Facility Administration Manual
Project Number: 42145 MFF Number: 0035 Updated as of 2 November 2011
Loan Numbers: Loan 2561-ARM (Project 1) Loan 2729-ARM (Project 2)
Republic of Armenia: Multitranche Financing Facility for the North–South Road Corridor Development Program
Important No te: This Facility administration manual is an active document. It will be updated and revised progressively as and when necessary during each review mission and following any changes in project investment costs, scope, or implementation arrangements. The contents herein are intended to assist and facilitate project management and implementation. If there is any conflict with any other legal agreement(s) related to this Investment program, the provision(s) in the legal agreement(s) will prevail. TABLE OF CONTENTS I. INTRODUCTION ...... 4
II. PURPOSE ...... 4
III. KEY PERSONS INVOLVED IN THE PROGRAM ...... 4
IV. PROCESSING HISTORY ...... 6
V. SPONSORS, STAKEHOLDERS, & EXTERNAL AGENCIES ...... 6 A. Sponsors B. Stakeholders C. External Agencies/International Financial Institutions (IFI)
VI. IMPACT, OUTCOMES, AND OUTPUTS ...... 6 A. Impact B. Outcomes C. Outputs
VII. IMPLEMENTATION ARRANGEMENTS ...... 7 A. Executing and Implementing Agencies B. Responsibility Allocation by Activity
VIII. IMPLEMENTATION SCHEDULE ...... 10 A. Implementation Schedule for Project 1 B. Implementation Schedule for Project 2
IX. COST ESTIMATES AND FINANCING PLAN DURING IMPLEMENTATION ..... 10 A. Cost Estimates Project 1 B. Cost Estimates Project 2 C. Allocation and Withdrawal of Loan Proceeds for Project 1 D. Allocation and Withdrawal of Loan Proceeds for Project 2
X. DISBURSEMENT PROCEDURES ...... 12
XI. CONSULTANT RECRUITMENT ...... 12
XII. PROCUREMENT ...... 12
XIII. PROJECT MONITORING AND EVALUATION ...... 13 A. Performance Indicators for Project 1 (as per Loan appraisal) B. Performance Indicators for Project 2 (as per Loan appraisal)
XIV. REPORTING REQUIREMENTS ...... 13
XV. AUDITING REQUIREMENTS ...... 14
XVI. MAJOR LOAN COVENANTS ...... 14
XVII. ANTICORRUPTION ...... 18
Abbreviations
ADB – Asian Development Bank DMF – design and monitoring framework EA – executing agency EARF – environmental Assessment and Review Framework EIA – environmental impact assessment EMP – environmental management plan FAM – facility administration manual FFA – framework financing agreement HIV/AIDS – human immunodeficiency virus/ acquired immunodeficiency syndrome IA – implementing agency IEE – initial environmental examination IFI – International Financial Institutions km – kilometer LARF – land acquisition and resettlement framework LARP – land acquisition and resettlement plan LIBOR – London interbank offered rate MFF – multitranche financing facility MOE – Ministry of Economy MOF – Ministry of Finance MOTC – Ministry of Transport and Communications MPW – Ministry of Public Works PFR – periodic financing report PMC – Project Management Consultant (PMC) PCMS – project communication management system PMO – Project Management Office PMU – project management unit PPMS – project performance monitoring system QCBS – quality- and cost based selection RRP – report and recommendation of the President to the Board RSA – Post-construction Road Safety Audit
I. INTRODUCTION
1. The Asian Development Bank (ADB) approved the $500 million Multitranche Financing Facility (MFF) for the North–South Road Corridor Development Program on 8 September 2009 to finance the improvement of the 550-kilometer (km) road corridor, modernize border, and customs infrastructure and facilities, and implement the road subsector strategy in Armenia. Per original plan, Tranche 1 Project will reconstruct an 18.4 km four-lane section of the Yerevan– Ashtarak road and improve road safety at Yerevan–Ararat road. The tranche 2 project will reconstruct and widen the 41.3 km, Ashtarak–Talin Section from two-lane to four-lane standard. The subsequent tranches are expected to include the upgrade and and/or rehabilitation of the remaining parts of the north–south road corridor. All other projects/subprojects to be included in the MFF will follow the agreed selection criteria.
2. ADB approved the Tranche 1 Project on 6 October 2009 for $60 million with project completion by 31 December 2013. As of November 2011, project 1 progress stands at 25% against the elapsed loan period of 44%.
3. ADB received the second Periodic Financing Request (PFR) for the Tranche 2 Project on 6 December 2010 in the amount of $170 million, and was approved by ADB on 21 December 2010, and became effective on 18 July 2011. Tranche 2 project will be implemented over 4 years, to be completed by 31 December 2014. All other projects/subprojects to be included in the MFF will follow the agreed selection criteria. As of November 2011, project 2 progress stands at 15% against the elapsed loan period of 20%.
II. PURPOSE
4. This Facility Administration Manual (FAM) focuses on the essentials for implementing the MFF and the second tranche project and will be updated as needed to reflect the implementation arrangements under the succeeding tranches. This FAM contains data and information that allows the Borrower, the executing agency, the implementing agency, and ADB to monitor project implementation and evaluate project impact.
III. KEY PERSONS INVOLVED IN THE PROGRAM
5. The department responsible for the implementation of the Project is the Central and West Asia Department (CWRD), represented by the Transport and Communications Division (CWTC). CWTC has the overall responsibility for implementing the project in ADB.
ADB Staff Transport & Communications Division Mr. Hong Wang (CWTC) Director, CWTC Central and West Asia Tel No. (632) 632 6765 / Email: [email protected] Department (CWRD) Mr. Arto Ahonen Transport Specialist / Project Officer Tel No. (632) 632 6716 / Email: [email protected]
Ms. Celia Africa Project Analyst, CWTC Tel No. (632) 632 6399 / Email: [email protected]
Ms. Anna Liza Silverio Operations Assistant Tel (632) 632-6716 / Email: [email protected]
Mr. L. Blanchetti-Revelli Sr. Social Development Specialist (Resettlement), CWOC Tel No. (632) 632 6231/ Email: [email protected]
Ms. Zehra Abbas Environment Specialist, CWOD-PSS Tel No. (632) 632 1761 / Email: [email protected]
Mr. Areg Barseghyan, AARM Sr. Country Coordination Officer, Armenia Resident Mission Tel No. (374 10) 546371(2,3,4) / Email: [email protected]
Ms. Gohar Mousaelyan Sr. Project Officer, Armenia Resident Mission Tel No. (374 10) 546371(2,3,4) / Email: [email protected]
Office of the General Counsel Mr. Baurzhan Konysbayev, Senior Counsel Tel No. (632) 632 4907 / Email: [email protected]
Controller's Department Mr. Viliami Sefesi, Financial Control Specialist, CTLA2 Loan Administration Division Tel No. (632) 632 6934 / Email: [email protected] (CTLA-2) Central Operations Services Office Mr. Amr Qari Consulting Operations Services Division 1 Procurement Specialist (COS1) Tel No. (632) 632 6462 / Email: [email protected]
Address: Asian Development Bank No. 6 ADB Avenue, Mandaluyong City 1550 Metro Manila P.O. Box 789 0980 Manila, Philippines
Facsimile (CWTC): (632) 636 2428 Website Address: http://www.adb.org
Executing/Implementing Agency Ministry of Transport and Communications Mr. Manouk Vardanyan Yerevan, Republic of Armenia Minister
Fax No: +374 10 524282 Mr. Hrant Beglaryan First Deputy Minister
Mr. Gagik Grigoryan Head, Foreign Relation Department
Project Management Unit Mr. Karen Badalyan, Acting PMU Head Ministry of Transport & Communications Phone/Fax/Email: +374 10 590147/526577 IV. PROCESSI NG HISTORY
MFF 0035 Project 1 (L2561) Project 2 (L2729) Approval of PPTA 12 December 2008 - - TA Completion 5 April 2010 - - Fact-Finding Mission/ 3–30 July 2009 3–30 July 2009 13-20 Sep 2010; Consultation Missions 25 Oct–4 Nov 2010 Management Review Meeting 19 August 2009 19 August 2009 Loan Negotiations - 31 Aug–1 Sep 2009 13–16 Dec 2010 Board/Management Approval 29 September 2009 6 October 2009 21 Dec 2010 Loan Agreement Signing 12 October 2009 12 October 2009 30 May 2011 Loan Effectiveness - 24 February 2010 18 July 2011
V. SPONSORS, STAKEHOLDERS, AND EXTERNAL AGENCIES
A. Sponsors (i) Ministry of Economy (MOE) (ii) Ministry of Finance (MOF) (iii) Ministry of Transport and Communications (MOTC) (iv) Asian Development Bank (ADB)
B. Stakeholders (i) Project Governing Council (ii) local self-government bodies (iii) transport and trade unions, freight forwarders, road users, affected people.
C. External Agencies/International Financial Institutions (IFI): (i) Japan International Cooperation Agency (ii) European Bank for Reconstruction and Development (iii) European Investment Bank (iv) World Bank (v) USAID
VI. IMPACT, OUTCOMES, AND OUTPUTS
A. Impact Project 1 and 2 of the investment program will contribute to socioeconomic development in Armenia and expanded regional trade.
B. Outcomes Efficient, safe, and sustainable north–south road corridor, linking Armenia domestically and internationally.
C. Outputs a. Project 1 output will be reconstructed 18.4 km four-lane section of the Yerevan– Ashtarak road and improved road safety for the Yerevan–Ararat road,
b. Project 2 output will be reconstructed and widened approximately 41.3km two- lane road between towns of Ashtarak and Talin into four-lane road
VII. IMPLEMENTATION ARRANGEMENTS
A. Executing and Implementing Agencies
6. MOTC will be the EA and will implement Projects 1 and 2 in accordance with the principles set forth in Schedule 1 to the FFA and the respective Loan Agreements for Project 1 and Project 2. For day-to-day activities like coordination, implementation of the Project 1 and Project 2 the North–South Road Corridor Investment Program Project Management Unit (PMU) State Non-Commercial Organization, established under MOTC serves as the implementing agency (IA) until the Project Management Consultant (PMC) financed under Tranche 2 Loan has been recruited. The Tranche 1 loan of the Investment Program will finance the PMU operations until the completion of Project 1. After completion of Project 1, the PMU operations will be financed by the government. Once the PMC has been recruited it will manage implementation of Project 1 and Project 2 on behalf of MOTC. The PMC will carry out the services in liaison with the MOTC and ADB. The MOTC will appoint a Project Director who will coordinate the implementation of the Project on behalf of MOTC.
7. The Project Director will be a qualified staff of MOTC with experience in project management. The PMC will introduce a suitable management information system to manage the Project. The PMC will prepare quarterly progress reports and will submit them to MOTC and ADB within 2 weeks from the end of the related quarter. The PMC will also submit other required performance and monitoring reports twice a year. Overall progress and compliance with conditions of the loan agreement will be monitored regularly with periodic reports to MOTC and ADB, consistent with existing project implementation requirements. Reports will include evaluation of issues and will recommend remedial actions. MOTC will recruit external individual consultants to audit a random sampling of documents issued or approved by the PMC.8. The PMC will maintain records and carry out the day-to-day coordination, monitoring and supervision of the Project, including the preparation of regular progress reports. The PMC will assist MOTC in the procurement of contracts in respect to the civil works for Project 1 and Project 2 of the MFF ensuring that procurement is carried out in compliance with ADB's Procurement Guidelines . The PMC will set up and operate an internet based multi-language tender platform on base of a project communication management system (PCMS). As applicable to the timing of the consultancy services contract, the PMC will update the bidding documents as necessary, acceptable for MOTC and ADB. The PMC will handle all contractual arrangements, including any revisions requested by contractors, ADB, and/or MOTC, to ensure quality and adherence to ADB’s rules and procedures. In case of any loan covenants and MFF undertakings the PMC will prepare assurance certifications and submit them to MOTC and ADB for approval. The PMC will ensure compliance with the contract conditions, payment terms, variations, dispute resolution, and monitoring, etc. The PMC will maintain all records relating to procurement, maintain a separate record relating to complaints and their redressing, and periodically update the procurement plan in agreement with MOTC and ADB to reflect the actual project implementation needs and improvements in institutional capacity. The PMC will also assist the MOTC and the ADB Mission during ADB project review missions. The PMC will organize trainings for the MOTC and other concerned authorities’ staff, according to the schedule to be agreed with MOTC and ADB.
8. The PMC will ensure financial management procedures are in place and are strictly followed, specifically relating to payments, financial accounting, financial reporting and record keeping. The PMC will carry out all financial management and administration under the Project, including review justifications provided for any variation orders proposed and submitted by the contractors, review withdrawal applications, maintain project accounts, prepare financial statements and submit them to MOTC and ADB for approval. 9. The PMC will monitor and report to MOTC and ADB the performance of the Project and ensure compliance with all social and environmental requirements and the requirements of design solutions. The PMC will develop a project performance monitoring system (PPMS), including a web-based PPMS, based on the design and monitoring framework (DMF) of Projects 1 (L2561-ARM) and 2 (L2729-ARM) of the MFF (refer to project and loan documents) according to ADB's Project Performance Management System (PPMS) Handbook, and operate and maintain the system providing full access to the system to MOTC. The PPMS will include key poverty and socioeconomic indicators and compliance with project assurances. The PPMS will monitor (i) performance targets set in the DMF through implementation; (ii) compliance with social and environmental safeguards as recommended in the Environment Assessment Review Framework (EARF), Initial Environmental Examination (IEE) for Project 1 of the MFF, Environmental Impact Assessment (EIA) for Project 2 of the MFF, Environmental Management Plan, Land Acquisition and Review Framework (LARF), and Land Acquisition and Resettlement Plan (LARP) for Project 2 of the MFF (refer to project and loan documents for Projects 1 and 2 of the MFF); other socioeconomic impact assessments including poverty impact. The PMC will ensure that all ADB policies and procedures on safeguards are followed throughout the implementation period. The PPMS will need to be approved by MOTC and ADB, and coordinated with ADB PPMS system. The PMC's responsibilities will be:
(i) Develop and implement an overall monitoring plan of the Project; (ii) Develop a consolidated construction program, showing the critical path of the overall implementation program. Any actions required Government actions that have potential implication in implementation should be attended timely and properly. Update overall Project planning accordingly; (iii) Review DMF performance targets, update and complement them with poverty and socioeconomic indicators, in agreement with MOTC and ADB; (iv) Compile baseline data for all performance targets and indicators as early as possible, but no later than first quarter of the construction mobilization; (v) Measure and report to MOTC and ADB progress of achieving the DMF performance targets at the MFF Project 1 and Project 2 midterm and completion stages; (vi) Monitor and report to MOTC and ADB socioeconomic impacts on beneficiaries through selective household surveys and participatory research methods; (vii) Monitor and report to MOTC and ADB compliance of the MFF Project 1 and Project 2 with the provisions preventing discrimination in employment, enforcing gender equality, and reducing risks of spread of communicable deceases; preventing human trafficking, and ensure that such requirements are included in the bid and contract documents; (viii) Monitor and report to MOTC and ADB compliance with MFF Project 1 and Project 2 assurances (refer to project and loan documents), including compliance with all environmental and social safeguards; (ix) Conduct training to build MOTC's capacity on performing impact assessments; (x) Ensure that the construction methods proposed by the contractor for carrying out the works are satisfactory, with particular reference to the technical requirements of sound environmental standards on the basis of ADB's Environmental Guidelines for Selected Infrastructure Development Proje ct (Highways &Roads) and the IEE, EIA and EMP prepared for the MFF Project 1 and Project 2; (xi) Assess the current procurement and financial management capacity of MOTC and prepare, in consultation with MOTC and ADB, an appropriate training program based on the results of the assessment. Conduct training. (xii) Document results in quarterly progress reports.
10. The PMC will report implementation progress of the Project to MOTC and ADB through quarterly and monthly progress reports. The quarterly progress reports should include project implementation status, major issues, and proposed corrective actions. The PMC will familiarize itself with all design and due diligence documents prepared for the MFF Project 1 and Project 2, covering all standard areas linked to project technical, financial, legal, economic, environmental, social, governance, fiduciary oversight, management, and institutional matters, ensure that all project related due diligence information is accurate and up-to-date, and present any updates to MOTC and ADB for approval as necessary.
11. The PMC will carry out all construction supervision activities for civil works for the Project, comprising upgrading and widening of the existing M1 Ashtarak to Talin road from two-lane single carriageway to four-lane dual carriageway road from Km 29+600 to Km 71+500. (Section 1), improvements of road safety measures of the existing M2 Yerevan to Ararat four-lane road from Km 9+312 to Km 47+ 400 (Section2) and rehabilitation of the existing M1 Yerevan to Ashtarak road from Km 18+370 to Km 29+773 (Section 3) in compliance with the requirements of international standards and best practices for highway construction.
B. Responsibility Allocation by Activity
Activities Responsible Parties EA PD CON CNT ADB 1. Establish Project Management Unit (PMU) or the Project Directorate (PD) Set up PMU/PD office 9 9* Recruit PMU/PD office staff 9 9* Procure office equipment and materials 9 9* 2. Prepare & Review Detailed Design & Bid Documents Engage Detailed Design Consultants 9* 9 Complete detailed design 9 9 9* 9 3. PMC Recruit PMC 9* 9 Day to day coordination, management, monitoring 9 9 9* 9 and technical supervision of Project1and Project 2 4. Civil Works Procurement Prepare Bid Documents 9 9 9* 9 Civil Works Procurement 9* 9 9 9 Civil Works Implementation 9 9 9 9* 9 5. Project Management and Administration Project Administration 9* 9 9 9 Construction Supervision 9 9 9* 9 Project Performance Monitoring 9 9 9* 9 Withdrawal and Disbursement 9 9 9* 9 Accounting and Auditing 9* 9* 9 9 Review of Covenant Compliance 9 9 9* 9* Midterm Review 9 9 9 9* Project Completion 9* 9 9 9 Loan Account Closing 9 9* ADB=Asian Development Bank, CNT=Contractors, CON=Consultants, CSRN=consulting services recruitment notice, EA=Executing Agency, EOI=expression of interest, RFP=request for proposals. * with primary responsibility VIII. IMPLEMENTATION SCHEDULE
A. Implementation Schedule for Project 1 Activity Target Date Field Supervision Consultants - Post CSRN 21 April 2010 - Evaluate EOIs and Shortlist* 25 Jun 2010 - Issue RFP 6 July 2010 - Evaluate technical & financial proposals 8 September 2010 - Negotiate/award contract 25 September 2010 - Mobilize consultants 5 October 2010 Mobilize Civil Works - Issue bidding documents 19 August 2011 - Evaluate bids November 2011 - Negotiate/award contract December 2011 Completion of construction By end-2013 *The EA delegated the selection of construction supervision consultants to ADB, with contract negotiations undertaken by the EA.
B. Implementation Schedule for Project 2 Activity Target Date Field Project Management Consultant (PMC) - Post CSRN 26 May 2011 - Evaluate EOIs and Shortlist* 28 September 2011 - Issue RFP 11 October 2011 - Evaluate technical & financial proposals By 15 December 2011 - Negotiate/award contract January 2011 - Mobilize consultants February 2011 Mobilize Civil Works - Issue bidding documents 19 August 2011 - Evaluate bids November 2011 - Negotiate/award contract December 2011 Completion of construction By end-2014
IX. COST ESTIMATES AND FINANCING PLAN DURING IMPLEMENTATION
A. Cost Estimates Project 1
Item Cos t Finance By ($ million) ADB Government A. Base Cost 1. Civil Works 38.0 38.0 0.0 2. Project Management and Institutional Support 7.0 7.0 0.0 3. Taxes and Duties 10.0 0.0 10.0 Subtotal (A) 55.0 45.0 10.0
B. Con tingencies 13.0 13.0 0.0 C. Interest During Construction 2.0 2.0 0.0 Total 70.0 60.0 10.0
B. Cost Estimates Project 2
Item Cost Financed By ($ million) ADB Government A. Bas e Cost 1. Land Acquisition and Resettlement 5.0 0.0 5.0 2. Civil Works 124.0 124.0 0.0 3. Consulting Services 7.0 7.0 0.0 4. Taxes and Duties 27.0 0.0 27.0 Subtotal 163.0 131.0 32.0 B. Con tingencies 37.0 29.0 8.0 C. Financing Charges during Construction 10.0 10.0 0.0 Total 210.0 170.0 40.0 Notes: 1. The government has requested a loan of $170 million from ADB’s ordinary capital resources to help finance Project 2. The loan will have a 24-year term, including a grace period of 4 years, an annual interest rate determined in accordance with ADB’s London interbank offered rate (LIBOR)-based lending facility, a commitment charge of 0.15% per year, and such other terms and conditions set forth in the loan agreement and the understandings in the FFA. 2. Retroactive financing is requested for the eligible expenditures, not exceeding 20% of ADB tranche financing, incurred before loan effectiveness, but not earlier than 12 months before the signing of the legal agreement.
C. Allocation and Withdrawal of Loan Proceeds for Project 1
CATEGORY ADB FINANCING Amount Allocated Percentage and Basis for SDR [$] '000 Withdrawal from the Loan Number Item Category Account* (%) 1 Works [38,000] 100 % of total expenditure 2 Consulting Services [5,000] 100 % of total expenditure 3 Goods [1,000] 100 % of total expenditure 4 Project Management Support [1,000] 100 % of total expenditure 5 Interest during construction [2,000] 100 % of amount due 6 Unallocated [13,000] TOTAL [60,000] * Exclusive of taxes and duties imposed within the territory of the Borrower.
D. Allocation and Withdrawal of Loan Proceeds for Project 2
CATEGORY ADB FINANCING Amount Allocated Percentage and [$] '000 Basis for Withdrawal No. Item Category from the Loan Account* (%) 1 Works 124.0 100 % of total expenditure 2 Consulting Services 7.0 100 %of total expenditure 3 Financing Charges during 10.0 100 %of amount due construction 4 Unallocated 29.0 100 %of amount due TOTAL 170.0 * Exclusive of taxes and duties imposed within the territory of the Borrower. X. DISBURSE MENT PROCEDURES
12. ADB’s Loan Disburse ment Handbook (2007) will guide the disbursement of loans proceeds from the project, following the provisions of Schedule 3 of the Loan Agreements.
(i) Direct payment procedures will be used for civil works expenditures, progress payments to consultants, and procurement of goods.
(ii) The initial withdrawal application to be submitted to ADB must include (i) an authorization letter from the Ministry of Finance, (ii) specimen signatures of authorized signatories, and (iii) duly accomplished estimate of expenditures sheet.
XI. CON SULTANT RECRUITMENT
13. For Project 1 a total of 72 person-months of international consulting services and 174 person-months of national consulting services are required for Construction Supervision and and preparation of tranches 2 and 3 Projects. The consultants will be recruited according to ADB's Guidelines on the Use of Consultants (2007, as amended from time to time) using quality- and cost-based selection (QCBS) method (80% for quality and 20% for cost).
14. A total of 180 person-months of international consulting services and 439 person-months of national consulting services are required for Project Management Consultant for Projects 1 and 2. The consultants will be recruited according to ADB's Guidelines on t he Use o f Consultants (April 2010, as amended from time to time) using quality- and cost-based selection (QCBS) method (90% for quality and 10% for cost).
XII. PROCUREMENT
15. ADB-financed works, goods, and services will be procured according to ADB’s Procurement Guidelines and Guidelines on the Use of Consultants b y ADB and it ’s Borrowers, respectively (2007 and 2010 for Project 1 and Project 2 respectively, as amended from time to time). The MOTC and ADB have agreed that civil works under Project 1 and Project 2 will be combined in one contract with three sections, comprising reconstruction and improvement of the M1 Ashtarak to Talin road from km 29+600 to km 71+500 (Section 1), M2 Yerevan to Ararat road from km 9+312 to km 47+400 (Section2) and M1 Yerevan to Ashtarak road from km 18+370 to km 29+773 (Section 3) .The Government will use international competitive bidding with post qualification and one-stage-one-envelope bidding procedure. Contract award is expected in December 2011, with completion of Project 1 civil works (sections 2 and 3) by end 2013, and Project 2 civil works (section 1) by end 2014, respectively.
16. Before granting an extension of the time for completion of any contract for Goods, works and/or consulting services, including issuing any change order or orders under such contract, the Government will need to seek ADB’s no objection to the proposed extension, modification, or change order. A copy of all amendments to the contract will need to be furnished to ADB for its record.
XIII. PROJECT MONITORING AND EVALUATION
A. Performance Indicators for Project 1 (as per Loan appraisal)
(i) Reduced travel time from Yerevan to Gyumri to 1.0 hour by 2015 (from 1.5 hours in 2008) (ii) Increased daily traffic from Yerevan to Gyumri to 14,500 vehicles in 2015 (from 9,300 vehicles in 2009) (iii) About 1.6 million people to benefit from improvement of Yerevan to Gyumri road
B. Performance Indicators for Project 2 (as per Loan appraisal)
(i) Reduced travel time from Yerevan to Talin to 0.6 hour by 2015 (from 1.33 hours in 2009) (ii) Increased daily traffic from Ashtarak to Talin (from 5,800 vehicles in 2009 to 9400 vehicles in 2015) (iii) About 1.6 million people to benefit from improvement of Yerevan to Gyumri road
Safeguards Monitoring Reporting Schedule 2011 2012 2013 2014 June Dec June Dec June Dec June Dec
Environment Monitoring Report P1 P1 P1 P1 P1 P1 - - P2 P2 P2 P2 P2 P2 P2 P2 2011 2012 2013 2014
June Dec June Dec Jan Dec June Dec
Involuntary Resettlement Report - P2 P2 - P2 - - - P1-Project 1; P2 –Project 2
XIV. REP ORTING REQUIREMENTS 17. The PMC will report implementation progress of Project 1 and Project 2 to MOTC and ADB through quarterly and monthly progress reports. The quarterly progress reports should include project implementation status, major issues, and proposed corrective actions. The consultants will familiarize themselves with all design and due diligence documents prepared for the MFF Project 1 and Project 2, covering all standard areas linked to project technical, financial, legal, economic, environmental, social, governance, fiduciary oversight, management, and institutional matters, ensure that all project related due diligence information is accurate and up-to-date, and present any updates to MOTC and ADB for approval as necessary. The PMC for Project 1 and Project 2 shall submit (i) Pre-construction; (ii) During Construction; and (iii) Post-construction Road Safety Audit (RSA) reports. In addition the PMC shall submit a relevant report for Accident Analysis and Mitigation based on their findings on the study conducted by the PMC during construction. The PMC will indicate the delivery dates of these reports in the Inception Report. The PMC will draft a PCR prior to physical completion of construction works in a manner satisfactory to MOTC and ADB, including the major project events, performance of the contractors, operation of the Project, actual and price inflated (to completion year) project cost (foreign and local costs separately) by implementation year, and labor employed by skilled/unskilled and foreign/local categories in man-years; (i) the major project events, the relative successes (problems) in the implementation of each of the sections, this section of the PCR shall also contain an assessment of the impact of road improvement on the economy and social aspects for the whole project area; (ii) "as-built" drawings (to be submitted to MOTC). These "as-built" drawings will be furnished by the Contractor as per Clause 4.1 (d) of the construction contract; (iii) detailed description of all the works by items of technical and non-technical matters, economic analysis, financial and disbursement data, analyses, difficulties and delays encountered or anticipated, and remedial actions taken or suggested, the overall progress of the Project as monitored against the design and monitoring framework and PPMS indicators, including recommendations to MOTC and ADB.
XV. AUDITIN G REQUIREMENTS
18. The MOTC will maintain separate project records and accounts adequate to identify the (i) goods and services financed from the loan proceeds, (ii) financing resources received, (iii) expenses incurred on the components, and (iv) use of counterpart funds. MOTC will engage independent external auditors acceptable to ADB to audit Projects accounts and financial statements annually, and will arrange a periodic or annual audit of statement of expenditure transactions Project 1 and financial statements and accounts of Project 2. MOTC will submit to ADB certified copies of audited annual projects accounts and related financial statements as well as the auditor’s report in English within 6 months of the end of each fiscal year during implementation.
XVI. MAJOR LOAN COVENANTS
A. Major Loan Covenants for Project 1
1. Road sector master plan
• The Borrower shall prepare a long-term Road Subsector Plan (2010–2020) and adopt it for implementation by 30 June 2010. Such plan shall detail policy actions and measures to: (i) establish a system for efficient planning and prioritization of road maintenance works; (ii) provide funding modalities to finance the maintenance of relevant roads acceptable to ADB; (iii) develop or adopt adequate road maintenance standards and prepare relevant road maintenance planning and operational manuals; and (iv) provide training to strengthen the capacity of local maintenance units.
2. Polic y Dialogue
• The Borrower shall ensure that ADB is kept informed of Borrower's policies and programs related to the road subsector that will materially affect the economic viability of the Project or any other project, subproject, or component financed under the Facility.
• Further, the Borrower shall ensure that: (i) policies under the PCA with the PMU governing the road subsector development and operations are harmonized in a way that road subsector roadmap and investment plan under the Investment Program are implemented coherently; (ii) best efforts are used to facilitate cross-border transit of road transport consistent with the European Agreement on Main International Traffic Arteries of 15 November 1975, and (iii) developing the human resources, technical, managerial and
administrative capacity in the 16 Schedule 5 road subsector to achieve greater efficiency in planning, developing and operating the infrastructure financed under the Investment Program is of high priority. Change in Ownership and Operation
• If any of the following is anticipated: (i) any change in ownership of the road, road facility, or structure financed under the Project; (ii) any sale, transfer, or assignment of interest or control in the road, road facility, or structure financed under the Project; or (iii) any lease or other contract or modification of the functions and authority of the ARD over operation and maintenance of any road, road facility, or structure financed under the Project; then the Borrower shall ensure that ADB’s consent is obtained at least six (6) months prior to the implementation of such a plan. The Borrower shall ensure that any such changes will be carried out in a legal and transparent manner. Counterpart Funding
• The Borrower shall ensure that (i) financial, technical and human resources are provided on a timely basis; (ii) adequate funds to sustainably maintain the road corridor throughout its service life are allocated; (iii) financial, human and technical resources to implement the road transport subsector plan are made available; and (iv) best efforts are used to obtain additional external financing as may be necessary for the reconstruction and rehabilitation of the north–south road corridor agreed with ADB.
3. Road maintenance funding
• The Borrower shall ensure that actual annual expenditures for road maintenance (including emergency maintenance, but excluding rehabilitation and new construction) for roads within ARD's jurisdiction are increased at least by 5% from the actual amount of road maintenance budget for 2008, adjusted for inflation at the same rate as increases in the overall national budget during 2010–2015.
4. Construction Quality
• The Borrower shall ensure that (i) the Project road is rehabilitated or constructed in accordance with the technical specifications of the design, construction specifications and other documents stipulated in the bidding documents; and (ii) construction supervision, quality control and contract management are performed in accordance with internationally acceptable standards. The Borrower shall cause MOTC and ARD to build, equip, operate, maintain and manage the Project facilities in compliance with all international agreements and conventions to which Armenia is a party.
5. Road safety
• The Borrower shall ensure that MOTC installs appropriate road safety signs and facilities during the Project implementation and after completion, such as warning signs, pavement markings, road signs and signals, communications facilities, hazard barriers, and traffic monitoring facilities, all in compliance with industry's best practices and relevant international conventions to which the Borrower is a party. The Borrower shall ensure that, at least six (6) months prior to the opening for operation of the Project Road, (i) MOTC will have developed and implemented a plan, acceptable to ADB, for ensuring safe operation of road infrastructure facilities; and (ii) relevant Borrower's authorities will have prepared to police the Project Road and enforce the national laws and regulations. The Borrower shall ensure that MOTC monitors the accident rate and traffic volume after commencement of the operation of the Project Road and institutes appropriate safety enforcement measures.
6. Environment
• The Borrower shall ensure that the Project is designed, carried out, maintained, and monitored in compliance with (a) all applicable environmental laws and regulations; (b) ADB’s Environment Policy (2002); and (c) the EMP, including the mitigation measures and monitoring requirements arising from the implementation of the IEE. The Borrower shall also cause MOTC to ensure that: (a) Works contractors’ specifications include requirements to comply with the environmental mitigation measures contained in the IEE and EMP, and (b) Works contractors are supervised to ensure compliance with the requirements of the IEE and EMP.
7. Land acquisition and resettlement
• While the Project does not anticipate land acquisition and resettlement activities, if and to the extent such become necessary, the Borrower shall ensure that land acquisition and resettlement are carried out promptly and efficiently following the land acquisition and resettlement plan prepared in accordance with applicable laws and regulations, ADB’s Involuntary Resettle ment Policy (1995), and the land acquisition and resettlement framework agreed with ADB pursuant to FFA. The Borrower shall ensure that implementation of the land acquisition and resettlement plan is monitored, evaluated, and reported to ADB as required in the resettlement plan. The Borrower shall also ensure that all land and right-of-way required for project implementation are made available to the Project in a timely manner.
• The Borrower shall ensure that contractors commence the Works only after the land acquisition and resettlement plan has been implemented with respect to the relevant road section in accordance with its terms.
8. Local consultation and gender
• The Borrower shall ensure that all local consultations with respect to safety, social, and cultural issues during Project implementation are carried out as recommended in the summary poverty reduction and social analysis prepared for the Project. The mechanisms for maximizing local employment benefits shall be included in the bidding documents.
9. Labor
• The Borrower shall ensure that all Works contractors (i) comply with all applicable labor laws; (ii) use their best efforts to employ women and local people, including disadvantaged people, living in the vicinity of the Project; (iii) disseminate information on the risks of sexually transmitted infections to those at worksites employed during construction; (iv) provide equal pay to men and women for work of equal type; (v) provide safe working conditions for male and female workers; and (vi) abstain from child labor. Relevant Works contracts financed under the Project must include specific clauses on these undertakings, and compliance will be strictly monitored during implementation.
10. Health risks and prevention
• The Borrower shall ensure that the Works contracts include a requirement to conduct an information and education campaign on sexually transmitted diseases and HIV/AIDS for construction workers as part of the health and safety program at campsites during the construction period.
11. Illegal trafficking
• The Borrower shall undertake concrete and adequate measures to detect and prevent trafficking of humans, wildlife, endangered species, and illegal substances on the Project Road.
B. MAJOR LOAN COVENANTS FOR PROJECT 2
• Construction Quality. The MOTC will ensure that the construction of the Project road complies with technical specifications of the design. The MOTC, through the PMU and the construction supervision consultant, will ensure that construction supervision, quality control, and Project management are undertaken according to internationally accepted standards and practices.
• Road Main tenance. The MOTC will ensure that (i) financial, technical and human resources are provided on a timely basis; (ii) adequate funds to sustainably maintain the road corridor throughout its service life are allocated; (iii) financial, human and technical resources to implement the road transport subsector plan are made available; and (iv) best efforts are used to obtain additional external financing as may be necessary for the reconstruction and rehabilitation of the north–south road corridor agreed with ADB.
• Road Safety. The MOTC will ensure that appropriate road safety signs and facilities are installed during the Project implementation and after completion, such as warning signs, pavement markings, road signs and signals, communications facilities, hazard barriers, and traffic monitoring facilities, all in compliance with industry's best practices and relevant international conventions to which the Borrower is a party. Furthermore, the MOTC will ensure that, at least 6 months prior to the opening for operation of the Project Road, (i) the PMU and construction supervision consultant will have developed and implemented a plan, acceptable to ADB, for ensuring safe operation of road infrastructure facilities; and (ii) relevant Government authorities will have prepared to police the Project Road and enforce the national laws and regulations. The MOTC will monitor the accident rate and traffic volume after commencement of the operation of the Project Road and institutes appropriate safety enforcement measures.
• Axle Loads. The MOTC will ensure that vehicle weighing stations along the Project road to control the axle overloading and formulate appropriate procedures and regulations to enforce the axle load controls will be established.
• Vehicle Emissions. MOTC will, through the relevant agencies, enforce that the vehicle emission standards are followed.
• Environment. The MOTC will ensure that (i) all roads, and road facilities and structures, under this Project are designed, constructed, and operated in accordance with all applicable laws and regulations of Armenia, ADB’s Safeguard Policy Statement (2009), and environmental impact assessment (EIA); (ii) any adverse environmental impacts are minimized by the mitigating measures and the monitoring program set out in the environmental management plan (EMP) in the EIA; (iii) implementation of the EMP and any violation of the environmental standards are reported to ADB semiannually in accordance with the EIA; and (iv) the EMP is incorporated in the bidding documents and bill of quantities of the civil works contracts. The EA will ensure that the detailed design sufficiently addresses any Government and/or ADB concerns regarding archaeological findings and provide appropriate solutions as well as chance-find procedures during implementation for avoiding and mitigating all impacts.
• Land Acquisition and Resettlem ent. The MOTC will ensure that land acquisition or involuntary resettlement shall be promptly and efficiently carried out in a legal and transparent manner in accordance with the resettlement framework attached to the FFA, and in compliance with the LARP, applicable laws and regulations of Armenia, and ADB’s Safeguards Policy Statement (SPS) (2009); and (iii) all land needed temporarily during construction is leased from the willing lessors. The MOTC shall ensure that contractors commence the Works only after the land acquisition and resettlement plan has been implemented with respect to the relevant road section in accordance with its terms.
• Labour, Social, Gender and Development, Health. The MOTC will ensure that all local consultations with respect to safety, social, and cultural issues during Project implementation are carried out as recommended in the summary poverty reduction and social analysis prepared for the Project. The mechanisms for maximizing local employment benefits shall be included in the bidding documents. MOTC will ensure that all Works contractors (i) comply with all applicable labor laws; (ii) use their best efforts to employ women and local people, including disadvantaged people, living in the vicinity of the Project; (iii) disseminate information on the risks of sexually transmitted infections to those at worksites employed during construction; (iv) provide equal pay to men and women for work of equal type; (v) provide safe working conditions for male and female workers; and (vi) abstain from child labor. Relevant Works contracts financed under the Project must include specific clauses on these undertakings, and compliance will be strictly monitored during implementation. The MOTC will ensure that the Works contracts include a requirement to conduct an information and education campaign on sexually transmitted diseases and HIV/AIDS for construction workers as part of the health and safety program at campsites during the construction period. The MOTC shall undertake concrete and adequate measures to detect and prevent trafficking of humans, wildlife, endangered species, and illegal substances on the Project Road.
XVII. ANTICORRUPTION
20Consistent with ADB’s Anticorruption Policy and its commitment to good governance, accountability, and transparency, ADB reserves the right to investigate, directly or through its agents, any alleged corrupt, fraudulent, collusive, or coercive practices relating to Projects 1 and 2. To support these efforts, relevant provisions of ADB’s Anticorruption Policy are included in the loan regulations and bidding documents for the project road. In particular, all contracts financed by ADB in connection with Projects1 and 2 will include provisions specifying the right of ADB to audit and examine the records and accounts of the PMU and all contractors, suppliers, consultants, and other service providers as they relate to Projects 1 and 2.
21The Government agreed to take additional measures to improve governance, accountability, and transparency under Projects1 and 2. These measures include (i) independent external auditing of contracts, project accounts, and financial statements; (ii) decisions of all procurement-related matters by the Tendering Committee, which comprises representatives of the Ministry of Economic Development, Ministry of Finance, Ministry of Transport, and the State Procurement Agency (as observer) in accordance with ADB’s Procurement Guidelines; (iii) verification of contractors’ payment claims by the supervision consultant in accordance with contract specifications; and (iv) timely disclosure of information on selection of consultants and contractors through local newspapers.
APPENDIXES
Appendix 1 Periodic Financing Requests for Tranche 1 and 2 Projects Appendix 2 Project Organizational Chart Appendix 3 Procurement Plans Appendix 4 TORs for Consulting Services Appendix 5 Detailed Implementation Schedules Appendix 6 Contract Awards and Disbursements Projections Appendix 7 EA’s Progress Report Format Appendix 8 Environmental Assessment and Review Framework for the MFF Program Appendix 9 Initial Environmental Examination for Project 1 Appendix 10 Environmental Impact Assessment for Project 2 Appendix 11 Land Acquisition and Resettlement Framework Appendix 12 Land Acquisition and Resettlement Plan for Project 2
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.
Attachment
TRANCHE 1 PROJECT SUMMARY
Project Description The Tranche 1 Project (Project 1) will (i) reconstruct 18.4 km four-lane section of the Yerevan–Ashtarak road, (ii) improve road safety for the Yerevan–Ararat road, (iii) prepare design and bidding documents for tranche 2 and 3 projects, and (iv) help implement the road subsector plan under the Transport Sector Strategy..
Cost Estimates and The total cost of Project 1—including taxes, duties, physical and price Financing Plan contingencies, interest, and other charges—is estimated at $70 million equivalent.
Cost Estimates Item Cost ($ million) A. Base Cost 1. Civil Works 38.0 2. Project Management Support 1.0 3. Consulting Services for Project Implementation 4.0 4. Support for Road Subsector Plan 2.0 5. Taxes and Duties 10.0 Subtotal (A) 55.0 B. Con tingencies 13.0 C. Interest During Construction 2.0 Total 70.0 Source: Asian Development Bank estimates.
Financing Plan Source Amoun t % ($ million) Asian Development Bank Special Funds Resources 60.0 86 Government 10.0 14 Total 70.0 100 Source: Asian Development Bank estimates.
Loan Amount and The request is for a loan of $60 million from the Special Funds resources Terms of the Asian Development Bank (ADB) provided with a 32 years, including a grace period of 8 years, and interest of 1.0% per annum during the grace period and 1.5% per annum thereafter, and such other terms and conditions as agreed in the FFA, and further supplemented under the Loan Agreement.
Period of The components are expected to be completed by 31 December 2013. Loan Utilization No disbursements from the loan account will be requested or made later than 30 June 2014. The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in Advance contracting is requested for detailed design consultancy and civil Advancenature. Contracting works.
Retroactive Retroactive financing is requested for the eligible expenditures, not Financing exceeding 20% of ADB tranche financing, incurred before loan effectiveness, but not earlier than 12 months before the signing of the legal agreement.
Implementation The Ministry of Transport and Communication (MOTC) will be the Arrangements executing agency (EA) responsible for overall planning and implementation of the Investment Program and coordination with Project Governing Council (PGC). MOTC will sign and act as an Employer for contracts with consultants and contractors. Implementation and monitoring of the Investment Program will be delegated to the Armenian Road Directorate (ARD), which will serve as the implementing agency (IA). ARD will set up a Program Management Unit (PMU) to manage day- to-day coordination, implementation, and administration activities of individual projects, including (i) selecting individual tranche projects, (ii) maintaining project accounts, (iii) handling the procurement, (iv) monitoring and reporting on individual project implementation, (v) facilitating environmental and social safeguards measures, (vi) selecting consultants, and (vii) overseeing detailed designs and construction supervision. ARD will appoint a program implementation team comprising expertise in highway engineering, tunneling, procurement, project management, financial accounting, and social and environmental safeguards.
Procurement and The procurement plan is attached as Annex 1. Consulting Services
Readiness of The Government will start detailed design of Tranche 1 Project in October the Project for 2009 with its own resources. The designs and bidding documents will be Implementation completed by December 2009.
The Government will start pre-qualification of contractors in September. Bidding for civil works will start by mid-December 2009 for targeted commencement of construction by April 2010.
Safeguards Environment: Category B. An initial environmental examination (IEE) is in Annex 2. Involuntary resettlement: Category C – limited or no impact Indigenous people: Category C – limited or no impact The summary poverty reduction and social strategy is in Annex 3.
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.
PROCUREMENT PLAN (TRANCHE 1 PROJECT)
Project Name: North–South Road Corridor Multitranche Financing Facility Number: to be Investment Program assigned Periodic Financing Request 1 Number: to be assigned Multitranche Financing Facilit y A mount: $500 Executing Agen cy: Ministry of Transport and million Communication Tranche 1 Periodic Financing Requ est Amou nt: $60.0 million Date of First Procurement Plan: 29 July 2009 Date of this Procurement Plan: 1 September 2009
A. Section 1: Process Thresholds, Review, and 18-Month Procurement Plan
1. Project Procurement Thresholds
1. Except as the Asian Development Bank (ADB) may otherwise agree, the following process thresholds shall apply to procurement of goods and works.
Procurement of Goods and Works Method Thresh old International Competitive Bidding for Works More than $1,000,000 International Competitive Bidding for Goods More than $500,000 National Competitive Bidding for Works Less than $1,000,000 Shopping for Works Less than $100,000 Shopping for Goods Less than $100,000
2. ADB Prior or Post Review
2. Except as ADB may otherwise agree, the following prior- or post-review requirements apply to the various procurement and consultant recruitment methods used for the Project.
Procurement of Goods and Works Procurement Method Prior or Post Comments International Competitive Bidding for Works Prior International Competitive Bidding for Goods Prior National Competitive Bidding for Goods Prior National Competitive Bidding for Works Prior Shopping for Works Prior Shopping for Goods Prior
Recruitment of Consulting Firms Quality- and Cost-Based Selection Prior Other selection methods: QBS, CQS, LCS, or SSS Prior To be determined during implementation. Recruitment of Individual Consultants Individual Consultants Prior CQS = consultant's qualification selection, LCS = least cost selection, QBS = quality-based selection, SSS = singeThe views source expressed selection. herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.
3. Goods and Works Contracts Estimated to Cost More than $1 Million
3. The following table lists goods and works contracts for which procurement activity is either ongoing or expected to commence within the next 18 months.
Contract Prequalification General Value Procurement of Bidders Advertisement Description ($ million) Method (Yes/No) Date (quarter/year) Comments Civil Works 38.0 ICB Yes Q4 2009 ICB = international competitive bidding, Q = quarter.
4. Consulting Services Contracts Estimated to Cost More than $100,000
4. The following table lists consulting services contracts for which procurement activity is either ongoing or expected to commence within the next 18 months.
Contract Advertise- International Value Recruitment ment Date or National General Description ($ million) Method (quarter/year) Assignment Comments Detailed Design for 0.2 CQS and Q3 2009 International With international Tranche 1 Project international or National individual individual consultants consultant Construction 3.8 QCBS Q4 2009 International Quality–cost ratio Supervision and Design 80/20 of Tranche 2 and 3 Projects Consulting Services for 1.0 QCBS Q4 2009 International Quality–cost ratio Implementation of 80/20 Road Subsector Plan CQS = consultant's qualification selection, QCBS = quality- and cost-based selection, Q = quarter.
5. Goods and Works Contracts Estimated to Cost Less than $1 Million and Consulting Services Contracts Less than $100,000
5. The following table groups smaller-value goods, works, and consulting services contracts for which procurement activity is either ongoing or expected to commence within the next 18 months.
Value of Contracts Procurement/ General (cumulative) Number of Recruitment Description Contracts Method Comments Traffic Management $1.0 million Up to 10 Shopping and Monitoring Equipment
B. Section 2: Project Procurement Plan
The views1. expressedIndicative herein List are of thosePackages of the Required consultant Under and do the not Project necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in 6.nature. The following table provides an indicative list of all procurement (goods, works, and consulting services) over the life of the project.
Estimated Value Estimated Domestic ($ million, Number of Procurement Preference General Description cumulative) Contracts Method Applicable Comments Works Civil works contract 38.00 1 ICB No package for improvement One-envelope of Yerevan–Ashtarak single stage with road (Km 11.8 to Km prequalification 30.2) and road safety improvement of Yerevan– Ararat road Goods Traffic management and 1.00 several Shopping No monitoring equipment Consulting Services Design of Civil Woks 0.15 several CQS Tranche 1 Project 0.05 and individual consultant
Construction Supervision 3.80 1 QCBS with FTP quality–cost for Tranche 1 Project and ratio 80/20 Design of Tranche 2 and 3 Projects
Project Management Unit 0.90 several Individual To be consultants determined External Financial Audit 0.10 1 LCS Yes
CQS = consultant's qualification selection, FTP = full technical proposal, ICB = international competitive bidding, LCS = least-cost selection, QCBS = quality- and cost-based selection.
C. National Competitive Bidding
1. General
7. The procedures to be followed for national competitive bidding shall be the open tender method (including the two-stage where appropriate) set forth in the Law on Procurements of 1 January 2005 with the clarifications and modifications described in the following paragraphs required for compliance with the provisions of ADB’s Procurement Guidelines (2007, as amended from time to time).
2. Eligibility
8. The eligibility of bidders shall be as defined under section I of ADB’s Procurement Guidelines; accordingly, no bidder or potential bidder should be declared ineligible for reasons other than those provided in section I of ADB’s Procurement Guidelines. Bidders must be nationals of member countries of ADB, and offered goods, services, and works must be produced in and supplied from member countries of ADB. The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.
3. Prequalification
9. Postqualification shall be used, unless prequalification is explicitly provided for in the loan agreement and/or procurement plan. Domestic and foreign contractors shall be allowed to participate in bid exercises using postqualification procedure. In case prequalification of contractors is stipulated in the loan agreement/procurement plan, domestic and foreign contractors shall be allowed to participate in the prequalification exercise.
4. Registration and Licensing
(i) Bidding shall not be restricted to pre-registered/licensed firms.
(ii) Where registration or licensing is required, bidders (a) shall be allowed a reasonable time to complete the registration or licensing process; and (b) shall not be denied registration and/or licensing for reasons unrelated to their capability and resources to successfully perform the contract, which shall be verified through postqualification.
(iii) Foreign bidders shall not be precluded from bidding. If a registration or licensing process is required, a foreign bidder declared the lowest evaluated bidder shall be given a reasonable opportunity to register or to obtain a license.
5. Biddi ng Period 10. The minimum bidding period is 28 days prior to the deadline for the submission of bids.
6. Bidding Documents 11. Procuring entities should use standard bidding documents for the procurement of goods, works, and services acceptable to ADB.
7. Prefere nces 12. No domestic preference shall be given for domestic bidders and for domestically manufactured goods.
8. Advert ising
13. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper or freely accessible, nationally known website allowing a minimum of 28 days for the preparation and submission of bids. Bidding of national competitive bidding contracts estimated at $500,000 equivalent or more for goods and related services or $1,000,000 equivalent or more for civil works shall be advertised on ADB’s website via the posting of the procurement plan.
9. Secur ities The views(i) expressed Bid security herein (tender are those security). of the Whereconsultant required, and do bid not security necessarily shall representbe in the formthose of a of ADB’s members,bank guarantee Board of fromDirectors, a reputable Management, bank. or staff, and may be preliminary in nature. (ii) Performance security (contract execution security). Performance security shall be provided within 28 days of the notification of contract award.
10. Bid Opening and Bid Evaluation
(i) Bids shall be opened in public.
(ii) No bid shall be declared invalid/rejected at the time of bid opening.
(iii) Minutes and/or record of bid opening shall be provided to all bidders.
(iv) Evaluation of bids shall be made in strict adherence with the criteria declared in the bidding documents and contracts shall be awarded to the lowest evaluated bidder.
(v) Bidders shall not be eliminated from detailed evaluation on the basis of minor, nonsubstantial deviations.
(vi) No bidder shall be rejected on the basis of a comparison with the employer's estimate and budget ceiling without ADB’s prior concurrence.
(vii) A contract shall be awarded to the technically responsive bidder that offers the lowest evaluated price and meets the qualifying requirements. Negotiations shall not be permitted.
(viii) Price verification shall not be applied.
11. Rejection of All Bids and Rebidding
14. Bids shall not be rejected and new bids solicited without ADB’s prior concurrence. Bids shall not be declared invalid because of procedural delays on the part of executing agencies without ADB’s prior approval.
12. Participation by Government-Owned Enterprises
15. Government-owned enterprises in Armenia shall be eligible to participate as bidders only if they can establish that they are legally and financially autonomous, operate under commercial law, and are not a dependent agency of the contracting authority/executing agency/implementing agency. Furthermore, they will be subject to the same bid and performance security requirements as other bidders.
13. Right to Inspect/Audit
16. A provision shall be included in all national competitive bidding works and goods contracts financed by ADB requiring suppliers and contractors to permit ADB to inspect their accounts and records and other documents relating to the bid submission and the performance of the contract, and to have them audited by auditors appointed by ADB.
14. Fraud and Corruption The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s(i) members, The Borrower Board ofshall Directors, reject aManagement, proposal for oraward staff, if andit determines may be preliminary that the bidderin nature. recommended for award has, directly or through an agent, engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the contract in question.
(ii) ADB will declare a firm or individual ineligible, either indefinitely or for a stated period, to be awarded a contract financed by ADB, if it at any time determines that the firm or individual has, directly or through an agent, engaged in corrupt, fraudulent, collusive, or coercive practices in competing for, or in executing, an ADB-financed contract.
15. Joint Venture and Estimated Contract Prices
(i) Joint venture partners shall be jointly and severally liable for their obligations.
(ii) Estimated contract prices shall not be advertised.
16. Disclosure of Decision on Contract Awards
17. At the same time that notification on award of contract is given to the successful bidder, the results of bid evaluation shall be published in a local newspaper, or a well-known freely accessible website identifying the bid and lot numbers and providing information on (i) the name of each bidder who submitted a bid; (ii) bid prices as read out at bid opening; (iii) the names of bidders whose bids were rejected and the reasons for their rejection; and (iv) the name of the winning bidder, and the price it offered, as well as duration and summary scope of the contract awarded. The executing showing separately net cost, contingencies, and taxes agency/implementing agency/contracting authority shall respond in writing to unsuccessful bidders who seek explanations on the grounds on which their bids are not selected.
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.
Annex 2
Initial Environmental Examination Report Project Number: TA 7208 August 2009
Armenia: Preparing the North-South Road Corridor Development Program (Tranche 1 Roads Improvement Project—Two Road Sections: Yerevan to Ashtarak and Yerevan to Ararat)
The initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members, Board of Directors, Management, or staff, and may be preliminary in nature.
LIST of ABBREVIATIONS
ADB Asian Development Bank ARD Armenia Roads Directorate EIA Environmental Impact Assessment EM Environmental Manager (in ARD) EMP Environmental Management Plan IEE Initial Environmental Examination IES International Environmental Specialist Km Kilometre (s) MFF Multi-tranche Financing Facility MNP Ministry of nature Protection MOTC Ministry of Transport and Communications NE North East NPE Nature Protection Expertise PPP Purchasing Power Parity RA Republic of Armenia ROW Right-of-Way SEI State Environmental Inspectorate SNCO State Non-Commercial Organization SW South West
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
TABLE OF CONTENTS Page
I. INTRODUCTION and SUMMARY 1 A. Project Background 1 B. IEE Report Outline and Methodology 3 C. Armenian and ADB Environmental Assessment Requirements 3 D. Alternatives to the Proposed Project 6
II. PROJECT DESCRIPTION 7 A. Project Location 7 B. Tranche 1 Project 8
III. ENVIRONMENTAL BASELINE – EXISTING CONDITIONS 9 A. Physical Resources 9 B. Ecological Resources 11 C. Human Use of Resources 11 D. Human Quality-of-Life Values (Social and Cultural Resources) 11
IV. SCREENING FOR POTENTIAL ENVIRONMENTAL IMPACTS 12 A. Environmental Parameters that may be Impacted 12 B. Activities that may Create Environmental Impacts 12 C. Environmental Screening: Potential Impacts 13 D. Significance of Potential Impacts 15
V. ENVIRONMENTAL IMPACT PREVENTION and MITIGATION MEASURES 16 A. Environmental Impact Prevention and Mitigation 16 B. Environmental Management Plan (EMP) 16 C. Responsibilities for Impact Prevention and Mitigation 25 D. Environmental Enhancement Measures 26 E. Environmental Monitoring Program 26 F. Cost of Impact Prevention, Mitigation, Monitoring and Enhancement 26 G. Environmental Management Seminars 28
VI. PUBLIC CONSULTATION and INFORMATION DISCLOSURE 29 A. Consultation Process 29 B. Community Involvement to Date 29 ANNEX 1 to Chapter 6: Questionnaire for Face-to-Face Survey 32
VII. SUMMARY, CONCLUSIONS, RECOMMENDATIONS 33 A. Summary 33 B. Environmental Screening – Potential Impacts and their Significance 34 C. Recommendations 34
REFERENCES 35
LIST of FIGURES
Page
Figure 1: North-South Roads Corridor Alignment 2
Figure 2: Ministry of Nature Protection (MNP) Organization Chart 4
Figure 3: Armenian Laws and Codes Pertinent to Roads and Environment 4
Figure 4: RA Environmental Clearance Procedure – Schedule 5
Figure 5: RA Environmental Clearance Procedure – Flow Diagram 5
Figure 6: Location of the Two Project Road Sections 7
Figure 7: Geology of Armenia 10
Figure 8: Construction Activities that may Create Environmental Impacts 13
Figure 9: Works Activities and Potential Impacts 14
Figure 10: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) 18
Figure 11: EMP and Operating Plans – Clauses for Inclusion in Contract Docs. 24
Figure 12: Monitoring Requirements - Site Preparation and Construction 27
Figure 13: Environmental Stakeholder Groups Met to Date 30
Figure 14: Results of Survey of Villagers (94 respondents) 31
I. INTRODUCTION
A. Project Background
1. Armenia is a land-locked, mountainous country in the Lesser Caucasus region, bordered by Azerbaijan, Georgia, Iran, and Turkey. Being land-locked, Armenia has been restricted in its ability to develop and to maintain reliable land transport linkages with the outside world particularly to Europe, Iran and Russia and, via Georgia, to the Black Sea.
2. The Government of Armenia (GoA) has made efforts to strengthen its economic linkages with other economies via land bridges to Central Asia, the Black Sea and Europe and, thus, create increased trade and investment opportunities. GoA formulated the Armenia Transport Strategy 2020 and the North-South Road Corridor Program under it, with a priority to rehabilitate, reconstruct and expand international transport corridors—in line with the ADB, Armenia…Country Strategy to support regional cooperation and rehabilitate regional road and railway infrastructure.
3. The RA has selected the Bavra-Yerevan-Agarak route as the north-south road corridor to be rehabilitated, reconstructed and expanded and has appointed the Armenian Roads Directorate (ARD) of the Ministry of Transport and Communications (MOTC) to coordinate the work. The Program is to be funded by the Asian Development Bank (ADB) under a multitranche financing facility (MFF).
4. The MFF is designed to rehabilitate and upgrade national north-south roads to form a new, upgraded and expanded N-S highway. The main objective is to widen the existing 2-lane roads (often in poor condition) to become 4-lane divided roads along existing alignments wherever possible or to construct new alternate 2-lane roads where a single 4-lane road would not be feasible.
5. The Project, to be financed from Tranche 1 under the MFF, is to improve two road sections of the N-S Corridor, namely, the M-1 section of road north from Yerevan to Ashtarak and the M-2 section of road south from Yerevan to Ararat. At Ashtarak and Ararat, the road sections to be improved under the Project join the existing 2-lane roads from Ashtarak north to Gyumri and Bavra and from Ararat south to Goris and Agarak respectively.
6. The location of the existing N-S national roads M-1 and M-2 and the provincial (marz) boundaries is shown on Figure 1.
1
Figure 1: North-South Road Corridor Alignment
2
B. IEE Report Outline and Methodology
7. This Initial Environmental Examination (IEE) report assesses the environmental settings of the corridors through which the Project road sections pass, identifies the likely impacts that may be created, determines the significance of those impacts, and presents a summary Environmental Management Plan (EMP) and a Monitoring Program.
8. The methodology is based on the ADB, Environmental Policie s (2002) and the ADB, Environmental Assessment Guidelines (2003), GoA IEA requirements, and the joint experience of the International and National environmental consultants involved in the IEE.
9. Background data and information was obtained from published and unpublished sources, e.g., on: climate, topography, geology and soils, natural resources, flora and fauna, agriculture, and socio-economic data.
10. Several site inspections were conducted jointly by the International Environmental Specialist and National Counterpart during June and July 2009. The existing roads were driven and areas of potential environmental significance assessed carefully.
11. Discussions were held with a number of stakeholders and a face-to-face survey was conducted of villagers along one of the roads in the N-S roads corridor in order to determine their perceptions of the level of impact from road works. Data and information obtained have been included where appropriate in the IEE Report.
C. Armenian and ADB Environmental Assessment Requirements
12. This IEE Report is to satisfy both the ADB and RA requirements with regard to environmental protection and management.
1. Armenian Laws Governing Environmental Management and Assessment
13. The RA Ministry of Nature Protection (MNP) is the principal national environmental administrative authority. Within it are several agencies or directorates administering various aspects of the Laws on Environmental Protection, EIA and Protected Natural Areas. See the MNP organization chart in Figure 2.
14. Of importance to EIA and IEE are the two state non-commercial organizations (SNCOs): a) Nature Protection Expertise (NPE) responsible for administering the EIA process, and b) the State Environmental Inspectorate (SEI) responsible for overseeing compliance with environmental laws and regulations
15. The EIA process and the SEI power to inspect are the principal tools used by the MNP to achieve compliance with environmental management principles. As well as the MNP, other ministries and agencies have responsibilities to administer natural resources and environmental matters (e.g., Ministries of Agriculture and Health, the State Committee for Water Systems, and the National Reserves Agency). The laws and regulations that may relate to this project are summarized in Figure 3.
3
Figure 2: Ministry of Nature Protection Organization Chart
Minister
Deputy Ministers
Agencies: Departments/Divisions: ¾ SNCOs & Others:
¾ Water Resources ¾ E Protection ¾ Info & Analysis ¾ Bio-resources ¾ Hazardous Substances and Waste Mgt ¾ National Park SNCOs ¾ State E Inspectorate ¾ Economics ¾ State Reserve SNCOs ¾ Nuclear Power Insp. ¾ Mineral Resources, Soil protection and ¾ Nature Protection Expertise Geological Monitoring ¾ E effects Monitoring Centre ¾ Public Relations ¾ Waste Research Centre ¾ Others ¾ Hydrometeorology’ ¾ Hydro-geological Monitoring Others ¾
Figure 3: Armenian Laws and Codes Pertinent to Roads and Environment Authority and Law or Regulation Pertinent Section
MNP: Law on Principles of The umbrella legislation Environmental Protection (1991) MNP: Law on Environmental Impact Requirements to assess environmental impacts of Assessment (1995) development projects, notification requirements, and the importance of the assessment conclusions. MNP: Law on Specially Protected Regulates state reserves, national parks, and Natural Areas (2006) natural monuments and classifies them according to their international, national or local importance. Ministry of Territorial Administration Delineates local government responsibilities (MTA): Law on Local-Government including use of natural resources and (2002) infrastructure, e.g., location of works camps and MTA supervises marz administrations earth borrow pits. MTA: Law on Waste (2004) Regulates responsibilities of state and local authorities with regard to disposal of solid waste MTA: Land Code (1991, updated 2001) Addresses land use and its protection – including environmental aspects MTA: Water Code (1992 updated 2002) Protects use of water resources. The MTA includes the State Committee on Water Economy. MTA can become involved with road impacts on water use and availability. M Culture: Law on Preservation and Preservation and Use of Historical and Cultural Use of Historical and Cultural Monuments Monuments (1998) M Agriculture: Forest Code (2005 & Sustainable forest management, forestation, use subsequent decrees) of forests and control of forest lands M Justice: Civil Code (1998) and The codes include clauses to regulate Criminal Code (1961) environment-related offenses
4
16. The RA environmental clearance procedures are set out in Figures 4 and 5. The ADB and MOTC will review the IEE Report and pass it to the MNP. The Report will then be made public by the NPE which invites public and government comment on the IEE and the Project before clearing it for implementation by the MOTC.
Figure 4: RA Environmental Clearance Procedure - Schedule Step A ction Time Lapse (days) 1 The project initiator (MOTC) sends the completed EIA/IEE Report to NPE. 5 Within 5-days the NPE (an SNCO within MNP) sends copies of the Report to MNP agencies and divisions (particularly the SEI), other ministries, and to the leaders of the affected marzes and communities. The public are notified via mass media as to where the Report may be viewed. 2 NPE, MOTC and affected communities organize public hearings. 30 Comments are submitted within 30-days to community leaders or to the NPE. 3 Within 10-days after time closure for receipt of public comments, community leaders 10 may add their own comments and send all comments to NPE. 4 MNP and other ministries and agencies have an additional period of 30-days in which 30 to provide their comments. During this same period, NPE reviews the public and community comments. When no negative comments are received by NPE within this 30-day period, it is concluded that there are no negative opinions with regard to the project. 5 The NPE takes the comments into account and has up to 70-days to conclude on the 70 (to 180) project. This period may be extended to 180-days when warranted. 6 Within 30-days of concluding on the IEE Report, the NPE releases its conclusion to 30 the public and may organize a second public hearing. 7 Within 20-days of the second public hearing, the NPE provides the Initiator (MOTC) 20 with a decision to proceed with the project or to cancel the project. -- Total Time Lapse (with no extensions by NPE) – up to ……………………….. 195-days
Figure 5: RA Environmental Clearance Procedure – Flow Diagram MOTC Roads Corridor Projects
ADB MOTC Proposes Projects
EIA/IEE report
EIA/IEE Report No Review:
Communities NPE Other Ministries
SEI
Yes or Yes with Conditions
MOTC Implements
Project Reporting by MOTC Project Monitored by:
MOTC and by SEI and Communities
5
2. ADB Environmental Assessment Requirements
17. The ADB requires that environmental impacts likely to be caused by the Project be identified during the project planning and pre-feasibility stages and prevented or mitigated as much as possible during the construction and operational phases.
18. For environmental management purposes the roads improvement Project assessed here is classified by the ADB as a Category B project. This means that impacts are not expected to be highly significant but nevertheless need to be identified and reported in an Initial Environmental Examination (IEE) report.
19. Public disclosure and opportunities for the public (and affected ministries, agencies and local authorities) to express their concerns about the project form an important part of the environmental assessment process. Therefore, the ADB will post the Summary IEE Report (attached as Appendix 1) on its website.
D. Alternatives to the Proposed Project
20. The ADB, Environmental Assessment Guide lines, 2003 state that alternatives to the project are to be considered and compared with the project in terms of their potential environmental impacts, capital and recurrent costs, suitability under local conditions and the institutional, training and monitoring requirements and that the economic values for alternatives should be estimated where possible.
21. The Project is to improve 18.4 km of the existing M-1 4-lane road section north from Yerevan to Ashtarak and 38.0 km of the existing M-2 4-lane road section south from Yerevan to Ararat. Both sections of road are existing 4-lane divided roads.
22. There is no other alternative. The economic factors and the benefits from safety improvements support the Project but short of not implementing it, there is no alternative.
6
II. PROJECT DESCRIPTION
A. Project Location
23. The Project road locations are shown on Figure 6.
Figure 6: Location of the Two Project Road Sections: 4-Lanes on M-1 North of Yerevan, and 4-Lanes on M-2 South of Yerevan
7
B. Tranche 1 Project
24. The overall MFF objective is to improve existing 4-lane divided roads, widen existing 2- lane roads (often in poor condition) to 4-lane divided roads along the existing alignment wherever possible, or construct alternative 2-lane roads where a single 4-lane road would not be feasible.
25. The two road sections to be improved under the Project are two sections of the North- South Road Corridor to be rehabilitated and expanded under the MFF. The location of the road sections to be improved under the 1st Tranche of the MFF, and covered in this IEE report, stretch short distances north and south of Yerevan.
26. The 18.4km M-1 4-lane road section north of Yerevan was originally built over the period 1975 to 2004. Its condition is deteriorated and its standard varies so that the road-bed needs improvement to meet the design and construction standards normally associated with international transit routes. The 38.0km M-2, 4-lane road section south of Yerevan was built more recently and is in relatively good condition. Neither road section is adequately drained, the shoulders in many parts are very narrow and not properly paved, there are many randomly located U-turns, signage, road markings and lighting are absent or inadequate, there are insufficient crash barriers and median separation barriers and road structures need to be investigated to determine their structural integrity.
27. A key objective of the Project is to ensure compliance with the road safety and signage requirements under the European Agreement on Main International Traffic Arteries to which GoA is a signatory. A second objective is to ensure the structural integrity of road structures and that drainage is adequate to enhance road-bed longevity. Shoulders, guard rails, road marking, turning lanes and proper drainage will be added as necessary.
28. Road works are planned to be fully confined to the existing ROW and be constructed in sections, one side of the 4-lane carriageway at a time, in order to enable continued use of the existing road during construction. Transport of materials will be confined to the existing 4-lane road, to the one-side being worked on, when possible. The road works on both road sections will include the following: (i) Constructing proper drainage side-ditches and cross-drainage as required. (ii) Improving the road-shoulders. (iii) Improving traffic safety measures: signage, guardrails, traffic markings and turning lanes. (iv) Repairing road structures: over-passes, under-passes, and cut and embankment slopes.
29. The road works on the M-1 north section (Yerevan to Ashtarak) will also include: (i) Removing the existing asphalt layer (and grinding and re-using it as much as possible). (ii) Removing below-standard top and sub-grades and sub-base as required and replacing it with material meeting accepted quality standards. (iii) Completing the travel lanes and shoulders with a new concrete asphalt layer. (iv) Providing landscaping where appropriate.
30. Construction is planned to begin late 2010 and be finished by mid-2012.
8
III. ENVIRONMENTAL BASELINE – EXISTING CONDITIONS A.
B. A. Ph ysical Resources
31. Both road sections are located in arid areas (annual precipitation less than 400mm) with most precipitation falling as rain in spring and autumn. Humidity is low, varying from a high of 78% in April/May, to a low of 56% in August. The temperature regime is that of the dry continental climate zone with average January temperatures (the coldest month) in the minus 4- 6 degrees C range. In July (the warmest month), the range is 25–38 degrees C.
32. The geology is very mixed but essentially a combination of volcanic basalt, faulted uplift and sedimentary infill overlying lava. The geological origins lie in the Pliocene, Paleocene and Cretaceous periods. To the north of Yerevan the basic geology is of uplifted Late-Quaternary- Pliocene volcanic deposits, mostly basalt and andesites broken down by earthquake and climatic elements into fractured rock and gravelly soil over most of the road corridor with small areas overlain by recent sedimentary material of volcanic origin. To the south the Ararat valley is sedimentary infilling of a basalt basin (see Figure 7).
33. Earthquakes occur from time to time, the last in December 1988, with an epicenter NE of Gyumri near the village of Spitak. The earthquake had little effect on the land and no apparent effect on structures located within or near the Project road sections. There are many small earthquakes and several large earthquakes have occurred in Central Armenia from time to time, including early in the 19th and 20th centuries. The seismic factor ranges 8-9 with an earthquake wave acceleration rate: g = 0.4 m/sec.
34. The landscape north of Yerevan along the M-1 Project road corridor is gently rolling uplands 1,060m to 1,270m in elevation. The Kasakh River dissects the landscape in a deep gorge north of Yerevan. There are no other surface streams along the north road section. The landscape south of Yerevan along the M-2 Project road corridor is flat and about 1,100m in elevation. There are no surface streams but the Ararat Valley is a noted artesian basin fed by snow melt and a sub-surface network of aquifers through the fractured lava. The land is irrigated wherever possible by water from aquifers and that carried in large pipes and canals from the mountains to the east.
9
Figure 7: Geology of Armenia
10
B. Ecological Resources:
35. The original fauna in the road corridors included steppe and semi-desert species has been largely supplanted. The native flora of arid and semi-desert varieties survive better in the corridor through which the M-1 4-lane north road section passes than the 4-lane M-2 south road section passes. The desiccated natural landscape along the north road corridor remains in patches amongst the mixed urban use land but along the south road corridor the native plants have been largely replaced by domestic plants except on the gravelly and saline bare patches where sage and similar species predominate.
36. There are no original trees along either road section, and few trees of any substance. Within the existing rights-of-way, to which the planned improvement and construction activities will be confined on both road sections, there are only the road itself, medians, limited shoulders, ditches and protective strips. There are no unique areas, no protected areas and no forests or ecological reserves within 500m either side of the right-of-way (ROW).
37. Within the Ararat Marz are the Khosrov Forest Reserve and a RAMSAR site 3-5km to the east of the ROW and a large area of aquaculture ponds in a former natural wetland some 2- 4km to the SW of the ROW.
C. Human Use of Resources
38. The existing 4-lane roads form important features of the existing environmental baselines along both road corridors and present a significant barrier to people trying to cross the road (particularly over north section because of the variable horizontal and vertical alignment). There are no industrial buildings, facilities, commercial operations or residences located within either ROW. No land purchase or resettlement will be necessary, and neither ROW passes close to any villages.
39. The areas near the Yerevan ends of both alignments are semi-urban transition zones where vacant land, industrial activities, run-down and disused industries and small residential areas are intermixed with remnant agricultural uses.
40. Agriculture along the north road section is limited to small orchards and a few hay fields towards Ashtarak. In complete contrast, agriculture predominates along both sides of the alignment in the south. The flat, irrigated land is intensely cropped with vineyards, wheat, orchards and market-gardens wherever irrigation is possible.
41. Energy Sources and Mining Activities. Within the road corridors of both road sections there are no nuclear, hydro or other electrical generating plants and no active mining.
42. Tourism Attractions and Facilitie s. There are no tourist attractions within or close to the road corridors.
D. Human Quality-of-Life Values (Socioeconomics and Sociocultural Resources)
43. Close to the ROW on the north road section there are two important known archeological sites protected by GoA Department of Historical Monuments (Ministry of Culture). One site stretches 500m along the edge of the ROW between it the Kasakh River near the bridge over the River and down the valley side to the River itself. The second site is located astride the interchange at Agarak and 200m either side of it. There may also be undiscovered
11
archaeological remains or artifacts below ground (see EMP). There are no known sites within 100m of the ROW to the south.
Social conditions are as to be expected where the annual average per capita monetary income is about US $2,000 (lower in rural areas and already 20% lower in 2009 than it was in 2007) but people manage to live above that level in terms of PPP, standard of living, lifestyles and social- support services.
Many people in the Project corridors work in Yerevan. But for the marzes (Aragatsotn and Ararat) as a whole, particularly in the south corridor more than 75% of the population are employed in agriculture as owner/operators of as employees.
There are many schools in the two provinces concerned. As well as general education schools, there are pre-schools, state and non-state secondary schools and specialist schools in music and sports. Communities are generally well served with health clinics.
IV. SCREENING FOR POTENTIAL ENVIRONMENTAL IMPACTS
A. Environmental Parameters that may be Impacted
44. The different elements of the environment that maybe impacted or affected by the road rehabilitation and expansion project are clustered under the four aspects of the environment, namely, the impact on the: (i) Physical Environment: Water, land and air quality (ii) Ecological or Biotic Resources: Migrating mammals (iii) Human Use of Resources: Agriculture, rural roads and transport (iv) Human Quality-of-Life: Health and safety, incomes and employment, archaeological and historical sites.
B. Activities that may Create Environmental Impacts
45. Project Summary. The two road sections to be improved under the Project are parts of the North-South Road Corridor to be rehabilitated and expanded under the MFF. The location of the two road sections to be improved under the 1st Tranche Project are: a) the 18.4km, 4- lane road section of the M-1 north from Yerevan to Ashtarak and b) the 38.0km, 4-lane road section of the M-2 south of Yerevan to Ararat.
46. Neither road section is adequately drained, the shoulders in many parts are very narrow and not properly paved, there are many randomly located U-turns, signage, road markings and lighting are absent or inadequate, and there are insufficient crash barriers.
47. A key objective of the Project is to ensure compliance with the road safety and signage requirements under the European Agreement on Main International Traffic Arteries to which GoA is a signatory. A second objective is to ensure the structural integrity of road structures and that drainage is adequate to enhance road-bed longevity. Shoulders, guard rails, road marking, turning lanes and proper drainage will be added as necessary.
48. Road works are planned to be fully confined to the existing ROW and be constructed in sections, one side of the 4-lane carriageway at a time, in order to enable continued use of the existing road during construction. Transport of materials will be confined to the existing 4-lane road, to the one-side being worked on, when possible.
12
49. Traffic growth for the next 20 years has been estimated based on the projected growth of GDP and an estimate of demand elasticity; little or no change in population is expected over the period. The results of the traffic forecast are shown in Figure 8.
Figure 8 – Traffic Forecast in number of vehicles per day
2012 2015 2020 2025 2032 With Project 13060 17110 24490 36660 65605 Without Project 13060 15550 22270 33330 59641
49. Eight construction activities with potential to impact on the four different aspects of the environment, including human safety are summarized in Figure 8. Note: The eight construction activities relate only to the north road section (4-lanes of M-1).
50. All eight works-related activities have the potential to create significant impacts on the environment or human safety. However, all impacts and safety issues can be prevented or mitigated by following sound engineering practices and implementing the impact prevention and mitigation measures set out in the Environmental Management Plan (EMP).
51. The operation or use of the improved roads may have some minor impacts on the local environment, air quality and noise levels may change but the level of change will not be significant.
Figure 8: Construction Activities that may Create Environmental Impacts (on M-1 section) Undertake earthworks: Prepare work sites, Dispose of surplus material Operate quarries borrow pits Transport materials Operate asphalt plants Construct and extend culverts Store/handle diesel and waste oil Manage traffic in and near work sites Operate work camps, including storage/disposal of sewage, domestic and solid waste
C. Environmental Screening—Potential Impacts
52. Works Acti vities—M-1, North Roa d Section. The works activities listed in Figure 8, above, are linked to the main causes of impacts and the elements of the environment that may be impacted in the Environmental Impact Screening Table (Figure 9).
53. The improvement works will impact the baseline environment only via minor impacts. Earthworks, construction activities and quarry and borrow-pit operations may create a number of short-term impacts on air and land quality, health and safety, may cause local flooding (by diverting runoff) and unearth archaeological sites or artifacts. Other activities that may cause negative impacts are asphalt plant operations, transport of materials, storage and handling of diesel, traffic in and near work sites, and work camp site preparation and operations.
54. Under the Project, there will be no changes to vertical or horizontal alignments. There will be no removal of top-soil, no new cut or fill sections and no bridge construction. Most 13
construction works will be confined to the 18.4km 4-lane north road section from Yerevan to Ashtarak, where the road-bed itself will be improved by removing the old asphalt, digging out and removing sub-standard road-bed materials and replacing both with new materials.
55. Digging may unearth archaeological sites or artifacts. Therefore, care needs to be taken, particularly around the two known archaeological sites near the north road section. Over the south section (Yerevan to Ararat) works will be limited to shoulder, drainage and culvert improvements; little material will be removed or new material placed, and there are no known archaeological sites within 100m of the ROW.
56. The disposal and replacement of up to 300,000m3 of sub-standard material from the existing north road section will require up to 100 truck movements per day over the construction period. With the current average daily traffic (ADT) of 11,680 vehicles including 13% trucks and other large vehicles, the works-truck traffic will add less than 5% to the existing ADT for large vehicles.
57. Works Acti vities—M-2, South Ro ad Section. Works will be confined to remedial improvements of safety, road markings, drainage and lighting.
58. Operation of the Improved Road. Minor positive impacts will be created. Air quality will improve, due to the smoother travel and better fuel combustion, road accidents will reduce due to the improved: safety barriers, road markings, lighting and the control of U-turns. Air quality and noise levels may be affected but it is unlikely that the level of change will be significant.
59. Noise. For a change in noise levels to be perceptible to the human ear the change must be greater than 3dB(A). A change of 3 dB(A) resulting from road traffic requires a doubling of the traffic flows. The traffic forecasts provided in table 8 show that this will not occur until after 2025 and so changes in noise levels will not be significant.
60. Air Quality. No quantitative air quality monitoring data was available for this assessment. In the last 15 years air quality in the city has improved, largely as a result of the closure of soviet era industries which were significant polluters. The gradual increase in vehicle numbers will lead to some increases in pollutants but this is likely to be offset by the implementation of more stringent emission standards and improvements in engine efficiency.
Figure 9: Works Activities and Potential Impacts (M-1 section) Construction Activity and Causes Environmental Elements Impacted of Impacts 1 Undertake earthworks: Prepare work sites, Air quality and noise levels Dispose of surplus material. Water quality Land quality Unstable and eroded material affects: water Vegetation bodies, water quality and aquatic biota; other land, vegetation, etc. Work site safety Dust reduces air quality. Unearth archaeological sites or artifacts Activities may unearth archaeological sites or artifacts. Equipment causes noise, vibration and safety issues, may impact road use, other land uses and communities. 2 Operate quarries borrow pits Same as above 3 Transport materials Air quality and noise levels Damage rural roads Truck traffic increases road hazards, noise and Health and Safety via road accidents vibration, dust, air pollution, and nuisance. 14
Construction Activity and Causes Environmental Elements Impacted of Impacts Heavy trucks can damage rural roads, affect communities and road users. Mud from truck wheels can cake onto existing roads. 4 Operate asphalt plants Air quality and noise levels Vegetation Air pollution, mostly particulate matter, and noise Water and Land quality via spills of diesel can affect people. Dust affects plants. Spills of diesel are toxic to all living organisms. 5 Construct and extend culverts Air quality Land quality May create local flooding. Health and Safety via road accidents Creates traffic safety hazards. 6 Store/handle diesel and waste oil Water and Land quality via spills of diesel and/or waste oil
Diesel and waste oil handling and vehicle and equipment servicing may cause spills. Diesel and waste oil are toxic to all living organisms. 7 Manage traffic in and near work sites Air quality and noise levels Water quality Work sites create accident conditions. Signage, Land quality barriers and clear directions are important. Vegetation Work site Safety and road user Safety 8 Operate work camps, including Air quality and noise levels storage/disposal of sewage, domestic and Water quality solid waste Land quality Health and Safety The work force generates large amounts of domestic and other solid waste and sewage with potential to damage water quality and create nuisance. Social impacts from the largely male work force may affect local communities.
D. Significance of Potential Impacts
59. Estimating significance involves careful consideration of the nature of each potential impact. Significance is defined by three factors: the magnitude including duration of the impact, the scope or area that may be affected, and the probability or frequency of occurrence. Each potential impact is considered against each of the three factors and assessed in-depth with reference to the environmental baseline and its sensitivity.
60. Short-term negative impacts will be created on water, land and air quality (and noise) and health and safety. These environmental elements are most likely to be impacted along the north road section, and rural roads may be damaged by the heavily laden trucks carrying earth, gravel and other works materials—depending on the truck routes taken. The contractor will therefore be required to re-instate pavements along transport routes at the end of the construction period if damage has occurred.
61. The area is arid, hence, there is very little water that may become affected and no improvements are foreseen for the high bridge over the Kasakh River. Therefore, impacts on water quality are expected to be insignificant. In order to prevent any pollution of the river
15
occurring in the event of an accident on the bridge catch drains will be included in the design to ensure that surface flows are directed away from the river.
62. The increase in traffic along existing sections of the carriageway when they are used to divert traffic around the resurfacing works may lead to increased damage to the pavement. The tender and contract documents will require the contractor to maintain the pavement of the carriageways for those sections that are being used for diversions at a standard suitable for the volume of traffic.
62. There are no ecologically important or sensitive environmental elements and few human use factors that may be seriously affected. The most important possible impact issue is the potential to unearth archaeological sites or artifacts (addressed in the EMP).
63. Air quality impacts will be confined to localized dust nuisance. This may be significant but manageable. Similarly noise may be significant, localized and manageable. Impacts on land quality are expected to be very minor because works will be minor on the south road section and confined to the existing ROW of the north road section. Hence, the likely impact on land is considered to be insignificant and manageable.
64. Health and safety impacts may be significant but preventable at all locations.
65. Actual impacts will be short-term and insignificant. Nevertheless, all impacts have been addressed in the EMP, the implementation of which will prevent or mitigate them.
66. Short-term positive impacts will be created via local employment and spin-off effects and the associated increase in short-term expenditure. Construction will create a number of local jobs to prepare and re-construct earthworks, operate and restore borrow pits and quarries and to transport and apply construction materials. In-turn, households and small businesses will benefit significantly over the short-term.
V. ENVIRONMENTAL IMPACT PREVENTION and MITIGATION MEASURES
A. Environmental Impact Prevention and Mitigation
67. The environmental impacts that may be created by the project were identified above. They are well known to competent civil engineers and competent construction companies – as are the standard impact prevention and mitigation measures to address them. Nevertheless, in order to ensure understanding of required prevention and mitigation measures, an Environmental Management Plan (EMP) and appropriate clauses for inclusion in works contracts are summarized below.
68. To further encourage understanding of and compliance with good environmental practices, Environmental Management seminars are proposed.
B. Environmental Management Plan (EMP)
69. The EMP summarized in Figure 1 0 and discussed below, is designed to address the impacts identified in Section 4.0 by guiding engineers and contractors in the prevention and mitigation of environmental impacts related to construction activities, to guide monitoring by ARD, SEI and the International Environmental Specialist (IES), and to guide ARD in the subsequent operation of the road. The Summary EMP:
16
(i) Links road works activities, their potential impacts and their prevention or mitigation. (ii) Provides the basis for the EMP, to be added to by Contractor statements of intent to comply and the detailed planning documents to be prepared by the contractor prior to commencement of specific, identified activities. (iii) Forms the basis for preparing a Monitoring Program for checking on compliance with impact prevention and mitigation measures.
1. Contractor to Prepare EMP and Operating Plans for Approval by Senior Engineer
70. Prior to commencing site preparation and construction activities, the Contractor will prepare a Draft EMP and Monitoring Program guided by Chapters 4 and 5 of this report, particularly the Summary EMP (Figure 10). The Contractor is advised to simply copy the Summary EMP below and prepare the required Operating Plans (referred to in the Summary EMP) and add a Performance Commitment Section including places for the signatures of the Contractor, Senior Engineer and Works Foremen.
71. The Draft EMP will be approved by the Senior Engineer (SE) and serve to support consultations in affected communities (village leaders and villagers) and with responsible authorities at the central and provincial (marz) levels. The EMP will be revised as required on receipt of comments from communities and the responsible authorities and then finalized. When finalized as the Approved EMP, the SE, Contractor and Works Foremen will sign it testifying to their agreement to comply with it.
72. Consultations with affected communities will help to gain local input/understanding, to guide revisions when warranted, and to support monitoring.
73. The Contractor will prepare suitable Operating Plans as required to guide satisfactory implementation of key activities that may create significant environmental impacts. The overall requirements of each Operating Plan are highlighted in Figure 10 as performance clauses to be included in the Main Contract Documents.
17
Figure 10: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 1 of 5 Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors 1. Construction: (i) Dust and emissions Construction and Related Activities (ii) Traffic hazards and safety The Contractor will prepare an Environmental Management Plan (EMP) for approval by the Senior Engineer (i) Earth works (iii) Work site safety (SE) -- prior to commencing site preparation and construction. The EMP will be guided by the IEE Report, the principles set out in the Summary EMP and the following: (ii) Cul verts (iv) Social nuisance (i) Prior to commencing any works, the Contractor will meet with the ARD, MNP and Marz authorities. (iii) Dispose of (v) Erosion of material piles and surplus runoff may affect nearby land (ii) Areas of disturbed land will be restored or rehabilitated as soon as possible.
material and plants (iii) Works stockpiles will be located away from drainage areas and water-courses. (vi) Works can cause local flooding (iv) Construction and related activities, such as stockpiling, servicing and drainage works will be restricted to (vii) Material beyond ROW affects identified sites. nearby land quality and use (v) Spoil and materials piles will be graded, stabilized and drained. (viii) Noise and vibration (vi) Construction material/waste will be kept within the ROW and away from water bodies. (ix) Works may unearth (vii) Adequate temporary drainage will be provided to prevent local flooding. archaeological artifacts (viii) Runoff from sites will be prevented from entering natural water-courses, for example by using sediment traps, silt aprons and/or straw bales. Also see: Drainage, Slope Stability Erosion and Sediment Control – below. (ix) Water sprinklers will be used to minimize dust in and around work areas. (x) Work along the north road section will be undertaken only during daylight hours. (xi) Workers will use safety equipment (helmets, eye-glasses, ear-plugs - as required) and follow safety procedures (xii) Nearby residents, commercial and industrial land users and communities will be informed of major activities ahead of their implementation and be informed of a clear mechanism for comments and complaints to be communicated to the SE. Waste Management The Co ntractor will prepare a W aste Man agement Plan fo r app roval b y th e Senior Eng ineer p rior to commencing work. The Plan will be guided by the following: (i) Solid waste will be separated (it is understood that clean paper, glass and poly-propylene plastics are recyclable in Armenia) and stored for regular collection for correct off-site disposal in a nearby municipal waste facility. (ii) Solid waste disposal sites will be identified in concert with local officials and the MNP prior to any dumping. (iii) Solid waste, waste spoil, waste aggregate/materials and waste material removed from the existing road (e.g., used asphalt-concrete that cannot be crushed and re-used) will be disposed of only in designated sites/locations. (iv) Waste oil will be collected and stored in used fuel drums for later safe disposal in a manner and/or at sites approved by the MNP. (v) Waste asphalt removed from the existing road (north) will be recycled and re-used in the new road construction as much as possible. All old asphalt that cannot be re-used will be handled as toxic waste and disposed of only at a site approved by MNP and local authorities.
18
Figure 10: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 2 of 5 Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors
1. Construction: Drainage, Slope Stability Erosion and Sediment Control (i) Control devices/actions will be designed to provide adequate protection for each area, according to slope, drainage (i) Earth works pattern, likely rainfall, and the construction site. (ii) Cul verts (ii) Measures to control runoff, erosion and sedimentation will include: (iii) Dispose of a. Diversion of natural runoff around construction areas surplus b. Use of temporary bunds to divert runoff to temporary or permanent drainage facilities material (iii) Drains, runoff, erosion and sedimentation protective measures will be maintained regularly to ensure adequate capacity. (iv) Temporary diversion drains will be extended beyond the toe line of an embankment to avoid embankment erosion (v) Drainage structures and erosion controls will be monitored and repaired/modified as soon as possible after rain. Noise and Vibration (i) Vehicles and equipment will be fitted with emission controls and silencers to meet national noise control and emission standards and be checked every six-months to ensure compliance. (ii) The asphalt plant and equipment will be operated only in daylight. (iii) Noise control barriers (e.g., solid walls, earth barriers, noise-reflective panels) will be used when necessary to shield houses, schools and hospitals Archaeological Finds When an archaeological site is found, work will be stopped immediately. The Senior Engineer will be notified. Then, the following steps will be taken: Isolate the site. (i) Call the Archaeology and Ethnography Inst., Armenian National Academy of Sciences and the Agency for Protection of Historical and Cultural Monuments to assess the site and determine whether and how it should be preserved (ii) Document and photograph the find and area immediately around it (iii) When advised and as directed by the Archaeologist, excavate and remove the find (iv) After documentation and after being advised that the site is not important, resume construction.
2. Sto re an d (i) Diesel and waste oil is toxic to (i) Diesel will be stored in drums or tanks under cover on an impervious pad of concrete or clay (for later removal and handle diesel an d all living organisms - in the soil safe disposal), and the pad will be surrounded by an impervious bund enclosing a catch volume at least 50% more waste o il or in surface or ground-water. than the volume of diesel stored. Should clay be used to form the bund and a spill occur, the bund will be removed (including v ehicle Diesel and waste oil kills all after construction has ceased and disposed of safely (as for impervious pads of clay). and e quipment living organisms (ii) Vehicles and equipment will be maintained in designated areas underlain by an impervious pad of concrete or clay servicing) (for later removal and safe disposal)
(iii) Waste oil will be collected and stored (in the same way that diesel is stored – see above) in used fuel drums for later safe disposal in approved sites. (iv) Also see Waste Management – above.
19
Figure 10: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 3 of 5 Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors 3. Op erate an d (i) The expected impacts are very The Contractor will prepare a Quarry and Borrow-pit Operations and Site Restoration Plan for approval by the restore q uarries similar to those shown for SE - prior to commencement of materials extraction. The Plan will be guided by the following: and borrow pits Construction, above. (i) Potential quarries and borrow pits will be identified in concert with marzpeteran (provincial) and Yerevan officials. (ii) Quarries and borrow pits will be made safe, have their slopes stabilized, be adequately drained and be restored or rehabilitated as soon as possible after extraction has ceased. 4. Tra nsport (i) Dust and emissions The Contra ctor will prepare a Dra ft Tra ffic Ma nagement Plan for co nsideration by th e SE an d affected materials and (ii) Noise and vibration communities, traffic au thorities a nd t he pol ice be fore fina lization a nd a pproval b y the SE -- prior t o equipment commencing construction,. The Traffic Management Plan will include: (iii) Traffic and other safety hazards 1. Carefully selected truck routes (iv) Social impact in affected 2. Clear route directions communities 3. Appropriate warning signs (v) Damage to rural roads and 4. Established speed limits and operating times (daylight as much as possible) other roads 5. Provision and maintenance of temporary access for public and nearby communities 6. Controls over the movement of vehicles particularly near communities and schools 7. Use of dust blankets or other means to cover load 8. Provisions to use and using water spray of road surfaces to control dust in and near affected settlements 9. Construction traffic giving way to regular traffic (i) Construction traffic routes will be defined in cooperation with local communities and the police (ii) Vehicles and equipment will be maintained to prevent fuel and oil leaks and to minimize air and noise pollution (iii) Trucks and equipment will be washed in specified areas with suitable runoff protection (as above). (iv) Roads used by construction vehicles will be swept regularly. (v) Vehicle and equipment movements will be restricted to the approved construction zone and the final ROW. (vi) Rural and other roads damaged by construction vehicles and other activities will be repaired or restored (i) Dust and emissions The Contractor will prepare an Asphalt Plant Site Development and Operating Plan for a pproval b y the SE - (ii) Noise prior to construction of an asphalt plant. The Plan will take the following into account: (i) The asphalt plant will be located at least 200m away from and downwind from any settlement and 200m away from (iii) Diesel (used in asphalt) is toxic any water body or stream and adjacent to other contractor facilities such as, works camps, storage areas and to all living organisms – in soil, vehicle and equipment maintenance areas. surface or ground-water. (ii) Electrostatic precipitators will be installed or exhaust gases will be released via a set of water baths (iii) Diesel will be stored under cover on a concrete pad surrounded by an impervious bund enclosing a catch volume at least 50% more than the volume of the diesel stored (see above). (iv) Conveyers and hoppers will be covered (v) Waste asphalt and bitumen will be disposed of at a site approved by marz, city and MNP authorities. (vi) The plant will be operated only in daylight hours when located less than 500m from a settlement.
20
Figure 10: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 4 of 5 5. Operate/ (i) Work force generates significant The Contractor will prepare a Facilities Plan (such as, work camps, concrete mixing plants, storage areas an d manage w ork amounts of domestic and other vehicle and equipment mai ntenance areas), for appro val b y the SE - prior to establishing facilities. The camps a nd other solid waste and sewage with Facilities Plan will take the following into account: facilities (incl. potential to damage water quality (i) Camp locations will be more than 200m from any water body and sited to prevent damage to landscape. and create nuisance store/dispose o f (ii) Domestic solid waste and hazardous waste disposal. (ii) Improper waste disposal sewage an d solid (iii) The need for adequate temporary drainage waste) creates health problems and habitat for disease vectors (iv) Sewage will be disposed of in on-site septic tanks, held in sealed tanks for proper disposal or disposed into latrines (iii) Communities may perceive constructed for the purpose and capped when no longer needed. potential or suffer from actual (v) Wastewater will be disposed of in on-site septic tanks, or be treated to meet the standards for domestic wastewater social impacts from large male discharge and discharged to a pond or natural drainage channel. workforce. (vi) Covered rubbish bins for solid waste will be placed at suitable locations where solid waste is generated. (iv) Site runoff affects the physical (vii) Solid waste will be separated (clean paper, glass and poly-propylene plastics are understood to be recyclable in water quality and aquatic life in Armenia) and stored for regular collection for recycling or off-site disposal in a municipal waste facility (also see rivers and water bodies, flora, Waste Management – above) nearby land, and other natural (viii) Work camp sites will be restored to the satisfaction of local officials after use and before abandonment. resources. 6. Work Site (i) Injuries and death of workers, (i) Safety and safety promotion will be of the highest priority. Safety road users, people in and near work-sites, quarries and borrow- (ii) Temporary traffic direction signs, markings, traffic signals and lighting will be installed and maintained, clearly visible pits, and possible sickness of solid barriers will be used to channel traffic, and flagmen will be employed as needed. workers and other people (iii) Water sprinklers will be used when needed to control dust because of sewage and waste (iv) Work areas will be kept clean and clear of waste and unused material disposal. (v) Waste will be disposed of properly (also see Waste Management) 7. P ublic (i)Lack of information and The Contra ctor will prepare a Community Cons ultation a nd Com munications Plan for a pproval b y the SE - Consultation understanding by communities prior to commencing site preparation and construction activities. The Plan will be guided by the following: and affected parties about the planned works activities and the (i) Procedures for communicating with local residents will be developed in advance of activities, particularly when noise, schedule for their implementation vibration or nuisances may be created and/or where local flooding may be an existing or potential problem. can lead to frustration and delays (ii) Community members will be provided with direct access to the SE or representative at a nominated location and in the schedule and sometimes time (particularly important where some residents may not have telephones). can contribute to accidents. (iii) A process will be developed whereby community members and other stakeholders may make complaints and be assured of receiving responses within a reasonable period. A record or Log will be maintained of the type and number of complaints received (name, subject, date, response and date of response). (iv) Regular meetings will be held with community representatives to discuss the project, its impacts, etc. The group should include community leaders and people who are well known in the community and who represent different interests, e.g., business people, teachers, priests, older people and those with special interests. (v) Community leaders and local newspapers will be provided with notices on project progress and anticipated issues. (vi) Clear signs will be posted on and around construction sites to provide information about the project. (vii) Employment opportunities will be maximized for local people by employing them as part of the project labour force, and prefabricating or manufacturing construction items locally when possible, e.g., drainage pipes, culverts and for sand, gravel and stone supply. 21
Figure 10: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 5 of 5 Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors (ii) Chemicals and Hazardous materials The Con tractor will p repare a Pl an for Han dling Ch emicals an d an Emerg ency Co ntingency have the potential to poison people, soil, Response Plan for approval by the SE - prior to commencing construction. The Plan will be guided surface and ground water and may by the following: cause death or severe damage to the health of people and all living animals (i) Procedures will be developed and implemented to ensure safe handling and storage of hazardous and plants. substances, e.g., diesel, waste oil, paints. Material safety data sheets, emergency response procedures and clean-up materials will be readily available on site. Copies of material data sheets will also be held by the Resident and Senior Engineers. (ii) An Emergency Contingency Response Plan (ECRP) will be in place to handle spills and ensure that clean-up materials are readily available on-site to clean-up spills that may occur. The ECRP will, at a minimum: 1. Identify the positions and persons responsible for emergency response action (e.g., the SE, RE, Works Foremen) 2. Specify the leader of the Emergency Response Team (ERT) and Alternate 3. Include an organizational diagram specifying the positions and responsible persons within the ERT, their work and home phone numbers, and the reporting lines among them. 4. Ensure that clean-up chemicals and materials to absorb and remove spilt substances are available and stored undercover in locked facilities located at works facility sites. 5. Ensure that the responsible persons receive training in emergency response. (iii) Hazard and risk management training will be provided to each Environmental Management Officer (appointed by the Contractor) and all personnel handling chemicals and hazardous substances. (iv) Spilled material will be collected and disposed of in a site approved by MNP. The spilled area will be cleaned in a timely manner to prevent potential contamination of surface and ground water and soil. (v) Only minimal chemicals, hazardous substances and fuel will be stored on-site, within an enclosed and covered secure area that has an impervious floor and impervious bund around it (with capacity at least 150% of the capacity of the largest tank). The storage area will be located away from water-courses and danger areas, e.g., facilities site.
22
74. The requirements for operating plans to be prepared by the Contractor are set out in the EMP Summary (Figure 10, above) and listed in Figure 11 as clauses to be included in the Main Contract Document. Operating Plans will be approved by the SE prior to undertaking any associated action, and be included as Annexes to the EMP.
Figure 11: EMP and Operating Plans - Clauses for Inclusion in Contract Documents EMP and EMP and Operating Plans Responsibility Annexes (Clauses to be included in the Contract Document - to it highlighted)
EMP The Contractor w ill, prior to commencing site Contractor + SE preparation and construction activities, prepare: An Environmental Management Plan (EMP) for approval by the Senior Engineer (SE). The EMP will be guided by Chapters 4 and 5 of this IEE Report, particularly the Summary EMP (Figure 17) and include, as Annexes, the Operating Plans listed below (all to be approved by the SE). ANNEX A A Waste Man agement Plan to guide the handling of materials for Contractor + SE recycling (glass, plastic and clean paper), domestic waste, sewage, and hazardous waste. ANNEX B A Quarry and Borrow-pit Operations and Site Restoration Plan. Contractor + SE ANNEX C A Traffic Management Plan Contractor + SE ANNEX.D An Asphalt Plant Site Development and Operating Plan Contractor + SE ANNEX.E A Facilities Plan (c overing: work c amps, c oncrete mixing pla nts, Contractor + SE storage areas and vehicle and equipment maintenance areas) ANNEX.F A Plan for H andling C hemicals a nd H azardous Ma terials and an Contractor + SE Emergency Contingency Response Plan ANNEX.G A Community Consultation and Communications Plan Contractor + SE
75. The Final EMP and the Operating Plans attached as Annexes “A” through “G” to the EMP will, after approval by the SE, become the Environmental Management Package and form part of the Contract Package with all of the requirements for commitment and performance as applied to engineering and financial performance.
76. The full contents of the EMP will be as follows: (i) Statement of Commitment and Signature Block; (ii) Summary of Potential Impacts; (iii) Planned Mitigation Measures; (iv) Planned Environmental Monitoring and Schedule for Monitoring; (v) Planned Public Consultation Process; (vi) Responsibilities for Implementing Mitigation Measures and Monitoring; (vii) Responsibilities for Reporting and Review; (viii) Environmental staff and activities/inputs of various government agencies; (ix) Environmentally Responsible Procurement Plan; (x) Operating Plans – Summary; and (xi) Annexes: Operating Plans: A through G.
24
C. Responsibilities for Impact Prevention and Mitigation
77. The Contractor will: (i) Prepare the Draft EMP (ii) Present the Draft EMP to the IES and EM for their review and comment before submitting it to the SE for approval and before discussing it with central and provincial government authorities, village leaders and villagers in affected communities. (iii) After the above discussions, revise the EMP as appropriate. (iv) Prepare the Operating Plans specified in the Summary EMP and include these as Annexes to the EMP. (v) During works ensure that environmental management issues are checked regularly in order to ensure compliance with the Contract Specifications and the EMP. (vi) Report as specified to the SE.
78. The ARD will, before accepting any Contractor bid to undertake the construction of any part of the Project road, check to ensure that the Contract Price explicitly identifies cost commitment to undertake the environmental protection measures specified in the EMP and the Environmental Enhancement Measures specified above.
79. Before completion of construction and releasing sections of road from Contractor to Government control, the ARD will: (i) Ensure that the design and construction standards meet the required standards including road markings, signage and safety devices and the posted travel speeds accord with international standards. (ii) Formulate and apply an Emergency Contingency Plan (ECP) to cope with accident events including potential spills of hazardous and other substances within the ROW and on adjacent land or streams nearby. (iii) To Report to the MOTC and ADB as required.
80. The ARD Environmental Manager (EM) will: (i) Participate with the IES to review the Draft EMP and recommend improvements as appropriate. (ii) Ensure that ARD becomes informed of any important environmental issues. (iii) Check on environmental performance weekly and submit Monthly Environmental Reports to the Senior Engineer (SE) for incorporation into Works Monthly Reports.
81. The Independent Environmental Specialist (IES) will: (i) Review the Draft EMP prepared by the Contractor and, with the EM, suggest revisions before the Contractor submits it to the SE and discussions with villagers (ii) Assist the Contractor to prepare the Final EMP (part of the Contract Package). (iii) Review the Monthly Environmental Reports and prepare a consolidated Environmental Management Report every 3-months. (iv) Visit works and associated sites as required and advise the EM and SE on environmental management issues as these may arise. (v) Prepare and deliver an Environmental Awareness Raising and Training Program.
25
D. Environmental Enhancement Measures
82. The only environmental enhancement measures will be: (i) The construction of pedestrian overpasses at locations to be determined during the Project Design Phase (beginning late 2009) (ii) General landscaping after completion of the road improvements on the 4-lane, M- 1, north road section.
E. Environmental Monitoring Program
83. From the ADB, Environmental Assessment Guidelines, (2003) and experience with other roads projects, key features of a useful monitoring program include: realistic sampling program (temporal and spatial), sampling methods relevant to source, ability to collect quality data, comparability of data over time, cost-effectiveness, ease of interpretation reporting simplicity (for internal management and external checking), allowance for, and response to, third parties, and suitability for public presentation and understanding.
84. The ARD wishes to monitor performance of its contractors during construction of the proposed road works in order to ensure an adequate level of compliance with environmental impact mitigation measures and employs its own staff to undertake the necessary tasks. An outside, Independent Environmental Specialist (IES) will be appointed to work alongside the ARD Environmental Manager (EM) and appointed community members from affected communities.
85. Monitoring requirements and responsibilities are summarized in Figure 12.
F. Cost of Impact Prevention, Mitigation, Monitoring and Enhancement
86. The cost of environmental impact prevention, mitigation and monitoring for the two, 4- lane road sections: the M-1 north section – Yerevan to Ashtarak and the M-2 south section – Yerevan to Ararat, will be minimal. The costs relate only to the actions required of the engineers and contractors in the normal execution of the Project and the incremental cost of environmental monitoring by the EM and the IES.
87. The impact prevention and mitigation measures recommended here are normal, standard, internationally recognized impact prevention and mitigation measures and form part of the Works Contract Price – the engineering and construction cost package.
88. Environmental monitoring to ensure compliance will be conducted by the EM within the ARD, the State Environmental Inspectorate (SEI) and be checked on periodically by an International Environmental Specialist (IES). Thus the cost will included the normal salary of the EM and a total of 6-person months for the IES. At normal international rates this will amount to approximately US $110,000 plus travel and accommodation.
89. The cost of constructing pedestrian overpasses at locations to be determined during the Project Design Phase (beginning late 2009), and of general landscaping after completion of the road improvements on the 4-lane, M-1, north road section, are covered in the Works Contract Price.
26
Figure 12: Monitoring Requirements - Site Preparation and Construction Parameters to be Monitored Locations for Frequency Responsibility Refer to EMP Monitoring and Data of for Monitoring Sources Monitoring Work Sites: Work sites: Weekly EM Visual inspection Quarterly IES Dust and use of water spray - Slope protection and drainage - Runoff control - Drainage maintenance - Substances/materials in water courses - Work site safety: Work sites: Weekly EM Visual inspection Quarterly IES Signage - Barriers - Site cleanliness - Use of safety equipment - Traffic and Road safety: Work sites: Weekly EM Visual inspection Quarterly IES Signage, Barriers, Routes - - Material on the road Traffic routes - Condition of rural roads - - Vehicle & equipment emissions control - - Incidents and complaints Vehicle Maintenance logs Quarterly Complaints Log Monthly Work camps: Works camps: Weekly EM Visual inspection Quarterly IES Solid waste management - - Sewage management - - Social issues Complaints Log Monthly Site restoration - Monthly Facilities areas: Facilities areas: Weekly EM Visual inspection Quarterly IES Storage of diesel and waste oil - - Material/substance sheets - Monthly Site restoration - Monthly Quarries and borrow pits: Quarries and borrow pits: Weekly EM Visual inspection Quarterly IES Slope management - - Runoff management - - Use of safety equipment - - Site restoration - Monthly Asphalt plants: Asphalt plants: Weekly EM Visual inspection Quarterly IES Diesel storage and use management - - Dust emission control - - Waste management and disposal: Work sites, Works Weekly EM camps, disposal sites: Quarterly IES Visual inspection Solid waste storage and transport - Solid waste disposal sites - - Asphalt recycling, re-use and disposal - - Sewage management and disposal - - Waste oil disposal - - Coordination with MNP and Local SE Log Monthly EM authorities Checking with MNP Complaints Complaints Log Monthly EM Consultation and Information sharing SE Log Quarterly EM with communities Minutes of meetings
27
5.7 Environmental Management Seminars
90. It is important to ensure that ARD officers, Area Engineers, Resident Engineers, Contractors, Contract Supervisors and Foremen, understand the basics of sound environmental management and the measures required to prevent and/or reduce environmental impacts. To facilitate such understanding, a set of five seminars will be designed for delivery to concerned parties.
91. The purpose of the seminars is to ensure that all managers and supervisors involved in the final design and construction of the road have basic and similar understanding of environmental issues and their management, and how to prevent or reduce the impacts likely to be created by the project particularly during the construction phase.
92. The seminars will be based on the contents of this report, particularly the EMP and Monitoring Program and follow closely the requirements set out in the ADB, Environmental Assessment Guidelines, 2003.
93. Delivery of five Environmental Management seminars, their locations and participants will be decided by the IES and EM, however, the timing of seminar delivery will be as set out below. Five Environmental Management seminars will be delivered as follows, during the: (i) 1 -- Detailed Project Design Phase (ii) 2 -- Preparation for construction (iii) 3 -- First month of Project activities (iv) 4 – Months 3-4 of construction activities (v) 5 – Month 6-7 of construction activities.
28
VI. PUBLIC CONSULTATION and INFORMATION DISCLOSURE
A. Consultation Process
94. The IEE Report will be made available publically in Armenia by GoA, MOTC and MNP and provided to affected communities. The NPE (of the MNP) will hold public meetings on the IEE Report and Project. Then the NPE will consider all comments, the IEE Report and the Project before granting, not granting, or granting with conditions, permission to proceed with the Project.
95. The Summary IEE report (SIEE) will be placed on the ADB Website in August 2009. It forms Appendix 1 to this IEE Report.
96. Meetings were held with representatives of a number of stakeholder groups and will be ongoing with the same and different stakeholder groups during the preparation of other (future) projects planned to be funded under the MFF.
97. Comments obtained to date relate to the MFF Program as a whole rather than to this specific 1st Tranche Project. Most concern was expressed with regard to possible future tranches in the south of Armenia rich in biodiversity. Little concern was expressed with regard to any intended road works in the central part of the country, particularly along existing road alignments. The most frequently expressed concern was that the EMP should be followed and enforced.
98. Meetings, guided by a discussion guide were held during June and July 2009.with representatives of the stakeholder groups listed in Figure 13.
B. Community Involvement to date:
99. Village leaders completed the Environmental Questionnaire that was included with the social and demographic questionnaire when provided to communities by the Resettlement Survey Team in July 2009. Results from this survey were not available at the time of preparing this IEE report (prepared late July 2009 so that the Summary IEE could be placed on the ADB Website in August).
100. Face-to-face interviews were held by the Environmental Impact Assessment Team with 94 villagers from 3 different communities: Agarak, Udjan and Kosh (located in Aragatsotn Marz but not along the M-1, 4-lane north road section of this IEE report). As stated above, discussions to date have related to the MFF Program as a whole, nevertheless, the three selected villages are located within 15km of the 4-lane section of the M-1 chosen for improvement and there are no villages located along the Project road sections.
101. The Environmental Questionnaire used in the survey is attached as ANNEX 1 to this Chapter. Interviews were conducted in the Armenian language. The essential features of the proposed road improvement program were described to respondents, the expected benefits and negative impacts outlined and questions asked via closed questions related to the existing road and respondent perceptions of likely environmental impacts.
29
Figure 13: Environmental Stakeholder Groups Met to Date Stakeholders Stakeholder Groups
Government ¾ Ministry of Transport and Communication ¾ Ministry of Nature Protection ‐ Bioresources Management Agency ‐ Nature Protection Expertise (NPE) ‐ State Environmental Inspectorate (SEI) ¾ Ministry of Culture ‐ Agency for Protection of Historical and Cultural Monuments Regional ¾ Aragatsotn administrations ¾ Shirak (marzpetaran) International ¾ ADB organizations ¾ WWF ¾ World Bank ¾ USAID ¾ UNDP and GEF ¾ US Millennium Challenge Account – Armenia Village leaders ¾ Community leaders: Leaders in 14 selected communities completed the and villagers Environmental Questionnaire ¾ Villagers: 94 villagers in 3 different communities were interviewed and the Environmental Questionnaire filled out by the interviewer ¾ NGO ¾ NGO Interest & Reason Selected ¾ Inst. Ethnography and ¾ Archaeological Research and National NGOs Archaeology Documentation ¾ Armenian Ecological Assoc. ¾ Ecological issues, assessment of projects, E education and research ¾ Biodiversity, particularly of fish ¾ Environmental Survival species ¾ Facilitation of public participation in ¾ Aarhuus Centre of Gyumri environmental issues
102. Results from the face-to-face survey are shown by number and percentage of responses in Figure 14.
30
Figure 14: Results of Survey of Villagers (94 respondents) Number and Percentage of Responses Responses: > No. % No. % 1 Do you use the existing road? Yes 89 95 No 5 5 2 Please comment on problems It is too narrow Yes 66 81 No 15 19 with the existing road: It is dangerous Yes 76 86 No 12 14 It is very poor quality Yes 31 48 No 33 52 No Problems Yes 77 95 No 4 5 3 Do you think that the road needs to be repaired & improved? Yes 83 99 No 1 1 4 Do you think that a 4-lane road is needed? Yes 75 87 No 11 13 Consider the environment near the existing road and the works Yes 35 40 No 53 60 5 to expand it. Do you think that impacts may be serious? 6 What you think about each of the following impacts from road construction? Please circle one number of the scale below. 1 indicates little concern, 5 most concern. 1 2 3 4 5 Results: > No. % N o. % N o. % N o. % N o. % 6.1 Noise 49 56 13 15 18 21 5 6 3 2 6.2 Water Pollution 70 79 10 11 5 6 3 3 1 1 6.3 Air Pollution 35 38 18 19 23 25 9 10 8 9 6.4 Construction Traffic 21 23 12 13 24 27 20 22 13 14 6.5 Workers or Work-Force 14 15 7 8 24 26 24 26 24 26 6.6 Disturbance of Land 40 43 6 6 17 18 17 18 21 22 6.7 Other Impact – Please describe: This question was poorly and hardly answered. Respondents provided comments under question 7. Please make any comments to 7 guide the works activities: Note: The 94 respondents did not answer all questions. The average response factor for the 8 yes/no questions was approximately 94%; for the 7 perception questions it was approximately 97%. The percentages shown in the table above refer to the percentages of the actual responses rather than the total number of respondents in the survey. All numbers are rounded to the nearest whole number.
103. Figure 15 shows that 95% of respondents used the existing 2-lane road, 81% considered it to be narrow, and 86% considered it to be dangerous but, on the other hand, 52% of respondents considered that the road was adequate.
104. When asked to rate the level of concern about some of the standard impacts from road construction, the respondents indicated that the greatest concerns were with potential issues related to the work force (52% - i.e., 4 or 5 on the semantic differential scale), and disturbance of land (40%). Another serious concern related to potential impacts from construction traffic (36%).
105. At the other end of the scale, of very little concern were the potential impacts from water pollution (90% expressed little concern) and noise (71%), followed by potential air pollution, 57% of respondents expressing little concern.
31
ANNEX 1 to Chapter 6 Environmental Questionnaire: Perceptions of Likely Impacts and Related Issues
Introduction: The Armenia Roads Directorate of the Ministry of Transport and Communications (MOTC) proposes to improve roads in the north-south corridor. One road project under consideration is to repair and expand the road from Ashtarak to Gyumri.
The work will expand the road from 2-lanes to 4-lanes and provide road shoulders and drainage to international standards. The final road will look very similar to the present 4-lane section from Yerevan to Ashtarak. Work is planned to begin next year.
We are assessing the likely environmental and social impacts arising from the road works and the expanded road and appreciate your help in assessing concerns about likely environmental impacts.
Please consider the following. Your responses will be included in our assessment report and provided to the MOTC, the engineers and the contractors involved in the construction.
Please Consider and Address the Following: 1 Do you use the existing road? Yes No 2 Please comment on problems It is too narrow Yes No with the existing road: It is dangerous Yes No It is very poor quality Yes No No Problems Yes No 3 Do you think that the road needs to be repaired & Yes No improved? 4 Do you think that a 4-lane road is needed? Yes No 5 Consider the environment near the existing road and the Yes No works to expand it. Do you think that impacts may be serious? 6 What impacts are you most concerned about? For each impact, please circle one number on the scale below. 1 indicates little concern, 5 most concern. What you think about each of the following impacts from road construction? Noise 1 2 3 4 5 Water Pollution 1 2 3 4 5 Air Pollution 1 2 3 4 5 Construction Traffic 1 2 3 4 5 Workers or Work-Force 1 2 3 4 5 Disturbance of Land 1 2 3 4 5 Other Impact – Please 1 2 3 4 5 describe: 7 Please make any comments to guide the works activities:
32
VII. SUMMARY, CONCLUSIONS, AND RECOMMENDATIONS
A. Summar y
106. A priority of the Asian Development Bank (ADB) funded multi-tranche funding facility (MFF) Program is to rehabilitate, reconstruct and expand international transport corridors including the Project road sections which form part of the Armenia north-south road corridor. The two road sections to be improved under the 1st Tranche Project of the MFF are the 4-lane divided roads of the M-1, north from Yerevan to Ashtarak, and of the M-2, south from Yerevan to Ararat. The Government of Armenia (RA) has appointed the Armenian Roads Directorate (ARD) of the Ministry of Transport and Communications (MOTC) to coordinate the work.
107. The RA Ministry of Nature Protection (MNP) administers Environmental Impact Assessment (EIA), via the Nature Protection Expertise (NPE) organization, and compliance with environmental laws and regulations, via the State Environmental Inspectorate (SEI).
108. Both the ADB and GoA require the likely environmental impacts that may be caused by a project be identified during the project planning and pre-feasibility stages and prevented or mitigated as much as possible during construction and operations. The Project is classified by the ADB (for environmental management purposes) as a Category B project. This means that impacts are not expected to be significant but nevertheless need to be identified and reported in an IEE report. The RA does not differentiate between IEE and EIA.
109. The ADB and MOTC will review the IEE Report before passing it to the MNP. The Report will then be made public by the MNP and MOTC before the NPE clears the Project for implementation by the MOTC. The ADB will post the Summary IEE Report on its website.
110. The two road sections to be improved under the Project are existing 4-lane divided roads.
111. Road works are to be fully confined to the existing rights-of way (ROW) and be constructed in sections, one side of the 4-lane carriageway at a time, in order to enable continued use of the existing road during construction.
112. There will be no changes to vertical or horizontal alignments. There will be no removal of top-soil, no new cut or fill sections and no bridge construction.
113. Both road sections are located in arid areas. The landscape over the M-1 north road section is gently rolling uplands; the landscape over the M-2 south road section is flat.
114. The native flora and fauna of semi-desert varieties has been largely replaced along the road corridor by domestic plants and animals. There are no original trees along either road section, and few trees of any substance. There are no unique areas, no protected areas and no forests or ecological reserves but, along the M-1 north road section there are two known archeological sites and there may be undiscovered archaeological remains or artifacts below ground. There are no known similar sites within 100m of the ROW on the south road section.
33
B. Environmental Screening - Potential Impacts and their Significance
115. Improvement of the road sections will impact the baseline environment only via minor, short-term impacts. Operation of the Completed Road will create minor positive impacts via air quality improvements (due to the smoother travel and better fuel combustion) and reduced road accidents (due to the improved safety barriers, road markings, lighting and the control of U- turns).
116. The area is arid, hence, there is very little water that may become affected and no improvements are foreseen for the high bridge over the Yeraskh River. Therefore, impacts on water quality are expected to be insignificant. There are no ecologically important or sensitive environmental elements and few human use factors that may be significantly affected. The most important possible impact issue is the potential to unearth archaeological sites or artifacts.
117. All negative impacts will be localized, short-term, insignificant and preventable or mitigable including: air quality impacts from dust nuisance, noise nuisance and impacts on land, which will be confined to the existing ROW, quarry and borrow-pit sites.
118. Health and safety impacts may be significant but preventable at all locations.
119. Potential negative impacts have been addressed in the EMP, the implementation of which will prevent or mitigate them.
120. Positive impacts will be created via short-term jobs, local employment and the associated increase in short-term expenditure. Households and businesses will benefit significantly over the short-term.
C. Recommendations
121. With reference to the IEE Report Chapters 5 and 6, it is recommended that: (i) The clauses set out in the Summary EMP and the IEE Report be included in the Contract Documents (ii) The Contractor prepare an EMP and the operating plans specified in the IEE Report (iii) The ARD and SEI ensure that the impact prevention and mitigation measures specified in the IEE, EMP and operating plans be implemented. (iv) Environmental Management Seminars be developed and delivered by the International Environmental Specialist (v) Environmental monitoring be carried out as specified in the EMP and Monitoring Program (vi) ARD ensure that the completed road meets the requirements under the European Agreement on Main International Traffic Arteries to which GoA is a signatory.
34
REFERENCES
Asian Development Bank (ADB), Environmental Policies, 2002. ADB, Environmental Assessment Guidelines, 2003. ADB, Republic of Armenia, Rural Roads Sector Project (Loan 2351-ARM), 2008. Armenia National Atlas, Yerevan, 2007 [email protected]. Also www.masstours.com. Nev, Rick, Aragatsotn Marz, Tour Armenia @ 2007. Also www.TACentral.com. Republic of Armenia (RA), Ministry of Nature Protection, Fourth National Report to the Convention on Biological Diversity, Yerevan, 2009 RA, Ministry of Transport and Communications, Armenia Roads Directorate (ARD), Armenia: Rural Road Sector Project - Environmental Assessment Report, June 2007. RA, National Statistics Service, Report of the Results of the 2001 Armenian Census World Bank, Roads and the Environment: A Handbook (technical paper 376), c. 1997.
35
APPENDIX 1: SUMMARY INITIAL ENVIRONMENTAL EXAMINATION (SIEE)
1. Multitranche Financin g Facility (MFF). Under the Armenia Transport Strategy 2020, the Government of Armenia (RA) formulated the North-South Road Corridor Program in line with the ADB, Armenia…Country Strategy, to support regional cooperation and revitalize road and railway infrastructure. A priority is to rehabilitate, reconstruct and expand the Bavra-Yerevan-Agarak north- south road corridor. A multi-tranche funding facility (MFF) funded by the Asian Development Bank (ADB) has been set up to assist Armenia. The RA has appointed the Armenian Roads Directorate (ARD) of the Ministry of Transport and Communications (MOTC) to co-ordinate the work.
2. The MFF objective is to improve existing 4-lane divided roads, widen existing 2-lane roads (often in poor condition) to 4-lane divided roads along existing alignments wherever possible, or to construct alternate 2-lane roads where a single 4-lane road would not be feasible.
st 3. Project Summary. The Project is to improve two sections of road under the 1 Tranche of the MFF, namely the 4-lane road section of the M-1 Highway from Yerevan north to Ashtarak and of the M-2 highway from Yerevan south to Ararat.
4. Environmental Assessment Requirement. Among other environmental laws, GoA Ministry of Nature Protection (MNP) administers: a) the environmental impact assessment (EIA) process via the Nature Protection Expertise (NPE) organization, and b) compliance with environmental laws and regulations via the State Environmental Inspectorate (SEI).
5. Both the ADB and GoA require the environmental impacts that may be caused by a project to be identified during the project planning and pre-feasibility stages and prevented or mitigated as much as possible during construction and operations. The Project is classified by the Bank (for environmental management purposes) as a Category B project. This means that impacts are not expected to be significant but nevertheless need to be identified and reported in an IEE report. The RA does not differentiate between IEE and EIA. 6. 7. The ADB and MOTC will review the IEE Report before passing it to the MNP. The Report will then be made public by the MNP and MOTC before the NPE clears the Project for implementation by the MOTC. The ADB will post the Summary IEE Report on its website.
st 8. Project Description. The road sections to be improved under this 1 Tranche Project are two sections of the North-South Road Corridor included for rehabilitation or expansion under the MFF. The two road sections to be improved stretch short distances north and south of Yerevan.
9. The 18.4km M-1, 4-lane road section north of Yerevan was originally built over the period 1975 to 2004. Its condition is deteriorated and its standard varies so that the road-bed needs improvement to meet the design and construction standards normally associated with international transit routes. The 38.0km M-2, 4-lane road section south of Yerevan was built more recently and is in relatively good condition. Neither road section is adequately drained, the shoulders in many parts are very narrow and not properly paved, there are many randomly located U-turns, signage, road markings and lighting are absent or inadequate, there are insufficient crash barriers and median separation barriers and road structures need to be investigated to determine their structural integrity.
10. A key objective of the Project is to ensure compliance with the road safety and signage requirements under the European Agreement on Main International Traffic Arteries (AGR) to which GoA is a signatory.
37
11. Road works are planned to be fully confined to the existing ROW and be constructed in sections, one side of the 4-lane carriageway at a time, in order to enable continued use of the existing road during construction. Transport of materials will be confined to the existing 4-lane road, to the one-side being worked on. The road works on both road sections will include the following: (i) Constructing proper drainage side-ditches and cross-drainage as required. (ii) Improving the road-shoulders. (iii) Improving traffic safety measures: signage, guardrails, traffic markings and turning lanes. (iv) Repairing road structures: over-passes, under-passes, and cut and embankment slopes.
12. The road works on the M-1 north section (Yerevan to Ashtarak) will also include: (i) Removing the existing asphalt layer (and grinding and re-using it as much as possible). (ii) Removing below-standard top and sub-grades and sub-base as required and replacing it with material meeting accepted quality standards. (iii) Completing the travel lanes and shoulders with a new concrete asphalt layer. (iv) Providing landscaping where appropriate.
13. Construction is planned to begin late 2010 and be finished by mid-2012.
14. Physical Resources. Both road sections are located in arid areas (annual precipitation less than 400mm) but the environmental settings are different. The landscape north of Yerevan along the M-1 Project road corridor is gently rolling uplands 1,060m to 1,270m in elevation. The Kasakh River dissects the landscape in a deep gorge north of Yerevan. There are no other surface streams along the north road section. The landscape south of Yerevan along the M-2 Project road corridor is flat and about 1,100m in elevation. There are no surface streams but the Ararat Valley is a noted artesian basin fed by snow melt and a sub-surface network of aquifers through the fractured lava. The land is irrigated wherever possible.
15. Ecological Resources. The native flora and fauna of semi-desert and steppe varieties has been largely replaced along the road corridor by domestic plants and animals. There are no unique areas, no protected areas and no forests or ecological reserves within several kilometers of the ROW.
16. Human Use of Resou rces. The existing 4-lane roads form an important feature of the existing environmental baselines along both road corridors and present a significant barrier to people trying to cross the road. There are no industrial buildings, facilities, commercial operations or residences located within either ROW. No land purchase or resettlement will be necessary.
17. Agriculture along the north road section is limited to small orchards and a few hay fields towards Ashtarak. In complete contrast, agriculture predominates along both sides of the alignment in the south. The flat, irrigated land is intensely cropped with vineyards, wheat, orchards and market-gardens wherever irrigation is possible.
18. Human Qu ality-of-Life Values (Social and Cultural Re sources). Close to the ROW on the north road section there are two known archeological sites protected by GoA Department of Historical Monuments (Ministry of Culture). One site stretches 500m along the edge of the ROW between it the Kasakh River near the bridge over the River and down the valley side to the River itself.
38
19. The second site is located astride the interchange at Agarak. There may also be undiscovered archaeological remains or artifacts below ground. There are no known sites within 100m of the ROW to the south.
20. Social conditions are as to be expected where the annual average per capita monetary income is about US $2,000 (lower in rural areas) but people manage to live above that level in terms of PPP, standard of living, lifestyles and social-support services. Many people in the Project corridors work in Yerevan and/or agriculture, particularly in the south corridor.
21. Environmental Screening - Pot ential Impa cts. Improvement of both road sections will impact the baseline environment only via minor, short-term incremental impacts. Earthworks, construction activities and quarry and borrow-pit operations may create a number of short-term impacts on air and land quality, health and safety, may cause local flooding (by diverting runoff) and unearth archaeological sites or artifacts. Other activities most likely to cause negative impacts are asphalt plant operations, transport of materials, storage and handling of diesel, traffic in and near work sites, and work camp site preparation and operations.
22. Under the Project, there will be no changes to vertical or horizontal alignments. There will be no removal of top-soil, no new cut or fill sections and no bridge construction. Most construction works will be confined to the north section, the 18.4km 4-lane road section from Yerevan to Ashtarak, where the road-bed itself will be improved by removing the old asphalt, digging out and removing sub-standard road-bed materials and replacing both with new material. Digging may unearth archaeological sites or artifacts. Over the south section (Yerevan to Ararat) works will be limited to shoulder, drainage and culvert improvements.
23. The disposal and replacement of up to 300,000m3 of sub-standard material from the existing north road section will require up to 100 truck movements per day over the construction period. With the current ADT of 11,680 vehicles including 13% trucks and other large vehicles, the works-truck traffic will add less than 5% to the existing ADT for large vehicles.
24. Operation/Use of the Completed Road will create minor positive impacts. Air quality will improve, due to the smoother travel and better fuel combustion, road accidents will reduce due to the improved: safety barriers, road markings, lighting and the control of U-turns
25. Significance of Potential Impacts: Water, land and air quality (and noise) and health and safety are most likely to be impacted along the north road section, and rural roads may be damaged depending on the selected truck routes. Each potential impact has been assessed in- depth with reference to the environmental baseline and its sensitivity.
26. The area is arid, hence, there is very little water that may become affected and no improvements are foreseen for the high bridge over the Yeraskh River. Therefore, impacts on water quality are expected to be insignificant. There are no ecologically important or sensitive environmental elements and few human use factors that may be affected. The most important possible impact issue is the potential to unearth archaeological sites or artifacts—addressed in the EMP.
27. Air quality impacts will be confined to localized dust nuisance. This may be significant but manageable. Similarly noise may be significant, localized and manageable. Impacts on land quality are expected to be very minor because works will be minor on the south road section and confined to the existing ROW of the north road section. Hence, the likely impact on land is considered to be insignificant and manageable.
28. Health and safety impacts may be significant but preventable at all locations.
39
29. While actual impacts will be short-term and expected to be insignificant, all have been addressed in the EMP, the implementation of which will prevent or mitigate them.
30. Short-term positive impacts will be created via short-term jobs, local employment and spin- off effects associated with the increase in short-term expenditure. In-turn, households and small businesses will benefit significantly over the short-term.
31. Environmental Impact Prevention and Mitigation. The identified environmental impacts are well known to competent civil engineers and competent construction companies – as are the impact prevention and mitigation measures to address them. Nevertheless, in order to ensure understanding of required prevention and mitigation measures, an EMP and appropriate clauses for inclusion in works contracts have been prepared and seminars on environmental management will be held for engineers, the Contractor, works supervisors and works foremen.
32. The EMP is designed to guide engineers and contractors to prevent or mitigate environmental impacts, to guide monitoring by ARD, the SEI, and the International Environmental Specialist (IES). Prior to commencing site preparation and construction activities, the Contractor will prepare a Draft EMP and Monitoring Program guided by the IEE Report, particularly the Summary EMP set out below. The Draft EMP will be approved by the Senior Engineer (SE) and support consultations with responsible authorities at central, regional and local levels. The EMP will be revised as required on receipt of comments from stakeholders and the responsible authorities and then finalized. The Contractor will also prepare operating plans to be attached to the EMP. When finalized as the Approved EMP, the SE, Contractor and Works Foremen will sign it testifying to their agreement to comply with it. The EMP and operating plans will become part of the Main Contract Package.
33. Environmental Monitoring Program. Monitoring requirements and the responsibilities for monitoring are summarized below. The cost of environmental impact prevention, mitigation and monitoring for the two road sections will be minimal as they relate only to the actions required by the engineers and contractors in the normal execution of the Project and the incremental cost of environmental monitoring by the EM and the IES.
34. The impact prevention and mitigation measures in the EMP are normal, standard, and widely recognized and will form part of the engineering and construction cost package. Environmental monitoring to ensure compliance will be conducted by the EM within the ARD, the State Environmental Inspectorate (SEI) and be checked on periodically by the IES. Thus the cost will be included the normal salary of the EM, the normal budget of the SEI, and a total of 6-person months for the IES (at normal international rates this will amount to approximately US $110,000 plus travel and accommodation). The costs of providing pedestrian over-passes and limited landscaping of the north road section are covered in the Works Contract Price.
35. Public Consultation and Information Disclosure. This Summary IEE report placed on the ADB Website will be made available publically in Armenia by GoA MOTC and MNP, and provided to affected communities.
36. Meetings with representatives of stakeholder groups obtained comments on the MFF program as a whole rather than this specific 1st Tranche project. Most concern was expressed with regard to possible future tranches in the south of Armenia rich in biodiversity. Little concern was expressed with regard to any intended road works in the central part of the country, particularly along existing road alignments. The most frequently expressed concern was that the EMP should be followed and enforced.
40
37. Environmental Screening - Poten tial Impact s and their Significan ce. Improvement of the road sections will impact the baseline environment only via minor, short-term negative impacts. Road operations will create minor positive impacts via air quality improvements and reduced road accidents.
38. The area is arid, hence, there is very little water that may become affected, thus impacts on water quality are expected to be minimal and not significant. There are no ecologically important or sensitive environmental elements and few human use factors that may be significantly affected. The most important possible impact issue is the potential to unearth archaeological sites or artifacts.
39. All negative impacts will be localized, short-term, insignificant and preventable or mitigable including: air quality impacts from dust nuisance, noise nuisance and impacts on land -- confined to the existing ROW, quarry and borrow-pit sites. All potential negative impacts have been addressed in the EMP.
40. Positive impacts will be created via short-term jobs and the associated increase in short- term expenditure and benefits to households and businesses.
41. Recommendations. With reference to the IEE Report Chapters 5 and 6, it is recommended that: (i) The clauses set out in the Summary EMP and the IEE Report be included in the Contract Documents (ii) The Contractor prepare an EMP and the operating plans specified in the IEE Report (iii) The ARD and SEI ensure that the impact prevention and mitigation measures specified in the IEE, EMP and operating plans be implemented. (iv) Environmental Management Seminars be developed and delivered by the International Environmental Specialist (v) Environmental monitoring be carried out as specified in the EMP and Monitoring Program (vi) ARD ensure that the completed road meets the requirements under the European Agreement on Main International Traffic Arteries to which GoA is a signatory.
41
Figure 11: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 1 of 5 Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors 1. Construction: (i) Dust and emissions Construction and Related Activities (ii) Traffic hazards and safety The Co ntractor will p repare an En vironmental Manag ement Pl an (EMP) fo r ap proval b y t he Sen ior (i) Earth works (iii) Work site safety Engineer (SE) -- prior to c ommencing site preparation and construction. The EMP will be guided by the IEE Report, the principles set out in the Summary EMP and the following: (ii) Cul verts (iv) Social nuisance (i) Prior to commencing any works, the Contractor will meet with the ARD, MNP and Marz authorities. (iii) Dispose of (v) Erosion of material piles and runoff (ii) Areas of disturbed land will be restored or rehabilitated as soon as possible. surplus may affect nearby land and plants (iii) Works stockpiles will be located away from drainage areas and water-courses. material (vi) Works can cause local flooding (iv) Construction and related activities, such as stockpiling, servicing and drainage works will be restricted to (vii) Material beyond ROW affects identified sites. nearby land quality and use (v) Spoil and materials piles will be graded, stabilized and drained. (vi) Construction material/waste will be kept within the ROW and away from water bodies. (viii) Noise and vibration (vii) Adequate temporary drainage will be provided to prevent local flooding. (ix) Works may unearth (viii) Runoff from sites will be prevented from entering natural water-courses, for example by using sediment archaeological artifacts traps, silt aprons and/or straw bales. Also see: Drainage, Slope Stability Erosion and Sediment Control – below. (ix) Water sprinklers will be used to minimize dust in and around work areas. (x) Work along the north road section will be undertaken only during daylight hours. (xi) Workers will use safety equipment (helmets, eye-glasses, ear-plugs - as required) and follow safety procedures (xii) Nearby residents, commercial and industrial land users and communities will be informed of major activities ahead of their implementation and be informed of a clear mechanism for comments and complaints to be communicated to the SE. Waste Management The Co ntractor will p repare a W aste Man agement Pl an fo r app roval b y th e Sen ior En gineer p rior to commencing work. The Plan will be guided by the following: (i) Solid waste will be separated (it is understood that clean paper, glass and poly-propylene plastics are recyclable in Armenia) and stored for regular collection for correct off-site disposal in a nearby municipal waste facility. (ii) Solid waste disposal sites will be identified in concert with local officials and the MNP prior to any dumping. (iii) Solid waste, waste spoil, waste aggregate/materials and waste material removed from the existing road (e.g., used asphalt-concrete that cannot be crushed and re-used) will be disposed of only in designated sites/locations. (iv) Waste oil will be collected and stored in used fuel drums for later safe disposal in a manner and/or at sites approved by the MNP. (v) Waste asphalt removed from the existing road (north) will be recycled and re-used in the new road construction as much as possible. All old asphalt that cannot be re-used will be handled as toxic waste and disposed of only at a site approved by MNP and local authorities.
42
Figure 11: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 2 of 5 Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors
1. Construction: Drainage, Slope Stability Erosion and Sediment Control (i) Control devices/actions will be designed to provide adequate protection for each area, according to slope, (i) Earth works drainage pattern, likely rainfall, and the construction site. (ii) Cul verts (ii) Measures to control runoff, erosion and sedimentation will include: (iii) Dispose of (a) Diversion of natural runoff around construction areas surplus (b) Use of temporary bunds to divert runoff to temporary or permanent drainage facilities material (iii) Drains, runoff, erosion and sedimentation protective measures will be maintained regularly to ensure adequate capacity. (iv) Temporary diversion drains will be extended beyond the toe line of an embankment to avoid embankment erosion (v) Drainage structures and erosion controls will be monitored and repaired/modified as soon as possible after rain. Noise and Vibration (i) Vehicles and equipment will be fitted with emission controls and silencers to meet national noise control and emission standards and be checked every six-months to ensure compliance. (ii) The asphalt plant and equipment will be operated only in daylight. (iii) Noise control barriers (e.g., solid walls, earth barriers, noise-reflective panels) will be used when necessary to shield houses, schools and hospitals Archaeological Finds When an archaeological site is found, work will be stopped immediately. The Senior Engineer will be notified. Then, the following steps will be taken: Isolate the site. (i) Call the Archaeology and Ethnography Inst., Armenian National Academy of Sciences and the Agency for Protection of Historical and Cultural Monuments to assess the site and determine whether and how it should be preserved (ii) Document and photograph the find and area immediately around it (iii) When advised and as directed by the Archaeologist, excavate and remove the find (iv) After documentation and after being advised that the site is not important, resume construction.
2. Sto rage an d (i)Diesel and waste oil is toxic to all (i) Diesel will be stored in drums or tanks under cover on an impervious pad of concrete or clay (for later removal and handle d iesel and living organisms - in the soil or in safe disposal), and the pad will be surrounded by an impervious bund enclosing a catch volume at least 50% more waste oil (including surface or ground-water. Diesel than the volume of diesel stored. Should clay be used to form the bund and a spill occur, the bund will be vehicle an d and waste oil kills all living removed after construction has ceased and disposed of safely (as for impervious pads of clay). equipment organisms (ii) Vehicles and equipment will be maintained in designated areas underlain by an impervious pad of concrete or clay servicing) (for later removal and safe disposal)
(iii) Waste oil will be collected and stored (in the same way that diesel is stored – see above) in used fuel drums for later safe disposal in approved sites. (iv) Also see Waste Management – above 43
Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 3 of 5 Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors 3. Op erate an d (i) The expected impacts are very The Contractor will prepare a Q uarry and Borrow-pit Operations and Site Resto ration Plan for approval by restore q uarries similar to those shown for the SE - prior to commencement of materials extraction. The Plan will be guided by the following: and borrow pits Construction, above. (i) Potential quarries and borrow pits will be identified in concert with marzpeteran (provincial) and Yerevan officials. (ii) Quarries and borrow pits will be made safe, have their slopes stabilized, be adequately drained and be restored or rehabilitated as soon as possible after extraction has ceased. 4. T ransport (i) Dust and emissions The Co ntractor will prepare a Draft T raffic Man agement Plan fo r consideration b y th e SE a nd affected communities, traffic au thorities an d the p olice b efore fina lization a nd a pproval by the SE -- prior t o materials and (ii) Noise and vibration equipment commencing construction,. The Traffic Management Plan will include: (iii) Traffic and other safety hazards 1. Carefully selected truck routes (iv) Social impact in affected 2. Clear route directions communities 3. Appropriate warning signs 4. Established speed limits and operating times (daylight as much as possible) (v) Damage to rural roads and other 5. Provision and maintenance of temporary access for public and nearby communities roads 6. Controls over the movement of vehicles particularly near communities and schools 7. Use of dust blankets or other means to cover load 8. Provisions to use and using water spray of road surfaces to control dust in and near affected settlements 9. Construction traffic giving way to regular traffic (i) Construction traffic routes will be defined in cooperation with local communities and the police (ii) Vehicles and equipment will be maintained to prevent fuel and oil leaks and to minimize air and noise pollution (iii) Trucks and equipment will be washed in specified areas with suitable runoff protection (as above). (iv) Roads used by construction vehicles will be swept regularly. (v) Vehicle and equipment movements will be restricted to the approved construction zone and the final ROW. (vi) Rural and other roads damaged by construction vehicles and other activities will be repaired or restored. 5. Establish (i) Dust and emissions The Contractor will prepare an Asphalt Plant Site Development and Operating Plan for approval by the SE - operate as phalt (ii) Noise prior to construction of an asphalt plant. The Plan will take the following into account: plants (i) The asphalt plant will be located at least 200m away from and downwind from any settlement and 200m away from (iii) Diesel (used in asphalt) is toxic to any water body or stream and adjacent to other contractor facilities such as, works camps, storage areas and all living organisms – in soil, vehicle and equipment maintenance areas. surface or ground-water. (ii) Electrostatic precipitators will be installed or exhaust gases will be released via a set of water baths (iii) Diesel will be stored under cover on a concrete pad surrounded by an impervious bund enclosing a catch volume at least 50% more than the volume of the diesel stored (see above). (iv) Conveyers and hoppers will be covered (v) Waste asphalt and bitumen will be disposed of at a site approved by marz, city and MNP authorities. (vi) The plant will be operated only in daylight hours when located less than 500m from a settlement.
44
Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 4 of 5 Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors
6. Operat e/ (i) Work force generates significant The Contractor will prepare a Fac ilities Plan (such as, work camps, c oncrete mixing plants, s torage areas manage w ork amounts of domestic and other and vehicle and equipment maintenance areas), for appro val by the SE - prior to establishing facilities. The camps a nd othe r solid waste and sewage with Facilities Plan will take the following into account: facilities (incl. potential to damage water quality (i) Camp locations will be more than 200m from any water body and sited to prevent damage to landscape. store/dispose o f and create nuisance (ii) Domestic solid waste and hazardous waste disposal. (iii) The need for adequate temporary drainage sewage an d so lid (ii) Improper waste disposal creates waste) (iv) Sewage will be disposed of in on-site septic tanks, held in sealed tanks for proper disposal or disposed into health problems and habitat for latrines constructed for the purpose and capped when no longer needed. disease vectors (v) Wastewater will be disposed of in on-site septic tanks, or be treated to meet the standards for domestic (iii) Communities may perceive wastewater discharge and discharged to a pond or natural drainage channel. potential or suffer from actual (vi) Covered rubbish bins for solid waste will be placed at suitable locations where solid waste is generated. social impacts from large male (vii) Solid waste will be separated (clean paper, glass and poly-propylene plastics are understood to be recyclable in workforce. Armenia) and stored for regular collection for recycling or off-site disposal in a municipal waste facility (also see (iv) Site runoff affects the physical Waste Management – above) water quality and aquatic life in (viii) Work camp sites will be restored to the satisfaction of local officials after use and before abandonment. rivers and water bodies, flora, nearby land, and other natural resources 7. Work Site (i) Injuries and death of workers, road (i) Safety and safety promotion will be of the highest priority. Safety users, people in and near work- (ii) Temporary traffic direction signs, markings, traffic signals and lighting will be installed and maintained, clearly sites, quarries and borrow-pits, visible solid barriers will be used to channel traffic, and flagmen will be employed as needed. and possible sickness of workers (iii) Water sprinklers will be used when needed to control dust and other people because of (iv) Work areas will be kept clean and clear of waste and unused material sewage and waste disposal. (v) Waste will be disposed of properly (also see Waste Management) 8. Public (i) Lack of information and The Contractor will prepare a Community Consultation and Communications Plan for a pproval by the SE - Consultation understanding by communities and prior to commencing site preparation and construction activities. The Plan will be guided by the following: affected parties about the planned (i) Procedures for communicating with local residents will be developed in advance of activities, particularly when works activities and the schedule noise, vibration or nuisances may be created and/or where local flooding may be an existing or potential problem. for their implementation can lead (ii) Community members will be provided with direct access to the SE or representative at a nominated location and to frustration and delays in the time (particularly important where some residents may not have telephones). schedule and sometimes can (iii) A process will be developed whereby community members and other stakeholders may make complaints and be contribute to accidents. assured of receiving responses within a reasonable period. A record or Log will be maintained of the type and number of complaints received (name, subject, date, response and date of response). (iv) Regular meetings will be held with community representatives to discuss the project, its impacts, etc. The group should include community leaders and people who are well known in the community and who represent different interests, e.g., business people, teachers, priests, older people and those with special interests. (v) Community leaders and local newspapers will be provided with notices on project progress and anticipated issues. (vi) Clear signs will be posted on and around construction sites to provide information about the project. (vii) Employment opportunities will be maximized for local people by employing them as part of the project labour force, and prefabricating or manufacturing construction items locally when possible, e.g., drainage pipes, culverts and for sand, gravel and stone supply. 45
Environmental Impact Mitigation – Summary Environmental Management Plan (EMP) Page 5 of 5 Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors 9. Ha ndling of (i) Chemicals and Hazardous The Contractor will prepare a Plan f or Handling Chemicals and an Emergency Contingency Response Plan chemical an d materials have the potential to for approval by the SE - prior to commencing construction. The Plan will be guided by the following: hazardous poison people, soil, surface and (i) Procedures will be developed and implemented to ensure safe handling and storage of hazardous substances, materials ground water and may cause e.g., diesel, waste oil, paints. Material safety data sheets, emergency response procedures and clean-up materials death or severe damage to the will be readily available on site. Copies of material data sheets will also be held by the Resident and Senior health of people and all living Engineers. animals and plants. (ii) An Emergency Contingency Response Plan (ECRP) will be in place to handle spills and ensure that clean-up materials are readily available on-site to clean-up spills that may occur. The ECRP will, at a minimum: (a) Identify the positions and persons responsible for emergency response action (e.g., the SE, RE, Works Foremen) (b) Specify the leader of the Emergency Response Team (ERT) and Alternate (c) Include an organizational diagram specifying the positions and responsible persons within the ERT, their work and home phone numbers, and the reporting lines among them. (d) Ensure that clean-up chemicals and materials to absorb and remove spilt substances are available and stored undercover in locked facilities located at works facility sites. (e) Ensure that the responsible persons receive training in emergency response. (iii) Hazard and risk management training will be provided to each Environmental Management Officer (appointed by the Contractor) and all personnel handling chemicals and hazardous substances. (iv) Spilled material will be collected and disposed of in a site approved by MNP. The spilled area will be cleaned in a timely manner to prevent potential contamination of surface and ground water and soil. (v) Only minimal chemicals, hazardous substances and fuel will be stored on-site, within an enclosed and covered secure area that has an impervious floor and impervious bund around it (with capacity at least 150% of the capacity of the largest tank). The storage area will be located away from water-courses and danger areas, e.g., facilities site.
46
47
Required EMP and Operating Plans (as Clauses for Inclusion in Contract) EMP and EMP and Operating Plans Responsibility Annexes to (Clauses to be included in the Contract Document - highlighted) it EMP The Contractor will, prior to co mmencing site preparation and Contractor + SE construction activities, prepare: An En vironmental Ma nagement Pla n (EMP) for approval by the Senior Engineer (SE). The EMP will be guided by Chapters 4 and 5 of this IEE Report, particularly the Summary EMP (Figure 17) and include, as Annexes, the Operating Plans listed below (all to be approved by the SE).
ANNEX A A Waste Man agement Plan to guide the handling of materials for Contractor + SE recycling (glass, plastic and clean paper), domestic waste, sewage, and hazardous waste.
ANNEX B A Quarry and Borrow-pit Operations and Site Restoration Plan Contractor + SE
ANNEX C A Traffic Management Plan Contractor + SE
ANNEX.D An Asphalt Plant Site Development and Operating Plan Contractor + SE
ANNEX.E A Facilities Plan (co vering: work camps, concrete mixing Contractor + SE plants, storage areas and vehicle and equipment maintenance areas)
ANNEX.F A Plan for Handli ng Che micals and Ha zardous Ma terials a nd Contractor + SE an Emergency Contingency Response Plan
ANNEX.G A Community Consultation and Communications Plan Contractor + SE
47
48
Monitoring Program and Responsibilities Parameters to be Monitored Locations for Frequency Responsibility Refer to EMP Monitoring and of for Monitoring Data Sources Monitoring Work Sites: Work sites: Weekly EM Visual inspection Quarterly IES Dust and use of water spray - Runoff control - Drainage maintenance - Work site safety: Work sites: Weekly EM Visual inspection Quarterly IES Signage - Barriers - Site cleanliness - Use of safety equipment - Traffic and Road safety: Work sites: Weekly EM Visual inspection Quarterly IES Signage - - Barriers - - Routes Traffic routes - Material on the road - - Condition of rural roads - - Vehicle and equipment Vehicle Maintenance Quarterly emissions control logs Monthly Incidents and complaints Complaints Log Work camps: Works camps: Weekly EM Visual inspection Quarterly IES Solid waste management - - Sewage management - - Social issues Complaints Log Monthly Site restoration - Monthly Facilities areas: Facilities areas: Weekly EM Visual inspection Quarterly IES Storage of diesel and waste oil - - Material/substance sheets - Monthly Site restoration - Monthly Quarries and borrow pits: Quarries and borrow Weekly EM pits: Quarterly IES Slope management Visual inspection - Runoff management - - Use of safety equipment - - Site restoration - Monthly - Asphalt plants: Asphalt plants: Weekly EM Visual inspection Quarterly IES Diesel storage and use - - management - - Dust emission control
Waste management and Work sites, Works Weekly EM
48
49
Parameters to be Monitored Locations for Frequency Responsibility Refer to EMP Monitoring and of for Monitoring Data Sources Monitoring disposal: camps, waste Quarterly IES disposal sites: Visual inspection Solid waste storage and - - transportation - - Solid waste disposal sites - - Asphalt recycling, re-use and - - disposal - Sewage management and disposal Waste oil disposal Coordination with MNP, marz SE Log Monthly EM and local authorities Checking with MNP Complaints Complaints Log Monthly EM Consultation and Information SE Log. Complaints Quarterly EM sharing with stakeholders and Log. affected land users Consultation meetings Log.
49
50
Annex 3 SUMMARY POVERTY REDUCTION AND SOCIAL STRATEGY
Country/Project Title: Armenia/North–South Road Corridor Investment Program
Lending/Financing Multitranche Financing Department/ Central and West Asia Department/ Modality: Facility Division: Transport and Communications Division
I. POVERTY ANALYSIS AND STRATEGY A. Link to the National Poverty Reduction Strategy and Country Partnership Strategy
The Sustainable Development Program of the Government, which was approved in October 2008, is a long term development strategy. The program is Armenia’s second Poverty Reduction Strategy Paper (PRSP II), which builds on the considerable achievements of PRSP I, and has three key goals covering the period 2009–2021 (with specific medium-term targets for 2009–2015): (i) reducing poverty and eliminating extreme poverty, (ii) ensuring human development, and (iii) deepening economic growth and accelerating the development of lagging regions. According to the Sustainable Development Program, the development and increased efficiency of the transport system is viewed as an important prerequisite for ensuring high growth, increased access to and efficiency of social services, increased labor force mobility, and elimination of regional disparities. That is why the Government made improving the existing regional road network a priority task, and it has developed an investment plan to improve the main road network. Its physical component will upgrade and rehabilitate Armenia's major highways, lifeline road network, and the cross- border infrastructure; the nonphysical component will facilitate implementation of the road sector development plan. The total cost of the Investment Program is estimated at $1.45 billion over the medium term (2010–2020). International financing institutions including the Asian Development Bank (ADB), the World Bank, the Japan International Cooperation Agency, the European Bank for Reconstruction and Development, and other bilateral aid agencies will share these investment costs.
The Agarak–Kapan–Yerevan–Bavra route (M1 and M2 roads) crossing Armenia from south to north is connected to the east–west highway of Georgia that leads to Poti and Batumi on the Black Sea. This route provides Armenia with the shortest access to the seaports linked to the Russian Federation, Europe, and Turkey. Meanwhile in Georgia, the east–west highway is being improved as the Government’s top priority, and Georgia plans to improve the Bavra– Zhdanov–Akhaltskha–Batumi road as an alternative link to Black Sea ports from Tbilisi. This will enable cargoes from Armenia to be transported to Black Sea ports more easily via a shorter route. On this basis, the Government has selected the north–south road corridor to be improved under the Investment Program as a priority, and ADB will support this program through a multitranche financing facility (MFF) of up to $500 million. The Government requested ADB to extend technical assistance for preparing the North–South Road Corridor Investment Program to be financed by a blending of ADB's Asian Development Fund and ordinary capital resources and implemented in phases in line with the priorities that will be identified by the transport sector strategy currently under preparation.
Tranche 1 Project of the Investment Program will (i) reconstruct an 18.4-kilometer (km), four-lane section of the Yerevan–Ashtarak road to international standards, and (ii) facilitate implementation of the road subsector plan under the Transport Sector Strategy.
B. Po verty Analysis Targeting Classification: General intervention 1. Key Issues
The human development Index (computed by the United Nations Development Programme, 2006) for Armenia is 0.777, which gives the country a rank of 83rd out of 179 countries. It is better placed than Georgia (93rd) and Azerbaijan (97rd). The Human Poverty Index-1 value was 4.5 % for Armenia (2006) and, according to it, Armenia ranks 14th among 135 developing countries. The situation with human poverty is better than in the neighboring countries (the value for Georgia was 5.5% and for Azerbaijan 11.8%).
Armenia’s rates for poverty (25.0% of the population) and extreme poverty (3.8%) in 2007 declined from the 2004 rates of 34.6% for poverty and 6.4% for extreme poverty. Poverty has become shallower and less severe as the poverty gap and the severity of poverty have also declined significantly. In 2007, the poverty gap was estimated at 4.9% (down from 7.4% in 2004), while the severity of poverty was estimated at 1.5% (down from 2.4% in 2004). The deficit between the consumption of the poor and the poverty line (expressed as a percentage of the poverty line) fell from 21% in 2004 to 19%. During 2004–2007, income inequality slightly decreased. Inequality measured by the Gini coefficient indicates that the population polarization in Armenia is deeper in income distribution than in consumption.
50
51
In 2007 the consumption inequality measured by the Gini coefficient increased by 0.028 compared with 2004 (0.288 in 2007 compared with 0.260 in 2004), while income inequality decreased by 0.024 (0.371 in 2007 compared with 0.395 in 2004).
Prudent fiscal and monetary policies were instrumental in maintaining macroeconomic stability and contributing to poverty reduction. Real gross domestic product (GDP) grew by 13.1% per year on average during 2003–2007, and inflation averaged 3.9% during the same period. Social expenditures increased to 4.7% of GDP, well above the projected PRSP I goal of 3.0%. Increased resources to the social sectors improved the access to and quality of general secondary education, and led to improvements in the use of and geographic access to basic health services, most notably through the free provision of primary health care to the population.
However, despite the fast poverty reduction (including very poor) in Armenia, the poverty level still significantly varies among marzes (provinces), and between rural and urban areas. This situation is mostly a result of the existing differences of economic development, and the peculiarities of physical, geographical, and infrastructure development of different regions. According to 2005 and 2006 National Statistical Service Household Survey data, the poverty incidence is higher in marzes affected by the earthquake of 1988; in bordering regions; in the regions with unfavorable conditions for agriculture, especially with small share of irrigated agriculture land; and in marzes with a predominantly urban population. The analysis of poverty incidence by gender during 1999–2007 shows that there are no significant gender disparities regarding poverty in the country.
After growing at an average rate of 13.5% in 2006–2007, the Armenian economy moderated with real GDP growth of 6.8% in 2008. It declined by 9.7% in the first 4 months of 2009 and is expected to decelerate by around 9.5% in 2009. Remittances, which at $1.5 billion accounted for 13% of GDP in 2008, are projected to be around 30% less in 2009. The Armenian dram has depreciated by 25% against the US dollar, which is significant as 70% of the economy is dollarized. The Government faces a revenue shortfall of 22% and a financing gap of $460 million. The fiscal deficit is estimated to increase from AMD40 billion (1.0% of GDP), forecast in the original 2009 budget, to 6.5% of GDP. Unemployment has increased and is likely to further rise. According to the National Statistical Service of Armenia, in 2009 unemployment is 6.6% (compared with 8% in 2007 and 6.2% in 2008), though unofficial estimates suggest figures closer to 20%–25%. The poverty and social analysis conducted for Tranche 1 Project will also be conducted for future tranche(s) as required.
2. Design Features
Design features may be incorporated to preserve and enhance local access along the four-lane highway for local produce vendors, such as creation of roadside markets, through local consultation, with full sanitary facilities on wide pull-out lanes. Other possible design features with poverty reduction potential will be explored during the planning and implementation of Tranche 1 Project and following tranches following recommendations in ADB’s Technical Note on Soci al A nalysis for Transport Pr ojects (http://www.adb.org/Documents/Books/Transport-Projects-Social- Analysis/Transport-Social-Analysis.pdf)
II. SOCI AL ANALYSIS AND STRATEGY A. Findings of Social Analysis
The social and poverty impact analysis of tranche 1 and 2 projects indicate that the poverty incidence in two marzes out of five (Ararat 25.5% and Shirak 32.1%) exceeded the national average of 25%. The unemployment rate is high in Shirak (11.8%) and Syunik (11.8%) marzes compared with the national republic average of 6.2%. While the Investment Program aims to facilitate regional trade and benefit major businesses and those involved in trade, it will also significantly benefit rural communities, especially rural poor. This is important taking into consideration that in three marzes (Aragatsotn, Ararat, and Vayots Dzor) the population is predominantly rural. While the incidence of rural poverty declined by 19.7% between 2004 and 2007, the trend is still 1.6 times lower than that in the urban area. In 2007, 25.5% of the rural population was poor compared to 25% of the population of Armenia and 24.7% in the urban area. The Investment Program will increase the mobility of about 1 million people living in six marzes, where the north–south corridor lies. In terms of human poverty modified index of 2005, an unfavorable situation has been recorded in three marzes—Aragatsotn (49.6%), Ararat (8.7%), and Shirak 34.8%, compared with the national average of 32.4%). From the viewpoint of human poverty (as against income poverty), the rural population is most vulnerable. The marz-level analysis of human modified index components shows that the most influential factor of human poverty in Armenia is the lack of access to health care services. According to survey data, about 62% of surveyed households visited health care facilities in case of need. Those who did not visit health care facilities (about 38%) cited high official and nonofficial payments for treatment as reasons for nonattendance.
Almost all marzes, except Ararat, are also in unfavorable situations in terms of social vulnerability index of 2005. In
51
52
Syunik marz the social vulnerability index (37.5%) exceeds the national average (36.6%) and in Shirak it is equal to the national average. This is because some social groups are heavily represented in the composition of marz population (lonely elderly, unemployed, elderly, and poverty family benefits receivers).
The majority of households in the program areas are engaged in agriculture activities or small and medium-size agro- industries (including cottage agro-industries). According to the same socioeconomic survey, 71.4% of household heads are employed, and about 30% of them are mainly occupied in agriculture activity. About 48% of households refer land as the main source of their food production, about 24% of households of which mentioned land as the main source of their income; 50% of surveyed households use the road corridor every day and about 40% use it several times a month. The majority of respondents think that improvement of the road will have a positive social impact. About 57% of the respondents believe that, as a result of the improvements, the road will be safer. More than 30% or respondents think that it will also have a positive economic impact. Hence, 17.9% of respondents think that it will promote trade and 14.3% think that the Investment Program will create short-term job opportunities for the community members during the construction period.
Reduced travel time and more available transport services will help improve the lives of people, especially women, the elderly, and children, as improved road transport under the Investment Program will increase their access to the nearest markets and social service delivery institutions such as schools, hospitals, and clinics, and create job opportunities. The Investment Program will generate estimated 2,500–3,000 jobs during implementation, of which an estimated 45%–50% will be sourced locally in the form of unskilled labor or related services to the construction sites.
Local community members have some concerns about construction waste, disturbance of land, and safety of their family members.
B. Cons ultation and Participation Consultation was carried out with all the stakeholders during the program preparation. Consultations were held at various levels such as the Armenian Roads Directorate (ARD), the Ministry of Transport and Communication (MOTC), the State Committee of Real Estate Cadastre, Municipality of Yerevan, Real World Real People (a nongovernment organization providing HIV/AIDS prevention and education services), and local communities to be directly affected by the Investment Program. The summary poverty reduction and social strategy recommends that (i) consultation on safety, social, and cultural concerns will be continued throughout the implementation of the Investment Program; (ii) men and women are given equal employment opportunities directly, or indirectly, arising from the Investment Program and without any differentiation of wages for equal work; and (iii) mechanisms for maximizing local employment benefits will be included in the bidding documents. These activities will be carried out by the program management unit to be established within ARD, with social and resettlement specialists supported by the supervision consultants. The specialists will organize public information meetings and workshops for stakeholders and affected persons, addressing the safety, social, and cultural issues and, in particular for involuntary resettlement. The land acquisition and resettlement framework (LARF) has been formulated and has been translated into Armenian, which will be distributed to the program regions for review and endorsement. During the different stages of the Investment Program (planning, implementation, and monitoring) following actions will be undertaken: (i) distribution of public information brochures or booklets in Armenian, (ii) placement of copies of land acquisition and resettlement plans (LARP) in Armenian in the marzes and local government offices, and (iii) uploading of the LARPs onto ADB's website. Community authorities and relevant stakeholders will be informed about all aspects of the Investment Program, and their assistance will be solicited. The processes and mechanisms ensuring active involvement of all stakeholders and affected persons will be detailed in the LARPs prepared for all future tranche projects, including the date, list of participants, and minutes of consultation meetings and workshops.
2. What level of consultation and participation (C&P) is envisaged during the project implementation and monitoring? Information sharing Consultation Collaborative decision making Empowerment
3. Was a C&P plan prepared? Yes No
Views and concerns of all stakeholders will be taken into account through consultation meetings and workshops and addressed whenever feasible.
C. Gender and Development 1. Ke y Issues. The Investment Program will have a positive impact on gender equality. The majority of women in the program areas are engaged in agriculture activities or small and medium-sized agro-industries (including cottage agro-industries). Reduced travel time and more available transport services will help improve the lives of women and
52
53 children, as improved road transport under the Investment Program will increase their access to the nearest markets and social service delivery institutions such as schools, hospitals, and clinics, and create employment opportunities. It is anticipated that greater road connectivity will have a positive impact on less-educated girls and women by promoting their access to more education and training opportunities.
2. Key Actions. Measures included in the design to promote gender equality and women’s empowerment—access to and use of relevant services, resources, assets, or opportunities and participation in decision-making process: Gender plan Other actions/measures No action/measure
Tranche 2 and 3 Projects will prepare a component to promote gender equality and women’s empowerment—access to and use of relevant services, resources, assets, or opportunities and participation in decision-making process III. SOCIAL SAFEGUARD ISSUES AND OTHER SOCIAL RISKS
Issue Significant/Limited/ Strategy to Address Issue Plan or Other Measures No Impact Included in Design
Involuntary No impact on Tranche LARF has been prepared for the Full Plan Resettlement 1 Project MFF Short Plan Resettlement LARP is under preparation for Framework Tranche 2 Project No Action
Indigenous Peoples No impact Plan Other Action Indigenous Peoples Framework No Action The Investment Program will Labor generate estimated 2,500–3,000 Employment No impact jobs during implementation, of Plan opportunities which an estimated 45%–50% will Other Action Labor be sourced locally in the form of No Action retrenchment unskilled labor or related services Core labor to the construction sites. standards All civil works will comply with applicable national and international labor, health, and safety laws and standards including (i) employ women, handicapped, and minorities, if any, without discrimination; (ii) prohibit use of child labor and illegal immigrants, and differentiation in wages among male, female, and other social groups for work of equal value; (iii) disseminate information and raise awareness of health risks at project sites, such as proper construction safety standards, prevention of communicable diseases, and sexual harassment; (iv) provide healthy, safe, and secure working conditions as well as adequate medical care; and (v) observe local protocols on acceptable social and professional behavior towards the local population and employees.
53
54
Issue Significant/Limited/ Strategy to Address Issue Plan or Other Measures No Impact Included in Design
Affordability No impact Action No Action Other Ris ks a nd/or Limited It is expected that the project is Vulnerabilities likely to bring in some risks related Plan HIV/AIDS to HIV/AIDS transmission as a Other Action Human trafficking result of improved mobility of the No Action Others(conflict, people and influx of labor at the political instability, time of construction. This aspect etc), please specify will be studied further during the detailed design stage, and mitigation measures will be developed to counter the spread of sexually transmitted diseases in the project area. Information and periodic seminars on HIV/AIDS prevention will be made available through the construction company to people directly and indirectly associated with the project and also to residents in the project area. These outreach activities will be designed by the construction company and submitted to MOTC for approval as part of the health and safety management part of the quality assurance/quality control plan. ADB will review and make specific recommendations if necessary. The responsibility for preparing and implementing such a plan will be an integral part of the construction contract.
IV. MONITORING AND EVALUATION
Are social indicators included in the design and monitoring framework to facilitate monitoring of social development activities and/or social impacts during project implementation? Yes □ No
The Design Monitoring Framework for the MFF and Tranche 1 Project include indicators to measure the number of beneficiaries served by the improved road at the outcome level.
54
Attachment 1
Project Project 2 of the investment program will contribute to socioeconomic Description development in Armenia and expanded regional trade. The outcome will be an efficient, safe, and sustainable north-south road corridor, linking Armenia domestically and internationally. The project output will be an upgraded 41 km section between Ashtarak and Talin. The project's design and monitoring framework is attached in Attachment 2.
Tranche 2 will comprise (a) civil works; and (b) consulting services. Details include: (i) The tranche 2 project will reconstruct and widen the 41.3 km, Ashtarak-Talin Section from 2-lane to 4-lane standard. (ii) A total of 260 person-months of international consulting services and 380 person-months of national consulting services are required for construction supervision and project management for Project 2, and preparation of subsequent tranche projects.
Cost Estimates The total cost including taxes, duties, contingency is approximately the and Financing equivalent of $210 million. Table A1.1 and A1.2 summarize the cost Plan estimates and financing plans, respectively. Attachment 3 outlines the detailed cost estimates and financing plan.
Table A1.1: Cost Estimates ($ million) Item Amount A. Base Cost 1. Land Acquisition and Resettlement 5 2. Civil works 124 3. Consulting Services 7 4. Taxes and Durties 27 Subtotal (A) 163
B. Contingency 37 C. Financing Charges During Construction 10 Total 210
Table A1.2: Financing Plan ($ million)
Source Total Percent Asian Development Bank 170 81 Government 40 19 Total 210 100
Loan Amount To finance part of Tranche 2, the Government has requested a loan of $170 and Terms million from ADB’s ordinary capital resources. The loan will have a 24-year term, including a grace period of 4 years, an annual interest rate determined in accordance with ADB’s London interbank offered rate (LIBOR)-based lending facility, a commitment charge of 0.15% per year, and such other terms and conditions set forth in the loan agreement and the understandings in the FFA. The rest of the cost will be financed by the Government. Attachment 1
Period of Tranche 2 is expected to be physically completed by December 31, 2014. Loan/ No disbursements from the loan account will be requested or made later Utilization than June 30, 2015.
Implementation The Ministry of Transport and Communications (MOTC) will be the Arrangements executing agency and will implement Project 2 in accordance with the principles set forth in Schedule 1 to the FFA and the loan agreement for Project 2. To ensure that ADB-financed projects are implemented on time, within budget, and with high quality, ADB requires that its financed projects be implemented through an outsourced professional firm. Considering that a transition period may be needed for implementing this, the following arrangements as an interim measure will be undertaken under Tranche 2 of the North-South Road Corridor Investment Program.
The North-South Road Corridor Investment Program Project Management Unit State Non-Commercial Organization (PMU) will continue, on behalf of MOTC, project implementation functions including (i) review and approve project progress reports; (ii) review and approve design and bid documents, and present them to MOTC/Governing Council (GC) and ADB; (iii) organize, conduct and evaluate bids and present the evaluation report to MOTC/GC and ADB; (iv) review and approve financial statements and withdrawal applications, and present them to MOTC/GC and ADB; (v) review and approve environmental and resettlement plans (and updates) and monitoring reports and present them to MOTC/GC and ADB; (vi) review and approve quarterly progress reports and present them to MOTC/GC and ADB; (vii) review and approve construction work completion certificates and present them to MOTC/GC and ADB; and (viii) maintain project accounts. ADB loan under Tranche 1 of the Investment Program (“Tranche 1”) will finance the PMU operations until the completion of the Tranche 1. Meanwhile, the construction supervision consultant will undertake the following activities: (i) Design review; (ii) prepare bidding documents and support in bid evaluation; (iii) prepare withdrawal applications for submitting to MOTC and ADB for approval, and support in preparing the financial statements; (iv) monitor environmental and social safeguards implementation; and (v) prepare quarterly progress reports. The supervision consultant will submit all documents to MOTC/GC through PMU for review and approval. The construction supervision consultant will be hired by MOTC (Employer) following ADB Procurement Guidelines. It will report to MOTC and ADB. Thus ADB's no objection for different stages of the recruitment process (longlisting, shortlisting, RFP, evaluation of proposals, contract awards) is required. The PMU, financed under Tranche 1, will continue managing daily project implementation activities as described above. After completion of Tranche 1 project, the PMU operations will be financed by the government.
Procurement The procurement plan (including civil works, goods and services) is attached and Consulting as Attachment 4. Services
Confirmation of The Government of the Republic of Armenia confirms that the Attachment 1
Continuing understandings in the FFA have been adhered, and remain true to date. Validity of and Adherence to A safeguards compliance report is provided below. current Undertakings
Readiness of The detailed design is underway, and the design and bidding documents will the Project for be completed by the end of December 2010. Bidding for civil works will start Implementation by February 2011 for targeted commencement of construction in May 2011.
The project director has been appointed. MOTC staffs involved in the project processing already teamed up with the project director. PMU, funded under Tranche 1, will assist the project director in managing Tranche 2.
Counterpart funding for 2011 has already been included in the government's budget.
Tranche 2 is a priority of the Government. The Government is keen to sign the Loan Agreement by end January 2011 and make the loan effective early 2011.
Safeguards Environment: Project 2 is classified as environmental category A. An environmental impact assessment (EIA) was prepared and posted on the ADB website on 7 August 2010. The EIA concludes that the impact on archaeological, historical, and cultural sites and monuments is widespread and requires special consideration. The EIA identifies 14 previously unknown archaeological/historical sites. To safeguard the most important sites, the EMP in the EIA contains mitigation measures. The EIA also determined that except for one important wetland that requires special protection measures, the impact on the environment – sparse flora and fauna - is relatively benign and can be mitigated through routine design changes and construction measures in the EMP. All recommendations in the EMP will be incorporated in the detailed design and bidding documents for the civil works contract to ensure that proper mitigation and protection measures are taken during project implementation.
Resettlement: Project 2 is classified as involuntary resettlement category A. MOTC prepared a draft land acquisition and resettlement plan (LARP). under Armenian laws and regulations, the Land Acquisition and Resettlement Framework, and ADB's policies, based on the preliminary design. The draft LARP will be finalized once the update of the detailed design is completed. After the finalization of the road alignment, the PMU and supervision consultant will revise the detailed measurement survey, expand the legalization process, and finalize the land acquisition and resettlement cost. The government will amend the decree and conduct the final round of information and consultation. The finalization of the implementation-ready LARP will be a condition to award civil works contracts under Project 2.
Indigenous Peoples: The project is classified as category C, as it has no impact on indigenous peoples. Attachment 1
Status of Safeguard Compliance Involuntary Resettlement and Indigenous People
. No impact on indigenous people. Classified as Category C. . Civil works throughout the whole Project 2 section Ashtarak-Talin (41.3 km) will involve land acquisition and resettlement, affecting 405 land parcels with a total area of 342,997 m2, 314 agricultural land plots with a total area of 214,017 m2, 73 non-agricultural plots (63 residential plots and 10 industrial plots) with a total area of 59,690 m2, and 69,290 m2 of used communal. Project 2 will also affect 269 households with 1,447 persons and 21 buildings/structures. . EA has prepared a draft Land Acquisition and Resettlement Plan (LARP). ADB approved the draft LARP in December 2010. . As described in the Loan Agreement no withdrawals shall be made from the Loan Account for the Works until ADB has received the Government’s certification, in form and substance satisfactory to ADB, that land and rights-of-way required for implementation of Project 2 shall have been obtained free and clear of any liens, rights, claims or any other encumbrance whatsoever. . The Government will not award a contract for Works until after the LARP has been fully implemented in accordance with its terms. The Government will provide sufficient funds to finance all LARP-related compensation and costs. . The PMU and construction supervision consultants will assist EA in implementing the LARP. Environment . Project 2 is classified as environmental category A. . An environmental impact assessment (EIA) was prepared and posted on the ADB website on 7 August 2010. . The EIA concludes that the impact on archaeological, historical, and cultural sites and monuments is widespread and requires special consideration. The EIA identifies 14 previously unknown archaeological/historical sites. To safeguard the most important sites, the EMP in the EIA contains mitigation measures. The EIA also determined that except for one important wetland that requires special protection measures, the impact on the environment – sparse flora and fauna - is relatively benign and can be mitigated through routine design changes and construction measures in the EMP. . The EA will ensure that (i) all roads, and road facilities and structures, under this Project are designed, constructed, and operated in accordance with all applicable laws and regulations of Armenia, ADB’s Safeguard Policy Statement (2009), and environmental impact assessment (EIA); (ii) any adverse environmental impacts are minimized by the mitigating measures and the monitoring program set out in the environmental management plan (EMP) in the EIA; (iii) implementation of the EMP and any violation of the environmental standards are reported to ADB semiannually in accordance with the EIA; and (iv) the EMP is incorporated in the bidding documents and bill of quantities of the civil works contracts. The EA will ensure that the detailed design sufficiently addresses any Government and/or ADB concerns regarding archaeological findings and provide appropriate solutions as well as chance-find procedures during implementation for avoiding and mitigating all impacts. . The Government will not award a contract for Works until the finalized EIA and EMP has been approved by ADB. . EA will monitor implementing EMP by the contractors.
Attachment 2
DESIGN AND MONITORING FRAMEWORK PROJECT 2
Design Summary Performance Data Assumptions and Risks Targets/Indicators Sources/Reporting Mechanisms Impact By 2015 Assumptions Contribution to Increased Armenia exports National economic The government’s socioeconomic to Georgia to $100 million and trade statistics continued commitment to development in from $52.8 million in 2009 economic growth and Armenia and expanded regional cooperation regional trade Increased Armenia imports from Georgia to $80 million Risk from $40.9 million in 2009 Macroeconomic instability in Armenia and the Caucasus sub-region due to the current global fragile economic recovery Outcome By 2015 Assumptions An efficient, safe, and Reduced travel time from Investment Program The government effective sustainable north-south Yerevan to Talin to 1 hour and tranche implementation of the road corridor, linking from 1.33 hours in 2009 completion reports strategy, policy Armenia domestically framework, and road map and internationally Increased daily traffic from National traffic and in the transport sector Ashtarak to Talin to 9,400 road accident statistics vehicles from 5,800 from the government Sufficient external vehicles in 2009 financing for the investment program Increased daily traffic by 10% per annum for 5 years Risk after project completion The government’s limited capacity for effective About 1.6 million people to implementation of the benefit from Project 2 investment program Outputs By December 2014 Assumptions An upgraded road 41.3 km of the 2-lane road Investment Program Timely provision of section between section upgraded to a 4- and tranche progress counterpart funds Ashtarak and Talin lane section with100 km and completion per hour operational reports Effective implementation standard of sustainable routine and Investment Program periodic maintenance by and tranche audit the Ministry Transport reports and Communication
Risk Cost overrun due to sharp escalation of prices of construction materials and labor
Activities with Milestones Inputs 1.1 Advance procurement action undertaken by February 2011 ADB (OCR): $170 1.2 Project supervision consultants recruited by May 2011 million 1.3 Civil works contracts for road improvement awarded by May 2011 Government: $40 1.4 Road improvement works started by June 2011 and completed by million December 2014 1.5 Project 2 completed by June 2015 Total: $2 10 million ADB = Asian development Bank, OCR = ordinary capital resource.
Attachment 3
Detailed Cost Estimates Item Cost Financed By ($ million) ADB Government A. Base Cost 1 Land Acquisition and Resettlement 5.0 0.0 5.0 2Civil orksW 124.0 124.0 0.0 3 Consulting Services for construction Supervision 7.0 7.0 0.0 and Design of Subsequent Tranches 4 Taxes and Duties 27.0 0.0 27.0 Subtotal 163.0 131.0 32.0 B. Contingencies 37.0 29.0 8.0 C. Financing Charges During Construction 10.0 10.0 0.0 Total 210.0 170.0 40.0 Attachment 4
PROCUREMENT PLAN (TRANCHE 2 PROJECT)
Project Name: North–South Road Corridor Multitranche Financing Facility Number: 0035- Investment Program ARM Periodic Financing Request 2 Number: to be assigned Multitranche Financing Facility Amount: $500 Executing Agen cy: Ministry of Transport an d million Communication Tranche 2 Periodic Fina ncing Request Amount: $170.0 million Date of First Procurement Plan: 16 December Date of this Procurement Plan: 16 December 2010 2010
A. Section 1: Process Thresholds, Review, and 18-Month Procurement Plan
1. Project Procurement Thresholds
1. Except as t he Asian Development Bank (ADB) may otherwise agree, the following process thresholds shall apply to procurement of goods and works.
Procurement of Goods and Works Method Thresh old International Competitive Bidding for Works More than $1,000,000 International Competitive Bidding for Goods More than $500,000 National Competitive Bidding for Works Less than $1,000,000 Shopping for Works Less than $100,000 Shopping for Goods Less than $100,000
2. ADB Prior or Post Review
2. Except as ADB may o therwise agree, the following prior- or post-revi ew requirements apply to the various procurement and consultant recruitment methods used for the Project.
Procurement of Goods and Works Procurement Method Prior or Post Comments International Competitive Bidding for Works Prior International Competitive Bidding for Goods Prior National Competitive Bidding for Goods Prior National Competitive Bidding for Works Prior Shopping for Works Prior Shopping for Goods Prior
Recruitment of Consulting Firms Quality- and Cost-Based Selection Prior Other selection methods: QBS, CQS, LCS Prior To be determined during implementation. Recruitment of Individual Consultants Individual Consultants Prior CQS = consultant's qualification selection, LCS = least cost selection, QBS = quality-based selection,
Attachment 4
3. Goods and Works Contracts Estimated to Cost More than $1 Million
3. The following table lists goods and works contracts for which procure ment activit y is either ongoing or expected to commence within the next 18 months.
Contract Prequalification General Value Procurement of Bidders Advertisement Description ($ million) Method (Yes/No) Date (quarter/year) Comments Civil Works 124.0 ICB No Q1 2011 ICB = international competitive bidding, Q = quarter.
4. Consulting Services Contracts Estimated to Cost More than $100,000
4. The following table lists consult ing services contracts for which procurement activity is either ongoing or expected to commence within the next 18 months.
Contract Advertise- International Value Recruitment ment Date or National General Description ($ million) Method (quarter/year) Assignment Comments Construction 6.8 QCBS Q1 2011 International Quality–cost Supervision, Project ratio 80/20 Management and Design of subsequent Tranches CQS = consultant's qualification selection, QCBS = quality- and cost-based selection, Q = quarter.
B. Section 2: Project Procurement Plan
1. Indicative List of Packages Required Under the Project
5. The followin g table pro vides an in dicative list of all procurement (goods, works, and consulting services) over the life of the project.
Estimated Value Estimated Domestic ($ million, Number of Procurement Preference General Description cumulative) Contracts Method Applicable Comments Works Civil works contract 124.0 1 ICB No package for Two-envelope improvement of 41.3 km single stage with Ashtarak-Talin road post qualification section Consulting Services Construction 6.8 1 QCBS with FTP quality– Supervision, Project cost ratio Management and Design 80/20 of subsequent Tranches External Financial Audit 0.2 1 LCS Yes
CQS = consultant's qualification selection, FTP = full technical proposal, ICB = international competitive bidding, LCS = least-cost selection, QCBS = quality- and cost-based selection.
Attachment 4
C. National Competitive Bidding
1. General
7. The procedures to be followed for national competitive bidding shall be the open tender method (including the two-stage where appropriate) set forth in the Law on Procurements of 1 January 2005 with the clarifications and modifi cations described in the following paragraphs required for compliance with the provisions of ADB’s Procurement Guidelines (2007, as amended from time to time).
2. Eligibility
8. The eligibilit y of bidders shall be as defined under section I of ADB’s Procurement Guidelines; accordingly, no bidd er or potential b idder should be declare d ineligible for reasons other than t hose provided in sect ion I of ADB’s Procurement Guidelin es. Bidders must b e nationals of me mber countries of ADB, and offered goods, services, and works must be produced in and supplied from member countries of ADB.
3. Prequalification
9. Post qualification shall be used, un less prequa lification is e xplicitly pro vided for in the loan agreement and/or procureme nt plan. Domestic and foreign contractors shall be allowed to participate in bid exerc ises using post qualification procedure. In case prequalification of contractors is st ipulated in the loan agree ment/procurement plan, domestic and foreig n contractors shall be allowed to participate in the prequalification exercise.
4. Registration and Licensing
(i) Bidding shall not be restricted to pre-registered/licensed firms.
(ii) Where registration or licensing is required, bidders (a) shall be allowed a reasonable time to complete the re gistration or licensing process; and (b) shall not be denied registr ation and/o r licensing for reasons unrelate d to their capability and resources to successfully perform the contract, which shall be verified through post qualification.
(iii) Foreign bidders shall not be precluded from bidding. If a registration or licensing process is r equired, a f oreign bidder declared the lowest evaluated bidder shall be given a reasonable opportunity to register or to obtain a license.
5. Biddi ng Period
10. The minimum bidding period is 28 days prior to the deadline for the submission of bids.
6. Bidding Documents
11. Procuring e ntities should use standard biddin g documents for the p rocurement of goods, works, and services acceptable to ADB.
7. Prefere nces Attachment 4
12. No dome stic p reference sha ll be given f or do mestic bi dders an d for do mestically manufactured goods.
8. Advert ising
13. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper or freely accessible, nationally known website allowing a minimum of 28 days for the pr eparation and su bmission of bids. B idding of na tional competitive bidd ing contracts estimated a t $50 0,000 equivalent or more fo r good s an d rela ted services or $ 1,000,000 equivalent or more for civil works shall be advertised on ADB’s website via the posting of the procurement plan.
9. Secur ities (i) Bid security (tender security). W here required, bid security shall be in the form of a bank guarantee from a reputable bank. (ii) Performance security (c ontract execution security). Performance security sh all be provided within 28 days of the notification of contract award.
10. Bid Opening and Bid Evaluation
(i) Bids shall be opened in public.
(ii) No bid shall be declared invalid/rejected at the time of bid opening.
(iii) Minutes and/or record of bid opening shall be provided to all bidders.
(iv) Evaluation of bids shall be made in strict adher ence with the criteria d eclared in the biddi ng documents and cont racts shall be awarded to t he lowest e valuated bidder.
(v) Bidders sha ll not be eliminated from detailed evaluation on the basis of minor, non-substantial deviations.
(vi) No bidder s hall be rejected on the basis of a comparison with the e mployer's estimate and budget ceiling without ADB’s prior concurrence.
(vii) A contract shall be awa rded to the technically responsive b idder that of fers the lowest evaluated price and meets the qualifying requirements. Negotiations shall not be permitted.
(viii) Price verification shall not be applied.
11. Rejection of All Bids and Rebidding
14. Bids shall n ot be reject ed and new bids solicited without ADB’s prior concurrence. Bids shall not be declared in valid because of proce dural delays on the part of executing agencies without ADB’s prior approval.
12. Participation by Government-Owned Enterprises
Attachment 4
15. Government-owned enterprises in Armenia shall be eligible to participate as bidders only if they can establish that they are legally and financially autonomous, operate under commercial law, and are not a depe ndent agency of t he contracting authority/executing agency/implementing agency. Furthermore, they will be subject t o the same bid and performance security requirements as other bidders.
13. Right to Inspect/Audit
16. A provision shall be included in all national competitive bidding works and goods contracts fin anced by ADB requiring suppliers and contractors to permit ADB to inspect their accounts and records and other documents relating to the bid submission and the performance of the contract, and to have them audited by auditors appointed by ADB.
14. Fraud and Corruption
(i) The Borrower shall reje ct a propo sal for award if it determines that th e bidder recommended for award has, dire ctly or through an agent, engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the co ntract in question.
(ii) ADB will declare a firm or individual ineligib le, either indefinitely or for a stated period, to be awarded a contract financed by ADB, if it at any time determines that the firm or individu al has, directly or throu gh an agent, engaged in corrupt, fraudulent, collusive, or coercive pr actices in competing for, or in executing, an ADB-financed contract.
15. Joint Venture and Estimated Contract Prices
(i) Joint venture partners shall be jointly and severally liable for their obligations.
(ii) Estimated contract prices shall not be advertised.
16. Disclosure of Decision on Contract Awards
17. At the same time that n otification on award of contract is given to the s uccessful bidder, the results of bid evaluation shall be publishe d in a local newspaper, or a well-known freely accessible website identifying the bid and lot numbers and providing information on (i) the name of each bidder who submitted a bid; (ii) bid pr ices as read out at bid o pening; (iii) the names of bidders whose bids were rejected a nd the reasons for their rejection; a nd (iv) the n ame of the winning bidder, and the price it offered, as well as duration and summary scope of the contract awarded. The executing showing separately net cost, contingencies, and taxes agency/implementing agency/contracting aut hority shall respond in writing t o unsucce ssful bidder s who seek explanations on the grounds on which their bids are not selected. Appendix 2
PROCUREMENT PLAN TRANCHE 2 PROJECT
Project Name: North–South Road Corridor Multitranche Financing Facility Number: 0035- Investment Program ARM Periodic Financing Request 2 Number: L2729- ARM Multitranche Financing Facility Amount: $500 Executing Agency: Ministry of Transport and million Communication Tranche 2 Periodic Financing Request Amount: $170.0 million Date of First Procurement Plan: 1 December Date of this Procurement Plan: 29 September 2010 2011
A. Section 1: Process Thresholds, Review, and 18-Month Procurement Plan
1. Project Procurement Thresholds
1. Except as the Asian Development Bank (ADB) may otherwise agree, the following process thresholds shall apply to procurement of goods and works.
Procurement of Goods and Works Method Threshold International Competitive Bidding for Works More than $1,000,000 International Competitive Bidding for Goods More than $500,000 National Competitive Bidding for Works Less than $1,000,000 Shopping for Works Less than $100,000 Shopping for Goods Less than $100,000
2. ADB Prior or Post Review
2. Except as ADB may otherwise agree, the following prior- or post-review requirements apply to the various procurement and consultant recruitment methods used for the Project.
Procurement of Goods and Works Procurement Method Prior or Post Comments International Competitive Bidding for Works Prior International Competitive Bidding for Goods Prior National Competitive Bidding for Goods Prior National Competitive Bidding for Works Prior Shopping for Works Prior Shopping for Goods Prior
Recruitment of Consulting Firms Quality- and Cost-Based Selection Prior Other selection methods: QBS, CQS, LCS Prior To be determined during implementation. Recruitment of Individual Consultants Individual Consultants Prior CQS = consultant's qualification selection, LCS = least cost selection, QBS = quality-based selection,
3. Goods and Works Contracts Estimated to Cost More than $1 Million
3. The following table lists goods and works contracts for which procurement activity is either ongoing or expected to commence within the next 18 months.
Contract Prequalification General Value Procurement of Bidders Advertisement Description ($ million) Method (Yes/No) Date (quarter/year) Comments Civil Works 124.0 ICB No Q3 2011 ICB = international competitive bidding, Q = quarter.
4. Consulting Services Contracts Estimated to Cost More than $100,000
4. The following table lists consulting services contracts for which procurement activity is either ongoing or expected to commence within the next 18 months.
Contract Advertise- International Value Recruitment ment Date or National General Description ($ million) Method (quarter/year) Assignment Comments Construction 6.1 QCBS Q2 2011 International Quality–cost Supervision ratio 90/10 andProject Management QCBS = quality- and cost-based selection, Q = quarter.
B. Section 2: Project Procurement Plan
1. Indicative List of Packages Required Under the Project
5. The following table provides an indicative list of all procurement (goods, works, and consulting services) over the life of the project.
Estimated Value Estimated Domestic ($ million, Number of Procurement Preference General Description cumulative) Contracts Method Applicable Comments Works Civil works contract 124.0 1 ICB No package for Single-stage- improvement of 41.3 km one-envelope Ashtarak-Talin road without pre section qualification Consulting Services Construction Supervision 6.1 1 QCBS with FTP quality– and Project Management cost ratio 90/10 External Financial Audit 0.2 1 LCS Yes
FTP = full technical proposal, ICB = international competitive bidding, LCS = least-cost selection, QCBS = quality- and cost-based selection.
C. National Competitive Bidding 1. General
6. The procedures to be followed for national competitive bidding shall be the open tender method (including the two-stage where appropriate) set forth in the Law on Procurements of 1 January 2005 with the clarifications and modifications described in the following paragraphs required for compliance with the provisions of ADB’s Procurement Guidelines (2010, as amended from time to time).
2. Eligibility
7. The eligibility of bidders shall be as defined under section I of ADB’s Procurement Guidelines; accordingly, no bidder or potential bidder should be declared ineligible for reasons other than those provided in section I of ADB’s Procurement Guidelines. Bidders must be nationals of member countries of ADB, and offered goods, services, and works must be produced in and supplied from member countries of ADB.
3. Prequalification
8. Post qualification shall be used, unless prequalification is explicitly provided for in the loan agreement and/or procurement plan. Domestic and foreign contractors shall be allowed to participate in bid exercises using post qualification procedure. In case prequalification of contractors is stipulated in the loan agreement/procurement plan, domestic and foreign contractors shall be allowed to participate in the prequalification exercise.
4. Registration and Licensing
(i) Bidding shall not be restricted to pre-registered/licensed firms.
(ii) Where registration or licensing is required, bidders (a) shall be allowed a reasonable time to complete the registration or licensing process; and (b) shall not be denied registration and/or licensing for reasons unrelated to their capability and resources to successfully perform the contract, which shall be verified through post qualification.
(iii) Foreign bidders shall not be precluded from bidding. If a registration or licensing process is required, a foreign bidder declared the lowest evaluated bidder shall be given a reasonable opportunity to register or to obtain a license.
5. Bidding Period 9. The minimum bidding period is 28 days prior to the deadline for the submission of bids.
6. Bidding Documents 10. Procuring entities should use standard bidding documents for the procurement of goods, works, and services acceptable to ADB.
7. Preferences 11. No domestic preference shall be given for domestic bidders and for domestically manufactured goods.
8. Advertising
12. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper or freely accessible, nationally known website allowing a minimum of 28 days for the preparation and submission of bids. Bidding of national competitive bidding contracts estimated at $500,000 equivalent or more for goods and related services or $1,000,000 equivalent or more for civil works shall be advertised on ADB’s website via the posting of the procurement plan.
9. Securities (i) Bid security (tender security). Where required, bid security shall be in the form of a bank guarantee from a reputable bank. (ii) Performance security (contract execution security). Performance security shall be provided within 28 days of the notification of contract award.
10. Bid Opening and Bid Evaluation
(i) Bids shall be opened in public.
(ii) No bid shall be declared invalid/rejected at the time of bid opening.
(iii) Minutes and/or record of bid opening shall be provided to all bidders.
(iv) Evaluation of bids shall be made in strict adherence with the criteria declared in the bidding documents and contracts shall be awarded to the lowest evaluated bidder.
(v) Bidders shall not be eliminated from detailed evaluation on the basis of minor, non-substantial deviations.
(vi) No bidder shall be rejected on the basis of a comparison with the employer's estimate and budget ceiling without ADB’s prior concurrence.
(vii) A contract shall be awarded to the technically responsive bidder that offers the lowest evaluated price and meets the qualifying requirements. Negotiations shall not be permitted.
(viii) Price verification shall not be applied.
11. Rejection of All Bids and Rebidding
13. Bids shall not be rejected and new bids solicited without ADB’s prior concurrence. Bids shall not be declared invalid because of procedural delays on the part of executing agencies without ADB’s prior approval.
12. Participation by Government-Owned Enterprises
14. Government-owned enterprises in Armenia shall be eligible to participate as bidders only if they can establish that they are legally and financially autonomous, operate under commercial law, and are not a dependent agency of the contracting authority/executing agency/implementing agency. Furthermore, they will be subject to the same bid and performance security requirements as other bidders.
13. Right to Inspect/Audit
15. A provision shall be included in all national competitive bidding works and goods contracts financed by ADB requiring suppliers and contractors to permit ADB to inspect their accounts and records and other documents relating to the bid submission and the performance of the contract, and to have them audited by auditors appointed by ADB.
14. Fraud and Corruption
(i) The Borrower shall reject a proposal for award if it determines that the bidder recommended for award has, directly or through an agent, engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the contract in question.
(ii) ADB will declare a firm or individual ineligible, either indefinitely or for a stated period, to be awarded a contract financed by ADB, if it at any time determines that the firm or individual has, directly or through an agent, engaged in corrupt, fraudulent, collusive, or coercive practices in competing for, or in executing, an ADB-financed contract.
15. Joint Venture and Estimated Contract Prices
(i) Joint venture partners shall be jointly and severally liable for their obligations.
(ii) Estimated contract prices shall not be advertised.
16. Disclosure of Decision on Contract Awards
16. At the same time that notification on award of contract is given to the successful bidder, the results of bid evaluation shall be published in a local newspaper, or a well-known freely accessible website identifying the bid and lot numbers and providing information on (i) the name of each bidder who submitted a bid; (ii) bid prices as read out at bid opening; (iii) the names of bidders whose bids were rejected and the reasons for their rejection; and (iv) the name of the winning bidder, and the price it offered, as well as duration and summary scope of the contract awarded. The executing showing separately net cost, contingencies, and taxes agency/implementing agency/contracting authority shall respond in writing to unsuccessful bidders who seek explanations on the grounds on which their bids are not selected.
D. Review of Contract Modifications
17. ADB will review contract modifications in accordance with the procedures set forth in the loan agreement between the Borrower and ADB.
Appendix 4
TERMS OF REFERENCE FOR CONSULTING SERVICES FOR DETAILED DESIGN OF TRANCHE 1 PROJECT
Project No. 42145
MFF NORTH-SOUTH ROAD CORRIDOR DEVELOPMENT PROGRAM
A. Background and Objective
1. The Government of Armenia (the Government) requested Asian Development Bank (ADB) to finance the consulting services for detailed engineering design of Tranche 1 Project under the Multitranche Financing Facility (MFF) for the North–South Road Corridor Development Program (the Program). The objective of the consulting services is to prepare a detailed engineering design for the Tranche 1 Project (the Project) under the Program.
B. Scope of Consulting Services
2. The Tranche 1 Project consists of two road sections, including: (i) reconstruction of pavement, drainage, and shoulders; road safety improvements; and repairs to existing structures on Yerevan–Ashtarak Road (km 11.8–30.2) (ii) road safety improvement on Yerevan–Ararat Road (km 9.6–47.2)
3. The detailed engineering design will produce (i) detailed working drawings for the construction, (ii) detailed engineering design report, (iii) detailed bill of quantities (BOQ), (iv) construction specifications and (v) schedules showing location, types and quantities of specific works to be undertaken.
4. To prepare detailed engineering design, the services of national design consulting firm (the Designer) will be required as detailed in Section C below. The Designer should have extensive experience in highway design and construction specifications. The selection procedure will follow consultants' qualification selection criteria (CQS) as per ADB's Guidelines on the Use of Consultants (2007 as amended from time to time). It is anticipated that the detailed design will be prepared within 3 months and the Designer's team will have expertise as set out below, or alternative arrangements may be proposed by the Designer, which, in the opinion of the Project Management Unit (PMU) established for Program implementation and ADB, will provide services of an equivalent quality.
Team Members: about 20 person-months technical staff (i) Highway Engineer – Team Leader – (3 months) (ii) Highway Engineer – Design – (2x2 months) (iii) Pavement/Materials Engineer – (3 months) (iv) Soil/Geotechnical Engineer – (2 months) (v) Bridge/Structural Engineer – (2x3 months) (vi) Hydraulics and Drainage Engineer – (1 months) (vii) Road Safety Specialist – (1 months) (viii) Electrical/Street lighting Specialist – (2 months)
5. To support the Designer, the services of an individual international pavement specialist will be procured under a separate contract. For reference purpose the suggested ToR is included in para 20 below.
2
C. The Terms of Reference for the Designer
1. General Guidance
6. The Designer shall make maximum use of available data, topographic, geological and seismic maps, road condition surveys, technical studies and documents available from the PMU and other Armenian government agencies, as well as data from any other studies conducted recently. Notwithstanding any reliance on existing information or analyses or studies, the Designer shall be solely responsible for the results of the design.
7. The geometric design shall follow close to the existing road alignment without necessitating land acquisition. Key design criteria shall satisfy minimum requirements of European Union Agreement on Traffic Arteries1, as well as below standards in use in Armenia.
Table 1. Geometric Design Standard for Project Road
No. Main Parameter Unit Flat Rolling Mountainous 1 Design speed Km/h 120 100 80 2 Number of lanes 4/2 4/2 4/2 3 Land Width m 3.75 3.75 3.75 4 Shoulder width m 3.0 3.0 3.0 5 Maximum longitudinal gradient % 4 5 6 6 Median to be applied over 4-lane m 2 2 2 7 Minimum horizontal curvature m 670 425 250 8 Super elevation at minimum horizontal % 6 6 6 curvature 9 Minimum radius of vertical curves: crest M 12,500 8,000 5,000 10 Minimum radius of vertical curves: sag m 6,000 4,500 1,500 11 Cross fall of carriageway % 2 2 2 12 Cross fall of shoulder % 4 4 4
8. The design shall be prepared with the consideration that the two lanes of one direction of the dual carriageway will be closed entirely for ease of construction.
2. Specific Tasks
9. The Designer will conduct field surveys, investigations and relevant laboratory tests for the detailed engineering design that will include, but not be limited to the following: (i) The Consultant shall carry out full topographic survey of the road over a width of 40m to either side from the median centerline. The topographic surveys shall provide information on utilities, trees, boundary fences and entrances to roadside properties, watercourses and any other feature that would affect the design of road rehabilitation or new construction. (ii) The Consultant shall prepare a digital terrain model of the completed ground survey suitable for preparing Computer Aided Design and Drawing (CADD) plan and profile drawings at a scale of 1:1,000 to a sufficient width to include the edges of the right-of-way (ROW) and the intercept between any cut or
1 United Nations. 1975. European Agreement on Main International Traffic Arteries (AGR). Washington, DC.
3
embankment slope and the adjacent ground. In unstable and potentially unstable areas, the cross-sections will cover as much of the slope area as is practical;
10. Under the guidance of the International Pavement Specialist, the Designer will carry out geotechnical, pavement and materials surveys and tests including: (i) representative sampling and testing of existing asphalt concrete pavement; (ii) soil sampling and testing at appropriate intervals, as necessary for road rehabilitation design; - in-situ density test within the layers underlaying the existing asphalt and 10cm below the level of the established existing sub-grade - DCP-test to a nominal depth of 1.5m at an interval of 200m for establishing the layer configuration - CBR test on subgrade material - testing procedures established in Armenia for determining the bearing capacity of the subgrade - identifying and sampling and testing of materials from quarries and borrow sites - any other geo-technical and soils investigations and testing necessary for final design
11. The Designer shall undertake a detailed inspection and dimensioning of existing bridges, culverts, retaining walls, river training and other structures, including non-destructive concrete testing of bridges and other major structures.
12. The Designer shall investigate the hydraulic and drainage efficiency of existing bridges, culverts and road side drainage facilities; shall examine scour, erosion, drainage and flood characteristics along the road;
13. The detailed design activities shall include, but not be limited to, the following: (i) geometric design based on the detailed survey results, approved geometric design standards (para 7 above), and re-establishing the layout and design of existing intersections/interchanges; (ii) preparation of plan, profile and cross-section drawings to scales shown in para 17; (iii) optimization of vertical/road profile of the road based on the pavement design that will reflect the new pavement structure, raising of embankment for drainage purposes in low lying areas, and minor geometric improvements for safety reasons; (iv) where appropriate, material used for embankment construction on top of the existing subgrade shall be locally extracted suitable material excavated from road cuts, with characteristics and strength modulus equal to/or better than the existing sub-grade materials; (v) detailed drainage design of culverts, side and cross-drainage; (vi) based on the analysis and pavement design provided by the individual international consultant, design the finished vertical/road profile; (vii) design of remedial works to existing bridges and other structures including all repairs necessary to render them safe and capable of supporting projected heavy loads; (viii) arrangements and/or design for relocation of affected public utilities along the road corridor;
4
(ix) other ancillary items such as road safety measures (road signs, pavement markings, safety barriers and delineators, lighting), access design, entrances to roadside properties, bus bays and bus shelters, pedestrian crossings, lay-bys and/or emergency stop areas, measures to reduce the effects of wind-blown snow on the road during the long winter periods (such as snow fences, if practical and economically justifiable) and other items; (x) incorporate all requirements from the Initial Environmental Examination and the Environmental Management Plan prepared for the Project;
14. The Designer is required to design a road safety component for the Yerevan–Ararat road that will include but not be limited to: (i) replacement and/or improvement of road signs to conform with the requirements of the international agreements (footnote 1) and standards in terms of type, layout and quality of materials used; (ii) inclusion in the design of lay-bys for seasonal vendors and emergency stops; (iii) design of road lighting in built-up areas and, if warranted, at interchanges (iv) investigate, and if feasible, make provision for replacing the central grassed reserve with a “New-Jersey” type barrier.
15. All works shall be designed in such a way that they will be located and executed within the existing ROW or unutilized government land.
16. The Designer shall prepare drawings, detailed technical specifications based on the Specifications prepared under the project performance monitoring system (PPMS), quantity and cost estimates and design reports as required for the proper execution of the Project. The technical specifications shall be based on standards applicable in Armenia for similar civil construction works, if required, amended by up-to-date standards having international applicability (such as American Associations Highway Transportation Officials [AASHTO}, British Standards [BS} or other comparable standards), all in considerations of the climatic conditions in Armenia, including specifications for materials to be used, workmanship, method of construction, quality of finished works, equipment and plant requirements, and include provisions for environment, social and road safety mitigation measures to be implemented by the civil works contractors.
17. The Designer shall obtain endorsement of the PMU for the standards to be used. The technical specifications shall include lists and descriptions of work (pay) items to be executed. (i) Quantity and cost estimates - The Designer shall prepare bills of quantities based on the various items of work to be executed in accordance with the drawings and the technical specifications. The items in the BOQ quantities shall correspond to the work (pay) items specified in the technical specifications; (ii) The Designer shall develop a Confidential Unit Price Analysis for each work item and a Confidential Cost Estimate, for each work item, work category and contract package as a whole. Unit prices shall be classified into direct costs (labor, materials and equipment), indirect costs (mobilization, on-site and general overheads, contractor’s contingencies and profit) and taxes. The Designer’s Confidential Cost Estimate shall break out separately all taxes and contingencies for ease of identification. (iii) Design Report and other documents - The Designer shall submit a Design Report providing a description of the Project, including selection of design standards, field surveys and investigations, geometric design, pavement design, geo-
5
technical design, drainage design, structure rehabilitation design, specifications, bid documents, quantity estimates, and various calculations. (iv) The Designer shall also submit a soils and materials report, including proposed location and characteristics of sources of borrow materials.
18. The Designer will prepare full set of bidding documents following ADB's Procurement Guideline and Standard B idding D ocuments f or Works – Large C ontracts and include in the Final Design and Bid Documents Report submission. The final design drawings shall include the following: location plan and vicinity map; road plan and profile drawings at scales of 1:1,000 horizontal and 1:100 vertical; roadside drainage plans and profiles, and drawings for subsurface drainage and pollution control measures; road cross-sections at 20 m intervals (or more frequently when necessary) at scale 1:50, arranged on A3-size sheets with frame and title block in digital format only (pdf- format for bidding purpose and dxf-format for construction purpose); typical road sections and details; bridge rehabilitation drawings (these drawings shall also show the extent of the works to be done at the bridge; detailed drawings of the works at appropriate scales shall also be provided); drainage drawings and details; standard drawings for junctions and property entrances; standard drawings for bus bays and bus shelters; local plan drawings and standard drawings for pavement markings, signs, safety barriers and other road features; quantity schedules; right-of-way delineation, if any; utility relocation drawings and/or arrangements, if any; other miscellaneous drawings; and tables showing the works quantities and the places where these works be implemented
19. The Designer is responsible for the quality of the surveys and designs in conformance with accepted standards and norms
20. For information purpose the ToR for the international Pavement Specialist are reproduced below: The international pavement specialist will (i) undertake a comparative analysis of asphalt concrete and cement concrete pavements to arrive at the best alternative; (ii) provide the Designer with detailed pavement calculations and design for the preferred pavement alternative; (iii) prepare detailed construction specifications for the preferred pavement alternative; and (iv) help the Designer to prepare bidding documents. In particular, the international pavement specialist will perform the following tasks:
(i) based on the traffic analysis and forecasts carried out under the TA 7208-ARM Preparing North–South Road Corridor Development Program, prepare forecast of Equivalent Standard Axle Loads (ESAL) over the pavement design life; (ii) prepare alternative analysis of asphalt and cement concrete pavements based on state-of-the-art construction standards and equipment application, the
6
availability of domestic materials, durability of the pavement, ease of maintenance, environmental concerns (comparing emissions produced for production of materials and construction); risks associated with construction such as expertise and quality control, construction cost and projected total cost of the pavement throughout its design life; (iii) recommend preferred alternative and seek the approval of the PMU and ADB; (iv) calculate pavement thicknesses for the preferred pavement alternative considering the composition and strength of existing pavement and sub-grade, forecast ESAL loads, and the use of natural or processed construction materials that are readily available, and provide it to the Designer for incorporating in the final road profile; (v) prepare construction specifications for each pavement layer including requirements for the materials, quality controls, construction technology and equipment; measurement and payment etc.; (vi) prepare detailed BOQ and Confidential Cost Estimates for the pavement materials; (vii) recommend maintenance strategies and prepare detailed maintenance manual specifying diagnostics and maintenance strategies, planning methodology, frequency, preventive measures, and recommended budget level;
D. Implementation Arrangements
21. PMU will act as an Employer for the contract with the consultants as well as will supervise and provide day-to-day guidance to the consultants and coordinate for securing necessary approvals from the Government, the Project Governing Council and ADB. The consultants will meet with PMU, its personnel (including project officers and environmental and social specialists), and other stakeholders to incorporate the concerns and recommendations in the final design. In the initial stage the Contract will be signed with the Foreign Financing Projects Management Center of the Ministry of Finance which will pass the obligations of the Employer under the contract to the PMU as soon as the PMU is properly set up and is legally operated.
22. From the date of the signature of the contract, the consultants shall have two weeks to mobilize the services. The tentative schedule is shown below, to be adjusted to the actual mobilization date at the time of contract signing:
- Consultant's contract signing 1 December 2009 - Draft final design completion 15 February 2010 - Final design completion 1 March 2010 - Bidding documents submission 1 March 2010
E. Reporting Requirements
23. The Designer, in coordination with the International Pavement Specialist, will prepare the following reports: (i) Inception Report within 3 weeks of mobilization of the Designer's contract; (ii) draft final design and bidding documents within 9 weeks; (iii) final design and bidding documents within two weeks after receiving comments from the PMU and ADB.
24. The Inception Report shall describe the planning the consultants has established for the assignment, the staffing and remarks as deemed appropriate. This report shall update the methodology and program of work that was included in the Consultant’s proposal and used as a
7 basis for agreed pricing, noting the changes and detailing any difficulties encountered, together with a proposal on how they may be overcome. The Inception Report shall include at least the following: (i) methodology statement defining the proposed limits of the design, including (a) an accurate estimation of the time they will take to complete; (b) methods and parameters; (c) any changes to the composition of the Consultant’s team and specialists needed; (d) agencies and government departments which would need to be involved; and (e) methods of consultation with the local authorities and population; (ii) detailed program of work, including field surveys and final design, showing time, duration and personnel as well as the inter-relationship between activities;
25. The Draft Final Report shall contain draft design and bid documents including (i) draft Design Report; (ii) plan and profile drawings; (iii) typical pavement and road cross-sections; (iv) typical drawings for road structures; (v) typical drawings for other ancillary works; (vi) BOQ and technical specifications; (vii) confidential cost estimates; and (viii) draft pavement design and maintenance report.
26. Final Design and Bidding Documents shall contain all detailed drawings and all supporting information and documents, including reports on selection of design standards, field survey, investigation and test reports and other aspects of the design.
27. The consultants will also produce short monthly progress reports on the ongoing and planned activities of the study team, as requested by PMU and ADB.
28. The Designer will be required to obtain all local approval for the designs from the “Independent Technical Review”, traffic police and other agencies as required under the Armenian regulations and bear the cost of such approvals.
29. Format of Reporting (i) Data shall be submitted to the PMU separately in electronic form, whose precise form shall be agreed between PMU and the consultants; (ii) The reconnaissance survey Report, should be submitted by the consultants to PMU in electronic file (MS Word) and three hard copies in Armenian and three hard copies in English; (iii) All milestone reports shall be submitted in six hard copies to PMU in both English and Armenian languages and one full set in soft copy on Data CD in English and Armenian languages.
F. Facilities and Offices
The Government will provide all necessary documentation, including the reports of the TA 7208- ARM, and other relevant documents to the consultants free of charge.
30. The Designer will use its own office space, equipment, materials, transport, senior and junior, skilled and unskilled personnel for completing the services within the required time. The Designer will also provide office accommodation to the international pavement specialist and related survey materials free of charge.
8
G. Qualification requirements
For the fulfillment of this assignment the Consultant will be required to have:
- extensive experience in highway design and construction specifications and all required licenses; - key staff of Consultant shall have at least 3 years of experience in highway design and construction specifications.
9
TERMS OF REFERENCE FOR CONSULTING SERVICES
FOR CONSTRUCTION SUPERVISION (TRANCHE 1) AND PREPARATION OF TRANCHE 2 AND 3 PROJECTS
LOAN 2561-ARM NORTH-SOUTH ROAD CORRIDOR INVESTMENT PROGRAM
A. Background and Objective
1. The Government of Armenia (the Government) requested Asian Development Bank (ADB) to finance the consulting services for construction supervision of Tranche 1 Project (Project 1) and preparation of Tranche 2 (Project 2) and Tranche 3 (Project 3) under the Multitranche Financing Facility (MFF) for the North–South Road Corridor Investment Program (the Program). The objective of the consulting services is to (i) supervise construction activities for Project 1; (ii) monitor project performance of Project 1; and (iii) prepare Detailed Design, Bidding Documents, final Land Acquisition and Resettlement Plan (LARP), final EIA and EMP, and all other due diligence documents, as required, for Projects 2 and 3 of the MFF Program. The consultant will also assist the North-South Road Corridor Investment Program Management Unit (PMU) on procurement activities for Projects 2 and 3.
B. Scope of Consulting Services
2. The consultants are required to carry out all works detailed and listed in, but not limited to section E. Terms of Reference. A summary of the tasks is as follows:
Task 1. Supervision of the Project 1, consisting of two road sections, including: reconstruction of pavement, drainage, and shoulders, road safety improvements, and repairs to existing structures on Yerevan–Ashtarak road (km 11.8–30.2) road safety improvements on Yerevan–Ararat road (km 9.6–47.2).
Task 2. The consultants are required to: (i) monitor the project performance, benefits and ensure compliance with all social and environmental requirements under the Project 1; and (ii) liaise with government authorities, consultants, NGO’s and other stakeholders concerned with the project implementation.
Task 3. The consultants will prepare due diligence documents (including updated feasibility studies), Detailed Design and Bidding Documents (including prequalification documents), final Land Acquisition and Resettlement Plan (LARP), final EIA and EMP, and other documents as required, for Tranche 2 (Ashtarak-Talin) and Tranche 3 (Talin-Guymri) Projects. The Consultant will assist the Government of Armenia in the preparation of Periodic Financing Request (PFR) 2 and PFR 3 acceptable for ADB's approval of Tranche 2 Project in 2010 and Tranche 3 Project in 2011. The Consultant will also assist the PMU on prequalification and bidding processes as necessary. The consultants are required to: (i) update feasibility studies prepared under TA7208-ARM for Ashtarak-Talin- Guymri road, and assist the Government of Armenia on preparation of Periodic Financing Request (PFR) 2 for ADB financing of Tranche 2 Project in 2010 and Tranche 3 Project in 2011
10
(ii) prepare detailed engineering design and bidding documents for Projects 2 and 3 based on preliminary design prepared under the Project Preparatory Technical Assistance (PPTA) for upgrading the existing road to Category 1 standard (four-lane dual carriageway), and take all necessary actions for getting required approvals and certifications for the prepared detailed engineering designs as prescribed by the Armenian legislation; (iii) update the draft land acquisition and resettlement plan (LARP) prepared under the PPTA and prepare final implementation-ready LARP for Projects 2 and 3, and help the PMU implement the LARP; (iv) update the draft EIA/EMP and prepare final EIA and EMP reports for Projects 2 and 3; and assist the EA in getting required approvals for the EIA and EMP as prescribed by the Armenian legislation (including conclusion from Environmental Expertise SNCO under the RA Ministry of Nature Protection, agreement on route with the RA Ministry of Culture, etc.); (v) prepare all other due diligence documentation for Projects 2 and 3 as required; (vi) assist the PMU on prequalification and bidding processes for the civil works of Projects 2 and 3.
C. Experience and Qualifications Required of the Firm and Specialists
3. The services of an international engineering firm in association with a national engineering firm (collectively called "the Consultant") will be required as detailed in Section E below. The Consultant should have extensive experience in highway design, construction supervision, construction specifications, quality control, contract management and dispute resolution of similar size international contracts. The Consultant's team must comprise specialists that have obtained, at least, a bachelor's degree from an accredited university, and have experience in Armenia and/or in Caucasus and Central Asian countries. The team leader and at least one other international specialist must have a valid (active) license or membership in a professional organization and recent professional development training related to his or her field. The curriculum vitae of the specialists should contain information of the assignment they have successfully completed in the last 5 years, with complete names and addresses of the clients and the name and contact information of the immediate supervisors, and the number(s) of the license(s) and membership(s) and the name(s) of the issuing organization(s). The team leader and the team member with the second highest person-months of input should provide letters from at least two clients in the past five years, confirming successful completion of the assignments. The Employer may contact randomly selected clients of the first ranked firm, for verification of the information provided by the firm, prior to signing the contract.
D. Selection Method and Criteria
4. The lead proposing firm is expected to form associations or joint ventures with one or more national firms with an established record of technical and project area experience. All firms are required to submit a full technical proposal, which will be evaluated according to the quality- and cost-based selection (QCBS) method described in ADB's Guidelines on the Use of Consultants (2010 as amended from time to time). A weighting system of 80% for quality and 20% for cost will be applied. The Consultant's team will have 72 person-months of international and 174 person-months of national expertise as set out in Section F below. The Consultant may propose alternative arrangements, which, subject to assessment and approval by the PMU and ADB, will provide services of an equivalent or better quality. The consulting services are
11 expected to be started on 1 October 2010. The Detailed Design for Projects 2 and 3 are expected to be completed by end February 2011.
E. Terms of Reference
1. Construction Supervision for Project 1
5. The civil works will be executed under the International Federation of Consulting Engineers (FIDIC) Conditions of Contract for Construction, for Building and Engineering Works designed by the Employer (Multilateral Development Bank Harmonized Edition, March 2006) to be procured under the ADB's International Competitive Bidding procedures. The construction period for the Contract will be 33 months plus 12 month defects liability period.
6. The PMU established by the Government under the Ministry of Transport and Communications (MOTC) for the implementation of the Program will act as the Employer on behalf of the Government and as the Implementing Agency who will perform day-to-day administration of the Project 1. The Employer will recruit the Consultant in accordance with ADB’s Guidelines on the Use of Consultants.
a. Design Review
7. The Consultant will review the detailed engineering designs prior to mobilization of civil works, with emphasis on the geotechnical investigations and pavement design. The Consultant shall prepare a report where his concurrence with the designs is stated and/or modifications are proposed. If modifications are proposed by the Consultant, it shall endeavor to adhere as close as possible to the scope of the civil works contract as defined in the specifications and bills of quantities. In addition, and in the framework of the above the Consultant will carefully review the design prepared for km11.8 to km18.37 of Yerevan-Ashtarak and km9.6 to km47.2 of Yerevan- Ararat sections, which are scheduled as civil works package 2 (CW2) under Project 1 of the MFF. The design for CW2 does not currently comply with the required standards. Based on the design review the Consultant will suggest technical solutions in the framework of required standards for European highways, taking into consideration environmental and nature protection issues, measures for improving safety, land acquisition and resettlement requirements (if necessary) as well as the financial implications of suggested technical solutions. The Consultant will carry out the examination works in November and December 2010 and submit a corresponding report by the end of December 2010.
b. Construction Supervision
8. As the Employer’s Representative, the Consultant,referred to as the Engineer under the construction contract. will administer the construction contract and ensure that the works are constructed in accordance with the provisions of the construction contract. The Consultant will make all engineering decisions required for the successful and timely implementation of the civil works contract1 and have all of those powers which are defined as being the Engineer, with the exception of the following which will be retained and exercised by the Employer, generally on the advice of the Engineer. The Engineer will be required to nominate a Sr. Resident Engineer who will be resident full-time on the Project.
1 As per the FIDIC conditions of contract for construction, for building and engineering works designed by the Employer, Multilateral Development Bank Harmonized Edition, March 2006.
12
(i) Determination of values, cost or time ...... (Cl. 3.5)2 (ii) Certifying additional cost to the Contract Price (Cl. 13 – Variations) (iii) Subcontracting ...... (Cl. 4.5) (iv) Order to Commence Works(Cl. 8.1) (v) Extension of Time ...... (Cl. 8.4) (vi) Suspension of Work ...... (Cl. 8.8) (vii) Performance Certificate .. (Cl. 11.9) (viii) Variation involving cost ...... (Cl. 13) (ix) Default of Contractor ...... (Cl. 15) (x) Contractor’s Claims...... (Cl. 20.1)
In addition, the Consultant, as the Engineer, should obtain the specific approval of the Employer when delegating duties and authorities to the Sr. Resident Engineer under Clause 3.2 or revoking such delegation.
9. In addition to, or as an expansion of the activities and responsibilities required of the Engineer under the civil works contract, the responsibilities of the Consultant will include the following: (i) as relevant assist the project management unit (PMU) on bidding processes for the civil works of Project 1; (ii) assist the PMU negotiate the mutually beneficial terms and conditions as well as construction schedule; (iii) Ensure the contractor adheres to the agreed schedule at the time of signing the contract for submitting all documents (performance bonds, insurance policies, etc.) completing the Engineers facilities, and all other requirements; (iv) Prepare an IPC submission and review schedule in consultation with the contractor, and hold joint monthly meetings with the Employer to review the approved payments and agree on the submissions to ADB; (v) review the geometry, pavement, bridge, and other structural designs, specifications, construction method etc, prepared by the employer and revise or update if possible to achieve greater economy, safety, reliability, and/or durability; (vi) prepare working drawings, and provide written confirmation to the Employer indicating the acceptance of ownership of the drawings; (vii) permanent presence on site such as but not limited to inspectors of works, surveyors, material technicians and senior Engineers’ staff, (viii) planning and execution of construction supervision and contract administration, including effective and regular supervision of the works, maintenance of project records, correspondence and diaries, as well as quality control testing to ensure that the Works are executed in accordance with the Contract; (ix) approve and monitor the contractor’s construction program and method statements, verifying that they are consistent with the implementation schedule for the Project; (x) provision of survey data to the contractor and checking the contractor’s setting- out of the works; (xi) inspect and test all materials and works to ensure compliance with specifications and giving immediate notice to the contractor in the event that such materials and
2 Clause Nos correspond to FIDIC Conditions of Contract for CONSTRUCTION, for Building and Engineering Works Designed by the Employer, Multilateral Development Bank Harmonized Edition, March 2006.
13
works fail to comply with the specifications; (xii) inspect regularly the contractor’s construction equipment, installations, housing, medical facilities, etc., and ensure that they are adequate and in accordance with the terms and conditions specified in the contract for the Works; (xiii) ensure that road safety design requirements are implemented in accordance with the contract; (xiv) issue notices to the contractor advising of any non-compliance with environmental mitigation measures, as set out in the contract documents. Copies of all notices should be provided to the Employer at the time of issue. Before issuing such notices the Engineer should, as appropriate, have advised the contractor of the non-compliance and given an opportunity to the contractor to make good any adverse impact prior to the notice being issued; (xv) establish efficient procedures for verifying contractor performance and reporting progress and problems in a timely manner, including quality control reports, quantity survey records, requests for variation or change orders, requests for time extension, and contractor’s claims and invoices; (xvi) ensure that the contractor does not involve child labor in the execution of the civil works contracts in accordance with the provisions of the contract agreement; (xvii) undertake supervision works; and prepare and issue the following reports, whose format and content should be acceptable to the employer: an inception report, a brief monthly progress report, a detailed quarterly report, and a detailed project completion report; (xviii) certify payments for the Works against the relevant bill of quantities and issue the Interim Payment Certificates, the Final Payment Certificate and other certificates, including Taking Over Certificate, as required under the civil works contract; (xix) keep the Employer and the ADB appraised of implementation problems which could jeopardize the Project goals and objectives and make recommendation on how those goals and objectives can be safeguarded; (xx) evaluate claims, disputes, extensions of time, and the like, including issuing variation orders as appropriate and in line with the limits placed on the Engineer’s authority, as well as advising the Employer on all matters relating to the execution of the Works; (xxi) issue of the Engineer’s decisions/instructions as appropriate under the civil works contract;; (xxii) provide timely assistance to the contractor in all matters related to interpretation of the contract documents, ground survey controls, planning, quality control testing and other matters relating to the Project; (xxiii) provide the Employer with complete records, reports and ―as-built‖ drawings for the works; (xxiv) assist the Employer prepare progress reports to ADB by incorporating the required information and submitting at the required frequency according the project administration memorandum; (xxv) conduct a complete joint review of the works with all stakeholders and ADB, as well as a safety audit, prior to handover of the site to the Employer; (xxvi) following the issue of the Taking Over Certificate, during the balance of the Contract Period inspect and approve the execution of the outstanding works (if any), as well as the rectification of any defects or damage – advise on any extension to the Contract Period that may be required for such works; (xxvii) the Consultant will, if so required by the Employer, provide any of the following additional services within the contract amount and/or contingencies: (i) prepare reports, including technical appraisals, additional contract documentation, and/or
14
reviewing and commenting on the contractor’s proposals, as may be required for any additional work required for the successful completion of the Project; and (ii) provision of any other specialist services as may be required from time to time.
2. Project 1 Performance Monitoring, Benefits, Evaluation, Safeguards, and Liaison with Stakeholders
10. The Consultant will design a web-based project performance monitoring system (PPMS) to monitor project performance against the targets set in the Design and Monitoring Framework (DMF) of the Project 1 (refer to project and loan documents) according to ADB’s Project Performance Management System (PPMS) Handbook. The PPMS will also include key poverty and socioeconomic indicators and compliance with project assurances. The PPMS will then be approved by the PMU and coordinated with ADB PPMS system for consistency. The PPMS will monitor (i) performance targets set in the DMF as the project progresses through implementation; (ii) compliance with social and environmental safeguards as recommended in the Environment Assessment Review Framework (EARF), Initial Environmental Examination (IEE), EMP, Land Acquisition and Review Framework (LARF) documents prepared for Project 1 (refer to project and loan documents); (iii) other socioeconomic impact assessments including poverty impact.
11. The Consultant's responsibilities will be: (i) review DMF performance targets, update and complement them with other poverty and socioeconomic indicators, in agreement with the PMU; (ii) compile baseline data for all performance targets and indicators as early as possible, but no later than first quarter of the construction mobilization; (iii) measure progress at the project mid-term and completion stages; (iv) monitor socioeconomic impacts on beneficiaries through selective household surveys and participatory research methods; (v) monitor compliance of the project with the provisions preventing discrimination in employment, enforcing gender equality, and reducing risks of spread of communicable deceases; preventing human trafficking, and ensure that such requirements are included in the bid and contract documents; (vi) monitor compliance with major project assurances (refer to project and loan documents); (vii) conduct training in social research methods and build the PMU capacity on performing impact assessments; (viii) ensure that the construction methods proposed by the contractor for carrying out the works are satisfactory, with particular reference to the technical requirements of sound environmental standards on the basis of ADB’s Environmental Guidelines for Selected Infrastructure Development Project (Highways & Roads) and the IEE and EMP prepared for the Project 1; and (ix) Document results in quarterly progress reports.
12. The Consultant will liaise with government authorities, consultants, NGO’s and other stakeholders concerned with the project implementation.
3. Preparation of Projects 2 and 3
13. Update of Feasibility Studies for Tranche 2 and 3 Projects. The Consultant will update the Feasibility Studies prepared under TA7208-ARM for the Ashtarak-Guymri road section, which will form the Tranche 1 (Ashtarak-Talin) and Tranche 2 (Talin-Guymri) Projects.
15
The task will include (i) update of the TA's findings and preparation of Technical, economical, financial, environmental, social and other due diligence documents; and (ii) the update of the EA’s Procurement Capacity Assessment. The Consultant will assist the Government of Armenia in the preparation of Periodic Financing Request (PFR) 2 and PFR 3 acceptable for ADB's approval of Tranche 2 Project in 2010 and Tranche 3 Project in 2011. The PFRs will reflect the Consultant's findings from the due diligence studies.
14. Detailed Design. The Consultant will prepare detailed engineering design and bidding documents for Project 2: Ashtarak–Talin, and Project 3: Talin-Guymri road following recommendations of the preliminary design prepared under the PPTA, and the agreed design parameters between the Government and ADB. All necessary actions shall be taken by the Consultant for getting required approvals and certifications for the prepared detailed engineering designs. The Consultant will also assist the project management unit (PMU) on prequalification and bidding processes for the civil works of Projects 2 and 3.The Consultant shall make maximum use of available data, topographic, geological and seismic maps, road condition surveys, technical studies and documents available from the PMU and other government agencies. Detailed terms of reference for the design will be agreed with the PMU and ADB prior to mobilization of design works. Key design criteria will be upgrading the existing two-lane Astharak–Talin-Gyumri road to four-lane Category 1 road including improvements to horizontal and vertical alignments, pavement reconstruction, improvements/reconstruction of road structures, and related road safety provisions.
The detailed design would include, but not be limited to the following: Achieving the optimum combination of rehabilitation costs and road serviceability, using modern design methods and requirements. The end product should have a life of 20 years or more and be maintainable at reasonable costs and with locally available technology.
a. Field Surveys, Investigations and Tests
Field surveys investigations and tests for detailed design would include, but not be limited to, the ones described below.
Topographic Surveys - Based on the most recent existing surveys (aerial surveys if available), updated by any further necessary surveys, the Consultant shall develop a digital terrain model at a scale of 1:1,000 covering each of the proposed segments. The width of the corridor is expected to vary between 100 and 500 m, as necessary for the overall study of slope stability, drainage, and other design requirements. The Consultant shall carry out a topographic survey along the road segments with cross- sections taken at 20 m intervals or more frequently where characteristics change. The cross-sections shall extend to a sufficient width to include the edges of the Right of Way (ROW) and the intercept between any cut or embankment slope and the adjacent ground. In unstable and potentially unstable areas, the cross-sections will cover as much of the slope area as is practical. The topographic surveys shall cover all necessary points of embankment and excavation slopes, road pavement and shoulders, junctions, roadside drainage, drainage structures, bridges, railway crossings, retaining walls, river training structures, safety features, road signs, utilities, trees, boundary fences and entrances to roadside properties, watercourses and any other feature that would affect the design of road rehabilitation or new construction. The Consultant shall prepare Computer Aided Design and Drawing (CADD) drawings and a digital terrain model of the completed ground survey. The
16
topographical surveys are to be procured using the provisional sums under the contract Geo-technical, Soils and Pavement Surveys - Pavement and materials surveys and tests,shall include the following: (i) core sampling and testing of existing asphalt concrete pavement (where this exists) at 500 m intervals; (ii) subsurface investigations and testing at the sites of proposed new bridges and other structures, as necessary for foundation design; (iii) soil sampling and testing at appropriate intervals, as necessary for road rehabilitation design; (iv) sampling and testing of materials from quarries and borrow sites; and (v) any other geo-technical and soils investigations and testing necessary for detailed design.
All standard geotechnical, soils and pavement surveys are to be procured using the provisional sums under the contract. The surveys and tests shall be conducted in the presence and supervision of the Consultant’s Pavement, Materials or Geotechnical Engineer with appropriate qualifications and experience for supervising and providing instructions on the surveys and tests.
In areas with unstable slopes, the Consultant shall carry out all necessary subsurface investigations and borings to determine the characteristics of soils and rock materials, and shall determine structural features such as folds, faults and fractures and their characteristics
Inspection of Bridges, Culverts and Other Structures - The Consultant shall undertake a detailed inspection and dimensioning of existing bridges, culverts, retaining walls, river training and other structures, including non-destructive concrete testing of bridges and other major structures. Hydrological, Hydraulic and Drainage Investigations - The Consultant shall investigate the hydraulic and drainage efficiency of existing bridges, culverts and road side drainage facilities; shall examine scour, erosion, drainage and flood characteristics along the road; and shall review the locations of climatic zone changes as they affect pavement design.
b. Detailed Design
The detailed design shall be based on the preliminary design developed during the FS stage, shall conform to the design standards approved and adopted for the Project, and shall incorporate the requirements and modifications or alternatives resulting from the Land Acquisition and Resettlement Plan (LARP), Environmental Assessment or any IEE/ EIA and the EMP. Detailed design activities shall include, but not be limited to, the following: Geometric Design - The detailed design alignment shall be based on the alignment developed during the preliminary design, with minor adjustments made to improve geometric characteristics, wherever practical. The detailed road profile would reflect the new pavement structure, embankment raising for drainage purposes in low lying areas, and minor geometric improvements for safety reasons. The road cross- section shall conform to the approved design standards, with the exception of areas where narrower roadway or shoulder widths would be justified on a cost basis or to
17
avoid hill-side excavation for widening that could exacerbate slope stability problems. Geometric design shall also include the design of junctions. Pavement Design - Pavement design shall consider the composition and strength of existing pavement and sub-grade, forecast ESAL loads, and the use of natural or processed construction materials that are readily available. Wherever possible, material used for embankment construction on top of existing pavement shall be locally extracted sand/gravel or material excavated from road cuts, with characteristics and strength modulus equal to/or better than the existing pavement/sub-grade materials. Drainage Design - The Consultant shall determine the drainage areas and basins of water crossings (based on topographic maps, aerial photos and field inspections), study rainfall, water flow and flood characteristics, and determine the requirements for cross-drainage, based on appropriate return flood periods for each drainage area and type of structure. When existing culverts are in poor condition or are deemed to be inadequate, replacements shall be provided. Otherwise, the existing structures will be repaired. Drainage design shall also cover requirements for longitudinal drains, including lining of same, sub-surface drainage, energy-dissipation works to preserve the stability of slopes and pollution control measures. Geo-technical Design – Geo-technical design shall include the design of foundations for new bridges and structures, if any, river training design, and the design of measures for stabilization and protection of unsafe slopes, including retaining walls, wherever practical and economically justified. Bridge and Structures Design - The design of remedial works to existing bridges shall include all repairs necessary to render them safe and capable of supporting projected heavy loads. New bridges, if any, shall be designed for a 50-year flood and shall conform to the seismic design requirements for the project area. Other Design Requirements - Other items to be covered in the detailed design include safety measures (pavement markings, signs, safety barriers, speed bumps), access design, entrances to roadside properties, urban section features (such as side walks, gutters, storm sewers), utility relocation, bus bays and bus shelters, pedestrian crossings, measures to reduce the effects of wind-blown snow on the road during the long winter periods (such as snow fences, if practical and economically justifiable) and other items. In sections, if any, where the existing ROW would not be sufficient to accommodate the Project road, the Consultant shall prepare detailed ROW plans showing the road located on property maps, including a description of the parcel of land which is required to be acquired.
c. Preparation of D rawings, S pecifications, C ost E stimates, Bidding Documents and Design Reports.
The Consultant shall prepare drawings, technical specifications, quantity and cost estimates, design reports, and bidding and contract documents (including prequalification documents) in compliance with ADB's and the Government's requirements as required for the proper execution of the Project. Detailed design drawings shall include the following: Location plan and vicinity map; Road plan and profile drawings at scales of 1:2,000 horizontal and 1:200 vertical; Roadside drainage plans and profiles, and drawings for subsurface drainage and pollution control measures; Road cross-sections at 20 m intervals (or more frequently when necessary);
18
Typical road sections and details; Drawings for major culverts, including plans, elevations and typical cross-sections, including indication of upstream and downstream invert levels and other details, at appropriate scales; Bridge drawings, including general arrangement drawing (plan), elevation and typical cross-section through the bridge deck, all dimensioned accordingly. These drawings shall also show the extent of the works to be done at the bridge. Detailed drawings of the works at appropriate scales shall also be provided; Drawings for retaining walls, river training, and slope stabilization measures; Standard culvert and other drainage drawings and details; Standard drawings for junctions and property entrances; Standard drawings for bus bays and bus shelters; Standard drawings for pavement markings, signs, safety barriers and other road features; Schedules; ROW delineation; Utility relocation plans; and Other miscellaneous drawings. Technical Specifications - The Technical Specifications shall be based on modern European standards having international applicability, amended by Special Provisions to suit conditions in Armenia and the Project’s requirements. The Consultant shall propose the standards to be used for Client’s approval. The Technical Specifications shall include lists and descriptions of work (pay) items to be executed. Quantity and Cost Estimates - The Consultant shall prepare Bills of Quantities based on the various items of work to be executed in accordance with the Drawings and the Technical Specifications. The items in the Bill of Quantities shall correspond to the work (pay) items specified in the Technical Specifications. The Consultant shall develop a confidential Unit Price Analysis for each work item and a Confidential Cost Estimate, for each work item, work category and contract package as a whole. Unit prices shall be classified into direct costs (labor, materials and equipment), indirect costs (mobilization, on-site and general overheads, contractor’s contingencies and profit) and taxes. The Consultant’s Confidential Cost Estimate shall break out separately all taxes for ease of identification. Design Report and Other Documents - The Consultant shall submit a Design Report providing a description of the Project and summarizing the environmental, and land acquisition and resettlement analysis (and EIAs and/or RAPs where required), EMPs, and the detailed design analysis, including selection of design standards, field surveys and investigations, geometric design, pavement design, geo-technical design, drainage design, bridge and structures design, specifications, bidding and contract documents (including prequalification documents), rehabilitation work program, ROW acquisition requirements, quantity estimates, and various calculations. The Consultant shall also submit a Soils and Materials Report, including location and characteristics of sources of borrow materials.
15. Land Acquisition and Resettlement. The Consultant will review, update and finalize the LARP prepared for Projects 2 and 3 (Ashtarak-Guymri) under the PPTA so as to bring it to the level of an implementation-ready LARP for the Government approval (Final LARP), and help the PMU implement the final LARP (including full delivery of the LARP, compensation and rehabilitation program) as agreed between the Government and ADB. In addition, the Engineer
19 will train, guide and assist the Social & Environment Division of the PMU to adhere to the LARP/LARF and implement as agreed. The key responsibilities will be: (i) Review, update and finalize the LARP based on the detailed engineering design (for the whole length of the Ashtarak-Guymri section) and associated impacts in accordance with the new ADB's Safeguards Policy Statement (SPS, 2009) in particular the safeguards requirements 2, Appendix 2, verify/update number of affected people (APs) and households (including the finalization of legalizable APs, signing of DMS final forms /Description protocols with all the APs), verify/update the maps showing the location of land plots/structures/other assets to be taken, verify/update the Impacts surveys so as to ensure that they have DMS standards, carry out the detailed valuation survey through the services of an independent assessor and update accordingly compensation rates and costs, etc, and finally make necessary changes to the LARP; (ii) submit the updated LARP for the PMU review and approval; (iii) guide and assist in the establishment and implementation of a centralized resettlement/social management system for dealing with resettlement and other related topics such as gender aspects; (iv) assist as needed in the implementation of the LARP (including AP legalization, information campaigns, stakeholder participation, disclosure tasks) and in delivering the compensation and rehabilitation program to the APs; (v) review and help the PMU address any claims or grievances; (vi) help the PMU draft implementation report for submission to ADB; (vii) train the Social and Environment Division of the PMU, resettlement committees, program management unit and other members of the project team involved in resettlement activities to sustain and coordinate all resettlement, social impact assessment, gender, and social development-related activities, and benefit monitoring and evaluation; familiarize, orient, and prepare program management unit, the PMU, and resettlement committees to perform tasks and responsibilities related to resettlement, social preparation, social impact assessment, gender, ethnic minorities and social development; (viii) organize training sessions on, but not limited to the following (a) policies, procedures, and best practices related to resettlement, social preparation/mobilization, social impact assessment, gender, ethnic minorities and social development, and benefit monitoring and evaluation; (b) social assessment methodologies; (c) stakeholder analysis; (d) participatory rapid appraisal; (e) participatory monitoring and evaluation; and (f) basic social research methodologies. (ix) Any other related tasks as necessary.
16. Environment Impact Assessment and Environment Management Plan. The Consultant will review and update the EIA report in accordance with ADB Safeguard Policy Statement (June 2009). Prepare the final EIA report in accordance with ADB’s Safeguard Policy Statement (June 2009), Safeguard Requirements 1: Environment (Appendix 1), Safeguard Requirements 4: Special Requirements for Different Finance Modalities (Appendix 4) and other relevant ADB manuals/guidelines, as well as relevant guidelines of the Republic of Armenia. The consultant's environmental study shall include, but not limited to: (i) Assessment of all potential direct and indirect environmental impacts of each road; present impacts in the order of project cycle: pre-construction, construction, and operation; and preparation of detailed EMPs for the Projects 2 and 3 that should also be included in the bidding document (ii) Estimation of the costs of the proposed environmental mitigation measures and of the implementation of the EMPs for the Projects 2 and 3. Appraisal of the cost
20
against expected environmental benefits, where possible, in a quantifiable manner. Help the road engineers incorporate appropriate mitigating measures into the project design. Preparation of terms of reference and a budget for independent environment monitoring and evaluation. (iii) Updating the archeological studies carried out for preparation of the Projects 2 and 3, including confirmation of existing sites and search of new ones, updating the plan of archeological supervision, and proposing mitigation measures, in accordance with the national legislation and ADB guidelines, for archaeological findings that would impact the Project. (iv) As this is an environmental category ―A‖ project, assist the PMU to carry out at least two meaningful, formal public consultations with affected people. The first consultation during the early stages of EIA fieldwork aims to gather environmental concerns from affected people and the final consultation when the draft EIA report is available and before loan appraisal by ADB aims to share the result of the assessment and the proposed mitigation measures. In an appendix to the EIA the time and location of each consultation, the names of attendees, the subjects discussed, and opinions expressed shall be recorded. (v) Soliciting and incorporating comments on the EIA reports for Projects 2 and 3 from the Nature Protection Ministry's environmental expertise agencies, NGOs, civil society, and other stakeholders. (vi) Assist the EA in all necessary actions for getting required approvals for the EIAs and EMPs (both for Projects 2 and 3) as prescribed by the Armenian legislation (including conclusion from Environmental Expertise SNCO under the RA Ministry of Nature Protection, agreement on route with the RA Ministry of Culture, etc).
The training and capacity building tasks mentioned in the para 14 shall cover also the environmental safeguard policy objectives and principles, as well as implementation requirements.
21
F. Staff Composition
International Team Members (total of 72 p-m input) Title Area of Specialization Special Skills and Knowledge, but not limited to
(Years) (Years) experience Total Inputs Min. General Project Specific (person-months) Experience (Years) Experience (Years)
Team 32 p-m 20 10 Civil Engineering-- Coordination and liaison with Government/Employer Leader/Resident Highway Design and In-depth overall knowledge in detailed design and construction supervision for Engineer/Highway Construction large, medium sized and small highway projects in flat and mountainous terrain Design Engineer Management and Latest AASHTO pavement material and mix design methods Professional Design review and safety auditing Engineering License Project management software State of the art QC/QA implementation Multi-disciplinary team leadership Report writing and oral presentation Highways Design 4 p-m 15 10 Civil Engineering-- In-depth overall knowledge in Highways Design and all concerned engineering Engineer Highway Design aspects. Contracts 4 p-m 15 7 Civil Engineering— Coordination and liaison with Government/Employer Specialist Procurement, contract FIDIC law, and FIDIC contract Civil works procurement and contract negotiation administration Evaluation and settlement of variations and claims Pavement Design 8 p-m 15 7 Civil Engineering— Coordination and liaison with Government/Employer Engineer Asphalt Pavement Asphalt and cement concreted pavement design and maintenance in cold and Design and hot climates Management, and Latest AASHTO pavement material and mix design methods Professional Review, update and design optimization Engineering License or Asphalt and cement concrete plant construction and operation Membership in Hotmix paving and pavement maintenance Professional Association Bridge and 4 p-m 15 7 Civil Engineering— Coordination and liaison with Government/Employer Structural Structural Engineering Bridge and hydraulic structure design Engineer with experience in Retaining wall design design and supervision Seismic retrofitting of construction of Design review bridges, culverts and Bridge condition assessment and maintenance other structures. 22
Title Area of Specialization Special Skills and Knowledge, but not limited to
(Years) (Years) experience Total Inputs Min. General Project Specific (person-months) Experience (Years) Experience (Years)
Soil and 3 p-m 15 7 Civil Engineering— Coordination and liaison with Government/Employer Geotechnical Geotechnical Slope and embankment construction Engineer Engineering and Soil Seismic retrofitting Mechanics Ground and soil investigations Design review Design of earthworks, retaining walls and land slide protection Transport 4 p-m 15 7 Transport Economics Coordination and liaison with Government/Employer Economist Due diligence review Project performance management system Road Safety 4 p-m 10 5 Civil Engineering – Coordination and liaison with Government/Employer Specialist Road Safety Auditing, Accident and Road Data Collection and analysis design of road safety Preparation of Road Safety Audits measures Highway Design Monitoring of Implementation of Road Safety Audits Training Environmental 3 p-m 10 5 Environmental Science Coordination and liaison with Government/Employer Specialist — environmental impact Environmental plan review assessment Environmental impact investigations Water and air quality analysis Construction and operational noise abatement Report preparation Electrical Street 2 p-m 10 5 Highway/Electrical Coordination and liaison with Government/Employer Lighting Specialist Engineer - relevant Road lighting design experience in road and Supervision of installation of road lighting street lighting design Supervision of installation of electrical wiring and appliances and installation Social 4 p-m 10 5 Social Science – Coordination and liaison with Government/Employer Development household and user Preparation of LARP in accordance with ADB requirements Specialist surveys Worker compensation and benefits assessment Community participation programming HIV and human trafficking awareness campaigning
23
National Team Members (total of 174 p-m input) Title Total inputs Min. Area of Specialization Special Skills and Knowledge (person- Experience months) (Years) Deputy Team 32 p-m 15 Civil Engineering-- Highway Coordination and liaison with Government/Employer Leader/Deputy Design and Construction Geometric design of roads Resident Management Design review and safety auditing Engineer/Highway Project management software Design Engineer QC/QA review Report writing and oral presentation Highway Engineer 22 p-m 10 Civil Engineering-- Highway Geometric design of roads Design and Construction Checking of maps and topographical surveys Supervision Design review and safety auditing Project management software QC/QA review Preparation of CAD drawings Pavement Design 4 p-m 15 Civil Engineering—Asphalt Asphalt and cement concrete mix design Engineer Pavement Design and Asphalt and cement concrete plant construction and operation Management Hotmix paving and pavement maintenance work supervision Laboratory and in-situ testing Structural Engineer 11 p-m 15 Civil Engineering—Structural Bridge and hydraulic structure design Engineering Bridge condition assessment Sampling and testing Geotechnical 8 p-m 15 Civil Engineering— Slope and embankment construction Engineer Geotechnical Engineering Geosynthetic and other advanced materials and Soil Mechanics Seismic retrofitting Laboratory and in-situ testing Hydrology and 6 p-m 15 Civil Engineering – Hydrological calculations Drainage Engineer Hydrological calculations, Design of culverts and other drainage facilities Civil Engineering, Structural Highway design Design, Drainage Design Road Safety 3 p-m 10 Civil Engineering – Road Accident and Road Data Collection and analysis Specialist Safety Auditing, design of Preparation of Road Safety Audits road safety measures Highway Design Monitoring of Implementation of Road Safety Audits Training 22 p-m 15 Highway/Electrical Engineer Road lighting design Electrical Street - relevant experience in road Supervision of installation of road lighting Lighting Specialist and street lighting design Supervision of installation of electrical wiring and appliances and installation
24
Title Total inputs Min. Area of Specialization Special Skills and Knowledge (person- Experience months) (Years) Inspectors 22 p-m 10 Minimum of a Diploma in Supervision of works Civil Engineering — quality Sampling control of road works Laboratory and in-situ testing Quality Control Reporting Environmental 5 p-m 10 Environmental Science — Environmental plan review Specialist environmental impact Environmental impact investigations assessment Water and air quality analysis Report preparation Social Development 7 p-m 15 Social Science – household Project performance management systems design and Resettlement and user surveys Worker compensation and benefits assessment Community participation programming HIV and human trafficking awareness campaigning Surveyors and 22 p-m 5 Technical School or College Route location and field surveying Laboratory Diploma GPS and total station use Technicians Laboratory design and management Asphalt and soil testing Archaeologist 5 p-m 15 Archeological Archeological impact investigations surveys/assessments Dealing with cultural heritage Relevant post-graduate Knowledge of Armenian history, archaeological sites and legislation degree Report writing 25
G. Implementation Schedule
17. The implementation schedule is as follows:
1. Construction Supervision: Project 1
Signing of Consultant’s contract September2010 Expected award of civil works contract for package 1 (CW1) November 2010 Design Review for civil works package 2: December 2010 Expected contract award for civil works package 2: August 2011 Substantial completion of all civil works under Tranche 1 Project December 2012
2. Preparation of Projects 2 and 3
Mobilization of design team September 2010 Commencing prequalification of bidders for civil works November 2010 for Project 2 and 3 of the MFF Preparation of PFR 2 By 15 November 2010 Completion of Draft Final Detailed Design for Tranche 2 December 2010 Completion of Draft Final Detailed Design for Tranche 3 March 2011 Preparation of PFR 3 By April 15 2011 Award of civil works contract (Project 2) August 2011
18. The balance of the contract period following the issue of the Taking-Over Certificate for whole of the main civil works under Project 1 is 365 days for the Defects Liability Period. The Consultant’s services are expected to start in October 2010 and conclude taking into account the contract period and the loan closing date, following recommendations to issue the Performance Certificate/issue any other final certification required under the contracts.
H. Reporting Requirements
1. Construction Supervision – Project 1
19. The Consultant will prepare the following reports in English and Armenian language and distribute them in the number of copies indicated below, to MOTC and ADB. The format and content of each report is to be agreed with the PMU and ADB. For each report submitted an electronic copy will be provided. Electronic copies will be in the format used in their preparation with all links, formulas, and fields active. When non-standard software has been used, the consultant will provide, at their own cost, two fully licensed copies of this software. For all reports an executive summary will be included.
PMU ADB Inception (including design review) 5 2 Monthly Progress (subsequent to Inception Report) 5 2 Project Performance Monitoring and Evaluation Report 5 2 Project Completion 5 2
26
a. Inception Report
20. The Consultant shall, within two months of Commencement of Services, submit an Inception Report setting out the parameters of the consulting services including the main civil works contract, the program of works, the Consultant's site organization chart, the manning schedule, and an updated methodology for the services including the education programs and the environmental and social monitoring plan. The Report shall also give the status at the start of the services of those items of the ToR which were already in progress (resettlement, environmental benchmarks etc.) together with the progress of the work to-date and a schedule of certified payments, if any.
b. Progress Reports
21. The Consultant shall, subsequent to the Inception Report, submit monthly progress reports by the 15th of the month following the reporting month, reflecting the progress of the work during the reporting month - the Executive Summary of these reports consisting of (i) one or two pages outlining the position for the complete Project together with (ii) a PPMS report update (quarterly), (iii) the single page contract status report for the ADB-funded sections of road. These reports should normally include, but no limited to: (i) a work program for the road with a bar chart showing scheduled against actual financial/physical progress by major work item, illustrated by bars and percentage of accomplishment (total and by major work item); the work program and the bar chart (showing the critical path) shall be suitably updated in each progress report; (ii) financial data, updated as appropriate, giving time, cost and financial forecast, a schedule of certified payments, update of quantities and cost estimates for construction and supervision; (iii) summary of implementation progress, the work performed, variations issued, payments certified, the equipment and manpower (skilled/unskilled by foreign/local categories in person-months) utilized by the contractor during the reporting month, together with an outline of the work to be performed during the next reporting period; the Engineer's personnel arrivals and departures; (iv) statement of causes of possible delays and remedial measures taken or recommended.
c. Project Performance Monitoring and Evaluation Report (PPMER)
22. The Consultant shall, subsequent to the Inception Report, submit baseline PPMER, mid- term PPMER by project mid-term progress, and final PPMER by project completion.
d. Project Completion Report (PCR)
23. The Consultant will draft a PCR immediately prior to physical completion of construction works in a manner satisfactory to the PMU and ADB, including the major Project events, performance of the contractors, operation of the Project, actual and price inflated (to completion year) Project cost (foreign and local costs separately) by implementation year, and labour employed by skilled/unskilled and foreign/local categories in man-years;
(i) the major Project events, the relative successes (problems) in the implementation of each of the sections, this section of the PCR shall also contain
27
an assessment of the impact of road improvement on the economy and social aspects for the whole Project area; (ii) ―as-built‖ drawings (to be submitted to the PMU Project Manager). These ―as- built‖ drawings will be furnished by the Contractor as per Clause 4.1 (d) of the construction contract;
2. Detailed Design and due diligence for Projects 2 and 3
24. The Consultant will prepare the following reports in English and Armenian language and distribute them in the number of copies indicated below, to PMU and ADB. The format and content of each report is to be agreed with the PMU and ADB. For each report submitted an electronic copy will be provided. Electronic copies will be in the format used in their preparation with all links, formulas, and fields active. When non-standard software has been used, the consultant will provide, at their own cost, two fully licensed copies of this software. For all reports an executive summary [ES] will be included.
25. All reports must contain an Executive Summary detailing the major events, and findings.
PMU ADB Inception 5 2 Monthly Progress (subsequent to Inception Report) 5 2 Final Due Diligence reports for Tranche 2 and 3 Projects, Draft Design, draft 5 2 final LARP, draft final EIA report and EMP, Bidding Documents Final Design, Final Implementation-Ready LARP, final EIA report and EMP, 5 2 Bidding Documents
(i) Inception Report - within 5 weeks from signing of the Contract. The Inception Report shall describe the planning the Consultant has established for the assignment, the staffing and remarks as deemed appropriate. This report shall update the methodology and program of work that was included in the Consultant’s proposal and used as a basis for agreed pricing, noting the changes and detailing any difficulties encountered, together with a proposal on how they may be overcome. The Inception Report shall include at least the following: a) Methodology statement defining the proposed limits of the study, including: a clear definition of the area to be subjected to the designs; an accurate estimation of the time they will take to complete; methods and parameters; any changes to the composition of the Consultant’s team and specialists needed; agencies and government departments which would need to be involved; and methods of consultation with the local authorities and population. b) Detailed Program of Work, including field surveys, LARP review and update, EIA and EMP review and update and final design, showing time, duration and personnel as well as the inter-relationship between activities: (ii) Due Diligence report for Project 2 with inputs to PFR 2 – within 6 weeks from signing of the contract. (iii) Draft Final Design for Tranche 2 Project - within 2.5 months from signing of the Contract, Prequalification and Bidding Documents (including Instructions to Bidders, Bid Data Sheet, Evaluation and Qualification Criteria, Bidding Forms, Bill of Quantities, Technical Specifications, cost estimates etc.), draft final LARP (including
28
compensation and rehabilitation program and DMS final forms/ Description protocols signed with all the APs), and draft Final EIA and EMP for Project 2. Comments on the Draft Final Design, Bid Documents the draft final LARP, draft final EIA and EMP from the PMU - within 2 weeks of receiving the Draft Final Documents (iv) Final Design, and prequalification and Bidding Documents for Tranche 2 Project within 3 weeks after receiving comments on the Draft Final documents. Special Reports – In addition to the regular submissions outlined above, the Consultant shall also submit various special reports, addressing specific Project requirements. Such reports may include the selection of design standards, field survey, investigation and test reports, prequalification document for construction contractors, and other aspects of the study. Final Implementation-Ready LARP, EIA and EMP for Project 2 within 2 weeks after receiving comments on the Draft Final LARP (v) Draft Final Design for Tranche 3 Project - within 5 months from signing of the Contract, Prequalification and Bidding Documents (including Instructions to Bidders, Bid Data Sheet, Evaluation and Qualification Criteria, Bidding Forms, Bill of Quantities, Technical Specifications, cost estimates etc.), draft final LARP (including compensation and rehabilitation program and DMS final forms/ Description protocols signed with all the APs) and draft Final EIA and EMP for Project 3. Comments on the Draft Final Design, Prequalification and Bid Documents, and the draft final LARP, draft final EIA and EMP for Project 3 from the PMU - within 2 weeks of receiving the Draft Final Documents (vi) Final Design, prequalification and Bidding Documents for Tranche 3 Project within 3 weeks after receiving comments on the Draft Final documents. Special Reports – In addition to the regular submissions outlined above, the Consultant shall also submit various special reports, addressing specific Project requirements. Such reports may include the selection of design standards, field survey, investigation and test reports, prequalification document for construction contractors, and other aspects of the study. Final Implementation-Ready LARP, EIA and EMP for Project 3 within 2 weeks after receiving comments on the Draft Final LARP (vii) Progress Reports – The Consultant shall provide monthly progress reports, reporting on the ongoing and planned activities of the study team. (viii) The social assessment surveys, should be submitted by the Consultant to the PMU for approval with the Bidding Documents for each construction package. (ix) All required approvals for the EIAs and EMPs for Projects 2 and 3 as prescribed by the Armenian legislation (including conclusion from Environmental Expertise SNCO under the RA Ministry of Nature Protection, agreement on route with the RA Ministry of Culture, etc) should be submitted by the Consultant to the PMU with the Bidding Documents for each construction package.
26. Format of Reporting; (i) Data shall be submitted to the PMU separately in electronic form, whose precise form shall be agreed between the PMU and the Consultant. (ii) The reconnaissance survey Report, any required RAP should be submitted by Consultant to the PMU in electronic file (MS Word) and five hard copies.
29
I. Facilities and Equipment
1. Provided by the Employer
a. Construction Supervision – Project 1
27. The Employer will provide the Engineer all material data relating to the services of the Engineer, including topographic, geotechnical, resettlement, environmental and design documents.
28. The contractor awarded the contract will provide the following facilities to the consultant at the project site: (i) suitable office space including maintenance and supply of office consumables and communication; (ii) office equipment and monthly operating allowances, including a telephone computer and printer, and photocopier; (iii) accommodation as specified in the bidding documents for use by the supervision consultants including the site inspectors; (iv) vehicles as specified in the bidding documents for use by the supervision consultants including the site inspectors. The cost of vehicle operation, maintenance, and drivers will be borne by the contractor; and (v) support personnel to include office assistants and drivers.
b. Due Diligence and Detailed Design – Projects 2 and 3
29. The Employer will provide the Engineer with all readily available material, and data, reports and designs that were prepared under TA7208-ARM relating to the services of the Engineer, including topographic, geotechnical, resettlement, environmental and design documents for Projects 2 and 3 as. The Consultant will be responsible for ensuring the adequacy, correctness and updating of all data and materials provided.
2. Provided by the Consultant
a. Construction Supervision – Project 1
30. The consultant is required to detail what additional facilities he requires in the performance of his work on this Project, and specify their cost in his financial proposal. All vehicles and equipment procured by the consultant for the performance of his services will remain the property of the Government. Any equipment temporarily imported for the proposed services during the duration of the project and then re-exported will be exempted from import duties or taxes. This will also apply to the personal effects of the consultant’s personnel.
b. Detailed Design - Projects 2 and 3
31. The Consultant will use its own accommodation, office space, equipment, materials, transport, senior and junior, skilled and unskilled personnel for completing the services within the required time, and specify their cost in the Consultant's financial proposal.
30
OUTLINE TERMS FOR CONSULTING SEVICES FOR IMPLEMENTING ROAD SUBSECTOR DEVELOPMENT PLAN
LOAN 2561-ARM MFF NORTH-SOUTH ROAD CORRIDOR DEVELOPMENT PROGRAM
A. Background and Objective
1. The Government of Armenia (the Government) requested Asian Development Bank (ADB) to finance the consulting services to help implement the road subsector development plan prepared with ADB assistance and included under the Multitranche Financing Facility (MFF) for the North–South Road Corridor Development Program (the Program). The objective of the consulting services is to (i) complete the road subsector development plan prepared under the earlier ADB assistance; (ii) facilitate all governmental statutory requirements for adopting the plan for implementation; and (iii) help implement key immediate components.
B. Scope of Consulting Services
2. In collaboration with the Ministry of Transport and Communications (MOTC) – the Executing Agency, and the Armenian Roads Directorate (ARD) – the Implementing Agency, the team of advisory consultants (the Advisor) will (i) review the road subsector development plan contained in the Final Report of the Transport Sector Strategy 2008-2020; (ii) formulate a stand alone road subsector development plan 2010-2020 through analysis, consultations and discussions with concerned government agencies, stakeholders and road users; (iii) facilitate the process to pass all necessary statutory government requirements including review, consolidation and incorporation of comments from concerned government agencies, stakeholders and road user groups through participatory approach and stakeholders consultation; (iv) build consensus among the stakeholders and prepare and agree final action plan for implementation; (v) help MOTC/ARD start implementation of the key priority components, which may include building operations capacity of the road agencies; and (vi) help MOTC/ARD select and procure road and traffic monitoring equipment.
3. Consulting services will be conducted over 12 months, requiring approximately 32 person-months of international and 45 person-months of national input. The Adviser will be selected and engaged through a consulting firm following the ADB’s Guidelines on the Use of Consultants. The quality- and cost-based selection method will be used, and a simplified technical proposal will be requested from the consulting firms. A weighting system of 80% for quality and 20% for cost will be applied.
C. Implementation Arrangements
4. МОТC will be the Executing Agency responsible for implementing the component. ARD will serve as the liaison between Project Governing Council (PGC), МОТC, the consultants, and other stakeholders and road users. ARD will be responsible for overall management of the component.
31
D. Terms of Reference
1. International Consultants (32 person-months)
5. The input of international consulting firm in the field of road asset management, finance, engineering, maintenance and other related areas as per the requirements of this TOR will be required. The team of international consultants will consist of:
(i) Road Asset Planner/Team Leader (9 person-months) (ii) Traffic Information System Expert (5 person-months) (iii) Road Financing Expert (3 person-months) (iv) Road Maintenance Engineer (6 person-months) (v) Road Safety Expert (2 person-months) (vi) Institutional/Legal Expert (3 person-months) (vii) Training Specialist (4 person-months)
6. The international consultants will:
(i) review in detail the road subsector plan under the Transport Sector Strategy; (ii) prepare a review report and circulate initial recommendation to improve and finalize the road subsector development plan 2010-2020; (iii) conduct consultations and discussions with concerned government agencies, stakeholders and road users; (iv) hold workshops and seminar to disseminate the recommendations and collect feedback from wider public; (v) formulate the final road subsector development plan 2010-2020 with a goal to integrate it with the multimodal transport sector development in Armenia, particularly a complementarity between road and railway subsectors; (vi) assist MOTC/ARD to circulate the draft document among the stakeholders by preparing necessary notes, summaries and elaborating proposed plan through discussions and consultations; (vii) facilitate the approval process including review, consolidation and incorporation of comments from concerned government agencies, stakeholders and road user groups through participatory approach and stakeholders consultation; (viii) build consensus among the stakeholders and prepare and agree final action plan for implementation; (ix) help MOTC/ARD identify key priority components of the plan for implementation; (x) help MOTC/ARD start implementation of the key priority components, which may include building operations capacity of the road agencies; (xi) prepare technical specifications for the state-of-the-art road condition and traffic monitoring equipment, which will include integrated traffic counters video surveillance equipment, axle weight control equipment, and mobile road condition diagnostics equipment; (xii) help MOTC/ARD procure and oversee installation and commissioning by the supplier.
32
2. National Consultants (45 person-months)
7. National consultants will have expertise in similar fields as international consultants. In addition, national consultants should have knowledge in road sector and its performance, specifically in road engineering, maintenance, finance, operation, and regulatory basis.
E. Counterpart Facilities
8. MOTC will provide the Adviser the counterpart support and facilities necessary for implementing the component which includes office accommodations, logistical services, information, and materials necessary for the services.
F. Reporting
9. The Adviser will provide ADB and MOTC with all papers and reports prepared under the contract, as well as workshops and training programs. The consultants will also provide brief monthly reports to MOTC and АDВ.
10. An inception report with a detailed work program will be prepared and submitted within 1 month of commencement of services, a midterm report within 5 months, and a draft final report covering all subjects and requirements under the study within 11 months. А final report will be prepared 30 days after the final tripartite review meeting with the Government, ADB, and the consultants. Inception, midterm, and final reports will be submitted in both English and Armenian languages in sufficient copies to the Government and in English language in 3 copies.
33
ARMENIA: North-South Road Corridor Program Tranche 2: Ashtarak-Talin Road Review of Land Acquisition and Resettlement Plan TOR for the Local Resettlement Specialist
I. Background and Tasks
1. To expedite the initiation of the work for the final LARP for the captioned Project so as to meet the ADB readiness requirements for PFR approval by the end of 2010, LARP activities will have to start before the Supervision Consultants team comes on board in October 2010. To start these activities as soon as possible MOTC intends to hire for the month of June the local Resettlement Specialist that prepared the draft LARP. Objective of the assignment is to establish continuity between the work done before and the work to be carried out in the next months by the PMU Land Acquisition and Resettlement (LAR) team. The Local Resettlement Specialist will also carry out the following tasks:
(i) Revise the draft LARP to reflect the reduction in scope of the project from the original Ashtarak-Gumri road leg to the Ashtarak-Talin road leg. (ii) Assist as needed the PMU in the LARF approval process and in the preparation of related documents (iii) Assist MOTC in carrying out all public consultation with affected communities within the Ashtarak-Talin road leg. (iv) Work with MOTC to provide the needed project background and capacity to the PMU LAR team; (v) Work with MOTC and other relevant Government institutions to establish a clear plan and relative procedures for the legalization of legalizable Affected Parties, including relevant initial governmental decree as well as forms to be applied during the verification process. The plan will be detailed in the revised LARP. (vi) Assess the work needed to carry out the detailed measurement survey (DMS) needed to finalize the LARP for the Ashtarak-Talin road leg. (vii) In collaboration with the PMU prepare the TOR for the final valuation of affected assets, identify the consultants that will do the work and assist the PMU in the selection process as needed. (viii) Organize and conduct two-day training for PMU staff on land acquisition and resettlement issues.
II. Outputs
2. The Local Resettlement Specialist will provide the following outputs: (i) a revised draft LARP for the Ashtarak-Talin section by June 15, 2010; (ii) a background paper and action plan for the legalization of legalizable affected parties, including relevant initial governmental decree as well as forms to be applied during the verification process, by June 25, 2010; (iii.) and a note detailing the results of the consultation in each village under the LARP by June 30, 2010.
3. At the end of the assignment the specialist will also prepare a brief final report detailing the tasks carried during the assignment and relative outcomes.
34
North-South Road Corridor Investment Program Tranche 2: Ashtarak – Talin and Tranche 3:Talin – Gyumri
Terms of Reference Independent Monitoring Agency (IMA)
I. Introduction
1. The Asian Development Bank (ADB) has agreed to provide Government of Armenia with a $ 500 million Multitranche Financial Facility to finance the North-South Road Corridor Investment Program (the Program). The North–South Road Corridor runs 556 km from the border with Georgia at Bavra via Gyumri, Ashtarak, Yerevan, Goris, and Kapan, to the border with Iran at Meghri. It is 2-lane throughout, with the exception of an 18km length on the M-1 (Yerevan–Ashtarak) and the M-2 (Yerevan–Ararat) sections, which are dual 2-lane. The overall objective of the Program is to provide a high-quality NSRC from the Georgian border to the Iranian border. The Program is divided into three tranches. Tranche 1, which will improve the existing 18.4 km four-lane dual carriageway highway between km 11.8-km 30.2 of the Yerevan- Ashtarak Road, has been approved. Tranche 2: Ashtarak – Talin and Tranche 3: Talin – Gyumri cover improvement of the existing highway from a 2-lane road to a 2-lane dual carriageway highway fitting international standards.
2. No relocation of households or acquisition of productive land is expected from Tranche 1. However, civil works for Tranches 2 and 3 may entail land acquisition and resettlement. A Land Acquisition and Resettlement Framework (LARF)1 has been prepared by the Project Preparation Technical Assistance Consultant, PADECO Ltd. (Tokyo), and endorsed by the Government of Armenia and ADB. Based on the LARF, draft Land Acquisition and Resettlement Plan (LARP) has been developed for both Tranches 2 and 3. These draft LARPs will be finalized during the final design stage.
3. The LARF specifies that land acquisition and resettlement be monitored externally by an Independent Monitoring Agency (IMA) with the objective to monitor implementation process, identify problems and suggest respective solutions.
II. Objectives
4. ADB policy and LARF require that external monitoring be carried out in parallel with the implementation of each LARP. The IMA is expected to submit quarterly reports of the resettlement progress and a final compliance reports which indicates whether the compensation program has been carried out based on the provisions of the LARF and ADB policy and with the satisfaction of the affected persons (APs). A year after the completion of the LARP implementation, the IMA is expected to carry out a post-implementation evaluation of the LARP to find out if the LARP objectives of restoring livelihood and improving standards of living of affected persons (APs). The final compliance report is a precondition to the commencement of construction under each Tranche
1 The LARF is currently being updated as part of Tranche 2 loan processing. The revised LARF will supersede the earlier LARF version approved in September 2009 once it is approved by the Government and ADB and made part of the Loan Agreement.
35
5. To ensure compliance with this requirement North-South Road Corridor Project Management Unit (PMU) intends to recruit a Local Company or Non-Governmental Organization as the Independent Monitoring Agency (IMA) for Tranches 2 and 3 of the Program to provide an independent review of resettlement implementation to determine whether intended goals are being achieved, and if not, what corrective actions are needed. The objectives of the independent monitoring agency will be two-fold:
(i) verify that resettlement has been implemented in accordance with the approved LARF and LARP; (ii) ensure that APs have been able to at least restore their livelihoods and living standards.
III. Scope of Work
6. For each of the Tranches 2 and 3 the work of the IMA can be subdivided into three phases:
(i) Baseline su rvey – This involves establishing the pre-LARP implementation conditions of the APs to allow for the measurement of the initial impacts of the compensation and assistance provided in the course of LARP implementation. In this phase, the IMA will:
Review the socio-economic baseline/land acquisition and resettlement (census) / DMS information of APs available with PIO/Final Designer for Tranches 2 and 3, and confirm its accuracy and validity. In order to obtain insight on the number and types of APs and impacts and determine the sampling plan for the conduct of surveys, the IMA shall review the socioeconomic data of APs/DMS information for each of the Tranches 2 and 3.
Having confirmed the validity of available socioeconomic and census data available with the PMU/ Final Designer for Tranches 2 and 3, IMA will undertake a baseline survey of each of the Tranches 2 and 3. To ensure that adequate pre-project data is collected and available for monitoring, the baseline survey shall be conducted prior to the implementation of the LARP. The survey will cover a representative sample of APs based on the census list, stratified according to types and severity of impact. The survey shall follow the general rule of taking 10% of all APs and at least 20% of severely affected APs. However, adjustment in the sample size can be made to ensure that the error margin is +/- 5% at a CI of 95%. The sampling procedures for the baseline survey and the subsequent formal survey for each of the Tranches 2 and 3 should be consistent to ensure comparability of samples.
(ii) LARP i mplementation review an d preparation of LARP Final C ompliance Report – This involves the review of LARP implementation process to ensure that activities are implemented according to the approved LARF and LARP. In this phase the IMA shall:
36
Review internal monitoring reports prepared by the PMU. The IMA shall review and verify in the field the results of the internal monitoring reports prepared by the PMU as a part of the Quarterly Program Progress Reports. The review shall involve a random check of payment/compensation records. Field verification will be done through interview with key informants involved in the consultations, and random interview with men and women APs.
Review of procedures/methodologies/systems. The IMA shall check if the valuation, consultations, disclosure, payments, and related processes are done in accordance with the approved LARF and LARP.
Prepare the LARP Final Compliance Report that shall demonstrate as to what extent the LARPs for each of the Tranches 2 and 3 were able to accomplish their objectives. The Compliance Report for each Tranche shall be used as basis for allowing the construction to proceed (under the respective Tranche). As part of the final compliance report, the IMA will also assess the status of project affected vulnerable groups such as female-headed households, disabled/elderly and families below the poverty line. The following will be considered as the basis for indicators in monitoring and evaluation of the project:
(a) Socio-economic conditions of the APs in the post-resettlement period (b) Communications and reaction from APs on entitlements, compensation, options, alternative developments and relocation timetables, etc. (c) Changes in housing and income levels (d) Rehabilitation of informal settlers (e) Valuation of property (f) Grievance procedures (g) Disbursement of compensation; and (h) Level of satisfaction of APs in the post-resettlement period
(iii) Post LA RP ev aluation – In about a year after completion of LARP implementation, a post-implementation evaluation shall be carried out to find out if the objectives of the LARPs for each of the Tranches 2 and 3 have been attained or not. The post-LARP Report will be developed at this stage for each of the Tranches 2 and 3.
Assess the impact of the LARP through formal and informal surveys with the APs. Upon completion of compensation payments/assistance, the IMA shall conduct a formal survey of a representative sample of men and women APs to determine changes that have occurred on the APs. Focus group discussions and other unstructured data gathering methods will also be used for men and women AP groups to supplement the findings from the formal survey. The assessment will also look into potential differential impact or benefit that men and women APs experienced from the resettlement activities. The result of the surveys will serve as the end term review report of the IMA for the specific Tranche.
37
Assess APs satisfaction on the valuation of assets and entitlements, timing of payments, fund availability and disbursements. In the same post-LARP survey, the IMA shall ascertain the satisfaction of APs on the valuation of assets, as well as, the scope and timing of assistance provided under the LARP.
Assess the resettlement efficiency, effectiveness and sustainability, drawing lessons for future resettlement policy formulation and planning. The post- LARP report shall also assess the efficiency, and effectiveness of the LARP to draw lessons for future LARP planning and implementation. Should the outcome of the study shows that the objectives of the LARP have not been attained, the IMA will recommend appropriate supplemental assistance for the APs.
Consult APs, officials, community leaders for preparing the end term review report. Prior to submission of the post-LARP report, the IMA shall ensure that informal and formal meetings are held with the men and women representatives from the APs, community leaders and other key officials and seek feedback on the contents/analysis in the review report. Highlights of these consultations will also be attached as annex to the report.
IV. Implementation Arrangements
7. The IMA shall report directly to the PMU Head of Unit on Safeguards, Resettlement and Environment. Close coordination with PMU and Final Designer for Tranches 2 and 3 will also be needed. The assignment is on an intermittent basis following the pace of the progress of LARP preparation and implementation in each of the Tranches 2 and 3.
V. Reporting Requirements
8. The IMA is expected to submit to PMU the following deliverables:
An Inception Report and detailed Work Plan including draft formats (as appropriate for various outputs) and draft outlines for various reports (including Baseline Survey Report, LARP Implementation Review Quarterly Report, LARP Final Compliance Report, Post-LARP Report, Final Report), 1 month upon signing of the contract;
for Tranche 2: o Baseline Survey Report; o LARP Implementation Review Quarterly Report; o LARP Final Compliance Report; o Post-LARP Report;
for Tranche 3: o Baseline Survey Report; o LARP Implementation Review Quarterly Report; o LARP Final Compliance Report; o Post-LARP Report;
A Final Report upon completion of the assignment.
38
9. The tentative schedule for deliverables submission is presented in the table below (the timing of deliverables submission may vary based on the progress of LARP preparation and implementation for each of the Tranches 2 and 3).
Name of deliverable 2010 2011 2012 2013 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Inception Report and Work Plan X Tranche 2 Baseline Survey Report X LARP Implementation Review X X Quarterly Report(s) LARP Final Compliance Report X Post-LARP Report X Tranche 3 Baseline Survey Report X LARP Implementation Review X X Quarterly Report(s) LARP Final Compliance Report X Post-LARP Report X Final Report X
10. The IMA shall submit the deliverables in Armenian and English languages in electronic and 3 hard copies along with the cover letter.
VI. Consultant Qualifications and Team Composition
11. North-South Road Corridor PMU SNCO intends to engage a Local Company or Non- Government Organization as the Independent Monitoring Agency (IMA) for the Program Tranches 2 and 3. The Consultant shall have prior experience in conducting external resettlement monitoring for development projects. Familiarity with ADB Safeguards Policy Statement (2009) is an advantage.
12. The Consultant shall mobilize the professional team consisting of competent experts to implement the current assignment. The team shall include at least the following experts: Team Leader (intermittent, as and when required); Sociologist (intermittent, as and when required); Lawyer (intermittent, as and when required).
13. The Consultant will appoint a Team Leader responsible for coordinating the works, ensuring involvement of relevant experts in the works and timely delivery of high-quality outputs, as well as liaising with the PMU.
14. Overall, the consultancy budget is estimated as 12 man/month. During implementation of this assignment the Consultant shall use its office, vehicles and equipment.
39
VII. Payment
(i) 20% of the Contract Cost will be paid to Consultant after approval of Inception Report and detailed Work Plan;
(ii) 30% of the Contract Cost will be paid to Consultant after approval of the Baseline Survey Report, LARP Implementation Review Quarterly Report and LARP Final Compliance Report for Tranche 2;
(iii) 30% of the Contract Cost will be paid to Consultant after approval of the Baseline Survey Report, LARP Implementation Review Quarterly Report and LARP Final Compliance Report for Tranche 3;
(iv) 20% of the Contract Cost will be paid to Consultant after approval of the Post- LARP report for Tranche 2, Post-LARP Report for Tranche 3 and Final Report;
15. Financial Proposal of the Consultant shall include all the taxes envisaged by RA legislation.
40
North South Road Corridor Investment Program Tranche 2: Ashtarak - Talin
Terms of Reference for Verification and Valuation of Land and Assets to be Taken
I. Introduction
1. This ToR is designed to support finalization of Land Acquisition and Resettlement Plan (LARP) for Tranche 2 Ashtarak-Talin section of the North-South Road Corridor Investment Program.
2. Land Acquisition and Resettlement Framework (LARF) that has been approved by the Government of Armenia (GoA) and the ADB will provide the legal basis and entitlement matrix for LARP. Preliminary Detailed Measurement Survey (DMS), Socio-Economic Survey (SES) and zonal Valuation Survey (VS) for the LARP for Tranche 2 have been completed in April 2010.
3. Surveys conducted by Project Preparation Technical Assistance Consultant, PADECO Ltd. (Tokyo) included overlay of the maps provided by the State Committee on Real Estate Cadastre under RA Government with the preliminary route of the road and the areas of the land plots were measured by means of AutoCAD computer software, afterwards the preliminary list of owners and cadastral prices have been compiled. It should be noted that the above surveys have been conducted only for the parts of the land plots to be taken (those located in the right- of-way of the road according to the preliminary design).
4. The objective of this document is to provide guidance in the preparation and implementation of the verification and valuation of land and assets to be taken from Affected People (APs), based on which a LARP will be updated and finalized for the Tranche 2. The LARP will include detailed compensation and administration budgets and implementation schedules. The LARP for Tranche 2 will serve as a model for preparing LARPs for the future tranches.
II. Purpose of the Assignment
5. Project Implementation Organization (PIO) will engage the services of a professional and competent company responsible for verification of results of previously conducted surveys and inventory, measurement, valuation of affected land and assets, determining compensation costs for land and assets to be taken, collection of necessary documents, as well as consultations with all the APs.
6. As a part of the assignment all the APs should be duly consulted and informed on project activities as well as their rights and responsibilities.
7. The final verification and valuation of land and assets to be taken will be implemented during the detailed engineering design. The data collected and verified during the current assignment will constitute the formal basis for determining AP entitlements and levels of compensation during the detailed design. It should be noted that lack of title, license or permit is not a bar to compensation.
41
III. Scope of Services
1. Verification
8. The baseline data and initial DMS for the current project were provided by Project Preparation Technical Assistance Consultant, PADECO Ltd. (Tokyo).
9. Verification is aimed at checking the data collected as a result of previous surveys, identification of the extent of land and asset taking, finalization of list of APs, identification of non-titled owners (including those to be legalized), as well as development of complete inventory of all APs and their land and assets.
10. As a result of the verification process the separate package will be developed for each AP (irrespective of entitlement or ownership) that includes filled in forms presented in Annex A to this TOR.
11. As a part of verification process the Consultant Company will be responsible for the following activities: Verification of total and affected areas of land, by type of land assets (including data on whether affected land or source of income is primary source of income) and land use (Agricultural, Commercial, Residential, Communal Forest, etc); Verification of total and affected areas of structures, by type of structure (main or secondary), size, material; Quantity and types of affected crops and trees; Quantity and area of affected common property, community or public assets, by type; Quantity and type of other losses, e.g., business or other income, jobs or other productive assets; estimated monthly net income from the business based on official tax declaration, etc.; Verification of legal status of affected land and assets, and duration of tenure and ownership; Verification of mapping data and update of maps developed under Project Preparation Technical Assistance (overlay of cadastral maps with right-of-way), measure each land plot and structure, update the cadastral list and maps confirming with regional cadastre officer and property owners; Identify vulnerable APs (below poverty line or headed by a woman); collect and summarize data on AP and AH, by ethnicity, age, gender of head of household, household size, primary and secondary source of household income vis-à-vis poverty line, income level, whether household is headed by women, elderly, disabled, poor or indigenous peoples; Completion of forms presented in the Annex A for each AP (including community, individual and business APs); Identify number of AHs (including AP) by category of loses (lands, structures, crops, trees, businesses etc.), including those loosing more than 10% of their agricultural land or to be relocated; Identify relocation needs (number of buildings, businesses to be relocated, etc.) Develop a file package for each AP including map and corresponding list showing property location, area/size, owner’s name, land category, number and location of crops, trees or buildings that needs to be acquired as well as relevant social data.
42
2. Valuation
12. After the verification of DMS the full Valuation Survey (VS) will be carried out to finalize an interim land and asset acquisition and compensation budget, following to the entitlement matrix categories found in the GoA approved LARF, for inclusion in the Tranche 2 LARP.
13. As a part of valuation process the Consultant Company will be responsible for the following activities:
Assessment of replacement cost both either at market rates or cadastral values (whichever the highest) for each identified land and asset to be taken (about 405 plots and 17 structures); o Market value or cadastral values (whichever the highest) of total affected lands (both in case the whole land plot or in case the affected part of it is taken) by land use type (Agricultural, Commercial, Residential, Communal Forest, etc); o Replacement cost /market value/ of affected structures by structure type, materials, size etc. Compensation will be free of deductions for depreciation, transaction costs and salvageable materials; Determine a detailed compensation budget according to estimated market cost of identified trees, crops to be compensated (both in case the trees/crops on the whole land plot or on the affected part of it are taken); Determine a detailed compensation budget for utilities for public services such as water, gas and electric supply infrastructure, etc.; Determine a detailed compensation budget for business and employment losses (about 31 businesses – temporary impacts); Determine a detailed compensation budget for relocation needs (market value of buildings, businesses to be relocated, etc., transportation cost, acquisition of land plot with similar quality and area); Determine a detailed administrative budget for LARP implementation.
IV. Procedure and Methodology
1. Verification
14. The procedure of the verification is based on ADB policy and the relevant laws of the Republic of Armenia.
15. The following procedures and methodology will be applied by the Consultant Company: Review of data and maps developed under Project Preparation Technical Assistance Consultancy; Measurement of land/assets to be taken and update of available maps to include measurement data; Review of APs’ census, social-demographic and socio-economic data; Review of the documents on legal status of affected land and assets (including duration of tenure and ownership); Development of profile for each AP including data on; o total and affected areas of land, by type of land assets and land use o total and affected areas of structures, by type of structure, size, material; o quantity and types of affected crops and trees;
43
o quantity and area of affected common property, community or public assets, by type; o quantity and type of other losses, e.g., business or other income, jobs or other productive assets; estimated monthly net income from the business based on official tax declaration, etc.; Data processing and analyses. Update of maps and preparation of reports.
2. Valuation
16. The procedure of the valuation survey is based on ADB policy and the relevant laws of the Republic of Armenia. The calculation of unit prices for each type of loss will is based on LARF Entitlement Matrix.
17. The following procedures and methodology will be applied by the Consultant Company: Reviewing the DMS information regarding the appraised objects, including public utilities; Technical examination of the documents concerning the businesses and structures/buildings; Visual examination of the appraised objects; Market examination; Application of the methodology and methods for the appraisal of market value of the impacted land and assets defined in the LARF; Data processing and analyses; Preparation of reports.
V. Expected Outputs
18. The Consultant Company will be responsible for providing:
Work plan and schedule; Revised and updated interim LARP; Profile for each AP (titled and non-titled) consisting of map and corresponding list showing property location, area or size, owner’s name, land category, number and location of crops, trees and/or buildings that need to be acquired (on a whole land plot and on the affected part of it), as well as completed forms presented in the Annex A with relevant attachments (copies cadastral certificate, lease agreement, passport of owners/lessees, birth certificates for those under 16, documents stating social categories, etc). This section shall also present the verified list and profiles of non-titled APs, including those subject to legalization; Valuation report for each AP based on type of assets and principals of Entitlement Matrix found in the attached LARF, including o Detailed compensation costs based on estimated market value or cadastre price (whichever the highest) of total and affected land, by type of land assets and land use. o Detailed compensation costs based on estimated replacement cost/market value of total and affected areas of structures, by type of structure (main or secondary). o Compensation costs of affected crops and trees, by quantity and type.
44
o Cost of other losses, e.g., business or other income, jobs or other productive assets; estimated monthly net income from the business, etc. o Estimated compensation costs of affected common property, community or public assets, by type, quantity and area. o Estimated relocation cost. o Estimated administrative cost for realization of compensation activities (including transportation cost, certificates and attorney fees etc.) o Estimated total cost to be paid to each AP for taking whole land plot/trees/crops and for taking those on the affected part of it. o Any other financial relevant information regarding the implementation of LARP; DMS and valuation databases in Excel format and relevant maps; Conclusions and recommendations, highlighting key issues and actions that need to be taken to address problems related to verification and legalization process, as well as estimation of LAR budget and lessons for future MFF valuation planning and implementation.
19. The Consultant Company will submit the outputs in Armenian and English languages to PIO in hard and electronic copies with a covering letter. Data will be presented on CAD maps and recorded in a database.
VI. Team Composition and Operational Arrangements
20. The Consultant Company shall mobilize multi-profile professional team consisting of competent expects to implement the current assignment within the timeframe mentioned in Section 8 of this ToR. The Consultant Company shall possess valid license of independent land and asset valuator issues by relevant state entities of RA. The team experts shall be experienced in: Cadastral mapping and measurements; Sociology (including interviewing, questionnaire filling in, etc.); Agronomy (including calculation of cost for crop and tree losses); Legal issues (including verification of legal status of affected land and structure assets); Land and asset valuation.
21. The Consultant Company will report to the PIO Social and Resettlement Officer. The Consultant Company will appoint a Team Leader responsible for coordinating the fieldwork activities, organizing data processing and report writing. The Team Leader will also be responsible for delivering the proposed outputs and liaising with the PIO.
22. PIO will provide Consultant Company with available documents and maps.
VII. Work Plan
23. The duration of the assignment is estimated at 5 weeks and is expected to start immediately after contract signing. All activities should be completed by the end of September 2010.
24. The Work plan and schedule shall e submitted for PIO approval within three days after the contract signing.
45
25. The Draft Final Report shall be submitted to PIO by the end of the forth week of the assignment for review and comment. The Final Report incorporating comments made by PIO and ADB shall be presented within one week following submission of comments by PIO.
VIII. Use of Equipment
26. During implementation of this assignment the Consultant Company shall use its office, vehicles and equipment, including portable equipment required for implementation of field works (such as laptops, portable scanner, printer and copier, etc.).
IX. Payment
27. 20% of Contract cost will be paid to Consultant Company as advance payment, after submission of bank guarantee in a format acceptable to ADB.
28. 80% of Contract cost will be paid to Consultant Company after approval of the Revised interim LARP, Final Report, databases and maps.
29. Financial Proposal of the Consultant Company shall include all the taxes envisaged by RA legislation.
46
TERMS OF REFERENCE FOR CONSULTING SERVICES FOR PROJECT MANAGEMENT OF PROJECTS 1 AND 2 (L2561-ARM AND L2729- ARM) OF THE MFF, NORTH-SOUTH ROAD CORRIDOR INVESTMENT PROGRAM IN ARMENIA
A. Background and Objective
1. The government of Armenia (the government) has requested the Asian Development Bank (ADB) to finance consulting services for project management and construction supervision of Projects 1 and 2 (the Project) under the Multitranche Financing Facility (MFF) for the North- South Road Corridor Investment Program (the investment program). The main tasks of the project management consultant (PMC) are (i) project management and procurement support; (ii) financial management; (iii) monitoring; (iv) construction supervision, and (v) evaluation and reporting of the Project. The government will recruit the PMC in accordance with ADB's Guidelines on the Use of Consultants. The Ministry of Transport and Communications (MOTC) of Armenia is the executing agency and acts as the Employer for the investment program.
B. Scope of Consulting Services
2. The PMC is required to carry out, but not limited to, the following tasks:
Project management and procurement support. The PMC will manage implementation of the Project on behalf of MOTC. The PMC will carry out the services in liaison with the MOTC and ADB. The PMC will maintain records and carry out the day- to-day coordination, monitoring and supervision of the Project, including the preparation of regular progress reports. The PMC will assist MOTC in the procurement of contracts in respect to the civil works for Project 1 and Project 2 of the MFF ensuring that procurement is carried out in compliance with ADB's Procurement Guidelines. The PMC will set up and operate an internet based multi-language tender platform on base of a project communication management system (PCMS). As applicable to the timing of the consultancy services contract, the PMC will update the bidding documents as necessary, acceptable for MOTC and ADB. The PMC will assist the MOTC in bid evaluation, and in preparation of the Bid Evaluation Report. The PMC will handle all contractual arrangements, including any revisions requested by contractors, ADB, and/or MOTC, to ensure quality and adherence to ADB’s rules and procedures. In case of any loan covenants and MFF undertakings the PMC will prepare assurance certifications and submit them to MOTC and ADB for approval. The PMC will ensure compliance with the contract conditions, payment terms, variations, dispute resolution, and monitoring, etc. The PMC will maintain all records relating to procurement, maintain a separate record relating to complaints and their redressing, and periodically update the procurement plan in agreement with MOTC and ADB to reflect the actual project implementation needs and improvements in institutional capacity. The PMC will also assist the MOTC and the ADB Mission during ADB project review missions. The PMC will organize trainings for the MOTC and other concerned authorities’ staff, according to the schedule to be agreed with MOTC and ADB. Financial management. The PMC will ensure financial management procedures are in place and are strictly followed, specifically relating to payments, financial accounting, financial reporting and record keeping. The PMC will carry out all financial management and administration under the Project, including review justifications provided for any variation orders proposed and submitted by the contractors, review withdrawal applications, maintain project accounts, prepare financial statements and submit them to MOTC and ADB for approval.
47
Monitoring. The PMC will monitor and report to MOTC and ADB the performance of the Project and ensure compliance with all social and environmental requirements and the requirements of design solutions. The PMC will develop a project performance monitoring system (PPMS), including a web-based PPMS, based on the design and monitoring framework (DMF) of Projects 1 (L2561-ARM) and 2 (L2729-ARM) of the MFF (refer to project and loan documents) according to ADB's Project Performance Management System (PPMS) Handbook), and operate and maintain the system. The PPMS will include key poverty and socioeconomic indicators and compliance with project assurances. The PPMS will monitor (i) performance targets set in the DMF through implementation; (ii) compliance with social and environmental safeguards as recommended in the Environment Assessment Review Framework (EARF), Initial Environmental Examination (IEE) for Project 1 of the MFF, Environmental Impact Assessment (EIA) for Project 2 of the MFF, Environmental Management Plan, Land Acquisition and Review Framework (LARF), and Land Acquisition and Resettlement Plan (LARP) for Project 2 of the MFF (refer to project and loan documents for Projects 1 and 2 of the MFF); other socioeconomic impact assessments including poverty impact. The PMC will ensure that all ADB policies and procedures on safeguards are followed throughout the implementation period. The PPMS will need to be approved by MOTC and ADB, and coordinated with ADB PPMS system. The PMC's responsibilities will be:
(i) Develop and implement an overall monitoring plan of the Project; (ii) Develop a consolidated construction program, showing the critical path of the overall implementation program. Any actions required Government actions that have potential implication in implementation should be attended timely and properly. Update overall Project planning accordingly; (iii) Review DMF performance targets, update and complement them with poverty and socioeconomic indicators, in agreement with MOTC and ADB; (iv) Compile baseline data for all performance targets and indicators as early as possible, but no later than first quarter of the construction mobilization; (v) Measure and report to MOTC and ADB progress of achieving the DMF performance targets at the MFF Project 1 and Project 2 midterm and completion stages; (vi) Monitor and report to MOTC and ADB socioeconomic impacts on beneficiaries through selective household surveys and participatory research methods; (vii) Monitor and report to MOTC and ADB compliance of the MFF Project 1 and Project 2 with the provisions preventing discrimination in employment, enforcing gender equality, and reducing risks of spread of communicable deceases; preventing human trafficking, and ensure that such requirements are included in the bid and contract documents; (viii) Monitor and report to MOTC and ADB compliance with MFF Project 1 and Project 2 assurances (refer to project and loan documents), including compliance with all environmental and social safeguards; (ix) Conduct training to build MOTC's capacity on performing impact assessments; (x) Ensure that the construction methods proposed by the contractor for carrying out the works are satisfactory, with particular reference to the technical requirements of sound environmental standards on the basis of ADB's Environmental Guidelines for Selected Infrastructure Development Project (Highways &Roads) and the IEE, EIA and EMP prepared for the MFF Project 1 and Project 2; (xi) Assess the current procurement and financial management capacity of MOTC and prepare, in consultation with MOTC and ADB, an appropriate training program based on the results of the assessment. Conduct training. (xii) Document results in quarterly progress reports.
48
Evaluation and reporting. The PMC will report implementation progress of the Project to MOTC and ADB through quarterly and monthly progress reports. The quarterly progress reports should include project implementation status, major issues, and proposed corrective actions. The PMC will familiarize itself with all design and due diligence documents prepared for the MFF Project 1 and Project 2, covering all standard areas linked to project technical, financial, legal, economic, environmental, social, governance, fiduciary oversight, management, and institutional matters, ensure that all project related due diligence information is accurate and up-to-date, and present any updates to MOTC and ADB for approval as necessary.
Construction supervision. The PMC will carry out all construction supervision activities for civil works for the Project, comprising upgrading and widening of the existing M1 Ashtarak to Talin road from 2-lane single carriageway to 4-lane dual carriageway road from Km 29+600 to Km 71+500. (Section 1), improvements of road safety measures of the existing M2 Yerevan to Ararat 4-lane road from Km 9+312 to Km 47+ 400 (Section2) and rehabilitation of the existing M1 Yerevan to Ashtarak road from Km 18+370 to Km 29+773 (Section 3) in compliance with the requirements of international standards and best practices for highway construction.
(i) The civil works will be procured under ADB's International Competitive Bidding procedures and executed using FlDIC Conditions of Contract for Construction (Multilateral Development Bank Harmonized Edition, 2010). The PMC shall assume all the powers, duties and responsibilities assigned to the "Engineer" under such civil works contract. The construction period for the contract will be 36 months plus 12 month defects liability period for Section 1 and 18 months plus 12 month defects liability period for Sections 2 and 3. (ii) The PMC will review the detailed engineering designs prior to the start of civil works. The PMC will prepare a report where his concurrence with the designs is stated and/or modifications are proposed. If modifications are proposed, the PMC should endeavor to adhere as close as possible to the scope of the civil works contract as defined in the specifications and bills of quantities. All proposed modifications should be discussed and agreed with MOTC and ADB prior to commencing with the modifications.
3. To the extent not already included in the scope of its responsibilities as the "Engineer" under the civil works contract, the PMC shall be responsible for: (i) Assist MOTC to negotiate the mutually beneficial terms and conditions as well as construction schedule; (ii) Ensure the contractor adheres to the agreed schedule at the time of signing the contract for submitting all documents (performance bonds, insurance policies, license, etc.) completing the Engineers facilities, and any other requirements as stipulated in the specifications and the civil works contract; (iii) Prepare an IPC submission and review schedule in consultation with the contractor, and hold joint monthly meetings with MOTC to review the contractor's claims, the consultant's verification of the accuracy of the claims and withdrawal applications, and agree on their submissions to ADB; (iv) Review the geometry, pavement, bridge, and other structural designs, specifications, construction method etc, ordered by the employer and revise or update if possible to achieve greater economy, safety, reliability, and/or durability; (v) Prepare working drawings, and provide written confirmation to the Employer indicating the acceptance of ownership of the drawings; (vi) Daily presence on site such as but not limited to inspectors of works, surveyors, material technicians and senior Engineers' staff. Day-to-day quality control and quantity measurements of the works carried out;
49
(vii) Planning and execution of construction supervision and contract administration, including effective and regular supervision of the works, maintenance of project records, correspondence and diaries, as well as quality control testing to ensure that the Works are executed in accordance with the Contract; (viii) Approve and monitor the contractor's construction program and method statements, verifying that they are consistent with the project implementation schedule and with the design solutions, the requirements of existing normative documents, technological sequence and safety of construction, informing about it in a written form to MOTC, with a copy to ADB; (ix) Develop quality and quantity assurance control manual and conduct daily monitoring in accordance with the manual, which will be oriented to the day by day quantity and quality control and approval of the contractor’s works. (x) Provide survey data to the contractor and checking the contractor's setting-out of the works and inform of its accuracy in a written form to MOTC, with a copy to ADB; (xi) Inspect, prepare inspection acts, and test all materials and works to ensure compliance with specifications and giving immediate notice to the contractor in the event that such materials and works fail to comply with the specifications. Copies of notices will be included in the quarterly progress reports to MOTC and ADB; (xii) Inspect regularly the contractor's construction equipment, installations, housing, medical facilities, etc. and prepare inspection acts, and ensure that they are adequate and in accordance with the terms and conditions specified in the contract for the works; (xiii) Maintain, check, record and approve the daily progress records produced by the contractors on work progress, labor, equipment, major construction materials, at site, work accomplished, weather, river conditions, accidents as well as any other events affecting projects cost or implementation conditions of the Project. (xiv) Ensure that road safety design requirements are implemented in accordance with the contract and prepare road safety audits as shown below; (xv) Issue notices to the contractor advising of any noncompliance with environmental mitigation measures, as set out in the contract documents. Copies of all notices should be provided to MOTC and ADB at the time of issue. Before issuing such notices, the PMC should, as appropriate, have advised the contractor of the noncompliance and given an opportunity to the contractor to make good any adverse impact prior to the notice being issued; (xvi) Establish efficient procedures for verifying contractor performance and reporting progress and problems in a timely manner, including quality control reports, quantity survey records, requests for variation or change orders, requests for time extension, and contractor's claims and invoices. The PMC will prepare the necessary procedures and present them to MOTC and ADB for approval; (xvii) Ensure that the contractor does not involve child labor in the execution of civil works contracts in accordance with the provisions of the contract agreement; (xviii) Prepare and issue to MOTC and ADB the following reports, whose format and content should be acceptable to MOTC and ADB: an inception report, monthly progress reports, a detailed quarterly report, and a project completion report; (xix) Certify payments for the works against the relevant bill of quantities and issue the Interim Payment Certificates, the Final Payment Certificate and other certificates, including Taking Over Certificate, as required under the civil works contract; (xx) Keep MOTC and ADB timely informed of implementation problems that could jeopardize the project objectives and recommend on how those objectives can be safeguarded; (xxi) Evaluate claims, disputes, extensions of time, and the like, including issuing variation orders list and quantity of additional works for MOTC's and ADB's
50
approval as appropriate and in line with the limits placed on MOTC's authority, as well as advising MOTC on all matters relating to the execution of the works; (xxii) Issue of the Engineer’s decisions/instructions as appropriate under the civil works contract; (xxiii) Provide timely assistance to the contractor in all matters related to interpretation of the contract documents, ground survey controls, planning, quality control testing and other matters relating to Project ; (xxiv) Provide MOTC with complete records, reports and ―as-built‖ drawings for the works; (xxv) Conduct a complete joint review of the works with all stakeholders and ADB, as well as a safety audit, prior to handover of the site to MOTC; (xxvi) Following the issue of the Taking Over Certificate, during the balance of the contract period inspect and approve the execution of the outstanding works (if any), as well as the rectification of any defects or damage - advise on any extension to the contract period that may be required for such works; (xxvii) To a reasonable amount, if so required by MOTC, provide any of the following additional services within the contract amount (i) prepare reports, including technical appraisals, additional contract documentation, and/or reviewing and commenting on the contractor's proposals, as may be required for any additional work required for the successful completion of the Project; and (ii) provision of any other specialist services as may be required from time to time; (xxviii) For sake of clarity, to the extent that duties of the PMC described in paragraph 3 hereof directly conflict with such PMC's obligations under the civil works contract, then the PMC shall be required to comply with the requirements specified in the civil works contract; (xxix) The PMC will be on its behalf responsible for the contractor’s low-quality works and/or low-quality materials used by the contractor if such works or materials have already been accepted and approved by the PMC.
Road Safety Audits (RSA)
Road Safety Audits of Detailed Designs. The PMC will conduct a design RSA prior to the start of civil works. The PMC will: a) conduct pre-audit meetings with the MOTC and detailed design consultant to review project information and drawings; b) carry out combined with field visits to the project road both during daytime and nighttime, together with representatives of MOTC, and other representatives (e.g., police) as appropriate; c) conduct office road safety audit analysis and preparing a concise Road Safety Audit Report with the list of road safety issues identified (if any), risk for each issue assessed, and specific countermeasures proposed to be incorporated into detailed designs; d) present RSA findings and recommendations to MOTC and ADB with cost estimates; e) revise the designs as agreed with MOTC and ADB incorporating the necessary road safety improvements f) monitor the implementation of the RSA on the ground.
Ensuring Road Safety During Construction. The PMC will review and approve, in coordination with MOTC, traffic control plans prepared by the contractor and ensure compliance with all applicable road safety standards, guidelines and regulations, before commencement of road works. The PMC will ensure adequacy of measures in contractor’s traffic control plans for the safety of all road users, including vulnerable road users, under different traffic, weather, and daytime/nighttime conditions. The PMC will, among others, verify design of temporary
51 diversions and traffic management arrangements; adequacy of signing, marking and delineation at work zones; adequacy of road safety devices (e.g., temporary and movable barriers, crash cushions, truck mounted attenuators, etc) and proper maintenance of the devices; and adequacy of personal protective equipment for the workers. The PMC will regularly inspect road safety audit work zones under traffic, and coordinate and control the timely addressing of all road safety issues. The PMC will be responsible for reporting to MOTC and ADB, and following up on road safety issues/lapses as appropriate.
Post-Construction Road Safety Audits. The PMC will conduct a post-construction road safety audit once the construction works have been completed and the road section is fully open to traffic. The PMC will observe the traffic and identify road safety issues, including those that might have not been obvious during previous road safety audits. The PMC will identify the list of road safety issues and provide recommendations to address them, submit them to MOTC, with a copy to ADB, for review and action, and subsequently check/monitor the implementation of recommendations as endorsed by the MOTC.
Accident Analysis and Mitigation. The PMC will also conduct analysis of road collisions occurred on project roads during project implementation, if any, identify road/traffic management related causes, and recommend specific road safety countermeasures for review and endorsement by MOTC and ADB.
C. Implementation Arrangements
4. MOTC will be the executing agency (EA) for the Investment Program. The PMC will be recruited by MOTC (Employer). The MOTC will appoint a Project Director who will coordinate the implementation of the Project on behalf of MOTC. The Project Director will be a qualified staff of MOTC with experience in project management and working knowledge of English language. The PMC will introduce a suitable management information system to manage the Project. The PMC will prepare quarterly progress reports and will submit them to MOTC and ADB within 2 weeks from the end of the related quarter. The PMC will also submit other required performance and monitoring reports twice a year. Overall progress and compliance with conditions of the loan agreement will be monitored regularly with periodic reports to MOTC and ADB, consistent with existing project implementation requirements. Reports will include evaluation of issues and will recommend remedial actions. MOTC will recruit external individual consultants to audit a random sampling of documents issued or approved by the PMC.
D. Experience and Qualifications Required of the PMC and Specialists
5. The services of the PMC will be provided through an international, professional project management consulting firm. If the firm is in association or JV with another firm all the parties of the given association or the JV shall be jointly or severally liable under the contract.
6. The PMC should have extensive and proven experience in project administration, financial management, procurement, design control, and project performance management, highway design, construction supervision, preparation of technical specifications, quality control, contract management and dispute resolution of similar type and size international contracts. The PMC should also have knowledge and experience in reviewing environmental assessments and resettlement action plans for road construction projects in accordance with guidelines of international donor organizations (ADB, WB, etc.). The PMC team shall comprise of specialists that have obtained, at least, a bachelor's degree from an accredited university, and have experience in similar international projects. The (i) Team Leader/ PMC Coordinator, (ii) the
52
Senior Resident Engineer/Highway Design Engineer, and (iii) the International Financial Specialist and Accountant should be Regular Staff of the lead firm or its international associates9. The Team Leader and preferably at least five other international specialists should have a valid (active) membership in a professional organization and undergone recent professional development training related to his or her field. The curriculum vitae of the specialists should contain information of the assignment they have successfully completed in the last 5 years, with complete names and addresses of the clients and the name and contact information of the immediate supervisors, and the number(s) of the membership(s) and the name(s) of the issuing organization(s). The Team Leader/ PMC Coordinator and the Senior Resident Engineer/Highway Design Engineers should provide letters from at least two clients in the past five years, confirming successful completion of the assignments. MOTC may contact randomly selected clients of the first ranked firm, for verification of the information provided by the firm, prior to signing the contract.
E. Selection Method and Criteria
7. The lead proposing firm may appear on its own or form associations or joint ventures with one or more international and national firms with an established record of technical and project area experience. The firm/ association/ JV is required to submit a full technical proposal, which will be evaluated according to the quality- and cost-based selection (QCBS) method described in ADB's Guidelines on the Use of Consultants (2010 as amended from time to time). A weighting system of 90% for quality and 10% for cost will be applied. The MOTC will engage the PMC on a mix of time-based (80 % of the contract price) and lump-sum based (20% of the contract price) contract. Payments for activities such as procurement assistance, financial management, monitoring and construction supervision will be made purely on time-basis. The lump-sum based portion of the contract will be tied in payments for the following tasks:(i) Submission of the Inception Report (10% of the lump-sum portion) acceptable to MOTC and ADB with the content described in paragraph 10 of the ToR. The inception report shall also include the critical path of the overall project implementation. The Inception report shall be submitted within one month of commencement of the services; (ii) PMC’s hand over of the operational Project Performance Monitoring and Evaluation System and report (30% of the lump-sum portion), acceptable to MOTC and ADB, populated with the updated DMF targets and indicators, baseline data for these targets and indicators, financial and procurement capacity assessment of MoTC, capacity building plan for MoTC inclusive of all aspects of project implementation, as well as capacity building for operation and maintenance of the project roads after construction, The Project Performance Monitoring System report shall be submitted within the first three months after commencement of the services;; (iii) Operation and maintenance of the Project Performance Monitoring and Evaluation system (5% of the lump-sum portion). Payment shall divided to and be made on a quarterly basis; (iv) Each Road Safety Audit Report submitted (15% of the lump- sum portion). Payment shall be divided into a. pre-construction RSA (50%), b. construction time RSA including Accident Analysis and Mitigation report (25%), and c. post construction RSA (25%). Payments shall be made upon submission of the reports acceptable to MOTC and ADB; (v) Conducted training for capacity building (20% of the lump-sum portion). The lump sum portion of the Contract Price will be paid after submission of Capacity Building Report on completion of a series of training programs for the MOTC staff on procurement, financial management, performance monitoring and evaluation, and ADB safeguard policies and procedures. The Capacity Building Report, acceptable to ADB and MOTC, shall be submitted within one year of commencement of the PMC services; (vi) Submission of mid-term PPMER (5% of the lump- sum portion). The mid-term PPMER shall be submitted within two years of commencement of the services; (vii) Submission of final PPMER upon project completion (5% of the lump-sum portion). The final PPMER shall be submitted at the end of the PMC services; (viii) Submission
9 Staff having Regular Employment Status with the lead firm or its international associates for a minimum of 3 years is considered Regular Staff
53
of the Project Completion Report (PCR) acceptable to MOTC and ADB (10% of the lump-sum portion). The PCR shall be submitted at the end of the PMC services. Additionally, all out of pocket expenses such as per diem, hotel expenses, travel etc. will be made on a lump-sum basis. The PMC shall indicate a breakdown of these items in their proposal. The PMC team will have 180 person-months of international and 439 person-months of national expertise as set out in Section F below. The PMC may propose alternative arrangements, which, subject to assessment and approval by MOTC and ADB, will provide services of an equivalent or better quality.
54
F. PMC Team Composition
(a) International Specialists (180 person-month inputs)
Minimum Preferable Project Inputs General Specific Area of Special Skills and Knowledge, Title (person- Experience experienc Indicative List of Tasks Assigned Specialization but not limited to months) (Years) e (Years) All administration and managerial work related to all aspects of the Project, including construction supervision, procurement, financial management, Overall Project Management and project performance monitoring, loan administration, procurement, covenants, safeguards, as well as project performance management management of the whole PMC staff and capacity building Project Coordination and liaison with Reporting to the MoTC and ADB Management and MOTC, ADB and other Permanent liaison and advice to the Administration, stakeholders MoTC and ADB Team Procurement and FIDIC Leader/ Quality Control, Early identification of issues and 20 12 Familiarity with ADB procurement, PMC 40 p-m Contract Law, and proposing mitigation and preventing safeguards and financial Coordinator FIDIC Contract measures management guidelines Administration, Evaluation and settlement of Resolution of disagreements of MoTC Engineering and variations and claims and Contractors Capacity Building Project Monitoring and Other tasks needed for timely and performance evaluation successful implementation of the Capacity Building Project Reporting At all stages raise the MoTC's capacity and awareness of international standards of managing contracts with similar scope and size Coordination and liaison with Overall responsibility for construction MOTC and other stakeholders contract in the role of the Engineer's In-depth overall knowledge in representative Civil Engineering-- detailed design and construction Highway Design Review of designs, specifications, Senior supervision for large, medium and Construction construction methods, etc Resident sized and small highway projects 36 p-m Management and Engineer/Hig 20 10 in flat and mountainous terrain Check and ensure that approved time Certified hway Design Latest AASHTO pavement schedules &quality assurance plans of Professional Engineer material and mix design methods the Contractors are implemented Engineering properly License In depth knowledge on structures and bridge design, construction, Approve payment certificates rehabilitation and repair Issue variation orders Due diligence and design review
55
and safety auditing Inspect completed works and prepare Project management software certificates State of the art QC/QA Maintain records, prepare reports implementation Multi-disciplinary team leadership At all stages raise the MoTC's capacity and awareness of international Reporting standards of road engineering Review of designs, specifications, construction method, etc. Review traffic control plans prepared by In-depth overall knowledge in the contractor detailed design and construction Verify design of temporary diversions Civil Engineering-- supervision for large, medium and traffic management arrangements Highway Design sized and small highway projects Road Safety and Construction in flat and mountainous terrain Regularly inspect road safety audit work and Management, Road Due diligence and design review zones under traffic Construction 9 p-m 20 10 Safety Audits and and road safety auditing and Conduct a post-construction road safety Safety Certified coordination with MOTC and other audit, identify road safety issues and Specialist Professional stakeholders provide recommendations to address Engineering Project management software them License State of the art QC/QA Check/monitor the implementation of implementation recommendations Reporting Raise the MoTC's capacity and awareness of the international standards of road safety Carry out all procurement activities under the Project set up and operate a web-based multi language tender platform on base of a project communication management Coordination and liaison with system Civil Engineering— MOTC Procurement, FIDIC Post announcements, receive and Contract Law, and Civil works procurement and evaluate bids/proposals, manage bid Procurement FIDIC Contract contract negotiation securities and 15 7 Administration, Familiarity with ADB procurement Prepare evaluation reports and obtain Contracts 2 p-m Certified License or guidelines MoTC and ADB approvals as per ADB’s Specialist Membership in Evaluation and settlement of Guidelines Professional variations and claims Negotiate, administer contracts Association Procurement capacity assessment including management of performance and reporting securities, FIDIC terms, variation orders, dispute resolution, etc. Assess the MoTC staff procurement capacity and develop and implement capacity development plan
56
Review of designs, specifications, materials requirements, construction Coordination and liaison with method,etc. MOTC Civil Engineering— Control and advice on asphalt/concrete Asphalt and Asphalt and cement concrete plant construction and operations Concrete pavement design, construction Quality, Pavement Design supervision and maintenance in Advice site inspectors on the Pavement, and Construction cold and hot climates requirements of materials testing, Geotechnica Supervision, and Latest AASHTO pavement Manage Contractors’ material surveys 30 p-m 15 7 l and Professional material and mix design methods in the project Materials Engineering Review, update and design Provide recommendations to MoTC on Engineer License or optimization pavement maintenance Membership in Asphalt and cement concrete plant Professional construction and operation Raise the MoTC’s capacity and Association Hotmix paving and pavement awareness on international standards maintenance for pavement design, construction and maintenance
Review designs, specifications, Civil Engineering— construction methods, etc. for bridges Structural and structures Engineering with experience in Coordination and liaison with Manage inspections of bridges and design and MOTC structures constructions with due Bridge, supervision of Bridge and hydraulic structure attention to seismic resistance Structural construction of Inspections and design requirements and 25 p-m 15 7 bridges, culverts Retaining wall design Provide recommendations to MoTC on Hydrological and other Seismic retrofitting bridge and structures conditions Engineer structures. Design review assessment and maintenance Engineering Bridge condition assessment and Raise the MoTC’scapacity and License or maintenance awareness on international standards Membership in for bridge and structures design, Professional construction and maintenance Association Review and update due diligence documents of the Project 2 in the Coordination and liaison with course of project implementation MOTC, ADB and other Review DMF performance targets to stakeholders update and complement with poverty Transport Transport Due diligence review and socioeconomic indicators Economist 15 7 4 p-m Economics Project performance management design a web-based project system performance monitoring system Training Reporting Compile baseline data for all performance targets and indicators Carry out necessary surveys and
57
regularly collect required information and update the data bases Quarterly update Performance Indicator Framework Measure and report to MOTC and ADB progress of achieving the DMF performance targets at the project midterm and completion stages; Raise the MoTC’s capacity and awareness of common international practices for economic assessment, as well as monitoring projects performance in all stages of implementation Carry out financial management and Financial management and administration of the administration Maintain Projects accounts Maintenance of project accounts Prepare financial statements and Preparation of financial statements withdrawal applications and submit for Financial and withdrawal applications MoTC approval Specialist Financial Specialist 15 7 Review of financial audit reports Assist MOTC in review of financial audit and 10 p-m Accounting reports Accountant Financial management capacity assessment and reporting Assess the MoTC staff financial Coordination and liaison with management capacity and develop and MOTC and ADB implement capacity building plan Reporting Provide quarterly financial reports to MoTC and ADB Assess the institutional structure and regulatory framework of the MoTC Institutional assessment Identify all institutional, governance, Capacity building and training staffing gaps Capacity Institutional Coordination and liaison with Develop institutional strengthening and Building 2 p-m 15 7 Development and MOTC, ADB and other capacity building plan Specialist Capacity Building stakeholders Increase the MoTC’s awareness of the Reporting international best practices of institutional management of the transport sector Coordination and liaison with Review environmental due diligence and MOTC, ADB and other EARF/EIA/EMP stakeholders Monitor EMP implementation by Environmental due diligence and contractor, including implementation of Environmental Environmental 15 7 EIA/EMP review mitigation measures Specialist 12 p-m Science Environmental impact Conduct environmental impact investigations investigations Environmental Monitoring Report violations to MoTC Construction and operational noise Prepare and submit quarterly
58
abatement environmental monitoring reports to Reporting MoTC and ADB Familiarity with ADB and Increase the MoTC’s capacity and Government environmental awareness of the international best safeguard requirements and practices and ADB policies of legislation environmental monitoring of projects at all stages of implementation
Conduct selective household surveys and Coordination and liaison with participatory research to monitor MOTC, ADB and other socioeconomic impacts on beneficiaries stakeholders Monitor compliance with major project Review of LARP and social due assurances (refer to project and loan diligence documents_ Social LARP implementation monitoring As necessary review the implementation Developmen Worker compensation and benefits ready LARP prepared by the Project 1 Social Science – t, assessment Technical Supervision Consultant gender analysis, Resettlemen 15 7 Community participation Monitor and support LARP 8 p-m household and user t and programming implementation by the MoTC and Project surveys Gender Gender assessment 1 Technical Supervision Consultant Specialist HIV and human trafficking Provide quarterly progress reports awareness campaigning Increase the MoTC’s capacity and Reporting awareness of the international best Familiarity with ADB and practices and ADB policies of social Government social safeguard monitoring at all stages of project requirements and legislation implementation
Highway/Electrical Coordination and liaison with Electrical Engineer - relevant Electrical works Government/Employer Street experience in road Road lighting design Lighting 2 p-m 10 5 and street lighting Supervision of installation of road lighting Specialist design and Supervision of installation of electrical installation wiring and appliances
59
(b) National Specialist (439 person-month input).
Minimum inputs Experience Special Skills and Indicative List of Tasks Title (person-months) Knowledge Assigned Coordination and liaison Coordinate and liaise with with MOTC and other MOTC and other stakeholders stakeholders Project Management and Provide all the construction supervision professional and logistic Design review and safety support to the team Deputy Team 15 years in auditing leader/project manager Leader/Highways 40 p-m Road Construction and/or Road Design and/or QC/QA review Manage the activities Engineer Road Construction Management Procurement national specialists Report writing and oral Review highway design presentation drawings, and prepare as Familiarity with ADB built drawings procurement, safeguards Any other tasks requested and financial management by the team leader/project guidelines manager Provide all the professional and logistic support to the team leader/project manager, Senior Resident Checking of maps and Engineer/Highway Design
topographical surveys Engineer and Road Highways Design 10 years in Design review and road Safety/construction Safety and Road Safety/ Road Construction and/or Road Design and/or safety auditing Specialist Construction 20 p-m Road Construction Supervision Project management Conduct regular visits to the Safety Specialist software project sites and report on
QC/QA review the progress/violations to the relevant international specialists Manage the activities of site inspectors Asphalt and cement Provide all the professional concrete mix design and logistic support to the Quality, Asphalt and cement team leader/project Pavement, 15 years in concrete plant construction manager, international geotechnical and Road Pavement (asphalt and concrete) and operation Quality/Pavement/ 30 p-m Materials Construction and/or Asphalt and concrete Hot mix paving and Geotechnical/Materials Engineer Pavement Design pavement maintenance Engineer, Senior Resident and work supervision Engineer/Highway Design Laboratory and in-situ Engineer and Road Safety / testing Construction Safety
60
Specialist Conduct regular visits to the project sites and report on the progress to the relevant international specialists Manage the activities of site inspectors Provide all the professional and logistic support to the team leader/project manager, international Bridge and Structural Bridge and hydraulic Engineer, Senior Resident structure design Engineer/Highway Design Bridge, Structural 15 years in Bridge condition Engineer, Road Safety / and Hydrological Road Artificial Structures Construction and/or 25 p-m assessment and Construction Safety Engineer Artificial Structures Design construction supervision Specialist Sampling and testing Conduct regular visits to the project sites and report on the progress to the relevant international specialists Manage the activities of site inspectors Permanent be present at Supervision of works project sites 8 Site Inspectors Sampling Conduct sampling and and Quality 10 years in Laboratory and in-situ testing of construction Control 216 p-m Road Construction Quality and Quantity Control testing materials Specialists Quality Control Report testing results to the Reporting relevant international and national specialists Environmental due Provide all the professional diligence and EIA/EMP and logistic support to the review team leader/and the Environmental impact international environmental investigations specialist Environmental Monitoring Conduct regular visits to 10 years in Environmental Construction and project sites 12 p-m Environmental Science — environmental impact Specialist operational noise Prepare reports to the assessment abatement international environmental Report preparation specialist Familiarity with ADB and Government environmental safeguard requirements and legislation Social 15 years in Review of LARP and social Provide all the professional Development, 10 p-m Social Science – household and user surveys due diligence and logistic support to the
61
Resettlement and LARP implementation team leader/and the Gender Specialist monitoring international social Worker compensation and development, resettlement benefits assessment and gender specialist Community participation Conduct regular visits to programming project sites Gender assessment Prepare reports to the HIV and human trafficking international social awareness campaigning development, resettlement Familiarity with ADB and and gender specialist Government social safeguard requirements and legislation Supervision of works Report measurement Sampling results to the relevant Quantity survey and international and national measurements specialists Quantity Surveyor 10 years in Quality Control Attend measurements 30 p-m Road Construction Quality and Quantity Control Checking of contractors Advise on methods of claims measurement Preparation of progress reports Reporting Review environmental due diligence and EARF/EIA/EMP from archaeological perspective Archeological impact Monitor archaeological part investigations of EMP implementation by Dealing with cultural contractor, 15 years in heritage Conduct archaeological Archeological surveys and/or assessments Knowledge of Armenian Archaeologist investigations at the project 20 p-m history, archaeological sites during construction sites and legislation Record and report Monitoring of archaeological finding to the archaeological excavations Team Leader, MoTC and Report writing Ministry of Culture Prepare and recommend archaeological plan for the findings Financial management and Provide all the professional administration and logistic support to the Financial and 15 years in Maintenance of project team leader and Accounting 36 p-m Financing and/or Accounting accounts international financial Specialist Preparation of financial specialist and accountant statements and withdrawal
62
applications Review of financial audit reports Financial management capacity assessment and reporting
63
G. Tasks and Responsibilities of Each Team Member
1. International Staff:
Team Leader/ PMC Coordinator
The Team Leader/ PMC Coordinator should be regular staff of the lead firm or its international associates as described in Section D, paragraph 6 above. He/She will be responsible for overall project management in performing scope of work indicated in section B. of the Terms of Reference for the Consulting Services. The specific focus of the Team Leader/ PMC Coordinator will be early identification of issues and proposing mitigation or preventive measures in all aspects of the scope of work related to various project activities. The Team Leader/ PMC Coordinator will be responsible for early identification of issues potentially leading to claims and increase of costs (especially in civil works contracts) by means of proper management of the construction supervision component and personal review of contracts’ progress. Special attention will be given to claim/ dispute resolution activities related to price escalation, as well as prevention of delays, possibly caused by right of way issues (if any), deficiencies in designs (if any), construction specifications and others. The Team Leader/ PMC Coordinator will be responsible for preparation of variation orders and their submission for the approval to MOTC and ADB. The Team Leader/ PMC Coordinator will also have advisory role on potentially expected or actual claims. The Team Leader/ PMC Coordinator will assist the Project Director and MOTC in contract negotiations for the civil works, ensuring that contract documents are in a manageable order, and as per ADB and MOTC requirements.
Qualifications. The Team Leader/ PMC Coordinator will have a minimum of master’s degree in civil engineering or other relevant field from a recognized university, with at least 20 years of experience, In line with the qualification requirements specified in section F above the Team Leader/ PMC Coordinator will have strong experience in Project Management and Administration, Procurement and Quality Control, Contract Law, and FIDIC Contract Administration, Engineering and Capacity Building. A minimum of 12 years project specific experience in similar large highways and infrastructure projects both in developed (6 years) and developing (6 years) countries, preferably in Central Asia and Caucasus is required. The candidate should hold a relevant Certified Professional License and a membership in a relevant professional association. Good communication, report writing and relationship building skills required. Knowledge and experience in Central Asia and Caucasus and of locally spoken languages will add an advantage.
Senior Resident Engineer/ Highway Design Engineer
The Senior Resident Engineer/ Highway Design Engineer should be regular staff of the lead firm or its international associates as described in Section D, paragraph 6 above. He/she will assist the Team Leader/ PMC Coordinator on the overall project management. The Senior Resident Engineer/ Highway Design Engineer will be responsible to the Team Leader/ PMC Coordinator for coordinating and supervising the construction supervision team and ensuring effective and timely implementation of the tasks indicated in section B. of the Terms of Reference for the Consulting Services. The Senior Resident Engineer/ Highway Design Engineer will coordinate and review updated designs and cost estimates prepared by the contractor(s), coordinate and supervise the work of field teams in the delivery of their tasks in accordance with contract conditions, and be responsible for early identification of any events leading to cost increase in implementation of the project, such as timely provision of possession of site to contractor(s), managing efforts of the construction supervision, design reviews and undertaking timely actions to mitigate any inconsistencies in design and tender/ contract documents. Relevant experience in both developed and developing countries is required.
Qualifications. The Senior Resident Engineer/ Highway Design Engineer will have a minimum of a bachelor’s degree in civil engineering from a recognized university, with at least 20 years of experience, 10 years of project specific experience in similar large highways and infrastructure projects in both developed (4 years) and developing (6 years) countries, preferably in Central Asia and Caucasus required. In line with the qualification requirements specified in section F above the Senior Resident Engineer/ Highway Design Engineer will have strong experience in Civil Engineering and Highway Design and Construction Management, and hold a Certified Professional Engineering License and membership in a relevant professional
64 association. Good communication, report writing and relationship building skills required. Knowledge and experience in Central Asia, Caucasus and of locally spoken languages will add an advantage.
Road Safety and Construction Safety Specialist
The Road Safety Specialist will be mobilized as early as possible before the mobilization of contractors and will be responsible to the Team Leader/PMC Coordinator specifically for performing scope of work indicated in section B, Road Safety Audits of the Terms of Reference for the Consulting Services, The specialist will also provide relevant inputs for monitoring, evaluating and reporting project progress and performance, His/her services will include, but are not limited to, (i) conducting road safety audits of detailed designs; (ii) ensuring road safety during construction; (ii) conducting post-construction road safety audits; (iii) identifying causes of accidents occurred over the project implementation period and develop road safety countermeasures reducing risk of reoccurring. The Road Safety Specialist will also be responsible for conducting on-the-job training of the national road safety/construction safety specialist and concerned staff of the MOTC. The input of the expert will be on the intermittent basis, including around [2-3] months in the first year of service to conduct road safety audits of detailed designs and, subsequently, of temporary traffic control for the work zones, along with training of the concerned staff of the MOTC and national road safety/construction safety expert. Subsequently, the Road Safety Expert will provide about [1] month of input per each year during the period of construction and post construction/defect liability period to continue his/her tasks and to ensure that road safety audits and accident analysis and mitigation work by the national road safety expert is done properly. During the final year of construction and defect liability period the Road Safety Specialist will conduct post construction road safety audits of the completed road sections under traffic.
Qualifications. A senior level engineer with graduation in civil engineering, preferably with master’s degree in traffic management and road safety from a recognized university, and/or extensive road safety and road safety audit training. Preferably 20 years of experience, of which 10 years as a Road Safety Expert or similar capacity for construction supervision consultancy contracts of major highway projects and/or road safety engineering, auditing and analysis for major highways, including experience in developing and implementation of road safety engineering countermeasures, conducting road safety audits, collision analysis, road safety monitoring and evaluation. Relevant experience in both developed (5 years) and developing (5 years) countries, preferably in Central Asia and Caucasus is required. The candidate should hold a Certified Professional Engineering License and a membership in a relevant professional association. Knowledge of locally spoken languages will add an advantage. Regular employment with the lead firm or its international associates is a plus.
Procurement and Contracts Specialist
The Procurement and Contracts Specialist will be responsible to the Team Leader/PMC Coordinator for performing scope of work indicated in section B, para.2 Procurement and Project Management, and construction supervision as applicable, of the of the Terms of Reference for the Consulting Services. The Procurement and Contracts Specialist will assist the MOTC in evaluating and processing all claims for additional payments or extensions of time submitted by the contractor(s)., He/she will assist the MOTC in Dispute Adjudication proceedings and give firm opinion on any claim which the Contractor(s) may put forward, by drawing up report including all the elements on which the judgment is based. He/she shall update procurement plan as and when required, record and archive complaints on procurement, and advise the MOTC for debriefing, keep all procurement records in proper order, acceptable to the MOTC and the ADB, and provide extensive training to national consultants staff on all types of procurement of goods, works, and services in accordance with ADB Procurement Guidelines. The specialist will help the Team Leader/PMC Coordinator in establishing efficient procedures for verifying Contractor performance and reporting progress and problems in a timely manner, including quality control reports, quantity survey records, requests for variation or change orders, requests for time extension, and Contractor’s claims and invoices. Regular
65 employment with the lead firm or its international associates is a plus.
Qualifications. A senior level engineer with preferably a masters degree in engineering or quantity surveying from a recognized university. Preferably 15 years experience including Project and Contract Administration, Evaluation of Extension of Time & Cost Claims of which 7 years of project specific experience, using the Federation International Des Ingenieurs Conseils (FIDIC) based contract documents, preferably in at least three projects of a similar nature and magnitude. . Relevant experience in both developed (3 years) and developing (4 years) countries, preferably in Central Asia and Caucasus required. He/she should be familiar with ADB procurement guidelines, national standards and terms of contract administration The candidate should hold a Certified License or Membership in a relevant Professional Association. Knowledge of locally spoken languages will add an advantage.
Quality, Pavement, Geotechnical and Materials Engineer
The Quality, Pavement, Geotechnical and Materials Engineer will be responsible to the Team Leader/PMC Coordinator for performing scope of work indicated in section B, Construction Supervision of the of the Terms of Reference for the Consulting Services. This position requires a senior Civil Engineer, with preferably 15 years of professional engineering experience, including preferably no less than seven years establishing quality assurance programs in highway construction projects using modern highway construction technology in both developed and developing countries. The candidate should have demonstrated capability of supervising the setting up, organization and layout of the various Contractors’ field laboratories; monitoring the mobilization of the testing equipment to ensure that the laboratories are adequately equipped and capable of performing all the specified testing requirements of the Contracts; and supervising the setting-up of the various Contractors’ rock crushers and bituminous and/or cement mixing plants to ensure that the specified requirements for such equipment are fully met. The Expert will supervise the testing and evaluation of highway construction materials used in modern highway construction techniques. The Quality, Pavement, Geotechnical and Materials Engineer’s experience should include preferably 7 years on projects of a comparable nature in Asphalt and concrete Pavement Design, construction supervision and maintenance in developed (2 years) countries and on projects in developing (5 years) countries, preferably in Central Asia and Caucasus. The candidate must be thoroughly familiar with all the standard laboratory testing procedures specified in the Contract Documents and must have had past experience in pavement design and bituminous/cement mix design works as well as earth works. The Expert shall also be familiar and have experience in geotechnical design, including collection of data, analyzing and reporting to understand and mitigate operational geotechnical risk in a pre-construction environment and during construction. The expert shall conduct training to the national experts and to MOTC staff as necessary. Regular employment with the lead firm or its international associates is a plus.
Qualifications. A senior level engineer with preferably no less than a bachelor’s degree in civil engineering from a recognized university. Minimum of 15 years experience as described above in Civil Engineering—Asphalt and concrete Pavement Design, construction supervision and maintenance. Certified License or Membership in a relevant Professional Association required.
Bridge,Structural and Hydrological Engineer
The Bridge,Structural and Hydrological Engineer will be responsible to the Team Leader/PMC Coordinator for performing scope of work indicated in section B, Construction Supervision of the of the Terms of Reference for the Consulting Services. This position requires a qualified bridge and structural engineer with preferably no less than 15 years experience in bridge and structural engineering and hydraulics, including preferably no less than 2 years of project specific assignments in developed countries, and 5 years in developing countries including Asia. The candidate should have a thorough understanding and experience with international ―best practices‖, and of modern bridge and other structural construction technology and hydrological
66 calculations. The candidate should be capable of monitoring the contractors’ bridge construction, rehabilitation and repair works to assess and determine the need for adjustment of the works specified in the Contracts, and, as required, provide working drawings, specification details and instructions to the Contractors for any bridge within the construction site for works which are found during the construction period to require rehabilitation but are not already specifically scheduled for rehabilitation under the contract. The expert shall conduct training to the national experts and to MOTC staff as necessary. Regular employment with the lead firm or its international associates is a plus.
Qualifications. A senior level engineer with preferably bachelor’s degree in civil engineering from a recognized university. Preferably 15 years experience as described above in Civil Engineering, bridge and structures design, including hydrological design and culvert dimensioning, construction supervision and maintenance. Certified License or Membership in a relevant Professional Association required.
Transport Economist
The Transport Economist will be responsible to the Team Leader/PMC Coordinator for performing scope of work indicated in section B, para.2 Monitoring, and Evaluation and Reporting of the of the Terms of Reference for the Consulting Services. The Transport Economist may be required to do any additional works as per the Team Leader/ PMC Coordinator instruction. The expert shall conduct training to the national experts and to MOTC staff as necessary.
Qualifications. The Transport Economist will be a qualified professional transport economist with preferably master’s degree in economics from a recognized university, holding a Certified License or Membership in relevant Professional Association. The candidate should preferably have no less than 15 years experience in transport economics of which 7 years in similar projects in formulation and preparation (including economic evaluation in accordance with ADB guidelines) and monitoring and evaluation of transport projects, including roads in developed (2 years) and developing (5 years) countries, preferably in Central Asia. The candidate should be fully familiar with project performance monitoring systems (PPMS), have proven experience on establishing a web-based PPMS, based on the design and monitoring framework (DMF) as per ADB’s requirements. The expert shall conduct training to the national experts and to MOTC staff as necessary. Knowledge of locally spoken languages will add an advantage. Regular employment with the lead firm or its international associates is a plus.
Financial Specialist and Accountant
The Financial Specialist and Accountant should be regular staff of the lead firm or its international associates as described in Section D, paragraph 6 above.. He/she will be responsible to the Team Leader/PMC coordinator for the financial management of the project as specified in Section B. of the Terms of Reference for the Consulting Services. The Financial Specialist and Accountant will ensure financial management procedures are in place and are strictly followed, specifically relating to payments, financial accounting, financial reporting and record keeping. The specialist will assist MOTC in all financial management and administration, including review justifications provided for any variation orders proposed and submitted by the contractors, assist the MOTC on review of withdrawal applications, maintain project accounts, prepare financial statements for submitting them for MOTC’s and ADB’s approval. The Financial Specialist and Accountant will develop an appropriate system for processing of Engineer’s Certificates of civil work contracts and monthly invoices of the construction supervision and keep up to date records of commitments and disbursements. The expert will train national officers and MOTC staff in sound financial control including budgeting, accounting, auditing, preparing withdrawal applications in accordance with ADB's Loan Disbursement Handbook (2007, as amended from time to time) and detailed arrangements agreed upon between the Government and ADB, book keeping, management information system, asset management, and auditing. The specialist will also provide relevant inputs for monitoring, evaluating and reporting project progress and performance,
67
Qualifications. The Financial Specialist and Accountant will have a qualified CIMA or equivalent accountancy qualifications, and preferably have a minimum of master’s degree in business administration or financial management from a recognized university. The specialist shall preferably have no less than 15 years of experience in Financial management and administration, maintenance of project accounts, preparation of financial statements and withdrawal applications, review of financial audit reports, financial management capacity assessment and reporting, of which preferably 7 years in similar projects and geographical areas both in the developed (2 years) and developing (5 years) countries. Knowledge of locally spoken languages and experience in Central Asia and Caucasus will add an advantage.
Capacity Building Specialist
The Capacity Building specialist will be responsible to the Team Leader/PMC Coordinator for (i) assessing the capacity-strengthening needs of the MOTC, line ministries and other agencies to assume new responsibilities and requirements for project administration and management; (ii) develop training programs and material for this purpose and conduct relevant training; (iii) analyze the bottlenecks, clarify the steps needed within the Government, and develop procedures to involve the same qualified staff in project preparation and administration of loan implementation to ensure continuity; (vi) provide a comprehensive project management training program together with the other PMC team members for MOTC staff on ADB’s requirements for procurement, financial management, monitoring and evaluation, and safeguard policies at the beginning of project implementation.(vii) undertake other tasks as requested by the Team Leader/PMC Coordinator. In coordination with other consultants, the Capacity Building Specialist will help achieve the impact/outcome and expected outputs of the project.
Qualifications. The Capacity Building Specialist will preferably have bachelor’s degree in public administration or project management or equivalent; and preferably no less than 15 years of practical experience in Institutional assessment, capacity building and training and portfolio/project management, of which preferably 7 years in similar projects and geographical areas both in the developed (2 years) and developing (5 years) countries. Knowledge of locally spoken languages and experience in Central Asia and Caucasus will add an advantage. Regular employment with the lead firm or its international associates is a plus.
Environmental Specialist.
The Environmental Specialist will be responsible to the Team Leader/PMC Coordinator for performing scope of work related to all environmental issues indicated in section B, of the Terms of Reference for the Consulting Services. The Specialist will prepare a detailed action plan to ensure that the Environmental Management System is established, implemented, maintained and will monitor its performance. He/she will also conduct environmental training and briefings to provide environmental awareness on ADB and the government environmental safeguard policies, requirements and standard operating procedures in conformity with the government’s regulations and international practice for project and MOTC staff; ensure baseline monitoring and reporting of contractor’s compliance with contractual environmental mitigation measures. He/she will monitor the implementation of the IEE, EIA and EMPs and also other environmental issues related to construction and commissioning of the Project. The Environmental Specialist will prepare Environmental Monitoring Reports as requested by the MOTC and ADB.
Qualifications. The Environmental specialist shall preferably hold a Master’s Degree in Environmental Sciences or equivalent with field experience of no less than 15 years in the area of eco systems and environmental protection, conducting environmental audits and environmental monitoring studies related to infrastructure development projects of which
68 preferably 7 years in similar projects and geographical areas both in the developed (2 years) and developing (5 years) countries. Familiarity with ADB and Government environmental safeguard requirements and legislation required. Knowledge of locally spoken languages and experience in Central Asia and Caucasus will add an advantage. Regular employment with the lead firm or its international associates is a plus.
Social Development, Resettlement and Gender Specialist
The Social Development, Resettlement and Gender Specialist will be responsible to the Team Leader/PMC Coordinator for performing scope of work related to all Social Development, Resettlement and Gender issues indicated in section B, of the Terms of Reference for the Consulting Services. He/she will also conduct training and briefings to provide awareness on ADB and the government safeguard policies, requirements and standard operating procedures in conformity with the government’s regulations and international practice for project and MOTC staff on Land Acquisition and Resettlement Plan (LARP) and social due diligence, preparation and implementation monitoring of (LARP) as per ADB requirements, worker compensation and benefits assessment, community participation programming, gender assessment, HIV and other communicable deceases, and human trafficking awareness campaigning etc. He/she will monitor the implementation of the LARF and LARP and also other Social Development, Resettlement and Gender issues, HIV and other communicable deceases, and human trafficking awareness campaigning etc. related to construction and commissioning of the Project. The Specialist will prepare Social Development, Resettlement and Gender Monitoring Reports as requested by the MOTC and ADB.
Qualifications. The Social Development, Resettlement and Gender Specialist shall preferably hold a Master’s Degree in social sciences or equivalent with experience of 15 years in social Science – household and user surveys, review of Land Acquisition and Resettlement Plan (LARP) and social due diligence, preparation and implementation monitoring of (LARP) as per ADB requirements, worker compensation and benefits assessment, community participation programming, gender assessment, HIV and other communicable deceases, and human trafficking awareness campaigning etc. of which preferably 7 years in similar projects and geographical areas both in the developed (2 years) and developing (5 years) countries. Familiarity with ADB and Government social safeguard requirements and legislation Knowledge of locally spoken languages and experience in Central Asia will add an advantage. Regular employment with the lead firm or its international associates is a plus.
Electrical Street Lighting Specialist
The Electrical Street Lighting Specialist will be responsible to the Team Leader/PMC Coordinator for performing scope of work indicated in section B, Construction Supervision of the of the Terms of Reference for the Consulting Services. This position requires a qualified electrical engineer with preferably 10 years’ experience in electrical engineering and street lighting design and supervision of installation in transport projects, of which preferably 2 years of project specific assignments in developed countries, and 3 years in developing countries including Asia. The candidate should have a thorough understanding and experience with international ―best practices‖, and of construction technology. The candidate should be capable of monitoring the contractors’ electrical cabling and lighting installation works to assess and determine the need for adjustment of the works specified in the Contracts, and, as required, provide working drawings, specification details and instructions to the Contractors.
69
Qualifications. An Electrical Street Lighting Specialist with preferably bachelor’s degree in electrical engineering from a recognized university. Preferably no less than 10 years’ experience as described above in electrical engineering and street lighting design and supervision of installation in transport projects. Regular employment with the lead firm or its international associates is a plus.
2. National Staff
The National Specialists as listed in Section F. PMC Team Composition of the Terms of Reference for Consulting Services above will be assisting relevant International Specialists and sharing scope of works assigned to them by the Team Leader/PMC Coordinator and the International Specialists. The National Specialists will observe specific focus of their respective assignments as per the Indicative List of Tasks described in Section F of the Terms of Reference for the Consulting Services.
Qualifications. The National Specialist should be senior level experts in their relevant field and have preferably the minimum number of years of experience as indicated in Section F. PMC Team Composition, National Specialists of the Terms of Reference for Consulting Services. The National Specialists should preferably hold a minimum of bachelor’s degree in their relevant field of expertise, with the exception of the Site Inspectors and Quantity Surveyor who should preferably hold a minimum of a diploma in civil engineering. The National specialists should be familiar and have work experience with ADB or other multilateral financing institution assisted projects of similar size and complexity, for construction supervision consultancy contracts of major highway projects using FIDIC Conditions of contract. The Highways Design and Road Safety/ Construction Safety Specialist should have previous experience in conducting road safety audits of temporary traffic control, and accident and analysis and mitigation will be an advantage. The Archaeologist should have extensive experience in planning, conducting and supervising archaeological excavations, and have knowledge and experience of mitigation measures of culturally and nationally sensitive archaeological findings in Armenia and internationally. The specialist should be member of a recognized archaeological association. Regular employment with the associating firm will add an advantage.
H. Implementation Schedule
8. For the purpose of preparing proposals, the PMC will adopt the following tentative Implementation schedule:
Signing of Consultant's contract February 2012 Award of civil works contract November 2011 Substantial completion of civil works contract December 2014
9. The balance of the contract period following the issue of the Taking-Over Certificate for civil works is 365 days for the Defects Notification Period. The PMC's services are expected to start in February 2012 and conclude in December 2014, taking into account the contract period and the loan closing date, following recommendations to issue the Performance Certificate and any other final certification required under the contracts. The PMC's contract may be extended as agreed with MOTC and ADB.
I. Reporting Requirements
10. The PMC will prepare the following reports in English and Armenian languages and submit them in the number of copies indicated below to MOTC and ADB. The format and content of each report should be agreed with MOTC and ADB. All reports submitted must have signatures of the author, checker and approver, with seals of the PMC firm. For each report submitted an electronic copy will be provided. Electronic copies will be in the format used in
70 their preparation with all links, formulas, and fields active. When software that is internationally ―non-standard‖ has been used, the PMC will provide, at its own cost, two fully licensed copies of this software. For all reports an executive summary will be included.
MOTC ADB Inception Report 5 2 Quarterly Progress Reports 5 2 Monthly Progress (subsequent to Inception Report) 5 1 Project Performance Monitoring and Evaluation 5 2 ReportsRoad Safety Audit Reports 5 2 Project Completion Report 5 2
(a) Inception Report
11. The PMC shall, within one month of commencement of services, submit an inception report setting out the parameters of the consulting services including the main civil works contracts, the program of works, the PMC's site organization chart, quality and quantity assurance control manual, the staffing schedule, firmed delivery schedule of reports, and an updated methodology for the services including the training programs, preparation of the PPME system and the environmental and social monitoring plan. The Report shall give the status at the start of the services of those items of the terms of reference which were already in progress (resettlement, environmental benchmarks etc.) together with the progress of the work to date and a schedule of certified payments, if any. The PMC will indicate the delivery dates of all reports in the Inception Report.
(b) Quarterly Progress Reports
12. The PMC shall prepare quarterly reports presenting a summary status of the Project (schedule, budget, actual and/or potential problems and delays), including illustration as necessary by means of photograph, graphs and tables to provide an up-to-date picture of construction progress during the reporting period. The reports shall be submitted within 30 days of the end of the report period and should include, but not limited to the following: (i) Principal work accomplished during the period covered by the report; (ii) Comparison of actual progress with the original estimated schedule of construction and procurement and with the schedule agreed upon with the contractors and suppliers; (iii) Actual or contemplated major deviations and reasons thereof from original plans or schedules other than changes of a character which would require prior consultation with MOTC and/ or ADB; (iv) Explanations on stoppages or delays, measures necessary to avoid any future delays; an indication of measures required to recover any lost time in the implementation of the Project; and contractual variations; (v) The development of cost estimates and expenditures and the availability of funds to meet the cost of the project; (vi) Conditions which would significantly affect construction schedules or the cost of the project; (vii) Progress made on training; (viii) Progress made and problems associated with environmental matters, any adverse environmental impacts that occur during construction, the corrective measures taken to remedy these impacts, and the steps taken to avoid their recurrence; (ix) Progress made and problems associated with resettlement; and
71
(x) Highlights of all matters requiring action.
(c) Monthly Progress Reports
13. The PMC shall submit monthly progress reports by the 15th of the month following the reporting month, reflecting the progress of the work during the reporting month - the Executive Summary of these reports consisting of (i) one or two pages outlining the position for the complete Project together with (ii) a PPMS report update (quarterly), and (iii) a single page contract status report. These reports should normally include, but not limited to: (i) a work program for the road with a bar chart showing scheduled against actual financial/physical progress by major work item, illustrated by bars and percentage of accomplishment (total and by major work item); the work program and the bar chart (showing the critical path) shall be suitably updated in each progress report; (ii) financial data, updated as appropriate, giving time, cost and financial forecast, a schedule of certified payments, update of quantities and cost estimates for construction and supervision; (iii) summary of implementation progress, the work performed, variations issued, payments certified, the equipment and manpower (skilled/unskilled by foreign/local categories in person-months) utilized by the contractor during the reporting month, together with an outline of the work to be performed during the next reporting period; the Engineer's personnel arrivals and departures; (Iv) statement of causes of possible delays and remedial measures taken or recommended;
(d) Project Performance Monitoring and Evaluation Report (PPMER) and Safeguards Monitoring Reports
14. The PMC shall submit baseline PPMER, mid-term PPMER by project mid-term progress, and final PPMER by project completion. The PMC shall submit Environmental and Social Safeguards Monitoring Reports as requested by MOTC and ADB.
(e) Road Safety Audit Reports
15. The PMC shall submit(i) Pre-construction; (ii) During Construction; and (iii) Post- construction Road Safety Audit (RSA) reports. In addition the PMC shall submit a relevant report for Accident Analysis and Mitigation based on their findings on the study conducted by the PMC during construction. The PMC will indicate the delivery dates of these reports in the Inception Report.
(e) Project Completion Report (PCR)
16. The PMC will draft a PCR prior to physical completion of construction works in a manner satisfactory to MOTC and ADB, including the major project events, performance of the contractors, operation of the Project, actual and price inflated (to completion year) project cost (foreign and local costs separately) by implementation year, and labor employed by skilled/unskilled and foreign/local categories in man-years; (I) the major project events, the relative successes (problems) in the implementation of each of the sections, this section of the PCR shall also contain an assessment of the impact of road improvement on the economy and social aspects for the whole project area; (ii) "as-built" drawings (to be submitted to MOTC). These "as-built" drawings will be furnished by the Contractor as per Clause 4.1 (d) of the construction contract;
(iii) detailed description of all the works by items of technical and non-technical matters, economic analysis, financial and disbursement data, analyses, difficulties and delays encountered or anticipated, and remedial actions taken or suggested, the overall
72 progress of the Project as monitored against the design and monitoring framework and PPMS indicators, including recommendations to MOTC and ADB.
IMPLEMENTATION SCHEDULE
2009 2010 2011 2012 2013 2014 2015 2016 Q4Q3 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q2Q1 Q4Q3 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Activity J A SOND J FMAMJ J A SONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASOND Tranche 1 Project Preparation TA
Construction Supervision - Tranche 1 Posting of CSRN Preparation of Shortlist/Draft RFP Approval of Shortlist/Draft RFP Issuing the RFP/Submission of Technical Proposals (TPs) Evaluating TPs Approving the Evaluation of TP Evaluating Financial Proposals Approving the Final Ranking Negotiating the contract Award of Supervision Contract
Detailed Design - Tranche 1, including Road Safety Selection of Design Consultant - Local Highway/Pavement Specialist - Foreign
Civil Works Procurement - Tranche 1 Bidding Documen t Prepara tion Approval Period (MOTC, ADB) Invitation and Bidding Period (6 weeks) Bid Evaluation Approval Period (MOTC, ADB) Contract Negotiations Award of Civil Works Contract
a Civil Works Contract Period - Tranche 1 (30 months, plus 12 months Defects Liability Period)
Detailed Design - Tranche 2 Prequalification of Bidders - Tranche 2
Implementation - Tranche 2 Bidding and Award Period a Civil Works Contract Period (33 months, plus 12 months Defects Liability Period)
Detailed Design - Tranche 3 Prequalification of Bidders - Tranche 2
Implementation - Tranche 3 Bidding and Award Period b Civil Works Contract Period (48 months, plus 12 months Defects Liability Period)
ADB = Asian Development Bank; AMJ = April, May, June; ARD = Armenian Roads Directorate; EOI = expression of interest; JAS = July, August, September; JFM = January, February, March; MOTC = Ministry of Transport and Communication; OND = October, November, December; TA = technical assistance. a The construction period has been determined in consideration of prevailing climatic conditions and allows for a complete construction season at the end of the construction period. b 48months, in consideration of complexity of works. Source: Asian Development Bank estimates. Appendix 6
CONTRACT AWARDS AND DISBURSEMENTS PROJECTIONS
Loan 2561-ARM: North–South Road Corridor Investment Program – Project 1
Contract Awards Disbursements Year (in USD million) (in USD million) Q1 Q2 Q3 Q4 Total Q1 Q2 Q3 Q4 Total 2010 0.0 0.0 0.0 3.6 3.6 0.0 0.0 0.0 1.5 1.5 2011 0.0 0.0 30.0 0.1 30.1 0.5 0.5 0.5 3.0 4.5 2012 2.0 8.0 0.0 0.0 10 0.5 3.5 8.0 10.0 22.0 2013 0.0 0.0 0.0 0.0 0 0.2 4.0 5.0 3.0 12.2 2014 0.0 0.0 0.0 0.0 0 1.0 0.5 0.0 0.0 1.5 2015 0.0 0.0 0.0 0.0 0 0.0 0.0 0.0 0.0 0.0
Total ADB Amount is USD60.0 million
Loan 2729-ARM: North–South Road Corridor Investment Program – Project 2
Contract Awards Disbursements Year (in USD million) (in USD million) Q1 Q2 Q3 Q4 Total Q1 Q2 Q3 Q4 Total 2010 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2011 0.0 0.0 5.0 100.0 105.0 0.0 0.0 0.5 10.0 10.5 2012 2.0 24.0 0.0 0.0 26.0 1.0 13.0 10.5 10.5 35.0 2013 0.0 0.0 0.0 0.0 0.0 0.0 20.5 20.5 10.5 51.5 2014 0.0 0.0 0.0 0.0 0.0 0.0 12.0 7.0 6.0 25.0 2015 0.0 0.0 0.0 0.0 0.0 3.0 3.0 0.0 0.0 6.0
Total ADB Amount is USD170.0 million
Appendix 7
Quarterly/ Monthly Project Progress Report
(Template)
Loan Number: xxx Reporting Period: xxx
Project Name
Prepared by the xxxxx
This report is a quarterly update to the project implementation progress. It is designed for ready use by the project executing agencies to provide direct input into ADB’s internal Project Progress and Project Completion Reports.
CURRENCY EQUIVALENTS
Currency Unit – Armenian Dram (AMD)
At Appraisal As of This Reporting (April 2008) (date) AMD1.00 = $xxxx $xxx $1.00 = AMD xxx Sum xxx
ABBREVIATIONS AND UNITS
ADB – Asian Development Bank EA – executing agency PIU – project implementation unit xxxx – xxx xxxx – xxx xxxx – xxx xxxx – xxx
NOTES
(i) The fiscal year (FY) of the xxxx ends on 31 December.
(ii) In this report, "$" refers to US dollars.
THIS REPORT IS REVIEWED AND ENDORSED FOR SUBMISSION TO ADB BY
Name Position
RESPONSIBLE ADB OFFICERS
Name Position Hong Wang Director, Transport and Communications Division (CWTC) Arto Ahonen Transport Specialist, CWTC Leonor Alejandro Assistant Project Analyst, CWTC
CONTENTS Page BASIC DATA i
MAP
I. PROJECT DESCRIPTION 1 II. IMPLEMENTATION PROGRESS 2 [insert subheading to describe the project progress]
ANNEXES
[list annexes]
BASIC DATA
A. Loan Identification
1. Country 2. Loan Number 3. Project Title 4. Recipient 5. Executing Agency 6. Amount of Loan
B. Loan Data for 2561 1. Appraisal – Date Started – Date Completed 2. Loan Negotiations – Date Started – Date Completed 3. Date of Board Approval 4. Date of Loan Agreement 5. Date of Loan Effectiveness – In Loan Agreement – Actual – Number of Extensions 6. Closing Date – In Loan Agreement – Current – Number of Extensions
7. Disbursements ($ million) Allocation at Current Amount Percent Loan Appraisal + Allocation Disbursed Disbursed Balance Category Supplementary
Total
C. Project Data
1. Project Cost ($ million)
Cost Appraisal Estimate + Current Supplementary
ii
Total
2. Financing Plan ($ million)
Cost Appraisal Estimate + Current Supplementary Project Cost ADB Government Total ADB = Asian Development Bank
3. Contract Award and Disbursement Projections ($ million) Cumulative Contract Awards 2009 Contract Awards ADB Others 1Q 2Q 3Q 4Q Total 30 June 2010 Proj 2010
Cumulative Disbursements 2009 Disbursements 30 June 2010 Proj 2010
4. Project Schedule Item Appraisal Estimate Actual Date of Supervision Contract with Consultants (Insert dates) (Insert dates) Civil Works Contracts (Package 1) Date of Award Completion of Work Consultancy Services contract for xxxx Date of Award Completion of Work Consultancy Services contract for xxxx Date of Award Completion of Work Consultancy Services contract for xxxx Date of Award Completion of Work
5. Project Performance Report Ratings Ratings
Development Implementation Implementation Period Objectives Progress
D. Data on Asian Development Bank Missions
Name of Mission Date
iii
E. Contracts, Dates and Amounts (provide contract data) Amount Contract Date No. Contractor ($million)
(insert project map here)
I. PROJECT DESCRIPTION
1. Provide Detailed Description of Project
2
II. IMPLEMENTATION PROGRESS
FOLLOW BELOW INSTRUCTION
A. Project Progress
Provide the following information
Summary statement on % physical progress and other achievements in implementation since the last progress report; Summary statement on the progress in implementing the overall project to date in comparison with the original implementation schedule—quantifiable and monitorable target. an assessment of the validity of key assumptions and risks in achieving the quantifiable implementation targets. an assessment of the likelihood that the immediate development objectives (project purpose) will be met in part or in full, and whether remedial measures are required based on the current project scope and implementation arrangements; an assessment of changes to the key assumptions and risks that affect attainment of the development objectives; and
Provide detailed assessment of achieving the project impact and outcome in Annex 1.
Summarize other project developments, (i) benefit monitoring and (ii) reporting on environmental and social requirements that might adversely affect the project's viability or accomplishment of immediate objectives. Supplement with detailed information in attachments.
Keep record of major milestone events in Annex 2.
B. Procurement and Disbursements
Provide the following:
status of procurement, including cumulative contract awards (commitment of funds to date), and comparison with time-bound projections (targets); cumulative disbursements from the ADB loan, cofinancing, and counterpart funds (expenditure to date), and comparison with time-bound projections (targets); and re-estimated costs to completion, need for reallocation within ADB loan categories, and whether an overall project cost overrun is likely.
Provide details of contract packages in Annex 3 and 4. Update project cost, financing plan and annual disbursements in Annex 5.
C. Project Scope and Implementation Arrangements
Provide the following:
3
assessment/update of project implementation arrangements such as establishment, staffing, and funding of the PMO or PIU;
information relating to other aspects of the EA’s internal operations that may impact on the implementation arrangements or project progress;
status of project scope/implementation arrangements (related to procurement and disbursements) compared with those in the report and recommendation of the President (RRP), and whether major changes have occurred or will need to be made;
D. Compliance with Covenants
Provide summary of the Borrower’s compliance with agreement covenants, indicating the total number of covenants (i) complied with; (ii) not complied with; (iii) ongoing; (iv) late complied with; and (v) not complied with. Provide explanation on reasons for not complying with particular covenants. Provide the detailed status of compliance in Attachment 6.
E. Major Project Issues and Problems
Summarize the major problems and issues affecting or likely to affect implementation progress, compliance with covenants, and achievement of immediate development objectives.
Recommend time bound actions to overcome these problems and issues (e.g., changes in scope, changes in implementation arrangements, and reallocation of loan proceeds).
Annex
3 3
4 Annex 1
Impact
(Provide information based on DMF)
Assessment: [provide assessment of achieving project impact]
Performance Targets/Indicators Progress/Status By xxx (Provide information based on DMF and PPMS) (Provide information based on PPMS) (Provide information based on DMF and PPMS) (Provide information based on PPMS) (Provide information based on DMF and PPMS) (Provide information based on PPMS)
Key Assumptions/Risks Assessment of Current Status Assumptions: (Provide information based on DMF and PPMS) (Provide information based on PPMS)
Outcome
(Provide information based on DMF)
Assessment: [provide assessment of achieving project outcome]
Performance Targets/Indicators Progress/Status By xxx (Provide information based on DMF and PPMS) (Provide information based on PPMS (Provide information based on DMF and PPMS) (Provide information based on PPMS (Provide information based on DMF and PPMS) (Provide information based on PPMS (Provide information based on DMF and PPMS) (Provide information based on PPMS (Provide information based on DMF and PPMS) (Provide information based on PPMS (Provide information based on DMF and PPMS) (Provide information based on PPMS Key Assumptions/Risks Assessment of Current Status Assumptions: (Provide information based on DMF and PPMS) (Provide information based on PPMS (Provide information based on DMF and PPMS) (Provide information based on PPMS (Provide information based on DMF and PPMS) (Provide information based on PPMS (Provide information based on DMF and PPMS) (Provide information based on PPMS
Risks: Mitigaged (Y/N) (Provide information based on DMF and PPMS) xxx (Provide information of actions taken to mitigate risks
Recent Development (Date: xxx) xxxxx
Problems with Impact and Outcome Description Action Taken/Proposed xxxxxx xxxxxx
Annex 1 5
IMPLEMENTATION PROGRESS
Project Outputs By 2011 Description Indicators/Targets Status (Provide information based on (Describe progress of contract DMF and PPMS) awards etc.) Example: To be measured after completion of individual road sections. (Provide information based on (Describe progress) DMF and PPMS) (Describe progress) (Describe progress) (Describe progress) (Describe progress) (Describe progress) (Describe progress) (Provide information based on (Describe progress) DMF and PPMS) (Describe progress) (Describe progress) (Describe progress)
Key Project Inputs 1. Indicate the detailed progress of each project component, such as, - recruitment of consultants and their performance; - procurement of go ods and works (from preparation of de tailed de signs and bidding documents to contract awards); and - the performance of suppliers, manufacturers, and contractors for goods and works contracts;
2. Update the Table below.
Remarks (give de scriptions of the s tatus of each package)
Targets: Package 1: (Provide information based on DMF) Sample for reference:
Procurement started in 200x and the invitation for bid for xx Lots (xx km, against xx km at appraisal)was issued on xx 200x under International Competitive Bidding
Procedure (ICB) Single-Stage: One-Envelope. On xxx Annex 200x the bids were received by the EA/IA and were evaluated. The bid evaluation report was submitted to
ADB for approval on xxx 200x. The total bid amount for 3 the said xx lots is $xxxx, around x% higher/lower than 5 the cost estimated at appraisal of the project in xx 200x. ADB endorsed the bid evaluation report for Lots x-x on xxx 200x. All contracts for the xx lots have been finalized/signed and submitted to ADB in xxx 200x.
6 Annex 1
Contractors were mobilized in xxx 200x with planned completion of xxx 200x. No physical works completed during xxx 200x to xxx 200x due to xxxxx; works resumed in xxx 200x Slippage/No slippage in completion time is foreseen.
Key Assumptions (Input-Output) (Provide information based on DMF) (Provide description of actions taken) (Provide information based on DMF) (Provide description of actions taken) (Provide information based on DMF) (Provide description of actions taken)
Risks (Input-Output) Mitigaged (Y/N) (Provide information based on DMF) xxx (Provide information of actions taken to mitigate risks (Provide information based on DMF) xxx (Provide information of actions taken to mitigate risks (Provide information based on DMF) xxx (Provide information of actions taken to mitigate risks (Provide information based on DMF) xxx (Provide information of actions taken to mitigate risks
Implementation Progress
Rating Criteria Remarks 1. Project Implementation Delays (Describe progress) 2. Change in Project Scope (Describe progress)
3. Change in Implementation Arrangements (Describe progress)
4. Project Costs (Describe progress)
5. Counterpart Funding/Cofinancing (Describe progress)
6. Major Covenants (exclude #7 below) (Describe progress)
7. Audited Project Accounts and Corporate (Describe progress) Financial Statements
Design Changes (Describe progress)
Recent Development (Date: 30 April 2009) (Provide information) Missions, revisions, changes etc.
Problems with IP Description Action Taken/Proposed (Provide descriptions)
3. Complement the above information by simple charts such as bar or milestone to illustrate progress, a chart showing actual versus planned expenditure, S-curve graph showing
Annex 1 7 the relationship between physical and financial performance, and actual progress in comparison with the original schedules and budgets, the reference framework or guidelines in calculating the project progress. Use PAI 5.01, para 7 and Appendix 2 for computation of actual project progress. Annex
3 7
2 8 CHRONOLOGY OF MAJOR MILESTONE EVENTS
Loan No. 2561-ARM Annex Date Event (Provide information of major events)
CONTRACT PACKAGES
Estimated Number Actual Contract of Contract Value Contracts Procurement Value Contract Works Contract Description ($ million) Awarded Method ($ million) Approved Completed Contractor
1. Civil Works
2. Goods
3. Etc. 4. 5. 6.
Source: Annex
3 9
10 Annex 4
PROJECT COSTS AND FINANCING PLAN ($ million)
Provide table as in Loan Agreement
Annex 5 11
ANNUAL DISBURSEMENTS (please fill out) ($ million) ADB Government % of % of Year Disbursement Total Cumulative % Disbursement Total Cumulative %
Source: Loan and Grant Financial Information System, executing agency and project consultants estimates.
Annex
3 11
12 Annex 6
STATUS OF COMPLIANCE WITH MAJOR LOAN COVENANTS LOAN COVENANTS
Covenant Due Date Status (As in Loan Agreement and FAM) (please provide info) (please describe status)
Environmental Assessment Report
Environmental Assessment and Review Framework Project Number: 42145 August 2009
Armenia: North–South Road Corridor Investment Program
Prepared by Ministry of Transport and Communications (MOTC) of Armenia for the Asian Development Bank.
The views expressed herein are those of the consultant and do not necessarily represent those of ADB’s members,The environmental Board of Director assessments, Management, and review or staff,framew andork may is bea preliminarydocument inof nature.the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
ABBREVIATIONS
ARD Armenia Roads Department ADB Asian Development Bank EARF environmental assessment and review framework EIA environmental impact assessment1 EMP environmental management plan EA executing agency IEE initial environmental assessment MNP Ministry of Environmental Protection and Natural Resources MOTC Ministry of Transport and Communication MFF multitranche financing facility NPE Nature Protection Expertise NGO nongovernment organization PMU Program Management Unit RAMSAR Ramsar Convention on Wetlands REA Rapid Environmental Assessment Checklist RA Republic of Armenia SEI State Environmental Inspectorate SNCO State Non-commercial Organizations SEIA summary environmental impact assessment SIEE summary initial environmental assessment TOR terms of reference
NOTE
In this report, “$” refers to US dollars.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
1 In this document, environmental impact means negative, or adverse, environmental impact
CONTENTS
A. Introduction 1
B. Overview of the Subprojects to be Assessed 1
C. Country’s Environmental Assessment and Review Procedures 2
D. Specific Procedures to be Used for Subprojects under MFF 2
E. Compliance with ADB’s Environmental Policy—Due Diligence 7
F. Public Disclosure 7
G. Staffing Requirements and Budget 8
Annexes
Annex 1 Rapid Environmental Assessment Checklist Annex 2 Sample Scoping Document Annex 3 Outline of an Environmental Impact Assessment Report Annex 4 Outline of Summary Environmental Impact Assessment Report Annex 5 Outline of an Initial Environmental Examination Report Annex 6 Outline of Summary Initial Environmental Examination Report Annex 7 Outline Terms of Reference for Consulting Services for Environmental Assessment
1
Environmental Assessment and Review Framework
A. Introduction
1. The mandatory requirements applicable to the multitranche financing facility (MFF) necessitate that the proposed subprojects of the first tranche and the subprojects of subsequent tranches follow adequate environmental assessment processes. To ensure that future components are evaluated in a manner consistent with the requirements of the Ministry of Nature Protection (MNP), the national environmental agency of the Republic of Armenia (RA), and the ADB, this Environmental Assessment and Review Framework (EARF) has been prepared. The EARF will guide the Armenia Roads Directorate (ARD) of the Ministry of Transport and Communication (MOTC) of the RA in carrying out the environmental assessment of the subprojects to be financed under the MFF: “North-South Road Corridor Investment Program”. This EARF sets forth the following:
(i) general principles, selection criteria, procedure of organization of and conducting environmental expert assessment of the subproject documents under this MFF; (ii) requirements on the type of subproject documents and the procedure of submitting thereof for environmental expert assessment; and (iii) a list of environmentally hazardous types of activities subject to mandatory environmental impact assessment (EIA) on the subproject approval stage.
2. The implementation arrangements are as follows:
(i) The Executing Agency (EA) will be the MOTC. (ii) The MOTC will be monitored by the Subproject Governing Council of Armenia, whose other key functions include guiding the overall policy and strategic direction of the MFF Program, reviewing and evaluating its performance, and coordinating with other external aid agencies. (iii) The ARD will set up a Program Management Unit (PMU) to manage day-to-day coordination, implementation, monitoring, and administration activities of individual subprojects. (iv) The PMU will include a Safeguards Team comprising expertise in, inter alia, social and environmental safeguards.
B. Overview of the Subprojects to be Assessed
3. Identification of subprojects through the MFF is in progress. So far, two tranches have been identified: (i) repavement of 18.4 km 4-lane section of the Ashtarak to Yerevan road and improved safety for the Yerevan to Ararat road, and (ii) widening the 88-km 2-lane road from Ashtarak to Gyumri to four lanes and a feasibility study and subproject preparation for subsequent tranch subprojects that improve border infrastructure and procedures, upgrading the remaining north-south road corridor, and may include the construction of a new road between Goris and Kapan.
4. The sections of road proposed to be improved under Tranche 1 of the North-South Roads Corridor Program are the Yerevan to Ashtarak and Yerevan to Ararat sections of the Corridor. These sections are both existing 4-lane divided roads within a semi-arid zone devoid of any unique or sensitive areas, forests, and protected areas within one km of the alignment for which environmental impacts can be expected to be minor, standard, and easily prevented or mitigated. Consequently, the ADB assessed this road section as a Category B subproject,
2 requiring only an initial environmental examination (IEE). The IEE report was prepared in accordance with ADB’s Environment Policy (2002) and Environmental Assessment Guidelines (2003) and was subsequently uploaded on ADB’s website on 9 September 2009.
5. Tranches 2 and 3 have been defined conceptually, and further tranches may be considered also, but they have not progressed to the environmental assessment stage, which will be guided by this EARF.
C. Country’s Environmental Assessment and Review Foundation
6. The relevant national laws on environmental protection and assessment are:
(i) Law on the Principles of Environmental Protection of 1991 (ii) Law on Environmental Impact Assessment (EIA) of 1995
These two laws are the main laws administered by the MNP. Other pieces of pertinent environmental legislation to be considered are:
(iii) Land Code of 1991, updated in 2001 (iv) Water Code of 1992, updated in 2002 (v) Law on Specially Protected Natural Areas of 2006
7. The key departments within the MNP that have administrative authority over EIA and the subproject approval process are two State Non-commercial Organizations (SNCOs):
(i) The SNCO “Nature Protection Expertise (NPE)” responsible for reviewing and approving EIA reports and subprojects for implementation and adding conditions when necessary to protect the environment, and (ii) The SNCO “State Environmental Inspectorate (SEI)” responsible for inspecting subprojects to ensure compliance with conditions imposed by the NPE and with the subproject Environmental Management Plan (EMP) and Monitoring Program.
8. The EIA process and the SEI’s power to inspect are the principal tools used by the MNP to achieve compliance with environmental management principles.
D. Specific Procedures to be Used for Subprojects under MFF
1. Responsibilities and Authorities
9. Responsibilities of the implementing and executing agencies (ARD and MOTC respectively) include:
(i) Prepare environmental screening checklist and classify subprojects in consultation with MNP and other departments. (ii) Based on the environmental classification of subprojects, prepare terms of reference to conduct IEE or EIA studies. (iii) Hire an environmental consultant to prepare IEE or EIA reports including EMP and summary EIA/IEE for public disclosure. (iv) Ensure that an IEE or EIA is prepared in compliance with the requirements of the Government and ADB, and that adequate consultation with affected people is undertaken in accordance with ADB requirements.
3
(v) Undertake review of the IEE or EIA, summary EIA/IEE, and EMP reports to ensure their compliance with the requirements of the Government and ADB. (vi) Obtain necessary permits and/or clearance, as required, from MNP and other relevant government agencies, ensuring that all necessary regulatory clearances are obtained before commencing any civil work on the relevant sections. (vii) Submit to ADB the IEE or EIA, summary EIA/IEE, and EMP reports and other documents, as necessary. (viii) Ensure that any EMP, including relevant mitigation measures that need to be incorporated during the construction stage by the contractor, are included in the bidding and contract documents. (ix) Ensure that contractors have access to the EIA or IEE and EMP reports of the subprojects. (x) Ensure that contractors understand their responsibilities to mitigate environmental problems associated with their construction activities. (xi) Ensure and monitor that an EMP, including an environmental monitoring plan, will be properly implemented. (xii) In case unpredicted environmental impacts occur during the subproject implementation stage, prepare and implement as necessary an environmental emergency program in consultation with MNP, other relevant government agencies, and ADB. (xiii) In case a subproject needs to be realigned during implementation, review the environmental classification, revise it accordingly, and identify whether a supplementary IEE or EIA study is required. If yes, prepare the terms of reference for undertaking a supplementary IEE or EIA and hire an environmental consultant to carry out the study. (xiv) Submit semi-annual reports on implementing EMPs, including implementation of an environmental emergency program, if any, to MNP and ADB. (xv) Submit subproject completion environmental monitoring report to ADB after three years of completion of construction summarizing the overall environmental impacts from the subprojects.
10. ADB is responsible for the following:
(i) Review EIA and SEIA reports prepared under supervision of EA; (ii) Review of IEE and SIEE reports if it requires ADB’s no objection approval; (iii) Undertake annual environmental review missions for category A and B subprojects; and (iv) Public disclosure of SEIA and SIEE (for category B subprojects) through ADB website.
2. Environmental Criteria for Subproject Selection
11. Considering the potential environmental impacts of the future subprojects and the relevant environmental requirements of ADB and the Government of Armenia, the following criteria was agreed upon (by the Government and ADB) for selection of the future subprojects to be included in the Subregional Road Corridor Investment Program:
(i) The subprojects shall only involve activities that follow all the applicable Government regulations;
4
(ii) The subprojects should not pass through any wildlife sanctuaries, national parks, nature reserves, and protected areas designated by national and international regulations; (iii) The subprojects should not pass through any ecologically sensitive and significant as recognized by the Government or any area that is internationally significant (such as protected wetlands and mangroves); and (iv) The subproject should as much as possible not include any stretch that passes through any cultural heritage and archaeological sites designated by UNESCO and the Ministry responsible for culture.
3. Procedures for Environmental Assessment of Subprojects
12. ADB categorizes road subprojects into two environmental categories, A and B. Subprojects with potential for significant adverse environmental impacts are category A, for which an EIA is required to address significant impacts. Subprojects judged to have some adverse impacts, but of lesser degree and/or significance than category A are category B, for which an IEE is required to determine whether or not significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. The guidelines to prepare environmental assessment reports for a category A subproject (EIA and SEIA) and for a category B subproject (IEE and SIEE) in compliance with the ADB’s Environment Policy (2002) and Environmental Assessm ent Guidelines (2003) are given in the following sections.
a. Screening
13. Every future subprojects to be included in this MFF Program will be screened to determine its environmental category based on the ADB’s Rapid Environmental Assessment Checklist (REA). A template of the REA is given in Annex 1. Classification is to be based on the most environmentally sensitive component, which means that if one part of a subproject has the potential for significant adverse environmental impacts, then the subproject is to be classified as category A regardless of the potential environmental impacts of other aspects of the subproject. In general, a subproject will be classified as ‘category A’ if it:
(i) is a new road alignment; (ii) a complex mitigation measure needs to be prepared through an in-depth assessment of the impacts and detailed study for preparing mitigation measures; (iii) will adversely impact an ecologically sensitive area, particularly if the subproject is located less than 500 meters from a designated wildlife or other sanctuary, a national park, a botanical garden, an area of international significance (e.g., an IUCN or RAMSAR site), or from cultural heritage and archaeological sites designated by UNESCO; and (iv) passes through any ecologically sensitive areas (hilly or mountainous, forested, nearby estuarine, or other area with important ecological function).
14. Road upgrading and rehabilitation subprojects that do not fall into the above category are classified as B.
b. Scoping
15. Before conducting any environmental studies, a scoping document consisting of the scope of the environmental surveys, methods of data collection and outputs anticipated from the
5 study is to be prepared. In case of category A subprojects, the scoping document is to be approved by the EA before detailed environmental studies are undertaken. Scoping should focus on identifying those components of the environment that are likely to be significantly affected by the subproject based on subproject location, past documented experience, the likely geographic and time-related extent of the effects, and the measurements or thresholds to be used to assess significance. A topographic map of the study area showing the subproject road(s), water courses, settlement areas, and preferably landuse should be part of the scoping document. A sample scoping document is in Annex 2.
c. Identifying Baseline Conditions and Impacts
1. With the screening and scoping results in hand, planning of the field program becomes relatively easy; however, it does require the involvement of an experienced environmental assessment practitioner.
2. The first step is to establish the baseline conditions against which any change is measured for the components of the environment likely affected by the subproject. This will usually be carried out through site visits and review of spatial databases for all available environmental parameters such as terrain, soils, rivers, forest, protected areas, and landuse. This will also include collection and analysis of background noise, and air and water quality. These data must be collected in such a manner that their source can be traced by anyone who picks up the document.
3. The second step is to predict likely changes as a result of construction activities and operation of the road, by relating cause and effect such as changes in traffic volume, fleet makeup, and traffic patterns to air quality and noise levels. The locations where based data were collected and where ongoing monitoring takes place should be well documented to facilitate analysis and provide credibility. While following strict scientific method in EIA is far too costly and time consuming, every effort should be made to make the entire study transparent and traceable.
d. Public Consultations/Hearing
4. The third step is to present the findings on impacts and benefits during a consultation and information session to inform key stakeholders and affected communities of the issues identified and to invite comments. For a category A subproject, consultation is required at least twice during the EIA:
(i) First, as part of the scoping stage to define the subproject and to get feedback in options, and (ii) Secondly, after the draft EMP has been prepared and prior to loan appraisal by ADB.
5. Public consultations include newspaper advertisements in the regional and national news papers 50 to 60 days before the intended consultations giving brief subproject description, location, and specific contact data (including telephone numbers). Often a subproject website is created and link information is provided. Further, the proponent, working with the consultant, should prepare a list of important participants and send emails or letters of invitation providing details including dates for both consultations.
6
6. Consultations must have meeting notes and attendance sheets prepared, which are included as part of the EIA documentation.
7. For Category B subprojects, nearly all conditions as defined above are the same except there is only one consultation session required, which generally takes place as the EMP is being prepared.
e. Preparation of the Environmental Management Plan
8. The Fourth Step is the preparation of the EMP, the most important output of an environmental assessment. The EMP must be practical, specific, and systematic such that it can easily facilitate mitigating and monitoring actions by contractors and proponents and that can form the basis of environmental clauses in bidding and contract documents. Each mitigation measure should be matched with a monitoring activity.
9. Good EMPs not only identify the source of the impact, the effect in the biophysical environment, and the monitoring action to be taken, but also where, when, how often, and by whom each mitigation and monitoring action should be performed. This applies to EIAs and IEEs.
10. The PMU of ARD is required to review and update the EMP as soon as the contractor has been appointed and the mobilization date is established and periodically thereafter as appropriate.
f. Assessing Institutional Capacity for EMP Implementation
11. The Fifth Step involves the identification of the agencies and units at the national and sub-national level that will likely be involved in the implementation and supervision of the mitigation and monitoring actions as well as the general management of the EMP from preconstruction through the operating period. The EMP is also useful in that it identifies the lead implementing and supervising agencies (ARD, MOTC, and MNP and their provincial/regional departments) involved in all mitigation and monitoring actions. The assessment, using mostly the interview approach, should be short and focused, identifying needs based on obvious gaps, such as lack of experience in international-level assessments or lack of experience with preparation and implementation of EMPs. Careful interviews will almost always result in those needing assistance identifying what they need. Finally, the needs are assessed in terms of longer-term capacity building and short-term training and workshops in relation to realistic budgetary limits and a capacity building and training program is proposed. Since the contractors play such an important role in EMP implementation, their safeguards skills must also be assessed with a view to strengthening them.
g. Estimating Mitigation, Monitoring, and Training Costs
12. The Sixth Step involves costing of each of the mitigation and monitoring actions as well as the institutional capacity building. Costing details must be systematic and include rates and unit costs and an indication of actions that, while referred to as environmental, are normally found in other budget items, for example slope stabilization, revegetation, fuel handling and storage protocols, and work camp waste management.
7
h. Reporting
13. The Seventh Step is preparation of the assessment document according to a prescribed format and level of details. The templates of the reports for preparation of EIA/IEE and SEIA/SIEE reports are in Annexes 3 to 6 and can also be found in ADB’s website at www.adb.org/documents/guidelines/environmental_assessment/default.asp.
E. Compliance with ADB’s Environmental Policy—Due Diligence
14. ARD, MOTC, and MNP have the responsibility to undertake environmental due diligence and monitor implementation of environmental mitigation measures for all subprojects under each respective mandate. The due diligence report as well as monitoring of EMP implementation (described in the annual report) need to be documented systematically. ADB must be given access as needed to undertake environmental due diligence for all subprojects.
15. An EMP will be part of the overall subproject monitoring and supervision, and will be implemented by the contractor with oversight from the supervision consultant and PMU. Progress on the preparation and implementation of an EMP will be included in the periodic subproject progress reports. Specific monitoring activities defined in the IEEs or EIAs and EMPs will be carried out by the contractors and monitored by the PMU. ARD will submit reports on EMP implementation to ADB every six months for category A and selected2 categoryB subprojects and annually for other category B subprojects.
16. The PMU, with assistance from the environmental consultants, will review the IEE or EIA and corresponding EMP for each subproject to ensure that mitigation measures and monitoring plans proposed in those documents are in compliance with ADB’s and Government’s requirements. According to the reports and reviews during its missions, ADB, in consultation with the Government, will confirm compliance. For this purpose, the PMU will provide ADB with access to information on any subprojects. The information on implementation of an EMP, as well as that on environmental and social safeguard compliance, will be systematically documented and reported to ADB as part of the regular progress reports.
F. Public Disclosure
17. ARD is responsible for ensuring that all environmental assessment documents, including the environmental due diligence and monitoring reports, are properly and systematically kept as part of the subproject record of each subproject under its responsibility. All environmental documents are subject to public disclosure. These documents should be made available to the public, if requested. In case there are category A and selected category B subprojects, the summary EIA/IEE will be disclosed to the public through ADB’s website at least 120 days before the subproject is approved. The SEIA/SIEE shall be reviewed by ADB before it is disclosed to the public. ARD will also ensure that public consultations, particularly with subproject affected persons, are undertaken adequately during the IEE or EIA preparation in consistent with ADB requirements.
2 Selected environmentally sensitive category B subprojects include those that are near environmentally sensitive areas, or that involve deforestation; loss of biodiversity; involuntary resettlement; the processing, handling, or disposal of toxic and hazardous substances; or activities that may be of concern to a wide group of external stakeholders.
8
G. Staffing Requirements and Budget
18. ARD and MOTC will recruit environmental consultants as a part of engineering design consultants to prepare environmental assessment reports for each subproject consistent with this EARF. Terms of reference for consultants along with the budget are given in Annex 7. The estimated cost for preparation of each IEE and EIA are about $100,000 and US$160,000 respectively. Adequate funding resources must be provided under each subproject for environmental monitoring and mitigation measures for each subproject.
Annex 1 9
Rapid Environmental Assessment (REA) Checklist Roads and Highways
Instructions: This checklist is to be prepared to support the environmental classification of a subproject. It is to be attached to the environmental categorization form that is to be prepared and submitted to the Chief Compliance Officer of the Regional and Sustainable Development Department. This checklist is to be completed with the assistance of an Environment Specialist in a Regional Department. This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB checklists and handbooks on (i) involuntary resettlement, (ii) indigenous peoples planning, (iii) poverty reduction, (iv) participation, and (v) gender and development. Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.
Country/Subproject Title: Armenia / [Name of subproject] Sector Division: Roads & Highways Conducted by / date: [Name(s) of Environmental Specialist(s)], [Date]
SCREENING QUESTIONS Yes No REMARKS A. SUBPROJE CT SITING
IS THE SUBPROJECT AREA ADJACENT TO OR WITHIN ANY OF THE FOLLOWING ENVIRONMENTALLY SENSITIVE AREAS? CULTURAL HERITAGE SITE PROTECTED AREA WETLAND MANGROVE ESTUARINE BUFFER ZONE OF PROTECTED AREA SPECIAL AREA FOR PROTECTING BIODIVERSITY B. POTENTIAL ENVIRONMENTAL IMPACTS
WILL THE SUBPROJECT CAUSE… encroachment on historical/cultural areas; disfiguration of landscape by road embankments, cuts, fills, and quarries? encroachment on precious ecology (e.g. sensitive or protected areas)? alteration of surface water hydrology of waterways crossed by roads, resulting in increased sediment in streams affected by increased soil erosion at construction site? deterioration of surface water quality due to silt runoff and sanitary wastes from worker-based camps and chemicals used in construction? increased local air pollution due to rock crushing, cutting and filling works, and chemicals from asphalt processing? noise and vibration due to blasting and other civil works? dislocation or involuntary resettlement of people other social concerns relating to inconveniences in living conditions in the subproject areas that may
Annex 1 10
SCREENING QUESTIONS Yes No REMARKS trigger cases of upper respiratory problems and stress? hazardous driving conditions where construction interferes with pre-existing roads? poor sanitation and solid waste disposal in construction camps and work sites, and possible transmission of communicable diseases from workers to local populations? creation of temporary breeding habitats for mosquito vectors of disease? dislocation and compulsory resettlement of people living in right-of-way? accident risks associated with increased vehicular traffic, leading to accidental spills of toxic materials and loss of life? increased noise and air pollution resulting from traffic volume? increased risk of water pollution from oil, grease and fuel spills, and other materials from vehicles using the road?
Annex 2 11
SAMPLE SCOPING DOCUMENT
Scoping Framew ork for the Environmental Impact Assessment of ‘Ajara By pass Roads Development Subproject’
A. Introduction
1. This scoping framework has been prepared to carryout detailed environmental impact assessment (EIA) for the ‘Ajara Bypass Roads Development Subproject’ in accordance with ADB’s Environment Policy (2002) and Environmental Assessment Guidelines (2003) and relevant laws and regulations in Armenia. The subproject involves new construction and widening of roads, bridges, overpasses, tunnels, and protection structures. The study will identify potential environmental impacts on physical, ecological, social, cultural, and economic resources of subproject areas during design (for different alignments), construction and operation. An EIA report will be prepared along with environmental management and monitoring plan to address all identified environmental impacts as per the work plan provided in Error! Reference source not found. . The study will be carried out by Consultant and the draft EIA report will be submitted along with the Final Report of the Subproject.
B. Scope of Work
1. Baseline Studies
a. Output 1: Memo on Armenian Legal and Administrative Procedures
2. Activity 1.1 : Collection and review of relevant information regarding environmental legislation, statutory orders, by-laws, etc. connected to preparation and approval of the EIA report by Armenian Authority, and draft the memo. The memo will also consider the requirements of ADB Guidelines for ‘Category A’ Subproject.
3. Activity 1. 2: Conducting a series of meetings with the senior staff of ministries responsible for environment protection, natural resources, culture, archeology to discuss appropriate legal and administrative procedures. Discussions also include issues such as basis for further approval / disapproval of EIAs by Armenian authorities and on the issuance. Review of other relevant environmental laws, regulations, Norms, and Standards on Air, Noise, Water, Waste, and Wildlife.
4. Activity 1.3: Discussions with the ARD of the MOTC on the issuance of construction permits and environmrntal clearance certificates in accordance with RA’s applicable laws and regulations.
b. Output 2: Preparation of Baseline Assessment
5. Activity 2.1 : Review of reports and field data collected from the subproject’s pre- feasibility study; and other road subprojects carried out under the World Bank, JBIC, EBRD, and MCC’s funding.
6. Activity 2.2: Collection of baseline information on existing environmental condition along the subproject road alignments and identification of the environmental components that need detailed further study. Baseline assessment will be done based on the available secondary
Annex 2 12 information, field visits, sampling and environmental monitoring including but not limited to the following:
(i) Physical resources: topography, climate, soils, geology, landuse, coastal resources, and surface and groundwater resources; (ii) Natural hazards: seismicity, floods, landslides, and volcanic activity; (iii) Ecological Resources: landscape and natural ecosystem, flora and fauna, wildlife and wetland habitats, nature reserve and protected areas; (iv) Environmental quality: Air quality (PM, CO, NOx, Sox, etc.), noise quality and water quality (DO, TPH, pH, total nitrogen, BOD, total phosphorus, and suspended solid, etc.); and (v) Cultural resources and archaeological sites: structures or sites that are of historical, archaeological, paleontological, or architectural significance.
2. Detailed Field Investigation to Screen Environmental Impacts
c. Output 3: Field Investigation and Analysis of Results
7. Activity 3.1: Preparation of layout plan of the subproject road including, but not limited to, the flowing information:
(i) Road alignments (ii) Sampling location for environmental parameters (air, noise, water) (iii) Construction camp including storage of petroleum products and explosives (iv) Asphalt and batch mixing plants, construction sites and camps, quarry sites and borrow pits (v) Water sources, waste disposal sites, environmentally sensitive areas
8. Activity 3.2: Collection of a cadastral land use map showing the subproject locations and descriptions of the surrounding activities. This is to ensure that the subproject road is compatible with the national regulation specified for construction sites.
9. Activity 3.3: Initiation of necessary investigations and fieldwork for gathering of following additional information about ecological and environmental parameters in the subproject area.
(i) Landscape, Geohazards and Slope Stability . Identification of natural landscape along the subproject road. Assessment of geological and geomorphologic features of the subproject area, as well as any violent interference in the natural processes. Investigation and evaluation of results to predict rock falls, landslide, mudflow and debris flow, erosion, ground subsidence, floods, and banks washing-off (lateral erosion) and seashore erosion. (ii) Soil Erosio n and Slo pe Stability . Analysis of soil characteristics, moisture contents, vegetation cover etc., in conjunction with the above activity, to predict possible soil erosion and landslides due to subproject activities. (iii) Terrestrial Flora and Fauna. Investigation of the composition of plant species and migratory birds in the Subproject area. Attention should be paid to the distribution of protected plant and animal/birds species in order to ensure favorable conservation status for these species. (iv) Wetland habitats and Aquatic Flora and Fauna. Investigations of occurrence of species (flora and fauna) in the identified wetlands along the subproject area
Annex 2 13
and assess the potential influence of the proposed road alignment. Attention should be paid to the distribution of protected species in order to ensure favorable conservation status for these species. (v) Protected Areas and Sensitive Environmental Receptors. Collection of protected and sensitive area maps and exact coordinates showing the boundaries and buffer zones of protected areas and subproject alignments and descriptions of the habitats. This is to ensure that the locations of sensitive areas and subproject alignment are sufficiently distant enough to maintain harmonization and avoid any potential disturbances on the habitats. Investigation will also be done for other sensitive sites along the subproject alignment, viz. wetlands, seashore, tourism, etc. (vi) Traffic Flow. Traffic counts and historical traffic flow to predict the future traffic growth and the load on the subproject road. (vii) Air Quality and Noise Level. Collection and analysis of air (PM, CO, NOx, SO2) and noise quality along the subproject road. (viii) Water Quality. Collection and analysis of water quality (DO, turbidity, pH, TOC, and dissolved solid) of the major rivers along the subproject road. Investigation of water quality impacts during construction and operations stages in selected river sites. (ix) Monuments and Archaeological Site. Investigation of the impact of the subproject on monuments and archaeological sites along the subproject corridor. (x) Quarry and Borrow Sites. Estimation of effects on the ecological resources in the area connected to quarry and barrow pit operations needed for construction.
3. Analysis of Alternatives and Economic Assessment
d. Output 4: Analysis of Alternative Options
10. Activity 4.1: Comparative environmental analysis of all available subproject alignments, including “No Subproject” scenario.
e. Output 5: Economic Assessment
11. Activity 5.1: Economic analysis of all alternatives in accordance with ADB’s Handbook on Economic Evaluation of Environmental Impacts for: (i) costs and benefits of environmental impacts; (ii) costs, benefits, and cost-effectiveness of mitigation measures; and (iii) discussion of impacts that have not been expressed in monetary values, in quantitative terms where possible.
4. Forecast Future Impacts and Mitigation Measures
f. Output 6: Forecast of Impacts
12. Activity 6.1 : Forecasting of air and noise quality based on predicted traffic estimates using computer modeling software and recommendation of mitigation measures.
13. Activity 6. 2: Evaluation of the subproject impact on all physical and ecological resources described in Activity 3.3 and recommendation of mitigation measures.
14. Activity 6.3: Evaluation of socio-economical and cultural impacts, such as:
Annex 2 14
(i) Assessment of the status of livelihoods (agriculture, business, etc.) in the context of socio-economical impact. (ii) Assessment of the impact on objects or areas with known archeological values in the subproject area. (iii) Assessment of impacts on culturally and religiously sensitive locations (church, cemetery, etc.) (iv) Assessment of impacts in tourism sector (v) Assessment of traffic safety.
15. Activity 6.4: Assessment of impact on human health and estimation of possible health impacts on construction workers and roadside residents (such as safety, HIV/AIDS, STDs, human trafficking) due to construction camps and other subproject activities.
g. Output 7: Environmental Management and Monitoring Plan
16. Activity 7.1: Preparation of Environmental Management and Monitoring Plan (EMP) for all phases of the subproject for effective implementation of environmental protection and mitigation measures and monitoring of significant environmental impacts. Preparation of environmental protection measures to (i) mitigate environmental impacts, (ii) provide in-kind compensation for lost environmental resources, or (iii) enhance environmental resources. Prepare cost estimates for each mitigation measure proposed in the EMP and include all the mitigation measures in the engineering design of the Subproject.
17. Activity 7.2: Setting up of environmental criteria for several variables such as:
(i) Air quality, noise level, water quality, accidental spills of hazardous substances; and (ii) Naturally protected areas.
5. Institutional Assessment and Monitoring Mechanism
h. Output 8: Institutional Assessment
18. Activity 8.1 : Assessment of institutional capacity of the implementing agencies for effective implementation of environmental management and monitoring plan. Identification of responsible institutes for implementation and supervision of the EMP. Assess training needs of these agencies and propose capacity building measures and institutional arrangements to strengthen these agencies along with the cost estimates.
i. Output 9: Monitoring Mechanism
19. Activity 9.1: Elaboration and specifying of “feed back monitoring” program, a tool to be used by implementing authorities in order to be able to interfere and respond quickly to activities, which during the construction and operation turn out to have a negative effect to the environment. The tool will specify the parameters, location, frequency and means of monitoring.
Annex 2 15
6. Public Consultations and Disclosure Plan
j. Output 10: Conduct Public Consultations and Document Them
20. Activity 10 .1: Assisting ARD to conduct two public consultations (one during the inception stage and the second one after finalization of EIA report) according to ADB’s Public Communications Policy (2005) for Category A subprojects and the pertinent clause in RA’s Law on Environmental Impact Assessment (1995). This will ensure that the consultation process will involve affected people, key agencies, NGOs, and other stakeholders and they are provided with opportunities to participate in the decision-making process and to influence decisions that will affect them. Address all the comments in the engineering designs.
21. Activity 10.2: Agreement by the appropriate authorities of specific zones where minor temporary and/or permanent impacts to the environment can be accepted during the construction and operation phase of the bypass road. The ranges of the zones will be determined on the basis of results of investigations and local conditions.
k. Output 11: Disclosure Plan
22. Activity 11 .1: In consultation with the stakeholders, preparation of information disclosure plan for dissemination of safeguard documents to the affected community and general public.
Annex 3 16
Outline of an Environmental Impact Assessment (EIA) Report
A. Introduction
1. This section usually includes the following:
(i) purpose of the report, including (a) identification of the subproject and its proponent, (b) brief description of the nature, size, and location of the subproject and its importance to the country, and (c) any other pertinent background information; (ii) stage of subproject preparation (i.e., pre-feasibility study, feasibility study, detailed engineering design preparation); (iii) extent of the EIA study, including the scope of the study, magnitude of effort, and persons/expertise or agency performing the study and corresponding person months; and (iv) brief outline of the contents of the report, including any special techniques or methods used for identifying issues, assessing impacts, and designing environmental protection measures.
B. Description of the Subproject
2. The subproject should be described in terms of its basic activities, location, layout, and schedule (in terms of the subproject cycle). This section of the EIA report should provide sufficient details on the following:
(i) Type of subproject; (ii) Need for subproject; (iii) Location (use maps showing general location, specific location, subproject boundary and subproject site layout); (iv) Size or magnitude of operation including any associated activities required by or for the subproject; (v) Proposed schedule for approval and implementation; and (vi) Description of the subproject including drawings showing subproject layout, components of subproject, etc. This information should be of the same type and extent as is included in feasibility reports for proposed subprojects, in order to give a clear picture of the subproject and its operations.
C. Description of the Environment
3. This section contains a description of the study area to provide a clear picture of the existing environmental resources and values within which the impacts must be considered. Detailed methodology to gather information, including data sources, should also be briefly described. As much as possible, the baseline information should be presented in maps, figures, and tables. The baseline environmental information area should include:
(i) Physical Resources: e.g. (a) atmosphere (e.g. air quality and climate) (b) topography and soils, (c) surface water (d) groundwater (e) geology/seismology.
Annex 3 17
(ii) Ecological Resources: (e.g.) (a) fisheries (b) aquatic biology (c) wildlife (d) forests (e) rare or endangered species (f) protected areas (g) coastal resources
(iii) Economic Development: (e.g.) (a) industries (b) infrastructure facilities (e.g. water supply, sewerage, flood control) (c) transportation (roads, harbors, airports, and navigation) (d) land use (e.g. dedicated area uses) (e) power sources and transmission (f) agricultural development, mineral development, and tourism facilities
(iv) Social and Cultural Resources: (e.g.) (a) population and communities (e.g. numbers, locations, composition, employment); (b) health facilities; (c) education facilities; (d) socio-economic conditions (e.g. community structure, family structure, social well being); (e) physical or cultural heritage; (f) current use of lands and resources for traditional purposes by Indigenous Peoples; and (g) structures or sites that are of historical, archaeological, paleontological, or architectural significance.
D. Alternative s
4. The consideration of alternatives is one of the more proactive sides of environmental assessment - enhancing the subproject design through examining options instead of only focussing on the more defensive task of reducing adverse impacts of a single design. This calls for the systematic comparison of feasible alternatives for the proposed subproject site, technology, and operational alternatives. Alternatives should be compared in terms of their potential environmental impacts, capital and recurrent costs, suitability under local conditions, and institutional, training and monitoring requirements. For each alternative, the environmental costs and benefits should be quantified to the extent possible, economic values should be attached where feasible, and the basis for the selected alternative should be stated.
5. Examining alternative means of carrying out a subproject involves answering the following three questions: (i) what are the alternatives? , (ii) what are the environmental impacts associated with each alternative? , and (iii) what is the rationale for selecting the preferred alternative? For example, a road connecting two points can follow a number of different routes. In this case, the EIA report must describe the process taken to select the most appropriate route based on a set of pre-determined criteria. The consideration of alternatives and the selection criteria used to identify the preferred alternatives must include environmental factors. The
Annex 3 18
information going into the decision and the decision-making process must be documented in the EIA report. For example, if "alternative means" refers to site selection for a large hydroelectric dam, the location of each alternative would have to be described, the environmental impacts of each alternative defined and the criteria and analysis of site selection presented.
6. Since the selection of alternatives can involve detailed technical analysis that includes more than just environmental factors, it may be preferable to present the details of this analysis as an appendix and include only the results and summary of this selection process in the body of the report. For example, a table listing the alternatives on one axis, and the criteria, such as reliability, cost, performance, inherent environmental effects and necessary mitigation measures, on the other axis may provide an effective summary.
7. Alternatives to the S ubproject. In some instances it will be necessary to consider “alternatives to” the subproject. This situation should not arise if the subproject is consistent with DMC’s development strategy, ADB’s Country and Strategy Program, and has been developed based on a sector strategy and roadmap. The EIA report should describe how the subproject fits into this larger strategic planning context. This context helps justify the subproject and demonstrates the requirements that may constrain the alternatives that are feasible or permitted.
8. However, in the case of potentially controversial subprojects, there may public concern that the subproject does not represent the best way to achieve stated development objectives. In addition, segments of the public may react negatively if they perceive that the EIA report has not considered alternatives to the subproject, or the preferred alternative is proceeding based on flawed assumptions. Therefore, if controversy is expected surrounding the fundamental reasons for the subproject, the EIA report should include a discussion of alternatives to the subproject.
9. One alternative that should receive special attention is the "no go" alternative. In some cases, this may be the only alternative to the subproject that can be realistically considered.
E. Anticipated Environmental Impacts and Mitigation Measures
10. Review Characteristics of each E nvironmental Impact. This section will evaluate the subproject’s expected impacts (in as quantified terms as possible) on each resource or value, and applicable sectoral environmental guidelines wherever any significant impact is expected (including environmental risk assessment, where appropriate. Environmental impacts to be investigated will include those due to (i) subproject location; (ii) caused by possible accidents; (iii) related to design; and (iv) during construction, regular operations, and final decommissioning or rehabilitation of a completed subproject. Where adverse effects are indicated, discuss measures for minimizing and/or offsetting these, and opportunities for enhancing natural environmental values will be explored. Both direct and indirect effects will be considered, and the region of influence indicated. This analysis is the key presentation in the report and if not sufficiently completed it may be necessary to delay the subproject until the analysis can be completed. It is necessary to present a reasonably complete picture of both the human use and quality of life gains to result from the subproject due to the utilization, alteration, and impairment of the natural resources affected by the subproject, so that fair evaluation of the net worth of the subproject could be made.
11. Mitigating Adverse Effects. For each significant adverse environmental impact, the
Annex 3 19
report will carefully explain how the subproject plan/design minimizes the adverse effects and in addition how the subproject plan/design, to the extent feasible, includes provision for offsetting or compensating of adverse effects and for positive enhancement of benefits or environmental quality. Where substantial cost of mitigation measures is involved, alternative measures and costs will be explored. 12. Irreversible and Irretri evable Impacts. The EIA report will identify the extent to which the proposed subproject would irreversibly curtail the potential uses of the environment. For example, highways that cut through stream corridors, wetlands, or a natural estuary can result in irretrievable damage to those sensitive ecosystems. Other impacts that may be irreversible include alteration of historic sites, and expenditure of construction materials and fuels. Also, subprojects through estuaries, marshes, etc., may permanently impair the area’s natural ecology; or elimination of recreation areas and parklands can precipitate drastic changes in the subproject area’s social and economic character.
13. Temporary Effects du ring Subproject Cons truction. In the event the construction phase of the subproject involves special environmental impacts (to be terminated on completion of construction), these will be separately discussed including proposed remedial measures.
F. Economic Assessment
14. This section may be drawn from the economic analysis conducted as part of the subproject feasibility study. It should include the following elements which should be integrated into the overall economic analysis of the subproject: (i) costs and benefits of environmental impacts; (ii) costs, benefits, and cost-effectiveness of mitigation measures; and (iii) discussion of impacts that have not been expressed in monetary values, in quantitative terms where possible (e.g. weight of volume estimates of pollutants).
G. Environmental Management Plan
15. The EMP describes how the mitigation and other measures to enhance the benefits of environmental protection will be implemented. It explains how the measures will be managed, who will implement them, and when and where they will be implemented. The following elements should be described in the EMP: (i) implementation of mitigation measures during subproject design; (ii) implementation of mitigation measures by contractors, and how impacts prevention will be incorporated in the materials procurement; (iii) social development program (e.g., resettlement plan, community training); (iv) contingency response plan for natural or other disasters, and subproject contingencies; and (v) environmental management and monitoring costs including mitigation costs.
16. The environmental monitoring plan describes the monitoring activities to ensure that adverse environmental impacts will be minimized, and the EMP implemented. The environmental monitoring plan will cover selected parameters to indicate the level of environmental impacts. It also describes how, when, and where the monitoring activities will be undertaken; who will carry them out; and who should receive the monitoring report. More importantly, it includes a proposal to carry out environmental compliance monitoring activities.
17. The present capacity of the executing agency to implement EMP should be described and implementation costs clearly identified.
Annex 3 20
H. Public Consultation and Information Disclosure
18. This section will (i) describe the process undertaken to involve the public in subproject design and recommended measures for continuing public participation; (ii) summarize major comments received from beneficiaries, local officials, community leaders, NGOs, and others, and describe how these comments were addressed; (iii) list milestones in public involvement (e.g., dates, attendance, topics of public meetings), and recipients of the report and other subproject-related documents; (iv) describe compliance with relevant regulatory requirements for public participation; (v) if possible summarize public acceptance or opinion on the proposed subproject; and (vi) describe other related materials or activities (e.g., press releases, notifications) as part of the effort to gain public participation. This section will provide of summary of information disclosed to date and procedures for future disclosure.
I. Conclusions
19. The EIA report will present the conclusions of the study including: (i) gains which justify subproject implementation; (ii) explanation of how adverse effects could be minimized or offset, and compensated to make these impacts acceptable; (iii) explanation of use of any irreplaceable resources; and (iv) provisions for follow-up surveillance and monitoring. Simple visual presentations of the type and magnitude of the impacts may aid the decision-maker.
Annex 4 21
Outline of Summary Environmental Impact Assessment (SEIA) Report
A. Introduction (1/2 page)
1. This section will include the purpose of the report, extent of the EIA study and brief description of any special techniques or methods used.
B. Description of the Subproject (1/2 page)
2. This section will include the type of and need for subproject, location, size or magnitude of operation and proposed schedule for implementation.
C. Description of the Environment (2-3 pages)
3. This section will include the physical and ecological resources, human and economic development and quality of life values in the area affected by the subproject. Where available, environmental standards will be used as the baseline for comparative purposes.
D. Alternatives (1-2 pages)
4. For each alternative, a summary of the probable adverse impacts and its relation to the subproject, and other alternatives will be discussed determine whether the subproject minimizes the environmental impact over all other alternatives and is within acceptable environmental impact limits. In most cases, environmental impacts "with" and "without" subproject alternatives should be examined.
E. Anticipated Environmental Impacts and Mitigation Measures (4-6 pages)
5. Environmental impacts, both direct and indirect, on different environmental resources or values due to subproject location, as related to design, during construction and regular operation will be discussed and mitigation, offsetting or enhancement measures will be recommended.
F. Economic Assessment (1-2 pages)
6. This section will include: (a) costs and benefits of environmental impacts; (b) costs, benefits and cost effectiveness of mitigation measures; and (c) for environmental impacts that have not been expressed in monetary values, a discussion of such impacts, if possible, in quantitative terms (e.g. weight or volume estimates of pollutants). This information should be integrated into the overall economic analysis of the subproject.
G. Environmental Management Plan (1-2 pages)
7. The EMP will describe the impacts to be mitigated, and activities to implement the mitigation measures, including how, when, and where they will be implemented. The environmental monitoring plan will describe the impacts to be monitored, and when and where monitoring activities will be carried out, and who will carry them out.
Annex 4 22
H. Public Consultation and Disclosure (1-3 pages)
8. This section will describe the process undertaken to involve the public in subproject design and recommended measures for continuing public participation; summarize major comments received from beneficiaries, local officials, community leaders, NGOs, and others, and describe how these comments were addressed; list milestones in public involvement such as dates, attendance, and topics of public meetings; list recipients of this document and other subproject related documents; describe compliance with relevant regulatory requirements for public participation; and summarize other related materials or activities, such as press releases and notifications. This section will provide of summary of information disclosed to date and procedures for future disclosure.
I. Conclusions (1 page)
9. This section will describe the gains which justify implementation of the subproject; explain how significant adverse environmental impacts will be mitigated or offset and compensated for; explain/justify use of any irreplaceable resources and; describe follow-up surveillance and monitoring.
Annex 5 23
Outline of an Initial Environmental Examination (IEE) Report
A. Introduction
1. This section usually includes the following:
(i) purpose of the report, including (a) identification of the subproject and subproject proponent; (b) brief description of the nature, size, and location of the subproject and of its importance to the country; and (c) any other pertinent background information; and (ii) Extent of the IEE study: scope of study, magnitude of effort, person or agency performing the study, and acknowledgement.
B. Description of the Subproject
2. Furnish sufficient details to give a brief but clear picture of the following (include only applicable items):
(i) type of subproject; (ii) category of Subproject; (iii) need for subproject; (iv) location (use maps showing general location, specific location, and subproject site); (v) size or magnitude of operation; (vi) proposed schedule for implementation; and (vii) description of the subproject, including drawings showing subproject layout, and subproject components.
3. This information should be of the same type and extent as is included in feasibility reports for proposed subprojects to give a clear picture of the subproject and its operations.
C. Description of the Environment
4. Furnish sufficient information to give a brief but clear picture of the existing environmental resources in the area affected by the subproject, including the following (to the extent applicable):
(i) Physical Resources: (e.g.)
(a) atmosphere (e.g. air quality and climate) (b) topography and soils, (c) surface water (d) groundwater (e) geology/seismology.
(ii) Ecological Resources: (e.g.)
(a) fisheries (b) aquatic biology (c) wildlife (d) forests
Annex 5 24
(e) rare or endangered species (f) protected areas (g) coastal resources
(iii) Economic Development: (e.g.)
(a) industries (b) infrastructure facilities (e.g. water supply, sewerage, flood control) (c) transportation (roads, harbors, airports, and navigation) (d) land use (e.g. dedicated area uses) (e) power sources and transmission (f) agricultural development, mineral development, and tourism facilities
(iv) Social and Cultural Resources: (e.g.)
(a) population and communities (e.g. numbers, locations, composition, employment) (b) health facilities (c) education facilities (d) socio-economic conditions (e.g. community structure, family structure, social well being) (e) physical or cultural heritage (f) current use of lands and resources for traditional purposes by Indigenous Peoples (g) structures or sites that are of historical, archaeological, paleontological, or architectural significance.
D. Screening of Potential Environmental Impacts and Mitigation Measures
5. Using the checklist of environmental parameters for different sector subprojects, this section will screen out “no significant impacts” from those with significant adverse impact by reviewing each relevant parameter according to the following factors or operational stages. Mitigation measures, where appropriate, will also be recommended environmental problems due to subproject location, and related to subproject design, construction, and operations. Potential environmental enhancement measures and additional considerations will also be covered.
E. Institutional Requirements and Environmental Monitoring Plan
6. This section should state the impacts to be mitigated, and activities to implement the mitigation measures, including how, when, and where they will be implemented. Institutional arrangements for implementation should be described. The environmental monitoring plan will describe the impacts to be monitored, and when and where monitoring activities will be carried out, and who will carry them out. The environmental management and monitoring costs should also be described.
F. Public Consultation and Information Disclosure
7. This section will describe the process undertaken to involve the public in subproject design and recommended measures for continuing public participation; summarize major comments received from beneficiaries, local officials, community leaders, NGOs, and others,
Annex 5 25
and describe how these comments were addressed; list milestones in public involvement such as dates, attendance, and topics of public meetings; list recipients of this document and other subproject related documents; describe compliance with relevant regulatory requirements for public participation; and summarize other related materials or activities, such as press releases and notifications. This section will provide of summary of information disclosed to date and procedures for future disclosure.
G. Findings and Recommendations
8. This section will include an evaluation of the screening process and recommendation will be provided whether significant environmental impacts exist needing further detailed study or EIA. If there is no need for further study, the IEE itself, which at times may need to be supplemented by a special study in view of limited but significant impacts, becomes the completed environmental assessment for the subproject and no follow-up EIA will be needed. If an EIA is needed, then this section will include a brief terms of reference (TOR) for the needed follow-up EIA, including approximate descriptions of work tasks, professional skills required, time required, and estimated costs. The Bank's Environment Guidelines provides a guide for preparing the TOR for different subprojects.
H. Conclusions
9. This section will discuss the result of the IEE and justification, if any, of the need for additional study or EIA. If an IEE, or an IEE supplemented by a special study, is sufficient for the subproject, then the IEE with the recommended institutional and monitoring program becomes the completed EIA.
Annex 6 26
Outline of Summary Initial Environmental Examination (SIEE) Report
A. Introduction (1/2 page)
1. This section will include the purpose of the report, extent of the IEE study and brief description of any special techniques or methods used.
B. Description of the Subproject (1/2 page)
2. This section will include the type of and need for the subproject; and subproject location, size or magnitude, operation, and proposed schedule for implementation.
C. Description of the Environment (2 pages)
3. This section will include the physical and ecological resources, human and economic development, and quality of life values.
D. Forecasting Environmental Impacts and Mitigation Measures (2-4 pages)
1. This section will identify "no significant impacts" from those with significant adverse impacts and will discuss the appropriate mitigation measures, where necessary.
E. Institutional Requirements and Environmental Monitoring Plan (1 page)
5. This section will describe the impacts to be mitigated, and activities to implement the mitigation measures, including how, when, and where they will be implemented. The environmental monitoring plan will describe the impacts to be monitored, and when and where monitoring activities will be carried out, and who will carry them out.
F. Public Consultation and Disclosure
6. This section will describe the process undertaken to involve the public in subproject design and recommended measures for continuing public participation; summarize major comments received from beneficiaries, local officials, community leaders, NGOs, and others, and describe how these comments were addressed; list milestones in public involvement such as dates, attendance, and topics of public meetings; list recipients of this document and other subproject related documents; describe compliance with relevant regulatory requirements for public participation; and summarize other related materials or activities, such as press releases and notifications. This section will provide of summary of information disclosed to date and procedures for future disclosure.
G. Findings and Recommendations (1-2 pages)
7. This section will include an evaluation of the screening process, and recommendation will be provided whether significant environmental impacts exist needing further detailed study or EIA. If there is no need for further study, the IEE itself, which at times may need to be supplemented by a special study in view of some small significant impacts, becomes the completed EIA for the subproject and no follow-up EIA will be needed. If further additional study is needed, then this section will include a brief terms of reference (TOR) for the needed follow- up EIA, including approximate descriptions of work tasks, professional skills required, time
Annex 6 27
required, and estimated costs. The Bank's Environment Guidelines provides a guide for preparing the TOR for different subprojects.
H. Conclusions (1/2 page)
8. This section will discuss the result of the IEE and justification if any of the need for additional study or EIA. If an IEE or an IEE supplemented by a special study is sufficient for the subproject, then the IEE with the recommended institutional requirements and monitoring program become the completed EIA.
Annex 7 28
Outline Terms of Reference for Consulting Services for Environmental Assessment
A. Objectives
1. The objective of the services are (a) to conduct environmental impact assessment (EIA)/ initial environmental examination (IEE) of the proposed subproject to identify potential environmental impacts on physical, environmental, ecological, social, cultural and economic resources, and (b) to prepare EIA/IEE report along with environmental management plan. The duration of an EIA study is 5 months and an IEE study is 3 months.
B. Scope of Work
2. The consultant’s scope of work will include the following tasks:
(i) reviewing prevailing government regulations and donor guidelines governing the assessment and management of environmental impacts of road subprojects; (ii) prepare a scoping document for the environmental studies to be carried out under the subproject; (iii) undertake the EIA/IEE study to assess the direct and in-direct environmental impacts of the Subproject such as: (a) ecological impacts (plants and wildlife); (b) soil erosion and desertification; (c) protection of wetland habitat; (d) impact of quarry sites; (e) impact of construction camps on local environment (natural and social); (f) operational traffic safety measures; (g) areas with known archeological value; and (h) potential spills of hazardous or toxic chemicals and an appropriate response plan for the Subproject; (iv) prepare the EIA/IEE report and its summary in accordance with ADB’s Environmental Policy (2002) and related Environmental Assessment Guidelines (2003) as well as ADB's Public Communications Policy (2005); (v) the EIA/IEE study should address all potential direct and indirect environmental impacts of the subproject. The assessment of environmental impact should be presented in the order of subproject cycle: pre-construction, construction and operation. This EIA/IEE report should include the detailed environmental management plan that should be included in the bidding document; Analyze the likely impacts during construction and operation and suggest appropriate mitigation measures; (vi) conduct formal public consultations with affected people (two consultations for EIA and one consultation for IEE). The first consultation aims to gather environmental concerns from affected people and the final consultation aim to share the result of the assessment and the proposed mitigation measures. The list of people attended the consultation, time and locations; subject discussed during consultation should be recorded in systematic manner and should be attached in the EIA/IEE report as an appendix; (vii) solicit and incorporate comments on the draft EIA and summary EIA reports from ADB, MPW, NGOs, civil society, and other stakeholders. Finalize the report to accommodate inputs from all the stakeholders; and (viii) submit the reports to MNP and make presentation as required by MNP to obtain an environmental impact clearance certificate or equivalent.
Annex 7 29
C. Organization and Staffing
3. The services are expected to be provided a team comprising one international and one national consultant.
4. The International Environmental Specialist shall have at least 15 years experience and familiarity with all aspects of environmental management and with significant experience in environmental management and monitoring of subprojects, environmental assessment and / or implementation of environmental mitigation measures on construction subprojects. The specialist shall also have experience working in teams of multi-discipline experts and leading a national team of consultants. Candidates with higher degrees in environmental engineering or environmental science or environment management are preferred.
5. The National Specialists shall at least be graduates in environmental science, environmental engineering, geological science, engineering hydrology, biology or related discipline with significant experience in environmental management and monitoring of subprojects, environmental assessment and/or design and implementation of environmental mitigation measures.
D. Budget
6. The estimated cost for preparation of each IEE and EIA are provided in Table 1 and Table 2, respectively. A team of International and national specialists are recommended for these studies. Generally for government funded subprojects, the environmental assessment team would include an environmental specialist, a geologist, and a biologist.
Table 1: Estimated Cost of IEE Preparation for each Subproject Item Unit Quantity Unit Cost ($) Total International Environmental Specialist Person-month 3 25,000 75,000 National Environmental Specialist Person-month 3 3,500 10,500 Land Transportation Months 3 1,250 3,750 Data collection, sample analysis Lump sum 1 4,000 4,000 Communication Months 3 500 1,500 Report production and distribution Lump sum 1 2,000 2,000 Public Consultation Lump sum 1 2,000 2,000 Total 98,750
Table 2: Estimated Cost of EIA Preparation for each Subproject Item Unit Quantity Unit Cost ($) Total International Environmental Specialist Person-month 4 25,000 100,000 National Environmental Specialist Person-month 4 3,500 14,000 National Hydrologist Person-month 2 3,500 7,000 National Geologist Person-month 2 3,500 7,000 National Biologist Person-month 2 3,500 7,000 Land Transportation Months 5 1,250 6,250 Communication Months 5 500 2,500 Data collection and sample analysis Lump sum 1 7,000 7,000 Report production and distribution Lump sum 1 2,000 2,000 Public Consultation Lump sum 2 2,000 4,000 Total 156,750
Annex 7 30
E. Supervision
7. The team will work in association with the PMU/ARD, reporting to the subproject director of the PMU/ARD on a day-to-day basis.
F. Outputs
8. The team’s outputs will include: (i) an inception report reviewing the available environmental reports and prepare preliminary assessment of impacts associated with the proposed subproject, (ii) an interim report; (iii) a draft final report, containing a description of subproject environment, anticipated environmental impacts for various alternatives and proposed environmental management, monitoring and mitigation plan, and (iv) final report incorporating comments from ADB and other stakeholders.
Environmental Assessment Report
Initial Environmental Examination Report Project Number. 42145 November 2011
Armenia: Preparing the North-South Road Corridor Development Program (Tranche 1 Roads Improvement Project—Two Road Sections: Yerevan to Ashtarak and Yerevan to Ararat)
Prepared by PADECO Co. Ltd., Japan (Peter Marriott, International Environmental Specialist, and Inessa Gabayan, National Environmental Specialist) for the Asian Development Bank (ADB). Updated by “NSRP” PMU SNCO.
The initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
CURRENCY EQUIVALENTS (as of 17 November 2011) Currency Unit – Armenian Dram (AMD) AMD1.00 = $ .0026 $1.00 = AMD384.608
LIST OF ABBREVIATIONS ADB – Asian Development Bank EIA – Environmental Impact Assessment EM – Environmental Manager (in “NSRP” PMU SNCO) EMP – Environmental Management Plan IEE – Initial Environmental Examination PMC ES – Project Management Consultant Environmental Specialist MFF – Multi-tranche Financing Facility MNP – Ministry of nature Protection MOTC – Ministry of Transport and Communications NE – North East NPE – Nature Protection Expertise “NSRP” PMU SNCO – “North-South road Corridor Investment Program PMU” SNCO PPP – Purchasing Power Parity RA – Republic of Armenia ROW – Right-of-Way SEI – State Environmental Inspectorate SNCO – State Non-Commercial Organization SW – South West
UNITS km – kilometers
NOTE In this report, "$" refers to US dollars.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
TABLE OF CONTENTS
I. INTRODUCTION and SUMMARY
A. Project Background B. IEE Report Outline and Methodology C. Armenian and ADB Environmental Assessment Requirements D. Alternatives to the Proposed Project
II. PROJECT DESCRIPTION
A. Project Location B. Tranche 1 Project
III. ENVIRONMENTAL BASELINE – EXISTING CONDITIONS
A. Physical Resources B. Ecological Resources C. Human Use of Resources D. Archeological resources and Human Quality-of-Life Values (Social and Cultural Resources)
IV. SCREENING FOR POTENTIAL ENVIRONMENTAL IMPACTS
A. Environmental Parameters that may be Impacted B. Activities that may Create Environmental Impacts C. Environmental Screening: Potential Impacts D. Significance of Potential Impacts
V. ENVIRONMENTAL IMPACT PREVENTION and MITIGATION MEASURES
A. Environmental Impact Prevention and Mitigation B. Environmental Management Plan (EMP) C. Responsibilities for Impact Prevention and Mitigation D. Environmental Enhancement Measures E. Environmental Monitoring Program F. Cost of Impact Prevention, Mitigation, Monitoring and Enhancement G. Environmental Management Seminars
VI. PUBLIC CONSULTATION and INFORMATION DISCLOSURE
A. Consultation Process B. Community Involvement to Date. ANNEX 1 to Chapter 6: Questionnaire for Face-to-Face Survey.
VII. SUMMARY, CONCLUSIONS, RECOMMENDATIONS
A. Summary B. Environmental Screening – Potential Impacts and their Significance C. Recommendations
REFERENCES
LIST of FIGURES
Figure 1: North-South Roads Corridor Alignment
Figure 2: Ministry of Nature Protection (MNP) Organization Chart
Figure 3: Armenian Laws and Codes Pertinent to Roads and Environment
Figure 4: RA Environmental Clearance Procedure – Flow Diagram
Figure 5: Location of the Two Project Road Sections
Figure 6: Geology of Armenia
Figure 7: Traffic Forecast in number of vehicles per day
Figure 8: Construction Activities that may Create Environmental Impacts
Figure 9: Works Activities and Potential Impacts
Figure 10: Environmental Impact Mitigation – Summary Environmental Management Plan
(EMP)
Figure 11: EMP and Operating Plans – Clauses for Inclusion in Contract Docs.
Figure 12: Monitoring Requirements - Site Preparation and Construction
Figure 13: Environmental Stakeholder Groups Met to Date
Figure 14: Results of Survey of Villagers (94 respondents)
I. IN TRODUCTION
A. Project Background
1. Armenia is a land-locked, mountainous country in the Lesser Caucasus region, bordered by Azerbaijan, Georgia, Iran and Turkey. Being land-locked, and experiencing many border issues, Armenia has been restricted in its ability to develop and to maintain reliable land transport linkages with the outside world particularly to Europe, Iran and Russia and, via Georgia, to the Black Sea.
2. The Armenian Government (RA) has made efforts to strengthen its economic linkages with other economies via land bridges to Central Asia, the Black Sea and Europe and, thus, create increased trade and investment opportunities. The RA formulated the Armenia Transport Strategy 2020 and the North-South Road Corridor Program under it, with a priority to rehabilitate, reconstruct and expand international transport corridors -- in line with the ADB, Armenia…Country Strategy to support regional cooperation and rehabilitate regional road and railway infrastructure.
3. The RA has selected the Bavra-Yerevan-Agarak route as the north-south road corridor to be rehabilitated, reconstructed and expanded and has appointed the “North-South road Corridor Investment Program PMU” SNCO (“NSRP” PMU SNCO) of the Ministry of Transport and Communications (MOTC) to co-ordinate the work. The Program is to be funded by the Asian Development Bank (ADB) under a multi-tranche funding facility (MFF).
4. The MFF is designed to rehabilitate and upgrade national north-south roads to form a new, upgraded and expanded N-S highway. The main objective is to widen the existing 2-lane roads (often in poor condition) to become 4-lane divided roads along existing alignments wherever possible or to construct new alternate 2-lane roads where a single 4-lane road would not be feasible.
5. The Project, to be financed from Tranche 1 under the MFF, is to improve two road sections of the N-S Corridor, namely, the M-1 section of road north from Yerevan to Ashtarak and the M-2 section of road south from Yerevan to Ararat. At Ashtarak and Ararat, the road sections to be improved under the Project join the existing 2-lane roads from Ashtarak north to Gyumri and Bavra and from Ararat south to Goris and Agarak respectively.
6. The location of the existing N-S national roads M-1 and M-2 and the provincial (marz) boundaries is shown on Figure 1.
Figure 1: North-South Roads Corridor Alignment
B. Initial Environmental Examination Report Outline and Methodology
7. This Initial Environmental Examination (IEE) report assesses the environmental settings of the corridors through which the Project road sections pass, identifies the likely impacts that may be created, determines the significance of those impacts, and presents a summary Environmental Management Plan (EMP) and a Monitoring Program.
8. The methodology is based on the ADB, Environmental Policie s (2002) and the ADB, Environmental Assessment Guid elines (2003), the RA IEA requirements, and the joint experience of the International and National environmental consultants involved in the IEE.
9. Background data and information was obtained from published and unpublished sources, e.g., on: climate, topography, geology and soils, natural resources, flora and fauna, agriculture, and socio-economic data.
10. Several site inspections were conducted jointly by the International Environmental Specialist and National Counterpart during June and July 2009. The existing roads were driven and areas of potential environmental significance assessed carefully.
11. Discussions were held with a number of stakeholders and a face-to-face survey was conducted of villagers along one of the roads in the N-S roads corridor in order to determine their perceptions of the level of impact from road works. Data and information obtained have been included where appropriate in the IEE Report.
C. Armenian and ADB Environmental Assessment Requirements
12. This IEE Report is to satisfy both the ADB and RA requirements with regard to environmental protection and management.
1. Armenian Laws Governing Environmental Management and Assessment
13. The RA Ministry of Nature Protection (MNP) is the principal national environmental administrative authority. Within it are several agencies or directorates administering various aspects of the Laws on Environmental Protection, EIA and Protected Natural Areas. See the MNP organization chart in Figure 2.
14. Of importance to EIA and IEE are the two state non-commercial organizations (SNCOs): a) Nature Protection Expertise (NPE) responsible for administering the EIA process, and b) the State Environmental Inspectorate (SEI) responsible for overseeing compliance with environmental laws and regulations
15. The EIA process and the SEI power to inspect are the principal tools used by the MNP to achieve compliance with environmental management principles. As well as the MNP, other ministries and agencies have responsibilities to administer natural resources and environmental matters (e.g., Ministries of Agriculture and Health, the State Committee for Water Systems, etc.). The laws and regulations that may relate to this project are summarized in Figure 3.
16. The RA environmental clearance procedures are set out in Figures 4. The ADB and MOTC will review the IEE Report and pass it to the MNP. The Report will then be made public by the NPE which invites public and government comment on the IEE and the Project before clearing it for implementation by the MOTC.
Figure 4: RA Environmental Clearance Procedure – Flow Diagram
2. ADB Environmental Assessment Requirements
17. The ADB requires that environmental impacts likely to be caused by the Project be identified during the project planning and pre-feasibility stages and prevented or mitigated as much as possible during the construction and operational phases.
18. For environmental management purposes the roads improvement Project assessed here is classified by the ADB as a Category B project. This means that impacts are not expected to be highly significant but nevertheless need to be identified and reported in an Initial Environmental Examination (IEE) report.
19. Public disclosure and opportunities for the public (and affected ministries, agencies and local authorities) to express their concerns about the project form an important part of the environmental assessment process. Therefore, the ADB will post the Summary IEE Report (attached as Appendix 1) on its website.
D. Alternatives to the Proposed Project
20. The ADB, Environmental Assessment Guide lines, 2003 state that alternatives to the project are to be considered and compared with the project in terms of their potential environmental impacts, capital and recurrent costs, suitability under local conditions and the institutional, training and monitoring requirements and that the economic values for alternatives
should be estimated where possible.
21. The Tranche 1 consists from two sections. a. Section 2. Rehabilitation and improvements of road safety measures of the existing M2 Yerevan to Ararat 4-lane road from Km 9+312 to Km 47+ 400.
Works on the existing M2, Yerevan to Ararat (approx. 38 km) 4-lane section consist of:
(i) Yerevan-Artashat section (19 km): reconstruction of median to provide continuous safety barriers and widened carriageway; leveling of existing asphalt and overlay with new cement concrete pavement; construction of additional ramps at three interchanges and rehabilitation of other ramps; installation of road lighting at interchanges; (ii) Artashat-Ararat section (19 km): upgrading of road signs and markings to international standards. b. Section 3. Rehabilitation of the existing M1 Yerevan to Ashtarak road from Km 18+370 to Km 29+773 (Section 3).
Works on the M1, Yerevan to Ashtarak (approx. 12 km) section will reconstruct the existing pavement, improve drainage and shoulders and carry out repairs to existing concrete structures. The new road pavement will be a 26 cm thick concrete slab on crushed stone base course. One existing over-bridge requires demolition and replacement by a new bridge. Repair works are required to eight other existing bridges.
22. There is no other alternative. The economic factors and the benefits from safety improvements support the Project but short of not implementing it, there is no alternative.
II. PROJECT DESCRIPTION
A. Project Location
23. The Project road locations are shown on Figure 6.
Figure 5: Location of the Two Project Road Sections: 4-Lanes on M-1 North of Yerevan, and 4-Lanes on M-2 South of Yerevan
B. Tranche 1 Project
24. The overall MFF objective is to improve existing 4-lane divided roads, widen existing 2- lane roads (often in poor condition) to 4-lane divided roads along the existing alignment wherever possible, or construct alternative 2-lane roads where a single 4-lane road would not be feasible.
25. The two road sections to be improved under the Project are two sections of the North- South Road Corridor to be rehabilitated and expanded under the MFF. The location of the road st sections to be improved under the 1 Tranche of the MFF, and covered in this IEE report, stretch short distances north and south of Yerevan.
26. The 18.4km M-1 4-lane road section north of Yerevan was originally built over the period 1975 to 2004. Its condition is deteriorated and its standard varies so that the road-bed needs improvement to meet the design and construction standards normally associated with international transit routes. The 38.0km M-2, 4-lane road section south of Yerevan was built more recently and is in relatively good condition. Neither road section is adequately drained, the shoulders in many parts are very narrow and not properly paved, there are many randomly located U-turns, signage, road markings and lighting are absent or inadequate, there are insufficient crash barriers and median separation barriers and road structures need to be investigated to determine their structural integrity.
27. A key objective of the Project is to ensure compliance with the road safety and signage requirements under the European Agreement on Main International Traffic Arteries to which the RA is a signatory. A second objective is to ensure the structural integrity of road structures and that drainage is adequate to enhance road-bed longevity. Shoulders, guard rails, road marking, turning lanes and proper drainage will be added as necessary.
28. Road works are planned to be fully confined to the existing ROW and be constructed in sections, one side of the 4-lane carriageway at a time, in order to enable continued use of the existing road during construction. Transport of materials will be confined to the existing 4-lane road, to the one-side being worked on, when possible. The road works on both road sections will include the following:
(i) Constructing proper drainage side-ditches and cross-drainage as required. (ii) Improving the road-shoulders (iii) Improving traffic safety measures: signage, guardrails, traffic markings and turning lanes. (iv) Repairing road structures: over-passes, under-passes, and cut and embankment slopes.
29. Construction is planned to begin at the end of 2011 and be finished by 2013.
III. ENVIRO NMENTAL BASELINE – EXISTING CONDITIONS
A. Ph ysical Resources
30. Both road sections are located in arid areas (annual precipitation less than 400mm) with most precipitation falling as rain in spring and autumn. Humidity is low, varying from a high of 78% in April/May, to a low of 56% in August. The temperature regime is that of the dry continental climate zone with average January temperatures (the coldest month) in the minus 4- 6 degrees C range. In July (the warmest month), the range is 25-38 degrees C.
31. The geology is very mixed but essentially a combination of volcanic basalt, faulted uplift and sedimentary infill overlying lava. The geological origins lie in the Pliocene, Paleocene and Cretaceous periods. To the north of Yerevan the basic geology is of uplifted Late-Quaternary- Pliocene volcanic deposits, mostly basalt and andesites broken down by earthquake and climatic elements into fractured rock and gravelly soil over most of the road corridor with small areas overlain by recent sedimentary material of volcanic origin. To the south the Ararat valley is sedimentary infilling of a basalt basin (see Figure 7).
32. Earthquakes occur from time to time, the last in December 1988, with an epicenter NE of Gyumri near the village of Spitak. The earthquake had little effect on the land and no apparent effect on structures located within or near the Project road sections. There are many small earthquakes and several large earthquakes have occurred in Central Armenia from time to time, th th including early in the 19 and 20 centuries. The seismic factor ranges 8-9 with an earthquake wave acceleration rate: g = 0.4 m/sec.
33. The landscape north of Yerevan along the M-1 Project road corridor is gently rolling uplands 1,060m to 1,270m in elevation. The Kasakh River dissects the landscape in a deep gorge north of Yerevan. There are no other surface streams along the north road section. The landscape south of Yerevan along the M-2 Project road corridor is flat and about 1,100m in elevation. There are no surface streams but the Ararat Valley is a noted artesian basin fed by snow melt and a sub-surface network of aquifers through the fractured lava. The land is irrigated wherever possible by water from aquifers and that carried in large pipes and canals from the mountains to the east.
Figure 6: Geology of Armenia
B. Ecological Resources:
34. The original fauna in the road corridors included steppe and semi-desert species has been largely supplanted. The native flora of arid and semi-desert varieties survive better in the corridor through which the M-1 4-lane north road section passes than the 4-lane M-2 south road section passes. The desiccated natural landscape along the north road corridor remains in patches amongst the mixed urban use land but along the south road corridor the native plants have been largely replaced by domestic plants except on the gravelly and saline bare patches where sage and similar species predominate.
35. There are no original trees along either road section, and few trees of any substance. Within the existing rights-of-way, to which the planned improvement and construction activities will be confined on both road sections, there are only the road itself, medians, limited shoulders, ditches and protective strips. There are no unique areas, no protected areas and no forests or ecological reserves within 500m either side of the right-of-way (ROW).
36. Within the Ararat Marz are the Khosrov Forest Reserve and a RAMSAR site 3-5km to the east of the ROW and a large area of aquaculture ponds in a former natural wetland some 2- 4km to the SW of the ROW.
C. Human Use of Resources
37. The existing 4-lane roads form important features of the existing environmental baselines along both road corridors and present a significant barrier to people trying to cross the road (particularly over north section because of the variable horizontal and vertical alignment). There are no industrial buildings, facilities, commercial operations or residences located within either ROW. No land purchase or resettlement will be necessary, and neither ROW passes close to any villages.
38. The areas near the Yerevan ends of both alignments are semi-urban transition zones where vacant land, industrial activities, run-down and disused industries and small residential areas are intermixed with remnant agricultural uses.
39. Agriculture along the north road section is limited to small orchards and a few hay fields towards Ashtarak. In complete contrast, agriculture predominates along both sides of the alignment in the south. The flat, irrigated land is intensely cropped with vineyards, wheat, orchards and market-gardens wherever irrigation is possible.
40. Energy Sources and Mining Activities. Within the road corridors of both road sections there are no nuclear, hydro or other electrical generating plants and no active mining.
41. Tourism Attractions and Facilities. There are no tourist attractions within or close to the road corridors.
D. Archeological resources and Hu man Quality-of-Life Values (Socioeconomics and Sociocultural Resources)
42. Close to the ROW on the north road section there are two important known archeological sites protected by the RA Department of Historical Monuments (Ministry of
Culture). One site stretches 500m along the edge of the ROW between it the Kasakh River near the bridge over the River and down the valley side to the River itself. The second site is located astride the interchange at Agarak and 200m either side of it. There may also be undiscovered archaeological remains or artifacts below ground (see EMP). There are no known sites within 100m of the ROW to the south. Social conditions are as to be expected where the annual average per capita monetary income is about US $2,000 (lower in rural areas and already 20% lower in 2009 than it was in 2007) but people manage to live above that level in terms of PPP, standard of living, lifestyles and social-support services. Many people in the Project corridors work in Yerevan. But for the marzes (Aragatsotn and Ararat) as a whole, particularly in the south corridor more than 75% of the population is employed in agriculture as owner/operators of as employees. There are many schools in the two provinces concerned. As well as general education schools, there are pre-schools, state and non-state secondary schools and specialist schools in music and sports. Communities are generally well served with health clinics.
IV SCREENING FOR POTENTIAL ENVIRONMENTAL IMPACTS
A. Environmental Parameters that may be Impacted
43. The different elements of the environment that maybe impacted or affected by the road rehabilitation and expansion project are clustered under the four aspects of the environment, namely, the impact on the:
(i) Physical Environment: Water, land and air quality (ii) Ecological or Biotic Resources: Migrating mammals (iii) Human Use of Resources: Agriculture, rural roads and transport (iv) Human Quality-of-Life: Health and safety, incomes and employment, archaeological and historical sites.
B. Activities that may Create Environmental Impacts
44. Project Summary. The two road sections to be improved under the Project are parts of the North-South Road Corridor to be rehabilitated and expanded under the MFF. The location of the two road sections to be improved under the 1st Tranche Project are: a) Rehabilitation and improvements of road safety measures of the existing M2 Yerevan to Ararat 4-lane road from Km 9+312 to Km 47+ 400 and b) Rehabilitation of the existing M1 Yerevan to Ashtarak road from Km 18+370 to Km 29+773.
45. Neither road section is adequately drained, the shoulders in many parts are very narrow and not properly paved, there are many randomly located U-turns, signage, road markings and lighting are absent or inadequate, and there are insufficient crash barriers.
46. A key objective of the Project is to ensure compliance with the road safety and signage requirements under the European Agreement on Main International Traffic Arteries to which the RA is a signatory. A second objective is to ensure the structural integrity of road structures and that drainage is adequate to enhance road-bed longevity. Shoulders, guard rails, road marking, turning lanes and proper drainage will be added as necessary.
47. Road works are planned to be fully confined to the existing ROW and be constructed in sections, one side of the 4-lane carriageway at a time, in order to enable continued use of the
existing road during construction. Transport of materials will be confined to the existing 4-lane road, to the one-side being worked on, when possible.
48. Traffic growth for the next 20 years has been estimated based on the projected growth of GDP and an estimate of demand elasticity; little or no change in population is expected over the period. The results of the traffic forecast are shown in Figure 8.
Figure 7 – Traffic Forecast in number of vehicles per day
2012 2015 2020 2025 2032 With Project 13060 17110 24490 36660 65605 Without 13060 15550 22270 33330 59641 Project
49. Eight construction activities with potential to impact on the four different aspects of the environment, including human safety are summarized in Figure 8. Note: The eight construction activities relate only to the north road section (4-lanes of M-1).
50. All eight works-related activities have the potential to create significant impacts on the environment or human safety. However, all impacts and safety issues can be prevented or mitigated by following sound engineering practices and implementing the impact prevention and mitigation measures set out in the Environmental Management Plan (EMP).
51. The operation or use of the improved roads may have some minor impacts on the local environment, air quality and noise levels may change but the level of change will not be significant.
Figure 8: Construction Activities that may Create Environmental Impacts
C. Environmental Screening—Potential Impacts
52. Works Activities. The works activities listed in Figure 8, above, are linked to the main causes of impacts and the elements of the environment that may be impacted in the Environmental Impact Screening Table (Figure 9).
53. The improvement works will impact the baseline environment only via minor impacts. Earthworks, construction activities and quarry and borrow-pit operations may create a number of short-term impacts on air and land quality, health and safety, may cause local flooding (by
diverting runoff) and unearth archaeological sites or artifacts. Other activities that may cause negative impacts are asphalt plant operations, transport of materials, storage and handling of diesel, traffic in and near work sites, and work camp site preparation and operations.
54. Under the Project, there will be no changes to vertical or horizontal alignments. There will be no removal of top-soil, no new cut or fill sections and no bridge construction. Most construction works will be on existing M2 Yerevan to Ararat 4-lane road from Km 9+312 to Km 47+ 400 and on existing M1 Yerevan to Ashtarak road from Km 18+370 to Km 29+773. Works on the existing M2, Yerevan to Ararat (approx. 38 km) 4‐lane section consist of:
(i) Yerevan-Artashat section (19 km): reconstruction of median to provide continuous safety barriers and widened carriageway; leveling of existing asphalt and overlay with new cement concrete pavement; construction of additional ramps at three interchanges and rehabilitation of other ramps; installation of road lighting at interchanges; (ii) Artashat-Ararat section (19 km): upgrading of road signs and markings to international standards.
Rehabilitation of the existing M1 Yerevan to Ashtarak road consist of
(i) Works on the M1, Yerevan to Ashtarak (approx. 12 km) section will reconstruct the existing pavement, improve drainage and shoulders and carry out repairs to existing concrete structures. The new road pavement will be a 26 cm thick concrete slab on crushed stone base course. One existing over-bridge requires demolition and replacement by a new bridge. Repair works are required to eight other existing bridges.
55. Digging may unearth archaeological sites or artifacts. Therefore, care needs to be taken, particularly around the two known archaeological sites near the north road section. Over the south section (Yerevan to Ararat) works will be limited to shoulder, drainage and culvert improvements; little material will be removed or new material placed, and there are no known archaeological sites within 100m of the ROW.
56. The disposal and replacement of up to 300,000m3 of sub-standard material from the existing north road section will require up to 100 truck movements per day over the construction period. With the current average daily traffic (ADT) of 11,680 vehicles including 13% trucks and other large vehicles, the works-truck traffic will add less than 5% to the existing ADT for large vehicles.
57. Operation of the Improved Road. Minor positive impacts will be created. Air quality will improve, due to the smoother travel and better fuel combustion, road accidents will reduce due to the improved: safety barriers, road markings, lighting and the control of U-turns. Air quality and noise levels may be affected but it is unlikely that the level of change will be significant.
58. Noise. A number of elements of the construction activities have the potential to cause noise impacts. Construction noise levels at nearby receptors will vary throughout the construction period depending on the activities carried out, the distance to sensitive receptors, as well as atmospheric conditions. These mitigation measures, that should be included in EMP, will minimize noise impacts:
(i) siting of construction camps away from residential areas; (ii) distancing noisier activities away from receptors where practicable; (iii) scheduling of noisy activities towards the middle of the day and avoiding night time activities; (iv) minimizing the need for heavy vehicles to pass through residential areas by specifying routes along public roads, site access points, and haul routes; (v) installing and maintaining effective exhaust silencing systems on vehicles and equipment; etc.
59. Air Quality. No quantitative air quality monitoring data was available for this assessment. In the last 15 years air quality in the city has improved, largely as a result of the closure of soviet era industries which were significant polluters. The gradual increase in vehicle numbers will lead to some increases in pollutants but this is likely to be offset by the implementation of more stringent emission standards and improvements in engine efficiency.
D. Significance of Potential Impacts
60. Estimating significance involves careful consideration of the nature of each potential impact. Significance is defined by three factors: the magnitude including duration of the impact, the scope or area that may be affected, and the probability or frequency of occurrence. Each potential impact is considered against each of the three factors and assessed in-depth with reference to the environmental baseline and its sensitivity
61. Short-term negative impacts will be created on water, land and air quality (and noise) and health and safety. These environmental elements are most likely to be impacted along the north road section, and rural roads may be damaged by the heavily laden trucks carrying earth, gravel and other works materials—depending on the truck routes taken. The contractor will therefore be required to re-instate pavements along transport routes at the end of the construction period if damage has occurred.
62. The area is arid, hence, there is very little water that may become affected and no improvements are foreseen for the high bridge over the Kasakh River. Therefore, impacts on water quality are expected to be insignificant. In order to prevent any pollution of the river occurring in the event of an accident on the bridge catch drains will be included in the design to ensure that surface flows are directed away from the river.
63. The increase in traffic along existing sections of the carriageway when they are used to divert traffic around the resurfacing works may lead to increased damage to the pavement. The tender and contract documents will require the contractor to maintain the pavement of the carriageways for those sections that are being used for diversions at a standard suitable for the volume of traffic.
64. There are no ecologically important or sensitive environmental elements and few human use factors that may be seriously affected. The most important possible impact issue is the potential to unearth archaeological sites or artifacts (addressed in the EMP).
65. Air quality impacts will be confined to localized dust nuisance. This may be significant
but manageable. Similarly noise may be significant, localized and manageable. Impacts on land quality are expected to be very minor because works will be minor on the south road section and confined to the existing ROW of the north road section. Hence, the likely impact on land is considered to be insignificant and manageable.
66. Health and safety impacts may be significant but preventable at all locations.
67. Actual impacts will be short-term and insignificant. Nevertheless, all impacts have been addressed in the EMP, the implementation of which will prevent or mitigate them.
68. Short-term positive impacts will be created via local employment and spin-off effects and the associated increase in short-term expenditure. Construction will create a number of local jobs to prepare and re-construct earthworks, operate and restore borrow pits and quarries and to transport and apply construction materials. In-turn, households and small businesses will benefit significantly over the short-term.
V. ENVIRONMENTAL IMPACT PREVENTION and MITIGATION MEASURES
A. Environmental Impact Prevention and Mitigation
69. The environmental impacts that may be created by the project were identified above. They are well known to competent civil engineers and competent construction companies – as are the standard impact prevention and mitigation measures to address them. Nevertheless, in order to ensure understanding of required prevention and mitigation measures, an Environmental Management Plan (EMP) and appropriate clauses for inclusion in works contracts are summarized below
70. To further encourage understanding of and compliance with good environmental practices, Environmental Management seminars are proposed
B. Environmental Management Plan (EMP)
71. The EMP summarized in Figure 1 0 and discussed below, is designed to address the impacts identified in Section 4.0 by guiding engineers and contractors in the prevention and mitigation of environmental impacts related to construction activities, to guide monitoring by NSRP SNCO, SEI and the International Environmental Specialist (PMC ES), and to guide NSRP SNCO in the subsequent operation of the road. The Summary EMP:
(i) Links road works activities, their potential impacts and their prevention or mitigation. (ii) Provides the basis for the EMP, to be added to by Contractor statements of intent to comply and the detailed planning documents to be prepared by the contractor prior to commencement of specific, identified activities (iii) Forms the basis for preparing a Monitoring Program for checking on compliance with impact prevention and mitigation measures
1. Contractor to Prepare EMP and Operating Plans for Approval by Engineer
72. Prior to commencing site preparation and construction activities, the Contractor will prepare a Draft EMP and Monitoring Program guided by Chapters 4 and 5 of this report,
particularly the Summary EMP (Figure 10). The Contractor is advised to simply copy the Summary EMP below and prepare the required Operating Plans (referred to in the Summary EMP) and add a Performance Commitment Section including places for the signatures of the Contractor, Engineer and Works Foremen.
73. The Draft EMP will be approved by the Engineer and serve to support consultations in affected communities (village leaders and villagers) and with responsible authorities at the central and provincial (marz) levels. The EMP will be revised as required on receipt of comments from communities and the responsible authorities and then finalized. When finalized as the Approved EMP, the Engineer, Contractor and Works Foremen will sign it testifying to their agreement to comply with it.
74. Consultations with affected communities will help to gain local input/understanding, to guide revisions when warranted, and to support monitoring.
75. The Contractor will prepare suitable Operating Plans as required to guide satisfactory implementation of key activities that may create significant environmental impacts. The overall requirements of each Operating Plan are highlighted in Figure 10 as performance clauses to be incuded in the Main Contract Documents.
Figure 10: Environmental Impact Mitigation – Summary Environmental Management Plan (EMP)
Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors 1. Construction: (i) Dust and emissions (ii) Traffic Construction and Related Activities The Contractor will prepare an Environmental Management hazards and safety Plan (EMP) for approval by the Engineer The EMP will be guided by the IEE - prior to commencing site preparation and construction. (i) Earthworks (iii) Work site safety Report, the (ii) Culverts (iv) Social nuisance principles set out in the Summary EMP and the following: (iii) Dispose of (v) Erosion of material piles and (i) Prior to commencing any works, the Contractor will meet with the NSRP SNCO, MNP and Marz surplus material runoff may affect nearby land and authorities. (ii) Areas of disturbed land will be restored or rehabilitated as soon as possible. (iii) Works plants stockpiles will be located away from drainage areas and water-courses. (vi) Works can cause local flooding (iv) Construction and related activities, such as stockpiling, servicing and drainage works will be (vii) Material beyond ROW affects restricted to identified sites. (v) Spoil and materials piles will be graded, stabilized and drained. (vi) nearby land quality and use (viii) Construction material/waste will be kept within the ROW and away from water bodies. (vii) Adequate Noise and vibration (ix) Works may temporary drainage will be provided to prevent local flooding. (viii) Runoff from sites will be prevented unearth archaeological artifacts from entering natural water-courses, for example by using sediment traps, silt aprons and/or straw bales. Also see: Drainage, Slope Stability Erosion and Sediment Control – below. (ix) Water sprinklers will be used to minimize dust in and around work areas. (x) Work along the north road section will be undertaken only during daylight hours. (xi) Workers will use safety equipment (helmets, eye-glasses, ear-plugs - as required) and follow safety procedures (xii) Nearby residents, commercial and industrial land users and communities will be informed of major activities ahead of their implementation and be informed of a clear mechanism for comments and complaints to be communicated to the Engineer. Waste Management The Contractor will prepare a Waste Management Plan for approval by the Engineer prior to commencing work. The Plan will be guided by the following: (i) Solid waste will be separated (it is understood that clean paper, glass and poly-propylene plastics are recyclable in Armenia) and stored for regular collection for correct off-site disposal in a nearby municipal waste facility. (ii) Solid waste disposal sites will be identified in concert with local officials and the MNP prior to any dumping. (iii) Solid waste, waste spoil, waste aggregate/materials and waste material removed from the existing road (e.g., used asphalt-concrete that cannot be crushed and re-used) will be disposed of only in designated sites/locations. (iv) waste oil will be collected and stored in used fuel drums for later safe disposal in a manner and/or at sites approved by the MNP and local authorities. (v) Waste asphalt removed from the existing road (north) will be recycled and re-used in the new road construction as much as possible. All old asphalt that cannot be re-used will be handled as toxic waste and disposed of only at a site approved by MNP and local authorities.
Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors 1. Construction: Drainage, Slope Stability Erosion and Sediment Control (i) Control devices/actions will be designed to provide adequate protection for each area, according to slope, drainage (i) Earthworks pattern, likely rainfall, and the construction site. (ii) Culverts (ii) Measures to control runoff, erosion and sedimentation will include: (iii) Dispose of a. Diversion of natural runoff around construction areas surplus b. Use of temporary bunds to divert runoff to temporary or permanent drainage facilities material (iii)Drains, runoff, erosion and sedimentation protective measures will be maintained regularly to ensure adequate capacity. (iv) Temporary diversion drains will be extended beyond the toe line of an embankment to avoid embankment erosion (v) Drainage structures and erosion controls will be monitored and repaired/modified as soon as possible after rain. Noise and Vibration (i) Vehicles and equipment will be fitted with emission controls and silencers to meet national noise control and emission standards and be checked every six-months to ensure compliance. (ii) The asphalt plant and equipment will be operated only in daylight. (iii)Noise control barriers (e.g., solid walls, earth barriers, noise-reflective panels) will be used when necessary to shield houses, schools and hospitals Archaeological Finds When an archaeological site is found, work will be stopped immediately. The Engineer will be notified. Then, the following steps will be taken: Isolate the site. (i) Call the Archaeology and Ethnography Inst., Armenian National Academy of Sciences and the Agency for Protection of Historical and Cultural Monuments to assess the site and determine whether and how it should be preserved (ii) Document and photograph the find and area immediately around it (iii) When advised and as directed by the Archaeologist, excavate and remove the find (iv) After documentation and after being advised that the site is not important, resume construction.
(i) Diesel will be stored in drums or tanks under cover on an impervious pad of concrete or clay (for 2. Store and (i) Diesel and waste oil is toxic to later removal and safe disposal), and the pad will be surrounded by an impervious bund enclosing a catch volume at all living organisms - in the soil handle diesel and least 50% more than the volume of diesel stored. Should clay be used to form the bund and a spill occur, the bund or in surface or ground-water. waste oil will be removed (including vehicle Diesel and waste oil kills all after construction has ceased and disposed of safely (as for impervious pads of clay). (ii) Vehicles and equipment will be maintained in designated areas underlain by an impervious pad and equipment living organisms of concrete or clay servicing) (for later removal and safe disposal) (iii)Waste oil will be collected and stored (in the same way that diesel is stored – see above) in used fuel drums for later safe disposal in approved sites. (iv) Also see Waste Management – above.
Activities Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors The Contractor will prepare a Quarry and Borrow-pit Operations and Site Restoration Plan for 3. Operate and (i) The expected impacts are very approval by the The Plan will be guided by the similar to those shown for Engineer - prior to commencement of materials extraction. restore quarries following: and borrow pits Construction, above. (i) Potential quarries and borrow pits will be identified in concert with marzpeteran (provincial) and Yerevan officials. (ii) Quarries and borrow pits will be made safe, have their slopes stabilized, be adequately drained and be restored or rehabilitated as soon as possible after extraction has ceased. The Contractor will prepare a Draft Traffic Management Plan for consideration by the 4. Transport (i) Dust and emissions Engineer and affected materials and communities, traffic authorities and the police before finalization and approval by the (ii) Noise and vibration Engineer -- prior to equipment (iii) Traffic and other safety hazards commencing construction,. The Traffic Management Plan will include: 1. Carefully selected truck (iv) Social impact in affected routes 2. Clear route directions 3. Appropriate warning signs 4. Established speed limits and communities (v) Damage to rural operating times (daylight as much as possible) 5. Provision and maintenance of temporary access roads and other roads for public and nearby communities 6. Controls over the movement of vehicles particularly near communities and schools 7. Use of dust blankets or other means to cover load 8. Provisions to use and using water spray of road surfaces to control dust in and near affected settlements 9. Construction traffic giving way to regular traffic (i) Construction traffic routes will be defined in cooperation with local communities and the police (ii) Vehicles and equipment will be maintained to prevent fuel and oil leaks and to minimize air and noise pollution (iii)Trucks and equipment will be washed in specified areas with suitable runoff protection (as above). (iv) Roads used by construction vehicles will be swept regularly. (v) Vehicle and equipment movements will be restricted to the approved construction zone and the final ROW. (vi) Rural and other roads damaged by construction vehicles and other activities will be repaired or restored The Contractor will prepare an Asphalt Plant Site Development and Operating Plan for (i) Dust and emissions approval by the Engineer - (ii) Noise prior to construction of an asphalt plant. The Plan will take the following into account: (i) The asphalt plant will be located at least 200m away from and downwind from any settlement and (iii) Diesel (used in asphalt) is toxic 200m away from any water body or stream and adjacent to other contractor facilities such as, works to all living organisms – in soil, camps, storage areas and vehicle and equipment maintenance areas. (ii) Electrostatic precipitators surface or ground-water. will be installed or exhaust gases will be released via a set of water baths (iii)Diesel will be stored under cover on a concrete pad surrounded by an impervious bund enclosing a catch volume at least 50% more than the volume of the diesel stored (see above). (iv) Conveyers and hoppers will be covered (v) Waste asphalt and bitumen will be disposed of at a site approved by marz, city and MNP authorities. (vi) The plant will be operated only in daylight hours when located less than 500m from a settlement.
(i) Work force generates significant The Contractor will prepare a Facilities Plan (such as, work camps, concrete mixing plants, 5. Operate/ storage areas and amounts of domestic and other vehicle and equipment maintenance areas), for approval by the Engineer - prior to manage work establishing facilities. The camps and other solid waste and sewage with Facilities Plan will take the following into account: facilities (incl. potential to damage water quality (i) Camp locations will be more than 200m from any water body and sited to prevent damage to store/dispose of and create nuisance (ii) Improper landscape. (ii) Domestic solid waste and hazardous waste disposal. (iii)The need for adequate sewage and solid waste disposal creates health temporary drainage (iv) Sewage will be disposed of in on-site septic tanks, held in sealed tanks for waste) problems and habitat for disease proper disposal or disposed into latrines constructed for the purpose and capped when no longer vectors (iii) Communities may needed. perceive potential or suffer from actual social (v) Wastewater will be disposed of in on-site septic tanks, or be treated to meet the standards for impacts from large male workforce. domestic wastewater discharge and discharged to a pond or natural drainage channel. (vi) Covered (iv) Site runoff affects the physical rubbish bins for solid waste will be placed at suitable locations where solid waste is generated. (vii) water quality and aquatic life in Solid waste will be separated (clean paper, glass and poly-propylene plastics are understood to be rivers and water bodies, flora, recyclable in Armenia) and stored for regular collection for recycling or off-site disposal in a municipal nearby land, and other natural waste facility (also see Waste Management – above) (viii) Work camp sites will be restored to the resources. satisfaction of local officials after use and before abandonment. 6. Work Site (i) Injuries and death of workers, (i) Safety and safety promotion will be of the highest priority. Safety road users, people in and near work-sites, quarries and borrow- (ii) Temporary traffic direction signs, markings, traffic signals and lighting will be installed and pits, and possible sickness of maintained, clearly visible solid barriers will be used to channel traffic, and flagmen will be employed workers and other people because as needed. (iii)Water sprinklers will be used when needed to control dust (iv) Work areas will be kept of sewage and waste disposal. clean and clear of waste and unused material (v) Waste will be disposed of properly (also see Waste Management) (i)Lack of information and The Contractor will prepare a Community Consultation and Communications Plan for approval 7. Public by the Engineer - Consultation understanding by communities and prior to commencing site preparation and construction activities. The Plan will be guided by the affected parties about the planned following: (i) Procedures for communicating with local residents will be developed in advance of works activities and the schedule activities, particularly when noise, vibration or nuisances may be created and/or where local flooding for their implementation may be an existing or potential problem. can lead to frustration and delays in (ii) Community members will be provided with direct access to the SE or representative at a nominated the schedule and sometimes can location and time (particularly important where some residents may not have telephones). (iii) A contribute to accidents. process will be developed whereby community members and other stakeholders may make complaints and be assured of receiving responses within a reasonable period. A record or Log will be maintained of the type and number of complaints received (name, subject, date, response and date of response). (iv) Regular meetings will be held with community representatives to discuss the project, its impacts, etc. The group should include community leaders and people who are well known in the community and who represent different interests, e.g., business people, teachers, priests, older people and those with special interests. (v) Community leaders and local newspapers will be provided with notices on project progress and anticipated issues. (vi) Clear signs will be posted on and around construction sites to provide information about the project. (vii)Employment opportunities will be maximized for local people by employing them as part of the project labour force, and prefabricating or manufacturing construction items locally when possible, e.g., drainage pipes, culverts and for sand, gravel and stone supply.
Potential Impacts Mitigation Measures -- for Implementation by Engineers and Contactors (ii) Chemicals and Hazardous materials The Contractor will prepare a Plan for Handling Chemicals and an Emergency Contingency have the potential to poison people, soil, Response Plan for approval by the Engineer - prior to commencing construction. The Plan will be guided surface and ground water and may by the following: cause death or severe damage to the (i) Procedures will be developed and implemented to ensure safe handling and storage of health of people and all living animals and hazardous substances, e.g., diesel, waste oil, paints. Material safety data sheets, plants. emergency response procedures and clean-up materials will be readily available on site. Copies of material data sheets will also be held by the Resident and Engineers. (ii) An Emergency Contingency Response Plan (ECRP) will be in place to handle spills and ensure that clean-up materials are readily available on-site to clean-up spills that may occur. The ECRP will, at a minimum: 1. Identify the positions and persons responsible for emergency response action (e.g., the Engineer, RE, Works Foremen) 2. Specify the leader of the Emergency Response Team (ERT) and Alternate 3. Include an organizational diagram specifying the positions and responsible persons within the ERT, their work and home phone numbers, and the reporting lines among them. 4. Ensure that clean-up chemicals and materials to absorb and remove spilt substances are available and stored undercover in locked facilities located at works facility sites. 5. Ensure that the responsible persons receive training in emergency response. (iii) Hazard and risk management training will be provided to each Environmental Management Officer (appointed by the Contractor) and all personnel handling chemicals and hazardous substances. (iv) Spilled material will be collected and disposed of in a site approved by MNP and local authorities. The spilled area will be cleaned in a timely manner to prevent potential contamination of surface and ground water and soil. (v) Only minimal chemicals, hazardous substances and fuel will be stored on-site, within an enclosed and covered secure area that has an impervious floor and impervious bund around it (with capacity at least 150% of the capacity of the largest tank). The storage area will be located away from water-courses and danger areas, e.g., facilities site.
76. The requirements for operating plans to be prepared by the Contractor are set out in the EMP Summary (Figure 10, above) and listed in Figure 11 as clauses to be included in the Main Contract Document. Operating Plans will be approved by the Engineer prior to undertaking any associated action, and be included as Annexes to the EMP.
Figure 11: EMP and Operating Plans - Clauses for Inclusion in Contract Documents
EMP and EMP and Operating Plans (Clauses to be included in Responsibility Annexes the Contract Document - highlighted) to it EMP The Contractor will, prior to commencing site preparation Contractor + and construction activities, prepare: An Environmental Engineer Management Plan (EMP) for approval by the Engineer. The EMP will be guided by Chapters 4 and 5 of this IEE Report, particularly the Summary EMP (Figure 17) and include, as Annexes, the Operating Plans listed below (all to be approved by the Engineer).
ANNEX A A Waste Management Plan to guide the handling of materials for Contractor + recycling (glass, plastic and clean paper), domestic waste, sewage, and Engineer hazardous waste. Contractor + . ANNEX B A Quarry and Borrow-pit Operations and Site Restoration Plan Engineer Contractor +
ANNEX C A Traffic Management Plan Engineer Contractor +
ANNEX.D An Asphalt Plant Site Development and Operating Plan Engineer ANNEX.E A Facilities Plan (covering: work camps, concrete mixing plants, Contractor + storage areas and vehicle and equipment maintenance areas) Engineer ANNEX.F A Plan for Handling Chemicals and Hazardous Materials and an Contractor + Emergency Contingency Response Plan Engineer Contractor +
ANNEX.G A Community Consultation and Communications Plan Engineer
77. The Final EMP and the Operating Plans attached as Annexes “A” through “G” to the EMP will, after approval by the Engineer, become the Environmental Management Package and form part of the Contract Package with all of the requirements for commitment and performance as applied to engineering and financial performance.
78. The full contents of the EMP will be as follows: (i) Statement of Commitment and Signature Block; (ii) Summary of Potential Impacts; (iii) Planned Mitigation Measures; (iv) Planned Environmental Monitoring and Schedule for Monitoring; (v) Planned Public Consultation Process; (vi) Responsibilities for Implementing Mitigation Measures and Monitoring; (vii) Responsibilities for Reporting and Review; (viii) Environmental staff and activities/inputs of various government agencies; (ix) Environmentally Responsible Procurement Plan; (x) Operating Plans – Summary; and (xi) Annexes: Operating Plans: A through G.
C. Responsibilities for Impact Prevention and Mitigation
79. The Contractor will:
(i) Prepare the Draft EMP (ii) Present the Draft EMP to the PMC ES and EM for their review and comment before submitting it to the Engineer for approval and before discussing it with central and provincial government authorities, village leaders and villagers in affected communities. (iii) After the above discussions, revise the EMP as appropriate (iv) Prepare the Operating Plans specified in the Summary EMP and include these as Annexes to the EMP (v) During works ensure that environmental management issues are checked regularly in order to ensure compliance with the Contract Specifications and the EMP (vi) Report as specified to the Engineer.
80. The NSRP SNCO will, before accepting any Contractor bid to undertake the construction of any part of the Project road, check to ensure that the Contract Price explicitly identifies cost commitment to undertake the environmental protection measures specified in the EMP and the Environmental Enhancement Measures specified above
81. Before completion of construction and releasing sections of road from Contractor to Government control, the NSRP SNCO will:
(i) Ensure that the design and construction standards meet the required standards including road markings, signage and safety devices and the posted travel speeds accord with international standards (ii) Formulate and apply an Emergency Contingency Plan (ECP) to cope with accident events including potential spills of hazardous and other substances within the ROW and on adjacent land or streams nearby (iii) To Report to the MOTC and ADB as required
82. The NSRP SNCO Environmental Manager (EM) will:
(i) Participate with the PMC ES to review the Draft EMP and recommend improvements as appropriate (ii) Ensure that NSRP SNCO becomes informed of any important environmental issues (iii) Check on environmental performance weekly and submit Monthly Environmental Reports to the Engineer for incorporation into Works Monthly Reports
83. The Project Management Consultant (PMC) environmental specialist (PMC ES) will:
(i) Review the Draft EMP prepared by the Contractor and, with the EM, suggest revisions before the Contractor submits it to the Engineer and discussions with villagers (ii) Assist the Contractor to prepare the Final EMP (part of the Contract Package) (iii) Review the Monthly Environmental Reports and prepare a consolidated Environmental Management Report every 3-months (iv) Visit works and associated sites as required and advise the EM and Engineer on environmental management issues as these may arise (v) Prepare and deliver an Environmental Awareness Raising and Training Program.
D. Environmental Enhancement Measures
84. The only environmental enhancement measures will be:
(i) General landscaping after completion of the road improvements on the 4-lane, M1, north road section
E. Environmental Monitoring Program
85. From the ADB, Environmental Assessment Guidelines, (2003) and experience with other roads projects, key features of a useful monitoring program include: realistic sampling program (temporal and spatial), sampling methods relevant to source, ability to collect quality data, comparability of data over time, cost-effectiveness, ease of interpretation reporting simplicity (for internal management and external checking), allowance for, and response to, third parties, and suitability for public presentation and understanding
86. The NSRP SNCO wishes to monitor performance of its contractors during construction of the proposed road works in order to ensure an adequate level of compliance with environmental impact mitigation measures and employs its own staff to undertake the necessary tasks. An outside, Project Management Consultant (PMC) environmental specialist (PMC ES) will be appointed to work alongside the NSRP SNCO Environmental Manager (EM) and appointed community members from affected communities. 87. Monitoring requirements and responsibilities are summarized in Figure 12.
F. Cost of Impact Prevention, Mitigation, Monitoring and Enhancement
88. The cost of environmental impact prevention, mitigation and monitoring for the two, 4- lane road sections: the M-1 north section – Yerevan to Ashtarak and the M-2 south section – Yerevan to Ararat, will be minimal. The costs relate only to the actions required of the engineers and contractors in the normal execution of the Project and the incremental cost of environmental monitoring by the EM and the PMC ES
89. The impact prevention and mitigation measures recommended here are normal, standard, internationally recognized impact prevention and mitigation measures and form part of the Works Contract Price – the engineering and construction cost package
90. Environmental monitoring to ensure compliance will be conducted by the EM within the NSRP SNCO, the State Environmental Inspectorate (SEI) and be checked on periodically by an International Environmental Specialist (PMC ES). Thus the cost will included the normal salary of the EM and PMC ES. PMC environmental specialist salary will be included in the PMC budget.
Figure 12: Monitoring Requirements - Site Preparation and Construction
Locations for Monitoring Frequency of Responsibility for Parameters to be Monitored Refer to EMP and Data Sources Monitoring Monitoring
Work Sites: Dust and use of water spray Slope protection and drainage Runoff control Work sites: Visual inspection Weekly Quarterly EM, PMC ES Drainage maintenance Substances/materials ----- in water courses
Work site safety: Signage Barriers Site Work sites: Visual inspection Weekly Quarterly EM, PMC ES cleanliness Use of safety equipment ----
Traffic and Road safety: Signage, Barriers, Work sites: Visual inspection Routes Material on the road Condition of -Traffic routes --Vehicle Weekly Quarterly ---- EM, PMC ES rural roads Vehicle & equipment emissions Maintenance logs Quarterly Monthly control Incidents and complaints Complaints Log
Work camps: Solid waste management Works camps: Visual Weekly Quarterly -- Sewage management Social issues Site inspection --Complaints Log EM, PMC ES Monthly Monthly restoration -
Facilities areas: Storage of diesel and waste Facilities areas: Visual Weekly Quarterly - EM, PMC ES oil Material/substance sheets Site restoration inspection --- Monthly Monthly
Quarries and borrow pits: Slope Quarries and borrow pits: Weekly Quarterly --- management Runoff management Use of EM, PMC ES Visual inspection ---- Monthly safety equipment Site restoration
Asphalt plants: Diesel storage and use Asphalt plants: Visual Weekly Quarterly -- EM, PMC ES management Dust emission control inspection --
Waste management and disposal: Solid waste storage and transport Solid waste Work sites, Works camps, disposal sites Asphalt recycling, re-use and disposal sites: Visual Weekly Quarterly ---- EM, PMC ES disposal Sewage management and disposal inspection ----- Waste oil disposal
Engineer Log Checking with Coordination with MNP and Local authorities Monthly EM MNP Complaints Complaints Log Monthly EM Consultation and Information sharing with Engineer Log Minutes of Quarterly EM communities meetings
5.7 Environmental Management Seminars
91. It is important to ensure that NSRP SNCO officers, Area Engineers, Resident Engineers, Contractors, Contract Supervisors and Foremen, understand the basics of sound environmental management and the measures required to prevent and/or reduce environmental impacts. To facilitate such understanding, a set of five seminars will be designed for delivery to concerned parties
92. The purpose of the seminars is to ensure that all managers and supervisors involved in the final design and construction of the road have basic and similar understanding of environmental issues and their management, and how to prevent or reduce the impacts likely to be created by the project particularly during the construction phase
93. The seminars will be based on the contents of this report, particularly the EMP and Monitoring Program and follow closely the requirements set out in the ADB, Environmental Assessment Guidelines, 2003
94. Delivery of five Environmental Management seminars, their locations and participants will be decided by the PMC ES and EM, however, the timing of seminar delivery will be as set out below. Five Environmental Management seminars will be delivered as follows, during the:
(i) 1 -- Detailed Project Design Phase (ii) 2 -- Preparation for construction (iii) 3 -- First month of Project activities (iv) 4 – Months 3-4 of construction activities (v) 5 – Month 6-7 of construction activities.
VI. PUBLIC CONSULTATION and INFORMATION DISCLOSURE
A. Consultation Process
95. The IEE Report will be made available publically in Armenia by the RA MOTC and MNP and provided to affected communities.
96. The Summary IEE report (SIEE) will be placed on the ADB Website in August 2009. It forms Appendix 1 to this IEE Report.
97. Meetings were held with representatives of a number of stakeholder groups and will be ongoing with the same and different stakeholder groups during the preparation of other (future) projects planned to be funded under the MFF
98. Comments obtained to date relate to the MFF Program as a whole rather than to this st specific 1 Tranche Project. Most concern was expressed with regard to possible future tranches in the south of Armenia rich in biodiversity. Little concern was expressed with regard to any intended road works in the central part of the country, particularly along existing road alignments. The most frequently expressed concern was that the EMP should be followed and enforced
99. Meetings, guided by a discussion guide were held during June and July 2009.with representatives of the stakeholder groups listed in Figure 13.
B. Community Involvement to date:
100. Village leaders completed the Environmental Questionnaire that was included with the social and demographic questionnaire when provided to communities by the Resettlement Survey Team in July 2009. Results from this survey were not available at the time of preparing this IEE report (prepared late July 2009 so that the Summary IEE could be placed on the ADB Website in August).
101. Face-to-face interviews were held by the Environmental Impact Assessment Team with 94 villagers from 3 different communities: Agarak, Udjan and Kosh (located in Aragatsotn Marz but not along the M-1, 4-lane north road section of this IEE report). As stated above, discussions to date have related to the MFF Program as a whole, nevertheless, the three selected villages are located within 15km of the 4-lane section of the M-1 chosen for improvement and there are no villages located along the Project road sections.
102. The Environmental Questionnaire used in the survey is attached as ANNEX 1 to this Chapter. Interviews were conducted in the Armenian language. The essential features of the proposed road improvement program were described to respondents, the expected benefits and negative impacts outlined and questions asked via closed questions related to the existing road and respondent perceptions of likely environmental impacts.
Figure 13: Environmental Stakeholder Groups Met to Date
Stakeholders Stakeholder Groups
Government Ministry of Transport and Communication Ministry of Nature Protection ‐ Bioresources Management Agency ‐Nature Protection Expertise (NPE) ‐State Environmental Inspectorate (SEI) Ministry of Culture ‐Agency for Protection of Historical and Cultural Monuments
Regional Aragatsotn Shirak administrations (marzpetaran) International ADB WWF World Bank USAID UNDP and GEF US Millennium organizations Challenge Account – Armenia