASURES

2.1 SignifcanntE nvironmental Impacts

6. The major environmental impacts of theproposed XLH project are summarized below.

2.1.1 Location Issues

i. Relocation, Cultivated Land Acquisition and Social Disniption

7. The total cultivated area impacted by construction of the highway is 58.7 ha. A total of 16 villages will be affected as a result of agricultural land acquisition or resident displacement. Agricultural land acquisition will affect 361 families (a total of 1771 people) who will need to be compensated with land of similar or superior quality. In addition, 18.9ha of agricultural land will be temporarily disrupted where the topsoil will be removed and subsurface soil excavated to provide construction materials. The topsoil will then be replaced and the land restored to its original use.

:G. The road construction activities and operation may also impact access between communities and farmland for pedestrians and vehicles. The locations of sensitive sites and residential areas are shown in Map I appended to this report.

*9. Dctails of resettlement and land acquisition compensation issues are provided in a separate Resettlement Action Plan (RAP).

ii. Cultural and Historic Sites

10. Two historic sites were identified along the alignment during a survey of cultural and historic locations undertaken during the EIA (see Map 1). Neither of these are listed as protected and they will not be directly impacted by the proposed highway.

2.1.2 Construction Phase

11. Potential construction phase impacts include disruption of areas adjacent to construction locations and excavation sites, soil erosion, potential air quality degraation, and noise and vibration disturbance resulting from construction activities, blasting and transportation of construo.tionmaterials. Impacts on water course and water quality may also arise where bridges are constructed across water courses or sand is excavated from flood courses. Map I shows the locations of water course along the alignment.

12. Soil erosion is of major concem during the construction phase. It is anticipated that uncontrolled soil erosion due to construction activities will be approximately 8 to 12

4 times current erosion levels. Prevention measureswill be adopted cspeciallyat excavation and fill sites to minimizeerosion potential.

13. An eslimated, 135,107 ni of earth and 2,270,117 m3 of stone will be excavatcd with estimated utilization ratiosof 88 and 41.4 percent respectively. Therefore significant volumes of surplus will be generated and stockpiledal various locations along the alignimentwhich may contribute to soil erosion and disruptionof vegetation cover. Improper disposal of debris and carth miayalso lead to obstruction of water courses during nood periods. Adequatc and secure disposal of the anticipated excavation debris is a signilicant concern and shall be managedas discussed below.

2.1.3 Operation Phase

-' 14. Operation of the road may lead to air quality degradation and an increase in background noise levels. Backgroundair quality monitoringindicates that current pollution j IIlevels are withinClass II NationalAnmbient Air QualityStandards. No significantimpacts on atmospheric quality are anticipatedduring the operationphase. In the proposed tunnels, air quality is expected to meet Design Standards for Tunnels (JTJ026-90) wilicil stipulates a maximumii CO level of 150ppmunder normialoperating conditions.

15. Since the road is to restrict access to all but mnotorvehicles, the risk from mixed vehicle type accidents will be eliminated. Althoughindustrial development along the alignmentis minimal, the road's importance as a link between Xi'an and Shangzhou municipalityand as a component of the nationalhighway network will increase the risk of traffic accidents resulting in chemical and other hazardous materialsspills. Emergency response measures and surveillancefacilities along the propose highway and in the 1.67 km tunnel are planned to respond to spill incidents, and mitigate impacts on the ecological environment and human health.

16. An additional potential impact is a slight increase in lead content of green leaf vegetables grown along the alignmentwhich is anticipated to exceed National Food Hygiene Criteria after 20 years of highway operation.

2.2 Proposed Mitigation Concepts and Measures

17. Environmentalprotection strategies for the project area are as follows:

a. project design includes elements which optimize opportunities for environmental improvemiientand avoids or minimizes adverse environmental impacts. Where avoidance or minimizationis not possible, economically and technically feasible mitigation measures have been formulated and shall be implementedwithin a reasonable time frame;

5 b. environmental protection measures include mitigation of impacts during design, construction anicloperation phases of lhe project.

18. E:nvironmentalimprovement measures include upgrading existing dirt roads along routes used for transport of materials. This reduces fugitive dust and irnprbvcsrural traffic movement. In addition, diversion of throughtrafrli' form "'e center of villages will have a net positivc impact on air quality and noise levels within scititenients. It will also 1 serve to reducc congestion and the risk of accidents which may involve loss of human life or release of hazardous materials.

2.2.1 Design Phase

I i. EnvirominentalConsideration

19. The project was formulated and authorized in accordance with the "Three Synchronization" rule, whichi requires that all developimienltand construction projects incorporate environmentalprotection measures in planning, design, construction and j operation phases.

20. Environmentalfactors have been taken into considerationin order to ininimize visual impacts and the need tor physical alteration of the landscape, as well as impacts to natural resources, sensitive ecosystems, cultural resources, agricultural lands and populated areas.

ii. Route Selection

- 21. The alignment of the proposed Xiaoshangyuan-Lantianhighway was selected from among four alternativeson the basis of minimizingland acquisition, adverse air quality and noise impacts on sensitive sites and residential areas, as well as avoiding cultural relics and unfavorable geological conditions.

n22. In comparison with the other three alternatives, the proposed alignment is environmentallypreferable on the following points:

1. Ninety percent of die alignment is located in mountainarea, making useof favorable natural terrain along Qipanheand Lanqiaoheriver valley. As | a result, agricultural land acquisition, land excavation and land fill, and impacts on natural scenery are minimized.

X 2. The route is shorter thanthe other alternatives and makes use of the existing Class 11 road in some sections. Road construction is therefore shorter and disruption to the natural and socio-economicenvironment is minimized.

6 3. Six ttunelswith a totallengtlh of 2470m,including one, I ,670mlong, are desiginedat the scctions with unfavorable topography whicil reduce destruction of natiuralvegetation, topography and potential soil erosioninduced by large amount of' land CUland lanclfill.

4. Tlicrcare fewresidential areas along the alignmentand thealignment detours aroundpopulated areas. This reducesresident displacement, relocation and noisedisturbalce.

iii. SocialDisrupLion

23. Provisionshave been madein the projectdesign for residenitialareas aflfccted by lhe proposeddevelopment. Thcse includereducing right-of-way land requirementsand minimizing severanceor local access roads in selectinigtransportation routes.

24. Seven large bridges, 22 medium bridges and 12 small bridges have been incorporatedin theproject design as well as 16 crossingsto facilitateaccess to farmland, avoid commnuniityseparation and meel requirements of vehicle access.

iv. Soil Erosion

25. Topographicaland geologicalcharacteristics of the alignment require that both engineering solutionisand stabilization tlhroughafforcstation be adopted to reduce surface erosion and prevent land subsidence.

26. A totalof 3130m of slope protection, 20643mnof retaining walls (hIeightrange from 3-8m), and 119 culverts have been incorporatedin the engineeringdesign so as to avoid soil erosion, slope failure and facilitate natural drainage. Drainage courses and silt traps will also be installed on slopes and emnbankmentswhere appropriate to prevent slope collapse and sedimentation impacts on water courses or fields. Temporary and permanent drainage systems were designed to minimize soil erosion and alteration of hydrological regimes, including impactson irrigation and artificial ponds. Drainage channels will be properly lined where necessaryand directed to discharge ponds so as to avoid direct discharge to farmland.

27. An extensive landscaping program has been integrated into the engineering design, takinginto account topographicaland geological characteristicsalong the alignment, to prevent potential soil erosion due to construction activities and during operation. This program will be initiated from the very beginning of road construction. Where appropriate, grading and revegetation of cut slopes, ernbankrnents, median dividers, shoulders, closed borrow sites and waste soil mounds will be undertaken. Following the completion of activities at each site, grading will be undertakenand trees and grasses will be planted.

7 U~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ v. Dust/Air Pollution

28. Quarries, borrow areas and transportationroutes, as well as waste disposal sites have been identiried, taking into account the transportationdistance from the material borrow sites to constructionsites (see Map 1). Dust and atmosphericpollution impacts from these areas were evaluatedwith particular emphasisto protectionof environmentallysensitive locationssuch as residentialareas.

29. Ventilationmeasures have been incorporatedin the design of the longesttunnel to ensure adequate ventilationin order to avoid accumulationof pollutants such as CO ane NO,L. Eighteen c-flractor fans shall be installed at regular intervals within the tunnel to facilitate ventilation. Details are provided in the project engineeringreport.

vi. Water Pollition

30. Permanent and temporary drainage systems are incorporated in the project design to minimize surface water pollution and disturbance to irrigation channels and drainage systems.

31. Sanitary waste water facilities (septic systems) have been incorporatedin the service station design proposed at Muhuguan. This station includes re-fuelingfacilities. In order to prevent direct discharge to surface water bodies, contaminated runoff shall be collected into settling tanks prior to discharge.

32. Undergroundstorage tanks for gasoline and other hazardousmaterials shall be installed in a crypt with adequate monitoring facilities to detect leakage and prevent groundwater contamination.

vi. Waste Construction Material Disposal

33. Twelve debris disposal sites have been included in the project design to stockpile surplus construction materials. These will be covered with soil and restored for cultivation. One of the largest debris sites. located in Putao Valley. will be restored for agricultural use.

34. Debris from tunnel excavation and quarry activities will be used to upgrade existing access road surfaces especially those affected by transportationof construction materials or shall be used for other local constructionprojects.

8 vii. Noise

35. Other than considerationof alternativealignments, noise screening measures such as forest belts have been integratedin the design and bid documents. The proposed I alignmentselected has minimalnoise impactson sensitive sites and residentialareas. 1 viii. Flooding

36. Bridgesand culverts were adequatelydesigned to meet safe flood discharge requirements.

ix. Cultural Relics

37. In additionto route selection, the designphase included initial studies and relic site surveys undertak-enby SPAIto identifyexisting cultural sites and appropriateprotection measureswhere necessary.

2.2.2 ConstructionPhase

.. DustlAir Pollution

38. Roadsurfaces, excavation areas and constructionsites will be sprayedregularly and k-eptmoist as necessaryparticularly near towns, water resourcesand sensitivelocations in order to control fugitivedust. Existingdirt roads used for transportationof construction rnaterialswill be upgradedand widened, and where necessarypaved to accommodatetwo way truck trafficand reduce fugitivedust emission. Dirt road affectedby constructiontraffic will be sprayed regularlyto minimizedust.

39. Stock-pilesand storage areas will be covered or sprayed to prevent fugitive dust. Constructionmaterials will be covered during haulingto prevent unduedust or debris on roads.

40. Asphalt and concrete mixing equipment shall be fitted with dust collection facilitiesand located500 meters down wind of residentialareas. Work-erswill be provided with dust masks.

ii. Soil Erosion/WaterPollution

41. During the constructionphase, reasonableactions will be taken to incorporate good constructionpractices into the project implementationand avoid undue or long term disturbanceof farmlandand water courses.

9 42. Trees, shrubsand grasses will be plantedalong the roadsideand on side slopes as soon as the road bed is constructed. Afforestedareas that have been disruptedduring road construction will be recovered. Quarries and disposal sites will be afforested after site closure.

43. Constructionof bridge piers and materialexcavation from water courses will be avoidedduring the rainy season. Excavationand debris disposalsites will be graded and re-vegetatedwhere applicableto avoid slope failureand soil erosion.

44. In areas adjacentto surfacewater bodies, rivers and drainagesystems, surplus excavated materialdisposal shall be appropriatelycontrolled so as to prevent sedimentation and adversewater qualityimpacts. Excessstone and gravel will be removedto disposalsites to avoid obstructionto river courses. Temporarychannels or conduits shall be constructed where necessary to facilitateirrigation and drainage,during the constructionof permanent drainage systems. If the existing irrigation or drainage systems and artificial ponds are damaged, appropriate measures includingeither rehabilitationor reconstruction,shall be undertaken.

45. Reasonablemeasures shall be undertakento preventdirectdischarge of polluted water fromconstruction activities into rivers and irrigationchannels. Temporaryponds shall be placed where appropriatewithin construction areas to collectwaste water and run-off from constructionsites and settleout eroded soils beforedischarge to avoid sedimentationof water courses.

46. Storageareas for gasolineand other hazardousmaterials will be enclosedand shall include concreteslabs and brims to control potentialspillage.

iii. ConstructionCamps

47. Septic tanks will be installed at constructioncamp sites to prevent direct discharge of sewage to surface water bodies. Sewage sludge and domestic waste from constructionsites will be collected,used as fertilizeror appropriatelydisposed of following recovery of recyclablecomponents. Disposalsites shall be approved and secured to avoid environmentalcontamination or site failures. Septic tanks will be regularlyemptied.

48. Campdomestic solid wastes willbe collectedin containersand/or at designated areas and disposed of regularlyto safeguardsanitary conditions.

49. Drinkingwater at constructionsites shall meet China's nationaldrinking water standards.

10 iv. Noise and Vibration

50. Hearing protection for constructionworkers will be provided and constrdction activities will be prohibitedbetween 1Opmand 6am where residentialareas are within 200m of the site to avoid disturbance to local residents.

51. Constructionmachinery and trucks will be properly operated and maintained Devices for the control of noise will be properly equipped so as to control noise in compliancewith ChineseClass IV noise standardsfor urban areas and with class II standards in sensitive areas includingschools and hospitals.

52. Vibration monitoringwill be undertakenby environmentalsupervisors at each contract lot and mitigationmeasures will be properly adopted to rectify any detected damage as a result of vibration of construction machinery. Heavy machines will not be operated at the same time.

V. Conservation of Ecological Resources

53. Forestcd areas will not be used for material borrow sites. As far as possible use of arable land for borrow sites has been minimized. In arable lands selected for material borrow sites, fertile topsoil layers (30cm) will be removed and stockpiledand sub-soil shall be excavated for constructionmaterials. Followingcompletion of the excavation, topsoilwill be replaced and the area will be reverted to original uses.

54. Education of construction workers will be strengthened to protect natural resources, wild plants and animals. Poachingwill be strictlyprohibited. Constructiontrucks will be restricted to approved or designated roads so as to avoid damage to the farmland and pasture land.

vi. Cultural Relics

55. Construction work will be stopped immediatelyif fossils, coins, artifacts of value or antiquity, structures or other remains of geological or archaeological interest are discovered during construction. The Shaanxi ProvincialArchaeological Bureau and Shaanxi Provincial Archaeological Research Institute, will be duly informed in case of such discovery. A survey of the site will be undertakenby authorized personnel and necessary mitigation measures will be identifiedand implementedunder the supervisionof the Shaanxi Provincial Archaeological Bureau. Detailed action plans will be formulated for sites discovered where excavation is required.

56. A separate action plan for cultural relics preservation has been developed incorporating protection measures to avoid any adverse impacts during construction on the

11 two historic sites located near the alignmentand establishprocedures in the case of discovery of new sites.

vii. Risk Management

57. Goodconstruction practice is the mosL efTicientway to reduce risks of accident and fatalities. Relevant government regulations and standards regarding construction proceduresshall be followedstrictly uo guaranteecor,struction safety. Constructionvehicles shall have effective lights; lighting and safety signs will be installed on roads and intersectionsused during construction. Traffic control measures will be implementedat intersections,especially at access roads used for material transportation. Adequate traffic regulationswill be adopted and enforced for all constructionroutes.

58. During the construction, effective safety and warning measures shall be adopted to reduce accidents. Blastingtimes, signalsand guards shall be stipulatedaccording to Chinese regulations. People and vehicles in danger areas shall be evacuated in time. Careful and thoroughchecks shall be made before blasting. Safetylookout posts shall be set up so that people and vehiclesdo not pass through until blastingis completed.

59. Management and usage of blasting materials shall strictly follow safety requirementof the Public SecurityDepartment.

viii. Traffic and Transportation

60. Local constructionmaterials will be used as much as possible to avoid long distancetransportation. A totalof twelveborrow sites have been selectedat various locations along the alignmenteach serving a localizedsegment of the highwayconstruction.

61. Where sections of existing roads are used for transportationof construction materials, temporaryservice roads will be constructedas appropriateto alleviate congestion on existing roads. Identifiedaccess roads which are generally existingdirt roads will be upgraded by paving or widened where necessary to accommodatetwo way truck traffic. Improvementand upgradingof existingdin roads along routes used for transport of materials can improve rural traffic movementand reduce fugitive dust.

62. Adequate traffic control measureswill be implementedin consultation with Communicationsand Public Security Departmentsto avoid traffic congestionand accident risk-swhere trucks use existing highway. The contractor is required to provide adequate diversionsand signs where the constructioncrosses existingalignments.

63. A constructionmaterials transportationplan and schedulewill be formulated to avoid hauling activitiesduring peak hours especially on existing roads.

12 I

2.2.3 Operation Phase

i. Transportation Managementand Road Safety

64. The Public Security Departmentshall be informed prior to transportation of hazardous materials on the roadway, especiallywith regard to the nature of the hazard, and the time, routes and parling places of vehiclestransporting such materials. The vehicles and drivers will be checkedby the Public Security DepartmenL Pertinent danger signs will be posted on the vehicles indicating the nature of the hazard. Transport of hazardous material will be restricted to a limited number of off-peak hours. Hazardous material may not be transported together with passengers, or other goods.

65. The local Fire Department will responsible for responding to hazardous materials spills, fires or major accidents. Signs will be posted in environmentallysensitive locations such as residential areas and water courses in order to alert and warn drivers.

46. To minimize the riskl of accidents from operation of the highway, adequate signing and signalswill be maintainedindicating speed restrictions, location of entrances and exit ramps. Signs shall be set up in residentialareas, at river crossings and tunnels to alert drivers.

67. Within the 1.67km tunnel, in addition to ventilationmeasures, a surveillance | system and safety facilities will be installed includinglighting, electronic message boards, traffic signals, CO detectors and fire extinguishers.

68. Xiaoshangyuan-LantianAdministrative Division will be responsible for managingand maintainingsafety and service facilities along the highway.

* ii. Vehicle Management

69. Vehicles speeds on the highwayshall not exceed 80 km/h in flat areas and 40 km/h in mountainous areas.

iii. Noise

70. Sound barriers will be installedor other mitigation measures implemented at sensitive sites and impacted residential areas as included in the project design. Additional noise barriers shall be installed at locations where noise impacts are found to exceed * standards based on the results of monitoring. Noise impacts along Qinglingpu Primay - School, QingfengPrimary School and HeilongkouHospital are within Class II standards and thus do not require mitigation.

13 71. Blowingof vehiclehorns in posted sensitivesites shall be prohibitedat night. Speed restriction shall be imposedon vehiclespassing these sensitive areas at night time. The maximumenforced speed for large and mediumsized vehicles shall be 30 Km/h at night. Small sized vehicleswill be restricted to speeds below 60 Kmth at night

iv. Other

72. Land use planningcontrols will be implementedto prohibitconstructionof new residential areas and other permanent'buildings within 50 meters from the edge of the alignment. Migrationto the area near the roadsidewill be strictly controlled.

3. ENVIRONMENTALMONITORING PLAN

3.1 Introduction

73. The EnvironmentalMonitoring Plan of the project has been formulated in consultation with the Shaanxi Provincial Highway Survey and Design Institute and the Shaanxi ProvincialInstitute of EnvironmentalScience.

74. As detailed in the EIA report, the overall project impactswill be minimized due to sound planningand implementationstrategies on the part of the project proponents. An overall monitoringprogram has been formulatedin order to (i) ensure early detectionof conditionsthat necessitateparticular mitigationmeasures, and (ii) provideinformation on the progress and consequencesof mitigationmeasures.

75. The purposeof monitoringactivities during highway construction and operation is to determinethe influenceon air, noiseand vibration,and water qualityso that appropriate mitigation measures can be undertaken to alleviate any identified impacL Monitoring parameters,network distribution and frequencyhave been determinedaccording to the nature and locationsof potentiallysignificant impacts as well as results of the baseline monitoring program.

32 MonitoringPlan: Schedule,Parameters and Locations

76. Baselineenvironmental monitoring along the alignmentwas performedby the Shaanxi Provincial EnvironmentalMonitoring Center (SPEMC) between 1993 and 1994, which includedair qualitymonitoring, background noise levels, surface water quality, and soil and crop lead content monitoring.

77. In addition, a survey of habitat and wildlife along the alignment was undertaken. No ecologicallysensitive locations were identified.

14 78. A systematicmonitoring plan is presented in Table3.1. The detailed locations of monitoring sites are shown in Map L.

3.2.1 ConstructionPhase

i. Air Quality Monitoring

79- TSP will be monitored four times per year for 3 consecutivedays, once in the morning and once in the afternoon, by the environmentalmonitoring group of the Centrl Supervision Laboratory. Monitoring will be undertaken around the construction sites, quarry areas, material borrow sites and major roads used for transportation of construction materials. Monitoring results will be assessed in relation to Class II National Air Quality Standards (GB 3095-82).

80. Fugitive dust monitoring wil1be undertakenby environmentalsupervisors at each contract lot every 5-10 days. Dustpans will be placed in at least 6 sampling locations at construction sites, quarries and material borrow sites and major access roads. More frequent monitoringwill be undertakenduring the beginning stages of construction.

ii. Noise and Vibration Monitoring

81. Noise and vibration monitoring will be undertaken by environmental supervisors on a weekly basis, two-three times per day (once in the morning, afternoon and at night) at construction sites and major access roads for transportation of construction materials. Ad hoc noise monitoring will also be undertaken as appropriate. Noise monitoringdata will be assessed on the basis of National Urban Noise Standards (GB 3096- 93) Class 1I for sensitive sites and Class IV for residential areas. Vibration monitoring results will be analyzed based on National Standards of EnvironmentalVibration in Urban Area (GB 10070-88). Noise monitoring at construction sites will comply with Noise Standards at ConstructionBoundary (GB 12523-90).

iii Water Quality Monitoring

82. Water quality monitoringwill be undertaken by the environmental monitoring group of the Centi-alSupervision Laboratory at rivers near construction sites and where bridges are being constructed. COD, SS, DO, oil, temperature and pH will be monitored one month before constructionstarts and after this three times each year for two consecutive days.

I

15 3.2.2 OperationPhase

i. Air Quality Monitoring

83. MonitoringofTSP, NO. and CO wilt be undertakenat Luolicun,semi-annually for period of five consecutivedays, four times per day.

ii. Noise Monitoring

84. Regular monitoringwill be undertakento establishnoise levels and trends and enablethe need for additionalnoise mitigationmeasures to be assessed. Monitoringof noise levels at Luolicun will be undertakenfour times a year over a period of three consecutive days, at daytime and night time as well as ad hoc monitoringwhere appropriate. Resulting data will be assessed for compliancewith NationalStandards for Noise in Urban Areas (GB 3096-93 - standardsfor sensitivesites and areas borderingtrunk roads).

iii. Water Quality Monitoring

85. COD, SS, DO, oil, temperatureand pH will be monitoredthree timesper year i at Lanqiaoand Muhuguan,semi-annually for a period of two consecutivedays. 86. Followingaccidents involving spills of chemicalsor other hazardoussubstances monitoring of water quality impacts will be underaken as appropriate. Parameters, frequency and location wilt be determinedaccording to the nature of the incident

3.3 Monitoring Organizations and Personnel

87. An environmental monitoring office comprising five to ten monitoring * specialistsin the Central SupervisionLaboratory under SPTD will be establishedfor the purpose of implementing the environmental monitoring plan during construction and operation of the expressway. U 88. All the monitoring activities will be undertaken by certified experts as - appropriate in compliance with monitoring technical criteria issued by the National EnvironmentalProtection Agency (NEPA). With the exceptionof fugitivedust and noise, samplingand analysis of monitoringdata will be undertakenby the Central Supervision Laboratory. Fugitive dust, noise and vibration monitoring will be undertaken by - environmentalsupervisors at each contract lot who will be trained in the use of the - monitoring equipment

1 16 Table3.1 Environmental Monitoring Plan

AIR CONSTRUCTIONPHASE OPERATION PHASE TSP: - frequency:semi-annually, once in - frequency:four times per year for January and July, over a period of 5 3-onsecutive days; once in the consecutivedays and 4 times per day; morningand afternoon: - monitorinrgitems: TSP, CO. NO, as - monitoringsites: around well as meteorologicaldata; constructionsites. quarry areas and - monitoringsites: Luolicun accessroads: Fugitivedust: - at least 6 pans at each site: - every 5-10 days. more frequentat the beginningstage of constrution activities

NOISE CONSTRUCI'ONPHASE | OPERATIONPHASE

- Monitorinmitems: noise levels and - frequency:4 times a year. at daytime vibration: and night; - monitoringsites: at construction - monitoringsites: Luolicun sites. quarry areas. and major - ad hoc monitoring accessroads: - frequency:weekly, 2-3 times (morning.afiemoon and night)

WATER CONSTRUCTIONPHASE OPERATION PHASE QUALITY

- monitoringitems: COD. SS. DO. - monitoringitems: COD. SS. DO, * oil, pH. temperature: oil. pH, temperature: - monitoringsites: major water bodies - monitoringsites: 2 lI and where bridges are being - frequency:two times each year for constructed: a period of two consecutivedays. -frequency:three times per yearfor a! period of two consecutivedays: monitor one monthbefore the start of constructiofn _ |

17 4. INSTITUTIONALARRANGEMENTS

4.1 ProjectEnvironmental Management and Supervision

89. In order to ensurethe implementationof environmentalmeasures as stipulated in the EnvironmentalAction Plan (EAP), the following agencies have been assigned responsibilityfor environmentalissues during the constructionand operationphases.

90. ShaanxiProvincial Transportation Department (SPTD) has overall authority within the project. A Deputy Director of SPTD shall be responsiblefor the oveall project administration.The Directorof ShaanxiHighway Bureau (SHB) shall be responsiblefor the managementof the constructionand operationphases of the proposed project. The project headquarterslocated in Xi'an will have project responsibilityduring both constructionand operationphases. Withinthis overall frameworkan institutionalstructure for management of environmentalissues has been formulatedas describedbelow.

i. ConstructionStage

a. An Engineer's Office will be established within SPTD, with the chief supervisionengineer and three assistantengineers. One of the three assistant engineerswill be assignedclear responsibilityfor environmentalissues related to the project.

b. Under the Engineer's Officeat the project Headquarters(HQ), in additionto three divisions and one central supervision laboratory, an Environmental SupervisionUnit (ESU)will be established. One senior environmentalofficer and one environmentalexpert will be assignedin this Unit on a full time basis to develop appropriateenvironmental policies for the highwayconstruction, to guide environmentalstaff at district officesand environmentalsupervisors at contract lots where necessary, and to liaise with the Provincial EnvironmentalProtection Bureau (EPB) and the World Bankl

c. At the Xiaoshangyuan-LantianDistrict Office, one well trained full time environmentalstaff will be assignedto coordinateenvironmental supervisors at contract lots, to review project environmentalmonitoring data, report the environmentalsupervision results to the HQ and to liaise with local EPBs on project environmentalprotection issues.

d. At eachof the two contractlots. one environmentalsupervisor will be assigned to carry out the environmentalsupervision of the construction activities, ensurethat all protectionmeasures stated in the constructionbid documentsor addressedin the EnvironmentalAction Plan (EAP)are implemented,undertake

18 noise, vibrationand fugitivedust monitoringand to report the results of the environmentalsupervision to the district environmentalstaff.

91. Figure 4.Ja presents the organizational structure for environmental j managementof the Xiaoshangyuan- LantianHighway during constructionand Figure4. lb presents the roles and responsibilitiesof each organizationinvolved.

ii. Operation Stage

a. The Environmental Protection Office of SPTD consisting of three environmentalstaff will be responsiblefor overall environmentalmanagement of the Shaanxi II Highway Project.

b. Shaanxi Highway Bureau (SHB) will be responsible for environmental managementof the Xiaoshangyuan-LantianExpressway project. At SHB Headquarters,one Deputy Director will be responsiblefor the environmental issues related to the Highway. One staff at deputy chief level in the Maintenance Division under SHB will be assigned responsibility for environmentalprotection of the highway.

* c. Withinthe Xiaoshangyuan-LantianHighway Administrative Division, one staff will be responsiblefor environmentalprotection of the highway.

92. Figure 4.2a presents the organizational structure for environmental managementof the Xiaoshangyuan- Lantian Highway during operaion and Figure 4.2b presents the roles and responsibilitiesof each organizationinvolved.

4.2 Environmental Training

93. A comprehensivetraining program for the Shaanxi II Highway Project has been formulated within the overall project budget, part of which will be assigned to improving the expertise of environmentalstaff and ensure the implementationof the EnvironmentalAction Plan for the Xiaoshangyuan- LantianHighway Project. The level of training will be determinedby the qualificationof the staff. Appropriateforms of training will be selected to optimize the effects taking into considerationfinancial feasibility and duration of the training.

94. The overall training plan and schedule for the Shaanxi II Highway Project is proposed as follows:

a. The senior environmentalofficer at HQ who will head the ESU shall be sent abroad for two or three weeks, if necessary,to attend a seminar on

19 I~~~~~~~~~~~~~~I. 1 11 11 1 1 1 I 11 1I Ilhli 1111I

Shaanxi Provincial TransportationDepartment

Engineers Office |FShaanxi2 Hilhway Project I

Other Project Environmenta Central Laboratory Divisins SupervisionUnit

. t ~~~~~Environmentall [ nianitia oshangyuan MonitoringOffice |Highway District Office

Contract Lot ContractLot No. 1 No. 2

Figure4. la InstitutionalArrangement of the Lantian - XiaoshangyuanHighway During ConstructionPhase FIGURE4.18 TASKORGANISATION DIAGRAM ENVIRONMENTALMANAGEMENT TASKS DURINGCONSTRUCTION XIAOSHANGYUAN-LANTIANHIGHWAY SHAMNXIPROVINCE, PEOPLE'S REPUBLIC OF CHINA

Shaanxl ProvincialTransportation Department Staff:1 AssistantEngineer Tasks: - OverallResponsibility for Environmental Issues mlatedto Shaanxl2 HighwayProject

CentmlLaboratory EnvironmentalSupeivision Unit EnvironmentalMonitoring Office Staff:Senior EnvIronmental Officer (1) Staff:5-10 technicalstaff EnvironmentalExpert (1) Tasks: Tasks: - Implementationof TSPand - developappropriate environmental policies Waterquality monitoring tor highwayconstruction - DataTabulation and reporting - provideguidance to environmentalstaff at to districtoffice districtoffices and contract lots l - liaisewith EnvironmentalProtection Bureau l______jandWorld Bank

District Office Staff:Environmental officer (1) Tasks: - guideenvironmental supervisors at contractlots - review of environmenta1 monitoring data - reportingresults of environmentalmonitoring data to EnvironmentalSupervision Unit - liaisewith localEPBs on environmentalprotecton regardingthe project

Contract Lots {2) Staff:Environmental Supervisor (1 for eachcontract lot) Tasks: - environmentalsupervision of constructionactivities - ensureimplementation of protectionmeasures outlinedin bid documentand EAP ! - undertakenoise and fugitive dust monitoring - periodicreportng to districtenvironmental staff on resultsof environmentalsupervision l pISPTD I

II ______EnvironmentalProtection Office Environmental Director | MonitoringOffice

B _ |MaintenanceOffice DeputyDirector DeputyDirector

Xiaoshangyuan-eantian H hayighway AdministrativeDivision|

Figure4.2a InstitutionalArrangement of the Lantian - XlaoshangyuanHighway DuringOperation Phase 4 FIGURE 4.2B TASKORGANISATION DIAGRAM ENVIRONMENTALMANAGEMENT TASKS DURINGOPERATION XIAOSHANGYUAN-lANTIANHIGHWAY I SMHAANXIPROVINCE, PEOPLE'S REPUBLIC OF CHINA l f Shaanxi ProvincialTransportation Department DeputyDirector I~ l Central Laboratory SPTD EnvironmentalProtection Office EnvironmentalMonitoring Office l Staff. EnvironmentalStaff (3) l Staff:5-10 technicalstaff Tasks: Tasks: - Monitoringof air quality - responsiblefor overallenvironmental - water qualityand noise managementof the Shaanxi2 Highway - DataTabulation and reporting project I

Shaanxi Highway Bureau SHB SHB Mainenance Office Staff:SHB DeputyDirector (1) EnvironmentalStaff (1) at DeputyChief Level from maintenanceoffice Task: - DeputyDirector responsible for environmental issuesrelated to Xiaoshangyuan-LantianHighway - EnvironmentalStaff at maintenanceoffice assigned to dealwith environmentalissues

Xiaoshangyuan- Lantian Highway I Administration Division

Environmentalstaff (1) at Deputy Chieflevel responsiblefor environmentalprotection of the highway environmental management of highway projects and to learn about environmental management practices from administrations of various highways.

b. The environmentalexpert in the ESU, environmentalstaff at the districtoffice and several highwaydesigners and planners will be sent for environmental trainingwithin China for two to three months,if necessary. In addition, the ; two highestachieving experts duringtraining in Chinawill be sent abroad for two to three months' to receive extensive and advanced training on environmentalmanagement of highwayprojects, if such trainingcourses are not availablein China.

* c. Environmentaltraining courses of approximatelyone month's durationwill be undertaken in Xi'an to train engineers responsible for environmental supervisionrelated to the constructionof highwaysincluded under Shaanxi 11 Highway Project. The resourcepersons may be invited from Xi'an, other parts of China or from abroad.

4.3 Environrnental Equipment

i. Central SupervisionLaboratory

95. The Central SupervisionLaboratory will play a k-eyrole in environmental monitoringduring both constructionand operation,including air quality, water quality and operational noise. In order to carry out this monitoring program the list of priority equipmentshown in Table 4.3a was identifiedand will be purchasedas part of the project. The cost of procuring equipmentwill be shared between the various componentsof the Shaanxi11 Highway project.

ii. District-level Supervision

96. Equipment to measure local meteorologicalconditions along [le proposed alignmentwill be procured such as atmospherictemperature gauge, hydrometerand wind gauge. and provided to environmentalstaff at the districtoffice.

iii. Contract Section Supervision

97. Fugitive dust. noise and vibration monitoring will be undertaken by environmentalsupervisors and the followingpackage listed in Table 4.3b will be provided to each contractlot.

24 Table 4.3a EquipmentProcurement List for Central Supervision Laboratory

No. Name of Equipment Number I COD detector 1 2 Ultra-violetspectro-photometer I 3 TSP sampler 6 4 atmospheficsampler 6 5 CO detector 6 atomic absorption photometer 1 7 high-gradenoise detector 5

l8 t analyticalbalance 2

;| 9 -rvibration analyzer 1 10 monitoring vehicle 2 11 computerand related equipmentfor data analysis 1 12 vehicleexhaust monitoringequipment 13 other equipmentand apparatus for chemical analysis

Table 4.3b Equipment Procurement List for Each Contract Section laboratorv

Name of Equipment Set Unit Price # I ; ~~~~~~~~~(RMB)_

I i Noise level detector 5,000 2 Accelerometer 1 15,00 3 Fugitivedust collectionequipment I500 25

25 5. IMPLIENIENTATIONSCHEDULE AND COSTS

5.1 Inplecnentation Scheduile

98. Environmentalissues that require appropriateaddressing prior to inceptionof projectconstruction and operationhave been tak-eninto consideration during the designphase by Shaanxi Highway Survey and Design Instituteand ShaanxiHighway Bureau in close coordinationwitil ShaanxiProvincial Research Instituteof EnvironmentalSciences, Shaanxi ProvincialTransportation Department and variouslocal authorities.

99. Mitigationmeasures proposed for theconstruction period will be implemented by contractors during construction of the expressway. During the operation phase the Environmental Protection Office of SPTD will be responsible for implementationof miligationmeasures through the Shaanxi Highway Bureau Maintenance Office as appropriate.

5.2 Sumnuarvof Costs

100. A total ot 1.76 million RN'IBwill be providedfor implementationof the EAP. includingengineering measures. direct mitigationmeasures. environmental personnel training and equipment purchiase. Tlis does not include environmental training. equipment procurementfor the CentralSupervision Laboratory and Culturalrelics protectionwhich has been assigned an overail budget shared between the six components of the Shaanxi 11 HighwavProject. A'NummaiJ detail of proposedexpenditures is presentedin Table S.2.

IU

U

U

. 2 I ' Table 5.2 Stmmary Costs of E.iviroitieuital Action Plait

Phase Actions Qulantity Cost ('OOORMB) Resource lmplementatio Remarks 1. Nlitigntlon 1leasures 1. Environmentalprotection design 80 Projectpre- SHDSI DesignPhase construction 2. Environmentaldesign of the budget . expressway 3. Soil erosion 50 Project Contractors engineering budget

4. Spray rticks 2 2000 _ 5. Domesticwaste water treatment 10 40 (septictanks) ConsiructionPhase 6. Coveringof constructionmaterial 30 stockpilesand storageareas

7. Constructionmaterial transporiation 50 covering(tarpaulin) S. Subsoilremoval, land reclamation 265 mu 300 . ._ and afforestation_ Operation 9. Comprehensivelandscape engineering 2 km 100 Project SHB Phase Management Maintenance and Division Maintenance ______Budget I-.- I I - - - - I______- ~- - - -

2.Environnientil 13.Construction period 160 Project Environmental Maonihoring supervision Monitorina budget Officel Environmental Supervisorsat contractlots 14.Operation period 747 Project Environmental Management Monitoring and Otflce Maintenance .______Bud g etet Sub-total 1757 3. Actiorusrur the 15. Environmentaltraining 400 Project SPTD 5 peoplewill overallShaianxi II training be trained lhighway Project _ budget abroad 16. Equipment procturenment 1466.5 Project SPTD equipment budget 17.Cultural relics protection 5000 Pre- SPAI . construction .______J ______I______budget __bdge .- lI l Il| 1 111Iii lii11 _ 111111

Appendik I Key Elements(fr the EAP/ENIPfor tile ProposedXiaosharigyuan-Lbntin Highway

Environmental Issues Action Taken/To he Taken ResponsibleEntity Remarks A. DesignPhasc 1. Environmental Theproject was formulated and authorized in accordancewith the 'Three ShaanxiProvincial Considerations Synchronization'rule which requires all developmentand construction projects Transportation incorporateenvironmental protection measures in planning,design, constriction and Department(SPTD) operationphases.

2. RouleSelection Thealignment was selected from amongfour proposedalternatives so as to minimizeSPTD landacquisition, impacts of air pollutionand noise on residentialareas, as well asto avoid cultural relicsand unfavorablegeological conditions. 3. SocialDisruption 2 largebridge, 22 mediumbridges, 12small bridges and 16crossings have been ShaanxiHighway Survey incorporatedinto the projectdesign in orderto minimizeseparation and Isolationof and DesignInstitute communitiesdue to the projectconstruction and meetlocal populationand vehicle (SHSDI) accessrcquirements. 4. Soil Erosion 3,130mof slope protection,20,643m of retainingwalls and 119culverts were SHSDI incorporatedin the engineeringdesign in order to facilitatenatural drainage and avoid soil erosionand slope failures. 6 tunnelswill also be constructedto reduce disturbanceto the Qinling mountains.

Treesand grasseswere designedto be plantedon mediandivider, sideslopes and alongthe roadside,where appropriate.

Temporaryand permanentdrainage systems were designedto minimizesoil erosion andalteration of hydrologicalregimes, including impacts on irrigationand artificial ponds. l l l l l lll ll l l l l

Environmental Issues Action Taken/To he Taken ResponsibleEntity Remarks 5. Dust/Air Pollution In additionto actionsregarding route selection, quarries, borrow areasand transportationroutes, as well as wastedisposal sites were identified. Dust and atmosphericpollution impactsfrom theseareas were evaluatedwith particular emphasisto protectionof environmentallysensitive locations such as residential areas.

6, Water Pollution Sanitarywaste water facilities (septicsystems) were designed for servicestations in SHSDI order to preventdirect dischargeto surfacewater bodies.

Undergroundstorage tanks have been designed to be Installedin a crypt to prevent groundwatercontamination. 7. Flooding Bridgesand culvertswere adequatelydesigned to meetrequirements of safe SHSDI dischargeof flood. 8. Culttiral Relics In additionto actionsregarding route selection, the designphase included initial ShaanxiProvince studiesand relic site surveys,identificatioci, avoidance and excavation planning ArchaeologicalInstitute wherenecessary. 9. Tunnels Ventilationsystems were adequatelydesigned at the 1670kmlong tunnelto avoid accumulationof pollutantsin the tunnel.

B. Consiruction PhiaEe 1. Dust/Air Pollution Roadsurfaces, excavation areas and constructionsites will be sprayedregtilarly and Contractors kept moistas necessaryfor dustcontrol particularlynear towns, waterresources and sensitivelocations. Dirt accessroads will he upgradedand wherenecessary paved, thoseaffected by constructiontraffic will be sprayedregularly.

Asphaltand concretemixing equipmentwill be fitted with dust collectionfacilities and located500m down wind of residentialareas. Workerswill be providedwith dust masks. urn- -l

Environnientall.ssues ActionTaiken/To he Takeni ResponsibleEntity Rernarks 2. Soil Erosion/Water Erosioncontrol will beachieved by minimizingvegetation removal and exposed Contractors Pollution surfacesuntil required by constructionand by othererosion prevention measures. Excavationsites will he reclaime<,stabilized and re-vegetated following cessationof activities. Temporaryponds shall ba placedwhere appropriate within construction andlexcavation areas to capturesurfiace drainage and settleout erodedsoils. In areasadjacent to surfacewater bodies, rivers, and drainagesystems surplus excavatedmaterial disposal shall beappropriately controlled so as to prevent sedimentationand adversewater quality impacts. Temporarychannels or conduitsshall he constructedwhere necessary to facilitate irrigation and drainage,during the constructionof permanentdrainage systems. All reasonablemeasures shall be takento preventdirect diischargeof pollutedwater from constructionactivities into riversan d irrigationchannels. Wastewater and run-off from constructionsites will ho collectedand settledbefore discharge to water courses.

Constructionof bridgepiers and materialexcavation from water courseswill be avoidedduring the rainy seaotn. Drainageinterception facilities will be installedat bridgesto preventpolluted run-off from enteringwater courses.

Storageareas for gasolineand olher hazardousnuterials will he enclosedand shall includeconcrete slabs and brims.

3. ConstructionCamps Adequatemeasures, such ILa provision of septictanks shall be tundertakenat Contractors constructioncamp sites to preventdirect dischargeof .sanitarysewage to surface water bodies. - - -. ------m - - - - m -

Environtmental lssues Action Itiken/To he Tuken Respornibie Enlity Remarks Sewvagosludge and domestic waste from construction sites will be collected to be used as fertilizer or disposed of foilowing recovering of recyclable components. Disposal sites shall be approved and secured to avoid environmental contamination or site failures. Septic tanksshall beregularly emptied.

Drinking water at construction sites shall meet China's national drinking water standards. 4. Noise Hearing protection for construction workers will be provided and construction Contractors activities will be prohibited between 1Opmand 6am. Construction machinety and tricks wvillbe properly operated and maintained.

5. Ecolog'ical Resources Foresis will not he used for material borrow sites. Where arzble land is occupied by Contractors the alignment, topsoil shall be mtOovedand tised for reclamation. Where arable landt is selected for material borrow sites, fertile topsoil will be removed and stockpiled and suh-soil excavated for construction materials. Following completion of exc%vation,topsoil will be replaced and the area will be revetted to original uses.

Education of construction workers will be sIrengthened io proleCt natural resources, wild plants and animals. Peachingwill be strictlyprohibited.

Construction t(ncks will be restricted to approved or designated roads so as to avoid damage to the farms and pasture lands. 6. Cultural Relics Work

During the construction,effective safety and waming measuresshall be adoptedto reduce accidents. Blasting times, signals and guards shall be stipulated according to Chinese regulations. People and vehicles in dangerous areas shall be evacuatedin time. Careful and thorough checks shall be made before blasting. Managementand blasting materials usage protocols shall strictly observe Public Security Department requirements. S. Traffic and Local sources will be used as much as possible to avoid long distance transportation Contractors Transportation of construction materials, particularly soil and rock.

Adequate traffic control measures will be implementedwhen roads are congested during the construction period. The contractor is required to provide adequate diversions and signs where the constructioncrosses existing alignments.

C. Openratinnal Phase 1. Transportation The Public Security Departnmentshall be informed prior to transportation of Shaanxi Highway Bureau Management hazardous materials on the roadway, especially with regard to the nature of the (SHB) hazard, and the time, routes and parking places of vehicles transporting such materials. The vehicles and drivers will be checked by the Public Security Department. Pertinent danger sign will be posted on the vchicles indicating the nature of the hazard. Transport of hazardous material will be restricted to a limited number of off-peak hours. Hazardous material may not be transported together with passengcrs, or other good. The local Fire Department will be responsible for responding to emergencies involving hazardous materials spills, fires or major accidents. Signs will be posted in environmentally sensitive locations in order to alert and warn drivers. Environmenlal Issues Action Taken/To he Taken Responsible Entity Renarks 2. Noise Soundbarriers will be installed or other mitigationmeasures implementedat sensitive sites and impacted residential areas as included in the project design. Additional noise barriers shall be installed as appropriate. Speed and horn restrictions will be enforced in residential areas. 3. Others Land use planning controls will be implementedto prohibit construction of new residential areas and other permanent buildings within S0 meters from the edge of the alignment. Migration.to the area near the roadside will be strictly controlled.

4. Service Stations Solid waste and waste water from service stations will be collected and treated. Septic tanks shall be installed for sanitary sewage, solid waste will be disposed of at secure landfills. D. Environpsental Monitoring 1. Atmosphere (I) Construction period: TSP: Environnental (a) monitoring items: TSP, fugitive dust Monitoring Office (b) monitoringfrequency: 4 times a year, 3 daystterm (EMO) (c) monitoringsites: constructionsites, quarry areasand access roads Fugitive dust: (2) Operation period: Environnental (a) monitoring items: TSP, CO, NO. supervisous (b, monitoring frequency: 4 timesa year, 5 days/term (c) monitoring site: 7 EMO ll~~~~~~~~Il l I i

Environmental Issues Action Taken/To be Taken Responsible Entity Remarks 2. Noise (I) Construction period (a) monitoring items: noise levels and vibration Environrnental (b) monitoring frequency: every two days and ad hoc noise and vibration supervisors monitoring (c) monitoring sites: sensitive sites within 100m of construction sites, along access roads

(2) Operation period (a) monitoring frequency: twice a year for a period of 3 days EMO (b) monitoring site: Luolicun 3. Water Quality (I) Construction period EMO (a) monitoringitems: COD, SS. pH. oil, temperature (b) monitoring frequency: 3 times a year, 2 days/term (c) monitoring sites: Lanqiaoxiang, Muhuguan

(2) Operation period (a) monitoring items: COD, SS. pH. oil, temperature (b) monitoring frequency: 2 times a year, 2 days/term (c) monitoring sites: Lanqiaoxiang, Muhuguan /~~~~~~~~~

Hjj."~ 0~ ~ ~ ~ ~~~~~~~X~gi ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Lb-m.La' k

0'ML ~~~~~~~~~~~~~~~~~~~~~~~~~ H-F .

LEGEND l jo PtEd Highgwy 0 SensitrveiS C.tutril Mdi. _~ WaterCouseI (3 ExcavationSite Turnull t) NoiseMoisting Site s AirQui MonitoringSite WaDeQuality Monitring Sit sdr1- S a ,5i

0 Mumn~~~~~~~~~~~~~~~~~~ *0~~~~~~~ w Sh!a_x 0 \ Qw .0 0 0 ;_ \ ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Jhac .oc&uk

:'~~~~~p IN

XIAOSHA4NGYUAN-"VLAXNAHIGHWAY PROJCT ENVfIRONYOMICS map I P/t1- rir Wt1 1 Locatons of SensitveSimes, Excvatioa

,I ERi~~~~~A~~Sites- and %fonitor:ngSimes