Coastal Zone Management Plan Prepared for Estuary Management Committee

5 IMPLEMENTATION STRATEGY AND ACTION PLANS

5.1 Implementation Strategy

The full list of prioritised management actions has been developed into an implementation strategy that forms the basis of the Parramatta River Estuary CZMP. There are a total of 67 management actions in the strategy, of which 21 are to be progressed by the Committee as a whole. The remaining 46 management actions are the responsibility of individual authorities. It should be noted that implementation of these actions are dependent on suitable funding and internal resources being available within the individual organisations. In addition, a further 16 management actions were identified as generic actions of significant benefit or high priority that may be implemented by any council or authority in the event the necessary resources become available. These generic actions have been provided as a stand-alone list as they cannot be coasted or prioritised along with the other actions in the strategy.

Where possible, the management actions have also been mapped and the corresponding GIS (Geographic Information System) file provided to the relevant authority responsible for implementation. The locations of management actions have been mapped using GIS layers prepared for the Estuary Processes Study (AECOM, 2010) where relevant, and also GIS layers created by Cardno.

5.1.1 Cost of Implementation

The estimated capital cost of implementation of the Plan is $19.4 million, with an estimated $1.6 million in annually recurrent costs over an assumed ten year period of implementation (corresponding to the first period of implementation). The cost of implementation has been broken down for the different authorities in Table 5.1.

For some actions, the capital cost relates to preparation of a plan, an investigation or time for a staff member to progress an activity (project management). In other cases, the capital cost involves on the ground works, which is highly variable depending upon the specific project. The annually recurrent costs may relate to ongoing project management, maintenance or an annual budget for implementation of a staged strategy.

Table 5.1: Preliminary Indicative Cost of Implementation of the Implementation Strategy Authority Estimated Capital Cost Estimated Annually Recurrent Cost Ashfield Council $ 300,000 $ 4,000 Auburn City Council $ 78,750 $ 10,525 City of Bay $ 4,193,375 $ 20,900 City of Ryde $ 1,312,918 $ 15,686 Hunters Hill Council $ 395,000 $ 416,125 Leichhardt Municipal Council $ 2,218,150 $ 45,700 Parramatta City Council $ 575,000 $ 97,000 Strathfield Council $ 5,237,250 $ 125,876 RMS (Maritime) $ 290,000 $ 7,000 SOPA $ 10,000 $ 134,500 Water $ 2,289,275 $ 163,063 Committee $ 2,473,000 $ 516,500 TOTAL $19,372,838 $1,556,875

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 77 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

As of 11 April 2013, the OEH website states that projects which can be subsidised under the coastal and estuary management programs include:

ƒ Preparation (or updating) of CZMPs and associated technical studies (including coastal hazard assessments); ƒ Action to manage the risks from coastal hazards; ƒ Action to implement environmental repairs, including habitat restoration and conservation projects; ƒ Pre-construction activities for projects that are eligible and are likely to proceed to construction; and ƒ Development of management tools (such as education projects). Funding of up to 50% of a project’s costs may be provided to successful grant applicants.

Other sources of grant funding include:

ƒ NSW Government Environment Trust and Heritage Grants Program; ƒ NSW DP&I’s Metropolitan Greenspace Program, Planning Reform Fund, and Sharing Sydney Harbour Access Program; ƒ NSW DPI Habitat Action Grants; ƒ RMS (Maritime)’s Better Boating Program; and ƒ Australian Government’s Caring for Our Country Program and Stormwater Harvesting and Reuse grants. Organisations like the HNCMA also play a role in working with local councils and community groups to undertake natural resource management projects.

5.1.2 Sub-Plans

In order to support the implementation strategy and identify where activities are proposed, a series of sub-plans have been developed, including Action Plans and ‘Process’ Sub-Plans. The Action Plans developed are discussed further and provided in Section 5.2.

A series of ‘Process’ Sub-Plans (provided in Appendix G) have been developed to map those management actions for each of the processes listed below. These Sub-Plans are useful for showing in a more holistic fashion the spatial distribution of different types of activities across the study area:

ƒ Land Use Planning and Development (Figures F.1A and B), ƒ Water and Sediments (Figures F.2A to D), ƒ Estuarine Ecology (Figures F.3A to C), ƒ Bank Condition (Figures F.4A and B), and ƒ Human Usage and Recreation (Figures F.5A and B).

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 78 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

5.2 Action Plans

In order to support the implementation strategy and identify where activities are proposed, a series of Action Plans have been developed as sub-plans.

An Action Plan has been prepared for each authority consisting of a table listing the actions for implementation and capital and annually recurrent costs. Where possible, an A3 sized plan has also been provided that maps any location specific actions. The Action Plans can be easily separated out from the main report and used to progress implementation of each authority’s management actions. One Action Plan has been developed for each of the 11 authorities as well as the Committee:

ƒ Ashfield Municipal Council (2 actions); ƒ Auburn Council (2 actions); ƒ City of (5 actions); ƒ City of Ryde (5 actions); ƒ Hunters Hill Council (5 actions); ƒ Leichhardt Municipal Council (5 actions); ƒ Parramatta City Council (5 actions); ƒ Strathfield Council (5 actions); ƒ RMS (Maritime) (4 actions); ƒ SOPA (4 actions); ƒ (4 actions); and ƒ Committee (21 actions). Action Plan tables for the above-listed authorities are provided in Tables 5.2 to 5.13, respectively, while Action Plan maps are provided in Figures 5.1 to 5.10, with the exception of RMS (Maritime) and the Committee where no map has been prepared due to a lack of site-specific actions.

Note that the Committee has an overarching responsibility to progress the Plan and support its members in implementing actions for which they are responsible.

In addition a further 16 management actions were identified as generic actions. As previously discussed, these generic actions have been provided as a stand-alone list. The Action Plans for the additional 16 General Actions are provided in Table 5.14.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 79 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.2: Ashfield Municipal Council Action Plan Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Capital Cost Annually Action ID Action Description Location(s) Indicative Annually Present Present Ratio Ratio

Supporting Category Decommissioning (as required) Comments Recurrent Cost Value Capital Cost Recurrent Priority Net

Organisation Comments Cost:Benefit Cost Utilise data collected for all seawalls, including referenced site Design, EIA, tender, Annual photographs, as a benchmark for ongoing monitoring and in For purposes of costing, assume project management, maintenance of particular continue to monitor the seawall identified in AECOM Ashfield Monitoring replacement seawalls identified as being site establishment. 21_ASH2 Haberfield $260,000 $4,000 seawalls, plus $288,094 0.37 1 (2010) as ASH_S03 for any decrease in structural stability. Include Council and Works in poor condition in AECOM (2010) in Develop monitoring regular intertidal habitat, such as artificial reefs, in the eventual repair and / addition to monitoring. framework & monitoring. or replacement of seawalls. systems. In conjunction with Leichhardt Municipal Council, and Sydney Water, undertake a critical review of existing stormwater management practices to determine: Ashfield - The efficacy of maintenance regimes of existing GPTs, and Council - Identify locations where additional gross pollutant trapping is Leichhardt 8_ASH1 required. Municipal Investigation $40,000 $ - $40,000 0.87 2 Catchment Include a review of current street sweeping activities in catchment Council, City of areas draining to Iron Cove Bay, given that the dominant gross Canada Bay, pollutant evident is leaf litter. Reference should be made to Sydney Water AECOM (2010) for further discussion of the issues relevant to this action.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 80 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 CANADA BAY CONCORD Iron Cove Bay

Haberfield Foreshore C A N A D A B A Y FIVE DOCK

LILYFIELD Action Plan - Ashfield Municipal Council

PARRAMATTA RIVER ESTUARY COASTAL ZONE MANAGEMENT PLAN

BURWOOD

LEICHHARDT Action 21_ASH2 Legend CROYDON Utilise data collected for all seawalls, including BURWOOD referenced site photographs, as a benchmark Ashfield LGA for ongoing monitoringLEICHHARDT and in particular LGA Boundaries continue to monitor the seawall identified in Waterway AECOM (2010) as ASH_S03 for any decrease in structural stability. Include intertidal habitat, such as artificial reefs,in the eventual repair and / or replacement of seawalls.

Iron Cove Catchment

ASHFIELD Note: Inaccuracies may be present in data provided by third parties. It is assumed that all GIS ASHFIELD data provided by third party suppliers is sufficient STANMORE and accurate for the purpose of this map. BURWOOD HEIGHTS

FIGURE 5.1 SUMMER HILL STANMORE

PETERSHAM LEWISHAM ® CROYDON PARK 1:16,000 Scale at A3

MARRICKVILLE Metres Action 8_ASH1 0 200 400 600 800 Undertake a critical review of existing stormwater management ASHBURY practices to determine: - The efficacy of maintenance regimes of existing GPTs, and - Locations where additional gross pollutant trapping is required. CANTERBURY DULWICH HILLInclude a review of current street sweeping activities in catchment areas draining to Iron Cove Bay, given that the dominant gross pollutant evident is leaf litter. Undertake in conjunction with Leichhardt MunicipalMARRICKVILLE Council, Map Produced by Cardno NSW/ACT Pty Ltd (2812) City of Canada Bay and Sydney Water. Date: 2013-06-19 CAMPSIE Coordinate System: GDA 1994 MGA Zone 56 CANTERBURY Project: LJ2929 Map: G5001_ActionsAshfield 03.mxd 02 HURLSTONE PARK Data source: NSW Land and Property Information (LPI) Aerial Imagery supplied by Sydney Metropolitan Catchment Management Authority and associated third party suppliers. Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.3: Auburn Council Action Plan

Primary Preliminary Preliminary Annually Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Indicative Capital Cost Comments Recurrent Present Present Ratio Ratio

Supporting Category Decommissioning (as required) Annually Value Capital Cost Cost Priority Net

Organisation Recurrent Cost Cost:Benefit Comments Design, EIA, tender, project management, site Undertake bank stabilisation works with natural establishment. Install sandstone materials and vegetation in Duck River, along Auburn City bank protection (200mm high, 10_AUB2 approximately a 20-30m reach adjacent to the Auburn Duck River Works $26,250 $525 $29,937 0.89 1 Council 50m long retaining wall) Botanic Gardens and approximately a 50m reach including footings, and adjacent to Mona Park. restoration as required to surrounding area. Feasibility, design, EIA, tender, project management, site For purposes of including a Investigate the installation of a GPT or WSUD feature establishment. Supply and Annual Auburn City realistic budgetary estimate within 7_AUB1 within Mona Park, Auburn, to treat stormwater Auburn Works $52,500 install GPT, including connection $10,000 maintenance of $122,736 0.79 2 Council the Plan, this has been costed discharging into Duck River. to existing drainage, and GPT. assuming installation of a GPT. discharge erosion protection as required.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 82 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 RYDALMERE MELROSE PARK MEADOWBANK RYDERYDE CAMELLIA ERMINGTON RYDE

PUTNEY PARRAMATTA HARRIS PARK

ROSEHILL PARRAMATTAPARRAMATTA Action Plan - Auburn HOLROYDHOLROYD RHODES HOLROYD Action 10_AUB2 Undertake bank stabilisation works with natural materials City Council and vegetation in Duck River, along approximately a PARRAMATTA RIVER ESTUARY 20-30m reach adjacent to the Auburn Botanic Gardens COASTAL ZONE MANAGEMENT PLAN and approximately a 50m reach adjacentCLYDE to Mona Park. SILVERWATER

NEWINGTON GRANVILLE

HOMEBUSH BAY SOPASOPA LIBERTY GROVE Legend Auburn LGA CONCORD WEST LGA Boundaries Waterway MERRYLANDS CC A A N N A A D D A A B B A A Y Y

Mona Park Action 7_AUB1 Investigate the installation of a GPT or WSUD feature within Mona Park, Auburn, to treat stormwater discharging into Duck River. Note: Inaccuracies may be present in data provided by third parties. It is assumed that all GIS data provided by third party suppliers is sufficient AUBURN AUBURNAUBURN and accurate for the purpose of this map. CONCORD

LIDCOMBE SOUTH GRANVILLE NORTH STRATHFIELD

FIGURE 5.2 HOMEBUSH WEST HOMEBUSH GUILDFORD ®

1:28,000 Scale at A3 STRATHFIELD STRATHFIELD Metres ROOKWOOD BERALA 0 250 500 750 1,000

STRATHFIELD BURWOODBURWOOD

BURWOOD REGENTS PARK Map Produced by Cardno NSW/ACT Pty Ltd (2812) BANKSTOWNBANKSTOWN Date: 2013-06-05 SEFTON Coordinate System: GDA 1994 MGA Zone 56 GREENACRE Project: LJ2929 Map: G5002_ActionsAuburn 03.mxd 02 CHULLORA ENFIELD Data source: NSW Land and Property Information (LPI) STRATHFIELD SOUTH Aerial Imagery supplied by Sydney Metropolitan Catchment BIRRONG STRATHFIELD SOUTH Management Authority and associated third party suppliers. BIRRONG POTTS HILL Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.4: City of Canada Bay Action Plan Preliminary Primary Notes on Implementation and Preliminary Indicative Responsibility Management Annually Action ID Action Description Location(s) Decommissioning (as Indicative Capital Cost Comments Annually Present Present Ratio Ratio

Supporting Category Recurrent Cost Value required) Capital Cost Recurrent Priority Net

Organisation Comments Cost:Benefit Cost Annual budget for Undertake enhancement of estuarine vegetation as a vegetation stabilisation method in areas of erosion, and to protect management existing seawalls from further erosion. Locations as identified City of Canada City of (noting that the 17_CAN3 Works $ - $2,500 $17,559 1.18 1 in the Estuary Processes Study (AECOM, 2010) include: Hen Bay Canada Bay effort will decrease and Chicken Bay, Sisters Bay, Half Moon Bay, Five Dock over time as the Bay and Iron Cove Bay. vegetation becomes established). Liaise with the NSW Government to progress the remediation Assumes 0.05 FTE City of Canada 2_CAN1 of Kendall Bay and others and seek appropriate rezoning to Kendall Bay Comms $ - $400 hours per week for $2,809 1.16 2 Bay W2 - Environmental Protection Zone. 6 months. Opportunities to reduce vulnerability of the stormwater drainage system to climate Develop and commence a staged implementation program change impacts may be from the City of Canada Bay Stormwater Drainage Asset City of Canada City of achieved more cost effectively 8_CAN2* Management Plan. The implementation program should Planning $50,000 $ - $50,000 1.06 3 Bay Canada Bay in a progressive fashion, incorporate activities that aim to reduce the potential impacts although some activities may be of climate change and SLR on stormwater drainage. more suitable for implementation once a trigger has been reached. Develop and commence a staged implementation program from the City of Canada Bay Estuary Foreshore Management Strategy to include environmentally friendly seawalls as key options for seawall and foreshore management, where Design, EIA, tender, project reasonable and feasible. Continue to monitor the condition of Planning, For purposes of costing, City of Canada City of management, site Assume 0.2 FTE 21_CAN4 seawall sections identified in the Estuary Processes Study Works and assumes replacement the two $3,265,875 $16,000 $3,378,252 0.46 4 Bay Canada Bay establishment. Upgrade hours. (AECOM, 2010) and prioritise in accordance with the City of Monitoring seawall sections identified. seawalls. Canada Bay Asset Management Plan (2010) to ensure structural integrity. As a priority, repair and/or upgrade existing seawall sections along Abbotsford Bay (CAN_S28) and Five Dock Bay (CAN_S23). Repair and/or upgrade sections of seawall, natural shoreline and adjacent affected infrastructure around Iron Cove, including the following sections identified in the Estuary Design, EIA, tender, project Processes Study (AECOM, 2010), avoiding the use of City of Canada Iron Cove management, site 23_CAN5 artificial structures where reasonable and feasible: Works $877,500 $2,000 $891,547 0.67 5 Bay Bay establishment. Upgrade CAN_S03, CAN_S04, CAN_S06, CAN_NS01 and seawalls. CAN_NS02. Seawall upgrades should, where possible, be designed in accordance with the DECC and SMCMA (2009) Guidelines for Environmentally Friendly Seawalls.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 84 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 ActionWEST 8_CAN2 RYDE EAST RYDE Develop and commence a staged implementation LANE COVE WEST program from the City of Canada Bay Stormwater Drainage Asset Management Plan. The implementation LANE COVE program should incorporate activities that aim to MEADOWBANK MELROSEreduce PARK the potential impacts of climate change and RYDE sea level rise on stormwater drainage. LL A A N N E E C C O O V V E E Action Plan - City of RYDERYDE Canada Bay Council PARRAMATTA RIVER ESTUARY RIVERVIEW COASTAL ZONE MANAGEMENT PLAN AUBURNAUBURN PUTNEY LINLEY POINT GLADESVILLE

RHODES Action 17_CAN3 LONGUEVILLE Legend TENNYSON POINT Undertake enhancement of estuarine vegetation as a HUNTERSHUNTERSAction HILLHILL 23_CAN5 Canada Bay LGA stabilisation method in areas of erosion, and to protect Repair and/orHUNTERS upgrade HILL sections of seawall, natural existing seawalls from further erosion. Locations as LGA Boundaries identified by AECOM (2010) include: Hen and Chicken shoreline and adjacent affected infrastructure around Bay, Sisters Bay, Half Moon Bay, Five Dock Bay and Iron Cove, including those sections identified by AECOM Waterway Iron Cove Bay. (2010) CAN_S03, CAN_S04, CAN_S06, CAN_NS01 HUNTLEYS COVEand CAN_NS02), avoiding the use of artificial structures where reasonable and feasible. Seawall upgrades should, whereHUNTLEYS possible, POINTbe designed in accordance with the DECC (2009) Guidelines for Environmentally Friendly Seawalls. MORTLAKE Kendall Bay and Breakfast Point Note: Inaccuracies may be present in data LIBERTY GROVE HENLEY (! provided by third parties. It is assumed that all GIS BREAKFAST POINT data provided by third party suppliers is sufficient CONCORD WEST and accurate for the purpose of this map. SOPASOPA

Five Dock Bay CABARITA

C A N A D A B A Y CAN_S28 C AAction N A D 2_CAN1 A B A Y CAN_S23 FIGURE 5.3 Liaise with the NSW Government to progress the ABBOTSFORD CHISWICK remediation of Kendall Bay and seek appropriate rezoning to W2 - Environmental Protection Zone. DRUMMOYNE

Hen and Chicken Bay

CONCORD ®

WAREEMBA Sisters Bay NORTH STRATHFIELD RUSSELL LEA CAN_NS02 1:25,000 Scale at A3 Half Moon Bay

CAN_S04 Metres Action 21_CAN4 0 250 500 750 1,000

HOMEBUSH Develop and commence a staged implementation Iron Cove Bay program from the City of Canada Bay Estuary Foreshore Management Strategy to include environmentally friendly CANADA BAY RODD POINT seawalls as key options for seawall and foreshore STRATHFIELDSTRATHFIELD management. Continue to monitor the condition of seawall FIVE DOCK sections identified in AECOM (2010) and prioritise in accordance with the City of Canada Bay Asset LEICHHARDTLEICHHARDT Management Plan (2010) to ensure structural integrity. LILYFIELD Map Produced by Cardno NSW/ACT Pty Ltd (COE) As a priority, repair and/or upgrade existing seawall Date: 2013-06-05 Coordinate System: GDA 1994 MGA Zone 56 sectionsSTRATHFIELD along Abbotsford Bay (CAN_S28) and Five Project: LJ2929 Dock Bay (CAN_S23). BURWOOD BURWOODBURWOOD Map: G5003_ActionsCanadaBay 03.mxd 02 CROYDON Data source: NSW Land and Property Information (LPI) Aerial imagery supplied by Sydney Metropolitan Catchment Management Authority and associated third party suppliers ASHFIELD ASHFIELDASHFIELD LEICHHARDT LEICHHARDT Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.5: City of Ryde Action Plan Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Annually Action ID Action Description Location(s) Indicative Capital Cost Comments Annually Present Present Ratio Ratio

Supporting Category Decommissioning (as required) Recurrent Cost Value Capital Cost Recurrent Priority Net

Organisation Comments Cost:Benefit Cost Works would be subject to Design, EIA, tender, project Investigate the potential for installing a SQID at Annual 7_RYD3 City of Ryde Meadowbank Works available funding. Potential $220,000 management, site $3,000 $241,071 1.11 1 Meadowbank Lane, Meadowbank. maintenance treatment area of 40,000m2. establishment, construction. Investigate the potential for installing irrigation and Works would be subject to Feasibility, design, EIA, tender, Annual bioretention systems at Peel Park in Gladesville to feasibility studies and available project management, site 7_RYD2 City of Ryde Gladesville Works $114,375 $4,575 maintenance of $146,508 0.97 2 provide improved treatment of stormwater flows entering funding. Peel Park has a potential establishment, construct features. the estuary from the site. treatment area of 150m2. bioretention treatment area. Rehabilitate the following two sections of eroding foreshore identified as being of a high priority and in poor Design, EIA, tender, project condition in the Estuary Processes Study (AECOM, management, site 23_RYD5 City of Ryde City of Ryde Works $55,125 $1,103 $62,872 0.83 3 2010), subject to available funding: establishment. Rehabilitate - RYD-NS07 (Kissing Point Park, Putney), and foreshore. - RYD-NS13 (Meadowbank, adjacent to rail bridge). Works would be subject to feasibility studies and available funding. Anzac Park has a Feasibility, design, EIA, tender, Investigate the potential for installing irrigation and potential bioretention system project management, site Annual bioretention systems at Anzac Park in West Ryde to catchment area of 3,100m2 and establishment, construction 7_RYD1 City of Ryde West Ryde Works $83,438 $3,008 maintenance of $104,565 0.80 4 provide improved treatment of stormwater flows entering treatment area of 67m2. There is bioretention treatment area, features. the estuary from the site. also a potential underground tank excavate and construct below catchment area of 14,000m2 and ground tank. treatment area of 20m2 for irrigation purposes. Upgrade and / or repair the following four sections of seawall identified as being in poor condition and of a high priority in the Estuary Processes Study (AECOM, 2010) Design, EIA, tender, project For purposes of costing, assumes Annual and seek to incorporate additional vegetated habitat in management, site Works and replacement the two seawall maintenance of 21_RYD4 the design, subject to available funding: RYD-S06, RYD- City of Ryde City of Ryde $840,000 establishment, upgrade $4,000 $868,094 0.34 5 Monitoring sections identified, as well as seawalls, plus S11, RYDS03 & RYD-S23. seawalls. Develop monitoring monitoring. regular monitoring. Continue to monitor the condition of other seawall framework and systems. sections identified in the Estuary Processes Study (AECOM, 2010) for any decrease in structural stability.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 86 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 DENISTONE Action 7_RYD1 DENISTONE WEST Investigate the potential for installing irrigation and Action 7_RYD3 bioretention systems at Anzac Park in West Ryde to NORTH RYDE provide improved treatment of stormwater flows Investigate the potential for installing a SQID at entering the estuary from the site. Meadowbank Lane, Meadowbank. Action Plan - Anzac Park City of Ryde

WEST RYDE EAST RYDE PARRAMATTA RIVER ESTUARY COASTAL ZONE MANAGEMENT PLAN

RYDE

RYDERYDE Legend MELROSE PARK Ryde LGA Action 21_RYD4 LGA Boundaries PARRAMATTAPARRAMATTA Upgrade or repair the four sections of seawall (RYD-S06, Waterway MEADOWBANK RYD-S11, RYDS03 and RYD-S23) identified as being in Action 7_RYD2 poor condition and of a high priority in the Estuary Investigate the potential for installing irrigation and Processes Study (AECOM, 2010). Seek to incorporate bioretention systems at Peel Park, Gladesville to additional vegetated habitat in the design, subject to RYD-NS13 provide improved treatment of stormwater flows available funding. Continue to monitor the condition of entering the estuary from the site. other seawall sections identified in the Estuary Processes Study for any decrease in structural stability.

RYD-S11

RYD-S23

Note: Inaccuracies may be present in data provided by third parties. It is assumed that all GIS data provided by third party suppliers is sufficient PUTNEY HUNTERS HILL and accurate for the purpose of this map. GLADESVILLE RYD-NS07 Peel Park

RHODES RYD-S06 FIGURE 5.4 TENNYSON POINT HUNTERSHUNTERS HILLHILL

Action 23_RYD5 Rehabilitate the following two sections of eroding HOMEBUSH BAY foreshore identified as being of a high priority and ® AUBURNAUBURN in poor condition in the Estuary Processes Study (AECOM, 2010), subject to available funding: - RYD-NS07 (Kissing Point Park, Putney), and 1:20,000 Scale at A3 HUNTLEYS COVE - RYD-NS13 (Meadowbank, adjacent to rail bridge). Metres 0 250 500 750 1,000

HENLEY SOPASOPA CONCORD WEST MORTLAKE

BREAKFAST POINT RYD-S03

CC A A N N A A D D A A B B A A Y Y CABARITA Map Produced by Cardno NSW/ACT Pty Ltd (2812) Date: 2013-06-05 ABBOTSFORD Coordinate System: GDA 1994 MGA Zone 56 CONCORD Project: LJ2929 Map: G5004_ActionsRyde 03.mxd 02 CC A A N N A A D D A A B B A A Y Y Data source: NSW Land and Property Information (LPI) Aerial imagery supplied by Sydney Metropolitan Catchment CHISWICK Management Authority and associated third party suppliers Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.6: Hunters Hill Council Action Plan

Primary Preliminary Notes on Implementation Preliminary Responsibility Management Indicative Action ID Action Description Location(s) and Decommissioning (as Indicative Capital Cost Comments Annually Recurrent Ratio

Supporting Category Annually Value required) Capital Cost Cost Comments Priority Net Present

Organisation Recurrent Cost Cost:Benefit

Implement the Stormwater Management Action Plan currently being prepared for Council consistent with the Budget for implementation CZMP and review the maintenance regimes for will depend on the stormwater infrastructure to ensure existing infrastructure Relies on completion of the strategy defined in the Hunters Hill Hunters Hill Planning and For review of existing 1_HUN1 is maintained regularly and adequately. This Action Plan Action Plan for $50,000 $250,000 Action Plan. Current $1,805,895 0.80 1 Council LGA Works maintenance regimes. will identify sites for stormwater infrastructure implementation. costings provide an improvements / upgrades, additional GPTs and/or other indicative annual budget stormwater quality controls in various locations, including for implementation. . Disseminate the Guidelines for Environmentally Friendly Seawalls (DECC and SMCMA, 2009) to council staff, particularly those involved in the assessment of DAs, to Hunters Hill encourage the promotion of the guidelines. This should Assume one week of staff Council Hunters Hill Costing assumes internal 24_HUN5 be undertaken on a regular basis so as to ensure new Comms $ - $1,500 members time for liaison $10,535 0.75 2 LGA communication only. staff are familiar with the guidelines. with internal staff. OEH Make sure the planned repairs to the following seawalls comply with the guidelines wherever possible: HUN_S01, HUN_S04 & HUN_S07. Assumed annual budget May require assessment of Undertake management of estuarine vegetation within Gladesville for implementation of potential SLR impacts on Gladesville Reserve and Riverglade Reserve to enhance Hunters Hill Reserve, activities identified in the 17_HUN3 Works the Reserves. Reference is $ - $50,000 $351,179 0.72 3 saltmarsh habitats in these areas and allow for future Council Riverglade relevant Estuary made to linked actions landward migration with SLR. Reserve Vegetation Rehabilitation 34_COM22 & 39_COM23. & Management Plans. Continue bush regeneration in all reserves of the Parramatta River estuary catchment located within Hunters Hill LGA, including undertaking the following recommendations made in the Estuary Processes Study (AECOM, 2010): Assumes annual salary - Targeted vine control and removal of young Phoenix for 0.4 FTE hours for palms, Coral trees and Green Cestrum within the upper Hunters Hill Hunters Hill 20_HUN4 Works $ - $50,000 Bushcare coordinator & $351,179 0.72 3 tidal reach of Tarban Creek; Council LGA budget for materials as - Control of emerging mangrove saplings in saltmarsh required. located within Gladesville Reserve; - Ongoing monitoring and management of Alligator Weed in Betts Park and Gladesville Reserve; and - Gradual removal of large Camphor Laurels in Betts Park and replacement with native species.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 88 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Primary Preliminary Notes on Implementation Preliminary Responsibility Management Indicative Action ID Action Description Location(s) and Decommissioning (as Indicative Capital Cost Comments Annually Recurrent Ratio

Supporting Category Annually Value required) Capital Cost Cost Comments Priority Net Present

Organisation Recurrent Cost Cost:Benefit

Design, EIA, tender, project Reference is made to management, site Provide for the ongoing monitoring, conservation and AECOM (2010) for a establishment. Install leaf traps Includes 0.05 FTE hours management of estuarine vegetation and adequately Hunters Hill Tarban Monitoring discussion on issues & GPTs, provide erosion for one staff member & 17_HUN2 $345,000 $64,625 $798,899 0.68 4 address stormwater / sewage issues in Tarban Creek (in Council Creek and Works currently impacting Tarban protection. Bank rehabilitation annual maintenance Riverglade Reserve). Creek & management upstream of pedestrian bridge. /monitoring / works costs. recommendations. Remediation of weir controlling flows to the wetland.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 89 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 LANE COVE NORTH Action 17_HUN2 ARTARMON EAST RYDE Implement the Stormwater Management Action Plan currently being prepared for Hunter'sWILLOUGHBYWILLOUGHBY Hill Council RYDE LANE COVE WEST consistent with the Parramatta River Estuary CZMP and review the maintenance regimes for stormwater infrastructure to ensure existing infrastructure is LANE COVEmaintained regularly. This Action Plan will identify sites for stormwater infrastructure improvements / upgrades, Action Plan - additional GPTs and/or other stormwater quality controls in various locations, including Tarban Creek. Hunters Hill Council RYDERYDE PARRAMATTA RIVER ESTUARY COASTAL ZONE MANAGEMENT PLAN LL A A N N E E C C O O V V E E

GREENWICH

RIVERVIEW Action 20_HUN4 Legend Continue bush regeneration in theHunters Hill LGA, including Hunters Hill LGA (AECOM, 2010): - Targeted vine control and removal of young Phoenix palms, LGA Boundaries Coral trees and Green Cestrum within the upper tidal reach of Waterway Tarban Creek; - Control of emerging mangrove saplings in saltmarsh located Action 17_HUN2 within Gladesville Reserve;LINLEY POINT Provide for the ongoing monitoring, conservation - Ongoing monitoring and management of Alligator Weed in NORTHWOOD and management of estuarine vegetation and Betts Park and Gladesville Reserve; and LONGUEVILLE adequately address stormwater / sewage - Gradual removal of large Camphor Laurels in Betts Park and issues in Tarban Creek (in Riverglade Reserve). replacement with native species.

Note: Inaccuracies may be present in data provided by third parties. It is assumed that all GIS data provided by third party suppliers is sufficient and accurate for the purpose of this map. HUNTERSHUNTERS HILLHILL Tarban Creek Reserve

GLADESVILLE HUNTERS HILL FIGURE 5.5

Riverglade Reserve

HUNTLEYS COVE HUN_S07 HUNTLEYS POINT WOOLWICH ® Betts Park GREENWICH

Gladesville Reserve HUN_S01 1:16,000 Scale at A3 Kellys Bush HENLEY Metres 0 250 500 750 1,000 HUN_S04

Action 24_HUN5 Disseminate Guidelines for Environmentally Friendly Seawalls (DECC, 2009) to Council staff, particularly Action 17_HUN3 those involved in the assessment of Development Undertake management of estuarine vegetation CC A A N N A A D D A A B B A A Y Y Applications, to encourage the promotion of the ABBOTSFORDwithin Gladesville Reserve and Riverglade Reserve DRUMMOYNE guidelines. This should be undertaken on a regular Map Produced by Cardno NSW/ACT Pty Ltd (2812) to enhance saltmarsh habitats in these areas and basis so as to ensure new staff are familiar with the Date: 2013-06-05 CHISWICK Coordinate System: GDA 1994 MGA Zone 56 allow for future landward migration with sea level rise. guidelines. Planned repairs for HUN_S01, HUN_S04 Project: LJ2929 Map: G5005_ActionsHuntersHill 03.mxd 02 and HUN_S07 should comply withLEICHHARDTLEICHHARDT the guidelines Data source: NSW Land and Property Information (LPI) wherever possible. Aerial Imagery supplied by Sydney Metropolitan Catchment CC A A N N A A D D A A B B A A Y Y Management Authority and associated third party suppliers. Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.7: Leichhardt Municipal Council Action Plan Preliminary Primary Preliminary Notes on Implementation Indicative Responsibility Management Indicative Action ID Action Description Location(s) and Decommissioning (as Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Capital Value required) Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost May include the incorporation Liaise with the State Government to identify potential rehabilitation of habitat features within Leichhardt Assume 0.1 FTE hours and habitat management opportunities for incorporation in the re- seawalls proposed for 17_LEI3 Municipal Comms $ - $4,000 for a staff member for five $28,094 1.12 1 development of Callan Park, including provision for potential upgrading, as well as other Council years. impacts of climate change. activities relating to management of open space. Leichhardt Provide information to Council staff on the DECC and SMCMA Municipal Assume one week of staff Leichhardt 24_LEI5 (2009) Guidelines for Environmentally Friendly Seawalls to Council Comms $ - $1,500 members time for liaison $10,535 0.99 2 LGA promote their usage within the LGA. with internal staff. OEH, HNCMA Works located on RMS Land. Improve the quality of stormwater flows by converting a stormwater Leichhardt Leichhardt Approval and MOUs required. Detailed design and 7_LEI2 detention basin collecting runoff from the into a Municipal Works $283,150 $10,000 Annual maintenance $353,386 0.72 3 LGA RMS have provided in construction. constructed wetland system at Blackmore Park. Council principle support. Investigation into options, Based on an average project Improve the quality of stormwater flows by providing GPTs or other Leichhardt design, EIA, tender, project Leichhardt cost as reported for the Annual maintenance of 7_LEI1 WSUD features as part of stormwater harvesting schemes, to Municipal Works $705,000 management, site $28,200 $903,065 0.67 4 LGA Sustaining the Parramatta features. include the installation of a GPT at Birchgrove Oval. Council establishment, implement River project. water quality system. Upgrade and/or repair the sections of seawall identified as being poor condition and of high priority in the Estuary Process Study (AECOM, 2010). Continue to monitor the condition of other seawall For purposes of costing, Design, EIA, tender, project sections identified in the Estuary Process Study (AECOM, 2010) Leichhardt assume replacement Leichhardt management, site 21_LEI4 for any decrease in structural stability. Incorporate potential habitat Municipal Works seawalls identified as being in $1,230,000 $2,000 $1,244,047 0.33 5 LGA establishment. Upgrade opportunities into seawall designs and/or upgrades. This will Council poor condition or failing in seawalls. include the advancement of knowledge through: AECOM (2010). - Contributing research into seawall habitat and - Carrying out further research into retrofitting habitat to seawalls.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 91 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Action 7_LEI1 Improve the quality of stormwater flows by providing GPTs or other WSUD features as part of stormwater harvesting schemes, to include the installation of a GPT at Birchgrove Oval. Action Plan - Leichhardt Municipal Council PARRAMATTA RIVER ESTUARY COASTAL ZONE MANAGEMENT PLAN

Action 17_LEI3 Liaise with the State Government to identify Legend potential rehabilitation and habitat management Leichhardt LGA opportunities for incorporation in the re-development LGA Boundaries of Callan Park, including provision for potential impacts of climate change. Waterway

Note: Inaccuracies may be present in data provided by third parties. It is assumed that all GIS data provided by third party suppliers is sufficient and accurate for the purpose of this map.

FIGURE 5.6

Action 21_LEI4 Upgrade and/or repair the sections of seawall identified as being poor condition and of high ® priority in the Estuary Process Study (AECOM, 2010). Continue to monitor the condition of other seawall sections identified 1:18,000 Scale at A3 in the Estuary Process Study (AECOM, 2010) for any decrease in structural stability. Metres Action 7_LEI2 Incorporate potential habitat opportunities into seawall designs and/or upgrades. This will 0 250 500 750 1,000 Improve the quality of stormwater flows by converting include the advancement of knowledge through: a stormwater detention basin collecting runoff from the - Contributing research into seawall habitat, and City West Link into a constructed wetland system at - Carrying out further research into retrofitting Blackmore Park. habitat to seawalls.

Action 24_LEI5

Provide information to Council staff on the DECC Map Produced by Cardno NSW/ACT Pty Ltd (2812) Date: 2013-06-05 (2009) Environmentally Friendly Seawalls guideline Coordinate System: GDA 1994 MGA Zone 56 to promote their usage within the LGA. Project: LJ2929 Map: G5006_ActionsLeichhardt 03.mxd 02 Data source: NSW Land and Property Information (LPI) Aerial Imagery supplied by Sydney Metropolitan Catchment Management Authority, Bing and associated third party suppliers. Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.8: Parramatta City Council Action Plan Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost This action is likely to require the collation of data and potentially Investigate the efficacy of existing water quality controls and review Parramatta Parramatta the acquisition of additional data. 8_PAR1 maintenance regimes for stormwater infrastructure across the Investigation $75,000 $ - $75,000 1.03 1 City Council LGA It is recommended that the Parramatta LGA. analysis and reporting be linked to mapping in GIS. Will likely involve both internal Assume 0.1 FTE hours. Facilitate the incorporation of public access into new and existing communications & adoption of a Note: Cost to be born Parramatta Parramatta 25_PAR5 developments with due consideration of sensitive estuarine Planning collaborative approach with $ - $8,000 as part of normal $56,189 0.63 2 City Council LGA environments and ecological values. developers through the operations under DA/master planning process. existing council budget. Potential for migration should be If possible, purchase land upslope of the Baludarri Wetlands and Parramatta Parramatta confirmed prior to implementation 18_PAR2 Eric Primrose Reserve, to allow for landward migration of the Planning $400,000 $ - $400,000 0.54 3 City Council LGA via ground-truthing and supported ecosystems at this location caused by the long term effects of SLR. by SLR mapping. Improve public access along the foreshore by investigating the feasibility of Shared Paths. A shared pedestrian and cycle bridge Parramatta Parramatta For investigations & 25_PAR4 connecting Morton St and Alfred St, Parramatta, and a Shared Works $100,000 $39,000 $373,920 0.36 4 City Council LGA design work. Path from Pike St to South St have been previously identified as being high priority. As seawalls in the Parramatta LGA need to be repaired or upgraded this should be done in compliance with the DECC and SMCMA (2009) Guidelines for Environmentally Friendly Seawalls For purposes of costing, assume and should incorporate habitat creation opportunities wherever Parramatta Parramatta replacement seawalls identified 21_PAR3 Works $ - $50,000 $351,179 0.36 4 possible. Note: at the time of writing of this report all Parramatta City Council LGA as being in poor condition in Council owned seawalls have been repaired to "good" standard. AECOM (2010). However, some funds will be required annually to inspect and repair these seawalls into the future.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 93 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Action Plan - Parramatta City Council

PARRAMATTA RIVER ESTUARY COASTAL ZONE MANAGEMENT PLAN

Action 18_PAR2 If possible, purchase land upslope of the Baludarri Wetlands and Eric Primrose Reserve, to allow for Legend landward migration of the ecosystems at this location Parramatta LGA caused by the long term effects of sea level rise. LGA Boundaries Waterway

Note: Inaccuracies may be present in data provided by third parties. It is assumed that all GIS data provided by third party suppliers is sufficient and accurate for the purpose of this map.

Action 8_PAR1 Investigate the efficacy of existing water quality FIGURE 5.7 controls and review maintenance regimes for stormwater infrastructure across the Parramatta LGA. Action 25_PAR4 (LGA-wide, not mapped). Improve public access along the foreshore by investigating the feasibility of Shared Paths. Action 21_PAR3 A shared pedestrian and cycle bridge connecting Morton St and Alfred St, Parramatta,and a Shared As seawalls in the Parramatta LGA need to be repaired ® Path from Pike St to South St have been previously or upgraded this should be done in compliance with the identified as being high priority. DECC (2009) Guidelines for Environmentally Friendly 1:44,000 Scale at A3 Seawalls and should incorporate habitat creation opportunities wherever possible. Note: at the time of Kilometres writing of this report all Parramatta Council owned seawalls have been repaired to "good" standard. 0 1 2 However, some funds will be required annually to inspect and repair these seawalls into the future. (LGA-wide, not mapped).

Action 25_PAR5 Facilitate the incorporation of public access into new and existing developments with due Map Produced by Cardno NSW/ACT Pty Ltd (2812) consideration of sensitive estuarine environments Date: 2013-06-05 and ecological values. (LGA-wide, not mapped). Coordinate System: GDA 1994 MGA Zone 56 Project: LJ2929 Note: The cost of implementation is provided for Map: G5007_ActionsParramatta 03.mxd 02 Data Source: LPMA (LGAs, suburbs, waterways) under Councils existing budget. Imagery supplied by Bing and associated third party suppliers. Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.9: Strathfield Council Action Plan Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost Outcomes of implementation will be dependent on ongoing commitment over a longer period of time. Those Assumes GIS based Review and update the Plans of Management for Mason Strathfield Strathfield elements of the Plans relating to analysis of potential 1_STR1 and Bressington Park to incorporate consideration of the Planning $26,000 $ - $26,000 0.91 1 Council LGA accommodating SLR should inundation extents & review impacts of SLR on vegetation. provide some capacity to adapt to of action plans / lists. changes in SLR projections/observations. It has been assumed that this Assumed annual budget Provide for the ongoing monitoring, conservation and action provides for strategic support based on allowance for management of saltmarsh, swamp oak floodplain forest & management planning to support control of weeds & and mangrove communities in the Mason Park wetlands to Strathfield the existing works program. mangrove seedlings, 17_STR3 Mason Park Planning $ - $50,000 $351,179 0.90 2 enhance estuarine habitats in these areas and allow for Council Reference should be made to monitoring vegetation their future landward migration with SLR (e.g. weed AECOM (2010) for a discussion on extents, propagation & control). vegetation management relating to transplantation of Mason Park. saltmarsh species. Seek to improve public access linkages to and along the Implementation should consider the estuary foreshores by preparing a draft pedestrian / For purposes of costing need to link in with existing cycleway plan that takes into consideration existing and incl. development of a Strathfield Strathfield Planning and transport services & other pathways Cycleway maintenance, 25_STR5 proposed infrastructure in the Strathfield LGA. As a priority $3,820,000 strategy and construction of $50,000 $4,171,179 0.30 3 Council LGA Works both within the Strathfield LGA & review plan regularly. activity under the CZMP, undertake works along Powells up to 5km cycleway across beyond. Reference is made to the Creek to improve cycleway connectivity with public 5 sites. Masterplan. transport. Design, EIA, tender, project management, site establishment. Undertake naturalisation of approximately 150m of the Detailed design should consider Naturalisation of creek incl. western wall of Boundary Creek, south from the end of Strathfield Homebush potential flood impacts. Ongoing removal of existing channel 19_STR4 Works $101,250 $3,375 $124,955 0.59 4 Mandemar Avenue, Homebush West, if investigations Council West maintenance will be critical to the if required, weed control, indicate this is feasible. long term success of these projects. preparation or soil for planting, planting & establishment of selected species. Design, EIA, tender, project management, site establishment. Construct Manage public access and/or off-leash dog walking near Consultation with the community path, reinstating the Mason Park wetlands. Managing public access may Strathfield 13_STR2 Mason Park Works may be required as to selection of a $1,290,000 surrounding disturbed area $22,501 $1,448,038 0.49 5 involve formalising a walking trail, prohibiting access or Council preferred option. as required. Install fencing installing signage to indicate appropriate activities. as required around sensitive areas to prevent access. Provide signage.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 95 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 SILVERWATER

LIBERTY GROVE NEWINGTON

Action Plan - Strathfield Council SOPASOPA PARRAMATTA RIVER ESTUARY HOMEBUSH BAY CONCORD WEST COASTAL ZONE MANAGEMENT PLAN

AUBURNAUBURN Action 25_STR5 Seek to improve public access linkages to and along the CANADACANADAestuary foreshores BAYBAY by preparing a Legend Action 1_STR1 draft pedestrian / cycleway plan that takes into Strathfield LGA Bressington Park consideration existing and proposed infrastructure Review and update the Plans of Management LGA Boundaries in the Strathfield LGA. As a priority activity under the for Mason and Bressington Park to incorporate CZMP, undertake works along Powells Creek to Waterways consideration of the impacts of sea level rise on Powells Creek improve cycleway connectivity with public transport. vegetation.

Mason Park CONCORD

LIDCOMBE Note: Inaccuracies may be present in data provided by third parties. It is assumed that all GIS NORTH STRATHFIELD dataprovided by third party suppliers is sufficient and accurate for the purpose of this map. Action 13_STR2 Manage public access and/or off-leash dog walking near the Mason Park wetlands. Managing public access may involve formalising a walking trail, prohibiting access or installing Boundary Creek signage to indicate appropriate activities. Action 17_STR3 HOMEBUSH FIGURE 5.8 HOMEBUSH WESTProvide for the ongoing monitoring, conservation and management of saltmarsh, swamp oak floodplain forest and mangrove communities in the Mason Park wetlands to enhance estuarine habitats in these areas and allow for their future landward migration with sea level rise (e.g. weed control). ® STRATHFIELDSTRATHFIELD

1:15,000 Scale at A3

Metres Action 19_STR4 0 200 400 600 Undertake naturalisation of approximately 150m of the western wall ofROOKWOOD Boundary Creek, south from the end of Mandemar Avenue, Homebush West, if investigations indicate this is feasible. BURWOODBURWOOD

STRATHFIELD BURWOOD

Map Produced by Cardno NSW/ACT Pty Ltd (COE) Date: 2013-06-05 Coordinate System: GDA 1994 MGA Zone 56 Project: LJ2929 Map: G5008_ActionsStrathfield 03.mxd 02 Data source: NSW Land and Property Information (LPI) Aerial imagery supplied by Sydney Metropolitan Catchment Management Authority and associated third party suppliers Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.10: RMS (Maritime) Action Plan Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost Assumes total of one This action will likely require some week of a staff member's Endorse the use of environmentally friendly moorings in the Waterway- 16_MAR2 RMS (Maritime) Comms internal communications/education $5,000 Develop a guidance note. $1,500 time over a year to $15,535 0.95 1 Parramatta River estuary. wide activities to ensure implementation. promote seagrass friendly moorings. Continue to encourage infrastructure improvements for This action should also consider Waterway- 29_MAR4 recreational boating facilities through the Better Boating RMS (Maritime) Planning environmentally friendly features or $ - $4,000 Assume 0.05 FTE hours. $28,094 0.45 2 wide Program. approaches to providing facilities. Identification, project Subject to further investigation, consider the management, site reconfiguration of moorings where they are impacting on This action may be undertaken 12_MAR1 Waterway- establishment, relocate (or have the potential to impact on) seagrass beds. This RMS (Maritime) Works opportunistically or in a targeted $285,000 $ - $285,000 0.73 3 * wide moorings. Assumes 5% of action should be informed by the Estuary Processes Study fashion. 1,764 moorings require (AECOM, 2010). relocation. Liaise with the Department of Planning and Infrastructure to include reference to the Guidelines for RMS (Maritime) Waterway- 24_MAR3 Environmentally Friendly Seawalls (DECC and SMCMA, Planning $ - $1,500 $10,535 1.24 4 wide 2009) as part of the Sydney Regional Environmental Plan OEH (Sydney Harbour Catchment) 2005 review.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 97 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.11: Authority Action Plan Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost Provide support to the relevant asset owner(s) in prioritising stormwater maintenance and upgrade works, Assumes total of two Sydney 8_SOP1 including gross pollutants and sediment control measures, SOPA Comms $ - $ 3,000 weeks of a staff member's $21,071 1.16 1 Olympic Park so as to reduce impacts on sensitive habitats within time over a year. Sydney Olympic Park. Undertake management of swamp oak floodplain forest It has been assumed that this Assume 1.0 FTE staff and mangroves within Sydney Olympic Park to enhance Sydney action provides for strategic support 17_SOP4 SOPA Planning $ - $130,000 member & operational $913,066 0.84 2 respective habitats, including saltmarsh habitats, and allow Olympic Park and management planning to budget of $50,000 p.a. for their future landward migration with SLR. support the existing works program. Feasibility investigations should Seek external funding for priority works to restore tidal Prepare funding Sydney consider impacts on catchment 16_SOP3 exchange and stormwater flows within Sydney Olympic SOPA Works $10,000 applications, liaison with $ - $10,000 1.00 3 Olympic Park flooding and potential future SLR Park sections of and Powells Creek. relevant organisations. impacts. Provide support to Sydney Water in prioritising works to SOPA Assumes total of one Bicentennial 9_SOP2 address sewer overflows affecting estuarine wetlands Comms $ - $1,500 week of a staff member's $10,535 1.24 4 Wetlands within Bicentennial Park. Sydney Water time over a year.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 98 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 MELROSE PARK MEADOWBANK RYDERYDE RYDERYDE RYDE CAMELLIA RYDALMERE ERMINGTON PARRAMATTAPARRAMATTA

Action Plan - Sydney Newington NR Olympic Park Authority ROSEHILL

Action 17_SOP4 PARRAMATTA RIVER ESTUARY COASTAL ZONE MANAGEMENT PLAN Undertake management of swamp oak floodplain forest and mangroves within Sydney Olympic Park to enhanceRHODES respective habitats, including saltmarsh habitats, and allow for their future landward migration with sea level rise. Legend SOPA Boundary LGA Boundaries

SILVERWATER Waterway

(! Oulton Avenue Haslams Creek

Action 16_SOP3 Note: Inaccuracies may be present in data Provide support to Sydney Water in prioritising provided by third parties. It is assumed that all GIS NEWINGTON works to address sewer overflows affecting data provided by third party suppliers is sufficient and accurate for the purpose of this map. estuarine wetlands within Bicentennial Park. SOPASOPA Priority should be given to the outlet at the end of Oulton Avenue. AUBURNAUBURN HOMEBUSH BAY LIBERTY GROVE

FIGURE 5.9 Action 8_SOP1 AUBURN CC A A N N A A D D A A B B A A Y Y Provide support to the relevant asset owner(s) in prioritising stormwater maintenance and Powells Creek CONCORD WEST upgrade works, including gross pollutants and sediment control measures, so as to reduce impacts on sensitive habitats within Sydney Olympic Park. ® AUBURN 1:15,000 Scale at A3

Metres 0 250 500 750 1,000

LIDCOMBE CONCORD Action 16_SOP3 Boundary Creek Seek external funding for priority works to Map Produced by Cardno NSW/ACT Pty Ltd (COE) restore tidal exchange and stormwater flows HOMEBUSH Date: 2013-06-05 Coordinate System: GDA 1994 MGA Zone 56 within Sydney Olympic Park sections of STRATHFIELDSTRATHFIELD Project: LJ2929 Haslams Creek and Powells Creek. Map: G5009_ActionsSOPA 03.mxd 02 NORTH STRATHFIELD Data source: NSW Land and Property Information (LPI) STRATHFIELDSTRATHFIELD Aerial Imagery supplied by Sydney Metropolitan Catchment HOMEBUSH WEST HOMEBUSH WEST Management Authority and associated third party suppliers. Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.12: Sydney Water Action Plan Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost Investigate the potential for channel naturalisation of Design, EIA, tender, the following five channels as they require asset project management, site renewal and/or replacement: establishment. Removal of Detailed design should consider - SWC 50 Powells Creek existing channel if required, potential flood impacts. Ongoing - SWC 18 Brickfield Creek Catchment- removal of foreign species, 19_SYD3 Sydney Water Works maintenance will be critical to the $1,426,875 $47,563 $1,760,938 0.64 1 - SWC 53 Dobroyd wide preparation or soil for long term success of these - SWC 90 St Lukes Park planting, planting of projects. - SWC 95 . selected species, & upkeep Any future channel naturalisation projects would be & protection during subject to feasibility studies and landowner consent. establishment. This action will likely require Review of designs, Ensure that new stormwater infrastructure is designed Catchment- some internal communications / Develop an internal assume 2 weeks of a 16_SYD2 to appropriately mitigate the impacts of scour on Sydney Water Comms $5,000 $3,000 $26,071 1.13 2 wide education activities to ensure guidance note. staff member's time per estuarine habitats. implementation. year. Investigate the potential for installing additional stormwater quality improvement devices (SQIDs) to provide improved treatment of stormwater flows entering the estuary at the 11 locations indicated, within the following stormwater channels: Investigation into options, - SWC 92 Tarban Creek The installation of any future design, EIA, tender, project - SWC 55 Johnsons Creek Catchment- SQIDs would be subject to Annual maintenance of 7_SYD1 Sydney Water Works $457,500 management, site $110,000 $1,230,094 0.82 3 - SWC 62 wide feasibility studies and landowner structure. establishment, buy & install - SWC 53 Dobroyd consent. SQID, site restoration. - SWC 50 Powells Creek - SWC 13 Haslams Creek - SWC 86 Sefton Park - SWC 27 Clay Cliff Creek - SWC 42 Finalysons Creek. In consultation with Strathfield Council and the City of Design, EIA, tender, project Canada Bay, consider the addition of tide gates along Feasibility investigations should management, site Powells Creek to increase the flushing of the Mason Sydney Water consider impacts on catchment establishment, installation 19_SYD4 Park wetlands, subject to feasibility studies. If Powells Strathfield Council, Mason Park Works $ 400,000 $2,500 $417,559 0.53 4 flooding and potential future SLR of a tide gate. See also Creek stormwater channel (SWC 50) is to be City of Canada Bay impacts. cost as listed in Mason Park naturalised these works should occur concurrently, if PoM. possible and subject to feasibility studies.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 100 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Action 19_SYD4 In consultation with Strathfield Council and the City of Canada Bay, consider the addition of tide gates along Powells Creek to increase the flushing of the Mason Park wetlands, subject to feasibility studies. If Powells Creek stormwater channel (SWC 50) is to be naturalised these works should occur concurrently, if possible and subject to feasibility studies.

Action 7_SYD1 Investigate the potential for installing additional stormwater quality improvement devices (SQIDs) to provide improved treatment of stormwater flows entering the estuary at the 11 locations indicated, within the following stormwater channels: - SWC 92 Tarban Creek - SWC 55 Johnsons Creek - SWC 62 Hawthorne Canal - SWC 53 Dobroyd - SWC 50 Powells Creek - SWC 13 Haslams Creek - SWC 86 Sefton Park - SWC 27 Clay Cliff Creek - SWC 42 Finalysons Creek

Action 19_SYD3 Investigate the potential for channel naturalisation of the following five channels as they require asset renewal and/or replacement: - SWC 50 Powells Creek - SWC 18 Brickfield Creek - SWC 53 Dobroyd - SWC 90 St Lukes Park - SWC 95 Whites Creek Any future channel naturalisation projects would be subject to feasibility studies and landowner consent.

Action 16_SYD2 Ensure that new stormwater infrastructure is designed to appropriately mitigate the impacts of scour on estuarine habitats. Legend (Catchment-wide) LGA Boundaries Parramatta River

Note: Inaccuracies may be present in data provided by third parties. It is assumed that all GIS data provided by third party suppliers is sufficient Action Plan - Sydney Water and accurate for the purpose of this map. PARRAMATTA RIVER ESTUARY Map Produced by Cardno NSW/ACT Pty Ltd (2812) Date: 2013-06-05 COASTAL ZONE MANAGEMENT PLAN Coordinate System: GDA 1994 MGA Zone 56 ® Project: LJ2929 1:50,000 Scale at A3 Map: G5010_ActionsSydneyWater 03.mxd 01 Data Source: LPMA (LGAs, suburbs, waterways) Kilometers FIGURE 5.10 Imagery supplied by Bing and associated third party suppliers. 0 1 2 3 4 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.13: Committee Action Plan Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost Liaise with RMS (Maritime) to encourage the ongoing Assumes total of one Waterway- 8_COM04 collection of gross pollutants from the estuary Committee Comms $ - $1,500 week of a staff $10,535 1.49 1 wide waterway. member's time per year. Consult with the NSW Department of Planning and Infrastructure to develop a model LEP clause for inclusion into the statutory planning framework that Assumes 0.05 FTE Catchment- 2_COM02 provides for consideration of issues such as foreshore Committee Planning $ - $1,200 hours / week over 3 $8,428 1.27 2 wide building lines, riparian setbacks and public access. years. Encourage inclusion by Councils into their standard instrument LEPs. In consultation with the NSW Department of Planning and Infrastructure, develop model DCP clauses for more specific aspects of estuarine management, such as: - Environmentally friendly seawalls; Committee Assumes 0.05 FTE - Site-based WSUD; Catchment- 4_COM03 Planning $ - $ 1,200 hours / week over 3 $8,428 1.27 3 - Stormwater retention, harvesting and re-use; wide OEH, HNCMA years. - Foreshore inundation/flooding (including from SLR); - Biodiversity corridors and habitat conservation; - Public access; and - Riparian setbacks. Encourage inclusion by local Councils in their DCPs. In order to mitigate the impacts of the RiverCat on seawalls, bank condition and fringing vegetation along Waterway- Assume 0.1 FTE staff 22_COM08 large sections of the shoreline, open the dialogue and Committee Comms Refer to linked action 22_COM09. $ - $1,600 $11,238 1.23 4 wide member over 2 years. formally negotiate with Harbour City Ferries for a change in vessel that has lower vessel wake impacts. Develop and implement a communication strategy utilising the PRCG website for the implementation stage of the Parramatta River Estuary CZMP to update the general public each time an action is being Assume 2 week of a progressed or is completed. Encourage all Refer to Section 6 of the CZMP staff members time per 33_COM16 Committee N/A Comms $ 5,000 Develop strategy. $10,000 $75,236 1.23 5 organisations on the Committee to provide links on on KPIs and reporting. year, plus graphic their web pages and in regular publications (i.e. design as required. newsletters) to the PRCG website, with a view to promoting the estuary and disseminating information about the progress of the CZMP.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 102 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost Work with local Councils and other land managers that are responsible for developing and implementing Plans of Management to ensure that they provide for the The Committee's role in landward retreat (where feasible) of all significant implementation will likely involve Assumes 0.05 FTE Catchment- 17_COM07 saltmarsh, swamp oak floodplain forest and mangrove Committee Planning technical advice and review, and $ - $4,000 hours for staff member $28,094 1.12 6 wide communities. Issues to be addressed in the Plans of should be supported by HNCMA per year Management include the protection and enhancement and OEH. of the communities, and provision for areas for landward retreat. Undertake annual reporting to the PRCG and the community on trends in estuarine health for the Parramatta River estuary. Estuarine health report Annual reporting, Committee cards should be prepared quarterly and published on including both an 34_COM18 N/A Monitoring Refer to Section 6 of the CZMP. $ - $50,000 $351,179 1.08 7 the PRCG website. Reporting on trends in estuarine annual report & OEH health should be undertaken in accordance with the quarterly report cards. recommendations made with respect to monitoring and evaluation within the Parramatta River Estuary CZMP. Develop and implement an education strategy targeting key groups, such as school groups and foreshore landowners. Where possible use existing educational materials, such as the: Printing and distribution - PRCG's program Growers for Greenspace, which It is recommended that this action Catchment- Develop strategy, collate of brochures & liaison; 32_COM14 aims to promote the protection and enhancement of Committee Comms target these key groups in the first $15,000 $6,000 $57,141 1.05 8 wide existing materials. assume 0.05 FTE hours biodiversity corridors; or the instance. per year. - Environmentally friendly seawalls guideline (DECC and SMCMA, 2009), which could be provided to foreshore landowners submitting applications for new seawalls or seawall upgrades. Support the PRCG Biodiversity Sub-Committee to This action will require develop a biodiversity corridors strategy for the consultation with the NSW Parramatta River catchment area. Work with State Department of Planning and agencies and other stakeholders for this Strategy to be Assume 0.1 FTE hours Catchment- Infrastructure on development of 11_COM06 recognised within planning and development Committee Planning $ - $8,000 for staff member per $56,189 1.05 9 wide standard clauses for LEPs and frameworks including LEPs and DCPs, DA year. DCPs. Reference should be assessments and Plans of Management. Encourage made to linked actions 2_COM02 on-ground rehabilitation works undertaken within these and 4_COM04. areas to support the biodiversity corridors concept.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 103 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost This is an important activity for improving our understanding of how tidal and flood flows impact on estuarine hydrodynamics, and Design, EIA, tender, project Liaise with OEH about opportunities for installation and Committee also in terms of monitoring for the Waterway- management, site 34_COM20 operation of permanent automatic water level gauges Monitoring potential impacts of climate $60,000 $4,500 $91,606 1.01 10 wide establishment. Install 3 on the Parramatta River estuary. OEH change. With respect to the gauges. latter, a long term data set would be required, and therefore it is recommended that the gauges be installed as a priority activity. Liaise with Harbour City Ferries and the RMS to encourage them to incorporate environmentally friendly features into their designs for new (or upgraded) ferry Assume one week of Existing guideline documents and wharf access ways and bike paths (respectively). As Catchment- staff members time per 25_COM11 Committee Comms other supporting materials should $ - $1,500 $10,535 0.99 11 part of the design and site selection process, due wide year for liaison with be used where possible. consideration should be given to the protection and internal staff. enhancement of riparian zones, biodiversity corridors and estuarine vegetation. Encourage the development or review of Plans of Management for all fresh water and saltwater wetlands in the PRCG area, focusing initially on high and medium priority wetlands identified in the HNCMA Wetlands Prioritisation process in the PRCG area, Committee Encourage councils to specifically: Catchment- undertake/update PoMs 1_COM01 - Newington Nature Reserve Wetland (Plan of Planning $88,000 $4,000 $116,094 0.99 12 SOPA, Auburn City wide for wetlands in the Management for Newington Nature Reserve, 2003), Council PRCG area. - Bicentennial Park (Plan of Management for The Parklands at Sydney Olympic Park, 2010), and - Upper Duck River 1 and 2 (Upper Duck River Riparian and Wetland Plan of Management - funded by HNCMA and to be completed 2012). Implement an estuarine health monitoring program for the Parramatta River estuary in accordance with the Based on cost of Refer to the recommendations on recommendations of the CZMP, and the requirements implementation of the Committee monitoring and evaluation in Detailed design of of the NSW MER Strategy, that coordinates the Catchment- 34_COM17 Monitoring Section 6 of the CZMP. $50,000 monitoring program, $200,000 $1,454,716 0.97 13 monitoring activities undertaken by the various wide monitoring program, OEH Linked actions include establish frameworks. stakeholders, including the Sydney Harbour Catchment relies on substantial 32_COM16 and 34_COM20. Water Quality Improvement Plan data coordinated by volunteer support. the HNCMA. Undertake a review of the Parramatta River Estuary Refer to Sections 6 and 7 of the 34_COM19 Committee N/A Planning $ - $35,000 $245,825 0.93 14 CZMP every 5 to 10 years. CZMP.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 104 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost Assume 0.1 FTE hours Liaise with Harbour City Ferries on opportunities to for a staff member & Waterway- 22_COM09 mitigate the impact of RiverCat wash on the foreshore Committee Comms Refer to linked action 22_COM08. $ - $38,000 $30,000 for $266,896 0.92 15 wide and, where feasible, rehabilitate impacted areas. rehabilitation costs per year. Continue to coordinate the provision and maintenance Replacement or Graphic design, tender & of educational and prohibited activities signage at Catchment- installation of up to 5 32_COM15 Committee Comms $75,000 install 8 new signs in first $40,000 $355,943 0.90 16 appropriate locations around the estuary by the local wide signs per year, plus year. councils. maintenance. Coordinate the efforts of the relevant local Councils Committee (Parramatta, City of Ryde and Hunters Hill) to extend Parramatta City Catchment- Assume 0.05 FTE 25_COM12 the Parramatta Valley Cycleway Shared Path to the Council, City of Comms $ - $4,000 $28,094 0.90 17 wide hours per year. end of the Parramatta River estuary (near Cockatoo Ryde, Hunters Hill Island). Council Collate and distribute guidelines to Councils and Printing and distribution foreshore landowners on best practice bank and Catchment- Collate and update as of brochures & liaison; 23_COM10 foreshore erosion control and rehabilitation techniques Committee Comms $5,000 $6,000 $47,141 0.86 18 wide required existing materials. assume 0.05 FTE hours that promote the use of riparian and estuarine per year. vegetation. Address recreational needs across the catchment in a two-step process as follows: 1) Conduct a recreational needs analysis that incorporates the DP&I's Accessing Sydney Harbour Policy and RMS (Maritime)'s Better Boating Policy, and 2) Develop and implement a strategy for the integrated management of recreational amenity across Catchment- Undertake needs analysis 29_COM13 Committee Planning $150,000 $ - $150,000 0.77 19 administrative boundaries for the estuary as a whole, wide and prepare strategy. giving consideration to: - The need to maintain and improve access and address safety issues (e.g. installation of safety barriers where appropriate); - Liaison between local Councils; and - Identification of priorities for management. When updating the CZMP, consider the implications of Refer to Section 2.5 & Appendix Review and refinements to Catchment- 39_COM21 the coastal hazard assessment (Section 2.5 & Committee Planning C of the CZMP, which contains $25,000 the CHA incorporating new $ - $25,000 0.68 20 wide Appendix C) for management. the CHA report. data obtained.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 105 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Preliminary Primary Preliminary Indicative Responsibility Management Notes on Implementation and Indicative Action ID Action Description Location(s) Capital Cost Comments Annually Annually Recurrent Ratio

Supporting Category Decommissioning (as required) Capital Value Recurrent Cost Comments Priority Net Present

Organisation Cost Cost:Benefit Cost Councils and the Committee should liaise with the HNCMA to prioritise and implement bank stabilisation works, focusing on upper catchment areas, based on the findings of the HNCMA's Waterways Health Strategy (EarthTech, 2007). The following recommendations from the Strategy are based on a desktop study only and must be ground-truthed prior to implementation: Investigation into options 1) Revegetate riparian zone, particularly focusing on Maintenance (feasibility studies), design, riverbank stabilisation through revegetation for the Feasibility investigations, requirements will Catchment- EIA, tender, project 10_COM05 Parramatta River main channel left hand bank between Committee Works including ground-truthing required $2,000,000 $100,000 reduce over time as $2,702,358 0.62 21 wide management, site the confluence with Duck River downstream to the prior to implementation. plants become establishment, & revegetate eastern extent of George Kendall Riverside Park, established. sites. 2) Revegetate riverbanks and riparian zone on both banks of the Girraween Creek (between and the western Railway line), 3) Revegetate riverbanks and riparian zone on both banks of the Lalor Creek (between M7 to confluence with Blacktown Creek), and 4) Revegetate riverbanks and riparian zone along the whole creek length of .

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 106 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Table 5.14: Generic Action Plan

Generic Management Action Description Action ID* Category Land Use Planning and Development: When undertaking reviews of planning instruments or engaging in strategic land use planning, seek consistency with the Parramatta River Estuary CZMP and, where possible, update the relevant instrument as required. Primary Objective Addressed: 1A Consult with the NSW Department of Planning and Infrastructure to develop a model LEP clause for inclusion into the statutory planning framework that provides for consideration of 2_GEN01 Planning issues such as foreshore building lines, riparian setbacks and public access. Councils to incorporate into their standard instrument LEPs. Land Use Planning and Development: Develop provisions under Development Control Plans that provide for the incorporation of best practice WSUD and ecological connectivity along the estuary foreshores for sites subject to re- development. Primary Objective Addressed: 2E In consultation with the NSW Department of Planning and Infrastructure, develop model DCP clauses for more specific aspects of estuarine management, such as: - Environmentally friendly seawalls; - Site-based WSUD; - Stormwater retention, harvesting and re-use; 4_GEN02 Planning - Foreshore inundation/flooding (including from sea level rise); - Biodiversity corridors and habitat conservation; - Public access; and - Riparian setbacks. Councils to incorporate into DCP.

Water and Sediments: Retrofit appropriate WSUD features in existing urban areas of the catchment targeting locations upstream from where stormwater runoff and associated pollutants are impacting sensitive estuary locations. Primary Objective Addressed: 3A

Improve the quality of stormwater flows by providing GPTs or other WSUD features as part 7_GEN03 Works of stormwater harvesting schemes.

Water and Sediments: Modify, upgrade or repair existing SQIDs, stormwater infrastructure and management practices as required to maintain or improve their effectiveness. This should include development of maintenance schedules for existing infrastructure where they are not currently in place. Primary Objective Addressed: 2B

Investigate the efficacy of existing water quality controls and review maintenance regimes 8_GEN04 Investigation for stormwater infrastructure across the LGA.

Conduct a critical review of existing stormwater management practices to determine: - The efficacy of maintenance regimes of existing GPTs, and - Identify locations where additional gross pollutant trapping is required. 8_GEN05 Investigation Include a review of current street sweeping activities in catchment areas. Reference should be made to AECOM (2010) for further discussion of the issues relevant to this action. Water and Sediments: Work with Sydney Water to prioritise maintenance and upgrade of the sewerage network within the catchment on an ongoing basis to reduce sewage overflows. This activity should include investigations into the incidence of illegal private connections to the sewerage and / or stormwater network. Primary Objective Addressed: 2C Provide support to Sydney Water in prioritising works to address sewer overflows affecting 9_GEN06 Communications the estuary.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 107 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Generic Management Action Description Action ID* Category

Estuarine Ecology: Develop and implement a strategy for the coordinated management of estuarine and riparian biodiversity across administrative boundaries for the estuary as a whole. The strategy should incorporate biodiversity corridors and SLR consideration, to ensure the ongoing provision of habitat and connectivity between habitat areas. Primary Objective Addressed: 4A Support the PRCG Biodiversity Sub-Committee to develop a biodiversity corridors strategy for the Parramatta River catchment area. Work with State agencies and other stakeholders for this Strategy to be recognised within planning and development frameworks including 11_GEN07 Planning LEPs and DCPs, DA assessments and Plans of Management. Encourage on-ground rehabilitation works undertaken within these areas to support the biodiversity corridors concept. Estuarine Ecology: Undertake improvements to foreshore infrastructure where possible to reduce their impacts on aquatic habitats. Consider the need, where feasible, to relocate or decommission infrastructure where it is impacting on environmentally sensitive locations. Primary Objective Addressed: 4A Ensure that new stormwater infrastructure is designed to appropriately mitigate the 16_GEN08 Communications impacts of scour on estuarine habitats.

Estuarine Ecology: Undertake works to provide for the ongoing preservation of estuarine and riparian habitats under climate change conditions. This should include the enhancement of existing habitats where there is possibility of retreat, or establishing additional habitat areas as required, to maximise habitat under SLR conditions. Primary Objective Addressed: 4A

Within Plans of Management, ensure provision for the landward retreat (where feasible) of all significant saltmarsh, swamp oak floodplain forest and mangrove communities. Issues 17_GEN09 Planning to be addressed in Plans of Management include the protection and enhancement of the communities, and provision for areas for landward retreat. Undertake enhancement of estuarine vegetation as a stabilisation method in areas of 17_GEN10 erosion, and to protect existing seawalls from further erosion, for locations as identified in Works the Estuary Processes Study (AECOM, 2010). Estuarine Ecology: Undertake ongoing monitoring and management of aquatic and terrestrial weeds (incl. noxious weeds) and introduced species (both flora and fauna). Primary Objective Addressed: 4C Continue bush regeneration in all reserves of the Parramatta River estuary catchment, 20_GEN11 including undertaking the recommendations made in the Estuary Processes Study Works (AECOM, 2010). Estuarine Ecology: Improve the environmental value of existing seawalls through the addition of habitat, where feasible. Primary Objective Addressed: 4D

Incorporate potential habitat opportunities into seawall designs and / or upgrades. This will include the advancement of knowledge through: 21_GEN12 Works - Contributing research into seawall habitat, and - Carrying out further research into retrofitting habitat to seawalls.

Periodically monitor the condition of seawalls along that portion of the Parramatta River 21_GEN13 within the LGA. If seawalls require attention incorporate the principles of the DECC and Monitoring SMCMA (2009) Environmentally Friendly Seawalls guideline. Bank Condition: All management authorities involved in the building, design and approval of new seawalls, or major upgrades of existing seawalls, should promote their compliance with the Environmentally Friendly Seawalls guideline (DECC and SMCMA, 2009) within legislative constraints. Primary Objective Addressed: 6B

Provide information to Council staff on the DECC and SMCMA (2009) Environmentally 24_GEN14 Communications Friendly Seawalls guideline to promote their usage within the LGA.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 108 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3 Parramatta River Estuary Coastal Zone Management Plan Prepared for Parramatta River Estuary Management Committee

Generic Management Action Description Action ID* Category

Human Usage and Recreation: Maintain and improve existing public access (i.e. bike and walking paths) for the Parramatta River estuary to provide transport linkages throughout the LGAs, giving consideration to sensitive environmental locations. Primary Objective Addressed: 7A Facilitate the incorporation of public access into new and existing developments with due 25_GEN15 Planning consideration of sensitive estuarine environments and ecological values. Incorporate environmentally friendly features into the designs for new (or upgraded) foreshore infrastructure. As part of the design and site selection process, due 25_GEN16 Works consideration should be given to the protection and enhancement of riparian zones, biodiversity corridors and estuarine vegetation. *The first number in the generic action ID is the relevant option number.

24 June 2013 Cardno (NSW/ACT) Pty Ltd Page 109 N:\COE\Data\Doc\2013\Reports.2013\Rep2701v3.doc Version 3