2 INDEX

Sr. No. Description Page Nos. 1. Covering letter 1 2. Index 2 3. Form-1 3-40 4. Form-1A with EMP 41-91

LIST OF ANNEXURE

Annexure Nos. Name of Annexure Page Nos. Annexure No. 1 Copy of Deed of Lease between Technopark & the 92-123 project proponent for the land Annexure No. 2 Daily Water Consumption Calculation details 124 Annexure No. 3 Daily Water Consumption Balance Chart 125 Annexure No. 4 Topographical Contour Survey map of the site 126 Annexure No. 5 Land use map of the 10 km radius of the site 127 Annexure No. 6 Vicinity map of the site showing site location 128 Annexure No. 7 Google map of the project site superimposed with 129 project boundary Annexure No. 8 Conceptual Plan 130 Annexure No. 9 Site photographs 131 Annexure No. 10 Open Well Water Test Report from NABL 132 accredited laboratory Annexure No. 11A Pond Water Test Report from NABL accredited 133 laboratory Annexure No. 11B Bio-diversity Assessment Report 134-149 Annexure No. 12 Ambient Air Quality Test Report from NABL 150 accredited laboratory Annexure No. 13 Parking plan (Basement 1 & Basement 2) 151-152 Annexure No. 14 Ambient Noise Level monitoring Report from NABL 153 accredited laboratory Annexure No. 15 Socio-economic Assessment Report along with 154-163 Corporate Environment Responsibility Report Annexure No. 16 Toposheet map showing 10 km. radius of the site 164 surrounding features Annexure No. 17 Google map showing 10 km. radius of the site 165 surrounding features Annexure No. 18 Copy of Accreditation Certificate of the laboratory 166-173 Annexure No. 19 Copy of Accreditation Certificate of the consultancy 174 organization Annexure No. 20 Undertaking by the consultancy organization 175 Annexure No. 21 Copy of Photo ID of the Authorized Signatory 176 Annexure No. 22 Copy of Resolution passed by the Board of 177 Directors in favour of Authorized Signatory Annexure No. 23 Copy of Structural Stability Certificate 178

3

FORM-1

3

4

APPENDIX I

(See paragraph – 6)

FORM 1

(I) Basic Information

Sr. Item Details No.

1. Name of the project/s Environment Clearance for proposed IT/ITES office building project to be developed by M/s Brigade Enterprises Limited. 2. S. No. in the schedule Schedule 8 (a), Construction Project with built-up area of 25,771.2 sqm which is more than 20,000 sqm and hence application for Environmental Clearance. 3. Proposed capacity / area / length / Total Plot Area = 0.4047 ha. tonnage to be handled/command Total Built-up Area = 25,771.2 sqm area/lease area/ number of wells to Total FAR area = 18,140 sqm (@4.5) be drilled 4. New/Expansion/Modernization New 5. Existing capacity/area etc., Not applicable

6. Category of Project i.e. ‘A’ or ‘B’ Category ‘B’ 7. Does it attract the general condition? NO If yes, please specify General Conditions are not applicable to Item no. 8 of 'SCHEDULE' to EIA Notification, 2006 8. Does it attract the specific condition? NO If yes, please specify Specific Conditions are not applicable to Item no. 8 of 'SCHEDULE' to EIA Notification, 2006 9. Location Within Technopark Phase-1 Campus in Plot no. 75, Re-survey no. 66/1-1 (old sy. no. 710), Pangappara Village, Corporation, & District, Plot/Survey/Khasra No. Technopark Phase-1 Campus, Plot No. 75, Re-survey no. 66/1-1 (old sy. no. 710), Village Pangappara Tehsil Thiruvananthapuram District Thiruvananthapuram State Kerala 10. Nearest railway station/airport along The nearest railway station with distance in Kms (Kazhakkoottam) is at 1 km (W) and Thiruvananthapuram Int. Airport is at 9 km (SE) away from the project site. (Source :- Google map, vintage : 2019) 4

5

11. Nearest Town, city, District Approx. S Headquarters along with distance in N Name Distance & Kms Direction 1. Thiruvananthapuram 7 km (SE) City 2. Civil Station, 9 km (E) Chenkallur, Thiruvananthapuram

(Source :- Google map, vintage : 2019) 12 Village Panchayats, Zilla Parishad, Village Office Address :- Municipal Corporation, Local body Pangapara Village Office, (complete postal addresses with Thiruvananthapuram,Loyola Road, telephone nos. to be given) Sreekariyam, Thiruvananthapuram, Kerala-695017.

Municipal Corporation Office Address :- Zonal Office of Municipal Corporation of Thiruvananthapuram, Kachani Rd, Vattiyoorkavu, Nettayam, Thiruvananthapuram, Kerala-695013. Ph. 0471 - 2320821. 13 Name of the applicant M/s Brigade Enterprises Limited 14 Registered Address M/s Brigade Enterprises Limited 29 th & 30 th Floor, World Trade Centre, Brigade Gateway Campus, Dr. Rajkumar Road, Malleswaram-Rajajinagar, Bengaluru-560055. 15 Address for correspondence : M/s Brigade Enterprises Limited 29 t h & 30 th Floor, World Trade Centre, Brigade Gateway Campus, Dr. Rajkumar Road, Malleswaram-Rajajinagar, Bengaluru-560055. Name Mr. Abraham Koshy Designation (Owner/Partner/CEO) Authorized Signatory Address M/s Brigade Enterprises Limited 29 t h & 30 th Floor, World Trade Centre, Brigade Gateway Campus, Dr. Rajkumar Road, Malleswaram-Rajajinagar, Bengaluru-560055. Pin Code Bengaluru-560055. E-Mail [email protected] & [email protected] Telephone No. 080-41379200 9980141453 (Mr. Anand Kumar) 09900059043 (Mr. Prajith) Fax No. 080-22210784 16 Details of Alternative Sites examined, The proposed project is for construction if any. Location of these sites should of IT/ITES office building within be shown on a topo sheet Technopark Phase-1 Campus. The land for the Project is leased to the project proponent by Technopark (A society wholly controlled by ) for a period of 99 years and hence no alternative site is proposed. 5

6

17 Interlinked Projects No. The proposed project is for construction of IT/ITES office building within the Technopark Phase-1 Campus 18 Whether separate application of No, interlinked projects has been As explained at Sr. No. 17 above. submitted? 19 If yes, date of submission Not applicable 20 If no, reason Not applicable 21 Whether the proposal involves approval/clearance under: If yes, details of the same and their status to be given. (a) The Forest (Conservation) Act, No 1980? The project site does not attract Forest (Conservation) Act, 1980.

(b) The Wildlife (Protection) Act, No, 1972? There is no Wildlife Sanctuary or National Park located within 15 km radius of the project site.

(c) The C.R.Z Notification, 2011? NO - There is no tide influenced water body abutting the site. Therefore, the project site is not in the regulation zone as per C.R.Z Notification, 2011 and hence the CRZ regulations is not applicable. 22 Whether there is any Government Yes. Order/Policy relevant/relating to the The following Central / State / Local site? Regulations & Standards Applicable to the Project :-  Environment Protection Act 1986  Environment Impact Assessment (EIA) Notification, 2006 and subséquent amendments.  Manual on norms and standards for environment clearance of large construction projects issued by MoEF.  Hazardous Waste (Management, Handling & Transboundary) Rules, 2016.  Water Pollution (Prevention & Control) Act, 1974  Air Pollution (Prevention & Control) Act, 1981  The Solid Waste Management Rules, 2016.  The E-Waste Management Rules, 2016.  The Noise Pollution (Regulation & Control) Rules, 2000.  The Construction & Demolition Waste Management Rules, 2016.  Plastic Waste Management Rules,

6

7

2016  National Building Code (NBC) of  The Indian Electricity Rules, 1956  Bureau of Energy Efficiency (BEE) norms  Norms issued by Fire & Rescue Department, Govt. of Kerala  Kerala Municipality Building Rules, 2009 / 2012 and its subsequent amendments.  The Kerala Promotion of Tree Growth in Non-Forest Areas (Amendment) Act, 2007.  The National Green Tribunal Act, 2010. 23 Forest land involved (hectares) NO - There is no Forest land involved. 24 Whether there is any litigation NO pending against the project and/or there is no any litigation pending land in which the project is propose to against the project and/or land which be set up? the project is proposed to be set up. (a) Name of the Court (b) Case No. (c) Orders/directions of the Court, if any and its relevance with the proposed project.

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) Sr. Information/Checklist Yes / Details thereof (with approximate No. confirmation No quantiti es /rates, wherever possible) with source of information data 1.1 Permanent or temporary Yes There will be change in land use, land change in land use, land cover or topography including increase cover or topography in intensity of land use. including increase in The proposed project is for intensity of land use (with construction of IT/ITES office building respect to local land use within the Technopark Phase-1 Campus plan) in Pangappara Village, Thiruvananthapuram Corporation, Thiruvananthapuram Taluk & District, Kerala. The land for the Project is leased to the project proponent by Technopark ( A society wholly controlled by Government of Kerala ) for a period of 99 years. As per the "Deed of Lease" between Technopark and the project proponent, the lessee of the land is M/s Brigade Enterprises Ltd. The copy of the said "Deed of Lease" is attached at

7

8

Annexure No. 1.

During construction phase, about 300 workers (daily average) will be at site.

During operation phase on full occupancy of the IT/ITES office building, the maximum population expected is about 2,000 persons (office staff, housekeeping staff, maintenance staff, security staff etc.- floating population) and hence there is increase in the intensity of land use. (Source: population is calculated based on NBC, 2016). 1.2 Clearance of existing land, Yes As per the Ecological S urvey conducted vegetation and buildings? by the Ecology & Bio-diversity expert, there are about 85 trees existing in the site. For the development of the proposed site, some of these existing trees & different varieties of shrubs, herbs, grass & climbers will be cut. Some of them will be retained and some of them which is falling within the building footprint will be transplanted. As per the “ Kerala Promotion of Tree Growth in Non-Forest Areas (Amendment) Act, 2007 ”, no permission is required for cutting of the trees mentioned in the Schedule. Some of the existing trees, cutting of which, no permission is required. 1.3 Creation of new land uses? Yes Presently, t he proposed site is covered with native species with shrub, herb, grass, climbers etc. For the development of the proposed site, these existing trees & different varieties of shrubs, herbs, grass & climbers will be cleared. The proposed project is construc tion of IT/ITES office building within the Technopark campus and new land use will be as office use. 1.4 Pre-construction Yes Pre-construction Soil Investigation has investigations e.g. bore been carried out by the agency houses, soil testing? (M/s Builtech Foundations, ) for the site. As per the soil investigation report, the ground water table level is encountered between 9 m to 11 m below the existing ground level (June, 2019). The soil profile is primarily of Lateritic clay. 1.5 Construction works? Yes The proposed project is for construction of IT/ITES office building with built-up area of 25,771.2 sqm with supporting infrastructure facilities. Internal roads 8

9

for movement inside the project site will be developed. 1.6 Demolition works? Yes As per the topographical survey map, there is small building / structure existing at site which will be demolished during development of the proposed site. The demolition waste to be generated due to the demolition of the existing build ing will be handled as per the Guidelines of Construction and Demolition Waste Management & Handling Rules, 2016. 1.7 Temporary sites used for Yes Temporary resting place will be construction works or constructed for hous ing of construction housing of construction workers (about 300 persons, daily avg). workers? Temporary sheds for site office (15 sqm), store room (100 sqm) etc. with built-up area of about 100 sqm will be constructed. 1.8 Above ground buildings, Yes Excavation / cutting of earthwork for the structures or earthworks foundation of structures and for including linear structures, basements which is proposed to be cut and fill or excavations occupied for parking. The total excavated/cutting of earth is 12,147 cum. The top soil (1,822 cum) which is fertile will be kept at site for future landscaping work. The excavated soil will be used for back filling work (3,644 cum) for site leveling and 4,203 cum will be used for internal road construction work, walkways. The excess excavated earth of 2,478 cum will be used for formation of soil stabilized blocks which shall be used in construction. As per the topographical contour survey map, there is level difference of 4 m in east to west direction. This level difference is made use during development of the proposed site. 1.9 Underground works including Yes The activity proposed is a building mining or tunneling? construction project. No underground works including mining / tunneling required except the foundation work for the structures an d for the construction of basement. 1.10 Reclamation works? No No Reclamation work is required. 1.11 Dredging? No The proposed project is a building construction project and there is n o dredging work required. 1.12 Offshore structures? No The proposed project is a building construction project and there is no offshore structures work required. 1.13 Production and No The proposed project is a building manufacturing processes? construction project. No production / manufacturing process involved. 9

10

1.14 Facilities for storage of Yes Separate raw material storage shed of goods or materials? cement and other construction materials will be made within the project premises with built-up area of about 100 sqm Bricks and steel will be laid in open in the earmarked areas. 1.15 Facilities for treatment or Yes Construction phase :- disposal of solid waste or Construction and Demolition Waste, liquid effluents? Rule, 2016 will be followed for handling of solid waste from the site during construction phase. Solid waste like packaging material, hazardous waste, e-waste etc generation from the project during construction phase will be about 75 Kg/day (domestic) + about 60 kg /day of other solid waste. Domestic sewage will be about 16 KL/day and there would be about 16 KL/day of construction waste liquid. The non-biodegradable waste and other packaging material will be sold to the vendors. The bio-degradable solid waste will be disposed through authorized collection agencies of Thiruvananthapuram Municipal Corporation. A mobile STP for the treatment of domestic sewage from the laborers will be setup in the labour camp. A sedimentation cum oil and grease trap for the treatment of construction waste liquid.

Operation phase :- SOLID WASTE :-  From the proposed IT/ITES o ffice building , it is expected to generated municipal solid waste of 800 Kg/day.  The Solid Waste Management Rules, 2016 will be followed in the Solid Waste Disposal Mechanism at the site during operation phase.  Collection & segregation within the site (bio-degradable waste (green bins), non-biodegradable waste (blue bins) and domestic hazardous waste (yellow bins).  The recyclable waste like packaging material, paper etc. would be sold through vendors (500 kg/day). The Bio-degradable waste would be dispose d through the Organic Waste Converter (OWC) to be installed within the site (300 kg/day).  The manure generated will be utilized for green area development within the 10

11

premises. E-WASTE :-  Discarded computer parts, monitor, key boards etc constitutes e-wa ste and this waste will be stored in an earmarked area.  E-waste will be generated after 4-5 years latency period  Separate earmarked space will be provided for e-waste storage.  E-waste will be disposed as per E Waste (Management & Handling) Rules. HAZARDOUS WASTE :-  As per Hazardous Waste (Management & Handling Rules), the hazardous waste i.e., the used oil from D.G. sets, discarded oil filters and discarded batteries and stored separately and will be disposed to CPCB / SPCB authorized vendors only.  M/s Perfect Alloys, , M/s Peejay Enterprises, , M/s Excel Petrochemicals, and M/s Cee Jee Lubricants, are the approved recyclers for discarded batteries & used oil located in Kerala. Also, domestic hazardous waste would be gener ated like discarded paint drums, pesticide cans, CFL bulbs, tube lights, expired medicines, broken mercur y thermometers, used batteries etc. generated shall be managed as per rule.

SEWAGE:- The total domestic sewage about 81 KL/day will be g enerated which will be treated through proposed Sewage Treatment Plant of capacity 85 KL to be installed within the project premises. The treatment scheme proposed for the domestic sewage is SBR treatment and Tertiary Treatment with UV method for disinfection and ultra filtration (UF). 1.16 Facilities for long term No There is no long term housing facility housing of operational proposed for the operational staff within workers? the site. 1.17 New road, rail or sea traffic No No new road, rail or sea traffic during during construction or construction or operation will be made. operation? Internal roads for movement inside the site will be constructed. 1.18 New road, rail, air No No new road, rail, air, waterborne or waterborne or other other transport infrastructure including transport infrastructure new or altered routes and stations, including new or altered ports, airports etc. will be made. routes and stations, ports, Internal roads for movement inside the 11

12

airports etc? site will be constructed. 1.19 Closure or diversion of No No closure or diversion of existing existing transport routes or transport routes or infrastructure infrastructure leading to leading to changes in traffic movements. changes in traffic movements? 1.20 New or diverted transmission No No diversion of transmission lines or lines or pipelines? pipelines for construction of IT/ITES office building within the Technopark campus. Supporting infrastructure (like drainage line, sewage line, electrical lines etc.) facilities are to b e developed within the site for proposed IT/ITES office building. 1.21 Impoundment, damming, No No impoundment, damming or other culverting, realignment or changes to the hydrology of other changes to the watercourses or aquifers. hydrology of watercourses or aquifers? 1.22 Stream crossings? No There is no stream crossings within the site. There is a drain flowing in the west direction of the proposed site. This drain will be protected by the project proponent during construction phase & operation phase and an area equivalent to the width of the drain will be as “ No Development Zone”. 1.23 Abstraction or transfers of No There is no use of Ground water for the water form ground or surface domestic water requirement of the waters? project. 1.24 Changes in water bodies or No There will be decrease in run-off due to the land surface affecting the proposed development. The details drainage or run-off? are given below :- Before the development of the project site :-  Total plot area = 4047 sq.m.  Annual rainfall = 3.359 m  Run-off Coefficient = 0.4  Total annual run-off from the site = 5,437 KL

After the development of the project site:- Description Ground Hard surface + coverage Green area Area (in sq.m.) 1,550 2,497

Annual rainfall 3.359 3.359 (in m.) Run-off co- 0.8 0.45 efficient Peak annual 4,165 3,774 run-off (in KL)

12

13

• Total annual run-off from the site = 7939 KL (4,165 + 3774) • Capacity of rain water storage tanks = 140 KL (concurrent use and post rainy use) • After development of the site, net run-off from the site = 3,774 KL

1.25 Transport of personnel or Yes Construction phase :- materials for construction, In construction phase, about 6-8 trucks / operation or day is env isaged for transportation of decommissioning? construction materials. About 2-3 four wheelers of senior staff and contractors, visitors, suppliers and about 5-10 two wheelers of other executive staff is expected. Operation phase :- 250 Cars are expected in the operation phase. 1.26 Long-term dismantling or Yes There is demolition/dismantling or decommissioning or decommissioning works required of the restoration works? old existing small structures / buildings. As part of the eco restoration, adequate number of saplings of native species would be planted. 1.27 Ongoing activity during Yes The demolition/dismantling work of decommissioning which some of the existing structures / could have an impact on the buildings will have impact on air environment? environment, noise environment, water environment, ecological environment and land environment. 1.28 Influx of people to an area in Yes The proposed project is building either temporarily or construction of IT/ITES office building permanently? project which would provide j ob facilities for about 300 numbers (avg) of laborers (skilled / unskilled) during construction phase. The influx of people during operation phase of the project who will be working staff in the IT/ITES office building will be about 2,000 persons (IT/ITES office staff + others staff) (floating population). Further, on full occupancy of the project during operation phase, the maximum population expected is 2,000 Persons (floating population) hence there will be influx of floating people to the project area. 1.29 Introduction of alien No Alien species are not proposed to be introduced. species? 1.30 Loss of native species or Yes As per the Ecological Survey conducted by the Ecology & Bio-diversity expert, genetic diversity? there are about 85 trees existi ng in the site. For the construction of the IT/ITES office building, all of the existing

13

14

shrubs, herbs, grass & climbers will be cleared. We propose to cut 30 nos., transplant 2 nos. & retain 53 nos. The trees to be cut are mostly of native species and widely common in the area.

As per the “ Kerala Promotion of Tree Growth in Non-Forest Areas (Amendment) Act, 2007 ”, no permission is required for cutting of the trees mentioned in the Schedule. Some of the existing trees, cutting of which, no permission is required. The list as per the said Act is provided below :- SN Name of tree 1 Coconut 2 Rubber 3 Cashew 4 Tamarind 5 Mango 6 Jack Fruit Tree 8 Matti 9 Arecanut 10 Konna 11 Seema Konna 12 Nelli 13 Neem 14 Murukku 15 Jathi 16 Albezia 17 Silk cotton 18 Acacia auraculiformis 19 Mangium 20 Anghili 21 Kilimaram 22 Manchadimaram 23 Vatta 24 Palm tree 25 Aranamaram 26 Eucalyptus 27 Seemaplavu 28 Paala 1.31 Any other actions? None Nil

14

15

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non- renewable or in short supply): S. Information/checklist Yes / Details thereof (with approximate No. confirmation No quantities /rates, w herever possible) with source of information data 2.1 Land especially undeveloped Yes The present project is development of or agricultural land (ha) IT/ITES office building project with supporting infrastructure facilities in a plot area of 0.4047 ha. At present, it is an undeveloped land. The proposed site is within the Technopark Phase-1 campus which is partially developed land having with other office buildings. 2.2 Water (expected source & Yes Construction phase :– competing users) unit: KLD The dai ly water consumption during construction phase to meet domestic water requirement for construction workers and technical staff (300 workers / staff daily average) is 40 KL (@135 ltr per person). The daily water consumption during construction phase for con struction activities is about 32 KL. (built-up area of 25,771.2 sq.m. x 1.1 KL per sq.m. / 900 days = about 32 KLD).

The source of water will be from recycled water from portable STP and treated water from Municipal treatment plants for construction purpo ses and for domestic purposes for labourer, water will be from Technopark/KWA supply.

Operation phase :- The total daily water consumption for the proposed project would be about 123 KLD (fresh 50 KLD + recycled 73KLD). The first day fresh water requirement is 123 KLD and subsequent days, the daily fresh water requirement is 50KL. The sources of water during operation phase for the proposed project are: - 1. Stored Rain Water in tank (140 KL capacity) (Non-Flushing Req.), 2. Technopark / Kerala Water Authority (Non-Flushing Req.) 3. Treated waste water from STP (Flushing, horticulture, HVAC Req.) (Entire Year). The daily water consumption calculation details and daily water consumption balance chart is attached at Annexure No. 2 & Annexure No. 3 respectively.

15

16

2.3 Minerals (MT) Yes The course aggregates and fine aggregates and M sand will be used (minor minerals from building stone). The expected required quantity details is given below :- SN Building Material Qty. 1 Sand 83846 MT 2 Aggregates 96268.32 MT 2.4 Construction material – Yes The construction materials would be stone, aggregates, sand / brought from local suppliers available in soil (expected source – MT) the area. The expected building construction material details ar e given below :- SN Building Material Qty. 1 Sand 83846 MT 2 Aggregate 96268.32 MT 3 Cement 342757 bags 4 Reinforcement Steel 19328 MT 5 Bricks 212097 nos 6 Plumbing Material 19843.82 m 7 Electrical Material 30925.44 m 8 Flooring Tiles 76798 sqm 9 Paints 19844 ltr 10 Ready Mix Concrete 127323 MT 11 Glass 41285 sqm 12 Granite 118005 MT 13 Wood 142228 MT 2.5 Forests and timber (source – Yes Wood will be required for doors & door MT) frames. 2.6 Energy including electricity Yes Total Power Req. : 1,778 kVA and fuels (source, competing Power Source: Kerala State Electricity users) Unit: fuel (MT), energy Board. (MW ) Total capacity of D.G. Sets proposed (1010 kVA x 2 nos + 380 kVA x 1 no) (as a standby power back up arrangement) Fuel – HSD (Ultra low sulphur) Fuel Consumption : 206 ltr/hr 2.7 Any other natural resources No Nil (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S. Yes / Details thereof (with approximate N. Information/Checklist No quantities/rates, wherever possible) with confirmation source of information data 3.1 Use of substances or No There will be no use of materials which materials, which are hazardous are hazardous as per MSIHC rules to (as per MSIHC rules) to human human health or the environment. health or the environment (flora, fauna, and water supplies)

16

17

3.2 Changes in occurrence of Yes The proposed development can cause disease or affect disease changes in occurrence of diseases vectors (e.g. insect or water through insects or other vectors. borne diseases) Suitable drainage and waste management measures wi ll be adopted in both the construction and operation phases which will restrict stagnation of water or accumulation of water within the site & the surroundings. This will effectively restrict the reproduction and growth of disease vectors. Further, appropr iate sanitation facility will be provided at site during construction phase & operation phase. Good house keeping and hygienic measures will be followed during construction and operation phase to avoid any cause which can lead to occurrence of disease. 3.3 Affect the welfare of people Yes The proposed project is construction of e.g. by changing living IT/ITES office building with supporting conditions? infrastructure facilities. Some of the activities during construction phase and operation phase of the pr oject may affect the welfare of the people. Also, along with the commissioning of IT/ITES office facilities, there will be various ancillary activities like convenient shops, medical shops, stationery shops, transport facilities etc. attached to the project but located outside the site and which will benefit the local people and improve their living conditions. 3.4 Vulnerable groups of people Yes The proposed constr uction activity for who could be affected by the the IT/ITES office building will generate project e.g. hospital patients, fugitive dust emissions and hence children, the elderly etc., increase in air pollution, increase in noise level and which can affect vulnerable groups of people and children and the elderly. 3.5 Any other causes N one Nil

4. Production of solid wastes during construction or operation or decommissioning (MT/month) S. Yes / Details thereof (with approximate No. Information/Checklist No quantities/rates, wherever possible) with confirmation source of information data 4.1 Spoil, overburden or mine Yes For construction of new buildings, it is wastes proposed to provide Stitched Raft Foundation. Period of foundation work- around 2 months. Quantity of spoil generation-6073.5 cu.m x 2 months = 12147 cu.m.

17

18

Construction or Demolition Waste :- • Demolition waste quantity - 1290 cum during the entire construction period. 4.2 Municipal waste (domestic Yes Construction Phase :- and or commercial wastes) There will be 75 kg/day of municipal solid waste will be generated from the labourers during construction phase. 60 Kg/day of other solid waste will be generated.

Operation Phase :- It is expected of 800 kg/day Municipal solid waste will be generated from the proposed IT/ITES office building project on full occupancy during opera tion phase. 4.3 Hazardous wastes (as per Yes Construction phase :- Hazardous Waste The oil used (about 4 ltr/month) in the Management Rules) D.G. sets (150 kVA x 1 no.) (as a standby source of power) after certain of hours of operations. This used oil from the D.G. Sets will be sold to the CPCB approved recyclers. The list of authorized recyclers are M/s Perfect Alloys, Chengannur, M/s Peejay Enterprises, Thiruvalla, M/s Excel Petrochemicals, Kochi & M/s Cee Jee Lubricants, Aluva are the approved recyclers for discarded batteries & used oil located in Kerala. Used oil will be stored in HDPE drums in isolated covered facility.

Operation phase :- The oil used (about 2 ltr/month) in the D.G. sets (from the operation of 3 nos., DG sets of 1010 kVA x 2 nos. + 380 kVA x 1 no) (as a standby source of power) after certain hours of operations. This used oil from the D.G. Sets will be sold to the CPCB approved recyclers. Used oil will be stored in HDPE drums in isolated covered facility. 4.4 Other industrial process No The present project is building construction of IT/ITES office building wastes project with supporting infrastructure facilities. No other industrial process wastes will be generated / anticipated from the site. However, the project being a off ice project, the following waste will be generated :- 1. E-waste 4.5 Surplus product No The present project is building construction of IT/ITES office building project with supporting infrastructure facilities.

18

19

No surplus product will be generated / anticipated from the site. 4.6 Sewage sludge or other Yes The sludge from STP will be processed sludge from effluent through sludge digester. treatment 4.7 Construction or demolition Yes • Construction waste (test pile) - There wastes is no waste from pile work. • Demolition waste quantity - 1290 cu.m during the entire construction period. • Construction & Demolition Waste Management and Handing Rules, 2016 will be followed. 4.8 Redundant machinery or Yes Not applicable equipment 4.9 Contaminated soils or other Yes During construction phase, some of the materials construction material in liquid form may spill to the land and can contaminate the soil. 4.10 Agricultural wastes Yes Clearing of site will be done before the commencement of construction and agricultur al waste will be generated. Similarly, during operation phase, agricultural / horticulture waste will be generated from the green areas. 4.11 Other solid wastes Yes During construction phase, apart from the waste envisaged there may be other types of solid wastes. Excavation / cutting of earthwork for the foundation of structures and for basements which is proposed to be occupied for parking. The total excavated/cutting of earth is 12,147 cum. The top soil (1,822 cum) which is fertile will be ke pt at site for future landscaping work. The excavated soil will be used for back filling work (3,644 cum) for site leveling and 4,203 cum will be used for internal road construction work, walkways. The excess excavated earth of 2,478 cum will be used for f ormation of soil stabilized blocks which shall be used in construction.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Details thereof (with approximate S. Information/Checklist Yes / quantities / rates, wherever possible) with No. confirmation No source of information data 5.1 Emissions from combustion Yes There will be emissions from combustion of fossil fuels from stationary of fossil fuels from the D.G. sets as well or mobile sources as from construction equipm ents and machinery. Similarly, there will be emissions from D.G. sets during operation phase. It is proposed to have DG set of 150 kVA

19

20

x 1 no capacity during construction phase and 1010 kVA x 2 nos + 380 kVA x 1 no during operation phase. 5.2 Emissions from production Yes During construction phase, there will be production of ready mix concrete through processes batching plant. During the transfer of materials to the batching plant, fugitive emissions are expected and which are temporary in nature & the i mpact is negligible. 5.3 Emissions from materials Yes The construction materials during handling including storage transportation, unloading etc. will have or transport fugitive emissions. Further, from the stock pile of excavated earth and loose const ruction materials, fugitive emissions are expected. 5.4 Emissions from construction Yes Dust will be generated during unloading activities including plant and of construction materials, drilling , marble equipment and tiles cutting, dry polishing and grinding operations etc. There will be emissions from construction equipments and batching plant etc. 5.5 Dust or odours from handling Yes During construction phase, fugitive of materials including emissions by wa y of fine dust will be construction materials, generated during the handling of sewage and waste construction materials. Also, due to the continuous movement of vehicles through the unpaved internal roads within the site, dust will be generated. The odor generation is expected from the stagnated sewage from the labour camp, unattended food waste etc. both during construction phase and operation phase. 5.6 Emissions from incineration No No incineration plant is proposed and of waste hence no emissions from incineration of waste.

5.7 Emissions from burning of No There will be no burning of waste in open waste in open air (e.g. slash air. materials, construction debris) 5.8 Emissions from any other No There will be no emissions from any other sources sources.

6.0 Generation of Noise and Vibration, and Emissions of Light and Heat: Sr. Information / Checklist Yes / Details thereof (with approximate No. confirmation No quantities/rates, wherever possible) with source of information data 6.1 From operation of equipment Yes Noise : e.g. engines, ventilation plan t, During construction phase, there will be crushers noise generation due to operation of vehicles, heavy construction machinery, construction activities, DG set operations etc. During operation phase, there will be

20

21

noise from the cooling tow ers, DG sets etc. Vibration : During construction phase, there are activities which can generate vibration, emission of light and heat. The sources of vibration from the project is during construction of the building. Pile foundation excavation through rot ary drilling is one of the source of vibration. The PPV levels from the rotary drilling for pile foundation would be maintained within 10 mm / sec at 20 m from the source. Therefore, there will not be any damage due to the vibration to be generated during foundation work to the nearby structures. The other source will be from operation of DG set during construction. 6.2 From industrial or similar No There are no industrial or similar processes processes envisaged within the proposed project. The proposed project is a construction of IT/ITES office building within the Technopark, Phase-1 campus. 6.3 From construction or Yes Due to the construction activities and the demolition short term demolition activities, there will be generation of noise, vibration etc which are explained at 6.1 above. 6.4 From blasting or piling No No blasting will be adopted in the construction process. No piling work will be done in the proposed development as we will be proposing stitched raft foundation. however, there wil l be minimum noise generation which shall be temporary & reversible. 6.5 From construction or Yes Some amount of noise will be generated operational traffic from construction and from vehicular movement in the construction phase of the project. There wil l be noise generation from vehicular movement during operation phase.

6.6 From lighting or cooling Yes There will be lighting proposed within the systems project area during construction phase and operation phase. A cooling tower attached to the air conditioning plant will generate noise in the area. Necessary acoustic enclosure around the tower shall be provided to dissipate the noise generation to the outside environment.

6.7 From any other sources No Nil

21

22

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Details thereof (with approximate S. Information/Checklist Yes / quantities/rates, wherever possible) with No. confirmation No source of information data

7.1 From handling, storage, use Yes During construction phase, there may be or spillage of hazardous rare incidents of spillage of paint, oil etc materials to the land and which can contaminate the land or ground water sources. 7.2 From discharge of sewage or Yes The land or the water resources may get other effluents to water or contaminated by domestic sewage from the land (expected mode and the site both during construction phase place of discharge) and operation phase. The liqui d waste in the construction phase will be treated through mobile toilet and treated water will be collected in a septic tank and use for landscaping & dust suppression purposes. During operation phase, the entire sewage will be treated and re-use. 7.3 By deposition of pollutants Yes The dust generated during various emitted to air into the land or construction activities emitted into the into water air may get deposited in the land or in the water and may get contaminated. 7.4 From any other sources No Nil 7.5 Is there a risk of long term Yes There will be risk of long term build up of build up of pollutants in the pollutants in the ambient air as well as in environment from these the land provided the mitigative sources? measures are not effectively implemented.

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

S. Details thereof (with approximate No. Information/Checklist Yes quantities/rates, wherever possi ble) with confirmation / No source of information data

8.1 From explosions, spillages, Yes The present project is building fires etc from storage, construction of IT/ITES office building handling, use or production of with supporting infrastructure facilities hazardous substances within the Technopark Phase-1 campus . The chances of explosions, spillages, fire are negligible. The used oil storage may have chances of spillages during storage or handling and accidents can occur and thereby can affect the contamination of lan d environment and water environment. No major hazardous waste is being stored within the project site. No Industrial or process activity is involved in this

22

23

project hence chances of chemical hazards and accidents are minimal. However, suitable fire fightin g measures will be provided. 8.2 From any other causes Yes The risk of accidents during construction phase is likely due to the engagement of workers in building. 8.3 Could the project be affected Yes. Earthquakes :- by natural disasters causing As per seismic classification, the project environmental damage (e.g. site falls in Zone-III. The maximum floods, earthquakes, expected earthquake intensity is VIII in landslides, cloudburst etc)? MM scale or 5.6 M in Richter scale. Though small and medium earthqu akes have occurred in the region. There is no reported large earth quake in the region as per the records available. Structural design aspects as per the IS Code (part 6) for Structural design of NBC of India, Other relevant codes for earthquake resistant design of structures and IS code of practice for ducting details of reinforced concrete structures subjected to seismic forces would be incorporated in the project development.

Landslide :- The topography of the project site and the area within 15 km rad ius is broadly flat in nature. There is no reported landslide within 15 km radius.

Erosion :- Part of the area falling within 15 km radius is abutting the sea and sea walls are constructed to prevent soil erosion.

Flooding :- The project site is not pro ne to flooding. As per the flood zonation map, part of the area falling within 15 km radius is abutting the sea and within 15 km. radius are prone to floods.

Lightening :- There are reported incidents of lightening in the area within 15 km radius during two seasons in the year viz. the season comprises of months April and May and second two months of October and November.

Tsunami :- Though Kerala Coast was encountered with the Tsunami dated 26-12-2004, the coastal area falling within 15 km. radius of th e project site was not affected by this Tsunami. 23

24

Could Burst :- No reported cloudburst in the area falling within 15 km radius of the project boundary.

Cyclone :- The area within 15 km radius from the project site falls within moderate damage risk zone - B (Vb = 39 m/s) as per the Wind and Cyclone Hazard Map published by BMTPC : vulnerability Atlas - 2nd Edition, 2006.

Drought :- The area within 15 km. radius from the boundary of the project site experiences seasonal drought conditions during the sum mer months. Even in the years of normal rainfall, summer water scarcity problems are severe in Thiruvananthapuram city.

Heat wave / sunburn / sun stroke :- Indian Meteorological Department (IMD) issued heat wave warning in 2016 and in subsequent years. Several sunburn incidents were reported from the area within 15 km radius.

Information Sources : 1. Landslide Zonation Maps and Flood Zonation Maps prepared by State Emergency Operations Centre (SEOC), Department of Disaster Management, Govt. of Kerala 2. Kerala State Disaster Management Profile published by Kerala State Disaster Management Authority, Govt. of Kerala 3. Vulnerability Atlas of India published by Building Materials & Technology Promotion Council, Ministry of Housing & Urban Poverty Allevi ation, Govt. of India. Year - 2006. 4. 26 th December, 2004 - Tsunami, published by Earth System Science, Department of Science and Technology, Govt. of India - Year 2006 5. Kerala State Disaster Management Plan, published by Kerala State Disaster Managem ent Authority, Department of Revenue and Disaster Management, Govt. of Kerala. - Year 2016.

24

25

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality. S. Information/Checklist Yes Details thereof (with approximate No. confirmation / No quantities/rates, wherever possible) with source of information data 9.1 Lead to development of The proposed development can lead to supporting utilitie s, ancillary various consequential developments development or development within the project vicinity. stimulated by the project which could have impact on the environment e.g.: • Supporting infrastructure Yes The proposed project is within (roads, power supply, waste or Technopark Phase-1 campus and the waste water treatment, etc.) necessary infrastructure facilities within the Technopark campus is already developed by the Technopark Authorities. The supporting infrastructure which are consequential to the proposed project and is outside the project site like roads, power supply, waste management and waste water treatment etc are required to be carried out by the respective L ocal Self Government and various Govt Departments.

• housing development No The housing requirement for the staff in the proposed project is required outsi de the project site. From the list of community facilities in the project vicinity elucidated below will provide necessary housing facility for the above. However, there can be additional facilities of the project development in the project vicinity.

• extractive industries No No extractive industries

• supply industries No Due to the proposed project, there can be consequential development like supply units and supply industries within the vicinity.

• other No The proposed project will lead to a large requirement of computation and transport facilities in the project vicinity. 9.2 Lead to after-use of the site, No Not applicable which could have an impact on the environment 9.3 Set a precedent for later No Not applicable developments 9.4 Have cumulative effects due to No Not applicable proximity to other existing or planned projects with similar effects. 25

26

(III) Environmental Sensitivity

Sr. Name/ Aerial distance (within 15 km.) Proposed project No. Areas Identity location boundary

1 Areas protected under international Approx. conventions, SN Name Distance & national or local Direction legislation for their 1. 9 km. (SE) ecological, 2. "Parvathy-Puthanaar" canal 2 km (SW) landscape, cultural 3. Arabian Sea 3.3 km (SW) or other related 4. lake 6 km (NW ) value (Important Coastal and Marine Diversity Area) 5. Aakulam lake 4.3 km (SE) 6. Amayizhanchan thodu 5 km (SE) 7. Pallithura beach 3.2 km (SW) 8. Karmana River 13 km (SE) 9. Killi river 11.5 km (SE) 10. Mamam river 12 km (NW) 11. river 15 km (NW) 12. Veli lake (backwater / kayal) 5 km (S) 13. Parasurama, Siva, Brahma and 15 km (SE) Matsya Temple, Thiruvallam (Archeological Protected Monument) 14. Sri Ananthapadmanabha Swamy Temple, 10.7km, (SE) 15. Beemapally Mosque 13.4 km (SW) 16. Palace, Trivandrum 9.5 km (SE) 17. Koyikkal Palace 14.4 km (NE) 18. Vikram Sarabhai Space Centre, Trivandrum 3 km (SW) 19. Chiruvallinairkavu, Sacred Grove, 4 km (SE) 20. Vilavilkadavil, Sacred Grove, Sreekaryam 4 km (SE) 21. Kuzhikkattukonam, Sacred Grove, 4 km (SE) Sreekaryam 22. Dharmasastha kavu, Sacred Grove, 4 km (SE) Sreekaryam 23. Peravilakavu Sacred Grove, Kidarakuzhy 14.8 km (NE) 24. Puthalathukavu Sacred Grove, Kidarakuzhy 14.8 km (NE) 25. Chinnakkanakavu Sacred Grove, Kidarakuzhy 14.8 km (NE) 26. Madanthampurankavu, Sacred Grove, 4.3 km (SE) Pongumoodu 27. Chokkankavu Sacred Grove, Thiruvalam 15 km (SE) 28. Durgadevi Temple Sacred Grove, 12.5 km (NE) Thanimoodu 29. Kunnuvila Devi Temple Sacred Grove, 7.8 km (SE) 30. Dharmasastha Kavu Sacred Grove, 8 km (NE) Poolanthara 31. Kunnampallykonatu Sacred Grove, Vattavila 11 km (NE) 32. Muttada kavu, Sacred Grove, Paruthippara 7 km (SE) 33. Pangottu kavu, Sacred Grove 12.5 km (SE) 34. Thottam Kavu, Sacred Grove, Manakkad 12 km (SE) 35. Madavoorpara Rock Cut Cave 4.7 km (NE) 36. Thirunarayanapuram Vishnu Temple 12 km (SE) 37. Trivikramangalam Mahavishnu (Vamana 14.2 km (SE)

26

27

Moorthi) Temple, Trivikramangalam 38. Neeramangara bhadrakali temple 14 km (SE) 39. Trivandrum Fort 10.8 km (SE) 40. , Trivandrum 9.6 km (SE)

Information Sources :- 1. Field Survey conducted in August, 2019 2. Kerala Tourist Guide Published by H&C Books 3. "A Glimps of Kerala through Districts" by Dr. K.C. Krishnakumar published by Mathrabhumi Books, 2017 4. " My Keralam " Published by Prime PSC Exam Coaching Centre 5. Toposheet no. C 43W14 & 15 (Old no. 58D14 & 15) 6. Google Earth, August, 2019 2 Areas which are important or Sr. Approx. Distance & Name sensitive for No. Direction ecological reasons - 1. Thiruvananthapuram Zoo 9 km. (SE) Wetlands, water 2. "Parvathy-Puthanaar" canal 2 km (SW) courses or other 3. Arabian Sea 3.3 km (SW) water bodies, 4. Kadinamkulam lake 6 km (NW ) coastal zone, (Important Coastal and Marine biospheres, Diversity Area) mountains, forests 5. Aakulam lake 4.3 km (SE) 6. Amayizhanchan thodu 5 km (SE) 7. Pallithura beach 3.2 km (SW) 8. Karmana River 13 km (SE) 9. Killi river 11.5 km (SE) 10. Mamam river 12 km (NW) 11. 15 km (NW) 12. Veli lake (backwater / kayal) 5 km (S)

Information Sources :- 1. Field Survey conducted in August, 2019 2. Kerala Tourist Guide Published by H&C Books 3. "A Glimps of Kerala through Districts" by Dr.K.C. Krishnakumar published by Mathrabhumi Books, 2017 4. " My Keralam " Published by Prime PSC Exam Coaching Centre 5. Toposheet no. C 43W14 & 15 (Old no. 58D14 & 15) Year 2011. 6. Google Earth, August, 2019

3 Areas used by protected, important Sr. Approx. Distance Name or sensitive species No. & Direction of flora or fauna for 1. Thiruvananthapuram Zoo 9 km. (SE) breeding, nesting, 2. "Parvathy-Puthanaar" canal 2 km (SW) foraging, resting, 3. Arabian Sea 3.3 km (SW) over wintering, 4. Kadinamkulam lake 6 km (NW ) migration (Important Coastal and Marine Diversity Area) 5. Aakulam lake 4.3 km (SE) 6. Amayizhanchan thodu 5 km (SE) 7. Pallithura beach 3.2 km (SW) 8. Karmana River 13 km (SE) 9. Killi river 11.5 km (SE) 10. Mamam river 12 km (NW) 11. Vamanapuram river 15 km (NW) 12. Veli lake (backwater / kayal) 5 km (S)

27

28

Information Sources :- 1. Field Survey conducted in August, 2019 2. Kerala Tourist Guide Published by H&C Books 3. "A Glimps of Kerala through Districts" by Dr. K.C. Krishnakumar published by Mathrabhumi Books, 2017 4. " My Keralam " Published by Prime PSC Exam Coaching Centre 5. Toposheet no. C 43W14 & 15 (Old no. 58D14 & 15) 6. Google Earth, August, 2019 4 Inland, coastal, marine or Sr. Approx. Distance Name underground waters No. & Direction 1. "Parvathy-Puthanaar" canal 2 km (SW) 2. Arabian Sea 3.3 km (SW) 3. Kadinamkulam lake 6 km (NW ) (Important Coastal and Marine Diversity Area) 4. Aakulam lake 4.3 km (SE) 5. Amayizhanchan thodu 5 km (SE) 6. Pallithura beach 3.2 km (SW) 7. Karmana River 13 km (SE) 8. Killi river 11.5 km (SE) 9. Mamam river 12 km (NW) 10. Vamanapuram river 15 km (NW) 11. Veli lake (backwater / kayal) 5 km (S) 12. Open Wells / Ponds Within 15 km

Information Sources :- 1. Ground Water Information Booklet of Thiruvananthapuram District published by Central Ground Water Board, Year- Dec., 2013 2. Field Survey conducted in August, 2019 3. Kerala Tourist Guide Published by H&C Books 4. "A Glimps of Kerala through Districts" by Dr. K.C. Krishnakumar published by Mathrabhumi Books, 2017 5. " My Keralam " Published by Prime PSC Exam Coaching Centre 6. Toposheet no. C 43W14 & 15 (Old no. 58D14 & 15) 7. Google Earth, August, 2019 5 State, National None within 15 km radius boundaries 6 Routes or facilities used by the public Approx. Sr. Name Distance & for access to No. recreation or other Direction tourist, pilgrim 1. N.H. 66 (Panvel-Kochi-) 0.7 km (W) areas 2. Karyavattam Thripadapuram Road 0.7 (N) 3. Kazhakkoottam Road 1.7 km (NW) 4. Sreekaryam-Kulathoor Road 1.8 km (S) 5. Sreekaryam-Aakulam Road 4 km (SE) 6. Thiruvananthapuram-Killimannoor Road 6.5 km (E) 7. Railway line (Kochi- Thiruvananthapuram) 1.1 km (W)

Information Sources : - 1. Field Survey conducted August, 2019 2. Road map of Kerala 3. Kerala Tourist Guide Published by H&C Books 4. Google Earth, August, 2019 7 Defense Sr. Approx. Distance installations Name No. & Direction

28

29

1. Military area, , 13 km (SE) Thiruvananthapuram 2. Military Hospital, Pangode, 13 km (SE) 3. Southern Air Command and Control 4.8 km (SE) Centre, Aakulam 4. Special Armed Police Parade Ground, 10.2 km (SE) 5. BASF Camp, Valiyathura 12 km (SE) 6. Thiruvananthapuram Air Force Base, 9 km (SE) Shangumukham 7. Brahmos Aerospace Limited, Chacka 8 km (SE) 8. VSSC training centre 4.5 km (S)

Information Sources : - 1. Field Survey conducted in August, 2019 2. Google Earth, August, 2019 8 Densely populated Sr. Approx. Distance or built-up area Name No. & Direction 1. Grama Panchayat 4.5 km (NW) 2. Kadinamkulam Grama Panchayat 4 km (NW) 3. Mangalapuram Grama Panchayat 8 km (NW) 4. Grama Panchayat 8.5 km (NE) 5. Grama Panchayat 12 km (NE) 6. Grama Panchayat 15 km (NE) 7. Grama Panchayat 14 km (N) 8. Aruvikkara Grama Panchayat 15 km (E) 9. Grama Panchayat 11 km (E) 10. Grama Panchayat 15 km (SE) 11. Grama Panchayat 7 km (N) 12. Grama Panchayat 10.5 km (NW) 13. Thiruvananthapuram Municipal Within the area Corporation

All the above Local Self Government Areas are highly populated urbanized area. Information Sources : - 1. Field Survey conducted in August, 2019 2. Google Earth, August, 2019 9 Areas occupied by 1. Hospitals Approx. sensitive man-made Sr. Name Distance & land uses No. (hospitals, schools, Direction places of worship, 1. IRIS Centre for Arthritis & Rheumatology, 1.8km, NE community Pangappara facilities) 2. Saji hospital, Kazhakuttam 900m, NE 3. TCS Hospital, Kazhakuttam 2.1km, SW 4. Fathima Hospital and Palliative Care Center, 3.2km, SW Thumba 5. A J Hospital, Kazhakuttam 1.5km, NW 6. Suja hospital, Kazhakuttam 1.6km, NW 7. CSI Mission Hospital, Kazhakuttam 2.3km, NW 8. KottakkalArya Vaidya Sala, Kazhakuttam 3.3km, NW 9. Hospital, Kaniyapuram 4.5km, NW 10. Simans Hospital, Pallipuram 4.9km, NW 11. Community health center 4.7km, NW 12. PHC Puthukurichy 10.2km, NW 13. Health Center, Perumathura 11.7km, NW 14. Primary Health Centre, Azhoor 11.2KM, NW 15. Primary Health Centre, Kizhuvalam 12.6km, NW

29

30

16. Al Neyadi Trust Hospital, 10.2km, NW 17. Mangalapuram Govt. PHC 8.3km, NW 18. Govt. Rural Health Center, Vengode 11km, NW 19. Govt. Homeo Hospital, Mulamoodu 7.8km, NW 20. PHC Andoorkonam 5km, NW 21. Sushrutha Medical Centre, Pothencode 6.5km, NE 22. Karunya Hospital, Pothencode 7km, NE 23. SS Medical Center, Chanthavila 3.6km, N 24. Primary Health Centre, 9.7km, NE 25. St. John's Malankara Medical VillagePirappancode 12km, NE 26. Leela Ravi Hospital, Venjaramoodu 13.4km, NE 27. Govt Hospital Kanyakulangara 10.2km, NE 28. Taluk Hospital, 13.8km, NE 29. IMB Hospital and Research Centre, Sreekariyam 3.6km, NE 30. DPMS Hospital, Karakulam 10.9km, E 31. PHC Kusavarakal 7.5km, SE 32. S U T Royal Hospital 5.6km, SE 33. Sree Uthradom Thirunal Hospital, Pattom 7.85km, SE 34. GG Hospital, Murinjapalam 7.3km, SE 35. Medical College Hospital, Thiruvananthapuram 6.2km, SE 36. RCC Thiruvananthapuram 6.2km, SE 37. Sree Avittam Thirunal Hospital, Medical college 6km, SE 38. Indian Institute of Diabetes, 5.3km, SE 39. Military Hospital, Pangodu 12.5km, SE 40. Jubilee Memorial Hospital, Palayam 9.9km, SE 41. General Hospital Thiruvananthapuram 9.1km, SE 42. PRS Hospital, Killipalam 12km, SE 43. Ananthapuri Hospitals And Research Institute, 9.3km, SE Chacka 44. Lords Hospital, Venpalavattom 6.4km, SE 45. KIMS Anayara 5.7km, SE

2. Schools Approx. Sr. Name Distance & No. Direction 1. Kerala University campus Nursery School, 250m, NE 2. Kerala University Kariavattom Campus 650m, NE 3. University College of Engineering, Kariavattom 630m, NE 4. Seventh-Day Adventist English Medium High 1.4km, NE School, Kariavattom 5. Jyothis Kinder Garden Play School, Kazhakuttam 1km, NW 6. Government Higher Secondary School, 1.1km, NW Kazhakuttam 7. Govt. ITI for women, Kazhakuttam 1.6km, NW 8. Pallithura HSS, Pallithura 2.9km, SW 9. Marian College of Architecture and Planning, 2.4km, W 10. Marian College of Arts and Science, Menamkulam 2.8km, W 11. St. Jacob’s Training College, Menamkulam 2.7km, W 12. Jyothis Central School, Kazhakuttam 1.8km, NW 13. Vidyaniketan, Menamkulam 3.55km, W 14. ST. Xavier’s College, Menamkulam 3.9km, NW 15. Xavier Institute of Management, Menamkulam 3.5KM, NW 16. St. Martha's Special School, Menamkulam 3.6km, NW 17. St. Andrews UP School, Menamkulam 4.2KM, NW 18. JyotiNilayam HSS, Menamkulam 4.2km, NW 19. A.J. School Of Nursing, Kazhakuttam 2.7km, NW 20. Al Uthuman English Medium Higher Secondary 3.1km, NW

30

31

School, Kazhakuttam 21. AJ Central school, Kazhakuttam 3.1km, NW 22. Sainik school, Kazhakuttam 2.6km, NW 23. Muslim HS School for boys, Kaniyapuram 3.9km, NW 24. Muslim HS School for girls, Kaniyapuram 4km, NW 25. Asian Aviation College of Management and Science 4.6Km NW & Airline Academy, Kaniyapuram 26. GUPS , Kaniyapuram 5.1km, NW 27. MGM Arts And Science College, Kaniyapuram 5.7Km, NW 28. St. Vincent's High School, Chittattumukku 4.1km, NW 29. St Ignatius English Medium School Puthenthope 5km, NW 30. Maulana Azad Secondary SchoolPuthenthope 6.4km, NW 31. Vidyasadan Central School, 5.8km, NW 32. St. Michael's Higher Secondary School, 9.6km, NW Kadinamkulam 33. Our Lady of Mercy Higher Secondary School, 10.1km, NW Puthukurichy 34. Musaliar College Of Engineering, Kadakom 14.2km, NW 35. Government Higher Secondary School Azhoor 12.8km, NW 36. Thiruvananthapuram International School, 11.9km, NW Edackode 37. A.J College of Science & Technology, Thonnakkal 9.4km, NW 38. Blue mount public school, Thonnakkal 9.4km, NW 39. Christ Nagar Public School (CBSE) Valakkad 13.8km, NW 40. Bishop Pereira Memorial School, Karamoodu 7.5km, NW 41. Edavilakom U P School, Velloor 7.8km, NW 42. Infant Jesus Convent ISC School, Murukkumpuzha 8.9km, NW 43. St. Augustine's Roman Catholic Latin Church, 8.8km, NW Murukkumpuzha 44. St Augustine's High School, Mundakal 8km, NW 45. Asian School of Business, Pallipuram 6.35km, NW 46. St. Thomas institute of science and technology, 4km, NE Mangattukonam 47. Logos College of Theology, Melekavuvila 5.1km, NE 48. Govt. UPS Pothencode 7km, NE 49. Govt. UPS Chanthavila 3.7km, N 50. Lakshmi Vilasom High school, Pothencode 7.3km, NE 51. GLPS Vellanickal 11.8km, N 52. Mary Matha English Medium School, Pothencode 6.7km, NE 53. Santhigirividya Bhavan Senior Secondary School, 8.5km, NE Santhigiri 54. UP School, Koliyakode 9.5km, NE 55. University Institute of Technology, 11.5km, NE 56. Vocational Higher Secondary School Pirappancode 11.6km, NE 57. Kaviyattu English Medium School, Manikkal 11.5km, NE 58. Govt. LP School Pirappancode 11.8km, NE 59. Government Model Higher Secondary School 13.6KM, NE Venjaramoodu 60. Maulana AbulKalam Azad Memorial School 13.4KM, NE Venjaramoodu 61. Govt LP School, Perumala 14.5km, NE 62. Oxford model school, Vembayam 10.6km, NE 63. Government Boys High School, Kanniakulangara 10.1km, NE 64. Government Girls Higher School, Kanniakulangara 9.8km, NE 65. Govt. UPS, Konchira 9.8km, NE 66. Holy Cross English School, Mottamoodu 8.75km, NE 67. M.G.M School, Vettinad 8.7km, NE 68. PMS College of Dental Science and Research, 9.3km, NE 69. Govt. Higher Secondary School, Poovathoor 11km, NE

31

32

70. SUT Medical College, Vencode 10.4km, NE 71. Government UP School, Ramapuram 13.5km, NE 72. Govt. Girls HSS, Nedumangad 13.9km, NE 73. Good Samaritan Public School, Nedumangad 14.45km, NE 74. Govt. Boys VHSS, Nedumangad 14.5km, NE 75. Govt. College, Nedumangad 12.8km, NE 76. LMS HSS, Vattappara 8.1KM, NE 77. LMS High , Vattappara 8.2KM, NE 78. LPS Kanjikkal 5.75km, NE 79. Sree Narayana Public school, Thundathil 3.4km, NE 80. SN College, 3.2km, NE 81. C.H Mohammed Koya Memorial State Institue For 2km, E The Mentally Challenged, Pangappara 82. College of Engineering, Thiruvananthapuram 2.9km, SE 83. Loyola School, Sreekariyam 3.7km, SE 84. St. Thomas Residential School, Mukkolakkal 7.7km, E 85. St Thomas Higher Secondary School, Mukkolakkal 7.7km, E 86. Sreekariyam Government High School 3.2km, SE 87. Mar Baselios College of Engineering And 6.15km, SE Technology, 88. Mar Ivanios College Nalanchira 6.4km, SE 89. Mar Theophilos Training College, Nalanchira 6.5km, SE 90. SarvodayavidyalayaNalanchira 6.35km, SE 91. Government High & Preprimary School, 6.7km, SE 92. Marygiri Senior Secondary School, Kairalinagar 9.1km, SE 93. Up school, Kusavarakal 7.5km, SE 94. St. Goretti Girls High School, Nalanchira 7km, SE 95. Infant Jesus Central School Priyadarshini Nagar 5km, SE 96. Mary Nilayam Senior Secondary School, 4.8km, SE Pongumood 97. MG College, Keshavadasapuram 7.2km, SE 98. St. Mary's HSS, Pattom 7km, SE 99. Kendriyavidyalaya, Pattom 7.6km, SE 100. Sree Chitra Tirunal Institute for Medical Sciences & 6.1km, SE Technology, Medical college 101. John Cox Memorial CSI Institute of Technology, 8km, SE Kannanmoola 102. Greenvalley International School, Gowreesapattom 8.2km, SE 103. University College, Palayam 9.5km, SE 104. Govt. Arts College, Thycaud 10.7km,SE 105. Govt. Model Boys HSS, Thycaud 10.7km, SE 106. NSS College for Women, Pazhavangadi 10.5km, SE

3. Place of Worship Approx. Sr. Name Distance & No. Direction 1. Vallathode Sri Thamburan Temple, Technopark 200m, SE 2. Koduthara Sree Yogeeshwara Devi Temple, 1.1km, NE Karyavattom 3. Thazhekunnath Sree Mahavishnu Temple, 2.1km, NE Karyavattom 4. Aattinkuzhy Sree Muththumaari, Amman Kovil, 1.1km, SW Kazhakuttam 5. St. Joseph's Roman Catholic Latin Church, 1km, NW Kazhakuttam 6. Pentecostal Maranatha Gospel Church, 900M, NW Kazhakuttam 7. Sree Krishna Temple, Kazhakuttam 1.1km, NW

32

33

8. FathimaMatha Church, Pallithura 1.8km, SW 9. Pallithura Church, Pallithura 2.9km, SW 10. St. Thomas Aquinas Church Kochuthura 3.1km, SW 11. St. John The Baptist Church, Pallithura 3.3km, SW 12. Anugraha Bhavan Retreat Center Kazhakuttom 3.1km, NW 13. SreeMahadeva TempleKazhakuttom 1.4km, NW 14. Sri Bhagavathi Temple, Kazhakuttom 1.6KM, NW 15. AlumoodBhagavathi Temple, Kazhakuttom 1.6km, NW 16. Pullattukari Temple Kazhakuttom 1.9km, NW 17. St. Dominic’s Church, Menamkulam 3.65km, W 18. Bethel Mar Thoma ChurchKazhakuttom 2.7km, NW 19. St. Mary's and St. Jude Orthodox Church, 3.3Km, NW Kazhakootam 20. St. Martha’s Convent. Congregation of Sisters of St. 3.6KM, NW MarthaKazhakuttom 21. PunnattuSreeThampuran Devi Temple Kazhakuttom 2.3km, NW 22. Town masjid Kaniyapuram 4.5km, NW 23. Major Sri Thonnal Devi Kshethram, Pallipuram 4.9km, NW 24. Fathimapuram Roman Catholic Latin 4km, NW Church,Fathimapuram 25. St. Mary’s Syro-Malankara Catholic Church, 5.1km, NW Chirakkal 26. Muslim jamaath Masjid, Kaniyapuram 5.4km, NW 27. St. Ignatius Latin Catholic Church, Puthenthope 5.2km, NW 28. KochuKodungalloor Devi Temple,Anapara 7.9km, NW 29. St. Joseph's Parish Church, Kadinamkualam 8.2km, NW 30. PadikkavilakkamBhgavathy temple,, Kadinamkulam 9.5km, NW 31. St. Michael's Forane Church, Puthukurichy 10.4km, NW 32. CheramanthuruthuJuma Masjid,Cheramanthuruthu 10.95km,NW 33. St.James Church, Kadakom 14.1km, NW 34. AzhoorBhagavathy Temple, Azhoor 12.9km, NW 35. SivaKrishnapuram Temple, SivaKrishnapuram 13.8km, NW 36. Salafi Masjid Muttappalam 12km, NW 37. Juma masjid Peruguzhi 11km, NW 38. Sreerajarajeshwari temple, Peruguzhi 10.6km, NW 39. ManneerVilakomSreeBhadrakali Temple nalumukku 10.5KM, NW 40. Little Flower Malankara Syrian Catholic Church, 11.3km, NW Vengode 41. Town Juma Masjid Mangalapuram 8.4km, NW 42. Kunnumpuram Masjid 5.5KM, NE 43. Sacred Heart Roman Catholic Latin Church, 4km, NE Mangattukonam 44. Panimoola temple, Pothencode 5.9km, NE 45. KoonayilSreedharmasastha Temple, Kattaikonam 5.6km, NE 46. Shanthigiriashramam, Shanthigiri 8.3km, NE 47. VelavoorBhagavathi Temple, 10.9km, NE 48. Sree Krishna Temple Pirappancode 11.8km, NE 49. St.Joseph's ChurchPirappancode 12km, NE 50. Vembayamjuma masjid 10.6km, NE 51. St.GeorgeSyro Malabar Church, Neduveli 8.6km, NE 52. St.Jerome Malankara catholic ChurchNedumangad 13.7km, NE 53. CSI Church, Vattappara 8.3km, NE 54. St. 's Church, Vattappara 8.2km, NE 55. St. Paul's Syro Malankara Catholic Church, Kuttiyani 7km, NE 56. AliyavoorElluvila Devi Temple, 5.7km, NE 57. Ganapathi Temple Chittazha 6.9km, NE 58. Aniyoor TempleChempazhanthy 2.8km, NE 59. ChristhurajaKatholikkaDevalayam, Karyavattam 1.3km, NE 60. Sri Dharmashasta Temple Karyavattom 1.3km, NE 61. Puliyoorkodu Sri Krishna Swami Temple, 3km, SE

33

34

Ambadynagar 62. Kariyam Devi Temple 4km, E 63. Mar Baselios Mar Gregarious Orthodox Syrian 3.6km, SE Church, SreeKariyam 64. Juma masjid SreeKariyam 3.8km, SE 65. KarumbukonamMudippura Devi 4.6km, SE KshethramSreeKariyam 66. Kudappanakunnudevi temple 8.1km, SE 67. SreeBalaSubramanyaSwamy Temple Ulloor 5.75km, SE 68. St. Mary's Malankara Syrian Catholic Cathedral, 7.1km, SE Pattom 69. Juma masjid, Kumarapuram 6.7km SE 70. Little flower church Chettikunnu 7km, SE 71. Lourdes Syro Malabar Forane Church, PMG 8.9KM, SE 72. Attukalbhagavathy temple 12.6km, SE 73. Sri Ananthapadmanabha Swamy Temple, East fort 10.7km, SE 74. St. Thomas Roman Catholic Latin Church Veli 5.1km, SE 75. Beemapally Mosque 13.4 km (SE) 76. St. Joseph Church, Palayam 9.7 km (SE) 77. Madre De Deus Church (Vettukadu Church) 7.4 km (SE) 78.

4. Community Facilities Approx. Sr. Name Distance & No. Direction 1. QUEST Global, Technopark 20m, N 2. Amphi Theatre, Technopark 30m, W 3. Chandragiri, Technopark 50m, NW 4. Oracle India Pvt Ltd Technopark 90m, NW 5. Park center, Technopark 100m, W 6. Leela,Technopark 300m, NW 7. Nila, Technopark 200m, NW 8. Guest House, Technopark 200m, W 9. Thejaswini, Technopark 150m, SW 10. Bhavani, Technopark 200m, SW 11. Technopark 150m, SW 12. SBI, Technopark 150m, SW 13. IBS Software Campus, Technopark 450m, SW 14. HDFC Bank, Technopark 550m, W 15. Club house, Technopark 600m, NW 16. BSNL Telephone exchange, Kariavattom 700m, NE 17. Kerala Highway research centre, Kariavattom 800m, NE 18. Post office, Kariavattom 900m, NE 19. SBI , Karyavattom 900m, NE 20. Railway station, Kazhakuttam 1.1km, W 21. FCI Godown, Kazhakuttam 1.2km, SW 22. KSEB sub station, Kazhakuttam 950m, NW 23. KSEB office, Kazhakuttam 1.1km, NW 24. Canara bank, Kazhakuttam 1KM, NW 25. Thiruvananthapuram corporation zonal office, 1.1km, NW Kazhakuttam 26. Rural Employment exchange office, Kazhakuttam 1.2km, NW 27. Sub registrar office, Kazhakuttam 1.4km, NW 28. Post office, Kazhakuttam 1.4km, NW 29. Krishna theater, Kazhakuttam 1.2km, NW 30. KINFRA International Apparel Park, Kazhakuttam 3km, W 31. Al-Saj International Convention Center, 2.3KM, NW Kazhakuttam 32. Sub Treasury, Kazhakootam 2.8km, NW

34

35

33. Block panchayat office, Kazhakootam 2.8km, NW 34. Magic Planet Thiruvananthapuram, Chanthavila 2.8km, NW 35. Kerala State film Academy, Chanthavila 2.8km, NW 36. Harishree theatre and marriage hall, 3.5km, NW 37. Railway station, Kaniyapuram 4.5km, NW 38. AndoorkonamGramaPanchayath Office, 4.5km, NW Kaniyapuram 39. Kadinamkulam panchayat office, Menakulam 4.1km, NW 40. Jawaharlal Nehru Tropical Botanic Garden and 5.8km, NW Research Institute, Puthenthope 41. Channakkara post office 6.1km, NW 42. Village office, Kadinamkualam 8.5km, NW 43. Police station, Kadinamkualam 8.5km, NW 44. Fish market, Mariyanad 8.8km, NW 45. Post office Perumathura 11.8km, NW 46. Village office Azhoor 12.8km, NW 47. Railway station Peruguzhi 11.7km, NW 48. Post office Peruguzhi 11.1km, NW 49. AzoorGrama panchayat 10.7km, NW 50. Police station, Mangalapuram 8.2km, NW 51. Railway station, Murukkumpuzha 8.3km, NW 52. Technocity 7.1km, NW 53. Police station Pothencode 6.8km, NE 54. Post office Pothencode 6.7km, NE 55. Village office, Ayiroorppara 5.1km, NE 56. M T Cineplex Theatre Pothencode 6.9km, NE 57. SBI Pothencode 7KM, NE 58. Sub registrar Pothencode 6.9km, NE 59. Village office, Koliyakode 9.7km, NE 60. Happyland Water Theme & Amusement Park, 12km, NE Vembayam 61. Sindhu cinemas venjaramoodu 13.2km, NE 62. SBI venjaramoodu 13.4KM, NE 63. Nellanadgrama panchayat venjaramoodu 13.6km, NE 64. KSRTC Bus stand venjaramoodu 13.6km, NE 65. Post office venjaramoodu 13.7km, NE 66. Police statrionvenjaramoodu 13.85km, NE 67. Vamanapuram Block panchayat Office 13.9km, NE 68. Thekkada village office 10.7km, NE 69. Village office Vembayam 8.9km, NE 70. Grama panchayat Office Vembayam 8.9KM, NE 71. Surya Theatre Nedumangad 14.3km, NE 72. KSRTC Bus stand Nedumangad 14.2km, NE 73. Municipal CoorporationNedumangad 14.3km, NE 74. Police station, Vattappara 8.6km, NE 75. Post office, Vattappara 8.2km, NE 76. Village office Vattappara 8.1km, NE 77. ICAR-Central Tuber Crops Research Institute, 3.7km, NE Sreekariyam 78. Police station, Sreekariyam 3.7km, NE 79. Thiruvananthapuram Collectrate, 8.7km, E 80. Dooradarshan Kendra, Kudappanakunnu 8.7km, E 81. Village office Karakulam 11km, E 82. Grama panchayat office Karakulam 11KM, E 83. Kerala State Council for Science - Technology and 7.6km, SE Environment (KSCSTE), Pattom 84. Kerala PSC Office Pattom 7.7km, SE 85. Thiruvananthapuram district panchayat office 7.8km, SE Pattom 86. Post office Pattom 7.8km, SE

35

36

87. Village office Pattom 7.8km, SE 88. Kerala State Electricity Board Ltd.Pattom 7.75km, SE 89. Kerala State Human Rights Commission, PMG 9km, SE 90. Municipal corporation Thiruvananthapuram 9.2km, SE 91. Kerala Govt. Secretariat,Thiruvanathapuram 9.9km, SE 92. Chandrasekharan Nair Stadium, MG road 9.5km, SE 93. District Court, Thiruvananthapuram 9.7km, SE 94. Kerala Legislative Assembly, Thiruvanathapuram 9.25km, SE 95. Kerala state Election 9.5km, SE CommissionThiruvanathapuram 96. RBI Thiruvananthapuram 10.1km, SE 97. Railway station Thampanoor 11km, SE 98. Ksrtc Bus terminal, Thampanoor 10.8km, SE 99. Police station,Thampanoor 11km, SE 100. KairaliSreeNila theatres, Thampanoor 11km, SE 101. Sree Kumar and sreeVisakh Theatres , Thampanoor 10.7km, SE 102. Regional Pass port officeThiruvanathapuram 9.8km, SE 103. Thiruvananthapuram International Airport, Chacka 9.2km, SE 104. Mall of , Chacka 9.3km, SE 105. Kochuveli railway station 5.6km, SE 106. Vikromsarabhai space center, Kochuveli 4.5km, S 107. Infosys, Kulathoor 2.7km, S 108. Tropical Botanical Garden and Research Institute, 6 km (NW) Trivandrum

Information Sources :- 1. Field Survey conducted in August, 2019 2. Kerala Tourist Guide Published by H&C Books 3. "A Glimps of Kerala through Districts" by Dr. K.C. Krishnakumar published by Mathrabhumi Books, 2017 4. " My Keralam " Published by Prime PSC Exam Coaching Centre 5. Toposheet no.C43W14 & 15 (old no. 58D14 & 15) - Year 2011 6. Google Earth, August, 2019.

10 Areas containing important, high 1. Ground Water Resources quality or scarce Sr. Approx. Distance Name resources (ground No. & Direction water resources, 1. Kazhakuttom (Safe Zone) Within the area surface resources, 2. Chirayinkil (Safe Zone) 15 km (NW) forestry, agriculture, 3. Nedumangad (Semi Critical) 14 km (NE) fisheries, tourism, 4. Thiruvananthapuram (Semi Critical) 7 km (SE) minerals) Artificial Recharge Structure: - Sr. Name Approx Distance & No. Direction 1. Recharge pits (3 nos.) 10 km (SE) (Thiruvananthapuram Government Secretariat ) 2. Subsurface dykes (Thalayil- 12 km (NE) Moottakkavu)

2. Surface Resources Sr. Approx. Distance Name No. & Direction 1. "Parvathy-Puthanaar" canal 2 km (SW) 2. Arabian Sea 3.3 km (SW) 3. Kadinamkulam lake 6 km (NW ) (Important Coastal and Marine 36

37

Diversity Area) 4. Aakulam lake 4.3 km (SE) 5. Amayizhanchan thodu 5 km (SE) 6. Pallithura beach 3.2 km (SW) 7. Karmana River 13 km (SE) 8. Killi river 11.5 km (SE) 9. Mamam river 12 km (NW) 10. Vamanapuram river 15 km (NW) 11. Veli lake (backwater / kayal) 5 km (S) 12. Open Wells / Ponds Within 15 km

3. Forestry There is no forest or forest land available within 15 km radius.

4. Agriculture The project site is located in the vicinity of Thiruvananthapuram Municipal Corporation. Further there are several villages in the district which are involved in agricultural activities and is located within 15 km radius from the project site. Depending on the location, different varieties of food crops as well as cash crops are cultivated. Rice is the principal crop extensively cultivated in low- lying regions. Rubber plantations is also extensively found in the land within 15 km. Apart from these, other crops cultivated are tapioca, coconut, pepper, vegetables etc.

5. Fisheries Sr. Name Approx. Distance & Direction No. 1. Aquaculture farms Within 15 km. radius

6. Tourism Approx. Sr. Name Distance & No. Direction 1. Happyland Water Theme & Amusement Park 12 km (NE) 2. Veli lake & Tourist village 5.5 km (S) 3. Aruvikara park 15 km (E) 4. Thampurampara View Point 13 km (NE) 5. Space Museum 3 km SW 6. Magic Planet 3 km, N 7. Koyikkal Palace, Nedumangad 14.35km, NE 8. Kerala State Science and Technology Museum & 8.8km, SE Priyadarsini Planetarium 9. Keralam - Museum of History and Heritage 9.6km, SE 10. Kanakakunnu Kottaram 9.65km, SE 11. 9.8km, SE 12. Shangumugam Beach 9.5km, SE 13. Veli beach 5.2km, SW 14 Sree Chitra Art Gallery 10 km, SE 15 Observatory, Trivandrum 10 km, SE 16 Kowdiar Palace, Trivandrum 9.5 km (SE) 17 Magic Planet, Trivandrum 3 km (N)

7. Minerals Sr. Name Approx. Distance & Direction No. 1 Bauxite Attipra - 2 km (SE) 37

38

Sashthavattom - 11 km (NW) Korani - 12.5 km (NW) Muttapalam - 12.1 km (NW) 2 Clay Aakulam - 3.5 km (SE) Murukkumpuzha 7.5 km (NW) Thonakkal - 9.5 km (NW)

Information Sources : 1. Ground Water Information Booklet of Thiruvananthapuram by Central Ground Water Board, Kerala. Year - December, 2013. 2. District Survey Report Published by Department of Mining and Geology, Govt. of Kerala. Year - Nov., 2016. 3. District Planning Map series by National Atlas and Thematic Mapping Organization, Department of Science and Technology - Year - 2000. 4. Toposheet no. C 43W14 & 15 (Old no. 58D14 & 15) 6. Google Earth, August, 2019 11 Areas already No critically polluted area is located within 15 km. radius. subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded)

12 Areas susceptible to Earthquakes :- natural hazard As per seismic classification, the project site falls in Zone- which could III. The maximum expected earthquake intensity is VIII in cause the project to MM scale or 5.6 M in Richter scale. Though small and present medium earthquakes have occurred in the region. There is environmental no reported large earth quake in the region as per the problems records available. Structural design aspects as per the IS (earthquakes, Code (part 6) for Struc tural design of NBC of India, Other subsidence, relevant codes for earthquake resistant design of landslides, erosion, structures and IS code of practice for ducting details of flooding or extreme reinforced concrete structures subjected to seismic forces or adverse climatic would be incorporated in the project development. conditions ) Landslide :- The topography of the project site and the area within 15 km radius is broadly flat in nature. There is no reported landslide within 15 km radius.

Erosion :- Part of the area falling within 15 km radius is abutting the sea and sea walls are constructed to prevent soil erosion.

Flooding :- The project site is not prone to flooding. As per the flood zonation map, part of the area falling within 15 km radius is abutting the sea and within 15 km. radius are prone to floods.

Lightening :- There are reported incidents of lightening in the area within 15 km radius during two seasons in the year viz. the

38

39

season comprises of months April and May and second two months of October and November.

Tsunami :- Though Kerala Coast was encountered with the T sunami dated 26-12-2004, the coastal area falling within 15 km. radius of the project site was not affected by this Tsunami.

Could Burst :- No reported cloudburst in the area falling within 15 km radius of the project boundary.

Cyclone :- The area with in 15 km radius from the project site falls within moderate damage risk zone - B (Vb = 39 m/s) as per the Wind and Cyclone Hazard Map published by BMTPC : vulnerability Atlas - 2nd Edition, 2006.

Drought :- The area within 15 km. radius from the boundar y of the project site experiences seasonal drought conditions during the summer months. Even in the years of normal rainfall, summer water scarcity problems are severe in Thiruvananthapuram city.

Heat wave / sunburn / sun stroke :- Indian Meteorological Department (IMD) issued heat wave warning in 2016 and in subsequent years. Several sunburn incidents were reported from the area within 15 km radius.

Information Sources :

1. Landslide Zonation Maps and Flood Zonation Maps prepared by State Emergency Operations Centre (SEOC), Department of Disaster Management, Govt. of Kerala 2. Kerala State Disaster Management Profile published by Kerala State Disaster Management Authority, Govt. of Kerala 3. Vulnerability Atlas of India published by Building Materia ls & Technology Promotion Council, Ministry of Housing & Urban Poverty Alleviation, Govt. of India. Year - 2006. 4. 26 t h December, 2004 - Tsunami, published by Earth System Science, Department of Science and Technology, Govt. of India - Year 2006 5. Kerala State Disaster Management Plan, published by Kerala State Disaster Management Authority, Department of Revenue and Disaster Management, Govt. of Kerala. - Year 2016.

(IV). Proposed Terms of Reference for EIA studies Ans. The project is having built-up area 25,771.2 sq.m. which is more than 20,000 sq.m. but less than 1,50,000 sq.m. and categorized as category 8(a), as per EIA Notification, 2006. Therefore, as per the said Notification for category 8(a), EIA Study is not required.

39

40

40

41

FORM-1 A

41

42

APPENDIX II

( See paragraph 6 )

FORM-1 A

(Only for construction projects listed under item 8 of the Schedule)

(Environmental Clearance for proposed IT/ITES office building project to be developed by M/s Brigade Enterprises Limited. at Technopark Phase-1 Campus in Re-survey no. 66/1-1 (old no. 710), Plot no. 75, Pangappara Village, Thiruvananthapuram Corporation, Thiruvananthapuram Taluk & District, Kerala.

CHECK LIST OF ENVIRONMENTAL IMPACTS

(Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme)

1.0 LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity)

1.1. Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. Ans. The proposed project is for construction of IT/ITES office building within the Technopark Phase-1 Campus in Pangappara Village, Thiruvananthapuram Corporation, Thiruvananthapuram Taluk & District, Kerala. The land for the Project is leased to the project proponent by Technopark ( A society wholly controlled by Government of Kerala) for a period of 99 years. The services like storm water drainage network, road network, water supply etc. are available in the Technopark campus. The topographical spot level survey map of the site is provided at Annexure No. 4. The land use map of the 10 km radius is provided at Annexure No. 5. The vicinity map and the satellite map showing the location of the project site & it’s surroundings is provided at Annexure No. 6 & 7 respectively. The conceptual plan showing the location of STP area, proposed building blocks, parking area, pavement area, utilities / services, entry & exit to the site, internal traffic circulation within the site etc. is enclosed at Annexure No. 8. Also, the site photographs showing the exiting KSRTC bus terminal area is provided at Annexure No. 9.

1.2. List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc. Ans. The major project requirements for this proposed construction project are mentioned below:- 42

43

Objective of the project = Proposed IT/ITES Office building

Total plot area = 0.4047 ha

Total Built-up area = 25,771.2 sqm

No. of building block = 1 no.

Max. height of the building = 48.4 m

Max. no. of floors = Basement 1, 2 + Gr. + 12 floors

Expected project cost = Rs. 52 Crores

Total Water Req. = 123 KL/day (fresh 50 KLD + Recycle 73 KLD)

First day water requirement = 123 KLD and subsequent days, the daily fresh water requirement is 50 KL

Total Domestic water Req. = 90 KL/day (flushing 50 KL + non-flushing 40 KL)

Domestic Sewage Generation = 81 KL/day

Sewage Disposal Facility = Sewage Treatment Plant & Recycling

Treated Water Available from STP = 73 KL/day

The sources of water during operation phase for the proposed project are: -

1. Stored Rain Water (140 KL storage tank capacity) (Non-Flushing Req.), 2. Technopark / KWA (Non-Flushing Req.) 3. Treated waste water from STP (Flushing, horticulture, HVAC Req.) (Entire Year).

The details of the daily water requirement balance chart is provided at Annexure No. 4. Also attached is the activity wise population & daily water consumption details are provided at Annexure No. 3.

Total Power Req. = 1,778 kVA

Source of Power = Kerala State Electricity Board & D.G. Sets (standby)

Capacity of D.G. Sets = 1010 kVA x 2 nos. + 380 kVA x 1 no.

Parking requirement = 181 Cars

Parking proposed = 250 Cars

Community facilities =

The proposed project is an IT/ITES office building project and is in Technopark Phase-1 campus. The site is located within the Trivandrum Municipal 43

44

Corporation, Trivandrum Taluk & District, Kerala and the community facilities are available in the project vicinity.

Connectivity :-

The access road to the project site is from 8.5 m wide internal road of Technopark campus. The internal roads of Technopark campus is connecting with N.H.-66 ( Trivandrum Byepass ) (Salem-Kochi-Kanyakumari Highway) at 0.7 km away from the site in west direction.

The nearest railway station (Kazhakkoottam) is at 1 km (W) and Trivandrum International Airport is at 9 km (SE) away from the project site. (Source :- Google map, vintage : 2019).

1.3. What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities, details of the existing land use, disturbance to the local ecology). Ans. The proposed project is for construction of IT/ITES office building within the Technopark Phase-1 Campus in Pangappara Village, Thiruvananthapuram Corporation, Thiruvananthapuram Taluk & District, Kerala. The land for the Project is leased to the project proponent by Technopark ( A society wholly controlled by Government of Kerala) for a period of 99 years. The services like storm water drainage network, road network, water supply etc. are available in the Technopark campus. There would be no negative impacts on the existing facilities adjacent to the proposed site. The proposed project has provision for (i) Treatment of sewage and it’s entire recycling thereby there is no discharge to the external drainage system or to the land or to any water body. (ii) By the use of stored rain water and the use of treated water from STP, the use of fresh water will be reduced. (iii) The project has made provision for roof rain water storage tank (140 KL capacity) which will use as source of water during rainy days (concurrent use). (iv) By the Organic Waste Converter (OWC) to be installed within the project site, the bio-degradable solid waste disposal will be managed within the site thereby no additional loading to the Common Solid waste disposal system. (v) There are some of native trees, shrubs & herbs etc. existing at site and for the development of the proposed site some of these will be cleared from the site. As part of the eco restoration, large number of saplings of native species would be planted. Due to the eco restoration, the impact to floral and faunal ecology will be short term and the ecology will be enhanced.

1.4. Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given). Ans. There will be no major land disturbances due to the proposed development of proposed IT/ITES office site. However, the necessary protection measures to prevent soil erosion will be made. The top soil will be preserved for future landscaping within the site. The top soil will be covered with climbers of native species to prevent erosion. The partially excavated earth will be consumed within the site. As far as possible, the natural drainage will be maintained. The project site falls within Zone-III as per the seismological classification map of India. There is no history of subsidence of the project site or it’s surroundings in the past. Pre-construction Soil Investigation has been carried out by the agency (M/s Builtech Foundations, Ernakulam) for the site. As per the soil investigation 44

45

report, the ground water level is encountered between 9 m to 11 m below the existing ground level (June, 2019). The soil profile is primarily of Lateritic clay. As per the topographical contour survey map, there is level difference of about 4 m. in east to west direction. This level difference made use during development of the proposed site.

1.5. Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site) Ans. The proposed project is for construction of IT/ITES office building within the Technopark Phase-1 Campus. The supporting infrastructure like drainage facilities are available in the Technopark campus and the drainage system are to be developed within the site for the office building also. The proposed development does not affect the drainage pattern of the site and surroundings. The topographical spot level survey map of the site is provided at Annexure No. 5.

1.6. What are the quantities of earthwork involved in the construction activity- cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site, etc.) Ans. Excavation / cutting of earthwork for the foundation of structures and for basements which is proposed to be occupied for parking. The total excavated/cutting of earth is 12,147 cum. The top soil (1,822 cum) which is fertile will be kept at site for future landscaping work. The excavated soil will be used for back filling work (3,644 cum) for site leveling and about 4,203 cum will be used for internal road construction work, walkways. The excess excavated earth of 2,478 cum will be used for formation of soil stabilized blocks which shall be used in construction. As per the topographical contour survey map, there is level difference of about 4 m. in east to west direction. This level difference made use during development of the proposed site.

1.7. Give details regarding water supply, waste handling etc. during the construction period. Ans. Construction phase – The daily water consumption during construction phase to meet domestic water requirement for construction workers and technical staff (300 workers / staff daily average) (@ 135 ltr. per capita per day) is 40 KL. The source of water will be from recycled water from portable STP and treated water from Municipal treatment plants for construction purposes and for domestic purposes for labourer, water will be from Technopark/KWA supply. Further, by using of ready mix concrete (RMC) & curing agents, the water will be reduced substantially. The major part of the construction water requirement will be fully consumed. The sewage generation from labourers during construction period would be about 32 KL/day and this quantity of domestic waste would be disposed through a mobile STP to be installed at the labour colony (temporary accommodation). The treated sewage will be used for meeting the landscape / dust suppression purposes. The non bio- degradable waste, the empty cement bags, other packaging materials etc. would be disposed to the vendors. The bio-degradable solid waste will be disposed through authorized collection agencies of Thiruvananthapuram Municipal Corporation.

45

46

1.8. Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity) Ans. The proposed project is for construction of IT/ITES office building within the Technopark Phase-1 Campus and there is no low lying area & wetlands altered.

1.9. Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal) Ans.The construction waste consists of earth, debris concrete, lumber, masonry and cardboards which are about 35%, 15%, 12% and 10% respectively. Construction waste would be disposed for backfilling purposes. The bio-degradable solid waste will be disposed through authorized collection agencies of Thiruvananthapuram Municipal Corporation. The non-biodegradable waste will be stored and sold to the vendors. The packaging material like cement bags etc. would also be sold to the vendors.

2.0 WATER ENVIRONMENT

2.1. Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement. Ans. The details are provided below :-

Construction phase :- The daily water consumption during construction phase to meet domestic water requirement for construction workers and technical staff (300 workers / staff daily average) is 40 KL. The source of water will be from recycled water from portable STP and treated water from Municipal treatment plants for construction purposes and for domestic purposes for labourer, water will be from Technopark/KWA supply.

Operation phase :- The total daily water requirement, water balance chart and source of water during the operation phase of the project calculated on the basis of full occupancy of the campus are mentioned below: -

Total Water Req. = 123 KL/day (fresh 50 KLD + recycle 73 KLD)

First day water requirement = 123 KLD and subsequent days, the daily fresh water requirement is 50 KL

Total Domestic water Req. = 90 KL/day (flushing 50 KL + non-flushing 40 KL)

Domestic Sewage Generation = 81 KL/day

Sewage Disposal Facility = Sewage Treatment Plant & Recycling

Treated Water Available from STP = 73 KL/day

46

47

The sources of water during operation phase for the proposed project are: - 1. Stored Rain Water (140 KL storage tank capacity) (Non-Flushing Req.), 2. Technopark / KWA (Non-Flushing Req.) 3. Treated waste water from STP (Flushing, horticulture, HVAC Req.)(Entire Year).

The project has made provision for rain water storage tank for the concurrent use as source of water supply during rainy days. Also, in the Technopark campus, there is dedicated water supply connection from Kerala Water Authority which will available for the project. Hence the availability of water is ensured. The Water Balance Chart and population & daily water consumption details is provided.

2.2. What is the capacity (dependable flow or yield) of the proposed source of water? Ans. Details are given below :- Construction Phase The source of water will be from recycled water from portable STP and treated water from Municipal treatment plants for construction purposes and for domestic purposes for labourer, water will be from Technopark/KWA supply. The daily water consumption during construction phase for construction activities is about 32 KL. Also, daily water consumption to meet domestic water requirement for construction workers and technical staff is about 40 KL.

Operation Phase The source of water for the proposed project during operation phase will be water from the proposed rain water collection tank with capacity of 140 KL within the site for meeting the water requirement for non-flushing (concurrent use during rainy days) and also from KWA water/Technopark. Also, it is proposed to construct sewage treatment plant to treat the sewage load from the office building. During non-rainy days, the source of water is from stored rain water in tank and KWA water / Technopark supply for meeting the non-flushing water requirement. Also, the treated water from STP would be used to meet the water requirement for flushing, horticulture & make-up water for cooling towers attached with HVAC system for cooling purposes. Therefore by these sources and by an integrated water management approach, a dependable source of water is ensured. Further details are provided in water balance chart which is enclosed at Annexure No. 3.

2.3. What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality) Ans. The sources of water during operation phase for the proposed project are: -  Stored Rain Water (140 KL storage capacity) (Non-Flushing Req.),  Kerala Water Authority / Technopark (Non-Flushing Req.)  Treated waste water from STP (Flushing, horticulture & HVAC Req.) (Entire Year).

The water quality of the open well and open pond available near to the site is collected and analyzed through an NABL accredited laboratory and copy of the report is attached as Annexure No. 10A and Annexure No. 10B.

47

48

2.4. How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage) Ans. The water requirement will met from the recycling of treated wastewater of 73 KL/day from sewage treatment plan (STP) which can be recycled for different purposes. The details of recycling and it’s usage are provided in water balance chart at Annexure No. 2.

2.5. Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption) Ans. The proposed project is an IT/ITES office building project which is in Technopark Phase-1 campus. In the Technopark campus, there is dedicated water supply connection from Kerala Water Authority which will available for the proposed project also. Also, the source of water for the proposed project will be from stored rain water during rainy days and also from KWA/ Technopark. However, the treated water from STP will be used for meeting the flushing, horticulture, and excess to use make-up water requirement for cooling towers attached with HVAC system and hence there will be minimum impact to other users within the surrounding. The daily water consumption details are provided in the water balance chart.

2.6. What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity) Ans. The proposed project is an IT/ITES office building project which is in Technopark Phase-1 campus. The sewage load from the proposed office building will be of 81 KL/day.

2.7. Give details of the water requirements met from water harvesting? Furnish details of the facilities created. Ans. It is proposed to have roof rain water storage tank to store the rain water for using of rain water as source of water during rainy days (concurrent use) & during non-rainy days. The rain water storage tank storage capacity of 140 KL which will be used as source of water. Also, it is proposed to construct rain water harvesting pit for recharge of ground water table.

2.8. What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long term basis? Would it aggravate the problems of flooding or water logging in any way? Ans. The proposed project is an IT/ITES office building project which is in Technopark Phase-1 campus. The land for the proposed project was allotted by the Technopark Authorities for the development of IT/ITES office building. It is proposed to have roof rain water storage tank (with storage capacity of 140 KL) to store the rain water for using of rain water as source of water. The runoff from the other area will be properly channelized through garland drains. Due to this measure, there would be no incremental load and will not cause any flooding or water logging. The excess runoff from the site before discharge outside the premises will be passing through a de-siltation cum oil removal unit. The excess storm water will be channelized to the drain which is available near to the site. There will be decrease in run-off due to the proposed development:- Before the development of the project site :-  Total plot area = 4047 sq.m.  Annual rainfall = 3.359 m  Run-off Coefficient = 0.4  Total annual run-off from the site = 5,437 KL 48

49

After the development of the project site:- Description Ground coverage Hard surface + Green area Area (in sq.m.) 1,550 2,497 Annual rainfall (in m.) 3.359 3.359 Run-off co-efficient 0.8 0.45 Peak annual run-off (in KL) 4,165 3,774

 Total annual run-off from the site = 7939 KL (4,165 + 3774)  Capacity of rain water storage tanks = 140 KL (concurrent use and post rainy use)  After development of the site, net run-off from the site = 3,774 KL

2.9. What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any) Ans. The primary source of water is from Kerala Water Authority/ Technopark and there is no use of ground water for the proposed development. Further, as per the Ground Water Information Booklet of Trivandrum District published by CGWA, 2013, the site is in Revenue Block which is declared as Safe Zone and hence use of ground water for domestic purposes is allowed by Central Ground Water Authority.

2.10. What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts) Ans. During construction phase : Before the 1 s t monsoon showers, the entire site will be cleaned and to be free from all litter and all loose construction materials to be stored properly. The run-off during construction phase will be partially channelized to the rain water storage tank. The excess runoff will be channelized to the storm water network from the site after de-silting and oil removal and therefore, the run-off will not contaminate the land and aquifer. Further regular housekeeping will be carried out at site in order to prevent the contamination of run-off due to non-point sources of pollution. The adequate portable toilet facility will be provided in labour colony (temporary accommodation) so as to avoid open defecation. The exposed earth and loose construction materials during rainy days will be protected by utmost care. During operation phase : During operation phase, the surface runoff will be channelized through a de-siltation cum oil removal unit before it leaves the site. Also regular house keeping will be carried out in order to prevent the contamination of run-off due to non-point sources of pollution. The roof run-off will be channelized to a rain water storage tank (storage capacity of 140 KL) and the excess run-off from the tanks will be discharged outside the existing storm water drain available in the Technopark campus.

2.11. How is the storm water from within the site managed? (State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels) Ans. During construction phase :

49

50

The storm water within the site will be partially channelized to the rain water storage tank. Appropriate de-silting and oil removal will be provided so that the storm water will not contaminate the land and aquifer. During operation phase : The roof storm water from the office building will be chanellized to the storm water collection tank of capacity 140 KL. The surface storm water will be channelized through a de-siltation cum oil removal unit before it leaves the site. The contour map of the site is provided at Annexure No. 5. During operation phase, the surface runoff will be channelized through a de-siltation cum oil removal unit before it leaves the site. Also regular house keeping will be carried out in order to prevent the contamination of run-off due to non-point sources of pollution. The roof run-off will be channelized to a rain water storage tank and the excess run-off will be discharged outside the storm water available near the site.

2.12. Will the deployment of construction laborers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation) Ans. No. The proposed project has provision of labor housing arrangement (temporary accommodation for about average 300 labourers) with toilet facility and the domestic sewage will be channelized to the portable STP during the construction period. The bio-degradable solid waste will be disposed through authorized collection agencies of Thiruvananthapuram Municipal Corporation. It is proposed to maintain good house keeping of the construction site premises and the labor colony premises. These measures will ensure good hygienic conditions around the labor colony (temporary accommodation).

2.13. What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal) Ans. During Operation Phase :

Quantity of waste water generation :- The sewage generation would be 81 KL/day.

Treatment capacity & technology :- The sewage during the operation phase will be treated through a STP of capacity 85 KLD. The treatment technology proposed is SBR treatment.

Treatment Units :- Screen chamber, Oil & grease trap, neutralization tank, chlorine contact tank, equalization tank, high rate anerobic filter, moving bed bio reactor, flocculation tank, secondary settling tank, sludge digestion chamber, clarified water tank, chlorine contact tank, treated water tank.

Recycle & disposal :- The treated water from STP (with BOD level as per KSPCB norms) will be recycled. The sewage generation will be of 81 KL and treated water from STP (capacity of 85 KL) recycled within the site for flushing (50 KLD), horticulture (8 KLD) and (15 KLD) to make-up water requirement for cooling 50

51

purposes. The total quantity of sewage generation will be 81 KL/day. The treated sewage from STP will be reuse within the site. There will be no sewage discharge from the proposed project premises after development of the proposed building.

2.14. Give details of dual plumbing system if treated waste used is used for flushing of toilets or any other use. Ans. Separate water supply line for fresh water distribution (green pipe) and treated water from STP distribution (yellow pipe) will be installed within the IT/ITES office building so as to achieve dual plumbing system. The treated water for flushing of toilets will be 50 KLD. The treated water for horticulture purpose will be 8 KLD, The excess treated water for cooling tower.

3.0 VEGETATION

3.1. Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem with its unique features, if any) Ans. No. The proposed project is an IT/ITES office building project within the Technopark Phase-1 campus and there is no any threat of the project to the biodiversity.

3.2. Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project) Ans. There is clearing of trees, shrubs, herbs, grass etc as part of site development and hence there will be loss of habitation. As per the Ecological Survey conducted by the Ecology & Bio-diversity expert, there are about 85 trees existing in the site. For the construction of the IT/ITES office building, all of the existing shrubs, herbs, grass & climbers will be cleared. We propose to cut 30 nos., transplant 2 nos. & retain 53 nos. The trees to be cut are mostly of native species and widely common in the area. As per the “ Kerala Promotion of Tree Growth in Non-Forest Areas (Amendment) Act, 2007 ”, no permission is required for cutting of the trees mentioned in the Schedule. Some of the existing trees, cutting of which, no permission is required. The detailed Bio-diversity assessment report is prepared by an approved expert and the report is enclosed as Annexure No. 11.

3.3. What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale) Ans. It is proposed to plant adequate number (mostly flowering & shady trees) of tree saplings (native species), shrubs, herbs as part of the landscape development of the project. These measures will enhance the floral ecology.  As compensatory afforestation, the project will plantation (@ 3 trees for every 1 tree cut) as per MoEF & CC norms). Therefore, 90 trees will be planted as compensatory afforestation.  Further, as per MoEF & CC norms, the project will plant 1 tree for every 80 sq m of plot area. Therefore, 51 trees to be planted as per MoEF & CC norms.  The total number of trees to be planted is 90 + 51 = 141 trees as per norms.

51

52

4.0 FAUNA

4.1. Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details. Ans. Yes, there will be temporary displacement of terrestrial fauna due to the clearing of trees for construction of the proposed project. It is proposed to plant adequate number (mostly flowering & shady trees) of tree saplings (native species), shrubs, herbs as part of the landscape development of the project. These measures will enhance the floral ecology. The total tree saplings to be planted is about 141 trees. There is no rare / endangered / threatened faunal species or red listed category as per the ecological assessment carried out for the site.

4.2. Any direct or indirect impacts on the avifauna of the area? Provide details. Ans. There is direct and indirect impact on the avifauna of the area due to the project development on short term basis during construction phase. As part of the eco restoration, adequate number of saplings of native species / fruit bearing / shady trees would be planted to attract faunal species.

4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna Ans. The proposed project is an IT/ITES office building project within the existing Technopark Phase-1 Campus. There is no corridors, fish ladders in the area. By plantation of flowering, fruit bearing and shady trees the faunal ecology specially the avifauna will be enhanced. These measures will minimize the adverse impact on the faunal ecology of the area.

5.0 AIR ENVIRONMENT

5.1. Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions) Ans. The proposed project is an IT/ITES office building project within the existing Technopark Phase-1 Campus and it will not increase atmospheric concentration of gases, the project has provision of D.G. Sets for standby arrangement of electricity and will run only during power failure. The stack attached to the D.G. Sets will follow all the rules and regulations of State Pollution Control Board and Central Pollution Control Board. Further only Low Sulphur diesel fuel will be used in the DG Sets. The ambient air quality monitoring of the site was carried out through an NABL accredited laboratory and the monitoring report is attached as Annexure No. 12.

5.2. What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters. Ans. Details are given below :- Construction phase:- Mitigation proposed are given below :-  Internal roads within the site will be black topped (i.e. metallic roads)  Excavation of soil will be carried out only after erection of wind breakers of height of 1/3rd of the building height to a maximum height of 10m height will be provided.  No loose soil or sand or construction & demolition waste or any other construction material will be left uncovered.  Water sprinkling during summer days will be put in place. 52

53

 Grinding and cutting of building material will be carried out in enclosures and wet jet shall be provided for grinding and stone cutting areas.  Construction material and waste will be stored within earmarked area only.  The loose construction materials will be covered with tarpaulin sheets during transportation.  The location of the Gen set and exhaust pipe height would be as per the provisions of the statutory norms.  The Gen set installed for the project would follow the emission limits, noise limits and general conditions notified by MoEF.  All vehicles used in construction phase will be ensured with PUC certificate.  All construction equipments will be maintained regularly so as to ensure the emissions within limits.  All workers working at the construction site and involved in loading, unloading, carriage of construction material and construction debris or working in any area with dust pollution shall be provided with dust mask and other personnel protective equipment’s (PPE) and ensured that workers wear while they are at work.  Ready mix concrete (RMC) will be used to avoid the use of loose construction materials at site to reduce dust emissions.  Ambient air quality monitoring shall be done on a monthly basis to monitor air, noise, water & soil during construction to ensure that the parameters are within permissible limits.

5.3. Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site. Ans. Parking Requirements as per KMBR norms :- 181 Cars. Parking Proposed :- 250 Cars The above parking space meets the parking norms as per KMBR. Provision of basement 1 & basement 2 for accommodation parking of vehicles within the site. The access road to the project site is from 8.5 m wide internal road of Technopark campus. The internal road of Technopark campus is connecting with N.H.-66 (Trivandrum Byepass) (Salem-Kochi-Kanyakumari Highway) at 0.7 km away from the site in west direction. The nearest railway station (Kazhakkoottam) is at 1 km (W) and Trivandrum International Airport is at 9 km (SE) away from the project site The parking plan is attached at Annexure No. 13.

5.4. Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category. Ans. The conceptual plan showing the internal traffic management with entry and exit to the proposed project site, all internal roads and its width, pedestrian path ways etc. Further provisions of ramp are proposed for the easy access to the building for physically challenged persons. The further details are explained in item no. 5.3 (above).

5.5. Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above. Ans. Yes. During construction phase there will be increase in traffic and vibration. 53

54

The project has provision of large area for the parking for the vehicles (250 cars) and the parking arrangement which is planned, that there would be easy movement of vehicles within the project area and smooth movement is provided for the vehicles to reduce the traffic congestion.

5.6. What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details. Ans. The D.G. sets which would be used for the project will be with sound proof acoustic enclosures and hence there will be no impact to the surrounding. The D.G. sets would be attached with proper anti vibration pads to reduce any vibration impact to the site surrounding. Further, DG sets will be installed on the ground level. The flue gases from the D.G. sets will be vented out through stack of appropriate height as per C.P.C.B. norms to reduce the impacts on air quality around the project site. The noise level of the project site has been monitored by an NABL accredited laboratory and the report is attached as Annexure No. 15 .

6.0 AESTHETICS

6.1. Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents? Ans. There is a no scenic amenity or landscapes near to the site and the project development is within the existing Technopark campus. The proposed construction shall not cause any obstruction of view or scenic amenity of the surroundings.

6.2. Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?

Ans. The proposed project is an IT/ITES office building project within the existing Technopark Phase-1 Campus. In the north direction, there is office building of QuEST Towers available to the project site. Also, in the north west direction, there is Oracle & Speridian office buildings. In the west direction, there is Technopark Amphitheater building. In east direction, there is Thripadappuram Road, Plantation and vacant land. Also there is Chandragiri building near to the site. Also in other area there are some small size individual houses / shops / educational buildings / religious buildings / other buildings available around the site. Thereby, there will be no any adverse impacts due to the proposed expansion of the project.

6.3. Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out. Ans. The proposed project would be constructed in conformity with the Kerala Municipal Building Rules (KMBR). As per seismic classification, the project site falls in Zone-III. No reported cloudburst in the area. Also, there is no hilly area around the project site, there is no chance of landslide. Structural design aspects as per the IS Code (part 6) for Structural design of NBC of India, Other relevant codes for earthquake resistant design of structures and IS code of practice for ducting details of reinforced concrete structures subjected to seismic forces would be incorporated in the project development.

54

55

6.4. Are there any anthropological or archaeological sites or artefacts nearby? State if any other significant features in the vicinity of the proposed site have been considered. Ans. There is no report of existence of any anthropological or archaeological site nearby the project area. As per the list published by Archeological Survey of India, the following place is located in the project vicinity. Approx. Distance & Sr. No. Name Direction 1. Parasurama, Siva, Brahma and Matsya 15 km (SE) Temple, Thiruvallam (Archeological Protected Monument)

Further details are provided in Form-1 in the Environmental Sensitivity portion. The proposed project is located in Trivandrum Municipal Corporation, Trivandrum District. The vicinity map showing the site & surrounding area is provided at Annexure No. 6.

7.0 SOCIO-ECONOMIC ASPECTS

7.1. Will the proposal result in any changes to the demographic structure of local population? Provide the details. Ans. The proposed project is an IT/ITES office building project within the existing Technopark Phase-1 Campus. During operation phase, on full occupancy of the proposed office building, the maximum population expected is about 2,000 persons (floating) and hence there will be influx of people to the project area and surrounding. Hence there will be increase in demographic structure of the local population. The Socio-economic Study Report along with Corporate Environment Responsibility (CER) at Annexure No. 15.

7.2. Give details of the existing social infrastructure around the proposed project. Ans. The proposed project is an IT/ITES office building project within the existing Technopark Phase-1 Campus. Within the Technopark campus, there are several office buildings. Also, the proposed site is falling in Pangappara Village which in Thiruvananthapuram Municipal Corporation, Thiruvananthapuram District. There are several schools, colleges, places of worship, hospitals, commercial and residential buildings, Govt. and private offices, which are located around the proposed project. Further, to assess the socio-economic conditions near the project site a socio-economic survey was carried out by the approved expert and the socio-economic report is enclosed at Annexure No. 15. The toposheet showing the project site and existing features around the 10 km radius of the project site is attached as Annexure No. 16. Also, enclosed herewith is the Satellite image showing the 10 km radius of the site surrounding features at Annexure No. 17.

7.3. Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed? Ans. The project site would not cause any adverse effects on local communities, disturbance to sacred sites or other cultural values. The proposed project is an IT/ITES office building project within the existing Technopark Phase-1 Campus and thereby the living index of the people around the project site will definitely improve. Also there will be various ancillary activities like convenience shops, offices, transport facilities etc. attached to the project which will benefit the local people and change their living condition.

55

56

For delivering the Corporate Environment Responsibility (CER) a need assessment study of the surrounding area near the site was carried out by the approved expert and the report is enclosed.

8.0 BUILDING MATERIALS

8.1. May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency) Ans. The proposed project is an IT/ITES office building project within the existing Technopark Phase-1 Campus. The proposed office building will be of centrally air conditioned, the selection of building materials plays a major role in the energy consumption. The proposed project will make attempts to use to avoid building materials with high embodied energy. The glass used will be low emissivity and having U value as per ECBC norms.

8.2. Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts? Ans. All vehicles which bring construction material to the site would possess Pollution Under Control Certificates (PUC). All vehicles would be of close body to avoid spread of dust from the loose materials, and vehicles which bring sand, stone dust, etc. would ensure that the above mentioned material are properly wetted during transportation to avoid dust generation. Pucca road will be made in the construction site for the vehicle movement so that the dust generation due to the vehicular movement within the project site can be minimized. Stacking of construction material shall be confined to the project site only. Further barricading of the site with GI sheets of 20 ft height in the side abutting the public road during construction phase.

8.3. Are recycled materials used in roads and structures? State the extent of savings achieved? Ans. The plastic (non-biodegradable solid waste) would be used along with coal tar during the construction of internal roads. This will increase the life of roads.

8.4. Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project. Ans. SOLID WASTE  The proposed IT/ITES office building will generate 800 Kg/day of solid waste.  The Solid Waste Management Rules, 2016 will be followed in the Solid Waste management at the site.  Collection & segregation within the site (bio-degradable waste (in green bins), non-biodegradable waste (in blue bins) and domestic hazardous waste (in yellow bins).  The recyclable waste like packaging material, paper etc. would be sold through vendors (500 kg/day). The Bio-degradable waste would be disposed through the Organic Waste Converter (OWC) to be installed within the site (300 kg/day).  The manure generated will be utilized for green area development within the premises.  The domestic hazardous waste which includes discarded painted drums, pesticide cans, LED bulbs, tube lights, expired medicines, broken mercury thermometers, used batteries, used needles and syringes and contaminated 56

57

gauge etc. generated at site will be collected in yellow bins and to be handed over to authorized waste pickers or waste collectors.

9.0 ENERGY CONSERVATION

9.1. Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption? Ans. The total power requirement is estimated to be 1,778 kVA which will be met from by Kerala State Electricity Board. The project will make provision of DG Sets (1010 kVA x 2 nos + 380 kVA x 1 no) as standby arrangement of electricity. Energy consumption assumed per square foot of built-up area = 0.0051 W/sq foot. The energy conservation measures to minimize energy consumptions are the following :-  Proposed facility will have water cooled chillers in place of air cooled chillers which are energy intensive & the treated water available from STP would be used as make-up water attached to the water cooled chillers.  Solar Energy operated Photovoltaic lighting for partial external areas lighting.  LED lamps will be used which amount to 10% of demand load.  Installation of HF ballast instead of conventional ballast in common area lighting including external lighting and landscape lighting.  Installation of solar lighting (20 nos of 90 watts) for external lighting with battery  Building Management System (BMS) through sensors for maximizing the energy conservation.  Electrical fixtures & HVAC unit would be of 5 star series as per Bureau of Energy Efficiency (BEE) to achieve reduction in energy consumption.  45 kW Solar system without battery for utility load mounted on terrace.

Further details are given below :-  Pumps and Transformer efficiency and losses shall be in compliance with ECBC 2017. LED light fixture throughout facility.  Occupancy based lighting in common toilet, conference hall & meeting rooms.  Solar power generation will be provided depending on space availability on the terrace.  Lighting power density ( LPD ) as considered as follows :- • Common areas - 0.35 w/sq.ft • Service areas - 0.35 w/sq.ft • Parking areas - 0.25 w/sq.ft • Office areas - 0.65 w/sq.ft • External areas - 0.1 w/sq.ft  The voltage drop allowed in the circuit will be 3% as per KSEB regulation. • DGs that comply with CPCB norms for emissions as well as noise levels will be considered. • Battery charging stations - Electrical vehicle supply equipment (EVSE) in 2% of all parking spaces used by the project. • Alternate circuit switching arrangements for corridors and parking areas. • Timer/Photocell based automatic switching for external lights. • Installation of Energy meters in each and every panels with RS 485 port provision for monitoring and computing energy conservation.

57

58

9.2. What type of and capacity of power back-up to you plan to provide? Ans. The project proponent has made provision of D.G. Sets (1010 kVA x 2 nos + 380 kVA x 1 no) as backup energy.

9.3. What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation? Ans. The glass used will be with low emissivity and the other specifications of the glass will comply with the norms as per ECBC.

9.4. What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project. Ans. Passive solar architectural feature like shading, orientation of the building etc are adopted in the design of the office building.

9.5. Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details. Ans. 45 kW Solar power system will be installed for use of solar generation without battery for utility loads mounted on terrace. 90 Watts of Solar street lights (20 nos.) with battery will be installed for use of solar energy which will be used for street lighting, emergency lighting etc.

9.6. Is shading effectively used to reduce cooling/ heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected? Ans. Passive solar architectural feature like shading, orientation of the building etc are adopted in the design of the new buildings.

9.7. Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications. Ans. Suitable energy optimization will be adopted during the calculation of energy load of the proposed project. The space heating load will be minimized using passive solar structure and suitable building envelop material. Uses of incandescent lamp and halogen lamps have been avoided and energy efficient LED lamps will be used for all common area. The diesel generator sets shall be automatically controlled to optimize their usage based on the actual load requirements at any time. Variable frequency drive systems would be adopted for the lifts etc. to maximize the energy saving.

9.8. What are the likely effects of the building activity in altering the micro-climates? Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects? Ans. More open spaces are proposed within the site to creation of any heat islands. The roads and parking spaces would be with concrete slabs intermittent with grass on surrounding.

9.9. What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R values of the individual components. Ans. The building construction material namely bricks, concrete and steel are being used in the construction. U-factor, also known as Thermal 58

59

Transmittance, is heat transmission in unit time through unit area of a material or construction and the boundary air films, induced by unit temperature difference between the environments on each side. The glass used will be low with low emissivity and the other specifications of the glass will comply with the norms as per ECBC.

9.10. What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans. Ans. Risk hazard from fire - List of equipments proposed for Fire Fighting Measures:- A. The major equipments proposed for Fire Fighting Measures are Main Hydrant Pump, Sprinkler Pump, Diesel Engine Pump, Jockey Pump. B. Capacity of Fire Water Storage Tanks:- It is proposed to have Fire Water Storage Tank of appropriate capacity of overhead tank for fire fighting provided at the tower. C. Fire Detecting Equipments: - The Fire Detecting Equipments would be as per BIS and NBC norms. D. Other Fire Fighting Measures: - The other Fire Fighting Measures proposed includes, an Emergency Control Room, Separate Fire exit during emergency, all rooms with Fire Detector / Smoke Detector, Fire Extinguishes at each entry and exit point on each floor, (5 Kg, 10 Kg and 9 Ltr. capacity), Public address system etc. The Fire Fighting Measures are backed by Electrical supply from D.G. sets in case of emergency. The nearest fire station is at Technopark fire station which is 0.6 km. (NW) away from the project site. E. The fire fighting related other details are given below :-

No. of lifts with capacity 3 nos. x 16 passagers / lift = 48 passagers (operate with jockey pumps during contingency) No. of stretcher lifts with capacity 1 nos. No. of Fire exits with width of fire exits 2 nos. with 1.5 m. wide Distance from the farthest point to the nearest fire 45 m. exit No. of assembly points with area and no. of 540 sqm, 1,800 Persons persons the assembly point can accommodate Total no. of automatic sprinklers Approx. 2250 nos. Total no. of fire detectors / alarms Approx. 413 nos Total no. of Hooters 30 nos. Name of nearest fire station Fire & Rescue Station, Technopark Campus (name & aerial distance) at 600 m Aerial Distance

Relevant NBC code for fire safety to be followed As per NBC Provisions Particulars requirements proposed 1 riser for every 2 nos. of sprinkler 1 Nos. of hydrant risers with diameter 1,000 m2 and hydrant riser

59

60

with 150 mm dia Manually operated fire alarm system details Addressable alarm (intelligent addressable manual call point with manual and system and 2 inbuilt turbo isolator and intelligent addressable automatic alarm Manually operated loop powered / external powered sounder cum system alarm system beacon. ) 3 Capacity of overhead Fire water storage tank 10,000 ltr. 20,000 ltr. 1 no. for every 30 nos. & 30 m. 4 Hose Reel Length & nos. 1000 sq.m. & length 30 m length 1 for every 30 m 5 Numbers of Fire Exits 2 nos. radius GI Heavy Class 6 Type of pipe to be used in the fire hydrant system MS/GI Pipe pipe,

9.11. If you are using glass as wall material provides details and specifications including emissivity and thermal characteristics. Ans. The glass will be used Low-e glass. Opaque assemblies shall be modeled as having the same heat capacity as the proposed design but with minimum U-factor. The U value of glass used as per ECBC guidelines.

9.12. What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration. Ans. Infiltration is the uncontrolled inward air leakage through cracks and crevices in any building element and around windows and doors of a building caused by pressure differences across these elements due to factors such as wind, inside and outside temperature differences, and imbalance between supply and exhaust air systems.

9.13. To what extent the non-conventional energy technologies are utilised in the overall energy consumption? Provide details of the renewable energy technologies used. Ans. The Non-conventional energy will be used. 45 kW Solar power system will be installed for use of solar generation without battery for utility loads mounted on terrace. 90 Watts of Solar street lights (20 nos.) with battery will be installed for use of solar energy which will be used for street lighting, emergency lighting etc.

10.0 Environment Management Plan The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire. Ans. The Environment Management Plan is enclosed with the application.

60

ENVIRONMENT MANAGEMENT PLAN 61 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

A

REPORT

ON

ENVIRONMENT MANAGEMENT

PLAN

ENVIRONMENT MANAGEMENT PLAN 62 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

INDEX

SR. CONTENTS NO.

1. INTRODUCTION

AREAS FOR IDENTIFICATION OF ENVIRONMENTAL ASPECTS & 2. IMPACTS

3. ENVIRONMENT MANAGEMENT PLAN (EMP)

IMPACTS & MITIGATION MEASURES DURING CONSTRUCTION A. PHASE

IMPACTS & MITIGATION MEASURES DURING OPERATION B. PHASE

ENVIRONMENT MANAGEMENT PLAN C. (BUDGETARY ALLOCATION) ENVIRONMENT MONITORING PLAN (BUDGETARY ALLOCATION) D. DURING CONSTRUCTION PHASE & OPERATION PHASE E. ENVIRONMENT MANAGEMENT / MONITORING CELL

F. RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN (DMP)

G. SUMMARY & CONCLUSION

ENVIRONMENT MANAGEMENT PLAN 63 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

1. INTRODUCTION M/s Brigade Enterprises proposes to construct IT/ITES office building project at Technopark Phase-1 Campus in Plot no. 75, Re-survey no. 66/1-1 (old sy. no. 710), Pangappara Village, Thiruvananthapuram Corporation, Thiruvananthapuram Taluk & District, Kerala.

The proposed land is spread over an area of 0.4047 ha. The total built- up area for the project will be of 25,771.2 sqm.

The land for the project is leased to the project proponent by Technopark (A society wholly controlled by Government of Kerala) for a period of 99 years.

The population expected during construction phase of the project is about 300 persons per day which includes the skilled, semi skilled & unskilled workers. Also, this includes engineers, supervisors, technicians & other managerial staff.

The population calculation for the proposed project during the operation phase of the project is made based on the specifications provided in National Building Code (NBC). The maximum expected population in a day during operation phase of the proposed IT/ITES office building project is worked out. The specifications as per NBC and the expected population for the proposed buildings is given below:-

FAR Area Activity Population (in sq.m.) 1,814 Persons IT/ITES office 18,140 ( @ 10 sq.m. per person of FAR area )

181 Persons Housekeeping staff -- ( 10% of I.T. staff of 1,814 Persons )

TOTAL 1,995 Persons say 2,000 Persons

One of the main criteria for quantifying the environment impacts related to the project during the construction phase and operation phase for the project is the maximum population expected in a day. Based on

ENVIRONMENT MANAGEMENT PLAN 64 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

which the requirement of daily water consumption, waste water generation, solid waste generation etc. is calculated. The Environment Management Plan (EMP) is a site specific plan developed to ensure that the project is implemented in an environmentally sustainable manner and to understand the potential environmental risks arising from the proposed project and take appropriate actions to minimize those risks. EMP also ensures that the project implementation is carried out in accordance with the planned design and by taking appropriate mitigation measures to reduce adverse environmental impacts during the project’s life cycle. 2. AREAS FOR IDENTIFICATION OF ENVIRONMENTAL ASPECTS AND IMPACTS The environmental parameters likely to be affected by a construction project are related to many factors, i.e. physical, social, economic etc. The operations may disturb environment of the project area and its surroundings in various ways, such as removal of mass / earth, change of landscape, clearing of flora and displacement of fauna of the area, surface drainage, and likely change in air quality, water quality and soil quality. While for the purpose of development and economic up-liftment of people, there is need for establishment of the project, but these should be environment friendly. Then only a sustainable development can be ensured. Therefore, it is essential to assess the impacts of proposed project on different environmental parameters, before starting the construction activities as well as the operational activities, so that abatement measures could be planned in advance for the area. 3. ENVIRONMENT MANAGEMENT PLAN (EMP) The Environment Management Plan (EMP) for a development project prescribes the mitigation measures to be adopted to nullify or to minimize various anticipated environment impacts so as to ensure nil / low impact due to the project to the surrounding environment. This will ensure sustainable and environment friendly development. The Environment Management Plan for various facets of environment are given below : -

ENVIRONMENT MANAGEMENT PLAN 65 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

A. IMPACTS & MITIGATION MEASURES DURING CONSTRUCTION PHASE Impacts on Environment during Construction phase are:- 1. Air environment 2. Water environment 3. Noise environment 4. Land environment including municipal solid waste 5. Biological environment 6. Socio Economic environment 7. Energy Conservation The detailed description of Impacts & mitigation measures envisaged during Construction phase are given below:- 1. AIR ENVIRONMENT Anticipated Impacts:- a. Particulate matter & gaseous emissions from operation of DG sets (150 kVA x 1 no.) b. Dust generation due to vehicular movement within the site c. Dust generation due to various construction activities (transportation of raw materials, loading & unloading, drilling, breaking & dismantling works etc.) Mitigation Measures:-  Stack height of D.G. set as per CPCB Standards.  Promotion of use of cleaner fuel  All DG set should comply emissions norms notified by MoEF / CPCB.  Sprinkling & wetting of roads  Wetting of loose construction materials before loading & unloading.  Tarpaulin cover for the loose construction material during transfer.  Temporary & portable enclosures where the drilling & dismantling works are carried out.  To avoid work during high windy conditions.  To erect the wind barriers around the construction area to avoid the influence of the winds in the construction activity.  Storing of all loose construction materials in covered condition. 2. WATER ENVIRONMENT Anticipated Impacts :-

ENVIRONMENT MANAGEMENT PLAN 66 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

a. Impact on competing users (if water is taken from the public supply) due to large consumption of water for curing, dust suppression, construction, domestic use etc. b. The daily construction water requirement for construction purposes is expected to be about 32 KL and the domestic water requirement (daily) is expected to be about 40 KL. Mitigation Measures :-  To avoid wastage of curing water, following procedures are suggested:- • Curing water should be sprayed on concrete structures: free flow of water should not be allowed for curing. • After liberal curing on the first day, all concrete structures should be painted with curing chemical to save water. This will stop daily water curing. • Concrete structures should be covered with thick cloth / gunny bags and then water should be sprayed on them. This would avoid water rebound and will ensure sustained and complete curing. • Ponds or tanks should be made using cement and sand mortar to avoid water flowing away from the flat surface while curing.  Monitoring water use:- Use of water meter conforming to ISO Standards would be installed at the inlet point of water uptake and at all discharge points to monitor the daily water consumption.  Use of labour sheds (temporary accommodation) (if proposed within the site) & for construction purposes.  Use of treated water from mobile STP (to be installed for the treatment of domestic sewage) for labour quarters/ labour sheds for flushing purposes.  Use of treated water from STP for sprinkling, wetting & dust suppression.  Install water efficient sanitary fixtures in the rest rooms & toilets attached to the labour quarters/ labour sheds.

ENVIRONMENT MANAGEMENT PLAN 67 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

3. NOISE ENVIRONMENT Anticipated Impacts :- a. Noise & vibration from D.G. sets due to inadequate acoustic enclosure. b. Noise due to cutting & grinding of marble stone / tiles. Mitigation Measures :-  Use of DG sets with appropriate acoustic enclosures  Use of anti vibration pads.  Wind breakers / acoustic enclosures made of gunny bags filled with sand or earth and stacked up to a height of about 7-8 ft. at the cutting & grinding area. This arrangement works as wind breaker & as a noise barrier. 4. LAND ENVIRONMENT INCLUDING MUNICIPAL SOLID WASTE Anticipated Impacts :- a. Improper disposal of excavated earth like disposal to natural drainage, filling of low land etc. b. Loss of top soil c. Soil erosion during the rainy season c. Disturbing the ground water table and thereby depletion of ground water (impact on hydrogeology) due to the excavation for of basement d. Improper disposal of municipal solid waste, construction debris may lead to impact on land environment. Mitigation Measures :-  Excavation / cutting of earthwork for the foundation of structures and for basements which is proposed to be occupied for parking. The total excavated/cutting of earth is 12,147 cum. The top soil (1,822 cum) which is fertile will be kept at site for future landscaping work. The excavated soil will be used for back filling work (3,644 cum) for site leveling and 4,203 cum will be used for internal road construction work, walkways. The excess excavated earth of 2,478 cum will be used for formation of soil stabilized blocks which shall be used in construction. As per the topographical contour survey map, there is

ENVIRONMENT MANAGEMENT PLAN 68 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

level difference of about 4 m. in east to west direction. This level difference made use during development of the proposed site.  There is old small structure / buildings existing which will be demolished. The demolition waste to be generated due to the demolition of existing buildings will be handled as per the Guidelines of Construction and Demolition Waste Management & Handling Rules, 2016.  Piling will be carried out before excavation for basements.  Excavation will be done only in summer season to prevent disturbance to the hydrogeology.  Prevention of water ingress to the structures below the existing ground level :- • After excavation, soil stabilization with sand filling of 15 cm. thickness will be done. • Over the sand filling, 12 cm. thick PCC will be done. • A polythene sheet of 0.40 mm thickness will be laid over the PCC. • Over the polythene sheet, raft slab of around 20 cm. thickness will be done. • Further, any leak observed, pressure grouting will be done.  Mitigation measures for handling of municipal solid waste (about 75 kg/day) from the site. • Segregation of waste at source into biodegradable and non biodegradable waste by providing colored bins. • Disposal of biodegradable Municipal Solid Waste through authorized agencies of Thiruvananthapuram Municipal Corporation. • Disposal of non biodegradable recyclable waste to vendors. • Disposal of inert waste by land filling / back filling. 5. BIOLOGICAL ENVIRONMENT Anticipated Impacts :- a. Loss of vegetation and loss of habitat of faunal species. b. Vibration due to movement / operation of heavy machinery c. Cutting of trees, shrubs etc. for procuring fire wood by construction workers. (resource loss)

ENVIRONMENT MANAGEMENT PLAN 69 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

Mitigation Measures :-  The proposed project is an IT/ITES office building and site is devoid of trees and there is not much of loss of vegetation and loss of habitat. Further, attempt will be made to save any tree existing at site by altering the footprint of the building (if possible).  The labourers would be provided with LPG or kerosene for cooking purposes. 6. SOCIO ECONOMIC ENVIRONMENT Anticipated Impacts :- a. Unhygienic site sanitation facilities may affect health to construction workers (about 300 persons). b. The project site being in the Municipal Corporation limits, will have disturbance to the traffic load in the existing approach roads to the site within the Technopark campus. Mitigation Measures :- The objective is to ensure health and safety of the workers with effective provisions for the basic facilities of sanitation, drinking water, safety of equipments or machinery etc. Following are some of the recommendations :-  Comply with the safety procedures, norms and guidelines (as applicable) as outlined in the National Building Code of India, Bureau of Indian Standards.  Provide clean drinking water to all workers.  Provide adequate number of decentralized latrines and urinals.  Guarding all parts of dangerous machinery.  Precautions for working on machinery.  Maintaining hoists and lifts, lifting machines, chains, ropes and other lifting tackles in good condition.  Durable and reusable formwork systems to replace timber formwork and ensure that formwork where used is properly maintained.  Ensuring that walking surfaces or boards at height are of sound construction and are provided with safety rails or belts.  Provide measures to prevent fires. Fire fighting extinguishers and buckets of sand to be provided in the fire prone area and elsewhere.  Provide sufficient and suitable light for working during night time.

ENVIRONMENT MANAGEMENT PLAN 70 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

Regarding the additional traffic during construction phase on the approach road to the site, the following mitigation measures are proposed :-  Procurement of materials in bulk & not in loose will reduce the traffic to the site.  Movement of raw material to the site only during night hours.  Dedicated parking space for vehicles coming to the site including those for the visitors so as to avoid parking on the roads.  The vehicle carrying ready mix concrete should be avoided in the peak traffic hours (morning 8 am to 11 am & evening 4 pm to 8 pm).

7. ENERGY CONSERVATION Anticipated Impacts :- a. Use of energy in-efficient building materials may lead to higher consumption of electricity in air-conditioned buildings. Mitigation Measures :-  Use of building material for roof, walls & glass (R & U values) as per ASHRAE standards for less heat gain in air-conditioned building.

ENVIRONMENT MANAGEMENT PLAN 71 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

B. ANTICIPATED IMPACTS & MITIGATION MEASURES DURING OPERATION PHASE

Anticipated impacts on Environment during Operation phase are given below:- 1 Air environment 2 Water environment 3 Noise environment 4 Land environment 5 Biological environment 6 Socio economic environment 7 Energy Conservation The detailed description of Impacts & mitigation measures during Operation phase are given below :- 1. AIR ENVIRONMENT Anticipated Impacts :- a. Particulate Matter & Gaseous emissions (including worst condition of operating all DG sets (1010 kVA x 2 nos + 380 kVA x 1 no) during power failure. Mitigation Measures :-  Stack height as per CPCB Standards.  Development of a green belt (vegetation buffer) around the project site.  Promotion of use of cleaner fuel  All DG set should comply emissions norms notified by MoEF / CPCB. 2. WATER ENVIRONMENT Anticipated Impacts :- a. Impact on competing users due to consumption of public supply / ground water (resource loss) for domestic consumption in the project site. b. Impact on competing users due to consumption of public supply / ground water as make-up water for HVAC in the campus (resource loss) c. Improper discharge of untreated sewage may lead to impact on surface / ground water quality. d. Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination.

ENVIRONMENT MANAGEMENT PLAN 72 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

e. Improper storage & disposal may lead to leaching of hazardous waste leading to contamination. f. The daily water requirement for the project is expected to be about 123 KL (fresh water req. 50 KLD + recycled water 73 KLD). The first day water requirement will be of 123 KLD and subsequent days, the daily fresh water requirement will be of 50 KL. Mitigation Measures :-  Monitoring water use: Use of water meter conforming to ISO Standards would be installed at the inlet point of water uptake and at the discharge point to monitor the daily water consumption.  Use of water saving devices / fixtures: Low water consumption fixtures like low flow flushing systems, sensor based fixtures, waterless urinals, tap aerators etc. to reduce the water usage.  Installation of dual plumbing for using the treated water from STP for flushing purposes, horticulture purposes and for other purposes.  Use of stored rain water (with storage tank capacity of 140 KL)  Sewage treatment plant proposed (85 KLD capacity).  Treatment of domestic sewage (81 KLD) and recycling of the treated sewage and ensuring zero discharge.  Use of excess treated water of STP as make-up water in HVAC system requirement water requirement.  Treatment unit with primary, secondary and territory treatment proposed.  Estimation of daily water consumption based on the HVAC losses, reuse and recycled options.  Monitoring water use: Use of water meter conforming to ISO Standards would be installed at the inlet point of water uptake and at the discharge point to monitor the daily water consumption in HVAC unit.  Disposal of e- waste only to the authorized agency  Maximum use of existing topography so as to minimize the excavation of earth.

ENVIRONMENT MANAGEMENT PLAN 73 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

3. NOISE ENVIRONMENT Anticipated Impacts :- a. Noise due to the operation of D.G. sets (1010 kVA x 2 nos + 380 kVA x 1 no.) during power failure. b. Noise due to the operation of cooling towers. Mitigation Measures :-  D.G. sets with acoustic enclosures.  A noise barrier will be made all around the cooling tower to prevent the noise.  Also, an environmental barrier by way of tree plantation can be created around the project site to prevent the noise. 4. LAND ENVIRONMENT Anticipated Impacts :-

ENVIRONMENT MANAGEMENT PLAN 74 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

a. Improper disposal of municipal solid waste (800 kg/day) may lead to impact on land. b. Improper discharge of untreated sewage may lead to impact on land. c. Improper storage & disposal of e-waste may lead to leaching of heavy metals leading to contamination. d. Improper storage & disposal of hazardous waste may lead to leaching of waste leading to contamination. Mitigation Measures :-  Segregation of waste at source into biodegradable and non biodegradable waste by providing colored bins.  Disposal of biodegradable Municipal Solid Waste by Organic Waste Converter system.  Disposal of non biodegradable recyclable waste to vendors.  Disposal of inert waste by land filling / back filling.  Disposal of sewage through the STP within the site and re-use the treated sewage within the site.  Storage of e-waste as per rules and in an isolated area.  Disposal of e-waste only to the authorized agency.  Disposal of the hazardous waste to the State Pollution Control Board approved agency. 5. BIOLOGICAL ENVIRONMENT Anticipated Impacts :- a. Improper disposal of MSW may attract scavenger avifauna which may lead to dissertations of native avifauna. Mitigation Measures :-  An appropriate landscape plan developed for the loss of vegetation.  The native species of flowering, fruit bearing & medicinal plants proposed in the green area development plan.  Segregation of waste at source into biodegradable and non biodegradable waste by providing colored bins.  Storage & segregation of biodegradable municipal solid waste in appropriate places & disposal of biodegradable Municipal Solid Waste by Organic Waste Converter system.  Disposal of non biodegradable recyclable waste to vendors.

ENVIRONMENT MANAGEMENT PLAN 75 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

 Disposal of inert waste by land filling / back filling.  Plantation of native species of trees / shrubs / herbs / grass for enhancement of avifauna  Conservation of the existing trees wherever possible.  Plantation of fruit bearing trees to enhance the avifauna 6. SOCIO-ECONOMIC ENVIRONMENT The OM No. 22-65/2017-IA.III states that every green field project having capital investment less than Rs. 100 crores need to allocate 2% of its project cost (capital investment) for activities under Corporate Environment Responsibility (CER). The instant project is a green field project and its capital investment is Rs. 52 Crores. Therefore, the project has to spend a maximum amount of Rs. 1.04 Crores under CER. In the OM, MoEF has suggested a wide range of areas, where the project proponent can implement their activities. The suggested areas by MoEF&CC is given below. The Suggested Sectors to Perform Activities under CER by MoEF&CC 1. Drinking water supply, 2. Sanitation, 3. Health, 4. Education, 5. Skill development, 6. Roads, 7. Cross drains, 8. Electrification including solar power, 9. Solid waste management facilities, 10. Scientific support and awareness to local farmers to increase yield of crop and fodder, 11. Rain water harvesting, 12. Soil moisture conservation works, 13. Avenue plantation, 14. Plantation in community areas etc. The detailed study for need assessment was carried out by the approved expert and report is attached with the application. 6. ENERGY CONSERVATION Anticipated Impacts :-

ENVIRONMENT MANAGEMENT PLAN 76 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

a. Adoption of energy in-efficient vehicles, HVAC system, appliances, lights etc may lead to wastage of energy. b. Non adoption of renewable sources of energy like solar energy may lead to increase dependency on public supply may lead to consumption of energy by competing users. c. The total power requirement is estimated to be 1,778 kVA. Mitigation Measures :- The energy conservation measures to minimize energy consumptions are the following :-  Proposed facility will have water cooled chillers in place of air cooled chillers which are energy intensive & the treated water available from STP would be used as make-up water attached to the water cooled chillers.  Solar Energy operated Photovoltaic lighting for partial external areas lighting.  LED / CFL lamps will be used which amount to 10% of demand load.  Installation of HF ballast instead of conventional ballast in common area lighting including external lighting and landscape lighting.  Installation of 45 kW Solar power system for use of solar generation without battery for utility loads mounted on terrace. 90 Watts of Solar street lights (20 nos.) with battery will be installed for use of solar energy which will be used for street lighting, emergency lighting etc  Building Management System (BMS) through sensors for maximizing the energy conservation.  Electrical fixtures & HVAC unit would be of 5 star series as per Bureau of Energy Efficiency (BEE) to achieve reduction in energy consumption. Further details are given below :-  Pumps and Transformer efficiency and losses shall be in compliance with ECBC 2017. LED light fixture throughout facility.  Occupancy based lighting in common toilet, conference hall & meeting rooms.  Solar power generation will be provided depending on space availability on the terrace.

ENVIRONMENT MANAGEMENT PLAN 77 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

 Lighting power density ( LPD ) as considered as follows :- • Common areas - 0.35 w/sq.ft • Service areas - 0.35 w/sq.ft • Parking areas - 0.25 w/sq.ft • Office areas - 0.65 w/sq.ft • External areas - 0.1 w/sq.ft  The voltage drop allowed in the circuit will be 3% as per KSEB regulation. • DGs that comply with CPCB norms for emissions as well as noise levels will be considered. • Battery charging stations - Electrical vehicle supply equipment (EVSE) in 2% of all parking spaces used by the project. • Alternate circuit switching arrangements for corridors and parking areas. • Timer/Photocell based automatic switching for external lights. • Installation of Energy meters in each and every panels with RS 485 port provision for monitoring and computing energy conservation.

C. ENVIRONMENT MANAGEMENT PLAN (BUDGETARY ALLOCATION) The details regarding Environment Management Plan (Expected Budgetary Allocation) during construction phase are given below :- Approx. Approx. Sr. Recurring Capital Basis for Cost Particulars No. Cost / Annum Cost Estimate Rs. In Lacs A First Aid medical Medical cum First Aid 1. 1.5 0.7 facility with a trained facility person with first aid kit. Portable Toilets type Portable Toilets like 2. mobile sanitation 0.5 1.5 “Sulabh Sauchalaya ” & system & STP STP Rain water from tank Supply of drinking with filtration 3. 3.0 2.0 water for the labourers disinfection, well water & KWA supply Barricading around the Barricading and Wind 4. 2.0 3.5 project site Wind breakers breakers at the marble

ENVIRONMENT MANAGEMENT PLAN 78 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

cutting area Sprinklers, pipeline Sprinklers for network, online micro 5. 1.0 2.5 suppression of dust filters and pressure pumps Segregation & Disposal of Solid waste from labour biodegradable Municipal 6. shed & construction 0.5 1 Solid Waste through site authorized agencies of Thiruvananthapuram Municipal Corporation TOTAL 8.5 11.2

The details regarding Environment Management Plan (Expected Budgetary Allocation) during operation phase are given below :- Approx. Approx. Sr. Recurring Capital Particulars Basis for Cost Estimate No. Cost/Annum Cost Rs. In Lacs Capital Cost of STP & Sewage Treatment recurring cost would 1. Plant with ultra 5.0 40.0 include operational cost filtration (energy & manpower) Capital cost of Coloured bins at appropriate Solid Waste 2. 2.0 10.0 locations & Organic waste Management Plant converter & its recurring cost. D.G. Sets will be new and will be fitted with acoustic Noise Control for D.G. enclosures & hence no 3. Sets through acoustic 2.0 6.5 separate capital cost & the enclosures recurring cost woul d include minor repair works The capital cost would include cost of providing Chimney for D.G. Sets adequate height of stack, 4. 1.5 4.5 Emission ladder and platform and recurring cost would include cost of painting Green Area Green Area Development 5. development including 3.0 8.0 Plan Grass Coverage Capital cost on Rain Water Storage 6. 2.0 14.0 construction of rain water tanks collection tanks

ENVIRONMENT MANAGEMENT PLAN 79 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

Capital cost on Solar energy operated 7. 4.0 20.0 procurement & installation lights of solar panels TOTAL 19.5 103

D. ENVIRONMENT MONITORING PLAN (BUDGETARY ALLOCATION) DURING CONSTRUCTION PHASE & OPERATION PHASE The environmental monitoring programmed is a vital process in the management Plan for any construction project. This helps in signaling the potential problems that would result from the proposed project and will allow for prompt implementation of effective corrective measures. The environmental monitoring will be required during construction and operational phases. The following routine monitoring programme as detailed below shall be implemented at site. Besides to this monitoring, the compliances to all environmental clearance conditions and consents / approvals from KSPCB / MoEF&CC / SEIAA will be monitored and reported periodically. The details regarding Environment Monitoring Plan (expected Budgetary Allocation) during construction phase are given below :- Approx. Sr. Particulars Parameters Frequency Recurring cost No. / Annum (Rs. In Lacs) Monthly Ambient Air

Quality PM 1 0 & PM 2 .5 , (2 Samples / 1. 1.5 Monitoring SO2, NOx, Location) (AAQM)

Monthly Ambient Noise 24 Hrs. Noise 2. (2 Samples / 0.50 Monitoring Level Location) Quarterly (All parameters listed 3. Ground Water 1 Sample in IS 10500 0.40 Standards)

4. Soil 1 Sample Quarterly (N, P, K 0.40

ENVIRONMENT MANAGEMENT PLAN 80 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

& Heavy Metals) TOTAL 2.80

The details regarding Environment Monitoring Plan (Budgetary Allocation) during operation phase are given below :- OPERATION PHASE Approx. Sr. Recurring Cost Particulars Parameters Frequency No. / Annum (Rs. In Lacs) Quarterly PM 1 0 & PM 2 . 5 , 1. Ambient Air 1 Sample / 1.5 SO 2 , NOx, CO Location Stack Emission Once in a 2. SPM, SO 2 , NOx 0.75 of D.G. sets year pH, BOD, COD, Oil Treated Water from & Grease, TSS, Once in a 3. Sewage Treatment 1.5 bacteriological month Plant parameters Once in a 4. Stored Rain water As per IS : 10500 0.75 season Quarterly 5. Noise Level 24 Hrs. Noise Level 1 Sample / 0.25 Location TOTAL 4.75

E. ENVIRONMENT MANAGEMENT / MONITORING CELL An environmental monitoring cell will be established for monitoring of important and crucial environmental parameters which are of immense importance to assess the status of environment during construction phase & operation phase. The details regarding Environment Monitoring Cell during Construction Phase & operation phase are given below :- Sr. No. Members Role

ENVIRONMENT MANAGEMENT PLAN 81 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

1. CEO Projects Chairman 2. Project Manager (Utility) Member 3. Health & Safety Officer Member 4. Representative of NABL accredited laboratory Member 5. Representative of NABET accredited Member Environmental Consultant 6. Representative of STP & Municipal waste disposal Member unit suppliers 7. Project Engineer Member & Convener Frequency of Meeting – Once In three months

F. RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN 1.1 Introduction This chapter broadly looks at various aspects related to risk & disaster management and resource conservation. 1.2 Risk Assessment and Disaster Management Plan 1.2.1 Need and Plans The proposed project is for construction of IT/ITES office building within the Technopark Phase-1 Campus encompasses the lives of a large number of people. It also involves installation of various structures and machineries that meet the comfort and needs of its population but may also pose serious threat to the occupants in case of accident. It is thus considered necessary to carry out a risk assessment and prepare a disaster management plan for the project. The planning and construction of the buildings follow all the safety norms, it may not be always possible to totally eliminate the risks of eventualities and failures of equipment or human errors. An essential part of major hazard control has therefore will be concerned with mitigating the effects of such emergency and restoration of normalcy at the earliest. The overall objective of an Emergency Response Plan (ERP) is to make uses of combined resources at the site and outside services to achieve the following: 1. To localize the emergency and if possible eliminate it; 2. To minimize the effects of the accident on people and property; 3. Effectively rescue and medical treatment of casualties; 4. Safeguard to other people;

ENVIRONMENT MANAGEMENT PLAN 82 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

5. Evacuate people to safe areas; 6. Informing and collaborating with statutory authorities; 7. Initially contain and ultimately bring the incident under control; 8. Preserve relevant records and equipment for the subsequent enquiry into the cause and circumstances of the emergency; 9. Investigating and taking steps to prevent reoccurrence The ERP is therefore related to identification of sources from which hazards can arise and the maximum credible loss scenario that can take place in the concerned area. The response plan takes into account the maximum credible loss scenario - actions that can successfully mitigate the effects of losses/ emergency need to be well planned so that they would require less effort and resources to control and terminate emergencies, should the same occur. Main hazards identified for the project include hazards pertaining to fires in buildings and fire in diesel storage areas, earthquake and LPG leakage an ERP pertaining to these condition is described in the following sections. 1.2.2 Response in Case of Earthquake Response Procedures for Occupants If indoors : 1. Take cover under a piece of heavy furniture or against an inside wall and hold on. 2. Stay inside: The most dangerous thing to do during the shaking of an earthquake is to try to leave the building because objects can fall on you. If outdoors : Move into the open, away from buildings, streetlights and utility wires. Once in the open, stay there until the shaking stops. If in a moving vehicle : Stop quickly and stay in the vehicle. Move to a clear / safe area away from buildings, trees, overpasses or utility wires. Once the shaking has stopped, proceed with caution. Avoid bridges or ramps that might have been damaged by the quake. After the quake 1. After the quake be prepared for aftershocks.

ENVIRONMENT MANAGEMENT PLAN 83 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

2. Although smaller than the main shock, aftershocks cause additional damage and may bring weakened structures down. Aftershocks can occur in the first hours, days, weeks, or even months after the quake. Help injured or trapped persons . 1. Give first aid where appropriate. Do not move seriously injured persons unless they are in immediate danger of further injury. Call for help. 2. Remember to help those who may require special assistance, like infants, the elderly and people with disabilities. 3. Stay out of damaged buildings. 4. Use the telephone only for emergency calls. Response Procedure for Emergency Team 1. Formulate an Emergency Response Team for earthquake response 2. Using the public address system, inform occupiers about response procedures discussed above. 3. Inform the necessary authorities for aid 4. Ensure no residents are stuck beneath any debris, in case of a structural failure. 5. Ensure that all occupiers standing outside near the buildings are taken to open areas. 6. Ensure that the first aid ambulance and fire tender vehicles are summoned if necessary. 7. Inform the nearby hospitals if there are any injuries. 8. Check the utilities and storage tanks for any damage. 1.2.3 Status on natural disasters w.r.t. site and surroundings Earthquakes :- As per seismic classification, the project site falls in Zone-III. The maximum expected earthquake intensity is VIII in MM scale or 5.6 M in Richter scale. Though small and medium earthquakes have occurred in the region. There is no reported large earth quake in the region as per the records available. Structural design aspects as per the IS Code (part 6) for Structural design of NBC of India, Other relevant codes for earthquake resistant design of structures and IS code of practice for ducting details of reinforced concrete structures subjected to seismic forces would be incorporated in the project development.

ENVIRONMENT MANAGEMENT PLAN 84 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

Landslide :- The topography of the project site and the area within 15 km radius is broadly flat in nature. There is no reported landslide within 15 km radius.

Erosion :- Part of the area falling within 15 km radius is abutting the sea and sea walls are constructed to prevent soil erosion.

Flooding :- The project site is not prone to flooding. As per the flood zonation map, part of the area falling within 15 km radius is abutting the sea and within 15 km. radius are prone to floods.

Lightening :- There are reported incidents of lightening in the area within 15 km radius during two seasons in the year viz. the season comprises of months April and May and second two months of October and November.

Tsunami :- Though Kerala Coast was encountered with the Tsunami dated 26-12-2004, the coastal area falling within 15 km. radius of the project site was not affected by this Tsunami.

Could Burst :- No reported cloudburst in the area falling within 15 km radius of the project boundary.

Cyclone :- The area within 15 km radius from the project site falls within moderate damage risk zone - B (Vb = 39 m/s) as per the Wind and Cyclone Hazard Map published by BMTPC : vulnerability Atlas - 2nd Edition, 2006.

Drought :- The area within 15 km. radius from the boundary of the project site experiences seasonal drought conditions during the summer months. Even in the years of normal rainfall, summer water scarcity problems are severe in Thiruvananthapuram city.

Heat wave / sunburn / sun stroke :- Indian Meteorological Department (IMD) issued heat wave warning in 2016 and in subsequent years. Several sunburn incidents were reported from the area within 15 km radius.

1.2.4 Response for LPG Leakage 1. The affected area should be evacuated and cordoned off immediately 2. Initiate an Emergency Response Team for LPG leakage. 3. Shut down the main valves in the gas bank, if any in the Canteen. 4. Ensure that only concerned personnel are present in the affected area and all other personnel and visitors are moved to the nearest assembly points. 5. Rescue trapped personnel, also check if any personnel are unconscious in the area and immediately move them outside and provide first aid. Ambulance should be summoned to take injured personnel to the nearest hospital.

ENVIRONMENT MANAGEMENT PLAN 85 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

6. Personnel in the nearby buildings to close all doors and windows to prevent entry of the leaked gas. 7. Source of leakage to be traced and isolated from all the other areas. And if required use pedestal fans to bring down the gas concentration. 8. In case of fire follow the instructions mentioned below: 1.2.5 Response in case of Fire 1. Required response during in the event of a fire should be described in sign boards located in the lobby. 2. On sighting a fire, it should be immediately informed to the environment manager / management giving the exact location and type of fire in detail. 3. Initiate the Emergency Response Team for fires. 4. If the fire is small, engage in extinguishing the fire using the nearest fire extinguisher. 5. Guide the Emergency Response Team staff to the emergency assembly point. 6. The Emergency Response Team should immediately inform the nearest dispensary and security force. If required a fire tender should be summoned. 7. The response team should immediately move to the point of fire and take all necessary steps to stop the fire. If the fire is not controllable and spreads then the manager in charge should inform the district authorities and call for external help. 8. The Emergency Response Team will provide immediate relief to the injured person at the scene of incident. Any injured persons should be evacuated on priority to the dispensary or one of the nearest hospitals based on their condition. Instructions for Occupants 1. Get out of buildings quickly and as safely as possible. 2. Use the stairs to escape. When evacuating, stay low to the ground. 3. If possible, cover mouth with a cloth to avoid inhaling smoke and gases. 4. Close doors in each room after escaping to delay the spread of the fire, if in a room with a closed door. 5. If smoke is pouring in around the bottom of the door or if it feels hot, keep the door closed. 6. Open a window to escape or for fresh air while awaiting rescue.

ENVIRONMENT MANAGEMENT PLAN 86 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

7. If there is no smoke at the bottom or top and the door is not hot, then open the door slowly. 8. If there is too much smoke or fire in the hall, slam the door shut. 9. Stay out of damaged buildings. 10. Check that all wiring and utilities are safe. A well planned fire fighting system is proposed for the project to prevent and control fire outbreaks. The fire fighting system will consist of portable fire extinguishers, hose reel, wet riser, yard hydrant, automatic sprinkler system and manual fire alarm system. The proposed building will also be provided with automatic fire detection and alarm system as per National Building Code guidelines for Fire & Safety.

G. SUMMARY & CONCLUSION Details of mitigative measures for the anticipated adverse impacts on different environmental facets are provided below: AIR ENVIRONMENT :- Construction phase :- • Internal roads within the site will be compacted with Jelly stones • Excavation of soil will be carried out only after erection of wind breakers of height of 1/3 rd of the building height to a maximum height of 10m height will be provided. • No loose soil or sand or construction & demolition waste or any other construction material will be left uncovered. • Water sprinkling and wetting of roads during summer days will be put in place. • Grinding and cutting of building material will be carried out in enclosures and wet jet shall be provided for grinding and stone cutting areas. • Construction material and waste will be stored within earmarked area only. • The loose construction materials will be covered during transportation. • The location of the DG set and exhaust pipe height shall be as per the provisions of CPCB / Kerala State Pollution Control Board norms. • The DG set installed for the project shall follow the emission limits, noise limits and general conditions notified by MoEF.

ENVIRONMENT MANAGEMENT PLAN 87 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

• All vehicles used in construction phase will be ensured with PUC certificate. • All construction equipments will be maintained regularly so as to ensure the emissions within limits. • All workers working at the construction site and involved in loading, unloading, carriage of construction material and construction debris or working in any area with dust pollution shall be provided with dust mask and other personnel protective equipments (PPE). • As far as possible, ready mix concrete (RMC) will be used to avoid the use of loose construction materials at site to reduce dust emissions. • Barricading all around the project site for a height of 20 feet.

Operation Phase : - • The stack attached to the proposed D.G. Set will follow all the rules and regulations of State Pollution Control Board and Central Pollution Control Board. • The fuel to be used in the DG set will use only Low Sulphur High Speed diesel. • Green area development around the project site boundary and within the site. WATER ENVIRONMENT :- Construction Phase: - • Use of curing agents to reduce water consumption • Use of ready mix concrete • A mobile STP for the treatment of domestic sewage from the laborers • Use of treated water from portable STP for wetting of roads, landscaping and for construction purposes. • A sedimentation cum oil and grease trap for the treatment of construction waste liquid. Operation Phase: • In order to improve the ground water table, ground water recharge structures can be installed (if required). • Treatment and recycling of the entire treated water from STP for different purposes.

ENVIRONMENT MANAGEMENT PLAN 88 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

• Installation of dual plumbing system • Installation of water efficient fixtures • Rain water tank proposed for storage of rain water and for its subsequent use so as to conserve fresh water consumption. NOISE & VIBRATION ENVIRONMENT :- Construction Phase: - Noise: - • All construction works and traffic movement only in day time. • All construction equipments and machinery in good working condition. • All construction workers are provided with PPE like ear plugs etc. • Rotation of duty who are involved in noise intense working area • Use of DG Sets with appropriate acoustic enclosures • All vehicles used in construction phase will be ensured with PUC certificate. • Wind breakers / acoustic enclosures made of gunny bags filled with sand or earth and stacked up to a height of about 7-8 ft. at the marble cutting & grinding area. This arrangement works as wind breaker & as a noise barrier. Vibration: - • For construction of new buildings, it is proposed to provide Stitched Raft Foundation to avoid conventional methods. • Anti vibration pads for DG Sets. Operation Phase: - Noise: - • Separate entry/exit arrangement for the vehicles & sufficient internal road width • The cooling tower will be isolated and to be kept in an enclosure so as to reduce the propogation of noise. • Use of DG Sets with appropriate acoustic enclosures • Green area development all along the project boundary and also within the site. Vibration: - • Anti vibration pads for DG Sets LAND ENVIRONMENT :- Construction Phase :-

ENVIRONMENT MANAGEMENT PLAN 89 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

• Construction and Demolition Waste, Rule, 2016 will be followed for handling of solid waste from the site during construction phase. • Solid waste like packaging material, hazardous waste and other solid waste generation from the project during construction phase. • The non-biodegradable waste and other packaging material will be sold to the vendors. Disposal of biodegradable Municipal Solid Waste through authorized agencies of Thiruvananthapuram Municipal Corporation. Operation phase: Domestic Solid Waste: - • The proposed project will generate about 800 Kg/day of solid waste. • The Solid Waste Management Rules, 2016 will be followed in the Solid Waste management at the site. • Collection & segregation within the site (bio-degradable waste (in green bins), non-biodegradable waste (in blue bins) and domestic hazardous waste (in yellow bins). • The recyclable waste like packaging material, paper etc. would be sold through vendors (500 kg/day). The Bio-degradable waste would be disposed through the Organic Waste Converter (OWC) to be installed within the site (300 kg/day). • The manure generated will be utilized for green area development within the premises. • The domestic hazardous waste which includes discarded painted drums, pesticide cans, LED bulbs, tube lights, expired medicines, broken mercury thermometers, used batteries, used needles and syringes and contaminated gauge etc. generated at the site will be collected in yellow bins and to be handed over to authorized waste pickers or waste collectors. e-WASTE :- • Discarded computer parts, monitor, key boards etc. constitutes e-waste and this waste will be stored in an earmarked area. • E-waste will be generated after 4-5 years latency period. Separate earmarked space will be provided for e-waste storage. • E-waste will be disposed as per E Waste (Management & Handling) Rules. HAZARDOUS WASTE :-

ENVIRONMENT MANAGEMENT PLAN 90 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

• As per Hazardous Waste (Management & Handling Rules), 2016, the hazardous waste i.e., the used oil from D.G. sets, discarded oil filters and discarded batteries and stored separately and will be disposed to CPCB / SPCB authorized vendors only. • M/s Perfect Alloys, Chengannur, M/s Peejay Enterprises, Thiruvalla, M/s Excel Petrochemicals, Kochi and M/s Cee Jee Lubricants, Aluva are the approved recyclers for discarded batteries & used oil located in Kerala. SOCIO-ECONOMIC ENVIRONMENT :- • The project would not cause any adverse effects on local communities, disturbance to sacred sites or other cultural values. • The proposed project is an IT/ITES office building project and thereby the social, economic and health index of the people around the project site will definitely improve. • Also there will be various ancillary activities like convenience shops, offices, ATM and transports facilities etc. attached to the project which will benefit the local people and change their living condition. • It is predicted that socio-economic impact due to this project will positively increase the chance of more employment opportunities for local inhabitants. • There are no resettlement and rehabilitation (R&R) issues involved in this project. • The project infrastructures will be of use to people of the area. The office facility in the area will definitely increase the health index due to the proposed activity. • The municipal solid waste, hazardous waste & e-waste will be handled and disposed as per norms. Thus the proposed project is not likely to affect the environment or adjacent ecosystem adversely and will ensure a sustainable development. ECOLOGICAL ENVIRONMENT :- • As part of the eco restoration, large no. of tree saplings of native species would be planted as per MoEF&CC norms. Due to the eco restoration, the impact to floral and faunal ecology will be short term and the ecology will be enhanced. • The landscaping will include fruit trees and shade trees to attract birds.

ENVIRONMENT MANAGEMENT PLAN 91 Proposed IT/ITES office building project of M/s Brigade Enterprises Ltd.

• The entire project area is devoid of any rare / endangered / threatened flora and fauna. • The suggested list of trees which included in green belt development plan are provided below: - Sr. Botanical name Vernacular / Family Type No. English Name 1. Cassia fistula Konna Fabaceae Flowering tree (Golden Shower) 2. Citrus limon Cherunaregam Rutaceae Domestic use 3. Moringa Muringa Moringaceae Domestic use pterygosperma (Drumstick tree) and flowering 4. Psidium guajava Pera (Guava) Myrtaceae Fruit tree 5. Garcinia Kodampulli Clusiaeae Domestic use cambogia (Malabar Gamboge) 6. Azadirachta Ariyaveppu (Neem) Meliceae Medicinal Tree indica 7. Mangifera Indica Mavu (Mango tree) Anardiaceae Fruit tree 8. Mimusops elengi Elangi tree Sapotaceae Medicinal & (Spanish cherry) flowering tree 9. Plumeria obtusa White Champa Apocynaceae Flowering (Vellachampakam)

***********************

Annexure No. 2 124 ACTIVITY WISE POPULATION & DAILY WATER CONSUMPTION DETAILS

Non-flushing Total Flushing Req. FAR Area Req. Req. Activity Population (in sq.m.) ( In KLD )

1814 Persons 1814 x 20 Ltr. 1814 x 25 Ltr. IT/ITES office 18,140 ( @ 10 sq.m. per 81.63 = 36.28 = 45.35 person of FAR area )

181 Persons Housekeeping 181 x 20 Ltr. 181 x 25 Ltr. -- ( 10% of I.T. staff of 8.15 staff = 3.62 = 4.53 1814 Persons ) 1995 Persons 39.9 49.88 89.78 TOTAL Say 2000 persons Say 40 Say 50 Say 90 DAILY WATER CONSUMPTION BALANCE CHART Annexure No. 3 Total daily water consumption = 123KL (fresh 50KL + 73 KL recycled) 125 Total daily domestic water consumption = 90 KL (40 KL Non-flushing + 50KL Flushing) Total daily sewage generation = 81 KL (90% of 90 KL) Total daily treated sewage available = 73 KL (90% of 81 KL) Total daily water saving = 73 KL (about 59%)

Fresh Water Req. Domestic Water Requirement 40 KL Stored Rain water / Wastewater generation @ KWA / Technopark = 50 KL ( Non - Flushing ), 40 KL 90% of Domestic water of ( First day Req. = 123 KL STP with Tertiary [Fresh 50 KL + Recycled 73 KL] 90 KL i.e. Treatment 81 KL ( 85 KL Capacity)

Domestic Water Requirement Treated 50 KL Wastewater ( Flushing), 50 KL generation @ 10 KL 90 % of total wastewater generated, i.e., 73 KL

Horticulture Water Requirement 8 KL

8 KL

1st day req.

Re-use Line Make-up water for cooling towers 15 KL attached with HVAC plant 10 KL+ 15 KL = 25 KL Recurrent Water Demand 1

Annexure No. 5 127 M/s Brigade Enterprises Ltd.

At Technopark Campus, Pangappara Village, Thiruvananthapuram Corporation, Thiruvananthapuram Taluk & District, Kerala.

LAND USE MAP OF 10 KM

Colour Coding Land Use % Area in sq. km Barran Rocky area 0.03 0.0942 Cropland 0.48 1.5072 Mining 0.01 0.0314 Plantation 68.58 215.3412 Reservoir/Lakes/Ponds 0.01 0.0314 River / Stream / Canals 2.15 6.751 Rural Area 8.2 25.748 Sandy land 4.29 13.4706 Scrub land 0.49 1.5386 Urban 15.74 49.49 30’30’ N N 0 08

Scale

Source: Extracted from Bhuvan, Indian Geo-Platform of ISRO

76 0 50’ E ISRO, Govt. of India VICINITY MAP OF THE SITE & SURROUNDINGS Annexure No. 6 128

Project site Annexure No. 7 SATELLITE MAP OF THE SITE & SURROUNDINGS 129

Annexure No. 9 131 SITE PHOTOGRAPH OF THE PROJECT SITE OF M/S BRIGADE ENTERPRISES LTD.

1

Annexure No. 11 134

BIODIVERSITY ASSESSMENT REPORT

OF

M/s BRIGADE ENTERPRISES LTD.,

PROPOSED IT/ITES OFFICE BUILDING PROJECT AT TECHNOPARK CAMPUS, PANGAPARA VILLAGE, TRIVANDRUM, KERALA

135

GENERAL VIEWS OF THE SITE

136

137

FINDINGS – FLORA

Analysis of the flora revealed that there are 60 plant species falling under 35 plant families. Angiosperms forms 55 species with 16 species of trees including saplings, 10 species of shrubs, 26 species of herbs and 13 species of climbers. There are five Pteridophytes (ferns) falling under Adiantaceae,Selaginellaceae and Pteridaceae family. The most dominant plant family is Leguminosae with 6 plant species followed by Euphorbiaceae, Malvaceaeand Compositae.

The Site has 60 species of plants. It consists of:

Trees : 12 species Shrubs : 10 species Herbs : 16 species Climbers : 13 species Tree saplings : 12 species Ferns : 5 species LIST OF TREES

Common SN Botanical Name Family Habitat Distribution Nos Status Name Evergreen Bridelia retusa Euphorbiace to 1 Mulluvenga Indo-Malaya 1 (L.) Spreng. ae Deciduous Forests Thespesia Poovarasu 2 Malvaceae Cultivated Pantropical 1 populnea Native of Planted as Madagascar;no Delonix regia Caesalpiniac gardens 3 Gulmohar w cultivated 21 (Hook.) Raf. eae and along throughout the roadsides tropics Moist and dry Morinda coreia deciduous 4 Manjanathi Rubiaceae 1 Buch.-Ham. forests, also in the plains Malesia to North Australia Terminalia Combretacea Plains, and Polynesia, 5 Badam 1 catappa L. e Cultivated Commonly planted in the tropics Moist Erumanakku/ deciduous Parakam/ and semi- Indo-Malesia to 6 Ficus hispida L.f. Moraceae 1 Thonditheraka evergreen Australia m forests, also in the

138

plains

Cultivated Coccos nucifera Thengu / 7 Arecaceae Cultivated throughout the 2 L. Coconut tropics Moist deciduous Tectona grandis forests, South and 8 Thekku Verbenaceae 5 L.f. also raised South East Asia in plantations Moist deciduous Macaranga and Euphorbiace India, 9 peltata (Roxb.) Vatta secondary 9 ae and Andamans Müll.Arg. forests, also in the plains Dry and moist Tropical Africa, 10 Trema orientalis deciduous Pottaama Ulmaceae Asia and 5 (L. ) Bl. forests, Australia also in the plains Acacia Native of 11 auriculiformis Acacia Leguminosae Cultivated Tropical 27 Benth. Australia Planted as Peltophorum Native of 12 Copperpod Fabaceae avenue 11 pterocarpum Australia tree.

LIST OF TREE SAPLINGS

Botanical Common SN Family Habitat Distribution Status Name Name Evergreen and semi- Mangifera evergreen 1 Mavu Anacardiaceae Indo-Malaysia indica L. forests and also widely cultivated Dry and Trema moist Tropical Africa, 2 orientalis ( L. ) Pottaama Ulmaceae deciduous Asia and Bl. forests, also Australia in the plains Acacia 3 Mangium Leguminosae Cultivated Australia mangium Wild Native of Planted as Madagascar;now Delonix regia gardens and 4 Gulmohar Caesalpiniaceae cultivated (Hook.) Raf. along throughout the roadsides tropics

139

Moist deciduous Erumanakku/ Ficus hispida and semi- Indo-Malesia to 5 Parakam/ Moraceae L.f. evergreen Australia Thonditherakam forests, also in the plains Peltophorum Planted as Native of 6 Copperpod Fabaceae pterocarpum avenue tree. Australia Moist deciduous Tectona South and South 7 Thekku Verbenaceae forests, also grandis L.f. East Asia raised in plantations Malesia to North Australia and Terminalia Plains, Polynesia, 8 Badam Combretaceae catappa L. Cultivated Commonly planted in the tropics Acacia Native of 9 auriculiformis Acacia Leguminosae Cultivated Tropical Benth. Australia Moist deciduous Alstonia South and South 10 Ezhilampala/ forests and scholaris (L.) Apocynaceae East Asia to Devil Tree sacred R. Br. Australia groves, also in the plains Moist Macaranga deciduous peltata and India, Sri Lanka 11 Vatta Euphorbiaceae (Roxb.) secondary and Andamans Müll.Arg. forests, also in the plains

Carica Native of 12 Papaya Caricaceae Cultivated Exotic papaya L. Tropical America

LIST OF SHRUBS

Botanical SN Common Name Family Habitat Distribution Status Name

Moist Urena lobata deciduous 1 Uram Malvaceae Pantropical L. forests and in the plains

Degraded Clerodendrum forest areas 2 infortunatum Perivelam Verbenaceae Indo-Malesia Exotic and also in L. the plains

140

Clerodendrum Krishnakireeda Native of Cultivated/Nat 3 paniculatum m,/Hanumankir Lamiaceae Malaysian uralized L. eedam Region

Native of Chromolaena A weed in all America; Exotic/ odorata (L.) Communist- 4 Compositae terrestrial naturalised Invasive R.M.King & pacha habitats in Tropical Species H.Rob. Asia

Wastelands, Sida also in 5 Kurunthotti Malvaceae Pantropical rhombifolia L. degraded forest areas

Evergreen Osbeckia forests and Peninsular aspera (L.) Melastomatacea 6 Kaattukkadalai grasslands, India and Sri Blume var. e also in the Lanka aspera. plains

Native of Most tropical aggresive America, weed of Lantana widely Exotic/Invasiv 7 Kongini Verbenaceae disturbed camara L. naturalised e Species ground from in tropics plains to the and hills. subtropics.

It grows along Tropical and Ziziphus roadside subtropical 8 Thudaly Rhamnaceae oenoplia forests and Asia and thickets Australasia.

Dry and moist Hibiscus deciduous 9 hispidissimus Matthippuli Malvaceae Paleotropics forests, also Griff. in the plains Native of Tropical Ricinus Aavannakku/ Cultivated, Africa; now 10 Euphorbiaceae Exotic communis L. Chittavanakku also runs wild cultivated throughout tropics

141

LIST OF HERBS

Botanical Common SN Family Habitat Distribution Status Name Name Grasslands, Cyanotis Crested Cat Commelinaceae degraded forest 1 Paleotropics cristata Ears areas and wastelands Semi-evergreen and Indo-Malesia Desmodium Adakkapaanal, moist deciduous to Pacific 2 Fabaceae triquetrum Adakkachokki forests, also in the Islands and plains China Dry and moist Axonopus Kaalappullu/ deciduous forests, Tropics and 3 compressus Poaceae Carpet Grass waste lands and subtropics (Sw.) P.Beauv. paddy fields Degraded forest Euphorbia hirta areas and forest Nilappaala Euphorbiaceae Pantropical. 4 L. plantations, also in the plains

Degraded moist Phyllanthus Keezharnelli/P deciduous, forest amarus Schum. Phyllanthaceae Tropics 5 hyllanthus plantations and also & Thonn. in plains

Native of Tropical Scoparia 6 Kallurukki Plantaginaceae Wasteplaces America; Exotic dulcis L. now Pantropical Dry and moist Sida acuta 7 Kurunthotti Malvaceae deciduous forests, Pantropical Burm.f. also in the plains

Cleome 8 rutidosperma Neelavela Cleomaceae In coastal areas Pantropical DC. Native of Tropical America; Deciduous forests, Tridax now Odiyancheera Asteraceae also waste lands in Exotic 9 procumbens L. widespread the plains throughout tropics and subtropics

142

Cultivated as Central Asia Pennisetum 10 Poaceae fodder grass, often and North orientale Rich. found running wild Africa Vernonia Deciduous forests, cinerea (L.) Puvankurunal Compositae Pantropics 11 also in the plains Less.

Most abundant weed of disturbed Ageratum Invasive 12 Appa Compositae ground and fallows, Pantropical conyzoides L. Species damp places and forest undergrowth. Native of Peperomia Degraded forest Tropical Mashitandu 13 pellucida (L.) Piperaceae areas and America; Exotic Chedi Kunth. wastelands now Pantropical Common on moist and ungrazed Native of places. Near South Mimosa 14 Thottavadi Leguminosae riverbanks, bunds America, pudica L. of arable lands, now fallow lands and pantropical. water courses. Tropical America, Ananas widely comosus (L.) Kaithachakka Bromeliaceae Cultivated 15 cultivated in Merr. the Paleotropics

Colocasia Waterlogged esculenta (L.) Chembu Araceae ditches and Pantropical 16 Schott streamside

LIST OF CLIMBERS

SN Botanical Name Common Name Family Habitat Distribution Status

Semi- evergreen Cyclea peltata and India and Sri 1 (Lam.) Hook. f. & Padathali Menispermaceae evergreen Lanka Thoms. forests, also in the plains Degraded Merremia vitifolia Manja kolambi forest areas Indo-China Invasive 2 Convolvulaceae (Burm. f.) Hallier f. valli and also in and China species the plains

143

Evergreen forests, India to Pothos scandens waste 3 Paruvakodi Araceae Malesia and L. places and Madagascar sacred groves Common along foothills, lower Tropical and slopes, Mikania micrantha subtropical 4 Vayara Compositae scrub Invasive Kunth regions of the jungles even world. in poor soils, on bare exposed slopes. Moist and Ichnocarpus dry Indo-Malesia 5 frutescens ( L. ) Palvalli Apocynaceae deciduous and Australia R.Br. forests, also in the plains Mukia Deciduous maderaspatana Kasappuchedi Cucurbitaceae forests, also Paleotropics 6 (L.) M.Roem. in the plains

Native of Centrosema Kattupayar/ 7 Leguminosae Cultivated Tropical Exotic pubescens Benth. Butterfly Pea America Valli Tragia involucrata India and Sri 8 choriyanam/Kodit Euphorbiaceae Wastelands L. Lanka hoova Found in foothill scrub India, Sri Dendrophthoe jungle s and Lanka, 9 falcata ( L.f. ) Ittikkanni Loranthaceae deciduous Thailand, Ettingsh. forests from Indo-China plains to and Australia. 1000m. Weed in Native of Mimosa diplotricha degraded Tropical Exotic/Invasive 10 Aanathottavadi Leguminosae var. diplotricha forests, also America; a species in the plains weed in India Along banks of back Derris trifoliata 11 Ponumvalli Leguminosae waters and Paleotropics Lour. mangrove forests Native in Epipremnum Mo'orea, 12 Money plant Araceae aureum French Polynesia Very Native of Passiflora foetid a 13 Poodapazham Passifloraceae common tropical Exotic L. along America, now

144

roadsides, widely thickets and naturalized water the tropics courses from plains

LIST OF FERNS

Sl. Common Botanical Name Family Habitat Distribution No. Name Selaginella Terrestrial in shaded 1 Selaginellaceae delicatula areas Widely cultivated Adiantum latifolium Native to tropical 2 Adiantaceae Disturbed open areas. Lam. America Pityrogramma Common on open American origin,now calomelanos (L.) Silver fern Adiantaceae ground in fairly widely distributed in 3 Link exposed places pan-tropics

Growing in moist Adiantum areas of all vegetation 4 Pteridaceae Tropics and sub tropics philippense types from coastal plains to forests. Semi evergreen and Adiantum Indo-Pacific and 5 Pteridaceae moist caudatum African deciduous forests

145

FAUNAL DIVERSITY

The faunal species recorded here is based on the direct/indirect sightings form the proposed study site.

Methodology

Birds, Butterflies, Dragon Flies: Line Transect & Point count method

Mammals: Line Transect method, Consultation with local people

Amphibians: Transect and Patch Sampling

Spiders: Searching and Direct Observations

Regarding the conservation status of the fauna, none of the animal species identified from the site belonged to the threatened categories identified by the International Union for Conservation of the Nature and Natural Resources (IUCN). Most of them are common and widely distributed and the range of occurrence extended to wide geographical area. The following lists of faunal elements were observed from the site:

Birds : 25 species Mammals : 11 species Butterflies : 21 species Odonates : 13 species Amphibians : 9 species Reptiles : 14 species Spiders : 12 species Ants : 7 species List of Mammals (In and around the project site) IW(P)A Sl. No. Common Name Scientific Name IUCN Status (Schedule) Three Striped Palm 1 Funambulus palmarum Least Concern - Squirrel 2 Common House Rat Rattus rattus Least Concern IV Common Indian Field 3 Mus booduga Least Concern IV Mouse Greater Short-nosed 4 Cynopterus sphinx Least Concern IV Fruit Bat 5 House Shrew Suncus murinus Least Concern -

6 Indian false vampire Megaderma lyra Least Concern IV

7 Lesser Bandicoot Rat Bandicota ,bengalensis Least Concern IV

8 House Mouse Mus musculus Least Concern IV

9 Palm Civet/Toddy Cat Paradoxurus hermaphroditus Least Concern II 10 Indian Flying Fox Pteropus giganteus Least Concern IV

11 Pig Rat Bandicota indica Least Concern IV * IW(P)A -The Indian Wildlife (Protection) Act, 1972.

146

List of Reptiles Sl. No. Scientific Name Common Name IUCN Status 1 Ptyas mucosa Oriental Rat Snake Least Concern 2 Grypotyphlops acutus Brahminy blind snake Not evaluated 3 Ahaetulla nasuta Common Vine Snake Not evaluated 4 Hemidactylus leschenaultii Bark Gecko Least Concern 5 Dendrelaphis tristis Common Indian Bronze-back Least Concern 6 Vipera russelli Russell's viper Not evaluated 7 Bungarus caeruleus Common krait Not evaluated 8 Hemidactylus frenatus Asian House Gecko Least Concern 9 Hemidactylus maculatus Spotted House Gecko Least Concern 10 Naja naja Asian cobra Least Concern 11 Lycodon aulicus Common Wolf Snake Not evaluated 12 Varanus bengalensis Common Indian monitor Least Concern 13 Eutropis carinata Common Keeled Skink Least Concern 14 Calotes versicolor Oriental Garden Lizard Least Concern

List of Birds Sl Scientific Name Common Name Family IUCN Status Remarks No. 1 Copsychus saularis Oriental magpie robin Musciccapidae Least Concern 2 Corvus splendens House Crow Corvidae Least Concern 3 Columba livia Blue Rock Pigeon Pteroclididae Least Concern 4 Megalaima viridis White cheeked barbet Capitonidae Least Concern 5 Dicrurus macrocercus Black Drongo Dicruridae Least Concern 6 Dendrocitta vagabunda Indian Treepie Corvidae Least Concern 7 Centropus sinensis Greater coucal Cuculidae Least Concern 8 Dicaeum agile Pale billed Flowerpecker. Dicaeidae Least Concern 9 Dinopium javanense Common flameback Picidae Least Concern 10 Pycnonotus jocosus Red Whiskered Bulbul Pycnonotidae Least Concern 11 Glaucidium radiatum Jungle Owlet Strigidae Least Concern 12 Psittacula krameri Rose ringed parakeet Psittacidae Least Concern 13 Eudynamys scolopacea Asian Koel Cuculidae Least Concern 14 Acridotheres tristis Common Myna Sturnidae Least Concern 15 Dinopium benghalense Black-rumped Flameback Picidae Least Concern 16 Nectarinia zeylonica Purple-rumped Sunbird Nectariniidae Least Concern 17 Haliastur indus Brahminy kite Accipitridae Least Concern 18 Nectarinia lotenia Loten’s Sunbird Nectariniidae Least Concern 19 Dicrurus paradiseus Racket tailed drongo Dicruridae Least Concern

147

20 Turdoides striatus Jungle Babbler Musciccapidae Least Concern 21 Bubulcus ibis Cattle Egret Ardeidae Least Concern 22 Hierococcyx varius Common Hawk Cuckoo Cuculidae Least Concern 23 Oriolus xanthornus Black headed oriole Oriolidae Least Concern 24 Egretta garzetta Little Egret Ardeidae Least Concern 25 Loriculus vernalis Indian Hanging Parrot Psittacidae Least Concern

List of Amphibians Sl. No. Scientific Name Common Name IUCN Status

1 Polypedates leucomystax Common Tree Frog Least Concern 2 Pseudophilatus kani Kani Bush Frog Least Concern 3 Duttaphrynus scaber Ferguson’s Toad Least Concern 4 Duttaphrynus melanostictus Indian common toad Least Concern 5 Hoplobatrachus tigerinus Indian bullfrog Least Concern 6 Sphaerotheca breviceps Indian Burrowing Frog Least Concern 7 Fejervarya limnocharis Cricket Frog Least Concern 8 Euphlyctis cyanophlyctis Indian skipper frog Least Concern 9 Euphlyctis hexadactylus Green Pond Frog Least Concern

List of Odonates Sl. No. Scientific Name Common Name 1 Rhyothemis vareiegata Common Picture Wing 2 Pantala flavescens Wandering Glider 3 Lathrecista asiatica Asiatic Bloodtail 4 Aethriamanta brevipennis Scarlet Marsh Hawk 5 Agriocnemis pygmaea Pygmy Dartlet 6 Orthetrum sabina Green Marsh Hawk 7 Urothemis signata Greater Crimson Glider 8 Pseudagrion microcephalum Blue Grass Dart 9 Ceriagrion cerinorubellum Orange-Tailed Marsh Dart 10 Acisoma panorpoides Asian Pintail 11 Ictinogomphus rapax Common Clubtail 12 Diplacodes trivialis Ground Skimmer 13 Potamarcha congener Yellow-Tailed Ashy Skimmer

148

List of Butterflies

Sl. No. Common Name Scientific Name Status

Papilionidae 1 Common Mormon Papilio polytes Linnaeus 2 Common Rose Pachliopta aristolochiae Fabricius 3 Crimson Rose Pachliopta hector Linnaeus 4 Southern Birdwing Troides minos Cramer Endemic to W.Ghats 5 Blue Mormon Papilio polymnestor Pieridae 6 Common Jezebel Delias eucharis Drury 7 Common Grass Yellow Eurema hecabe Linnaeus 8 Common Emigrant. Catopsilia pomona Fabricius Nymphalidae 9 Chocolate Pansy Junonia iphita Cramer 10 Common Four-ring Ypthima huebneri Kirby 11 Common Crow Euploea core Stoll 12 Common Five-ring Ypthima baldusFabricius 13 Common Palmfly Elymnias hypermnestra Linnaeus 14 Common Sailer Neptis hylas Linnaeus 15 Common Evening Brown. Melanitis leda Linnaeus 16 Clipper Parthenos sylvia Cramer Lycanidae 17 Common Pierrot Castalius rosimon Fabricius 18 Common Line-blue Prosotas nora C. Felder 19 Lesser Grass Blue Zizina otis Hesperidae 20 Pygmy Grass Hopper Aeromachus pygmaeus Fabricius 21 Straight Swift Parnara bada

List of Millipedes and Centipedes Sl. No. Scientific Name Common Name IUCN Status 1 Leptogoniulus sorornus Least Concern 2 Trigoniulus corallinus Rusty millipede Least Concern 3 Anoplodesmus saussurii Least Concern 4 Scolopendra morsitans -

149

List of Ants Sl. No. Common Name Scientific Name 1 Giant Honey Ant Camponotus irritans 2 Weaver Ant Oecophylla smaragdina 3 Miniscule House Ant Tetramorium smithi 4 Common Red Fire Ant Solenopsis geminata 5 Golden Backed Ant Camponotus sericeus 6 Black Crazy Ant Paratrechina longicornis 7 Yellow Crazy Ant Anoplolepis gracilipes

List of Spiders Sl. No. Family Species Name 1 Hersilidae Hersilla savigngi 2 Araneidae Eriovixia laglaisei 3 Pisauridae Pardosa psedoannulata 4 Salticidae Plexippus petersi 5 Oxyopidae Oxyopes biramanicus 6 Salticidae Plexippus paykulli 7 Lycosidae Hippasa agelenoides 8 Sparassidae Hetropoda venatoria 9 Salticidae Telamonia dimidiate 10 Clubionidae Clubiona drassodes 11 Pholcidae Crossopriza lyoni 12 Araneidae Argiope pulchella

Recommendations The following recommendations were made for the sustainable development of the project so as to protect the biodiversity of the area. 1. The landscaping will include fruit trees and shade trees to attract birds. As much as possible, native plants will be used for landscaping. 2. A bird bath will be provided in the garden which in turn helps the birds to get water during summer season. 3. Renewable sources of power like solar power should be installed and all the street lights should be powered by solar. 4. Proper waste management will be practiced with source segregation (colour coded bins should be used) and recycling of waste.

****************************

Annexure No. 15 154

SOCIO-ECONOMIC STUDY REPORT

&

CORPORATE ENVIRONMENT RESPONSIBILITY (CER)

OF

M/s BRIGADE ENTERPRISES LTD.

PROPOSED IT/ITES BUILDING PROJECT AT TECHNOPARK PHASE-1 CAMPUS, PANGAPPARA VILLAGE, THIRUVANANTHAPURAM TALUK & DISTRICT, KERALA.

155

INTRODUCTION To gather accurate information and identify the needs of the nearby community to the project site, a community need assessment study was carried out by Socio – Economic Expert, accredited by NABET in Trivandrum Corporation. The main purpose of the study was to assist the project proponent for taking up community welfare activities under their Corporate Environmental Responsibility (CER) as per OM dt. 01-05-2018 issued by MoEF&CC. Approach adopted To conduct the study, primary and secondary data were used. Primary Data: Stake holder interviews, unstructured interview, field observation, and telephonic survey. Secondary data: Yearly Project Document and Development Charter of LSG

TECHNOPARK In March 1990, the Government of Kerala conceptualised Technopark as a facility to foster the development of high-technology industries in the state. Technopark was set up under the auspices of Electronics Technology Park, Kerala—an autonomous body under the Department of Information Technology of the government of Kerala. Technopark is owned and administered by the Government of Kerala and is headed by a chief executive officer. In addition to this, it has a Governing Council and a Project Implementation Board, both of which include top officials of the government. [5] Administrative offices, including that of the CEO, are housed in the Park Centre building. Technopark also hosts a Technology Business Incubation Cell under Kerala Startup Mission. Technopark houses domestic firms, joint ventures, and subsidiaries of foreign companies engaged in a wide variety of activities, which include embedded software development, smart card technology, enterprise resource planning (ERP), process control software design, engineering and computer-aided design software development, IT Enabled Services (ITES), process re-engineering, animation, and e-business. The project falls in Trivandrum Corporation.

Thiruvannathapuram Corporation Thiruvananthapuram is known as the city of temples, Museums, Institutions and land of Art and Culture. The Thiruvananthapuram Municipality came into existence in 1920. After two decades, during the reign of Sere Chithira Thirunal, Thiruvananthapuram municipality was converted into Corporation on 30 th October 1940. The city being the capital is the center spot for the political activities of the State. This city is still adorned by the elegant structures and

156

palaces which were established as a result of the dedication of several great rulers who wished the well being of the people and valued arts. Corporation at a glance Name of the Corporation Thiruvananthapuram Corporation Geographical area 214.86Sq.Km Total ward 100 Taluk Thiruvananthpuram and Neyattinkara Villages Total 23 villages District Thiruvananthapuram

Demography of Trivandrum Corporation Total Population 9,57,730 Total Male Population 4,67,739 Total Female Population 4,89,991 Density of Population 4,454Sq,Km Sex ratio 1040:1000 Literacy 84.13 (Source: website Thiruvananthapuram Corporation)

To know social status of community near to the project site, the survey report of ICDS – urban No. 3 was collected as secondary data. Even though eighteen divisions of Thiruvananthapuram Corporation is coming under ICDS urban No. 3, collected the details of three divisions. The population details of Karikkakam division, part of Annamugham and part of Vettukad divisions are provided below .

Demography Total population – Age wise distribution 0-6 7-10 11-19 20-45 46–60 61-80 Above 80 Total Male 956 915 1730 5279 3272 1637 167 13956 Female 941 881 1649 5258 3395 1724 235 14083 Total 1897 1796 3379 19537 6667 3361 402 28039

157

6000 5279 5258

5000

4000 3272 3395

3000 Male 1730 1649 1637 1724 2000 Female 956 941 915 881 1000 167 235

0 (0 -6) (7 -10) (11 -19) (20 -45) (46 -60) (61 -80) (Above 80)

SC Population - Age wise distribution 0-6 7-10 11 -19 20 -45 46 –60 61 -80 Above 80 Total Male 264 219 320 1115 745 264 37 2964 Female 241 177 358 1113 722 336 53 3020 Total 505 396 678 2228 1467 600 90 5984

1113 1200 1115

1000 745 800 722

600 Male 358 320 264 336 Female 400 264 241 219 177 200 37 53 0 (0-6) (7-10) (11 -19) (20-45) (46-60) (61-80) Above 80

Total population – Religion wise distribution Hindu Muslim Christian Total Male 10481 538 2937 14110 Female 10680 526 2904 13956 Total 21161 1064 5841 28066

158

5843 1064 Hindu Muslim 21161 Christian

ECONOMIC STATUS The most of the population in the Urban No. 3 of ICDS (18 divisions) are middle income families. They are working in the field of IT /ITES, various companies, Government departments, commercial establishments and business. A portion of popu lation is working in agriculture, construction and allied job openings. A portion of the population started small scale business in connection with rapid growth of developmental activities in the area. However 1143 families are living in rented houses, 271 8 families are belongs to Below Poverty Line, 1069 families are led by women. There are 464 people who need extra care and protection. The above mentioned data shows, the Local self Government needs to focus welfare activities for the uplift of down trod den families. The huge investments in the community help in developmental and welfare activities of the community. Type of houses Concrete Tile Sheet Hut Mixed Total Total 5373 914 574 74 161 7096

6000 5373

5000

4000

3000

2000 914 574 1000 74 161 0 Concrete Tile Sheet Hut Mixed

159

Basic Facilities of houses Toilet Water Well Public well pipe Public tap others Total 7086 816 25 5317 669 269

Details of people who needs special care I U M. Ill D A Vision Hearing C P Others Total Total 70 90 136 47 64 10 47 464 I U = Intellectually unable, M.Ill = Mentally ill, D A = Differently able, C P =Cerebral palsy

140

120

100

80 136 60 90 40 70 64 47 47 20 10 0 IU M. Ill D A Vision Hearing C P Others

Details of widows 15 -45 46 -60 Above 60 Total Total 227 524 654 1405

Widows

227

15-45 654 46 -50 Above 60 524

160

Details of people who get welfare pension Widow Old People Agri. Un wed Rtd. from Others Total age needs labours women Govt. job care Total 714 529 142 29 31 710 240

Important infrastructure near to the project site in 2 Km radius The proposed project is situated near to Akkulam toll plaza. The important infrastructure around the proposed project is listed below. Sl. No. Main Infrastructure Direction Distance 1. English Indian Clays. Ltd. West 450 Mtr 2. VSSC Project Complex North West 1.50 Km 3. Veli Railway station North West 2.00 Km 4. Kochu veli railway station South West 750 Mtr 5. Kims Hospital East 1.40 Km 6. Kendriya Vidyalaya East 1.60 Km 7. Lords Hospital South East 1.70 Km 8. Travancore Titanium Ltd. South West 1.80 Km 9. All Saints College South 2.00 Km 10. Mar Gregarious Memorial Public North west 1.40 Km School 11. HLL Life care, Factory North East 1.80 Km 12. NCESS North East 1.50 Km 13. Indian institute of diabetes North East 1.60 Km

161

CORPORATE ENVIRONMENT RESPONSIBILITY (CER) The OM No. 22-65/2017-IA.III states that every green field project having capital investment less than Rs. 100 crores need to allocate 2% of its project cost (capital investment) for activities under Corporate Environment Responsibility (CER). The instant project is a greenfield project and its capital investment is Rs. 52 Crores. Therefore, the project has to spend a maximum amount of Rs. 1.04 Crores under CER. In the OM, MoEF has suggested a wide range of areas, where the project proponent can implement their activities. The suggested areas by MoEf is given below. Suggested Sectors to Perform Activities under CER 1. Drinking water supply, 2. Sanitation, 3. Health, 4. Education, 5. Skill development, 6. Roads, 7. Cross drains, 8. Electrification including solar power, 9. Solid waste management facilities, 10. Scientific support and awareness to local farmers to increase yield of crop and fodder, 11. Rain water harvesting, 12. Soil moisture conservation works, 13. Avenue plantation, 14. Plantation in community areas etc.

The identified areas for execution of activities under CER are given below. 1. Conservation of Parvathy Puthanar 2. Well recharge 3. Solid waste management facility 4. Avenue plantation 5. Renewable energy

Identified Corporate Environment Responsibility The Socio - Economic expert conducted need assessment study in Kazhakoottam and identified Corporate Environment Responsibility (CER) for the project proponent. The identified CER activities are given below.

162

1. Conservation of Parvathy Puthanar The Parvathy Puthanar is flowing 2 Km away from the project site. This stream is one of the polluted streams in Trivandrum district. The project proponent can support the Corporation to execute the activities to clean and conserve Parvathy Puthanar. Particulars Total (in Rs.) Clean and conserve the stream 15,00,000 Total 15,00,000

2. Well Recharge To enhance the ground water table, the project can introduce well recharge (ground water recharging by rain water harvesting) programme in the region of water scarcity. the same will be done in consultation & association with LSG. Particulars Basis of Calculation Total (in Rs.)

Well recharge Rs. 15,000 x 100 wells 15,00,000 Total 15,00,000

3. Solid Waste Management Facility A. The project will implement a programme for Solid Waste Management programme by installing bio bins in association with Local Self Government. Particulars Total (in Rs.) Solid waste Management facility 20,00,000

Maintenance of waste management system 6,50,000

Total 26,50,000

4. Plantation of saplings A. The project can plant various saplings of trees and shrubs at road sides, banks of streams, Schools, Colleges, parking spaces, and areas suggested by Local Self Government and NHAI in association with Local Self government, NHAI, College, Schools, Kudumbasree, NGOs and various community based agencies Particulars Basis of Calculation Total (in Rs.) Saplings Rs.150 x 5,000 saplings 7,50,000 Maintenance Rs. 100 x 5,000 saplings 5,00,000 Total 12,50,000

163

5. Renewable Energy The project proponent can install solar panel of 3 Kw to 10 public institutions like schools, hospitals, offices Etc. Particulars Basis of Calculation Total (in Rs.) Solar system, 3 kw Rs.3,50,000 x 10 nos 35,00,000 Total 35,00,000

SUMMARY OF THE ABOVE ACTIVITIES

Sl. No. of Areas of Intervention Expenses (in Rs.) No Intervention 01 Conservation of Parvathy Puthanar 01 15,00,000 02 Well recharge 01 15,00,000 03 Solid Waste Management facility 01 26,50,000 04 Plantation of Saplings 01 12,50,000 05 Renewable Energy 01 35,00,000 Total 05 1,04,00,000

********************

Toposheet showing the Project site of Annexure No. 16 164 M/s Brigade Enterprises Ltd. at Pangappara Village, Thiruvananthapuram Taluk & Dist, Kerala

C 43W14 & 15 (Old no. 58D14 & 15) 30’ N 0 08

76 0 50’ E Annexure No. 17 165 SATELLITE MAP SHOWING 10 KM. RADIUS PROJECT SITE OF BRIGADE ENTERPRISES LTD.