Bid Date Bid Time Location Project Name Bidding This Week... APRIL 1, 2019 4/1/19 3:00 PM San Jose Del Mar High School Fire Alarm System Replacement - Campbell Union High School District NEW 4/1/19 5:00 PM San Benito Replacment Of Two Ac Units At Pinnacles National Park 4/1/19 3:00 PM San Luis Obispo 2018-19 Surface Treatment - Various County Roads 4/1/19 2:00 PM Saratoga Wvma - Commercial Building (Request For General Contractors Only) 4/2/19 10:00 AM Palo Alto Hoover Elementary School Interim Portables - Palo Alto Unified School District 4/2/19 2:00 PM Salinas Everett Alvarez High School Swimming Pool Renovation 4/2/19 2:00 PM Monte Sereno 2019 Annual Pavement Improvement - City Of Monte Sereno 4/2/19 12:00 PM Cupertino Rfq Construction Inspection Services & Public Works Inspection Services For Vallco Town Center - City Of Cupertino 4/2/19 5:00 PM San Luis Obispo Athleta - Higuera St - San Luis Obispo 4/3/19 2:00 PM San Jose Prop 39: Lighting At Dartmouth & Union Middle Schools - Union School District 4/3/19 3:00 PM Sunnyvale Pipe & Miscellaneous Pipe Supplies - City Of Sunnyvale 4/3/19 11:00 AM Watsonville Green Valley Rd Pavement Preservation 4/3/19 4:00 PM Tres Pinos Immaculate Conception Catholic Church 4/4/19 2:00 PM Santa Clara County Cdot 04-0q9804 Individual Slab Replacement (Rsc) * 4/4/19 3:00 PM San Jose Rfq South Parking Facility Elevator Upgrade - Sjsu 4/4/19 3:00 PM Santa Cruz College Nine And Ten Dining Hall - Dining Commons Dish Room Modifications * 4/4/19 3:00 PM Morgan Hill Britton Middle School New Science Lab Buildings - Morgan Hill Unified School District NEW 4/4/19 2:00 PM Aptos Aptos High School Structural Repairs & Re-Roofing NEW 4/4/19 2:00 PM Los Altos Los Altos High School New Classrooms, Engineering Lab & Auxiliary Gym - Mvla Union High School District NEW * 4/4/19 2:00 PM San Jose Horace Mann Exterior Improvements- San Jose Unified School District (Sjusd) NEW * 4/4/19 2:00 PM San Jose 8931-2019 Local Streets Resurfacing (North) Project - City Of San Jose NEW 4/4/19 3:00 PM San Jose 8936-On-Call Cured-In-Place Pipe (Cipp) General Contract 18-20 - City Of San Jose NEW 4/4/19 3:00 PM San Jose 7202-Westmontavenye & Harriet Avenue Sanitary Sewer Improvement - City Of San Jose 4/4/19 2:00 PM Saratoga Dyer House Renovation Sanborn Park - County Of Santa Clara 4/4/19 2:00 PM Arroyo Grande Huasna Road/Oro Drive Corrugated Metal Pipe And Woodland Drive Sewer Lining 4/4/19 2:00 PM Hollister Sb 1 Seal Coat Project 2019 At Various Locations * 4/4/19 3:00 PM Oceano Oceano Drainage Improvement Project - Phase Ii 4/4/19 2:00 PM Carmel-By-The-Sea Fy 2018/2019 Pavement Rehabilitation Program 4/4/19 2:00 PM San Luis Obispo Anholm Bikeway Phase 1a - Foothill Crossing * 4/4/19 3:00 PM Oceano Oceano Drainage Utility Relocation 4/4/19 2:00 PM Santa Cruz 2019 Surface Seal Project

4/5/19 3:00 PM San Jose Rfq 96-Inch & 87-Inch Settled Sewage Pipe Rehabilitation Project - City Of San Jose

Page 1 of 1 “We’re Not The Best Because We’re the Oldest… We’re The Oldest Because We’re the Best!”

Overhead Door Company of Salinas 733 Sanborn Place • Salinas, CA 93901 Salinas (831) 422-3667 • Monterey (831) 375-3667 Fax (831) 422-1061 • Santa Cruz (831) 662-3122 Lic. #529655

Overhead Door Company of Santa Clara Valley 1266 Lawrence Station Road • Sunnyvale, CA 94089 Tel (408) 734-8010 • Fax (408) 734-3728 Lic. #215098 We Build Futures ~ Communities ~ Confidence ~ We Build Your Business Central Coast Builders Association

242 East Romie Lane (831) 758-1624 Salinas Salinas, CA 93901 (831) 423-5900 Santa Cruz Mon-Thurs 8-5 Fri 8-3 (831) 883-3933 Monterey

(831) 758-6203 Fax

[email protected] Board of Directors

President: Kevin McIntosh, Blach Constuction Brian Kenny, Hayward Lumber

Vice President: Miguel Bustos, MIG Electric

Secretary/Treasurer: Anka Hepper, WM. B Saleh Painting Kate Rueter, AON Risk Services

Past President: Clifford Fasnacht, Dougherty Pump & Drill Gabriel Torres, CCRB/CHISPA

Oscar Blancas, Blancas Construction

CCBA STAFF Christie Cromeenes Executive Director

Merary Rodriguez Finance Coordinator Shelly Verba Office Planroom Manager Rikki Montejano Public Relations Coordinator Disclaimer All information provided by CCBA is obtained from sources deemed to be reliable. It is the user’s responsibility to confirm the accuracy of all facts. We assume no responsibility for errors and/or omissions. All information included is for the intended recipient only, we ask that you do not share this information FactSheet Hazard Alert: Combustible Dust Explosions Combustible dusts are fine particles that present an explosion hazard when suspended in air in certain conditions. A dust explosion can be catastrophic and cause employee deaths, injuries, and destruction of entire buildings. In many combustible dust incidents, employers and employees were unaware that a hazard even existed. It is important to determine if your company has this hazard, and if you do, you must take action now to prevent tragic consequences.

How Dust Explosions Occur In addition to the familiar fire triangle of oxygen, heat, and fuel (the dust), dispersion of dust particles in sufficient quantity and concentration can cause rapid combustion known as a deflagration. If the event is confined by an enclosure such as a building, room, vessel, or process equipment, the resulting pressure rise may cause an explosion. These five factors (oxygen, heat, fuel, dispersion, and confinement) are known as the “Dust Explosion Pentagon”. If one element of the pentagon is missing, an explosion cannot occur.

Catastrophic Secondary Explosions An initial (primary) explosion in processing A pharmaceutical plant after a dust explosion. equipment or in an area where fugitive dust has accumulated may dislodge more accumulated Industries at Risk dust into the air, or damage a containment Combustible dust explosion hazards exist in system (such as a duct, vessel, or collector). a variety of industries, including: agriculture, As a result, if ignited, the additional dust chemicals, food (e.g., candy, sugar, spice, dispersed into the air may cause one or more starch, flour, feed), grain, fertilizer, tobacco, secondary explosions. These can be far more plastics, wood, forest, paper, pulp, rubber, destructive than a primary explosion due to furniture, textiles, pesticides, pharmaceuticals, the increased quantity and concentration of tire and rubber manufacturing, dyes, coal, metal dispersed combustible dust. Many deaths in processing (e.g., aluminum, chromium, iron, past incidents, as well as other damage, have magnesium, and zinc), recycling operations, been caused by secondary explosions. fossil fuel power generation (coal), and 3D welding (a form of 3D printing). Initial Explosion Secondary Explosion Prevention of Dust Explosions To identify factors that may contribute to a explosion, OSHA recommends a thorough hazard assessment of: • All materials handled; • All operations conducted, including by-products; • All spaces (including hidden ones); and • All potential ignition sources. ProjectsWeekly Projects Out To Bidding Bid 3/28/2019

Reasonable care is given in gathering, compiling and furnishing the information contained herein which is obtained from sources believed to be reliable, but the Planroom is not responsible or liable for errors, omissions or inaccuracies.

Name Bid Date Time OPR# Contract # Location Estimate

Monterey County EVERETT ALVAREZ HIGH SCHOOL SWIMMING POOL RENOVATION Addenda: 0 4/2/19 2:00 PM 19-00851 B-19009 Salinas Plan Issuer: Salinas Union High School District [email protected] 831-796-7080 Prebid Conf: MAND 3/21 @ 10am- site This project consists of the removal / demolition of the existing Swimming Pool finishes, including plaster and tile and miscellaneous mechanical equipment items as noted, and other miscellaneous items shown on plans. Construction of new Swimming Pool plaster and tile finishes and mechanical equipment, and other items as shown on plans. All other items as required to provide a completely operational aquatic facility.

PREVAILING WAGE

Questions: [email protected] Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract FY 2018/2019 PAVEMENT REHABILITATION PROGRAM Addenda: 0 4/4/19 2:00 PM 19-00763 Carmel-by-the-Sea Plan Issuer: City of Carmel-by-the-Sea 831-620-2010 831-624-2004 Prebid Conf: 3/12 @ 10am- Vista Lobos parking lot Pavement rehabilitation and slurry seal for various City streets and includes pavement grinding, sawcutting, patching, crack seal, reconstruction, asphalt concrete overlays including leveling courses, rolled asphalt berms, replacement of cobblestone curb & gutter, curb ramp, raising manholes, clean-outs and valve boxes, thermoplastic pavement markings.

PREVAILING WAGE

Questions: Robert Estrella Email: [email protected] Bidders: Teichert Construction Asphalt /Road / Bridge / Heavy Office: 831-901-0072 Fax: 000-000-0000 Highway Contractor Monterey Peninsula Engineering General Contractor Office: 831-384-4081 Fax: 831-384-5078 Keith Day Trucking Supplier Office: 831-771-0126 Fax: 831-771-0109 MARINA HIGH SCHOOL CULINARY ARTS CLASSROOM RENOVATION Addenda: 4 4/8/19 3:00 PM 19-00518 Marina Plan Issuer: Monterey Peninsula Unified School District 831-645-1200 831-649-4175 Prebid Conf: MAND 2/27 @ 4pm- site RENOVATION OF EXISTING CONCRETE CLASSROOM BUILDING 3A AND ATTACHED WOOD STUD CONSTRUCTION RESTROOMS, AND ADJACENT COURTYARD. CONSTRUCTION OF ONE NEW 30'X30'X12' SHADE STRUCTURE. TWO NEW CMU BUILDINGS, 3A.1 AND 3A.2, TO BE CONSTRUCTED WITH STANDING SEAM METAL ROOFING. VOLUNTARY SEISMIC UPGRADE TO OCCUR FOR CONCRETE ROOF STRUCTURE AT BUILDING 3A. NEW FIRE SPRINKLER SYSTEM THROUGH OUT.

PREVAILING WAGE

Questions: Tom Millman Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract Jm Electric Electrical Contractor Office: 831-422-7819 Fax: 831-758-9638 Avila Construction General Contractor Office: 831-372-5580 Fax: 831-372-5584 Cal Pacific Construction General Contractor Office: 415-824-8871 Fax: 650-557-1239 Deadline for submission of materials for our Bulletin is end of day Wednesday each week. Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

Dmc Commercial Inc. General Contractor Office: 831-656-1600 Fax: 000-000-0000 Jacob Construction & Design General Contractor Office: 831-869-8100 Fax: 805-548-1995 Selden & Son General Contractor Office: 831-722-9949 Fax: 831-722-9360 Tombleson Inc General Contractor Office: 831-422-9696 Fax: 831-422-0566 Advanced Air Inc HVAC Contractor Office: 831-384-1988 Fax: 831-384-1989 American Plumbing Systems, Inc. Plumbing & Piping Contractor Office: 916-631-1315 Fax: 916-859-0993 Michael Venosta Plumbing Plumbing & Piping Contractor Office: 408-842-4004 Monterey Structural Steel Steel Contractor Office: 831-768-1277 Fax: 831-768-1352 SALINAS ITC SANITARY SEWER & STORM DRAIN PIPELINE RELOCATION Addenda: 1 4/9/19 2:00 PM 19-00826 9006 & 9007 Salinas $785,000 Plan Issuer: City of Salinas 831-758-7912 831-758-7935 Prebid Conf: 3/25 @ 10am- site In general, the work shall include, but is not limited to, Construction of new storm and sewer lines including manholes, removal and abandonment of storm and sewer facilities, restoration of surfaces over new storm and sewer facilities and associated construction period storm water control and traffic control and all incidental and appurtenant improvements and restorations specified on the Plans and Specifications.

Project Contact: Patrick Fung - 831-758-7186 Email: [email protected] Bidders: Monterey Peninsula Engineering General Contractor Office: 831-384-4081 Fax: 831-384-5078 PRESIDIO OF MONTEREY B838 - BOILER, WATER PIPING REPLACEMENT - REBID Addenda: 0 4/9/19 2:00 PM 19-00853 Monterey $200,000 to $700,000 Plan Issuer: City of Monterey [email protected] 831-242-8777 831-646-3405 Prebid Conf: MAND 3/19 & 3/26 @ 10am- Lower Presidio, in front of the Presidio Museum, off Corporal Ewing Road, Monterey In general, the work consists of, but is not limited to, rebuilding the water heater system in a mechanical room, re-plumbing the cold water feed in a mechanical room, removing a steam boiler and steam system appurtenances, relining a hot water storage tank, re- roofing the flat roof equipment well, installing an evacuated tube solar hot water heating system, removing abandoned piping and unused equipment, and ensuring all remaining piping is properly supported, insulated and labeled for a clean and operational mechanical room.

Project Contact: Andreas Baer Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Demolition Contractor Office: 831-761-5511 Fax: 831-761-5513 Avila Construction General Contractor Office: 831-372-5580 Fax: 831-372-5584 SANITARY SEWER SYSTEM REHABILITATION, PHASE II CIPP AND MANHOLE LINING Addenda: 0 4/9/19 2:00 PM 19-00863 33c1750 Monterey $400,000 to $500,000 Plan Issuer: City of Monterey [email protected] 831-242-8749 831-646-5686 Prebid Conf: 3/27 @ 2pm- 601 Wave Street, Suite 100, Monterey In general, the work consists of, but is not limited to, the rehabilitation of sanitary sewer pipe via cured-in-place pipe (CIPP) as well as rehabilitation of sanitary sewer manholes, cleanouts and lampholes owned and maintained by the City of Monterey. There is a limited amount of work located on the Presidio of Monterey and on the Naval Postgraduate School that will require the contractor to follow the special access procedures described in the specifications. The work will not entail offsite disposal of sewer material, contractor will be required to install bypass pumps from the upstream manhole into the downstream manhole during the curing process.

Project Contact: Regina Trinque Email: [email protected] Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

ON CALL GREENBELT MAINTENANCE CONTRACT 2019 FOR CITY PROJECTS Addenda: 0 4/9/19 2:00 PM 19-00944 Monterey Plan Issuer: City of Monterey [email protected] 831-242-8724 831-646-3921

In general, the work consists of, but is not limited to, all phases of greenbelt management and maintenance, including control and removal of vegetation for fire fuel reduction, and the protection, preservation, and enhancement of native plants and trees in open space areas in greenbelts, parks, and along roadways.

Project Contact: Sara South Email: [email protected]

NEW ON CALL TREE GREENBELT CONTRACT 2019 FOR PMSA Addenda: 0 4/9/19 2:00 PM 19-01051 Monterey Plan Issuer: City of Monterey [email protected] 831-242-8724 831-646-3921

In general, the work consists of, but is not limited to, all phases of greenbelt management and maintenance, including control and removal of vegetation for fire fuel reduction, and the protection, preservation, and enhancement of native plants and trees in open space areas in greenbelts, parks, along roadways, and near private property.

Project Contact: Sara South Email: [email protected]

PLAY AREA IMPROVEMENTS AT KING CITY ELEMENTARY SCHOOLS Addenda: 0 4/10/19 10:00 AM 19-00840 King City

Prebid Conf: MAND 3/27 @ 10am- 502 King Street, King City Project consists of: Site Preparation, Demolition and Clearing; Earthwork and Grading; Excavation & Backfill for Utilities, Storm Drains and Footings; Aggregate Base (Concrete & Paving); Hot Mix Asphalt Paving; Granular Surfacing; Concrete Curbs, Gutters, Walks, Pavements & Finishes; Storm Drains and Drainage Structures; Chain Link Fences and Gates; Site Furnishings; Concrete Formwork; Concrete Reinforcement; Cast-In-Place Concrete.

PREVAILING WAGE Bidders: R.E. Schultz Construction, Inc. General Contractor Office: 714-649-2627 Spectra Turf Inc. Sub-Contractor/Specialty Office: 925-303-8577 Fax: 925-663-0308 Contractor Keith Day Trucking Supplier Office: 831-771-0126 Fax: 831-771-0109 DEL REY ELEMENTARY SCHOOL REPLACEMENT OF HVAC EQUIPMENT Addenda: 0 4/10/19 11:00 AM 19-00842 King City

Prebid Conf: MAND 3/28 @ 1:30pm- site 1. Remove and legally dispose of 16 existing rooftop heat pump units complete, including disposal of the R-22 Refrigerant. Install new AC Units. 2. Disconnect and reconnect gas piping at F-1-1. 3. Disconnect and reconnect condensate drain piping at all units. 4. Disconnect and reconnect the 208 volt/3 phase power at all units. 5. Disconnect and reconnect the existing control wiring at all units. 6. Replace the flexible duct connectors at all units. 7. Provide start-up, testing and air balance.

PREVAILING WAGE Bidders: Coastwide Environmental Tech, Inc. Demolition Contractor Office: 831-761-5511 Fax: 831-761-5513 Della Mora Heating HVAC Contractor Office: 831-883-4500 Fax: 831-883-2800 Otavilla Mechanical Contractors Inc. HVAC Contractor Office: 831-524-4484 Fax: 999-999-9999 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location NEW Estimate

KING CITY ARTS MAGNET ELEMENTARY SCHOOL REPLACEMENT OF HVAC EQUIPMENT Addenda: 0 4/10/19 12:00 PM 19-00845 King City

Prebid Conf: MAND 3/28 @ 3pm- site 1. Remove and legally dispose of 13 existing rooftop gas heat/electric cooling units AC-H-1 through AC-H-13 complete, including disposal of the R-22 refrigerant, install new AC units. 2. Disconnect and reconnect gas piping. 3. Disconnect and reconnect condensate drain piping. 4. Disconnect and reconnect the 208 volt/3 phase power. 5. Disconnect and reconnect the existing control wiring. 6. Replace the flexible duct connectors. 7. Provide start-up, testing and air balance.

PREVAILING WAGE Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract Della Mora Heating HVAC Contractor Office: 831-883-4500 Fax: 831-883-2800 Otavilla Mechanical Contractors Inc. HVAC Contractor Office: 831-524-4484 Fax: 999-999-9999 GABILAN DRIVE STORM DRAIN IMPROVEMENTS Addenda: 0 4/10/19 11:00 AM 19-00902 Soledad $1,400,000 Plan Issuer: Harris & Associates [email protected] 925-827-4900 Prebid Conf: 3/21 @ 10:30am- 248 Main Street, Soledad In general, the Project consists of: · Open cut construction of approximately 2,350 linear feet of reinforced concrete and/or HDPE pipe along Gabilan Drive in Soledad. · Installation of new concrete manholes. · Making storm drain pipe connections between the new system and the existing system.

PREVAILING WAGE

Project Manager: Kyle Carbert Email: [email protected] Bidders: Don Chapin Co General Contractor Office: 831-449-4273 Fax: 831-449-0700 Granite Rock Company General Contractor Office: 408-574-1400 Fax: 408-365-9548 Monterey Peninsula Engineering General Contractor Office: 831-384-4081 Fax: 831-384-5078 Ap Traffic Services, Inc. Sub-Contractor/Specialty Office: 916-997-6653 Fax: 000-000-0000 Contractor DISTRICT SERVICE CENTER INSTALLATION OF NEW WALK-IN FREEZER Addenda: 1 4/11/19 2:00 PM 19-00415 Del Rey Oaks Plan Issuer: Monterey Peninsula Unified School District 831-645-1200 831-649-4175 Prebid Conf: MAND 3/5 @ 3pm- site CONSTRUCTION OF A NEW WALK-IN COOLER/FREEZER BUILDING. WORK INCLUDES DEMOLITION, SITE IMPROVEMENTS, MECHANICAL, PLUMBING, ELECTRICAL AND LOW VOLTAGE IMPROVEMENTS.

PREVAILING WAGE

Questions: Tom Millman Email: [email protected] Bidders: Mig Electric Electrical Contractor Office: 831-524-8507 Varni, Darrel Electric Inc. Electrical Contractor Office: 831-761-2288 Fax: 831-761-2285 Dmc Commercial Inc. General Contractor Office: 831-656-1600 Fax: 000-000-0000 Pueblo Construction , Inc. General Contractor Office: 831-641-0580 Fax: 831-641-0586 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

CDOT 05-1K1604 EXTRACT CHLORIDE CONTAMINATION, INSTALL AND REMOVE SCAFFOLD Addenda: 0 4/11/19 2:00 PM 19-00104 05-1K1604 Monterey County $12,800,000 Plan Issuer: CDot [email protected] 916-227-6098

In Monterey County Near Lucia At Big Creek Bridge The Contractor must have either a Class A license or the following Class C license which constitutes a majority of the work: . 445 Working Days * DVBE participation incentive up to $250,000 *

NEW STORM DRAIN GRATE UPGRADE PROJECT-INSTALLATION Addenda: 0 4/11/19 2:00 PM 19-01053 Seaside Plan Issuer: City of Seaside [email protected] NEW 831-899-6825 831-899-6211

Measurement support and installation of replacement storm drain grates, storm grates to be provided by others, in conformance with 2015 Caltrans Standard Specification Section 75-2.02B and equivalent to the Caltrans Standard Plan (D77B) for bicycle safe grates within the City of Seaside, County of Monterey.

Project Contact: Scott Ottmar Email: [email protected]

LAS LOMAS DRAINAGE Addenda: 1 4/12/19 3:00 PM 19-00693 1723 Salinas $795,432 Plan Issuer: County of Monterey 831-755-4800 831-755-4958

Installation of new storm drainage infrastructure including reinforced concrete pipe, manholes, junction structures, catch basins, concrete flared end sections, rock slope protection, corrugated metal pipe, including but not limited to minor earthwork/grading, utility relocation and traffic control. The Additive Alternate for the project consists of, but not limited to installation of new storm drainage infrastructure including reinforced concrete pipe, manholes, junction structure, catch basins, including but not limited to earthwork/grading, utility relocation and traffic control.

PREVAILING WAGE

Project Contact: Ruby Jacinto Email: [email protected] Bidders: Granite Rock Company General Contractor Office: 408-574-1400 Fax: 408-365-9548 Monterey Peninsula Engineering General Contractor Office: 831-384-4081 Fax: 831-384-5078 Teichert Construction General Contractor Office: 831-901-0072 Fax: 000-000-0000 Ap Traffic Services, Inc. Sub-Contractor/Specialty Office: 916-997-6653 Fax: 000-000-0000 Contractor Keith Day Trucking Supplier Office: 831-771-0126 Fax: 831-771-0109 RFP - DESIGN AND BUILD SOLAR PHOTOVOLTAIC (PV) SYSTEMS Addenda: 0 4/16/19 5:00 PM 19-00644 Monterey Plan Issuer: TerraVerde Energy, LLC 415-404-2268 000-000-0000 Prebid Conf: MAND 3/14 @ 10am- 298 Patton Pkwy, Marina The District is seeking proposals from qualified solar contractors (“Respondents”) to design, engineer, procure, construct, interconnect and commission solar photovoltaic systems (“Systems” or “Solar Facilities”) at one or more of the sites listed in the Executive Summary (“Project Sites”).

Contact Person: Brandon Hartman Email: [email protected] Bidders: Spectrum Energy Development, Inc. Elevator Contractor Office: 805-550-7520 California Commercial Fence Sub-Contractor/Specialty Office: 559-260-4699 Fax: 559-575-8244 Contractor Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

CDOT 05-1F7004 REPLACE CONCRETE PANEL AND RESURFACE HMA PAVEMENT Addenda: 0 4/17/19 2:00 PM 19-00070 05-1F7004 Monterey County $24,400,000 Plan Issuer: CDot [email protected] 916-227-6098

In Monterey County Near Chualar From 0.5 Mile North Of North Gonzales Overcrossing To East Market Street Undercrossing The Contractor must have either a Class A license or the following Class C license which constitutes a majority of the work: C-12. 200 Working Days * 16% DBE Requirement Bidders: Granite Construction General Contractor Office: 831-763-6100 Fax: 831-761-1042 Granite Rock Company General Contractor Office: 408-574-1400 Fax: 408-365-9548 Keith Day Trucking Supplier Office: 831-771-0126 Fax: 831-771-0109 WORLDMARK MARINA DUNES CONDOMINIUMS Addenda: 1 4/18/19 5:00 PM 19-00880 Marina Plan Issuer: DMR Builders [email protected] 707-596-7575 000-000-0000 Prebid Conf: MAND 3/21 @ 9am- site DMR Builders is actively seeking quotes from qualified contractors for the interior renovations at the WorldMark Marina Dunes condominiums located in Marina, CA.

Scope #1: Replacement of 33 sliding door and window at WorldMark Marina Dunes in Marina CA. Scope #2: Demo of 31 existing kitchen & Vanity countertops and install new granite countertops and 2 ADA units.

Site visit instructions: Please stop by the lobby as you enter the property and tell them your with Elements Hospitality and they will direct you to a room or two to view.

Project Contact: JR Da Silva Email: [email protected]

NEW RUNWAY 8-26 AND HELIPORT REHABILITATION Addenda: 0 4/18/19 2:00 PM 19-00999 9012 Salinas $855,535 Plan Issuer: City of Salinas [email protected] 831-758-7185 Prebid Conf: 4/1 @ 10am- 30 Mortensen Ave, Salinas In general, the work includes but is not limited to: Base Bid: Asphalt Pavement Crack Seal, Seal Coat, and Re-mark of Runway 8-26 and Heliport.

PREVAILING WAGE

Project Contact: Josie Lantaca - 831-758-7185 Email: [email protected]

MONTEREY HIGH SCHOOL SCIENCE INNOVATION CENTER Addenda: 0 4/23/19 3:00 PM 19-00809 Monterey Plan Issuer: Monterey Peninsula Unified School District 831-645-1200 831-649-4175 Prebid Conf: MAND 3/20 @ 3pm- site Project consists of: Structure Demolition; Selective Structure Demolition; Concrete; Metals; Wood, Plastics and Compsites; Thermal and Moisture Protection; Openings; Finishes; Visual Display Surfaces; Signage; Folding Panel Partitions; Emergency Key Cabinets; Fire Protection Specialties; Projection Screens; Roll-Down Shades; Entrance Floor Mats and Frames; Site Furnishings; Preassembled Buildings; Hydraulic Elevators; Fire Protection General; Overhead Fire Protection; Underground Fire Service; Plumbing; HVAC; Electrical; Data/Telephone System; Fire Alarm System; Earthwork; Exterior Improvements; Water Systems; Sanitary Sewer; Storm Drainage.

PREVAILING WAGE

Project Contact: Tom Millman Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract Cve Contracting Group Inc. Dba Central Asbestos Abatement / Office: 559-222-1122 Fax: 559-222-1174 Valley Envi Hazardous Materials Contract Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

Monterey Environmental Solutions + Asbestos Abatement / Office: 831-333-6431 Fax: 000-000-0000 Services Hazardous Materials Contract Enos Communications Communications/Technology Office: 408-375-1554 Fax: 000-000-0000 Contractor Mig Electric Electrical Contractor Office: 831-524-8507 Ausonio Incorporated General Contractor Office: 831-970-5360 Fax: 831-633-3389 Avila Construction General Contractor Office: 831-372-5580 Fax: 831-372-5584 Dmc Commercial Inc. General Contractor Office: 831-656-1600 Fax: 000-000-0000 Advanced Air Inc HVAC Contractor Office: 831-384-1988 Fax: 831-384-1989 Keith Day Trucking Supplier Office: 831-771-0126 Fax: 831-771-0109 NEW LOT 59 LANDSCAPING Addenda: 0 5/7/19 1:00 PM 19-01033 PRK16013 Seaside $150,000 Plan Issuer: CSUMB [email protected] 831-582-4169 831-582-4436 Prebid Conf: 4/16 @ 9am- Mountain Hall A (Bldg 84) In general, work will consist of the provisions and installation of landscaping at Parking Lot 59, on the campus of CSU Monterey Bay.

Project Contact: Reyola Carlisle - 831-582-3506 Emails: [email protected]

NEW SALINAS STORM WATER GRANT (PHASE 1A, DRY WEATHER DIVERSION PROJECT) Addenda: 0 5/20/19 2:30 PM 19-01071 Salinas Plan Issuer: Monterey One Water [email protected] 831-883-6182 831-883-0516 Prebid Conf: MAND 4/17 @ 10am- 14811 Del Monte Blvd, Marina The Work of this Contract includes the Dry Weather Diversion Project (Phase 1A) work at the City of Salinas (COS) site identified as Salinas TP1 and known as the Monterey One Water’s (M1W’s) Salinas Pump Station, and also includes some electrical, instrumentation and communication work at the COS IWWTF Influent Pump Station.

Project Contact: Yohana Vargas Email: [email protected]

NEW 2019 CASTROVILLE SEAWATER INTRUSION PROJECT-WELL DESTRUCTION PROJECT Addenda: 0 5/23/19 2:00 PM 19-01070 Monterey County Plan Issuer: Monterey County Water Resources Agency 831-755-4860 831-424-7935 Prebid Conf: 4/11 @ 2pm- Approximately 1.08 miles south of Castroville on HWY 183 This project is for the destruction of two (2) water wells to prevent degradation of the groundwater by intermixing of aquifers. The well sites are located approximately six miles west from the City of Salinas, in Monterey County, California, (see Exhibit B - Attachment No. 1, for well location map) . The Base Bid for the Project consists of the following: Well destruction design, permitting, mobilization and demobilization, well borehole cleaning, casing perforation, grout emplacement, casing excavation and removal, and concrete pad and wiring removal. The Contractor shall furnish all labor, materials, equipment, supplies, transportation, all applicable permits, and incidentals to perform all work in accordance with the requirements of the Contract Documents and Monterey County Health Department Well Destruction Permit.

PREVAILING WAGE

Questions: Manuel Saavedra Email: [email protected] Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

San Benito County NEW REPLACMENT OF TWO AC UNITS AT PINNACLES NATIONAL PARK Addenda: 0 4/1/19 5:00 PM 19-00974 140P8419Q0029 San Benito

INSTALL TWO AC UNITS, PINNACLES NATIONAL PARK, SAN BENITO, CALIFORNIA. The National Park Service, Pinnacles National Park, has a requirement for the installation of air conditioning units in two housing units within the park. The Contractor shall provide all supervision, labor, materials and equipment necessary to complete the work as identified in the project specifications and associated documents provided as attachments to the solicitation. This acquisition is a Total Small Business Set-Aside. Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall not be considered. This award is expected to be a Firm Fixed Price award. Award is subject to the availability of funding at the time of award. This award will be made as a service contract and the corresponding Service Contract Act Wage Rates shall apply.

Project Contact: Elizabeth Chico Email: [email protected]

IMMACULATE CONCEPTION CATHOLIC CHURCH Addenda: 0 4/3/19 4:00 PM 19-00903 Tres Pinos Plan Issuer: James Fruit, Architect [email protected]

Repair and upgrade Parish Hall electrical system. TRADES REQUESTING BIDS FOR: Primarily electrical, some minor carpentry around sub panel when removed/replaced.

*** SEND BIDS TO James Fruit @ [email protected] & John Gudgeon @ [email protected] ***

For Work Technical Info: James Fruit, Architect Email: [email protected] Phone: 408-981-4121

For Business &/or Contact Info: John Gudgeon Email: [email protected]

SB 1 SEAL COAT PROJECT 2019 AT VARIOUS LOCATIONS Addenda: 3 4/4/19 2:00 PM 19-00664 PWB-1902 Hollister $360,000 to $385,000 Plan Issuer: County of San Benito 831-636-4170 831-636-4176

The project includes, but is not limited to, improve roadways at various locations by Seal Coats.

Questions: [email protected]

NEW SAN BENITO COUNTY SERVICE AREAS ROAD MAINTENANCE Addenda: 0 5/9/19 2:00 PM 19-00990 PWB-1903 Hollister $600,000 to $650,000 Plan Issuer: County of San Benito 831-636-4170 831-636-4176

The project includes, but is not limited to improve roadways within County Service Areas #5, 8, 9, 11, and 35 by Seal Coats and Hot Asphalt Concrete Pavement Removal and Replacement.

Project Contact: [email protected] Bidders: Bay Area Traffic Solutions (Bats) Signage Contractor Office: 559-365-2269 Fax: 559-498-0453 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

San Luis Obispo County 2018-19 SURFACE TREATMENT - VARIOUS COUNTY ROADS Addenda: 0 4/1/19 3:00 PM 19-00681 300614 San Luis Obispo $1,853,551 Plan Issuer: County of San Luis Obispo [email protected] 805-781-4073

This project will place micro-surfacing and/or slurry seal on various County roads throughout Paso Robles, Cambria, Cayucos, Morro Bay, Los Osos, and other such items or detail work not mentioned herein that are required by the Plans, the Standard Specifications, Standard Plans, or these Special Provisions.

Bid Contact: JR Beard (805) 781-4073 [email protected]

ATHLETA - HIGUERA ST - SAN LUIS OBISPO Addenda: 0 4/2/19 5:00 PM 19-00958 San Luis Obispo Plan Issuer: West Coast Construction Services, Inc. 909-982-6979 909-476-9005

Project consists of: Interior Build Out; Energy Calculation Attached; Toilet Facilities Provided / Existing; Fire System Modifications; Strobes/Alarms/Sprinklers. Trades: DEMOLITION; CONCRETE; MISCELLANEOUS METAL FABRICATIONS; CASEWORK/MILLWORK/CORIAN/ FINISH CARPENT; SHEET METAL FLASHING & TRIM; DOORS, FRAMES & HARDWARE; STOREFRONT- GLASS & GLAZING; DRYWALL; CERAMIC TILE; ACOUSTICAL CEILING; RESILIENT FLOORING (VCT); FLOOR SEAL/STAIN/POLISH; PAINTING- INTERIOR/EXTERIOR; FRP; FIRE ALARM; FIRE SPRINKLERS; PLUMBING; HVAC; ELECTRICAL.

Questions: Norberto “Yob” Leano Email: [email protected] Bidders: !!!There May Be Other Gc's Bidding This General Contractor Office: 000-000-0000 Project That We Are Unaware Of West Coast Construction Services, Inc. General Contractor Office: 909-982-6979 Fax: 909-476-9005 Hps Mechanical, Inc. Sub-Contractor/Specialty Office: 661-397-2121 Fax: 661-396-2589 Contractor HUASNA ROAD/ORO DRIVE CORRUGATED METAL PIPE AND WOODLAND DRIVE SEWER LINING Addenda: 1 4/4/19 2:00 PM 19-00652 PW 2018-01 Arroyo Grande $191,000 Plan Issuer: City of Arroyo Grande [email protected] 805-473-5444 805-473-5462 Prebid Conf: 3/21 @ 2pm- 1375 Ash Street, Arroyo Grande In general the project involves the rehabilitation of approximately 868 feet of 14-inch sewer line, 146 feet of 8-inch sewer line, 635 feet of 24-inch storm drain pipe, and 265 feet of 42-inch storm drain pipe by the installation of a resin-impregnated flexible tube, which is tightly formed to the original conduit.

PREVAILING WAGE

Project Contact: Jill McPeek Email: [email protected] Bidders: Badger Daylighting Corporation Sub-Contractor/Specialty Office: 559-997-9762 Contractor OCEANO DRAINAGE IMPROVEMENT PROJECT - PHASE II Addenda: 3 4/4/19 3:00 PM 19-00680 300465.08.02 Oceano $3,698,274 Plan Issuer: County of San Luis Obispo [email protected] 805-781-4073 Prebid Conf: 3/13 @ 1:30pm- 1909 Delta Lane in Oceano The proposed project consists of the construction of approximately 2,500 feet of storm drain pipe adjacent to Highway 1 in the community of Oceano, to a new outfall pond (sedimentation basin) adjacent to Arroyo Grande Creek. The basin will collect storm flows and allow debris and sediments to settle out prior to discharge through the Arroyo Grande Creek levee. Construction includes jack and bore operations at a railroad crossing, drainage improvements, utility relocations, and appurtenant work and improvements.

Bid Contact: JR Beard (805) 781-4073 [email protected] Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

ANHOLM BIKEWAY PHASE 1A - FOOTHILL CROSSING Addenda: 1 4/4/19 2:00 PM 19-00773 91619 San Luis Obispo $233,000 Plan Issuer: City of San Luis Obispo 805-781-7200 805-781-7198

In general, the project includes the installation of a Pedestrian Hybrid Beacon system—often referred to as a “HAWK Beacon”—at the intersection of Foothill Boulevard at Ferrini Road to improve crossing safety for bicyclists and pedestrians. The project will include new pavement markings, accessible curb ramps and concrete cross gutter replacement, installation of new traffic signal poles, service enclosure, traffic controller and cabinet, conduit and related accessories as shown in the plans.

PREVAILING WAGE

OCEANO DRAINAGE UTILITY RELOCATION Addenda: 1 4/4/19 3:00 PM 19-00847 2019-02 Oceano $74,635 Plan Issuer: Oceano Community Services District 805-481-6730 805-481-6836

Project consists of: SR-1 STA 10+90 12” WATERLINE MODIFICATION; RAILROAD STREET 6” SEWER MODIFICATION; 15TH STREET STA 13+85 12” WATERLINE MODIFICATION; PASO ROBLES STREET STA 10+15 6” WATERLINE MODIFICATION; RAILROAD STREET STA 13+45 6” WATERLINE MODIFICATION. The work described in the Contract Documents is also included as an additive bid item for San Luis Obispo County Contract No. 300465.08.02 - Oceano Drainage Improvement Project Phase II. The bidding and contracting process conducted by the County is independent of the bidding and contracting process conducting by the District. The work reflects permanent water and wastewater utility relocation of certain District facilities that the District is obliged to perform as a result of the County's Oceano Drainage Improvement Project Phase II. The District reserves the right to have the County's contractor perform the work as an additive bid item even if the District's responsible bidder with the lowest responsive bid provides a bid that is lower than the bid amount for related work obtained by the County.

PREVAILING WAGE Bidders: Badger Daylighting Corporation Sub-Contractor/Specialty Office: 559-997-9762 Contractor CAYUCOS SUSTAINABLE WATER PROJECT - WATER RESOURCE RECOVERY FACILITY Addenda: 2 4/10/19 11:00 AM 19-00636 Morro Bay $16,000,000

Prebid Conf: MAND 3/21 @ 1pm- site The Project consists of constructing a .335 MGD average daily flow Water Resource Recovery Facility.

Questions: Dylan Wade Email: [email protected] Bidders: Cushman Contracting Corp General Contractor Office: 805-964-8661 Fax: 805-357-5315 Hps Mechanical General Contractor Office: 661-397-2121 Fax: 661-396-2589 Katch Environmental, Inc. General Contractor Office: 559-292-6653 Fax: 559-272-3276 Klassen Corporation General Contractor Office: 661-324-3000 Fax: 661-324-3900 Western Water Constructors, Inc. General Contractor Office: 707-540-9640 Fax: 707-540-9641 2019 PAVEMENT RESURFACING Addenda: 0 4/10/19 2:00 PM 19-00765 C2018R03 Atascadero $470,000 to $520,000 Plan Issuer: City of Atascadero [email protected] 805-470-3180 805-470-3181

Approximately 120,000 SY of microsurfacing (Type II), including existing striping removal and restriping on various streets in Atascadero.

Project Contact: [email protected] or [email protected] Bidders: California Pavement Maintenance Co., General Contractor Office: 916-381-8033 Fax: 916-381-3703 Inc. Dba Cpm Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

SANTA LUCIA ROAD PAVEMENT REHABILITATION Addenda: 2 4/10/19 2:30 PM 19-00807 C2017R03 Atascadero $725,000 to $770,000 Plan Issuer: City of Atascadero [email protected] 805-470-3180 805-470-3181

Roadway rehabilitation. Mill and overlay with deep lift paving at failed locations. Minor drainage improvements include AC berm and culvert replacements.

Project Contact: Dawn Patterson E-mail: [email protected]

NEW CUESTA COLLEGE SLO CAMPUS - 2000 COMPLEX ADA UPGRADES Addenda: 0 4/16/19 1:00 PM 19-01009 San Luis Obispo

Prebid Conf: 4/9 @ 10am- Parking Lot 5 ACCESSIBILITY UPGRADE OF BUILDINGS 2100, 2200, 2300, 2400, 2500. RESTROOM(S) FIXTURE RELOCATION TO MEET CURRENT ACCESSIBILITY STANDARDS, REPLACEMENT OF DOOR HARDWARE AND THRESHOLDS AT NON COMPLAINT CONDITIONS THROUGHOUT. PROVIDE ACCESSIBLE BUILDING SIGNAGE, UPGRADE EXISTING DRINKING FOUNTAINS TO ACCESSIBLE HI-LOW DRINKING FOUNTAINS AND FILLING STATIONS, AND CORRECT SITE ACCESS AT PARKING AND WALKWAYS FOR COMPLIANT ACCESSIBILITY. REMEDIATION OF EXISTING SITE FLATWORK CONDITIONS TO PROVIDE COMPLIANT WALKWAY AND RAMP SURFACES. MINOR FIRE ALARM MODERNIZATION AT BUILDING 2400.

PREVAILING WAGE

Project Contact: Jayson Bryan Email: [email protected]

NEW CUESTA COLLEGE SLO CAMPUS - 2000'S COMPLEX RE-ROOF & HVAC REPLACEMENT Addenda: 0 4/16/19 3:00 PM 19-01012 San Luis Obispo

Prebid Conf: 4/9 @ 1pm- Parking Lot 5 COMPLETE AND INCLUSIVE REMOVAL OF EXISTING ROOFING MATERIAL, FLASHINGS, COPINGS, AND RELATED FEATURES TO BE REPLACED WITH NEW 80MM SINGLE PLY ROOFING SYSTEM. INSTALLATION OF NEW POLY ISO INSULATION TAPERED PER SLOPE OF PLAN AND 1/4" PROTECTION BOARD BACKER. REMOVAL AND REPLACEMENT OF EXISTING ROOF MOUNTED HVAC UNITS AND EXHAUST FANS, DUCT WORK, AND ALL ASSOCIATED ELECTRICAL CONDUIT, SUPPORT FRAMES, & WIRING ABOVE THE ROOF LINE WITH IN-KIND ELEMENTS AS INDICATED. CONTRACTOR TO INCLUDE 10% CONTINGENCY FOR REPLACING SUCH ELEMENTS AS SHEATHING, BLOCKING AND RELATED EXISTING ROOF CONSTRUCTION DEEMED INADEQUATE FOR THE COMPLETION OF THE ROOF AS ACCEPTED BY THE OWNER. REMAINING BALANCE TO BE RETURNED AS CREDIT TO THE DISTRICT.

PREVAILING WAGE

Project Contact: Jayson Bryan Email: [email protected] Bidders: Mesa Energy Systems, Inc. (Emcor HVAC Contractor Office: 559-277-7900 Fax: 559-277-4920 Services) NEW CUESTA COLLEGE SLO CAMPUS - 2000'S BLDGS WIRELESS AND TR UPGRADES Addenda: 0 4/16/19 2:00 PM 19-01016 San Luis Obispo

Prebid Conf: 4/9 @ 9am- Parking Lot 5 Project consists of: COMMON WORK RESULTS FOR ELECTRICAL; SELECTIVE ELECTRICAL DEMOLITION; LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES; GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS; HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS; RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS; IDENTIFICATION OF ELECTRICAL SYSTEMS; INTERCOMMUNICATION SYSTEMS.

PREVAILING WAGE

Project Contact: Jayson Bryan Email: [email protected] Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

CURB RAMP UPGRADES SIERRA BONITA - QUEENANNE ROAD Addenda: 0 4/18/19 2:00 PM 19-00697 18-06 Paso Robles $142,300 Plan Issuer: City of Paso Robles 805-237-3861 805-237-3904

The work shall include but is not limited to remove and replace existing curb ramps, spandrel, sidewalk, and paving all as shown on the plans and/or as specified herein.

Project Contact: Ditas Esperanza Email: [email protected]

SOUTHLAND WWTF METAL STORAGE BUILDING Addenda: 0 4/18/19 2:00 PM 19-00945 Nipomo

Prebid Conf: MAND 3/28 @ 10am- 509 Southland St, Nipomo The work involves furnishing all labor, materials, equipment, services, utilities and performing all work necessary and incidental to the construction of a concrete foundation and pre-engineered/prefabricated metal building with all necessary hardware. Contractor to provide all necessary plans and inspections necessary for complete turnkey installation.

PREVAILING WAGE

Questions: Anthony Severy Email: [email protected] Bidders: Cali Concrete Concrete/Masonry Contractor Office: 661-398-8143 Fax: 661-398-1382 SIERRA DRIVE DRAINAGE IMPROVEMENTS Addenda: 0 4/23/19 2:00 PM 19-00900 PW 2018-02 Arroyo Grande $91,000 Plan Issuer: City of Arroyo Grande [email protected] 805-473-5444 805-473-5462 Prebid Conf: 4/2 @ 2pm- 1375 Ash Street, Arroyo Grande In general, the project consists of installation and/or replacement of storm drainage catch basins, storm drain pipe, and asphalt concrete dike along a portion of Sierra Drive in the City of Arroyo Grande.

PREVAILING WAGE

Project Contact: Jill McPeek Email: [email protected] Bidders: Houchin Brother's Equipment Rentals Equipment Office: 661-809-6838 Badger Daylighting Corporation Sub-Contractor/Specialty Office: 559-997-9762 Contractor Core & Main Supplier Office: 661-393-2288 Fax: 661-393-2288 LIFT STATION NO. 1 FORCE MAIN REPLACEMENT Addenda: 0 4/23/19 3:00 PM 19-00901 PW 2017-07 Arroyo Grande $735,000 Plan Issuer: City of Arroyo Grande [email protected] 805-473-5444 805-473-5462 Prebid Conf: MAND 4/2 @ 3pm- 1375 Ash Street, Arroyo Grande In general the project consists of installation of approximate 3500 feet of 8 inch sewer force main pipe using horizontal directional drilling techniques.

PREVAILING WAGE

Project Contact: Jill McPeek Email: [email protected] Bidders: Houchin Brother's Equipment Rentals Equipment Office: 661-809-6838 Badger Daylighting Corporation Sub-Contractor/Specialty Office: 559-997-9762 Contractor Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

NEW HARLOE FURNACE REPLACEMENT AT HARLOE ELEMENTARY SCHOOL Addenda: 0 4/23/19 2:00 PM 19-01038 16134/19-11 Arroyo Grande

Prebid Conf: MAND 4/2 @ 9am- site Provide all necessary labor and material to remove and dispose of existing furnaces and replace with new furnaces, thermostats, ducting and requisite utility infrastructure as outlined in specifications.

PREVAILING WAGE

Project Contact: Cindy Naber Email: [email protected]

NEW DISPATCH CENTER HVAC REPLACEMENT Addenda: 0 4/25/19 2:00 PM 19-00994 91569 San Luis Obispo $130,000

Prebid Conf: MAND 4/16 @ 10am or 2pm- site In general, the project consists of replacement of the existing cooling unit with installation of an outside air intake system and exhaust system.

PREVAILING WAGE

Bidders: Mesa Energy Systems, Inc. (Emcor HVAC Contractor Office: 559-277-7900 Fax: 559-277-4920 Services) Santa Clara County WVMA - COMMERCIAL BUILDING (REQUEST FOR GENERAL CONTRACTORS ONLY) Addenda: 0 4/1/19 2:00 PM 19-00819 Saratoga Plan Issuer: West Valley Muslim Association 000-000-0000 Prebid Conf: 3/18 @ 11AM New 2,283 square foot building and parking lot. Trades includes: Foundation Concrete Slab, Wood Frame and Roof construction, and front Parking Lot.

Project Manager: Farooq Abbasi 408-802-0279 cell Email: [email protected]

DEL MAR HIGH SCHOOL FIRE ALARM SYSTEM REPLACEMENT - CAMPBELL UNION HIGH SCHOOL Addenda: 2 DISTRICT 4/1/19 3:00 PM 19-00952 218-980014-030 San Jose $900,000 Plan Issuer: Campbell Union High School District [email protected] 408-371-0960 Prebid Conf: MAND 3/21 @ 1PM Complete campus fire alarm system replacement at Del Mar High School. Scope of work includes installation of new fire alarm system and new main panel in Building J, demolition of existing devices, conduit, and wire as required, cross over to new system, and final testing.

Bidders: Communication Service Co. Fire Alarm/Security Contractor Office: 925-755-3473 Fax: 925-755-3418 Aram Electric, Inc. General Contractor Office: 510-357-2726 Fax: 000-000-0000 Fe Construction Dba Fe Controls General Contractor Office: 408-969-0258 Fax: 408-969-0263 Sound & Signal Inc. Security / Fire Alarm Contractor Office: 925-455-1778 Fax: 925-455-6153 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

2019 ANNUAL PAVEMENT IMPROVEMENT - CITY OF MONTE SERENO Addenda: 0 4/2/19 2:00 PM 19-00651 Monte Sereno Plan Issuer: City of Monte Sereno 408-354-7635 408-395-7653

Various forms of pavement maintenance on 18 different low traffic volume, residential street segments in close proximity to each other totaling about 11,200 lineal feet.

Project Contact For Questions: Jessica Kahn Email: [email protected] Bidders: Tri-Valley Excavating General Contractor Office: 408-442-4286 Fax: 925-862-0905 California Pavement Maintenance Co., Sub-Contractor/Specialty Office: 916-381-8033 Fax: 916-381-3703 Inc. Dba Cpm Contractor HOOVER ELEMENTARY SCHOOL INTERIM PORTABLES - PALO ALTO UNIFIED SCHOOL DISTRICT Addenda: 3 4/2/19 10:00 AM 19-00801 HPI-19 Palo Alto Plan Issuer: Palo Alto Unified School District- PAUSD 650-329-3927 Prebid Conf: MAND 3/6 @ 10AM (Front of Admin Building) Site improvements for the installation of SIX (6) 24’x40’ Portable Classroom Buildings and ONE (1) 12’x40’ Portable Toilet Building. Includes temporary construction fencing with fabric, modification, cut/cap to existing playing field irrigation, site grub & clear, earthwork, grading for new AC pavement, existing playing field topsoil & reseeding at areas of disturbance, selective demolition & repair to site perimeter chain link fence, construction of new transformer pad, installation of pipe bollards at (n) site transformer (transformer furnished/installed by others), extension/modification of existing sanitary sewer, domestic water, electrical power distribution including new main switchboard, disconnect/reconnect existing electrical service onsite, low voltage, fire alarm, salvage and reinstallation of District classroom equipment (assistive listening system and Smartboards with Smartboard projectors from SIX (6) existing upper wing classrooms, room ID signage, relocation of existing 8’x8’ Tuff-shed between existing portables ‘18’ & ‘19’, new chain link fence enclosures at SIX (6) ea. Wall-mount HVAC units. Coordination of work by others: 1) Site delivery & set-up of portable buildings and ramps, 2) City of Palo Alto Electrical transformer & primary conductor upgrade. Bidders: Enos Communications Communications/Technology Office: 408-375-1554 Fax: 000-000-0000 Contractor Agbayani Construction General Contractor Office: 415-221-2065 Fax: 415-665-9470 Bosco Construction General Contractor Office: 866-233-2248 Fax: 408-904-4792 Brco Constructors, Inc. General Contractor Office: 916-253-9373 Fax: 916-253-9377 Cumiskey Construction Corporation General Contractor Office: 415-769-5770 Fax: 415-769-5790 Lewis & Tibbitts Inc. General Contractor Office: 408-925-0220 Fax: 408-925-0240 Rodan Builders Inc. General Contractor Office: 650-508-1700 Fax: 650-508-1705 RFQ CONSTRUCTION INSPECTION SERVICES & PUBLIC WORKS INSPECTION SERVICES FOR Addenda: 0 VALLCO TOWN CENTER - CITY OF CUPERTINO 4/2/19 12:00 PM 19-00817 2019-001 Cupertino Plan Issuer: City of Cupertino 408-777-3354 408-777-3333

Provide regulatory building inspection and public works construction inspection services for a wide variety of new buildings and structures proposed for Vallco Town Center

Hard copies available for review at Santa Clara Builders Exchange

PIPE & MISCELLANEOUS PIPE SUPPLIES - CITY OF SUNNYVALE Addenda: 1 4/3/19 3:00 PM 19-00917 Sunnyvale Plan Issuer: City of Sunnyvale DPW 408-730-7403 000-000-0000

Provide pipe and miscellaneous pipe supplies to be used in support of municipal services for the City of Sunnyvale.

Project Contact For Questions: Lisa Vo Email: [email protected]

Hard copies available for review at Santa Clara Builders Exchange Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

PROP 39: LIGHTING AT DARTMOUTH & UNION MIDDLE SCHOOLS - UNION SCHOOL DISTRICT Addenda: 1 4/3/19 2:00 PM 19-00943 San Jose Plan Issuer: Greystone West Company 707-933-0624 707-996-8390 Prebid Conf: MAND 3/21 @ 3:30PM (Starting @ Union MS, 2130 Los Gatos Almaden Rd, San Jose and continuing to Dartmouth Middle School 5575 Dartmouth Dr, San Jose) Provide all necessary equipment, hardware, adapters, and any other materials necessary for acomplete and quality installation. Ensure installation quality, compliance with project schedule and proper disposal and/or recycling of old luminaires and equipment. Bidders: Aram Electric, Inc. General Contractor Office: 510-357-2726 Fax: 000-000-0000 Cupertino Electric Inc. General Contractor Office: 408-808-8000 Fax: 408-275-8092 BRITTON MIDDLE SCHOOL NEW SCIENCE LAB BUILDINGS - MORGAN HILL UNIFIED SCHOOL Addenda: 4 DISTRICT 4/4/19 3:00 PM 19-00318 G1711.3 Morgan Hill Plan Issuer: Morgan Hill Unified School District 408-201-6085 408-201-6094 Prebid Conf: MAND 2/7 @ 9AM (Administration Buildling) Construction of new 6 classroom science building wing and outdoor science quad. Construction of shade structures. This includes, but is not limited to: earthwork, grading, paving, stormwater pollution prevention plan (SWPPP), installation of site utilities, landscaping, irrigation, site concrete, hardscape, site furnishings, wood framing, steel erection, structural concrete, glulams, storefront openings, polished concrete floors, restrooms, casework, acoustical ceilings, fire alarm, voice/data, folding glass partitions, operable window shades, standing seam metal roofing, Owner Furnished Contractor Installed items, coordination of installation with Owner Furnished Owner Installed Items, coordination with increment 1 contractor scope of work, etc.

Project Contact For Questions: Casino Fajardo 408-201-6000 Email: [email protected] Bidders: Fremont Millwork Co. Casework / Millwork Contractor Office: 541-884-5554 Fremont Millwork Co. Casework / Millwork Contractor Office: 541-884-5554 3d Datacom Communications / Technology Office: 925-455-1884 Fax: 925-455-1692 Contractor Itek Contractors Inc Concrete/Masonry Contractor Office: 650-518-4028 Fax: 650-618-2444 4 Point Power Inc Electrical Contractor Office: 408-331-7617 Fax: 000-000-0000 Adept Electrical Services Electrical Contractor Office: 831-566-8648 Fax: 831-480-8469 Elco Electric Electrical Contractor Office: 408-434-6601 Fax: 408-434-6615 Ibarra Wiring Systems, Inc Electrical Contractor Office: 408-813-1237 Fax: 408-955-0294 Tri-Signal Integration, Inc. Fire Alarm/Security Contractor Office: 925-428-3889 101 Builders, Inc General Contractor Office: 408-842-3355 Fax: 000-000-0000 Bjork Construction General Contractor Office: 510-656-4688 Fax: 510-656-0806 Dilbeck & Sons General Contractor Office: 831-422-8213 Fax: 831-422-1882 Dl Falk Construction, Inc. General Contractor Office: 510-887-6500 Fax: 510-887-6501 Drp Builders Inc General Contractor Office: 408-683-4221 Fax: 408-686-9006 Rc Benson & Sons, Inc. General Contractor Office: 650-965-3430 Fax: 650-965-7139 Strawn Construction, Inc General Contractor Office: 408-286-1299 Fax: 408-286-1288 Swenson & Associates General Contractor Office: 408-866-7600 Fax: 408-866-7692 Pacific Glazing Contractors Glass & Glazing Contractor Galaxy Construction Services, Inc HVAC Contractor Office: 415-756-0950 Fax: 925-265-6877 Otavilla Mechanical Contractors Inc. HVAC Contractor Office: 831-524-4484 Fax: 999-999-9999 Otavilla Mechanical Contractors Inc. Interior Contractor Office: 831-524-4484 Fax: 999-999-9999 American Plumbing Systems, Inc. Plumbing & Piping Contractor Office: 916-631-1315 Fax: 916-859-0993 Michael Venosta Plumbing Plumbing & Piping Contractor Office: 408-710-8653 Fax: 855-758-6268 Aec Structural Detailing, Inc. Professional Services Office: 661-706-1340 Fax: 661-706-1340 Linden Steel & Construction, Inc. Sub-Contractor/Specialty Office: 209-239-2160 Fax: 209-239-2178 Contractor Mckim Corporation Sub-Contractor/Specialty Office: 408-848-8700 Fax: 408-848-8778 Contractor Mission City Rebar Inc. Sub-Contractor/Specialty Office: 925-449-6999 Fax: 408-727-7051 Contractor Monterey Bay Rebar, Inc. Sub-Contractor/Specialty Office: 831-724-3013 Fax: 831-724-3151 Contractor Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

Nalevia Wallcovering Sub-Contractor/Specialty Contractor Presidential Fire Protection, Inc. Sub-Contractor/Specialty Office: 916-379-9199 Fax: 916-379-9099 Contractor Stormwater Specialists, Inc. Sub-Contractor/Specialty Office: 916-230-0370 Fax: 916-405-4180 Contractor Corix Water Products Supplier Office: 831-262-9778 Fax: 831-262-9778 Keith Day Trucking Supplier Office: 831-771-0126 Fax: 831-771-0109 Universal Doors Supplier Office: 000-000-0000 Fax: 000-000-0000 RFQ SOUTH PARKING FACILITY ELEVATOR UPGRADE - SJSU Addenda: 2 4/4/19 3:00 PM 19-00797 SJSU-371 San Jose Plan Issuer: SJSU - Contracts 408-924-6994 408-924-1910 Prebid Conf: 3/20 @ 2PM (Facilities, 2nd Floor, 404 E. San Fernando St., San Jose) The Trustees of California State University are circulating this Request for Qualifications (RFQ) to identify the necessary and desirable qualifications of design-build teams who wish to be considered for participation in a competitive Request for Proposals (RFP) for the design and construction of the South Parking Facility Elevator project.

Project Contact For Questions: Sylvia Sosa Email: [email protected] Bidders: Agbayani Construction Corp General Contractor Office: 650-994-9380 Fax: 415-665-9470 Blach Construction Company General Contractor Office: 408-244-7100 Fax: 408-244-2220 Oc Jones & Sons General Contractor Office: 510-526-3424 Fax: 510-526-0990 CDOT 04-0Q9804 INDIVIDUAL SLAB REPLACEMENT (RSC) Addenda: 0 4/4/19 2:00 PM 19-00093 04-0Q9804 Santa Clara County $600,000 Plan Issuer: CDot [email protected] 916-227-6098

In Santa Clara County In Gilroy And Morgan Hill From Leavesley Road To Cochrane Road Overcrossing The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-8, C-12. 35 Working Days * 5% DVBE Requirement

DYER HOUSE RENOVATION SANBORN PARK - COUNTY OF SANTA CLARA Addenda: 0 4/4/19 2:00 PM 19-00864 Saratoga $350,000 Plan Issuer: County of Santa Clara - Parks & Recreation 408-355-2200 Prebid Conf: 3/25 @ 10AM (Sanborn County Park) Improvements to the Ground Floor consist of the following: Demolition, salvaging of furniture and equipment, electrical, HVAC work, propane gas line work, interior work consisting of bathroom and kitchen remodel and amenities, new flooring, windows, doors, cabinetry, lighting, appliances, painting, chimney and fireplace work, porch decking, sanitary adjustments.

Project Contact For Questions: Tom McLaughlan 408-355-2208

Hard copies available for review at Santa Clara Builders Exchange Bidders: Coastwide Environmental Tech, Inc. Demolition Contractor Office: 831-761-5511 Fax: 831-761-5513 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

NEW LOS ALTOS HIGH SCHOOL NEW CLASSROOMS, ENGINEERING LAB & AUXILIARY GYM - MVLA UNION Addenda: 0 HIGH SCHOOL DISTRICT 4/4/19 2:00 PM 19-01022 Los Altos Plan Issuer: Mountain View Los Altos (MVLA) High School District 650-940-4650 Prebid Conf: MAND 3/7 @ 1PM (District Office, 1299 Bryant Ave, Mountain View) This is a Multi-Prime project. Prime bids shall be received for the following Bid Packages:

Bid Package A: General Trades Bid Package B: Earthwork & Paving Trades Bid Package C: Underground Utilities Trades Bid Package D: Electrical & Low Voltage Trades Bid Package E: Plumbing Trades Bid Package F: HVAC Trades Bid Package G: Fire Protection Trades Bid Package H: Painting Trades Bid Package I: Flooring Trades Bid Package J: Cabinet & Millwork Trades Bid Package K: Site Concrete Trades Bid Package L: Landscaping Trades Bidders: Sausal Corporation General Contractor Office: 925-568-2200 Fax: 925-568-2525 Mbs Engineering, Inc. Plumbing & Piping Contractor Office: 925-334-7200 Fax: 925-365-1718 Mission City Rebar Inc. Sub-Contractor/Specialty Office: 925-449-6999 Fax: 408-727-7051 Contractor NEW 8931-2019 LOCAL STREETS RESURFACING (NORTH) PROJECT - CITY OF SAN JOSE Addenda: 1 4/4/19 2:00 PM 19-01042 8931 San Jose $7,271,452 Plan Issuer: City of San Jose - DPW 408-535-8300

Clearing, grubbing, and removal of obstructions; milling (grinding), asphalt overlay; saw cutting, excavation; protection or adjustments of existing facilities and utilities; traffic control.

Project Contact For Questions: Binh Tran 408-794-6457

NEW 8936-ON-CALL CURED-IN-PLACE PIPE (CIPP) GENERAL CONTRACT 18-20 - CITY OF SAN JOSE Addenda: 0 4/4/19 3:00 PM 19-01044 8936 San Jose $1,000,000 Plan Issuer: City of San Jose - DPW 408-535-8300

On-call service to repair defective sanitary sewer pipeline with a diameter between 6 inches and 18 inches by means of a cured-in- place pipe (CIPP) liner method of rehabilitation, rehabilitate sewer manholes by means of lining, and CIPP point repair.

Project Contact For Questions: Lynn To

NEW 7202-WESTMONTAVENYE & HARRIET AVENUE SANITARY SEWER IMPROVEMENT - CITY OF SAN Addenda: 0 JOSE 4/4/19 3:00 PM 19-01055 7202 San Jose $4,445,586 Plan Issuer: City of San Jose - DPW 408-535-8300

Removal of existing 6-inch diameter vitrified clay pipe (VCP) and installation of approximately 6,300 feet of new 15-inch and 18-inch diameter VCP using open trench excavation along portions of Westmont Avenue in City of San Jose, and Silacci Drive, and Harriet Avenue in City of Campbell. This project will also install approximately 50 feet of 36-inch minimum diameter steel casing by jack and bore trenchless method with 8-inch and 12-inch dual barrel DIP carrier pipe and 12-inch single barrel HDPE air jumper under an existing box culvert along at Harriet Avenue. Additionally, the project will remove and replace existing manholes, install new manholes, remove and replace sanitary sewer service laterals, and reconnect active sanitary sewer service laterals to the sewer mains.

Project Contact For Questions: Titus Raceles Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

NEW HORACE MANN EXTERIOR IMPROVEMENTS- SAN JOSE UNIFIED SCHOOL DISTRICT (SJUSD) Addenda: 4 4/4/19 2:00 PM 19-01076 Z0502/3061C San Jose Plan Issuer: SJUSD-San Jose Unified School District 408-535-6071 Prebid Conf: MAND 2/27 & 2/28 @ 10:30AM Reconfiguring and enclosing the Sixth Street entry into Horace Mann Elementary.

Project Contact For Questions: Eric Berger, Van Pelt 303-502-6700 Email: [email protected]

RFQ 96-INCH & 87-INCH SETTLED SEWAGE PIPE REHABILITATION PROJECT - CITY OF SAN JOSE Addenda: 2 4/5/19 3:00 PM 19-00830 #ESD 9002 San Jose $3,725,000 Plan Issuer: City of San Jose - DPW 408-535-8300 Prebid Conf: 3/13 @ 9:30AM (San Jose-Santa Clara Regional Wastewater Facility, 700 Los Esteros Rd, San Jose) It is mandatory that all General Contractors\ who intend to submit a bid for the PROJECT, fully complete the Pre-qualification Submittal, provide all materials requested herein, and be approved by the CITY to be on the final pre-qualified bidders list. Project is scope is for re-establishment of the temporary flow reroute system furnished by the City, rehabilitation of the 96-inch SES pipeline using Cured in Place Pipe (CIPP) method and 87-inch x 136-in SES pipeline using Concrete Crown Repair, and site restoration.

Project Contact For Questions: Helena Choi 408-635-4010 Email: [email protected]

(REBID) LIGHT RAIL TRACK INTRUSION PREVENTION - SCVTA Addenda: 9 4/9/19 1:00 PM 19-00466 C19003F Santa Clara County Plan Issuer: SCVTA -Santa Clara Valley Transportation Authority 408-321-7189 Prebid Conf: 2/20 @ 10AM (SCVTA, Procurement, 3331 N. First St., Bldg A, San Jose) Construction of fencing and barriers to prevent pedestrians from crossing the tracks. Also, sliding gates will be placed at a specified interval along the fencing alignment to allow maintenance crew access the tracks.

Project Contact For Questions: Ehab Azab Email: [email protected] Bidders: Graniterock Asphalt /Road / Bridge / Heavy Office: 408-573-9364 Fax: 408-365-8349 Highway Contractor Bugler Construction General Contractor Office: 925-416-0700 Fax: 925-416-7746 George Bianchi Construction General Contractor Office: 408-453-3037 Fax: 408-452-1366 Granite Rock Company General Contractor Office: 408-574-1400 Fax: 408-365-9548 Proven Management General Contractor Office: 510-671-0000 Fax: 510-671-1000 PORTABLE REFRESH PROJECT AT BUBB, HUFF, LANDELS, LATHAM,THEUERKAUF, CRITTENDEN & Addenda: 2 GRAHAM SCHOOLS - MOUNTAIN VIEW WHISMAN SCHOOL DISTRICT 4/9/19 2:00 PM 19-00732 Mountain View $2,700,000 Plan Issuer: Greystone West Company 707-933-0624 707-996-8390 Prebid Conf: MAND 3/14 @ 1PM (Theuerkauf ES, 1625 San Luis Ave., Mtn View) Portable Refresh at Bubb Elementary School, Huff Elementary School, Landels Elementary School, Latham PreSchool, Monta Loma Elementary School, Theuerkauf Elementary School, Crittenden Middle School and Graham Middle School.

Project Contact For Questions: Dotty Selmeczki Email: [email protected] Bidders: Beals Martin General Contractor Office: 650-364-8141 Fax: 650-367-7645 Brco Constructors, Inc. General Contractor Office: 916-253-9373 Fax: 916-253-9377 Eternal Construction Inc General Contractor Office: 650-826-1190 Fax: 650-692-6686 Mar Con Company General Contractor Office: 510-639-1914 Fax: 510-639-1915 Pacific Contractors Group Inc. General Contractor Office: 818-993-5899 Fax: 818-993-5895 Premier Builders Inc. General Contractor Office: 408-710-5576 Fax: 000-000-0000 Premier Builders, Inc. General Contractor Office: 408-847-4622 Fax: 408-847-4655 Rodan Builders Inc. General Contractor Office: 650-508-1700 Fax: 650-508-1705 Strawn Construction, Inc General Contractor Office: 408-286-1299 Fax: 408-286-1288 Stormwater Specialists, Inc. Sub-Contractor/Specialty Office: 916-230-0370 Fax: 916-405-4180 Contractor Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

CDOT 04-0J6604 ROADWAY EXCAVATION AND MINOR CONCRETE PAVING Addenda: 0 4/9/19 2:00 PM 19-00091 04-0J6604 Santa Clara County $8,200,000 Plan Issuer: CDot [email protected] 916-227-6098

In Santa Clara County In San Jose And Milpitas From Route 101/680 Separation To Scott Creek Road Undercrossing The Contractor must have either a Class A license or any combination of the following Class C licenses which constitutes a majority of the work: C-8, C-12. 140 Working Days * 11% DBE Requirement Bidders: Ghilotti Construction Company, Inc. General Contractor Office: 707-585-1221 Fax: 707-585-1601 Granite Construction General Contractor Office: 408-327-7000 Fax: 408-327-7090 Granite Rock Company General Contractor Office: 408-574-1400 Fax: 408-365-9548 2019 SIDEWALK, CURB & GUTTER REPAIRS - CITY OF PALO ALTO Addenda: 0 4/9/19 3:00 PM 19-00932 174910 Palo Alto Plan Issuer: City of Palo Alto - DPW 650-329-2271

Removal and replacement of sidewalks, driveways, curbs, gutters, curb ramps and asphalt pavement; installation of catch basins and pipe including all incidental and related work

Project Contact For Questions: Holly Boyd Bidders: R & S Construction Management Inc. General Contractor Office: 415-297-1280 Fax: 415-534-6692 Stormwater Specialists, Inc. Sub-Contractor/Specialty Office: 916-230-0370 Fax: 916-405-4180 Contractor RFP FREMONT AVENUE PAVEMENT REHABILITATION - CITY OF LOS ALTOS Addenda: 0 4/9/19 4:00 PM 19-00960 TS-01056 Los Altos Plan Issuer: City of Los Altos - Engineering 650-947-2780

The work scope includes: • Project Management • Basemap Development • Pavement Rehabilitation Design Study • PS&E Development • Construction Support • Community Engagement

Project Contact For Questions: Jaime Rodriguez 650-947-2626 Email: [email protected]

CDOT 04-1Q9604 PAVEMENT DELINEATION Addenda: 0 4/10/19 2:00 PM 19-00103 04-1Q9604 Santa Clara County $2,490,000 Plan Issuer: CDot [email protected] 916-227-6098

In Santa Clara County From Route 101/85 Separation To 0.5 Mile North Of Winchester Boulevard Overcrossing And From 0.5 Mile South Of Stevens Creek Boulevard Overcrossing To Route 85/101 Separation The Contractor must have either a Class A license or the following Class C license which constitutes a majority of the work: C-32. 85 Working Days * 3% DVBE Requirement

POLICE BUILDING CHILLER REPLACEMENT - CITY OF SANTA CLARA Addenda: 0 4/10/19 3:00 PM 19-00914 CE-18-19-03 Santa Clara Plan Issuer: City of Santa Clara - DPW 408-615-3000 408-985-7936 Prebid Conf: Strongly Encouraged 4/3 @ 10AM Removal and replacement of existing chillers, pumps, and associated appurtenances.

Project Contact For Questions: Huy Nguyen 408-615-3073 Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

Aria Electric & Construction HVAC Contractor Office: 916-213-7575 Fax: 916-389-0720 Arc Perfect Solutions Inc Plumbing & Piping Contractor Office: 707-330-9087 2019 SIDEWALK REPAIR PROJECT - CITY OF MORGAN HILL Addenda: 1 4/10/19 2:30 PM 19-00948 Morgan Hill Plan Issuer: City of Morgan Hill, DPW 408-778-6480 Prebid Conf: MAND 3/26 @ 9AM (Corporation Yard Training Room, 100 Edes Court, Morgan Hill) Removal and replacement of damaged concrete sidewalk, curb & gutter, including root removal.

Project Contact For Questions: Cynthia Iwanaga 408-776-7383 Email: [email protected] Bidders: 101 Builders, Inc General Contractor Office: 408-842-3355 Fax: 000-000-0000 Monterey Peninsula Engineering General Contractor Office: 831-384-4081 Fax: 831-384-5078 FIRE STATION #2 & #6 ROLL UP DOOR REPLACEMENT - CITY OF SUNNYVALE Addenda: 1 4/10/19 3:00 PM 19-00956 F19-118 Sunnyvale Plan Issuer: City of Sunnyvale DPW 408-730-7403 000-000-0000 Prebid Conf: MAND 3/28 @ 10AM (Fire Station #6, 1282 Lawrence Station Road, Sunnyvale) Removal of 8 roll-up doors at two Fire Stations #2 and #6. The project will require replacement of 7 doors and reinstalling 1 of the existing doors.

Project Contact For Questions: Lisa Vo 408-730-7608 Email: [email protected]

Hard copies available for review at Santa Clara Builders Exchange Bidders: Varsity Doors, Inc. Sub-Contractor/Specialty Office: 661-231-3705 Fax: 661-374-8101 Contractor NEW PERFORMING ARTS INFRASTRUCTURE-ORCHESTRA PIT COVER RENOVATION - CITY OF Addenda: 1 SUNNYVALE 4/10/19 3:00 PM 19-01000 PW19-16 Sunnyvale Plan Issuer: City of Sunnyvale DPW 408-730-7403 000-000-0000 Prebid Conf: 3/27 @ 11AM (Meet in Lobby) Installing a new removable pit cover system that provides similar functionality to the current pit covers

Project Contact For Questions: Lisa Vo 408-730-7608 Email: [email protected]

MONTAGUE PEDESTRIAN OVERCROSSING - SCVTA Addenda: 6 4/11/19 2:00 PM 19-00726 C18231F Santa Clara County Plan Issuer: SCVTA-Contracts 408-321-7189 Prebid Conf: 3/14 @ 10AM (SCVTA, 3331 N. First St., Bldg. A, San Jose) Construct a steel, Warren-type truss, with a total length of 229 feet and 4 inches, including a 194-foot and 8-inch long single span crossing over Montague Expressway. A 32-foot-long cantilever extension at the south end of the pedestrian over crossing, will connect to the second floor of the existing parking garage at the Milpitas BART Station Campus. At the north end, the landing structure of the POC consists of (i) a platform area at the bridge deck level, (ii) a stairway, (iii) an elevator, and (iv) two rooms for communications, electrical, and elevator equipment. Both the bridge and the landing structure are supported by reinforced columns and Cast-In-Drill- Hole piles foundations. The Project includes construction of other facilities such as water service, drainage, an external sump pit for the elevator, landscape, drainage, Mid-West Guardrail system, lighting, new PG&E electricity services, and CCTV. Traffic handling is also an important aspect of the Project as lane and roadway closures for construction staging and bridge truss erection are required for Montague Expressway and adjacent roadways and facilities.

Project Contact For Questions: Cathy Clegg Email: [email protected] Bidders: Verux, Inc. Consultant Office: 916-930-6000 Fax: 888-840-5935 Biggs Cardosa Assoc. General Contractor Office: 408-296-5515 Fax: 000-000-0000 Disney Construction General Contractor Office: 650-259-9545 Fax: 650-259-9651 Dmz Builders General Contractor Office: 510-715-2237 Fax: 000-000-0000 Granite Construction General Contractor Office: 408-327-7013 Fax: 408-327-7090 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

Proven Management, Inc. General Contractor Office: 415-421-9500 Fax: 415-421-9600 8469-TAMIEN PARK PHASE II - CITY OF SAN JOSE (REBID) Addenda: 3 4/11/19 3:00 PM 19-00769 8469 San Jose $1,800,000 Plan Issuer: City of San Jose - DPW 408-535-8300

Demolition, clearing and grubbing, earthwork and grading, storm drainage, rigid and flexible paving, irrigation, landscaping, exercise area with resilient surfacing, natural turf field, stage, shade structures, security lighting, fencing, and miscellaneous site amenities.

Project Contact: Chris Mastrodicasa 408-535-8416 Bidders: Guerra Construction & Engineering, Inc General Contractor Office: 408-279-2027 Fax: 408-279-2044 Redgwick Construction Company General Contractor Office: 510-792-1727 Fax: 510-792-1728 California Commercial Fence Sub-Contractor/Specialty Office: 559-260-4699 Fax: 559-575-8244 Contractor SAN JOSE CITY COLLEGE (SJCC) PARKING LOT BOLLARDS - SAN JOSE EVERGREEN COMMUNITY Addenda: 3 COLLEGE DISTRICT 4/11/19 2:00 PM 19-00786 G2010.0197 San Jose Plan Issuer: San Jose Evergreen Community College District 408-270-6496 [email protected] Prebid Conf: MAND 3/14 @ 10AM (JGM Construction office @ TK3) Installing, and painting new steel bollards at the Parking Lot Pay Stations. Contractor must coordinate its work with a scheduled power shut-down when necessary, as well as ongoing day-to-day operations of an active school site. Bidders: Bosco Co. Facilities/ Bldg Maintenance Office: 866-233-2248 Fax: 408-404-4792 Ashron Construction General Contractor Office: 408-956-0909 Fax: 408-956-0918 Tri-Valley Excavating General Contractor Office: 408-442-4286 Fax: 925-862-0905 California Commercial Fence Sub-Contractor/Specialty Office: 559-260-4699 Fax: 559-575-8244 Contractor LEIGH HIGH SCHOOL SEISMIC RETROFIT BUILDING H - CAMPBELL UNION HIGH SCHOOL DISTRICT Addenda: 2 4/11/19 2:00 PM 19-00811 218-970242-050-02 San Jose $280,000 Plan Issuer: Campbell Union High School District [email protected] 408-371-0960 Prebid Conf: MAND 3/21 @ 9AM (Front of Administration Building) Seismic retrofit of Building H.

Project Contact For Questions: Dale Grogan408-371-0960 Xt. 2053 Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract Cve Contracting Group Inc. Dba Central Asbestos Abatement / Office: 559-222-1122 Fax: 559-222-1174 Valley Envi Hazardous Materials Contract Cal-Pacific Construction General Contractor Office: 650-557-1238 Fax: 650-557-1239 Fast Track Construction General Contractor Office: 310-215-3099 Fax: 310-215-3098 Mar Con Company General Contractor Office: 510-639-1914 Fax: 510-639-1915 Overhaul Construction General Contractor Office: 209-968-1947 Fax: 000-000-0000 LEIGH HIGH SCHOOL SWIMMING POOL ALTERATIONS - CAMPBELL UNION HIGH SCHOOL DISTRICT Addenda: 2 4/11/19 2:00 PM 19-00812 218-970248-050 San Jose $3,900,000 Plan Issuer: Campbell Union High School District [email protected] 408-371-0960 Prebid Conf: MAND 3/21 @ 9:30AM (Front of Admin Building) Demolition of existing pool and all associated equipment and facilities. new construction includes regrading, pool, pool decking, all associated mechanical and plumbing systems, miscellaneous site furnishings, and associated fencing.

Project Contact For Questions: Dale Grogan 408-371-0960 xt 2053 Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

4 Point Power Inc Electrical Contractor Office: 408-331-7617 Fax: 000-000-0000 Mar Con Company General Contractor Office: 510-639-1914 Fax: 510-639-1915 Mission City Rebar Inc. Sub-Contractor/Specialty Office: 925-449-6999 Fax: 408-727-7051 Contractor PROSPECT HIGH SCHOOL SWIMMING POOL ALTERATIONS - CAMPBELL UNION HIGH SCHOOL Addenda: 2 DISTRICT 4/11/19 2:00 PM 19-00815 218-970248-080 San Jose $3,900,000 Plan Issuer: Campbell Union High School District [email protected] 408-371-0960 Prebid Conf: MAND 3/21 @ 10:30AM (Front of Administration Building) Demolition of existing pool and all associated equipment and facilities. New construction includes regrading, pool, pool decking, all associated mechanical and plumbing systems, miscellaneous site furnishings, and associated fencing.

Project Contact For Questions: Dale Grogan 408 371-0960 xt 2053 Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract 4 Point Power Inc Electrical Contractor Office: 408-331-7617 Fax: 000-000-0000 Agbayani Constructors General Contractor Office: 510-783-1262 Fax: 510-783-1263 Calstate Construction General Contractor Office: 510-657-1800 Fax: 510-657-1810 Fast Track Construction General Contractor Office: 310-215-3099 Fax: 310-215-3098 Waterworks Industries, Inc. Pools / Foundations / Water Office: 707-837-7900 Fax: 707-837-7997 Displays Mission City Rebar Inc. Sub-Contractor/Specialty Office: 925-449-6999 Fax: 408-727-7051 Contractor 7890-RINCON SOUTH PARK DEVELOPMENT - CITY OF SAN JOSE Addenda: 1 4/11/19 3:00 PM 19-00962 7890 San Jose $1,198,900 Plan Issuer: City of San Jose - DPW 408-535-8300

Park area construction and renovation.

Project Contact For Questions: Mike Pruitt 408-535-8439

8720-MISCELLANEOUS SANITARY SEWER REPAIRS FY 2017-18 (PACKAGE III) - CITY OF SAN JOSE Addenda: 0 4/11/19 3:00 PM 19-00964 8720 San Jose $904,128 Plan Issuer: City of San Jose - DPW 408-535-8300 Prebid Conf: 4/2 @ 10AM (385 McCovely Lane, San Jose) & @ 11AM (3720 E. Hills Dr., San Jose) Abandonment of 8-inch vitrified clay pipe (VCP), installation of 8-inch vitrified clay pipe (VCP), installation of 8-inch polyvinyl chloride pipe (PVC), and installation of cured-in-place liner (CIPP). This project includes removal of existing manholes, construction of new manholes, replacement of manholes, point repairs to an existing 8-inch VCP sewer, reconnection/extension of active sanitary sewer service laterals, reconstruction of active sanitary sewer service laterals and reinstatement of active sanitary sewer service laterals. The partial removal and reconstruction of existing PCC sidewalk, curb, gutter, driveways, AC roadway pavement, and re-installing fencing in kind.

Project Contact For Questions:

8710-2019 LOCAL STREETS MICROSURFACING PROJECT - CITY OF SAN JOSE Addenda: 2 4/11/19 3:00 PM 19-00965 8710 San Jose $7,379,023 Plan Issuer: City of San Jose - DPW 408-535-8300

Crack sealing, the application of Microsurfacing, striping, marking, color pavement markings, signs, markers, and bicycle detector loops to the streets.

Project Contact For Questions: Matthew Sablan 408-794-6451 Bidders: Granite Rock Company General Contractor Office: 408-574-1400 Fax: 408-365-9548 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

RFQ 2X ROLLING STEEL DOORS INSTALLATION - COUNTY OF SANTA CLARA Addenda: 0 4/11/19 3:00 PM 19-00970 RFQ-FAF-FY19-0231 San Jose $16,000 Plan Issuer: County of Santa Clara Facilities & Fleet 408-993-4600 408-993-4895 Prebid Conf: 3/26 @ 10AM Furnish and install two, rolling steel doors at the Vector Control Building.

Project Contact For Questions: Phillip Chacon 408-993-4646 Email: [email protected]

Hard copies available for review at Santa Clara Builders Exchange Bidders: Varsity Doors, Inc. Sub-Contractor/Specialty Office: 661-231-3705 Fax: 661-374-8101 Contractor NEW MONTHLY PREVENTATIVE ELEVATOR MAINTENANCE - EMPLOYMENT DEVELOPMENT DEPARTMENT Addenda: 0 4/11/19 3:00 PM 19-01013 84547 San Jose Plan Issuer: Employment Development Department 916-653-0774 Prebid Conf: MAND 4/3 @ 11AM San Jose Monthly Preventative Elevator Maintenance and "As Needed" repair services for the EDD facility

Project Contract For Questions: Caitlin Clark 916-654-5351 Email: [email protected]

Hard copies available for review at Santa Clara Builders Exchange

NEW 8874-CAST IRON SEWER REPLACEMENT FY 18-19 PACKAGE II - CITY OF SAN JOSE Addenda: 1 4/11/19 3:00 PM 19-01057 8874 San Jose $874,515 Plan Issuer: City of San Jose - DPW 408-535-8300

Removal of 6- inch and 8-inch diameter cast iron pipe (CI), and the installation of 6-inch and 8-inch ductile iron pipe (DIP). This project also includes the replacement of existing and construction of new sanitary sewer manholes and the evaluation, repair and reconnection of sanitary sewer service laterals.

Project Contact For Questions: Bryan Pignone 408-793-4141

NEW 9027-PUBLIC WORKS GENERAL ENGINEERING CONTRACT FOR SEWER REPAIRS 2018-2020 Addenda: 0 (CONTRACT 1) - CITY OF SAN JOSE 4/11/19 3:00 PM 19-01058 9027 San Jose $1,000,000 Plan Issuer: City of San Jose - DPW 408-535-8300

Provide construction of various sanitary and storm sewer facilities/structures citywide. The work shall be implemented as individual project(s) for the purpose of maintaining, repairing and improving the existing sewer system and other utility infrastructure in the City.

Project Contact For Questions: Jefrey Jackson 408-535-7934

NGUYEN RESIDENCE (REQUEST FOR SUB BIDS) Addenda: 0 4/12/19 2:00 PM 19-00859 Saratoga Plan Issuer: Dale Rutledge Construction [email protected] 831-227-0817 000-000-0000

New residence; all trades needed. Bidders: Professional Grade Construction Concrete/Masonry Contractor Office: 408-605-6861 Fax: 213-443-9563 New Image Electric, Inc. Electrical Contractor Office: 831-809-2623 Fax: 831-809-2623 Universal Doors Supplier Office: 000-000-0000 Fax: 000-000-0000 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

RFB 60/12 KV 30/40/50 MVA POWER TRANSFORMER - CITY OF SANTA CLARA Addenda: 2 4/12/19 4:00 PM 19-00968 Santa Clara Plan Issuer: City of Santa Clara - DPW 408-615-3000 408-985-7936 Prebid Conf: 4/1 @ 1PM ( Power, 881 Martin Ave., Santa Clara) Provide and install a prefabricated, fully assembled 60/12 kV 30/40/50 Mega Volt Ampere (MVA) Power Transformer, in support of Silicon Valley Power, the City’s electric utility.

Project Contact For Questions: Jamil (Jay) Coleman Email: [email protected]

2019 PAVING MAINTENANCE GROUP 2 - SAN JOSE UNIFIED SCHOOL DISTRICT (SJUSD) Addenda: 1 4/16/19 1:00 PM 19-00941 80044/3074C San Jose Plan Issuer: SJUSD-San Jose Unified School District 408-535-6071 Prebid Conf: MAND 3/27 @ 10:30AM (Willow Glen Middle School, 2105 Cottle Ave, San Jose) Repairing asphalt and concrete, grinding and seal coating, striping and other enhancement for ADA regulations at Discovery Charter School at Randol Elementary School, Pine Hill School at Hammer Elementary School, Willow Glen Warehouse, Willow Glen Middle School and Willow Glen High School.

Project Contact For Questions: Jenny Choi, Van Pelt 707-315-3918 Email: [email protected] Bidders: American Asphalt Repair & Resurfacing General Contractor Office: 510-723-0280 Fax: 510-723-0288 Co., Inc. Tri-Valley Excavating General Contractor Office: 408-442-4286 Fax: 925-862-0905 PROSPECT HIGH SCHOOL ELECTRICAL INFRASTRUCTURE - CAMPBELL UNION HIGH SCHOOL Addenda: 0 DISTRICT 4/16/19 11:00 AM 19-00954 218-980011-080-01 San Jose $975,000 Plan Issuer: Campbell Union High School District [email protected] 408-371-0960 Prebid Conf: MAND 3/29 @ 9AM Reroute existing electrical lines on canopies and under Building K to be underground and avoid building footing area. Relocate electrical panel(s). Reconnect all electrical service after work is complete.

NEW BIKE BOULEVARD IMPROVEMENTS PHASE 1 - CITY OF CUPERTINO Addenda: 0 4/16/19 2:00 PM 19-01020 2017-01.05 Cupertino $1,500,000 Plan Issuer: City of Cupertino 408-777-3354 408-777-3333

The project includes associated civil improvements including sidewalk, curb ramps and roadway markings and reconstruction at or near the following intersections: - NORTH PORTAL AVENUE FROM STEVENS CREEK BOULEVARD TO MERRITT DRIVE - MERRITT DRIVE FROM PORTAL AVENUE TO LARRY WAY - GREENLEAF DRIVE AT BEARDON DRIVE TO CASTINE AVENUE - BANDLEY DRIVE AT MARIANI AVENUE - TORRE AVENUE AT TOWN CENTER LANE.

EVERGREEN VALLEY COLLEGE (EVC) PHYSICAL EDUCATION ACCESSIBILITY IMPROVEMENTS - SAN Addenda: 2 JOSE EVERGREEN COLLEGE DISTRICT 4/17/19 2:00 PM 19-00925 X2016.0011 San Jose $731,000 Plan Issuer: San Jose Evergreen Community College District, Cindy Giesing 408-270-6487 Prebid Conf: 4/1 @ 10AM (Gilbane-Cordoba CM Office, Evergreen Campus) Improvements to pathway accessibility and site issues related to the areas around the PE Building. This includes improvements to the physical condition and slopes of walkways, the condition and railings at stairway(s) and ramps, site and landscape conditions (ponding, drainage, irrigation and planting), and student comfort {benches).

Project Contact For Questions: Daniel Powell 408-274-6009 Email: [email protected] Bidders: 4 Point Power Inc Electrical Contractor Office: 408-331-7617 Fax: 000-000-0000 Mission City Rebar Inc. Sub-Contractor/Specialty Office: 925-449-6999 Fax: 408-727-7051 Contractor Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

RFP SECURITY SYSTEMS ASSESSMENT & DESIGN-CONSULTING SERVICES - SAN JOSE EVERGREEN Addenda: 0 COLLEGE DISTRICT 4/17/19 2:00 PM 19-00926 X2016.0018 San Jose Plan Issuer: San Jose Evergreen Community College District, Cindy Giesing 408-270-6487 Prebid Conf: MAND 3/28 @ 9AM ( Evergreen Valley College, 3095 Yerba Buena, San Jose @ Gilbane/Cordoba Construction Offices (west of Student Parking Lot 5) & @ 1PM (San Jose City College, 2100 Moorpark Ave, San Jose @ the Brailsford & Dunlavey Offices, near Building K near 787 Mansfield Ave) The District is seeking a consultant to provide Security System Consulting Services, including review and recommendations, for district wide access control, intrusion alarm, and video surveillance systems to be fully integrated and centrally monitored.

Project Contact For Questions: Cindy Giesing 408-270-6487 Email: [email protected]

BICYCLE IMPROVEMENTS I-280/PAGE MILL ROAD - COUNTY OF SANTA CLARA Addenda: 1 4/18/19 2:00 PM 19-00748 Santa Clara County Plan Issuer: County of Santa Clara Roads & Airports 408-573-2440 Prebid Conf: 3/19 @ 9:30AM (Roads & Airports, 101 Skyport Dr., Room 101, San Jose) Pavement marking removal, restriping, microsurfacing (type 2), sign installation, bike detection, lighting/flashing beacon installation, minor excavation, construction of bike cut through.

Project Contact For Questions: Paul Pascoal 408-573-2485 Email: [email protected]

Hard copies available for review at Santa Clara Builders Exchange Bidders: California Pavement Maintenance Co., General Contractor Office: 916-381-8033 Fax: 916-381-3703 Inc. Dba Cpm Stormwater Specialists, Inc. Sub-Contractor/Specialty Office: 916-230-0370 Fax: 916-405-4180 Contractor ENROUTE-COLUMBIA MIDDLE SCHOOL PAINTING & LANDSCAPE - SUNNYVALE SCHOOL DISTRICT Addenda: 0 4/18/19 2:00 PM 19-00909 Sunnyvale Plan Issuer: Sunnyvale School District 408-522-8200 Prebid Conf: MAND 4/4 @ 1PM (825 West Iowa Avenue, Sunnyvale) NOTICE TO BIDDERS IS POSTED ONLY. BID DOCUMENTS WILL BE AVAILABLE AFTER 3/27/19.

Painting and associated prep work of all buildings on campus along with multiple murals. New landscaping on the interior portion of the campus.

RFB BOILER MAINTENANCE & REPAIR SERVICES - CITY OF SAN JOSE Addenda: 0 4/18/19 2:00 PM 19-00966 RFB-18-19-33 San Jose Plan Issuer: City of San Jose - DPW 408-535-8300

Provide labor, materials and equipment for boiler maintenance and repair services at various City facilities on an as needed basis

Project Contact For Questions: Rhea Schmitz 408-535-7056 Email: [email protected]

NEW FY 19 CITYWIDE PAVEMENT MAINTENANCE PROJECT - CITY OF GILROY Addenda: 0 4/18/19 2:00 PM 19-01031 19-PW-252 Gilroy Plan Issuer: City of Gilroy - DPW 408-846-0234

Construction of concrete curb and gutter repairs, access ramps, weed kill, crack seal, sweeping asphalt point repairs, micro-surfacing, rubberized cape seal, asphalt grind and hot mix asphalt overlay, utility lowering and adjusting and pavement striping and markings and clean up on various streets throughout the City. Bidders: Monterey Peninsula Engineering General Contractor Office: 831-384-4081 Fax: 831-384-5078 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

RFP FIRE LIFE SAFETY SYSTEMS INSPECTIONS, TESTING, MAINTENANCE, & REPAIR SERVICES - Addenda: 1 CITY OF SAN JOSE 4/19/19 2:00 PM 19-00866 RFP 18-19-04 San Jose Plan Issuer: City of San Jose - DPW 408-535-8300 Prebid Conf: MAND 3/25 @ 9AM (SJIA, Boeing Conference Room, 2075 Airport Blvd., San Jose) Provide all labor, equipment, and material to inspect, test, maintain and repair Fire Life-Safety System at various City facilities as required by the Department of Aviation.

Project Contact For Questions: Lisa Watt 408-535-7058 Email: [email protected]

NEW LEONG DRIVE WATER & SANITARY SEWER MAIN REPLACEMENT - CITY OF MOUNTAIN VIEW Addenda: 0 4/22/19 2:00 PM 19-01056 16-22 Mountain View $5,900,000 to $6,170,000 Plan Issuer: City of Mountain View, DPW 650-903-6311 Prebid Conf: Strongly Encouraged 4/10 @ 10AM (City's Municipal Operations Center, 231 North Whisman Rd., Mtn View) Replacement of the existing water and sanitary sewer mains located within and adjacent to Leong Drive and other related improvements to the water and sanitary sewer system.

Project Contact For Questions: Tina Seng Email: [email protected] Bidders: Ranger Pipelines, Inc. General Contractor Office: 415-822-3700 Fax: 415-822-3703 Bedrock Engineering, Inc. Professional Services Office: 559-645-4849 Fax: 559-645-4869 SAN JOSE CITY COLLEGE (SJCC) PARKING LOT FOG COAT & PAINTING - SAN JOSE EVERGREEN Addenda: 1 COLLEGE DISTRICT 4/24/19 2:00 PM 19-00888 G2010.0198 San Jose Plan Issuer: San Jose Evergreen College District 408-270-6481 Prebid Conf: MAND 3/27 @ 10AM (JGM Construction Office, TK3, SJCC) The Project entails prepping existing asphalt such as cleaning and crack filling, slurry sealing, installing wheel stops, installing signage, and providing necessary painting and striping. Contractor must provide traffic control and private locator services as needed to complete work. Bidders: Onpoint Construction General Contractor Office: 650-347-3090 Fax: 650-347-3099 Tri-Valley Excavating General Contractor Office: 408-442-4286 Fax: 925-862-0905 NEW SUNNYVALE PUBLIC LIBRARY LED LIGHTING RETROFIT REBID - CITY OF SUNNYVALE Addenda: 0 4/24/19 3:00 PM 19-01073 F19-084 Sunnyvale Plan Issuer: City of Sunnyvale DPW 408-730-7403 000-000-0000 Prebid Conf: MAND 4/10 @ 8AM Retrofitting all designated lower ceiling light fixtures to new LED retrofit bulbs at the Sunnyvale Public Library.

Project Contact For Questions: Jeremy leung 408-730-7632 Email: [email protected]

Hard copies available for review at Santa Clara Builders Exchange Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

TENNIS COURTS RESURFACE & REPAIR LEIGH, DEL MAR, WESTMONT HIGH SCHOOLS - CAMPBELL Addenda: 2 UNION HIGH SCHOOL DISTRICT 4/25/19 2:00 PM 19-00814 218-980020-000 San Jose $780,000 Plan Issuer: Campbell Union High School District [email protected] 408-371-0960 Prebid Conf: 3/22 @ 8:30AM (Westmont HS, 4805 Westmont Ave, Campbell) @ 9:30AM (Leigh HS, 5210 Leigh Ave., San Jose) @ 10:00AM (Del Mar HS,1224 Del Mar Ave, San Jose) Leigh High School: Repair of existing cracks as required, install new acrylic surface, install new nets and posts. Del Mar High School: Remove existing asphalt and fencing between courts. Install new asphalt, acrylic surface, fencing between courts, nets and posts. Westmont High School: Remove existing asphalt and fencing between.

Project Contact For Questions: Dale Grogan 408-371-0960 xt 2053 Email: [email protected]

Bidders: Guerra Construction & Engineering, Inc General Contractor Office: 408-279-2027 Fax: 408-279-2044 ENROUTE-CUMBERLAND TEMPORARY CLASSROOM PORTABLES - SUNNYVALE SCHOOL DISTRICT Addenda: 0 4/25/19 2:00 PM 19-00913 Sunnyvale Plan Issuer: Sunnyvale School District 408-522-8200 Prebid Conf: MAND 4/4 @ 2PM (825 W. Iowa Avenue, Sunnyvale) NOTICE TO BIDDERS IS POSTED ONLY. BID DOCUMENTS WILL BE AVAILABLE AFTER 3/27/19.

The disconnect and transportation of 4 portables from Columbia Middle school to Cumberland Elementary school, along with the associated clean up work and Columbia and new infrastructure work at Cumberland. Additionally, there is a new PC Shade Cover being installed at Cumberland and the disconnect of an existing portable at Cumberland so that it can be hauled off by the vendor it is currently on lease from.

NEW SCC BEHAVORIAL HEALTH SERVICES TI - COUNTY OF SANTA CLARA Addenda: 0 4/25/19 2:00 PM 19-01039 Campbell Plan Issuer: County of Santa Clara - Capital Programs 408-993-4600 Prebid Conf: MAND 4/2 @ 10AM Renovation of one 23,950 SF building including but not limited to replacement of interior partitions, finishes, roofing, addition of skylights and modification of mechanical, plumbing, electrical and security systems. Accessibility upgrades inclusive of but not limited to new door thresholds and new restrooms. Modifications to the site including site accessibility, accessible parking, installation of EV charging stations, exterior light replacement on the exterior of the building, and modification of an existing patio.

Project Contact For Questions: Annie Shi 408-993-4784 Email: [email protected]

NEW EMERGENCY STANDBY GENERATOR PARATRANSIT FACILITY - SCVTA Addenda: 0 4/25/19 2:00 PM 19-01068 C18227 San Jose $300,000 to $500,000 Plan Issuer: SCVTA-Contracts 408-321-7189 Prebid Conf: 4/10 @ 10AM (Eastridge Paratransit Facility) Furnish and install a new 250 kW Diesel Fueled Standby Generator Set with a 660 Gallon Sub-base belly tank.

Project Contact For Questions: David Montenegro Email: [email protected] Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

Santa Cruz County GREEN VALLEY RD PAVEMENT PRESERVATION Addenda: 0 4/3/19 11:00 AM 19-00942 ST-18-02 Watsonville $1,300,000 Plan Issuer: City of Watsonville 831-768-3115 831-763-4065

The work includes asphalt pavement removal; grading roadbed to indicated grades; compaction of base; removal and replacement of concrete curb ramps; construction of sidewalks, curbs, and gutters (as noted on plans); replacing water valve boxes; protecting and raising to grade valves and manholes in paving area; provide and install electrical conduit and pull boxes for future fiber optic lines; install new reinforced concrete guardrail, modify existing metal beam guardrail, provide and install striping and signage; maintaining traffic through work area; community communication and notifications of work schedule. The contractor shall implement at all times, the measures required by the Water Pollution Control Plan. The disturbed soil shall be seeded.

Project Contact: Patrice Theriot Email: [email protected] Bidders: Granite Rock Company General Contractor Office: 408-574-1400 Fax: 408-365-9548 Keith Day Trucking Supplier Office: 831-771-0126 Fax: 831-771-0109 2019 SURFACE SEAL PROJECT Addenda: 1 4/4/19 2:00 PM 19-00805 c400810 Santa Cruz $1,000,000 to $1,200,000 Plan Issuer: City of Santa Cruz 831-420-5160 831-420-5161

The work to be done consists in general of resurfacing with a double SAMI-R seal and Microsurfacing.

Project Contact: Ricardo Valdes Email: [email protected] Bidders: California Pavement Maintenance Co., General Contractor Office: 916-381-8033 Fax: 916-381-3703 Inc. Dba Cpm COLLEGE NINE AND TEN DINING HALL - DINING COMMONS DISH ROOM MODIFICATIONS Addenda: 0 4/4/19 3:00 PM 19-00820 5510-043A Santa Cruz $2,000,000 Plan Issuer: UCSC Physical Planning & Construction 831-459-2366 831-459-5540 Prebid Conf: MAND 3/19 @ 1:30pm- Physical Planning, Development & Operations Conference Room 151H Alterations to the dish room, entry lobby, point of sales and associated building accessibility upgrades, as shown on the plans and specifications.

Project Contact: Luis Roa Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract NEW APTOS HIGH SCHOOL STRUCTURAL REPAIRS & RE-ROOFING Addenda: 1 4/4/19 2:00 PM 19-00978 19-02-04-802-8105 Aptos

Prebid Conf: MAND 3/20 @ 2pm- site The Project consists of: a. Removal & replacement of existing roofing including flashing, gutters & downspouts and roof sheathing. b. Removal and repairs of dry rot on structural beams, rafters & sheathing. c. Epoxy repairs on existing wood columns. d. Painting of all repairs and exposed beams, rafters and columns e. This work will be done in phases as listed in the Preliminary Schedule.

PREVAILING WAGE

Project Contact: Erlindo Fernandez Email: [email protected] Bidders: Ausonio Incorporated General Contractor Office: 831-970-5360 Fax: 831-633-3389 Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

WATER STREET WATER MAIN REPLACEMENT Addenda: 0 4/8/19 2:00 PM 19-00935 CWO 2018-003 Santa Cruz $2,500,000 to $2,700,000 Plan Issuer: City of Santa Cruz 831-420-5327 831-420-5201

1) NO Traffic Loop Repair Required (Item Removed) 2) Striping & marking that needs replacement will be water based traffic paint with top dressing of glass beads. NO Thermoplastic striping or marking required. 3) The Geotechnical compaction testing consultant requirements have changed. 4) A recently installed fiber optic line was added to the plans-shown on sheets 4,5,6 & 10. The work to be completed under this Contract consists of furnishing all materials, labor, equipment, fuel and tools required to install approximately 150 feet of 16” pipe, 2,310 feet of 12” pipe, 120 feet of 8” pipe, 260 feet of 6” pipe, 15 feet of 4” pipe, 10 pipeline connections, 46 water service re-connections (3/4” - 6”), 7 water service renewals, and 90 feet of slip lining, as shown on the Plans and detailed in the Specifications. Construction activities will occur on Water Street between Water Street Bridge and Reed Way and on part of Ocean Street at the Water St. & Ocean St. intersection. Work performed at the Water St. & Ocean St. intersection will be performed as night work. Night work may be required at the Water St. & Market St. intersection depending on proposed traffic control & staging of work.

Project Contact: Nicole Haley Email: [email protected] Bidders: Monterey Peninsula Engineering General Contractor Office: 831-384-4081 Fax: 831-384-5078 STEVENSON LOWER QUAD 5-8 UTILITY UPGRADE Addenda: 1 4/9/19 2:00 PM 19-00778 1700-182 Santa Cruz $1,085,000 Plan Issuer: UCSC Physical Planning & Construction 831-459-2366 831-459-5540 Prebid Conf: MAND 3/19 @ 10am- Physical Planning, Development & Operations Conference Room #151H, Barn G Project includes replacing existing gas, domestic water and fire water lines to Stevenson dorms 5-8. Includes new fire double check, new master domestic meter assembly and new gas and water meters in each building. Provide new sewer lines to buildings 5 & 8. Replace all concrete and asphalt from trenching. Provide new irrigation controller and master valve. Provide various stormwater improvements to building 5-8.

Project Contact: Nathan Weiner Email: [email protected] Bidders: Mbs Engineering, Inc. Plumbing & Piping Contractor Office: 925-334-7200 Fax: 925-365-1718 SANTA CRUZ HARBOR ALDO’S SEAWALL REPLACEMENT Addenda: 2 4/10/19 11:00 AM 19-00692 F027 Santa Cruz Plan Issuer: Santa Cruz Port District [email protected] 831-475-6161 831-475-9558 Prebid Conf: MAND 3/13 @ 10am- 135 Fifth Avenue, Santa Cruz Construction of a new steel sheet pile seawall in front of an existing steel sheet pile seawall. Modification of existing public wharf and rip rap to accept new sheet pile wall. Modification of AA-Dock gangway landing, demolition of existing restaurant building foundation (restaurant building demolition by Santa Cruz Port District) and demolition of existing wood pile supported deck, all as shown in the Proposal Packet and as specified in the Special Provisions and the permits appended hereto.

PREVAILING WAGE Bidders: Coastwide Environmental Tech, Inc. Demolition Contractor Office: 831-761-5511 Fax: 831-761-5513 Granite Construction General Contractor Office: 831-763-6100 Fax: 831-761-1042 Granite Rock Company General Contractor Office: 408-574-1400 Fax: 408-365-9548 R.E. Staite Engineering, Inc. General Contractor Office: 619-233-0178 Fax: 619-233-3706 Mission City Rebar Inc. Sub-Contractor/Specialty Office: 925-449-6999 Fax: 408-727-7051 Contractor Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

NEW PERFORMING ARTS CENTER AND SITE WORK AT MOUNTAIN ELEMENTARY SCHOOL Addenda: 1 4/10/19 2:00 PM 19-00776 19-01 Soquel Plan Issuer: MADI Group [email protected] 800-725-0571 Prebid Conf: MAND 3/13 @ 2pm- site The Scope of Work is the construction of a new performing arts center and site work on an approximately 7.55-acre District-owned site located at 3042 Old San Jose Road, in Soquel, Santa Cruz County, California. The Project will include approximately 2,880 square feet of building and approximately 10,000 SF of sitework outside of the building footprint. The Contractor whose proposal is determined to offer the best value to the District pursuant to this RFP must execute the Lease- Leaseback Agreement, the Site Lease, and the Sublease prior to the Board’s award of the Contract to Contractor.

PREVAILING WAGE Bidders: Schreder And Brandt Mfg, Inc. General Contractor Office: 530-228-9242 Fax: 530-899-2683 Monterey Structural Steel Steel Contractor Office: 831-768-1277 Fax: 831-768-1352 SANTA CRUZ HARBOR PILE REPAIR AND REPLACEMENT - PHASE 2 Addenda: 0 4/10/19 10:00 AM 19-00947 2019-F005 Santa Cruz Plan Issuer: Santa Cruz Port District [email protected] 831-475-6161 831-475-9558

The Phase 2 work to be done consists, in general, of removal and replacement of eighty (80), 14” to 16” OD piles ranging in length from 50 to 75 feet, pile caps, pile guides and appurtenant hardware as needed with hollow, 14” steel piles with a high density polyethylene (HDPE) sleeve (color: black with white pile cap). HDPE sleeve must penetrate the mud line no less than 2 feet. Contractor shall verify depth of embedment in field before fabrication and installation of replacement piles identified in Appendix B – Pile Removal and Replacement Schedule and Vicinity Maps. Pile driving work will be accomplished with a 2.5-inch diameter water jet pipe system that drives piles to within 4 feet of tip. Piles will then be seated as necessary for embedment relative to geotechnical conditions using a dynamic hammer. Geotechnical and boring data from original harbor construction is appended as Appendix C. Work shall be performed in accordance with all permits, including, but not limited to completion of all work by November 30, 2019; deployment of silt booms for turbidity control prior to pile removal and installation; and a limit of 6 piles per workday. Contractor shall retain biologist(s) for required pre-construction survey, training and on-site monitoring during construction. Access to portions of the work will require use of small boat(s) and a floating barge for workers and pile driving equipment, all as shown in the Proposal Packet and as specified in the Special Provisions and the permits appended hereto.

PREVAILING WAGE

NEW WELL 19 GENERATOR REPLACEMENT Addenda: 0 4/10/19 11:00 AM 19-00976 WA-19-01 Watsonville $190,000 to $230,000 Plan Issuer: City of Watsonville 831-768-3115 831-763-4065 Prebid Conf: 4/3 @ 1pm- 6 Eureka Canyon Road, Watsonville Well 19 Generator Replacement Project will consist of the provision, installation, and testing of new standby backup power generator in case of emergency to Well 19 and the Corralitos Filtration Plant, including all labor, materials, tools and equipment necessary for the complete and satisfactory installation. The current site contains an existing portable generator to be disconnected and decommissioned. The new diesel, stationary emergency-standby generated shall be rated for 350 kW, wired for 277/480 VAC, three phase, 60 HZ, with Level 1 Acoustic Enclosure, control panel, minimum 400 usable gallon double-wall base tank, spill containment, and vent extension. The Contractor shall ensure the new generator is compatible with and meets demands of the existing electrical system and Monterey Air Resources Board (MBARD) requirements. New conduits for electrical, instrumentation, controls wiring may tie into the existing conduits where possible, with new conduits, wiring, panels, etc. provided as needed for complete installation. The existing automatic transfer switch is to remain in service. The Contractor shall be responsible for successful start-up and testing. A new concrete pad shall be provided and installed for the generator. Existing asphalt paving shall be removed and replaced as needed to accommodate the new pad and conduit trenching.

Project Contact: Clara Cawaling Email: [email protected] Bidders: Mig Electric Electrical Contractor Office: 831-524-8507 Varni, Darrel Electric Inc. Electrical Contractor Office: 831-761-2288 Fax: 831-761-2285 James Day Construction Inc. Dba Coastal General Contractor Office: 707-994-0437 Fax: 707-994-8504 Mountain Electric Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

EUREKA CANYON ROAD PM 0.36 STORM DAMAGE REPAIR Addenda: 1 4/11/19 2:00 PM 19-00904 P79143 Corralitos $220,000 to $260,000 Plan Issuer: County of Santa Cruz 831-454-2160 831-454-2385

This project involves the construction of steel pile and timber lagging retaining wall requiring earth excavation and backfill, wall gutter and gutter drain system, gabion end closures, Midwest guardrail system with end treatment and transition to adjacent existing metal beam guardrail, asphalt pavement replacement, slurry sealing, thermosplastic traffic striping, asphalt dike, drainage facilities, roadway embankment backfill, erosion control and revegetation.

Project Contact: Riley Gerbrandt Email: [email protected] Bidders: Pacific Coast Drilling Co., Inc. Sub-Contractor/Specialty Office: 707-778-8316 Fax: 707-789-9542 Contractor Superior Hydroseeding Sub-Contractor/Specialty Office: 831-763-1811 Fax: 831-763-1409 Contractor Keith Day Trucking Supplier Office: 831-771-0126 Fax: 831-771-0109 STUDENT HOUSING TELECOMMUNICATIONS UPGRADES PHASE 2 - COWELL, STEVENSON AND Addenda: 1 COLLEGE NINE APARTMENTS 4/12/19 2:00 PM 19-00779 9805B Santa Cruz $1,229,000 Plan Issuer: UCSC Physical Planning & Construction 831-459-2366 831-459-5540 Prebid Conf: MAND 3/13 @ 1pm- Barn G, PPDO Conference Room 151H Construction of STUDENT HOUSING TIU PHASE 2 includes modifications to existing Telecommunications Rooms, electrical power for telecommunications, grounding for the telecommunication systems, floor and wall mounted communications racks and cabinets, communications cable tray, communications horizontal station cabling using new and existing pathway, placement of University furnished wireless access points at interior and exterior locations, demolition of existing communications riser and horizontal station cabling, demolition of existing broadband video system. Work will be required to be performed over the Summer break and completed in time for student move-in for Fall quarter. Contractor will be required to coordinate with University’s Representative for work in buildings being occupied by summer conference attendees.

Project Contact: Joshua Schneider Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Asbestos Abatement / Office: 831-761-5511 Fax: 831-761-5513 Hazardous Materials Contract NEW STEVENSON RESIDENCE HALLS 5, 6, 7 & 8 - INTERIOR REFRESH Addenda: 0 4/12/19 3:00 PM 19-00996 1700-186 Santa Cruz $2,185,000 Plan Issuer: UCSC Physical Planning & Construction 831-459-2366 831-459-5540 Prebid Conf: MAND 3/27 @ 9am- Physical Plant Training Room located behind the Carriage House which is adjacent to Barn G Interior finish upgrades to four Student Residence Halls at Stevenson College. Work to include labor and materials to provide: new painting of all interior walls, ceilings and doors; replacement carpeting and base in all bedrooms and corridors; replacement of light fixtures and switches in corridors, stairwells and bedrooms; and replacement of drinking fountains and addition of new where indicated. Demolition and abatement as required.

Project Contact: Gerald Greenleaf Email: [email protected]

NEW MOUNT HAMILTON - RESIDENCE DEMOLITION AND SITE RESTORATION Addenda: 0 4/17/19 3:00 PM 19-00995 6643 Santa Cruz $200,000 Plan Issuer: UCSC Physical Planning & Construction 831-459-2366 831-459-5540 Prebid Conf: MAND 4/4 @ 11am- UCO Complex Dining Hall Project includes: Abatement of existing building; Removal and disposal of structure and foundation; Restoration of site.

Project Contact: Arthur Wellersdick Email: [email protected] Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

NEW BUENA VISTA - LEVEE REPAIRS RFP 2019 Addenda: 1 4/17/19 10:00 AM 19-01054 Watsonville Plan Issuer: Housing Authority of the County of Santa Cruz 831-454-5928 831-469-3719

The Housing Authority of the County of Santa Cruz invites proposals from appropriately licensed contractors for repair of levee at wastewater facility.

Project Contact: Peter Rogers, Facility Manager Email: [email protected]

BLDG 1000 HVAC REPAIR/REPLACE COUPLINGS, CONDENSATE AND CONTROLS Addenda: 0 4/18/19 2:00 PM 19-00940 B19-05 Aptos $450,000 Plan Issuer: Cabrillo College 831-477-5613 Prebid Conf: MAND 4/4 @ 10am- Purchasing, Bldg 2030, 6500 Soquel Dr, Aptos This project includes redesign of condensate drain piping, provide thermal expansion joint fitting & welded piping between gridlines, replace all hot water heating steel piping main couplings with temperature rated fittings, provide pre-balance tab services and final balancing tab services as described. Upgrade of existing HVAC System Central Controls with Tridium DDC System.

PREVAILING WAGE

Questions: Gale Stevens Email: [email protected] Bidders: Coastwide Environmental Tech, Inc. Demolition Contractor Office: 831-761-5511 Fax: 831-761-5513 American Plumbing Systems, Inc. General Contractor Office: 916-631-1315 Fax: 916-859-0993 Aria Electric & Construction HVAC Contractor Office: 916-213-7575 Fax: 916-389-0720 NEW SOQUEL VILLAGE SEWER PIPE REHABILITATION Addenda: 0 4/18/19 2:00 PM 19-00992 Soquel $688,670 Plan Issuer: County of Santa Cruz 831-454-2160 831-454-2385

This project involves the replacement of Sanitary Sewer Main, and Replacement/Rehabilitation of Sanitary Sewer Manholes in various county roads in Soquel Village and in some easements on private property.

Project Contact: Marcella Bailey Email: [email protected]

NEW 2019 MEAURE D RESURFACING Addenda: 0 4/18/19 2:00 PM 19-01072 Santa Cruz County $1,470,548 Plan Issuer: County of Santa Cruz 831-454-2160 831-454-2385

This project involves the construction of pavement grinding, pavement pulverization, digouts, asphalt concrete overlays, microsurfacing, rubberized cape seals, striping, pavement markings, subdrain, and adjusting street monuments to grade.

Project Contact: Casey Carlson Email: [email protected]

NEW EXTERIOR MODIFICATIONS OF GYMNASIUM AT NATURAL BRIDGES ELEMENTARY Addenda: 1 4/24/19 1:30 PM 19-01036 2019-02 Santa Cruz

Prebid Conf: 3/13 @ 10am & 4/4 @ 10:30am- site The proposed project will include: interior upgrades, remove and replace exterior finishes and minor ADA upgrades.

PREVAILING WAGE

Project Contact: Presley Obenshain Email: [email protected] Projects Out To Bid

Name Bid Date Time OPR# Contract # Location Estimate

NEW STUDENT HOUSING TELECOMMUNICATIONS UPGRADES PHASE 2 – RACHEL CARSON RESIDENCE Addenda: 0 HALLS AND APARTMENTS 4/26/19 2:00 PM 19-00997 9805C Santa Cruz $1,151,000 Plan Issuer: UCSC Physical Planning & Construction 831-459-2366 831-459-5540 Prebid Conf: MAND 3/26 @ 1pm- Barn G, PPDO Conference Room 151H Construction of STUDENT HOUSING TIU PHASE 2 includes modifications to existing Telecommunications Rooms, electrical power for telecommunications, grounding for the telecommunication systems, floor and wall mounted communications racks and cabinets, communications cable tray, communications horizontal station cabling using new and existing pathway, placement of University furnished wireless access points at interior and exterior locations, demolition of existing communications riser and horizontal station cabling, demolition of existing broadband video system. Work will be required to be performed over the Summer break and completed in time for student move-in for Fall quarter.

Project Contact: Joshua Schneider Email: [email protected]

NEW PLUMBING SERVICE & REPAIRS AT CABRILLO COLLEGE Addenda: 0 4/30/19 2:00 PM 19-01048 B19-08 Aptos Plan Issuer: Cabrillo College 831-477-5613

Cabrillo is requesting Plumbing Service & Repair Support for our Facilities Maintenance Staff.

PREVAILING WAGE

Project Contact: Gale Stevens 831-477-5613 Email: [email protected] and [email protected]

NEW HVAC SERVICE & REPAIRS AT CABRILLO COLLEGE Addenda: 0 4/30/19 2:00 PM 19-01049 B19-07 Aptos Plan Issuer: Cabrillo College 831-477-5613

Cabrillo is requesting HVAC Service & Repair Support for our Facilities Maintenance Staff.

PREVAILING WAGE

Project Contact: Gale Stevens Email: [email protected] and [email protected]

NEW HVAC CONTROLS AT CABRILLO COLLEGE Addenda: 0 4/30/19 2:00 PM 19-01050 B19-06 Aptos Plan Issuer: Cabrillo College 831-477-5613

Cabrillo is in need of HVAC Controls Support and has a wide variety of HVAC Control Systems, which may include: Trane Tracer Summit, Trane Tridium, Johnson, Siemens, York, Honeywell and others.

PREVAILING WAGE

Project Contact: Gale Stevens Email: [email protected] and [email protected]

NEW NEARY LAGOON TULE AND SEDIMENT REMOVAL Addenda: 0 4/30/19 2:00 PM 19-01067 Santa Cruz $500,000 Plan Issuer: City of Santa Cruz [email protected] 831-420-5428 831-420-5161

The work to be done consists of vegetation removal, sediment removal/dredging, trucking within the site for temporary storage and drying, and trucking both to the off-site final disposal site likely the City of Santa Cruz Recovery Facility located at 605 Dimeo Lane.

Project Contact: Steve Wolfman Email: [email protected]

Ron Silveira Territory Sales Manager Cell: 805-252-1798 [email protected] www.muesinc.com Central Coast Central Valley

9195 El Camino Real Atascadero, CA 93422

SERVING MONTEREY COUNTY, SANTA CRUZ & BENITO COUNTY CONSTRUCTION DIVISION

GRANITEROCK CONSTRUCTION DIVISION

ALL OF YOUR CONSTRUCTION NEEDS - FROM DRIVEWAYS TO FREEWAYS

• Asphalt and Concrete Driveways • Culverts and Walls • Parking Lots • Golf Cart Path Work • Site Work • Concrete Curb and Gutters • Seal Coating and Striping • Concrete Flatwork • Underground Utilities • Asphalt Grinding (Water, Sewer, Storm Drain) • Subdivision Site Work Development • Chip Sealing • Structures

General Engineering Contractor - LIC#22 • For an estimate call 831.768.2789 • Fax 831.768.2701 GREEN YOUR LANDSCAPE 25% OFF BULK SALES OF NATURAL-COLORED WOOD CHIPS

Excellent for use as mulch to suppress weed growth, replace lawns and delineate garden pathways. SOLD BY THE TRUCKLOAD AT THE MRWMD SCALES Sale price $37.50 per ton (regularly $50) Sale price good through April 30, 2019.

Wood chips made from 100% recycled, untreated, unpainted construction lumber. Magnets remove most nails and screws. Not recommended for children's playgrounds or animal bedding. Price per ton includes loading. Also available by the ton: Compost, Top Soil, Terra Cotta Wood Chips. Visit mrwmd.org/landscapeproducts for more tips and products. HOW MUCH DO YOU NEED? 1 Ton = approximately 5 cubic yards (for estimating purposes only, actual ton to cubic yard conversion may vary).

MONTEREY REGIONAL WASTE MANAGEMENT DISTRICT 14201 Del Monte Blvd, 2 miles north of Marina www.mrwmd.org | whatgoeswhere.info | 831-384-5413 | How to change ‘horses’ in midstream and end up A: Thank you for contacting Capitol on the same ride. Ditto, this ‘inactive’ answer and a Services. A corporation can transfer its license couple more complex contractor issues with expert number to a newly formed LLC under certain assistance in discovering where ‘truth’ lies… circumstances: 1) The existing Corporate license is in good standing immediately before Q: You were originally helping us with it's cancellation in connection with the new transferring one of our Officer’s Sole Owner LLC; 2) The LLC was formed by a Corporation license number to our newly formed to continue the business of the corporation; and Corporation. The transaction would have 3) The personnel listed for each entity are the involved issuing 51% ownership to the same. Qualifying Officer in order to retain his Sole Owner license number. However, we are If you don't meet all of these requirements, changing for the option to issue each of the then the LLC will be issued a new license three Officers 33% interest in the company. Is number. the paperwork you sent us still the same, or does it require new/different paperwork? Q: Our license is set to expire at the end of May. I am trying to be proactive because we A: The paperwork would remain the have had some issues in the past with getting it same. Either way it’s Original Contractor’s on time, but the license still going suspended License (Examination Waiver) application. for a period of time because of the CSLB’s processing time. Do you have any Q: We have an employee with an Inactive suggestions? contractor license and we would like to utilize his qualification to be the RME (Responsible A: First, I would make sure the address the Managing Employee) on our license. Would CSLB has on record is current. You can look he be required to re-activate his license prior to up your license online to verify. The CSLB will applying for the company license? We just send you the renewal notice to the address of don’t want to pay the additional fees if it’s not record about 60 days prior to your necessary. expiration. Truthfully, they take several weeks to process them once you submit, so you’ll A: No, that is not required. In fact, RME’s are want to keep that in mind and get it submitted only allowed to Qualify one Active license at a well before the expiration date. Be sure that time, so even if you re-activated it, he would be you have all the correct signatures and fees to required to Inactivate it again to be added to avoid rejection. Let me know if we can be of the company license. any assistance here in Sacramento.

Q: I was wondering if it is possible to move our While knowledge is power, knowing where to current license number to a different company, go for the answers is half the battle. Get expert the new one is an LLC. We want to close down assistance immediately when you call 866-443- the Corporation, but at the same time, we don’t 0657, email [email protected], or write us at want to lose our low license number. Is this Capitol Services, Inc., 1225 8th St. Ste. 500, possible? Sacramento, CA 95814. Research past columns at www.cutredtape.com. Earn cash back on each product you install

Over 80+ Partners offer builder incentives exclusively through HomeSphere's national rebate program. Start collecting rebates on building essentials today!

What's In It For You: How the homesphere •Get access to Single-Family program works: and Multi-Family Rebates •Bundle all your rebates into CONNECT one monthly check Choose from 80+ Preferred Partner brands across 23 product categories to earn rebates. Continue to purchase products locally. •Continue to increase your rebate check through TRACK HomeSphere’s network of Your local HomeSphere expert will help you efficiently building product manufacturers track your closings by community, lot and block. bundle and earn more COLLECT HomeSphere bundles your rebate incentives together Your cash back can grow. across all products and brands in a single check. Tap in to HomeSphere's network of 80 manufacturers It’s Easy to Get Started! and brands to increase your Set a 10-minute meeting with your local HomeSphere rebate check, including: Expert who will walk you through: 1. Your Builder Profile & Latest Closed Homes 2. Your Enrollment Form 3. Your W-9 Form CONTACT Lorri Lasley to enroll [email protected] | (650) 793-8432

Build a Better Benefits Package!

Through the California Builders Exchanges (CBX), the Central Coast Builders Association now offers a highly competitive benefits program to our member firms and their employees.

Individual Options Valuable products, services and discounts that your employees can get directly from one of our contracted providers because you are a member of the Association.

 Health Insurance for Individuals and Families  Nationwide Pet Insurance  LifeLock Identity Theft Protection  MetLife Home & Auto Insurance  Working Advantage Employee Perks Program  LegalShield Pre-Paid Legal Services  LegalShield Identity Theft Shield

Employer Sponsored Options Products you can get through your employer. Enrolling is easy! Your company receives a single, consolidated bill and participating employees have the convenience of payment through payroll deductions. Both Group and Voluntary options are available.

 Medical – All CA Carriers & Covered CA  Colonial Life Optional Benefits  MetLife Dental – Group and Voluntary  Accident Insurance  VSP Group Vision  Critical Illness Insurance  Anthem Blue View Voluntary Vision  Short Term Disability Insurance  Landmark Chiropractic & Acupuncture  Hospital Confinement Insurance  MetLife Term Life - Group and Voluntary  Whole Life with LTC Rider  CADR+ Telemedicine - 24/7 Doctors on Call  LegalShield Pre-Paid Legal Services  LifeLock Identity Theft Protection  Legal Shield Identity Theft Shield

Want More Information? Great Voluntary Go to www.cbxbenefits.com Benefits! Or contact our local Benefits Consultant!  No Minimum Participation Tina Nelson  Q&A Insurance Marketing, CA Lic. 0B17048 Low Rates Cecy Insurance Services, CA Lic. 0802215  Consolidated Billing (831) 477-1730  Guarantee Issue Options [email protected] Construction Project Manager / Estimator CONSTRUCTION ESTIMATING Monterey CA $80,000-$90,000 a year General Contractor specializing in Prevailing Wage Projects seeks experienced Project Material quantity takeoffs for Manager for California. Must have a minimum of 10 years hands-on abilities to handle the planning, coordination, and control of a project from inception through comple- tion. Strong estimating skills a must. Our projects are fast paced and require immedi- residential/commercial. ate response to field personnel and customer requirements. The position will require job walks and client meetings throughout Central and Northern California. In addition Foundation,excavation, to the required experience above, the right candidate will have natural leadership abilities, be able to work independently, and is organized and detail-oriented. It is criti- forms, reinforcing, concrete. cal that you have the ability to communicate effectively and appropriately with clients, colleagues and coworkers, as well as the ability to recognize a potential problem and Rough and finish carpentry. resolve immediately and effectively. Must have experience supervising field staff in- cluding sub-contractors. Responsibilities Include: Lumber lists. Experienced. Bidding and estimating TI projects throughout California, performing prevailing wage projects. Selecting, negotiating and coordinating the work of sub-contractors Contact email: Adhering to proper administration of construction contracts with knowledge of and the experience with AIA documents [email protected] Reporting/updating to owners the progress of projects including any changes needed Preparing transmittals, submittals, contracts and daily logs Preparing and processing change orders timely and accurately Supervising and supporting field staff Timely preparing of monthly invoicing for the accounting department For Sale: Maintaining data and cost of projects Travel will be required Strong verbal and written communication skills DriWater time-release water replacement Advanced computer skills including MS Project, Word, Excel and Outlook gel pacs, 100+/- cases, 20/case. MUST be able to read plans and be willing to work as a Team member to ensure the success and timely completion of all projects Email resume to [email protected] Contact Kim O'Bryan at KCI Environmental, Inc. Job Type: Full Time Salary: $80,000-$90,000 & Federal Holidays + 2 weeks of Vacation [email protected] or 805 431-1168. Experience: Construction: 5 years minimum Construction Project Management: 5 years minimum

Architectural Photography A&R Corporation, Inc Harold Gomes is seeking a Project Manager, Project En- Email: gineer and Superintendents to staff a mul- [email protected] tifamily apartment project located in Paso Robles. Please send resumes to Neil Mil- Cell: 831-227-1942 ler at the following email address, [email protected]

“Job Posting: Assistant Bookkeeper and Administrator: Salinas construction company is in search of a full-time assistant bookkeeper and office administrator with at least 5 years’ experience. Individual must be highly organized and professional. Responsibilities will include: Assisting with accounts payable, accounts receivable, general ledger and GL account analysis. Processing payrolls in a timely manner. Attention to detail and accuracy is a must as well as compliance with federal and state wage laws, prevailing wage rate laws, and union benefits. Must possess a general knowledge of payroll. Must be proficient in current computer software. Competitive salary commensurate with experience. Competitive benefits package. Background check required. Please send resumes and references to [email protected].”

Safety Tip of the Week ARC WELDING SAFETY

Safe and accident free completion of any welding operation should be the goal of all welders. Here are a few welding safety tips that will help you achieve that goal.

Wearing proper eye protection is verv important. Welders and their helpers should be sure to use the correct filter lens in their goggles or helmets to protect their eyes from infrared and ultraviolet light. (See 1926.102, Tables E-1 and E-2 for a guide to eye and face protection and filter lens shade numbers.)

Precautions for fire prevention must be taken in areas where welding is being done, for example, isolating the welding and cutting area and removing fire hazards from the vicinity. If normal fire prevention precautions are not sufficient, a qualified person should be assigned to guard against fire during the operation and for a suitable time after completion of the work, to ensure that no possibility of fire exists. Be sure that fire extinguishing equipment is available and ready for immediate use. In areas where heavy dust concentrations exist, or where flammable paints or other flammable materials are present, welding, cutting or heating can create a significant fire hazard. Proceed with extreme caution!

A noncombustible or flameproof screen should isolate the welding or cutting area to protect other workers in the vicinity from direct arc rays. Watch your slag; it could cause a serious injury to someone working below. I

If the electrode holder is left unattended, the electrodes must be removed, and the holder must be placed so that electrical contact cannot be made with another employee or any conducting object.

All arc welding and cutting cables must be completely insulated and capable of handling the maximum current requirements for the job. The insulation on any splice within 10 feet of the electrode holder must be equal to the insulation of the cable.

Review 1926.351 through 1926.354 for additional information

All welding and cutting operations in a confined space shall be ventilated to prevent the accumulation of I toxic materials or possible oxygen deficiency.

Safety Recommendations:______

Job Specific Topics:______

M.S.D.S Reviewed:______

Attended By:

______

______

______

______

______