STU/TRANS-PLAN/DOC-4 /WEF 01/04/10

COTETS

SO PARTICULARS PAGE O.

1 INTRODUCTION 1-74

2 MSETCL PLAN FOR THE YEAR 2010-11 TO 2014-15 75-173

i) Evacuation Schemes 77-78

ii) Washi EHV Construction Cum O& M Zone 79-90

iii) Pune EHV Construction Cum O& M Zone 91-101

iv) Karad EHV Construction Cum O& M Zone 102-113

v) Nasik EHV Construction Cum O& M Zone 114-130

vi) Aurangabad EHV Construction Cum O& M Zone 131-148

vii) Amravati EHV Construction Cum O& M Zone 149-157

viii) Nagpur EHV Construction Cum O& M Zone 158-171

ix) Capacitor and Reactor requirement 172-173

3 R-INFRA PLAN FOR THE YEAR 2010-11 TO 2014-15 174-178

4 TPC PLAN FOR THE YEAR 2010-11 TO 2014-15 179-185

5 756 KV & 400 KV TRANSMISSION NETWORK OF 186-188 STATE INCLUDING INTERSTATE LINES

omenclatures for substation

Sr. Nomenclature used in Substations No. plan 1 400 kV Akola (existing) 400 kV Akola-I 2 765 kV Akola (proposed) 765 kV Akola-II 3 400 kV Koradi (existing) 400 kV Koradi-I 4 400 kV Koradi (proposed) 400 kV Koradi-II 5 765 kV Koradi (proposed) 765 kV Koradi-III 6 400 kV Lonikand (existing) 400 kV Lonikand-I 7 400 kV Lonikand (proposed) 400 kV Lonikand-II 8 400 kV Bhusawal (existing) 400 kV Bhusawal-I 9 400 kV Bhusawal (proposed) 400 kV Bhusawal-II 10 400 kV Karad (existing) 400 kV Karad-I 11 400 kV Karad (proposed at Malharpeth) 400 kV Karad-II (Malharpeth) 12 400 kV Padghe (existing) 400 kV Padghe-I 13 400 kV Padghe (proposed at Kudus) 400 kV Padghe-II (Kudus) 14 400 kV Dhule (existing) 400 kV Dhule-I 15 400 kV Dhule (proposed at Dondaicha) 400 kV Dhule-II (Dondaicha) 16 400 kV Aurangabad (existing at Waluj) 400 kV Aurangabad-I 400 kV Aurangabad 400 kV Aurangabad-II 17 (proposed at Pandhari Pimpalgaon) (Pandhari Pimpalgaon)

A-PDF Watermark DEMO: Purchase from www.A-PDF.com to remove the watermark

INTRODUCTION

1 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

‘‘We as a State Transmission Utility (STU) dedicate ourselves to plan, develop, operate and maintain the State Transmission System to facilitate transmission of electricity from its source to load centres in a secure, reliable and economic manner for the best services to the consumers.’’

‘‘We aim to provide an effective transmission services’’

Table – 1 - The network of Transmission System of MSETCL as on 31-03-2010

Voltage Level Trans. Capacity EHV Lines Ckt Sr. No. No. of EHV S/s (KV) (MVA) (KM)

1 500 2 3582 1504 2 400 21 13270 6562 3 220 149 31161 12357 4 132 246 19517 11063 5 110 33 2080 1691 6 100 35 2323 678 7 66 34 1139 3270 Total 520 73072 37125

Table – 1.1 - The network of Transmission System of TATA as on 31-03-2010

Sr Voltage Level No. of EHV S/S Trans Capacity EHV Lines Ckt No. (KV) (MVA) (KM)

1 220 7 3120 364.86 2 110 11 4272 713.06 Total 18 7392 1077.92

Table – 1.2 - The network of Transmission System of REL as on 31-03-2010

Sr Voltage Level Trans Capacity EHV Lines Ckt No. of EHV S/S No. (KV) (MVA) (KM)

1 220 3 1475 484.59 2 110 0 0 0 Total 3 1475 484.59

2 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table – 2 - Previous Power scenario in Maharashtra

Peak Peak Demand (MW) Availability Shortfall(-) Year (MW) /Surplus(+) State MSEDCL (MW) 2001-02 11895 10119 1776 10879 -1016 2002-03 13418 11425 1993 10997 -2421 2003-04 13692 11357 2335 11650 -2042 2004-05 14822 12749 2073 11777 -3045 2005-06 16049 14016 2033 11889 -4160 2006-07 17161 14825 2336 13027 -4134 2007-08 18390 15946 2444 12522 -5868 2008-09 18072 15630 2442 13189 -4883 2009-10 19120 16582 2538 14952 -4168

Table - 3 MSPGCL(Mahagenco) Generation Table – 3.1 - Available Generation by MSPGCL

Sr. Generating Station MW No. 1 Nasik ( 2x125MW+ 3x210MW ) 792

2 Koradi (4X105MW +2X210MW+1X200MW) 936

3 Khaperkheda (4X210MW ) 756

4 Parli (2X20MW+3X210MW+2X250) 1053

5 Paras ( 1X55 MW + 2X250MW) 500

6 Chandarpur (4X 210MW + 3X500MW) 2106

7 Bhusawal ( 1X55MW+2X210MW) 428

8 Uran ( 612 MW +240 MW (WHR )) 767

Koyna 9 440 (4X70MW+4X80MW+4X250MW+4X80MW+2X18MW)

10 Other Hydro Generations (388MW) As per Table 3.2 97

Total MAHAGENCO Generation 7875

3 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table- 3.2 - MSPGCL Installed Capacity of Other Hydro Generations

Sr. No. Power Stations Unit Capacity (MW)

1 Bhatghar(IP) 1x16 16 2 Bhatsa (DW) 1x15 15 3 Bhira Tail Race (PP) 2x40 80 4 Dhom (IP) 2x1 2 5 Dimbhe (IP) 1x5 5 6 Dhudhganga (IP) 2x12 24 7 Eldari (IP) 3x7.5 22.5 8 Kanher (IP) 1x4 4

9 Manikdoh (IP) 1x6 6

10 Paithan PSS (DW) 1x12 12 11 Panshet (DW) 1x8 8 12 Pawna (IP) 1x10 10 13 Radhanagari (IP) 4x1.2 4.8 14 Surya (DW & IP) 1x6 6 15 Terwanmedhe(IP) 1x0.2 0.2 16 Tillari (PP) 1x66 66 17 Ujani PSS (DW&IP) 1x12 12 18 Vaitrna (DW &PP) 1x60 60

19 Vaitarna Dam Toe (DW) 1x1.5 1.5

20 Varasgaon (DW) 1x8 8 21 Veer (IP) 2x4.5 9 22 Warna (IP) 2x8 16 TOTAL 388

4 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table – 3.3 – Proposed Year wise Generation addition (in MW Ex-Bus) by MSPGCL

MAHAGENCO Projects 2010-11 2011-12 2012-13 2013-14 2014-15 Uran Unit-9 (1x814) - - 789 - - Uran Unit-10 (1x406) - - 394 - - Bhusawal E Unit-4 (1 x 500) 450 - - - - Bhusawal E Unit -5 (1x500) - 450 - - - Khaparkheda Unit-5 (1x500) 450 - - - - Parli Rep. Unit-8 (1x250) - 189 - - - Bhusawal Unit 6 (1x660) - - - 400 - Chandrapur Unit -8 (1x500) - - 450 - - Chandrapur Unit -9 (1x500) - - 450 - - Koradi Rep. Unit 8 (1x660) - - - 216 - Koradi Unit 9 (1x660) - - - - 594 Koradi Unit 10 (1x660) - - - - 594 Total 900 639 2083 616 1188 Existing Generation 7875 8775 9414 11497 12113 Yearwise Generation 8775 9414 11497 12113 13301 Availability

Table – 4 STATE GOVERNMENT & INTER STATE GENERATION

Table – 4.1 Existing State Government & Inter state Generation as on 31-03-10

Existing(State Government, MAHADISCOM) Capacity (MW)

Ghatghar (2x125MW) 225 RGPPL 1862 Total 2087

5 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table – 4 .2 – Proposed Generation by State Government & MAHADISCOM

Proposed (State Govt., MAHADISCOM) 2010-11 2011-12 2012-13 2013-14 2014-15

LEPL (Lanco Energy Pvt. Ltd.) - - 1062 - - (500MW & 680MW) M/s Maharashtra Water Resourse Dept.Koyna 79 (2 x 80 MW) Total 0 79 1062 0 0 Existing Allocation 2087 2087 2166 3228 3228 Yearwise Allocation Availability 2087 2166 3228 3228 3228

Table- 5 Central Sector Power Allocation

Table – 5.1 Available Allocation of Power by Central Sector as on 31-03-10

Installed Available at Name of Generating Station Capacity MSETCL N/W

KSTPS (Korba) 2100 608 Vindhyachal STPS Stage -I 1260 412 Vindhyachal STPS Stage -II 1000 322 Vindhyachal STPS Stage -III 1000 268 KGPS (Kawas) 658 180 GGPP (Gandhar) 657 177 SIPAT Stage – II (2 x 500MW) 1000 268 KAPS (Kakrapar) 440 134 TAPS (Tarapur 3 & 4) 1080 391 TAPS (Tarapur 1 & 2) 324 161 SSP (Sardar Sarowar) 1450 354 NTPC ER to MSEDCL 4940 137 Total 15910 3412

6 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table – 5 .2 – Proposed Year wise Allocation of power by Central Sector

Name of Generating Station 2010-11 2011-12 2012-13 2013-14 2014-15

Sipat 170 - - - - Sipat - 170 - - - Mundra UMPP - 320 - - - Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat - - 170 - - Vindhyachal - - 300 - - Krishnapattanam UMPP - - - 400 - North Karnapura - - - 33 - Barh - - - 33 - Total Allocation 170 840 950 466 0

Existing Allocation 3412 3582 4422 5372 5838

Yearwise Allocation 3582 4422 5372 5838 5838 Availability

Table – 6 Proposed Year wise total generation available in Mumbai (TATA/REL) as on 31-03-10

Generation 2010-11 2011-12 2012-13 2013-14 2014-15 TPC - - - - - REL - - - - - (1924 + Existing Generation 459) = 2383 2383 2383 2383 Availability (TPC + REL) 2383

Table – 7 - Power scenario in Mumbai (TATA/REL)

Expected Demand in Peak Shortfall (-) Mumbai Generation capacity in Year / Surplus (+) TPC + Mumbai R-Infra Total (MW) BEST 2010-11 976 2154 3130 2383 -747 2011-12 1109 2233 3342 2383 -959 2012-13 1221 2350 3571 2383 -1188 2013-14 1343 2474 3817 2383 -1434 2014-15 1468 2706 4174 2383 -1791

* Shortfall of Mumbai would be met from the bilateral power purchase.

7 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table - 8 IPP Plants

Table- 8.1 Existing Generation from IPP/CPP/Biomass/Bagasse/Biogas based Plants

EX - Bus Sr. Location of the CAPACITY NAME OF APPLICANT Generation No. Plant APPLIED (MW) (MW)

M/s Indrajit Infrastructure Pvt.Ltd. Bhugaon 1 Modern Centre,'B' Wing, 2nd Floor, Sane 2 x 40 = 80 72 (Wardha-II) Guruji Marg, Mahalaxmi, Mumbai-400011.

2 M/s. Purty Sakhar Karkhana, Dist. Wardha. Wardha. 1 x 24 = 24 22

M/s Ind-barath Engineers (Maharashtra) Village Kharab 3 Ltd.Plot No.30-A,Road No.1, Film Khandgaon,,Dist. 20 18 Nagar,Jubillee Hills, Hyderabad-500 033. Nanded M/s Lokmangal Sugar Ethanol & Co- Generation Industries Ltd, Bhandarkavathe, Tal. 4 33/A, Sahyadri Nagar,Hotgi Road, Solapur - South Solapur, Dist. 1 X 15 = 15 13.5 413 003. Solapur.

M/s M/s Hotel Leelaventure Ltd, Village Khaparale,Tal. 5 The Leela Kempinski, 4.5 4.05 Sinnar dist Nasik. Sahar, Andheri (E), Mumbai 400 059.

M/s Hotel ITC the Maratha, Near Blue Dart Village Khaprale 6 Office,Sahar Airport Road, 6 5.4 (Sinnar),Dist. Nasik Mumabi -400 099.

M/s Renuka Sugars Ltd.at Deshbakta Ratnnappanna Kumbhar Panchaganga Ganga Nagar, 7 1 X 30 = 30 27 Sahakari Sakhar Karkhana, Ganga Nagar, Dist.Ichalkarangi Ichalkarangi. M/s Daund Sugar Ltd, Village Alegaon, Tal. 8 ICC Trade Tower, B-Wing 201,Senapati Bapat 18 16.2 Daund, Dist. Pune. Road, Pune-411 016. M/s Baramati Agro Ltd, At Pimpli, Tal. 9 Pimpli, Baramati, Dist. Pune, 22 19.8 Baramati, Dist. Pune. Maharashtra - 413 102. M/s Finolex Industries Ltd. At Ranpar-Golap,dist. 10 Project Office,26/27, Mumbai -Pune 22 19.8 Ratnagiri Road,Pimpri,Pune-411 018. M/s Kranti Sahakari Sakhar Kundal, Tal. Palus, 11 Karkhana,Kundal,Tal. Palus, Dist.sangli-416 6.65 (8.85) 6 Dist. Sangli. 309.

Total EX Bus Generation ( MW ) 224

8 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table – 8.2.1 Proposed Year wise Generation Addition by IPP/CPP/Biomass/Bagasse/ Biogas based Plants Capacity MW ( EX - BUS GENERATION ) SR. Location of NAME OF APPLICANT Applied NO. the Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s JSW Energy Ltd. Jindal Mansion, 4 X 300 = 1 Jaigad 1080 ------5A.Dr.G.Deshmukh Marg. 1200 Mumbai 400 026. M/s M/s Gupta Energy Pvt. Ltd.(Formerly Gupta Coal Usegaon, Fields and Washaries Ltd.) 2 X 60 = 2 Dist. 108 ------7th Floor,Shriram Towers, 120 Chandrapur Kingsway, Nagpur 440 001Tal. Ghugus, Dist.Chandrapur. M/s Nagpur Energy Near Infrastructure Ltd.(Formerly 250 + 250 Bhadravati,Di 3 Baidyanath Power &Mining), + 500 = -- -- 450 450 -- st. 5, Temple Road,Civil Lines, 1000 Chandrapur. Nagpur-440 001. M/s Patni Energy Ltd. 302-304, Regent Medhekar, 2 x 135 = 4 -- -- 243 -- -- Chembers,, Tal.Alibag. 270 Mumbai 400021. M/s Emco Energ y Ltd.Warora, Plot No.F-5, Road No.28, 2 x 135 = 5 Warora -- 243 ------wagle industrial Estate,Thane- 270 400 604. M/s Sun-Flag Iron and Steel At Warthi, 2 x 15 = 6 Co.Ltd. Bhandara Road, Dist. 27 ------30 Bhandara-441 905 Bhandara M/s Wardha Power Company Pvt.Ltd, 8-2- 2 x 135 = Warora,Dist. 7 293/82/A/431/A, Road No.22, 270 243 ------Chandrapur Jubilee Hills, Hyderabad - (Phase -I) 500033. M/s Ultra Tech Cement Ltd. Awapur, Tal. 8 Awapur Cement works, tal. Korpana,Dist. 12 10.8 ------Korpana, Dist. Chandrapur. Chandrapur. M/s Finolex Industries Ltd. At Ranpar- Project Office,26/27, Mumbai - 9 Golap,dist. 22 19.8 ------Pune Road,Pimpri,Pune-411 Ratnagiri 018. M/s Reliance Industries Ltd, Maker Chanbers IV,3rd 10 Nagothane 345 ------Floor,222,Nariman Point,Mumbai 400 021. M/s Ind-Barath Power At Village (Konkan) Ltd. Plot No.321, Br. 11 Aonda,Dist. 300 -- 270 ------Nath Pai Road,RamtirthNagar, Sawanwadi. Belgaum-590016.

9 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity MW ( EX - BUS GENERATION ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Wardha Power Company 2 x 135 = Pvt.Ltd, 8-2-293/82/A/431/A, Warora,Dist. 12 270 121.5 121.5 ------Road No.22, Jubilee Hills, Chandrapur (Phase -II) Hyderabad -500033. M/s Finolex Infrastructure Ltd. At Ranpar- 26-27,Mumbai -Pune Road, 13 Golap,dist. 1000 -- -- 450 450 -- Pimpri, Ratnagiri Pune-411 018 M/s Indiabulls Real Tech Limited. Indiabulls House, 448- 2 X 660 = 14 Sinnar -- -- 1188 -- -- 451, Udyog Vihar, Phase, 1320 Gurgaon -122 001. M/s Sophia Power Company Nandgaon 4 X 660 = 15 Limited.At Nandgaon pet Peth -- -- 1215 -- -- 2640 Ind.Area.Amravati Amravati M/s Abhijit MADC Nagpur At Gumgaon 4 X 50 = 16 Energy Pvt.Ltd.39, Ambazari MIHAN SEZ, 90 -- -- 90 -- 200 Layout, Nagpur-440 033. Dist. Nagpur M/s Maharashtra Vidyut Nigam Ltd. 7th Floor,Shriram Towers, MIDC Deoli. 17 10 9 ------Kingsway, S.V.Patel Marg, Dist. Wardha Sadar,Nagpur.Nagpur M/s Lloyds Metals & Engineers Ltd, Modern Mills Ghugus, 4 X30 = 18 Compound,101, Keshavrao Dist. 27 ------12 Khade Marg, Jacob Chandrapur. circle,Mumbai 400 011. M/s IDEAL Energy Projects Ltd, Near Bela, IRB Complex, 2nd Floor, 2 X 135 = 19 tal. Umred, -- 243 ------Chandivili Village, Andheri (E), 270 Dist.Nagpur Mumbai -400 072 M/s JS W Steel Ltd. B-6,Tarapur MIDC Industrial 20 Tarapur. 30 27 ------Area, Navapur road, Boiser - 401 506. Uttam Galva Steels Ltd, Donavat Complex,Village Narangi,Dist. 2 X 30 = 21 54 ------Donavat, Tal. Khalapur, Dist. Raigad. 60 Raigad.

M/s Jay Mahesh Sugar Parewadi,Di 1 X 30 = 22 Industries Ltd, Off. Pawarwadi, 27 ------st. Beed. 30 tal. Majalgaon, Dist. Beed.

10 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity MW ( EX - BUS GENERATION ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Renuka Sugars Ltd.at Ganga Deshbakta Ratnnappanna Nagar, 23 Kumbhar Panchaganga 1 X 30 = 30 27 ------Dist.Ichalkar Sahakari Sakhar Karkhana, angi Ganga Nagar, Ichalkarangi. M/s Birla carban, Patalganga Project, Village Lohop, Patalganga, 24 2 x 15 = 30 27 ------Patalganga, Tal.Khalapur, Dist. Raigad. Dist.Raigad M/s Gangakhed Sugar and Energy Pvt. Ltd. C/O Gangakhed, 25 Sunil Hitech Engineers Ltd,97, Dist. 1 X 30 = 30 27 ------East High Court Road, Parbhani Ramdaspeth M/s Tembhu Power Private Limited, Koregaon, 3 X 1.5 = 26 Krishnangan C-7, karad Tal.Karad, 4.455 ------4.5 Wakhan Road, Karad Gramin, Dist. Satara. Tal. Karad, Dist. Satara. Village M/s Saikrupa Sakhar Takaliwadi, Karkhana Ltd, A/P 27 Tal. 35 31 ------Hiradgaon, Tal.Shigonda,Dist. Shirol,Dist. Kolhapur. Kolhapur. M/s ISMT Ltd. Kurla, Dist. 28 At Lunkad Towers, Viman 40 36 ------Chandrapur. Nagar, Pune 411 014. M/s Urjankur Shree Datta Datta Nagar, Power Company Ltd.at Datta Tal.Shirol, 29 36 32.4 ------Nagar, Taluka Shirol, Dist. Dist. Kolhapur. Kolhapur. M/s Urjankur Shree Datta Warnanagar Power Company Ltd.at Shree , Tal. 30 Tatyasaheb Kore Warna 44 39.6 ------Panhala,Dist SSKL, Warnanagar, Tal. . Kolhapur. Panhala, Dist. Kolhapur. M/s Purna Sahakari Sahkar Basmat 31 Karkhana Ltd,At Basmatnagar nagar Dist. 18 -- -- 594 -- -- Dist. Hingoli. Hingoli M/s Shree Someshwar Someshwar Sahakari Sakhar Sakhar nagar, Tal. 32 Karkhana 18 16.2 ------Baramati, Ltd.,Someshwarnagar, Dist.Pune. Taluka- Baramati, Dist. Pune

11 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity MW ( EX - BUS GENERATION ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Daund Sugar Ltd, Village ICC Trade Tower, B-Wing Alegaon, 33 18 16.2 ------201,Senapati Bapat Road, Tal. Daund, Pune-411 016. Dist. Pune. M/s Samarth Sahakari Sakhar Ankush Karkhana Ltd, Post. nagar, 34 18 16.2 ------Ankushnagar, Tal. Ambad, Dist. Tal.Ambad, Jalna. Dist. Jalna. Nivrutinagar M/s Vighnahar Sahakari Sakhar (Dhalewadi) Karkhana Ltd, At 35 Tal. 12 10.8 ------Nivrutinagar(Dhalewadi),P.O. Junnar,Dist. Shiroli, Tal. Junnar, Dist. Pune. Pune M/s Baramati Agro Ltd, Pimpli, Tal. 36 Pimpli, Baramati, Dist. Pune, Baramati, 22 19.8 ------Maharashtra - 413 102. Dist. Pune. Mohanrao M/s Sonhira Sahakari Sakhar Kadam Karkhana Ltd, At Mohanrao Nagar, 37 22 19.8 ------Kadamnagar, Wangi, Tal. Wangi. Tal. Kadegaon,Dist. Sangli. Kadegaon Dist.Sangli. M/s Adani Power Maharashtra Ltd, Adani House (Power Tiroda,Dist. 5 X 660 = 38 Division),Plot No.83, Industrial -- 1782 1188 -- -- Gondia 3300 area,Sector-32,Gurgaon- 122001 M/s Vidarbha Industries Power Ltd, Dhirubai Ambani MIDC Knoledge City,I, Block,2nd 39 Butibori, 50 (300) -- 45 ------Floor, Noth Wing, tane Belapur Nagpur Road, Koperkhiirne- New Mumbai M/s Bhaurao Chavan Sahakari Laxminagar, Sakhar Karkhana Tal.Ardhapur 40 Ltd,Laxminagar, Degaon- 16.2 14.58 ------, Yelegaon,Post. Laxminagar, Dist.Nanded Tal. Ardhapur, Dist. Nanded. Village M/s Gurudatt Sugars Ltd, Takaliwadi, 41 A/P Takaliwadi, Tal. Shirol,Dist. Tal. 15 13.5 ------Kolhapur. Shirol,Dist. Kolhapur. M/s Spark Green energy (Satara), Ltd,"Link Side" 50, MIDC 42 Carter Road, 25 22.5 ------Lonand Bandra (West), Mumbai -400 050

12 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity MW ( EX - BUS GENERATION ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Spark Green energy (Satara), Ltd,"Link Side" 50, MIDC 43 25 22.5 ------Carter Road, Bandra Newasa (West),Mumbai -400050 M/s Yashvantrao Mohite Rehthare Krishna Sahakari Sakhar BK., P.O. Karkhana Ltd, 44 Shivajinagar, 16 14 ------Rehthare Budruk,Tal. Karad, Tal. Karad, Dist. Satara, P.P.Shivajinagar - Dist. Satara 415 108. Kh. No.324, M/s A.A. Energy Ltd, Mauza 101, Nikalas Tower, Central Wadsa, 45 10 9 ------Bazar Road, Ramdaspeth, Desaiganj, Nagpur-440 010. Dist. Gadchiroli M/s Ballarpur Industries Ltd. At Ballarpur, 46 P.O.Ballarpur Paper Mills, Dist. 10 (40) 9 ------Dist. Chandrapur-4420901 Chandrapur Veer NLBC M/s Mahati Hydro Power Small HEP, Projects Pvt. Ltd.32-33, 47 Tal. 4.8 4.752 ------Shankarshet Road,Behind Purandar,Di S.T.Workshop, Pune st. Pune M/s Mahati Hydro Power Sonwade Projects Pvt. Ltd.32-33, (Chandoli),T 48 5 4.95 ------Shankarshet Road,Behind al. Shirala, S.T.Workshop, Pune Dist.Sangli. At M/s Dudhaganga Vedganga Mouninagar 49 SSK.Ltd. Mouninagar,Tal. 20 18 ------(Bidri) Kagal ,Dist. Kolhapur-416 208. Dist.Klhapur. M/s Technocraft Industries Ltd.A-25. MIDC, Street No.3, At Village 50 Marol Indusrial Area, Andheri Dahivali, 15 13.5 ------(E),Mumbai-400 093. Murbad.

M/s R.M Mohite Textile Ltd, At R.S.347, Ambapwadi Phata,Off Radhanagari 51 10 9 ------NH4, P.O.1 Wadgaon, Tal. Dam Dist. Hatkanagle, Dist.Kolhapur Kolhapur

13 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity MW ( EX - BUS GENERATION ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

Tadali(Chan M/s Dhariwal drapur 52 Infrastructure(P)Ltd.At Tadali, 300 MW -- -- 270 -- -- MIDC),Dist. Dist.Chandrapur. Chandrapur. M/s Shri Vasant Dada Sahakari Vithewadi Sakhar Karkhana Ltd Vithewadi (Lohoner) 53 17 MW 15.3 ------(Lohoner) Tal. Deola, Dist. Tal. Deola, Nasik Dist. Nasik. M/s ACI Infotech Ltd, A division of Infocom Ltd, 278, Vasan At Bhigwan, 54 Udyog Bhawan, Opp. Tal. Indapur, 15 MW 13.5 ------Highstreet Phoenix Mill, Lowar Dist. Pune. Parel(W), Mumbai-400 013 MIDC M/s Gopani Iron &Power (India) Growth 8MW(15 55 P.Ltd.A-22 MIDC Growth 7.2 ------Centre MW) Centre, Post Tadali-442 406. Tadali M/s Uttam Galva Metallics At Bhugaon 10 MW 56 Ltd,Bhugaon Link Road,Wardha Link Road, 9 ------(15 MW) -442001. Wardha. M/s Grace Industries Ltd, At MIDC 28 MW(33 57 A-23, MIDC Estate, Tadali Estate 25.2 ------MW) Growth Centre, Chandrapur Tadali. M/s Shree Virangana Steels At Mauja Pvt. Ltd. 126-128, 1st Ukerwahi, 22 MW(30 58 Floor, Shriram Tower, Village Heti, 19.8 ------MW) Kingswamy Sadar, near NIT Umrer Road, office ,Nagpur-440001 Nagpur. Village M/s RPL URJA (Division of Kalmana, Rasoya Protiens Ltd), 8.5MW 59 Tal. Wani, 7.65 ------Village Kalmana, Tal.Wani, (10 MW) Dist. Dist.Yavatmal. Yavatmal Village M/s B.S.Ispat Ltd.Survey No.97, Salori, 60 Village Salori, Yensa, Tal. 15 MW 13.5 ------Yensa, Tal. Warora, dist. Chandrapur. Warora At Vaishli M/sVikas SSK. Ltd, Nagar, tal. 61 Vaishali Nagar, Tal. Nivali, Dist. 18 MW 16.2 ------Nivali. Dist. Latur. Latur At M/s Shankar Sahakari Sakhar Sadashivnag 17.5MW 62 Karkhana Ltd. -Kaulage, ar, Tal. 15.75 ------(20 MW) Tal.Kagal Dist.Kolahapur. Malshiras, Dist.Solapur.

14 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity MW ( EX - BUS GENERATION ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

At M/s Sadashivrao Mandalik Sadashivnag Kagal Taluka SSK.Ltd, ar, 63 Sadashiv Nagar, Hamidwada - Hamidwada, 12 MW 10.8 ------Kaulage, Tal.Kagal Tal. Dist.Kolahapur. Kagal,Dist. Kolhapur. M/s Vayunandana Power Ltd, 12-2-460,Plot No.2, New Huda At Village 10MW(12 64 layout, Gudimalkapur, Kaneri,Dist. 9 ------MW) Mahadipatnam, Hyderabad-500 Gadchiroli. 028. M/s M/s Bombay Rayon Fashions Ltd,Plot No.C-7, At Tarapur 6MW(8 65 Tarapur MIDC, Near Tarapur 5.4 ------MIDC MW) Vidya Mandir, Boisar, Tal. Palghar, Dist. Thane. M/s Shri Shankar Maharshi Shankarrao Mohite-Patil SSK At Akluj,Tal. 66 Ltd, Malshiras, 33 MW 29.7 ------Shankarnagar, Akluj Tal. Solapur Malshiras, Dist. Solapur. M/s Pepsico India Holdings Pvt. Ltd, L.U.Gadkari Marg, Village Sadawagha 67 1.85 MW -- 1.665 ------Anik,Mahul, Chembur,Mumbai pur, Dist. 400 074. Satara M/s Shree Renuka Sugars At Ltd,7th floor, Devchand House, Shiv sagar Estate, Dr.Annie SSK,Shahun 22 MW(24 68 Beasant Road, Worli, Mumbai- 20 ------agar, MW) 400 018. Shendre,

Satara

M/s Dwarkadhish SSSK Ltd, At Village KarkhanaShalivahana Projects Seware, 69 Ltd,1582,7th Floor, Minerva Taharabad, 10MW 9 ------Complex, S.D. Road, tal.Satana,Di Secunderabad. st. Nasik M/s Mahalaxmi Vidyut Private Ltd, 363/11, Balaji Niwas,Deep At Konal, 70 Bangalow Chowk, Shiwaji 2 X 5 MW 9 ------Sindhudurg Nagar, Pune-411 016.

M/s Kalyani Renewable Energy India Ltd,D.No.5- At Balapur 13.8 MW 71 6,Prathipadu Village, MIDC, Dist. 12.42 ------(15 MW) Tadepalligudem, west Akola Godavari, Dist. A.P.534 146.

15 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity MW ( EX - BUS GENERATION ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s The Sanjivani (Takli) Sahajanand Sahakari Sakhar Karkhana nagar, Tal. 6.6 Ltd.Sahajanandnagar, Kopargaon, 72 MW(15.9 -- 5.94 ------P.O.Shinganapur - 423 603, Dist. MW) Tal. Kopargaon, Dist. Ahmednagar Ahmednagar . M/s Kisanveer Satara Sahakari At Kisan Sakhar Karkhana Ltd, Veer Nagar, 19.56MW 73 Tal. 17.604 ------Kianveer Nagar, Tal. Wai, Wai.Dist. (22 MW) dist.Satara. Satara M/s Ideal Energy Projects Kundal, Tal. Ltd,122, 2nd Floor, Telecom Addil.1 X 74 Palus, Dist. -- -- 243 -- -- Nagar, Near Ranta Pratap 270 square, Nagpur-440 022. Sangli. M/s Shriram Jawahar Shetkari Sahakari Sakhar Phaltan, 1.2 MW 75 1.08 ------Udyog,Phaltan, Tal.Satara (1.5 MW) Tal.Phaltan,Dist.Satara M/s Hindustan Electricity Generation Company Pvt. At 76 Ltd.Olympia, Central Navlakhumb 350 MW 339.5 ------Avenue, Hiranandani re, pune Business Park. Village M/s Vidarbha Energy and Choramba, Infrastructure P.Ltd, 4th Floor, Tal. 77 10 MW 9 ------MG House, R.T. Road, Civil Ghatangi, Lines, Nagpur. Dist. Yeotmal. M/s Malegaon Sahakari Village Sakhar Karkhana Ltd.At Post. Shivajinagar, 14MW(2 78 tal. 12.6 ------Shivajinagar,Tal. Baramati, Baramati, 1 MW) Dist. Pune. Dist.Pune M/s M/s Greta Energy Ltd, Mul Station Road, Brahampuri- MIDC,Tal 79 15 MW 13 ------441206. Mul, Dist. Dist. Chandrapur. Chandrapur M/s Shree Sidhabali Ispat Ltd, Plot No.C-2, MIDC Area, C-2 MIDC 10MW(2 80 Tadali, Dist. Chandrapur- Area 9 ------0 MW) 442406. Tadali,Dist. Chandrapur.

16 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity MW ( EX - BUS GENERATION ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Renuka Sugar Ltd, Balaji 7th Floor, Devchand House, nagar, Shiv Sagar Estate, Nandur, 26 MW 81 Dr. Annie Besant Road, 23 ------Tal. (30 MW) Worli, Mumbai-400 018. Mangalwed

a Dist. Solapur M/s Kukadi Sahakari Sakhar Karkhana Ltd, Pimpalgaon At Pimpalgaon Pisa, Tal. Pisa, Tal. 10MW(1 82 Shrigonda, Dist.Ahmednagar. Shrigonda, 9 ------6 MW) Dist.Ahmed nagar

Total 3021 2712 5841 990 0

Existing EX BUS Generation 224 3245 5957 11798 12788

Year Wise EX - BUS Availability 3245 5957 11798 12788 12788

Note :1. The year wise date of commissioning is considered as per the dates indicated in application forms. 2. ( ) The figures indicated in the brackets are Installed capacities of Generating Plant

17 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table – 8.2.2 Proposed Yearwise Generation Addition by IPPs'/ Biogas/Bagasse/Biomass Plants etc. for which PPA signed with Various Distribution Companies in State Capacity Available Generation in MW (PPA Signed ) SR. Location of NAME OF APPLICANT Applied NO. the Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s JSW Energy Ltd. Jindal Mansion, 4 X 300= 1 Jaigad 1080 ------5A.Dr.G.Deshmukh Marg. 1200MW Mumbai 400 026. M/s M/s Gupta Energy Pvt. Usegaon, 2 X 60 Ltd7th Floor,Shriram Towers, 2 Dist. MW = 120 108 ------Kingsway, Tal. Ghugus, Chandrapur MW Dist.Chandrapur. M/s Emco Energy Ltd.Warora, 2 x 135 Plot No.F-5, Road No.28, 3 Warora MW = 270 -- 200 ------wagle industrial Estate,Thane- MW 400 604. M/s Wardha Power Company 2 x 135 Pvt.Ltd, 8-2- Warora,Dist. MW = 270 4 293/82/A/431/A, Road No.22, 50 100 ------Chandrapur MW Jubilee Hills, Hyderabad - (Phase -I) 500033. M/s Ultra Tech Cement Ltd. Awapur, Tal. 5 Awapur Cement works, tal. Korpana,Dist. 12 MW 10.8 ------Korpana, Dist. Chandrapur. Chandrapur. M/s Finolex Industries Ltd. At Ranpar- Project Office,26/27, Mumbai - 6 Golap,dist. 22 MW 19.8 ------Pune Road,Pimpri,Pune-411 Ratnagiri 018. M/s Wardha Power Company 2 x 135 Pvt.Ltd, 8-2- Warora,Dist. MW = 270 7 293/82/A/431/A, Road No.22, -- 150 ------Chandrapur MW Jubilee Hills, Hyderabad - (Phase -II) 500033. M/s Finolex Infra structure Ltd. At Ranpar- 26-27,Mumbai -Pune Road, 8 Golap,dist. 1000MW -- -- 450 -- -- Pimpri, Pune- Ratnagiri 411 018 M/s Indiabulls Real Tech Limited. Indiabulls 2 X 660 9 Sinnar -- -- 450 -- -- House, 448-451, Udyog Vihar, MW Phase, Gurgaon -122 001. M/s Sophia Power Company Nandgaon 5 X 270 10 Limited.At Nandgaon pet Peth -- -- 750 -- -- MW Ind.Area.Amravati Amravati

M/s Abhijit MADC Nagpur At Gumgaon 4 X 50 11 Energy Pvt.Ltd.39, Ambazari MIHAN SEZ, 90 -- -- 90 -- MW Layout, Nagpur-440 033. Dist. Nagpur

18 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity Available Generation in MW (PPA Signed ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Maharashtra Vidyut Nigam Ltd. 7th Floor,Shriram MIDC Deoli. 12 10 MW 9 ------Towers, Kingsway, S.V.Patel Dist. Wardha Marg, Sadar,Nagpur.Nagpur M/s IDEAL Energy Projects Ltd, Near Bela, IRB Complex, 2nd Floor, 2 X 135 13 tal. Umred, -- 200 ------Chandivili Village, Andheri (E), MW Dist.Nagpur Mumbai -400 072 M/s JSW Steel Ltd. B-6,Tarapur MIDC Industrial 14 Tarapur. 30 MW 27 ------Area, Navapur road, Boiser - 401 506. Uttam Galva Steels Ltd, Donavat Complex,Village Narangi,Dist. 2 X 30 15 54 ------Donavat, Tal. Khalapur, Dist. Raigad. MW Raigad. M/s Jay Mahesh Sugar Industries Ltd, Off. Parewadi,Di 1 X 30 16 27 ------Pawarwadi, tal. Majalgaon, Dist. st. Beed. MW Beed. M/s Renuka Sugars Ltd.at Ganga Deshbakta Ratnnappanna Nagar, 1 X 30 17 Kumbhar Panchaganga 27 ------Dist.Ichalkar MW Sahakari Sakhar Karkhana, angi Ganga Nagar, Ichalkarangi. M/s Gangakhed Sugar and Gangakhed, Energy Pvt. Ltd. C/O Sunil 1 X 30 18 Dist. 27 ------Hitech Engineers Ltd,97, East MW Parbhani High Court Road, Ramdaspeth M/s Tembhu Power Private Limited, Koregaon, 3 X 1.5 19 Krishnangan C-7, karad Tal.Karad, 4.455 ------MW Wakhan Road, Karad Gramin, Dist. Satara. Tal. Karad, Dist. Satara. Village M/s Saikrupa Sakhar Karkhana Takaliwadi, 20 Ltd, A/P Hiradgaon, Tal. 35 MW 31 ------Tal.Shigonda,Dist. Kolhapur. Shirol,Dist. Kolhapur .

M/s ISMT Ltd. Kurla, Dist. 21 At Lunkad Towers, Viman 40 MW 36 ------Chandrapur. Nagar, Pune 411 014.

M/s Urjankur Shree Datta Datta Nagar, Power Company Ltd.at Datta Tal.Shirol, 22 36 MW 32.4 ------Nagar, Taluka Shirol, Dist. Dist.Kolhapu Kolhapur. r.

19 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity Available Generation in MW (PPA Signed ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Urjankur Shree Datta Warnanagar Power Company Ltd.at Shree , Tal. 23 Tatyasaheb Kore Warna 44 MW 39.6 ------Panhala,Dist SSKL, Warnanagar, Tal. . Kolhapur. Panhala, Dist. Kolhapur. At M/s Purna Sahakari Sahkar Basmatnaga 24 Karkhana Ltd,At Basmatnagar 18 MW 16.2 ------r Dist. Dist. Hingoli. Hingoli M/s Shree Someshwar At Sahakari Sakhar Sakhar Someshwar 25 Karkhana nagar, Tal. 18MW 16.2 ------Ltd.,Someshwarnagar, Baramati, Taluka- Baramati, Dist. Pune Dist.Pune. M/s Daund Sugar Ltd, Village ICC Trade Tower, B-Wing Alegaon, 26 18 MW 16.2 ------201,Senapati Bapat Road, Tal. Daund, Pune-411 016. Dist. Pune. At M/s Samarth Sahakari Sakhar Ankushnaga Karkhana Ltd, Post. 27 r, 18 MW 16.2 ------Ankushnagar, Tal. Ambad, Tal.Ambad, Dist. Jalna. Dist. Jaln a. At M/s Vighnahar Sahakari Nivrutinagar( Sakhar Karkhana Ltd, At Dhalewadi) 28 Nivrutinagar(Dhalewadi),P.O. 12 MW 10.8 ------Tal. Shiroli, Tal. Junnar, Dist. Junnar,Dist. Pune. Pune At Pimpli, M/s Baramati Agro Ltd, Tal. 29 Pimpli, Baramati, Dist. Pune, 22 MW 19.8 ------Baramati, Maharashtra - 413 102. Dist. Pune. M/s Sonhira Sahakari Sakhar Wangi. Tal. Karkhana Ltd, At Mohanrao 30 Kadegaon 22 MW 19.8 ------Kadamnagar, Wangi, Tal. Dist.Sangli. Kadegaon,Dist. Sangli. M/s Adani Power Maharashtra Ltd, Adani House (Power Tiroda,Dist. 31 5 X 660 MW -- 1320 1200 -- -- Division),Plot No.83, Industrial Gondia area,Sector-32,Gurgaon M/s Vidarbha Industries Power Ltd, Dhirubai MIDC 1 X 50 MW Ambani Knoledge City,I, 32 Butibori, out of 300 -- 45 ------Block,2nd Floor, Noth Wing, Nagpur MW tane Belapur Road, Koperkhiirne- New Mumbai

20 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location Capacity Available Generation in MW (PPA Signed ) SR. NAME OF APPLICANT of the Applied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Spark Green energy (Satara), Ltd,"Link Side" 50, MIDC 33 Carter Road, 25 MW 22.5 ------Lonand Bandra (West), Mumbai -400 050 M/s Spark Green energy (Satara), Ltd,"Link Side" 50, MIDC 34 Carter Road, 25 MW 22.5 ------Newasa Bandra (West), Mumbai -400 050 M/s Yashvantrao Mohite Rehthare Krishna Sahakari Sakhar BK., P.O. Karkhana Ltd, 35 Shivajinagar 16 MW 14 ------Rehthare Budruk,Tal. Karad, , Tal. Karad, Dist. Satara, P.P.Shivajinagar Dist. Satara -415 108. Kh. No.324, M/s A.A. Energy Ltd, Mauza 101, Nikalas Tower, Central Wadsa, 36 10 MW 9 ------Bazar Road, Ramdaspeth, Desaiganj, Nagpur-440 010. Dist. Gadchiroli M/s Ballarpur Industries Ltd. At Ballarpur, 10 MW 37 P.O.Ballarpur Paper Mills, Dist. 9 ------(40 MW) Dist. Chandrapur-4420901 Chandrapur Veer NLBC M/s Mahati Hydro Power Small HEP, Projects Pvt. Ltd.32-33, 38 Tal. 4.8 MW 4.752 ------Shankarshet Road,Behind Purandar,Di S.T.Workshop, Pune st. Pune M/s Mahati Hydro Power Sonwade Projects Pvt. Ltd.32-33, (Chandoli),T 39 5 MW 4.95 ------Shankarshet Road,Behind al. Shirala, S.T.Workshop, Pune Dist.Sangli. M/s Dudhaganga Vedganga At SSK.Ltd. Mouninagar 40 20 MW 18 ------Mouninagar,Tal. Kagal ,Dist. (Bidri) Kolhapur-416 208. Dist.Klhapur. M/s R.M Mohite Textile Ltd, At R.S.347, Ambapwadi Radhanagari 41 Phata,Off NH4, P.O.1 10 MW 9 ------Dam Dist. Wadgaon, Tal. Hatkanagle, Kolhapur Dist.Kolhapur M/s Shri Vasant Dada Vithewadi Sahakari Sakhar Karkhana (Lohoner) 42 17 MW 15.3 ------Ltd Vithewadi (Lohoner) Tal. Tal. Deola, Deola, Dist. Nasik Dist. Nasik.

21 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location CapacityA Available Generation in MW (PPA Signed ) SR. NAME OF APPLICANT of the pplied NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

M/s Gopani Iron &Power MIDC (India) P.Ltd.A-22 MIDC Growth 8MW 43 7.2 ------Growth Centre, Post Tadali- Centre (15 MW) 442 406. Tadali M/s Uttam Galva Metallics At Bhugaon 10 MW 44 Ltd,Bhugaon Link Link Road, 9 ------(15 MW) Road,Wardha -442001. Wardha. M/s Shree Virangana Steels At Mauja Pvt. Ltd. 126-128, 1st Ukerwahi, 22 MW 45 Floor, Shriram Tower, Village Heti, 19.8 ------(30 MW) Kingswamy Sadar, near NIT Umrer Road, office ,Nagpur-440001 Nagpur. Village M/s RPL URJA (Division of Kalmana, Rasoya Protiens Ltd), 8.5MW 46 Tal. Wani, 7.65 ------Village Kalmana, Tal.Wani, (10 MW) Dist. Dist.Yavatmal. Yavatmal M/s Shankar Sahakari Sakhar Tal. 17.5MW 47 Karkhana Ltd. -Kaulage, Malshiras, 15.75 ------(20 MW) Tal.Kagal Dist.Kolahapur. Dist.Solapur. M/s Vayunandana Power Ltd, 12-2-460,Plot No.2, New At Village 10MW 48 Huda layout, Gudimalkapur, Kaneri,Dist. 9 ------(12 MW) Mahadipatnam, Hyderabad- Gadchiroli. 500 028. M/s Pepsico India Holdings Sadawagha Pvt. Ltd, L.U.Gadkari Marg, 49 pur, Dist. 1.85 MW -- 1.665 ------Village Anik,Mahul, Satara Chembur,Mumbai 400 074. M/s Shree Renuka Sugars Ltd,7th floor, Devchand Shahunagar, 22 MW 50 House, Shiv sagar Estate, Shendre,Sat 20 ------(24 MW) Dr.Annie Beasant Road, ara Worli, Mumbai-400 018. M/s Kalyani Renewable Energy India Ltd,D.No.5- At Balapur 13.8 MW 51 6,Prathipadu Village, MIDC, Dist. 12.42 ------Tadepalligudem, west Akola (15 MW) Godavari, Dist. A.P.534 146. M/s The Sanjivani (Takli) Sahakari Sakhar Karkhana Tal. Ltd.Sahajanandnagar, Kopargaon, 6.6 MW 52 -- 5.94 ------P.O.Shinganapur - 423 603, Dist. (15.9 MW) Tal. Kopargaon, Dist. Ahmednagar Ahmednagar

22 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Location CAPACITY Available Generation in MW (PPA Signed ) SR. NAME OF APPLICANT of the APPLIED NO. Plant (MW) 2010-11 2011-12 2012-13 2013-14 2014-15

At Kisan M/s Kisanveer Satara Veer Nagar, Sahakari Sakhar Karkhana 19.56MW 53 Tal. 17.604 ------Ltd, Kianveer Nagar, Tal. Wai, (22 MW) Wai.Dist. dist.Satara. Satara Village M/s Malegaon Sahakari Shivajinagar Sakhar Karkhana Ltd.At Post. 14MW 54 ,tal. 12.6 ------Shivajinagar,Tal. Baramati, (21 MW) Baramati,Dis Dist. Pune. t.Pune M/s Kukadi Sahakari Sakhar Tal. Karkhana Ltd, Shrigonda, 10MW 55 9 ------At Pimpalgaon Pisa, Tal. Dist. (16 MW) Shrigonda, Dist.Ahmednagar. Ahmednagar Total 2057 2023 2850 90 0

Existing EX BUS Generation 224 2281 4304 7154 7244

Year Wise EX - BUS Availability 2281 4304 7154 7244 7244

23 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table – 8.4 – Evacuation Arrangement for existing IPP /CPP/Biomass/Bagasse/Biogas based Plants

CAPACITY SR. Location of the NAME OF APPLICANT APPLIED Evacuation Arrangement NO. Plant (MW)

1 M/s Indrajit Infrastructure Bhugaon 2 x 40 MW = 220kV line from their plant upto 220 kV Bhugaon Pvt.Ltd. (Wardha-II) 80 MW S/S. Modern Centre,'B' Wing, 2nd Floor, Sane Guruji Marg, Mahalaxmi, Mumbai- 400011. 2 M/s. Purty Sakhar Wardha. 1 x 24 = LILO on 220 kV Khaparkheda – Wardha S/c at Karkhana, Dist. Wardha. 24 MW 220 kV Purty S/s 3 M/s Ind-barath Engineers Village Kharab 20MW 132 kV line from their plant upto 132 kV Mukhed (Maharashtra ) Ltd.Plot Khandgaon,,Dist. S/S. No.30-A,Road No.1, Film Nanded Nagar,Jubillee Hills, Hyderabad-500 033. 4 M/s Lokmangal Sugar Bhandarkavathe, 1 X 15 MW 132 kV line from their plant upto 132 kV Ethanol & Co-Generation Tal. South Mandrup S/S Industries Ltd, Solapur, Dist. 33/A, Sahyadri Nagar,Hotgi Solapur. Road, Solapur -413 003. 5 M/s M/s Hotel Leelaventure Village 4.5 MW 33 kV line from their plant at Khaprale, upto Ltd, Khaparale,Tal. MSETCL 132 /33 kV Khaprale S/S- The Leela Kempinski, Sinnar dist Nasik. Sahar, Andheri (E), Mumbai 400 059. 6 M/s Hotel ITC the Maratha, Village Khaprale 6 MW 33 kV line from there proposed plant at Near Blue Dart (Sinnar),Dist. Khaprale, Sinnar upto MSETCL 132/33 kV Office,Sahar Airport Road, Nasik Khaprale S/S, Mumabi -400 099. 7 M/s Renuka Sugars Ltd.at Ganga Nagar, 1 X 30 MW LILO on 110 kV Kolhapur-II -Ichalkarangi Line. Deshbakta Ratnnappanna Dist.Ichalkarangi Kumbhar Panchaganga Sahakari Sakhar Karkhana, Ganga Nagar, Ichalkarangi. 8 M/s Daund Sugar Ltd, Village Alegaon, 18 MW LILO on 132 kV Daund -Shrigonda Line. ICC Trade Tower, B-Wing Tal. Daund, Dist. 201,Senapati Bapat Road, Pune. Pune -411 016. 9 M/s Baramati Agro Ltd, At Pimpli, Tal. 22 MW 220 kV lines from their plant to Bhigwan S/S. Pimpli, Baramati, Baramati, Dist. Dist. Pune Pune. 10 M/s Finolex Industries Ltd. At Ranpar- 22 MW 220 kV line from their plant upto 220 kV Pawas Project Office,26/27, Golap,dist. S/S. Pimpri,Pune Ratnagiri 11 M/s Kranti Sahakari Kundal, Tal. 6.65 MW 33 kV lines from your plant at Kundal, Tal. Sakhar Karkhana, Kundal, Palus, Dist. (8.85 MW) Palus,Dist Sangli upto MSETCL 110/33 kV Dist.sangli Sangli. Kundal S/S

24 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 /WEF 01/04/10

Table – 8.5 – Evacuation Arrangement for proposed IPP /CPP/Biomass/Bagasse/Biogas based Plants

CAPACITY SR. Location of NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. the Plant (MW)

1 M/s JSW Energy Ltd. Jaigad 4 X 300 = 1) 400 kV Jaigad-New Koyna D/C with Quad Cond. Jindal Mansion, 1200 2) 400 kV Jaigad-Karad D/C with quad cond. 5A.Dr.G.Deshmukh Marg. Mumbai 400 026. 2 M/s M/s Gupta Energy Pvt. Usegaon, 2 X 60 = 120 1) 220 kV Ghugus -Chandrapur MIDC D/C line. Ltd.(Formerly Gupta Coal Dist. Fields an d Washaries Ltd.) Chandrapur 7th Floor,Shriram Towers, Kingsway, Nagpur 440 001Tal. Ghugus, Dist.Chandrapur. 3 M/s Nagpur Energy Near 250 + 250 + 1) 400 kV Bhadravati Plant-Chandrapur-II D/C line Infrastructure Ltd.(Formerly Bhadravati,Dist. 500 = 1000 with quad. Cond. Baidyanath Power Chandrapur. &Mining), 5, Temple Road,Civil Lines, Nagpur-440 001. 4 M/s Pat ni Energy Ltd. Medhekar, 2 x 135 = 270 1) 220 kV Patni Plant -Wadkhal D/C line. 302-304, Regent Tal.Alibag. Chembers,Nariman Point, Mumbai 400021. 5 M/s Emco Energy Warora 2 x 135 = 270 1) 220 kV Emco Plant -Warora D/C line Ltd.Warora, Plot No.F-5, Road No.28, wagle industrial Estate,Thane-400 604. 6 M/s Sun-Flag Iron and At Warthi, Dist. 2 x 15 = 30 1) 220 kV Lines from the plant to 220 kV Bhandara Steel Co.Ltd. Bhandara Bhandara S/S Road, Bhandara -441 905 7 M/s Wardha Power Warora,Dist. 2 x 135 = 270 1) 220 kV Warora plant - Warora D/C line Company Pvt.Ltd, Chandrapur (Phase -I) 8-2-293/82/A/431/A, Road No.22, Jubilee Hills, Hyderabad -500033. 8 M/s Ultra Tech Cement Awapur, Tal. 12 1) 220 kV line from their Plant at Awapur upto 220 Ltd. Awapur Korpana,Dist. kV Gadchandur Cement works, tal. Chandrapur. Korpana, Dist. Chandrapur. 9 M/s Finolex Industries Ltd. At Ranpar- 22 1) 220 kV line from their plant upto 220 kV Pawas Project Office,26/27, Golap,dist. S/S. Mumbai -Pune Ratnagiri Road,Pimpri,Pune-411 018. 10 M/s Reliance Industries Nagothane 345 1) 220 kV RIL Plant-Nagothane D/C line Ltd, Maker Chanbers IV,3rd Floor,222,Nariman Point,Mumbai 400 021.

25 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

CAPACITY SR. Location of NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. the Plant (MW)

11 M/s Ind-Barath Power At Village 300 1) From their Plant at Aronda upto 220 kV Sawantwadi (Konkan) Ltd. Plot No.321, Aonda,Dist. S/S. Br. Nath Pai Sawanwadi. Road,RamtirthNagar, Belgaum-590016. 12 M/s Wardha Power Warora,Dist. 2 x 135 = 1) 220 kV line from Warora Plant to 400 kV Warora Company Pvt.Ltd, Chandrapur 270 (Phase S/S by making LILO on 220 kV Warora-Bhugaon Line. 8-2-293/82/A/431/A, Road -II) No.22, Jubilee Hills, Hyderabad -500033. 13 M/s Finolex Infrastructure At Ranpar- 1000 1) 400 kV D/C line from Golap to Korad-II S/S Ltd. 26- Golap,dist. 27,Mumbai -Pune Road, Ratnagiri Pimpri, Pune-411 018 14 M/s Indiabulls Real Tech Sinnar 2 X 660 = 1) 400 kV Sinnar - Babhaleshwar D/C line with quad Limited. Indiabulls 1320 cond. House, 448-451, Udyog Vihar, Phase, Gurgaon - 122 001. 15 M/s Sophia Power Nandgaon 4 X 660 = 1) 400 kV Nandgaon Peth- Akola D/C line with quad Company Limited.At Peth 2640 cond. Nandgaon pet Amravati 2) LILO on Akola-Koradi-II S/C at Nandgaon Peth. Ind.Area.Amravati 16 M/s Abhijit MADC Nagpur At Gumgaon 4 X 50 = 1) LILO on 220 kV Wardha-I to Ambazari S/C line Energy Pvt.Ltd.39, MIHAN SEZ, 200 Ambazari Layout, Nagpur- Dist. Nagpur 440 033. 17 M/s Maharashtra Vidyut MIDC Deoli. 10 1) 132 kV D/C line from Plant at MIDC Deoli - Deoli Nigam Ltd. 7th Dist. Wardha S/S. Floor,Shriram Towers, Kingsway, S.V.Patel Marg, Sadar,Nagpur.Nagpur 18 M/s Lloyds Metals & Ghugus, Dist. 4 X30 = 12 1) 220 kV D/C line from From Plant to Matradevi. Engineers Ltd, Chandrapur. Modern Mills Compound,101, Keshavrao Khade Marg, Jacob circle,Mumbai 400 011. 19 M/s IDEAL Energy Projects Near Bela, 2 X 135 = 1) 220 kV D/C line from Bela to Purti Ltd, IRB Complex, 2nd tal. Umred, 270 2) LILO on K'khed-Wardha-I at Purti. Floor, Chandivili Village, Dist.Nagpur Andheri (E), Mumbai -400 072 20 M/s JSW Steel Ltd. Tarapur. 30 1) 220 kV D/C line from Tarapur to Boiser-II B-6,Tarapur MIDC Industrial Area, Navapur road, Boiser -401 506.

26 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

CAPACITY SR. Location of NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. the Plant (MW)

21 Uttam Galva Steels Ltd, Narangi,Dist. 2 X 30 = 60 1) 100 kV D/C line from Donavat to Tambati S/S Donavat Complex,Village Raigad. Donavat, Tal. Khalapur, Dist. Raigad. 22 M/s Jay Mahesh Sugar Parewadi,Dist. 1 X 30 = 30 1) 132 kV D/C line Parewadi to 132 kV Majalgaon Industries Ltd, Beed. S/S. Off. Pawarwadi, tal. Majalgaon, Dist. Beed. 23 M/s Renuka Sugars Ltd.at Ganga Nagar, 1 X 30 = 30 1) LILO on 110 kV Kolhapur – Ichalkarangi Line Deshbakta Ratnnappanna Dist.Ichalkarangi Kumbhar Panchaganga Sahakari Sakhar Karkhana, Ganga Nagar, Ichalkarangi. 24 M/s Birla carban, Patalganga,Dist. 2 x 15 = 30 1) 100 kV D/C line from Lohop to Patalganga S/S Patalganga Project, Raigad. Village Lohop, Patalganga, Tal.Khalapur, Dist.Raigad 25 M/s Gangakhed Sugar and Gangakhed, 1 X 30 = 30 1) 132 kV D/C line from their Plant to 132 kV Energy Pvt. Ltd. C/O Dist. Parbhani Gangakhed S/S. Sunil Hitech Engineers Ltd,97, East High Court Road, Ramdaspeth 26 M/s Tembhu Power Private Koregaon, 3 X 1.5 = 1) 110 kV D/C line form Plant to Tembhu S/S. Limited, Tal.Karad, Dist. 4.5 Krishnangan C-7, karad Satara. Wakhan Road, Karad Gramin, Tal. Karad, Dist. Satara. 27 M/s Saikrupa Sakhar Village 35 1) 132 kV lines from their plant to 132 kV Shrigonda Karkhana Ltd, Takaliwadi, Tal. S/S A/P Hiradgaon, Shirol,Dist. Tal.Shigonda,Dist. Kolhapur. Kolhapur. 28 M/s ISMT Ltd. Kurla, Dist. 40 1) From their Plant to 132 kV level of 220/132 kV At Lunkad Towers, Viman Chandrapur. Hinganghat S/S Nagar, Pune 411 014. 29 M/s Urjankur Shree Datta Datta Nagar, 36 1) 110 kV D/C line from Dattanagar to Jaysingpur Power Company Ltd.at Tal.Shirol, S/S. Datta Nagar, Taluka Shirol, Dist.Kolhapur. Dist. Kolhapur. 30 M/s Urjankur Shree Datta Warnanagar, 44 1) 132 kV line from Warnanagar to 132-110 kV Power Company Ltd.at Tal. Wathar S/S. Shree Tatyasaheb Kore Panhala,Dist. Warna SSKL, Warnanagar, Kolhapur. Tal. Panhala, Dist. Kolhapur.

27 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

CAPACITY SR. Location of the NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. Plant (MW)

31 M/s Purna Sahakari Sahkar At Basmatnagar Dist. 18 1) 132 kV lines from their plant to 132 kV Karkhana Ltd,At Hingoli Basmatnagar S/S. Basmatnagar Dist. Hingoli. 32 M/s Shree Someshwar At Someshwarnagar, 18 1) 132 kV Line from their plant to 132 kV Sahakari Sakhar Sakhar Tal. Baramati, Someshwar S/S Karkhana Dist.Pune. Ltd.,Someshwarnagar, Taluka- Baramati, Dist. Pune 33 M/s Daund Sugar Ltd, Village Alegaon, Tal. 18 1) LILO on 132 kV Daund -Shrigonda Line. ICC Trade Tower, B-Wing Daund, Dist. Pune. 201,Senapati Bapat Road, Pune-411 016. 34 M/s Samarth Sahakari At Ankushnagar, 18 1) 132 kV lines from Plant to Deoli S/S. Sakhar Karkhana Ltd, Post. Tal.Ambad, Dist. Jalna. Ankushnagar, Tal. Ambad, Dist. Jalna. 35 M/s Vighnahar Sahakari At 12 1) 132 kV lines from Plant to 132 kV Sakhar Karkhana Ltd, At Nivrutinagar(Dhalewadi) Narayangaon S/S. Nivrutinagar(Dhalewadi),P.O. Tal. Junnar,Dist. Pune Shiroli, Tal. Junnar, Dist. Pune. 36 M/s Baramati Agro Ltd, At Pimpli, Tal. Baramati, 22 1) 220 kV lines from their plant to Bhigwan Pimpli, Baramati, Dist. Pune, Dist. Pune. S/S. Maharashtra - 413 102. 37 M/s Sonhira Sahakari At Mohanrao Kadam 22 1)132 kV lines from their plant to 220/132 Sakhar Karkhana Ltd, At Nagar, Wangi. Tal. kV Kadegaon S/S. Mohanrao Kadamnagar, Kadegaon Dist.Sangli. Wangi, Tal. Kadegaon,Dist. Sangli. 38 M/s Adani Power Tiroda,Dist. Gondia 5 X 660 = 1) 765 kV 2 x S/C line from plant to Maharashtra Ltd, Adani 3300 MSETCL's proposed 765 kV Koradi -III S/s. House (Power Division),Plot 2) 2 x 1000 MVA, 765/400 kV ICT at plant. No.83, Industrial 3) 400 kV D/C line from Tiroda to Warora area,Sector-32,Gurgaon- S/S. 122001 4) With 765 kV lines, 400 kV Tiroda - Koradi-II D/C line will not be required. 39 M/s Vidarbha Industries MIDC Butibori, Nagpur 50 (300) 1) 220 kV lines from plant to MIDC Butibori Power Ltd, S/S. Dhirubai Ambani Knoledge City,I, Block,2nd Floor, Noth Wing, tane Belapur Road, Koperkhiirne- New Mumbai 40 M/s Bhaurao Chavan Laxminagar, 16.2 1) 132 kV lines from their plant to 132 kV Sahakari Sakhar Karkhana Tal.Ardhapur, Ardhapur S/S. Ltd,Laxminagar, Degaon- Dist.Nanded Yelegaon,Post. Laxminagar, Tal. Ardhapur, Dist. Nanded.

28 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

CAPACITY SR. Location of NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. the Plant (MW)

41 M/s Gurudatt Sugars Ltd, Village 15 1) 110 kV lines from their plant to 110 kV A/P Takaliwadi, Tal. Takaliwadi, Kurundhawadi S/S. Shirol,Dist. Kolhapur. Tal. Shirol,Dist. Kolhapur. 42 M/s Spark Green energy MIDC Lonand 25 1) 132 kV level of 220/132 kV MIDC Lonand S/S (Satara), Ltd,"Link Side" 50, Carter Road, Bandra (West), Mumbai - 400 050 43 M/s Spark Green energy MIDC Newasa 25 1) MSETCL proposed 132 kV Ghodegaon S/S (Satara), Ltd,"Link Side" 50, Carter Road, Bandra (West), Mumbai - 400 050 44 M/s Yashvantrao Mohite Rehthare BK., 16 1) 110 kV lines from t heir plant to 110 kV Rethare S/S. Krishna Sahakari Sakhar P.O. Karkhana Ltd, Shivajinagar, Rehthare Budruk,Tal. Tal. Karad, Karad, Dist. Satara, Dist. Satara P.P.Shivajinagar -415 108. 45 M/s A.A. Energy Ltd, Kh. No.324, 10 1) 132 kV lines from their plant to 132 kV Bramhapuri 101, Nikalas Tower, Mauza S/S. Central Bazar Road, Wadsa, Ramdaspeth, Nagpur-440 Desaiganj, 010. Dist. Gadchiroli 46 M/s Ballarpur Industries At Ballarpur, 10 (40) 1) 220 kV Line from their plant to 220 kV Ballarpur S/S Ltd. Dist. P.O.Ballarpur Paper Mills, Chandrapur Dist. Chandrapur-4420901 47 M/s Mahati Hydro Power Veer NLBC 4.8 1) 110 kV Line from their Plant at sonwade to 110 kV Projects Pvt. Ltd.32-33, Small HEP, Warna S/S Shankarshet Road,Behind Tal. S.T.Workshop, Pune Purandar,Dist. Pune 48 M/s Mahati Hydro Power Sonwade 5 1) 110 kV Line from their plant at Veer upto 110 kV Projects Pvt. Ltd.32-33, (Chandoli),Tal. Veer S/S. Shankarshet Road,Behind Shirala, S.T.Workshop, Pune Dist.Sangli. 49 M/s Dudhaganga At Mouninagar 20 1) From their Plant at Bidri (Mouninagar) Upto 220/132 Vedganga SSK.Ltd. (Bidri) kV Bidri S/S Mouninagar,Tal. Kagal Dist.Klhapur. ,Dist. Kolhapur-416 208.

29 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

CAPACITY SR. Location of the NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. Plant (MW)

50 M/s Technocraft Industries At Village Dahivali, 15 1) LILO on 100 kV Padhge-Murbad line Ltd.A-25. MIDC, Street Murbad. No.3, Marol Indusrial Area, Andheri (E),Mumbai-400 093. 51 M/s R.M Mohite Textile Ltd, At Radhanagari 10 1) 33 kV level of MSETCL existing 110/33 kV R.S.347, Ambapwadi Dam Dist. Radhanagari S/S Phata,Off NH4, P.O.1 Kolhapur Wadgaon, Tal. Hatkanagle, Dist.Kolhapur 52 M/s Dhariwal Tadali(Chandrapur 300 1) 400 kV Lines from their plant to 400/220 kV Infrastructure(P)Ltd.At MIDC),Dist. Chandrapur -II S/S Tadali, Dist.Chandrapur. Chandrapur. 53 M/s Shri Vasant Dada Vithewadi 17 1) From their Plant at Vithewadi to 132 kV level of Sahakari Sakhar (Lohoner) Tal. 220/132 kV Satana S/S Karkhana Ltd Vithewadi Deola, Dist. Nasik. (Lohoner) Tal. Deola, Dist. Nasik 54 M/s ACI Infotech Ltd, A At Bhigwan, Tal. 15 1) 220 kV Line from their plant to 220/22 kV division of Infocom Ltd, Indapur, Dist. Bhigwan S/S 278, Vasan Udyog Pune. Bhawan, Opp. Highstreet Phoenix Mill, Lowar Parel(W), Mumbai -400 013 55 M/s Gopani Iron &Power MIDC Growth 8 (15) 1) 33 kV lines from their plant to 220/33 kV (India) P.Ltd.A-22 MIDC Centre Tadali Chandrapur MIDC S/S. Growth Centre, Post Tadali-442 406. 56 M/s Uttam Galva Metallics At Bhugaon Link 10 (15) 1) 220 kV Lines from their plant to 220 kV Ltd,Bhugaon Link Road, Wardha. Bhugaon (Wardha-II) S/S Road,Wardha -442001. 57 M/s Grace Industries Ltd, At MIDC Estate 28 (33) 1)LILO on 220 kV Gadchandur –CTPS line A-23, MIDC Estate, Tadali Tadali. Growth Centre, Chandrapur 58 M/s Shree Virangana At Mauja 22 (30) 1) 220 kV Lines from their plant to220 kv Umred Steels Pvt. Ltd. Ukerwahi, Village S/S. 126-128, 1st Floor, Shriram Heti, Umrer Road, Tower, Kingswamy Sadar, Nagpur. near NIT office ,Nagpur- 440001 59 M/s RPL URJA (Division of Village Kalmana, 8.5 (10) 1) 33kV Lines from their plant to 220/33 kV Wani Rasoya Protiens Ltd), Tal. Wani, Dist. S/S. Village Kalmana, Tal.Wani, Yavatmal Dist.Yavatmal.

30 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

CAPACITY SR. Location of the NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. Plant (MW)

60 M/s B.S.Ispat Ltd.Survey Village Salori, 15 1) 33 kV Lines from their plant to 220/33 kV No.97, Village Salori, Yensa, Tal. Warora S/S Yensa, Tal. Warora, dist. Warora Chandrapur. 61 M/sVikas SSK. Ltd, At Vaishli Nagar, 18 1) 132 kV line from their plant to 132/33 kv Nivali Vaishali Nagar, Tal. Nivali, tal. Nivali. Dist. S/S Dist. Latur. Latur

62 M/s Shankar Sahakari At 17.5 (20) 1) 132 kV Line from their plant to 132kV Sakhar Karkhana Ltd. - Sadashivnagar, Purandwade S/S Kaulage, Tal.Kagal Tal. Malshiras, Dist.Kolahapur. Dist.Solapur. 63 M/s Sadashivrao Mandalik At 12 1) 33 kV Lines from their plant to proposed 220/33 Kagal Taluka SSK.Ltd, Sadashivnagar, kV Hamidwada S/S- Sadashiv Nagar, Hamidwada, Tal. Hamidwada -Kaulage, Kagal,Dist.Kolhap Tal.Kagal Dist.Kolahapur. ur. 64 M/s Vayunandana Power At Village 10 (12) 1) 132 kV line from their plant to 220/132 kV Ltd, 12-2-460,Plot No.2, Kaneri,Dist. Gadchir oli S/S New Huda layout, Gadchiroli. Gudimalkapur, Mahadipatnam, Hyderabad-500 028. 65 M/s M/s Bombay Rayon At Tarapur MIDC 6 (8) 1) 33 kV lines from their plant toMSETCL Fashions Ltd,Plot No.C-7, 220/132/33 kV Boiser –II S/S Tarapur MIDC, Near Tarapur Vidya Mandir, Boisar, Tal. Palghar, Dist. Thane. 66 M/s Shri Shankar Maharshi At Akluj,Tal. 33 1) 132 kV line from their plant to MSETCL Shankarrao Mohite-Patil Malshiras,Solapur proposed 132 kV Shankarnagar S/S SSK Ltd, Shankarnagar, Akluj Tal. Malshiras, Dist. Solapur. 67 M/s Pepsico India Holdings t Sadawaghapur, 1.85 1) 33 kV line from their plant to 220/33 kV Pvt. Ltd, L.U.Gadkari Dist. Satara Sadvaghapur S/S Marg, Village Anik,Mahul, Chembur,Mumbai 400 074. 68 M/s Shree Renuka Sugars At Ajinkyatara 22 (24) 1) LILO on 220 kV Vankuswadi –Satara MIDC Ltd,7th floor, Devchand SSK,Shahunagar, S/S House, Shiv sagar Estate, Shendre,Satara Dr.Annie Beasant Road, Worli, Mumbai-400 018. 69 M/s Dwarkadhish SSSK At Village 10 1) 132kV lines from their plant to 132 kV Ltd, KarkhanaShalivahana Seware, Taharabad S/S. Projects Ltd,1582,7th Taharabad, tal. Floor, Minerva Complex, Satana,Dist. S.D. Road, Secunderabad. Nasik

31 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

CAPACITY SR. Location of the NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. Plant (MW)

70 M/s Kalyani Renewable At Balapur MIDC, 13.8 (15) 1) 132 kV Lines from their plant to 220/132/33 kV Energy India Ltd,D.No.5- Dist. Akola Balapur S/S. 6,Prathipadu Village, Tadepalligudem, west Godavari, Dist. A.P.534 146. 71 M/s The Sanjivani (Takli) Sahajanandnagar, 6.6 (15.9) 1) 33 kV Lines from their plant to 132/33 kV Sahakari Sakhar Karkhana Tal. Kopergaon S/S. Ltd.Sahajanandnagar, Kopargaon,Dist. P.O.Shinganapur - 423 Ahmednagar. 603, Tal. Kopargaon, Dist. Ahmednagar 72 M/s Kisanveer Satara At Kisan Veer 19.56 (22) 1) LILO on IInd circuit of 132 kV Lonand-Wai line Sahakari Sakhar Karkhana Nagar, Tal. Ltd, Kianveer Nagar, Tal. Wai.Dist. Satara Wai, dist.Satara. 73 M/s Ideal Energy Projects Kundal, Tal. Addil.1 X 1) 400 kV D/C line from thier plant to 440 kV Ltd,122, 2nd Floor, Palus, Dist. 270 = 270 Warora S/S. Telecom Nagar, Near Sangli. Ranta Pratap square, Nagpur-440 022. 74 M/s Shriram Jawahar Phaltan, 1.2 (1.5) 1) 33 kV lines from their plant to 132/33 kV Phaltan Shetkari Sahakari Sakhar Tal.Satara S/S Udyog,Phaltan, Tal.Phaltan,Dist.Satara 75 M/s Hindustan Electricity At Navlakhumbre, 350 1) LILO on 400 kV Lonikand – Kalwa S/C Line Generation Company Pvt. pune upto their plant Ltd.Olympia, Central Avenue, Hiranandani Business Park. 76 M/s Vidarbha Energy and Village 10 1) 132 kV lines from their plant to 132 kV Ghatangi Infrastructure P.Ltd, 4th Choramba, Tal. S/S. Floor, MG House, R.T. Ghatangi, Dist. Road, Civil Lines, Nagpur. Yeotmal. 77 M/s Mahalaxmi Vidyut At Konal, 2 X 5 MW 1) LILO on 220 kV Kolhapur-III – Phonda S/C Line Private Ltd, 363/11, Balaji Sindhudurg upto their plant Niwas,Deep Bangalow Chowk, Shiwaji Nagar, Pune-411 016.

32 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

CAPACITY SR. Location of the NAME OF APPLICANT APPLIED Proposed Evacuation Arrangement NO. Plant (MW)

78 M/s Malegaon Sahakari Village 14 (21) 1) LILO on 400 kV Lonikand – Kalwa S/CLine Sakhar Karkhana Ltd.At Shivajinagar,tal. upto thier plant Post. Shivajinagar,Tal. Baramati,Dist.Pune Baramati, Dist. Pune. 79 M/s M/s Greta Energy Ltd, Mul MIDC,Tal Mul, 15 1) 132 kV lines from their plant to 132 kV Mul S/S Station Road, Brahampuri- Dist. Chandrapur 441206. Dist. Chandrapur. 80 M/s Shree Sidhabali Ispat 10 (20) 1) 33 kV lines from their plant to 220 /33 kV Ltd, C-2 MIDC Area Chandrapur MIDC S/S Plot No.C-2, MIDC Area, Tadali,Dist. Tadali, Dist. Chandrapur- Chandrapur. 442406.

81 M/s Renuka Sugar Ltd, Balaji nagar, 26 (30) 1) LILO on 132 kV Pandharpur –Mangalwedha 7th Floor, Devchand Nandur, Tal. line House, Shiv Sagar Estate, Mangalweda Dist. Dr. Annie Besant Road, Solapur Worli, Mumbai-400 018.

82 M/s Kukadi Sahakari Pimpalgaon Pisa, 10 (16) 1) 132 kV Lines from their plant upto MSETCL Sakhar Karkhana Ltd, Tal. Shrigonda, proposed 220/132 kV Belwandi S/S At Pimpalgaon Pisa, Tal. Dist.Ahmednagar Shrigonda, Dist.Ahmednagar.

33 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

9. Wind Generation In this plan the aspect of wind generation is also covered. Existing wind generation is 2526MW out of which 260 MW generation (considering 10.28 % PLF) has been considered in the study. 10.28 % PLF is obtained during peak load conditions as per Demo results of Wind mills installed by MEDA

Table 9.1 - Existing Wind Generation as on 31.03.10

SR. NO DISTRICT CAPACITY (MW)

1 Satara 885

2 Sangli 700 3 Ahmednagar 108 4 Dhule 729 5 Nasik 90 6 Solapur 2 7 Sindhudurg 2 6 Beed 10 GRAND TOTAL 2526 TOTAL WIND POWER GENERATION 260 (10.28 % of total capacity)

34 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table 9.2 - Proposed Wind Generation Developerwise for the year 2010-11

Peak Capacity SR. NAME OF CAPACITY DISTRICT ( 80 %) Proposed Evacuation Arrangement NO. SITE (MW) MW in Monsoon M/s. Suzlon Energy Pvt. Ltd.

1) 220/33 KV, 2 X 100 MVA S/S. at 1 Satara 100 80 Sadawaghapur. Sadawaghapur 2) 220 KV DC Line Froam Munde S/S to Sadawaghapur S/S.-30KM. 3) 220 KV Line Bays at Mundhe S/S.-2 Nos 2 Satara 70 56

1) 132/33 KV, 3 X 50 MVA S/S. at Amberi 2) 132 KV DC Line Froam Phaltan S/S to Kas 3 Satara Amberi 127.5 102 S/S.- 24.5 KM. 3) 132 KV Line Bays at Phaltan S/S.-2 Nos

1) 132/33 KV, 2 X 50 MVA S/S. at Kas. 2) 132 KV DC Line Froam Satara Road S/S to 4 Satara Kas 100 80 Kas S/S.- 44KM. 3) 132 KV Line Bays at Satara Road S/S.-2 Nos

1) 132/33 KV, 1 X 50 MVA Transformer 5 Satara GudePanchgani 50 40 installation at Shira la S/S. 2) 33KV Line Bays at Shirala S/S.-2 Nos 1) 220/33 KV, 2 X 100 MVA S/S. at Nigade. 6 Satara GudePanchgani 170 136 2) 220 KV DC Line From Nigade S/S to LILO point.-40KM.

1) 132/33 KV, 1 X 50 MVA S/S at Wind Farm Site. 7 Satara Matrewadi 50 40 2) 132KV Line Bays at Kale S/S.-1 Nos 3) 132 KV line second ckt. Stringing - 29KM. 4) 132 KV SC on DC line - 20KM.

1) 220/33 KV, 1 X 50 MVA T/F at Hivare S/S. 2) 220 KV SC on DC Line Froam Hivare S/S to 8 Sangli Dhalgaon 50 40 Lamboti S/S.-125KM. 3) 220 KV Line Bays at Lamboti S/S.- 1 Nos

1) 220/33 KV, 1 X 100 MVA T/F installation at Ghatnandre S/S. 9 Sangli Ghatnandre 85 68 2) 220 KV line second ckt. Stringing from Ghatnandre to Vita.- 40KM. 3) 220 KV Line Bays at Vita S/S.- 1 No.

1) 220/33 KV, 1 X 50 MVA Transformer 10 Sangli Dhalgaon 40 32 installation at Vita S/S. 2) 33KV Line Bays at Vita S/S.- 2 Nos

35 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Peak Capacity SR. NAME OF CAPACITY DISTRICT ( 80 %) Proposed Evacuation Arrangement NO. SITE (MW) MW in Monsoon M/s. Suzlon Energy Pvt. Ltd. 1) 220/33 KV, 3 X 100 MVA S/S. at Hivare. 2) 220 KV DC Line From Hivare S/S to 11 Sangli Dhalgaon 300 240 Lamboti S/S.-125KM. 3) 220 KV Line Bays at Lamboti S/S.-2 Nos 1) 220/33 KV, 2 X 100 MVA S/S. at Mogarpada. 2) 220 KV SC on DC Line From Mogarpada S/S to Gangapur S/S.-25KM. 12 Dhule Brahamanwel 245 196 3) 220 KV DC on DC Line From Mogarpada S/S to Satana & Second Ckt. Stringing on Satana Malegaon Line 4)220 KV Line Bay at Satana & Malegaon & Gangapur S/S.-3 Nos 1) 132/33 KV, 2 X 50 MVA S/S at Wind Farm Site. 13 Dhule Balsane 100 80 2) 132KV Line Bays at Nardhane S/S.-2 Nos 3) 132 KV DC line - 70KM.

1) 132/33 KV, 1 X 50 MVA Transformer at 14 Nasik Sinnar 50 40 Khaprale S/S.

1) 220/33 KV, 2 X 100 MVA T/F Adwadi S/S.. 2) 220 KV DC Line From Adwadi S/S to 15 Nasik Panchpatta 170 136 Babhaleshwr S/S.-70KM. 3) 220 KV Line Bays at Babhaleshwr S/S.-2 Nos 2x50 MVA, 132/33 kV SS 16 Ahmednagar Kolgaon 100 80 132 kV DC ACSR Panther Line-28 KM 132 kV bay at 220/132 KV Nagar SS 1) 132/33 KV, 2 X 50 MVA S/S at Kolgaon Wind Farm Site. 17 Ahmednagar Kolgaon 127.5 102 2) 132KV Line Bay at Shrigonda & Karjat S/S.-1 No at each S/S. 3) 132 KV S/C on DC line - 25 KM. 1) 220/33 KV, 2 X 100 MVA S/S at Wind Farm. 18 Ahmednagar Sautada 170 136 2) 220 KV DC Line From wind farm S/S to Patoda S/S. 3) 220 KV Line Bays at Patoda S/S.-2 Nos

36 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Peak Capacity SR. NAME OF CAPACITY DISTRICT ( 80 %) Proposed Evacuation Arrangement NO. SITE (MW) MW in Monsoon M/s. Suzlon Energy Pvt. Ltd.

1) 132/33 KV, 2 X 50 MVA S/S at Gavalwadi Wind Farm Site. 19 Nasik Gavalwadi 100 80 2) 132KV Line Bays at Dindori S/S.-2 Nos 3) 132 KV DC line from Wind farm S/S.to Dindori S/S.

1) 132/33 KV, 1 X 50 MVA Transformer at 20 Nasik Khaprale 50 40 Khaprale S/S.

1) 132/33 KV, 2 X 50 MVA S/S at Chikhali Wind Farm Site. 21 Beed Sautada 100 80 2) 132KV Line Bays at Raimoha S/S.-2 Nos 3) 132 KV DC line - 28KM. 1) 220/33 KV, 2 X 100 MV A S/S. 2) 220 KV DC Line From wind farm S/S to 22 Beed Khandke 170 136 Ahmednagar. 3) 220 KV Line Bays at Ahmednagar S/S.-2 Nos 1) 220/33 KV, 2 X 100 MVA S/S. 2) 220 KV DC Line From wind farm S/S to 23 Pune Lonavala 170 136 Urse. 3) 220 KV Line Bays at Urse S/S.-2 Nos 1) 220/ 33 KV, 2 X 100 MVA S/S. 2) 220 KV DC Line From wind farm S/S to 24 Pune Lonavala 200 160 Chakan S/S. 3) 220 KV Line Bays at Chakan S/S.-2 Nos 1) 220/33 KV, 3 X 100 MVA S/S. at Gangapur. 2) 220 KV SC Line From Gangapur S/S to Valve S/S. 25 Nandurbar Chakla 255 204 3) 220 KV DC Line Froam Gangapur S/S to Satana & Malegaon S/S. 4) 220 KV Line Bay at Valve, Satana & Malegaon S/S. - 1 No. at each S/S.

37 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Peak Capacity SR. NAME OF CAPACITY DISTRICT ( 80 %) Proposed Evacuation Arrangement NO. SITE (MW) MW in Monsoon M/s. Suzlon Energy Pvt. Ltd. 1) 33 KV DC Panther Line From Ranala S/S 26 Nandurbar Chakla 50 40 to Wind Farm. 2) 33 KV 2 No. Bays at Nandurbar S/S.

1) 33 KV SC Dog Line From Ranala S/S to 27 Nandurbar Chakla 10 8 Wind Farm.- 5KM. 2) 33 KV 1 No. Bay at Ranala S/S.

1) 132/33 KV, 2 X 50 MVA S/S at Wind Farm Site. 28 Aurangabad Kankora 121 96.8 2) 132KV DC Line from Wind Farm S/S. to LILO point - 8KM. 3) 33 KV Bay- 1No. TOTAL WIND GENERATION OF M/S. SUZLON ENERGY PVT.LTD. : - 3331 MW M/s. Enercon India Pvt. Ltd. 1) 2 x 50 MVA, 132-110/33 kV Transformer at Bhayara (Andhra Lake) S/S. 2) 132 kV DC line on DC Tower using 0.2 1 Pune Andhra Lake 100 80 ACSR Panther Conductor from Proposed Wind Farm SS Bhayara to Existing LILO on 132-110 kV DC line from Talegaon – Lonavala of MSETCL's – 20 kms.

1) 132-110 kV Line Bay at 132-110/33 kV 2 Pune Andhra Lake 25 20 Bhayara SS – 2 Nos. 2) 33 kV Outlets – 08 Nos

1) 2 x 50 MVA, and 1 x 25 MVA , 132-110 / 33 kV Transformer at Wind Farm 2) LILO on 110 kV Sangola – Oglewadi 3 Satara Khanapur 100 80 Line to Wind Farm. 3) 110 kV Line Bays at Wind Farm S/S.– 02 Nos 1) 2 x 50 MVA, 132/33 KV S/S at Chawaneshwar 2) LILO on 4 Satara Chavaneshwar 76.8 61.44 132 KV Lonand - Wai line 3) 33 KV outlets - 3 nos. at Chavaneshwar & 01 no at Satara Road SS

38 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Peak Capacity SR. NAME OF CAPACITY DISTRICT ( 80 %) Proposed Evacuation Arrangement NO. SITE (MW) MW in Monsoon M/s. Enercon India Pvt. Ltd. 1) 2 x 50 MVA, 132/33 KV T/F at Ghoti S/S 2) 132 KV D/C line from M/s. Suzlon S/S 5 Nashik Aundhewadi 75 60 located near by Sinnar 3) 33 KV outlets - 4 nos. 4) Space for 33 KV outlets -8 nos. 1) 2 x 100 MVA, 220/33 kV TF at Wind Farm Site ( Ghargoti). 2) LILO on 220 kV Talandge - Sawantwadi 6 Kolhapur Vedganga 200 160 S/C line at Ghargoti. 3) 220 kV Bays at Ghargoti : 2 Nos. 4) 33 kV bays at Ghargoti : 14 Nos.

1) 33 kV D/C line from Wind farm site to 110/33 kV Kavathemahakal S/s. 7 Sangli Dongerwadi 32 25.6 2) 33 kV Bays at 110/33 kV Kavathemahakal S/s. : 2 Nos.

TOTAL WIND GENERATION OF M/S. ENERCON INDIA PVT.LTD. : - 608.8 MW M/s. Shri Maruti Wind Park Developoers Pvt. Ltd.

1) 1 x 25 MVA, 132/33 kV TF at 132 kV Amberi, Tal. 1 Satara 24 19.2 Aundh. 2) 33 kV Bays - 2 Khatav Nos. at 132/33 kV Aundh.

1) 33 kV S/C line from Wind farm site to Amberi, Tal. 110/33 kV Satara Road S/s. 2 Satara 10 8 Khatav 2) 33 kV bays at 110/33 kV Satara Road S/s.: 1 No. 1) 33 kV S/C line from Wind farm site to Bhud/Kaledhon, 132-110/33 kV Mayni S/s. 3 Satara Tal. 25 20 2) 1 x 25 MVA, 132-110/33 kV TF at 110/33 Khatav/Man kV Mayni S/s. 3) 33 kV Bay at Mayni : 1 No.

1) LILO of 110 kV Mayni - Dighanchi S/C Bhud/Kaledhon, line at Wind farm Site. 4 Satara Tal. 75 60 2) 1 x 50 & 1 x 25 MVA, 132-110/33 kV TF Khatav/Man at Wind farm site.

39 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Peak Capacity SR. NAME OF CAPACITY DISTRICT ( 80 %) Proposed Evacuation Arrangement NO. SITE (MW) MW in Monsoon

M/s. Shri Maruti Wind Park Developoers Pvt. Ltd. 1) 1 x 50 MVA, 132-110/33 kV TF at Jath S/s. 2) 33 kV D/C line with 0.2 ACSR Panther Vaspeth, Tal. 5 Sangli 40 32 conductor from wind farm site to 110/33 kV Jath Jath S/s. 3) 33 kV bays at 110/33 kV Jath S/s. : 2 Nos. 1) TF : 1 x 50, 1 x 25 MVA, 132-110/33 kV at 110/33 kV Valsang wind farm s/s. Vaspeth, Tal. 2) 110 kV S/C line from wind farm s/s to 6 Sangli 50 40 Jath LILO on existing 110 kV Jath - Sankh line of MSETCL. 3) 33 kV outlets : 3 nos. 1) 132 kV D/C line from Wind farm site to 132 kV Sangola S/S, 2) TF : 2 x 50, 1 x 25 MVA, 132/33 kV at Vaspeth, Tal. 7 Sangli 100 80 wind farm S/S. Jath 3) 132 kV Line bay at 132 kV Sangola : 2 nos 4) 132 kV line bay at 132 kv wind farm s/s. 1) TF : 2 x 50 MVA, 220/33 kV at proposed 220 kV Patoda s/s. 2) 2 nos. of 33 kV D/C lines from wind farm 8 Beed Sautada 80 64 s/s to proposed 220 kV Patoda s/s. of MSETCL. 3) 33 kV line bays at 220/33 kV Patoda s/s : 4 nos. TOTAL WIND GENERATION OF M/S. ENERCON INDIA PVT.LTD. : - 404 MW M/s. T.S. Wind Power Developers Pvt. Ltd. 1) 1 x 25 MVA, 132/33 kV TF at 132 kV Aundh S/s. Amberi, Tal. 1 Satara 25 20 2) 33 kV D/C line from Wind farm Site to Khatav 132/33 kV Aundh S/s. 3) 33 kV byas at 132/33 kV Aundh : 2 Nos. 1) LILO of 220 kV Vita - Solapur S/C line at Wind farm Site. Bhud, Tal. 2 Satara 100 80 2) 2 x 50 MVA, 220/33 kV TF at wind farm Man/Khatav site. 3) 33 kV bays at wind farm site S/s. : 5 Nos.

40 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Peak Capacity SR. NAME OF CAPACITY DISTRICT ( 80 %) Proposed Evacuation Arrangement NO. SITE (MW) MW in Monsoon M/s. T.S. Wind Power Developers Pvt. Ltd. 1) LILO of 220 kV Karad - Kolhapur Ckt. IV at Wind farm Site. 3 Satara Gudepachgani 100 80 2) 2 x 50 MVA, 220/33 kV TF at Wind Farm Site. 3) 33 kV Bays at Wind Farm Site : 5 Nos. 1) 1 x 50 MVA, 220/33 kV TF at 220 kV Vankuswade S/s. 2) 33 kV D/C Line from Wind Farm Site to 4 Satara Vankuswade 25 20 220/ 33 kV Vankuswade S/s. 3) 33 kV Bays at 220/33 kV Vankuswade S/s. : 2 Nos. TOTAL WIND GENERATION OF M/S. T.S.WIND POWER DEVELOPERS PVT.LTD. : - 250 MW M/s. Acorn Properties Pvt. Ltd. 1) 1 x 25 MVA, 132/33 kV TF at 132 kV Amberi, Tal. 1 Satara 24 19.2 Aundh. 2) 33 kV Bays Khatav - 2 Nos. at 132/33 kV Aundh. 1) LILO of 110 kV Satara Road - Satara MIDC S/C line at Wind farm site. Amberi, Tal. 2 Satara 50 40 2) 2 x 50 MVA, 132-110/33 kV TF at Khatav Wind farm site. 3 ) 33 kV bays at wind farm site : 5 Nos. TOTAL WIND GENERATION OF M/S. ACORN PROPERTIES PVT.LTD. : - 74 MW M/s. Theolia Wind Pvt. Ltd.

1 Sangli Sankh & Jath 20 16 1) 2x33KV bay at 132KV Sankh S/S

2 Sangli Sankh & Jath 10 8 1) 1x33kv bay at 110KV Jath S/S

1) 2 X 50 MVA, 132/33 kV TF at Wind Famr Site. 2) 132 kV D/C line from Wind Farm Site 3 Sangli Vaspet 100 80 - 220 kV Jath 3) 2 x 132 KV bays at 220 Jath S/s. 4) 132 kV bays at Wind Farm S/s. : 2 Nos. TOTAL WIND GENERATION OF M/S. THEOLIA WIND PVT.LTD. : - 130 MW

41 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Peak Capacity SR. NAME OF CAPACITY DISTRICT ( 80 %) Proposed Evacuation Arrangement NO. SITE (MW) MW in Monsoon M/s. Shri Ram EPC Pvt. Ltd. 1) 1 x 25 MVA, 132/33 kV TF at 132 kV Aundh., Amberi, Tal. 2) 33 kV D/C line from Wind Farm Site 1 Satara 15 12 Man to 132/33 kV Aundh S/s. 3) 33 kV Bays - 2 Nos. at 132/33 kV Aundh. 1) TF : 2 x 50 MVA, 132-110/33 kV at Amberi s/s w ith bays. 2) LILO for Karad - Dighanchi 110 kV line 2nd ckt. At Mayni s/s. 2 Satara Amberi 90 72 3) 110 kV bays at Mayni - 4 nos. & at Amberi - 2 nos. 4) 33 kV outlets at Amberi s/s - 8 nos 5) 132/110 kV line from Amberi s/s to Mayni s/s. TOTAL WIND GENERATION OF M/S. SHRI RAM EPC PVT.LTD. : - 105 MW M/s. RRB Pvt. Ltd. 1) TF : 3 x 50 MVA, 132/33 kV at 132 kV Mahir ( Wind Farm Site ) s/s. 2) 132 kV Mahir - Nampur D/C line. 1 Nashik Mahir 75 60 3) 132 kV Dongarpada - Mahir SCDC line. 4) 132 kV Mahir - Sakri D/C Line. 5) 33 kV outlets : 18 nos. 1) TF : 2 x 50 MVA, 132/33 kV at Ayne(Tek) wind farm s/s. Ayne 2 Dhule 75 60 2) 132 kV Dule-II -- Ayne(Tek) D/C line. ( Tek) 3) 132 kV line bays - 4 nos. 4) 33 kV outlets - 4 nos. TOTAL WIND GENERATION OF M/S. RRB PVT.LTD. : - 150 MW

TOTAL PROPOSED WIND POWER GENERATION : - 5273 MW TOTAL PROPOSED WIND POWER GE NERATION CONSIDERED IN PLAN ( 10.28 % of total capacity ) : - 542 MW TOTAL (EXISTING + PROPOSED) WIND POWER GENERATION (10.28 % of total capacity) : - 260 + 542 = 802 MW

42 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table – 10 - Power scenario in Maharashtra (including Mumbai) Generation Available By - A. Mahagenco (Table - 3.3) B. State Govt/Inter State /MAHADISCOM (Table - 4.2) C. Central Sector (Table - 5.2) D. Mumbai (Table- 7) E. IPP (Table- 8.2.2) F. Wind Generation(Table-9.2)

Peak Total Total Total Shortfall (-) Demand Year A B C D E F A+B+C+D+E+F Demand / Surplus (Non (Availibility)* (coincident) (+) (MW) coincident) (coinc)

2010-11 8775 2087 3582 3130 2281 802 20657 20795 27449 (-)138

2011-12 9414 2166 4422 3342 4304 802 24450 22635 29199 (+)1815

2012-13 11497 3228 5372 3571 7154 802 31624 24638 31291 (+)6986

2013-14 12113 3228 5838 3817 7244 802 33042 26610 32996 (+)6432

2014-15 13301 3228 5838 4174 7244 802 34587 28738 35067 (+)5849

Note – * Availability Considered subject to timely commissioning of upcoming generation

Graph – Present and Future scenario in Maharashtra

43 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Maharashtra has catered Peak demand of 14,952 MW as against the requirement of 19,120 MW during peak load condition during the year 2009-10. With the capacity addition from State Generation companies and Central Generation companies with Generation from IPP’s, the demand and availability that would prevail in each year would be:

Peak Demand Peak Demand (Non- Availability Peak Shortfall (-) / Year (Coincidence) Surplus (+) (MW) Coincidence) (MW) (MW) (MW) (coinc)

2010-11 20795 27449 20657 (-) 138

2011-12 22635 29199 24450 (+) 1815

2012-13 24638 31291 31624 (+) 6986

2013-14 26610 32996 33042 (+) 6432

2014-15 28738 35067 34587 (+) 5849

Load Growth The draft STU Five year transmission plan was formulated taking in to account previous years load growth and upcoming load centers SEZ’s, New Cities, Malls etc Load Growth is considered as per District wise Load forecasting carried out by this office.

44 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Methodology The EHV network of 400 kV, 220 kV and 132 kV networks are modelled in detailed along with their respective transformer capacities. To make critical analysis of the network in terms of voltage profile and network loading, load flow & Short Circuit studies are carried out on MiPower Software. The simulation was carried out by matching the power flows at 400 kV and 220 kV levels along with voltage profile at various buses The standard practices followed by CEA as well as the guidelines by MERC have been incorporated while conducting the simulation studies which are as follows:

CEA – Transmission system planning & design criteria:

Central Electricity Authority (CEA) has evolved transmission system planning & design criteria for the National Electricity Plan. The planning criteria as per CEA are

• In the national approach N-2 criteria may be adopted for large generating complex (3000 MW or above) and multi line corridors (3 D/C lines or more), on case-to-case basis. Whereas, regional planning may be continued with N-1 criteria. However, while N-1 would be applied to test withstand without necessitating load shedding or rescheduling of generation during steady state operation, N-2 would be applied to test withstand without necessitating load shedding but could be with rescheduling of generation during steady state operation.

• The steady state voltage limit on 400kV system is within 380kV to 420kV.

The Maharashtra State Grid Code: Maharashtra Electricity Regulatory Commission (MERC) has published the Final State Grid code 2006 which lays down the rules, guidelines and standards to be followed by various agencies and participants in the intra –State transmission system to plan, develop, maintain and operate the intra-state transmission system apart of Western Regional Grid System, in the most efficient, reliable and economic manner, while facilitating a healthy competition on in the generation and supply of electricity. Section 9 of the Grid Code prescribes the planning criterion to be followed for planning the transmission system. The planning criterions as per the regulation are:

45 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

9.1 The planning criterion shall be based on the security philosophy on which the ISTS (Inter State Transmission System) has been planned. The security philosophy may be as per the Transmission Planning Criteria and other guidelines as given by the authority provided that State Transmission Utility shall carry out appropriate system studies while developing the transmission system plan. 9.2 The intra state transmission system, as a general rule, shall be capable of With standing and be secured against the following contingency outages without Necessitating load shedding or rescheduling of generation during Steady State Operation: 1) Outage of a 110kV /132 kV D/C line or, 2) Outage of a 220 kV D/C Line or, 3) Outage of a 400 kV S/C line or, 4) Outage of a single Interconnecting Transformer or, 5) Outage of a one pole of HVDC Bi-pole or, 6) Outage of a 765 kV S/C Line. Provided that the above contingencies shall be considered assuming a pre-contingency system deletion (planned outage) of another 220 kV D/C line or 400 kV S/C line in another corridor and not emanating from the same substation.

9.3 All the Generating Units may operate within their reactive capability curves and the network voltage profile shall be maintained within voltage limits specified.

9.4 The intra-State transmission system shall be capable of withstanding the loss of most severe single in feed without loss of stability

9.5 Any one of the events defined in the Regulation 9.2 above shall not cause:

(i) Loss of supply;

(ii) Prolonged operation of the system frequency below & above specified limits;

(iii) Unacceptable high or low voltage;

(iv) System instability;

(v) Unacceptable overloading of ISTS elements.

46 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

9.6 In all substations (66kV/110kV/132kV and above), except HVDC, suitable number and capacity of transformers shall be provided to have adequate redundancy required to maintain firm capacity at the substation. In HVDC substations, at least one spare converter/inverter transformer shall be kept ready to use at any time.

Explanation – for the purpose of Regulation 9.6, the term firm capacity shall mean the

minimum transformation capacity available at the substation in case of outage of

any one transformer.

9.7 State Transmission Utility shall carry out planning studies for Reactive Power compensation of ISTS including reactive power compensation at the in-State Generating Station’s switchyard.

Section 22.24 of the Grid Code/CEA Transmission planning criteria describes the voltage profile as per

Voltage (kV – rms) Nominal Maximum Minimum 765 800 728 400 420 380 220 245 198 132 145 122 66 73 60

With the operational study as initial conditions, prioritization study was carried out with the following assumptions  Priority i. Generation Evacuation schemes – High priority ii. Meeting the Demand iii. Improving quality of power supply iv. Improving reliability satisfying grid code security requirements

 While carrying out system requirement, network of PGCIL (existing and proposed) is also considered. The details of the same are given below

47 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

11. PGCIL NETWORK IN MAHARASHTRA Table -11.1- Existing Network of PGCIL

Sr. Name of s/s Total Scope of Work No. PGCIL'S Existing S/s’s and associated Lines in Maharashtra 1 400KV Boisar (PG) 1 400/220 KV, 2X315 MVA ICT with bays 2 400 KV Tarapur - Boisar(PG) D/C Line LILO on 400 KV Padghe-I - Gandhar S/C 3 Line at Boisar (PG) 4 400 KV Tarapur – Padghe-I D/C Line 2 400KV Bhadravati (PG) 400 KV Bhadravati (PG) – Chandrapur-I 1 4 ckts. 2 400 KV Bhadravati (PG) - Raipur 3 ckts 3 400 KV Bhadravati (PG) - Bhilai S/C Line +/-500 KV Bhadravati (PG)-Ramagundam 4 BTB HVDC 3 400KV Wardha (PG) Establishment of New 400/220 KV, 2X315 1 MVA ICT with bays 2 400 KV Wardha (PG) – Akola-I D/C Line 3 400 KV Akola-I – Aurangabad-I D/C Line 765 kV 1st S/C Seoni (PG)–Wardha (PG) 4 line (Initially to be operated at 400kV) PGCIL'S E xis ting Interstate Lines in Maharashtra 1 400 KV Bhilai – Koradi-I S/C Line 2 400 KV Satpur – Koradi-I S/C Line 3 400 KV Khandva – Dhule-I D/C Line 4 400 KV Sardar Sarovar – Dhule-I D/C Line 5 400 KV Kolhapur - Mhapusa D/C Line

48 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table -11.2 - Proposed Network of PGCIL

Sr. Length Month of Name of S/s Total Scope of Work No. (km) Comm.

1 400KV Wardha (PG) 765 kV 2nd S/C Seoni (PG)–Wardha (PG) 1 275 Mar-11 (Comm.) line (Initially to be operated at 400kV) 400 kV Wardha (PG)–Parli (PG) (Quad.) D/C 2 363 Dec-10 Line 3 400 kV Raipur (PG)–Wardha (PG) D/C Line 363 Mar-11 2 400KV Parli (PG) 1 400 kV Bhadravati (PG)-Parli (PG) D/C Line 380 July-10 Switching Station (Sept-10) 2 400 kV Parli (MSEB) – Parli (PG) D/C Line 7 July-10 3 400 kV Parli (PG) – Pune (PG) D/C Line 308 June-11 4 400 kV Parli (PG) - Solapur (PG ) D/C Line 196 May-11 3 400 KV Pune (PG) Establishment of New 400/220 KV, 2X315 1 July-10 (July-10) MVA ICT with bays (ICT-1 Errected) 400 kV Pune (PG) – Aurangabad-I (MSEB) 2 225 Apr-11 D/C Line LILO of 400 kV Lonikand (MSEB) – Kalwa 3 24 Feb-10 (MSEB) D/C at Pune (PG ) 4 400 KV South Solapur Establishment of New 400/220 KV, 2X315 1 May-10 (PG) MVA ICT with bays (ICT-1 Errected) (May-10) 400 kV South Solapur (PG) – 2 189 May-11 Kolhapur(MSEB) D/C Line LILO of 400 kV Solapur (MSEB) – Karad 3 (MSEB) S/C at South Solapur (PGCIL ) (25 27 May-10 Km D/C + 2Km S/C) 5 400 KV Navi Mumbai Establishment of New 400/220 KV, 2X315 1 (PG) MVA ICT with bays 2 400 kV Navi Mumbai (PG) – Vapi D/C Line 185 Mar-11 LILO of 400 kV Pune (PG) – Kalwa (MSEB) 3 10 Mar-11 S/C at Navi Mumbai (PG ) 6 400 KV GIS New 400 kV D/C Line from Navsari (PG) will be 1 220 Oct-12 location near Mumbai terminated at Boisar (PG).

49 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

The transmission system proposed and indicated in the Minutes of the 29th meeting of standing Committee on Power System Planning in western region.

 Transmission System within WR associated with New IPP projects in Chattishgarh (i) Raipur Pooling station- Wardha 765 kV 2XD/C or 4XS/C. (ii) Wardha- Aurangabad (PG) 765 kV 2XD/C or 4XS/C. (iii) Aurangabad (PG) - Padge(PG) 765 kV 1XD/C or 2XS/C. (iv) Establishment of 765/400 kV 2x1500 MVA substations at Aurangabad and Padghe (GIS) (v) Aurangabad (PG)-Khargar 400 kV D/C (quad) (vi) Padghe (PG)- Padghe 400 kV D/C (quad) (vii) Vadodra-Asoj (GETCO) 400 kV D/C (quad) (viii) Establishment of 2X315 MVA, 400/220 kV Dhule (PG). (ix) Dhule (PG) – Dhule (IPTC) 400 kV 2X D/C (quad) (x) Dhule (PG) – Nasik (MSETCL) 400 kV D/C (quad) (xi) Dhule (PG) – Malegaon (MSETCL) 400 kV D/C (quad) (xii) + 600 kV 4000 MW HVDC bipole between Raigarh pooling station (Kotra) – Dhule (PG) with mettalic return conductor. (xiii) 4000 MW, + 600 kV HVDC bipole terminal each at Raigarh pooling station (Kotra) and Dhule (PG). (xiv) Aurangabad- Dhule (IPTC) 765 kV S/C (xv) Dhule (IPTC) – Vadodara (PG) 765 kV S/C (xvi) Establishment of 765/400 kV 2x1500 MVA substations at Dhule (IPTC) (xvii) Dhule (IPTC) – Dhule (MSETCL) 400 kV D/C (quad)

50 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

 Transmission system associated with Krishnapatnam (5x800 MW) (WR Portion) (i) Raichur – Solapur 765 kV S/c (ii) Solapur – Pune 765 kV S/c (iii) Establishment of new 765/400 kV substations at Solapur & Pune with 2x1500 MVA transformation capacity

 Tr. System associated with South-West interconnection (i) Establishment of 2 x 500MW HVDC back-to-back station at Kolhapur (ii) Narendra – Kolhapur 400 kV D/c line with Lapwing conductor (iii) LILO of both circuits of existing Kolhapur –Mapusa 400 kV D/c line at (iv) Kolhapur HVDC back-to-back station

51 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Spill Over Upto Year 2009-10

In the year 2009-10, it is estimated that Maharashtra met a demand of about 14952 MW considering the available generation against the requirement of 19120 MW at peak load condition. The substation requirement for the year for meeting the demand is tabulated in Table 12, Augmentation in Table 13 & Additional link lines in Table 14

Table: 12 - No. of Substation requirement upto year 2009-10 Sr. Voltage Level (kV) Spill over No 1 400 6 2 220 42 3 132 31 4 110/100 2 Total 81

Table 13: No. of Augmentations upto year 2009-10

Table: 13.1 - No. of Augmentation by Addition of transformers upto year 2009-10 Sr. Voltage Ratio Spill over No 1 400/220 11 2 220/132, 110 33 3 220/33, 22 70 4 132/33 147 5 110/33, 22 15 Total 276

52 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 13 .2 - No. of Augmentation by Replacement of transformer upto year 2009-10 Sr. Voltage Ratio Spill over No 1 400/220 2 2 220/132, 110 41 3 220/33, 22 9 4 132/33 116 5 110/33, 22 35 Total 203

Table 14: No. of Additional Link Lines required upto year 2009-10

Table: 14 .1 - No. of Additional link lines upto year 2009-10 for S/S’s where only single source is available Sr. Voltage (kV) Spill over No 1 400 - 2 220 4 3 132 32 4 110-100 4 Total 40

Table: 14 .2 - No. of Additional link lines upto year 2009-10 to meet Demand without Load shedding and to insure reliability and quality of supply Sr. Voltage (kV) Spill over No 1 400 - 2 220 11 3 132 11 4 110-100 6 Total 28

53 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 14 .3 - No. of Additional link lines upto year 2009-10 for evacuation arrangement Sr. Voltage (kV) Spill over No 1 400 - 2 220 7 3 132 2 4 110-100 - Total 9

Table: 14 .4 - No. of Additional link lines upto year 2009-10 for New substations to have alternate source Sr . Voltage (kV) Spill over No 1 400 - 2 220 1 3 132 6 4 110-100 - Total 7

List of substations commissioned during 2009-10.

Sr Name of Voltage District Zone No. substation level

1) Chakan 400 KV Pune Pune 2) Khaparkheda 400 KV Nagpur Nagpur 3) Bhusawal 400 KV Jalgaon Vashi 4) Knowledge Park 220 KV Thane Vashi Airoli 5) Pahur 132 KV Akola Amaravati

List of substations proposed for 2008-09 but could not commission during the year 2009-10 (Spill Over).

Sr No. Name of substation Voltage level Dist rict Zone

1) Vasai 220 KV Thane Vashi

2) Bapgaon 220 KV Thane Vashi

3) Bhandup (GIS) 220 KV Thane Vashi

54 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

4) Kudus 220 KV Thane Vashi

5) Bhiwandi-III 220 KV Thane Vashi

6) Bhiwandi-IV 220 KV Thane Vashi

7) Khadakwasala 220 KV Pune Pune

8) Talegaon 220 KV Pune Pune

9) Kharadi (GIS) 220 KV Pune Pune

10) Rajgurunagar 220 KV Pune Pune

11) Shendra 220 KV Aurangabad Aurangabad

12) Hingoli 220 KV Hingoli Aurangabad

13) Paranda 220 KV Osmanabad Aurangabad

14) Patoda 220 KV Beed Aurangabad

15) Wani 220 KV Yeotamal Amaravati

16) Mankapur 220 KV Nagpur Nagpur

17) New Pardi 220 KV Nagpur Nagpur

18) New Butibori 220 KV Nagpur Nagpur

19) Matradevi* 220 KV Chandrapur Nagpur

20) Bibawewadi 132 KV Pune Pune

21) Rasta Peth 132 KV Pune Pune

22) Navi Vesh 132 KV Solapur Pune

23) Badanapur 132 KV Jalna Aurangabad

24) Shelu 132 KV Pabhani Aurangabad

25) Ghatanji 132 KV Yeotamal Amaravati

26) Barshi Takali 132 KV Akola Amaravati

27) Bharshingi 132 KV Amaravati Amaravati

28) Jam 132 KV Wardha Nagpur

55 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

29) Lakhandur 132 KV Bhandara Nagpur

30) Lendra (GIS) 132 KV Nagpur Nagpur

31) Serum Institute* 132 KV Pune Pune

32) Mumbra 100 KV Thane Vashi

33) Neral 100 KV Raigad Vashi

*Covered under ORC

List of substations proposed for 2009-10 but could not commission during the year.

Sr No. Name of substation Voltage level District Zone

1) Lonikand-II 400 KV Pune Pune

2) Nanded 400 KV Aurangabad Aurangabad

3) Warora 400 KV Nagpur Nagpur

4) Ulhasnagar 220 KV Thane Vashi

5) Vashi 220 KV Thane Vashi

6) Goregaon 220 KV Mumbai Vashi

7) South Solapur 220 KV Solapur Pune

8) Akurdi 220 KV Pune Pune

9) Jath 220 KV Sangli Karad

10) Mudhal titha 220 KV Kolhapur Karad

11) Lonand (MIDC) 220 KV Satara Karad

12) Phaltan (MIDC) 220 KV Satara Karad

13) Kadegaon 220 KV Sangli Karad

14) Pimpalgaon 220 KV Nasik Nasik

15) Bhambori 220 KV Jalgaon Nasik

16) Kopargaon 220 KV Ahamadnagad Nasik

17) Sinnar- II 220 KV Nasik Nasik

56 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

18) Valandi 220 KV Latur Aurangabad

19) Tuljapur 220 KV Osmanabad Aurangabad

20) Narsi -II 220 KV Latur Aurangabad

21) Malegaon 220 KV Washim Amaravati

22) Nandgaon Peth 220 KV Amaravati Amaravati

23) Ghatodi 220 KV Yeotamal Amaravati

24) Uppalwadi 220 KV Nagpur Nagpur

25) Ballarshah 220 KV Chandrapur Nagpur

26) Dapcheri 132 KV Thane Vashi

27) Someshwarnagar 132 KV Pune Pune

28) Borivel 132 KV Pune Pune

29) Karajagi 132 KV Solapur Pune

30) Waghadari 132 KV Solapur Pune

31) Soregaon 132 KV Solapur Pune

32) Shankarnagar 132 KV Solapur Pune

33) Ruddewadi 132 KV Solapur Pune

34) Taharabad 132 KV Nasik Nasik

35) Vadgire 132 KV Ahmadnagar Nasik

36) Ghargaon 132 KV Ahmadnagar Nasik

37) Soygaon 132 KV Aurangabad Aurangabad

38) Mahakala 132 KV Jalna Aurangabad

39) Niwali 132 KV Latur Aurangabad

40) Mahur 132 KV Nanded Aurangabad

41) Pandharkavada 132 KV Yeotamal Amaravati

42) Deolgaon Raja 132 KV Buldana Amaravati

57 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

43) Murtizapur 132 KV Akola Amaravati

44) Jafarabad 132 KV Gadchiroli Nagpur

45) Pulgaon 132 KV Wardha Nagpur

46) Sahuli 132 KV Nagpur Nagpur

47) Allapalli 132 KV Gadchiroli Nagpur

48) Yetapalli 132 KV Gadchiroli Nagpur

Conclusion According to Load flow studies overloading can be removed by constructing proposed 400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing S/s.

58 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Year 2010-11

In the year 2010-11, it is estimated that Maharashtra will meet a demand of about 20657 MW considering the available generation against the requirement of 20795 MW at peak load condition. The substation requirement for the year for meeting this demand is tabulated in Table 15, Augmentation in Table 16 & Additional link lines in Table 17

Table: 15 - No. of Substation requirement for the year 2010-11 Sr. Voltage Level (kV) 2010-11 No 1 400 5 2 220 13 3 132 14 4 110 - Total 32

Table 16: No. of Augmentations for the year 2010-11

Table: 16 .1 - No. of Augmentation by Addition of transformers for the year 2010-11 Sr. Voltage Ratio 2010-11 No 1 400/220 - 2 220/132, 110 3 3 220/33, 22 12 4 132/33,22,11 8 5 110/33, 22 1 Total 24

59 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 16 .2 - No. of Augmentation by Replacement of transformer for the year 2010-11 Sr. Voltage Ratio 2010-11 No 1 400/220 - 2 220/132, 110 22 3 220/33, 22 19 4 132/33 13 5 110/33, 22 6 Total 60

Table 17: No. of Additional Link Lines required for the year 2010-11

Table: 17 .1 - No. of Additional link lines for the year 2010-11 for S/S’s where only single source is available Sr. Voltage (kV) 2010-11 No 1 400 - 2 220 8 3 132 15 4 110-100 3 Total 26

Table: 17 .2 - No. of Additional link lines for the year 2010-11 to meet Demand without Load shedding and to insure reliability and quality of supply Sr. Voltage (kV) 2010-11 No 1 400 - 2 220 8 3 132 13 4 110-100 1 Total 22

60 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 17 .3 - No. of Additional link lines for the year 2010-11 for evacuation arrangement Sr. Voltage (kV) 2010-11 No 1 400 - 2 220 3 3 132 - 4 110-100 - Total 3

Table: 17 .4 - No. of Additional link lines for the year 2010-11 for New substations to have alternate source Sr. Voltage (kV) 2010-11 No 1 400 - 2 220 4 3 132 6 4 110-100 - Total 10

List of substations proposed for commissioning during 2010-11.

Sr No. Name of substation Voltage level District Zone

1) Koradi -II 400 KV Nagpur Nagpur

2) Bhusawal 400 KV Jalgaon Nasik

3) Hinjewadi 400 KV Pune Pune

4) Karad -II 400 KV Satara Karad

5) Kesurdi 400 KV Satara Karad

6) Palghar 220 KV Thane Vashi

7) Biosar MIDC 220 KV Thane Vashi

8) Vile Bhagad 220 KV Raigad Vashi

9) Yeolewadi 220 KV Pune Pune

(VSNL Dighi)

61 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

10) Kondhawa 220 KV Pune Pune

11) Hamidwada 220 KV Kolhapur Karad

12) Kalwan 220 KV Nasik Nasik

13) Sayane 220 KV Nasik Nasik

14) Deogaon Rangari 220 KV Aurangabad Aurangabad

15) Bhokardan 220 KV Jalna Aurangabad

16) Anjangaon 220 KV Amaravati Amaravati

17) Tadali 220 KV Chandrapur Nagpur

18) Katol - II 220 KV Nagpur Nagpur

19) Nimboni 132 KV Solapur Pune

20) Mhaswad 132 KV Satara Karad

21) Ghodegaon 132 KV Ahmednagar Nasik

22) Panchincholi 132 KV Latur Aurangabad

23) Shengaon 132 KV Hingoli Aurangabad

24) Sonpeth 132 KV Parbhani Aurangabad

25) Jalgaon Jamod 132 KV Buldana Amaravati

26) Yeotmal MIDC 132 KV Yeotmal Amaravati

27) Jat Tirodi 132 KV Nagpur Nagpur

28) Morgaon Arjuni 132 KV Gondia Nagpur

29) Seloo 132 KV Wardha Nagpur

30) Paghora* 132 KV Nagpur Nagpur

31) Mokhabardi 132 KV Nagpur Nagpur

*Covered under ORC Conclusion According to Load flow studies overloading can be removed by constructing proposed 400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing S/s.

62 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Year 2011-12

In the year 2011-12, it is estimated that Maharashtra will meet a demand of about 22635 MW considering the available generation of 24450 MW indicating surplus position of state. The substation requirement for the year for meeting this demand is tabulated in Table 18, Augmentation in Table 19 & Additional link lines in Table 20

Table: 18 – No. of Substation requirement for the year 2011-12 Sr. Voltage Level (kV) 2011-12 No 1 400 2 2 220 14 3 132 3 4 110/100 - Tot al 19

Table 19: No. of Augmentations for the year 2011-12

Table: 19 .1 - No. of Augmentation by Addition of transformers required for the year 2011-12 Sr. Voltage Ratio 2011-12 No 1 400/220 3 2 220/132, 110 - 3 220/33, 22 12 4 132/33 14 5 110/33, 22 2 Total 31

63 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 19 .2 - No. of Augmentation by Replacement of transformer for the year 2011-12 Sr. Voltage Ratio 2011-12 No 1 400/220 1 2 220/132, 110 5 3 220/33, 22 12 4 132/33 9 5 110/33, 22 0 Total 27

Table 20 : No. of Additional Link Lines required for the year 2011-12

Table: 20.1 - No. of Additional link lines for the year 2011-12 for S/S’s where only single source is available. Sr. Voltage (kV) 2011-12 No 1 400 - 2 220 10 3 132 12 4 110-100 - Total 22

Table: 20.2 - No. of Additional link lines for the year 2011-12 to meet Demand without Load shedding and to insure reliability and quality of supply. Sr. Voltage (kV) 2011-12 No 1 400 - 2 220 8 3 132 8 4 110-100 2 Total 18

64 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 20.3 - No. of Additional link lines for the year 2011-12 for evacuation arrangement. Sr. Voltage (kV) 2011-12 No 1 400 3 2 220 7 3 132 - 4 110-100 - Total 10

Table: 20 .4 - No. of Additional link lines for the year 2011-12 for New substations to have alternate source. Sr. Voltage (kV) 2011-12 No 1 400 - 2 220 4 3 132 1 4 110-100 - Total 5

Conclusion According to Load flow studies overloading can be removed by constructing proposed 400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing S/s.

65 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Year 2012-13

In the year 2012-13, it is estimated that Maharashtra will meet a demand of about 24638 MW considering the available generation of 31624 MW indicating surplus position of state. It is anticipated that there will not be any load shedding during this year and we can supply power to all categories of consumers without any interruption due to generation shortage or transmission network inadequacy. The substation requirement for the year for strengthening of the network is tabulated in Table 21, Augmentation in Table 22 & Additional link lines in Table 23.

Table: 21 – No. of Substation requirement for the year 2012-13 Sr. Voltage Level (kV) 2012-13 No 1 765 2 2 400 4 3 220 - 4 132 - 5 110/100 - Total 6

Table 22: No. of Augmentations for the year 2012-13

Table: 22 .1 - No. of Augmentation by Addition of transformers required for the year 2012-13 Sr. Voltage Ratio 2012-13 No 1 400/220 2 2 220/132, 110 1 3 220/33, 22 6 4 132/33 6 5 110/33, 22 1 Total 16

66 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 22.2 - No. of Augmentation by Replacement of transformer for the year 2012-13 Sr. Voltage Ratio 2012-13 No 1 400/220 - 2 220/132, 110 - 3 220/33, 22 4 4 132/33 9 5 110/33, 22 2 Total 15

Table 23: List of Additional Link Lines required for the year 2012-13

Table: 23.1 – No. of Additional link lines for the year 2012-13 For S/S’s where only single source is available. Sr. Voltage (kV) 2012-13 No 1 400 - 2 220 1 3 132 12 4 110-100 2 Total 15

Table: 23 .2 - No. of Additional link lines for the year 2012-13 to meet Demand without Load shedding and to insure reliability and quality of supply. Sr. Voltage (kV) 2011-12 No 1 400 - 2 220 2 3 132 13 4 110-100 - Total 15

67 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 23 .3 - No. of Additional link lines for the year 2012-13 for evacuation arrangement. Sr. Voltage (kV) 2013-14 No 1 400 - 2 220 - 3 132 - 4 110-100 - Total 0

Table: 23 .4 - No. of Additional link lines for the year 2012-13 for New substations to have alternate source. Sr. Voltage (kV) 2011-12 No 1 400 - 2 220 - 3 132 3 4 110-100 - Total 3

Conclusion According to Load flow studies overloading can be removed by constructing proposed 400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing S/s. Also from this year we can meet Unrestricted Demand.

68 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Year 2013-14

In the year 2013-14, it is estimated that Maharashtra will meet a demand of about 26610 MW considering the available generation of 33042 MW indicating surplus position of state. It is anticipated that there will not be any load shedding during this year and we can supply power to all categories of consumers without any interruption due to generation shortage or transmission network inadequacy. The substation requirement for the year for strengthening of the network is tabulated in Table 24, Augmentation in Table 25 & Additional link lines in Table 26.

Table: 24 – No. of Substation requirement for the year 2013-14 Sr. Voltage Level (kV) 2013-14 No 1 765 0 2 400 4 3 220 1 4 132 - 5 110/100 - Total 5

Table 25: No. of Augmentations for the year 2013-14

Table: 25 .1 - No. of Augmentation by Addition of transformers required for the year 2013-14 Sr. Voltage Ratio 2013-14 No 1 400/220 2 2 220/132, 110 - 3 220/33, 22 6 4 132/33 2 5 110/33, 22 1 Total 11

69 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 25 .2 - No. of Augmentation by Replacement of transformer for the year 2013-14 Sr. Voltage Ratio 2013-14 No 1 400/220 - 2 220/132, 110 1 3 220/33, 22 3 4 132/33 3 5 110/33, 22 1 Total 8

Table 26: List of Additional Link Lines required for the year 2013-14

Table: 26 .1 – No. of Additional link lines for the year 2013-14 For S/S’s where only single source is available. Sr. Voltage (kV) 2013-14 No 1 400 - 2 220 - 3 132 1 4 110-100 - Total 1

Table: 26 .2 – No. of Additional link lines for the year 2013-14 to meet Demand without Load shedding and to insure reliability and quality of supply. Sr. Voltage (kV) 2013-14 No 1 400 - 2 220 2 3 132 5 4 110-100 - Total 7

70 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 26 .3 - No. of Additional link lines for the year 2013-14 for evacuation arrangement. Sr. Voltage (kV) 2013-14 No 1 400 2 2 220 - 3 132 - 4 110-100 - Total 2

Table: 26 .4 - No. of Additional link lines for the year 2013-14 for New substations to have alternate source. Sr. Voltage (kV) 2013-14 No 1 400 - 2 220 4 3 132 6 4 110-100 - Total 10

Conclusion According to Load flow studies overloading can be removed by constructing proposed 765kV, 400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing S/s. Also from this year we can meet Unrestricted Demand.

71 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Year 2014-15 In the year 2014-15, it is estimated that Maharashtra will meet a demand of about 28738 MW considering the available generation of 34587 MW indicating surplus position of state. It is anticipated that there will not be any load shedding during this year and we can supply power to all categories of consumers without any interruption due to generation shortage or transmission network inadequacy. The substation requirement for the year for strengthening of the network is tabulated in Table 27, Augmentation in Table 28 & Additional link lines in Table 29.

Table: 27 – No. of Substation requirement for the year 2014-15 Sr. Voltage Level (kV) 2014-15 No 1 765 - 2 400 2 3 220 - 4 132 - 5 110/100 - Total 2

Table 28: No. of Augmentations for the year 2014-15

Table: 28 .1 - No. of Augmentation by Addition of transformers required for the year 2014-15 Sr. Voltage Ratio 2014-15 No 1 400/220 - 2 220/132, 110 - 3 220/33, 22 1 4 132/33 - 5 110/33, 22 - Total 1

72 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 28 .2 - No. of Augmentation by Replacement of transformer for the year 2014-15 Sr. Voltage Ratio 2014-15 No 1 400/220 - 2 220/132, 110 - 3 220/33, 22 - 4 132/33 2 5 110/33, 22 - Total 2

Table 29: List of Additional Link Lines required for the year 2014-15

Table: 29 .1 – No. of Additional link lines for the year 2014-15 For S/S’s where only single source is available. Sr. Voltage (kV) 2014-15 No 1 400 - 2 220 - 3 132 - 4 110-100 - Total 0

Table: 29 .2 – No. of Additional link lines for the year 2014-15 to meet Demand without Load shedding and to insure reliability and quality of supply. Sr. Voltage (kV) 2014-15 No 1 400 - 2 220 - 3 132 - 4 110-100 - Total 0

73 STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 STU/TRASPLA/DOC4 WEF 01/04/10

Table: 29 .3 - No. of Additional link lines for the year 2014-15 for evacuation arrangement. Sr. Voltage (kV) 2014-15 No 1 400 - 2 220 - 3 132 - 4 110-100 - Total 0

Table: 29 .4 - No. of Additional link lines for the year 2014-15 for New substations to have alternate source. Sr. Voltage (kV) 2014-15 No 1 400 - 2 220 2 3 132 - 4 110-100 - Total 2

Summary Report Maharashtra system is modeled with all the above considerations so as to ensure catering the demand prevailing by 2014-15 including exporting power outside the state in such a way that in all Sub-stations suitable numbers of lines and capacity of transformers are available with sufficient redundancy in the transmission system. This will also ensure following: 1) N-1 criteria for Transformers and all link lines. 2) N-2 criteria for Generation evacuation lines. Western Maharashtra will be connected very strongly with the rest of the grid thereby ensuring synchronized operation of the entire Maharashtra system to the maximum possible extent.

74

MAHARASHTRA STATE TRANSMISSION COMPANY LTD.

75 STU/TRANS-PLAN/DOC-04/ WEF 01.04.10

TECHNICAL ABSTRACT (MSETCL) SPILL OVER SCHEMES Sr. No. Voltage Level 2010-11 2011-12 2012-13 2013-14 2014-15 Total 2008-09 2009-10 New Sub-Station 1 765 KV 0 0 0 0 2 0 0 2 2 400 KV 0 4 5 2 4 4 2 21 3 220 KV 18 22 13 14 0 1 0 68 4 132 KV 11 13 12 2 0 0 0 38 5 110-100 KV 3 0 0 0 0 0 0 3 TOTAL 32 39 30 18 6 5 2 132 New Sub-Station for 66KV Elimination 1 220 KV 2 1 0 0 0 0 0 3 2 132 KV 2 6 1 1 0 0 0 10 TOTAL 4 7 1 1 0 0 0 13 TOTAL NEW 36 46 31 19 6 5 2 145 Transmission Lines (Ckt. KM) Transmission Lines for New Sub-Station 1 765 KV 0 0 0 0 900 0 0 900 2 400 KV 0 230 630 272 672 100 60 1964 3 220 KV 763 1878 1024 1049 412 394 35 5554 4 132 KV 420 1295 763 943 0 25 0 3446 5 110-100 KV 99 0 20 0 0 0 0 119 TOTAL 1282 3403 2437 2264 1984 519 95 11983 Transmission Lines for S/S/ where only Single Source & Single ckt is available 1 765 KV 0 0 0 0 0 0 0 0 2 400 KV 0 0 0 0 0 0 0 0 3 220 KV 76 30 321 85 42 0 0 554 4 132 KV 718 251 475 732 277 37 0 2490 5 110-100 KV 72 56 0 18 42 0 0 188 TOTAL 866 337 796 835 361 37 0 3232 Transmission Lines to ensure Reliability 1 765 KV 0 0 0 0 0 0 0 0 2 400 KV 0 0 0 0 0 0 0 0 3 220 KV 55 257 275 212 40 153 0 992 4 132 KV 119 162 138 57 307 80 0 863 5 110-100 KV 90 3145 25 55 0 0 0 3315 TOTAL 264 3564 438 324 347 233 0 5170 Transmission Lines to have Alternate Source 1 765 KV 0 0 0 0 0 0 0 0 2 400 KV 0 0 0 0 0 0 0 0 3 220 KV 0 0 90 255 0 280 80 705 4 132 KV 26 82 155 0 180 75 0 518 5 110-100 KV 0 0 15 0 0 0 0 15 TOTAL 26 82 260 255 180 355 80 1238 Transmission Lines for Strengthening of Evacuation 1 765 KV 0 0 0 0 0 0 0 0 2 400 KV 0 0 0 273 0 100 0 373 3 220 KV 200 95 30 94 0 0 0 419 4 132 KV 0 30 0 32 0 0 0 62 5 110-100 KV 0 0 0 0 0 0 0 0 TOTAL 200 125 30 399 0 100 0 854 TOTAL EHV LINES (Ckt.KM) 1 765 KV 0 0 0 0 900 0 0 900 2 400 KV 0 230 630 545 672 200 60 2337 3 220 KV 1094 2260 1740 1695 494 827 115 8224 4 132 KV 1283 1820 1531 1764 764 217 0 7379 5 110-100 KV 261 3201 60 73 42 0 0 3637 TOTAL EHV LINES 2637 7511 3961 4077 2872 1244 175 22477 Capacity Addition (MVA) Capacity addition by New Sub-Station 1 765 KV 0 0 0 0 3000 3000 0 6000 2 400 KV 830 4434 7002 3334 2427 4000 2000 24027 3 220 KV 4500 6175 2300 3400 0 200 0 16575 4 132 KV 818 1650 600 200 0 0 3268 5 110-100 KV 150 0 0 0 0 0 0 150 TOTAL 6298 12259 9902 6934 5427 7200 2000 50020 Capacity addition by Augmentation by Addition of Transformer 1 765 KV 0 0 0 0 0 0 0 0 2 400 KV 2815 3315 500 500 0 0 0 7130 3 220 KV 4725 3605 1425 725 425 300 25 11230 4 132 KV 2175 2400 275 350 175 50 0 5425 5 110-100 KV 350 400 50 0 25 25 0 850 TOTAL 10065 9720 2250 1575 625 375 25 24635 Capacity addition by Augmentation by Replacement of Transformer 1 765 KV 0 0 0 0 0 0 0 0 2 400 KV 0 370 0 370 185 0 0 925 3 220 KV 1245 2742 2530 625 100 175 0 7417 4 132 KV 1724 1098 455 425 225 75 50 4051 5 110-100 KV 423 260 160 38 25 25 0 931 TOTAL 3392 4470 3145 1458 535 275 50 13324 TOTAL CAPACITY ADDITION 1 765 KV 0 0 0 0 3000 3000 0 6000 2 400 KV 3645 8119 7502 4204 2612 4000 2000 32082 3 220 KV 10470 12522 6255 4750 525 675 25 35222 4 132 KV 4716.9 5147.5 1330 975 400 125 50 12744 5 110-100 KV 923 660 210 37.5 50 50 0 1931 TOTAL CAPACITY 19755 26449 15297 9967 6587 7850 2075 87979 76

EVACUATION SCHEMES

77 STU/TRANS-PLAN/DOC-04/WEF 01/04/10 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 EVACUATION SCHEMES SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS SUBSTATION

EVACUATION SCHEMES ( MAHAGENCO ) 1 400/220 KV KORADI -II SUB- NAGPUR 1) 400/220 KV , 2X500 MVA ICTS WITH BAYS Evacuation of M/s Adani STATION 400/220KV, 1X 167 MVA 1 PHASE ICT SPARE Generation at Gondia & (KORADI 3 X 660 MW) 2) LILO OF 400KV BHUSAWAL - I - KORADI - I AT KORADI -II - 15 KM MAHAGenco (ADANI 2 X 660 MW) (2010-11) 3) LILO OF 400KV SATPURA - KORADI -I AT KORADI-II - 15 KM 4) 220 KV KORADI -II - MANKAPUR M/C -25KM WITH BAYS 5) 220 KORADI - II - BUTTIBORI D/C -55KM WITH BAYS 6) 220 KORADI - II - NEW KHAPERKHEDA D/C -15KM WITH BAYS

7) KORADI -II - KORADI - III 400KV QUAD D/C LINE- 25 KM 2 400/220 KV CHANDRAPUR-II CHANDRAPUR 1) 400/220 KV, 2 X 500 MVA ICTS WITH BAYS LOA Date 30/04/08 Land S/S ALONG WITH 400/220 KV, 1 X 167 MVA 1 PHASE ICT SPARE Available SWITCHING STATION 2) LILO ON 400 KV CHANDRAPUR - PARLI D/C AT CHANDRAPUR -II - (CHANDRAPUR S/STN - 1.8 KM WITH BAYS 2 X 500 MW) 3) 400 KV D/C CHANDRAPUR-II - WARRORA - 20 KM (2011-12) 4) 400KV D/C WARORA - WARDHA (PG) - 110KM 5) 220 KV CHANDRAPUR(MIDC) - CHANDRAPUR - II S/STN -20 KM

6) 2X400KV QUAD D/C FROM KORADI - WARDHA(PG) - 70KM

3 EVACUATION OF POWER RAIGAD 1) UPGRADATION OF EXISTING 220 KV BOTH D/C URAN- APTA LINE LOA Date 30/04/08 FROM URAN G.T. WITH ACCC TW 620 SQ MM CONDUCTOR Land Available EXPANSION PROJECT 2) 220KV URAN - KHARGHAR D/C LINE USING 0.5 ZEBRA ON M/C 1) Block No. -I - 700 MW WITH BAYS - 36 KMS (ONLY STRINGING) 2) Block No. - II - 340 MW (2009-10) 4 400/220 KV BHUSAWAL - II JALGAON 1) 400/220 KV, 2 X 500 MVA ICTS WITH BAYS 400/220 KV, 1 X 167 LOA Date 23/01/07 SUB-STATION MVA 1 PHASE ICT SPARE 2 X 500 MW EXP. (2010 - 11) 2) 400 KV BHUSAWAL (KHADKA) - BHUSAWAL-II - D/C - 10 KM WITH LOA for Civil Works Date 1 X 300 MW REP. BAYS 05/11/07 (2010 - 11) 3) 400 KV BHUSAWAL-II- AURANGABAD-I D/C LINE - 185 KM WITH BAYS 4) 220 KV D/C ON M/C TOWER FROM 400 KV BHUSAWAL(II) - BHUSAWAL (KHADKA) -10 KM WITH BAYS 5) 220KV BHUSAWAL-II- AMALNER D/C - 90 KM WITH BAYS 6) 400KV LINE BAYS EACH AT EXISTING 400KV KHADKA & AURANGABAD S/S & 4NOS. 400KV LINE BAYS WITH ONE & HALF BREAKER TYPE CONST. AT BHUSAWAL-II S/S 5 EVACUATION OF POWER BEED 1) 220KV PARLI - NANDED D/C LINE - 110 KMS LOA Date 31/08/06 24.5% FROM PARLI TPS Civil Work Completed 2) 220KV PARLI GCR - BEED AT PARLI D/C LINE -70 KMS EXTENSION 1 X 250 MW EXP. ( 2008-09) 1 X 300 MW REP. ( 2011-12) 6 EVACUATION OF POWER AKOLA 1) 2 X 25 MVA, 220/33 KV T/FS WITH BAYS AT BALAPUR MIDC LOA Date 31/08/06 FROM PARAS EXTENSION 2) 2 X 100 MVA, 220/132 KV ICTS WITH BAYS AT BALAPUR MIDC 20.5% Civil Work PROJECT Completed (2008-09) 3) 220KV PARAS-BALAPUR MIDC M/C LINE - 6 KM WITH BAYS 1 X 250 MW EXP. 1 X 300 MW REP. 4) LILO OF 220 KV AKOLA-CHIKHALI AT PARAS EXTENSION - 15 KM

5) REORIENTATION OF 132KV LINES-30 KM WITH BAYS 6) 132 KV BAYS -2 NOS 7) 33 KV OUTLETS - 8 NOS 7 400KV KHAPERKHEDA S/S NAGPUR 1) 400/220 KV, 2 X 500 MVA ICTS WITH BAYS 400/220 KV, 1 X 167 LOA Date 23/01/07 (500MW GENERATION MVA 1 PHASE ICT SPARE 3.5% Civil Work Completed EVACUATION PROJECT) 2) 400KV KHAPERKHEDA - 765 KORADI-III D/C QUAD -5 KMS (2009-10) 3) 220KV KHAPERKHEDA- II -220 KV KHAPERKHEDA OLD - 7 KM , M/C LINE WITH BAYS 4) LILO OF 01 CKT AT CHANDRAPUR - I - KORADI-I AT KHAPERKHEDA - COMMISSIONED 10KM 8 400KV DHULE-II S/S DHULE 1) 400KV D/C DHULE-II-DHULE-I - 15 KM WITH BAYS Evacuation of Power from ( DONDAICHA) central sector & to feed the (2012-13) 2) 400 KV D/C LINE FROM 400 KV DHULE-II - NASHIK - 190KMS. upcoming load. 3) 2x315MVA,400/220kV ICT 4) 220 KV D/C LINE TO DONDAICHA ( existing) S/S -15 KMS .

78

EHV CC O&M ZONE : WASHI

79 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

SPILL OVER SCHEMES 1 220KV VASAI S/S THANE 1) 220/100KV, 2 X 100MVA T/FS WITH BAYS Voltage improvement & load catering. (2008-09) 2) 2 X 220KV BAYS 3) LILO ON 220 KV PADGHE-BOISAR AT VASAI S/S- 9 KM

4) 2 NOS.OF 100KV LINE BAYS EACH AT OLD & NEW SWITCHYARDS 5) REORIENTATION OF 100KV LINES - 15KM 2 220KV BAPGAON S/S THANE 1) 2X200MVA,220/100KV ICT This station is considered to meet the load growth in Kalwa circle (2008-09) 2) 2X50 MVA, 220/22KV T/F and to improve the voltage profile. Bapgaon -220kV S/S is proposed on LILO on 220kV existing Padghe –Kalwa D/C & 220 3) D/C LINE LILO ON 220KV PADGHE - KALWA LINE WITH kV Nasik-Kalwa ckt 3&4 at Bapgaon. BAYS - 3 KM 4) LILO OF 100 KV PADGHE - BHIWANDI SC LINE - 1 KM

5) LILO OF 100KV PADGHE - PANJARPUR SC LINE - 1 KM 6) D/C LILO OF 100 KV PADGHE - PISE LINE - 4 KM

7) LILO OF 220KV NASIK - KALWA CKT 3&4 AT BAPGAON- 3 KM 8) 12X22 KV OUTLETS 3 220 KV BHANDUP GIS MUMBAI 1) 4 X 50 MVA, 220/22 KV T/FS WITH BAYS Voltage improvement & load catering. (2008-09) 2) LILO ON 220 KV BORIVALI- MULUND S/C LINE AT BHANDUP S/S- 3KM 3) 22 KV OUTLETS - 24 NOS. 4 220KV KUDUS S/S THANE 1) LILO OF 220 KV PADGHE-WADA - 3.0 KM WITH BAYS Present recorded peak load on Kolshet and Wada S/S are 90MW (2008-09) AT KUDUS S/S and 72MW. It is anticipated by the year 2007-08 the load will 2) 2X50MVA, 220/22KV T/F WITH BAYS reach to about 172MW. Hence it is necessary to go in for 220kV sub-station at Kudus. Kudus-220kV S/S is proposed on LILO of 3) 22KV OUTLETS - 12 NOS. 220kV existing Padghe–Wada line in year 2007-08 for reducing loading on Kolshet and Wada network.

5 * 220KV KNOWLEDGE THANE 1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS Voltage improvement & load catering. PARK, AIROLI (2008-09) 2) 22KV OUTLETS - 12 NOS. 3) LILO ON 220KV KALWA - PADGHE LINE WITH BAYS - 1 KM

6 220 KV BHIWANDI - IV S/S THANE 1) 4 X 50 MVA, 220/22 KV T/F'S WITH BAYS Voltage improvement & load catering. (2008-09) 2) LILO OF 220KV PADGHE - KALWA CKT-I - 7 KM WITH BAYS 3) 24 X 22KV OUTLETS 7220KV BHIWANDI - III THANE 1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS Voltage improvement & load catering. (2008-09) 2) 22KV OUTLETS - 12 NOS. 3) LILO ON KALWA - PADGHE LINE WITH BAYS - 2.5 KM

8 110 KV THANE 1) 2 X 50 MVA, 110/22 KV T/FS WITH BAYS Voltage improvement & load catering. MUMBRA S/S (2008-09) 2) LILO ON 110KV KALWA - DOMBIVALI LINE - 4 CKM WITH BAYS 3) 10 x 22KV OUTLETS 9 100 KV NERAL RAIGAD 1) 100/22KV, 2 X 25MVA T/FS WITH BAYS Neral 100kV S/S is considered for reducing the loading on (KOLHARE) S/S Ambernath 220kV S/S. This new Substation is fed from 2) 100KV D/C LINE AMBERNATH II - NERAL - 25 KM (2008-09) Ambernath 220 kV S/S by constructing 100kV D/C line of 25kM. 3) 6 X 22KV OUTLETS 10 400KV NAVI MUMBAI THANE SCOPE OF WORK BY MSETCL Voltage improvement & load catering. (PGCIL) 1) LILO ON 220KV APTA - KALWA S/C TO NAVI MUMBAI (2009-10) (PGCIL) - 10 KMS WITH BAYS 2) LILO ON 220KV KANDALGAON - KHARGHAR FOR NAVI MUMBAI -5KM. 11 220KV THANE 1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS Present recorded peak load on Mahane-100kV, Amernath-100kV ULHASNAGAR S/S 2) 12 X 22KV OUTLETS S/S are 50MW and 40MW respectively. It is anticipated by the (2009-10) 3) LILO ON 220KV PADGHE - JAMBHUL LINE - 10 KMS year 2009-10 that total load will reach to about 108MW. Hence it WITH BAYS is necessary to go in for new 220kV sub-station at Ulhasnagar.

12 220KV WASHI GIS THANE 1) 220KV KHARGHAR - WASHI D/C LINE WITH BAYS - 20 Present recorded peak load on Vashi-100kV is 110MW. It is (2009-10) KMS anticipated by the year 2009-10 that the load will reach to about 2) 2 X 100MVA, 220/100KV ICTS WITH BAYS 135MW. Hence it is necessary to go in for new 220kV sub-station at Vashi The new substation Vashi -220kV S/S is proposed in 3) 2 X 50MVA, 220/22KV T/FS WITH BAYS year 2009-10 for reducing loading on Vashi-100kV S/S and 4) 2 X 100KV BAYS improve voltage profile. By the commissioning of this substation, 5) 12 X 22KV OUTLETS voltage profile will improve . 6) REORIENTATION OF 100 KV LINES -20 KM 13 220 KV MUMBAI 1) 2 X 50 MVA, 220/33-22 KV T/FS WITH BAYS Goregaon FC-220kV is considered to reduce the loading of Kalwa- GOREGAON FILM CITY S/S 2) 12 X 33-22KV OUTLETS 220kV S/S. (2009-10) 3) 220KV U/G CABLE FROM BORIVALI - 8 KMS 14 132 KV DAPCHERI S/S THANE 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Dapcheri-132kV S/S is considered in year 2009-10 for reducing (2009-10) 2) 8 X 33KV OUTLETS the loading and to feed the upcomming load at proper voltage. 3) 132KV DHANU - DAPCHERI D/C LINE WITH BAYS - 25 KMS 80 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE As per the methodology stipulated in the guideline of State Grid Code Regulation No. 9.4 1 132 KV LINK LINE THANE 1) 132kV BOISAR-II - DAPCHERI SCDC LINE - 25 KM To provide uninterrupted supply during planned outages it is (2009-10) necessary to add proposed line ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

1 220 KV LINK LINE RAIGAD 1) 220KV KHARGHAR - NERUL SCDC LINE WITH BAYS- Since the existing 220kV Kharghar-Nerul S/c line is critically (2009-10) 10 KMS loaded to an extent of 186 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

2 220 KV LINK LINE MUMBAI 1) 220KV D/C LINE NAGOTHANE - IPCL - 9 KMS WITH Since the existing 220kV Nagothane-IPCL S/c line is getting (2008-09) BAYS loaded to an extent of 147 MW. It is anticipated the load will reach to critical value by the year 2011-12. Hence it is suggested to add proposed line to meet additional load growth and contingency. 3 220 KV LINK LINE RAIGAD 1) 220KV TROMBAY(MSETCL) - NERUL SCDC LINE Since the existing 220kV Trombay-Nerul S/c line is loaded to an (2009-10) WITH BAYS-30 KMS extent of 136 MW during Non-Coinsident peak condition. Considering the increasing developement at Nerul it is necessary to propose additional line to meet additional load growth and contingency.

4 220 KV LINK LINE THANE 1) 220KV BOISAR (PGCIL) - 220KV BOISAR (MSETCL) Since the existing 220kV Boisar-II-Boisar-PG S/c line is critically (2008-09) LINE - 15 KM loaded to an extent of 241 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

5 220 KV LINK LINE RAIGAD 1) 220 KV NAGOTHANE -WADKHAL D/C LINE - 30 KM For strengthening of evacuation of Dabhol power. (2008-09) 6 220 KV LINK LINE THANE 1) 220KV KALWA - TROMBAY SCDC LINE WITH BAYS- Line is required for evacuation of proposed Generation at (2009-10) 25.56 KMS Trombay

7 132 KV LINK LINE THANE 1) 132KV LINE FROM 220KV BOISAR - 132KV BOISAR Since the existing 132kV Boisar-Boisar MIDC S/c line is critically (2008-09) MIDC SCDC LINE - 8.7KM loaded to an extent of 68 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

8 100 KV LINK LINE THANE 1) 100 KV BAPGAON-MOHANE SCDC LINE - 20 KM Since the existing 100kV Mohane-Padghe S/c line is 60 MW. (2008-09) Mohane Being the industrial estate and considering heavy load growth it is suggested to add proposed line to meet additional load growth and contingency.

9 100 KV LINK LINE THANE 1) 100KV BHIVANDI - PADGHE SCDC LINE WITH BAYS- Since the existing 100kV Bhiwandi-Padghe S/c line is critically (2009-10) 16 KMS loaded to an extent of 106 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

10 100 KV LINK LINE THANE 1) 100 KV BAPGAON - BHIWANDI - 15 KM WITH BAYS Since the existing 100kV Bhiwandi-Padghe S/c line is critically (2009-10) loaded to an extent of 106 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

STRENGTHENING FOR EVACUATION ARRANGEMENT 1 220 KV LINK LINE RAIGAD 1) 220KV APTA - CHICHWAD M/C LINE WITH BAYS- 60 For strengthening of evacuation scheme of Uran. (2009-10) KMS 2 220 KV LINK LINE * RAIGAD 1) LILO ON 220KV APTA - MAHAD LINE AT NAGOTHANE For strengthening of evacuation scheme of Uran. (2009-10) WITH BAYS- 5 KMS

81 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

AUGMENTATION OF S/S BY ADDITION OF ICT/T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

1 220KVAMBERNATH - II* THANE 1) ADD. 1X100 MVA, 220/100KV ICT WITH BAYS To avoid loss of supply in case of outages or interruptions on any S/S (JAMBHUL) 2) 100 KV D/C LINE ON D/C TOWER FOR AMBARNATH I one transformer (2008-09) TO INTERCONNECTION - 5 KM 3) 2X100KV BAYS AT AMBERNATH - I 2 220 KV WASHALA S/S* THANE 1) 1X 25MVA , 220/22KV T/FS WITH BAYS To avoid loss of supply in case of outages or interruptions on any (2008-09) one transformer 2) 2 X 22KV OUTLETS. 3 220 KV DOMBIVALI II S/S THANE 1) 1X200 MVA, 220/100 KV ICT WITH BAYS To avoid loss of supply in case of outages or interruptions on any (2008-09) one transformer 4 220 KV PADGHE S/S THANE 1) 1X50 MVA, 100/22 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions on any (2008-09) one transformer 2) 22KV OUTLETS - 6 NOS 5 132 KV TALEBAZAR S/S* SINDHUDUR 1) 1 X 25MVA , 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions on any (2008-09) G one transformer 2) 4 X 33KV OUTLETS. 3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM 6 100 KV JITE S/S* RAIGAD 1) 1 X 25MVA , 100/22KV T/F WITH BAY To avoid loss of supply in case of outages or interruptions on any (2008-09) one transformer 2) 4 X 22KV OUTLETS. 7 220 kV NAGOTHANE Raigad 1) Add 1 X 25 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 1 x 25 MVA and (2009-10) 2) 4 x 22 kV outlets the Load reach is 8 MVA.To avoid the loss of supply in case of outages or interruptions of transformers.

8 132 kV DAHANU THANE 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 50, 1 X 25 MVA and (2009-10) 2) 4 X 33 kV out lets the load reached is 33 MVA To avoid loss of supply in case of outages or interruptions on transformer. AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER 1 220 KV MAHAPE S/S THANE 1) 1X50 MVA,220/22 KV T/F Existing transformer capacity available in S/s is, (2008-09) 220/22 - 2 x 50 - 66 MVA 2) 6X22 KV OUTLETS Considering the maximum load reach on the transformer, in event 3) 3 CORE, 300SQMM, XLPE CABLE - 0.6 KM of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 2220 KV PADGHE S/S THANE 1) 1X200 MVA, 220/100 KV ICT WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/100 - 2 x 200 - 281 MVA Considering the maximum load reach on the transformer, in event 2) 100 KV BAYS - 2 NOS of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 3 220K KV MAHAD S/S RAIGAD 1) 1 X25MVA , 220/22KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/22 - 2 x 50 - 44 MVA 2) 6 X 22KV OUTLETS. Hence it is necessary to propose additional transformer to meet 3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM additional load growth and contingency. 4 220 KV ONGC S/S PANVEL RAIGAD 1) 1 X 50MVA , 220/33-22KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/33 - 2 x 50 - 55 MVA 2) 3 X 22KV OUTLETS Considering the maximum load reach on the transformer, in event 3) 2 X 33KV OUTLETS of interruption/outage on any one of the transformer other 4) 3 CORE, 400SQMM, XLPE CABLE - 0.6 KM transformer should take care of existing load so as to avoid load shedding. 5 220KV NERUL S/S THANE 1) 1X50 MVA, 220/33-22KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/33 - 2 x 50 - 73 MVA load 2) 4X33KV OUTLET Considering the maximum load reach on the transformer, in event 3) 2X22KV OUTLET of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 6 COMPREHENSIVE THANE 1) CONST. OF 220KV D/C LINE ON D/C TOWERS LILO ON Existing transformer capacity available in Temghar S/s is, SCHEME FOR CAPACITY 220KV PADGHE - COLOURCHEM LINE TO TEMGHAR 220/22 - 2 x 50 - 85 MVA load ADDITION AT EHV S/S IN S/S - 10 KM 100/22 - 2 x 50 - 74 MVA load BHIWANDI AREA 2) 220KV LINE BAYS AT TEMGHAR S/S - 2 NOS. Considering the maximum load reach on the transformer, in event (2008-09) of interruption/outage on any one of the transformer other 3) REPLACEMENT OF 2X50MVA, 100/22KV T/FS BY transformer should take care of existing load so as to avoid load 2X50MVA, 220/22KV T/FS AT 220KV TEMGHAR S/S shedding. WITH 12 X 22KV OUTLETS 4) CONST. OF 100KV SCDC LINE FOR DIVERSION OF 100KV LINE AT TEMGHAR S/S - 0.5KM 5) ADDITION OF 1X50MVA, 100/22KV T/F AT 100/22KV BHIWANDI S/S WITH 4X 22KV GIS BAYS 7 400KV NAGOTHANE S/S RAIGAD 1) 1 X 500 MVA, 400/220KV ICT WITH BAYS Existing transformer capacity available in S/s is,400/220kV, 2 x (2009-10) 315 MVA and the load reached is 487 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 8 400 KV KALWA S/S THANE 1) 1 X 500 MVA 400/220 KV ICT WITH BAYS Existing transformer capacity available in S/s is,400/220kV, 2 x (2009-10) 600 MVA and the load reached is 979 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 9 132 kV PALGHAR Thane 1) Add 1 X 50 MVA ,132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 MVA and (2009-10) 2) 6 X 33 kV out lets. load is 44 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 82 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

10 100 kV VASAI Thane 1) Add 1x50 MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 3 x 50 (2009-10) 2) 6 x 22 kV outlets And the Load reach is 126 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 11 100 kV SHAHAPUR Thane 1) Add 1x25 MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 25 (2009-10) 2) 4 x 22 kV outlets And the Load reach is 32 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 12 100 kV PATALGANGA Raigad 1) Add 1x25 MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 25 (2009-10) 2) 4 x 22 kV outlets And the Load reach is 32 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 13 100 kV MHSALA Raigad 1) Add 1x25 MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 12.5 (2009-10) 2) 4 x 22 kV outlets And the Load reach is 19 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 14 100 kV ROHA Raigad 1) Add 1x50 MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 25 (2009-10) 2) 6 x 22 kV outlets And the Load reach is 46 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 15 220 kV KALWA Thane 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (2009-10) 2) 6 x 22 kV outlets And the Load reach is 81 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 16 220 kV URAN Raigad 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 25 (2009-10) 2) 6 x 22 kV outlets And the Load reach is 41 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 17 220 kV TEMGHAR * Thane 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (2009-10) 2) 6 x 22 kV outlets And the Load reach is70 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing loadTo remove 100/22 kV Temghar I.

18 220 kV ANANDNAGAR Thane 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (AMBARNATH - III ) 2) 6 x 22 kV outlets And the Load reach is 62 MVA.Considering the maximum load (2009-10) reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 19 220 kV DOMBIVALI-II (PAL) Thane 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (2009-10) 2) 6 x 22 kV outlets And the Load reach is 54 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 20 220 kV MAHAD Raigad 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (2009-10) 2) 6 x 22 kV outlets And the Load reach is 54 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 21 220 kV WADA Raigad 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 3 x 50 (2009-10) 2) 6 x 22 kV outlets And the Load reach is 99 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

83 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

AUGMENTATION OF S/S BY REPLACEMENT OF ICT/T/F 1 220KV THANE 1) 1 X (50-20)MVA, 100/22KV T/F WITH BAYS Existing transformer capacity available in S/s is, APTA S/S 2) 2X22KV OUTLETS 100/22 - 2 x 20 - 12 load (2008-09) The transformers are replaced to meet anticipated load growth.

2 132 KV DAHANU S/S THANE 1) 1 X (50-25) MVA, 132/33 KV T/FS. Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 16 MVA load 2) 3 X 33 KV OUTLETS The transformers are replaced to meet anticipated load growth.

3 132 KV BOISAR MIDC S/S THANE 1) 1 X (50-25) MVA, 132/33 KV T/F Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 36 MVA load 2) 3 X 33KV OUTLETS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 4 100KV THANE 1) REP. 1 X (50-25)MVA, 100/22KV T/FS. Existing transformer capacity available in S/s is, DOMBIVALI S/S 100/22 - 1 x 50 - 49 MVA load (2008-09) 2) 3 X 22KV OUTLETS 100/22 - 3 x 25 - 46 MVA load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 5 100KV VASHI S/S THANE 1) 1 X (50-25)MVA, 100/22KV T/FS. Existing transformer capacity available in substation is 100/22kv, (2008-09) 2x25MVA - 12MVA load . The transformer is replaced to meet 2) 4 X 11KV OUTLETS anticipated load growth 6 100KV RAIGAD 1) 1 X (50-25)MVA, 100/22KV T/F WITH BAYS Existing transformer capacity available in S/s is, TAMBATI S/S 100/22 - 2 x 25 - 22 load (2008-09) The transformers are replaced to meet anticipated load growth. 2) 2X22KV OUTLETS 7 100KV THANE 1) 1 X (50-25)MVA, 100/22KV T/F WITH BAYS Existing transformer capacity available in S/s is, AMBERNATH I S/S 2) 2X22KV OUTLETS 100/22 - 1 x 50 - 34 load (2008-09) 100/22 - 2 x 25 - 30 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 8 100KV RAIGAD 1) 1 X (50-25)MVA, 100/22KV T/F WITH BAYS Existing transformer capacity available in S/s is, THAL WAISHET S/S 100/22 - 2 x 25 - 26 load (2008-09) 2) 2X22KV OUTLETS Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 9100KV RAIGAD 1) 1 X (50-25)MVA, 100/22KV T/F WITH BAYS Existing transformer capacity available in S/s is, ROHA S/S 2) 2X22KV OUTLETS 100/22 - 2 x 25 - 38 load (2008-09) Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 10 220 kV KANDALGAON Raigad 1) 1 X ( 50-20) MVA , 220/22 kV T/F with bays. Existing transformer capacity available in S/s is 1 x 20 , (2009-10) 2) 4 X 22 kV outlets. 1 x 50 and the Load reach is 39 MVA. The T/F is replaced to meet anticipated load growth

11 220KV KALWA S/S THANE 1) 1x(200-125)MVA, 220/100KV ICT'S WITH BAYS Existing transformer capacity available in S/s is, (2009-10) 2) 100KV BAYS - 2NOS 220/100kV, 4 x 125MVA and the load reached is 368MVA considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 12 220KV TROMBAY S/S MUMBAI 1) 1x(200-125)MVA, 220/100KV ICT'S WITH BAYS Existing transformer capacity available in S/s is 220/100kV, 2 x (2009-10) 2) 100KV BAYS - 2NOS 125 MVA and the load reached is 165 MVA,Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 13 220KV BORIVLI S/S MUMBAI 1) 1x(200-125)MVA, 220/100KV ICT'S WITH BAYS Existing transformer capacity available in S/s is 220/100kV, 2 x (2009-10) 2) 100KV BAYS - 2NOS 125 MVAand the load reached is 223MVA,Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 14 220KV PADGHE S/S THANE 1) 1x(200-125)MVA, 220/100KV ICT'S WITH BAYS Existing transformer capacity available in S/s is,220/100kV,2 x (2009-10) 2) 100KV BAYS - 2NOS 200 MVA and 220/100 kV,1 x 125MVA and the load reached is 263MVA and 98 MVA respectively.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

15 220KV BOISAR II S/S THANE 1) 1X(200-150)MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is 220/132kV 2 x (2009-10) 2) 100KV BAYS - 2NOS 150MVAand1X 200MVA the load reached is 315MVA,Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

84 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

16 220 KV TALOJA S/S RAIGAD 1) 1X(200-100)MVA, 220/100KV WITH BAYS 100KV Existing Transformer capacity available is 2 X 100 MVA and load (2009-10) 2) BAYS - 2NOS reached is 83 MVA, Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

17 220KV APTA S/S RAIGAD 1) 1X(200-125)MVA, 220/100KV WITH BAYS Existing transformer capacity available in S/s is 220/100 kV, 2 x (2009-10) 2) 100KV BAYS - 2NOS 200 MVA and 2 X 125 MVA the load reached is 235 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 18 100 kV NOCIL Raigad 1) 2x(50-25) MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 25 (2009-10) 2) 4 x 22 kV outlets And the Load reach is 38 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 19 100 kV AMBERNATH-I Thane 1) 1 X ( 50-25)MVA, 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 1 x 50, (2009-10) 2) 4 X 22 kV outlets. 2 x 25 and the Load reach is 57 MVA. The T/F is replaced to meet anticipated load growth

20 100 kV MURBAD Thane 1) 1 X ( 50-25) 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 1 x 50 , (2009-10) 2) 4 X 22 kV outlets. 1 x 25 and the Load reach is 29 MVA. The T/F is replaced to meet anticipated load growth

21 100 kV VASHI Thane 1) 1 X ( 50-25)MVA, 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 50, (2009-10) 2) 4 X 22 kV outlets. 1 x 25 and the Load reach is 85 MVA. The T/F is replaced to meet anticipated load growth

22 100 kV KHOPOLI (2009- Raigad 1) 1 X ( 50-25)MVA, 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 1 x 50 , 10) 2) 4 X 22 kV outlets. 1 x 25 and the Load reach is 41 MVA. The T/F is replaced to meet anticipated load growth

23 100 kV ROHA Raigad 1) 1 X ( 50-25) MVA , 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25 MVA and (2009-10) 2) 4 X 22 kV outlets. the Load reach is 46 MVA. The T/F is replaced to meet anticipated load growth

24 100 kV TALOJA-I Raigad 1) 1X ( 50-20)MVA, 100/22 kV T/F WITH BAYS Existing transformer capacity available in S/s is 2 x 20, 1 x 25 and (2009-10) 2) 2X22KV OUTLETS the Load reach is 46 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

85 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

NEW SCHEMES

1 220 KV PALGHAR S/S THANE 1) 220KV NALASOPARA - PALGHAR D/C LINE WITH BAYS Palghar 220kV S/S is considered to cater increasing loads in the (2010-11) - 40 KMS area. 2) 2 X 50MVA, 220/22KV T/FS WITH BAYS

2 220 KV BOISAR MIDC THANE 1) 220 KV D/c LINE FROM BOISER (PG) - 10 KMs Voltage improvement & load catering. (2010-11) 2) 220 KV D/c LINE FROM 220 KV PALGHAR - 20 KMs

3) 2 X 100 MVA 220/132 KV ICT WITH BAYS 4) 2 X 50 MVA 220/33 KV T/F WITH BAYS

5) 132 KV D/C LINE TO BOISER MIDC S/S - 10 KM WITH BAYS 3 220KV VILE-BAGAD (2010- RAIGAD 1) LILO OF ONE CIRCUIT OF 220KV D/C APTA - Voltage improvement & load catering. 11) PEDAMBE LINE - 4KM 2) 2X25MVA , 220/22K V TF 3) 33KV OUTLETS - 08 NOS 4 220 KV THANE 1) 2 X 50 MVA, 220/22 KV TFS WITH BAYS It is necessary to go in for new 220kV sub-station at kalyan to KALYAN S/S 2) 220KV PADGHE - KALYAN D/C LINE WITH BAYS - 20 FEED THE UPCOMMING LOAD (2011-12) KMS 3) 12 X 22KV BAYS FOR FUTURE EXPANSION 5 132 KV JAWHAR S/S (2011- THANE 1) LILO ON 132 KV BOISAR-I - DAHANU S/C LINE AT To overcome low voltage & to feed the upcomming load. 12) JAWHAR - 75 KM WITH BAYS 2) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS 3) 8 NOS OF 33 KV BAYS 6765KV THANE BY PGCIL PADGHE-II S/S (PG) 1 MSETCL SCOPE Evacuation of Central Sector Power. (2012-13) 400KV PADGHE(PG) - 400KV PADGHE -II (KUDUS) MSETCL USING D/C QUAD MOOSE CONDUCTOR- 10KM 2) 400KV D/C QUAD LINE FOR NALASOPARA S/STN- 57KM 7 400KV PADGHE - II THANE 1) 2X 500 MVA , 400/220KV ICT'S WITH BAYS To improve the voltage profile of the area and to meet the (KUDUS) S/S 1X167 MVA 400/220 KV 1 PHASE ICT SPARE upcomming load. (2012 -13) 2) LILO ON 400 KV TARAPUR - PADGHE D/C AT PADGHE - II (KUDUS) -15 KM 3) INTERCONNECTING D/C LINE BETWEEEN 220 KV D/C LINE TO 220 KV KUDUS- -5 KMS

4) 220 KV D/C LINE TO 220 KV BHIVANDI IV- 30 KMS 5) 220KV LINE FROM KUDUS TO BHIVANDI-III - 30 KM 8 400 KV NERUL THANE 1) LILO ON 400 KV KHARGHAR - KALWA AT NERUL -10 400 KV Nerul S/s is Considered for upcomming load near by (2013-14) KM Nerul and to feed the area at proper voltage. 2) LILO ON 400 KV KHARGHAR - PADGHE AT NERUL -10 KM 3) 2 X 500 MVA 400/220 KV ICT'S WITH BAYS 4) 220 KV D/C LINE FROM 400 KV NERUL TO 220 KV NERUL-5 KM 9 400KV NALASOPARA S/S THANE 1) 2X500MVA ,400/220KV ICT 400 KV Nalasopara S/s is Considered for upcomming load near (2013-14) 2) SCOPE CONSIDERED IN 765KV PADGHE-II (PG) by area. S/STN 3) 220KV NALASOPARA-VASAI D/C LINE-20KM

4) INTER LINK D/C LINES BETWEEN EXISTING 220KV NALASOPARA - 400KV NALASOPARA 15KM 10 400KV AMBERNATH S/S THANE 1) 2X500MVA ,400/220KV ICT 400 KV Ambernath S/s is considered for existing and upcomming (2014-15) 2) LILO ON 400KV PADGHE - NAGOTHANE D/C LINE AT load near by area. 400KV AMBERNATH- 10KM 3) 220KV D/C LINE BETWEEN 400KV AMBERNATH- 220KV AMBERNATH(ANANDNAGAR) -2.5KM 4) REORIENTATION OF 220KV LINES - 20KM ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 100KV LINK LINE RAIGAD 1) 100 KV MHASALA -KANDALGAON SCDC LINE 37 KM 100kV Mhasala S/S is fed from 100kV Kandalgaon S/s with S/c (2012-13) line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

2 100kV LINK LINE THANE 1) 100KV IOL - STANDARD D/C LINE USING U.G CABLE - Single source to be made double. (2012-13) 5KM ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 220 KV LINK LINE THANE 1) 220KV AMBERNATH -II - PADGHE D/C LINE WITH BAYS- Since the existing 220kV Ambernath-Padghe S/c line is critically (2010-11) 20 KMS loaded to an extent of 199 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

2 220 KV LINK LINE THANE 1) 220KV AMBERNATH - II - DOMBIVLI-II SCDC LINE Since the existing 220kV Dombivali-Ambernath S/c line is loaded (2010-11) WITH BAYS- 15 KMS to an extent of 147 MW during Non-Coinsident peak condition and Ambernath is an industrial zone hence it is necessary to propose additional line to meet additional load growth and contingency.

86 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

3 220 KV LINK LINE (2010-11, THANE 1) COVERSION OF EXISTING D/C TOWER IN TO M/C Existing Kharghar-Kalwa S/C line is of 1971. Existing Boiser JULY 2010) NARROW BASE TOWER USING EXISTING CORRIDOR (MSETCL)- Borivali (MSETCL) S/C line is of 1973. For FROM 220KV KHARGHAR-KALWA-BORIVALI-BOISAR. srengthening of network and upcoming future demand of mumbai 2) REPLACEMENT OF 0.4 ACSR CONDUCTOR, WITH AAAC area this work is proposed. TWIN CONDUCTOR a) 220KV LILO PT OF TARAPUR - BORIVALI- 95KM b) 220 KV LILO PT OF MULUND- BORIVALI - 15KM c)220 KV KALWA -LILO PT OF MULUND -6.2KM d) 220KV KALWA - LILO PT OF MAHAPE - 8.1KM e) 220 KV LILO PT OF MAHAPE- LILO PT OF TIFFIL- 1.6KM f) 220KV LILO PT OF TIFFIL - LILO PT OF TROMBAY - 31KM g) 220KV LILO PT OF NERUL - KHARGHAR -9.7KM 3) REPLACEMENT OF 0.4 ACSR CONDUCTOR, WITH AAAC TWIN CONDUCTOR OF 220KV KHARGHAR - KALWA - BORIVALI - BOISAR S/C ON M/C. 4) STRINGING OF D/C ON M/C FROM 220KV KHARGHAR - BORIVALI-BOISAR WITH AAAC TWIN CONDUCTOR BYPASSING KALWA SWITCHYARD WITH 220KV CABLES.- 125KM 5) *LILO OF EXISTING S/C BOISER (MSETCL) - BORIVALI (MSETCL) AT 220KV GHODBUNDER (R-INFRA). (*THIS WORK WILL BE DONE BY M/S R-INFRA) - 10KM 4 220KV LINK LINE THANE 1 200KV PEDAMBE- TAMBATI (APTA) LINE AT MAHAD - Strengthining of existing network. (2010-11) 160KM

5 132KV LINK LINES THANE 1 2ND CIRCUIT STRINGING OF 132KV LINE FROM 220KV Since the existing 132kV Boisar - Boisar MIDC S/C line is loaded (2010-11) BOISER-132KV BOISAR MIDC- 8.5KM to an extent of 67MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

6 220 KV LINK LINE THANE 1) 220 KV APTA - IPCL SCDC LINE - 55 KM Since the existing 220kV Wadkhal-IPCL S/c line is getting loaded (2011-12) to an extent of 151 MW. It is anticipated the load will reach to critical value by the year 2011-12. Hence it is suggested to add proposed line to meet additional load growth and contingency.

7 100kV LINK LINE THANE 1) 100kV MURBAD - SHAHAPUR DC LINE WITH BAYS-30 Strengthining of existing network. (2011-12) KMS 8 220KV LINK LINE (2011- THANE 1) 220KV APTA - WADKHAL D/C -25KM Strengthining of existing network. 12) 9 220KV LINK LINE (2011- THANE 1) 220KV COLOURCHEM - KOLSHET D/C -8KM Strengthining of existing network. 12) 10 132KV LINK LINES THANE 1) 132KV DAHANU - PALGHAR D/C LINE WITH BAYS - 30 Strengthining of existing network. (2011-12) KMS 11 100kV LINK LINE THANE 1) 100KV BHIVANDI - PADGHE D/C -25KM USING HIGH Strengthining of existing network. (2011-12) AMPICITY CONDUCTOR 12 100kV LINK LINE THANE 1) CONVERSION OF TEMGHAR TAP OF 100KV BHIVANDI - Strengthining of existing network. (2011-12) PADGHE LINE USING HIGH AMPICITY CONDUCTOR (BETWEEN LOC NO. 1 - 53) . 13 132KV LINK LINES THANE 1) 132KV BOISAR-I - BOISAR-II - 7 KM USING HIGH Strengthining of existing network. (2011-12) AMPICITY CONDUCTOR 14 220 KV LINK LINE THANE 1) 220KV TALOJA - 400KV PANVEL (PG) D/C LINE - 28 KM Line is required considering increasing load growth in nearby area (2013-14) ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE 1 220 KV LINK LINE RAIGAD 1) 220KV KHARGHAR - NEW MUMBAI SCDC LINE WITH Linking to New 400 kV New (2011-12) BAYS- 50 KMS Mumbai S/s STRENGTHENING FOR EVACUATION ARRANGEMENT 1 400 KV LINK LINE AHMEDNAGA 1) 400KV D/C LINE FROM 400KV BABLESWAR - PADGHE - Strengthening for wind power evacuation at Nasik and (2011-12) R/ THANE II(KUDUS) -153KM Doindaicha AUGMENTATION OF S/S BY ADDITION OF ICT / TF AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT / TF 1 400 kV PADGHE THANE 1) Add 1x500 MVA 400/220 KV ICT bays Existing transformer capacity available in S/s is 3 x 315 MVA ( 2010 - 11 ) 2) 3 x 220 kV Line bays And the Load reach is 875 MVA.Considering the maximum load reached on the ICTs in the event of interruptions/outage on any one of the transformer other ICTs' should take care of existing load

2 220 kV KOLSHET Thane 1) Add 1x50 MVA 220/22 KV T/F with GIS bays Existing transformer capacity available in S/s is 2 x 25 (2010-11) 2) 4 x 22 kV outlets And the Load reach is 63 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 2 220 kV KALWA Thane 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 81 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 3 220 kV TEMGHAR Thane 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 78 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 4 220 kV MAHAPE Thane 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 82 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 87 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

5 220 kV NERUL Thane 1) Add 1x50 MVA 220/33-22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 75 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

6 220 kV WADA Raigad 1) Add 1x50 MVA 220/22 KV T/F with GIS bay Existing transformer capacity available in S/s is 3 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 99 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 7 220 kV VASAI Raigad 1) Add 2x50 MVA 220/22 KV T/F with bay To reduce the loading on 100 kV VASAI (2010-11) 2) 8 x 22 kV outlets

8 100 kV MOHNE Thane 1) Add 1x50 MVA 220/22 KV T/F with 22KV GIS bay Existing transformer capacity available in S/s is 2 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 56 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

9 100 kV APTA Raigad 1) Add 1x25 MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 20 (2010-11) 2) 4 x 22 kV outlets And the Load reach is 15 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 10 400KV KHARGHAR S/S THANE 1) 1 X 500 MVA, 400/220KV ICT WITH BAYS Existing transformer capacity available in S/s is,400/220 kV , 2 x (2011-12) 315 MVA and the load reached is 386 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 11 220 kV KOLSHET Thane 1) Add 1x50 MVA 220/22 KV T/F with GIS bay Existing transformer capacity available in S/s is 2 x 50 (2011-12) 2) 6 x 22 kV outlets And the Load reach is 63 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 12 100 kV JITE Raigad 1) Add 1 X 25 MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 1 x 25 MVA and (2012-13) 2) 4 x 22 kV outlets the Load reach is 8 MVA.To avoid the loss of supply in case of outages or interruptions of transformers.

13 220 kV MAHAD Raigad 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 3 x 50 (2013-14) 2) 6 x 22 kV outlets And the Load will reach 102 MVAin year 2013-14. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

14 220KV KAMBA THANE 1) Add 1x 50 MVA ,220/22kV with GIS Bays. For redundancy. ( 2013-14)

15 100 kV SHAHAPUR Thane 1) Add 1x25 MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 25 (2013-14) 2) 4 x 22 kV outlets And the Load reach is 32 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

AUGMENTATION OF S/S BY REPLACEMENT OF ICT 1 220 kV BOISAR-II Thane 1) 1 X(100- 50) MVA ,220/33-22 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 50 MVA and (2010-11) 2) 6 X 33/22 kV out lets. load is 40. MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

2 220KV KALWA S/S THANE 1) 1x(200-125)MVA, 220/100KV ICT'S WITH BAYS Existing transformer capacity available in S/s will be ,220/100kV, (2010-11) 2) 100 KV BAYS - 02 NOS 3 x 125MVA and 1 X 200 MVA and load will reach 440MVA considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 3 220KV TROMBAY S/S MUMBAI 1) 1x(200-125)MVA, 220/100KV ICT'S WITH BAYS Existing transformer capacity available in S/s will be 220/100kV, (2010-11) 2) 100 KV BAYS - 02 NOS 1 x 125MVAand1X 200 MVA and the load will reach198MVA,Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 4 220KV BORIVLI S/S MUMBAI 1) 1x(200-125)MVA, 220/100KV ICT'S WITH BAYS Existing transformer capacity available in S/s is 220/100kV 2 x (2010-11) 2) 100 KV BAYS - 02 NOS 125MVAand the load reached is 223MVA,Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 5 220KV BOISAR II S/S THANE 1) 1x(200-150)MVA, 220/100KV ICT'S WITH BAYS Existing transformer capacity available in S/s is 220/132kV 2 x (2010-11) 2) 100 KV BAYS - 02 NOS 150MVAand the load reached is 207MVA,Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 6 220 KV TALOJA S/S RAIGAD 1) 1x(200-100)MVA, 220/100KV ICT'S WITH BAYS Existing Transformer capacity available is 2 X 100 MVA and load (2010-11) 2) 100 KV BAYS - 02 NOS reached is 83 MVA, Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 88 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

7 220 kV WADKHAL Raigad 1) 1x(50-20) MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 1 x 20 , 1 x 50 (2010-11) 2) 4 x 22 kV outlets and the Load reach is 25 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

8 220 kV COLOURCHEM Thane 1) 1x(100-50) MVA 220/22-22 KV T/F with bay Existing transformer capacity available in S/s is 4 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 130 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

9 220 kV MULUND Mumbai 1) 1x(100-50) MVA 220/22-22 KV T/F with bay Existing transformer capacity available in S/s is 4 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 169 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

10 100 kV THAL Raigad 1) 2x(50-25) MVA 100/22 KV T/F with bay Existing transformer capacity available in S/s is 2 x 25 (2010-11) 2) 4 x 22 kV outlets And the Load reach is 27 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

11 220KV KAMBA THANE 1) 1x(100- 50) MVA ,220/22-22kV with GIS Bays. For redundancy. ( 2010-11) 2) 4 x 22 kV outlets 12 132 kV PALGHAR Thane 1) 1 X (50-25) MVA,132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 MVA and (2010-11) 2) 4 X 33 kV outlets. load is 44 MVA. The transformer is replaced to meet anticipated load growth. 13 100 kV TALOJA-I Raigad 1) 1 X ( 50-20) 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 20 , (2010-11) 2) 4 X 22 kV outlets. 1 x 25 and the Load reach is 46 MVA. The T/F is replaced to meet anticipated load growth

14 100 kV MHSALA Raigad 1) 1 X ( 50-12.5) 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 12.5 (2010-11) 2) 4 X 22 kV outlets. and the Load reach is 19 MVA. The T/F is replaced to meet anticipated load growth

15 220 kV URAN Raigad 1) 1 X ( 50-25) 220/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25 (2010-11) 2) 4 X 22 kV outlets. and the Load reach is 41 MVA. The T/F is replaced to meet anticipated load growth

16 220 kV NALASOPARA Thane 1) 1x(100-50) MVA 220/22-22 KV T/F with GIS bay Existing transformer capacity available in S/s is 3 x 50 (2010-11) 2) 6 x 22 kV outlets And the Load reach is 63 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 17 220 kV MULUND Mumbai 1) 1x(100-50) MVA 220/22-22 KV T/F with bay Existing transformer capacity available in S/s is 4 x 50 (2011-12) 2) 6 x 22 kV outlets And the Load reach is 169 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

18 400 KV NAGOTHANE S/S RAIGAD 1) 1 X (500-315)MVA, 400/220KV ICT WITH BAYS Existing Transformer capacity available is 2 X 315 MVA and load (2011-12) 2) 220KV BAYS - 02 NOS reached is 487 MVA, Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

19 220 kV COLOURCHEM Thane 1) 1x(100-50) MVA 220/22-22 KV T/F with bay Existing transformer capacity available in S/s is 4 x 50 (2011-12) 2) 6 x 22 kV outlets And the Load reach is 130 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

20 220 kV BOISAR-II Thane 1) 1 X(100- 50) MVA ,220/22-22 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 50 MVA and (2011-12) 2) 6 X 33 kV out lets. load is 40. MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

21 220KV KAMBA THANE 1) 1x(100- 50) MVA ,220/22-22kV with GIS Bays. For redundancy. ( 2011-12) 2) 4 x 22 kV outlets

22 132 kV BOISAR MIDC Thane 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 MVA. And (2011-12) 2) 4 X 33 kV outlets. the load reached is 40 MVA The transformer is replaced to meet anticipated load growth.. 23 100 kV TALOJA-I Raigad 1) 1 X ( 50-25) 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 20 , (2011-12) 2) 4 X 22 kV outlets. 1 x 25 and the Load reach is 46 MVA. The T/F is replaced to meet anticipated load growth

24 100 kV MHSALA Raigad 1) 1 X ( 50-12.5) 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 12.5 (2011-12) 2) 4 X 22 kV outlets. and the Load reach is 19 MVA. The T/F is replaced to meet anticipated load growth

25 220 kV NALASOPARA Thane 1) 1x(100-50) MVA 220/22-22 KV T/F with GIS bay Existing transformer capacity available in S/s is 3 x 50 (2011-12) 2) 6 x 22 kV outlets And the Load reach is 63 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of

89 STU/TRANS/DOC-04/ W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 WASHI EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

26 100 kV PATALGANGA Raigad 1) 1 X ( 50-25) 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25 (2012-13) 2) 4 X 22 kV outlets. and the Load reach is 32 MVA. The T/F is replaced to meet anticipated load growth 27 220 kV TAMBATI-II Raigad 1) 1 X ( 50-25) 220/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25 (2012-13) 2) 4 X 22 kV outlets. and the Load reach is 32 MVA. The T/F is replaced to meet anticipated load growth 28 100 kV NOCIL Raigad 1) 1 X ( 50-25) 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25 (2012-13) 2) 4 X 22 kV outlets. and the Load reach is 38 MVA. The T/F is replaced to meet anticipated load growth

29 132 kV DAHANU Thane 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 25 MVA, 1 X (2012-13) 2) 4 X 33 kV outlets. 50 MVA. And the load reached is 33 MVA The transformer is replaced to meet anticipated load growth..

30 100 kV PATALGANGA Raigad 1) 1 X ( 50-25) 100/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25 (2013-14) 2) 4 X 22 kV outlets. and the Load reach is 32 MVA. The T/F is replaced to meet anticipated load growth 31 220 kV TAMBATI-II Raigad 1) 1 X ( 50-25) 220/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25 (20013-14) 2) 4 X 22 kV outlets. and the Load reach is 32 MVA. The T/F is replaced to meet anticipated load growth 32 220 kV URAN Raigad 1) 1 X ( 50-25) 220/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25 (2013-14) 2) 4 X 22 kV outlets. and the Load reach is 41 MVA. The T/F is replaced to meet anticipated load growth

* COMMISSIONED IN 2009-10 ** 1No. TF COMMISSIONED IN 2009-10

90

EHV CC O&M ZONE : PUNE

91 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION SPILL OVER SCHEMES 400KV CHAKAN S/S PUNE 1) 2 X 315 MVA, 400/220KV ICT WITH BAYS & 1 X 105MVA The existing 400/220kV station at Lonikand is overloaded 1 * (2008-09) SPARE ICT leading low voltage profile in pune circle. By the 2) 400KV CHAKAN - PUNE (PG) S/C LINE - 20 KM commissioning of this substation, voltage profile of Pune ring main Circle will improve to 0.93pu. Chakan-400kV is 3) LILO OF 400 KV LONIKAND-PADGHA AT CHAKAN S/S - connected from Lonikand by onstructing 400kV D/C line of 15 KM 28kM length. 4) 220KV CHAKAN - TALEGAON (PG) D/C - 20KMS

5) 220KV LILO ON EXISTING BHOSARI-CHINCHWAD S/C LINE - 15 KMS 6) 3 X 50 MVA, 220/22KV T/F 7) 22 KV OUTLETS - 18 NOS.

2 220KV KHADAKWASLA PUNE 1) LILO OF 220 KV CHINCHWAD-THEUR S/C- 12 CKTS VOLTAGE IMPROVEMENT & LOAD CATERING S/S (NANDED CITY) WITH BAYS (2008-09) 2) 2X50 MVA, 220/22KV T/FS WITH BAYS 3) 12X22KV OUTLETS 3 220KV TALEGAON PUNE 1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS Talegaon 220kV S/S is considered for meeting the existing (2008-09) loads in Pune circle. Talegaon-220kV S/S is feed from 2) 400KV PGCIL PUNE -TALEGAON S/S - 40 KM D/C LINE Urase by constructing 220kV M/C line of 7kM. WITH BAYS 3) 220 KV URSE-TALEGAON D/C LINE. 4) 12 X 22 KV OUTLETS

4 220KV GIS-KHARDI PUNE 1) 2 X 50 MVA, 220/33KV T/FS WITH BAYS Present recorded peak load on Khardi-132 V is 70MW. It is (2008-09) anticipated by the year 2009-10 the load will reach to about 2) 33KV OUTLETS - 12 NOS. 90MW. Hence it is necessary to go in for 220kV sub-station 3) 220KV D/C LINE FROM LONIKAND-KHARDI 5 KMS WITH at Khardi. Khardi-220kV S/S is fed from Lonikand- BAYS 400/220kV S/S by constructing 220kV D/C line of 25kM length. 5 220KV RAJGURUNAGAR PUNE 1) 2 X 50 MVA, 220/33KV T/FS WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING (2008-09) 2) 2 X 100MVA, 220/132KV ICT WITH BAYS

3) 220 KV LINE FROM CHAKAN - RAJGURUNAGAR D/C - 15 KMS 4) LILO ON 220KV LONIKAND - PARGAON S/C AT RAJGURUNAGAR 10 KMS WITH BAYS 5) LILO ON 132 KV CHINCHWAD-NARAYANGAON-10 KM WITH BAYS 6) 33KV OUTLETS - 8 NOS

6 132KV SOLAPUR 1) 132/33KV, 2 X 25MVA T/FS WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING NAVI - VES S/S 2) 8 X 33KV OUTLETS. (2008-09) 3) 132KV LINE BAYS -02 NOS

7 132 KV BIBWEWADI S/S PUNE 1) LILO ON 132 KV PHURSUNGI - RAHATANE- 10 KM Bibwewadi132kV S/S is considered for reducing the loading (2008-09) on Phursangi & Khothrod and also to improve the voltage 2) 2 X 50 MVA, 132/22 KV T/FS WITH BAYS profile in Pune Circle. This new Substation is proposed on 3) 22 KV OUTLET - 12 NOS, LILO of existing Phursangi–Khothrod 132kV line.

8 132KV PUNE 1) 2 X 50MVA, 132/22KV T/FS WITH BAYS Rastapeth 132kV S/S is considered for reducing loading on RASTAPETH G.I.S S/S Parvathi S/S and for strengthening in Pune circle. (2008-09) 2) 2 X 25MVA, 132/11KV T/FS WITH BAYS Rastapeth-132kV S/S is fed from Parvati 220/132 kV S/S 3) 12 X 22KV OUTLETS, BUS SECTIONALISER & by constructing 132kV S/C line of 8kM INCOMMERS 4) 12 X 11KV OUTLETS, BUS SECTIONALISER & INCOMMERS 5) SCADA SYSTEM FOR 132 KV

6) 132KV U.G CABLE XLPE SINGLE CORE 4 CABLE FROM PARVATI - RASTAPETH - 8KM. 9 RENOVATION OF 100KV PUNE 1) RENOVATION OF 100KV LINE GANESHKHIND - STRENTHENING THE SUPPLY NETWORK GANESHKHIND - KHOPOLI - 70 CKM. KHOPOLI D/C 10 UPGRADATION OF PUNE 1) ERECTION 2 X 25 MVA, 132/22KV T/FS WITH BAYS STRENTHENING THE SUPPLY NETWORK 100KV GANESHKHIND 2) 3 X 25 MVA, 132/11 KV T/FS WITH BAYS S/S TO 132KV 3) REPLACEMENT OF 22KV EQUIPMENT 4) DISMENTALLING OF 110/33KV/110/11KV T/F AT BARSHI, 11 400KV PUNE (PG) PUNE SANGOLA,SCOPE OF PULUJ,WORK BYDIGANCHI, MSETCL DEGAON Pune-PGCIL is constructed by PGCIL and will facilitate (2009-10) LILO ON 220KV HINJEWADI - CHINCHWAD S/C TO additional infeed to pune circle 1) PUNE (PG) - 25 KMS WITH BAYS 12400 KV SOUTH SOLAPUR SCOPE OF WORK BY MSETCL Evacuation of Power from PG. SOLAPUR S/S(PGCIL) 400KV D/C LINE FROM SOUTH SOLAPUR(PG)- (2009-10) 1) SOLAPUR (MSETCL)-20KM 2) 220 KV DC LINE FROM 400/220KV SOUTH SOLAPUR (PG) - SOUTH SOLAPUR (MSETCL) S/S - 5 KM WITH BAYS 3) 220KV DC LINE FROM 400KV SOUTH SOLAPUR - PANDHARPUR - 60KM

92 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION 13 400 KV LONIKAND-II S/S PUNE 1) 2 X 500 MVA, 400/220 KV ICT WITH BAYS To improve the voltage profile of the area and to cater the (2009-10) 1 X 167 MVA, 400/220 KV SPARE ICT WITH BAYS upcomming load. 2) LILO OF 400 KV PARLI (PG)-PUNE (PG) D/C AT LONIKAND-II S/S-30 KM 3) 220 KV LONIKAND-II-THEUR D/C LINE WITH BAYS- 18 KM 4) 220 KV LONIKAND-II-CHAKAN D/C LINE WITH BAYS- 28 5) 220KM KV LONIKAND-II-RAJGURUNAGAR D/C LINE WITH 6) 220BAYS- KV 40 DC KM LINE FROM 400KV LONIKAND-II - 220KV VSNL DIGHI WITH BAYS- 25 KM ( OH LINE 16.9KM &UG CABLE 8.1KM ) (2010 -2011) 14 220 KV SOUTH SOLAPUR 1) 2 X 100 MVA, 220/132 KV ICT'S WITH BAYS South Solapur-220kV S/S is considered for evacuating SOLAPUR (MSETCL) S/S power from the proposed 400/22kV sub-station of South (2009-10) solhapur by PGCIL. By the commissioning of this 2) 2 X 25 MVA, 220/33 KV T/FS WITH BAYS substation, voltage profile will improve to 1.0pu from 0.93pu.

3) LILO OF 132 KV SOLAPUR - AKKALKOT AT SOUTH SOLAPUR S/S - 5 KM

4) 220KV DC LINE FROM 220KV SOUTH SOLAPUR - BALE - 10KM

5) 33KV OUTLETS - 8 NOS

15 220KV AKURDI PUNE 1) 3 X 50MVA, 220/22KV T/FS WITH BAYS The loads around Chinchwad-is 80MW. It is anticipated by (2009-10) the year 2009-10 that the load will reach to about 96MW. 2) LILO ON 220KV BHOSARI (AKURDI) -TELCO S/C LINE Hence it is necessary to go in for new 220kV sub-station at 1.6 KMS WITH BAYS Akurdi. 3) 33KV OUTLETS - 8 NOS

16 132 KV SOMESHWAR PUNE 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS It is anticipated by the year 2009-10 that the load will reach NAGAR S/S 2) LILO ON 132KV LONAND -PHALTAN LINE 7KM FROM to its extent near baramati region . To avoid interruptions (2009-10) LOCATION NO. 29 due to over loading Someshwar nagar-132kV S/S is considered. 3) 8 X 33 KV OUTLETS 17 UPGRADATION OF PUNE 1) 2 X 50MVA, 220/22KV T/FS WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING 220KV CHAKAN S/S 2) 12 X 22KV OUTLETS (2009-10) 3) 220 KV D/C ON D/C FROM 220 KV PARGAON TO 220 KV CHAKAN -20KMS 4) 220 KV M/C ON M/C FROM 220 KV CHAKAN- 132 KV NARAYANGAON -20 KMS 5) 220 KV D/C ON D/C FROM 220 KV NARAYANGAON SUBSTATION TO 220 KV ALEPHATA S/S -19 KMS 6) 220 KV M/C ON M/C FROM 220 KV CHAKAN- 220 KV CHINCHWAD -35 KMS 7) 220 KV M/C ON M/C LILO ON 220 KV CHAKAN- 220 KV CHINCHWAD -5 KMS 8) 220 KV LINE BAYS - 8 NOS 9) 132 KV LINE BAYS-7 NOS 10) 220 KV XLPE CABLE- 1.62 KM 11) 132 KV XLPE CABLE-0.9 KM 18 132 KV KARAJGI S/S SOLAPUR 1) 2 X 25MVA, 132/33KV T/FS WITH BAYS Present recorded peak load on Akkakalkot-132kV is 40MW. (2009-10) It is anticipated by the year 2009-10 that the load will reach 2) 132KV SCDC LINE FROM AKKALKOT-KARAJGI - 20 KM to about 50MW. Hence it is necessary to go in for new WITH BAYS 132kV sub-station at Karjagi. The new Karjagi-132kV S/S is 3) 33KV OUTLETS - 8 NOS proposed in year 2009-10 for reducing loading on Akkakalkot-132kV.

19 132 KV WAGDARI S/S SOLAPUR 1) 2 X 25MVA, 132/33KV T/FS WITH BAYS Wagdari (Gogaon)-132kV S/S is considered for meeting (GOGAON) 2) 132KV AKKALKOT-WAGDARI (GOGAON) - S/C LINE ON load growth in and around Solhapur. (2009-10) D/C TOWER - 25 KM WITH BAY 3) 132KV NALDURG-WAGDARI (GOGAON) S/C D/C - 25 KM WITH BAY 4) 33KV OUTLETS - 8 NOS 20 132 KV SOREGAON S/S SOLAPUR 1) 2 X 25MVA, 132/33KV T/FS WITH BAYS Soregaon-132kV S/S is considered to meet the load growth (2009-10) in Solapur ring main. 2) LILO ON 132KV MANDRUP - DEGAON S/STN - 5 KM WITH BAYS 3) 33KV OUTLETS - 8 NOS 21 132 KV SHANKARNAGAR SOLAPUR 1) 132 KV D/D LINE FROM 220 KV MALINAGAR S/S 6 KMS 132 KV Shankarnagar substation is proposed for catering (2009-10) WITH BAYS upcomming load nearby Akaluj. 2) 2 X 25 132/33 KVT/F 3) 33 KV OUTLETS 8 NOS. 22 132KV BORIVEL PUNE 1) 2X25MVA, 132/33KV T/F System Strengthining (2009-10) 2) 132KV D/C LINE FROM 220KV KURKUMBH S/STN-15KM

3) 33KV OUTLETS - 8 NOS 23 132KV RUDDEWADI SOLAPUR 1) 2X25MVA, 132/33KV T/F System Strengthining (2009-10) 2) 132KV D/C LINE FROM AKKALKOT -22KM 3) 33KV OUTLETS - 8 NOS

93 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 132KV LINK LINE PUNE 1) 132KV YAWAT - THEUR SCDC LINE - 23 KM 132kV Yawat S/S is fed from 132kV Theur S/s with S/c line. (2008-09) Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 2 132KV LINK LINE PUNE 1) 132KV KURULI - RANJANGAON SCDC - 20 KM 132kV Kuruli S/S is connected with 132kV Ranjangaon S/s (2008-09) with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

3 132KV LINK LINE* SOLAPUR 1) 132KV LINE FROM 220KV SOLAPUR II - MOHOL SCDC 132kV Mohol S/S is connected with 220kV Solapur S/s with (2009-10) LINE - 32 KM S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 132KV LINK LINE PUNE 1) 132 KV CHINCHWAD - MARKAL SCDC LINE - 29 KMS Since the existing 132kV Theur-Kharadi S/c line is getting (2008-09) WITH BAYS loaded to an extent of 34 MW. It is anticipated the load in Pune district will reach to critical value by the year 2011-12. Hence it is suggested to add proposed line to meet additional load growth and contingency.

2 132KV LINK LINE PUNE 1) 132 KV NCL PUNE - KOTHRUD SCDC LINE - 6.4 KMS Since the existing 132kV NCL-Rahatane S/c line is critically (2008-09) WITH BAYS loaded to an extent of 75 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

3 132KV LINK LINE PUNE 1) 132 KV CHINCHWAD - RAHATANE SCDC LINE - 6 KMS Since the existing 132kV Chinchwad-Rahatane S/c line is (2008-09) WITH BAYS critically loaded to an extent of 82.6 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. 4 132KV LINK LINE PUNE 1) 132 KV PHURSUNGI - THEUR SCDC LINE - 14 KMS Since the existing 132kV Theur-Phursangi S/c line is (2008-09) WITH BAYS critically loaded to an extent of 103 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. 5 132KV LINK LINE PUNE 1) 132 KV PHURSUNGI - MUNDWA SCDC LINE - 12 KMS Since the existing 132kV Mundwa-Phursangi S/c line is (2008-09) WITH BAYS critically loaded to an extent of 103 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. 6 132KV LINK LINE PUNE 1) 132 KV NCL PUNE - RAHATANE SCDC LINE - 6.4 KMS Since the existing 132kV NCL Pune-Rahatane S/c line is (2008-09) WITH BAYS critically loaded to an extent of 75 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. 7 132KV LINK LINES PUNE 1) 132KV STRINGING OF IIND CIRCUIT CHINCHWAD - Since the existing 132kV Chinchwad - Rahatane line is (2009-10) RAHATANE -NCL-12.4KM loaded to an extent of 67 MW and 132kV Rahatane - NCL line is loaded to an extent of 89 MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

1 132KV LINK LINE PUNE 1) 132 KV CHAKAN - URSE SCDC LINE - 20 KMS WITH Only single ckt and single source is available at Urse S/S. (2009-10) BAYS 2 220 KV LINK LINE RAIGAD 1) LILO ON 220 KV APTA - CHINCHWAD LINE FOR URSE Linking to New 220 kV Urse S/s (2009-10) S/S ON IIND CKT - 22 KM AUGMENTATION OF S/S BY ADDITION OF T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE 1 400KV AUGMENTATION PUNE SOLAPUR 1) 3 X 167 MVA, 400/220KV ICT WITH BAYS To avoid loss of supply in case of outages or interruptions AT JEJURI & SOLAPUR * on any one transformer (2008-09) 2 132 KV JANAI S/S PUNE 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 4 X 33 KV OUTLETS

3 132KV PAREWADI S/S SOLAPUR 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 4 X 33 KV OUTLETS 4 220 KV KURKUMBH S/S PUNE 1) 1X200 MVA, 220/132 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) 2) 2X132 KV BAYS on any one transformer 5 220 KV BARAMATI S/S PUNE 1) 1X100 MVA, 220/132 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 2X132 KV BAYS

6 220 KV RANJANGAON PUNE 1) 1X100 MVA, 220/132 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions S/S 2) 1X50 MVA, 220/22 KV T/F WITH BAYS on any one transformer (2008-09) 3) 132 KV BAY - 2 NOS. 4) 6X22 KV OUTLETS 7 132 KV SANASWADI S/S PUNE 1) 1X25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 4X22 KV OUTLETS 3) 3 CORE, 400SQMM, XLPE CABLE - 0.8 KM 94 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION 8 132 KV YAWAT S/S PUNE 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 4 X 33 KV OUTLETS 9 220 KV JEUR S/S SOLAPUR 1) 1X100 MVA, 220/132 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 2X132 KV BAYS

10 132KV PURANDWADE SOLAPUR 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions S/S on any one transformer (2008-09) 2) 4 X 33 KV OUTLETS 2) 22 KV OUTLETS - 4 NOS. 11 132 KV DAUND S/S PUNE 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x25 - 5 2) 4 X 33 KV OUTLETS To avoid loss of supply in case of outages or interruptions on any one transformer 12 132 KV KAMTHADI S/S PUNE 1) ADDL. 1 X 50 MVA, 132/22 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x 10 - 8MVA load 2) 4 X 33 KV OUTLETS 132/22 - 1 x 25 - 16MVA load 3) 4 X 22 KV OUTLETS To avoid loss of supply in case of outages or interruptions on any one transformer

13 400KV JEJURI S/S * PUNE 1) 1 X 500 MVA, 400/220 KV ICT WITH BAYS The existing Trans,Capacity is 400/220 kV 1 X500 MVA and (2009-10) the load reach is 529 MVA To avoid loss of supply in case of outages or interruptions on any one ICT addil. ICT Is proposed

14 220 KV PHURSUNGI S/S* PUNE 1) 1X200 MVA, 220/132 KV T/F WITH BAYS Existing transformer capacity available in S/s is 220/132 kV (2009-10) ,1 x 100 - load reach is 154MVA To avoid loss of supply in case of outages or interruptions on any one ICT addil. ICT Is proposed. 15 132 kV KAMTHADI Pune 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 10 MVA. And (2009-10) 2) 4 X 33 kV out lets the load reached is 6 MVA.To avoid loss of supply in case of outages or interruptions on transformer.

16 132 kV KURUDUWADI * Solapur 1) Add 1 X 50 MVA 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 50 MVA. And (2009-10) 2) 8 X 33 kV out lets the load reached is 26 MVA.To avoid loss of supply in case of outages or interruptions on transformer.

17 132 kV MARKAL* Pune 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. To (2009-10) 2) 4 X 33 kV out lets avoid loss of supply in case of outages or interruptions on transformer. 18 220 kV PIRANGUT Pune 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. And (2009-10) 2) 4 X 33 kV out lets the load reached is 15.1 MVA.To avoid loss of supply in case of outages or interruptions on transformer.

19 132 kV VELAPUR Solapur 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. And (2009-10) 2) 4 X 33 kV out lets the load reached is 14 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 20 132 kV SHIRUR Pune 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. And (2009-10) 2) 4 X 33 kV out lets the load reached is 5 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 21 220 kV BHIGWAN * Pune 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. And (2009-10) 2) 4 X 33 kV out lets the load reached is 14 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 22 220 kV PIRANGUT* Pune 1) Add 1 X 50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 1 X 50 and (2009-10) load reach is 24 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 2) 6 x 22 kV outlets

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER 1 220KV PARVATI S/S PUNE 1) 2X200MVA, 220/132KV ICTS WITH BAYS Newly Introduced 220/132kV level to feed Rastapeth S/s & (2008-09) the nearby area at proper voltage and to take care of 2) 4X132KV LINE BAYS anticipated load growth of the area. 3) 1X132KV TBC BAY 4) 220KV D/C LINE ON M/C TOWERS - 4 KM WITH BAYS 5) 132KV D/C LINE ON M/C TOWERS - 4 KM (STRINGING ONLY) 2 220 KV URSE S/S PUNE 1) 1X50 MVA, 220/22 KV T/F WITH BAYS New S/s (2008-09) 2) 6X22 KV OUTLETS 3 220 KV PARVATI S/S PUNE 1) 1X50 MVA, 220/22 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 2) 6X22 KV OUTLETS 220/22 - 3 x 50 -141 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

4 132 KV MARKAL S/S * PUNE 1) ADDL. 1 X 25 MVA, 132/22 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x 25 - 13 load 2) 4 X 33 KV OUTLETS 132/22 - 1 x 25 - Nil load 132/22 - 1 x 12.5 - 11 load Hence it is necessary to propose additional transformer to meet additional load growth and contingency.

95 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION 5 220KV TEMBHURNI S/S * SOLAPUR 1) ADDL. 1X25MVA, 220/33KV T/F WITH BAYS New S/s (2008-09) 2) 4X33KV OUTLETS

6220 KV MALINAGAR SOLAPUR 1) 1 X 50MVA, 132/33KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/132 - 1 x 100 - 48 load 220/33 - 2 x 50 - 56 load 2) 1X 200MVA, 220/132KV ICT WITH BAYS Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer 3) 6 X 33KV OUTLETS other transformer should take care of existing load so as to 4) 1 X 132KV BAY avoid load shedding. 7 220 KV ALEPHATA S/S PUNE 1) 1X100 MVA, 220/132 KV T/F WITH BAYS Existing transformer capacity available in S/s is 220/132 kV (2009-10) ,2 x 100 - load reach is 100MVA To avoid loss of supply in case of outages or interruptions on any one transformer addil. Trans. is proposed.

8 220KV THEUR S/S PUNE 1) 1X200 MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is,220/132, 1 (2009-10) x 150 MVA and 1 X 200 MVA and the load reach is 268 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

9 132kV MANGALWEDHA * Solapur 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X 25 MVA (2009-10) 2) 4 X 33 kV out lets. and load is 20 MVA. Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 10 132 kV BARAMATI Pune 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X 25, 1 X (2009-10) 2) 4 X 33 kV out lets. 50 MVA and load is 34 MVA. Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 11 132 kV JEJURI Pune 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25MVA (2009-10) 2) 4 X 33 kV out lets. and load is 27 MVA. Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 12 132 kV NARAYANGAON Pune 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25MVA (2009-10) 2) 4 X 33 kV out lets. and load is 31 MVA. Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 13 132 kV CHAKAN - I * Pune 1) Add 1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X 25, 1 X (2009-10) 2) 6 X 33 kV out lets. 50 MVA and load is 51 MVA. Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

14 132 kV SANGOLA Solapur 1) Add 1 X 25 MVA , 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 50 (2009-10) 2) 4 X 33 kV out lets. MVA. And the load reached is 48 MVA The transformer is replaced to meet anticipated load growth 15 132 kV SOLAPUR - I Solapur 1) 1) Add 1 X 25 MVA , 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 (DEGAON) 2) 2) 4 X 33 kV out lets. MVA. And the load reached is 22 MVA The transformer is (2009-10) replaced to meet anticipated load growth.

16 132 kV KURUDUWADI Solapur 1) Add 1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 50 (2009-10) 2) 6 X 33 kV out lets. MVA. And the load reached is 26 MVA The transformer is replaced to meet anticipated load growth.

17 220 kV ALEPHATA Pune 1) Add 1 X 50 MVA , 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 50 (2009-10) 2) 6 X 33 kV out lets. MVA. And the load reached is 47 MVA Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 18 220 kV JEUR Solapur 1) Add 1 X 25 MVA , 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 MVA (2009-10) 2) 4 X 33 kV out lets. and load is 36 MVA. Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

19 132 kV YAVAT Pune 1) Add 1x50 MVA 132/22 KV T/F with bay Existing transformer capacity available in S/s is 1 X 50, 1 x (2009-10) 25 and load reach is 45 MVA.Considering the maximum load reached on the transformer in the event of 2) 6 x 22 kV outlets interruptions/outage on any one of the transformer other transformer should take care of existing load. 20 132 kV PHURSANGI-I Pune 1) Add 1x25 MVA 132/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 25 and (2009-10) load reach is 40 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other 2) 4 x 22 kV outlets transformer should take care of existing load.

21 220 kV LONIKAND Pune 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 50 and (2009-10) load reach is 53 MVA.Considering the maximum load 2) 6 x 22 kV outlets reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 22 220 kV CHINCHWAD Pune 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 3 X 50 and (2009-10) load reach is 120 MVA.Considering the maximum load 2) 6 x 22 kV outlets reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 96 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION 23 220kV HINJEWADI -I Pune 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 25 and (2009-10) load reach is 41 MVA.Considering the maximum load reached on the transformer in the event of 2) 6 x 22 kV outlets interruptions/outage on any one of the transformer other transformer should take care of existing load. 24 220 kV PHURSANGI-II Pune 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 50 and (2009-10) load reach is 70 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other 2) 6 x 22 kV outlets transformer should take care of existing load. 25 220 kV TELCO Pune 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 50 and (2009-10) load reach is 66 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other 2) 6 x 22 kV outlets transformer should take care of existing load. 26 220 kV THEUR Pune 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 50 and (2009-10) load reach is 75 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other 2) 6 x 22 kV outlets transformer should take care of existing load. AUGMENTATION OF S/S BY REPLACEMENT OF T/F 1 220 KV KARKAMBH S/S* SOLAPUR 1) 1 X ( 50 - 25) MVA, 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/33 - 2 x 25 - 34.40 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 2 220 KV SOLAPUR II S/S* SOLAPUR 1) 1 X (50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (BALE) 132/33 - 1 x 25 -18 load (2008-09) 132/33 - 1 x 50 - 31.43 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

3 132 KV CHAKAN S/S * PUNE 1) REP. 1 X (50-25) MVA, 132/22 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/22 - 2 x 50 - 76 load 132/22 - 2 x 25 - 39 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 4132KV SANGOLA S/S * SOLAPUR 1) 1X50 MVA 132-110/33KV T/F Existing transformer capacity available in S/s is, (2008-09) 132-110/33 - 2 x 25 - 36 load Considering the maximum load reach on the transformer, in 2) 6X33KV OUTLETS event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 5 132 KV MOHOL S/S* SOLAPUR 1) REP. 1 X (50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/22 - 1 x 50 - 39.3 load 110/22 - 1 x 25 - 20 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 6 132 KV AKKALKOT S/S* SOLAPUR 1) 2 X (50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 37 load Considering the maximum load reach on the transformer, in 2) 33 KV OUTLETS - 4 NOS. event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 7 132 KV SOLAPUR MIDC SOLAPUR 1) REPL. 1 X (50- 25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, S/S* 132/33 - 1 x 50 - 30 load (2008-09) 132/33 - 1 x 25 - 19 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 8 132 KV DEGAON S/S* SOLAPUR 1) REP.1 X ( 50 -25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 2) 33 KV OUTLETS - 3 NOS. 132/33 - 2 x 25 - 43 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 9 132 KV SANGOLA S/S* SOLAPUR 1) REPL. 1 X (50- 25) MVA, 132-110/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 36 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 10 132 KV INDAPUR S/S* PUNE 1) (25-16) MVA, 132/33 KV T/F Existing transformer capacity available in S/s is, (2008-09) 2) 2X33 KV OUTLETS 132/33 - 1 x 25 - 19 load 132/33 - 1 x 16 - 15 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 97 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION 11 110KV KURDUWADI S/S* SOLAPUR 1) 1X(50 - 25)MVA, 132-110/33KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/22 - 1 x 50 - 34.34 load 110/22 - 1 x 25 - 22.41 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 12 220KV RANJANGAON PUNE 1) 1X(200-100) MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is, 220/132,1 S/S (2009-10) x 100 MVA - load reach is- 86MVA replacement of existing transformer of 220/132 kV 1 x 100 MVA is being proposed during2009-10 to have sufficient capacity during interuption and to cater the load.

13 220KV CHINCHWAD PUNE 1) 1X(200-50) MVA ,220/132-110KV WITH BAYS Existing transformer capacity available in S/s is, 220/132,1 ( 2009-10) x 200 MVA and 2 x 50 MVA and the load reach is 144 MVA. Considering the maximum load reach on the transformer in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

14 220KV CHINCHWAD PUNE 1) 1X(200-50) MVA ,220/110-100KV WITH BAYS Existing transformer capacity available in S/s is, 220/110,1 ( 2009-10) x 50 MVAand 1 X 100 MVA and the load reach is 54.60 MVA. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

15 220 KV SOLAPUR-II S/S SOLAPUR 1) 1X(200-100)MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, 220/132,1 (2009-10) x200 MVA,1X150 and1X100MVA the load reach is 358 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

16 220KV PANDHARPUR SOLAPUR 1) 1X(200-100)MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, S/S(2009-10) 220/132 - 1 x 100 - load reach is 70 220/100 - 1 x 100 - 52 The transformers are replaced to meet anticipated load growth.

17 220KV BARAMATI S/S PUNE 1) 1X(100-50)MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, 220/132,1 (2009-10) x 50 MVA and the load reach is 30 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 18 220 kV KARKUMBH * Solapur 1) 1 X (50-25) MVA, 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 50 & 1 (2009-10) 2) 4 X 33 kV outlets. X 25 MVA and the load reached is 35 MVA The transformer is replaced to meet anticipated load growth.

19 132 KV MUNDHWA S/S PUNE 1) 1X(50-25) MVA, 132/22 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2009-10) 132/22 - 3 x 25 - 53.49 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer 2) 22 KV OUTLETS - 2 NOS. other transformer should take care of existing load so as to avoid load shedding.

20 132 kV NCL PUNE* Pune 1) 2 X ( 50-25) MVA 132/22 kV T/F with bays Existing transformer capacity available in S/s is 2 x 25 (2009-10) 2) 4 X 22 kV outlets. and the Load reach is 30 MVA.The T/F is replaced to meet anticipated load growth 21 132 kV SHIRUR Pune 1) 2 X ( 50-25) MVA 132/22 kV T/F with bays Existing transformer capacity available in S/s is 2 x 25 (2009-10) 2) 4 X 22 kV outlets. and the Load reach is 26 MVA. The T/F is replaced to meet anticipated load growth 22 132 kV Pune 1) 2 X ( 50-25) MVA 132/22 kV T/F with bays Existing transformer capacity available in S/s is 2 x 25 WALCHANDNAGAR* 2) 4 X 22 kV outlets. and the Load reach is 32 MVA. The T/F is replaced to meet (2009-10) anticipated load growth

23 132 kV MUNDHAWA Pune 1) 1 X ( 50-25) MVA 132/22 kV T/F with bays Existing transformer capacity available in S/s is 3 x 25 (2009-10) 2) 4 X 22 kV outlets. and the Load reach is 51 MVA. The T/F is replaced to meet anticipated load growth 24 132 kV KURULI Pune 1) 1 X(50- 25) MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. And (2009-10) 2) 4 X 33 kV out lets the load reached is 19 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 25 100 kV LONAWALA Pune 1) 1 X ( 50-25) MVA 132-100/22 kV T/F with bays Existing transformer capacity available in S/s is 1 x 16, 1 x (2009-10) 2) 4 X 22 kV outlets. 12.5 and the Load reach is 15 MVA.The T/F is replaced to meet anticipated load growth 26 100 kV TALEGAON-I Pune 1) 1 X ( 50-20) MVA 132-100/22 kV T/F with bays Existing transformer capacity available in S/s is 1 x 28, 1 x (2009-10) 2) 4 X 22 kV outlets. 25, 1 x 20 and the Load reach is 47 MVA.The T/F is replaced to meet anticipated load growth

98 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION NEW SCHEMES 1 400 KV HINJEWADI S/S PUNE 1) 2 X 500 MVA, 400/220 KV ICT WITH BAYS 400 kV Hinjewadi S/s is considered to cater the upcoming (2010-11) 1 X 167 MVA, 400/220 KV SPARE EHV load and for strengthening of Pune region. 2) 400 KV HINJEWADI - KESURDI D/C - 60 KM WITH BAYS 3) 220 KV INTERCONNECTION FROM 400 KV HINJEWADI- HINJEWADI-II - 5 KM 2 220 KV YEWALEWADI PUNE 1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING S/S (VSNL DIGHI) 2) LILO ON 220 KV LONIKAND - KHADAKI LINE - 2.2 KM (2010-11) 3) 22 KV OUTLET - 12 NOS 3 220KV KONDHWA PUNE 1) 2X50MVA,220/22KV T/F System strengthining (2010-11) 2) LILO ON 220KV CHINCHWAD-THEUR AT KONDHWA - 1KM 3) 22KV OUTLETS -12Nos 4 132KV NIMBONI SOLAPUR 1) 132KV D/C LINE FROM 132KV MANGALWEDHA - 22KM System strengthining (2010-11) 2) 2X25MVA, 132/33KV T/F 3) 33KV OUT LETS - 6 NOS. 5 132KV KARMALA SOLAPUR 1) 2X25MVA,132/33KV T/F System strengthining (2010-11) 2) 2nd CKT STRINGING OF 132KV JEUR - KARJAT LINE - 42KM 3) LILO OF ONE CKT OF 132KV JEUR - KARJAT LINE AT KARMALA - 16KM 4) 33KV OUTLETS - 06NOS. 6 220 KV PUNE 1) 220 KV D/C LINE FROM 220 KV BARAMATI -20 KM 220 KV Walchandnagar substation is proposed to reduce WALCHANDNAGAR 2) 220 KV D/C LINE FROM 220 KV PHALTAN (MIDC) -26 KM overloading of 132 KV Walchandnagar- Indapur line and to (2011-12) cater upcomming load in that area. 3) 2 X 100 MVA, 220/132 KV ICT'S WITH BAYS 4) 132 KV D/C LINE TO 132 KV WALCHANDNAGAR - 5 KM 4) 132 KV D/C TO INDAPUR - 35 KM 7 400 KV RETWADI S/S PUNE 1) 2 X 500 MVA, 400/220 KV ICT WITH BAYS 400 kV Retwadi S/s is considered to cater the upcoming (KHED,RAJGURUNAGAR 1 X 167 MVA, 400/220 KV SPARE SEZ load of 500MW of Pune region. ) (2014-15) 2) LILO ON 400 KV AURANGABAD-PUNE(PG) D/C - 20 KM WITH BAYS 3) 220 KV INTERCONNECTION FROM 400 KV RETWADI- RAJGURUNAGAR - 5 KM

ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 132KV LINK LINE PUNE 1) 132 KV DUAND - YAWAT SCDC LINE - 6 KMS WITH 132kV Yawat S/S is fed from 132kV Theur S/s with S/c line. (2010-11) BAYS Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 2 132KV LINK LINE SOLAPUR 1) 132KV PANDHARPUR - MANGALWEDHA SCDC LINE - 132kV Mangalwedha S/S is fed from 132kV Pandharpur S/s (2010-11) 22 KM with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

3 132KV LINK LINE SOLAPUR 1) 132KV KARAJGI - MANDRUP SCDC LINE - 22 KM 132kV Mandrup S/S is fed from 132kV Degaon S/s with S/c (2010-11) line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 4 132KV LINK LINE* SOLAPUR 1) 132 KV CHINCHOLIKATE TAP ON BALE (SOLAPUR-II)- 132kV Chincholikate S/S is Tapped on 132kV Bale-Mohol (2012-13) MOHOL S/C LINE - 1.8 KM S/c line & Also the requirement from MIDC of 40 MW. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 5 132KV LINK LINE SOLAPUR 1) 132 KV 2ND CIRCUIT LINE STRINGING FROM 132kV Parewadi S/S is fed from 132kV Jeur S/s with S/c (2012-13) PAREWADI -JEUR 22 KM line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 6 132KV LINK LINE PUNE 1) 132 KV SHIRUR -FROM 220KV RANJANGAON SCDC 132kV Shirur S/S is fed from132kV Supa S/s with S/c line. (2012-13) LINE - 26.0 KM Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 220 KV LINK LINE RAIGAD /PUNE 220 KV KANDALGAON -CHINCHWAD D/C ON M/C LINE - This line is of 1962. For strengthning of network this work is (2010-11) 60 KMS proposed. 2 132KV LINK LINE SOLAPUR 1) 132KV LINE FROM 220KV BALE - SOLAPUR MIDC DC Since the existing132kV Solapur - solapur MIDC line is (2010-11) STRINGING OF 2ND CIRCUIT- 16.5KM loaded to an extent of 56 MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

3 220KV LINK LINE SOLAPUR 1) 220 KV D/C LINE FROM VITA (KHARSUNDI) - Since the existing 220kV Vita-Pandharpur-Lamboti S/c lines (2011-12) PANDHARPUR -LAMBOTI- 160km are getting overloaded during noncoincident peak condition. Hence it is suggested to add proposed line to meet additional load growth and contingency. 4 132KV LINK LINES SOLAPUR 1) 132KV LINK LINE FROM 220KV SOUTH SOLAPUR TO System strengthining (2011-12) SOLAPUR MIDC - 30KMS 5 132KV LINK LINES SOLAPUR 1) 132KV CABLE FROM 220KV MAGARPATTA TO System strengthining (2011-12) RASTAPETH - 2X12KM ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE 1 220KV LINK LINE PUNE 1) 220 KV BHOSARI - CHAKAN D/C LINE - 22 KMS WITH Linking to New 400 kV Chakan S/s (2010-11) BAYS 2 132KV LINK LINES SOLAPUR 1) 132KV CABLE FROM 220KV MAGARPATTA TO KHARADI To have alternate source for Kharadi (2010-11) - 7.5KM 3 220KV LINK LINE PUNE 1) 220KV SOLAPUR -KARKAMB D/C LINE - 100KM To cater additional load on the S/S (2011-12)

99 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION AUGMENTATION OF S/S BY ADDITION OF ICT/T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE T/F IS AVAILABLE 1 132 kV KURULI Pune 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. To (2011-12) 2) 4 X 33 kV out lets avoid loss of supply in case of outages or interruptions on transformer. AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT/T/F 1 220 KV MALINAGAR SOLAPUR 1) 1X 100MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is, 220/132, 2 (2010-11) x 100 MVA and the load will reach 108 MVA. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 2 220 KV JEUR S/S SOLAPUR 1) 1X100 MVA, 220/132 KV T/F WITH BAYS Existing transformer capacity available in S/s is, 220/132 (2010-11) kV, 2 X100 MVA and the load will be 100 MVA To avoid loss of supply in case of outages or interruptions on any one transformer addil. trans. is proposed.

3 132 kV KHARADI Pune 1) Add 1x50 MVA 132/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 50 (2010-11) 2) 6 x 22 kV outlets and the Load reach is 60 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 4 132 kV AKKALKOT Solapur 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 50 & 1 (2010-11) 2) 4 X 33 kV out lets. X 25 MVA. And the load reached is 46 MVA Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

5 132 kV CHINCHOLI KATE Solapur 1) Add 1 X 25 MVA , 110/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 MVA (2010-11) 2) 4 X 33 kV out lets. and load is 22 MVA. Considerinh thre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 6 132 kV SOLAPUR MIDC Solapur 1) Add 1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X 25 , (2010-11) 2) 6 X 33 kV out lets. 1X50 MVA and load is 52 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 7 132 kV Pune 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 MVA WALCHANDNAGAR 2) 4 X 33 kV out lets. and load is 20 MVA. Considering the maximum load (2010-11) reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 8 132 kV INDAPUR Pune 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X 25, 1 X ( 2011-12) 2) 4 X 33 kV out lets. 16 MVA and load is 19 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 9 220 kV RANJANGAON Pune 1) Add 1x50 MVA 220/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 50 (2011-12) 2) 6 x 22 kV outlets MVA,Load reached is 39 MVAConsidering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 10 132 kV CHAKAN-I * Pune 1) Add 1x50 MVA 132/22 KV T/F with bay Existing transformer capacity available in S/s is 2 X 50 and (2012-13) 2) 6 x 22 kV outlets the Load reach is 36 MVA.Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 11 132 kV BAWDA Pune 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 MVA (2012-13) 2) 4 X 33 kV out lets. and load is 18 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. AUGMENTATION OF S/S BY REPLACEMENT OF ICT/T/F 1 220KV RANJANGAON PUNE 1) 1X(200-100) MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s will be S/S (2010-11) 220/132 - 2 x 100 MVA the maximum load reach will be150MVA replacement of existing transformer of 220/132 kV 1 x 100 MVA is being proposed during2010-1 to have sufficient capacity during interuption and to cater the load.

2 220 KV MALINAGAR SOLAPUR 1) 1X(200-100) MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, 220/132, 1 (2010-11) x100 MVA and the load reach is 81 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 3 220 KV SOLAPUR-II S/S SOLAPUR 1) 1X(200-150) MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s will be, (2010-11) 220/132,2 X 200,1 X 100 and the load will reach 392 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

4 132 kV MUNDHAWA Pune 1) 1 X ( 50-25) MVA, 132/22 kV T/F with bays Existing transformer capacity available in S/s is 3 x 25, (2010-11) 2) 4 X 22 kV outlets. And the Load reach is 51 MVA. The T/F is replaced to meet anticipated load growth

5 220KV KHADKI S/S PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL (2010-11) 100 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 PUNE EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION 6 220KV BHOSARI S/S PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL (2010-11) 7 220KV PARVATI S/S PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL (2010-11) 8 220KV CHINCHWAD S/S PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL (2010-11) 9 132KV MARKAL PUNE 1) 1(50-25)MVA,132/33KV TF WITH BAYS To meet upcoming load of MSEDCL (2010-11) 10 220 KV MALINAGAR SOLAPUR 1) 1X(200-100) MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, 220/132,1 (2011-12) x100 MVA and the load reach is 98 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 11 132 kV MUNDHAWA Pune 1) 1 X ( 50-25) MVA, 132/22 kV T/F with bays Existing transformer capacity available in S/s is 3 x 25, (2011-12) 2) 4 X 22 kV outlets. And the Load reach is 51 MVA.The T/F is replaced to meet anticipated load growth 12 100 kV TALEGAON-I Pune 1) 1 X ( 50-28) MVA, 132-100/22 kV T/F with bays Existing transformer capacity available in S/s is 1 x 28, 1 x (2011-12) 2) 4 X 22 kV outlets. 25, 1 x 20 and the Load reach is 47 MVA. The T/F is replaced to meet anticipated load growth 13 220KV KHADKI S/S PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL (2011-12) 14 220KV BHOSARI S/S PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL (2011-12) 15 220KV PARVATI S/S PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL (2011-12) 16 220KV CHINCHWAD S/S PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL (2011-12) 17 220 kV BARSHI Solapur 1) 1 X (50-25) MVA, 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 MVA ( 2012-13) 2) 4 X 33 kV outlets. and the load reached is 40 MVA The transformer is replaced to meet anticipated load growth. 18 220KV CHINCHWAD PUNE 1) 1X(200-100) MVA ,220/132-100KV WITH BAYS Existing transformer capacity available in S/s is, 220/110,1 ( 2013-14) x 100 MVA and 1 X 150 MVA the max.load will reach 98 MVA. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

ICT PROPOSED TO INTRODUCE 132 LEVEL. 1 110KV PANDHARPUR PUNE 1) 2X25MVA, 132-110/33KV T/F NEW VOLTAGE LEVEL INTRODUCED (2010-11) 2) 33KV OUTLETS - 8 NOS 2 220 kV BARSHI PUNE 1) 1X100 MVA, 220/132 KV T/F WITH BAYS NEW VOLTAGE LEVEL INTRODUCED ( 2011-12) 3 220 kV BARSHI PUNE 1) 1X100 MVA, 220/132 KV T/F WITH BAYS NEW VOLTAGE LEVEL INTRODUCED ( 2012-13) * COMMISSIONED IN 2009-10 ** 1No. TF COMMISSIONED IN 2009-10

101

EHV CC O&M ZONE : KARAD

102 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

SPILL OVER SCHEMES 1 220 KV JATH S/S SANGLI 1) 220KV MAISAL - JATH D/C LINE - 70 KMS WITH BAYS Present recorded peak load on Jath-110kV, (2009-10) 2) 2X100MVA, 220/132KV ICTS WITH BAYS Kavathemankal-110kV and Sankh-110kV S/S are 30MW, 3) 2X25MVA, 220/33KV T/FS WITH BAYS 30MW and 25MW respectively. It is anticipated by the year 2009-10 that the load will reach to about 105MW. 4) 8X132KV BAYS Hence it is necessary to go in for new 220kV sub-station 5) 8X33KV OUTLETS at Jath. By the commissioning of this substation, voltage profile of Karad Circle will improve . 6) D/C ON D/C FROM 132KV JATH TO 220KV JATH - 0.5 KM

7) STRINGING OF 2ND CIRCUIT FROM PROPOSED JATH 220KV S/STN TO 132KV SANKH S/STN - 40 KM 8) 132KV KAVATHE MAHNKAL-JATH DC LINE -35 KM

2 220KV MUDHALTITTA KOLHAPUR 1) LILO ON 220KV KOLHAPUR -SAWANTWADI LINE - Mudal Tal is considerd for reducing loading of Kolhapur- (BIDRI) S/S 10KMS WITH BAYS 220kV S/S & to meet upcoming load (2009-10) 2) IIND CKT STRINGING OF KOLHAPUR - SAWANTWADI LINE - 40 KMS 3) 132 KV SCDC LINE TO 110 KV KOTHALI S/S- 35 KMS

4) 2 X 100 MVA 220/132 -110 KV ICT'S WITH BAYS 5) 2 X 25MVA, 220/33KV T/FS WITH BAYS 6) 8 X 33KV OUTLETS. 3 220KV MIDC LONAND SATARA 1) LILO ON 220KV KANDALGAON - LONAND AT 220KV Lonand MIDC-220kV S/S is considered to meet the load S/STN (2009-10) LONAND MIDC S/STN - 10KM growth in Karad Circle and load requirement of MIDC 2) 220KV LINE FROM 400KV JEJURI TO LONAND MIDC DC - 30KM 3) 2X100, 220/132KV ICT 4) 2X50 , 220/33KV TF 5) 132KV D/C INTERLINK TO 220 KV LONAND- 10KM 6) 132KV LINE BAYS - 4 NOS 7) 33KV BAYS - 12 NOS 4 220KV PHALTAN (MIDC) SATARA 1) 220KV LINE FROM LONAND MIDC D/C LINE- 30KM To take care of industrial load growth. S/STN 2) LILO OF 220KV LINE FROM LONAND - BOTHE - 4.5KM (2009-10) 3) 132 KV D/C LINE TO PHALTAN S/S - 10KM 4) 2X100MVA , 220/132KV ICT 5) 2X50 MVA, 220/33KV 6) 33KV BAYS - 12 NOS 5 220KV KADEGAON S/S SANGLI 1) LILO OF 220KV KARAD - MIRAJ S/C AT KADEGAON - 220 kV Kadegaon s/s is considered to take care of (2009-10) 2.5KM industrial growth & additional load requirement of MIDC. 2) LILO ON TWO CIRCUITS OF 220KV M/C LINE FROM KARAD TO MIRAJ AT KADEGAON- 5 KMS 2) 2X100MVA , 220/132KV ICT

3) 2X50 MVA, 220/33KV 4) 132 KV SCDC LINE TO KIRLOSKARWADI S/S-20 KM 5) 33KV BAYS - 12 NOS ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 220KV LINK LINE KOLHAPUR 1) 220KV LILO ON 2ND CKT OF KOLHAPUR - PHONDA - 2 220kV Phonda S/S is fed from 400kV Talandge S/s with (2008-09) KM WITH BAYS FOR HALKARNI S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

2 220KV LINK LINE* KOLHAPUR 1) 220KV LILO ON 2ND CKT OF KOLHAPUR - PHONDA -10 220kV Phonda S/S is fed from 400kV Talandge S/s with (2008-09) KM WITH BAYS FOR MUMEWADI S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

3 220KV LINK LINE KOLHAPUR 1) 220KV LILO ON HALKARNI - PHONDA FOR TILLARI ON 220kV Phonda S/S is fed from 400kV Talandge S/s with (2008-09) IIND CKT - 26 KM WITH BAYS S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

4 132 KV LINK LINE (2008- SATARA 1) 132KV SATARA (MIDC)- AUNDH SCDC -60 KM 132kV Aundh S/S is fed from 132kV Dahiwadi S/s with 09) S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

5 132KV LINK LINE SATARA 1) 132KV SATARA ROAD - SATARA MIDC -D/C LINE-15 KM 110kv satara road s/stn is fed from 110kv satara MIDC (2008-09) S/S with S/C line .Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line.

6 110 KV LINK LINE SATARA 1) 110KV SCDC LINE FROM 220KV OGALEWADI S/S - 110kV Mayani S/S is fed from 220kV Ogalewadi S/s with (2008-09) 110KV MAYNI S/S - 40 KM S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

103 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

7 110KV LINK LINES KOLHAPUR 1) 110KV MIRAJ - JISINGPUR D/C LINE-16 KM 110kV Jaysingpur S/S is fed from 220kV Miraj S/s with (2008-09) S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

8 132 KV LINK LINE SANGLI 1) 132KV PETH - SHIRALA SCDC LINE - 26 KM 132kV Shirala S/S is fed from 132kV Peth S/s with S/c (2009-10) line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

9 132 KV LINK LINE SINDHUDURG 1) 132kV KUDAL - KANKAVALI SCDC LINE - 30 KM To provide uninterrupted supply during planned outages it (2009-10) is necessary to add proposed line

10 110 KV LINK LINE SANGLI 1) 110KV TASGAON S/S - 220KV MIRAJ S/S SCDC LINE - 23 110kV Tasgaon S/S is fed from 220kV Miraj S/s with S/c (2009-10) KM line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

11 110 KV LINK LINE KOLHAPUR 1) 220KV ICHALKARANJI S/S - 110KV KURUNDWAD S/S 110kV Kurundwad S/S is fed from 220kV Ichalkaranj S/s (2009-10) SCDC LINE - 25 KM with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 220KV LINK LINE KOLHAPUR 1) 220KV MIRAJ - ICHALKARANJI D/C LINE-30 KM Since the existing 220kV Ichalkaranji-Mudshingi S/c line (2008-09) is critically loaded to an extent of 74 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. 2 132 KV LINK LINE SATARA 1) 132KV PHALTAN - WALCHANDNAGAR SCDC LINE - 36 Since the existing 132kV Phaltan-Walchandnagar S/c line (2008-09) KM is critically loaded to an extent of 89 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. 3 110 KV LINK LINE SANGLI 1) 110 KV DC LINE MIRAJ - KAVATHEMAHANKAL - 35 KM Since the existing line is loaded to an extent of 71 MW (2008-09) WITH BAYS during Non-Coinsident peak condition. Hence it is suggested to add proposed line to meet additional load growth and contingency.

4 220kV LINK LINES KARAD 1) 220KV KARAD - GUDEPACHGANI (NIGADE) SCDC - 15KM To have the facility for wind evacuation at Gudepachgani (2009-10) and nearby Karad S/s 5 220KV LINK LINE SATARA 1) 220KV KARAD - KOYNA (POPHALI) D/C LINE - 40 KM Since the existing 220kV Karad-Koyna S/c line is loaded (2009-10) WITH BAYS to an extent of 160 MW during Non-Coinsident peak 2) condition. It is anticipated the load will reach to about 220KV GIS BAYS AT 400KV KARAD S/STN - 02 NOS critical value by the year 2011-12. Hence it is necessary to propose additional line to meet additional load growth and contingency. 6 110 KV LINK LINE SATARA 1) 110KV KARAD - TEMBU SCDC LINE - 20 KM Since the existing 110kV Karad-Tembhu S/c line is (2009-10) loaded to an extent of 42 MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value by the year 2011-12. Hence it is necessary to propose additional line to meet additional load growth and contingency. 7 110 KV LINK LINE KOLHAPUR 1) 110KV SHIROLI - KALE SCDC LINE - 25 KM Since the existing 110kV Shiroli-Bapat Camp S/c line is (2009-10) critically loaded to an extent of 80 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. AUGMENTATION OF S/S BY ADDITION OF T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

1 220K KV SAWANTWADI SINDHUDURG 1) 1 X 25MVA , 220/33KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions S/S* on any one transformer (2008-09) 2) 4 X 33KV OUTLETS.

2 220K KV NIVALIPHATA RATNAGIRI 1) 1 X 25MVA , 220/33KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions S/S on any one transformer (2008-09) 2) 4 X 33KV OUTLETS.

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM 3 220K KV FINOLEX S/S RATNAGIRI 1) 1 X 25MVA , 220/33KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) 2) 4 X 33KV OUTLETS. on any one transformer

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM

104 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

4 220K KV KHAREPATAN SINDHUDURG 1) 1 X 25MVA , 220/33KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions S/S on any one transformer (2008-09) 2) 4 X 33KV OUTLETS.

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM

5 220KV HALKARNI S/S * KOLHAPUR 1) 1 X 25 MVA, 220/33 KV T/F WITH BAYS COMMISSIONED (2008-09) 2) 33 KV OUTLETS - 4 NOS.

6 220KV PETH S/S SANGLI 1) 1 X 100MVA, 220/132KV ICT WITH BAY To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 1 X 132KV BAY

7 132KV DIGHANCHI SANGLI 1) ADDL. 1X25 MVA 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 4X33KV OUTLETS 8 132 KV WAI S/S SATARA 1) ADDL. 1 X 50 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 33 KV OUTLETS - 4 NOS.

9 132 KV AUNDH S/S SATARA 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer

2) 33 KV OUTLETS - 4 NOS.

10 132 KV KURUNDWAD S/S KOLHAPUR 1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) on any one transformer 2) 33 KV OUTLETS - 4 NOS.

11 132 KV SHIRVAL S/S SATARA 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/22 -1 x 25 -16 132/33 -1 x 12.5 -6 2) 4 X 33 KV OUTLETS To avoid loss of supply in case of outages or interruptions on any one transformer 12 132-110/33 KV KOTHALI KOLHAPUR 1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, S/S 110/33 -1 x 25 -24 2) 33 KV OUTLETS - 4 NOS. (2008-09) To avoid loss of supply in case of outages or interruptions 13 110 KV BORGAON S/S SANGLI 1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS Existingon any one transformer transformer capacity available in S/s is, (2008-09) 132-110/33 -1 x 25 -19 2) 33 KV OUTLETS - 4 NOS. To avoid loss of supply in case of outages or interruptions on any one transformer 14 110 KV SANKH S/S SANGLI 1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or interruptions (2008-09) 2) 33 KV OUTLETS - 4 NOS. on any one transformer 15 400 kV NEW KOYNA Ratnagiri 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. (2009-10) 2) 4 X 33 kV out lets And the load reached is 14 MVA To avoid loss of supply in case of outages or interruptions on transformer.

16 220 kV KARAD-I Satara 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA.And (OGALEWADI) 2) 4 X 33 kV out lets the load reached is 16 MVA. To avoid loss of supply in (2009-10) case of outages or interruptions on transformer.

17 220 kV TALANDAGE Kolhapur 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. (5 STAR MIDC) 2) 4 X 33 kV out lets And the load reached is 50 MVA. To avoid loss of supply (2009-10) in case of outages or interruptions on transformer.

18 220 kV ONI Ratnagiri 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. (2009-10) 2) 4 X 33 kV out lets And the load reached is 8 MVA To avoid loss of supply in case of outages or interruptions on transformer.

19 220KV PETH S/S SANGLI 1) 1 X 50 MVA.220/132 kV ICT WITH BAYS The existing Transformer capacity available is 220/132 (2009-10) kV 1X50MVA and the load reached is 32 MVA To avoid loss of supply in case of outages or interruptions on any one transformer other transformer should take care of 20 220KV SATARA MIDC S/S SATARA 1) 1 X 100 MVA, 220/132KV ICT WITH BAYSexisting The existing load Transformerso as to avoid capacity load shedding. available is 220/132 (2009-10) kV 1X100MVA and the load reached is 65 MVA. To avoid loss of supply in case of outages or interruptions on any one transformer other transformer should take care of 21 132 kV DAHIWADI Satara 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. (2009-10) 2) 4 X 33 kV out lets And the load reached is 4 MVA. To avoid loss of supply in case of outages or interruptions on transformer.

22 132 kV KALE-T Satara 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. (2009-10) 2) 4 X 33 kV out lets And the load reached is 16 MVA. To avoid loss of supply in case of outages or interruptions on transformer.

105 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

23 132 kV WAI Satara 1) Add 1 X 25 MVA , 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. (2009-10) 2) 4 X 33 kV out lets And the load reached is 23 MVA. To avoid loss of supply in case of outages or interruptions on transformer.

24 132 kV KANKAVALI Sindhudurg 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 16 MVA. (2009-10) 2) 4 X 33 kV out lets And the load reached is 10 MVA To avoid loss of supply in case of outages or interruptions on transformer.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER 1 400KV KARAD & SATARA 1) ADDL. 1 X 500 MVA, 400/220KV ICT WITH BAYS AT EACH Existing transformer capacity available in S/s is, KOLHAPUR S/S KOLHAPUR S/S KARAD- (2008-09) 400/220 -3 x 315 - 592 Kolhapur- 400/220 -2 x 315 - 390 2 220 KV MUMEWADI S/S KOLHAPUR 1) 1 X 25 MVA, 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/33 -2 x 25 -36 Considering the maximum load reach on the transformer, 2) 33 KV OUTLETS - 4 NOS. in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 3 220 KV ICHALKARANJI* KOLHAPUR 1) 1X200MVA, 220/132-110 KV ICT WITH BAYS Newly introduced 220/132-110 Level (2008-09) 2) 2 X 132KV OUTLETS 4 132 KV SATARA MIDC SATARA 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, S/S 132/33 -2 x 25 -49.8 (2008-09) Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the 2) 4 X 33 KV OUTLETS transformer other transformer should take care of existing load so as to avoid load shedding.

5 132 KV PHALTAN S/S SATARA 1) ADDL. 1 X 50 MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/22 -2 x 25 -34 2) 33 KV OUTLETS - 4 NOS. 132/33 -1 x 25 -21 To avoid loss of supply in case of outages or interruptions on any one transformer

6 132 KV KANKAVLI S/S SINDHUDURG 1) 1 X 25MVA , 132-110/33KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 27 MVA load 132/33 - 1 x 16 - 6 MVA load 2) 4 X 33KV OUTLETS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing 3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM load so as to avoid load shedding. 7 110KV SHIROLI S/S* KOLHAPUR 1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 -1 x 25 -18 132/33 -2 x 16 -25 2) 33 KV OUTLETS - 4 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 8 400KV N-KOYNA S/S RATNAGIRI 1) 1 X 500 MVA, 400/220KV ICT WITH BAYS Existing transformer capacity available in S/s (2009-10) is,400/220kV, 2 x 315 MVA and the load reached is 473 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

9 220KV KARAD S/S SATARA 1) ADDL. 1 X 100 MVA, 220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s is,220/110 (OGALEWDI) kV, 1 x 100 MVA, 1X75 MVA &1X50 MVA - load reach is- (2009-10) 134 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 10 220 kV LOTE Ratnagiri 1) Add 1 x 25 MVA, 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 PARSHURAM (2009- 2) 4 X 33 kV out lets. MVA. And the load reached is 40 MVA Considering the 10) maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

11 220 kV DASTURI Ratnagiri 1) Add 1 x 25 MVA, 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA. And the load reached is 27 MVA The transformer is replaced to meet anticipated load growth..

12 220 kV KOLHAPUR-II Kolhapur 1) Add 1 X 50 MVA , 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X 50 & (MUDSHINGI) 2) 8 X 33 kV out lets. 1 X 25 MVA and load is 45 MVA.Considering the (2009-10) maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load. 106 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

13 220 kV ICHALKARNJI-II Kolhapur 1) Add 1 X 50 MVA, 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 50 (TILWANI) 2) 6 X 33 kV out lets. MVA and load is 71 MVA. Considerin the maximum load (2009-10) reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

14 220 kV MALHARPETH Satara 1) Add 1 X 50 MVA ,220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 50 (2009-10) 2) 6 X 33 kV out lets. MVA and load is 51 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

15 220 kV MUMEWADI Kolhapur 1) Add 1 X 25 MVA, 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA and load is 36 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

16 220 kV PETH Sangli 1) Add 1 X 25 MVA , 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA and load is 30 MVA. Considering the maximum load reached on the transformer in the event of 17 132 kV SAVLAJ Sangli 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existinginterruptions/outage transformer oncapacity any one available of the transformerin s/s is 1 X other 25 (2009-10) 2) 4 X 33 kV out lets. MVA. And the load reached is 12 MVA The transformer is replaced to meet anticipated load growth..

18 110 kV RATNAGIRI Ratnagiri 1) Add 1 X 25 MVA , 132-110/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA and load is 35 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 19 110 kV ASHTA Sangli 1) Add 1 X 25 MVA , 132-110/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA and load is 36 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

20 110 kV GOKUL Kolhapur 1) Add 1 X 25 MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 50 SHIRGAON 2) 4 X 33 kV out lets. MVA and load is 47 MVA. Considering the maximum (2009-10) load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

21 110 kV KALE KOLHAPUR Kolhapur 1) Add 1 X 25 MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA and load is 27.75 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

22 110 kV KOLHAPUR-I Kolhapur 1) Add 1 X 25 MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (BAPAT CAMP) 2) 4 X 33 kV out lets. MVA and load is 38 MVA. Considering the maximum (2009-10) load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

23 110 kV PUIKHADI Kolhapur 1) Add 1 X 25 MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA and load is 32 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

24 110 kV VISHRAMBAUG Sangli 1) Add 1 X 25 MVA , 132-110/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X 25 & (2009-10) 2) 4 X 33 kV out lets. 1 X 20 MVA and load is 29 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

25 110 kV JAYSINGPUR Kolhapur 1) Add 1 X 25 MVA , 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 3 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA. And the load reached is 47 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

26 110kV WATHAR-I Kolhapur 1) Add 1 X 25 MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2009-10) 2) 4 X 33 kV out lets. MVA and load is 34 MVA. CConsidering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

107 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

AUGMENTATION OF S/S BY REPLACEMENT OF T/F 1 220 KV VITA S/S SANGLI 1) 1 X ( 50 - 25) MVA, 220/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/33 -1 x 50 -38 220/33 -1 x 25 -12.22 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 2 220 KV MIRAJ S/S SANGLI 1) 1 X ( 50-25) MVA, 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/33 -1 x 50 -35 220/33 -1 x 25 -21 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 3 220KV OGALEWADI S/S SATARA 1) (50 -25)MVA, 220/33KV T/F Existing transformer capacity available in S/s is, (2008-09) 220/33 - 1 x 25 - 24 2) (25-10)MVA, 110/33KV T/F 110/33 - 1 x 10 - 9 Additional transformer of 220/33 kV 25 MVA is being added during the year 2007-08 to have redundancy during outage/interuption to cater the load. So to take care of anticipated load growth replcement is required.

4 220KV MIRAJ S/S SANGLI 1) 1 X ( 200-100) MVA, 220/132-110 KV ICTS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/132 - 3 x 100 - 252 2) 132 KV BAYS - 1NOS. Considering the maximum load reach on the transformer, 3) 33 KV OUTLETS - 4 NOS. in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

5 110KV MAYANI S/S SATARA 1) (12.5-7.5) MVA 132/110-22KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 110/22 -3 x 7.5 -18 110/33 -1 x 25 -15 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 6 110 KV ASHTA * SANGLI 1) 2(25-16/12.5) MVA, 110/33 KV T/F Existing transformer capacity available in S/s is, (2008-09) 110/33 -1 x 16 -12 110/33 -1 x 12.5 -9.5 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 7 110 KV KAVATHE SANGLI 1) REP. 1 X ( 25-16) MVA, 110/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, MAHANKAL S/S 110/33 -1 x 25 -18 (2008-09) 110/33 -1 x 16 -14 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 8 110 KV VISHRAMBAG SANGLI 1) REP. 2 X ( 50 -20/25) MVA, 132-110/33 KV T/FS WITH Existing transformer capacity available in S/s is, S/S** BAYS 110/33 -1 x 20 -15.55 (2008-09) 110/33 -1 x 25 -16.66 2) 33 KV OUTLETS - 8 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 9 110KV JATH S/S** SANGLI 1) REP. 2 X ( 25-10) MVA, 132-110/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 110/33 -2 x 10 -19 2) 33 KV OUTLETS - 4 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 10 110KV TASGAON S/S** SANGLI 1) REP. 2 X ( 25-12.5) MVA, 132-110/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 110/33 -1 x 16 -13 110/33 -1 x 12.5 -10 2) 33 KV OUTLETS - 4 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 11 110KV KIRLOSKARWADI SANGLI 1) REP. 2 X ( 25-12.5) MVA, 132-110/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, S/S** 110/33 -1 x 10 -9 (2008-09) 2) 33 KV OUTLETS - 4 NOS. 110/33 -1 x 12.5 -7.4 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

108 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

12 110KV GOKULSHIRGAON KOLHAPUR 1) REP.1 X ( 50-25) MVA, 132-110/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, S/S 110/33 -1 x 50 -27 (2008-09) 110/33 -1 x 25 -20 Considering the maximum load reach on the transformer, 2) 33 KV OUTLETS - 4 NOS. in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 13 110KV KALE S/S * KOLHAPUR 1) REP. 1 X ( 25-10) MVA, 132-110/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 110/33 -1 x 25 -22.2 110/33 -1 x 10 -9 2) 33 KV OUTLETS - 2 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 14 110KV RADHANAGARI* KOLHAPUR 1) REP.1 X ( 25-10) MVA, 132-110/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is, S/S 110/33 - 2 x 10 - 18.14 2) 33 KV OUTLETS - 4 NOS. (2008-09) Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 15 110KV CHABUKHEDI KOLHAPUR 1) 1X(25-12.5)MVA, 132-110/33KV T/F WITH BAYS Existing transformer capacity available in S/STN S/STN 110/33 - 1 x 12.5MVA & 110/33KV, 10 MVA- 22MVA 2) 1X(25-10)MVA, 132-110/33KV T/F WITH BAYS (2008-09) Considering the maximum load reach on the transformer, 3) 33KV OUTLETS - 4 NOS in event of interruption/outage on any one of the transformer other transformer should take care of existing 2) 33 KV OUTLETS - 2 NOS. load so as to avoid load shedding. 16 220KV MIRAJ S/S SANGLI 1) 1 X ( 200-100) MVA, 220/132-110 KV ICTS WITH BAYS Existing transformer capacity available in S/s (2009-10) is,220/110kV 3 x 100MVA and the load reached is 258 MVA.The transformer is replaced to meet the anticipated load growth. 17 220 KV LONAND *S/S SATARA 1) 1 X (200- 63) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s (2009-10) is,220/132kV ,2 X 63+1 x 115 MVA and the load reached is 249 MVA.The transformer is replaced to meet the anticipated load growth. 18 220 KV KOLHAPUR-II KOLHAPUR 1) 1 X ( 200 - 100) MVA, 220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s (MUDSHINGI) S/S is,220/110kV ,3 X 100 MVA and the load reached is 300 (2009-10) MVA.The transformer is replaced to meet the anticipated load growth. 19 220 KV KARAD S/S SATARA 1 1 X (100-75) MVA,220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s (2009-10) is,220/110kV,1 x 100 MVA,1X75MVA &1X50MVA - load reach is- 134 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

20 220 KV KARAD S/S SATARA 1 1 X (100-50) MVA,220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s (2009-10) is,220/110kV,1 x 100 MVA,1X75MVA &1X50MVA - load reach is- 134 MVA Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

21 220 kV KARAD-I Satara 1) 1 X(50- 25) MVA , 132/33-22 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA.And (OGALEWADI) 2) 4 X 33 kV out lets the load reached is 16 MVA. To avoid loss of supply in (2009-10) case of outages or interruptions on transformer.

22 220KV PETH S/S SANGLI 1) 1 x(100-50 )MVA.220/132 kV ICT WITH BAYS The existing Transformer capacity available is 220/132 (2009-10) kV 1X50MVA and the load reached is 32 MVA To avoid loss of supply in case of outages or interruptions on any one transformer other transformer should take care of existing load so as to avoid load shedding.

23 132 kV WAI Satara 1) 1 X(50- 25) MVA , 132/33-22 kV T/F with bay. Existing Transformer capacity available is 1 X 25 MVA. (2009-10) 2) 4 X 33 kV out lets And the load reached is 23 MVA. To avoid loss of supply in case of outages or interruptions on transformer.

24 132 kV DIGHANCHI Sangli 1) 1 X (25-12.5) MVA, 132-110/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. To (2009-10) 2) 4 X 33 kV out lets avoid loss of supply in case of outages or interruptions on transformer. 25 132 kV Sangli 1) 1 X (50-25) MVA MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 KAVATHEMAHAKAL 2) 2 X 33 kV outlets. MVA. And the load reached is 32 MVA The transformer is (2009-10) replaced to meet anticipated load growth.

26 132 kV DIGHANCHI Sangli 1) 1 X (25-12.5) MVA , 132-110/33 kV T/F with bays. Existing Transformer capacity avaible is 1 X 12.5 MVA. (2009-10) 2) 2 X 33 kV outlets. To avoid loss of supply in case of outages or interruptions on transformer. 27 132 kV PHALTAN * Satara 1) 1 X (50-25) MVA,132/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x (2009-10) 2) 4 X 22 kV outlets. 25,132/22 kV and load reach is 26 MVA. The T/F is replaced to meet anticipated load growth

109 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

28 132 kV DAHIWADI Satara 1) 1 X (25-12.5) MVA,132/22 kV T/F with bays. Existing transformer capacity available in S/s is 1 x 25, (2009-10) 2) 4 X 22 kV outlets. 1 X 12.5 ,132/22 kV and load reach is 14 MVA. The T/F is replaced to meet anticipated load growth

29 110 kV RADHANAGARI * Sangli 1) 1 X (25-10) MVA MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 10 & (2009-10) 2) 2 X 33 kV outlets. 1 X 25 MVA. And the load reached is 13 MVA The transformer is replaced to meet anticipated load growth.

30 110 kV MAYNI Satara 1) 1 X (25-7.5) MVA , 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 25 & (2009-10) 2) 2 X 33 kV outlets. 1X 7.5 MVA. And the load reached is 19 MVA The transformer is replaced to meet anticipated load growth

31 110 kV MAYNI Satara 1) 1 X (25-7.5) MVA,110/22 kV T/F with bays. Existing transformer capacity available in S/s is, (2009-10) 2) 4 X 22 kV outlets. 15 MVA. And the Load reach is 7 MVA. The T/F is replaced to meet anticipated load growth 32 110 kV ICHALKARANGI-I Sangli 1) 1 X (50-20) MVA MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 10 & (2009-10) 2) 2 X 33 kV outlets. 1 X 20 , 1 X 25 MVA. And the load reached is 31 MVA The transformer is replaced to meet anticipated load growth NEW SCHEMES 1 400 KV KARAD-II S/S SATARA 1) 2 X500MVA 400/220 KV ICT'S WITH BAYS To improve voltage profile of the area and to meet the (MALHAR PETH) 1 X 167 MVA , 400/220 KV 1 PHASE ICT SPARE upcoming load. (2010-11) 2) LILO ON BOTH CIRCUITS OF 400 KV NEW KOYNA - KARAD-I AT KARAD - II WITH BAYS -5KM 3) 220 KV D/C LINE TO 220 KV MALHARPETH S/S - 10KM 4) 220KV D/C TO 220KV KADEGAON - 40KM

2 400 KV KESURDI S/S SATARA 1) 400/220 KV , 2X 500 MVA ICT'S WITH BAYS Kesurdi 400kV S/S is proposed for strenghtning for (2010-11) 400/220 KV , 1 X 167 MVA 1 PHASE ICT SPARE evacuation of power, upcoming load and to improve 2) LILO OB BOTH CIRCUITS OF 400KV KOYNA - LONIKAND / voltage profile of the area. JEJURI AT KESURDI - 15 KM 3) 400 KV D/CLINE FROM 400 KV KARAD II (MALHARPETH) TO KESURDI S/S 60 KM 4) 400 KV KESURDI - LONIKAND - II D/C LINE - 55KM 5) 220 KV LINE FROM 400KV KESURDI - 220 KV LONAND MIDC D/C LINE - 30 KM WITH BAYS 6) 220KV LINE BETWEEN KESURDI - 400KV JEJURI D/C LINE - 40 KM 3 220 KV HAMIDWADA kOLHAPUR 1) 220KV D/C LINE FROM FIVE STAR MIDC KAGAL - 220KV Kagal-220kV S/S is considered to meet the load growth (KAGAL) S/S HAMIDWADA(KAGAL) WITH BAYS - 35 KMS in Karad Circle and load requirement of MIDC area. (2010-11) 2) 2 X 50MVA, 220/33KV T/FS WITH BAYS 3) 12 X 33 KV OUTLETS 4 132KV MHASWAD SATARA 1) LILO OF 110KV OGALEWADI - PANDHARPUR LINE - 15 System Strengthining & Voltage improvement. (2010-11) KM 2) 2X25MVA, 132-110/33KV T/FS WITH BAYS 3) 33KV OUTLETS - 8NOS. 5 220 KV KHARSUNDI S/S SANGLI 1) 2X100 MVA , 220/132KV ICT'S Kharsundi 220kV S/S is considered for upcoming load (2011-12) 2) 2 X 25 MVA, 220/33KV T/FS WITH BAYS requirement in karad area 3) 220KV D/C LINE FROM GHTNANDRE - KHARSUNDI - 30 KMS 4) 132KV SCDC LINE FROM 220KV KHARSUNDI - MAYANI - 23KMS 5) 132KV SCDC LINE FROM 220KV KHARSUNDI - DIGHANCHI - 25KMS 6) 132KV SCDC LINE FROM 220KV KHARSUNDI - SAWALAJ - 28KMS 7) 8 X 33 KV OUTLETS 6 220 KV SANGLI S/S SANGLI 1) 220KV MIRAJ - SANGLI D/C LINE WITH BAYS - 12 KMS Present recorded peak on Vishrambag is 70MW . It is (2011-12) 2) LILO ON 220KV MIRAJ - TILWANI LINE -35KM anticipated by the year 2011-12, the load will reach about 106MW. Hence it is necessary to go in for new 220kV 3) 2 X 100 MVA 220/132 -110 KV ICT'S WITH BAYS sub-station at Sangli. 4) 132 KV VISHRAMBAG SCDC LINE -10 KMS 5) 132 KV ASHTA SCDC LINE -15 KMS 6) 2 X 50 MVA, 220/33KV T/FS WITH BAYS 7) 12X 33 KV OUTLETS 7 132 KV SHIRADWAD S/S KOLHAPUR 1) FROM 220KV TALANDGE S/S D/C LINE- 20KM To meet the upcoming load. (2011-12) 2) 2X50MVA , 132/33KV TF 3) 33KV OUTLET - 08 NOS. 8 400KV ALKUD SANGLI 1) LILO OF ONE CKT OF 400KV SOUTH SOLAPUR (PG) - Strengthining of existing network. (SANGLI) KOLHAPUR AT 400 KV ALKUD - 15KM (2012-13) 2) 400KV D/C LINE FROM KARAD -II - ALKUD - 100KM 3) LILO OF 0NE CKT OF 220KV VITA MHAISHAL LINE -18KM

4) LILO OF ONE CKT OF 220KV MHAISHAL - JATH LINE - 5) 220KV23KM D/C FROM 400KV ALKUD - KHARSUNDI LINE - 40KM 6) 2X500MVA 400/220KV ICT 7) 1X167 MVA , 400/220KV SPARE ICT

110 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 220 KV LINK LINE KOLHAPUR 1) 220KV KOLHAPUR - SAWANTWADI (STRINGING ONLY) - 220kV Sawantwadi S/S is fed from 220kV Talandge S/s (2010-11) 122 KM with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 2 220 KV LINK LINE SATARA 1) LILO ON 2ND CIRCUIT OF 220KV PEDAMBE - For redundancy. (2010-11) KANDALGAON AT LOTE PARSHURAM -30KM

3 220 KV LINK LINE SATARA 1) LILO ON 2ND CIRCUIT OF 220KV PEDAMBE - For redundancy. (2010-11) KANDALGAON AT DASTURI - 29KM 4 132 KV LINK LINE KOLHAPUR 1) 132KV D/C LINE FROM 220KV OGALEWADI - 132KV For redundancy. (2010-11) KALE(T) -15 KM 5 220KV LINK LINE SATARA 1) 220KV LONAND - VANKUSWADI SCDC LINE - 85 KM To have the facility for wind evacuation at Vankuswadi (2011-12) WITH BAYS and nearby Lonand S/s

6 132KV LINK LINES SATARA 1) 132KV LONAND-SHIRWAL D/C LINE WITH BAYS -25KM To provide uninterrupted supply during planned outages it (2011-12) is necessary to add proposed line 7 132KV LINK LINES SATARA 1) 132KV SCDC LINE FROM 220KV TILAWANI - 110KV For redundancy. (2011-12) JAYSINGPUR - 18KM 8 132KV LINK LINES SATARA 1) 132KV SCDC LINE FROM 220KV LONAND - 132KV For redundancy. (2011-12) SATARA ROAD -35 KM 9 132KV LINK LINES KOLHAPUR 1) 132KV D/C LINE FROM 132KV KALE(T) - 220KV WATHAR - For redundancy. (2011-12) 35 KM 10 132KV LINK LINES SATARA 1) 132KV D/C LINE FROM 132KV DAHIWADI - 132KV For redundancy. (2011-12) PHALTAN 40 KM 11 132KV LINK LINES SATARA 1) 132KV D/C LINE FROM 220KV KOLHAPUR - 110KV For redundancy. (2011-12) PUIKHADI -8 KM 12 132KV LINK LINES SATARA 1) 132KV SCDC LINE FROM 132KV KALE(T) - WARNA 20KM For redundancy. (2011-12) 13 132KV LINK LINES SATARA 1) 2ND CIRCUIT STRINGING FROM 132KV SCDC LINE For redundancy. (2011-12) FROM LONAND - PHALTAN 55 KM 14 132KV LINK LINES SATARA 1) 2ND CIRCUIT STRINGING FROM 132KV SCDC LINE For redundancy. (2011-12) FROM 220KV TILAWANI - KURUNDWAD 25 KM 15 132KV LINK LINES SATARA 1) 2ND CIRCUIT STRINGING FROM 132KV SCDC LINE For redundancy. (2011-12) FROM 132KV AUNDH - DAHIWADI 30KM 16 220KV LINK LINE RATNAGIRI 1) 220 KV NIVALIPHATA TAP ON NEW-KOYNA -FINOLEX - Nivaliphata S/s is presently tapped on New Koyna- (2012-13) 42 KM Phinolex line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 17 132KV LINK LINE SATARA 1) 132 KV WAI-LONAND SECOND CKT STRINGING - 41.86 132kV Wai S/S is fed from 220kV Lonand S/s with S/c (2012-13) KM line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

1 132KV LINK LINE KOLHAPUR 1) UPGRADATION OF EXISTING 110KV MUDSHINGI TO System strengthining & redundancy. (2010-11) BAPAT CAMP LINE TO 132KV LINE USING SAME ROW.

2 110 KV LINK LINE KOLHAPUR 1) LILO ON 110KV CHAMBUKHADI - KALE LINE FOR System strengthining & redundancy. (2010-11) BAMBVADE -25 KM 3 220KV LINK LINE SATARA 1) 220KV KESURDI TO VANKUSWADI SCDC LINE - 85 KM To have the facility for wind evacuation at Vankuswadi (2011-12) WITH BAYS and nearby Lonand S/s

4 132KV LINK LINE KOLHAPUR 1) UPGRADATION OF EXISTING 110KV SCDC LINE FROM System strengthining & redundancy. (2011-12) 220KV MUDSHINGI - KOTHALI -RADHANAGARI - KANKAVALI LINE TO 132KV LINE USING SAME ROW. 5 132KV LINK LINE KOLHAPUR 1) UPGRADATION OF EXISTING 110KV SC LINE FROM System strengthining & redundancy. (2011-12) 220KV PEDAMBE - ARAVALI -NIWALI - RATNAGIRI LINE TO 132KV D/C LINE USING SAME ROW. 6 132KV LINK LINE KOLHAPUR 1) UPGRADATION OF EXISTING 110KV SC LINE FROM System strengthining & redundancy. (2011-12) 220KV MUDSHINGI TO ICHALKARANJI LINE TO 132KV LINE USING SAME ROW. 7 220KV LINK LINE KOLHAPUR 1) CONVERSION OF EXISTING S/C 220KV KARAD TO System strengthining & redundancy. (2013-14) PEDAMBE LINE TO PARTLY M/C (UP TO KOYANANAGAR) AND D/C LINE FROM KOYANANAGR TO POPHALI AND KOYANANAGAR TO PEDAMBE. ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

1 110 KV LINK LINE KOLHAPUR 1) 220KV KAGAL S/S (5 STAR MIDC.) - 110KV Linking to New 220 kV Kagal S/s (2010-11) GOKULSHIRGAON SCDC LINE - 15 KM 2 132 KV LINK LINE SANGLI 1) 132KV KAVATHEMAHAKAL - SAVALAJ SCDC LINE - 25KM To have alternate source for Kavathemahakal. (2012-13) STRENGTHENING FOR EVACUATION ARRANGEMENT 1 220KV LINK LINE KARAD 1) 220KV KDPH - VANKUSWADI SCDC LINE -32KM To have evacuation facility af 2x40mw generation at (2011-12) KDPH

111 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

AUGMENTATION OF S/S BY ADDITION OF ICT/T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE ICT/T/F IS AVAILABLE 1 132 kV KANKAVALI Sindhudurg 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 16 MVA. (2011-12) 2) 4 X 33 kV out lets And the load reached is 10 MVA To avoid loss of supply in case of outages or interruptions on transformer.

2 132 kV WAI Satara 1) 1 X 25 MVA ,220/33 kV T/F with bays. Existing Transformer capacity avaible is 1 X 25 MVA. To (2011-12) 2) 2 X 33 kV out lets. avoid loss of supply in case of outages or interruptions on transformer.

3 132 kV SHIRVAL Satara 1) Add 1 x 25 MVA, 132/22 KV T/F with bays. Existing transformer capacity available in S/s is 1 x 25, (2013-14) 132/22 kV and load reach is 14 MVA. To avoid the loss of 2) 4 x 22 kV outlets supply in case of outages or interruptions of transformers

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT/T/F 1 132-110 kV SATARA Satara 1) Add 1 x 25 MVA, 132-110/22 KV T/F with bays. Existing transformer capacity available in S/s is ROAD 2 x 20, 132-110/22 kV and load reach is 19 MVA. (2010-11) Considering the maximum load reached on the transformer in the event of interruptions/outage on any 2) 4 x 22 kV outlets one of the transformer other transformer should take care of existing load 2 110KV ARAVALI S/S RATNAGIRI 1) 1 x 25 MVA, 132-110/33 KV T/F with bays. For redundancy. (2010-11) 2) 4 x 33 kV outlets

3 110 kV SATARA MIDC Satara 1) Add 1 X 25 MVA , 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 (2011-12) 2) 4 X 33 kV out lets. MVA. And the load reached is 46 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

4 132 kV LONAND Satara 1) Add 1 x 25 MVA, 132/22 KV T/F with bays. Existing transformer capacity available in S/s is 2 x 25, (2011-12) 2) 4 x 22 kV outlets 132/22 kV and load reach is 23 MVA. The T/F is replaced to meet anticipated load growth

INTRODUCTION OF 33KV LEVEL 1 220KV MHAISHAL SANGLI 1) 2X25MVA, 220/33KV T/FS WITH BAYS To reduce loading of 220kv Miraj & 110kV Vishrambag (2010-11) S/Stn. 2) 33KV OUTLETS - 6NOS AUGMENTATION OF S/S BY REPLACEMENT OF TRANSFORMER 1 220KV MIRAJ S/S SANGLI 1) 1 X ( 200-100) MVA, 220/132-110 KV ICTS WITH BAYS Existing transformer capacity available in S/s (2010-11) is,220/110kV 3 x 100MVA and the load reached is 258 MVA.The transformer is replaced to meet the anticipated load growth. 2 220 KV KOLHAPUR-II KOLHAPUR 1) 1X ( 200-100) MVA, 220/132-110 KV ICTS WITH BAYS Existing transformer capacity available in S/s (MUDSHINGI) S/S is,220/110kV ,1 X 100 MVA and the load reached is 328 (2010-11) MVA.The transformer is replaced to meet the anticipated load growth. 3 220KV TILAWANI kOLHAPUR 1) 1X(100-50)MVA, 220/33-33KV T/F WITH BAYS To cater upcoming load of MSEDCL (2010-11) 4 220KV PETH Sangli 1) 1X(50-25)MVA, 220/33KV To cater upcoming load of MSEDCL (2010-11) 5 110 kV ICHALKARANJI-I KOLHAPUR 1) 1 X (50-25) MVA MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 10 & (2010-11) 2) 2 X 33 kV outlets. 1 X 20 , 1 X 25 MVA. And the load reached is 31 MVA The transformer is replaced to meet anticipated load growth. 6 110 kV Sangli 1) 1 X (50-25) MVA MVA, 132-110/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 KAVATHEMAHAKAL 2) 2 X 33 kV outlets. MVA. And the load reached is 32 MVA The transformer is (2010-11) replaced to meet anticipated load growth.

7 110 kV MAYNI Satara 1) 1 X (25-7.5) MVA,132-110/22 kV T/F with bays. Existing transformer capacity available in S/s is, (2010-11) 2) 4 X 22 kV outlets. 15 MVA and the Load reach is 7 MVA. The T/F is replaced to meet anticipated load growth

8 220KV TILAWANI 1) 1X(100-50)MVA, 220/33-33KV T/F WITH BAYS To cater upcoming load of MSEDCL (2011-12) 9 220 KV KOLHAPUR-II KOLHAPUR 1) 1 X ( 200 - 100) MVA, 220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s is, (MUDSHINGI) S/S 220/110kV, 2 X 200 MVA & 1 x 100 MVA and the load (2011-12) reached is 353 MVA.The transformer is replaced to meet the anticipated load growth. 10 220 kV LOTE Ratnagiri 1) 1 X (50-25) , 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 PARSHURAM 2) 4 X 33 kV out ets. MVA. And the load reached is 40 MVA The transformer is (2011-12) replaced to meet anticipated load growth.

11 220KV KHAREPATAN SINDHUDURG 1) 1X (100-50) MVA 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is S/S 220/132kV, 1 x 50MVAand the load reached is 30 MVA (2011-12) Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

112 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 KARAD EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO. SUBSTATION

12 400KV N-KOYNA S/S RATNAGIRI 1) 1 X (500-315) MVA, 400/220KV ICT WITH BAYS Existing Transformer capacity available is 2 X 315 MVA (2012-13) 2) 220KV BAYS - 02 NOS. and load reached is 473 MVA, Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

13 220 kV MUDSHINGI Kolhapur 1) 2 X (50-25) MVA , 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 10 (KOLHAPUR-II) 2) 4X 33 kV outlets. MVA. And the load reached is 12 MVA The transformer is (2012-13) replaced to meet anticipated load growth.

14 220 kV LOTE Ratnagiri 1) 1X (50-25) , 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X 25 PARSHURAM 2) 4 X 33 kV outlets. MVA. And the load reached is 40 MVA The transformer is (2013-14) replaced to meet anticipated load growth.

15 132 kV PHALTAN Satara 1) 1 X (50-25) MVA,132/22 kV T/F with bays. Existing transformer capacity available in S/s is 2 x 25, (2013-14) 2) 4 X 22 kV outlets. 132/22 kV and load reach is 26 MVA. The T/F is replaced to meet anticipated load growth 16 132 kV WAI Satara 1) 1 X(50- 25) MVA ,132/33-22 kV T/F with bays. Existing Transformer capacity avaible is 1 X 25 MVA. To (2014-15) 2) 2 X 33 kV out lets. avoid loss of supply in case of outages or interruptions on transformer. ICT PROPOSED TO INTRODUCE 132 LEVEL. 1 220 KV SAWANTWADI SINDHUDURG 1) 2 X 100 MVA , 220/132 KV ICT WITH BAYS To introduce 132 kV Level to feed the nearby area. S/S (2011-12) 2 220KV PEDAMBE S/S Satara 1) 1 X 100 MVA , 220/132-110 KV ICT WITH BAYS To introduce 132 kV Level to feed the nearby area. (2011-12)

3 220KV PEDAMBE S/S Satara 1) 1 X 100 MVA , 220/132-110 KV ICT WITH BAYS To introduce 132 kV Level to feed the nearby area. (2012-13)

* COMMISSIONED IN 2009-10 ** 1No. TF COMMISSIONED IN 2009-10

113

EHV CC O&M ZONE : NASIK

114 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION SUBSTATION SCHEMES 1 220KV PIMPALGAON NASIK 1) 2X100MVA, 220/132KV ICTS WITH BAYS Present recorded peak load on Ranwad-132kV, (RANWAD) Lasalgaon-132kV, Chandwad-132kV are 60MW, (2009-10) 2) 220KV NASIK (EKLAHARE )- PIMPALGAON D/C 45MW, 15MW respectively. It is anticipated by the LINE - 43.72 KM year 2009-10 the load will reach to about 150MW. Hence it is necessary to go in for 220kV sub- 3) 132KV OUTLETS - 4NOS. station at Ranwad. 4) 132KV D/C LINE TO RANVAD S/S-17 KMS 5) 132KV D/C LINE TO DINDORI S/S-17 KMS

2 220KV BHAMBORI JALGAON 1) LILO ON 220 KV BHUSAWAL - AMALNER It is necessary to go in for 220kV sub-station at (JALGAON) CKT. I AT 220 KV BHAMBORI - 3 KMS. Bhambori. To improve voltage profile of the area (2009-10) 2) 2X100MVA, 220/132KV ICT WITH BAYS and to meet the demand. 3) 2X25MVA, 220/33KV T/F WITH BAY 4) 132KV SCDC LINE FROM 220KV PROPOSED BHAMBORI TO DHARANGAON S/STN - 28 KM 5) 132KV DC ON MC FROM 220KV PROPOSED BHAMBORI TO 132KV JALGAON MIDC - 8 KM 7) 33KV OUTLETS - 8 NOS. 3 220 KV KOPERGAON S/S AHMEDNAGAR 1) 2 X 200MVA, 220/132KV ICTS WITH BAYS Present recorded peak load on Vaijapur-132kV, (2009-10) Yeola-132kV and Kopargaon-132kV S/S are 2) 2 X 50 MVA, 220/33 KV T/FS WITH BAYS 30MW, 40MW and 40MW respectively. It is 3) LILO OF 220 KV BABHALESHWAR-CHALISGAON anticipated by the year 2009-10 the load will reach S/C AT KOPARGAON-10 KM to about 135MW. Hence it is necessary to go in for new 220kV sub-station at Kopergaon 4) 220 KV BABHALESHWAR-KOPARGAON D/C-20 KM 5) 132 KV D/C LINE TO 132 KV KOPARGAON -10 KM 6) 132 KV SCDC LINE TO YEOLAS/S -25 KM 7) 12 X 33 KV OUTLETS 4 132 KV VADJIRE S/S AHMEDNAGAR 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Present recorded peak load on Kedgaon-132kV is (2009-10) 70MW. It is anticipated by the year 2009-10 the 2) 132 KV D/C LINE SUPA - VADJIRE - 25 KM load will reach to about 85MW. Hence it is necessary to go in for new 132kV sub-station at 3) 8 X 33 KV OUTLETS Vadjire. The new substation Vadjire-132kV S/S is proposed in year 2009-10 for reducing loading on Kedgaon-132kV. 5 220KV SINNAR II S/S NASIK 1) LILO ON 220KV BABHALESHWAR - NASIK D/C Present recorded peak load on Sinnar-132kV is (2009-10) LINE - 10 KMS 90MW. It is anticipated by the year 2009-10 the 2) 2X100MVA, 220/132KV ICT WITH BAYS load will reach to about 110MW. Hence it is necessary to go in for 220kV sub-station at 3) 2X50MVA, 220/33KV T/FS WITH BAYS Sinnar. By the commissioning of this substation, 4) 12 X 33KV OUTLETS voltage profile will improve to 0.97pu from 0.93pu. 5) LILO OF 132 KV EKLAHARE - SINNAR LINE AT 220 KV SINNAR - II - 23.79 KMS 6) 132KV LINE TO SINNAR (MALEGAON) MIDC -10 KMS 6 132KV GHARGAON S/S AHMEDNAGAR 1) 132KV D/C LINE FROM 220 KV ALEPHATA - Ghargaon-132kV S/S is considered in year 2009- (2009-10) GHARGAON - 33.46KM 10 for reducing the loading of Rahuri-132kV S/S & 2) 2X25 MVA, 132/33KV T/F WITH BAYS bhenda-132kV S/S. & to meet the increased load in the area. 3) 33KV OUTLETS-8 NOS ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

1 132 KV LINK LINE AHMEDNAGAR 1) 132KV YEOLA - KOPERGAON SCDC LINE - 25 KM 132kV Yeola S/S is fed from 132kV Manmad S/s ( 2008 - 09) with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 2 132 KV LINK LINE NASIK 1) 132 KV SAKRI - VISARWADI D/C LINE - 40 KMS 132kV Sakri S/S is fed from 132kV Dhule S/s with ( 2008 - 09) WITH BAYS S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

3 132 KV LINK LINE NASIK 132KV NAMPUR - MALEGAON SCDC LINE-30 KM 132kV Nampur S/S is fed from220/132kV ( 2008 - 09) Malegaon S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

4 132 KV LINK LINE NASIK 132KV MALEGAON - MANMAD D/C LINE-34 KM 132kV Manmad S/S is fed from220kV Malegaon ( 2008 - 09) S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 115 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 5 220KV LINK LINE NASIK 1) 220 KV SATANA - MALEGAON SCDC LINE - 30 220kV Satana S/S is fed from 220kV Malegaon (2009-10) KMS S/s with S/c line and this line is also critically loaded to an extent of 210 MW. Hence to provide uninterrupted supply during planned outages & Reduce the loading of line it is necessary to add proposed line 6 132KV LINK LINE AHMEDNAGAR 1) 2ND CIRCUIT STRINGING OF 132 KV AKOLE- 132kV Sangamner S/S is fed from 220kV (2009-10) SANGAMNER - 20 KM. Babhaleshwar S/s with S/c line and this line is also critically loaded to an extent of 71 MW. Hence to provide uninterrupted supply during planned outages & Reduce the loading of line it is necessary to add proposed line ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

1 220 KV LINK LINE NASIK 1) 220KV DHULE - MALEGAON D/C LINE - 40 KMS Since the existing 220kV Dhule-Malegaon S/c line (2009-10) is loaded to an extent of 162 MW during Non- Coinsident peak condition. It is anticipated the load will reach to about critical value by the year 2011-12. Hence it is necessary to propose additional line to meet additional load growth and contingency. 2 132KV LINK LINE NASIK 1) 132 KV AMALNER - NARDANE SCDC LINE - 35 Since the existing 132kV Dhule-Nardane S/c line (2009-10) KMS is getting loaded to an extent of 66 MW during Non-coinsident peak condition. It is anticipated the load will reach to about critical value by the year 2011-12. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

AUGMENTATION OF S/S BY ADDITION OF T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE 1 220 KV MALEGAON - II NASIK 1) ADDL. 1X 50 MVA, 220/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or S/S ( 2008 - 09 ) 2) 6 X 33 KV OUTLETS interruptions on any one transformer 2 220 KV SATANA NASIK 1) ADDL. 1 X 200 MVA, 220/132 KV ICT WITH BAYS To avoid loss of supply in case of outages or ( 2008 - 09 ) 2) 132 KV BAYS - 2 NOS. interruptions on any one transformer 3 220 KV SHAHADA NANDURBAR 1) ADDL. 1 X 100 MVA, 220/132 KV ICT WITH BAY To avoid loss of supply in case of outages or ( 2008 - 09 ) 2) 132 KV BAYS - 2 NOS. interruptions on any one transformer 4 220 KV DHULE S/S * DHULE 1) 1 X 25 MVA , 220/33KV T/F WITH BAYS To avoid loss of supply in case of outages or ( 2008 - 09 ) 2) 33 KV OUTLETS - 4 NOS. interruptions on any one transformer 5 220KV DONDAICHA S/S* DHULE 1) 1X100MVA, 220/132KV ICT WITH BAYS To avoid loss of supply in case of outages or ( 2008 - 09 ) interruptions on any one transformer 2) 132 KV BAYS - 2 NOS. 6 132 KV PIMPERKHED S/S NASIK 1) 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or ( 2008 - 09 ) interruptions on any one transformer 2) 33 KV OUTLETS - 4 NOS. 7 132KV JALGAON (MIDC) JALGAON 1) ADDL. 1X50 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or S/S interruptions on any one transformer ( 2008 - 09 ) 2) 6 X 33KV OUTLETS

8 132 KV BODWAD S/S ( JALGAON 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or 2008 - 09 ) interruptions on any one transformer 2) 33 KV OUTLETS - 4 NOS. 9 132 KV PAROLA S/S ( JALGAON 1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or 2008 - 09 ) interruptions on any one transformer 2) 33 KV OUTLETS - 4 NOS.

10 132 KV NARDANE S/S ( DHULE 1) ADDL. 1X25MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or 2008 - 09 ) interruptions on any one transformer 2) 33 KV OUTLETS - 4 NOS.

11 132 KV NIMBHORA S/S JALGAON 1) 1 X 25 MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, ( 2008 - 09 ) 132/33 - 1 x 25 - 16 To avoid loss of supply in case of outages or 2) 33 KV OUTLETS - 4 NOS. interruptions on any one transformer

116 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 12 220 KV NASIK - II S/S NASIK 1) ADDL. 1 X 200 MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s is, (RAYMOND)* 220/132 - 1 x 200 - 152 ( 2008 - 09 ) 132 KV BAYS - 2 NOS. Considering the maximum load reach on the 2) transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

13 400 KV BHUSAWAL JALGAON 1) 1 X 315 MVA, 400/220 KV ICT WITH BAYS Existing Transformer capacity available is 400/220 S/S(2009-10) 2) 220 KV BAYS - 2 NOS. kV, 1 X 315 MVA and load reached is 198 MVA, Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

14 AHEMADNAGAR AHMEDNAGAR 1) ADDL. 1 X 100 MVA, 220/132 kV T/F with bays. The existing Transformer capacity available is (2009-10) 2) 132 KV BAYS - 2 NOS. 220/132 kV 1X100MVA and the load reached is 64 MVA. To avoid loss of supply in case of outages or interruptions on any one transformer other transformer should take care of existing load so as to avoid load shedding.

15 220 kV DHULE-II * Dhule 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. To avoid loss of supply in case of outages or interruptions on transformer.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

1 220 KV AHMEDNAGAR AHMEDNAGAR 1) ADDL. 2X 25 MVA, 220/33 KV T/FS WITH BAYS Newly established LV level (33 kV) to feed the S/S(2008-09) nearby area at proper voltage 2) 33 KV OUTLETS - 8 NOS.

2 132 KV OZAR S/S NASIK 1) ADDL. 2 X 25 MVA, 132/33 KV T/FS WITH BAYS To eliminate 11 kV level from the existing (2008-09) 2) 8 X 33 KV OUTLETS S/s.33KV is introduced.

3 132 KV MALEGAON S/S NASIK 1) 1X 50 MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 50MVA - LOAD IS 78 MVA. 2) 6 X 33 KV OUTLETS Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

4 132KV VARANGAON NASIK 1) ADDL. 1X25MVA,132/33KV TF'S WITH BAYS Consedering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should 2) 33KV OUT LET-04 nos take care of existing load so as to avoid load shedding.

5 400 KV DHULE S/S DHULE 1) 1 X 500 MVA, 400/220KV ICTS WITH BAYS Existing Transformer capacity available is 400/220 (2009-10) 2) 220 KV BAYS - 4 NOS. kV, 2 X 315 MVA and load reached is 503 MVA, Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

6 400 KV BABHALESHWAR AHMEDNAGAR 1) 1 X 500 MVA, 400/220KV ICTS WITH BAYS Existing Transformer capacity available is 400/220 S/S 2) 220 KV BAYS - 4 NOS. kV, 2 X 315 MVA and load reached is 598 MVA, (2009-10) Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

7 220KV EKLAHARE GCR* NASIK 1) ADDL. 1X150MVA,220/132KV ICT WITH BAYS Existing Transformer capacity available is 220/132 (2009-10) 2) 132 KV BAYS - 3 NOS. kV, 2X 150 and 1 X 200 MVA and load reached is 290 MVA. Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

117 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 8 220 KV MALEGAON S/S NASIK 1) 1 X 200 MVA, 220/132 KV ICTS WITH BAYS Existing Transformer capacity available is 220/132 (2009-10) 2) 132 KV BAYS - 4 NOS. kV, 2 X 100 MVA and load reached is 185 MVA.The transformer is replaced to meet the anticipated load growth. Considering the maximum load reach on the transformer, in event of intruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 9 220KV DHULE S/S DHULE 1) 1X 150 MVA, 220/132KV WITH BAYS Existing Transformer capacity available is 220/132 (2009-10) 2) 132 KV BAYS - 3 NOS. kV, 2 X150 MVA and load reached is 201 MVA.The transformer is replaced to meet the anticipated load growth. 10 132 kV SATANA Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 27 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

11 132 kV DHARANGAON Jalgaon 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 (2009-10) 2) 4 X 33 kV out lets. X 25 & 1 X 16 MVA. And the load reached is 20 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

12 132 kV RAHURI Ahmednagar 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 (2009-10) 2) 4 X 33 kV out lets. X 50 & 1 X 25 MVA. And the load reached is 37 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

13 132 kV AMBAD NASIK Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA. And the load reached is 42 MVA TConsidering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

14 132 kV AHMEDNAGAR Ahmednagar 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 MIDC 2) 4 X 33 kV out lets. X 25 MVA and load is 26 MVA. Considering the (2009-10) maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

15 132 kV AHMEDNAGAR Ahmednagar 1) Add 1 X 50 MVA, 132/33 kV T/F with bays Existing transformer capacity available in S/s is 1 (Kedgaon) 2) 6 X 33 kV out lets. X 50 &1 X 25 MVA and load is 39 MVA. (2009-10) Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

16 132 kV AKOLE Ahmednagar 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing transformer capacity available in S/s is 1 (2009-10) 2) 2) 4 X 33 kV out lets X 50 MVA and load is 32 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

17 132 kV CHALISGAON-I Jalgaon 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 37 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

118 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 18 132 kV CHOPDA Jalgaon 1) 1 X 50 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 6 X 33 kV out lets. X 50 & 1X 25 MVA and load is 63 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

19 132 kV DHULE-I * Dhule 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 4 X 33 kV out lets. X 25, 1 X 50 MVA and load is 44 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

20 132 kV SHIRPUR Nandurbar 1) Add1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 6 X 33 kV out lets. X 50 & 1 X 25 MVA and load is 49 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

21 132 kV NANDURBAR (2009- Nandurbar 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 10) 2) 4 X 33 kV out lets. X 25, 1 X 50 MVA and load is 44 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

22 132 kV TALODA Nandurbar 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25MVA and load is 34 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

23 132 kV DEEPNAGAR (2009- Jalgaon 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 10) 2) 4 X 33 kV out lets. X 25, 1 X 16 MVA and load is 28 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

24 132 kV DINDORI Nasik 1) Add1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 6 X 33 kV out lets. X 50 & 1 X 25 MVA and load is 49 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

25 132 kV KARJAT Ahmednagar 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 26 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

26 132 kV KOPERGAON Ahmednagar 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 34 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

27 132 kV LASALGAON Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 25 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

119 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 28 132 kV MALEGAON-I Nasik 1) Add 1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 6 X 33 kV out lets. X 50 MVA and load is 88 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

29 132 kV MANMAD Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 4 X 33 kV out lets. X 25 & 1 X 50 MVA and load is 33 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

30 132 kV NAMPUR Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 24 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

31 132 kV NEWASA Ahmednagar 1) Add 2 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 8 X 33 kV out lets. X 50 &1 X 25 MVA and load is 40 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

32 132 kV SATPUR MIDC Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 22 MVA. Considerin the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

33 132 kV SHAHADA Dhule 1) Add 1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 6 X 33 kV out lets. X 25, 1 X 50 MVA and load is 50 MVA. Considerin the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

34 132 kV SHEVGAON Ahmednagar 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 28 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

35 132 kV SUPA Ahmednagar 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 26 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

36 132 kV TAKLI Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 25 MVA and load is 34 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

37 132 kV YAVAL Jalgaon 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 4 X 33 kV out lets. X 25 & 1 X 16 MVA and load is 31 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

120 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 38 132 kV PACHORA Jalgaon 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2009-10) 2) 4 X 33 kV out lets. X 10.8 MVA and load is 10 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

39 132 kV DHARANGAON Jalgaon 1) Add 1 X 25 MVA 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 (2009-10) 2) 4 X 33 kV out lets. X 25 & 1 X 16 MVA. And the load reached is 20 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

40 220 kV DONDAICHA (2009- Dhule 1) Add 1 X 25 MVA 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 10) 2) 4 X 33 kV out lets. X 25 MVA. And the load reached is 20 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

41 220 kV BABHALESHWAR Ahmednagar 1) Add 1 X 50 MVA, 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2009-10) 2) 6 X 33 kV out lets. X 50 MVA and load is 45 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

121 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION AUGMENTATION OF S/S BY REPLACEMENT OF TRANSFORMER 1 132 KV PACHORA S/S JALGAON 1) 1 X ( 50-25) MVA, 132/33 KV T/FS Existing transformer capacity available in S/s (2008 - 09 ) is,132/33 - 2 x 25 MVA and load is 44 MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any 2) 33 KV OUTLETS - 2 NOS. one of the transformer other transformer should take care of existing load so as to avoid load shedding.

2 132 KV DHARANGAON JALGAON 1) 1 X ( 25 - 16) MVA, 132/33 KV T/FS Existing transformer capacity available in S/s S/S 2) 33 KV OUTLETS - 2 NOS. is,132/33 - 2 x 16 MVA and load is 28 (2008 - 09 ) MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

3 132 KV DHULE S/S* DHULE 1) REP.1 X ( 50-25) MVA, 132/33 KV T/FS Existing transformer capacity available in S/s (2008 - 09 ) 2) 33 KV OUTLETS - 2 NOS. is,132/33 - 2 x 25 MVA and load is 50 MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

4 132 KV AKOLE S/S AHMEDNAGAR 1) REP. 1 X ( 50-25) MVA, 132/33 KV T/FS Existing transformer capacity available in S/s (2008 - 09 ) 2) 33 KV OUTLETS - 2 NOS. is,132/33 - 2 x 25 MVA and load is 30 MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

5 132 KV SHRIGONDA S/S* AHMEDNAGAR 1) REP. 1 X ( 50-25) MVA, 132/33 KV T/FS Existing transformer capacity available in S/s (2008 - 09 ) is,132/33 - 2 x 25 MVA and load is 20 MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 2) 33 KV OUTLETS - 2 NOS. 6 132 KV SANGAMNER S/S AHMEDNAGAR 1) REP.1 X ( 50-25) MVA, 132/33 KV T/FS Existing transformer capacity available in S/s (2008 - 09 ) is,132/33 - 1 x 25 MVA and load is 24 MVA, 132/33 - 1 x 20 MVA and load is 19.66 MVA.Considering the maximum load reach on the 2) 33 KV OUTLETS - 2 NOS. transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

7 220 KV MALEGAON - II NASIK 1) 2 X (200-100) MVA, 220/132 KV ICTS Existing transformer capacity available in S/s S/S is,220/132KV - 2 x 100 MVA and load is 160 (2008 - 09 ) MVA. Considering the maximum load reach on the transformer, in event of interruption/outage on any 2) 4 X 132KV BAYS one of the transformer other transformer should take care of existing load so as to avoid load shedding.

8 220 & 132KV JALGAON 1) 2 X (200-100)MVA 220/132KV ICTS Existing transformer capacity available in S/s CHALISGAON S/S is,220/132 KV - 1 x 150 MVA and load is 119 (2008 - 09 ) MVA, 220/100 KV - 1 x 100 MVA and load is 79 MVA. 132/33 KV - 2 x 25 MVA and load is 40 2) 2 X ( 50 - 25) MVA, 132/33 KV T/FS MVA. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should 3) 2 X 33KV OUTLETS take care of existing load so as to avoid load 4) 2 X 132 KV OUTLETS shedding.

122 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 9 132KV MALEGAON NASIK 1) REP. (25 -16)MVA, 132/33KV T/F Existing transformer capacity available in S/s ( MIDC) S/S is,132/33 KV - 2 x 25 MVA and load is 40.52 (2008 - 09 ) 2) 2 X 33KV OUTLETS MVA, 132/33 KV - 1 x 16 MVA and load is 9.76 MVA. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

10 132 KV NANDURBAR S/S* NANDURBAR 1) 1 X ( 50-25) MVA, 132/33 KV T/F Existing transformer capacity available in S/s (2008 - 09 ) is,132/33 KV - 2 x 25 MVA and load is 30 MVA. 2) 33 KV OUTLETS - 2 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

11 132 KV DEEPNAGAR S/S ( JALGAON 1) 1 X (25-16) MVA, 132/33 KV T/F Existing transformer capacity available in S/s BHUSAWAL) is,132/33 KV - 1 x 25 MVA and load is 17 MVA, (2008 - 09 ) 132/33 KV - 1 x 16 MVA and load is 12 2) 33 KV OUTLETS - 2 NOS. MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

12 132 KV RAVER S/S** JALGAON 1) 2 X (50-25/10) MVA, 132/33 KV T/F Existing transformer capacity available in S/s (2008 - 09 ) is,132/33 KV - 1 x 25 MVA and load is 15 MVA, 132/33 KV - 1 x 10 MVA and load is 9 2) 33 KV OUTLETS - 6 NOS. MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

13 132 KV JALGAON S/S* JALGAON 1) REP. 2 X ( 50-25) MVA, 132/33 KV T/FS Existing transformer capacity available in S/s (2008 - 09 ) is,132/33 KV - 1 x 50 MVA and load is 32 MVA, 132/33 KV - 2 x 25 MVA and load is 29 2) 33 KV OUTLETS - 4 NOS. MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

14 220 KV CHALISGAON S/S JALGAON 1) 1 X (200-100)MVA 220/132 KV ICTS Existing Transformer capacity available is 220/132 (2009-10) 2) 132 BAYS - 2 NOS. kV, 2 X 100 MVA and load reached is 141 MVA, The transformer is replaced to meet the anticipated load growth. 15 220 KV BHUSAWAL JALGAON 1) 1X(200-100)MVA, 220/132KV ICT Existing Transformer capacity available is 220/132 (2009-10) 2) 132 KV BAYS - 2 NOS. kV, 2 X 100 MVA and load reached is 102 MVA,The transformer is replaced to meet the anticipated load growth. 16 220KV BABHALESHWAR AHMEDNAGAR 1) 1X(200-100)MVA, 220/132KV Existing transformer capacity available in S/s S/S 2) 132 KV BAYS - 2 NOS. is,220/132kV, 1 x 200 and 1 X 100 MVA and the (2009-10) load reached is 115 MVA and 110 MVA respectively.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

17 132 kV IGATPURI Nasik 1) Add 2 X (25-12.5) , 132/25 kV T/F Existing transformer capacity available in s/s is 2 (2009-10) 2) 4 X 33 kV out lets. X 12.5 MVA. And the load reached is 15 MVA The transformer is replaced to meet anticipated load growth..

18 132 kV AMALNER Jalgaon 1) Add 2X (50-12.5) MVA , 132/33 kV T/F Existing transformer capacity available in s/s is 2 (2009-10) 2) 6 X 33 kV out lets. X 12.5 MVA. And the load reached is 15 MVA The transformer is replaced to meet anticipated load growth..

19 132 kV DEEPNAGAR (2009- Jalgaon 1) 1 X (20-12.5) MVA, 132/25 kV T/F Existing transformer capacity available in s/s is 1 10) 2) 25 KV BAYS - 2 NOS. X 12.5 & 1 X 20 MVA. And the load reached is 28 MVA The transformer is replaced to meet anticipated load growth..

123 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 20 220 kV NASIK OCR Nasik 1) Add 1X (50-25) MVA, 132/33 kV T/F Existing transformer capacity available in s/s is 3 (2009-10) 2) 2 nos. of 33 kV outlets X 25 MVA. And the load reached is 43 MVA The transformer is replaced to meet anticipated load growth.. 21 132 kV JALGAON ( Old) Jalgaon 1) 1 X (50 -25 ) 132/33 kV T/F. Existing transformer capacity available in S/s is 1 (2009-10) 2) 2 X 33 kV out lets. X 50, 1 X 25 MVA and load is 42 MVA. The transformer is replaced to meet anticipated load growth.

22 132 kV SAVDA Jalgaon 1) 1 X (50 -20 ) 132/33 kV T/F Existing transformer capacity available in S/s is 3 (2009-10) 2) 2 X 33 kV out lets. X 20 MVA and load is 55 MVA. The transformer is replaced to meet anticipated load growth.

23 132 kV SATPUR* Nasik 1) 1 X (50 -25 ) 132/33 kV T/F. Existing transformer capacity available in S/s is 1 (2009-10) 2) 2 X 33 kV out lets. X 50, 1 X 25 MVA and load is 38 MVA. The transformer is replaced to meet anticipated load growth. 24 132 kV SINNAR ( Old) Nasik 1) 1 X (50 -25 ) 132/33 kV T/F Existing transformer capacity available in S/s is 1 (2009-10) 2) 2 X 33 kV out lets. X 50, 1 X 25 MVA and load is 36 MVA. The transformer is replaced to meet anticipated load growth.

124 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION NEW SCHEMES 1 220KV KALWAN II S/S NASIK 1) 220KV MALEGAON - KALWAN D/C LINE - 48.56 Upgradation of existing 132 kv Kalwan s/s for the (2010-11) KMS WITH BAYS load requrement in Nasik area. 2) 2X100MVA, 220/132KV ICTS WITH BAYS

3) 2X50MVA, 220/33KV T/FS WITH BAYS 4) 2 X 132KV BAYS

5) 12 X 33KV OUTLETS 6) 132KV DC LINE TO 132 KV KALWAN S/S - 10 KM 2 220KV SAYANE S/S NASIK 1) LILO OF 220 KV DHULE - MALEGAON CKT. - I AT Sayne-220kV is considered for reducing the (2010-11) 2) 2X25220 KV MVA, SAYANE 220/33KV - 10 KMS.T/F WITH BAYS loading of Dhule-220kV S/S. to meet the upcoming load in the area. 3) 33KV OUTLETS-8 NOS 3 132 KV GHODEGAON S/S ( AHMEDNAGAR 1) 2X50MVA, 132/33KV T/F WITH BAYS. Strengthening of existing network. 2010 - 11) 2) 132KV SCDC LINE FROM SHEVGAON S/STN - 3) GHODGAON 33KV OUTLETS -37KM - 12 NOS 4 400 KV NASIK S/S NASIK 1) 400 KV D/C LINE FROM 400 KV BABHALESHWAR Evacuation of Power from central sector & to (2011-12) - NASHIK LINE - 60 KMS cater the increasing load in nearby area

2) 400 KV SINNAR (IPP) - NASIK D/C LINE. -10KMS.

3) 2 X 500 MVA 400/220 KV ICT'S WITH BAYS. 4) 220 KV D/C LINE TO SINNAR II S/S -15 KMS . 5) LILO of 220 KV EKLAHARE - BABHALESHWAR 5 220KV SAKRI S/S DHULE 1) LILOLINE ONAT 400220 KVKV NASHIKMALEGAON - 15 KMS.- GANGAPUR S/C Present recorded peak on Sakri and Nampur (2011-12) LINE AT 220 KV SAKRI - 45 KMS. 132kV S/S are 70 and 28 MW respectively. It is 2) LILO OF 220 KV SATANA - GANGAPUR S/C LINE anticipated by the year 2011-12, the load will AT 220 KV SAKRI - 45 KMS. reach to criticle value. Hence it is necessary to go 3) 2X100 MVA, 220/132KV T/F WITH BAYS in for new 220kV sub-station at Sakri. 4) 132 KV SCDC LINE TO VISARWADI- 15 KMS 5) 132KV SCDC LINE TO NAMPUR S/S - 20 KMS

6) LILO OF 132 KV SATANA - TAHARABAD LINE AT 220 KV SAKRI - 10 KMS. 6 220KV BHOSE S/S AHMEDNAGAR 1) 220KV D/C A'NAGAR-BHOSE - 45 KM WITH BAYS Bhose 220kV S/S is considered to improve the ( BELWANDI) voltage profile in Ahemadnagar District & to meet 2) 2X100 MVA, 220/132KV T/F WITH BAYS (2011-12) the upcoming load. 4) 132KV LINE BHOSE - KARJAT D/C- 80 KMS

5) 132KV LINE BHOSE - SHRIGONDA D/C - 30 KMS.

7 220 KV VIRODA S/S JALGAON 1) LILO ON 220 KV BHUSAWAL - AMALNER 220 KV Viroda substation is proposed to meet (2011-12) CKT. II LINE AT 220 KV VIRODA - 10 KMS. requirement of alternate feed to existing S/c lines 2) 2 X 200MVA, 220/132KV ICTS WITH BAYS to 132 KV substations. Will improve voltage profile and meet upcoming load. 3) 2 X 50 MVA 220/33 KV T/F WITH BAYS

4) 132 KV VIRODA - YAWAL D/C LINE - 30 KM

5) 132 KV VIRODA - SAWADA M/C LINE - 10 KM (OUT OF 4 CKTS TWO CIRCUITS TO SAWADA 6) 132AND KV TWO D/C CIRCUITS LINE FROM TO SAWDA BE CONNECTED TO NIMBHORA TO - 16 KM 7) 132 KV SCDC LINE FROM NIMBHORA TO RAVER - 20 KM 8) 132KV VIRODA - BHUSAWAL-II M/C LINE - 25 KM

125 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 8 400KV MALEGAON NASIK 1) 2X500MVA,400/220KV ICT To improve voltage profile of the area and to meet (SATANA) the upcoming demand. 2) 400KV D/C LINE FROM DHULE- (2013-14) MALEGAON(NASIK) D/C - 60KM WITH BAYS 3) 220KV LINE FROM MALEGAON - CHALISGAON SCDC -69KM 4) REORINTATION OF EXISTING 220 KV MALEGAON - SATANA S/C LINE AT 400 KV MALEGAON ( Proposed) - 10 kms. 5) 220KV D/C LINE FROM 400KV MALEGAON(SATANA) - 220KV NASIK -80KM 6) 220KV D/C LINE FROM 400KV MALEGAON(SATANA) - KALWAN -32KM 7) INTER LINK D/C LINE FROM EXISTING 220KV MALEGAON - 400KV MALEGAON (SATANA) - 9 220KV MANMAD NASIK 1) 2X100MVA,10KM 220/132KV ICT WITH BAYS To cater the increasing load in nearby area (2013-14)

2) 220KV D/C LINE FROM MANMAD - 400KV MALEGAON (SATANA) - 38KM 3) 132KV INTER LINK FROM 220KV MANMAD TO MANMAD ( Existing) - 15KM 4) REORINTATION OF EXISTING 132 KV MANMAD - YEOLA LINE AT 220 KV MANMAD ( Proposed) - 10 kms. ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 132KV LINK LINE NASIK 1) 132 KV SHIRPUR - FROM 220/132KV DONDAICHA 132kV Shirpur S/S is fed from 132kV Nardane S/s (2011-12) S/S SCDC LINE - 50 KMS WITH BAYS with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

2 132KV LINK LINE NASIK 1) 132 KV CHOPADA- YAWAL SCDC LINE - 43 KM 132kV Chopda S/S is fed from132kV Yawal S/s (2012-13) with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

3 132KV LINK LINE JALGAON 1) 132 KV PAROLA - AMALNER 2ND CKT 132kV Parola S/S is fed from132kV Amalner S/s (2012-13) STRINGING - 17.16 KM with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

4 132KV LINK LINE DHULE 1) 132 KV TALODA - SHAHADA SCDC LINE - 132kV Taloda S/S is fed from220/132kV Shahada (2012-13) 28.61KM S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

5 132KV LINK LINE AHMEDNAGAR 1) 2ND CIRCUIT STRINGING OF 132 KV SHEVGAON 132kV Ghodegaon S/S is fed from132kV (2013-14) - GHODEGAON - 37 KMS. Shevgaon S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 132KV LINK LINE NASIK 1) 132 KV MALEGAON-II - MALEGAON ONLY Since the existing 132kV Malegaon -II - Malegaon (2010-11) STRINGING OF 2ND CKT - 2.5 KMS WITH BAYS S/c line is getting loaded to an extent of 35 MW during Non-coinsident peak condition. It is anticipated the load will reach to about critical value by the year 2011-12. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

2 132KV LINK LINE NASHIK 1) 2ND CIRCUIT STRINGING OF 132 KV MANMAD - It is anticipated the load will reach to about critical (2010-11) YEOLA - 25 KMS. value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. 3 132KV LINK LINE DHULE 1) 132 KV D/C LINE FROM NANDURBAR - TALODA - For System Strengthening. (2010-11) 35 KMS. 4 220KV LINK LINE JALGAON 1) 220KV BHUSAWAL - CHALISGAON D/C LINE - Since the existing 220kV Bhusawal-Chalisgaon (2011-12) 123.88 KM WITH BAYS D/c line is loaded to an extent of 126.5(EACH) MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value by the year 2011-12. Hence it is necessary to propose additional line to meet additional load growth and contingency.

126 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 5 132KV LINK LINE NASHIK 1) LILO OF 132 KV RAYMONDS - ADGAON AT 132 For System Strengthening. (2011-12) KV MHASRUL S/S. - 10 KMS. 6 132KV LINK LINE NASIK 1) 2ND CIRCUIT STRINGING 132 KV KOPARGAON - It is anticipated the load will reach to about critical (2012-13) YEOLA-20 KM value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. 7 132KV LINK LINE NASIK 1) 132KV LASALGAON - RANWAD SCDC -14KM Since the existing 132kV Lasalgaon - Ranwad (2012-13) S/C line is loaded to an extent of 39 MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

8 132KV LINK LINE NASIK 1) 132KV EKLAHARE(OCR) - TAKLI SCDC -12KM Since the existing 132kV Eklahare (OCR) - Takli (2012-13) line is loaded to an extent of 63 MW during Non- Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

9 132KV LINK LINE NASIK 1) 132KV AMBAD - EKLAHARE (OCR) SCDC -19KM Since the existing 132kV Eklahare (OCR) - (2012-13) Ambad line is loaded to an extent of 24 MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. 10 132KV LINK LINE NASIK 1) 132KV EKLAHARE(GCR)-OZAR SCDC -17KM Since the existing 132kV Eklahare (GCR) - Ozar (2012-13) D/C line is loaded to an extent of 90 MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

11 132KV LINK LINE JALGAON 1) 132 KV SCDC LINE FROM CHOPDA - SHIRPUR - For System Strengthening. (2012-13) 50 KMS. 12 132KV LINK LINE NASHIK 1) 2ND CIRCUIT STRINGING OF 132 KV MALEGAON It is anticipated the load will reach to about critical (2012-13) - NAMPUR LINE - 30 KMS. value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

STRENGTHENING FOR EVACUATION ARRANGEMENT 1 400 KV LINK LINE NASHIK 1) 400 KV D/C LINE FROM 400 KV MALEGAON ( Strengthening for power evacuation of proposed (2013-14) Proposed) - NASHIK - 100 KMS. generations at Nashik & Dondaicha.

STRENGTHENING FOR WIND POWER EVACUATION 1 132 KV LINK LINE DHULE 132 KV DONDAICHA(220 S/S)- DONDAICHA D/C Strengthening for wind power evacuation (2010-11) LINE -10KMS. 2 132 KV LINK LINE NASIK 2ND CIRCUIT STRINGING OF 132 KV KALWAN - For System Strengthening. (2010-11) SATANA LINE -20KMS ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE 1 220KV LINK LINE JALGAON 1) CONVERSION OF S/C TO D/C OF 220KV To reduce the loading of the existing line (2011-12) CHALSIGAON - BABHALESHWAR LINE UPTO KOPERGAON TAP - 120 KM AUGMENTATION OF S/S BY ADDITION OF T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE ICT IS AVAILABLE 1 220 KV BHENDA 1) ADDL. 1 X 100 MVA, 220/132 kV T/F with bays The Transformer capacity available is 220/132 kV ( BELWANDI) 2) 132 KV BAYS - 2 NOS. 1X100MVA . To avoid loss of supply in case of ( 2010-11) outages or interruptions on any one transformer other transformer should take care of existing load so as to avoid load shedding.

127 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER 1 132 kV AMBAD NASIK Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 (2010-11) 2) 4 X 33 kV out lets. X 25 MVA. And the load reached is 42 MVA TConsidering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

2 132 kV SANGAMNER Ahmednagar 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 (2011-12) 2) 4 X 33 kV out lets. X 50 & 1 X 25 MVA. And the load reached is 42 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

3 132 kV SATPUR Nashik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 (2011-12) 2) 4 X 33 kV out lets. X 50 & 1 X 25 MVA. And the load reached is 38 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

4 132 kV KHARDA Ahmednagar 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2011-12) 2) 4 X 33 kV out lets. X 25 MVA and load is 20 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

5 132 kV RANWAD Nasik 1) Add 1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2011-12) 2) 6 X 33 kV out lets. X 50 MVA and load is 40 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

6 132 kV RAVER Jalgaon 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2011-12) 2) 4 X 33 kV out lets. X 25 & 1 X 10 MVA and load is 22 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

7 132 KV PIMPARKHED S/S. NASHIK 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 ( 2011 - 12) 2) 4 X 33 kV out lets. X 25 MVA . Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

8 132 KV SINNAR NASHIK 1) Add 1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 (MALEGAON) S/S. 2) 6 X 33 kV out lets. X 25 & 1 X 50 MVA. And the load reached is 43 ( 2011 - 12) MVA .Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

9 132 kV RAMACHE Nasik 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 PIMPLAS 2) 4 X 33 kV out lets. X 25 MVA and load is 22 MVA. Considering the (2012-13) maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

10 220 kV BHENDA Ahmednagar 1) Add 1 X 25 MVA, 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 (2013-14) 2) 4 X 33 kV out lets. X 25 MVA and load is 18 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

128 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 11 132 kV CHALISGAON-I Jalgaon 1) Add 1 X 25 MVA, 132/25 kV T/F with bays. Existing transformer capacity available in S/s is 1 (2013-14) 2) 4 X 33 kV out lets. X 10.8 MVA . Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

AUGMENTATION OF S/S BY ADDITION OF T/F Creation of new 33 KV level ( EHV substations already proposed in STU plan). 1 220 KV PIMPALGAON NASHIK 1) 1 X 50 MVA 220/33 KV T/F WITH BAYS Creation of new 33 KV level ( BASVANT) S/S 2) 33 KV OUTLETS : 6 NOS. (2010-11) 2 220 KV SAKRI S/S. DHULE 1) 2 X 25 MVA , 220/33 KV T/F WITH BAYS Creation of new 33 KV level ( 2011-12) 2) 33 KV OUTLETS : 8 NOS.

3 220 KV PIMPALGAON NASHIK 1) 1 X 50 MVA 220/33 KV T/F WITH BAYS Creation of new 33 KV level ( BASVANT) S/S 2) 33 KV OUTLETS : 6 NOS. (2011-12)

4 220 KV SAKRI S/S. DHULE 1) 2 X 25 MVA , 220/33 KV T/F WITH BAYS Creation of new 33 KV level ( 2012-13) 2) 33 KV OUTLETS : 8 NOS.

5 220 KV BHOSE S/S NASHIK 1) 1 X 50 MVA 220/33 KV T/F WITH BAYS Creation of new 33 KV level (2012-13) 2) 33 KV OUTLETS : 6 NOS.

6 220 KV BHOSE S/S NASHIK 1) 1 X 50 MVA 220/33 KV T/F WITH BAYS Creation of new 33 KV level (2013-14) 2) 33 KV OUTLETS : 6 NOS.

7 220 KV MANMAD S/S. NASHIK 1) 1 X 25 MVA , 220/33 KV T/F WITH BAYS Creation of new 33 KV level ( 2013-14) 2) 33 KV OUTLETS : 4 NOS.

8 220 KV MANMAD S/S. NASHIK 1) 1 X 25 MVA , 220/33 KV T/F WITH BAYS Creation of new 33 KV level ( 2014-15) 2) 33 KV OUTLETS : 4 NOS.

Creation of new 33 KV level ( Existing EHV substations ). 1 220 KV RAYMONDS S/S. ( NASHIK 1) 1 X 50 MVA 220/33 KV T/F WITH BAYS Creation of new 33 KV level 2011 - 12 ) 2) 33 KV OUTLETS : 6 NOS. 2 220 KV RAYMONDS S/S. ( NASHIK 1) 1 X 50 MVA 220/33 KV T/F WITH BAYS Creation of new 33 KV level 2012 - 13 ) 2) 33 KV OUTLETS : 6 NOS. 3 220 KV AMALNER S/S DHULE 1) 1 X 25 MVA 220/33 KV T/F WITH BAYS Creation of new 33 KV level (2012-13) 2) 33 KV OUTLETS : 4 NOS. 4 220 KV AMALNER S/S DHULE 1) 1 X 25 MVA 220/33 KV T/F WITH BAYS Creation of new 33 KV level (2013-14) 2) 33 KV OUTLETS : 4 NOS. AUGMENTATION OF S/S BY REPLACEMENT OF TRANSFORMER 1 400 KV BABHALESHWAR NASIK 1) 1X(500-315)MVA, 400/220 KV ICT Existing Transformer capacity available is 400/220 S/S 2) 220 KV BAYS - 2 NOS. kV, 2 X 315 MVA and load reached is 598 (2010-11) MVA.The transformer is replaced to meet the anticipated load growth.

2 220 KV MALEGAON S/S NASIK 1) 1 X (200-100) MVA, 220/132 KV ICTS Existing Transformer capacity available is 220/132 (2010-11) 2) 132 KV BAYS - 2 NOS. kV, 2 X 100 MVA and load reached is 185 MVAThe transformer is replaced to meet the anticipated load growth.

3 220 KV CHALISGAON S/S JALGAON 1) 1 X (200-100)MVA 220/132 KV ICTS Existing Transformer capacity availablewill be (2010-11) 2) 132 KV BAYS - 2 NOS. 220/132 kV, 1 X 100 MVA and1 X 200 MVA load reached is 158 MVA.The transformer is replaced to meet the anticipated load growth.

4 220 KV BHUSAWAL JALGAON 1) 1X(200-100)MVA, 220/132KV ICT Existing Transformer capacity available will be (2010 -11) 2) 132 KV BAYS - 2 NOS. 220/132 kV, 1 X 100 MVAand 1 X 200 MVA and load reached will be 115 MVA.The transformer is replaced to meet the anticipated load growth.

5 220KV BABHALESHWAR AHMEDNAGAR 1) 1X(200-100)MVA, 220/132KV Existing transformer capacity available in S/s S/S 2) 132 KV BAYS - 2 NOS. is,220/132kV, 2 x 200 and 1 X 100 MVA and the (2010-11) load reached will be 165 and 115 MVA respectively.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

129 STU/TRANS/DOC-04 - W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NASIK EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION 6 220 kV NASIK OCR Nasik 1) Add 1 X (50-25) MVA, 132/33 kV T/F. Existing transformer capacity available in s/s is 3 (2010-11 ) 2) 2 nos. of 33 kV outlets X 25 MVA. And the load reached is 43 MVA The transformer is replaced to meet anticipated load growth.. 7 132 kV SAVDA Jalgaon 1) 1 X (50 -20 ) 132/33 kV T/F Existing transformer capacity available in S/s is 3 (2010-11) 2) 2 X 33 kV out lets. X 20 MVA and load is 55 MVA. The transformer is replaced to meet anticipated load growth.

8 220 KV BHAMBORI JALGAON 1) Add 1 X (50-25) MVA, 220/33 kV T/F . To meet additional demand of MSEDCL. ( Proposed in 2009-10) S/S. 2) 2 nos. of 33 kV outlets ( 2010 - 11) 9 220 KV BHAMBORI JALGAON 1) Add 1 X (50-25) MVA, 220/33 kV T/F . To meet additional demand of MSEDCL. ( Proposed in 2009-10) S/S. 2) 2 nos. of 33 kV outlets ( 2011 - 12) 10 220 KV SAYANE NASHIK 1) Add 1 X (50-25) MVA, 220/33 kV T/F . To meet additional demand of MSEDCL. ( Proposed in 2010-11) S/S. 2) 2 nos. of 33 kV outlets ( 2011 - 12)

11 220 KV SAYANE NASHIK 1) Add 1 X (50-25) MVA, 220/33 kV T/F . To meet additional demand of MSEDCL. ( Proposed in 2010-11) S/S. 2) 2 nos. of 33 kV outlets ( 2012 - 13) 12 132 KV MANMAD S/S. NASHIK 1) Add 1 X (50-25) MVA, 132/33 kV T/F Existing transformer capacity available in S/s is 1 ( 2012-13) 2) 2 nos. of 33 kV outlets X 25 & 1 X 50 MVA and load is 52 MVA. The transformer is replaced to meet anticipated load growth. 13 132 KV NAMPUR S/S. ( NASHIK 1) Add 1 X (50-25) MVA, 132/33 kV T/F . Existing transformer capacity available in S/s is 2 2012-13) 2) 2 nos. of 33 kV outlets X 25 MVA and load is 38 MVA. The transformer is replaced to meet anticipated load growth.

14 220 KV BHENDA S/S. AHMEDNAGAR 1) Add 1 X (50-25) MVA, 132/33 kV T/F . To meet additional demand of MSEDCL. ( 2012-13) 2) 2 nos. of 33 kV outlets

15 220 KV KHARDA S/S. 1) Add 1 X (50-25) MVA, 132/33 kV T/F To meet additional demand of MSEDCL. ( 2012-13) 2) 2 nos. of 33 kV outlets 16 220 KV BHENDA S/S. AHMEDNAGAR 1) Add 1 X (50-25) MVA, 132/33 kV T/F . To meet additional demand of MSEDCL. ( 2013-14) 2) 2 nos. of 33 kV outlets 17 220 KV KHARDA S/S. 1) Add 1 X (50-25) MVA, 132/33 kV T/F . To meet additional demand of MSEDCL. ( 2013-14) 2) 2 nos. of 33 kV outlets 18 220 KV BHENDA S/S. AHMEDNAGAR 1) Add 1 X (200-100) MVA, 220/132 kV T/F To cater the increasing load in nearby area ( 2014 - 15) 2) 132 KV BAYS - 2 NOS.

130

EHV CC O&M ZONE : AURANGABAD

131 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

SPILL OVER SCHEMES 1 220KV SHENDRA S/S AURANGABAD 1) 2X50MVA, 220/33KV T/FS WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING (2008-09)

2) 10X33KV OUTLETS 3) 2X100MVA, 220/132KV ICTS WITH BAYS 4) 220KV CHITEGAON -SHENDRA SCDC LINE-25 KM 5) 132 KV SHENDRA DEOLAI SCDC LINE -25 KMS. 6) LILO ON 220KV WALUJ-JALNA D/C ON M/C - 3 KM D/C ON D/C-12 KM 2 220 KV HINGOLI S/S HINGOLI 1) 2X 100 MVA, 220/132 KV ICTS WITH BAYS This station is considered to meet the load growth (2008-09) in Aurangabad Circle and improving voltage 2) 2X 50 MVA, 220/33 KV T/F'S WITH BAYS profile. Hingoli-220kV S/S is proposed on LILO of 3) LILO ON 220 KV PUSAD - PARBHANI LINE - 22 KM WITH 220kV existing Pusad -Nanded D/C line – 4kM BAYS 4) 132KV BAYS - 4 NOS

5) 33KV OUTLETS - 12 NOS

6) LILO ON BOTH CKT OF 132KV DC KURANDA - HINGOLI LINE ON M/C -10KM 132KV AKHADA BALAPUR - 220KV HINGOLI SCDC LINE - 7) 25 KM 3 220KV PARANDA S/S OSMANABAD 1) 2X25MVA, 220/33KV T/FS WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING (2008-09) 2) 2 X 100 MVA 220/132 KV ICT'S WITH BAYS (2010-11)

3) 8X33KV OUTLETS 4) 220KV D/C LINE FROM 220KV BARSHI S/S- 30 CKM WITH BAYS 5) 132 KV SCDC LINE TO BHOOM S/S - 30 KMS

4 220KV BEED 1) 220KV D/C LINE BEED - PATODA - 45 KM WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING PATODA S/S 2) 2X50MVA, 220/33KV T/FS WITH BAYS (2008-09) 3) 12X33KV OUTLETS

5 132 KV BADNAPUR JALNA 1) 2 X 25MVA, 132/33KV T/F'S WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING S/S (2008-09) 2) LILO OF 132 KV PADEGAON - JALNA AT BADNAPUR S/S WITH BAYS -10KM 3) 8X33KV OUTLETS

6 132KV SHELU S/S PARBHANI 1) 2 X 25MVA, 132/33KV T/F'S WITH BAYS Shelu132kV S/S is considered to improve the (2008-09) voltage profile in Aurangabad circle and to cater 2) LILO ON 132KV PARBHANI-PARTUR AT SHELU S/S - 5 the new loads coming in nearby area. Shelu132kV CKM WITH BAYS S/S is fed from Pathri132kV S/S by constructing 3) 8X33KV OUTLETS 132kV D/C line of 10kM.

7 400KV NANDED S/S NANDED 1) LILO ON 400KV PARLI -CHANDRAPUR ON S/C AND To improve the voltage profile and to meet the (2009-10) LILO ON ONE CIRCUIT OF 400KV PARLI -CHANDRAPUR upcoming load. 2) 2D/C X 500 -40KM MVA, EACH 400/220KV ICTS WITH BAYS AND 1 X 167 SINGLE PHASE SPARE ICT 3) 220KV D/C LINE TO 220 KV NANDED (WAGHALA) S/S - 10KMS WITH BAYS 8 220KV LATUR 1) 2X100MVA, 220/132KV ICTS WITH BAYS To improve the voltage profile and to meet the VALANDI S/S upcoming load. (2009-10) 2) 2 X 50MVA, 220/33KV T/FS WITH BAYS

3) 220KV D/C LINE HARANGUL - VALANDI - 60 KM WITH BAYS 4) 132KV LINE TO NILANGA S/S - 15 KM WITH BAYS

5) 132KV LINE TO UDGIR S/S - 20 KM WITH BAYS

4X132KV BAYS

132 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

9 220KV TULJAPUR S/S OSMANABAD 1) 2X100MVA, 220/132KV ICTS WITH BAYS Tuljapur is considered to meet the increasing loads (2009-10) in Osmanabad district and improve the voltage 2) 220KV D/C FROM SOLAPUR II (BALE) TO TULJAPUR - profile. 50KM 3) 220KV D/C FROM GIRAVALI TO TULJAPUR - 80KM 4) 2X25MVA, 220/33KV T/FS WITH BAYS 5) 132 KV TULAJAPUR-UJANI S/C-25 KM 6) 133 KV TULAJAPUR-NALDURG S/C-25 KM 7) 4X132KV BAYS

10 220KV NANDED 1) 400KV NANDED - NARSI WITH BAYS-60 KMS 220 kV Narsi is considered to meet the increasing NARSI II S/S 2) 2X100MVA, 220/132KV ICTS WITH BAYS loads in Latur District. By constructing this station, (2009-10) the voltage profile improves. 3) 2 X 25MVA, 220/33KV T/FS WITH BAYS 4) 132KV MUKHED-NARSI S/C-30KM 5) 132KV KUNDALWADI-NARSI S/C- 30KM 6) LILO ON 132 KV NARSI - DEGLOOR- 30KM 7) 132KV-220KV NARSI -10KM 8) 8 X 33KV OUTLETS 11 132KV SOYGAON S/S AURANGABAD 1) 2X25MVA, 132/33KV T/FS WITH BAYS Present recorded peak load on Pahur-132kV, (2009-10) 2) 132KV SCDC PAHUR-BULDHANA - 60 KMS WITH BAYS Sillod-132kV S/S, Pishor-132kV are 35MW, 60MW and 30MW respectively. It is anticipated by the 3) 132KV SCDC SILLOD - SOYGAON - 35 KMS WITH BAYS year 2009-10 the load will reach to about 150MW. Hence it is necessary to go in for new 132kV sub- 4) 132KV SOYAGAON - PAHUR SCDC - 14KM WITH BAYS station at Soygaon. The new Soygaon-132kV S/S is proposed in year 2009-10 for reducing loading 5) 8X33KV OUTLETS on Pahur-132kV, Sillod-132kV S/S, and Pishor- 132kV S/S. By the commissioning of this substation, voltage profile of Aurangabd Circle will improve.

NEW SUBSTATION TO ELIMINATE 33 KV LEVEL AT GENERATION SWITCHYARD AT PARLI GEN. 1 132KV PANGRI BEED 1) LILO ON PARLI - TELGAON - 15KM To eliminate 33KV level from GCR Parli. (2009-10) 2X25 MVA,132/33KV 2) 8 X 33KV OUTLETS

ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 132KV LINK LINE JALNA 1) 132KV PADEGAON - PISHOR SCDC LINE - 40KM WITH 132kV Pishor S/S is fed from 132kV Padegaon S/s (2008-09) BAYS with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

2 132KV LINK LINE JALNA 1) 132KV AMBAD - 220KV JALNA SCDC LINE - 29 KM 132kV Ambad S/S is fed from 220kV Jalna S/s (2008-09) GIS BAY AND CABLE with S/c line. Hence to provide uninterrupted 2) supply during planned outages it is necessary to add proposed line. ( GIS bays & cable is proposed due to no space at Ambad & Jalana and ROW problem at Jalana.)

3 132KV LINK LINE AURANGABAD 1) 132KV DEOLAI - 220KV CHITEGAON LINE (STRINGING 132kV Deolai S/S is fed from 132kV Chitegaon S/s (2008-09) ONLY ) - 28.9 KM with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

4 132KV LINK LINE AURANGABAD 1) 132KV GANGAPUR - VAIJAPUR SCDC LINE - 40 KM 132kV Gangapur S/S is fed from 132kV Padegaon (2008-09) S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

5 132KV LINK LINE OSMANABAD 1) 132KV NILANGA - OMERGA SCDC LINE - 31.22KM 132kV Killari S/S is Tapped on 132kV Ujani- (2009-10) Omerga S/c line. Hence to provide alternate supply during planned outages it is necessary to add proposed line considering the anticipated load growth in that region

6 132KV LINK LINE OSMANABAD 1) 132KV DC LINE BHOOM - PARANDA - 20 KM WITH 132kV Bhoom S/S is fed from 132kV Kalamb S/s (2009-10) BAYS with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

133 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 132KV LINK LINE LATUR 1) 132 KV D/C CHAKUR - RENAPUR LINE- 35 KMS. Since the existing 132kV Parli (girwali)-Renapur (2009-10) (ONE CKT WILL BE CONNECTED TO LATUR MIDC S/S { S/c line is critically loaded to an extent of 86 MW. PARTIAL M/C AT LATUR MIDC END} AND ANOTHER TO Hence it is suggested to add proposed line to RENAPUR) reduce the loading of existing line and to meet additional load growth and contingency.

2 132KV LINK LINE AURANGBAD 1) 132 KV DC LINE FROM SAWANGI - HARSOOL -10KM It is anticipated the load will reach to about critical (2009-10) value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

1 132KV LINK LINE JALNA 1) 132KV KHULTABAD - SAVANGI SCDC LINE - 26KM Only single ckt and single source is available at (2008-09) WITH BAYS Sawangi S/S. STRENGTHENING FOR EVACUATION ARRANGEMENT 1 220KV LINK LINE JALNA 1) 220 KV D/C LINE JALNA - CHIKHALI - 75 KM WITH BAYS To have evacuation facility at Paras Generation (2008-09) AUGMENTATION OF S/S BY ADDITION OF T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

1 220 KV PARLI GCR BEED 1) 1X100 MVA, 220/132 KV ICT WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 1 X 132 KV BAYS 2 220KV JALNA S/S JALNA 1) 1 X 200MVA, 220/132KV ICT WITH BAYS To avoid loss of supply in case of outages or (2008-09) 2) 2X132KV BAYS interruptions on any one transformer

3 132 KV KHULTABAD AURANGABAD 1) ADD. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or S/S 2) 33 KV OUTLETS - 4 NOS. interruptions on any one transformer (2008-09) 4 132KV HINGOLI 1) 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or AKHADA-BALAPUR S/S interruptions on any one transformer (2008-09) 2) 4X33KV OUTLETS

5 132 KV PURNA S/S PARBHANI 1) 1 X25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33 KV OUTLET - 4 NOS.

6 132 KV BASMATH S/S PARBHANI 1) 1 X50 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33 KV OUTLET - 6 NOS.

7 132 KV MAJALGAON BEED 1) ADD. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or S/S interruptions on any one transformer (2008-09) 2) 33 KV OUTLETS - 4 NOS. 3) 4 X 33 KV OUTLETS 8 132KV AUSA S/S LATUR 1) ADDL. 1 X50 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33 KV OUTLET - 6 NOS.

9 132KV CHAKUR S/S LATUR 1) ADDL. 1 X25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33 KV OUTLET - 4 NOS.

10 132 KV RENAPUR S/S LATUR 1) ADD. 1 X 50 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) 2) 33 KV OUTLETS - 6 NOS. interruptions on any one transformer

11 132KV NANDED 1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or MUKHED S/S interruptions on any one transformer 2) 4X33KV OUTLETS (2008-09)

12 132KV NANDED 1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or HIMAYATNAGAR S/S interruptions on any one transformer (2008-09) 2) 4X33KV OUTLETS 13 132KV NANDED 1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or DEGLOOR S/S interruptions on any one transformer (2008-09) 2) 4X33KV OUTLETS

14 132KV LATUR MIDC LATUR 1) ADDL. 1 X25 MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, S/S 132/33 - 1 x 12.5 - 12.22 LOAD (2008-09) 2) 33 KV OUTLET - 4 NOS. To avoid loss of supply in case of outages or interruptions on any one transformer

15 132 KV KILLARI S/S LATUR 1) 1 X 25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33KV OUTLETS - 4 NOS.

134 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

16 132KV ARDHAPUR AURANGABAD 1) 1X25 MVA,132/33 KV TF To avoid loss of supply in case of outages or S/STN interruptions on any one transformer 2) 33KV BAY - 04 NOS (2008-09) 17 220 KV PARLI GCR BEED 1) 1X100 MVA, 220/132 KV ICT WITH BAYS The existing transformer capacity available is (2009-10) 220/132 kV, 1X100 MVA and the load reached is 144 MVA To avoid loss of supply in case of outages or interruptions on any one transformer additional transformer is proposed.

18 220 KV CHITEGAON AURANGABAD 1) 1 X 100 MVA, 220/132 KV ICT WITH BAYS The existing transformer capacity available is S/S 220/132 kV, 1X100 MVA and the load reached is (2009-10) 59 MVA.To avoid loss of supply in case of outages or interruptions on any one transformer additional transformer is proposed.

19 132 kV KUNDALWADI Nanded 1) Add. 1 X 25 MVA, 132/33 kV T/F with bays. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV bays MVA. And the load reached is 16 MVATo avoid loss of supply in case of outages or interruptions on transformer. 20 132 kV RAIMOHA Beed 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. And the load reached is 21 MVATo avoid loss of supply in case of outages or interruptions on transformer.

21 132 kV GHANSAWANGI Jalna 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. And the load reached is 6 MVATo avoid loss of supply in case of outages or interruptions on transformer.

22 132 kV KURUNDA Hingoli 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 2 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. And the load reached is 26 MVATo avoid loss of supply in case of outages or interruptions on transformer.

23 132 kV NARSI Nanded 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25, 1 x (2009-10) 2) 4 X 33 kV out lets 16 MVA. And the load reached is 23 MVATo avoid loss of supply in case of outages or interruptions on transformer.

24 132 kV UMRI Nanded 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. And the load reached is 20 MVATo avoid loss of supply in case of outages or interruptions on transformer.

25 132 kV BASMATH Parbhani 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. To avoid loss of supply in case of outages or interruptions on transformer. 26 132 kV DEOLAI Aurangabad 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (SATARA) 2) 4 X 33 kV out lets MVA. And the load reached is 20 MVATo avoid (2009-10) loss of supply in case of outages or interruptions on transformer.

27 132 kV KAIJ * Beed 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. And the load reached is14 MVATo avoid loss of supply in case of outages or interruptions on transformer.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER 1 400KV S/S - AURANGABAD 1) ADDL. 1 X 500 MVA 400/220 KV, ICT WITH BAYS AT - Existing transformer capacity available in AURANGABAD, PARLI BEED AURANGABAD, PARLI S/S Aurangabad S/s is,400/220 - 2 x 315 - 244 & S/S Existing transformer capacity available in Parli S/s (2008-09) is,400/220 - 2 x 315 - 316 Considering the maximum load reach on the 2 220 KV JALNA S/S JALNA 1) 1 X 25 MVA, 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 1 x 50 - 41 load 132/33 - 1 x 25 - 20 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the 2) 33KV OUTLETS - 4 NOS. transformer other transformer should take care of existing load so as to avoid load shedding.

3 220 KV Osmanabad S/S OSMNABAD 1) 1 X 100 MVA, 220/132 KV ICT WITH BAYS To feed nearby 132 kv S/s on 132 kv level. (2008-09)

2) 132KV BAYS - 2 NOS.

135 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

4 132KV JALNA 1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS New S/s MANTHA S/S (2008-09)

2) 4X33KV OUTLETS 5 132KV JALNA 1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS New S/s GHANSAWANGI S/S (2008-09) 2) 4X33KV OUTLETS

6 132 KV KINWAT S/S NANDED 1) ADD. 1 X 25 MVA, 132/33 KV T/F WITH BAYS To Eliminate 66 KV level at Kinwat S/s. (2008-09) 2) 33KV OUTLETS - 4 NOS.

7 220 KV HARANGUL S/S LATUR 1) 1 X 200 MVA, 220/132 KV ICT WITH BAYS The existing transformer capacity available is (2009-10) 220/132 kV, 2X200 MVA and the load reached is 181MVATo avoid loss of supply in case of outages or interruptions on any one transformer additional transformer is proposed.

8 220 kV OSMANABAD Osmanabad 1) Add1 X 25 MVA , 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 50MVA. And the load reached is 49 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load.

9 220 kV MURUD Latur 1) Add 1 X 50 MVA, 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X (2009-10) 2) 6 X 33 kV out lets. 25 & 1 X 50 MVA and load is 50 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

10 220 kV JALNA-II Jalna 1) Add 1 X 50 MVA, 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 6 X 33 kV out lets. 50 MVA and load is 61 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

11 132 kV AMBAD (JALNA) Jalna 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 25 MVA and load is 36 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

12 132 kV ASHTI (BEED) Beed 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is,2 X (2009-10) 2) 4 X 33 kV out lets. 25 MVA and load is 30 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

13 132 kV BEED Beed 1) Add 1 X 50 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X (2009-10) 2) 6 X 33 kV out lets. 25 & 1 X 50 MVA and load is 47 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

14 132 kV GANGAPUR Aurangabad 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is, 1 (2009-10) 2) 4 X 33 kV out lets. X 25, 1 x 16 MVA and load is 24 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

136 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

15 132 kV OMERGA Osmanabad 1) Add 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X (2009-10) 2) 4 X 33 kV out lets. 25, 1 x 16 MVA and load is 30 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

16 132 kV SILLOD Aurangabad 1) Add1 X 50 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 6 X 33 kV out lets. 25 & 1 X 50 MVA and load is 54 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

17 132 kV TAMSA Nanded 1) Add 1 X 25 MVA A, 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X (2009-10) 2) 4 X 33 kV out lets. 25 & 1 X 12.5 MVA. And the load reached is 24 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load..

18 132 kV ELICHPUR Aurangabad 1) Add 1 X 25 MVA A, 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 25 MVA. And the load reached is 35 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load..

19 132 kV PARBHANI Parbhani 1) Add 1 X 50 , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X (2009-10) 2) 4 X 33 kV out lets. 50 & 1 X 25 MVA. And the load reached is 45 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load..

20 132 kV GEORAI Beed 1) Add1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 25MVA. And the load reached is 24 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load..

21 132 kV PISHOR Aurangabad 1) Add1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X (2009-10) 2) 4 X 33 kV out lets. 25MVA. And the load reached is 13 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load..

22 132 kV JALNA-I Jalna 1) Add1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 25MVA. And the load reached is 24 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load..

23 132 kV NANDED-I Nanded 1) Add1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 50MVA. And the load reached is 53 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load..

24 132 kV HARSOOL Aurangabad 1) Add 1 X 50 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 6 X 33 kV out lets. 50 MVA and load is 47 MVA. Considering thr maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

137 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

AUGMENTATION OF S/S BY REPLACEMENT OF T/F 1 220 KV PADEGAON S/S AURANGABAD 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/132 - 4 x 100 - 282 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

2 220 KV MURUD S/S LATUR 1) 1 X (50-25) MVA, 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 220/33 - 1 x 25 - 22.33 220/33 - 2 x 50 - 58.20 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load 2) 33 KV OUTLET - 2 NOS. shedding.

3 220 KV BEED S/S BEED 1) 1X (200-100) 220/132 KV ICTS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,220/132 - 2 x 100 - 147 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should 2) 132KV BAY - 4 NO. take care of existing load so as to avoid load shedding. 4 220KV NANDED II NANDED 1) 2X(50-25) MVA,132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s (WAGHALA) S/S is,132/33 - 2 x 25 - 36 load (2008-09) Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load 2) 33 KV OUTLETS - 4 NOS. shedding.

5 220KV NANDED II S/S NANDED 1) REP.(200-80)MVA, 220/132 KV T/F WITH BAYS Existing transformer capacity available in S/s (WAGHALA) is,220/132 - 1 x 200 - 120 load (2008-09) 220/132 - 1 x 150 - 83 load 220/132 - 1 x 80 - 57 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load 2) 132KV BAYS - 2 NOS shedding.

6 132 KV KALAMB S/S OSMANABAD 1) 2 X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 43.1 load 2) 33 KV OUTLETS - 8 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 7 132 KV BEED S/S BEED 1) 2X(50-25) 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) 2) 33 KV OUTLETS - 8 NOS. is,132/33 - 2 x 25 - 43.82 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

8 132 KV OMERGA S/S LATUR 1) 1X(25-16) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s (2008-09) 1x (50-25)MVA,132/33kv is,132/33 - 1 x 25 - 19 load 132/33 - 1 x 16 - 12 load 2) 2X33 KV OUTLETS Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

3) 8 X 33KV OUTLETS

9 132 KV JALNA MIDC JALNA 1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s S/S is,132/33 - 2 x 25 - 44 load (2008-09) Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should 2) 33 KV OUTLET - 4 NOS. take care of existing load so as to avoid load shedding.

138 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

10 132KV CHIKALTHANA AURANGABAD 1) 1X (50-25)MVA, 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s S/S is,132/33 - 2 x 25 - 41load (2008-09) Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should 2) 33 KV OUTLET - 4 NOS. take care of existing load so as to avoid load shedding.

11 132 KV PAITHAN S/S AURANGABAD 1) 1X(50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 30 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should 2) 8X33KV OUTLETS take care of existing load so as to avoid load shedding.

12 132 KV KANNAD S/S AURANGABAD 1) 1 X (50-12.5) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 -2 x 12.5 - 13 load 132/33 - 1 x 10 - 5 load Considering the maximum load reach on the transformer, in event of interruption/outage on any 2) 33 KV OUTLET - 4 NOS. one of the transformer other transformer should take care of existing load so as to avoid load shedding.

13 132 KV VAIJAPUR S/S AURANGABAD 1) 1 X (50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 40 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should 2) 33 KV OUTLET - 8 NOS. take care of existing load so as to avoid load shedding.

14 132KV KURUNDA S/S HINGOLI 1) 2X(50-25)MVA, 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 29 load Considering the maximum load reach on the transformer, in event of interruption/outage on any 2) 8 X 33KV OUTLETS one of the transformer other transformer should take care of existing load so as to avoid load shedding.

15 132 KV JINTOOR S/S PARBHANI 1) 1 X (50-25/12.5) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 1 x 25 - 15 load 132/33 - 1 x 10 - 8 load 2) 33 KV OUTLET - 4 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

16 132KV WALUJ AURANGABAD 1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 37 2) 33 KV OUTLET - 4 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

17 132 KV PARLI S/S BEED 1) 2X(50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 44.4 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

139 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

18 132 KV LATUR & LATUR 1) 1X(25-16) MVA, 132/11 KV T/F WITH BAYS AT LATUR Existing transformer capacity available in S/s LATUR MIDC S/S MIDC S/S is,Latur MIDC 132/11 - 1 x 16 - 12.11 (2008-09) Latur-132/11 -2 x 10 - 16.8 2) 1X(25-10) MVA, 132/11 KV T/F WITH BAYS AT LATUR Considering the maximum load reach on the S/S transformer, in event of interruption/outage on any 3) 4X11KV OUTLETS one of the transformer other transformer should take care of existing load so as to avoid load shedding.

19 132 KV NILANGA S/S LATUR 1) REP 1X(50-25) 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 -2 x 25 - 44 load 2) 33 KV OUTLETS - 8 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 20 132 KV JALNA (I) S/S JALNA 1) 1X(50-25) MVA,132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 41load 2) 33 KV OUTLETS - 8 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

21 132 KV AMBAD S/S JALNA 1) 1X(50-25) MVA,132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 -45 2) 33 KV OUTLETS - 8 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

22 132 KV PARTUR S/S JALNA 1) 2 X (50-25/12.5) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 45 2) 33 KV OUTLET - 7 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

23 132 KV GANGAPUR AURANGABAD 1) 1 X (25-16) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s S/S is,132/33 - 1 x 25 - 17MW,132/33 - 1 x 16 - (2008-09) 12MWConsidering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 2) 33 KV OUTLET - 2 NOS.

24 132 KV ASHTI S/S BEED 1) 1X(50-25) MVA,132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 44 MW Considering the maximum load reach on the transformer, in event 2) 33 KV OUTLETS - 4 NOS. of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

25 132 KV NARSI S/S NANDED 1) 1 X (50-16) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x 25 - 16.5 132/33 - 1 x 16 - 10.2 2) 33 KV OUTLET - 2 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

26 132 KV TAMSA S/S NANDED 1) 1 X (25-12.5) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x 25 - 23 2) 33 KV OUTLET - 2 NOS. 132/33 - 1 x 12.5 - 10 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

140 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

27 132 KV GEORAI S/S BEED 1) 1 X (25-12.5) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x 25 - 18.55 132/33 - 1 x 12.5 - 9.33 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 2) 33 KV OUTLET - 2 NOS.

28 132 KV TELGAON S/S BEED 1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 45MVA Considering the maximum load reach on the transformer, in event 2) 33 KV OUTLET - 2 NOS. of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

29 132 KV UJANI S/S OSMANABAD 1) 1 X (25-10) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s (2008-09) 2) 33 KV OUTLET - 2 NOS. is,132/33 - 1 x 25 - 15.5 , 132/33 - 1 x 10 - 8.22 .Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

30 132 KV PARBHANI S/S PARBHANI 1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 2) 1X(200-100)MVA, 220/132KV ICT 132/33 - 1 x 25 - 15.2 3) 33 KV OUTLET - 4 NOS. 132/33 - 1 x 50 - 30.4 220/132- 2 x 100 - 143 Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

31 132 KV LATUR MIDC LATUR 1) 1 X (25-12.5) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, S/S 132/33 - 1 x 12.5 - 12.22 (2008-09) Additional transformer of 132/33 kV 25 MVA is being added during the year 2007-08 to have redundancy during outage/interuption to cater the load.So to take care of anticipated load growth replcement is required.

32 132 KV RENAPUR S/S LATUR 1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x 25 - 22.3 Additional transformer of 132/33 kV 25 MVA is being added during the year 2008-09 to have redundancy during outage/interuption to cater the load.So to take care of anticipated load growth replacement is required.

33 132 KV LATUR (K) S/S LATUR 1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 32.22 Considering the maximum load reach on the 2) 33 KV OUTLET - 4 NOS. transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

34 132 KV UDGIR S/S LATUR 1) 1X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 38.66 2) 33 KV OUTLET - 4 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

35 132 KV KAIJ BEED 1) 1X(50-25)MVA ,132/33KV TF 'S WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer

36 132KV BHOOM AURANGABAD 1) 1X(50-25)MVA ,132/33KV TF'S WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer

141 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

37 132KV NALDURG LATUR 1) 1X(50-25)MVA ,132/33KV TF'S WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer

38 220 KV BEED S/S BEED 1) 1X (200-100) 220/132 KV ICTS WITH BAYS Existing transformer capacity available in S/s is (2009-10) 220/132kV, 2 x 100 MVA. And the load reached is 122 MVA. The transformer is replaced to meet the anticipated load growth.

39 220 KV PADEGAON S/S AURANGABAD 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s is (2009-10) 220/132kV,4 X 100 MVA. The load reached is 233 mVA.The transformers are replaced to meet the anticipated load growth.

40 220 KV PARLI BEED 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s is GIRAVALI 220/132kV,3 X 100 MVA. The load reached is 144 (2009-10) MVA.The transformers are replaced to meet the anticipated load growth.

41 220 kV NANDED-II Nanded 1) 1 X (50-25) MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1X (WAGHALA) 2) 6 X 33 kV out lets. 50MVA and load is 36 MVA. Considering the (2009-10) maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load growth

42 220 kV PARLI GIRWALI Beed 1) 1 X (50-25) MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 25 MVA and load is 26 MVA. The transformer is replaced to meet anticipated load growth

43 132 kV HINGOLI Hingoli 1) Add 1 X (50-25) MVA , 132/33 kV T/F 4 Existing transformer capacity available in S/s is 1 X (2009-10) 2) X 33 kV out lets. 25,1 X 50 MVA and load is 32 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load growth

44 132 kV WALUJ Aurangabad 1) Add 1 X (50-25) MVA , 132/33 kV T/F 4 Existing transformer capacity available in S/s is 1 X (2009-10) 2) X 33 kV out lets. 25,1 X 50 MVA and load is 32 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load growth

45 132 kV CHIKHALTHANA Aurangabad 1) Add 1 X (50-25) MVA , 132/33 kV T/F 4 Existing transformer capacity available in S/s is 2 X (2009-10) 2) X 33 kV out lets. 25 MVA and load is 29.5 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load growth

46 132 kV GANGKHED* Parbhani 1) Add 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 2 X 33 kV out lets. 25 MVA and load is 33 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load growth

47 132 kV JALNA MIDC Jalna 1) Add 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 25 MVA and load is 34 MVA. The transformer is replaced to meet anticipated load growth

48 132 kV KANNAD Aurangabad 1) 1 X (25-10) MVA, 132/33 kV T/F with bays Existing transformer capacity available in S/s is 2 X (2009-10) 2) 2 X 33 kV out lets. 12.5 MVA and load is 12 MVA. The transformer is replaced to meet anticipated load growth

49 132 kV SILLOD * Aurangabad 1) 1 X (50-25) MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 25 MVA and load is 50 MVA. The transformer is replaced to meet anticipated load growth

142 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

50 132 kV UDGIR Latur 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 4 X 33 kV out lets. 25 MVA and load is 24 MVA. The transformer is replaced to meet anticipated load growth

51 132 kV PAITHAN Aurangabad 1) 1 X (50-25) MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2009-10) 2) 2 X 33 kV out lets. 25 MVA and load is 36 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load growth

NEW SCHEMES 1 220KV DEOGAON AURANGABAD 1) 2X200MVA, 220/132KV ICTS WITH BAYS Deogaon Rangari-220kV S/S is considered to RANGARI S/S 2) 2 X 50MVA, 220/33KV T/FS WITH BAYS meet the load growth in Aurangabd Circle. (2010-11) 3) LILO ON 220 KV BABHALESHWAR - WALUJ LINE AT DEOGAON RANGARI - 20 KMS 4) 132KV D/C LINE FROM 220 KV DEOGAON RANGARI (ONE CKT WILL BE CONNECTED TO KANNAD AND ANOTHER TO PISHOR) {PARTLY D/C AND PARTLY SCDC} - 30 KM 5) 132KV VAIJAPUR- DEOGAON-RANGARI D/C LINE- 35KM 6) 132KV GANGAPUR - DEOGAON-RANGARI D/C LINE- 40KM 2 220KV JALNA 1) 220KV SAWANGI - BHOKARDHAN D/C LINE - 60 KMS Present recorded loading on Sillod-132kv, BHOKARDHAN S/S Jafrabad-132kV, and Pisor-132kV S/S are 45MW, (2010-11) 2) 220KV CHIKHALI - BHOKARDHAN D/C LINE - 60 KMS 15MW, and 25MW respectively. It is anticipated by the year 2010-11 the load will reach to about 110MW. Hence it is necessary to go in for new 220kV sub-station at Bhokardan. 3) 132KV BHOKARDHAN-SILLOD D/C LINE - 20 KMS 4) 2X100MVA, 220/132KV ICTS WITH BAYS 5) 2 X 50MVA, 220/33KV T/FS WITH BAYS 6) 4X132KV BAYS 7) 132KV LINE - 40 KM WITH BAYS 8) LILO ON 132KV RAJUR - JAFRABAD FOR BHOKARDHAN-10 KM 3 132KV LATUR 1) 132KV LINE FROM 220 KV VALANDI - PANCHINCHOLI Present recorded peak load on Omerga-132kV PANCHINCHOLI S/S D/C LINE - 20KMS and Latur 132kV is 40MW and 50 MW (2010-11) 2) 2 X 25MVA, 132/33KV T/F'S WITH BAYS respectively. It is anticipated by the year 2010-11 3) 8X33KV OUTLETS the load will reach to about 120 MW. Hence it is necessary to go in for new 132kV sub-station at Panchincholi. The new substation Panchincholi- 132kV is proposed in year 2010-11 for reducing loading on 132kV Nilanga and 132 Latur S/S.

4 132KV HINGOLI 1) 132KV HINGOLI - SHENGAON D/C LINE - 30KMS Sengaon-132kV S/S is considered to meet the SHENGAON S/S 2) 2 X 25MVA, 132/33KV T/F'S WITH BAYS load growth in Hingoli District. (2010-11) 3) 8X33KV OUTLETS 5 132KV PARBHANI 1) 132KV GANGAKHED - SONPETH D/C LINE - 40 KMS Present recorded peak load on Majalgaon-132kV, SONPETH S/S WITH BAYS Telgaon-132kV and Pathari 30 MW, 30 MW and (2010-11) 2) 2 X 25MVA, 132/33KV T/F'S WITH BAYS 20MW. It is anticipated by the year 2010-11 the 3) 8X33KV OUTLETS load will reach to about 105MW. The new substation Sonpeth –132kV S/S is proposed in year 2010-11 for reducing loading on Majalgaon- 132kV, Telgaon-132kV and Pathari 132kV.

6 220KV BHOKAR S/S NANDED 1) 220KV D/C LINE FROM 400KV NANDED - 40 KM WITH Present recorded peak on Umerkhed, Tamsa and (2011-12) BAYS Kinwat 132kV S/S are 35, 36 and 20 MW 2) 2X100MVA, 220/132KV ICTS WITH BAYS respectively. It is anticipated by the year 2011-12, 3) 2X25MVA, 220/33KV T/FS WITH BAYS the load will reach about 97MW. Hence it is 4) 132 KV BHOKAR-HIMAYATNAGAR S/C 30 KM necessary to go in for new 220kV sub-station at 5) 132 KV BHOKAR-TAMASA S/C 16 KM Bhokar. 6) 8X33KV OUTLETS 7 220KV PARBHANI 1) 132KV LINE FROM 220KV SHELU - PARTUR D/C LINE - This substation will help to meet the increased SHELU S/S 30KMS WITH BAYS load in Jalna & Parbhani district. (2011-12) 2) 2X100MVA, 220/132KV ICTS WITH BAYS 3) 132KV LINE FROM 220KV SHELU - PATHRI D/C LINE - 22KMS WITH BAYS 4) 220KV LINE FROM 220KV PARBHANI - 220KV SHELU S/STN -40 KM

143 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

8 220 KV AURANGABAD 1) LILO OF 220KV SAWANGI - BHOKARDAN AT This substation will help to meet the increased PHULAMBRI S/S PHULAMBRI D/C LINE - 25KMS WITH BAYS load in Aurangabad district. (2011-12) 2) 132 KV PHULAMBRI-RAJUR D/C WITH BAYS - 25 KM

3) 2 X 100MVA, 220/132KV ICTS WITH BAYS 4) 2 X 50 MVA, 220/33KV T/FS WITH BAYS 5) 12 X 33KV OUTLETS 9 220KV NANDED 1) 220KV D/C LINE FROM 400KV NANDED - KRISHNOOR - Krishnoor is considered to cater the increasing KRISHNOOR S/S 30 KMS WITH BAYS loads in Nanded District. (2011-12) 2) 2X200MVA, 220/132KV ICTS WITH BAYS 3) 2X50MVA, 220/33KV T/FS WITH BAYS 4) 132 KV KRISHNOOR - UMRI S/C-15 KM 5) 12 X 33KV OUTLETS 10 220KV JALKOT S/S LATUR 1) 220KV D/C LINE FROM 400KV NANDED TO JALKOT - JALKOT 220kV S/S is considered to meet the load (2011-12) 65 KMS growth and for reliable operation in Parli circle and 2) 2X100MVA, 220/132KV T/F WITH BAY also to improve the voltage profile. 3) 132KV SCDC LINE TO DEGLOOR S/S - 20 KM 4) 132KV SCDC LINE TO AHAMEDPUR S/S - 20 KM 4) 132KV OUTLETS - 4 NOS 11 220KV PACHOD S/S AURANGABAD 1) 220KV FROM CHITEGAON - PACHOD D/C WITH BAYS- This S/Stn will help to meet the increased load in (2011-12) 25KM Aurangabad district. 2) 132KV AMBAD - PACHOD D/C -30KM 3) 132KV GHANSAWANGI - PACHOD D/C- 30KM 4) LILO ON PAITHAN-GEORAI AT PACHOD- 20KM 5) 2X100MVA, 220/132KV T/F WITH BAY 6) 132KV OUTLETS - 4 NOS 12 400/220 KV AURANGABAD 1) 2 X 315 MVA, 400/220KV ICT'S WITH BAYS , Evacuation of Power and to improve voltage AURANGABAD - II 1 X 105 MVA , 400/ 220 KV 1 PHASE ICT SPARE profile. S/S(PANDHARI 2) LILO ON BOTH CKT OF 400 KV DC BHUSAWAL - II - PIMPALGAON) AURANGABAD - 15 KM (2012-13) 3) 220KV D/C LINE TO PADEGAON S/S -15 KMS WITH BAYS 13 765KV AURANGABAD BY PGCIL 400 KVD/C LINE FOR AURANGABAD-II S/S Evacuation of Power. AURANGABAD S/S FROM 765 KV AURANGABAD S/S (2012-13)

14 400/220KV OSMANABAD 1) 2X500 MVA, 400/220 KV ICT'S WITH BAYS To reduce the over loading of the existing 220 kV OSMANABAD S/S 2) LILO ON 400 KV PARLI (PG) - SOUTH SOLAPUR (PG) network in Osmanabad area.To improve the (2013-14) S/C LINE - 10 KM voltage profile and to meet the upcoming demand. 3) LILO ON 220KV MURUD - SOLAPUR (BALE) AT OSMANABAD - 10KM 4) 220KV OSMANABAD-II - BARSHI S/C LINE -10KM 5) INTER LINK D/C LINES BETWEEN EXISTING 220 KV OSMANABAD - 400 KV OSMANABAD - 10KM 6) 220KV OSMANABAD-II - TULJAPUR D/C LINE - 40KM

66KV LEVEL ELIMINATION

1 ELIMINATION OF 66 KV NANDED A 66 KV KINWAT A.132 KV Kinwat s/stn is in existance.To eliminate LEVEL AT 66/11 KV at 66 kV Kinwat new 33 /11kv s/stn along AURANGABAD 66/33 1X10MVA,1X5MVA , 66/11 1X5MVA with 2x10 MVA T/F and 33 kv line from 132 kv Kinwat s/stn is to be established by Discom at Kinwat. After complition of above said work 66/11kv Kinwat s/stn will be absolate.

HINGOLI B 66KV HINGOLI B.132 KV Hingoli s/stn is in existance.To eliminate 66/33 2X10MVA, 66/11 1X10MVA 66/11 KV at 66 kV Hingoli a new 33 /11kv s/stn alongwith 2x10 MVA T/F and 33 kv line from 132 kv Hingoli s/stn is to be established by Discom at Hingoli. After complition of above said work 66/11kv Hingoli s/stn will be absolate.

YAVATMAL C 66 KV PUSAD C.220 KV Pusad s/stn is in existance.To eliminate 66/33 KV & 66/11 KV T/Fs at Pusad s/stn, 2 nos of new 33 kv s/stn alongwith 2x10 MVA T/F each and 33 kv line from 220 kv Pusad s/stn considering load centre are to be established by 66/33 KV 2 x10MVA , 66/11 KV 2X10 MVA Discom at Pusad. After complition of above said work 66/33kv & 66/11 KV T/Fs at Pusad s/stn will be absolate.

YAVATMAL D. 220/66kv PUSAD D.On getting the above work done at Sr.No. A, B & C the 220/66 kV 2X50MVA T/F at 220/66KV 2x50MVA, 220 kv Pusad will be absolate.

144 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE As per the methodology stipulated in the guideline of State Grid Code Regulation No. 9.4 The intrastate transmission system shall be capable of withstanding the loss of most severe single infeed without loss of stability. 1 132KV LINK LINE BEED 1) 132KV PARANDA - KALAMB DC LINE - 66 KM 132kV Kalamb S/S is fed from 132kV Kaij S/s with (2010-11) S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

2 132KV LINK LINE BEED 1) 132KV ASHTI - RAIMOHA SCDC LINE - 40 KM 132kV Ashti S/S is fed from 220kV Ahemadnagar (2010-11) S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

3 132KV LINK LINE LATUR 1) 132KV AHMEDPUR - CHAKUR SCDC LINE - 22 KM 132kV Chakur S/S is Tapped on 132kV Harangul- (2010-11) Udgir S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

4 132KV LINK LINE OSMANABAD/ 1) 2ND CIRCUIT STRINGING OF 132 KV SCDC LINE FROM Strengthening for wind power evacuation (2010-11) AHMEDNAGAR PARANDA - KHARDA - 30 KM

5 132KV LINK LINE LATUR 1) 220KV JALKOT - UDGIR SCDC LINE - 25 KM 132kV Udgir S/S is fed from 220kV Harangul S/s (2010-11) with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

6 132KV LINK LINE LATUR 1) 220KV JALKOT - DEGLOOR SCDC LINE - 27 KM 132kV Degloor S/S is fed from 132kV Narsi S/s (2010-11) with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

7 132KV LINK LINE LATUR 1) 220KV JALKOT - AHMEDPUR SCDC LINE - 29 KM 132kV Ahemadpur S/S is Tapped on 132kV (2010-11) Girwali-Renapur S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

8 132KV LINK LINE PARBHANI 1) 132KV PURNA - BASMATH SCDC LINE - 21 KM 132kV Purna S/S is fed from 132kV Parbhani S/s (2010-11) with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

9 132KV LINK LINE NANDED 1) 132KV NANDED - UMRI 2ND CKT STRINGING - 31.73 KM 132kV Umri S/S is fed from 132kV Nanded S/s (2011-12) with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

10 132KV LINK LINE LATUR 1) 132KV UJANI - KILLARI SCDC LINE - 25 KM 132kV Killari S/S is Tapped on 132kV Ujani- (2011-12) Omerga S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 11 132KV LINK LINE JALNA 1) 132KV MAJALGAON - PATHRI SCDC LINE - 35KM To provide uninterrupted supply during planned (2011-12) outages it is necessary to add proposed line 12 132KV LINK LINE JALNA 1) 132KV DUSARBID - MANTHA SCDC LINE - 36 KM To provide uninterrupted supply during planned (2011-12) outages it is necessary to add proposed line

13 132KV LINK LINE JALNA 1) 132KV MAJALGAON - GEORAI SCDC LINE - 25KM To provide uninterrupted supply during planned (2012-13) outages it is necessary to add proposed line

14 132KV LINK LINE PARBHANI 1) 132 KV HIMAYATNAGAR - UMARKHED LINE 2ND CKT 132kV Himayatnagar S/S is fed from 132kV (2012-13) STRINGING - 28.6 KM Umarkhed S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

15 132KV LINK LINE LATUR 1) 132 KV LILO ON HARANGUL -UJANI SCDC LINE FOR 132kV Ausa S/S is Tapped on 132kV Harngul- (2012-13) AUSA- 43KM Ujani S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

145 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 220 KV LINK LINE AURANGABAD 1) 220 KV SHENDRA -SAVANGI SCDC LINE - 25KM Since the existing 220kV Shendra-Savangi line is (2010-11) critically loaded to an extent of 86 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. 2 132KV LINK LINE BEED / 1) LILO ON 132 KV PARLI - PARBHANI AT GANGAKHED Since the existing 132kV Gangakhed-Parli line is (2010-11) AHMEDNAGAR D/C - 15KM getting loaded to an extent of 52 MW during Non- coinsident peak condition. It is anticipated the load will reach to about critical value by the year 2011- 12. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency.

3 132KV LINK LINE BEED/ 1) 132KV SCDC LINE FROM RAIMOHA-PATHARDI - It is anticipated the load will reach to about critical (2010-11) AHMEDNAGAR 10KM value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. 4 132KV LINK LINE BEED 1) 132KV SCDC LINE FROM PATODA - KHARDA - It is anticipated the load will reach to about critical (2010-11) 15KM value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. 5 132KV LINK LINE BEED 1) 132KV SCDC LINE FROM PATODA - RAIMOHA - 12KM It is anticipated the load will reach to about critical (2010-11) value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. 6 132KV LINK LINE BEED 1) 132KV BEED - GEORAI LINE 2ND CKT STRINGING - Since the existing 132kV Beed - Georai line is (2012-13) 36KM loaded to an extent of 120 MW during Non- Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

7 132KV LINK LINE JALNA 1) 132KV SCDC LINE FROM 220KV PADEGAON- It is anticipated the load will reach to about critical (2012-13) HARSOOL - 15KM value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. 8 220KV LINK LINE AURANGABAD 1) 220KV D/C LINE FROM 400KV WALUJ TO SAWANGI - It is anticipated the load will reach to about critical (2012-13) 20KMS value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

9 132KV LINK LINE AURANGABAD 1) 132 KV D/C LINE FROM 220 KV PADEGAON TO It is anticipated the load will reach to about critical (2012-13) SAWANGI - 20KM value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

10 132KV LINK LINE BEED 1) CONVERSION OF TAP TO LILO OF 132KV PARLI - It is anticipated the load will reach to about critical (2012-13) RENAPUR LINE AT AHEMADPUR S/S BY 2ND CKT value in future. Hence it is necessary to propose STRINGING OF EXISTING AHEMADPUR LINE - 45KMS additional line to meet additional load growth and contingency.

11 220KV LINK LINE AURANGABAD 1) 220KV D/C LINE FROM 400KV BHUSAWAL TO CHIKHALI It is anticipated the load will reach to about critical (2012-13) - 70KMS value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

12 132KV LINK LINE AURANGBAD 1) 132KV LILO ON 2ND CIRCUIT PADEGAON - PAITHAN AT Since the existing 132kV Padegaon - Harsool 3 (2013-14) 132KV CHITEGAON - 10KM ckts are loaded to an extent of 154 MW during Non- Coinsident peak condition. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

13 132KV LINK LINE AURANGBAD 1) LILO OF 132KV PADEGAON- SAWANGI - BOTH CIRCUIT It is anticipated the load will reach to about critical (2013-14) AT CHIKHALTHANE- 10KM. value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

146 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

14 132KV LINK LINE JALNA 1) 132KV SCDC FROM 220 KV CHIKHALI TO JAFRABAD - It is anticipated the load will reach to about critical (2013-14) 40 KM value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency.

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE 1 220 KV LINK LINE BEED /LATUR/ 1) 220KV GIRAVALI-HARANGOOL-MURUD SCDC LINE-55 For System strengthning (2010-11) OSMANABAD KM

2 132KV LINK LINE HINGOLI 1) 132KV AKHADA BALAPUR - 220KV HINGOLI SCDC LINE - Linking to 132 kV AkhadaBalapur S/S (2010-11) 25 KM

3 132KV LINK LINE LATUR 1) 220KV VALANDI - UDGIR SCDC LINE - 35 KM Linking to Proposed 220 kV Valandi S/s (2010-11)

4 132KV LINK LINE LATUR 1) 132KV HARANGUL - LATUR (MIDC) SCDC LINE - 60 KM For System strengthning (2010-11)

5 132 KV LINK LINE AURANGABAD - 1) 132KV KHARDA -ASHTI D/C LINE - 35 KM Strengthening for wind power evacuation (2010- 11) AHMEDNAGAR

6 132KV LINK LINE LATUR 1) 132KV NILANGA - PANCHINCHOLI SCDC LINE - 20 KMS Alternate source for proposed 132 kV (2011-12) Panchincholi S/Stn. 7 132 KV LINK LINE BEED 1) 132KV PANGRI -SONPETH D/C LINE - 15 KMS ALTERNATE SOURCE FOR PROPOSED 132 KV (2012- 13) PANGRI S/S 8 220KV LINK LINE JALNA 1) 220KV JALNA - SHELU D/C LINE - 70 KMS ALTERNATE SOURCE FOR PROPOSED 220 KV (2013-14) SHELU S/S 9 220KV LINK LINE BEED 1) 220KV BEED - PACHOD D/C LINE - 70 KMS ALTERNATE SOURCE FOR PROPOSED 220 KV (2013-14) PACHOD S/S 10 132KV LINK LINE AURANGABAD 1) 132KV SCDC LINE FROM 220 KV PHULAMBRI TO ALTERNATE SOURCE FOR PROPOSED 220 KV (2013-14) PISHOR - 10 KMS PHULAMBRI S/S 11 132KV LINK LINE NANDED 1) 132KV SCDC LINE FROM 220 KV KRISHNOOR TO ALTERNATE SOURCE FOR PROPOSED 220 KV (2013-14) PURNA - 35 KMS KRISHNOOR S/S 12 132KV LINK LINE NANDED 1) 132KV SCDC LINE FROM 220 KV KRISHNOOR TO ALTERNATE SOURCE FOR PROPOSED 220 KV (2013-14) KANDHAR - 30 KMS KRISHNOOR S/S 13 220KV LINK LINE NANDED 1) 220KVMALEGAON (WASHIM) - HINGOLI D/C LINE - 40 ALTERNATE SOURCE FOR PROPOSED 220 KV (2014-15) KMS HINGOLI S/S AUGMENTATION OF S/S BY ADDITION OF ICT AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE ICT IS AVAILABLE 1 132 kV DEOLAI Aurangabad 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (SATARA) 2) 4 X 33 kV out lets MVA. And the load reached is20 MVATo avoid loss (2011-12) of supply in case of outages or interruptions on transformer. AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER 1 220 KV PARBHANI S/S PARBHANI 1) 1 X 100 MVA, 220/132 KV ICT WITH BAYS The existing transformer capacity available is (2010-11) 220/132 kV, 2X100 MVA and the load reached is 136MVA.To avoid loss of supply in case of outages or interruptions on any one transformer additional transformer is proposed. 2 220 kV BEED Beed 1) Add 1 X 50 MVA, 220/33 kV T/F with bays. Creation of new 33kV level to meet the anticipated (2010-11) 2) 6 X 33 kV out lets. load growth. 3 400 kV WALUJ Aurangabad 1) Add 1 X 50 MVA , 220/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 (2011-12) 2) 6 X 33 kV out lets. X 50 MVA. And the load reached is 42 MVA Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 4 220 kV BEED Beed 1) Add 1 X 50 MVA, 220/33 kV T/F with bays. To meet the anticipated load growth. (2011-12) 2) 6 X 33 kV out lets. 5 132 kV LATUR Latur 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X (2012-13) 2) 4 X 33 kV out lets. 25 & 1 X 20 MVA and load is18 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

6 132 kV RENAPUR Latur 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2012-13) 2) 4 X 33 kV out lets. 25 MVA and load is 22 MVA. Considerig the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

147 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME SUBSTATION

AUGMENTATION OF S/S BY REPLACEMENT OF T/F

1 220 KV BEED S/S BEED 1) 1X (200-100) 220/132 KV ICTS WITH BAYS Existing transformer capacity available in S/s is (2010-11) 220/132kV, 1 x 100 MVA and 1X 200 MVA. The load reached is 132 MVA. The transformer is replaced to meet the anticipated load growth.

2 220 KV PADEGAON S/S AURANGABAD 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available will be (2010-11) 220/132kV,3 X 100 MVA and 1 X 200 MVA.. The load will reached 262 MVA.The transformers are replaced to meet the anticipated load growth.

3 220 KV PARLI BEED 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s will GIRAVALI be 220/132kV,2 X 100 MVA and 1 X 200 MVA. The (2010-11) load reachedwill be 162 MVA.The transformers are replaced to meet the anticipated load growth.

4 400KV AURANGABAD AURANGABAD 1) 1X(500-315) MVA, 400/220 KV ICT WITH BAYS The existing transformer capacity available is S/S 400/220 kV, 2X315 MVA and the laod reached is (2011-12) 510 MVA.The transformer is replaced to meet the anticipated load growth. 5 132 kV GANGKHED Parbhani 1) Add 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2010-11) 2) 4 X 33 kV out lets. 25 MVA and load is 33 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load growth 6 132 kV JALNA MIDC Jalna 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2010-11) 2) 4 X 33 kV out lets. 25 MVA and load is 34 MVA. The transformer is replaced to meet anticipated load growth

7 132 kV UDGIR Latur 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2010-11) 2) 4 X 33 kV out lets. 25 MVA and load is 24 MVA. The transformer is replaced to meet anticipated load growth

8 132 kVPAITHAN Aurangabad 1) 1 X (50-25) MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2010-11) 2) 4 X 33 kV out lets. 25 MVA and load is 36 MVA. The transformer is replaced to meet anticipated load growth

9 220 kV PARLI GIRWALI Beed 1) 1 X (50-25) MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2010-11) 2) 4 X 33 kV out lets. 25 MVA and load is 26 MVA. The transformer is replaced to meet anticipated load growth

10 132 kV UJANI Latur 1) 1 X (50-25) MVA, 132/33 kV T/F with bays. The transformer is replaced to meet anticipated (2011-12) 2) 4 X 33 kV out lets. load growth 11 132 kV AUSA Latur 1) 1 X (50-25) MVA, 132/33 kV T/F with bays. The transformer is replaced to meet anticipated (2011-12) 2) 4 X 33 kV out lets. load growth 12 132 kV AHMEDPUR Latur 1) Add 1 X (50-25) MVA , 132/33 kV T/F 2 Existing transformer capacity available in s/s is 1 X (2012-13) 2) X 33 kV out lets. 25 & 1 X 50 MVA. And the load reached is 21 MVA The transformer is replaced to meet anticipated load growth.. 13 132 kV UJANI Latur 1) Add 1 X (50-25) MVA , 132/33 kV T/F 2 The transformer is replaced to meet anticipated (2014-15) 2) X 33 kV out lets. load growth * COMMISSIONED IN 2009-10 ** 1No. TF COMMISSIONED IN 2009-10

148

EHV CC O&M ZONE : AMRAVATI

149 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE SUBSTATION DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME

SPILL OVER SCHEMES 1 220 KV WANI S/S YAVATMAL 1) 2 x 25 MVA, 220/33 KV T/S WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING. 132 (2008-09) KV Wani - Pandharkavda D/C line - 30 Kms. Is 2) 8 x 33 KV OUTLETS proposed in 2009 - 10. 3) 220 KV D/C LINE WARORA - WANI - 35 KM 4) 2X100MVA,220/132KV 132 KV Wani - Pandharkavda D/C line - 30 Kms ( 5) Considered in Additional Link Line)

2 132 KV PATUR S/S * AKOLA 1) 2 X 25 MVA, 132/33 KV T/F It is necessary to go in for new 132kV sub-station at (2008-09) 2) 132 KV D/C ON D/C TOWER ON LILO PARAS- Partur. The new substation Partur-132kV is proposed on MALEGAON - 18 CKT.KM LILO of existing 132kV Paras-Malegaon line of 10kM in year 2009-10 for reducing loading on Akola-132kV S/S. 3) 8 X 33 KV OUTLET

3 132KV YAVATMAL 1) 132 KV D/C YAVATMAL TO GHATANJI S/S - 36 VOLTAGE IMPROVEMENT & LOAD CATERING GHATANJI S/S KM (2008-09) 2) 2X25 MVA, 132/33KV T/F WITH BAY 3) 33KV OUTLET - 8 NOS. 4) 132KV LINE BAY- 04NOS

4 132KV BARSHI-TAKLI S/S AKOLA 1) 2X25MVA, 132/33KV T/FS WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING (2008-09) 2) 132KV D/C LINE FROM AKOLA MIDC S/STN TO BARSHI TAKLI - 50 KM 3) 33KV OUTLETS - 08NOS 5 132 KV S/S YAVATMAL 1) 2 X 25 MVA , 132/33KV T/F WITH BAY. To eliminate 66kV level PANDHARKAWADA -II 2) 132 KV D/C YAVATMAL TO PANDHARKAWADA - (2009-10) 60 KM 3) 33KV OUTLETS - 08NOS 6 220KV MALEGAON II S/S WASHIM 1) 2X100MVA, 220/132KV ICTS WITH BAYS Present recorded peak load on Malegaon-132kV, (2009-10) Mehkar 132kV and Partur 132kV S/S are 26MW, 35 2) 220KV BALAPUR - MALEGAON D/C LINE - 52 MW and 20 MW respectively. It is anticipated by the KM WITH BAYS year 2010-11 the load will reach to about 105MW. 3) 132KV SCDC LINE FROM MALEGAON - II TO Hence it is necessary to go in for 220kV sub-station at PATUR - 25KM Malegaon. By the commissioning of this substation, voltage profile of Amaravathi Circle will improve. 4) 132KV REORIENTATION FROM OLD 132KV TO PROPOSED 220KV MALEGAON S/STN -20KM

7 220 KV NANDGAON PETH S/S AMRAVATI 1) LILO ON 220KV AMRAVATI -BADNERA AT Amravati-MIDC 220kV S/S is considered for Amravati (2009-10) NANDGAON PETH - 10KMS WITH BAYS industrial load. 2) 2nd CKT STRINGING OF 220 KV AMARAVATI- BADNERA-15 KM WITH BAYS 3) 132 KV WARUD-NANDGAON PETH SCDC LINE- 50 KM WITH BAYS 4) 2 X 50 MVA, 220/33KV T/FS WITH BAYS 5) 2 X 100 MVA, 220/132KV T/FS WITH BAYS 6) 12 X 33KV OUTLETS

8 220KV GHATODI S/S YAVATMAL 1) 2 X 100 MVA, 220/132KV T/FS WITH BAYS Ghatodi-220 kV S/S is considered for reducing the (2009-10) loading of Pusad-132kV & Digas-132kV S/S and also 2) 2 X 50 MVA, 220/33 KV T/FS WITH BAYS for reducing the loading of existing 220/66kV 3) LILO ON 220KV PUSAD - NANDED AT GHATODI transformer at Pusad-220kV S/S. This S/Stn is - 10 KMS WITH BAYS proposed for evacuation of power. 4) LILO ON 132KV PUSAD - JAMBAZAR AT GHATODI - 10 KMS WITH BAYS 5) LILO ON132KV PUSAD - DIGRAS AT GHATODI - 10 KMS WITH BAYS 6) 33 KV OUTLETS - 8 NOS 9 132 KV DEOLGAON RAJA S/S BULDHANA 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Present recorded peak load on Jalna-132kV is 50MW. It (2009-10) 2) 132 KV DUSARBID - DEOLGAON RAJA D/C is anticipated by the year 2009-10 that the load will LINE - 20 KM WITH BAYS reach to about 60MW. Hence it is necessary to go in for 3) 33 KV OUTLETS - 8 NOS new 132kV sub-station at Deolgaon-Raja.

10 132 KV MURTIZAPUR S/S AKOLA 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Inplace of 132 kv Durgwada s/s as existing 132 kV (2009-10) Durgwada S/s having sinking problem 2) 132 KV MURTIZAPUR D/C LINE FROM AKOLA - 220KV APATAPA S/STN- 45 KM WITH BAYS

3) 33 KV OUTLETS - 8 NOS

150 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE SUBSTATION DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME

66KV LEVEL ELIMINATION IN AMARAVATI, AKOLA DISTRICT 1 ELIMINATION OF 66KV LEVEL IN AMARAVATI A 66KV AMRAVATI A.To Eliminate 66 kV Amravati S/stn, new 33/11kv AKOLA DISTRICT substation with 2x 5 MVA T/F and 33 kv line from 220 kv (2008-09) 66/33KV , 1 X 10 MVA Amravati S/stn is to be established by DISCOM at Amravati. After completing the said work the 66 kV, Amravati s/stn will be absolate.

AMARAVATI B 66/11KV AMRAVATI MIDC B.To Eliminate 66 kV MIDC Amravati S/stn, new 33/11kv substation with 2x 10 MVA T/F and 33 kv line 66/11 KV, 2 X 10 MVA from 220 kv Amravati S/stn is to be established by DISCOM at MIDC Amravati. After completing the said work the 66 kV, MIDC Amravati s/stn will be absolate.

AKOLA C 66/33 KV MURTIZAPUR C. 132kv Murtizapur s/stn is proposed during 2009- 10.To Eliminate 66 kV Murtizapur S/stn, new 33/11kv 66/33 KV , 2 X 5 MVA substation with 2x 5 MVA T/F and 33 kv line from 132 Murtizapur S/stn is to be established by DISCOM at Murtizapur. After completing the said work the 66 kV, Murtizapur s/stn will be absolate.

AKOLA D 66 KV KARANJA D.132kv Karanja s/stn is proposed during 2008-09.To Eliminate 66 kV Karanja S/stn, new 33/11kv substation 66/33KV 2x10MVA , 66/11 KV,2 X 10 MVA with 3x 10 MVA T/F and 33 kv line from 132 Karanja S/stn is to be established by DISCOM at Karanja. After completing the said work the 66 kV, Karanja s/stn will be absolate. AMARAVATI E 66/11 KV CHANDUR RLY. E. To Eliminate 66 kV Chandur Rly S/stn, new 33/11kv substation with 2x 5 MVA T/F and 33 kv line from 220 kv 66/11 KV 2 X 5 MVA Dhamangaon S/stn is to be established by DISCOM at Chandur Rly. After completing the said work the 66 kV, Chandur Rly. s/stn will be absolate.

YAVATMAL F 66/11 KV DHAMANGAON RLY F. 220 kV Dhamangaon s/stn is in existance.To Eliminate 66 kV Dhamangaon Rly. S/stn, new 33/11kv 66/11 KV 2 X 5 MVA substation with 2x 5 MVA T/F and 33 kv line from 220 kv Dhamangaon S/stn is to be established by DISCOM at Dhamangaon Rly.After completing the said work the 66 kV, Dhamangaon RLy s/stn will be absolate.

AMARAVATI G 66/33KV OF 132/66KV AMRAVATI G. After completing work at Sr.No.A&B a 66/33 KV T/F at 132/66 kv Amravati S/stn will be absolate. 66/33 KV 1X10 MVA AKOLA H 132/66 KV PARAS H. After completion of works at Sr.No. A to G 132/66 kv T/F at Amravati s/stn will be absolate and also 132/66 132/66 KV , 1X 25 MVA kv T/F at Paras s/stn will be absolate. ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 132KV LINK LINE WASHIM 1) 132KV WASHIM - JAMBAZAR SCDC LINE - 43 132kV Jambazar S/S is fed from 132kV Pusad S/s with (2008-09) KM S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

2 132KV LINK LINE AMARAVTI 1) 132 KATOL - WARUD SCDC LINE -76 KM WITH 132kV Katol S/S is fed from 132kV Kalmeshwar S/s with (2008-09) BAYS S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

3 132KV LINK LINE AKOLA 1) 132 KV WASHIM - MANGURLPIR (STRINGING 132kV Mangrulpir S/S is fed from 132kV Malegaon S/s (2009-10) ONLY) - 33 KM WITH BAYS with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

4 132KV LINK LINE YAVATMAL 1) 132KV UMARKHED - GUNJ (STRINGING ONLY) - 132kV Gunj S/S is fed from 132kV Pusad S/s with S/c (2009-10) 21.67 KM line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE 1 132KV LINK LINE YAVATMAL 1) LILO ON YAVATMAL - PANDHARKAWADA LINE Since 132kv D/C line from Yavatmal - Ghatanji S/Stn (2009-10) AT GHATANJI S/S - 15KM proposed in year 2008-09 under new scheme is practically not feasible so this alternate arrangement is proposed. STRENGTHENING FOR EVACUATION ARRANGEMENT 1 132KV LINK LINE YAVATMAL 1) 132 KV WANI - PANDHARKAVDA D/C LINE - 30 To have evacuation facility for open access (2009-10) KMS WITH BAYS

151 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE SUBSTATION DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME

AUGMENTATION OF S/S BY ADDITION OF T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

1 220KV PUSAD S/S YAVATMAL 1) 1X100MVA, 220/132KV ICT WITH BAY To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 1X (50-25)MVA, 220/33 KV T/F 3) 132 KV BAYS - 2 NOS. 4) 2X33 KV OUTLETS 2 220KV AKOLA - II S/S * AKOLA 1) ADDL. 1X 25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) 2) 4 X 33KV OUTLETS. interruptions on any one transformer 3 220KV DHAMANGAON S/S * AMRAVATI 1) 1X25 MVA 220/33KV T/F To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33KV OUTLETS - 4NOS. 4 220KV CHIKHALI S/S BULDHANA 1) 1 X 100MVA, 220/132KV ICT WITH BAYS To avoid loss of supply in case of outages or (2008-09) 2) 132 KV BAYS - 2 NOS. interruptions on any one transformer 5 132KV DUSARBID S/S BULDHANA 1) ADDL 1X25 MVA 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 4 X 33KV OUTLETS. 6 132KV MOTALA BULDHANA 1) 1X25MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) 2) 33KV OUTLETS - 4 NOS. interruptions on any one transformer 7 132 KV DARYAPUR S/S AMRAVATI 1) 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) 2) 33 KV OUTLETS - 4 NOS. interruptions on any one transformer

8 132 KV RISOD S/S * WASHIM 1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33 KV OUTLETS - 4 NOS. 9 132KV DARWHA S/S* YAVATMAL 1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33KV OUTLETS - 4NOS. 10 132KV UMERKHED S/S* YAVATMAL 1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33KV OUTLETS - 4NOS. 11 132KV DIGRAS S/S* YAVATMAL 1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33KV OUTLETS - 4NOS. 12 132KV JAMBAZAR S/S YAVATMAL 1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33KV OUTLETS - 4NOS.

13 132KV GUNJ S/S YAVATMAL 1) 1X25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33KV OUTLETS - 4NOS. 14 400kV AKOLA S/S Akola 1) 3x105MVA , 400/220KV ICT WITH BAYS To avoid loss of supply in case of outages or interruption (2009-10) 2) 220 KV BAYS - 3 NOS. on any one transformer

15 220 kV DHAMANGAON Yeotamal 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. & (2009-10) 2) 4 X 33 kV out lets load reached is 4 MVA To avoid loss of supply in case of outages or interruptions on transformer.

16 132 kV DARYAPUR Amaravati 1) Add 1 X25 MVA, 132/33 kV T/F with bays Existing transformer capacity available in S/s is 1 X (2009-10) 2) 4 x 33 kV outlets 25MVA and load is 11. MVA. The transformer is replaced to meet anticipated load growth.

17 132 kV HIVERKHED Akola 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. & (2009-10) 2) 4 X 33 kV out lets load reached is 7 MVA To avoid loss of supply in case of outages or interruptions on transformer.

18 132 kV TIWSA Amaravati 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA.& (2009-10) 2) 4 X 33 kV out lets load reached is 8 MVA To avoid loss of supply in case of outages or interruptions on transformer.

152 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE SUBSTATION DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME

ICT PROPOSED TO INTRODUCE 132 LEVEL. 1 220KV YAVATMAL * YAVATMAL 1) 1X100 MVA, 220/132KV ICTS WITH BAYS Newly Introduced 220/132kV Level to feed 132 kV (2009-10) Darwha S/s as an alternate source.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER 1 132 KV ACHALPUR S/S* AMRAVATI 1) 1X25 MVA, 132/33KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x 25 - 21.8 load 2) 33 KV OUTLETS - 4 NOS. 132/33 - 2 x 10 - 20.4 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

2 132 KV LALKHEDI S/S * * AMRAVATI 1) 2X25 MVA, 132/33KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 16 - 13 load 2) 33KV OUTLETS - 8 NOS. Hence it is necessary to propose additional transformer to meet additional load growth and contingency.

3 132KV AKOLA MIDC S/S AKOLA 1) 1X25 MVA, 132/33KV T/F WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 29 load Considering the maximum load reach on the 2) 33KV OUTLETS - 4NOS. transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

AUGMENTATION OF S/S BY REPLACEMENT OF T/F 1 220KV AMARAVATI S/S AMRAVATI 1) REP.2X25MVA, 132/66KV T/FS BY 132/33KV To Eliminate 66 kV Level (2008-09) 2) DOWN GRADATION OF 66KV TO 33KV S/S

2 220KV AMRAVATI S/S * AMRAVATI 1) 1X(200-150)MVA, 220/132KV ICT Existing transformer capacity available in S/s is, (2008-09) 220/132 - 1 x 150 - 114.5 load 220/132 - 1 x 100 - 80.2 load 2) 2X132KV BAYS Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

3 220KV YAVATMAL* YAVATMAL 1) 1X(50-25)MVA, 220/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 37.2 load 2) 33KV OUTLETS - 8 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

4 220KV CHIKHALI S/S * BULDHANA 1) 1 X (50 -25) MVA, 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 25 - 19.3 load The transformers are replaced to meet anticipated load 2) 33 KV OUTLETS - 8 NOS. growth.

5 132KV ANJANGAON* AMRAVATI 1) 1X(25-12.5), 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 12.5 - 19.8 load Considering the maximum load reach on the 2) 33KV OUTLETS - 4 NOS. transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

6 132KV CHANDURBAZAR S/S AMRAVATI 1) 1 x (25-10) MVA, 132/33 KV T/F Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 10 - 19.4 load 2) 33KV OUTLETS - 2 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one 7 132KV MEHEKAR S/S * BULDHANA 1) 1X(50-25) MVA, 132/33KV T/FS WITH BAYS ofExisting the transformer transformer other capacity transformer available should in S/s take is, care of (2008-09) 132/33 - 2 x 25 - 24.2 load 2) 33 KV OUTLETS - 2 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

8 132KV MORSHI S/S AMRAVATI 1) 1X(25-10), 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 2 x 10 - 15.1 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 153 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE SUBSTATION DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME

9 132KV WARUD S/S * AMRAVATI 1) 1X(25-10), 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 - 1 x 25 - 12.7load 132/33 - 1 x 10 - 5.06 load The transformers are replaced to meet anticipated load growth. 10 132KV AKOLA 1) 2 X (50 -25) MVA, 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is, AKOT S/S** 132/33 - 1 x 25, 1 x 10 - 31.78 load (2008-09) Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

11 132KV ANJANGAON S/S AMRAVATI 1) 1X(25-12.5), 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is, (2008-09) 132/33 -2 x 12.5 - 19.8 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one 2) 33KV OUTLETS - 4 NOS. of the transformer other transformer should take care of existing load so as to avoid load shedding.

12 220KV AKOLA S/S AMRAVATI 1) 1X(200-150) MVA, 220/132KV ICT WITH BAYS The existing transformer capacity available in S/s is (2009-10) 220/132kV 2 X 150 MVA.The load reached is 163 MVA. The transformer is replaced to meet the anticipated load growth.

13 220 KV CHIKHALI S/S BULDHANA 1) 1X(200-100) MVA, 220/132KV ICT WITH BAYS The existing transformer capacity available in S/s is (2009-10) 220/132kV 2 X 100 MVA.The load reached is 138MVA.The transformer is replaced to meet the anticipated load growth. 14 132 KV MORSHI Amaravati 1) 1 X (50-25) , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 10 & (2009-10) 2) 2 X 33 kV out lets. 1 X 25 MVA. And the load reached is 10 MVA TConsidering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 15 132 KV MEHKAR * Buldana 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2009-10) 2) 2 X 33 kV out lets. MVA and load is 44 MVA. The transformer is replaced to meet anticipated load growth.

16 220 KV CHIKHALI * Buldana 1) 2 X (50-25) MVA, 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X 50 & (2009-10) 2) 4 X 33 kV out lets. 1 X 25 MVA. And the load reached is 24 MVA TConsidering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

154 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE SUBSTATION DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME

NEW SCHEMES 1 220 KV ANJANGAON II S/S YAVATMAL 1) 220KV LINE FROM 400KV AKOLA - It is necessary to go in for 220kV sub-station at (2010-11) ANJANGAON D/C LINE - 45KMS WITH BAYS Anjangaon. Anjangaon-220kV S/S is fed from Amaravathi by constructing 220kV D/C line of 52kM 2) 2 X 100MVA, 220/132KV ICTS WITH BAYS length.

3) 2 X 50 MVA, 220/33KV T/FS WITH BAYS 4) 4 X 132KV BAYS

5) 12 X 33KV OUTLETS 6) LILO ON 132KV KATOL -132KV ANJANGAON 7) LILOS/S AT ON 220KV 132KV ANJANGAON ACHALPUR -132KVNEW S/STN-14 KM 8) 132KVANJANGAON SCDC LINE S/S FOR TOD 220KV ARYAPUR ANJANGAON S/S- 30 KM WITH BAYS 2 132 KV S/S AT JALGAON - JAMOD BULDHANA 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Jalgaon Jamod is considered for catering increasing (2010-11) 2) 132 KV FROM 220KV BALAPUR - JALGAON loads in Buldhana District. JAMOD D/C LINE-30 KM WITH BAYS

3) 33 KV OUTLETS - 8 NOS 3 132 KV YAVATMAL MIDC S/S YAVATMAL 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Yavatamal MIDC –132kV S/S is considered for the (2010-11) 2) 132 KV YAVATMAL - YAVATMAL MIDC D/C Industrial load coming in year 2010-11. LINE - 13 KM WITH BAYS 3) 33 KV OUTLETS - 8 NOS 4 220KV WARUD II S/S AMRAVATI 1) 2 X 100 MVA, 220/132 KV T/FS WITH BAYS To meet the increased load in that area. (2011-12) 2) 220 KV D/C KALMESHWAR -WARUD - 70 KM WITH BAYS 3) 132 KV OUTLETS - 4 NOS 4) 132 KV D/C LINE TO WARUD- I S/S -5 KM WITH BAYS 5) LILO OF 132 KV WARUD - MORSHI S/S AT 220KV WARUD - 30 KM 5 765/400 KV AKOLA -II S/S AKOLA 1) 765/400 KV , 4 X 500 MVA , 1 - PHASE ICT'S Evacuation of Power. ( 2012-13) WITH BAYS 2) 765 KV AKOLA -II - AURANGABAD 2 X S/C QUAD LINE - 420 KM 3) 400KV LINE FROM AKOLA - II - AKOLA -I D/C QUAD 66KV LEVEL ELIMINATION IN AMARAVATI, AKOLA DISTRICT 1 ELIMINATION OF 66KV LEVEL IN YAVATMAL A 66 KV DARWHA A.132kv Darwha s/stn is in existance.To Eliminate 66 YAVATMAL DISTRICT kV Darwha S/stn, new 33/11kv substation with (2010-11) 2x 5 MVA T/F and 33 kv line from 132 Darwha S/stn is (66/33 KV,1X10 MVA, 66/11 KV 1 X5 MVA) to be established by DISCOM at Darwha. After completing the said work the 66 kV, Darwha s/stn will be absolate. B 66 KV DIGRAS B.132kv Digras s/stn is in existance.To Eliminate 66 kV Digras S/stn, new 33/11kv substation with 2x 10 MVA T/F and 33 kv line from 132 Digras S/stn is to be (66/11KV, 2X 5 MVA, 66/33 KV 1 X 10 MVA) established by DISCOM at Digras. After completing the said work the 66 kV, Digras s/stn will be absolate.

C 66 KV GHATANJI C.132kv Ghatanji s/stn is proposed during 208-09.To Eliminate 66 kV Ghatanji S/stn, new 33/11kv substation with 2x 10 MVA T/F and 33 kv line from 132 Ghatanji 66/33 KV,2X10 MVA S/stn is to be established by DISCOM at Ghatanji. After completing the said work the 66 kV, Ghatanji s/stn will be absolate. D 66 KV PANDHARKAVDA D.132 kv Pandarkavda s/stn is proposed during 2009- 10.To Eliminate 66 kV Pandharkavda S/stn,new 33/11kv substation with 3x 10 MVA T/F and 33 kv line 66/33 2x10 ,66/11 KV, 2 X 5 MVA from 132 kv Pandharkavda S/stn is to be established by DISCOM at Pandharkavda. After completing the said work the 66 kV, Pandharkavda s/stn will be absolate.

E 220/66 KV YAVATMAL E. After getting the above work done at Sr.No. A,B,C&D the 220/66 kv T/F at 220 kv Yavatmal S/stn.will be (220/66 KV, 1X 50 MVA) absolate.

155 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE SUBSTATION DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME

ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 132KV LINK LINE YAVATMAL 1) 132KV DIGRAS - DARWHA SCDC LINE - 27 KM 132kV Darwha S/S is fed from 132kV Digraj S/s with S/c (2010-11) line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

2 132KV LINK LINE AMRAVATI 1) 132KV DARYAPUR - ANJANGAON SCDC LINE - 132kV Daryapur S/S is fed from 132kV Durgwada S/s (2011-12) 30 KM with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 3 132KV LINK LINE AKOLA 1) 132KV DC LINE FROM 132KV MURTIZAPUR - System Strengthining. (2011-12) RAILWAY TSS - 15KM 4 132KV LINK LINE YAVATMAL 1) 132KV SCDC LINE FROM 132KV YAVATMAL - System Strengthining. (2011-12) DARVA - 40 KM 5 132KV LINK LINE AKOLA 1) 2ND CIRCUIT STRINGING OF 132KV AKOT- 132 kV Hiwarkhed S/s. is fed from 132 kV Akot S/s. with (2011-12) HIWARKHED LINE-20 KM S/C line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

6 132KV LINK LINE AMRAVATI 1) 2ND CIRCUIT STRINGING OF 132KV KATOL- System Strengthining. (2012 - 13 ) BHARSHINGI-WARUD LINE-50 KM 7 132KV LINK LINE BULDHANA 1) 2ND CIRCUIT STRINGING OF 132KV CHIKHALI - 132 kV Dhad S/s. is fed from 132 kV Chikhali S/s. with (2012 - 13 ) DHAD LINE - 22 KM S/C line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 220KV LINK LINE WARDHA 1) 220KV WARDHA II -YAVATMAL SCDC LINE - 80 Since the existing 220kV Wardha-I-Yavatmal S/c line is (2010-11) KM WITH BAYS critically loaded to an extent of 263 MW. Hence it is suggested to add proposed line to reduce the loading of existing line and to meet additional load growth and contingency. STRENGTHENING FOR EVACUATION ARRANGEMENT 1 220KV LINK LINE AKOLA 1) 220 KV AKOLA -BALAPUR (MIDC) D/C LINE - 27 To have evacuation facility for additional 1 x 250 MW for (2011-12) KM WITH BAYS gen at Paras 2 220KV LINK LINE YAVATMAL 1) 220KV GHATODI - WANI D/C -320KM To have evacuation facility for open access (2011-12) ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE 1 220KV LINK LINE HINGOLI 1) 220 KV D/C LINE FROM GHATODI - HINGOLI Additional Line is considered to (2011-12) SCDC LINE -85 KM WITH BAYS strengthen the Network 2 132KV LINK LINE AKOLA 1) 132KV SCDC LINE FROM 132KV MURTIZAPUR - Additional Line is considered to (2012-13) KARANJA - 35KM strengthen the Network 3 132KV LINK LINE BULDHANA 1) 132KV SCDC LINE FROM 132KV DEOLGAON Additional Line is considered to (2012-13) RAJA - DHAD -50KM strengthen the Network 4 132KV LINK LINE BULDHANA 1) 132KV SCDC LINE FROM 132KV JALGAON Additional Line is considered to (2012-13) JAMOD - HIWARKHED - 40KM strengthen the Network AUGMENTATION OF S/S BY ADDITION OF ICT/ TF AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE 1 220KV YAVATMAL YAVATMAL 1) 1X100 MVA, 220/132KV ICTS WITH BAYS Newly Introduced 220/132kV Level to feed 132 kV (2010-11) 132KV BAYS - 2NOS Darwha S/s as an alternate source.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT/TF 1 132 kV CHANDUR BAZAR * Amaravati 1) 1 X 25 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1X 25 & (2010-11) 2) 4X 33 kV out lets. 1 X 10 MVA. And the load reached is 22 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 2 220 kV DHAMANGAON YAVATMAL 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 MVA. & (2013-14) 2) 4 X 33 kV out lets load reached is 4 MVA To avoid loss of supply in case of outages or interruptions on transformer.

AUGMENTATION OF S/S BY REPLACEMENT OF ICT/TF 1 220 KV AKOLA S/S AMRAVATI 1) 1X(200-150) MVA, 220/132KV ICT WITH BAYS The existing transformer capacity available in S/s is (2010-11) 132KV BAYS - 2NOS 220/132kV 1 X 150and 1 X 200 MVA.The load reach will be 175 MVA.The transformer is replaced to meet the anticipated load growth. 2 220 KV CHIKHALI S/S (2010- BULDHANA 1) 1X(200-100) MVA, 220/132KV ICT WITH BAYS The existing transformer capacity available in S/s is 11) 132KV BAYS - 2NOS 220/132kV 1 X 100and 1 X 200 MVA.The load will be reach156 MVA.The transformer is replaced to meet the anticipated load growth. 3 220KV WANI S/S 1) 1 X (50-25) MVA , 220/33 kV T/F with bays. To cater upcoming load & for redundacy. (2010-11) 2) 2 X 33 kV out lets.

4 132 KV MEHKAR Buldana 1) 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X 25 (2010-11) 2) 2) 2 X 33 kV out lets. MVA and load is 44 MVA. The transformer is replaced to meet anticipated load growth. 5 132 KV AKOT * Akola 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X (2011-12) 2) 2 X 33 kV out lets. 25MVA. And the load reached is 23 MVA The transformer is replaced to meet anticipated load growth.

6 220KV WANI S/S 1) 1 X (50-25) MVA , 220/33 kV T/F with bays. To cater upcoming load & for redundacy. (2011-12) 2) 2 X 33 kV out lets. 156 STU/TRANS/DOC-04 - W.E.F 01/04/2010 STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE SR NO NAME OF THE SUBSTATION DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME

7 132 KV AKOT * Akola 1) 1 X (50-25) MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 2 X (2012-13) 2) 4 X 33 kV out lets. 25MVA. And the load reached is 23 MVA The transformer is replaced to meet anticipated load growth.

* COMMISSIONED IN 2009 - 10 * * 1 No. TF. COMMISSIONED IN 2009 - 10.

157

EHV CC O&M ZONE : NAGPUR

158 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

SPILL OVER SCEHEMES 1 132 KV JAM S/S WARDHA 1) 132 KV DC LINE FROM 220 KV HINGANGHAT VOLTAGE IMPROVEMENT & LOAD CATERING (2008-09) S/S - 24 KM 2) 2 x 25 MVA, 132/33 KV T/F WITH BAYS 3) 8 x 33 KV OUTLETS 2 132KV LAKHANDUR S/S BHANDARA 1) 132 KV D/C LINE FROM ASGOAN TO VOLTAGE IMPROVEMENT & LOAD CATERING (2008-09) LAKHANDUR 46 KM 2) 2 X 25 MVA, 132/33 KV T/F WITH BAYS

3) 33 KV OUTLET - 8 NOS. 3 NAGPUR RING MAIN NAGPUR 1) A) ESTABLISHMENT OF 220/132/33 KV S/S 220kV Uppalwadi, Mankapur, New Pardi, New MANKAPUR WITH 2x50MVA, 220/33 KV T/F AT Buttibori S/S are considered to meet the load NEW PARDI UPPALWADI growth and to improve the voltage profile in Nagpur NEW BUTTIBORI B) ESTABLISHMENT OF 220/132/33 KV S/S circle. (2008-09) WITH 2x100 MVA, 220/132 KV ICT, 2x50MVA, 220/33 KV T/F AT MANKAPUR C) ESTABLISHMENT OF 220/132/33 KV S/S WITH 2x100 MVA, 220/132 KV ICT, 1x50MVA, 220/33 KV T/F AT NEW PARDI D) ESTABLISHMENT OF 220/132/33 KV S/S WITH 2x100 MVA, 220/132 KV ICT AT BUTIBORI II E)2x50MVA, 220/33 KV T/F AT BUTIBORI III

CONSTRUCTION OF 220 KV LINK LINES CONNECTING THE SUBSTATIONS ON NAGPUR RING MAIN, viz.

i) 220 KV Khaperkheda - Uppalwadi D/C line O/H - 12KM & U/G - 1 KM ii)220KV UPPALWADI - MANKAPUR M/C line O/H - 8KM & U/G - 2.5KM iii)220KV UPPALWADI - PARDI M/C line O/H - 13.5KM & U/G - 0.5KM

iv) 220KV NEW PARDI -BUTTIBORI III D/C line 1)M/C line from Pardi to Loc . No 68 of Ex. 132KV line 21KM 2)Only stringing from Loc. No 68 to 47 on M/C tower 6KM 3)D/C line from Loc . No 68 of Ex. 132KV line to Butibori III 14.5KM & U/G - 1KM ( Pardi end)

v) 220KV OLD BUTTIBORI - BUTTIBORI III with reorientation near Old B'bori -D/C on M/C line - 1.5 KM

Only stringing on M/c towers of 220KV Koradi- Butibori 38KM & U/G - 0.5KM ( M/C near A'zari end) 220KV AMBAZARI - MANKAPUR M/C line O/H - 13KM & U/G - 4KM i) IInd ckt. stringing of 220KV Kanhan Umred O/H : 51 KM & LILO of same at Pardi S/s O/H : 7 KM U/G : 4KM ii) LILO ON KHAPARKHEDA (OLD) - WARDHA FOR BUTTIBORI III D/C on M/C line- 1 KM

Additional Lines : i) 132 KV M/C Butibori I to Butibori II line for reorientation at Butibori II - 5 km O/H : 3.5KM U/G : 1.5KM

2) ii)220 KV D/C Tower line for reorientation at Butibori II - 1 KM iii) Reorientation of 132KV lines at Mankapur (0.5KM), Pardi (0.5KM)

159 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

4 132KV GIS LENDRA S/S NAGPUR 1) 2X50 MVA 132/33KV T/FS WITH BAYS VOLTAGE IMPROVEMENT & LOAD CATERING (2008-09) 2) 132KV LILO ON MANKAPUR-HINGNA -I AT LENDRA - 16 CKM O/H : 7CKM & U/G : 9CKM 3) LILO ON 132KV AMBAZARI - HINGNA -I AT LENDRA S/STN -10KM 4) 12 X 33KV OUTLETS. 5 400KV WARDHA (PG) * WARDHA SCOPE OF WORK BY MSETCL Wardha-PGCIL is constructed by PGCIL. (2009-10) 1)* LILO ON 220KV WARDHA-I - BADNERA S/C TO WARDHA (PGCIL) - 10 KMS WITH BAYS

2) 220KV LINE FROM PGCIL WARDHA 400KV - GHATODI D/C LINE-50 KM WITH BAYS 3) LILO OF 220KV BHUGAON - PUSAD S/C AT 400KV WARDHA(PG) - 15KM

6 400KV WARORA S/S WARDHA 1) 400KV WARDHA (PG) - WARORA - 70 KM Warora 400kV station is proposed to take care of (2009-10) (ALREADY CONSIDERED IN CHANDRAPUR open access consumer’s power injections and feed EVA.) the area.

2) 2 X 500 MVA 400/220 KV ICT'S WITH BAYS 3) LILO ON ONE CIRCUIT OF 220 KV WARDHA-II (BHUGAON) - WARORA D/C LINE AT 400 KV WARORA - 10KM

7 220 KV NAGPUR 1) 2 X 100 MVA, 220/132 KV T/FS WITH BAYS 220kV Uppalwadi S/S IS considered to meet the UPPALWADI S/S load growth and to improve the voltage profile in 2) 2 X 50 MVA, 220/33 KV T/FS WITH BAYS (2009-10) Nagpur circle. 3) (A) 220 KV MC ON MC LINES (0.4 SQ.MM ACSR ZEBRA COND.) i) i ) KHAPARKHEDA (OLD) - UPPALWADI D/C - 12.6 KM (O/H -11.8KM & U/G -0.8KM.) ii) UPPALWADI - MANKAPUR D/C - 10 KM (O/H - 7.5KM & U/G -2.5KM). III) UPPALWADI - PARDI -D/C - 15 km (O/H - 14.5KM & U/G -0.5KM) 4) REORIENTATION OF 132KV LINES-20KM 5) 33 KV OUTLETS - 12 NOS. NEW SUBSTATION TO ELIMINATE 66 KV LEVEL 1 132KV BHARSHINGI NAGPUR 1) 2 X 25MVA, 132/33KV T/FS WITH BAYS ELIMINATION OF 66 KV LEVEL (2008-09) 2) 132KV KATOL-BHARSHINGI-WARUD SCDC LINE-50 KM 3) 33KV BAYS - 08 NOS 2 220 KV BALLARSHAH S/S CHANDRAPUR 1) 2X25 MVA 220/33KV T/FS WITH BAYS ELIMINATION OF 66 KV LEVEL (2009-10) 220 KV CHANDRAPUR-MIDC-BALLARSHAH 2) D/C LINE-20 KM

3 132KV PULGAON S/S WARDHA 1) 2X25MVA 132/33KV T/FS WITH BAYS ELIMINATION OF 66 KV LEVEL (2009-10) 2) 132 KV WARDHA-II-PULGAON D/C LINE-15 KM 132KV PULGAON - ARVI - 35 KM 3) 8X33KV OUTLETS 4 132KV SAHULI S/S NAGPUR 1)4) 2X25MVA 132/33KV T/FS WITH BAYS ELIMINATION OF 66 KV LEVEL (2009-10) 2) LILO ON 132 KV BHANDARA-AMBHORA AT SAHULI-5 KM 3) 132 KV PARDI - SAHULI SCDC LINE - 25 KM WITH BAYS 4) 8X33KV OUTLETS 5 132 KV ALLAPALLI GADCGHIROLI 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Allapali-132kV S/S is considered to cater increasing (2009-10) loads in Chandrapur circle and to eliminate 66 kv 2) 132 KV ASHTI - ALAPPALI D/C LINE - 35 KM level.

3) 33 KV OUTLETS - 8 NOS

6 132 KV YETAPALLI GADCGHIROLI 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Yetapalli-132kV S/S is considered to cater (2009-10) 2) 132 KV YETAPALLI - ALAPPALI D/C LINE - 35 increasing loads in Chandrapur circle and to KM eliminate 66 kv level. 3) 33 KV OUTLETS - 8 NOS 160 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

66KV LEVEL ELIMINATION 1 ELIMINATION OF 66KV BHANDARA & A 66 KV TUMSAR A.132kv Tumsar s/stn is proposed during 2011- LEVEL AT MADGI, GONDIA 12.To eliminate 66 kV Tumsar s/stn, new 33 /11kv TIRODA, SAHULI, s/stn alongwith 2x10 MVA T/F and 33 kv line from GONDIA, TUMSAR IN 66/11KV 2x5 MVA and 66/33 kV 1x5 132 kv Tumsar s/stn is to be established by BHANDARA & GONDIA MVA,1x3MVA DISCOM at Tumsar. After complition of above said DISTRICT work 66/11kv Tumsar s/stn will be absolate. (2008-09)

B 66 KV MORGAON ARJUNI B. 132KV Morgaon Arjuni s/stn is proposed during 2010-11.To eliminate 66/11 KV at 66 kV Morgaon Arjuni new 33 /11kv s/stn alongwith 2x5 MVA T/F 66/33KV, 1X5MVA, 66/11 2X5MVA and 33 kv line from 132 kv Morgaon Arjuni s/stn is to be established by Discom at Morgaon Arjuni after complition of above said work 66/11kv s/stn will be absolate. C 132kV MADGI C. After getting the above work the 132/66 kv 2 X 25MVA T/F at 132 kv Madgi s/stn will be 132/66 kv 2x25 MVA absolate. 2 ELIMINATION OF 66KV WARDHA A 66 KV SEVAGRAM A. To eliminate 66 kv Sewagram s/stn, a new 33 kv LEVEL IN WARDHA s/stn with 2x10 MVA T/F and 33 kv line from 220 kv 66/11 KV 2X10 MVA DISTRICT 2009-10 Wardha s/stn is to be established by DISCOM.After completing this work 66 kv Sewagram s/stn will be absolate. B 66 KV NANDURI B. To eliminate 66 kv Nanduri s/stn, new 33 kv s/stn 2X10 MVA 66/33KV, 1X5 MVA 66/11KV alongwith 3x10MVA T/F and 33 kv line from 220 KV Hinganghat substation is to be established by Discom at Nanduri.After compltion of above said work 66kv Nanduri s/stn will be absolate.

C 66KV SONEGAON C. To eliminate 66 kv sonegaon s/stn, new 33 kv s/stn alongwith 2x5 MVA T/F and 33 kv line from 2x5MVA 66/11kv 132kv Khapri s/stn.is to be established by Discom at sonegaon.after completion of above said work 66 kv Sonegaon s/stn will be absolate.

D 66 KV PULGAON D. To eliminate 66 kv Pulgaon s/stn. a new 33 kv s/stn with 2x10 MVA T/F and 33 kv line from 220 kv 66/33 KV 1 X 5MVA, 66/11 KV 2 X 5MVA Wardha s/stn is to be established by DISCOM.After completing this work 66 kv Pulgaon s/stn will be absolate. E 66KV HINGANGHAT E. 220/33 kv Hinganghat s/stn.is in existance.To eliminate 66 kv Hinganghat s/stn, new 33 kv s/stn. 2X10MVA 66/11KV, 1X5MVA 66/11KV with 3x10 MVA T/F alongwith 33 kv line from 220 KV Hinganhat s/stn is to be established by discom.

F 66/11 KV SELDOH F. 132 kv Seloo is proposed during 2009-10.To eliminate 66 KV Seldoh s/stn new 33 /11kv s/stn 2x5MVA 66/11KV alongwith 2x5 MVA T/F and 33 kv line from 132 kv Seloo S/stn. is to be established by Discom at Seldoh after complition of above said work 66kv Seldoh s/stn will be absolate. G 66 KV SEL00 G. 66 KV consumer M/s.NOBLE EX is connected to 66 kv seloo s/stn. Now the consumer is PD. 132 kv 1 X 10MVA 66/11 KV seloo s/stn is proposed to be commossioned during 2009-10.To eliminate 66 kv Seloo s/stn new 33 kv s/stn alongwith 2x5 MVA T/F and 33 kv line from 132kv seloo s/stn. is to be established by Discom at Seloo. After completion of said work 66 kV seloo s/stn will be absolate.

H 66 KV WARDHA -I H. To eliminate 66/11 kv T/Fs at Wardha - I s/stn. new 33 kv s/stn alongwith 3x10 MVA T/F and 33 kv line from 220 kv Wardha - I s/stn. is to be 66/11 KV, 3 X 10 MVA established by Discom at Wardha.After completion of above said work 66/11 kv T/Fs at Wardha - I s/stn will be absolate. I 220/66 KV WARDHA -I I. After completing all the works at Sr.No. A to H the 2x50 MVA 220/66 kv T/F at 220 kv Wardha will be 220/66 KV, 2 X 50 MVA absolate. 161 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

1 132KV LINK LINE NAGPUR 1) 132KV KALMESHWAR - SAONER (STRINGING 132kV Saoner S/S is fed from 132kV Kalameshwar (2008-09) ONLY) - 49 KM S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 2 132KV LINK LINE BHANDARA 1) 132 KV KARDHA - ASGAON LINE (2ND 132kV Asgaon S/S is fed from 132kV Kardha S/s (2008-09) CIRCUIT STRINGING ) - 58 KM WITH BAYS with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line

3 132KV LINK LINE NAGPUR 1) 132 KV KATOL - SAONER D/C with 2nd CKT 132kV Saoner S/S is fed from 132kV Kalameshwar (2008-09) LILO at 220 KV KATOL S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line for the connectivity at 220KV Katol S/stn 4 132KV LINK LINE GONDIA 1) 132 KV AMGAON -AMGAON TSS SCDC LINE - To avoid overloading on 132 kV Amgaon-TSS- (2008-09) 5 KM Gondia S/c the additional 132 kV Amgaon-TSS - Amgaon S/c is proposed 5 132KV LINK LINE WARDHA 1) 132 KV WARDHA-II-HINGANGHAT D/C LINE- To Eliminate 66 kV level at Hinganghat S/s. (2008-09) 28.1 KM (OH LINE-27.1KM ,U/G CABLE- 1.011KM) 6 132KV LINK LINE NAGPUR 1) 132 KV BUTTIBORI - KHAPRI D/C LINE - 25 KM For Strengthing of Nagpur Ring Main (2008-09) WITH BAYS

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 1 220KV LINK LINE NAGPUR 1) 2ND CKT STRINGING OF 220KV KANHAN- Since 220kV M/C line from New Pardi- Umred (2009-10) UMRED LINE AND LILO OF THIS CIRCUIT AT proposed in earlier plan is practically not feasible so NEW PARDI S/STN -56 KM this alternate line is proposed.

2 132KV LINK LINE NAGPUR 1) STRINGING OF 2ND CKT FROM 132 KV Since the existing 132kV Khapri-Besa S/c line is (2009-10) KHAPRI - BUTTIBORI LINE - 20 KM WITH loaded to an extent of 38 MW and 132kV Khapri- BAYS Hingana-I S/c line is loaded to an extent of 43 MW during Non-Coinsident peak condition. It is anticipated the load will reach to about critical value by the year 2011-12 due to load growth in the vicinity of Khapri. Hence it is necessary to add additional line to meet additional load growth and contingency.

3 132KV LINK LINE GONDIA 1) LILO ON ONE CKT OF 132 KV GONDIA - Since 132kV Amgaon TSS - Amgaon S/S -5km (2009-10) AMGAON TSS AT AMGAON S/STN - 5 KM proposed in year 2008-09 is practically not feasible this alternate line is proposed . ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

1 132KV LINK LINE NAGPUR 1) 132 KV KALMESHWAR - HINGANA - I - For Strengthing of Nagpur Ring Main (2009-10) HINGANA -II D/C LINE - 25 KM WITH BAYS STRENGTHENING FOR EVACUATION ARRANGEMENT 1 220KV LINK LINE CHANDRAPUR 1) LILO ON 220KV CHANDRAPUR MIDC - Strengthening for Chandrapur Evacuation (2009-10) GADCHANDUR LINE AT WANI -30KM AUGMENTATION OF S/S BY ADDITION OF T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

1 220KV WARORA S/S * CHANDRAPUR 1) ADDL. 1X25 MVA 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s (2008-09) is,220/33 - 1 x 25 - 11.42 load 2) 4 X 33 KV OUTLETS To avoid loss of supply in case of outages or interruptions on any one transformer 2 220KV CHANDRAPUR 1) 1 X 100MVA, 220/132KV ICTS WITH BAYS To avoid loss of supply in case of outages or VIRUR S/S 3)2) 1132 X 25MVA,KV BAYS 132/33KV - 2 NOS. T/FS WITH BAYS interruptions on any one transformer (2008-09) 4) 4 X 33KV OUTLETS. 3 132KV CHANDRAPUR 1) ADDL. 1X 25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or MUL S/S interruptions on any one transformer (2008-09) 2) 4 X 33KV OUTLETS. 4 132KV WARDHA 1) ADDL. 1X 25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or ARVI S/S interruptions on any one transformer (2008-09) 2) 4 X 33KV OUTLETS. 5 132KV WARDHA 1) ADDL. 1X 25 MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or DEOLI S/S 2) 4 X 33KV OUTLETS. interruptions on any one transformer (2008-09) 162 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

6 220KV WARDHA 1) 1 X 100MVA, 220/132KV ICTS WITH BAYS To avoid loss of supply in case of outages or HINGANGHAT S/S 2) 132 KV BAYS - 2 NOS. interruptions on any one transformer (2008-09) 3) 1 X 50MVA, 220/33KV T/FS WITH BAYS

4) 1X25MVA, 132/33KV T/F

5) 10 X 33KV OUTLETS.

7 132 KV KHAPRI S/S NAGPUR 1) 1X25 MVA, 132/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33 KV OUTLETS - 4 NOS. 8 220 KV KAULEWADA S/S BHANDARA 1) 1X25 MVA, 220/33 KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) interruptions on any one transformer 2) 33 KV OUTLETS - 4 NOS. 9 132KV SAKOLI S/S BHANDARA 1) 1X25MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) 2) 33KV OUTLETS - 4 NOS. interruptions on any one transformer 10 132KV AMGAON S/S GONDIA 1) 1X25MVA, 132/33KV T/F WITH BAYS To avoid loss of supply in case of outages or (2008-09) 2) 33KV OUTLETS - 4 NOS. interruptions on any one transformer 11 220KV HINGANGHAT S/S WARDHA 1) 1 X 80 MVA, 220/132KV ICTS WITH BAYS The existing transformer capacity available is (2009-10) 2) 132 KV BAYS - 2 NOS. 220/132 kV,1 X80 MVA and the laod reached is 11 MVA.To avoid loss of supply in case of outages or interruptions on any one ICT additional ICT is proposed. 12 220KV WARDHA II WARDHA 1) 1 X 100 MVA, 220/132KV ICT WITH BAYS The existing transformer capacity available is (BHUGAON) S/S 2) 132 KV BAYS - 2 NOS. 220/132 kV,1 X100 MVA and the laod reached is (2009-10) 20 MVA.To avoid loss of supply in case of outages or interruptions on any one ICT additional ICT is proposed. 13 132 kV HINGANA-I Nagpur 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. & load reach is 13 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 14 132 kV SINDEWAHI Gadchiroli 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. & load reach is 14 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 15 132 Kv ASHTI Gadchiroli 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 10 GADCHIROLI 2) 4 X 33 kV out lets MVA. & load reach is 5 MVA.To avoid loss of (2009-10) supply in case of outages or interruptions on transformer. 16 220 kV HINGANGHAT Wardha 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. & load reach is 5 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 17 220 kV WARDHA-II Wardha 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (BHUGAON) * 2) 4 X 33 kV out lets MVA. To avoid loss of supply in case of outages or (2009-10) interruptions on transformer. 18 220 kV GADCHIROLI Gadchiroli 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. & load reach is 13 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 19 220 kV UMRED * Nagpur 1) Add 1 X 25 MVA, 220/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2009-10) 2) 4 X 33 kV out lets MVA. & load reach is 9 MVA.To avoid loss of supply in case of outages or interruptions on transformer. AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER 1 400KV S/S - KORADI S/S NAGPUR 1) ADDL. 1 X500 MVA, 400/220KV ICT WITH Existing transformer capacity available in S/s (2008-09) BAYS AT - KORADI S/S is,400/220 - 1 x 315 - 220 load 400/220 - 1 x 300 - 2) 220 KV BAYS - 3 NOS. 245 load Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 2 220 KV S/S WARDHA 1) ADD 2X 25 MVA, 220/33KV T/FS WITH BAYS Newly Introduced 220/33 kV Level to feed proposed WARDHA - II Discom S/s. (BHUGAON) S/S * 2) 33 KV OUTLETS - 8 NOS. (2008-09)

163 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

3 220KV NAGPUR 1) ADDL. 1X100 MVA 220/132 KV ICT WITH BAYS Newly Introduced 220/132 kV Level to feed 132 kV BUTTIBORI S/S * Khapri S/s as an alternate source (2008-09) 2) 2 X 132 KV BAYS 3) 220KV BUTTIBORI TO 132KV KHAPRI S/S SCDC LINE - 20 CKT.KM WITH BAY 4 220KV NAGPUR 1) 1X50 MVA 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s BUTTIBORI S/S * is,220/33 - 2 x 50 - 66 load Considering the (2008-09) maximum load reach on the transformer, in event of interruption/outage on any one of the transformer 2) 6X33 KV OUT LETS other transformer should take care of existing load so as to avoid load shedding. 5 220KV GADCHANDUR S/S CHANDRAPUR 1) ADD 1X25 MVA, 220/33KV T/F WITH BAYS Newly Introduced 220/33 kV Level to remove 66/33 (2008-09) 2) 33 KV OUTLETS - 4 NOS. kV Level by introduing 220/33 transformer.

6 220 KV SICOM - CHANDRAPUR 1) ADD 1X 50 MVA, 220/33KV T/FS WITH BAYS Newly Introduced 220/33 kV Level to remove CHANDRAPUR S/S * 220/66 kV Level by introduing 220/33 transformer. (2008-09) 2) 33 KV OUTLETS - 6 NOS.

7 220 KV KANHAN S/S * NAGPUR 1) 1X25 MVA, 132/33KV T/F WITH BAYS Newly Introduced 132/33 kV Level to eliminate 11 (2008-09) kV level from the existing S/s 2) 4 X 33 KV OUTLETS

8 132 KV AMBHORA S/S NAGPUR 1) 1X25 MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s (2008-09) is,132/33 - 2 x 25 - 10 load Considering the maximum load reach on the 2) 33 KV OUTLETS - 4 NOS. transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

9 220 KV BHANDARA BHANDARA 1) ADD 2X25 MVA, 220/33 KV T/F WITH BAYS Newly Introduced 220/33 kV Level to eliminate 11 S/S * kV level from the existing S/s (2008-09) 2) 33 KV OUTLETS - 8 NOS. 10 220 KV AMBAZARI S/S* NAGPUR 1) ADDL. 1X200 MVA 220/132 KV ICT WITH BAYS The eisting transformer capacity available is (2009-10) 220/132 kV,1 X150 MVA AND 1 x 250 MVA and the laod reached is 307 MVA.To avoid loss of supply in 2) 132 KV BAYS - 4 NOS. case of outages or interruptions on any one transformer additional transformer is proposed.

11 220KV KALMESHWAR NAGPUR 1) ADDL. 1X200 MVA 220/132 KV ICT WITH BAYS The eisting transformer capacity available is S/S (2009-10) 220/132 kV,2 X100 MVA and the laod reached is 193 MVA.To avoid loss of supply in case of outages or interruptions on any one transformer additional transformer is proposed. 2) 132 KV BAYS - 4 NOS.

12 132 kV KATOL* Nagpur 1) Add 1 X 25,132/33 kV T/F with bays. Existing transformer capacity available in s/s is 1 X (2009-10) 2) 4 X 33 kV out lets. 12.5, 1 x 25 MVA. And the load reached is 23 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

13 132 kV BESA Nagpur 1) Add 1 X 50 MVA , 132/33 kV T/F with bays. Existing transformer capacity available in s/s is 3 x (2009-10) 2) 6 x 33 kV outlets. 25 MVA. And the load reached is 54 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 14 132 kV GONDIA Gondia 1) Add 1 X 25 MVA, 132/33 kV T/F with bays. Existing transformer capacity available in S/s is 1 X (2009-10) 2) 4 X 33 kV out lets. 25 MVA and load is 24 MVA. Considering tre maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 15 132 kV MADGI Gondia 1) Add 2 X 25 MVA , 132/33 kV T/F with bays. To eliminate 66 kV level. (2009-10) 2) 4 X 33 kV out lets.

164 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

AUGMENTATION OF S/S BY REPLACEMENT OF T/F 1 220KV NAGPUR 1) 2X(200-100) MVA 220/132 KV ICT'S Existing transformer capacity available in S/s KALMESHWAR S/S is,220/132 KV - 2 x 100 MVA and LOAD is 158.4 (2008-09) * * MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any 2) 132 KV BAYS - 2 NOS. one of the transformer other transformer should take care of existing load so as to avoid load 3) 132 KV LINE - 40 KM shedding. 2 132 KV TALEGAON S/S WARDHA 1) REP. 1 X (25-10) 132/33 KV T/FS Existing transformer capacity available in S/s (2008-09) * * is,132/33 KV - 2 x 10 MVA and load is 14 2) 33KV OUTLETS - 2 NOS. MVA.Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

3 132KV SAONER S/S * NAGPUR 1) 1X(50-25)MVA, 132/33KV T/FS Existing transformer capacity available in S/s (2008-09) is,132/33 KV - 2 x 25 MVA and load is 20 MVA.The 2) 33KV OUTLETS - 2 NOS. transformers are replaced to meet anticipated load growth. 4 132KV MANSAR S/S * NAGPUR 1) 2X(50-25)MVA, 132/33KV T/F Existing transformer capacity available in S/s (2008-09) is,132/33 KV - 1 x 25 MVA and load is 19.55 MVA,132/33 KV - 1 x 10 MVA and load is Nil 2) 33KV OUTLETS - 2 NOS. Considering the maximum load reach on the transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding.

5 132KV NAGPUR-I NAGPUR 1) 2X(50-25)MVA, 132/33KV T/FS Existing transformer capacity available in S/s MANKAPUR S/S * is,132/33 KV -3 x 25 MVA and load is 58 (2008-09) MVA.Considering the maximum load reach on the 2) 33KV OUTLETS - 2 NOS. transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 6 132KV BRAHMAPURI S/S CHANDRAPUR 1) 1X(50-25)MVA, 132/33KV T/FS Existing transformer capacity available in S/s * is,132/33 KV - 2 x 25 MVA and load is 35.1 MVA. (2008-09) Considering the maximum load reach on the 2) 33KV OUTLETS - 2 NOS. transformer, in event of interruption/outage on any one of the transformer other transformer should take care of existing load so as to avoid load shedding. 7 400KV KORADI S/S NAGPUR 1) 1X(500-315) MVA, 400/220 KV ICT Existing Transformer capacity available is 400/220 (2009-10) kV, 1 X 300 MVA and load reached is 263 MVA.The 2) 220 KV BAYS - 2 NOS. transformer is replaced to meet the anticipated load growth. 8 220KV KALMESHWAR NAGPUR 1) 1X(200-100) MVA 220/132 KV ICT'S Existing transformer capacity available in S/s is S/S* 220/132kV, 1 x 100 MVA and the load reached is (2009-10) 88MVA.The transformer is replaced to meet the 2) 132 KV BAYS - 2 NOS. anticipated load growth. 9 220kV AMBAZARI S/S* NAAGPUR 1) 1 X (250-150) ,220/132KV ICT Existing transformer capacity available in S/s is (2009-10) 220/132kV, 1 x 150 MVA and the load reached is 2) 132 KV BAYS - 2 NOS. 124MVA.The transformer is replaced to meet the anticipated load growth. 10 220 KV KANHAN S/S NAGPUR 1) 1 X ( 200-100) ,220/132KV ICT Existing Transformer capacity available is 220/132 (2009-10) kV, 2 X 100 MVA and load reached is 133 MVA.The transformer is replaced to meet the anticipated load 2) 132 KV BAYS - 2 NOS. growth. 11 132 kV KATOL* Nagpur 1) 1 X (25-12.5)MVA, 132/33 kV T/F Existing transformer capacity available in s/s is 2 X (2009-10) 2) 2 X 33 kV out lets. 12.5 MVA. And the load reached is 23 MVA The transformer is replaced to meet anticipated load growth. 12 132 kV MANSAR* Nagpur 1) 1 X (50-25) MVA, 132/33 kV T/F Existing transformer capacity available in s/s is 1 X (2009-10) 2) 2 X 33 kV out lets. 50, 1 X 25 MVA. And the load reached is 30 MVA The transformer is replaced to meet anticipated load growth. 13 132 kV TALEGAON (2009- Wardha 1) 1 X (25-10) MVA, 132/33 kV T/F Existing transformer capacity available in s/s is 1 X 10) 2) 2 X 33 kV out lets. 10, 1 X 25 MVA. And the load reached is 19 MVA The transformer is replaced to meet anticipated load growth.. 165 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

14 132 kV MANKAPUR (NGP- Nagpur 1) 1 X (50-25) MVA, 132/33 kV T/F Existing transformer capacity available in s/s is 1 X I)* 2) 2 X 33 kV out lets. 50, 2 X 25 MVA. And the load reached is 51 MVA (2009-10) The transformer is replaced to meet anticipated load growth. 15 132 kV PARDI (NGP-II)* Nagpur 1) 1 X (50-25) MVA, 132/33 kV T/F Existing transformer capacity available in s/s is 1 X (2009-10) 2) 2 X 33 kV out lets. 50, 2 X 25 MVA. And the load reached is 30 MVA The transformer is replaced to meet anticipated load growth.

ORC WORKS 1 220KV MATRADEVI S/S CHANDRAPUR 1) 2X25 MVA, 220/33KV T/FS WITH BAYS Matradevi-220kV S/S is considered for reducing (2008-09) loading on Chandrapur and Chandur 220kV S/S. 2) 220KV LILO OF CHANDRAPUR GCR - This Substation is proposed on LILO of existing GADCHANDUR AT MATRADEVI Chandrapur–Chandur 220kV line in year 2007-08. By the commissioning of this substation, voltage 3) 33KV OUTLETS-4 NOS. profile will improve.

166 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

NEW SCHEMES 1 220KV TADALI S/S CHANDRAPUR 1) 2X50MVA, 220/33KV T/FS WITH BAYS TADALI -220kV S/S is considered to meet the load (2010-11) growth in Chandrapur Circle. 2) LILO ON 220KV CHANDRAPUR -PARLI FOR TADALI -1 KM 3) 12X33KV OUTLETS 2 220 KV NAGPUR 1) 2 X 100 MVA, 220/132 KV T/FS WITH BAYS Present recorded peak load on Katol-132kV, Warud KATOL II S/S –132kV S/S is 50MW and 40MW. It is anticipated 2) 220KV D/C KALMESHWAR-KATOL-40KM (2010-11) by the year 2010-11 the load will reach to about WITH BAYS 130MW. Hence it is necessary to go in for 220kV 3) 132 KV OUTLETS - 4 NOS 132 KV D/C sub-station at Katol. By the commissioning of this INTERLINK BETWEEN KATOL I TO KATOL II- substation, voltage profile will improve to 0.95pu 10 KM WITH BAYS from 0.92pu. 4) 132KV LINE FROM KATOL - SAONER SCDC - 49KMS 5) 4KM UG CABLE 3 132 KV JAT-TARODI S/S NAGPUR 1) 132 KV U.G. CABLE - 10 CKT. KM NAGPUR - II Jat Tirodi-132kV S/S is considered for strengthning (2010-11) TO JAT - TARODI SCDC - 5 CKT KM the Nagpur ring main. 2) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS 3) 8 X 33KV OUTLETS. 4 132KV MORGAON GONDIA 1) 2X25MVA 132/33KV T/FS WITH BAYS Morgaon Arjuni is upgraded to 132kV S/S to reduce ARJUNI S/S the eliminate 66kV network in Nagpur circle. 2) 132KV LAKAHNDUR - MORGAON ARJUNI D/C (2010-11) LINE - 20 KMS 3) 8X33KV OUTLETS

5 132 KV WARDHA 1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS Seloo-132kV S/S is considered to meet the load SELOO S/S growth in Chandrapur Circle. 2) 132 KV S/C D/C WARDHA-II-SELOO-18 KM (2010-11) WITH BAYS 3) 33 KV OUTLETS - 8 NOS

6 132KV TUMSAR S/S GONDIA 1) 2X25MVA 132/33KV T/FS WITH BAYS To eliminate 66 kV level. (2011-12) 2) 132KV GONDIA - TUMSAR D/C LINE - 44 KMS

3) 132kV MADGI - TUMSAR DC LINE -7 KM

7 765 KV KORADI-III S/S NAGPUR 1) 765/400 KV, 4 X 500 MVA , 1-Phase ICT WITH Evacuation of Generation coming in nearby area (2012-13) BAYS 2) 765 KV KORADI -AKOLA , 2 X S/C QUAD LINE - 480 KM 3) INTERCONNECTING LINES BETWEEN 400 KV KORADI-765 KV KORADI -15 KM ORC SCHEMES 1 132 KV PAGHORA S/S NAGPUR 1) 2 X 25 MVA T/F WITH BAYS 132 KV Paghora substation is proposed to cater the (2010-11) load of LIS. 2) 33 KV OUTLETS - 8NOS.

3) LILO OF 132KV KARDHA-ASGAON LINE AT PAGHORA- 10KM 2 132KV MOKHABARDI NAGPUR 1) 2 X 25 MVA T/F WITH BAYS 132kV Mokhabardi substation is proposed to cater (2010-11) the load of LIS. 2) 33 KV OUTLETS - 8NOS. 3) LILO OF 132KV BHANDARA-AMBHORA LINE AT MOKHABARDI-10KM 66KV LEVEL ELIMINATION 1 ELIMINATION OF 66KV NAGPUR A 66KV BHARSHINGI A.132kv Bharsingi S/stn is proposed during 2008- LEVEL IN NAGPUR (U) 66/33KV 1X5MVA, 66/11KV 1X5MVA,1X2MVA 09.To eliminate 66 kV Bharshingi s/stn, new 33 kv DISTRICT s/stn alongwith 2x5 MVA T/F and 33 kv line from (2011-12) 132 kv Bharshingi s/stn is to be established by Discom at Bharshingi after complition of above said work 66/11kv s/stn at Bharshingi will be absolate.

B 132/66 KV KATOL B. After getting above work at Sr.No. A 132/66 kv 132/66 KV 1X25MVA,1X10MVA T/Fs at Katol will be absolate. C 132/66 KV WARUD C. After getting above work at Sr.No. A 132/66 kv 132/66KV 1X12MVA T/Fs at Warud will be absolate.

167 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

2 ELIMINATION OF 66KV NAGPUR A 66 KV KANHAN W/W A.To eliminate 66/11 KV substation at 66 kV LEVEL IN NAGPUR (U) 66/11 KV, 1X10 MVA Kanhan, new 33 /11kv s/stn alongwith 3x5 MVA T/F DISTRICT and 33 kv line from 220 kv Kanhan s/stn is to be (2011-12) established by Discom at Kanhan. After complition of above said work 66/11kv s/stn will be absolate.

3 ELIMINATION OF 66KV NAGPUR A 66/11KV SAHULI A.132 kv Sahuli s/stn is proposed during 2009-10. LEVEL IN NAGPUR (U) To eliminate 66 kV Sahuli s/stn. new 33 /11kv s/stn DISTRICT alongwith 2x10 MVA T/F and 33 kv line from 132 kv (2011-12) Sahuli s/stn is to be established by Discom at 66/11 KV, 2x10MVA Sahuli. After complition of above said work 66/11kv s/stn will be absolate.

B 132 KV PARDI B.After getting above work done at Sr.No. A the 2x50 MVA 132/66 kv T/F at Pardi will become 132/66 KV , 2X50 MVA absolate. 4 ELIMINATION OF 66KV NAGPUR A 66 KV UMRED A. 220/33 KV Umred s/stn is already commissioned. LEVEL IN NAGPUR (U) To eliminate 66 kV Umred s/stn, new 33 /11kv s/stn DISTRICT alongwith 2x5 MVA T/F and 33 kv line from 220kv (2011-12) Umred s/stn is to be established by Discom at 66/33KV 1x10MVA, 66/11KV 2x5MVA Umred. After complition of above said work 66/11kv Umred s/stn will be absolate.

5 ELIMINATION OF 66KV CHANDRAPUR A 66 KV BHANDAK A. To eliminate 66 kV Bhandak S/stn, new 33 LEVEL IN CHANDRAPUR 66/11 KV 1X 10MVA, /11kv s/stn alongwith 2x10 MVA T/F and 33 kv line DISTRICT 1 X5 MVA from 220 kv Chandrapur MIDC s/stn is to be (2010-11) established by Discom at Bhandak after complition of above said work 66/11kv s/stn will be absolate.

B 66KV GHUGHUS B. 66kv Ghuggus s/stn is feeding to 66kv consumers. (1.66kV WCL Majri 2. 66 kV LLoyd metal). 66 kv Ghughus s/stn can be eliminated only after connecting these 66 kv consumers on 66/11 KV 1 X 5 MVA, 220/33/11 kv.Further new 33 kv s/stn alongwith 1 X 3 MVA 2x10 MVA T/F and 33 kv line from 220 kv Chandrapur MIDC s/stn to be established by Discom at Ghughus after complition of above said work 66/11 kv T/Fs at Ghughus s/stn will be absolate.

C 66 KV CHANDRAPUR MIDC C. To eliminate 66 kV Chandrapur MIDC new 33 kv (66/11 KV, 2 X 5 MVA) s/stn alongwith 2x10 MVA T/F and 33 kv line from 220 kv Chandrapur MIDC s/stn to be established by Discom at chandrapur MIDC after complition of above said work 66kv s/stn at Chandrapur MIDC will be absolate. D 66 KV WANI D. 220 kv Wani s/stn is proposed during 2008- 09.66kv Wani s/stn is feeding 66kV Ghuggus s/stn which is feeding to 66kv consumers (1. 66kV WCL Majri 2. 66 kV LLoid metal).66 kv level at Wani can be eliminated only after connecting these 66 kv consumers on 220/33/11 kv.Till the conversion of 66/33 KV 2 X10 MVA, 66/11 KV existing 66 KV consumers to 220/33/11/KV, 66 kV 2 X10 MVA Wani s/stn will act as a switching s/stn.Further 2 nos of new 33 kv s/stn alongwith 2x10 MVA T/F each and 33 kv line from 220 kv Wani s/stn is to be established by Discom considering load centre at Wani. After complition of above said work 66/33 kv & 66/11 kv T/Fs at Wani s/stn will be absolate.

E 220/66 KV WARORA E. After getting the work at Sr.No. A to D 220/66 kv 220/66 KV 2 X 50 MVA, T/F at Warora will be absolate. 66/11, 1X10 MVA

168 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

6 ELIMINATION OF 66KV CHANDRAPUR A 66KV SHASTRINAGAR A.To eliminate 66 kV shastrinagar s/stn. new 33 LEVEL IN CHANDRAPUR /11kv s/stn alongwith 3x10 MVA T/F and 33 kv line DISTRICT(2010-11) from 220 kv SICOM s/stn is to be established by Discom at Shastrinagar. After complition of above 66/33 KV, 2X10 MVA, 66/11KV, 2X10 MVA said work 66 KV Shastrinagar s/stn will be absolate.

B 66/11KV CHANDRAPUR TPS B. To eliminate 66 kV Chandrapur TPS S/stn., new 33 /11kv s/stn alongwith 2x10 MVA T/F and 33 kv line from 220 kv Chandrapur MIDC s/stn is to be established by Discom at Chandrapur TPS after 66/11 KV 2X10MVA complition of above said work 66kv Chandrapur TPS s/stn will be absolate. After getting work at Sr.No. A & B the 66 kv Chandrapur TPS s/stn will be absolate.

7 ELIMINATION OF 66KV CHANDRAPUR A. 66 KV BALLARSHA A. 220kv Ballarsha s/stn is to be commissioned by LEVEL IN CHANDRAPUR 66/11 kv 1x14MVA ,1x12.5MVA 2009-10.A 66 kv consumer Ballarpur Paper Mill is DISTRICT feeded from 66 kv Ballarsha s/stn.To eliminate 66 (2010-11) kV Ballarsha s/stn. this 66kv consumer is to be connected on 220/33/11 kv . Further a new 33 /11kv s/stn alongwith 3x10 MVA T/F and 33 kv line from 220 kv Ballarsha s/stn to be established by Discom at Ballarsha. After complition of above said work the 66/11kv Ballarsha s/stn will be absolate.

B. 66 KV GONDPIMPRI B. To eliminate 66 kV Gondpimpri S/stn, new 33 /11kv s/stn alongwith 2x5 MVA T/F and 33 kv line 66/11 KV 2 X5 MVA from 132 kv Aashti s/stn is to be established by Discom at Gondpimpri. After complition of above said work 66/11kv Gondpimpri s/stn will be absolate. C 66KV ALLAPALLI C. 132 kv Allapalli s/stn is to be commissioned by 66/11KV , 2X1.5MVA 2009-10.To eliminate 66 kV Allapalli s/stn, new 33 /11kv s/stn alongwith 1 x 3 MVA T/F and 33 kv line from 132 kv Allapalli s/stn is to be established by Discom at Allapalli. After complition of above said work the 66/11kv Allapalli s/stn will be absolate.

D 66 KV YETAPALLI D. 132 kv Allapalli s/stn is to be commissioned by 66/11KV , 1X5MVA, 1X3MVA 2009-10.To eliminate 66 kV Yetapalli s/stn, new 33 /11kv s/stn alongwith 2x5 MVA T/F and 33 kv line from 132 kv Allapalli s/stn to be established by Discom at Yetapalli. After complition of above said work the 66/11kv Yetapalli s/stn will be absolate.

E 66 KV SIRONCHA E.New 132 KV Jafarabad substation is proposed 66/11KV 1X5MVA,1X1MVA, 66/33KV,1X5MVA during 2009-10. To eliminate 66/33/11 KV AT 66 kV Sironcha new 33 /11kv s/stn alongwith 2x3 MVA T/F and 33 kv line from 132 kv Jafrabad s/stn is to be established by Discom at Sironcha. After complition of above said work 66/11kv Sironcha s/stn will be absolate.

F 66KV JAMALGATTA F.New 132 KV Jafarabad substation is proposed during 2009-10.To eliminate 66/11 KV AT 66 kV Jamalgatta new 33 /11kv s/stn alongwith 2x3 MVA T/F and 33 kv line from 132 kv Jafrabad s/stn (Proposed) to be established by Discom at 66/11KV , 1X1MVA Jamalgatta. After complition of above said work 66/11kv Jamalgatta s/stn will be absolate

G 220 KV SICOM G.A 66 kv consumer WCL at Sashti is feeding from 220/66KV, 1X50 MVA 220/66 kv SICOM s/stn. This consumer is to be connected on 220/33/11 kv. After conversion of the existing 66 KV consumer 220/66 KV ICT at Chandrapur SICOM will be absolate. After getting work done at Sr.No. A to G the 1x50 MVA 220/66 KV T/F at SICOM will be absolate.

169 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

8 ELIMINATION OF 66KV CHANDRAPUR A 66 KV MANIKGHAD (EHV CONSUMER) A.The 66kv manikgadh s/ckt. Consumer is feeded LEVEL IN CHANDRAPUR from 220/66 kv Gadchandur s/stn. DISTRICT(2010-11) B 66 KV L & T (EHV CONSUMER) B.The 66kv L&T ( awarpur) D/ckt. consumer is feeded from 220/66 kv Gadchandur s/stn.

C 220/66/33/11 KV GADCHANDUR C.To eliminate 66/33 kv 1x10MVA & 66/11KV 2X5 220/66KV 2X150MVA , 66/33KV 1X10MVA, MVA T/F at 220 kv Gadchandur s/stn, new 33 kv 66/11KV 2X5 MVA s/stn with 2x10MVA T/F with 33 kv line from 220 kv Gadchandur s/stn is to be established by DISCOM at Gadchandur. After completing the said work the 66/33 kv & 66/11 kv T/F at Gadchandur will be absolate. After connecting the above 66 kv consumers at Sr.No. A, B on 220/33/11kV & after completing work at Sr.No.C the 2 x 150 MVA 220/66 KV ICT at 220 KV Gadchandur s/stn. Will be absolate.

ADDITIONAL LINK LINES ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE 1 132KV LINK LINE CHANDRAPUR 1) 132 KV SINDEWAHI - BRAHMAPURI SCDC 132kV Sindewahi S/S is fed from 132kV Mul S/s (2010-11) LINE -50 KM WITH BAYS with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 2 132KV LINK LINE CHANDRAPUR 1) 132KV VIRUR - ASHTI SCDC LINE - 55 KM 132kV Ashti S/S is fed from 132kV Virur S/s with (2010-11) WITH BAYS S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 3 132KV LINK LINE GONDIA 1) 132 KV LILO OF GONDIA - AMGAON (TSS) AT To avoid overloading on 132 kV Amgaon-Gondia (2010-11) AMGAON LINE - 10 KM S/c the additional 132 kV Amgaon - Gondia S/c is proposed 4 132KV LINK LINE BHANDARA 1) 2ND CIRCUIT STRINGING OF EXISTING 132 132kV Asgaon S/S is fed from 132kV Kardha S/s (2010-11) KV KARDHA - ASGAON SCDC LINE - 58 KM with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 5 132KV LINK LINE GONDIA 1) 132 KV PARDI - SAHULI SCDC LINE - 40 KM 132kV Gondia S/S is fed from 132kV Kaulewada (2011-12) WITH BAYS S/s with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line 6 132KV LINK LINE WARDHA 1) 132 KV DEOLI -WARDHA-II SCDC LINE - 28 132kV Deoli S/S is fed from 132kV Wardha-II S/s (2011-12) KM (ONLY STRINGING) with S/c line. Hence to provide uninterrupted supply during planned outages it is necessary to add proposed line ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY 5 132KV LINK LINE NAGPUR 1) REPLACEMENT OF CONDUCTOR AMBAZARI- Since the existing 132kV Ambazari - Nagpur-I line is (2012-13) NAGPUR-I (MANKAPUR) -9 KM loaded to an extent of 99 MW during Non- Coinsident peak condition and there is no space in Ambazari S/s. It is anticipated the load will reach to about critical value in future. Hence it is necessary to propose additional line to meet additional load growth and contingency. STRENGTHENING FOR EVACUATION ARRANGEMENT 1 400KV LINK LINES NAGPUR 1) 400KV DC LINE FROM 400KV KORADI-II TO To have evacuation facility . (2011-12) WARDHA - 120KM 2 220KV LINK LINE CHANDRAPUR 1) 22OKV WANI - WARORA D/C LINE -35KM To have evacuation facility at Warora S/S (2011-12) AUGMENTATION OF S/S BY ADDITION OF T/F AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE 1 220KV VIRUR S/S CADCHIROLI 1) 1 X 100 MVA, 220/132KV ICTS WITH BAYS The existing transformer capacity available is (2012-13) 2) 132 KV BAYS - 2 NOS. 220/132 kV,1 X100 MVA and the laod reached is 55 MVA.To avoid loss of supply in case of outages or interruptions on any one ICT additional ICT is proposed. 2 400KV CHANDRAPUR-I Chandrapur 1) 1X50MVA, 220/33KV TF WITH BAYS To have redundancy (2011-12) 2) 33 KV OUTLETS - 6 NOS. 3 220 kV SICOM Chandrapur 1) Add 2 X 25 MVA, 220/33 kV T/F with bay. To eliminate 66 kV level. (2011-12) 2) 8 X 33 kV out lets 4 220 kV HINGANGHAT Wardha 1) Add 1 X 25 MVA, 132/33 kV T/F with bay. Existing Transformer capacity avaible is 1 X 25 (2012-13) 2) 4 X 33 kV out lets MVA. & load reach is 5 MVA.To avoid loss of supply in case of outages or interruptions on transformer. 170 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE SR NAME OF THE DISTRICT TOTAL SCOPE OF WORK REMARKS / PURPOSE OF SCHEME NO SUBSTATION

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT/T/F 1 220 kV BUTTIBORI-I Nagpur 1) Add 1 X 50 MVA , 220/33 kV T/F with bays. Existing transformer capacity available in S/s is 2 X (2011-12) 2) 6 X 33 kV out lets. 50 MVA and load is 68 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 2 220 kV SICOM Nagpur 1) Add 1 x 50 MVA, 220/22 KV T/F with bays. Existing transformer capacity available in S/s is 2 x (2013-14) 2) 6 x 22 kV outlets 40 and load reach is 46 MVA. The T/F is replaced to meet anticipated load growth 3 220 kV WARDHA - I (2012- Wardha 1) Add 1 X 50 MVA, 220/33 kV T/F with bays. To eliminate 66 kV level. 13) 2) 6 X 33 kV out lets. AUGMENTATION OF S/S BY REPLACEMENT OF T/F 1 220KV KALMESHWAR NAGPUR 1) 1X(200-100) MVA 220/132 KV ICT'S Existing transformer capacity available in S/s is S/S 2) 132 KV BAYS - 2 NOS. 220/132kV, 1 x 100 MVA and the load reached is (2010-11) 90MVA.The transformer is replaced to meet the anticipated load growth. 2 220 KV KANHAN S/S NAGPUR 1) 1 X ( 200-100) ,220/132KV ICT Existing Transformer capacity available is 220/132 (2010-11) 2) 132 KV BAYS - 2 NOS. kV, 1 X 100 MVAand 1 X 200 MVA and load will reach 154 MVA.The transformer is replaced to meet the anticipated load growth. 3 132 kV AMGAON Gondia 1) 2 X (50-25)MVA,132/33 kV T/F Existing transformer capacity available in s/s is 2x (2010-11) 2) 33 KV PUTLETS - 2 NOS. 25 MVA. And the load reached is 25 MVA Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load 4 132 kV MOUDA Nagpur 1) 2 X (50-25)MVA,132/33 kV T/F Existing transformer capacity available in S/s is 2 X (2010-11) 2) 33 KV OUTLETS - 2 NOS. 25 MVA and load is 24 MVA. Considering the maximum load reached on the transformer in the event of interruptions/outage on any one of the transformer other transformer should take care of existing load

5 132 kV BESA * Nagpur 1) Replac. (50-25) MVA 132/33 kV T/F Existing transformer capacity available in s/s is 3 X 2) 2x 33 kV outlets. 25 MVA. And the load reached is 24 MVA The (2010-11) transformer is replaced to meet anticipated load growth. 6 132 kV PARDI (NGP-II) Nagpur 1) 1 X (50-25)MVA, 132/33 kV T/F Existing transformer capacity available in s/s is 1 X (2010-11) 2) 2 X 33 kV out lets. 50, 2 X 25 MVA. And the load reached is 30 MVA The transformer is replaced to meet anticipated load growth.. 7 220 kV KALAMESHWAR Nagpur 1) 1 X (50-25) MVA, 220/33 kV T/F Existing transformer capacity available in s/s is 2 X (2010-11) 2) 2 X 33 kV out lets. 25 MVA. And the load reached is 21 MVA The transformer is replaced to meet anticipated load growth..

8 220 kV KALAMESHWAR Nagpur 1) 1 X (50-25) MVA, 220/33 kV T/F Existing transformer capacity available in s/s is 2 X (2011-12) 2) 2 X 33 kV out lets. 25 MVA. And the load reached is 21 MVA The transformer is replaced to meet anticipated load growth.. 9 132 kV HINGNA-II (MIDC) Nagpur 1) 1 X (50-25) MVA, 132/33 kV T/F Existing transformer capacity available in s/s is 2 X (2011-12) 2) 2 X 33 kV out lets. 25 MVA. And the load reached is 20 MVA The transformer is replaced to meet anticipated load growth.. 10 132 kV HINGNA-II (MIDC) Nagpur 1) 1 X (50-25) MVA,132/33 kV T/F Existing transformer capacity available in s/s is 2 X (2012-13) 2) 2 X 33 kV out lets. 25 MVA. And the load reached is 20 MVA The transformer is replaced to meet anticipated load growth.. * COMMISSIONED IN 2009 - 10. ** 1 No. TF. COMMISSIONED IN 2009 - 10.

171

CAPACITOR & REACTOR REQUIREMENT

172 STU/TRANS/DOC-04 - WEF 01.04.2010

CAPACITOR REQUIREMENT DURING 2010-11

Capacitor Sr No Name of S/s Voltage (MVAR) 1 NEWASE 132 kV 10 2 SATANA 132 kV 20 3 AKOLE 132 kV 20 4 RAHATNE 132 kV 10 5 VARASGAON 132 kV 10 6 KALWAN 132 kV 10 TOTAL 80

REACTOR REQUIREMENT LINE REACTOR

Line Reactor Line (MVAR) Sr No Name of S/s Name of Line Length/ckt (km) From To bus Bus 2 x 240 (7 x 80 1 765 kV TIRODA 765 kV Tiroda - Koradi-III 2 x S/c Line 120 - MVAR 1-ph unit) 2 x 240 2 x 240 (7 x 80 (7 x 80 2 765 kV KORADI - III 766 kV Koradi-III - Akola-II 2 x S/c Line 282 MVAR MVAR 1-ph unit) 1-ph unit)

2 x 240 2 x 240 767 kV Akola-II - Aurangabad (PG) 2 x S/c (7 x 80 (7 x 80 3 765 kV AKOLA - II 210 Line MVAR MVAR 1-ph unit) 1-ph unit)

BUS REACTOR Sr No Name of S/s Name of Line

2 x 240 1 765 kV KORADI - III (7 x 80 MVAR 1-ph unit)

2 x 240 2 765 kV AKOLA - II (7 x 80 MVAR 1-ph unit)

173

RELIANCE INFRASTRUCTURE LTD.

174 STU/TRANS/DOC-04 - W.E.F 01/04/2010

RELIANCE INFRASTRUCTURE LTD. (TRANSMISSION) FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15 TECHNICAL ABSTRACT (R Infra-T)

Sr. No. Voltage Level 2010-11 2011-12 2012-13 2013-14 2014-15 Total New Sub-Station (Nos.) 1 765kV 0 0 0 0 0 0 2 400kV 0 0 0 0 2 2 3 220kV 2 3 4 3 3 16 4 132kV 0 0 0 0 0 0 5 110/100kV 0 0 0 0 0 0 6 HVDC IGBT Technology 0 2 0 0 0 2 Total 2 5 4 4 5 20

Transmission Lines (Ckt kM) Tansmission lines for New Sub -Station 1 765kV 0 0 0 0 0 0 2 400kV 0 0 0 0 152 152 3 220kV 11.8 49 73 62 42 248.8 4 132kV 0 0 0 0 0 0 5 110/100kV 0 0 0 0 0 0 6 HVDC Cable 0 300 0 0 0 300 Total (Ckt kM) 11.8 349 73 73 194 700.8 Transmission lines for s/s where only single source or single ckt is available 1 765kV 0 0 0 0 0 0 2 400kV 0 0 0 0 0 0 3 220kV 0 0 0 16 44 60 4 132kV 0 0 0 0 0 0 5 110/100kV 0 0 0 0 0 0 6 HVDC Cable 0 0 0 0 0 0 Total (Ckt kM) 0 0 0 16 44 60 Transmission lines to have alternate source 1 765kV 0 0 0 0 0 0 2 400kV 0 0 0 0 0 0 3 220kV 10 0 0 0 0 10 4 132kV 0 0 0 0 0 0 5 110/100kV 0 0 0 0 0 0 6 HVDC Cable 0 0 0 0 0 0 Total (Ckt kM) 10 0 0 0 0 10

Capacity Addition (MVA) Capacity addition by New Sub Station 1 765kV 0 0 0 0 0 0 2 400kV 0 0 0 0 1800 1800 3 220kV 625 1125 1250 750 750 4750 4 132kV 0 0 0 0 0 0 5 110/100kV 0 0 0 0 0 0 6 HVDC Cable 0 2400 0 0 0 2400 Total 625 3525 1250 1000 2550 8950

175 STU/TRANS/DOC-04 -W.E.F 01/04/2010

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 R-INFRA POWER CO. LTD. SR NAME OF THE DISTRICT Total Scope of Work Justification NO SUBSTATION A) ONGOING SCHEMES 1 220/33 kV Chembur EHV Mumbai 1)3X 125 MVA ,220/33 kV T/F With 220 kV GIS Bays 1) STU & MERC approval received. 2) Major equipment order placed. 3) 30% Station 2) D/C 3X1/c 1200sqmm 220 kV cables 8.5KM/ckt With 220kV GIS Bays of Civil work is completed. 4)Outlets released on firm basis to Rinfra-D at Commissioning (2011-12) (i)Raheja Acropois (ii) Natwar Parekh (iii) HDIL Chunabhatti (iv) Infrastructure 3) 3X220 kV GIS Bays at MSETCL Trombay Venture (v) Chembur Trading Corporation. Targeted to be commissioned by 2011-12

2 220/33 kV Nagariniwara EHV Mumbai 1)3X125MVA,220/33 kV T/F with 220 kV GIS bays STU & MERC approval received. Approval from forest awaited to take up job Station 2) 2x 220 kV GIS bay at MSETCL Borivali of cable laying. This scheme will relieve overload of Aarey-Borivali Tie lines. (2012-13) 3) 9X 220 kV GIS bay at Nagari Niwara Targeted to be commissioned by 2012-13 4) 2X 220 kV GIS bay at Aarey 5)3X 33 kV GIS 13 pannel board 6)D/C 3X1/c 1200sqmm ,220 kV cable -15KM/ckt, (MSETCL Borivali to Aarey via Nagari Niwara

3 220/33 kV Borivli EHV Station Mumbai 1)3X125MVA, 220/33 kV T/F with 220 kV GIS bays 1) STU & MERC approval received. 2) Orders processed for GIS, 125MVA (2011-12) 2) 3x 220 kV GIS bay at MSETCL Borivali Transformers & 220kV cable. 3) Civil work initiated. 4) Outlets released on firm 3) 10X 220 kV GIS bay at Rinfra-Borivali basis to Rinfra-D at (i)Kanakia CCI (ii)Neev Infrastructure (iii)Lokhandwala 4)D/C 3X1/c 1200sqmm , 220 kV cable -3.5KM/ckt, (MSETCL Borivali to (iv)Vasant Marvals (v) EKTA Meadows (vi) Vinod Silk Mill. Part commissioning RInfra Borivali) targeted by March-11

5) 3X 33 kV GIS 13 pannel board 6) LILO of TPC Borivli to Rinfra Aarey one line at Rinfra-Borivli) 4 220/33 kV Saki EHV Station Mumbai 1)3X125MVA,220/33 kV T/F with 220 kV GIS bays 1) STU & MERC approval received. 2) Major equipments & 220kV cable order (2010-11) placed. 3) 40% civil work is completed. 4) HDPE pipes are laid for cable laying. 5)Relieve transformers at Aarey. 6)Outlets released on firm basis to 2)2X 220kV GIS bay at Aarey Rinfra-D at (i)Kanakia Chandivali (ii)Saki R/s (iii) Metro Rail (iv)Akruti City (v) 3)9X 220 kV GIS bay at Saki Sumer Corporation (vi) Eliza Chandivali (vii) Seven Hills Health Care 4)D/C 3X1/c 1200sqmm ,220 kV cable 6 KM/ckt,(Aarey to Saki) (viii)Nahar Shakti. Targeted to be commissioned by 2010-11 5)3X 33 kV GIS 13 pannel board

5 220/33 kV Gorai EHV Station Mumbai 1)3X125MVA,220/33 kV T/F with 220 kV GIS bays 1) STU & MERC approval received. 2) Major equipment order placed. 3) Commissioning(2011-12) 2)9X 220 kV GIS bay at Gorai Building civil work is in progress. 4) HDPE pipes are laid for cable laying. 4) 3)3X 33 kV GIS 13 pannel board Forest approval received for cable laying job. However, station will be 4)D/C 3X1/c 1200sqmm , 220 kV cable 12.56 KM/ckt,(MSETCL Borivali to commissioned by LILO of existing Ghodbunder-Versova line. 5)Outlets Gorai & Gantry to Gorai) released on firm basis to Rinfra-D at (i) Kanti Park (ii) Universal SRA (iii)MHADA Sector 8 (iv) KIE-5 (v) CPWD (vi) East & West RNA Park. Part 5) LILO of Versova Godbunder 220 kV OH line SC at Gorai ( near Tower commissioning targeted by March-11. no 307)

6 220 /33kV Goregaon EHV Mumbai 1)2X125MVA, 220/33 kV T/F with 220 kV GIS bays 1) STU & MERC approval received. 2) Major equipment orders are placed. 3) Station 2)9X 220 kV GIS bay at Goregaon 40% civil work is completed. 4) Relieve transformers at Versova 5)Outlets (2010-11) 3)2X 33 kV GIS 13 pannel board released on firm basis to Rinfra-D at (i) Elanza (ii) Andhri (iii) SRA Goregaon 4)LILO of Aarey -Versova D/C lines at Goregaon (iv) C B Sons (v) Oshiwara SRA (vi) Ozone (v) Emgeen (vi) Vijay Associates, Oshiwara.Targeted to be commissioned by 2010-11

7 220/33 kV Dahisar Housing EHV Mumbai 1)3X125MVA,220/33 kV T/F with 220 kV GIS bays 1) STU & MERC approval received. 2)Lad procurement is under legal vetting.. Station 2)2X 220 kV GIS bay at Ghodbunder 3) Specifications for PR ready. 4) Relieve transformers at (2012-13) 3)9X 220 kV GIS bay at Dahisar Housing Ghodbunder.Targeted to be commissioned by 2012-13 4)3X 33 kV GIS 13 pannel board 5)D/C 3X1/c 1200sqmm , 220 kV cable 6.5 KM/ckt,(Rinfra Ghodbunder to Dahisar Housing)

8 Procurrement of Land for Mumbai / Procurrement of Land for costruction of proposed EHV stations at MERC approval received. Land procurement is in progress. costruction of proposed EHV Thane Ghodbunder, Aarey, Irla, Bhayander, Dahisar, KIE, Kandivli, Malavani stations HVDC IGBT(Connectivity from MSETCL New Padghe-II 400 kV EHV (2012-13) Station) , Nagari Niwara, Valnai Goregaon, Khar Danda, Vikhroli.

B NEW Schemes 220kV EHV Stations 1 220/33 kV Airport EHV Station Mumbai 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays STU approval received & basic engineering work completed. DPR submitted ( 2012-13) 24 Months after to MERC. As per MERC Standard Of Performance of distribution Licensees, MERC Approval 2)2X 220 kV GIS bay at Aarey period for giving supply and determination of compensation Regulations, 3)2X 220 kV GIS bay at Versova 2005, 2 bays has been considered for loads by MAIL as the requirement of load is above 5MVA. Existing 50 MVA load is fed from Aarey is to be 4)10X 220 kV GIS bay at Airport relocated at Airport. To meet new load from this area RInfra-D has requested 5)2X 33 kV GIS 13 pannel board for additional 6 nos of 33kV outlets.This station is proposed to meet future 6)D/C 3X1/c 1200sqmm ,220 kV cable 5 KM/ckt (Aarey to Airport) growth, to meet transformation redundancy at Aarey ,Reduce losses, 7)D/C 3X1/c 1200sqmm ,220 kV cable 15 KM/ckt( Versova to Airport) Enhance reliability.

2 220/33 kV Golibar EHV Station Mumbai 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays RInfra-D indicated the requirment of additional 132MW load for SRA projects and commercial complex in Santacruz (E) & Khar (E) area required 17 outlets. ( 2013-14) 30 Months after This station is proposed to meet future growth, to meet transformation MERC/STU Approval 2)6X 220 kV GIS bay at Golibar redundancy at Aarey , Reduce losses, Enhance reliability. 3)2X 33 kV GIS 13 pannel board 4) D/C 3X1/C 1200sqmm 220 kV cable from Airport to Golibar 5KM/ckt

5) Static VAR Compensator

176 STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR NAME OF THE DISTRICT Total Scope of Work Justification NO SUBSTATION 3 220/33 kV Khar Danda EHV Mumbai 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays Existing 80 MW load of this area is fed from Versova.RInfra-D requested for 8 Station additional outlets for this area. Versova peak reached to 343MW and are incapable to meet the load growth.The 80 MW load is to be relocated at Khar (2014-15) 30 Months after Danda. This station is proposed to meet future growth, to meet transformation MERC/STU Approval 2)2X 220 kV GIS bay at Versova redundancy at Versova, Reduce losses, Enhance reliability. 3)6X 220 kV GIS bay at Khar Danda 4)2X 33 kV GIS 13 pannel board 5) D/C 3X1/C 1200sqmm 220 kV cable from Versova to Khar Danda 10 KM/ckt 4 220/33 kV Bhayander Rai EHV Thane 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays Existing 50 MW load of this area is fed from Ghodbunder.RInfra-D requested Station for 6 additional outlets for this area. Ghodbunder peak reached to 269MW and incapable to meet the load growth.The 50 MW load is to be relocated at (20014-15) 24 Months after Bhayander Rai. This station is proposed to meet future growth, to meet MERC/STU Approval 2)6X 220 kV GIS bay at Bhayander Rai transformation redundancy at Ghodbunder, Reduce losses, Enhance reliability, 3)2X 33 kV GIS 13 pannel board 4)LILO of Dahanu Vesova OH line at Bhyander Rai by 1/C, 1200sqmm 220kV cable from tower to Bhayander Rai EHV Station (3kM/ckt).

5 220/33 kV KIE EHV Station Mumbai 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays Existing 36 MW load of this area is fed from Ghodbunder is to be relocated at (20013-14) 24Months after KIE. RInfra-D requested for 15 additional outlets for this area & 4 outlets for MERC/STU Approval 2)2X 220 kV GIS bay at Gorai Mumbai Metro-II. This station is proposed to meet future load growth, Reduce 3)6X 220 kV GIS bay at KIE losses, Enhance reliability. The firm capacity of Gorai EHV station is already commited. 4)2X 33 kV GIS 13 pannel board 5) D/C 3X1/C 1200sqmm 220 kV cable from Gorai to KIE 6 KM/ckt

6 220/33 kV Drive In Theater EHV Mumbai 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays Existing 65 MW load of this area is fed from RInfra Aarey & TPC Dharavi is to (20012-13)Station 24 Months after be relocated at Drive In Theater. RInfra-D requested for 24 additional outlets MERC/STU Approval 2)2X 220 kV GIS bay at Chembur for this area & 4 outlets for Mumbai Metro-II. This station is proposed to meet future load growth, Reduce losses, Enhance reliability, 3)6X 220 kV GIS bay at Drive In Theater 4)2X 33 kV GIS 13 pannel board 5) D/C 3X1/C 1200sqmm 220 kV cable from Chembur to Drive In Theater 10 KM/ckt 7 220/33 kV Mankhurd EHV Mumbai 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays RInfra-D requested for 11 additional outlets for this area & 4 outlets for (20013-14)24Station Months after Mumbai Metro-II. This station is proposed to meet future load growth, Reduce MERC/STU Approval 2)2X 220 kV GIS bay at Chembur losses, Enhance reliability, 3)6X 220 kV GIS bay at Mankhurd 4)2X 33 kV GIS 13 pannel board 5) D/C 3X1/C 1200sqmm 220 kV cable from Chembur to Mankhurd 5 KM/ckt 8 220/33 kV Vikhroli EHV Station Mumbai 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays Existing 30MW load of this area is fed from Aarey.RInfra-D requested for 8 (2014-15) 24 months after STU additional outlets for this area. Aarey peak reached to 412MW (2009-10) and /MERC approval 2)2X 220 kV GIS bay at Saki are incapable to meet the load growth.The 30 MW load is to be relocated at 3)6X 220 kV GIS bay at Vikhroli Vikhroli. This station is proposed to meet future growth, to meet transformation redundancy at Aarey, Reduce losses, Enhance reliability, 4)2X 33 kV GIS 13 pannel board 5) D/C 3X1/C 1200sqmm 220 kV cable from Saki to Vikhroli 8 KM/ckt

400 kV EHV Stations 10 400/220 kV Ghodbunder EHV Thane 1)3X400/220 kV 600 MVA T/F With GIS Bays To meet increamental and future demand, Source Bulk Power, Reduce Station losses, Enhance reliability, Create Corridor to wheel in Power (Connectivity from PGCIL Boisar) 2) D/C 400 kV OH lines from Boisar (PGCIL) 76 KM/ckt (2014-15) 48 months after STU /MERC approval 3) 400 kV GIS bays at Boisar(PGCIL) -02 nos 4) 400 kV GIS bays at Ghodbunder -09 nos 5) 220 kV GIS bays at Ghodbunder -09 nos 11 400kV PGCIL Mumbai-II to Thane 1) D/C 400 kV OH lines from Mumbai-II (PGCIL) to Rinfra Ghodbunder To meet increamental and future demand, Source Bulk Power, Reduce Rinfra-Ghodbunder (Approx 17kM /ckt) losses, Enhance reliability, Create Corridor to wheel in Power (2014-15) onward 48 months after STU /MERC approval 2) 400 kV GIS bays at Ghodunder- 3 nos 3) 400 kV GIS bays at Mumbai-II (PGCIL) -2 nos 4) 400 kV BUS Reactor at Ghodbunder 12 400/220 kV or HVDC IGBT at Mumbai 1)3X400/220 kV 600 MVA T/F With GIS Bays To meet increamental and future demand, Source Bulk Power, Reduce Malvani EHV Station losses, Enhance reliability, Create Corridor to wheel in Power 2) D/C 400 kV OH lines from MSETCL Padghe-II(Kudus) / Dahanu (2014-15) onwards 48 months 80kM/ckt after STU/MERC approval 3) 400 kV GIS bays at MSETCL Padghe-II / Dahanu -02 nos 4) 400 kV GIS bays at Malvani-09 nos 5) 220 kV GIS bays at Malvani -09 nos HVDC IGBT EHV Stations 13 2x400 MW HVDC IGBT Mumbai 1) 2X 150/220 kV Transformer To meet increamental and future demand, Overcome limitation in power Technology at Aarey EHV transfer capacity over length of AC cable, Source Bulk Power, Reduce Station losses, Enhance reliability, Create Corridor to wheel in Power, VAR control, Voltage Fluctuation Mitigation, Block Short power frequency and switching (2011-12) 24 months after surges. STU approval is received. MERC approval 2)150 kV, 600 MVA Inverter unit( Bipole)

14 2x400 MW HVDC IGBT Thane 1) 2X 220/150 kV Transformer To meet increamental and future demand, Overcome limitation in power Technology at Nagothane EHV transfer capacity over length of AC cable, Source Bulk Power, Reduce (2011-12) 24 months after losses, Enhance reliability, Create Corridor to wheel in Power, VAR control, MERC approval 2)150 kV, 600 MVA Converter unit (Bipole) Voltage Fluctuation Mitigation, Block Short power frequency and switching 3) 5X 1/C +/- 150 kV 1200sqmm DC cable from Nagothane to Aarey- 180 surges. STU approval is received. KM/ckt

177 STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR NAME OF THE DISTRICT Total Scope of Work Justification NO SUBSTATION C Additional Link Lines 1 ADDITIONAL 400kV LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY & QUALITY OF SUPPLY Nil 2 ADDITIONAL220kV LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY & QUALITY OF SUPPLY i) 220 kV D/C cables between 220 Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 8 KM / ckt, Enhance reliability, Flexibility of load transfer kV Dahisar to 220 kV Rinfra / TPC Borivli (2013-14)

ii) 220 kV D/C cables between 220 Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 7 KM / ckt, Enhance reliability, Flexibility of load transfer kV TPC Ghatkoper to 220 kV Rinfra Mankhurd (2014-15)

iii) 220 kV D/C cables between 220 Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 5 KM / ckt, Enhance reliability, Flexibility of load transfer kV Drive In Theater to 220 kV Rinfra Golibar (2014-15)

iv) 220 kV D/C cables between 220 Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 3 KM / ckt, Enhance reliability, Flexibility of load transfer kV TPC Saki to 220 kV Rinfra Saki (2014-15) v) 220 kV D/C cables between 220 Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 10 KM / ckt, Enhance reliability, Flexibility of load transfer kV Golibar to 220 kV Rinfra Versova (2014-15) 220 kV D/C cables between 220 Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 7 KM / ckt, Enhance reliability, Flexibility of load transfer kV TPC Dharavi to 220 kV Rinfra Khar Danda (2014-15) vi) D AUGMENTATION OF S/S BY ADDITION OF TRANSFORMER NIL E Others Schemes 1 LILO MSETCL Boisar- Borivli at Thane 1)220 kV Gantry near Tower no TRP-BVL-257 & cable Interfaces: STU approval is received.Existing load on Aarey-Borivli line reached to 400 RInfra Ghodbunder (2010- MW , Kalwa-Salsete reached to 545 MW & above SIL limit.This proposal will 11) 18 Months after MERC 2)DC 3x1/C 220 kV 1200 mm2 XLPE cable: 5KM/ckt, relieve Aarey Borivli and Kalwa Salsete Lines.Enhance Stability of DTPS, Approvals Create Corridor to wheel in Power, Additional Back Up to DTPS.

3)220 kV GIS bays: 4 nos at Ghodbunder, 2 Conversion of 220 kV AIS to Mumbai 220 kV GIS Bays: 14 nos at RInfra Aarey Future expansion is not possible due to unavalability of space at Aarey or GIS at Existing Aarey requirement of land as given in land DPR. This proposal will create space for HVDC IGBT Technology at Aarey to enhance reliability & to source bulk power (2010-11) 24 Months after in Mumbai. MERC Approval

3 Refurbishment of existing 220kV Thane / Replacement of existing old 220kV Porcelain Insulators by Composite MERC approval is received. 10% work completed. Transmission Lines Mumbai Polymer Insulators & refurbishment of transmission tower foundation.

( 2010-11)

4 Conversion of 220 kV AIS to Mumbai 220 kV GIS Bays: 9 nos at RInfra Ghodbunder Future expansion is not possible due to unavalability of space at Ghodbunder GIS at Existing Ghodbunder or requirement of land as given in land DPR. This proposal will create space (2013-14) 30 Months after for proposed 400kV GIS EHV Station at Ghodbunder to enhance reliability & MERC Approval to source bulk power in Mumbai.Short circuit study for Maharashtra Transmission network carried out in March 2010 by STU (from PRDC) recommanded for increasing breaker capacity to 63kA at RInfra Ghodbunder & this can be achieved by conversion of AIS to GIS.

178

TATA POWER COMPANY LTD.

179 STU/TRANS/DOC-04 - W.E.F 01/04/2010

TPC FIVE YEAR TRANSMISSION PLAN Year 2010-11 to 2014-15 TATA POWER (TPC) Technical Abstract

2012-13 Sr No Voltage Level 2009-10 2010-11 2011-12 Total & Beyond

New Sub-Stations (Nos.) 1 765 kV - - - - - 2 400 kV - - 3 3 3 220 kV - - 3 7 10 4 132 kV - - - - 0 5 110 kV 1 1 7 9 Total 0 1 4 17 22 Transmission Line / Cable Ckt kms: 1 765 kV - - - - - 2 400 kV - - - 681 681 3 220 kV 0 0 116 63 179 4 132 kV - - - - - 5 110 kV 0 16 15 59 90 Total (ckt km) 0 16 131 803 950 Capacity Addition (MVA): By New S/S 1 400kV 0 0 0 3000 3000 2 220kV 0 0 1250 2800 4050 3 132kV 0 0 0 0 0 4 110kV 0 150 180 1440 1770 Total 0 150 1430 7240 8820 By Augmentation of Transformer 1 400kV 0 0 0 0 0 2 220kV 0 0 0 0 0 3 132kV 0 0 0 0 0 4 110kV 250 75 655 250 1230 Total 250 75 655 250 1230 Total (MVA) 250 225 2085 7490 10050

180 STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE YEAR 2010-11 TO 2014-15 TATA POWER CO.LTD. SR. NAME OF THE DISTRICT TOTAL SCOPE OF WORK Date of REMARK / PURPOSE / JUSTIFICATION NO. SUBSTATION Completion A) ONGOING SCHEMES STARTED PRIOR TO APRIL 2009 1 Uprating of 110KV Raigad / Thane a) Replacement of existing 0.2 ACSR Conductor by FY10 To bring more power to Mumbai area from outside. Transmission Lines for / Mumbai 2X 0.15 ACSR Conductor of 110KV Khopoli- System strengthening Chembur, Khopoli-Mankhurd and Mankhurd-Parel Scheme approved by MERC. Lines ( 80 Circuit kms). 70% work completed. b) Two Circuit KM of XLPE Cable between Taping structure at Chembur & Chembur R/S . c) Terminal equipments at taping structures & Chembur R/S. 2 Expansion of existing Mumbai a) Construction of 145KV GIS Building. FY09 To provide additional outlets to Railways and BEST for 110KV Receving Stations b) Installation of 12 Bays of 145 KV GIS. Central Mumbai area. at Mahalaxmi c) Diversion of existing 110KV Cables to GIS by addition of cables. Scheme approved by MERC. d)Additional cables between GIS & 3 nos Power Scheme Completed in FY09. Transformers. e) Associated SCADA,Protection& Control and Aux System. 3 Establishing 220KV GIS Mumbai a) 1 Km of 220KV underground cable system. FY12 To augment input capacity to Mahalaxmi and to meet R/S at Mahalaxmi b) 5, 245 kV GIS bays. the additional requirement of BEST, Railways & Tata c) 1, 220/110/33KV, 250 MVA, ICT. Power-D reliably. d) 600 Mtrs of 630 Sqmm XLPE power cable. e) SCADA, Protection & other associated auxiliary Scheme approved by MERC. equipments. 4 220KV Interconnection Mumbai a) Construction of two, 220KV bays at MSETCL. FY10 To bring more power from MSETCL/ National Grid to with MSETCL at Borivali b) Construction of 0.5 KM of 220KV transmission Mumbai area for meeting the requirements of line. distribution companies in Mumbai & Suburban area. c) Replacement of conductor on the existing line ( 3 C - KM). Scheme approved by MERC. d) Addition of 220KV cable (700 mtr) between the Gantry and existing 220KV GIS bays. 40% work complete. e) Associated protection, Terminal equipments etc. 5 220KV Trombay- Dharavi- Mumbai a) Construction of four circuit transmission line from FY12 For meeting the additional load growth in North & Salsette Line Tromaby to Salsette (60 cir Kms). Centeral Mumbai. b) Construction of Transmission line from Trombay to Pratiskha nagar ( 10 Cir Kms) and laying of Scheme approved by MERC. 220KV cable system from Pratiskha nagar to Dharavi. c) Additional GIS bays at Dharavi and Salsette. d) Associated Protection, SCADA System, Aux Power Supply & Civil works etc. 6 Land for new Receiving Mumbai / Procurement of Land for setting up of 220 / 110KV FY11 Required for setting up the EHV Receving stations to Stations. Thane Receving stations at various Load centers like meet the additional load requirement of distribution Hiranandani, Parel, Bangur nagar. utilities. a) Plot at Hiranandani b) Plot at Parel Scheme approved by MERC. c) Plot at Bangur Nagar Hiranandani land - agreement under finalization.

7 Establishment of new Mumbai a) LILO of 110 kV Salsette-Dharavi by addition of 5 FY11 The existing 22 kV Substation is inadequate to meet 145 kv GIS R/S at circuit Km 110kV cable system from Vikhroli to the growing demand of the distribution licencees Hiranandani, Powai Hiranandani. requirement in the Hiranandani area. b) Construction of 145/33 KV GIS Bldg. c) 7, 145 kV GIS bays. Existing area is supplied from Tata Power Vikhroli (E) & d) 2, 100 MVA 110/33 kV power transformers. Saki & Salsette Stations. Load growth about 8% to10%. e) 17, 33 kV GIS bays.. Present 22 kV network is not adequate. Proposal will f) Protection, SCADA and Associated auxiliary efficiently and adequately meet the load. equipment, Fire protection & ventilation system etc. Scheme Approved by MERC

8 Establishment of 110 kV Mumbai a) Purchase of land from MMRDA. FY11 The existing 22 kV network is inadequate to meet the R/S at Bandra - Kurla b) Construction of 145 kV GIS Bldg. additional load in BKC area. The proposal will meet the Complex c) 6, 145KV GIS bays. additional requirement in BKC area. d) 2, 75 MVA 110/33 kV power transformers. e) 1 Km 110 kV power cable system. Existing area is supplied from Tata Power's Dharavi f) 15 bays of 33 kV GIS. (Matunga West) at 22 kV. Load growth is about 6% to g) Protection, SCADA & Associated equipments. 8%. Present 22 kV network not adequate.

Conversion of BKC station to 110 kV will enhance the efficiency of transmission lines which are presently utilised at 22 kV.

Scheme Approved by MERC

Land acquisition in final stage. 9 220 / 110 KV four Circuit Mumbai a) Construction of 220KV Transmission line FY12 To improve the supply reliabilty and to meet demand Transmission line with between Salsette & Narayan Industrial estate (14 growth of Saki area. 245KV GIS at Saki. Cir Kms). b) Laying of 220KV cable from Narayan Industrial To provide n-1 redundnacy at Saki. estate to Saki. c) Construction of GIS building. Scheme approved by MERC. d) installation of 8 nos 220KV GIS bays. e) Insatallation of two nos 250MVA, 220 / 110 / 33KV ICTs. f) Installation of 33KV GIS with two incomer, 1 Bus coupler and 18 outlets.

181 STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

10 145 kV GIS at Versova Mumbai a) Land from BMC. FY12 To meet the additional power requirement of Versova R/S b) 11, 145KV GIS Bays. area. c) 1, 90 MVA, 110/33KV Transformer. d) 14, 33KV Switchgear panels Conversion of AIS to GIS will enhance the life of the e) Associated power cables, Auxiliaries, Control & station equipments. They will serve efficently and Protection panels etc. adequately.

Scheme approved by MERC. 11 220 kV Mumbai a) Construction of additional 220 KV Trombay- FY12 To meet N-1 criteria. Ring system Overhead line (1 km). To improve reliability. b) 16 circuit KM of 220 KV Cable sytem from To meet additional load. The existing cable rated for Sewri-Backbay. 860 Amp cannot meet the load. c) 1, 250 MVA 220/110/33 KV ICT. Proposal will reduce the overloading of Carnac R/S d) 1, circuit Km of 110 kV cable system. and thus release the capacity for Carnac local load e) 11, 145 kV GIS bays. growth. f) Protection, SCADA & Associated equipments. Proposal will also make sure availability of alternate supply due to ring system.

Scheme Approved by MERC. 12 Installation of additional Mumbai a) 1, 250 MVA, 220/110/33KV ICT. FY10 To augment the input capacity to Dharavi R/S. interconnecting b) 1, 110 kV Hybrid switchgears transformer alongwith 33 c) 120 Mtr of 220 kV Bus duct. To meet the additional power requirement in Dharavi kv outlets at Dharavi R/S d) 675 Mtr of 110 kV 1600 Sqmm power cable area through additional outlets. e) 7, 33KV Switchgear panels. f) 33 kV power cables, protection SCADA system Scheme Approved by MERC. and other auxiliary systems. 13 Installation of additional Mumbai a) Installation of 1, 110 kV Bay at Vikhroli FY09 To meet the additional load requirements in Vikhroli new 4th, 75 MVA, 110 /22 b) 1, 75 MVA,110/22 KV power transformer. area through additional outlets. kV transformer at Vikhroli c) 1, 22 KV Switchgear. d) 500 Mtrs of 22 kV cable. Scheme Approved by MERC e) Associated protection, SCADA etc. Scheme completed in FY 09. 14 Uprating of 110KV Mumbai a) Replacement of existing conductor (900 A) by FY10 To improve supply reliability and to meet demand Transmission line by High Highampacity super Conductor (1800 A) on the growth in Saki & Malad areas. Ampacity Super existing 110KV Borivali - Malad, Salsette - Saki Conductor Transmission lines (32 cir Kms) Scheme approved by MERC. b) Uprating of 110KV bay equipments at Borivali, Malad,Salsette & Saki. B) NEW SCHEMES

1 110 kV New R/S at Mumbai a) Procurement of land. FY14 To meet the additional power requirement of Borivali (west) b) Construction of Two 110 kV Bays at Tata Power distribution licencees in the Borivali West area. Borivali (East). c) 6 circuit Km of underground cable system Borivli West area is served by Tata Power Borivli between Borivai (east) and west s/s. (East) Station at 22 kV. d) Nine 110 kV GIS Bays. e) 2, 100 MVA 110 /33 kV Transformers. The load growth is about 10%. The existing 22 kV f) 17 outlets of 33 kV GIS Bays. network inadequate. Proposal will efficiently and g) Protection, Scada and other auxiliary adequately meet the load. 2 Establishment of 220KV Mumbai a)equipments. Loop in Loop out of proposed 220 kV Trombay- FY14 To provide input capacity to Antop Hill (Wadala) and to R/S at Antop Hill Dharavi and laying of 1.5 circuit Km of 220KV cable meet the additional requirement of distribution (Wadala) system to the proposed GIS Bldg at Antop Hill. licencees. b) Construction of GIS Bldg. c) 6 bays of 220 kV GIS. Existing area is supplied from Tata Power Dharavi d) 2, 100 MVA, 220/33 kV power transformers. (Matunga West). Load growth about 5% to 6%. Present e) 17, 33 kV GIS bays. 22/33 kV network not adequate. f) Protection, SCADA and Associated Auxiliary system etc. 3 Establishment of new Mumbai a) LILO of existing 220 KV Bhira-Dharavi line. FY15 The load growth of about 5% to 6% is expected due to 220/33 kV GIS R/S at b) Construction of 220 kV GIS Bldg. rehabilitation of Dharavi slums. The existing Tata Chunabhatti c) Installation of 9, 220 kV GIS bays. Power's R/S capacity at Matunga (W) will be d) Installation of 2, 220/33 kV power transformers. inadequate to meet the additional load growth. Hence it e) Installation of 17, 33 kV GIS bays. is proposed to construct a new station at Chunabhatti f) Associated protection, SCADA, Auxiliary to meet the requirements of distribution licencees (33 equipments. kV outlets).

4 Establishment of new Mumbai a) LILO of existing 110 kV Malad-Versova lines. FY14 Adequate space is not available at the existing Malad- 110/33 KV R/S at Bangur b) Construction of GIS Bldg. Versova R/S for expansion and hence it is proposed to Nagar R/S c) Installation of 7 bays of 145 kV GIS. construct an additional 110/33 kV R/S at Bangur Nagar d) Installation of 2 x 100 MVA, 110/33 kV for meeting the load requirement of Distribution transformers. Licencees in that area. e) Installation of 17 bays of 33 kV GIS. f) Asscoiated protection, SCADA & Associated The load are supplied from Tata Power Malad & auxiliary system. Versova R/S. Load grwoth 8% to 10%. Present network / infrastructre not adequate therefore the existing EHV lines are getting tapped to meet loads efficently.

5 Establishment of new Mumbai a) Loop in Loop out of existing 110 kV Salsette-Saki FY15 To meet the additional power requirement of 110 /33 KV R/S at L&T lines. distribution licencees in the Powai area. b) Procurement of land. c) Construction of 145/33 kV GIS Bldg. Existing area is supplied from Tata Power Salsette d) Installation of 9 bays of 145 kV GIS bays. (Bhandup West) / Saki Stations at 22 kV. Load growth e) 2, 100 MVA, 110/33 kV power transformers. about 8% to10%. Present network not adequate. f) 17 bays of 33 KV GIS bays. Proposal will efficiently and adequately meet the load. g) Associated protection, SCADA, Auxiliary equipment, Fire system etc. MERC has approved 220 kV Saki proposal, which will enhance the upgradation and setting up of the stations to benefit the consumers including licencees.

182 STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

6 New 400/220/33 kV Mumbai a)400 KV Ghatkopar - Kharghar D/C Line - 20 km FY14 To increase power input to Mumbai from Natonal Station at b) 400 KV Ghatkopar - New Panvel (PGCIL) S/C Power Grid. Ghatkopar Line - 40 km. c) 400 KV PGCIL, Kalher - Ghatkopar line - 40 km The proposal will bring reliable and cheap power to d) Construction of 400/220/33 kV GIS Bldgs. Mumbai to mitigte the shortage face today. e) 3 x 500 MVA, 400/220/33 kV power transformers. f) 3 x 250 MVA, 220/110/33 kV ICTs g) Installation of 400 kV GIS bays. h) Installation of 220 kV GIS bays. i) LILO of 220kV Trombay - Salsette - Saki lines j) LILO of MSETCL Trombay - Mulund/Kalwa line k) 2 x 220kV lines for Godrej & Boyce l) Installation of 33 kV GIS bays. m) Installation of 145 kV GIS bays. n) Asscoiated protection, SCADA, auxiliary equipment, fire protection system etc.

7 New 220/33 KV R/S at Mumbai a) LILO of 220 KV UG Salsette - Saki cable system FY12 To meet the growing power requirements in Airport Air Port Area (Vidyavihar from Narayan Ind Estate to Air Port are, route area (expected load about 300MVA eventually.) West) length 15 KM. b) Development of land at Airport S/S. Existing area is supplied from Tata Power's Dharavi & c) Construction of 220/33 kV GIS Bldg. Saki. Load growth about 6% to 8%. Present 22 kV d) Installation of 7 bays of 220 kV GIS. network not adequate. e) 2, 220/33 kV, 125 MVA Power transformers. f) Installation of 17 bays of 33 kV GIS bays. Proposal will meet the loads efficiently and adequately. g) Associated protection, SCADA, auxiliary equipment etc.

8 New 400/220/33 kV R/S Mumbai/ Thane a) 400 KV S/C line from PGCIL Kalher to Marve, FY15 To get more power input from PGCIL;s proposed at Marve S/C line from Majlipada to Marve Kalher / Panvel 400 kV Stations to meet the load b) Purchase of land at Marve. requirements of entire North-West Mumbai area. c) Construction of 400/220/33 kV GIS Bldgs. d) 3 x 315 MVA, 400/220/33 kV ICTs. Present supply is from Tata Power's Trombay/ Borivli e) Installation of 400 kV GIS bays. at 220 kV. The load growth is about 8% to 10%, the f) Installation of 220 kV GIS bays. network is not adequate. The proposal will bring in bulk g) Installation of 33 kV GIS bays. power efficiently and adequately. h) Asscoiated protection, SCADA, auxiliary equipment, fire protection system etc.

9 New 400/220/33 kV R/S Mumbai/ Thane a) LILO of 400kV Kalher-Marve line. FY15 To get more power input from PGCIL Kalher/ Panvel at Majlipada b) 400 kV D/C line from PGCIL Boisar to Majlipada to meet the load requirements of North Mumbai c) Purchase of land at Majlipada. covered in PGCIL report for power evacuation. d) Construction of 400/220/33 kV GIS Bldgs. e) 3 x 315 MVA, 400/220/33 kV ICTs Present supply is from Tata Power's Trombay/ Borivli f) Installation of 400 kV GIS bays. at 220 kV. The load growth is about 8% to 10%, the g) Installation of 220 kV GIS bays. network is not adequate. The proposal will bring in bulk h) Installation of 33 kV GIS bays. power efficiently and adequately. i) 2 X 220 kV lines to DFCC. j) Associated protection, SCADA, auxiliary Proposal under discussions with PGCIL and STU equipment, fire protection system etc.

10 New 220/33 kV R/S at Mumbai/ Thane a) 220 KV D/C UG cable system from Majlipada to FY14 To meet the growing load of Mira Road (West) area. Mira Road (West) Mira Road (West), route length 12 KM. b) Purchase of land at Mira Road (West) Mira Road (West) area is served by Tata Power's c) Construction of 220/33 kV GIS Bldg. Borivli (East) Station at 22 kV. d) Installation of 220 kV GIS. e) 2 X 125 MVA, 220/33 kV Power transformers. The load growth about 10%. The existing network f) Installation of 33 kV GIS bays. inadequate. Proposal will efficiently and adequately g) Associated protection, SCADA, auxiliary meet the load, it will also load the proposed 400 kV equipment etc. Majlipada station mentioned above.

11 New 220/33 KV Versova Mumbai a) 220 KV D/C UG cable system from Marve to FY15 To meet the growing load of Versova area. (West) S/S Versova (West), route length 10 Km. b) Purchase of land at Versova (West) Versova (West) area is served by Tata Power's c) Construction of 220/33 kV GIS Bldg. Versova R/S at 22 kV. The Versova station cannot be d) Installation of 220 kV GIS. expanded due to shortage of space. e) 2 X 250 MVA 220/110/33 kV Power transformers. f) Installation of 33 kV GIS bays. The load growth is about 10%. The existing network g) Associated protection, SCADA, auxiliary inadequate. Proposal will efficiently and adequately equipment etc. meet the load, it will also load the proposed 400 kV Marve station mentioned above. 12 New 220kV/33kv Godrej Mumbai a) 220 KV D/C UG cable system from Ghatkopar to FY13 To meet load growth arising out of development of (East) S/S Godrej (East), route length- 4 KM. Godrej property in Vikhroli (East) and additional loads b) Construction of 220/33 kV GIS Bldg. in that area. c) Installation of 220 kV GIS. d) 2 X 125 MVA, 220/33 kV Power transformers. Presently loads in Godrej area are fed at 22kV which e) Installation of 33 kV GIS bays. will not be economical with increased load. f) Associated protection, SCADA, auxiliary equipment etc. Expected load in this area is about 120 MVA by FY13/14

13 New 220kV/33kv Godrej Mumbai a) 220 KV D/C UG cable system from Ghatkopar to FY14 To meet load growth arising out of development of (West) S/S Godrej (West), route length- 4 KM. Godrej property in Vikhroli (West) and additional loads b) Construction of 220/33 kV GIS Bldg. in that area. c) Installation of 220 kV GIS. d) 2 X 125 MVA, 220/33 kV Power transformers. Presently loads in Godrej area are fed at 22kV which e) Installation of 33 kV GIS bays. will not be economical with increased load. f) Associated protection, SCADA, auxiliary equipment etc. Expected load in this area is about 120 MVA by FY13/14

183 STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

14 New 220kV/33kV S/S at Mumbai a) LILO of 110kV Trombay-Parel line at Sewri FY14 To meet increased load demand in Wadala area. Bombay Dyeing, Wadala b) 110kV S/C Cable system Sewri fort - Wadala - Parel, route length 7 km Expected loads in due to development of commercial & c) 220kV GIS bays at Wadala residential complexes in Bombay Dyeing, Wadala area d) 2X90 MVA Transformers is about 70 MVA e) Associated protection, SCADA, auxiliary equipment etc.

15 New 220kV/33kV S/S at Mumbai a) 110kV Cable system to Worli from Dharavi and FY14 To meet increased load demand in Worli area. Bombay Dyeing, Worli Parel R/S, route length - 10 km b) Construction of GIS building Expected loads in due to development of commercial & c) Instalaltion of 145kV GIS bays at Bombay residential complexes in Bombay Dyeing, Worli area is Dyeing, Worli about 60 MVA d) Installation of 33 kV GIS bays. e) Associated protection, SCADA, auxiliary equipment etc. 16 New 220kV/33kV S/S at Mumbai a) Uprating of 22kV overhead lines from Dharavi FY14 To meet prospective loads in Kurla (West) area - about HDIL, Kurla R/S to Mithi river - 2.5 km 50 MVA b) 110kV D/C cable system from Mithi river to HDIL, Kurla - 4 km Subsequently, the expected load growth in Kurla c) Instalaltion of 145kV GIS bays (West) area is about 5%. d) 2 x 90 MVA Transformers e) Installation of 33kv GIS bays f) Associated protection, SCADA, auxiliary equipment etc.

17 New 110kV/33kV R/S at Mumbai a) LILO of existing 110kV Trombay-Chembur and FY14 There is no scope for expansion of existing Chembur Chembur Tapping Khopoli - Lodhiwali-Chembur lines at tapping R/S for additional outlets. Structure structure b) Installation of 145kV GIS bays To meet increased demand in Chembur area c) Installation of 2X90 MVA Transformers d) Installation of 33kV GIS bays e) Associated protection, SCADA, auxiliary equipment etc.

C) ADDITIONAL LINK LINES I FOR SUB-STATIONS WHERE ONLY SINGLE CIRCUIT AND SINGLE SOURCE IS II TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND 1 220kV Kalwa - Salsette Thane Uprating of existing 110kV Kalwa - Salsette to 220 FY12 To meet increased Mumbai demand reliably. Third Line kV The existing 220kV Kalwa-Salsette lines have reached full capacity and tripping any one line jeopardises system stability. III FOR NEW SUBSTATIONS TO HAVE ALTERNATE SOURCE

NIL IV FOR STRENGTHENING OF EVACUATION ARRANGEMENT 1 Evacuation of power from Mumbai / a) 400 kV D/C lines (twin conductor) from Dehrand FY14 To provide evacuation of Tata Power's proposed the proposed 3x800 MW Thane / Raigad to Ghatkopar - 65 Km. Thermal station to Tata Power area and to power plant at Dehrand / b) 400 kV D/C lines (twin conductor) from Dehrand MSETCL/and other states through PGCIL's 400 kV Mankule, Maharashtra to Nagothane - 65 Km. network from Panvel / Pune.

Proposal included in PGCIL evacuation report. D) AUGMENTATION OF SUB-STATIONS BY ADDITION OF TRANSFORMER I WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

NIL II TO REDUCE LOADING ON EXISTING TRANSFORMER (N-1)

1 Installation of additional Mumbai a) 1, 250 MVA, 220/110/33KV ICT. FY13 To augment the input capacity to Borivli R/S. interconnecting b) 1, 110 kV Hybrid switchgears transformer alongwith 33 c) 120 Mtr of 220 kV Bus duct. To meet the additional power requirement in Borivli kv outlets at Borivli R/S d) 675 Mtr of 110 kV 1600 Sqmm power cable area through additional outlets. e) 7, 33KV Switchgear panels. f) 33 kV power cables, protection SCADA system and other auxiliary systems. 2 Installation of additional Mumbai a) Installation of 1X75 MVA Transformer FY11 The expected load on 33kV at Parel is about 160 MVA 75 MVA, 110/33kV b) Instalaltion of 33kV GIS bays which will exceed firm capacity of 75 MVA. Transformer along with c) 33 kV power cables, protection SCADA system 33kV GIS bays at Parel and other auxiliary systems. To meet increased load on 33kV reliably additional transformer is required. 3 Installation of additional Mumbai a) Installation of 1x315 MVA additional ICT at FY12 315 MVA, 220kV/110kV Trombay ICT at Trombay b) Construction of 110kV O/H line from Trombay 220kV to 110kV - 2 ckt km

III AUGMENTATION OF SUB-STATIONS BY REPLACEMENT OF TRANSFORMER

1 Life extension Mumbai Procurement, Installation, Testing Commissioing of FY12 The transformers are having high Furan content. The (Replacement) of existing 3 Nos. 75/90 MVA, 110/22 kV power transformers transformers cannot be repaired. transformer 2 at Saki & at Saki & Mahalaxmi R/S respectively. existing transformer 2 at Transformers are 35 years old. Hence they are Mahalaxmi and required to be replaced. transformer 2 at Carnac R/S

E) LIFE EXTENSION AND MODERNISATION

1 Expansion and life Mumbai a) Construction of 145 KV GIS Bldg. FY13 The existing AIS equipments are old and served there extension of existing 110 b) Installation of 9, 145 kV GIS bays. utility therefore they need replacement by GIS. kV R/S at Mankhurd c) Associated protection, SCADA & Auxiliary equipments. To increase the reliability of station and to meet additional load.

To provide additional 110 kV outlets to consumers.

184 STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

2 Expansion and life Mumbai a) Construction of 145 KV GIS Bldg. FY14 The existing AIS equipments are old and served there extension of existing 110 b) Installation of 30, 145 kV GIS bays. utility therefore they need replacement by GIS. kV R/S at Dharavi c) Associated protection, SCADA & Auxiliary equipments. To increase the reliability of station to meet consumers d) 110 kV power cables between GIS and power load. transformers. To provide additional 110 kV outlets to consumers and other Satelite R/S to be setup.

3 Expansion and life Mumbai a) Construction of 145 KV GIS Bldg. FY14 Increase in reliability. extension of existing 110 b) Installation of 9, 145 kV GIS bays. kV R/S at Malad c) Associated protection, SCADA & Auxiliary To provide additional outlets to consumers. equipments. d) 110 kV power cables between GIS and power transformers. 4 Expansion and life Mumbai a) Construction of 145 kV GIS Bldg. FY14 Increase in reliability. extension of existing 110 b) Installation of 15 bays of 145 kV GIS Bldg. kV R/S at Parel c) Associated protection, SCADA etc. Creation of additional outlets for meeting the d) 110 kV cable system between Transformer / requirement of customers. Lines & GIS. 5 Expansion and life Mumbai a) Construction of 145 kV GIS Bldg. FY15 Increase in reliability. extension of existing 110 b) Installation of 9 bays of 145 kV GIS Bldg. kV R/S at Saki c) Associated protection, SCADA etc. Creation of additional outlets for meeting the d) 110 kV cable system between Transformer / requirement of customers. Lines & GIS. 6 Expansion and life Mumbai a) Installation of 5 bays of 145 kV GIS. FY15 Increase in reliability. extension of existing 110 b) Associated protection, SCADA etc. kV R/S at Carnac c) 110 kV cable system between Transformer / Creation of additional outlets for meeting the Lines & GIS. requirement of customers.

7 Replacement and life Mumbai a) Replacement of switchgear. To meet the annual capital expenditure requirement of extension of exising b) Replacement of Station transformers. replacing the old outdated transmission assets in the switchgear/auxiliary c) Replacement of batteries and chargers. Tata Power's R/S. equipment etc. of existing d) Replacement of UPS. 17 Receiving Stations of e) Replacement of AC & DC boards. Tata Power. f) Other fire system equipment. g) SCADA & Communication system.

185

756 KV & 400 KV TRANSMISSION NETWORK OF MAHARASHTRA STATE INCLUDING INTERSTATE LINES

186 400 KV DHULE-II 765 kV & 400 kV TRANSMISSION NETWORK OF MAHARASHTRA DONDAICHA GEN 1&2 (DONDAICHA) INCLUDING INTERSTATE LINES

2 x 660 MW 2 x 635MVA 400 KV NASHIK 15 km, Quad Moose 95 km, Quad Moose Towards 95 km, Quad Moose 400 KV DHULE- I 15 km, Quad Moose

175 km, Quad Moose } 30 km, Quad Moose Towards 400 KV INDIABULLS, 30 km, Quad Moose Towards NASHIK 400 KV DHULE PG 400 KV PADGHE 175 km, Quad Moose } 174 km, Twin Moose

150 km, Quad Moose Towards BABLESHWAR 174 km, Twin Moose 190 km, Quad Moose } 150 km, Quad Moose Towards } 400 KV NAVSARI PG 400 KV CAHKAN 190 km, Quad Moose Towards PADGHA 220 kV 144 km, Twin Moose 400 KV KUDUS (MSETCL) 400 KV TARAPUR PG 3 x 315 MVA 2 x 500 MVA 102 km, Twin Moose Towards NASIK 220 kV 20 km, Twin Moose CHANDRAPUR 400 KV PUNE PG 102km, Twin Moose 28 km, Twin Moose 2 x 315 MVA

20 km, Twin Moose 116.315 km, Twin AAAC TARAPUR GEN 3&4 Towards 400 KV BOISAR PG Towards 220 KV CHAKAN-II 400 KV 400 KV HEGC 20.5 km, Twin Moose 77.1 km, Twin Moose 400 KV LONIKAND-I 116 .315 km, Twin AAAC } NAGOTHANE 2 x 540 MW 284 km, Twin Moose 2 x 635MVA 2 x 500 MVA HEGC GEN. Towards 20.5 km, Twin Moose 400 KV PARLI Towards 285 km, Twin Moose } KUDUS 220 kV 1x 350 MW Towards 400 KV NALASOPARA BOISAR 220 kV 400 KV PADGHE PG 37 km, Twin Moose Towards 50 km, 765 KV PADGHE PG 765 KV PUNE PG 3 x 315 MVA Twin Moose NALPSOPARA 220 kV Quad Zebra 20 km, Quad Moose 91 km, Twin Moose Towards 2 x 500 MVA 50 km, 230 km, Twin Moose

400 KV VAPI 20 km, Quad Moose 2 x 1500 MVA 2 x 1500 MVA Quad Zebra Towards Towards

3 x 315 MVA 400 KV LONIKAND-220kV } 250 km, Quad Bersimis 230 km, Twin Moose } AURANGABAD-I Towards 765 KV AURANGABAD-PG 250 km, Quad Bersimis 400 KV KALWA 400 KV JEJURI

71.5 km, Twin Moose 2 x 315 MVA

1 x 500 MVA Towards 2 x 500 MVA PUNE-PG 220 kV 48 km, Twin Moose Towards { 71.5 km, Twin Moose JEJURI 220kV

161.05 km, Twin Moose 400 KV NERUL Towards 84 km, Twin Moose Towards 400 KV NAVI MUMBAI PG 80 km, Twin Moose 2 x 600 MVA Towards KARAD 400 KV KESURDI NERUL 220 kV 400 KV LONIKAND-II 185 km, Twin Moose Towards KALWA 220 kV 2 x 500 MVA 400 KV KHARGHAR 55 km, Twin Moose Towards 15 km, Twin Moose VAPI 2 x 315 MVA { 185 km, Twin Moose 270 km, Twin Moose

40 km, Twin Moose Twin km, 40 Moose Twin km, 76 Moose Twin km, 76 Towards 55 km, Twin Moose 58 km, Twin Moose Bersimis Quad km, 260 23 Twin Moose 15 km, Twin Moose Towards 400 KV 400 KV VIKROLI KHARGAR 220 kV PARLI-PG (GHATKOPER) 1 x 500 MVA } } 106 km, Twin Moose 270 km, Twin Moose 40 km, Twin Moose 270 km, Quard Moose 20 km, Twin Moose Towards 400 KV AURANGABAD PG 270 km, Quard Moose } 116

Towards 2 x 315 MVA 400 KV OSMANABAD 400 KV KESURDI Moose Twin GHTKOPR2 220kV 2 x 500 MVA 765 KV SOUTH SOLAPUR PG 400 KV HINJEWADI 2 x 500 MVA 2x 500 MVA Towards Towards OSMANB2N 220 kV NMUM-PG2 220kV Towards 60 km, Quad Moose 400 KV GHODBUNDER 220 KV 129 km, Twin moose Towards LONIKAND-II 400 KV SOLAPUR 2 x 500 MVA 400 KV PARLI PG 230 km, Quad Bersimis 60 km, Quad Moose Towards 182 km, Twin Moose Towards 400 KV 400 KV SOUTH SOLAPUR PG HINJEWADI 220kV PARLI 67 km, Twin moose Towards RAICHUR 230 km, Quad Bersimis } 55 km, Quad Moose Towards 2 x 1500 MVA SOL-III2 220 kV 55 km, Quad Moose 2 x 500 MVA 20 km, Quad Moose Towards 220KV GHODBUNDER 400 KV KARAD 189 km, Twin Moose Towards Towards 400 KV 400 KV KOYNA Towards 3x 600 MVA 220 kV KARAD-I PARLI-PG { 3 x 315 MVA 246 km, Twin Moose KESURDI 220 kV 2x 500 MVA KOYNA-4 GEN

2x 600 MVA SSOLPRNG [110] 110 km 400 KV KOLHAPUR 1 x 500 MVA Twin Moose 2x 500 MW 118 km 4 x 300 MVA 4 x 250MW 196km, Twin Moose Towards NARENDRA Twin Moose HVDC back to back converter Towards 196km, Twin Moose 400 KV KARAD-II 84 km Twin Moose JEJURI 2 x 315 MVA 56 km, Twin Moose 400 KV MHAPUSA PG Towards 220kVSOUTH 105 km, Twin Moose 56 km, Twin Moose Towards 192.7 km, Twin Moose SOLAPUR PG 220 kV MHAPUSA 400 KV NEW KOYNA 22 km, Twin moose 3 x 315 MVA 105 km, Twin Moose 14 192.7 km, Twin Moose 56 km, Twin Moose Twin Moose

14

139 km, Quad Moose 22 km, Twin Moose Twin Moose Towards } Towards 2 x 315 MVA 56 km, Twin Moose 400 KV JAIGAD 161.05 km, Twin Moose Towards 220 kV KOLHAPUR-III 139 km, Quad Moose 400 KV LONIKAND-I Towards 400 KV FINOLEX { FINOLEX GEN 220 KV KARAD-II 150 km Quad Moose 1 x 500 MVA 2x 500 MVA 1 x 315 MVA

150 km 2x 600 MVA

Quad Moose 2x 500 MW RGPPL GEN-1 400 KV RGPPL Towards 1 x 640 MW NEW KOYNA 220 kV } 2 x 500 MVA 400 KV NAGOTHANE 60 km, Quad Moose } Towards 2 x 500 MVA 1 x 753 MVA 220 kV NAGOTHANE RGPPL GEN 2&3 60 km, Quad Moose 2 x 668 MW

400 KV JAIGAD 120 km, Quad Moose

1 x 315 MVA 2 x 786 MVA 136 km, Quad Moose

} 139 km, Quad Moose

Towards 120 km, Quad Moose 116.315 km, Twin AAAC 136 km, Quad Moose 400 KV KARAD-I } 139 km, Quad Moose Towards 400 KV PADGHE JAIGAD GEN 116.315 km, Twin AAAC 4 x 355 MVA 4 x 300 MW

LEGEND PARTICULARS 765 kV EXISTING LINES (PGCIL) 765 kV PROPOSED LINES (PGCIL) 765 kV EXISTING LINES (MSETCL) 765 kV PROPOSED LINES (MSETCL) MAHARASHTRA STATE ELECTRICITY TRANSMISSION CO. LTD. 400 kV EXISTING LINES (PGCIL) State Transmission Utility,4th Floor, 400 kV PROPOSED LINES (PGCIL) Prakashganga',Bandra Kurla Complex Bandra (E), MUMBAI - 400 051 SHEET - I 400 kV EXISTING LINES (MSETCL) 187 400 kV PROPOSED LINES (MSETCL) 400 KV MALEGAON 765 KV & 400 kV TRANSMISSION NETWORK OF MAHARASTRA

INCLUDING INTERSTATE LINES Towards } 50 km, Quad Moose 400 KV DHULE PG 400 KV DHULE-II 50 km, Quad Moose 400 KV DHULE (DONDAICHA) Quad Moose (MSETCL)

175 km, Quad Moose Quad Moose

} 50 km, Quad Moose 2 x 315 MVA Towards Towards

400 KV NASHIK 50 km, Quad Moose 175 km, Quad Moose 400 KV NASHIK RAIGHAR (KOTRA) } } 210 km Twin Moose Towards Towards Towards 1 x 500 MVA 400 KV DHULE (IPTC) 400 KV KHANDWA DHULE 220 kV 220kV MALEGAON 210 km 400 KV BABHALESHWAR INDIABULLS,NASHIK GEN. Quad Moose Twin Moose } 400 KV INDIABULLS NASHIK 2 x 500 MVA 76 km, Quard Moose 142 km, Twin Moose 2 x 660 MW 76 km, Quard Moose 2 x 780 MVA Quad Moose Towards 765 KV DHULE (IPTC) 142 km, Twin Moose} SARDAR SAROVAR 30 km, Quard Moose 174 km, Twin Moose Towards 400 KV NASIK 170 km, Twin Moose 30 km, Quard Moose 2 x 1500 MVA Towards } Towards 250 km, Quad Bersimis PADGHA 765 KV BARODA BHUSAWAL EXP 400 KV BHUSAWAL-II 174 km, Twin Moose } 2 x 500 MW 170 km, Twin Moose

765 KV AURANGABAD PG 400 KV AURANGABAD-II (MSETCL) 2 x 600MVA 400 KV BHUSAWAL-I 2 x 500 MVA 130 km, Quad Bersimis Towards 2 x 500 MVA AURANGABAD-II 220 kV 190 km, Quad Moose Towards 2 x 500 MVA BHUSWALII 220 kV 220 km, Twin Moose 190 km, Quad Moose 7 km, Twin Moose Towards

400 KV AURANGABAD PG 3 x 200 MVA 220 KV BABHALESHWAR

7 km, Twin Moose 1 x 315 MVA } Towards } 270 km, Quad Moose 400 KV AURANGABAD-I 30 km, Quad Moose 132 kV BHUSAWAL 25 km, Quad Moose Towards 131 km, Twin Moose 270 km, Quad Moose 400 KV KHARGHAR 30 km, Quad Moose 25 km, Quad Moose

238 km, Twin Moose

Towards 230 km, Twin Moose } 2 x 315 MVA 400 KV PUNE PG 400 KV PARLI PG

400 KV AKOLA-I Towards 400 KV WARDHA PG BHUSAWAL-220 kV 230 km, Twin Moose 265 270 km, Twin Moose 2 x 1500 MVA 182 km 400 km, Quad Moose } Twin Moose Twin Moose 343km, Twin Moose Towards Towards Towards 189 km, Twin Moose 400 KV KORADI-II 400 KV SOUTH SOLAPUR (PG) 400 KV PUNE PG 400 km, Quad Moose 2 x 500 MVA 265 270 km, Twin Moose } Twin Moose 2 x 315 MVA 400 KV PARLI (MSETCL) 765 KV WARDHA PG Towards 129 km, Twin Moose 400 KV OSMANABAD Towards Towards 7 km, Twin Moose 220 KV 1 x 315 MVA AKOLA-220 kV 400 KV KORADI-II AURANGABAD-I 2 x 1500 MVA Towards 7 km, Twin Moose 269 km, WARDHAPG 220 kV 341 km, Quard Moose

400 km, Quad Bersimis 2 x 315 MVA Quad Bersimis Towards 2x500 MVA

765 K SEONI 341 km, Quard Moose 269 km, }(Charged at 400 kV) 400 km, Quad Bersimis Quad Bersimis 70 km, Quad Moose } 285 km km, Twin moose 400 KV CHANDRAPUR-I 400 KV BHADRAVATI PG

Towards 70 km, Quad Moose

400 km, 24 km, Twin Moose 388 km, Twin Moose 1 x 500 MVA PRLI-GR 220 kV 400 km, Quad Bersimis Quad Bersimis 284 km, Twin Moose } 81 km, Quad Moose IDEAL GEN. } 400 km, Quad Bersimis Towards Towards 400 KV IDEAL Towards 400 km, Quad Bersimis 24 km, Twin Moose RAIPUR 400 kV WARORA 400 kV 388 km, Twin Moose 400 KV LONIKAND-I 400 km, 81km, Quad Moose 400 KV MAUDA Quad Bersimis 120 km, Quad Moose

400 km, } 2 x 270 MW 22.5 km, Twin Moose Quad Bersimis 345 km, Twin Moose

363 km, Twin Moose 120 km, Quad Moose MAUDA GEN. } Towards 182 km, Twin Moose Towards 22.5 km, Twin Moose 345 km, Twin Moose Raipur PGCIL 400 kV 160 km, Twin Moose 400 K RAIPUR 400 KV SOLAPUR 363 km, Twin Moose 2 x 600 MVA 2 x 500 MW 333 km, Twin Moose } 160 km, Twin Moose 40 km Towards Quad Moose Towards RAMAGUNDAM 156 km, Twin Moose (HVDC back to back converter) 40 km 400 KV KORADI-III Towards 400 KV AKOLA - II 322 km 400 KV NANDED Quad Moose Twin Moose 400 KV BHILAI 765 KV AKOLA - II 10 km, Quad Moose Towards 281 km, Twin Moose 400 KV 210 km, Quad Bersimis 400 KV KHAPERKHEDA BHUSAWAL-I K'KHEDA EXP. 10 km, Quad Moose Towards 400 KV CHANDRAPUR-II 2 x 1500 MVA 156 km CHANDRAPUR-II 220 kV 210 km, Quad Bersimis 400 KV INDIABULLS, 2 x 500 MVA 2 x 500 MVA 1 x 600 MVA Twin Moose 2 x 315 MVA NANDGAONPETH 1 x 500 MW C'PUR EXP. 90 km Towards Quad Moose Towards PADGHE 2 x 500 MW NANDED 220 kV 765 KV KUDUS 90 km 220 kV KHAPERKHEDA-II Towards 2 x 600 MVA (PADGHE) PG Quad Moose Towards 138 km, Twin Moose 2 x 500 MVA CHANDRAPUR-I 220 kV SATPURA 1 x 500 MVA 250 km, Quad Bersimis } 340 km, Twin Moose INDIABULLS GEN. 340 km, Twin Moose 250 km, Quad Bersimis 400 KV KORADI-I 30 km, Twin Moose 5 x 270 MW 2 x 780 MVA 10 km 400 KV DHARIVAL Twin moose 30 km, Twin Moose DHARIVAL GEN. 30 km, Twin Moose 4 x 135 MW 174 km, Twin Moose 30 km, Twin Moose 4 x 160 MVA CHANDRAPUR GEN.3 15 km, Twin Moose Towards 765 K KORADI - III 3 x 500 MW NAGPUR ENERGY GEN. KORADI2 GEN 3 x 600 MVA 400 KV NAGPUR ENERGY 400 KV KUDUS PG 15 km, Twin Moose 2 x 1500 MVA 240 km CHANDRAPUR GEN.2 50 km, Quard Moose 2 x 500 MW Quad Bersimis 3 x 250 MVA 2 x 600 MVA 272 km, Twin Moose Towards 50 km, Quard Moose WARORA40 [2504044] 3 x 210 MW BHILAI 3 x 210 MW 5 km, 240 km 5 km, 3 x 250 MVA Towards 1 x 315 MVA 50 km, Quad Moose Quad Moose Quad Bersimis KORADI-220 kV Quad Moose { 2 x 500 MVA 50 km, Quad Moose 400 KV ADANI,GONDIA Towards 2 x 500 MVA 400 KV KORADI-III WARORA 220 kV 174 km, Quad Moose

765 KV ADANI( GONDIA) 174 km, Quad Moose

2 x 1500 MVA

130 km, Quad Bersimis 40 km 2 x 500 MVA Towards Quad Moose 10 km, Quad Moose 81 km ADANI GEN. 4 & 5 } 400 KV MAUDA 40 km Towards ADANI GEN. 1,2 & 3 Towards Quad Moose Quad Moose 10 km, Quad Moose KORADI-II-220 kV 400 KV WARDHA (PG) LEGEND 130 km, Quad Bersimis KORADI-II GEN. 81 km 3 x 660 MW PARTICULARS 2 x 660 MW 2 x 780 MVA Quad Moose 3 x 660 MW 3 x 780 MVA 765 kV Commissioned Lines (PGCIL) 3 x 780 MVA 765 kV Proposed Lines (PGCIL) 2 x 1000 MVA 765 kV Commissioned Lines (MSETCL) 765 kV Proposed Lines (MSETCL) MAHARASHTRA STATE ELECTRICITY TRANSMISSION CO. LTD. 400 kV Commissioned Lines (PGCIL) State Transmission Utility,4th Floor, 400 kV Proposed Lines (PGCIL) Prakashganga',Bandra Kurla Complex SHEET - II 400 kV Commissioned Lines (MSETCL) Bandra (E), MUMBAI - 400 051 188 400 kV Proposed Lines (MSETCL)