INITIAL ENVIRONMENTAL EXAMINATION (IEE)

Contract Package No.: CTEIP/KAL/WS/01

May 2016

Coastal Towns Environmental Infrastructure Project (CTEIP) ADB Loan ID No. L3133-BAN (SF)/L8284-BAN(SCF)

Batch 1: Stage I CTEIP Programme

Installation of One Production TW; One OHT, Pipeline (25.5km new pipeline; 3.1 km Replaced Pipeline; 1800 new Service Connections and 500 replaced Service Connections); One Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical works under Kalapara Pourashava, District: Patuakhali

CURRENCY EQUIVALENTS

(as of 31 December 2017)

Currency unit – taka (Tk)

Tk1.00 = $0.01209

$1.00 = Tk82.650

NOTES (i) The fiscal year (FY) of the Government of ends on 30 June. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2017 ends on June 2017.

(ii) In this report, "$" refers to US dollars.

This IEE is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

APPENDIX E

Coastal Towns Environmental Infrastructure Project (CTEIP) ADB Loan ID No. L3133-BAN (SF)/L8284-BAN(SCF)

Local Government Engineering Department

(Ministry of Local Government, Rural Development and Cooperatives)

INITIAL ENVIRONMENTAL EXAMINATION (IEE)

Batch 1: Stage I CTEIP Programme

Contract Package No.: CTEIP/KAL/WS/01

Installation of One Production TW; One OHT, Pipeline (25.5km new pipeline; 3.1 km Replaced Pipeline; 1800 new Service Connections and 500 replaced Service Connections); One Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical works under Kalapara Pourashava, District: Patuakhali

May 2016

Package: CTEIP/KAL/WS/01: IEE

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

1. INTRODUCTION ...... 1

1.1 BACKGROUND ...... 1 1.2 PURPOSE OF IEE ...... 2 1.3 SCOPE OF SERVICES ...... 2 1.4 APPROACH AND METHODOLOGY ...... 3 1.5 FORMAT OF THE REPORT ...... 5 2. POLICY, LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY ...... 6

2.1 NATIONAL RELEVANT POLICIES AND STRATEGY ...... 6 2.1.1 National Environmental Policy ...... 6 2.1.2 National Water Policy (NWP) ...... 6 2.1.3 National Forest Policy ...... 6 2.1.4 Bangladesh Climate Change Strategy and Action Plan ...... 6 2.2 LEGAL INSTRUMENTS ...... 7 2.3 INSTITUTIONAL ARRANGEMENTS / FRAMEWORK ...... 9 2.3.1 LGED and Kalapara Pourashava ...... 10 2.4 ENVIRONMENTAL CLEARANCE PROCEDURE ...... 10 2.4.1 Environmental Category: Bangladesh ...... 11 2.4.2 Environmental Category: ADB...... 12 2.4.3 Bangladesh Environmental Standards ...... 12 2.4.4 Institutional Capacity ...... 13 3. PROJECT DESCRIPTION ...... 14

3.1 THE STUDY AREA ...... 14 3.2 EXISTING AND PROPOSED WATER SUPPLY IN KALAPARA ...... 14 3.2.1 Existing Water Supply ...... 14 3.2.2 Proposed Water Supply ...... 15 3.3 LOCATION AND SELECTION OF WATER SUPPLY PROJECT ...... 15 3.4 ENVIRONMENTAL CATEGORIZATION ...... 16 3.5 PROJECT DETAILS ...... 16 3.5.1 Objective of the Project ...... 16 3.6 ANALYSIS OF ALTERNATIVES ...... 16 3.6.1 Without Project Alternative ...... 17 3.6.2 With Project Alternative ...... 17 3.7 QUANTITY OF CONSTRUCTION MATERIAL ...... 17 3.8 CONSTRUCTION SCHEDULE ...... 19 3.9 COST OF ENVIRONMENTAL MITIGATION MEASURES & MONITORING ...... 19 4. ENVIRONMENTAL BASELINES ...... 20

4.1 METHODOLOGY USED FOR THE BASELINE STUDY ...... 20 4.2 PHYSICAL CHARACTERISTICS ...... 20 4.3 BIOLOGICAL CHARACTERISTICS ...... 23 4.4 ECONOMIC DEVELOPMENT ...... 23 4.5 SOCIO-ECONOMIC CHARACTERISTICS ...... 23 5. POTENTIAL ENVIRONMENTAL IMPACTS ...... 25 5.1 METHODOLOGY ...... 25 5.2 POSITIVES IMPACTS ...... 26 5.2.1 Impact during Planning and Design Phase...... 26

Package: CTEIP/KAL/WS/01 IEE i

5.2.2 Impacts during Construction Phase ...... 26 5.2.3 Impacts during Project Operation ...... 27 5.3 NEGATIVE IMPACTS ...... 27 5.3.1. Impact during Planning Phase ...... 27 5.3.2. Impact during Construction Phase ...... 28 5.3.3 Impact during Operation Phase ...... 32 5.4 IMPACTS ANALYSIS...... 32 5.5 CUMULATIVE IMPACT ...... 33 6 GRIEVANCE REDRESS MECHANISM ...... 37 7 PUBLIC CONSULTATION ...... 39

7.1 PUBLIC CONSULTATIONS AND PARTICIPATION ...... 39 7.2 STAKEHOLDERS ...... 39 7.3 PUBLIC PARTICIPATION – METHODS AND PROCESS ...... 40 7.4 FINDINGS OF PUBLIC CONSULTATION MEETING ...... 40 8. CONCLUSION AND RECOMMENDATIONS ...... 42 8.1 CONCLUSIONS ...... 42 8.2 RECOMMENDATIONS ...... 43 8.3 DISCLOSURE OF ENVIRONMENTAL SAFEGUARDS INSTRUMENTS ...... 43

Package: CTEIP/KAL/WS/01: IEE ii

List of Tables

Table 1 Kalapara Scope of Work (CTEIP Batch 1, Stage 1) 2 Table 2 Applicable GoB Environmental Legislations 7 Table 3 DoE Classification of Water Distribution Line 11 Table 4 Relevant Environmental Quality Standards 12 Table 5 Detail of Existing Production Tube well 14 Table 6 Water Supply Project Component Details 15 Table7 Location of proposed Production Tube well 15 Table 8 Quantity of Construction material 18 Table 9 Projections Climate Change in Project Area in Years 21 Table 10 Kalapara Pourashava Population Data 25 Table 11 Environmental Attributes not Expected to have Significant Impacts 25 Table 12 Construction Material and Construction Spoils 27 Table 13 Impact Matrix of Potential Environmental Impacts 29 Table 14 Noise Levels during Construction, dB(A) 31 Table 15 Noise due to Construction Machinery 32 Table 16 Impacts Analysis 35

List of Figures

Figure 1 IEE Approach and Methodology Resulting to EMP 4 Figure 2 Environmental Clearance Process in Bangladesh 11 Figure 3 Typical Construction Schedule 19 Figure 4 Grievance Redress Process 38 Figure 5 Photograph of Public Consultation at Kalapara Pourashava 39

List of Annexure

Annexure I Rapid Environmental Assessment Checklist 45 Annexure II Grievance Registration Form 46 Annexure III Categorization Form 47 Annexure IV Involuntary Resettlement Impact Categorization Checklist 48

Package: CTEIP/KAL/WS/01: IEE iii

ABBREVIATIONS

ADB Asian development Bank DPHE Department of Public Health Engineering LGED Local Government Engineering Division BWDB Bangladesh Water Development Board CTEIP Coastal Towns Environmental Infrastructure Project SPCR Strategic Program for Climate Change Resilience PPCR Pilot Program for Climate Change Resilience DANIDA Danish Development Association OHT Over Head Tank PTW Production Tube Well TTW Test Tube Well MLD Million liter per day mbgl Meter below ground level SWL Static Water Level DWL Dynamic Water Level ft/s Feet per second DPD (WSS) Deputy Project Director (Water Supply and Sanitation) MS Mild Steel GI Galvanized Iron SS Stainless Steel BDS Bangladesh Standard BRTC Bureau of Research Testing & Consultation BUET Bangladesh University of Engineering & Technology BNBC Bangladesh National Building Code CW Cylindrical Wall DL Dead Load LL Live Load WL Wind Load HBB Herring Bone Bend BC Bituminous Carpeting CC Concrete GPS Global Positioning System RCC Reinforcement Concrete BBS Bangladesh Bureau of Statistics

WEIGHTS AND MEASURE

°C Degree Celsius Ha Hectare Km Kilometer M Meter Mm Millimeter Tk Taka % Percentage

Package: CTEIP/KAL/WS/01: IEE iv

Executive Summary

i) Coastal region of Bangladesh mostly comprises low lying areas and is exposed to sea level rise, storm surges and frequent and intense storm events leading to widespread disastrous consequences. Uncontrolled urbanization, coupled with existing inadequate capacities of the Pourashavas to manage requisite infrastructure, makes this region still more vulnerable to adverse impacts of severe and highly variable climatic conditions. Such adverse conditions, along with the burden of increased urban growth, prevailing regional poverty, exacerbated by weak urban governance, have resulted in undue pressure on basic urban services and infrastructure, which has severely impaired economic growth. As a result of these natural disasters the population in the coastal region remains poor and development significantly lags behind the rest of the country even though there is a lot of potential for further development. However, the number, intensity and the regularity of such disasters appear to be increasing and this trend is restricting further development of the coastal region. ii) The Coastal Towns Environmental Infrastructure Project (CTEIP) is a key infrastructure initiative of the Government of Bangladesh. The intervention is planned to develop climate resilient water supply infrastructural works. The proposed subproject is for the Installation of One Production TW; One OHT, Pipeline (25.5km new pipeline; 3.1 km Replaced Pipeline; 1800 new Service Connections and 500 replaced Service Connections); One Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical works iii) The challenge for the project is that the water supply infrastructures are implemented in the most economically feasible, and environmentally and socially sensitive, manner. The PPTA feasibility study, has provided a comprehensive set of recommendations for the planning, design and implementation of the Project. Based on the recommendations of this study, the DDS Consultant has completed the detailed engineering design for the installation/construction/ improvement of the Kalapara water supply works. iv) The proposed locations for the water supply components for installation/construction/ improvement in Kalapara Pourashava area under the package CTEIP/KAL/WS/01 were selected based on the recommendations of the PPTA report and subsequent site verification by the DDS Consultant, which is assessed to have minimum environmental impacts. The selected sites are well suited for their intended purpose, and have the advantages of immediate accessibility from the immediate local vicinity catchment areas within Kalapara Pourashava area. v) Categorization. An environmental assessment using ADB‟s Rapid Environmental Assessment (REA) checklist for urban development (Annexure I) was conducted and results of the assessment show that the subproject is unlikely to cause significant adverse impacts on environment and society. Kalapara water supply subproject is classified as environmental category B as per the ADB‟s Safeguard Policy Statement (SPS) 2009 as no significant impacts are envisioned. This initial environmental examination (IEE), hence, has been prepared in accordance with the requirements of Bangladesh ECR 1997 and ADB SPS 2009 and provides mitigation and monitoring measures to ensure no significant impacts as a result of the subproject. vi) Initial Environmental Examination of installation/construction/improvement of the Kalapara water supply under package CTEIP/KAL/WS/01 has followed and fulfilled the requirements of the Environmental Assessment Review Framework (EARF) Subproject Selection Criteria enumerated in the PPTA document. vii) There is no resettlement or land acquisition requirement in this subproject. The adverse environmental impacts (e.g., soil pollution, increase in water demand, impairment of air and noise qualities, health and safety risks of workers and community, etc.) due to the subproject are anticipated during the construction period, and will be of a relatively short duration. Adequate provisions have been incorporated into the planning and design of the water supply components to minimize or mitigate these unavoidable environmental impacts that are a result of the works. viii) The environmental costs are estimated at 733,718.20. The environmental monitoring cost is

Package: CTEIP/KAL/WS/01: IEE v estimated as Tk. 520000 while environmental management cost is Tk. 213718.2 (excluding those included in the cost of water supply design). This Appendix A: IEE is to be read in conjunction with the attached Appendix B: EMP, which gives a detailed breakdown of the costs for the Environmental Management and Monitoring, which are also referred in the attached Bill of Quantities. ix) The major positive achievements of water supply sub-project are:  Development of water supply will serve not only the connected houses but also the influenced area in the town.  Establishment of water supply will development and will stimulate ancillary projects which will improve economic status of the local population;  More employment of people during construction phases;  Will be potential socio-economic enhancement of economy by connecting people to semi- urban areas;  Reduction in water borne disease and better health;  Development of trained and skilled manpower in areas of plumbing, house connection; Reduction in fuel consumption, exhaust emission and green house gases;  Will facilitate capacity development and training. x) The major negative impacts, to be limited within and around the areas of construction sites, will be changes in soil loss in terms of soil erosion from RoWs, borrow-pits, quarries, etc., soil pollution, water pollution, air pollution, noise pollution, etc. These will be appropriately mitigated, for example the noise impact at source will be mitigated by job rotation and use of ear plug and other measures suggested in Environmental Management Plan (EMP). xi) The subproject‟s potential cumulative impacts were considered with respect to valued components in environmental and socio-economic categories. There are no foreseeable projects that will overlap with the subproject. xii) The environmental mitigation measures as stipulated in EMP and in the obtained environmental permit shall be monitored during implementation of the water sub-project. In order to perform monitoring of EMP, the contractor shall engage experienced laboratory and third party services in complying the required environmental testing of listed parameters. xiii) The labour camps shall be established with the septic tank and soak pit for treatment and disposal of sewage and sullage water to avoid pollution of water bodies. Contractor shall submit the EMP for construction camp site for approval of engineer in charge. In addition, contractor shall arrange water of required quality for the camp and construction activities. xiv) The environmental monitoring will be required before the start of the construction and during the construction phase. The parameters of Water Quality, Air Quality, Noise quality, and Soils shall be monitored; as specified in EMP. During the whole project period, total frequency of monitoring has been estimated is 8. xv) During public consultation recommendations were drawn including: i) involve local communities in all stages of project planning and development, ii) establish permanent communication between project initiators and local authorities, iii) setup grievance redress mechanism which will publicized through Pourashava level co-ordination committee and monitoring register and iv) during construction, local people including women shall be given first priority in the employment of skilled and unskilled labour. xvi) In view of above, it is concluded that the Project will bring benefit to the people of the area. The negative impacts occurring during implementation are within the manageable limits and shall be mitigated with the proposed EMP and hence project may be implemented. xvii) LGED will disclose this Environmental Management Framework by making copies available at its head office and in District / Pourashava where the Project is situated. The copies shall also be made available to the Local Government‟s Agencies, the Environmental and Social Group and other stakeholders. The Government of Bangladesh will also authorize the Asian Development Bank to disclose this IEE and EMP electronically through its InfoShop.

Package: CTEIP/KAL/WS/01: IEE vi

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

1. Introduction

1.1 Background

1 Bangladesh‟s urban water supply is facing a massive challenge in providing safe water supply and sanitation services to sharply increasing population in towns. To meet the future demand for water supply and sanitation services with reliable and safe water supply systems, the management capacity of urban utilities should continue to improve. The overall population growth rate is about 1.5 percent. However, the influx of population in urban areas has taken the growth rate over 3.5 percent, on average, whereas the growth rate of urban migration in metropolitan cities is about 5 percent. Urban areas in Bangladesh can be divided into three tiers: Dhaka and Chittagong city that have populations of many millions; four city corporations with populations of between 0.3 to 1.5 million; and 309 urban municipalities with populations of 0.05 to 0.3 million. The total urban population, estimated to be about 25 million, is expected to be 50 million by the end of 2015. The average coverage by piped water supply in the Pourashavas is only 39 percent; 32 percent is served by hand tube wells and remaining 29 percent having their own sources. At present, urban populations, especially poor people are the most vulnerable if water supply and sanitation services are inadequate. Large numbers of future urban populations will thus require a reliable and safe piped water supply system.

1 Coastal region of Bangladesh mostly comprises low lying areas and is exposed to sea level rise, storm surges and frequent and intense storm events leading to widespread disastrous consequences. Water Supply system along with existing other infrastructural facilities in urban, semi- urban and rural areas of the region become easy prey to extensive damages and disasters caused by such natural events. Coupled with such natural events are the two-thirds of the country lying at heights less than 500mm of the mean-sea-level, the impacts of impending changes in the climatic phenomena and the existing limited as well as inadequate management capacities of the Pourashavas make the situation of the water supply of this region still more vulnerable. Such a situation has necessitated consideration of anticipated climate change impacts on the water supply of the country over the 20-25 years design life and providing for additional protection measures with improved sewerage and/or drainage system.

3 The Coastal Towns Environmental Infrastructure Project (CTEIP) is a key infrastructure initiative of the Government of Bangladesh. The Project was prioritized in the Government's 2010 Strategic Programme for Climate Resilience (SPCR), prepared under the Pilot Program for Climate Resilience (PPCR), whereby the CTEIP is eligible for financing from the Strategic Climate Fund (SCF) within the multi-donor coordinated Climate Investment Funds (CIF) as a pilot project for demonstrating ways to mainstream climate resilience into development. Intervention is planned to develop climate resilient structures, including cyclone shelters; roads and bridges; water supply; sanitation; drainage; solid waste management; municipal facilities and flood protection infrastructural works.

4 The coastal towns Environmental Infrastructure Project (CTEIP) finances basic urban infrastructure services to increase climate resilience due to climate change. These projects will receive investments in two stages: i) Stage 1 focuses on infrastructure crucial for climate resilience such as roads, cyclone shelters, water supply and sanitation, solid waste management and drainage; and Stage 2 includes other infrastructure that contribute to general economic development such as roads, markets, boat landing station and bus terminals. This project report is on Initial Environmental Examination due to the construction of water supply in Kalapara Town. The package is designated as CTEIP/KAL/WS/01. Initial Environmental Examination (IEE) of water supply components is reported in Appendix-A. This Appendix B is on Environmental Management Plan (EMP) for the Installation/Construction / Improvement of Water Supply .

5 Water supply sub-project is planned for Kalapara town. The sub-project will improve the water coverage mostly within urban and semi urban areas of Kalapara, . The water supply components are designed to meet future water requirements. EPTISA Services de Ingenieria S.L., the Detailed Design Services (DDS) Consultant under the CTEIP, in accordance with the ADB‟s requirements and guidelines, has conducted this Initial Environmental Examination (IEE). The IEE is based upon a study of available reports, documents and field visits including the Project Preparatory Technical Assistance (PPTA), under TA 8128 BAN; relevant sections of the Capacity Development Technical Assistance (CDTA) Report; discussions with related stakeholders and PIU/Pourashava authorities.Read this IEE in conjunction with the following documents, attached to this Bid Document:

Package: CTEIP/KAL/WS/01: IEE 1

 Environmental Management Plan (EMP) attached hereto as Appendix F;  Due Diligence Report (DDR) attached hereto as Appendix G;  Gender Action Plan (GAP) attached hereto as Appendix H.

1.2 PURPOSE OF IEE

6 The initial environmental examination aims to provide guidance on safeguard screening, assessment, institutional arrangement and process to be followed for components of the project, where design takes place after Boards approval. This IEE (i) describes the project and its components; (ii) explains the general anticipated environmental impacts and mitigation measures for the subprojects; (iii) specifies the requirements that will be followed in relation to screening and categorization, assessment, and planning, including arrangements for meaningful consultation with affected people and other stakeholders and information disclosure requirements; (iv) assesses the capability of the project proponents to implement national laws and ADB‟s requirements, and identifies needs for capacity building; (v) specifies implementation procedures, institutional arrangements, and capacity development requirements; and (vi) specifies monitoring and reporting requirements. Moreover, this IEE is to ensure that it is in line with ADB EARF and in the entirety of its project cycle, will not deteriorate or interfere with the environmental sensitivity of the project area, but rather improve environmental quality.

1.3 SCOPE OF SERVICES

7 The scope of the project includes installation of One Production TW; One OHT, Pipeline (25.5km new pipeline; 3.1 km Replaced Pipeline; 1800 new Service Connections and 500 replaced Service Connections); One Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical works

The major components to be taken up in Kalapara under this project are described in Table 1. This report is on IEE of Kalapara for water supply in Kalapara Pourashava area, District: Patuakhali and the package is designated as CTEIP/KAL/WS/01.

Table 1: Kalapara Scope of Work (CTEIP Batch 1, Stage 1) Sl. No. Scope of Works i. Production TW- One with Test TWs. ii. Overhead Tank-one (500m3) iii. Distribution and transmission pipeline- 25.5 km (Ranging from100mm dia to 200mm dia with HDPE pipe ) iv. Replaced Pipeline -3.1 km (From 63mm dia to 100 mm dia) v. Service Connection: 2,300 nos. including 500 reconnection of existing service connection. vi. Pump house-One Pump house at PTW site. vii. Supply of O & M tools viii. Electro-mechanical works

8 The scope of work includes ensuring that installation and/or construction and/ or implemented of the works will be in an environmentally sustainable manner and in full compliance with the Asian Development Bank‟s environmental safeguard policies and regulations. The scope of services in brief is as follows:

 Document baseline data for various environmental attributes on physical, water, ecological pollution and physical cultural resources and Socio-economic profile;  Assess positive and negative environmental impacts of the proposed works;

Package: CTEIP/KAL/WS/01: IEE 2  Prepare environmental mitigation measures and management plans to effectively address the impacts;  Prepare Initial Environmental Examination (IEE) so that these are acceptable to the Asian Development Bank;  Prepare post-project monitoring programs, institutional arrangement to implement the environmental plans; and  Prepare cost estimates for the environmental management and monitoring programs.

1.4 APPROACH AND METHODOLOGY

9 The package CTEIP/KAL/WS/01 has followed the Environmental Assessment Review Framework (EARF) subproject selection criteria as enumerated in PPTA document. The approach in preparation of IEE has been to follow the sequence of steps adopted in an EIA study in relation to EARF. Apart from following standard environmental impact assessment practices and procedures, methodologies have deployed advanced technologies, techniques and tools to the extent these are applicable and relevant to this project. The approach and methodology flow chart is presented in Figure-1. Toward ascertaining baseline conditions and assessing the impacts during construction and operation of the project, the consultants have taken into account the various parameters of the environment – topography, physiographic, soils, hydrology and drainage, meteorology, qualities of ambient air and noise, surface water, groundwater, biodiversity, socio-economic aspects including gender issues, land/property, physical and cultural resources. The baseline data for environmental attributes were collected from primary and secondary sources. The primary sources include site visits and visual inspection. The secondary sources include the reports, books, maps and documents from various government and non-government organizations on subject matter. The impacts are assessed for various phases of project cycle namely:

 Impacts due to project location and design,  Impacts due to project construction, and  Impacts due to project operation. 10 The impacts are categorized as negative and positive. The standard methodology for the review, field visit, data collection, impact assessment and formulation of management plans is adopted. The Bangladesh National Acts, Legislation and Laws were consulted with a view to ensuring compliance with various requirements. The environmental attributes were compiled from both primary and secondary sources.

11 The management plans are essential to ensure that stress/ loads on the systems are within carrying capacity. The management plans aims at maintaining the environmental quality of project area at-least in pre-project stage. An environmental management plans were developed to mitigate the adverse impacts. Efforts are made to enhance the quality of environmental attributes.

12 It is necessary to monitor any changes of the quality of environmental parameters during construction and operation. Monitoring would indicate any environmental problems, which will be reviewed for correction. This will facilitate to assess the effectiveness of management and/or mitigation measures.

Package: CTEIP/KAL/WS/01: IEE 3

Desk Research, Acts, Legislation, Review of Previous Reports, Reconnaissance and Discussion

Scoping / Identification of Field visit Parameters

EcologicalEnvir Environmental Physical Socio-economics onment Pollution  EnvironmentTopography  Flora  Water  Social Status  Fauna: Pollution  Land use  Infrastructure  Tree /  Soil pattern facilities Forest  Air  Drainage/  Physical Cultural  Fisheries  Noise hydrology Resources

Compile Environmental Baseline Data

Field Studies

Analysis and Screening of Environmental Impacts Public Consultation

Review and Update of Impacts

Potential Environmental Impact Assessment No impact

Preparation of Environmental Management Plan

Environmental Monitoring Programs, Management Viability of Conclusion and Recommendations

Figure 1: IEE Approach and Methodology Resulting to EMP

Package: CTEIP/KAL/WS/01: IEE 4 1.5 FORMAT OF THE REPORT

13 This report has been prepared taking into consideration the IEE mechanisms, procedures and contents spelt out in Environmental Conservation Act of 1995 and its subsequent amendments in 2000, 2002 and 20101 of Bangladesh and ADB Environmental Assessment Guidelines (2003) and Safeguard policy statement (2009). The main findings are reported in conclusions and recommendations for discloser locally and the ADB web site. The report has an Executive Summary in the beginning.

Chapter 1 provides a general introduction to the project along with the project background, objectives and scope of the study and an outline on the approach and methodology adopted for the study. Chapter 2 is a concise document on the policy and strategies; legal instruments, and institutional arrangement under which the project will be developed. Chapter 3 is on the Project Description which highlights the need for the development. The project Construction Schedules material requirements and cost of project are also summarized. Chapter 4 is on the baseline environmental and social conditions in pre-construction phase in sufficient detail to enable an adequate assessment of the potential environmental and social impacts. Chapter 5 is on Screening of Potential Environmental Impacts and describes the environmental impacts that could occur as a result of the proposed project. Chapter 6 is on Grievance Redress Mechanism; Chapter 7 is on public consultation; Chapter 8 is on Conclusion and Recommendations.

14 The literature, books, reports and maps referred are presented as foot notes in the main body of the report. At the end, the report has Annexure which are reported in the main body of the report.

1 ECA Amendment 2000 focuses on ascertaining responsibility for compensation in cases of damage to ecosystems, increased provision of punitive measures both for fines and imprisonment and the authority to take cognizance of offences. ECA Amendment 2002 elaborates restrictions on polluting automobiles; restrictions on sale, production of environmentally harmful items like polythene bags; assistance from law enforcement agencies for environmental actions; break up of punitive measures; and authority to try environmental cases. In ECA Amendment 2010, no individual or institution (government or semi-government/non-government/ self governing can cut any hill or hillock; earth-fill or change the status of any water body/wetland/lakes/natural canals, etc., even in national interest; the aforementioned activities can be done only after getting clearance from respective the departments/agencies/authorities.

Package: CTEIP/KAL/WS/01: IEE 5 2. POLICY, LEGAL FRAMEWORK AND INSTITUTIONAL CAPACITY

2.1 NATIONAL RELEVANT POLICIES AND STRATEGY

15 This Section describes the relevant policies and strategies, legal instruments, institutional arrangement and framework applicable to CTEIP-related rehabilitation and /or construction activities in various Pourashava areas in the Bangladesh coastal region. It summarizes the National Laws and describes the procedure for obtaining environmental permits to allow project implementation. Over the years the Government of Bangladesh has enacted Environmental Acts, Rules, Policies and Regulation toward imposing restrictions facilitating minimization / mitigation of likely impacts due to development projects. The most important Act is Environmental Conservation Act, 1995 (ECA, 1995) and Environmental Conservation Rules (ECR, 1997).

2.1.1 National Environmental Policy

16 The National Environmental Policy was adopted in 1992 and is now under revision. It embraces different sectors related to agriculture, forest, power, health, transport, housing etc. The central theme of policy is to ensure protection and improvement in environment. The policy gives a thrust to sustainable development and long-term use of natural resources. The National Environment Policy contains policy statements and strategic options with regard to population and land-use management, management and utilization of natural resources and other socio-economic sectors, as well as the necessary arrangements for the implementation of the policy. The policy enables:

 the country to strike a dynamic balance between population and resources while complying with the balance of ecosystems;  to contribute to sustainable and harmonious socio-economic development such that, both in rural and urban areas, and well-being in a sound and enjoyable environment; and  to protect, conserve and develop natural environment.

2.1.2 National Water Policy (NWP)

17 The National Water Policy, 2004 (NWP) aims for sustainable management of water. The Policy also integrates the environmental impact assessment for water development projects. The policy stresses on issues related to climate change such as:

 Augmentation of dry season flows;  Awareness raising in consumptive use of surface and ground water; and  Structural and non-structural mitigation measures (early warning systems).

2.1.3 National Forest Policy

18 National Forest Policy (NFP) was established in 1994. Under this policy it is proposed to increase the forest cover and to promote and oversee forestry activities. The policy fixed the target of forest cover at least 20% of geographic area by the year 2015. Tree plantation on the roadside verges courtyards of rural organization such as Union Parishad, school, Eidgah, mosque-Moktob, temple, club, orphanage home, madrassa etc. and other fallow lands around will be encouraged. The government will encourage this type of initiative and extend technical and other supports.

2.1.4 Bangladesh Climate Change Strategy and Action Plan

19 The Bangladesh climate change strategy and action plan was approved in 2009. The climate change plan is built on six pillars namely i) food security, social protection and health; ii) comprehensive Disaster Management; iii) infrastructure; iv) research and knowledge management; v) mitigation and low carbon development; and vi) capacity building and institutional. The strategy and action plan emphasizes on eensuring existing assets (e.g., coastal and river embankments) are well maintained and fit for purpose and that urgently needed infrastructure is put in place to deal with the likely impacts of climate change. - enhance the capacity government ministries, civil society and private sector to meet the challenge of climate change.

Package: CTEIP/KAL/WS/01: IEE 6 2.2 LEGAL INSTRUMENTS

20 The Ministry of Environment and Forests (MoEF) is responsible for preparation of environmental policies. MoEF also has formulated regulation toward clearance of projects from environmental angles based on environmental impact assessment report. The Department of Environment is responsible for environmental issues while forest issues are looked after Department of Forests. Over the years the MoEF has adopted number of legal instrument in the form of acts for the protection and conservation of the environment. Table 2 summarizes the Environmental Legislation applicable to the sub-project.

Table 2: Applicable GoB Environmental Legislations Sl.No Legislation Requirement for the Project Relevance 1. Environmental  Restriction on operation and process, which The provisions of the Act apply to the Conservation can be continued or cannot be initiated in the entire subproject in the construction Act of 1995 and ecologically critical areas and operation and maintenance amendments in  Regulation on vehicles emitting smoke (O&M) phases. harmful to the environment 2000, 2002  Remedial measures for injuries to ecosystems and 20102  Standards for quality of air, water, noise and soil for different areas and limits for discharging and emitting waste  Environmental guidelines 2. Environmental Environmental clearances The subproject is categorized as Conservation  Compliance to environmental quality Orange-B and requires LCC and Rules of 1997 and standards ECC. All requisite clearances from amendments in DoE shall be obtained prior to 2002 and 2003 commencement of civil works. 3. Forest Act 1927 &  Clearance for any felling, extraction, and Refer Baseline and EMP amendments transport of forest produce (2000) 4. Bangladesh  Ensure existing assets (e.g., coastal and river Considered in project design Climate embankments) are well maintained and fit for components Change Strategy purpose and that urgently needed and Action infrastructures (cyclone shelters and urban drainage) is put in place to deal with the likely Plan of 2009 impacts of climate change.  enhance the capacity government ministries, civil society and private sector to meet the challenge of climate change 5. Bangladesh Labour  Compliance to the provisions on employment The provisions of the act apply to the Law of standards, occupational safety and health, entire subproject in the construction 2006 welfare and social protection, labour relations and O&M phases. Provides for and social dialogue, and enforcement occupational health and safety of  Prohibition of employment of children and workers and community during adolescent construction phase. 6. The Building Act is in English and rules currently Construction Act, available in Bangla: Pourashava to 1952 (amended & develop the conditions under this Act gazetted in 2008) but have yet to utilize. 7. The Town Only applicable for RAJUK and

2 ECA Amendment 2000 focuses on ascertaining responsibility for compensation in cases of damage to ecosystems, increased provision of punitive measures both for fines and imprisonment and the authority to take cognizance of offences. ECA Amendment 2002 elaborates restrictions on polluting automobiles; restrictions on sale, production of environmentally harmful items like polythene bags; assistance from law enforcement agencies for environmental actions; break up of punitive measures; and authority to try environmental cases. In ECA Amendment 2010, no individual or institution (government or semi-government/non-government/ self governing can raise any hill or hillock; earth-fill or change the status any water body/wetland/lake/natural canal, etc., even in national interest; the aforementioned activities can be done only after getting clearance from respective departments.

Package: CTEIP/KAL/WS/01: IEE 7 Sl.No Legislation Requirement for the Project Relevance Improvement Act therefore not relevant. 1953 8. Building Building Construction Rules 2008 Construction Rules version appropriate to Dhaka City. 2008 Pourashava utilizing 1996 version. 9. Bangladesh Bangladesh National Building Code National Building (BNBC) 2006 currently not gazetted Code (BNBC) 2006 by the GoB. Approved copy 1993 referred for which the relevant clauses have been closely followed and incorporated within IEE. 10. Bangladesh Water  Restriction on design, operation and process  The provisions of the Act apply to Act, 2013 in order to comply to the requirements of the the entire subproject in the design, Act for integrated development, management, construction and operation and extraction, distribution, usage, protection and maintenance (O&M) phases. conservation of water resources for better  Requires LCC and ECC. All management of water resources requisite clearances from DoE shall be obtained prior to commencement of civil works. 11. Water Pollution EPCO‟77 superseded WPCO‟70 & Control Ordinance, extended the control, prevention & 1970 abatement of pollution to the entire environment & expanded definition of “pollution” from that specifically relating to waters to “air, water or soil”. 12. Environmental  EPCO‟77 repealed, and ECA‟95 & Pollution Control ECR‟97 enacted Ordinance, 1977  Environmental Pollution Control Board formed under EPCO‟77 has now grown into DoE 13. National  Restriction on operation and process to The provisions of the policy apply to Environmental maintain overall development through the entire subproject in the Policy, 1992 protection and improvement of environment construction and O&M phases through environmental management. (revised in 2015)  Remedial measures for injuries to ecosystems  Standards for quality of air, water, noise and soil for different areas and limits for discharging and emitting waste 14. National NEMAP‟95 includes activities relating Environmental to fisheries and agriculture Management Plan, 1995 15. The Environmental  Compliance to the relevant provisions &  The provisions of the Act apply to Court Act, 2000 requirements of ERA‟95 & ECR‟97 the entire subproject in the (amended in 2002 construction and operation and & 2010) maintenance (O&M) phases.  Requires LCC and ECC. All requisite clearances from DoE shall be obtained prior to commencement of civil works. 16. The National Water  Restriction on operation and process in order The provisions of the policy apply to Policy, 1999 for protection of water quality the entire subproject in the construction and O&M phases through environmental management. 17. Ozone Layer No relevance with the project Destruction Materials (Control) Rules, 2004 18. Bio-safety Rules, No relevance with the project 2012 Source: TA 8128 Coastal Towns Infrastructure Improvement Project Volume 6

Package: CTEIP/KAL/WS/01: IEE 8 2.3 INSTITUTIONAL ARRANGEMENTS / FRAMEWORK

21 The main Ministry, Department, Institutions and Boards responsible for development of policy, framing regulation, developing projects, monitoring and approval of issues related to environment protection and conservation are presented in this section.

22 The Department of the Environment In 1977, Environment Pollution Control Board with 16 members headed by a Member of the Planning Commission and Environment Pollution Control Cell headed by a Director with staff complement of 26 was established. This was followed in 1977 by the establishment of the Environment Pollution Control Project, in 1985 by the establishment of the Department Pollution Control and finally, in 1989 by the restructured and renamed the Department of Environment (the Department) the activities of which are overseen by a Director General. The Department discharges its responsibilities through a head office and six Divisional offices located in Dhaka, Chittagong, Khulna, Bogra, and Sylhet. Of late, the Government has established 21 new offices at district level with the creation of 468 new positions.

23 DOEs activities affect every socio-economic sector and direct and influence all activities wherever they might take place in Bangladesh. The department was created in 1989 to ensure sustainable development and to conserve and manage the environment of Bangladesh. Over the last decades the major activities performed by the department had undergone significant metamorphosis- from a limited scope of performing merely regulatory and routine function scope of performing merely regulatory and routine function to a wider and broader horizon comprising more action-intensive and research oriented endeavors of investigating, identifying, conserving and nurturing as well as enhancing the qualities of the various ecosystems encompassing the overall environment of country.

24 The basic philosophy behind the establishment of the DOE was environment conservation, pollution control and management of environment in its totality. So we can easily measure the major functions of the DOE through analyzing the following points of activities:  Environmental quality monitoring  Awarding environmental clearance to industries/development project  Compliance & Enforcement  Ecologically Critical Areas and Natural Resource Management  Planning & Development and Research  Environmental awareness and partnership building  Human Resource Development  Compliance to regional and international conventions, treaties and protocols  Information, Library and Documentation

25 The Ministry of Environment & Forests is the nodal agency in the administrative structure of the Central Government, for the planning, promotion, co-ordination and overseeing the implementation of environmental and forestry programmes. MoEF oversees all environmental matters in the country and is a permanent member of the Executive Committee of the National Economic Council. The Ministry also plays a pivotal role as a participant of United Nations Environment Programme (UNEP). The principal activities undertaken by Ministry of Environment & Forests consist of conservation & survey of flora, fauna, forests and wildlife, prevention & control of pollution, forestation & regeneration of degraded areas and protection of environment, in the framework of legislations. The main tools utilized for this include surveys, impact assessment, control of pollution, regeneration programmes, support to organizations, research to solve solutions and training to augment the requisite manpower, collection and dissemination of environmental information and creation of environmental awareness among all sectors of the country's population. The organizational structure of the ministry covers a number of divisions, directorate, board, subordinate offices, autonomous institutions and public sector undertakings. In short, Ministry of Environment & Forest (MoEF) has the following major functions:  Management of environment and ecology.  Matters relating to environment pollution control.  Conservation of forests and development of forest resources (government and private), forest inventory, grading and quality control of forest products.  Forestation and regeneration of forest extraction of forest produce.  Plantation of exotic cinchona and rubber.  Botanical gardens and botanical surveys.  Tree plantation.

Package: CTEIP/KAL/WS/01: IEE 9  Planning cell is responsible for preparation of schemes and coordination in respect of forest.  Research and training in forestry.  Mechanized forestry operations.  Protection of wild birds and animals and establishment of sanctuaries.  Matters relating to marketing of forest produce.  Liaison with international organizations and matters relating to treaties and agreements with other countries and world bodies relating to subjects allotted to this Ministry.

2.3.1 LGED and Kalapara Pourashava

26 The Local Government Engineering Department (LGED) is the executing agency. LGED has constituted a Project Management Unit (PMU) and Project Implementation Unit (PIU). The PMU is headed by Project Director (PD). In order to put the project to logical conclusion the PD is assisted by three consultant team to assist and support the PMU and PIU (Project Implementation Unit). The consultant teams are: i) Detailed Design Services (DDS); ii) Project Management and Supervision Consultant (PMSC), and Institutional Capacity and Community Development consultant (ICCDC). The Pirojpur Pourashava will be the implementing agency and will be assisted by PIU. The facility created during the sub-project will be operated and maintained by Pirojpur Pourashava.

2.4 ENVIRONMENTAL CLEARANCE PROCEDURE

27 Under ECR 1997 industrial units and projects are classified into four categories according to “their site and impact on the environment”, and each category (Green, Orange-A, Orange-B and Red) requires a different level of environmental assessment as a prerequisite for granting the ECC that allows project to proceed. The Environmental Clearance Certification Process is shown in Figure 2.

28 Rule 7 of the ECR indicates that the application for ECC must be made to the relevant DoE Divisional Officer, and the application for the projects will include the following: . Completed Application for ECC, and the appropriate fee; . Report on the feasibility of the project; . Report on the IEE for the project; . Report on the environmental management plan (EMP); . No objection certificate from the local authority; . Emergency plan relating to adverse environmental impact and plan for Mitigation of the effect of pollution; and . Outline of the relocation and rehabilitation plan (where applicable).

29 Under the ECR, DoE has 30 days to respond to receipt of the ECC application for project.

Package: CTEIP/KAL/WS/01: IEE 10

Figure 2: Environmental Clearance Process in Bangladesh

2.4.1 Environmental Category: Bangladesh

30 For the purpose of issuance of Environmental Clearance Certificate, the industrial units and projects shall, in consideration of their site and impact on the environment, be classified into the following four categories: (a) Green, (b) Orange – A, (c) Orange – B, and (d) Red. The Industries and projects included in the various categories are specified in sub-rule (1) have been described in Schedule – 1. The ECA indicates that all industrial units or projects must obtain a Location Clearance Certificate (LCC) and Environmental Clearance Certificate (ECC) from the Department of Environment (DoE). No industrial unit or project shall be established or undertaken without obtaining environmental clearance from DoE in the manner prescribed by the rules.The environmental category of projects is listed in Schedule – 1 of ECR.Table 3 describes DoE classification for water supply components and the project may be classified as Orange B.

Table 3: DoE Classification of Water Distribution Line

Sl.No. in ECR Components Items in Schedule-1 of ECR DOE Classification 64 Water distribution line Construction, Re-construction and Orange B. laying/relaying/extension Extension of water distribution line Source: ECR, 1997, MOEF

Package: CTEIP/KAL/WS/01: IEE 11 2.4.2 Environmental Category: ADB

31 Asian Development Bank (ADB) requires the consideration of environmental issues in all aspects of ADB‟s operations, and the requirements for environmental assessment are described in ADB SPS, 2009. This states that ADB requires environmental assessment of all project loans, program loans, sector loans, sector development program loans, loans involving financial intermediaries, and private sector loans.

32 Screening and categorization: The nature of the environmental assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project; the sensitivity, scale, nature, and magnitude of its potential impacts; and the availability of cost-effective mitigation measures. Projects are screened for their expected environmental impacts, and are assigned to one of the following four categories:

 Category A. Projects could have significant adverse environmental impacts. An EIA is required to address significant impacts.  Category B. Projects could have some adverse environmental impacts, but of lesser degree or significance than those in category A. An IEE is required to determine whether significant environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report.  Category C. Projects are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed.  Category FI. Projects involve a credit line through a financial intermediary or an equity investment in a financial intermediary. The financial intermediary must apply an environmental management system, unless all projects will result in insignificant impacts.

33 As per above environmental classification of ADB, the water supply sub-project in Kalapara falls in Category B.

2.4.3 Bangladesh Environmental Standards

34 The Ministry of Environment and Forest has developed standards from time to time for water and air quality for discharge in the ambient air. The relevant standards are summarized in Table 4.

Table 4: Relevant Environmental Quality Standards

Standards ECR 1997 Rule Details of Specification Air Quality Schedule 2 Standards for Air parameters: Suspended Particulate Maters (SPM); Sulphur dioxide; Carbon; Monoxide Oxides; Nitrogen For the categories: a) Industrial and mixed; b) Commercial and mixed; c) Residential and rural; d) Sensitive. A) Inland Surface Schedule 3 Standards for water parameters: pH; BOD (mg/l); DO (mg/l); Total Coliform Waters (number/100) For the Classifications: a) Source of drinking water for supply only after disinfecting; b) Water usable for recreational activity; c) Source of drinking water for supply after conventional treatment; d) Water usable by fisheries; e) Water usable by various process and cooling industries f) Water usable for irrigation. B) Drinking Water Schedule 3 Standards for the given parameters

Sound Schedule 4 Standards for Sound (determined for Day (dBa unit); and Night (dBa unit) For the categories: a) Silent Zone; b) Residential Area; c) Mixed Area; d) Commercial Area; e) Industrial Area: Sound originating from Schedule 5 Standards of sound of Motor Vehicles (all types) (dBa) As measured:

Package: CTEIP/KAL/WS/01: IEE 12 Standards ECR 1997 Rule Details of Specification

Motor Vehicles at a distance of 7.5 meters from exhaust pipe; at a distance of 0.5 meter from exhaust pipe.

Emissions from Motor Schedule 6 Standard Limits for Emission of Motor Vehicles for the parameters of Black Vehicles Smoke (Hartridge Smoke Unit (HSU)); Carbon Monoxide (gm/km percent area); Hydrocarbon (gm/km ppm); Oxides of Nitrogen (gm/km ppm)

Odour Schedule 8 Standards for odour (ppm) for the parameters of Acetaldehyde; Ammonia; Hydrogen Sulfide; Methyl Disulfide; Methyl Sulfide; Styrene; Trim ethylamine.

Sewage Discharge Schedule 9 Standards for Sewage Discharge for the Parameters of BOD (miligram/l); Nitrate (miligram/l); Phosphate (miligram/l); Suspended Solids (SS) (miligram/l); Temperature (Degree Centigrade); Coliform (number per 100 ml). Waste water from Schedule 10 Standards for Waste water from Industrial Units or Projects Waste for the Industrial Units or given parameters for the Places of Determination of Standards: Projects Waste Inland Surface Water; Public Sewerage system connected to treatment at second stage; Irrigated Land. Source: ECR 1997, MOEF

2.4.4 Institutional Capacity

35 The Ministry of Environment and Forests has the capacity to formulate policy, legislation, standards and review the environmental impact assessment (EIA) of the development projects. The project is cleared by two committees. The Pourashava gives the site clearance by location clearance committee (LCC). The project is submitted to DoE for environmental clearance committee (ECC). The projects are implemented at local or Pourashava level and executed at central level. Local Government Engineering Department (LGED) executes the projects on water supply, sewerage, solid waste management, etc. The environmental impact assessment is conducted by the consulting agencies by outsourcing including the DDC and PMSC Consultants. The sphere of LGED activities is for a better environment and health. Most of the engineers involved with design and construction activities are familiar with the environmental issues. LGED has also appointed an Executive level officer to look into the critical issues. The LGED is assisted by consultants for monitoring of environmental attributes and training. LGED has established a quality control lab where parameters related to water, waste water and soils can be monitored. However there is a scope to train engineers at each level for conducting environmental impact assessment and preparation of management plans. Further, to avoid adverse negative environmental impacts of a proposed shelter, no contract tender should be launched before specific IEE / EIA based on final design is prepared, the EMP with the management measures is approved by DoE.

Package: CTEIP/KAL/WS/01: IEE 13 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

3. PROJECT DESCRIPTION

3.1 THE STUDY AREA

36 Kalapara is situated in Patuakhali District, which is located at the southern coastal region of the country. It is bound by on the north, the Bay of on the south, on the east, and Patuakhali District on the west.Kalapara Pourashava was a police station in the past and was upgraded as a Pourashava in 1997. It is located between 210 48‟and 220 05‟ north latitudes and between 900 05‟ and 900 20‟east longitudes and bound on the north and the west flanks by Kalapara Upazila of Patuakhali District, on the east by of Patuakhali District and on the south by the Bay of Bengal.

2 37 KalaparaPourashava is the only urban area of the Upazila andoccupies an area of 3.82km , with a population of 17,311 as per BBS Census 2011.

3.2 EXISTING AND PROPOSED WATER SUPPLY IN KALAPARA

3.2.1 Existing Water Supply

38 The current system of piped water supply of Kalapara Pourashava is based on groundwater source. Quality of Groundwater is acceptable for use directly from source without any treatment. The potential abstraction rate and the acceptable water quality confirm the aquifer potential as a source for piped water supply. Size and Capacity of existing PTWs: Size of the existing PTWs is 300X150 mm and capacity of designed discharge was calculated 60m3/h. The present abstraction rate of existing three PTWs is 178m3/hour. The existing PTWs are installed at depth of around 306m below from ground level. Location of the existing PTWs Both Production Tube wells have been installed in Kalapara Degree College compound under DPHE –DANIDA Water Supply and Sanitation Project in 1998. Distance between these PTWs is only around 100m. Detail of Existing Production Tube well is shown in Table -5

Table No.5 Detail of Existing Production Tube well

Sl PTW-03 Production TW Details PTW-01 PTW-02 No 01 Year of installation 1998 1998 2012

02 Size of well 150mmX350mm 150mmX350mm 150mmX350mm

03 Drilled depth 380m 375m 342m

04 Cased depth 354 370m 335m

05 Base of Pump 34m 34m 36m

06 Top of screen 310m (& 2nd screen 311m (& 2nd screen top 289m top 336m) 336m)

07 Base of screen 325m (& 2nd screen 326m (& 2nd screen base 281m base 351m 351m)

08 Production Capacity 62m3/h 56m3/h 70m3/h

09 Present Capacity 60m3/h 56m3/h 62m3/h

10 Av Operational time 16 hours per day 16 hours per day 10 hours per day

11 Production capacity per day 960 m3 896 m3 620 m3

Source: Kalapara Pourashava Project

Package: CTEIP/KAL/WS/01: IEE 14

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Comments on Exiting PTWs: Designed yield of the Exiting three PTWs are calculated as 70m3/h. But distance of the two PTWs installed from the DPHE-DANIDA project is only 100m. As a result, drawdown is high and efficiency of the PTWs is going down day by day. The Present abstraction rate of the PTWs is 60m3/h and 56m3/h. After some years it will be decreased. Third PTW was installed from the UGIIP-II project, its production rate is 62 m3/h.

3.2.2 Proposed Water Supply

39 Uncontrolled urbanization, along with the absence of adequate capacity to manage requisite infrastructure, the Pourashavas of coastal towns are vulnerable to adverse affects of severe and highly variable climate. This is more acute in low lying areas naturally exposed to sea level rise, storm surges and more frequent and intense storm events, leading to potential environmental and social impacts. In order to increase and expand the water supply in Kalapara Pourashava coverage for 24/7 e.g. 100% coverage to the designed period, 2040 the following water supply components have been designed.

The summary of works of proposed water supply network for Kalapara Town is summarized in Table 6.

Table 6: Water Supply Project Component Details

Sl. No. Component Description Quantity Type of Material 1 Production Tube Well (PTW) (Number) 1.0 MS / DI Pipes 2 Over Head Tank (OHT) for water Storage and 1.0 RCC Distribution (Number) 3 Water Supply Distribution Lines (km) 25.5km (new) uPVC/HDPE/GI/DI/MS 3.1 km (replaced) 4 Service Connection (Numbers) 2,300 nos. uPVC/HDPE/GI including 500 reconnection 5 Power Generators (Numbers) 1.0 Diesel Generators 6 Pump House 1.0 RCC

3.3 LOCATION AND SELECTION OF WATER SUPPLY PROJECT

40 . The proposed water supply sub-project at Kalapara Pourashava in Patuakhali District. The geographic location of the Pourashava is between latitude 210 48‟and 220 05‟ north and between longitude 900 05‟ and 900 20‟east. Particular attention has been paid to the data and recommendations contained in the PPTA Reports, which have been further reviewed and site verified in advance of progressing with the detailed design

The proposed source/storage for Kalapara Pourashava designed based on proposed OHT (500m3). and proposed one PTW are considered as water source. One PTW location selected at Pumping station at proposed new bus terminal. On further vision, it has been decided to increase water supply source. The location for the new PTW is presented in Table : 7

Table No.7- Location of proposed Production Tube well

PTWs No. Location Remarks 01 Proposed new bus terminal Site selected by Pourashava

Package: CTEIP/KAL/WS/01: IEE 15

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

The sub-project was identified during PPTA through officials from relevant organizations. Particular attention was paid to the data and recommendations contained in the PPTA reports, which are further reviewed, and sites verified in advance of progressing with detailed design and IEE study.

3.4 ENVIRONMENTAL CATEGORIZATION

41 The construction of the proposed works, as per ECA 1997 classification and ADB SPS 2009 categorization, falls in Bangladesh environmental category Orange-B and in ADB SPS category B. As a consequence of the construction of the proposed works, which entails construction of production tube wells, over head tank, pump houses, and water supply network and house connections to the existing houses. There is no problem due to land acquisition, rehabilitation and resettlement as the project will be on Government and pourashava land or along the roads for lying of water supply network. Besides, PTW location selected at Pumping station at proposed new bus terminal. The environmental issues related to construction are anticipated during construction phase. IEE has, hence, been conducted following ECA, Bangladesh and ADB SPS 2009. The potential adverse environmental impacts are mainly related to the construction period, which can be minimized by the mitigating measures and by adopting environmentally sound engineering and construction practices as referred to in the Environmental Management Plan (EMP).

3.5 PROJECT DETAILS

42 Kalapara Pourashava is having inadequate water supply. Due to non-availability of adequate water supply, the houses are not connected to piped water supply. In order to meet the increasing demand, two aquifers have been identified new bus terminal for digging the tube well. There is a need to design these aquifers as climate resilient and usable throughout various seasons of the year. The climate change adaptation shall also be incorporated in finalizing the water demand. The OHT shall meet the design requirements of surge impacts.

3.5.1 Objective of the Project

43 Prime objectives of the project have been to improve water supply infrastructure with a view to supporting social, economic and climate resilient development of the project area. Project development will facilitate economic growth and improved health services and development of ancillary water based industries. Specifically, the major purpose of the proposed water supply infrastructure has been to meet the increasing demand in Kalapara Pourashava toward meeting the following objectives:

 Promoting socio-economic development in the project area by providing house connection in the town area;  Increasing climate resilience in infrastructure;  Ensuring enhanced water supply networks to facilitate drinking, commercial activities of urban and rural households; and  Facilitating improved access to services toward reducing poverty and better health.

3.6 ANALYSIS OF ALTERNATIVES

44 Various options were explored during the IEE stage of the proposed installation/construction /improvement project and were weighed from all considerations such as cost, environment, and ease of implementation and maximum utilization of available infrastructure. The aim of alternative analysis has been to arrive at a development option, which maximizes the benefits while minimizing the adverse impacts. The two alternatives were considered “No Project Scenario” and “With Project Scenario”.

Package: CTEIP/KAL/WS/01: IEE 16

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

3.6.1 Without Project Alternative

45 The „No Project Option‟ in respect to the proposed project implies that the status quo is maintained. This option may be suitable alternative from an environmental perspective as it ensures non-interference with the existing environmental conditions. This option will however, involve several losses on socioeconomic condition both to the local population and the nation as a whole. The local population will continue to face the constraints they are currently experiencing due to inefficient water supply network and system and the anticipated economic development aimed at fulfilling the infrastructure gap remain unattainable. The „No Project Option‟ is the least preferred from the socio- economic and partly environmental perspective due to the following factors:

 The socio economic and water borne diseases health status of the Kalapara residents would remain unchanged;  The local skills such as planner, plumbing and construction would remain under-utilized as no employment opportunities will be created for local population who would have otherwise worked at the project area;  Reduced business development due to current bad condition of the water development project;  Opportunity to exploit tourism will not change; and  No project scenario case will also avoid social impacts due to the implementation of the project.

3.6.2 With Project Alternative

46 Implementation of the project will contribute to socioeconomic and health improvement and will have positive impacts on residents‟ life quality. The „With Project Alternative‟ has the following advantages:

 There will be improved and assured water supply facilities to the residents of the Kalapara Pourashava.  Water development will stimulate socio-economic development of the area. The inadequate water supply is major deterrent to growth in the area. The project scenario will catalyse commercial growth in various centres of the respective locality and will facilitate better business opportunities for local people.  Water improved infrastructure will also result in savings on health facilities due to water borne disease.  The project will provide potable water at required pressure and quantity. This alternative will have negative impact on land use, trees, noise and air qualities during construction phases.

3.7 QUANTITY OF CONSTRUCTION MATERIAL

47 The Kalapara water supply sub-project proposes the construction of tube-well, over head water tank, pump house, distribution network and house connection. The design report summarizes the quantities of construction material3. These have been further utilized in assessing the environmental impact due to development of water supply sub-project. The quantity of material is summarized in Table 8.

3Source: Detailed Engineering Design of water supply in Amtali Pourashava; District- Barguna, March 2015; LGED

Package: CTEIP/KAL/WS/01: IEE 17

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Table 8: Quantity of Construction Material

Sl. Description Unit Quantity No. 1 Tube well i) Digging, putting casing in well, Installation, operation, production and testing for Test Tube Well Nos 1.0 ii) Digging, putting casing in well, Installation, operation, production and testing for Production Tube Nos 1.0 Well 2 Over Head Water Tank i) Over Head Water Tank No 1.0 3 Pipeline i) Water Supply Network (New) km 25.5 .00 ii) Replacement of Existing Pipeline km 3.1 iii) Service Connection (New) Nos 1800 iv) Service Connection (Replaced) Nos 500 4 Pump House i) Pump Motor Set (Submersible) Nos 1.0 ii) Boundary Wall of Pumping Station LS 1.0 5 O & M Tools i) O&M Tools Set 1.0 6 Electro/Mechanical Works i) Electrical Connections inside Pump House Nos 1.0 ii) Generator Set Nos 1.0

Package: CTEIP/KAL/WS/01: IEE 18

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

3.8 CONSTRUCTION SCHEDULE

48 Construction schedule of water supply depends on the methodology adopted for construction. In general the time period will also depend on the resources put in place by the contractor. Designs have been finalized in February 2016. The package for the construction of the Kalapara water supply is proposed to be implemented by post-qualified contractors under a single envelope single stage bidding process through National Competitive Bidding (NCB) procedures. The water supply project may take about 18 months for construction. A Typical Construction Schedule is shown in Figure 3 including pre-construction and post construction activities. The post construction will also include defect liability period of 12 months.

Figure 3: Typical Construction Schedule Duration In Months Pre- Construction Post Activity construction Construction

0-2 3-4 5-6 7-9 10-12 13-15 16-18 19-21 22-24 25-36 Detailed Field Investigation, Topographical Surveys and Geo- Technical Investigations Detail designs, Bill of Quantities (BOQ) and Tender documents Notice inviting Tender, Tender process evaluation & award Mobilization, Preliminary works (site office, site clearing, identification of material collection site) 1 Picking up Material (bricks, pipes, sand, cement and gravel) 2 Digging of Tube-wells, Testing and Commissioning 3 Construction of Over Head Water Tank 4 Excavation of Tranches for laying of Pipes and Construction Sub Base for laying of pipes 5 House Connection 6 Testing, Commissioning, Monitoring and Evaluation Defect liability Period Defect liability Period 3.9 COST OF ENVIRONMENTAL MITIGATION MEASURES & MONITORING

49 The project components are Production TW, OHT, Pipeline, Pump Houses including supply of O & M tools and supply, fitting, fixing and commissioning of electro-mechanical works. The contract is designated as CTEIP/KAL/WS/01. This Appendix A: IEE is to be read in conjunction with the attached Appendix B: EMP, which gives a detailed breakdown of the costs for the Environmental Management and Monitoring, which are also referred in the attached Bill of Quantities.

Package: CTEIP/KAL/WS/01: IEE 19

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

4. ENVIRONMENTAL BASELINES

4.1 METHODOLOGY USED FOR THE BASELINE STUDY

50 Data for this study has been primarily collected through comprehensive literature survey, discussion with stakeholder agencies, and field visits to the proposed subproject sites. The literature survey broadly covered the following: (i) Sub-project details, reports, maps, and other documents available with the ADB CDTA PPTA and DDS consultants, LGED, and Kalapara Pourashava; (ii) relevant acts and extraordinary gazettes, and guidelines issued by Government of Bangladesh; and (iii) Literature on land use, soil, geology, hydrology, climate, socio-economic profiles, and environmental planning documents collected from Government of Bangladesh‟s agencies and websites.

51 Visits were undertaken to the subproject sites toward assessing the existing environment (physical, biological, and socioeconomic) and gathering information in respect of the proposed sites and scale of the proposed subproject. A separate socio-economic study was conducted to determine the demographic information, archaeological and religious places, densely populated pockets, and settlements.

52 Data were collected during the above site visits and were analyzed based upon which interpretations were made to assess the physical, biological, and socio-economic features of the project area. The relevant information is presented in the succeeding paragraphs.

4.2 PHYSICAL CHARACTERISTICS

53 Topography: Kalapara has a flat topography with minimum and maximum ground level varying between 1.5m and 4.86 m and average elevation of about 2.43m. It is greatly influenced by the river network and canals. At present the Pourashava is connected with the whole of the country both by roads and waterways. Besides, the Sundarbans, the world heritage is located close to Kalapara which has important socio-economic impact on the area and the southernmost area of Kalapara Upazila is open to Bay of Bengal and the pourashava is endowed with a sea resort, the sea-beach which distinctly indicates as the future potential passage for export and import business and tourism industry through the Pourashava. On the other hand, northern, eastern and western region of Bangladesh including the capital, Dhaka are inter connected with the Kalapara Pourashava. It is well defined that the linkage and connectivity of the Pourashava in the national context will further increase with the gradual implementation of the projected development plan.

54 Rainfall and Temperature: The annual rainfall in Kalapara was between 1,907 mm to 3,514 mm in year 1990 to 2010 with average rainfall of 2,567 mm. The decadal average increase in rainfall is about 22%. The seasonal distribution shows that most of the rainfall occurs in monsoon season between 1032 mm to 2,179 mm per year with average of monsoon months as 1,576 mm/ year between May and September which is 62% of annual rainfall. Monsoon rainfall is increasing about 38% per decade. Rainfall exhibits increasing trend in all seasons. In view of past trends the rainfall is likely to increase about 16% from the 2010 level. The annual and monsoon projections for rainfall are 14.86 to 19 % and 22.3 to 24.7 % respectively for the year 2050 from the base year 2000. The country average minimum and maximum temperature shows increasing trends. The analysis has indicated that the minimum temperature is increasing at the rate of .00580C/year and maximum temperature 0.00250C/year. The minimum and maximum temperature in town is also increasing by 0.07-0.15 and 0.07-0.38 0C/decade respectively. The annual increase is in temperature is anticipated between 1.98-2.35 0C in 2050.

Package: CTEIP/KAL/WS/01: IEE 20

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

The Bangladesh delta has number of geological factors such as land subsidence and deposition. The studies have indicated subsidence and sedimentation rate around 3 mm/year. The analysis has indicated the net sea rise for Bangladesh between 29.4 cm to 39.4 cm in year 2050. Because of sea level rise the height of storm surge as well as tide level will increase. The climate change results are summarized in Table 9

Table 9: Projections Climate Change in Project Area in Years4

Year PPTA (ADB)5 Sea level Rise Temperature Change in (cm) Rise (0C) Rainfall (%) 2010 3.5-5.5 0.49-0.51 3.6-3.8 2030 15-21 1.38-1.42 13.5-18.7 2050 29-39 1.98-2.35 22.3-24.7

The tropical cyclones will increase with the increase in sea surface temperature. World Bank (2010) study has indicated 5 severe cyclones hit Bangladesh coast since 1995. Last decades (1990-2010) witnessed 7 intensive cyclones. In addition PPTA report has indicated the probability of higher category cyclones. The Category -0 (cyclonic storms of low intensity; 62-117 km/hr) occurs once in two years. Tropical cyclones of Category-1 (118-153 km/hr), Category-2 (154-177 km/hr) and Category-3 (178-251 km/hr) has the probability of 0.52 which means that Bangladesh is hit on an average by One (1) cyclone every two years. The category-4 (209-251 km/hr) cyclone is a 12.5 year event, while category-5 (above 251 km/hr) cyclone is 50 years event. Available data indicates storm surge height varied from 4.5 to 9.6 m high at the sea cost. The building code has recommended the use 6.2 to 7.2 m at landfall point. The dampening of surge from land fall point is taken 1.0 m per 3 km length. Maximum evaporation in Bangladesh occurs during the summer months (March to May), the highest evaporation generally occurs during April. The mean monthly evaporation varies from the minimum of 51 mm in winter to a maximum of 183 mm in summer. The average increase in the post-monsoon and winter months is about 6.5%. The rate of evaporation in the eastern part is generally lower than in the western and northern-western parts. Humidity ranges between 60% in the dry season and 98% during the monsoon. There are reports that the evaporation rate has decreased in Bangladesh except the months of October to February, when the evaporation has increased. The reduction in sunshine duration is attributed to be the principal reason for such a decrease in evaporation. The decrease is higher in pre-monsoon summer months of March to May. The average decrease during this period is about 15%. These findings indicate that demand will actually decreased, rather than increased which is generally thought, due to climate change. Hence no increase in water demand is anticipated due to evaporation.

55 Hydrology: The Pourashava suffers from both internal and external flooding due to periodic tidal surges and seasonal monsoon storm events. Internal flood mainly occurs due to localized storm rainfall. Due to inadequate drainage system, it has become very hard to manage local storm water during heavy rain period and causes internal flood. External flood is likely to occur as the area is situated in the tidal zone which causes mainly due to the storm surges. Floods are naturally occurred

4TA 8128 BAN (PPTA): Preparing Coastal Towns Infrastructure Improvement Project : Final Report Annex- Climate Change Assessment and Adaptation Strategy 5TA 8128 BAN (PPTA): Preparing Coastal Towns Infrastructure Improvement Project : Final Report Annex- Climate Change Assessment and Adaptation Strategy

Package: CTEIP/KAL/WS/01: IEE 21

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

in every rainy season. Flood mainly occurs during May to November. Ward no. 1, 8 and 9 have low contour spot height which is more vulnerable to flood hazard.

Water Logging is common throughout Kalapara, which results from man-made and natural causes. High volume of rainfall and poor drainage system are most important causes of water logging. The depth of maximum internal inundation ranges from 3 ft to 4 ft but it does not stay for more time. The Andharmanik River of Kalapara Pourashava is moderately stable and river erosion rate is moderate.

56 Drainage and Flood Control: About 46.25.5 km of drainage network exist in the Kalapara Pourashava and about 56% of the households have no access to planned drainage facilities. The drainage network of the Pourashava consists of both natural and man-made drainage. Most of the drains are open and natural. Besides, the man-made drainage network includes both Pucca and Katcha. Natural drainage network includes 31 khals, 1 River, 59 Ditches and 694 Pond etc, which drain out or sometimes store not only waste water but also storm water. Especially, the khals play vital roles to drain out the storm water. During high tide or Cyclone these khals act as the natural bless to the Pourashava people. The man-made drainage network consists of Pucca and Katcha drains. In Pourashava area, about 83% drains are primary and natural, which is followed by 17% tertiary drains. The pucca and katcha drain coverage in the Pourashava area is about 7 km and 6 km respectively. Additionally, width of drains varies between 0.5-1.12 m and depth of drains varies between 0.45-1.4 m.

Kalapara Pourashava has one embankment which is mainly used as primary road. The embankment is about 3.25.5 km long, 11.52 m wide and 3 m high. LGED is the construction and maintenance authority. The embankment is Pucca, its present condition is good and is regularly maintained. There are 3 sluice gates in the Pourashava. BWDB is the main construction and maintenance authority of the sluice gates. The major outfalls are River and the surrounding Khals which are connected to the River including low lying areas.

However, the congestion of drainage and water is a common scenario in Kalapara Pourashava because of uncontrolled and haphazard disposal of solid waste and garbage into drains, lack of purposive utilization of sluice gates connecting canals and river, illegal connection of latrines to the drains, absence of adequate road-side drains, lack of secondary drains, missing links in drainage network, very low drainage coverage in some wards, low elevation and lack of proper slop of drains, lack of proper and adequate maintenance of drains, and lack of proper dumping site.

57 Ambient Air Quality: Air pollution mainly occurs from locally established industries, which have been identified as a key source of air pollution. Wood based industries are prevalent in Kalapara Pourashava. There is no heavy industry in the area but there are several small and medium industries which are used for different industrial purpose such as manufactories, flour mills, rice mills, ice mills, saw mills, goldsmith, blacksmith, wood works, etc. These industries create sound and noise and pollute water and air. Besides, a number of heavy and small motorized vehicles move through the roads and extract some pollutant particle and emissions that also cause air pollution in and around stoppages and market areas.

58 Ambient Noise: Noise pollution is a minor phenomenon in Kalapara Pourashava. However, such type of pollution problem is mainly occurring from the road vehicles. But it has been identified that this is not a major problem for all over the Pourashava. It is mainly a problem to the road side residents, not to all over the Pourashava.

59 Groundwater Quality and Availability: Hydro-geological investigation in Kalapara Pourashava carried out under DPHE project shows availability of groundwater in sufficient quantity within the area. The WHO recommended the value of arsenic contamination in water is 0.01 mg/l, while the maximum permissible limit for Bangladesh and India has been fixed at 0.05 mg/l. The level of arsenic contamination in Kalapara Pourashava is not at alarming level. According to DPHE (2009), the value of

Package: CTEIP/KAL/WS/01: IEE 22

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

arsenic contamination found in Kalapara is less than 0.01 mg/l. This area may be considered as completely safe from arsenic pollution.

4.3 BIOLOGICAL CHARACTERISTICS

60 Kalapara Pourashava location is mainly devoid of vegetation other than nominal roadside trees, with some secondary growth trees and shrubs. There are no forests along the proposed route to and from the water supply sites. There are no national parks or sanctuaries. There are also no rare or endangered species reported. There is no evidence of wildlife of the higher species within the urban location. There are no sensitive habitats in the areas of the proposed water supply sites.

4.4 ECONOMIC DEVELOPMENT

61 The Pourashava has insufficient capacity and resources and is finding it difficult to respond to the need for forward planning and investment in basic urban infrastructure and services. This undercuts sustainable local urban governance, makes local planning ineffective and undermines local economic development. The impact of climate change further exacerbates the weaknesses in municipal management more generally.

4.5 SOCIO-ECONOMIC CHARACTERISTICS a) Population 57 Information on population and number of households with average size of Kalapara Pourashava is presented in

Table:10 Kalapara Pourashava population in Information

Population Total Population Projection of Area (Acre) Kalapara 2011 2015 2020 2025 2030 Pourashava

Ward No-01 297.66 3319 3539 3835 4156 4504

Ward No-02 57.27 1501 1601 1735 1880 2037

Ward No-03 73.05 1681 1793 1943 2105 2281

Ward No-04 38.8 1331 1419 1538 1667 1806

Ward No-05 57.56 1193 1272 1379 1494 1619

Ward No-06 36.65 1662 1772 1921 2081 2255

Ward No-07 59.04 1347 1436 1557 1687 1828

Ward No-08 94.65 1824 1945 2108 2284 2475

Ward No-09 229.87 3474 3705 4015 4350 4714

Total 944.56 17332 18483 20029 21705 25.5521

Source: BBS Housing Census Report, 2011. b) Land Use 63 Kalapara Pourashava is comprised of various categories of land, where prominent land use categories are residential, water bodies and agricultural. Residential land use (about 42% of the total)

Package: CTEIP/KAL/WS/01: IEE 23

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

followed by agricultural land (about 22%) and water body land use (about 19%). Basing on the percentage of land under different use categories the ranking is: Residential (42.20%), Agriculture (21.58%), Water bodies (18.88%), Urban Green Space (5.08%), Circulation Network (3.26%), Commercial (2.34%), Government Services (1.82%), Industrial/Processing and Manufacturing (1.77%), Education and Research (1.41%), Community Services (1.09%), Health Facility (0.21%), Restricted area (0.14%), Transport & Communication (0.08%), Non-Government Services (0.05%) and Mixed Use (0.05%), and Recreational Facility (0.04%). c) Socio-economic Status 64 About 18% of the respondents are engaged in business activities. The scenario reveals that there are significant numbers of respondents who are engaged as small businessman, while 10% service holders both government and semi-government including employees in private offices. The unskilled labors are rickshaw and van pullers accounts for 0.7% of the total occupation group in the study area. Only 3.6% is unemployed.

d) Historical, Cultural and Archaeological Characteristics 65 The subproject components are not immediately located near historical, cultural and archaeological sites, no excavation works will be conducted in the vicinities of such sites. There are no other scheduled or unscheduled archaeological, paleontological, or architectural sites of heritage listed by local and/or national authority.

Package: CTEIP/KAL/WS/01: IEE 24

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

5. POTENTIAL ENVIRONMENTAL IMPACTS

5.1 METHODOLOGY

67 Issues for consideration have been raised by the following means: (i) input from interested and affected parties; (ii) desktop research of information relevant to the proposed subproject; (iii) site visits; and (iv) evaluation of proposed design scope and potential impacts. Categorization of the subproject and formulation of mitigation measures have been guided by ADB‟s REA Checklist for water supply and ADB SPS 2009.

68 The subproject will not have major negative impacts because activities will be localized/site- specific and short in duration, corridors of impact will be on existing public ROWs, and construction will be conducted within a relatively small area. Because of these there are several aspects of the environment that are not expected to be significantly affected (Table 11).

69 Refer to the guidelines detailed in the Traffic Management Plan (TMP) given in Annexure I of the Environmental Management Plan (EMP), whereby the Contractor shall prepare and submit for approval from the Employer, details of all required mitigate measures, associated with vehicular and pedestrian road-user issues, during any possible closure and/or infringement to road access through the course of implementation.

Table 11: Environmental Attributes Not Expected to have Significant Impacts

Environmental Attribute Rationale

A. Physical Characteristics

Topography, landforms, Required amount of materials will not cause alteration of topography, landforms, geology and Soils geology and soils. Erosion hazard is insignificant, as trenching and excavation works will be conducted only during construction stage (short-term) and specific to sites along public roads.

Climatic conditions Short-term production of dust is the only effect on atmosphere. However, impact is short-term, site-specific and within a relatively small area. There are well- developed methods for mitigation.

Water quality Trenching and excavation, run-off from stockpiled materials, and chemical contamination from fuels and lubricants may result to silt-laden runoff during rainfall, which may cause siltation and reduction in the quality of adjacent bodies of water. However, impact is short-term, site-specific and within a relatively small area. There are well-developed methods for mitigation.

Air quality Conducting works at dry season and moving large quantity of materials may create dusts and increase in concentration of vehicle-related pollutants (such as carbon monoxide, sulphur oxides, particulate matter, nitrous oxides, and hydrocarbons) which will affect people who live and work near the sites. However, impact is short-term, site-specific and within a relatively small area. There are well-developed methods for mitigation.

Acoustic environment Construction activities will be on settlements, along and near schools, and areas with small-scale businesses. Temporary increase in noise level and vibrations may be caused by excavation equipment, and the transportation of equipment, materials, and people. However, the proposed subproject will follow existing ROW alignment and impact is short-term, site-specific and within relatively small area. There are well-developed methods for mitigation.

B. Biological Characteristics Biodiversity Activities being located in the built-up area of Kalapara Pourashava will not cause direct impact on biodiversity values. The construction activities do not anticipate any cutting of trees. C. Socioeconomic Characteristics

Package: CTEIP/KAL/WS/01: IEE 25

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Environmental Attribute Rationale

Land use No alteration on land use. Lying of water pipes will be along the road. Type of community spread No alteration on type of community spread.

Existing provisions for Road closure is not anticipated. Hauling of construction materials and operation pedestrians/ Transport of equipment on-site can cause traffic problems. However, the proposed subproject will follow existing road alignment and impact is short-term, site- specific and within a relatively small area. There are well developed methods for mitigation. Socio-economic status Subproject components will be located in government land and on along the existing roads thus there is no requirement for land acquisition or any resettlements. Manpower will be required during the 24-monthsconstruction stage. This can result to generation of contractual employment and increase in local revenue. Thus potential impact is positive and long-term. Impact on People Although construction of subproject components involves quite simple techniques of civil work, the invasive nature of excavation and the subproject sites being in built-up areas of Kalapara Pourashava where there are a variety of human activities, will result to impacts to the sensitive receptors such as residents, businesses, and the community in general. These anticipated impacts are temporary and for short duration. D. Historical, Cultural, and Archaeological Characteristics Physical and cultural The subproject components are not located in or near and excavation works will heritage not be conducted in the vicinities of identified historical and sites.

5.2 POSITIVES IMPACTS

70 Based on project particulars Chapter 3 and the existing environmental conditions Chapter 4 potential positive impacts have been identified that are likely to result from the proposed project and wherever possible these have been quantified. Positive impacts have been identified for different phases of project cycle and discussed in the following sections.

5.2.1 Impact during Planning and Design Phase

71 Employment opportunities: During the planning and design period, new jobs will be created for the skilled and unskilled manpower in the community to conduct topographical and geological investigations. In addition employment will also be generated for planning and design of infrastructure. Women will also have equally an opportunity to secure employment.

72 Skills transfer: The international consultant will associate with local partners. In the process of planning and design the local technical manpower will work with the international experts. This process of working together will transfer design and planning tools, computer design software and other useful guideline to local counterpart working for the project.

73 Training: The international consultant will provide training to local counter parts for activities likely to be implemented during planning and construction phases. This training and trained manpower will go a long way in meeting the requirements of the country in the infrastructure sector and water supply sub-sectoring particular.

5.2.2 Impacts during Construction Phase

74 Employment Opportunities: During the construction phase it is estimated that around 100 people will be working as labor both skilled and unskilled. A majority of unskilled labor will be sourced from the local residents and hence this will create an employment. In addition new jobs will be created in the Government to implement, monitoring and evaluation of the project. Women will also have an opportunity to secure employment.

Package: CTEIP/KAL/WS/01: IEE 26

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

75 Enhanced Social Interaction: The National and International; local and regional manpower will be working together for the project. This interaction will enhance social interaction between the people of two different places and levels.

76 Boost to Industrial Activities: During construction country made product will be utilized such as cement, gravel, steel, pipes, pump and motor etc. The consumption of these will give boost to industrial production of material manufacturing organization. In addition, the transport sector will be benefited for transport of material from manufacturing site to construction site. This will provide direct and indirect employment.

77 Water and Health: The availability of potable water will reduce the water borne disease and hence there will be a positive impact on the health of people which in turn will reduce the load on hospitals.

78 Reduction in Fuel Consumption and Greenhouse Gases: The pumps and motors will be operated on electricity which will reduce the impact on fuel consumption and subsequently the green house gases locally as the electricity is generated at other places which will have positive impact locally and regionally.

5.2.3 Impacts during Project Operation

79 The proposed works will play an important role in its post construction period. It will ensure adequate supply of water at required pressure, quantity and round the clock. This will add directly to working hours for other productivity activities and will add to GDP.

5.3 NEGATIVE IMPACTS

80 Impacts on environmental component due to project activities, during different phases of project cycles, are summarized in Table 11. Mostly the impacts during project construction have been considered and reported.

5.3.1. Impact during Planning Phase

81 Change of Land Use due to Proposed Laying of Pipelines/Borrow/Quarry Areas: The details on earth work, reinforced cement concrete and brick work etc are summarized in Table 12. It is anticipate that about 2,597.1 cum of construction spoils will be generated which has to be disposed in scientific manner.

Table 12: Construction Material and Construction Spoils Sl. No. Construction Material Quantity of Material (M3) Construction Spoils (M3) 1 Earth Work 18182 1818.2 2 Brick Work 197 19.7 3 Reinforced Cement Concrete 875 87.5 4 Sand in Cushioning 6717 671.7

If a depth of 1.0 m is taken for quarry/mining, the land required for brick and sand activities will be 0.014 ha for borrow areas. This area need to be identified in the vicinity of proposed site to avoid transport problems. Emphasis should be laid on maximum use of the stripped top soil in refilling, redevelopment of borrow areas and additional landscape works in the project. Excavations of earth from borrow areas may also lead to loss of topsoil and soil erosion problem during rains. That is why; the whole balk of soil required for construction work will be brought from outside of the Pourashava area.

Package: CTEIP/KAL/WS/01: IEE 27

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

5.3.2. Impact during Construction Phase

82 Soil Loss: The soil loss will be in terms of top soil erosion from right of way, borrow pits, quarries, and storage of material areas. Erosion is of relevance to slope stability, which is a level topography. The construction will be completed in 18 months. Excavated earth material will be reused in the road construction or will be used to fill the low laying areas hence its disposal is not likely to have impact on the environment. Besides, the whole balk of soil further required for construction work will be brought from outside of the Pourashava area. To prevent the soil erosion, monsoon season work is likely to be stopped. During the construction, vegetation will need to be cleared within the proposed RoW, which may pose some soil erosion problem during first few rains. Embankment/slopes near newly constructed culverts and structures may be prone to the soil erosion. Such embankment and slops will need to be stabilized as soon as construction is over. The impact of soil loss is of short duration and will be reversible.

83 Soil Pollution: The soil pollution will be due to first stripping of soil which is rich in carbon to nitrogen ratio being 13.8 to 18.2; secondly due to improper disposal of waste material on the open ground. The waste likely to fall on the ground may be solid waste / liquid waste form labour camps. Soil pollution may also be due to spillage of oil and grease by construction machinery and equipment. Appropriate waste disposal methods have to be adopted. Proper care should be taken while locating the above utilities / facilities so as to minimize the soil pollution. The impacts are of short duration and will be reversible.

84 Disruption in Drainage Pattern: The water supply pipes will cover over 25.5 km. The water pipes that intersect drainage basins generally modify the natural flow of surface water by concentrating the flow to certain points and increasing the velocity of flow. Depending upon the flow, these changes can contribute to flooding, soil erosion, channel modification, siltation of streams etc. These effects are often felt well beyond the immediate vicinity of the site. Being the existing alignment getting modified by upgrading/constructing along the existing road alignment; hence no change in drainage pattern is anticipated due to the project.

85 Water Pollution: Surface water bodies such as canal and ponds may get polluted due to the boring operation of tube-well. The construction and lying of pipes will excavate soil which may join the runoff during monsoon and may pollute water bodies. Contamination of water bodies may result due to spilling of construction materials, oils and greases and paint during transportation and at the equipment yards. But the quantity of such spills will be negligible. Care however, needs to be taken to provide adequate sanitary facilities and drainage in the temporary colonies of the construction workers. Provision of adequate washing and toilet facilities with septic tanks and soak pit appropriate refuse collection and disposal system should be made obligatory. Water pollution impacts on surface water quality during construction will be low, spatially restricted and very short term and reversible.

86 Increased Water Demand: The water requirement will be increased during construction phase. Around 100 are estimated during peak period. The peak demand is estimated about 28 KL/day. In addition, water will be required for construction purpose. All these activities shall have to be located within the vicinity of the project site during construction phase, hence proper care have to be taken while deciding the location of these activities. Identification of suitable locations shall have to be carried out based on water availability in order to safeguard the nearby environment. Water sources and quality, including surface water, is likely to be impacted due to construction activities such as setting up of workers camp, transportation and storage of construction material.

87 Health Risks due to Waste Disposal: Health risks include disease hazards due to lack of sanitation facilities (water supply and human waste disposal) to the workers during construction both at construction site and at Contractor‟s camp. Unscientific disposal of waste from contractor‟s camp can lead to contamination of both ground and surface water. This could lead to outbreak of water borne disease such as diarrhoea, dysentery, typhoid etc. The solid waste generated (about 20 kg/day) in contractor‟s camp if not treated properly may cause leaching and environmental pollution. Management measures include proper sanitation, health care, and solid waste disposal facilities. In addition to these, efforts need to be made to avoid water spills, adopt disease control measures. The impact will be of short duration and reversible.

Package: CTEIP/KAL/WS/01: IEE 28

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Table13: Impact Matrix of Potential Environmental Impacts

Project Activity Pre- construction Construction Phase Operation Phase Component Phase Affected Vehicles & Removing Construction/m Land Site Contractor Machines Construction trees and Quarries odification of Operation Demarcation clearance camps operation Machinery vegetation Roads &maintenance Soil Loss of land Loss of Soils Erosion and Contamination Contamination Increase in Soil pollution Pollution due to Soil contamination loss of top soil from wastes by fuel and erosion, from Construction spills due to surface lubricants siltation and Spoils runoff Compaction of slope soil instability Ground Water Evaporation Water extraction Water extraction Exploitation of Maintenance of for drinking and for cleaning water for trees /shrubs other purposes construction Surface water Loss of water Change in Siltation Torrent Pollution from Contamination Water Change in water Pollution due to Degradation due body water quality runoff sanitary & other by fuel & logging and quality and spill into water to spills &more wastes lubricants mosquito reduction of GW bodies sewage flow breeding recharge Drainage Change in Change in Change in Change in Change in Interference with Cleaning & natural natural drainage drainage pattern natural drainage drainage natural drainage maintenance drainage pattern due to disposal of pattern due to pattern and water logging pattern wastes on soils spills

Air Quality Increase in Reduced Pollution due to Dust & air Dust Dust pollution SPM, SO2 Increase in SPM, SPM buffering of air fuel burning pollution pollution and odour SO2 and NOX pollution, problems change in climate Noise Quality Increase in Reduced Increase in Vibration Vibrators, mixing Increase in Noise Increase in noise Noise level buffering of Noise level from plant noise etc. levels due to Noise operation increased in Machinery.

Package: CTEIP/KAL/WS/01: IEE 29

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Project Activity Pre- construction Construction Phase Operation Phase Component Phase Affected Vehicles & Removing Construction/m Land Site Contractor Machines Construction trees and Quarries odification of Operation Demarcation clearance camps operation Machinery vegetation Roads &maintenance Flora & Fauna Impact on Loss of trees Cutting of trees Disturbance to Fishery due to for fuel burning Flora and fauna pollution Socio- Loss of Trees Transmission of economic Disease Loss to Utilities Re-placement of telephone lines

Package: CTEIP/KAL/WS/01: IEE 30

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

88 Pollution at Construction Site: Construction materials will be required for the construction of tube-well, lying of water pipeline, construction of over head water tank etc. About 10-15% of the construction material is left behind by the contractor as construction waste / spoils. The material required for construction which will leave construction spoils is estimated 2597.1m3. Dumping of construction waste / spoil in haphazard manner may cause surface and ground water pollution near the construction sites and breeding site for mosquitoes, hence, it is proposed to clean the area and dump/dispose the construction spoils at the dumping site specified by the local authority to avoid any adverse impact on health and well-being of people.

89 Air Pollution: The impact on air environmental is a factor of type of vehicle, fuel used and its capacity. The consultant has taken emission factor to estimate the pollution potential on air environment during construction. The material will be transported by canal route and hence the impact on air environment will be insignificant. In the construction phase, air quality impacts are of short duration. The most important pollutant during this phase will be suspended particulate matter. Such deterioration of air quality can be assigned to:

 Fugitive dust emission from construction activities like excavation, back-filling and concreting;  Hauling and dumping of earth & construction spoils;  Vehicular movement along the feeder roads or temporary diversions.  Gaseous emission from construction equipment and vehicular traffic.

Impacts on air quality will be low and spatially restricted along the immediate site of construction. The above will be operated at different location the impact at a particular site will be insignificant.

90 Noise Levels: The magnitude of impact during the construction phase will depend upon the types of the equipment used, the construction methods employed and the scheduling of the work. Noise associated with construction of water supply development affects the environment through which system is laid. The noise pollution may be due to four main sources: a) vehicles due to engine and friction between vehicles and the road surface; and b) operation of construction machinery activity. Water supply construction and maintenance generally require the use of heavy machinery, and although these activities may be intermittent and localized, they nevertheless contribute sustained noise during equipment operation. Construction activities are expected to produce noise levels in the range of 80-85 dB (A) at 15 m distance which will decrease with increase in distance. Noise due construction machinery is predicted as presented in Table 11. The noise levels will be with a limit of 55-65 dB (A) at a distance of 100-125 m from construction site. The expected noise levels due to operation of construction machinery at site are summarized in Table 12. Table 14: Noise Levels during Construction, dB(A)

Excavation Excavation Source Dump Truck Compactor Dozer by Shovel by caterpillar Noise Level dB(A) 83 81 85 87 87 Source Distance (m) 15 15 15 15 15 Noise Levels at Distance (m) from source 20 78.5 76.5 80.5 82.5 82.5 25 76.1 74.1 78.1 80.1 80.1 30 74.0 72.0 76.0 78.0 78.0 35 72.1 70.1 74.1 76.1 76.1 40 70.5 68.5 72.5 74.5 74.5 45 69.0 67.0 71.0 73.0 73.0 50 67.5 65.5 69.5 71.5 71.5 55 66.2 64.2 68.2 70.2 70.2 60 65.0 63.0 67.0 69.0 69.0

Package: CTEIP/KAL/WS/01: IEE 31

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Excavation Excavation Source Dump Truck Compactor Dozer by Shovel by caterpillar 75 61.5 59.5 63.5 65.5 65.5 100 56.5 54.5 58.5 60.5 60.5 125 54.6 52.6 56.6 58.6 58.6 150 53.0 51.0 55.0 57.0 57.0 175 51.7 49.7 53.7 55.7 55.7 200 50.5 48.5 52.5 54.5 54.5 225 49.5 47.5 51.5 53.5 53.5 250 48.6 46.6 50.6 52.6 52.6

Table 15: Noise Due to Construction Machinery

Sl. No. Machine Operation Noise In dB(A) 1. Dump Truck Haul 83 2. Compactor Fill 81 3. Dozer Fill 85 4. Excavation by Shovel Cut 87 5. Excavation by Caterpillar Cut 87

5.3.3 Impact during Operation Phase

91 Water Pollution: The increase in water supply will increase the sewage/wastewater effluent. The extent of water pollution will depend upon i) the rate of water supply and ii) the prevailing treatment facilities. About 80% of water supply will come in the form of wastewater. Hence it is proposed that Pourashava and LGED should device the mechanism to treat the waste water likely to be generated due to increase in water supply.

92 Soil Pollution: The spill of oil, grease and other chemical/ material from machinery may pollute the soil and surface and ground water. Such spills shall be closely monitored.

93 Noise Levels: During the operation phase of the water supply, the source of noise will be operating pump and pumping machinery. The day time noise levels may be of 55 dB (A).

5.4 IMPACTS ANALYSIS

94 Checklist is the list of environmental parameters or impact indicators, which the environmentalist is encouraged to consider when summarizing the potential impacts. A typical checklist identifying the anticipated environmental impacts due to the project activities are shown in Table 13. The impacts have been categorized and analyzed in the following manner: i) Nature (positive/negative, direct/indirect); ii) Magnitude (high, moderate, low); iii) Extent/location (area/volume covered, distribution); iv) Timing (during construction or operation, immediate; or delayed); v) Duration (short term/long term, intermittent/continuous); vi) Reversibility/irreversibility; vii) Likelihood (probability, uncertainty); and viii) Significance (local, regional, global)

Package: CTEIP/KAL/WS/01: IEE 32

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

5.5 CUMULATIVE IMPACT

95 The project has identified the valued components as acoustic environment, socioeconomic and socio-community components, and human health and safety. There are no foreseeable projects that will overlap with the subproject. The cumulative impact assessment examined the interaction between the subproject‟s residual effects (i.e., those effects that remain after mitigation measures have been applied) and those associated with other past, existing, and reasonably foreseeable future projects or activities. The interaction of residual effects associated with multiple projects and/or activities can result in cumulative impacts, both positive and negative. The project‟s potential cumulative effects were considered with respect to valued components in environmental and socioeconomic categories, in four areas:

(i) of any potential residual project effects that may occur incrementally over time; (ii) consideration of other known relevant projects or activities within the specified study area boundaries, even if not directly related to the project; (iii) potential overlapping impacts that may occur due to other developments, interventions, even if not directly related to the proposed subproject; and (iv) Future developments that are reasonably foreseeable and sufficiently certain to proceed.

Package: CTEIP/KAL/WS/01: IEE 33

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Package: CTEIP/KAL/WS/01: IEE 34

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Table 16: Impacts Analysis

S. No. Activity Potential Impact Nature Magnitude Extent/ Timing/ Phase Duration Reversible Likelihood Significance Location /Irreversible i) Planning and Design of Water Skill Transfer & Positive Low Medium Pre- Long Term Probable Regional Supply infrastructure Training Direct Construction ii) Disposal of waste material, Soil Pollution Negative Low Small area Construction Short Term Reversible Probable Local construction spoils, spill of oil Direct and grease from construction machinery. iii) Exposed surface due to Soil Loss/ Erosion Negative Low Small area Construction/ Short Term Reversible Probable Local excavation of trenches, borrow on site Direct Operation pits, quarries site construction Soil Loss from Negative Low Small area Construction Short Term Reversible Probable Local of cross drainage Borrow/Quarry Areas Direct iv) Vehicles Movement on Loss of soil fertility Negative Low Small area Construction Short Term Reversible Probable Local adjoining productive land Direct v) Construction of Over Head Change in Natural Negative Low Small area Construction Short Term Reversible Probable Local Water Tank, borrow areas and Drainage Pattern Direct quarry sites vi) Runoff from Trench, quarry Water Pollution Negative Low Small Construction Short Term Reversible Probable Local site and borrow areas Direct Distribution vii) Disposal of waste Health Risk Negative Low Low Construction Short Term Reversible Probable Local Direct viii) Use of water in Construction Increased Water Negative Low low Construction Short Term Reversible Probable Local and drinking Demands Direct ix) Increase in Wastewater Flow Water Pollution into Negative Medium low Construction/ Long Term Irreversible Probable Local and Disposal water bodies Direct Operation x) Historical Resources Loss of Physical No Impact Cultural Resources xi) Construction of Water Re location of Negative Low Less Construction Short Term Reversible Probable Local

Package: CTEIP/KAL/WS/01: IEE 35

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

S. No. Activity Potential Impact Nature Magnitude Extent/ Timing/ Phase Duration Reversible Likelihood Significance Location /Irreversible Distribution Network Telephone Wires. Direct xii) Movement of vehicles for Air Quality Negative Low low Construction/ Long Term Reversible Probable Regional construction works and then Direct Operation use of road Increase in Green Negative Low low Construction/ Long Term Reversible Probable Regional House Gases Direct Operation Fuel Consumption Negative Low low Construction/ Long Term Irreversible Probable Regional Direct/ Operation Indirect Noise Levels Negative Low low Construction/ Long Term Reversible Probable Regional Indirect Operation xiii) Construction and operation of Employment Positive Medium Large Construction/O Long Term Probable Regional Water Tube Well Opportunities Direct Distribution peration

Enhancement of Positive Medium Large Construction/O Long Term Permanent Probable Regional Rural Economy Direct Distribution peration xiv) Construction and operation of Increase in Water Positive Medium Permanent Operation Long Term Probable Regional Water Tube Well Availability Direct

Increase in Water Negative Medium Permanent Construction/ Long Term Probable Regional Pollution In/Direct Operation xv) Construction of Pump house, Skill Transfer and Positive Medium Permanent Construction/O Long Term Probable Regional Distribution Network, OHT, Training Direct peration Tube-well, House Connection r and Operation xvi) Construction Activities Workers Safety Negative Low Temporary Construction Short Term Reversible Probable Local xvii) Employment of outside labour Health Safety Negative Low Temporary/ Construction Short Term Reversible Probable Local (Transmission of Permanent STD, HIV/AIDS)

Package: CTEIP/KAL/WS/01: IEE 36

Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

6 GRIEVANCE REDRESS MECHANISM

96 Generally complaint procedures are developed for those who have been adversely affected by the Project infrastructure and/or have not been compensated as per law/ legal entitlement. In this case no land related dispute is applicable as the land is already owned by the authorities. A project-specific grievance redress mechanism (GRM) will be established to receive, evaluate, and facilitate the concerns, complaints, and grievances about the social and environmental performance at the level of the project. The GRM will aim to provide a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project. A common GRM will be in place for social, environmental, or any other grievances related to the project. GRM was discussed with stakeholders during field visits. The GRM will provide an accessible and trusted platform for receiving and facilitating grievances related to the project. The multi-tier GRM for the project is outlined below, each tier having time-bound schedules and with responsible persons identified to address grievances and seek appropriate persons‟ advice at each stage, as required.

97 Pourashava-wide public awareness campaigns will ensure that awareness on grievance redress procedures is generated through the campaign. The project implementation unit (PIU) safeguards assistant and institutional capacity and community development consultants (ICCDC) that will conduct Pourashava-wide awareness campaigns to ensure that poor and vulnerable households are made aware of grievance redress procedures and entitlements, and will work with the PIU safeguards assistant to help ensure that their grievances are addressed. Affected persons (APs) will have the flexibility of conveying grievances/suggestions by dropping grievance redress/ suggestion forms in complaints/suggestion boxes that have already been installed by project Pourashavas or through telephone hotlines at accessible locations, by e-mail, by post, or by writing in a complaints register in Pourashava offices.

98 The grievance registration form is available in Annexure II. Careful documentation of the name of the complainant, date of receipt of the complaint, address/contact details of the person, location of the problem area, and how the problem was resolved will be undertaken. The project management unit (PMU) safeguards officer will have the overall responsibility for timely grievance redressal on environmental and social safeguards issues and for registration of grievances, related disclosure, and communication with the aggrieved party through the PIU safeguards assistant.

99 Grievance Redress Process. In case of grievances that are immediate and urgent in the perception of the complainant, the contractor and supervision personnel from the project management and supervision consultants (PMSC) on-site will provide the most easily accessible or first level of contact for quick resolution of grievances. Contact phone numbers and names of the concerned PIU safeguards assistant, contractors, PMU safeguards officer, PMSC environmental and social safeguards specialists will be posted at all construction sites at visible locations.

1st Level Grievance. The contractors, PIU supervision personnel and PIU safeguards assistant can immediately resolve issues on-site in consultation with each other, and will be required to do so within 3 days of receipt of a complaint/grievance. Assistance of ward level coordination committees (WLCC) will be sought if required for resolution of the issue, by any one or all of them jointly.

2nd Level Grievance. All grievances that cannot be redressed within 3 days at field/ward level will be jointly reviewed by the grievance redress committee (GRC) at town-level and PIU safeguards assistant, who will attempt to resolve them within 7 days. The PIU safeguards assistant will be responsible to see through the process of redressal of each grievance.

3rd Level Grievance. The PIU safeguards assistant will refer any unresolved or major issues to the PMU safeguards officer and PMSC (third level of grievance redress), who will resolve them within 15 days.

4th Level Grievance. Very major issues that are beyond the jurisdictional authority of the GRC or those that have the potential to cause social conflicts or environmental damage or those that remain unresolved at PMU level, will be referred to the project steering committee (PSC) to be resolved within 14 days. All paperwork (details of grievances) needs to be completed by the PIU

Package: CTEIP/KAL/WS/01: IEE 37 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

safeguards assistant and circulated to the respective WLCC, GRC and PSC members at least a week in advance of the scheduled meetings. All decisions taken by the GRC and PSC will be communicated to the APs by the PIU safeguards assistant. Despite the project GRM, an aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM. In the event that the established GRM is not in a position to resolve the issue, the affected person also can use the ADB Accountability Mechanism (AM) through directly contacting (in writing) the Complaint Receiving Officer (CRO) at ADB headquarters or the ADB Bangladesh Resident Mission (BRM). The complaint can be submitted in any of the official languages of ADB‟s DMCs. The ADB Accountability Mechanism information will be included in the PID to be distributed to the affected communities, as part of the project GRM.

100 Grievance redress process can be diagrammatically represented as under (Figure 4).

Figure 4: Grievance Redress Process

Aggrieved Persons

FIELD/WARD LEVEL 3 days Grievance st 1 Level Contractor, PIU Days3 Redressed Supervision Personnel Grievance Days and PIU Safeguards Assistance of Assistants (to be assisted WLCCdays (as and by ICCDC) when required) Not redressed

nd 2 Level TOWN LEVEL 7 days Grievance Grievance PIU Safeguard Assistant Redressed and GRC

Not redressed

rd PMU LEVEL 3 Level 15 days Grievance Grievance PMU Safeguard Officer and PMSC Safeguard Redressed Specialists

Not redressed

th 4 Level PROJECT STEERING Grievance COMMITTEE

101 Records will be kept by PIU of all grievances received, including contact details of complainant, date the complaint was received, nature of grievance, agreed corrective actions and the date these were affected and final outcome. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PMU office, municipal office, and on the web, as well as reported in monitoring reports submitted to ADB on a semi-annual basis. All costs involved in resolving the complaints (meetings, consultations, communication and reporting/information dissemination) will be borne by the concerned PIU at town-level; while costs related to escalated grievances will be met by the PMU.

Package: CTEIP/KAL/WS/01: IEE 38 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

7 PUBLIC CONSULTATION

7.1 PUBLIC CONSULTATIONS AND PARTICIPATION

102 Public participation and community consultation has been taken up as an integral part of environmental assessment process of the project. Consultation was used as a tool to inform and educate stakeholders about the proposed action both before and after the development decisions were made. It assisted in identification of the impacts problems associated with the project as well as the needs of the Project Affected People (PAP). This participatory process helped in reducing public resistance to change and enabled participation of local people in decision making process. 103 Initial Public consultation has been carried out in the project area with the objectives of minimizing probable adverse impacts of the project and to achieve speedy implementation of the project through bringing in awareness among the community on the benefits of the project. As part of the project consultations, efforts were made to consult with the public as well as a number of local authorities, to determine their thoughts, opinions and feedback on the impact of the proposed Shelter in their respective locations. Information and comments collected from the public early in the study process were of use. 104 Different stakeholders were consulted to give them the opportunity to express their views and concerns. As part of the process, they were also provided with relevant and sufficient information on the project prior to its start-up. These stakeholders include the central and local authorities, as well as the local population so as to determine their thoughts, opinions and feedback on the impact of the project. Public consultation was held at the Kalapara Pourashava in March 2016. Attendees in the consultation meeting were apprised of the processes through which the project was to proceed toward implementation and the environmental impacts to arise out of such processes along with the steps to be taken toward mitigating the impacts. They were told about the impacts all of which could be easily mitigated. The audience expressed satisfaction of such mitigation measures. Some of the Photographs for public consultation are presented in Figure 5. Figure 5 : Photograph of Public Consultation at Kalapara Pourashava

FGD for Production Tube Well & Pipeline FGD for Production Tube Well & Pipeline

105 As part of the impact assessment, the consultants conducted focus group discussions with selected groups at the locations of the proposed water supply sub-project and met Mayor and apprised about the project. Mayor has shown interest in the project and assured to extend all support for the sub-project. More details on the discussion are available in the Due Diligence Report given in Appendix III.

7.2 Stakeholders

106 Involving stakeholders through participatory direct or indirect consultations is central to completion of the IEE. Therefore, during the public consultations and disclosure of information, various groups of stakeholders were consulted. The stakeholders were those who have an interest in the project, and who will be involved in the further consultative process.

Package: CTEIP/KAL/WS/01: IEE 39 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

107 During the consultative process, beside the local authorities and ordinary population (potential users), other educational organizations were also invited to attend the communication meetings.

7.3 Public Participation – Methods and Process

108 During these consultations, the communities were explained about the project, its benefits, social and environmental impacts. The participants were encouraged to (i) be open and make known their concerns and claims. The presentation highlighted the project background, objectives, expected upcoming activities, social economic information, and environmental information. The salient features of the meetings are presented below:  Create awareness of the project;  To obtain stakeholders responses, feedback and concerns on the project;  To obtain environmental information on the community. 109 After the presentations, the community was given opportunity to give their views, comments and queries. Different community opinions were addressed during the meeting in which the local participants expressed repeatedly their main concerns as follows:  Critical needs for water supply and access to paurashava water supply service;  Types of positive impact to the daily lives, health, and socio-economic status;  Prospects of jobs and income generating activities;  Likely impacts and proposed mitigation measures.

110 Any comments or questions raised by stakeholders were responded to. Safety opportunities associated was a theme brought up in the meetings. The consultant explained that positive and negative impacts of the project on people and the environment will be analyzed such as air pollution, dust, influx of people, employment. The consultant team highlighted that the project will follow government policies in protecting the population. All the participants confirmed that they appreciate the Project. The project received high degree of acceptability, which will boost local economy due to no-loss of life during storms.

7.4 FINDINGS OF PUBLIC CONSULTATION MEETING

111 For details of the public consultations and Focus Group discussions held during the design stage of the sub-project, refer to the Due Diligence Report given in Appendix III. People were keen to know the possibility of employment in the project. There is a requirement of around 100 (skilled plus unskilled) (estimated) during the peak period of the project. The employment is largely depends on the types of job and will be assessed on a case to case basis by the contractor according to needs.

i) There is presence of excess iron in the existing ground/tube well water hence is reddish in color and is not fully safe for drinking. They need water supply connection for getting safe drinking water.

ii) The households, who have neither water supply connection nor individual tube well, are to go to the tube well of others for getting drinking water. Sometimes, these tube wells are located very far from their house. But often the tube well owners do not want to give them access to their tube wells. They misbehave with them, even put gate closed to stop their access.

iii) As they have neither water supply connection nor individual tube well, they, especially the women, have least scope to take bath at home. That is why; they are to go to river or canal or pond which is embarrassing to the women. Besides, this water is not good in quality due to getting polluted by different types of waste which is detrimental to their health. Besides, this water is not safe for using for their daily household activities as well.

iv) Existing municipal water supply capacity is not sufficient to cover all of its households. Besides, not all people have access to Pourashava water supply service due to of the

Package: CTEIP/KAL/WS/01: IEE 40 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

limited capacity. Even, people are ready to pay for getting the connection but they have no scope because of the existing limited capacity of the municipality.

v) No access to existing municipal water supply creating adverse impact to the households who have won land and want to construct/ have constructed new house for giving rent. Tenants are neither willing to hire nor they want to pay appropriate rent to the houses which do not have water supply connection. Only water supply connection to these houses will increase house rent twice than if there is no connection.

vi) For the above reasons including for the purpose of better living of their next generation, people want water supply connection as an important element of their lives. They are ready to pay for getting this service as per cost to be measured by water meter. PS select New Bus terminal hav land for the purpose of installing one production tube well.

vii) The water supply schemes will improve socio-economic-physical conditions of the local people through creating provision of getting access to piped and safe water supply, and creating more opportunity of income, employment, environmental improvement as well as exploiting local resources for boosting local productions.

viii) People were happy to know that water supply project is coming to their town. However they were also keen to know if there is any land acquisition and, if yes, then people shall be paid the market cost of the land.

ix) Priority for jobs should also be given to those who will have any negative impact due to the project. Both men and women shall be consider with equal opportunity;

x) Participant has also shown their inclination to participate in the project during planning and construction.

xi) The participants were also interested to know the likely date of start which will be after monsoon.

Package: CTEIP/KAL/WS/01: IEE 41 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

8. CONCLUSION AND RECOMMENDATIONS

8.1 CONCLUSIONS

112 Based on Project Description (Chapter 3), Environmental Baseline Data (Chapter 4), Environmental Impacts (Chapter 5), and Environmental Mitigation Measures, (Chapter 6), the following conclusions are drawn:

i) The Kalapara water supply project is in plain terrain in the Patuakhali District of . The package number is CTEIP/KAL/WS/01. It is located between latitude 210 48‟and 220 05‟ north and between longitude 900 05‟ and 900 20‟ east. The sub-projects have been selected based on criteria explained in Project Administrative Management (PAM). ii) The PPTA feasibility study has provided a comprehensive set of recommendations for the planning, design and implementation of the Project. Based on the recommendations of this study, the DDS Consultant has completed the detailed engineering design for the construction of water supply in Kalapara.

iii) The project layout will be either on government land of Pourashava land or along the roads or land voluntarily donated by people. Hence there is no resettlement or land acquisition requirement in this subproject. Categorization form is prepared and submitted in Annexure –III.

iv) The integration of water supply with urban and semi-urban areas will help in socioeconomic, physical and health development of the town and town people. The water supply sub-project includes: the /Installation/Construction / Improvement of One production tube well, one over head tank (OHT), 25.5km of pipeline, 3.1 km Replaced Pipeline, 1800 new service connections, 500 replaced Service Connections One pump houses, supply of O&M tools and supply, fitting, fixing and commissioning of electro- mechanical works. Educational, cultural and health centres will have an easy access thus making improved living standards and quality of life of the people.

v) The adverse environmental impacts will occur during the construction period, and will be of a relatively short duration. Adequate provisions have been incorporated into the planning and design of the water supply to minimize or mitigate these unavoidable environmental impacts that are a result of the works.

v) The major positive achievements of water supply sub-project are:  Development of water supply will serve not only the influence area but also the surrounding area in the town.  Establishment of water development will stimulate ancillary projects which will improve economic status of the local population;  More employment of people during construction phases;  Reduction in fuel consumption, increase in health safety, less emission and greenhouse gases responsible for climate change;  Will be potential socio-economic enhancement of economy by connecting people to water;  Skill Transfer and Training.

vi) The major negative impacts will be on water pollution, soil erosion, and noise pollution during construction. In addition, there will be insignificant increase in ambient air quality and noise at about 250 m from source and will be at acceptable level for mixed land use. The noise and air quality of the project area is within the permissible limits. The overall impact on air and noise quality during construction is limited to site and of short duration and can be mitigated.

viii) The environmental mitigation measures as stipulated in EMP and in the obtained environmental permit shall be monitored during implementation of the water supply sub- project. In order to perform monitoring of EMP the contractor shall engage experienced

Package: CTEIP/KAL/WS/01: IEE 42 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

laboratory and third party services in complying the required environmental testing of parameters listed in Section 2 of EMP.

ix) The labour camps shall be established with the septic tank and soak pit for treatment and disposal of sewage and sullage water to avoid pollution of water bodies. Contractor has to make own arrangement for water supply for construction and domestic purpose.

x) The environmental monitoring will be required before the start of the construction and during the construction phase. The parameters of Water Quality, Air Quality, Noise quality, and Soils shall be monitored; as specified in Section 2 of EMP.

xi) The environmental costs are estimated at 733,718.20. The environmental monitoring cost is estimated as Tk. 520000while environmental management cost is Tk. 213718.2(excluding those included in the cost of water supply design). This Appendix A: IEE is to be read in conjunction with the attached Appendix B: EMP, which gives a detailed breakdown of the costs for the Environmental Management and Monitoring, which are also referred in the attached Bill of Quantities.

xi) During public consultation recommendations were drawn including: i) involve local communities in all stages of project planning and development, ii) establish permanent communication between project initiators and local authorities, iii) setup grievance redress mechanism which will publicized through Pourashava level co-ordination committee and monitoring register and iv) during construction, local people including women shall be given first priority in the employment of skilled and unskilled labour.

xii) The ground water quality for Manganese and Iron is more and can only be utilized with proper treatment.

8.2 RECOMMENDATIONS

113 In view of above, it is concluded that the Project will bring benefit to the people of the area and will improve health aspects especially the water borne disease including their socioeconomic and physical conditions. The negative impacts occurring during implementation are within the manageable limits and shall be mitigated with the proposed EMP and, hence, the project may be implemented. Water source needs treatment for Mn and Fe.

8.3 DISCLOSURE OF ENVIRONMENTAL SAFEGUARDS INSTRUMENTS

114 The LGED will disclose this Environmental Management Framework by making copies available at its head office and in District / Pourashava where the Project is situated. The copies shall also be made available to the Local Government‟s Agencies, the Environmental and Social Group and other stakeholders. The Government of Bangladesh will also authorize the Asian Development Bank to disclose this IEE and EMP electronically through its Info Shop.

Package: CTEIP/KAL/WS/01: IEE 43 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

Package: CTEIP/KAL/WS/01: IEE 44 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

ANNEXURE I: RAPID ENVIRONMENTAL ASSESSMENT CHECKLISTS

Installation of One Production TW; One OHT, Pipeline (25.5km new pipeline; 3.1 km Replaced Pipeline; 1800 new Service Connections and 500 replaced Service Connections); One Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical works under Kalapara Pourashava, District: Patuakhali

Screening Questions Yes No Remarks A. Project Siting Is the project area adjacent to or within any of the following areas:  Underground utilities No  Cultural heritage site No  Protected Area No  Wetland/Ponds No  Mangrove No  Estuarine No  Buffer zone of protected area No  Special area for protecting biodiversity No  Bay No B. Potential Environmental Impacts Will the Project cause:  Encroachment on historical/cultural areas? No  Encroachment on precious ecology (e.g. sensitive or protected areas)? No  Impacts on the sustainability of associated sanitation and solid waste disposal systems? No  Dislocation or involuntary resettlement of people? No  Disproportionate impacts on the poor, women and children, Indigenous Peoples or other No vulnerable groups?  Accident risks associated with increased vehicular traffic, leading to loss of life? yes EMP to be followed  Increased noise and air pollution resulting from increased traffic volume? Yes EMP to be followed  Occupational and community health and safety risks? yes EMP to be followed  Risks and vulnerabilities related to occupational health and safety due to physical, No chemical, biological, and radiological hazards during project construction and operation?  Generation of dust in sensitive areas during construction? Yes EMP to be followed  Requirements for disposal of fill, excavation, and/or spoil materials? Yes EMP to be followed  Noise and vibration due to blasting and other civil works? Yes EMP to be followed  Long-term impacts on groundwater flows as result of needing to drain the project site prior No to construction?  Long-term impacts on local hydrology as a result of building hard surfaces in or near the No building?  Large population influx during project construction and operation that causes increased No burden on social infrastructure and services (such as water supply and sanitation systems)?  Social conflicts if workers from other regions or countries are hired? No  Risks to community safety caused by fire, electric shock, or failure of the buildings safety No features during operation?  Risks to community health and safety caused by management and disposal of waste? yes EMP to be followed  Community safety risks due to both accidental and natural hazards, especially where the No structural elements or components of the project are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation and decommissioning? Note: Hazards are potentially damaging physical events.

Package: CTEIP/KAL/WS/01: IEE 45 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

ANNEXURE II: GRIEVANCE REGISTRATION FORM (Bangla translation to be available)

The Coastal Towns Environmental Infrastructure Project (CTEIP) welcomes complaints, suggestions, queries and comments regarding project implementation. We encourage persons with grievance to provide their name and contact information to enable us to get in touch with you for clarification and feedback.

Should you choose to include your personal details but want the information to remain confidential, please inform us by writing/typing *(CONFIDENTIAL)* above your name.

Thank you.

Date Place of Registration

Contact Information/Personal Details Name Gender * Male Age * Female Home Address Place Phone no./Cell no. E-mail Complaint/Suggestion/Comment/Question Please provide the details (who, what, where, and how) of your grievance below: If included as attachment/note/letter, please tick here:

How do you want us to reach you for feedback or update on your comment/grievance?

FOR OFFICIAL USE ONLY Registered by: (Name of Official Registering Grievance)

Mode of Communication: Note/Letter E-mail Verbal/Telephonic Reviewed by: (Names/Positions of Officials Reviewing Grievance)

Action Taken:

Whether Action Taken Disclosed: Yes No Means of Disclosure:

Package: CTEIP/KAL/WS/01: IEE 46 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

ANNEXTURE III: CATEGORIZATION FORM INVOLUNTARY RESETTLEMENT IMPACT CATEGORIZATION

Date: ___/___/2014 A. Project Data

Country/Project No./Project : Country: Bangladesh Title ADB No.: (No. to be designated)

Coastal Towns Environmental Infrastructure Project (CTEIP)

Subproject: CTEIP/KAL/WS/01

B. Involuntary Resettlement Category

[ ] New [ ] Recategorization ― Previous Category [ ]

Category A Category B Category C Category FI

C. Comments

 No unavoidable dislocation or involuntary resettlement of persons affected by the subproject will take place as a result of the Installation of One Production TW; One OHT, Pipeline (25.5km new pipeline; 3.1 km Replaced Pipeline; 1800 new Service Connections and 500 replaced Service Connections); One Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical works under Kalapara Pourashava, District: Patuakhali

 The project layout will be either on government land of Pourashava land or along the roads is annexed in Annexure IV of Due Diligence Report).

Package: CTEIP/KAL/WS/01: IEE 47 Section 6: Employer’s Requirements: Subsection 3 Particular Specification: Initial Environmental Examination (IEE)

ANNEXURE IV: INVOLUNTARY RESETTLEMENT IMPACT CATEGORIZATION CHECKLIST

Installation of One Production TW; One OHT, Pipeline (25.5km new pipeline; 3.1 km Replaced Pipeline; 1800 new Service Connections and 500 replaced Service Connections); One Pump Houses; Supply of O & M tools and Supply, fitting, fixing and commissioning of Electro-mechanical works under Kalapara Pourashava, District: Patuakhali

Probable Involuntary Resettlement Effects Yes No Not Known Remarks

Involuntary Acquisition of Land

1. Will there be land acquisition? No 2. Is the site for land acquisition known? Not applicable 3. Is the ownership status and current usage of land to be Not applicable acquired known? 4. Will easement be utilized within an existing Right of Way Not applicable (ROW)? 5. Will there be loss of shelter and residential land due to land Not applicable acquisition? 6. Will there be loss of agricultural and other productive assets Not applicable due to land acquisition? 7. Will there be losses of crops, trees, and fixed assets due to Not applicable land acquisition? 8. Will there be loss of businesses or enterprises due to land Not applicable acquisition? 9. Will there be loss of income sources and means of livelihoods Not applicable due to land acquisition? Involuntary restrictions on land use or on access to legally designated parks and protected areas 10. Will people lose access to natural resources, communal No facilities and services? 11. If land use is changed, will it have an adverse impact on No social and economic activities? 12. Will access to land and resources owned communally or by No the state be restricted? Information on Displaced Persons: Not Applicable

Any estimate of the likely number of persons that will be displaced by the Project? [--] No [--] Yes

If yes, approximately how many? ______

Are any of them poor, female-heads of households, or vulnerable to poverty risks? [--] No [--] Yes

Are any displaced persons from indigenous or ethnic minority groups? [--] No [--] Yes

Note: The project team may attach additional information on the project, as necessary.

Package: CTEIP/KAL/WS/01: IEE 48