HIGHWAY PROGRAM

FY 2015-2016

SORTED BY CATEGORY

FOR LEGISLATIVE REVIEW AND APPROVAL

This public document is published at a total cost of $2.81. 66 copies of this public document were published in this first printing at a cost of $185.46. The total cost of all printings of this document including reprints is $185.46. This document was published by the Department of Transportation reproduction unit, 1201 Capitol Access Road, Baton Rouge, LA 70804. This material was printed in accordance with standards for printing by state agencies established in R.S. 43.31.

INTRODUCTION

1. R.S. 48:229, 230 states that each year “the Department shall provide the Legislature a program of construction to be commenced in the ensuing fiscal year, which shall be based upon anticipated revenues to be appropriated by the Legislature…” The Department shall also provide the Legislature a list of projects “which are in various stages of planning and preparation”.

2. In compliance with this statute, the attached Highway Program identifies the projects that are scheduled for construction letting in FY 2015-16. These are denoted as being in Stage 4. Projects being developed in the other stages are also included in the document.

3. There are many projects remaining to be let prior to the end of the current fiscal year, FY 2014-15. For informational purposes, these projects are also listed in this document. In the event any of these projects cannot be let as planned, they will become part of the FY 2015-16 construction program, and will be let as soon as practicable in that fiscal year.

4. The one year construction program and the list of other projects in various stages are combined into this document which is called the Highway Priority Program or Highway Program. These projects are also submitted to the Federal Highway Administration along with the Transit Program. The two programs together are referred to as the State Transportation Improvement Program (STIP). The Public Hearings held each year in each Highway District fulfill both the State and Federal requirements for public involvement regarding these programs.

5. At this point in time, future funding levels are uncertain. DOTD has based this preliminary Highway Program on previous allocations of funding. If funding above the expected amount is made available, funding may be used on projects listed in Stages 0, 1, 2, or 3.

6. In the event all of the projects listed for letting in FY 2015-16 cannot be let to construction due to funding issues or unforeseen problems encountered in the pre-construction process, the affected project(s) will be let as soon as practicable in the following year and other projects listed in Stages 0, 1, 2, or 3 may be advanced into FY 2015-16.

7. Construction estimates are for informational purposes only and are subject to change.

TENTATIVE FY 15-16 BUDGET PARTITION CONSTRUCTION (COSTS IN MILLION DOLLARS)

CATEGORY SUB-CATEGORY PROPOSED

SUSTAINABILITY NON-INTERSTATE (PAVEMENT) 80.0 (FORMERLY CALLED NON-INTERSTATE (PAVEMENT) (non-federal aid) 30.2 PRESERVATION) ROAD PREVENTIVE MAINTENANCE 7.5 INTERSTATE (PAVEMENT) 74.0 BRIDGE (ON SYSTEM) 133.1 BRIDGE (OFF SYSTEM) 13.0 SUB-TOTAL 337.8 ITS (regular & earmarks) 11.0 OPERATIONS TRAFFIC CONTROL DEVICES 14.8 ROADWAY FLOODING 3.7 WEIGH STATIONS 1.9 TRANSPORTATION SYSTEMS MANAGEMENT 7.4 INTERSTATE LIGHTING 2.8 REST AREAS 0.0 ACCESS MANAGEMENT 8.1 FERRIES/MAJOR REPAIRS 3.5 MOVABLE BRIDGE PM 1.9 INTERMODAL CONNECTOR 7.5 ADA PROGRAM 3.0 SUB-TOTAL 65.6

SAFETY HWY. PROGRAM 49.4 RR CROSSING UPGRADES & SEPARATIONS 16.0 SUB-TOTAL 65.4

CAPACITY REGULAR PROGRAM 50.6 CORRIDOR UPGRADE 0.0 SUB-TOTAL 50.6 TRANSPORTATION ALTERNATIVES PROJECTS 12.0 URBAN SYSTEMS, CONGESTION MITIGATION & AIR QUALITY, LOCAL ROAD SAFETY PROGRAM, SAFE ROUTES TO SCHOOLS, URBAN TRANSIT, MISC. DEMAND MANAGEMENT 85.0 FED EARMARKS (DEMO,...) 20.8

OTHER (BONDS, TOLLS, LOCAL ) 9.3

ROAD TRANSFER 23.1 SUB-TOTAL 150.2 GRAND TOTAL 669.6

Subject to funding availability. FUNDING TYPES FEDERAL

NHPP (NATIONAL HIGHWAY PERFORMANCE PROGRAM)

STP (SURFACE TRANSPORTATION PROGRAM) STP>200K (URBAN AREAS – NEW ORLEANS, BATON ROUGE, SHREVEPORT, LAFAYETTE) STP<200K (URBAN AREAS – ALEXANDRIA, HOUMA-THIBODAUX, LAKE CHARLES, MONROE, SLIDELL, MANDEVILLE-COVINGTON, HAMMOND-PONTCHATOULA) STPFLEX (FLEXIBLE) STP<5K (RURAL AREAS) FBROFF (OFF SYSTEM BRIDGE MAP 21)

TAP (TRANSPORTATION ALTERNATIVES PROGRAM) TAP>200K (URBAN AREAS – NEW ORLEANS, BATON ROUGE, SHREVEPORT, LAFAYETTE) TAP<200K (URBAN AREAS – ALEXANDRIA, HOUMA-THIBODAUX, LAKE CHARLES, MONROE, SLIDELL, MANDEVILLE-COVINGTON, HAMMOND-PONTCHATOULA) TAPFLEX (FLEXIBLE) TAP<5K (RURAL AREAS)

HSIP, SR2S, HRRR, SATRANS (SAFETY FUNDS, SAFE ROUTES TO SCHOOLS, HIGH RISK RURAL ROADS, SAFETY TRANSFER)

RAIL HE, RAIL PD (ELIMINATIONS OF HAZARDS AT RAILWAY-HIGHWAY CROSSINGS)

CM (CONGESTION MITIGATION AIR QUALITY – EAST BATON ROUGE, WEST BATON ROUGE, LIVINGSTON, ASCENSION, AND IBERVILLE)

DEMO (FEDERAL DEMONSTRATION AND HIGH PRIORITY PROJECTS – DEFINED BY U.S. CONGRESS)

ER (FEDERAL EMERGENCY RELIEF PROGRAM FUNDING)

FEMA (FEDERAL EMERGENCY MANAGEMENT AGENCY FUNDS)

STATE / LOCAL

NFA (STATE TRANSPORTATION FUNDS FOR NON-FEDERAL AID ROUTES)

NFABOND (STATE BONDS FOR NON-FEDERAL AID ROUTES)

STCASH (STATE TRANSPORTATON TRUST FUNDS FOR STATE FUNDED CONSTRUCTION)

TIME (TRANSPORTATION INFRASTRUCTURE MODEL FOR ECONOMIC DEVELOPMENT)

STBONDS (STATE GENERAL OBLIGATION BONDS)

STGEN (STATE GENERAL FUNDS CASH)

TOLLS

LOCAL (FUNDS PROVIDED BY LOCAL GOVERNMENT)

OTHER (OTHER SOURCE NOT LISTED)

NFI (NO FUNDING IDENTIFIED) DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CAPACITY - Project: H.004932 - INTERCHANGE US 90 @ LA 318 Project Manager: Type Impv: NEW INTERCHANGE. DESIGN-BUILD PROJECT Remarks: 700-51-0110; STGEN IS UNCLAIMED PROPERTY FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY US 90 424-05 STGEN 44,965 CAPACITY 4-SCHEDULED IN CURRENT FY 14-15

ST MARY US 90 424-05 DEMO 15,035 DEMO / HIGH PRIORITY

Project: H.011711 - US190: LA 22 TO LONESOME ROAD (PHASE II) Project Manager: Type Impv: LANDSCAPING, BULB-OUTS, RETAINING WALL Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 190 013-12 STGEN 500 CAPACITY 4-SCHEDULED IN CURRENT FY 14-15

Project: H.002622 - ARKANSAS ROAD: (CALDWELL ROAD - LA 143) Project Manager: Type Impv: WIDENING Remarks: 324-02-0008;CONVERTED FROM BOND TO FED AID-2001 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 616 324-02 STPFLEX 25,000 CAPACITY 4-SCHEDULED FOR LETTING FY 15-16

OUACHITA LA 616 324-02 STBONDS 0 CAPACITY

Project: H.005508 - VEROT SCHOOL RD (VINCENT - EX. 5-L) Project Manager: Type Impv: RECONST. & ADD LANES Remarks: 828-12-0014; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 339 828-12 STPFLEX 24,355 CAPACITY 4-SCHEDULED FOR LETTING FY 15-16

LAFAYETTE LA 339 828-12 STP>200K 2,256 URBAN SYSTEMS

Project: H.011088 - W PRIEN LAKE RD RELOCATION Project Manager: Type Impv: NEW ALIGNMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 3088 870-02 STBONDS 13,000 CAPACITY 4-SCHEDULED FOR LETTING FY 15-16

CALCASIEU LA 3088 870-02 LOCAL 2,000 CAPACITY

CALCASIEU LA 1138-2 810-06 LOCAL 100 CAPACITY

CALCASIEU LA 1138-1 810-34 LOCAL 100 CAPACITY

Project: H.011213 - I 12: SOUND BARRIER WALL @ ESSEN LANE Project Manager: Type Impv: CONSTRUCT SOUND BARRIER WALLS ALONG I-12 WESTBOUND AT ERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-12 454-01 NHPP 1,250 CAPACITY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.002344 - LA 427: PERKINS RD (SIEGEN - HIGHLAND) Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 258-01-0033;GREEN LIGHT PROJECT(LET BY CITY); STAGE 0 COM Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 427 258-01 LOCAL 44,552 CAPACITY 3-DESIGN/DEVELOPMENT

Page 1 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CAPACITY - Project: H.004634 - JUBAN RD WIDENING (I-12 - US 190) Project Manager: Type Impv: WIDENING (CONC PAVEMENT) Remarks: 832-13-0019;700-32-0122 ENGINEERING ($800.000) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 1026 832-13 STBONDS 5,980 CAPACITY 3-DESIGN/DEVELOPMENT

LIVINGSTON US 190 013-06 STBONDS 2,070 CAPACITY

LIVINGSTON US 190 013-06 HSIP 3,530 SAFETY

Project: H.005043 - LA311: LA 664 (ST CHARLES ST)-SAVANNE RD Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 700-55-0122 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 311 413-01 NFI 38,000 CAPACITY 3-DESIGN/DEVELOPMENT

Project: H.009300 - HOOPER ROAD WIDENING (LA 3034 - LA 37) Project Manager: Type Impv: FEASIBILITY STUDY TO WIDEN HOOPER ROAD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 408 255-02 NFI 51,000 CAPACITY 3-DESIGN/DEVELOPMENT

Project: H.010560 - ESSEN LANE WIDEN: PERKINS RD TO I-10 Project Manager: Type Impv: WIDEN TO 6 LANES SECTION W/16'CURB & GUTTER MEDIAN Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 3064 258-32 STBONDS 5,980 CAPACITY 3-DESIGN/DEVELOPMENT

E BATON ROUGE LA 3064 258-32 STPFLEX 500 CAPACITY

Project: H.011065 - NELSON INTERCHANGE IMPROVEMENTS Project Manager: Type Impv: IMPROVEMENTS TO THE NELSON INTERCHANGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 1138-2 810-06 STBONDS 6,000 CAPACITY 3-DESIGN/DEVELOPMENT

CALCASIEU I-210 450-30 STBONDS 1,000 CAPACITY

CALCASIEU I-210 450-30 LOCAL 7,800 CAPACITY

Project: H.011137 - I-12: LA 21 TO US 190 Project Manager: Type Impv: ROADWAY WIDENING AND OVERLAY, BRIDGE WIDENING/REPLACEM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-12 454-04 NHPP 21,041 CAPACITY 3-DESIGN/DEVELOPMENT

ST TAMMANY I-12 454-04 NHPP 13,220 SUSTAINABILITY INTERSTATE ST TAMMANY I-12 454-04 NHPP 14,913 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.011152 - I-12: US 190 TO LA 59 Project Manager: Type Impv: ROADWAY WIDENING AND OVERLAY, BRIDGE WIDENING/REPLACEM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-12 454-04 NHPP 39,557 CAPACITY 3-DESIGN/DEVELOPMENT

ST TAMMANY I-12 454-04 NHPP 4,395 SUSTAINABILITY INTERSTATE

Page 2 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CAPACITY - Project: H.011235 - I-49 SOUTH @ VEROT SCHOOL ROAD Project Manager: Type Impv: CONSTRUCT NEW INTERSECTION - CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 90 424-02 NFI 97,000 CAPACITY 3-DESIGN/DEVELOPMENT

Project: H.011298 - US 90: CAPT CADE TO AMB CAFF FRONTAGE RD Project Manager: Type Impv: NEW CONSTRUCTION OF FRONTAGE RDS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN US 90 424-03 STGEN 3,500 CAPACITY 3-DESIGN/DEVELOPMENT

LAFAYETTE US 90 424-02 STGEN 2,500 CAPACITY

IBERIA US 90 424-04 STGEN 1,500 CAPACITY

Project: H.011307 - US 90: LA 92 @ YOUNG ST INTERCHANGE Project Manager: Type Impv: WIDENING OF US 90 AND CONSTRUCTION OF INTERCHANGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 90 424-02 STGEN 39,000 CAPACITY 3-DESIGN/DEVELOPMENT

LAFAYETTE LA 92 213-06 STGEN 1,000 CAPACITY

Project: H.011309 - MACARTHUR INTERCHANGE COMPLETION PH. II Project Manager: Type Impv: RELOCATE THE EXIT RAMP AND CONSTRUCT AN ENTRANCE RAMP Remarks: USE CCCD TOLL CREDITS AS MATCH FOR 1.6 MIL. PRELIMINARY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 90-Z 283-09 NFI 40,000 CAPACITY 3-DESIGN/DEVELOPMENT

Project: H.001550 - CHATHAM RD. (RUSTON) Project Manager: Type Impv: WIDEN TO 5 LANES Remarks: 068-01-0009;$200 BONDS AVAIL. FOR PE (E?) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 146 068-01 0 CAPACITY 2-WAITING FOR FUNDING

Project: H.001724 - SHREVEPORT-BLANCHARD HWY. Project Manager: Type Impv: 4 LANING (CONTINGENT ON BOND FUNDS) Remarks: 094-01-0029;ORIGINATED BY DEPT OF ECON DEV. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 173 094-01 NFI 25,000 CAPACITY 2-WAITING FOR FUNDING

Project: H.001725 - JCT. LA 3094 - JCT. I-220 Project Manager: Type Impv: WIDENING Remarks: 094-01-0032; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 173 094-01 NFI 10,000 CAPACITY 2-WAITING FOR FUNDING

Project: H.002391 - TCHEFUNCTE - CAUSEWAY APPROACH Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 261-06-0030;CITY/STATE AGREEMENT REQUIRED Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 22 261-06 0 CAPACITY 2-WAITING FOR FUNDING

ST TAMMANY LA 22 261-06 0 OTHER / MISCELLANEOUS

Page 3 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CAPACITY - Project: H.009488 - LA 378 WIDENING (WESTLAKE TO MOSS BLUFF) Project Manager: PORTER BETTS, CONNIE Type Impv: STAGE 0 STUDY TO WIDEN LA 378 (WESTLAKE TO MOSS BLUFF) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 378 810-12 NFI 0 CAPACITY 2-WAITING FOR FUNDING

Project: H.000582 - US 165 WIDENING @ PINEVILLE EXPRESSWAY Project Manager: Type Impv: WIDENING Remarks: 015-30-0013; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 165 015-30 NHPP 5,000 CAPACITY 1-PLANNING/ENVIRONMENTAL

RAPIDES US 165 015-02 0 CAPACITY

Project: H.001164 - LA 169 - LA 538 (N. OF OIL CITY) Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 045-01-0026; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 1 045-02 NFI 23,223 CAPACITY 1-PLANNING/ENVIRONMENTAL

CADDO LA 1 045-01 STPFLEX 4,000 CAPACITY

Project: H.001270 - NATCH. BY-PASS - KEYSER AVE Project Manager: Type Impv: WIDEN TO 5 LANES Remarks: 053-04-0025;(NO FUNDING) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 1-X 053-04 0 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.001779 - JIMMIE DAVIS BRIDGE (LA 511) Project Manager: Type Impv: NEW BRIDGE Remarks: 102-03-0010; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 511 102-03 NFI 0 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.001799 - LA 531 OVERPASS Project Manager: Type Impv: NEW INTERCHANGE Remarks: 451-03-0047;GEOM. STUDY UNDERWAY (E) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER LA 531 111-02 STPFLEX 20,000 CAPACITY 1-PLANNING/ENVIRONMENTAL

WEBSTER I-20 451-03 NHPP 0 CAPACITY

Project: H.004100 - I-10: LA 415 TO ESSEN ON I-10 AND I-12 Project Manager: VOSBURG, CHAD Type Impv: INCREASE CAPACITY(STAGE 0/1 STUDIES) Remarks: 700-17-0209;STAGE 0 & 1; ADVANCE CONSTRUCT STAGE 0 & 1 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-10 450-10 0 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.004825 - WIDENING LA 28 EAST (LIBUSE TO HOLLOWAY) Project Manager: Type Impv: WIDEN FROM 3 TO 4 LANES Remarks: 700-40-0145;FEASIBILITY/STAGE 0 WIDEN TO 4 LANE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 28 074-02 NFI 29,185 CAPACITY 1-PLANNING/ENVIRONMENTAL

Page 4 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CAPACITY - Project: H.008399 - US 51 (LA 22 TO CLUB DELUXE RD) Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 853-36-0031;PORTION OF PROJECT COMPLETED UNDER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA US 51-X 853-36 NFI 40,000 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.009335 - LA 182: I-10 TO WEST PONT DES MOUTON RD Project Manager: Type Impv: WIDENING AND ADDING TRAVEL LANES TO PROVIDE 4 LANE HIGHWARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 182 032-01 NFI 40,200 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.009932 - US 80 WIDENING: WELL ROAD - AVANT ROAD Project Manager: Type Impv: WIDEN LANES 4-12' DIVIDED, CURB & GUTTER,SUBSURFACE DRAINARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 80 001-09 NFI 4,800 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.010152 - LA 1: CONSTRUCTION CANAL DREDGING Project Manager: Type Impv: DREDGE CANAL AND MITIGATION FOR LA 1 ELEVATED CONSTRUCTIORemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 064-90 NHPP 2,000 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.010571 - LA 70 BYPASS Project Manager: Type Impv: STUDY FOR BYPASS ROAD FOR LA 70-PIERRE PART TO NEAR LA 69 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASSUMPTION LA 70 232-01 NFI 140,000 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.010572 - LA 30 IMPROVEMENTS (LA 3251 TO LA 44) Project Manager: Type Impv: FEASIBILITY STUDY TO WIDEN LA 30 FROM I-10 TO LA 44 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 30 414-03 0 CAPACITY 1-PLANNING/ENVIRONMENTAL

Project: H.010753 - US 90/I-310 INTERCHANGE Project Manager: STACK, MICHAEL Type Impv: RECONSTRUCTION OF INTERCHANGE OR NEW FLYOVER RAMP Remarks: MATCH FOR ENVIRONMENTAL FROM DOTD SURPLUS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES I-310 450-38 NFI 0 CAPACITY 1-PLANNING/ENVIRONMENTAL

ST CHARLES US 90 005-08 NFI 0 CAPACITY

Project: H.011303 - US 90:ALBERTSON TO SOUTHPARK FRONTAGE RD Project Manager: Type Impv: FRONTAGE RD CONSTRUCTION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 90 424-02 STGEN 6,000 CAPACITY 1-PLANNING/ENVIRONMENTAL

Page 5 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CAPACITY - Project: H.011718 - BR URBAN RENEWAL & MOBILITY PLAN PROJECT Project Manager: DONMYER, TODD Type Impv: IMPROVE EXISTING US 190/US61 TO FREEWAY TYPE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61 007-90 0 CAPACITY 1-PLANNING/ENVIRONMENTAL

W BATON ROUGE US 190 008-01 0 CAPACITY

E BATON ROUGE US 190 007-10 0 CAPACITY

E BATON ROUGE US 61 007-08 0 CAPACITY

Project: H.009214 - LA 339: WIDENING (LA 82 TO LA 3073) Project Manager: Type Impv: WIDENING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 339 828-11 0 CAPACITY 0-FEASIBILITY/SCOPING

LAFAYETTE LA 339 828-12 0 CAPACITY

Project: H.009215 - LA182:WIDENING(W PONT DES MOUTON RD-I49) Project Manager: Type Impv: WIDENING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 182 032-01 0 CAPACITY 0-FEASIBILITY/SCOPING

Project: H.009837 - LA 64 MOBILITY IMP. (LA 1019 TO LA 16) Project Manager: Type Impv: FEASIBILITY STUDY FOR MOBILITY IMPROVEMENTS OF LA 64 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 64 273-03 0 CAPACITY 0-FEASIBILITY/SCOPING

Page 6 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CONGESTION MITIGATION - Project: H.011483 - BIKE RACKS - DOWNTOWN BR & SOUTHERN UNIV Project Manager: Type Impv: PURCHASE & INSTALLATION OF BIKE RACKS Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 CM 53 CONGESTION MITIGATION 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011610 - CHOCTAW TRAIL (WEST BATON ROUGE) Project Manager: Type Impv: CHOCTAW TRAIL ENVIRONMENTAL PHASE Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 0 CONGESTION MITIGATION 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011619 - CNG FUELING STATION (WEST BATON ROUGE) Project Manager: Type Impv: CONSTRUCT CNG FUELING STATION Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 CM 625 CONGESTION MITIGATION 4-SCHEDULED IN CURRENT FY 14-15

W BATON ROUGE 000-61 LOCAL 910 CONGESTION MITIGATION

Project: H.010768 - MULTI-USE TRAILS, PHASE I-B (WBR) Project Manager: Type Impv: 3 MILES OF LEVEE-TOP TRAIL IN WBR Remarks: USE WBR AS 20% MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 CM 700 CONGESTION MITIGATION 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011551 - CNG VEHICLES-CONVERT AND PURCHASE (WBR) Project Manager: Type Impv: CONVERT EXISTING VEHICLES TO CNG & PURCHASE NEW CNG VEHICRemarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 CM 355 CONGESTION MITIGATION 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011558 - ACADIAN TRAIL (WEST BATON ROUGE) Project Manager: Type Impv: CONSTRUCT ACADIAN TRAIL Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 CM 373 CONGESTION MITIGATION 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011625 - PUBLIC EDUC, OUTREACH, PLANNING (NO RPC) Project Manager: Type Impv: CLEANER TRANSPORTATION FOR THE MARITIME AND ENERGY INDUSRemarks: USE LOCAL AS MATCH; ALL WORK WILL BE IN PHASE 5 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 0 CONGESTION MITIGATION 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010729 - TRAFFIC SIGNAL COORD & SYNCH PH VI (EBR) Project Manager: Type Impv: TRAFFIC SIGNAL COORDINATION & SYNCHRONIZATION Remarks: EBR WILL PROVIDE 20% MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 67 060-01 CM 4,413 CONGESTION MITIGATION 3-DESIGN/DEVELOPMENT

E BATON ROUGE LA 73 077-05 CM 232 CONGESTION MITIGATION

E BATON ROUGE US 61-X 013-04 CM 697 CONGESTION MITIGATION

E BATON ROUGE 000-17 CM 2,787 CONGESTION MITIGATION

Page 7 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CONGESTION MITIGATION - Project: H.010995 - LA 724:[email protected](LAFAYETTE) Project Manager: Type Impv: CONSTRUCT ROUNDABOUT Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 724 828-28 CM 490 CONGESTION MITIGATION 3-DESIGN/DEVELOPMENT

LAFAYETTE 000-28 CM 490 CONGESTION MITIGATION

Project: H.011490 - LA 30: LEFT TURN LANE AT S. PURPERA AVE Project Manager: Type Impv: CONSTRUCT LEFT TURN LANE FOR EASTBOUND TRAFFIC Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 30 414-03 CM 304 CONGESTION MITIGATION 3-DESIGN/DEVELOPMENT

ASCENSION 000-03 CM 304 CONGESTION MITIGATION

Project: H.011496 - QUAIL DR: TURN LANE AT PERKINS (LA 427) Project Manager: Type Impv: CONSTRUCT RIGHT TURN LANE ON NORTHBOUND QUAIL DR. Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 CM 233 CONGESTION MITIGATION 3-DESIGN/DEVELOPMENT

E BATON ROUGE LA 427 258-02 CM 233 CONGESTION MITIGATION

Project: H.011543 - TRAFFIC SIGNAL COORD & SYNCH PH VII(EBR) Project Manager: Type Impv: TRAFFIC SIGNAL COORDINATION AND SIGNAL SYNCHRONIZATION Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 3164 019-01 CM 3,421 CONGESTION MITIGATION 3-DESIGN/DEVELOPMENT

E BATON ROUGE US 61 019-02 CM 540 CONGESTION MITIGATION

E BATON ROUGE LA 408 255-01 CM 398 CONGESTION MITIGATION

E BATON ROUGE 000-17 CM 1,852 CONGESTION MITIGATION

E BATON ROUGE LA 37 254-01 CM 1,014 CONGESTION MITIGATION

E BATON ROUGE LA 37 254-02 CM 1,022 CONGESTION MITIGATION

Project: H.009731 - L/CNG FUEL FLEETS DISTRICT 02 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: H.009732 - L/CNG FUEL FLEETS DISTRICT 03 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 03 000-93 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: H.009733 - L/CNG FUEL FLEETS DISTRICT 04 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 04 000-94 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Page 8 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CONGESTION MITIGATION - Project: H.009734 - L/CNG FUEL FLEETS DISTRICT 05 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 05 000-95 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: H.009735 - L/CNG FUEL FLEETS DISTRICT 07 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 07 000-97 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: H.009736 - L/CNG FUEL FLEETS DISTRICT 08 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 08 000-98 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: H.009737 - L/CNG FUEL FLEETS DISTRICT 58 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 58 000-91 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: H.009738 - L/CNG FUEL FLEETS DISTRICT 61 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 61 000-96 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: H.009739 - L/CNG FUEL FLEETS DISTRICT 62 Project Manager: Type Impv: FLEET CONVERSION TO CNG Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 62 000-90 0 CONGESTION MITIGATION 1-PLANNING/ENVIRONMENTAL

Project: L.000093 - STATEWIDE CONGESTION MITIGATION Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - CM 5,500 CONGESTION MITIGATION STAGES 4, 3, 2, 1, 0

Page 9 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CORRIDOR - Project: H.000497 - US190: BAYOU CASTINE-SE LA HOSPITAL Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 013-12-0039;PROJ ON XXX PER LIST FROM F.BORNE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 190 013-12 NFI 12,000 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.001399 - HAPPY JACK - N.PORT SULPHUR Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 062-04-0029;$1M GS9$ FOR STUDY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage PLAQUEMINES LA 23 062-04 NFI 30,000 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.003074 - I 10: WILLIAMS BLVD - VETERANS BLVD Project Manager: Type Impv: MAJOR WIDENING - ADD TRAVEL LANES Remarks: 450-15-0124 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON I-10 450-15 NFI 70,000 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.003184 - I-10: TEXAS STATE LINE-E. OF COONE GULLY Project Manager: DUPONT, RONALD R. Type Impv: WIDEN TO 6 LANES Remarks: 450-91-0078; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-10 450-91 NHPP 24,000 CORRIDOR 3-DESIGN/DEVELOPMENT

CALCASIEU I-10 450-91 NHPP 41,000 SUSTAINABILITY INTERSTATE

Project: H.009087 - I-10: LOYOLA DR. TO WILLIAMS BLVD. Project Manager: Type Impv: MAJOR WIDENING - ADD TRAVEL LANES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON I-10 450-15 NFI 10,000 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.009250 - I-10 HIGHLAND TO LA 73 Project Manager: Type Impv: WIDEN INTERSTATE TO 3 LANES EACH DIRECTION Remarks: LHIP USED FOR ENG Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION I-10 450-11 NFI 50,500 CORRIDOR 3-DESIGN/DEVELOPMENT

E BATON ROUGE I-10 450-10 NFI 16,000 CORRIDOR

Project: H.009266 - I-10: LA 73 TO LA 30 Project Manager: Type Impv: WIDEN INTERSTATE TO 3 LANES EACH DIRECTION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION I-10 450-11 NFI 46,700 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.009276 - I-10: LA 30 TO LA 22 Project Manager: Type Impv: WIDEN INTERSTATE TO 3 LANES EACH DIRECTION Remarks: LHIP USED FOR ENG Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION I-10 450-11 NFI 50,300 CORRIDOR 3-DESIGN/DEVELOPMENT

Project: H.010558 - I-12 WDN: .5 M W SATSUMA-SATSUMA RAMPS Project Manager: Type Impv: WIDEN I-12 TO 3 LANES Remarks: CAN'T ADD TO TIP & STIP UNTIL COMPLETE NEW CONFORMITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON I-12 454-02 NHPP 12,000 CORRIDOR 3-DESIGN/DEVELOPMENT

Page 10 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 CORRIDOR - Project: H.010601 - I-10: LA 328 TO LA 347 Project Manager: Type Impv: RUBBLIZE AND OVERLAY AND WIDEN TO 3 LANES IN EACH DIRECTIORemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN I-10 450-06 NHPP 38,571 CORRIDOR 3-DESIGN/DEVELOPMENT

ST MARTIN I-10 450-06 NHPP 19,386 SUSTAINABILITY BRIDGE (ON SYSTEM) ST MARTIN I-10 450-06 NHPP 43,882 SUSTAINABILITY INTERSTATE

Project: H.000494 - LA 433 - US 11 Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 013-12-0031;404 REQ.(E?). PUB.MT.TO BE HELD. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 190 013-12 0 CORRIDOR 2-WAITING FOR FUNDING

Project: H.000758 - LA 772 - HAIR CREEK(JENA) Project Manager: Type Impv: WIDENING Remarks: 022-05-0045; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE US 84 022-05 NFI 50,000 CORRIDOR 1-PLANNING/ENVIRONMENTAL

Project: H.010549 - I20: MP RR (LM 6.5) TO PINES RD (LM 9.7) Project Manager: Type Impv: WIDEN FROM 4 TO 6 LANES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-20 451-01 NHPP 15,000 CORRIDOR 1-PLANNING/ENVIRONMENTAL

Project: H.010550 - I 20: LA 546 TO LA 594 Project Manager: Type Impv: WIDEN FROM 4 TO 6 LANES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA I-20 451-06 NHPP 200,000 CORRIDOR 0-FEASIBILITY/SCOPING

Page 11 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 DEMO / HIGH PRIORITY - Project: H.000326 - HEMLOCK ST.(LA 3224) @ US 61 Project Manager: Type Impv: SAFETY & CAPACITY MODIFICATIONS Remarks: 848-19-0007;STP>200K FUNDS, USE TTF AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 3224 848-19 DEMO 364 DEMO / HIGH PRIORITY 4-SCHEDULED IN CURRENT FY 14-15

ST JOHN LA 3224 848-19 STP>200K 141 URBAN SYSTEMS

Project: H.002370 - LA 42 (US 61 - LA 44) Project Manager: ELISAR, AARON Type Impv: WIDENING AND IMPROVEMENTS Remarks: 260-01-0026; SEE NOTES FOR DETAILS. STGEN MATCH FOR UTIL Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 42 260-01 DEMO 0 DEMO / HIGH PRIORITY 4-SCHEDULED IN CURRENT FY 14-15

ASCENSION LA 42 260-01 HSIP 0 SAFETY

ASCENSION LA 42 260-01 STBONDS 23,631 OTHER / MISCELLANEOUS

ASCENSION LA 42 260-01 TAPFLEX 1,231 ENHANCEMENTS

ASCENSION LA 73 077-03 STBONDS 112 OTHER / MISCELLANEOUS

ASCENSION LA 930 803-14 STBONDS 27 OTHER / MISCELLANEOUS

ASCENSION LA 44 265-02 STBONDS 430 OTHER / MISCELLANEOUS

ASCENSION 000-03 STBONDS 99 OTHER / MISCELLANEOUS

Project: H.003200 - FRONTAGE ROAD CONST IN LAKE CHARLES Project Manager: Type Impv: TURNAROUND UNDERNEATH INTERSTATE Remarks: 450-91-0171;STAGE 0 COMPLETE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-10 450-91 IM DISCR 1,268 DEMO / HIGH PRIORITY 4-SCHEDULED IN CURRENT FY 14-15

CALCASIEU I-10 450-91 TCSP 631 DEMO / HIGH PRIORITY

CALCASIEU 000-10 TCSP 814 DEMO / HIGH PRIORITY

Project: H.004823 - 3RD ST ENHANCEMENTS-ST JAMES TO BROADWAY Project Manager: RACHAL, JASON Type Impv: ENHANCEMENT Remarks: 700-40-0143;STAGE 0 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 DEMO 2,850 DEMO / HIGH PRIORITY 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009978 - US 84: PASSING LANES Project Manager: Type Impv: COLD PLANING, SUPERPAVE ASPHALTIC CONCRETE, PAVEMENT STRRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO US 84 021-02 DEMO 1,875 DEMO / HIGH PRIORITY 4-SCHEDULED IN CURRENT FY 14-15

DESOTO US 84 021-02 STPFLEX 558 OTHER / MISCELLANEOUS

Project: H.004929 - IMP RALPH DARDEN PKWY B/W LA182 MLK Project Manager: DOMINGUE, CHRISTOPHER Type Impv: LA 182 & MLK IMPROVEMENTS Remarks: 700-51-0107;STAGE 0 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY 000-51 DEMO 160 DEMO / HIGH PRIORITY 4-SCHEDULED FOR LETTING FY 15-16

Page 12 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 DEMO / HIGH PRIORITY - Project: H.006599 - TAMMANY TRACE CAMP SALMEN CONNECTOR Project Manager: Type Impv: CONSTRUCT PEDESTRIAN AND BIKE PATH Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 DEMO 144 DEMO / HIGH PRIORITY 4-SCHEDULED FOR LETTING FY 15-16

ST TAMMANY 000-52 TAP<200K 231 ENHANCEMENTS

Project: H.010155 - US 90 RAILROAD OVERPASS SE OF LA 85 Project Manager: Type Impv: BRIDGE OVERPASS Remarks: STBONDS AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA US 90 424-04 DEMO 15,000 DEMO / HIGH PRIORITY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010723 - NORTH BOULEVARD PROMONADE Project Manager: FOURNERAT, CHRIS Type Impv: PED. AND BIKE PATH Remarks: MATCH FROM ENTITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 TCSP 1,431 DEMO / HIGH PRIORITY 4-SCHEDULED FOR LETTING FY 15-16

E BATON ROUGE 000-17 LOCAL 69 DEMO / HIGH PRIORITY

Project: H.011435 - US 11 IMPROVEMENTS AT SCHNEIDER CANAL Project Manager: Type Impv: LEVEE IMPROVEMENT AND ROADWAY WIDENING WITH ACCESS MGMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 11 018-03 DEMO 2,300 DEMO / HIGH PRIORITY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007175 - LAPALCO (VICTORY - WESTWOOD) Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 742-26-0033;FUND WITH DEMO FUNDS.PH.PUR.R/W Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 DEMO 3,600 DEMO / HIGH PRIORITY 3-DESIGN/DEVELOPMENT

JEFFERSON 000-26 STP>200K 8,578 URBAN SYSTEMS

Project: H.010649 - EBR PARISHWIDE SIGNAL MODIFICATIONS Project Manager: Type Impv: SIGNAL MODIFICATIONS Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 DEMO 1,439 DEMO / HIGH PRIORITY 3-DESIGN/DEVELOPMENT

Project: H.002358 - ESSEN LANE INTERCHANGE Project Manager: Type Impv: (PHASE 2)(REQ DEMO FUNDS) Remarks: 454-01-0068;IM-D $250K FY03.REQ MORE DEMO Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 3064 258-32 DEMO 14,000 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

E BATON ROUGE I-12 454-01 0 DEMO / HIGH PRIORITY

Project: H.003756 - NEW INTERCHANGE LA 98 RAYNE Project Manager: Type Impv: FED EARMARK FOR STUDY Remarks: 700-01-0112;$993.500(IMD)&$110.000C.O.AVAILABLE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA 000-01 DEMO 0 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

Page 13 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 DEMO / HIGH PRIORITY - Project: H.003855 - BOSSIER PAR CONG RELIEF WINFIELD RD Project Manager: Type Impv: ROADWAY EXT (WINFIELD RD) STUDY Remarks: 700-08-0130;STAGE 0 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 NFI 27,900 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

Project: H.004367 - LA3139:EARHART EXPRESSWAY EXT TO US 61 Project Manager: Type Impv: ENVIRONMENTAL. LINE & GRADE STUDY Remarks: 700-26-0242;HP NO.1600 (SEE ALSO 736-92-0003) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 NFI 125,000 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

ORLEANS 000-36 0 DEMO / HIGH PRIORITY

Project: H.004721 - TCHOUPITOULAS SIGNAGE AND STRIPING PLAN Project Manager: Type Impv: STUDY Remarks: 700-36-0176;$48K H.P.DEMO. $12K MATCH BY RPC Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 DEMO 200 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

Project: H.006447 - I-69: SIU 14 JCT I-20 TO US 82 Project Manager: GOZA, VERNIE DARRELL Type Impv: DESIGN AND ACQUIRE R/W Remarks: 736-99-1032; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 0 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

Project: H.007272 - HOWARD AVENUE EXTENSION Project Manager: Type Impv: NEW 2-LANE ROADWAY Remarks: 742-36-0136;CITY OWNS R/W Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 DEMO 3,226 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

Project: H.007289 - KANSAS LANE EXTENSION Project Manager: Type Impv: ASPHALT NEW PAVEMENT Remarks: 742-37-0016;US 80 - US 165. R/W & UTIL BY CITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 DEMO 4,531 DEMO / HIGH PRIORITY 2-WAITING FOR FUNDING

OUACHITA 000-37 LOCAL 15,470 OTHER / MISCELLANEOUS

Project: H.001061 - EL CAMINO EAST/WEST COR (EAST SEG ) Project Manager: Type Impv: MAJOR WIDENING LA 117 TO I 49 Remarks: 034-05-0035;USING STBONDS AS MATCH TO DEMO TO ACQUIRE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 6 034-05 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

NATCHITOCHES LA 6 034-05 NFI 25,000 DEMO / HIGH PRIORITY

Project: H.002264 - BAYOU BARATARIA BRIDGE@JEAN LAFITTE Project Manager: CAPOTE, NELSON Type Impv: BRIDGE REPL.(KERNER'S) Remarks: 249-90-0041;TEA-21 KERNER'S FERRY BRIDGE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 45 249-90 DEMO 546 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

JEFFERSON LA 45 249-90 STPFLEX 4,305 SUSTAINABILITY BRIDGE (ON SYSTEM) JEFFERSON LA 302 826-39 FBROFF 67,978 SUSTAINABILITY BRIDGE (ON SYSTEM)

Page 14 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 DEMO / HIGH PRIORITY - Project: H.002397 - PETE'S HWY(LA 16)INTERCHANGE @ I-12 Project Manager: Type Impv: INTERCHANGE IMPROVEMENTS Remarks: 262-01-0037; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 16 262-01 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

LIVINGSTON I-12 454-02 0 DEMO / HIGH PRIORITY

Project: H.002729 - GRAND PRAIRIE HWY INTR.&FRONTAGE RD Project Manager: Type Impv: NEW BRIDGE. NEW CONCRETE PAVEMENT Remarks: 389-01-0011; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 98 389-01 NFI 19,734 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

ACADIA I-10 450-04 0 DEMO / HIGH PRIORITY

Project: H.002861 - CAUSEWAY BLVD - EARHART EXPRESSWAY INTER Project Manager: Type Impv: NEW INTERCHANGE Remarks: 430-01-0013;JEFF. PH CONSULTANT WORKING (E) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 3139 430-01 NFI 60,000 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

JEFFERSON LA 3046 423-01 0 DEMO / HIGH PRIORITY

Project: H.003047 - PECUE LANE/I-10 INTERCHANGE Project Manager: Type Impv: NEW INTERCHANGE Remarks: 450-10-0161; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-10 450-10 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

E BATON ROUGE I-10 450-10 STGEN 0 DEMO / HIGH PRIORITY

Project: H.003454 - LAFAYETTE CONNNECTOR Project Manager: Type Impv: IN LAFAYETTE NEW INTERSTATE Remarks: 455-01-0035;ENGR 700-24-0073. R/W 455-01-0034 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE I-49 455-01 DEMO 400,000 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.003857 - WAFER ROAD EXTENSION Project Manager: Type Impv: ROAD EXTENSION (ENGINEERING) STUDY Remarks: 700-08-0132; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.004608 - CHOUDRANT I-20 SERVICE ROAD Project Manager: Type Impv: NEW SERVICE ROAD Remarks: 700-31-0121;STAGE 0 COMPLETED Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN 000-31 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.004782 - LA 143 - US 165 CONNECTOR& OUACH Project Manager: Type Impv: CONNECTOR & OUACHITA R. BR.(ENGR) Remarks: 700-37-0129;STAGE O Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Page 15 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 DEMO / HIGH PRIORITY - Project: H.004791 - REPL.BRIDGE AND TUNNEL BELLE CHASSE Project Manager: Type Impv: STATE FUNDS FOR STUDY Remarks: 700-38-0108;FEASIBILITY STUDY STAGE 0 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage PLAQUEMINES 000-38 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.004983 - US HIGHWAY 11 WIDENING Project Manager: Type Impv: WIDENING WITH BIKE PATH Remarks: 700-52-0196 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 11 018-03 DEMO 3,517 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

ST TAMMANY US 11 018-03 NFI 15,829 DEMO / HIGH PRIORITY

Project: H.005158 - FUTURE I-49 SOUTH (RACELAND TO WESTBANK Project Manager: Type Impv: UPRGRADING US 90 FOR FUTURE I-49 SOUTH Remarks: 700-92-0011; EIS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.005164 - SMART GROWTH STRATEGIES LAND USE Project Manager: Type Impv: LAND USE STUDY Remarks: 700-92-0017;STAGE O UNDER WAY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.005167 - LONG-RANGE TRANSPORTATION STRATEGY Project Manager: Type Impv: GROWTH MANAGEMENT STUDY Remarks: 700-92-0020;PRE STAGE 0 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.005168 - NEW ORLEANS RAIL GATEWAY EIS Project Manager: Type Impv: EIS Remarks: STATE & RR EACH PUTTING UP 10% OF MATCH FOR DEMO Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.005184 - HIGH PRIORITY CORRIDOR NO. 18 Project Manager: Type Impv: ENVIRONMENTAL IMPACT STATEMENT Remarks: 700-94-0003;NCPD FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

CADDO 000-09 0 DEMO / HIGH PRIORITY

Project: H.006442 - AIRPORT - CBD COMMUTER RAIL STUDY Project Manager: Type Impv: STUDY Remarks: 736-92-0003;HP 1600 (SEE ALSO 700-26-0242) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

ORLEANS 000-36 0 DEMO / HIGH PRIORITY

ST CHARLES 000-45 0 DEMO / HIGH PRIORITY

Page 16 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 DEMO / HIGH PRIORITY - Project: H.006513 - US 61 CORRIDOR PRESERVATION Project Manager: Type Impv: ABANDONED RR R/W ACQ. (HP NO 1600) Remarks: 737-26-0001;HP=$0.5M. >2OOK=$0.3M IN FY 2001 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 DEMO 6,750 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

ORLEANS 000-36 0 DEMO / HIGH PRIORITY

ST CHARLES 000-45 0 DEMO / HIGH PRIORITY

Project: H.008415 - INFORMATION CENTER @ SOUTHERN UNIVERSITY Project Manager: Type Impv: FEDERAL EARMARK Remarks: DEMO$ & $ FROM SOUTHERN;AUTHORIZED; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 DEMO 600 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

E BATON ROUGE 000-17 OTHER 1,773 OTHER / MISCELLANEOUS

Project: H.008732 - STUDY OF BATON ROUGE LOOP Project Manager: Type Impv: EIS Remarks: EIS IS DEMO WITH MATCH FROM LOCALS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.009153 - US HWY 84 IMPROVEMENTS Project Manager: Type Impv: MAJOR WIDENING Remarks: STBONDS AS MATCH; $1.5M IN CLOC PRIORITY 1 AVAILABLE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN US 84 022-02 NFI 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

WINN US 84 022-03 NFI 0 DEMO / HIGH PRIORITY

Project: H.010170 - SMART GROWTH PLANNING Project Manager: NGUYEN, WAYNE Type Impv: TRANSPORTATION PLANNING - LAND USE EDUCATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.010274 - US 190: US 11 TO LA 433 Project Manager: Type Impv: STAGE 0 FEASIBILITY STUDY FOR INTERIM CAPACITY IMPROVEMENTRemarks: DUE TO HURRICANE ISAAC MPO CAN'T FORMALLY APPROVE PR Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 190 013-12 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.010912 - MISSIPPIPPI RIVER TRAIL-PLAQUEMINES PAR Project Manager: Type Impv: STAGE 0 FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage PLAQUEMINES 000-38 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: H.011136 - MRT EXTENSION ST. JOHN PARISH Project Manager: Type Impv: STAGE 0 FEASIBILITY STUDY Remarks: 20% NON-FEDERAL MATCH PROVIDED BY RPC Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 44 256-02 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Page 17 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 DEMO / HIGH PRIORITY - Project: H.011328 - US 90: WAX LAKE OUTLET TO BERWICK Project Manager: Type Impv: UPGRADING US 90 FOR FUTURE I-49 SOUTH Remarks: REF. H.005171 FEASIBILITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY US 90 424-05 DEMO 0 DEMO / HIGH PRIORITY 1-PLANNING/ENVIRONMENTAL

Project: L.000031 - DEMO/HI-PRI/OTHER FEDERAL PROGRAMS Project Manager: Type Impv: AS DEFINED BY FEDERAL GOVERNMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - DEMO 10,000 DEMO / HIGH PRIORITY STAGES 4, 3, 2, 1, 0

Page 18 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.001306 - ST MARTINVLLE PEDESTRIAN IMPROVEMENTS Project Manager: Type Impv: RECONSTRUCTION OF SIDEWALKS Remarks: FEDERAL SHARE IS 80%. 15% MATCH TOLL CREDITS & 5% LOCA Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN 000-50 TAP>200K 195 ENHANCEMENTS 4-SCHEDULED IN CURRENT FY 14-15

ST MARTIN LA 31 056-02 TAP>200K 122 ENHANCEMENTS

ST MARTIN LA 96 238-03 TAP>200K 93 ENHANCEMENTS

ST MARTIN 000-50 LOCAL 63 ENHANCEMENTS

ST MARTIN LA 31 056-02 LOCAL 18 ENHANCEMENTS

ST MARTIN LA 96 238-03 LOCAL 24 ENHANCEMENTS

Project: H.007485 - CADE FARM SEEDBANK BLDG RENOVATION Project Manager: Type Impv: RENOVATION OF EXISTING BUILDING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN 000-50 TAP>200K 975 ENHANCEMENTS 4-SCHEDULED IN CURRENT FY 14-15

ST MARTIN 000-50 LOCAL 75 ENHANCEMENTS

Project: H.009770 - ST JOHN MISS EASTBANK MU PATH, PH 3/3A Project Manager: Type Impv: MULTI-USE PATH ON EB MISS. RIVER LEVEE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN 000-48 TAP<200K 855 ENHANCEMENTS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.007476 - FAT CITY STREETSCAPES Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 TAP>200K 1,165 ENHANCEMENTS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007492 - CHOUDRANT SIDEWALK PROJECT Project Manager: Type Impv: SIDEWALK AND BIKE PATH Remarks: 15% OF MATCH IS TOLL CREDITS 5% IS LOCAL MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 145 157-03 TAP<5K 204 ENHANCEMENTS 4-SCHEDULED FOR LETTING FY 15-16

LINCOLN US 80 001-08 TAP<5K 146 ENHANCEMENTS

LINCOLN LA 145 157-02 TAP<5K 35 ENHANCEMENTS

Project: H.010184 - LA 59: CURVE REALIGN AND TUNNEL AT TRACE Project Manager: SHARP, LARRY W. Type Impv: REALIGN CURVE & PROVIDE A TUNNEL FOR TAMMANY TRACE CROSRemarks: ENG & R/W BY ST TAMMANY PARISH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 59 281-03 TAP<200K 1,900 ENHANCEMENTS 4-SCHEDULED FOR LETTING FY 15-16

ST TAMMANY LA 59 281-03 HSIP 750 SAFETY

Page 19 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.000470 - HOLDEN SIDEWALK PROGRAM Project Manager: Type Impv: ENHANCEMENT Remarks: 744-32-0011; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON US 190 013-07 TAP<200K 235 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

LIVINGSTON LA 441 270-02 0 ENHANCEMENTS

LIVINGSTON LA 441 270-01 0 ENHANCEMENTS

Project: H.002123 - RAYNE SIDEWALKS, PH. III Project Manager: Type Impv: Remarks: 207-07-0028 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 35 207-07 TAP<200K 434 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.002263 - JEAN LAFITTE: DOWNTOWN SIDEWALK, PHASE 1 Project Manager: Type Impv: Remarks: 249-90-0040 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 45 249-90 TAPFLEX 188 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.002901 - CAJUN COAST TRAILHEAD Project Manager: Type Impv: CONSTRUCTION OF A TRAILHEAD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY 000-51 TAP<200K 1,205 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

ST MARY US 90 424-05 TAP<200K 269 ENHANCEMENTS

Project: H.007369 - RAYNE SIDEWALKS, PH. II Project Manager: Type Impv: CONCRETE WALKS AND DRIVES AND RELATED WORK Remarks: 744-01-0013 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA US 90 003-10 TAP<200K 265 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

ACADIA LA 35 207-07 TAP<200K 155 ENHANCEMENTS

Project: H.007417 - LAKE SHORE DRIVE MULTI-USE PATH Project Manager: Type Impv: SIDEWALKS, LANDSCAPING AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 TAP<200K 700 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009720 - LA 1250: PINEVILLE URBAN STREETSCAPING Project Manager: MEEK, STEPHEN Type Impv: SIDEWALK WITH LIGHTING, LANDSCAPE & SUBSURFACE DRAINAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 1250 142-01 TAP<200K 227 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009723 - WOODWORTH SIDEWALK IMPROVEMENTS PH 3 Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS AND REALTED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 TAP<5K 251 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Page 20 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.009724 - ST JAMES MISS EBANK MULTI-USE TRAIL PH 1 Project Manager: MEEK, STEPHEN Type Impv: MULTI-USE PATH AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JAMES 000-47 TAP<200K 1,259 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009741 - MARKSVILLE SIDEWALK IMPROVEMENTS Project Manager: Type Impv: SIDEWALK W/ LIGHTING, LANDSCAPE & SUBSURFACE DRAINAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES 000-05 TAP<200K 338 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009742 - ACADIA RD: AUDUBON-CARDINAL PED PATHS Project Manager: MEEK, STEPHEN Type Impv: SIDEWALK WITH LIGHTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE 000-29 TAP<200K 204 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009743 - BUNKIE SIDEWALK IMPROVEMENTS Project Manager: Type Impv: SIDEWALKS AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES US 71 008-07 TAP<5K 96 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

AVOYELLES LA 115 805-18 TAP<5K 16 ENHANCEMENTS

AVOYELLES 000-05 TAP<5K 88 ENHANCEMENTS

Project: H.009744 - OIL CITY MULTI-USE TRAIL, PHASE 2 Project Manager: Type Impv: MULTI-USE TRAIL AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 TAP<5K 438 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009745 - SCOTLANDVILLE PKWY MULTI-MODAL IMPRVMENT Project Manager: Type Impv: MULTI-USE TRAIL & PED. BRIDGES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-110 450-92 TAP>200K 234 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009746 - RUSTON DOWNTOWN REVITALIZATION PHASE 6 Project Manager: Type Impv: SIDEWALK W/ LIGHTING, STREETSCAPING, & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 150 831-07 TAP<200K 895 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

LINCOLN LA 150 831-07 LOCAL 190 OTHER / MISCELLANEOUS

LINCOLN 000-31 TAP<200K 1,569 ENHANCEMENTS

LINCOLN 000-31 LOCAL 284 OTHER / MISCELLANEOUS

Project: H.009747 - LA 31: PEDESTRIAN IMPROVEMENTS, PH 2 Project Manager: Type Impv: SIDEWALK W/ LANDSCAPING & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 31 056-02 TAP<200K 467 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Page 21 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.009748 - BERWICK DOWNTOWN SIDEWALKS Project Manager: Type Impv: SIDEWALKS AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY 000-51 TAP<200K 73 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009749 - WALKER SIDEWALKS, PH 3 Project Manager: Type Impv: SIDEWALKS & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 1027 273-03 TAP>200K 323 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

LIVINGSTON LA 447 268-02 TAP>200K 31 ENHANCEMENTS

LIVINGSTON 000-32 TAP>200K 223 ENHANCEMENTS

Project: H.009750 - TOPSY ROAD SIDEWALK Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS, SUBSURFACE DRAINAGE, & RELATED WORK Remarks: ROW IS 80/20, CONSTRUCTION 95/5 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 TAP<200K 145 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009751 - BELL CITY SCHOOL SIDEWALK Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS, SUBSURFACE DRAINAGE, WARNING LIGHTS &RELATED Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 14 196-01 TAP<200K 102 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

CALCASIEU 000-10 TAP<200K 13 ENHANCEMENTS

Project: H.009752 - DESIARD ST: STREETSCAPING S GRAND-6TH ST Project Manager: MEEK, STEPHEN Type Impv: SIDEWALK W/ LIGHTING, LANDSCAPE & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 TAP<200K 513 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009753 - JEAN LAFITTE: DOWNTOWN SIDEWALK, PHASE 2 Project Manager: MEEK, STEPHEN Type Impv: SIDEWALK W/LIGHTING, LANDSCAPE & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 TAP>200K 336 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009761 - LA 14: DOWNTOWN ABBEVILLE STREETSCAPING Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS W/LIGHTING, LANDSCAPE & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 14 055-06 TAP<200K 500 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009762 - ENTERPRISE BLVD MULTI-USE PATH Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE 000-24 TAP<200K 288 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Page 22 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.009763 - ST CHARLES EBANK LEVEE MU PATH, PHASE 6 Project Manager: MEEK, STEPHEN Type Impv: MULTI-USE PATH & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES 000-45 TAP>200K 1,025 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009764 - NO CITY PARK: MARCONI MULTI-USE PATH Project Manager: Type Impv: MULTI-USE PATH, LANDSCAPING & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 TAP>200K 727 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009765 - JENA: MULTI-MODAL CONNECTIVITY Project Manager: MEEK, STEPHEN Type Impv: MULTI-USE PATH W/LIGHTING, LANDSCAPE & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE 000-30 TAP<5K 787 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

LASALLE LA 8 830-08 TAP<5K 120 ENHANCEMENTS

Project: H.009766 - WPARK AVE: ROYCE ST-MARIETTA PL SIDEWALK Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS, SUBSURFACE DRAINAGE & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 24 065-04 TAP<200K 959 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009769 - ROSEDALE GATEWAY ENHANCEMENT Project Manager: Type Impv: SIDEWALK & GATEWAYS W/LIGHTING,LANDSCAPE&SUBSURFACE D Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 77 219-03 STPENH 73 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

IBERVILLE LA 77 219-02 STPENH 24 ENHANCEMENTS

IBERVILLE LA 76 228-04 STPENH 73 ENHANCEMENTS

IBERVILLE LA 76 228-05 STPENH 24 ENHANCEMENTS

Project: H.009784 - WINNSBORO: ADAMS&COMMON ST STREETSCAPING Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS W/LIGHTING, & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage FRANKLIN 000-21 TAP<200K 229 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009792 - LA 35: KAPLAN SIDEWALKS, PHASE 1 Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS W/ LANDSCAPING, SUBSURFACE DRAINAGE & RELATED Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 35 207-03 TAP<200K 324 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009793 - SLIDELL: OLDE TOWN STREETSCAPING Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS W/LIGHTING, LANDSCAPING, & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 TAP<200K 954 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Page 23 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.009795 - LA 182: US 90-MLK DRIVE SIDEWALKS Project Manager: Type Impv: SIDEWALKS & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 182 032-01 TAP>200K 571 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009798 - CITY OF CENTRAL SIDEWALKS Project Manager: Type Impv: SIDEWALK & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 3034 255-30 TAP>200K 274 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

E BATON ROUGE 000-17 TAP>200K 168 ENHANCEMENTS

Project: H.009799 - EBR MISS E BANK MULTI-USE PATH, PHASE 3 Project Manager: Type Impv: MULTI-USE PATH & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 TAP>200K 1,500 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009804 - KENNER: S WILLIAMS BLVD STREETSCAPING Project Manager: Type Impv: SIDEWALKS W/ LIGHTING, STREETSCPAING & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 TAP>200K 446 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009805 - MOREAUVILLE SIDEWALKS Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS W/ SUBSURFACE DRAINAGE & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES LA 114 052-05 TAP<5K 102 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

AVOYELLES 000-05 TAP<5K 102 ENHANCEMENTS

Project: H.009852 - MASONIC DRIVE CORRIDOR ENHANCEMENT, PH 3 Project Manager: Type Impv: SIDEWALK W/LIGHTING & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 TAP<200K 575 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009938 - MAGNOLIA CONVERTED PED BRIDGE REHAB Project Manager: Type Impv: REHAB OF EXISTING PED BRIDGE (CONVERTED VEHICLE) & REL. WORRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 TAP>200K 889 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011770 - FARMERVILLE DOWNTOWN SW IMPROVEMENTS Project Manager: Type Impv: RECONSTRUCTION OF EXISTING SIDEWALKS Remarks: TOWN OF FARMERVILLE PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage UNION LA 2 069-02 TAPFLEX 202 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

UNION LA 2 070-05 TAPFLEX 51 ENHANCEMENTS

UNION 000-56 TAPFLEX 563 ENHANCEMENTS

Page 24 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.011772 - LA 824-3: TOWN OF DUBACH SIDEWALKS Project Manager: Type Impv: SIDEWALKS Remarks: MATCH BY THE TOWN OF DUBACH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 824-3 831-21 TAPFLEX 41 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011773 - HANKS DR/LANDIS DR PED IMPROVEMENTS Project Manager: Type Impv: SIDEWALKS Remarks: BATON ROUGE/PARISH OF EAST BATON ROUGE WILL PROVIDE M Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 TAP>200K 2,008 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011774 - LA 327-S: GARDERE LANE PED IMPROVEMENTS Project Manager: Type Impv: SIDEWALK/MULTI-USE PATH Remarks: MATCH PROVIDED BY CITY OF BATON ROUGE/EAST BATON ROU Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 327-S 257-03 TAP>200K 864 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011775 - US 11 & US 190 BICYCLE AND PED CROSSINGS Project Manager: Type Impv: PED/BICYCLE CROSSWALKS, SIGNS AND SIGNALS Remarks: CITY OF SLIDELL PROVIDES MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 11 018-03 TAP<200K 372 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011779 - POWER BLVD MEDIAN IMPROVEMENTS Project Manager: Type Impv: MULTI-USE PATH Remarks: MATCH PROVIDED BY CITY OF KENNER. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 TAP>200K 2,011 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011780 - LAKEFRONT PEDESTRIAN PATH Project Manager: Type Impv: PEDESTRIAN PATH Remarks: MATCH PROVIDED BY JEFFERSON PARISH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 TAP>200K 429 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011799 - SPARTAN DRIVE SHARED USE PATH Project Manager: MEEK, STEPHEN Type Impv: SHARED USE PATH Remarks: MATCH PROVIDED BY CITY OF SLIDELL. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 TAP<200K 986 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011800 - ST. BERNARD MISS RIVER TRAIL PH III Project Manager: RIGGS, LAURA Type Impv: SHARED USE PATH ON LEVEE TOP Remarks: MATCH PROVIDED BY ST. BERNARD PARISH GOVERNMENT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD 000-44 TAP>200K 1,022 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011801 - ST. CHARLES WB LEVEE PATH PH IV AND V Project Manager: MEEK, STEPHEN Type Impv: SHARED USE PATH Remarks: MATCH PROVIDED BY ST. CHARLES PARISH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES 000-45 TAP>200K 2,602 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Page 25 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.011802 - PINECONE DRIVE SIDEWALK Project Manager: Type Impv: SIDEWALKS Remarks: MATCH PROVIDED BY THE CALCASIEU PARISH POLICE JURY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 TAP<200K 358 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011803 - RUSTON DOWNTOWN REVITALIZATION PHASE VII Project Manager: Type Impv: SIDEWALKS AND STREETSCAPING Remarks: MATCH PROVIDED BY THE CITY OF RUSTON. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN 000-31 TAP<200K 660 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011804 - RUSTON DOWNTOWN REVITALIZATION PHASE IX Project Manager: Type Impv: SIDEWALKS AND STREETSCAPING Remarks: MATCH PROVIDED BY CITY OF RUSTON Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN 000-31 TAP<200K 675 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011805 - JEFFERSON WB MISS RIVER MU PATH 3B & 3C Project Manager: Type Impv: MULTI-USE PATH Remarks: MATCH PROVIDED BY JEFFERSON PARISH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 TAP>200K 481 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

JEFFERSON LA 541 826-13 TAP>200K 141 ENHANCEMENTS

Project: H.011820 - JEAN LAFITTE PKWY: SW & SHARED USE PATH Project Manager: Type Impv: SIDEWALKS AND SHARED USE PATH Remarks: MATCH PROVIDED BY ST. BERNARD PARISH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD 000-44 TAP>200K 433 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011822 - LA21: LA1085 - PINNACLE, SHARED USE PATH Project Manager: Type Impv: SHARED USE PATH Remarks: MATCH PROVIDED BY ST. TAMMANY PARISH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 TAP<200K 783 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

ST TAMMANY LA 21 059-01 TAP<200K 363 ENHANCEMENTS

Project: H.011823 - NO CITY PARK: HARRISON AVENUE TRAILHEAD Project Manager: Type Impv: TRAILHEAD Remarks: MATCH PROVIDED BY CITY PARK IMPROVEMENT ASSOCIATION Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 TAP>200K 287 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.011835 - LA25: WASHINGTON PARISH SEG A, B & C, SW Project Manager: Type Impv: SIDEWALKS Remarks: MATCH PROVIDED BY WASHINGTON PARISH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 25 059-04 TAPFLEX 276 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

WASHINGTON 000-59 TAPFLEX 69 ENHANCEMENTS

Page 26 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ENHANCEMENTS - Project: H.011836 - NEW ORLEANS: LAKE VISTA, SIDEWALKS Project Manager: Type Impv: SIDEWALKS Remarks: MATCH PROVIDED BY NON-FLOOD PROTECTION MANAGEMENT A Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 TAP>200K 499 ENHANCEMENTS 3-DESIGN/DEVELOPMENT

Project: H.009783 - BR DOWNTOWN GREENWAY MULTI-USE PATH Project Manager: Type Impv: MULTI-USE PATH W/LIGHTING, LANDSCAPING & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-110 450-92 TAP>200K 401 ENHANCEMENTS 1-PLANNING/ENVIRONMENTAL

E BATON ROUGE I-10 450-10 TAP>200K 320 ENHANCEMENTS

E BATON ROUGE 000-17 TAP>200K 332 ENHANCEMENTS

Project: H.009794 - GRETNA BICYCLE ACCESS IMPROVEMENTS Project Manager: Type Impv: SIGNING, PAVEMENT MARKINGS, M/U PATH & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 TAP>200K 170 ENHANCEMENTS 1-PLANNING/ENVIRONMENTAL

JEFFERSON US 90-Z 283-09 TAP>200K 75 ENHANCEMENTS

JEFFERSON LA 466 063-02 TAP>200K 50 ENHANCEMENTS

JEFFERSON LA 466 063-02 TAP>200K 25 ENHANCEMENTS

Project: H.009934 - ABITA SPRINGS TOWN CTR SIDEWALK LIGHTING Project Manager: MEEK, STEPHEN Type Impv: SIDEWALK LIGHTING & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 TAP<200K 218 ENHANCEMENTS 1-PLANNING/ENVIRONMENTAL

ST TAMMANY LA 435 281-04 TAP<200K 82 ENHANCEMENTS

Project: H.009939 - ST CHARLES AVE: STREETSCAPING IMP., PH 1 Project Manager: Type Impv: STREETSCAPING, DECORATIVE LIGHTING, & RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 TAP>200K 1,053 ENHANCEMENTS 1-PLANNING/ENVIRONMENTAL

Project: H.010051 - LSU HIGHLAND RD PED CORRIDOR, PHASE I Project Manager: MEEK, STEPHEN Type Impv: SIDEWALKS W/LIGHTING & LANDSCAPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 TAP>200K 267 ENHANCEMENTS 1-PLANNING/ENVIRONMENTAL

Project: L.000029 - FEDERAL ENHANCEMENT PROGRAM Project Manager: Type Impv: MISC PROJECTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - TAPFLEX 1,000 ENHANCEMENTS STAGES 4, 3, 2, 1, 0

Page 27 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 INTERMODAL CONNECTOR - Project: H.011464 - LA 3090: LA 1 - FOURCHON CITY Project Manager: Type Impv: ROADWAY REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 3090 064-30 STPFLEX 4,009 INTERMODAL CONNECTOR 4-SCHEDULED IN CURRENT FY 14-15

Project: H.005967 - NELSON RD EXT & BRIDGE Project Manager: Type Impv: NEW ROAD & BRIDGE Remarks: 706-10-0001;TEA-21. STA 87.USE STGEN$ FOR ENG Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 STGEN 2,500 INTERMODAL CONNECTOR 3-DESIGN/DEVELOPMENT

CALCASIEU 000-10 NHPP 10,000 INTERMODAL CONNECTOR

CALCASIEU 000-10 DEMO 18,300 DEMO / HIGH PRIORITY

Project: H.007250 - ALMONASTER BRIDGE AND APPR. Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 742-36-0104;OTHER FUNDS - PORT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STPFLEX 20,000 INTERMODAL CONNECTOR 3-DESIGN/DEVELOPMENT

ORLEANS 000-36 STPFLEX 20,000 SUSTAINABILITY BRIDGE (ON SYSTEM) ORLEANS 000-36 OTHER 22,000 OTHER / MISCELLANEOUS

Project: H.007300 - KANSAS LANE-GARRETT RD CONNECTOR Project Manager: Type Impv: RD CONNECTOR & INTERCHANGE IMPRVMNT Remarks: 742-37-0028;4TH FUND SOURCE US $300K STP<200K Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STPFLEX 10,000 INTERMODAL CONNECTOR 3-DESIGN/DEVELOPMENT

OUACHITA 000-37 DEMO 6,616 DEMO / HIGH PRIORITY

OUACHITA 000-37 NFI 7,431 OTHER / MISCELLANEOUS

Project: H.011670 - I-10 / LOYOLA INTERCHANGE IMPROVEMENT Project Manager: Type Impv: FEASIBILITY STUDY, IMR AND ENVIRONMENTAL ASSESSMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON I-10 450-15 0 INTERMODAL CONNECTOR 1-PLANNING/ENVIRONMENTAL

Project: H.008915 - LA3234 EXT FROM LA1065 - HAMMOND AIRPORT Project Manager: Type Impv: FEASIBILITY STUDY FOR LA 3234 EXTENSION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 3234 853-40 0 INTERMODAL CONNECTOR 0-FEASIBILITY/SCOPING

Project: L.000001 - INTERMODAL CONNECTORS PROGRAM Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 3,100 INTERMODAL CONNECTOR STAGES 4, 3, 2, 1, 0

- NHPP 6,200 INTERMODAL CONNECTOR

Page 28 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ACCESS MANAGEMENT Project: H.005693 - LA 447/I-12 INTERCHANGE Project Manager: Type Impv: CONSTRUCTING ROUNDABOUTS @ I-12 AND LA 447 WB AND EB RAMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 447 268-01 STPFLEX 5,000 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ACCESS MANAGEMENT

Project: H.009341 - LA 1085 & LA 1077: ROUNDABOUT Project Manager: HARROUCH, JOSHUA Type Impv: CONSTRUCT ROUNDABOUT Remarks: PARISH ACQUIRE R/W Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 1085 852-02 STPFLEX 822 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ACCESS MANAGEMENT ST TAMMANY LA 1085 852-02 STP<200K 500 URBAN SYSTEMS

ST TAMMANY LA 1077 852-03 STPFLEX 1,410 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.009140 - LA 1026 AT LA 1030 ROUNDABOUT Project Manager: Type Impv: ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 1026 273-03 STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ACCESS MANAGEMENT LIVINGSTON LA 1030 832-15 STPFLEX 750 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT LIVINGSTON 000-32 LOCAL 750 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.009142 - LA 86 & LA 320: ROUNDABOUT Project Manager: Type Impv: ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 86 237-01 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ACCESS MANAGEMENT IBERIA LA 320 823-12 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.009143 - LA 31 & LA 92: ROUNDABOUT Project Manager: Type Impv: ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 31 056-02 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ACCESS MANAGEMENT ST MARTIN LA 92 213-08 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.008369 - US 11 @ CLEO ROAD Project Manager: Type Impv: CONSTRUCT A ROUNDABOUT Remarks: 852-26-0021; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 190 852-26 STPFLEX 950 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ACCESS MANAGEMENT

Project: H.010206 - LA 3132 AT LA 523: EXTEND C OF A Project Manager: Type Impv: EXTEND CONTROL OF ACCESS LA 3132 AT LA 523 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 3132 427-01 NHPP 1,183 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ACCESS MANAGEMENT CADDO LA 523 103-01 NHPP 1,147 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Page 29 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ACCESS MANAGEMENT Project: H.010923 - US 79 BYPASS @ LA 9 ROUNDABOUT Project Manager: Type Impv: DESIGN AND CONSTRUCTION OF ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CLAIBORNE US 79 027-05 STPFLEX 2,950 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ACCESS MANAGEMENT

Project: H.010924 - LA 75 ROUNDABOUTS Project Manager: Type Impv: DESIGN AND CONSTRUCTION OF 2 ROUNDABOUTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 75 824-02 STPFLEX 4,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ACCESS MANAGEMENT

Project: H.011014 - LA 3002: J-TURN Project Manager: Type Impv: ADD SOUTH BOUND J-TURN FOR LEFT TURNING VEHICLES EXITING CRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 3002 832-32 NHPP 600 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ACCESS MANAGEMENT

Project: H.011189 - LA 1026 @ DUNN & EDEN CHURCH ROUNDABOUTS Project Manager: Type Impv: ROUNDABOUT INTERSECTION IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 1026 273-03 STPFLEX 4,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ACCESS MANAGEMENT

Project: H.011824 - LA 1026: ROUNDABOUT AT BUDDY ELLIS RD Project Manager: Type Impv: ROUNDABOUT INTERSECTION IMPROVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STPFLEX 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ACCESS MANAGEMENT LIVINGSTON LA 1026 832-13 STPFLEX 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011098 - LA 30: CORRIDOR IMPROVEMENTS Project Manager: Type Impv: ACCESS MANAGMENT LA 30 - NICHOLSON DR. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 30 414-01 NHPP 1,319 OPER EFFICIENCY/MOTORIST ASSISTANCE2-WAITING FOR FUNDING ACCESS MANAGEMENT

Project: H.010116 - LA 1088 CORRIDOR STUDY Project Manager: Type Impv: TRAFFIC STUDY ON LA 1088 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 1088 852-11 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT

Project: H.010672 - LA 3002 & LA 16 CORRIDOR STUDY Project Manager: Type Impv: TRAFFIC STUDY ON LA 3002, LA 16, AND LA 1034 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 3002 832-32 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT LIVINGSTON LA 16 262-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT LIVINGSTON LA 1034 832-14 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Page 30 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ACCESS MANAGEMENT Project: H.010824 - US 71 CORRIDOR STUDY Project Manager: Type Impv: CONDUCT CORRIDOR STUDY ALONG US 71 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 71 008-09 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT RAPIDES US 71 840-43 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT RAPIDES US 71 008-30 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.010960 - LA 30 ROUNDABOUTS @ TANGER MALL & I-10 Project Manager: Type Impv: 3 ROUNDABOUTS ON LA 30 INCLUDING 2 AT THE I-10 RAMPS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 30 414-03 STPFLEX 8,000 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT

Project: H.011160 - LA 73: LA 74 TO LA 621 CORRIDOR STUDY Project Manager: Type Impv: CORRIDOR STUDY TO COLLECT DATA AND DEVELOP ALTERNATIVESRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 73 077-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT

Project: H.011226 - US190/US61: LA 415 TO I-12 STUDY Project Manager: Type Impv: CORRIDOR STUDY ON US 190 / US 61 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61 007-90 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT E BATON ROUGE US 61 007-90 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT W BATON ROUGE US 190 008-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011279 - LA 328: LATIOLAIS DRIVE TO JULIE STREET Project Manager: Type Impv: STAGE 0/FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 328 404-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT

Project: H.011280 - LA 10 IMPROVEMENTS IN BOGALUSA Project Manager: Type Impv: STAGE 0/FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 10 047-04 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT

Project: H.011281 - US 171: CORRIDOR IMPROVEMENTS Project Manager: Type Impv: FEASIBILITY STUDY FOR CORRIDOR IMPROVEMENTS TO US 171 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO US 171 025-08 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT DESOTO US 171 025-07 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT DESOTO US 171 025-06 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT DESOTO US 171 025-05 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Page 31 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ACCESS MANAGEMENT Project: H.011282 - US 80: CORRIDOR IMPROVEMENTS Project Manager: Type Impv: FEASIBILITY STUDY FOR CORRIDOR IMPROVEMENTS TO US 80 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER US 80 001-04 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT BOSSIER US 80 001-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011283 - LA 1: CORRIDOR IMPROVEMENTS Project Manager: Type Impv: FEASIBILITY STUDY FOR CORRIDOR IMPROVEMENTS TO LA 1 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 1 053-08 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT

Project: H.011284 - LA 3: CORRIDOR IMPROVEMENTS Project Manager: Type Impv: LA 3 CORRIDOR FEASIBILITY/STAGE 0 STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 3 044-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT

Project: H.011288 - LA 531 AT US 79 INTERSECTION IMPROVEMENT Project Manager: Type Impv: INTERSECTION IMPROVEMENTS AT US 79 AND LA 531 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER US 79 027-04 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT WEBSTER LA 531 111-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT WEBSTER 000-60 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011340 - LA157 @ LA3227 INTERSECTION IMPROVEMENTS Project Manager: Type Impv: TRAFFIC COUNTS TO LA 157 AT LA 3227 INT. IMPROVE FEAS STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 157 082-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT BOSSIER LA 3227 808-08 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011392 - US 80 AT LA 169 INTERSECTION IMPROVEMENT Project Manager: Type Impv: INTERSECTION IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO US 80 001-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT CADDO LA 169 048-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT CADDO US 79 048-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011408 - US90(EVANG THWY)@US167(JOHNSTON ST) Project Manager: Type Impv: INTERSECTION STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 90 424-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT LAFAYETTE US 167 080-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT LAFAYETTE LA 94 828-43 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Page 32 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ACCESS MANAGEMENT Project: H.011618 - LA 22 CORRIDOR STUDY: ROU MAR NEI TO 1ST Project Manager: Type Impv: CORRIDOR STUDY FOR ACCESS MGMNT/TRAFFIC OP IMPROVEMENTSRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA US 51-X 853-36 STPFLEX 90 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT TANGIPAHOA LA 22 261-03 STPFLEX 80 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT TANGIPAHOA LA 22 261-04 STPFLEX 80 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011643 - LA 617: COUNTS FOR TRAFFIC STUDY Project Manager: Type Impv: ACCESS MANAGEMENT FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 617 837-17 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT OUACHITA LA 34 067-09 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011644 - US90: NASHVILLE - S PETERS IMPROVEMENTS Project Manager: Type Impv: CORRIDOR IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90 006-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT ORLEANS US 90-Z 283-08 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: H.011645 - LA3002:LA16:LA1034:CORRIDOR STUDY PHASE2 Project Manager: Type Impv: CORRIDOR STUDY FOR ACCESS MANAGEMENT IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 16 262-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ACCESS MANAGEMENT LIVINGSTON LA 3002 832-32 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT LIVINGSTON LA 1034 832-14 0 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Project: L.000068 - ACCESS MANAGEMENT PROJECTS Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 2,500 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 ACCESS MANAGEMENT - STPFLEX 2,500 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT - STPFLEX 8,300 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT - STPFLEX 8,100 OPER EFFICIENCY/MOTORIST ASSISTANCE ACCESS MANAGEMENT

Page 33 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - AMERICANS WITH DISABILITIES ACT Project: L.000097 - ADA PROGRAM Project Manager: Type Impv: ADA PROGRAM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 AMERICANS WITH DISABILITIES ACT - NHPP 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE AMERICANS WITH DISABILITIES ACT

Page 34 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - FERRY PROJECTS Project: H.010691 - MV STUMPF: DRY-DOCK: 5 YR EXAM & REPOWER Project Manager: Type Impv: DRY-DOCK FOR USCG 5 YEAR EXAM & REPOWER Remarks: FUNDS TRANSFERRED FROM FHWA TO FTA Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 FB DISCR 1,250 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 FERRY PROJECTS

Project: H.010689 - CCC FERRY VESSEL: TERM/LAND TECH UPGRADE Project Manager: Type Impv: TECHNOLOGY IMPROVEMENTS TO FERRY VESSELS AND TERMINAL LRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 FB DISCR 200 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS

Project: H.010694 - INSTALL AND MODIFY BARGES AND FERRIES Project Manager: Type Impv: MODIFICATION, INSTALLATION LANDING BARGE,CONVERSION TO FERemarks: FB DISCR FLEXED TO FTA THEREFORE NOT AUTH THROUGH FHW Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 FB DISCR 420 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS STATEWIDE 000-99 OTHER 330 OPER EFFICIENCY/MOTORIST ASSISTANCE FERRY PROJECTS

Project: H.011473 - BARGE 305-068: DRY-DOCK FOR REPAIRS Project Manager: Type Impv: DRY-DOCK FERRY LANDING BARGE FOR MAINTENANCE AND REPAIRRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 FB DISCR 200 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS

Project: H.011474 - BARGE 305-069: DRY-DOCK FOR REPAIRS Project Manager: Type Impv: DRY-DOCK FERRY LANDING BARGE FOR MAINTENANCE AND REPAIRRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 FB DISCR 200 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS

Project: H.011475 - M/V NEW ROADS: 5 YEAR DRYDOCK (2016) Project Manager: Type Impv: DRY-DOCK FERRY FOR 5 YEAR USCG EXAMS, MAINTENANCE & REPARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 FB DISCR 1,125 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS

Project: H.011478 - BARGE 305-008: DRYDOCK FOR REPAIRS Project Manager: Type Impv: DRYDOCK WORK BARGE 305-008 FOR REPAIRS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 STCASH 250 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS

Project: H.011479 - M/V GRIFFITH: DRYDOCK FOR REPAIRS Project Manager: Type Impv: DRYDOCK TUGBOAT M/V GRIFFITH FOR REPAIRS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 STCASH 150 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS

Project: H.011480 - M/V GRAND: DRYDOCK FOR REPAIRS Project Manager: Type Impv: DRYDOCK M/V GRAND FOR REPAIRS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 STCASH 150 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS

Page 35 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - FERRY PROJECTS Project: H.011716 - PLAQ. PAR. FERRY LAND: REPLACE DOLPHINS Project Manager: Type Impv: REPLACEMENT OF FERRY LANDING DOLPHINS (MOORING STRUCTURRemarks: LOCAL ENTITY TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 FB DISCR 950 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 FERRY PROJECTS

Project: H.010037 - NEW FERRY BOAT / CAMERON FERRY CROSSING Project Manager: Type Impv: CONSTRUCT NEW FERRY BOAT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 NFI 12,500 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL FERRY PROJECTS

Project: L.000015 - MISC FERRY PROJECTS Project Manager: Type Impv: REHABILITATION/REPAIR Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - OTHER 500 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 FERRY PROJECTS - STCASH 500 OPER EFFICIENCY/MOTORIST ASSISTANCE FERRY PROJECTS

Page 36 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - INTERSTATE LIGHTING Project: H.000687 - I-12 @ US 11 INTERCHANGE LIGHTING Project Manager: Type Impv: INTERSECTION LIGHTING IMPROVEMENTS Remarks: 018-04-0048; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-12 454-04 NHPP 898 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE LIGHTING

Project: H.003451 - I-12: LA 434 INTCHG LIGHTING (LACOMBE) Project Manager: Type Impv: INTERSTATE LIGHTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-12 454-04 NHPP 943 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE LIGHTING ST TAMMANY LA 434 852-12 0 OPER EFFICIENCY/MOTORIST ASSISTANCE INTERSTATE LIGHTING

Project: H.003452 - I-12 @ NORTHSHORE BLVD INTER. LIGHTING Project Manager: Type Impv: ROADWAY LIGHTING Remarks: 454-04-0089; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-12 454-04 NHPP 1,082 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE LIGHTING

Project: H.010720 - I-12: LA 1088 INTCHG LIGHTING Project Manager: Type Impv: INTERSTATE LIGHTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-12 454-04 NHPP 850 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE LIGHTING

Project: H.011393 - I-55: LA 38 (KENTWOOD) INTCHG LIGHTING Project Manager: Type Impv: INTERSTATE LIGHTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA I-55 452-90 NHPP 800 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE LIGHTING

Project: L.000018 - INTERSTATE LIGHTING PROGRAM Project Manager: Type Impv: IN ACCORDANCE WITH MAINTENANCE AGREEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 INTERSTATE LIGHTING - STCASH 100 OPER EFFICIENCY/MOTORIST ASSISTANCE INTERSTATE LIGHTING

Page 37 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ITS Project: H.011078 - NO RTMC BUILDING SECURITY Project Manager: SMITH, ERIK Type Impv: BUILDING SECURITY SYSTEM FOR THE NO RTMC Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STPFLEX 94 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ITS ORLEANS 000-36 STCASH 26 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011182 - ITS DYNAMIC MESSAGE SIGNS (KENNER) Project Manager: Type Impv: INSTALL 4 DYNAMIC MESSAGE SIGNS. Remarks: ENTITY WILL PROVIDE MATCH FOR LOYOLA AND POWER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 49 283-30 STPFLEX 512 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ITS JEFFERSON 000-26 STPFLEX 251 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011566 - TRAFFIC SIGNAL CONTROL SOFTWARE Project Manager: FERRIER, CARRYN Type Impv: REPLACE STREETWISE SOFTWARE WITH ATMS.NOW Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 STPFLEX 750 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ITS

Project: H.010192 - LAKE CHARLES ITS PHASE 2 Project Manager: Type Impv: ITS DEPLOYMENT AS PER REGIONAL ARCHITECTURE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-10 450-91 NHPP 2,575 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS

Project: H.011350 - CAMERON FERRY TRAVELER MESSAGE SIGNING Project Manager: KIMBENG, LUCY Type Impv: DYNAMIC MESSAGE SIGNS INSTALLATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CAMERON LA 27 193-02 STPFLEX 60 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS CAMERON LA 27 193-01 STPFLEX 60 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS CAMERON LA 27 031-01 STPFLEX 60 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS CALCASIEU LA 27 031-05 STPFLEX 60 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS CAMERON LA 82 384-01 STPFLEX 60 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011472 - I-10 BONNET CARRE EMERGENCY CROSSINGS Project Manager: Type Impv: EMERGENCY CROSSING UPGRADES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES I-10 450-14 NHPP 420 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS

Project: H.011476 - I-10 ATCHAFALAYA EMERGENCY CROSSINGS Project Manager: Type Impv: EMERGENCY CROSSOVERS UPGRADE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN I-10 450-06 NHPP 70 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS IBERVILLE I-10 450-07 NHPP 35 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Page 38 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ITS Project: H.011477 - I-55 EMERGENCY CROSSINGS Project Manager: Type Impv: EMERGENCY CROSSOVER UPGRADES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN I-55 452-01 NHPP 70 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS TANGIPAHOA I-55 452-90 NHPP 35 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011493 - LA 1: ITS EQUIPMENT UPGRADE Project Manager: Type Impv: UPGRADING AND PROVIDING NEW ITS EQUIPMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 829-32 NHPP 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS

Project: H.011499 - DMS LADDER SYSTEM PHASE 5 Project Manager: Type Impv: THIS PROJECT INCLUDES INSTALLING LADDERS ON EXISTING DMSS.Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON I-10 450-15 NHPP 550 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS ORLEANS I-10 450-90 NHPP 150 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS ORLEANS I-610 450-34 NHPP 150 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS ORLEANS US 90-Z 283-08 NHPP 150 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011500 - LAKE CHARLES ITS PHASE 3 Project Manager: Type Impv: THIS PROJECT INCLUDES INSTALLING CAMERAS & DMSS ALONG I-21Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-210 450-30 NHPP 3,000 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS

Project: H.011503 - I-10 TWIN SPAN ITS Project Manager: Type Impv: THIS PROJECT INVOLVES INSTALLING A DMS AND CAMERAS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-17 NHPP 450 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS

Project: H.011538 - TMC OPERATION/MOTORIST ASSISTANCE PATROL Project Manager: Type Impv: MOTORIST ASSISTANCE Remarks: WILL BE FOR SFY 2016, 2017, 2018, 2019 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 NHPP 3,600 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS

Project: H.011763 - LA 1 TOLL VIOLATION ENFORCEMENT SYSTEM Project Manager: Type Impv: UPGRADE TO VIOLATION ENFORCEMENT SYSTEM EQUIPMENT. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 829-32 STCASH 300 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ITS

Project: H.011326 - LAKE CHARLES TMC Project Manager: Type Impv: RENOVATION OF EXISTING BUILDING TO HOUSE TMC Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 STCASH 124 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS CALCASIEU 000-10 STPFLEX 76 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Page 39 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ITS Project: H.011504 - ALEXANDRIA ITS PHASE 2 Project Manager: Type Impv: INSTALLING BRIDGE ADVISORIES, CCTVS, AND DMSS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 167 023-01 NHPP 1,800 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS

Project: H.011505 - ALEXANDRIA ITS PHASE 3 Project Manager: Type Impv: THIS PROJECT INCLUDES INSTALLING CCTVS AND DMSS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 71 008-09 NHPP 320 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS RAPIDES US 71 008-30 NHPP 320 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS RAPIDES US 71 840-43 NHPP 320 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS RAPIDES US 165 015-30 NHPP 320 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS RAPIDES US 165 015-02 NHPP 320 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011506 - ALEXANDRIA ITS PHASE 4 Project Manager: Type Impv: THIS PROJECT INVOLVES INSTALLING CCTVS AND DMSS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES I-49 455-05 NHPP 1,300 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS

Project: H.011507 - MONROE ITS PHASE 3 Project Manager: Type Impv: THIS PROJECT WILL INSTALL CCTVS ALONG US 80. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 80 001-09 NHPP 1,250 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS OUACHITA US 80 002-01 NHPP 1,250 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011508 - MONROE ITS PHASE 4 Project Manager: Type Impv: THIS PROJECT WILL INSTALL CCTVS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 617 837-17 NHPP 1,400 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS OUACHITA LA 840-6 837-04 NHPP 1,400 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011509 - LAKE CHARLES ITS PHASE 4 Project Manager: Type Impv: THIS PROJECT WILL INSTALL DMSS AND CCTVS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-10 450-91 NHPP 1,250 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS

Project: H.011510 - SHREVEPORT ITS PHASE 4 Project Manager: Type Impv: DEPLOY ITS EQUIPMENT AND COMMUNICATIONS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-20 451-01 NHPP 100 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS BOSSIER I-20 451-02 NHPP 100 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Page 40 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ITS Project: H.011511 - US 190 ITS DEPLOYMENT Project Manager: Type Impv: DEPLOY ITS EQUIPMENT AND COMMUNICATIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY US 190 012-13 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS ST LANDRY US 190 008-04 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS POINTE COUPEE US 190 008-03 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS POINTE COUPEE US 190 008-02 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS W BATON ROUGE US 190 008-01 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011513 - MONROE ITS PHASE 2 Project Manager: Type Impv: THIS PROJECT WILL INSTALL CCTVS, DMSS, AND A RR WARNING. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 165 015-31 NHPP 600 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS OUACHITA US 165 016-01 NHPP 600 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011518 - I-10 RAMP METERS BATON ROUGE Project Manager: Type Impv: INSTALLING I-10 RAMP METERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-10 450-10 NHPP 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS

Project: H.011535 - NEW ORLEANS TRAVEL TIME (BLUETOOTH) Project Manager: Type Impv: BLUETOOTH EQUIPMENT IN DISTRICT 02 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS

Project: H.011537 - STATEWIDE ITS MAINTENANCE Project Manager: Type Impv: THIS IS A 3 YEAR MAINTENANCE CONTRACT FOR ITS EQUIPMENT. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 STPFLEX 3,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS STATEWIDE 000-99 STPFLEX 3,000 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS STATEWIDE 000-99 STPFLEX 3,000 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: H.011568 - LADOTD TOLL OPERATIONS BUSINESS PLAN Project Manager: Type Impv: DEVELOP A BUSINESS PLAN FOR LADOTD TOLL OPERATIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ITS

Project: H.007026 - ITS MAINTENANCE - STATEWIDE Project Manager: Type Impv: ROUTINE & EMERGENCY REPAIR TO ITS STATEWIDE SYSTEM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 STPFLEX 1,847 OPER EFFICIENCY/MOTORIST ASSISTANCE2-WAITING FOR FUNDING ITS STATEWIDE 000-99 STPFLEX 1,617 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS STATEWIDE 000-99 STPFLEX 1,617 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Page 41 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ITS Project: H.011334 - 511 ATIS SYSTEM Project Manager: Type Impv: DEVELOP CONOPS, FUNC. REQUIREMENTS AND RFP Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ITS

Project: H.011356 - I-12 RAMP METERS (NORTH SHORE) Project Manager: Type Impv: FEASIBILITY STUDY (I-12 RAMP METERS (NORTH SHORE)) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-12 454-04 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ITS

Project: L.000006 - MOTORIST ASSISTANCE PATROL Project Manager: Type Impv: MAP Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 1,200 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 ITS - STCASH 1 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Project: L.000017 - MISC ITS SYSTEMS Project Manager: Type Impv: ENGINEERING, CONSTRUCTION, MAINTENANCE, OPERATIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 ITS - DEMO 300 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS - CM 400 OPER EFFICIENCY/MOTORIST ASSISTANCE ITS

Page 42 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - MOVABLE BRIDGE REHABILITATION Project: H.010169 - KRAEMER LIFT BRIDGE MECHANICAL REPAIRS Project Manager: Type Impv: MECHANICAL REPAIR Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 307 829-15 STPFLEX 650 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 MOVABLE BRIDGE REHABILITATION

Project: L.000013 - MOVABLE BRIDGE PREVENTIVE MAINTENANCE Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STCASH 500 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 MOVABLE BRIDGE REHABILITATION

Page 43 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - REST AREAS Project: H.011446 - MOUND REST AREA RENOVATIONS Project Manager: Type Impv: REST AREA RENOVATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON 000-33 NHPP 11,100 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT REST AREAS

Project: H.011448 - IDA SAFETY REST AREA Project Manager: Type Impv: DESIGN AND CONSTRUCT NEW REST AREA Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 NHPP 20,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT REST AREAS

Project: H.011449 - GREENWOOD REST AREA RENOVATIONS Project Manager: Type Impv: REST AREA RENOVATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 NHPP 4,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT REST AREAS

Project: H.011471 - GRAND BAYOU REST AREA Project Manager: Type Impv: CREATE A REAST AREA BETWEEN SHREVEPORT AND NATCHITOCHERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO 000-16 NHPP 19,000 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL REST AREAS

Project: L.000032 - REST AREA REHABILITATION Project Manager: Type Impv: FACILITY REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 REST AREAS

Page 44 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ROADWAY FLOODING Project: H.009406 - LA 48 @ EVANS DR. Project Manager: Type Impv: DRAINAGE STRUCTURE REPLACEMENTS AND ADDITIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 48 006-30 NHPP 451 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ROADWAY FLOODING

Project: H.010260 - LA 21 VARNADO DRAINAGE IMPROVEMENTS Project Manager: Type Impv: ADDING A SUBSURFACE DRAINAGE SYSTEM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 21 030-04 STPFLEX 83 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ROADWAY FLOODING

Project: H.010420 - LA 505 ROADWAY FLOODING .9 MI N WINN P/L Project Manager: Type Impv: REPLACE EXISTING CMP CROSS DRAIN WITH RCB CROSWS DRAIN Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON LA 505 321-03 NFA 131 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ROADWAY FLOODING

Project: H.011022 - US 61 @ EVANGELINE RD. Project Manager: Type Impv: RAISING ROADWAY GRADE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES US 61 007-03 STPFLEX 786 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ROADWAY FLOODING

Project: H.011614 - LA 15: DRAINAGE IMPROV 1.0 MI N OF US 80 Project Manager: Type Impv: REMOVE AND REPLACE EXISTING CROSS DRAIN W/ LARGER STRUCTRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 15 156-01 STPFLEX 117 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ROADWAY FLOODING

Project: H.011624 - LA 576: DRAINAGE IMPROV 0.4 MI N LA 135 Project Manager: Type Impv: REMOVE AND REPLACE EXISTING DRAINGE STRUCTURE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 576 341-02 NFA 264 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ROADWAY FLOODING

Project: H.011626 - LA 577: DRAINAGE IMPROV 0.7 MI N LA 134 Project Manager: Type Impv: REMOVE AND REPLACE EXISTING CROSS DRAIN W/ LARGER STRUCTRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W CARROLL LA 577 862-17 NFA 400 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 ROADWAY FLOODING

Project: H.009391 - LA 3188 DRAINAGE IMPROVEMENTS Project Manager: Type Impv: DRAINAGE IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 3188 848-15 STPFLEX 1,800 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Project: H.010256 - LA 182:BRUNER ST - VINE ST DRAINAGE IMP. Project Manager: Type Impv: INSTALL NEW DRAINAGE STRUCTURES, CONCRETE CURB AND GUTTRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 182 004-04 STPFLEX 900 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Page 45 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ROADWAY FLOODING Project: H.010257 - GRADE RAISING I-10 RAMPS @ LA 3188 INT. Project Manager: Type Impv: RAISING THE EXISTING GRADE OF THE I-10 RAMPS AT LA 3188 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN I-10 450-13 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Project: H.010263 - LA 1: DRAINAGE IMPROVEMENTS Project Manager: Type Impv: CROSS DRAIN IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage POINTE COUPEE LA 1 052-04 STPFLEX 88 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Project: H.010331 - US 90: FLOODWALL - CHEF PASS BRIDGE Project Manager: Type Impv: RAISING ROADWAY GRADE TO CONSISENT ELEVATION BY ADDING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90 006-90 STPFLEX 600 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Project: H.010424 - LA 823 ROADWAY FLOODING 1.8 MI E LA 151 Project Manager: Type Impv: RAISE THE ROADWAY ELEVATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 823 314-01 NFA 500 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Project: H.010439 - BOYD ST & 21ST ST PUMPING STA IMP I-110 Project Manager: Type Impv: REPLACE PUMP STATION FLOAT SYSTEM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-110 450-92 NHPP 750 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING E BATON ROUGE I-110 450-92 NHPP 750 OPER EFFICIENCY/MOTORIST ASSISTANCE ROADWAY FLOODING

Project: H.011019 - LA 101: ELEVATE ROADWAY Project Manager: Type Impv: ELEVATE THE ROADWAY Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 101 209-01 STPFLEX 300 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Project: H.011024 - I-10: OAK HARBOR RAMPS Project Manager: Type Impv: RAISING EXISTING GRADE WITH EMBANKMENT IN EXISTING CROWN.Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-10 450-18 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Project: H.011027 - LA 111 SOUTH OF EVANS - ADD CROSS DRAIN Project Manager: Type Impv: REPLACE 4 EXISTING PIPE WITH 5 - 48" RCPAS AND ELEVATE ROAD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 111 132-02 STPFLEX 341 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 ROADWAY FLOODING

Project: H.009425 - LA 16 AMITE DRAINAGE IMPROVEMENTS Project Manager: NILFOROUSHAN, MEHDI Type Impv: DRAINAGE IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 16 047-01 STPFLEX 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Page 46 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ROADWAY FLOODING Project: H.010251 - CHIPPEWA ST PUMP STATION IMP US61/190-X Project Manager: Type Impv: REPLACE/UPGRADE PUMP HOUSE COMPONENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61-X 817-20 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.010253 - LUEBONNET BLVD. PUMP STAT. IMP LA 1248 Project Manager: Type Impv: REPLACE PUMP STATION FLOAT SYSTEM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 1248 258-33 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.010324 - LA 1: GOLDEN MEADOW - LEEVILLE Project Manager: Type Impv: RAISING ROADWAY GRADE TO CONSISENT ELEVATION BY ADDING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 064-90 NHPP 900 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.010565 - ACADIAN STREET PUMPING STATION Project Manager: Type Impv: REPLACE/UPGRADE PUMPHOUSE COMPONENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 427 258-02 STPFLEX 650 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011021 - LA 17: SHARON STREET TO TENNESSEE STREET Project Manager: Type Impv: REMOVE AND REPLACE EXISTING SUBSURFACE DRAINAGE STRUCTURemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 17 051-04 STPFLEX 1,114 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011025 - LA 40: NATALBANY RIVER TO I-55 Project Manager: Type Impv: ADDITIONAL PIPE(S), CATCH BASINS, AND/OR ASPHALT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 40 415-02 STPFLEX 50 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011026 - LA 182 WB: LASALLE ST. - VINE ST. Project Manager: Type Impv: DRAINAGE STRUCTURE REMOVAL AND REPLACEMENT, ROADWAY WRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 182 004-04 STPFLEX 342 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011512 - US 51 @ SYCAMORE ST AMITE CITY DRAINAGE Project Manager: Type Impv: ADDITIONAL PIPE(S), CATCH BASINS, AND/OR ASPHALT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA US 51 017-05 STPFLEX 50 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011515 - LA 44: PALM ST & BEECH ST DRAINAGE Project Manager: Type Impv: ADDITIONAL PIPE(S), CATCH BASINS, AND/OR ASPHALT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 44 256-01 STPFLEX 50 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Page 47 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ROADWAY FLOODING Project: H.011516 - US 90 @ LA 182 Project Manager: Type Impv: RAISING ROADWAY ELEVATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE US 90 005-07 NHPP 250 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011517 - LA 654: LA 308 - GREENS S. CUT RD. Project Manager: Type Impv: RAISING ROADWAY ELEVATION BY ADDING ASPHALT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 654 829-10 NFA 350 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011519 - LA 1063: GLENDALE DR - US 51 DRAINAGE Project Manager: Type Impv: ADDITIONAL PIPE(S), CATCH BASINS, AND/OR ASPHALT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 1063 853-34 NFA 100 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011520 - LA 1019: LA 16-CALMES RD DRAINAGE Project Manager: Type Impv: REMOVE AND REPLACE PIPES, CATCH BASINS, AND/OR ASPHALT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 1019 832-02 STPFLEX 300 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011547 - LA 541 & LA 560-2: JESSIE ST. - LA 18 Project Manager: Type Impv: ADD DRAINAGE STRUCTURES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 560-2 826-49 STPFLEX 800 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING JEFFERSON LA 541 826-13 STPFLEX 200 OPER EFFICIENCY/MOTORIST ASSISTANCE ROADWAY FLOODING

Project: H.011548 - LA 48: LOWERLINE ST. - PROSPECT AVE. Project Manager: Type Impv: ADDING DRAINAGE STRUCTURES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 48 282-02 STPFLEX 250 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011549 - US 190 EB: DRAINAGE IMPROVEMENTS Project Manager: Type Impv: REMOVE BASE & SURFACING, RECONSTRUCT AT HIGHER ELEV Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY US 190 012-12 STPFLEX 800 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011613 - US 425: DRAINAGE IMPROV AT EAST PINE AVE Project Manager: Type Impv: SUBSURFACE DRAINAGE IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE US 425 038-03 NHPP 320 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Project: H.011615 - LA 151: DRAINAGE IMPROV 0.02 MI N US 80 Project Manager: Type Impv: REMOVE AND REPLACE THE EXISTING DRAINAGE STRUCTURE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 151 317-02 STPFLEX 85 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT ROADWAY FLOODING

Page 48 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - ROADWAY FLOODING Project: H.009402 - RDWY DRAINAGE IMP.-US 71 @ US 371 PH III Project Manager: Type Impv: SUBSURFACE DRAINAGE AND OUTFALL CHANNEL IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RED RIVER US 371 021-30 STPFLEX 535 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ROADWAY FLOODING

Project: H.010328 - LA 659: HOWARD BRIDGE-DAIGLEVILLE BRIDGE Project Manager: Type Impv: CB-06 TOP MODIFICATIONS, CROSS DRAIN REMOVAL AND REPLACEMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 659 855-04 STPFLEX 200 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ROADWAY FLOODING

Project: H.010441 - GRADE RAISING ON LA 1077 Project Manager: Type Impv: DRAINAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 1077 852-13 NFA 2,000 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL ROADWAY FLOODING

Project: L.000020 - MISC DRAINAGE PROJECTS Project Manager: Type Impv: TO ALLEVIATE FLOODING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 ROADWAY FLOODING - STCASH 250 OPER EFFICIENCY/MOTORIST ASSISTANCE ROADWAY FLOODING

Page 49 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.011176 - INSTALL SE LA PERM CONTRAFLOW SIGNING Project Manager: Type Impv: SE LA - PERMANENT SIGNING FOR CONTRAFLOW EVACUATION EVENRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JAMES I-10 450-12 NHPP 18 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES JEFFERSON I-10 450-15 NHPP 64 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST JOHN I-10 450-13 NHPP 38 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ASCENSION I-10 450-11 NHPP 22 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST JOHN US 61 007-04 NHPP 18 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST JAMES US 61 007-05 NHPP 17 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST CHARLES I-310 450-36 NHPP 36 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST TAMMANY I-59 453-01 NHPP 29 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST TAMMANY I-12 454-04 NHPP 25 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST TAMMANY US 190 013-12 NHPP 15 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011267 - I-20 & I-49 PAVEMENT MARKING REPL. I Project Manager: Type Impv: REMOVE AND REPLACE EXISTING PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-20 451-01 NHPP 400 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES BOSSIER I-20 451-02 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES CADDO I-49 455-08 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011269 - I-10 PAVEMENT MARKING REPLACEMENT IV Project Manager: Type Impv: REMOVE AND REPLACE EXISTING PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION I-10 450-11 NHPP 370 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES E BATON ROUGE I-10 450-10 NHPP 30 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011271 - I-10 PAVEMENT MARKING REPLACEMENT II Project Manager: Type Impv: REMOVE AND REPLACE EXISTING PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-90 NHPP 800 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES

Project: H.011407 - DISTRICT 02H CONTROLLER UPGRADE Project Manager: Type Impv: UPGRADE OF EXISTING SIGNAL CONTROLLERS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 STPFLEX 252 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES

Project: H.011554 - I-10 & I-210: PAVEMENT MARKING REPL. II Project Manager: Type Impv: REMOVE AND REPLACE EXISTING PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-10 450-91 NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES CALCASIEU I-210 450-30 NHPP 200 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Page 50 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.011641 - US 90: PAVEMENT MARKING REPLACEMENT II Project Manager: Type Impv: RAISED PAVEMENT MARKERS, PLASTIC PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY US 90 424-05 NHPP 900 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES LAFAYETTE US 90 424-02 NHPP 200 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST MARTIN US 90 424-03 NHPP 100 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES IBERIA US 90 424-04 NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ASSUMPTION US 90 424-06 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011646 - US 90 - US 61 - LA 611-9 CORRIDOR IMPROV Project Manager: Type Impv: INTERSECTION IMPROVEMENT STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90 006-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES ORLEANS US 61 007-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS LA 611-9 836-05 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011658 - US 90 BUS SIGNING UPGRADE-WEST BANK Project Manager: COURTIER, KAY Type Impv: SIGNING UPGRADES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 90-Z 283-09 NHPP 767 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED IN CURRENT FY 14-15 TRAFFIC CONTROL DEVICES ORLEANS US 90-Z 283-08 NHPP 190 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.003328 - I-20: GARRETT RD. TO MADISON Project Manager: Type Impv: INTERSTATE SIGNING REHAB Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND I-20 451-07 NHPP 1,226 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRAFFIC CONTROL DEVICES OUACHITA I-20 451-06 NHPP 423 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.003476 - LA 8 TO LA 6 (I-49 SIGNING) Project Manager: Type Impv: INTERSTATE SIGNING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES I-49 455-06 NHPP 1,211 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRAFFIC CONTROL DEVICES RAPIDES I-49 455-05 NHPP 358 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.009194 - DIST. 08 PAVEMENT MARKING REPLACE III: Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 08 000-98 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRAFFIC CONTROL DEVICES

Page 51 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.011186 - DIST. 61 TRAFFIC CONTROL UPGRADE 3 Project Manager: Type Impv: SIGNALS TO BE UPGRADE TO CURRENT DOTD STANDARDS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61-X 019-01 STPFLEX 600 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRAFFIC CONTROL DEVICES E BATON ROUGE US 61-X 013-04 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES E BATON ROUGE LA 67 060-01 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES E BATON ROUGE LA 67 060-01 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011331 - OVERHEAD SIGN TRUSS INVENTORY/INSPECTION Project Manager: Type Impv: INVENTORY/INSPECTION OF OVERHEAD SIGN TRUSSES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRAFFIC CONTROL DEVICES

Project: H.011341 - DIST 03 FLASHING YELLOW ARROW UPGRADE Project Manager: Type Impv: SIGNAL UPGRADES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 03 000-93 STPFLEX 3,500 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRAFFIC CONTROL DEVICES

Project: H.011405 - DISTRICT 04 CONTROLLER UPGRADE Project Manager: Type Impv: UPGRADE OF EXISTING SIGNAL CONTROLLERS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 04 000-94 STPFLEX 389 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRAFFIC CONTROL DEVICES

Project: H.009052 - DIST. 58 PAVEMENT MARKING REPLACEMENT II Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 58 000-91 STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.009054 - DIST. 02 PAVEMENT MARKING REPLACEMENT II Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MAKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.009056 - DIST 07. PAVEMENT MARKING REPLACEMENT II Project Manager: Type Impv: PLASTIC PAVEMENT STIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 07 000-97 STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.009186 - DIST. 02 PAVEMENT MARKING REPLACE III: Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAVISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Page 52 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.009189 - DIST. 04 PAVEMENT MARKING REPLACE III: Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 04 000-94 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.009199 - DIST. 61 PAVEMENT MARKING REPLACE III: Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 61 000-96 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.009200 - DIST. 62 PAVEMENT MARKING REPLACE III: Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 62 000-90 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.011187 - DISTRICT 02H: SIGNAL TIMING Project Manager: Type Impv: SIGNAL TIMING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 24 065-04 STPFLEX 2 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES TERREBONNE LA 3040 065-30 STPFLEX 1 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES TERREBONNE LA 24 065-91 STPFLEX 1 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES LAFOURCHE LA 1 064-06 STPFLEX 2 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011219 - I-10: NO CBD1 I610-CARROLLTON Project Manager: Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT & UPGRADE IN NORemarks: C Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-90 NHPP 4,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.011220 - I-10: NO CBD2 CARROLLTON - POYDRAS Project Manager: Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT & UPGRADE IN NORemarks: C Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-90 NHPP 8,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.011406 - DISTRICT 02BC CONTROLLER UPGRADE Project Manager: Type Impv: UPGRADE OF EXISTING SIGNAL CONTROLLERS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 02 000-92 STPFLEX 331 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Project: H.011733 - US 80 TRAFFIC CONTROL UPGRADES Project Manager: Type Impv: SIGNAL UPGRADES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO US 80 001-02 STPFLEX 2,250 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRAFFIC CONTROL DEVICES

Page 53 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.005734 - LA 447 CORRIDOR STUDY Project Manager: COLVIN, JODY Type Impv: TRAFFIC ANALYSIS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.005759 - LA 44 SIGNAL TIMING STUDY Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 44 265-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.009191 - DIST. 05 PAVEMENT MARKING REPLACE III: Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 05 000-95 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.009193 - DIST. 07 PAVEMENT MARKING REPLACE III: Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 07 000-97 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.009197 - DIST. 58 PAVEMENT MARKING REPLACE III: Project Manager: Type Impv: PLASTIC PAVEMENT STRIPING AND RAISED PAVEMENT MARKERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 58 000-91 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.009905 - LA 415 CORRIDOR STUDY Project Manager: Type Impv: EFFICIENCY AS DETOUR ROUTE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 415-S 013-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES W BATON ROUGE LA 415 225-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES W BATON ROUGE LA 415 861-22 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.010031 - DISTRICT 62 TRAFFIC SIGNAL INVENTORY Project Manager: Type Impv: INVENTORY TRAFFIC SIGNALS IN DIST 62 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 62 000-90 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.010634 - CCCD-US90BUS SIGN UPGRADE-EAST/WEST BANK Project Manager: Type Impv: UPGRADING SIGNS ENTIRE LIMITS. UPGRADING STRUCTURES AS NEERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90-Z 283-08 NHPP 3,500 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES JEFFERSON US 90-Z 283-09 NHPP 3,500 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Page 54 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.010876 - I-20 & I-49 SPEED STUDY Project Manager: Type Impv: CONDUCT SPEED STUDY ON INTERSTATE 20 AND INTERSTATE 49 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 04 000-94 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES DISTRICTWIDE 05 000-95 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES DISTRICTWIDE 08 000-98 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011099 - DIST. 04 SIGNAL TIMING STUDIES PHASE 2 Project Manager: Type Impv: IMPROVE SIGNAL TIMING FOR DISTRICT 04 CORRIDORS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO US 171 025-08 NHPP 64 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES BOSSIER LA 72 010-30 STPFLEX 10 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES CADDO LA 1 053-09 NHPP 37 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES BOSSIER LA 3105 808-07 STPFLEX 42 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES CADDO LA 526 809-08 STPFLEX 37 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES BOSSIER LA 72 010-31 STPFLEX 10 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011177 - INTERCHANGE TRAFFIC COUNTS: PHASE 2 Project Manager: Type Impv: ANALYZE INTERCHANGES TO IMPROVE TRAFFIC FLOW &SAFETY @ Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.011180 - INTERCHANGE TRAFFIC COUNTS: PHASE 1 Project Manager: Type Impv: ANALYZE INTERCHANGES TO IMPROVE TRAFFIC FLOW &SAFETY @ Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.011181 - INTERCHANGE TRAFFIC COUNTS: PHASE 3 Project Manager: Type Impv: ANALYZE INTERCHANGES TO IMPROVE TRAFFIC FLOW &SAFETY @ Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.011221 - I-10: NO CBD3 POYDRAS - LOUISA Project Manager: Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT & UPGRADE IN NORemarks: C Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-90 NHPP 8,000 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Project: H.011222 - I-10: NO CBD4 LOUISA - I-510 Project Manager: Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT & UPGRADE IN NORemarks: C Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-90 NHPP 5,000 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES

Page 55 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.011223 - I-10: NO CBD5 I-510 - STATELINE Project Manager: Type Impv: SIGNING & SIGNING STRUCTURES REPLACEMENT &UPGRADE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-10 450-18 NHPP 2,412 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES ORLEANS I-10 450-90 NHPP 1,578 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS I-10 450-17 NHPP 1,010 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011460 - I-10: LA47 & 3021 INTERSEC IMPROV Project Manager: Type Impv: INTERSECTION IMPROVEMENT STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS LA 47 148-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011514 - INTERSECT IMPROV ALONG US 61 & LA 3154 Project Manager: Type Impv: INTERSECTION IMPROVEMENT STUDY Remarks: FEASIBILITY STUDY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 61 007-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES JEFFERSON LA 3154 826-44 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011640 - I-10 ATCHAFALAYA SPEED LIMIT SIGNS Project Manager: Type Impv: REPLACE SPEED LIMIT SIGNS AND RELATED WORKS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN I-10 450-06 NHPP 125 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES IBERVILLE I-10 450-07 NHPP 125 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011642 - LA39, LA46 & LA3021 CORRIDOR IMPROVEMENT Project Manager: Type Impv: TRAFFIC COUNTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS LA 39 046-31 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES ORLEANS LA 46 046-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS LA 3021 419-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011647 - US61, LA611 & LA3152 CORRIDOR IMPROVE Project Manager: Type Impv: CORRIDOR IMPROVEMENT STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 61 007-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES JEFFERSON LA 3152 826-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES JEFFERSON LA 611-9 826-04 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Page 56 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.011648 - LA39, 46 & 47 CORRIDOR IMPROVE Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS LA 39 046-31 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES ST BERNARD LA 39 046-32 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS LA 46 046-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST BERNARD LA 46 046-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST BERNARD LA 47 148-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011649 - I-610, US 90 & LA3021 CORRIDOR IMPROVE Project Manager: Type Impv: CORRIDOR IMPROVEMENT STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90 006-90 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES ORLEANS I-610 450-34 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS LA 3021 419-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011651 - I-10: LOYOLA DR-BONNABEL CORRIDOR IMPROV Project Manager: Type Impv: CORRIDOR IMPROVEMENT STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES JEFFERSON LA 3152 826-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES JEFFERSON I-10 450-15 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.011708 - US 61 AT US 190 INTERCHANGE SIGNING Project Manager: Type Impv: REPLACE EXISTING SIGNS AND RELATED WORKS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61-X 013-04 NHPP 200 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES E BATON ROUGE US 190 013-05 NHPP 200 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES E BATON ROUGE US 61 007-90 NHPP 200 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Page 57 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRAFFIC CONTROL DEVICES Project: H.011750 - INTERSTATE HIGHWAY SPEED STUDIES Project Manager: Type Impv: SPEED STUDIES CONDUCTED ALONG STATEWIDE INTERSTATE SYSTERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA I-55 452-90 0 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRAFFIC CONTROL DEVICES ST TAMMANY I-59 453-01 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES E BATON ROUGE I-110 450-92 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES CALCASIEU I-210 450-30 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES BOSSIER I-220 451-31 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST CHARLES I-310 450-36 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS I-510 450-43 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ORLEANS I-610 450-34 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES CADDO I-220 451-30 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: H.009321 - DISTRICT 62 TRAFFIC CONTROL Project Manager: Type Impv: INTERSECTION IMPROVEMENTS - STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA US 51 017-05 0 OPER EFFICIENCY/MOTORIST ASSISTANCE0-FEASIBILITY/SCOPING TRAFFIC CONTROL DEVICES TANGIPAHOA LA 38 263-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES ST TAMMANY US 190 059-02 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES WASHINGTON LA 436 859-09 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES TANGIPAHOA LA 16 262-07 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES WASHINGTON LA 10 047-03 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES WASHINGTON LA 3124 030-32 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES WASHINGTON LA 60 279-04 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES WASHINGTON LA 16 058-05 0 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: L.000033 - MISC SIGNS, STRIPING, SIGNALS Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 TRAFFIC CONTROL DEVICES - STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE TRAFFIC CONTROL DEVICES

Project: L.000034 - INSTALL RAISED PAVEMENT MARKERS Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STCASH 2,000 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 TRAFFIC CONTROL DEVICES

Page 58 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRANSPORTATION SYSTEMS MANAGEMENT Project: H.010430 - LA 594: TURN LANE @ OUACHITA PAR HIGH Project Manager: Type Impv: THROUGH LANE WITH RIGHT TURN LANE AT HIGH SCHOOL Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 594 326-01 STPFLEX 1,200 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010432 - US 167 & US 63: TURN LANE @ REYNOLDS DR Project Manager: Type Impv: US 167 ADD RT TURN LANE AT REYNOLDS RD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN US 63 023-10 NHPP 700 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010442 - LA 3073: INTERSECT IMPROVE @ JCT LA 89 Project Manager: Type Impv: CONSTRUCT TURN LANES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 3073 828-39 NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT LAFAYETTE LA 89-1 216-03 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010728 - LA 1090: US 190 TO I-10 WIDENING Project Manager: Type Impv: THREE LANE BY WIDENING. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 1090 852-26 STPFLEX 1,135 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010821 - US 71:WIDENING OF SERVICE RD CONNECTIONS Project Manager: Type Impv: WIDEN EXISTING SERVICE ROAD CONNECTIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 71 008-30 NHPP 270 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010945 - LA 30 & LA 74: INTERSECTION IMPROVS Project Manager: Type Impv: TURN LANE ADDITIONS AND CLOSURE OF SELECTED CROSSOVERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 30 414-02 STPFLEX 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT IBERVILLE LA 74 264-01 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010975 - LA 175: NB LEFT TURN LANE AT LA 3015 Project Manager: Type Impv: ADDING LEFT TURN LANE TO IMPROVE TRAFFIC FLOW Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 175 035-04 STPFLEX 350 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010977 - US 371: BI-DIRECTIONAL TURN LANE AT LA 4 Project Manager: Type Impv: ADDING LEFT TURN LANES AT LA 4 IN BOTH DIRECTIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE US 371 027-02 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010982 - LA 25 : JACKSON ST. - HAY HOLLOW RD. Project Manager: Type Impv: WIDENING & RE-STRIPING FOR CENTER TURN LANE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 25 059-02 STPFLEX 550 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Page 59 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRANSPORTATION SYSTEMS MANAGEMENT Project: H.010983 - I-55: RAMP WIDENING, NB OFF RAMP @ LA 16 Project Manager: Type Impv: RAMP WIDENING, ADDITIONAL TURN LANE ON EXIT RAMP Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA I-55 452-90 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010985 - US 90: IMP @ US 90B & NEAR LA 18 Project Manager: Type Impv: EXTEND ACCELERATION LANE AT THE INTERSECTION OF US 90B Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 90 005-10 NHPP 550 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010987 - LA 433: BYU BONFOUCA - US 11 CENTER TURN Project Manager: Type Impv: CENTER TURN LANE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 433 852-21 STPFLEX 450 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011154 - US 71 AND LA 3170 TURN LANES Project Manager: Type Impv: ADD TURN LANE AND INSTALL CONCRETE ISLAND Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 71 008-09 NHPP 225 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT RAPIDES LA 3170 840-35 STPFLEX 175 OPER EFFICIENCY/MOTORIST ASSISTANCE TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011212 - LA 948: EXTEND WB RIGHT TURN LANE Project Manager: Type Impv: EXTEND WESTBOUND RIGHT TURN LANE FOR ADDITIONAL CAPACITYRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 948 258-01 NHPP 600 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011305 - US 61: LEFT TURN LANE AT LOG MILE 6.0 Project Manager: DEVILLE, JACQUES Type Impv: ADD LEFT TURN LANE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES US 61 007-03 STPFLEX 430 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011354 - LA 107: STILLEY RD & PINEGROVE INT IMP Project Manager: Type Impv: RE-STRIPE LA 107 AT PINEGROVE FOR RIGHT TURN LN AND CONST RRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 107 142-04 STPFLEX 290 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011361 - US 71: TURN LANES FOR EMERG STAGING AREA Project Manager: Type Impv: MILL, CONSTRUCT TURN LANES, AND INSTALL PAVEMENT STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 71 008-09 STBONDS 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011421 - LA 3032: LT TURN LANES AT CAMILLA DR Project Manager: Type Impv: ADDING LEFT TURN LANES IN THE MEDIAN IN BOTH DIRECTIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 3032 420-01 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Page 60 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRANSPORTATION SYSTEMS MANAGEMENT Project: H.011441 - LA 3185: RIGHT TURN LANE AT LA 20 Project Manager: Type Impv: ADD RIGHT TURN LANE ON LA 3185 AT LA 20 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 3185 855-17 STPFLEX 100 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011442 - LA 3127: RIGHT TL @ ASPHALT PLANT RD Project Manager: Type Impv: ADD RIGHT TURN LANE AND ACCELERATION LANE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 3127 428-03 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011443 - LA 56: RIGHT TURN LANE AT LA 24 Project Manager: Type Impv: ADD RIGHT TURN LANE ON LA 56 AT LA 24 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 56 247-03 STPFLEX 150 OPER EFFICIENCY/MOTORIST ASSISTANCE4-SCHEDULED FOR LETTING FY 15-16 TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.002075 - PAVEMENT WIDENING-MP42.7-I-10 FR RD Project Manager: Type Impv: PAVEMENT WIDENING Remarks: 197-02-0023;ON GRANDFATHER LIST FOR FED FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 383 197-02 STPFLEX 1,250 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.002672 - JACKSON(LA 1208-3) @ HORSESHOE Project Manager: Type Impv: INTERSECTION IMPROVEMENT Remarks: 368-03-0030 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 1208-3 368-03 STPFLEX 1,000 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT RAPIDES LA 1208-3 368-03 STP<200K 15 URBAN SYSTEMS

RAPIDES 000-40 STPFLEX 600 OPER EFFICIENCY/MOTORIST ASSISTANCE TRANSPORTATION SYSTEMS MANAGEMENT RAPIDES 000-40 STP<200K 15 URBAN SYSTEMS

Project: H.008065 - HICKORY/DOCK ROUNDABOUT Project Manager: Type Impv: ROUNDABOUT INSTALLATION Remarks: 826-44-0032; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 3154 826-44 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010792 - US 61 & LA 73: IMPROV'S AT PECUE LANE Project Manager: Type Impv: INTERSECTION MODIFICATIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61 007-08 STPFLEX 500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT E BATON ROUGE LA 73 077-04 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010890 - LA 182: ROUNDABOUT AT HOLLYWOOD RD Project Manager: Type Impv: ADD ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 182 005-05 STPFLEX 600 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Page 61 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRANSPORTATION SYSTEMS MANAGEMENT Project: H.010964 - US 167:TURN LANE IMPROVEMENT AT HODGE Project Manager: Type Impv: TURN LANE IMPROVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON US 167 023-06 NHPP 250 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010974 - US 79: NB LEFT TURN LANE AT MILLER ROAD Project Manager: Type Impv: ADDING LEFT TURN LANE AT MILLER ROAD (WEBSTER PARISH) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER US 79 027-04 STPFLEX 350 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010978 - US 84: LEFT TURN LANES AT LA 481 Project Manager: Type Impv: ADDING A LEFT TURN LANES IN BOTH DIRECTIONS AT LA 481 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO US 84 021-02 STPFLEX 400 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010980 - LA 10:CUMBERLAND ST- AUSTIN ST(BOGALUSA) Project Manager: Type Impv: LANE CONFIGURATION MODIFICATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 10 047-04 NHPP 150 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010997 - LA 3185: IMP @ MAIN PROJECT RD Project Manager: Type Impv: INTERSECTION IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 3185 855-17 STPFLEX 150 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011404 - US 171: ADD ACCELERATION LANE CRYER RD Project Manager: Type Impv: CONSTRUCT ACCELERATION LANE SOUTH OF CRYER CEMETERY RDRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON US 171 024-06 NHPP 300 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011420 - LA 3132: EB ENTRANCE LANE EXTENSION Project Manager: Type Impv: EXTENDING ACCELERATION LANE FROM ENTRANCE RAMP Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 3132 427-01 NHPP 250 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011436 - I-20: EB EXIT RAMP AT LA 3105 EXTENSION Project Manager: Type Impv: EXTEND EXIT RAMP Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER I-20 451-02 NHPP 600 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011437 - I-220: EB EXIT RAMP IMPROVEMENT AT LA 3 Project Manager: Type Impv: EXTENDING TURN LANE TO PROVIDE ADDITIONAL VEHICLE STORAGERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER I-220 451-31 NHPP 150 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Page 62 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - TRANSPORTATION SYSTEMS MANAGEMENT Project: H.011444 - LA 308: TURN LANES AT TIGER DRIVE BRIDGE Project Manager: Type Impv: ADD TURN LANES FORM LA 308 TO TIGER DRIVE BRIDGE (LA 3266) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 308 407-05 STPFLEX 300 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011447 - US 90: INTERSECTION IMP AT MLK BLVD Project Manager: Type Impv: INTERSECTION IMPROVEMENTS ON US 90 AT MLK BLVD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90 006-03 NHPP 500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011501 - LA 70: GATOR LANDFILL TURN LANE Project Manager: Type Impv: TURN LANE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 70 426-03 STPFLEX 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011502 - US 61: TURN LANE IMPROVEMENTS @ LA 621 Project Manager: Type Impv: TURN LANE IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION US 61 007-07 NHPP 1,500 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011661 - INTERSECTION IMPROVEMENT LA 33 @ LA 15 Project Manager: Type Impv: WIDEN INTERSECTION WITH ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage UNION LA 33 069-03 STPFLEX 210 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011662 - INTERSECTION IMPROVEMENT LA 2 @ LA 15 Project Manager: Type Impv: INTERSECTION IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage UNION LA 2 070-04 STPFLEX 200 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.011687 - LA 447: LA 1029 - WESTCOLL RD TURN LANES Project Manager: Type Impv: WIDENING FOR LEFT TURN LANES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 447 268-02 STPFLEX 617 OPER EFFICIENCY/MOTORIST ASSISTANCE3-DESIGN/DEVELOPMENT TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010267 - US 90: LEWIS ST. LEFT TURN LANE Project Manager: Type Impv: CONSTRUCT LEFT TURN LANE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA US 90 424-04 NHPP 125 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL TRANSPORTATION SYSTEMS MANAGEMENT

Project: L.000007 - TRANSPORTATION SYSTEMS MANAGEMENT Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 250 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 TRANSPORTATION SYSTEMS MANAGEMENT - STCASH 500 OPER EFFICIENCY/MOTORIST ASSISTANCE TRANSPORTATION SYSTEMS MANAGEMENT

Page 63 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OPER EFFICIENCY/MOTORIST ASSISTANCE - WEIGH STATIONS Project: H.003672 - KENTWOOD WEIGH STATION REHAB. Project Manager: Type Impv: DEMO..CONST. AND PIT SCALE REHAB Remarks: 690-29-0008;PRIORITY 7 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA 000-53 NHPP 2,901 OPER EFFICIENCY/MOTORIST ASSISTANCE2-WAITING FOR FUNDING WEIGH STATIONS

Project: H.003740 - STARKS WEIGH STATION BUILDING Project Manager: Type Impv: NEW WEIGH STATION BUILDING Remarks: 697-13-0005;PRIORITY 1 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 0 OPER EFFICIENCY/MOTORIST ASSISTANCE2-WAITING FOR FUNDING WEIGH STATIONS

Project: H.006881 - WEIGH STATION SEWER TREATMENT EQU. Project Manager: Type Impv: NEW SEWER TREATMENT EQU. STATEWIDE Remarks: 737-99-0823; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 NHPP 350 OPER EFFICIENCY/MOTORIST ASSISTANCE1-PLANNING/ENVIRONMENTAL WEIGH STATIONS

Project: L.000036 - WEIGH STATION REHABILITATION/UPGRADE Project Manager: Type Impv: MISC SITES STATEWIDE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 1,900 OPER EFFICIENCY/MOTORIST ASSISTANCESTAGES 4, 3, 2, 1, 0 WEIGH STATIONS

Page 64 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: H.011128 - I-10 @ LA 3188 OVERPASS GIRDER REPAIR Project Manager: Type Impv: REPAIR. TRUCK IMPACTED GIRDERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 3188 848-15 REIMB 250 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

ST JOHN LA 3188 848-15 NHPP 250 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.011324 - LA 495: CLOUTIERVILLE FLOODGATE X-DRAIN Project Manager: Type Impv: REPAIR DRAINAGE STRUCTURE AND ROADWAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 495 053-30 NFA 1,170 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

NATCHITOCHES LA 495 053-30 LOCAL 130 OTHER / MISCELLANEOUS

Project: H.011425 - BLACK BAYOU PONTOON BR COLLISION REPAIRS Project Manager: Type Impv: REPAIR DAMAGE CAUSED BY MARINE VESSEL COLLISION Remarks: SECRETARY'S EMERGENCY FUND LETTER DATED 7/8/2014 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 384 382-04 STGEN 300 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011652 - LA 92: VERMILION P/L - LA 339 Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 92 213-05 STBONDS 2,235 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

LAFAYETTE LA 92 213-05 STPFLEX 965 OTHER / MISCELLANEOUS

Project: H.011736 - US 190 TREE TRIMMING Project Manager: Type Impv: TREE TRIMMING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE US 190 008-01 STCASH 90 OTHER / MISCELLANEOUS 4-SCHEDULED IN CURRENT FY 14-15

E BATON ROUGE US 190 007-90 STCASH 10 OTHER / MISCELLANEOUS

Project: H.002320 - SULLIVAN RD (WAX - HOOPER) Project Manager: Type Impv: 4 LN DIVIDED CONC HWY RAISED MEDIAN Remarks: 255-30-0014;GREEN LIGHT PROJECT.LET BY CITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 3034 255-30 LOCAL 19,000 OTHER / MISCELLANEOUS 4-SCHEDULED FOR LETTING FY 15-16

E BATON ROUGE LA 3034 255-30 STBONDS 3,000 SUSTAINABILITY NON-INTERSTATE E BATON ROUGE LA 3034 255-30 STPFLEX 3,000 SUSTAINABILITY NON-INTERSTATE

Project: H.008145 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2C Project Manager: Type Impv: ROUTE LA 1 RELOCATION Remarks: 829-32-0010;NEW BRIDGE.NEW ALIGNMENT; AC-ING WITH STBON Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 829-32 STBONDS 40,000 OTHER / MISCELLANEOUS 4-SCHEDULED FOR LETTING FY 15-16

LAFOURCHE LA 1 829-32 LOCAL 6,600 OTHER / MISCELLANEOUS

Page 65 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: H.009316 - LA 1016-2:ELEVATION AND DRAINAGE UPGRADE Project Manager: Type Impv: RAISE ELEVATIOIIN AND UPGRADE DRAINAGE PIPES Remarks: 804-38-0010 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASSUMPTION LA 1016-2 804-38 FEMA 664 OTHER / MISCELLANEOUS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011217 - DEMOLISH NINE MILE TURNAROUND Project Manager: Type Impv: PROVIDE FOR THE DEMOLITION OF THE NINE MILE TURNAROUND. Remarks: DIR NUMBER LA-2012-1-051-010 USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 ER 1,073 OTHER / MISCELLANEOUS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011239 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2E Project Manager: GISCLAIR, GARY Type Impv: CONSTRUCT LEEVILLE MAIN LINE INTERSECTION Remarks: AC-ING WITH STBONDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 829-32 STBONDS 8,584 OTHER / MISCELLANEOUS 4-SCHEDULED FOR LETTING FY 15-16

LAFOURCHE LA 1 829-32 LOCAL 1,416 OTHER / MISCELLANEOUS

Project: H.011247 - UPDATES TO GIS HISTORIC SITES DATABASE Project Manager: Type Impv: UPDATE THE STATE GIS DATABASE FOR HISTORIC SITES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 OTHER / MISCELLANEOUS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.000762 - JCT LA 28 - JCT LA 3037 Project Manager: REEVES, JUSTIN Type Impv: WIDEN TO 4 LANES Remarks: 022-06-0038; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CATAHOULA US 84 022-06 NFI 6,000 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

CATAHOULA US 84 022-06 NFI 6,000 CAPACITY

Project: H.000770 - JCT LA 565 - JCT LA 129 Project Manager: ROUSSELL, CHRIS Type Impv: WIDEN TO 4 LANES Remarks: 022-07-0053; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA US 84 022-07 0 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

Project: H.000771 - LA 129 - US 65 (FERRIDAY) Project Manager: ROUSSELL, CHRIS Type Impv: WIDEN TO 4 LANES Remarks: 022-07-0054; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA US 84 022-07 NFI 3,000 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

Project: H.001524 - OAKDALE-LA 106 Project Manager: Type Impv: RECONSTRUCT Remarks: 066-05-0016;INCL204-01-0010 LM 0-0.38 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage EVANGELINE LA 10 066-06 NFI 14,500 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

ALLEN LA 10 066-05 0 OTHER / MISCELLANEOUS

EVANGELINE LA 106 204-01 0 OTHER / MISCELLANEOUS

Page 66 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: H.001618 - JCT LA 173 - MIDDLE SCHOOL Project Manager: Type Impv: RECONST.W/GEOMETRIC IMP NEED STAGE0 Remarks: 078-02-0019;NEED FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 538 078-02 NFI 5,604 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

CADDO LA 173 094-01 0 OTHER / MISCELLANEOUS

Project: H.001809 - AJAX - I-49 Project Manager: Type Impv: CURVE REALIGNMENT Remarks: 112-06-0008;PROJECT TO BE RE-SCOPED Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 174 112-06 STPFLEX 2,410 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

Project: H.002426 - SUNSHINE BRIDGE - I-10 Project Manager: Type Impv: CLEARING AND GRUBBING Remarks: 426-02-0052;(CONST)426-02-42.426-03-04.NO FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JAMES LA 70 426-02 NFI 0 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

ASCENSION LA 22 266-01 NFI 0 OTHER / MISCELLANEOUS

Project: H.004359 - HICKORY (LA 48 - MOUNES) Project Manager: STANDIGE, FRANK H. Type Impv: RELOCATION AND 4-LANING Remarks: 826-44-0027; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 3154 826-44 STBONDS 7,296 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

JEFFERSON LA 3154 826-44 OTHER 2,673 OTHER / MISCELLANEOUS

Project: H.007973 - OLD HAMMOND (BLVD DE PROV-MILL) Project Manager: Type Impv: CLEARING AND GRUBBING Remarks: 817-09-0040; GREEN LIGHT PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 426 817-09 NFI 0 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

Project: H.007974 - OLD HAMMOND HWY(MILLERVILLE-O'NEAL) Project Manager: Type Impv: NEW CONC PAVEMENT Remarks: 817-09-0042;LET BY CITY. GREEN LIGHT PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 426 817-09 LOCAL 9,681 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

Project: H.009483 - LA HIGHWAY 44 RE-ROUTE Project Manager: Type Impv: ADDING TURN LANES ON LA 3125 AND REALIGNING LA 44 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JAMES LA 3125 426-31 LOCAL 775 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

ST JAMES LA 44 256-05 LOCAL 620 OTHER / MISCELLANEOUS

Project: H.010446 - EMERGENCY BR REPLACE: LA 1077-ST TAMMANY Project Manager: MCCASKILL, LACEY Type Impv: CONT TO FURNISH ALL MATERIALS AND LABOR TO RECONSTRUCT BRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 1077 852-13 STCASH 200 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

Page 67 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: H.010469 - EMERG CONT F/REPAIR TO ELMER'S ISLAND RD Project Manager: Type Impv: FURNISH, PLACE, AND COMPACT AGGREGATE SURFACE COURSE MARemarks: LETTER BID 9/17/2012 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE 000-29 STCASH 300 OTHER / MISCELLANEOUS 2-WAITING FOR FUNDING

Project: H.001344 - JCT LA 25 - JCT US 190 BUS Project Manager: Type Impv: WIDENING Remarks: 059-30-0008; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 190 059-30 NFI 58,000 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.001606 - JEFFERSON HWY @ STUMBERG LN EXT Project Manager: Type Impv: INTERSECTION IMPROVEMENTS Remarks: 077-04-0025;GREEN LIGHT PROJECT (AA)LET BY CITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 73 077-04 LOCAL 11,000 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.001790 - INT. PAPER PLANT - LA 1 Project Manager: Type Impv: RECON W/GEOMETRIC IMPROVEMENTS Remarks: 105-02-0017;$.5 AVAIL. (ORIGINATED BY DED) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 509 105-02 NFI 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

RED RIVER LA 509 105-03 0 OTHER / MISCELLANEOUS

Project: H.002297 - MAGNOLIA BRIDGE RD - INDIAN MOUND Project Manager: Type Impv: RECON W/GEOMETRIC IMPROVEMENTS Remarks: 254-02-0040;SAFETY TRANSFER FUNDS-4 MILLION MAX Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 37 254-02 NFI 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

E BATON ROUGE LA 37 254-03 0 OTHER / MISCELLANEOUS

Project: H.002313 - HOOPER RD.(BLKWATER BAYOU - DEVALL) Project Manager: Type Impv: WIDEN TO 5 LANES Remarks: 255-02-0027;HOLD - SEWER & FUNDING PROBLEM Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 408 255-02 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.002317 - LA 408: HOOPER RD (JOOR RD-SULLIVAN RD) Project Manager: Type Impv: NEW 4 LANE DIVIDED CONCRETE HIGHWAY WITH RAISED MEDIAN Remarks: GREEN LIGHT PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 408 255-02 LOCAL 10,928 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.002361 - ESSEN LANE AT I-10 Project Manager: Type Impv: CONCRETE NEW PAVEMENT Remarks: 258-32-0022;GREEN LIGHT PROJ(G) LET BY CITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 3064 258-32 LOCAL 2,400 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Page 68 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: H.002424 - SUNSHINE BRIDGE - I-10 Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 426-02-0042;(C&G)426-02-52.426-03-05.NO FUNDING Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 22 266-01 NFI 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

ST JAMES LA 70 426-02 NFI 0 OTHER / MISCELLANEOUS

ASCENSION LA 70 426-03 NFI 0 OTHER / MISCELLANEOUS

Project: H.002868 - I-49 S:AMB CAFFERY/US90 INTERCHANGE Project Manager: Type Impv: NEW INTERCHANGE Remarks: 424-02-0090;ENG DEMO. RW/UTL S9$1.2M AVAILABLE.NFI FOR C Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 90 424-02 NFI 57,970 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.003790 - LA 930: CAUSEY RD TO LA 42 Project Manager: Type Impv: WIDEN LA 930 & ADD OPEN DITCHES Remarks: 803-14-0005;STATE BONDS BEING REQUESTED Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 930 803-14 STBONDS 5,300 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.003859 - I-20 (LA 3 - I-220 E.) Project Manager: Type Impv: STATE FUNDS FOR STUDY Remarks: 700-08-0134;FEASIBILITY STUDY (STAGE 0) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.004738 - I-610 - TWIN SPANS AND I-10 @ RR Project Manager: Type Impv: STATE FUNDS FOR STUDY Remarks: 700-36-0198;(STAGE 0.PHASE1) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.004937 - US 11 - US 190 Project Manager: Type Impv: 2 LANE RECONSTRUCTION Remarks: 852-21-0030; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 433 852-21 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.005039 - LA 3040 (REPLACE TUNNEL) Project Manager: Type Impv: STATE FUND FOR STUDY Remarks: 700-55-0118;FEASIBILITY STUDY STAGE 0 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE 000-55 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.005083 - VERNON PARISH TRANSPORTATION PLAN Project Manager: Type Impv: INCLUDES US 171 IMPROVEMENT STUDY Remarks: 700-58-0140; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON 000-58 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.005121 - LA 1 - I-10 CONNECTOR Project Manager: Type Impv: FEDERAL EARMARK FOR STUDY Remarks: 700-61-0113;STAGE 0 COMPLETED Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 STGEN 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Page 69 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: H.005403 - LA408(HOOPER RD EXT)LA37-LA16 Project Manager: Type Impv: EXTENSION OF HOOPER ROAD FROM LA 37 TO LA 16 Remarks: 700-99-0527;GEN.OBLIGATION BOND(PR2=$100K & PR5=$900K) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 NFI 108,100 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.008157 - JCT US 80 - JCT LA 150 Project Manager: Type Impv: RECON W/GEOMETRIC IMPROVEMENTS Remarks: 831-12-0008;$4.0 M SAFETY TRANSFER FUNDS MAX Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 150 831-07 SATRANS 4,000 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

LINCOLN LA 818 831-12 NFI 5,000 OTHER / MISCELLANEOUS

Project: H.008159 - JCT US 80 - JCT LA 150 Project Manager: Type Impv: RECON W/GEOMETRIC IMPROVEMENTS Remarks: 831-12-0008;$4.0 M SAFETY TRANSFER FUNDS MAX Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 818 831-12 SATRANS 350 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

LINCOLN LA 818 831-12 NFI 5,000 OTHER / MISCELLANEOUS

LINCOLN LA 150 831-07 0 OTHER / MISCELLANEOUS

Project: H.008277 - FT. BUHLOW BR (US 71/US 165) Project Manager: Type Impv: RED RIVER BRIDGE Remarks: 840-43-0014;PHASE 3 OF FORT BUHLOW RED RIVER BR Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 71 840-43 NFI 32,500 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.008793 - FRANKLIN FARMS MEGA SITE Project Manager: Type Impv: INTERCHANGE IMPROV., NEW ROADWAY, ROADWAY WIDENING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 183 185-01 NFI 95,000 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.009725 - LA 3034: SULLIVAN RD @ WAX RD Project Manager: JESCLARD, TREY Type Impv: PERMIT PROJECT WITH CEA Remarks: 255-30-0012 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 3034 255-30 LOCAL 4,500 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.010081 - LA 156 IMPROVEMENTS (CALVIN TO US 167) Project Manager: Type Impv: FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN LA 156 092-03 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.010473 - ISAAC, I-10, FLOOD PROTECT ST. TAMMANY Project Manager: Type Impv: PROVIDE TEMPORARY SAND BERM LEVEE FOR PROTECTION OF I-10Remarks: SECRETARY EMERGENCY LETTER DATED 9/2/2012 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-10 450-18 STGEN 130 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Page 70 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: H.010590 - EMERG ELEC REP&DEBR REM OSTRICA LK&CANAL Project Manager: Type Impv: EMERGENCY ELECTRICAL REPAIR AND DEBRIS REMOVAL Remarks: SECRETARY EMERGENCY LETTER 9/5/2012 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage PLAQUEMINES 000-38 STGEN 400 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.011003 - BR MPO TRAVEL DEMAND MANAGEMENT 2013 Project Manager: Type Impv: PROMOTE COMMUTER CARPOOLING AND VANPOOLING/FLEX TIME Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 62 000-90 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

DISTRICTWIDE 61 000-96 0 OTHER / MISCELLANEOUS

Project: H.011004 - ALEX MPO TRAVEL DEMAND MANAGEMENT 2013 Project Manager: Type Impv: PROMOTE COMMUTER CARPOOLING AND VANPOOLING/FLEX TIME Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.011005 - HOUMA MPO TRAVEL DEMAND MANAGEMENT 2013 Project Manager: Type Impv: PROMOTE COMMUTER CARPOOLING AND VANPOOLING/FLEX TIME Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE 000-55 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.011207 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2A Project Manager: GISCLAIR, GARY Type Impv: CONSTRUCT RELOCATED LA 1 ON ELEVATED STRUCTURE Remarks: SEE NOTES FOR FUNDING INFO Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 829-32 NFI 43,400 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.011208 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2B Project Manager: GISCLAIR, GARY Type Impv: ELEVATED RELOCATED LA 1 -LEEVILLE TO GOLDEN MEADOW LEVEERemarks: SEE NOTES FOR FUNDING INFO Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 829-32 NFI 230,000 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.011209 - LA 1: LEEVILLE TO GOLDEN MEADOW PHASE 2D Project Manager: GISCLAIR, GARY Type Impv: NEW TOLL FACILITY FOR LA 1 SOUTHBOUND AND APPROACH. Remarks: SEE NOTES FOR FUNDING INFO Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 829-32 NFI 10,000 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

Project: H.011289 - LA 70: DETOUR ROAD Project Manager: Type Impv: CONSTRUCTION OF A DETOUR ROUTE FOR LA 70 IF NECESSARY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASSUMPTION LA 70 232-01 STPFLEX 15,280 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

ASSUMPTION LA 69 406-01 STPFLEX 1,063 OTHER / MISCELLANEOUS

Page 71 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: H.011358 - US 190 (VINE STREET) RECONSTRUCTION Project Manager: Type Impv: STAGE 0/FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY US 190 012-12 0 OTHER / MISCELLANEOUS 1-PLANNING/ENVIRONMENTAL

ST LANDRY US 190 012-13 0 OTHER / MISCELLANEOUS

Project: H.011029 - LA 559: REPLACE DUTY FERRY WITH BRIDGE Project Manager: Type Impv: FEASIBILITY STUDY TO REPLACE DUTY FERRY WITH A BRIDGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CATAHOULA LA 559 813-29 STPFLEX 18,000 OTHER / MISCELLANEOUS 0-FEASIBILITY/SCOPING

CATAHOULA LA 559 346-01 STPFLEX 18,000 OTHER / MISCELLANEOUS

Project: L.000009 - MISC BOND PROJECTS Project Manager: Type Impv: AS APPROVED BY LEGISLATURE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STBONDS 1,000 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000014 - MISC ECONOMIC DEVELOPMENT INITIATIVES Project Manager: Type Impv: IN CONJUNCTION WITH DED Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STCASH 500 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

- STBONDS 500 OTHER / MISCELLANEOUS

Project: L.000019 - STATE PARK ROADS Project Manager: Type Impv: OVERLAY/REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STBONDS 100 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000021 - MISC FEDERAL PROJECTS/PROGRAMS Project Manager: Type Impv: FEDERAL LANDS HIGHWAYS, ETC. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - FLH 500 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000025 - TOLL FUNDED PROJECTS Project Manager: Type Impv: ORLEANS AND JEFFERSON PARISHES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - TOLLS 1,000 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000026 - WETLAND MITIGATION BANK Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STCASH 1,000 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

- TIME 1,000 OTHER / MISCELLANEOUS

Page 72 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 OTHER / MISCELLANEOUS - Project: L.000027 - EMERGENCY RELIEF PROVIDED BY CONGRESS Project Manager: Type Impv: EMERGENCY RELIEF Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - ER 100 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000028 - MAINTENANCE MATERIALS Project Manager: Type Impv: HOT MIX, PIPE, BRIDGE MATERIAL, ETC Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STCASH 5,000 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000039 - ACCELERATED LOADING FACILITY Project Manager: Type Impv: CONSTRUCT TEST SECTIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 50 OTHER / MISCELLANEOUS STAGES 4, 3, 2, 1, 0

Project: L.000038 - PLANNING, TRAINING AND RESEARCH Project Manager: Type Impv: HANDLED THROUGH OPERATING BUDGET Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - SPR MAND 7,000 OTHER / MISCELLANEOUS STAGES 2, 1, 0

- SPR OPT 7,000 OTHER / MISCELLANEOUS

Project: L.000023 - SCOPING AND ENVIRONMENTAL STUDIES Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 400 OTHER / MISCELLANEOUS STAGES 1, 0

- STPFLEX 300 OTHER / MISCELLANEOUS

- STCASH 300 OTHER / MISCELLANEOUS

Page 73 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RAILROADS - Project: H.009892 - LDRR (NEW IBERIA) US 90 FR Project Manager: Type Impv: NEW XING PER DISTRICT 03 & NEW IBERIA Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA US 90 424-04 STPFLEX 340 RAILROADS 4-SCHEDULED IN CURRENT FY 14-15

IBERIA US 90 424-04 LOCAL 10 RAILROADS

Project: H.011188 - RIVERTON CAMP RD: UP RR XING (CALDWELL) Project Manager: Type Impv: THIS PROJECT PROPOSES TO INSTALL FLASHING LIGHTS AND GATERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL 000-11 RAIL PD 353 RAILROADS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011680 - LA 147: LAS RR XING (NORTH HODGE) Project Manager: Type Impv: REPLACE RAILROAD CROSSING SURFACE. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON LA 147 043-01 RAIL HE 222 RAILROADS 4-SCHEDULED IN CURRENT FY 14-15

JACKSON LA 147 043-01 LOCAL 178 RAILROADS

Project: H.009884 - NOGC (STATEWIDE) Project Manager: Type Impv: RELOCATING LED CROSSBUCK ASSEMBLIES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 RAIL HE 250 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010069 - UP (W. BATON ROUGE) WINTERVILLE RD. Project Manager: Type Impv: RAILROAD SIGNALIZATION Remarks: 714-61-0006 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 RAIL PD 300 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010645 - IC(KENTWOOD) LA 38 RR X-ING IN KENTWOOD Project Manager: Type Impv: RAILROAD SIGNALS AND SURFACE WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 38 263-04 RAIL HE 500 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011109 - US 61: IC RR XING (BATON ROUGE) Project Manager: LUKE, SHAWN Type Impv: INSTALL NEW CROSSING SURFACE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61 007-90 RAIL HE 500 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011113 - LA 1064: IC RR XING (TANGIPAHOA) Project Manager: LUKE, SHAWN Type Impv: REPLACE THE SURFACING OF THE CROSSING. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 1064 853-09 RAIL HE 83 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

TANGIPAHOA LA 1064 853-09 LOCAL 67 RAILROADS

Page 74 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RAILROADS - Project: H.011135 - E. PERDUE: IC RR XING (BATON ROUGE) Project Manager: LUKE, SHAWN Type Impv: INSTALLATION OF ACTIVE WARNING DEVICES. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 RAIL PD 300 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011291 - DALE, LA 677 &344:LDRR XINGS(NEW IBERIA) Project Manager: Type Impv: RR ACTIVE WARNING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 344 823-14 RAIL PD 250 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

IBERIA LA 677 823-15 RAIL PD 150 RAILROADS

IBERIA 000-23 RAIL PD 100 RAILROADS

Project: H.011293 - LA 126: UP RR XING (GRAYSON) Project Manager: Type Impv: RR SIGNAL PREEMPTION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL LA 126 091-09 RAIL PD 50 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011296 - LCHD SEVERAL RR XINGS (CALCASIEU) Project Manager: Type Impv: INSTALL NEW CBAS AT LCHD PASSIVE PUBLIC CROSSINGS. Remarks: 714-10-0117 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 RAIL PD 190 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

CALCASIEU LA 385 195-04 RAIL PD 10 RAILROADS

Project: H.011315 - IC SEVERAL RR XINGS (EBR & E. FELICIANA) Project Manager: SHREWSBERRY,BILL Type Impv: UPGRADE ACTIVE WARNING DEVICES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E FELICIANA LA 412 819-11 RAIL PD 500 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

E FELICIANA LA 964 019-31 RAIL PD 200 RAILROADS

E FELICIANA LA 68 252-02 RAIL PD 200 RAILROADS

E FELICIANA US 61 019-03 RAIL PD 150 RAILROADS

E BATON ROUGE 000-17 RAIL PD 150 RAILROADS

E BATON ROUGE LA 64 253-02 RAIL PD 200 RAILROADS

Project: H.011320 - SIDNEY RICHARD RD: BNSF RR XING (ACADIA) Project Manager: Type Impv: INSTALL ACTIVE WARNING DEVICES. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA 000-01 RAIL PD 300 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011325 - IC SEVERAL RR XINGS (STATEWIDE) Project Manager: SHREWSBERRY,BILL Type Impv: INSTALL CBAS AT IC'S PASSIVE PUBLIC CROSSINGS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 RAIL PD 250 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Page 75 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RAILROADS - Project: H.011762 - LA 449: IC RR XING (WALKER) Project Manager: Type Impv: INSTALL RR GATES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 449 271-01 STPFLEX 225 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011786 - RAILROAD ST: BNSF RR XING (CADE) Project Manager: Type Impv: INSTALL F/L'S, GATES AND BELLS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN 000-50 RAIL PD 480 RAILROADS 4-SCHEDULED FOR LETTING FY 15-16

ST MARTIN 000-50 LOCAL 120 RAILROADS

Project: H.009843 - BNSF (NEW IBERIA) LA 14/CENTER ST. Project Manager: Type Impv: INSTALLING NEW F/L'S AND GATES Remarks: 055-07-0077 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 14 055-07 RAIL PD 280 RAILROADS 3-DESIGN/DEVELOPMENT

IBERIA LA 14 055-07 LOCAL 70 RAILROADS

Project: H.009856 - BNSF (NEW IBERIA) JULIA ST. Project Manager: Type Impv: INSTALL FLASHING LIGHTS & GATES Remarks: 714-23-0100 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 RAIL PD 280 RAILROADS 3-DESIGN/DEVELOPMENT

IBERIA 000-23 LOCAL 70 RAILROADS

Project: H.009857 - BNSF (NEW IBERIA) IBERIA ST. Project Manager: Type Impv: INSTALL FLASHING LIGHTS & GATES Remarks: 714-23-0101 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 RAIL PD 280 RAILROADS 3-DESIGN/DEVELOPMENT

IBERIA 000-23 LOCAL 70 RAILROADS

Project: H.009860 - BNSF (NEW IBERIA) RR XINGS ALONG THE BNS Project Manager: Type Impv: INSTALL RAILROAD CROSSING FLASHING LIGHTS & GATES Remarks: 714-23-0102 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 RAIL PD 280 RAILROADS 3-DESIGN/DEVELOPMENT

IBERIA 000-23 LOCAL 70 RAILROADS

Project: H.009861 - BNSF (NEW IBERIA) LA 14/CENTER/FRENCH ST Project Manager: Type Impv: TRACK WORK FROM LA 14 TO FRENCH ST. (RAIL HE) Remarks: 714-23-0105 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 RAIL HE 889 RAILROADS 3-DESIGN/DEVELOPMENT

IBERIA 000-23 LOCAL 311 RAILROADS

Project: H.009862 - BNSF (NEW IBERIA) CAROLINE ST. Project Manager: Type Impv: INSTALL RAILROAD CROSSING FLASHING LIGHTS & GATES Remarks: 714-23-0108 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 RAIL PD 215 RAILROADS 3-DESIGN/DEVELOPMENT

Page 76 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RAILROADS - Project: H.009871 - KCS(SIMSBORO) WOODLAND DR. Project Manager: Type Impv: INSTALL F/L'S AND GATES Remarks: 714-31-0110 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN 000-31 RAIL PD 300 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.009891 - BNSF (NEW IBERIA) WEEKS ST. Project Manager: Type Impv: INSTALL F/L'S AND GATES Remarks: 714-23-0099 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 RAIL PD 280 RAILROADS 3-DESIGN/DEVELOPMENT

IBERIA 000-23 LOCAL 70 RAILROADS

Project: H.010074 - UP (DONALDSONVILLE) LA 3089 SERVICE RD. Project Manager: Type Impv: ROAD WORK AROUND CROSSING TO MAKE SAFER Remarks: 426-01-0026 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 3089 426-01 RAIL HE 250 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.010075 - UP (ADDIS) SEVERAL RR-X-INGS Project Manager: Type Impv: RAILROAD SIGNALIZATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 RAIL PD 1,200 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.010076 - IC (RESERVE) W. 19TH ST. Project Manager: Type Impv: RAILROAD SIGNALIZATION Remarks: 714-48-0001 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN 000-48 RAIL PD 300 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.010696 - BROWN & GANDY: KCS RR XINGS (SABINE) Project Manager: Type Impv: INSTALL F/L'S & GATES AT BROWN AND GANDY XINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE 000-43 RAIL PD 600 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.010698 - RIVERBARGE ST: UP RR XING (MONROE) Project Manager: Type Impv: INSTALL F/L'S & GATES AT UP RIVERBARGE ST. CROSSING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 RAIL PD 300 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.010702 - IC SEVERAL RR XINGS (HAMMOND) Project Manager: Type Impv: INSTALL F/L'S & GATES AT SEVERAL IC CROSSINGS IN HAMMOND Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA 000-53 RAIL PD 600 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.010703 - IC SEVERAL RR SPUR XINGS (HAMMOND) Project Manager: Type Impv: INSTALL F/L'S AT LA 443 & CBA'S AT SEVERAL OTHER SPUR XINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 443 853-27 RAIL PD 300 RAILROADS 3-DESIGN/DEVELOPMENT

TANGIPAHOA 000-53 RAIL PD 100 RAILROADS

Page 77 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RAILROADS - Project: H.011108 - NS SEVERAL RR XINGS (NEW ORLEANS) Project Manager: SHREWSBERRY,BILL Type Impv: RAIL/HIGHWAY CROSSING WARNING IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 RAIL PD 1,000 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.011112 - LA 1: UP RR XING (CADDO) Project Manager: LUKE, SHAWN Type Impv: UPGRADE RR WARNING DEVICES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 1 053-08 RAIL PD 50 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.011144 - ALM SEVERAL RR XINGS (OUACH & MOREHOUSE) Project Manager: SHREWSBERRY,BILL Type Impv: INSTALL CROSSBUCK ASSEMBLIES AT ALM'S PASSIVE PUBLIC XING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 RAIL PD 100 RAILROADS 3-DESIGN/DEVELOPMENT

MOREHOUSE 000-34 RAIL PD 100 RAILROADS

Project: H.011306 - ROBBINS RD: UP RR XING (FOREST HILL) Project Manager: Type Impv: INSTALL FLASHING LIGHTS, GATES & BELLS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 RAIL PD 300 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.011706 - BNSF SEVERAL RR XINGS (BALDWIN) Project Manager: Type Impv: NEW ROAD CONSTRUCTION TO CLOSE THREE BNSF & LDRR CROSSINRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY 000-51 DEMO 585 RAILROADS 3-DESIGN/DEVELOPMENT

ST MARY 000-51 RAIL HE 452 RAILROADS

ST MARY 000-51 LOCAL 63 RAILROADS

Project: H.011723 - COTTON & SILO: BNSF RR XINGS (ST MARY) Project Manager: Type Impv: NEW ROAD CONSTRUCTION, RR CROSSING UPGRADE & RR CLOSURERemarks: 714-51-0010 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY 000-51 RAIL HE 350 RAILROADS 3-DESIGN/DEVELOPMENT

Project: H.008251 - LA456:RDWY CLOSURE@UPRR CROSSING (MEEKER Project Manager: Type Impv: RDWY CLOSURE@UPRR CROSSING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 456 840-07 RAIL HE 34 RAILROADS 2-WAITING FOR FUNDING

Project: H.011133 - LA 1: UP RR XING (WEST BATON ROUGE) Project Manager: LUKE, SHAWN Type Impv: REMOVE CROSSING Remarks: H.011133 MUST LET BEFORE H.009288 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 1 050-07 RAIL HE 300 RAILROADS 1-PLANNING/ENVIRONMENTAL

Page 78 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RAILROADS - Project: H.011323 - NIGHTHAWK/SPAN TRL:BNSF RR XINGS(ACADIA) Project Manager: Type Impv: CONSTRUCT A NEW RR XING BETWEEN TWO XINGS THAT WILL CLOSRemarks: 714-01-0120 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA 000-01 RAIL HE 500 RAILROADS 1-PLANNING/ENVIRONMENTAL

Project: L.000022 - RAILROAD CROSSING IMPROVEMENTS Project Manager: Type Impv: FEDERAL RAILROAD CROSSING IMPROVEMENTS PROGRAM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - RAIL HE 3,000 RAILROADS STAGES 4, 3, 2, 1, 0

- RAIL PD 3,000 RAILROADS

- STPFLEX 2,000 RAILROADS

- STCASH 200 RAILROADS

Page 79 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RAILROADS - GRADE SEPARATION Project: H.002960 - LA 3213:GRAMERCY BRIDGE OVER UP RAILROAD Project Manager: Type Impv: GRADE SEPARATE EXISTING AT GRADE CROSSING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 3213 434-01 STPFLEX 20,000 RAILROADS 3-DESIGN/DEVELOPMENT GRADE SEPARATION

Project: H.009288 - LA 1:NEW RR BRIDGE@DOW SPUR XING (WBR) Project Manager: Type Impv: GRADE SEPARATE EXISTING AT-GRADE CROSSING Remarks: H.011133 MUST LET BEFORE H.009288 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 1 050-07 NHPP 20,000 RAILROADS 3-DESIGN/DEVELOPMENT GRADE SEPARATION

Project: H.009520 - LA 3168:NEW BRIDGE@BNSF-US 90(LAFAYETTE) Project Manager: Type Impv: GRADE SEPARATE EXISTING AT-GRADE CROSSING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 3168 433-01 STPFLEX 24,700 RAILROADS 1-PLANNING/ENVIRONMENTAL GRADE SEPARATION

Project: H.009521 - LA 397: NEW BRIDGE AT UPRR Project Manager: Type Impv: GRADE SEPARATE EXISTING AT-GRADE CROSSING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 397 193-31 STPFLEX 10,200 RAILROADS 1-PLANNING/ENVIRONMENTAL GRADE SEPARATION

Project: H.009522 - LA 3105:UNDERPASS@KCS S OF I-20(BOSSIER) Project Manager: Type Impv: GRADE SEPARATE EXISTING AT-GRADE CROSSING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 3105 808-07 STPFLEX 9,100 RAILROADS 1-PLANNING/ENVIRONMENTAL GRADE SEPARATION BOSSIER I-20 451-02 NHPP 300 RAILROADS GRADE SEPARATION

Page 80 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RECREATIONAL TRAILS PROGRAM - Project: H.009354 - BROAD STREET CORRIDOR BIKEWAY Project Manager: Type Impv: CONSTRUCTION OF BIKE LANES, A MULTI-USE PATH AND CROSSINGRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 RTP 89 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 LOCAL 11 RECREATIONAL TRAILS PROGRAM

Project: H.009359 - BONNET CARRE'S SPILLWAY ATV RIDING AREA Project Manager: Type Impv: RESTORATION AND CONSTRUCTION OF A MOTORIZED TRAIL SYSTEMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES 000-45 RTP 199 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010554 - SAINT GABRIEL TRAIL AT THE LEVEE, PH 2 Project Manager: Type Impv: CONSTRUCTION OF A PED-BIKE TRAIL ON THE MISS. RIVER LEVEE. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 RTP 183 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

E BATON ROUGE 000-17 LOCAL 5 RECREATIONAL TRAILS PROGRAM

Project: H.010586 - ST BERNARD P MISSISSIPPI RIVER TRAIL PH3 Project Manager: Type Impv: CONSTRUCTION OF A PED-BIKE TRAIL. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD 000-44 RTP 112 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ST BERNARD 000-44 LOCAL 425 RECREATIONAL TRAILS PROGRAM

Project: H.010593 - BAYOU TECHE PADDLE TRAIL Project Manager: Type Impv: CONSTRUCTION OF A PADDLE AND ATV TRAIL. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY 000-49 RTP 104 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ST LANDRY 000-49 LOCAL 13 RECREATIONAL TRAILS PROGRAM

Project: H.010594 - LOUISIANA TRAIL: GOLDONNA TO CHESTNUT Project Manager: Type Impv: CONSTRUCTION OF A MULTI-USE TRAIL. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES 000-35 RTP 199 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010595 - LOUISIANA TRAIL - CASTOR TO JAMESTOWN Project Manager: Type Impv: CONSTRUCTION OF A MULTI-USE TRAIL. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE 000-07 RTP 199 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010828 - PARC DES PONTS TRAILHEAD Project Manager: Type Impv: CONSTRUCTION OF MULTI-USE TRAILHEAD. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN 000-50 RTP 200 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

Page 81 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RECREATIONAL TRAILS PROGRAM - Project: H.010869 - WARDS CREEK TRAIL - BLUEBONNET EXTENSION Project Manager: Type Impv: CONSTRUCTION OF A PED-BIKE TRAIL ON WARDS CREEK. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 RTP 256 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

E BATON ROUGE 000-17 LOCAL 140 RECREATIONAL TRAILS PROGRAM

Project: H.010870 - -ISHAK BREAUX BRIDGE TRAIL Project Manager: Type Impv: CONSTRUCTION OF A 8.2 PED-BIKE TRAIL. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 RTP 128 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

LAFAYETTE 000-28 LOCAL 12 RECREATIONAL TRAILS PROGRAM

Project: H.010872 - EARHART CORRIDOR BIKEWAY LINKAGE Project Manager: Type Impv: CONSTRUCTION OF 2.3 MILES OF BIKE LANE. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 RTP 146 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ORLEANS 000-36 LOCAL 30 RECREATIONAL TRAILS PROGRAM

Project: H.010875 - WARDS CREEK TRAIL - SIEGEN EXTENSION Project Manager: Type Impv: CONSTRUCTION OF A PED-BIKE TRAIL ON WARDS CREEK. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 RTP 222 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

E BATON ROUGE 000-17 LOCAL 106 RECREATIONAL TRAILS PROGRAM

Project: H.010877 - PHARR ESTATES TRAIL, PHASE 2 Project Manager: Type Impv: CONSTRUCTION OF 850' OF PED-BIKE TRAIL Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY 000-51 RTP 223 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ST MARY 000-51 LOCAL 107 RECREATIONAL TRAILS PROGRAM

Project: H.010878 - ACADIANA HILLS TRAIL Project Manager: Type Impv: CONSTRUCTION OF 900' OF PED-BIKE TRAIL. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 RTP 78 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

LAFAYETTE 000-28 LOCAL 14 RECREATIONAL TRAILS PROGRAM

Project: H.011106 - SOUTH GRAND STREET TRAIL Project Manager: Type Impv: CONST. OF 10' X 1,000' BOARDWALK ALONG THE RIVERFRONT Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 RTP 116 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

OUACHITA 000-37 LOCAL 14 RECREATIONAL TRAILS PROGRAM

Page 82 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 RECREATIONAL TRAILS PROGRAM - Project: H.011115 - PENNINGTON TRAIL SEGMENT Project Manager: Type Impv: CONST. OF 12' X 1480' PED-BIKE TRAIL Remarks: CRT IS THE PROJECT MANAGER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 RTP 116 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

E BATON ROUGE 000-17 LOCAL 397 RECREATIONAL TRAILS PROGRAM

Project: H.011117 - WEST HALL TRAIL Project Manager: Type Impv: CONSTRUCTION OF 1,746' PED-BIKE TRAIL EXTENSION Remarks: CRT IS THE PROJECT MANAGER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 RTP 116 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

ST TAMMANY 000-52 LOCAL 20 RECREATIONAL TRAILS PROGRAM

Project: H.011130 - BOEUF WMA MORENGO SWAMP TRAIL - PHASE 1 Project Manager: Type Impv: RESTORATION OF 4.25 MILES OF MOTORIZED TRAILS IN WMA Remarks: CRT IS THE PROJECT MANAGER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL 000-11 RTP 185 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011145 - LOUISIANA TRAILS RESTORATION PHASE 2 Project Manager: Type Impv: RESTORATION, NON-ROUTINE MAINT & CONS. OF 30 MILES OF TRAILRemarks: CRT IS THE PROJECT MANAGER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES 000-35 RTP 199 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010585 - DOWNTOWN BATON ROUGE GREENWAY PH. 2 Project Manager: Type Impv: CONSTRUCTION OF A PED-BIKE TRAIL. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 RTP 112 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED FOR LETTING FY 15-16

E BATON ROUGE 000-17 LOCAL 13 RECREATIONAL TRAILS PROGRAM

Project: H.010829 - ST. MARY PARISH BAYOU TECHE TRAILHEADS Project Manager: Type Impv: CONSTRUCTION OF MULTI-USE TRAILHEADS. Remarks: NATIONAL RECREATIONAL TRAILS PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY 000-51 RTP 125 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED FOR LETTING FY 15-16

ST MARY 000-51 LOCAL 38 RECREATIONAL TRAILS PROGRAM

Project: H.011118 - ST. BERNARD PARISH MRT TRAILHEADS Project Manager: Type Impv: CONST. OF 1600' OF LEVEE ACCESS RAMPS ALONG MS RIVER TRAIL Remarks: CRT IS THE PROJECT MANAGER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD 000-44 RTP 116 RECREATIONAL TRAILS PROGRAM 4-SCHEDULED FOR LETTING FY 15-16

ST BERNARD 000-44 LOCAL 44 RECREATIONAL TRAILS PROGRAM

Page 83 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ROAD TRANSFER - Project: H.011313 - MOUNCE RD: HOWARD RD TO BLUNT MILL RD Project Manager: MURPHY, MICHAEL Type Impv: ROADWAY REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 3106 870-04 NFA 627 ROAD TRANSFER 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011423 - LA 3159: US 84 - END OF MAINTENANCE Project Manager: Type Impv: STABILIZE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE LA 3159 830-19 NFA 1,706 ROAD TRANSFER 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010901 - LA 1265: FIVE FORKS ROAD REALIGNMENT Project Manager: Type Impv: RECONSTRUCTION WITH GEOMETRIC IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 1265 835-23 NFA 1,900 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011322 - US 61-X: FLORIDA STREET - PHLOX AVENUE Project Manager: Type Impv: PATCH, COLD PLANE, 2" OVERLAY / PATCH PCCP, RESEAL JOINTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61-X 817-20 NHPP 1,500 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011337 - LA 30, LA 73, AND US 61-X REHAB Project Manager: GARY, VERTIE Type Impv: PATCH, COLD PLANE, 2" OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 30 414-01 NHPP 322 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

E BATON ROUGE LA 73 077-05 NHPP 1,743 ROAD TRANSFER

E BATON ROUGE US 61-X 013-04 NHPP 316 ROAD TRANSFER

Project: H.011674 - LA 1263 & LA 3057: PATCH & OVERLAY Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W FELICIANA LA 1263 061-04 STPFLEX 289 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

W FELICIANA LA 1263 061-04 STPFLEX 114 ROAD TRANSFER

W FELICIANA LA 3057 863-13 NFA 279 ROAD TRANSFER

W FELICIANA LA 3057 863-14 NFA 258 ROAD TRANSFER

W FELICIANA LA 1263 061-04 STPFLEX 93 ROAD TRANSFER

Project: H.011694 - LA 1027: E. END W. COLYELL BR - LA 447 Project Manager: Type Impv: PVMNT PATCHING, SUPERPAVE ASPHALTIC CONC., DRAINAGE, STRIPRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 1027 273-03 STPFLEX 450 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

Page 84 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ROAD TRANSFER - Project: H.011703 - LA 64 & LA 1209: CP, OVERLAY, & PCCP Project Manager: Type Impv: COLD PLANE & OVERLAY, ASPHALT AND CONCRETE PAVEMENT PA Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 64 253-02 NHPP 2,240 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

E BATON ROUGE LA 1209 817-30 STPFLEX 325 ROAD TRANSFER

E BATON ROUGE LA 1209 817-43 STPFLEX 525 ROAD TRANSFER

Project: H.011715 - LA 3124: LA 21 - LA 10 Project Manager: Type Impv: PATCHING, COLD PLANING, OVERLAY & STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 3124 030-32 STPFLEX 1,307 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011755 - LA 3111&LA 3171:WASHINGTON ROAD TRANSFER Project Manager: Type Impv: STABILIZE BASE, COLD PLANE, OVERLAY, STRIPING & RELATED WO Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 3111 870-07 NFA 1,100 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

WASHINGTON LA 3171 870-08 NFA 600 ROAD TRANSFER

Project: H.011781 - LA 675 & LA 87 IMP. IN NEW IBERIA (RT) Project Manager: Type Impv: COLD PLANE, PATCH, OVERLAY, AND RELATED WORK. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 675 823-02 NHPP 450 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

IBERIA LA 87 823-26 STPFLEX 350 ROAD TRANSFER

Project: H.011792 - LA 1065 & LA 3260: HAMMOND ROAD TRANSFER Project Manager: Type Impv: COLD PLANE, OVERLAY, PATCHING & STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 3260 853-41 STPFLEX 350 ROAD TRANSFER 4-SCHEDULED FOR LETTING FY 15-16

TANGIPAHOA LA 1065 853-33 NHPP 150 ROAD TRANSFER

Project: H.000212 - LA 182: COUPLET - LA 3195 (EB & WB) Project Manager: Type Impv: ASPHALT OVERLAY, CONCRETE REHABILITATION, AND RELATED WORemarks: 004-04-0025 AND 004-05-0032 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 182 004-04 STPFLEX 1,150 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

IBERIA LA 182 004-04 STPFLEX 563 SUSTAINABILITY NON-INTERSTATE IBERIA LA 182 004-05 STPFLEX 1,713 SUSTAINABILITY NON-INTERSTATE

Project: H.010713 - LA 89: ROUNDABOUT AT FORTUNE RD. Project Manager: Type Impv: RECONSTRUCTION, ADDED CAPACITY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 89-1 216-03 HSIP 1,175 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

Page 85 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ROAD TRANSFER - Project: H.011676 - GULDE ROAD BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT - NO ADDED CAPACITY Remarks: TTF AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE 000-30 FBROFF 347 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

Project: H.011682 - LA 30: SOUTH BOULEVARD - LA 42 Project Manager: Type Impv: PATCH, COLD PLANE, 2" OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 30 414-01 NHPP 1,716 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

Project: H.011684 - LA 327 SPUR: STARING LANE EXTENSION Project Manager: Type Impv: EXTEND 4-LANE DIVIDED ROADWAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 LOCAL 7,350 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

E BATON ROUGE LA 327-S 257-03 LOCAL 2,450 ROAD TRANSFER

Project: H.011748 - LA 731 & LA 731-S IMPROVEMENTS Project Manager: Type Impv: ASPHALT OVERLAY AND RELATED WORK. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 731 828-21 STPFLEX 675 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

LAFAYETTE LA 731-S 828-47 STPFLEX 150 ROAD TRANSFER

Project: H.011767 - BAYOU CRAB ROAD BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASSUMPTION 000-04 FBROFF 431 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

Project: H.011782 - LA 438: LA 21 - OLD COLUMBIA RD Project Manager: Type Impv: IN PLACE STABILIZE, OVERLAY, AGGREGATE SHOULDERS & STRIPINRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 438 859-02 NFA 1,500 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

Project: H.011788 - OAK STREET / OVER POYDRAS BAYOU Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE 000-61 FBROFF 232 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

W BATON ROUGE 000-61 LOCAL 14 OTHER / MISCELLANEOUS

Project: H.011806 - GRACIE LANE BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE 000-24 FBROFF 830 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

Page 86 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ROAD TRANSFER - Project: H.011829 - IMP@LA13 & LA100 & I-10 ACC.RD (CROWLEY) Project Manager: Type Impv: WIDENING, CLASS II BASE, BASE REHAB, AND ASPHALT OVERLAY. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA I-10 450-04 STPFLEX 2,500 ROAD TRANSFER 3-DESIGN/DEVELOPMENT

ACADIA LA 100 211-01 LOCAL 75 ROAD TRANSFER

Project: H.007946 - LA 3102: LA 124 - 4.8 MI NW OF LA 124 Project Manager: Type Impv: PATCH AND OVERLAY Remarks: 813-24-0024; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CATAHOULA LA 3102 813-24 NFA 1,941 ROAD TRANSFER 1-PLANNING/ENVIRONMENTAL

Project: H.010815 - LA 124 EXTENSION Project Manager: Type Impv: CONSTRUCTION ON NEW ALIGNMENT OF AN EXISTING ROUTE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CATAHOULA LA 124 143-03 0 ROAD TRANSFER 1-PLANNING/ENVIRONMENTAL

Project: H.011683 - PICARDY PERKINS CONNECTOR: FEASIBILITY Project Manager: Type Impv: NEW ROADWAY CONNECTOR AND BRIDGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 0 ROAD TRANSFER 1-PLANNING/ENVIRONMENTAL

Project: H.011685 - WILLIS AVENUE EXTENSION: LA 3124 - LA 21 Project Manager: Type Impv: NEW ROADWAY EXTENSION/CONNECTOR. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON 000-59 0 ROAD TRANSFER 1-PLANNING/ENVIRONMENTAL

Project: H.011686 - LA 3066 REPAIR REALIGN: LA 3066-S -LA 75 Project Manager: Type Impv: REPAIR AND REALINGMENT OF LA 3066. A PORTION SLID INTO GIWWRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 3066 230-02 0 ROAD TRANSFER 1-PLANNING/ENVIRONMENTAL

IBERVILLE LA 3066 230-01 0 ROAD TRANSFER

Project: H.011690 - PORT HUDSON PRIDE RD: LA 964-LA 19 STUDY Project Manager: Type Impv: FEASIBILITY STUDY TO WIDEN PORT HUDSON PRIDE RD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 0 ROAD TRANSFER 1-PLANNING/ENVIRONMENTAL

Project: H.011691 - LA 64: ROUNDABOUT AT MCHUGH ROAD Project Manager: Type Impv: MULTI-LANE ROUNDABOUT AT INTERSECTION OF LA 64 AND MCHUGRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 64 253-02 0 ROAD TRANSFER 1-PLANNING/ENVIRONMENTAL

E BATON ROUGE 000-17 0 ROAD TRANSFER

Page 87 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 ROAD TRANSFER - Project: H.011695 - LA 19 WIDENING: LA 64 - SUNSET BLVD Project Manager: Type Impv: WIDENING OF LA 19 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 19 250-01 0 ROAD TRANSFER 1-PLANNING/ENVIRONMENTAL

Project: H.011310 - FORD ST. EXT. & NEW CONNECTION TO LA 408 Project Manager: Type Impv: CONSTRUCTION OF NEW ROADWAY (DETAILS TBD BY STUDY) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 0 ROAD TRANSFER 0-FEASIBILITY/SCOPING

Project: L.000069 - ROAD TRANSFER PROGRAM Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STCASH 1,000 ROAD TRANSFER STAGES 4, 3, 2, 1, 0

- STPFLEX 1,000 ROAD TRANSFER

Page 88 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.000466 - US 190: ROUNDABOUT AT EDEN CHURCH ROAD Project Manager: Type Impv: CONSTRUCT 4-LEGGED SINGLE LANE ROUNDABOUT Remarks: 013-06-0054 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON US 190 013-06 HSIP 2,160 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

LIVINGSTON 000-32 HSIP 240 SAFETY

Project: H.001491 - LA 20 WIDENING: LA 308 - ST PATRICK ST Project Manager: ROGERS, CHRIS Type Impv: COLD PLANE AND OVERLAY Remarks: 065-06-0046; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 20 065-06 STBONDS 2,190 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

LAFOURCHE LA 20 065-06 HSIPPEN 4,878 SAFETY

LAFOURCHE LA 20 065-06 HSIPPEN 182 ROAD TRANSFER

Project: H.008193 - LA 1034 - US 190 Project Manager: Type Impv: COLD PLANE. PATCH AND OLAY Remarks: 832-32-0015 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 3002 832-32 HSIP 1,300 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

LIVINGSTON LA 3002 832-32 NHPP 774 SUSTAINABILITY NON-INTERSTATE

Project: H.010777 - US 71: TURN LANES FOR LEE ST & RANDOM DR Project Manager: Type Impv: CONSTRUCTION OF POSITIVE OFFSET LEFT TURN LANE ON US 71 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 71 008-09 HSIP 385 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

RAPIDES US 71 008-30 HSIP 125 SAFETY

Project: H.011292 - ER REPLACEMENT RPMS - I-49 & US 167 Project Manager: Type Impv: REPLACEMENT OF RAISED PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES I-49 455-05 SATRANS 135 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

RAPIDES US 167 023-01 SATRANS 19 SAFETY

AVOYELLES I-49 455-04 SATRANS 47 SAFETY

Project: H.011675 - I-20: DIST 04 CABLE BARRIER SPARE PARTS Project Manager: Type Impv: PROVIDE SPARE PARTS FOR MAINTAINING CABLE BARRIER. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-20 451-01 SATRANS 43 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

BOSSIER I-20 451-02 SATRANS 43 SAFETY

WEBSTER I-20 451-03 SATRANS 43 SAFETY

BIENVILLE I-20 451-04 SATRANS 43 SAFETY

Project: H.011757 - I-10 (CONSTITUTION/BUNKER HILL): CURVE Project Manager: Type Impv: HIGH FRICTION SURFACE COURSE, CENTER-LINE RUMBLE STRIPES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-10 450-10 SATRANS 130 SAFETY 4-SCHEDULED IN CURRENT FY 14-15

Page 89 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.002163 - ROUNDABOUT ON LA 342 AT LA 724 Project Manager: Type Impv: ROUNDABOUT Remarks: 218-01-0019;PRIORITY 3 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 342 218-01 HSIP 1,595 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

LAFAYETTE LA 724 218-30 HSIP 367 SAFETY

Project: H.002780 - LA 308 CURVE IMPROVEMENT Project Manager: Type Impv: STRAIGHTEN CURVE IN ROADWAY Remarks: 407-04-0043;407-04-0044 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 308 407-04 SATRANS 2,073 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.009012 - WIDEN INTERSECTIONS AT LA 67 & LA 10 Project Manager: Type Impv: SAFETY - WIDEN INTERSECTION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E FELICIANA LA 67 060-03 HSIP 125 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

E FELICIANA LA 67 060-04 HSIP 125 SAFETY

E FELICIANA LA 10 061-05 HSIP 50 SAFETY

Project: H.009475 - LA 538: ROUNDABOUT AT RAVENDALE Project Manager: Type Impv: INSTALL SINGLE LANE ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 538 078-02 HSIP 1,500 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.009956 - LA 44: TURN LANES AND MEDIANS Project Manager: Type Impv: INTERSECTION IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 44 265-02 HSIP 5,429 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010026 - LA 431: REALIGN CURVE, C/L RUMBLE STRIPS Project Manager: Type Impv: REALIGN CURVE, CENTER LINE RUMBLE STRIP, RESTRIPE ROAD. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 431 267-02 SATRANS 3,900 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010178 - LA 120: CURVE REALIGNMENT Project Manager: Type Impv: REALIGNMENT OF LA 120 TO ELIMINATE SHARP REVERSE CURVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 120 042-05 HSIP 1,572 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010197 - US 171: J-TURN @ N. PERKINS FERRY RD. Project Manager: Type Impv: INSTALL TURN LANES (RIGHT, LEFT AND J-TURN) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU US 171 024-02 HSIP 750 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Page 90 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.010202 - I-20: EXIT LANE EXTENSION (EXITS 3 & 5) Project Manager: Type Impv: EXTEND EXIT LANES FOR DECELLERATION. PCC PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-20 451-01 HSIP 1,127 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010212 - LA 175: IMPROVEMENT BTWN US 84 & LA 509 Project Manager: Type Impv: LENGTHEN TURN LANE, ADD TURN LANE AND MINOR WIDENING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 175 035-04 HSIP 900 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010268 - US 90: CURVE IMPROVEMENTS Project Manager: Type Impv: INCREASE VERTICAL GRADE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY US 90 424-05 HSIP 604 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

ASSUMPTION US 90 424-06 HSIP 498 SAFETY

Project: H.010275 - LA 792: CURVE IMPROVEMENT Project Manager: Type Impv: REALIGN CURVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE LA 792 293-02 HSIP 740 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010287 - LA 3249: ROUNDABOUT @ I-20/WELL RD. Project Manager: Type Impv: ROUNDABOUT AT I-20/WELL RD. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 3249 837-19 HSIP 1,400 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010289 - LA 22: ROUNDABOUT DUNSON/RIDGEDELL RDS. Project Manager: Type Impv: CONSTRUCT ROUNDABOUT @ LA 22/DUNSON/RIDGEDELL Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 22 261-04 HSIP 1,000 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010680 - I-10: CABLE BARRIER IN WBR & IBERVILLE Project Manager: Type Impv: INSTALL MEDIAN CABLE BARRIER Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE I-10 450-08 HSIPPEN 950 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

IBERVILLE I-10 450-07 HSIPPEN 750 SAFETY

W BATON ROUGE I-10 450-08 NHPP 750 SUSTAINABILITY INTERSTATE

Project: H.010683 - I-55: MEDIAN CABLE BARRIER Project Manager: Type Impv: INSTALL MEDIAN CABLE BARRIER Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA I-55 452-90 HSIPPEN 5,936 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Page 91 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.010743 - LA 3: LEFT TURN LANE Project Manager: Type Impv: INSTALL LEFT TURN LANE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 3 044-02 HSIP 350 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010864 - I-10: DISTRICT 07 CABLE BARRIER Project Manager: Type Impv: INSTALLATION OF CABLE BARRIER SYSTEM IN MEDIAN. Remarks: USE HSIP FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS I-10 450-03 HSIP 3,219 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

CALCASIEU I-10 450-91 HSIP 2,541 SAFETY

Project: H.010865 - I-210: DISTRICT 07 CABLE BARRIER Project Manager: Type Impv: INSTALLATION OF CABLE BARRIER SYSTEM IN MEDIAN. Remarks: USE HSIP FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-210 450-30 HSIP 939 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010894 - US 165: RIGHT TURN LANE AT LA 112 Project Manager: Type Impv: CONSTRUCT RIGHT TURN LANE ON US 165 TO THE INTERSECT LA 11Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 165 014-05 HSIP 260 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

RAPIDES US 165 014-05 NHPP 65 OPER EFFICIENCY/MOTORIST ASSISTANCE TRANSPORTATION SYSTEMS MANAGEMENT

Project: H.010962 - I-10: CABLE BARRIER (LAFAYETTE/ACADIA) Project Manager: Type Impv: INSTALL MEDIAN CABLE BARRIER Remarks: PLEASE USE HSIPPEN FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA I-10 450-04 HSIPPEN 4,041 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

LAFAYETTE I-10 450-05 HSIPPEN 1,478 SAFETY

Project: H.011100 - LA 3059: REALIGN @ PARISH LINE Project Manager: Type Impv: REALIGN CURVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 3059 383-01 SATRANS 1,475 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

JEFF DAVIS LA 3059 383-02 SATRANS 1,025 SAFETY

Project: H.011224 - US 190: GUARDRAIL/RUTTING REP. (PHASE 1) Project Manager: Type Impv: REPLACE GUARDRAIL. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage POINTE COUPEE US 190 008-03 HSIPPEN 3,123 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

POINTE COUPEE US 190 008-02 HSIPPEN 2,082 SAFETY

Project: H.011295 - LA 73 (GOVT ST) EAST BLVD - LOBDELL AVE Project Manager: Type Impv: CONVERSION OF 4-LANE UNDIVIDED TO 3-LANE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 73 077-05 HSIPPEN 4,892 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

E BATON ROUGE 000-17 STPFLEX 4,431 ROAD TRANSFER

Page 92 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.011302 - LA 28: LEFT TURN LANES AT LA 116 Project Manager: Type Impv: LEFT TURN LANE ON LA 28 AT THE INTERSECTION OF LA 116 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 28 074-02 HSIP 650 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011314 - LA 22: NEAR I-10 GEOMETRIC IMPROV Project Manager: Type Impv: IMPROVE THE SAFETY OF LA 22 USING ACCESS MGMENT (J-TURNS) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 22 266-01 HSIPPEN 2,250 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

ASCENSION LA 70 426-03 HSIPPEN 150 SAFETY

Project: H.011327 - US 90: J-TURNS - ST. MARY PARISH Project Manager: Type Impv: INTERSECTION IMPROVEMENTS AND MEDIAN CROSSOVERS CONSTRRemarks: REF. H.005171 FEASIBILITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY US 90 424-05 SATRANS 4,500 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011489 - DISTRICT 04 LOW COST SAFETY IMPROV Project Manager: Type Impv: SIGNING, PAVEMENT MARKINGS, RUMBLE STRIPS, RPMS, AND HFSTSRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 04 000-94 HSIPPEN 1,690 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011659 - LA 28: TURN LANE IMPROVEMENTS Project Manager: Type Impv: TURN LANE IMPS AT HEYMAN LANE AND GEORGETOWN DRIVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 28 417-02 HSIP 700 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011735 - LRSP/SRTS ENGINEER SEPT 2015 - SEPT 2018 Project Manager: Type Impv: LRSP/SRTS ENGINEER Remarks: USE SATRANS FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011764 - DISTRICT 58 GUARDRAIL REPLACEMENT A Project Manager: Type Impv: GUARDRAIL REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 58 000-91 HSIP 1,500 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011778 - LA 45: BARATARIA BLVD SAFETY IMPROVEMENT Project Manager: Type Impv: RECONSTRUCTION WITH NO ADDED CAPACITY Remarks: LETTERBID IN DISTRICT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 45 249-01 SATRANS 100 SAFETY 4-SCHEDULED FOR LETTING FY 15-16

Project: H.001557 - 22' PAVEMENT - JCT. US 165 Project Manager: Type Impv: WIDENING & O'LAY W/CURVE REALIGN. Remarks: 068-04-0030; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL LA 4 068-04 HSIP 1,120 SAFETY 3-DESIGN/DEVELOPMENT

Page 93 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.001749 - LA 5 REALIGNMENT AND CROSS SLOPE IMPROVE Project Manager: Type Impv: CURVE REALIGNMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 5 098-03 HSIP 1,200 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.002059 - LA 384 @ LA 385 Project Manager: Type Impv: INTERSECTION IMPROVEMENTS Remarks: 195-04-0029;INTR IMP.WIDEN LA 384&385 @MCNEESE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 385 195-04 HSIP 1,000 SAFETY 3-DESIGN/DEVELOPMENT

CALCASIEU LA 384 382-05 NHPP 550 SUSTAINABILITY NON-INTERSTATE CALCASIEU LA 384 382-05 HSIP 500 SAFETY

Project: H.003331 - ROUNDABOUT @ GARRETT RD INTERCHANGE Project Manager: Type Impv: SAFETY AND TRAFFIC FLOW Remarks: 451-06-0161; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA I-20 451-06 HSIP 900 SAFETY 3-DESIGN/DEVELOPMENT

OUACHITA I-20 451-06 LOCAL 300 OTHER / MISCELLANEOUS

Project: H.003459 - ROUNDABOUT @ LA 726 AND I-49 FRONTAGE RD Project Manager: Type Impv: CONSTRUCT ROUNDABOUT Remarks: 455-01-0054 AND 828-44-0015 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE I-49 455-01 HSIP 850 SAFETY 3-DESIGN/DEVELOPMENT

LAFAYETTE LA 726 828-44 HSIP 850 SAFETY

Project: H.006187 - LA 15 @ DEER PARK (S OF US 65 - LEVEE) Project Manager: Type Impv: LA 15 AT DEER PARK REALIGNMENT Remarks: 177-04-0033 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA LA 15 177-04 HSIP 1,657 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.008263 - LA 3144/SUSEK DRIVE ROUNDABOUT Project Manager: Type Impv: ROUNDABOUT Remarks: 840-34-0008; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 3144 840-34 HSIP 1,500 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.009093 - LA 175: TURN LANES @ LA 5 Project Manager: Type Impv: ADD TURN LANES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 175 035-04 HSIP 800 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.009320 - ACADIAN ROAD ROUNDABOUT Project Manager: Type Impv: 5 LEGGED ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 20 065-05 HSIP 1,570 SAFETY 3-DESIGN/DEVELOPMENT

Page 94 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.009456 - LA 347: ROUNDABOUT @ MELANCON RD. Project Manager: Type Impv: INSTALL ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 347 056-04 HSIP 2,134 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.010124 - LA 16: ROUNDABOUT @ LA 447 Project Manager: Type Impv: ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 16 262-01 HSIP 1,000 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.010204 - US 425: ROUNDABOUT @ JULIA & LOUISA Project Manager: Type Impv: INSTALL ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND US 425 071-01 HSIP 1,200 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.010277 - LA 593: INTER. IMPRV. NAFF @ COLLINGSTON Project Manager: Type Impv: INTERSECTION IMPROVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE LA 593 162-01 HSIP 800 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.010291 - I-10: TREE REMOVAL Project Manager: Type Impv: TREE REMOVAL ON I-10 IN ACADIA PARISH Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA I-10 450-04 HSIP 1,096 SAFETY 3-DESIGN/DEVELOPMENT

LAFAYETTE I-10 450-05 HSIP 514 SAFETY

Project: H.010353 - US 167: ACCESS MANAGEMENT (LFT TURN LNS) Project Manager: Type Impv: ACCESS MANAGEMENT, LEFT TURN LANES AND U-TURNS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION US 167 080-01 STPFLEX 248 SAFETY 3-DESIGN/DEVELOPMENT

LAFAYETTE US 167 080-02 NHPP 3,352 SAFETY

Project: H.010443 - LA 308: CURVE REALIGN AND SHOULDERS Project Manager: Type Impv: REALIGN CURVE AND ADD SHOULDERS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASSUMPTION LA 308 407-07 SATRANS 9,760 SAFETY 3-DESIGN/DEVELOPMENT

ASSUMPTION LA 308 407-08 SATRANS 1,900 SAFETY

Project: H.010922 - LA 88: REALIGN CURVES IN COTEAU Project Manager: Type Impv: REALIGN 2 CURVES ON LA 88 IN COTEAU Remarks: USE HSIP FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 89 397-05 SATRANS 4,900 SAFETY 3-DESIGN/DEVELOPMENT

Page 95 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.011030 - LA 59:ROUNDABOUT @ LONESOME RD. Project Manager: Type Impv: CONSTRUCT ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 59 281-03 HSIP 1,709 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.011075 - LA 59:ROUNDABOUT @ SHARP RD. Project Manager: Type Impv: CONSTRUCT ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 59 281-03 HSIP 1,914 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.011260 - US 190B @ JEFFERSON AVE. ROUNDABOUT Project Manager: Type Impv: ROUNDABOUT CONSTRUCTION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 190-X 013-10 HSIP 600 SAFETY 3-DESIGN/DEVELOPMENT

ST TAMMANY 000-52 HSIP 600 SAFETY

Project: H.011261 - LA427: S.ACADIAN TWY;PERKINS RD-LA73(BR) Project Manager: Type Impv: INTERSECTION IMPRS, MEDIAN MODS, OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 427 258-02 HSIP 1,500 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.011266 - LA 989-1: GEOMETRIC IMPROVEMENTS Project Manager: Type Impv: CURVE WIDEN Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 989-1 861-08 HSIPPEN 1,200 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.011278 - I-12:MEDIAN CABLE BARRIER Project Manager: Type Impv: MEDIAN CABLE BARRIER INSTALLATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON I-12 454-02 HSIP 3,836 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.011308 - I-10:MED PROTECTION TWIN SPANS-I-12/I-59 Project Manager: Type Impv: CONCRETE & CABLE MEDIAN BARRIER AND LIGHTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-10 450-18 HSIPPEN 8,500 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.011495 - US 90: RAMPS @ LA 88 ROUNDABOUTS Project Manager: Type Impv: ROUNDABOUTS, J-TURNS, U-TURNS, AND RELATED WORK. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 88 397-05 HSIP 2,800 SAFETY 3-DESIGN/DEVELOPMENT

IBERIA US 90 424-04 HSIP 2,000 SAFETY

Project: H.011660 - LA 3225: TURN LANES AT LA 623 Project Manager: Type Impv: CONSTRUCTION OF TURN LANES ON LA 3225 AT LA 623 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 3225 840-36 HSIP 1,120 SAFETY 3-DESIGN/DEVELOPMENT

Page 96 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.011665 - LA 308:BELLVIEW BRIDGE TO RITA BRIDGE Project Manager: Type Impv: LA 308 REALIGNMENT. Remarks: 407-90 LOGMILE 13.115 TO 13.52 NFA MATCH (DETAIL 1) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 308 407-90 HSIP 832 SAFETY 3-DESIGN/DEVELOPMENT

LAFOURCHE LA 308 407-90 HSIP 242 SAFETY

Project: H.011765 - DISTRICT 58 GUARDRAIL REPLACEMENT B Project Manager: Type Impv: GUARDRAIL REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 58 000-91 HSIP 1,500 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.011789 - LA 14 BYP: RIGHT TURN LANE AT US 167 Project Manager: Type Impv: INSTALL A RIGHT TURN LANE ON THE WB APPROACH Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 14-B 055-30 HSIP 425 SAFETY 3-DESIGN/DEVELOPMENT

Project: H.009421 - LA 1: J-TURNS @ SUGAR MILL PARKWAY Project Manager: Type Impv: FULL J-TURN & J-TURN BETWEEN TWO U-TURNS Remarks: 050-07 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 1 050-07 SATRANS 900 SAFETY 2-WAITING FOR FUNDING

Project: H.009420 - US 165: INSTALL J-TURN @ LA 101 Project Manager: Type Impv: INSTALL J-TURN ON US 165 @ LA 101 Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS US 165 014-02 HSIP 1,000 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.009952 - LA 1: MEDIAN CLOSURES Project Manager: Type Impv: MEDIAN CLOSURE WITH HSIP FUNDS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 1 050-06 HSIP 250 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.009997 - US 167 CORRIDOR STAGE 0 STUDY Project Manager: Type Impv: ACCESS MANAGEMENT AND OTHER SAFETY COUNTERMEASURES Remarks: STUDY FUNDED WITH SAFETY TRANSFER FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 167 080-02 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.010211 - I-110 NB RAMP AT CAPITOL ACCESS ROAD Project Manager: Type Impv: I-110 NB RAMP IMPROVEMENTS AT CAPITOL ACCESS ROAD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-110 450-92 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.010570 - LA 49 (WILLIAMS BLVD) CORRIDOR STUDY Project Manager: Type Impv: SAFETY/ACCESS MANAGEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 49 283-30 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Page 97 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.010688 - LA 3235 FEASIBILITY STUDY Project Manager: Type Impv: ACCESS MANAGEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 3235 829-26 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.010795 - JOE SEVARIO/RODDY ROUNDABOUTS STUDY Project Manager: Type Impv: ROUNDABOUTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 42 260-01 0 SAFETY 1-PLANNING/ENVIRONMENTAL

ASCENSION 000-03 0 SAFETY

Project: H.010823 - LA 21: ROUNDABOUT @ US 190 Project Manager: Type Impv: FEASIBILITY STUDY FOR ROUNDABOUT Remarks: FEASIBILITY STUDY FUNDED WITH SATRANS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 21 030-01 SATRANS 0 SAFETY 1-PLANNING/ENVIRONMENTAL

ST TAMMANY US 190-X 013-10 SATRANS 0 SAFETY

Project: H.010902 - US 61 FEASIBILITY STUDY Project Manager: Type Impv: FEASIBILITY STUDY Remarks: FEASIBILITY STUDY FUNDED WITH SATRANS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN US 61 007-04 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.010909 - LA 44: LA 941 TO LA 22 Project Manager: Type Impv: FEASIBILITY STUDY Remarks: FEASIBILITY STUDY FUNDED WITH SATRANS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 44 265-01 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011242 - LA 384 (BIG LAKE RD TO MCNEESE ST) Project Manager: Type Impv: TBD BY FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 384 382-05 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011243 - I-49 INTERCHANGE IMP. AT US 190 & LA 31 Project Manager: Type Impv: TBD BY FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY US 190 012-13 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011401 - US 51: W UNIV AVE TO I55 CORRIDOR STUDY Project Manager: Type Impv: CORRIDOR/TRAFFIC STUDY FOR ACCESSMAN AND SAFETY IMPROV Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA US 51 017-04 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011402 - US 51 BUS: I12 TO COLEMAN CORRIDOR STUDY Project Manager: Type Impv: TRAFFIC/CORRIDOR STUDY FOR ACCESS MGMT AND SAFETY IMPVERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA US 51-X 853-36 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Page 98 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: H.011403 - LA1208-3 TRAFFIC STUDY:VERSAILLES- LA488 Project Manager: Type Impv: CORRIDOR STUDY FOR SAFETY & ACCESS MANAGEMENT IMPROVEMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 1208-3 368-03 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011424 - LA157: BOOKER RD TO LA614 CORRIDOR STUDY Project Manager: Type Impv: ACCESS MANAGEMENT AND SAFETY IMPROVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 157 082-04 0 SAFETY 1-PLANNING/ENVIRONMENTAL

BOSSIER LA 157 082-03 0 SAFETY

Project: H.011428 - LA3105:GREENACRES TO LA72 CORRIDOR STUDY Project Manager: Type Impv: ACCESS MANAGEMENT AND SAFETY IMPROVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 3105 808-07 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011438 - US 71@LA 28: TRAFFIC SIGNAL TIMING STUDY Project Manager: Type Impv: SIGNAL TIMING STUDY OF US 71 @ LA 28 INTERCHANGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 28 417-02 0 SAFETY 1-PLANNING/ENVIRONMENTAL

RAPIDES US 71 008-30 0 SAFETY

Project: H.011440 - US 165 PEDESTRIAN CROSSING STUDY Project Manager: Type Impv: PEDESTRIAN CROSSING IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 165 015-31 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011454 - LA22:DALWILL-RODGER STORME CORRIDOR STUD Project Manager: Type Impv: ACCESS MANAGEMENT AND SAFETY IMPROVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 22 261-06 0 SAFETY 1-PLANNING/ENVIRONMENTAL

Project: H.011688 - US 165: CORRIDOR STUDY US 165 BUS - LA 2 Project Manager: Type Impv: CORRIDOR STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 165 015-31 0 SAFETY 1-PLANNING/ENVIRONMENTAL

OUACHITA US 165 016-01 0 SAFETY

Project: L.000016 - FEDERAL SAFETY PROGRAMS Project Manager: Type Impv: MISC PROJECTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - HSIP 300 SAFETY STAGES 4, 3, 2, 1, 0

- STPFLEX 200 SAFETY

- STCASH 100 SAFETY

Page 99 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - Project: L.000030 - CRASH ATTENUATOR REPAIRS Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 200 SAFETY STAGES 4, 3, 2, 1, 0

- STCASH 100 SAFETY

Project: L.000037 - HIGHWAY SAFETY IMPROVEMENTS Project Manager: Type Impv: RUMBLE STRIPS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 2,000 SAFETY STAGES 4, 3, 2, 1, 0

Project: L.000024 - SOFT SIDE SAFETY Project Manager: Type Impv: HANDLED THROUGH OPERATIONS BUDGET Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - HSIP 1,000 SAFETY STAGES 2, 1, 0

- STCASH 500 SAFETY

Page 100 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - LOCAL ROADS SAFETY Project: H.006482 - CITY OF WESTLAKE SIGN REPLACEMENT Project Manager: Type Impv: SIGN INSTALLATION Remarks: 737-10-0120;ENTITY REQUIRED TO MATCH FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 SATRANS 44 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 LOCAL ROADS SAFETY

Project: H.010850 - SIGN SAFETY IMPROVEMENTS Project Manager: Type Impv: PURCHASE AND INSTALL REGULATORY & WARNING SIGNS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 SATRANS 23 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 LOCAL ROADS SAFETY

Project: H.006468 - BEAUREGARD PARISH GUARDRAIL REPLACEMENT Project Manager: Type Impv: GUARDRAIL REPLACEMENT Remarks: ENTITY REQUIRED TO MATCH FUNDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BEAUREGARD 000-06 0 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.006472 - CITY OF SHREVEPORT TRAFFIC SIG BKUP Project Manager: Type Impv: TRAFFIC SIGNAL POWER GENERATOR INST Remarks: 737-09-0104; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 SATRANS 216 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.006475 - CITY OF SHRVPRT TRAFFIC SIGNAL BKUP Project Manager: Type Impv: TRAFFIC SIGNAL POWER GENERATOR Remarks: 737-09-0108; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 SATRANS 158 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.006511 - GUARDRAIL & ROAD ALLIGNMENT CHANGES Project Manager: Type Impv: SITE DISTANCE IMPROVEMENTS Remarks: 737-25-0002; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON 000-25 SATRANS 402 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY JACKSON 000-25 LOCAL 45 SAFETY LOCAL ROADS SAFETY

Project: H.006530 - ROUNDABOUT AT GEN. MOUTON/TAFT STREET Project Manager: Type Impv: CONSTRUCTION OF A ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 SATRANS 419 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY LAFAYETTE 000-28 LOCAL 47 SAFETY LOCAL ROADS SAFETY

Project: H.006548 - LINER & ROUGH EDGE ROAD IMPROVEMENT Project Manager: Type Impv: SITE DISTANCE AND ALIGNMENT Remarks: 737-31-0003; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN 000-31 HRRR 168 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY LINCOLN 000-31 LOCAL 16 SAFETY LOCAL ROADS SAFETY

Page 101 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - LOCAL ROADS SAFETY Project: H.006567 - PEDESTRIAN CROSSWALK ENHANCEMENTS Project Manager: Type Impv: SIGNS & PVMT.MARKINGS INSTALLATION Remarks: 737-36-0016; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SATRANS 276 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.006618 - SIDEWALK ON HIGH SCHOOL DRIVE Project Manager: Type Impv: SIDEWALK INSTALLATION Remarks: 737-58-0001; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON 000-58 HRRR 96 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY VERNON 000-58 LOCAL 8 SAFETY LOCAL ROADS SAFETY

Project: H.006619 - SIDEWALK ON LOUISIANA AVENUE Project Manager: Type Impv: SIDEWALK INSTALLATION Remarks: 737-58-0002; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON 000-58 HRRR 134 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY VERNON 000-58 LOCAL 13 SAFETY LOCAL ROADS SAFETY

Project: H.009176 - LULING INTERSECTION SAFETY IMPROVEMENTS Project Manager: Type Impv: PURCHASE AND INSTALL SIGNS AND SOLAR BEACONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES 000-45 SATRANS 40 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.009434 - VARIOUS ROADS:SIGNING (BIENVILLE) Project Manager: Type Impv: SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE 000-07 SATRANS 10 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.009438 - VARIOUS ROADS:SIGNING (CADDO) Project Manager: Type Impv: SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 SATRANS 47 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.009451 - VARIOUS ROADS:SIGNING (SABINE) Project Manager: Type Impv: SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE 000-43 SATRANS 10 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.009453 - VARIOUS ROADS:SIGNING (ST. CHARLES) Project Manager: Type Impv: SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES 000-45 SATRANS 5 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.009460 - VARIOUS ROADS:SIGNING (ST. TAMMANY) Project Manager: Type Impv: SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 SATRANS 20 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Page 102 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - LOCAL ROADS SAFETY Project: H.009463 - VARIOUS ROADS:SIGNING (VERMILION) Project Manager: Type Impv: SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION 000-57 SATRANS 30 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.009466 - VARIOUS ROADS:SIGNING (WEBSTER) Project Manager: Type Impv: SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER 000-60 SATRANS 12 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.011216 - CITY OF SLIDELL PAVEMENT MARKINGS Project Manager: Type Impv: PURCHASE AND INSTALL PAVEMENT MARKINGS ON 12 LOCAL ROADRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 SATRANS 60 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.011776 - NATCHITOCHES SIGNING Project Manager: Type Impv: PURCHASE AND INSTALL REGULATORY & WARNING SIGNS, ETC. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES 000-35 SATRANS 20 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY

Project: H.011777 - PLAQUEMINES PH MESSAGE BOARD PURCHASE Project Manager: Type Impv: PURCHASE 2 MESSAGE BOARDS Remarks: PROJECT FUNDED 95% SATRANS AND 5% LOCAL MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage PLAQUEMINES 000-38 SATRANS 38 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 LOCAL ROADS SAFETY PLAQUEMINES 000-38 LOCAL 2 SAFETY LOCAL ROADS SAFETY

Project: H.006531 - ROUNDABOUT AT HOSPITAL DRIVE AND GIRARD Project Manager: Type Impv: CONSTRUCTION OF A ROUNDABOUT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 SATRANS 500 SAFETY 3-DESIGN/DEVELOPMENT LOCAL ROADS SAFETY LAFAYETTE 000-28 LOCAL 56 SAFETY LOCAL ROADS SAFETY

Project: H.006457 - ROUNDABOUT @ PR 929 & PARKER ROADS Project Manager: Type Impv: ROUNDABOUT CONSTRUCTION Remarks: 737-03-0104; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION 000-03 SATRANS 500 SAFETY 2-WAITING FOR FUNDING LOCAL ROADS SAFETY

Project: H.006578 - FAIRWAY DRIVE SIGN IMPROVEMENTS Project Manager: Type Impv: SIGN & FLASHING BEACON INSTALLATION Remarks: 737-37-0013; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 HRRR 16 SAFETY 1-PLANNING/ENVIRONMENTAL LOCAL ROADS SAFETY

Page 103 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - SAFE ROUTES TO SCHOOLS Project: H.006528 - FENTON ELEMENTARY Project Manager: GROS, SCOTT Type Impv: SIDEWALK CONSTRUCTION AND CROSSWALKS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS 000-27 SR2S 81 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS JEFF DAVIS 000-27 SATRANS 10 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.006538 - LAFAYETTE SAFE ROUTES TO SCHOOL PROJECT Project Manager: Type Impv: CONSTRUCTION OF SIDEWALKS AND CROSSWALKS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 SR2S 126 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS LAFAYETTE LA 92 213-05 SR2S 112 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009282 - ST. JOHN THE BAPTIST PARISH PROJECT Project Manager: GROS, SCOTT Type Impv: SIDEWALKS,MARKINGS,SIGNALS,EDUCATION&ENCOURAGEMENT ACRemarks: ST. JOHN THE BAPTIST PH.LAPLACE ELEMENTARY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN 000-48 SR2S 193 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS ST JOHN 000-48 SATRANS 28 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009290 - LSU LABORATORY SCHOOL SRTS PROJECT Project Manager: Type Impv: BICYCLE LANES AND EDUCATION AND ENCOURAGEMENT ACTIVITIESRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 SR2S 190 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS E BATON ROUGE 000-17 SATRANS 30 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009297 - OUACHITA PAR. POLICE JURY SRTS PROJECT Project Manager: Type Impv: SIDEWALKS/PED PATHS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 SR2S 172 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS OUACHITA 000-37 SATRANS 27 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009838 - SAFE ROUTES TO ARISE ACADEMY Project Manager: Type Impv: NON-INFRASTRUCTURE SRTS PROJECT ONLY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 50 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Project: H.009949 - ESPERANZA SAFE ROUTES TO SCHOOL Project Manager: Type Impv: NON-INFRASTRUCTURE SRTS PROJECT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 18 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Project: H.010115 - JACK HAYES ELEM. SRTS NON-INFRASTRUCTURE Project Manager: Type Impv: PURCHASES, INCENTIVES, BICYCLE RACKS, TRAINING. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 SR2S 100 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Page 104 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - SAFE ROUTES TO SCHOOLS Project: H.011192 - OUACHITA SRTS PROJECT JACK HAYES II N.I. Project Manager: Type Impv: EDUCATION AND ENCOURAGEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 0 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Project: H.011193 - OUACHITA SRTS PROJECT - RISER N.I. Project Manager: Type Impv: EDUCATION AND ENCOURAGEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 0 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Project: H.011197 - DENHAM SPRINGS SRTS PROJ - NORTHSIDE Project Manager: Type Impv: SIDEWALKS, STRIPING AND SIGNING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 SR2S 170 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS LIVINGSTON 000-32 SATRANS 25 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.011199 - NEW ORLEANS SRTS PROJ. - EINSTEIN II NI Project Manager: Type Impv: EDUCATION AND ENCOURAGEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 50 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Project: H.011200 - NEW ORLEANS SRTS PROJ. - AUDUBON N.I. Project Manager: Type Impv: EDUCATION AND ENCOURAGEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 74 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Project: H.011201 - KENNER SRTS PROJECT - CHATEAU ELEM Project Manager: Type Impv: EDUCATION AND ENCOURAGEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 0 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Project: H.011202 - FRANKLINTON SRTS PROJECT - FJHS Project Manager: Type Impv: SIDEWALKS STRIPING AND SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON 000-59 SR2S 178 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS WASHINGTON 000-59 SATRANS 28 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.011203 - PINEVILLE SRTS PROJ - PINEVILLE ELEM NI Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 0 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Project: H.011204 - ALEXANDRIA SRTS PROJECT - MARTIN PARK NI Project Manager: Type Impv: EDUCATION AND ENCOURAGEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 0 SAFETY 4-SCHEDULED IN CURRENT FY 14-15 SAFE ROUTES TO SCHOOLS

Page 105 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - SAFE ROUTES TO SCHOOLS Project: H.006484 - CALCASIEU PH.LEGER RD.SIDEWALK SRTS Project Manager: Type Impv: SIDEWALKS Remarks: 737-10-0123;SR2S PROGRAM FUNDING Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 SR2S 202 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS CALCASIEU 000-10 SATRANS 26 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.006499 - SAFE ROUTES TO WESTDALE MIDDLE SCHOOL Project Manager: GROS, SCOTT Type Impv: CONSTRUCTION OF BIKEPATH AND PURCHASE OF SPEED FEEDBACKRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 SR2S 180 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS E BATON ROUGE 000-17 SATRANS 23 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.006524 - CITY OF GRETNA SAFE ROUTES TO SCHOOL - M Project Manager: GROS, SCOTT Type Impv: SIDEWALKS, CROSSWALKS, SIGNS, ETC. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 SR2S 247 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS

Project: H.006525 - CITY OF GRETNA SAFE ROUTES TO SCHOOLS - Project Manager: GROS, SCOTT Type Impv: SIDEWALKS, CROSSWALKS, AND SIGNING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 SR2S 188 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS JEFFERSON 000-26 SATRANS 30 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.006738 - KIDS ON THE MOVE PH. 2 Project Manager: GROS, SCOTT Type Impv: SIDEWALK REPAIR,SIGNS AND PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 SR2S 125 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS BOSSIER 000-08 SATRANS 21 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.007229 - LAFAYETTE CON.GOV. SR2S PROJECT Project Manager: Type Impv: SIDEWALKS. ETC. Remarks: 742-28-0003;SR2S PROGRAM FUNDING Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 SR2S 178 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS LAFAYETTE 000-28 SATRANS 22 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009277 - GRAMBLING SR2S PROJECT Project Manager: GROS, SCOTT Type Impv: SIDEWALK, CROSSWALKS, MARKINGS ETC. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN 000-31 SR2S 180 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS LINCOLN 000-31 SATRANS 26 SAFETY SAFE ROUTES TO SCHOOLS LINCOLN LA 149 831-16 SR2S 11 SAFETY SAFE ROUTES TO SCHOOLS LINCOLN LA 149 831-16 SATRANS 3 SAFETY SAFE ROUTES TO SCHOOLS

Page 106 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - SAFE ROUTES TO SCHOOLS Project: H.009278 - BERNICE SR2S PROJECT Project Manager: GROS, SCOTT Type Impv: SIDEWALK, CROSSWALKS, HANDICAP RAMPS, ETC Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage UNION 000-56 SR2S 162 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS UNION 000-56 SATRANS 23 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009298 - TOWN OF OBERLIN SRTS PROJECT Project Manager: GROS, SCOTT Type Impv: SIDEWALK IMPROVMENTS, MARKED CROSSINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ALLEN 000-02 SR2S 194 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS ALLEN 000-02 SATRANS 28 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009299 - RAPIDES PARISH SCHOOL DIST. SRTS PROJECT Project Manager: Type Impv: SIDEWALK CONSTRUCTION, MARKINGS, ADA IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 SR2S 193 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS RAPIDES 000-40 SATRANS 28 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009308 - NEW ORLEANS DPW - EP HARNEY SCHOOL PROJ. Project Manager: GROS, SCOTT Type Impv: BICYCLE & PEDESTRAIN CROSSING IMPROVEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 175 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS ORLEANS US 90 006-03 SATRANS 20 SAFETY SAFE ROUTES TO SCHOOLS ORLEANS US 90 006-03 SR2S 25 SAFETY SAFE ROUTES TO SCHOOLS ORLEANS US 90 006-03 SATRANS 5 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.009433 - OUACHITA SRTS PROJECT - JACK HAYES II Project Manager: Type Impv: SIDEWALKS, SIGINING AND STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 SR2S 181 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS

Project: H.010066 - I A LEWIS ELEM. SRTS SIDEWALK PROJECT Project Manager: GROS, SCOTT Type Impv: SIDEWALK IMPROVEMENT, TRAFFICE CALMING, SPEED REDUCTION IMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN 000-31 SR2S 200 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS LINCOLN 000-31 SATRANS 25 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.010070 - RUGG ELEM. SAFE ROUTES TO SCHOOL PH. II Project Manager: Type Impv: SIDEWALKS, STRIPING AND MARKINGS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 SR2S 203 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS RAPIDES 000-40 SATRANS 26 SAFETY SAFE ROUTES TO SCHOOLS

Page 107 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - SAFE ROUTES TO SCHOOLS Project: H.010086 - E.P. HARNEY SCHOOL SRTS NON-INFRASTRUCT Project Manager: Type Impv: SRTS NON-INFRASTRUCTURE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 0 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS

Project: H.010092 - SRTS JACK HAYES ELEM., OUACHITA PARISH Project Manager: Type Impv: CONSTRUCT SIDEWALKS AND CROSSWALKS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 SR2S 200 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS OUACHITA 000-37 SATRANS 5 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.010100 - PESSON ELEM. SAFE ROUTES PHASE I Project Manager: Type Impv: SIDEWALK CONSTRUCTION, MARKINGS, Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 SR2S 190 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS IBERIA 000-23 SATRANS 28 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.010106 - BOGALUSA SRTS PROJECT - COLUMBIA AVE Project Manager: GROS, SCOTT Type Impv: SIDEWALK IMPROVMENTS, STRIPING, ENCOURAGMENT AND EDUCATRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON 000-59 SR2S 195 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS WASHINGTON 000-59 SATRANS 27 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.010108 - INDEPENDENCE SRTS - PHASE II Project Manager: GROS, SCOTT Type Impv: SIDEWALK IMPROVMENTS, CROSSING AND STRIPING, NON-INFRASTRRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA 000-53 SR2S 190 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS TANGIPAHOA 000-53 SATRANS 27 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.010109 - RACELAND SRTS PROJECT Project Manager: GROS, SCOTT Type Impv: SIDEWALK IMPROVMENTS, CROSSWALK, SPEED DETECTION DEVICESRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE 000-29 SR2S 202 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS LAFOURCHE 000-29 SATRANS 26 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.010110 - EAST ST. JOHN ELEM SCHOOL SRTS PROJECT Project Manager: GROS, SCOTT Type Impv: SIDEWALK IMPROVMENTS, TRAFFIC CALMING, STRIPING AND MARKINRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN 000-48 SR2S 193 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS ST JOHN 000-48 SATRANS 28 SAFETY SAFE ROUTES TO SCHOOLS

Page 108 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - SAFE ROUTES TO SCHOOLS Project: H.010111 - AUDUBON CHARTER SCHOOL SRTS INFRASTRUCT Project Manager: GROS, SCOTT Type Impv: SIDEWALK IMPROVMENTS, TRAFFIC CALMING, STRIPING AND MARKINRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 174 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS ORLEANS 000-36 SATRANS 28 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.010112 - AUDUBON CHARTER SCHOOL SRTS NON-INFRAST Project Manager: Type Impv: BIKE AND PED SAFETY TRAINING,PURCHASES, ENFORCEMENT ACTIVRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 125 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS

Project: H.010113 - EINSTEIN CHARTER SCHOOL SRTS NON-INFRAST Project Manager: Type Impv: BIKE/PED SAFETY TRAINING, PURCHASES, ENCOURAGEMENT ACTIVIRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 100 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS

Project: H.010114 - EINSTEIN CHARTER SCHOOL INFRASTRUCTURE Project Manager: GROS, SCOTT Type Impv: SIDEWALK IMPROVEMENTS, TRAFIC CALMING, MARKINGS AND STRIPRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 190 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS ORLEANS 000-36 SATRANS 30 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.010352 - OUACHITA SRTS PROJECT - RISER Project Manager: Type Impv: SIDEWALKS, SIGINING AND STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 3033 837-12 SR2S 42 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS OUACHITA LA 3033 837-12 SATRANS 7 SAFETY SAFE ROUTES TO SCHOOLS OUACHITA 000-37 SR2S 100 SAFETY SAFE ROUTES TO SCHOOLS OUACHITA 000-37 SATRANS 11 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.011138 - COVINGTON SRTS PROJ. - PINE VIEW MIDDLE Project Manager: Type Impv: SIDEWALKS, DRAINAGE, STRIPING AND SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 SR2S 188 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS ST TAMMANY 000-52 SATRANS 30 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.011194 - PINEVILLE SRTS PROJECT - PINEVILLE ELEM. Project Manager: Type Impv: SIDEWALKS, SIGNING AND STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 165-X 015-01 SR2S 150 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS RAPIDES US 165-X 015-01 SATRANS 18 SAFETY SAFE ROUTES TO SCHOOLS RAPIDES 000-40 SR2S 47 SAFETY SAFE ROUTES TO SCHOOLS RAPIDES 000-40 SATRANS 6 SAFETY SAFE ROUTES TO SCHOOLS

Page 109 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SAFETY - SAFE ROUTES TO SCHOOLS Project: H.011195 - ALEXANDRIA SRTS PROJECT - MARTIN PARK Project Manager: Type Impv: SIDEWALKS, STRIPING AND SIGNAGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 SR2S 231 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS RAPIDES 000-40 SATRANS 29 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.011196 - LAKE CHARLES SRTS PROJ. - BARBE ELEM. Project Manager: Type Impv: SIDEWALKS, STRIPING AND SIGNING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 SR2S 200 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS CALCASIEU 000-10 SATRANS 25 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.011198 - NEW ORLEANS SRTS PROJ. - EINSTEIN II Project Manager: Type Impv: SIDEWALKS, STRIPING AND SIGNING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 SR2S 200 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS ORLEANS 000-36 SATRANS 25 SAFETY SAFE ROUTES TO SCHOOLS

Project: H.011232 - LAKE CHARLES SRTS PROJ. - BARBE ELEM. NI Project Manager: Type Impv: EDUCATIONAL AND ENCOURAGEMENT ACTIVITIES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 0 SAFETY 4-SCHEDULED FOR LETTING FY 15-16 SAFE ROUTES TO SCHOOLS

Page 110 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.006196 - WISNER BLVD BRIDGE REPLACEMENT Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 713-36-0108;SEE LONG TEXT FOR FUNDING INFORMATION Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 FBROFF 12,705 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (OFF SYSTEM) ORLEANS 000-36 TAP>200K 3,176 ENHANCEMENTS

Project: H.010036 - FUSELIER ROAD & JEAN DUOS ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage EVANGELINE 000-20 FBROFF 666 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (OFF SYSTEM)

Project: H.010067 - LYONS HILL AND FLAT LICK ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CLAIBORNE 000-14 FBROFF 962 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (OFF SYSTEM)

Project: H.010598 - DERRICK ROAD BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE 000-24 FBROFF 493 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (OFF SYSTEM)

Project: H.010861 - KATELAND GIN ROAD / DARROW BAYOU Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage GRANT 000-22 FBROFF 1,168 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (OFF SYSTEM)

Project: H.010024 - SMITHVILLE ROAD / BRALY CREEK Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER 000-60 FBROFF 354 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM)

Project: H.010032 - SHUTEYE ROAD & MARTHAVILLE ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE 000-43 FBROFF 393 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) SABINE 000-43 FBROFF 593 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010033 - PIONEER ROAD & LAKESIDE LOOP BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE 000-43 FBROFF 193 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) SABINE 000-43 FBROFF 585 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Page 111 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.010034 - JOE W ROAD & GALLOW ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY 000-49 FBROFF 570 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) ST LANDRY 000-49 FBROFF 246 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010035 - ANDREPONT RD & BAYOU GERMOND RD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY 000-49 FBROFF 293 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) ST LANDRY 000-49 FBROFF 601 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010040 - BUD ROAD & BONNE IDEE ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE 000-34 FBROFF 585 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) MOREHOUSE 000-34 FBROFF 416 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010054 - PARK ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ALLEN 000-02 FBROFF 447 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) ALLEN 000-02 FBROFF 308 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010055 - CHERRY WITCHIE & N. CARPENTER RD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ALLEN 000-02 FBROFF 2,510 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) ALLEN 000-02 FBROFF 1,426 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010061 - N. RIVER ROAD AND DURBIN ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA 000-53 FBROFF 731 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM)

Project: H.010062 - WEINBERGER RD & JERUSALEM CH RD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA 000-53 FBROFF 878 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM)

Project: H.010068 - BUSH ROAD AND LISHMAN ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage FRANKLIN 000-21 FBROFF 662 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) FRANKLIN 000-21 FBROFF 447 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Page 112 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.010150 - S. AVENUE F & NAPP STREET BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA 000-01 FBROFF 732 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) ACADIA 000-01 FBROFF 262 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010559 - BAYOU MERCIER ROAD / BERARD CANAL BAYOU Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN 000-50 FBROFF 1,178 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM)

Project: H.010561 - CASTOR CK RD/BEAR CK RD/DANIEL ST BRDGS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE 000-07 FBROFF 370 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) BIENVILLE 000-07 FBROFF 454 SUSTAINABILITY BRIDGE (OFF SYSTEM) BIENVILLE 000-07 FBROFF 293 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010592 - WILLET LOOP RD & ROCK HILL RD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage GRANT 000-22 FBROFF 585 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) GRANT 000-22 FBROFF 470 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010659 - RAFE-MEYER ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 FBROFF 732 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (OFF SYSTEM) E BATON ROUGE 000-17 FBROFF 593 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.006128 - VIDA SHAW BRIDGE OVER BAYOU TECHE Project Manager: BORAZJANI, MOHAMMAD Type Impv: BRIDGE REPLACEMENT Remarks: 713-23-0001;MOVEABLE BRIDGE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 FBROFF 4,177 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.006202 - BREARD STREET BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 713-37-0109; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 FBROFF 400 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Page 113 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.009981 - SKINNER LANE & ODIS WADE ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W CARROLL 000-62 FBROFF 447 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) W CARROLL 000-62 FBROFF 300 SUSTAINABILITY BRIDGE (OFF SYSTEM) W CARROLL 000-62 FBROFF 231 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010038 - TENDAL NORTH RD / DRAIN TO TENSAS BAYOU Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON 000-33 FBROFF 1,001 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010039 - BEAR KNOLL DRIVE & ZOAR ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON 000-25 FBROFF 578 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010056 - EAVES ROAD & JEFFERSON AVENUE BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN 000-31 FBROFF 693 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010060 - BLANCHARD FURRH ROAD / CHOCTAW BAYOU Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 FBROFF 1,047 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010079 - MOUTON RE/W DIVISION ST/POWELL RD BRDGS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS 000-27 FBROFF 1,317 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) JEFF DAVIS 000-27 FBROFF 732 SUSTAINABILITY BRIDGE (OFF SYSTEM) JEFF DAVIS 000-27 FBROFF 439 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010557 - LAJAUNIE RD / LATERAL 1 BAYOU ST. CLAIR Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 FBROFF 447 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010562 - BANK STREET & SINGLETARY STREET BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E FELICIANA 000-19 FBROFF 539 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) E FELICIANA 000-19 FBROFF 300 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Page 114 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.010563 - 5TH AVE (SOUTHBOUND) / FIFTH AVE DRAIN Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 FBROFF 439 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010564 - PEARL STREET / LATERAL L-3 Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 FBROFF 295 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010596 - PETERSON ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W FELICIANA 000-63 FBROFF 385 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) W FELICIANA 000-63 FBROFF 616 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010597 - SLIGO ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W FELICIANA 000-63 FBROFF 3,388 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) W FELICIANA 000-63 FBROFF 747 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010599 - WELCOME CEMETERY ROAD / MENACE CREEK Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON 000-58 FBROFF 316 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010608 - PLEASANT HILL RD & LAWRENCE CK RD BRDGS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON 000-59 FBROFF 447 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) WASHINGTON 000-59 FBROFF 655 SUSTAINABILITY BRIDGE (OFF SYSTEM) WASHINGTON 000-59 FBROFF 739 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010625 - PEA RIDGE AND JOHN BARBER ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 FBROFF 370 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) LIVINGSTON 000-32 FBROFF 254 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010626 - SAUVE ROAD / SONIAT CANAL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 FBROFF 1,033 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Page 115 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.010660 - TUCKER RD/DYER RD/DENHAM RD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 FBROFF 732 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) E BATON ROUGE 000-17 FBROFF 593 SUSTAINABILITY BRIDGE (OFF SYSTEM) E BATON ROUGE 000-17 FBROFF 739 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010661 - N. FLANNERY/FIREWOOD/CLOVERLAND BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 FBROFF 601 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) E BATON ROUGE 000-17 FBROFF 439 SUSTAINABILITY BRIDGE (OFF SYSTEM) E BATON ROUGE 000-17 FBROFF 439 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010668 - MIL DOLLAR/HOSMER MILL/HWY 41 SPUR BRDGS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 FBROFF 3,389 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010724 - PECAN ISLAND ROAD BRIDGE OVER THE CHENAL Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage POINTE COUPEE 000-39 FBROFF 1,109 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010817 - ROGERS FIELD AND MOUNCE ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO 000-16 FBROFF 285 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) DESOTO 000-16 FBROFF 293 SUSTAINABILITY BRIDGE (OFF SYSTEM) DESOTO 000-16 FBROFF 1,117 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010867 - JUDE & PLACIDE ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION 000-57 FBROFF 308 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) VERMILION 000-57 FBROFF 300 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.010915 - BEEHIVE LP & FIELDING WILLIAMS RD BRDGS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BEAUREGARD 000-06 FBROFF 600 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) BEAUREGARD 000-06 FBROFF 308 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Page 116 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.010941 - RATCLIFF ROAD / DUCK CREEK Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CATAHOULA 000-13 FBROFF 1,625 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.010943 - CLARK/GOOD HOPE/ROBELINE-PROVENCAL BRDGS Project Manager: Type Impv: BRIDGE REPLACEMENTS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES 000-35 FBROFF 1,224 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) NATCHITOCHES 000-35 FBROFF 601 SUSTAINABILITY BRIDGE (OFF SYSTEM) NATCHITOCHES 000-35 FBROFF 447 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011087 - WESTDALE PLANTATION ROAD / BAYOU PIERRE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: DOTD PROVIDES THE MATCH FOR THE OFF-SYSTEM HWY BR PR Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RED RIVER 000-41 FBROFF 1,794 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.011159 - CAROLL STREET AND BUQUET STREET BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT - NO ADDED CAPACITY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE 000-55 FBROFF 939 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) TERREBONNE 000-55 FBROFF 585 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011522 - FAITH BAPTIST MISSION & BILL BELT ROADS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES 000-05 FBROFF 308 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) AVOYELLES 000-05 FBROFF 285 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011523 - CARL HUNT & GERMAN BAYOU ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES 000-05 FBROFF 493 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) AVOYELLES 000-05 FBROFF 231 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011524 - KATIE LANE & LEO MORROW ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES 000-05 FBROFF 308 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) AVOYELLES 000-05 FBROFF 223 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011525 - SNEED ROAD / TORO CREEK Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE 000-43 FBROFF 246 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Page 117 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.011526 - CASTOR PLNGE/H.STRANGE/PALMER CHPL BRDGS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 FBROFF 539 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) RAPIDES 000-40 FBROFF 408 SUSTAINABILITY BRIDGE (OFF SYSTEM) RAPIDES 000-40 FBROFF 300 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011527 - RANDALL / BROWN / VITRANO ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA 000-53 FBROFF 447 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) TANGIPAHOA 000-53 FBROFF 447 SUSTAINABILITY BRIDGE (OFF SYSTEM) TANGIPAHOA 000-53 FBROFF 400 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011528 - GEORGE MASHON RD & TRAVIS STREET BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 FBROFF 716 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) LIVINGSTON 000-32 FBROFF 223 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011529 - MITCHINER ROAD & GUNTER LOOP BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W CARROLL 000-62 FBROFF 454 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) W CARROLL 000-62 FBROFF 308 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011530 - CYPRESS CREEK ROAD / BOATWRIGHT CREEK Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage UNION 000-56 FBROFF 239 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.011531 - DIXIE CHURCH & SETLIFF ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 FBROFF 454 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) RAPIDES 000-40 FBROFF 377 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011532 - MOTT LANE / DRAIN TO LAKE ERWIN Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE 000-34 FBROFF 239 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Page 118 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: H.011533 - N. BAYOU BLACK DRIVE / HANSON CANAL Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE 000-55 FBROFF 524 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.011534 - WEST LOYOLA & METAIRIE HEIGHTS BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 FBROFF 462 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) JEFFERSON 000-26 FBROFF 447 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011539 - PERCY BURNS ROAD / LITTLE CROOKED CREEK Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER 000-60 FBROFF 601 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.011540 - BABIN ROAD / BAYOU NARCISSE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION 000-03 FBROFF 293 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.011541 - NATION ROAD / COULEE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA 000-01 FBROFF 647 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.011542 - PELLERIN ROAD / DELAHOUSSAYE CANAL Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA 000-23 FBROFF 439 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.011544 - ROZENA AND BILLEAUX ROAD BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY 000-49 FBROFF 477 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM) ST LANDRY 000-49 FBROFF 400 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Project: H.011545 - LITTLE CHENIER RD / LITTLE CHENIER BAYOU Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CAMERON 000-12 FBROFF 293 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Project: H.011546 - NURSERY STREET / BUXTON CREEK Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 FBROFF 385 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (OFF SYSTEM)

Page 119 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (OFF SYSTEM) Project: L.000035 - MISC FEDERAL OFF-SYSTEM BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENTS/INSPECTIONS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - FBROFF 1,000 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 BRIDGE (OFF SYSTEM) - STCASH 200 SUSTAINABILITY BRIDGE (OFF SYSTEM)

Page 120 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.003353 - I-20 DRAINAGE CANAL BRIDGE Project Manager: Type Impv: BRIDGE REHAB Remarks: 451-08-0086;REHAB ABUTMENT WALLS. & APP. SLABS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON I-20 451-08 NHPP 1,750 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (ON SYSTEM)

Project: H.007961 - LA 410: BLACKWATER BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 817-05-0015; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 410 817-05 STPFLEX 1,202 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (ON SYSTEM)

Project: H.008345 - BAYOU ALEXANDRE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 850-29-0005;USE NFA AS MATCH PHASES 1 TO 5 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 3083 850-29 NFA 1,219 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (ON SYSTEM)

Project: H.010498 - I-310: LULING BR DECK OVERLAY & REPAIR Project Manager: Type Impv: REMOVE AND REPLACE BRIDGE DECK OVERLAY & STRUCTURAL REPRemarks: PRIORITY BRIDGE PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES I-310 450-37 NHPP 28,000 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (ON SYSTEM)

Project: H.011343 - I-10 WHISKEY BAY FIRE REPAIR Project Manager: Type Impv: FIRE DAMAGE REPAIR Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE I-10 450-07 REIMB 500 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE (ON SYSTEM) IBERVILLE I-10 450-07 NHPP 50 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.000169 - UNION PACIFIC RAILROAD BRIDGE AT SICARD Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 002-01-0047; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 80 002-01 STPFLEX 7,780 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.000517 - US 165 BRIDGES NEAR FENTON Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 014-02-0025; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS US 165 014-02 STP<5K 5,500 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.000577 - US 165-X: KCS RAILWAY OVERPASS Project Manager: Type Impv: BRIDGE REMOVAL. REPLACE WITH AT GRADE CROSSING Remarks: 015-01-0049;SCOPE CHANGED Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 165-X 015-01 STPFLEX 1,763 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.000673 - US 51 BRIDGE REHABILITATION Project Manager: Type Impv: TEMP. SUPPORT, REPAIR CONCRETE, INSTALL POST-TENSIONING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA US 51 017-04 STPFLEX 380 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Page 121 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.000974 - BOUEF RIVER BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 026-09-0024; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 15 026-09 STPFLEX 7,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.001257 - INTERSECTION LA 114 @ LA 1 Project Manager: Type Impv: REPLACE BRIDGE W/ T-INTERSECTION AND WIDEN ANOTHER BRIDGERemarks: 052-05-0050; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES LA 114 052-05 FBROFF 765 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM) AVOYELLES LA 114 052-05 HSIP 89 SAFETY

AVOYELLES LA 1 052-30 HSIP 255 SAFETY

AVOYELLES LA 1 052-30 STPFLEX 249 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.001439 - LA 1 BRIDGES NEAR GRAND ISLE Project Manager: Type Impv: NEW BRIDGE Remarks: 064-01-0047;STRU.IN POOR COND. JT W/064-02-0030 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 1 064-01 STPFLEX 800 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM) LAFOURCHE LA 1 064-02 NHPP 2,900 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.001623 - CREEK BRIDGE & IRISH BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 079-01-0034;USE NFA AS MATCH PHASES 1 TO 5 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 3049 079-01 NFA 900 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.001689 - TOPY CREEK BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 088-02-0023; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE LA 153 088-02 STPFLEX 1,831 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.001763 - LA 520: MIDDLE FORK BAYOU D'ARBONNE BRG. Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 101-01-0012; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CLAIBORNE LA 520 101-01 STPFLEX 898 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.001795 - RED CHUTE AND OLD CHANNEL BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 108-01-0019 AND 108-01-0017;USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 612 108-01 STPFLEX 3,632 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.001923 - FLAGON BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 149-02-0011; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 623 149-02 STPFLEX 1,916 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Page 122 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.002048 - LA 82 BRIDGES NEAR ESTHER Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 194-07-0056; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 82 194-07 STPFLEX 2,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.002070 - LA 14 BAYOU BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 196-01-0023;MULTI PIPE OR CULVERT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 14 196-01 STPFLEX 579 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.002133 - Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 213-02-0007; NFA AS MATCH PHASES 1 TO 5 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 705 213-02 NFA 2,628 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.002262 - DRAIN CANAL BRIDGE ON LA 45 Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 249-90-0037; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 45 249-90 STPFLEX 1,592 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.002281 - LA 66: BIG BAYOU SARA BRIDGE REHAB. Project Manager: Type Impv: BRIDGE REHABILITATION Remarks: 251-01-0018;STAGE 0 FEASIBILITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W FELICIANA LA 66 251-01 STPFLEX 4,106 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.002333 - LA 327: BAYOU PAUL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 257-02-0014; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 327 257-02 NFA 1,397 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.002423 - LA44: BLACK BAYOU BRIDGE REPLACEMENT Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 265-02-0016; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 44 265-02 STPFLEX 1,541 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.002562 - BAYOU LALOUTRE BRIDGE REHABILITATION Project Manager: Type Impv: STRUCTURAL/ELECTRICAL REPAIRS, CLEANING & PAINTING Remarks: 284-02-0032; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD LA 46 284-02 STPFLEX 3,500 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM) ST BERNARD LA 46 284-02 ER 800 OTHER / MISCELLANEOUS

Project: H.002798 - BAYOU TECHE BRIDGE(OAKLAWN) Project Manager: LISSARD, CHRIS Type Impv: BRIDGE REPLACEMENT Remarks: 408-30-0008;CG PERMIT SURV ORDERED IN METRIC (M Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY LA 323 408-30 STPFLEX 9,342 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Page 123 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.007939 - LA 378-S: INDIAN BAYOU BRIDGE & APPROACH Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 810-33-0002; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 378-S 810-33 STPFLEX 2,039 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.007940 - BAYOU LAFOURCHE CUTOFF BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 811-01-0009;USE NFA AS MATCH PHASES 1 TO 5 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL LA 847 811-01 NFA 3,083 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.008335 - LA 91 DRAINAGE CANAL BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 849-23-0009; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY LA 91 849-23 STPFLEX 1,032 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.010013 - US 84: LAS RAILROAD OVERPASS BR REHAB Project Manager: Type Impv: REHABILITATION OF RAILROAD BRIDGE OVERPASS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN US 84 022-02 NHPP 989 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.010014 - LA 1 OVER I-49 BRIDGE REHABILITATION Project Manager: Type Impv: BRIDGE OVERPASS REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 1 053-01 STPFLEX 5,201 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.010016 - US 11: LAKE PONTCHARTRAIN BR. REHAB PH 1 Project Manager: Type Impv: MAJOR BRIDGE REHABILITATION Remarks: PRIORITY BRIDGE PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 11 018-02 STPFLEX 25,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.010673 - US90Z:HARVEY CANAL TUNNEL REHABILITATION Project Manager: Type Impv: CLEANING, MECHANICAL, ELECTRICAL AND STRUCTURAL REHABILITRemarks: SEE NOTES FOR FUNDING INFO Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 90-Z 283-09 NHPP 12,700 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.010916 - PRIEN LAKE MAIN SPAN RE-DECKING Project Manager: Type Impv: REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-210 450-30 NHPP 10,300 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM) CALCASIEU I-210 450-30 NHPP 10,000 SUSTAINABILITY INTERSTATE

Project: H.011158 - LA 3139: RAMP-A OVER LA 3152 REPAIR Project Manager: Type Impv: REPLACE TWO PRESTRESSED CONCRETE GIRDERS AND ASSOCIATERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 3139 430-01 STPFLEX 375 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM) JEFFERSON LA 3139 430-01 REIMB 375 SUSTAINABILITY BRIDGE (ON SYSTEM)

Page 124 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.011190 - LA3213: MISS RIVER BR REHAB (GRAMERCY) Project Manager: Type Impv: REHABILITATE SUPERSTRUCTURE OF THE MAIN TRUSS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JAMES LA 3213 434-02 STPFLEX 1,500 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.011236 - I-10 OVER LA42 GIRDER REPLACEMENT Project Manager: Type Impv: REPLACE IMPACT DAMAGED GIRDER Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-10 450-10 REIMB 400 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM) E BATON ROUGE I-10 450-10 NHPP 100 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.011342 - EB OFF RAMP GIRDER RPL @ US 90 EXIT 182 Project Manager: Type Impv: GIRDER REPLACEMENT AND ASSOCIATED DECK AND RAIL Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASSUMPTION US 90 424-06 NHPP 392 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.011771 - N 19TH ST OVER I-110 GIRDER REPAIR Project Manager: Type Impv: STEEL GIRDER REPAIR. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-110 450-92 NHPP 500 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE (ON SYSTEM)

Project: H.000118 - BAYOU FIFI BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 001-03-0095; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER US 80 001-03 STPFLEX 1,019 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000163 - US 80 STEEP BAYOU BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 001-09-0089; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 80 001-09 STPFLEX 1,280 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000186 - US 90 OVER I-10 RAMPS @ LOCKMOOR Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 003-04-0064; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU US 90 003-04 STPFLEX 12,248 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000304 - I 10 - US 61 OVERPASS Project Manager: Type Impv: BRIDGE REHABILITATION Remarks: 007-01-0022;STAGE 0 PROJECT FEASIBILITY STUDY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 61 007-01 NHPP 4,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000337 - US 61:BAYOU MANCHAC & FRANCOIS BRS. Project Manager: Type Impv: NEW BRIDGES Remarks: 007-07-0058;JT W/007-08-0040 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION US 61 007-07 STPFLEX 1,700 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM) E BATON ROUGE US 61 007-08 STPFLEX 10,300 SUSTAINABILITY BRIDGE (ON SYSTEM)

Page 125 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.000358 - US 190 @ LA 415: LOBDELL INTERCHANGE Project Manager: Type Impv: NEW BRIDGE Remarks: 008-01-0051; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE US 190 008-01 NHPP 55,866 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000382 - SALINE BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 009-04-0010; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN US 71 009-04 STPFLEX 3,441 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM) NATCHITOCHES US 71 009-05 0 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.000425 - LA 12 SABINE RIVER BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 012-01-0004;JOINT PROJECT WITH TEXAS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 12 012-01 STPFLEX 4,346 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000428 - LA 12 BRIDGES Project Manager: Type Impv: NEW BRIDGES Remarks: 012-02-0036;6 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 12 012-02 STPFLEX 29,903 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000689 - LA 433: SALT BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 018-30-0024; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 433 018-30 FBROFF 2,250 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000754 - UNION PACIFIC R.R.OPASS NEAR TULLOS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 022-04-0033; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE US 84 022-04 NHPP 3,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.001133 - LA MIDLAND RR OVERPASS REPLACEMENT Project Manager: Type Impv: REPLACE RR OVERPASS/BRIDGE REMOVAL Remarks: 040-04-0030;DOES NOT QUALIFY FOR BR FUNDS.WANT TO REMO Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE LA 772 040-04 STPFLEX 687 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.001140 - LA 124: HOOTER CREEK BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 041-03-0025; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CATAHOULA LA 124 041-03 FBROFF 1,504 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.001146 - LA120: BRIDGES NEAR PROVENCAL Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 042-07-0022;2 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 120 042-07 FBROFF 2,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Page 126 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.001166 - CADDO LAKE BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 045-01-0029; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 1 045-01 STPFLEX 21,398 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.001498 - LA 24 & LA 316: COMPANY CANAL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 065-91-0017;STAGE 0 FEASIBILITY STUDY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 24 065-91 STPFLEX 16,700 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.001661 - BLACK BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 085-01-0022; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 530 085-01 FBROFF 2,356 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002101 - BR NEAR VILLE PLATTE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 202-01-0019; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage EVANGELINE LA 104 202-01 FBROFF 1,381 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002151 - BAYOU PARC PEROU AND CREEK BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 216-02-0016; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 734 216-02 FBROFF 1,525 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002238 - ROBINSON CANAL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 247-01-0009; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 56 247-01 NFA 1,200 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002260 - GOOSE BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 249-90-0035; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 45 249-90 STPFLEX 3,836 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002337 - LA 327-S: BAYOU FOUNTAIN Project Manager: Type Impv: NEW BRIDGE Remarks: 257-03-0025; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 327-S 257-03 STPFLEX 1,666 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002365 - LA 63 BRIDGES NEAR BLUFF CREEK Project Manager: Type Impv: NEW BRIDGES Remarks: 259-01-0011;3 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E FELICIANA LA 63 259-01 STPFLEX 5,497 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Page 127 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.002381 - LA 43 CREEK BRIDGE NEAR ALBANY Project Manager: Type Impv: NEW BRIDGE Remarks: 260-07-0025; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 43 260-07 STPFLEX 651 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002407 - PIGEON CREEK Project Manager: Type Impv: NEW BRIDGE Remarks: 262-30-0008; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST HELENA LA 63 262-30 STPFLEX 1,611 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002446 - LA 40: TCHEFUNCTE RIVER BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 269-07-0012; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 40 269-07 STPFLEX 3,260 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM) TANGIPAHOA LA 40 269-06 0 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.002631 - LA 834: OVERFLOW CREEK BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 329-03-0014; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE LA 834 329-03 FBROFF 1,555 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002650 - CASTOR,CASTOR RELIEF & DRAIN BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 345-03-0029;3 BRIDGES; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL LA 506 345-03 NFA 4,265 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002747 - LA 335 BRIDGES Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 396-02-0008;2 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 335 396-02 FBROFF 1,735 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002794 - VALENTINE CANAL BR. NEAR RACELAND Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 407-90-0018; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 308 407-90 FBROFF 1,421 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002893 - US 90 BRIDGE OVER LA 14 Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 424-04-0059;EAST AND WEST BOUND LANES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA US 90 424-04 NHPP 5,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.002896 - US90 FRTG ROAD DRAIN BR NEAR JEANERETTE Project Manager: Type Impv: NEW BRIDGE Remarks: 424-04-0064; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA US 90 424-04 NHPP 1,180 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM) IBERIA LA 668 399-02 STPFLEX 5 SUSTAINABILITY BRIDGE (ON SYSTEM)

Page 128 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.002980 - I-10 OVERPASS OVER US 165 & MP R.R Project Manager: Type Impv: NEW BRIDGES Remarks: 450-03-0085;PARALLEL BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS I-10 450-03 NHPP 30,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.003263 - I-20: OVERPASSES REHAB. (BOSSIER CITY) Project Manager: Type Impv: BRIDGES REHAB.; Remarks: 451-02-0097;APP SLAB.BACK WALL.REVETMENT.BEARNG Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER I-20 451-02 STPFLEX 4,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.008118 - BAYOU DUMAR & DRAIN CANAL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 829-12-0021; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 653 829-12 FBROFF 670 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.008190 - LA 1025: CREEK BR. NEAR FRIENDSHIP Project Manager: Type Impv: NEW BRIDGE Remarks: 832-29-0012; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 1025 832-29 STPFLEX 571 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.008226 - CHENIERE SPILLWAY & BRIDGE REPLACEMENT Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 837-12-0026; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 3033 837-12 STPFLEX 1,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.008278 - US 71:UP RR OVERPASS NEAR TIOGA Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 840-43-0016; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 71 840-43 NHPP 15,862 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.008332 - ROGUE BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 849-11-0010; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY LA 360 849-11 FBROFF 3,062 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.008469 - LA 835: BOEUF RIVER BRIDGE NEAR CONCORD Project Manager: Type Impv: NEW BRIDGE Remarks: 862-22-0006; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W CARROLL LA 835 862-22 STPFLEX 3,551 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.009122 - LA1204:BAYOU FLAGON & KITCHEN CR BRIDGES Project Manager: Type Impv: NEW BRIDGES Remarks: 840-31-0015; 3 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 1204 840-31 STPFLEX 3,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Page 129 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.009481 - LA 20 BAYOU CHEVREVIL BRIDGE Project Manager: Type Impv: BRIDGE REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JAMES LA 20 065-07 STPFLEX 821 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.009485 - LA 404: BAYOU CHOCTAW BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 404 405-01 STPFLEX 1,992 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.010004 - BAYOU TECHE MOVABLE BRIDGES REHAB Project Manager: Type Impv: MOVABLE BRIDGE REHABILITATION Remarks: NFA AS MATCH TO C.S. 823-12; TTF AS MATCH TO C.S 400-30 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 320 823-12 STPFLEX 3,642 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM) ST MARTIN LA 350 400-30 STPFLEX 4,199 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.010008 - LA 532 OVER I-20 BRIDGE REPLACEMENT Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER LA 532 860-07 FBROFF 3,517 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.010009 - LA 507 OVER I-20 BRIDGE REHABILITATION Project Manager: Type Impv: REPLACEMENT OF SUPERSTRUCTURE Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 507 308-04 FBROFF 3,247 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.010012 - I-20: US 80 OVERPASS BRIDGE REPLACEMENT Project Manager: Type Impv: REPLACEMENT OF BRIDGE OVERPASS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 80 001-09 STPFLEX 3,414 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.010612 - I-20 MRB SOIL AND SCOUR STABILIZATION Project Manager: Type Impv: IMP SLOPE & SOIL STABILITY AROUND PIERS E1 & E2 ADD RIP RAP Remarks: OTHER IS $ FROM MDOT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON I-20 451-09 NHPP 13,973 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM) MADISON 000-33 OTHER 13,973 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.010897 - I-20: MRB ISLAND ANCHORING PIER E1 Project Manager: Type Impv: REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON I-20 451-09 NHPP 13,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM) MADISON 000-33 OTHER 13,500 SUSTAINABILITY BRIDGE (ON SYSTEM)

Page 130 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.011094 - LA 3094: HEARNE AV BR REHAB Project Manager: Type Impv: REPLACE SUPERSTRUCTURE, RAISE GRADE, ROADWAY & EMBANKMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 3094 025-08 NHPP 2,700 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.011484 - US80: RED RIVER BR. TEXAS ST. REHAB (HB) Project Manager: Type Impv: CLEANING AND PAINTING, AND STRUCTURAL REPAIRS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER US 80 001-03 NHPP 5,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.011485 - LA336-1: BAYOU TECHE BRIDGE REHAB (HB) Project Manager: Type Impv: CLEANING AND PAINTING, AND STRUCTURAL REPAIRS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 336-1 056-04 NHPP 1,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.011487 - LA 182: BERWICK BAY BRIDGE REHAB Project Manager: Type Impv: BRIDGE CLEANING, PAINTING AND STRUCTURAL REPAIRS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY LA 182 005-01 STPFLEX 15,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.011494 - US 90: ATCHAFALAYA RIVER BRIDGE REHAB Project Manager: Type Impv: BRIDGE CLEANING, PAINTING AND STRUCTURAL REPAIRS. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY US 90 424-05 NHPP 21,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.011705 - US 11: LAKE PONTCHARTRAIN BR. REHAB PH 2 Project Manager: Type Impv: REHAB THE MOVABLE SPANS ON THE US 11 BRIDGE OVER LAKE PO Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 11 018-02 STPFLEX 25,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.011720 - US 90 DRAINAGE CANAL NO.2 EROSION REPAIR Project Manager: Type Impv: DRIVING SHEET PILES AND REPAIRING FAILED EMBANKMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE US 90 424-07 NHPP 500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.011808 - LA 10: PALMETTO COMPANY CANAL BR Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY LA 10 219-07 STPFLEX 1,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE (ON SYSTEM)

Project: H.000133 - US 80 OVERPASS @ KCS RR Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 001-07-0026; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN US 80 001-07 STPFLEX 22,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Page 131 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.000263 - CHEF MENTEUR PASS BRIDGE & APPROACH Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 006-05-0067;STAGE 1 PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90 006-05 STPFLEX 85,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.000284 - US 90: PEARL RIVER BRIDGES Project Manager: Type Impv: NEW BRIDGES Remarks: 006-07-0048; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 90 006-07 STPFLEX 24,382 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.000286 - EAST PEARL RIVER BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 006-08-0031;STAGE 0 PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 90 006-08 STPFLEX 15,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM) ST TAMMANY US 90 006-07 0 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.000413 - CROSS BAYOU BRIDGE REPLACEMENT Project Manager: Type Impv: BRIDGE REHAB Remarks: 011-01-0054;STAGE 0 - FUTURE REHAB PROJECT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO US 71 011-01 NHPP 2,800 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.000445 - MISSOURI PACIFIC R.R. OVERPASS Project Manager: Type Impv: BRIDGE REHAB.REDECK & MAYBE WIDEN Remarks: 012-13-0101; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY US 190 012-13 NHPP 6,500 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.000665 - UP R.R. OVERPASS NEAR BONITA Project Manager: Type Impv: NEW BRIDGE Remarks: 016-05-0031; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE US 165 016-05 STPFLEX 8,926 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.000688 - US 11 NORFOLK SOUTHERN R.R.OVERPASS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 018-04-0049; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 11 018-04 STPFLEX 21,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.000986 - SABINE RIVER BR (BURR FERRY) Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 029-01-0004;ADMIN. BY TEXAS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 8 029-01 STPFLEX 12,700 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001234 - PORT ALLEN CANAL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 050-07-0066;2 STRUCTURES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 1 050-07 NHPP 60,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Page 132 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.001271 - CANE RIVER BRIDGE AT CHURCH STREET Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 053-04-0031;STAGE 0 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 1-X 053-04 STPFLEX 4,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001537 - LA 4: BEE BRANCH BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 067-03-0014; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE LA 4 067-03 STPFLEX 1,310 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001553 - LA 146 BRIDGES NEAR KELLEYS Project Manager: Type Impv: NEW BRIDGES Remarks: 068-02-0017;3 BRIDGES & JT W/068-03-0021 2BRS. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON LA 146 068-02 STPFLEX 4,696 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM) JACKSON LA 4 068-03 STPFLEX 2,954 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.001666 - DORCHEAT BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 085-05-0029; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER LA 160 085-05 FBROFF 4,100 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001674 - LA 146 BRIDGES NEAR HOMER Project Manager: Type Impv: NEW BRIDGES Remarks: 085-08-0032;4 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CLAIBORNE LA 146 085-08 STPFLEX 6,068 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001679 - LA 146 BRIDGES NEAR VIENNA Project Manager: Type Impv: NEW BRIDGES Remarks: 085-09-0017;3 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 146 085-09 STPFLEX 3,569 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001707 - SALINE BAYOU RELIEF BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 090-05-0030; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE LA 507 090-05 FBROFF 1,178 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001711 - SALINE BAYOU RELIEF & MILL CR. BRS. Project Manager: Type Impv: NEW BRIDGES Remarks: 091-05-0014;2 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN LA 126 091-05 STPFLEX 3,023 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001761 - LA 507 CREEK BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 100-02-0013; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RED RIVER LA 507 100-02 FBROFF 2,133 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Page 133 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.001798 - PARMERS CREEK BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 111-01-0018; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER LA 531 111-01 STPFLEX 1,843 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001820 - LA 485 BRIDGES NEAR ALLEN Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 115-01-0017;4 NEW BRIDGES.JT W/115-02-0011 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 485 115-01 FBROFF 5,159 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM) NATCHITOCHES LA 485 115-02 FBROFF 2,085 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.001842 - LA 471: DARTIGO CREEK & CREEK BRIDGES Project Manager: Type Impv: NEW BRIDGE Remarks: USE NFA FUNDS TO PAY FOR MITIGATION UNTIL FEMA REIMBURS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage GRANT LA 471 123-01 FEMA 3,534 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001881 - LA 392 BRIDGES NEAR HORNBECK Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 135-02-0009;2 BRIDGES; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 392 135-02 FBROFF 3,560 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001961 - JOES BAYOU & CARRAWAY LAKE BRIDGES Project Manager: Type Impv: NEW BRIDGES Remarks: 161-08-0022;2 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E CARROLL LA 134 161-08 STPFLEX 2,873 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001970 - BOEUF RIVER BRIDGE NEAR HEBERT Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 166-03-0015; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 561 166-03 FBROFF 7,011 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.001972 - MUDDY BAYOU BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 167-02-0016; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 135 167-02 STPFLEX 1,128 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.002091 - LA 97 OVERPASS (I-10) Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 201-01-0008;PROJECT TO BE SCOPED Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS LA 97 201-01 STPFLEX 6,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.002176 - BAYOU HA HA & PALMETTO CO.CANAL BRS Project Manager: Type Impv: NEW BRIDGES Remarks: 219-07-0025;2 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY LA 10 219-07 STPFLEX 4,950 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Page 134 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.002184 - BAYOU CHENAL & BAYOU DISCHARGE BRS. Project Manager: Type Impv: NEW BRIDGES Remarks: 227-04-0019;2 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage POINTE COUPEE LA 413 227-04 STPFLEX 4,395 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.002244 - BOUDREAUX CANAL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 247-02-0030; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 56 247-02 STPFLEX 30,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.002375 - AMITE R.BR. NEAR FRENCH SETTLEMENT Project Manager: Type Impv: NEW BRIDGE Remarks: 260-02-0040; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 16 260-02 STPFLEX 23,124 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.002567 - REGGIO CANAL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 284-30-0023; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD LA 300 284-30 FBROFF 1,834 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.002735 - BAYOU VERMILION BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 391-04-0018; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 1252 391-04 FBROFF 2,335 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.003931 - CALCASIEU RIVER BRIDGE Project Manager: Type Impv: FEASIBILITY & ENVIRON. STUDY Remarks: 700-10-0115;INCL. UPRR GRADE SEPARATION Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-10 450-91 NFI 0 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM) CALCASIEU LA 378 810-12 0 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.007873 - BAYOU BOEUF & TURNER CANAL BRIDGES Project Manager: HERATH, ANANDA Type Impv: BRIDGE REPLACEMENT Remarks: 805-09-0007;2 BRIDGES; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES LA 1176 805-09 FBROFF 2,375 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.007963 - BLACKWATER BAYOU BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 817-05-0017; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 410 817-05 STPFLEX 1,811 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.008161 - CALVIN CREEK BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 831-14-0005; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 3072 831-14 FBROFF 1,199 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Page 135 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.008170 - LA 1024 CREEK BRS. NEAR FRIENDSHIP Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 832-10-0019;2 BRIDGES; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 1024 832-10 FBROFF 1,302 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.008203 - LA 835 CREEK BRIDGES Project Manager: Type Impv: NEW BRIDGES Remarks: 834-07-0022;2 BRIDGES Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE LA 835 834-07 STPFLEX 2,892 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.008230 - LA 838 STEEP BAYOU BRIDGE Project Manager: Type Impv: NEW BRIDGE Remarks: 837-14-0009; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 838 837-14 STPFLEX 1,055 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.008288 - BOEUF RIVER BRIDGE NEAR BUCKNER Project Manager: Type Impv: BRIDE REPLACEMENT Remarks: 842-13-0009; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 132 842-13 FBROFF 3,672 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.008312 - LA 1042 BRIDGES NEAR GREENSBURG Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 846-03-0014;2 BRIDGES; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST HELENA LA 1042 846-03 FBROFF 2,161 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.008358 - BLACK BAYOU BR. NEAR MADISONVILLE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 852-13-0017; USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 1077 852-13 FBROFF 1,391 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.008411 - BAYOU TERREBONNE BR (LA 660) Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 855-07-0010; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 660 855-07 STPFLEX 507 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.008449 - DRAIN BRIDGE NEAR STONEY POINT Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 859-04-0010;USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 450 859-04 FBROFF 1,093 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.009296 - QUAD BEAM SPECIAL DETAILS Project Manager: Type Impv: PREPARE QUAD BEAM SPECIAL DETAILS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Page 136 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.009470 - LA 82: SUPERIOR CANAL BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT - MOVEABLE BRIDGE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CAMERON LA 82 194-02 STPFLEX 11,161 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.009482 - LA 113: JIM BURNEY BRANCH BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BEAUREGARD LA 113 139-03 STPFLEX 950 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.009484 - LA 75: BAYOU BREAUX BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 75 257-01 FBROFF 1,381 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.009486 - US 90: BAYOU BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS US 90 003-07 STPFLEX 1,370 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.009489 - US 61: JEFFERSON HIGHWAY OVERPASS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61 007-90 NHPP 6,854 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.009497 - LA 106: BAYOU BOEUF BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES LA 106 204-04 STPFLEX 2,600 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.009498 - LA 121: CALCASIEU RIVER BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: 029-05 USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 121 029-05 FBROFF 8,900 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.010005 - VERMILLION RIVER MOVABLE BRIDGES REHAB Project Manager: Type Impv: MOVABLE BRIDGE REHABILITATION Remarks: CONTROL SECTION 828-14 IS IN URBANIZED AREA, THE OTHER N Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 733 828-14 STPFLEX 4,568 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM) VERMILION LA 82 194-07 STPFLEX 3,418 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.010006 - LA 182 & LA 58: MOVABLE BRIDGE REHAB Project Manager: Type Impv: MOVABLE BRIDGE REHABILITATION Remarks: BOTH CONTROL SECTIONS IN HOUMA MPO AREA. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 182 005-07 STPFLEX 5,089 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM) TERREBONNE LA 58 247-30 STPFLEX 4,253 SUSTAINABILITY BRIDGE (ON SYSTEM)

Page 137 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: H.010015 - LA 143: BAYOU D'ARBONNE BRIDGE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 143 315-02 STPFLEX 626 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.010017 - US 90Z: WESTBANK EXPRESSWAY REHAB Project Manager: Type Impv: MAJOR BRIDGE REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 90-Z 283-09 NHPP 12,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.010018 - I-10: NO EAST DRAIN CANAL BRIDGE REPLACE Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-90 NHPP 11,758 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.010616 - I 20: LA 544 OVERPASS REPLACEMENT Project Manager: Type Impv: OVERPASS REHABILITATION Remarks: NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 544 296-03 FBROFF 4,807 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.010885 - LA 91: BAYOU PLAQUEMINE BRULE BR REPLACE Project Manager: Type Impv: REPLACEMENT OF PONTOON BRIDGE Remarks: CONSTRUCTION FUNDS WILL BE STATE BONDS Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 91 801-09 0 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: H.011717 - LA 70: SUNSHINE BRIDGE PIER PROTECTION Project Manager: Type Impv: PIER PROTECTION SYSTEM Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JAMES LA 70 426-02 0 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE (ON SYSTEM)

Project: L.000010 - URGENT BRIDGE REPAIR/REPLACEMENT Project Manager: Type Impv: REIMBURSABLE AND NON-REIMBURSABLE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - REIMB 5,000 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 BRIDGE (ON SYSTEM) - NHPP 1,000 SUSTAINABILITY BRIDGE (ON SYSTEM) - STPFLEX 1,000 SUSTAINABILITY BRIDGE (ON SYSTEM) - STCASH 1,000 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: L.000011 - BRIDGE PREVENTIVE MAINTENANCE Project Manager: Type Impv: MAINTENANCE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 1,500 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 BRIDGE (ON SYSTEM) - STPFLEX 1,500 SUSTAINABILITY BRIDGE (ON SYSTEM) - STCASH 1 SUSTAINABILITY BRIDGE (ON SYSTEM)

Page 138 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE (ON SYSTEM) Project: L.000012 - BRIDGE PAINTING PROGRAM Project Manager: Type Impv: MISC SITES Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 1,000 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 BRIDGE (ON SYSTEM) - STCASH 1 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: L.000040 - FEDERAL BRIDGE INSPECTION PROGRAMS Project Manager: Type Impv: INSPECTIONS, RATINGS, LOAD FACTORS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 3,000 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 BRIDGE (ON SYSTEM) - STCASH 600 SUSTAINABILITY BRIDGE (ON SYSTEM)

Page 139 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE PREVENTIVE MAINTENANCE Project: H.000792 - DIST 08 BRIDGE DK OVERLAYS & PAINTING Project Manager: Type Impv: BRIDGE DECK EPOXY OVERLAYS & PAINTING Remarks: 023-01-0073;BRPM Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 08 000-98 STPFLEX 10,600 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE PREVENTIVE MAINTENANCE

Project: H.003182 - IHNC AND ALGIERS CUTOFF BRIDGE REHAB Project Manager: Type Impv: FINGER JOINTS,ROCKER BEARINGS & DECK OVERLAY Remarks: 450-90-0246; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-90 NHPP 7,578 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE PREVENTIVE MAINTENANCE ORLEANS LA 407 836-08 NHPP 754 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE

Project: H.003244 - DIST 04 BRIDGE BRG REHAB & MISC REPAIRS Project Manager: Type Impv: BRIDGE BEARING REPAIRS Remarks: 451-01-0135;BRPM Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER I-220 451-31 NHPP 2,450 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE PREVENTIVE MAINTENANCE DISTRICTWIDE 04 000-94 STPFLEX 1,670 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE

Project: H.010636 - US 90 OVER MISS RVR (GNO2)-CLEAN & PAINT Project Manager: Type Impv: BRIDGE REPAIRS, CLEANING & PAINTING Remarks: CCCD TOLL CREDITS AS MATCH PHASE 6 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90-Z 283-08 NHPP 16,581 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 BRIDGE PREVENTIVE MAINTENANCE

Project: H.000351 - DIST 61 BRIDGE DK JT & MISC REPAIRS Project Manager: Type Impv: GROUT. REMOVE. REPLACE BEARINGS Remarks: 007-90-0029;BRPM Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 61 000-96 STPFLEX 2,184 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE PREVENTIVE MAINTENANCE

Project: H.006713 - DIST 03 BRIDGE JT REPAIRS & OVERLAY Project Manager: Type Impv: DECK JT REPAIRS & DECK OVERLAY Remarks: 737-93-0074;BRPM Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARY US 90 424-05 NHPP 400 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE PREVENTIVE MAINTENANCE DISTRICTWIDE 03 000-93 NHPP 600 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE ST LANDRY US 190 008-04 NHPP 200 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE ASSUMPTION LA 182 005-02 NHPP 1,250 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE

Project: H.009319 - I-10 OVERPASS BRIDGES CLEAN & PAINT Project Manager: Type Impv: BRIDGE PAINTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS I-10 450-03 FBR-ON/OFF 345 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE PREVENTIVE MAINTENANCE ACADIA I-10 450-04 FBR-ON/OFF 957 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE CALCASIEU I-10 450-91 FBR-ON/OFF 1,268 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE

Page 140 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE PREVENTIVE MAINTENANCE Project: H.011482 - US 90 HUEY P. LONG BRIDGE CLEAN & PAINT Project Manager: Type Impv: CLEANING & PAINTING BRIDGE STEEL NOT PART OF THE WIDENING.Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 90 006-01 NHPP 20,100 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE PREVENTIVE MAINTENANCE

Project: H.011486 - I-20: BRIDGE REHABILITATION (MONROE) Project Manager: Type Impv: BEARING REHABILITATION,STRUCTURAL REPAIRS, AND SPOT PAINTIRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA I-20 451-06 NHPP 13,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 BRIDGE PREVENTIVE MAINTENANCE

Project: H.009455 - I-210 BRIDGE CLEANING & PAINTING Project Manager: Type Impv: CLEANING & PAINTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-210 450-30 NHPP 3,400 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE PREVENTIVE MAINTENANCE

Project: H.009461 - I-10 ATCHAFALAYA FLDWY CLEAN & PAINT Project Manager: Type Impv: CLEANING & PAINTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN I-10 450-06 NHPP 4,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE PREVENTIVE MAINTENANCE IBERVILLE I-10 450-07 NHPP 6,520 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE

Project: H.010007 - LA 70 PIERRE PART BAY BRIDGE CLN & PAINT Project Manager: Type Impv: CLEANING & PAINTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASSUMPTION LA 70 232-01 STPFLEX 400 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE PREVENTIVE MAINTENANCE

Project: H.010020 - I-110 BRIDGE OVER LA 67 CLEAN & PAINT Project Manager: Type Impv: CLEANING & PAINTING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-110 450-92 NHPP 650 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE PREVENTIVE MAINTENANCE

Project: H.011766 - DIST 05 BRIDGE PAINTING & MISC REPAIRS Project Manager: Type Impv: BRIDGE PAINTING, SPALL REPAIRS & DECK JOINT RE-SEALING. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 05 000-95 STPFLEX 2,600 SUSTAINABILITY 3-DESIGN/DEVELOPMENT BRIDGE PREVENTIVE MAINTENANCE

Project: H.009327 - I-10/110 EPOXY BR DECK OVERLAY-BTN ROUGE Project Manager: Type Impv: EXPOXY BRIDGE DECK OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-10 450-10 NHPP 8,250 SUSTAINABILITY 2-WAITING FOR FUNDING BRIDGE PREVENTIVE MAINTENANCE E BATON ROUGE I-110 450-92 NHPP 750 SUSTAINABILITY BRIDGE PREVENTIVE MAINTENANCE

Project: H.000790 - US 167 BRIDGE MAINTENANCE Project Manager: Type Impv: BRIDGE MAINTENANCE Remarks: 023-01-0069;BRPM Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 167 023-01 NHPP 3,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE PREVENTIVE MAINTENANCE

Page 141 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - BRIDGE PREVENTIVE MAINTENANCE Project: H.010000 - US171 CALCASIEU RVR BRIDGE CLEAN & PAINT Project Manager: Type Impv: CLEANING & PAINTING & MISC. REPAIRS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU US 171 024-01 NHPP 1,700 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE PREVENTIVE MAINTENANCE

Project: H.010001 - LA27 ICWW ELLENDERS BRIDGE CLEAN & PAINT Project Manager: Type Impv: CLEANING & PAINTING & MISC. REPAIRS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 27 031-04 STPFLEX 1,800 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL BRIDGE PREVENTIVE MAINTENANCE

Page 142 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - INTERSTATE Project: H.009494 - I-49 FRONTAGE ROADS:I-10 - ST.LANDRY P/L Project Manager: Type Impv: COLD PLANE, PATCH, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE I-49 455-01 STPFLEX 9,230 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 INTERSTATE

Project: H.009546 - I-20: DIST 05 CRACK & JOINT SEAL & PATCH Project Manager: Type Impv: CRACK SEAL, JOINT SEAL & PATCHING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 05 000-95 NHPP 11,198 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 INTERSTATE

Project: H.009598 - I-55: END OF ELEVATED ROADWAY - US 51 Project Manager: Type Impv: ROADWAY MAINTENANCE RESTORATION & REHAB Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA I-55 452-90 NHPP 4,693 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 INTERSTATE

Project: H.010488 - I-49: 0.32 MI S LA 181-0.44 MI N US 167 Project Manager: Type Impv: PATCH,COLD PLANE, & OVERLAY(MAINLINE SHOULDERS & RAMPS) Remarks: USE NFA AS MATCH FOR C.S. 372-05 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES I-49 455-05 NHPP 1,650 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 INTERSTATE RAPIDES LA 181 372-05 STPFLEX 215 SUSTAINABILITY INTERSTATE RAPIDES LA 181 372-05 STPFLEX 370 SUSTAINABILITY NON-INTERSTATE

Project: H.011241 - I-20: AIRLINE DRIVE RAMP EXTENSION Project Manager: Type Impv: ON-RAMP EXTENSION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER I-20 451-02 NHPP 550 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 INTERSTATE

Project: H.003298 - ROAD INTERCHANGE & I-20 FRONTAGE RD Project Manager: Type Impv: NEW CONC PVMT TARBUTTON RD OVERPASS Remarks: 451-05-0115;STAGE 3 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN I-20 451-05 TCSP 0 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE LINCOLN I-20 451-05 IM DISCR 0 SUSTAINABILITY INTERSTATE LINCOLN I-20 451-05 DEMO 3,186 DEMO / HIGH PRIORITY

LINCOLN I-20 451-05 STGEN 250 SUSTAINABILITY INTERSTATE LINCOLN I-20 451-05 STBONDS 10,864 SUSTAINABILITY INTERSTATE

Project: H.009575 - I-20:TEXAS STATE LINE TO MONKHOUSE DR. Project Manager: Type Impv: COLD PLANE & OVERLAY AND PCCP PATCHING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-20 451-01 NHPP 7,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.009576 - I-49: DESOTO PARISH LINE TO LA 526 Project Manager: Type Impv: PCC PATCHING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-49 455-08 NHPP 900 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Page 143 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - INTERSTATE Project: H.009593 - I-10,I-12,I-55,I-59:DISTRICTWIDE SPOT RP Project Manager: Type Impv: ROADWAY MAINTENANCE RESTORATION & REHAB Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 62 000-90 NHPP 1,500 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.009595 - I-12:LIVINGSTON PAR APPROACH SLAB REP P2 Project Manager: Type Impv: ROADWAY MAINTENANCE RESTORATION & REHAB Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON I-12 454-02 NHPP 12,810 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.009596 - I-10&I-12:ST.TAMMAY PAR APR SLAB REPAIRS Project Manager: Type Impv: ROADWAY MAINTENANCE RESTORATION & REHAB Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-10 450-18 NHPP 750 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE ST TAMMANY I-12 454-04 NHPP 750 SUSTAINABILITY INTERSTATE

Project: H.010402 - I-10: WILLIAMS BLVD - VETERANS BLVD Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON I-10 450-15 NHPP 4,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.010480 - I-20: 0.4 MI W LA 531 TO BIENVILLE P/L Project Manager: Type Impv: COLD PLANE AND ASPHALTIC OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER I-20 451-03 NHPP 12,480 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.010489 - I-49: LA 106 - LA 115 (RAMPS & SIDE RD) Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY (RAMPS AND SIDE ROAD) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES I-49 455-04 NHPP 487 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE AVOYELLES LA 106 204-04 STPFLEX 503 SUSTAINABILITY INTERSTATE AVOYELLES LA 106 204-04 STPFLEX 600 SUSTAINABILITY NON-INTERSTATE

Project: H.011250 - I-20: DELTA SCALES - MS RIVER BRIDGE Project Manager: Type Impv: REPLACE CONCRETE ROADWAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON I-20 451-08 NHPP 4,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.011550 - I-49:LA 93 OPASS - 0.26 MI N LA 93 OPASS Project Manager: Type Impv: CONCRETE REMOVAL & REPLACEMENT, STONE BASE, SHLDER UNDERemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY I-49 455-02 NHPP 75 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Page 144 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - INTERSTATE Project: H.011609 - I-10: US 11 DECELERATION LANE EXTENSION Project Manager: Type Impv: EXTENDING THE EXISTING DECELERATION EXIT LANE TO US 11 FROMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS I-10 450-90 NHPP 300 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.011620 - I-20: WALNUT BAYOU - EAST OF US 65 RAMPS Project Manager: Type Impv: CONCRETE PAVEMENT REHABILITATION AND UNDERDRAIN SYSTEMRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON I-20 451-08 NHPP 7,500 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.011622 - I-910: RAMPS NEAR SUPERDOME/CLAIBORNE Project Manager: Type Impv: PCC REHABILITATION; RESURFACING ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90-Z 283-08 NHPP 500 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 INTERSTATE

Project: H.003003 - I-10: E. JCT. I-49 TO LA 328 Project Manager: Type Impv: RUBBLIZE AND OVERLAY AND WIDEN TO 3 LANES IN EACH DIRECTIORemarks: 450-05-0062;450-06-0068 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE I-10 450-05 NHPP 34,666 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE LAFAYETTE I-10 450-05 NHPP 14,058 SUSTAINABILITY BRIDGE (ON SYSTEM) LAFAYETTE I-10 450-05 NHPP 29,791 CORRIDOR

ST MARTIN I-10 450-06 NHPP 17,504 CORRIDOR

ST MARTIN I-10 450-06 NHPP 5,133 SUSTAINABILITY BRIDGE (ON SYSTEM) ST MARTIN I-10 450-06 NHPP 20,109 SUSTAINABILITY INTERSTATE

Project: H.003014 - I-10: LA 347 TO ATCHAFALAYA FLDWY BR Project Manager: Type Impv: REHABILITATION Remarks: 450-06-0068; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN I-10 450-06 NHPP 23,184 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE ST MARTIN I-10 450-06 NHPP 169 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: H.003425 - I-12: LA 63 - TANGIPAHOA PARISH LINE Project Manager: Type Impv: C.P. AND OVERLAY Remarks: 454-02-0077; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON I-12 454-02 NHPP 7,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.009594 - I-10:RESERVE RELIEF CANAL - I-55 NB RAM Project Manager: Type Impv: ROADWAY MAINTENANCE RESTORATION & REHAB Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN I-10 450-13 NHPP 10,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.009597 - I-10: W PEARL RIVER BR - PEARL RIVER BR Project Manager: Type Impv: ROADWAY MAINTENANCE RESTORATION & REHAB Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-10 450-18 NHPP 3,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Page 145 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - INTERSTATE Project: H.009620 - I-10:WEST OF LA 108 TO 1-210 INTERCHANGE Project Manager: Type Impv: RUBBLIZE & OVERLAY, REPLACE AT UNDERPASS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-10 450-91 NHPP 15,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.009621 - I-210: W JCT I-10 - E JCT I-10 Project Manager: Type Impv: OGFC Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU I-210 450-30 NHPP 3,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.010319 - I-110: NORTH ST. - PLANK RD. Project Manager: Type Impv: RECONSTRUCT JCP @ GRADE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE I-110 450-92 NHPP 21,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.010468 - I-20: WEST END HUDSON ST. BRIDGE TO I-49 Project Manager: Type Impv: REMOVE AND REPLACE PCC Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-20 451-01 NHPP 15,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.010475 - I-20: MONKHOUSE TO W END OF HUDSON ST BR Project Manager: Type Impv: REMOVE AND REPLACE PCC Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO I-20 451-01 NHPP 20,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.010989 - I-20: LINCOLN/OUACHITA P. RAMP REHAB Project Manager: Type Impv: RE-SURFACE SELECTED I-20 RAMPS IN LINCOLN & OUACHITA PARISHRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA I-20 451-06 NHPP 2,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE LINCOLN I-20 451-05 NHPP 1,500 SUSTAINABILITY INTERSTATE

Project: H.010991 - I-12: LIVINGSTON P/L - US 51 BUS OPASS Project Manager: Type Impv: MILL, OVERLAY AND PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA I-12 454-03 NHPP 10,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.010992 - I-12: I-12 INTERSTATE RAMP REPAIR Project Manager: Type Impv: PATCHING AND STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON I-12 454-02 NHPP 5,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.010993 - I-10: TWIN SPANS - FRENCH BRANCH Project Manager: Type Impv: MILL, OVERLAY, GUARDRAIL AND PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-10 450-18 NHPP 10,993 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Page 146 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - INTERSTATE Project: H.010994 - I-12: BAYOU LACOMBE - NORTHSHORE BLVD. Project Manager: Type Impv: MILL, OVERLAY, GUARDRAIL AND PAVEMENT MARKINGS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY I-12 454-04 NHPP 5,830 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.011077 - I-20: MOUND TO DELTA SCALES PHASE 2 Project Manager: Type Impv: COLD PLANE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON I-20 451-08 NHPP 6,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.011536 - I-49: 0.44 MI N US 167 TO EXIT 80 Project Manager: Type Impv: PATCH, COLD PLANE, & OVERLAY I-49 SHOULDERS AND RAMPS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES I-49 455-05 NHPP 4,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.011565 - I-49: N OF LA 498 TO 0.66 MI E LA 1200 Project Manager: Type Impv: PATCH, MILL, OLY (I-49 MAINELINE, SHOULDERS & RAMPS) & SIDE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES I-49 455-05 NHPP 7,400 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE RAPIDES 000-40 NHPP 340 SUSTAINABILITY INTERSTATE

Project: H.011569 - I-49: NORTH OF LA 8 TO NATCHITOCHES P/L Project Manager: Type Impv: PATCH, MILL, & OLY (I-49 MAINLINE SHOULDERS, RAMP & SIDE RD) Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES I-49 455-05 NHPP 1,700 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE RAPIDES 000-40 NHPP 350 SUSTAINABILITY INTERSTATE

Project: H.011611 - I-10: CAUSEWAY BLVD. - ORLEANS P/L Project Manager: Type Impv: COLD PLANE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON I-10 450-15 NHPP 2,250 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.011621 - I-20: LA 133 - US 425 Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND I-20 451-07 NHPP 7,400 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.011623 - I-20: LA 577 - WALNUT BAYOU Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON I-20 451-08 NHPP 14,200 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Project: H.011627 - I-20: BIENVILLE P/L - 1 MILE WEST LA 149 Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN I-20 451-05 NHPP 11,900 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE

Page 147 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - INTERSTATE Project: H.011628 - I-20: LA 17 - LA 577 Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON I-20 451-08 NHPP 6,395 SUSTAINABILITY 3-DESIGN/DEVELOPMENT INTERSTATE RICHLAND I-20 451-07 NHPP 1,305 SUSTAINABILITY INTERSTATE

Project: H.003251 - I-20 (HAMILTON RD TO AIRLINE DR) Project Manager: Type Impv: REMOVE & REPLACE PCC Remarks: 451-02-0078; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER I-20 451-02 IM 23,500 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL INTERSTATE

Project: H.011319 - I-20: AIRLINE DR. TO I-220 Project Manager: Type Impv: INTERSTATE WIDENING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER I-20 451-02 NFI 94,907 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL INTERSTATE BOSSIER I-20 451-02 NFI 40,919 CAPACITY

BOSSIER I-20 451-02 NFI 19,977 SUSTAINABILITY BRIDGE (ON SYSTEM)

Project: L.000002 - INTERSTATE PAVEMENT PREVENTIVE MAINT Project Manager: Type Impv: SURFACE IMP, PM, REPAIR FOR PAVEMENT/EMBANKMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NHPP 1,000 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 INTERSTATE

Page 148 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.001148 - LA 154: LA 792 TO LA 507 Project Manager: Type Impv: WIDENING WITH THIN OVERLAY Remarks: 043-02-0017; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE LA 154 090-04 STPFLEX 1,855 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE

Project: H.009569 - LA 182: MAIN ST - LA 316 Project Manager: Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 182 005-05 STPFLEX 2,025 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE

Project: H.009610 - LA 133: LA 4 - LA 561 Project Manager: Type Impv: ASPHALT OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL LA 133 166-01 STPFLEX 2,714 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE

Project: H.009649 - LA 67: US 61/190 - LA 3006 Project Manager: Type Impv: PCCP PATCHING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 67 060-01 STPFLEX 2,767 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE E BATON ROUGE LA 67 060-02 STPFLEX 2,133 SUSTAINABILITY NON-INTERSTATE

Project: H.010602 - LA 1: LA 69 - LA 75 Project Manager: Type Impv: PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 1 050-06 STBONDS 10,000 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE IBERVILLE LA 1 050-06 NHPP 100 SUSTAINABILITY NON-INTERSTATE

Project: H.011009 - US 84: US 171 TO LA 175 SOUTH Project Manager: Type Impv: MILL AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO US 84 021-03 NHPP 525 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE

Project: H.011240 - LA 147: UNION CHURCH RD TO LINCOLN P/L Project Manager: Type Impv: ASPHALTIC OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE LA 147 043-02 STPFLEX 2,600 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE

Project: H.011312 - US 90: MEDIAN CROSSOVER IMPROVEMENTS Project Manager: Type Impv: ADD LEFT TURN LANES AT MEDIAN CROSSOVERS AND CLOSING OT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES US 90 005-08 STGEN 1,080 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE ST CHARLES US 90 005-09 STGEN 84 SUSTAINABILITY NON-INTERSTATE

Page 149 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.002311 - LA 38 - MISSISSIPPI STATE LINE Project Manager: Type Impv: COLD PLANE.BASE.DRAINAGE & OLAY Remarks: 254-07-0009; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST HELENA LA 43 254-07 STPFLEX 3,790 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009547 - JCT US 190 - S. JCT LA 40 Project Manager: Type Impv: MAINTENANCE RESTORATION & REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 445 278-02 STPFLEX 3,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009548 - E. BATON ROUGE PARISH LINE - W JCT LA 16 Project Manager: Type Impv: MAINTENANCE RESTORATION & REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON US 190 013-06 NHPP 1,211 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009559 - LA 156: MAMMY TRAIL - LA 479 Project Manager: Type Impv: CTB AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 156 092-01 STPFLEX 2,813 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009570 - US 61:TRANSCONTINENTAL DR - DAVID DR Project Manager: Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 61 007-02 NHPP 1,469 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009572 - LA 39:JUDGE SEEBER BR-ST BERNARD P/L Project Manager: Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS LA 39 046-31 NHPP 1,406 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009586 - LA 4: LA 578 - BAYOU MACON BRIDGE Project Manager: Type Impv: ASPHALT CONCRETE OVERLAY OVER IN PLACE STABILIZATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage FRANKLIN LA 4 036-04 STPFLEX 1,218 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009588 - LA 125: LA 3259 - ALPS ROAD Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE LA 125 131-01 STPFLEX 1,518 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009611 - US 90: EDGERLY - SULPHUR Project Manager: Type Impv: CP 2", PATCH , OVERLAY 4" Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU US 90 003-03 STPFLEX 3,825 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Page 150 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.009660 - LA 311/312: US 90 - LA 24 Project Manager: Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 312 413-30 STPFLEX 844 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009661 - LA 406: DONNER CANAL BR - STANTON RD Project Manager: Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS LA 406 409-02 STPFLEX 823 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009663 - LA 47: I-10 - BULLARD RD. Project Manager: Type Impv: PCC PATCHING AND JOINT SEALING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS LA 47 148-03 STPFLEX 1,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.009707 - LA 112: LA 113 - E DAVIS ROAD Project Manager: Type Impv: STABILIZE AND OVERLAY Remarks: APPLIED FOR STBONDS. DID NOT MAKE LIST. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 112 141-03 NFI 3,400 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010219 - LA 104: ALLEN P/L - LA 3277 Project Manager: Type Impv: STABLIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage EVANGELINE LA 104 200-02 STPFLEX 2,275 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010222 - LA 97: LA 98 - LA 368 Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 97 201-03 STPFLEX 4,130 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010240 - LA 12: TEXAS STATE LN - LA 109 Project Manager: Type Impv: CP ROADWAY 2", OL ROADWAY 3.5", OL SHOULDERS 1.5" Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 12 012-02 STPFLEX 2,308 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010300 - US 80: JCT JEFFERSON PAIGE RD- HEARNE RD Project Manager: Type Impv: COLD PLANING, ASPHALTIC OVERLAY, PAVEMENT MARKING, Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO US 80 001-02 STPFLEX 2,350 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010344 - LA 174: LA 175 - DESOTO P/L Project Manager: Type Impv: STABILIZE BASE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE LA 174 112-04 STPFLEX 1,888 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Page 151 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010364 - LA 114: LA 1188 - N JCT LA 115 Project Manager: Type Impv: CTB AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES LA 114 145-01 STPFLEX 788 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010379 - LA 40: N. JCT. LA 445 - ST. TAMMANY P/L Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 40 269-06 STPFLEX 1,782 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010394 - LA 585: LA 879 - SANDERS ROAD Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W CARROLL LA 585 332-02 STPFLEX 2,500 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010395 - US 425: JCT I-20 TO JCT US 80 Project Manager: Type Impv: MILL & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND US 425 071-01 STPFLEX 750 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010403 - LLA 182/LA 1: US 90 - GUIDRY LN Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 182 005-06 STPFLEX 2,750 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010455 - US 80: JCT LA 577 TO QUBEC Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON US 80 002-04 STPFLEX 4,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.010670 - LA 27&LA 1256:0.97 MI S LA1133- I-10 INT Project Manager: Type Impv: PATCH, CP 2", OL 4" Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 1256 031-05 STPFLEX 2,315 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE CALCASIEU LA 1256 031-05 STPFLEX 1,543 SUSTAINABILITY NON-INTERSTATE

Project: H.011816 - DISTRICT 58 ASPHALTIC SURFACE TREATMENTS Project Manager: Type Impv: ASPHALTIC SURFACE TREATMENT Remarks: USE TOLL CREDITS AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DISTRICTWIDE 58 000-91 1,579 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE

Project: H.001223 - RESURFACING ON US 84 AND LA 5 Project Manager: Type Impv: MILL. OVERLAY Remarks: 049-01-0017; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 5 049-01 STPFLEX 2,895 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE DESOTO US 84 021-02 STPFLEX 1,853 SUSTAINABILITY NON-INTERSTATE

Page 152 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.009505 - US 79: BILLY SHAW - N END OF PASSING LA Project Manager: Type Impv: ASPHALT OVERLAY, DRAINAGE, PAVEMENT MARKING & RELATED W Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CLAIBORNE US 79 027-06 STPFLEX 1,940 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE CLAIBORNE LA 2 070-02 STPFLEX 3,200 SUSTAINABILITY NON-INTERSTATE

Project: H.009508 - LA 2: CANEY CREEK BRIDGE TO WEBSTER P/L Project Manager: Type Impv: ASHPALT OVERLAY, DRAINAGE, PAVEMENT STRIPING, & RELATED WRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 2 083-04 STPFLEX 3,114 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.009587 - US 84: MISS. RIVER BR. - LA 3180 Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA US 84 026-02 NHPP 1,900 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.009589 - LA 28: RAPIDES LINE - DIVERSION CANAL Project Manager: Type Impv: ASPHALT CONCRETE OVERLAY OVER IN PLACE STABILIZATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE LA 28 074-03 NHPP 1,604 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.009651 - US 61/190: MCCLELLAND - MISS RIVER BR Project Manager: Type Impv: COLD PLANE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE US 61 007-90 NHPP 3,100 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.009658 - US 90: LA 182 - LA 1 Project Manager: Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE US 90 424-08 NHPP 3,938 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.010216 - LA 31: LA 351 - BEG. OF CURB & GUTTER Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 31 056-03 STPFLEX 1,771 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.010273 - LA 154: EAST JCT LA 4 TO JCT LA 792 Project Manager: Type Impv: ASPHALTIC OVERLAY, PAVEMENT STRIPING AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE LA 154 090-04 STPFLEX 1,450 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.010290 - LA 796: LA 508 TO LA 155 Project Manager: Type Impv: ASPHALTIC OVERLAY, PAVEMENT STRIPING AND RELATED WORK Remarks: AC WITH NFA Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BIENVILLE LA 796 090-05 STPFLEX 1,150 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Page 153 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010292 - US 79: TEXAS STATE LINE TO US 80 Project Manager: Type Impv: COLD PLANE, ASPHALTIC OVERLAY, PAVEMENT STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO US 79 048-01 STPFLEX 1,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.010357 - LA 153: JCT LA 9 - FIVE FORKS ROAD Project Manager: Type Impv: STALIZE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 153 088-01 STPFLEX 1,600 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.010388 - LA 155: US 167 - LA 542 Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON LA 155 319-30 STPFLEX 1,200 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.010460 - LA 565: LA 129 - LA 600 Project Manager: Type Impv: PATCH AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA LA 565 178-03 STPFLEX 1,305 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.010462 - LA 15: LA 131 - US 84 Project Manager: Type Impv: PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA LA 15 177-05 STPFLEX 3,200 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE

Project: H.011734 - LA 568, LA573: US 65 - BIG CHOCTAW BAYOU Project Manager: Type Impv: PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TENSAS LA 573 186-04 STPFLEX 1,235 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE TENSAS LA 568 075-03 STPFLEX 336 SUSTAINABILITY NON-INTERSTATE

Project: H.001838 - BOSSIER PARISH LINE - LA 163 Project Manager: Type Impv: MILL. OVERLAY Remarks: 122-02-0009; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER LA 164 122-02 STPFLEX 813 SUSTAINABILITY 2-WAITING FOR FUNDING NON-INTERSTATE

Project: H.002148 - JCT LA 35 - JCT LA 700 Project Manager: Type Impv: STABILIZE BASE AND OVERLAY Remarks: 214-01-0013; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 699 214-01 STPFLEX 4,220 SUSTAINABILITY 2-WAITING FOR FUNDING NON-INTERSTATE

Project: H.009625 - LA 182: LA 89 - 0.36 MI. N. US 90 UPASS Project Manager: Type Impv: COLD PLANE, PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 182 004-02 STPFLEX 2,159 SUSTAINABILITY 2-WAITING FOR FUNDING NON-INTERSTATE

Page 154 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.009629 - US 90 (EB):RR JCT-JCT US 90BUS (PINHOOK) Project Manager: Type Impv: P.C.C.P. REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 90 424-02 NHPP 8,813 SUSTAINABILITY 2-WAITING FOR FUNDING NON-INTERSTATE

Project: H.000320 - JEFFERSON PARISH LN. - LA 50 Project Manager: Type Impv: ULTRATHIN HMAC WEARING COURSE Remarks: 007-03-0060; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES US 61 007-03 NHPP 1,688 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.001006 - E. JCT. LA 40 - LA 16 Project Manager: Type Impv: RUBBLIZE AND OVERLAY Remarks: 030-02-0029; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 21 030-02 NHPP 7,575 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.002258 - LA 45 (FLOOD GATE - LA 560-4) Project Manager: Type Impv: COLD PLANE AND OVERLAY Remarks: 249-01-0056; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 45 249-01 STPFLEX 1,551 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.002762 - LA 86: LA 3242 - LA 347 Project Manager: Type Impv: STABILIZE BASE AND OVERLAY Remarks: 400-01-0007; 400-01 NFA MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 86 400-01 STPFLEX 4,229 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.002765 - LA 86: LA 347 - LA 31 Project Manager: Type Impv: STABILIZE BASE AND OVERLAY Remarks: 400-31-0013; 400-31 MATCH TTF Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 86 400-31 STPFLEX 1,008 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.007992 - LA 883-1 - US 65 Project Manager: Type Impv: ASPHALT OVERLAY Remarks: 818-12-0004; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E CARROLL LA 883-2 818-12 STPFLEX 307 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.008200 - US 65 - FRONTAGE ROAD Project Manager: Type Impv: ASPHALT OVERLAY Remarks: 833-06-0009; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON LA 601 833-06 STPFLEX 0 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009493 - LA 107: LA 1179 - LA 1181 Project Manager: Type Impv: CTB AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES LA 107 147-03 STPFLEX 2,322 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 155 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.009513 - LA 164: JCT. LA 163 TO JCT. US 371 Project Manager: Type Impv: ASPHALT OVERLAY, DRAINAGE, PAVEMENT STRIPING & RLEATED W Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WEBSTER LA 164 122-03 STPFLEX 3,114 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009530 - US 80: OUACHITA PL TO 1.32 MILES EAST Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND US 80 002-02 STPFLEX 6,204 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009532 - LA 2: E END D'ARBONNE BRIDGE TO LA 15 Project Manager: Type Impv: COLD PLANE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage UNION LA 2 070-04 STPFLEX 2,250 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009538 - US 165: S LA 599 - N LA 599 Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE US 165 016-05 STPFLEX 1,220 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009543 - LA 113: VERNON LINE - LA 112 Project Manager: Type Impv: BASE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 113 140-02 STPFLEX 3,449 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009549 - E. JCT. LA 16 - JCT. LA 447 Project Manager: Type Impv: MAINTENANCE RESTORATION & REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON US 190 013-06 STPFLEX 2,322 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009552 - JCT. LA 1034 - JCT. US 190 Project Manager: Type Impv: MAINTENANCE RESTORATION & REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 16 262-01 STPFLEX 1,405 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009556 - LA 107: LA 454 - 320' S OF ESTATE DRIVE Project Manager: Type Impv: STABLIZE BASE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 107 142-04 STPFLEX 3,251 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009568 - LA 660:US 90 - LA 316 Project Manager: Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 660 855-07 STPFLEX 1,125 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 156 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.009571 - US 61:DAVID DR - WILLIAMS BLVD Project Manager: Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 61 007-02 NHPP 1,998 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009573 - LA 39:LAKE BORGNE CANAL BR - LA 46 Project Manager: Type Impv: COLD PLANE AND OVERLAY EXISTING ASPHALTIC CONCRETE PAVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD LA 39 046-32 STPFLEX 2,614 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009583 - LA 4: LA 562 - LA 128 Project Manager: Type Impv: PATCHING & SINGLE LIFT OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage FRANKLIN LA 4 036-02 STPFLEX 452 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009585 - LA 128: LA 573 - US 65 Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TENSAS LA 128 036-06 STPFLEX 1,772 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009591 - LA 4: US 65 - LA 605 Project Manager: Type Impv: ASPHALT OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TENSAS LA 4 173-01 STPFLEX 541 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009602 - LA 557: LA 4 - OUACHITA LINE Project Manager: Type Impv: MICROSURFACING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL LA 557 159-02 STPFLEX 1,276 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009603 - LA 3259: LA 125 - US 165 Project Manager: Type Impv: ASPHALT OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE LA 3259 830-21 STPFLEX 294 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009605 - LA 4: LA 128 - LA 15 Project Manager: Type Impv: CHIP SEAL Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage FRANKLIN LA 4 036-03 STPFLEX 1,716 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009612 - LA 12: LA 109 - BEAUREGARD P/L Project Manager: Type Impv: CP 2", OVERLAY 4", 2" SHLD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 12 012-02 STPFLEX 4,863 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 157 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.009613 - LA 14: MC NEESE ST - E. PRIEN LAKE RD Project Manager: Type Impv: PCCP RECONSTRUCTION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 14 193-06 STPFLEX 4,926 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009614 - LA 14: LA 101 - JEFFERSON DAVIS P/L Project Manager: Type Impv: CP 2", PATCH, OVERLAY 4" Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 14 196-02 STPFLEX 1,181 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009615 - LA 26: US 171 - ALLEN P/L Project Manager: Type Impv: CP 2", OVERLAY 4", 2" SHLD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BEAUREGARD LA 26 028-04 STPFLEX 8,069 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009626 - US 190 (WB):MPRR OPASS-BAYOU COURTABLEAU Project Manager: Type Impv: COLD PLANE, PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY US 190 012-13 NHPP 6,863 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009627 - LA 35: LA 335 - LA 14 Project Manager: Type Impv: COLD PLANE, PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 35 207-02 STPFLEX 2,234 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009628 - LA 92: LA 13 - VERMILION P/L Project Manager: Type Impv: ASPHALT CONCRETE OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 92 385-04 STPFLEX 2,213 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009633 - LA 67: LA 10 - MISSISSIPPI STATE LINE Project Manager: Type Impv: STABILIZE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E FELICIANA LA 67 060-04 STPFLEX 8,813 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009639 - LA 343: LA 342 - 1.0 MI. N. LA 342 Project Manager: Type Impv: COLD PLANE, PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 343 393-03 STPFLEX 619 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009644 - LA 125: US 165-PENTECOSTAL CHURCH ROAD Project Manager: Type Impv: ASPHALT OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE LA 125 131-01 STPFLEX 1,384 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 158 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.009662 - LA 308: GOLDEN MEADOW BR - GALLIANO BR Project Manager: Type Impv: ASPHALTIC CONCRETE OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 308 407-01 STPFLEX 2,115 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009664 - LA 20: TERREBONNE P/L - JACKSON ST. Project Manager: Type Impv: COLD PLANE AND OVERLAY OF EXISTING ASPHALTIC CONCRETE PARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 20 065-05 STPFLEX 1,116 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.009955 - LA 111: BEAUREGARD LINE - C DAVIS LOOP Project Manager: Type Impv: CTB AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 111 132-02 STPFLEX 4,167 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010207 - LA 94: LA 353 - ST. MARTIN PL Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 94 080-03 STPFLEX 127 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010209 - LA 35: LA 365 - LA 95 Project Manager: Type Impv: COLD PLANE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 35 207-07 STPFLEX 1,054 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010214 - US 71: LA 10 - AVOYELLES P/L Project Manager: Type Impv: COLD PLANE, PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY US 71 008-06 STPFLEX 6,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010220 - LA 97: BAYOU NEZPIQUE BR. - LA 100 Project Manager: Type Impv: STONE BASE WITH ASPHALT OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 97 201-02 STPFLEX 2,709 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010223 - LA 106: LA 10 - US 167 Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage EVANGELINE LA 106 204-01 STPFLEX 6,426 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE EVANGELINE LA 106 204-02 STPFLEX 3,136 SUSTAINABILITY NON-INTERSTATE

Project: H.010225 - LA 178: ACADIA P/L - LA 357 Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY LA 178 208-02 STPFLEX 700 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 159 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010226 - LA 82: LA 35 - LA 333 Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 82 215-01 STPFLEX 5,383 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010234 - LA 14: 0.15 MI S LOGNION RD - LA 101 Project Manager: Type Impv: PATCH, CP 2", 4" OVERLAY RDWY, AGGREGATE SHLDR Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 14 196-01 STPFLEX 1,111 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010238 - LA 26: US 90 - RACCA RD(JENNINGS) Project Manager: Type Impv: PATCH, CP 2", OVERLAY 3", 3" SHLD Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS LA 26 054-05 STPFLEX 1,156 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010241 - LA 12: 0.63 MI NE AIRPORT DR - BUXTON CR Project Manager: Type Impv: PATCH, CP2", 4" OVERLAY RDWY, 2" PAVED SHOULDER Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 12 012-04 STPFLEX 1,541 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010243 - LA 26: HOSPITAL RD - JCT US 90 Project Manager: Type Impv: PATCH, CP 2", OVERLAY 3" Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS LA 26 054-04 STPFLEX 576 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010244 - LA 113: LA 26 - LA 112 Project Manager: Type Impv: PATCH, CP 2", WIDEN 2.5', OL 4" Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BEAUREGARD LA 113 139-04 STPFLEX 2,187 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010245 - LA 389: MONROE WHITMAN RD - US 190 Project Manager: Type Impv: PATCH, CP 2", WIDEN 2.5', OL 4" Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BEAUREGARD LA 389 187-04 STPFLEX 7,117 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010246 - LA 112: LA 399 - LA 113 Project Manager: Type Impv: PATCH, CP 2", WIDEN 2.5', OL 4" Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BEAUREGARD LA 112 188-02 STPFLEX 2,163 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010271 - LA 1: SUNDOWN ROAD TO JCT LA 538 Project Manager: Type Impv: OVERLAY, SHOULDER STABILIZATION AND STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 1 045-01 STPFLEX 1,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 160 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010278 - LA 173: JCT HEARNE AVE TO I-220 Project Manager: Type Impv: OVERLAY, SHOULDER STABLIZATION, STRIPING, RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 173 094-01 STPFLEX 1,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010279 - LA 173: LA 1 TO US 71 Project Manager: Type Impv: ASPHALTIC OVERLAY, PAVEMENT STRIPING AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 173 094-02 STPFLEX 900 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010281 - LA 2: WEBSTER P/L TO LA 3062 Project Manager: Type Impv: COLD PLANE, ASPHALTIC OVERLAY, CTB SHOULDERS, PAVEMENT S Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CLAIBORNE LA 2 085-07 STPFLEX 3,350 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010286 - LA 538: JCT US 71 TO LA 1 Project Manager: Type Impv: ASPHALTIC OVERLAY, PAVEMENT STRIPING AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 538 078-04 STPFLEX 1,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010288 - LA 789: PRESTON ROAD TO LA 169 Project Manager: Type Impv: ASPHALTIC OVERLAY, PAVEMENT STRIPING AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 789 809-07 STPFLEX 2,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010299 - US 80: EASTRIDGE TO WEBSTER PARISH LINE Project Manager: Type Impv: COLD-PLANING, INLAY, CHIP SEAL SHOULDERS, PAVEMENT MARKIN Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER US 80 001-03 STPFLEX 2,492 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010320 - LA 42: JCT. HIGHLAND RD - LA 30 Project Manager: Type Impv: PCC PATCH Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 42 258-31 STPFLEX 2,400 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE E BATON ROUGE LA 42 257-04 STPFLEX 4,100 SUSTAINABILITY NON-INTERSTATE

Project: H.010339 - LA 10: LOOK OUT RD - 850' E BAILEY RD Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 10 066-02 NHPP 1,226 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010340 - LA 107: S JCT LA 1 - N JCT LA 1 Project Manager: Type Impv: WIDENING AND OVERLAY OF PCCP Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage AVOYELLES LA 107 052-06 STPFLEX 980 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 161 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010341 - LA 115: LA 1207 - LA 28 Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 115 033-04 STPFLEX 1,928 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010342 - LA 155: RED RIVER P/L - S JCT LA 153 Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 155 091-02 STPFLEX 1,939 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010343 - LA 174: DESOTO P/L - I-49 INTERCHANGE Project Manager: Type Impv: PATCH. COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 174 112-06 STPFLEX 1,925 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010345 - LA 175: N JCT LA 120 - RAY CANTO RD Project Manager: Type Impv: STABILIZE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE LA 175 035-02 STPFLEX 1,973 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010346 - LA 487: LA 120 - LA 174 Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 487 113-03 STPFLEX 3,844 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010348 - LA 8: LA 464 - US 171 Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 8 029-02 STPFLEX 4,661 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010354 - LA 111: US 171 - LA 117 Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 111 133-03 STPFLEX 1,898 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010355 - LA 113: LA 112 - CALCASIEU RIVER Project Manager: Type Impv: CTB AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 113 140-03 STPFLEX 1,679 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010356 - LA 126: JCT LA 34 - NW JCT LA 499 Project Manager: Type Impv: CTB AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN LA 126 091-07 STPFLEX 2,733 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 162 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010358 - LA 3226: BEAUREGARD P/L - US 171 Project Manager: Type Impv: PATCH. COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 3226 858-11 STPFLEX 2,329 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010359 - LA 9: JCT US 71 - JCT LA 156 Project Manager: Type Impv: PATCH. COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 9 089-01 STPFLEX 1,509 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010361 - US 84: LA 477 TO WOLF CREEK Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN US 84 022-02 NHPP 3,790 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010362 - LA 8: JCT US 167 - N JCT US 165 Project Manager: Type Impv: PATCH & INLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage GRANT LA 8 040-02 STPFLEX 2,300 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010363 - LA 34: 1200' S OF LA 1236 TO LA 126 Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN LA 34 124-01 STPFLEX 979 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010365 - LA 117: BELLWOOD - LA 478 Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 117 114-03 STPFLEX 1,288 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010366 - LA 175: 300' S OF SHIRWILLIS DR - LA 120 Project Manager: Type Impv: CTB AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE LA 175 035-01 STPFLEX 2,456 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010375 - LA 1077: LA 21 - U.S. 190 Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 1077 852-03 STPFLEX 2,484 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010376 - LA 25: ST. TAMMANY P/L - S JCT. LA 16 Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 25 059-03 STPFLEX 3,504 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 163 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010377 - LA 36: LA 41 - IGC RAILROAD Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 36 280-03 STPFLEX 1,120 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010378 - LA 38: U.S. 51 - WASHINGTON PARISH LINE Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 38 263-04 STPFLEX 6,487 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010380 - LA 433: U-PASS I-10 - BEHRMAN STREET Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 433 018-30 STPFLEX 740 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010384 - LA 442: LA 63 - W. JCT. LA 441 Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 442 269-01 STPFLEX 2,420 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010385 - LA 3127: ST. JAMES P/L - ST. CHARLES P/L Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 3127 428-02 STPFLEX 3,115 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010387 - U.S. 90: LA 433 - U.S. 190 Project Manager: Type Impv: RUBBILIZE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 90 006-07 STPFLEX 3,323 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010389 - LA 507: US 80 - S. END OVERPASS I-20 Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 507 308-04 STPFLEX 735 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010390 - US 65: PANOLA PLANT ROAD TO ARK. LINE Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E CARROLL US 65 020-09 NHPP 3,600 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010391 - US 80: GILBERT ST TO JCT LA 139 Project Manager: Type Impv: MILL & OVERLAY; OFGC WITH SAFETY FUNDS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 80 002-01 NHPP 1,500 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 164 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010392 - LA 550: LA2 - LA 15 Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage UNION LA 550 311-01 STPFLEX 3,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010393 - LA 582: JCT LA 17 TO EAST CARROLL LINE Project Manager: Type Impv: STABILIZED BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W CARROLL LA 582 333-02 STPFLEX 3,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010404 - US 90: 2.5 MI E LA 182 - ST CHARLES P/L Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE US 90 005-07 NHPP 4,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010405 - US 90: CAMELOT DR - FLOOD GATE Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS US 90 006-90 STPFLEX 1,400 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010408 - LA 1: VALENTINE BR - LA 655 Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 064-05 STPFLEX 2,300 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010409 - LA 1: LA 655 - CHAMPAGNE-HARRELSON BR Project Manager: Type Impv: COLD PLANE AND SUPERPAVE ASPHALTIC CONCRETE OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 1 064-06 STPFLEX 1,500 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010410 - LA 24: LA 20 - LA 664 (SB) Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 24 065-04 NHPP 4,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010411 - LA 24: LA 55 - PROSPECT STREET BRIDGE Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 24 065-91 STPFLEX 4,500 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010412 - LA 57: THOMPSON RD - CEDAR GROVE RD Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 57 246-01 STPFLEX 1,750 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Page 165 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010413 - LA 48: ORMOND PLANTATION - WESCO ST Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 48 282-02 STPFLEX 1,750 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010414 - LA 1253: DOWMAN RD - I-10 FRONTAGE RD Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS LA 1253 419-02 STPFLEX 250 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010416 - LA 3127: ST. JOHN P/L - 3700' W I-310 Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 3127 428-03 STPFLEX 5,500 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010417 - LA 306: LA 18 - LA 632 Project Manager: Type Impv: COLD PLANE, GEOGRID & 4" OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 306 845-07 STPFLEX 3,600 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010418 - LA 611-1 & LA 611-3:COLD PLANE & OVERLAY Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 611-1 826-14 STPFLEX 200 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE JEFFERSON LA 611-1 826-16 STPFLEX 500 SUSTAINABILITY NON-INTERSTATE JEFFERSON LA 611-1 826-16 STPFLEX 100 SUSTAINABILITY NON-INTERSTATE JEFFERSON LA 611-1 826-17 STPFLEX 325 SUSTAINABILITY NON-INTERSTATE

Project: H.010428 - US 71: JCT US 80 TO HEARNE AVE Project Manager: Type Impv: ASPHALTIC OVERLAY, PAVEMENT STRIPING AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO US 71 011-01 NHPP 470 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE CADDO US 71 053-09 NHPP 110 SUSTAINABILITY NON-INTERSTATE

Project: H.010434 - LA 15: LA 1 - W. FELICIANA P/L Project Manager: Type Impv: STABILIZE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage POINTE COUPEE LA 15 177-01 STPFLEX 4,200 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010452 - LA 144: EROS (LA 34) - OUACHITA P/L Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON LA 144 318-01 STPFLEX 1,500 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE JACKSON LA 144 319-04 STPFLEX 500 SUSTAINABILITY NON-INTERSTATE

Page 166 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE Project: H.010453 - US 80: RIVER OAK DR - 0.92 E OF LA 818 Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN US 80 001-07 STPFLEX 2,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010457 - US 80: LA 133 TO US 425 Project Manager: Type Impv: MILL AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND US 80 002-02 STPFLEX 2,058 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE RICHLAND US 80 002-03 STPFLEX 1,442 SUSTAINABILITY NON-INTERSTATE

Project: H.010461 - LA 15: LA 910 - LA 565 Project Manager: Type Impv: PATCH AND OVERLAY, AST Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA LA 15 177-04 STPFLEX 5,745 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010470 - LA 138: JCT LA 593 TO JCT LA 2 Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MOREHOUSE LA 138 330-01 STPFLEX 5,600 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010472 - US 80: 0.9 MILES E. OF LA 818 - US 167 Project Manager: Type Impv: OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN US 80 001-07 STPFLEX 700 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010482 - US167 FRONT: HICKORY HILL - KIWANIS CAMP Project Manager: Type Impv: STABILIZE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES US 167 023-01 STPFLEX 526 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.010652 - LA 73: US 61 (AIRLINE) - ESSEN LANE Project Manager: Type Impv: PCCP PATCHING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 73 077-05 NHPP 3,500 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: H.011311 - US 90: WESTWOOD DR - ELEVATED WB EXPY Project Manager: Type Impv: WIDEN RDWY FOR NEW TURN LANE; CONVERT EX. TL INTO THRU LARemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 90-Z 283-09 STGEN 1,000 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE

Project: L.000003 - PREVENTIVE MAINTENANCE NON-INTERSTATE Project Manager: Type Impv: PREVENTIVE MAINTENANCE/REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 2,000 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 NON-INTERSTATE

Page 167 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE NFA Project: H.009555 - LA 1199: LA 112 - LA 121 Project Manager: Type Impv: CTB AND OVERLAY Remarks: NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 1199 840-27 STPFLEX 3,479 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE NFA

Project: H.009607 - LA 124/LA 559: ENTERPRISE TO DUTY FERRY Project Manager: Type Impv: PATCH AND OVERLAY Remarks: NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CATAHOULA LA 124 041-03 STPFLEX 970 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE NFA CATAHOULA LA 559 813-29 STPFLEX 88 SUSTAINABILITY NON-INTERSTATE NFA

Project: H.010208 - LA 104: CSLM 0.8(END CURB/GUTR)-LA 1161 Project Manager: Type Impv: COLD PLANE AND OVERLAY Remarks: NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage EVANGELINE LA 104 202-01 STPFLEX 541 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE NFA

Project: H.010269 - LA 1131: ARDOIN COVE RD - US 90 Project Manager: Type Impv: ASHPALT SURFACE TREATMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS LA 1131 827-07 NFA 101 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE NFA

Project: H.010471 - LA 542: LA 811 - LA 155 Project Manager: Type Impv: OVERLAY Remarks: NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JACKSON LA 542 319-01 STPFLEX 1,376 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE NFA

Project: H.011035 - LA 580: JONES BAYOU - US 65 Project Manager: Type Impv: MAINTENANCE RESURFACING, 6" OVERLAY Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E CARROLL LA 580 818-01 STPFLEX 3,441 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE NFA

Project: H.011047 - LA 577: LA 860 - NEW BOYS ROAD Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: NFA WILL BE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON LA 577 164-02 STPFLEX 3,093 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE NFA

Project: H.011076 - LA 605 & LA 607 PATCH AND OVERLAY Project Manager: Type Impv: STABILIZE & OVERLAY/PATCH & OVERLAY Remarks: 854-23/LA 605 USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TENSAS LA 605 854-23 STPFLEX 1,856 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 NON-INTERSTATE NFA TENSAS LA 605 854-23 STPFLEX 65 SUSTAINABILITY NON-INTERSTATE

Project: H.002076 - LA 383: LA 101 - ALLEN PARISH LINE Project Manager: Type Impv: PATCH & OVERLAY Remarks: 197-03-0016; NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFF DAVIS LA 383 197-03 NFA 3,275 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Page 168 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE NFA Project: H.002474 - LA 1061: LA 10 - LA 440 Project Manager: Type Impv: COLD PLANE, IN PLACE STABILIZATION, OVERLAY AND STRIPING Remarks: 278-05-0006; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 1061 278-05 NFA 2,043 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.010398 - LA 57:LA 3011-LA 56 Project Manager: Type Impv: SUPERPAVE ASPHALTIC CONCRETE OVERLAY Remarks: AC WITH NFA AND USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 57 246-01 STPFLEX 1,299 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.011560 - LA 55:1.65 MI S MADISON CANAL - EXXON RD Project Manager: Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE LA 55 248-02 NFA 1,600 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.011570 - LA 559: 5 MI. N. PARISH LINE - LA 4 Project Manager: Type Impv: PATCH, OVERLAY & AST Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL LA 559 346-02 NFA 1,480 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.011572 - LA 559:DUTY FERRY - 5 MI. N. PARISH LINE Project Manager: Type Impv: PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALDWELL LA 559 346-02 NFA 1,908 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA CATAHOULA LA 559 346-01 NFA 445 SUSTAINABILITY NON-INTERSTATE NFA

Project: H.011579 - LA 127: LA 1238 TO LA 126 Project Manager: Type Impv: STABILZE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WINN LA 127 127-05 NFA 3,542 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.011581 - LA 154: LA 518 TO LA 9 Project Manager: Type Impv: RESURFACING ASPHALTIC CONCRETE PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CLAIBORNE LA 154 088-06 NFA 375 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.011583 - LA 3015: LA 5 TO US 171 Project Manager: Type Impv: RE-SURFACING ASPHALTIC CONCRETE PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 3015 298-02 NFA 5,000 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.011584 - LA 103: LA 359 - 3.20 MILES SOUTH Project Manager: Type Impv: COLD PLANE, PATCH, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY LA 103 380-04 NFA 2,200 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Page 169 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE NFA Project: H.011587 - LA 87: CSLM 1.89 - CSLM 5.56 Project Manager: Type Impv: COLD PLANE, PATCH, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 87 823-27 STPFLEX 2,600 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.011612 - LA 347: CSLM 1.59 - LA 350 Project Manager: Type Impv: BASE STABILIZATION AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 347 400-04 NFA 4,800 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 NON-INTERSTATE NFA

Project: H.001145 - LA 120: SABINE PARISH LINE TO LA 6 Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: USE AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 120 042-05 STPFLEX 3,812 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.010285 - LA 512 & LA 483: US 171 TO LA 175 Project Manager: Type Impv: ASPHALTIC OVERLAY, PAVEMENT STRIPING AND RELATED WORK Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage DESOTO LA 483 301-02 STPFLEX 4,600 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011552 - LA 307: LA 20 - LA 182 Project Manager: Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 307 829-15 STPFLEX 1,750 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011553 - LA 632: LA 306 - LA 631 Project Manager: Type Impv: ASPHALT OVERLAY, PATCHING, STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 632 845-09 STPFLEX 500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011555 - LA 46:FLORRISANT HWY - GULF OUTLET CANAL Project Manager: Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD LA 46 284-02 STPFLEX 300 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011556 - LA 541: E JCT LA 18 - W JCT LA 18 Project Manager: Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 541 826-05 STPFLEX 550 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011557 - LA 300: LA 1245 - END LA 300 (DELACROIX) Project Manager: Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD LA 300 284-30 STPFLEX 2,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Page 170 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE NFA Project: H.011559 - LA 308: 0.53 MI W DUET DRIVE - LOCKPORT Project Manager: Type Impv: ASPHALT OVERLAY, PATCHING, GUARD RAIL, STRIPING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE LA 308 407-90 NFA 950 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011561 - LA 129: LEVEE RD - S JCT LA 909 Project Manager: Type Impv: STABILIZE BASE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA LA 129 178-01 STPFLEX 2,100 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011562 - LA 129: N. JCT. LA 909 - LA 907 Project Manager: Type Impv: STABILIZE BASE, OVERLAY & PATCH, OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CONCORDIA LA 129 178-01 STPFLEX 5,710 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011563 - GUM COVE RD - .384 MI W SOUTHLAND FIELD Project Manager: Type Impv: PATCH, WIDEN, COLD PLANE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 108 192-02 STPFLEX 3,555 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011564 - LA 857: LA 15 - LA 132 Project Manager: Type Impv: PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage FRANKLIN LA 857 168-01 STPFLEX 1,684 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011571 - .7 MI. W. OF LA 506 - W. JCT LA 126 Project Manager: Type Impv: PATCH & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE LA 124 125-03 NFA 2,100 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011573 - LA 1061: LA 440 - SPRING CREEK BRIDGE Project Manager: Type Impv: 1" THIN ASPHALTIC CONCRETE OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 1061 278-06 STPFLEX 1,010 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011574 - LA 1048: ST HELENA P/L - ROCH ROAD Project Manager: Type Impv: 1" THIN ASPHALTIC CONCRETE OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 1048 853-37 STPFLEX 580 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Page 171 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE NFA Project: H.011575 - LA 417 & LA 10: STAB, OVLAY & MAT ACQ Project Manager: Type Impv: STABLIZE, OVERLAY & MATERIAL ACQUISITION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage POINTE COUPEE LA 417 223-02 NFA 4,880 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA POINTE COUPEE LA 417 223-30 NFA 1,375 SUSTAINABILITY NON-INTERSTATE NFA POINTE COUPEE LA 10 219-06 NFA 80 SUSTAINABILITY NON-INTERSTATE NFA POINTE COUPEE LA 10 219-30 NFA 20 SUSTAINABILITY NON-INTERSTATE NFA

Project: H.011576 - LA 415 & LA 965: STABILIZE & OVERLAY Project Manager: Type Impv: STABILIZE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 415 225-01 STPFLEX 2,400 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA W FELICIANA LA 965 863-06 STPFLEX 1,600 SUSTAINABILITY NON-INTERSTATE NFA

Project: H.011577 - LA 18: SUNSHINE BR - LA 3120 Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 18 063-10 STPFLEX 2,278 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA ST JAMES LA 18 063-09 STPFLEX 222 SUSTAINABILITY NON-INTERSTATE NFA

Project: H.011580 - LA 181: EVANGELINE PARISH LINE TO US 71 Project Manager: Type Impv: STABILIZE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 181 372-05 NFA 1,752 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011582 - LA 92: S JCT LA 700 - CSLM 6.56 Project Manager: Type Impv: COLD PLANE, PATCH, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 92 213-03 STPFLEX 4,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011585 - LA 473: SABINE PARISH LINE TO LA 392 Project Manager: Type Impv: PATCHING AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 473 357-02 STPFLEX 273 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011586 - LA 3277: LA 1158 - LA 757 Project Manager: Type Impv: BASE STABILIZATION AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage EVANGELINE LA 3277 820-26 NFA 1,600 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011588 - LA 121: LA 28 -400' E OF RED CUT HILL RD Project Manager: Type Impv: PATCHING, COLD PLANING, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 121 029-04 STPFLEX 1,440 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Page 172 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE NFA Project: H.011589 - LA 121 400' E RED CUT HILL RD-RAPIDES PL Project Manager: Type Impv: PATCHING, COLD PLANING, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 121 029-04 STPFLEX 2,495 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011590 - LA 98: LA 367 - CSLM 5.35 Project Manager: Type Impv: BASE STABILIZATION AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 98 210-04 STPFLEX 1,500 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011591 - LA 330: CSLM 0.43 - LA 690 Project Manager: Type Impv: COLD PLANE, PATCH, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 330 397-01 STPFLEX 3,750 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011592 - LA 330: LA 690 - LA 685 Project Manager: Type Impv: COLD PLANE, PATCH, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 330 397-02 STPFLEX 2,800 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011593 - LA 330: LA 685 - CSLM 2.45 Project Manager: Type Impv: COLD PLANE, PATCH, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 330 397-03 STPFLEX 1,700 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011594 - LA 485: 570' N OF ALLEN-BUELAH RD - LA 1 Project Manager: Type Impv: PATCHING, COLD PLANING, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage NATCHITOCHES LA 485 115-02 STPFLEX 2,527 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011595 - LA 473: LA 191 TO VERNON PARISH LINE Project Manager: Type Impv: PATCHING AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE LA 473 357-01 STPFLEX 1,795 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011596 - LA 471: LA 122 TO WINN PARISH LINE Project Manager: Type Impv: PATCHING, COLD PLANING, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage GRANT LA 471 123-02 STPFLEX 285 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011597 - LA 8: VERNON PARISH LINE TO LA 119 Project Manager: Type Impv: PATCHING, COLD PLANING, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 8 134-03 STPFLEX 2,210 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Page 173 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE NFA Project: H.011598 - LA 8: LA 119 TO LA 1 Project Manager: Type Impv: PATCHING, COLD PLANING, STABILIZING, AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 8-S 134-04 STPFLEX 4,626 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011599 - LA 529: LA 160 TO LA 2 Project Manager: Type Impv: ASPHALTIC CONCRETE PAVEMENT RESURFACING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER LA 529 808-01 STPFLEX 2,900 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011600 - LA 514 & 507: US 371 TO BIENVILLE PL Project Manager: Type Impv: ASPHALTIC CONCRETE PAVEMENT RESURFACING WITH MINOR WIDENRemarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RED RIVER LA 514 100-02 STPFLEX 1,260 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011602 - LA 577: NEW BOYS ROAD - SHWART ROAD Project Manager: Type Impv: ASPHALT OVERLAY OF EXISTING ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage MADISON LA 577 164-02 NFA 3,000 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011603 - LA 132: LA 135 TO WHITEHALL ROAD Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 132 166-05 NFA 913 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011604 - LA 132: US 425 TO BIG CREEK Project Manager: Type Impv: ASPHALT OVERLAY OF EXISTING ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RICHLAND LA 132 348-01 NFA 343 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011605 - LA 585: LA 577 TO LA 2 Project Manager: Type Impv: ASPHALT OVERLAY OVER IN PLACE CEMENT TREATED BASE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W CARROLL LA 585 334-01 STPFLEX 5,744 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011606 - LA 596: US 65 TO DELTA ROAD Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E CARROLL LA 596 183-02 STPFLEX 200 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011607 - LA 580: LA 877 TO US 65 Project Manager: Type Impv: ASPHALT OVERLAY OVER IN PLACE STABILIZED BASE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E CARROLL LA 580 818-01 STPFLEX 6,880 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Page 174 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - NON-INTERSTATE NFA Project: H.011608 - LA 586: LA 585 TO LA 17 Project Manager: Type Impv: ASPHALT OVERLAY OF ASPHALT PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W CARROLL LA 586 862-09 STPFLEX 2,450 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011616 - LA 101: LA 14 - JEFFERSON DAVIS P/L Project Manager: Type Impv: PATCH, COLD PLANE AND OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 101 209-01 STPFLEX 690 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA

Project: H.011617 - LA 75 & LA 141: CP, OVLAY & STAB, OVLAY Project Manager: Type Impv: STABILIZE, COLD PLANE, & OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 75 257-02 STPFLEX 2,420 SUSTAINABILITY 3-DESIGN/DEVELOPMENT NON-INTERSTATE NFA IBERVILLE LA 141 256-10 STPFLEX 1,500 SUSTAINABILITY NON-INTERSTATE NFA IBERVILLE LA 141 256-10 NFA 408 SUSTAINABILITY NON-INTERSTATE NFA

Project: H.010381 - LA 436: LA 62 - N. JCT. LA 21 Project Manager: Type Impv: COLD PLANE, BASE & OVERLAY Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage WASHINGTON LA 436 859-08 STPFLEX 7,618 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE NFA

Project: H.010382 - LA 441: LA 16 - LA 10 Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST HELENA LA 441 260-09 STPFLEX 3,972 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE NFA

Project: H.010383 - LA 441: LA 442 - ST. HELENA PARISH LINE Project Manager: Type Impv: COLD PLANE & OVERLAY Remarks: USE NFA AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 441 270-03 STPFLEX 2,480 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL NON-INTERSTATE NFA

Project: L.000004 - PREVENTIVE MAINT NON-INTERSTATE (NFA) Project Manager: Type Impv: PREVENTIVE MAINTENANCE/REHABILITATION Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - NFA 2,500 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 NON-INTERSTATE NFA

Page 175 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - ROAD PREVENTIVE MAINTENANCE Project: H.002112 - LA 29: LA 182 - AVOYELLES P/L Project Manager: Type Impv: ASPHALTIC SURFACE TREATMENT AND RELATED WORK Remarks: 205-02-0014; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST LANDRY LA 29 205-02 STPFLEX 350 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011010 - LA 628: ST. CHARLES PL - AIRLINE OVERLAY Project Manager: Type Impv: THIN LIFT OVRLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 628 845-02 STPFLEX 584 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011497 - LA 18: ST CHARLES P/L - GRAMMERCY BR Project Manager: DEVILLE, JACQUES Type Impv: 1" THIN ASPHALTIC CONCRETE OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 18 063-07 STPFLEX 1,700 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011578 - FRANKLIN PARISH AST Project Manager: Type Impv: ASPHALTIC SURFACE TREATMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage FRANKLIN LA 135 165-04 STPFLEX 225 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE FRANKLIN LA 618 167-01 STPFLEX 121 SUSTAINABILITY ROAD PREVENTIVE MAINTENANCE FRANKLIN LA 130 169-01 STPFLEX 185 SUSTAINABILITY ROAD PREVENTIVE MAINTENANCE FRANKLIN LA 578 821-07 STPFLEX 57 SUSTAINABILITY ROAD PREVENTIVE MAINTENANCE

Project: H.011632 - LA 3059: US 171 - PUJOL RD Project Manager: Type Impv: ASPHALT SURFACE TREATMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 3059 383-01 STPFLEX 198 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011633 - LA 109: US 90 - N CHARLIE STANLEY LOOP Project Manager: Type Impv: ASPHALTIC SURFACE TREATMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU LA 109 187-01 STPFLEX 363 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011634 - LA 124: US 165 - .7 MI. W OF LA 506 Project Manager: Type Impv: ASPHALTIC SURFACE TREATMENT Remarks: C.S. 125-03 FROM 1.14 TO 1.58 MATCH WITH TTF (DETAIL 2) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LASALLE LA 124 125-03 STPFLEX 475 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE LASALLE LA 124 125-03 STPFLEX 130 SUSTAINABILITY ROAD PREVENTIVE MAINTENANCE

Project: H.011635 - LA 557: CALDWELL PARISH LINE - LA 34 Project Manager: Type Impv: MAINTENANCE RESURFACING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 557 159-03 STPFLEX 1,537 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Page 176 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - ROAD PREVENTIVE MAINTENANCE Project: H.011636 - LA 389: MONROE WHITMAN RD - SNYDER RD Project Manager: Type Impv: ASPHALT SURFACE TREATMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BEAUREGARD LA 389 187-04 STPFLEX 113 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011638 - LA 3061: US 167 - LA 146 Project Manager: Type Impv: MAINTENANCE RESURFACING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LINCOLN LA 3061 831-13 STPFLEX 477 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011639 - LA 35: LA 700 - LA 699 Project Manager: Type Impv: THIN ASPHALT OVERLAY AND RELATED WORK. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERMILION LA 35 395-01 STPFLEX 564 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011653 - LA 365: LA 13 - LA 35 Project Manager: Type Impv: MICROSURFACING AND RELATED WORK Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ACADIA LA 365 220-01 STPFLEX 987 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE ACADIA LA 365 220-01 STPFLEX 90 SUSTAINABILITY NON-INTERSTATE NFA

Project: H.011656 - LA 31: 0.12 MI N LA 96-LOCAL RD (LEVERT) Project Manager: Type Impv: ASPHALT OVERLAY AND RELATED WORK. Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN LA 31 056-02 STPFLEX 250 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE

Project: H.011704 - LA 1 & LA 69: CONCRETE PATCHING Project Manager: Type Impv: CONCRETE PATCHING Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERVILLE LA 69 405-01 STPFLEX 858 SUSTAINABILITY 4-SCHEDULED IN CURRENT FY 14-15 ROAD PREVENTIVE MAINTENANCE IBERVILLE LA 1 050-06 NHPP 242 SUSTAINABILITY ROAD PREVENTIVE MAINTENANCE

Project: H.009659 - US 90: 1.5 MI E LA 20 - 0.3 MI W LA 309 Project Manager: Type Impv: 3/4" THIN OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE US 90 424-07 NHPP 643 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 ROAD PREVENTIVE MAINTENANCE

Project: H.011630 - LA 626: LA 48 TO US 61 Project Manager: Type Impv: ULTRA THIN OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 626 282-31 STPFLEX 210 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 ROAD PREVENTIVE MAINTENANCE

Project: H.011631 - LA 3060: US 90 TO LA 18 Project Manager: Type Impv: ULTRA THIN OVERLAY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 3060 845-18 STPFLEX 95 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 ROAD PREVENTIVE MAINTENANCE

Page 177 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 SUSTAINABILITY - ROAD PREVENTIVE MAINTENANCE Project: H.011655 - LA 675: 0.41 MI SE US 90 - LA 674 Project Manager: Type Impv: MICROSURFACING AND RELATED WORK. Remarks: 823-02 LM 0.41 TO 1.19 NFA AS MATCH (DETIAL 2) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage IBERIA LA 675 823-02 STPFLEX 155 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 ROAD PREVENTIVE MAINTENANCE IBERIA LA 675 823-02 STPFLEX 85 SUSTAINABILITY ROAD PREVENTIVE MAINTENANCE

Project: H.011678 - US 171: HORNBECK TO WHITFIELD ROAD Project Manager: Type Impv: PATCHING AND GRINDING OF EXISTING CONCRETE PAVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage SABINE US 171 025-02 NHPP 700 SUSTAINABILITY 4-SCHEDULED FOR LETTING FY 15-16 ROAD PREVENTIVE MAINTENANCE VERNON US 171 025-01 NHPP 100 SUSTAINABILITY ROAD PREVENTIVE MAINTENANCE

Project: H.001883 - LA 8 - LA 28 Project Manager: Type Impv: CHIP SEAL Remarks: 137-02-0017; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage VERNON LA 465 137-02 NFA 336 SUSTAINABILITY 2-WAITING FOR FUNDING ROAD PREVENTIVE MAINTENANCE

Project: H.001952 - US 165 - MOREHOUSE PH. LINE Project Manager: Type Impv: DOUBLE CHIP SEAL Remarks: 160-01-0012;JTW/318-03-07.325-01-24.831-15-03 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 554 160-01 STCASH 106 SUSTAINABILITY 2-WAITING FOR FUNDING ROAD PREVENTIVE MAINTENANCE

Project: H.002624 - US 165 - W.JCT. LA 2 Project Manager: Type Impv: DOUBLE CHIP SEAL Remarks: 325-01-0024;JTW/160-01-12 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA LA 553 325-01 STCASH 461 SUSTAINABILITY 2-WAITING FOR FUNDING ROAD PREVENTIVE MAINTENANCE

Project: H.009913 - LA 1: 1.32 MI N JCT LA 2-TEXAS STA LINE Project Manager: Type Impv: CHIP SEAL Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 1 045-03 STPFLEX 430 SUSTAINABILITY 2-WAITING FOR FUNDING ROAD PREVENTIVE MAINTENANCE

Project: H.010551 - LA 16: LA 64/LA 1026 - AMITE CHURCH RD. Project Manager: Type Impv: ASPHALT SURFACE TREATMEENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON LA 16 262-02 STPFLEX 199 SUSTAINABILITY 1-PLANNING/ENVIRONMENTAL ROAD PREVENTIVE MAINTENANCE

Project: L.000005 - ROAD PREVENTIVE MAINTENANCE Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STPFLEX 4,400 SUSTAINABILITY STAGES 4, 3, 2, 1, 0 ROAD PREVENTIVE MAINTENANCE - STCASH 6,000 SUSTAINABILITY ROAD PREVENTIVE MAINTENANCE

Page 178 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 TIME - Project: H.004113 - LA 3241: LA 435 TO LA 40/LA 41 Project Manager: Type Impv: NEW 4-LANE Remarks: 852-33-0001;BL DATE 10-08 404 RE-SUBMITTED 3-96 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 3241 852-33 NHPP 63,000 TIME 3-DESIGN/DEVELOPMENT

Project: H.004435 - LA 3241: LA 36 TO LA 435 Project Manager: Type Impv: NEW 4-LANE Remarks: 852-33-0003;BL DATE 7-08 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 3241 852-33 NHPP 92,000 TIME 3-DESIGN/DEVELOPMENT

Project: H.004957 - LA 3241:I-12/LA 434 INTERCHANGE TO LA 36 Project Manager: Type Impv: NEW 4-LANE Remarks: 852-33-0002;BL DATE 7-08 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 3241 852-33 NHPP 70,000 TIME 3-DESIGN/DEVELOPMENT

Project: H.005720 - FLORIDA AVENUE EXPRESSWAY Project Manager: Type Impv: FLORIDA AVENUE EXPRESSWAY - ENVIRONMENTAL ASSESSMENT Remarks: TTF AS MATCH TO PHASE 2 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 0 TIME 1-PLANNING/ENVIRONMENTAL

Page 179 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.001278 - INTERSECTION IMPR YOUREE DR AT KINGS HWY Project Manager: BORNE, FRED Type Impv: INTERSECTION IMPROVEMENT Remarks: 053-09-0053; USE TTF AS MATCH PER AGREEMENT Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 1 053-09 STP>200K 4,220 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

CADDO LA 1 053-09 STPFLEX 764 URBAN SYSTEMS

CADDO LA 3032 420-01 HSIP 865 SAFETY

CADDO LA 3032 420-01 STPFLEX 270 URBAN SYSTEMS

Project: H.002822 - NICHOLSON @ BRIGHTSIDE LANE Project Manager: Type Impv: INTERSECTION IMPROVEMENT Remarks: 414-01-0036;SEE NOTES USE TTF AS MATCH FOR R/W ON LA 30 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 30 414-01 CM 3,816 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

E BATON ROUGE 000-17 CM 2,763 URBAN SYSTEMS

Project: H.007085 - SHED ROAD (BENTON - AIRLINE) Project Manager: CHRISTNER, STEVE Type Impv: RECONSTRUCTION & WIDEN Remarks: 742-08-0001;CITY IS FUNDING ENGR.&ACQUIRING R/W Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 STP>200K 9,014 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

BOSSIER 000-08 STPFLEX 1,082 ROAD TRANSFER

Project: H.007265 - ST CHARLES AVE (LA AVE-CALLIOPE ST) Project Manager: Type Impv: OVERLAY Remarks: 742-36-0126; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 3,666 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.007277 - LAKE FOREST BOULEVARD Project Manager: Type Impv: MINOR WIDENING Remarks: 742-36-0142;ADD ENGINEERING TO FY 10 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 768 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.007331 - PACKENHAM DR (LA46 - LA39) Project Manager: GUILBEAU, JUSTIN Type Impv: RECONSTRUCT Remarks: 742-44-0006;WAS 742-07-0079 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD 000-44 STP>200K 5,120 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.008046 - LA 3152 : CLEARVIEW OPERATIONAL IMPRV. Project Manager: Type Impv: INTERSECTION IMPROVEMENTS, INCLUDING ADDITIONAL TURN LANESRemarks: USE TTF AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 3152 826-03 STP>200K 1,588 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.008318 - LA 636-3 (LA 628 - LA 44) Project Manager: Type Impv: COLD PLANE, PATCH, AND OVERLAY Remarks: 848-04-0010 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 636-3 848-04 STP>200K 597 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Page 180 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.009069 - TRI-CENTENNIAL PL PARKING, CITY PARK NO Project Manager: Type Impv: PARKING LOT Remarks: SEE NOTES FOR FUNDING INFORMATION Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 1,837 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009179 - WAX ROAD Project Manager: Type Impv: OVERLAY AND WIDENING Remarks: USE LOCAL OF MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 1,296 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009180 - PLANTATION AVE/ENTERPRISE DR Project Manager: Type Impv: OVERLAY AND WIDENING Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 555 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.009834 - ST BERNARD PARISH STREET REHAB PROGRAM Project Manager: Type Impv: OVERLAYS/PANEL REPAIR/PANEL REPLACEMENT Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD 000-44 STP>200K 4,668 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010406 - LA 46: ORLEANS P/L - PARIS RD Project Manager: Type Impv: COLD PLANING AND SUPERPAVE ASPHALTIC CONCRETE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST BERNARD LA 46 046-03 STP>200K 3,000 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.010639 - LA 939 AND LA 940 REHAB Project Manager: Type Impv: MILL AND OVERLAY Remarks: 10% MATCH FROM ENTITY AND 10% MATCH FROM TTF Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 939 803-23 STP>200K 770 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

ASCENSION LA 940 803-06 STP>200K 660 URBAN SYSTEMS

ASCENSION 000-03 LOCAL 178 URBAN SYSTEMS

Project: H.010650 - OLOL MEDICAL COMPLEX AREA STREETS Project Manager: Type Impv: REHABILITATE EXISTING ROADWAY Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 STP>200K 1,000 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011455 - LA 3179 (LA 44 - US 61) Project Manager: Type Impv: ULTRA THIN OVERLAY Remarks: DOTD TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN LA 3179 848-14 STP>200K 511 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Project: H.011761 - I-49: CORRIDOR PLAN Project Manager: Type Impv: PLANNING TO FOCUS ON CONNECTIVITY AND CORRIDOR IMPROVEMERemarks: LAFAYETTE CONSOLIDATED GOVERNMENT TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 0 URBAN SYSTEMS 4-SCHEDULED IN CURRENT FY 14-15

Page 181 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.000506 - LA 22 (DALWILL BLVD - US 190) Project Manager: Type Impv: WIDENING AND DRAINAGE IMPROVEMENT Remarks: 013-12-0060; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 22 261-06 STP<200K 5,900 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.000870 - YOU WINN RD./ GLORIA DRIVE @ US 171 Project Manager: Type Impv: INTERSECTION REALIGNMENT Remarks: 742-10-0137;USE LOCAL AS MATCH FOR C.S. 000-10; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 STP<200K 1,011 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

CALCASIEU US 171 024-02 STP<200K 511 URBAN SYSTEMS

Project: H.002394 - LA 22: W END TCHEFUNCTE RB-MARINA BEAU C Project Manager: Type Impv: COLD PLANE.PATCH AND OLAY Remarks: 261-06-0041; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY LA 22 261-06 STP<200K 2,755 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.006441 - LA 23 (ENGINEERS RD. - LAPALCO) Project Manager: Type Impv: Remarks: 736-38-0002;TRAFFIC STUDY FOR BELLE CHASE HWY. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 23 062-01 STP>200K 3,345 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

PLAQUEMINES LA 23 062-02 STP>200K 2,900 URBAN SYSTEMS

Project: H.007130 - JOHN STINE(MYRTLE SPRINGS-SAMPSON) Project Manager: Type Impv: WIDENING Remarks: 742-10-0146; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 STP<200K 5,500 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007160 - EBR COMPUTERIZED TRAFFIC SIGNAL Project Manager: Type Impv: TRAFFIC SIGNAL SYNCHRONIZATION Remarks: 742-17-0159;CHOCTAW @ CHIPPEWA ST. & N.CHOCTAW@ Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 CM 6,200 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007214 - EAST AMES BOULEVARD IMPROVEMENTS Project Manager: Type Impv: WIDEN FROM 2 TO 3 LANES Remarks: 742-26-0080;OREGON DR.-BLANCHE DR. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 7,400 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007232 - LAFAYETTE MPO NON STATE PVT MARKING Project Manager: Type Impv: PAVEMENT MARKINGS Remarks: 742-28-0006; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 STP>200K 1,000 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007259 - FLEUR DE LIS (30TH ST - OLD HAMMOND HWY) Project Manager: Type Impv: RECONSTRUCTION Remarks: 742-36-0118;(HARRISON - OLD HAMMOND HWY) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 6,100 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Page 182 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.007271 - CANAL BLVD (R.E. LEE - AMETHYST) Project Manager: Type Impv: RECONSTRUCT EXISTING 4 LANE DIVIDED Remarks: 742-36-0135; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 3,000 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007273 - MAGAZINE ST (BROADWAY - CALHOUN) Project Manager: Type Impv: REHABILITATION Remarks: 742-36-0137; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 3,500 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007274 - MAGAZINE ST (CALHOUN TO NASHVILLE) Project Manager: Type Impv: REHABILITATION Remarks: 742-36-0139; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 3,000 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007275 - ST CHARLES AVENUE (NASHVILLE TO LA AVE) Project Manager: Type Impv: OVERLAY Remarks: 742-36-0140; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 1,700 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.007351 - COUNTRY DRIVE WIDENING PHASE A Project Manager: Type Impv: WIDENING Remarks: 742-55-0102; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TERREBONNE 000-55 STP<200K 4,000 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.008259 - LA 1204: 0.369 MI E SPRINGHILL RD-US 165 Project Manager: Type Impv: AC OVERLAY/INPLACE BASE Remarks: 840-31-0014; USE TTF AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 1204 840-31 STP<200K 764 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.008265 - SUGARHOUSE RD. RECONSTRUCTION Project Manager: Type Impv: RECONSTRUCT Remarks: 840-37-0001;ON STATE SYSTEM (WAS 742-07-0040) Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES LA 3250 840-37 STP<200K 4,953 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.009028 - AIRLINE PARK BLVD: W METAIRIE AV-0.4 M N Project Manager: Type Impv: PANEL REPLACEMENT AND DRAINAGE Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 2,430 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010640 - LA 3038 (CORNERVIEW): REHAB & TURN LANE Project Manager: Type Impv: MILL AND OVERLAY Remarks: 10% MATCH FROM ENTITY AND 10% MATCH FROM TTF Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 3038 077-30 STP>200K 660 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Page 183 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.010648 - ACADIAN THRUWAY/N. ACADIAN THRUWAY OVLY Project Manager: Type Impv: PAVEMENT REHABILITATION Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 STP>200K 2,900 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010653 - LA 986 SIDEWALKS Project Manager: Type Impv: INSTALLATION OF SIDEWALKS Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 986 228-07 STP>200K 658 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010654 - LA 415:I-10 TO APPROXIMATELY 0.41M NORTH Project Manager: Type Impv: PAVEMENT REHABILITATION Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 415 861-22 STP>200K 530 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.010843 - ORMOND BLVD PAVEMENT REHAB Project Manager: Type Impv: COLD PLANE, ASPHALT PATCHING, OVERLAY EXISTING ASPHALT, N Remarks: ST. CHARLES PARISH TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES 000-45 STP>200K 4,284 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011018 - CHEMIN METAIRIE PARKWAY BIKE LANES Project Manager: Type Impv: STRIPING, PAVEMENT MARKINGS AND SIGNING OF BIKE LANES. Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 STP>200K 116 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011230 - LA 48: I-310 - ORMOND BLVD Project Manager: Type Impv: INTERSECTION IMPROVEMENTS AT RIVER OAKS DRIVE Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES LA 48 282-02 STP>200K 950 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011276 - NEW ORLEANS AIRPORT CONNECTOR ROAD Project Manager: Type Impv: NEW AIRPORT ACCESS ROAD IN NEW ORLEANS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 0 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011339 - W ESPLANADE @ HOMESTEAD TRAFFIC SIGNAL Project Manager: Type Impv: INSTALL TRAFFIC SIGNALS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 250 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011450 - LA 70 MILL AND OVERLAY Project Manager: Type Impv: MILL AND OVERLAY EXISTING ROADWAY Remarks: PARISH TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 70 426-03 STP>200K 429 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Page 184 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.011451 - LA 22 REHABILITATION Project Manager: Type Impv: PATCH, MILL AND OVERLAY Remarks: PARISH TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 22 266-01 STP>200K 1,210 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

ASCENSION LA 22 266-02 STP>200K 924 URBAN SYSTEMS

Project: H.011671 - LA 22: IC RR XING (PONCHATOULA) Project Manager: Type Impv: NEW RR SURFACE AND LEDS FOR RR FLASHING LIGHTS. Remarks: RR CROSSING IS FEDERAL DOT NO. 300203H. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 22 261-04 STP<200K 200 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011722 - GLENWOOD DRIVE REHABILITATION Project Manager: Type Impv: REHABILITATION Remarks: WEST MONROE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 194 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011738 - US 165-Y:VERNON STREET-HIPPOLYTE AVENUE Project Manager: Type Impv: PAVEMENT PRESERVATION Remarks: CITY OF MONROE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 165-Y 015-08 STP<200K 1,145 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011741 - HADLEY STREET REHABILITATION Project Manager: Type Impv: REHABILITATION Remarks: CITY OF MONROE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 435 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011742 - OLE HIGHWAY 15 (ARKANSAS RD - US 80) Project Manager: Type Impv: MILL, PATCH AND OVERLAY Remarks: OUACHITA PARISH POLICE JURY WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 765 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011759 - PATHS TO PROGRESS (GROUP 40) Project Manager: Type Impv: COLD MILL AND OVERLAY, RE-GRADING, PATCHING, STRIPING Remarks: STBOND AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 3,642 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

ORLEANS 000-36 STP>200K 1,366 URBAN SYSTEMS

Project: H.011760 - PATHS TO PROGRESS (GROUP 41) Project Manager: Type Impv: REMOVE/REPLACE FAILED/DAMAGED CONC RDWY/CURBS, PERM STRemarks: CITY OF NEW ORLEANS WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 897 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011768 - ALEXANDRIA MPO AERIAL PHOTOGRAPHY Project Manager: Type Impv: AERIAL PHOTOGRAPHY Remarks: RAPIDES AREA PLANNING COMMISON WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 0 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Page 185 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.011794 - NEW ORLEANS AIRPORT CONNECTOR ROAD SEG.B Project Manager: DUPLANTIS, MICHAEL Type Impv: INTERSECTION IMPROVEMENTS Remarks: CITY OF KENNER WILL PROVIDE MATCH. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 1,000 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.011821 - MARTIN LUTHER KING JR DRIVE OVERLAY Project Manager: Type Impv: OVERLAY Remarks: DENHAM SPRINGS WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 837 URBAN SYSTEMS 4-SCHEDULED FOR LETTING FY 15-16

Project: H.001413 - LA 18(4TH ST.EXT.-BURMASTER(GRETNA) Project Manager: Type Impv: CONSTRUCT 2 LANES Remarks: 063-02-0048; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 18 063-02 STP>200K 4,850 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

JEFFERSON LA 18 063-02 STGEN 0 OTHER / MISCELLANEOUS

JEFFERSON LA 18 063-02 TOLLS 0 CCC TOLL PROJECTS

JEFFERSON LA 18 063-02 STPFLEX 1,250 OTHER / MISCELLANEOUS

Project: H.002301 - NORTH SHERWOOD FOREST DRIVE IMPROVEMENTS Project Manager: Type Impv: WIDEN FROM 2 TO 5 LANES Remarks: 742-17-0118;ENV DOC. BY CITY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 STP>200K 14,710 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

E BATON ROUGE LA 37 254-02 0 URBAN SYSTEMS

Project: H.007087 - HAMILTON ROAD IMPROVEMENTS PHASE I Project Manager: Type Impv: ROAD IMPROVEMENTS Remarks: 742-08-0003; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 STP>200K 6,078 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.007090 - HAMILTON RD IMPROVEMENTS PH I(C&G) Project Manager: Type Impv: CLEARING AND GRUBBING Remarks: 742-08-0006; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 STP>200K 520 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.007113 - J.BENNETT JOHNSTON AVENUE Project Manager: Type Impv: OVERLAY Remarks: 742-10-0125; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 STP<200K 580 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.007122 - MYRTLE SPRINGS ROAD Project Manager: Type Impv: SURFACE WIDENING AND OVERLAY Remarks: 742-10-0136; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 STP<200K 1,582 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Page 186 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.007181 - L&A ROAD IMPROVEMENTS Project Manager: Type Impv: NEW ROADWAY AND ALIGNMENT Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 4,500 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.007208 - HARVEY BLVD EXT(PETERS RD-MANHATTAN Project Manager: Type Impv: NEW ROADWAY EXTENSION Remarks: 742-26-0073;SEE NOTES. Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 3017 826-11 STP>200K 876 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

JEFFERSON 000-26 STP>200K 9,597 URBAN SYSTEMS

Project: H.007223 - HARVEY BLVD (MANHATTAN - WALL) Project Manager: Type Impv: WIDEN TO 4 LANE URBAD SECT W MEDIAN Remarks: 742-26-0090; USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 7,100 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.007233 - LAFAYETTE MPO NON STATE PVT MARKING Project Manager: Type Impv: PAVEMENT MARKINGS Remarks: 742-28-0007; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 STP>200K 500 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.007288 - MONTGOMERY ST (LA 34 - I-20) Project Manager: Type Impv: PATCH, COLD PLANE, AND OVERLAY Remarks: 742-37-0015 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 4,295 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.007855 - LA 431 @ LA 934 INTERSECTION IMPROVEMENT Project Manager: Type Impv: TURNLANES Remarks: 803-20-0006; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 431 267-02 CM 500 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

ASCENSION LA 934 803-20 CM 250 URBAN SYSTEMS

Project: H.009181 - US167(JOHNSTON ST)@LA3073(AMB CAFF PKWY) Project Manager: Type Impv: INTERSECTION IMPROVEMENT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 167 080-02 STP>200K 2,000 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

LAFAYETTE LA 3073 828-39 STP>200K 500 URBAN SYSTEMS

Project: H.010656 - LA 1 @ LA 76 INTERSECTION IMPROVEMENTS Project Manager: Type Impv: TURN LANES Remarks: USE LOCAL AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage W BATON ROUGE LA 1 050-07 STP>200K 214 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

W BATON ROUGE LA 76 013-01 STP>200K 214 URBAN SYSTEMS

Page 187 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.010973 - VETERANS BLVD LIGHTING(AIRPORT-LOYOLA) Project Manager: Type Impv: ROADWAY LIGHTING Remarks: CITY OF KENNER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 660 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011007 - CHATEAU BLVD RESURFACING Project Manager: Type Impv: RE-SURFACING Remarks: CITY OF KENNER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 1,470 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011248 - JULIA STREET OVERLAY AND WIDENING Project Manager: Type Impv: OVERLAY AND WIDENING Remarks: CITY PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 425 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011249 - MAPLE STREET OVERLAY AND WIDENING Project Manager: Type Impv: OVERLAY AND WIDENING Remarks: CITY OF DENHAM SPRINGS PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 611 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011363 - SHERWOOD (AIRLINE HWY TO OLD HAMMOND) Project Manager: Type Impv: REHABILITATE AND RECONSTRUCT Remarks: EBR CITY-PARISH TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 STP>200K 3,864 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011364 - GOODWOOD BLVD REHAB (LOBDELL - AIRLINE) Project Manager: Type Impv: RECONSTRUCT AND REHABILITATE Remarks: EBR CITY-PARISH TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 STP>200K 1,527 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011439 - LA 22:TURN LN@WAGNER,DRUDE,& KRAFT RDS Project Manager: Type Impv: LT & RT TURN LN @ WAGNER AND DRUDE RD. LT TURN LN @ KRAFT Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage TANGIPAHOA LA 22 261-03 STP<200K 900 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011452 - LA 942 REHABILITATION Project Manager: Type Impv: REHABILITATION Remarks: PARISH TO PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ASCENSION LA 942 256-07 STP>200K 722 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011457 - WILLIAMS/US61 INTERSECTION IMPROVEMENTS Project Manager: Type Impv: INTERSECTION ENHANCEMENTS Remarks: CITY OF KENNER Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON US 61 007-02 STP<200K 487 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

JEFFERSON 000-26 STP<200K 487 URBAN SYSTEMS

JEFFERSON LA 49 283-30 STP<200K 487 URBAN SYSTEMS

Page 188 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.011463 - KENNER TRAFFIC SIGNALS UPGRADE Project Manager: Type Impv: RESTRIPING AND UPGRADING EXISTING SIGNALS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 395 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011721 - US 190/LA 22 IMPROVEMENTS Project Manager: Type Impv: INTERSECTION IMPROVEMENTS Remarks: ENTITY WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY US 190 013-12 STP<200K 2,134 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

ST TAMMANY LA 22 261-06 STP<200K 1,066 URBAN SYSTEMS

Project: H.011724 - COLEMAN AVENUE REHABILITATION Project Manager: Type Impv: REHABILITATION, PATCH AND OVERLAY Remarks: WEST MONROE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 208 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011725 - 4TH STREET REHABILITATION Project Manager: Type Impv: REHABILITATION Remarks: WEST MONROE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 166 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011726 - SWAN LAKE RD (FLAT RIVER TO CROUCH RD) Project Manager: CHRISTNER, STEVE Type Impv: NEW ALIGNMENT Remarks: ENTITY WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 STP>200K 14,158 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011727 - SWAN LAKE RD (E-W CORRIDOR TO FLAT RIVER Project Manager: CHRISTNER, STEVE Type Impv: WIDENING, TWO TO THREE LANES Remarks: LOCAL ENTITY WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 STP>200K 6,318 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011729 - NATCHITOCHES STREET REHABILITATION Project Manager: Type Impv: REHABILITATION Remarks: WEST MONROE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 432 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011731 - W. ESPLANADE BRIDGES @ DUNCAN CANAL Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: CITY OF KENNER PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 5,500 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

JEFFERSON 000-26 LOCAL 5,500 URBAN SYSTEMS

Project: H.011732 - JEFFERSON PARISH: CANAL ST. IMPROVEMENTS Project Manager: Type Impv: BIKE LANES; SIDEWALKS AND CROSSWALKS Remarks: JEFFERSON PARISH PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 6,557 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Page 189 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.011739 - US 165 SOUTH LIGHTING Project Manager: Type Impv: LIGHTING Remarks: CITY OF MONROE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA US 165 015-31 STP<200K 337 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011740 - WALNUT STREET OVERLAY Project Manager: Type Impv: REHABILITATION Remarks: CITY OF MONROE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 520 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011743 - 40 OAKS FARM RD (ARK RD - STANDARD REED) Project Manager: Type Impv: MILL, PATCH, AND OVERLAY Remarks: OUAHCITA PARISH POLICE JURY WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 520 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011745 - SANDAL STREET (LA 3033 - LA 34) Project Manager: Type Impv: MILL, PATCH AND OVERLAY Remarks: OUACHITA PARISH POLICE JURY WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 460 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011747 - EDWARDS RD (LA 3033 - PINE RIDGE ROAD) Project Manager: Type Impv: MILL, PATCH AND OVERLAY Remarks: OUACHITA PARISH POLICE JURY WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 282 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011753 - HIGHLAND DRIVE ROADWAY IMPROVEMENTS Project Manager: Type Impv: REHABILITATION Remarks: CITY OF PINEVILLE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 STP<200K 570 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011754 - ALEXANDRIA STREET IMPROVEMENTS PHASE 2 Project Manager: Type Impv: REHABILITATION Remarks: CITY OF ALEXANDRIA WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 STP<200K 3,106 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011783 - PARKER RD (MOORE RD - GARRETT RD) Project Manager: Type Impv: MILL, PATCH AND OVERLAY Remarks: OUACHITA PARISH POLICE JURY PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 959 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011784 - STUBBS VINSON RD(STUBBS RITCHIE - US 80) Project Manager: Type Impv: MILL, PATCH AND OVERLAY Remarks: OUACHITA PARISH POLICE JURY PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 1,193 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Page 190 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.011785 - STUBBS VINSON RD (LA 139-STUBBS RITCHIE) Project Manager: Type Impv: MILL, PATCH AND OVERLAY Remarks: MATCH PROVIDED BY OUACHITA PARISH POLICE JURY Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage OUACHITA 000-37 STP<200K 635 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011790 - RIVER ROAD NORTH OVERLAY Project Manager: Type Impv: PAVEMENT PRESERVATION - COLD PLANING, PATCHING AND OVERLRemarks: CITY OF DENHAM SPRINGS PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 703 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011795 - SB WESTWOOD DRIVE (WB EXPY TO LAPALCO) Project Manager: Type Impv: CONCRETE REHABILITATION Remarks: JEFFERSON PARISH WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 1,800 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011796 - NB WESTWOOD DRIVE (WB EXPY TO LAPALCO) Project Manager: Type Impv: REHABILITATION Remarks: JEFFERSON PARISH WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 1,800 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011797 - AMES BLVD (WB EXPY - HAPPY ST) Project Manager: Type Impv: COLD-MILL AND OVERLAY Remarks: JEFFERSON PARISH WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 1,200 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011798 - AIRLINE PARK BLVD (CAMPHOR - W NAPOLEON) Project Manager: Type Impv: CONCRETE REHABILITATION WITH DRAINAGE IMPROVEMENTS Remarks: JEFFERSON PARISH WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 3,000 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011825 - BUDDY ELLIS ROAD IMPROVEMENTS Project Manager: Type Impv: OVERLAY Remarks: LIVINGSTON PARISH WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 2,565 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011826 - LINDER ROAD IMPROVEMENTS Project Manager: Type Impv: OVERLAY Remarks: LIVINGSTON PARISH PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 2,211 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011827 - DUNN ROAD IMPROVEMENTS Project Manager: Type Impv: OVERLAY Remarks: LIVINGSTON PARISH PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 2,499 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Page 191 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.011828 - FORREST DELATTE ROAD IMPROVEMENTS Project Manager: Type Impv: OVERLAY Remarks: LIVINGSTON PARISH PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LIVINGSTON 000-32 STP>200K 1,446 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011830 - LA 93: APOLLO RD OVERLAY Project Manager: Type Impv: OVERLAY WITH ISOLATED RECONSTRUCTION WHERE NECESSARY Remarks: CITY OF SCOTT PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 93 433-01 STP>200K 300 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011831 - FORTUNE ROAD OVERLAY Project Manager: Type Impv: OVERLAY Remarks: LAFAYETTE CONSOLIDATED GOVERNMENT WILL PROVIDE MATC Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 STP>200K 850 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011832 - US 90: CAMERON ST. OVERLAY Project Manager: Type Impv: OVERLAY WITH ISOLATED RECONSTRUCTION WHERE NECESSARY Remarks: CITY OF SCOTT PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE US 90 003-11 STP>200K 2,000 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011833 - ST. MARY STREET SIDEWALKS Project Manager: Type Impv: SIDEWALKS Remarks: CITY OF SCOTT PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 STP>200K 3,600 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011834 - LA 93: WESTGATE RD OVERLAY Project Manager: Type Impv: OVERLAY WITH ISOLATED RECONSTRUCTION WHERE NECESSARY Remarks: CITY OF SCOTT PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 93 828-15 STP>200K 750 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.011837 - HAZEL STREET OVERLAY Project Manager: Type Impv: COLD PLANE AND OVERLAY, PAVEMENT MARKINGS Remarks: CITY OF SULPHUR PROVIDING MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CALCASIEU 000-10 STP<200K 520 URBAN SYSTEMS 3-DESIGN/DEVELOPMENT

Project: H.000201 - LA 182 AT BENDEL ROAD Project Manager: Type Impv: GEOMETRIC IMPR. (INCL PINHOOK IMPR) Remarks: 004-01-0039; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE LA 182 004-01 LOCAL 4,252 URBAN SYSTEMS 2-WAITING FOR FUNDING

LAFAYETTE LA 182 004-01 HSIP 731 SAFETY

Project: H.002955 - EARHART EXPRESSWAY Project Manager: Type Impv: ACCESS IMPROVEMENTS Remarks: 430-01-0016 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 3139 430-01 STP>200K 5,000 URBAN SYSTEMS 2-WAITING FOR FUNDING

Page 192 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.002956 - EARHART AT DAKIN Project Manager: Type Impv: RAMP CONNECTOR (EB EARHART - DAKIN) Remarks: 430-01-0020; USE TTF AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON LA 3139 430-01 STP>200K 2,375 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.003854 - SWAN LAKE RD (I-220 TO E-W CORRIDOR) Project Manager: Type Impv: WIDENING STUDY Remarks: 700-08-0129;STAGE 0 COMPLETE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage BOSSIER 000-08 STP>200K 7,845 URBAN SYSTEMS 2-WAITING FOR FUNDING

BOSSIER 000-08 LOCAL 1,961 URBAN SYSTEMS

Project: H.004924 - DEV.& CONST ST. MARTINVILLE BYPASS Project Manager: Type Impv: FEDERAL EARMARK FOR STUDY Remarks: 700-50-0112;STAGE 0 COMPLETED Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST MARTIN 000-50 NFI 0 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.007234 - ACADIAN RD-WEST (CANAL TO LA 3185) Project Manager: Type Impv: 4-LANE Remarks: 742-29-0001; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFOURCHE 000-29 STP<200K 9,359 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.010052 - BR - NO INTERCITY RAIL Project Manager: Type Impv: FEASIBILITY STUDY Remarks: NEW ORLEANS MPO TO PROVIDE MATCH TO BTR STP>200K Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.010053 - BR - NO INTERCITY RAIL Project Manager: Type Impv: FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage STATEWIDE 000-99 0 URBAN SYSTEMS 2-WAITING FOR FUNDING

Project: H.003915 - I-49 INNER CITY CONNECTOR Project Manager: Type Impv: STAGE 0 AND ENVIRONMENTAL Remarks: USE STATE SURPLUS AS MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO 000-09 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.004490 - STAGE 0 STUDY FOR VARIOUS ROUNDABOUTS Project Manager: Type Impv: STAGE 0 STUDY Remarks: 700-28-0221; MATCH BY LAF MPO Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 STP<200K 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.004492 - I-10 INTERCHANGE AT N AMBASSADOR CAFFERY Project Manager: Type Impv: INTERCHANGE DESIGN Remarks: 700-28-0223;STUDY FED FY2013.ENGR FED FY2014 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Page 193 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.004876 - LA 52: LA 18 - N OAK COURT Project Manager: Type Impv: SAFETY AND TSM IMPROVEMENTS Remarks: DTSGE O COMPLETED UNDER DESIGN PHASE Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST CHARLES 000-45 STP>200K 1,850 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

ST CHARLES 000-45 OTHER 1,850 URBAN SYSTEMS

Project: H.004895 - LA 44 (ELM - HEMLOCK) Project Manager: Type Impv: FEASIBILITY STUDY Remarks: 700-48-0106;RPC LOCAL SHARE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST JOHN 000-48 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.004981 - LA 434 CORRIDOR Project Manager: Type Impv: PHASES 1 AND 2 ENVIRONMENTAL STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ST TAMMANY 000-52 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.007970 - OLD HAMMOND (BLVD DE PROV-MILL) Project Manager: Type Impv: WIDEN TO 4 LANES Remarks: 817-09-0035;INCLUDES I'SECT @ FLANNERY; GREEN LIGHT PROJ Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE LA 426 817-09 NFI 8,658 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.008220 - LA406/WOODLAND HWY (LA23 - LA407) Project Manager: Type Impv: WIDENING Remarks: 836-14-0002;JT W 838-06-0002 Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS LA 406 836-14 STP>200K 1,500 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

PLAQUEMINES LA 406 838-03 0 URBAN SYSTEMS

PLAQUEMINES LA 406 838-06 0 URBAN SYSTEMS

Project: H.008271 - SUGARHOUSE RD EXTENSION Project Manager: Type Impv: NEW CONSTRUCTION, 2-LANE WITH PAVED SHOULDERS Remarks: 840-37-0007; Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 STP<200K 2,500 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

RAPIDES 000-40 LOCAL 2,500 URBAN SYSTEMS

Project: H.009213 - LA 3132 (INNER LOOP) EXTENSION Project Manager: Type Impv: STAGE 0 FEASIBILITY STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage CADDO LA 3132 427-01 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.009499 - LEAKE AVENUE IMPROVEMENTS Project Manager: Type Impv: PLANNING STUDY Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Page 194 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: H.009500 - 2040PLAN IMPLEMENTATION&I-49 ACTION PLAN Project Manager: Type Impv: PLAN IMPLEMENTATION AND ACTION PLAN Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage LAFAYETTE 000-28 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.011072 - CENTRAL LA BELTWAY FEASIBILITY STUDY Project Manager: Type Impv: PLANNING STUDY Remarks: RAPIDES AREA PLANNING COMMISSION Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage RAPIDES 000-40 0 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.011752 - SEVERN AVE: VETERANS - W. ESPLANADE Project Manager: Type Impv: SIDEWALKS AND BIKELANES Remarks: JEFFERSON PARISH WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage JEFFERSON 000-26 STP>200K 7,962 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

Project: H.011791 - CAL RD AND MOSS SIDE LN BR REPLACEMENTS Project Manager: Type Impv: BRIDGE REPLACEMENT Remarks: EAST BATON ROUGE WILL PROVIDE MATCH Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage E BATON ROUGE 000-17 STP>200K 1,025 URBAN SYSTEMS 1-PLANNING/ENVIRONMENTAL

E BATON ROUGE 000-17 STP>200K 1,025 URBAN SYSTEMS

Project: H.009920 - REMOVE TOLL BOOTHS/RECONFIG TRAVEL LANES Project Manager: Type Impv: REMOVE TOLL BOOTHS/RECONFIGURATION OF TRAVEL LANES/SIGNRemarks: USE FEDERAL CCC TOLL CREDITS AS MATCH TO STP>200K Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage ORLEANS 000-36 STP>200K 3,000 URBAN SYSTEMS 0-FEASIBILITY/SCOPING

Project: L.000008 - URBAN SYSTEM PROJECTS Project Manager: Type Impv: SELECTED BY MPO'S Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - STP>200K 1,000 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

- STP<200K 1,000 URBAN SYSTEMS

Project: L.000041 - CONGESTION MITIGATION PROJECTS Project Manager: Type Impv: NON-ATTAINMENT AREAS Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - CM 1,000 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

Project: L.000042 - MISC CONGESTION MITIGATION PROJ - LKC Project Manager: Type Impv: IN LAKE CHARLES AS APPROVED BY FHWA Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - CM 500 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

Project: L.000043 - MISC CONGESTION MITIGATION PROJ - BTR Project Manager: Type Impv: IN BATON ROUGE AS APPROVED BY FHWA Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - CM 1,000 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

Page 195 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM DOTD HIGHWAY PRIORITY PROGRAM FOR FY 2015 - 16 URBAN SYSTEMS - Project: L.000094 - URBAN TRANSIT(INCL TRANSFER TO AGENCIES) Project Manager: Type Impv: Remarks: Parish Route Ctrl Sec Fund Con Est x$1000 Category/SubCategory Stage - CM 100 URBAN SYSTEMS STAGES 4, 3, 2, 1, 0

- STP<200K 100 URBAN SYSTEMS

- STPFLEX 100 URBAN SYSTEMS

Page 196 of 196 Version No: 1.15.1 Report Date: 3/30/2015 4:58:40AM