POSITION OF SURVEYS IN PROGRESS (2013-14)

"as on 31st July"

S. BB Survey State Target Status Remarks Unit N No Sanctioned Year 2011-12 1 1 New line between Barmer- Sept,14 Estimate Prepared & ROR Dy.CE/C/ Palanpur. is being calculated & under JU Finance vetting. 2 2 RECT survey for New BG Haryana/ Dec,14 Under finance vetting. Dy line between Alwar-Charkhi Rajasthan CE/C/III/ Dadri. JP 3 3 New Line between Taranga- Gujrat/ Sept,14 Field work completed and Dy.CE/C/ Abu Road via Ambaji. Rajasthan estimate under preparation. II/AII Sanctioned Year 2012-13 4 4 RECT survey for aNew Gujrat Dec,14 Place "Goradu" could not be Dy.CE/C/ linebetween Dhanera- traced out. Rly. Bd. vide JU Goradu HQ letter dated 20.11.12 has been requested for rechecking. 5 5 RECT survey for a New line Gujrat/ Dec,14 Work of fixing of alignment Dy.CE/C/ between Palanpur-Ambaji- Rajasthan is under progress. II/AII Abu Road (76 km) 6 6 RECT survey for a New line Gujrat Sept,14 Under finance vetting since Survey for only Dy.CE/C/ between Dhanera-Tharad- April,2013. Dhanera- Tharad section JU Vav-Suigam (75 km) is being done. Tharad- Vav-Suigam section is covered in new line survey of border area of Rajasthan (BB No. 15). 7 7 Updating of Jalore-Falna Rajasthan Sept,14 Finance vetted the proposal Dy.CE/C/ New line (72 km) now case is under appr of JU GM in order to send to Rly Bd. S. BB Survey State Target Status Remarks Unit N No 8 8 RECT survey for New line Rajasthan/ Aug,14 Field work completed and Dy.CE/C/ between Sardarsahar-Sirsa Haryana estimate under preparation. BKN (94 km)

9 9 RECT survey for New line Rajasthan Done Survey report sent to Rly. Length - 110.60 km, Dy.CE/C/ Nathdawara-Kankroli- Bd. on 30.05.13. Rly Bd Cost - Rs. 916.87 cr, UDZ Gangapur-Bhilwara (115 asked approval of CSTE on ROR = (-) 6.56%. km) proposed Signalling Scheme,vide letter dt :04/11/2013. Now Revise survey report has been submitted to Rly Bd on 5th,May. Rly Bd shelved the projet vide letter 3/WI/NWR/NL/5/Survey dt 17/06/2014. 10 10 RECT survey for New line Rajasthan Sept,14 Under Finance vetting since Survey for -Neem Dy.CE/C/ between Neem Ka Thana 04/07/2013 Ka Thana to be done. GC/JP and Sujangarh via Sikar, Sikar-Sujangarh section Salasar and Udaipurwati already covered in (150 km) Nokha-Sikar survey for which report already sent to Rly. Bd. 11 11 RETS survey of By Pass line Rajasthan Sept,14 Updating in progress. This survey sanctioned Dy.CE/C/ between Salawas and Banad vide Rly. Bd’s letter no. JU (35 km) 2012/W-I/Genl./ Surveys/Budget dt. 19.07.12 Sanctioned Year 2013-14 12 12 PETS for doubling between Raj & Dec,14 Survey included in current Requirement of Land is Dy.CE/C/ Bathinda - Suratgarh (150 Haryana year.Estimate is under Identified. HMH km) preparation is to be started. S. BB Survey State Target Status Remarks Unit N No 13 13 RET survey for New line Rajasthan Oct,14 Estimate Prepared & under Dy.CE/C/ between Pipar Road - scrutiny & Finance vetting JU Bhopalgarh - Asop - since 27th,June. Shankwas - Mundwa - Nagore (96 km) 14 14 RETS for New line between Raj March,15 Survey included in current Dy.CE/C/ Gajsinghpur - Sadulpur via year.Estimate is under HMH Padampur, Golowala, preparation is to be started. Rawatsar, , Dadrewa (315 km) 15 15 PETS for New line between Rajasthan Oct,14 Route selected and estimate Dy.CE/C/ Lunkaransar - under preparation BKN Sardarshahar (82 km) 16 Updating New BG line RECT Raj Updated survey estimate This survey was done by Dy.CE/C/ Anoopgarh to Bikaner returned by Finance on Northern Railway in HMH conducted by NR year 2005 3/04/2014. "Now year 2005. Revision (155 km). case is under Vetting". done vide Rly.Bd. Letter No. 2004/W- 2/SY/NWR/1 dt 13.06.08. Length - 151.56 km, Cost - Rs. 707.38 cr, ROR = (-) 7.24%. S. BB Survey State Target Status Remarks Unit N No 17 Marwar-Nathdwara Raj (i) The revised estimate (i)The survey of Marwar Dy.CE/C/ (167Km) GC & Bari Sadri- duly vetting by Finance on -Mavli-Bari Sadri (GC) UDZ Neemuch (48.35Km) New 13/02/2013 & appd by submitted by NWR to BG Line. GM/NWR on 13/02/2013 & Rly Bd on submitted to Rly Bd on 14/05/2012,out of which 12/02/2013. Marwar-Mavli (GC) (ii) Revised updated santioned by Rly Bd RECT survey report of vide letter No. 2008/W- proposal is vetted by 1/NWR/GC/2 dt 11.8.10 Finance on28/01/2014 & . after approwal of GM (ii) The survey of Bari Report submitted to Rly Bd Sadri -Neemuch (NL) on 28th,April. submitted by WR. (iii)Rly Bd vide letter (iii) However Rly Bd Dt:27th,may asked for santioned only Marwar- consolidated report based Mavli (GC). on updated cost as (iv) Now The proposal submitted report is of 2012- of BalanceMarwar- 13. Nathdwara (GC) & Bari Updation of Marwar- Sadri -Neemuch (NL) is Nathdwara by NWR & of prepared & vetted by Bari sadri-Neemuch by WR finance is now being is in process". processed for appr of GM for onward submission to Rly Bd. (v) Sailent Feature:Length - Marwar-Nathdwara (167Km) GC & Bari Sadri- Neemuch(48.35Km) New BG Line,Cost - Rs. 1687.18cr, ROR = (-) 1.36%.

Survey Completed

"as on 31st July"

S.N BB Survey State Target Status Remarks Unit No Year 2001-02 1 6 PECT survey for doubling of Raj Survey report sent to Rly. Bd. Length - 152.99 km, Cost - Rs. Dy.CE/C/JU Phulera – Merta Road on 07.06.07. 283.33 cr, doubling (152.99 km) ROR = (+) 11.43%. Year 2005-06 2 3 RECT survey for a new line Raj Survey report sent to Rly. Bd. Report shelved vide Rly. Bd’s Dy.CE/C/BKN from Anupgarh-Khajuwala- on 05.02.08. letter No. 2008/W1/NWR/NL/4 Ramgarh-Jaisalmer (431 km) dt. 14.07.08. Length - 431 km, Cost - Rs. 914.49 cr, ROR =(-) 5.30%. 3 4 RECT survey for a new line Raj Survey report sent to Rly. Rly. Bd's letter No.2008/W- Dy.CE/C/AII from to Kota (145 km) Bd. on 15.02.08. 1/NWR/NL/06 dt. 17.06.08, Reply of Rly. Bd.'s Project is financially unviable observations sent on and operationally not desirable. 05.12.11. Length - 145 km, Cost - Rs. 821.64 cr, ROR = (-) 6.61%. Work sanctioned in 2013-14 wide PB Item No 6. Year 2006-07 4 9 RECT survey for new line Raj Survey report sent to Rly. Bd. Report shelved vide Rly. Bd’s Dy.CE/C/BKN between Anupgarh to Kolayat on 05.02.08. letter No. 2008/W1/NWR/NL/4 via Khajuwala (199.92 km) dt. 14.07.08. Length - 199.92 km, Cost - Rs. 441.06 cr, ROR = (-) 5.37% . S.N BB Survey State Target Status Remarks Unit No 5 10 RECT survey for new line Raj Survey report sent to Rly. Not found feasible vide Rly. Dy.CE/C/ between Loharu-Bhiwani (65 Bd. on 03.01.07.Proposal Bd’s letter No. HMH km) Part of S.No No 25 has not been found feasible 2007/W2/NWR/NL/02 dt. due to heavy through 29.06.07. forward & limited Length - 58.83 km, Cost - Rs. availability of Resources 99.85 cr, (Rly. BD's letter No. ROR = (-) 6.16%. 2007/W2/NWR/NL/02 Survey dated 29/06/2007) Year 2008-09 6 1 Updating survey for new line Raj Survey report sent to Rly. Lenth - 27 km, Cost - Rs. Dy.CE/C/BKN Bhiwadi to Rewari BG line (27 Bd. on 27.01.09. 153.73 cr, km) ROR = (-) 13.53%. 7 2 RECT survey for of a new line Raj Survey report sent to Rly. Length - 50.10km, Cost - Rs. Dy.CE/C/GC between Amarpura (Jorasi) to Bd. on 06.04.09. 162.09 cr, Chirawa via Tathwari and ROR = (-) 5.40%. Singhana (50.10 km) 8 14 RECT survey for a new line Raj Survey report sent to Rly. Length - 17 km, Cost - Rs. 55.01 Dy.CE/C/GC between Jhunjhunu-Pilani via Bd. on 06.04.09. cr, Chirawa (17 km) ROR = (-) 6.54%. 9 Updating New BG line RECT Raj Updated survey estimate This survey was done by Dy.CE/C/ Anoopgarh to Bikaner returned by Finance on Northern Railway in year 2005. HMH conducted by NR year 2005 3/04/2014 & now under Revision done vide Rly.Bd. (155 km). compliance. Letter No. 2004/W- 2/SY/NWR/1 dt 13.06.08.Length - 151.56 km, Cost - Rs. 707.38 cr, ROR = (-) 7.24%. Year of 2009-10 10 RECT survey for BG doubling Raj Survey report sent to Rly. Length - 354.33 km, Cost - Rs. Dy.CE/C/AII between Ajmer-Palanpur Bd. on 14.12.09. 1379.87 cr, (354.33 km) ROR = (+) 16.49%. S.N BB Survey State Target Status Remarks Unit No 11 RECT survey for Ajmer- Raj Survey report sent to Rly. Length -165 km, Cost - Rs. Dy,CEC/II/AII Sawaimadhopur via Tonk Bd. on 23.2.11. Rly Bd 873.71 cr, New line (165 km) observed the that capital ROR = (-) 7.25%. cost is based on two year old rate & asked the updatation of Cost & ROR,vide letter no 2012/W-1/NWR/Nl/8 Survey Dt:04/11/2013.The updated proposal has been submitted yo Rly Bd on16/12/2013,vide letter Dt:13/12/2013. 12 5 RECT survey for new BG line Raj Survey report sent to Rly. Rly. Bd's observations replied on Dy.CE/C/JU between Didwana-Ringus via Bd. on 30.07.09 01.02.10. Report shelved vide Khatushyam ji (105.50 km) Rly. Bd’s letter No. 2009/WL/NWR/NL/15/5 dt. 20.07.10. Length - 105.50 km, Cost - Rs. 330.23 cr, ROR = (-) 5.81%. 13 18 RECT survey for New line Raj Survey report sent to Rly. Reply of Rly. Bd’s letter No. Dy.CE/C/I/ between Churu-Nohar via Bd. on 31.01.11. 2010/W/1/NWR/NL/3/ Survey BKN Tarangar New BG Line.(Km dated 10.03.11 was sent on 118.700 km) 26.07.2011. Railway Board vide letter No. 2010/W/1/NWR/NL/3/ Survey dated 19.10.11 stated that "project may not be taken up for the time being as it is highly unremunerative". Length - 118.70 km, Cost - Rs. 342.20 cr, ROR = (-) 7.65%. 14 RECT survey for BG doubling Raj Survey report sent to Rly. This survey was announced in Dy.CE/C/III/ between Bandikui-Alwar Bd. on 4.10.11. Compliance Budget speech on 13.02.09. JP (60.37 km) of Rly. Bd.'s observation sent Length - 60.37 km, Cost - Rs. to Board on 11.11.11. 247.29 cr, S.N BB Survey State Target Status Remarks Unit No ROR = (+) 13.86%. Work sanctioned in 2013-14 wide PB No. 28 15 RECT survey for New BG line Raj Survey report sent to Rly. This survey was announced in Dy.CE/C/JU between Samdari-Phalodi Bd. on 13.02.12. Budget speech on 13.02.09. (156.40 km) Length - 156.40 km, Cost - Rs. 514.944 cr, ROR = (-) 7.38%. 16 RECT survey for new line Raj Survey report sent to Rly. Survey sanctioned vide Rly. Dy.CE/C/JU between Bilara-Bar (51.15 km) Bd. on 09.02.12. Bd’s letter No. 2009/W- 1/Genl./Survey/09-10 dt 16.09.09.Length - 46.7 km, Cost - Rs. 204.83 cr, ROR = (-) 10.95%. 17 New Line survey from Raj Survey report sent to Rly. Survey sanctioned as per Rly. Dy.CE/C/ Sardarshar to Sadulpur via Bd. on 27.03.12. Bd’s letter No. HMH Tarangar (104.019 km) 2009/W/1/NWR/6/Petition dt 05.11.09. Length - 102.838 km, Cost - Rs. 515.84 cr, ROR = (-) 6.95%. 18 Updating survey of Mavli-Bari Raj Survey report sent to Rly. Survey sanctioned as per Rly. Dy.CE/C/UDZ Sadri GC (82.01 km). Bd. on 20.02.12. Bd’s Letter No. 2009/W- 1/NWR/GC/1 dt 26.05.10. Project shelved vide Rly. Bd.'s letter No. 2009/W-I/NWR/GC/1 Survey dt. 23.07.12. Length - 82.01 km, Cost - Rs.311.32 cr, ROR = (-) 5.24%. Work sanctioned in 2013-14 wide PB Item No 8. S.N BB Survey State Target Status Remarks Unit No 19 RECT survey for new line Harya Survey report sent to Rly. Survey sanctioned vide Rly. Bd's Dy.CE/C/ between Dabwali-Kalanwali na Bd. on 14.05.12. letter No. 2009/W- HMH via Sirsa (33.70 km) 1/Genl./Survey/09-10 dt 16.9.09. Length - 31.824 km, Cost - Rs. 187.14 cr, ROR = (-) 7.93%. 20 New BG line Sardarshar to Raj Survey report sent to Rly. Survey sanctioned vide Rly. Bd's Dy.CE/C/I/ Suratgarh & Ratangarh to Bd. on 21.05.12. letter No. BKN Sardarshara (118.840 km) 2009/W/1/NWR/6/Petition dt 05.11.09. Length - 118.84 km, Cost - Rs.392.427 cr, ROR = (-) 7.59% Year 2010-11 21 9 RECT survey for New BG line \ (i) Survey report sent to Rly. Length - 58.50 km, Cost - Rs. Dy.CE/C/JU between Jaisalmer-Sanu- Bd. on 03.11.11. (ii) Reply 236.93 cr, Hamira (55 km). of Rly. Bd.'s observation sent ROR = (+) 15.58%. on 27.01.12. Work sanctioned in 2013-14 wide PB No. 5 22 10 Updating survey report Raj Survey report sent to Rly. Length - 59 km, Cost - Rs. Dy.CE/C/I/AII Pushkar-Merta New BG line Bd. on 04.02.11. 322.98 cr, (59 km) ROR = (-)7.65%. Work sanctioned in 2013-14 wide PB No. 7# 23 73 Updating survey report Nokha- Raj Survey report sent to Rly. Length -189.083 km, Cost - Rs. Dy.CE/C/GC Sikar New BG line (209.615 Bd. on 12.03.12. 819.11 cr, km). ROR = (-) 7.43. 24 100 Updating survey report Raj Survey sent to Rly. Bd. on Length - 149 km, Cost - Rs. Dy.CE/C/I/ Sardarshar-Hanumangarh 04.10.11. 403.96 cr, BKN New BG line (149 km). ROR = (-) 8.09%. S.N BB Survey State Target Status Remarks Unit No 25 PECT survey for Bhiwani- Raj & Survey report sent to Rly. Survey sanctioned as per Rly. Dy.CE/C/ Loharu-Pilani-Churu (136.74 Harya Bd. on 29.05.12. Survey sent Bd's letter HMH km). na to Rly. Bd. on 04.10.11. No.2009/W/1/Genl/survey/09-10 Survey sent to Rly. Bd. on dated 24.6.2010.Length - 136.74 04.10.11. km, Cost - Rs. 617.79 cr, ROR "Proposal shelved due to = (-) 7.07%. very poor traffic potential and severe resource crunch faced by Railways (Rly. BD's letter No. 2012/W1/NWR/NL/25 Survey dated 04.09.13." 26 Updating survey report to Raj Survey report sent to Rly. Survey sanctioned as per Rly. Dy.CE/C/UDZ Marwar-Mavli GC. Bd. on 14.05.12. Bd's Letter No. 2008/W- 1/NWR/GC/2 dt 11.8.10. Length - 160.00 km, Cost - Rs.1287.80 cr, ROR = (-) 0.10% 27 New Line - Jodhpur-Agolai- Raj Survey report sent to Rly. Survey sanctioned as per Rly. Dy.CE/C/JU Shergarh-Phalsund. Bd. on 26.04.12. Bd's letter No. 2010/W- 1/Genl/Survey/10-11 dt. 04.02.11. Length - 116 km, Cost - Rs. 428.593 cr, ROR = (-) 8.04%. 28 Jodhpur-Jaisalmer Doubling Raj Survey report sent to Rly. Survey sanctioned as per Rly. Dy.CE/C/JU (290 km). Bd. on 13.12.12. Bd's letter No. 2010/W - "Rly Bd Shelved the Survey 1/Genl/Survey/10-11 dt. vide letter 04.02.11. 2012/NL/NWR/40 dated Length - 290.46 km, Cost - Rs. 28/10/2013." 1032.17 cr, ROR = (-) 0.02%. S.N BB Survey State Target Status Remarks Unit No 29 Marwar-Nathdwara (167Km) Raj (i) The revised estimate (i)The survey of Marwar -Mavli- Dy.CE/C/UDZ GC & Bari Sadri- duly vetting by Finance on Bari Sadri (GC) submitted by Neemuch(48.35Km) New BG 13/02/2013 & appd by NWR to Rly Bd on Line. GM/NWR on 13/02/2013 & 14/05/2012,out of which submitted to Rly Bd on Marwar-Mavli (GC) santioned 12/02/2013. by Rly Bd vide letter No. (ii) Revised updated RECT 2008/W-1/NWR/GC/2 dt survey report of proposal is 11.8.10 . vetted by Finance (ii) The survey of Bari Sadri - on28/01/2014 & after Neemuch (NL) submitted by approwal of GM Report WR. submitted to Rly Bd on (iii) However Rly Bd santioned 28th,April. only Marwar -Mavli (GC). (iii)Rly Bd vide letter (iv) Now The proposal of Dt:27th,may asked for BalanceMarwar-Nathdwara consolidated report based (GC) & Bari Sadri -Neemuch on updated cost as (NL) is prepared & vetted by submitted report is of 2012- finance is now being processed 13. for appr of GM for onward "Updation of Marwar- submission to Rly Bd. Nathdwara by NWR & of (v) Sailent Feature:Length - Bari sadri-Neemuch by WR Marwar-Nathdwara (167Km) is in process". GC & Bari Sadri- Neemuch(48.35Km) New BG Line,Cost - Rs. 1687.18cr, ROR = (-) 1.36%. Year 2011-12 30 8 RECT survey for New BG bye Harya Survey report sent to Rly. Length - 6.0 km, Cost - Dy.CE/C/III/ pass line at Rewari from na/ Bd. on 19.01.12. Rs.33.608 cr, ROR = (+) JP Alwar-Sadulpur ((8 km). Rajas 18.23%. than S.N BB Survey State Target Status Remarks Unit No 31 15 New line for providing Raj (i) Survey report sent to Rly. New line from Tharad road, Dy.CE/C/JU connectivity to border areas of Bd. on 16.11.12. (ii) Santalpur, Suigam, Vav, Raj. From Santalpur, Suigam, Revised cost sent to Rly. Bd Chhansara (existing). Vav, Sanchor, Radhanpur. on 11.06.13. Length - 80.75 km, Cost - Rs. 370.71 cr, ROR = (-) 7.59%. Revised Cost - Rs.374.64 cr(gross), Revised ROR = (-) 7.59%. 32 16 New line between Jaisalmer- Rajas Survey report sent to Rly. Survey report of Jaisalmer- Dy.CE/C/JU Kandla.(Barmer-Bhabher) than/ Bd. on 31.08.12. Revised Barmer already sent to Rly. Bd. Gujra cost sent on 14.03.13. This report only covers Barmer- t "Survey Shelved by Rly Bd Bhabhar section. Line from vide letter Bhabhar to Kandla via 2012/Wl/Nl/NW32 Survey Radhanpur-Santalpur already Dt:25/11/2013". exists. Length - 193.94 km, Cost - Rs. 798.727 cr, ROR = (-) 7.65%. 33 17 New line between Nagaur- Raj Survey report sent to Rly. Length - 148 km, Cost - Dy.CE/C/JU Phalodi. Bd. on 01.3.12. Rs.436.122 cr, ROR = (-) 7.76%. 34 21 Updating survey between Raj Survey report sent to Rly. Length - 145.00 km, Cost - Rs. Dy.CE/C/JU Jaisalmer-Barmer New BG Bd. on 08.05.12. Revised 516.305 cr, line (145 km). cost sent to Rly. Bd on ROR = (-) 7.74%. 11.06.13. Revised Cost - Rs. 517.70 cr(gross), Revised ROR = (-) 7.74%.

35 22 Updating survey between Raj Survey report sent to Rly. Length - 92.00 km, Cost - Rs. Dy.CE/C/I/AII Devli-Tonk-Sakatpura New Bd. on 08.01.13. 705.42 cr, BG line (62 km). ROR = (-) 17.76%. S.N BB Survey State Target Status Remarks Unit No 36 RECT survey for Patch Harya Rly Bd vide letter 2011/w- Survey for Manheru - Hisar Dy.CE/C/ Doubling between Manheru - na 1/NWR/WT/2012-13/DL/13 patch doubling sanctioned vide HMH Hisar (73.500 km) DT:3/09/2012 asked Rly. Bd's letter No. 2011/W- clarification regarding I/NWR/WP 2012-13/DL/13 covered/not covered coal dated 08.12.11. route for Thermal Length - 73.500 km, Cost - Plants.Revise Ror is under Rs.413.399 cr, Finance vetting since ROR = (+) 6.35%. 07/04/14. Survey report sent to Rly. Bd. on 10.07.12 37 22 Up DatingSurvey Tonk- Raj (i)Survey Report Initially (i) Length - 165.00 km, Dy.CE/C/AII/I swaimadhopur NL (165Km) Submitted on Vide letter (ii) Gross Cost - Rs.709017 Cr, CAO/C/W/401/AII- ROR = (-) 7.(iii) Revised Gros SWM,via Cost - Rs. 873.72 Cr, (iv) Tonk,dated:22/02/2011. (ii) Revised ROR = (-) 7.25%. Rly Bd Retuned the proposal stating rates are of 2010-11 hence Revise Cost along with Revise ROR is to submitted vide letter 2010/W- 1/NWR/NL/8/Survey dated 04/11/2013.(iii) Updated Revise surver & ROR submitted to Rly Bd vide letter CAO/C/W/401/AII- SWM,via Tonk,dated:13/12/2013.