September 2020 2 Background Information Development Stage Time Stage 1 Community Engagement (CE1) February 2016 – March 2016

Stage 2 Community Engagement (CE2) November 2016 – January 2017

Stage 3 Community Engagement (CE3) February 2019 – April 2019

Commencement of Design December 2019

South Development Office Civil Engineering and Development Department 3

Objective of the Briefing

 To brief members on the gazette scheme of the proposed Boardwalk underneath Island Eastern Corridor (IEC) (Boardwalk), including the gazette procedure and the enhancement of the Boardwalk scheme

 In response to the public views to commence the construction works as early as possible, preparation works are ongoing and will be completed by phases

 The proposed scheme is ready for gazettal and we will continue to work on the architectural and landscape design of the Boardwalk and consult HC in due course

South Development Office Civil Engineering and Development Department 4 Major Views and Comments from Key Stakeholders in CE3

 General agreement on the alignment and width as well as supporting facilities and clear support for early implementation

 Reducing the gradient and level of boardwalk for a more comfortable and closer to water walking environment

 More Viewing Platforms for public enjoyment

 Integrating with the planned and existing promenade to achieve a continuous waterfront promenade

South Development Office Civil Engineering and Development Department Gazette Scheme – Layout Plan

South Development Office Civil Engineering and Development Department Gazette Scheme – Eastern Section 6

/ Viewing Decks Movable Bridge Access Linkbridge

Outside IEC footprint Underneath IEC structure

Additional Viewing Decks under Current Scheme 4

Additional Movable 5 Bridges under Current Scheme

Tin Chiu Street 6 Man Hong Street Extension to Promenade Healthy Street East

Hoi Yu Street Quarry 5 Bay 4 6 Promenade

South Development Office Civil Engineering and Development Department Gazette Scheme – Western Section 77

/ Viewing Decks Movable Bridge Fishing Platform Access Linkbridge

Outside IEC footprint Additional Viewing Decks 3 under Current Scheme Underneath IEC structure 2

1

Provident Garden

Oil Street East Coast 1 2 3 Park

South Development Office Civil Engineering and Development Department Gazette Scheme – Eastern Section 8

NPVFP

NPFSD Pier

Hoi Yu Street Extension

Movable Bridge

South Development Office Civil Engineering and Development Department Gazette Scheme – Western Section 9

Movable Bridge

South Development Office Civil Engineering and Development Department Enhanced Boardwalk Scheme 10

V6. • Added new Viewing Platform V2. to improve the • Modify the shape of experience on V1. V5. Viewing Platform to the boardwalk V3. • Modify the • Added new improve the • the shape V4. Viewing Platform of Viewing shape of pedestrian • Modify the to improve the Platform Viewing circulation shape of experience on the remained Platform to Viewing boardwalk unchanged improve the Platform to pedestrian improve the circulation pedestrian circulation

L1. F1. • Lower the • Modify the shape of gradient of Fishing Platform the Link and the Corridor to Bridge improve pedestrain L2. L3. D1. circulation • the shape of Link • Lower the • Extend boardwalk Bridge remained gradient of the to Quarry Bay unchanged Link Bridge Promenade

South Development Office Civil Engineering and Development Department Vertical Profile of Gazette Scheme

South Development Office Civil Engineering and Development Department Typical Section 12

min. 10m

1100m(h) railing

Waterfront Inland

South Development Office Civil Engineering and Development Department Access from MTR Station/Tram Stop 13 Access Points Route Time Taken Time Taken (From MTR) (From Tram Stop) Oil Street Approx. 9 mins Approx. 10 mins Provident Garden Approx. 7 mins Approx. 5 mins Tong Shui Road Approx. 4 mins Approx. 4 mins

Pedestrian Access

MTR

Tram

South Development Office Civil Engineering and Development Department Access from MTR Station/Tram Stop 14

Access Points Route Time Taken Time Taken (From MTR) (From Tram Stop) Promenade Approx. 6 mins Approx. 6 mins North Point Vehicular Ferry Pier Approx. 7mins Approx. 6mins Man Hong Street Approx. 9 mins Approx. 3 mins Healthy Street East Approx.6mins Approx. 3mins Hoi Yu Street Approx. 7 mins Approx. 4 mins Pedestrian Access

MTR

Tram

South Development Office Civil Engineering and Development Department Design Elements of Boardwalk 15

Playful elements Viewing decks Water playground Place for sunbathing Display artist's Open space artwork Fishing platform

Food and beverage facilities Bicycle facilities

South Development Office Civil Engineering and Development Department Other Facilities 16

- Toilets

- Drinking Fountains

- Refreshment Kiosks

- Shelters

- Seatings

South Development Office Civil Engineering and Development Department 17 Photomontage

Access Point of Boardwalk at Oil Street South Development Office Civil Engineering and Development Department 18 Photomontage

Near North Point FSD Pier

South Development Office Civil Engineering and Development Department 19 Photomontage

Movable bridge along Proposed Boardwalk South Development Office Civil Engineering and Development Department Return 20 Photomontage

Movable bridge at the linkbridge of Proposed Boardwalk South Development Office Civil Engineering and Development Department Return 21 Boardwalk underneath IEC Tentative Implementation Programme / Key Dates Event Date

Gazette Procedures Q4 2020

Consult Harbourfront Commission and other stakeholders on Architectural and Landscape First half of 2021 Design Seek funding approval from the Legislative Q2 2021 Council

Commencement of Construction Work late 2021

Phased Completion from Completion and Commissioning of the project end 2024

South Development Office Civil Engineering and Development Department North Point Vehicular Ferry Pier (NPVFP)

Key Plan

Upper Deck Of NPVFP Proposed lift & staircase

Return South Development Office Civil Engineering and Development Department Non-Shared use of North Point FSD Pier ‐ Closure at irregular hours Re‐provisioning of Relocation of Petrol cause inconvenience to Inner Berth 23 the Boardwalk users Refueling facility

Additional Movable Bridge Existing Existing Petrol Inner Berth Refueling facility Return South Development Office Civil Engineering and Development Department Hoi Yu Street Extension

Hoi Yu Street Extension

Existing 2m wide footpath

Return South Development Office Civil Engineering and Development Department South Development Office Civil Engineering and Development Department

Thank you