Date of issue: Wednesday, 6 March 2019

MEETING BERKSHIRE LOCAL TRANSPORT BODY

Member Authority Councillor Bicknell The Royal Borough of Windsor & Councillor Brunel-Walker Bracknell Forest Council Councillor Carter Slough Borough Council Councillor Clifford West Berkshire Council Councillor Jorgensen Wokingham Borough Council Councillor Page (Chair) Reading Borough Council Stuart Atkinson Thames Valley Berkshire LEP Charles Eales (Vice-Chair) Thames Valley Berkshire LEP Malcolm Kempton Thames Valley Berkshire LEP Bob Mountain Thames Valley Berkshire LEP Simon Ratcliffe Thames Valley Berkshire LEP Matthew Taylor Thames Valley Berkshire LEP

DATE AND TIME: THURSDAY, 14TH MARCH, 2019 AT 4.00 PM

VENUE: THE CURVE - WILLIAM STREET, SLOUGH, BERKSHIRE, SL1 1XY

DEMOCRATIC SERVICES NICHOLAS PONTONE OFFICER: (for all enquiries) 01753 875120

NOTICE OF MEETING

You are requested to attend the above Meeting at the time and date indicated to deal with the business set out in the following agenda.

JOSIE WRAGG Chief Executive

AGENDA

PART 1 AGENDA REPORT TITLE PAGE WARD ITEM Apologies for absence.

1. Declarations of Interest -

It is a principle of the BLTB that the interests of the Thames Valley Berkshire area will take precedence over a member’s own interests or those of their nominating authority.

All members must declare, and take relevant action, if they believe they have a pecuniary or other interest on a matter to be considered at the meeting in accordance with the Code of Conduct of the nominating authority or LEP.

The Chair will invite any member representing a local authority seeking financial approval for a scheme to declare that interest.

2. Minutes of the Meeting held on 15th November 2018 and the 1 - 16 Extraordinary Meeting held on 31st January 2019

3. Briefing Note - TVB LEP/BLTB 'How We Work' - To Note 17 - 18

4. Thames Valley Berkshire Local Growth Deal 2015/16 to 19 - 64 2020/21

5. Financial Approval for 2.29 Wokingham: Winnersh Triangle 65 - 98 Park & Ride

6. 2.19 Bracknell: Town Centre Regeneration - One Year 99 - 142 Impact Report

7. Business Rates Retention Pilot - Revenue Support 143 - 148

8. Revised Local Growth Fund Programme 2015/16 to 2020/21 149 - 154 - Update

9. TfSE - Proposal to Seek Statutory Status - Informal 155 - 182 Engagement

10. Transport for the South East - call for Major Roads Network 183 - 186 schemes

11. BLTB Forward Plan 187 - 188

12. Date of Next Meeting - 18th July 2019 - AGENDA REPORT TITLE PAGE WARD ITEM Press and Public

You are welcome to attend this meeting which is open to the press and public, as an observer. You will however be asked to leave before the Committee considers any items in the Part II agenda. Please contact the Democratic Services Officer shown above for further details.

The Council allows the filming, recording and photographing at its meetings that are open to the public. By entering the meeting room and using the public seating area, you are consenting to being filmed and to the possible use of those images and sound recordings. Anyone proposing to film, record or take photographs of a meeting is requested to advise the Democratic Services Officer before the start of the meeting. Filming or recording must be overt and persons filming should not move around the meeting room whilst filming nor should they obstruct proceedings or the public from viewing the meeting. The use of flash photography, additional lighting or any non hand held devices, including tripods, will not be allowed unless this has been discussed with the Democratic Services Officer. This page is intentionally left blank AGENDA ITEM 2

Berkshire Local Transport Body – Meeting held on Thursday, 15th November, 2018.

Present:- Charles Eales (in the chair) Thames Valley Berkshire LEP Stuart Atkinson Thames Valley Berkshire LEP Councillor Bicknell RBWM Councillor Brunel-Walker Bracknell Forest Council Councillor Carter Slough Borough Council Councillor Clifford (from 4.10pm) West Berkshire Council Simon Ratcliffe Thames Valley Berkshire LEP Councillor Sleight Wokingham Borough Council Matthew Taylor Thames Valley Berkshire LEP

Also present under Rule 30:- Councillor Chopping (Wokingham Borough Council)

Observer:- Rob Stubbs, RBWM (accountable body for TVB LEP)

Apologies for Absence:- Councillor Page, Dr Peter Howe and Malcolm Kempton

PART 1

19. BLTB Membership

It was noted that two new Thames Valley Berkshire LEP representatives, Simon Ratcliffe and Malcolm Kempton, had been appointed to BTLB. A further appointment was due to be ratified by TVB LEP in the near future.

Resolved – That the new members be welcomed to BTLB.

20. Declarations of Interest

Charles Eales declared that he worked for Microsoft based at Thames Valley Park, which would be served by the East Reading MRT scheme.

Matthew Taylor declared that he worked for Stewarts Coaches, which could operate services on Mass Rapid Transit schemes supported by BLTB.

21. Minutes of the Meeting held on 19th July 2018

Resolved – That the minutes of the meeting of the Berkshire Local Transport Body (BLTB) held on 19th July 2018 be approved as a correct record.

Page 1 Berkshire Local Transport Body - 15.11.18

22. Briefing Note - TVB LEP/BLTB 'How We Work' - To Note

Members noted a briefing note that summarised the process by which Thames Valley Berkshire LEP and the Berkshire Local Transport Body operated in investing in local transport schemes.

Resolved – That the BLTB ‘How we work’ briefing note be noted.

23. Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21

A report was received on the progress of the Thames Valley Berkshire Local Growth Deal which set out the status of approved schemes, updated financial profile and identified risks.

Updates were provided by scheme promoters on each of the approved schemes:

2.01 Newbury: Kings Road Link Road – the delays had been resolved and the scheme was on site.

2.02 Bracknell: Warfield Link Road – the scheme had been completed.

2.03 Newbury: London Road Industrial Estate – works had been completed on the transport scheme, although it was noted that legal issues had impacted on the redevelopment of the industrial estate.

2.04: Wokingham: Distributor Roads – update noted. Work on the DfT business case was progressing for the northern section. A planning application was expected in early 2019 to complete the southern section.

2.05 Newbury: Sandleford Park – update noted. The land ownership issues had been resolved and the scheme was on site. The risk rating was now ‘green’.

2.06 Reading: Green Park Railway Station – update noted. Interchange works were on site although design work on the station was not complete.

2.07 Bracknell: Coral Reef Roundabout – project completed.

2.08 Slough: MRT Phase 1 – the scheme was completed. A closed service had been running since July and a public service, delivered by Stewart’s Coaches, was due to commence from 2nd January 2019.

2.09.1 Sustainable Transport NCN 422 – update noted.

2.09.2 Sustainable Transport A4 Cycle Route with Bucks – update noted. Work was almost complete.

2.10 Slough: A332 Improvements – update noted. A January completion was expected.

Page 2 Berkshire Local Transport Body - 15.11.18

(Councillor Clifford joined the meeting)

2.11 and 2.12 Reading: South Reading MRT phases 1 and 2 – update noted. The final part of the scheme was under construction.

2.13 Wokingham: Thames Valley Park & Ride (previously called 2.13 Reading: Eastern Park & Ride) – update noted. Planning approval had been secured and preliminary works had started on site.

2.14 Reading: East Reading MRT Phase 1 and 2.25 Reading: East Reading MRT Phase 2 – a revised planning application had been submitted after the first application had been refused by Wokingham’s Planning Committee. The new application would be considered first by Wokingham and then by Reading, if approved. BLTB was concerned about whether the timescales for delivery of the scheme by 2021 could be achieved. The scheme promoters provided assurance that the scheme could be delivered within the required timescale if planning was approved. Members considered the approach if planning permission was refused again. In such an event, the scheme would almost certainly not be deliverable by 2021 and the £20m LGF would most likely be available to invest in other schemes. There was a pipeline of alternative schemes in the agreed programme, although they would need to be progressed quickly. This process would be triggered when the scheme promoter confirmed it wouldn’t be able to deliver the scheme on time. BLTB recognised that this was a significant risk to the programme and Members agreed it was important to move forward urgently if planning permission was refused to ensure that all the available funds could be spent on schemes in Berkshire. A decision was expected by Wokingham’s Planning Committee in December 2018.

2.15 Bracknell: Martins Heron Roundabout – update noted. The final phase of work was starting with completion due in February.

2.16 Maidenhead Station Access – update noted. Agreement had been reached with Network Rail and work was due to start in January.

2.17 Slough: A355 Route – the scheme was complete.

2.18 No scheme.

2.19 Bracknell: Town Centre Regeneration and Infrastructure Improvements – the scheme had been completed.

2.20 No scheme.

2.21 Slough: Langley Station Access Improvements – update noted. Work was progressing on site.

2.22 Slough: Burnham Station Access Improvements – the scheme was completed.

Page 3 Berkshire Local Transport Body - 15.11.18

2.23 Reading: South Reading MRT Phases 3 and 4 – update noted.

2.24 Newbury: Railway Station improvements – update noted. Work was due to start in the new year.

2.25 – see 2.14.

2.26 Wokingham: Winnersh Relief Road (Phase 2) – update noted. Planning permission had been approved and the business case was due for consideration shortly.

2.27 Maidenhead Town Centre: Missing Links – update noted. A report would be considered later in the agenda.

2.28 Bracknell: A3095 Corridor Improvements – update noted. Preliminary works had started.

2.29 Wokingham: Winnersh Parkway – update noted. A full business case was due to be considered in March 2019.

2.30 Thames Valley Berkshire Smart City Cluster – the programme had been amended but was on track.

2.31Slough: Stoke Road Area Regeneration – the full business case was due in March 2019.

2.32 Maidenhead: Housing Sites Enabling Works Phase 1 – the full business case had been due to be considered at this meeting, however, it had been slightly delayed. Councillor Bicknell proposed and Councillor Brunel-Walker seconded that an additional meeting of BLTB be arranged on 31st January 2019 to consider the full business cases for 2.32 Maidenhead Missing Links and 2.34 Slough MRT. Possible further items could be on the Slough: Stoke Road business case and, if necessary, on the reallocation of funds if East Reading MRT Planning Permission was not approved. This was agreed.

2.33 GWR: Maidenhead to Marlow-Branch Line Upgrade – this was a GWR scheme managed by Buckinghamshire County Council.

2.34 Slough MRT Phase 2 – as agreed at 2.32, the business case would be considered at an extraordinary BLTB meeting in January 2019.

Resolved –

(a) That the progress made on schemes previously given programme entry status be noted.

(b) That an extraordinary meeting of BLTB be held on 31st January 2019. The agenda would include the following:

Page 4 Berkshire Local Transport Body - 15.11.18

 Financial approval for 2.32 Maidenhead Housing Sites Enabling Works.  Financial approval for 2.34 Slough: MRT Phase 2.  Financial approval for 2.31 Slough: Stoke Road Area Regeneration, if required.  Reallocation of funds if East Reading MRT Phases 1 and 2 could not be delivered.

24. Financial Approval for 2.26 Wokingham Winnersh Relief Road Phase 2

A report was considered that recommended giving conditional financial approval to scheme 2.26 Wokingham Winnersh Relief Road Phase 2 from the Business Rates Retention Pilot.

The project would deliver a new relief road to the west of Winnersh, avoiding the current Winnersh Crossroads junction. The new Independent Assessors, Hatch Regeneris Consulting, concluded that the scheme would deliver good value for money, although, some further evidence was required which meant that conditional approval was recommended.

After due consideration, the scheme was given conditional approval.

Resolved –

(a) That scheme 2.26 Wokingham Winnersh Relief Road Phase 2 be given financial approval in the sum of £6,260,000 (£3,000,000 in 2018/19 and £3,260,000 in 2019/20) on the terms of the funding agreement set out at paragraph 13 step 5 of the report, subject to meeting the following conditions:

(b) The supply of further evidence which supported the conclusions reached in the Full Business Case in respect of:

 The provision of cycle lanes and footpaths and their social impacts;  Revisions to the net land value uplift calculation and adjusted present value of costs in the Economic Case;  Sensitivity tests, scheme build cost, risk contingency, financial profiles, inflation, maintenance, renewals and optimism bias in the Financial Case;  Procurement and management of project cost variations;  The risk register, risk management, contract management and contingency plans.

25. Financial Approval for 2.27 Maidenhead Town Centre: Missing Links

A report was considered that recommended giving final approval to scheme 2.27 Maidenhead Town Centre: Missing Links. The proposal aimed to complete the ‘missing links’ between planned major development areas in and around Maidenhead and improve their connectivity to the town centre.

Page 5 Berkshire Local Transport Body - 15.11.18

The report of the Independent Assessor at Appendix A to the report was noted. It concluded that it was a good scheme, however, conditional approval was recommended pending the supply of further evidence on a number of matters.

BLTB welcomed the scheme and agreed to give it conditional approval on the terms set out in the report.

Resolved –

(a) That scheme 2.27 Maidenhead Town Centre: Missing Links be given financial approval in the sum of £2,241,787 (£243,310 in 2018/19 and £817,718 in 2019/20 and £1,180,759 in 2020/21) on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions:

(b) The supply of further evidence which supports the conclusions reached in the Full Business Case in respect of:

 the impact of disruption caused during scheme construction;  the impact of interim arrangements for cycling and walking pending development of key sites;  the impact of late- or non-delivery of inter-dependent development;  the demand forecasts and monetised benefits in the Economic Case  procurement, cost estimates, spend profile and inflation;  the risk register;  the monitoring and evaluation and contingency plans.

26. 2.04.4 Wokingham: Arborfield Cross Relief Road - Preliminary Costs

An administrative report was considered that sought approval for the transfer of preliminary costs relating to the scheme, Arborfield Cross Relief Road, to Wokingham.

The scheme was supported in the 2013 Strategic Economic Plan and was a “DfT-retained scheme” with a contribution of £24m. Wokingham had made sufficient progress with the development of the Full Business Case for DfT to release £874,176 as a contribution to the preliminary costs.

A resolution of BLTB was required to enable the LEP’s accountable body, Royal Borough of Windsor and Maidenhead, the authority to transfer the money to Wokingham. This was agreed.

Resolved – That the transfer of £874,176 to Wokingham Borough Council in respect of preliminary costs associated with scheme 2.04.4 Wokingham: Arborfield Cross Relief Road be approved.

Page 6 Berkshire Local Transport Body - 15.11.18

27. Business Rates Retention Pilot - Revenue Support and New Bid

BLTB considered a report on the revenue support to local authorities for the development of a pipeline of schemes and on the new bid for a further year of BRRP funding for c. £10m to support priority investment schemes.

An allocation of the £600,000, “top-sliced” from the £25m BRRP, had been agreed by BLTB in July 2018 and the proposals were set out in Appendices 1 to 4 of the report for Reading, West Berkshire, Royal Borough of Windsor & Maidenhead and Wokingham. Slough and Bracknell Forest’s proposals were expected in March 2019. It was noted that the revenue “top-slice” had been extended by £90,000 to allow the LEP to draw down revenue funding for the Berkshire Local Industrial Strategy and consequential amendments were proposed to keep the overall BRRP spending at £25m.

The six Berkshire authorities, led by Bracknell Forest and supported by the LEP, had made a further bid to the Ministry of Housing, Communities & Local Government for a further c. £10m for 2019-20. It was not known whether the bid would be successful, but it was necessary for BLTB to confirm the priority projects in the event that it was. The priority schemes identified in the previously agreed prioritisation process were recommended to be allocated funding, which were Slough MRT Phase 2, Maidenhead Sites Enabling Works Phase 1, East Reading MRT, subject to planning permission and if not, South Wokingham Distributor Road Eastern Gateway and some further revenue support to future infrastructure business cases. In response to a question about the approach if a sum less than £10m was awarded, it was responded that the funding would be allocated in line with the agreed priority of schemes i.e. the lowest ranking scheme would not be allocated funding.

Members considered each of the recommendations in turn and they were all approved.

Resolved –

(a) That the revenue support proposals and the drawdown of BRRP funds by Reading, West Berkshire, Windsor and Maidenhead and Wokingham set out in appendixes 1-4 of the report be approved; and

(b) That the revenue support arrangements set out in appendix 5 and the drawdown of £90,000 from BRRP funds by TVB LEP be noted; and

(c) That the consequential switch of £90,000 support for South Reading MRT phases 3 and 4 from BRRP to LGF be approved, thereby reducing the unallocated LGF funds from £360,000 to £240,000; and

(d) That the following priorities for the allocation of BRRP funds in the event that the application for a second pilot in 2019-20 is successful be approved:

(i) Slough MRT Phase 2 £3.058m

Page 7 Berkshire Local Transport Body - 15.11.18

(ii) Maidenhead Housing Sites Enabling Works Phase 1 £1.068m (iii) Subject to Planning Permission, East Reading MRT Phases 1 and 2 (and failing planning permission, South Wokingham Distributor Road – Eastern Gateway) £5.000m (iv) Further revenue support for the future infrastructure business cases, the balancing amount (£0.874m based on a £10m overall approval)

28. Network Rail Access for All: CP6 Programme

A report was considered on the Network Rail Access for All station improvement programme. In July 2018, the Government had confirmed that it would make £300m available to Network Rail to continue the programme in Control Period 6 (2019 to 2024) to improve accessibility to stations. BLTB was asked to agree the stations shortlisted in Berkshire to be submitted to Network Rail for inclusion. Network Rail guidance set out the criteria to identify stations for improvement and the Berkshire Strategic Transport (Officer’s) Forum had applied these and recommended submitted a shortlist of Mortimer, Pangbourne, Reading West, Tilehurst and Winnersh Triangle.

BLTB discussed other options on the Long List, including the recommendation of Winnersh over Earley, however, the rationale was explained and it was noted that neither platform at Winnersh was accessible and it was therefore considered to best meet Network Rail’s criteria. After discussion, the shortlist in Table 3 of the report was agreed to be submitted to Network Rail who managed the programme.

Resolved – That the prioritised list of stations set out in table 3, paragraph 11 of the report be submitted to Network Rail for consideration for inclusion in the CP 6 Access for All programme.

29. BLTB Forward Plan

The BLTB Forward Plan set out the matters expected to be considered at future meetings. The plan would be adjusted in view of the earlier decision to arrange an extraordinary meeting in January 2019.

Resolved – That the BLTB Forward Plan be noted.

30. Date of Next Meeting - 14th March 2019

It was agreed that an extraordinary meeting of BLTB would be held on 31st January 2019.

The next scheduled meeting would be held on 14th March 2019.

Chair (Note: The Meeting opened at 4.01 pm and closed at 4.55 pm)

Page 8 Berkshire Local Transport Body – Meeting held on Thursday, 31st January, 2019.

Present:- Councillor Page (in the Chair) Reading Borough Council Charles Eales (Vice-Chair) Thames Valley Berkshire LEP Stuart Atkinson Thames Valley Berkshire LEP Councillor Bicknell RBWM Councillor Carter Slough Borough Council Councillor Clifford West Berkshire Council Malcolm Kempton Thames Valley Berkshire LEP Bob Mountain Thames Valley Berkshire LEP Simon Ratcliffe Thames Valley Berkshire LEP Councillor Sleight (deputy) Wokingham Borough Council Matthew Taylor Thames Valley Berkshire LEP

Also present under Rule 30:- Councillor Chopping (Wokingham Borough Council)

In attendance:- Rob Stubbs (RBWM, TVB LEP accountable body)

Apologies for Absence:- None.

PART 1

31. BLTB Membership

It was noted that following a recruitment process, Bob Mountain had been appointed to BLTB as a representative of Thames Valley Berkshire LEP.

Resolved – That Bob Mountain be welcomed to BTLB.

32. Declarations of Interest

Matthew Taylor declared that he worked for Stewarts Coaches Ltd, which had a potential commercial interest in Item 8: 2.34 Slough MRT Phase 2. He withdrew from the meeting during consideration of the item.

33. Briefing Note - TVB LEP/BLTB 'How We Work' - To Note

Members noted a briefing note that summarised the process by which Thames Valley Berkshire LEP and the Berkshire Local Transport Body operated in investing in local transport schemes. The Chief Executive of Thames Valley Berkshire LEP commented that the organisation was going through a new assurance process which was likely to include a review of BLTB Assurance Framework and ways of working.

Resolved – That the BLTB ‘How we work’ briefing note be noted.

Page 9 Berkshire Local Transport Body - 31.01.19

34. Revised Local Growth Fund Programme 2015/16 to 2020/21

A report was considered on proposals to revise the Local Growth Fund (LGF) programme 2015/16 to 2020/21.

East Reading MRT Phases 1 and 2 had been delayed following the refusal of planning permission for the second time by Wokingham Borough Council. The scheme promoter had confirmed that it could not therefore be delivered within the current LGF programme by the end of 2020/21. It was proposed that the £19,067,000 of LGF be re-allocated to following schemes from the previously agreed prioritised list:

 2.35 Reading: Reading West Station Upgrade  2.36 Wokingham: Coppid Beech Park and Ride  2.37 Bracknell: A322 A329 Corridor Improvements  2.38 Theale: Theale Station Park and Rail Upgrade  2.39 Wokingham: Coppid Beech northbound on-slip widening  2.40 Windsor: Town Centre Package

It was also proposed that consideration of programme entry status for a further scheme, 2.41 Slough: MRT Phase 3 A4 West Park & Ride, be deferred until the BLTB meeting in March 2019.

BLTB was disappointed that the delays to the East Reading MRT scheme had meant that it could not be delivered in the timescales required for LGF investment and some of the lessons learned were discussed. Councillor Page commented that Reading Borough Council would continue to look at the options to address the transport issues that the scheme sought to address. It was recognised that there were delivery risks to major schemes but that effective programme management meant that there were other strong schemes able to be funded and realistically delivered on time. The timetable was tight for the proposed schemes and assurance was sought from scheme promoters that they would able to bring forward their schemes by 2021.

There were particular timetable risks for the Slough MRT Phase 3 A4 West Park and Ride scheme given the involvement of other interested parties and discussions were ongoing with Highways . BLTB agreed that it would want to be assured that the delivery risks could be managed by the time it was considered for financial approval in March 2019. It was also agreed that the links with bodies such Highways England and Network Rail were important and TVB LEP was asked to discuss with them their engagement at the LTB and/or Berkshire Strategic Transport Forum.

At the conclusion of the discussion, the LTB agreed that the East Reading MRT schemes be deleted from the programme and the funding released be reallocated to other schemes as per the prioritised list.

Page 10 Berkshire Local Transport Body - 31.01.19

Resolved –

(a) That scheme 2.14 and 2.25 East Reading MRT Phases 1 and 2 be deleted from the LGF programme following notification from Reading Borough Council that it cannot now be progressed before March 2021.

(b) That programme entry status be granted to the following schemes (agreed at the meeting of the BLTB in July 2018):

 2.35 Reading: Reading West Station Upgrade  2.36 Wokingham: Coppid Beech Park and Ride  2.37 Bracknell: A322 A329 Corridor Improvements  2.38 Theale: Theale Station Park and Rail Upgrade  2.39 Wokingham: Coppid Beech northbound on-slip widening  2.40 Windsor: Town Centre Package

(c) That consideration of programme entry status for scheme 2.41 Slough: SMaRT Phase 3 A4 West Park and Ride be deferred until the meeting of the BLTB in March.

35. Business Rates Retention Pilot Year 2 - Approvals

Following the successful application for a second Berkshire-wide Business Rates Retention Pilot (BRRP), a report was considered that recommended the allocation of BRRP 2 monies.

The Berkshire Treasurers’ Group had calculated a planning figure of £11m for allocation for 2019/20 on the same basis as for schemes in the first year which was for major infrastructure schemes which supported housing development or major regeneration projects.

The schemes proposed to be funded through BRRP 2 were as follows:

 Slough MRT Phase 2 £3.058m.  Maidenhead Housing Sites Enabling Works Phase 1 £1.068m.  South Wokingham Distributor Road – Eastern Gateway £5.000m.  Further revenue support for the development of infrastructure business cases (£1.874m).

Approval was also sought to award programme entry status to 2.42 Wokingham: South Wokingham Distributor Road – Eastern Gateway. The recommendations were in line with the priorities agreed by BLTB at the meeting in November 2018. It was also noted that there was an anomaly in the minutes of the meeting held on 19th July 2018 relating to Slough MRT Phase 2 and it was proposed that this be clarified as per resolution (c) below.

After due consideration, the LTB agreed the recommendations as proposed.

Page 11 Berkshire Local Transport Body - 31.01.19

Resolved –

(a) That the following allocation of BRRP funds in 2019-20 be confirmed:

i. Slough MRT Phase 2 £3.058m (top up from BRRP1) ii. Maidenhead Housing Sites Enabling Works Phase 1 £1.068m (20% own contribution from LGF) iii. South Wokingham Distributor Road – Eastern Gateway £5.000m iv. Further revenue support for the development of infrastructure business cases, the balancing amount (£1.874m based on a £11m overall approval), subject to a detailed report to a future meeting of BLTB

(b) That programme entry status be granted to 2.42 Wokingham: South Wokingham Distributor Road – Eastern Gateway.

(c) That Minute 7 of the BLTB meeting of 19th July 2018 in relation to Slough MRT Phase 2 be corrected, by reiterating that in order to cap the level of BRRP commitment at £25m, the funding for the Slough MRT scheme was agreed to be reduced from £13.3m to £10.242m

36. TfSE - Proposal to Seek Statutory Status - Informal Engagement Process

A report was considered that set out the process for Transport for the South East (TfSE) to seek statutory status. The purpose of the Sub-National Transport Body would be to facilitate the development of a transport strategy and so promote economic growth for the area.

The TfSE Shadow Board had approved a draft Proposal to Government for informal engagement in the period to 1 March 2019 followed by a formal period of consultation between 2 May and 31 July 2019 after the local elections. Briefings were proposed for each of six Berkshire authorities and those in West Berkshire, Slough and Reading were already confirmed. Each authority would need to take a report to their relevant decision making body to make a formal resolution to become a constituent authority of TfSE.

Councillor Page, who was the Vice-Chair of TfSE, encouraged authorities to participate during the engagement periods and informed members of the approach that was being taken to ensure the new body added value to work at local and sub-regional level.

The membership arrangements and distribution of votes were clarified. There would be one representative for BLTB with six votes of a total of 54 from TfSEs constituent authorities. Each Berkshire authority were contributing circa £10,000 for their membership. It was an option for each unitary authority to participate individually rather than through BLTB jointly, the cost of which would be circa £30,000 each.

Page 12 Berkshire Local Transport Body - 31.01.19

Members agreed the importance of working collaboratively to develop the strategy and schemes. It was noted that workshops would be held and proposals would come back to the LTB for consideration as the work of TfSE moved forward.

At the conclusion of the discussion, the recommendations were agreed.

Resolved –

(a) That it be noted that the officers would prepare a response on behalf of BLTB which would be subject to your further consideration and response on 15 March 2019;

(b) That it be noted that TfSE proposed to conduct formal consultation on its final proposal to government and that this would be the subject of a further report to the BLTB meeting on 18 July 2019.

37. Financial Approval for 2.32 Maidenhead: Housing Sites Enabling Works Phase 1

A report was considered that sought giving financial approval to scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1. The scheme consisted of a package of traffic management measures to deliver additional capacity at key junctions around Maidenhead.

It was proposed that conditional approval for a total of £4.2m be given subject to the supply of further evidence to support the business case. The scheme had been reduced from the original 8 junctions to 6 and the costs had reduced by £600k accordingly. The scheme had a high Benefit-Cost Ratio of 3.2.

BLTB welcomed the progress of the scheme and agreed financial approval, subject to the conditions set out in the report.

Resolved –

(a) That scheme 2.32 Maidenhead: Housing Sites Enabling Works Phase 1 be given conditional financial approval in the sum of £2,123,200 in 2019/20 and £2,090,000 in 2020/21 on the terms of the funding agreement set out at paragraph 12 step 5 below, subject to meeting the following conditions:

(b) The supply of further evidence which supported the conclusions reached in the Full Business Case in respect of:

 Additional detail outlining the approach adopted to determine the dependent development sites and preferred junction enhancements.  Further detail on how the package of junction improvements will address the secondary objectives relating to accidents, air quality and accessibility for walking & cycling.

Page 13 Berkshire Local Transport Body - 31.01.19

 Additional detail on the RBWM-HM2 model, its baseline calibration and validation, and how it reflects current junction performance.  Detailed workings to support the outputs of the quantified economic assessment.  Inclusion of sensitivity tests to understand the impact of any variability in the benefits and costs of the scheme.  Full assessment of environmental and social impacts of the scheme and inclusion of an Appraisal Summary Table.  Further detail around scheme costs, contingency (linked to a quantified risk assessment), and levels of cost inflation.  Clarifications to the Commercial Case in relation to the procurement processes.  Provision of a full project programme, risk register and Quantified Risk Assessment  That the scheme retains high or better value for money once these conditions have been met.

(Matthew Taylor withdrew from the meeting at this point)

38. Financial Approval for 2.34 Slough MRT Phase 2

A report was considered that sought full financial approval for a total of £13.3m for Slough Mass Rapid Transit (MRT) Phase 2 from the Business Rates Retention Pilot. It was noted that a revised version of the report had been published in a Supplementary Agenda and it was this version that was considered.

Phase 2 would extend the MRT project from its current end point at Langley and take it onto the Heathrow service road. Bus lanes and other priority measures would be put in place and there was also funding for a 600-car park and ride site at Brands Hill. Members asked a number of questions including about the impact on the commercial viability of the scheme if Heathrow Airport expansion did not take place. The scheme promoter responded that three bus services were already in operation and would link into the park and ride. Heathrow expansion would add further and more frequent services but assurance was provided that the scheme was not dependent on airport expansion.

After due consideration, financial approval was given to the scheme.

Resolved – That scheme 2.34 Slough MRT Phase 2 be given full financial approval in the sum of £13,300,000, with £10,242,000 in 2018/19 from BRRP1 and £3,058,000 in 2019/20 from BRRP2 on the terms of the funding agreement set out at paragraph 12 step 5 of the report.

(Matthew Taylor rejoined the meeting)

Page 14 Berkshire Local Transport Body - 31.01.19

39. Business Rates Retention Pilot - Revenue Support

A report was considered that recommended approval of the revenue support proposal of Bracknell Forest Council under the provision put in place in July 2018 to “top slice” £600k from the BRRP to provide revenue funding to assist authorities develop a strong pipeline of future infrastructure schemes.

The revenue funding of £100k each for Reading, West Berkshire, Windsor & Maidenhead and Wokingham had been agreed by the LTB in November 2018 and the proposal of Bracknell Forest was set out in Appendix 1. Slough’s proposal was due to be approved in March 2019.

The LTB agreed the revenue support proposal of Bracknell Forest Council as at Appendix 1 to the report.

Resolved – That the revenue support proposal and the drawdown of BRRP funds by Bracknell Forest Council set out in appendix 1 to the report be approved.

40. Date of Next Meeting - 14th March 2019

The date of the next meeting was confirmed as 14th March 2019.

Chair

(Note: The Meeting opened at 4.00 pm and closed at 4.40 pm)

Page 15 This page is intentionally left blank AGENDA ITEM 3

How we work

Thames Valley Berkshire Local Enterprise Partnership (TVB LEP) and the Berkshire Local Transport Body (BLTB) – investing in local transport schemes

This briefing note is intended to set out the way TVB LEP works with BLTB to invest Local Growth Funds in transport schemes.

1. TVB LEP is a business-led organisation responsible for determining the key funding priorities to which Local Growth Funds (LGF) and other public resources are directed in order to implement a Strategic Economic Plan (SEP) and meet its commitments in the TVB Growth Deals. As a company limited by guarantee (registered at Companies House No. 07885051) it operates according to its Articles of Association, which comply with the Companies Act 2006. As a publicly-funded body it behaves in accordance with an Assurance Framework, which determines the practices and standards necessary to provide assurance to government and local partners that decisions over (all government) funding are proper, transparent and deliver value for money. [LEP Assurance Framework (AF) January 2017]

2. BLTB consists of six elected members (usually the lead member for transport or related portfolio), and six private sector representatives recruited and appointed by the LEP. [LEP AF 1.11]. It is a Joint Committee of the six unitary authorities in Berkshire and its constitution is set out in its Founding Document.

3. TVB LEP recognises BLTB as “the competent body to a) prioritise and b) implement transport capital schemes on its behalf. In practice the LEP will accept any BLTB recommendations or refer them back but will not substitute its own recommendations.” [LEP AF 1.12]

4. The process established by government for making Growth Deals is to invite LEPs to submit competitive proposals, and after due consideration to make awards based on all or part of a LEP bid. To date TVB LEP has agreed three Growth Deals. Each of these has included, among other things, the award of capital funds for individual transport schemes that were prioritised in the TVB LEP bid and named in the Growth Deal settlement.

5. TVB LEP works with its partners to identify and prioritise suitable schemes. It is a lobbying organisation, and, via Growth Deals, a joint-funder of selected schemes promoted by (usually, but not always) a local transport authority. [BLTB Founding Document (FD) 11-13]

6. BLTB requires promoters to develop each scheme in accordance with current WebTAG guidance published by DfT. In order to receive financial approval from BLTB, the Full Business Case must be subject to independent assessment and a positive recommendation about value for money. [BLTB FD 14-16]

7. The scheme promoter is responsible for all aspects of the design, risk management, insurance, procurement, construction and implementation of the scheme, including their responsibilities as highway and planning authorities, any other statutory duties, and any financial or other liabilities arising from the scheme. [BLTB FD 18]

8. The time taken between an initial government call for bids and the final announcement of a new Growth Deal can be in excess of a year. TVB LEP (together with BLTB for transport schemes) must go through a number of steps to respond to a government call for bids. Similarly, a transport scheme promoter also must go through several steps:

Page 17 Page 18 AGENDA ITEM 4

BERKSHIRE LOCAL TRANSPORT BODY (BLTB)

REPORT TO: BLTB DATE: 14 March 2019

CONTACT OFFICER: Joe Carter, Director of Regeneration, Slough Borough Council, lead officer to the BLTB

PART I

Item 4: Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21

Purpose of Report

1. To report on the progress of the Thames Valley Berkshire Local Growth Deali, as amended by Growth Deal 2 (£10.2 million further support to Thames Valley Berkshireii) and Growth Deal 3 (Factsheet GD3iii) with particular reference to the schemes included in the Transport Packages of the Strategic Economic Planiv; and on the progress of schemes funded by the Business Rates Retention Pilot (BRRP) 2018/19.

2. The headline figure for transport scheme grants under the three Local Growth Deals is £135.926m. This includes £24m of “DfT retained” allocation relating to the Wokingham Distributor Roads. This report provides progress reports on all programme entry schemes and the TVB Smart City Cluster (Smart Berkshire) scheme. A further £25m has been released through BRRP1 2018/19 and £11m from BRRP2 2019/20.

3. £14.742m was spent on transport schemes in 2015/16, £16.546m in 2016/17 and £15.055m in 2017/18. We are planning (at 5 March 2019) to spend £19.618m this year; £8.810m from Local Growth Deals and £10.808m from BRRP.

Recommendations

4. That you note the progress made on the schemes previously given programme entry status, as set out in Appendix 1.

Other Implications

Financial

5. Thames Valley Berkshire LEP has been granted freedoms and flexibilities in managing the Local Growth Deal Capital Programme. This means that we will receive an annual allocation of capital within which it will be our responsibility to manage the allocation to individual schemes. This is a positive development for TVB LEP and recognises the confidence that government has in our governance arrangements.

6. The government has confirmed the allocation of funding for 2018/19 and there is a provisional profile for payments in the financial years 2019/20 - 2020/21.

Item 4 BLTB 14 March 2019 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Page 19 Table 1: Available Finance for Transport Schemes in TVB Local Growth Deal and BRRP £m 2015/16 – 2020/21 LTB previously approved 14.5 Growth Deal 1 56.1 Less unallocated - 0.7 55.4 Growth Deal 1 “DfT Major Schemes” 24.0 Growth Deal 2 7.5 Growth Deal 3 33.8 Plus unallocated 0.7 34.5 Local Growth Deal Total 135.9 BRRP 2018/19 and 2019/20 36.0 Grand Total 171.9

7. The profile and status of the available money in each year is as follows:

Table 2: Local Growth Deal and BRRP Financial Allocations by Financial Year £m 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Combined Growth Deal 1, 2, 3 14.7 16.5 15.1 8.8 - - 55.2 and LTB Allocation approved Growth Deal 1 (DfT Major - - - 0.9 22.1 1.0 24.0 Schemes) indicative Combined Growth Deal 1, 2 and 3 - - - - 19.8 37.0 56.8 LTB Allocation indicative profile Local Growth Deal Total 14.7 16.5 15.1 9.7 41.9 38.0 135.9 BRRP - - - 11.5 24.5 - 36.0 Grand Total 14.7 16.5 15.1 21.2 66.4 38.0 171.9

8. Table 3 sets out the final allocation of scheme finance for 2015/16, 2016/17 and 2017/18 and the provisional allocation for future financial years, which are subject to alteration following the government’s confirmation of the Local Growth Deal funding profile.

Table 3 – Local Growth Deal and BRRP Scheme Funding Profiles Scheme Name Status 15/16 16/17 17/18 18/19 19/20 20/21 £m Newbury: King’s Rd 2.01 GD 1 On site - 1.335 1.000 - - - 2.335 Link Road Bracknell: Warfield 2.02 GD 1 Complete 3.500 - - - - - 3.500 Link Road Newbury: London Rd 2.03 GD 1 Complete 0.500 1.400 - - - - 1.900 Industrial Estate Wokingham: DfT 2.04 Programme entry - - - 0.874 22.126 1.000 24.000 Distributor Roads major

Item 4 BLTB 14 March 2019 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Page 20 Scheme Name Status 15/16 16/17 17/18 18/19 19/20 20/21 £m Newbury: Sandleford 2.05 GD 2 On site - - - 2.000 0.900 - 2.900 Park Reading: Green Park 2.06 GD 1 On site - - 4.575 - 4.575 - 9.150 Railway Station Bracknell: Coral Reef 2.07 GD 1 Complete 2.100 - - - - 2.100 Roundabout 2.08 Slough: MRT Phase 1 GD 1 Complete 3.100 2.500 - - - - 5.600 2.09 Sustainable Transport: GD 1 On site - 2.100 1.500 0.200 0.400 - 4.200 .1 NCN 422 2.09 Sustainable Transport: GD 1 Complete - 0.483 - - - - 0.483 .2 A4 Cycle Slough: A332 2.10 GD 1 On site 1.267 1.433 - - - - 2.700 improvements Reading: South 2.11 Reading MRT Ph 1 GD 1 On site - 2.970 1.530 - - - 4.500 Reading: South 2.12 Reading MRT Ph 2 Wokingham: Thames 2.13 Valley Park and Ride GD 1 On site - - - 2.000 0.900 - 2.900 formerly Reading: Eastern Reading Park and Ride Reading: East Reading 2.14 GD 1 MRT Ph1 Withdrawn ------Reading: East Reading 2.25 GD 3 MRT Ph2 Bracknell: Martins 2.15 GD 1 On site - 0.200 2.700 - - - 2.900 Heron Roundabout Maidenhead: Station 2.16 GD 1 On site - - - 0.690 3.060 - 3.750 Access 2.17 Slough: A355 route GD 1 Complete 2.275 2.125 - - - - 4.400 2.18 not used ------Bracknell: Town 2.19 GD 2 Complete 2.000 - - - - - 2.000 Centre Regeneration 2.20 not used ------Slough: Langley 2.21 Station Access GD 2 On site - - 1.500 - - - 1.500 Improvements Slough: Burnham 2.22 Station Access GD 2 On site - 2.000 - - - - 2.000 Improvements Reading: South On site. 2.23 Reading MRT Phases GD 3* Part-funded by - - 2.250 0.090 - - 2.340 3-4 BRRP see below Newbury: Railway 2.24 GD 3 On site - - - 3.630 0.921 1.500 6.051 Station Improvements 2.25 Withdrawn 2.26 Wokingham: Winnersh Relief Rd Phase 2 – See BRRP below Conditional Maidenhead Town 2.27 GD 3 approval - - - - 0.842 1.400 2.242 Centre: Missing Links November 2018 Bracknell: A3095 2.28 GD 3 On site - - - 0.200 1.800 3.519 5.519 Corridor Improvements GD 3 FBC (conditional Wokingham: Winnersh 2.29 reserve approval) due - - - - 0.250 2.750 3.000 Parkway scheme March 2019 Slough: Stoke Road GD 3 FBC due 2.31 - - - - 2.500 5.150 7.650 Area Regeneration reserve July 2019

Item 4 BLTB 14 March 2019 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Page 21 Scheme Name Status 15/16 16/17 17/18 18/19 19/20 20/21 £m scheme GD 3 Conditional Maidenhead: Housing reserve approval. 2.32 Sites Enabling Work - - - - 2.123 2.090 4.213 scheme Part-funded by Phase 1 BRRP see below GWR: Maidenhead to GD 3 Being managed by 2.33 Marlow Branch Line reserve - - - - 1.525 - 1.525 Bucks TV LEP Upgrade scheme 2.34 Slough MRT Phase 2 – See BRRP below GD 3 Reading West Station Programme Entry 2.35 reserve - - - - - 3.100 3.100 Upgrade January 2019 scheme GD 3 Wokingham: Coppid Programme Entry 2.36 reserve - - - - - 2.400 2.400 Beech Park and Ride January 2019 scheme GD 3 Bracknell: A322 A329 Programme Entry 2.37 reserve - - - - - 1.200 1.200 Corridor Improvements January 2019 scheme GD 3 Theale Station Park Programme Entry 2.38 reserve - - - - - 4.000 4.000 and Rail Upgrade January 2019 scheme GD 3 Wokingham: Coppid Programme Entry 2.39 reserve - - - - - 2.322 2.322 Beech northbound January 2019 scheme GD 3 Windsor: Town Centre Programme Entry 2.40 reserve - - - - - 1.563 1.563 Package January 2019 scheme N/a Unallocated - - - - - 6.005 6.005 Local Growth Deal Total 14.742 16.546 15.055 9.684 41.922 37.999 135.948 Reading: South On site. 7.808 2.23 Reading MRT Phases BRRP Part funded in - - - 7.808 - - LEP total 3-4 GD3 see above 10.148 FBC approved 2.34 Slough MRT Phase 2 BRRP - - - - 13.300 - 13.300 January 2019 Conditional Wokingham: Winnersh 2.26 BRRP approval - - - 3.000 3.260 - 6.260 Relief Road Phase 2 November 2018 Conditional Maidenhead: Housing approval. 2.32 Sites Enabling Works BRRP - - - - 1.068 - 1.068 Part-funded in Phase 1 GD3 see above South Wokingham Programme Entry 2.41 Distributor Road – BRRP - - - - 5.000 - 5.000 January 2019 Eastern Gateway Approved / N/a BLIS development BRRP - - 0.090 - - 0.090 underway - 5 proposals Business Case N/a BRRP approved, 1 to be - - - Preparation 0.600 - - 0.600 approved Mar 19 N/a Unallocated BRRP - - - - 1.874 - 1.874 BRRP Total - - - 11.498 24.502 - 36.000

Risk Management

9. The delegation of programme management responsibilities to the LEP/BLTB brings risks. The well-established scrutiny given by both BST(O)F and BLTB meetings is designed to mitigate that risk.

10.There will be an element of risk for scheme promoters who invest in developing their schemes to full business case stage in accordance with the approved

Item 4 BLTB 14 March 2019 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Page 22 Assurance Frameworkv. However, there is also risk involved in not developing the schemes; that risk is that any reluctance to bring the schemes forward will result in any final approval being delayed or refused.

11.The risks associated with each scheme are monitored locally and one of the 30 currently has a “red” risk rating. Tables 4, 5 and 6 show the current risk rating of each of the schemes. Table 4: Completed schemes (7)

Scheme Notes 2.02 Bracknell: Warfield Link Road One-year-on impact report due November 2019 2.03 Newbury: London Rd Industrial Estate One-year-on impact report submitted July 2018 2.07 Bracknell: Coral Reef One-year-on impact report submitted November 2017 2.08 Slough: Rapid Transit Phase 1 One-year-on impact report due March 2020 2.09.2 Sustainable Transport: A4 Cycle One-year-on impact report due November 2019 2.17 Slough: A355 route One-year-on impact report submitted July 2018 2.19 Bracknell: Town Centre Regeneration One-year-on impact report due March 2019

Table 5: Risk rating of schemes with a 2015/16, 2016/17, 2017/18 or 2018/19 start (15) RAG Scheme Status Notes rating Newbury: Kings Road 2.01 On site Green Completion due January 2021 Link Road Newbury: Sandleford 2.05 On-site Amber Completion revised to November 2021 Park Reading: Green Park 2.06 On site Amber Completion revised to summer 2020 Station Sustainable Transport: 2.09.1 On site Green Completion due December 2019 NCN 422 Slough: A332 2.10 On site Amber Completion revised to April 2019 improvements 2.11 Reading: South and Reading MRT phases On site Green Completion due May 2019 2.12 1 and 2 Wokingham: Thames 2.13 Valley Park and Ride On site Green Completion due summer 2019 formerly Reading: Eastern Reading Park and Ride Bracknell: Martins 2.15 On site Green Completion due April 2019 Heron Maidenhead: Station 2.16 On site Green Completion due March 2020 Access Slough: Langley 2.21 Station Access On site Amber Completion revised to September 2019 Improvements Slough: Burnham LGF forecourt work revised to March 2.22 Station Access On site Green 2019 Improvements Reading: South 2.23 Reading MRT Phases On site Green Completion March 2020 3-4 Newbury: Railway 2.24 On site Green Completion due March 2021 Station Improvements On site Wokingham: Winnersh 2.26 (enabling Green Completion due September 2020 Relief Road Phase 2 works)

Item 4 BLTB 14 March 2019 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Page 23 On site Bracknell: A3095 2.28 (enabling Green Completion due November 2021 Corridor Improvements works)

Table 6: Risk rating of schemes with later starts (14) RAG Scheme Status Notes rating FBC being Funding now 100% to Arborfield Wokingham 2.04.4 developed for Amber Cross Relief Road. Advance fees Distributor Roads approval by DfT approved FBC approved Maidenhead Town 2.27 (conditional) Amber Start on site due July 2020 Centre: Missing Links November 2018 FBC approval Financial approval (conditional) Wokingham: 2.29 (conditional) due Amber recommendation elsewhere on this Winnersh Parkway March 2019 agenda Slough: Stoke Road Detailed scheme 2.31 Amber Full Business Case due July 2019 Area Regeneration in development Maidenhead: FBC approved Housing Sites 2.32 (conditional) Amber Start on site due August 2019 Enabling Works January 2019 Phase 1 GWR: Maidenhead Detailed scheme 2.33 to Marlow Branch Amber Approval process via Bucks TV LEP in development Line Upgrade FBC approved 2.34 Slough MRT Phase 2 Green Start of site due July 2019 January 2019 Reading West Detailed scheme 2.35 Amber Station Upgrade in development Wokingham: Coppid Detailed scheme 2.36 Amber Beech Park and Ride in development Bracknell: A322 Detailed scheme 2.37 A329 Corridor Amber in development Improvements Theale Station Park Detailed scheme 2.38 Amber and Rail Upgrade in development Wokingham: Coppid Detailed scheme 2.39 Amber Beech northbound in development Windsor: Town Detailed scheme 2.40 Amber Centre Package in development South Wokingham Detailed scheme 2.41 Distributor Road – Amber in development Eastern Gateway

Table 7: Withdrawn schemes (1) RAG Scheme Status Notes rating 2.14 Reading: East Scheme withdrawn following failure to and Reading Mass Rapid Full approval Red 2.25 Transit 1&2 secure planning consent

12.In addition to these capital schemes, the is a further Local Growth Deal funded project called 2.30 TVB Smart City Cluster (Smart Berkshire). The project delivers three key deliverables: a. Smart city platform: consisting of an Internet of Things (IoT) communication platform across Reading, Wokingham, West Berkshire and Bracknell and a cross-authority open data platform. This is enabling infrastructure for the delivery of a wide range of IoT technologies

Item 4 BLTB 14 March 2019 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Page 24 including traffic signal communications which will provide the revenue savings to maintain and operate the system. b. Challenge funded IoT solutions: grant funded IoT solutions to real Local Authority challenges which will utilise the platform. These grants will be awarded through competition and will be on the basis of co-funding. c. Cross authority / cross sector smart city group: This includes a Steering Group to oversee the project delivery and act as a catalyst for wider smart city debate, project development and funding A pro-forma giving detailed progress is included in Appendix 1.

Human Rights Act and Other Legal Implications

13.The Assurance Frameworkvi referred to above identifies the steps that scheme promoters should take in order to secure financial approval from the LTB. There are, in effect, two layers of scheme approval. The first, and primary layer rests with the scheme promoter (all the schemes referred to in this report are being promoted by Local Authorities). In order to implement the schemes in question, each promoter will need to satisfy themselves that all the legal implications have been considered and appropriately resolved. The secondary layer of approval, given by the LTB, is concerned with the release of funds against the detailed business case. The arrangements for publication of plans via the LEP and promoters’ websites, the arrangements for independent assessment and the consideration of detailed scheme reports are appropriate steps to ensure that any significant Human Rights Act or other legal implications are properly identified and considered.

Supporting Information

14.The Thames Valley Berkshire LEP website has published summary information about all its Growth Deal-funded projects, including all transport projects. Please go to Thames Valley Berkshire Local Growth Fund e-Bookvii

15.There is a detailed progress report on each of the schemes at Appendix 1 to this report.

Monitoring and Evaluation

16.The Monitoring and Evaluation Plan for the Thames Valley Berkshire Growth Deal has now been drafted with advice from government. In addition to the need for transport scheme promoters to collect and publish monitoring and evaluation reports that comply with DfT guidance for capital schemes, there will be requirements to cooperate with the overall monitoring and evaluation plan for the Growth Deal.

17.The difference between the two processes is that one concentrates on the transport impacts and the other on the economic impacts. The basic information required from each scheme promoter is set out in paragraph 6 of the scheme proformas. This requirement is less onerous for schemes under £5m Growth Deal contribution and runs to much more detail for the larger schemes.

Item 4 BLTB 14 March 2019 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Page 25 18.For most schemes there will be little or no additional Growth Deal monitoring burden beyond that already signalled. Extra effort may be required to comply with the standard set out in the Monitoring and Evaluation plan which is “accurate, timely, verified and quality assured monitoring data”. For schemes mentioned by name in the Monitoring and Evaluation Plan (see list below) there will be a separate discussion about the duties on the scheme promoter:

2.01 Newbury: King’s Road Link Road 2.04 Wokingham: Distributor Roads Programme 2.06 Reading: Green Park Railway Station 2.08 Slough: Rapid Transit Phase 1 2.14 Reading: East Reading Mass Rapid Transit (scheme has been withdrawn)

Background Papers Each of the schemes referred to above has a proforma summarising the details of the scheme. Both the SEP and LTB prioritisation processes and scoring schemes are also available background papers. The Monitoring and Evaluation Plan for TVB Growth Deal is also available. ihttps://www.gov.uk/government/uploads/system/uploads/attachment_data/file/327587/35_Thames_ Valley_Berkshire_Growth_Deal.pdf iihttps://www.gov.uk/government/uploads/system/uploads/attachment_data/file/399438/Thames_Vall ey_Berkshire_Factsheet.pdf iiihttps://www.gov.uk/government/uploads/system/uploads/attachment_data/file/589268/170202_Tha mes_Valley_Berkshire_LEP_GD_factsheet.pdf iv http://www.thamesvalleyberkshire.co.uk/documents?page=1&folder=192&view=files vhttp://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum vihttp://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum vii http://www.thamesvalleyberkshire.co.uk/investing-in-growth

Item 4 BLTB 14 March 2019 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Page 26 Meeting Date: 14 March 2019 2.01 Newbury: King’s Road Link Road

Highlights since last report

1 The Scheme 1.1.The scheme is the delivery of the Kings Road Link Road in Newbury. It is a new direct link between the Hambridge Road industrial area and the A339 to support housing delivery and significantly improve access to a key employment area.

2 Progress with the scheme 2.1. The Western Area Planning Committee recommended approval for the scheme on 18 March 2015 and referred it to the District Planning Committee (DPC) for final decision. The DPC considered the planning application on 25 March 2015 and granted approval. 2.2. Work on site started on 24 October 2016. The demolition works are complete. Geo-environmental Consultants have produced the Remediation Strategy based on results of the geotechnical and contamination reports. The strategy has also been discussed with the who have a strong interest in the site. The outcome of this work and the remediation strategy is that the costs have increased. 2.3. To assist with the shortfall in funding now that costs have significantly increased (as evidenced by an updated viability assessment), the Council submitted a bid for £1.5m to the Housing Infrastructure Fund. The site was considered to fit well with the criteria for their Marginal Viability Fund and the full £1.5m requested has been allocated to this scheme. There has been a delay in this funding becoming available, due to Homes England’s protracted process in agreeing a form of contract that they will take up with the individual authorities. The Council is therefore working with the developer to plug this temporary shortfall in funding during the decontamination process. As a result of this working together, works have re-commenced on site and the decontamination is well underway. 2.4. The Council and the Developer have established a funding agreement to ensure the correct governance of the public money contributing to this scheme. 2.5. Network Rail has completed the work to replace the rail bridge adjacent to the redevelopment site. The new bridge was open to traffic at the end of January 2017 following the 12 month replacement programme. Initially there is a traffic light controlled single lane system operating until the redevelopment of the industrial estate is complete and the northern approach to the bridge has been widened. Then the bridge will operate with two lanes and the traffic lights will be removed. This will have a great benefit to the transport network in this area. 2.6 Delivery continuing and payments being made to Developer as per funding agreement. 3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £1,335,000 £1,000,000 £2,335,000 Local contributions from - Section 106 agreements £40,000 £80,000 £200,000 £180,000 £500,000 - Council Capital Programme £180,000 £200,000 £380,000 - Other sources (NR and HIF) £1,010,000 £600,000 £1,500,000 £3,110,000 Total Scheme Cost £1,010,000 £1,975,000 £1,000,000 £1,580,000 £380,000 £380,000 £6,325,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Delivery of scheme being delayed and not fitting with BLTB funding. Ongoing discussions with the developer and liaison with the LEP will help to manage issues and delays. Ongoing assessment of costs as further details of the scheme are developed. Opportunities will be explored for any additional funding sources Escalating costs (such as HIF). A funding agreement sets out a maximum sum available to the Developer for the delivery of the road from the Council, the HIF and the LEP. 5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status 14-Jul-13 Independent Assessment of FBC Due October 2014 Mar-15 Financial Approval from LTB Due November 2014 Mar-15 Feasibility work N/a Acquisition of statutory powers Complete Detailed design Nov-14 Mar-15 Procurement Dec-14 Start of construction Jan-15 Remediation July '18 - Feb '19 Main works March '19 Completion of construction Apr-15 Jan-21 One year on evaluation Mar-17 Jan-22 Five years on evaluation Mar-20 Jan-26 Growth Deal Reporting Framework 6 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.01 Newbury: King’s Road Link Road Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £6,325,000 £2,441,000 £0 Funding breakdown Local Growth Deal £2,335,000 £831,000 s.106 and similar contributions £500,000 £0 Council Capital Programme £380,000 £0 Other £3,110,000 £1,610,000 In-kind resources provided £20,000 £13,000 Outcomes Actual to date Planned Jobs connected to the intervention 150 20 Commercial floorspace constructed (square metres) - Housing unit starts 177 0 Housing units completed 177 0 Number of new homes with new or improved fibre optic provision 100% 0

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.01 Newbury: King’s Road Link Road Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads N/a 0 Total length of newly built roads 230m 0 Total length of new cycle ways N/a 0 Type of infrastructure Highway Type of service improvement New road link in key town centre location Outcomes Follow on investment at site N/a Commercial floorspace occupied N/a Commercial rental values N/a

7. Further Information for Summary Reports The road will support housing delivery and significantly improve access to a key employment area. The scheme went on site in October 2016 and the demolition and preparation works have been delayed by the discovery of additional contamination. The first Growth Deal payment was made in March 2017; the second and final payment was made in March 2018. This is the original scheme approved in Growth Deal 1.

Page 27 Meeting Date: 14 March 2019

2.02 Bracknell: Warfield Link Road

Highlights since last report

1 The Scheme The project involves building a road to unlock a Strategic Development Location in Bracknell Forest (for 2,200 new dwellings, schools, neighbourhood centre, open space, SANGs and other infrastructure and facilities). The link road crosses the middle of the site and will serve as access for many of the development parcels.

2 Progress with the scheme 2.1. The scheme is now completeThe road is operating well and new parcels of development have started and are due to begin with the road fully opened to the public on 26 Ocotber 2018 2.2. The road is operating well and new parcels of development have started and are due to begin

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £3,500,000 £3,500,000 Local contributions from £0 - Section 106 agreements £1,700,000 £1,700,000 - Council Capital Programme £0 - Other sources £0 Total Scheme Cost £3,500,000 £1,700,000 £0 £0 £0 £0 £5,200,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk A delay on the development impacting on the need for the road and Liaison with developers and review agreement re programme delaying the programme

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-14 Independent Assessment of FBC Due October 2014 Financial Approval from LTB Due November 2014 Jan-15 Feasibility work Complete Acquisition of statutory powers Not needed Detailed design Mar-15 Jan-15 Procurement Developer s278 agreement Start of construction Apr-15 Feb-15 Completion of construction Mar-17 Road open for construction traffic Apr-17; Fully open to the public Nov-18 One year on evaluation Mar-18 Nov-19 (1 year from when open to public) Five years on evaluation Mar-22 Nov-23

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.02 Bracknell: Warfield Link Road Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £5,200,000 £5,200,000 £0 Funding breakdown Local Growth Deal £3,500,000 £3,500,000 s.106 and similar contributions £1,700,000 £1,700,000 Council Capital Programme Other £30,000 In-kind resources provided Outcomes Planning Numbers Actual to date Planned Jobs connected to the intervention 0 Commercial floorspace constructed (square metres) 0 Housing unit starts 750 473 Housing units completed 2,200 323

Number of new homes with new or improved fibre optic provision 2200 323

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.02 Bracknell: Warfield Link Road Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads Approximately 100m of resurfaced road Total length of newly built roads Approximately 750-1000m of newly built road. Total length of new cycle ways Approximately 750-1000m of new cycleways adjacent to proposed link road. Type of infrastructure New link road to allow for access to new development Type of service improvement Unlocking proposed development. Outcomes Follow on investment at site N/a Commercial floorspace occupied N/a Commercial rental values N/a

7. Further Information for Summary Reports

This road unlocks 2,200 new dwellings, schools, neighbourhood centre, etc. Started on site in February 2015, completion of construction achieved March 2017. Road two-thirds open to public, remainder restricted to housing construction traffic. Developers bringing forward additional housing starts. All Growth Deal payments made. This is the original scheme set out in Growth Deal 1.

Page 28 Meeting Date: 14 March 2019 2.03 Newbury: London Road Industrial Estate

Highlights since last report

1 The Scheme 1.1. This scheme is a new junction on the A339 in Newbury and associated widening to provide access to the London Road Industrial Estate (LRIE) which will unlock its potential for redevelopment. The scheme will open up a 10-hectare edge of town centre site for redevelopment and employment intensification. The proposal will unlock the potential for additional housing delivery and encourage an extension to the vibrant town centre. 1.2. The scheme and the redevelopment of the industrial estate that it will unlock is a long-standing objective within the Council’s Newbury Vision 2025. This vision document is seen very much as a community project and annual conferences in relation to its delivery are very well attended by all sectors of the Newbury community. 1.3. The redevelopment of the industrial estate and the highways scheme are both included in Council plans and documents the latest of which is the Housing Site Allocations DPD. Both political parties wish to see the redevelopment of this area which this scheme will enable. 1.4. The Council has appointed a development partner (St. Modwen) for the redevelopment project. This is an indication of the commitment of the Council to the wider project and has the full support of the Executive. 2 Progress with the scheme 2.1. Planning permission was granted for the scheme on 4 February 2015. 2.2. Financial approval was given for the scheme by the BLTB following confirmation from White Young Green in relation to the supporting Business Case (letter 9 March 2015). 2.3. The scheme was successfully completed on 27 March 2017. 2.4. Previous update reports set out that an outline planning permission could be in place by the end of 2018, but this was dependent on the outcome of a possible legal appeal in relation to the Council’s appointment of development partner St Modwen. After losing at the High Court, the opposing party sought leave to Appeal and after very extensive delays, this was granted. The Court of Appeal has ruled that the agreement WBC entered into with St Modwen was unlawful. The Council remains firmly committed to the redevelopment of the London Road Industrial Estate, including the delivery of housing, and is actively considering the way forward following the Court of Appeal's judgement. 2.5. The one-year evaluation report has been completed and is available on the Council’s website along with all other documents relating to the scheme www.westberks.gov.uk/sep 2.6. In relation to the development that this scheme seeks to unlock, the Court of Appeal has ruled that the development agreement entered into by the Council was unlawful. The Council is now actively seeking the best way forward to deliver the redevelopment plans to which it remains firmly committed.

3 Funding 3.1. The following table sets out the funding for the road access scheme on the basis of a provisional funding profile. It has been updated to include some additional money spent on the Challenge Fund works which were managed alongside this project.

Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £500,000 £1,400,000 £1,900,000 Local contributions from £0 - Section 106 agreements £90,000 £90,000 - Council Capital Programme £255,000 £945,000 £1,200,000 - Other sources £1,310,000 £1,310,000 Total Scheme Cost £845,000 £3,655,000 £0 £0 £0 £0 £4,500,000

4 Risks 4.1. The scheme is complete

5 Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status 24-Jul-14 Independent Assessment of FBC Oct-14 Financial Approval from LTB Nov-14 Mar-15 Feasibility work Complete Acquisition of statutory powers Feb-15 Detailed design trial pits and other investigation underway Complete Procurement Aug 2014 – March 2015 Sep-15 Start of construction Aug-15 Feb-16 Completion of construction May-16 Mar-17 One year on evaluation May-17 Jul-18 Five years on evaluation May-21 Mar-22

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.03 Newbury: London Road Industrial Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £4,500,000 £4,500,000 Funding breakdown Local Growth Deal £1,900,000 £1,900,000 s.106 and similar contributions £90,000 £90,000 Council Capital Programme £1,200,000 £1,200,000 Other £1,310,000 £1,310,000 In-kind resources provided Outcomes Actual to date Planned Jobs connected to the intervention 1,000 0 Commercial floorspace constructed (square metres) 14,000 0 Housing unit starts 300 0 Housing units completed 300 0 Number of new homes with new or improved fibre optic provision 100% 0

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.03 Newbury: London Road Industrial Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 400 metres (one lane) 400 metres (one lane) Total length of newly built roads 400 metres (one lane) plus 70 metres (2 400 metres (one lane) plus 70 metres (2 Total length of new cycle ways390 metres 390 metres Total length of new footways 390 metres 390 metres Type of infrastructure New signalised junction Type of service improvement New access link and associated highway improvements in central town location. Outcomes Follow on investment at site Exact amount not yet known but development partner, St Modwen will be investing significantly Commercial floorspace occupied 14,000 m2 Commercial rental values Not yet known

7. Further Information for Summary Reports This scheme will unlock a 10-hectare town centre industrial estate for redevelopment and employment intensification. The scheme went on site in February 2016 and is now complete. The first Growth Deal payment was made in March 2016 and the final Growth Deal payment was made in March 2017. This is the original scheme set out in Growth Deal 1. The 1-Year Evaluation Report has been completed.

Page 29 Meeting Date: 14 March 2019 2.04.4 Wokingham – Arborfield Cross Relief Road

Highlights since last report

DfT are currently assessing the draft Business Case sections and liaising with officers prior to submission of the final version.

1 The Scheme 1.1 The Arborfield Cross Relief Road will provide relief to the existing A327 through the Village of Arborfield and also Arborfield Cross Gyratory to accommodate and reduce the traffic impacts of strategic development at Arborfield Garrison and South of the M4 (Shinfield and Spencer’s Wood). The Arborfield SDL calls for 3,500 new homes.

2 Progress with the scheme 2.1 The preferred line of the scheme was approved by Executive in March 2015 and outline design and field surveys are progressing to support submission of a Planning Application. Full planning permission for the scheme was granted on 10 January 2018. Work is ongoing to complete a business case submission to DfT in early 2019, with the methodology approach confirmed at the DfT meeting in mid-June.

2.2 Negotiations finalised with title owners for voluntary acquisition of land and property on the route of the scheme, WBC now owns one piece of land and agreements have been signed on the other two pieces. Title Owners Farley Farms has submitted a Planning Application for mineral extraction within their estate and has a small impact on the route. However, it is considered that the scheme delivery is not disadvantaged or delayed by the existence of the mineral extraction proposals. 2.3 The detailed design work will be completed by Febuary 2019. Early archaeological enabling surveys have commenced and the discharge of some planning conditions is being sought. 2.4 Work on the business case continues ahead of the early 2019 submission to the DfT. 2.5 DfT now reviewing the Business Case, all sections submitted excluding the Economic case which is due to be submitted in February. 2.6 On site enabling works including compound set-up and archaeological investigations have begun 2.7 Work on the business case continues ahead of early 2019 submission to the DfT

3 Funding 3.1. The following table sets out the funding for the scheme on the basis of our unapproved funding profile. N.B WBC forward funded work, which is being clawed back in 2019/20. Source of funding 2016/17 2017/18 2018/19 2019/20 2020/21 Later years Total Amount from LEP Local Growth Deal - - £874,176 £22,125,824 £1,000,000 - £24,000,000 Local contributions from - Section 106 agreements - Council Capital Programme £544,360 £318,879 £3,481,085 -£3,957,324 £1,658,000 £2,070,000 £4,115,000 - Other sources (private sector) £0 Total Scheme Cost £544,360 £318,879 £4,355,261 £18,168,500 £2,658,000 £2,070,000 £28,115,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Acquisition of necessary land need to develop the scheme All land purchase agreements have been finalised.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-14 Independent Assessment of FBC Nov-15 Feb-19 Financial Approval from LTB Mar-16 Nov-18 Feasibility work Complete Mar-15 Acquisition of statutory powers Planning permission required Jan-18 Detailed design Detailed design needed to complete the scheme Feb-19 Procurement On going Apr-19 Start of construction 2016 May-19 Completion of construction 2019 Jul-20 One year on evaluation 2020 Jul-21 Five years on evaluation 2024 Jul-25

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.04.4 Wokingham – Arborfield Cross Mar-19 Q3 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £28,115,000 £863,239 £0 Funding breakdown Local Growth Deal DfT £24,000,000 s.106 and similar contributions £0 Council Capital Programme £4,115,000 £863,239.00 Other £0 In-kind resources provided £0 Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts 198 (As at 31 March 2018) Housing units completed 171 (As at 31 March 2018) Number of new homes with new or improved fibre optic provision

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.04.4 Wokingham – Arborfield Cross Mar-19 Q3 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads 2.5km Total length of newly built roads 2.5km Total length of new cycle ways 2.5km Type of infrastructure New carriageway Type of service improvement Enabling housing development Outcomes Follow on investment at site Unknown at present. To be assessed 1 and 5 years after scheme opening Commercial floorspace occupied Unknown at present. To be assessed 1 and 5 years after scheme opening Commercial rental values Unknown at present. To be assessed 1 and 5 years after scheme opening

3. ADDITIONAL MONITORING - for specific schemes Transport - to be collected for all projects/programmes involving more than £5m public funding and where these metrics and the collection points are relevant to the Planning Numbers Actual to date Actual for the quarter intervention Average daily traffic and by peak/non-peak periods To be determined by FBC (due end Jan 19) Average AM and PM peak journey time per mile on key routes To be determined by FBC (due end Jan 19) Average AM and PM peak journey time on key routes (journey To be determined by FBC (due end Jan 19) Day-to-day travel time variability To be determined by FBC (due end Jan 19) Average annual CO2 emissions To be determined by FBC (due end Jan 19) Accident rate To be determined by FBC (due end Jan 19) Casualty rate To be determined by FBC (due end Jan 19) Nitrogen Oxide and particulate emissions To be determined by FBC (due end Jan 19) Traffic noise levels at receptor locations To be determined by FBC (due end Jan 19) Annual average daily and peak hour passenger boardings n/a Bus/light rail travel time by peak period n/a Mode share (%) n/a Pedestrians counts on new/existing routes n/a Cycle journeys on new/existing routes n/a Households with access to specific sites by mode within n/a threshold times (#)

7. Further Information for Summary Reports This road is one of 4 new roads supporting the development of up to 10,000 new dwellings, schools, neighbourhood centre, etc across four Strategic Development Locations. This is a retained scheme, and assurance framework matters are being managed by the DfT. Due on-site April 2019. This scheme was identified as one of four in the Wokingham Distributor Roads Programme in Growth Deal 1; the funding allocations with the Distributor Roads Programme have been changed.

Page 30 Meeting Date: 14 March 2019 2.05 Newbury: Sandleford Park

Highlights since last report Work continues to progress well on site. The funding profile has been amended to reflect the split of the funding between the two planned accesses.

1 The Scheme 1.1 The purpose of this scheme is to deliver additional accesses to Sandleford Park, a strategic development site that will deliver up to 1,500 dwellings. This will ensure permeability through the site and better manage the impact on the highway network. There are two main elements: i) a new access from the A339, and ii) new junction arrangements on the A343 and the upgrading of a route to provide a suitable access. The scheme will also unlock land for a new primary school and for new enterprises seeking to build better links between business and education. 1.2 The parties involved in the scheme are: the Council, the developers and their agents, Newbury College. 2 Progress with the scheme 2.1 The scheme received full financial approval from the Berkshire Local Transport Body at its meeting in July 2016. 2.2 Following planning application refusals (in December 2017) of the housing that the LEP scheme is helping to unlock, West Berkshire Council has received new planning applications. Two applications have been submitted and the Council are currently considering these with a decision expected in 2019. The two developers have presented joint plans (where appropriate in relation to master planning) and have produced a Memorandum of Understanding which has been submitted as part of the application documentation. This includes a commitment to a contribution to the A339 element of the LEP scheme which had never been previously confirmed. 2.3 The Council and Newbury College have signed a Development Agreement in relation to the delivery of the new A339 access road and the Primary School. This has enabled the construction contract for the school and first section of the access road to be fully awarded. Work on site is well underway with the first phase seeking to deliver the middle section of the access road and the Primary School by July 2019. This has enabled the LEP to amend the RAG rating for this scheme from red back to green as it is now on track for successful delivery. 2.4 At the request of Newbury College a further planning application was submitted for the new A339 access and link road which now includes bunds alongside the road. This is in order to protect the security of the wider Newbury College site which could otherwise become vulnerable. The Planning Committee resolved to grant planning permission at their meeting on 14 March 2018. 2.5 Work is progressing well on site. The contractors for the first phase of works will now also construct the second phase of the new access road which will see the road extended to the boundary of the strategic housing site. This enables them to continue on site and provides good value for money for the delivery of this phase of the scheme. 2.6 The total funding received from the Local Growth Deal for this project will be split proportionately between the two accesses to which it is contributing. The more expensive access to deliver will receive £2m (access from the A339) and the access from the A343 and Warren Road will receive a contribution of £0.9m. The A339 accesss is currently being delivered but the details of the other access are not yet confirmed and planning permission is yet to be achieved. Therefore there remains a risk over the delivery of the A343 and Warren Road access. The funding profile has therefore been amended to reflect this situation with £2m being drawn down in 2018/19 and the remainder in 2019/20 once the details of the second access have been secured. 2.7 Work continues to progress well on site. The funding profile has been amended to reflect the split of the funding between the two planned accesses.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,000,000 £900,000 £2,900,000 Local contributions from - Developers (private) £6,200,000 £860,000 £7,060,000 - Council Capital Programme £400,000 £400,000 - College land (private) £600,000 £600,000 Total Scheme Cost £0 £0 £0 £3,000,000 £7,100,000 £860,000 £10,960,000

4 Risks The key risks on delivering this scheme and how they will be managed are set out in the table below Risk Management of risk There is close liaison with the Developers and their agents and frequent meetings discussing the wide range of topics associated with the overall development. These channels of communication will be used to coordinate timing of accesses and how this links with planning applications and Timing of planning applications for housing and education phases of development. To a certain extent the LEP scheme could be delivered independently or prior to the housing site as it is for enabling development and road delivery not working together. infrastructure. However, there is a more critical link with the school delivery so this will be delivered first and the mechanism to anable this be closely managed.

The access from the A343 and Warren Road does not yet have planning permission and the details of the design and how that works in terms of Details of access from the A343 / Warren the surrounding network is still not decided. Links with the developer and their transport consultants are good and there is regular contact. The Road part of the site remaining uncertain situation will be monitored and it will be made clear to the developer that the funding is time limited.

There are a number of utility companies that have confirmed that equipment will need to be moved / diverted prior to work starting on the final phase of the A339 access road delivery. An allowance has been made in the budget for the scheme. Some companies have already come back with costs Utility Diversions but others are yet to confirm, one of which is Thames Water which it is anticipated will be a high cost. The cost of diversion works and the timing of the work will be closely monitored to ensure that this does not pose a risk to the project budget or delivery timescales.

The costs have been reviewed after more detailed work and additional funding secured from all parties as a result. The project team will continue to monitor costs closely as the project progresses. Escalating costs The legal costs escalated as a result of the drawn out legal negotiations. A cap on these costs was implemented in order that it can be better managed within the overall budget for the project.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Mar-15 Independent Assessment of FBC Jan-16 (provisional) Jun-16 Financial Approval from LTB Mar-16 (provisional) Jul-16 Feasibility work Spring / Summer 2015 (provisional) Acquisition of statutory powers Winter 2015/16 (provisional) Summer 2017 (and further in March 2018) Detailed design Summer 2015 (provisional) Autumn / Winter 2017 / 18 Procurement Autumn / Winter 2015/16 (provisional) Spring 2018 Start of construction April 2017 (provisional) Aug-18 Completion of construction March 2020 (provisional) Autumn 2021 One year on evaluation March 2021 (provisional) Autumn 2022 Five years on evaluation March 2025 (provisional) Autumn 2026

6 Growth Deal Reporting Framework 6.1 The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.05 Newbury: Sandleford Park Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £10,960,000 £660,000 £400,000 Funding breakdown Local Growth Deal £2,900,000 £600,000 £400,000 s.106 and similar contributions £7,660,000 £0 Council Capital Programme £400,000 £60,000 Other In-kind resources provided £100,000 £35,000 Outcomes Actual to date Planned Jobs connected to the intervention 450 Commercial floorspace constructed (square metres) 35,500 Housing unit starts 1,500 Housing units completed 1,500 Number of new homes with new or improved fibre optic provision 100%

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.05 Newbury: Sandleford Park Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 400m Total length of newly built roads 450m Total length of new cycle ways 750m Total length of new footways 850m Type of infrastructure Highway Type of service improvement New highway access routes Outcomes Follow on investment at site Not yet known Commercial floorspace occupied Not yet known Commercial rental values Not yet known

7. Further Information for Summary Reports These access roads unlock up to 1,500 new dwellings, schools, neighbourhood centre, etc. Developer negotiations not yet complete. Due on site in Autumn 2018, completion due Spring 2020. First of two Growth Deal payments due March 2019. The scheme set out in Growth Deal 2 has been revised and the financial contribution increased.

Page 31 Meeting Date: 14 March 2019 2.06 Reading Green Park Railway Station

Highlights since last report

1 The Scheme 1.1. Reading Green Park Station is a proposed new railway station on the Reading to Basingstoke line in south Reading. This scheme, which includes the station, multi-modal interchange and access road, will significantly improve accessibility and connectivity of the existing Green Park business park and surrounding area, and will help to enable delivery of the Green Park Village mixed use development.

2 Progress with the scheme The full business case has been completed and reviewed by DfT Rail and the BLTB independent assessors, confirming the scheme represents good value for money in both a low and high forecast patronage scenario. Financial approval for the 2.1 scheme was granted by the BLTB in November 2014. Planning permission for the station, multi-modal interchange, car park and access road was granted by Reading Borough Council in April 2015 and West Berkshire Council in May 2015. The process of discharging planning conditions for the 2.2 station and interchange is on-going with both Reading and West Berks planning authorities. A new planning application has been submitted to Wokingham and West Berkshire due to the platforms moving south outside the original red line 2.3 Detailed design work for the station and building is being progressed in partnership with Network Rail and GWR to ensure compliance with the latest railway standards. 2.4 Design work for the interchange is complete, which has been modified to improve accessibility, passenger safety and security. 2.5 Enabling works for the interchange construction commenced on-site in March 2018. Construction of the station is due to start in he winter. Balfour Beatty has been appointed by the Council for the construction contract.

2.6 The DfT announced that £2.3m had been awarded for the station from the New Stations Fund 2 and a revised programme has been agreed with the DfT given the enhanced scope for the station. 2.7 Electrification of the line from Southcote Junction to Basingstoke was delayed from December 2018 to an unspecified date between 2019 – 2024 as part of the Hendy Review, however the DfT has confirmed that a third diesel unit for the line between Reading and Basingstoke will be funded from December 2018 to enable the new station to be served. 2.8 Discussions are on-going to identify any opportunities to align implementation of the station with other major upgrade works on the railway. An Interdisciplinary Design Review (IDR) meeting was held in April 2017 to brief all relevant parts of the Network Rail organisation on the detailed plans for Green Park station and interchange so they are fully aware of the impact of the station on other schemes and vice versa. 2.9 Liaison with nearby landowners is on-going to ensure coordination with the wider development plans for the area, including the mixed-use Green Park Village development. 2.10 Scheme development is being undertaken in line with Network Rail’s GRIP process and to take account of the latest developments from related projects such as Reading Station Redevelopment, Great Western Mainline Electrification, Electric Spine, East-West Rail and Western Rail Access to Heathrow (WRATH). 2.11 Engagement with Green Park and Madejski Stadium has been initiated and operational discussions will follow at the appropriate time to ensure maximum accessibility for the station and connectivity with other public transport services.

2.12 Enabling works for the interchange construction commenced on-site in March 2018. Construction of the station is due to start in the spring. 2.13 Detailed design work for the station and building is being progressed in partnership with Network Rail and GWR. Form 1 designs for the station building have been approved in principle and design work for the interchange is complete.

2.14 The process of discharging planning conditions for the station and interchange is on-going with both Reading and West Berks planning authorities. A new planning application has been submitted to Wokingham and West Berkshire due to the platforms moving south outside the original red line boundary, with a decision due in February. 2.15 In principle agreement has been reached with the Environment Agency regarding flood compensation measures as part of the revised planning application. Wokingham and West Berkshire Councils are therefore expected to make a decision on the planning application in April following a formal response by the Environment Agency. 2.16 The outcome of the planning application submitted to Wokingham and West Berkshire is expected in April 2019.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £4,575,000 £4,575,000 £9,150,000 Local contributions from - Section 106 agreements £2,300,000 £2,300,000 £4,600,000 - Council Capital Programme - Other sources (Prupim undergrounding) £1,000,000 £1,000,000 -Other sources New Stations Fund 2 £2,300,000 £2,300,000 Total Scheme Cost £0 £1,000,000 £4,575,000 £6,875,000 £4,600,000 £0 £17,050,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Historic planning application has been updated to reflect the latest situation. Planning permission has been granted by both Reading and West Berkshire Planning permission is not granted. Councils. Amended planning permission required from Wokingham and West Berkshire and a decision is expected in April. Planning conditions are not discharged ahead of development Talks are underway with Reading, West Berks and Wokingham to discharge planning conditions ahead of development. Timetable capability assessment has been undertaken with Network Rail which confirms service options for the station which have been included in the scheme It is not feasible to stop trains at the new station within the existing timetable. business case. TOC does not agree to stop trains at the new station. Scheme development is being undertaken in partnership with GWR, including preparation of the business case and design of the station. Scheme costs significantly increase. Costs are being reviewed and cost savings sought, contingency has been built into the overall scheme cost.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-13 Feasibility work Mar-14 Independent Assessment of FBC Oct-14 Financial Approval from LTB Nov-14 Acquisition of statutory powers Jan-15 May-15 Design (GRIP 1-3) Apr-15 Dec-17 Procurement Sep-15 Jan-18 Start of construction – interchange Oct-15 Mar-18 Design (GRIP 4-5) Oct-15 May-19 Start of construction – station Oct-15 Aug-19 Completion of construction Sep-16 Jun-20 Open to public Dec-16 Aug-20 One year on evaluation Sep-17 Aug-21 Five years on evaluation Sep-21 Aug-26

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.06 Reading Green Park Railway Station Mar-19 Q4 18/19 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £17,050,000 £1,870,093 Funding breakdown Local Growth Deal £9,150,000 £1,870,093 s.106 and similar contributions £4,600,000 Council Capital Programme Other (PRUPIM) £1,000,000 Other (New Stations Fund 2) £2,300,000 In-kind resources provided £635,000 Outcomes Planned Jobs connected to the intervention 3,580 Commercial floorspace constructed (square metres) 68,000 Housing unit starts 735 Housing units completed 735 Number of new homes with new or improved fibre optic provision TBC

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.06 Reading Green Park Railway Station Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads 230m n/a n/a Total length of newly built roads 250m n/a n/a Total length of new cycle ways 310m n/a n/a Type of infrastructure Rail/public transport Interchange Type of service improvement Decongestion Benefits, Journey Time Savings Reliability Journey Ambience Outcomes Follow on investment at site Development of GPV & GP Business Park Commercial floorspace occupied N/A Commercial rental values N/A

3. ADDITIONAL MONITORING - for specific schemes Transport - to be collected for all projects/programmes involving more than £5m public funding and where these metrics and the collection Planning Numbers Actual to date Actual for the quarter points are relevant to the intervention 4,109 High Growth; 2,143 Low Growth; Annual average daily and peak hour passenger boardings 668 AM Peak; 596 PM Peak

Bus/light rail travel time by peak period N/A Mode share (%) 8% for rail Pedestrians counts on new/existing routes New access – no existing count Cycle journeys on new/existing routes New access – no existing count

Households with access to specific sites by mode within threshold times (#) N/A 7. Further Information for Summary Reports The scheme will develop a new category C railway station on the Reading – Basingstoke line. It started on site in March 2018, with completion due winter 2019. First of two Growth Deal payments was made in March 2018. The scheme set out in Growth Deal 1 has been revised and enlarged with additional funding from the Growth Deal and from the New Stations Fund.

Page 32 Meeting Date: 14 March 2019

2.07 Bracknell: Coral Reef Roundabout

Highlights since last report

1 The Scheme 1.1. The Coral Reef roundabout is the first junction encountered as you enter Bracknell on the A322 heading from M3 J3 towards the A329, the A329(M) and the M4. Proposals are to convert the existing roundabout to a fully signalised crossroads that reduces delay on all arms and improves journey times along the route. These measures will improve access to existing employment areas and new developments, unlocking their economic potential and also assist in reducing carbon emissions. Benefits would also be felt by neighbouring LEP areas and assist in the overall control and co-ordination of the strategic corridor network within the Borough 2 Progress with the scheme 1) Junction complete and working well 2) 12 month evaluation report completed in Autumn 2017

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,100,000 £2,100,000 Local contributions from £0 - Section 106 agreements £270,000 £270,000 - Council Capital Programme £640,000 £640,000 - Other sources £0 Total Scheme Cost £2,100,000 £910,000 £0 £0 £0 £0 £3,010,000

4 Risks 4.1.The scheme is complete

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-13 Independent Assessment of FBC Jun-14 Complete Financial Approval from LTB Jul-14 Jan-15 Feasibility work Complete Complete Acquisition of statutory powers None required Detailed design Oct-14 Complete Feb 2015 Procurement Term contractor Complete Start of construction Jun-15 Apr-15 Completion of construction Nov-16 Apr-16 One year on evaluation Nov-17 Five years on evaluation Nov-21 Apr-21

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.07 Bracknell: Coral Reef Roundabout Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £3,010,000 £3,010,000 £0 Funding breakdown Local Growth Deal £2,100,000 £2,100,000 s.106 and similar contributions £270,000 £270,000 Council Capital Programme £640,000 £640,000 Other In-kind resources provided £100,000 Outcomes Actual to date Planned Jobs connected to the intervention0 0 Commercial floorspace constructed (square metres)0 0 Housing unit starts 0 0 Housing units completed 0 0 Number of new homes with new or improved fibre optic provision0 0

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.07 Bracknell: Coral Reef Roundabout Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads Approximately 2000m of resurfacing following Complete Approximately 100m following removal of the Total length of newly built roads roundabout and realignment of the Complete carriageway. Existing cycleway network runs adjacent to the Total length of new cycle ways N/a junction and is unaffected by the works. Type of infrastructure Replacement of existing roundabout with new signalised junction Improvement to journey times following removal of an existing pinch point on the network. Type of service improvement AM Peak Hour: 4.7% improvement northbound; 22.8% improvement southbound PM Peak: 3.9% improvement northbound; 9.1% improvement southbound Outcomes Follow on investment at site0 0 Commercial floorspace occupied0 0 Commercial rental values 0 0

7. Further Information for Summary Reports The Coral Reef junction has been successfully converted from roundabout to signal controls. It finished ahead of time and on budget in April 2016. One-year-on monitoring report submitted November 2017. All Growth Deal payments made. This is the original scheme set out in Growth Deal 1

Page 33 Meeting Date: 14 March 2019 2.08 Slough: Rapid Transit Phase 1 Highlights since last report

1 The Scheme 1.1 The A4 forms the spine of a 12km strategic public transport corridor that links Maidenhead, Slough and Heathrow and plays an important role in providing surface access to the airport. The western section of the Slough Mass Rapid Transit (SMaRT) project will provide for buses to operate along the service roads fronting Slough Trading Estate. Bus lanes and other priority measures will be provided in the central section between the estate, Slough town centre and eastwards to Junction 5 of the M4.

2 Progress with the scheme 2.1 A comprehensive report was put to the 15th September 2014 meeting of the Council’s Cabinet. The Cabinet agreed to progress the scheme and gave permission to use CPO powers if necessary to assemble land. 2.2 Public consultation has been carried out and was presented to the Cabinet on 19th January 2015. The consultation highlighted some concerns about the design of the scheme and revisions have been made in discussion with stakeholders. Planning permission due imminently for elements of the scheme outside highway boundaries. 2.3 Procurement has proceeded in parallel with schemes 2.10 Slough: A332 Improvements and 2.17 Slough: A355 Route. Tenders have been sought, a contractor has been selected and the construction programme in place to meet the LEP and Local Authority spend profile. 2.4 Civil works co-ordinated with the A355/A332 schemes in order to meet the programme schedule. 2.5 Widening works between Upton Court Road and High Street, Langley and works near trading estate started in mid-October 2016. 2.6 Eastern section complete. Western section - complete. 2.7 Scheme completed – snagging in progress including final updates to traffic signals configurations. 2.8 Service for Trading Estate Commuters has been running since Sept 2018. Service for the public commenced in January 2019. 2.9 One year evaluation report to be submitted to BLTB for March 2020 - as agreed with Bill Hicks

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £3,100,000 £2,500,000 £5,600,000 Local contributions from £0 - Section 106 agreements £600,000 £300,000 £900,000 - Council Capital Programme £700,000 £1,000,000 £900,000 £2,600,000 - Other sources £0 Total Scheme Cost £4,400,000 £3,800,000 £900,000 £0 £0 £0 £9,100,000 4 Risks The scheme is complete 5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-13 Jul-13 Independent Assessment of FBC Jun-14 Jun-14 Financial Approval from LTB Jul-14 Jul-14 Feasibility work Complete Acquisition of statutory powers Planning permission and CP Orders required Complete Detailed design Council Cabinet 15th September 2014 agreed subject to outcome of public consultation Complete Procurement Due May 2015 May-15 Start of construction Dec-15 Dec-15 Completion of construction Jun-16 Dec-17 One year on evaluation Jun-17 Mar-20 Five years on evaluation Jun-21 Dec-22 6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.08 Slough: Rapid Transit Phase 1 Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £9,100,000 £9,100,000 Funding breakdown Local Growth Deal £5,600,000 £5,600,000 s.106 and similar contributions £900,000 £900,000 Council Capital Programme £2,600,000 £2,600,000 Other In-kind resources provided £110,000 £110,000 Outcomes Actual to date Planned Jobs connected to the intervention 2,460 Commercial floorspace constructed (square metres) 108,700 Housing unit starts 3,120 Housing units completed 3,120 Number of new homes with new or improved fibre optic provision 3,120

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.08 Slough: Rapid Transit Phase 1 Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads Partial resurfacing of 2000m for bus lane provision 1500m Total length of newly built roads 150m 110m Total length of new cycle ways 2850m (bus lane) 2140m Type of infrastructure Junction improvements, traffic signal enhancement, road widening, bus lanes Type of service improvement Enhanced bus services: greater frequency and reliability, reduced journey times Outcomes Follow on investment at site To be determined Commercial floorspace occupied To be determined Commercial rental values To be determined

3. ADDITIONAL MONITORING - for specific schemes Transport - to be collected for all projects/programmes involving more than £5m 2.08 Slough: Rapid Transit Phase 1 Mar-19 public funding and where these metrics and the collection points are relevant to Planning Numbers Actual to date the intervention Data for 3 sections of A4: • Bath Rd Average daily traffic and by peak/non-peak periods • Wellington Rd • London Rd Average AM and PM peak journey time per mile on key routes (journey time N/A measurement) Data for A4 Bath Rd between Burnham and town centre and for A4 Average AM and PM peak journey time on key routes (journey time measurement) London Rd between town centre and M4 J5

Day-to-day travel time variability Data for bus travel time variations from timetabled services on A4 Bath Rd and A4 London Rd Average annual CO2 emissions Data for Slough-wide emissions from traffic on ‘A’ roads Accident rate Data for rates along A4 Casualty rate Data for KSI and slights along A4 Nitrogen Oxide and particulate emissions Data for Slough AQMAs 3 & 4 Traffic noise levels at receptor locations N/A Data for 'Series 7’ Heathrow bus services: • Boarding's in A4 Bath Rd and A4 London Rd Annual average daily and peak hour passenger boarding's • Boarding's in A4 Bath Rd and A4 London Rd • Boarding's in A4 Bath Rd and A4 London Rd

Bus/light rail travel time by peak period Data for end-to-end and intermediate bus travel times for A4 Bath Rd services Mode share (%) n/a Pedestrians counts on new/existing routes n/a Cycle journeys on new/existing routes Data for journeys along A4 Bath Rd Households with access to specific sites by mode within threshold times (#) Data for households within 45 mins bus journey time of Heathrow

7. Further Information for Summary Reports The Mass Rapid Transit scheme will provide a segregated bus link from M4 Junction 7 to Heathrow Airport. Phase 1 covers a section from the Trading Estate via the station and town centre to M4 Junction 5. Started on site in December 2015, and completed in December 2017. All Growth Deal payments made. This is the original scheme set out in Growth Deal 1.

Page 34 Meeting Date: 14 March 2019 2.09.1 Sustainable Transport NCN 422 Highlights since last report

1 The Scheme 1.1. There have been changes to the scheme as originally set out in the Major Scheme Business Case, as the Royal Borough of Windsor and Maidenhead declined to take any further part in the scheme. However despite this setback the NCN can still largely achieve its original ambitions in joining a number of economic centres across Berkshire as a new National Cycle Route. 1.2. The route will start in Newbury and will follow the A4 to Thatcham and then in a line onto Theale, central Reading, Wokingham and to Bracknell, with the end of the NCN in Ascot. 1.3. It will still be possible to follow a route towards LEGOLAND Windsor as there is an existing route via Ascot and Windsor Great Park. 1.4. However the route through the park is closed at night, the Park Ranger has agreed that cyclists can use it during daylight hours. 2 Progress with the scheme 2.1. A full business case for the route has been approved for funding and although the scheme has slightly altered from its original inception the BCR is not expected to change (the NCN steering group will discuss how best to complete a reassessment of this task). 2.2. Work has been undertaken in Reading, Wokingham, Bracknell and West Berkshire to develop new cycle facilities. 2.3. The works in Reading have included: • Two raised tables have been constructed on Honey End Lane and Southcote Road • Four key junctions have benefitted from crossing improvements and entry treatments, including imprinting across junctions to improve visibility • Approximately 1,500 metres of footway converted to shared-use following reconstruction and widening of footways • Street furniture has been relocated or upgraded to reduce obstructions along the shared-use route and maximise the footway width, including the removal of 100 metres of guard rail • Installation of regulatory signing complimented by official NCN branding and supplementary considerate use signing. • Phase 2 Design work linking Bath Road to London Road via the town centre is now complete and delivery commenced in November 2017, due to finish Q3 2018/19. • Phase 3 route, between Watlington Street/London Road and Three Tuns, is currently being developed and is due to commence Q3 2018/19. 2.4. The works in Bracknell have included: • New 3m – 4m wide shared footway / cycleway alongside The Ring (also known as ‘The Canyon’) with a crossing to newly landscaped ‘Station Green’, using existing crossing outside Bracknell Rail Station, and linking to the existing network at Station roundabout • Delivery of 3 new signalised crossing points • New raised table crossing, adjacent to Station Green and Bracknell Bus Station • Introduction of new permanent cycle counters • Delivery of 350 new cycle parking spaces at the Lexicon shopping centre 2.5. The works in Wokingham have included: • Removal of pedestrian islands in the centre of the A329 which cause pinch points for cyclists • Two new mandatory on-carriageway lanes • Significant kerb realignment • New traffic calming measures on Holt Lane (near Holt School) • Introduction of a new Toucan crossing point • Resurfacing some parts of the carriageway, subject to progress of overall resurfacing contract • The section between Wokingham Town Centre and Coppid Beech has been programmed to be completed by the end of 2018/19. 2.6. In West Berks consultation has been completed on Phase 2 on the West Berks scheme Newbury to Thatcham. 2.7. In Wokingham, the section between Wokingham Town Centre and Coppid Beech has been programmed to be completed by the end of 2018/19. • In Reading the delivery of Phase 2, linking Bath Road to London Road via the town centre, is underway and is expected to be complete in Q3 2018/19. • The design work for Phase 3 of the Reading route, between Watlington Street/London Road and Three Tuns, is expected to be complete September 2018 and works are due to commence on-site in Q3 2018/19. • In West Berks consultation has been completed on Phase 2 on the West Berks scheme Newbury to Thatcham. 2.8. Reading Phase 2: Improved signing through the Oracle is expected to be complete in early 2019, along with on-carriageway cycle facilities on Berkeley Avenue and a contraflow cycle facility on Kennet Side. Reading Phase 3: Spend approval for Final Phase was granted on November 2018 Strategic, Environment, Planning and Transport Committee. - Wokingham Phase 4: Section between Wokingham Town Centre and Coppid Beech due to be completed in Q1 of 2019/20. - West Berks Phase 1: Work ongoing between Newbury and Thatcham due for completion April/May 2019. West Berks Phase 2: Work started in Thatcham. Due to continue in 2019. West Berks Phase 3: Designs currently being reviewed and work to begin Summer 2019.

3 Funding

3.1. There have been some minor changes to funding for the scheme. This has resulted from greater clarity regarding in year budgets as they progress and requirements dictated by the phased delivery programme. 3.2. The two tables below set out the latest funding profile for the scheme based on allocation of LEP funds to NCN partners and the level of local support that can be generated alongside the LEP allocation. West Berks Reading Wokingham Bracknell RBWM Totals 2016/17 0 450,000 800,000 850,000 0 2,100,000 2017/18 500,000 750,000 250,000 0 0 1,500,000 2018/19 200,000 0 0 0 0 200,000 2019/20 400,000 400,000 Total 1,100,000 1,200,000 1,050,000 850,000 0 4,200,000

Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,100,000 £1,500,000 £200,000 £400,000 £4,200,000 - Wokingham Council Capital Section 106 £600,000 £600,000 £400,000 £550,000 £600,000 £2,750,000 - Reading Council Capital Programme £100,000 £100,000 - West Berkshire Capital Programme £50,000 £50,000 £100,000 - Bracknell Forest Capital Programme £50,000 £50,000 £100,000 Total Scheme Cost £600,000 £2,750,000 £2,100,000 £800,000 £1,000,000 £0 £7,250,000 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Booking Road Space The cycleway is being delivered in phases and to a yearly budget allocation, however getting the phases costed, designed, consulted and agreed is problematic as the scheme needs to be able to be delivered on the highway in the time and space available. There are significant other works taking place on the highway in Reading, Wokingham and Bracknell and programme time and space on the highway is congested. This can lead to delays in starting works in time. There are a number of new housing developments being delivered to the West of Wokingham and to the east of Bracknell, where the cycleway passes new planned junctions and altered highways layout Integrating with development There are risks that new planned housing developments with new junctions on the A329 corridor. There are risks that their designs do not reflect the ambition to deliver the cycleway and add significant extra cost to the project. As with any multi-faceted project there are risks of securing all the funding needed for completion of the whole NCN. This project has proven to be flexibly Funding delivered and is bring the large section of the project forward. As portfolio holders at partners change, so does the level of support for cycling. Political support This project has experienced this issue previously with the RBWM political support.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-14 Independent Assessment of FBC Complete Nov-15 Financial Approval from LTB Due July 2015 Nov-15 Feasibility work Sustrans work complete COMPLETE Acquisition of statutory powers Unlikely to be needed N/A Progress is being delivered in stages across a number of years. Design work for 2017/18 stages in progress with works programmed and Detailed design Programmed sections complete in Reading and Bracknell. West Berks works to be complete during 2018/19 and Wokingham have works on going Supported by developer schemes, such as Bellway Homes and The Procurement Term Contractors undertaking works Lexicon redevelopment Start of construction Nov-16 Jan-17 Completion of construction End of 2019 Dec-19 One year on evaluation End of 2020 Dec-20 Five years on evaluation End of 2024 Dec-24

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.09.1 Sustainable Transport NCN 422 Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £7,250,000 £5,450,000 £0 Funding breakdown Local Growth Deal £4,200,000 £3,600,000 s.106 and similar contributions £2,750,000 £1,600,000 Council Capital Programme £300,000 £250,000 Other In-kind resources provided estimated required Outcomes Planned Jobs connected to the intervention 0 Commercial floorspace constructed (square metres) 0 Housing unit starts 0 Housing units completed 0 Number of new homes with new or improved fibre optic provision 0

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.09.1 Sustainable Transport NCN 422 Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads 1.1km 1.1km Total length of newly built roads N/A N/A Total length of new cycle ways 4.9km 4.9km Type of infrastructure Cycleway Type of service improvement Cycling Outcomes Follow on investment at site To be determined Commercial floorspace occupied To be determined Commercial rental values To be determined 7. Further Information for Summary Reports

NCN 422 will form part of the National Cycle Network. The route runs from Theale in West Berkshire through Reading, Wokingham and Bracknell to Ascot. Started on site in January 2017, completion due in 2019. First Growth Deal payment made in March 2017, second in March 2018, with the third due in March 2019. The works within the scheme set out in Growth Deal 1 have been revised; no change to the financial contribution.

Page 35 Meeting Date: 14 March 2019 2.09.2 Sustainable Transport A4 Cycle Route with Bucks

Highlights since last report

1 The Scheme 1.1 This scheme will provide a safe and convenient cycle route between Slough and South Buckinghamshire. It will follow the A4 corridor and will link with a scheme being promoted by Thames Valley Buckinghamshire LEP, which is progressing along similar time-scales. The scheme will connect the two urban areas of Slough and Maidenhead and will give access to: the Bishops Centre Retail Park; Slough Trading Estate; Burnham and Taplow stations; and adjacent residential areas. It will cater for commuting and other utility cycling trips, as well as leisure trips, connecting to National Cycle Network Route 61 via the , and to Cliveden and Burnham Beeches. 2 Progress with the scheme 2.1 Progress with scheme is as follows: - RBWM has decided not to take up this scheme and has returned the funds allocated for the Maidenhead section of the scheme. - Bucks: Thames Bridge to Slough Borough boundary – feasibility study completed and design underway – designs are being revised in response to stakeholder feedback. - Slough: Borough boundary east to Burnham station and Slough Trading Estate – design work completed. The scheme will be coordinated with the delivery of the LSTF-funded cycle link between Slough Trading Estate and Slough town centre. SBC has designed traffic signals for the Huntercombe Lane / A4 junction - toucan crossings are proposed for both arms of the junction to tie in with the A4 Cycle scheme. The Local Access Forum has been consulted and no objections have been received. Consulted with all frontagers in February. Slough is ready to proceed with construction of their element of the scheme. - Traffic signal design work of Huntercombe Lane/A4 has been varied, however has been recently completed. Work is planned to begin in October. 2.2 There have been regular project meetings between SBC and Bucks County Council (BCC) to coordinate the scheme design and to explore opportunities for joint working. 2.3 Further design changes required along the A4 in Slough due to pinch points not being addressed in initial design. 2.4 Junction work now rescheduled for early 2018. Trial holes carried out. 2.5 Delay in construction. Now on course for completion in July 18. 2.6 Work completed September 2018. 3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £483,000 £483,000 Local contributions from £0 - Section 106 agreements £50,000 £50,000 - Council Capital Programme £397,000 £397,000 - Other sources £0 Total Scheme Cost £0 £533,000 £397,000 £0 £0 £0 £930,000 Note: Other sources of funding include £1,542,700 from Thames Valley Bucks LEP and £185,900 from Bucks S106. This is not reported here. 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Utilities alterations greater than expected. Early consultations with Statutory Authorities

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status 24-Jul-14 Data collection Apr-15 Jun-15 Independent Assessment of FBC Due May 2015 Oct-15 Financial Approval from LTB Due July 2015 Nov-15 Feasibility work complete Acquisition of statutory powers Unlikely to be needed Cabinet approve scheme Spring/summer 2015 Jan-16 Detailed design - February – June 2016 Procurement Complete by December 2015 Sep-16 Start of construction Spring 2016 Feb-17 Completion of construction Dec-16 Sep-18 One year on evaluation Dec-17 Sep-19 Five years on evaluation Dec-21 Sep-23

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.09.2 Sustainable Transport A4 Cycle Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £930,000 £950,000 Funding breakdown Local Growth Deal £483,000 £483,000 s.106 and similar contributions £50,000 £90,000 Council Capital Programme £397,000 £377,000 Other £0 In-kind resources provided £50,000 £0 Outcomes Outputs under review - likely to be reported inActual MRT schemeto date Planned Jobs connected to the intervention - Commercial floorspace constructed (square metres) - Housing unit starts - Housing units completed - Number of new homes with new or improved fibre optic provision -

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.09.2 Sustainable Transport A4 Cycle Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 0 0 Total length of newly built roads 0 0 Total length of new cycle ways 2.4km Excl. Bucks section 1.8km Type of infrastructure Shared use footway / cycleway and on-carriageway cycle lanes Type of service improvement New cycle route Outcomes Follow on investment at site 0 Commercial floorspace occupied 0 Commercial rental values 0 7 Further Information for Summary Reports The A4 Cycle scheme is coordinated with works in South Bucks and the arrival of Crossrail services at Taplow (Bucks) and Burnham (Slough) stations. Started on site in February 2017, completion due July 2018. First and only Growth Deal payment was made in March 2017. The scheme set out in Growth Deal 1 has been revised and the financial contribution reduced.

Page 36 Meeting Date: 14 March 2019 2.10 Slough: A332 Improvements Highlights since last report

1 The Scheme 1.1 This project includes a programme of junction improvements, road widening and other works along the A332 on the approach to Slough town centre with the aim of improving conditions for general traffic as well as buses along this strategic route, making journeys quicker and more reliable. 2 Progress with the scheme 2.1 The business case for this scheme was assessed by WYG in October 2014. Financial Approval was given by the BLTB on 20th November 2014. 2.2 Detailed design and public consultation have been completed. Approval was granted by the Cabinet on the 15th December 2014 to proceed to tender and implementation. The Council has worked with other 2.3 Utility works commenced December 2015 and main civil works started January 2017 with completion due September 2017. 2.4 Some civil works were started early in order to utilise downtime at other sites the contractor is working on (Slough Rapid Transit/A355 Improvements). 2.5 Work approaching completion. 2.6 Temporary delay due to additional utility service works. Completion date revised to March 2018. 2.7 Utility services work still to be completed. Anticipated completion date revised to July 2018. 2.8 Temporary delay due to additional utility service works. Completion date revised to November 2018. 2.9 Completion date revised to January 2019. 2.10 Completion date revised to April 2019 due to ongoing problems with utility services

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £1,266,667 £1,433,333 £2,700,000 Local contributions from £0 - Section 106 agreements £250,000 £250,000 - Council Capital Programme £2,050,000 £2,050,000 - Other sources £0 Total Scheme Cost £1,516,667 £1,433,333 £2,050,000 £0 £0 £0 £5,000,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Utilities alterations greater than expected. Early consultations with Statutory Authorities. Changes to design after commencing Fully complete design prior to commencing construction/ allow for contingency provision. construction.

[1] This has been supported by the 27th November 2014 Planning Committee’ s decision to designate the area as a ‘Selected Key Location’ for regeneration in line with Core Policy 1 of the Slough Local Plan.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-14 Jul-14 Independent Assessment of FBC Oct-14 Oct-14 Financial Approval from LTB Nov-14 Nov-14 Feasibility work Completed Acquisition of statutory powers planning permission and CP Orders required Sep-14 Cabinet approve scheme Dec-14 Detailed design Mar-15 Jan-15 Procurement May-15 Sep-15 Start of construction Jun-15 Dec-15 Completion of construction Jun-16 Apr-19 One year on evaluation Jun-17 Apr-20 Five years on evaluation Jun-21 Apr-24

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.10 Slough: A332 Improvements Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £5,000,000 £5,000,000 0 Funding breakdown Local Growth Deal £2,700,000 £2,700,000 s.106 and similar contributions £250,000 £250,000 Council Capital Programme £2,050,000 £2,050,000 Other In-kind resources provided £90,000 Outcomes Actual to date Planned Jobs connected to the intervention 2,150 Commercial floorspace constructed (square metres) 79,150 Housing unit starts 2,995 Housing units completed 2,995 Number of new homes with new or improved fibre optic provision 2,995

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.10 Slough: A332 Improvements Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 500m 375 Total length of newly built roads 500m of additional traffic 375 Total length of new cycle ways 350m 265 Type of infrastructure Junction improvements, road widening, bus lanes Type of service improvement Relieve congestion, reduce journey times, increase journey reliability Outcomes Follow on investment at site Redevelopment for 125 housing units Commercial floorspace occupied To be determined Commercial rental values To be determined

7 Further Information for Summary Reports The scheme includes junction improvements, road widening and other works along the A332 on the approach to Slough town centre with the aim of improving conditions for general traffic as well as buses along this strategic route, making journeys quicker and more reliable. Start on site was December 2015 and it is due to finish in March 2018. All Growth Deal payments made. This is the original scheme set out in Growth Deal 1. Anticipated completion date revised to July 2018 due to extended delay in resolution of utility services work.

Page 37 Meeting Date: 14 March 2019 2.11 Reading: South Reading MRT phase 1 2.12 Reading: South Reading MRT phase 2

Highlights since last report

1 The Scheme 1.1 South Reading Mass Rapid Transit (MRT) Phases 1 and 2 will provide a series of bus priority measures on the A33 between M4 junction 11 and the A33 junction with Longwater Avenue (Green Park) (Phase 1) and Island Road (Phase 2). The scheme will reduce congestion and journey times, improving public transport reliability on the main corridor into Reading.

2 Progress with the scheme 2.1 Outline design and preliminary business case development is complete. The scheme was granted programme entry status by the BLTB in July 2014. 2.2 The business case has been completed and full financial approval for the scheme was granted by the BLTB in November 2015. The business case incorporates comments received previously from WYG regarding the need to update elements of the Reading Transport Model, therefore an updated model of the A33 corridor was used to prepare the business case. 2.3 The economic appraisal for the scheme gives a BCR of 3.55, showing the scheme represents high value for money. Sensitivity tests undertaken with increased scheme costs and high and low patronage forecasts still show a positive BCR of between 2.4 to 4.2. 2.4 Statutory consultation for the scheme has been completed with no objections received to the Traffic Regulation Orders. In addition a public exhibition was held in June 2016 to provide information about this element of the MRT scheme and proposals for future phases. 2.5 Construction works are complete for the majority of the scheme, with outbound sections of bus lane provided between Island Road and M4 junction 11, specifically: •Southbound bus lane between Imperial Way and Basingstoke Road (Dec 2016). •Southbound bus lane between Basingstoke Road and M4 junction 11 (Dec 2016). •Southbound bus lane between Island Road and Bennet Road (Aug 2017). •Southbound bus lane between Bennet Road and Imperial Way (Nov 2017). 2.6 Construction of the final section of bus lane (northbound between Imperial Way and South Oak Way has been delayed until autumn 2018 to be delivered alongside the Phases 3 & 4 scheme. 2.7 Feedback on the scheme has been positive to date and quantitate data regarding bus journey times is being collated to understand the impact of the scheme so far. 2.8 A revised design for phase 2 of the scheme has been prepared due to uncertainties regarding the Southside development site, with an outbound bus lane parallel to the existing carriageway to be constructed as part of the phase 2 works. In addition an inbound bus lane alongside the development site has been included within phases 3 and 4 of the scheme. 2.9 A phased construction programme for the overall MRT scheme has been developed, including measures to reduce disruption to the flow of traffic while the construction works take place, for instance by limiting any necessary lane closures to off peak hours only. 2.10 The potential for cost savings for the scheme continues to be reviewed, both to the overall scheme costs and the level of LGF funding required. 2.11 Construction works are complete for the majority of the scheme, with outbound sections of bus lane provided between Island Road and M4 junction 11.B15 2.12 Construction of the final section of bus lane (northbound between Imperial Way and South Oak Way) will be delivered alongside the Phases 3 & 4 scheme. Completion due May 2019. 2.13 On-site utility works ongoing near Island Road to reallocate utility chamber, expected completion date May 2019.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,970,000 £1,530,000 £4,500,000 Local contributions from - Section 106 agreements - Council Capital Programme £1,120,000 £1,120,000 - Other sources (Prupim undergrounding) -Other sources New Stations Fund 2 Total Scheme Cost £0 £2,970,000 £2,650,000 £0 £0 £0 £5,620,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Scheme is within highway or safeguarded land. The principle of MRT on this corridor has been consulted upon through preparation of policy Objections through the TRO process. documents including the LTP3. Detailed designs for the scheme are being prepared with all the relevant information from utility searches and in line with surface water Utility diversions and surface water drainage alterations. drainage requirements. Securing the required third party land where this falls outside The MRT route has been safeguarded for this purpose and negotiations with land owners are being undertaken. highway land.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Mar-14 Programme Entry Status Jul-14 Independent Assessment of FBC Sep-15 Financial Approval from LTB Nov-15 Acquisition of statutory powers Mar-16 Jun-16 Detail Design Jun-15 Phase 1 - Apr' 16; Phase 2 - Nov' 16 Procurement Jun-16 Phase 1 - Jul' 16; Phase 2 - Mar' 17 Start of construction Aug-16 Phase 1 - Aug' 16; Phase 2 - Apr' 17 Completion of construction Nov-17 May-19 One year on evaluation Nov-18 May-20 Five years on evaluation Nov-22 May-24

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme 2.11 & 2.12 Reading: South Reading MRT Thames Valley Berkshire LEP Mar-19 Q4 18/19 phase 1 & 2 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £5,620,000 £5,018,633 £0 Funding breakdown Local Growth Deal £4,500,000 £4,500,000 s.106 and similar contributions £1,120,000 £518,633 Council Capital Programme Other In-kind resources provided £350,000 Outcomes Planned Jobs connected to the intervention 2,424 Commercial floorspace constructed (square metres) 44,016 Housing unit starts 527 Housing units completed 527 Number of new homes with new or improved fibre optic provision TBC

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.11 & 2.12 Reading: South Reading MRT Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter 1,000m (Phase 1) 210m (Phase 1) Total length of resurfaced roads 390m (Phase 2) 390m (Phase 2) 1,900m (Phase 1) 300m (Phase 1) Total length of newly built roads 1,360m (Phase 2) 500m (Phase 2) 2,000m (Phase 1) 100m (Phase 1) Total length of new cycle ways 200m (Phase 2) 200m (Phase 2) Type of infrastructure Bus Priority Lanes Type of service improvement Reduced & consistent journey times Outcomes Follow on investment at site N/A Commercial floorspace occupied N/A Commercial rental values N/A

7. Further Information for Summary Reports

The South Reading MRT, when complete, will provide segregated bus lanes from Mereoak Park and Ride south of Junction 11 of the M4 to Reading Station. Phases 1 and 2 extend from J11 to Island Road. Started on site July 2016 and due to complete September 2018. First of two Growth Deal payments made March 2017. This is the original scheme set out in Growth Deal 1.

Page 38 Meeting Date: 24 February 2019 2.13 Wokingham: Thames Valley Park, Park and Ride Highlights since last report Work is to commence on site in February 2019

1 The Scheme 1.1 Thames Valley Park and Ride (P&R) is a proposed P&R facility off the A3290 in the east of the Reading urban area. The scheme will improve access to Reading town centre and major employment sites by providing congestion relief on the road network in east Reading. 1.2 The scheme is being jointly promoted by Reading Borough Council (RBC) and Wokingham Borough Council (WBC). 1.3 The scheme was originally called 2.13 Reading: Eastern Park and Ride, but has since been re-named 2.13 Wokingham: Thames Valley Park, Park and Ride

2 Progress with the scheme 2.1 Wokingham BC secured LSTF revenue funding for 2015/16 to progress the scheme to submission of a planning application. Progression of a public consultation, planning application (including an Environmental Statements), has been undertaken in line with the scheme programme. 2.2 Balfour Beatty have been appointed to deliver the contract and will be delivering the scheme as a design and build, which will improve the speed of which the scheme can be delivered. 2.3 BB have appointed the project team including the Project Manager and Commercial Officer. 2.4 Site management works are now complete. 2.5 Progressing with the ecological next steps and the extents of the site has been secured by temporary fencing and signing. 2.6 Topographical survey completed. 2.7 Commencing with the Ground Investigation works. 2.8. Ecology surveys now complete 2.9. Archaoelogy surveys now complete 2.10. Detailed Design ongoing and Planning Variation to be considered at October 2018 Planning Committee. 2.11. Planning variation approved at October 2018 Planning Committee. Detailed Design due to be completed January 2019 with construction due to start before the end of 2018/19 2.12 Work is to commence on site in February 2019 3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,000,000 £900,000 £2,900,000 Local contributions from £0 - Section 106 agreements £250,000 £450,000 £700,000 - Council Capital Programme £0 - Other sources £0 Total Scheme Cost £0 £0 £250,000 £2,450,000 £900,000 £0 £3,600,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk

Subject to planning conditions and consultation process. Initial key survey work has been undertaken and scheme subject to a rigorous site Environmental consents / mitigation option assessment process. Ecology surveys now complete and discussions have commenced with WBC Development Management.

Securing operationally viable bus service Liaison with possible providers including TVP underway, operational principles established. Heads of Terms agreed in principle.

Requirement for Utility Diversion Ongoing discussions with SGN and SSE 5 Programme Task Original TimescaleFeb-19 Timescale (where changed) Programme Entry Status Jul-14 Independent Assessment of FBC Sep-15 October 2016 (submit first draft FBC) Financial Approval from LTB Nov-15 Jul-17 Feasibility work Mar-14 Acquisition of statutory powers Sep-15 Nov-16 Detailed design Sep-15 Oct-18 Procurement Mar-16 Nov-18 Start of construction Apr-16 Clearance work commenced Feb 2018 Completion of construction Sep-17 Summer 2019 One year on evaluation Sep-18 2020 Five years on evaluation Sep-22 2024

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.13 Wokingham: Thames Valley Park, Park Feb-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £3,600,000 £250,000 £0 Funding breakdown Local Growth Deal £2,900,000 s.106 and similar contributions £700,000 £250,000 Council Capital Programme Other In-kind resources provided Outcomes Planned Jobs connected to the intervention 0 Commercial floorspace constructed (square metres) 0 Housing unit starts 0 Housing units completed 0 Number of new homes with new or improved fibre optic provision 0

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.13 Wokingham: Thames Valley Park, Park Feb-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads TBC Total length of newly built roads TBC Total length of new cycle ways TBC Type of infrastructure Highways Type of service improvement Public transport Outcomes Follow on investment at site TBC Commercial floorspace occupied TBC Commercial rental values TBC

7. Further Information for Summary Reports This Park and Ride site will serve Thames Valley Park and the A329(M). It will complement the planned East Reading MRT scheme. Full business case approved in July 2017; started clearance work on site in February 2018 and completion in summer 2019. First of two Growth Deal payments due March 2019. This is the original scheme set out in Growth Deal 1.

Page 39 Meeting Date: 14 March 2019

2.15 Bracknell: Martins Heron

Highlights since last report

1 The Scheme This is part of a wider programme to improve access between the M3 and M4 via the A322, A329 and A329(M). This route runs through the middle of Bracknell and forms part of the original inner ring road. The main capacity constraint is the junctions where radial and orbital routes intersect. This scheme focuses on the Martins Heron roundabout on the east of Bracknell and includes associated junction improvements and minor alteration to the London Road corridor to improve congestion and journey times. The original intention had been to fund a major part of the improvements from developer contributions arising from Bracknell Town Centre redevelopment but this is no longer possible on viability grounds. 2 Progress with the scheme 1) Traffic lights commisoned on 31st January and junction working well. 2) Final stage of scheme including landscaping to comence in the coming months

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £200,000 £2,700,000 £2,900,000 Local contributions from £0 - Section 106 agreements £100,000 £100,000 £250,000 £450,000 - Council Capital Programme £100,000 £350,000 £450,000 - Other sources £0 Total Scheme Cost £0 £300,000 £2,900,000 £600,000 £0 £0 £3,800,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk That the overall cost of the Martins Heron Junction exceeds the Detailed Bill of Quantities with effective site and contract management funding available Statutory undertakers C4 cost estimates significantly exceed C3 cost Early liaison with statutory undertakers and early commission of C4 estimates (underway) estimates Highway Works in neighbouring local authority area during construction leading to traffic congestion and possible impact on Liaison with neighbouring authorities and agreement re. programme programme and costs Unexpected need for additional Temporary Traffic Management Liaison with Traffic Management Section and early quantification of TM requirements and costs (underway) increasing costs

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-14 Independent Assessment of FBC Apr-16 Nov 2016 (conditional) Financial Approval from LTB Nov-16 Jan-17 Feasibility work Apr-16 Acquisition of statutory powers N/a Detailed design Oct-16 Procurement Term contractor Start of construction Jun-17 Apr-17 Completion of construction Nov-18 Spring 19 One year on evaluation Nov-19 Mar-20 Five years on evaluation Nov-23 Mar-23

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.15 Bracknell: Martins Heron Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £3,800,000 £3,650,000 £0 Funding breakdown Local Growth Deal £2,900,000 £2,900,000 s.106 and similar contributions £450,000 £450,000 Council Capital Programme £450,000 £300,000 Other In-kind resources provided Surveys and turning counts £10,000 Outcomes Actual to date Planned Jobs connected to the intervention 0 Commercial floorspace constructed (square metres) 0 Housing unit starts 0 Housing units completed 0 Number of new homes with new or improved fibre optic provision 0

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.15 Bracknell: Martins Heron Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads Approximately 750m – 1000m 330m Total length of newly built roads Approximately 100m where the existing Phase 5 & 6 underway Total length of new cycle ways Shared facilities already run along London Rd. Phase 3 and 4 complete Type of infrastructure Replacement of existing roundabout with signalised junction Type of service improvement Improvement to journey times following removal of an existing pinch point on the network. Outcomes Follow on investment at site Not applicable Commercial floorspace occupied Not applicable Commercial rental values Not applicable 7. Further Information for Summary Reports The Martins Heron Junction is being converted from roundabout to signal controls. The start on site was achieved in March 2017 and completion is due in November 2018. The second and final Growth Deal payment was made in March 2018. This is a repackaged scheme: the original Growth Deal 1 scheme was enlarged and additional funding approved in July 2016.

Page 40 Meeting Date: 14 March 2019 2.14 Reading: East Reading Mass Rapid Transit (MRT) Phase 1 2.25 Reading: East Reading Mass Rapid Transit (MRT) Phase 2

Highlights since last report This scheme has been withdrawn and is therefore not being pursued by the scheme promoters.

1 The Scheme 1.1 East Reading Mass Rapid Transit (MRT) Phases 1 and 2 is a proposed public transport, walking and cycling link between central Reading town centre and the proposed Thames Valley Park P&R site to the east of the Reading urban area, running parallel to the Great Western mainline. 1.2 The scheme is being promoted by Reading Borough Council (RBC) in partnership with Wokingham Borough Council (WBC).

2 Progress with the scheme 2.1 Feasibility work and outline design is complete. Phase 1 of the scheme was granted programme entry status by the BLTB in July 2014, followed by phase 2 in March 2017. 2.2 The business case has been approved and full financial approved was granted for the scheme by the BLTB in November 2017. As part of the independent validation of this process it was identified that the Reading Transport Model should be updated, which resulted in a significant delay to the original programme for the scheme. 2.3 A planning application was submitted to both Reading and Wokingham Planning Authorities in July 2017, following pre-application discussions. Significant work was subsequently undertaken post-submission in order to mitigate the environmental, flooding, landscaping and visual impact aspects of the scheme, resulting in no objections being raised to the application from statutory consultees. 2.4 The scheme revisions were consolidated into an updated planning application for the scheme which was formally submitted in May 2018. Reading’s Planning Application’s Committee resolved to grant permission for this application on 30th May, however Wokingham’s Planning Committee refused permission for the application on 25th June. 2.5 New planning applications were submitted to Reading and Wokingham Councils to address concerns raised by Wokingham’s Planning Committee, including a new EIA (Environmental Impact Assessment) scoping opinion agreed with both planning authorities. A decision on the planning applications is expected early 2019. 2.6 The scheme programme, risk register and funding profile have been updated to reflect the implications resulting from the significant planning delays associated with the scheme. 2.7 Negotiations are on-going with third party landowners in order to acquire the land required for the scheme. 2.8 The scheme is being developed to ensure compatibility with other schemes contained within the TVB Strategic Economic Plan (SEP), particularly the Thames Valley Park P&R scheme. 2.9 Following Wokingham’s Planning Committee refusal in June, a further public exhibition was undertaken in September on options to enhance the visual aspects of the proposal to feed into the new planning application.

3.0 A new planning application was submitted in October and a decision is anticipated in early 2019. The scheme programme and funding profile have been amended accordingly. 3.1 Wokingham's Planning Committee refused to grant East Reading MRT planning permission in December for a second time, following the submission of the new application in October. This is scheme is now unable to be delivered in line with the LGF funding requirements therefore it has been agreed that the funding will be reallocated to new schemes by the BLTB. This scheme remains a vital element to enable both Wokingham and Reading's planned growth therefore the two authorities are currently considering next steps for the scheme.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal Local contributions from - Section 106 agreements - Council Capital Programme - Other Total Scheme Cost £0 £0 £0 £0 £0 £0 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Environmental consents / mitigation A rigorous site option assessment process has been undertaken and significant mitigation measures proposed as part of the scheme. Planning permission is not granted / objections through the planning process A new planning application is being prepared to address the concerns raised by Wokingham’s Planning Committee. A Public Inquiry is called by the Planning Inspectorate Robust scheme development and planning application documentation has been prepared. Land availability Land constraints have been identified, elements of land are within local authority ownership and negotiations are on-going with third party landowners.

Scheme costs increase significantly Costs are being reviewed and cost savings sought due to the significant cost increases associated with delays and increased scope of the scheme.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Jul-13 Programme Entry Status Mar-14 Independent Assessment of FBC Sep-15 Sep-17 Financial Approval from LTB Nov-15 Nov-17 Acquisition of statutory powers Procurement (Design & build contract) Legal Processes (River Crossing Order and Land Appropriation) Land Acquisitions/CPO Detailed design Start of construction (including enabling works and utility diversions) Completion of construction One year on evaluation Five years on evaluation

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme 2.14 & 2.25 Reading: East Reading Mass Rapid Thames Valley Berkshire LEP Mar-19 Q4 18/19 Transit (MRT) Phase 1 & 2 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure Funding breakdown Local Growth Deal s.106 and similar contributions Council Capital Programme Other In-kind resources provided Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts Housing units completed Number of new homes with new or improved fibre optic provision

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.14 & 2.25 Reading: East Reading Mass Rapid Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads N/A Total length of newly built roads Total length of new cycle ways Type of infrastructure Dedicated public transport link Type of service improvement Decongestion Benefits, Journey Time Savings; Reliability; Journey Ambience Outcomes Follow on investment at site Commercial floorspace occupied Commercial rental values

7. Further Information for Summary Reports When complete, the East Reading MRT scheme will create a segregated bus, cycle and pedestrian route between Reading Station and Thames Valley Park and the proposed Park and Ride site. The full business case was approved in November 2017, and the scheme is due on site in March 2020, with completion in April 2023. The first of two Growth Deal payments is due in March 2020. Phase 1 is the original scheme set out in Growth Deal 1; Phase 2 is the original scheme set out in Growth Deal 3.

Page 41 Meeting Date: 14-Mar-19 2.16 Maidenhead: Station Access

Highlights since last report

- Exploratory works commenced on site 28 January, with trial holes at the Broadway / Frascati Way junction preceding changes to the junction layout. Construction works commenced at this junction, programmed for completion by the end of April. - RBWM met with on 13 February to discuss future parking arrangements for the station. - A public engagement event was held on 1-2 March covering all of the town centre regeneration developments and major transport schemes, including Maidenhead Station. - Weekly newsletters are being produced to keep internal and external stakeholders informed as to the timing and likely impact of current and future phases of the scheme. - A site office has been set up in an empty retail unit in King Street. Members of the public are encouraged to drop in to ask questions about the scheme. The information from the public exhibition will also be on display here. - Still on programme to meet delivery timescales with completion by end of March 2020.

1 The Scheme 1.1. The scheme has four elements: i) Construction of a multi-modal transport interchange on Maidenhead Station forecourt to prioritise journeys made on foot, bicycle and by bus; ii) Improved pedestrian and cycle linkages between the rail station and the town centre, with environmental enhancements that will create a proper gateway to the town centre; iii) Re-provision of long stay parking in Stafferton Way; and iv) Traffic management improvements, banning the right turn on Queen Street and converting Broadway to two-way. 2 Progress with the scheme 2.1. Maidenhead Railway Station is a major gateway into the town centre with over 4.5 million people passing through it each year, putting it in the top 50 UK stations outside London, and significantly higher if interchanges are taken into account. 2.2. With the upgrades on the Great Western Main Line, including electrification, new rolling stock and implementation of the Elizabeth Line (Crossrail), passenger footfall and the importance of Maidenhead station will increase. 2.3. Maidenhead Town Centre Area Action Plan (AAP) has identified the station and surrounding area as an Opportunity Site for development. Access to the station by non-car modes is currently poor. Buses call at a number of different stops scattered over a wide area. In a recent passenger survey, access by bus was the second most identified area for improvement. 2.4. The station forecourt is congested with parked cars, taxis and vehicles involved in dropping off / picking up passengers. Walking and cycling routes to the station are narrow and congested and cycle parking facilities operating above capacity. 2.5. In 2013, a provisional scheme was developed jointly with Crossrail incorporating a transport interchange at Maidenhead Station to improve connections between rail and other forms of transport and an all-movements, scramble crossing between the station and the town centre, similar to that at Oxford Circus in London. Vehicles would largely be removed from the station forecourt to enable creation of interchange facilities and a high quality public space commensurate with its importance as a gateway to the town centre and western terminus to the Elizabeth Line. Unfortunately, the scheme was ultimately found to be unviable, but it provided a useful starting point. 2.6. The Council appointed consultants to progress designs for a multi-modal interchange at the station. The constrained nature of the station site means that it is not possible to provide all of the required interchange elements within the existing station forecourt and so additional land would be needed for the bus interchange. 2.7. The adjacent landowners declined to enter into a joint venture, which meant that compulsory purchase of all or part of the area to the north of the station would be required in order to deliver the interchange scheme. 2.8. The consultants appraised numerous options and sub-options, including redevelopment of all or part of the site in order to minimise any funding gaps created by the compulsory purchase. However, even the lowest cost option could not be progressed with the funding available. Also, it was found that the bus interchange would potentially limit the potential for the adjacent office buildings to be redeveloped. Therefore, it was decided to develop a scheme minus the bus interchange. 2.9. Also, redesigning the King Street / Queen Street / A308 junction to provide an Oxford Circus style crossing was found to have a negative impact on traffic congestion. 2.10. Further design and junction modelling work was undertaken for four separate options for the crossing, including two surface and two bridge options. These were presented to Cabinet Regeneration Sub-Committee on 5 September 2017. 2.11. A scheme featuring improved surface crossings with a banned right turn out of Queen Street is now being progressed as the preferred option. Additional modelling work has shown that there are significant traffic benefits associated with making Broadway two-way between the Nicholson’s car park and A308 Frascati Way. This has been incorporated into the scheme and works will be coordinated with the replacement of the Nicholson’s Centre Car Park.

2.12. Long-stay parking that is currently on the forecourt is regulated by the Office for Road and Rail and any parking that is lost must be re-provided nearby. 2.13. The council adopted its Parking Strategy in October 2016, which set out the policies and principles that will govern future parking provision in the borough. A draft implementation plan has been developed and contains proposals to provide a range of temporary and permanent parking solutions in Maidenhead town centre. This initially included plans for an additional deck on the Stafferton Way multi-storey car park to accommodate the parking displaced from the station forecourt. However, this was subsequently discounted due to issues with the foundations and difficulties in keeping the car park open during construction. Alternative solutions have since been identified, including the construction of a new multi-storey car park on Vicus Way. 2.14. A meeting was held with rail industry partners on 15 September 2017 to resolve any outstanding issues and agree the forecourt scheme details. Minor amendments have been incorporated into the scheme design as a result. 2.15. The business case was approved at the November 2017 meeting of the Local Transport Body. The original value of the project was estimated at £8 million and the LEP provisionally allocated £6.75 million of Local Growth Deal Funding to the scheme. This was based on the inclusion of a bus interchange within the scope of the project. However, this has now been shown to be unviable and so the cost of the scheme has reduced to £4.5 million of which £3.75 million is funded from Local Growth Deal. 2.16. The feasibility design proposal had been approved and detailed design was completed in December 2018.

2.17. The Project Working Group including representatives from Network Rail and Great Western Railway met on 21 March 2018 to review the Business Case and to confirm the outline plans. It was confirmed that several agreements are needed in order for the scheme to be progressed. 2.18. RBWM has signed a Basic Service Agreement allowing Network Rail to engage on the project. A Basic Asset Protection Agreement (BAPA) that defines the scope of the works and programme for delivery has also been signed. The design programme is integrated into the Network Rail process and Network Rail has assigned a Project Manger to co-ordinate the works. 2.19. Network Rail has confirmed that there will be a redesign of the station building as part of the Crossrail / Elizabeth Line works. This is currently going through the station GRIP process (and is at GRIP 4). A meeting has been held with the project team who have confirmed the proposed layout at the station forecourt and southern entrance. The station will be developed to account for future predicted passenger numbers which will result in an expansion of the main ticket hall and gate lines. The new ticket hall will not extend past the current awning and should not impact on the proposed design for the station forecourt. Further details will be made available once the GRIP process has been completed. The current programme is to deliver the interchange scheme in advance of the Elizabeth Line works. 2.20. In order for RBWM to progress the re-provision of the long-stay parking a Non-Disclosure Agreement has been signed to cover the financial elements. This allows discussions on the legal agreement to commence. At this stage, the form of agreement for the re-provision of parking is open for discussion. This will need to be based on a long-term lease agreement. 2.21. It is proposed that the long-stay parking that will be lost from the station forecourt will be reprovided within the existing Stafferton Way multi-storey car park and a new multi-storey car park is being provided at Vicus Way to accommodate vehicles dusplaced from Stafferton Way as well as increased parking demand associated with town centre regeneration. The planning application for Vicus Way multi-storey car park was approved at Maidenhead Development Control Panel on 16 January.

2.22. Exploratory works commenced on site 28 January, with trial holes at the Broadway / Frascati Way junction preceding changes to the junction layout. Works at this junction should be complete by the end of April. 2.23. RBWM met with Great Western Railway on 13 February to discuss future parking arrangements for the station. 2.24. A public engagement event was held on 1-2 March covering all of the town centre regeneration developments and major transport schemes. Weekly newsletters are being produced to keep internal and external stakeholders informed as to the timing and likely impact of current and future phases of the scheme. A site office has been set up in an empty retail unit in King Street. Members of the public are encouraged to drop in to ask questions about the scheme. The information from the public exhibition will also be on display here. 2.25. Still on programme to meet delivery timescales with completion by end of March 2020. Early contractor involvement has commenced to facilitate this. Programme does not account for any delays based on Crossrail / Elizabeth Line posession of site.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £690,000 £3,060,000 £3,750,000 Local contributions from - Section 106 agreements £125,000 £625,000 £750,000 - Council Capital Programme -Other Total Scheme Cost £0 £0 £125,000 £690,000 £3,685,000 £0 £4,500,000 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Insufficient scheme budget Apply high level of contingencies at outset and ensure BCR includes optimism bias Office of Rail and Road does not give regulatory approval for relocation of forecourt parking Hold early meetings with ORR and secure support of Network Rail / Great Western Railway to Stafferton Way Objections from stakeholders Hold early discussions with key stakeholders (e.g. Network Rail, GWR, bus / taxi operators, cycle forum, access advisory forum) Unable to agree to parking charge reimbursements and provision of temporary spaces Hold early discussions with GWR and ensure support for project at business case stage. Develop detailed plan in conjunction with GWR. Drainage / SUDS requirements for station forecourt Early discussion with NR to identify standards and scheme requirements The tender prices received from the contractors exceed the available budget to construct Cost estimate is based on an outline bill of quantities with appropriate allowances for optimism bias and risk CrossRail station improvements conflict with the scheme and delivery programme Meetings with delivery team to fully understand and integrate the two projects.

Delays in construction programme resulting in increased contract administration costs Ensuring design, investigations, programme and procurement are robust, reducing likelihood of construction delays reduced

Increases in statutory undertakers’ apparatus diversion costs to that assumed at bid stage. Apply legally for C3 notices for cost update.

Long lead times for permanent service diversions Early liaison with utilities companies to ensure stats get diverted before the construction programme begins. Detailed design for the contract tender documents will provide as much detail as possible on the site conditions and methods of construction; so as to avoid questions Changes to design (after construction has commenced). about "buildability".

Unknown services struck during construction works incurring delays to programme Digging of trial holes and CAT scans. Disclosure of buried services information by Network Rail as part of the BAPA process.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status 24-Jul-14 Feasibility / outline design Mar-15 Aug-17 Selection of preferred option Sep-17 Preparation of FBC Oct-17 Independent Assessment of FBC Mar-16 Oct-17 Financial Approval from LTB Jul-16 Nov-17 Car park design Aug-18 Car park planning application submitted Aug-18 Junction design Dec-18 Start of construction - junctions / car park Jan-19 Forecourt design Mar-19 Procurement Mar-17 Apr-19 Start of construction - forecourt Apr-17 Jun-19 Completion of construction Mar-17 Mar-20 One year on evaluation Oct-18 Mar-21 Five years on evaluation Oct-22 Mar-25

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.16 Maidenhead: Station Access Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £4,500,000 £310,000 £0 Funding breakdown Local Growth Deal £3,750,000 £228,000 s.106 and similar contributions £750,000 £82,000 Council Capital Programme £0 Other £0 In-kind resources provided £100,000 £75,000 Outcomes* Planned Jobs connected to the intervention 2,080 Commercial floorspace constructed (square metres) 29,000 Housing unit starts 212 Housing units completed 50 Number of new homes with new or improved fibre optic provision 50 * Figures based on existing outline planning application for The Landing. These are subject to change as a new application will be submitted in 2018. 2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.16 Maidenhead: Station Access Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads 0 Total length of newly built roads 0 Total length of new cycle ways 0 Type of infrastructure Multi-modal transport interchange; 125 space extension to existing multi-storey car park Improved interchange between journeys made on foot, bicycle, bus, train, taxi and car with associated public realm enhancements; improved crossing between the Type of service improvement station and town centre; and Increased car park capacity serving the rail station and town centre. Outcomes Follow on investment at site TBC Commercial floorspace occupied TBC Commercial rental values TBC 7. Further Information for Summary Reports Maidenhead Station will be served by Elizabeth Line services from December 2019, and this scheme is designed to improve the capacity of the forecourt area to cope with the anticipated increase in pedestrian traffic. The scheme is coordinated with capacity improvements inside the station. A start on site is due in January 2019 and completion in March 2020. The first Growth Fund payment is due in March 2019.

Page 42 Meeting Date: 14 March 2019 2.17 Slough: A355 Route

Highlights since last report

1 The Scheme 1.1 This is a scheme to improve traffic flow on the strategic north-south A355 route that links the M4, Slough Trading Estate and the M40 and to enhance access to Slough town centre. The scheme involves the remodelling of the Copthorne roundabout, signal and junction upgrades and selected road widening. 1.2 The A355 Route Enhancement scheme will deliver a major contribution to reducing road congestion and increasing economic efficiency and business confidence. This project will support the delivery of the 150,000m2 of office and ancillary space proposed in the Slough Trading Estate master plan and over 60,000m2 of office space, 2,300 dwellings and other development to be delivered in the town centre as part of the ‘Heart of Slough’ project. 2 Progress with the scheme 2.1 Scheme complete 2.2 Outcomes under review. 2.3 One year on report provided to the July 2018 BLTB meeting. 3. Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,275,000 £2,125,000 £4,400,000 Local contributions from - Section 106 agreements £700,000 £700,000 - Council Capital Programme £700,000 £700,000 - Other sources Total Scheme Cost £3,675,000 £2,125,000 £0 £0 £0 £0 £5,800,000 4 Risks The scheme is complete. [1] This has been supported by the 27th November 2014 Planning Committee’ s decision to designate the area as a ‘Selected Key Location’ for regeneration in line with Core Policy 1 of the Slough Local Plan. 5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-14 Jul-14 Independent Assessment of FBC Oct-14 Oct-14 Financial Approval from LTB Nov-14 Nov-14 Feasibility work Completed Acquisition of statutory powers n/a Completed Detailed design Mar-15 Mar-15 Procurement May-15 May-15 Start of construction Jun-15 Dec-15 Completion of construction Jun-16 Feb-17 One year on evaluation Jun-17 Jul-18 Five years on evaluation Jun-21 Feb-22

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.17 Slough: A355 Route Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £5,800,000 £5,800,000 Funding breakdown Local Growth Deal £4,400,000 £4,400,000 s.106 and similar contributions £700,000 £700,000 Council Capital Programme £700,000 £700,000 Other In-kind resources provided £90,000 £90,000 Outcomes Actual to date Planned Jobs connected to the intervention 1,260 Commercial floorspace constructed (square metres) 48,000 Housing unit starts 600 Housing units completed 600 Number of new homes with new or improved fibre optic provision 600

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.17 Slough: A355 Route Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 550m 550m Total length of newly built roads 500m of additional traffic 500m Total length of new cycle ways Nil Type of infrastructure Signalised roundabout, road widening and bridge improvements Type of service improvement Relieve congestion, reduce journey times, increase journey reliability Outcomes Follow on investment at site To be determined Commercial floorspace occupied To be determined Commercial rental values To be determined 7 Further Information for Summary Reports The scheme improves traffic flow on the strategic north-south A355 route that links the M4 with Slough Trading Estate. The scheme involved the remodelling of the Copthorne roundabout, signal and junction upgrades and selected road widening. The start on site was in December 2015 and completion was achieved in February 2017. All Growth Deal payments made. This is the original scheme set out in Growth Deal 1.

Page 43 Meeting Date: 14 March 2019

2.19 Bracknell Town Centre Regeneration

Highlights since last report

1 The Scheme The scheme has funded transport infrastructure improvements linked to the town centre regeneration.

2 Progress with the scheme 2.1. The scheme is complete and the Lexicon Centre opened for business on 7 Sept 2017. It is one of the biggest town centre regenerations in the UK. In addition to 70 new shops and restaurants, the project also encompasses improvements to the existing High Street buildings and a new 1,300 space multi-storey car park. 2.2. 12 months after opening and the early figures show a positive story with more shops coming on line and further phases of development to begin shortly. Officers are now gathering data collected over the past 12 months to prepare the first year evaluation report for the March 2019 LTB meeting.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,000,000 £2,000,000 Local contributions from £0 - Section 106 agreements £0 - Council Capital Programme £1,000,000 £3,382,000 £4,382,000 - Other sources £0 Total Scheme Cost £3,000,000 £3,382,000 £0 £0 £0 £0 £6,382,000

4 Risks The scheme is complete

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Mar-15 Independent Assessment of FBC Oct-15 Financial Approval from LTB Nov-15 Feasibility work Nov-14 Acquisition of statutory powers Not needed Detailed design Mar-15 Procurement Developer s278 agreement Start of construction Apr-15 Completion of construction Apr-17 Sep-17 One year on evaluation Apr-18 Mar-19 Five years on evaluation Apr-22 Sep-22

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.19 Bracknell Town Centre Regeneration Mar-19 Q3 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £6,382,000 £6,382,000 Funding breakdown Local Growth Deal £2,000,000 £2,000,000 s.106 and similar contributions Council Capital Programme £4,382,000 £4,382,000 Other In-kind resources provided Outcomes Actual to date Planned Jobs connected to the intervention 3,540 3,500 Commercial floorspace constructed (square metres) 270,000 270,000 Housing unit starts 1,000 892 Housing units completed 1,000 287 Number of new homes with new or improved fibre optic provision 1000 287

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.19 Bracknell Town Centre Regeneration Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 3000m of resurfaced road Complete Total length of newly built roads 50m of newly built road. Complete Total length of new cycle ways 700m of new cycleways adjacent to link road. Complete Type of infrastructure Improved accessibility to new development Type of service improvement Unlocking proposed development. Outcomes Follow on investment at site Work underway to determine value Commercial floorspace occupied Work underway to determine figures Commercial rental values Work underway to determine value

7. Further Information for Summary Reports

This project has funded several necessary junction modifications and other works associated with the major redevelopment of Bracknell Town Centre. The scheme is complete and the Lexicon Centre opened in September 2017. All Growth Deal payments made. This is the original scheme set out in Growth Deal 2

Page 44 Meeting Date: 14 March 2019 2.21 Slough: Langley Station Access Improvements

Highlights since last report

1 The Scheme

1.1. This is a scheme to improve station facilities at Langley and enhance access to the station from the surrounding area. Activities will include new station buildings, lifts and enhancements to the station entrances and parking. Improvements will be made to pedestrian, cycling, and bus facilities. Better information and signage will be provided and measures to enhance the safety and security of the station. 1.2. The scheme is aimed at preparing the station for the enhanced travel opportunities that will arise when Crossrail services begin in 2019. Some short-term works are being undertaken at Langley as part of Network Rail’s electrification programme and further investment has been committed by the DfT towards improving accessibility. Rail for London is planning station enhancements in connection with the Crossrail programme and First Great Western retains an interest in station infrastructure improvements as incumbent train operating company. 1.3. This scheme will add value to these rail industry plans by upgrading access to the station from the surrounding area.

2 Progress with the scheme 2.1. Discussions are being held between the Council and its rail partners to coordinate project planning and design work with the aim of delivering the scheme to build on and take advantage of rail investment commitments. Detailed proposals are being drawn up by both parties taking account of other rail proposals in the Langley area: the Western Rail Link to Heathrow scheme and potential relocation of the Heathrow Express depot. Public consultation will follow. 2.2. Work commenced on site in March 2018 with trial holes. Ongoing work programme requires further coordination with Network Rail and MRT. 2.3. Expected completion date revised to March 2019 2.4. Expected completion date revised to September 2019 due to delays in design work for remaining part of the scheme

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £1,500,000 £1,500,000 Local contributions from £0 - Section 106 agreements £50,000 £50,000 - Council Capital Programme £210,000 £210,000 - Other sources (public - railway) £3,500,000 £3,500,000 Total Scheme Cost £0 £0 £5,260,000 £0 £0 £0 £5,260,000 [1] £1,500,000 coming from Growth Deal 2 announced in January 2015. The bulk of the local contribution will come from rail partners made up of the DfT (funding for accessibility); Network Rail and Rail for London (Crossrail); and First Group (train operating company). The funding for the scheme is set out on the basis of our unapproved funding profile. 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Higher than expected costs Financial and project management. Delays in procurement process Programme allows sufficient time for process. 5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status March 2015 BLTB Independent Assessment of FBC Oct-15 May-16 Financial Approval from LTB Nov-15 Nov-16 Feasibility work Sep-15 Dec-15 Acquisition of statutory powers n/a Cabinet approve scheme Jan-16 Jan-17 Detailed design Summer 2016 Oct-17 Procurement Autumn 2016 Nov-17 Start of construction Jan-17 Mar-18 Completion of construction Mar-18 Sep-19 One year on evaluation Mar-19 Sep-20 Five years on evaluation Mar-23 Sep-24

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.21 Slough: Langley Station Access Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £5,260,000 £750,000 £0 Funding breakdown Local Growth Deal £1,500,000 £750,000 s.106 and similar contributions £50,000 Council Capital Programme £210,000 Other (public - railway) £3,500,000 In-kind resources provided £130,000 Outcomes Actual to date Planned Jobs connected to the intervention 0 Commercial floorspace constructed (square metres) 0 Housing unit starts 500 Housing units completed 500 Number of new homes with new or improved fibre optic provision 500

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.21 Slough: Langley Station Access Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 400 Total length of newly built roads 0 Total length of new cycle ways 400 Type of infrastructure Station enhancements and local highway and public realm improvements Type of service improvement Preparations for Crossrail and better access to station Outcomes Follow on investment at site To be determined Commercial floorspace occupied To be determined Commercial rental values To be determined

7 Further Information for Summary Reports Crossrail Services are due to serve Langley station from December 2019 and this scheme is designed to improve the facilities in anticipation of an increase in pedestrian numbers. The scheme started on site in March 2018 with completion in December 2018. The first and only Growth Deal payment was made in March 2018. This is the original scheme set out in Growth Deal 2.

Page 45 Meeting Date: 14 March 2019 2.22 Slough: Burnham Station Access Improvements

Highlights since last report

1 The Scheme 1.1 This is a scheme to improve station facilities at Burnham and enhance access to the station. Activities will include new station buildings, lifts, enhancements to the station entrances and parking. Highway improvements and traffic management measures will be carried out to achieve better access for pedestrians, cyclists, buses and general traffic. 1.2 The scheme is aimed at preparing the station for Crossrail services, which begin in 2019. Some short-term works have been undertaken at Burnham as part of Network Rail’s electrification programme and further investment is committed towards improving accessibility through the DfT Access for All Fund. Rail for London is planning station enhancements in connection with the Crossrail programme and Great Western retains an interest in station infrastructure improvements as incumbent train operating company. 1.3 This scheme will add value to these rail industry plans by upgrading access to the station from the surrounding area. 2 Progress with the scheme 2.1 Discussions are being held between the Council and its rail partners to coordinate project planning and design work with the aim of delivering the scheme as early as possible to build on and take advantage of rail investment commitments. Detailed proposals are being drawn up by both parties. The Council is carrying out an experimental order on the highway aspects of the scheme this is due to start in October.

2.2 The majority of the work has been completed, including car park, footways and road crossings. 2.3 Forecourt work to be completed. Ongoing coordination with Network Rail’s works. End date revised to October 2018. 2.4 The majority of the work has been completed, including car park, footways and road crossings. 2.5 Station forecourt work 90% completed, final completion date revised to March 2019. Network Rail work set to start in 2019, 1 year impact will follow this completion.

3 Funding 3.1. The following table sets out the funding for the scheme with £2,000,000 coming from the Expanded Growth Deal announced in January 2015. The bulk of the local contribution will come from rail partners made up of DfT (Access for All fund); Network Rail and Rail for London (Crossrail); and First Group (train operating company). Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,000,000 £2,000,000 Local contributions from £0 - Section 106 agreements £0 - Council Capital Programme £100,000 £100,000 - Other sources (public railway) £4,150,000 £4,150,000 Total Scheme Cost £0 £2,000,000 £100,000 £0 £4,150,000 £0 £6,250,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Higher than expected costs. Financial and project management.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status March 2015 BLTB Independent Assessment of FBC Jun-15 Started October 2015 Financial Approval from LTB Jul-15 Mar-16 Feasibility work May-15 Sep-15 Acquisition of statutory powers n/a Cabinet approve scheme Sep-15 Jan-16 Detailed design Autumn 2015 Jul-16 Procurement Autumn 2015 Sep-16 Start of construction Jan-16 Jan-17 Forecourt March 19 Completion of construction Mar-17 NR work TBC One year on evaluation Mar-18 2020 Five years on evaluation Mar-22 2024

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.22 Slough: Burnham Station Access Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £6,250,000 £2,100,000 £0 Funding breakdown Local Growth Deal £2,000,000 £2,000,000 s.106 and similar contributions £100,000 £100,000 Council Capital Programme Other (rail) £4,150,000 To be advised In-kind resources provided Outcomes Actual to date Planned Jobs connected to the intervention 1,050 Commercial floorspace constructed (square metres) 40,000sqm Housing unit starts Housing units completed Number of new homes with new or improved fibre optic provision

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.22 Slough: Burnham Station Access Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 600m Total length of newly built roads Total length of new cycle ways 600m Type of infrastructure Station enhancements and local highway and public realm improvements Type of service improvement Preparations for Crossrail and better access to station Outcomes Follow on investment at site To be determined Commercial floorspace occupied To be determined Commercial rental values To be determined

7 Further Information for Summary Reports Crossrail Services are due to serve Burnham station from December 2019 and this scheme is designed to improve the facilities in anticipation of an increase in pedestrian numbers. The scheme started on site in January 2017 with completion due in June 2018. All Growth Deal payments made. This is the original scheme set out in Growth Deal 2.

Page 46 Meeting Date: 14 March 2019 2.23 Reading: South Reading MRT Phases 3 and 4 Originally an LGF scheme, now jointly funded by Business Rates Retention Pilot Highlights since last report

1 The Scheme 1.1 South Reading Mass Rapid Transit (MRT) Phases 3 and 4 will provide a series of bus priority measures on the A33 between Rose Kiln Lane and Bennett Road, and connecting routes in Reading town centre. The scheme will reduce congestion and journey times, improving public transport reliability on the main corridor into Reading. 2 Progress with the scheme 2.1 Preparation of the full business case for the scheme is complete demonstrating that the scheme represents high value for money in line with central Government guidance. The business case has been approved by the LEP’s independent assessors the scheme was granted financial approval by the BLTB in November 2017. 2.2 Construction of the town centre elements of the scheme are complete, including commissioning of the pedestrian crossing on London Street. 2.3 Construction of Phase 3 A33 works commenced in August and are due to be complete in Spring 2019. 2.4 Detailed design of Phase 3 A33 works and traffic signal upgrades at Oracle Roundabout and A33 Bennet Road gyratory are on-going. 2.5 This work is being progressed in line with the latest land-use development proposals for the A33 corridor. Discussions are on-going with the developer of the Southside site to acquire the third party land needed for the scheme, although a revised scheme is also being developed to avoid third party land if it cannot be acquired. 2.6 A phased construction programme for the full scheme has been developed, including measures to reduce disruption to the flow of traffic while the construction works take place, for instance by limiting any necessary 2.7 Construction of the town centre elements of the scheme are complete, including commissioning of the pedestrian crossing on London Street. 2.8 Construction of Phase 3 A33 works has commenced with detailed design for Phase 4 ongoing. 2.9 Contractor on-site for Phase 3 scheme check when works September 2019. Detailed design being progressed for phase 4 scheme with procurement due to take place in June 2019

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,250,000 £90,000 £2,340,000 Local contributions from - Section 106 agreements £1,268,000 £1,268,000 £2,536,000 - Council Capital Programme - Other BRRP (TVB LEP) £7,808,000 £7,808,000 Total Scheme Cost £0 £0 £2,250,000 £9,166,000 £1,268,000 £0 £12,684,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Scheme is within highway or safeguarded land. The principle of MRT on this corridor has been consulted upon through preparation of policy Objections through the TRO process. documents including the LTP3. Detailed designs for the scheme are being prepared with all the relevant information from utility searches and in line with surface water drainage Utility diversions and surface water drainage alterations. requirements. Securing the required third party land where this falls outside of The MRT route has been safeguarded for this purpose and negotiations with land owners are being undertaken. highway land.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work May-16 Programme Entry Status Mar-17 Independent Assessment of FBC May-17 Sep-17 Financial Approval from LTB Jul-17 Nov-17 Acquisition of statutory powers Sep-17 Mar-18 Detailed design Phase 3 March 2018 - Phase 3 Sep-17 Phase 4 March 2019 - Phase 4 Phase 3 June 2018 Procurement Jan-18 Phase 4 June 2019 Start of construction Mar-18 Completion of construction Mar-20 One year on evaluation Mar-21 Five years on evaluation Mar-25

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme 2.23 Reading: South Reading MRT Phases Thames Valley Berkshire LEP Mar-19 Q4 18/19 3 and 4 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £12,684,000 £3,519,001 £0 Funding breakdown Local Growth Deal £2,340,000 £2,340,000 s.106 and similar contributions £2,536,000 Council Capital Programme BRRP (TVB LEP) £7,808,000 £1,179,001 In-kind resources provided £300,000 Outcomes Planned Jobs connected to the intervention TBC Commercial floorspace constructed (square metres) TBC Housing unit starts TBC Housing units completed TBC Number of new homes with new or improved fibre optic provision TBC

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.23 Reading: South Reading MRT Phases Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter 300m (Phase 3) Total length of resurfaced roads 1050m (Phase 4) 550m (Phase 3) Total length of newly built roads 600m (Phase 4) Total length of new cycle ways N/A Type of infrastructure Bus Priority Lanes Type of service improvement Reduced & consistent journey times Outcomes Follow on investment at site N/A Commercial floorspace occupied N/A Commercial rental values N/A 7. Further Information for Summary Reports The South Reading MRT, when complete, will provide segregated bus lanes from Mereoak Park and Ride south of Junction 11 of the M4 to Reading Station. Phases 3 and 4 extend from Rose Kiln Lane and Bennett Road. Start on site due March 2018 and due to complete March 2020. First of three Growth Deal payments made in March 2018. This is the original scheme set out in Growth Deal 3.

Page 47 Meeting Date: 14 March 2019 2.24 Newbury: Railway Station Improvements

Highlights since last report Hatch Regeneris have confirmed that all conditions have been met. Full financial approval of the scheme for Local Growth Deal funding has therefore been confirmed. Work has started on site for some of the interchange elements on the south side of the station.

1 The Scheme 1.1 This scheme plans to enhance and improve multi-modal transport interchange at Newbury Railway station including upgrade and improvement of station buildings. This will work alongside, and help to deliver, the Market Street housing-led development and also help to deliver the Sandleford Park strategic housing site, through enhanced connectivity for bus passengers, rail passengers, cyclists and pedestrians. The scheme will allow Newbury Railway Station to cope with anticipated increases in passengers with corresponding increases in demand for travel and car parking.

1.2 The scheme is promoted jointly by West Berkshire Council and Great Western Railway. It seeks to deliver 4 to 5 start-up incubator business units within rail land to the south of Newbury Railway Station and 2 new retail outlets on the station (north and south) with an additional 8 to 10 jobs created within these retail outlets. New and enhanced cycle facilities, ticket hall and waiting areas will be created.

1.3 The scheme will deliver a new multi-modal interchange with rail to the south of Newbury Railway Station along with a new multi-storey car park, station forecourt, and pedestrian/cycle link to the town centre to the north of Newbury Railway Station as part of the Market Street redevelopment. 1.4 The proposal will complement the investment being made in delivering electrification of the Berks and Hants line from Newbury to Reading as part of the wider Great Western electrification project.

1.5 Following conditional permission being granted in July 2018, the work to address the conditions has been completed and Hatch Regeneris have confirmed that all conditions have been met. The Capital Grant letter between the LEP and the Council has been signed confirming full financial approval of the scheme for Local Growth Deal funding. 1.6 Work has started on site for some of the interchange elements on the south side of the station.

2 Progress with the scheme 2.1 A feasibility study was conducted by WSP / Parsons Brinckerhoff which was completed in October 2015. It examined the opportunities to provide an improved interchange at Newbury Railway Station and considered various options recommending the one that provides the most effective benefits. 2.2 The scheme gained Programme Entry status following the announcement on Growth Deal 3 and a decision from the Berkshire Local Transport Body in March 2017. 2.3 A Project Team has been set up which consists of representatives from West Berkshire Council and Great Western Railway (both as scheme promoters) and also involves Network Rail. Other organisations are involved in the Project Team as required. 2.4 Flooding in and around Newbury Railway Station is a significant problem. The Project Team is remaining in contact with the group that is looking at the flooding issues. The short-term work that has been identified has been delivered, the medium term proposals have also been delivered and it is looking likely that the identified longer term solutions may not be necessary. Drainage features have been included in the design work for the interchange enhancements on the south side of the station to help contribute to improving the situation on the surrounding highway in relation to the flooding issues.

2.5 The Market Street mixed use (but predominantly housing) development with which this scheme closely links was approved by the Council’s Planning Committee in November 2016. Closer links have been forged with the wider Market Street development and road schemes programme for the A339 corridor in order that the masterplan can be coordinated. There are monthly meetings for the Market Street development which representatives from the Newbury Station Project Team attend. 2.6 The new pedestrian bridge to enable the delivery of electrification of the line is complete and in use in terms of a like for like replacement of the existing. The lifts that are incorporated into the new bridge are anticipated to be operational soon thereby delivering a significant improvement for passengers. 2.7 Detailed design and assessment work for the works to the station buildings has taken place to feed into the final business case. This work has established how the range of improvements required will be delivered and has enabled more detailed costs to be established. This has fed into the final scope of works and costs described and assessed in the business case. The new layout and better use of the buildings will bring about significantly improved facilities for passengers and a more welcoming station providing an improved gateway to Newbury. 2.8 The full business case was considered at the July BLTB meeting and was granted conditional approval. The work to address the conditions set by Regeneris has been completed and final comments from Regeneris are awaited. The business case prepared assesses the scheme to represent high value for money with a Benefit to Cost Ratio (BCR) of 3.8:1 2.9 Work has started on site for some early part of the interchange element and a start on site for the work within the station lease area is planned for May 2019. Further phasing will take into account the linked Market Street redevelopment work and nearby highways works affecting the A339. 2.10 Confirmation has been received that the Network Rail compound will be relocated which provides additional certainty for the delivery of all aspects of the scheme and provides options for the location of the business start up units. 2.11 Following conditional permission being granted in July 2018, the work to address the conditions has been completed and confirmation has been received from Hatch Regeneris that all the conditions have been met. Full financial approval has therefore been granted to the scheme and the grant letter between the LEP and the Council has been signed. 3 Funding The following table sets out the funding for the scheme on the basis of provisional funding allocations and updated in line with the final costs established through the business case work. The profile is yet to be 3.1 confirmed for expenditure for this scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £3,630,000 £921,000 £1,500,000 £6,051,000 Local contributions from £0 GWR (SCPF) - Public £1,890,000 £1,890,000 GWR (DfT Cycle Rail) - Public £450,000 £450,000 Network Rail - Public £2,000,000 £1,900,000 £3,900,000 WBC £20,000 £20,000 £40,000 Market St Devt (Grainger) - Private £4,710,000 £1,400,000 £6,110,000 Total Scheme Cost £0 £0 £2,000,000 £5,550,000 £7,991,000 £2,900,000 £18,441,000

4 Risks 4.1 The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below: Risk Management of risk Network Rail and GWR are close to finalising a Funding Agreement to secure vacant possession of the MDU site. Delay / inability to secure Network Rail maintenance depot The maintenance depot area is proposed for car parking, subject to relocation of the access to this area and acceptance of reduced parking, relocation. it would be possible to implement the remainder of the scheme without this area. Network Rail is already progressing a maintenance depot rationalisation investigation for this area.

Planning permission is required for two small elements of the scheme - the business start up units and a retaining wall on the south side of the station as part of the highway works. All other works are permitted development or require a notification process. Initial discussions Obtaining statutory powers have taken place with the Principal Conservation & Design Officer at the Council and advice has been taken on board in terms of sympathetic design etc. A pre-application process is likely to be followed also in order to help make the passage through planning as smooth as possible. The current design drawn up by WSP closely aligns to the current demand for bus services with relatively little spare capacity. Any reduction Changes to funding for bus services in bus services would simply provide more tolerance for changes in bus timings, alternative services etc.

The bus interchange at The Wharf has been delivered (Nov 2018) leaving the site vacant for the Market Street development. Planning permission is in place for the mixed use development and significant work on site is due to start in Spring 2019. Grainger holds regular Timing of Market Street development meetings with West Berkshire Council, Network Rail and Great Western Railway and representatives from the Newbury Station project are part of this group.

Vodafone have Travel Plan commitments to operate their bus services and links to Newbury Station form a key part of ensuring that staff travel by sustainable modes, avoiding breaching planning conditions in relation to car parking on their site. Withdrawal of Vodafone buses to another location. Vodafone are currently re-committing to this bus service through Reading Buses for the next few years. In the very unlikely event that Vodafone buses were routed elsewhere, the stops anticipated for Vodafone buses could be re-used for College shuttle, taxis, parking, drop-off/pick-up on another relevant purpose for the interchange at low cost.

Investigation works will continue in-house at West Berkshire Council and in conjunction with the Market Street developers (Grainger), Network Rail and Great Western Railway to ensure that as many factors as possible can be considered to reduce the likelihood and severity of cost escalation. This will include: consideration of utilities; consideration of GWR building fabric; obtaining as much detail as possible Cost escalation about Network Rail’s proposed new footbridge and Grainger’s proposed multi-storey car park; liaison will stakeholders including WBC asset management, WBC car parking, taxi-operators, bus operators etc. One initial element will be a detailed feasibility of the public access bridge over the railway as this is the part of the scheme which is likely to be vulnerable to escalating costs due to the complexity of design and delivery.

A full search of utilities across the whole scheme area will be undertaken prior to detailed design work being undertaken to ensure that the design can mitigate against the need to divert or relocate services. Buried services / utilities Some initial utilities searches have already been undertaken by West Berkshire Council. These indicate that there are no significant utilities issues which are likely to prevent the project from proceeding as planned or which cannot be accommodated in the design.

The re-working, demolition and replacement of buildings and structures on the station owned and managed by GWR/NR may detect the GWR/NR building fabric and asbestos presence of asbestos. Accordingly, all building fabric will be examined prior to undertaking works and suitable certified contractors will be used to undertake the works and remove asbestos appropriately should it be discovered.

Whilst it is accepted that Newbury station is low-lying and has flooded in the past, much of the existing area for the scheme is already hard- surfaced. Any new areas for surfacing will require SUDS principles to be applied. Any re-working of existing hard-surfaced areas may give Surface water drainage the opportunity to introduce SUDS or other drainage improvement measures to provide an overall betterment over the existing situation. The Project Team are will also work closely with a group set up to address the flooding issues at the station. The timing of bus services for Sandleford will have negligible impact on the proposed interchange design. The timing of contributions could require West Berkshire Council to bridge the timing of contributions to ensure that the scheme can be Timing of Sandleford development delivered in the required time frame. The Project Team is well linked to the Council’s Officers working on the Sandleford Housing Site so will be aware of the challenges of timing.

5 Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Mar-17 Independent Assessment of FBC September / October 2017 (provisional) Jun-18 Financial Approval from LTB November 2017 (provisional) Jul-18 conditional Feasibility work Second Phase Feb –May 2017 Second Phase Oct’17 – Jan’18 Acquisition of statutory powers Tbc Spring / Summer 2019 Detailed design Tbc November 2017- June 2019 Procurement Tbc Mar-19 Start of construction Sep-18 January 2019 / May 2019 Completion of construction March 2020 (tbc) Mar-21 One year on evaluation March 2021 (Tbc) Mar-22 Five years on evaluation March 2025 (tbc) Mar-26

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.24 Newbury: Railway Station Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £18,441,000 £4,078,281 £127,000 Funding breakdown Local Growth Deal £6,051,000 £158,281 £120,000 s.106 and similar contributions £6,110,000 £0 Council Capital Programme £40,000 £20,000 £7,000 Other (public) £6,240,000 £3,900,000 In-kind resources provided £12,000 £2,000 Outcomes Actual to date Planned Jobs connected to the intervention TBC This will be clarified once proposals for regeneration of the station buildings have been Commercial floorspace constructed (square metres) TBC finalised Housing unit starts N/a Housing units completed N/a Number of new homes with new or improved fibre optic provision N/a

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.24 Newbury: Railway Station Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads 250m Total length of newly built roads 0 Total length of new cycle ways 0 Type of infrastructure Railway station and interchange Type of service improvement Public transport Outcomes Follow on investment at site 0 Commercial floorspace occupied 0 Commercial rental values Not known

7. Further Information for Summary Reports The Newbury Station Improvements will enhance and improve multi-modal transport interchange at Newbury Railway station including upgrade and improvement of station buildings. Programme Entry was awarded in March 2017. Works have started on site for the interchange enhancements (Jan 2019) and the station improvement works are due to start on site May 2019. Full scheme completion is due March 2021. First Growth Fund payment due March 2019. This is the original scheme set out in Growth Deal 3.

Page 48 Meeting Date: 14 March 2019 2.26 Wokingham: Winnersh Relief Road (Phase 2) Originally an LGF scheme but moved to Business Rates Retention Pilot Highlights since last report The conditions on the approval have been met and the scheme approved.

1 The Scheme

1.1. The full project will deliver a new relief road to the west of Winnersh, avoiding the current Winnersh Crossroads junction. 1.2. The work will be delivered in two phases. The first phase, delivered by a Bovis / Persimmon, opened on Monday 11 June. 1.3. The second phase will be delivered by Wokingham Borough Council and will provide a new junction on the A329 Reading Road and will dual the section of Lower Earley Way (B3270). 1.4. The route requires funding to deliver new infrastructure that is essential to facilitate planned housing and economic growth locally. 1.5. The full scheme when joined with the Wokingham Northern Distributor Road will offer an alternative route around the centre of Wokingham and avoiding Winnersh Crossroads.

2 Progress with the scheme 2.1. The BCR for the FULL Winnersh Relief Road scheme is 2.2 (including the funding provide by the developer Bovis.). Considering only the elements to be funded from the LEP the BCR rises to 3.3. 2.2. The route alignment has been agreed and features in a number Wokingham Borough Councils plans such as the Core Strategy and LTP. 2.3. Planning permission has been granted for Phase 1 of the scheme and the scheme construction is now complete and the opened in June 2018. The planning permission includes the Lower Earley Way junction portion of the scheme as well as the section to be delivered by Bovis Persimmon (including the phase 1 junction on Kings Street Lane). 2.4. Lawful Development approval has been granted for phase 2a (dualling of Lower Earley Way) and detailed design has commenced on this section. Full planning permission for phase 2b (King Street Lane to Reading Road) is being sort and an application was submitted in March 2018 and was approved at Planning Committee in October 2018. All the land needed to deliver phase 2b is already in control of Wokingham Borough Council, which reduces the risks associated with planning applications. 2.5. Wokingham Borough Council do not require any further partnership working to complete the scheme and will tendering the scheme in due course to seek maximum value. 2.6. The Phase 2b planning application was approved at planning committee on 10 October. Business case submitted to Hatch Regeneris ahead of November BTLB. Final scheme costs updated. 2.7. Business case obtained conditional approval at November BTLB. Follow up information required by Hatch Regeneris (to achieve full approval) issued by WBC on 10 January. 2.8 Addendum to BC submitted and being considered. 2.9 WBC have sent their response to Hatch Regeneris, this is currently being reviewed. 2.10 Addendum to BC submitted and being considered. 2.11 The conditions on the approval have been met and the scheme approved.

3 Funding 3.1.The following table sets out the funding for the full scheme (includes Phase 1 & Phase 2). Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Business Rates Retention Pilot £3,000,000 £3,260,000 £6,260,000 Local contributions from Private sector (Developer delivery of Phase 1) £6,500,000 - - £6,500,000 - Council Capital Programme £7,204,223 £7,204,223 - Other sources (private sector) £438,000 £438,000 Total Scheme Cost £0 £438,000 £6,500,000 £3,000,000 £10,464,223 £0 £20,402,223

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Project will be managed and designed by Wokingham Borough Council and this will reduce the risk of delivering the junctions as issues can be Design & Delivery internalised. The land on which the relief road is being constructed, floods, but that has been mitigated by using flood analysis data and the associated construction Flooding techniques.

Political support There is strong political support for the scheme as it’s seen as part of wider package of measures to support the growth of Wokingham Borough.

Land ownership Land constraints identified, elements of land within local authority ownership.

5 Programme

Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Mar-17 Independent Assessment of FBC Spring 2018 Financial Approval from LTB Jul-18 Nov-18 Feasibility work Complete. (2015-2016) Acquisition of statutory powers Nov-17 Mar-18 Detailed design May-18 Apr-18 Procurement Nov-18 Summer 2018 (enabling), Start of construction Jan-19 main works to start summer/autumn 2019. Completion of construction Aug-20 Sep-20 One year on evaluation 2021 Sep-21 Five years on evaluation 2025 Sep-25

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.26 Wokingham: Winnersh Relief Road Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £20,402,223 £0 £0 Funding breakdown Business Rates Retention Pilot £6,260,000 s.106 and similar contributions £6,500,000 Council Capital Programme £7,204,223 Other £438,000 In-kind resources provided Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) (Under construction as Housing unit starts 74 at March 2018) Housing units completed 152 (As at March 2018)

Number of new homes with new or improved fibre optic provision

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.26 Wokingham: Winnersh Relief Road Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads 1.5km (Both phases) Total length of newly built roads 1.5km (Both phases) Total length of new cycle ways 1.5km (Both phases) Type of infrastructure New carraigeway Type of service improvement Enabling housing development and congestion relief Outcomes Follow on investment at site Unknown at present. To be assessed 1 and 5 years after scheme opening Commercial floorspace occupied Unknown at present. To be assessed 1 and 5 years after scheme opening Commercial rental values Unknown at present. To be assessed 1 and 5 years after scheme opening

7. Further Information for Summary Reports A new relief road to the west of Winnersh, avoiding the current Winnersh Crossroads junction and completing the developer-funded Phase 1. Programme Entry awarded March 2017. The scheme is due to complete in August 2020. The first of three Growth Deal payments is due in March 2019. This is the original scheme set out in Growth Deal 3.

Page 49 Meeting Date: 14-Mar-19 2.27 Maidenhead Town Centre Missing Links

Highlights since last report

- Design works are split into three elements - preliminary design on traffic elements has been commissioned, with the footbridge and subway to be taken to detailed design in one package. An inception meeting was held on 19th February. - There has been a request for Strand Water to become a navigable channel as part of a future phase of the Maidenhead Waterways scheme, which would have implications for the design of the bridge and cycle routes across Town Moor - these elements have therefore been slipped to next financial year while designs are reviewed. This does not impact on the overall programme. - The Royal Borough's Cabinet have adopted an ambitious 10-year cycling strategy seeking to improve infastructure; increase cycling numbers and reduce cycling casulaties. This scheme is embedded in the strategy. - A public engagement event was held on 1-2 March covering all of the Maidenhead Major Schemes and town centre regeneration proposals. A site office has been set up in an empty retail unit in King Street and information from the public exhibition will be on display here.

1 The Scheme 1.1 The purpose of this scheme is to complete the ‘missing links’ between planned major development areas in and around Maidenhead and to improve their connectivity to the town centre and surrounding residential areas and local facilities. 1.2 A new ‘inner-ring’ is proposed for pedestrians and cyclists, which will be tied into new / enhanced crossings over the A4. The routes will tie into the infill public realm areas in the town, which will in turn trigger a review of the core town centre road network.

2 Progress with the scheme 2.1. The project directly supports and strengthens the regeneration plans for Maidenhead. The Maidenhead Town Centre Area Action Plan sets a clear vision for economic growth, designating six ‘opportunity areas’ for regeneration, including: Maidenhead Station; Broadway; West Street; Chapel Arches; York Road; and Stafferton Way. Since then, a further two major development sites have been identified, namely St Clouds Way to the north of the A4 and Reform Road to the east of the town centre. 2.2. Cumulatively, this regeneration will result in: • Up to 4,870 new dwellings • Over 65,000 m2 of new office space • An enhanced retail offer • An improved leisure offer, with new cafes and restaurants • Public realm enhancements 2.3. These will be in addition to the recent developments at Boulter’s Meadow and Kidwells Park to the north of the town centre. It is important to ensure that all new development is integrated with the wider town centre and the surrounding urban area, with continuity in public realm and high quality walking and cycling networks. 2.4. The Maidenhead Waterways project is integral to the regeneration of the town centre – restoring and enlarging the waterways that run through the town centre. When complete, this will allow continuous navigation by small boats. It will also enhance the setting of the Chapel Arches development. In addition, the towpaths will provide a valuable recreation resource, and will improve access to the town centre for pedestrians and cyclists. In order to be effective these towpaths will need to be linked to wider walking and cycling networks. 2.5. Aspirations for continuous and cohesive walking and cycling networks and public realm cannot be delivered by these developments alone. If walking and cycling access is left solely to the developers of each Opportunity Area, then financial and land constraints will lead to disjointed and incomplete networks serving individual developments rather than the wider town centre and North Maidenhead area. 2.6. The Maidenhead Town Centre Area Action Plan identifies the need to enhance entrance points into the town centre with high quality public realm. It also includes an objective to improve the quality of existing public spaces, with a specific focus on the train station, High Street, King Street and Queen Street. Some sections will be delivered as part of the regeneration of the Opportunity Sites, but gaps will remain. 2.7. The Royal Borough has also developed a draft Cycling Action Plan, which identifies an ‘inner ring’ route, which will connect the major development sites and link them to employment and retail opportunities in Maidenhead town centre and Maidenhead Station. The ring will also improve links to surrounding residential areas, local schools and the Waterway towpaths. This will help to increase the proportion of local trips made on foot and by bike, delivering congestion and air quality benefits. 2.8. Some sections of the ‘inner ring’ will be provided as part of the regeneration of the Opportunity Areas and as part of the Maidenhead Station Access scheme. These include: remodelling of the King Street / Queen Street / A308 junction to improve pedestrian / cycle crossings; and provision of a new link through the St Cloud Way site. Additional works are required to join up these disparate links, including a new link across the A4 between West Street and Kidwells Park and replacing the existing footbridge over Strand Water with a new shared use facility. An additional pedestrian / cycle bridge is being built to provide a link to Oldfield School to the south of the town centre. 2.9. The regeneration activity will also impact on traffic flows around the town centre, prompting a review of the of the existing road network, including directional flow, changes in terms of one / two way operation and changes to the pedestrianised areas / public open space. 2.10. The project steering group has been established with the project inception meeting taking place on 13 January 2017. 2.11. In March 2017, the council appointed Countryside PLC as joint venture partners for the regeneration of four major development sites, including: West Street; St Cloud Way; York Road; and Reform Road. 2.12. Countryside developed a number of options for the bridge link over the A4 between West Street and Kidwells Park, but it proved challenging to integrate the bridge ramps with the new development and alternative options had to be explored, including surface and subway crossings. 2.13. RBWM paused development work on the Missing Links scheme in order to be able to take account of significant changes proposed in connection with a number of major developments. 2.14. Work is concluding on the Parking Plan, including proposals for a new multi-storey car park at Vicus Way, redevelopment of the Nicholsons Multi-Storey Car Park and delivery of temporary car parks to accommodate parking that will be displaced during construction. 2.15. As part of proposals for The Landing development and the York Road Opportunity Area, changes to the town centre were proposed. These prompted a wider feasibility study looking at options for the town centre road network as a whole. 2.16. The Royal Borough is also one of the shortlisted local authorities bidding for the ‘forward funding’ element of the Housing Infrastructure Fund. The Council’s bid is focused on providing enabling works for the Golf Course Development to the south of Maidenhead, with up to £9.8 million earmarked for major highways works and access improvements to this major development site. RBWM has appointed CALA Homes as the joint venture partner for the development. 2.17. The above projects are likely to have a significant impact on how people and vehicles will travel around the town and the Council needed to understand how these schemes will look and how they interact before considering how the Missing Links proposal can best be designed to serve the developments and be integrated with the proposed highway network.

2.18. The business case was submitted and approved on 15 November subject to conditions. The economic assessment showed a BCR of 2.1. Currently working with Hatch Regenersis on discharging the conditions. 2.19. Design works are split into three elements - preliminary design on traffic elements has been commissioned, with the footbridge and subway to be taken to detailed design in one package. An inception meeting was held on 19th February. 2.20. There has been a request for Strand Water to become a navigable channel as part of a future phase of the Maidenhead Waterways scheme, which would have implications for the design of the bridge and cycle routes across Town Moor - these elements have therefore been slipped to next financial year while designs are reviewed. This does not impact on the overall programme. 2.21. The Royal Borough's cabinet has adopted an ambitious 10-year cycle strategy seeking to improve infrastructure; increase cycle numbers and reduce cycle casulaties. This scheme is embedded in the strategy. 2.22. A public engagement event was held on 1-2 March covering all of the Maidenhead Major Schemes and town centre regeneration proposals. A site office has been set up in an empty retail unit in King Street and information from the public exhibition will be on display here.

3 Funding 3.1.The following table sets out the funding for the scheme on the basis of our unapproved funding profile. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £842,000 £1,399,788 £2,241,788 Local contributions from - Section 106 agreements £5,379 £57,815 £104,940 £168,134 - Council Capital Programme £12,550 £134,904 £244,859 £392,313 - Other Total Scheme Cost £0 £0 £0 £17,929 £1,034,719 £1,749,587 £2,802,235

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Construction Cost Increase Scheme design and material specs will need to be amended to reduce project costs or the Council will need to provide additional funding If the A4 crossing were to not receive planning consent then a key section of the scheme would be missing. Subject to the reasons for refusal there may be scope to resubmit a revised scheme, which will add delay Planning Consent and cost. Seeking consent earlier than required would limit the risk or highlight issues at a much earlier stage to allow time for mitigation. Cost of Utilities Protection/Diversion Early engagement with the utility companies and knowledge of their requirements and locations is key to seeking to reduce this risk Although the majority of the scheme is within public highway land or RBWM property, there is always a risk that small sections of private land may impact on the buildability of the scheme. The Council will seek Land Ownership records and legal deeds during design stage and clarify their impact on the scheme and redesign accordingly to limit any need for 3rd party land. Where the ‘Inner Ring’ crosses the waterways, park or moorland, the ecology of these areas may be impacted by the scheme and suitable measures may be needed to mitigate the impact. Early investigation is key Ecological to removing the need for mitigation or seeking cost effective measures to address any issues.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jan-17 - Feasibility / outline design Apr-17 Sep-18 Preparation of FBC Sep-17 Oct-18 Independent Assessment of FBC Oct-17 Oct-18 Financial Approval from LTB Nov-17 Nov-18** Procurement Dec-17* Oct-19 Start of construction Jan-18 Jul-20 Completion of construction Mar-21 - One year on evaluation Mar-22 - Five years on evaluation Mar-26 - *Oldfield Bridge procurement already completed and construction commenced May 2018. **Conditional approval granted in November 2018 6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.27 Maidenhead Town Centre Missing Links Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £2,802,235 £166,000 £0 Funding breakdown Local Growth Deal £2,241,788 s.106 and similar contributions £420,335 Council Capital Programme £140,112 £166,000 Other In-kind resources provided £150,000 £15,000 Outcomes Planned Jobs connected to the intervention 8,000 Commercial floorspace constructed (square metres) 65,404 Housing unit starts 1,986 Housing units completed 2,884 No. new homes with new or improved fibre optic provision 2,884

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.27 Maidenhead Town Centre Missing Links Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads 0.33 km Total length of newly built roads 0 km Total length of new cycle ways 0.8 km Type of infrastructure New / upgraded pedestrian / cycle bridge links at Holmanleaze, A4 and Oldfield School Type of service improvement Active travel investments Outcomes Follow on investment at site TBC Commercial floorspace occupied 3,637 Commercial rental values TBC

7. Further Information for Summary Reports A central Maidenhead ‘inner-ring’ is proposed for pedestrians and cyclists, which will be tied into enhanced crossings over the A4, including a pedestrian and cycle bridge. Programme Entry achieved March 2017. The Oldfield Bridge element of the scheme went on site in May 2018 with the remainder of the works due to start in January 2019, and completion in March 2021. The first Growth Fund payment is due in March 2021.

Page 50 Meeting Date: 14 March 2019

2.28 Bracknell: A3095 Corridor

Highlights since last report

1 The Scheme This project delivers significant improvements to one of the key highway corridors in the Thames Valley Berkshire. The project will significantly help in terms of accommodating movements and reducing congestion between the M4 (J8/9/10) and M3 (J4) and between Maidenhead, Reading, Wokingham, Bracknell, and Camberley/Blackwater Valley and beyond. This work would also assist in unlocking housing delivery at TRL and Broadmoor that will provide 1415 new houses and enhance urban connectivity.

2 Progress with the scheme 2.1. Officers are now carrying out detailed design of the various elements of the scheme including trial holes and tree surveys. 2.2. Survey work is now being undertaken to gather all the information required to inform the design process. Information being gathered includes a 3d model of the underground services, ground condition surveys, core samples and widow testing around the subway structures. Once this information is collected the design team can use this information within the ongoing detailed design of the various elements of the scheme.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £200,000 £1,800,000 £3,518,800 £5,518,800 Local contributions from £0 - Section 106 agreements £500,000 £2,000,000 £2,500,000 - Council Capital Programme £0 - Other sources £0 Total Scheme Cost £0 £0 £0 £200,000 £2,300,000 £5,518,800 £8,018,800

4 Risks Risk Management of risk That the overall cost of the Coral Reef Junction exceeds the funding Detailed Bill of Quantities with effective site and contract management available Statutory undertakers C4 cost estimates significantly exceed C3 cost Early liaison with statutory undertakers and early commission of C4 estimates (underway) estimates Highway Works in neighbouring local authority area during construction leading to traffic congestion and possible impact on Liaison with neighbouring authorities and agreement re. programme programme and costs Unexpected need for additional Temporary Traffic Management Liaison with Traffic Management Section and early quantification of TM requirements and costs (underway) increasing costs

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jan-17 Independent Assessment of FBC Apr-17 Feb-18 Financial Approval from LTB Jul-17 Jul-18 Feasibility work Apr-16 Acquisition of statutory powers None required Detailed design Jan-19 Procurement Term contractor Start of construction Apr-19 Enabling works Oct-18; construction Nov-19 Completion of construction Nov-21 One year on evaluation Nov-22 Five years on evaluation Nov-26

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.28 Bracknell: A3095 Corridor Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £8,018,800 £200,000 £0 Funding breakdown Local Growth Deal £5,518,800 £200,000 s.106 and similar contributions £2,500,000 Council Capital Programme Other In-kind resources provided £15,000 Outcomes Planned Jobs connected to the intervention 0 Commercial floorspace constructed (square metres) 0 Housing unit starts 1,415 181 Housing units completed 1,415 26 Number of new homes with new or improved fibre optic provision1,415 26

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.28 Bracknell: A3095 Corridor Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads Approximately 2500 m of resurfacing Total length of newly built roads Approximately 5700m following removal of the roundabout and realignment of the carriageway. Total length of new cycle ways Existing cycleway network runs adjacent to the junction and is unaffected by the works Type of infrastructure Replacement of existing roundabout with new signalised junction Type of service improvement Improvement to journey times following removal of an existing pinch point on the network. Outcomes Follow on investment at site Commercial floorspace occupied Commercial rental values

7. Further Information for Summary Reports This project will support the development of 1,415 new houses along the A3095 south of Bracknell. An outline case has been prepared, and the full business case is due in July 2018. The first of two Growth Deal payments is due in March 2020. This is the original scheme approved in Growth Deal 3.

Page 51 Meeting Date: 14 March 2019 2.29 Wokingham: Winnersh Triangle Parkway Highlights since last report

1 The Scheme 1.1. The purpose of this scheme is to redevelop the transport links at Winnersh Triangle and consider renaming the station to Winnersh Triangle Parkway. 1.2. The redevelopment will include double decking the new park and ride site to add at least 250 car parking spaces, improvement of the station building including the surrounding area, reorganising the highways layout and exploring the value of reinstating the redundant Reading bound ‘on ramp’ of the A3290. These arrangements would complement growth plans of Frazer Centrepoint who are intensifying the use of the Business Park. 2 Progress with the scheme 2.1. Progress to date has been limited to commissioning WSP to develop a design capable of submission to planning for approval and to develop the necessary business case to ensure the scheme demonstrates value for money, following Thames Valley LEP Board approval to progress in November 2017. 2.2. Initial discussions have been undertaken with South Western Railway (SWR) to understand the level of investment needed to change the layout of the platforms, which are on an embankment. We have asked SWR to explore what would be needed to deliver access for all funding to make sure that the station was inclusive for all users. 2.3. The Council has had an initial meeting with the new owners of Winnersh Triangle Business Park, Frazer Centrepoint. The initial meeting suggested that the business park would be willing to improve access and the visual appearance to the station approach as far as they could and on the land within their control. 2.4. Reading Transport were equally enthusiastic about expanding the service offer at Winnersh Triangle to take advantage of new infrastructure and links to central Reading. 2.5. A business case will be developed around the usefulness of the redundant on ramp to the A3290. At present no contact has been made with National Amusements to understand what is needed to regain access across a narrow strip of car park to link both sections of highway [Initial assessment of this element of the project has ruled out this element]. 2.6. Updates have been provided to both SWR and Frazer Centrepoint, with both parties still engaged and supportive of the scheme. 2.7. WSP to be commissioned to develop a Business Case for the scheme and this will be forthcoming before March 2019. 2.8. WSP has been comissioned to develop Business Case for March 2019. Meeting has taken place between WSP and Regeneris regarding the Business Case. Discussions ongoing with potential parking deck suppliers and SWR to refine cost estimates. 2.9 Work on Business Case is ongoing with submission due to be made in time for the March LEP Board meeting. Project costs revised following refined costs from suppliers.

3 Funding 3.1 The following table sets out the indicative funding for the scheme on the basis of our unapproved funding profile. The funding profile will be updated as the scheme progresses further towards planning and business case approval, however the bulk of the funding will be spent in 2020/21. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £250,000 £2,600,000 £2,850,000 Local contributions from - Section 106 agreements £50,000 £500,000 £550,000 - Railway contributions £0 - Other sources (private sector) £0 Total Scheme Cost £0 £0 £0 £0 £300,000 £3,100,000 £3,400,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Project will be managed and designed by Wokingham Borough Council and will deliver a parkway project that will improve the opportunity for Design & Delivery sustainable travel. The site identified, has recently been developed with a car park that manages flooding. The flood risk assessments provided for the car park Flooding upgrade in 2015/16 are still relevant. Political support There is strong political support for the scheme from both Wokingham Borough and Reading Borough members. Land ownership The land on which the parkway project is to be developed is within the control of both Wokingham Borough and South Western Railway.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Dec-17 Independent Assessment of FBC Oct-18 Feb-19 Financial Approval from LTB Nov-18 Mar-19 Feasibility work Acquisition of statutory powers Sept 2019 (Provisional) Detailed design Jan 2020 [Car Park Deck] Procurement Apr 2020 [Car Park Deck] Start of construction Jan 2020 [Station Building/Forecourt]Jun 2020 [Car Park] Completion of construction Sep-20 One year on evaluation Sep-21 Five years on evaluation Sep-25

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.29 Wokingham: Winnersh Triangle Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £3,600,000 £0 £0 Funding breakdown Local Growth Deal £3,000,000 s.106 and similar contributions £600,000 Council Capital Programme Other In-kind resources provided Outcomes Planned Jobs connected to the intervention 220 Commercial floorspace constructed (square metres) 5,500 Housing unit starts 433 Housing units completed Number of new homes with new or improved fibre optic provision 433

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.29 Wokingham: Winnersh Triangle Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads 0 Total length of newly built roads 0 Total length of new cycle ways 0 Type of infrastructure Car Park, Station & Bus turning area Type of service improvement Mode shift opportunity Outcomes Follow on investment at site To be determined Commercial floorspace occupied To be determined Commercial rental values To be determined

7. Further Information for Summary Reports Wokingham Winners Triangle will improve the station facilities, more than double the capacity of the adjacent Park and Ride car park and support the development of employment at the Business Park. The first of two Growth Deal payments is due in March 2020. This is a new scheme not identified in Growth Deal 1, 2 or 3; it was added to the programme from the reserve list of schemes following the identification of unallocated Growth Deal money.

Page 52 Meeting Date: 14 March 2019 2.30 Thames Valley Berkshire Smart City Cluster Highlights since last report

1 The Scheme 1.1. The project delivers three key deliverables: 1.2. Smart city platform: consisting of an Internet of Things (IoT) communication platform across Reading, Wokingham, West Berkshire and Bracknell and a cross-authority open data platform. This is enabling infrastructure for the delivery of a wide range of IoT technologies including traffic signal communications which will provide the revenue savings to maintain and operate the system. 1.3. Challenge funded IoT solutions: grant funded IoT solutions to real Local Authority challenges which will utilise the platform. These grants will be awarded through competition and will be on the basis of co- funding. 1.4. Cross authority / cross sector smart city group: This includes a Steering Group to oversee the project delivery and act as a catalyst for wider smart city debate, project development and funding.

2 Progress with the scheme 2.1. The process for defining the challenge funds has beeen amended with agreement of the SG. instead of a large 4th cross sector and cross authority workshop to define the detailed challenges it was agreed that there should be a short listing process by the SG with techincal input (undertaken in December) and then individual small workshops focused on services for vulnerable people (an outcome of the shortlisting) in each authority to define the actual challenges. This approach will make it easier to achieve the defined output required. There is an impact on programme in getting the right people together but it is worth it to get the right result. The Chief Execs have also given their endorsment to engagement at this meeting and have been involved in identifying who should attend. Individual authroity workshops are set for the end of Jan to mid Feb. This first call will be for four £100k projects, one in each authority - cross checking will be done so that the calls are complementary and can benefit cross authroity learning. We will be marketing the 1st call towards the end of Feb. 2.2. The LoRa coverage trials which were due to be complete by the end of September have been delayed due to a variety of issues including technical and access issues. There remain technical difficulties at two of the trial sites however the network coverage has been remapped. Authorities are still working to identify futher high buildings but with the current proposals we will have generally good coverage across the urban areas. Approvals for procurement of the LoRa units were further delayed and request for quotes was issued just before Christmas with quotes just recieved at the time of writing this report. Quotes are within the expected range of costs and install is expected to commence in mid February once the unites are supplied and configured. 2.3 Draft programme still completes by Feb 2020 taking acount of the above although we have removed any contingency time in the programme. 2.4 Reading Backhaul upgrade is on hold subject to specification of main LoRa network and evaluation of the wider cross authority benefits. 2.5 Programme is being reviewed in light of the above with the Steering Group on 15th November. Draft programme still complete by Feb 2020 taking acount of the above. 2.6 Workshop 3 has been completed as per the programme. Technical issues have led to some delays in delivery of the LoRa trial and programme is delivery programme is being revised. Workshop 4 timetable is being delayed from Oct / Nov to January to allow reivew of approach and proper preparation to ensure that Challenges can be developed. Neither are expected to impact on end completion date or deliverables.

2.7 Local Authoirty Challenge funding workshops - Workshops have been undertaken with with key officers around developing vulnerable people challenges at West Berks and Reading and these have gone very well with decisions made for focus of first £100k challenges for both authorities - these are now being detailed up. Wokingham's on 13th Feb and Bracknells on March 1st. This now means that advertising of challenge funds need to be pushed back to mid to end of March with award slipping to April and project end date needs to be kept under review.

2.8 Quotes for LoRa gateways have been recieved and award expected at beginning wc 11th Feb. delivery timescale can be up to 8 weeks and confirmation needed of delivery dates so that configuration and installation timescales can be confirmed - looking to confirm WC 11th Feb with successful supplier. This will impact substantial completion of Communications Platform date and associated payment date which has been deferred from end of March 2019. Estimated end of May for substantial completion based on current information although project team still pushing for end of April as previously advised.

2.9 Associated bid to Adept has been awarded £4.7m of highway and transport innovation funding with a detailed project plan to be developed by 1st May.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £83,400 £280,000 £1,370,254 £1,733,654 Local contributions from - DfT C-ITS Funding £100,000 £150,000 £250,000 - WND SigFox £8,000 £217,000 £225,000 - Challenge Fund (co-funding) £0 £311,000 £311,000 Total Scheme Cost £0 £0 £83,400 £388,000 £2,048,254 £0 £2,519,654

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Smart city communications platform does not meet functional Due diligence expert appointed to advise on proposal. requirements Opportunities will be widely marketed. Already good interest in calls that will come out so seen as a low risk. More than one call so that second call Insufficient ‘good’ interest in challenge fund calls to industry can be re-targeted. Challenge fund calls do not result in commercially viable solutions Good input to the definition of the challenge fund calls through working across the authorities. Expert panel to be identified to evaluate calls and that meet the real needs. question commercial viability. Calls to avoid generating solutions that collect personal data. Combination of datasets to reviewed so that there is not a risk due to aggregating Data security and personal information data. If proposals come forward with data that needs to be kept secure, then these will be carefully evaluated as to their benefit against not providing open data for the smart city platform to ensure data security. Delays / spend over runs Effective project management, scalability of challenge fund calls to target spend to the budget.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Communications platform specification Mar-18 Sep-19

Communication platform procurement and implementation Mar-18 Dec-18

Substantial completion of communications platform Aug-18 Apr-19 Data platform specification Mar-18 Jul-18 Data platform Implementation May-19 Jan-19

Reading backhaul upgrade specification Mar-18 -

Reading backhaul upgrade delivery Jul-18 - Feb '18; Mar '18; May '18; July '18; Stakeholder workshops July '18; Aug '18 Sep '18; Jan / Feb 19 Definition of challenge fund call requirements Apr-18 Jan / Feb -19 Award of challenge fund call 1 Aug-18 Mar-19 Substantial delivery of challenge fund call 1 May-19 Sep-19 Award of challenge fund call 2 Feb-19 Jun-19 Substantial completion of challenge fund call 2 Oct-19 Dec-19 Project end Oct-19 Feb-20 One year on evaluation Oct-20 Feb-21 Five years on evaluation Oct-24 Feb-25

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme 2.30 Thames Valley Berkshire Smart City Thames Valley Berkshire LEP Mar-19 Q4 18/19 Cluster 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £2,519,654 £231,000 £0 Funding breakdown Local Growth Deal £1,733,654 £135,000 - DfT C-ITS Funding £250,000 £88,000 - WND SigFox £225,000 £8,000 - Challenge Fund (co-funding) £311,000 £0 In-kind resources provided £786,000 £0 Outcomes Planned Jobs connected to the intervention 63 Commercial floorspace constructed (square metres) N/A Housing unit starts N/A Housing units completed N/A Number of new homes with new or improved fibre optic provision N/A

7. Further Information for Summary Reports The TVB Smart City Cluster project will provide an Internet of Things (IoT) communication platform across Reading, Wokingham, West Berkshire and Bracknell and a cross-authority open data platform. This is enabling infrastructure for the delivery of a wide range of IoT technologies. First of three Growth Deal payments was made in March 2018.

Page 53 Meeting Date: 14 March 2019

2.31 Slough: Stoke Road Area Regeneration

Highlights since last report

1 The Scheme 1.1. Sustainable transport infrastructure and highway works to support regeneration of six major brownfield sites at Stoke Road and improved interchange and parking at Slough station. 2 Progress with the scheme 2.1. New scheme. Plans to develop the scheme are in progress. 2.2. Program entry status BLTB 14th July 2018 2.3. Funding profile amended due to June 2019 start on site (construction work) 2.4. Business case to be submitted to BLTB for July 2019 2.5. Public consultation on concept designs took place in Jan 2019

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,500,000 £5,150,000 £7,650,000 Local contributions from £0 - Section 106 agreements £1,000,000 £1,000,000 - Council Capital Programme £0 - Other sources £2,250,000 £2,250,000 Total Scheme Cost £0 £0 £0 £0 £3,500,000 £7,400,000 £10,900,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Delays in approval granted following Limit changes to design scope independent assessment

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul 2018 BLTB Independent Assessment of FBC Oct-18 Financial Approval from LTB Nov-18 Jul-19 Feasibility work Acquisition of statutory powers Cabinet approve scheme Dec-18 Detailed design Procurement Mar-2019 - enabling works Start of construction Jun-19 Q3 2019 construction Completion of construction Mar-22 One year on evaluation Mar-23 Five years on evaluation Mar-27

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.31 Slough: Stoke Road Area Regeneration Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £10,900,000 £150,000 £0 Funding breakdown Local Growth Deal £7,650,000 £150,000 s.106 and similar contributions £1,000,000 £0 Council Capital Programme £0 Other £2,250,000 £0 In-kind resources provided £0 £0 Outcomes Actual to date Planned Jobs connected to the intervention 293 Commercial floorspace constructed (square metres) 6400 Housing unit starts 4360 Housing units completed 0

Number of new homes with new or improved fibre optic provision Not known

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.31 Slough: Stoke Road Area Regeneration Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads TBC Total length of newly built roads 0 Total length of new cycle ways TBC Type of infrastructure Highway improvements including junction modifications, cycle ways, footbridge, interchange and associated improvements Type of service improvement Improved network for all road users, including walking and cycling infrastructure and parking facilities at Slough Station Outcomes Follow on investment at site To be determined Commercial floorspace occupied To be determined Commercial rental values To be determined

3. ADDITIONAL MONITORING - for specific schemes Transport - to be collected for all projects/programmes involving more than £5m public funding and where these metrics and the Planning Numbers Actual to date collection points are relevant to the intervention Average daily traffic and by peak/non-peak periods Data for: A4 Wellington Street and B416 Stoke Average AM and PM peak journey time per mile on key routes N/A (journey time measurement) Average AM and PM peak journey time on key routes (journey time Data for: A4 Wellington Street and B416 Stoke measurement) Road Day-to-day travel time variability Data for bus travel time variations from Average annual CO2 emissions Data for Slough-wide emissions from traffic on Accident rate Data for rates along A4 and B416 Casualty rate Data for KSI and slights along A4 and B416 Nitrogen Oxide and particulate emissions Data for Slough AQMA 4 Traffic noise levels at receptor locations N/A Annual average daily and peak hour passenger boardings N/A Bus/light rail travel time by peak period N/A Mode share (%) N/A Pedestrians counts on new/existing routes TBC Data for journeys along A4 Wellington Street Cycle journeys on new/existing routes and B416 Stoke Road Households with access to specific sites by mode within threshold Data for households: destinations TBC times (#) 7 Further Information for Summary Reports

Page 54 Meeting Date: 14-Mar-19 2.32 Maidenhead: Housing Sites Enabling Works Phase 1

Highlights since last report - A public engagement event was held on 1-2 March covering all of the Maidenhead Major Schemes and town centre regeneration proposals. A site office has been set up in an empty retail unit in King Street and information from the public exhibition will be on display here.

1 The Scheme 1.1. This scheme consists of a package of traffic management measures to deliver additional capacity at key junctions around Maidenhead where modelling has indicated that severe peak hour congestion is likely to occur as a result of planned development and regeneration activity. 1.2. The scheme will facilitate economic growth by unlocking major housing and commercial development. It will also improve journey times for passengers accessing the Great Western Main Line / Elizabeth Line. The works will be progressed in phases in order to minimise the impact on the local road network. 2 Progress with the scheme 2.1. The Council submitted the Borough Local Plan (BLP) to the Secretary of State in January 2018. It is currently at the examination stage. The BLP makes provision for at least 14,240 new dwellings over the plan period from 2013 to 2033. Development in and adjacent to Maidenhead town centre will provide many of these new dwellings, including redevelopment of existing sites for higher intensity development. The plan also makes provision for at least 11,200 net new jobs across a range of floor spaces, including at least 130,700m2 of B Class floor space comprising: 81,300m2 of B1 (office); 24,500m2 of B2 (manufacturing); and 24,900m2 of B8 (warehousing). Sites in and around Maidenhead will account for the majority of this development. 2.2. The impacts of the additional traffic associated with these proposed development sites have been evaluated using a strategic traffic model with a 2032 forecast scenario. This identified several key junctions where severe peak hour congestion is likely to occur. These include: • M4 Junction 8/9 • A308(M) / A308 / A330 / The Binghams roundabout • A404(M) / Stafferton Way / Norreys Drive roundabout • A404(M) / A404 / A4 roundabout • A308 / Stafferton Way / Rushington Avenue roundabout • A4 / A308 roundabout • A4 / B4447 roundabout • A4 / A4094 roundabout 2.3. The M4 junctions need to be addressed by Highways England through their Road Investment Strategy processes, but the other schemes mostly affect the local road network for which the Royal Borough is the highway authority. Delivering additional capacity at these junctions is necessary for planned housing and commercial development to come forward. 2.4. Traffic management schemes have been identified for each of the junctions identified above. These schemes have been tested in the borough’s strategic traffic model and have been shown to effectively mitigate the congestion issues in each case. Full details can be found in the Strategic Highway Model – Local Plan Assessment Report available on the council's website. 2.5. In addition, the A4 / Oldfield Road junction has been shown as likely to experience significant congestion, albeit just below the levels predicted at the other junctions. However, significant queues are already observed in the peak periods. A proposal for signalisation of this junction has been developed separately to the other mitigation measures identified in the Local Plan Assessment Report. 2.6. Most of the above junctions have been identified as being in a poor condition and are in need of full structural maintenance now or in the next couple of years. Therefore it would be sensible to ensure that this work is carried out at the same time as the capacity improvement works. 2.7. RBWM has appointed CALA Homes as its joint venture partner for the Maidenhead Golf Club development, and is submitting a Housing Infrastructure Fund bid for on and off-site transport infrastructure improvements, which is complementary to the LGF bid. 2.8. The scope of the project has been reduced from the original proposal - A4 / A404(M), A4 / Cannon Lane, and Shoppenhangers Road / Norreys Drive roundabouts have been omitted to compensate for increases in costs on other junctions as a result of more accurate cost estimates. '2.9. Business case approved subject to condtitions at extraordinary meeting of the Local Transport Body held on 31 January 2019. Currently working with Hatch Regenersis on discharging the conditions. 2.10. A public engagement event was held on 1-2 March covering all of the Maidenhead Major Schemes and town centre regeneration proposals. A site office has been set up in an empty retail unit in King Street and information from the public exhibition will be on display here. 3 Funding 3.1.The following table sets out the funding for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Local Growth Deal £2,315,000 £1,898,000 £4,213,000 Local contributions from - Section 106 agreements £174,000 £142,000 £316,000 - Council Capital Programme £405,000 £332,500 £737,500 - Other BRRP (TVB LEP) £1,068,000 £1,068,000 Total Scheme Cost £0 £0 £0 £0 £3,962,000 £2,372,500 £6,334,500 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Construction Cost Increase Scheme design and material specs will need to be amended to reduce project costs or the Council will need to provide additional funding. Cost of Utilities Protection/Diversion Early engagement with the utility companies and knowledge of their requirements and locations is key to seeking to reduce this risk. Although the majority of the scheme is within public highway land or RBWM property, small sections of private land may impact on the buildability of the Land Ownership scheme. The Council will seek records and legal deeds during design stage and clarify their impact on the scheme and redesign accordingly to limit any need for 3rd party land.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul-18 Feasibility / outline design Oct-18 Preparation of FBC Oct-18 Independent Assessment of FBC Oct-18 Financial Approval from LTB Oct-18 Jan-19 Detailed design - phase 1 Jan-19 Jun-19 Procurement - phase 1 Jan-19 Jul-19 Start of construction - phase 1 Feb-19 Aug-19 Completon of construction - phase 1 Mar-19 Mar-20 Detailed design - phase 2 Jun-19 Procurement - phase 2 Jul-19 Start of construction - phase 2 Aug-19 Completion of construction - phase 2 Mar-20 Detailed design - phase 3 Jun-20 Procurement - phase 3 Jul-20 Start of construction - phase 3 Aug-20 Completion of construction - phase 3 Mar-21 One year on evaluation Mar-22 Five years on evaluation Mar-26

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.32 Maidenhead: Housing Sites Enabling Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £5,266,500 £42,000 £0 Funding breakdown Local Growth Deal £4,213,000 s.106 and similar contributions £316,000 Council Capital Programme £737,500 £42,000 Other BRRP (TVB LEP) £1,068,000 In-kind resources provided £20,000 Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts Housing units completed No. new homes with new or improved fibre optic provision

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.32 Maidenhead: Housing Sites Enabling Mar-19 Q4 18/19 Outputs Planning Numbers Actual to date Actual for the quarter Total length of resurfaced roads 2 km Total length of newly built roads 0 km Total length of new cycle ways 0 km Type of infrastructure Junction improvements Type of service improvement Additional traffic capacity to improve journey times, congestion and journey times. Outcomes Follow on investment at site TBC Commercial floorspace occupied 28,894 Commercial rental values TBC

7. Further Information for Summary Reports

Page 55 Meeting Date: 14 March 2019 2.34 Slough MRT Phase 2

Highlights since last report

1 The Scheme 1.1. The A4 forms the spine of a 12km strategic public transport corridor that links Maidenhead, Slough and Heathrow and plays an important role in providing surface access to the airport. Phase 2 will extend the Slough Mass Rapid Transit (SMaRT) project from its current end point at Langley and take it onto the Heathrow service road. Bus lanes and other priority measures will be provided in the new section between

2 Progress with the scheme 2.1. New scheme. Plans to develop the scheme are in progress. 2.2. Program entry status BLTB 14th July 2018 2.3. We (Slough) have recently updated our traffic model using 2017 survey data, and we encountered a few technical issues that took longer than anticipated to resolve. The resulting delay has meant that we have missed the deadline for submitting a complete Full Business Case for independent assessment by Hatch Regeneris in time for the November meeting. 2.4. The elements of the Full Business Case relating to the bus priority measures along the A4 are now complete and ready for assessment; however the elements relating to the Brands Hill Park and Ride are not. We remain confident that we can produce a WebTAG-compliant Full Business Case that demonstrates good or better value for money. We have recast our timetable on the basis of financial approval in March 2019 and a start on site in the first quarter of 2019-20. 2.5. Business case currently with Regeneris. SBC expecting to present this to BLTB for the end of January 2019. 2.6. Public consultation on concept designs took place in Jan 2019 2.7. Business case approved by Regeneris January 2019 2.8. Construction start date revised to July 2019

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Amount from LEP Business Rates Rentention £13,300,000 £13,300,000 Local contributions from 0 - Section 106 agreements £0 - Council Capital Programme £0 - Other sources £0 Total Scheme Cost £0 £0 £0 £0 £13,300,000 £0 £13,300,000

4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Delays in approval granted following Limit changes to design scope independent assessment

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Programme Entry Status Jul 2018 BLTB Independent Assessment of FBC Oct-18 Jan-19 Financial Approval from LTB Nov-18 Jan-19 Feasibility work Acquisition of statutory powers Cabinet approve scheme Dec-18 Detailed design Procurement Start of construction Feb-19 Jul-19 Completion of construction Feb-20 Jul-20 One year on evaluation Feb-21 Jul-21 Five years on evaluation Feb-25 Jul-25

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.34 Slough MRT Phase 2 Mar-19 Q4 18/19 1. CORE METRICS Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £10,242,000 £130,000 £0 Funding breakdown Business Rates Rentention £10,242,000 £130,000 s.106 and similar contributions £0 Council Capital Programme £0 Other £0 In-kind resources provided £0 Outcomes Actual to date Planned Jobs connected to the intervention 400 Commercial floorspace constructed (square metres) 5,000 Housing unit starts 2,160 Housing units completed 0

Number of new homes with new or improved fibre optic provision Not known

2. PROJECT SPECIFIC OUTPUTS AND OUTCOMES - to be collected where relevant to the intervention Transport 2.34 Slough MRT Phase 2 Mar-19 Outputs Planning Numbers Actual to date Total length of resurfaced roads TBC Total length of newly built roads 0 Total length of new cycle ways TBC Type of infrastructure Junction improvements, traffic signal enhancement, road widening, bus lanes Type of service improvement Enhanced bus services: greater frequency and reliability, reduced journey times Outcomes Follow on investment at site To be determined Commercial floorspace occupied To be determined Commercial rental values To be determined

7 Further Information for Summary Reports

Page 56 Meeting Date: 14 March 2019 2.35 Reading West Station Upgrade Highlights since last report - Reading West Station was granted programme entry by BLTB in January 2019. - A full business case is expected to be submitted to BLTB in July 2019.

1 The Scheme 1.1. The Reading West Station scheme will deliver an improved passenger experience and multi-modal interchange, including a new station building, highway changes and improvements to platform facilities and the Tilehurst Road entrance.

2 Progress with the scheme 2.1. Reading West Station was granted programme entry by BLTB in February 2019. 2.2. A full business case is expected to be submitted to BLTB in July 2019.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 Total Amount from LEP Local Growth Deal £3,100,000 £3,100,000 Local contributions from £200,000 - Section 106 agreements £200,000 - Council Capital Programme - Other (Network Rail) £940,000 £940,000 Total Scheme Cost £0 £0 £940,000 £200,000 £3,100,000 £0 £4,240,000 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk Delay to programme due to securing necessary consents from Network Rail will be engaged early in the programme to minimise risk of securing consents Network Rail and GWR Utility diversions greater than anticipated Initial enquiries have been made and are managable More detailed cost estimates will be investigated as part of business case development, reviewed throughout programme and contingency built Scheme costs significantly increase. into the overall scheme cost. Works affected by operation of railway and delayed due to potential Proceed to book processions as soon as scheme granted approval. Interchange works away from railway so not affected by the need to secure requirements for possessions. possessions.

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Jul-18 Programme Entry Status Jan-19 Independent Assessment of FBC Oct-19 Financial Approval from LTB Nov-19 Outline Design - Phase 1 (Network Rail) Complete - Phase 2 (RBC) Sep-19 - Phase 3 (GWR) Sep-19 Detailed design - Phase 1 (Network Rail) Complete - Phase 2 (RBC) Jan-20 - Phase 3 (GWR) Jan-20 Acquisition of statutory powers Mar-20 Procurement (Design & build contract) May-20 Start of construction - Phase 1 (Network Rail) Ongoing - Phase 2 (RBC) Mar-20 - Phase 3 (GWR) Jul-20 Completion of construction Sep-21 Project end Sep-21 One year on evaluation Sep-22 Five years on evaluation Sep-26

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.35 Reading West Station Upgrade Mar-19 Q4 18/19

1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £4,240,000 £0 £0 Funding breakdown Local Growth Deal £3,100,000 s.106 and similar contributions £200,000 Council Capital Programme Other £940,000 In-kind resources provided Outcomes Planned Jobs connected to the intervention 11 Commercial floorspace constructed (square metres) 191 Housing unit starts 65 Housing units completed Number of new homes with new or improved fibre optic provision

7. Further Information for Summary Reports

Page 57 Meeting Date: 14 March 2019 2.36 Wokingham: Coppid Beech Park and Ride Highlights since last report

1 The Scheme 1.1.This is a new park and ride site to serve both Wokingham and Bracknell Town Centres as well as a potential bus route for Twyford Station. 2 Progress with the scheme 2.1. Following approval, work is set to commence on the Business Case

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 Total Amount from LEP Local Growth Deal £2,400,000 £2,400,000 Local contributions from £600,000 600,000 - Section 106 agreements - Council Capital Programme - Other (please specify) Total Scheme Cost £0 £0 £0 £0 £3,000,000 £0 £3,000,000 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Programme Entry Status Jan-19 Independent Assessment of FBC Financial Approval from LTB Acquisition of statutory powers Procurement (Design & build contract) Legal Processes (River Crossing Order and Land Appropriation) Land Acquisitions/CPO Detailed design Start of construction (including enabling works and utility diversions) Completion of construction Project end One year on evaluation Five years on evaluation

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme 2.36 Wokingham: Coppid Beech Park and Thames Valley Berkshire LEP Mar-19 Q4 18/19 Ride 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £3,000,000 £0 £0 Funding breakdown Local Growth Deal £2,400,000 s.106 and similar contributions Council Capital Programme £600,000 Other In-kind resources provided Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts Housing units completed Number of new homes with new or improved fibre optic provision

7. Further Information for Summary Reports

Page 58 Meeting Date: 14 March 2019 2.37 Bracknell: A322 A329 Corridor Improvements Highlights since last report

1 The Scheme 1.1.Capacity improvements to two key junctions along the A329/A322 corridor building on schemes delivered through the Local Growth, Pinch Point and National Productivity Investment Funds

2 Progress with the scheme 2.1. Officers are working on devloping the strategic business case to secure full financial approval

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 Total Amount from LEP Local Growth Deal £1,200,000 £1,200,000 Local contributions from - Section 106 agreements - Council Capital Programme £300,000 £300,000 - Other (please specify) Total Scheme Cost £0 £0 £0 £0 £1,500,000 £0 £1,500,000 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Programme Entry Status Jan-19 Independent Assessment of FBC Oct-19 Financial Approval from LTB Nov-19 Acquisition of statutory powers Procurement (Design & build contract) Dec-19 Legal Processes (River Crossing Order and Land Appropriation) Land Acquisitions/CPO Detailed design Jan-20 Start of construction (including enabling works and utility diversions) Jul-20 Completion of construction Mar-21 Project end Apr-21 One year on evaluation Apr-22 Five years on evaluation Apr-26

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme 2.37 Bracknell: A322 A329 Corridor Thames Valley Berkshire LEP Mar-19 Q4 18/19 Improvements 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £1,500,000 £0 £0 Funding breakdown Local Growth Deal £1,200,000 s.106 and similar contributions Council Capital Programme £300,000 Other In-kind resources provided Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts Housing units completed Number of new homes with new or improved fibre optic provision

7. Further Information for Summary Reports

Page 59 Meeting Date: 14 March 2019 2.38 Theale Station Park and Rail Upgrade Highlights since last report

This scheme received programme entry status at the January meeting of the BLTB. An initial project team meeting has taken place to progress the details of delivery and scope out the business case.

1 The Scheme 1.1. The scheme is a joint scheme between GWR and WBC and will deliver station enhancements at Theale to improve sustainable transport interchange, increase parking capacity and enhance customer facilities. Specifically, the scheme will seek to deliver: a new cycle hub for up to 100 bicycles, enhanced multi-modal interchange, increased parking capacity, installation of Electric Vehicle charging points, opening of the new ticket office with fully accessible ticket desk, passenger retail provision, new Ticket Vending Machines, new waiting shelters all alongside aiming to be a carbon neutral station.

1.2 The wider scheme will also deliver the AfA fully accessible bridge and lifts to access to all platforms in conjunction with Network Rail. 1.3 The scheme seeks to unlock significant benefits from investment in rail in the Thames Valley and is an enabler for economic growth. The focus will be to provide a strategic Park & Rail offer at Theale to connect surrounding areas in the Thames Valley to the rail network, providing access to important economic hubs across the Thames Valley and beyond. 2 Progress with the scheme 2.1. The project team made up of representatives from GWR and WBC have met since the scheme was given programme entry status. Plans are progressing to provide further details and scoping of works and to progress with the development of the business case.

3 Funding 3.1 The table below sets out the proposed provisional funding profile for the scheme. Source of funding 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 Total Amount from LEP Local Growth Deal £4,000,000 £4,000,000 Local contributions from GWR (CCIF) £20,000 £20,000 - Council Capital Programme £250,000 £200,000 £450,000 - Other (Network Rail / DfT) £2,000,000 £2,000,000 £4,000,000 Total Scheme Cost £0 £0 £20,000 £0 £6,250,000 £2,200,000 £8,470,000 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk

Timescales for work for LEP / Council funded parts of project conflict Discussions to take place with Network Rail to coordinate project milestones and establish programme alignment. Regular workstream meeting with Network Rail AfA works for installation of lifts and bridge. with NR to be set up.

Much of the work will be delivered under permitted development rights. Early discussions to take place with the Local Planning Authority, Parish Planning permission / notifications rejected Council and other local consultees for any part of the project requiring specific permission. Local discussions are considered important to the project whether or not specific permission is required for the work so this will be programmed by the Project Team. Detailed scoping and cost estimates to be established as early as possible and full details to be assessed through the business case. The work Scheme deliverables not achievable within the project budget on the business case and option assessment in particular will enable the benefits to be maximised for the budget available. Any further opportunities to access additional funding in order to deliver extra benefits will be pursued by the organisations involved.

5 Programme - further details to be added once discussed and agreed by Project Team Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Programme Entry Status Jan-19 Independent Assessment of FBC Dec-19 Financial Approval from LTB Mar-20 Acquisition of statutory powers Procurement (Design & build contract) Legal Processes (River Crossing Order and Land Appropriation) Land Acquisitions/CPO Detailed design Start of construction (including enabling works and utility diversions) Completion of construction Project end One year on evaluation Five years on evaluation

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.38 Theale Station Park and Rail Upgrade Mar-19 Q4 18/19

1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £0 £0 £0 Funding breakdown Local Growth Deal s.106 and similar contributions Council Capital Programme Other In-kind resources provided Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts Housing units completed Number of new homes with new or improved fibre optic provision

7. Further Information for Summary Reports

Scheme was given Programme Entry status in January 2019. Full Business Case expected to be brought to BLTB for full financial approval in March 2020.

Page 60 Meeting Date: 14 March 2019 2.39 Wokingham: Coppid Beech northbound Highlights since last report

1 The Scheme 1.1. Widening of the northbound on-slip at the Coppid Beech (A329(M)/London Road) Junction. 2 Progress with the scheme 2.1. Business case work to commence in April 2019.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 Total Amount from LEP Local Growth Deal £2,322,431 £2,322,431 Local contributions from - Section 106 agreements £29,030 £551,578 £580,608 - Council Capital Programme - Other (please specify) Total Scheme Cost £0 £0 £0 £29,030 £2,874,009 £0 £2,903,039 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk TBC as Business case develops

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Programme Entry Status Jan-19 Independent Assessment of FBC Financial Approval from LTB Acquisition of statutory powers Procurement (Design & build contract) Legal Processes (River Crossing Order and Land Appropriation) Land Acquisitions/CPO Detailed design Start of construction (including enabling works and utility diversions) Completion of construction Project end One year on evaluation Five years on evaluation

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme 2.39 Wokingham: Coppid Beech Thames Valley Berkshire LEP Mar-19 Q4 18/19 northbound 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £0 £0 £0 Funding breakdown Local Growth Deal s.106 and similar contributions Council Capital Programme Other In-kind resources provided Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts Housing units completed Number of new homes with new or improved fibre optic provision

7. Further Information for Summary Reports

Page 61 Meeting Date: 14 March 2019 2.40 Windsor: Town Centre Package Highlights since last report

1 The Scheme 1.1.

2 Progress with the scheme 2.1.

Add next progress item:

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 Total Amount from LEP Local Growth Deal £1,562,500 £1,562,500 Local contributions from - Section 106 agreements - Council Capital Programme - Other (please specify) Total Scheme Cost £0 £0 £0 £0 £1,562,500 £0 £1,562,500 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Programme Entry Status Jan-19 Independent Assessment of FBC Financial Approval from LTB Acquisition of statutory powers Procurement (Design & build contract) Legal Processes (River Crossing Order and Land Appropriation) Land Acquisitions/CPO Detailed design Start of construction (including enabling works and utility diversions) Completion of construction Project end One year on evaluation Five years on evaluation

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme Thames Valley Berkshire LEP 2.40 Windsor: Town Centre Package Mar-19 Q4 18/19

1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £0 £0 £0 Funding breakdown Local Growth Deal s.106 and similar contributions Council Capital Programme Other In-kind resources provided Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts Housing units completed Number of new homes with new or improved fibre optic provision

7. Further Information for Summary Reports

Page 62 Meeting Date: 14 March 2019 2.41 South Wokingham Distributor Road – Eastern Gateway Highlights since last report

1 The Scheme 1.1. Part of the South Wokingham Distributor Road, the Eastern Gateway scheme will comprise of a single carriageway distributor road connecting Montague Park with Waterloo Road, including a new road bridge over the Waterloo rail line. 2 Progress with the scheme 2.1. Business case work to commence in April 2019.

3 Funding 3.1 The table below sets out the proposed funding profile for the scheme. Source of funding 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 Total Amount from Business Rates Retention £5,000,000 £5,000,000 Pilot Local contributions from - Section 106 agreements £519,324 £668,655 £5,449,455 £3,724,727 £600,000 £10,962,161 - Council Capital Programme £0 - Other (please specify) £0 Total Scheme Cost £0 £519,324 £668,655 £10,449,455 £3,724,727 £600,000 £15,962,161 4 Risks The key risks on delivering this Programme Entry scheme and how they will be managed are set out in the table below Risk Management of risk TBC as Business case develops

5 Programme Task Original TimescaleMar-19 Timescale (where changed) Feasibility work Programme Entry Status Jan-19 Independent Assessment of FBC Financial Approval from LTB Acquisition of statutory powers Procurement (Design & build contract) Legal Processes (River Crossing Order and Land Appropriation) Land Acquisitions/CPO Detailed design Start of construction (including enabling works and utility diversions) Completion of construction Project end One year on evaluation Five years on evaluation

6 Growth Deal Reporting Framework 6.1. The following table is an extract from the Growth Deal reporting matrix. The entries made here will be reported on a project by project basis. Growth Deal Schemes: Transport scheme 2.41 South Wokingham Distributor Road – Thames Valley Berkshire LEP Mar-19 Q4 18/19 Eastern Gateway 1. Core Metrics Planning Numbers Actual to date Actual for the quarter Inputs Expenditure £15,962,161 £0 £0 Funding breakdown Business Rates Retention Pilot £5,000,000 s.106 and similar contributions £10,962,161 Council Capital Programme Other In-kind resources provided Outcomes Planned Jobs connected to the intervention Commercial floorspace constructed (square metres) Housing unit starts Housing units completed Number of new homes with new or improved fibre optic provision

7. Further Information for Summary Reports

Page 63 This page is intentionally left blank AGENDA ITEM 5

BERKSHIRE LOCAL TRANSPORT BODY (BLTB)

REPORT TO: BLTB DATE: 14 March 2019

CONTACT OFFICER: Joe Carter, Director of Regeneration, Lead Officer to the BLTB

PART I

Item 5: Financial Approval for 2.29 Wokingham: Winnersh Triangle Park & Ride

Purpose of Report

1. To consider giving financial approval to scheme 2.29 Wokingham: Winnersh Triangle Park and Ride (previously referred to as Wokingham: Winnersh Parkway).

2. The purpose of this scheme is to redevelop the transport links at Winnersh Triangle. The redevelopment will include double-decking the new park and ride site to add at least 250 additional car parking spaces, improvement of the station building including the surrounding area, reorganising the highways layout. These arrangements would complement growth plans of Frazer Centrepoint who are intensifying the use of Winnersh Triangle Business Park.

Recommendation

3. You are recommended to give scheme 2.29 Wokingham: Winnersh Triangle Park and Ride conditional financial approval in the sum of £250,000 in 2019/20 and £2,600,000 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below, subject to meeting the following conditions:

3.1. Either: Provision of clear evidence to justify the different journey time and vehicle operating cost impacts across all user classes Or: Provision of updated VISUM model and TUBA model outputs that demonstrate both positive and consistent impacts across all user classes. 3.2. Provision of benefits sensitivity test outputs for a low growth and reduced P&R occupancy scenario that demonstrate the scheme will continue to represent high value for money from investment under these circumstances. 3.3. Provision of additional evidence to support the commercial case to demonstrate the optimum procurement approaches will be adopted by both Wokingham BC and South Western Railway (SWR). 3.4. Provision of confirmation of SWR management arrangements for delivering the internal station works. 3.5. That the scheme retains high or better value for money once these conditions have been met.

Other Implications

Financial

Page 65 4. Scheme 2.29 Wokingham: Winnersh Triangle Park and Ride is a scheme being funded from the Thames Valley Berkshire Growth Deali. This scheme received funding on the basis of scheme 2.16 Maidenhead Station Access being awarded financial approval for a lesser amount on 16 November 2017 (minute 18a refers)ii.

5. This report recommends that the Wokingham Borough Council be authorised to draw down the capital sum £2,850,000 from the Local Transport Body funding for this scheme, subject to meeting the conditions set out in the recommendation.

6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk Management

7. The risk management arrangements already put in place by the Local Transport Body are as follows:  The Assurance Frameworkiii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes  Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme  The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

8. Slough Borough Council will provide legal support for the BLTB should any questions arise.

Supporting Information

9. The scheme will be carried out by Wokingham Borough Council.

10. The full details of the scheme are available from the Wokingham Borough Council websiteiv. A summary of the key points is given below:

Task Timescale Procurement April 2020 [Car Park Deck] Contractor appointed As above Construction January 2020 [Station Building/Forecourt] / June 2020 [Car Park]

Page 66 Open to public September 2020

Activity Funder Cost (approx) Scheme development Wokingham Borough Council £0.0m Major scheme funding Berkshire Local Transport Body £2.850m Section 106 agreements Developers etc £0.550m Total £3.400m

11.The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of Assurance Frameworkv.

Assurance Framework 2.29 Wokingham: Winnersh Triangle Park & Ride Check list Wokingham Winnersh Triangle Park & Ride will improve the station facilities, more than double the capacity of the adjacent Park and Ride car park and support the development of employment at the Winnersh Triangle Business Park.

The SEP assessment process was used and the scheme was given 25.5 points and ranked No 8 of 28 schemes submitted in for Growth Deal 3 in 2016 Raw Weighted Factor Weighting score score SEP 3 1.5 4.5 Deliverability 2 2.0 4.0 Economic Impact 3 4.0 12.0 TVB area coverage 2 1.5 3.0 Natural Capital 1 0.5 0.5 Social Value 3 0.5 1.5 Total 25.5 Programme Entry status was given by the BLTB on 16 November 2017vi (Minute 18a refers)

The Wokingham Borough Council websitevii holds the latest details of the full business case, including the VfM statement certified by the Step 2: senior responsible officer. Programme Entry: evolution of the Any comments or observations on the scheme received by either TVB scheme from LEP or Wokingham Borough Council have been fully considered during outline proposal to the development of the scheme. full business case, external view on The report of the Independent Assessor is attached at Appendix 1. The the business case, Independent Assessor was asked to report as follows: and independent • Completeness – has the promoter prepared a complete Full assessment (See Business Case submission, when judged against the prevailing paragraphs 15 and advice from the DfT 16) • Accuracy – has the promoter performed the relevant calculations and assessments accurately and without error • Relevance – has the Full Business Case considered all relevant matters, including use of appropriate forecasting models and planning assumptions, and has it included any irrelevant

Page 67 Assurance Framework 2.29 Wokingham: Winnersh Triangle Park & Ride Check list considerations such unduly-optimistic assumptions or out of date modelling data • Value for Money – does the scheme promoter’s Value for Money assessment comply with the prevailing DfT guidance • Evaluation arrangements – has the scheme promoter made provision for appropriate post-implementation evaluation of the scheme. • Remedies – where the independent assessment reveals a gap between the FBC supplied and the standard anticipated by the DfT guidance, then the advice for the LTB should include recommendations for remedial actions required – e.g., collection of further data, sensitivity tests on particular assumptions etc. The Independent Assessor has recommended that in this case Conditional Approval is appropriate. This is on the basis that further evidence is supplied which supports the conclusions reached in the Full Business Case in respect of:

1) Either: Provision of clear evidence to justify the different journey time and vehicle operating cost impacts across all user classes Or: Provision of updated VISUM model and TUBA Model outputs that demonstrate both positive and consistent impacts across all user classes. Step 3: Conditional 2) Provision of benefits sensitivity test outputs for a low growth Approval and reduced P&R occupancy scenario that demonstrate the scheme will continue to represent high value for money from investment under these circumstances. 3) Provision of additional evidence to support the commercial case to demonstrate the optimum procurement approaches will be adopted by both Wokingham BC and SWR. 4) Provision of confirmation of SWR management arrangements for delivering the internal station works. 5) That the scheme retains high or better value for money once these conditions have been met.

Step 4: The scheme has a Benefit- Cost Ratio (BCR) of 4.4 Recommendation of Financial DfT has set thresholds of 2.00 (High VfM) and 4.00 (Very High VfM) Approval and schemes with BCRs above these thresholds can described as - High Value for having High or Very High Value for Money. Money - Support of the Independent assessor Step 5: Formal - Roles: TVB LEP is a part funder of the scheme. Wokingham Agreement Borough Council is the scheme promoter, and is the relevant - roles highway and planning authority. - responsibilities - implementation - Responsibilities: TVB LEP is responsible for allocating the - reporting capital finance in accordance with its Assurance Framework. - auditing Wokingham Borough Council is responsible for all aspects of - timing and the design, risk management, insurance, procurement,

Page 68 Assurance Framework 2.29 Wokingham: Winnersh Triangle Park & Ride Check list triggers for construction and implementation of the scheme, including its payments, responsibilities as highway and planning authority, any other - contributions statutory duties, and any financial or other liabilities arising from from other the scheme. funders, - consequences of - Implementation: In addition to any reporting requirements within delay, Wokingham Borough Council, the scheme promoter will use the - consequences of proforma supplied by TVB LEP to make reports on progress of failure, the implementation of the capital scheme to each meeting of - consequences of the BLTB until the build is complete. In particular, Wokingham change to the Borough Council will report on any change in the size, scope or design or specification of the scheme; and on any substantial savings specification of against the scheme budget whether achieved by such changes the scheme to the size, scope or specification of the scheme, or through - claw back, procurement, or through the efficient implementation of the - evaluation one scheme. and five years on - other conditions - Reporting: The scheme promoter must provide accurate, timely, of Local Growth verified and quality assured quarterly monitoring and forecast Funds data, which relate to defined output and outcome indicators agreed between TVB LEP and government as a condition of the Growth Deal. This scheme will not be required to participate in an evaluation as set out in the Growth Deal Monitoring and Evaluation Plan.

- Auditing: Wokingham Borough Council will keep financial records such that the expenditure on the scheme is readily identifiable, and if and when BEIS, DfT or other government department or the accountable body for TVB LEP requests access to financial or other records for the purposes of an audit of the accounts, Wokingham Borough Council will co-operate fully.

- Timing and Triggers for payments: See the Claim Proforma at Appendix 1 – available on request.

- Contributions from Other Funders: Wokingham Borough Council will contribute £50,000 of s.106 contributions secured in 2019/20 & £500,000 of s.106 contributions in 2020/21. In the event that the scheme experiences or it is anticipated that the scheme will experience a shortfall in these contributions, Wokingham Borough Council will be required to notify TVB LEP of these developments. The provisions of clauses 8, Consequences of Delay; 9, Consequences of Change to the Design or Specification of the Scheme; or 10, Consequences of Failure will then be applied.

- Consequences of Delay: In the event that the scheme experiences minor delays to its overall Business Case programme (no more than 10 weeks), Wokingham Borough Council will report these delays and the reasons for them, and

Page 69 Assurance Framework 2.29 Wokingham: Winnersh Triangle Park & Ride Check list the proposed remedial action to the next available meeting of the BLTB. In the event that the scheme experiences major delays to its overall Business Case programme (11 weeks or longer) Wokingham Borough Council will be required to seek permission from TVB LEP to reschedule any payments that are due or may be delayed in falling due because of the delay to the overall Business Case programme.

- Consequences of Change to the Design or Specification of the Scheme: In the event that Wokingham Borough Council wishes to change the design or specification of the scheme such the scheme delivered will vary in any material aspect from the description given in the overall business case, Wokingham Borough Council will be required to seek prior written consent from TVB LEP. Failing this permission, no further monies will be paid to Wokingham Borough Council after the change becomes apparent to TVB LEP. In addition, consideration will be given to recovering any monies paid to Wokingham Borough Council in respect of this scheme.

- Consequences of Failure: As soon as it becomes apparent to Wokingham Borough Council that it will not be possible to deliver the scheme within the current LGF programme, i.e. by the end of 2020/21, written notice shall be given to the accountable body for TVB LEP. No further monies will be paid to Wokingham Borough Council after this point. In addition, consideration will be given to recovering any monies paid to Wokingham Borough Council in respect of this scheme.

- Claw back: If the overall scheme achieves savings against budget, these savings will be shared by TVB LEP and the other funders noted above in proportion to the amounts set out in the Financial Profile. The accountable body for TVB LEP reserves the right to claw back any amounts of grant that have been spent on purposes other than the scheme as approved and any repayments due as a consequence of changes to the design or specification of the scheme or scheme failure.

- Evaluation One and Five Years On: Wokingham Borough Council will produce scheme evaluations One and Five years after practical completion that comply with DfT guidance.

- Other Conditions of Local Growth Funds: Wokingham Borough Council will acknowledge the financial contribution made to this scheme through Local Growth Funds and follow the ‘Growth Deal Identity Guidelines’ – see link here: http://www.thamesvalleyberkshire.co.uk/getfile/Public%20Docu ments/Strategic%20Economic%20Plan/Logos%20for%20brand ing/GROWTH%20DEAL%20IDENTITY%20GUIDELINES%202 80219.pdf?inline-view=true

Page 70 Assurance Framework 2.29 Wokingham: Winnersh Triangle Park & Ride Check list It will also give due regard to the Equality Act 2010 ‐ Public Sector and with the Public Services (Social Value Act) 2012, particularly through the employment of apprentices across the scheme supply chain.

Conclusion

12. The scheme will redevelop the transport links at Winnersh Triangle and help enable further development at the Winnersh Triangle Business Park.

Background Papers

13. The LTB and SEP scoring exercise papers are available on request ihttps://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/39 8880/35_Thames_Valley_Berkshire_Growth_Deal.pdf ii http://www.slough.gov.uk/moderngov/ieListDocuments.aspx?CId=601&MId=5756&Ver=4 iii http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum iv www.myjourneywokingham.com/discover-wokingham/bus-travel/park-and-ride/ v http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum vi http://www.slough.gov.uk/moderngov/ieListDocuments.aspx?CId=601&MId=5756&Ver=4 vii www.myjourneywokingham.com/discover-wokingham/bus-travel/park-and-ride/

Page 71 This page is intentionally left blank

Independent Assessment Summary Report: Winnersh Triangle Park and Ride

A Final Report by Hatch Regeneris Consulting March 2019

Page 73 Thames Valley Berkshire Local Enterprise Partnership

Independent Assessment Summary Report: Winnersh Triangle Park and Ride

March 2019 www.regeneris.co.uk

Page 74 Winnersh Triangle Park and Ride

Contents Page

Executive Summary 1 Scheme Summary 1 Review Findings 1

1. Introduction 3 Submitted Information 3 Report Structure 3

2. Option Assessment Report 4 Overview 4 Review 5 OAR Additional Information 6 Comments upon OAR Additional Information 6

3. Appraisal Specification Report 7 Overview 7 Review 7

4. Full Business Case 9 Overview 9 Key Input Assumption and Parameters 9 Strategic Case 10 Economic Case 12 Financial Case 14 Commercial Case 15 Management Case 17 Summary and Conclusions 19

Page 75 Winnersh Triangle Park and Ride

Executive Summary i. This technical note provides an independent assessment of the Winnersh Triangle Park and Ride (WTP&R) Scheme Business Case submission to the Thames Valley Berkshire Local Enterprise Partnership (TVB LEP). Scheme Summary ii. The business case submission sets out the case for investment in a series of improvements to the existing Winnersh Triangle Park & Ride facilities. This includes:

• Development of a circa 130-space single deck car park over the existing Winnersh Triangle surface car park site; • Improvements to the station building interior by revamping the passenger waiting area and ticketing office; and • Improvements to the pedestrian amenities in the station forecourt area by moving dropped kerbs and tactile paving to a better location, as well as improving access between the park and ride bus shelter and footbridge Review Findings

Conclusions iii. The overall scheme aligns well with local, TVB LEP, and national strategic priorities to encourage sustainable travel, reduce congestion, and support growth. It has been demonstrated that there are specific constraints at the existing Winnersh Triangle P&R site, in terms of the standard of passenger facilities and the car parking spaces available. iv. The analytical modelling demonstrates both demand for the proposed additional car parking provision and the overall positive impact that removing these trips from the highway network will bring. Some of the disaggregate model outputs do, however, require further explanation in order to understand the impacts of the scheme upon all road users. v. The analysis also demonstrates the positive impact that the additional works to the station buildings and surrounds will have in terms of the improving the quality of the travel experience for passengers and encouraging higher overall rail patronage. vi. The overall economic case demonstrates the scheme will deliver very high value for money, although there are limited tests to demonstrate how sensitive the results are to any changes in external circumstances. vii. The financial case appears reasonably robust, with a quantified risk budget included. Given the way in which the costs have been forecast, and that a competitive contract tendering process is still to be completed, there is the potential for the costs to vary, either up or down. In the event that costs were to rise, confirmation has been sought from WBC that they have a procedure in place to address any cost overruns to ensure the project is delivered. viii. The commercial and management cases are generally considered to be robust but could be enhanced in some areas. This includes providing specific evidence that the design and build contracting approach for the decked car park represents the best procurement option

1 Page 76 Winnersh Triangle Park and Ride

for this element of the scheme, as well as a greater understanding of the approach SWR will take to the internal station works. Additional reference to the management processes for the internal station works to be delivered by SWR are also required.

Recommendations ix. Whilst the overall case for funding appears strong, it is our conclusion that the evidence presented within the business case does not currently permit an unconditional approval of the scheme.

Conditions for Approval x. We recommend that the following series of conditions are applied before the scheme is taken forward:

1) Either: Provide clear evidence to justify the different journey time and vehicle operating cost impacts across all user classes Or: Provide updated VISUM model and TUBA Model outputs that demonstrate both positive and consistent impacts across all user classes. 2) Provide benefits sensitivity test outputs for a low growth and reduced P&R occupancy scenario that demonstrate the scheme will continue to represent high value for money from investment under these circumstances 3) Provide additional evidence to support the commercial case to demonstrate the optimum procurement approaches will be adopted by both WBC and SWR. 4) Provide confirmation of SWR management arrangements for delivering the internal station works 5) That the scheme retains high or better value for money once these conditions have been met

2 Page 77 Winnersh Triangle Park and Ride

1. Introduction

1.1 This report provides an independent assessment of the Full Business Case (FBC) submitted by Wokingham Borough Council (WBC) for the delivery of the Winnersh Triangle Park and Ride (WTP&R) scheme. 1.2 The report considers the evidence presented and whether it represents a robust case for the investment of Thames Valley Berkshire Local Enterprise Partnership (TVB LEP) growth deal funds. 1.3 The independent assessment has applied criteria from TVB LEP assurance framework and the requirements for transport scheme business cases set out within the Department for Transports (DfT) WebTAG. Submitted Information 1.4 The independent assessment process for the WTP&R submission has been conducted on the following set of documentation submitted by WBC and their consultant team (WSP):

• Options Assessment Report (September 2015)

• Appraisal Specification Report (18th December 2018)

• Full Business Case (21st February 2019) 1.5 In addition to these formal documents, Hatch Regeneris have engaged with WBC and their consultants between November 2018 and February 2019 to discuss the requirements of the final business case submission and comment upon the acceptability of the proposed appraisal approach and input assumptions and parameters. Report Structure 1.6 This Independent Assessors Report responds to the formal submission of documentation, as well as the informal engagement process with WBC and their consultants, to provide a review of information provided, assess it suitability and robustness against TVB LEPs assurance requirements, and provide recommendations in relation to the approval of LEP funding for the proposed scheme. 1.7 The report is structure as follows:

• Section 2: Option Assessment Report – provides commentary upon the OAR and the process by which a preferred scheme option has been identified

• Section 3: Appraisal Specification Report – presents a high-level review of the ASR and the acceptability of the proposed appraisal approach to be adopted

• Section 4: Full Business Case Submission – presents a summary of the scheme elements included within the business case submission, alongside the details presented within each of the five ‘cases’ (Strategic, Economic, Financial, Commercial, Management). It also sets out the recommendations to the LEP Local Transport Body relating to the suitability of the scheme for funding.

3 Page 78 Winnersh Triangle Park and Ride

2. Option Assessment Report Overview 2.1 An Options Assessment Report (OAR), dated September 2015, has been reviewed. This sets out the background to the scheme, the study objectives, the strategic context, and the current and potential future use of Winnersh Triangle Station. It summarises a set of identified issues that need to be addressed and establishes the implications of ‘not changing’. 2.2 A set of four strategic transport objectives are then established that relate to the need to provide sustainable transport choices that are accessible to all, and offer a realistic alternative to private car trips. It also establishes the importance of supporting local economic development in Wokingham. 2.3 The OAR then develops and appraises four options for enhancing sustainable transport provision at Winnersh Triangle Station:

• Do Minimum: Name change to include Parkway; and extended ticket office opening hours • Do Minimum + car park extension: Name change to include Parkway; extended ticket office opening hours; and car park expansion (i.e. decked). • Do Minimum + new station buildings/lifts to platform: Name change to include Parkway; construction of accessible toilets; construction of new station building; and lifts to platforms. • Full Station Redevelopment: Name change to include Parkway; construction of accessible toilets; construction of new station building; lifts to platforms; and expanded car park (i.e. decked).

2.4 Each scheme option is appraised against:

• The established Strategic Transport Objectives:

◼ Promoting economic development in Wokingham to support the production of jobs in the local area.

◼ Ensuring sustainable transport is accessible for all types of users.

◼ Enabling a variety of transport choices for the public.

◼ Promoting sustainable transport as an alternative to the car.

• The key LEP Economic Objectives:

◼ Unlocking housing development.

◼ Enhancing urban connectivity.

◼ Encouraging vibrant town centres.

◼ Positioning TVB for a digital future.

◼ Foundations for future growth – housing, transport, utilities.

◼ Enhancing the strategic growth network.

4 Page 79 Winnersh Triangle Park and Ride

2.5 The Do Minimum option was considered not to be a suitable option as it did not meet strategic transport or SEP objectives. The remaining three options were then assessed against a set of deliverability and feasibility criteria:

◼ Infrastructure Feasibility

◼ Operational Feasibility

◼ Property / Land Take Requirements

◼ Environmental Impact (Local)

◼ Complexity of Delivery

◼ Stakeholder acceptance / support

◼ Costs

◼ Benefits

◼ Affordability

2.6 The OAR concludes that the ‘Full Station Redevelopment’ scores the highest in terms of performance against Strategic Transport Objectives and LEP Economic Objectives and it scores joint highest in terms of deliverability and feasibility. On this basis it was identified as the preferred scheme option, albeit that the conclusion also notes that the ‘Do Minimum and car park expansion’ option scores as well as in terms of deliverability and feasibility. Review 2.7 The OAR represents a well set out document, providing a detailed understanding of the underlying issues at Winnersh Triangle Station, as well as the surrounding highway network, and how there is a need to support future employment and housing growth in the area. 2.8 The option generation process is restricted to enhancements to Winnersh Triangle Station itself, as opposed to any alternative transport options that could be provided within the corridor. It is accepted, however, that WBC has a broader local transport strategy that incorporates a number of Park & Ride and Mass Rapid Transit schemes and so the focus of this scheme is on the specific opportunities presented at the station. 2.9 The options presented are relatively strategic in nature, which is considered acceptable for an initial OAR, but means that subsequent scheme development work still needs to consider potential alternative specifications. For example, the options to include an expanded car park do not consider the potential optimal size of the car park provision. 2.10 The OAR concludes that the ‘Full Station Development’ should be taken forward to the full business case. This is primarily upon its ability to deliver against the strategic transport objectives and LEP Economic Objectives. It is ranked 1st on ‘affordability’, which seems a little counterintuitive, as it is the most expensive option, albeit the option with the new station building and lifts will also include the majority of the same costs. 2.11 The FBC will clearly need to demonstrate that all aspects of the ‘Full Station Development’ represent high value for money.

5 Page 80 Winnersh Triangle Park and Ride

OAR Additional Information 2.12 The original OAR was developed in 2015 and in discussion with the Applicant it is understood that, since that time, a range of design options have been considered that have concluded the construction of new station buildings and, in particularly, step-free access to the platforms is prohibitively expensive to deliver at this time. 2.13 It is also understood that South Western Railway (SWR) are unable to commit to increased periods of staffing at the station, at this time. 2.14 The refined preferred scheme option therefore reflects a hybrid version of the ‘Do Minimum + car park extension’ and the ‘Full Station Development’ options and includes an extended (decked) car park, with improvements to the station buildings (passenger waiting areas and ticket office), and improved pedestrian and cyclist amenities outside the station. Comments upon OAR Additional Information 2.15 Whilst the process by which the revisions to the scheme option have been explained, there is no formal update to the OAR process. It is recognised that the revisions have been primarily enforced through current funding availability and that there are still longer-term options to provide step-free access at the Winnersh Triangle Station’. 2.16 In the absence of further scheme optioneering work within the OAR, it will be imperative that the FBC is able to demonstrate that the promoted scheme represents the option for addressing the identified objectives and will represent high/very high value for money from investment.

6 Page 81 Winnersh Triangle Park and Ride

3. Appraisal Specification Report Overview 3.1 A meeting was held with WBC and their consultants (WSP), in November 2018, to discuss the broad approach to developing the business case. 3.2 The Appraisal Specification Report (ASR) was subsequently submitted for assessment in December 2019 and reviewed by Hatch Regeneris. It provided: • An overview of the scheme, its objectives, its location, and then describes the key issues and implications of a ‘do-nothing’ scenario; • A description of the options considered [discussed further within the OAR in Section 2 of this report] and the principal risks and mitigation requirements; • The proposed approach to modelling, including the scenarios to be appraised, a description of the Wokingham Strategic Transport Model 3 (WSTM3) to be used to assess the removal of vehicle trips from the highway network, an overview of the Logit Model used to forecast Park & Ride Mode Share; • The proposed approach to the appraisal, including calculating Transport User Benefits from P&R users and decongestion benefits for road users, revenue impacts, benefits from the station improvements, reliability improvements, wider economic impacts, social & distributional impacts, and environmental impacts; and • An Appraisal Summary Table summarising the appraisal elements included within the assessment.

Review 3.3 The initial discussions with the Applicant in November 2018 identified the focus of the appraisal would be to determine the benefits associated with the removal of car trips from the highway network to instead use the P&R facilities. This approach requires both the ability to forecast the number of person trips that will switch from currently driving to instead travelling by P&R, as well as to then understand the impact this has upon other road users. 3.4 The Applicant identified two mechanisms for conducting the assessment: • The volume of trips that will be removed from the highway network will be assessed using a Logit Model. • The benefits associated with removing car trips from the highway network will be assessed using a strategic highway model.

Logit Model

3.5 The Logit Model will focus upon vehicle trips that currently pass near to the WTP&R site that are travelling into Reading and seek to predict the proportion of them who would choose to use the P&R site instead. Given that there is already a P&R operation from the WTP&R site, this premise only makes sense if the car park at WTP&R is either currently operating at capacity, or will do as a result of future growth, thus restricting the number of vehicles that are able to use the site. The information provided within the ASR supports this premise. 3.6 The Logit Model to be used will be based upon the model developed by WBC for Thames Valley P&R Site. It will provide an assessment of generalised cost of travelling into Reading

7 Page 82 Winnersh Triangle Park and Ride

by private car and by the P&R site, taking into account in-vehicle journey times (including congestion), access times, wait times, and egress times, as well as applying a mode constant to car trips of 10 minutes and a Lambda of 0.04 calibrated from data from the East Reading MRT. The Logit Model will focus on commuting and business trips. 3.7 In general, the proposed Logit Model approach is considered to be an appropriate method for forecasting modal shift from car to P&R. It will be important that any capacity constraints within the P&R car park are taken into consideration.

Strategic Highway Model

3.8 The impact of removing the car trips from the highway model will be assessed using the Wokingham Strategic Transport Model 4 (WSTM4). This has been created within the VISUM modelling software package. It is calibrated and validated to a base year of 2015, with forecast years of 2021, 2026 and 2036. 3.9 The model will assess the reduction in journey times for other road users when commuters and business travellers have switched to using the P&R site. 3.10 The proposed approach is considered acceptable, but it will be important to consider the time periods during which the trips are likely to switch from car to P&R and whether they all occur during peak periods of congestion, in both the AM and PM peak periods.

Appraisal Approach

3.11 The approach outlined to assess the benefits in road decongestion resulting from mode shift from private car trips to P&R use appears broadly acceptable, although care will need to be taken in the detailed assumptions applied. 3.12 The approach appears not to be directly capturing the benefits derived by those travellers who actually switch from car to P&R (and who presumably benefit from a reduction in the overall generalised journey cost of their trip), although some benefits in terms of reduced Vehicle Operating Costs (VOCs) may be captured. It will be important to ensure that these savings are representative, given that P&R users will be subject to P&R charges/fares instead of paying VOCs. 3.13 Forecast reductions in carbon emissions, from reduced car journeys, will be captured in monetary terms, but any potential accident reduction benefits will only be qualitatively assessed, and so is likely to represent a conservative estimate of potential benefits. 3.14 The additional car parking revenue will be captured as part of the assessment but, as with the VOCs, it will be important to ensure that the impacts of car parking charges upon P&R users is adequately captured within the appraisal. 3.15 Benefits from the station improvements will be captured by applying unit monetary values derived through market research work presented within TfL’s Business Case Development Manual and the Rail Industry’s Passenger Demand Handbook. This is considered to be a standard approach. 3.16 Assessments of reliability, wider impacts, social/distributional impacts, and environmental, impacts will be conducted qualitatively but this is considered to be consistent with WebTAG requirements for a scheme of this type and magnitude. There will, however, need to be clear evidence in the FBC that more detailed quantitative assessments of any individual impacts are not required.

8 Page 83 Winnersh Triangle Park and Ride

4. Full Business Case Overview 4.1 The full business case submission sets out the case for investment in a series of improvements to the existing Winnersh Triangle Park & Ride (WTP&R) facilities. This includes: • Development of a circa 130-space single deck car park over the existing Winnersh Triangle surface car park site; • Improvements to the station building interior by revamping the passenger waiting area and ticketing office; and • Improvements to the pedestrian amenities in the station forecourt area by moving dropped kerbs and tactile paving to a better location, as well as improving access between the park and ride bus shelter and footbridge 4.2 The current site has around 390 spaces, so the proposed scheme will represent an increase of around a third in the available parking spaces. 4.3 As well as being a P&R site, Winnersh Triangle Station also serves the adjacent Winnersh Triangle Business Park and so is a destination point for rail trips. The station currently has no customer toilets available and no customer information screens. Staffing is also limited.

Key Input Assumption and Parameters 4.4 The overarching business case is based upon a range of key assumptions, as follows:

• Scheme opening year will be 2021 with benefits being accrued, in full, from the year of opening. • The new car park deck has a minimum life expectancy of 30 years, whilst the benefits from the station improvements are assumed to last for at least 15 years • Traffic decongestion benefits are only assessed during the AM and PM peak hours of travel (08:00 to 09:00, and 17:00 to 18:00) • The profile of new P&R Users will match the current profile in terms of: 70% full fare bus P&R users; full fare 20% Rail P&R users; 10% bus concessionaires • Reading buses will continue to operate the current 15-minute frequency into Reading City Centre (Minster Street) and would increase bus capacities/ frequencies, if required. • 13,000 new homes will be delivered by 2026 within the WBC area, including 4,450 units in the vicinity of Winnersh, North and South Wokingham. 4.5 There is also a commitment from South Western Railway to increase the frequency of their trains serving Winnersh Triangle Station from half-hourly up to every 15 minutes, although this is not explicitly referenced as an input parameter within the business case analysis.

Independent Assessor Comment

4.6 The scheme opening year is compliant with LGF3 requirements and the appraisal periods for the car park decking and station improvement are considered to be consistent with these types of infrastructure projects. The accrual of full benefits from the year of opening is considered to be optimistic and is reliant upon their being constrained demand for car

9 Page 84 Winnersh Triangle Park and Ride

parking provision at the P&R site equivalent to the proposed release of additional car parking spaces. 4.7 The assessment of traffic decongestion benefits during only peak hours of travel is considered to be a robust approach for assessing the impacts, since this is when the highest levels of congestion occur. It will, however, be important to robustly demonstrate the proportion of additional P&R trips that will take place specifically during these time periods. 4.8 In the absence of any separate market testing analysis, the assumption that future P&R users will follow the same profile as current users is considered to be acceptable, albeit the implications for any variance may wish to be tested. 4.9 The assumption that Reading Buses will continue to operate the current frequency of bus services to and from the station, and may increase the capacity if required, is considered to be acceptable, given the letters of support provide by Reading Buses. It would be useful to demonstrate the impact the additional P&R trips may have upon peak period bus loadings and any implications for the requirement for additional bus capacity. 4.10 Given the delivery of 13,000 homes, including 4,450 in the vicinity of Winnersh and Wokingham, is within the adopted Local Plan, it is considered acceptable for this to form part of the assessment of future growth.

Strategic Case 4.11 The Strategic Case describes the background to the scheme and the area, and then provides an overview of the key policy context for the scheme, referencing national, regional and local transport policy. Four key problems are identified that the scheme will aim to address, and each is discussed in detail, in short to: • Congestion – along the A3290 into Reading • Housing growth – 13,000 new homes to be delivered by 2036 across the WBC area, 4,450 within the local catchment of WTP&R • Passenger growth – forecast 0.6% annual growth in rail patronage • Inadequate station facilities – waiting facilities dated and poorly heated, limited customer information screens, limited staffing hours 4.12 The impact of not changing is presented in terms of the increase in highway congestion resulting from housing growth and the lost opportunity to establish Winnersh Triangle P&R as a key transport interchange, with poor facilities and constrained demand. 4.13 Four scheme objectives are presented based around ensuring sustainable transport is accessible to all, enabling a variety of transport options for the public, promoting sustainable travel as an alternative to private car, and promoting economic development. 4.14 The indirect impacts of the scheme are also discussed, in terms of climate change (reduced private car mileage); health (reduced emissions and reduced driver stress); accessibility (access to central Reading); and safety (reduced chance of vehicle accidents). 4.15 The strategic outcomes are presented within a logic chain showing how the outputs lead to direct impacts, indirect impacts, achievement of specified objectives, and strategic outcomes. 4.16 The measures for success are set out in relation to each scheme objective and include an assessment of bus and train patronage, journey times and journey time reliability, employment levels, and housing delivered.

10 Page 85 Winnersh Triangle Park and Ride

4.17 It is stated that no constraints have been identified for the scheme, whilst the only inter- dependencies are stated as relating to securing planning approval, as well as the LGF funding. 4.18 A list of stakeholders who have already been consulted is presented, alongside their key messages relating to the scheme. 4.19 The options assessment process is presented, reiterating the outcomes of the 2015 OAR, but then stating that the preferred option identified by the OAR, the ‘Full Station Redevelopment’ option, has since been deemed prohibitively expensive and subject to engineering challenges, particularly in relation to the provision of step-free access to the station platforms. This has resulted in the scaling down of the scheme to focus primarily upon provision of the decked car park, with smaller-scale works to the existing station buildings and station forecourt. It is noted that the full works remain part of WBC’s long- term aspirations for the station. 4.20 The final scope of the scheme is then set out in detail, with scheme drawings for the car parking deck provided. It has been confirmed that the scheme will not result in increased levels of staffing at the station.

Independent Assessor Comment

4.21 The Strategic Case is considered to provide a clear overview of the issues, objectives, and the preferred solution for enhancing provision at the Winnersh Triangle P&R site. 4.22 The background context provides a useful insight into the history of the scheme and the local geographic area, whist the policy context demonstrates alignment with national, regional and local policy priorities. 4.23 There is a logical presentation of the overarching problems that have been identified both at the station itself, but also along the adjacent A3290 highway corridor that runs into central Reading. Model output data is presented to substantiate the statements made. This is the same with the assessment of impacts of not changing, which present logical arguments for the potential impacts. 4.24 The scheme objectives are clearly set out with associated ‘desired outcomes’. There is considered to be some overlap between the first three objectives, which relate to improving sustainable transport choices, making them attractive to current car users and be accessible to all. The desired outcomes link back to the identified issues, providing assurance that the appraisal process will be focused upon achieving the right outcomes. 4.25 The wider objectives also, generally, relate to the identified issues, although discussions around health and accidents is more implied than explicitly raised as a key issue. The strategic outcomes are well presented within a logic chain diagram and demonstrate how the physical outputs of the scheme are anticipated to provide direct and indirect impacts that lead to the individual strategic outcomes. 4.26 The measures for success are clearly set out and identify a range of metrics that will be used to determine success. These metrics appear reasonable but are generic in nature and there is no definition of the scale of change anticipated that would be considered successful. 4.27 The sections on constraints and inter-dependencies have not identified any likely issues. This appears reasonable based upon our understanding of the scheme and the evidence presented. 4.28 There is clear demonstration that a range of key stakeholders have already been engaged with, including the key transport bus and rail operators from the P&R site.

11 Page 86 Winnersh Triangle Park and Ride

4.29 The section on ‘options considered’ replicates the work presented within the OAR; however, there is limited discussion around the change in scope that has occurred since the identification of the preferred scheme option. It is recognised that cost and engineering constraints were the key factors in scaling down the proposed projects. Ideally, the whole optioneering process would have been re-opened to re-consider the potential scheme options that could be delivered within the identified funding constraints. It is recognised, however, that the car park decking remains the key component of the overall scheme and that this was identified as a strong element within the original optioneering process.

Economic Case 4.30 The Economic Case outlines the approach and parameters used to assess the economic impacts, including the traffic modelling approach and P&R demand forecasting. The scheme costs are also presented, along with environmental, social and wider economic impacts. 4.31 The assessment utilises two core analytical approaches to forecast the additional P&R users that will be generated by the scheme and the subsequent impact of removing vehicle trips from the congested highway network leading into central Reading. 4.32 A Logit Model is used to forecast demand, utilising an assessment of generalised journey time when travelling by private car and by bus P&R into central Reading. This is used to predict the proportion of commuters, business travellers, and other travellers (e.g. leisure) who will use the P&R option instead of the private car option. These proportions are applied to flow bundles generated on the A3290 an A329 Reading Road directly adjacent to the site and reflecting current car trips into central Reading. The model predicts that over 110 trips will choose to travel by bus P&R in 2021 and that this remains broadly constant up to 2036. 4.33 The Wokingham Strategic Transport Model 4 (WSTM4) has been used to assess the impact of removing car trips from the network upon levels of congestion (journey times), vehicle operating costs (fuel / non-fuel) and carbon emissions. Reference is made to the Local Model Validation Report (LMVR) for WSTM4, although no indication of how well the model performs is described, particularly within the specific area of the A3290 and A329 Reading Road corridors. The model covers two single peak hous (8am to 9am, 5pm to 6pm), with forecast models available for 2021 and 2036. The forecast changes in journey times and journey distances from the WSTM4 model have been input into TUBA to estimate the economic impacts. 4.34 The TUBA outputs indicate that, overall, the scheme is forecast to reduce journey times and vehicle operating costs for highway users. The disaggregate outputs, however, suggest that commuters will generate significantly higher benefits than business travellers and people travelling for ‘other’ purposes. 4.35 The station user impacts assess current station demand, taken from the industry dataset MOIRA, and uses historical changes over time to predict future growth in patronage. In addition, elasticities from the rail industry Passenger Demand Forecasting Handbook (PDFH) are used to predict the impact of the station improvements upon further uplift in passenger demand. This predicts that an additional 5 passenger per day will travel by rail as a result of the improvements, which is translated into a monetary benefit from increased farebox revenue. 4.36 Attribute values from Transport for London’s Business Case Development Manual (TfL BCDM) are applied to assess the value of station improvements to existing station users. 4.37 The additional car parking revenue generated by the decked car park is forecast, based upon full occupancy and assuming the same profile of current users.

12 Page 87 Winnersh Triangle Park and Ride

4.38 A summary of investment and maintenance costs is presented, including a discussion of the quantified risk budget applied (equivalent to 12% of investment costs) and optimism bias (applied in the Central Case assessment at a rate of 15%). 4.39 An assessment of environmental impacts is presented covering air quality, noise, landscape, historic environment, biodiversity, and water environment. 4.40 An assessment of other social and economic impacts is presented covering reliability, physical activity, accidents, security, access to services, severance, and wider impacts upon the economy. 4.41 Formal assessments of direct economic impacts are presented within tables of Transport Economic Efficiency (TEE), Public Accounts (PA), and Analysis of Monetised Costs and Benefits (AMCB). The information presented indicates the overall scheme is forecast to deliver a monetised Benefit Cost Ratio of 4.4 to 1. This would represent very high value for money. 4.42 Cost sensitivity testing is presented with optimism bias set at 44% (as opposed to 15%), which demonstrates the scheme would still deliver high value for money from investment, even with these higher costs. 4.43 No benefits sensitivity testing results are provided. 4.44 A clear value for money statement is also provided setting out an overview of the scheme direct scheme benefits and costs, as well broader non-monetised scheme impacts. An Appraisal Summary Table (AST) has also been completed and included within the appendices.

Independent Assessor Comment

4.45 The overarching process for forecasting demand using the generalised cost Logit Model is considered robust. The input parameters used have been discussed with the Applicant, revised and have now been verified. The forecasts of P&R usage are, therefore, considered appropriate to use within the appraisal. For the selected ‘bundles’ of trips passing by the Winnersh Triangle P&R site travelling into central Reading, the model predicts between 45% and 55% of the selected trips will switch from car travel to use the P&R service. Whilst this is a relatively high proportion, it is for a relatively select group of trips travelling directly past the WTP&R site into central Reading. 4.46 The use of the WSTM4 model to assess the impact of reduced vehicle trips is considered an appropriate tool. Whilst no specific information is presented around the local calibration and validation of the model, reference is provided to the LMVR and so it is presumed that the model meets WebTAG requirements. It is understood the 110 vehicle trips are removed from the ‘flow bundle’ of trips passing directly by the Winnersh Triangle P&R site travelling into central Reading. This is considered to be an appropriate approach. 4.47 The direct transport benefits that are ‘captured’ within the FBC relate to the journey time and vehicle operating cost savings experienced by travellers continuing to use the highway network. Whilst the overall forecast impacts are positive, assessing these impacts by individual trips purposes (business/commuter/ other) indicates that the impacts are not consistent across the groups. This requires further explanation. 4.48 The assessment of direct impacts does not include the benefits derived by those individuals who switch to use the P&R, although some of these benefits will be captured through reduce vehicle operating costs. 4.49 The use of PDFH to assess the impact of improvements in station facilities upon the uplift in passenger demand is considered an acceptable standard industry approach. The

13 Page 88 Winnersh Triangle Park and Ride

capture of the full additional farebox revenue for these passengers is considered acceptable on the premise that there are no additional rail operating costs. 4.50 The use attribute values from TfL’s BCDM to value station improvements for existing station users is considered an acceptable standard industry approach. 4.51 The assessment of additional car parking revenue is considered acceptable, although it would be useful to understand the impact of lower car park occupancy levels in line with current occupancy rates (85%). 4.52 The investment and maintenance costs are clearly presented, although there are considered to be some uncertainties in the way the costs have been generated (see section on Financial Case below). The approach to assessing the quantified risk budget is considered robust, although the percentage value of 12% is potentially low given some of the uncertainties with the investment costs. Similarly, the application of an optimism bias of only 15% appears low, given no detailed schedule of costs is available; however, it is noted that a sensitivity has been undertaken with 44% optimism bias. 4.53 The assessment of environmental impacts has been undertaken qualitatively and concludes that all impacts will be neutral. This is considered appropriate given the scale of the scheme and the nature of the infrastructure enhancement that is being delivered on the existing footprint of the station and park and ride site. 4.54 The assessment of social impacts and wider impact has been undertaken qualitatively and concludes that the impacts across the elements will generally be slight positive (the exception being physical activity where the impact is considered neutral). All of these forecasted outcomes are considered to be appropriate. 4.55 The TEE, PA, and ACMB tables have all be completed, as required. Whilst the overall outcomes appear valid, some of the individual impacts upon user groups needs to be investigated further (this relates to the issues discussed in paragraph 4.47). 4.56 The cost sensitivity test provides a useful assessment of the impact of applying a higher level of optimism bias. Given some of the uncertainties around the cost of the car park decking, it is a positive outcome for the economic case that the value for money remains high even when a higher optimism bias is applied. 4.57 The absence of any benefit sensitivity test means we are unable to comment upon the potential impact of lower growth or lower P&R usage. Whilst it is considered highly unlikely that this will result in the value for money falling below 2 to 1, these tests still need to be completed 4.58 The Appraisal Summary Table provides a sufficient summary of the impacts, not withstanding the earlier issues identified with some of the disaggregate outputs (as discussed in paragraph 4.47 and 4.55)

Financial Case 4.59 The Financial Case provides details of the schemes anticipated costs, as well as the budgets and funding cover. 4.60 The estimated total cost of the scheme is £3.37m in 2018 prices, of which around £264,500 relates to the station improvement work and pedestrian crossing and £2.645m relates to the delivery of the decked car park. A further £102,000 is allowed for design and supervision and the quantified risk assessment has identified the need for a risk contingency of around £363,000.

14 Page 89 Winnersh Triangle Park and Ride

4.61 The costs for the decked car parking have been built up from a unit ‘price per space’ supplied by a specialist contractor and comprises the complete civils package for design and build, including CCTV. 4.62 The cost of the station facility upgrade has been provided by South Western Railway, inclusive of preparation and management costs. The costs of the pedestrian crossing facility have been provided by WBC. 4.63 All costs have been adjusted for inflation. 4.64 The profile of total scheme costs is £306,744 in 2019/20 and £3,067,808 in 2020/21. 4.65 Maintenance costs for the additional car parking spaces have been estimated at £100/space. Maintenance for the other elements are considered negligible and can be accommodated within existing maintenance budgets for the site. 4.66 The scheme is seeking £2,824,552 from LGF funds, with an additional S106 contribution of £550,000, which has already been secured. Independent Assessor Comment

4.67 The majority of the scheme costs relate to the additional decked car parking provision. These have been developed based upon a unit price per space provided by a specialist contractor. This approach to cost estimation, whilst acceptable for early stage scheme assessments, is not considered to be fully robust and it is conceivable that it could be subject to notable variation. WBC have, separately, provided further assurance over the accuracy of the scheme costs and a signed letter from the Section 151 Officer demonstrates the procedure that would be undertaken in the event of costs exceeding overall budget availability. 4.68 No specific details are presented on how the other scheme elements have been costed, other than the internal station elements have been costed by SWT and the pedestrian crossing by WBC. These elements represent a relatively small proportion of the total scheme budget. 4.69 The quantified risk budget represents around 12% of the overall scheme costs (including design and supervision). Whilst this has been based upon a detail risk assessment process, the value, itself, it is not considered to be a significant contingency given some of the potential uncertainties around the car park decking costs. 4.70 An allowance for on-going maintenance of the decked car park in included and is stated as being based upon typical maintenance costs for the site. It is unclear whether the decked structure is likely to add any additional maintenance requirements, in comparison to the current surface car park. It seems reasonable to assume the other construction elements will have negligible impact upon the overall current maintenance of the station and forecourt area. Commercial Case 4.71 The Commercial Case provides an output-based specification for the scheme, an overall procurement strategy, the sourcing options and payment/charging mechanisms, as well as a broad discussion of the risk allocation and management processes. Issues around human resource management and contract management are also addressed. 4.72 The output-based specification identifies the outcomes which the procurement strategy must address, including costs certainty, minimisation of preparation costs, assurance of contractor experience, and establishment of contractor risk allocations. In addition, the specification also defines the scheme outputs that the preferred procurement solution must ultimately deliver.

15 Page 90 Winnersh Triangle Park and Ride

4.73 The procurement strategy establishes that WBC will have responsibility for procurement and contract management. As responsibility for station infrastructure rests with South Western Railway (SWR) the station infrastructure works will be undertaken through SWR’s standard procurement routes. The construction of the pedestrian crossing facility will be undertaken by VolkerHighways, WBC term contractor. The specialist nature of the car park decking has led to the conclusion that a full tendering process will be undertaken to identify a specialist contractor as a design and build contract. 4.74 The sourcing options for procurement are stated to utilise standard procurement procedures and follow a tendering process. 4.75 The payment mechanisms will be based on specific task orders on a target price arrangement and awarded based on the NEC contract model. 4.76 Risks will be minimised through the contracting process, with the contract being based on a schedule or rates, rather than a fixed price, so as to reduce the level of risk allocated to the contractor and, hence, reduce the overall price they will quote. 4.77 A Risk Management Plan will be developed throughout the life of the project and will set out the process and responsibilities for updating risk management. The risk management organisation will consist of the Project Board and the Risk Owner. WBC will act as the Project Sponsor. The roles of the Project Board and Project Manager in relation to risk management are set out. 4.78 A series of key project risks are identified along with mitigation measures. These are categorised as ‘planning/approval risks and mitigation’; ‘cost risks and mitigation’; and ‘delivery risks and mitigation’. 4.79 No specific human resource issues are identified, although the contractor’s ability to resource the project effectively will be scrutinised during the procurement stage. 4.80 The contract lengths for delivery will be from Q2 2019 to Q3 2020. 4.81 The station improvements contract management will be the responsibility of SWR. For the parking deck, the contract will follow a design and build NEC4 format and contractual /commercial arrangements will be well-defined. The pedestrian crossing, and ancillary works, will be managed by WBC.

Independent Assessor Comment

4.82 The Commercial Case broadly covers that required range of elements; however, the level of detail provided, particularly in relation to the procurement processes, is considered limited. 4.83 The outputs-based specification is well set out, establishing both the requirements of the procurement process but also clearly setting out the outputs that the contracts will need to deliver. 4.84 The procurement strategy provides a broad outline of the procurement process and identifies the approach to procuring contractors for the three distinct elements of work: ii) internal station works; ii) external station highway and public realm works; and iii) the decked car park. It does not, however, establish the potential full range of procurement options and why the selected options will represent the optimum solution and best value for money. 4.85 There is no discussion of how procuring three separate contractors to complete the work will be advantageous or otherwise, although it is noted that the decked car park is, by far, the most significant construction element. The Commercial Case should present the evidence for how the preferred procurement strategy has been selected, particularly for the decked car park element.

16 Page 91 Winnersh Triangle Park and Ride

4.86 The sections on sourcing options and payment mechanisms provide some information but are relatively limited in scope. 4.87 There is a reasonably detailed amount of information in relation to risk allocations and management, that provides a useful understanding of how it is anticipated that risks will be allocated between parties and managed. It is not clear whether all three elements will follow similar protocols and, in particularly, there is relatively limited information related to the works to be conducted by SWR and their protocols. 4.88 It is acknowledged that human resource issues will be minimal, and the contract lengths set out appear reasonable although, again, it is not clear whether this applies to all three elements of construction works. 4.89 There is a broad overview of contract management responsibilities, but the details presented are relatively limited.

Management Case 4.90 The Management Case presents information on how the proposal will be delivered and managed. 4.91 Examples of similar projects that WBC has successfully delivered are presented, including a detailed description of another Park & Ride scheme recently completed. 4.92 Project dependencies are discussed, albeit the scheme is relatively free from dependencies, being an existing P&R facility owned by WBC. The car park decking element requires planning permission, however, the principle of the scheme has long been established in planning policy and strategic transport plans. In addition, the application for the original Winnersh Triangle P&R site did not identify any issues of not. The planning risk is, therefore, considered by the Applicant to be low. 4.93 An organisational governance structure is provided, demonstrating key roles and reporting lines. The responsibilities of the Project Board are set out, as well as the Project Manager (who is named). 4.94 A communications and stakeholder management plan is presented with key objectives established, along with the identification of the main stakeholders. A summary of engagement activities already undertaken by WBC is presented and reference made to letters of support. 4.95 A project programme has been developed, with key milestones, timescales and tasks, although it is relatively high-level in nature. 4.96 An assurance and approvals plan sets out the expectation of applying a ‘Gateway Process’ as a mechanism for assessing the project at critical stages in its lifecycle, although the actual ‘Gateways’ are not identified. 4.97 The various responsibilities for reporting are outlined to ensure that the Project Board and Elected Members are kept informed. 4.98 A live risk register contains a full set of key issues for implementation, along with planned mitigation. 4.99 Contract Management aspects are presented for the three elements of the project with WBC taking overall responsibility and leading on the external station works and car park decking and SWR leading on the internal station works. 4.100 A risk management strategy is presented that set out the process by which risks will be managed and refers to the risk register that has been developed and informed through a Quantified Risk Assessment (QRA) workshop undertaken in January 2019.

17 Page 92 Winnersh Triangle Park and Ride

4.101 A benefits realisation strategy is presented setting out the responsibilities for realisation of benefits and the components element to the process. The scheme objectives, outcomes and impacts are set out and how the monitoring of benefits realisation will be controlled. There is also a broad discussion of contingency planning, albeit at a relative high-level. 4.102 A detailed monitoring and evaluation plan sets out a three-stage approach, relating to pre-construction baseline, and 1-year, and 5-year post-evaluation. The evaluation will consider ‘process evaluation: efficiency of scheme delivery’; ‘impact evaluation: delivery of projected outcomes’; and ‘economic evaluation: accountability for investment’. A detailed assessment programme for all three elements is presented and how these will be used to answer a summary set of key evaluation questions and a set of evaluation metrics, both which are set out. Independent Assessor Comment

4.103 The previous project examples demonstrate WBC’s ability to deliver projects of this type, including specific P&R schemes. It is not explicitly stated the experience of SWR or VolkerHighways in delivering the specific elements of the project that they will be responsible for. However, given the scale of these works, it is assumed that these will represent standard projects. 4.104 The project dependencies are well presented and demonstrate that there are few dependencies and that the risks associated with planning requirements are very low. 4.105 The governance structure is clear, with responsibilities outlined. 4.106 The communications and stakeholder engagement plan demonstrates a comprehensive approach and that engagement work has already commenced. 4.107 The project programme is relatively high-level, and will need to be developed further, but provides sufficient confidence that there is a broad understanding of the overall project timeframes. 4.108 The assurance and approvals plan provides an overall structure, referring to a ‘Gateway Process’ but there is limited detail about when these ‘gateways’ will be. 4.109 The summary of reporting is considered to provide sufficient information and the key issues for implementation are identified within the risk register. 4.110 The overview of the contract management process is relatively high-level and only really discusses responsibilities, as opposed to processes. 4.111 The risk management strategy and risk register are considered to be well structured and transparent and demonstrate sufficient considerations of risk and mitigation measures. 4.112 The benefits realisation plan provides a good structure for determining whether benefits are being delivered, but it does not focus upon any pre-emptive approaches to ensure that maximum benefits are realised from the investment. 4.113 The monitoring and evaluation plan is considered to be well structured and relatively comprehensive. Whilst a range of evaluation metrics are identified, these are not translated into specific targets.

18 Page 93 Winnersh Triangle Park and Ride

Summary and Conclusions

Summary

4.114 The review of the five cases has identified a series of points for further consideration. These are summarised below: • The Strategic Case demonstrates good policy alignment and provides a clear case for the intervention to encourage sustainable travel, reduce highway congestion leading into central Reading, and support local housing growth. The need to enhance provision at the current Winnersh Triangle Station is established, in terms of enhanced passenger facilities, as well as the capacity of parking provision. • A range of options for improvements at the station are presented, with a clear framework demonstrating how an optimum solution was initially selected. This includes complete re-development of the station buildings and step-free access to platforms. Ultimately, it is not this initial preferred option that has taken forward within the full business case process, as it was deemed that insufficient funds were available, at this time, to complete all of the proposed works. The final solution proposed represents a scaled-down version and excludes complete re-development of the station buildings, step-free access to platforms, and extended ticket office opening hours. These elements remain a longer-term aspiration. • The overall Economic Case for the scheme appears strong. The forecast transfer of travellers from car to P&R delivers decongestion benefits to the highway network and the improvements in and around the station buildings result in journey quality benefits and projected increases in rail patronage. Some of the disaggregate impacts upon individual highway users are not clearly explained and requires further information to be provided. Additional tests on the sensitivity of the results to changing external circumstances are also required. • The scheme will deliver a range of benefits in terms of environmental and social impacts, and support wider economic growth, through increased sustainable travel opportunities. • The Financial Case presents a clear overview of scheme costs and funding profiles. The car park decking costs are built up from a unit cost price per space, provided by an independent specialist supplier. A Quantified Risk Budget representing 12% of overall scheme costs has been added. Typically, we would require a more detailed breakdown of scheme costs within a FBC; however, such is the modular nature of a car park decking scheme, these cost estimate are considered likely to be relatively accurate. Furthermore, assurances has been sought from the Applicant to verify both these cost and to confirm the process by which any cost overruns will be covered. • The costs for the internal station work have been provided by South Western Railway, whilst the costs for external pedestrian improvement works have been developed by WBC. Neither have provided a detailed breakdown of the cost elements, but confirmation is provided that they include preparation, management and supervision costs. • The Commercial Case is reasonably detailed but could elaborate on a few aspects to strengthen and provide additional assurance. Whilst a clear procurement approach is set out, there is no overarching discussion of any potential alternative approaches that may have been considered and/or how the preferred approach was selected.

19 Page 94 Winnersh Triangle Park and Ride

• The Management Case presents sufficient detail to provide overall assurance in relation to the delivery of the scheme. It focuses primarily upon the processes to be employed by WBC in the management of the car park decking and external station pedestrian improvements, with limited reference to SWR procedures. It is, however, acknowledged that the SWR works will make up a relatively small element of the overall project. Whilst a project programme is provided, it is relatively high level in nature. It indicates that the internal and external station works will be completed by April 2020 and the decked car park will open before the end of December 2020. Conclusions

4.115 The overall scheme aligns well with local, TVB LEP, and national strategic priorities to encourage sustainable travel, reduce congestion, and support growth. It has been demonstrated that there are specific constraints at the existing Winnersh Triangle P&R site, in terms of the standard of passenger facilities and the car parking spaces available. 4.116 The analytical modelling demonstrates both demand for the proposed additional car parking provision and the overall positive impact that removing these trips from the highway network will bring. Some of the disaggregate model outputs do, however, require further explanation in order to understand the impacts of the scheme upon all road users. 4.117 The analysis also demonstrates the positive impact that the additional works to the station buildings and surrounds will have in terms of the improving the quality of the travel experience for passengers and encouraging higher overall rail patronage. 4.118 The overall economic case demonstrates the scheme will deliver very high value for money, although there are limited tests to demonstrate how sensitive the results are to any changes in external circumstances. 4.119 The financial case appears reasonably robust, with a quantified risk budget included. Given the way in which the costs have been forecast, and that a competitive contract tendering process is still to be completed, there is the potential for the costs to vary, either up or down. In the event that costs were to rise, confirmation has been sought from WBC that they have a procedure in place to address any cost overruns to ensure the project is delivered. 4.120 The commercial and management cases are generally considered to be robust but could be enhanced in some areas. This includes providing specific evidence that the design and build contracting approach for the decked car park represents the best procurement option for this element of the scheme, as well as a greater understanding of the approach SWR will take to the internal station works. Additional reference to the management processes for the internal station works to be delivered by SWR are also required. 4.121 It is our conclusion that whilst there appears to be strong overarching case for the scheme, there are currently too many uncertainties within the business case to permit an unconditional approval of the scheme.

20 Page 95 Winnersh Triangle Park and Ride

Conditions for Approval

4.122 We recommend that the following series of conditions are applied before the scheme is taken forward: 1) Either: Provide clear evidence to justify the different journey time and vehicle operating cost impacts across all user classes Or: Provide updated VISUM model and TUBA Model outputs that demonstrate both positive and consistent impacts across all user classes. 2) Provide benefits sensitivity test outputs for a low growth and reduced P&R occupancy scenario that demonstrate the scheme will continue to represent high value for money from investment under these circumstances 3) Provide additional evidence to support the commercial case to demonstrate the optimum procurement approaches will be adopted by both WBC and SWR. 4) Provide confirmation of SWR management arrangements for delivering the internal station works 5) That the scheme retains high or better value for money once these conditions have been met

21 Page 96

www.regeneris.co.uk London: 0207 336 6188 Manchester: 0161 234 9910 Page 97 This page is intentionally left blank AGENDA ITEM 6

BERKSHIRE LOCAL TRANSPORT BODY (BLTB)

REPORT TO: BLTB DATE: 14 March 2019

CONTACT OFFICER: Joe Carter, Director of Regeneration, Slough Borough Council, lead officer to BLTB

PART I

Item 6: 2.19 Bracknell: Town Centre Regeneration – One Year Impact Report

Purpose of Report

1. At your meeting in March 2017, you approved guidance for the preparation of one- and five-year-on impact reports for BLTB funded local transport schemes.

2. This report introduces the impact report for scheme 2.19 Bracknell: Town Centre Regeneration.

Recommendation

3. You are recommended to note the reports from the scheme promoter and the independent assessor.

Other Implications

Financial

4. There are no direct financial implications of this report.

Risk Management

5. The government requires all LEPs to have Assurance Frameworks which set out governance arrangements and financial procedures. One of the specific requirements for transport schemes is to require scheme promoters to submit impact reports one and five years post implementation.

Human Rights Act and Other Legal Implications

6. Slough Borough Council will provide legal support for the BLTB should any questions arise on the application of the Assurance Framework.

Supporting Information

7. Bracknell Forest Council received £2m towards the £6.382m cost of this scheme. Therefore, it has been treated as a “small” scheme being under the £5m threshold.

8. The one-year on impact report is attached at Appendix 1; and the independent assessor’s report is attached at Appendix 2.

Item 6: 2.19 Bracknell: Town Centre Regeneration – One Year Impact Report Page 99 Conclusion

9. There is no further action required

Background Papers

None.

Page 100 Appendix 1

Bracknell Town Centre Regeneration

12 Month Evaluation Report

Page 101 1.0 Introduction

1.1 Background

1.1.1 Bracknell Town Centre is located in the heart of Bracknell Forest, approximately 45km west of central London and 16km east of Reading. The A329(M) / A322 corridor between Reading and the M3 at Bagshot passes 0.5km to the south of the town centre and the M4 passes within 7km with access via junction 10.

1.1.2 The town is a major employment centre within the South-East, and is also conveniently situated for both Heathrow and, to a lesser extent, Gatwick airports. Our location is perfect for movement in and around the Thames Valley area which is a major economical hub with the UK and has led to some global brands including Fujitsu, Hewlett Packard, Waitrose, TRL, Syngenta and 3M locating their regional and UK headquarters here.

1.1.3 Regenerating the town’s retail centre is of vital economic importance for maintaining the long term viability of this employment base through supporting the Borough Council’s growing residential population and associated housing growth, both of which underpin economic growth.

1.1.4 The highway changes, improved public realm, new and enhanced walk / cycle connections and the improved transport information technologies that were proposed all assisted in underpinning this economically important regeneration of the retail centre.

1.1.5 The Bracknell Town Centre scheme comprised the demolition of buildings and the redevelopment of the area for a mix of uses, including retail, food and drink, leisure, residential, community and business uses. To support the redevelopment, the planning application proposed a number of transport improvements, including the public realm and junction enhancement schemes.

1.1.6 Bracknell Forest Council received £2,000,000 from the Local Growth Fund towards the various highway network and public realm improvements. Additional funding was provided by Bracknell Forest Council via S106 agreements and capital funds, making an overall total of £6,382,000 for the delivery of the schemes. This report evaluates the success of the project, and the impact of the regenerated Town Centre following its opening in Sept 2017.

Page 102 1.2 Baseline demand in the Town Centre

1.2.1 Following the original redevelopment scheme, and the 2012 update to the regeneration proposals, improvements would be required on the local highway network and to the Town Centre’s public realm to support the additional trips and footfall that the improvements were projected to attract.

1.2.2 The local highway network and public realm improvements consisted of:

 Millennium Way signal controlled junction - provision of a new all movement signal controlled junction serving the multi-storey car park associated with the northern development zone, incorporating a new pedestrian / cycle crossing facility and forming part of a new route between Bull Lane and the Met Office roundabout;

 Weather Way - re-alignment of The Ring (north) providing access to the northern retail quarter;

 Met Office Roundabout and Station Roundabout – capacity / operational improvements;

 Bond Way - provision of a new drop off / collection point and also covered cycle parking facilities;

 Conventional Advanced Directional Signing (ADS) - revisions for surrounding network routing, including car parks and service yards improving movement on the network and reducing delay;

 Variable message signing (VMS) - further urban traffic control capability applying to Variable Message Signing for Town Centre car parks - enabling greater co-ordination and management and maximising car park occupancy;

 Real Time Bus Information (RTI) - providing further RTI displays at key stops linked to the Town Centre;

 Urban Traffic Management Control (UTMC) system - further urban traffic control capability at key traffic signal junctions relating to the Town Centre and enabling greater co-ordination, control and congestion management;

Page 103  Cycle and pedestrian facilities improvements - planting, lighting, resurface cycleway and adjacent carriageway - providing a new route into the heart of the Town Centre for pedestrians and cycles. Continuation of the new pedestrian / cycle route by crossing The Ring and linking with recent improvements at the bus and train stations, and

 Charles Square service yard / multi-storey car park / hotel entrance improvements - new junction providing access to key services including new toucan crossing across The Ring connecting to existing pedestrian / cycle network serving the Town Centre and wider area.

1.2.3 This report has been prepared to evaluate the 12 month performance of the local highway network and public realm improvements since the opening of the Lexicon.

1.2.4 It has been prepared in line with the Department for Transport Guidance ‘Monitoring and Evaluating Framework for Local Authority Major Schemes’ September 2012, and in agreement with Thames Valley Berkshire Local Enterprise Partnership.

1.3 Report Structure

1.3.1 The report has been split into eight sections as detailed in section 3 of the aforementioned guidance;

 Scheme Build;

 Delivered Scheme;

 Costs;

 Scheme Objectives and Monitoring;

 Travel Demand;

 Urban Traffic Control and Variable Message Signage, and

 Impacts on the Economy.

1.3.2 The report then summarises the overall impacts in the final section.

Page 104 2.0 Scheme Build

2.1 Highway Works

2.1.1 The off-site highway works followed a programme spanning from March 2015 to February 2017.

2.1.2 The project programme ran as follows;

 Millennium Way – March 2015 to November 2015;

 Weather Way – March 2015 to April 2016;

 Bond Way - June 2015 to April 2016;

 Met Office Roundabout – July 2015 to February 2016;

 Station Roundabout – September 2015 to February 2017, and

 High Street West – December 2015 to July 2016

2.1.3 Each of these programmed elements included detailed design of the various schemes and the post completion Stage 3 Road Safety Audit.

2.1.4 The overall build programme for the Town Centre was delayed by six months due to the many factors involved in such a complex build. However the supporting transport infrastructure funded through the Local Growth Fund was completed ahead of schedule. This allowed us time to optimise traffic controlled junctions, car park management, sustainable links and the running of extended bus services all ahead of opening day in September 2017.

2.2 VMS, ADS and UTMC

2.2.1 The advanced directional signage was updated as a result of the construction of the Town Centre at all of the main approaches to the Town Centre between June 2017 and July 2017.

2.2.2 The Variable Message Signs were installed during the two month period between April 2017 and June 2017.

2.2.3 UTMC improvements were undertaken over the whole construction period between March 2015 and February 2017.

Page 105 2.2.4 These improvements are discussed further in Section 7 of this report.

2.3 Charles Square Access

2.3.1 The revised access to Charles Square car park was installed during the three month period of March 2016 to June 2016.

2.3.2 The works entailed construction of a new junction providing access to key services including a new toucan crossing across The Ring that connects to existing pedestrian / cycle networks serving the Town Centre and the wider area.

Page 106 3.0 Delivered Schemes

The Avenue Car Park

The Canyon

Page 107 Toucan Crossing on The Canyon

Eagle Lane

Page 108 The Avenue

Bull Square

Page 109 Braccan Walk

The Avenue

Page 110 Town Centre Cycle Parking

Charles Square Access

Page 111 VMS signage at Station Roundabout

Page 112 4.0 Costs

4.1 The local contribution was made up from LTP grant, developer Section 106 funds, and a substantial amount drawn from the Borough Council’s capital programme.

4.2 Securing funds through the Growth Deal not only helped accelerate the Town Centre regeneration by removing some financial burden on the Borough and developers, but it also allowed the authority to allocate funds to schemes aimed at bringing forward further developments, attracting businesses to the area and bringing economic growth to Bracknell and the Thames Valley.

4.3 The business case for funding was broken down as detailed in Table 4.1.

Table 4.1 – Project Funding Breakdown

Source of Funding Total

Amount from LEP Local Growth Deal £2,000,000

BFC Capital Programme £3,619,000

Developer Funding £763,000

Total Scheme Cost £6,382,000

4.4 A quantified risk assessment and Monte Carlo simulation were undertaken for key risks identified in the business case. The risk register contained all risks associated with the scheme including where any potential overspend had been identified. It provided a forecast probability of each risk occurring and defines a range of probable costs which may be incurred in that instance.

4.5 A cumulative distribution for the forecast risk was prepared. From this distribution, a mean value was extracted for both pre and post mitigation (£543,315 pre and £84,565 post) and added to the costs of appraisal. The P(80) value for both pre and post mitigation (£709,841 pre and £188,027 post) was also assessed for the outturn cost calculation for the financial assessment.

4.6 Although the business case stated that overrun costs would be covered by the Local Authority, the relatively small overspend was in fact covered by the developer following negotiations during the early stages of construction.

Page 113 4.7 The final spend for the project came out at £6,393,696. This presented a very modest overspend of approximately £12,000, which was covered by developer funding.

Page 114 5.0 Scheme Objectives and Monitoring

5.1 Objectives

5.1.1 The original objectives of the schemes were to achieve the following;

 Improve journey times, reliability and journey quality for all road users

 Improve accessibility to Bracknell Town Centre for pedestrians, cyclists and road users

 Reduce congestion and its environmental impacts

 Improve access to Bracknell train station

 Enhance the viability of the town centre, support Economic Development and other key areas

5.1.2 The schemes have improved access to the Town Centre by providing management of movement and introducing better way-finding measures to reduce delays at junctions, particularly Market Street which had been predicted to operate with significant levels of queuing and delay.

5.1.3 The schemes did not require third party land and were within the extent of adopted highway and therefore did not require planning approval.

5.1.4 The schemes were relatively small in scale with a limited scope of works and no complexity in terms of construction tasks, site access etc.

5.1.5 Some of the work was able to be undertaken off-line, simplifying the traffic management issues.

5.1.6 Overall, the identified risks associated with delivering the projects were considered to be straightforward and manageable. The scheme was delivered through well- understood management practices with the main works of the project secured through the Council’s highways term contract, simplifying the procurement process and demonstrating value for money.

5.1.7 By improving movement at busy junctions and reducing delays, we have also contributed towards a reduction in carbon emissions and removed a significant barrier to development in the area. It has assisted in the overall control and co-

Page 115 ordination of the strategic corridor network within the Borough, whilst benefits will also be felt by neighbouring LEP areas.

5.1.8 The key measure of success of the improvements will be further realised as development continues in the Borough as part of the forthcoming Local Plan.

5.2 Monitoring

5.2.1 The business case outlined a number of monitoring and evaluation targets. These included;

 Traffic congestion and journey times on the Town Centre access routes (see sections 6.1, 6.2, 6.6, 6.7 and 6.8);

 Road safety for Town Centre routes (see section 6.5);

 Pedestrian and cycle counts on key routes into and around the Town Centre (see section 6.3);

 Car park usage (see section 6.1.2);

 Public transport use (See section 6.4), and

 Air Quality (See Section 6.9).

5.2.2 Due to the significant amount of roadworks being undertaken on the local highway network during the last 12 months, some surveys were not undertaken but will be reported in future evaluation reports. This is explained further in section 6.

Page 116 6.0 Travel Demand

6.1 Observed Turning Counts

6.1.1 Junction turning counts were undertaken in March 2013 and again at the end of November 2018 to illustrate the pre and post-implementation effect of the improved junction layout.

Table 6.1 – Junction Turning Count Summary

Location 2013 2018 % Increase

Met Office Roundabout AM 9,464 10,677 12.8%

Met Office Roundabout PM 9,939 11,348 14.2%

Station Roundabout AM 6,102 6,383 4.6%

Station Roundabout PM 6,426 6,876 7.0%

6.1.2 Observations taken across the year since the opening of the Lexicon with regard to travel preferences to the Town Centre indicate that 54% of visitors travelled by car, and 1.75 million car parking spaces were used across the opening year.

6.2 Journey Time Monitoring

6.2.1 At the time of writing, there is a significant amount of roadworks being undertaken in the vicinity of the corridor that would be monitored for journey time purposes.

6.2.2 It is considered that these works would impact on journey times and temporarily displace some journeys to alternative routes, thus skewing any results that would be recorded and therefore monitoring surveys have been postponed.

6.2.3 BFC are due to undertake manual classified turning counts and journey time surveys at key junctions and routes as part of the update of the Bracknell Forest Multi Modal Traffic Model in March 2019. The monitoring for this corridor is to be included within these surveys and will be reported on in future evaluation reports.

Page 117 6.3 Pedestrian and Cycle Movements

6.3.1 The improvements undertaken as part of the Town Centre infrastructure enhancements have resulted in a significant increase in the levels of pedestrian and cycle movements in and around the Town Centre.

6.3.2 Observations across the year taken since the Lexicon opening between September 2017 and August 2018 indicate that the footfall within the Town Centre has been in the region of 17 million people movements, with 23% of those visitors arriving on foot.

6.3.3 Tables 6.2 and 6.3 illustrate snapshot surveys undertaken at selected locations on the outskirts of the Town Centre and demonstrate the level of increase in pedestrian and cycle movements before and after the redevelopment of the Town Centre.

Table 6.2 – Observed Pedestrian Movements

Location 2016 2018 % Increase

Met Office Roundabout 772 1049 35%

Skimped Hill / Western Roundabout 841 1340 59%

Table 6.3 – Observed Cycle Movements

Location 2016 2018 % Increase

Met Office Roundabout 76 106 39%

Skimped Hill / Western Roundabout 105 124 18%

6.3.4 These observed increases in pedestrian and cycle movements and the modal share outlined above are far in excess of the measures of success for walking and cycling that were detailed within the business case (2.2% and 10% respectively)

6.3.5 The regeneration of the Town Centre included a number of associated cycle infrastructure improvements. These included a key route linking the rail station to the town centre, better access – including a new Toucan crossing – from the north, and 360 new cycle parking spaces in and around The Lexicon.

6.3.6 Although the usage of the cycle parking is not monitored, anecdotal evidence suggests it is well used, particularly in good weather, and that this continues to improve as the Town Centre grows.

Page 118 6.4 Public Transport

6.4.1 The public transport contribution from the planning agreement for the Town Centre enabled Bracknell Forest Council to commission additional bus services specifically to serve the regenerated town centre. Three local routes were extended later into the evening from Monday to Saturday, and new Sunday services were also introduced.

6.4.2 The services provide a public transport option for visitors enjoying the new evening economy in the town, and for those working in the retail and leisure outlets. In addition, these services provide benefits to the wider community; providing access to retail, health services, friends and family and church-going in the parishes surrounding the Town Centre.

6.4.3 Local bus operators also extended some of their commercial services to better serve the Town Centre, including one service extended from Arborfield to call at Bracknell on an hourly frequency Monday to Sunday.

6.4.4 Due to the significant amount of roadworks being undertaken on the local highway network during the last 12 months, passenger surveys have not been undertaken but will be reported in future evaluation reports.

6.5 Road Safety

6.5.1 In the year before opening from September 2016 to September 2017, there were 12 slight accidents recorded on the highway network around the Town Centre.

6.5.2 Following the opening of the Town Centre, the number of accidents recorded in the year from September 2017 to September 2018 was four, three of which were classified as slight and one being classified as fatal.

6.5.3 It can be seen that the introduction of the highway improvements have resulted in a significant reduction in the level of slight injury accidents on the local highway network

6.5.4 The fatal accident occurred late at night and the driver of one of the involved vehicles failed to stop at traffic lights. It is noted that contributory factors to the accident were driver error, driving an unsafe vehicle and driving at excessive speeds. Local Police have stated that the accident was not caused by any highway related factor.

Page 119 6.6 Traffic Monitoring

6.6.1 Traffic in the Borough is monitored by both the Council and the Department for Transport (DfT). The Council has 51 Automatic Traffic Counter (ATC) sites on a variety of roads across the Borough including key strategic routes. The DfT periodically carries out day counts at set points on key routes, devising a figure accordingly.

6.6.2 Data obtained from the Borough’s 51 ATC sites have shown a cross-borough increase over the 2014 – 2018 period of 6% (verified by DfT traffic count data which have shown a similar increase). This follows a period of decline in traffic from a high point in 2006, observed in Bracknell Forest and nationally.

6.6.3 For the purposes of this report, we will consider weekly / monthly data from Bracknell Forest Council ATC sites (shown in Figure 1 with a blue marker).

6.6.4 Site 237 Station Way was not included in the weekly analysis in section 6.6.7 as there was an insufficient level of comparison data for October 2017.

Figure 1 – BFC ATC Locations

Page 120

Impact of town centre regeneration on traffic

6.6.5 Bracknell Forest Council’s own automatic traffic counters can be used to take a more in-depth look at traffic trends over shorter periods – days, weeks and months, as opposed to a broader view of a whole year. It is more difficult to draw comparison conclusions using average annual traffic counts as data timeframes and reliability can vary. However, in an effort to analyse the impact of Bracknell’s regenerated town centre, we have compared total monthly data from nine traffic count sites, on a range of roads around the Town Centre between January 2015 and December 2018.

6.6.6 The graph clearly shows a peak around the opening of the Lexicon in September 2017, and a continued steady increase in traffic to the end of 2018. The troughs observed around January and during the summer holidays are normal in annual traffic surveys. Also, the large fall between autumn 2016 and the opening of the Lexicon in September 2017 reflects the significantly reduced availability of retail and leisure facilities following the demolition of the old Town Centre.

Weekend traffic – before and after comparisons

Page 121 6.6.7 Given that the Lexicon provides many new retail and leisure opportunities, it was assumed that it would generate significantly more weekend traffic. Considering the same sites, we have compared October 2016 with October 2017 and October 2018 (before, immediately after and one year after opening).

Table 6.4 Weekend traffic – October 2016 / October 2017 / October 2018 comparison Oct-16 Oct-17 Oct-18 Saturday Sunday Saturday Sunday Saturday Sunday % change % change % change % change 16-17 16-17 16-18 16-18 Saturday Sunday Saturday Sunday Site 15 - 13704 10664 14168 11109 14703 11227 3.27% 4.01% 6.79% 5.01% Wokingham Road Site 16 - 8432 6781 9082 7256 9435 7478 7.16% 6.55% 10.63% 9.32% Warfield Road Site 17 - 7166 5429 7413 5701 7587 5761 3.33% 4.77% 5.55% 5.76% Binfield Road Site 82 - 17217 12617 18809 14118 18818 13691 8.46% 10.63% 8.51% 7.84% Skimped Hill Lane Site 86 - 17136 13612 17692 13661 18372 14141 3.14% 0.36% 6.73% 3.74% London Road (Met Office) Site 236 - 8787 6181 9142 6731 8639 6303 3.88% 8.17% -1.71% 1.94% Market Street Site 238 - 11380 7430 11221 8055 11420* 8108* -1.42% 7.76% 0.35% 8.36% High Street Average 4.88% 5.75% 6.08% 5.60%

6.6.8 The figures show that average daily traffic on Saturdays and Sundays has increased on all monitored roads around the Town Centre between 2016 (pre-opening), 2017 (post-opening) and 2018, with the exception of a very modest traffic reduction on High Street in ‘17 and Market Street in ‘18 on Saturdays. The small Saturday reduction on these streets can be attributed to the huge increase in availability of car parking at the Avenue serving the Lexicon.

6.6.9 Weekend traffic on Skimped Hill Lane, a road which is predominantly used for access to the Town Centre’s shops and offices, increased by 10% between 2016 and 2017. On Warfield Road to the north, there was a similar increase over the two year period between 2016 and 2019. This is an indicator of the increased attraction of the Town Centre, as Skimped Hill Lane provides the most direct route from the major southern (A3095 Mill Lane) and western (A329 Berkshire Way) corridors, whilst Warfield Road provides the main northern route.

Page 122 6.6.10 It is expected that traffic levels associated with the Town Centre will continue to increase in the short to mid-term future with further phases of regeneration planned following opening in 2018.

6.7 Station Roundabout Junction Modelling Summary

6.7.1 The industry standard modelling program ARCADY was used to calculate the capacity and estimate vehicle queuing on Station Roundabout before the introduction of the traffic signal scheme.

6.7.2 The pre-improvement roundabout was tested using 2013 observed traffic volumes, whilst the observed 2018 traffic flows and 2026 modelled traffic flows illustrate how the junction would have operated if the signalised junction had not been installed. These results are illustrated in Tables 6.5, 6.6 and 6.7.

6.7.3 LINSIG was used on the subsequent signalised roundabout to illustrate the effect of introducing signals here using the 2018 observed turning counts, and then retested using the 2026 modelled flows to illustrate the future performance of the junction. These results are shown in Table 6.8 and 6.9.

Table 6.5 – Standard Roundabout ARCADY results – 2013 Observed AM Peak PM Peak Arm Ratio of Queue Delay Ratio of Queue Delay Flow to (s/veh) Flow to (s/veh) Capacity Capacity Station 0.1 >1 2.47 0.26 >1 3.05 Way Church 0.35 >1 2.47 0.35 >1 2.82 Road Hazell Hill 0.26 >1 5.70 0.03 >1 6.59 Bagshot 0.67 2 4.73 0.39 >1 2.39 Road Market 0.69 3 23.86 0.70 3 15.69 Street

Page 123 Table 6.6 – Standard Roundabout ARCADY results – 2018 Observed AM Peak PM Peak Arm Ratio of Queue Delay Ratio of Queue Delay Flow to (s/veh) Flow to (s/veh) Capacity Capacity Station 0.03 >1 2.52 0.16 >1 3.07 Way Church 0.32 >1 2.27 0.41 >1 2.99 Road Hazell Hill 0.22 >1 5.16 0.06 >1 7.02 Bagshot 0.69 3 5.02 0.41 >1 2.50 Road Market 0.80 4 33.98 0.96 14 65.26 Street

Table 6.7 – Standard Roundabout ARCADY results – 2026 Modelled AM Peak PM Peak Arm Ratio of Queue Delay Ratio of Queue Delay Flow to (s/veh) Flow to (s/veh) Capacity Capacity Station 0.06 >1 2.66 0.05 >1 2.69 Way Church 0.38 >1 2.72 0.44 >1 3.26 Road Hazell Hill 0.28 >1 6.48 0.12 >1 9.15 Bagshot 0.79 4 6.97 0.43 >1 2.63 Road Market 0.96 12 79.99 0.88 7 35.26 Street

6.7.4 Tables 6.5 - 6.7 illustrate that although the roundabout operated within capacity in 2013, it was predicted to get progressively worse in the when using the 2018 observed flows and modelled 2026 future flows.

Table 6.8 – Station Roundabout LINSIG results – 2018 Observed AM Peak PM Peak Deg. Of Sat Mean Max Deg. Of Sat Mean Max (%) Queue (%) Queue Station Way 3.5 0.0 19.4 >1 Church Road 36.4 >1 46.9 1.6 Hazell Hill 24.0 >1 5.4 0.0 Bagshot Road 70.5 7.7 37.2 3.5 Market Street 53.0 3.0 51.1 4.6 Cycle Time 44s 52s Delay 12.48 pcuHr 9.07 pcuHr PRC (%) 27.7 75.1

Page 124 Table 6.9 – Station Roundabout LINSIG results – 2026 Modelled AM Peak PM Peak Deg. Of Sat Mean Max Deg. Of Sat Mean Max (%) Queue (%) Queue Station Way 9.7 >1 6.5 >1 Church Road 63.2 2.8 69.0 3.5 Hazell Hill 36.3 >1 10.0 >1 Bagshot Road 64.1 7.7 35.9 3.3 Market Street 62.2 5.9 68.7 5.4 Cycle Time 55s 53s Delay 13.54 pcuHr 11.10 pcuHr PRC (%) 32.1 30.4

6.7.5 The introduction of a signalised junction is shown to demonstrate a reduction in queuing and delay when compared with the original roundabout based on the 2018 observed traffic flows, particularly on the Market Street arm of the junction which had been predicted to operate over capacity with increasing queue levels.

6.7.6 The roundabout is also predicted to continue to operate within capacity when using the 2026 future modelled flows.

6.8 Met Office Roundabout Summary

6.8.1 Primarily, the improvements to the Met Office Roundabout comprised the upgrading of the signal infrastructure at the junction and installation of MOVA at the junction which would improve the coordination of the signals around the roundabout and make it operate more efficiently.

6.8.2 As part of the installation, modifications were made to the kerb lines on London Road and Weather Way and to the white lining around the roundabout.

6.8.3 LINSIG was used to test the before and after scenarios to illustrate the impact of the improvements made to the junctions. Note LINSIG can only model based on fixed signal timings and as such, the roundabout would benefit from significantly larger improvements as a result of the operation of MOVA.

Page 125 Table 6.10 – Met Office Roundabout “Before” LINSIG results – 2013 Observed AM Peak PM Peak Deg. Of Sat Mean Max Deg. Of Sat Mean Max (%) Queue (%) Queue Warfield Road 54.7 4.8 63.8 5.1 Park Road 51.3 3.9 51.9 3.1 London Road 87.1 11.1 63.9 5.0 Church Road 61.8 5.4 60.2 4.9 Weather Way 20.6 >1 46.1 2.8 Millennium 52.4 4.3 62.8 5.9 Way Cycle Time 53s 55s Delay 33.26 27.36 PRC (%) 3.3 40.4

Table 6.11 – Met Office Roundabout “Before” LINSIG results – 2018 Observed AM Peak PM Peak Deg. Of Sat Mean Max Deg. Of Sat Mean Max (%) Queue (%) Queue Warfield Road 52.6 5.2 70.6 6.7 Park Road 66.3 7.0 65.6 5.9 London Road 89.4 15.5 68.7 5.6 Church Road 75.2 8.3 57.7 5.4 Weather Way 6.7 >1 28.6 >1 Millennium 46.1 6.0 73.4 7.9 Way Cycle Time 64s 56s Delay 44.17 34.46 PRC (%) 0.7 22.6

Table 6.12 – Met Office Roundabout “Before” LINSIG results – 2026 Modelled AM Peak PM Peak Deg. Of Sat Mean Max Deg. Of Sat Mean Max (%) Queue (%) Queue Warfield Road 106.2 29.4 74.9 9.3 Park Road 76.7 11.4 71.6 8.0 London Road 108.6 82.4 73.7 10.2 Church Road 84.7 12.8 57.2 7.3 Weather Way 21.3 0.9 61.4 4.0 Millennium 80.6 16.2 85.9 17.1 Way Cycle Time 90s 90 Delay 165.19 44.74 PRC (%) -20.6 4.8

6.8.4 Tables 6.10 – 6.12 illustrate that the original layout of the Met Office Roundabout was approaching capacity in 2018 and was predicted to operate over capacity in 2026.

Page 126 Table 6.13 – Met Office Roundabout “After” LINSIG results – 2018 Observed AM Peak PM Peak Deg. Of Sat Mean Max Deg. Of Sat Mean Max (%) Queue (%) Queue Warfield Road 46.1 4.6 62.6 6.1 Park Road 65.3 6.7 62.6 5.1 London Road 73.6 10.2 56.4 5.8 Church Road 68.6 7.4 52.8 4.8 Weather Way 6.7 >1 7.8 >1 Millennium 69.2 7.4 71.2 8.0 Way Cycle Time 64 56 Delay 38.52 31.65 PRC (%) 8.2 26.4

Table 6.14 – Met Office Roundabout “After” LINSIG results – 2026 Modelled AM Peak PM Peak Deg. Of Sat Mean Max Deg. Of Sat Mean Max (%) Queue (%) Queue Warfield Road 61.4 8.5 69.8 8.7 Park Road 67.2 9.2 74.2 8.2 London Road 90.3 18.5 61.4 8.9 Church Road 89.6 14.6 58.8 7.4 Weather Way 21.3 >1 56.3 3.8 Millennium 83.5 17.3 82.9 13.2 Way Cycle Time 90 90 Delay 65.13 43.67 PRC (%) -0.4 7.4

6.8.5 The revised layout is shown to operate significantly better when modelled with 2018 observed and 2026 modelled flows. This compounded with the effect of the installation of MOVA on the junction (which cannot be simulated in LINSIG) that is estimated to reduce delays by over 13% compared to junctions under VA control.

6.9 Carbon Impacts

6.9.1 Bracknell Forest’s annual Air Quality Action Plan (AQAP) considers air quality across the Borough, focussing on emissions that are harmful to human health, such as nitrogen dioxide, particulates and sulphur dioxide. Pollutants are monitored at two Air Quality Management sites in Crowthorne, and adjacent to the A322 Downshire Way in Bracknell.

6.9.2 The levels of NOx and particulates have been steadily decreasing over the past ten years, but there is still a need for improvement. The report notes that “it is well recognised that queuing traffic can have a massive impact upon air quality and as

Page 127 such this is an area which needs to be considered in both AQMAs. The stopping and starting of traffic can also impact upon air quality and therefore any measures to ease congestion within the AQMAs will assist in improving air quality”.

6.9.3 The Council’s junction improvement projects in the town centre and along the A322 / A329 corridor aim to provide more reliable journey times and a smoother flow of traffic by better managing traffic at key junctions. The further works to dual Downshire Way (adjacent to an AQMA monitoring site) should also help to keep traffic flowing, where it is often currently stationary, creating a network bottleneck. Once this improvement is in place, there will be a resulting improvement in overall air quality.

6.9.4 Air quality is monitored at various sites around Bracknell Town centre. There is an Air Quality Management Area along the A322 Downshire Way and part of Bagshot Road, with a permanent monitoring station between the Twin Bridges roundabout and Fire Station, and monitoring tubes at separate locations along the AQMA route.

6.9.5 Air quality data is also being collected from 11 new sites around the town centre, in order to monitor the impacts of the town centre regeneration and related road improvements. These sites have not been in long enough to provide a trend pattern, however data from monitoring sites along the AQMA suggests a steady reduction in pollutants recorded over the past 5 years, including 2016 – 2017.

6.10 Summary

6.10.1 Broadly speaking, the increases to travel demand were marginally higher than those forecast in the business case.

6.10.2 However, it is noted that the highway improvements are more than capable of handling the additional traffic and are still predicted to perform well in future traffic simulations.

Page 128 7.0 Urban Traffic Control and Variable Message Signage

7.1 As part of the Town Centre (Lexicon) redevelopment, Bracknell Forest Council was allocated funding to undertake major infrastructure development in order to ensure the surrounding highways network was suitable to cope with additional demands placed upon it by the regeneration.

7.2 A key area of investment was a reliable, fast and adaptable telecommunications network. This system provides a solid platform for the Town Centre signals and other intelligent transport systems. It is also scalable for the future and cost-effective, both in terms of capital and revenue outlay.

7.3 The Council opted for a high speed internet protocol based mesh system which has afforded the ability for live real-time communication monitoring, quick connections of new systems, and a nearly revenue-neutral ongoing cost.

7.4 The systems have been implemented across the entire Town Centre, being utilised in an advanced car park guidance system, as well as traffic signal control and monitoring, plus CCTV.

7.5 The Council are now looking to expand its use into a journey time monitoring and traffic counting system.

7.6 The Town Centre funding also allocated money to a comprehensive variable messaging system, which is being used for car park guidance.

7.7 The system has successfully linked all the major Town Centre car parks, giving road users an overview of all available parking, including information on car park closures, and if there are any major incidents. This system has proven to be very reliable and ensures efficient use of the network and our available parking facilities.

7.8 Furthermore, a key part of the investment into the Town Centre was the installation and upgrade of new and existing pedestrian crossing facilities and traffic signal junctions.

7.9 Significant development work was undertaken, and the Town Centre now benefits from modern, efficient and advanced functioning traffic signals equipment. The junction installations have adaptive control and live monitoring, which has been used to benefit the highway network already.

Page 129 8.0 Impacts on the Economy

8.1 The transport infrastructure improvements have helped facilitate the delivery of 270,000sqm of retail floor space generating over 3,500 retail and leisure jobs.

8.2 This increase in floor space has resulted in Bracknell being ranked 31st in the South East in terms of retail footprint, and boosted the town to be the 33rd best shopping destination in the UK (up from position 255 in 2017), with each visitor making a trip to the town centre on average 73 times per year.

8.3 The Town Centre development was also to facilitate the construction of 1,000 new housing units, of which 892 are have been started of which 287 are complete. Following the success of the town centre regeneration, this figure is set to rise by a further 500 housing units which have also been secured for delivery by 2026.

8.4 Since opening, the Town Centre redevelopment has received a number of awards ;

 REVO 2017 Re:new Award (December 2017)

 REVO 2017 Best of the Best Award (December 2017)

 2018 iESE Transformation Gold Award, Community Regeneration Category (March 2018)

 2018 iESE Transformation Best of the Best Award (March 2018)

 Thames Valley Property Awards 2018 – Development of the Year (May 2018)

 REVO Purple Apple Marketing Awards 2018 – Strategic Marketing ‘Winning Back Local Hearts and Minds’ (May 2018)

8.5 Reception for the redevelopment on social media has been favourable with high ratings on Facebook, Google and Trip Advisor. There has also been a large level of increase in followers on Instagram and Twitter.

8.6 There is significant development due to come forward within Bracknell Forest Borough as part of the forthcoming Local Plan, and this will require suitable infrastructure to mitigate any associated impacts on the road network.

Page 130 8.7 By improving movement and control at the busy junctions around the Town Centre and reducing delays, we have assisted in reducing carbon emissions and removed a significant barrier to development in the area.

Page 131 9.0 Summary

9.1 With the benefits of the scheme based on a modelled forecast year of 2026, it is too early to report on the impact of the delivered schemes, but it is clear that overall movement and capacity at the junctions have been improved, forming an important part in the overall management the local highway network.

9.2 Observations taken across the year since the opening of the Lexicon with regard to travel preferences to the Town Centre indicate that 54% of visitors travelled by car, and 1.75 million car parking spaces were used across the opening year.

9.3 It is also noted that between September 2017 and August 2018 footfall within the Town Centre was reported to be in the region of 17 million people movements, with 23% of those visitors arriving on foot. We have also seen an increase in bus patronage, with this mode of transport accounting for 18% of the visitors to the site.

9.4 The huge positive changes in Bracknell town centre since the demolition of the old shopping area had the potential to bring increased traffic congestion, unsustainable parking demand, poorer air quality, reduced safety and a lack of technological future proofing. However the integrated and cost-effective approach adopted by the Council from the planning to the implementation stage has ensured that none of these eventualities have come to pass.

9.5 Instead, Bracknell now has a flourishing 21st century retail and leisure hub that will serve the existing and projected population, as well as the increased number of visitors to the town. All this whilst ensuring that the local and strategic transport network continues to provide efficient access to and from these new facilities.

Page 132 Appendix 2

Thames Valley Berkshire Local Enterprise Partnership

Independent Assessment Summary Report: Bracknell Town Centre Regeneration

One Year Impact Report

Hatch Regeneris

February 2019 www.regeneris.co.uk

Page 133

Contents Page

Independent Assessment

Process

Scheme Summary

Review Findings

Page 134 Independent Assessment i. This technical note provides an independent assessment of the One-year Impact Report submitted by Bracknell Forest Council (BFC) in relation to the Bracknell Town Centre Regeneration (BTCR) scheme. ii. The BTCR scheme received funding through the Thames Valley Berkshire Local Enterprise Partnership (TVB LEP) Local Growth Fund deal. As part of the on-going assurance process, TVB LEP requires all funded schemes to produce one-year and five-year post-implementation impact reports to demonstrate how each scheme has performed against expectations.

Process iii. The one and five-year impact reports are expected to assess the following elements of the scheme: a. did it get built? b. was it to plan? c. was it on time? d. was it to budget? e. is it working ok? f. what impact has it had? g. any learning points? iv. Hatch Regeneris have applied these criteria but also sought to use the process as positive influence to identify specific ways in which project scheme design or delivery could be enhanced to enhance future value of this scheme or other future LEP funded schemes

Page 135 Scheme Summary v. The Council received £2,000,000 from the TVB LEP Local Growth Fund as part of an overall estimated scheme cost of £6,382,000. vi. The scheme was delivered in support of the wider regeneration of Bracknell Town Centre that comprised the demolition of buildings and the redevelopment of the area for a mix of uses, including retail, food and drink, leisure, residential, community and business uses. vii. The associated transport scheme elements incorporated the delivery of changes to the local highway provision, improved public realm, new and enhanced walk / cycle connections, and the improved transport information technologies. The specific improvements included: • Provision of a new signal-controlled junction on Millennium Way serving the multi-storey car park, incorporating a new pedestrian / cycle crossing facility and forming part of a new route between Bull Lane and the Met Office roundabout; • Re-alignment of The Ring (north) from Weather Way; • Improvements at the Met Office Roundabout and Station Roundabout; • Provision of a new drop off / collection point on Bond Way and covered cycle parking facilities; • Revisions to Conventional Advanced Directional Signing (ADS); • Additional Variable Message Signing (VMS) - enabling greater co- ordination and management and maximising car park occupancy; • Additional Real Time Bus Information (RTI) at key stops linked to the Town Centre; • Enhanced Urban Traffic Management Control (UTMC) system;

Page 136 • A range of cycle and pedestrian facilities improvements across the heart of the town; and • A new junction to provide enhanced access to Charles Square service yard / multi-storey car park. viii. The primary objectives of the scheme were to: improve journey times, reliability and journey quality for all road users; improve accessibility to Bracknell Town Centre for pedestrians, cyclists and road users; reduce congestion and its environmental impacts; improve access to Bracknell train station; and enhance the viability of the town centre, support Economic Development and other key areas. ix. The Full Business Case included a series of monitoring and evaluation targets relating to: traffic congestion and journey times on the Town Centre access routes; road safety for Town Centre routes; pedestrian and cycle counts on key routes into and around the Town Centre; car park usage; public transport use; and air quality.

Review Findings

General Observations x. The scheme elements were all delivered as planned. Whilst the overall regeneration programme was delayed by 6 months, the transport infrastructure, funded through the LGF, was delivered ahead of schedule. xi. The scheme was delivered for a final cost of £6,393,696, representing a very modest cost overrun of just £12,000, which was covered by the developer. It is worth noting that the projected scheme costs included a monetary value derived from the Quantified Risk Assessment and so it can be

Page 137 concluded that this represented an accurate assessment of required cost contingency. xii. Comparative junction turning count data for pre and post-scheme implementation are presented within the one-year impact report. This data demonstrates increases in traffic movements through the Met Office and Station Roundabouts of between 4.6% and 14.2%. These increases are reported as being marginally higher than those forecast within the FBC. xiii. Comparative data on vehicle journey times has not been presented within the one-year impact report. This is because there is currently a significant amount of roadworks being undertaken in the vicinity of the corridor that is likely to distort the outcomes of the survey work. BFC have scheduled these surveys, alongside other manual classified turning counts, to be undertaken in March 2019. xiv. Surveys undertaken since the opening of the main Lexicon Centre in the town centre estimate around 17 million people movements, with 13% arriving on foot. It is not clear whether these movements are in-line with expectations for the scheme. xv. Comparative data on pedestrian and cycle movements pre and post- scheme implementation are presented within the one-year impact report. This data demonstrates increases in pedestrian movements at the Met Office Roundabout and Skimped Hill / Western Roundabout of between 35% and 59%, whilst cycle movements have increased between 18% and 39%. These observed increases are reported as far in excess of the ‘measures of success’ for walking and cycling detailed within the FBC of 2.2% and 10%, respectively.

Page 138 It would be insightful if a broader range of count locations were available for future surveys. xvi. Monitoring data for the use of the 360 cycle spaces delivered in and around the Lexicon is not available; however, the report states that anecdotal evidence suggests it is well used, particularly during good weather. xvii. It is reported that the town centre improvements have enable BFC to commission additional bus services to serve the town and that these now serve the evening and Sunday time periods. Local bus operators are also reported to have extended their commercial services. Whilst specific patronage data is not available, the evidence presented infers that the schemes are encouraging greater use of public transport to access the town centre. xviii. There is no commentary on how the schemes have specifically contributed to enhancing access to Bracknell Train Station and any associated benefits. xix. Comparative data on accident levels indicates that there were 12 slight accidents in the year prior to the scheme opening, and in the subsequent year there were three slight accidents and one fatal. Local Police have stated that the one fatal accident was not caused by any highway-related factor, but rather driver error. It can be concluded that the overall frequency of accidents has fallen significantly. xx. Monitoring data from BFC and the DfT traffic count locations have indicated a 6% average increase in cross-borough traffic between 2014 and 2018. Specific count locations within the town centre have been used to demonstrate a peak in demand when the Lexicon opened and steady growth thereafter, providing evidence of the overall success of the regeneration

Page 139 scheme in attracting new trips into Bracknell Town Centre. Traffic data presented for the weekend, when retail and leisure activity was anticipated to be highest, indicates a post-scheme implementation increase in traffic of 6.1% and 5.6% on Saturdays and Sunday, respectively. xxi. To assess the impact of changing traffic flows upon the operation of junctions within the town centre, the report utilises local junction modelling tools (ARCADY, LINSIG) to assess the performance of two junctions under different levels of traffic flow. The outputs indicate that the revisions to both the Station Road and Met Office Roundabouts have resulted in enhanced operational performance, despite the increases in traffic flow. xxii. It is reported that improving the flow of vehicles across the town centre network, and reducing the stop/start nature of traffic, will help improve local air quality. No evidence is currently reported to verify this position, but it is reported that this will be collected in future years. xxiii. The UTMC and VMS system delivered is described and it is stated that it now successfully links with all major Town Centre car park to help optimise the use of the road network and car parking capacity. No specific examples of how it works in practice are presented. xxiv. The impacts that the overall town centre regeneration scheme has had upon the economy is described in broad terms, with a range of positive benefits, including the delivery of 3,500 retail and leisure jobs.

Page 140 Conclusions xxv. The BTCR one-year impact report represents a well-constructed and balanced document, making good use of the available evidence. It is considered to meet the majority of requirements for a one-year impact report. xxvi. The report provides a good overview of the scheme delivered and the positive impacts that have occurred in terms of increased junction capacity, increased walking and cycling flows, and overall improved management of the local transport network. The scheme has also clearly facilitated access to the enhanced regeneration scheme and helped to secure positive local economic benefits, including the delivery of jobs. It would be more insightful if all the described impacts were presented against the prior expectations of the scheme, as set out/forecast within the FBC. xxvii. The absence of journey time data makes it challenging to assess the overall impact of the scheme measures and it will be important to review this data when it becomes available. It also remains unclear what the specific impact the scheme has had upon local air quality. xxviii. The scheme was delivered ahead of time and extremely close to budget, and at no extra cost to the public sector, and demonstrates that a robust budgeting process was completed and that the delivery of the project was well-managed. Subject to considerations of journey time impacts and air quality, the scheme is considered to be working well and has delivered the broad outcomes required.

Page 141 xxix. The key points for consideration, both to enhance the future outcomes of the project and to facilitate wider learning, include: • The collection of journey time data will be a key metric for assessing the ultimate impact of the scheme upon the operation of local highway network and the collection, analysis, and presentation of this data should be prioritised. • For a scheme that appears to have increased the levels of vehicular traffic moving across parts of the local transport network, it will be critical to demonstrate that this traffic is being managed in a way that minimises the impact upon local air quality. • It would be beneficial to have broader assessments of the impact of the scheme upon public transport, cycling and walking levels, including how the scheme has support the use of Bracknell Train Station and use of cycle parking. • The budgeting and management processes applied within the development and delivery of the scheme, including the quantified risk assessment, should be shared with future projects of this type.

Page 142 AGENDA ITEM 7

BERKSHIRE LOCAL TRANSPORT BODY (BLTB)

REPORT TO: BLTB DATE: 14 March 2019

CONTACT OFFICER: Tim Wheadon, Chief Executive Bracknell Forest Council

PART I

Item 7: Business Rates Retention Pilot – Revenue Support

Purpose of Report

1. In March 2018 you agreed to issue calls for bids for funding via the Business Rates Retention Pilot (BRRP) and the associated re-prioritisation of schemes in the Growth Deal 3 list; in July 2018 you agreed to “top-slice” the £25m BRRP allocation by £600,000 in order to establish a scheme for providing revenue support to local authorities for the development of a strong pipeline of future infrastructure schemes.

2. In November 2018 and January 2019, you approved the revenue support proposals and the drawdown of BRRP funds by Reading, West Berkshire, Windsor and Maidenhead, Wokingham and Bracknell Forest.

3. This report recommends a further payment under the revenue support scheme to Slough.

Recommendation

4. You are recommended to approve the revenue support proposal and the drawdown of BRRP funds by Slough Borough Council set out in appendix 1.

Other Implications

Financial

5. The lead authority for BRRP and the process of operating the Business Rates element (agreeing baseline amounts, managing the pool of retained funds) is Bracknell Forest Council. The planning figure of £25m for 2018-19 is based on current estimates of business rates collection in 2018-19, and no revisions are anticipated.

6. The lead authority for the control of Local Growth Funds allocated to infrastructure or regeneration projects is the Royal Borough of Windsor & Maidenhead, the LEP’s Accountable Body.

7. The BRRP has been approved for financial year (2018-19); MHCLG has since approved a second year of the pilot (2019/20) and a planning number of c.£11m has been calculated for new infrastructure investment.

Item 7 BLTB 14 March 2019 Business Rates Retention Pilot – Revenue Support Page 143 8. At your meeting in July 2018, you prioritised the following schemes from BRRP1:

Scheme £’000’s Slough Mass Rapid Transit (SMaRT) Phase 2 10.242 South Reading MRT Phases 3 and 4 7.898 Wokingham Winnersh Relief Road Phase 2 6.260 Revenue Support for Scheme Development 0.600 Total 25.000

Risk Management

9. The risks associated with large scale infrastructure investments are well known, and the BLTB has established risk management arrangements for the LGF transport capital programme (£111m over 6 years), referred to as the Assurance Framework1.

10. As part of the LGF oversight, government officials have reviewed this assurance framework and found it fit for purpose.

11. The Berkshire authorities have identified the LEP and its associated processes as an appropriate framework for managing the BRRP sums available; in this instance this means programme management by the BLTB and ultimate sign- off by the LEP Forum. The LEP Forum ratified this approach on 27 March 2018.

12. The implication is that promoters of infrastructure projects seeking funding from the BRRP will need to follow the same assurance framework as for LGF. This means acceptance at “programme entry” stage, followed by submission and independent assessment of a WebTAG compliant Full Business Case before being considered for financial approval.

Human Rights Act and Other Legal Implications

13. Slough Borough Council will provide legal support for the BLTB should any questions arise on the application of the BRRP.

Supporting Information

Revenue Support for Business Case Preparation

14. In July 2018 you agreed that the £25m BRRP allocation for major capital schemes should be “top-sliced” by £600,000, which should then be allocated to the six Berkshire authorities. This would be a contribution to the development costs associated with major infrastructure projects identified in each of the emerging Local Plans.

15. The revenue support proposal has the following details:

1 http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum

Item 7 BLTB 14 March 2019 Business Rates Retention Pilot – Revenue Support Page 144 a. £100,000 of BRRP funds in 2018/19 be allocated to each of the six Berkshire Unitary Authorities for the purpose of developing major infrastructure projects identified in the emerging Local Plans, subject to: b. The money being spent on the development outline business cases for transport infrastructure projects which support or enable the development of housing, employment, leisure or retail projects c. BLTB approving the timetable and list of projects before the money is released.

16. It is now proposed that following details be added to the revenue support scheme:

a. When seeking BLTB approval, an Authority should identify the lead officer contact; timetable start and end date for developing the specified schemes; and also propose a schedule of progress reports to BLTB b. Where known, for each infrastructure project the Authority should identify i. Name of the project ii. Local Plan (or emerging Local Plan) references iii. Approximate Capital Value of the project a. up to £2m b. £2m-£5m c. £5m-£10m d. £10-£20m e. over £20m iv. The housing, employment, leisure or retail development to be enabled v. Partner organisations involved (if any) vi. Brief Description of Project (100 words max) vii. How the resource will be used to develop the outline business case (in-house? Retained consultant? Other?) c. Where specific schemes are not yet identified, and the intention is to use the revenue resource to fund the investigation of specific schemes that are consequent on the Local Plan (or emerging Local Plan) requirements, then the application should be adapted to reflect this. A specific commitment to reporting back as and when named schemes are identified should be included.

17. The proposal from Slough (appendix 1) is attached. This is the final BRRP revenue support submission from the BRRP Pilot.

Conclusion

18. There is an imperative to invest some of the BRRP £25m in the development of the pipeline of major infrastructure or regeneration schemes, which will support emerging local plans and be eligible for funding in future years.

Background Papers

19. The Business Rates Retention Pilot bid and approval letters.

Item 7 BLTB 14 March 2019 Business Rates Retention Pilot – Revenue Support Page 145 APPENDIX 1

Revenue Support for Business Case Preparation

Business Rates Retention Pilot – Slough Borough Council Proposal

Lead Officer; Savio De Cruz

Contact details: Savio. DeCruz @slough.gov.uk Telephone: 01753875640

Name of Project: Heart of Slough Strategic Routes.

Reporting; Monthly reports will be submitted to the BLTB by the Lead Officer.

Background Following the announcement by the BLTB regarding the £100,000 funding available for development of business cases for transport infrastructure projects that will support/enable the development of housing, employment, leisure or retails projects identified in the emerging Local Plans, Slough Borough Council has identified transport schemes that will support regeneration in the Town Centre as part of the Transport Vision. In order for these schemes to be developed further Slough Borough Council is seeking £100,000 funding to develop an outline business case.

Supporting Policies

Local Plan (or emerging Local Plan) references; The Heart of Slough strategic routes scheme supports the following Emerging Local Plan for Slough 2016-2036 aims:

 Delivering major, comprehensive redevelopment within the “Centre of Slough” by providing opportunities to support high quality development through provision of improved journey times and cheaper alternative sustainable modes of transport.  Selecting other key locations for appropriate development by improving transport links and unlocking housing development in the town centre.  Accommodating the changes in Slough expected to arise from the expected development of the proposed third runway at Heathrow and mitigating its impact; Scheme will provide better transport links to and from Heathrow.

Approximate Capital Value of project: over £20m

Item 7 BLTB 14 March 2019 Business Rates Retention Pilot – Revenue Support Page 146 The housing, employment, leisure or retail development to be enabled;

The improvement of transport links in the centre of Slough will compliment proposed housing development and aid further development of retail development and leisure facilities in the centre of Slough.

Partner organisations involved; Slough Urban Renewal, Slough Direct Service Organisation (DSO)

Brief Description of Project The Council is proposing to identify schemes that will support the proposed Transport Vision in the centre of Slough which will unlock regeneration in the Town Centre and enhance transport links including provision of high-quality walking and cycling facilities. The existing network does not have sufficient capacity to complement the proposed developments therefore the Council is investigating the introduction of a low volume car zone that prioritises buses within the centre of Slough. The proposals include introducing a central section of the SMaRT scheme in the town centre and bus station and connecting it with the existing western section and proposed eastern section (SMaRT phase2), to improve journey times and support the town centre regeneration. The funding will enable the Council to undertake an options appraisal exercise and prepare an outline business case.

How the resource will be used to develop the outline business case - The £100,000 funding will be used to investigate the options that will then develop the outline business case. The Council is currently undertaking a tender exercise to procure a professional services contract. It is expected that the selected contractor will prepare the business case and undertake preliminary drawings for the scheme. Programme management and reporting for the business case will be undertaken by experienced Slough Borough Council Officers. There are also options to use existing Framework agreements for professional services available through Hampshire County Council and Wokingham Borough Council.

Proposed Time Table

Project Task Start Drafts To BLTB Final submission Options April 2019 - October 2019 assessment Draft Initial Outline November 2019 February 2020 February 2020 Business Case Final Outline March 2020 May 2020 June 2020 Business case

Item 7 BLTB 14 March 2019 Business Rates Retention Pilot – Revenue Support Page 147 This page is intentionally left blank AGENDA ITEM 8

BERKSHIRE LOCAL TRANSPORT BODY (BLTB)

REPORT TO: BLTB DATE: 14 March 2019

CONTACT OFFICER: Joe Carter, Director of Regeneration, Lead Officer to the BLTB

PART I

Item 8: Revised Local Growth Fund Programme 2015/16 to 2020/21 - Update

Purpose of Report

1. To give consideration to granting programme entry status to a new scheme from the July 2018 prioritised list (see Appendix 1) following confirmation from Slough Borough Council that, due to complexities of land ownership, scheme 2.41 Slough: SMaRT Phase 3 A4 West Park and Ride cannot be delivered by the required March 2021 timing.

Recommendation

2. You are recommended to grant programme entry status for scheme 2.42 Wokingham: Barkham Bridge for £4,265,431

Other Implications

Financial

3. The LGF programme covers six financial years, 2015-16 to 2020-21, and the expectation is that the funds allocated to Thames Valley Berkshire LEP will be spent in that period, or failing that, fully committed to schemes that have started on site by March 2021 and have a “tail” of funding carried over into financial year 2021-22.

4. In January 2019, Reading Borough Council (RBC), had notified the LEP that they could not achieve a start on site for the East Reading (ER) MRT scheme in the required time limit. Your meeting in January agreed to the reallocation of £14,584,931 to six schemes, and postponed a decision about a seventh scheme, 2.41 Slough SMaRT Phase 3 A4 West Park and Ride.

5. This report recommends that a new seventh scheme, 2.42 Wokingham: Barkham Bridge, replaces the scheme previously indicated.

6. The amount available for reallocation is £5,648,069, as set out in Table 1 below. Table 1: Reallocation amounts Unallocated amount as at November 2018 1,166,000 Add: 2.14 and 2.25 East Reading MRT phases 1 and 2 19,067,000 20,233,000

Item 8 BLTB 14 March 2019 Revised Local Growth Fund Programme 2015/16 to 2020/21 update Page 149 Less: 2.35 Reading: Reading West Station Upgrade 3,100,000 2.36 Wokingham: Coppid Beech Park and Ride 2,400,000 2.37 Bracknell: A322 A329 Corridor Improvements 1,200,000 2.38 Theale: Theale Station Park and Rail Upgrade 4,000,000 2.39 Wokingham: Coppid Beech northbound on-slip widening 2,322,431 2.40 Windsor: Town Centre Package 1,562,500 14,584,931 Unallocated amount as at 14 March 2019 5,648,069 Less: if agreed 2.42 Wokingham: Barkham Bridge 4,235,641 Available 1,412,428

7. Although the vast majority of LGF is ringfenced for strategic transport schemes there remains the possibility that the LEP will bring forward skills or enterprise capital projects for consideration, if these offer VfM, make more of a strategic impact and can be delivered swiftly. The LEP Board will be discussing this on 12 March 2019.

Risk Management

8. There remains a risk that the new scheme identified in this report will be unable to mobilise quickly enough to achieve the necessary start on site by March 2021; in that event any LGF not committed would be liable for return the government unspent.

9. This risk has been anticipated and reassurances have been given by Wokingham Borough Council that this scheme is already in development and will be able to start on site in the required time.

Human Rights Act and Other Legal Implications

10. Slough Borough Council will provide legal support for the BLTB should any questions arise.

Supporting Information

11. At your meeting in July 2018, a list of 16 potential LGF schemes was considered and prioritised. They are listed at Appendix 1. See Appendix 2 for short summaries of each scheme and hyperlinks to detailed scheme proformas.

12. Following the delay to the progress of scheme 2.14 and 2.25 East Reading MRT Phases 1 and 2, and the subsequent confirmation from the scheme promoter that it could not be delivered within the current Local Growth Fund (LGF) programme, i.e. by the end of 2020/21, it was agreed at the January 2019 meeting of the BLTB to re-allocate £19,067,000 LGF previously awarded.

13. Six schemes were taken from the previously agreed (July 2018) prioritised list and granted programme entry status. Those schemes were:

Item x BLTB 14 March 2019 Revised Local Growth Fund Programme 2015/16 to 2020/21 update Page 150 a. 2.35 Reading: Reading West Station Upgrade b. 2.36 Wokingham: Coppid Beech Park and Ride c. 2.37 Bracknell: A322 A329 Corridor Improvements d. 2.38 Theale: Theale Station Park and Rail Upgrade e. 2.39 Wokingham: Coppid Beech northbound on-slip widening f. 2.40 Windsor: Town Centre Package

14. A seventh scheme, 2.41 Slough: SMaRT Phase 3 A4 West Park and Ride was deferred for consideration of programme entry status until the March 2019 BLTB meeting.

15. It has now been confirmed by Slough Borough Council that due to complexities of land ownership that this scheme cannot be delivered by the required March 2021 timing.

16. Therefore, the next scheme in the priority list, Wokingham: Barkham Bridge is now being considered. The scheme is to build a new bridge next to the existing Barkham Bridge (located between Barkham Street and Langley Common Road) to facilitate 2-way traffic through the existing bottleneck. The current Barkham Bridge structure is only wide enough to accommodate a single lane of traffic and currently operates a priority give way traffic system, causing a bottleneck, queues and delays.

17. The scheme will also help to support the Arborfield Garrison Strategic Development Location (SDL). The Arborfield Garrison location is identified in the Wokingham Borough Core Strategy as being capable of accommodating around 3,500 new dwellings with associated transport and green community infrastructure.

18. Wokingham Borough Council colleagues have confirmed that the scheme is already in development and that much of the early preparation work has been completed. They are confident that if funding is agreed, a start on site can be achieved before March 2021.

Overall priorities for the LEP LGF programme

19. By 26 March 2019 there will be clarity on whether any skills or enterprise capital projects will be competing for LGF. As noted in the financial implications section above, there will be at least £1.41m unallocated in March.

20. A further report will be made to the July meeting.

Conclusion

21. The scheme to alleviate the bottleneck at Barkham Bridge is a viable scheme, that meets the criteria for support from these funds and is worthy of your support.

Item x BLTB 14 March 2019 Revised Local Growth Fund Programme 2015/16 to 2020/21 update Page 151 APPENDIX 1 – Local Growth Deal list of prioritised schemes agreed in July 2018

Weighting Factor 1.5 2 4 1.5 0.5 0.5 GD3 Deliver Econ TVB Natural Social Total Ran Factor SEP £m Bid for Cumulative able Impact area Capital Value Score k Slough: Stoke Road Area Programme 2.31 4.5 6 12 3 1 1.5 28 1= 7,650,000 Regeneration entry July 18 Maidenhead: Housing Sites Programme 2.32 4.5 6 12 3 1 1.5 28 1= 4,660,000 Enabling Works entry July 18 GWR: Maidenhead to Programme 2.33 Marlow Branch Line 4.5 6 8 4.5 1 1.5 25.5 3 1,525,000 entry July 18 Upgrade Reading: Reading West Programme 2.35 4.5 6 8 3 1 1.5 24 4= 3,100,000 Station Upgrade entry Jan 19 Wokingham: Coppid Beech Programme 2.36 4.5 6 8 3 1.5 1 24 4= 2,400,000 Park and Ride entry Jan 19 Bracknell: A322 A329 Programme 2.37 4.5 6 8 3 0.5 1.5 23.5 6= 1,200,000 Corridor Improvements entry Jan 19 Theale: Theale Station Programme 2.38 4.5 6 8 3 1 1 23.5 6= 4,000,000 Park and Rail Upgrade entry Jan 19 Wokingham: Coppid Beech Programme 2.39 northbound on-slip 4.5 6 8 3 0.5 1 23 8 2,322,431 entry Jan 19 widening Windsor: Town Centre Programme 2.40 4.5 4 8 3 1 1 21.5 9 1,562,500 Package entry Jan 19 Slough: SMaRT Phase 3 2.41 4.5 2 8 3 0.5 0.5 18.5 10 4,160,000 Deferred A4 West Park and Ride Wokingham: Barkham Recommen 2.42 3 4 8 1.5 0.5 1 18 11 4,235,641 Bridge ded Slough: A355 Route 4.5 2 8 1.5 0.5 0.5 17 12 3,600,000 Enhancement Phase 2 Slough: Town Centre to M4 3 2 8 1.5 0.5 1 16 13 9,600,000 Junction 6 Link Wokingham: Tan House 4.5 2 4 1.5 1 1 14 14 1,200,000 Crossing Slough: Chalvey 3 2 4 3 0.5 0.5 13 15 28,000,000 Regeneration Wokingham: California 1.5 4 4 1.5 0.5 1 12.5 16 3,581,129 Crossroads

Item x BLTB 14 March 2019 Revised Local Growth Fund Programme 2015/16 to 2020/21 update Page 152 Appendix 2

Ra Amount Bidder Short Title Short Description Notes nk Sought Slough Stoke Road Area Sustainable transport infrastructure and highway works to support regeneration of six major Programme Entry 1= Slough 7,650,000 Regeneration brownfield sites at Stoke Road and improved interchange and parking at Slough station. July 2018 Maidenhead Housing Sites Windsor and Junction improvements and new highway infrastructure required to deliver major housing Programme Entry 1= Enabling Works Phases 1 and 4,660,000 Maidenhead developments and town centre regeneration in Maidenhead. Phase 1 £5.825m; phase 2 £21.300m. July 2018 2 Infrastructure works to allow two direct trains per hour between Marlow and Maidenhead and GWR Maidenhead to Marlow Programme Entry 3 GWR improvements to intermediate stations 1,525,000 Branch Line Upgrade July 2018 See note at paragraph 15 below Reading West Station Delivering improved passenger experience and multi-modal interchange through a new station Programme Entry 4= Reading 3,100,000 Upgrade building, highway changes and improvements to platform facilities and the Tilehurst Road entrance. January 2019 Wokingham Coppid Beech Coppid Beech Park and Ride will improve access to Wokingham and Bracknell Town centres, Programme Entry 4= Wokingham 2,400,000 Park and Ride railway stations and employment sites by tackling congestion in east Wokingham. January 2019 Bracknell Bracknell A322 A329 Corridor Capacity improvements to two key junctions along the A329/A322 corridor building on schemes Programme Entry 6= 1,200,000 Forest Improvements delivered through the Local Growth, Pinch Point and National Productivity Investment Funds. January 2019 West Theale Station Park and Rail Station enhancements at Theale to improve sustainable transport interchange, increase Park and Programme Entry

Page 153 Page 6= 4,000,000 Berkshire Upgrade Rail capacity and enhance customer facilities. January 2019 Wokingham Coppid Beech Programme Entry 8 Wokingham Widening of the northbound on-slip at the Coppid Beech (A329(M)/London Road) Junction. 2,322,431 northbound on-slip widening January 2019 Windsor and Measures to improve pedestrian priority and streetscape around the castle and eastern gateway, Programme Entry 9 Windsor Town Centre Package 1,562,500 Maidenhead purchase of vehicles for a demand-responsive bus service, and car park expansion. January 2019 Slough SMaRT Phase 3 A4 Park and ride to serve Slough, Maidenhead and Windsor town centres with bus priorities on the A4 10 Slough Deferred 4,160,000 West Park and Ride to link with SMaRT Phase 1 infrastructure. A new bridge next to the existing Barkham Bridge (located between Barkham Street and Recommended for 11 Wokingham Wokingham Barkham Bridge 4,235,641 Langley Common Road) to facilitate 2-way traffic through the existing bottleneck. programme entry Slough A355 Route Extending the existing A355 Route Enhancement to address congestion north of the Three Tuns 12 Slough 3,600,000 Enhancement Phase 2 A4/A355 intersection with carriageway widening, bus priorities and a new footbridge. Slough Town Centre to M4 Link between A332 and A355 to provide a direct route from Slough town centre to M4 Junction 6 13 Slough 9,600,000 Junction 6 Link avoiding A4 Bath Road and Tuns Lane. Wokingham Tan House A new Disability Discrimination Act compliant crossing of the railway where an at-grade crossing was 14 Wokingham 1,200,000 Crossing previously provided. A temporary footbridge is currently provided but is not “step free”. Conversion of heavy rail to bus-based mass rapid transit, new roads, pedestrian and cycling 15 Slough Slough Chalvey Regeneration 28,000,000 infrastructure, flood alleviation and waste heat recovery to support regeneration. Wokingham California A public realm project that will deliver an enhanced user experience for residents, shoppers, patrons 16 Wokingham 3,581,129 Crossroads and all who travel through California Crossroads.

Item 8 BLTB 14 March 2019 Revised Local Growth Fund Programme 2015/16 to 2020/21 update This page is intentionally left blank AGENDA ITEM 9

BERKSHIRE LOCAL TRANSPORT BODY (BLTB)

REPORT TO: BLTB DATE: 14 March 2019

CONTACT OFFICER: Joe Carter, Director of Regeneration, Lead Officer to the BLTB

DRAFT

PART I

Item 9: TfSE – Proposal to Seek Statutory Status – Informal Engagement

Purpose of Report

1. On Monday 10 December 2018 the Transport for the South East Shadow Board (TfSE) approved a draft Proposal to Government for informal engagement (See Appendix 1). Staff from TfSE have separately approached each of the Berkshire Unitary Authorities and Thames Valley Local Enterprise Partnership to gather responses to the draft proposal.

2. The informal engagement period will close on 1 March 2019, and a final Proposal will be recommended to the Shadow Partnership Board meeting on 18 March 2019, which will be followed by a formal period of consultation which will run from 2 May to 31 July 2019.

3. Unfortunately, this timetable does not quite fit with your schedule of meetings, and therefore the purpose of this report is to seek your retrospective endorsement of the comments set out below, and to gather any further additions or amendments you may have which can be contributed to the TfSE meeting on 18 March.

Recommendation

4. You are recommended to i) endorse the response set out in paragraph 22 ii) suggest any further additional comments or amendments iii) note that TfSE proposes to conduct formal consultation on its final proposal to government and that this will be the subject of a further report to your meeting on 18 July 2019

Other Implications

Financial

5. TfSE collects an annual contribution from its constituent authorities. The current rate is £58,000 per county authority and £30,000 per unitary authority. The six Berkshire Unitary Authorities have previously chosen to act together and join TfSE via this joint committee (BLTB). Therefore, for the purposes of subscriptions, BLTB has been treated as a county authority. Slough BC, acting

Item 9 BLTB 15 March 2019 TfSE – proposal to seek statutory status – informal engagement Page 155 as the lead authority for the joint committee has paid the subscription and collected a one-sixth share from each unitary (£9,667 each).

6. TfSE received a contribution towards the development of its Transport Strategy of £1m from the DfE.

Risk Management

7. There are no significant risks for BLTB.

Human Rights Act and Other Legal Implications

8. Slough Borough Council will provide legal support for the BLTB should any questions arise.

Supporting Information

9. The subject of the consultation is the exact terms of a Proposal to Government requesting statutory status for TfSE, which if approved by Parliament, will become a second sub-national transport body alongside Transport for the North, which was confirmed in April 2018. The draft proposal is set out in Appendix 1.

10. The statutory basis for sub-national transport bodies is set out in Part 5A of the Local Transport Act 20081, as amended by the Cities and Local Government Devolution Act 2016, which says that “the Secretary of State may by regulations establish a sub-national transport body for any area in England outside Greater London” (s102E(1)) and it goes on to set the conditions and limits for such arrangements.

11. The twin purposes of creating sub-national transport bodies are to facilitate the development of a transport strategy and so promote economic growth for the area.

12. The Act requires a new sub-national transport body to be promoted by its constituent authorities, to have the consent of its constituent authorities, and that the Proposal has been the subject of consultation within the area and with neighbouring authorities. TfSE are planning that the formal consultation running from 2 May – 31 July 2019 will be carried out in a way that meets this condition.

13. The Proposal must also set out the membership, voting powers, decision- making arrangements, functions and general powers.

14. The attached draft Proposal to government confirms that the 16 constituent authorities are proposed as: Bracknell Forest; Brighton and Hove; East Sussex; Hampshire; Isle of Wight; Kent; Medway; Portsmouth; Reading; Slough; Southampton; Surrey; West Berkshire; West Sussex; Windsor and

1 http://www.legislation.gov.uk/ukpga/2008/26/part/5A

Item 9 BLTB 15 March 2019 TfSE – proposal to seek statutory status – informal engagement Page 156 Maidenhead; and Wokingham. It also confirms that the six Berkshire Unitaries will act together via this joint committee, the Berkshire Local Transport Body.

15. The Proposal sets out arrangements for involving the five Local Enterprise Partnerships; two National Park Authorities, 44 Boroughs and Districts and the transport industry voice in governance

16. The Proposal identifies the powers TfSE wants to draw down from central government; it goes on to identify a number of powers it hopes to exercise concurrently with local authorities. The Proposal emphasises that it will only ever exercise these local powers with the consent of the local authority concerned.

17. In a separate exercise, TfSE is currently developing its Transport Strategy, and will also be subject to consultation with constituent authorities and other stakeholder partners.

18. For more information please visit www.transportforthesoutheast.org.uk

19. Members of BLTB will recall that Transport for the South East was debated on 16 March 2017 when you resolved to “…participate in the shadow arrangements for a sub-national transport body for the south east; and that Councillor Page represent BLTB at the shadow board meetings.” (minute 22 refers).

20. Members will further recall that TfSE subscriptions and membership were debated and agreed on 16 November 2017 (minute 19 refers); and that on 19 July 2018 you authorised Joe Carter (Director of Regeneration Slough BC) to sign the collaboration agreement on your behalf (minute 15 refers).

Draft Response to the Informal Engagement

21. This matter has been considered by the Berkshire Strategic Transport (Officers’) Group and by individual transport authorities and by the LEP.

22. The following draft response has been submitted to TfSE and you are invited to suggest further amendments or additions before endorsing the response.

i) Berkshire Local Transport Body continues to support the creation of Transport for the South East, and reaffirms its position representing the six Berkshire Unitary Authorities ii) It welcomes the detail set out in the draft proposal to government and supports the engagement process currently underway iii) It supports the aim of coordinating Transport Strategy in order to promote economic growth iv) It supports the emphasis on a strong influencing role and, by implication, relatively low-key role in delivering transport policies and programmes v) It supports the intention to operate by consensus with the Partnership Board

Item 9 BLTB 15 March 2019 TfSE – proposal to seek statutory status – informal engagement Page 157 vi) It supports the seeking of concurrent powers with the local transport authorities, and the commitment to only use such powers with the consent of the local transport authority concerned.

Conclusion

23. The emergence of Transport for the South East as a potential sub-national transport body including the Berkshire area is to be welcomed.

Background Papers

24. Correspondence with TfSE

Item 9 BLTB 15 March 2019 TfSE – proposal to seek statutory status – informal engagement Page 158 Appendix 1

TRANSPORT FOR THE SOUTH EAST

Draft Proposal for Informal Engagement

December 2018

1. Executive Summary

 Why TfSE needs Statutory Status – the document needs to clearly set out the value the STB will add beyond a joint committee or collaboration. The impact of not having TfSE is that the current pressures on strategic transport infrastructure will continue to grow. Without TfSE there will not be a regional organisation to make the case for investment in infrastructure, leading to increased congestion, inability to consider multi-modal investments or cross boundary schemes that will benefit the end user. o Traction with Government and key stakeholders (Highways England & Network Rail) who will need to have ’due regard’ to the Transport Strategy. TfSE will need to have statutory status if it is to take on specific legal power and responsibilities relating to the operation of the transport system in its area o Permanence – STB needs to be in place on permanent basis if it is to deliver on its strategy in the longer term. Achieving statutory status will enable TfSE to operate on a permanent basis and will provide a governance structure that matches the lifecycle of major infrastructure projects. o Facilitate the delivery of jobs, housing and growth – the Transport Strategy will identify the strategic transport priorities. Implementation of the schemes will connect economic centres and international Gateways. The region has a significant impact on GVA and this can be increased with investment in strategic infrastructure. o Geography of TfSE region – polycentric nature of the region means that strategic transport corridors cross local authority boundaries and can best be addressed by a body with the regional scale of TfSE.  Aims of the Transport Strategy: Local Transport Authorities and Local Enterprise Partnerships across South East England, operating in partnership with TfSE, will develop a long term and ambitious Transport Strategy. The Strategy will identify the strategic transport priorities for the region and will develop an investment plan to support the delivery of the identified schemes.  Powers and Functions of TfSE: The Executive Summary will set out the powers and functions which TfSE is seeking, including General Functions and more specific Transport Functions, such as influencing the development of rail franchise specifications and implementation of an integrated, smart ticketing scheme.

Page 159  Timescale: TfSE is aiming to secure statutory status in 2020. The draft Proposal will be subject to a public consultation from May 2019 to July 2019, prior to being submitted to Government in December 2019.  Stakeholder Engagement: the draft Proposal has been developed in partnership with TfSE’s members and stakeholders. The constituent authorities and Local Enterprise Partnerships have steered the development of the Proposal, with input from the various members of the Transport Forum. We will secure support from key businesses in the TfSE area prior to submission to Government and will engage with a range of partners during the public consultation exercise. Letters of support from key stakeholders and businesses will be attached to the Proposal.

Page 160 2. Transport for the South East

2.1 Transport for the South East (TfSE) was established in shadow form in June 2017. It brings together 16 Local Transport Authorities, five Local Enterprise Partnerships and other key stakeholders, including environmental groups, transport operators, district and borough authorities and national agencies, to develop an ambitious Transport Strategy for the South East region.

2.2 TfSE will support the growth of the South East economy, ensuring the delivery of a high quality, sustainable and integrated transport system:  that supports increased productivity to grow the South East and UK economy and compete in the global marketplace  that works to improve safety, quality of life and access to opportunities for all  that protects and enhances the South East’s unique natural and historic environment

2.3 TfSE is in the process of developing its Transport Strategy, which will run until 2050 and it will be accompanied by a clear investment plan for strategic infrastructure schemes in the South East. It will identify how targeted investment in strategic infrastructure could enable the GVA of the South East to grow up to £500 billion by 2050, with almost 3 million additional jobs.

2.4 During its operation in Shadow form, TfSE has already added considerable value in bringing together key partners and stakeholders to influence Government thinking. To date TfSE has contributed to the Roads Investment Strategy 2 and Major Road Network consultation.

2.5 The TfSE area and its key issues:  Overview of the TfSE area drawing on the analysis given in the Economic Connectivity Review, Strategic Economic Plans and emerging Local Industrial Strategies. Include a map of the key towns, gateways, transport corridors and key sectors.  Overview of the economy  Economic Outcomes of Transport  Context the key issues which need addressing e.g. where high levels of usage of the transport system is blocking the full growth potential and where links need to be enhanced to access a wider range of opportunities.  Highlight housing challenge, importance of international gateways, end user benefits and air quality. Need to highlight the importance of innovation and digital and the impact that it is likely to have on transport – links to Innovation South.

2.6 The scale of the challenge and why change is needed:  Continuing underinvestment in the south east (IPPR research on investment per head outside of London)  Underperformance of coastal strip  Poor connectivity – particularly orbital routes  Region is not reaching its full potential (Economic Connectivity Review data to support this)

Page 161 3. The Ambition – this section will set out the vision for TfSE, highlight the economic characteristics of the area and the background to TfSE

The South East is crucial to the UK economy and is the nation’s major international gateway for people and businesses.

We will grow the South East’s economy by facilitating the development of a high quality, integrated transport system that makes the region more productive and competitive, improves access to opportunities for all and protects the environment.

3.1 The South East is a powerful regional economy contributing more than £200 billion to the UK economy each year. It is home to major international gateways, including Gatwick and Heathrow airports, as well as Dover, Southampton and Portsmouth ports. It has rail connections with the rest of the UK and into Europe, and a considerable road network, including key parts of the Strategic Road Network, proposed Major Road Network and a number of highly significant local roads.

3.2. Many international and national companies are based in the region, alongside a large number of thriving, innovative SMEs. Key Sectors – include reference here.

3.3 However, our infrastructure is operating beyond capacity and unable to sustain ongoing growth. Underinvestment in road and rail infrastructure is causing issues for our residents and businesses.

3.4 Proximity to London – and impacts, including travel to work patterns. The nature of the relationship with London means that there are good connections into London, but orbital routes have suffered from lack of investment.

3.5 Environment and protected landscapes – the South East is an area of unrivalled natural beauty. It is home to two National Parks, a number of Areas of Outstanding Natural Beauty and much of the region is allocated as Green Belt. TfSE will play a role in maintaining and protecting the landscape. Additionally, there are a number of areas with air quality issues. It will be important that TfSE is enabled to address these issues and improve air quality for our residents.

Page 162 4. TfSE: Strategic and Economic Case

 Background to STBs – the Government introduced powers to establish Sub- national Transport Bodies through the Cities and Local Government Devolution Act 2016. The legislation sets out that STBs will have General Functions, including to develop a Transport Strategy and provide advice to the Secretary of State. Once statutory status has been secured the Government must have due regard to the Transport Strategy which means that they must actively consider and respond to TfSE proposals. As well as exerting strategic influence there is also the potential for the STB to propose specific transport functions, including the operation of smart ticketing schemes, highway improvement construction and maintenance and rail franchising.  Why do we need TfSE o Why TfSE covers the geography designated o How TfSE will sustain and grow the South East’s contribution to the UK economy o How TfSE will help sustain growth in the regional economy o How TfSE will help facilitate strategic transport improvements o How TfSE will help improve social inclusion through improved access to jobs education and health facilities  The value that could be added by establishing TfSE as a statutory STB: o One voice for strategic transport in the South East – Transport for the South East will offer an effective mechanism for Government to engage with local authorities and LEPs in the region. The collective strength of the partnership will offer a more effective way to develop clear priorities for investment and to influence critical spending decisions. This will provide traction with Government and key stakeholders (Highways England & Network Rail) who will need to have ’due regard’ to the Transport Strategy. o Local Democratic Accountability – the Partnership Board will comprise elected representatives and business leaders who will have responsibility for the delivery of the Transport Strategy. TfSE offers a route to engage with other emerging STBs and Transport for London. o Delivering benefits for the end user – TfSE can support the delivery of region wide programmes that will offer considerable benefits to the end user. Integrated travel solutions, combined with smart ticketing will operate more effectively at a regional scale and can best be facilitated by a regional body, than by individual organisations. o Facilitating economic growth –The Transport Strategy will facilitate the delivery of jobs, housing and growth. Implementation of strategic, cross-boundary schemes, particularly investment in the orbital routes, will connect economic centres and international Gateways. The region has a significant impact on GVA and this can be increased with investment in strategic infrastructure. o Access to International Gateways – The Economic Connectivity Review highlighted the importance of key corridors connecting the international gateways in the South East to the rest of the UK. TfSE will work to ensure improved access to these gateways including first mile- last mile connectivity. o Permanence – securing statutory status offers TfSE the security to deliver the Transport Strategy to 2050. Achieving statutory status will enable TfSE to operate on

Page 163 a permanent basis and will provide a governance structure that matches the lifecycle of major infrastructure projects. o Geography of TfSE region – polycentric nature of the region means that strategic transport corridors cross local authority boundaries and can best be addressed by a body with the regional scale of TfSE. Improved orbital connections required to enhance regional cohesion and improve access to international gateways. This will support the national economy, given the importance of these gateways..  The strategic and economic case for each of the powers and responsibilities being sought The powers will be sought in a way which means they will operate concurrently and with the consent of the constituent authorities. o Strategic influence: the benefits of being able to set a single vision for the longer term. Acting as a statutory consultee and influencing the development of national programmes, such as the Road Investment Strategy and Major Road Network. TfSE has already worked with Government on a number of proposals that will help to support economic growth in the region, including RIS2, influencing rail franchising discussions and providing collective views on schemes such as southern and western rail access to Heathrow. o Collective voice on strategic transport planning: the benefits of a single voice and promoting cross regional transport priorities o Complement existing powers and responsibilities of LTAs o Environmental enhancement and protection as a key part of scheme delivery. o Delivering improvements in air quality and reductions in carbon dioxide emissions o Lobbying for investment in transport projects o Liaison with key stakeholders and delivery partners o Taking forward joint issues o Effective working with other organisations who operate at a similar level o Possible development and sponsorship of transport initiatives such as integrated ticketing – working to improve customer journeys and implement digital transport solutions. o Possible operation/delivery of transport initiatives at a regional scale where there is a clear business case for doing so.

Page 164 5. Constitutional Arrangements

Transport for the South East’s (“TfSE”) proposal to form a Sub-National Transport Body (“STB”) builds on our track record to date and our objective to act as a strong voice for the whole of the South East. Our draft proposal sets out how TfSE would strengthen existing arrangements, ensuring we align with primary legislation. This proposal sets out a summary of our proposal which should be proportionate and effective to build on our current strength of business and civic leadership.

Requirements from Legislation

Name 5.1 The name of the STB would be ‘Transport for the South East (“TfSE”)’ and the area would be the effective boundaries of our ‘constituent members’. A map would be provided as part of any formal proposal.

Members 5.2 The membership of the STB is listed below: o Bracknell Forest Borough Council o Brighton and Hove City Council o East Sussex County Council o Hampshire County Council o Isle of Wight Council o Kent County Council o Medway Council o Portsmouth City Council o Reading Borough Council o Slough Borough Council o Southampton City Council o Surrey County Council o West Berkshire Council o West Sussex County Council o The Royal Borough of Windsor and Maidenhead Council o Wokingham Borough Council

Partnership Board 5.3 The current Partnership Board is the only place where all ‘constituent members’ are represented at an elected member level2. Therefore this Board will need to have a more formal role, including in ratifying key decisions. This would effectively become the new ‘Partnership Board’ and meet at least twice per annum. The Partnership Board could agree through Standing Orders if it prefers to meet more regularly.

5.4 Each constituent authority will appoint one of their councillors / members or their elected mayor as a member of TfSE on the Partnership Board. Each constituent authority will also appoint another one of their councillors / members or their elected

2 The six constituent members of the Berkshire Local Transport Body (BLTB) will have one representative between them on the Partnership Board.

Page 165 Mayor as a substitute member (this includes directly elected Mayors as under the Local Government Act 2000). The person appointed would be that authority’s elected mayor or leader, provided that, if responsibility for transport has been formally delegated to another member of the authority, that member may be appointed as the member of the Partnership Board, if so desired.

5.5 The Partnership Board may delegate the discharge of agreed functions to its officers or a committee of its members in accordance with a scheme of delegation or on an ad hoc basis. Further detail of officer groups and a list of delegations will be developed through a full Constitution.

Co-opted Members 5.6 TfSE propose that governance arrangements for a statutory STB should maintain the strong input from our business leadership, including LEPs and other business representatives. The regulations should provide for the appointment of persons who are not elected members of the constituent authorities to be co-opted members of the TfSE Partnership Board.

5.7 A number of potential co-opted members are also set out in the draft legal proposal. Co-opted members would not automatically have voting rights but the Partnership Board can resolve to grant voting rights to them on such issues as the Board considers appropriate.

Chair 5.8 The Partnership Board will agree to a chair and vice-chair of the Partnership Board. The Partnership Board may also appoint a single or multiple Vice-Chairs from the constituent members. Where the Chair or Vice-Chair is the representative member from a Constituent Authority they will have a vote.

Proceedings 5.9 It is expected that the Partnership Board will continue to work by consensus but to have an agreed approach to voting where necessary.

5.10 Whilst there is a clear expectation that the Partnership Board would work by consensus, where consensus cannot be reached and for certain specific decisions an agreed mechanism is needed to ensure that decisions can be made.

5.11 A number of voting options were considered to find a preferred option that represents a straightforward mechanism, the characteristics of the partnership and which does not provide any single authority with an effective veto. We also considered how the voting metrics provide a balance between county and other authorities, urban and rural areas and is resilient to any future changes in local government structures.

5.12 The Steering group considered these options and preferred the population weighted option based on the population of the Constituent Authority with the smallest population, the Isle of Wight with 140k.

Page 166 5.13 This option requires that the starting point for decisions will be consensus, and if that can’t be achieved then decisions will require a simple majority of those Constituent Bodies who are present and voting. The decisions below will however require both a super-majority, consisting of three quarters of the weighted vote in favour of the decision, and a simple majority of the constituent authorities appointed present and attending at the meeting: (i) The approval and revision of Transport for the South East’s (“TfSE”) Transport Strategy; (ii) The approval of TfSE annual budget; (iii) Changes to the TfSE constitution. The population weighted vote would provide a total of 54 weighted votes, with no single veto. A table showing the distribution of votes across the constituent authorities is set out in Appendix 1. This option reflects the particular circumstances of TfSE, being based on the population of the smallest individually represented constituent member who will have one vote, and only a marginally smaller proportionate vote. It is considered that this option is equitable to all constituent authority members, ensures that the aim of decision making consensus remains, and that smaller authorities have a meaningful voice, whilst recognising the size of the larger authorities in relation to certain critical issues.

5.14 The population basis for the weighted vote will be based on ONS statistics from 2016 and reviewed every 10 years.

5.15 The Partnership Board is expected to meet twice per year, where full attendance cannot be achieved, the Partnership Board will be quorate where 50% of Constituent Members are present.

Scrutiny Committee (To be confirmed – pending outcome of discussions with DfT) 5.16 TfSE will establish a scrutiny committee and each ‘constituent authority’ will be entitled to appoint a member to the committee and a ‘substitute’ nominee. Such appointees cannot be otherwise members of TfSE, including at the Partnership Board.

5.17 The scrutiny committee appointed by TfSE may not include a member, substitute member or co-opted member of TfSE, but may include co-opted persons representative of non-constituent authorities and non-councillor representatives of passengers, road users, employers and employees.

Standing Orders 5.18 TfSE will need to be able to make, vary and revoke standing orders for the regulation of proceedings and business, including that of the scrutiny committee. This will ensure that the governance structures can remain appropriate to the effective running of the organisation.

5.19 In regards to changing boundaries and therefore adding or removing members, TfSE would have to make a new proposal to Government under Section 102Q of the Local Transport Act 2008 and require formal consents from each Constituent Authority.

Page 167 Miscellaneous 5.20 It may be necessary that certain additional Local Authority enactments are applied to TfSE as if TfSE were a Local Authority, including matters relating to staffing arrangements, pensions, ethical standards, and provision of services etc. These are set out in the draft legal proposal.

5.21 TfSE also proposes to seek the functional power of competence as set out in section 102M of the Local Transport Act 2008.

5.22 TfSE will consider options for appointing to the roles of a Head of Paid Service, a Monitoring Officer and a Chief Finance Officer whilst considering possible interim arrangements.

Funding 5.23 TfSE will work with partners and Department for Transport (“DfT”) to consider a sustainable approach to establishing the formal STB as effectively as possible.

Governance

Transport Forum and Senior Officer Group 5.24 The Partnership Board will appoint a Transport Forum. This will be an advisory body to the Senior Officer Group and Partnership Board, comprising a wider group of representatives from user groups, operators, District and Borough Councils as well as Government and National Agency representatives.

5.25 The Transport Forum will meet four times a year and be chaired by an independent person appointed by the Partnership Board. The Transport Forum may also appoint a Vice-Chair for the Transport Forum, who will chair the Transport Forum when the Chair is not present.

5.26 The Transport Forum’s terms of reference will be agreed by the Transport for the South East Partnership Board. It is envisaged that the Transport Forum will provide technical expertise, intelligence and information to Senior Officer Group and the Partnership Board.

5.27 The Partnership Board and Transport Forum will be complemented by a Senior Officer Group representing members at official level providing expertise and co-ordination to the TfSE programme. The Steering Group will meet monthly.

Page 168 6. Functions

Transport for the South East’s proposal is to become a statutory Sub National Transport Body as set out in section part 5A of the Local Transport Act 2008. The precise legal proposal is set out in a separate document but includes the following functions.

General Functions 6.1 Transport for the South East proposes to have the ‘General Functions’ as set out in Section 102H (1) including: a. to prepare a Transport Strategy for the area; b. to provide advice to the Secretary of State about the exercise of transport functions in relation to the area (whether exercisable by the Secretary of State or others); c. to co-ordinate the carrying out of transport functions in relation to the area that are exercisable by different constituent authorities, with a view to improving the effectiveness and efficiency in the carrying out of those functions; d. if the STB considers that a transport function in relation to the area would more effectively and efficiently be carried out by the STB, to make proposals to the Secretary of State for the transfer of that function to the STB; e. to make other proposals to the Secretary of State about the role and functions of the STB. (2016, 102H (1))5

6.2 The General Functions are regarded as the core functions of a Sub-National Transport Body and will build on the initial work of Transport for the South East in its shadow form. To make further proposals to the Secretary of State regarding constitution or functions, Transport for the South East will need formal consents from each ‘Constituent Member’.

6.3 Transport for the South East recognises that under current proposals the Secretary of State will remain the final decision-maker on national transport strategies, but critically that the Secretary of State must have regard to a Sub- National Transport Body’s statutory Transport Strategy. This sets an important expectation of the strong relationship Transport for the South East aims to demonstrate with Government on major programmes like the Major Road Network and Rail Upgrade Plan.

Local Transport Functions 6.4 Initial work has identified a number of additional powers that Transport for the South East may require that will support the delivery of the Transport Strategy. The table below provides an assessment of these functions and will be used to support the informal engagement with constituent authorities and members of the Shadow Partnership Board.

6.5 The powers which are additional to the general functions relating to STBs will be requested in a way that means they will operate concurrently and with the consent of the constituent authorities.

Page 169 Appendix 1

Table 1: Powers and Responsibilities for further discussion

Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power General functions Section 102 H of the Prepare a transport All the general powers Functions required for Local Transport Act 2008 strategy, advise the set out in Section 102H. TfSE to operate as a Secretary of State, STB and meet the co-ordinate the requirements of the carrying out of enabling legislation to transport functions, facilitate the make proposals for development and the transfer of implementation of

Page 170 Page functions, make other transport strategies for proposals about the the area and thereby role and functions of further the economic the STB. growth objective.

Rail Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power Right to be consulted The right of a The right to be TfSE requires a strong, TfSE acts as the about new rail franchises Passenger Transport consulted about rail formal role in decision collective voice of (Section 13 of the Executive to be franchises in its area. making over and above constituent authorities Railways Act 2005 – consulted before the that which is available and delivers a regional Railway Functions of Secretary of State to individual constituent perspective and Passenger Transport issues an invitation to authorities. The right of consensus on the Executives) tender for a franchise consultation is priorities for rail in its agreement important because it area. confirms TfSE’s role as a strategic partner. This

Page 171 Page power would enable TfSE to exert strategic influence over future rail franchises to ensure the potential need for changes to the scope of current services and potential new markets identified by TfSE are considered. Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power Set High Level Output Power of Secretary of Power to act jointly with Exert strategic influence TfSE acts as the Specification (HLOS) for State to set the HLOS the Secretary of State over the future collective voice of Rail setting out objectives to set the HLOS for the development of the rail constituent authorities (Schedule 4A, paragraph for next railway rail network in TfSE network in the TfSE and delivers a regional 1D, of the Railways Act control period. area. area. The power to perspective and 1993) influence the objectives consensus on the within the HLOS would priorities for rail in its enable TfSE’s area. aspirations for transformational investment in rail

Page 172 Page infrastructure that will facilitate economic growth Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power Highways Set Road Investment Power of Secretary of Power to act jointly with TfSE requires a strong, TfSE acts as the Strategy (RIS) for the State to set and vary the Secretary of State formal role in decision collective voice of its Strategic Road Network the RIS to set and vary the RIS making over and above constituent authorities (RIS) in the TfSE area. that which is available and delivers a regional to individual constituent perspective and (Section 3 and Schedule authorities. This power consensus on the 2 of the Infrastructure Act would enable TfSE to priorities for the RIS. 2015) exert strategic influence, and ensure TfSE’s aspirations for

Page 173 Page transformational investment in road infrastructure that will facilitate economic growth as identified in its Transport Strategy are reflected in the RIS. Enter into agreements to Power that local Concurrent power to These powers will TfSE could overcome undertake certain works highway authorities enter into such enable TfSE to promote the need for complex on Strategic Road currently have to agreements with and expedite the ‘back-to-back’ legal and Network, Major Road enter into an highway authorities for delivery of regionally funding agreements Network or local roads. agreement with other trunk roads and local significant schemes, between neighbouring (Section 6(5) of the highway authorities to roads across boundaries that authorities improving Highways Act 1980, construct, reconstruct, otherwise might not be efficiency by reducing (trunk roads) & Section 8 alter, improve or progressed, scheme development of the Highways Act 1980 maintain roads time and reducing (local roads) overall costs. Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power Acquire land to enable Power to acquire land Concurrent power Allow preparations for Enable TfSE to construction, for various purposes. the construction of a expedite the delivery of improvement, or mitigate highways scheme to be regionally adverse effects of expedited where significant schemes, highway construction. highway authorities are that otherwise might not (Sections 239,240,246 not in a position to be progressed. Land and 250 of the Highways acquire land. Power acquisition by TfSE Act 1980) only to be exercisable could facilitate quicker with the consent of the scheme delivery. highway authority Construct highways, Powers to construct Concurrent powers that Without these powers Enable TfSE to enter

Page 174 Page footpaths, bridleways highways, footpaths will enable TfSE to TfSE would not be able into contractual (Sections 24,25 & 26 of and bridleways. promote, coordinate to enter into any arrangements that will the Highways Act 1980) and fund road schemes contractual expedite the delivery of arrangement in relation regionally significant to procuring the schemes set out in its construction, Transport strategy that improvement or cross constituent maintenance of a authority boundaries highway or the that otherwise might not construction or be progressed. improvement of a trunk road. Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power Make capital grants for public transport facilities Make capital grants for Power of a local TfSE to be granted this This will enable TfSE to This will enable TfSE to the provision of public authority to pay power concurrently with fund public transport support the funding and transport facilities capital grants for the local authorities. improvements. delivery of joint projects (Section 56(2) of the provision of facilities with constituent local Transport Act 1968) for public passenger authorities. transport.

Page 175 Page Bus Service Provision Duty to secure the Local transport TfSE to have this duty Would enable TfSE to Travel to work areas do provision of Bus Services authorities and concurrently with the fill in identified gaps in not respect local (Section 63(1) Transport Integrated transport local transport bus service provision in authority boundaries. Act 1985) have a duty to authorities in its area its geography or secure Potential for TfSE to secure the provision the provision of secure regionally of such public regionally important bus important bus services passenger transport services covering one that would not services as it or more constituent otherwise be provided considers appropriate authority areas in the and which would not future which would not otherwise be otherwise be provided. provided. Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power Quality Bus Partnerships Powers to enable Concurrent power for To facilitate the To expedite the (The Bus services Act local transport TfSE to be able to enter introduction of Quality introduction of Quality 2017 Sections 113C – authorities and into Advanced Quality Partnership schemes to Partnership schemes 113O & Sections 138A – Integrated Transport Partnerships and be introduced in an covering more than one 138S) Authorities to enter Enhanced Plans and area covering more local transport authority into Advanced Quality Schemes. than one constituent area which otherwise Partnerships and authority. might not be introduced Enhanced Partnership Plans and Schemes to improve the quality of services

Page 176 Page and facilities within an identified area. Bus Service Franchising Power of Mayoral Power for TfSE to To facilitate the To expedite the (The Bus Services Act Combined Authorities implement bus service introduction of bus introduction of 2017) to implement bus franchising in its area service franchising in an franchising franchising in their area covering more arrangements covering area. than one constituent more than one local authority. transport authority area which otherwise might not be introduced. Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power Smart Ticketing Introduce Integrated Powers of local Concurrent powers with These powers will Expedite the Ticketing Schemes transport authorities local transport enable TfSE to procure introduction of a cost (Sections 134C- 134G & to make advanced, authorities in the TfSE services, goods, effective smart and Sections 135-138 joint and through area equipment and/or integrated ticketing Transport Act 2000) ticketing schemes infrastructure; enter into system on a regional contracts to deliver scale smart ticketing and receive or give payments. Air Quality Page 177 Page Establish Clean Air Power of local traffic Powers to introduce Air quality issues do not Ability to expedite the Zones authority and road user charging respect local authority introduction of larger (Sections 163-177A of integrated transport schemes to enable boundaries which may scale air quality zones the Transport Act 2000 – authorities to make charged clean air zones necessitate Clean Air where air quality issues Road User Charging) local charging to be introduced Zones being introduced extend across existing schemes imposing across constituent boundaries. Reduced charges in respect of authority boundaries. implementation and the use or keeping of operating costs motor vehicles on compared to two or roads. more continuous zones. Function/Power Description of What is TfSE seeking Why power is being Added benefit of TfSE existing sought having this power function/power Other Powers Promote or oppose bills Local Authorities have Power to promote or Enable TfSE to promote Expedite the delivery of in Parliament the power to promote oppose Bills in coordinate and fund regionally significant Section 239 Local or oppose Bills in Parliament. Transport regionally significant schemes (including Government Act 1972 Parliament. Under the and Works Act powers infrastructure schemes railway schemes) that Transport and Works to apply for orders to Transport and Work Act cross constituent Act 1992, a body that promote, construct or powers are the means authority boundaries has power to promote operate certain types of by which railway, that otherwise might not or oppose bills also transport facilities. tramway, inland be progressed. has the power to waterways and coastal apply for an order to piers are promoted and

Page 178 Page construct or operate operated. certain types of infrastructure (e.g. railways, tramways waterways & piers) Incidental amendments to Incidental The same incidental To enable TfSE to the Local Government amendments to amendments as were function as a type of Act 1972, Localism Act enable TfSE to included in the TfN S.I. local authority 2011, Local Government operate as a type of Pension Scheme local authority with Regulations 2013, as per duties in respect of the TfN S.I. staffing, pensions, monitoring and the provision of information about TfSE. Appendix 1

Possible Functions not being sought 6.6 Transport for the South East has also given consideration to a wide range of powers does not propose seeking the functions set out in the table below

Function not being sought Rationale Act as co-signatories to rail franchises No existing involvement from constituent Be responsible for rail franchising authorities in rail operations and no Carry passengers by rail. current aspirations to become involved in this area. Set priorities for local authorities for TfSE will only be responsibility for roads that are not part of the Major Road identifying priorities on the Major road Network Network.

Being responsible for any highway No rationale for TfSE involvement in maintenance responsibilities. routine maintenance of Major Road Network or local roads. Take on any consultation function instead of an existing local authority.

Give directions to a constituent authority This power contained in the enabling about the exercise of transport functions legislation will not be requested. by the authority in their area.

Page 179 6. Summary of Support and Engagement  The draft Proposal will be shaped and will be endorsed by the Shadow Partnership Board in March 2019 prior to the launch of the consultation.  During the consultation process, the draft Proposal will be made available on the TfSE website. Meetings will be held with key contacts, such as Network Rail, Highways England, Transport for London, England’s Economic Heartlands and the Transport Forum.  Following the consultation exercise TfSE will update the draft Proposal and publish a summary of the consultation comments received.  TfSE will seek consent from its constituent authorities and the final draft Proposal will be endorsed by the Shadow Partnership Board in autumn 2019.  The final Proposal will include a summary of the engagement process, including a list of the organisations engaged in the process and an appendix with a number of letters of support from key organisations and businesses.

Page 180 Appendix 1 – Distribution of votes

Number TfSE Constituent Population1 of Authorities Votes2 Brighton and Hove City 287,173 2 Council

East Sussex County 549,557 4 Council

Hampshire County Council 1,365,103 10

Isle of Wight Council 140,264 1

The Kent County Council 1,540,438 11

Medway Council 276,957 2

Portsmouth City Council 213,335 2

Southampton City Council 250,377 2

Surrey County Council 1,180,956 2 West Sussex County 846,888 6 Council Bracknell Forest Council 119,730

Reading Borough Council 162,701

Slough Borough Council 147,736

West Berkshire Council 158,576

The Royal Borough of 149,689 Windsor and Maidenhead

Wokingham Borough Council 163,087 Berkshire Local Transport 901,519 6 Body (Total) Total 7,552,567 54

1 Population as per ONS 2016 Estimates 2 Number of votes = Population/140,000 (the population of constituent authority with the smallest population, this being the Isle of Wight.

Page 181 Page 182 AGENDA ITEM 10

BERKSHIRE LOCAL TRANSPORT BODY (BLTB)

REPORT TO: BLTB DATE: 14 March 2019

CONTACT OFFICER: Joe Carter, Director of Regeneration, Lead Officer to the BLTB

PART I

Item 10: Transport for the South East – call for Major Roads Network schemes

Purpose of Report

1. To advise that government has announced that a fund of £3.5 billion is available to improve the Major Roads Network (MRN) across the UK. The MRN is made up of vital A roads administered by local authorities and sits below the national network of motorway and trunk roads (known as the Strategic Roads Network or SRN) managed by Highways England.

2. Further, the government has indicated sub-national transport bodies (including TfSE) will play a major role in identifying priorities for their areas. To this end, TfSE has issued a call for schemes with a deadline of May 2019.

Recommendation

3. You are asked to note the TfSE call for MRN schemes and that a further report, detailing any schemes submitted to TfSE will be produced for the July BLTB meeting.

Other Implications

Financial

4. There are no direct financial implications of this report for Berkshire Local Transport Body. In the event that any Thames Valley Berkshire scheme is selected by government to receive MRN funding, it is anticipated that this funding will support the capital costs of the MRN.

5. The call for bids requires the promoter to make a 15% local contribution to the capital cost of each scheme.

Risk Management

6. BLTB are not prioritising the submitted schemes – this will be done by TfSE – therefore there are no risks for Berkshire Local Transport Body associated with the government’s Major Roads Network call for schemes.

7. Any local authority that decides to submit a scheme in response to this call for bids can also seek funding for the same scheme from any other source; there is

Item 10: BLTB 14 March 2019 TfSE Call for Major Roads Network Schemes

Page 183 no risk that by choosing to bid it will reduce the chances of securing funding from other sources.

Human Rights Act and Other Legal Implications

8. Slough Borough Council will provide legal support for the BLTB, should any questions arise.

Supporting Information

9. Department for Transport guidance gives confirmation of the types of schemes that are eligible: • DfT contribution to be between £20m and £50m (although the lower threshold will not be applied rigidly) • Schemes over £50m should be dealt with as potential Large Local Major schemes • A local contribution of at least 15% is required • There is potential for development funding

10.Full details here:

https://www.gov.uk/government/publications/major-road-network-and-large-local- majors-programmes-investment-planning

11.TfSE has already prioritised the first tranche of MRN schemes, but there is commitment to ensure that this will become an ongoing process, with a possible annual call for schemes.

12.Here is a summary of the MRN within the TfSE and surrounding area:

Item 10: BLTB 14 March 2019 Major Roads Network – Call for MRN Schemes Page 184 Conclusion

13. The work to prepare a response to this call for schemes is a good example of the benefits of our membership of TfSE.

Background Papers

BSTOF working papers

Item 10: BLTB 14 March 2019 Major Roads Network – Call for MRN Schemes Page 185 This page is intentionally left blank BLTB Forward Plan 2019/20 18th July 2019

Deadline for final reports: 8th July Agenda published: 10th July

 Financial approval for 2.04.4 Wokingham: Arborfield Cross Relief Road (tbc)  Financial approval for 2.31 Slough: Stoke Road Area Regeneration (tbc)  Heathrow Airport Expansion Development Consent Application – formal consultation  Progress reports  Page 187 Page Forward Plan

14th November 2019

Deadline for final reports: 4th November Agenda published: 6th November

 Financial approval for 2.41 South Wokingham Distributor Road – Eastern Gateway (tbc) AGENDA ITEM 11  One-year-on impact report for 2.02 Bracknell: Warfield Link Road (tbc)  One-year-on Impact report for 2.09.2 Sustainable Transport: A4 Cycle (tbc)  Progress reports  Forward Plan 12th March 2020

Deadline for final reports: 2nd March Agenda published: 4th March

 One-year-on impact report for 2.08 Slough: Rapid Transit Phase 1 (tbc)  One-year-on Impact report for 2.10 Slough: A332 Improvements (tbc)  One-year-on Impact report for 2.22 Slough: Burnham Station Access Improvements (tbc)  Progress reports  Page 188 Page Forward Plan

Other

 Scheme evaluation and monitoring (to be scheduled)  Programme and risk management (to be scheduled)