DEPARTMENT OF GENERAL SERVICES

PROJECT MANUAL

FOR REPAIRS TO THE BOAT RAMPS

AT SANDY POINT STATE PARK ANNE ARUNDEL COUNTY,

FOR THE DEPARTMENT OF NATURAL RESOURCES

DGS PROJECT NO.: P-021-102-010

ISSUE DATE: September 9, 2014

PROJECT COST CLASSIFICATION: Class “C”

State of Maryland

Department Of Natural Resources Joseph P. Gill, Secretary Tawes State Office Building Annapolis, Maryland 21401

Department of General Services Board of Public Works Alvin C. Collins, Secretary Martin O’Malley Governor 301 West Preston Street Peter Franchot, Comptroller Baltimore, MD 21201 Nancy K. Kopp, Treasurer

Engineer Whitman, Requardt & Associates, LLP 801 S. Caroline Street Baltimore, MD 21231

“Minority Business Enterprises are Encouraged to Respond to this Solicitation Notice.”

TABLE OF CONTENTS

DIVISION 0 – PROCUREMENT & CONTRACTING REQUIREMENTS

- Notice To Bidders - Solicitation Fact Sheet (eMarylandMarketplace attachment) - Instructions to Bidders for Construction Projects (March 2007) (eMarylandMarketplace attachment) - General Conditions for Construction Projects (August 2013) (eMarylandMarketplace attachment) - Bid Proposal Affidavit (eMarylandMarketplace attachment) - Contractors Questionnaire - Bid Bond, if applicable (eMarylandMarketplace attachment) - Minority Business Enterprise Utilization Procedures (July 2014) (eMarylandMarketplace attachment) - MBE Attachment D1-A Forms (eMarylandMarketplace attachment) - List of Prevailing Wage Rates, if applicable - Addenda, if any (eMarylandMarketplace attachment) - List of Drawings -Pre-Bid Conference/Site Visit-Each bidder is encouraged to attend the scheduled pre-bid conference/site visit, although is not mandatory. However, if there is any Minority Business Enterprise (MBE Goal) whatsoever on this solicitation, ALL BIDDERS ARE REQUIRED TO ATTEND THE PRE_BID CONFERENCE/SITE VISIT (SEE COMAR 21.11.03.09.C.(2)(e).

Important Note: Bidders are to download ALL the above referenced documents located in the eMaryland Solicitation Review and Response Section, under Forms and Attachments, and thoroughly read each document.

Section 00100 Professional Certification (page 1 – 1) Section 00500 Directory (page 1 – 1) Section 00600 Drawing List (page 1 – 1)

DIVISION 1 – GENERAL REQUIREMENTS

Section 01010 Summary of Work (page 1 – 3) Section 01020 Permits (page 1 – 1) Section 01025 Measurement and Payment (page 1 – 1) Section 01090 Reference Standards (page 1 – 2) Section 01210 Preconstruction Conference (page 1 – 1) Section 01220 Progress Meetings (page 1 – 2) Section 01270 Unit Prices (page 1 – 4) Section 01310 Progress Schedules (page 1 – 1) Section 01330 Submittals (page 1 – 9) Section 01380 Construction Photographs (page 1 – 2) Section 01732 Selective Demolition (page 1 – 4)

Repairs to the Boat Ramps TOC-1 TABLE OF CONTENTS Sandy Point State Park Anne Arundel County, MD P-021-102-010 DIVISION 2 – SITE CONSTRUCTION

Section 02010 Subsurface Exploration (page 1 – 1) Section 02200 Earthwork, Excavation, Trenching and Backfilling (page 1 – 15) Section 02464 Vinyl Sheet Piling (page 1 – 8)

DIVISION 3 – CONCRETE

Section 03013 Maintenance of Cast-in-Place Concrete (page 1 – 6) Section 03301 Miscellaneous Cast-in-Place Concrete (page 1 – 5)

DIVISION 6 – WOOD, PLASTICS, AND COMPOSITES

Section 06108 Exterior Rough Carpentry (page 1 – 3)

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

Section 07920 Joint Sealants (page 1 – 7)

APPENDIX A – Wetlands License

APPENDIX B – Environmental Correspondence

APPENDIX C – Geotechnical Report

APPENDIX D – Sub-aquatic Survey of Sandy Point State Park Boat Ramps

Repairs to the Boat Ramps TOC-2 TABLE OF CONTENTS Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 00100

PROFESSIONAL CERTIFICATION

Repairs to the Boat Ramps PROFESSIONAL CERTIFICATION Sandy Point State Park P-021-1 02-0 I 0 The contract documents for the indicated public improvements were prepared under my supervision and to the best of my knowledge, information and belief, they comply with the requirements ofthe Building Code ofthe State of Maryland. I hereby certify that these documents were prepared or approved by me, and that I am a duly licensed Professional Engineer under the laws ofthe State ofMaryland.

ENGINEER Whitman Requardt & Associates, LLP /s/ 1/dAnthony--- U. Olsen, PE 801 S. Caroline Street MD Registered No. 19376 Baltimore, MD 21231

END OF SECTION

Repairs to the Boat Ramps 00100-1 PROFESSIONAL CERTIFICATION Sandy Point State Park Anne Arundel County, MD P-021-1 02-010

SECTION 00500

DIRECTORY

DIRECTORY: CONTACT

Contracting Agency

State of Maryland David Hall, P.E. Department of General Services Capital Projects Manager

301 West Preston Street Room #1405 Baltimore, Maryland 21201-2369

Using Agency

Maryland Department of Natural Resources Dave Decker Regional Engineer Southern Region Engineering & Construction Matapeake Marine Terminal 305 Marine Academy Drive Stevensville, MD 21666

Engineer Whitman Requardt & Associates, LLP Pam Strickland, P.E. 801 S. Caroline Street Senior Project Engineer Baltimore, MD 21231

APPROVING AUTHORITIES

State of Maryland Compliance Program Department of the Environment Darwin Feheley, Chief Water Management Administration Regulatory Services Coordination 1800 Washington Boulevard Baltimore, Maryland 21230

Repairs to the Boat Ramps 00500-1 DIRECTORY Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 00600

DRAWING LIST

SHEET DRAWING TITLE

GENERAL 1. G1.1 COVER SHEET

CIVIL 2. C1.1 EXISTING SURVEY PLAN

STRUCTURAL 3. S1.1 DEMOLITION PLAN SECTION AND DETAILS 4. S1.2 BOAT RAMP SITE PLAN AND STRUCTURAL GENERAL NOTES 5. S4.1 ENLARGED PLAN - BOAT RAMP AND SECTION 6. S5.1 STRUCTURAL DETAILS 7. S5.2 STRUCTURAL DETAILS

END OF SECTION

Repairs to the Boat Ramps 00600-1 DRAWING LIST Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 01010

SUMMARY OF WORK

PART 1 – GENERAL

1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specifications, apply to this Section.

1.2 WORK COVERED BY CONTRACT DOCUMENTS:

A. Work of this Contract consists of installing new support sheeting at the outboard end of the existing concrete boat ramp, as shown in the construction documents for the Repairs to the Boat Ramps at Sandy Point State Park. The project is located within Mezick Pond at Sandy Point State Park in Anne Arundel County, Maryland. The address of the park is:

Sandy Point State Park 1100 East College Parkway Annapolis, Maryland 21409

B. The Contractor shall provide all labor, equipment, materials, supplies, insurance, permits, etc. necessary to install the sheeting and to repair the boat ramps at Sandy Point State Park.

C. The Contractor shall perform the following in accordance with the attached Drawings and the Specifications:

a. Mobilization and demobilization; b. Stakeout of construction controls; c. Installing, maintaining, and removing temporary erosion and sediment control measures and devices; d. Installing, maintaining, and removing dewatering and temporary cofferdam to allow the work be done in the dry. e. Selective demolition of the existing timber bumper at the end of the boat ramps, selective demolition of a portion of the existing timber sheeting, selective demolition of a portion of the existing concrete ramp, and selective demolition of a portion of the existing timber piers. f. Furnish all material, including but not limited to, exterior rough carpentry, vinyl sheet pile, cast-in-place concrete, riprap, and aggregate. g. All specified earthwork. h. Removal and restoration of timber stringers and deck planks on the wood pier to allow installation vinyl sheet pile and other associated work underneath the wood pier. i. Replacement of diagonal timber bracing members that are not embedded in the concrete slab. j. Performed concrete and void repairs on the existing concrete boat ramp slabs. k. Restoration and stabilization of all disturbed areas.

Repairs to the Boat Ramps 01010-1 SUMMARY OF WORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 D. The Drawings and written Contract Documents are intended to indicate as clearly as practicable the Work to be done. The CONTRACTOR must realize, however, that construction details cannot always be accurately anticipated and that in executing the Work, field conditions may require reasonable modifications in the details of the Drawings and the work involved. Changed field conditions from those indicated on the Drawings must be brought to the attention of the ENGINEER in writing by the CONTRACTOR in accordance with Section 3.03 of the General Conditions. Work under the Contract shall be performed to meet field conditions to the satisfaction of the ENGINEER and in strict conformance with his instructions, the Drawings, the Specifications, and the terms, conditions, and covenants of the Contract Documents in accord with their true intent and full meaning.

1.3 QUALIFICATIONS OF THE CONTRACTOR:

A. The Contractor shall be licensed in the State of Maryland as a Contractor to perform work associated with this project.

B. The Contractor shall have a minimum of three (3) years experience performing construction work of a similar nature within the last five (5) years.

C. Upon request, the Contractor shall supply the Procurement Officer a list of similar projects, which have been successfully completed by the Contractor within the last five (5) years.

D. The Contractor shall be registered with the Maryland Department of the Environment in accordance with Chapter 286 of the 2010 laws of Maryland. See item D in the Wetlands License under Appendix A.

1.4 SITE VISIT:

A. All prospective bidders are encouraged to visit the Pre-bid Conference and familiarize themselves with all the requirements for the project. Failure to do so will not relieve the successful bidder from complying with all requirements of these specifications at no additional cost to the Owner.

B. Please notify the Sandy Point State Park prior to any site visit, other than the Pre-bid Conference, by calling the Park Ranger, at 410-974-2149.

1.5 CONTRACTOR USE OF PREMISES:

A. Coordinate schedule and access with the Sandy Point State Park.

B. The Contractor shall make his own arrangements, coordinating with Sandy Point State Park and DGS Inspector, for storage of materials and any construction yard required to execute this project. Any costs shall be at the Contractor’s expense.

C. The Contractor shall assume full responsibility for protection and safekeeping of materials and products under this contract.

Repairs to the Boat Ramps 01010-2 SUMMARY OF WORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 D. The Contractor shall remove all debris associated with the work from the project site and dispose of all debris in an approved method at an approved disposal site at the Contractor’s expense.

E. The Contractor’s personnel (i.e., welders, carpenters, equipment operators, etc.) shall be skilled craftsmen and fully qualified by experience and technical training to perform their assigned responsibilities.

F. The Contractor shall take all necessary precautions and measures to protect all Sandy Point State Park property from damage. The Contractor shall repair all damage caused by his operations to all public and private property including roads, walks, curbs, boardwalk, utilities, trees, shrubs, etc. to the satisfaction of the Park Manager and DGS Inspector, and leave the property in an as good or better condition than found.

G. The Contractor shall coordinate his operations with the DNR to prevent conflicts with their operations. The Contractor shall maintain navigation, safety and lighting in accordance with all Coast Guard and applicable State codes and regulations.

H. Contractor shall use a barge crane to perform the work as necessary. No heavy construction equipment shall be permitted on the roads and parking lot of the park.

1.6 SCHEDULE OF WORK:

A. The Contractor shall perform all work Monday through Friday during normal working hours 7:00 am to 5:00 pm, unless permission is given in writing by the Managers and DGS Inspector to do otherwise.

B. The Contractor shall notify the Managers and DGS Inspector seven (7) days prior to his start of work and a minimum of 48 hours prior to the delivery of the construction materials.

END OF SECTION

Repairs to the Boat Ramps 01010-3 SUMMARY OF WORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 01020

PERMITS

PART 1 – GENERAL

The information provided in this section has been added to supplement the requirement of the general conditions.

1.1. RELATED DOCUMENTS:

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specifications, apply to this Section.

1.2. SECTION INCLUDES:

A. Wetland License. See Appendix.

1.3. RELATED SECTIONS:

A. General Conditions – Section 6.02, Permits and Licenses

END OF SECTION

Repairs to the Boat Ramps 01020-1 PERMITS Sandy Point State Park Anne Arundel County, MD P-021-102-010

SECTION 01025

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Payment for all materials furnished and work done under this Contract shall be made under the lump sum bid in the Bid Form and Section 8: Payments. The CONTRACTOR shall not be entitled to receive additional compensation for anything furnished or done except for such extra work authorized in writing by the DGS INSPECTOR or PROJECT MANAGER.

B. Should the CONTRACTOR be directed by authorized personnel to perform additional work not covered by the unit price bid, such Work shall be considered extra work and shall be paid for as specified in the General and Supplemental Conditions.

1.2 BASE BID

A. The lump sum price bid shall include full compensation for all supervision, labor, materials, equipment, tools and incidentals necessary to satisfactorily construct, complete, in place the works to the Boat Ramps at Sandy Point State Park. The Work includes, but is not necessarily limited to, the following:

1. Mobilization and demobilization; 2. Stakeout of construction controls; 3. Installing, maintaining, and removing temporary erosion and sediment control measures and devices; 4. Installing, maintaining, and removing of dewatering and temporary cofferdam to allow the work be done in the dry. 5. Selective demolition of the exiting timber bumper at the end of the boat ramps, portion of the existing timber sheeting, portion of the existing timber piers, and portion of the existing concrete ramp. 6. Furnish all material, including but not limited to, exterior rough carpentry, vinyl sheet pile, cast-in-place concrete and sand above the riprap. 7. All specified earthwork, except for unit price work items specified in Section 01270. 8. Removal and restoration of timber stringers and deck planks on the wood pier to allow installation vinyl sheet pile and other associated work underneath the wood pier. 9. Replacement of diagonal timber bracing members that are not embedded in the concrete slab. 10. Restoration and stabilization of all disturbed areas.

1.3 UNIT PRICE

A. Contractor shall submit a unit price for all unit price items listed in Specification Section 01270 Unit Price. The submitted unit price will be used as the basis for payment for unit price items furnished.

END OF SECTION

Repairs to Boat Ramps 01025-1 MEASUREMENT AND PAYMENT Sandy Point State Park Anne Arundel County, MD P-021-102-010

SECTION 01090

REFERENCE STANDARDS

PART 1 – GENERAL

1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SECTION INCLUDES:

A. Applicability of Reference Standards.

B. Provision of Reference Standards at Site.

C. Acronyms used in Contract Documents for Reference Standards. Source of Reference Standards.

1.3 QUALITY ASSURANCE:

A. For products or workmanship specified by association, trade or Federal Standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. The date of the standard is that in effect as of the Bid Date, or date of Owner-Contractor Agreement when there are no bids, except when a specific date is specified.

C. When required by individual Specification Section, obtain a copy of standard. Maintain copy at jobsite during submittals, planning and progress of the specific work, until Substantial Completion.

1.4 APPLICABILITY OF REFERENCE STANDARDS:

A. For products or workmanship specified by association, trade or Federal Standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

1.5 SCHEDULE OF REFERENCES:

AASHTO American Association of State Highway and Transportation Officials 444 North Capitol Street, N.W. Washington, D.C. 20001

ADA Americans with Disabilities Act

AGC Associated General Contractors of America

Repairs to the Boat Ramps 01090-1 REFERENCE STANDARDS Sandy Point State Park Anne Arundel County, MD P-021-102-010 ANSI American National Standard Institute 1430 Broadway New York, NY 10018

ASTM American Society for Testing and Materials 1916 Race Street Philadelphia, PA 19103

COMAR Codes for the State of Maryland Division of State Documents 11 Bladen Street Annapolis, Maryland 21401

FS Federal Specification General Services Administration Specifications and Consumer Information Distribution Section (WFSIS) Washington Navy Yard, Bldg 197 Washington, D.C. 20407

MDOT Maryland Department of Transportation State Highway Administration 707 North Calvert Street Baltimore, Maryland 21203-0717

OSHA Occupational Safety and Health Administration 200 Constitution Avenue, N.W. Washington, D.C. 20210

PART 2 – PRODUCTS

(Not Used)

PART 3 – EXECUTION

(Not Used)

END OF SECTION

Repairs to the Boat Ramps 01090-2 REFERENCE STANDARDS Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 01210

PRECONSTRUCTION CONFERENCE

PART 1 – GENERAL

The information provided in this section has been added to supplement the requirements of the general conditions.

1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Other Division 1 Specification Sections, apply to this Section.

1.2 SECTION INCLUDES:

A. Contractor participation in preconstruction conference.

1.3 RELATED SECTIONS:

A. Section 01010 – Summary of Work

B. Section 01220 – Progress Meetings

1.4 PRECONSTRUCTION CONFERENCE:

A. DGS Area Supervisor will schedule conference within 15 days after Notice of Award.

B. Attendance: Owner, Engineer and Contractor.

C. Notes and Minutes of the Meeting: to be provided by Engineer.

PART 2 – PRODUCTS

(Not Used)

PART 3 – EXECUTION

(Not Used)

END OF SECTION

Repairs to the Boat Ramps 01210-1 PRECONSTRUCTION CONFERENCE Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 01220

PROGRESS MEETINGS

PART 1 – GENERAL

The information provided in this section has been added to the supplement the requirements of the General Conditions.

A. The Contractor shall schedule and administer construction progress meetings, called Progress Meetings at regularly scheduled intervals following NTP. There shall be progress meetings at least twice monthly.

B. The Contractor shall prepare agenda based on the last Progress Meeting, and establish and confirm each Progress Meeting to the Contractor in advance of the next Progress Meeting date.

C. The Contractor shall conduct the meetings, record minutes and distribute copies within 5 days after the Progress Meeting to participants and to others affected by decisions made at the Progress Meetings.

D. Location of Meetings: As coordinated by the Owner. A Field Trailer will not be required for this project; however, Contractor may set up his own trailer.

E. Attendance: Owner, Engineer, Contractor, job superintendent, subcontractors and supplies as appropriate to agenda; professional consultants may attend as appropriate and the Construction and Inspection Testing firm (CITF) representative may attend if required.

F. Minimum Agenda:

1. Review of minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems and decisions.

4. Identification of problems that impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Review delivery schedules.

7. Maintenance of progress schedules.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards

Repairs to the Boat Ramps 01220-1 PROGRESS MEETINGS Sandy Point State Park Anne Arundel County, MD P-021-102-010 12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to work.

G. Documents: The General Contractor shall prepare for distribution at each Progress Meeting

1. Schedule Narrative: A description of the work by trade or system. Describe the past two weeks effort and the next two weeks effort. Indicate where the two week scheduled tasks were not accomplished and report on the methods to be employed to mitigate the schedule slippage.

2. Look ahead schedule: Two 2-week back and 4-week look ahead bar chart developed from the CPM program.

3. Request for Information (RFI) log.

4. Proposed Change Order (PCO) log.

5. Approved Change Order (ACO) log.

6. Submittal log.

7. New Business: General Contractor produced itemized list of issues to be discussed.

PART 2 – PRODUCTS

(Not Used)

PART 3 – EXECUTION

(Not Used)

END OF SECTION

Replacement of Marine Facility 01220-2 PROGRESS MEETINGS DNR Piney Point Aquaculture Center St. Mary’s County, MD G-019-090-010

SECTION 01270

UNIT PRICES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions, Division 01 Specification Sections, and Division 0 contracting requirements, including the latest edition of the “Instructions to Bidders for Construction Projects”, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for unit prices.

1.3 DEFINITION

A. “Unit Price”: A Unit Price is the cost per unit of measure specified for materials and labor. An extended Unit Price is the Unit Price multiplied by an estimated quantity specified in the contract documents. This cost, or extended Unit Price, shall be included in the Total Bid amount. Actual usage of Unit Price items will be verified by the Owner or Owner's representative. Adjustment to the contract sum based on actual verified usage will be made by Change Order.

Should the contractor be required to perform Unit Price work in excess of the estimated quantity specified, an equitable adjustment shall be made to the contract price, subject to Sections 3.06 and 3.07 of the General Conditions. Similarly, should the contractor perform Unit Price work less than that estimated, an equitable adjustment shall be made to the contract price, subject to Sections 3.06 and 3.07 of the General Conditions.

In determining the amount of any such adjustment to the contract price, the amount of the increase to the contract price will be calculated using the Unit Price bid by the contractor, or a reasonable price, whichever is less. The amount of any credit due the State will be calculated using the Unit Price bid by the contractor or a reasonable price, whichever is greater.

A Unit Price bid shall be the sum total price per unit for such items to include without limitation all work, labor, materials, bailing, shoring, removal, overhead, profit, insurance, etc. Unit price is a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

1.4 UNIT PRICE PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

Repairs to Boat Ramps 01270-1 UNIT PRICES Sandy Point State Park Anne Arundel County, MD P-021-102-010 B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit price items are specified in 3.1 SCHEDULE OF UNIT PRICES below.

C. Before proceeding with unit price work items, the Contractor shall allow the Owner to perform visual observation of the existing condition of the concrete boat ramps after the work area is dewatered. Contractor shall clean the existing concrete ramp to the satisfaction of the Owner to perform visual observation to determine the locations of deteriorated concrete and voids underneath the existing concrete slabs that need to be repaired. Contractor shall obtain approval from the Owner before proceeding with unit price work items. Owner reserves the right to refuse payment if Contractor fails to obtain approval from Owner before proceeding with unit price work items.

D. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

E. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 SCHEDULE OF UNIT PRICES

A. Base Bid:

1. Description: The cost to complete all work as described in the project manual including any addenda, and the project drawings for the DGS project number P-021-102-010, Repairs to the Boat Ramps, Sandy Point State Park; but excluding the following unit prices.

2. Unit of Measurement: Lump Sum

B. Unit Price No. 1 - Crack Repair:

1. Description: Crack repair in accordance with contract documents. The work includes but not limited to cleaning the concrete surface as required for preparation of work, routing the existing cracks as indicated, installing all primer, backing rods, and sealant material, finishing sealant material and touchup repairs as required.

2. Unit of Measurement: Linear Foot

3. Contractor shall submit a unit price for crack repair during the bid process. The submitted unit price will be used as the basis for payment for all crack repair furnished.

4. Estimated Linear Feet of Crack Repair: 1000 LF

5. Refer to Specification Section 07920 “Joint Sealants” Repairs to Boat Ramps 01270-2 UNIT PRICES Sandy Point State Park Anne Arundel County, MD P-021-102-010 C. Unit Price No. 2 - Spall Repair :

1. Description: Spall repair in accordance with contract documents. The work includes but not limited to cleaning the concrete surface as required for preparation of work, saw cutting the area around the spalls as indicated, demolishing and removing delaminated concrete, removal of bond inhibiting debris, installation of bonding agent, placement and finishing of repair mortar, and touchup repairs as required.

2. Unit of Measurement: Square Foot.

3. Contractor shall submit a unit price for spall repair during the bid process. The submitted unit price will be used as the basis for payment for all spall repair furnished.

4. Estimated Square Feet of Crack Repair: 1500 SF.

5. Refer to Specification Section 03013 Maintenance of cast-in-place concrete for specification repair.

D. Unit Price No. 3: Void Repair :

1. Description: Void repair in accordance with contract documents. The work includes but not limited to selective demolition as required to fill the voids beneath the existing boat ramp concrete slab with grout.

2. Unit of Measurement: Cubic Foot.

3. Contractor shall submit a unit price for void repair during the bid process. The submitted unit price will be used as the basis for payment for all void repair furnished.

4. Estimated Cubic Feet of Void Repair: 405 CF.

5. Refer to Specification Section 02200 Earthwork, Excavation, Trenching, and Backfilling for specification.

E. Unit Price No. 4: Miscellaneous Cast-In-Place Concrete:

1. Description: Provide miscellaneous Cast-in-place concrete in accordance with contract documents. The work includes but not limited to saw cut exiting concrete slabs, provide steel reinforcement, dowel reinforcement bars into adjacent existing slabs, and provide new cast-in-place concrete at areas deemed more economical to replace an area of slab instead of spall repair.

2. Unit of Measurement: Cubic Yard.

3. Contractor shall submit a unit price for miscellaneous cast-in-place concrete during the bid process. The submitted unit price will be used as the basis for payment for all miscellaneous cast-in-place concrete furnished.

Repairs to Boat Ramps 01270-3 UNIT PRICES Sandy Point State Park Anne Arundel County, MD P-021-102-010 4. Estimated Cubic Yards of Miscellaneous Cast-in-place Concrete: 60 CY.

5. Refer to Specification Section 03301 Miscellaneous Cast-in-place Concrete for specification.

F. Unit Price 5: Riprap:

1. Description: Provide riprap in accordance with the contract documents. The work includes but not limited to excavation, grading, subgrade preparation, and placement of riprap.

2. Unit of Measurement: Cubic Yard.

3. Contractor shall submit a unit price for riprap during the bid process. The submitted unit price will be used as the basis for payment for all riprap furnished.

4. Estimated Cubic Yards of Riprap: 100 CY.

5. Refer to Specification Section 02200 Earthwork, Excavation, Trenching, and Backfilling for specification.

G. Unit Price 6: MDSHA NO. 57 stone:

1. Description: Provide MDSHA No. 57 stone in accordance with the contract documents. The work includes but not limited to excavation, grading, subgrade preparation, and placement of MDSHA No. 57 stone.

2. Unit of Measurement: Cubic Yard.

3. Contractor shall submit a unit price for MDSHA No.57 stone during the bid process. The submitted unit price will be used as the basis for payment for all MDSHA No. 57 stone furnished.

4. Estimated Cubic Yards of MDSHA No.57 stone: 100 CY.

5. Refer to Specification Section 02200 Earthwork, Excavation, Trenching, and Backfilling for specification.

END OF SECTION

Repairs to Boat Ramps 01270-4 UNIT PRICES Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 01310

PROGRESS SCHEDULES

PART 1 – GENERAL

PROGRESS SCHEDULE

A. In lieu of CPM schedule, as specified in Section 7.06 J. of the General Conditions, a Gantt Chart Schedule will be accepted. At a minimum, the following information will be included in the Contractor’s progress schedule.

1. Material & Shop Drawing submittal and review time 2. Lead time on critical materials and equipment 3. Construction Tasks and Activities

B. All tasks and/or activities shall have a duration period not to exceed 21 calendar days.

C. The progress schedule will reflect a rational, chronological progression of the work, as the contractor proposes to complete the project.

D. The progress schedule will demonstrate any interrelationship such as “Predecessor/Successor” relationship, between tasks.

E. All tasks and/or activities shall be cost-loaded. The accepted Progress Schedule will become the basis for payment. All payments to the contractor will be made based on the completion of these tasks and/or activities. Payments made to the contractor, for partial completion of any task, shall not exceed 65% of the task’s monetary value.

END OF SECTION

Repairs to the Boat Ramps 01310-1 PROGRESS SCHEDULES Sandy Point State Park Anne Arundel County, MD P-021-102-010

SECTION 01330

SUBMITTALS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.4 ACTION SUBMITTALS

A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time required for making corrections or revisions to submittals noted by Engineer and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule. 2. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

3. Format: Arrange the following information in a tabular format:

Repairs to the Boat Ramps 01330-1 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 a. Scheduled date for first submittal. b. Specification Section number and title. c. Submittal category: Action; informational. d. Name of subcontractor. e. Description of the Work covered. f. Scheduled date for Engineer's final release or approval. g. Scheduled date of fabrication.

1.5 SUBMITTAL ADMINISTRATIVE REQUIREMENTS

A. Engineer's Digital Data Files: Electronic digital data files of the Contract Drawings will not be provided by Engineer for Contractor's use in preparing submittals.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity. 2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule. 3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals. 4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Engineer's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Engineer will advise Contractor when a submittal being processed must be delayed for coordination. 2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal. 3. Resubmittal Review: Allow 14 days for review of each resubmittal.

D. Paper Submittals: Place a permanent label or title block on each submittal item for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block. 2. Provide a space approximately 6 by 8 inches on label or beside title block to record Contractor's review and approval markings and action taken by Engineer . 3. Include the following information for processing and recording action taken:

a. Project name. Repairs to the Boat Ramps 01330-2 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 b. Date. c. Name of Engineer. d. Name of Construction Manager. e. Name of Contractor. f. Name of subcontractor. g. Name of supplier. h. Name of manufacturer. i. Submittal number or other unique identifier, including revision identifier.

1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 06100.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 06100.01.A).

j. Number and title of appropriate Specification Section. k. Drawing number and detail references, as appropriate. l. Location(s) where product is to be installed, as appropriate. m. Other necessary identification.

4. Additional Paper Copies: Unless additional copies are required for final submittal, and unless Engineer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.

5. Transmittal for Paper Submittals: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Engineer will return without review submittals received from sources other than Contractor.

a. Transmittal Form for Paper Submittals: Provide locations on form for the following information:

1) Project name. 2) Date. 3) Destination (To:). 4) Source (From:). 5) Name and address of Engineer. 6) Name of Construction Manager. 7) Name of Contractor. 8) Name of firm or entity that prepared submittal. 9) Names of subcontractor, manufacturer, and supplier. 10) Category and type of submittal. 11) Submittal purpose and description. 12) Specification Section number and title. 13) Specification paragraph number or drawing designation and generic name for each of multiple items. 14) Drawing number and detail references, as appropriate. 15) Indication of full or partial submittal. 16) Transmittal number. 17) Submittal and transmittal distribution record. 18) Remarks.

Repairs to the Boat Ramps 01330-3 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 19) Signature of transmitter.

E. Options: Identify options requiring selection by Engineer.

F. Deviations and Additional Information: On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Engineer on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal.

G. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal. 2. Note date and content of revision in label or title block and clearly indicate extent of revision. 3. Resubmit submittals until they are marked with approval notation from Engineer's action stamp.

H. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

I. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer's action stamp.

PART 2 - PRODUCTS

2.1 SUBMITTAL PROCEDURES

A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Action Submittals: Submit ten (10) paper copies of each submittal unless otherwise indicated. Engineer will return two copies. 2. Informational Submittals: Submit two paper copies of each submittal unless otherwise indicated. Engineer will not return copies. 3. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. a. Provide a notarized statement on original paper copy certificates and certifications where indicated.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are not suitable for use, submit as Shop Drawings, not as Product Data. Repairs to the Boat Ramps 01330-4 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable:

a. Manufacturer's catalog cuts. b. Manufacturer's product specifications. c. Standard color charts. d. Statement of compliance with specified referenced standards. e. Testing by recognized testing agency. f. Application of testing agency labels and seals. g. Notation of coordination requirements. h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams showing factory-installed wiring. b. Printed performance curves. c. Operational range diagrams. d. Clearances required to other construction, if not indicated on accompanying Shop Drawings.

5. Submit Product Data before or concurrent with Samples.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products. b. Schedules. c. Compliance with specified standards. d. Notation of coordination requirements. e. Notation of dimensions established by field measurement. f. Relationship and attachment to adjoining construction clearly indicated. g. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches, but no larger than 24 by 36 inches. 3. Submit Shop Drawings in the following format:

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package. 2. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample. b. Product name and name of manufacturer. c. Sample source. Repairs to the Boat Ramps 01330-5 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 d. Number and title of applicable Specification Section. e. Specification paragraph number and generic name of each item.

3. For projects where electronic submittals are required, provide corresponding electronic submittal of Sample transmittal, digital image file illustrating Sample characteristics, and identification information for record. 4. Disposition: Maintain sets of approved Samples at Project site, available for quality- control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use. b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

5. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit one full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer's product line. Engineer will return submittal with options selected.

6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit three sets of Samples. Engineer will retain two Sample sets; remainder will be returned.

1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated. 2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.

E. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated. 2. Manufacturer and product name, and model number if applicable. 3. Number and name of room or space.

Repairs to the Boat Ramps 01330-6 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 4. Location within room or space.

F. Coordination Drawing Submittals: Comply with requirements specified in Division 1 Section "Project Management and Coordination."

G. Contractor's Construction Schedule: Comply with requirements specified in Division 1 Section "Construction Progress Documentation."

H. Application for Payment and Schedule of Values: Comply with requirements specified in Division 1 Section "Payment Procedures."

I. Test and Inspection Reports and Schedule of Tests and Inspections Submittals: Comply with requirements specified in Division 1 Section "Quality Requirements."

J. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Division 1 Section "Closeout Procedures."

K. Maintenance Data: Comply with requirements specified in Division 1 Section "Operation and Maintenance Data."

L. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of Engineers and owners, and other information specified.

M. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

N. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

O. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

P. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

Q. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

R. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

S. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency. Repairs to the Boat Ramps 01330-7 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 T. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

1. Name of evaluation organization. 2. Date of evaluation. 3. Time period when report is in effect. 4. Product and manufacturers' names. 5. Description of product. 6. Test procedures and results. 7. Limitations of use.

U. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

V. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

W. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

X. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

PART 3 - EXECUTION

3.1 CONTRACTOR'S REVIEW

A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer.

B. Project Closeout and Maintenance Material Submittals: See requirements in Division 1 Section "Closeout Procedures."

C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

Repairs to the Boat Ramps 01330-8 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 3.2 ENGINEER'S ACTION

A. Action Submittals: Engineer will review each submittal, make marks to indicate corrections or revisions required, and return it. Engineer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.

B. Informational Submittals: Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements. Engineer will forward each submittal to appropriate party.

C. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Engineer.

D. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

E. Submittals not required by the Contract Documents may be returned by the Engineer without action.

END OF SECTION

Repairs to the Boat Ramps 01330-9 SUBMITTALS Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 01380

CONSTRUCTION PHOTOGRAPHS

PART 1 – GENERAL

1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Other Division 1 Specification Sections, apply to this Section.

1.2. SECTION INCLUDES:

A. Construction Photography.

B. Submittals.

1.3 RELATED SECTIONS:

A. Section 01010 – Summary of Work.

1.4 PHOTOGRAPHY:

A. Contractor to provide color photographs of site and construction throughout progress of Work.

B. Take photographs on cutoff date for each Application for Payment.

C. Take photographs on a bi-monthly basis and submit in compliance with Article “Digital” Files and Color Prints” of this Section.

D. Take up to 20 photographs of preconstruction conditions. Subject material and views will be determined by DGS/Engineer.

1.5 PHOTOGRAPH FORMAT:

A. Full color; 4 prints of each view specified, except for preconstruction photographs where 2 prints will be sufficient.

B. Paper: Single weight.

C. Finish: Smooth surface, glossy.

D. Size: 8 inches by 10 inches. Mount in acid-free vinyl 3 inch “D” ring type three ring holders. Provide loose leaf white binders for photograph filing with Owner’s name, job title, and project number on front cover and binder side cover, and binder side shall have see through sleeves for protection of title information.

E. Identification: List name of Project, phase, orientation of view, date and time of view, name and address of photographer, and photographer’s numbered identification of exposure.

Repairs to the Boat Ramps 01380-1 CONSTRUCTION PHOTOGRAPHS Sandy Point State Park Anne Arundel County, MD P-021-102-010 PART 2 – PRODUCTS

2.1 DIGITAL FILES AND COLOR PRINTS:

A. Deliver digital files and color prints to Owner, at each Application for Payment submission with contract sheet. Catalog and index Files in chronological sequence; provide typed table of contents.

B. Provide photographer’s release of copyrights at job completion.

PART 3 – EXECUTION

3.1 TECHNIQUE:

A. Provide factual presentation.

B. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

3.2 VIEWS:

A. Consult with Owner Representative or Engineer as required for instructions on views required.

3.3. CONTRACTOR’S COORDINATION:

A. Deliver prints and files with each Application for Payment with transmittal letter.

END OF SECTION

Repairs to the Boat Ramps 01380-2 CONSTRUCTION PHOTOGRAPHS Sandy Point State Park Anne Arundel County, MD P-021-102-010

SECTION 01732

SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of wood piers. 2. Demolition and removal of selected site elements.

B. Related Requirements:

1. Division 1 Section "Summary" for restrictions on the use of the premises, Owner- occupancy requirements, and phasing requirements.

1.3 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled.

B. Existing to Remain: Existing items of construction that are not to be permanently removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.4 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

1.5 PREINSTALLATION MEETINGS

A. Preconstruction Meeting: Items relating to demolition to be addressed at preconstruction meeting:

1. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays Repairs to the Boat Ramps 01732-1 SELECTIVE DEMOLITION Sandy Point State Park Anne Arundel County, MD P-021-102-010

2. Review requirements of work performed by other trades that rely on the concrete boat ramps exposed by temporary cofferdam and dewatering.

3. Review areas where existing construction is to remain and requires protection

1.6 FIELD CONDITIONS

A. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

B. Notify DGS of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. The existing timber sheeting submerged in water may contain Chromated Copper Arsenate (CCA) or creosote. Contractor shall dispose treated timber material in accordance with all Federal, State and Local ordinance.

D. Storage or sale of removed items or materials on-site is not permitted.

E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

PART 2 - PRODUCTS

2.1 PEFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Review record documents of existing construction provided by DGS. DGS does not guarantee that existing conditions are same as those indicated in record documents.

Repairs to the Boat Ramps 01732-2 SELECTIVE DEMOLITION Sandy Point State Park Anne Arundel County, MD P-021-102-010 C. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to DGS.

E. Survey of Existing Conditions:

1. Comply with requirements specified in Division 1 Section "Photographic Documentation." 2. Inventory and record the condition of items to be removed and salvaged. Provide photographs of conditions that might be misconstrued as damage caused by salvage operations.

3.2 PREPARATION

A. Site Access and T emporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

3.3 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.

B. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by DGS, items may be removed to a suitable, protected storage location during selective demolition and reinstalled in their original locations after selective demolition operations are complete.

3.4 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, then break up with maximum 30 pound chipping hammer and remove.

B. Timber framing: remove timber framing member as indicated. Care shall be taken not to damage adjacent members to remain. If adjacent member are damaged due to action or inaction of the Contractor during the course of construction, Contractor shall repair or replace these members at no additional cost to the owner.

Repairs to the Boat Ramps 01732-3 SELECTIVE DEMOLITION Sandy Point State Park Anne Arundel County, MD P-021-102-010 3.5 DISPOSAL OF DEMOLISHED MATERIAL

A. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.

1. Do not allow demolished materials to accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.

3.6 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 01732

Repairs to the Boat Ramps 01732-4 SELECTIVE DEMOLITION Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 02010

SUBSURFACE EXPLORATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. A “Geotechnical Evaluation” dated November 2010 has been prepared by Whitman, Requardt & Associates and is bound herein as Appendix C.

1.3 RESPONSIBILITY

A. Data indicated on subsurface conditions is not intended as representation or warranty of the continuity of such conditions. It is expressly understood that Owner and Engineer will not be responsible for interpretations or conclusions drawn by the Contractor; data is made available simply for the Contractor’s convenience. The opinions expressed in the geotechnical report are those of the geotechnical engineer and represent his interpretation of the subsoil conditions, tests, and results of analyses which he has conducted.

1.4 ADDITIONAL TESTING

A. Additional test borings, subsurface investigations, and other exploratory operations may be made by the Contractor at his own expense after receiving approval from the Owner.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION

Repairs to the Boat Ramps 02010-1 SUBSURFACE EXPLORATION Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 02200

EARTHWORK, EXCAVATION, TRENCHING AND BACKFILLING

PART 1 - GENERAL

1.01 DESCRIPTION

A. The Contractor shall provide all labor, materials, equipment and services necessary for, and incidental to, preparing the site, excavating, excavation support and dewatering systems, drainage, pumping, laboratory testing, backfilling, compacting, grading and protection of the work as shown on the Drawings, as herein specified, and in accordance with the STANDARD SPECIFICATIONS, as defined below.

B. The Contractor shall accept the site in the condition that it exists at the time of the award of the Contract.

C. The Engineer will determine whether materials that are to be used in the work are suitable or unsuitable, as defined in Paragraph 2.01 FILL AND BACKFILL MATERIAL, after reviewing the test results as required in Paragraph 1.04 MONITORING AND TESTING. All excess or unsuitable materials excavated shall be removed from the site by the Contractor and disposed of at a permitted off-site disposal location of its own choosing, at no additional cost to the Owner.

D. The Contractor shall be aware that the work shall also include requirements described in the following Paragraphs of this section:

1.07 TEMPORARY EXCAVATION SUPPORT SYSTEMS 3.06 PLACEMENT OF GROUT 3.07 PLACEMENT OF RIPRAP

E. The Contractor shall be aware the Project Site may have private wells, private springs and/or wetlands. In particular, it is recommended that the Contractor employ the services of a professional consultant to perform a pre-construction hydrogeologic assessment of any wells, springs or wetlands that could potentially be affected by construction. The Contractor shall be responsible for replacement of wells, springs or wetlands that are damaged by construction, at no additional cost to the Owner or property owner.

1.02 QUALITY ASSURANCE

A. Standard Specifications and Details

Reference in this Section to STANDARD SPECIFICATIONS or STANDARD DETAILS shall mean the following, and are hereby made part of this specification:

Repairs to the Boat Ramps 02200-1 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 1. Maryland Department of Transportation, State Highway Administration (MDSHA), "Standard Specifications for Construction and Materials", dated July 2008, with the latest incorporated revisions.

2. The official Book of Standards for Highway and Incidental Structures, edited by the Maryland Department of Transportation, State Highway Administration (MDSHA), with the latest incorporated revisions.

3. "2000 Maryland Stormwater Design Manual, Volumes I and II", prepared by the Center for Watershed Protection and the Maryland Department of the Environment, with the latest incorporated revisions.

In case of conflict between the STANDARD SPECIFICATIONS or STANDARD DETAILS and this contract specification, this contract specification shall govern.

B. Codes and Standards

The following Standards in effect on the date bids are received form a part of this Specification to the extent indicated by the following references:

American Association of State Highway and Transportation Officials (AASHTO):

M 6 Fine Aggregate for Portland Cement Concrete M 43 Standard Sizes of Coarse Aggregate for Highway Construction M 145 Classification of Soils and Soil-Aggregate Mixtures T 88 Particle Size Analysis of Soils T 89 Determining the Liquid Limit of Soils T 90 Determining the Plastic Limit and Plasticity Index of Soils T 119 Slump of Portland Cement Concrete T 180 Moisture-Density Relations of Soils Using 10-lb. Ram and 18-inch Drop T-99 Moisture-Density Relations of Soils Using 5-lb. Ram and 12-inch Drop T 191 Density of Soil In-Place by the Sand-Cone Method T 206 Penetration Test and Split-Barrel Sampling of Soils T 238 Density of Soils and Soil-Aggregate In-Place by Nuclear Methods T 239 Moisture Content of Soil and Soil-Aggregate In-Place by Nuclear Methods T 265 Laboratory Determination of Moisture Contents of Soils

American Society for Testing and Materials (ASTM):

D421-85(98) Standard Practice for Dry Preparation of Soil Samples for Particle-Size Analysis and Determination of Soil Constants D422-63(98) Standard Test Method for Particle-Size Analysis of Soils D1557-00 Test Method for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))

Repairs to the Boat Ramps 02200-2 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 D2216-98 Standard Test Method for Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass D2487-00 Standard Classification of Soils for Engineering Purposes (Unified Soil Classification System) D2922-01 Standard Test Methods for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth) D3740-01 Standard Practice for Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction D4318-00 Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils D5261-92(03) Standard Test Method for Measuring Mass Per Unit Area of Geotextiles E329-00b Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction E548-94e1 Standard Guide for General Criteria Used for Evaluating Laboratory Competence

All work shall comply with Occupational Safety and Health Regulations for Construction of the Code of Federal Regulations.

1.03 MONITORING AND TESTING

A. Monitoring

The Contractor shall perform excavation, subgrade preparation, and construction of fills and backfills under the direct monitoring and approval of the Engineer. The Contractor shall allow safe access for the Engineer to all parts of the project at all times.

B. Testing

The Contractor shall be responsible for all testing of concrete and soils, including field sampling, laboratory testing, and full-time inspection. The Contractor shall employ the services of an independent, professional testing consultant to perform the work. Inspections and test results shall be certified by the testing consultant’s licensed professional engineer, stating that the tests and observations were performed by the consultant or under the direct, full-time supervision of the consultant, that the results are representative of the materials or conditions being certified by the tests, and that the results are in conformance with the these Specifications. All costs for inspection and testing will be incidental to the Contract and additional payment will not be made.

C. Testing Facilities

The testing consultant shall provide the services of an approved commercial testing laboratory. Approval of testing facilities shall be based on requirements described in ASTM D 3740 and ASTM E 329.

Repairs to the Boat Ramps 02200-3 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 D. Laboratory Testing

Test reports or material certifications shall be submitted to the Engineer prior to use of any material in the work. Any change in the source or change in the character of the material shall require the Contractor to retest and resubmit for approval. Material certifications and laboratory test reports shall include the following:

1. Source of Material 2. Particle Size Analysis (AASHTO T88) 3. Modified Proctor (AASHTO T180) 4. Natural Moisture (AASHTO T265) 5. Atterberg Limits (AASHTO T89 and T90)

1.04 JOB CONDITIONS

A. Subsurface Investigations

1. The Owner has had a number of subsurface test borings made at various locations shown on the Drawings. Geotechnical data, including Driller’s boring logs and laboratory test results, are part of the Geotechnical Report, and are in the Appendix. The geotechnical data has been included for informational purposes to the Contractor. The Contractor shall be responsible for making any interpretations or conclusions drawn from the information contained therein. Neither the Engineer nor the Owner will be responsible for the conclusions drawn by the Contractor from the information presented or implied.

2. Boring samples are presently being stored by the office of Whitman, Requardt and Associates in Baltimore, Maryland and they may be reviewed at a time acceptable to the Owner and the Engineer.

3. The Contractor shall be responsible for reading the geotechnical data, and shall become familiar with the site and the subsurface conditions. Ignorance of conditions will not be accepted as a basis of claim for additional compensation. The Owner does not warrant or guarantee that the conditions actually encountered in the prosecution of the work under this contract will be the same as the conditions indicated by the geotechnical data. No additional compensation will be allowed the Contractor because of subsurface conditions actually encountered in the work.

4. The Contractor shall determine to its own satisfaction the ground water conditions and character and type of soil, decomposed rock, rock and other material to be encountered in the work to be done under this Contract.

5. If the Bidder determines, after visiting the site and reading the geotechnical data, that the data is not sufficient for bid preparation, the bidder may make its own investigation and tests, at a time acceptable to the Owner and as specified elsewhere. All government and private approvals and/or permits shall be obtained in writing by the Contractor prior to performing any investigations or tests.

Repairs to the Boat Ramps 02200-4 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 1.05 DEWATERING, DRAINAGE AND PUMPING

A. During construction, the grading operations shall be performed in such a manner that the excavations shall be well drained at all times. Sufficient grading shall be performed during the progress of the work so that no water, at any time, is allowed to flow towards the walls of the structures or trenches. The entire site shall be well drained and free from water pockets. When necessary, sumps shall be provided and pumped continuously. The Contractor shall maintain and keep all ditches open and free from soil and debris while in service or until final acceptance of the work and all grading shall be done on neat, regular lines. All work shall be done in proper sequence with all other associated operations. Before any slab or surfacing is placed, all utilities to be covered shall be installed and all drainage facilities shall be installed that are required to allow free and uninterrupted flow of the surface and ground water from the site or to pumping sumps.

B. The Contractor shall provide and continuously operate and maintain all temporary dewatering, drainage and pumping systems required to satisfactorily perform all work under the Contract. Water shall be controlled to such an extent as may be necessary to keep excavations free from water during construction and to maintain a minimum of 12 inches dry below the bottom of pipes and structures. The Contractor shall be entirely responsible for the design and adequacy of the dewatering system.

C. Dewatering systems required to perform the work shall be provided, operated and maintained by the Contractor at no additional cost to the Owner.

D. The Contractor shall exercise every precaution to prevent flotation of any of the work constructed under this Contract, and the Contractor shall be responsible for all damage due to flotation.

E. Such grading shall be done as necessary to prevent surface water from flowing into trenches or other utility excavations, and any water accumulating therein shall be continuously removed and properly filtered to remove sediment.

F. The method of water disposal shall be in accordance with State of Maryland sediment and storm water management requirements, and in compliance with all other erosion and sediment control regulations and regulatory agencies.

G. Methods of dewatering excavations shall be at the Contractor's discretion. Continuous investigations and checks shall be made by the Contractor to assure that the dewatering system employed is functioning properly, and not causing damage or settlement to adjacent surfaces or structures. Temporary pipes or flumes shall be used to carry surface water across open and/or unstabilized construction areas. The system shall be modified as required and repairs for damage caused by the system shall be the responsibility of the Contractor.

H. Should the Contractor’s dewatering operations affect any existing private water supply well or spring used as a water source, the Contractor shall, at no additional cost to the Owner, take whatever steps are necessary to provide uninterrupted water service, including the installation of temporary water lines or the installation of permanent wells with treatment systems, if required.

Repairs to the Boat Ramps 02200-5 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 The Contractor shall provide bottled water immediately to residents whose private wells are damaged during construction.

1.06 TEMPORARY EXCAVATION SUPPORT SYSTEMS

The Contractor shall temporarily support the sides and ends of all excavations, where necessary, with braces, sheeting, shoring, stringers or other methods of the type, size and quality required. The Contractor shall be entirely responsible for the design and adequacy of the excavation support system.

Pile driving hammers or vibratory hammers shall only be used to drive or extract temporary excavation support systems when approved in writing by the Engineer. However, the Contractor shall be responsible for any damage caused by operations involving vibrations.

Direction by the Engineer to leave portions of the temporary excavation support systems in-place, or the absence of direction by the Engineer to leave portions in-place, does not relieve the Contractor from its responsibility to protect existing structures and facilities.

A. Unless otherwise specified on the Drawings or directed by the Engineer, temporary excavation support systems shall be removed as refilling proceeds, in a manner so as not to damage any structures, roadbed, fill or private property.

Payment will not be made for use of temporary excavation support systems; the cost will be incidental to the bid items in the Contract.

B. If, where specified on the Drawings, excavation support systems are to be left in-place after backfill has been completed, they shall be cut off 2 feet below finished grade.

Payment will not be made for excavation support systems specified on the Drawings to be left in- place; the cost is included in the bid items in the Contract.

C. Although not directed by the Engineer, if the Contractor determines that removal of temporary excavation support systems will jeopardize any existing facilities or any of the work performed under this Contract, the Contractor may, with the written approval of the Engineer, leave all or part of the temporary excavation support systems in-place and shall cut them off 2 feet below finished grade.

Payment will not be made for temporary excavation support systems requested by the Contractor to be left in-place.

1.07 RESPONSIBILITY FOR CONDITION OF EXCAVATIONS

A. The Contractor shall be entirely responsible for the condition of all excavations performed by the Contractor, for the entire period of the Contract. All slides, caves or other unacceptable conditions shall be promptly corrected whenever they occur, without extra compensation. B. The neglect, failure or refusal of the Engineer to order or approve any excavation support system shall not in any way or to any extent relieve the Contractor of any responsibility concerning the

Repairs to the Boat Ramps 02200-6 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 conditions of excavations or of any of its obligations under the Contract; nor shall any delay whether caused by an action or want of action on the part of the Contractor or by any action or want of action of the Owner or its agents or employees, or the Engineer, resulting in the keeping of an excavation open longer than would otherwise have been necessary, relieve the Contractor from the necessity of properly and adequately protecting the excavation from caving or slipping, nor from any of its obligations under the Contract relating to injury of persons or property nor entitle it to any claim for extra compensation.

1.08 PROTECTION OF PROPERTY, STRUCTURES AND UTILITIES

The Contractor shall, at its own risk and at no additional cost to the Owner, maintain, support-in- place, and protect all pipes, poles, cables, utilities, walls, buildings, and other structures or property in the vicinity of its work, whether above or below ground, or that may appear in the excavation. The Contractor shall at all times have available on site sufficient quantity of timber, planks, beams, chains, ropes, etc., and shall use them as necessary for supporting any structures and utilities that are uncovered, undermined, endangered, threatened or weakened. The Contractor shall be responsible for all damage, shall take all risks, and shall assume all expense for injury or damage, to any person or property of every kind and description, caused directly or indirectly by the Contractor's work, whether such structures or utilities are or are not shown on the Drawings. In the event that the Contractor damages any existing utility lines the Contractor shall notify the Engineer and the utility owner immediately.

1.09 SUBMITTALS

The Contractor shall submit the following in accordance with the Contract.

A. Qualifications of the independent, professional testing consultant and commercial testing laboratory shall be submitted to the Engineer for approval prior to use in the work, in accordance with Paragraph 1.03 MONITORING AND TESTING.

B. Material certifications and laboratory test reports shall be submitted to the Engineer for approval prior to use in the work, in accordance with Paragraph 1.03 MONITORING AND TESTING.

C. Manufacturer’s product catalog data for geosynthetics (geotextiles, geogrids, geocomposites, geomembranes, etc.) to be furnished, shall be submitted to the Engineer for approval, showing compliance with the specification requirements of PART 2 - PRODUCTS. The submittal shall be provided a minimum of two weeks prior to the planned installation of the materials, shall include two samples of each material to be furnished, and shall be labeled appropriately with the Manufacturer’s name and product identification.

D. A Compaction Plan shall be submitted to the Engineer for approval, including a list of proposed compaction equipment to be used, Manufacturer’s specifications and catalog data, and the Contractor’s plan for compaction in the work. E. Delivery tickets shall be submitted by the Contractor for each load of material brought to the site under the authorization of the Engineer showing the following information:

Repairs to the Boat Ramps 02200-7 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 1. Name and location of supplier or source. 2. Type and amount of material delivered by volume and weight. 3. Test information on the material as required by this Specification Section.

F. Copies of nuclear gauge calibration curves and results of calibration tests shall be furnished to the Engineer within 24 hours of conclusion of tests.

G. Copies of test results and re-test results of in-place field compaction shall be furnished to the Engineer within 24 hours of conclusion of each test.

H. Excavation Support Systems and Dewatering Systems

1. Contractor shall submit working drawings and calculations for the design of all excavation support systems and dewatering systems to be utilized for the project.

The working drawings and calculations shall be performed by an engineer obtained and paid for by the Contractor. The Contractor’s engineer shall be a professional engineer engaged in such practice and licensed in the State of Maryland, and shall sign and seal all drawings and calculations. Signed and sealed drawings and calculations submitted to the Engineer will be for information only.

2. The working drawings and calculations for the dewatering systems shall include the following information:

a. Planned method of dewatering. b. Excavation plan. c. Location of the water table before and during dewatering. d. Location and capacity of such facilities as dewatering wells, well points, sumps, collection and discharge lines, proposed standby unit, and protective fills and ditches required for control of ground water and surface water.

3. The Contractor shall obtain and submit copies of all permits that may be required for installation and operation of pumps, well points and dewatering wells.

4. The Contractor shall be responsible for determining the existing subsurface conditions for the excavation support systems and dewatering systems. The Owner does not guarantee or warrant the conditions actually encountered on this project. The Owner will not be held responsible for the basis of claims by the Contractor or any other parties in the execution of these systems. The Contractor's submittals of the excavation support systems and dewatering systems, prepared by the Contractor’s engineer, are for information purposes only.

I. Grouting Work Plan and Mix 1. Contractor shall submit a work plan, in writing to the Engineer for approval, at least 10 days prior to any mobilization, including but not limited to the following:

Repairs to the Boat Ramps 02200-8 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 a. The injection hole locations and/or general spacing, sequence of grouting, grout injection pressure limits, grout take limits, and other factors which the Contractor recommends to successfully complete the work.

b. A list of all equipment to be used, including drilling, measuring, pumping, and mixing equipment.

c. A list of all personnel who will be working on this project.

2. Prior to the start of construction, the Contractor shall submit a grout mix to the Engineer for approval, including but not limited to the following:

a. A description of the materials to be used, including source and gradation of aggregate. b. The proposed grout mix designs. c. Laboratory test results documenting unconfined compression strengths and bleed test results for the proposed grout mix design.

PART 2 – PRODUCTS

2.01 FILL AND BACKFILL MATERIAL

A. Fill and backfill material shall be suitable material from on-site excavations or from other sources, unless otherwise shown on the Drawings. The material shall be clean earth. The material shall be free from vegetable matter, organic material, sludge, grit, trash, muck, roots, logs, stumps, frozen material or other deleterious substances. Rubber, ashes, cinders and other miscellaneous inorganic fill substances removed from required excavations within the project and that in the judgment of the Engineer will decompose, consolidate further, or shrink appreciably within the fill may not be incorporated in the fill. Rubble and construction debris shall not be used in the work.

B. Except as otherwise specified or approved, the material shall not contain rocks or lumps larger than 6 inches in greatest dimension. No rocks or lumps larger than 3 inches in greatest dimension will be allowed within 12 inches of subgrade, or within 12 inches of pipes in all directions, or within 24 inches of any structure during backfill. The material shall not contain mica in quantities that, in the judgment of the Engineer, are sufficient to affect compaction characteristics. Materials having a maximum dry density of less than 100 pounds per cubic foot (AASHTO T180), and materials having a plasticity index (AASHTO T90) greater than 30, shall not be used unless specifically approved in writing by the Engineer.

C. Suitable material is any material that is not frozen, that has a moisture content at the time it is placed that enables the material to be compacted to the density specified, and that meets the quality requirements specified above for the particular location and application specified. Unsuitable material is any material not meeting all the requirements for suitable material.

2.02 BORROW MATERIAL

Repairs to the Boat Ramps 02200-9 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 Borrow material, from off-site sources, shall meet the following requirements and shall be used only where specified on the Drawings or as required by the Engineer, and shall be furnished from a specific source or sources approved in writing by the Engineer:

A. AASHTO M145 Soil Groups A-1, A-2-4, A-2-6 B. AASHTO M145 Soil Group A-3 Fine Sand

2.03 DENSE GRADED AGGREGATE (DGA)

Dense Graded Aggregate shall meet the following requirements and shall be used only where specified on the Drawings or as required by the Engineer, and shall be furnished from a specific source or sources approved in writing by the Engineer:

A. MDSHA CR-6 (Crusher Run Aggregate) B. MDSHA GAB (Graded Aggregate Base) C. MDSHA BRG S/B (Bank Run Gravel Subbase) D. MDSHA BRG Base (Bank Run Gravel Base)

2.04 OPEN GRADED COARSE AGGREGATE (OGCA)

Open Graded Coarse Aggregate shall meet the following requirements and shall be used only where specified on the Drawings or as required by the Engineer, and shall be furnished from a specific source or sources approved in writing by the Engineer:

A. MDSHA No. 57 Aggregate (AASHTO M43) B. MDSHA No. 1 Coarse Aggregate (AASHTO M43 No. 1) C. MDSHA No. 2 Coarse Aggregate (AASHTO M43 No. 3)

2.05 GEOTEXTILE

Geotextile shall be used only where specified on the Drawings or as required by the Engineer, and shall meet the following requirements.

Nonwoven Geotextile

Geotextile shall be a nonwoven fabric consisting of continuous filaments of polyester or polypropylene formed into a stable network by needle punching. It shall be inert to commonly encountered chemicals and hydrocarbons, mildew and rot resistant, and insect and rodent resistant. The fabric shall have a mass per unit area of at least 6 ounces per square yard as determined by ASTM D5261.

The geotextile shall provide a permeable layer or media, while retaining the soil matrix. It shall be provided in rolls wrapped with protective covering to protect the fabric from mud, dirt, and debris. The geotextile shall be TC Mirafi 160N or approved equal.

Repairs to the Boat Ramps 02200-10 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 2.06 GROUT

The grout mix shall be design to provide workability compatible with the Contractor’s proposed method of placement and shall have a compressive strength not less than 500 pounds per square inch. The bleed of the proposed grout mix shall be documented to not exceed 2%.

Portland Cement Concrete MDSHA 902.02 and 902.03 Water MDSHA 921.01 Fly Ash, Class F MDSHA 902.06.04 (a)

Sand and gravel may be used as bulk fillers and to control fluidity. Fly Ash may be used to enhance pumpability. Other additives shall not be used without prior written approval of the Engineer. Bentonite, bottom ash, and other potentially deleterious materials shall not be used.

The Plasticity Index of aggregate materials passing the 200 sieve shall be less than 20. All materials shall be accurately measured by volume, weight, or other approved means. The grout mix proportions shall be adjusted for each point of injection, if necessary to obtain optimum grout take and penetration.

2.07 RIPRAP

Riprap shall meet the requirements of Paragraph 3.07 PLACEMENT OF RIPRAP.

Class 0, Class I, and Class II riprap for sinkhole or cavity backfill, and for slope protection and stabilization shall meet the following requirements and shall be used only where specified on the drawings or as required by the Engineer. The stone shall be hard, durable, resistant to weathering, angular in shape, free from overburden, spoil, shale, slate and organic material, and shall meet the quality and size requirements of Section 901 of the MDSHA STANDARD SPECIFICATIONS.

A. Class 0 riprap stones shall not be heavier than 33 pounds, with 50 percent of the total, by weight, heavier than 10 pounds, and a maximum of 10 percent of the total, by weight, shall weigh less than 1 pound.

B. Class I riprap stones shall not be heavier than 150 pounds, with 50 percent of the total, by weight, heavier than 40 pounds, and a maximum of 10 percent of the total, by weight, shall weigh less than 2 pounds.

C. Class II riprap stones shall not be heavier than 700 pounds, with 50 percent of the total, by weight, heavier than 200 pounds, and a maximum of 10 percent of the total, by weight, shall weigh less than 20 pounds.

D. The riprap may be obtained from on-site blast material if it complies with these specifications or shall be furnished from a specific source or sources approved in writing by the Engineer. When on-site blast material is used, the stone will be accepted at the point of usage, upon visual inspection and upon the judgment of the Engineer.

Repairs to the Boat Ramps 02200-11 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 PART 3 - EXECUTION

3.01 SITE PREPARATION

All rubble, trash, unusable and unsuitable material, pavements, concrete structures, piping, sludge, grit, etc., within areas required to be filled, excavated or graded, except as otherwise specified or shown, shall be fully removed from the site and disposed of by the Contractor, at no additional cost to the Owner. Such material may exist on the site. The Contractor shall obtain and pay for all necessary permits related to this disposal.

3.02 COMPACTED FILLS AND BACKFILLS

Prior to placing any fill or backfill, notice shall be given the Engineer so that the work may be inspected, and filling or backfilling shall not proceed without the Engineer’s approval. Unless otherwise noted in this Section, placing, spreading and compacting suitable material for fills and backfills shall be as follows:

A. Fill and backfill material shall be placed in approximately horizontal layers that, before compaction, shall not exceed 8 inches in thickness. Fill and backfill material within 5 feet of structures shall be placed in approximately horizontal layers that, before compaction, shall not exceed 6 inches in thickness. Each layer shall be spread uniformly and evenly. All rocks shall be distributed throughout the earth materials and all voids shall be carefully filled and the material properly compacted by rolling, tamping, vibratory compactors, or other methods specified herein and approved by the Engineer. Compaction by heavy rollers or other heavy equipment is prohibited within 5 feet of any structure.

B. Moisture content of fill and backfill material shall be within 2% above or below the optimum moisture content for the material while placing and during compaction. After each layer has been placed, mixed and spread evenly, it shall be thoroughly compacted to not less than the following:

1. 92% of maximum dry density for cohesive soils, 2. 95% of maximum dry density for cohesionless soils, 3. 97% of maximum dry density for fills and backfills within 12 inches of slab or roadway subgrade.

Cohesionless soils are defined as granular soils containing less than 15% by weight passing the No. 200 sieve. Optimum moisture content and maximum dry density shall be determined by AASHTO T 180. Weaving or creeping of the soil beneath the roller shall be sufficient evidence that the moisture content of the fill or subsoils is excessive, and that required compaction has not been achieved.

C. The fill or backfill shall be constructed in such a manner that the surface will be sloped to drain at all times and shall be sealed by rolling at the completion of each day or prior to rain. Materials containing free water or having a moisture content higher than specified shall not be deposited upon the fill or backfill until after they have been dried to the specified moisture content.

Repairs to the Boat Ramps 02200-12 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 D. No fill or backfill shall be placed, spread or rolled while it is frozen or thawing or be placed upon frozen or thawing ground or during unfavorable weather conditions. Any compacted layer that has been previously frozen shall be reworked or removed before the next layer is placed.

3.03 FILLS AND BACKFILLS FOR STRUCTURES

A. Subgrade for structures is defined as the bottom of the granular bedding material, 6 inches below the underside of the slab or structure, unless otherwise noted on the Drawings.

B. Bedding material for structures shall be 6 inches of MDSHA No. 57 Aggregate, as defined in PART 2 - PRODUCTS, unless otherwise noted on the Drawings.

C. After completing the construction of structure foundations, footings, walls, etc., below finished grade, all forms shall be removed and the excavation cleaned of all trash and debris. The excavation shall not be used for the disposal of refuse. Any refuse or other foreign materials shall be removed before backfilling. Prior to placing any backfill, notice shall be given to the Engineer so that the work may be inspected, and backfilling shall not proceed without the Engineer’s approval. No backfill shall be placed against any structure until the structure is complete and the concrete has reached its specified strength, or the structure has been properly braced and has sufficient strength to support the applied load.

D. The fill or backfill for structures may include suitable, on-site material originating on the job, as defined in PART 2 - PRODUCTS, unless otherwise noted. Compaction shall be in accordance with Paragraph 3.03 COMPACTED FILLS AND BACKFILLS.

E. If contingent unit price items are used for backfill of structures, measurement will be based on the actual in-place volume of material not exceeding vertical planes 18 inches outside of the structure, and payment will be in accordance with Paragraph 3.04 CONTINGENT BORROW AND AGGREGATE.

3.04 CONTINGENT BORROW AND AGGREGATE

A. If the Engineer determines that sufficient suitable, on-site, fill or backfill material is not available from the required excavations to perform the work required, the Engineer will direct that the Contractor shall furnish borrow material from approved off-site sources. Borrow material shall not be used unless all available suitable excavated material has been utilized for the work. If on- site excavated material is determined to be unsuitable due to inadequate or excessive moisture content, the Contractor shall make the material suitable as specified in Paragraph 3.02 COMPACTED FILLS AND BACKFILLS.

B. The Engineer may direct the use of any additional quantity of borrow and/or aggregate to be used below subgrade or at locations other than as specified on the Drawings.

C. Borrow and/or aggregate shall be as specified in PART 2 – PRODUCTS. Placement and compaction of these materials shall be in accordance with Paragraph 3.02 COMPACTED FILLS

Repairs to the Boat Ramps 02200-13 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 AND BACKFILLS. Payment will be in accordance with the appropriate unit price item of the Bid.

3.05 RIVER AND STREAM

A. All underwater river and stream crossings shall be as shown on the Drawings for the individual crossing.

B. All underwater river and stream crossings shall be in accordance with the Joint Permit Application for Activities in Waters and Wetlands of the State of Maryland, included in the INFORMATION FOR BIDDERS of these Specifications.

C. No underwater river or stream crossing shall be conducted during the prohibited times of year indicated in the Permit Application for Activities in Waters and Wetlands of the State of Maryland.

D. Temporary cofferdam structures shall be “Port-a-Dam”, or approved equal, and methods and materials shall be in accordance with Paragraph 1.09 SUBMITTALS.

E. Riprap Slope and Channel Protection

1. Subgrade preparation and placement of riprap for the protection of river and stream channels and slopes shall be as described in this Section, as shown on the Drawings, and shall conform to the requirements of Section 312 of the MDSHA STANDARD SPECIFICATIONS.

2. Placement of riprap shall be by excavator bucket and by hand, to provide a dense, interlocking layer. Free-fall dumping shall not be allowed. The surface shall be graded trimly and evenly to the lines and grades shown on the Drawings, using blades and heavy tracked equipment.

F. Payment is included in the base price of the Bid.

3.06 PLACEMENT OF GROUT

A. The contractor shall keep accurate record for all grout injection holes, including the following information:

1. hole identification 2. location, pier # and offset 3. depth and description of strata, voids, rubble, and collapsed zones 4. method of drilling, volume of grout injected, and any difficulties encountered during drilling and placement.

B. Only approved mixing and pumping equipment shall be used in the preparation and handling of grout. All oil or other rust inhibitors shall be removed from the mixing drums, stirring mechanisms and other portions of the the equipment in contact with the grout before the mixers are used. All equipment shall be maintained in first class operating condition at all times

Repairs to the Boat Ramps 02200-14 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 C. The grouting superintendent/engineer shall be present during the drilling and grouting of all holes. If the project involves more than one shift per day, the grouting superintendent/engineer shall be present on the job site for no less than one shift per day, and shall be readily available to the site for the other shifts should the need arise. Any change of personnel, especially supervisory personnel, during the performance of any phase of this contract will be subject to the approval of the Engineer.

D. The Contractor shall locate all private and public utilities prior to the initiation of any drilling. The Contractor shall correct any damage to utilities resulting from the drilling and grouting operations at no additional cost to the Owner.

E. The Contractor shall monitor for ground heave during the grouting operation, using survey methods capable of detecting movement of 0.01-foot. The Contractor shall correct heave in excess of ¾ inch at no additional cost to the Owner.

F. The Contractor shall develop an erosion and sediment control plan. The Contractor shall control any dust from the drilling operation, and from the concrete plant, if applicable. The Contractor shall dispose of all waste or spilled grout, as well as grout-bearing material washed from the hose or the casing, in compliance will all applicable laws and regulations.

3.07 PLACEMENT OF RIPRAP

A. Subgrade of riprap used for embankment surface stabilization, shall be graded trimly and evenly, with blades and heavy tracked equipment so as to provide a rough, dense surface to key and knead the riprap layer. Vibratory rolling is not required.

B. Riprap shall be used as shown on the Drawings, or at locations as directed by the Engineer, and wherever possible to reduce the need for topsoil and to utilize excavated rock material.

C. Placement of riprap shall be by excavator bucket and by hand, to provide a dense, interlocking layer. Free-fall dumping shall not be allowed.

END OF SECTION

Repairs to the Boat Ramps 02200-15 EARTHWORK Sandy Point State Park Anne Arundel County, MD P-021-102-010 SECTION 02464

VINYL SHEET PILING

PART 1 – GENERAL

1.1 RELATED DOCUMENTS:

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specifications, apply to this Section.

1.2 SCOPE

A. Work consists of furnishing and driving vinyl sheet piling to be left in place for the Boat Ramp wall, as shown on the Drawings, including cutting off, splicing and welding and all labor, materials, tools and equipment needed to install the piling.

B. Base bids on pile sections and lengths as indicated. No additional payment will be made for withdrawn, damaged, rejected, or misplaced piles; for any portion of a pile remaining above the cut-off elevation; for backdriving; for cutting off piles, or for any cut off length of piles.

C. All sheet piles for the Boat Ramp wall shall be driven to penetrate into the soil to the minimum depths shown on the Drawings.

1.3 RELATED WORK INCLUDED ELSEWHERE:

A. The Contractor shall be aware that the work described in this section shall be in addition to the requirements of the following Sections:

1. Section 01025: Measurement and Payment 2. Section 02200: Earthwork, Excavation, Trenching and Backfilling

Repairs to the Boat Ramps 02464-1 VINYL SHEET PILING Sandy Point State Park Anne Arundel County, MD P-021-102-010 1.4 SUBMITTALS

Prior to the start of pile driving, submit the following for approval by the Engineer in accordance with the Proposal.

A. Contractor’s Qualifications

1. Piles shall be installed by a Contractor qualified to install the specified pile type.

B. Vinyl Sheet Piles

1. Submit detail drawings for sheet piles, including fabricated sections, showing complete pile dimensions and details, driving sequence and location layout details of installed piles. Include in the drawings details of top protection, special reinforcing tips, tip protection, lagging, splices (including drawing details), fabricated additions to plain piles, cut-off method, corrosion protection, and dimensions of templates and other temporary guide structures for installing piles.

2. Provide details of the method for handling piles to prevent permanent deflection, distortion or damage to pile interlocks.

3. Provide schedules for monitoring existing structures.

4. Prior to commencement of work, submit descriptions of sheet pile driving equipment to be employed in the work. Descriptive information includes manufacturer's name, model numbers, capacity, rated energy, hammer details, cushion material, helmet, templates, jetting equipment, extractors, protection caps, and other installation appurtenances and manufacturer's recommendations.

C. Materials Test Reports and Certification

1. Certified materials tests reports, showing that sheet piles meet the specified requirements, for each shipment and identified with specific lots prior to installing materials.

2. Include in the identification data pile type, dimensions, chemical composition, mechanical properties, section properties, heat number, and mill identification mark.

3. Submit written certification from the manufacturer that piles meet specification requirements.

Repairs to the Boat Ramps 02464-2 VINYL SHEET PILING Sandy Point State Park Anne Arundel County, MD P-021-102-010 D. Pile Driving Record

1. Records of the completed sheet pile driving operations, including a system of identification which shows the disposition of approved piling in the work, record for each sheet pile driven, as specified, driving equipment performance data, pile penetration rate data, pile dimensions and top and bottom elevations of installed piles.

PART 2 – PRODUCTS

2.1 VINYL SHEET PILES

A. All sheet piling shall be manufactured entirely from a rigid, high impact, UV- inhibited, weatherable vinyl compound. All exposed surfaces of the sheet piling shall be UV resistant, and comprised of virgin material with a minimum ASTM D4216 Cell Classification of 1-42443-33 to ensure reliable performance and color consistency. If mono-extrusion technology is used, the entire sheet pile must be comprised of virgin material with a minimum ASTM D4216 Cell Classification of 1-42443-33.

B. The section modulus of the sheet piling section shall be no less than 20.2 cubic inches per linear foot of wall.

C. The moment of inertia of the sheet piling section shall be no less than 91 in4 per linear foot of wall.

D. The sheet piling shall have a minimum thickness of 0.290 inches.

E. The sheet piling shall have a maximum section depth of 9.0 inches to prevent web buckling.

F. The sheet piling shall have a minimum width of 24 inches per sheet resulting in a maximum of ½ an interlock per linear foot of wall.

G. All male interlocks must incorporate I-Beam Lock reinforcement to resist lock separation and decrease seepage.

H. General Requirements: Sheet piles including special fabricated sections shall be full-length sections of the dimensions submitted and approved. Sheet piles shall be of the same manufacturer.

I. Connectors and Fabricated Sections: Provide fabricated sections conforming to the requirement and the pile manufacturer's recommendations for fabricated sections.

J. Sheet piling supplied for the project shall be manufactured by Crane Materials International or approved equal. Alternate manufacturers shall provide no less

Repairs to the Boat Ramps 02464-3 VINYL SHEET PILING Sandy Point State Park Anne Arundel County, MD P-021-102-010 than five (5) references for projects similar in scope and function which have been in service for no less than one (1) year, which shall include the following:

Detailed project description and location. Completion Date Name and address of owner

1. Alternate manufacturers must submit all documentation (references, specification sheets, etc.) and one (1) physical sample for each product requested for approval no less than ten (10) days prior to bid.

PART 3 – EXECUTION

3.1 DELIVERY, STORAGE, AND HANDLING

A. Materials delivered to the site shall be new and undamaged and shall be accompanied by certified test reports. Store and handle sheet piles in the manner recommended by the manufacturer to prevent permanent deflection, distortion or damage to the interlocks. Storage of sheet piles should also facilitate required inspection activities and prevent damage to coatings and corrosion prior to installation.

3.2 EARTHWORK

A. Perform in accordance with Section 02200 EARTHWORK, EXCAVATION, TRENCHING AND BACKFILLING. Backfill as indicated.

3.3 INSTALLATION

A. All sheet piles for the Boat Ramp wall shall be driven to penetrate into the soil to the minimum depths shown on the Drawings.

B. Pile Driving Equipment

1. Provide pile driving equipment conforming to the following requirements.

a. Driving Hammers

i. Hammers shall be steam, air, or diesel drop, single-acting, double-acting, differential-acting, or vibratory type. The driving energy of the hammers shall be suitable to install the piles to the specified depth considering the pile weights and subsurface materials to be encountered. Replace piles or repair damage to piles caused by use of a pile hammer with excess delivered force or energy.

b. Jetting Equipment Repairs to the Boat Ramps 02464-4 VINYL SHEET PILING Sandy Point State Park Anne Arundel County, MD P-021-102-010 i. Jetting for the installation of the sheet piles shall be performed as necessary for pile installation.

C. Placing Piles

1. Piles properly placed and driven shall be interlocked throughout their length with adjacent piles to form a continuous diaphragm throughout the length or run of pile wall.

a. Piles shall be carefully located as shown. Piles shall be placed plumb with out-of-plumbness not exceeding 1/4 inch per foot of length and true to line. Place the pile so the face will not be more than 6 inches from vertical alignment at any point. Top of pile at elevation of cut- off shall be within 2 inches horizontally and 2 inches vertically of the location indicated. Manipulation of piles to force them into position will not be permitted. Check all piles for heave. Redrive or replace all heaved piles to the required tip elevation.

2. Provide temporary wales, templates, current deflectors or guide structures to ensure that the piles are placed and driven to the correct alignment. Use a system of structural framing sufficiently rigid to resist lateral and driving forces and to adequately support the sheet piles until design tip elevation is achieved. Use two templates, at least, when placing each pile. Templates shall not move when supporting sheet piles. Fit templates with wood blocking to bear against the web of each alternate sheet pile and hold the sheet pile at the design location alignment. Provide outer template straps or other restraints as necessary to prevent the sheets from warping or wandering from the alignment. Mark template for the location of the leading edge of each alternate sheet pile. If in view, also mark the second level to assure that the piles are vertical and in position. If two guide marks cannot be seen, other means shall be used to keep the sheet pile vertical along its leading edge.

D. Driving Piles

1. Prior to driving piles in water, paint a horizontal line on both sides of each pile at a fixed distance from the bottom so that it will be visible above the water line after installation. This line shall indicate the profile of the bottom elevation of installed piles and potential problem areas can be identified by abrupt changes in its elevation. Drive piles with the proper size hammer and by approved methods so as not to subject the piles to damage and to ensure proper interlocking throughout their lengths.

2. Each pile shall be driven continuously without voluntary interruption, from the first blow until the penetration depth as indicated elsewhere in this Section.

Repairs to the Boat Ramps 02464-5 VINYL SHEET PILING Sandy Point State Park Anne Arundel County, MD P-021-102-010 a. Maintain driving hammers in proper alignment during driving operations by use of leads or guides attached to the hammer. Caution shall be taken in the sustained use of vibratory hammers when a hard driving condition is encountered to avoid interlock-melt or damages. Discontinue the use of vibratory hammers and impact hammers employed when the penetration rate due to vibratory loading is one foot or less per minute.

b. Employ a protecting cap in driving when using impact hammers to prevent damage to the tops of piles. Remove and replace piles damaged during driving or driven out of interlock at the Contractor's expense.

c. Drive piles with the aid of a water jet when necessary.

d. Take adequate precautions to ensure that piles are driven plumb. If at any time the forward or leading edge of the pile wall is found to be out-of-plumb in the plane of the wall the pile being driven shall be driven to the required depth and tapered piles shall be provided and driven to interlock with the out-of-plumb leading edge or other approved corrective measures shall be taken to insure the plumbness of succeeding piles. The maximum permissible taper for any tapered pile shall be 1/8 inch per foot of length.

e. Piles in each run or continuous length of pile wall shall be driven alternately in increments of depth to the required depth or elevation. No pile shall be driven to a lower elevation than those behind it in the same run except when the piles behind it cannot be driven deeper. Incrementally sequence driving of individual piles such that the tip of any sheet pile shall not be more than 4 feet below that of any adjacent sheet pile. When the penetration resistance exceeds five blows per inch, the tip of any sheet pile shall not be more than 2 feet below any adjacent sheet pile. If the pile next to the one being driven tends to follow below final elevation it may be pinned to the next adjacent pile.

f. If obstructions restrict driving a pile to the specified penetration, the obstructions shall be removed or penetrated. If the Contractor demonstrates that removal or penetration is impractical, make changes in the design alignment of the pile structure as directed to ensure the adequacy and stability of the structure. Piles shall be driven to depths shown and shall extend up to the elevation indicated for the top of piles. A tolerance of 2 inches above the indicated top elevation will be permitted.

3. Do not drive piles within 30 feet of cast-in-place concrete, which has been in place for less than 72 hours.

Repairs to the Boat Ramps 02464-6 VINYL SHEET PILING Sandy Point State Park Anne Arundel County, MD P-021-102-010 4. Do not place cast-in-place concrete while pile driving operations are being carried out within a 30 foot distance

E. Cutting-Off and Splicing

1. Piles driven to refusal or to the point where additional penetration cannot be attained and are extending above the required top elevation in excess of the specified tolerance shall be cut off to the required elevation. Piles driven below the required top elevation and piles damaged by driving and cut off to permit further driving shall be extended as required to reach the top elevation at no additional cost to the Owner.

F. Inspection of Driven Piles

1. Perform continuous inspection during pile driving. Inspect all piles for compliance with tolerance requirements. Bring any unusual problems which may occur to the attention of the Engineer. Inspect the interlocked joints of driven piles extending above ground. Piles found to be out of interlock shall be removed and replaced at the Contractor's expense.

G. Pulling and Redriving

1. Pull, as directed, selected piles after driving to determine the condition of the underground portions of piles. Any pile so pulled and found to be damaged, to the extent that its usefulness in the structure is impaired, shall be removed and replaced at the Contractor's expense. Piles pulled and found to be in satisfactory condition shall be redriven when directed.

3.4 REMOVAL

A. The removal of sheet piles shall consist of pulling, sorting, cleaning the interlocks, inventorying and storing previously installed sheet piles as shown and directed.

1. Pulling

a. The method of pulling piles shall be approved. Provide pulling holes in piles, as required. Extractors shall be of suitable type and size. Care shall be exercised during pulling of piles to avoid damaging pile interlocks and adjacent construction. If the Engineer determines that adjacent permanent construction has been damaged during pulling, the Contractor will be required to repair this construction at no cost to the Owner. Pull piles one sheet at a time. Piles fused together shall be separated prior to pulling, unless the Contractor demonstrates, to the satisfaction of the Engineer, that the piles cannot be separated. The Contractor will not be paid for the removal of piles damaged beyond structural use due to proper care not being exercised during pulling.

Repairs to the Boat Ramps 02464-7 VINYL SHEET PILING Sandy Point State Park Anne Arundel County, MD P-021-102-010 2. Sorting, Cleaning, Inventorying and Storing

a. Pulled piles shall be sorted, cleaned, inventoried and stored by type into groups as:

i. Piles usable without reconditioning. ii. Piles requiring reconditioning. iii. Piles damaged beyond structural use.

3.5 INSTALLATION RECORDS

A. Maintain a pile driving record for each sheet pile. Record any unusual pile driving problems during driving. Submit complete records to the Engineer which shall include:

1. installation dates and times; 2. type and size of hammer; 3. rate of operation; 4. total driving time; 5. dimensions of driving helmet and cap used; 6. blows required per foot for each foot of penetration; 7. final driving resistance in blows for final 6 inches; 8. pile locations; 9. tip elevations; 10. ground elevations; 11. cut-off elevations, 12. any reheading or cutting of piles. 13. Length of pile taken into the leads; and, 14. Location and type of splice.

END OF SECTION

Repairs to the Boat Ramps 02464-8 VINYL SHEET PILING Sandy Point State Park Anne Arundel County, MD P-021-102-010

SECTION 03013

MAINTENANCE OF CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Removal of damaged concrete and subsequent replacement and patching. 2. Crack and joint repair 3. Spall repair

B. Related Requirements:

1. Section 01025: Measurement and Payment. 2. Section 01270: Unit Prices 3. Section 01732: Selective Demolition. 4. Section 03301: Miscellaneous Cast-In-Place Concrete. 5. Section 07920: Joint Sealant.

1.2 UNIT PRICES

A. General: Refer to Section 01270 Unit Prices.

B. Miscellaneous Cast-In-Place Concrete Removal and Replacement or Patching: Work will be paid for by the cubic yard computed on the basis of rectangular solid shapes approximating the actual shape of concrete removed and replaced with average depths, widths, and lengths, measured to the nearest inch.

C. Crack Repair: Work will be paid for by the linear foot of crack repaired.

D. Spall Repair: Work will be paid for by the square foot of spalled area repaired.

1.3 PREINSTALLATION MEETINGS

A. Preconstruction Meeting: Conduct meeting at site as chosen by the Owner

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product. Include construction details, material descriptions, chemical composition, physical properties, test data, and mixing, preparation, and application instructions.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For installers and manufacturers.

Repairs of Boat Ramps 03013 - 1 MAINTENANCE OF Sandy Point State Park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 B. Material Certificates: For each type of Portland Cement aggregate supplied for mixing or adding to products at Project site.

C. Product Test Reports: For each manufactured bonding agent cementitious patching mortar and joint-filler, for tests performed by manufacturer and witnessed by a qualified testing agency.

D. Field quality-control reports.

E. Maintenance Program: Submit before work begins.

1.6 QUALITY ASSURANCE

A. Manufacturer Qualifications: Each manufactured bonding-agent manufacturer shall employ factory-trained technical representatives who are available for consultation and Project-site inspection and assistance at no additional cost.

B. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer to apply packaged patching-mortar materials.

C. Maintenance Program: Prepare a written plan for maintenance of cast-in-place concrete, including each phase or process, protection of surrounding materials during operations, and control of debris and runoff during the Work. Describe in detail materials, methods, equipment, and sequence of operations to be used for each phase of the Work.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Comply with manufacturer's written instructions for minimum and maximum temperature requirements and other conditions for storage.

B. Store cementitious materials off the ground, under cover, and in a dry location.

C. Store aggregates covered and in a dry location; maintain grading and other required characteristics and prevent contamination.

1.8 FIELD CONDITIONS

A. Cold-Weather Requirements for Cementitious Materials: Do not apply unless concrete- surface and air temperatures are above 40 deg F and will remain so for at least 48 hours after completion of Work.

B. Cold-Weather Requirements for Cementitious Materials: Comply with the following procedures:

1. When air temperature is below 40 deg F, heat patching-material ingredients and existing concrete to produce temperatures between 40 and 90 deg F. 2. When mean daily air temperature is between 25 and 40 deg F, cover completed Work with weather-resistant insulating blankets for 48 hours after repair or provide enclosure and heat to maintain temperatures above 32 deg F within the enclosure for 48 hours after repair.

Repairs of Boat Ramps 03013 - 2 MAINTENANCE OF Sandy Point State Park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 3. When mean daily air temperature is below 25 deg F, provide enclosure and heat to maintain temperatures above 32 deg F within the enclosure for 48 hours after repair.

C. Hot-Weather Requirements for Cementitious Materials: Protect repair work when temperature and humidity conditions produce excessive evaporation of water from patching materials. Provide artificial shade and wind breaks, and use cooled materials as required. Do not apply to substrates with temperatures of 90 deg F and above.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Source Limitations: Obtain each color, grade, finish, type, and variety of product from single source with resources to provide products of consistent quality in appearance and physical properties.

B. VOC Content: Provide materials that comply with VOC limits of authorities having jurisdiction.

2.2 BONDING AGENTS

A. Epoxy-Modified, Cementitious Bonding and Anticorrosion Agent: Manufactured product that consists of water-insensitive epoxy adhesive, portland cement, and water- based solution of corrosion-inhibiting chemicals that forms a protective film on steel reinforcement.

1. Bonding agent shall be SikaDur Armatec 110 as manufactured by Sika Chemical Corporation or approved equal.

2.3 PATCHING MORTAR

A. Patching Mortar, General:

1. Only use patching mortars that are recommended by manufacturer for each applicable orientation. 2. Coarse Aggregate for Patching Mortar: ASTM C 33, washed aggregate, Size No. 8, Class 5S. Add to patching-mortar mix only as permitted by patching- mortar manufacturer.

B. Polymer-Modified, Cementitious Patching Mortar: Packaged, dry mix for repair of concrete and that contains a latex additive as either a dry powder or a separate liquid that is added during mixing.

1. Polymer-Modified, Cementitious Patching Mortar shall be Sikatop 123 Plus as manufactured by Sika Chemical Corporation or approved Equal.

Repairs of Boat Ramps 03013 - 3 MAINTENANCE OF Sandy Point State Park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 2.4 PREPLACED CONCRETE MATERIALS

A. When an area of existing concrete ramps has deteriorated to an extent that is deemed by the Owner’s representative to be more economical to be replaced as a whole. The contractor shall saw cut the deteriorated area in a square pattern and remove the existing concrete. The areas of existing concrete that are removed shall be replaced with either cast-in-place concrete or patching mortar at the discretion of the owner’s representative.

B. See specification 03301 Miscellaneous Cast-In-Place Concrete.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Around each visible spall repair location locate additional areas of deteriorated or delaminated concrete using hammer or chain-drag sounding and mark boundaries. Mark areas for removal by simplifying and squaring off boundaries as directed by the Owner’s Representative.

B. Perform surveys as the Work progresses to detect hazards resulting from concrete- maintenance work.

3.2 PREPARATION

A. Ensure that supervisory personnel are on-site and on duty when concrete maintenance work begins and during its progress.

B. Preparation for Removal of Deteriorated Concrete: Examine construction to be repaired to determine best methods to safely and effectively perform concrete maintenance work. Examine adjacent work to determine what protective measures will be necessary. Make explorations, probes, and inquiries as necessary to determine condition of construction to be removed in the course of repair.

C. Protect persons, surrounding surfaces of the areas being restored, construction site, and surrounding properties from harm resulting from concrete maintenance work.

1. Comply with each product manufacturer's written instructions for protections and precautions. Protect against adverse effects of products and procedures on people and adjacent materials, and components. 2. Use only proven protection methods appropriate to each area and surface being protected. 3. Provide barricades, barriers, and temporary directional signage to exclude public from areas where concrete maintenance work is being performed. 4. Contain dust and debris generated by concrete maintenance work and prevent it from reaching the public, adjacent surfaces, or falling into the water. 5. Use water-mist sprinkling and other wet methods to control dust only with adequate, approved procedures and equipment that ensure that such water will not create a hazard or adversely affect other areas or materials. 6. Protect surfaces along haul routes from damage, wear, and alterations.

Repairs of Boat Ramps 03013 - 4 MAINTENANCE OF Sandy Point State Park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 7. Provide supplemental sound-control treatment to isolate removal and dismantling work from other areas. 8. Neutralize and collect alkaline and acid wastes for disposal off Owner's property. 9. Dispose of debris and runoff from operations by legal means and in a manner that prevents soil erosion, undermining of paving and foundations, contamination of water, and damage to landscaping.

D. Concrete Removal: 1. Saw-cut perimeter of areas indicated for removal to a depth of at least 1/2 inch. Make cuts perpendicular to concrete. 2. Remove deteriorated and delaminated concrete by breaking up. 3. Remove additional concrete if necessary to provide a depth of removal of at least 2 inches over entire removal area. 4. Test areas where concrete has been removed by tapping with hammer, and remove additional concrete until unsound and disbonded concrete is completely removed. 5. Provide surfaces with a fractured profile of at least 1/8 inch that are approximately perpendicular or parallel to original concrete surfaces. 6. Thoroughly clean removal areas of loose concrete, dust, and debris.

3.3 APPLICATION

A. General: Comply with manufacturer's written instructions and recommendations for application of products, including surface preparation.

B. Epoxy-Modified, Cementitious Bonding and Anticorrosion Agent: Apply to concrete by stiff brush or hopper spray according to manufacturer's written instructions. Allow to dry before placing patching mortar or concrete.

C. Placing Patching Mortar: Place as follows unless otherwise recommended in writing by manufacturer:

1. Provide forms where necessary to confine patch to required shape. 2. Wet substrate and forms thoroughly and then remove standing water. 3. Pretreatment: Apply specified bonding agent . 4. General Placement: Place patching mortar by troweling toward edges of patch to force intimate contact with edge surfaces. For large patches, fill edges first and then work toward center, always troweling toward edges of patch. 5. Consolidation: After each lift is placed, consolidate material and screed surface. 6. Multiple Lifts: Where multiple lifts are used, score surface of lifts to provide a rough surface for placing subsequent lifts. Allow each lift to reach final set before placing subsequent lifts. 7. Finishing: Allow surfaces of lifts that are to remain exposed to become firm and then finish to a surface matching adjacent concrete. 8. Curing: Wet-cure cementitious patching materials, including polymer-modified cementitious patching materials, for not less than seven days by water-fog spray or water-saturated absorptive cover, or other approved methods.

D. Crack and Joint Repair: Repair according to Division 07 Section “Joint Sealant”.

Repairs of Boat Ramps 03013 - 5 MAINTENANCE OF Sandy Point State Park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 3.4 FIELD QUALITY CONTROL

A. Testing Agency: Contractor will engage an independent qualified testing agency to perform tests and inspections.

B. Perform the following tests and inspections:

1. Packaged, Cementitious Patching Mortar: 5 randomly selected sets of samples for each type of mortar required, tested according to ASTM C 928. 2. Concrete: As specified in Division 03 Section " Miscellaneous Cast-in-Place Concrete ."

C. Product will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

END OF SECTION

Repairs of Boat Ramps 03013 - 6 MAINTENANCE OF Sandy Point State Park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010

SECTION 03301

MISCELLANEOUS CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes cast-in-place concrete, including reinforcement, concrete materials, mixture design, placement procedures, and finishes to provide new concrete curbs at the end of the boat ramps.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Other Action Submittal:

1. Design Mixtures: For each concrete mixture.

1.3 QUALITY ASSURANCE

A. Ready-Mix-Concrete Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.

B. Comply with the following sections of ACI 301, unless modified by requirements in the Contract Documents:

1. "General Requirements." 2. "Formwork and Formwork Accessories." 3. "Reinforcement and Reinforcement Supports." 4. "Concrete Mixtures." 5. "Handling, Placing, and Constructing."

C. Comply with ACI 117, "Specifications for Tolerances for Concrete Construction and Materials."

PART 2 - PRODUCTS

2.1 FORMWORK

A. Furnish formwork and formwork accessories according to ACI 301.

2.2 STEEL REINFORCEMENT

A. Reinforcement Steel: Concrete reinforcement shall be deformed billet-steel bars per ASTM A615, Grade 60. Reinforcement shall be newly rolled in an approved mill and Repairs to Boat Ramps 03301 - 1 MISCELLANEOUS

Sandy Point State park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 accurately fabricated to the dimensions indicated on the Drawings. Rail-steel bars not prohibited.

2.3 CONCRETE MATERIALS

A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source throughout Project:

1. Portland Cement: ASTM C 150, Type I/II.

a. Fly Ash: ASTM C 618, Class C or F. b. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 100 or 120.

B. Normal-Weight Aggregate: ASTM C 33, graded, 1-1/2-inch nominal maximum aggregate size.

2.4 ADMIXTURES

A. Air-Entraining Admixture: ASTM C 260.

B. Water reducing and retarding admixture conforming to ASTM C494, Type D when concrete placed at ambient air temperature above 75 deg. F. when temperature are below 75 deg. F, a water-reducing admixture shall be use conforming to ASTM C494, Type A. Proportioning and mixing shall be as recommended by the manufacturer.

C. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

2.5 CURING MATERIALS

A. Curing or Curing and Hardening Compounds: ASTM C309, Type I-D.

B. Sheet Material for Curing Concrete: ASTM C171.

2.6 CONCRETE MIXTURES

A. Comply with ACI 301 requirements for concrete mixtures.

B. Normal-Weight Concrete: Prepare design mixes, proportioned according to ACI 301, as follows:

1. Minimum Compressive Strength: 4500 psi at 28 days. 2. Maximum Water-Cementitious Materials Ratio: 0.45 3. Cementitious Materials: Use fly ash, pozzolan, and ground granulated blast- furnace slag as needed to reduce the total amount of portland cement, which would otherwise be used, by not more than 50 percent. 4. Slump Limit: 4 inches, plus or minus 1 inch. 5. Air Content: 6%, +/-1%. Repairs to Boat Ramps 03301 - 2 MISCELLANEOUS

Sandy Point State park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 2.7 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M, and furnish batch ticket information.

1. When air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.

B. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M. Mix concrete materials in appropriate drum-type batch machine mixer.

1. For mixer capacity of 1 cu. yd. or smaller, continue mixing at least 1-1/2 minutes, but not more than 5 minutes after ingredients are in mixer, before any part of batch is released. 2. For mixer capacity larger than 1 cu. yd., increase mixing time by 15 seconds for each additional 1 cu. yd.. 3. Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mix type, mix time, quantity, and amount of water added. Record approximate location of final deposit in structure.

PART 3 - EXECUTION

3.1 FORMWORK

A. Design, construct, erect, brace, and maintain formwork according to ACI 301.

3.2 EMBEDDED ITEMS

A. Place and secure anchorage devices and other embedded items required for adjoining work attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

3.3 STEEL REINFORCEMENT

A. Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.

3.4 JOINTS

A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

B. Construction Joints: Locate and install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Engineer.

3.5 CONCRETE PLACEMENT

A. Comply with ACI 301 for placing concrete.

Repairs to Boat Ramps 03301 - 3 MISCELLANEOUS

Sandy Point State park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 B. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301.

C. Do not add water to concrete during delivery, at Project site, or during placement.

D. Consolidate concrete with mechanical vibrating equipment.

E. Placing on Ground or Subcourse: Subgrade or base course shall be free from injurious material, well drain, and moist at time of concreting. Prior to placing concrete, thoroughly clean and dampen as necessary leaving no free water standing on base course or subgrade and no soft or muddy spots in subgrade.

F. Deposit concrete into the forms as nearly as practical to its final position, and in a manner not to cause or permit segregation. Do not use vibrators for extensive shifting of the mass of fresh concrete. The free drop of any concrete shall not exceed three feet without the use of adjustable length pipes.

G. Layers of concrete shall not be tapered off in wedge shaped slopes but shall be built with squared ends and level tops. Deposit concrete continuously or in layers of such thickness that no concrete will be deposited on concrete which has hardened sufficiently to cause the formation of seams or planes of weakness within the section. If a section cannot be placed continuously, locate construction joints at points as indicated or as approved. Place concrete at such a rate that all concrete being integrated with fresh concrete is plastic.

H. Align slab top surfaces to screed contours by strikeoff, or if the nature of the finished surface so requires, by approved vibrating screeds or roller pipe screeds.

3.6 CONSOLIDATION

A. Consolidation: Consolidate concrete in accordance with ACI 309R. Consolidate concrete by means of approved internal vibrators. The vibrator operators shall be experienced in operating the equipment for a minimum of three years.

B. Employ a sufficient number of vibrators to consolidate the incoming concrete to a proper degree within 15 minutes after depositing in forms. In all cases, maintain at least one spare vibrator available at the site of any structure during concrete placement. Do not vibrate the forms or the reinforcing steel.

C. The location, manner and duration of the application of vibrators shall be such as to secure maximum consolidation of the concrete without causing segregation of mortar and coarse aggregate and without causing water or cement paste to flush to the surface. The thickness of the layers shall be not greater than can be satisfactorily consolidated by vibrators. Vibrators shall vertically penetrate a few inches into the previous lift at regular intervals.

3.7 FINISHING UNFORMED SURFACES

A. General: Comply with ACI 302.1R for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

Repairs to Boat Ramps 03301 - 4 MISCELLANEOUS Sandy Point State park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010 B. Screed surfaces with a straightedge and strike off. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane before excess moisture or bleedwater appears on surface.

1. Do not further disturb surfaces before starting finishing operations.

2. Provide herringbone pattern to match adjacent existing boat ramp slab.

3.8 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and with ACI 301 for hot-weather protection during curing.

B. Evaporation Retarder: Apply evaporation retarder to concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

C. Curing Methods: Cure formed and unformed concrete for at least seven days by the following method:

1. Curing and Sealing Compound: Apply uniformly to slabs in a continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Repeat process 24 hours later and apply a second coat. Maintain continuity of coating and repair damage during curing period.

3.9 FIEL D QUALITY CONTROL

A. Testing Agency: Contractor will engage a qualified testing agency to perform tests and inspections.

B. Tests: Perform according to ACI 301.

1. Testing Frequency: Obtain at least one composite sample for each 150 cu. yd. or fraction thereof of each concrete mixture placed each day. If total volume of concrete is such that frequency of testing required would provide less than five strength tests for a give class of concrete, test shall be made from at least five randomly selected batches or from each batch if fewer than five batches are used.

2. Each composite sample shall consist of nine, 4 inch by 6 inch, standard cured cylinders (ASTM C31) made from the same sample of concrete. Perform strength tests in accordance with ASTM C39 at 7 days, 28 days, and 56 days.

3.10 REPAIRS

A. Remove and replace concrete that does not comply with requirements in this Section.

END OF SECTION Repairs to Boat Ramps 03301 - 5 MISCELLANEOUS

Sandy Point State park CAST-IN-PLACE CONCRETE Anne Arundel County, MD P-021-102-010

SECTION 06108

EXTERIOR ROUGH CARPENTRY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Provide new diagonal bracing members that are not embedded in concrete in between the timber piles of the boat ramps’ wood piers. Provide new connection hardware to connect the diagonal bracing members to the timber piles.

2. Provide new stringers, butt blocks, decking boards in between two column lines to facilitate the installation of vinyl sheet piling.

1.2 DEFINITIONS

A. Dimension Lumber: Lumber of 2 inches nominal or greater but less than 5 inches nominal in least dimension.

B. Lumber grading agencies, and the abbreviations used to reference them, include the following:

1. SPIB: The Southern Pine Inspection Bureau. 2. ALSC: American Lumber Standard Committee. 3. NDS: National Design Standard – ANSI/AF&PA NDS 4. FSC: Forest Stewardship Council. 5. AWPA: American Wood Preservers Association

1.3 SUBMITTALS

A. Product Data: For preservative-treated dimension lumber and fasteners.

B. Material Certificates:

1. Notarized certificate of treatment from supplier that timber meets specifications as to the type of treatment used, method of applications and final net retention by assay in pounds per cubic foot.

PART 2 - PRODUCTS

2.1 LUMBER, GENERAL

A. Lumber: Comply with DOC PS 20 and with applicable rules of grading agencies indicated. If no grading agency is indicated, provide lumber that complies with the applicable rules of any rules-writing agency certified by ALSC's Board of Review.

Repairs to Boat Ramps 06108-1 EXTERIOR ROUGH CARPENTRY Sandy Point State Park Anne Arundel County, MD P-021-102-010 Provide lumber graded by an agency certified by ALSC's Board of Review to inspect and grade lumber under the rules indicated.

1. Factory mark each item with grade stamp of grading agency. 2. For items that are exposed to view in the completed Work, mark grade stamp on end or back of each piece. 3. All lumber shall be free from wrap, knot holes, and excessive checking. 4. Provide dressed lumber, S4S (surface four side), PET (precision end trim). Kiln dried to within 1/4 inch of length specified before treatment. 5. Lumber shall be banded properly for handling and shipment.

2.2 DIMENSION LUMBER

A. Dimension Lumber: Southern pine, No. 1 SPIB

B. Minimum allowable stresses Fb = 1,250 psi and modulus of elasticity E = 1,600,000 psi.

2.3 PRESERVATIVE TREATMENT

A. Fabricate lumber before preservative treatment. Each piece of treated lumber shall be branded, by the producer, in accordance with AWPA M6.

B. Pressure treats stringers and decking boards with waterborne preservative according to AWPA Use Category 4B (UC4B)

1. ACQ with minimum retention of 0.60 pounds per cubic foot

C. Pressure treats bracing dimension lumber with waterborne preservative according to AWPA Use Category 5B (UC5B).

1. CCA with minimum retention of 2.50 pounds per cubic foot

D. Mark treated wood with treatment quality mark of an inspection agency approved by ALSC's Board of Review.

E. Application: Treat all exterior rough carpentry unless otherwise indicated.

2.4 FASTENERS

A. General: Provide fasteners of size and type indicated that comply with requirements specified in this article for material. Provide nails or screws, in sufficient length, to penetrate not less than 2-1/2 inches into wood substrate.

1. For pressure-preservative-treated wood – use hot-dipped galvanized fasteners that meet ASTM A 153 unless noted otherwise. The zinc coating shall be class A, a minimum of 2.0 ounces of zinc per square foot of hardware surface.

Repairs to Boat Ramps 06108-2 EXTERIOR ROUGH CARPENTRY Sandy Point State Park Anne Arundel County, MD P-021-102-010 2. For wood decking, use stainless-steel (type 316) fasteners where fasteners are exposed to view.

B. Nails: ASTM F 1667 (Ring Shank Patio/Deck Nail – 20D).

C. Wood Screws and Lag Screws: ASME B18.2.1, ASME B18.6.1, or ICC-ES AC233.

D. Carbon-Steel Bolts: ASTM A 307 with ASTM A 563 nuts and where indicated, flat washers all hot-dip zinc coated.

E. Plate Washer: Plate washer shall be fabricated from ASTM A 36 steel.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Set bracing lumber to match existing location and existing bolt holes on the timber piles. Provide bracing of sufficient length to provide a minimum 6 inches between outside bolt and end of brace. Bracing shall bear firmly against piles. Place fillers to avoid bending the bracing more than 1 inch out of line when bracing bolts are drawn up tight. Built-up filler will not be permitted. Make filler a single piece of the same treated lumber as that in the brace, with a width of at least 6 inches and a length of at least 12 inches. Bolt ends of brace through pile with a bolt of at least the indicated diameter.

B. Frame lumber so joints will fit over contact surface and in alignment. Open joints are unacceptable.

C. Bore holes for drift pins and dowels with a bit 1/16 inch less in diameter than the pin or dowel. Bore holes for through bolts with bit 1/16 inch larger in diameter than the bolt. Bore holes for lag screws in two parts. Make lead hole for shank the same diameter as shank. Make lead hole for the threaded portion approximately two-thirds of the shank diameter.

D. Place stringers crown up and, if possible, the better edge of deck stringers down. Tops of stringers shall not vary from a plane more than will permit bearing of the decking boards on stringers.

E. Make decking of a single thickness of plank supported by stringers. Unless otherwise indicated, lay plank with heart side down and with tight joints. Fastener each plank to each stringer with at least three hot-dipped galvanized ring shank nails (size 20d). Place nails at least 1-1/2 inches from edges of the plank.

F. Do not splice structural members between supports

G. Comply with AWPA M4 for applying field treatment to cut surfaces of preservative- treated lumber.

END OF SECTION

Repairs to Boat Ramps 06108-3 EXTERIOR ROUGH CARPENTRY Sandy Point State Park Anne Arundel County, MD P-021-102-010

SECTION 07920

JOINT SEALANTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Elastomeric joint sealants.

1.2 PRECONSTRUCTION TESTING

A. Preconstruction Field-Adhesion Testing: Before installing sealants, field test their adhesion to Project joint substrates. Test joint sealants according to Method A, Field- Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

1.3 ACTION SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

1.4 INFORMATIONAL SUBMITTALS

A. Product test reports.

1. Joint Sealant: Submit catalog cuts, specifications, materials Safety Data Sheets and other information documenting conformance to contract requirements.

B. Field-adhesion test reports.

C. Warranties.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Inspect materials delivered to the site for visible damage, and unload and store with a minimum of handling. Joint materials shall be delivered in original sealed containers and shall be protected from freezing or overheating. Provide jobsite storage facilities capable of maintaining temperature ranges within manufacturers recommendations.

1.6 ENVIRONMENTAL REQUIREMENTS

A. Work shall not proceed when weather conditions detrimentally affect the quality of cleaning joints or applying joint sealants. Joint preparation and sealing shall proceed only when weather conditions are in accordance with manufacturer's instructions. During

Repairs to Boat Ramps 07920-1 JOINT SEALANTS Sandy Point State Park Anne Arundel County, MD P-021-102-010 installation, surfaces shall be dry and sealant and bond breakers shall be protected from moisture.

1.7 EQUIPMENT

A. Submit an equipment list and description of the equipment to be used and a statement from the supplier of the joint sealant that the proposed equipment is acceptable for installing the specified sealant. Equipment for heating, mixing, and installing joint seals shall be in accordance with the instructions provided by the joint seal manufacturer. Furnish equipment, tools, and accessories necessary to clean existing joints and install liquid joint sealants. Maintain machines, tools, and other equipment in proper working condition.

1. Joint Cleaning Equipment

a. Concrete Saw: Self-propelled power saw with diamond saw blades designed for sawing, refacing, widening, or deepening existing joints as specified without damaging the sides, bottom, or top edge of joints. Blades may be single or gang type with one or more blades mounted in tandem for fast cutting. Select saw adequately powered and sized to cut specified opening with not more than two passes of the saw through the joint.

b. Sandblasting Equipment: Commercial type capable of removing residual sealer, oil, or other foreign material. Equipment shall include an air compressor, hose and nozzles of proper size, shape, and opening. Attach an adjustable guide that will hold the nozzles aligned with the joint to effectively and efficiently clean without damage to concrete edges. Adjust height, angle of inclination, or size of nozzles to sandblast joint faces and not bottom of joint.

c. Air Compressor: Portable air compressor capable of operating the sandblasting equipment and capable of blowing out sand, water, dust adhering to sidewalls of concrete, and other objectionable materials from the joints. The compressor shall furnish air at a pressure not less than 90 psi and a minimum rate of 150 cubic feet of air per minute at the nozzles and free of oil.

d. Vacuum Sweeper: Self-propelled, vacuum pickup sweeper capable of completely removing loose sand, water, joint material, and debris from concrete surface.

e. Hand Tools: When approved, hand tools such as brooms and chisels may be used in small areas for repairing or cleaning the joint faces.

f. Joint Sealing Equipment: Joint sealing equipment shall be of a type required by the joint seal manufacturer's installation instructions.

Repairs to Boat Ramps 07920-2 JOINT SEALANTS Sandy Point State Park Anne Arundel County, MD P-021-102-010 Equipment shall be capable of installing sealant to the depths, widths and tolerances indicated. When malfunctions are noted, joint sealing shall not proceed until they are corrected.

1.8 QUALITY ASSURANCE

A. Testing Agency Qualifications: Qualified according to ASTM C 1021 to conduct the testing indicated.

1.9 WARRANTY

A. Special Installer's Warranty: Manufacturer's standard form in which Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Two years from date of Substantial Completion.

B. Special Manufacturer's Warranty: Manufacturer's standard form in which joint-sealant manufacturer agrees to furnish joint sealants to repair or replace those that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Two years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Source Limitation: Obtain joint sealant and primer from simple source with resources to provide products of consistent quality in appearance and physical properties.

B. Liquid-Applied Joint Sealants: Comply with ASTM C 920 and other requirements indicated for each liquid-applied joint sealant specified, including those referencing ASTM C 920 classifications for type, grade, class, and uses related to exposure and joint substrates.

1. Suitability for Immersion in Liquids. Where sealants are indicated for Use I for joints that will be continuously immersed in liquids, provide products that have undergone testing according to ASTM C 1247. Liquid used for testing sealants is deionized water, unless otherwise indicated.

2.2 ELASTOMERIC JOINT SEALANT

A. Elastomeric Joint Sealant : ASTM C 920.

Repairs to Boat Ramps 07920-3 JOINT SEALANTS Sandy Point State Park Anne Arundel County, MD P-021-102-010 1. Joint Sealant shall be Sikaflex-2cNSEx mix or approved equal.

2. Type: multicomponent (M).

3. Grade: nonsag (NS).

4. Class: 25.

5. Uses Related to Exposure: Traffic (T) .

2.3 JOINT SEALANT BACKING

A. Cylindrical Sealant Backings: ASTM C 1330, Type C (closed-cell material with a surface skin), and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance.

1. Backer Rod: Compressible, nonshrinkable, nonreactive with joint sealant and nonabsorption. Free of oils or bitumens. Backer Rod shall be consistent with the joint seal manufacturer's installation instructions and be at least 25 percent larger in diameter than the width of the cleaned and re-faced joints as shown

2.4 MISCELLANEOUS MATERIALS

A. Primer: Primer shall be Sikaflex Sealant/Adhesive Primers 929/202, or approved equal.

PART 3 - EXECUTION

3.1 JOINT PREPARATION

A. Unless otherwise indicated, remove existing material, saw, clean and seal joints. Do not proceed with final cleaning operations by more than one working day in advance of sealant. Thoroughly clean joints by removing bond-breakers, dirt, and other foreign material with the equipment specified herein, but not limited thereto. Cleaning procedures which damage joints or previously repaired patches by chipping or spalling will not be permitted. Precise shape and size of existing joints vary, and conditions of joint walls and edges vary and include but are not limited to rounding, square edges, sloping, chips, voids, depressions, and projections.

B. Refacing the Joints: Reface concrete joint walls. Re-saw joint grooves to the dimensions indicated. Refacing shall be by power-driven concrete saw specified herein to remove residual sealant and a minimum of concrete. Removal shall provide exposure of newly clean concrete. Remove burrs and irregularities from sides of joint faces. Immediately after sawing each joint, thoroughly clean saw cut and adjacent concrete surface. Flush with water under pressure, simultaneously blowing water out with compressed air until debris is removed from the joint. Protect adjacent previously cleaned joint spaces from receiving water and debris during the cleaning operation.

Repairs to Boat Ramps 07920-4 JOINT SEALANTS Sandy Point State Park Anne Arundel County, MD P-021-102-010 C. Final Cleaning of Joints

1. Sandblasting Cleaning: Following removal of existing material, and sawing, and immediately before sealing, thoroughly clean newly exposed concrete joint faces and pavement surface extending up to 2 inches from each joint edge by sandblasting until concrete surfaces in the joint space are free of sealants, dust, dirt, water and other foreign materials which would prevent bonding of new sealants to the concrete. Use sand particles of the proper size and quality for the work. Perform sandblasting with specified nozzles, air compressor, and other appurtenant equipment. Position nozzles to clean the joint faces. Make at least two passes; one for each joint face. Make as many passes as required for proper cleaning. Immediately prior to sealing the joint, blow out the joint spaces with compressed air until completely free of sand, water, and dust. Joints shall be dry before installation of joint sealant. Replace expansion joint filler material damaged in performing the work with new materials of the same type and dimensions as the existing material, or with appropriate blocking media.

D. Backer Rod: Plug or seal off the lower portion of the groove by installing the specified blocking media as indicated.

E. Rate of Progress: The final stages of joint preparation, which include placement of backer rod, if required, shall be limited to only that length of joint that can be sealed during the same workday.

F. Disposal of Debris: Sweep from pavement surface to remove excess joint material, dirt, water, sand, and other debris by vacuum sweepers or hand brooms. Remove the debris immediately in accordance with Section 024119 SELECTIVE DEMOLITION.

3.2 PREPARATION OF SEALANT

A. Test Section: Install a test section of 50 linear feet at the start of the sealing operation for each type sealant to be used. A representative of the joint seal manufacturer shall be on site full time during the installation of the test section. Test section shall meet contract requirements. The Engineer shall be notified upon completion of the test section

B. Time of Application: After approval of the test section, seal joints immediately following final cleaning and placing of bond breakers. Commence sealing joints when walls are dust free and dry, and when weather conditions meet joint seal manufacturer's instructions. If the above conditions cannot be met, or when rains interrupts sealing operations, reclean and permit the joints to dry prior to installing the sealant.

C. Sealing the Joints: Do not install joint sealant until joints to be sealed have been inspected and approved. Install bond breaker just prior to pouring sealant. Fill the joints with sealant from bottom up until joints are uniformly filled solid from bottom to top using the specified equipment for the type of sealant required. Fill joints to flush with top of pavement and without formation of voids or entrapped air. Except as otherwise permitted, tool the sealant immediately after application to provide firm contact with the

Repairs to Boat Ramps 07920-5 JOINT SEALANTS Sandy Point State Park Anne Arundel County, MD P-021-102-010 joint walls and to form the indicated sealant profile below the pavement surface. Remove excess sealant that has been inadvertently spilled on the pavement surface. When two- component sealants are placed, each day check hourly the proportioning capability of the equipment to determine that the preset volume output for each component is being maintained. The material used for these checks may be returned to the proper component reservoir. In no case shall two component sealants be installed using gravity methods and pouring spouts, except for approved hand mixing methods. When a primer is supplied or recommended by the manufacturer of a two component sealant, apply the primer evenly to the joint faces in accordance with the manufacturer's recommendations. Check sealed joints frequently to assure that newly installed sealant is cured to a tack-free condition within 3 hours. Protect new sealant from rain during curing period.

D. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.

1. Remove excess sealant from surfaces adjacent to joints.

2. Use tooling agents that are approved in writing by sealant manufacturer and that do not discolor sealants or adjacent surfaces.

3. Provide concave joint profile per Figure 8A in ASTM C 1193, unless otherwise indicated.

E. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

3.3 FIELD QUALITY CONTROL

A. Field-Adhesion Testing: Field test joint-sealant adhesion to joint substrates as follows:

1. Extent of Testing: Test completed and cured sealant joints as follows:

a. Perform 10 tests for the first 1000 feet of joint length for each kind of sealant and joint substrate. b. Perform 1 test for each 1000 feet of joint length thereafter or 1 test per each floor per elevation.

2. Test Method: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

B. Evaluation of Field-Adhesion Test Results: Sealants not evidencing adhesive failure from testing or noncompliance with other indicated requirements will be considered satisfactory. Remove sealants that fail to adhere to joint substrates during testing or to comply with other requirements. Retest failed applications until test results prove Repairs to Boat Ramps 07920-6 JOINT SEALANTS Sandy Point State Park Anne Arundel County, MD P-021-102-010 sealants comply with indicated requirements.

C. Sampling Joint Seal: Obtain a one gallon sample of each type of joint seal on the project from material used for each 3,000 m (10,000 linear feet) or less of joints sealed. Store samples according to joint seal manufacturer's instructions. Retain samples until final acceptance of the work by the Contracting Officer.

D. Joints: Inspect and approve joints which have been cleaned and have backer rods or bond breaking tape installed prior to sealing.

E. Joint Seal Test Section: Inspect joint seal test section with the joint seal manufacturer's representative. The joint seal manufacturer's representative shall provide written notice of deficiencies and required corrections or adjustments in joint seal installation procedures. Correct deficiencies and obtain approval of test section by the Engineer prior to installing joint seals.

F. Joint Sealer: Inspect installed joint seals for conformance to contract requirements, joint seal manufacturer's instructions, and the test section. Obtain approval for each joint seal installation.

3.4 ACCEPTANCE

A. Reject joint sealer that fails to cure properly, or fails to bond to joint walls, or reverts to the uncured state, or fails in cohesion, or shows excessive air voids, blisters, surface defects, swelling, or other deficiencies, or is not properly recessed within indicated tolerances. Remove rejected sealer and reclean and reseal joints in accordance with the specification. Perform removal and reseal work promptly by and at the expense of the Contractor

END OF SECTION

Repairs to Boat Ramps 07920-7 JOINT SEALANTS Sandy Point State Park Anne Arundel County, MD P-021-102-010

APPENDIX A

WETLANDS LICENSE

Repairs to the Boat Ramps Sandy Point State Park Anne Arundel County, MD P-021-102-010

State of Maryland

Board of Public Works Wetlands Administration Post Office Box 1510

Annapolis, Maryland 21404 Peter Fta:a:acltut 410-260-7791 Compfto!ln-

Doldon W. Moore,Jr. Fax:410-974-5240 Sheil. C. McDon.Jd Wttlllntls AdminUtrator &mdiw Stcrd4ry Toll Free:1-877-591-7320

December 7, 20 II

Dept. ofNatural Resources Attn: Dave Decker, Engn. & Canst. 580 Taylor Ave. AnnapolisMD 21401

Dear Applicant(s):

RE: Wetlands Licen:;e No. 12-0119, Sandy Point State Park, Anne Arundel County

Enclosed please find the original and one copy of the above-mentioned wetlands license issued to you on December 7, 2011.

After you have read all the conditions of the license, please ensure that the license is signed by the named licensee and the entire original (including plans) is returned to this office within 15 days in the enclosed envelope. Please retain the copy of the license for your records. This license is valid for a period of three years, as indicated on page three.

Please note that you must notify the MD Department of the Environment, Inspections and Compliance Program, by calling (410) 537-3510 in Baltimore, or (410) 901-4020 in Cambridge, prior to commencing work.

This does not constitute your federal authorization. Please contact the U.S. Army Corps of Engineers, Baltimore District, at (410) 962-4500 (Maryland Section Southern) or (410) 962-4252 (MD Section Northern) regarding the status of the federal permit, if it has not been received.

If you have any questions concerning any of the terms and conditions of the attached license, please contact me at the address or telephone number shown above.

;! Doldon=:it W. Moore, Jr./

Wetlands Administrator

Enclosure cc: MDE, Tidal Wetlands Division

Internet address:httpllwww.bpw.state.md.us • E-mail a s: [email protected] Fo'tho hearing U.pai:ed' M"J'Iand Rclay 711 o TTY 41G-260-7157 o EOE

State of Maryland Mmin O'Milley Board of Public Works o...rn Wetlands Administration Post Office Box 1510

Annapolis, Maryland 21404 Peter Franchot 410-260-7791 C...pmik>-

Doldon W.Moore,Jr. Fax:410-974-5240 Sheih C. McDonald Wetlands Administrator Toll Free:1-877-591-7320 E=uJiu S=tary

WETLANDS LICENSE NO. 12-0119

MARYLAND DEPARTMENT OF NATURAL RESOURCES

In response to an application dated August 8, 2011, for a Wetlands License, upon the recommendation of the Wetlands Administrator of the Board of Pnblic Works, and pUISuant to the provisions of Title 16, Environment Article, Annotated Code of Maryland (1996 Rep!. Vol. and Supplement), entitled "Wetlands and Riparian Rights," enacted to provide a State policy for the preservation of wetlands and regulation of the filling and dredging of wetlands in Maryland, and for other pwposes, you are hereby authorized by the Board ofPnblic Works, for the State of Maryland to:

"Maintain and repair the existing 528-foot long boat ramp section that includes the installation of new sheeting at the outboard end of the concrete boat ramp and the filling of any voids underneath the ramp, in addition to adding sand fill for added scour protection, a maximum of 46 feet channelward of the mean high water, as depicted on the attached plans dated September 16, 20ll; and to repair and replace the decking and stringers over and above the section of ramp to be repaired.., Mezick Pond at Sandy Point State Park. Anne Arundel County

This license is subject to the following special conditions:

A. All work shall be permitted under, and performed in accordance with, the Critical Area requirements of the local jurisdiction where the project is located. This authorization does not constitute authorization for disturbance in the l 00-foot Critical Area Buffer. "Disturbance" in the Buffer means clearing, grading, construction activities, or removal of any size of tree or vegetation. Any anticipated Buffer disturbance requires prior written approval, before commencement of land-disturbing activity, from the local jurisdiction in the fonn of a Buffer Management Plan.

B. All work shall be performed in accordance with the required Soil Erosion and Sediment Control Plan as approved by the Anne Arundel County Soil Conservation District.

C. All work shall be performed in accordance with the required Water Quality Certification issued by the Maryland Deparbnent of the Environment and in accordance with the Maryland State Programmatic General Permit (MDSPGP-3) or the U.S. Army Corps of Engineers' Individual Authorization.

Internet address: http/lwww.bpw.state.md.us • E-mail address: [email protected] For the hearing impaired: Maryland Relay 711 • TrY 410-260-7157 • EOE

Tidal Wetlands License No. 12-0119 MDDNR December 7, 2011

-lA-

D. No marsh shall be filled, dredged, or otherwise altered or destroyed.

E. The Maryland Department of Environment has determined that the proposed activity complies with, and will be conducted in a manner consistent with, the State's Coastal Zone Management Program, as required by Section 307 of the Federal Coastal Zone Management Act of 1972, as amended.

F. All work performed under this tidal wetlands license shall be conducted by the property owner or by a marine contractor registered with the Maryland Department of the Environment in accordance with Chapter 286 of the 2010 Laws of Maryland. A list of registered marine contractors can be obtained by contacting the Department at 410-537- 3837 or by visiting the department's website at: http://www.mde.state.md.us/prograrns/ water/wetlandsandwaterways!documents/marinecontractor_registered_list.pdf.

G. The license shall remain onsite during construction and be made available to representatives of the Maryland Department of the Environment during routing compliance inspections.

The authorized work is to be accomplished in accordance with the plans and drawings attached hereto, dated September 16, 20II.

This license is subject to the following general conditions and is revocable or subject to modification prior to the completion of the project as described above when such action is deemed to be in the State's interest.

-2-

This license is subject to the following standard conditions:

a. This license does not authorize a trespass or infringement upon private or public property rights or interests, nor does it relieve the licensee of the obligation to obtain applicable federal, State, or local approvals.

b. The legal requirements of all federal, State, and local agencies shall be met.

c. The license does not transfer a property interest of the State Wlless expressly stated by the Board of Public Works (usually in a separate document).. d. The licensee shall allow full and free use by the public of State wetlands and navigable waters. e. A copy of this license and the plans or drawings attached hereto shall be available at the site until the construction or activity is complete. f The licensee shall submit written notification to the Inspections and Compliance Program of the MD Department of the Environment at least I 0 days in advance of commencing the construction or activity, and shall furnish written notification of the date of its completion within 30 days. g. The licensee consents to reasonable inspections by representatives of the Board of Public Works or the MD Department of the Environment to ens\U'e consistency with the conditions of the license. h. The licensee shall comply promptly with any lawful regulations, conditions, or site complaints and orders affecting the structure or activity authorized herein, if and when issued by the MD Department of the Environment, which is authorized to enforce this license.

1. The licensee shall maintain the structure authorized herein in good condition or perform the activity in accordance with the approved plans or drawings and otherwise comply with all license provisions !llllil the structure is removed or the activity permanently ceases. j. The Board of Public Works or the Wetlands Administrator may modifY, suspend, or revoke this license as necessary to protect the State's interests. The decision to modify, suspend, or revoke the license shall be based upon a consideration of the ecological, economic, developmental, recreational, and aesthetic values involved as they may :dfect the public a..11d propriet ' ry L11terests of the State.

- 3 -

k. Any modification, suspension, or revocation of this license shall not be the basis for a claim for damages against the State of Maryland, or any unit or agency of the State.

1. All provisions of this license shall be binding on any assignee or successor in interest of the licensee, with the procedure for assignment or transfer set by the Board of Public Works.

m. The licensee or any successor or assignee agrees to make every reasonable effort to construct the structure or perfonn the activity authorized herein in a workmanlike manner so as to eliminate or minimize any adverse effects of the construction or activity on fish, wildlife and natural environmental values.

n. The licensee agrees to indemnify, defend and save harmless the State of Maryland, its elected officials, officers and employees from and against any and all liability, suits, claims and actions of whatsoever kind, caused by or arising from the placement of fill and/or piles or construction of structures in the waters of the State pursuant to this wetlands license.

o. If the structure or activity authorized herein is not completed on or before the 7th day of December, 2014, this license, if not previously revoked or specifically extended, shall cease and be null and void. NOTE: In most cases, a 3-year license may be renewed for one additional3-year period if the request is received prior to the expiration date; 6-year licenses cannot be renewed and licensee must reapply to the Maryland Department of Environment.

By the authority of the Board of Public Works:

Issued for and in behalf of the Members of the Board old Executive Secretary

Effective Date: December 7, 20 II

The terms and conditions of this license are hereby accept ..!?

IZ)zt/2.DI{ Date ;-L'"icCJenl.;s:.>ee=O;(S ignUatu4-

I

\

5"' 7 :i I ! -•.3.! 5.Sf :;:,'': ' ' \ ' : • -29 I ' .!19 I ' PAVED ?.4f"KIM;; '-CT

\

II) 21 1

I -e.2c,. I - .2l ' '' \_ ....

SANDY POINT BOAT RAMP AlfNII ARUNDEL COUN'l'Y, l!ARYLAND 1" 60' 1 "' 4

A.L No. 88960 Tidal Autb. No. ll-WI,0119 Trackioe- No. 201161193

I I

I I

\ SANDY POINT STATE PARK . D.

..., I

' ' ' \ I I I ' ' I '

\

GENERAL NOTES I \

15' JO' ... b I

SITE PLAN 9/11/2011 SANDYANN!: ARUNDELPOINT COUNTY, BOAT M/J!YUNIJ RAMP l" = 60' 2 of (

A.L No. 88960 Tidal Auth. No. 12-WL-0119 Trackinrz No. 201161193

0 . ,-,_·.. . - -o·-_.:0 - 0 0

I I -I'

_¢ ---- _,' · · .. "'' ' ,, 0' ''t.; \ ,_,

- '- - - -

SCAlf:TYPICAL 1/16" • 1'BOAT-(1' RAMP ENLARGED PLAN

{. ... ------.. --. --

SCAl£• : 1/16' .. f -{}'

I SI ::::::::::::::::;=:::::::::::: =J ., ,t N un:;e:::::::::::::r R • un p LAN ;=:::;Do g:= SANDY POINT BOAT RAMP A ECTIONScale 9/16/2011Sheet ;:L.lll.li-'J.-W-I., 1: JD·X:lAw1.IS,·W-' ------A-R_mmn c_o_u_NTY._ YUND - 1 1-_._=_!_'_6 -_o_" s -w-= '

A.L No. 88960 Tidal Autb. No.ll-WL-0119 Trackin2 No. 201161193

REiillJj[ 1-r' If" 'EXiSJliiC TilER SIIDIIG. REST IF {)(5;N; HrntG ro RElWf llll&HA Ill. 57 ,..... """"" ."..."." '

(,hl A ,.f REPAIR DETAIL '-.../

N£W4'l6" """""""" ""Cll " S"I"O""'IIDI " "'""""""'

, PIER REPAIR SECTION seN.£: 1/4" .. 1'-11"

!

b ,. r ,. I SCN..E: 1/4' ., ;·-o·

Dat. Project Name DETAIL AND .·_.... I!J.A 9/16/2011 SANDY POINT BOAT RAMP SECTION Sheet ; : ..,.. --.IIIIIIIIN.IIDtu!n ANN1 ARUNDEL COUNTY, MARYUND / " 4 = 1 0 4 of 4

A.L No. 88960 Tidal Autb. No. ll-WL-0119 Trackine: No. 201161193 -llllllWI , • """"" ' -" '------,_ ,

A.L No. 88960 Tidal Autb. No. ll-WL-0119 Trackine: No. 201161193

APPENDIX B

Environmental Correspondence

Repairs to the Boat Ramps Sandy Point State Park Anne Arundel County, MD P-021-102-010

USFWS Field Office -- Online certification letter Page 1 of2

United States Department of the Interior U.S. Fish & Wildlife Service Chesapeake Bay Field Office 177 Admiral Cochrane Drive Annapolis, MD 21401 410/573 4575

Online Certification Letter

Project: The goal of the project is to install new sheeting at the outboard end of the concrete boat ramps and fill any voids underneath the ramp with suitable material. •·•········································•···········•··••·••······•·•·•·•••·•••••••·•••·•······························•••

Dear Applicant for online certification:

Thank you for choosing to use the U.S. Fish and Wildlife Service Chesapeake Bay Field Office online list request certification resource. This letter confirms that you have reviewed the conditions in which this online service can be used. On our website (.fws.gov/chesapeakebay) are the USGS topographic map areas where no federally proposed or listed endangered or threatened species are known to occur in Maryland, Washington D.C. and Delaware.

Y<:> y 4 <:!:! 4!h<: :tx<:> P!<:>J (:;!is. <:> <:i!t:!d on the following USGS topographic map Gibson Island 7.5 min Quad Based on this information and in accordance with section 7 of the Endangered Species Act (87 Stat. 884, as amended; 16 U.S.C. 1531 et seq.), we certify that except for occasional transient individuals, no federally proposed or listed endangered or threatened species are known to exist within the project area. Therefore, no Biological Assessment or further section 7 consultation with the U.S. Fish and Wildlife Service is required. Should project plans change, or if additional information on the distribution of listed or proposed species becomes available, this determination may be reconsidered.

This response relates only to federally protected threatened or endangered species under our jurisdiction. For additional information on threatened or endangered species in Maryland, you should contact the Maryland Wildlife and Heritage Division at (410) 260-8540. For information in Delaware you should contact the Delaware Natural Heritage and Endangered Species Program, at (302) 653-2880. For information in the District of Columbia, you should contact the National Park Service at (202) 535-1739.

The U.S. Fish and Wildlife Service also works with other Federal agencies and states to minimize loss of wetlands, reduce impacts to fish and migratory birds, including bald eagles, and restore habitat for wildlife. Information on these conservation issues and how development projects can avoid affecting these resources can be found on our website (www.fws.gov/chesapeakebay).

We appreciate the opportunity to provide information relative to fish and wildlife issues, and thank you for your interest in these resources. If you have any questions or need further assistance, please contact Chesapeake Bay Field Office Threatened and Endangered Species

1 ,, II 1 (\ /1 '}/')(I1 (\

USFWS Chesapeake Bay Field Office -- Online certification letter Page 2 of2

program at (410) 573-4531.

Sincerely,

Leopoldo Miranda Field Supervisor

1 , II 1 (\/1 'l/'")1\1(\

F_ (..pt;-

t=JL WHITMAN, REQUARDT & ASSOCIATES, LLP ENGINEERS· ARCHITECTS· PLANNERS EST. 1915

October 13, 2010

Ms. Elizabeth Cole Maryland Historical Trust Project Review and Compliance, Office of Preservation Services 100 Community Place Crownsville, MD 21032

Re: Sandy Point Park Boat Ramps Maryland Department of General Services Anne Arundel County, Maryland

WR&A WO #42052-000

Dear Ms. Cole:

On behalf of the Maryland Department of General Services, Whitman, Requardt & Associates, LLP is designing the proposed maintenance improvements for the boat ramps located in Sandy Point Park in Anne Arundel County. The goal of the project is to install new sheeting at the outboard end of the concrete boat ramps and fill any voids underneath the ramp with suitable material. In addition, the sheeting will be reinforced with additional protection to prevent future scouring. Construction will be separated into two phases to maintain public access to the boat ramps at all times. Although no as-built records of the existing boat ramps are available, DNR has provided the original design drawing of the boat ramps, a topographic survey of the existing facilities and a diver investigation r port. The project location is noted on the attached USGS 7.5 Minute Quadrangle (Gibson Island (MD)).

Federal and/or State involvement for this project is Federal USACE Section 404 CWA permitting. No readily visible histOric structures, ruins or other cultural resources are identified in the project area. The project location is noted on the attached USGS 7.5 Minute Quadrangle (Germantown (MD)). Past land use at the project site is state park. Current land use is state park. No impacts are anticipated outside of the limits of disturbance (LOD).

As required by the State/Federal involvement, we are requesting any information or records regarding the presence of culturat archaeological, or historic resources within the project area. Thank you for your assistance. We look forward to working with your agency to successfully complete this needed project. Should you require additional information, please contact me at (443) 224-1601.

Sincerely,

Whitman, Requardt & Associates, LLP

Timothy Hess

Environmental Scientist

Enclosure: project location map : l 18 190 I D /IJ ' . /2./.)/ZA> hfor-k.. fY' t2:l!. s 801 South Caroline-Street, Efaltimore, Maryland 21231 www.wrallp.com · Phone: 410.235.3450 Fax: 410.243.5716

Baltimore, MD • Blacksburg, VA • Fairfax, VA • Georgetown, DE • Newport News, VA • Pittsburgh, PA • Richmond, VA • Wilmington, DE • York, PA r'.1 n" '" ''"' n•1 Sr>ttin Ys\ driz,.wri\ Local Settings\ Temporary Internet File\ Content.Outlnok \ UA3A YQBD\ ltr02_!viHT.doc

Martin O'Malley. Governor MARYLAND Anthony G. Brown, Lt.Governor DEPARTMENT OF John R.Griffin, Secretary Joseph P.Gill, Deputy Secretary NATURALRE9DURCES

11-MIS-057 December 20, 2010

Timothy Hess Whitman, Requardt & Associates, LLP 801 South Caroline Street Baltimore, MD 21231

Subject: Fisheries Information for Proposed Maintenance Improvements of Boat Ramps in Sandy Point Park in Anne Arundel County, Maryland.

Dear Mr. Hess,

The above referenced project has been reviewed to determine fisheries species in the vicinity of the proposed project. The proposed activities include the maintenance improvements of the boat ramps in Sandy Point Park in Anne Arundel County, Maryland.

The Chesapeake Bay coastline (West Chesapeake Bay Basin) and the Chesapeake Bay proper near the site are classified as Use II waters (Shell Fish Harvesting Waters). No anadromous fish species have been documented near the project site.

If you have further questions, please contact the Environmental Review Program at 410-260-8799.

Sincerely, /C: Ken Yetman Environmental Review Program

Tawes State Office Building • 580 Taylor Avenue • Annapolis,Maryland 21401

410.260.8DNR or toll free in Maryland 877.620.8DNR • www.dnr.maryland.gov • TTY users call via Maryland Relay

Attachments

\1\111ite Perch_Odell A Clupid Species_Odell • MBSS Sites MOE Designated Uses

N 0.5 0.25 0 0.5 Miles

+

Martin O'Malley,Governor ...... ,.-· ······ .... - MARYLAND Anthony G. Brown,Lt. Governor John R.Griffin, Secretary Joseph P. Gill, Deputy Secretary

December 8, 2010

Mr. Timothy Hess -. : Whitman, Requardt and Associates, LLP '· F 801 South Caroline Street Baltimore, MD 21231

RE: Environmental Review for Sandy Point State Park Boat Ramps, Maryland Department of General Services, WR&A W0#42052-000, Anne Arundel County, Maryland.

Dear Mr. Hess:

The Wildlife and Heritage Service has determined that there are no State ofFederal records for rare, threatened or endangered species within the boundaries of the project site as delineated. As a result, we have no specific comments or requirements pertaining to protection measures at this time. This statement should not be interpreted however as meaning that rare, threatened or endangered species are not in fact present. If appropriate habitat is available, certain species could be present without documentation because adequate surveys have not been conducted.

Thank you for allowing us the opportunity to review this project. If you should have any further questions regarding this information, please contact me at (410) 260-8573.

Sincerely, l ·a. Bvv-

Lori A. Byrne Environmental Review Coordinator Wildlife and Heritage Service MD Dept. of Natural Resources

ER# 2010.1563.aa Cc: B. Norden, DNR K. Charbonneau, CAC

Tawes State Office Building- 580 Taylor Avenue- Annapolis, Maryland 21401 410-260-8DNR or toll free in Maryland 877-620-8DNR- www.dnr.maryland.gov- TTY Users Call via the Maryland Relay

MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard • Baltimore MD 21230 MDE 410-537-3000.1-800-633-6101

Martin O'Malley Robert M. Summers, Ph.D. Governor Secretary

Anthony G. Brown ) .athy M. Kinsey Lieutenant Governor Deputy Secretary "

August 11, 2011 '! j / Whitman Requardt and Associates LLP Attn: Timothy Hess 801 South Caroline St Baltimore, MD 21231

Project Name: MD DNR-Sandy Point State Park Boating Facility/Boat Ramps Tracking Number: 201161193 Application Received: August 8, 2011 County: Anne Arundel

Dear Mr. Hess,

The Regulatory Services Coordination Office of the Water Management Administration (WMA) has received your Joint Application for construction in a floodplain, waterway, tidal or nontidal wetland area in Maryland.

Based upon the information contained in your application and an initial WMA review, your application has been forwarded to the following groups_ for processing:

Forwarded To: Approval Received ;g) Tidal Wetlands Division (410)537-3837' ( ) 0 Nontidal Wetlands Division (410)537-3768 ( ) 0 Dam Safety Division (410)537-3538 ( ) 0 Minerals, Oils and Gas Division (410)537-3557 ( ) 0 Source Protection and Appropriation Div (410)537-3590 ( ) ;g) U.S. Army Corps of Engineers (410)962-3670 ( )

You will be contacted individually or jointly by the groups that have been checked above. They will advise you of requirements for any additional information. If a Tidal Wetlands License issued by the State Board of Public Works is required for your project, you will be advised by that agency as to the license fee.

Recycled Paper www.mde.state.md.us TTY Users 1-800-735-2258 Via Maryland Relay Service

Joint Application for Construction Acknowledgement Letter August 11, 2011 Page2

You should not proceed with any work on your project until you have received the required written authorizations.

Obtaining the authorizations checked above will satisfy the requirements of the Water Management Administration and the federal permit from the U.S. Army Corps of Engineers. We have provided a space that you may use to check-off each approval as it is received.

You are still obligated to obtain any other required authorizations including other federal and state approvals as well as local grading and building permits. We suggest that you keep this letter to determine when all replies from the review groups have been obtained.

In many cases (principally with nontidal wetlands involvement), one review group will coordinate responses for other units. Their correspondence and approvals will indicate that they are satisfying the interests of these other review groups. When multiple permits are required for a particular project, WMA may consolidate all permit reviews into one process. If this occurs, you will be notified.

Please note that ifthe proposed project changes during the' course of processing, or if we determine other regulated resources are impacted, your application may be forwarded to another group for review. You will be notified in writing if this occurs.

For information on the status of your application, you may call the Regulatory Services Coordination Office at (410)537-3762 (Baltimore/Annapolis) or 1-800-876-0200. Please reference your tracking number listed above for all written and telephone correspondence" You may also contact the individual review groups that are processing your application at the listed telephone numbers to obtain or provide specific information relating to this application.

Sincerely,

Regulatory Services Coordination Staff

Recycled Paper www.mde.state.md.us TTY Users 1-800-735-2258 Via Maryland Relay Service

APPENDIX C

Geotechnical Report

Repairs to the Boat Ramps Sandy Point State Park Anne Arundel County, MD P-021-102-010

MARYLAND DEPARTMENT OF NATURAL RESOURCES 580 TAYLOR AVENUE TAWES STATE OFFICE BUILDING ANNAPOLIS, MARYLAND 21401

Maryland Department of Natural Resources

SANDY POINT STATE PARK BOAT RAMPS

GEOTECHNICAL REPORT

NOVEMBER, 2010

WHITMAN, REQUARDT & ASSOCIATES, LLP 801 SOUTH CAROLINE STREET BALTIMORE, MARYLAND 21231

MARYLAND DEPARTMENT OF NATURAL RESOURCES SANDY POINT STATE PARK BOAT RAMP

GEOTECHNICAL REPORT

TABLE OF CONTENTS

I. INTRODUCTION

II. GEOLOGIC SETTING

III. SUBSURFACE INVESTIGATION

IV. DISCUSSION OF SUBSURFACE CONDITIONS

V. SHEET PILING CONSIDERATIONS

VI. VOID & SCOUR CONSIDERATIONS

APPENDIX A. Boring Plan B. Driller’s Logs C. Laboratory Results

MARYLAND DEPARTMENT OF NATURAL RESOURCES SANDY POINT STATE PARK BOAT RAMPS

GEOTECHNICAL REPORT

I. INTRODUCTION

Sandy Point State Park Boat ramp provides boat access to the Chesapeake Bay from Sandy Point State Park. Twenty-two ramps provide boaters a safe place to launch and the ramps are very well used during boating season. The ramps are concrete with timber sheet piling at the toe. The soil at the toe is scouring causing the sheet piling to be exposed. Portions of the sheet piling have gone missing and voids are forming in the soil under the ramp. The ramps were constructed in 1970s, according to design drawings provided by the Maryland Department of Natural Resources (DNR).

A soils investigation was conducted during September 2010 to ascertain the subsurface conditions at the project site. Geomatrix Drilling, Inc. of Baltimore, MD drilled and sampled five (5) borings under the supervision of Whitman, Requardt & Associates, LLP. Soil samples were tested for moisture content, gradation, and Atterberg limits. Testing was conducted by O’Berry Engineering, Inc of Edgewater, Maryland. Three soil samples were taking in addition to the SPT samples and were tested for BTEX and Total Petroleum Hydrocarbons by Microbac Laboratories, Inc of Baltimore, Maryland.

II. GEOLOGIC SETTING

The project site is located within the Alluvium interbedded sand, silt-clay, and subordinate gravel as defined by the “Geologic Map of Anne Arundel County”, by John D. Glaser published in 1976 by the State of Maryland, Department of Natural Resources, Maryland Geological Survey.

III. SUBSURFACE INVESTIGATION

All of the borings, labeled SP-1 through SP-5, were located on site at the end of the concrete boat ramp with the drilling barge anchored to the nearest pier.

All borings were drilled using 6-inch diameter hollow stem augers. Samples were taken and standard penetration tests were performed using a 2-inch O.D. split spoon sampler driven by a 140-pound hammer falling freely for 30 inches. Blow counts were recorded for each 6-inch increment for a total penetration of 18 inches. For each boring samples were taken starting at the pond bottom and occurring at 5 foot intervals to a total depth of 30 feet from the pond surface.

N:\42052-000\Engineering\Design\Geotechnical Report 1

Water level readings were not taken due to the borings being drilled beneath the pond surface. The depth to the pond bottom varied throughout the day as the tide changed. Tides change based on season as well as time of day.

The Boring Location Plan, copies of the Driller’s Boring Logs, and Laboratory Test Results are included in the Appendix.

Representative soils were classified and laboratory tested for Gradation Analysis, Atterberg Limits, Natural Moisture Content, BTEX and Total Petroleum Hydrocarbons (TPH). The results of the laboratory tests identified the soil according to the Unified Soil Classification System (USCS) and the Plasticity Index (PI). The PI is the Liquid Limit (LL) minus the Plastic Limit (PL) as shown in the laboratory results.

IV. DISCUSSION OF SUBSURFACE CONDITIONS

All borings encountered 8 to 9 feet of oligohaline brackish water from the Chesapeake Bay. The difference in depths can be accounted for by the changing tides.

Borings SP-1 and SP-5 encountered very soft, 0 blows per foot (bpf), organic silt as the top most submerged soil layer. The organic layer had an average thickness of 18 inches. Below the organic silt lay 10 bpf silt and clay. The blows per foot increased with depth before both borings ended at 30 feet below the water level in 15 to 22 bpf material. Boring SP-1 had a final layer, 3.5 feet thick, of organic silt while boring SP-5 remained silt and clay.

Borings SP-2 and SP-3 encountered approximately 18 inches of very soft, 0 bpf, organic silt as the top most submerged soil layer. Below the organic silt lay approximately 15 feet of 2 to 12 bpf sand with clay. The last layer was 4 to 6 feet of organic clayey silt having an average of 13 bpf.

Boring SP-4 encountered four feet of very loose, 4 bpf, sand as the top most submerged soil layer. Below the sand lay 18 feet of 3 to 15 bpf sandy clay. The blows per foot increased with depth and this boring appeared to have only two layers. Organic soil was present at the top of the submerged soils but in a thin layer that was taken for BTEX and TPH laboratory testing and did not show up in the first SPT sample.

BTEX and TPH testing showed contaminates were not detected at or above the reporting limit. Full results of these tests are included in the appendix.

Natural Moisture Content and Atterberg Limit tests were performed on selected samples. The results of these tests are summarized as follows:

N:\42052-000\Engineering\Design\Geotechnical Report 2

Boring No. Sample No. Sample Depth Natural PL LL PI Moisture (%) SP-1 S-2 13.5’ - 15’ -- 19 32 13 S-3 18.5’ - 20’ 52.3 ------S-5 28.5’ – 30’ 50.6 ------SP-2 S-2 13.5’ - 15’ 22.6 ------S-4 23.5’ – 25’ -- 43 88 45 SP-3 S-2 13.5’ - 15’ 23.7 ------S-3 18.5’ – 20’ ------S-5 28.5’ – 30’ 66 54 97 43 SP-4 S-2 13.5’ – 15’ ------S-3 18.5’ – 20’ -- 31 71 40 S-4 23.5’ – 25’ 46.8 ------SP-5 S-2 13.5’ – 15’ 24.1 ------S-3 18.5’ - 20’ ------S-4 23.5’ – 25’ -- 37 74 37

V. SHEET PILING CONSIDERATIONS

Several options are available for replacing the failing sheet piling wall at the end of the boat ramp. The first is flat panel vinyl sheet piling, the second is z-shaped vinyl sheet piling and the last is z-shaped steel sheet piling.

The sheet piling was designed to withstand scour up to 6 feet deep, based on the dive report from the DNR, be subjected to loading from trucks with boats on trailers and be capped with concrete. It will be installed as close as possible to the existing sheet piling and backfilled with sand.

A flat panel vinyl sheeting section was requested in the project design program and the Flat Panel from Crane Materials International was selected for analysis. Using a sheet pile embedment depth of 12 feet and a design moment of 4796 ft-lbs the deflection was 3.45 inches.

A z-shaped vinyl sheeting section was analyzed to minimize the deflection. SG-650 from Crane Materials International was analyzed. Using a sheet pile embedment depth of 12 feet and a design moment of 4796 ft-lbs the deflection was 2.14 inches.

A z-shaped steel sheeting section was analyzed as a standard material choice. PZC 13 was analyzed. Using a sheet pile embedment depth of 12 feet and a design moment of 4796 ft-lbs the deflection was 2.09 inches.

The cost per square foot of vinyl sheet piling is lower than that of steel sheet piling. The deflections generated are reflection of 6 feet of scour; in reality the scour considerations should limit scour to near zero feet thus making deflection a mute point.

The flat panel vinyl sheeting requested by the MD DNR is recommended.

N:\42052-000\Engineering\Design\Geotechnical Report 3

The following soil parameters were used in the above sheet piling analyses:

Buoyant unit weight of soil ' = 70 pcf Angle of Soil Incline = 6.8° Angle of Internal Friction = 25° Active Pressure Coefficient ka = 0.4 Passive Pressure Coefficient kp = 2.5

VI. VOID & SCOUR CONSIDERATIONS

Missing timber sheet piling has caused scour beneath the concrete boat ramp. To fill these voids grout will be pumped underneath the boat ramp behind temporary forms.

Open graded coarse aggregate will be used to fill the void between the existing sheet piling and the new sheet piling.

The client suggested #2 stone to a depth of 1 foot below the mudline. WR&A determined that #2 stone would be too lightweight to counter scour. A nonwoven geotextile to reduce sinking and 18 inches (minimum) of Class 1 rip rap is proposed instead.

N:\42052-000\Engineering\Design\Geotechnical Report 4

APPENDIX A

N:\42052-000\Engineering\Design\Geotechnical Report

GRASSISlANO(lYP.)

TIMBER BULKHEAD

CONCRETE RAMP (TYP.) + D WOOD PIER (TYP.)

ELEC.BOX

TRAVERSE POINT #1 ELEV. = +3.58' (MLW) PAVED PARKING LOT PKNAILSET 8

MEZICK POND

; EE POINT#2 Er·- +6.47' (MLW)

v

v

WOOD PIER (lYP.)

SURVD' DATEo SCALEo 1" = '91' STATE OF MARYLAND DEPARTMENT OF 3/10/09 SANDY POINT STATE PARK SHEET NUMBERo NATURAL RESOURCES ENGINEERING AND V.M. ANNE ARUNDEL COUNTY ORAWI 09 CONSTRUCTION BOAT RAMP SCOUR SURVEY G.G. 1 OFo 1

APPENDIXB

N:\42052-000\Engineering\Design\Geotechnical Report

SOIL BORING LOG

Client Whitman. Requardt & Associates. LLP. Boring # -=SP'--_,_1 _ Project Name Sandy Point State Park--Boat Ramp Job # W.O.# 42052 Location Sandy Point Park---Anne Arundel County 21401

Datum ------Driller Paul Suit Hammer Type Safety,140 LBS. Boring Method ,_H'-'=S"-'A --­ Surf. Elev. ,O.::..O,._,_F_,.t..__ _ Inspector Jessie Cunningham Sampler Type -'='-S'-PT,__ _ Borehole Diameter 6" In. Date Started 09/22/2010 Date Completed 09/22/2010 Rig Type CME-45C Rock Core Size --'-'N/ A"'-----

Jl. I-­

- WATER. I-

- 1- - r- - I­ - I-­ - I­ - I­ - I­ 9.0 I- 10.0 Black, wet, very loose, 24" ORGANIC SPT WOR/24" 1-- sn.r. - - Gray and brown, wet, very soft - - to stiff to very soft, SD. - TY - - CLAY. - SPT 4-5-8 18" - -

- ;-

- -

- - - - SPT 2-2-1 18" 20.0 - Gray and brown, wet, medium - - stiff, SD.TY a.AY.WITH a.AYEY - r- SANl LAYERS. - 1- - SPT 2-2-3 18" - - -

- 26.5 -

- Black, damp, medium dense, - I­ - ORGANIC SD.T. I­ - 5-11-11 18" 30.0 SPT I-­ Bottom of test boring 30.0 feet. - I­ - I­ - I ­ - I­ - 135-- t-­ - - I­ - - I­ - - I­ - I­ - 140- t--- - - 1- - - I­ - - I- - 45- 1-

BORING METHOD SAMPLER TYPE GROUNDWATER DEPTH

HSA - HOLLOW STEM AUGERS SPT - STANDARD PENETRATION AT COMPLETION FT. HA/TR-HAND AUGER & TRIPOD TEST SPLIT SPOON AFTER HRS. FT. DC - DRIVING CASING ST - SHELBY TUBE AFTER 24 HRS. .l:lLA_FT. MD - MUD DRILLING AS - AUGER SAMPLE CAVED AT FT. AR - AIR ROTARYI AIR HAMMER RC - ROCK CORE

SPT -Standard Penetration Test: Driving 2 Inch OD Sampler 1.0 foot with 140 pound Hammer Falling 30 inches; Blow Count Recorded at 6 inch Intervals PID - Photoionization Detector (parts per million)

SOIL BORING LOG

Client Whitman. Reguardt & Associates. LLP. Boring # --=SP'-- ,2 ----- Project Name Sandy Point State Park--Boat Ramp Job # W.O.# 42052 Location Sandy Point Park---Anne Arundel County 21401

Datum _ Driller Paul Suit Hammer Type Safety,140 LBS. Boring Method ,_H""S'-'A _ Surf. Elev. ,0""".0"'-'-F t. _ Inspector Jessie Cunningham Sampler Type _S""'P'-'T'----- Borehole Diameter 6" In. Date Started 09/22/2010 Date Completed 09/22/2010 Rig Type CME-45C Rock Core Size _N,_,/'-'-A_,_ _

A. - I-- - WATER. - I) Sample collected for r­ - - TPH & BTEX, soil lab r­ - - from 9.0 to 11.0 feet. r­ - 5- r- ::...._ - 1-­ - - r­ - - r­ - - r- 9.0 -9.0 Black, wet, very loose, - ORGANIC -- SPT WOR/24" 18" - 11.0 -11.0 -- sn.T. 19 - ;;-/. - Greenish gray, wet, very loose, - - medium to coarse, SANJ. /// - WITH A v-·7· . - - LITTLE Q.AY. /// - 2 SPT 2-1-2 18" - v-·7··/ -.!lrJ - ;. - - /// - ;- - /- -7· . - - /.(/ - /- ·7· . - /// 3 SPT 1-1-1 18" - /-/'.7(' /. I - v-·7· . - /.(/ - - v-·7· . - - - ;•/--/ - - 24.0 -24.0 - /// 4 SPT 3-4-6 18" - Black, damp, stiff, a.AYEY sn.T. · v/ // - - v// // - - - / - -

/ - 5 SPT - I 6-7-7 18"

- v/ // - 30.0 -30.0 v/ // c-- 1-­ - Bottom of test boring 30.0 feet. - r­ - - r­ - - r­ - 35- r- - 1- 1-­ - - r­ - - r­ - - r­ - 40- r- - - 1-­ - - r­ - - r­ - - r­ - 45- r- MD - MUD DRILLING BORING METHOD AR - AIR ROTARYI AIR SAMPLER TYPE HAMMER HSA - HOLLOW STEM AUGERS SPT - STANDARD PENETRATION TEST SPLIT SPOON HA/TR-HAND AUGER & TRIPOD ST - SHELBY TUBE AS AUGER SAMPLE RC - ROCK CORE DC - DRIVING CASING

_ HRS. FT. GROUNDWATER DEPTH l AFTER 24 HRS. .JiLL FT. : CAVED AT .JiLL._FT. A l T L L C O M F P T L . E T A I F O T N E R

SPT -Standard Penetration Test: Driving 2 Inch OD Sampler 1.0 foot with 140 pound Hammer Falling 30 inches; Blow Count Recorded at 6 inch Intervals PID - Photoionization Detector (parts per million)

SOIL BORING LOG

Client Whitman. Reguardt & Associates. LLP. Boring # --'S,P_-....:::3:__ _ Project Name Sandy Point State Park--Boat Ramp Job # W.O.# 42052 Location ---"S a n"'-d.Ly_,_P-"o"'-in'-"t-'-P-'=a"-'rk'-'----_-._!A n.!!.nl!=e'-'A r-"ue!..!n""-de I C o u!!..;n'-'-ty:t.....!=22.:14 0""1 _

Datum _ Driller Paul Suit Hammer Type Safety,140 LBS. Boring Method ,_H=S"-A,__ _ Surf. Elev. ,0'"".0"-"-F_,_t. _ Inspector Jessie Cunningham Sampler Type _S""P--'T'----- Borehole Diameter 6" In. Date Started 09/22/2010 Date Completed 09/22/2010 Rig Type CME-45C Rock Core Size -'N'""/'-'-A,__ _

1--- WATER. 1- .Jl. 1- - r­ - f- = 1--­ - - I- - [f9:: - - - - 8.5 -8.5 %.AI.,, - - Black, wet, very loose, CR;ANIC - 10.0 -10.0 - - !Qj SPT WOR/18" 0" Sll.T. - - Orangish tan, wet, loose, medium, -:-:-: - - - ·.·.·. - - SANl - ... - - - 4-4-4 18" - :::::: !d 2 SPT - - - ... - - 17.0 -17.0 ·.·.·. Greenish gray and orange, loose - - c­ to medium dense, a.AYEY/SILTY c- - SAN). 18" SPT 2-2-2 - 1--- -

------4-5-7 18" - - SPT - 26.0 - - Black, damp, stiff, - - ClAYEY/SILT. - - 5-5-7 r- 30.0 18" SPT r-­ Bottom of test boring 30.0 feet. - - r­ - - r­ - - r­ - r- - 135- 1--- - - 1- - - r­ - - r­ - r- - 1--­ - r- - 1- - r- - 1-

BORING METHOD SAMPLER TYPE GROUNDWATER DEPTH

HSA - HOLLOW STEM AUGERS SPT - STANDARD PENETRATION AT COMPLETION .l!i.LFT. HA/TR-HAND AUGER & TRIPOD TEST SPLIT SPOON AFTER HRS. FT. DC - DRIVING CASING ST - SHELBY TUBE AFTER 24 HRS. _l:!LA_FT. MD - MUD DRILLING AS - AUGER SAMPLE CAVED AT FT. AR - AIR ROTARYI AIR HAMMER RC - ROCK CORE

SPT-Standard Penetration Test: Driving 2 Inch 00 Sampler 1.0 foot with 140 pound Hammer Falling 30 inches; Blow Count Recorded at 6 inch Intervals PID - Photolonization Detector (parts per million)

SOIL BORING LOG

Client Whitman. Reguardt & Associates. LLP. Boring # _S=P,_-_4_,__ _ Project Name Sandy Point State Park--Boat Ramp Job # W.O.# 42052 Location Sandy Point Park---Anne Arundel County 21401

Datum _ Driller Paul Suit Hammer Type Safety,140 LBS. Boring Method ,_H=S"-'A _ Surf. Elev. ,0"".0"'-'--F""'t. _ Inspector Jessie Cunningham Sampler Type _,S""'P_,T _ Borehole Diameter 6" In. Date Started 09/22/2010 Date Completed 09/22/2010 Rig Type CME-45C Rock Core Size _,N'""/:...cA_,__ _

JL. - - IIIATER. I) Sample collected for - - TPH & BTEX, soil lab - - from 8.0 to 9.5 feet. r­

- r­ - r--

- 1- - 1- 8.0 r­ Orangish tan, wet, loose, medium - 2-2-2 18" I­ to coarse, SANl - f--

- 1- 12.0 r­ - Gray and tan, wet to damp, very r- stiff to stiff, - (1AY, WITH satE 1- SAN). SPT 2-2-1 18" - r------SPT 1-2-3 18" ------SPT 5-7-8 18" ------

- 18" - 30.0 SPT 5-5-6 - Bottom of test boring 30.0 feet. - - - - - "­ - - r­ - r­ - -35- r-- - - 1- - - r­ - - r- - 40- 1- - - r-­ - - r- - - 1- - - r­ - 45- f-

BORING METHOD SAMPLER TYPE GROUNDWATER DEPTH

HSA - HOLLOW STEM AUGERS SPT - ST ANDARO PENETRATION AT COMPLETION ----"!ft_ FT. HA/TR-HAND AUGER & TRIPOD TEST SPLIT SPOON AFTER HRS. FT. DC - DRIVING CASING ST - SHELBY TUBE AFTER 24 HRS. ....!::!.LL_ FT. MD - MUD DRILLING AS - AUGER SAMPLE CAVED AT FT. AR - AIR ROTARYIAIR HAMMER RC - ROCK CORE

SPT -Standard Penetration Test: Driving 2 Inch OD Sampler 1.0 foot with 140 pound Hammer Falling 30 inches; Blow Count Recorded at 6 inch Intervals PID - Photoionization Detector (parts per million)

SOIL BORING LOG

Client Whitman. Requardt & Associates. LLP. Boring # S,_P----'5 ----- Project Name Sandy Point State Park--Boat Ramp Job # W.O.# 42052 Location S'='-a"'"n_,_,d"-'y'-P'-'o""in'"'"'t'-'P'-'a=r.!.!.k-_-_--'A'-"n_,_,_n=e'-'A'-"r-"'u'"'"nd=e=I--=C'-"o=un'"'"'t'-'y_,2=-!1--'-4""-01,__ _

Datum ------Driller Paul Suit Hammer Type Safety.140 LBS. Boring Method ----'-H!:=S'-"'A _ Surf. Elev. ,0,_,.0"'-'--F-"-t. _ Inspector Jessie Cunningham Sampler Type _,S=P-'T _ Borehole Diameter 6" In. Date Started 09/22/2010 Date Completed 09/22/2010 Rig Type CME-45C Rock Core Size -'N /u:Ac__ _

MATER. - ll Sample collected for f- - TPH & BTEX, soil lab f- - from 8.0 to 9.5 feet. - - - - :,.

- f-

- 1- 8.0 I­ Black, wet, very loose, C - SPT WOH/18" 18" I- 10.0 sn.r. 1--

- Light gray to dark gray, wet to 1- - moist, medium stiff to very stiff, I­ - sn.T.WITH sa£ SANl ANJ I­ SOEQ.AY. - f- SPT 1-4-5 18" - 1-­

- I­

- I­

- I­

- I- SPT 6-7-8 18" - 1-­ - f­ - I­ - I­

- .f- SPT 6-11-12 16" - 1-­

- I­

I­ - - f­

- 14" f- 30.0 SPT 5-7-8 1--­ Bottom of test boring 30.0 feet. - - f­ - - f­ - - f­ - 35- f- - - 1-­ - - I­ - - I- - - - - 40- - - 1------45- -

BORING METHOD SAMPLER TYPE GROUNDWATER DEPTH

HSA - HOLLOW STEM AUGERS SPT - STANDARD PENETRATION AT COMPLETION FT. HAITR-HAND AUGER & TRIPOD TEST SPLIT SPOON AFTER HRS. FT. DC - DRIVING CASING ST - SHELBY TUBE AFTER 24 HRS. _HLLFT. MD - MUD DRILLING AS - AUGER SAMPLE CAVED AT FT. AR - AIR ROTARYI AIR HAMMER RC - ROCK CORE

SPT -Standard Penetration Test: Driving 2 Inch OD Sampler 1.0 foot with 140 pound Hammer Falling 30 inches; Blow Count Recorded at 6 inch Intervals PID - Photolonization Detector (parts per million)

APPENDIXC

N:\42052-000\Engineering\Design\Geotechnical Report

O'BERRY ENGINEERING, INC.

GEOTECHNICAL ENGINEERS 3161 Solomons Island Road, Suite 2 • Edgewater, MD 2103 7 Phone: (41 0) 956-7820 • Fax: (41 0) 956-1 53 7

LETTER OF TRANSMITTAL

TO: Geomatrix Drilling, Inc. DATE: October 19, 2010 3345 Hollins Ferry Road Baltimore, MD 21227

ATTN: Paul Suit

RE: Sandy Point Park - Project #42052 OBEI JOB NO: 10132 Materials Testing

We are sending you _ attached under separate cover the following:

Shop drawings Specifications -- Prints Copy of letter -- Plans ------Field Reports --Samples x Other- Laboratory Test Results

These are transmitted as checked below:

For approval x Approved as submitted Resubmit -- -- Foryouruse Approved as noted Submit -- -- As requested Return -- Returned for corrections --

REMARKS:

Copies: Mail (2); email (1)

Materials Testing Summary Sandy Point Park Boat Ramp (Project No. 42052)

Natural Boring Sample Sample Moisture Atterberg Limits No. No. Depth (%) PL LL PI Gradation

SP-1 S-2 13.5'- 15' 19 32 13 .

S-3 18.5'- 20' 52.3 S-5 28.5'- 30' 50.6

SP-2 S-2 13.5' -15' 22.6

S-4 23.5'- 25' 43 88 45

SP-3 S-2 13.5' -15' 23.7 S-3 18.5'- 20' * S-5 28.5'- 30' 66 54 97 43

SP-4 S-2 13.5'-15' * S-3 18.5'- 20' 31 71 40- S-4 23.5'- 25' 46.8

SP-5 S-2 13.5' -15' 24.1 S-3 18.5'- 20' * S-4 23.5'- 25' 37 74 37

*see attached Particle Size Distribution Report

,:; Particle Size Distribution Report U.S. SIEVE OPENING IN INCHES U.S. STANDARD SIEVE NUMBERS HYDROMETER 6 3 2 1-1/2 1 3/4 112 3/8 Jl. 0 20 30 40 60 100 140 200 I 100 I I' Ill I 0 I' I ! I' I I 1 II I I 1- ' I' 1'- I I 90 !'1_1 I i 10 r---1'\\ " I I f ! rei II 80 I \,\ I 20 I I I + ' IJ ! I ! I I II I "\I\ I ------u 1- 70 I 30 g:j C) () il.i mz 5 60 I\. I 40 -1 >- () Il l 0 0:: )> 50 I 50 m u::: ;:o 1- I' ) l I OJ a] 40 "' ---- 60 -<

0 :;E 0:: m LU I --i I a. 30 c-r--- +---. 70 ) -1 I I I I 20 -- 80 I I I I 10 I 90

0 I I I I I I 100 500 100 10 1 0.1 0.01 I 0.001

GRAIN SIZE IN MILLIMETERS ,---- %COBBLES %GRAVEL %SAND %SILT %CLAY 0 0.0 0.5 56.9 42.6 0 0.0 0.0 45.5 54.5 to 0.0 0.0 16.0 84.0 SOURCE SAMPLE# DEPTH/ELEV. DATE SAMPLED uses MATERIAL DESCRIPTION NM% LL PL 0 SP-3 S-3 18.5'-20' 10/07/10 Olive Gray* 0 SP-4 S-2 13.5'-15' 10/07/10 Brown and Gray Sandy Clay 6 SP-5 S-3 18.5'-20' 10/07/10 Brown and Olive Brown Sandy Clayey Silt o * Sample consisted of layered Clayey Sand, Silty Sand and Client Geomatrix Drilling, Inc. Sandy Clayey Silt soils Project Sandy Point State Park Boat Ramp (Project #42052) 0 O'Berry Engineering, Inc. 6 Top half jar- Sandy Clayey Silt (tested) Bottom half jar- Sand w/Silt to Silty Sand within Sandy Silt Project No. 10132 I Figure lavers (not tested)

Microbac Laboratories, Inc. Phone:410-633-1800 Baltimore Division Fax:410-633-6553 www.microbac.corn 21 01 Van Deman Street • Baltimore, MD 21224

COVER LETTER

Paul Suit September 30, 2010

Geomatrix Drilling, Inc. Report No.: 101130 I

3345 Hollins Ferry Rd

Halethorpe, MD 21227-2013

RE: Soil

The report of analyses contains test results for samples received at Microbac Laboratories, Inc., Baltimore Division on 09/22/2010 14:00.

The enclosed results were obtained from and applicable to the sample(s) as received at the laboratory. All sample results are reported on an "as received" basis unless otherwise noted.

All data included in this report has been reviewed and meet the applicable project and certification specific requirements, unless otherwise noted.

This report has been paginated in its entirety and shall not be reproduced except in full, without the written approval of Microbac Laboratories, Inc.

We appreciate the opportunity to service your analytical needs. If you have any questions, please feel free to contact us.

This Data Package contains the following: - This Cover Page - Sample Summary -Test Results - Notes and Definitions - Cooler Receipt Log - Chain of Custody

9/30/2010

Final report reviewed by: Mark B. Horan!Laboratory Director Report issue date

All samples received in proper condition and results conform to ISO 17025 stanJIJirds unless otherwise noted.

If we hal'e not mel or exceeded your expectations. please contact the Director or Trevor Boyce, President at [email protected] or Robert Morgan, Chief Operation Officer, at [email protected].

[ . Page 1 of8

Microbac Laboratories, Inc. Phone: 410-633-1800

Baltimore Division Fax: 410-633-6553 www.microbac.com 2101 Van Deman Street • Baltimore, MD 21224

CERTIFICATE OF ANALYSIS

Geomatrix Drilling, Inc. Project Soil Report: 10Il301 3345 Hollins Feny Rd Project Number: Sandy Point Park Reported: 09/30/2010 11:34 Halethorpe, MD 21227-2013 Project Manager: Paul Suit

SAMPLE SUMMARY

SampleiD Laboratory ID Matrix Type Date Sampled Date Received

SP-2S-19'to 11' IOIJ301-QI Solid Grab 09/22/2010 09:12 09/22/2010 14:00

SP-4 S-1 8' to 9.5' lOIJ301-02 Solid Grab 09/22/2010 09:12 09/22/2010 14:00

SP-5 S-1 8' to 9.5' 10I1301-03 Solid Grab 09/22/2010 12:50 09/22/2010 14:00

Microbac Laboratories, Inc., Baltimore Division The results in this repon apply to the samples anaZvzed in accordance with the chain of custody document. 17•is analytical report must be reproduced in its entirety.

Mark B. Horan, Laboratory Director ( Page2 of8

® Microbac Laboratories, Inc. Phone:410-633-1800 Baltimore Division Fax:410-633-6553 WW\V.microbac.com 2101 Van Deman Street • Baltimore, MD 21224

CERTIFICATE OF ANALYSIS

Geomatrix Drilling, Inc. Project: Soil Report: I Oil 301 3345 Hollins Ferry Rd Project Number: Sandy Point Park Reported: 09/30/2010 11:34 Halethorpe, MD 21227-2013 Project Manager: Paul Suit

SP-2 S-19' to 11' 1011301-01 (Solid) Sampled:09/22/2010 09:12; Type: Grab

Reporting Analyte Result Limit Units Prepared Analyzed Analyst Method Notes

Microbac Laboratories, Inc., Baltimore Dnision

Wet Chemist

%Solids 44.36 0.05 %byWeight 092410 1230 092710 0832 LCR SM (20) 2540G

BTEX

EPA8260B Benzene ND 540 ug(kg dry 092810 0554 092910 0247 TDH U,D Toluene ND 540 uglkg dry 092810 0554 092910 0247 TDH EPA8260B U,D Ethylbenzene ND 540 ug(kgdry 092810 0554 092910 0247 TDH EPA8260B U,D m,p-Xylenes ND 1100 ug(kgdry 092810 0554 092910 0247 TDH EPA8260B U,D o-Xylene ND 540 ug(kgdry 092810 0554 092910 0247 TDH EPA8260B U,D Total Xylenes ND 1600 ug(kgdry 092810 0554 092910 0247 EPA8260B ------"·· ------·----- TDH U,D Surrogate: Dibrom fluoromethane 101% 80-120 0928100554 0929100247 EPA 8260B Surrogate: 1,2-Dichloroethane--d-1 90.7% 80-120 092810 055-1 092910 02-17 EPA 8260B Surrogate: Toluene--dB 92.8% 75-!20 0928100554 092910 02-17 EPA 8260B Surrogate: 4-Bromoj/uoroben;;ene 89.6% 60-149 0928100554 092910 02-17 EPA 8260R Total Petroleum Hydrocarbons (TPH (SGT-HEM))

Total Petroleum Hydrocarbons ND 200 mglkg 092710 0900 092710 0910 BAB SW8469071B

Microbac Laboratories, Inc., Baltimore Division The results in this report apply to the samples ana vzed in accordance with the chain of custody document. This analytical report must be reproduced in its entirety.

Mark B. Horan, Laboratory Director [ Page 3of8

Microbac Laboratories, Inc. Phone:410-633-1800 Baltimore Division Fax:410-633-6553 www.microbac.com 2101 Van Deman Street • Baltimore, MD 21224

CERTIFICATE OF ANALYSIS

Geomatrix Drilling, Inc. Project: Soil Report: I OII301 3345 Hollins Ferry Rd Project Number: Sandy Point Park Reported: 09/30/2010 l 1:34 Halethorpe, MD 21227-2013 Project Manager: Paul Suit

SP-4 S-1 8' to 9.5' 1011301-02 (Solid) Sampled:09/22/2010 09:12; Type: Grab

Reporting Analyte Result Limit Units Prepared Analyzed Analyst Method Notes

Microbac Laboratories, Inc., Baltimore Di"ision

Wet Chemist

%Solids 82.94 0.05 %by Weight 092410 1230 092710 0832 LCR SM(20)Z540G

BTEX

Benzene ND 290 ug/kgdry 092810 0554 092910 0323 TDH EPA8260B U,D Toluene ND 290 ug/kg dty 092810 0554 092910 0323 TDH EPA8260B U,D Ethylbenzene ND 290 ug/kg dry 092810 0554 092910 0323 TDH EPA8260B U,D m,p-Xylenes ND 590 ug/kgdry 092810 0554 092910 0323 TDH EPA8260B U,D o-Xylene ND 290 ug/kgdry 092810 0554 092910 0323 TDH EPA8260B U,D Total Xylenes ND 880 ug/kgdry 092810 0554 092910 0323 EPA8260B U,D -··------·-·- TDH Surrogate: Dibromojluoromethane 99.4% 80-120 092810 0554 092910 0323 EPA 8260B

Surrogate: 1,2-Dichloroethane-d.f 91.0% 80-120 092810 055./ 0929100323 EPA 8260B

Surrogate: Toluene-dB 95.0% 75-/20 092810 055./ 092910 0323 EPA8260B

Surrogate: 4-Bromojluoroben=ene 87.8% 60-149 0928100554 0929100323 EPA 8260B

Total Petroleum Hydrocarbons

Total Petroleum Hydrocarbons ND 200 mglkg 092710 0900 092710 0912 BAB SW8469071B

Microbac Laboratories, Inc., Baltimore Division The results in this report apply to the samples onaZv=ed in accordance with the chain of cu.

Mark B. Horan, Laboratory Director [ Page 4of8

Microbac Laboratories, Inc. Phone:410-633-1800 Baltimore Division Fax:410-633-6553 www.rnicrobac.com 2101 Van Deman Street • Baltimore, MD 21 224

CERTIFICATE OF ANALYSIS

Geomatrix Drilling, Inc. Project: Soil Report: 1011301 3345 Hollins Feny Rd Project Nmnber: Sandy Point Park Reported: 09/30/2010 11:34 Halethorpe, MD 21227-2013 Project Manager: Paul Suit

SP-5 S-1 8' to 9.5' 1011301-03 (Solid) Sampled:09/22/2010 12:50; Type: Grab

Reporting Analyte Result Limit Units Prepared Analyzed Analyst Method Notes

Microbac Laboratories, Inc., Baltimore Division

Wet Chemist

SM (20) 2540G %Solids 82.41 0.05 %by Weight 092410 1230 092710 0832 LCR

BTEX

ugfkgdry 092810 0554 092910 0358 EPA8260B Benzene ND 300 TDH U,D Toluene ND 300 ugfkg dry 092810 0554 092910 0358 TDH EPA8260B U,D Ethylbenzene ND 300 ugfkg dry 092810 0554 092910 0358 TDH EPA8260B U,D m,p-Xylenes 610 ug(kgdry 092810 0554 092910 0358 EPA8260B ND TDH U,D a-Xylene ND 300 ug/kgdry 092810 0554 092910 0358 TDH EPA8260B U,D Total Xylenes ND 910 ugfkgdry 092810 0554 092910 0358 TDH EPA8260B U,D ···---·-··---··········------. ------·---· ------·-·-- SwTogate: Dibromojluoromethane 99.4% 80-120 0928100554 0929100358 EPA 8260B Surrogate: 1,2-Dichloroethane-d-1 89.2% 80-120 0928!0055-1 0929100358 EPA 8260B Surrogate: Toluene-dB 94.8% 75-120 092810055-1 092910 0358 EPA8260B Surrogate: -1-Bromojluorobenzene 89.2% 60-149 092810055-1 0929100358 EPA 8260B Total Petroleum Hydrocarbons (TPH (SGT-HEM))

Total Petrolewn Hydrocarbons 092710 0900 092710 0914 BAB SW846 9071B ND 200 mg/kg

Microbac Laboratories, Inc., Baltimore Division The results in this report apply to the sampies anaZw::ed in accordance with the chain of cus!Ody document. This analytical report must be reproduced in its entirety.

Mark B. Horan, Laboratory Director [ Page 5of8

Microbac Laboratories, Inc. Phone:410-633-1800

Baltimore Division Fax:410-633-6553 www.microbac.com 210 I Van Deman Street • Baltimore, MD 21224

CERTIFICATE OF ANALYSIS

Geomatrix Drilling, Inc. Project Soil Report: 10Il301 3345 Hollins Ferry Rd Project Number: Sandy Point Park Reported: 09/30/20l 0 II:34 Halethorpe, :MD 21227-2013 Project Manager: Paul Suit

Notes and Definitions

U Sample concentration is less than the :MDL.

D Sample Diluted

DET Analyte DETECTED

ND Analyte NOT DETECTED at or above the reporting limit

NR Not Reported

dry Sample results reported on a dry weight basis

RPD Relative Percent Difference

Certifications

Below is a list of certifications maintained by Microbac Laboratories, Inc. All data included in this report has been reviewed for and meets all project specific and quality control requirements of the applicable accreditation, unless otherwise noted. A complete list of individual analytes pursuant to each certification below is available upon request. - A2LA(Microbiology): 410.02 - A2LA (Environmental): 410.01 - A2LA (ELLAP): 410.01 - CPSC: 1115 -Maryland: 109 - Pennsylvania (NELAC): 68-00339 -USDA: S-53726 -Virginia: 00152

( . Page 6 of8

Microbac Laboratories, Inc.

Phone:410-633-1800 Baltimore Division Fax:410-633-6553 2101 Van Deman Street • Baltimore, MD 21224 "WWw.microbac.com

Cooler Receipt Log

Cooler ID: Default Cooler Cooler Temp: 4JO •c

Custody Seals Intact: Yes CDC/Containers Agree: Yes Containers Intact: Yes Correct Preservation: Yes Received On Ice: Yes Correct Nmnber of Containers Received: Yes Radiation Scan Acceptable: Yes Sufficient Sample Volume for Testing: Yes COC Present: Yes Samples Received in Proper Condition: Yes

Comments:

[ Page 7 of8

Baltimore Division Sample Submittal Worl< Ordtar Number: Baltimorn. MO 2'1224 Chain of Custod.v Record ----·------1 Tal: 4H.I-6:J3·1800 Fax: 410-633-6553 Page ...... _,_of ...... www.microbac.com 6£..1:'!_ , tSA_NP j_jl}J.JlJLt'NifL_ :.T """ """''!&.t-- --QC ar!£! Er]J! .ili!9.!:!!r.!E.l _ Addres . Jj[ . l!- . t_l !. ilAlt:?):.Jf!tf/vvz ---IJ:1./!_:.:._...... '(Stanclont [I LrlVI?.II (NAG) [I EDD fl::.lfiJ8JJ.zff!_'!_...... _ City, Sta!!,':l_ .ftt1J..illJ.l! .il/L2;_£3.i2.2._2.. # [] H\J' fl' {nr;\lly !,.Jh) ll Level II •• Format· Con _itt!.Q. !=:d.'-!_ l z. -·------..... MDE l1rH1 11](J W:::! '!tlollJL -:;:z--·-""·;7";7"" --·-·..·------·---..--- l I'-:: .::------···-:-··------

:). ,...... (tH f'fif.-•\J by/ samplad by (PRINT) Sampler S1gnnturc C;Z.. d

SendReportvia [IP-rnHII{adOresst ... . -- - ·- --· i]Mtid [jfd<.,ptlf)•l•c (jt-. x.(f

0

. - .....;...,.,.

·u "0 Client Sample ID -1:

-- .,...... ,.w...... __ _ - · _ LL _J...... +----+·--·..·+··--+ ------·-·------..:. -----..-·-..-·- ·-:-- --t-...-. -.. =

:E -- : ,[J!_----· ------;:;-r.:::-·--··t- ...... om···--·-----···-·· (..) :-::: (ll -=-=:-: - ...... :... _e. j.:

---t...... l"2·;--:------:---1·-----·------·-· :--:-· ---..--...---...... J...... _. t--·-r·-.. ·--r-----·j 0 = -= 1- =- = := = = =-=:- -======- -- ' - C)"' <; ; Jd:.. I s··I t''h t. ·sP? /-! • s ·v / z·::.J. J:L' 0 L x· · ===' ------· ....------··------·.,.-.....:.-...-· -- -... --...---...... --- r 1 ·------:. ·--l :-..."""""' .....,._" ---- . , ,_ ...... -...... -.. .l--. - ··-"' ... ·· ;.· .-...-...... :t-t --f.. --·· ...,_.,.,...... ,. ··· ------·*·" ..-.-...-...--.. - -"'k··N.. ·u"'.-...... ,. ...._.,...-·-· - ---- ...... !!!!!!!!!!!!!! -- -..--- --.,·-...... ,.,...... - ...... --.--...... ,._.,_,_.. !!!!!!!!!!!!!! ... t-...... -,.4· ---...... ------..... ><- •·""'·+·-·---· ------,_.. .,, ,.,.& !!!!!!!!!!!!! --...... ,...... ,.,.. ..._.,...... ,---...... ,...... iiiiiiiiiiiiiii

. -· - , ...... od-----...:.=- ro=.=LJ·- 1 -= =..: ------Sample Dispo sition [jl:k>pO"''' m; .-lppropn''lie Possible Hazard ldentifiGatlon [ J Hn1ardous [ l Non+la.<:drdous [ 1 f <.\diodcliv•' ll f elurn [ ll\rchive

- ,.,.,)..•·e-•r" •••cf-·- ·" ..._ .•,..••, ., ,-·-1---•-...... ""''"" --+ !!!!!!!!! ,._,.,..,. .,. .,,._,..,.._,..,.._,,_,,_ , ------...... ,,.....,._,._,...,_., _ Nu.mb.er of Containers: . . R I !Je BV1fi o)- Pr .:lom:/Af!ili -:·-::To ;mme. ' '. R:.l;fJived By (si!;_Jnat lre),: .. ('-··;:' Prlntod Namo/Aflili •ti:f) ooler Number: t "·- -"" }!il: :-· .: ...=::S:::: ::?.::...... -- b.d2Jl.:.. /. .. J.-:.v:_ {: - _d( ::: ';Jt_,i,,;J. J:.Q...L:/Jf:_ · l Y) ':::!.?:.!W.I 1/:.. LL" ---· "J? omp upon rocolpt(•C): '-'l1 ,. elinquish By (:signature) Printed NmnaiAfllli•Uon Oato/Time , ,calved By (slgnaturF { . fAmnauon I 1 J . . . El'";f;;,.,::::; ,::;;·, :;,. YNo R hOdBYfiiij;;;,;""!· ;;;;;;;;-;-;;;;,w:;;;;;------o;;;;m;;;,;1 ------;;;;;;;r;;dfOCL>bBy[,ig;;;;;;;;;,j------r,;;;;;- ---

, 'i <- ... -1l'lf!l'I\Zio1 - -#!W · ;...:;., M? l.._._, _,_.., ,_.""'_..,.,tl>-.--1»0- - -"""""""" '""------J

1, :; Pt)UO 2 n (;on ,,.,Surcharge May J pply to ndd'l QG Pac!q;l 1f)!J "" \;\:'1--llH-: 1.;\El Yl·: 1 :.·>'!V 'lf::F'OFII FiNh !l. H HLC[iPl

APPENDIX D

Sub-aquatic Survey of Sandy Point State Park Boat Ramps

Repairs to the Boat Ramps Sandy Point State Park Anne Arundel County, MD P-021-102-010

Pristine Marine, LLC

9200 Tayloes Neck Road, Nanjemoy, MD 20662 Phone 301-246-4362 Mobile 410-303-0747 or 202-288-4537 fax 301-246-9532

.....,==--·====· -""'"'--"'==-======·· MEMORANDUM

TO; MR. ANDY HANAS MARYLAND DEPARTMENT OF NATURAL RESOURCES ENGINEERING AND CONSTRUCTION FROM: . RANDYWITTE.....::-f--

SUBJECT: RESULTS OF SUBAQUATIC SURVEY OF SANDY POINT STATE PARK BOAT RAMPS

DATE: APRIL 10, 2007

CC: FILE

·- ----..---· ·--·----··..-----'--:·

Pursuant to our agteetnenon April 5, 2007, I conducted a sub-aquatic survey of the boat ramp area at Sandy Point State Park. This survey was conducted in response to a teport from the Anne Arundel County Fire Department Dive Tenm (AADT) indicating that there were large pieces of concrete and large .rocks on or around several of the boa1 ramps.

Dw:.ing my survey, T only located two possible hazards to navigation. lhese hazards were crab pots, which l removed from the water. 1 located several piles of broken concrete, in the areas indicated by the AADT, but none of these piles extended mote than n few inches above the surrounding bottom. As such, I do not believe them to be a hazard to tuvigation. In the locations where MDT indicated there wete pieces of com.:tet:e sticking out of the sllttOunding bottom, I located the concrete ••kicker" at the end of boat .tamp #21. At the location where n large rmk was reported to be, Ifound only the end of thtboat ramp (#20). However, the pond bottom nt the end of the ramp app!.".ars to have washed away, and the end of the ramp extends two to three feet above the bottom. Because of the scouring, and the murky conditions, the ends of the tamps could have been mistaken fur la.tge .rocks or pieces of concrete. I also observed some undercutting of the ends of the several boat ramps, and decided to survey all cif the ramp ends to detetmi11e the conditions. Wood "V" groove sheeting, dtiven .into the pond bottom, originally protected the ends of the mmps. ln many areas, this sheeting has been broken off at pushed away from the end oftht! ramp. In areas where this sheeting is missing, the pond bottom has washed from under the concrete i:amp as far back as 6'. The concrete ramps appear to be about 8' thick, with a kicker about (/' high. Below is a chart with a description of whnl I observed at the end of each .ramp.

. •, RAM1.J# DESCRIPTION OF CONDITION

1 The end nf the ramp is covered in silt, up to the kicker. ..,-

2 Oniy a few of the V groove boards are missing. No undercutting of the: tamp observed. ... -- 3&4 Only a few of the V gtoove boards are missing. No undercuttine; of the tatnp observed. ' '

-·-··..- ..... _,, ..

5&6 No tnissing boards or undercutting observed. - -·· 7&8 Less than about 5% of the V groove boards arc missing, undercutting about 3' deep observed, the w-ashed out area under the ramp is.about 8" high, d1ere is a 2'- 3' drop from the top of the kickt".t to the pond bottom

9& 10 About 10% of the V groove boards are missing, undercutting abou't 4' deep observed, the washed ut area umler the ramp is about 8" high, there is a 2' drop from the tc.1p of the kicker to the pond bottom

11 & 12 Less thati 1\boul 5% of the V groove boards are .missit1g,· undercutting about 1' - 2' deep observed, the washed out ru:ea under the ramp is about 8" high, there is1'...:. 2' drop from the ·top of the kicker to the pond bottom

13 & 14 About l0°/i1 of tht'. V groove boards are missing, undercutting about 6' deep obseJ.ved, the washed . "ont atea Ullder the ramp lS about 8" high, there iN a 1' - 2' dtop from the top of the kicker to the pond bottom

15 & 16 About 10% or the V groove boards are missing, undercutting about 2' deep observed, the washed oul area under the ramp is about 8"·high, there is a 2' drop from the top of-the kicker to the pond bottom (NOTE: In one area ot1ly, the undercutting was about 5' deep.

17 & 18 About 30% or the V groove boards are missing, undercutting about 4' deep obsaved, the washed out area under the ramp is about 8" high, there is a 2' drop from the top of the kicker to the ·pond bottom

19 About 7' - 8' of the V groove boards ate nlisHi.ng, undercutting tbout 4'· deep observed, the washed out area under the ramp is about 8" high, there is a 2' drop from the top of the lcicker to the pond bottom

20 About 8' - 9' of the V groove boards arc mis:;ing, undc.rcutting about 4' deep observed, the washed out area under the ramp is about 8" high, there is a 3' dtop from the top of d1e kicker to the pond bottom

21 Numerous V gt:oove boards are missing, undercutting about 4' deep observed, ·the washed out area under the t11mp is about 8" high, thete is a 2' drop .&om the top of the kicket to the pot1d bottom

22 No missing V groove boards or undercutting observed, thete is a 1'- 2' drop from the top of the kicker to the pond bottom

If you have any questions or would like additional information, please let me !mow. I m11y be reached at 410-303-0747.