Renewable Energy Integration Study for ASPA power grid Entura submission

E303587 18 July 2013

Prepared by Hydro‐Electric Corporation ABN48 072 377 158 t/a Entura, Level 25, 500 Collins St. Melbourne VIC 3000 Australia

Entura in Australia is certified to the latest version of ISO9001, ISO14001, and OHSAS18001.

©Entura. All rights reserved. Entura has prepared this document for the sole use of the client and for a specific purpose, as expressly stated in the document. Entura undertakes no duty nor accepts any responsibility to any third party not being the intended recipient of this document. The information contained in this document has been carefully compiled based on the client’s requirements and Entura’s experience, having regard to the assumptions that Entura can reasonably be expected to make in accordance with sound professional principles. Entura may also have relied on information provided by the client and/or other parties to prepare this document, some of which may not have been verified. Subject to the above conditions, Entura recommends this document should only be transmitted, reproduced or disseminated in its entirety.

Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

i Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

Executive summary

Entura is pleased to submit this proposal to American Samoa Power Authority (ASPA) in response to a Request for Proposal (RFP) released on 17 June 2013.

Entura is offering its technical services to ASPA for the ‘Renewable Energy Integration Study’ for the ASPA power grid.

Entura has considerable experience with renewable energy systems studies dating back to 1998 when the King Island Renewable Energy project connected 3 Nordex 225 kW turbines to the distribution system on the island. Since that time Entura has successfully undertaken many connections in Australia and overseas including China, India and Pacific Islands.

We are ideal for this assignment for the following reasons:  Entura is the consulting arm of Hydro , Australia’s largest renewable energy producer and the utility responsible for providing to the remote communities of King, Flinders and Cape Barren Islands in the middle of Bass Strait. We therefore understand the unique but broad issues relating to working in isolated communities; not just the grid connection issues relating to producing reliable, continuous supply but also the logistical problem of installing a solution.  Entura has hands on experience in integrating wind turbines, solar PV arrays, wind/diesel, solar/diesel and wind/solar/diesel systems having delivered similar systems on King, Flinders, Cape Barren, Maria, Bruny and Maatsuyker Islands.  Entura has experience in integrating these systems with existing local distribution network infrastructure and associated risks and grid connection issues.  Entura has experience with a wide range of storage technologies, having investigated many technologies and deployed several on King Island. The technologies we have deployed include Vanadium Redox Batteries (VRBs), carbon block, small battery systems and pumped storage. We also are familiar with a wide range of other technologies such as kinetic energy storage and recovery systems.  Entura has experience delivering similar projects into some of the world’s most remote and harsh environments. We have undertaken master‐plans for deployment of 100% renewable systems to Norfolk Island. Our staff have also been seconded into the Australian Antarctic Division to integrate wind turbines with existing diesel systems at Australia’s Antarctic bases.

Entura understands that ASPA is looking to make a decision on its involvement by 1 August 2013. Entura will commit to delivering the scope of work detailed by the RFP and this proposal, for a total fee of USD80 000.

Entura’s proposed team of experienced consultants is set out in Section 1.3 with individual CVs provided in Appendix B.

ii Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

iii Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

Contents

1. Entura’s response 7 1.1 Introduction to Entura and Group 7 1.2 Why Entura – Entura’s experience 7 1.3 Why Entura – Entura’s team 10 1.3.1 Simon Gamble – Project Director 11 1.3.2 Donald Vaughan – Technical Director (Electrical and Grid) 11 1.3.3 Seth Langford – Technical Director (Renewables) 12 1.3.4 Preeti Arora – Technical Lead (Electrical and Grid)/Client Interface 12 1.3.5 Ranjith Perera – Specialist Electrical Engineer 12 1.3.6 Ray Massie – Technical Lead (Renewables Energy) 13 1.3.7 Daniel Bennett – Renewables Energy Engineer 13

2. Scope of works 15 2.1 Introduction 15 2.2 Indicative methodology and work flow for project 15 2.3 Inputs 17 2.4 Outputs 18 2.5 Assumptions/limitations/exclusions 18

3. Our approach 19 3.1 Outline of project tasks 19 3.1.1 Task 0 – Base case development 19 3.1.2 Task 1 – Production cost modelling 20 3.1.3 Task 2 – Steady state analysis 21 3.1.4 Task 3 ‐ Dynamic modelling/stability analysis 21 3.1.5 Task 4 ‐ Short circuit analysis 22 3.1.6 Task 5 ‐ Individual feeder analysis 23

4. Commercial 25 4.1 Proposed fees 25 4.2 Terms and Conditions 25 4.3 Schedule 25 4.4 Insurances 25

5. Management systems 27 5.1 Quality 27 5.1.1 Our commitment 27 5.2 Environmental management 27 5.2.1 Our commitment 28 5.3 Occupational health and safety management 28 5.3.1 Our commitment 28

v

Appendices

A ASPA required attachments A.1 Proposal Invitation A.2 Special Reminders to Prospective Offerors A.3 Attachment A – Proposal Transmittal Form A.4 Attachment C – Proposal Cost Form A.5 Attachment D – Offeror’s Qualification Sheet A.6 Attachment E – Non‐collusion Affidavit of Prime Offeror A.7 Attachment F – Disclosure Statements

B CVs

C Capability statements

D Standard terms and conditions

List of figures

Figure 1.1: Project team structure ...... 10

Figure 2.1: Indicative work flow for project ...... 16

List of tables

Table 1.1: Summary of relevant experience ...... 7

Table 1.2: Client referees ...... 9

Table 1.3: Project team roles...... 10

Table 4.1: Proposed fees ...... 25

vi Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

1. Entura’s response

1.1 Introduction to Entura and Hydro Tasmania Group

Entura is the design and consulting arm of Hydro Tasmania, Australia’s largest generator of renewable energy and Australia’s largest water manager. Hydro Tasmania, our parent company, owns and operates 32 hydro, wind, diesel, and remote area integrated power generation stations throughout Tasmania and the Bass Strait Islands and has previously owned and operated wind and hydro assets in South Australia and assets in India and China.

Entura employs over 300 highly qualified engineers, environmental scientists, planners, technical and support staff that enables us to put together a suitable project team at very short notice with a high degree of flexibility. Entura’s hub office locations are Melbourne, Hobart, Brisbane and New Delhi with project offices in Sydney, Darwin, Perth, and Kuching.

Entura is currently engaged under the design and regulatory compliance contract panel client arrangements with most of Australia’s electrical utilities together with the national regulator AEMO. The services provided by Entura include project development applications, feasibility and options, detailed design studies, power system modelling and assessments, through to project implementation for power generation (wind, hydro, solar PV & CSP), transmission, and distribution infrastructure. In renewables, Entura undertakes resource and climate investigations, energy yield predictions and technology assessments for wind and solar PV projects.

Please refer to some of the project examples in Section 1.2, Entura’s capability statements in Appendix C and staff capabilities in Section 1.3 and Appendix B. Entura’s clients include Government, research agencies, project developers, equipment suppliers, financiers and industrials. Entura brings a wealth of experience both in terms of its corporate experience, but also in its staff.

1.2 Why Entura – Entura’s experience

Table 1.1: Summary of relevant experience

Example projects Entura services Year King Island wind King Island was reliant on diesel fuel to provide its power. In February 1994– power and expansion 1998, three 250 kW Nordex wind turbines were installed (Huxley Hill ongoing project (wind/diesel/ ). The initial project has delivered a long term saving of 15% battery storage), of annual diesel fuel consumption (over the current 14 years of Australia operation) and led to further work though the King Island Renewable Energy Expansion (KIREX). The KIREX project added further to the island and introduced energy storage, in the form of a Refer to Appendix C Vanadium Redox Battery (VRB). A long term saving of 40% of annual for further details on diesel fuel consumption for the expanded system has been achieved. this project. Further stages of development are continuing on the island with the aim to achieve over 65% savings on diesel fuel consumption. Full details can be found at: http://www.kingislandrenewableenergy.com.au/ Wind, solar and The previous power generation system on Cape Barren Island was 2006–10 diesel power system ‐ unreliable and needed replacing with a renewable, cost efficient and

7 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

Example projects Entura services Year Cape Barren Island reliable energy source. Entura was engaged under an EPCM (Engineer, Procure, Construct and Maintain) contract to provide the island with a hybrid wind solar diesel power system. Entura completed feasibility studies, design, construction and integration management for two 20 kW wind turbines, 3 kW of solar PV panels a battery inverter system and upgrades to the diesel power station on Cape Barren Island. The design included an economic analysis with cost benefit and present value analysis completed. The final design incorporated 40 kW of power via two Westwind turbines on 15 metre towers, and 3 kW of backup solar. Low maintenance battery banks store excess wind energy for times of variable wind speed, and this is supplied to the 11 kV distribution system to meet demand. Two 65 kW diesel generators back up the system and are invoked at times of low battery voltage levels. Power system Entura was engaged to conduct a review study on generation 2007–08 augmentation augmentation options on Rarotonga, Cook Islands. Feasibility studies review/ Renewable were conducted on the implementation of a secondary power station energy study ‐ Cook and its impact on the distribution network. The study included high Islands level investigation of the wind and solar resources and the possible options for electricity generation from these sources. Entura also conducted a technical review of the operational risks associated with operating the existing infrastructure and an economic evaluation of the proposed upgrades on the island’s economy. Recommendations were given for future augmentation of the power system, including generation type, sizing specifications, appropriate locations, timing and approximate costs. Distribution and secondary system improvements were also recommended. 0.5–30 MW Solar PV Grid connection analysis for solar PV farm in 2012 Grid Connections Network, New South Wales (NSW) Australia. High level grid connection studies for proposed sites in both ACT and adjacent locations to NSW. Wind farm technical Technical due diligence on over 4000 MW of wind farms proposed, 2006–13 due diligence – under construction or operational. This work covered site inspections, Asia Pacific wind resource assessments, energy predictions, technology reviews (including inspection of wind turbine manufacturing facilities), wind turbine site suitability, operational wind farm assessments, grid connection reviews, and advice on contractual terms for projects. Locations of projects includes: New Zealand, India, Sri Lanka, China, Philippines and the Pacific Islands. This work has been undertaken for developers, Independent Power Producers, wind turbine manufacturers and financiers.

8 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

Example projects Entura services Year Wind farm technical Technical due diligence on 2000 MW of wind farms proposed, under 2007–13 due diligence – construction or operational. This work covered site inspections, wind Australia resource assessments, energy predictions, wind turbine technology reviews, wind turbine site suitability, operational wind farm assessments, grid connection reviews, reviews of permit status and associated conditions and advice on contractual terms for projects. This work has been undertaken by Entura for developers, wind turbine manufacturers and financiers. 168 MW Musselroe Grid connection analysis and design services for a wind farm being 2013 Wind Farm, Australia developed by Hydro Tasmania Generation in Tasmania Australia and currently R2 model validation and GPS compliance studies for the wind farm. 150 MW Solar Grid connection power systems modelling, analysis and advice 2011 Flagships, Australia detailing technical access standards compliance assessment for solar PV farm in New South Wales, Australia Solar site suitability Eleven sites due diligence for solar PV farms (2 to 25 MW) covering 2012–13 due diligence – site suitability with regard to environs and characteristics, ground Australia, ACT conditions, grid access, utilisable area and identified constraints for a Developer. Solar PV due Three solar PV projects due diligence covering design, solar resource, 2010 diligence – Australia, predicted energy yields, technology and design, contracts, and PPA Northern Territory conditions for a Developer Solar resource Solar ground monitoring station methodology and operational 2011 monitoring due considerations due diligence for a PV project. diligence – Thailand Solar resource Solar ground monitoring station methodology, installation, 2011 monitoring due configuration and data management due diligence for a Solar diligence – Australia Flagships project.

The following clients can attest to the quality of our work on technical projects:

Table 1.2: Client referees

Client details Contact name and position Telephone and email Te Aponga Uira O Tumu‐Te‐Varovaro Mr Apii Timoti +682 20 054 (TAU) Chief Executive Officer [email protected] Rarotonga, Cook Islands Asia Sustainable and Alternative Energy Mr Antonie de Wilde [email protected] (ASTAE) Coordinator The World Bank, Sydney, Australia CLP Power Mr Avinash P Rao +91 22 67588877 India General Manager – Business [email protected] Development (Renewables) LTL Holdings (pvt) Limited Mr Sameera Ganegoda + 94 112 698586 Sri Lanka Project Manager [email protected]

9 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

1.3 Why Entura – Entura’s team

Entura proposes Mr Simon Gamble as Project Director with Mr Donald Vaughan as Technical Director (Electrical and Grid) and Mr Seth Langford as Technical Director (Renewables). Ms Preeti Arora will be the client interface and will coordinate the provision of Entura’s services.

All the consultancy activities will be carried out by highly qualified and experienced staff. The work will be carried out by consultants in the Entura offices in Australia. The key team members and structure are presented below. CVs are also provided in Appendix B.

Figure 1.1: Project team structure

Table 1.3: Project team roles

Role Personnel Position at Entura Project Director Simon Gamble Manager Small Renewable Asset Development Technical Director (Electrical and Grid) Donald Vaughan Principal Electrical Engineer Technical Director (Renewables) Seth Langford Specialist Renewable Energy Engineer Renewables Energy Lead Ray Massie Specialist Renewables Engineer Technical Lead/Client Interface Preeti Arora Senior Power Systems Engineer Specialist Electrical Engineer Ranjith Perera Specialist Electrical Engineer Renewables Energy Engineer Daniel Bennett Renewables Energy Engineer

Additionally, Entura has a highly skilled and experienced team of consultants in the areas of energy storage solutions and Remote Area Power Systems (RAPS) who can be called on to provide specialised advice as required.

10 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

1.3.1 Simon Gamble – Project Director

Simon is an executive manager with a 15 year track record of delivering impressive outcome focussed, whole of business results. Simon has demonstrated an ability to build, lead and inspire talented teams to deliver innovative results and produce world leading outcomes.

Currently, as Manager Small Renewable Asset Development, Simon has led the development and implementation of Hydro Tasmania’s small and emerging renewable energy and Off‐grid development strategies; the assessment of emerging renewable energy technologies; and the preparation of distributed energy and off‐grid power system project feasibility assessments, project approvals and business cases.

Simon heads the development of a world leading hybrid power station on King Island in the Bass Strait, Australia. In seeking to commercialise emerging renewable energy technologies, Simon has forged a number of partnerships with emerging suppliers in wave, tidal, solar and energy storage technologies. This also incorporated the preparation of an annual technology watching brief report for the Board of Hydro Tasmania and the delivery of the R&D programme for the Corporation, both programmes that were established under Simon’s leadership. Simon has created a network of support for ongoing R&D utilising the King Island facility with organisations including the UTAS, CSIRO, Sandia National Labs, Pacific Northwest National Labs and the US Department of Energy.

For this project, Simon will be the Project Director of Entura’s services.

1.3.2 Donald Vaughan – Technical Director (Electrical and Grid)

Donald Vaughan is a Principal Consultant for Entura in the area of primary electrical engineering.

He has worked for all sides of the electrical industry (generators, equipment suppliers, customers, Network Service Providers and Market operators), and has 17 years of experience providing advice on regulatory and technical requirements for generators, substations and transmission systems.

Donald specialises in the performance of power systems that rely on both traditional and renewable energy generation and transmission systems. Donald advises clients on a wide range of networks and applications that include embedded generation systems; grid‐connected, large‐scale generating units and transmission/generation projects. Donald has worked on projects overseas and in Australia focussing on power system performance and generator integration. Donald’s expertise is now focused on network connections and facilitating the development of renewable energy through network analysis and strategic advice to clients throughout the development and operational phases of renewable energy projects.

For this project, Donald will be a Technical Director of Entura’s services, focussing on all grid connection and electrical design aspects.

11 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

1.3.3 Seth Langford – Technical Director (Renewables)

Seth Langford is a Specialist Consultant with 11 years’ experience in the renewable energy industry as a technical lead and project manager on feasibility studies, due diligence projects and major wind farm projects in Australia, India, Sri Lanka, South Africa, New Zealand and China. He has also had oversight of Entura’s feasibility studies of wind and wind‐diesel projects and in a review role for Entura’s PV solar projects. Seth has spent considerable time in India and China on behalf of developers assessing greenfield and operational wind farms for the purposes of acquiring projects. Seth leads the provision of Entura’s renewable services.

As part of his work, Seth has been involved with assessments of projects using the following wind turbine manufacturers: Enercon, Vestas, Suzlon, Siemens, Goldwind, Nordex, GE, Gamesa, Regen Power Tech, REPower and Sinovel. During this time, Seth has worked on the energy assessments for wind farms of over 5000 MW.

For this project, Seth will be a Technical Director of Entura’s services, focussing on the wind and solar resource and energy assessments.

1.3.4 Preeti Arora – Technical Lead (Electrical and Grid)/Client Interface

Preeti is a Senior Power Systems Engineer with six years’ experience within the power industry. Her technical expertise includes leading the grid connection process from initial assessment of options and constraints through to achievement of connection. Of this, five years were spent at a renewable energy developer, assessing and connecting solar and wind projects.

Her expertise includes feasibility studies, regulatory compliance (connection enquiries, applications, generation registration and license application processes), power system studies comprising plant modelling, load flow analysis and dynamic stability analysis using a variety of modelling packages.

For this project, Preeti will lead the grid connection studies and perform PSS/E modelling and simulations. She will also be the client interface and will coordinate the provision of Entura’s services

1.3.5 Ranjith Perera – Specialist Electrical Engineer

Ranjith Perera is a Specialist Electrical Engineer in Power System team, responsible for power system studies and network connections. Ranjith performs power system planning, network modelling, dynamic simulations and analysis. This role requires Ranjith to be involved in connection agreement process and continual close liaison with utility and regulators for the approval. With fifteen years' experience in the electrical filed across wide range of disciplines (power system planning, transformer design, substation constructions, power quality analysis, insulation coordination and generator connections), currently Ranjith manages complex generator connection approval process.

Ranjith worked both within Australia and internationally, including the Singapore, Malaysia, Sri Lanka and Solomon Islands. With qualifications in electrical engineering, Ranjith has received a number of prizes for his high achievement in academic and research work.

For this project, Ranjith will provide specialist input into the grid connection studies.

12 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

1.3.6 Ray Massie – Technical Lead (Renewables Energy)

Ray is a Specialist Renewables Engineer With over 25 years’ experience; Ray continues to be a key player in developing Hydro Tasmania’s renewable energy technology expertise. He has been the primary expert in developing the skills and capabilities for renewable energy team. He is also in the role of advising the wider business on developments in the renewable energy industry, both technically and strategically covering wind, solar, ocean, geothermal, as well as electric vehicles, energy storage and wide range of emerging demand side and supply side options impacting the energy industry.

He has managed multi‐disciplined teams in many aspects of renewable energy project development and technical specification for many projects both at utility scale as well as Remote Area Power Systems, including the Bass Strait Islands, Pitcairn Island and Cape Barren Island Projects.

For this project, Ray will lead the production cost and energy modelling.

1.3.7 Daniel Bennett – Renewables Energy Engineer

Daniel is a Renewable Energy Engineer with Entura and has worked on renewable power projects since joining Entura. He has gained an understanding of the analysis required to produce energy estimates from recorded and operational data, and the requirements involved in wind turbine selection based on the site conditions. He has performed due diligence work on numerous wind farms since 2008, for a variety of clients across Australia and India and has spent time in India as part of wind technical due diligence activities. He has reviewed wind monitoring masts and power curve verification tests.

For this project, Daniel will perform production cost and energy modelling.

13 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

14 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

2. Scope of works

2.1 Introduction

The American Samoa Power Authority (ASPA) released a Request for Proposal (RFP NO. FY13. 1127. ESD. RENEWABLE ENERGY) on 17 June 2013. This RFP is for Renewable Energy Integration Study for the ASPA Power Grid. Entura proposes to be technical consultant for this work.

This document outlines how Entura proposes to analyse the network and energy resource information provided by ASPA and perform production cost modelling and load flow, dynamic simulations to meet increased renewable penetration for ASPA power grid.

2.2 Indicative methodology and work flow for project

In our response to your Request for Proposal, we have developed a methodology that directly responds to your requirements and background and information provided. Entura proposes to undertake the following activities as part of the study. This is further detailed in Section 3.

15 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

Figure 2.1: Indicative work flow for project

Task 0: Base case development

Network Production data information from solar PV site

Max. of 1 iteration Max. of 1 iteration if model different from Develop load flow and Energy modeling using Pvsyst if model different from dynamic model using PSS/E system performance software system performance data Develop system data performance and Produce production cost Engineering decision on operational characteristicts modeling Engineering decision on PSS/E model to use for energy model to use for further studies further studies ASPA’s current Compare system performance Compare data

Close match? Close match? No OR OR No > 1 iteration > 1 iteration Interim report for ASPA Inform decision on energy and Yes PSS/E model to use for further Yes studies

Task 5: Individual Feeder Analysis

Task 1: Production cost modeling

P/Q injection exercise (stepped) for each feeder RE penetration limit Propose ‘easy’ upgrades to optimisation increase RE penetraton Identify lowest cost of production Model 5 scenarios Retuned scenarios

Retuned scenarios

Task 2: Steady state analysis Task 3: Dynamic modeling/stability analysis

Develop five scenario load flow models using PSS/E Develop five scenarios dynamic models using PSS/E Steady state analysis (voltage and ASPA grid thermal limit impacts for each Dynamic simulations for selected code scenario) system conditions

Propose and simulate mitigation Propose mitigation for key issues, retune RE limit (optimisation) Cost implications, new RE limits

Task 4: Short circuit analysis

Short circuit analysis Existing (3ph, 1ph, 2ph‐g etc) CB fault ratings Compare with lowest CB duties

FINAL REPORT to ASPA

16 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

2.3 Inputs

ASPA to supply:

Network:  Network topology including feeder, load and generator characteristics  Unique characteristics of the ASPA system:

o load dynamics

o under‐frequency load shedding (UFLS) schemes

o automatic generation control (AGC) schemes.  ASPA’s current system performance data for year 2013 for validation  ASPA’s grid code and/or permitted thermal and voltage limits  Existing network fault levels  Protection settings including under/over speed protection.

Wind:  Full wind data records with a 10 minute data step including wind speed (average, standard deviation, and maximum speed) and direction data (average and standard deviation) as well as any information on the climatic conditions (temperature, humidity, air pressure used to calculate air density).  Wind mast commissioning reports; including photos of masts, surrounds in all 360 directions, and instrumentation; mast set‐up diagrams including instrumentation types, instrument heights, boom lengths; maintenance history; calibration certificates; mast location (in latitude and longitude as well as Eastings and Northings with associated Datum); and mast elevation.  If available a long term wind record (preferably 10+ years), including a description of the mast location and surrounds, height of instrument(s) and other pertinent information that may have affected measurements. Entura assumes that any data available will be provided (i.e. no pertinent data shall be withheld).

Solar:  Manufacturer, model, location, orientation, shading, of existing solar PV panels and inverters  Connection diagram showing string length and layout and metering point  Details of meter (manufacturer and model number)  Operational data, including generation and grid availability for the full operating life of all existing solar installation. This should be provided at a minimum hourly frequency  CAPEX and OPEX for existing solar PV installations.

Existing diesel generation:  Generator type, manufacturer, and model for each diesel generator  Diesel generator efficiency curves if known  Generator O&M costs broken down into sub categories as much as possible

17 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

 Generator fuel volume usage and output generation  CAPEX and OPEX for existing generation  Fuel pricing information (current and forecast for the life of operation).

Future plan details:  The capacities, locations and points of interconnection (POI) for individual wind turbines generators or whole wind power plants  Location, capacity, orientation, shading and points of interconnect for solar PV to meet the scenarios as given  Any internal reports and/or other supporting information describing the sites, surrounds, expected generation, wind turbine generator availabilities, grid availabilities, contractual guarantees, etc.  Proposed wind turbine generator model  Proposed model of solar PV panel and system design  WAsP Model of proposed wind farm, if available, or the following inputs:

o Terrain contours and surface roughness, or a WAsP map

o Co‐ordinates of wind monitoring masts and wind turbines in same datum as map

o Wind turbine generator specifications.

2.4 Outputs

An interim report will be sent to ASPA to provide results of baseline production cost and PSS/E model validation against ASPA’s system performance data. This will follow into a teleconference with ASPA to discuss validation results and assumptions that were made to finalise models to facilitate further work.

A final report in standard Entura format will be provided to ASPA with PSS/E network models detailing the results of energy and production cost modelling and grid analysis and recommendations for further actions (if warranted).

2.5 Assumptions/limitations/exclusions

The following activities are excluded, but can be added by negotiation:  ASPA will be requested to provide the list of data inputs given in Section 2.3 above. In the absence of the data, Entura may make informed assumptions which will be communicated back to ASPA.  Additional work to address changes to the scenarios or modification to the inputs (costs/ designs/assumptions) will be done outside this scope of work and will be charged at Entura’s standard rates.  Any site visits and travel to American Samoa.  Any purchases of data, models or standards except those identified in Section 2.3 above.

18 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

3. Our approach

Entura proposes to undertake the proposed assessment through the following task breakdown.

3.1 Outline of project tasks

Task 0 Base case development Task 1 Production cost modelling Task 2 Steady State Analysis Task 3 Dynamic modelling/stability analysis Task 4 Short Circuit Analysis Task 5 Individual Feeder Analysis

3.1.1 Task 0 – Base case development

Purpose:  To develop and validate baseline (year 2013) steady state and dynamic model of ASPA’s network  To develop and validate baseline (year 2013) energy resource model  To perform and validate baseline production cost modelling.

Methodology:  Collate all the available information on ASPA’s network including unique characteristics of the system to produce a system model that accurately represents the physical system. We are proposing to use PSS/E modelling software to build steady state and dynamic system model. Validate and retune this model using available system performance data.  Similarly, to accurately perform production cost modelling, we have proposed to collate all available solar irradiation and power output time series data from existing 2.4 MWAC PV plant and integrate mesoscale/satellite data to produce baseline (year 2013) energy resource model using PVsyst software. Validate and retune this energy model using available system performance data. This will in turn be used to project baseline production costs.  Both production cost and dynamic simulations will be validated against available system performance data. We will re‐tune energy resource and PSS/E model to match system performance data to build confidence in study scenarios. Maximum of one iteration is proposed for re‐tuning the model or else make moderately conservative assumptions.

Output:  Working steady state PSS/E model of ASPA’s network.  Working dynamic PSS/E model of each existing diesel generator, PV units, load dynamics, under‐frequency load shedding (UFLS) schemes and automatic generation control (AGC) using PSS/E software and available system performance data.

19 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

3.1.2 Task 1 – Production cost modelling

Purpose:  To review the available wind and solar data for American Samoa and prepare the data for further analysis  To estimate the unconstrained annual energy and a time series of generation for each of the ASPA renewable production scenarios outlined in the RFP  Report on cost of production modelled under each scenario, as well as other factors such as emissions, spinning reserve forecasts and changes in O&M costs.

Methodology:  Review wind data supplied from sites in American Samoa, quality check, and create record  Obtain local weather station and mesoscale/satellite data (3TIER and NASA SSE) in order to provide an indication of the long term variability of wind and solar resource  Compare and correlate the wind speed data to create a time series wind speed data set at likely wind turbine hub height which can be used in the energy generation modelling  Compare and correlate the solar radiation data with production data from solar installations to create a representative time series data set which can be used in the energy generation modelling  Prediction of unconstrained energy generation for indicative wind turbine generators at location of wind plant (specified by ASPA), using WAsP software in conjunction with Entura’s wind analysis procedures  Prediction of PV plant output at locations specified by ASPA using PVsyst software  Collate indicative costs for plant, operations & maintenance and fuel  Model the operation of the five future renewable generation scenarios with the representative time series resource data and loads and test the system’s ability to meet demand and any requirement for energy storage  Compare capital and operating costs estimated by varying the mix between solar and wind to obtain the overall renewable percentage, and identify the lowest cost installation  Comment on likely production costs changes in the case of accurate resource forecasting.

Output:  Hourly generation/dispatch data (wind, solar, storage and diesel generator) for each scenario for a single representative year  Summary of cost of energy, fuel and emissions reductions, requirement for spinning reserve/storage, O&M costs and reliability of design under each scenario.

20 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

3.1.3 Task 2 – Steady state analysis

Purpose:  To develop PSS/E load flow models for five scenarios at both high and low load system conditions  To identify voltage and thermal issues and mitigation for each penetration scenario.

Methodology:  Use the validated baseline load flow case from Task 0 and location information for wind and solar capacity to be proposed by ASPA to develop PSS/E models for each penetration scenario.  Use these cases to investigate steady state voltage rise/drop and fluctuations at the connection point and at key points on the network and thermal line loading impacts with changing renewable penetration levels at both high and low load system conditions.  Identify key issues for each case.  Some of the overloading issues identified can be relieved by certain dispatch actions like splitting busbars, changing lower voltage network topology in order to redistribute load‐ demand or change of generation units engagement etc. Investigate such opportunities or else propose and simulate mitigation measures and identify cost implications and resulting renewable penetration levels.

Output:  Working PSS/E load flow models for five penetration scenarios at both high and low load system conditions  Identify key risks and issues and propose mitigation measures and cost implications.

3.1.4 Task 3 ‐ Dynamic modelling/stability analysis

Purpose:  To propose any mitigation measures required so as with increased renewable energy penetration, the operating conditions are always within adequate limits, both during the contingency and after clearing the fault.

Methodology:  Use the validated baseline PSS/E dynamic model from Task 0 and location information for wind and solar capacity to be proposed by ASPA to develop PSS/E models for each penetration scenario for both high and low load system conditions.  Identify worst‐case generation scenarios in terms of system performance based on the generation profiles developed from the production cost modelling and energy modelling from Task 0 and 1. The system conditions will be chosen based on inertia, fault level, synchronous generation distribution and penetration level. Use dynamic simulation to illustrate system performance under disturbances for these system conditions.  In ASPA’s power grid with increased renewable energy penetration limits, there are some operation conditions in which transient stability is severely at risk. The critical operating scenario takes place when the highest renewable generation coincides with the lowest

21 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

demand in the system because there are less diesel units connected. In this operating situation, the two disturbances that will be studied are:

o Three‐phase fault on a feeder which doesn’t isolate the two power stations

o Three‐phase fault on the tie line between Tafuna and Satala power plants. Use dynamic simulations for selected system conditions and for the largest ASPA contingency event (loss of largest generator) for all study scenarios and verify the system’s ability to provide adequate frequency response and restore its nominal frequency without load shedding or tripping of diesel generators due to under/over speed protection.  Use dynamic simulations of the highest wind and solar power ramps to verify system’s ability to provide stable operation during such weather driven ramping events.  Identify mitigation measures for high penetration scenarios (such as additional spinning reserves, wind providing inertia/frequency response, voltage control or energy storage) in case the system is not stable under the above conditions and use simulations to show improved system performance.  Use transient simulation under self‐recovering voltage faults for all penetration levels and load conditions to verify the system’s ability to maintain satisfactory operation (low voltage ride‐ through capability).  Propose and simulate mitigation measures in case of unsatisfactory transient performance for certain scenarios and load conditions.  Evaluate the need for ancillary services and if deemed necessary, include in production cost modelling.

Output:  Working PSS/E load flow models for five penetration scenarios at both high and low load system conditions.  Identify key risks and issues and propose mitigation measures and cost implications.

3.1.5 Task 4 ‐ Short circuit analysis

Purpose:  To identify any limitations in terms of existing switchgear capability to accommodate additional fault level from the proposed generation.

Methodology:  Utilise re‐tuned (if necessary) renewable energy penetration scenarios from Task 1 & 3 to estimate the fault contribution at the point of connection of proposed wind and solar plant and at key locations of the ASPA’s network. The short circuit analysis will be using PSS/E and will include three‐phase, single and double line‐to‐ground faults.

Output:  Identify limitations in existing switchgear capability.

22 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

3.1.6 Task 5 ‐ Individual feeder analysis

Methodology:  Use the validated baseline PSS/E case from Task 0.  Perform load flow analysis to determine existing limits for generation penetration for individual feeders. This stepped multi‐sited P/Q injection exercise will take into consideration current feeder and substation limits.  Provide ASPA the limits of renewable energy penetration for individual feeder without any augmentation.  Identify ‘easy’ upgrades that could be made to increase these penetration limits.

Output:  Determine maximum renewable energy penetration level for individual ASPA feeders  Propose mitigation options to increase penetration limits.

23 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

24 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

4. Commercial

4.1 Proposed fees

Entura has submitted this proposal on the basis of its own standard terms and conditions, which are attached. Entura reserves the right to revise or withdraw its proposal and payment terms based on negotiated terms and conditions. Entura’s proposed fees for this consultancy are presented below. Please refer to A.4 for task cost proposal as per ASPA’s RFP requirement.

Table 4.1: Proposed fees

Task # Description Fees (USD) Project Management $4500 Task 0 Base case development $16 500 Task 1 Production cost modelling $17 000 Task 2 Steady State Analysis $11 000 Task 3 Dynamic modelling/Stability Analysis $21 000 Task 4 Short Circuit Analysis $3000 Task 5 Individual Feeder Analysis $7000 Total cost $80 000

4.2 Terms and Conditions

Entura has submitted this proposal on the basis of its own standard terms and conditions, which are attached in Appendix D. Entura requests that the client provide feedback on whether these are acceptable.

4.3 Schedule

As per the meeting minutes from pre‐teleconference dated 24 June 2013, Entura understands that ASPA requires completion of this project within six months of Notice to Proceed (NTP). Entura will propose a detailed schedule and agree with ASPA at NTP stage.

4.4 Insurances

Entura is covered by the Hydro‐Electric Corporation’s general liability insurance with the David Constable syndicate and a panel of international insurers. The insurance is placed through our broker Marsh and a copy of their ‘Certificate of Currency’ is available on request. The policy is current to 30 September 2013 and is for:  Public liability (policy #DR461411)  Professional indemnity (policy #DR461411).

Workers compensation policies are also in place in Tasmania, Victoria, South Australia, and Queensland and are current until June 2014.

25 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

26 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

5. Management systems

5.1 Quality

Entura operates in accordance with an ISO9001 certified quality management system. Quality assurance is an important part of our overall business improvement strategy and is critical to the long‐term competitive success of Entura. Quality compliance is managed through an internal and external audit program and certified by Bureau Veritas.

Entura considers that quality is everyone’s personal responsibility and the key to achieving employee satisfaction. All staff members are responsible for performing their work in accordance with our management system, and for taking the initiative to ensure that consistently reliable services are provided.

5.1.1 Our commitment

The management and employees of Entura are committed to implementing and maintaining an effective quality system aiming to:  satisfy our clients by continually meeting their needs and expectations  enhance our reputation for consistently delivering projects that represent real ‘value for money’.

Entura achieves this by:  complying with AS/NZS ISO 9001 in our quality manual, plans, procedures and instructions  fostering close working relationships with clients, suppliers and subcontractors, which result in ‘win‐win’ solutions  developing the skills and knowledge of all employees through training and professional development, to enable them to reach their full potential  continually improving in all areas of business operations, to become a world‐class provider of high quality consulting solutions and services.

5.2 Environmental management

Entura operates under an ISO 14001 certified environmental and sustainability management system. We ensure our activities, products and services comply with environmental legislation as well as relevant environmental commitments and agreements. Compliance is certified by NCS International Certification.

27 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

5.2.1 Our commitment

The management and employees of Entura are committed to implementing and maintaining an effective environmental management system. We are committed to:  leadership in environmental management  careful management of natural resources and preventing pollution  encouraging efficient use of energy and other resources  developing sustainable solutions for our clients.

We do this by:  continual improvement in environmental management practices  implementing objectives and targets that support our environmental policy and strategic directions  offering environmentally responsible products and services  integrating environmental considerations into research and development, planning, new projects, investments and operations  ensuring our staff and contractors have the necessary expertise to fulfil their environmental responsibilities.

5.3 Occupational health and safety management

Entura operates under an organisation safety management system certified to OHSAS 18001, an internationally recognised standard for managing occupational health and safety. Our safety managements system is based on the PDCA (plan do check act) cycle to ensure continual improvement of our safety management system and associated procedures. Key elements of our system include risk profiling of key activities to ensure Entura identifies and controls relevant health and safety risks, a yearly management review to assess performance and identify areas for improvement, and a detailed audit program to assess compliance with our systems. Employee health and wellbeing also features prominently in our overall health and safety strategy through a program known as ‘Healthy Hydro’.

5.3.1 Our commitment

We are committed to providing and maintaining a safe and healthy work environment for our people, contractors, customers, and visitors. Our responsibility extends to ensuring Entura’s operations do not place the local community at risk.

We do this by:  identifying health and safety risks associated with any project and ensuring appropriate assessment of risks and development of applicable controls takes place before work commences  ensuring compliance with all legislative requirements  providing and maintaining a safe working environment and safe systems of work  maintaining and communicating written procedures and instructions to ensure safe systems of work

28 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

 providing measurable objectives and targets, ensuring continuous improvement of our safety performance  providing appropriate information, training and supervision to our people, contractors and visitors  encouraging and supporting our people to manage their mental and physical health through initiatives offered under our fitness for work program  ensuring timely rehabilitation and return to work plans for work and non‐work related injury and illness.

29 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

30 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

Appendices

Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

A ASPA required attachments

This section includes following attachments in accordance with ASPA’s RFP FY13.1127.

A.1 Proposal Invitation

A.2 Special Reminders to Prospective Offerors

A.3 Attachment A – Proposal Transmittal Form

A.4 Attachment C – Proposal Cost Form

A.5 Attachment D – Offeror’s Qualification Sheet

A.6 Attachment E – Non‐collusion Affidavit of Prime Offeror

A.7 Attachment F – Disclosure Statements

Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

This page is intentionally blank.

Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

B CVs

Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

curriculum vitae

Simon Gamble

Position Manager Small Renewable Asset Development Business Development – Hydro Tasmania Key areas of • Renewable energy technologies, integration, RAPS development expertise • Project identification, assessment, acquisition and development • New business development and strategic leadership • Commercial negotiation and contract management • Innovative R&D, product development and commercialisation • Engineering, Project and Program Management Qualifications • MBA – Australian National Business School, 2006 • M.Eng.Sc – University of Adelaide, 1998 • B.E (Hons) – University of Adelaide, 1993 • GAICD – Graduate Certificate Australian Institute of Company Directors, 2009 Prizes/awards • Fulbright Scholar – Renewable energy integration applied research and industry engagement, Hosted by the National Renewable Energy Laboratory, Colorado, USA, 2011 • Next Generation Leaders Programme – Australia-Korea Foundation, 2009

Summary of expertise Simon is an executive manager with a 15 year track record of delivering impressive outcome focussed, whole of business results. Simon has demonstrated an ability to build, lead and inspire talented teams to deliver innovative results and produce world leading outcomes. Simon talents span the commercial, technical, environmental and social fields with hands on experience in each of these areas, with specific application in the energy industry. Simon is recognised as an accomplished leader in the Australian renewable energy industry. This leadership position has been recognised most recently through Simon’s selection as a Professional Fulbright Scholar. This opportunity in 2011 to spend five months in the USA engaging with leading research and industry groups provided Simon with a unique perspective of emerging trends, issues and solutions in the scale up of renewable energy in the energy market. Prior to this Simon was selected in 2009 as an Australian delegate in the Next Generation Leaders Programme by the Australia-Korea Foundation. This programme provided an opportunity for Simon to engage with Korean counterparts and institutions and create networks with leaders in sustainability and green growth in Korea. Simon is in demand as a talented speaker at industry events throughout Australia and internationally, with recent specific invitations to present on various topics in Barbados (Clinton Foundation), Japan (IRENA) and Russia (APEC), as well as presenting nationally on wind, energy storage, smart grids, and renewable energy integration in recent years.

Relevant experience Manager Small Renewable Asset Development, Business Development, Current Currently, as Manager Small Renewable Asset Development, Simon has led the development and implementation of Hydro Tasmania’s small and emerging renewable energy and Off-Grid development strategies; the assessment of emerging renewable energy technologies; and the preparation of distributed energy and off-grid power system project feasibility assessments, project approvals and business cases. Simon heads the development of a world leading hybrid power station on King Island in the Bass Strait, Australia. His involvement started with the preparation of the winning application for $15.28m grant fund received from the Australian Federal Government, and the development of the business case for the $40m project. Simon has personally led the community engagement for the project resulting in high levels of engagement and participation as evidenced by the high turn out to Community events and to the Consultative Committee. In continue to advocate for the project Simon has engaged at Federal, State and Local Government level and with the executive management and Board of Hydro Tasmania to influence and negotiate a successful path for the project. In seeking to commercialise emerging renewable energy technologies, Simon has forged a number of partnerships with emerging suppliers in wave, tidal, solar and energy storage technologies. This also incorporated the preparation of an annual technology watching brief report for the Board of Hydro Tasmania and the delivery of the R&D programme for the Corporation, both programmes that were established under Simon’s leadership. Simon has created a network of support for ongoing R&D utilising the King Island facility with organisations including the UTAS, CSIRO, Sandia National Labs, Pacific Northwest National Labs and the US Department of Energy. Regional Manager, South East Asia and Development Agencies, Entura, 2005 – 2007 As Regional Manager South East Asia, Simon developed the strategic sales and marketing plan for the region, and for the identification and account management of key clients in countries such as Malaysia, China, and the Philippines. As Regional Manager Development Agencies, Simon was responsible for the development of business with the Multi-lateral Agencies, including the World Bank, Asian Development Bank, UNEP and AusAID. During this period Simon was successful in winning and/or delivering the following projects for Entura: • Power Rehabilitation Phase 2, Tajikistan, Asian Development Bank (Quote from ADB Project Officer: “I really appreciated your efforts to deliver on time one of the best studies I ever received”) • River Basin Development Optimisation, India, World Bank • Design and Installation of wind/diesel system, Pitcairn Island, Department for Infrastructure Development, UK • Wind energy assessment workshops and training, North Korea, United Nations Energy Programme Simon was also successful in obtaining a further seven short-listings by the World Bank and ADB for projects in PNG, Lao PDR, Sri Lanka, Azerbaijan, Tajikistan, and Fiji during this period. During this period Simon created relationships with key contacts within the ADB, World Bank and United Nations Energy Programme in Washington, Hong Kong, Paris and Sydney. Group Manager, Renewable Energy, Entura, 2003 – 2005 As Group Manager Renewable Energy within the Entura Business, Simon led: the provision of all consulting services provided by Hydro Tasmania in the areas of wind, hydro (small and large), dams, and emerging renewable energy technologies; the leadership and management of over 115 consulting engineers and the financial performance of the group within Entura. Financial and commercial accountability for the Groups’ capital and operational budget and P&L accounts (>$15m pa). Business Development Manager, Wind Energy, 2002 – 2003 As Business Development Manager of Wind Energy, Simon was responsible for acquiring and delivering all wind energy consulting services provided by Hydro Tasmania, including site selection, pre-feasibility and feasibility studies, preliminary and final design of large and small scale wind farms, and provision of business case and due diligence advice to national and international clientele. During this period Simon oversaw the development and growth of Hydro Tasmania’s wind energy expertise and led the team that acquired a wind project pipeline of over 800 MW. During his leadership wind energy consulting services at its peak grew to a team of over 100 FTEs making this the largest wind consultancy business in the Southern Hemisphere at that time. Managing Consultant, Wind Energy, 2001 – 2002 Manager of the Wind Energy Department and the provision of wind energy consulting services. Personally grew the technical wind team from a total of four consultants to an expert team of over 20 staff, making this the largest technical wind unit in Australia at that time.

Other relevant project experience Cathedral Rocks Wind Farm – Member of JV Management Committee, 2006-2008 Led the successful conclusion to the EPC delivery of the 66 MW Cathedral Rocks wind farm on behalf of the Cathedral Rocks Construction and Management JV between Hydro Tasmania and Acciona Energy. Successfully negotiated the rectification of civil defects to allow practical completion of EPC to be achieved. Conducted technical negotiations and assisted commercial negotiations with WTG supplier for yaw gear rectification plan and ongoing wind sector management regime. Project Director, Technical Due Diligence of Wind Farm Developments in Maharashtra (Roaring 40s), India, 2006 Technical oversight and leadership of Due Diligence and risk assessment of two potential wind farm developments in the State of Maharashtra, India. Project Director and Programme Manager, Technical Consulting Services for Large Scale Wind Developments (Hydro Tasmania), 2001 – 2004 • Cathedral Rocks Wind Farm: Feasibility and approvals for the 66 MW project • Heemskirk Wind Farm: Feasibility and approvals for the 140 MW project • : Feasibility and approvals for the 150 MW project • Bluff Point Wind Farm: Technical feasibility of the third stage of the 125 MW Woolnorth project.

Donald Patrick Vaughan

Position Principal Consultant Key areas of • Control systems expertise • Control systems detailed design • Power systems Qualifications • BE (Hons) Elec, University of Tasmania, Hobart Australia - 1993 Memberships • Association of Professional Engineers, Scientists & Managers, Australia • Charted Professional Engineer (CPEng) • Member & Chartered Professional Engineer, Institute of Engineers Australia • Member of Institute of Electrical and Electronics Engineers (IEEE) • Member, Clean Energy Council Grid Directorate

Summary of expertise Donald Vaughn is a Principal Consultant for Entura in the area of primary electrical engineering. He has worked for all sides of the electrical industry (generators, equipment suppliers, customers, NSPs and Market operators), and has 17 years of experience providing advice on regulatory and technical requirements for generators, substations and transmission systems. Donald specialises in the performance of power systems. His experience in generating units, governors and excitation systems provides a helpful perspective of how the physical electrical network behaves. Graduating from the University of Tasmania in 1993 with honours in Electrical Engineering, Donald’s early career included work on automated truck loading systems and bulk fluids handling in the petrol industry. In 1996 he commenced work designing and commissioning generator and stations control systems and ancillary plant, before moving into generator performance, where he defined and implemented compliance tests for generating unit controls against the electricity code.

Power systems Donald has provided power system analysis advice on a wide range of networks and applications including embedded generation systems, grid connected, large scale generating units and transmission or generation projects in all states of Australia. Donald is highly proficient in the modelling of hydro and wind generating technologies with particular expertise and experience in DFIG wind turbines, hydro governors, excitation systems and alternators. Donald also has experience in site testing for parameter determination and model validation.

Control systems Donald has a theoretical and practical understanding of generating unit control systems such as governors, AVRs and PSSs. He has developed and implemented performance and model identification test procedures and analysed the results of site testing to derive models and demonstrate performance.

Control systems detailed design Donald has worked on a number of projects designing control systems for hydro generators and their auxiliaries. This work has given Donald an appreciation of the complex interrelationships between generating unit performance and auxiliary controls.

Selected project experience - Team leader, Musselroe Wind Farm Reactive Support Sizing - Dec-2008 to Jul-2013 Plan, execute and evaluate power system studies to determine reactive power support requirements. Liaise with transmission network service providers, proponents and manufacturers to determine characteristics and drivers for plant selection. Musselroe is a large wind farm located in a remote area of 110 kV transmission. The reactive support is needed for both steady state and dynamic requirements. Roaring 40s - Power Systems Analyst, - Jan-2004 to Jul-2013 • Reactive support requirements • Simplified turbine modelling • Detailed turbine modelling and testing • Loss estimates • Liquidated damages assessment. The development of the Bluff Point and Studland Bay wind farms in the north west of Tasmania. Transend Networks - Technical Lead, Musselroe Wind Farm Connection Studies - May-2009 to Mar-2010 Technical leader for connection studies. Oversight of technical work and review of development of basis for generator performance standards. • Wind farm modelling • Network modelling • Stability analysis. Eureka Funds Management - Technical Lead, Robbins Island and Jims Plain Transmission Connection - Sep-2008 to Mar- 2009 Develop load flow, power voltage analysis, marginal loss factor (MLF), transmission options study for the largest proposed wind farm in Tasmania. Roaring 40s - Power System Analyst, NER Compliance Monitoring Plan - Sep-2007 to Feb-2008 Define a compliance monitoring plan (CMP) in compliance with NER chapter 5 and the guidelines and norms established by NEMMCO, AER and the NGF. Provide input to Roaring 40s Asset management and compliance system pertaining to Generator Performance Standards and NER compliance. Roaring 40s - Technical reviewer, Project Manager, R2 testing of Cathedral Rocks Wind farm - Sep-2004 to Jul-2007 Test design and liaison with client and TNSP (Electranet) to gain approval for testing and then subsequently communicating results and modelling approach to TNSP and NEMMCO. • Test design • Modelling (public domain and measurement inferred block diagram development) • Test results analysis • Model validation. Hydro Tasmania - Technical Advisor and Compliance Plan Developer, NEM Registration and Compliance Monitoring - Jan- 2003 to Jun-2007 Connection and Registration advice for hydro, wind and thermal power stations as per NEC/NER requirements. Development of Compliance Monitoring Plan. Drawing registration, approval and compliance monitoring streams together to meet NER requirements for Generator Performance Standards and Compliance Monitoring Plans within the framework of the NGF process.

2

Hydro Tasmania - Advisor, NEM entry - Jan-2004 to Mar-2006 • Frequency Control and Network Control System Protection Schemes • FCAS capability assessment and registration • Tasmanian frequency control constraint analysis • Generator Modelling Review and Development. A range of small and large projects facilitating the entry of the Tasmanian region to the NEM and Hydro Tasmania as a generator in the NEM. Transend - Technical Advisor, Farrell - Sheffield Stability Limit - Sep-2003 to Sep-2003 Determine the small signal stability limit for a long-heavily loaded transmission line on Tasmania's West Coast A project designed to unlock spare capacity on the transmission line between Farrell and Sheffield due to prior conservative small signal analysis. NRG Flinders - Technical Advisor, Loss of Synchronism Discrimination - Nov-2002 to Mar-2003 Relay setting studies to allow SRAS capability at Northern Power Station SA. A study to discriminate between network collapse and maintenance of thermal plant operation to enable system restart. Facilitating the ‘trip to house’ for system restart support of the Northern power station units in South Australia. Hydro Tasmania - Lead technical resource, Hydro Tasmania TEC Compliance - Jan-2000 to Dec-2002 Design, implement and analyse testing of generating unit controls to enable detailed dynamic models to be developed suitable for power system analysis. • Legacy equipment design review and block diagram development • Test procedure development • Site measurement • Performance assessment relative to electricity rules • Model validation. NEMMCO - Data analyst, QNI Small Signal Analysis - Jan-2001 to Jan-2001 Small Signal mode analysis for Queensland New South Wales Interconnector (QNI), assessing pre and post test system conditions and identifying mode locations. The commissioning of a new interconnector between Queensland and New South Wales. Specifically the NEMMCO due diligence around the stability of the new interconnector for increasing power transfers.

3

Seth Langford

Position Specialist Engineer Key areas of • Due diligence studies • Wind data assessments expertise • Feasibility studies • Wind power • Renewable energy project assessment • Wind resource assessment • Renewable energy resource assessment • Wind site identification and assessment • Renewable energy solar-diesel systems • Wind turbine performance data analysis • System performance analysis and modelling • Wind turbine selection Qualifications • Bachelor of Engineering (1st Class Honours) - 2000 • Bachelor of Science - 1998

Summary of expertise Seth has 10 years’ experience in the renewable energy industry as a technical specialist, team leader and project manager on feasibility studies, due diligence projects and major wind farm projects in Australia, India, Sri Lanka, South Africa, New Zealand and China. He has also been involved with feasibility studies of wind and wind-diesel projects and in a review role for Entura’s PV solar projects. Seth has spent considerable time in India and China on behalf of developers assessing greenfield and operational wind farms for the purposes of acquiring projects. As part of his work, Seth has been involved with assessments of projects using the following wind turbine manufacturers: Enercon, Vestas, Suzlon, Siemens, Goldwind, Nordex, GE, Gamesa, Regen Power Tech, REPower and Sinovel. During this time, Seth has worked on the energy assessments for wind farms of over 5000 MW.

Selected project experience Confidential - Project Manager and Technical Specialist, South African Wind Farm (100MW) - Dec-2008 to Jul-2013 Project Management and Technical Specialist assisting with a wind farm development project in determining wind resource and energy estimates. This project is now in its final stages of completion. Suzlon - Project Manager and Technical Specialist, Bhanwad Wind Farm Due Diligence - Feb-2012 to Apr-2012 Technical due diligence of a wind farm portfolio in India, including presentation of findings to financial institutions. Independent review of wind conditions at site and likely energy generation. Providing ongoing support in assessing 10 separate projects under this portfolio. CLP Power India - Project Director and Technical Specialist, Andhra Lake Wind Farm Due Diligence (114 MW) - Aug-2007 to Apr-2012 Project Director and technical specialist coordinating Entura’s input into the technical due diligence of the wind resource assessment for CLP India. This work initially consisted of a site visit and a review of the wind monitoring practices, the design techniques of the wind farm layout, the proposed connection to the electricity grid, and an independent analysis of the wind resource assessment, extreme wind speed risk and the wind turbine suitability. Revision of original assessment with further wind data captured by additional wind monitoring infrastructure installed after initial assessment. Project direction of latest studies in 2010 looking at the wind turbine suitability and likely energy generation for the wind farm.

National Development Bank and LTL Holdings - Project Director, Kalpitiya Wind Power Project - Technical Due Diligence - Oct-2010 to Jun-2011 Prepared a long term annual energy assessment for the 10 MW project for two proposed wind farm layouts. Technical due diligence of the project including: wind farm design, permits and licences, WTG supply contracts and specifications, business case models, and development schedules. Enercon India - Project Manager and Technical Specialist, Enercon India Wind Farm Portfolio (440MW) - Jan-2010 to May- 2011 Technical due diligence of a wind farm portfolio in India, including presentation of findings to financial institutions. Independent review of wind conditions at site and likely energy generation. Providing ongoing support in assessing 10 separate projects under this portfolio. TKLN Solar (Epuron) - Project Director, TKLN Solar - 3 Solar Farms (1MW) - Jun-2010 to Sep-2010 Oversight of project team conducting due diligence works looking at augmenting existing diesel generators with additional PV solar systems for three sites in the Northern Territory. Responsibilities included delivery of reports and technical coverage of all necessary areas, including battery back-system, inverters, solar resource analysis, and general project due diligence CLP Power India - Project Manager, Technical Specialist and Owner's Engineer, Samana Wind Farm Due Diligence (100.8MW) - Apr-2007 to Feb-2010 Project manager and technical specialist coordinating Entura’s input into the technical due diligence of the wind resource assessment for CLP India. This work consisted of a site visit and a review of the wind monitoring practices, the design techniques of the wind farm layout, the proposed connection to the electricity grid, and an independent analysis of the wind resource assessment, extreme wind speed risk and the wind turbine suitability. Owner's engineer role through pre-construction stages advising on impacts of layout changes, wind monitoring mast requirements to support warranties, and other issues arising as the project is developed. Confidential - Technical Specialist, Indian Operational Wind Farm Portfolio Acquisition (200+MW) - Nov-2009 to Jan-2010 Technical Specialist as part of an acquisition process advising on likely energy generation, review of operations and maintenance practices at each wind farm, and condition of operational wind turbines. Hydro Tasmania/Roaring 40s - Technical Specialist, Musselroe Wind Farm, Heemskirk Wind Farm, and Woolnorth Wind Farm - Jan-2004 to Jul-2009 Technical specialist for Roaring 40s assisting with wind resource assessment and final layout design for feasibility studies and business case submissions, including comparisons of different wind turbine types. Wind engineer participating in wind farm layout optimisation for alternative transmission connection scenarios including assessments of the impact of future transmission constraints at Musselroe Wind Farm and at Woolnorth Wind Farm (Bluff Point and Studland Bay Wind Farms). Wind engineer conducting an operational assessment of the energy production at Woolnorth Wind Farm. Macquarie Capital - Project Director and Technical Specialist, China Wind Farm Portfolio Assessment (2000MW) - Nov-2008 to Feb-2009 Project Director and Technical Specialist for a project looking at a wind resource assessment of a portfolio of 30 wind farms. The wind farms were at different stages of development each consisting of multiple 50 MW stages. The assessment included a review of the wind monitoring practices, the design techniques of the wind farm layout, the proposed connection to the electricity grid, and the wind turbine suitability. CLP Power India - Project Manager, Technical Specialist and Owner's Engineer, Saundatti Wind Farm Due Diligence (82.4MW) - Aug-2007 to Feb-2009 Project manager and technical specialist coordinating Entura's input into the technical due diligence of the wind resource assessment for CLP India. This work consisted of a site visit and a review of the wind monitoring practices, the design techniques of the wind farm layout, the proposed connection to the electricity grid, and an independent analysis of the wind resource assessment, extreme wind speed risk and the wind turbine suitability.

2

Project manager of the condition assessment of an operational wind farm in Maharashtra to assess the suitability of the proposed wind turbine technology for the Saundatti site. This work consisted of a site visit to an existing wind farm including inspection of the site terrain, the operational wind turbines and spare parts, an examination of operation and& maintenance records and discussions with wind farm operators. Owner's engineer role through pre-construction stages advising on impacts of layout changes, wind monitoring mast requirements to support warranties, and other issues arising as the project is developed. Roaring 40s - Project Manager and Technical Specialist, Hainan Island Wind Farm Due Diligence (4 x 50 MW) - Oct-2006 to Jan-2009 Project manager for Roaring 40s’ wind farm development program on Hainan Island including attending an in-country workshop with the Guangdong Meteorological Bureau to assess the design techniques employed by the GDMB and the local Design Institute. Recommendations were made regarding the techniques used for wind data assessment, instrument calibration processes and equipment, instrument selection and the physical layout of the wind monitoring masts on Hainan Island. Key technical advisor undertaking Entura's input into the technical due diligence of the wind resource assessment for two (2) wind farms, Mu Lan Wind Farm and Weng Tian Wind Farm, on behalf of Roaring 40s. This work consisted of a review of the wind monitoring practices, the design techniques of the wind farm layout, and an independent analysis of the wind resource assessment, extreme wind speed risk and the wind turbine suitability. Key technical advisor providing an assessment of the wind resource and resulting likely energy generation at Eman Wind Farm. Hydro Tasmania/Roaring 40s/Acciona Energy - Project Director and Technical Specialist, Cathedral Rocks Wind Farm Operational Assessment (66 MW) - Jul-2002 to Dec-2008 Project director coordinating Entura's multi-disciplinary input (and management of OH&S matters) into the operational optimisation process for the operational Cathedral Rocks Wind Farm providing key technical advice on wind flow behaviour and wind turbine operational characteristics, including modelling of key wind farm parameters. Technical advisor for the commercial team involved with the resolution of the operational issues at Cathedral Rocks Wind Farm providing key advice on impacts of negotiations both with counterparties and financial institutions. Technical advisor providing key expertise in undertaking wind resource assessment, energy assessment, layout design and other related tasks as part of the feasibility analysis during the pre-construction phase of the project. CLP Power India - Project Manager and Technical Specialist, Suzlon Wind Farm Due Diligence (25 MW, 3 x 50 MW) - Jul- 2006 to Nov-2008 Project manager and key technical advisor coordinating Entura's multi-disciplinary input into the technical due diligence. This work included in-country assessment of production facilities for a wind turbine manufacturer, construction practices, training programs, operation and maintenance methodology, design techniques (for wind resource assessment, wind farm layout and wind turbine selection), site visits to both operational and proposed wind farm sites and providing advice on commercial/contractual issues associated with the proposed wind farms. Roaring 40s - Client Seconded Technical Advisor, Rongcheng Wind Farm, Stages 2 & 3 (100 MW) - Apr-2008 to Oct-2008 Technical Specialist seconded to Roaring 40s conducting a site assessment on behalf of Roaring 40s and managing the technical due diligence of the wind resource assessment for Roaring 40s using external consultants. Each stage of the wind farm consists of 50 MW. This work consisted of a site visit and discussions with project partners in China. Tasks included within the site visit are a review of the wind monitoring practices, the design techniques of the wind farm layout, the proposed connection to the electricity grid, and the wind turbine suitability.

3

Preeti Arora

Position Engineer Key areas of • Generator expertise • Power systems • Pre-feasibility • Tender technical specification Qualifications • Bachelor of Electrical Engineering (Honours) University of Auckland, New Zealand - 2007 • September 2012 – Ongoing Postgraduate Diploma in Management (Part time) Melbourne Business School

Summary of expertise

Preeti has 6 years’ experience within the power industry. Her technical expertise includes leading the grid connection process from initial assessment of options and constraints through to achievement of connection. This includes feasibility studies, regulatory compliance (connection enquiries, applications, generation registration and license application processes), power system studies comprising plant modelling, load flow analysis and dynamic stability analysis using PSS/E, SKM Power Tools, DigSILENT and Mathematica.

Power systems Power system modelling and analysis using PSS/E - Static and Dynamic. Generator Generator connection applications and performance standards - regulatory compliance. Pre-feasibility Pre and detailed feasibility studies, costing, reticulation and high level grid connection design. Tender technical specification Tender specifications (electrical scope of works and long lead items’).

Selected project experience Top Energy Ltd - Graduate Engineer, Tender for construction of 4 green field substations in Fiji - Jun-2007 to Jul-2013 Liaising with various equipment suppliers and design consultants for best price. Comparison of technical information provided by the suppliers with what is required. Preparation of financial spreadsheets and withholding Tax calculations. Preparation of tender documents. ACCIONA Energy - Power Systems Engineer, EPC bidder for proposed 250 MW wind farm - Dec-2012 to Apr-2013 Finalised high level design of proposed 250 MW wind farm project ACCIONA is bidding on as an EPC contractor. Written and released the electrical scopes of work RFP to various electrical contractors. Finalised reticulation design and commenced initial network fault level studies Various wind farm sites in prospecting stage. High level feasibility analysis in progress to determine best grid connection options; Costing connection options to determine project economics for ranking sites.

ACCIONA Energy - Power Systems Engineer, Mt Gellibrand wind farm - Mar-2012 to Apr-2013 Completed detailed feasibility study, PSS/E static and dynamic studies and submitted Generator Performance Standards to AEMO. Finalised work on tender arrangements and contract models for electrical works relating to shared and connection assets with AEMO. Finalised and released the electrical scopes of work RFP to various electrical contractors. In process of proposing changes to PFRs and PCRs to reduce interface costs for Mt Gellibrand Terminal Station. ACCIONA Energy - Power Systems Engineer, Various Projects - Jul-2008 to Apr-2013 Pre and detailed feasibility analysis. Connection enquiries. Detailed costing. Design of reticulation system. ACCIONA Energy - Power Systems Engineer, Re-assessment of 22 kV Reactors at Waubra Terminal Station - Jul-2012 to Mar-2013 Re-negotiating Generator Performance Standards with AEMO to allow disconnecting 29 MVAr reactors at Waubra Terminal Station (providing a significant reduction in losses). Detailed steady state and dynamic studies using PSS/E done against the requirements of NER to assess the impact of disconnecting reactors on the transmission network. Based on the findings presented in the report and negotiation activities, disconnection of the two tertiary winding reactors on the 220/66/22 kV transformers is acceptable to AEMO. ACCIONA Energy - HV Engineer, Study to meet SA Reactive Requirements - Jul-2011 to Nov-2011 Studied in detail South Australian Licence Requirements for connecting new generation using SKM PowerTools and PSS/E. Detailed load flow analysis done to determine capacitive or inductive support required at proposed . Connection - Jun-2009 to Mar-2011 Completed Generator Registration Application process. Completed Static and Dynamic Studies which formed part of Generator Performance Standards and Connection Agreement. Completed and submitted Generator Compliance Program to AEMO. Conducted SCADA and site tests to prove model validation. Designed reticulation system and assisted Senior Power Engineer in preparing electrical works specifications. ACCIONA Energy - HV Engineer, Federal Government’s Solar Flagships Program - Nov-2009 to Feb-2010 Pre-feasibility studies and costing for various initial sites in Australia. Full detailed feasibility studies (using PSS/E), detailed costing, timelines, connection enquiries and reports for four of the chosen photo-voltaic (PV) and concentrated solar power (CSP) sites. Top Energy Ltd - Graduate Engineer, Network Augmentation at 33/11 kV Kerikeri Substation - Nov-2007 to Mar-2008 Supported Planning Engineer by developing comprehensive network models on DigSILENT software for proposed 33/11 kV substation. Developed matrix with various ‘what-if’ scenarios to identify benefits of capital investment in existing feeder strengthening, voltage support solution and critical costs associated with the project. Top Energy Ltd - Graduate Engineer, Reliability Improvement on Top Energy’s 10 Worst Feeders - Mar-2007 to Jan-2008 Analysed fault data to develop financial model that correlated outage statistics. Used reliability indices to prioritise installation of over-current devices. Introduced and installed 102 ganged dropout sectionalisers and 6 reclosers on Top Energy’s network. Presented as a paper at EEA’s Annual Power Engineering Exchange (APEX), 2007.

2

Dhammika Ranjith Perera

Position Specialist Electrical Engineer Key areas of • Generator connection studies/application expertise • HVDC • NER compliance • Power station pre-feasibility • Power systems • Utility power quality • Wind power Qualifications • Master of Engineering, “Development of Controller for the Dynamic Voltage Restorer (DVR)”, Nanyang Technological University, Singapore - 2000 • BSc Engineering (Electrical), 1st Class Honors, University of Moratuwa, Sri Lanka - 1993 Memberships • Member, Institute of Electrical and Electronics Engineers (IEEE)

Summary of expertise Ranjith Perera is a Specialist Electrical Engineer in Power System team, responsible for power system studies and network connections. Ranjith performs power system planning, network modelling, dynamic simulations and analysis. This role requires Ranjith to be involved in connection agreement process and continual close liaison with utility/AEMO for the approval. With fifteen years' experience in the electrical filed across wide range of disciplines (power system planning, transformer design, substation constructions, power quality analysis, insulation coordination and generator connections), currently Ranjith manages complex generator connection approval process. Ranjith worked both within Australia and internationally, including the Singapore, Malaysia, Sri Lanka and Solomon Islands. With qualifications in electrical engineering, Ranjith has received a number of prizes for his high achievement in academic and research work. He also received Master of Engineering from Nanyang Technological University, Singapore. Ranjith has published several technical papers including IEEE transaction papers. Wind power Ranjith's experience extends in conducting network planning, pre-feasibility, feasibility and connection studies for the wind farms. This includes development of Generator Performance Standards (GPS) as part of connection agreement. Also he has experience in development of test plans, wind farm testing, model validations and tuning of model parameters. Power systems Ranjith has provided power system advice on a wide range of networks augmentations, network planning and system stability in Australia and overseas. These studies include option analysis in transmission planning, constraint analysis, determination of reactive support (dynamic or static) in system stability/TOV and detail load modelling in voltage stability. Ranjith also developed voltage recovery guidelines to TNSP based on regulatory requirement and customer equipment tolerances. Utility power quality Ranjith has conducted power quality analysis in various parts of power system including, harmonics due to non-linear loads, harmonics resonances due to capacitor banks, flicker due to rapid changing loads, Transients due to lightning/ capacitor switching and voltage dip due to starting of induction machines/system faults. He is competent with the requirements under AS/NZS 61000.3.6 and AS/NZS 61000.3.7 in power quality. Ranjith also specialise in conducting TRV/RRRV studies to determine new (or evaluate existing) circuit breakers in generating stations and transmission networks.

Selected project experience AECOM - Specialist Engineer, Purari Hydro Project - Jul-2011 to Feb-2013 Conduct option studies including HVDC option. Preliminary modelling of HVDC and key option evaluation. Marginal Loss Factor (MLF) calculations. PSCAD modelling. 2500 MW HVDC link with more than 1000 km transmission line and undersea cable. Transend Networks Pty Ltd - Specialist Engineer, Review/ Redesign of Network Control Special Protection Scheme (NCSPS) - Sep-2012 to Jan-2013 Conduct PSSe studied to identify parameter used in the new NCSPS. Validate the design using dynamic simulations. Optimum and generic generator selection algorithm. Melbourne Water Corporation - Specialist Engineer, Thomson Hydro Connection Study - Apr-2010 to Oct-2012 Conduct power system study to connect 7 MW induction generator to a weak 22 kV distribution network. Provide solution to mitigate generator starting voltage drop. Write and review equipment specifications. Conduct presentation to SP Ausnet. Provide technical advice during commissioning. Confidential Client - Specialist Engineer, Development of Gas Generation Sites in NSW, VIC and QLD - Nov-2011 to Sep-2012 Conduct fatal flow analysis for large number of sites. Conduct pre-feasibility for selected sites around NSW, VIC and QLD. Calculate Marginal Loss Factors (MLF) and analyse revenue loss due to network constraints. Work with different disciplines (water, environmental, gas and commercial). Discussion with various network utility companies. Downer EDI Engineering Power Pty Ltd - Specialist Engineer, Karara Mine Connection Option Study - Nov-2010 to Jul-2011 Conduct option studies. Conduct dynamic simulations to decide maximum power transfer during weak network option (early mine operation). Analyse transient stability and determine reactive support requirement. Due-diligence of previous Western power studies. Coordination with Western Power. Evaluate reactive support requirement. Transient stability analysis. Energex Limited - Specialist Engineer, Brisbane CBD Network Option Study - Jun-2010 to Jan-2011 Conduct PSS/e simulation to identify optimum network option to satisfy Energex's CBD planning requirements. Conduct presentation to Energex's management. N-1-1 and N-2 planning studies. This involved range of network augmentation options and switching arrangements to find the optimum outcome to Energex. Alstom Power Limited - Senior Engineer, Burdekin Falls Hydro - Electrical Review - Jun-2010 to Jun-2010 Evaluate optimum transformer tap range for the generator transformer. Conduct TRV/RRRV studies to select a suitable generator circuit breaker. TRV/RRRV studies. Transend Networks Pte Ltd - Senior Engineer/Project Manager, Southern Region Dynamic Voltage Stability Analysis - Apr- 2009 to Jun-2010 Conduct voltage stability simulation and analysis for southern region of Tasmania. Develop voltage recovery recommendation paper. Incorporate complex load modelling. Show importance of accurate load modelling to voltage stability in Tasmania. Successfully managed the project to expectation of the client on budget and time. Melbourne Water Corporation - Senior Engineer, Mini hydro connection studies for Melbourne Water and SP Ausnet (2006/2007) - Aug-2006 to Feb-2010

2

Olinda mini hydro: Conduct system studies for the proposed induction generator. Silvan mini hydro: Conduct system studies for the proposed induction generator. Upper Yarra mini hydro: Conduct system studies for the proposed synchronous generator. Sugarloaf mini hydro: Conduct system studies for the proposed induction generator. Connection studies to satisfy the NER. Connection to weak distribution network involve challenging analysis/solutions to meet distribution code requirements. Generator staring voltage drop. AEMO - Specialist Engineer, Taralga/Gunning/Cullering Range/ Connection Studies (Due-diligence) - Jan-2009 to Apr-2009 Conduct due-diligence studies. Review Generator Performance Standard (GPS). Identification of model discrepancy. Transend Networks Pty Ltd - Senior Engineer, Lindisfarne-Risdon Substation Reactor Replacement - Apr-2008 to Dec-2008 Conduct harmonic analysis for range of network operating scenarios. Design harmonic filter. Proposed capacitor bank operation guideline. Harmonic studies using PSCAD. McLennan Magasanik Associates - Senior Engineer, Robbins Island Wind Farm - Apr-2008 to Sep-2008 Conduct pre-feasibility studies to connect 300 MW wind farm to Tasmanian network. Roaring 40s - Senior Electrical Engineer, Vestas V66, V80 and V90 wind farm parameter verification - Dec-2007 to Jan-2008 Wind farm parameters are verified against the Generator Performance Standard submitted to NEMMCO. This includes checking of all protection settings, AGO operation settings and reactive power limits in the turbines. Wind farm model verification work. Roaring 40s - Senior Electrical Engineer, Wind Farm Model Verification and Tuning - Jun-2007 to Nov-2007 Conduct site test to verify overall wind farm performance and model validation. Parameters of the wind farm model was tuned based on the on-site test results. Tuning of parameters of the wind model to represents actual performance. Hydro Tasmania - Technical & Operations - Senior Electrical Engineer, Constraint Analysis - Jun-2005 to Aug-2007 Conduct transmission line constraint analysis work for Hydro Tasmania's Technical & Operations group (2005/2006). Develop constraint analysis tool to evaluate constraints. This covers all constraints in Tasmanian network and key Victorian constraints. Analysis of constraint to optimise Basslink flow. Roaring 40s - Project Manager, Reactive support of Studland Bay wind farm - Oct-2005 to Sep-2006 Due-diligence of connection studies. Evaluate dynamic reactive support requirement to suppress temporary over voltage (TOV) due to 600 MW load rejection by Tasmanian DC link to mainland Reactive support design for the wind farm. Design appropriate switching scheme to avoid TOV.

Roaring 40s - Senior Engineer, Studland Bay wind farm connection study in Tasmania - Jan-2006 to Aug-2006 Conduct system studies for wind farms connection applications. This involves dynamic and steady state studies. Simulations and data verification.

Roaring 40s - Project Manager, Studland Bay/Bluff Point/Musselroe wind farms transformer tap-design in Tasmania - Sep- 2005 to Dec-2005 Evaluate suitable tap-range to cover all three wind farm project with a single rated transformer. Designing a tap range for wind farm transformer.

3

curriculum vitae

Ray Massie

Position Senior Renewable Energy Engineer - Business Development Key areas of • Renewable Energy Advice expertise • Remote Area Power Supplies • Energy Resource assessment • Site Assessment • Renewable Energy Project Assessment • Feasibility studies • Detailed Design • Project Management Qualifications • Post Graduate Diploma in Energy Studies, Murdoch University, Australia, 2008–10 • MBA – Australian National Business School, 2006 • M.Eng.Sc – University of Adelaide, 1998 • B.E (Hons) – University of Adelaide, 1993 • GAICD – Graduate Certificate Australian Institute of Company Directors, 2009 Prizes/awards • BE Civil Engineering – University of Tasmania, 1986 • Post Grad Diploma – Murdoch University, WA, 2009

Summary of expertise With over 25 years’ experience, Ray continues to be a key player in developing Hydro Tasmania’s renewable energy technology expertise. He has been the primary expert in developing the skills and capabilities for HTC’s renewable energy team. He is also in the role of advising the wider business on developments in the renewable energy industry, both technically and strategically covering wind, solar, ocean, geothermal, as well as electric vehicles, energy storage and wide range of emerging demand side and supply side options impacting the energy industry. He has managed multi-disciplined teams in many aspects of renewable energy project development and technical specification for many projects both at utility scale as well as Remote Area Power Systems, including the Bass Strait Islands, Pitcairn Island and Cape Barren Island Projects. His involvement in Wind Farms started in 1997 and has continued since then concentrating largely on wind farm development. He is experienced in many aspects of Wind Farm Development including wind resource assessment, data collection, wind data analysis and modelling, site assessment through to wind farm layout and micrositing. His wind analysis experience included extensive use of software packages such as WAsP, WindFarm, WinMap and Meso scale modelling of wind resources. He has managed multidiscipline teams in many aspects of project development including investigation, site assessment, resource assessment, concept design, feasibility assessment, business case development and technical specification for many projects for both internal & external clients. He took a primary consulting role in developing the capabilities of BC Hydros wind team in Vancouver, Canada (2001–2003) developing and delivering a training program to the BC Hydro Staff. He also helped BC Hydro in assessing potential wind farm sites across British Columbia, assisting them in developing a way forward for their Wind Energy Developments. His broader experience has involved working on renewable energy projects, primarily in wind & hydro covering resource assessment, feasibility studies, civil & structural detail design, tender specification and evaluation, cost and economic modelling and construction supervision. Over this time he has developed considerable computing skills as well.

Relevant experience • Investigation and feasibility of high renewable energy penetration Remote Area Power Systems across Australia and Pacific region, 2010–13 • Undertook feasibility and development of Hydro Tasmania’s King Island Renewable Energy Integration Project (KIREIP) – a high renewable energy RAPS system that allows 100% renewable energy • Principal Role for advising Hydro Tasmania internal business on developments in the renewable energy business, 2008–10 • Developing business strategy for developing power system on Bass Strait Islands, 2008–09 • Team Technical Leader role for design of remote area power supply for Cape Barron Island undertaking wind energy assessment and system optimisation, Australia, 2007–08 • Team Technical Leader role for design of remote area power supply for Pitcairn Island undertaking wind energy assessment and system optimisation and economic assessment, UK Territory (Pacific), 2007–08 • Lead Renewable Energy advisor for assessment of renewable energy options for Desalination project in Victoria coordinating a team of people assessing the options of wind , wave, tidal, solar, bioenergy and geothermal, Australia, 2008 • Lead Technical role for assessment of renewable energy options for Cook Islands power system augmentation study, Cook Islands, 2007 • Renewable energy assessment for wind, hydro, wave and tidal options as part of renewable energy options study for Rio Tinto, Australia, 2007 • Design Engineer for Melbourne Water Mini Hydro Projects undertaking technical design as well as project management of two mini hydro EPC projects, Australia, 2007 • Owners Engineer for Tender Development for Musselroe Wind Farm (129 MW), Australia, 2006 • Team Leader – Wind Feasibility & Design Team (2004–05) • Project Manager for Studland Bay Wind Farm (75 MW) Finalisation, Australia • Consultancy development for Canadian Wind Energy Developer • Management of Due Diligence Process for Cathedral Rocks Wind Farm, Australia • Seconded to BC Hydro for 6 months in Canada to act as wind energy expert • Providing onsite training to BC Hydro in Wind data Analysis & Wind Resource assessment including site investigation on Malcolm Island, 2001 • Consultant to BC Hydro on assessing potential wind farm sites in BC. Both through rigorous resource analysis and mapping as well as on site assessment and verification of identified sites • Principal role in the identification and assessment of prospective wind farm sites in Tasmania, Mainland Australia and New Zealand, and includes the preparation of wind speed and wind farm potential atlases incorporating engineering, environmental and economic variables as well as stakeholder management • Technical team leader for feasibility study into Hydro Tasmania’s Musselroe wind farm in NE Tasmania • Responsible for constantly developing the techniques used in Wind Resource and Farm assessment with in Hydro Tasmania Previous experience • Investigation of the best small/mini hydro sites in Tasmania in relation to the emerging renewable energy policies in Australia, 1999–00 • Anthony Power Station (Single Machine, Underground), Australia o Operating Floor (suspended concrete slab) - Design of supporting steelwork and concrete floor o Generator Floor (suspended slab including generator stator blocks) - Design of reinforced concrete floor supporting generator loads o Steel Generator Support Cylinder (stiffened steel cylinder directly below generator) o Structural design review station crane beam. Review the design of a reinforced concrete beam fixed to the rock cavern wall of the station. • Crotty Dam, Australia o Design of Crotty Dewatering Outlet Plug and concrete work associated with Controllable dewatering outlet for Crotty Dam. Outlet is in a tunnel at the base of a 70 m shaft o Construction Liaison for Crotty Dewatering Outlet and Dewatering Shaft o Preliminary Design for Crotty Dewatering Shaft Control House. • King Power Station Generator Floor, Australia o Structural design review of Power Station Generator floor o Design of concrete Intake deck for the installation and removal of intake gate and stoplogs. Designed to crane and bridge codes o Design of Tailrace Retaining Wall - an 11 m high reinforced concrete retaining wall at the outlet of the station. • King Intake Structure, Australia o Structural design review of Intake structure and trashracks. • Clark Dam Intake Gate Crane, Australia o Structural design for replacement intake Gantry Crane at Clark Dam (Butlers Gorge). • Assessment of HEC Bridges o Structural assessment and appraisal of various HEC bridges. • Upgrade of Penstock Hilltop Valves, HEC Tasmania, Australia o Computer modelling of hydraulic/mechanical interaction of various closing operations of two hilltop valve systems. Including surge effects in surge chamber and modelling of piston hydraulic controls.

Daniel Bennett

Position Renewable Energy Engineer Key areas of • Business development expertise • Geographic information systems • Modelling and pre-feasibility study • Programming • Renewable energy • Solar energy • Wind resource assessment • Wind site identification and assessment • Wind turbine siting Qualifications • Bachelor of Engineering (Hons)/Bachelor of Computer Science (University of Melbourne) - 2003

Summary of expertise Daniel has worked on renewable power projects since joining Entura in 2008. He has gained an understanding of the analysis required to produce energy estimates from recorded wind and operational data, and the requirements involved in wind turbine selection based on the site conditions. He has reviewed wind monitoring masts and power curve verification tests. He has also worked on wind farm site identification and land owner negotiations. He has performed resource mapping for both wind and solar radiation, at local and mesoscale levels.

Geographic information systems Daniel has a number of years ‘experience with ArcGIS, AutoCAD, and 3D design packages such as Inventor and SolidWorks.

Modelling and pre-feasibility study Daniel has been working with the industry standard wind farm modelling packages since joining the company, and has a good understanding of WAsP, WAsP Engineering and GH WindFarmer.

Renewable energy Daniel has a good general understanding of the issues relating to wind energy, as a part of the Renewables industry.

Wind resource assessment Daniel has taken part in wind resource assessments across a number of sites, providing analysis of the wind conditions expected at the site, estimates of energy outputs, and suitability of particular locations for wind turbine siting.

Wind turbine siting Daniel has worked on the siting of wind turbines to maximise energy output and reduce the wake losses resulting from complex wind farm arrangements.

Wind site identification and assessment Daniel has performed high level site identification work, broadly assessing areas to select suitable sites for wind farms.

Business development Daniel assisted in the customer survey stage of Hydro Tasmania's Customer and Revenue strategy project. This involved

exposure to marketing strategy, product development, and face to face interviewing of prospective retail customers.

Programming Daniel has a wide exposure to numerous programming languages and environments, through study and employment. He is capable of working with programs in Visual Basic, C, Java, Python and Matlab scripting, and is familiar with the process of software specification and design.

Solar energy Daniel has hands on experience with solar monitoring equipment, as well as familiarity with prediction of solar resource across local and wider regions.

Selected project experience Confidential - Test Engineer, Power curve test including Site Calibration - Aug-2012 to Jul-2013 Supervision, reporting and analysis of an IEC 61400-12 compliant Power performance test, including Site Calibration. Hydro Tasmania - Wind Engineer, Hydro Tasmania Wind Developments assistance - Jul-2011 to Jul-2013 Technical assistance on Hydro Tasmania's wind development program. In particular, work on the Musselroe Wind Farm leading up to construction commencing in 2012, due diligence on potential project acquisitions, and further early development stage investigations and reporting. Confidential - Test Engineer, Wind turbine power curve test - May-2012 to Jan-2013 IEC 61400-12-1 Power performance test supervision, including site visit to review test setup. Data collection and analysis. Reporting of results. Both the client and manufacturer were inexperienced with the requirements of the test, so significant work and educating was necessary to ensure compliance with the best practices and the standard. CLP India - Wind Engineer, Indian wind farm site visits - Nov-2011 to Dec-2011 Travelling with the client and wind turbine supplier, visit and assess wind monitoring masts at five proposed wind farm sites. Identify and request further information from the supplier. Assess key factors across wider wind farm site, and visit nearby operating wind farms which may assist in energy estimates to be performed at a later stage. Department of Sustainability and Environment - Technical Lead, Melbourne Urban Solar Atlas - Jan-2010 to Dec-2011 Assess the technical feasibility of the creation of an urban solar atlas covering the Melbourne metropolitan area. Investigate available tools, test software, identify practical solution to produce suitable results for the end-user. In the prototype development stage, performing data processing by creating automated tools to run analysis, and assisting with the web server setup and web site design. First stage - Feasibility assessment, Second stage - prototype development for demonstration purposes. The tool is designed to allow a home user to assess the potential energy output of installing solar panels on their residence. Using a web interface, a user will zoom to their address and be able to see the best location and energy estimate for their roof for solar panel siting. Roaring 40s Renewable Energy - Wind Engineer, Roaring 40s secondment - Nov-2010 to Jun-2011 Daniel was permanently seconded to Roaring 40s' Melbourne office for a period of 8 months. During this period he worked in the Roaring 40s wind technical team, performing a range of technical tasks for Roaring 40s development and wind farm operations. These included: Site Identification; Managing incoming Mast data; Turbine review and selection; Wind farm energy estimates. operational assessment and preliminary Site Calibration and Power Curve Verification. Musselroe Wind Farm energy estimate, and participation in Due Diligence process on proponent side.

2

Confidential - Project Manager and Renewable Engineer, Wind mapping and indicative site suitability - Jul-2010 to Sep- 2010 Project managed a wind mapping study and delivered report providing high level assessment and recommendations of next steps for progressing the development of wind energy. Wind mapping and basic introduction to methodology of assessing wind farm sites. Recommendations for further work to progress potential wind projects. Confidential - Wind Engineer, Indian due diligence - Mar-2010 to Jul-2010 Performing an assessment of the design of a developer's 50 MW proposed wind farm, to provide technical analysis of wind data and a long term energy estimate. Turbine manufacturer Regen proposed a layout of 33 turbines, at a site previously assessed for the client. Further wind monitoring data was assessed. Yarra Valley Water - Renewable Assessment and Project Manager, Renewable energy options study - Apr-2010 to Jun-2010 Conducted preliminary site assessment of multiple client owned sites, incorporating desktop resource assessment, site visit, options generation and presentation of findings for potential wind and solar generation projects. Project managed delivery of report. Multiple renewable energy technologies assessed for potential installation, including Wind, Solar, Hydro, Biogas, and Geothermal. Atoll - Wind Engineer, Small wind turbine technology assessment - Jul-2009 to Sep-2009 Technical due diligence tasks covering manufacture, components, systems, non-standard design Client required an assessment of a small wind turbine manufacturing company, covering the technical aspects of their product. The wind turbines assessed were vertical axis design and rated at up to 8 kW CLP India - Wind Engineer, Theni Wind Farm due diligence - Apr-2009 to Aug-2009 Performing an assessment of supplied data from a developer's 100 MW proposed wind farm, to provide technical analysis of wind data and a long term energy estimate. Turbine manufacturer Vestas proposed a layout of 120 V82 turbines, offering 60 to the client. The site showed high seasonality in wind distribution, and adjustments were required as the modelling did not adequately capture this variation. Roaring 40s - Wind Engineer, Site assessment - Oct-2008 to Jul-2009 Producing preliminary turbine layouts for possible sites supplied by the client with consideration for risks due to electricity grid connection, terrain, vegetation, fauna, and noise restrictions. Roaring 40s - Wind Engineer, Site identification work - Nov-2008 to Mar-2009 Performing broad site identification and ranking to provide the client with a targeted list of possible wind farm sites. This identification work involved consideration of wind resource, grid proximity, environmental and planning risks, and access. ArcGIS software used to produce maps of areas. Roaring 40s - Wind Engineer, Xiangyang Long Term Annual Energy Output Estimate - Aug-2008 to Sep-2008 Principal author of Wind data analysis, turbine suitability and energy estimate report. This assessment included turbulence intensity, maximum wind gust, wind shear and estimates of annual energy output, resulting in the preparation of appropriate documentation.

3 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

C Capability statements

Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

Renewable energy Entura is one of Australia’s most experienced energy and water consultants. As a leading consultancy in the Asia-Pacific region, we help utilities, governments, developers and international companies tackle big problems with clever solutions.

We offer a full range of consulting services Renewable energy services For example, Entura has been at the covering the planning, design, construction, Entura has a long history in the renewable forefront of solar resource monitoring that operation and maintenance of all kinds energy industry through our connection facilitates project identification in Australia of major energy and water projects. with Hydro Tasmania. This unique and has been trusted by governments and There are over 350 dedicated minds relationship enables Entura to gain industry to develop or review best practice at Entura, all ready to work closely first-hand experience, developing projects guidelines for wind farm development. with our clients — wherever they are. from site identification through to operation, Meanwhile, our expert power systems We specialise in: from the perspective of both a consultant modelling provided to developers, network and an owner. providers, or regulators has informed the • renewable energy For example, Entura was a key contributor to industry and provided a sound basis for grid • power engineering the development of Hydro Tasmania’s wind connection of renewable energy projects in • hydropower assets from as early as 1998 when its first Australia. • water management wind farm was established on King Island. This expertise and experience has been applied around the world, for different • water infrastructure We use this development and operation experience to create practical solutions for purposes in a variety of environments. • environmental management and our clients, to meet technical, sustainability, Entura’s clients span the spectrum from planning. commercial and/or economic development government, financiers and aid agencies to Because we are part of Hydro Tasmania, goals. technology providers, generators, utilities, Australia’s largest renewable energy Our approach is based on identifying, and mining and manufacturing companies. supplier and water resource manager, our understanding and mitigating the risks at Our experience includes projects in Australia, expertise is backed up by almost 100 years each phase of the project cycle, while Pacific, India, south-east Asia, South Africa of experience in developing and operating maintaining a focus on the long-term and other international locations. power and water infrastructure. performance of the assets. Hydro Tasmania continues its history with a Entura’s early involvement across a range of vision to be Australia’s leading clean energy renewable technologies has made an business. Entura supports the delivery of important contribution to the industry this vision with expert services to identify, through the development of various tools, develop, operate and maintain renewable techniques and guidelines that facilitate energy assets. decision-making about renewable energy Entura shares this experience and projects. Our experience, therefore, has knowledge with clients to manage the been directly and indirectly informing the technical and commercial risks of their own industry to enable project advancement. projects. Our services

We support clients across a range of geographic regions. Our strength comes from an ability to deploy the best combination of expertise to meet the needs of clients and projects in any location.

PROJECTS/WHERE WE WORK OFFICE LOCATIONS

Client needs Policy Prospecting Development Finance Construction Operation Entura Guidelines Resource Feasibility studies Business case Ground surveys Performance services development investigation preparation assessment

Sustainability Site Project design Due diligence Technology Asset evaluation strategies identification and layout assessment, selection and procurement

Resource Environmental Energy estimate Detailed design Warranty monitoring and planning reports and tender compliance approvals specification preparation

Pre-feasibility Community Geotechnical studies consultation investigation

Grid connection Grid connection Environmental enquiry studies compliance

Owner’s engineer

In addition to providing the above services, our technical, scientific and consulting specialists are well placed to perform independent peer reviews of other services providers to support the risk management needs of your business. Our team specialises in a number of renewable energy technologies.

Wind Mini-hydro Geothermal As a key contributor to the development of Mini-hydro projects have the potential to We have in-house and partnership Hydro Tasmania’s wind assets for nearly two deliver more immediate outcomes for experience in the area of geothermal decades, we are one of the most utilities, governments, or developers to meet energy and have the capability to support experienced wind energy consultants diesel replacement, electrification, projects at various stages of development. in Australia. sustainability and/or grid stability goals. Our strategic alliance with leading Using this strong experience across all Entura has extensive experience in geothermal consultancies provides stages of project development, we have mini-hydro planning, design and clients with an end-to-end service worked on more than 60 wind farm projects construction. We can provide the best across Australia and Asia. in Australia and overseas, including China, technical and engineering design to We provide a single point of relationship India, South Africa and New Zealand. optimise production and minimise potential contact for clients to make it easy when Entura has the expertise to meet any impacts on supply reliability. dealing with multiple service providers. client’s needs, whether it be developing We are renowned for our innovative Our capabilities include feasibility studies, a green field project to business case or and economic engineering, providing shallow drilling, deep drilling, fracture and undertaking due diligence of a proposed or the right balance between efficiency, reservoir modelling, injection and operating wind farm. cost effectiveness and constructability. production, and generation. Our involvement spans all technical streams This ensures our designs are robust, including resource monitoring, technology economic and appropriate. Renewable energy options studies selection, environmental and planning Combining Entura’s knowledge of Tidal/Wave approvals and grid connection. numerous renewable energy technologies, From resource investigation and planning Solar integration and energy storage, we have approval to connection agreement, proven capability in assessing energy As a leading consultant in the area of Entura can work with technology providers options and helping our clients lower their solar energy, Entura can accelerate the and developers to identify and develop a carbon footprint by integrating renewable development of solar projects or bids. commercially focused project. We energy into their power supply. We provide evaluation of market understand the advantages of alternative opportunities based on our experience technology solutions to particular projects, Low emission hybrid generation systems and we are well placed to undertake in the sector. We have practical experience Entura has extensive experience with independent peer review to support risk from ground monitoring stations to detailed remote area and off-grid power supply mitigation and governance. design of hybrid projects in remote areas. systems, and distributed generation, Our knowledge of the world’s leading solar Our experience managing regulatory, utilising renewable energy. Entura has had a technology manufacturers enables us to environmental and community challenges, long involvement with the iconic King Island review and recommend the best options ensures projects are both commercially power system, which has been a test-bed for each project. and environmentally successful. for achieving high levels of renewable energy penetration. Case studies

Solar Ground mounted solar PV array design and Wind Melbourne urban solar atlas tender assessment support Musselroe wind farm (168 MW) Victoria, 2010-12 Queensland, 2010–11 Tasmania, 2000-current Client: Dept. of Sustainability Client: Confidential Client: Hydro Tasmania and Environment (Vic) Feasibility study for the installation of Entura was integral to the development The first stage of an urban solar atlas a solar PV ground-mounted array system through undertaking grid connection for metropolitan Melbourne to assess for a mining operation and nearby township. studies, preparing EIA and development the technical, practical and financial Entura assisted with tender preparation approvals, developing preliminary and feasibility of solar energy. and provided technical support to review detailed designs, identifying the transmission tender submissions. line route and wind turbine pre-selection The atlas was designed to provide web assessments (including wind turbine access for an individual home user to assess Solar PV array grid connection study factory inspections). Entura continues to the potential energy output of installing New South Wales, 2010 provide technical support during construction. solar panels on their residence. Client: Confidential Grid connection study involving power R2 compliance Queensland and Victoria solar atlases system modelling and analysis to assess South Australia, 2009-12 Queensland and Victoria, 2009-11 the grid connection requirements and Client: Infigen Energy Client: Dept. of Sustainability and regulations compliance at 132 kV for R2 model and data validation for the Environment (Vic) and a multi-sited 150 MWp PV solar farm. Office of Clean Energy (Qld) Lake Bonney wind farm to demonstrate Services included working with electrical the wind farm complied with AEMO The solar atlases outline the available solar design integrators, inverter and PV panel grid connection requirements. energy resource, based on ground station suppliers, and discussions with the utility measurements, correlated with satellite operator and the network regulator for the Woolnorth wind farm (65 MW) and and climate data, and mapped together grid connection application and agreement. Studland Bay wind farm (75 MW) with critical infrastructure and other Tasmania, 1999-current topographical datasets. Solar-diesel design review Client: Hydro Tasmania Northern Territory, 2010 A major component of the project involved Client: Confidential Entura was integral to the full development Entura installing and operating four solar of these two wind farms through Technical due diligence assessment ground monitoring stations in Queensland involvement in site identification, landowner of the proposed design for three solar and Victoria. negotiations, wind monitoring, feasibility power stations to be integrated into diesel studies, environmental studies, power stations in the Northern Territory, development approvals, wind turbine tender including review of the solar resource, evaluation, balance of plant detailed design, energy estimates, power system integration, transmission line design, construction structural design and contractual matters. supervision and commissioning activities. Case studies

Technical due diligence services Kalpitiya wind farm owners Mini-hydro India, 2006-current engineer/lenders engineer Melbourne Water mini-hydro program Client: CLP India Sri Lanka, 2010-11 Victoria, 2006-11 Entura has been CLP India’s primary Client: National Development Bank Client: Melbourne Water and LTL Holdings technical consultant for site inspections, Feasibility studies of fourteen potential wind resource assessments, energy Whole project review of the wind mini-hydro projects on Melbourne predictions, reviews of wind turbine farm design, permits and licences, Water’s water supply system. This led technology, including inspection wind turbine supply contracts and to the completion of detailed design, of wind turbine manufacturing facilities specifications, business case models, construction and commissioning, of seven (Enercon India, Vestas and Suzlon), and construction schedules. sites ranging from 0.4 MW to 5.0 MW wind turbine site suitability, and advising on China Datang Corporation (with mainly variable Francis turbines contractual terms for the following projects: or variable Kaplan turbines). Khandke; Samana; Saundatti; Andhra Lake; clean development mechanism Theni; Harpanahalli; Sipla; Tejuva and compliance review Tolukuma Gold Mine mini-hydro Bhakrani. The combined mega watts of China, 2009-10 Stage 2 (1.8 MW) wind farms assessed is in excess of Client: ADB (Asian Development Bank) Papua New Guinea, 2010 1,200 MW. Technical review of 9 x 50 MW wind Client: Tolukuma Gold Mine farms being developed by China Datang Operational wind farm assessment Pre-feasibility study of a second stage Corporation located in Inner Mongolia, development, and to investigate penstock South-east Asia, 2010 -11 Hebei, Chongqin Municipality and Client: Confidential losses at the existing 1.8 MW mini-hydro Shandong, including site inspections station. Feasibility studies were then Technical due diligence, reviewing and of construction, inspection of wind undertaken to extend the existing 1.8 MW forecasting production, assessing the turbine manufacturing facilities scheme, to include an upstream scheme condition of the wind turbines, reviewing and review of feasibility studies. and for additional machines. operation and maintenance cost forecasts, and providing advice on potential Jounama small hydro (16 MW), expansion of the wind farm. New South Wales, 2006 Client: Limited Preliminary and detailed design of a 16 MW small hydro scheme in conjunction with Alstom Power (as part of a wider project portfolio), including concept design, optimisation, design management, preliminary and detailed design and drawings, and specifications. Tidal/Wave Koolan Island tidal turbine Renewable energy option studies Port Fairy ocean wave energy installation Western Australia, 2009-10 Renewable energy options investigations Victoria, 2011-current Client: Atlantis Resources Corporation Northern Territory, Queensland and Client: BioPower Systems Preparation of an environmental impact Western Australia, 2007-11 Preparation of an environmental impact assessment and EPBC (Environment Clients: Mining companies (confidential) assessment and development application, Protection and Biodiversity Conservation Assessment of wind, solar, geothermal, including sourcing of consent to develop Act 1999) referral for a pilot biomass and biofuels, hydro, wave and tidal coastal crown land from the Victorian tidal turbine project located in northern power options to replace or reduce diesel Department of Sustainability and Western Australia. The environmental based generation for mining operations Environment, for the development assessment included consideration of the and/or nearby townships. This included of an ocean wave energy converter potential impacts of the tidal turbine on resource assessment, design of resource near Port Fairy in Victoria. a broad range of tropical marine species monitoring programs, preliminary expected to occur at the location. cost benefit analyses and determining King Island and Flinders Island wave Benthic surveys were undertaken preferred options. and tidal test facility at the location and a collision risk model Tasmania, 2009-10 developed. 3D current profiling was Renewable energy options investigation, Client: BioPower Systems also undertaken at several locations. Victoria, 2008-11 Clients: Victorian water utilities and councils, Preparation and submission of Sihwa tidal project environmental effects reports for the including: Barwon Water, Grampians South Korea, 2004-5 Wimmera Mallee Water, South-East Water, pilot systems of wave and tidal energy Client: Daewoo E&C generation systems off the coasts of Yarra Valley Water and Frankston City Council King Island and Flinders Island respectively. Owners engineer for the detailed design Assessment of renewable energy power The works covered all marine and terrestrial and construction of the 254 MW tidal supply options, to reduce greenhouse works required to install the prototype power station that was completed emissions and exposure under a carbon tax. systems, and to connect them into the local in August 2010 and in full operation The assessments included projection of electrical grids. The work also included mode from August 2011. future electricity usage, identification of applications to the Tasmanian Government technical development and market for seabed leases at the two sites. opportunities, preliminary costing of opportunities, analysis of the policy environment, and identification of funding mechanisms. Contacts

Hobart 89 Cambridge Park Drive Cambridge 7170 Tasmania, Australia Telephone +61 3 6245 4500 Melbourne Level 25, 500 Collins Street Melbourne 3000 Victoria, Australia Telephone +61 3 8628 9700 Brisbane Level 1, 52 Merivale Street South Brisbane 4101 Queensland, Australia Telephone +61 7 3214 6607 Adelaide 322 Glen Osmond Road Myrtle Bank 5064 South Australia, Australia Telephone +61 8 8338 0085 Sydney 2/11-13 O'Keefe Lane Kogarah 2217 New South Wales, Australia Telephone +61 2 8594 5168

New Delhi D–2 Second floor, Mira Corporate Suites Old Ishwar Naga, Mathura Road New Delhi 110 065, India Telephone +91 11 4320 3203

www.entura.com.au [email protected] Power engineering Entura is one of Australia’s most experienced energy and water consultants. As a leading consultancy in the Asia-Pacific region, we help utilities, governments, developers and international companies tackle big problems with clever solutions.

We offer a full range of consulting services Power engineering covering the planning, design, construction, Entura has one of the largest and most operation and maintenance of all kinds experienced power engineering teams of major energy and water projects. in Australia, with over 100 electrical There are over 350 dedicated minds engineers and technicians. at Entura, all ready to work closely Our experts handle every aspect of electrical with our clients –– wherever they are. power engineering, from the planning stage Areas we specialise in right through to commissioning. • Renewable energy We have a long history in developing • Power engineering Hydro Tasmania’s electrical system, as well as daily involvement in operations • Hydro power in the National Electricity Market (NEM). • Water management This gives us hands-on knowledge and • Water infrastructure understanding of full system requirements. • Environmental management Our consultants take a ‘whole of life’ and planning approach to projects, and will work hard to And because we’re part of Hydro Tasmania, deliver the best technical and commercial Australia’s largest renewable energy solution for you –– whether it’s building supplier and water resource manager, new infrastructure or modifying our expertise is backed up by almost existing networks. 100 years of experience in developing and We provide services in the areas of operating power and water infrastructure. • Primary electrical design • Secondary electrical design • Transmission line design • Automation • Rotating electrical machines • Power systems • Field services Our services

We support clients across a range of geographic regions. Our strength comes from an ability to deploy the best combination of expertise to meet the needs of clients and projects in any location.

Projects/where we work Office locations

We offer full project management and engineering services for greenfield and brownfield projects, from generators through to the local electrical substation.

System Construction & Client need Strategy Design Operation management commissioning

Entura services Business case Power system Asset design, Client engineer Operational asset development studies documentation management and WOLC & procurement

Investigation and TNSP connection Primary electrical, Factory acceptance Condition pre feasibility agreements secondary electrical, testing assessment and for return on transmission lines, performance investment generators, earthing monitoring & automation

Concept designs R1 data & modelling Inspection and Site acceptance Operator and R2 testing test plans testing maintenance (AEMO compliance) training

Project Developing Construction staging Fault diagnostics management technical standards, and design cutover policies and documentation procedures

Compliance auditing Constructability Energy efficiency support

Earthing tests

In addition to providing the above services, our technical, scientific and consulting specialists are well placed to perform independent peer reviews of other service providers to support the risk management needs of your business. Our experts handle every aspect of electrical power engineering, from the planning stage right through to commissioning.

Primary electrical design Secondary electrical design Transmission line design Our experienced consultants provide Entura’s expertise in secondary electrical We offer comprehensive transmission services in all areas of substation design, design is the result of our experience in and distribution line design services, with refurbishment experience up to 500kV. the design and construction of more than with experience in new lines and 26 power plants and numerous substations, brownfield line upgrade up to 500kV. Our capability spans over a number ranging from small to large capacity with of applications, including Our transmission and distribution varying complexity and voltage. • Specification preparation –– line design capabilities include comprehensive specifications Our services cover the secondary system • Transmission and distribution line for equipment and turnkey for the entire power production and route selection and surveying substation projects transmission delivery process, encompassing all aspects of protection, metering, control • Above ground and underground • Construction phase consultancy and SCADA in new and existing sites. transmission line designs and/or project management • Detailed structural analysis and design Our industry reputation for brownfield design • Client’s engineer consultancy services, of poles and lattice towers, conductor is second to none. Our extensive skills enable including review and/or verification sag and tension determination us to deliver packages to clients even under of third-party designs substantial logistical and outage restrictions. • Specification preparation –– • Remote area power solutions/integrations comprehensive specifications (diesel/battery/wind/hydro/hydrogen) Our secondary electrical design for equipment and turnkey capabilities include • Detailed design drafting, using AutoCAD transmission line projects and Microstation, including 3D modelling • Conceptual design and development of • Construction phase consultancy metering and protection one line diagrams • Greenfield substations, substations and/or project management refurbishment and extensions • Detailed protection scheme design • Client’s engineer consultancy services, up to 500kV and documentation including review and/or verification • AC and DC supply systems • Functional protection and of third-party designs control specifications • Wind farm electrical system development • Secondary equipment specification • Analysis of existing earthing systems, and procurement earthing design and earthing • Design of new or retrofit SCADA installations fault investigations • Protection coordination and relay setting calculations • Instrumentation and revenue metering systems • Analysis of protection system operations and performances • System modelling for protection setting determinations

Our consultants have an in-depth knowledge of Australia’s National Electricity Rules (NER) as well as market and network connection issues.

Automation • Control systems for gates, valves and dam Rotating electrical machines Entura has extensive engineering capability outlet works for power stations, as well as We combine design and analytical in the design and commissioning of PLC, capacitor banks voltage control schemes, expertise to provide a state-of-the-art RTU and automation networks for power transmission line auto reclose schemes service, covering virtually all aspects generation, transmission, distribution and and automatic restoration schemes of generator control, construction, water supply utilities, as well as general for substations maintenance and operation. industrial applications. We also have a wide • Systems such as generator runback We have extensive experience with range of experience in engineering the AC schemes and network special protection hydro generators, as well as considerable and DC systems to support these solutions. schemes to provide maximum generation expertise with windfarm developments output on existing transmission and Our control capabilities include and compliance/performance testing distribution assets • Review of existing plant, including of thermal generating plant, particularly • Hydro machine control systems suitable preparation of reports and estimates gas and combined cycle/cogeneration. for manual, automatic and remote control Our specific focus is on primary generating • Design and drafting of control systems • Hydro machine protection systems equipment including generators, and auxiliary power systems in incorporating temperature, excitation systems, power system stabilisers, accordance with client specifications vibration and process variables governors and synchronisers. • PLC programming over the complete • Dewatering and fire protection systems Our consultants have an in-depth knowledge Allen-Bradley range from MicroLogic of Australia’s National Electricity Rules and SLC through to ContorlLogix • Integration of governor and excitation and synchronising systems (NER) as well as market and network • Configuration and programming of connection issues, such as ancillary • Remote control and remote access Intelligent Electronic Devices (IED’s) service capabilities and generator systems for remote plant operation, and Remote Terminal Units (RTU’s), performance standards. for example Foxboro, GE Harris, condition monitoring and post fault Serck, Logica etc analysis all of which allow faster Our capabilities include established plant restoration conceptual design, detailed design, • Operator interference programming installation supervision and commissioning and commissioning using SCADA • Site supervision and commissioning experience of hydropower plant covering software such as RSView and Citect • Complex documentation for projects and Invensys I/A SCADA including commissioning reports and • Excitation systems/governor systems/ synchronisers • Design of field networks for both serial operation and maintenance manuals and Ethernet devices, including DeviceNet • Preparation of technical specifications and IEC-61850 networks for the purchase of new and replacement generators based on internationally • Experience with a wide range of SCADA recognised standards protocols including DNP3, Conitel, IEC-61870-103 and IEC-61850 GSSE • Management of technical portions (for substation interlocking of supply contracts including design and CB fail systems) reviews, inspections and factory and site acceptance testing We improve products and project outcomes through our tight working relationships with clients and manufacturers.

• Generator testing for performance Our comprehensive service offering includes Field services and code compliance assessment, • Power system performance assessment With over 50 years of protection scheme, as well as model development • Connection studies for transmission, metering and SCADA experience, our field • Tuning of AVR, governor and PSS loads and generators services provide clients with the ability control systems via model simulation to identify and act to correct any potential • Investigation and resolution of electricity and analysis to optimise response problems, while minimising valuable market issues • Generator condition assessments downtime for their assets. • Rural electrification • Reliability centred maintenance Our engineers and technicians are experts • Dynamic model development (RCM) and associated software in installing, commissioning and testing • Preparation and validation of • Asset management plans activities for secondary systems of power generating unit data and models distribution networks. • Power station automation and remote • Transmission network augmentation studies control requirements We provide routine electrical test services • Transmission and distribution planning in the following areas Power systems We use a range of modern tools including • Power system metering Our consultants provide both theoretical Matlab and Simulink, PSSe, PSCAD, EMTP, • Protection and control knowledge and practical experience in @Risk, TPRICE, MUDPACK and PowerFactory • Teleprotection assessing power systems performance to provide detailed and insightful analysis and connection issues. of power system issues. • HV electrical plant We are experts in using innovative control • Earthing systems solutions to overcome plant or network Our testing service is NATA-accredited deficiencies to meet regulatory requirements. for polyphase induction metering, voltage These solutions provide cost savings and and current transformer calibration. performance benefits to our clients. We improve products and project outcomes through our tight working relationships with clients and manufacturers, as well as our understanding of the inherent technologies and their application to the power system. We have strong relationships with AEMO and the Transmission and Distribution Network Service Providers and have assisted many clients in their negotiations with these bodies when they are connecting or altering their connections. Contacts

Hobart 89 Cambridge Park Drive Cambridge 7170 Tasmania, Australia Telephone +61 3 6245 4500 Brisbane Level 1, 52 Merivale Street South Brisbane 4101 Queensland, Australia Telephone +61 7 3214 6607 Melbourne Level 25, 500 Collins Street Melbourne 3000 Victoria, Australia Telephone +61 3 8628 9700 Adelaide 322 Glen Osmond Road Myrtle Bank 5064 South Australia, Australia Telephone +61 8 8338 0085 Sydney Level 9, 190 George Street Sydney 2000 New South Wales, Australia Telephone +61 2 9251 7693 New Delhi D–2 Second floor, Mira Corporate Suites Old Ishwar Nagar, Mathura Road New Delhi 110 065, India Telephone +91 11 4320 3203

www.entura.com.au [email protected] Project overview OctoberKING 2012 ISLAND RENEWABLE ENERGY INTEGRATION PROJECT (KIREIP) Welcome to King Island

Hydro Tasmania is pleased to showcase the world- leading renewable energy projects that have been undertaken on King Island over the past 15 years and our plans for further development. King Island is one of several inhabited islands located in Bass Strait, the body of water separating the north coast of Tasmania and the south coast of Victoria on mainland Australia.

King Island is famous for its premium products such as beef and dairy, as well as kelp farming and tourism. The residents of King Island form a tightly-knit and self-reliant community – finding ways to overcome the challenges of living on a remote island.

Generation of electricity on this remote island is the same – it must be self-reliant.

Hydro Tasmania is responsible for the generation, distribution and retail of electricity on King Island. Like thousands of other islands across the globe, King Island has historically relied purely on diesel generators for electricity supply, a reliable but costly and emissions-intensive source of power.

Since 1985 Hydro Tasmania has been improving the power system on King Island and aspiring to reduce the dependence on imported diesel fuel through deploying a range of innovative technologies. Read on to find out about what we have achieved to date and our world-leading plans for the future.

King Island King Island Power Station Historically power on King Island was regionally focused on the main towns on the island. Privately-owned power stations existed in the two major towns.

In 1986 that all changed when the King Island Power Station was officially opened and a The old Currie Power Station power system for the whole of King Island was established with a distribution network spanning most of the island.

The original King Island Power Station

By taking on the responsibility for the power system, Hydro Tasmania could increase the reliability of power supply and provide power to both commercial and residential customers.

The station was originally fitted with 2 x 1200 kW Diesel machines and 1 x 800 kW machine giving a firm capacity of 2000 kW. Space to accommodate a fourth unit was included in the original construction – a good piece of forward thinking.

As load has grown over time a fourth 1200 kW machine was added to this space, RENEWABLE ENERGY and all three 1200 kW units have since been upgraded to 1600 kW machines. The new diesel units are more efficient and themselves contribute to reducing diesel consumption. Diesel In 2012 the station’s installed diesel capacity was 6000 kW with a firm capacity of 4400 kW.

The King Island Power Station has been designed for automatic operation and is only staffed during business hours. Essential maintenance and daytime 0% supervised operation of the station is carried out by our skilled operators. 1

Nordex wind turbine nose cone and blades being moved into place

Hydro Tasmania is a pioneer of renewable energy.We’ve had nearly 100 years experience in generating power from clean, renewable sources.

Our next natural step on King Island was to ensure that renewable energy was part of the mix.

King Island has the advantage of being located in the path of a world-class wind resource - the roaring forties.

In 1998 Hydro Tasmania commissioned three Nordex N29 wind turbine generators at Huxley Hill near the King Island Power Station and in doing so established Australia’s second commercial wind farm.

The three turbines are rated at 250 kW each, providing a total renewable energy capacity of 750 kW.

RENEWABLE ENERGY

Diesel Wind

15% The tower base and nacelle 2 This new renewable source of energy showed dividends right away, by reducing diesel use. This in turn reduced carbon emissions and the cost of supplying the island with electricity.

When the Nordex machines were the sole renewable generation on the island they contributed on average around 15 per cent of the island’s energy needs. This resulted in a 15 per cent reduction in annual diesel fuel use or approximately 590 000 litre reduction in diesel use per annum.

The Huxley Hill Wind Farm was a huge success, paving the way for more renewable energy development on the island. It was also the first wind farm in Australia to earn Renewable Energy Certificates, one of many ‘firsts’ for King Island.

Nose cone and blades ready for assembly The completed Nordex wind turbine

Nose cone and blades being lifted into place The nose cone and blades being fitted to the nacelle 3 King Island Renewable Energy Expansion (KIREX) project

The larger Vestas wind turbine

The next step in King Island’s renewable energy journey started in the year 2000 and was officially opened in 2004.

The goal of KIREX was to increase the contribution of renewable energy in the system, through expanding the Huxley Hill Wind Farm, and implementing a new control system and an emerging battery technology to store energy.

Two larger wind turbines were constructed to expand the wind farm. For those who are technically minded, the turbines were Vestas V52s which are capable of producing a maximum of 850 kW of power each, increasing the total rated capacity of the wind farm to 2.45 MW.

RENEWABLE ENERGY

Diesel Wind

Liquid Control Battery Upgrade 30% Tower component being transported to site 4 The extended Huxley Hill Wind Farm

These newer turbines also allow our operators to vary the power output for the same quantity of wind, making them a bit easier to add to the power system.

The KIREX project looked at two other important technologies which help to maximise renewable generation.

The first was a liquid-based battery, specifically a Vanadium Redox Battery (VRB). The purpose of the VRB was to capture excess wind generation when available and to use this to smooth the variable output of the wind farm to make this more manageable in the system. Vanadium Redox Battery (VRB) tanks This battery system showed some early promise, but being an emerging technology it was subject to plant outages and was unfortunately not able to deliver on a sustained basis, prior to an eventual plant failure. As with other R&D activities, Hydro Tasmania has learned from this demonstration project and incorporated those learnings in our current battery projects. The VRB has since been decommissioned and with the rapid advance of battery technology in recent years this is planned to be replaced by a more proven technology in 2013.

The final element of KIREX was a substantial upgrade to the existing power station controls. This new system allowed the operators to optimise the operation of the power system as a whole, balancing renewable generation, energy storage and diesel generation with load while keeping the system reliable for our customers.

Vestas tower sections being erected 5 Resistive Frequency Control and Photovoltaic Solar Installation

Photovoltaic Solar panel

In 2008 two further technologies were added to the King Island power system. Solar generation was added by a third party and Hydro Tasmania developed a new and promising technology which enables the system to use more of the available renewable energy generation.

The solar installation on King Island is owned by KI Solar Pty Ltd (a subsidiary of CBD Energy Ltd) and adds approximately 100kW of renewable energy to the King Island Power Station. The six solar photovoltaic arrays can rotate on a dual axis to track the path of the sun.

Because no single renewable energy source is perfectly placed to generate all of the time, having two or more sources is important for a remote system like King Island.

The Resistive Frequency Control system is a technology which, simply put, allows our wind turbines to operate unhindered, providing as much energy as the wind will allow, and converts this to more useful energy reserves to offset diesel generation.

RENEWABLE ENERGY

Diesel Wind Control Computer

Resistor Solar 35% Some local livestock 6 The transformer element of the Resistive Frequency Control unit The resistive heating elements of the Resistive Frequency Control unit

Before the resistor was installed, the wind turbines were It can thus take over the role of keeping the supply/demand required to be constrained so that they did not disrupt the balance. By taking that role away from the diesel engines delicate balance of power supply to customer demand, more of the wind energy can be used, offsetting diesel resulting in blackouts. The balancing of demand and supply generation. was provided by the diesel engines. Although the solar installation is an important demonstration With the resistor operating, any excess energy generated by of integrating different renewable energy sources, the wind the wind turbines is absorbed and because the resistor can turbines generate the vast bulk of the renewable energy and be adjusted rapidly, it can either absorb this excess energy or working with the resistor technology has contributed the allow more of the wind energy to serve customers. majority of diesel savings.

Dierence in Diesel Generation (18/05/08) 3,000

2,500

2,000

1,500 Power (kW)

1,000

500

0 6:30 7:00 7:30 8:00 8:30 9:00 9:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 Time

Wind Spill Wind to Load Diesel Savings Current Diesel Generation Previous Diesel Generation Customer Load

7 Achievements

Since the whole of King Island was brought together in an close to $2 million. We’ve saved over 38,000 tonnes of integrated power system, Hydro Tasmania has been striving CO2e, that’s like removing almost 7,500 cars off the road to improve reliability and reduce reliance on diesel fuel. permanently. The below two graphs show just how the projects we have Hydro Tasmania is proving that renewable energy can play completed to date have impacted on the power system in a key role in reducing exposure to oil price volatility and the terms of reduction of diesel use and carbon emissions. cost and emissions associated with remote power supply. Annual diesel savings peaked at 1.5 mega-litres representing an annual saving in operational costs of

8 The ultimate goal of this project is that when conditions allow, when it is very windy, the island will be powered by What is 100 per cent renewable energy. In a remote area power system of this scale that is quite an achievement.

To achieve this, the project brings together a portfolio of next for new and existing technologies to increase renewable energy use on King Island. An innovative aspect of this system is the integration of these technologies. King Island? Although the renewable generation sources are mature, it is the integration of these sources with the emerging The King Island Renewable enabling technologies, such as storage, that is world leading. Energy Integration Project Solutions developed under KIREIP have enormous potential to increase the use of renewable energy and reduce reliance (KIREIP) on diesel fuel for power generation on islands and in off-grid KIREIP is a world-leading project that has one main goal systems across the globe. – to further reduce dependence on diesel generation by KIREIP is an initiative of Hydro Tasmania and is being increasing the use of renewable energy generation. developed with the assistance of the Australian When the project is completed renewable energy sources Government’s Renewable Energy Demonstration Program will provide more than 65 per cent of the annual energy and the Tasmanian Government. demand, with the remainder provided by biofuels.

Thermal Generation Renewable Generation Enabling Technologies 2011-12 Diesel 2008 Uninterruptable Power 96 kW Supply to allow periods of Solar PV Existing 2012 100% RE to meet load Diesel Biodiesel Diesel UPS Solar Photovoltaic Array Engines Trial 6 MW Total 2008 Diesel Generators Resistive Frequency Control Resistor Bank 1998 2003 2013 Wind Farm 3 Wind 2 Wind 2012-13 Update Expansion Turbines Turbines Energy Storage up to 4 MW Station Station 750 kW 1700 kW Technology Controller Operator Wind Farm Interface Station Control

2012-13 Smart Grid New Developments Smart Grid - Demand Side Management

9 Stage 1 King Island Renewable Energy Integration Project (KIREIP) Diesel uninterruptible power supply (D-UPS) Two diesel-uninterruptible power supply (D-UPS)units have now been installed at the King Island Advanced Hybrid Power Station. Each D-UPS unit contains a large mass flywheel, which uses excess wind energy rather than diesel power to maintain its motion. Its diesel engine operates only rarely when the unit is required to provide power for an extended period, otherwise the mass of the flywheel carries sufficient energy to provide the power response.

Although D-UPS is a well-proven commercial technology, common in airports and data centres, the application of these units in a remote power system of this size is a world first.

In the King Island system the D-UPS allows all primary diesel generation units to be switched off when there is a period where renewable energy generation is greater than the customer demand, resulting in what is called 100 per cent renewable energy penetration.

Without the D-UPS, switching diesel units completely off would present a problem. If the wind generation were to reduce rapidly the primary diesel generators would not be able to be switched back on fast enough – resulting in a gap in power generation and a blackout.

This is where the D-UPS comes in.

The D-UPS provides an immediate short-term backup for the primary diesel generators – it makes sure that there is not a gap in generation when the customer demand rapidly exceeds renewable generation.

The flywheel of the D-UPS contains significant inertia and if renewable generation drops, the inertia of the flywheel can quickly start the attached secondary diesel generator. The D-UPS unit can cover the gap for enough time to allow a larger primary diesel engine to be started.

RENEWABLE ENERGY

Diesel Wind Solar

Control Resistor Diesel UPS Upgrade >45% 10 The D-UPS provides the system operator with the confidence to switch off the primary diesels knowing that they have the short-term backup required under all circumstances.

The completion of the D-UPS is a huge step in the King Island renewable energy journey allowing the island to have periods where it is powered by 100 per cent renewable energy.

Upgraded high voltage switch gear New high voltage (HV) switch gear was also installed and commissioned as part of the first stage of KIREIP. While the HV gear is a supporting element to other major project elements, such as the D-UPS, it is vital to the success of the project. One of the diesel-uninterruptible power supply units The new HV switch gear provides the connection points for the new equipment and will increase electricity supply reliability and allow our team to test new equipment while maintaining power supply to customers.

Power station building extension On the more practical side of things, this first stage of the project also required additional space for new technologies. An extension to the existing station was completed before any of the new technology arrived. Space for the D-UPS, HV switch gear and a new space to permanently house the resistor as well as offices for the operational staff and a meeting room to showcase the project were included in the station extension. The upgraded high voltage switch gear

The extended King Island Advanced Hybrid Power Station Showcase centre – explaining how the technologies are integrated 11 Stage 2 King Island Renewable Energy Integration Project (KIREIP) Wind farm expansion An increase in the wind farm capacity is planned for King Island. The increase in renewable wind generation will allow for a greater percentage of time running the system at 100 per cent renewable penetration.

The wind farm expansion is made possible because the enabling nature of the D-UPS and the fact that with the diesels able to be switched off significantly more customer load can be met by wind energy.

The wind farm expansion is an important element in demonstrating the high level of contribution renewable energy can play in modern remote power systems utilising innovative enabling and storage technologies. Smart Grid The Smart Grid component of KIREIP looks beyond the generation component of power supply to the demand or customer side.

The Smart Grid is the next phase in the evolution of the electrical power generation, transmission and distribution system. In the King Island context the Smart Grid aims to match customer demand to the available supply as much as possible through the use of communication technologies and a ‘smart’ control system.

The Smart Grid project will focus on the dynamic and rapid direct control of customer loads in order to maintain the system demand/supply balance under increased levels of renewable energy supply, providing a more efficient and reliable power system.

RENEWABLE ENERGY

Diesel Wind Battery Control Upgrade

Resistor Solar Diesel Bio Smart UPS Diesel Grid >65% 12 Smart Grid

means that it isn’t as simple as just switching fuels. The best Hot Water Commercial DSM approach is to test the performance of biodiesel in controlled conditions prior to any potential implementation.

A trial is being undertaken at the King Island Advanced Hybrid Power Station in order to prove the biodiesel in one of the existing engines. This gives us the opportunity to test Data Reporting PV control EV Charging fuel supply logistics, suitability of existing fuel infrastructure and trial the reliability of biodiesel suppliers.

Upon successful completion of the trial, the station diesel The demand response consists of selected customer supply infrastructure such as tanks and fuel lines may be loads, activated by Hydro Tasmania with the customer’s modified to allow the use of biodiesel. permission.

The demand response is to be provided through a system Energy storage system of smart switches installed on selected customer loads, Many renewable energy sources, including solar and wind, activated via a wireless communications network, through produce intermittent power. That is because the source of a centrally located automatic control system operated by power (wind or sunlight) is not continuous. Hydro Tasmania. When intermittent power sources reach high levels of grid It is hoped that by combining a large number of individual penetration, energy storage becomes one option to provide loads across the island the effect is magnified significantly. reliable energy supplies – the extra energy is stored for use The nature of the loads selected for control, largely hot water when the wind is not blowing or sun is not shining. heaters, and the short periods that they would be switched It also allows a rapid response to system requirements and off means that there will be no impact on customers. takes that role away from the primary diesel generators, The idea is that they simply won’t know when the system saving even more diesel fuel. is operating. On King Island, Hydro Tasmania will install an The immediate benefits from a Smart Grid project on King electrochemical battery system, capable of 3 MW of power Island will be the ability to switch off primary diesel units at contribution and storing 1.6 MWh of useable energy. a greater frequency and delay diesel engine start up. This will make the battery the largest ever installed Biodiesel in Australia. The size of the battery will increase the amount of time the Hydro Tasmania has been monitoring the development of network can operate on 100 per cent renewable energy. biodiesel for some time; it has the potential to be a substitute When conditions such as high winds allow, the battery on King Island for ‘regular’ diesel – known as mineral diesel. can store excess wind energy for later use. To put this into By implementing biodiesel, greenhouse emissions can be perspective the energy stored in the battery will be sufficient substantially reduced. There are, however, differences in to power the island for approximately 45 minutes. the properties between biodiesel and mineral diesel. This

13 Remote area power supply in Australia and around the world

Seth Langford and Andrew Ling of Entura working on a project for the remote community of Cape Barren Island

There are many thousands of remote communities, as well as commercial projects and mine sites throughout Australia and the world that rely on diesel generation for power in remote area power supply systems. In many instances the high cost of diesel power generation prevents them from receiving a continuous electricity supply, greatly impacting their quality of life and productivity.

The innovative solutions developed under KIREIP have enormous potential to increase the use of renewable energy and reduce reliance on diesel fuel for power generation on islands and in off-grid systems across the globe, reducing the cost of energy services and the exposure to volatile oil prices. Pitcairn Island

As a leader in renewable energy Hydro Tasmania is intent on pursuing how King Island can be used as a blueprint for other power systems across the world.

14 Research and development

Mike Ross of Entura developing Smart Grid equipment with Brook Sneldon of Cambium Networks

Hydro Tasmania has implemented KIREIP as a unique opportunity to develop and deploy innovative world-leading renewable and enabling technology in a sizeable, real-world ‘closed system’.

We believe that the applied R&D conducted in the design and operation of King Island system, with very high levels of renewable energy, will be deployed over time within the larger mainland Australian power system and similar global networks.

Knowledge generated through the completion of the development program will be instrumental in realising solutions to manage high levels of intermittent renewable energy penetration in the National Electricity Market, helping to achieve the mandated 20 per cent renewable energy target by 2020.

Hydro Tasmania has received significant interest in the work being undertaken on King Island, including from leading research groups such as the University of Tasmania, CSIRO, Sandia National Labs and Pacific Northwest National Laboratories. We are seeking ongoing collaborations with research institutions to promote the utilisation of KIREIP Dusan Nikolic of Entura and Patrick Nogara of Hitzinger commissioning one of the diesel-uninterruptible power supply units for applied R&D.

15 Helping the communities in which we operate

Picturesque King Island

Hydro Tasmania ensures that our projects not only achieve Clean energy and water technical excellence, but address environmental and social training centre issues, ensure local staff are trained and communities are engaged. This approach is mirrored by our consulting Entura is so committed to developing skills in the clean business Entura. energy and water markets that, in November 2012, it is planning to expand its training and capability development Having such a close relationship with Hydro Tasmania, many services with the launch of a dedicated clean energy and Entura projects involve more than just the application of water training centre. The centre will be an RTO (registered expert advice – the transfer of knowledge is an important training organisation) accredited with the Australian Skills component of Entura’s work to build the capability of its Quality Authority. clients, suppliers and the communities in which it works. The centre will focus on building skills and capability in Capacity building services clean energy and water markets, both in Australia and Entura provides training and capability development internationally – particularly in the Pacific, Asia, and Africa. services alongside water and energy advice, which have The King Island Advanced Hybrid Power Station will form a been successfully utilised by organisations around the world. key part of this training centre. Some prominent examples are training for Cambodian policy makers and water managers, Bhutan’s Department for Energy and generating utilities in Papua New Guinea and Micronesia.

Entura has also assisted in remote systems, such as developing training to enable the local indigenous community on Cape Barren Island to maintain their remote wind-diesel-solar power supply that was designed and installed by Entura.

16 Entura delivering training to Sarawak Energy Berhad employees

Community development Inherently, projects that enhance energy supply and reliability in remote parts of the world have immediate community benefits – keeping the lights on. However, Hydro Tasmanian and Entura both look to achieve further benefits for the community – such as solutions to health concerns or social issues.

On King Island Hydro Tasmania is supporting local clubs through our Smart Grid program and are sponsoring events that enrich the island’s social value and bring tourists to King Island.

Peter Kempster of Hydro Tasmania speaking to a King Island community group

17 2012 2013

Bio Smart Diesel Wind Solar Resistor Diesel Control Wind Battery UPS Upgrade Diesel Grid

www.hydro.com.au

www.kingislandrenewableenergy.com.au 121187 Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

D Standard terms and conditions

Renewable Energy Integration Study for ASPA power grid ‐ Entura submission Revision No: 0 E303587 18 July 2013

This page is intentionally blank.

Client: Consultant: Name: [Insert name] Hydro-Electric Corporation ABN: [Insert ABN] T/A Entura Address: [Insert address] ABN 48 072 377 158 Please select street Single Use Consultancy Contract Please select suburb

Entura as Consultant

Contract Particulars (to be read in conjunction with the General Conditions of Contract here attached)

PROJECT NUMBER CONTRACT DESCRIPTION

[Insert number] [insert description]

1. The Parties: Client’s representative: [name] Consultant’s representative: [name]

Position: [title] Position: [title]

Phone Number: [phone] Fax Number: [fax] Phone Number: [phone] Fax Number: [fax]

E-mail address: [e-mail] E-mail address: [e-mail]

2. The Services: The "Services" means the whole of the work to be carried out and completed in accordance with the Contract, including variations provided for by the Contract, which is to be completed by the Consultant and includes:

[Insert a description of the Services and, if applicable, refer to and attach the relevant document/specification, list any reports, designs etc to be produced by the Consultant unless listed in the attachment]

3. The Contract Sum: The "Contract Sum" is: The Lump Sum amount of: $[insert amount]

(click the applicable box/boxes and insert either a lump sum and/or The following schedule of rates: state the applicable schedule of rates and delete as appropriate) [Insert role] hours @ $[insert amount] per hour; *All prices stated exclude GST [Insert role] hours @ $[insert amount] per hour;

Expenses shall be reimbursed by the Client at cost plus 10 percent (%).

The attached schedule of rates

The time for claiming payment is: [Insert time period, e.g. fortnightly for work performed, or insert milestones]

[If nothing stated, on the 20th day of each month or the next business day thereafter.]

4. Time: The "Commencement Date" is: [insert date]

The "End Date" is: [insert date]

5. Intellectual Property Rights: "Intellectual Property Right" means any patent, registered design, trademark or name, copyright or other protected right

6. Governing Law: The Laws of the State of Tasmania.

______/ ______

Entura Single Use Consultancy Contract for ASPA Bid.doc Approved version as of Thursday, 18 July 2013 Page 1 of 4

EXECUTED as an Agreement

Executed for the Client by: Executed for Hydro Electric Corporation by:

Please print name and capacity: Please print name and employee number:

In the presence of: In the presence of:

Please print name and capacity: Please print name and employee number:

DATED ...... (completed by final signatory)

______/ ______

Entura Single Use Consultancy Contract for ASPA Bid.doc Approved version as of Thursday, 18 July 2013 Page 2 of 4 SINGLE USE CONSULTANCY CONTRACT- GENERAL CONDITIONS OF CONTRACT

1. THE SERVICES (c) a workers' compensation policy until the End Date for the maximum amount permitted by law, covering the Consultant's liability under 1.1 The Consultant shall perform the Services in accordance with the common law and statute for death or injury to any person Contract. employed by the Consultant. 1.2 The Consultant represents and warrants that: (a) it has informed itself as to the general nature of the Services and 5. PAYMENT the requirements of the Contract; 5.1 The Client shall pay the Consultant the Contract Sum in accordance with (b) it has examined the contents of the Contract and any other this Contract. information provided by the Client (or anybody acting on behalf of 5.2 The Consultant shall submit to the Client claims for payment progressively the Client) to the Consultant prior to the execution of the Contract; in accordance with the Contract Particulars. and 5.3 All monies due and payable by the Client to the Consultant must be paid (c) it shall perform the Services in a proper and workmanlike manner to within 14 days of the receipt by the Client of a properly prepared tax the standard prescribed in the Contract and, to the extent that it is invoice from the Consultant in accordance with clause 6.4. not so prescribed, to a standard consistent with good practice for 5.4 If the Client does not pay the amount of the claim the Client shall, either carrying out services of a nature similar to the Services. with the payment or not later than the time for payment, provide the 2. RESPONSIBILITIES AND OBLIGATIONS OF THE CONSULTANT Consultant with a written statement of the reason for any difference between the amount claimed and the amount paid or to be paid. 2.1 The Consultant shall: 5.5 If any moneys due and payable to either party remain unpaid after the (a) comply with all directions of the Client given pursuant to a provision date upon which or the expiration of the period within which they should of the Contract; have been paid, then interest shall be payable thereon at the then current (b) employ staff with appropriate qualifications and experience to carry benchmark interest rate applicable to Division 7A of Part III of the Income out the Services; Tax Assessment Act 1936 (Cth) from (but excluding) the date upon which (c) as soon as practicable after becoming aware of any matter or or the expiration of the period within which they should have been paid circumstance which may adversely affect or has adversely affected to and including the date upon which the moneys are paid. the scope, timing or carrying out of the Services, give written notice to the Client detailing the matter or circumstance and its 6. GST anticipated effect on the Services; 6.1 Words or expressions used in this clause 6 which are defined in A New Tax (d) comply with all legislative requirements of which it has been System (Goods and Services Tax) Act 1999 (Cth) have the same meaning in notified by the Client in carrying out the Services; this clause. (e) when on the Client's premises, and when using the Client's facilities, 6.2 All amounts stated in and payable under or in connection with this comply with all directions, procedures and policies relating to Contract exclude GST unless otherwise indicated. occupational health, safety and security requirements relating to 6.3 If a payment to a party under this Contract is a reimbursement or the Client's premises and facilities of which it has been notified by indemnification, calculated by reference to a loss, cost or expense the Client; incurred by that party, then the payment will be reduced by the amount (f) take reasonable care of the Client's property provided to the of any input tax credit to which that party is entitled for that loss, cost or Consultant in connection with carrying out the Services; and expense. (g) commence the performance of the Services on the Commencement 6.4 The recipient will not be liable to pay the supplier for a taxable supply Date and provide the Services on the terms of this Contract until the made under or in connection with this Contract until the supplier has End Date. given the recipient a tax invoice for the supply to which the payment 3. RESPONSIBILITIES AND OBLIGATIONS OF THE CLIENT relates. 6.5 Where an adjustment event occurs in relation to a supply made by the 3.1 The Client shall: supplier under or in connection with this Contract, the supplier will issue (a) when and as required under the Contract, provide the Consultant an adjustment note to the party providing consideration in respect of that with relevant documents, samples, patterns, moulds and other supply within 28 days after becoming aware of the relevant adjustment. information in the possession or control of the Client sufficient to enable the Consultant to carry out the Services; 7. VARIATIONS

(b) give or cause to be given to the Consultant in writing timely 7.1 The Client may, by written notice to the Consultant, direct the Consultant directions, instructions, decisions and information sufficient to to vary the Services and, provided that the variation does not change the define the Services required and facilitate the provision of the general scope of the Services, the Consultant shall be bound to comply Services by the Consultant; with that direction ("Variation").

(c) provide the Consultant with such access to premises or sites of the 7.2 The parties must use their best endeavours to agree in writing on the Client as is necessary for the Consultant to carry out the Services; value of a Variation, but in the event that the parties are unable to agree and within 7 days of the issue of the direction, then the value of the Variation

(d) bear the cost of all fees and charges required to comply with shall be determined using reasonable rates and prices. legislative requirements incurred in connection with carrying out 7.3 If a new legislative requirement or a change in a legislative requirement the Services. after the date of the Contract could not reasonably have been anticipated 4. INSURANCE at the date of the Contract, then the extent to which the Services are changed by that legislative requirement shall be deemed to be a Variation 4.1 From the Commencement Date, the Consultant must effect and have in pursuant to clause 7.1. place the following insurances: 7.4 Where, due to circumstances beyond the reasonable control or (a) a professional indemnity insurance policy for the Services with a anticipation of the Consultant, the Consultant is required to alter, add to total aggregate cover of not less than $2,000,000.00 which shall: or delete documents or other things previously submitted and which (i) include provision for loss of documents; and otherwise would have complied with the Contract, the Consultant shall (ii) be maintained until the End Date and thereafter for a period inform the Client and seek directions and any subsequent alteration, of 6 years; addition or deletion shall be deemed to be a Variation pursuant to clause 7.1. (b) a public liability policy until the End Date for an amount in respect of any one claim or series of claims arising from the one original cause of not less than $20,000,000.00; and

______/ ______

Entura Single Use Consultancy Contract for ASPA Bid.doc Approved version as of Thursday, 18 July 2013 Page 3 of 4 SINGLE USE CONSULTANCY CONTRACT- GENERAL CONDITIONS OF CONTRACT

8. DELAYS 12.2 The parties must meet within 14 days of the date of the Notice of Dispute and undertake genuine and good faith negotiations with a view to 8.1 The Consultant shall proceed with the work under the Contract with due resolving the dispute. Unless the parties agree otherwise, the meeting expedition and without delay. must take place in Hobart, Tasmania. 8.2 When it becomes evident to a party that an act or omission of the Client, 12.3 If the parties are unable to resolve the dispute in accordance with clause or an employee, other consultant, contractor or agent of the Client, may 12.2 within 14 days of first meeting under clause 12.2, the dispute may be delay carrying out the Services, that party shall promptly notify the other referred, by written notice of either party, to mediation, which is to be party in writing with details of the possible delay and the cause. conducted in accordance with the Institute of Arbitrators and Mediators 8.3 The Client may direct the Consultant in what order and at what time the Australia Mediation Rules. Services shall be performed and if: 13. (a) the Consultant: INTELLECTUAL PROPERTY

(i) can reasonably comply with the direction the Consultant shall 13.1 Unless the Contract otherwise provides, the Consultant retains all do so; and Intellectual Property Rights in the Services and in any design, materials, (ii) cannot reasonably comply with the direction the Consultant documents and methods of working used or produced in relation to the Services. The Consultant grants to the Client an irrevocable, royalty free, shall so notify the Client in writing, giving reasons; and non-exclusive, transferable, perpetual licence to exercise all rights of the (b) compliance with the direction causes the Consultant to incur more owner of the Intellectual Property Rights associated with the Services, for or less cost than otherwise would have been incurred had the any business purpose of the Client, including additions or alterations or Consultant not been given the direction, the difference shall be entering into any agreement with any third party which is associated with valued pursuant to clause 7.2 as though the direction was a or uses the Services or things produced in the course of performing the Variation. Services.

9. CONFIDENTIALITY 14. NOTICES 9.1 Except as required by law, the Consultant and the Client will keep 14.1 A notice (and other documents) must be in writing, legible, in English and confidential information which is so designated in writing by the party delivered in person, by facsimile, by email or by post. providing the information, or which should reasonably be known by the 14.2 A notice (and other documents) shall be deemed to have been given and recipient party to be confidential. This clause 9 will survive the expiry or received: termination of the Contract. (a) if addressed or delivered to the relevant address listed in the Contract Particulars or last communicated in writing to the person 10. LIABILITY OF THE CONSULTANT giving the notice; and 10.1 The maximum liability of the Consultant arising out of the performance or (b) on the earliest date of: non-performance of the Contract or the Services whether under the law (i) actual receipt if delivered in person; of contract, tort or otherwise, shall be limited to 500% of the Contract (ii) confirmation of correct transmission of fax; Sum. (iii) the notice being recorded as having been first received at the 10.2 To the maximum extent permitted by law and notwithstanding any other electronic mail destination; or provision of the Contract, the Consultant is not liable to the Client, (iv) 3 days after posting. whether under contract, in tort, in equity, in restitution, under statute or otherwise, in respect of any: 15. TERMINATION a. business interruption loss; 15.1 The Contract may be terminated: b. loss of actual or anticipated profit, revenue, production, opportunity or anticipated savings; (a) at any time by mutual agreement; c. loss of use; or (b) for the convenience of the Client, upon the giving of not less than 7 d. exemplary damages. days notice, in which case the Client shall pay the Consultant:

10.3 This clause 10 shall not apply to claims in respect of personal injury or (i) that portion of the Contract Sum payable to the date of death. termination; 11. CONSULTANT'S INDEMNITY (ii) any direct costs incurred by the Consultant to the date of termination; and 11.1 Subject to clause 10, the Consultant shall indemnify the Client against: (iii) an amount equal to 2% of the Contract Sum; (a) loss of or damage to property of the Client; and (b) claims by any person against the Client in respect of personal injury (c) upon a substantial breach of the Contract by either party which is or death or loss of or damage to any other property, not remedied within a reasonable time (and in any case within 7 arising out of or in consequence of carrying out the Services by the days) of notice by the non-breaching party of the substantial Consultant. breach; or (d) immediately by either party in the event the other party becomes 11.2 The Consultant's liability to indemnify the Client under clause 11.1 shall be insolvent or financially unable to proceed with the Contract. reduced proportionally to the extent that the act or omission of the Client or the employees, agents or other contractors of the Client contributed to 15.2 Upon termination of the Contract, the Consultant shall, as soon as the loss, damage, death or injury. possible, return to the Client the Client's property provided to the Consultant in carrying out the Services. 12. DISPUTES 15.3 If a party breaches (including repudiates) the Contract, nothing in this 12.1 If a dispute arises between the Consultant and the Client in respect of any clause 15 shall prejudice the right of the other party to recover damages or exercise any other right or remedy. fact, matter or thing arising out of, or in any way in connection with, the Contract or the Services, either party may give a notice in writing ("Notice 16. GOVERNING LAW of Dispute") to the other party specifying the nature of the dispute, the particulars of the party's reasons for being dissatisfied and the position 16.1 This Contract is governed by and construed with reference to the laws that the party believes is correct. stated in the Contract Particulars.

______/ ______

Entura Single Use Consultancy Contract for ASPA Bid.doc Approved version as of Thursday, 18 July 2013 Page 4 of 4