: Power Transmission Project E1090 ENVIRONMENTAL MANAGEMENT PLAN v. 2

I Musfiq Substation Public Disclosure Authorized Disclosure Authorized Public Public Replacement of Transformers

A. PROJECT DESCRIPTION – MUSFIQ SUBSTATION

The Azerbaijan Government has applied for funding from the International Bank for Reconstruction and Development (the World Bank) for a project to develop transmission system control and to rehabilitate power transmission facilities. Some of the funds are planned used for investments at this substation.

The Musfiq facility is located to the west of City on the periphery of the Greater Baku urban area. The substation is on quite steeply sloping ground directly above Lake Ceyranbatan. There is no obvious sign of environmental damage to lands surrounding the substation. Site access is good and will pose no problems for equipment installation and evacuation. Public Disclosure Authorized Disclosure Authorized Public Public Musfiq 220/110 kV substation is one of the five main substations in the Apsheron load centre area, west of Baku city. The station was placed in service in 1985/1986. It has connections to three 220 kV transmission lines, eight 110 kV lines and two 200 MVA autotransformers with a total combined rating of 400 MVA.

It is expected that load growth will maintain a high rate, considering the current development within the urban area serviced by the station. Moreover, the current loading conditions of the Mushfiq substation do not tolerate any maneuverability measures for the transformers. If for any reason one of the two transformers fails, Azerenerji will not be able to transfer the entire load on the second transformer. A load amounting to 120 MW will have to be shed.

Necessary rehabilitation / upgrading works subject of this EMP: Substitution of the existing transformers by two transformers rated 250 MVA each.

(Additional project work at the substation, but outside the scope of this EMP: Replacing the instrumentation and controls; and adaptation of the Public Disclosure Authorized Disclosure Authorized Public Public substation equipment for allowing installation of Remote Terminal Units for the SCADA/EMS system (transmission system control).)

The planned investment is expected to cost less than US$4 million. Public Disclosure Authorized Disclosure Authorized Public Public B. SCHEDULE – MUSFIQ SUBSTATION

Starting date Ending date

MITIGATION ACTIVITIES Construction – preliminary estimate, March 1, 2006 October 1, 2006 depending on timing of World Bank loan Operation – preliminary estimate October 1, 2006

MONITORING ACTIVITIES Construction March 1, 2006 October 1, 2006 Operation October 1, 2006

Note: The Starting and Ending Dates shown hereinafter are conditional ones. Specific dates will be determined during evaluation of bidding documents.

Sections C through G of this Environmental Management Plan (EMP) are identical for the transformer/switchgear/breakers/batteries rehabilitation subprojects of the Azerbaijan Power Transmission Project.

2 II Substation

Replacement of Transformers

A. PROJECT DESCRIPTION – IMISHLI SUBSTATION

The Azerbaijan Government has applied for funding from the International Bank for Reconstruction and Development (the World Bank) for a project to develop transmission system control and to rehabilitate power transmission facilities. Some of the funds are planned used for investments at this substation.

The Imishli substation is located some 1-2 kilometres from the urban area in relatively close proximity to a rail corridor. The access road to the site is surfaced and in fair condition but any heavy traffic will have to pass through much of the urban area. The site and surrounding areas are very flat but with no obvious high water table or contamination concerns. Agricultural land use adjacent to the site may have been intensive in the past but levels of activity are now low.

Imishli 330/230/110 kV substation is a principal switching station in the southern area of Azerbaijan, on the borders with Iran. It is the main connection point to the Iranian grid. The station was initially placed in service in 1984 (1 x 125 MVA transformer) and has been subsequently upgraded in 1994 and 2000 (1 x 125 MVA and 1 x 250 MVA respectively). The connection to the Iranian grid is at the 230 kV level. The substation has connections to two 330 kV transmission lines, one 230 kV line, six 110 kV lines, two 125 MVA autotransformers and one 250 MVA autotransformer with a total combined transformers rating of 500 MVA.

Currently, the loading of the 125 MVA transformers has reached a very critical limit (105 % at peak demand times). Imishli substation provides supply to a central railway power supply station, and growing industrial, agricultural and residential sectors in the area.

Necessary rehabilitation / upgrading works subject of this EMP: Substitution of the two existing 125 MVA transformers by two transformers rated 200 MVA each.

(Additional project work at the substation, but outside the scope of this EMP: Replacing the instrumentation and controls; and adaptation of the substation equipment for allowing installation of Remote Terminal Units for the SCADA/EMS system (transmission system control).)

The planned investment is expected to cost less than US$4 million.

3 B. SCHEDULE – IMISHLI SUBSTATION

Starting date Ending date

MITIGATION ACTIVITIES Construction – preliminary estimate, March 1, 2006 October 1, 2006 depending on timing of World Bank loan Operation – preliminary estimate October 1, 2006

MONITORING ACTIVITIES Construction March 1, 2006 October 1, 2006 Operation October 1, 2006

Sections C through G of this Environmental Management Plan (EMP) are identical for the transformer/switchgear/breakers/batteries rehabilitation subprojects of the Azerbaijan Power Transmission Project.

4 III Gandja Substation

Replacement of Transformers

A. PROJECT DESCRIPTION – GANDJA SUBSTATION

The Azerbaijan Government has applied for funding from the International Bank for Reconstruction and Development (the World Bank) for a project to develop transmission system control and to rehabilitate power transmission facilities. Some of the funds are planned used for investments at this substation.

The Gandja substation is located 10 km to the south of Gandja city within a rural landscape. Access to the site is good and there are no obvious problems with ground condition.

Gandja 330/110 kV substation is a principal switching station in the eastern area of Azerbaijan. The station was initially placed in service in 1969 (1 x 125 MVA transformer) and has been subsequently upgraded in 1992 (1 x 200 MVA). The substation has connections to three 330 kV transmission lines, fifteen 110 kV lines, one 125 MVA autotransformers and one 200 MVA autotransformer with a total combined transformers rating of 325 MVA.

Currently, the loading of the 125 MVA transformers has reached a very critical limit (overloaded at peak demand). Considering that Gandja is the second biggest city, and the heavy industrial activities in this area, it is expected that load growth will continue. Moreover, this transformer has exceeded its operational lifetime.

Necessary rehabilitation / upgrading works subject of this EMP: Substitution of the existing 125 MVA transformers by a new transformers rated 200 MVA.

(Additional project work at the substation, but outside the scope of this EMP: Replacing the instrumentation and controls; and adaptation of the substation equipment for allowing installation of Remote Terminal Units for the SCADA/EMS system (transmission system control).)

The planned investment is expected to cost less than US$2 million.

5 B. SCHEDULE – GANDJA SUBSTATION

Starting date Ending date

MITIGATION ACTIVITIES Construction – preliminary estimate, March 1, 2006 October 1, 2006 depending on timing of World Bank loan Operation – preliminary estimate October 1, 2006

MONITORING ACTIVITIES Construction March 1, 2006 October 1, 2006 Operation October 1, 2006

Sections C through G of this Environmental Management Plan (EMP) are identical for the transformer/switchgear/breakers/batteries rehabilitation subprojects of the Azerbaijan Power Transmission Project.

6 IV Yashma Substation

Replacement of Circuit Breakers

A. PROJECT DESCRIPTION – YASHMA SUBSTATION

The Azerbaijan Government has applied for funding from the International Bank for Reconstruction and Development (the World Bank) for a project to develop transmission system control and to rehabilitate power transmission facilities. Some of the funds are planned used for investments at this substation.

The Yashma substation is located just north of the Apsheron Peninsula some 20 km north of Sumqait City. It is an isolated complex set in an agricultural landscape in proximity to the main rail line between Baku and Russia and an associated, large rail yard. A small village is located approximately 1km from the site. The area is low lying within the coastal plain. The water table is obviously high, with all major facilities, road, and rail elevated on bunds or embankments. Adjacent lands are actively utilized for agriculture and are set well below built development levels.

Yashma 330/220/110 kV substation is a principal switching station north of the Apsheron peninsula. It is one of the two main stations on the connection link to the Russian grid. The station was initially placed in service in 1974 (1 x 200 MVA transformer) and has been subsequently upgraded in 1979 and 1983 (1 x 240 MVA and 1 x 200 MVA respectively). The substation has connections to two 330 kV transmission lines, one 220 kV line, nine 110 kV lines, two 200 MVA autotransformers and one 240 MVA autotransformer with a total combined transformers rating of 640 MVA.

The circuit breakers type Y-220 are physically worn out and have outlived their lifetime.

Necessary rehabilitation / upgrading works subject of this EMP: Replacing the three existing oil breakers type Y-220 with new GI motorized circuit breakers.

(Additional project work at the substation, but outside the scope of this EMP: Adaptation of the substation equipment for allowing installation of Remote Terminal Units for the SCADA/EMS system (transmission system control).)

The planned investment is expected to cost less than US$300,000.

7 B. SCHEDULE – YASHMA SUBSTATION

Starting date Ending date

MITIGATION ACTIVITIES Construction – preliminary estimate, March 1, 2006 October 1, 2006 depending on timing of World Bank loan Operation – preliminary estimate October 1, 2006

MONITORING ACTIVITIES Construction March 1, 2006 October 1, 2006 Operation October 1, 2006

Sections C through G of this Environmental Management Plan (EMP) are identical for the transformer/switchgear/breakers/batteries rehabilitation subprojects of the Azerbaijan Power Transmission Project.

8 V Qala Substation

Replacement of Transformers

A. PROJECT DESCRIPTION – QALA SUBSTATION

The Azerbaijan Government has applied for funding from the International Bank for Reconstruction and Development (the World Bank) for a project to develop transmission system control and to rehabilitate power transmission facilities. Some of the funds are planned used for investments at this substation.

The substation is located on the southeast of the low-lying Apsheron peninsula, 25 kilometers to the east of Baku City. It is an isolated facility set in a heavily degraded industrial landscape comprising an onshore oilfield and other individual, generally abandoned, industrial units. All built development in this area is on fill, and roads are placed on bunds suggesting high water tables. Widespread land contamination (predominantly oil) is evident in many areas in the vicinity of the site, but there is no evidence of contamination within the substation site or in its immediate proximity.

The substation was put in service in 1985. It has a single bus on the 110 kV voltage level with connections to six 110 kV transmission lines and two 40 MVA autotransformers with a total combined transformers rating of 80 MVA. The substation also has a number of switchgears at 35 kV & 6 kV voltage levels (9 cells on the 35 kV switchgear and 11 cells on the 6 kV switchgear).

The transformers are currently loaded at a critical limit. During winter, the transformers’ load reaches beyond 100%, and Azerenerji is forced to perform load-shedding maneuvers. It is expected that the load growth will continue at a high rate in this area. Qala substation provides power supply mainly to oil industries and to residential complexes.

Necessary rehabilitation / upgrading works subject of this EMP: Substitution of the existing 40 MVA transformers by a new transformer rated 63 MVA.

(Additional project work at the substation, but outside the scope of this EMP: Replacing the instrumentation and controls; and adaptation of the substation equipment for allowing installation of Remote Terminal Units for the SCADA/EMS system (transmission system control).)

The planned investment is expected to cost less than US$1.5 million.

9 B. SCHEDULE – QALA SUBSTATION

Starting date Ending date

MITIGATION ACTIVITIES Construction – preliminary estimate, March 1, 2006 October 1, 2006 depending on timing of World Bank loan Operation – preliminary estimate October 1, 2006

MONITORING ACTIVITIES Construction March 1, 2006 October 1, 2006 Operation October 1, 2006

Sections C through G of this Environmental Management Plan (EMP) are identical for the transformer/switchgear/breakers/batteries rehabilitation subprojects of the Azerbaijan Power Transmission Project.

10 VI Substation

Replacement of Transformers

A. PROJECT DESCRIPTION – KURDAMIR SUBSTATION

The Azerbaijan Government has applied for funding from the International Bank for Reconstruction and Development (the World Bank) for a project to develop transmission system control and to rehabilitate power transmission facilities. Some of the funds are planned used for investments at this substation.

The Kurdamir substation is located on agricultural lands within a few kilometres of the Kurdamir urban area. The access from the main road is straightforward and would pose no problems. There is no obvious evidence of a high water table or difficult ground conditions at the site.

The Kurdamir 110/35/10 kV substation is an urban primary distribution station. It was initially placed in service in 1959 (1 x 15 MVA transformer) and has been subsequently upgraded in 1970 (1 x 16 MVA transformer). It has a single bus on the 110 kV voltage level with connections to six 110 kV transmission lines, one 15 MVA transformer and one 16 MVA transformer with a total combined transformers rating of 31 MVA. The substation also has a number of switchgears at 35 kV & 10 kV voltage levels.

The transformers are currently loaded at a critical limit. During winter, the transformers loading reaches 108 %, and Azerenerji is forced to perform load-shedding maneuvers. Azerenerji expects that the load growth will continue at a high rate in this area.

Necessary rehabilitation / upgrading works subject of this EMP: Substitution of the existing 15 MVA transformer by a new transformer rated 25 MVA.

(Additional project work at the substation, but outside the scope of this EMP: Replacing the instrumentation and controls; and adaptation of the substation equipment for allowing installation of Remote Terminal Units for the SCADA/EMS system (transmission system control).)

The planned investment is expected to cost less than US$400,000.

11 B. SCHEDULE – KURDAMIR SUBSTATION

Starting date Ending date

MITIGATION ACTIVITIES Construction – preliminary estimate, March 1, 2006 October 1, 2006 depending on timing of World Bank loan Operation – preliminary estimate October 1, 2006

MONITORING ACTIVITIES Construction March 1, 2006 October 1, 2006 Operation October 1, 2006

Sections C through G of this Environmental Management Plan (EMP) are identical for the transformer/switchgear/breakers/batteries rehabilitation subprojects of the Azerbaijan Power Transmission Project.

12 VII Substation

Replacement of Switchgear

A. PROJECT DESCRIPTION – YEVLAKH SUBSTATION

The Azerbaijan Government has applied for funding from the International Bank for Reconstruction and Development (the World Bank) for a project to develop transmission system control and to rehabilitate power transmission facilities. Some of the funds are planned used for investments at this substation.

Yevlakh 110/35/10 kV substation is an urban primary distribution station located at the outskirts of Yevlakh city. The substation site is located within a flat, rural setting just beyond the urban area.

The station was placed in service in 1966. The control building is in need of refurbishment. It has a single bus on the 110 kV voltage level with connections to six 110 kV transmission lines and two 31.5 MVA autotransformers with a total combined transformers rating of 63 MVA. The substation also has a number of switchgears at 35 kV & 10 kV voltage levels.

Azerenerji expects that city load growth rate will increase. Within a short period, the capacity of the existing 10 kV switchgear will not meet the demand.

Necessary rehabilitation / upgrading works subject of this EMP: Replacement of the existing 10 kV switchgears (22 cubicles) by new ones and increasing the number of cubicles to allow the connection of additional 10 kV feeders.

(Additional project work at the substation, but outside the scope of this EMP: Adaptation of the substation equipment for allowing installation of Remote Terminal Units for the SCADA/EMS system (transmission system control).)

The planned investment is expected to cost less than US$200,000.

13 B. SCHEDULE – YEVLAKH SUBSTATION

Starting date Ending date

MITIGATION ACTIVITIES Construction – preliminary estimate, March 1, 2006 October 1, 2006 depending on timing of World Bank loan Operation – preliminary estimate October 1, 2006

MONITORING ACTIVITIES Construction March 1, 2006 October 1, 2006 Operation October 1, 2006

Sections C through G of this Environmental Management Plan (EMP) are identical for the transformer/switchgear/breakers/batteries rehabilitation subprojects of the Azerbaijan Power Transmission Project.

14 VIII Alyat Substation

Replacement of DC Batteries

A. PROJECT DESCRIPTION – ALYAT SUBSTATION

The Azerbaijan Government has applied for funding from the International Bank for Reconstruction and Development (the World Bank) for a project to develop transmission system control and to rehabilitate power transmission facilities. Some of the funds are planned used for investments at this substation.

Alyat 110/35/6 kV substation is an urban primary distribution station located at the outskirts of Alyat urban area, some 80kms to the south-east of Baku. It is an isolated facility constructed on an extremely flat site. However, there are no obvious high water table concerns.

The station was initially placed in service in 1969 (2 x 20 MVA transformer) and has been subsequently upgraded in 1971 (1 x 15 MVA transformer). It has a single bus on the 110 kV voltage level with connections to seven 110 kV transmission lines, two 20 MVA transformers and one 15 MVA transformer with a total combined transformers rating of 55 MVA. The substation also has a number of switchgears at 35 kV & 6 kV voltage levels.

The existing DC batteries type CK-12 are physically worn out.

Necessary rehabilitation / upgrading works subject of this EMP: Replacing the DC batteries type CK-12 by new ones with the same capacity.

(Additional project work at the substation, but outside the scope of this EMP: Adaptation of the substation equipment for allowing installation of Remote Terminal Units for the SCADA/EMS system (transmission system control).)

The planned investment is expected to cost less than US$20,000.

15 B. SCHEDULE – ALYAT SUBSTATION

Starting date Ending date

MITIGATION ACTIVITIES Construction – preliminary estimate, March 1, 2006 October 1, 2006 depending on timing of World Bank loan Operation – preliminary estimate October 1, 2006

MONITORING ACTIVITIES Construction March 1, 2006 October 1, 2006 Operation October 1, 2006

Sections C through G of this Environmental Management Plan (EMP) are identical for the transformer/switchgear/breakers/ rehabilitation subprojects of the Azerbaijan Power Transmission Project.

However, in this case with only batteries replacement, remove items from the mitigation and monitoring plans concerning: • Air emissions • Noise • PCB • PCB soil contamination • Soil and subsoil • Electromagnetic field • Affected land and vegetation

16 C. MITIGATION PLAN

Phase Issue Mitigating Cost of Mitigation Responsibility* Measure (if Substantial) I. a. Air emissions (dust) from Spray with water, particularly during windy, Small Contractor Construction demolition, removal of old dry conditions equipment, and/or topsoil leveling or removal, and vehicle/ machinery exhausts b. Noise. Adverse noise and vibration Substation works will be carried out during Small Contractor impacts may be generated by some daylight hours. If power outages are required, it activities at construction site. may be necessary to carry out some works at Impacts not likely to be significant night or weekends. In such cases, the local and will be short lived, highly population will be informed sufficiently in localized in nature and generally advance through local media. isolated from communities. c. Wastes generated from Wastes to be sorted and placed in temporary Small Contractor construction and demolition storage on-site. Subsequently, removed by activities (metals, ceramics, glass, licensed contractors for disposal at wood, oil, concrete, battery acid, government- approved sites, or sold for etc.). reprocessing to companies with legitimate operating permits. d. PCB. Existing If PCBs are present, they will be disposed by Small Contractor transformers/switchgear /breakers internationally accepted procedures. (to be replaced) to be tested for PCBs. e. Harmful and dangerous material Temporary storage on-site at a location that is Small Contractor specially prepared to receive these materials (impervious base, fenced and locked with only authorized access etc.) and removed by firms with valid license recognized by the environmental authorities.

17 Phase Issue Mitigating Cost of Mitigation Responsibility* Measure (if Substantial) f. PCB soil contamination Soil testing to be conducted by licensed Small Contractor laboratory. If PCBs are found to be present at levels exceeding international (EU or equivalent) standards, the contaminated soil will be removed and treated by licensed contractors in accordance with internationally accepted practice.

g. Affected land and vegetation Ecological reshaping by filling holes, soil Small Contractor leveling, and re-vegetation. No pesticides will be used for any land clearing operations (e.g. new equipment platforms, access roads preparation, etc.). All land clearing will be done by manual or mechanical methods. h. New equipment .New equipment is not to contain any PCBs. Small Contractor II. Operation a. Noise Any new equipment purchased shall limit Small Operator operational noise to levels within Azerbaijan standards and/or in accordance with good international practices

b. Electromagnetic field Any new equipment purchased shall limit Small Operator electromagnetic field levels to within Azerbaijan standards and/or in accordance with good international practices c. Soil and subsoil All new equipment will be placed upon Small Operator impervious bases with bunding high enough to contain any liquid spills or with channeling of spills to other safe, temporary depository.

* Items indicated to be the responsibility of the contractor shall be specified in the bid documents.

18 D. MONITORING PLAN

Phase What parameter is Where How When Monitoring Cost Responsibility to be monitored? is the parameter to is the parameter to is the parameter to What is the cost of be monitored? be monitored/ type be monitored- equipment or of monitoring frequency of contractor charges equipment? measurement or to perform continuous? monitoring I. Construction a. Air emissions On site Visual Dry, windy Small Contractor (dust) periods b. Noise On site, nearby DB[A] meter During noisy Small Contractor population centers equipment operation c. Wastes On site Visual During/after Small Contractor generated from removal of old construction and equipment demolition activities

d. PCB. Possible Approved Chromatography Prior to disposal of Small Contractor PCB content of laboratory spent coolant transformer/ switchgear/ breaker to be replaced e. Harmful and On site, under or Visual Within Small Contractor dangerous near potentially construction material leaking equipment period to be replaced

f. PCB soil At certified Chromatography Before starting the Small Contractor contamination laboratory new construction

19 Phase What parameter is Where How When Monitoring Cost Responsibility to be monitored? is the parameter to is the parameter to is the parameter to What is the cost of be monitored? be monitored/ type be monitored- equipment or of monitoring frequency of contractor charges equipment? measurement or to perform continuous? monitoring g. Affected land On site Visual Within Small Contractor and vegetation construction period II. Operation a. Noise On site, nearby DB[A] meter If local complaints Small Head of substation population centers b. Electromagnetic Near high-voltage Electrometer and When new Small Operator field equipment magnetometer equipment is energized c. Soil and subsoil On site Visual Permanent Small Head of substation

20 E. INSTITUTIONAL STRENGTHENING

1. Equipment Purchases1

Type of equipment Noise-measuring system (analyzer +software) • Number of units 1 • Total cost About US$5,000 • Local or international International purchase

Type of equipment Electric and magnetic field measurement equipment • Number of units 1 • Total cost About $5,000 • Local or international International purchase

2. Training

Type of Training Mitigation, monitoring • Number of students 1 (Environmental person in the Project Implementation Unit) • Total costs US$5,000 (if travel) • Local or international International purchase • Comment Azerenerji will consider training for more personnel, i.e. beyond the specific needs related to the World Bank project components

3. Consultant Services

Type of Services Mitigation and monitoring training • Cost Indicatively $20,000

• Comment Environmental training planned as one of several components in a broader project implementation consultancy contract • Local or international International purchase

1 The cost of equipment is approximate and may change depending on the kind of equipment to be bought.

21 F. INSTITUTIONAL ARRANGEMENTS

Decision Making Chain of Command for Environmental Management Activity Institution(s) Responsible Environmental Monitoring Head of Substation Environmental Data Analysis Project Implementation Unit (project phase) Environmental Report Project Implementation Unit Preparation (project phase) Environmental Decision Operator Environmental Management Operator Authority

G. CONSULTATION WITH LOCAL NGOs AND PROJECT-AFFECTED GROUPS

The announcements on consultations were done by radio broadcasting in local radio networks, and by telephone, and by notices located at places where peoples usually crowded: close to markets, shops, schools, bus stations. Moreover, special letters were sent to appropriate persons and authorities.

By Azerenerji’s initiative, the EMPs were disclosed and considered in the framework of the regular Conference of the “Caspian Basin Greenhouse Gas Emission Reduction Training Program”, funded by the Canadian International Development Agency. The Conference was arranged on October 5-8, 2004, in Baku with participation of representatives of the local environmental authorities and different non-governmental institutions.

The meeting for sub-projects and EMPs public consideration in Imishli was carried out on November 8, 2004; in Kurdamir such meeting took place on November 9, 2004. In Imishli the information about the works under sub-projects around the region was provided by Mr. A. Samedov, Director of the Ali-Bayramli High Voltage Power Network Enterprise, and appropriate information in Kurdamir was provided by Mr. N. Djabrailov, Chief Engineer of the same Enterprise. The appropriate sub-projects and EMPs public consideration in Yevlakh was carried out on November 15, 2004; in Gandja corresponding meeting was held on November 18, 2004. The report about the sub-project and EMP in Yevlakh was presented by Mr. A. Farzaliyev, Head of Yevlakh Region Department of Gandja High Voltage Power Network Enterprise. In Gandja corresponding sub-projects and relevant EMPs were advised to the public by Mr. E. Mamedov, Director of the Gandja High Voltage Power Network Enterprise.

The following persons were invited specially:

No Name and Surname Organization/Occupation Address Tel. No. 1 Khayyam Rahimov National Academy of Sciences, Head of c. Baku 492-67-21 laboratory home 439-33-54 office

22 No Name and Surname Organization/Occupation Address Tel. No. 2 Jamila Akhmedova National Academy of Sciences, Scientist c. Baku 439-33-54 office 3 Rasim Aliyev Ministry of Industry and Energy, c. Baku 444-02-60 Leading engineer office 320-89-12 mob. 4 Arif Sadigov SOCAR, Leading engineer c. Baku 492-23-19 office 5 Arif Agakishiyev “Azneft” Production Unit, Engineer c. Baku 497-37-15 office 6 Abdulxalig Heydarov “Azerenerji” JSC, Chief specialist c. Baku 498-41-84 office 7 Feride Rzayeva “Azerbaijan Scientific and Technical c. Baku 490-43-59 Project and Gas Institute”, Scientist office 8 Liliya Lavrova “Azerbaijan Scientific and Technical c. Baku 440-68-64 Project and Gas Institute”, Scientist office 9 Baba Askerov Executive authority of Sumgayit city, c. 5-23-08 Head of department Sumgayit 10 Zarifa Guliyeva Ministry of Economic Development, c. Baku 492-41-10 advisor office 11 Talat Kengerli “Chevra” Non-Governmental c. Baku 439-52-12 Organization, Manager home 12 Feyzulla Muradov “Chevra” Non-Governmental c. Baku 439-52-02 Organization, Leading specialist 13 Israfil Gurbanov “Chevra” Non-Governmental c. Baku 442-21-78 Organization, Leading specialist home 14 Ali Orujov Ministry of Ecology and Natural c. Baku 438-84-32 Resources, Advisor office 15 Basharat Aliyev Ministry of Ecology and Natural c. Baku 438-56-28 Resources, Leading advisor office 16 Umayra Tagiyeva Hydrometeorology Forecast Bureau, c. Baku 441-11-75 Head of bureau office 17 Lyudmila Piyakina Hydrometeorology Forecast Bureau, c. Baku 466-50-34 Head of department office 18 Irina Poltovets Hydrometeorology department, c. Baku 441-56-85 Specialist office 19 Maharram Mehdiyev Ozone and Climatic Changes Centre, c. Baku 498-27-95 Director office 20 Gulmali Suleymanov Ozone and Climatic Changes Centre, c. Baku 498-27-95 Head of department office 21 Elnur Akhmedov Ozone and Climatic Changes Centre, c. Baku 708-13-56 Leading specialist mob. 22 Muslim Gurbanov “Ekoil” Non-Governmental c. Baku 494-12-14 Organization, Director home 312-60-19 mob. 23 Zemfira Isgenderova “Ekoil” Non-Governmental c. Baku 498-27-95 Organization, Specialist office 24 Giyas Bayramov “Azerneftyag” oil refinery, Deputy c. Baku 490-45-02 Chief Engineer office 25 Ramil Mamishov Executive Authority of Baku city, c. Baku 497-51-29 Advisor office 26 Hamlet Akhmedov Baku Ecology and Natural Resources c. Baku 462-85-80 department, Leading advisor office

23 No Name and Surname Organization/Occupation Address Tel. No. 27 Rafig Abdullayev 1st District Heating Enterprise, Head of c. Baku 471-59-74 department office 471-20-34 office 28 Aligulu Mehdiyev 2nd District Heating Enterprise, Head of c. Baku 491-22-54 department office 491-12-56 office 29 Rena Lazimova State Statistical Committee, Head of c. Baku 438-93-61 department office 30 Sevil Aliyeva State Statistical Committee, Deputy c. Baku 438-91-47 Head of department office 31 Aygun Narimanova Ozone and Climatic Changes Centre, c. Baku 498-27-35 Head of department office 32 Gunel Amirli Ozone and Climatic Changes Centre, c. Baku 631-03-84 Leading specialist mob. 33 Amina Agayeva Ozone and Climatic Changes Centre, c. Baku 498-27-95 Specialist office 34 Jamila Aliyeva Ozone and Climatic Changes Centre, c. Baku 498-27-95 Specialist office 35 Vusala Abdullayeva Ozone and Climatic Changes Centre, c. Baku 498-27-95 Specialist office 36 Mahbuba Mammadova Ozone and Climatic Changes Centre, c. Baku 662-34-09 Specialist mob. 37 Vusala Jafarova Ozone and Climatic Changes Centre, c. Baku 648-54-80 Specialist mob. 38 Anar Mehdiyev Ozone and Climatic Changes Centre, c. Baku 300-07-40 Leading specialist mob. 39 Aynur Piriyeva Ozone and Climatic Changes Centre, c. Baku 498-27-95 Specialist office 40 Fuad Aslanov Ozone and Climatic Changes Centre, c. Baku 520-12-01 Specialist office 41 Xanlar Ismayilov Executive Authority of Yevlakh city, c.Yevlakh 6-46-08 Administrative representative office 42 Xalis Akhmedov Executive Authority of Yevlakh city, c.Yevlakh 6-28-69 Deputy Head of construction and office architectural department 43 Rasim Kazimov Executive authority of Yevlakh city, 1st c. Imishli 229-77-02 Deputy Head of Authority mob. 44 Sekhavet Shirinov Head of Imishli Municipality c. Imishli 336-25-64 mob. 45 Aydin Mammadov State Cartography and Land Committee c. Imishli 329-21-57 of Azerbaijan Republic, Imishli branch, mob. Head of department 46 Sabit Khalilov Executive Authority of Kurdamir city, c. 349-82-28 1st Deputy Head of Authority Kurdamir mob. 47 Nizami Garibov Head of Kurdamir Municipality c. 220-17-95 Kurdamir mob. 48 Gulbala Askerov State Cartography and Land Committee c. of Azerbaijan Republic, Kurdamir Kurdamir branch, Head of department 49 Shahmali Javadov Executive Authority of Ganja city, c. Ganja 332-85-69 Deputy Head of Authority mob. 50 Chingiz Muxtarov Executive authority of Kapaz c. Ganja 312-08-88

24 No Name and Surname Organization/Occupation Address Tel. No. administrative district of Ganja city, mob. Head of Authority

The following persons attended at consultations and meetings:

No Name and Surname Organization/Occupation Address Tel. No. 1 Khayyam Rahimov National Academy of Sciences, Head of c. Baku 492-67-21 laboratory home 439-33-54 office 2 Jamila Akhmedova National Academy of Sciences, Scientist c. Baku 439-33-54 office 3 Rasim Aliyev Ministry of Industry and Energy, c. Baku 444-02-60 Leading engineer office 320-89-12 mob. 4 Arif Sadigov SOCAR, Leading engineer c. Baku 492-23-19 office 5 Arif Agakishiyev “Azneft” Production Unit, Engineer c. Baku 497-37-15 office 6 Abdulxalig Heydarov “Azerenerji” JSC, Chief specialist c. Baku 498-41-84 office 7 Feride Rzayeva “Azerbaijan Scientific and Technical c. Baku 490-43-59 Project and Gas Institute”, Scientist office 8 Liliya Lavrova “Azerbaijan Scientific and Technical c. Baku 440-68-64 Project and Gas Institute”, Scientist office 9 Baba Askerov Executive authority of Sumgayit city, c. 5-23-08 Head of department Sumgayit 10 Zarifa Guliyeva Ministry of Economic Development, c. Baku 492-41-10 advisor office 11 Talat Kengerli “Chevra” Non-Governmental c. Baku 439-52-12 Organization, Manager home 12 Ali Orujov Ministry of Ecology and Natural c. Baku 438-84-32 Resources, Advisor office 13 Basharat Aliyev Ministry of Ecology and Natural c. Baku 438-56-28 Resources, Leading advisor office 14 Umayra Tagiyeva Hydrometeorology Forecast Bureau, c. Baku 441-11-75 Head of bureau office 15 Lyudmila Piyakina Hydrometeorology Forecast Bureau, c. Baku 466-50-34 Head of department office 16 Irina Poltovets Hydrometeorology department, c. Baku 441-56-85 Specialist office 17 Maharram Mehdiyev Ozone and Climatic Changes Centre, c. Baku 498-27-95 Director office 18 Gulmali Suleymanov Ozone and Climatic Changes Centre, c. Baku 498-27-95 Head of department office 19 Elnur Akhmedov Ozone and Climatic Changes Centre, c. Baku 708-13-56 Leading specialist mob. 20 Muslim Gurbanov “Ekoil” Non-Governmental c. Baku 494-12-14 Organization, Director home 312-60-19 mob.

25 21 Feyzulla Muradov “Chevra” Non-Governmental c. Baku 439-52-02 Organization, Leading specialist 22 Israfil Gurbanov “Chevra” Non-Governmental c. Baku 442-21-78 Organization, Leading specialist home 23 Giyas Bayramov “Azerneftyag” oil processing plant, c. Baku 490-45-02 Deputy Chief engineer office 24 Ramil Mamishov Executive authority of Baku city, c. Baku 497-51-29 Advisor office 25 Hamlet Akhmedov Baku Ecology and Natural Resources c. Baku 462-85-80 department, Leading advisor office 26 Rafig Abdullayev 1st Heating administration, Head of c. Baku 471-59-74 department office 471-20-34 office 27 Aligulu Mehdiyev 2nd Heating administration, Head of c. Baku 491-22-54 department office 491-12-56 office 28 Rena Lazimova State Statistical Committee, Head of c. Baku 438-93-61 department office 29 Sevil Aliyeva State Statistical Committee, Deputy c. Baku 438-91-47 Head department office 30 Zemfira Isgenderova “Ekoil” Non-Governmental c. Baku 498-27-95 Organization, Specialist office 31 Aygun Narimanova Ozone and Climatic Changes Centre, c. Baku 498-27-35 Head of department office 32 Gunel Amirli Ozone and Climatic Changes Centre, c. Baku 631-03-84 Leading specialist mob. 33 Amina Agayeva Ozone and Climatic Changes Centre, c. Baku 498-27-95 Specialist office 34 Jamila Aliyeva Ozone and Climatic Changes Centre, c. Baku 498-27-95 Specialist office 35 Vusala Abdullayeva Ozone and Climatic Changes Centre, c. Baku 498-27-95 Specialist office 36 Mahbuba Mammadova Ozone and Climatic Changes Centre, c. Baku 662-34-09 Specialist mob. 37 Vusala Jafarova Ozone and Climatic Changes Centre, c. Baku 648-54-80 Specialist mob. 38 Anar Mehdiyev Ozone and Climatic Changes Centre, c. Baku 300-07-40 Leading specialist mob. 39 Aynur Piriyeva Ozone and Climatic Changes Centre, c. Baku 498-27-95 Specialist office 40 Fuad Aslanov Ozone and Climatic Changes Centre, c. Baku 520-12-01 Specialist office 41 Vugar Heydarov “Azerenerji” JSC, Engineer c. Baku 490-09-67 office 42 Xanlar Ismayilov Executive authority of Yevlakh city, c.Yevlakh 6-46-08 Administrative representative office 43 Xalis Akhmedov Executive authority of Yevlakh city, c.Yevlakh 6-28-69 Deputy Head of construction and office architectural department 44 Rasim Kazimov Executive authority of Yevlakh city, 1st c. Imishli 229-77-02 Deputy Chief executive mob. 45 Sekhavet Shirinov Head of Imishli municipality c. Imishli 336-25-64 mob.

26 46 Aydin Mammadov State Cartography and Land Committee c. Imishli 329-21-57 of Azerbaijan Republic, Imishli branch, mob. Head of department 47 Alirza Samedov “Ali-Bayramli YGES” High Voltage c. Ali- 4-55-25 Network Enterprise, Director Bayramli office 223-45-56 mob. 48 Sarraf Gedimov “Ali-Bayramli YGES” High Voltage c. Ali- 376-77-19 Network Enterprise, Head of technical Bayramli mob. department 49 Vahid Manafov “Ali-Bayramli YGES” High Voltage c. Imishli 5-22-15 Network Enterprise, Imishli branch, office Chief engineer 50 Sabit Khalilov Executive authority of Kurdamir city, c. 349-82-28 1st Deputy Chief executive Kurdamir mob. 51 Nizami Garibov Head of Kurdamir municipality c. 220-17-95 Kurdamir mob. 52 Gulbala Askerov State Cartography and Land Committee c. of Azerbaijan Republic, Kurdamir Kurdamir branch, Head of department 53 Nushiravan Jahangirov “Ali-Bayramli YGES” High Voltage c. Ali- 376-77-28 Network Enterprise, Chief engineer Bayramli mob. 54 Adil Nasibov “Ali-Bayramli YGES” High Voltage c. Network Enterprise, Agsu branch, Director 55 Shahmali Javadov Executive authority of Ganja city, c. Ganja 332-85-69 Deputy Chief executive mob. 56 Chingiz Muxtarov Executive authority of Kapaz c. Ganja 312-08-88 administrative district of Ganja city, mob. Chief executive 57 Hagverdi Allahverdiyev “Ganja YGES” High Voltage Network c. Ganja 57-42-46 Enterprise, Head on regime office 58 Akif Akhmedov “Ganja YGES” High Voltage Network c. Ganja 57-42-47 Enterprise, substations maintenance office service, Head 59 Ali Ferzaliyev “Ganja YGES” High Voltage Network c. 6-02-47 Enterprise, Yevlakh branch, Director Yevlakh office 60 Ildirim Efendiyev “Ganja YGES” High Voltage Network c. - Enterprise, Yevlakh branch, Engineer Yevlakh 61 Mamedali Huseynov “Ali-Bayramli YGES” High Voltage c. Imishli 5-22-25 Network Enterprise, Imishli branch, office Leading engineer 62 Asif Dadashov “Ali-Bayramli YGES” High Voltage c. Imishli 5-22-25 Network Enterprise, Imishli branch, office mechanician 63 Abid Huseynov “Ali-Bayramli YGES” High Voltage c. - Network Enterprise, Agsu branch, Kurdamir Leading engineer 64 Ramiz Mammedov “Ali-Bayramli YGES” High Voltage c. - Network Enterprise, Agsu branch, Kurdamir Engineer 65 Novruz Abdullayev pensioner c. Ganja - 66 Yevgeniya Kerimova pensioner c. Ganja - 67 Rafig Hashimov pensioner c. Ganja - 68 Hasan Gambarov pensioner c. Ganja -

27 69 Javanshir Mammedov pensioner c. Ganja - 70 Ilyas Orujov pensioner c. - Yevlakh 71 Asli Ismayilova pensioner c. - Yevlakh 72 Ganim Mammedov pensioner c. - Yevlakh 73 Hasanali Mammedov Pensioner c. - Yevlakh 74 Nisa Khanlarova Pensioner c. - Yevlakh 75 Vahid Osmanov “Ganja YGES” High Voltage Network c. 6-07-06 Enterprise, Yevlakh branch, Chief Yevlakh engineer 76 Elburus Mammedov “Ganja YGES” High Voltage Network c. Ganja 57-42-12 Enterprise, Director office 77 Zahid Mammedov “Ganja YGES” High Voltage Network c. Ganja 57-19-62 Enterprise, Chief engineer office 78 Vahid Hasanov “Ali-Bayramli YGES” High Voltage c. Agsu 5-36-73 Network Enterprise, Agsu branch, Chief office engineer 79 Agasultan Kerimov “Ali-Bayramli YGES” High Voltage c. Agsu 645-74-12 Network Enterprise, Agsu branch, Head mob. foreman on TLs 80 Elmar Mammedov “Ali-Bayramli YGES” High Voltage c. Imishli 5-53-64 Network Enterprise, Imishli branch, office Leading engineer on relay protection

The consultation meetings in Yevlah and Ganja caused no particular comments from the participants, and the meetings concluded that the rehabilitation works would have no negative impact on the environment.

In the meetings in Kurdamir and Imishli, representatives from municipalities stated that the rehabilitation would have minimal or no impact on the environment. In the meeting in Baku, similar statements were made by NGOs and representatives of academia and scientific institutes.

28

29